ASSISTANT SECRETARY OF THE ARMY WASHINGTON St 1981 TO: THE PRESIDENT OF THE SENATE AND THE SPEAKER OF THE HOUSE OF REPRESENTATIVES SUBJECT: Annual Report of the Chief of Engineers on Civil Works Activities for Fiscal Year 1985 I am forwarding the Annual Report of the Chief of Engineers for Fiscal Year 1985 in accordance with Section 8 of the River and Harbor Act of 1888. Fiscal Year 1985 has been an important year for the Corps and the Nation. After practically no new construction starts since 1980, Congress enacted the Supplemental Appropriations Act of 1985, Public Law 99-88, which included authorization and funding for start-up of construction of 41 projects. This year is also important in that it marked the beginning of a new era of cost sharing between the Federal government and local sponsors of water resource projects. The passage of Public Law 99-88 makes funding for the new projects dependent upon the successful negotiation of cost sharing and financing agreements between the Corps and local sponsors. Assistant Secretary of the Army (Civil Works) DEPARTMENT OF THE ARMY OFFICE OF THE CHIEF OF ENGINEERS WASHINGTON, D.C. 20314-1000 REPLY TO ATTENTION OF: SUBJECT: Annual Report of the Chief of Engineers on Civil Works Activities for Fiscal Year 1985 THE SECRETARY OF THE ARMY I am forwarding the Annual Report of the Chief of Engineers on Civil Works Activities for Fiscal Year 1985. This volume of field reports contains narrative summaries and statistics on Corps water resource projects where there has been activity during the fiscal year. E. R. HEIBERG III Lieutenant General, USA Chief of Engineers w CONTENTS S Page NEW ENGLAND DIVISION ........................................................................ 1-1 NORTH ATLANTIC DIVISION: New York, NY, District ............................................................... ........ 2-1 Philadelphia, PA, District ......................................................................... 3-1 Baltimore, MD, District ................................................................. 4-1 Norfolk, VA, District .................................................................. .......... 5-1 SOUTH ATLANTIC DIVISION: Wilmington, NC, District ................................................................. 6-1 Charleston, SC, District ................................................................ 7-1 Savannah, GA, District............................................................. ............ 8-1 Jacksonville, FL, District ................................................................ 9-1 Mobile, AL, District ................................................................................. 10-1 LOWER MISSISSIPPI VALLEY DIVISION: New Orleans, LA, District .............................................. ......................... 11-1 Vicksburg, M S, District ........................................................................... 12-1 Memphis, TN, District .................................................................. 13-1 St. Louis, M O, District ................. ......................................................... 14-1 SOUTHWESTERN DIVISION: Galveston, TX, District ................................................................. 15-1 Fort Worth, TX, District........................................................................ 16-1 Albuquerque, NM , District ........................................................................ 1 -1 Little Rock, AR, District ... ............ ....................... ................................. ... 1 -1 Tulsa, OK, District.................................................................................... 19-1 MISSOURI RIVER DIVISION: Kansas City, M O, District ........................................................................ 20-1 Omaha, NE, District .............................................................. ......... 21-1 OHIO RIVER DIVISION: O hio River........................................................................................ 22-1 Nashville, TN, District ........................................................................... 23-1 Louisville, KY, District............................................................................ 24-1 Huntington, W V, District......................................................................... 25-1 Pittsburgh, PA, District .......................................................................... 26-1 NORTH CENTRAL DIVISION: St. Paul, M N , District............................................................................ 27-1 Rock Island, IL, District.......................................................................... 28-1 Mississippi River between Missouri River and Minneapolis, MN ................................... 29-1 Chicago, IL, District.............................................................................. 30-1 Detroit, M I, District.............................................................................. 31-1 Buffalo, NY, District ............................................................................. 32-1 SOUTH PACIFIC DIVISION: Los Angeles, CA, District......................................................................... 33-1 San Francisco, CA, District....................................................................... 34-1 Sacramento, CA, District ......................................................................... 35-1 PACIFIC OCEAN DIVISION:....................................................................... 36-1 NORTH PACIFIC DIVISION: Portland, OR, District............................................. ............................... 37-1 Seattle, W A, District............................................................................. 38-1 W alla W alla, W A, District......................................................................... 39-1 A laska D istrict ................................................................................... 40-1 Board of Engineers for Rivers and Harbors .......................................................... 41-1 M ississippi River Commission....................................................................... 42-1 Natural Disaster Preparedness, Response & Recovery Activities ....................................... 43-1 California Debris Commission ....................................................................... 44-1 Waterways Experiment Station.... ........................ .................. .45-1 Permanent International Association of Navigation Congresses ......... . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 46-1 Investigations of Projects Under Federal Power Act .................................................. 47-1 Regulatory Sunken Vessel Removal and National Emergency Preparedness............................. 48-1 International Boundary Waters Boards.............................................................. 49-1 Construction Engineering Research Laboratory ...................................................... 50-1 Engineer Topographic Laboratories ................................................................. 51-1 Cold Regions Research Engineering Laboratory...................................................... 52-1 W ater Resources Support Center.................................................................... 53-1 APPENDICES: Flood Control Reservoirs Operable September 30, 1985.............................................. A-1 Flood Control Projects Under Construction During Fiscal Year 1985 .............................. B-1 Navigation Locks and Dams Operable September 30, 1985........................................... C-1 Navigation Projects Under Construction September 30, 1985........................................ D-1 Multipurpose Projects Including Power In Operation September 30, 1985. ............................ E-1 Multipurpose Projects Including Power Under Construction September 30, 1985 ....................... F-1 Flood Damages Prevented (By Region and by District) During Fiscal Year 1985 ....................... G-1 IN D EX ...................... .................................................................... I-1 NEW ENGLAND DIVISION* The New England Division, an operating division with both district and division functions, comprises all of New England except western Vermont and small portions of Massachusetts and Connecticut along their western boundaries, and includes small portions of southeastern New York, all embraced in the drainage basins tributary to Long Island Sound and the Atlantic Ocean east of the New York-Connecticut State line. It also includes Fishers Island, NY. IMPROVEMENTS Navigation Page 1. Aquatic Plant Control ...................... 1-3 2. Black Rock Harbor, CT .................... 1-3 3. Buttermilk Bay Channel, MA .............. 1-3 4. Cape Cod Canal, MA ....................... 1-3 5. Clinton Harbor, CT ......................... 1-4 6. Connecticut River Below Hartford, CT ............................... 1-4 7. Green Harbor, MA ......................... 1-4 8. Hyannis Harbor, MA ....................... 1-5 9. Jonesport Harbor, ME .................. :... 1-5 10. Kennebunk River, ME ..................... 1-6 11. Mianus River, CT .......................... 1-6 12. New London Harbor, CT ................... 1-6 13. Newburyport Harbor, MA ................. 1-6 14. Penobscot River, ME ....................... 1-7 15. Point Judith Pond and Harbor of Refuge, Point Judith, RI ................. 1-7 16. Portland Harbor, ME ...................... 1-8 17. Provincetown Harbor, MA .................. 1-8 18. Royal River, ME ........................... 1-8 19. Saco River, M E ............................ 1-8 20. Stonington Harbor, ME .................... 1-9 21. Reconnaissance and condition surveys ...................................... 1-9 22. Other authorized navigation projects ................................... 1-9 23. Navigation activities pursuant to Section 107, Public Law 86-645 (Preauthorization) .......................... 1-9 24. Authorized bridge alteration ............... 1-9 Beach Erosion Control 25. Revere Beach, MA ......................... 1-9 26. Inspection of completed beach erosion control projects ...... ................ 1-9 27. Other authorized beach erosion control projects ............................. 1-9 28. Beach erosion control activities pursuant to Section 103, Public Law 87-874 (Preauthorization) ............ 1-10 Flood Control 29. Blackstone River Basin, MA and RI ........ 1-10 29A. Blackstone River, Millbury, MA ............ 1-10 1-1 Page 29B. Clear River, Burrillvile, RI ................ 1-10 29C. Pawtuxet River, Warwick, RI ............. 1-10 29D. West Hill Dam, MA ....................... 1-11 29E. Charles .jyer (Natural Valley Storage Areas), MA ....................... 1-11 30. Connecticut River Basin, VT, NH, MA and CT .......................... 1-11 30A. Ball Mountain Lake, VT ................... 1-12 30B. Barre Falls Dam, MA ..................... 1-12 30C. Beaver Brook, Keene, NH ................. 1-12 30D. Birch Hill Dam, MA ...................... 1-12 30E. Colebrook River Lake, CT ................. 1-13 30F. Conant Brook Dam, MA ................... 1-13 30G. Knightville Dam, MA ..................... 1-13 30H. Littleville Lake, MA ....................... 1-13 30I. North Hartland Lake, VT ................. 1-13 30J. North Springfield Lake, VT ............... 1-14 30K. Otter Brook Lake, NH ..................... 1-14 30L. Park River, Hartford, CT ................. 1-14 30M. Surry Mountain Lake, NH ................ 1-14 30N. Townshend Lake, VT ...................... 1-15 300. Tully Lake, MA ........................... 1-15 30P. Union Village Dam, VT ................... 1-15 30Q. Village of Saxtons, VT .................... 1-15 30R. West Springfield, MA ..................... 1-15 31. Housatonic River Basin, CT and MA ...... 1-16 31A. Black Rock Lake, CT .................. :.... 1-16 31B. Hancock Brook Lake, CT .................. 1-16 31C. Hop Brook Lake, CT ....................... 1-16 31D. Housatonic River, Pittsfield, MA ........... 1-17 31E. Northfield Brook Lake, CT ................ 1-17 31F. Thomaston Dam, CT ...................... .1-17 32. Nonewaug River, Woodbury, CT .......... 1-17 33. Gulf Street and Trumbull Avenue, M ilford, CT ............................... 1-17 34. Islesboro (The Narrows), ME ............... 1-18 35. Johnson Bay, Lubec, ME .................. 1-18 36. Port 5 Facility, Bridgeport, CT ............ 1-18 37. Merrimack River Basin, NH and MA ...... 1-18 37A. Blackwater Dam, NH ..................... 1-18 37B. Edward MacDowell Lake, NH ............ 1-19 37C. Franklin Falls Dam, NH .................. 1-19 37D. Hopkinton-Everett Lakes, NH .............. 1-19 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Page 38. New Bedford, Fairhaven, and Acushnet, MA ............................. 1-19 39. New London, CT .......................... 1-19 40. Saint John River Basin, ME ................ 1-20 41. Bagaduce River, Castine, ME ............. 1-20 42. Penobscot River, Old Town, ME ........... 1-20 43. Sebasticook River, Hartland, ME ........... 1-20 44. Stamford, CT .............................. 1-20 45. Thames River Basin, CT, RI and M A ................................... 1-21 45A. Buffumville Lake, MA .................... 1-21 45B. East Brimfield Lake, MA ................. 1-21 45C. Hodges Village Dam, MA ................. 1-21 45D. Mansfield Hollow Lake, CT ................ 1-21 45E. West Thompson Lake, CT ................. 1-21 45F. Westville Lake, MA ....................... 1-22 46. Inspection of completed flood control projects ............................ 1-22 47. Flood control reservoir operations .................................. 1-22 48. Hurricane barrier operations ............... 1-23 49. Other authorized flood control projects ............................ 1-23 50. Flood control work under special authorization ...................... 1-23 51. Deauthorized projects ..................... 1-24 General Investigations 52. Surveys ................................... 1-24 53. Collection and Study of Basic Data ......... 1-24 Page 54. Continuation of Planning and Engineering .......................... 1-24 55. Advance Engineering and Design .......... 1-24 Tables Table 1-A Cost & Financial Statement ............................ 1-25 Table 1-B Authorizing Legislation .............. 1-32 Table 1-C Other Authorized Navigation Projects ................... 1-37 Table 1-D Other Authorized Beach Erosion Control Projects ............... 1-41 Table 1-E Other Authorized Flood Control Projects ................ 1-42 Table 1-F Other Authorized Multiple- Purpose Projects including Power ..... 1-43 Table 1-G Deauthorized Projects ................. 1-44 Table 1-H Navigation Activities Pursuant to Sec. 107 .................. 1-45 Table 1-I Beach Erosion Activities Pursuant to Sec. 103 .................. 1-45 Table 1-J Flood Control Activities Pursuant to Sec. 205 .................. 1-46 Table 1-K Blackstone River Basin ................ 1-46 Table 1-L Connecticut River Basin .............. 1-47 Table 1-M Housatonic River Basin ............... 1-48 Table 1-N Merrimack River Basin ............... 1-50 Table 1-0 Thames River Basin .................. 1-51 Table 1-P Boston Harbor, MA ................... 1-51 Table 1-Q Reconnaissance and Condition Surveys .................... 1-52 1-2 NEW ENGLAND DIVISION Navigation 1. AQUATIC PLANT CONTROL Location. The program is conducted in all navigable waters, tributary streams, connecting channels and associated waters under the New England Division jurisdiction. Existing project. The purpose of the program is to provide technical assistance in the eradication or control of aquatic plants that are causing or have the potential to cause major economic problems in the above waterways. The plant control is done in the interest of navigation, flood control, drainage, agriculture, fish and wildlife conservation, public health and research. The program is administered by the Chief of Engineers, under the direction of the Secretary of the Army, and in cooperation with other Federal and State agencies. (See Table 1-B at end of chapter for Acts authorizing existing program). Local cooperation. Local interests must contribute 30 percent of the cost of controlling the aquatic plants, and in addition must hold the United States free from damages that may occur from control operations. Operations during fiscal year. A contract study was performed to survey the six New England States to determine priorities and extent of specific needs for aquatic plant control. As a result of these surveys, we have received numerous verbal requests from state and local lake associations for more information on the Corps' Aquatic Plant Control Program. We have contacted the states to further explain the Corps' program, and are continuing to work closely with them. A report was also completed that presented a detailed evaluation of the codium fragile (Japanese green staghorn algae) problem at Vineyard Haven Harbor on Martha's Vineyard in Massachusetts at the request of the Town of Tisbury. A follow-up study was also completed for the Charles River Lake District in Waltham, Massachusetts. This study provided additional qualitative information on the surrounding watershed and the lakes district itself to assist in a long-range management program for the area. No cost-sharing programs for control operations were developed with any of the states during the fiscal year. 2. BLACK ROCK HARBOR, CT Location. On north shore of Long Island, about 51 miles east of New York City. (See National Ocean Survey Chart 12369). Existing project. Black Rock Harbor and Cedar Creek Channel, 18 feet deep and 100 to 200 feet wide from the 18 foot contour in Black Rock Harbor to the heads of both branches of Cedar Creek, about 2.4 miles. (See Table 1-B at end of chapter for Act authorizing existing project). Local cooperation. Fully complied with for completed portion of project; for Black Rock Harbor breakwaters and Burr and Cedar Creek anchorage there is no reasonable prospect that required cooperation will be forthcoming from local interests. For further details see Annual Report for 1968. Terminal facilities. There are 6 waterfront facilities serving Black Rock Harbor. Facilities are adequate for existing ,,nimerce. Operations during fiscal year. Maintenance: In conjunction with Field Verification Program, $22,180 was expended to extend existing lease of land. 3. BUTTERMILK BAY CHANNEL, MA Location. Buzzards Bay, MA, is at the southern end of Cape Cod Canal. It is connected with Buttermilk Bay to the north by a natural channel branching from Cape Cod Canal and extending northerly past Butler Cove for a distance of 2 miles into Buttermilk Bay. (See National Ocean Survey Chart 13236). Existing project. Provides for a channel 100 feet wide and 7 feet deep at mean low water through the sand bar across the channel, to just above Taylor's Point, then a 2,500 foot extension 6 feet deep and 80 feet wide to the site of a public marina to be built by the Town of Bourne and the Commonwealth of Massachusetts. Project except for channel extension was completed in 1953. Construction of extension was completed in February 1984. (See Table 1-B at end of chapter for Acts authorizing existing project). Local cooperation. Fully complied with. Terminal facilities. There are no wharves bordering on the channel. The only facilities in Buttermilk Bay are small private piers for shallow-draft boats. Operations during fiscal year. New work and maintenance: Administrative closeout for the improvement dredging portion resulted in reduced contract cost. Final contract amount was $78,950. Hired labor costs of $29,895 were incurred for condition surveys. Contract payment of $10,130 was incurred for the maintenance portion of the dredging contract completed last fiscal year. Final cost sharing adjustments were completed. 4. CAPE COD CANAL, MA Location. This waterway is a sea level canal; extending from head of Buzzards Bay, MA, to a point on Cape Cod Bay about 15 miles southeast of Plymouth Harbor, MA. In general direction canal trends from Buzzards Bay easterly to Cape Cod Bay. (See National Ocean Survey Chart 13246). Existing project. For description of existing project see Annual Report for 1975. (See Table 1-B at end of chapter for Acts authorizing existing project). Navigational improvements were completed in April 1963, with completion of East Boat Basin extension. Initial recreational development consists of public use facilities at various locations, which were completed in February 1965. Improvements to public use facilities at the East Boat Basin were completed in May 1974. Construction of public use facilities at Bourne Scenic Park were completed in May 1976. Canal is crossed by two high-level highway bridges and a vertical-lift railroad bridge. Initial major rehabilitation of Bourne Highway Bridge was completed in December 1965. Minor rehabilitation of stone breakwater was completed in October 1963. Local cooperation. Fully complied with. Local interests must also bear 50 percent of future recreational development in accordance with 1965 Federal Water Project Recreation Act. 1-3 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Terminal facilities. There are seven terminals on the canal, of which three are privately owned. Four are used for receipt and freezing of fish and two are used for receipt and storage of oil. Seventh terminal is State pier, owned by Commonwealth of Massachusetts, and on north bank of canal at Bourne Neck. Terminals are adequate for purposes for which they are used. Operations during fiscal year. Maintenance: Funds expended for contracts awarded in fiscal year 1984 and completed in fiscal year 1985 were: repair of mooring dolphins $91,000; repair of suicide deterring fence, Bourne Highway Bridge $43,900; replacement of three public use comfort stations $342,300; repair of Railroad Bridge elevators $26,400 and replacement of water proofing for Bourne Bridge sidewalk $26,800. Contracts awarded and completed in fiscal year 1985 were: repair of marine diesel engines $58,900; inspection of highway bridge concrete structures $29,500; procurement of audiovisual equipment $29,600; emergency repair of Bourne Bridge roadway surface $6,500 and purchase of vehicles $19,000. A continuing contract was awarded for rehabilitation of the Sandwich Bulkhead with $2,502,400 expended in fiscal year 1985. Components for the computerized electronic traffic control system were procured under a continuing contract at a cost of $75,600. A contract for procurement of suspension cables for the Bourne Bridge was awarded with fiscal year 1985 costs of $180,000. Other fiscal year 1985 costs for work accomplished by hired labor and contract were: contract operation and maintenance of Railroad Bridge, tower and signal system $287,200; condition surveys $67,900; operational costs for roads, bridges and project facilities $1,006,500; real estate activities $62,600; traffic control activities $1,377,900; administrative costs $116,900; engineering and design including preparation of plans and specifications $228,500 and contract supervision and inspection $138,500. 5. CLINTON HARBOR, CT Location. On north shore of Long Island Sound, about 10 miles west of mouth of Connecticut River and about 20 miles east of New Haven Harbor, CT. (See National Ocean Survey Charts 12374 and 12354). Previous Project. For details see page 640, Annual Report for 1894 and page 112, Annual Report for 1943. Existing project. A channel 8 feet deep at mean low water and 100 feet wide from Long Island Sound to upper end of wharves at Clinton, an anchorage area of same depth opposite and above wharves, 50 feet wide south of channel and extending 600 feet above end of channel, with widths of 150 to 250 feet, and for maintenance of a stone dike closing a breach in the sandy peninsula which separates the river from outer harbor. (See Table 1-B at end of chapter for Acts authorizing existing project). Project was completed in 1950. Local cooperation. Fully complied with. Terminal facilities. There are several small private wharves, some of which are open to public use. These facilities are adequate for existing commerce. Operations during fiscal year. Maintenance: The dredging contract awarded last fiscal year was completed in November 1984. A total of 19,125 cubic yards of material was removed at a final contract cost of $123,930. Hired labor costs of $32,000 were incurred for supervision and inspection and after dredge surveys. 6. CONNECTICUT RIVER BELOW HARTFORD, CT Location. Has its source in Connecticut Lake in northern New Hampshire, flows southerly 380 miles and empties into Long Island Sound at Saybrook, CT, 14 miles west of New London. Hartford, now head of commercial navigation, is 52 statute miles, by channel, from mouth. (See National Ocean Survey Charts 12373 and 12377). Previous project. For details see Annual Reports for 1915 and 1938. Eightmile River, CT, elimination as separate project: Provides for a channel 8 feet deep and 75 feet wide from deep water in Connecticut River to Hamburg and for turning basin of same depth, 150 feet wide, approximately 300 feet long at Hamburg. Project was adopted by River and Harbor Act of 1910. Costs and expenditures were $9,000 all for new work. In accordance with River and Harbor Act of 1950, project for Connecticut River below Hartford was modified to include project for Eightmile River. Aforementioned Act also provided for an anchorage basin 6 feet deep and about 6.5 acres in area in upper cove in Hamburg. A channel 15 feet deep and 150 feet wide for a distance of 52 miles upstream to Hartford; two riprap jetties at the mouth of the river; and dikes, training walls, revetments and other regulatory works along the river between Hartford and Gildersleeve Island. The project provides for small-boat improvements at Wethersfield Cove; Eightmile River; Essex; and North Cove, Old Saybrook. For a more detailed description of project see page 7 of Annual Report for 1974. (See Table 1-B at end of chapter for Acts authorizing existing project). Existing project was completed in September 1965 with the construction of channel and anchorage in North Cove, Old Saybrook, CT. For further details, see Annual Report for 1974. Local cooperation. Fully complied with. Terminal facilities. Along both Connecticut and Eightmile Rivers there are two or three wharves at each river town, one or more in each town being open to public use. At Hartford and Middletown there is about one-half of wharf frontage along west bank of river. Facilities are adequate for existing commerce. Operations during fiscal year. Maintenance: Scheduled maintenance dredging was deferred due to insignificant shoaling resulting from low spring floods. A survey was completed by contract in August 1985 to revise and update horizontal controls for use with automated survey system. Total contract cost was $96,848. Hired labor costs of $86,832 were incurred for supervision and inspection, preparation of plans and specifications, plotting and surveys. 7. GREEN HARBOR, MA Location. On west side of Massachusetts Bay within the town of Marshfield about 30 miles southeast of Boston and 1-4 NEW ENGLAND DIVISION 9 miles north of Plymouth Harbor. (See National Ocean Survey Chart 13253) Existing project. Provides for channel 6 feet deep (8 feet at entrance), 100 feet wide extending about 4,000 feet from deep water to head of navigation with small turning basin at upstream limit; 5-acre anchorage near Town Pier, 6 feet deep; sealing, rebuilding in part, and a 200 feet extension of existing west jetty at elevation +12, with dike to beach berm at elevation +14 feet, and raising east jetty to elevation +14. (See Table 1-B at end of chapter for Act authorizing existing project). Construction was completed in October, 1969. Local cooperation. Fully complied with. Terminal facilities. Major terminal facility is Town Pier in village of Brant Rock. Facility is a bulkheaded, earth-filled landing and parking area about 290 feet wide, extending 210 feet into harbor. A marina service is south of Town Pier; and a facility for recreational craft has been developed on south side of harbor near head of navigation. Operations during fiscal year. Maintenance: A contract in the amount of $152,800 for maintenance dredging in the entrance channel was awarded in April 1985. Contractor was given "Notice to Proceed" in September 1985. There were no contract costs ending fiscal year 1985; $77,000 was expended on a specification survey and a pre-dredge survey for the dredging work as well as surveys in conjunction with the evaluation of entrance modifications. A total of $14,000 was expended for a study of the present harbor entrance structures by the Waterways Experiment Station. 8. HYANNIS HARBOR, MA Location. On south shore of Cape Cod about 16 miles west of Chatham, Massachusetts and 20 miles northeast of Vineyard Haven, Massachusetts. (See National Ocean Survey Chart 13237) Existing project. A stone breakwater 1,170 feet long, lying about 0. 7 mile off shore, dredging to 15.5 feet deep in protected area behind breakwater; a channel 12 feet deep with widths of 150 and 100 feet in outer and inner harbors respectively, an anchorage area 12 feet deep and and about 5 acres in area adjacent to inner harbor channel north of Harbor Bluff; and a riprap jetty 1,000 feet long extending south from Dunbar Point. Mean spring tidal ranges in outer harbor 3.1 and 3.7 feet, respectively. Breakwater was completed in 1882 and dredging behind breakwater in 1906. Rehabilitation was necessary to restore breakwater to its designed purpose of providing a harbor of refuge. Restoration was completed in November 1961. Construction of 12-foot channel and anchorage was initiated in May and completed in November 1959. Commonwealth of Massachusetts constructed the jetty extending south from Dunbar Point in 1962. (See Table 1-B at end of chapter for Acts authorizing existing project). Local cooperation. Fully complied with. Terminal facilities. There are two town wharves in the inner harbor. One has a bulkhead frontage of about 800 feet. Other private landings are available. Facilities are adequate for existing commerce. Operations during fiscal year. Maintenance: A contract in the amount of $237,870 for maintenance dredging was awarded in March 1985. A total of 25,000 cubic yards were dredged during the fiscal year at a cost of $220,250. Hired labor costs of $117,600 were incurred for an environmental assessment, preparation of plans and specifications, supervision and inspection, surveys and plotting. Work was essentially complete by the end of the fiscal year. 9. JONESPORT HARBOR, ME Location. Jonesport Harbor is situated on the north side of Moosabec Reach in Washington County, Maine about 190 miles northeast of Portland, Maine, and about 40 miles southwest of the Canadian border at Eastport, Maine. Existing project. Provides for a combined rubble mound and cellular steel sheet pile breakwater, 1,200 feet in length; a 15-acre anchorage composed of 9 acres, 6 feet deep, and 6 acres, 8 feet deep; and an entrance channel 100 feet wide and 8 feet deep. Latest approved cost estimate (October 1984) is $9,200,000. (See Table 1-B at end of chapter for Act authorizing existing project). Local cooperation. Local interests are required to provide without cost to the United States, all lands, easements, and rights-of-way required for construction and subsequent maintenance of the project and for aids to navigation upon the request of the Chief of Engineers, including suitable areas determined by the Chief of Engineers to be required in the general public interest for initial and subsequent disposal of spoil, and also necessary retaining dikes, bulkheads, and embankments therefor or the costs of such retaining works; hold and save the United States free from damages that may result from the construction and maintenance of the project; provide, maintain, and operate necessary mooring facilities and utilities including a public landing in Sawyer Cove with berthing depths alongside the landing commensurate with the depth provided in the entrance channel and including an adequate access road, parking area, and suitable related facilities open to all on equal terms, including transients; accomplish without cost to the United States such utility or other relocations or alterations as necessary for project purposes; reserve spaces within the harbor adequate for the accommodation of transient craft; regulate the use, growth, and free development of the harbor facilities with the understanding that said facilities will be open to all on equal terms, including transients; and establish regulations prohibiting discharge of pollutants into the waters of Jonesport Harbor by users thereof, which regulations shall be in accordance with applicable laws or regulations of Federal, State, and local authorities responsible for pollution prevention and control. Terminal facilities. There are thirteen privately owned wharves in the harbor, twelve of which are used by local fishermen and one which is used for receiving about three million gallons of petroleum annually. Operations during fiscal year. New work: Engineering and planning continued on a moderate basis, focusing primarily on updating the project cost estimate and co- 1-5 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 ordinating effects of proposed cost sharing changes with local interests. 10. KENNEBUNK RIVER, ME Location. Source of Kennebunk River is in central part of York County in southwestern Maine. Stream flows about 15 miles southeasterly and discharges into Atlantic Ocean about 350 miles southwestof Portland, Maine. (See National Ocean Survey Chart 13286). Existing project. For description of existing project see Annual Report for 1977. (See Table 1-B at end of chapter for Acts authorizing existing project). Project was completed in December 1968 with completion of rock removal at entrance to west channel. Extension of west jetty was completed in April 1965. Dredging and sand fence were completed in November 1965. Local cooperation. Fully complied with. Terminal facilities. There are 22 landings 16 of which are private, 1 public, 2 yacht clubs, 1 hotel, and 2 boatyards. Marine railway facilities include two of 15-ton capacity, and one of 10-ton capacity. There are 4 berths and 10 moorings. Open storage, boat building, repairs, and supplies are available for pleasure and commercial craft. Public landing of granite block construction, has unloading facilities which include two tackle and falls on arms; and is used by fishing craft to transfer catches for transportation. Facilities are adequate for existing commerce. Operations during fiscal year. Maintenance: Work under a maintenance dredging contract awarded late last fiscal year began in November 1984 and was completed in March 1985. A total of 26,156 cubic yards of material were dredged at a total contract cost of $202,447. Hired labor costs of $76,200 were incurred for supervision and inspection, surveys and plotting. 11. MIANUS RIVER, CT Location. Has its source in southeastern New York, and flows in a southerly direction about 20 miles, crossing southwestern corner of Connecticut, emptying into Captain Harbor, Long Island Sound. Project is about 3 miles west of Stamford Harbor, CT. (See National Ocean Survey Chart 12367). Previous project. For details see page 106, Annual Report for 1904. Existing project. Provides for channel 6 feet deep and 100 feet wide from Cos Cob Harbor to head of navigation at Boston Post Road, Mianus, distance of about 1.2 miles. Lower end of project is about 1 mile above entrance to Cos Cob Harbor. (See Table 1-B at end of chapter for Acts authorizing existing project.) Project was completed in 1951. Local cooperation. Fully complied with. Terminal facilities. There are two town wharves with about 750 feet of berthing space, a commercial wharf, several piers at small shipyards and one at the yacht club and two marinas. Most of these are open to the public subject to owners convenience. Facilities are adequate for existing commerce. Operations during fiscal year. Maintenance: A contract for maintenance dredging, awarded in March 1985. was completed in June 1985. Contract costs were $323,994 with 52,682 cubic yards of material removed. Hired labor costs of $102,700 were incurred for preparation of an environmental assessment, plans and specifications, supervision and inspection and surveys. 12. NEW LONDON HARBOR, CT Location. On the north shore of Long Island, at its eastern end and about 14 miles east of the mouth of the Connecticut River. (See National Ocean Survey Chart 13213). Previous projects. Adopted by River and Harbor Acts of June 14, 1880, March 3, 1881, and July 13, 1892. For further details see Annual Reports for 1915 and 1938, pages 1753 and 116, respectively. Existing project. For description of existing project and authorizing legislation see Annual Report for 1978. Project was completed in 1938. The Department of the Navy has twice deepened extensive lengths of the harbor in the interest of the National Defense. In May 1980 they completed their second effort. The Corps, at request of the Department of the Navy is currently maintaining these deeper depths within width limits of the authorized Corps' project. Local cooperation. Fully complied with for completed work; for new work, local interests are required to provide easements and rights-of-way required for construction and subsequent maintenance of the project; hold and save the United States free from damages due to construction of the project; make sure alterations to underwater utilities as necessary to enable full realization of the project benefits; and improve berth and access channels commensurate with the project depth. Terminal facilities. There are 36 wharves and piers in a developed frontage of about 3 miles. Seven piers are owned by the Federal Government of which five are being used. One pier is owned by the State and one by the city. Eight waterfront facilities are equipped to receive petroleum products. Seven of the wharves have direct rail connections. The total available berthage space is about 27,000 feet. (For further details, see Port and Terminal Facilities at the Ports of Southern New England, 1976.) Operations during fiscal year. Maintenance: Hired labor costs of $24,380 were incurred for an environmental assessment, a specification survey, plotting and preparation of plans and specifications. Bids were opened in August 1985 and contract award was pending resolution of protest. 13. NEWBURYPORT HARBOR, MA Location. On south bank of Merrimack River, about 2.5 miles above mouth, and about 48 miles by water north of Boston. (See National Ocean Survey Chart 13282). Existing project. Two jetties, one projecting 4,118 feet from the north shore, the other projecting 2,445 feet from the south shore, converging until 1,000 feet apart, then extending seaward 1,000 feet parallel to axis of channel; 1-6 NEW ENGLAND DIVISION partially closing Plum Island Basin by a timber dike; channel 12 feet deep and 400 feet wide through bar, thence 9 feet deep and 200 feet wide to and including a widened turning basin in front of wharves. Portion of project for continuous channel from sea to wharves at Newburyport, 15 feet deep and 200 feet wide to and including a widened turning basin in front of wharves is considered inactive. Estimated cost of this portion (June 1955) is $106,000. (See Table 1-B at end of chapter for Acts authorizing existing project). Existing project except for inactive portion was completed in August 1958, with the improvement of 12-foot channel and outer harbor. North jetty was completed in 1914; south jetty was completed, except for a length of about 30 feet at its outer end, in 1905. Required rehabilitation in these jetties completed in September 1970. Plum Island Basin was partially closed in 1883 by construction of a timber dike. North Rock was removed in 1901. Local cooperation. Fully complied with. Terminal facilities. Twenty wharves extending along a frontage of about 3,500 feet of south bank of Merrimack River below highway bridge and one small pier on north side of river. Terminal facilities are adequate for existing commerce. Operations during fiscal year. Maintenance: This fiscal year $2,783 was expended on work done by the Waterways Experiment Station for a model study. All work is now complete. 14. PENOBSCOT RIVER, ME Location. Drains a large number of lakes and small streams in north, central and eastern Maine and, after assuming definite character as a stream, flows about 100 miles southerly through middle of State, discharging into Penobscot Bay, about 90 miles northeast of Portland, Maine. (See National Ocean Survey Chart 13309). Previous projects. For details see Annual Reports for 1915, 1938, and 1949. Existing project. Dredging channel 22 feet deep between Winterport and Bucksport, about 16 miles below Bangor; for straightening, widening, and deepening to 15 feet channel near Stearns Mill and near Crosby's Narrows from 3 to 4.5 miles below Bangor; and for deepening harbor at Bangor to 14 feet and widening it along Bangor water front, giving an additional width of from 100 to 300 feet for a length of about 2,000 feet. Project depths refer to mean low water which is 3 feet above extreme low tide. Mean range of tide at Bangor is 13.1 feet, and extreme about 15 feet. (See Table 1-B at end of chapter for Acts authorizing existing project). Existing project was completed in 1913. Controlling depths at mean low water were: 22-foot channel between Winterport and Bucksport, generally 22.0 feet (1964) except 19.3 feet in channel opposite Lawrence Cove (1968); and 19.0 feet in channel opposite Frankfort Flats (1968); 15-foot channel near Sterns Mill and near Crosby's Narrows, 15 feet available for variable widths (1964): 14-foot harbor at Bangor, 13 feet available for a width of 270 to 600 feet (1964). Local cooperation. None required. Terminal facilities. Riverfront of Bangor has 12 wharves, most of which are timber-crib stone-ballasted type. Eleven wharves have railroad connections. On east side of river at Brewer, opposite Bangor, there is one water terminal, a coal handling plant having mechanical appliances and three petroleum products storage plants. At South Brewer there is a large pulp and paper plant which has water connections, oil pumping and storage facilities. A number of private wharves are open to public at moderate charges. At Bucksport north side of river there are three important terminals, one a coal handling plant and two used by a large paper manufacturing plant which has terminal facilities for receipt and storage of oil products and pulpwood. Facilities are adequate for existing needs. Operations during fiscal year. Maintenance: Final payment was made on a maintenance dredging contract completed last fiscal year. A total of 44,625 cubic yards were dredged at a cost of $170,021. Hired labor costs of $2,000 were incurred for administration of the contract. 15. POINT JUDITH POND AND HARBOR OF REFUGE, POINT JUDITH, RI Location. Point Judith marks southwestern entrance to Narragansett Bay. Harbor lies in shallow bight west of point, about 14 miles southwest of Newport Harbor, RI, and 33 miles east of New London Harbor, CT. Point Judith Pond is a shallow salt pond, with a length north and south of about 4 miles, lying in rear of sandy beach of Rhode Island shore, just west of Point Judith Harbor by a narrow opening through sand dunes. (See National Ocean Survey Charts 13218 and 13219). Previous project. For details see Annual Report for 1948. Existing project. For description of existing project see Annual Report for 1977. (See Table 1-B at end of chapter for Acts authorizing existing project). All work for project authorized prior to 1949 was completed in 1950. Breakwaters were completed in 1914 and dredging of shoals in project area was done in 1921. Main and east shore arm breakwater had deteriorated and required restoration to project design. In 1962 reconstruction of east arm breakwater and main breakwater dock facilities were completed. Rehabilitation required for remainder of breakwater restoration was completed in October 1963. The extension of the 15-foot channel was completed in April 1977. Local cooperation. Fully complied with. Terminal facilities. For further details on terminal facilities see Annual Report for 1977. Operations during fiscal year. Maintenance: A contract for repairs to center breakwater was terminated for convenience in March 1985. Subsequently, work under a contract modification was terminated for default. Contractor earnings were not resolved at the end of the fiscal year pending resolution of claims. Hired labor costs of $31,000 were incurred for supervision and administration as well as auditing of the contract; $13,700 was spent on testing rock samples. 1-7 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 16. PORTLAND HARBOR, ME Location. On southwestern coast of Maine about 100 miles northeast of Boston, MA. (See National Ocean Survey Chart 13292). Previous projects. For details see Annual Reports for 1915 and 1936. Existing project. For description of existing project and authorizing legislation see Annual Report for 1978. Project was completed in 1966, except for ledge removal that was completed in 1968. Local cooperation. Fully complied with. Terminal facilities. There are 37 waterfront facilities, of which 4 are not used. Seven wharves are publicly owned, 4by the U.S. Government, 2 by State of Maine, and 1 by city of South Portland. Mechanical-handling facilities are available at 24 wharves. Railroad connections have been made to 27 of them. Facilities are adequate for existing commerce. (For further details see page 13, H. Doc. 216, 87th Cong., and Port Series 1 for Ports of Searsport Harbor and Portland, Maine and Portsmouth, NH (revised 1964). Operations during fiscal year. Maintenance: Final payment was made on a maintenance dredging contract completed last fiscal year. An additional 24,650 cubic yards were dredged bringing the total to 44,650 cubic yards at a final contract cost of $313,488. Hired labor costs of $25,700 were incurred for supervision and inspection and after dredge surveys and plotting. 17. PROVINCETOWN HARBOR, MA Location. In the bight at northern extremity of Cape Cod, 40 miles southeast of Gloucester, 24 miles northeast of Cape Cod Canal and about 40 miles southeast of entrance to Boston Harbor. (See National Ocean Survey Charts 13249 and 13246). Previous project. For details see Annual Reports for 1915 and 1931. Existing project. Preservation of point of land forming the harbor, a rubblestone protection dike 5 feet wide and 15 feet above mean low water, 6,150 feet across House Point Island Flats from Stevens Point to Wood End, and a stone breakwater to elevation 15.5 feet with a top width of 10 feet commencing at a point about opposite MacMillan (Town) wharf, approximately 835 feet from shore and extending 2,500 feet northeasterly. The 300-foot extension of Long Point beach protection and bringing it up to grade, where necessary, portion is considered inactive. (See Table 1-B at end of chapter for Acts authorizing existing project). Existing project is complete except for inactive portion. Local cooperation. Fully complied with. Terminal facilities. Developed waterfront of Provincetown is approximately 1.5 miles in extent and mostly privately owned. There are seven piers in this area which handle entire commerce of harbor. None of the piers has railroad connections. Facilities are adequate for existing commerce. Operations during fiscal year. Maintenance: Final payment was made on work for repairs to dike between Stevens Point and Wood End completed at the end of last fiscal year. A total of 15,044 tons of quarried stone were placed at a final contract cost of $662,227. Hired labor costs of $12,000 were incurred for supervision and inspection. 18. ROYAL RIVER, ME Location. Situated 11 miles north of Portland, Maine in Yarmouth Village. Royal is a small coastal stream which empties into Casco Bay. (See National Ocean Survey Chart 13290). Existing project. Provides for enlargement of channel through bar at Gravel Point, 100 feet wide, 4.5 feet deep up to head of commercial navigation at Yarmouth, and removal of several ledges near village of Yarmouth; construction of 195-foot rubblestone jetty opposite Wolfe's Point, and dredging channel 4.5 feet deep through obstructed channels; channel 8 feet deep, 80 feet wide from State channel in Casco Bay to commercial wharf at Yarmouth and anchorage of 8 acres, 6 feet deep downstream of Interstate 95 Highway Bridge. Project was completed in June 1969. (See Table 1-B at end of chapter for Acts authorizing existing project). Local cooperation. Fully complied with. Terminal facilities. Town has constructed public landing and launching ramp immediately below Interstate 95 Highway Bridge on north bank. There are two boatyards equipped with floats, marine railways and launching ramps. Operations during fiscal year. Maintenance: A maintenance dredging contract in the amount of $147,600 was awarded in March 1985. Due to administrative delays in securing necessary bonds, work did not begin until July. By the end of the fiscal year 37,500 cubic yards had been dredged at a cost of $147,750. Hired labor costs of $55,400 were incurred for plans and specifications, surveys, supervision and inspection. 19. SACO RIVER, ME Location. Rises in White Mountain region of New Hampshire at an elevation about 1,900 feet above sea level, flows about 105 miles in a general southeasterly direction, and discharges into Atlantic Ocean about 16 miles southwest of Portland, Maine. (See National Ocean Survey Chart 13287). Existing project. For description of completed existing portion of project see Annual Report for 1978. For a description of completed improvement of project see Annual Report for 1983. (See Table 1-B at end of chapter for Acts authorizing existing project). Local cooperation. Fully complied with. Terminal facilities. There are five wharves of solid fill construction at Saco and Biddeford, none of which has railroad connection; and a small pier near mouth of river used for summer passenger business. 1-8 NEW ENGLAND DIVISION Operations during fiscal year. Maintenance: A contract for $9,600 was awarded for installation of four daybeacon spindles to replace deteriorated stone beacons on the north breakwater and south jetty. Hired labor costs of $13,000 were incurred for preparation of plans and specifications as well as a specification survey. Agreement was reached to transfer maintenance of the new daybeacons to the First Coast Guard District. 20. STONINGTON HARBOR, ME Location. The town of Stonington in Hancock County is the southernmost of two municipalities located on Deer Isle at the eastern boundry of Penobscot Bay approximately 90 miles east of Portland and 40 miles south of Bangor, ME. (See National Ocean Survey Charts 13315 and 13308). Existing project. Provides for an access channel 10 feet deep extending from deep water in Deer Isle Thoroughfare 525 feet for a width of 100 feet, narrowing to 60 feet in width for a length of 275 feet, for a total length of 800 feet; and an anchorage basin 10 acres in size, of which 3 acres would be dredged to a depth of 8 feet mean low water and 7 acres dredged to a depth of 6 feet mean low water. (See Table 1-B at end of chapter for Act authorizing existing project). Project is complete. Local cooperation. Fully complied with. Terminal facilities. There are presently no public shore facilities in Stonington Harbor. There are several private commercial piers and wharves where Stonington fishermen currently offload. There are also two municipally- owned docks which are only accessible at higher stages of the tide. Operations during fiscal year. New Work: Administrative closeout of the contract completed in May 1984 resulted in additional expenditure of $3,223. Final contract cost is $493,123. 21. RECONNAISSANCE AND CONDITION SURVEYS (See Table 1-Q at end of chapter). 22. OTHER AUTHORIZED NAVIGATION PROJECTS (See Table 1-C at end of chapter). 23. NAVIGATION ACTIVITIES PURSUANT TO SECTION 107, PUBLIC LAW 86-645 (PREAUTHORIZATION) (See Table 1-H at end of chapter). Alterations of Bridges 24. AUTHORIZED BRIDGE ALTERATION Location. Chelsea Street Highway Bridge, MA. Construction was completed in October 1961 with a Federal cost of $138,518. In addition non-Federal contributed funds amounted to $8,062. For details see page 63 of Annual Report for 1962. 25. REVERE BEACH, MA SLocation. In the city of Revere, Suffolk County, Massachusetts, approximately 7 miles north of the main entrance channel to Boston Harbor and 6 miles northeast of the city of Boston. (See National Oceanic and Atmospheric Administration Chart No. 13275 and U.S Geological Survey Maps, Boston Bay quadrangle). Existing project. Placement of sandfill along 13,000 feet of beach. The top of the sandfill will be placed at 18 feet above mean low water, including a 50 foot wide berm, sloping one-foot vertical in 15 feet horizontal to meet the existing beach. The total width of the beach will extend approximately 300 feet, of which, about 185 feet is above the mean high water line. The estimated total first cost (August 1985) of the project is $6,900,000 of which 50 percent is non-Federal as presently authorized. (See Table 1-B at end of chapter for Acts authorizing existing project). Local cooperation. Formal assurances have not been requested. Local interests are required to: contribute in cash 50 percent of the cost of construction of the project, presently estimated at $3,450,000; contribute in cash 50 percent of the periodic nourishment cost for an initial period of 15 years, now estimated at $30,000 annually, such contribution to be prior to each nourishment operation; assure the continued performance of the periodic nourishment and repair of the project after the first 15 years and during the economic life as may be required to serve the intended purpose; assure that water pollution that would endanger the health of bathers would not be permitted; hold the United States free from damages due to construction of the project; provide all necessary lands, easements and rights-of-way for the initial construction and subsequent nourishment of the project; assure continued public ownership of the shore and its administration for public use during the economic life of the project. Operations during fiscal year. New work: Advance engineering and design was continued. The General Design Memorandum was completed in August 1985. 26. INSPECTION OF COMPLETED BEACH EROSION CONTROL PROJECTS Inspections of beach erosion projects were not conducted in fiscal year 1985. 27. OTHER AUTHORIZED BEACH EROSION CONTROL PROJECTS (See Table 1-D at end of chapter). 1-9 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 28. BEACH EROSION CONTROL ACTIVITIES PURSUANT TO SECTION 103, PUBLIC LAW 87-874 (PREAUTHORIZATION) (See Table 1-I at end of chapter). Flood Control 29. BLACKSTONE RIVER BASIN, MA AND RI Works covered by this plan include a dam and reservoir on West River and local protection works at three cities on Blackstone River. Flood Control Act of 1944 authorized plan for a reservoir on West River and local protection works at Worcester, MA, and Woonsocket and Pawtucket, RI, substantially in accordance with House Document 624, 78th Congress, 2nd session. Flood Control Act of 1960 authorized a local flood protection project at Lower Woonsocket, RI, substantially in accordance with Senate Document 87, 85th Congress, 2nd session. Local protection nonstructural project authorized in 1982 for Belmont Park section of Warwick, RI along the Pawtuxet River. Streambank protection projects on the Blackstone River in Millbury, MA and on the Clear River in Burrillville, RI were authorized in 1985. (See Table 1-K at end of chapter on reservoir and local protection projects, Blackstone River Basin, for projects comprising authorized plan). 29A. BLACKSTONE RIVER, MILLBURY, MA Location. The town of Millbury is located in the southcentral part of Worcester County in central Massachusetts, and lies about 3 miles south of Worcester. Existing project. Remove the existing shoal and construct a stone slope protection along both banks of the Blackstone River to prevent further erosion and possible loss of McCracken Road Bridge. Local cooperation. Provide without cost to the United States all lands, easements, rights-of-way and utility relocations necessary for project construction; hold and save the United States free from damages due to the construction, operation and maintenance of the project, except where such damages are due to the fault or negligence of the United States or its contractors; maintain and operate the project after completion without cost to the United States; assume responsibility for all costs in excess of the Federal cost limitation of $250,000; prevent future encroachment which might interfere with proper functioning of the project. Operations during fiscal year. New work: Plans and specifications were prepared. A construction contract in amount of $175,475 was awarded in late July 1985. On site work began in mid-August and at year end the contract was 37 percent completed. 29B. CLEAR RIVER, BURRILLVILLE, RI Location. The town of Burrillville is located in the northwest corner of Rhode Island. The main stem of the Clear River originates in the northwest corner of Rhode Island and flows easterly for 8 miles to its confluence with the Branch River. Existing project. Remove approximately 60 linear feet of granite retaining wall, which has been damaged from erosion, and construct a new mortared stone wall. Local cooperation. Provide without cost to the United States all lands, easements, rights-of-way and utility relocations necessary for project construction; hold and save the United States free from damages due to the construction, operation and maintenance of the project, except where such damages are due to the fault or negligence of the United States or its contractors; maintain and operate the project after completion without cost to the United States; assume responsibility for all costs in excess of the Federal cost limitation of $250,000; and prevent future encroachment which might interfere with proper functioning of the project. Operations during fiscal year. New work: Plans and specifications were prepared. Contract bids were received in July 1985 but were rejected as excessive. Project will be re-advertised next fiscal year. 29C. PAWTUXET RIVER, WARWICK, RI Location. The Pawtuxet River flows in a northeasterly direction through West Warwick, Warwick and Cranston before it discharges into Narragansett Bay at Pawtuxet Cove. The watershed has a maximum length of 18 miles running west to east and 23 miles width from north to south. The drainage area at its mouth in Pawtuxet Cove is 230 square miles. The project is located in the Norwood section of Warwick, locally referred to as Belmont Park Existing project. Consists of acquisition, demolition and removal from the flood plain a total of 61 homes; acquisition of 19 privately-owned vacant lots; construction of 12 above-ground utility room additions to residences which experience basement flooding; and the installation of an automated flood forecasting and warning system. The current estimated project cost is $4,000,000 with the Federal government paying 80 percent of the project cost up to a Federal limit of $4 million. After implementation, the city of Warwick would be responsible for the cost of operating and maintaining the flood forecasting/warning system. (See Table 1-B at end of chapter for authorizing legislation). Project implementation was begun in September 1982 with property acquisition. Acquisition is approximately 93 percent complete with 6 vacant lots remaining to be acquired. Local cooperation. Local interests must implement acqusition and removal of properties and pay 20 percent of project costs unless total project costs exceed $5,000,000 in which case local interests incur all costs above that figure. Operations during fiscal year. New Work: Acquisition continued. A total of 28 properties were acquired during the year, bringing the total to date to 74. Design of the utility room additions was completed and two contracts were awarded at a total price of $360,000. Work on these additions was underway at year end. 1-10 NEW ENGLAND DIVISION 29D. WEST HILL DAM, MA Location. Dam is on West River, MA, 3 miles above its confluence with Blackstone River and 2.5 miles northeast of Uxbridge, MA. (See Geological Survey maps - Blackstone, MA and RI, Milford, MA, and Grafton, MA). Existing project. For description of completed improvement and authorizing legislation see Annual Report for 1975. Project is complete. Work on contract for dam and appurtenant structures was initiated in June 1959 and completed in June 1961. Construction of recreational facilities was completed in June 1967. Local cooperation. Section 3, Flood Control Act of 1944 applies. Operations during fiscal year. Maintenance: Ordinary operation and maintenance activities. 29E. CHARLES RIVER (NATURAL VALLEY STORAGE AREAS), MA Location. The Charles River extends inland from Boston Harbor southwesterly toward the Massachusetts- Rhode Island border and is some 80 miles long with a watershed covering 307 square miles Existing project. The project provides for Federal acquisition and protection of 17 natural valley storage areas totalling 8,136 acres in what is known as the Middle and Upper watershed of the Charles River. The acquisition in fee or by easement of the major natural valley storage areas within the Charles River watershed is intended as a multiple-purpose project for flood control, recreation, and fish and wildlife management. The latest cost estimate for new work is $9,000,000. (See Table 1-B at end of chapter for Act authorizing existing project). Land acquisition is complete. A total of 3,252 acres have been acquired in fee at a cost of $2,139,483 and restrictive easements have been obtained for 4,863 acres at a cost of $526,243. Local cooperation. Local interests are required to prevent modifications or alteration of existing roadways, utilities, bridges, culverts, and any other improvements that might affect the drainage characteristics of the natural storage areas; adopt and enforce regulations to restrict development of flood plan lands; and operate and maintain the existing dams along the Charles River. Local assurances have been received. Operations during fiscal year. New work: Resolution of remaining condemnation cases continued. Of 72 tracts remaining to be settled at the beginning of the fiscal year, 45 were resolved. Fiscal year costs totalled $177,900 including $132,667 for fee/easement acquisition, $8,600 for appraisal contracts, $11,349 in hired labor costs for miscellaneous project administration activities, and $25,284 for condemnation trial activity. Maintenance: Contract costs of $72,689 for boundary marking were incurred. Hired labor costs for project surveillance and inspection as well as land use administration were $76,411. A license was executed on August 1, 1985, by the Commonwealth of Massachusetts, Massachusetts Division of Fisheries and Wildlife, spread over 9 storage areas, totaling approximately 2,640 acres of fee land and water under the primary jurisdiction of the Department of the Army, and accepted by the Corps of Engineers on August 20, 1985. 30. CONNECTICUT RIVER BASIN VT, NH, MA and CT Location. Works covered by this project are a series of dams and reservoirs on tributaries of Connecticut River in Vermont, New Hampshire and Massachusetts, within a radius of 230 miles from Hartford, CT, and local protection works at several cities in the basin Existing project. Flood Control Act of 1936, as amended by Act of May 25, 1937, authorized construction of 10 reservoirs on tributaries of Connecticut River in accordance with plans in House Document 412, 74th Congress, 2nd session, as the same may be revised upon further investigation of 1936 flood. Flood Control Act of 1938 approved a general comprehensive plan for control of floods and other purposes in Connecticut River Valley, as set forth in House Document 455, 75th Congress, 2nd session, and authorized $11,524,000 for construction of local flood protection projects in the plan. Act of October 15, 1940, modified Act of June 18, 1938, to provide additional protection at East Hartford, CT, as set forth in House Document 653, 76th Congress, 3rd session. Act of August 18, 1941, modified comprehensive plan approved in 1938 to include improvements recommended in House Document 653, 76th Congress, 3rd session, and House Document 724, 76th Congress, 3rd session, with such further modifications as may be found justifiable in discretion of Secretary of the Army and Chief of Engineers. Latter Act also authorized to be appropriated additional $6 million for local protection works and $10 million for reservoirs. Act of October 26, 1942, further modified plan by including construction of Gully Brook conduit at Hartford, CT. Flood Control Act of 1944 authorized expenditure of $30 million in addition to previous authorization for comprehensive plan approved in 1938 and modified plan by directing specific consideration of an alternative plan of Vermont State Water Conservation Board instead of Williamsville Reservoir in West River Basin, VT; directing consultation with affected States during course of investigations and transmission of proposal and plans to each affected State for written views and recommendations for reservoir projects heretofore authorized for construction at Cambridgeport, Ludlow, South Tunbridge, and Gaysville, and resubmission of projects or modifications for construction of Sugar Hill site. Flood Control Act of 1950 modified project for flood control at Hartford, CT, authorized by Flood Control Act of 1938, as amended to include Folly Brook dike and conduit. Flood Control Act of 1954 modified plan for flood control in Connecticut River Basin to provide for construction of a reservoir on Otter Brook at South Keene, NH, in lieu of any reservoir or reservoirs heretofore authorized. This Act further modified plan for West River Basin of Connecticut River in Vermont to consist of three reservoirs at Ball Mountain, The Island, and Townshend sites, in lieu of plan of eight reservoirs authorized in Flood Control Act of 1944. Flood Control Act of 1958 modified plan for flood control in 1-11 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Connecticut River Basin to include construction of Littleville Reservoir on Middle Branch of Westfield River, MA and Mad River Reservoir on Mad River, above Winsted, CT. Flood Control Act of 1960 included authorization in Connecticut River Basin of plan for flood protection on Chicopee River, MA, substantially in accordance with House Document 434, 86th Congress; plan for flood protection on Westfield River, MA, substantially in accordance with Senate Document 109, 86th Congress; plan for flood control and related purposes on Farmington River, CT, substantially in accordance with House Document 443, 86th Congress. Flood Control Act of 1968 included authorization in Connecticut River Basin of plan for construction of Beaver Brook Reservoir, on Beaver Brook in Keene, NH, substantially in accordance with Senate Document 60, 90th Congress; and plan for protection on Park River, CT, substantially in accordance with Senate Document 43, 90th Congress. Flood Control Act of 1970 deauthorized the construction of a reservoir at Claremont, NH. The Water Resources Development Act of 1976 deauthorized the construction of Gaysville Lake, Vermont project. Flood control projects at Cambridgeport Lake, Brockway Lake, Victory Lake, South Tunbridge Lake, Ludlow Lake and The Island Lake, Vermont; Honey Hill Lake, West Canaan Lake, and the Alternative to Sugar Hill Reservoir, New Hampshire were deauthorized in August 1977 in accordance with section 12 of the Water Resources Development Act of 1974. The authorization for Beaver Brook Lake, New Hampshire project expired in April 1978 due to lack of local cooperation. Local protection projects at Gardner, MA, Hartford, VT and Wethersfield, CT authorized and constructed in accordance with section 205 of 1948 Flood Control Act. Local protection project at Keene, NH authorized in accordance with Section 205 of 1948 Flood Control Act, is under construction. (See Table 1-L at end of chapter for reservoirs and local protection works included in comprehensive plan). 30A. BALL MOUNTAIN LAKE, VT Location. Dam is on West River, 29 miles above its junction with Connecticut River at Brattleboro, VT. It is 2 miles north of village of Jamaica, VT. (See Geological Survey map for Londonderry, VT). Existing project. For description of completed improvements and authorizing legislation see Annual Report for 1975. Project is complete. Construction of dam and appurtenant works was initiated in May 1957 and completed in November 1961. Construction of initial recreation facilities was initiated in June 1975 and completed in June 1977. Local cooperation. Section 2, Flood Control Act of 1938 applies. Operations during fiscal year. Maintenance: Ordinary operation and maintenance activities. A contract awarded in November 1984 for installation of lightning protection at nine dam sites was completed in July 1985. Total contract amount was $84,541 of which $19,200 was for the Ball Mountain Lake installation. A contract to update the control panels was awarded in May 1985. Completion is scheduled for November 1985. Final contract amount is expected to be $15,845. 30B. BARRE FALLS DAM, MA Location. Dam is on Ware River in town of Barre,MA, 31.9 miles above confluence of Ware and Swift Rivers. It is 13 miles, northwest of Worcester, MA (See Geological Survey maps for Barre, MA, and Wachusett Mountain, MA). Existing project. For description of completed improvements and authorizing legilation see Annual report for 1975. Project is complete. Construction of dam and appurtenant works was initiated in May 1956 and completed in May 1958. Local cooperation. Section 2, Flood Control Act of 1938 applies. Operations during fiscal year. Maintenance: Ordinary operation and maintenance activities. A contract awarded in November 1984 for installation of lightning protection at nine dam sites was completed in July 1985. Total contract amount was $84,541 of which $4,776 was for the Barre Falls Dam installation. A contract for gatehouse furnace and Utility Building boiler replacement was awarded in June 1985. The contract was 95% complete at fiscal year end. Final contract amount is expected to be $14,700. A contract to replace the sewage disposal system was awarded in August 1985. Contract amount is $23,644 and was 25 percent complete at fiscal year end. 30C. BEAVER BROOK, KEENE, NH Location. Keene is located in southwestern New Hampshire approximately 15 miles north of the Massachusetts border and 12 miles east of the Vermont border. Existing project. Consists of structural modifications to the outlet of the Three Mile Swamp and widening the Beaver Brook channel in the reach between Water Street and Marlboro Street. Estimated project first costs amount to $2,100,000 of which the Federal first cost totals $1,925,000. Non-Federal first costs are estimated to total $175,000. Local cooperation. Provide all lands, easements, rightsof- way, utility relocations and alterations necessary for project implementation; hold and save the United States free from damages due to the construction, operation and maintenance of the project except where such damages are due to the fault of the United States or its contractors; maintain and operate the project after completion without cost to the United States; assume full responsibility for all project costs in excess of the Federal statutory limitation of $4,000,000; twice yearly inform residents and property owners within the Beaver Brook floodplain of the limitations of the flood control improvements and alert them to the continued threat of major flooding along the brook. Operations during fiscal year. New work: Contract plans and specifications were completed. A construction contract in the amount of $1,672,195 was awarded in September 1985. Work has not yet begun. 30D. BIRCH HILL DAM, MA Location. Dam is on Millers River, 27.3 miles above its junction with Connecticut River. It is 1.3 miles east of 1-12 NEW ENGLAND DIVISION South Royalston, MA and 7.5 miles northwest of city of Gardner, MA. (See Geological Survey maps for Royalston and Winchendon, MA-NH and Templeton, MA). Existing project. For description of completed improvement and authorizing legislation see Annual Report for 1975. Project is complete. Construction of dam and appurtenant works was initiated in June 1940 and completed in February 1942. Local cooperation. Section 2, Flood Control Act of 1938 applies. Local interests have contributed $32,000 as their required 50 percent cost sharing of recreational development in accordance with 1965 Federal Water Project Recreation Act. Operations during fiscal year. Maintenance: Ordinary operation and maintenance activities. A contract to replace the standby generator was awarded in February 1985 and completed in June 1985. Final contract amount was $20,389. 30E. COLEBROOK RIVER LAKE, CT Location. Damsite is in town of Colebrook, Litchfield County, CT, on West Branch Farmington River about 3.9 miles upstream from its confluence with Still River at Riverton, CT, and about 1.5 miles upstream from Goodwin (Hogback) Dam. (See Geological Survey map for Winsted, CT). Existing project. For description of completed improvement and authorizing legislation see Annual Report for 1975. Project is complete. Construction of dam and appurtenant works was initiated in May 1965 and completed in June 1969. Construction of recreation facilities was initiated in August 1969 and completed in June 1970. Local cooperation. Water supply contract was signed by Hartford Connecticut Metropolitan Water District. Repayment is being made in accordance with provisions of 1958 Water Supply Act. Operations during fiscal year. Maintenance: Ordinary operation and maintenance activities. A contract to replace the gatehouse roof was awarded in April 1985. Five other projects are included in the total contract amount of $23,985. Completion is scheduled for next fiscal year and is expected to amount to $3,895 for the Colebrook project. 30F. CONANT BROOK DAM, MA Location. Site is in south central part of Massachusetts in town of Monson. Damsite, across Conant Brook, is about 2 miles southeast of community of Monson. (See Geological Survey map for Monson, MA). Existing project. For description of completed improvement and authorizing legislation see Annual Report for 1975. Project is complete. Construction of dam, highway relocations, and appurtenances was initiated in June 1964 and completed in December 1966. Local cooperation. Section 2, Flood Control Act of 1938 applies. Operations during fiscal year. Maintenance: Ordinary operation and maintenance activities. 30G. KNIGHTVILLE DAM, MA Location. Dam is on Westfield River, 27.5 miles above its confluence with ConnecticutRiver. It is 4 miles north of town of Huntington, MA, and about 12 miles west of city of Northampton, MA. (See Geological Survey map for Westhampton, MA). Existing project. For description of completed improvements and authorizing legislation see Annual Report for 1975. Project is complete. Construction of dam and appurtenant works was initiated in August 1939 and completed December 1941. Local cooperation. Section 2, Flood Control Act of 1938 applies. Operations during fiscal year. Maintenance: Ordinary operation and maintenance activities. A contract for rehabilitation of the gatehouse awarded in May 1984 was completed in April 1985. Final contract amount was $279,398. Another contract to repair the concrete conduit was awarded in July 1985 and completed in August. Contract amount was $6,224. 30H. LITTLEVILLE LAKE, MA Location. Dam is on Middle Branch of Westfield River, 1 mile above its confluence with main stem of Westfield River and 25.2 miles above confluence of Westfield River with Connecticut River, in town of Chester. (See Geological Survey map for Chester, MA). Existing project. For description of completed improvement and authorizing legislation see Annual Report for 1975. Project is complete. Construction of dam and appurtenances was initiated under a multicomponent contract in June 1962 and completed in September 1965. Local cooperation. Section 2, Flood Control Act of June 28, 1938, and Title III, Water Supply Act of 1958 applies and fully complied with. Operations during fiscal year. Maintenance: Ordinary operation and maintenance activities. A contract to replace the Intake Tower roof was awarded in April 1985. Five other projects are included in the total contract amount of $23,985. Completion is scheduled for next fiscal year and is expected to amount to $4,865 for the Littleville project. 30I. NORTH HARTLAND LAKE, VT Location. Dam is on Ottauquechee River, 1.5 miles above its junction with Connecticut River and 1 mile northwest of North Hartland, VT. Reservoir extends upstream 5.5 miles. (See Geological Survey map for Hanover, NH-VT). Existing project. For description of completed improvement and authorizing legislation see Annual Report for 1975. Project is complete. Construction of dam was initiated in June 1958 and completed in June 1961. Local cooperation. Section 2, Flood Control Act of 1938 applies. Operations during fiscal year. Maintenance: Ordinary operation and maintenance activities. A contract awarded in November 1984 for installation of lightning protection 1-13 REPORT OF THE CHIEF OF ENGINEERS .-U.S. ARMY 1985 at nine dam sites was completed in July 1985. Total contract amount was $84,541, of which $18,340 was for the North Hartland Lake installation. A contract to replace the emergency generator and feeder circuit awarded in June 1984 was 73 percent complete at fiscal year end. Contract amount is $47,987. 30J. NORTH SPRINGFIELD LAKE, VT Location. Dam is in town of Springfield, VT, on Black River, 8.7 miles above its junction with Connecticut River, and 3 miles northwest of Springfield, VT. (See Geological Survey maps for Ludlow, VT and Claremont, NH). Existing project. For description of completed improvement and authorizing legislation see Annual Report for 1975. Project is complete. Construction of dam was initiated in May 1958 and completed in November 1960. Local cooperation. Section 2, Flood Control Act of 1938 applies. Operations during fiscal year. Maintenance: Ordinary operation and maintenance activities. A contract for remedial measures for seepage control was awarded in July 1985 and was 30 percent complete at fiscal year end. Contract amount is $560,945. 30K. OTTER BROOK LAKE, NH Location. Dam is on Otter Brook, 2.4 miles upstream from its junction with The Branch, which flows 2.5 miles to Ashuelot River at Keene. (See National Ocean Survey maps for Keene, NH-VT, and Monadnock, NH). Existing project. For description of completed improvement and authorizing legislation see Annual Report for 1975. Project is complete. Construction of dam and appurtenant works was initiated in September 1956 and completed in August 1958. Local cooperation. Section 2, Flood Control Act of 1938 applies. Operations during fiscal year. Maintenance: Ordinary operation and maintenance activities. A contract awarded in November 1984 for installation of lightning protection at nine dam sites was completed in July 1985. Total contract amount was $84,541, of which $5,650 was for the Otter Brook Lake installation. A contract awarded in July 1984 to replace the Control Tower heating system was completed in May 1985. Contract amount was $9,270. A contract awarded in November 1984 to replace the service bridge rocker bearings was completed in November 1984. Contract amount was $10,600. A contract to replace the emergency generator awarded in June 1984 was 42 percent complete at fiscal year end. Contract amount is $23,229. A contract to replace the two bridges in the recreation area was awarded in June 1985 and was 20 percent complete at fiscal year end. Contract amount is $101,998. 30L. PARK RIVER, HARTFORD, CT Location. On the Park River in the city of Hartford, Hartford County, CT. (See Geological Survey map of Hartford North, CT). Existing project. Authorized as a modification to completed Hartford, CT local protection project. (For details on completed project see Annual Report for 1960). Two sections of reinforced concrete conduit totalling 2,569 feet with width of 34 feet and height of 26.5 feet on the Park River; one section of reinforced concrete conduit 103 feet long, 36 feet wide and 27.5 feet high on the South Branch; two sections of reinforced concrete conduit 1,364 feet long, 22 feet wide and 25 feet high on the North Branch; a reinforced concrete junction structure to combine the flows from the North and South Branches and distribute them to the Park River and auxiliary conduits and thence to the Connecticut River, circular auxiliary conduit approximately 9,200 feet long to be constructed as a deep tunnel in rock with an inside diameter of 22 feet and lined with 9-inch thick precast concrete walls, an inlet structure and an outlet structure; a concrete headwall at the entrance to the North Branch conduit extension; and two pumping stations on the banks of the Park River. The lastest approved cost estimate (September 1984) for new work is $1,300,000 for lands including relocations and $60,177,000 for construction, a total of $61,477,000. Total includes local costs of $1,200,000 for lands and $100,000 for relocations. (See Table 1-B at end of chapter for Act authorizing existing project). Construction was completed in 1981. Local cooperation. Provide all lands, easements and rights-of-way for construction and operation of project; hold and save the United States free from damages due to construction works; maintain and operate all works after completion; upon completion of conduit construction replace pavements, sidewalks, drainage and other appurtenances, including those at Broad Street, Flower Street and Laurel Street and bear cost of removal, replacement and modification to sewers, drains, utilities or highways beyond the area required for excavation and construction of the project; prevent changes in headpool ponding areas which would decrease the effectiveness of the improvements and if ponding areas and capacities are impaired, promptly substitute equivalent storage capacity; and undertake all practical measures to prevent pollution from entering the Park River conduit system. Operations during fiscal year. New work: Closeouts of utility contracts and non-Federal escrow account were accomplished. Fiscal year costs were $54,889 and only minor administrative closeout remains. 30M. SURRY MOUNTAIN LAKE, NH Location. Dam is on Ashuelot River, 34.6 miles above its junction with Connecticut River and 5 miles north of Keene, NH. (See Geological Survey maps for Keene and Bellows Falls, NH-VT). Existing project. For description of completed improvement and authorizing legislation see Annual Report for 1975. Project is complete. Construction of dam and appurtenant works was initiated in August 1939 and completed in June 1942. Initial phase of additional recreational facilities completed in September 1969, secondary phase in 1980. Local cooperation. Section 2, Flood Control Act of 1938 applies. 1-14 NEW ENGLAND DIVISION Operations during fiscal year. Maintenance: Ordinary operation and maintenance activities. A contract awarded in November 1984 for installation of lightning protection at nine dam sites was completed in July 1985. Total contract amount was $84,541 of which $6,400 was for the Surry Mountain Lake installation. A contract to repair roads and parking areas of the recreation area was awarded in January 1985 and was 95 percent complete at fiscal year end. Contract amount is $87,170. A contract to replace the standby generator was awarded in March 1985 and is scheduled for completion next fiscal year. Contract amount is $19,222. 30N. TOWNSHEND LAKE, VT Location. Dam is on West River, 19.1 miles above its junction with Connecticut River at Brattleboro, VT, and about 2 miles west of Townshend, VT. Reservoir extends upstream about 4 miles. (See Geological Survey maps for Saxtons River, VT, and Londonderry, VT). Existing project. For description of completed improvement and authorizing legislation see Annual Report for 1975. Project is complete. Construction of dam and appurtenant works was initiated in November 1958 and completed in June 1961. Initial phase of additional recreational facilities comoleted in October 1969. Secondary phase completed in tember 1971. Local cooperation. Section 2, Flood Control Act of 1938 applies. Operations during fiscal year. Maintenance: Ordinary operation and maintenance activities. A contract awarded in June 1984 to replace the exterior gatehouse hoist was completed in July 1985. Contract amount was $17,875. A contract to update the control panels was awarded in May 1985 and was 50 percent complete at fiscal year end. Contract amount is $15,845. A contract awarded in July 1985 for remedial measures for seepage control - relief wells was 20 percent complete at fiscal year end. Contract amount is $257,070. 300. TULLY LAKE, MA Location. Dam is on East Branch of Tully River, 3.9 miles above its junction with Millers River. It is 1 mile north of Fryville, MA and 3.5 miles north of Athol, MA. (See Geological Survey map for Royalston, MA-NH). Existing project. For description of completed improvement and authorizing legislation see Annual Report for 1975. Project is complete. Construction of dam and appurtenant works was initiated in March 1947 and completed in September 1949. Local cooperation. Section 2, Flood Control Act of 1938 applies. Local interests must also bear 50 percent of future recreational development, in accordance with 1965 Federal Water Project Recreational Act. Operations during fiscal year. Maintenance: Ordinary operation and maintenance activities. A contract awarded in November 1984 for installation of lightning protection at nine dam sites was completed in July 1985. Total contract amount was $84,541 of which $3,782 was for the Tully Lake installation. 30P. UNION VILLAGE DAM, VT Location. Dam is on Ompompanoosuc River 4 miles above its junction with Connecticut River. It is one-fourth mile north of Union Village, VT and 11 miles north of White River Junction, VT. (See Geological Survey maps for Strafford, VT and Mount Cube, NH-VT). Existing project. For description of completed improvement and authorizing legislation see Annual Report for 1975. Project is complete. Construction of dam was initiated in March 1947 and completed in June 1950. Local cooperation. Section 2, Flood Control Act of 1938 applies. Operations during fiscal year. Maintenance: Ordinary operation and maintenance activities. A contract awarded in November 1984 for installation of lightning protection at nine dam sites was completed in July 1985. Total contract amount was $84,541 of which $6,800 was for the Union Village Dam installation. 30Q. VILLAGE OF SAXTONS, VT Location. The town of Rockingham is located along the west bank of the Connecticut River in southeastern Vermont, about 22 miles north of Brattleboro and 8 miles south of Springfield. The town is comprised of several villages, including Saxtons River which is located along the banks of the Saxtons River, a tributary of the Connecticut River. The total drainage area of the Saxtons is 78 square miles and it flows from its upper watershed in the Green Mountains generally west to east for a distance of about 20 miles to its confluence with the Connecticut River. Existing project. Provides for correction of streambank erosion problems that endanger town-owned access ramps to the Saxtons River which are used during fire emergencies to pump water from the river. Work includes providing for construction of a precast concrete, modulartype wall about 175 feet long to protect the primary pumping site. (See Table 1-B at end of chapter for Act authorizing existing project). Local cooperation. Fully complied with. Operations during fiscal year. New work: Work on the prior year contract was completed in January 1985. Contract earnings this fiscal year were $13,665. In addition $6,519 was expended for Real Estate project planning and supervision and inspection this fiscal year. 30R. WEST SPRINGFIELD, MA Location. The West Springfield local protection works are located in the town of West Springfield, MA. The project is on the west bank of the Connecticut River, 76 miles above its mouth. (See Geological Survey maps for Springfield South and West Springfield, MA-CT). Existing project. This project consists of a system of earth levees and concrete floodwalls approximately 24,500 1-15 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 feet in length. The system starts at high ground, in the vicinity of Harrison Place, and extends downstream along the Connecticut River and up the north bank of the Westfield River to high ground at the Boston & Albany Railroad. The work involved raising 13,700 feet of existing levee, constructing 2,300 feet of floodwall, improving 2,400 feet of river bank, and treating 6,100 feet of existing levee foundation. Three pumping stations with appurtenant drainage facilities were also constructed for the disposal of interior drainage. The project, with the approved plan of reservoirs, is designed to protect against a flood greater than any of record. The levee and floodwall grades are, at all points, above the maximum stage of the greatest flood of record, that of March 1936. A modification to the project was authorized in October 1982 providing for the raising of the floodwall sections by one foot and the provision of a flood forecasting system. The project is a unit of the comprehensive plan of flood control and other purposes in the Connecticut River Basin and was authorized by the Flood Control Act approved June 28, 1938. The project is complete. Construction of the prior project work was initiated in March 1939 and completed in July 1942 with the exception of foundation treatment along the Westfield River south of Agawam Bridge, which was initiated in May 1947 and completed in November 1947, and relief well and drainage system, which was initiated in August 1952 and completed in July 1953. Local cooperation. Fully complied with. Operations during fiscal year. New work: Tentative sites were selected for installation of flood warning system. Easements for field equipment were initiated. 31. HOUSATONIC RIVER BASIN, CT and MA Authorized improvements in Housatonic River Basin are comprised of seven flood control reservoirs on tributaries of the Naugatuck River, principal tributary of the Housatonic River, and seven local protection projects, five of which are along Naugatuck River, one on Housatonic River and one on Still River. Naugatuck and Housatonic Rivers converge 12 miles above mouth of Housatonic River. A project for emergency snagging and clearing of the Blackberry River, a tributary of the Housatonic River, was authorized under authority contained in Section 208 of the 1954 Flood Control Act. Emergency bank protection projects at Alford, Green River, Massachusetts and at Sheffield, MA, and Salisbury, CT along the Housatonic were authorized under authority provided by Section 14 of the 1948 Flood Control Act. A project for local flood protection along the Housatonic River in Pittsfield, Massachusetts was authorized under authority provided by Section 205 of the 1948 Flood Control Act. (See Table 1-B at end of chapter for Acts authorizing existing project; also Table 1-M on dams and reservoirs and local protection projects for Housatonic River Basin). 31A. BLACK ROCK LAKE, CT Location. Dan:, " on Br~nach IE k about 2 miles upstream from its confluence with Naugatuck River in towns of Thomaston and Watertown, CT. (See Geological Survey map for Thomaston, CT). Existing project. For description of completed improvement and authorizing legislation see Annual Report for 1975. Project is complete. Road relocation completed in November 1967. Contract for construction of dam and appurtenances was awarded in July 1967 and completed in July 1971. Local cooperation. Section 2, Flood Control Act of 1938 applies. However, local interests must establish encroachment lines downstream of dam to permit efficient reservoir operation. State legislation requires establishment of such lines. Operations during fiscal year. Maintenance: Ordinary operation and maintenance activities. 31B. HANCOCK BROOK LAKE, CT Location. Dam is on Hancock Brook in town of Plymouth CT, about 3.4 miles above its confluence with Naugatuck River. (See Geological Survey map for Waterbury, CT). Existing project. For description of completed improvements and authorizing legislation see Annual Report for 1975. Project is complete. Construction of dam and appurtenant structures was initiated in July 1963 and completed in August 1966. Local cooperation. Section 2, Flood Control Act of 1938 applies. However, local interests must establish encroachment lines downstream of dam to permit efficient reservoir operation. State legislation requires establishment of such lines. Operations during fiscal year. Maintenance: Ordinary operation and maintenance activities. 31C. HOP BROOK LAKE, CT Location. Damsite is on Hop Brook in city of Waterbury and towns of Middlebury and Naugatuck, CT about 1.4 miles upstream of confluence of Naugatuck River and Hop Brook. (See Geological Survey map for Waterbury, CT). Existing project. For description of completed improvement and authorizing legislation see Annual Report for 1975. Project is complete. Construction of dam and appurtenant structures was initiated in December 1965 and completed in December 1968. Construction of a public use facility was completed in November 1973. Construction of an additional restroom was completed in 1980. Local cooperation. Section 2, Flood Control Act of 1938 applies. However, local interests must establish encroachment lines downstream of dam to permit efficient reservoir operation. State legislation requires establishment of such lines. Operations during fiscal year. Maintenance: Ordinary operation and maintenance activities. A contract to replace the Intake Tower roof was awarded in April 1985. Five other projects are included in the total contract amount of $23,985. Completion is scheduled for next fiscal year and is expected to amount to $3,245 for the Hop Brook 1 oject. 1-16 NEW ENGLAND DIVISION 31D. HOUSATONIC RIVER, PITTSFIELD, MA Location. The city of Pittsfield is located in Berkshire County, approximately 6 miles east of the Massachusetts- New York border and about 40 miles northwest of Springfield, Massachusetts, where the confluence of the East and West Branch of the Housatonic Rivers form the headwaters of the main stem. Existing project. Supplement the existing 8-foot high by 15-foot wide stone arch culvert under the Penn Central Railroad embankment with a new 15-foot diameter pipe culvert. Construct an improved channel by clear cutting the existing stream bank extending about 2,000 feet upstream from the railroad culvert. (See Table 1-B at end of chapter for Act authorizing existing project). Project is complete. Local cooperation. Fully complied with. Operations during fiscal year. New Work: Administrative closeout of a contract completed in previous fiscal year resulted in expenditure of $17,344 this fiscal year. Final contract amount was $438,662. 31E. NORTHFIELD BROOK LAKE, CT Location. Dam is on Northfield Brook about 1.3 miles upstream from its confluence with Naugatuck River, in town of Thomaston, CT. (See Geological Survey map for Thomaston, CT). Existing project. For description of completed improvement and authorizing legislation see Annual Report for 1975. Project is complete. Construction of dam and appurtenances was initiated in May 1963 and completed in October 1965. Construction of recreation facilities was initiated in November 1966 and completed in August 1967. Local cooperation. Section 2, Flood Control Act of 1938 applies. However, local interests must establish encroachment lines downstream of dam to permit efficient reservoir operation. State legislation requires establishment of such lines. Operations during fiscal year. Maintenance: Ordinary operation and maintenance activities. 31F. THOMASTON DAM, CT Location. On Naugatuck River about 30.4 miles above its junction with Housatonic River and about 1.6 miles north of Thomaston, CT. Reservoir extends upstream about 6.4 miles. (See Geological Survey map for Thomaston, CT). Existing project. For description of completed improvement and authorizing legislation see Annual Report for 1975. Project is complete. Construction of dam and appurtenant works was initiated in May 1958 and completed in November 1960. Local cooperation. Section 3, Flood Control Act of 1944 applies. Operations during fiscal year. Maintenance: Ordinary operation and maintenance activities. A contract to replace the Intake Tower roof was awarded in April 1985. Five other projects are included in the total contract amount of $23,985. Completion is scheduled for next fiscal year and is expected to amount to $2,965. A contract to perform remedial measures for seepage control was awarded in Spetember 1985. The contract will be completed next fiscal year. Contract amount is $200,960. 32. NONEWAUG RIVER, WOODBURY, CT Location. The town of Woodbury is located in western central Connecticut about 14 miles west of Waterbury, at the headwaters of the Pomperaug River. Located in the lower portion of the Housatonic River Basin, the Pomperaug River is formed by the confluence of the Weekeepeemee and Nonewaug Rivers in Woodbury. Existing project. A gabion-type retaining wall along the base of the eroded riverbank with compacted pervious backfill placed behind the wall up to the roadway. Local cooperation. Fully complied with. Operations during fiscal year. New work: Administrative closeout including determination of final quantities resulted in additional expenditures of $18,029 for the contract completed last fiscal year. 33. GULF STREET AND TRUMBULL AVENUE, MILFORD, CT. Location. The city of Milford, is located in the southwest corner of New Haven County, in southwestern Connecticut. The erosion site at Gulf Street is located immediately to the southeast of Milford Harbor and the site at Trumbull Avenue is located immediately to the southwest of Milford Harbor. Existing project. Shoreline protection measures will consist of construction of stone slope protection for the 140 foot long reach of shoreline, roadway and associated utilities. Local cooperation. Provide without cost to the United States all lands, easements, rights-of-way and utility relocations necessary for project construction; hold and save the United States free from damages due to the construction, operation and maintenance of the project, except where such damages are due to the fault or negligence of the United States or its contractors; maintain and operate the project after completion without cost to the United States; assume responsibility for all costs in excess of the Federal cost limitation of $250,000; prevent future encroachment which might interfere with proper functioning of the project. Operations during fiscal year. New work: Contract plans and specifications were completed. Bids were opened in August 1985 but rejected as being excessive. Project will be readvertised early next fiscal year. 1-17 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 34. ISLESBORO (THE NARROWS), ME Location. The town of Islesboro is an island, located in the west-central section of Penobscot Bay about three miles east of Lincolnville and about 30 miles south of Bangor. The island is about 10 miles long and the project is located at the center of the island in a location known as The Narrows. Existing project. Provides for shoreline erosion protection extending along about 325 feet adjacent to Main Road which connects the two halves of the island by placement of stone slope protection. (See Table 1-B at end of chapter for Act authorizing existing project). Project is complete. Local cooperation. Fully complied with. Operations during fiscal year. New work: The contract awarded in previous fiscal year was completed in December 1984. Administrative closeout resulted in additional expenditure of $2,000 for the contract and $4,676 for hired labor costs this fiscal year. Final contract amount was $107,025. 35. JOHNSON BAY, LUBEC, ME Location. The town of Lubec is located in the Maine Eastern Coastal Area. It is the easternmost community in the continental United States, situated on Holmes Bay adjacent to Campobello Island, Canada. It is approximately 25 miles northeast of Machias, ME and 25 miles southeast of Calais, ME. Existing project. Emergency bank protection project provides for protection of eroded shoreline at Johnson Bay adjacent to a section of Commercial Street. Work consists of removal of existing timber bulkhead and its replacement with stone protection, random fill and a gabion wall. Construction along a 300-foot reach of shoreline was completed in June 1980. Following a fire in adjacent timber bulkhead, protection along an additional 125 feet of shoreline was authorized in May 1983. Local cooperation. Fully complied with. Operations during fiscal year. New work: Administrative closeout of the contract completed last fiscal year resulted in additional expenditure of $4,411 for recon reports and other hired labor costs. 36. PORT 5 FACILITY, BRIDGEPORT, CT Location. The Naval Veterans Port 5 Facility is located in the city of Bridgeport in coastal southwestern Connecticut, specifically on a peninsula extending from the right bank at the mouth of Cedar Creek and facing south toward Black Rock Harbor and Long Island Sound. Existing project. Provides for protection of Naval Veterans property against further shoreline erosion from wave action by placement of 250 linear feet of graded riprap slope protection. (See Table 1-B at end of chapter for Acts authorizing existing project). Project is complete. Local cooperation. Fully complied with. Operations during fiscal year. New work: Administrative closeout and computation of final quantities resulted in additional 'expenditure of $21,001 for contract completed last fiscal year 37. MERRIMACK RIVER BASIN, NH AND MA Works covered by comprehensive plan are on Merrimack River and its tributaries in New Hampshire and Massachusetts. Flood Control Act of 1936 authorized construction of a system of flood control reservoirs in Merrimack River Basin for reduction of flood heights in Merrimack Valley. Flood Control Act of 1938 approved general comprehensive plan for flood control and other purposes as approved by Chief of Engineers pursuant to preliminary examinations and surveys authorized by Act of June 22, 1936, and modified project to provide in addition to construction of a system of flood control reservoirs, related flood control works which may be found justified by the Chief of Engineers. All operations pertaining to flood control in Merrimack River Basin are now carried on under and reported under projects for individual units of comprehensive plan referred to above. No further expenditures are contemplated under general project for flood control in Merimack River Basin. For final cost and financial summary, see Annual Report for 1946. A comprehensive plan for development of water resources of the North Nashua River Basin, a principal tributary of the Merrimack River, was authorized by 1966 Flood Control Act substantially in accordance with Senate Document 113, 89th Congress. Plan provides for construction of coordinated system for four reservoirs and three local protection projects for flood protection, water supply, recreation and allied purposes. The 1966 Flood Control Act also authorized construction of Saxonville local protection project substantially in accordance with Senate Document 61, 89th Congress. An emergency bank protection project at Amesbury, MA was authorized under authority provided by Section 14 of the 1948 Flood Control Act. (See Table 1-N at end of chapter for reservoirs and related flood control works included for construction under comprehensive plan). 37A. BLACKWATER DAM, NH Location. Dam is on Blackwater River, NH, 8.2 miles above confluence with Contoocook River and 118.8 miles above mouth of Merrimack River. It is in the town of Webster, just above village of Swetts Mills, 12.5 miles by highway northwest of Concord, NH. (See Geological Survey maps for Penacook and Mount Kearsage, NH). Existing project. For description of completed improvement and authorizing legislation see Annual Report for 1975. Project is complete except for construction of public facilities. Construction of dam and appurtenant works was initiated in May 1940 and completed in November 1941. Local cooperation. Section 2, Flood Control Act of 1938 applies. Operations during fiscal year. Maintenance: Ordinary operation and maintenance activities. 1-18 NEW ENGLAND DIVISION 37B. EDWARD MACDOWELL LAKE, NH Location. Dam is on Nubanusit Brook, a tributary of Contoocook River, one-half mile upstream from village of West Peterborough, NH and 14 miles east of Keene, NH. (See Geological Survey map for Peterboro and Manadnock, NH). Existing project. For description of completed improvement and authorizing legislation see Annual Report for 1975. Project is complete. Construction of dam and appurtenant works was initiated in March 1948 and completed in March 1950. Local cooperation. Section 2, Flood Control Act of 1938 applies. Operations during fiscal year. Maintenance: Ordinary operation and maintenance activities. 37C. FRANKLIN FALLS DAM, NH Location. Dam is on Pemigewasset River, NH main tributary of Merrimack River, and about 2 miles upstream of Franklin, NH. (See Geological Survey maps for Penacook and Holderness, NH). Existing project. For description of completed improvement and authorizing legislation see Annual Report for 1975. Project is complete. Construction of dam and appurtenant works was initiated in November 1939 and completed in October 1943. Local cooperation. Section 2, Flood Control Act of 1938 applies. Operations during fiscal year. Maintenance: Ordinary operation and maintenance activities. A contract awarded in previous fiscal year for removal of debris and sediment was completed in July 1985. Contract earnings this fiscal year were $7,880. A contract awarded in November 1984 for installation of lightning protection at nine dam sites was completed in July 1985. Total contract amount was $84,541 of which $13,853 was for the Franklin Falls Dam installation. A contract for repainting the service bridge was awarded in September 1985. The contract amount is $8,600 37D. HOPKINTON-EVERETT LAKES, NH Location. Hopkinton Dam is on Contoocook River, NH, 17.3 miles above its junction with Merrimack River and about one-half mile upstream from village of West Hopkinton. Everett Dam is on Piscataquog River, NH, 16 miles above its junction with Merrimack River and about 1.3 miles southeast of village of East Weare. Two interconnecting canals were provided to enable the two reservoir areas to function as one. (See Geological Survey map for Hillsboro, NH, and Concord, NH). Existing project. For description of completed improvement and authorizing legislation see Annual Report for 1975. Project is complete. Construction of two dams and appurtenant works was initiated in November 1959 and completed in December 1962. Construction of recreation facilities was initiated in November 1974 and completed in September 1975. Local cooperation. Section 2, Flood Control Act of 1938 applies. Local interests must also bear 50 percent of future recreational development in accordance with 1965 Federal Water Project Recreation Act. Operations during fiscal year. Maintenance: Ordinary operation and maintenance activities. Planning continued for proposed installation of submersible hydropower unit. 38. NEW BEDFORD, FAIRHAVEN, AND ACUSHNET, MA Location. Main harbor barrier is across New Bedford and Fairhaven Harbor in vicinity of Palmer Island. Supplemental dikes and walls are provided in Clark Cove area of New Bedford and Fairhaven. (See Geological survey maps for New Bedford North, New Bedford South, Marion, and Sconticut Neck, MA and National Ocean Survey Charts 13230, 13070 and 13218). Existing project. For description of completed improvement and authorizing legislation see Annual Report for 1975. Project is complete. Construction of barrier and appurtenances was initiated in October 1962 and completed in January 1966. Construction of the pumping station was initiated in October 1962 and completed in June 1964. Local cooperation. Fully complied with. Operations during fiscal year. Maintenance: Operating costs included $119,400 for project operations; $13,700 for administrative activities and $96,800 for performance of the five year periodic inspection. 39. NEW LONDON, CT Location. In the city of New London, CT, about 45 miles southeast of Hartford, CT, and 50 miles southwest of Providence, RI. (See Geological Survey map for New London, CT). Existing project. The hurricane protection project consists of approximately 715 feet of rock-faced earthfill dike and 800 feet of I-walls around the northerly shore of Shaw Cove and the regrading of approximately 21 acres of land along the west shore of the Cove to elevation 12.5 feet mean sea level. Top of dike and floodwalls will be 14.5 feet mean sea level. Appurtenant structures will include a street gate, pressure conduit and a pumping station to discharge interior drainage. Latest estimate (December 1984) for the project is $10,860,000 for construction and $1,140,000 for lands and damages including relocations, a total of $12,000,000 for new work. Total includes local costs of $1,140,000 for lands and relocations and a $2,310,000 cash contribution. (See Table 1-B at end of chapter for Act authorizing existing project). Project is under construction and is approximately 98 percent complete. Local cooperation. Local interests must: (a) Provide lands and rights-of-way for construction; (b) make alterations and relocations; (c) bear 30 percent of construction cost with credit allowed for (a) and (b); (d) hold the United States free from damages; and (e) maintain and operate all works. Assurances have been provided. Operations during fiscal year. New work: Construction of the Part V contract awarded in prior year was com- 1-19 pleted in April 1985. Current contract earnings total $962,918. A contract for the final phase, Part VI, was awarded in January 1985 in the amount of $837,050. This REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 last phase will provide for closure of openings left in new dike construction, while railroad was being realigned. Work on this contract was 72 percent complete at year end. 40. SAINT JOHN RIVER BASIN, ME Comprehensive plan for water resources development within the basin was comprised of the multiple-purpose Dickey and Lincoln School Reservoirs on the upper Saint John River. Projects were authorized by Flood Control Act of 1965 substantially in accordance with plans included in report of Department of Interior and Corps of Engineers dated August 1964 which is supplement to July 1963 report of International Passamaquoddy Tidal Power Project and Upper Saint John River Hydroelectric Power Development. *The Dickey Dam component of the project was deauthorized by Public Law 97-128 on 29 December 1981. Local protection project at Fort Kent authorized by Chief of Engineers on 25 September 1975 in accordance with Section 205 of 1948 Flood Control Act. (See Table 1-F at end of chapter for authorized multiple-purpose projects including power). 41. BAGADUCE RIVER, CASTINE, ME Location. The town of Castine is located along the northeast side of Penobscot Bay in Hancock County about 30 miles south of Bangor and 10 miles east of Belfast. The town forms the southern end of a peninsula that juts into Penobscot Bay where the Penobscot and Bagaduce Rivers converge. The specific project location is at historic Fort Pentagoet along the Bagaduce River at Castine Harbor. Existing project. Provides for protection against further shoreline erosion of the archeological remains of Fort Pentagoet by the placement of stone slope protection along 200 linear feet of shoreline. (See Table 1-B at end of chapter for Act authorizing existing project). Project is complete. Local cooperation. Fully complied with. Operations during fiscal year. New work: Administrative closeout of the work completed in May 1984 resulted in additional expenditure of $5,446. 42. PENOBSCOT RIVER, OLD TOWN, ME Location. The town of Old Town, Maine is located on Indian Island along the Penobscot River in south-central Maine about 14 miles northeast of Bangor, Maine. Existing project. The project consists of modification of two existing earth dike structures. These dikes, located on the left and right banks of Indian Island just beyond the access road bridge are 560 and 700 feet long respectively. The modifications include raising the existing top elevation from about 107 feet to 110 feet and providing rock slope protection at the riverside face. In addition, more adequate interior drainage facilities, consisting of two 18-inch gated drainage lines and two portable pumps to discharge interior runoff will be provided. Project is complete. (See Table 1-B at end of chapter for Acts authorizing existing project). Local cooperation. Fully complied with. Operations during fiscal year. New work: A contract to remedy problems with the drainage structures was awarded in September 1985 in amount of $16,935. Work had not yet started. 43. SEBASTICOOK RIVER, HARTLAND, ME Location. Hartland is situated on the Sebasticook River in Somerset County, approximately 50 miles west of Bangor and 30 miles north of Augusta, ME. Existing project. Provides for a system of earth dikes and floodwalls to protect a major tanning company, removal of the Right Mill Dam and construction of an earth dike across the bypass channel to protect residential and commercial properties, and construction of a water supply pipeline to ensure continued fire protection and process water. (See Table 1-B at end of chapter for authorizing legislation). Project is complete. Local cooperation. Fully complied with. Operations during fiscal year. New work: Administrative closeout of the contract which was completed in November 1983 resulted in additional expenditure of $28,450. Final contract amount was $1,303,363. 44. STAMFORD, CT Location. In Fairfield County on north shore of Long Island Sound, about 30 miles east of New York City and 20 miles southwest of Bridgeport, CT. (See Geological Survey map for Stamford, CT). Existing project. For description of completed improvement see Annual Report for 1974. (See Table 1-B at end of chapter for Act authorizing existing project). Project was completed in 1969. Local interests still owe a substantial amount based on recent claims settlements, including interest payment under the Contract Disputes Act. Local cooperation. Local interests will provide lands, easements, and rights-of-way; make modifications to existing storm drainage system which may be required to obtain full benefits of protection plan, all necessary modifications to existing sanitary sewer facilities required to prevent entry of tidal-waters, and all changes, alterations and additions to or relocations of any buildings and utilities made necessary by construction of project; bear 30 percent of total first cost, estimated at $4,340,000 and consisting of cost items listed above plus a cash contribution estimated at $3,150,000; contribute in cash, in lieu of cost of annual maintenance and operation of tidal portion of East Branch barrier which is to be operated and maintained by the United States, an amount estimated at $880,000; maintain and operate all works after completion with exception of tidal portion of East Branch barrier and aids to navigation; and hold the United States free from damages. Assurances received and cash contributions have been deposited except for $662,000 outstanding which is local share of final claims settlement including interest payment. Operations during fiscal year. Maintenance: Ordinary operation and maintenance activities. Maintenance dredging of the navigation gate area was accomplished. 1-20 NEW ENGLAND DIVISION 45. THAMES RIVER BASIN, CT, RI, AND MA Works covered by this plan are a series of dams and reservoirs on tributaries of Thames River in Massachusetts and Connecticut, within a radius of 45 miles from Norwich, CT, and a channel enlargement on Shetucket River where it discharges into Thames River at Norwich. Flood Control Act of August 18, 1941, approved plan for a system of reservoirs and channel improvements in Thames River Basin in accordance with House Document 885, 76th Congress, 3rd session, and authorized $6 million for initiation and partial accomplishment of project. Flood Control Act of December 22, 1944, authorized completion of approved plan. Flood Control Act of July 14, 1960, authorized project for West Thompson Reservoir, substantially as recommended in Senate Document 41, 86th Congress, 2nd session. (See Table 1-0 at end of chapter on reservoirs and local protection districts, Thames River Basin, for projects comprising approved plan). 45A. BUFFUMVILLE LAKE, MA Location. Dam is on Little River, 1.3 miles above its junction with French River and 8 miles northeast of Southbridge, MA. Reservoir extends upstream about 1.7 miles northerly and 1.9 miles southerly. (See Geological Survey maps for Webster, MA and CT, and Leicester, MA). Existing project. For description of completed improvement and authorizing legislation see Annual Report for 1975. Project is complete. Construction of dam and appurtenant works was initiated in September 1956 and completed 1958. Local cooperation. Section 2, Flood Control Act of 1938 applies. Operations during fiscal year. Maintenance: Ordinary operation and maintenance activities. A contract awarded in November 1984 for installation of lightning protection at nine dam sites was completed in July 1985. Total contract amount was $84,541 of which $5,740 was for the Buffumville Lake installation. A contract to replace the heating system in the Utility Building was awarded in June 1985 and was 96 percent complete at fiscal year end. Contract amount is $14,500. 45B. EAST BRIMFIELD LAKE, MA Location. Dam is on Quinebaug River, 64.5 miles above its confluence with Shetucket River and 1 mile southwest of village of Fiskdale, MA. (See Geological Survey maps for Whales, MA and CT, Southbridge, MA and CT, East Brookfield MA, and Warren, MA). Existing project. For description of completed improvement and authorizing legislation see Annual Report for 1975. Project is complete. Construction of dam and appurtenant works was initiated in May 1958 and completed in June 1960. Local cooperation. Section 2, Flood Control Act of 1938 applies. Operations during fiscal year. Maintenance: Ordinary operation and maintenance activities. 45C. HODGES VILLAGE DAM, MA Location. Dam is on French River, 15 miles above its confluence with Quinebaug River, at Hodges Village in town of Oxford, MA, about 5 miles north of Webster, MA. (See Geological Survey maps for Webster, MA, and CT, Leicester, MA, Worcester South, MA, and Oxford, MA). Existing project. For description of completed improvement and authorizing legislation see Annual Report for 1975. Project is complete. Construction of dam and appurtenant works, initiated in March 1958, was completed in December 1959. Local cooperation. Section 2, Flood Control Act of 1938 applies. Operations during fiscal year. Maintenance: Ordinary operation and maintenance activities. A contract awarded in February 1985 to replace the emergency generator was 10 percent complete ending the fiscal year. Contract amount is $23,820. 45D. MANSFIELD HOLLOW LAKE, CT Location. Dam is at Mansfield Hollow, CT, on Natchaug River, 5.3 miles above its confluence with Willimantic River. It is 4 miles northeast of city of Willimantic, CT. (See Geological Survey maps for Spring Hill and Willimantic, CT). Existing project. For description of completed improvement and authorizing legislation see Annual Report for 1975. Project is complete. Construction of dam, initiated in 1949, was completed in May 1952. Local cooperation. Section 2, Flood Control Act of 1938 applies. Operations during fiscal year. Maintenance: Ordinary operation and maintenance activities. A contract to replace the Control House roof was awarded in April 1985. Five other projects are included in the total contract amount of $23,985. Completion is scheduled for next fiscal year and is expected to amount to $4,230 for the Mansfield Hollow project. 45E. WEST THOMPSON LAKE, CT Location. Dam is on Quinebaug River in town of Thompson, CT. Site is in village of West Thompson, 2 miles upstream from city of Putnam, CT. (See Geological Survey map for Putnam, CT). Existing project. For description of completed improvement and authorizing legislation see Annual Report for 1975. Project is complete. Construction of dam, road relocation, and appurtenances was initiated in August 1963 and completed in October 1965. Initial phase of recreation facilities was completed in May 1976. Local cooperation. Section 2, Flood Control Act of 1938 applies. Operations during fiscal year. Maintenance: Ordinary operation and maintenance activities. A contract awarded in May 1985 for miscellaneous repairs to the service bridge was 22 percent completed at fiscal year end. Contract amount is $15,875. 1-21 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 45F. WESTVILLE LAKE, MA Location. Dam is on Quinebaug River, 56.7 miles above its confluence with Shetucket River, in towns of Sturbridge and Southbridge, MA, and 1.3 miles west of center of Southbridge. (See Geological Survey maps for Southbridge, MA and RI, and East Brookfield, MA). Existing project. For description of completed improvement and authorizing legislation see Annual Report for 1975. Project is complete. Construction of dam and appurtenant works was initiated in April 1960 and completed in August 1962. Local cooperation. Section 2, Flood Control Act of 1938 applies. Operations during fiscal year. Maintenance: Ordinary operation and maintenance activities. A contract awarded in March 1985 to replace the emergency generator was 95 percent complete at fiscal year end. Contract amount is $19,222. A contract to replace the Control House roof was awarded in April 1985. Five other projects are included in the total contract amount of $23,985. Completion is scheduled for next fiscal year and is expected to amount to $4,785. A contract to replace the gatehouse furnace and utility building boiler was awarded in May 1985 and was 96 percent complete at fiscal year end. Contract amount is $10,900. A contract awarded in August 1985 to repair the concrete of Intake Tower and access stairway was completed in September 1985 at a cost of $4,475. 46. INSPECTION OF COMPLETED FLOOD CONTROL PROJECTS In accordance with provisions of the Flood Control Act of 1936, as amended, local flood protection works constructed with Federal funds are transferred to local interests to operate and maintain. To insure compliance with regulations prescribed for their operation and maintenance, regular inspections of the following projects were made during the fiscal year: CONNECTICUT: October 1984 and May 1985 - Ansonia, Danbury, Derby, East Hartford, Hartford, New London, Pawcatuck, Stamford; April 1985 - Colchester/ East Hampton, North Canaan, Salisbury, Torrington, Winsted; May 1985 - East Branch, Hall Meadow, Mad River, New Fairfield -Squantz Pond, Norwalk, Sucker Brook, Waterbury, Wethersfield. MAINE: May 1985 - Beals, Blaine, Cherryfield, Fort Kent, Harpswell, Hartland, Indian Island, Islesboro, Lubec, Whiting. MASSACHUSETTS: October 1984 and April 1985 - Gardner, Haverhill, Lowell; October 1984 and May 1985 - Charles River Dam, Chicopee, Fitchburg, Holyoke, Northampton, Saxonville, Springfield, West Springfield; April 1985 - Alford, Canton, Lancaster, Lee, Pittsfield, Scituate, Sheffield, Three Rivers, West Warren, Worcester; May 1985 - Amesbury, Blackstone, Haywood Creek- Braintree, Haywood Creek-Quincy, Huntington, Quincy - Island Avenue, Ware, Weymouth-Braintree. NEW HAMPSHIRE: October 1984 - Keene; October 1984 and May 1985 - Nashua; April 1985 - Lincoln, Shelburne, Wilton; May 1985 - Charlestown, Farmington, North Stratford, West Stewartstown. RHODE ISLAND: October 1984 and May 1985 - Upper and Lower Woonsocket; November 1984 - Fox Point Hurricane Barrier. VERMONT: April 1985 - Weston. 47. FLOOD CONTROL RESERVOIR OPERATIONS A coordinated system of reservoirs, many of which are multipurpose in nature and all containing significant amounts of storage for flood control purposes, has been established in five major flood producing basins in New England. During periods of floodflows, regulation of reservoirs is fully coordinated within each basin dependent upon upon its location in the watershed, its available storage capacity and origin of flood. In addition to flood control releases, water supply, flow augmentation and hydropower, releases were made from selected reservoirs. There were no freshwater flooding events in New England in FY 1985, hence no benefits associated with Corps' reservoirs were realized. Connecticut River Basin There was no significant flooding in the Connecticut River Basin; no appreciable storage was experienced at any of the Corps' reservoirs in the Basin during FY 1985. Regulation for canoe activities occurred at Ball Mountain and Townshend - October 1984 and May 1985; Otter Brook - March and April 1985; Knightville and Littleville - April 1985; Birch Hill and Tully - April 1985. Water supply and fisheries releases were made throughout the year from Colebrook Lake. A new hydropower plant began operation downstream of North Hartland in July 1985. This plant will essentially control discharges from North Hartland during non-flood periods for hydropower generation. A set of override controls is located in the North Hartland gatehouse, allowing the Corps to interrupt generating activities anytime it is considered necessary to regulate the project for flood control purposes. Merrimack River Basin Peak storages at all reservoirs in the Merrimack River Basin were insignificant because of the absence of any flooding in the basin during FY 1985. Releases from the Blackwater Dam were made in April to accommodate canoeists. Thames River Basin No appreciable storages were experienced at reservoirs in the Thames River Basin in FY 1985. East Brimfield and Westville were regulated in April to accommodate a combination river cleanup and canoe race in April; Mansfield Hollow was operated for canoe races in June and September and the West Thompson pool level was raised on several occasions for AKC retriever trials. There were no releases for flow augmentation from East Brimfield Lake during FY 1985. Housatonic River Basin There were no significant storages at any of the Corps' reservoirs in the Housatonic River Basin in FY 1985. 1-22 NEW ENGLAND DIVISION Blackstone River Basin No important flood control storages were experienced at West Hill Dam during FY 1985. 48. HURRICANE BARRIER OPERATIONS Four hurricane barriers situated along the southern coast of New England protect coastal communities from tidal flooding associated with hurricanes or severe coastal storms. In addition, the Corps is presently constructing a hurricane protection project at New London, Connecticut. The Corps operates the navigational elements of the Stamford, Connecticut and New Bedford-Fairhaven, Massachusetts barriers. The Fox Point, Rhode Island and Pawcatuck, Connecticut barriers are operated by the local communities. A brief resume of operations for the fiscal year follows: Stamford Barrier. The barrier gates were operated on 6 occasions for coastal storms and once for Hurricane Gloria in September. There were no benefits associated with the coastal storm operations; however, the barrier prevented $225,000 in damages during Hurricane Gloria. New Bedford-Fairhaven Barrier. The New Bedford- Fairhaven Barrier was operated 3 times for coastal storms and once during Hurricane Gloria. No damages were prevented as a result of the 3 coastal storm operations; however, $200,000 in benefits were realized as a result of the barrier operation during Hurricane Gloria in September. Fox Point.During FY 1985, the Fox Point Barrier was operated for Hurricane Gloria; benefits of $175,000 were experienced as a result of the operation during this event. New London. Although still under construction, the New London Hurricane Barrier prevented $25,000 in damages during Hurricane Gloria. 49. OTHER AUTHORIZED FLOOD CONTROL PROJECTS (See Table 1-E at end of chapter). 50. FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION Flood control activities pursuant to Section 205, Public Law 858, 80th Congress, as amended (preauthorization). (See Table 1-J at end of chapter). Snagging and clearing activities pursuant to Section 208 of the 1954 Flood Control Act. Exeter River, NH $5,500 Housatonic River, 5,500 Stockbridge, MA Konkapot River, 6,217 North Canaan, CT Konkapot River, MA 5,500 Moose River, 5,400 St. Johnsbury, VT Suncook River, NH 3,500 1-23 Emergency Bank Protection activities pursuant to Section 14 of the 1946 Flood Control Act. Fiscal year costs were as follows: Bagaduce River, Castine, ME $5,446 (See Section 41 of Text) Blackstone River, Millbury, MA 84,277 (See Section 29A of Text) Boothbay Harbor, ME 4,000 Camp Ellis, Saco, ME 7,500 Clear River, Burrillsville, RI 40,704 (See Section 29B of Text) Connecticut Harbor, 5,000 Chesterfield, NH Connecticut River, Hatfield, ME 15,000 Connecticut River, 6,545 North Stratford, NH Covered Bridge, Sheffield, MA 660 Factory Brook, Middlefield, MA 7,104 Gulf Street-Fort Trumbull Beach 38,921 Milford, CT (See Section 33 of Text) Housatonic River, Salibury, CT 6,500 Islesboro Island, ME 6,676 (See Section 34 of Text) Johnson Bay, Lubec, ME 4,411 (See Section 35 of Text) Manhan River, Easthampton, MA 7,500 Marginal Way, Ogunquit, ME 13,081 Millbrook-Brownville, VT 10,694 Nonewaug River, Woodbury, CT 18,029 (See Section 32 of Text) Port 5 Facility, Bridgeport, CT 21,001 (See Section 36 of Text) Sand Cove, Gouldsboro, ME 2,299 Sandy River, Farmington, ME 7,500 Sebasticook River, Pittsfield, ME 5,487 South River, Conway, MA 7,735 Town River Bay, Quincy, MA 7,500 Village of Saxtons, VT 20,184 (See Section 30Q of Text) West Branch, Westfield River, 245 Huntington, MA White River, Royalton, VT 6,500 Emergency flood control activities - repair, flood fighting, and rescue work (Public Law 99, 84th Cong., and antecedent legislation). Federal costs for fiscal year were $110,040 for disaster preparedness and $47,782 for rehabilitation work in Farmington, NH. Expenditures for rehabilitation work conducted in fiscal year 1984 in Westfield, MA were reduced by $5,512 in final adjustment. Streambank Erosion Control Evaluation and Demonstration Act of 1974 as amended in 1976 (Section 32 of the Water Resources Development Act of 1974. P.L. 93-251). There were no fiscal year costs for demonstration project proposals. Total costs to 30 September 1985 were $1,204,996. REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 51. DEAUTHORIZED PROJECTS (See Table 1-G at end of chapter). General Investigations 52. SURVEYS Costs for the fiscal year for surveys from regular funds were $1,826,014 of which $186,481 was for five navigation studies; $374,572 for four flood damage prevention studies; $95,211 for one special study; $481,333 for three comprehensive studies; $363,923 for review of five completed or deferred projects; $323,618 for coordination studies and $876 for one supplemental pre-authorization study. 53. COLLECTION AND STUDY OF BASIC DATA The Division Engineer is the U.S. member on Saint Croix River Board of Control. Annual inspections are made of conditions on the Saint Croix River and a continuing program of compilation of basic hydrologic information is carried out. Division Engineer's representatives during the past year kept closely in touch with developments in the basin and cooperated with their Canadian counterparts assisting in development of basins' resources. Total costs for the fiscal year were $7,630. Total costs to 30 September 1985 were $164,534. Flood plain studies comprise compilation and dissemination, upon responsible local request, of information on floods and potential flood damages, including identification of areas subject to inundation by floods of various magnitudes and frequencies, and general criteria for guidance in use of flood plain area; and engineering advice to local interests for their use in planning to ameliorate flood hazard. Total costs for the fiscal year were $188,684. Total costs to 30 September 1985 $4,752,400. 54. CONTINUATION OF PLANNING AND ENGINEERING Total costs for continuation of Planning and Engineering were $579,747 of which $237,073 was for channels and harbors and $342,674 for local protection. The channels and harbor study was at Portsmouth, New Hampshire. The continuing local protection studies were for Town Brook in Quincy, Massachusetts and for Roughans Point in Revere, Massachusetts. 55. ADVANCE ENGINEERING AND DESIGN Advance Engineering and design costs were $195,093 for the beach erosion control project at Revere Beach, Massachusetts. 1-24 NEW ENGLAND DIVISION TABLE 1-A COST AND FINANCIAL STATEMENT See Total Cost Section to In Text Project Funding FY82 FY83 FY84 FY85 Sept. 30, 1985 1. Aquatic Plant Control 2. Black Rock Harbor, CT 3. Buttermilk Bay Channel, MA Contributed Funds-Required) 4. Cape Cod Canal, MA 5. Clinton Harbor, CT 6. Connecticut River below Hartford, CT 7. Green Harbor, MA (Contributed Funds) 8. Hyannis Harbor, MA 9. Jonesport Harbor, ME 10. Kennebunk River, ME New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Contrib. Cost New Work Approp. Cost Maint. Approp. Cost Minor rehab. Approp. Cost Major rehab. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost Major rehab. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Contrib. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost New Work Approp. Cost Maint. Approp. Cost 5,000 9,793 10,000 2,093 - 1,426,000 - 1,244,713 20,386 18,534 386 100,000 22,793 4,816,821 3,965,408 7,475,000 7,426,768 215,100 222,200 55,000 29,799 95,000 14,363 60,500 -9,000 75,308 4,541,756 5,043,968 874,000 930,549 -6,000 -2,250 7,995 79,359 242,071 13,229 40,823 30,000 94,094 8,823 63,323 40,000 36,134 215,496 211,628 22,900 1,528,259 22,180 1,508,964 -550 -550 23,495 40,038 6,000 163,855 163,855 183,70928 183,70928 69,323 69,323 - - 32,786,750495 - - 32,786,2194,5 4,865,718 6,469,630 80,603,413 5,311,711 6,765,682 80,325,045 - 14,269 95,277 83,414 906,650 2,011,524 1,775,602 815,033 695,246 3,387,864 34,392 31,535 1,852 99,400 166,710 1-25 305,561 272,598 12,946 12,946 25,000 8,160 61,740 57,095 154,525 192,598 18,398 18,398 25,000 13,889 70,528 64,640 - 390,677 - 390,677 - 26,609,000 168 26,609,000 - 104,957 - 104,957 144,508 946,619 156,372 946,619 - 1,541,1851o,11 - 1,541,1851o,11 177,567 14,614,50912 179,124 14,614,49112 - 60,000 - 60,000 - 254,512 - 254,512 254,900 1,707,183 264,505 1,696,147 357,454 339,813 40,000 3,725 168,000 158,342 484,4991 484,499 626,0112 608,3702 305,000 240,162 350,33427 350,33427 271,165 1,217,322 281,454 1,217,023 TABLE 1-A (Continued) REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 COST AND FINANCIAL STATEMENT See Total Cost Section to In Text Project Funding FY82 FY83 FY84 FY85 Sept. 30, 1985 11. Mianus River, CT 12. New London Harbor, CT 13. Newburyport Harbor, MA 14. Penobscot River, ME 15. Point Judith Pond and Harbor of Refuge, RI 16. Portland Harbor, ME 17. Provincetown Harbor, MA 18. Royal River, ME (Contributed Funds-Required) 19. Saco River, ME New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost Major rehab. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost Major Rehab. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Contrib. Cost New Work Approp. Cost Maint. Approp. Cost 422 422 17,299 17,299 56,026 54,532 773,584 772,839 425,600 427,094 132,43531 132,43531 660,222 659,390 638,77440 638,77440 176,641 1,228,259 177,322 1,228,195 565,225 565,225 8,066 7,776 697,825 680,448 - 8,132 - 8,132 31,530 2,463,926 31,530 722,522 2,328,445 2,328,942 -5,872 -6,880 -19,652 6,305 293,060 225,760 -125,695 612,029 450,608 450,729 770,730 628,243 1,258 1,258 240,000 34,785 40,464 40,714 31,116 31,116 15,000 211,293 316 21,243 4,060,552 24,225 4,058,189 - 1,415,524 - 1,415,524 - 501,020 - 501,020 -66,800 837,447 500 837,447 - 2,714,51022 - 2,714,51022 -358,831 3,413,939 644,031 3,413,121 - 1,926,000 - 1,926,000 - 9,588,710s15 - 9,588,7101s 58,500 7,903,331 59,387 7,903,331 - 3,548,95438 - 3,548,95438 -15,400 1,053,966 127,087 1,053,966 223,772 204,072 336,70414 336,704' 4 511,2623 491,5623 49,562 49,562 -5,000 8,194 9,891 9,891 - 1,064,983 - 1,064,983 59,880 1,566,142 50,176 1,556,438 1-26 TABLE 1-A (Continued) NEW ENGLAND DIVISION COST AND FINANCIAL STATEMENT See Total Cost Section to In Text Project Stonington Harbor, ME 25. Revere Beach, MA (Contributed Funds) 29A. Blackstone River, Millbury, MA 29B. Clear River, Burrillville, RI 29C. Pawtuxet River, Warwick, RI 29D. West Hill Danm, MA 29E. Charles River (Natural Valley Storage Areas), MA 30A. Ball Mountain Lake, VT 30B. Barre Falls Dam, MA 30C. Beaver Brook, Keene, NH 30D. Birch Hill Dam, MA (Contributed Funds) 30E. Colebrook River Lake, CT FY82 FY83 FY84 FY85 Sept. 30, 1985 20. Funding New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost New Work Contrib. Cost New Work Approp. Cost New Work Approp. Cost New Work Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Contrib. Cost New Work Approp. Cost Maint. Approp. Cost 55,000 48,040 -13,288 762 80,000 89,094 187,000 185,689 1,100,000 1,119,443 221,000 60,336 254,000 270,347 247,200 254,804 110,000 89,246 298,000 239,837 176,000 219,707 700,000 124,499 770,000 635,554 150,650 168,669 615,000 567,600 16,000 176,430 256,800 255,273 243,000 243,211 65,000 87,689 278,400 328,596 111,500 129,544 1-27 580,883 47,500 34,149 1,015,000 1,128,982 182,000 171,654 125,000 118,167 132,000 120,973 4,000 3,872 354,000 341,628 252,000 240,017 50,000 22,795 230,000 204,543 107,000 104,747 - 898,500 3,223 898,500 2,830 2,830 2,830 2,830 230,000 483,71221 195,093 448,80521 - 142,965 - 142,965 202,500 250,000 84,277 118,426 50,000 50,000 40,704 40,704 1,375,000 3,300,000 1,151,872 3,038,000 - 2,306,90239 - 2,306,90239 212,700 2,460,234 196,959 2,434,066 140,000 8,415,000 177,899 8,377,316 144,000 276,000 149,099 270,072 336 11,039,2986 698 11,039,29845 588,800 4,871,739 456,093 4,715,385 - 1,967,819 - 1,967,819 416,600 3,281,627 378,002 3,216,322 236,000 511,000 223,473 463,874 - 4,815,67941 - 4,815,67941 230,800 3,550,727 261,717 3,543,408 - 32,00030 - 32,00080 - 14,263,971 -- 14,263,971 150,900 1,809,444 159,338 1,803,188 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 1-A (Continued) COST AND FINANCIAL STATEMENT See Total Cost Section to In Text Project Funding FY82 FY83 FY84 FY85 Sept. 30, 1985 30F. Conant Brook New Work Dam, MA Approp. - - - 30G. Knightville Dam, MA 30H. Littleville Lake, MA 301. North Hartland Lake, VT 30J. North Springfield Lake, VT 30K. Otter Brook Lake, NH 30L. Park River, Hartford, CT (Other Contributed Funds) 30M. Surry Mountain Lake, NH 30N. Townsend Lake, VT 300. Tully Lake, MA (Contributed Funds) Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost New Work Contrib. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Contrib. Cost 58,000 54,872 606,100 622,331 221,800 213,191 256,000 272,950 296,000 313,424 185,000 48,856 302,000 299,122 281,919 864,059 580,000 558,862 422,000 471,918 291,000 265,168 48,000 54,350 231,200 305,915 222,000 216,117 229,600 232,025 270,300 280,799 13,000 148,619 352,300 341,681 75,000 67,401 364,000 369,268 235,000 241,188 244,500 256,745 82,000 76,250 588,000 465,260 237,000 251,701 301,000 281,472 312,000 309,613 2,000 2,525 339,000 321,897 225,000 233,110 394,000 403,328 289,000 266,179 285,000 279,572 1-28 - 2,950,530 - 2,950,530 59,000 954,680 55,768 945,536 - 3,415,64044 - 3,415,64044 349,400 4,632,904 490,983 4,617,271 - 7,013,412 - 7,013,412 248,800 2,745,891 250,330 2,738,515 - 7,312,22518 - 7,312,22518 329,700 3,493,815 325,812 3,461,405 - 6,831,52625 - 6,831,52625 818,000 5,121,097 715,240 4,996,679 - 4,360,44843 - 4,360,44843 401,300 3,363,614 333,319 3,251,237 - 60,176,919 54,889 60,164,740 13,408 259,408 - 234,993 - 2,833,61033 - 2,833,61033 391,300 4,213,443 373,176 4,175,372 - 7,398,4 1320 - 7,398,41320 673,900 4,604,471 569,734 4,460,011 - 1,666,7527 - 1,666,7527 371,900 3,286,986 297,333 3,189,683 - 40,00030 - 40,00030 TABLE 1-A (Continued) NEW ENGLAND DIVISION COST AND FINANCIAL STATEMENT See Total Cost Section to In Text Project Funding FY82 FY83 FY84 FY85 Sept. 30, 1985 30P. Union Village New Work Dam, VT Approp. - - - 30,000 204,700 35,444 241,811 - 127,500 - 35,842 - 215,000 - 58,510 30Q. Village of Saxtons, VT 30R. West Springfield, MA (Contributed Funds) 31A. Black Rock Lake, CT 31B. Hancock Brook Lake, CT 31C. Hop Brook Lake, CT 31D. Housatonic River, Pittsfield, MA 31E. Northfield Brook Lake, CT 31F. Thomaston Dam, CT 32. Nonewaug River, Woodbury, CT 33. Gulf Street, Fort Trumbull Beach, Milford, CT 34. Islesboro (The Narrows), ME 35. Johnson Bay, Lubec, ME 36. Port 5 Facility, Bridgeport, CT Cost Maint. Approp. Cost New Work Approp. Cost New Work Approp. Cost New Work Contrib. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost New Work Approp. Cost New Work Approp. Cost New Work Approp. Cost New Work Approp. Cost 162,500 163,710 61,000 56,261 375,500 432,924 460,000 72,045 20,000 7,039 81,000 82,780 279,500 279,613 28 23 293,000 284,628 84,474 112,162 13,000 181,000 178,239 79,000 77,599 382,000 379,251 84,000 137,008 129,000 117,350 254,000 236,598 50,000 177,186 131,976 -17,000 39,861 207,000 171,445 1-29 192,200 186,989 61,500 65,798 307,550 312,547 67,000 384,636 12,961 122,500 118,349 237,000 241,314 187,500 27,285 195,500 26,848 75,000 13,728 32,500 27,705 - 4,095,16017 - 4,095,16017 250,700 3,309,556 243,528 3,274,254 13,000 140,500 20,184 140,500 - 215,000 12,169 182,841 - 13,000 - 8,182,300 - 8,182,300 162,000 1,979,609 170,351 1,977,770 - 4,178,911 - 4,178,911 94,400 991,649 96,252 991,576 - 6,151,56232 - 6,151,56282 375,400 3,399,885 321,003 3,323,253 - 739,003 17,344 739,003 - 2,850,51226 - 2,850,51226 156,800 1,447,711 151,456 1,422,623 - 14,282,112 - 14,282,112 588,500 3,949,767 405,293 3,739,014 -15,000 222,500 18,029 222,500 48,500 48,500 38,921 38,921 -30,000 165,500 6,676 165,500 - 163,082 4,411 163,082 -12,000 227,500 21,001 220,151 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 1-A (Continued) COST AND FINANCIAL STATEMENT See Total Cost Section to In Text Project Funding FY82 FY83 FY84 FY85 Sept. 30, 1985 37A. Blackwater Dam, NH 37B. Edward MacDowell Lake, NH 37C. Franklin Falls Dam, NH 37D. Hopkinton-Everett Lakes, NH 38. New Bedford, Fairhaven, and Acushnet, MA (Contributed Funds) 39. New London, CT (Contributed Funds-Required) (Other Contributed Funds) 41. Bagaduce River, Castine, ME 42. Penobscot River, Old Town, ME 43. Sebasticook River, Hartland, ME 44. Stamford, CT (Contributed Funds-Required) (Other Contributed Funds) New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Contrib. Cost New Work Approp. Cost New Work Contrib. Cost New Work Contrib. Cost New Work Approp. Cost New Work Approp. Cost New Work Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Contrib. Cost New Work Contrib. Cost 167,000 153,854 199,000 187,080 364,000 277,490 507,000 517,152 527,000 444,272 224,000 234,591 171,600 169,835 438,000 434,604 533,900 564,139 509,000 475,213 410,000 1,160,000 523,521 1,018,945 250,000 573,505 83,894 140,000 165,095 36,008 - 132,500 - 28,359 573,475 900,000 171,361 1,242,753 - 121,000 2,023 120,960 118,000 341,000 121,346 150,264 167,000 165,282 - 1,319,74637 - 1,319,74637 193,200 2,602,985 197,527 2,602,051 - 2,014,25336 - 2,014,25336 205,000 232,600 3,094,392 207,435 229,583 3,076,126 325,000 336,139 429,000 428,898 202,000 330,791 825,000 625,839 300,000 93,884 84,750 58,208 95,694 260,000 284,927 190,000 364,097 - 7,950,48735 - 7,950,48735 562,100 5,027,137 563,698 4,940,375 - 21,452,44034 - 21,452,44034 568,800 5,676,040 489,672 5,578,408 - 11,510,088 - 11,510,088 227,750 3,439,864 230,766 3,437,500 - 6,513,76329 - 6,513,76329 350,000 9,272,046 540,331 9,119,129 65,000 2,255,00019 218,246 2,196,38219 37,640 -3,000 5,447 40,000 4,923 215,750 215,750 129,500 129,500 188,045 152,968 -6,000 1,857,475 28,450 1,857,475 - 9,911,300 - 9,900,618 210,000 2,302,372 207,808 2,265,049 - 3,367,97024 - 3,367,45324 - 210,000 - 209,969 1-30 NEW ENGLAND DIVISION TABLE 1-A (Continued) COST AND FINANCIAL STATEMENT See Total Cost Section to In Text Project Funding FY82 FY83 FY84 FY85 Sept. 30, 1985 45A. Buffumville Lake, New Work MA Approp. - - - - 2,998,6039 Cost - - - - 2,998,6039 Maint. Approp. 207,000 239,000 297,000 312,400 2,846,322 Cost 182,146 253,141 305,796 292,103 2,823,002 45B. East Brimfield New Work Lake, MA Approp. - - - - 7,057,0438 Cost - - - - 7,057,0438 Maint. Approp. 166,000 170,000 164,000 191,100 2,305,683 Cost 160,056 179,248 137,426 208,938 2,295,054 45C. Hodges Village New Work Dam, MA Approp. - - - 195 4,461,26842 Cost - - - 195 4,461,26842 Maint. Approp. 168,000 225,300 308,000 350,800 2,712,598 Cost 162,332 203,446 291,612 350,711 2,664,676 45D. Mansfield Hollow New Work Lake, CT Approp. - - - - 6,447,16416 Cost - - - - 6,447,16416 Maint. Approp. 206,000 203,000 207,000 239,500 2,912,797 Cost 179,166 228,848 204,938 244,183 2,911,300 45E. West Thompson New Work Lake, CT Approp. 25,000 3,000 - - 7,001,22046 Cost 7,812 19,708 480 - 7,001,22023 Maint. Approp. 257,000 477,800 320,000 317,300 2,933,998 Cost 252,752 434,456 376,345 301,293 2,910,224 45F. Westville Lake, New Work MA Approp. - - - - 5,684,68313 Cost - - - - 5,684,68313 Maint. Approp. 229,000 213,000 243,000 373,300 2,687,096 Cost 224,705 199,653 199,852 377,556 2,626,901 1 Excludes $103,001 expended from Contributed Funds. 2 Excludes $129,757 expended for rehabilitation; breakwater repaired in 1961. 3 Excludes $20,000 expended from Contributed Funds, Other. 4 Includes $6,138,157 from Public Works Funds and $4,849,740 from Emergency Relief Funds. Excludes $115,432 Contributed Funds. 5 Includes $389,929 Code 711 funds and $412,988 Code 713 funds. 6 Includes $503,724 Code 711 funds. 7 Includes $3,695 Code 711 funds and $115,138 Code 713 funds. 8 Includes $208,100 Code 711 funds. 9 Includes $71,943 Code 711 funds. 10 Includes $287,374 for previous projects. Excludes $130,410 Contributed Funds. 11 Excludes $9,000 for subproject "Eightmile River, CT." 12 Includes $366,348 for previous projects. 13 Includes $67,667 Code 711 funds. 14 Excludes $18,000 expended from Contributed Funds, Other. 15 Includes $692,435 for previous projects. 16 Includes $68,717 Code 711 funds. 17 Includes $84,462 Code 711 funds. 18 Includes $228,236 Code 711 funds. 19 Excludes $22,517 expended to date for land condemnations. 20 Includes $245,168 Code 711 funds. 21 Excludes $73,800 for previous project. 22 Includes $12,000 for previous project and excludes $17,587 expended for new work from Contributed Funds. 23 Includes $314,281 Code 711 funds. 24 Cash for construction only. Excludes $199,410 expended to date for land condemnations. 25 Includes $59,536 Code 711 funds. 26 Includes $20,000 Code 711 funds. 27 Includes $88,917 expended Contributed Funds. 28 Includes $35,214 from previous project. 29 Cash for construction only. Excludes $164,020 expended to date for land condemnation. 30 Recreational Cost Sharing. 31 Excludes $46,500 expended Contributed Funds. 32 Includes $143,538 Code 711 funds. 33 Includes $470,077 Code 711 funds. 34 Includes $179,728 Code 711 funds. 3 Includes $4,671 Code 711 funds. 36 Includes $6,432 Code 711 funds. 37 Includes $2,881 Code 711 funds. 38 Includes $215,801 for previous project. Excludes $760,000 Contributed Funds expended. 39 Includes $18,310 Code 711 funds. 40 Includes $40,800 for previous project. 41 Includes $618,469 Code 711 funds and $32,000 Code 713 funds. 42 Includes $6,255 Code 711 funds and $40,158 Code 713 funds. 43 Includes $364,688 Code 711 funds. 4 Includes $199,304 Code 711 funds. 45 Includes $503,362 Code 711 funds. 46 Includes $319,503 Code 711 funds. 1-31 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 1-B AUTHORIZING LEGISLATION Acts Work Authorized Documents July 3, 1958 Oct. 23, 1962 Oct. 27, 1965 July 3, 1930 June 30, 1948 July 14, 1960, as amended Jan. 21, 1927 (Sec. 2) Included in Public Works Administration program, Sept. 6, 1933 June 26, 1934 (Permanent Appropriations Repeal Act) Included in Public Works Administration program Apr. 29, 1935 Included in Emergency Relief Program. May 28, 1935 Aug. 30, 1935 Mar. 2, 1945 July 3, 1958 Aug. 2, 1882 Mar. 2, 1945 June 10, 1872 Mar. 3, 1881 June 25, 1910 Feb. 27, 1911 Mar. 2, 1919 Aug. 30, 1935 May 24, 1937 Mar. 2, 1945 May 17, 19503 July 14, 1960, as amended AQUATIC PLANT CONTROL (See Section 1 of Text). Control and progressive eradication of obnoxious Aquatic Plant growths from the waters and streams in the U.S. Research and planning costs to be borne by U.S. Provided for continued research. BLACK ROCK HARBOR, CT (See Section 2 of Text). Black Rock Harbor 18 feet deep and 100 to 200 feet wide from the 18-foot contour in harbor to the heads of both branches of Cedar Creek, about 2.4 miles. BUTTERMILK BAY CHANNEL, MA (See Section 3 of Text). A channel 100 feet wide and 7 feet deep at mean low water through the sand bar across the channel. Channel extension 2,500 feet long, dredging only upper 300 feet. Mark jurisdictional channel in lower 2,200 feet of channel. Channel to be 80 feet wide with a depth of -6 feet at MLW. CAPE COD CANAL, MA. (See Section 4 of Text). Purchase canal from Boston, Cape Cod & New York Canal Co., in accordance with contract dated July 29, 1921, executed by that company. Construct 3 bridges and widen canal to 250 feet Operation and care of works of improvement provided for the funds from War Department appropriations for rivers and harbors. Construct a mooring basin. Dredging and bank protection. Existing project for main canal adopted. 15-foot channel and turning basin in Onset Bay. Extend East Boat Basin for an area of about 4.3 acres to a depth of 8 feet. CLINTON HARBOR, CT (See Section 5 of Text) Maintenance of a stone dike closing a breach in sandy peninsula which separates river from outer harbor. 8-foot channel and anchorage. CONNECTICUT RIVER BELOW HARTFORD, CT (See Section 6 of Text). Jetties at the mouth The Hartford dike. Channel and turning basin in Eightmile River. Present project dimensions of channel over Saybrook bar. Dikes, training walls, and revetments. Present project dimensions of channel and additional dikes, training walls, revetments, and accessory works. Park River declared nonnavigable. Channel and anchorages, North Cove, Old Saybrook Channel, anchorage, and turning basin, Eightmile River. Channel and anchorage in Essex Cove. Channel and anchorage in Wethersfield Cove. H. Doc. 37, 85th Cong., 1st sess. Public Law 87-874, 87th Cong. H. Doc. 251, 89th Cong. H. Doc. 281, 71st Cong., 2nd sess. H. Doc. 552, 80th Cong., 2nd sess. P.L. 86-645, Sec. 107. Authorized by Chief of Engineers, April 7, 1983. H. Doc. 139, 67th Cong., 2nd sess. H. Doc. 795, 71st. Cong., 3rd sess. Do. Do. Do. Rivers and Harbor Committee Doc. 15, 74th Cong., 1st sess. H. Doc. 431, 77th Cong., 1st sess. H. Doc. 168, 85th Cong., 1st sess. S. Ex. Doc. 84, 47th Cong., 1st sess. H. Doc. 240, 76th Cong., 1st sess. Present project dimensions approved by Chief of Engineers, Dec. 22, 1887. Present project dimensions authorized by Chief of Engineers in 1889. H. Doc. 327, 60th Cong., 1st sess. H. Doc. 1294, 61st. Cong.,3rd sess. H. Doc. 132, 65th Cong., 1st sess.4 H. Doc. 49, 73rd Cong., 1st sess. Ltr. Sec. War, Apr. 21, 1937. H. Doc. 368, 76th Cong., 1st sess.4 H. Doc. 666, 80th Cong., 2nd sess. 4 P.L. 86-645, Sec. 107, Authorized by Chief of Engineers, October 18, 1961. P.L. 86-645, Sec. 107, Authorized by Chief of Engineers, Nov. 15, 1960. 1-32 NEW ENGLAND DIVISION TABLE 1-B (Continued) AUTHORIZING LEGISLATION Acts Work Authorized Documents July 14, 1960, as amended Mar. 2, 1827 July 11, 1871 Aug. 5, 1886 Mar. 2, 1945 Oct. 27, 1965 Mar. 2, 1829 Aug. 14, 1876 Sept. 19, 1890 Oct. 23, 1962 Mar. 2, 1945 June 13, 1902 June 25, 1910 July 27, 1916 Aug. 26, 1937 Oct. 22, 1976 June 14, 1880 June 25, 1910 Mar. 2, 1945 July 5, 1884 Aug. 11, 1888 July 31, 1892 Mar. 2, 1907 GREEN HARBOR, MA (See Section 7 of Text) Channel 6 feet deep, 100 feet wide from deep water to head of navigation; anchorage near town pier; sealing rebuilding in part and extension of existing west jetty. HYANNIS HARBOR, MA (See Section 8 of Text) Breakwater. Present dimensions of breakwater. Dredging behind breakwater. Channel, anchorage and jetty. JONESPORT HARBOR, ME. (See Section 9 of Text). A steel sheetpile breakwater 1200 feet in length. A 15-acre anchorage composed of 9 acres; 6 feet deep and 6 acres 8 feet deep. An entrance channel 100 feet wide and 8 feet deep. KENNEBUNK RIVER, ME (See Section 10 of Text). Repair of pier on east side of channel entrance. Deepening at Wading Place and Mitchells Point. Jetty at Wading Place. 8-foot channel. 6-foot channel. 6-foot anchorage, west side of channel. 6-foot anchorage, east side of channel. Extension of west jetty, and construction of sand fence. MIANUS RIVER, CT (See Section 11 of Text). Provides for a channel 6 feet deep and 100 feet wide from Cos Cob Harbor to head of navigation at Boston Post Road, Mianus, distance about 1.2 miles. NEW LONDON HARBOR, CT (See Section 12 of Text). Waterfront channel and branch channels in Winthrop Cove and east of Central Vermont Railroad pier. Dredging in Shaws Cove. Entrance channel. Maneuvering area and present project extent of entrance channel. Deepening existing channel to 40 feet; providing a 40-acre turning basin 30 feet deep and a 4.9-acre maneuvering area 32 feet deep. (Phase I Authorization) NEWBURYPORT HARBOR, MA. (See section 13 of Text). Construction of rubblestone jetties. Dredging the bar at entrance to harbor. Dredging channel from sea to wharves and a widened turning basin. PENOBSCOT RIVER, ME (See Section 14 of Text). Widening channel at Bangor and Crosby's Narrows. Dredging between Winterport and Bucksport. Widening the channel at Bangor. Further widening of the harbor at Bangor. P.L. 86-645, Section 107. Authorized by Chief of Engineers, Dec. 15, 1965. S. Doc. 32, 18th Cong., 2nd sess. H. Doc. 63, 41st Cong., 2nd sess. H. Ex. Doc. 96, 48th Cong., 2nd sess. H. Doc. 98, 77th Cong., 1st sess.4 H. Doc. 481, 94th Cong., 2nd sess. Authorized by H. Res. 23 Sept. 76 and S. Res. 1 Oct. 76 pursuant to Section 201 of cited Act. Annual Report, 1875, p. 115 H. Ex. Doc. 136, 51st Cong., 1st sess. and Annual Report 1890, p. 471. H. Doc. 459, 87th Cong., 2nd sess.4 H. Doc. 549, 78th Cong., 2nd sess. H. Doc. 392, 56th Cong., 1st sess. H. Doc. 329, 60th Cong., 1st sess. H. Doc. 613, 63rd Cong., 2nd sess.4 Rivers and Harbors Committee Doc. 82, 74th Cong., 2nd sess.4 Chief of Engineers report dated February 20, 1975. Annual Report 1910, p. 59. H. Doc. 703, 76th Cong., 3rd sess. S. Ex. Doc. 44, 48th Cong., 1st sess. and Annual Report, 1884, p. 475. H. Ex. Doc. 133, 50th Cong., 1st sess. and Annual Report 1888, p. 425. H. Ex. Doc. 37, 52nd Cong., 1st sess. and Annual Report, 1892, p. 553. H. Doc. 739, 59th Cong., 1st sess. (Other maps are in H. Doc. 652, 71st. Cong., 3rd sess.) 1-33 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 1-B (Continued) AUTHORIZING LEGISLATION Acts Work Authorized Documents Sept. 16, 1890 Mar. 2, 1907 June 25, 1910 Mar. 2, 1919 June 30, 1948 July 14, 1960, as amended July 14, 1836 June 23, 1866 June 3, 1896 Mar. 3, 1905 (sundry civil) July 25, 1912 August 8, 19171 Mar. 2, 1945 Do. July 24, 1946 Aug. 13, 1957 Oct. 23, 1962 June 25, 1910 June 30, 1948 Mar. 3, 1871 River and Harbor Act 1882 July 14, 1960, as amended in 1965 POINT JUDITH POND AND HARBOR OF REFUGE, POINT JUDITH, RI (See Section 15 of Text). The main breakwater. Present dimensions of eastern shore arm. Western shore arm. Removing 3 shoals from the harbor arm. Abandons project for entrance to Point Judith Ponds, and authorizes channels and anchorages in lower pond and upper pond. Extension of existing 15-foot channel. PORTLAND HARBOR, ME (See Section 16 of Text). Breakwater on southerly side of mouth of inner harbor. Extension of breakwater. Dredging to 30 feet over greater part of inner harbor. Extension of 30 foot depth up Fore River to Boston & Maine R.R. bridge and in channel of approach to Back Cove. 30-foot anchorage; 14 feet at entrance to Back Cove; restore 12-foot depth in Back Cove and 30-foot depth in approach as well as in lower part of harbor. 35-foot depth in lower part of main harbor and channel of approach and remove 2 obstructing ledges in main channel. 35-foot anchorage approximately 170 acres in area northwest of House Island. Maintain Soldier Ledge Channel in Hussey Sound at depth of 40 feet. Deepen 30-foot channel to 35 feet, 35-foot turning basin easterly of Vaughon Bridge: breakwater at Spring Point. Abandonment of upper end of 12-foot channel from 2,500 feet upstream of Tukey Bridge to head of Back Cove. Entrance channel 45 feet deep from deep water in Casco Bay to a line opposite Fort Gorges. A maneuvering basin and anchorage 45 feet deep in existing House Island anchorage area. PROVINCETOWN HARBOR, MA (See Section 17 of Text). Rubblestone protection dike across House Point Island Flats from Stevens Point to Wood End and extension of Long point beach protection.2 Offshore breakwater about 2,500 feet long. ROYAL RIVER, ME (See Section 18 of Text). Enlargement of channel through bar at Gravel Point and removal of several ledges near Yarmouth. Construction of 195-foot rubblestone jetty and dredging channel. 8-foot channel, 80 feet wide and anchorage. H. Doc. 66, 51st Cong., 1st sess. H. Doc. 60, 58th Cong., 2nd sess. H. Doc. 911, 60th Cong., 1st sess. H. Doc. 2001, 64th Cong., 2nd sess. S. Doc. 15, 80th Cong., 1st sess. PL 86-645, Section 107, Authorized by Chief of Engineers, Sept. 29, 1976. H. Doc. 491, 23rd Cong., 1st sess. S. Doc. 271, 54th Cong., 1st sess. H. Doc. 489, 62nd Cong., 2nd sess. H. Doc. 71, 65th Cong., 1st sess. H. Doc. 560, 76th Cong., 3rd sess. H. Doc. 730, 79th Cong., 3rd sess. H. Doc. 510, 79th Cong., 2nd sess. Public Law 126, 85th Cong., 1st sess. 71 stat. 344 H. Doc. 216, 87th Cong., 1st sess. H. Doc. 821, 61st Cong., 2nd sess. H. Doc. 600, 80th Cong., 2nd sess. P.L. 86-645, Section 107. Authorized by Chief of Engineers, April 27, 1965. SACO RIVER, ME (See Section 19 of Text). Extension of piers, placing of buoys, and removal of obstructions at entrance to harbor. Breakwater on north side of mouth of river. Jetty on north side of mouth of river. Channel improvements and jetty extension on south side of mouth of river. Present project channel dimensions and extensions of north breakwater about 1,600 feet. Extension of north breakwater to Sharps Ledge. Anchorage and maneuvering basin. S. Ex. Doc. 44, 48th Cong., 1st sess., and Annual Report 1884, p. 482 H. Doc. 752, 61st Cong., 2nd sess.4 H. Doc. 477, 68th Cong., 2nd sess. Rivers and Harbors Committee. Doc. 11, 74th Cong., 1st sess.4 P. 86-645. Section 107. Authorized by Chief of Engineers, Nov. 14, 1967. 1-34 Mar. 2, 1827 June 23, 1866 Sept. 19, 1890 June 25, 1910 Mar. 3, 1925 Aug. 30, 1935 July 14, 1960, as amended NEW ENGLAND DIVISION TABLE 1-B (Continued) AUTHORIZING LEGISLATION Acts Work Authorized Documents July 14, 1960, as amended Sept. 3, 1954 Oct. 27, 1965 July 24, 1946, as amended. July 24, 1946, as amended June 30, 1948, as amended Mar. 7, 1974 June 30, 1948, as amended. Aug. 13, 1968 July 24, 1946, as amended June 30, 1948, as amended June 30, 1948, as amended STONINGTON HARBOR, ME (See Section 20 of Text). Dredge access channel 10 feet deep extending from deep water in Deer Isle Thoroughfare 525 feet for a width of 100 feet, narrowing to 60 feet in width for a length of 275 feet. An anchorage basin 10 acres in size (3 acres dredged to a depth of 8 feet MLW and 7 acres dredged to a depth of 6 feet MLW.) REVERE BEACH, MA (See Section 25 of Text). Placement of sandfill for protection and improvement. Raising and widening of about 13,000 feet of beach by placement of sandfill BLACKSTONE RIVER, MILLBURY, MA (See Section 29A of Text). Remove existing shoal and construct stone slope protection along both banks of the Blackstone River to prevent further erosion and possible loss of the McCracken Road bridge. CLEAR RIVER, BURRILLVILLE, RI (See Section 29B of Text). Remove approximately 60 linear feet of granite retaining wall, damaged from erosion, and construct a new mortared stone wall. PAWTUXET RIVER, WARWICK, RI (See Section 29C of Text). Flood damage reduction through acquisition of land and improvements in the flood plain. Demolition and removal of acquired structures. Flood proofing certain dwellings and installing a flood forecasting system. CHARLES RIVER (NATURAL VALLEY STORAGE AREAS), MA (See Section 29E of Text). Federal acquisition and perpetual protection of 17 crucial natural valley storage areas totalling 8,422 acres in what is known as the Middle and Upper watershed of the Charles River. BEAVER BROOK, KEENE, NH (See Section 30C of Text). Construct improvements to reduce the damaging effects of floods. PARK RIVER, HARTFORD, CT (See Section 30R of Text). Flood protection on Park River in Hartford, CT. VILLAGE OF SAXTONS, VT (See Section 30Q of Text). Construct about 175 feet of "doublewal" pre-cast concrete cells along enbankment slope. Wall would be approx. 12 feet high WEST SPRINGFIELD. MA (See Section 30R of Text). Raise the floodwall section of the West Springfield project by 1 foot in combination with a flood forecasting system. HOUSATONIC RIVER, PITTSFIELD, MA (See Section 31D of Text). Supplement the existing 8-foot high by 15-foot wide stone arch culvert under Penn Central Railroad embankment with four 10-foot diameter concrete pipe culverts. P.L. 86-645, Section 107. Authorized by Chief of Engineers, April 7, 1983. H. Doc. 146, 82nd cong., 1st sess. H. Doc. 211, 91st Cong., 2nd sess. Authorized by H. Res. 15 Dec. 70 and S. Res. 17 Dec. 70 pursuant to Section 201 of 1965 Flood Control Act. P.L. 79-526, Section 14. Authorized by Chief of Engineers, November 29, 1984. P.L. 79-526, Section 14. Authorized by Chief of Engineers, May 15, 1985. P.L. 80-868, Section 205. Authorized by Chief of Engineers, July 12, 1982. Chief of Engineers report dated December 6, 1972. P.L. 80-858, Section 205. Authorized by Chief of Engineers, June 21, 1985. S. Doc. 43, 90th Cong., 1st sess. P.L. 79-526, Section 14, Authorized by Chief of Engineers, February 24, 1983. P.L. 80-858, Section 205. Authorized by Chief of Engineers, October 5, 1982. P.L. 80-858, Section 205. Authorized by Chief of Engineers, July 17, 1981. 1-35 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 1-B (Continued) AUTHORIZING LEGISLATION Acts Work Authorized Documents July 24, 1946, as amended July 24, 1946, as amended July 24, 1946, as amended July 24, 1946, as amended Do. July 24, 1946, as amended July 3, 1958 Oct. 23, 1962 Oct. 22, 1976 July 24, 1946, as amended June 30, 1948, as amended June 30, 1948, as amended June 30, 1948, as amended July 14, 1960 NONEWAUG RIVER, WOODBURY, CT (See Section 32 of Text). Construct a gabion-type retaining wall extending to a height of 17 feet above channel invert and angled back from river at a slope of 6 vertical on 1 horizontal. GULF STREET AND TRUMBULL AVENUE, MILFORD, CT (See Section 33 of Text). Construction of stone slope protection. ISLESBORO (THE NARROWS), ME (See Section 34 of Text). Construct graded quarry stone revetment along 325 feet of shoreline. Riprap revetment extend above Main Road to height of 18 feet MLW. JOHNSON BAY, LUBEC, ME (See Section 35 of Text). Emergency bank and shoreline protection. Extension of existing emergency bank and shoreline protection. PORT 5 FACILITY, BRIDGEPORT, CT (See Section 36 of Text). 250 linear feet of graded riprap slope protection. NEW BEDFORD, FAIRHAVEN AND ACUSHNET, MA (See Section 38 of Text). Hurricane barriers in New Bedford Harbor. NEW LONDON, CT (See Section 39 of Text). Hurricane barrier protecting city of New London from tidal damage. BAGADUCE RIVER, CASTINE, ME (See Section 41 of Text). Placement of approximately 200 linear feet of stone slope protection along the shoreline of Castine Harbor adjacent to Fort Pentagoet. PENOBSCOT RIVER, OLD TOWN, ME (See Section 42 of Text). Modification of two existing earth dike structures. Repair settling of the inlet and/or outlet structures and reinforced concrete pipe of east and west dikes. SEBASTICOOK RIVER, HARTLAND, ME (See Section 43 of Text). Raise concrete wall near abutment of Great Moose Lake Dam. Construct earthfill dikes outward from left and right abutments of Great Moose Lake Dam. Clear main river channel at base of Great Moose Lake Dam and extending downstream to Main Street Bridge. Repair sluice gates in lower dams and reconstruct concrete bridge abutment approach wall. STAMFORD, CT (See Section 44 of Text). Hurricane barrier protecting areas of Stamford from tidal damage. P.L. 79-526, Section 14. Authorized by Chief of Engineers, April 15, 1983. P.L. 79-526, Section 14. Authorized by Chief of Engineers, September 11, 1984. P.L. 79-526 Sec. 14 Authorized by Chief of Engineers, December 7, 1982. P.L. 79-526, Section 14. Authorized by Chief of Engineers, May 15, 1979. P.L. 79-526, Section 14. Authorized by Chief of Enginners, May 3, 1983. P.L. 79-526, Section 14 Authorized by Chief of Engineers, May 26, 1983. S. Doc. 59, 85th Cong., 1st sess. H. Doc. 478, 87th Cong., 2nd sess. P.L. 79-526, Section 14. Authorized by Chief of Engineers, February 23, 1983. P.L. 80-858, Section 205. Authorized by Chief of Engineers, May 20, 1974. P.L. 80-858, Section 205. Authorized by Chief of Engineers, May 16, 1985. P.L. 80-858, Section 205. Authorized by Chief of Engineers, March 9, 1982. H. Doc. 210, 86th Cong., 1st sess. S Removal of one ledge inactive. 2 The 300-foot extension of Long Point beach protection is inactive. 3 Inactive. 4 Contains latest maps. 1-36 NEW ENGLAND DIVISION TABLE 1-C OTHER AUTHORIZED NAVIGATION PROJECTS For Last Cost to September 30, 1985 Full Report Contributed See Annual Operation and Funds Expended Project Report for Construction Maintenance (Construction) Andrews River, MA",6w 5 1981 $ 219,042 $ 393,272 $ 187,500 Apponaug Cove, RI',6 1964 156,8742 21,679 104,583 Bagaduce River, MEa, 4 ,5 1912 28,000 39 Bar Harbor, ME 5 1932 406,591 2,187 Bass Harbor, ME1,6 1965 188,859 21,475 Bass Harbor Bar, ME' 1920 4,076 12,175 Beals Harbor, ME' 1959 184,880 47,923 Belfast Harbor, ME' 1971 61,561 224,449 Bellamy River, NH',3,4 1897 34,643 - Beverly Harbor, MA' 1951 246,048 16,821 100,000 Boothbay Harbor, ME' 1953 18,000 22,983 Boston Harbor, MA",22 1984 25,313,08353 9,678,3275 Branford Harbor, CT' 1978 9,537 975,345 Bridgeport Harbor, CT' 1983 4,491,11949 1,964,18250 147,887 Bristol Harbor, RI 1983 238,288 1,654 Bucks Harbor, Machiasport, ME1,6 1976 277,420 16,838 Bucksport Harbor, ME' 1907 18,421 13,593 Bullocks Point Cove, RI' 1979 170,902 76,667 123,757 Bunker Harbor, ME1,6 1969 95,372 28,406 Camden Harbor, ME' 1960 102,400 125,936 Canapitsit Channel, MA',4 1899 9,113 12,279 Cape Porpoise Harbor, ME' 1977 175,037 347,865 20,000 Carvers Harbor, Vinalhaven, ME' 1964 190,438 9,021 Cathance River, ME 3,s 1884 21,000 - Chatham (Stage) Harbor, MA' 1984 266,70555 1,900,08056 Coasters Island Harbor, R1',4 1911 5,500 13,161 Cobscook Bay, ME'3,4 1866 4,173 - Cocheco River, NH,3',4 1913 119,089 42,617 Cohasset Harbor, MA' 1979 267,76738 219,487 127,000 Connecticut River (above Hartford), CT8 1932 116,324 15,822 Corea Harbor, Gouldsboro, ME,6 1984 797,954 73,150 Criehaven Harbor, ME' 1939 40,776 8,125 Cross Rip Shoals Nantucket Sound, MA' 1954 24,200 54,328 Cuttyhunk Harbor, MA' 1978 27,167 943,42052 11,643 Damariscotta River, ME',4 1906 5,000 905 Deer Island Thoroughfare, ME', 4 1916 40,000 - Dorchester Bay and Neponset River, MA" 1968 94,584 301,944 Duck Island Harbor, CT' 1953 482,166 374,216 Duxbury Harbor, MA' 1978 421,29729 798,722 35,00030 East Boothbay Harbor, ME' 1953 6,500 17,238 Eastport Harbor, ME' 1984 638,67547 192,624 Edgartown Harbor, MA' 1978 65,61435 32,589 10,000 Essex River, MA' 1948 21,759 83,93814 Exeter River, NH"'4 1913 27,454 3,032 Fall River Harbor, MA' 1984 6,164,75740 2,064,76751 Falmouth Harbor, MA' 1978 123,763 279,080 35,000 Fivemile River Harbor, CT' 1969 35,490 188,802 Frenchboro Harbor, ME' 1978 657,345 24,616 Georges River, ME' 1978 25,788 228,937 Gloucester Harbor and Annisquam River, MA' 1983 1,296,93436 1,375,491 25,000 Great Salt Pond, Block Island, RI'5 1983 189,037 529,753 Greenwich Bay, RI' 1893 2,000 6,527 Greenwich Harbor, CT 1969 198,758 204,872 100,000 Guilford Harbor, CT 1983 137,222 1,224,965 25,000 Hampton Harbor, NH' 1984 200,000 1,758,174 193,761 Harbor of Refuge, Block Island, RI' 1983 576,856 1,327,290 Harraseeket River, ME',' 1896 30,963 5,309 Hay (West Harbor), Fisher's Island, NY' 1931 8,401 3,032 Hendrick's Harbor, ME' 1957 28,204 6.325 Hingham Harbor, MA' 1954 28,316 154,349 Housatonic River, CT2 1983 859,691 2,360,321 222,010 1-37 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 1-C (Continued) OTHER AUTHORIZED NAVIGATION PROJECTS For Last Cost to September 30, 1985 Full Report Contributed See Annual Operation and Funds Expended Project Report for Construction Maintenance (Construction) Ipswich Harbor, MA Island End River, Chelsea, MA,6 Isle Au Haut Thoroughfare, ME Isle of Shoals Harbor, ME and NH' Josias River, ME 1 ' Kennebec River, ME 5 Kingston Harbor (North Plymouth), MA' Lagoon Pond, Martha's Vineyard, MA1,6 Lamprey River, NH1,4 Little Harbor. NHI,4,26 Little Harbor, Woods Hole, MAI,4 Lubec Channel, ME' Lynn Harbor, MA 19 Machias River, ME' Malden River, MA,20 Matinicus Harbor, ME' Medomak River, ME' Menemsha Creek, MA' Merrimack River, MA' Milford Harbor, CT 5 Moosabec Bar, ME' Mystic River, CTI Mystic River, MA' Nantucket (Harbor of Refuge), MA 5 Narraguagus River, ME' New Bedford and Fairhaven Harbors, MA 5 New Harbor, ME',22 New Haven Breakwater, CT' New Haven Harbor, CT' Newport Harbor, RI' Niantic Bay and Harbor, CT1,6 Northeast Harbor, ME' Norwalk Harbor, CT' Owl's Head Harbor, ME 13 Patchogue River, CTI,22 Pawcatuck River, Little Narragansett Bay and Watch Hill Cove, RI & CTI Pawtuxet Cove, RI' Pepperell Cove, ME' Pig Island Gut, ME,6 Pleasant Bay, MA Pleasant River, MEI Plymouth Harbor, MA' Pollock Rip Shoals, Nantucket Sound, MA' Portsmouth Harbor & Piscataqua River, ME & NHI,22 Potowomut River, RI' Providence River & Harbor, RI5 Red Brook Harbor, Bourne, MA 9 Richmond Harbor, ME1,4 Richmond's Island Harbor, MEI,4 Rockland Harbor, ME" Rockport Harbor, MA' Rockport Harbor, ME1,3 Rye Harbor, NH1,22 St. Croix River, ME 1 ' Sakonnet Harbor, RI' Sakonnet River, RI1,1 0 Salem Harbor, MA' Sandy Bay (Harbor of Refuge), Cape Ann, MA 8 1969 1983 1980 1977 1977 1982 1895 1976 1913 1977 1906 1956 1956 1972 1922 1962 1953 1981 1940 1981 1930 1957 1984 1965 1969 1953 1966 1950 1984 1953 1972 1954 1983 1968 1984 1978 1975 1969 1966 1971 1892 1978 1956 1984 1882 1976 1972 1883 1882 1976 1979 1915 1965 1950 1983 1909 1969 1922 5,618 311,850 137,653 80,691 115,565 1,599,94046 8,940 99,098 19,980 133,227 18,000 380,322 755,576 32,000 104,853 14,00021 17,000 56,926 369,891 90,506 11,400 197,582 3,222,777 502,66123 821,144 1,857,618 118,62024 1,242,246 4,205,24641 733,524 66,464 138,942 531,12939 124,158 355,445 318,78731 295,356 171,351 191,753 3,500 2,127,21832, 33 1,083,504 5,384,04312 5,000 25,417,02228 38,764 20,000 119,844 1,948,462 22,000 32,000 130,342 179,550 764,651 38,427 1,693,202 1,925,553 32,947 140,747 643,364 122,173 1,792,756 6,587 33,563 266,119 5,224 23,941 205,497 185,217 45,097 8,989 92,359 622,346 158,224 622,369 25,227 104,932 1,971,846 444,059 57,592 708,967 26,944 40,273 12,763,17927 128,223 71,570 51,032 3,723,52042 13,867 621,988 644,186 152,105 26,553 43,863 217 924,90134 846,590 1,934,159 50 3,830,502 1,808 452,800 194,963 44,478 83,634 36,392 180,016 9,549 364,945 16,060 314,50048 26,813 80,990 62,000 12,500 11,380 14,000 20,385 7,015 67,500 34,500 4,383 56,694 20,000 295,356 541,611 99,707 255,000 61,338'17 19,892 21,928 1-38 NEW ENGLAND DIVISION TABLE 1-C (Continued) OTHER AUTHORIZED NAVIGATION PROJECTS For Last Cost to September 30, 1985 Full Report Contributed See Annual Operation and Funds Expended Project Report for Construction Maintenance (Construction) Sasanoa River, ME1,3 ,4 1915 35,000 124 Scarboro River, ME' 1976 392,635 1,239,293 10,000 Scituate Harbor, MA' 1971 379,851 108,195 69,976 Searsport Harbor, ME' 1966 572,56816 31,120 Seekonk River, RI' 1954 672,214 793,234 67,792 Sesuit Harbor, MA1,6 1983 226,306 4,887 124,588 South Bristol Harbor, ME' 1971 89,593 11,052 2,663 Southport Harbor, CT' 1962 96,9277 231,489 18,525 Southwest Harbor, ME' 1962 180,042 54,207 7,501 Stamford Harbor, CT 1980 892,82437 1,683,02045 169,636 Stockton Harbor, ME1,3,4 1915 33,000 23,216 Stonington Harbor, CT' 1959 377,328 123,060 Stony Creek, Branford, CT, 6 1978 112,487 269,370 Sullivan Falls Harbor, ME' 1914 19,871 - Taunton River, MA5 1948 442,895 32,917 Tenants Harbor, ME1 1920 18,750 13,292 Thames River, CT5 1967 1,471,919 1,489,826 Union River, ME3,' 5 1912 146,855 114,562 Vineyard Haven, MA' 1943 27,186 8,699 Wareham Harbor, MA5 1896 95,997 10,296 Warren River, RI' 1890 5,000 - Warwick Cove, RI1,6 1975 155,430 51,196 107,220 Wellfleet Harbor, MA1 1981 157,63425 850,770 32,000 Wells Harbor, ME 1 1979 360,973 1,554,836 212,000 Westcott Cove, CT i 1978 55,960 217,309 21,000 Westport Harbor and Saugatuck River, CT' 1972 19,308 180,824 Westport River, MA4 ,9 1942 - - Weymouth Back River, MA' 1944 48,740 7,184 20,000 Weymouth-Fore & Town Rivs., MA1, 22 1979 and 1983 30,194,61343 1,307,03144 630,133 Wickford Harbor, RI, 22 1973 233,410 70,435 49,094 Wilson Point Harbor, CT1, 4 1895 54,177 - Winnipesaukee Lake, NH' 1952 7,500 29,870 Winter Harbor, ME, 6 1976 162,937 - Winthrop Harbor, MA1 1895 8,992 38,515 Wood Island Harbor, and Pool at Biddeford, ME' 1957 143,112 14,707 12,000 Woods Hole Channel, MA' 1940 230,000 51,718 York Harbor, ME 1977 239,654 351,090 32,161 S Completed. 2 Excludes costs of $33,000 for local cooperation requirements, which includes $104,583 cash contribution. 3Abandonment recommended in H. Doc. 467, 69th Congress, 1st session. 4No commerce reported. 5 Completed except for inactive portion. 6 Authorized by the Chief of Engineers (Public Law 86-645, Sec. 107). 7 Includes$37,714EmergencyReliefFunds.Excludes$18,525 Contributed Funds, of which $1,785 was for work outside approved project. 8 Inactive. 9 Awaiting local cooperation. Improvement to be restudied. 10 Commerce included under Tiverton Harbor, RI. " Authorized work remaining on project is comprised of an incomplete and an inactive portion. 12 Includes $130,393 for previous projects. 13 Recommendation for abandonment of existing project made in H. Doc. 467, 69th Congress 1st session. Portion of project authorized by the Chief of Engineers (P.L. 86-645, Sec. 107) is complete. 14 Excludes $5,000 Contributed Funds expended. 15 Improvement adequate for commerce. 16 Costs to local interests for berth improvements are estimated to be $60,000. 17 Excludes $81,548 Contributed Funds "Other" expended. s18 Abandonment recommended in H. Doc. 411, 64th Congress, 1st session, and in River and Harbor Committee Doc. 3, 65th Congress, 1st session. 19 Improvement to be restudied. 20 Under State maintenance. 21 Excludes $114,327 expended for rehabilitation; breakwater repaired in 1962. 22 Portion of project authorized by Chief of Engineers. 23 Excludes $211,649 expended for rehabilitation; jetty repaired in 1963. 24 All assurances of local cooperation have not been fulfilled. Public landing at Back Cove has not been constructed. Portion of project authorized by Chief of Engineers (Public Law 86-645, Sec. 107). 25 Includes $11,350 for previous project. 26 H. Doc. 467, 69th Cong., lstsess. recommended eliminating maintenance dredging. 1-39 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 1-C (Continued) OTHER AUTHORIZED NAVIGATION PROJECTS 27 Includes $32,570 for previous projects. 28 Final fund adjustment made FY 1978 ($52,323.28). 29 Includes $37,000 for new work for previous project. so Excludes local requirements of $65,000 consistingof $13,000 for public wharf and $52,000 for additional construction costs. s31 Includes $133,357 for previous project. 32 Includes $188,647 for previous project. 33 Excludes $894,475 major rehabilitation for Long Beach Dike. 34 Includes $2,013 for previous projects. In addition $400 was expended for maintenance from Contributed Funds. 35 Includes $15,614 for new work for previous projects. 36 Includes $21,000 for previous projects. 37 Includes $135,143 for previous project. 38 Includes $10,000 for previous project. 39 Includes $162,517 for previous project. 40 Includes $330,204 for previous project. 41 Includes $331,626 for previous projects. Includes $290,877 National Industrial Recovery Funds and $59,207 Public Works Funds. 42 Includes $66,120 for previous projects. 4 Includes for previous projects $735,900 (Weymouth, Fore R.) and $25,000 (Town R.). 44 Includes for previous project $5,250 (Weymouth, Fore River) and $12,577 (Weymouth Town River). 45 Includes $59,420 for previous project. 46 Includes $509,411 for previous projects. 47 Excludes $141,530 expended Contributed Funds, Other. 48 Excludes $829,000 Contributed Funds "Other" exexpended. 49 Includes $378,450 for previous project. 50 Includes $11,949 for maintenance of previous project. 51 Includes $81,410 for previous project. 52 Excludes $50,000 Contributed Funds expended for maintenance. 53 Includes $1,465,123 for previous projects. Includes $935,303 Emergency Relief Funds and $1,030,806 Public Works Funds. 54 Includes $17,879 for previous projects. Excludes $17,767 Contributed Funds. 55 Includes $7,889 for previous project. 56 Includes $83,276 for maintenance of previous project. 1-40 NEW ENGLAND DIVISION TABLE 1-D OTHER AUTHORIZED BEACH EROSION CONTROL PROJECTS For Last Full Report Cost to Amount See Annual Sept. 30, 1985 Expended by Project Report For Construction Local .Interest Burial Hill Beach, Westport, CT' 1958 $ 5,810 $ 11,612 Calf Pasture Beach Park, Norwalk, CT' 1964 56,286 120,179 Clark Point Beach, New Bedford, MA' 1982 228,081 228,080 Cliff Walk, Newport, RI7 1984 405,491 955,237 Compo Beach, Westport, CT' 1962 84,544 169,089 Cove Island, Stamford, CT' 1961 47,131 94,262 Cummings Park, Stamford, CT' 1963 26,886 53,771 Guilford Point Beach (Jacobs Beach), Guilford, CT' 1961 15,620 31,241 Gulf Beach, Milford, CT' 1958 21,303 42,606 Hammonasset Beach, Madison, CT' 1956 163,183 326,366 Hampton Beach, Hampton, NH' 1966 260,868 385,641 Jennings Beach, Fairfield, CT' 1956 14,401 28,802 Lighthouse Point Park (Area 9), CT' 1961 3,930 7,859 Lynn-Nahant Beach, MA - 50,000 - Matunuck Beach, South Kingston, RI 1961 - - Middle Beach, CT' 1958 8,810 17,620 Misquamicut Beach, Westerly, RI 1963 14,512 29,024 Nantasket Beach, MA4 1971 - - North Scituate Beach, Scituate, MA' 1969 106,552 106,552 Oak Bluffs Town Beach, Martha's Vineyard, MA' 1976 273,334 198,583 Oakland Beach, Warwick, RI' 1982 559,200 181,175 Plum Island, MA' 1977 118,882 104,875 Prospect Beach, West Haven, CT' 1958 104,573 240,819 Quincy Shore Beach, Quincy, MA' 1962 621,440 1,242,880 Sand Hill Cove Beach, RI' 1959 40,143 82,000 Sasco Hill Beach, Fairfield, CT' 1961 23,759 47,518 Seaside Park, CT' 1958 150,000 329,921 Sherwood Island State Park, Westport, CT' 1983 1,186,830 889,330 Short Beach, CT' _ _ 5- Silver Beach to Cedar Beach, CT 1964 62,560 270,695 Southport Beach, CT' 1960 17,631 35,263 Town Beach, Plymouth, MA 1964 5,490 10,981 Town Neck Beach, Sandwich, MA 1961 - - Wallis Sands State Beach, Rye, NH' 1966 65,131 435,942 Wessagusset Beach, Weymouth, MA' 1971 180,944 200,208 Willard Beach, South Portland, ME 1983 171,000 - Winthrop Beach, MA' 1960 176,5676 353,134 Woodmont Shore, Milford, CT' 1961 53,838 111,6792 S Completed. 2 Excludes $118,215 expended for work beyond scope of project. 3 Additional Federal participation will be required based on Public Law 87-874. 4Project inactive. 5 Project completed at no cost to Federal Government by using fill from federal navigation improvement at Housatonic River. 6 Project is complete. There are three additional groins, construction of which is deferred until it is determined that they are necessary. 7 Completed except for inactive portion. 1-41 TABLE 1-E REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 OTHER AUTHORIZED FLOOD CONTROL PROJECTS For Last Cost to September 30, 1985 Full Report See Annual Contributed Project Report for Construction Funds Alley Bay, Beals, ME 3 ,4 Alford, Green River, MA3, 4 Amesbury, Powwow River, MA 3,4 Ansonia-Derby, CT 3 Bound Brook, Scituate, MA3, 4 Canton, MA 3, 4 Charles River Dam, MA 3 Charlestown, NH 3, 4 Cherryfield, ME3, 4 Chicopee, MA3 Chicopee Falls, MA 3 Cocheco River, NH3,4 Connecticut River, North Stratford, NH 3, 4 Connecticut River, W. Stewartstown, NH 3, 4 Danbury, CT 3 Derby, CT 3 East Branch Dam, CT3 East Hartford, CT 3 Fitchburg, MA (See No. Nashua River) Folly Brook, Wethersfield, CT 3 ,4 Frt Kent, ME 3,4 Fox Point Barrier, RI3 Gardner, MA3,4 Hall Meadow Brook Dam, CT3 Hartford, CT3 Hartford, White River, VT3,4 Hayward Creek, Braintree-Quincy, MA3, 4 Holmes Bay, Whiting, ME 3 Holyoke, MA3 Housatonic River, Salisbury, CT3,4 Housatonic River, Sheffield, MA 3,4 Huntington, MA3, 4,10 Island Avenue, Quincy, MA3 ,4 Keene, NH3 ,4 Lancaster, Israel River, NH3,4 Lee, Housatonic River, MA 3,10 Lincoln School Lake, ME Little River Dike, Westfield, MA 3 Lowell, MA 3 Lower Woonsocket, RI3 Mad River Lake, CT 3 Merriconeag Sound, Harpswell, ME 3 Monoosnoc Brook, MA 13 Monoosnoc Lake, MA 13 Nashua, NH 3 , Nookagee Lake, MA Northampton, MA 3 North Canaan, Blackberry River, CT3,4 North Nashua River, Fitchburg, MA 3 North Nashua River, Lancaster, MA3, 4 Norwalk, CT3,4 Norwich, CT3 Pawcatuck, CT3 Phillips Lake, MA Prestile Stream, Blaine, ME 3 Riverdale, MA 3 Salmon River, Colchester, CT34 Sand Cove, Gouldsboro, ME Saxonville, MA 3 Shelburne, Androscoggin River, NH 3,4 Smelt Brook, Weymouth-Braintree, MA3, 4 Springdale, MA3 1979 1977 1978 1977 1974 1964 1981 1976 1963 1954 1978 1963 1982 1976 1978 1977 1973 1951 1979 1979 1976 1970 1970 1960 1973 1979 1980 1953 1982 1981 1960 1983 1955 1982 1976 1984 1945 1977 1973 1980 1967 1967 1950 1976 1950 1977 1981 1979 1952 1960 1966 1982 1980 1952 1983 1984 1981 1977 1978 1952 $ 190,500 41,419 132,113 18,266,040 47,300 180,6705 41,167,643 113,330 203,000 1,433,6007 2,183,912 183,100 180,000 54,703 13,143,000 7,582,642 1,959,836 2,135,447 220,284 1,997,820 11,112,801 495,691 2,572,357 6,094,1009 332,236 2,235,470 207,390 3,418,000 102,800 202,608 3,900 172,000 44,100 551,606 37,852 13,155,29826 5,000 490,60011 6,600,681 4,773,020 107,681 270,0008 563,677 680,00017 73,865 3,235,00023 81,671 52,150 1,209,000 644,311 300,000 73,674 1,138,000 247,100 127,500 4,218,700 37,657 1,803,739 700,000 1-42 21 92,891 5,554,08715 385 411,29222 2 - 2 __ 19 7,637 3,679,50014 15,500 2,781,100 24,447 __ 25 1,266,63820 327 214,106 25,000 24 NEW ENGLAND DIVISION TABLE 1-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS For Last Cost to September 30, 1985 Full Report See Annual Contributed Project Report for Construction Funds Springfield, MA3 1950 577,00018 5,350 Squantz Pond, New Fairfield, CT 3,4 1983 116,296 - Stony Brook, Wilton, NH 3,4 1973 19,500 - Sucker Brook Dam, CT3 1976 2,227,712 58,800 Three Rivers, MA 3 1970 1,577,18912- Torrington, East Branch, CT 3 ,4 1963 389,200 - Torrington, West Branch, CT 3 ,4 1963 228,300 - Trumbull Lake, CT 1 1983 1,498,799 - Ware, MA 3,4 1963 400,000 - Waterbury-Watertown, CT3,4 1963 263,300 - Westerly, RI 1966 - - Weston, VT 3 ,4 1957 13,000 1,800 West Branch, Westfield River, Huntington, MA3,4 1983 116,492 - West Springfield, MA3 1954 1,334,00016- West Warren, MA 3,4 1964 389,200 41,000 Whitmanville Lake, MA 1979 605,023 - Winsted, CT3 1954 245,500 - Woonsocket, RI3 1962 4,040,000 224, 500 Worcester Diversion, MA3 1978 5,086,859 79,300 1 Inactive. 15 Excludes $1,674,567 Contributed Funds, Other. 2 Excludes $1,146,828 expended from Contributed Funds, 16 Excludes $245,000 Public Works Administration funds. Other. 17 Excludes $280,000 Public Works Administration funds. 3 Completed. 18 Excludes $355,000 Public Works Administration funds. 4 Authorized by Chief of Engineers. 19 Excludes $406,653 Contributed Funds, Other. 5 Reflects FY1967 settlement of outstanding claims. 20 Excludes $488,920 Contributed Funds, Other. 6 Completed except for inactive portion. 21 Excludes $727,460 Contributed Funds, Other. 7 Includes $295,000 Public Works Administration funds. 22 Excludes $12,000 expended for land condemnations and 8 Excludes $147,366 Flood Control and Coastal Emergency $25,184 Contributed Funds, Other for relocations. funds expended. 23 Excludes $1,370,000 Public Works Administration funds 9 Excludes $835,000 Public Works Administration funds. expended on Fitchburg, MA. 10 Emergency Bank Protection. 24 Excludes $8,503 Contributed Funds, Other. 11 Excludes $794,374 Public Works Administration funds. 25 Excludes $3,000 Contributed Funds, Other. 12 Excludes $565,168 Contributed Funds, Other. 26 Dickey Lake portion deauthorized; costs shown reflect 13 To be restudied. combined Dickey-Lincoln School effort. 14 Cash for construction only. Excludes $245,000 expended for land condemnation. TABLE 1-F OTHER AUTHORIZED MULTI-PURPOSE PROJECTS INCLUDING POWER For Last Cost to September 30, 1985 Full Report See Annual Contributed Project Report for Construction Funds Passamaquoddy Tidal Power Project, ME' 1935 6,384,394- 1 Work discontinued in 1937. Facilities transferred to War Assets Administration. 1-43 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 1-G DEAUTHORIZED PROJECTS For Last Funds Expended Full Report See Annual Date Contributed Project Report For Deauthorized Federal Funds Alternative for Sugar Hill Reservoir -Aug 1977 $ - $ - Andover Lake, CT -Aug 1977 - - Bagaduce River, ME (uncompleted portion) - Oct 1978 -- Baker Brook, MA 1972 Nov 1979 94,000 - Beards Brook Reservoir, NH 1949 Aug 1977 78,000 - Beaver Brook Lake, NH 1973 Apr 1978 378,300 - Bennington Reservoir, NH 1949 Aug 1977 205,000 - Brant Rock Beach, Marshfield, MA 1961 Nov 1979 - - Bridgeport Harbor, CT (uncompleted portion) 1980 Nov 1979 - - Brockway Lake, VT 1946 Aug 1977 - - Cambridgeport Lake, VT - Aug 1977 - - Chicopee, MA (uncompleted portion) 1954 Aug 1977 - - Claremont Lake, NH 1968 Dec 1970 242,700 - Clyde, RI 1948 Apr 1951 8,800 - Connecticut River below Hartford, 1979 Oct 1978 -- CT (uncompleted portion) Cotuit Harbor, MA 1962 Oct 1978 8,541 - Dickey Lake, ME 1983 Dec 1981 13,130,000'- Fivemile River Harbor, CT (uncompleted portion) 1969 Oct. 1978 - - Gaysville Lake, VT 1970 Oct 1976 206,600 - Greenwich Point Beach, CT 1959 Oct 1978 - - Housatonic River, CT (uncompleted portion) 1979 Nov 1979 - - Honey Hill Lake, NH 1949 Aug 1977 92,000 - Ludlow Lake, VT - Aug 1977 - - Manchester Harbor, MA 1949 Nov 1979 23,986 - Marblehead Harbor, MA 1968 Oct 1978 43,711 - Mattapoisett Harbor, MA 1950 Oct 1978 - - Mountain Brook Dam, NH 1949 Aug 1977 57,000 - Mystic, CT 1968 Aug 1972 67,700 - Napatree Beach, RI - Nov 1979 - - Narragansett Pier, RI 1966 Nov 1970 115,590 - North Andover and Lawrence, MA 1949 Aug 1977 20,000 - North Hampton Beach, North Hampton, NH 1963 Nov 1981 -- Norwalk-Wilton, CT 1973 Nov 1979 -- Pawcatuck River, RI & CT (uncompleted portion) 1979 Nov 1979 -- Pawtucket, RI 1949 Nov 1977 -- Pepperell Cove, ME (uncompleted portion) 1969 Nov 1981 -- Point Judith, RI 1968 Nov 1977 198,477- Pontiac Diversion, RI 1948 Apr 1951 24,200- Provincetown Beach (Herring Cove), MA 1961 Oct 1978 -- Provincetown Harbor, MA (uncompleted portion) 1979 Oct 1978 -- Saco River, ME (uncompleted portion) 1979 Oct 1979 -- Sakonnet Harbor, RI (uncompleted portion) 1982 Jun 1982 176,000-- Sandy Bay, Cape Ann, MA (uncompleted portion) 1922 Oct 1978 -- South Coventry Lake, CT 1951 Aug 1977 96,000- South Tunbridge Lake, VT - Aug 1977 -- Stamford Harbor, CT (2 projects uncompleted portions) 1979 Oct 1978 -- Stonington Harbor, ME 1961 Nov 1979 2,543- Stratford, CT 1973 Mar 1977 934,500 - Sugar Hill Reservoir, NH 1946 Dec 1944 -- The Island Lake, VT - Aug 1977 - - Thumperton Beach, Eastham, MA 1961 Nov 1979-- Wareham-Marion, MA 1965 Aug 1977 81,715 - Victory Lake, VT 1967 Aug 1977 168,400 - West Brookfield Reservoir, MA 1948 July 1960 67,000 - West Canaan Lake, NH 1948 Aug 1977 92,000 - Westfield, MA 1967 Sep 1969 507,200 - Westport, CT 1965 Feb 1970 29,634 - Westport Harbor and Saugatuck River, CT 1972 Nov 1979 (uncompleted portion) Williamsville Reservoir, VT 1949 Dec 1944 146,500 1 For Dickey-Lincoln School Lakes Project. 1-44 NEW ENGLAND DIVISION TABLE 1-H Study Identification Bass Harbor, Tremont, ME Bass River, MA Eel Pond, Falmouth, MA Gloucester Harbor, Gloucester, MA Green Harbor, Marshfield, MA Hampton Harbor, Hampton, NH Milford Harbor, Wepawaug River, CT Perkins Cove, Ogunquit, ME Pine Point Harbor, Scarborough, ME Pines River, Revere, MA Provincetown Harbor, MA Point Judith Pond, Narragansett, RI Rockport and Old Harbors. MA Saquatucket Harbor, Harwich, MA Saugus and Pine Rivers, MA Scituate Harbor, MA South Gouldsboro Harbor, ME Weymouth Back River, Weymouth, MA Winthrop Harbor, Winthrop, MA Wood Island Harbor, Biddeford, ME TABLE 1-I NAVIGATION ACTIVITIES PURSUANT TO SECTION 107, PUBLIC LAW 86-645 (PREAUTHORIZATION) Fiscal Year Costs $82,468 28,086 5,168 62,999 38,826 7,500 7,500 53,855 49,032 29,222 64 31,123 85,406 724 56,448 38,108 7,500 7,240 50,712 41,718 BEACH EROSION ACTIVITIES PURSUANT TO SECTION 103, PUBLIC LAW 78-874 (PREAUTHORIZATION) Study Identification Belfast City Park, Belfast, ME Conimicut Beach, Warwick, RI Cornhill Beach, Truro, MA Sea Gull Beach, Yarmouth, MA Seaview and Parkers River, MA South End Beach, Rockland, ME Town Beaches, CT West Haven Beaches, CT Willard Beach, ME Woodmont Beach, CT Fiscal Year Costs $8,389 39,177 15,312 84,180 8,783 71,656 46,490 39,446 885 4,994 1-45 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 1-J FLOOD CONTROL ACTIVITIES PURSUANT TO SECTION 205, PUBLIC LAW 80-858 (PREAUTHORIZATION) Study Identification Fiscal Year Costs Aroostook River, Fort Fairfield, ME $13,068 Ashuelot River, Winchester, NH 6,000 Baker Brook, Fitchburg, MA 38,435 Beaver Brook, Pelham, NH 6,000 Blackstone River, Cumberland, RI 753 Blow-Me-Down Pond, NH 7,500 Cocheco River, Farmington, NH 5,500 Connecticut River, Agawam, MA 7,500 Connecticut River, Glastonbury, CT 7,500 Dorthy Creek, Millbury, MA 5,000 East Branch, Housatonic River, Pittsfield, MA 7,000 Hockanum River, Vernon, CT 5,300 Housatonic River, New Milford, CT 2,866 Housatonic River, Lee, MA 16,500 Industrial Area, Waterbury, CT 24,921 Mad River, Waterbury, CT 67,108 Means Brook, Shelton, CT 10,700 Merrimack River, Methuen, MA 7,500 Millers River, Winchendon, MA 7,500 Pawtuxet River, Cranston, RI 15,000 Pawtuxet River, West Warwick, RI 18,925 Piscataquag-Goffstown, NH 7,500 Point of Pines, Revere, MA 8,174 Quinnipiac River, Wallingford, CT 55,936 Still River, Danbury, CT 7,500 Tanyard Brook, Bristol, RI 7,500 Ten Mile River, Cheshire, CT 50,827 Wepawaug River, Milford, CT 132,490 West River, New Haven, CT 62,130 Wood Harbor, Richmond, RI 4,000 Woonasquatucket River, Providence, RI 6,200 TABLE 1-K BLACKSTONE RIVER BASIN, MA AND RI (See Section 29 of Text) RESERVOIR Miles Above Estimated Federal Cost Mouth of Black- Reservoir Lands stone Height Capacity and Name Nearest City River (feet) Type (acre-feet) Construction Damages' Total West Hill2 Worcester, MA 25.8 51 Earthfill 12,400 $1,366,902 $940,000 $2,306,902 1 Includes highway, railroad, and utility relocations. 2 See individual report for details. 1-46 NEW ENGLAND DIVISION TABLE 1-K (Continued) LOCAL PROTECTION PROJECTS Miles Above Estimated Cost Mouth of Black- Lands stone and Location River Type of Structure Construction Damages' Total Worcester, MA 48 Diversion tunnel and channel $4,923,500 $1,179,0002 $6,102,500 Woonsocket, RI 15 Channel improvement 3,740,100 .1,069,0003 4,809,100 Lower Woonsocket, RI 13 Flood wall, conduits and channel improvement 8,356,239 435,000 8,791,239 1 Includes relocations. 2 $158,000 Federal; $1,021,000 non-Federal. 3 $300,000 Federal; $769,000 non-Federal. TABLE 1-L CONNECTICUT RIVER BASIN, VT, NH, MA AND CT (See Section 30 of Text) DAMS AND RESERVOIRS Miles Above Estimated Federal Cost Mouth of Conne- Reservoir Lands cticut Height Capacity and Name Nearest City River (feet) Type (acre-feet) Construction Damages' Total Vermont: Union Village2 White River 228.4 170 Earthfill 38,000 $3,186,860 $ 908,300 $4,095,160 Junction North Hartland 2 White River 211.7 185 Earthfill 71,400 6,349,225 963,000 7,312,225 Junction North Springfield 2 Springfield 191.3 120 Earthfill 50,600 4,781,526 2,050,000 6,831,526 Ball Mountain2 Brattleboro 178.2 265 Rockfill- 54,600 10,689,298 350,000 11,039,298 earth Townsend2 Brattleboro 168.3 133 Earthfill 33,200 5,520,413 1,878,000 7,398,413 New Hampshire: Surry Mountain 2 Keene 174.4 86 Earthfill 32,500 2,448,610 385,000 2,833,610 Otter Brook2 Keene 171.2 133 Earthfill 18,300 2,982,048 1,378,400 4,360,448 Massachusetts: Birch Hill2 Gardner 153.3 56 Earthfill 49,900 1,740,679 3,075,000 4,815,679 Tully2 Athol 148.7 62 Earthfill 22,000 1,298,752 368,000 1,666,752 Barre Falls2 Worcester 130.2 62 Rockfill- 24,000 1,928,819 39,000 1,967,819 earth Knightville2 Northampton 102.8 160 Earthfill 49,000 2,594,440 821,200 3,415,640 Littleville2 Northampton 102.0 150 Earthfill 32,400 5,863,412 1,150,000 7,013,412 Conant Brook2 Springfield 122.0 85 Rockfill- 3,740 1,935,530 1,015,000 2,950,530 earth Connecticut: Colebrook River2 Winsted 116.0 223 Rockfill- 98,500 8,341,971 5,922,000 14,263,971 earth Mad River Winsted 120.0 178 Earthfill 9,700 4,773,020 2,210,0004 6,983,020 Sucker Brook Winsted 118.5 68 Earthfill 1,480 2,227,712 180,0003 2,407,712 1 Includes highway, railroad, and utility relocations. 2 For details, see individual report. 3 Non-Federal cost. 4 Non-Federal $670,000; Federal $1,540,000. 1-47 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 1-L (Continued) LOCAL PROTECTION PROJECTS Miles Above Estimated Cost Mouth of Conne- Lands cticut and Location River Type of Structure Construction Damages' Total Charlestown, NH 181 Riverbank protection $ 113,330 - $ 113,330 Chicopee, MA 80 Wall and levee 1,434,000 $ 250,000 1,684,000 Chicopee Falls, MA 83 Wall and levee 2,600,000 70,000 2,670,000 East Hartford, CT 52 Wall and levee 2,135,447 271,000 2,406,447 Folly Brook, Wethersfield, CT 50 Channel improvement 220,284 - 220,284 Gardner, MA 163 Dam and levee 495,691 35,000 530,691 Hartford, CT 52 Wall and levee 6,930,0004 1,150,000 8,080,000 Hartford, VT 216 Channel improvement 332,236 - 332,236 Holyoke, MA 85 Wall and levee 3,418,000 150,000 3,568,000 Huntington, MA 100 Riverbank protection 3,900 - 3,900 Israel R., Lancaster, NH 314 Gabion overflow weir 551,606 - 551,606 Keene, NH 167 Channel improvement 44,100 - 44,100 Northampton, MA 94 Wall and levee 960,0005 150,000 1,110,000 North Stratford, NH 345 Slope protection 180,000 - 180,000 Park River, CT 2 51 Conduit 60,164,740 1,300,000 61,464,740 Riverdale, MA 80 Wall and levee 1,138,000 50,000 1,188,000 Salmon R., Colchester, CT 2 38 Slope protection 247,100 - 247,100 Springdale, MA 84 Wall and levee 700,000 57,000 757,000 Springfield, MA 76 Wall and levee 932,0006 272,000 1,204,000 Three Rivers, MA 98 Wall and levee 1,577,189 700,000 2,277,189 Ware, MA 110 Channel improvement 400,000 85,000 485,000 Weston, VT 195 Channel improvement 13,000 2,000 15,000 West Springfield, MA 76 Wall and levee 1,579,0003 30,000 1,609,000 West Warren, MA 111 Wall and levee 389,200 64,000 453,200 Winsted, CT 115 Channel improvement 245,500 30,000 275,500 ' To be borne by local interests. Also includes local interests 4 Includes $835,000 Public Works Administration funds. portion of relocation. 5 Includes $280,000 Public Works Administration funds. 2 For details see individual report. 6 Includes $355,000 Public Works Administration funds. $ Includes $245,000 Public Works Administration funds. TABLE 1-M HOUSATONIC RIVER BASIN, CT AND MA (See Section 31 of Text) DAMS AND RESERVOIRS1 Miles Above Estimated Federal Cost Mouth of Nagua- Reservoir Lands tuck Height Capacity and Name Nearest City River (feet) Type (acre-feet) Construction Damages2 Total Hall Meadow 4 East Branch5 Thomaston Northfield Brook Black Rock Torrington, CT Torrington, CT Torrington, CT Torrington, CT Waterbury, CT 41.0 73 Rock and earthfill 43.7 92 Earthfill 30.5 142 Rock and earthfill 30.6 118 Earthfill 29.0 154 Earthfill 8,620 $2,572,357 $1,290,0003 $3,862,357 4,350 1,959,836 1,290,0003 3,249,836 42,000 6,382,112 7,900,000 14,282,112 2,432 1,875,512 975,000 2,850,512 8,700 5,223,700 2,958,600 8,182,300 1-48 NEW ENGLAND DIVISION TABLE 1-M (Continued) HOUSATONIC RIVER BASIN, CT AND MA (See Section 31 of Text) DAMS AND RESERVOIRS1 Miles Above Estimated Federal Cost Mouth of Nagua- Reservoir Lands tuck Height Capacity and Name Nearest City River (feet) Type (acre-feet) Construction Damages2 Total Hancock Brook Waterbury, CT 25.0 57 Earthfill 4,030 $1,593,911 $2,585,000 $4,178,911 Hop Brook Waterbury, CT 15.9 97 Earthfill 6,970 2,701,562 3,450,000 6,151,562 1 For details of projects, see individual reports. 4 For last full report, see Annual Report for 1970. 2 Includes highway, railroad, and utility relocations. * For last full report, see Annual Report for 1973. 3 Includes cost of lands borne by local interests. LOCAL PROTECTION PROJECTS1 Miles Above Estimated Cost Mouth of Housa- Lands tonic and Location River Type of Structure Construction Damages2 Total Alford, Green River, MA 111.0 Earth dike and stone slope $ 41,419 $ - $ 41,419 protection Ansonia-Derby, CT 13.0 Wall, levee, channel 18,266,040 1,178,000 19,444,040 improvement and pumping station Danbury, CT 56.0 Walls, channel improvement 13,143,000 1,862,000 15,005,000 and bridge replacememt Derby, CT 12.0 Walls, levees and pumping 7,582,642 647,000 8,229,642 station North Canaan, Blackberry 83.0 Snagging and clearing 73,865 - 73,865 River, CT project Pittsfield, MA 133.0 Stone arch culvert 739,003 85,000 824,003 Salisbury, CT 76.0 Gabionade with slope 102,800 - 102,800 protection Sheffield, MA 96.0 Stone slope protection 202,608 - 202,608 Squantz Pond, New 43.0 Timber Bulkhead 116,296 - 116,296 Fairfield, CT Torrington, East Branch, CT 51.0 Dike and channel 389,200 - 389,200 improvement Torrington, West Branch, CT 52.0 Walls, dikes and channel 228,300 - 228,300 Waterbury- Watertown, CT 32.0 Wall, dike and channel 263,300 - 263,300 1 For details of projects, see individual reports. 2 To be borne by local interests. Includes relocations. 1-49 TABLE 1-N REPORT OF THE CHIEF OF ENGINEERS. U.S. ARMY 1985 MERRIMACK RIVER BASIN, NH, AND MA (See Section 37 of Text) RESERVOIRS Miles Above Estimated Federal Cost Mouth of Merri- Reservoir Lands mack Height Capacity and Name Nearest City River (feet) Type (acre-feet) Construction Damages' Total Franklin Falls2 Franklin, NH 118.2 140 Earthfill 154,000 $ 6,190,487 $ 1,760,000 $ 7,950,487 Blackwater 2 Concord, NH 118.8 75 Earthfill 46,000 766,746 553,000 1,319,746 Hopkinton-Everett2," Concord, NH 87.3 115 Earthfill 157,300 12,715,440 8,737,000 21,452,440 Edward MacDowell2 Keene, NH 161.3 67 Earthfill 12,800 1,708,253 306,000 2,014,253 Monoosnoc3 Leominster, MA 100.6 71 Earthfill 2,000 3,430,000 370,000 3,800,0005 Phillips2 Fitchblurg, MA 105.4 48 Earthfill 1,600 13,450,000 7,350,000 20,800,0006 Nookagee Fitchburg, MA 107.9 106 Earthfill 8,100 15,476,000 5,742,000 21,200,000 Whitmanville Fitchburg. MA 110.6 76 Earthfill 9,350 11,590,000 6,210,000 17,800,000 ' Includes highway, railroad, and utility relocations. 4 Substituted for Bennington and Beards Brook. Distance and 2 For details, see individual report. height are for Everett Dam. Distance and height for Hopkinton ' Project deferred, cost not revised on current price basis. Dam are 118 miles and 76 feet, respectively. 5 Includes Non-Federal reimbursement. 6 Based on "large" Phillips plan which would eliminate Nookagee Lake. LOCAL PROTECTION PROJECTS Miles Above Estimated Cost Mouth of Merri- Lands mack and Location River Type of Structure Construction Damages' Total Amesbury, Powwow and 3.0 Wall and revetment $ 132,113 $ - $ 132,113 Merrimack Rivers, MA 2 Nashua, NH2 55.0 Wall and levee 270,000 3,000 273,0004 Lowell, MA2 39.0 Wall and levee 490,6006 90,000 580,600 Monoosnoc Brook, MA3 98.4 Channel improvement 310,000 90,000 400,000 North Nashua River, MA2,6 100.5 Channel improvement 3,235,000 - 3,235,000 Saxonville, MA2 69.0 Wall, levee, channel 4,218,700 530,000 4,748,700 I To be borne by local interests. 2 Project completed. 3 Project deferred. Cost has not been revised on current price basis. 4 Excludes $15,000 expended from Contributed Funds. 5 Excludes $794,374 Public Works Administration funds. 6 Excludes $1,370,000 Public Works Administration funds expended on Fitchburg, MA. 1-50 NEW ENGLAND DIVISION TABLE 1-0 THAMES RIVER BASIN, CT, RI AND MA (See Section 45 of Text) RESERVOIRS Miles Above Estimated Federal Cost Mouth of Reservoir Lands Thames Height Capacity and Name Nearest City River (feet) Type (acre-feet) Construction Damages' Total Hodges Village2 Webster, MA 74.5 55 Earthfill 13,000 $1,317,268 $3,144,000 $4,461,268 Buffumville2 Webster, MA 74.4 66 Earthfill 12,700 2,157,603 841,000 2,998,603 East Brimfield2 Southbridge, MA 82.8 55 Earthfill 30,000 1,337,043 5,720,000 7,057,043 Westville 2 Southbridge, MA 75.2 80 Earthfill 11,000 2,284,683 3,400,000 5,684,683 West Thompson2 Putman, CT 59.3 70 Earthfill 25,600 5,036,221 1,965,000 7,001,220 Mansfield Hollow2 Willimantic, CT 40.0 70 Earthfill 52,000 4,107,164 2,340,000 6,447,164 1 Includes highway, railroad, and utility relocations. 2 For details, see individual report. LOCAL PROTECTION PROJECTS Miles Estimated Cost Above Mouth of Lands Thames and Location River Type of Structure Construction Damages Total Norwich, CT 15.0 Channel improvements $1,209,000 $72,000 $1,281,000 1 Borne by local interests. TABLE 1-P BOSTON HARBOR, MA Total Federal Cost for Existing Project to September 1985 Funds New Work Maintenance Total Regular $21,881,851 $ 8,953,809 $30,835,660 Public Works 1,030,806 - 1,030,806 Emergency Relief 935,303 - 935,303 $23,847,960 $8,953,8091 $32,801,769 1 Excludes $17,767 contributed funds. 1-51 TABLE 1-Q REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 RECONNAISSANCE AND CONDITION SURVEYS Date Survey Date Survey Project Conducted Project Conducted Massachusetts Bridgeport Harbor (survey incomplete) Duck Island (survey incomplete) Housatonic River Milford Harbor (sampling & testing) Mystic River Narraguagus River New Haven Harbor (sampling & testing) New London Harbor (sampling & testing) Pequonnock River Southport Harbor Thames River Westcott Cove Wethersfield Cove (sampling & testing) Aug 1985 Aug 1985 May 1985 Apr 1985 Apr 1985 Jun 1985 Dec 1984 Jun 1985 Jul 1985 Nov 1984 May 1985 Jun 1985 Apr 1985 Maine Andrews River (sampling & testing) Annisquam River Boston Harbor Buttermilk Bay Cape Cod Canal Cohasset Harbor Falmouth Harbor Green Harbor Hingham Harbor Lynn Harbor Nantucket Harbor (environmental assessment) Newburyport Harbor Onset Bay Plymouth Harbor (sampling & testing) Sesuit Harbor (environmental assessment) Wellfleet Harbor (sampling & testing) Weymouth Fore & Town River (sampling & testing) New Hampshire Georges River (survey incomplete) Kennebec River Kennebunk River New Harbor Northeast Harbor Pig Island Gut Rockport Harbor Royal River (sampling & testing) Saco River (survey incomplete) Southwest Harbor Stonington (survey incomplete) Union River (sampling & testing) Wells Harbor Aug 1985 May 1985 Apr 1985 Oct 1984 Dec 1984 Dec 1984 Aug 1985 Feb 1985 Sep 1985 Dec 1984 Aug 1985 Sep 1985 May 1985 Hampton Harbor (sampling & testing) Rye Harbor (sampling & testing) Rhode Island Apponaug Cove Block Island Great Salt Pond Little Narragansett Bay Warwick Cove Westcott Cove (sampling & testing) Condition surveys conducted and completed unless otherwise noted. 1-52 Connecticut Aug 1985 Aug 1985 Apr 1985 Dec 1984 Jan 1985 Jan 1985 Jan-Feb 1985 Dec 1984 Dec 1984 Jun 1985 Jul 1985 May 1985 Apr 1985 Aug 1985 Aug 1985 May 1985 Apr 1984 Aug 1985 Apr 1985 Jun 1985 Jun 1985 Jun 1985 Oct 1984 Jul 1985 Jun 1985 NEW YORK, N.Y. DISTRICT* This district comprises western Vermont, small portions of western Massachusetts and Connecticut, eastern New York including Long Island, and northeastern New.Jersey, embraced in the drainage basins tributary to Lake Champlain and St. Lawrence River system east thereof and to the Atlantic Ocean from New York-Connecticut State line to, but not including, Manasquan Inlet, N.J. It exercises jurisdiction, however, Navigation over all matters pertaining to improvement of Great Lakes to Hudson River waterway. Under the direction of the Secretary of the Army, the District Engineer, as Supervisor of New York Harbor, also exercises jurisdiction under the laws enacted for the preservation of the tidal waters of New York Harbor, its adjacent or tributary waters, and the waters of Long Island Sound. IMPROVEMENTS Page 1. Aquatic Plant Control........................ 2-2 2. Bay Ridge-Red Hook Channels, N.Y............ 2-2 3. Bronx River, N.Y............................ 2-2 4. Buttermilk Channel, N.Y...................... 2-3 5. East Chester Creek, N.Y...................... 2-3 6. East River, N.Y............................. 2-4 7. East Rockaway Inlet, N.Y..................... 2-4 8. Fire Island to Jones Inlet, N.Y.................. 2-5 9. Hudson River, N.Y.......................... 2-5 10. Jamaica Bay, N.Y............................ 2-6 11. Jones Inlet, N.Y............................. 2-6 12. Keyport Harbor, N.J......................... 2-7 13. M oriches Inlet, N.Y.......................... 2-7 14. Narrows of Lake Champlain, N.Y............... 2-8 15. Newark Bay Hackensack Passaic Rivers, N.J..... 2-8 16. New York & New Jersey Channels .............. 2-9 17. New York Harbor-collection and removal of drift.............................. 2-9 18. New York Harbor-entrance channels & anchorage areas ............................. 2-10C 19. Port Chester Harbor, N.Y..................... 2-10C 20. Raritan River, N.J........................... 2-11 21. Sandy Hook Bay, N ......................... 2-12 22. Shinnecock Inlet, N.Y........................ 2-12 23. Shrewsbury River, N....................... 2-12 24. Supervisor of New York Harbor................ 2-13 25. 26. 27. Reconnaissance and condition surveys........... Other authorized navigation projects............ Navigation work under special authorization ...... 2-14 2-14 2-14 Beach Erosion Control 28. East Rockaway Inlet to Rockaway Inlet and Jamaica Bay, N.Y. (Part 1).................... 29. Sea Bright to Ocean Township, N.J............. 30. Other authorized beach erosion control projects .................................... 31. Beach erosion control work under special authorization................................ 32. 33. 34. 2-14 2-14 2-15 2-15 Flood Control Ardsley, N .Y................................ 2-15 Elizabeth, N ...... ............ ............ 2-15 Liberty State Park Levee and Seawall, N.J........ 2-16 35. 36. 37. 38. 39. 40. 41. Passaic River Basin, N.J. & N.Y. Phase I ........ 2-16 Sawmill River Elmsford-Greenburg, N.Y........ 2-17 Inspection of completed flood control projects ..... 2-18 Other authorized flood control projects........... 2-18 Dam Safety Program ......................... 2-18 Flood control work under special authorization .... 2-18 Emergency streambank and shoreline protection under special authorization........... 2-18 General Investigations 42. 43. 44. Surveys .................................... 2-18 Collection and study of basic data............... 2-18 Deauthorized projects........................ 2-18 Tables Table 2-A Cost & Financial Statement.............. 2-19 Table 2-B Authorizing Legislation.................. 2-23 Table 2-C Hudson River, N.Y. Features of Lock and Dam Included in Existing Project ..... 2-28 Table 2-D Total Costs for Existing Project........... 2-28 Table 2-E Supervisor of New York Harbor Statement of Activities.................. 2-28 Table 2-F Reconnaissance and Condition Surveys .... 2-29 Table 2-G Other Authorized Navigation Projects ..... 2-30 Table 2-H Other Authorized Beach Erosion Control Projects.............................. 2-31 Table 2-I Other Authorized Flood Control Projects... 2-32 Table 2-J Surveys............................. 2-33 Table 2-K Flood Plains Studies Completed During the Period............................ 2-33 Table 2-L Costs for Flood Plain Management Services.............................. 2-33 Table 2-M Deauthorized Projects.................. 2-34 Table 2-N Section 17 Continue Detailed Project Report............................... 2-35 Table 2-0 Section 13 Complete Preauthorization Reconnaissance Report................. 2-35 Table 2-P Section 25 Continue Preauthorization Reconnaissance Report................. 2-36 Table 2-Q Section 14 Complete Reconnaissance Reports .............................. 2-36 t Z 3 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Navigation 1. AQUATIC PLANT CONTROL Location. Navigable waters, tributary streams, connecting channels, and other allied waters in New York District. Existing Project. Provides for control and progressive eradication of water-hyacinth, alligator-weed, Eurasian water milfoil, and other obnoxious aquatic plant growths, from the navigable waters, tributary streams, connecting channels, and other allied waters of the United States, in the combined interest of navigation, flood control, drainage, agriculture, fish and wildlife conservation, public health, and related purposes, including continued research for development of the most effective and economic control measures (See Table 2-B for Authorizing Legislation.) Local cooperation. Local interests must provide 30 percent of the cost of the program except as modified by 1962 River and Harbor Act and agree to hold the United States free from damages. Operations and results during period. During the fourth year of a ten year control program for removal of nuisance aquatic plants in Lake Champlain, work was performed for removal of these plants in South Bay and St. Albans Bay at a cost of $126,000. Condition as of September 30. Reconnaissance report covering the aquatic plant problems of the North Atlantic Division area was completed in August 1967. Planning for the waterchestnut control in the Hudson-Mohawk basin was completed by the New York District, contracts for $181,562 accomplished during FY1971 through FY1976. Reconnaissance report for Lake Champlain, Vermont and a General Design Memorandum have been completed. 2. BAY RIDGE AND RED HOOK CHANNELS, N.Y. Location. These channels lie along east shore of Upper Bay, New York Harbor and, with Buttermilk Channel, form an easterly channel along Brooklyn waterfront from the Narrows to East River. (See Coast and Geodetic Survey Charts 12327 and 12334) Previous projects. For details see Annual Reports for 1915 and 1938, pages 1768 and 195, respectively. Existing projects. A channel 1,200 feet wide and 40 feet deep at mean low water from the Narrows to Bay Ridge Avenue, Brooklyn, thence 1,750 feet wide to junction of Bay Ridge and Red Hook channels, thence 1,200 feet wide through Red Hook Channel to junction with Buttermilk Channel and a channel of same depth extending into Gowanus Bay from junction of Bay Ridge Channel with Red Hook channel, narrowing uniformly in width to about 500 feet at 28th Street, Brooklyn. Section included in project is 4 miles long. Mean tidal range, 4.7 feet; mean range of spring tides, 5.6 feet; irregular fluctuations due to wind and atmospheric pressure vary from 3.9 feet below mean low water up to 5.2 feet above mean high water. New work for completed project cost $4,277,197, exclusive of amounts expended on previous projects. (See Table 2-B for Authorizing Legislation). Local cooperation. None required. Terminal facilities. See Port Series No. 5, revised 1978. Vol. 2. Operations and results during period. A continuing contract for the removal and satisfactory disposal of all material except ledge rock, lying above the planes of 40 feet below mean low water in specified sections of Bay Ridge Channel, New York, was awarded December 21, 1984. Work commenced March 12, 1985 and was completed July 12, 1985. Condition as of September 30. Work under existing project was commenced March 1901 and completed June 1940. 3. BRONX RIVER, N.Y. Location. Empties into a shallow bay in north shore of East River, 11 miles by water northeast of the Battery, New York City. (See National Ocean Survey Chart 12339.) Previous projects. For details see Annual Report for 1915, page 1762, and Annual Report for 1938, page 166. Existing project. A channel 10 feet deep at mean low water and 100 feet wide to extend from deep water in East River to the head of navigation at the dam at East 177th Street, involving the first dredging from East River at Randall Avenue to a width of 200 feet; thence to Spofford Avenue, 150 feet; thence to Watson Avenue, 125 feet; thence to railroad bridge near Westchester Avenue, 100 feet, except in southern approach to bridge, where it is to be 140 feet. Section included in project is about 2.4 miles long. Mean tidal range is 6.9 feet in the estuary; mean range of spring tides, 8.2 feet; irregular fluctuations due to wind and barometric pressure vary from 4 feet below mean low water up to 8.5 feet above mean high water. New work for completed active portion of project as described above cost $1,080,910, exclusive of amounts expended under previous projects, and exclusive of $10,000 contributed by local interests. Channel widening from Westchester Avenue to East 172d Street is considered inactive and excluded from foregoing description of existing project and cost estimate. Estimated cost of this portion (1953) is $299,000. For latest published map, see Annual Report for 1912, page 1470. (See Table 2-B for Authorizing Legislation.) Local cooperation. River and Harbor Act of 1913, provides that any right-of-way that may be necessary for the execution of the project shall be furnished free of cost to the United States. Right-of-way within bulkhead lines below Westchester Avenue Bridge was accepted by Chief of Engineers June 1920, and above the Westchester Avenue Bridge October 1928. On September 10, 1940, the Chief of Engineers approved releases from damages furnished by adjoining property owners between Westchester Avenue and East 174th Street. On November 12, 1940, the Chief of Engineers approved an agreement under which City of New York would reimburse the United States for cost of a retaining wall to protect adjoining property in reach of river between Westchester Avenue and New York, New Haven and Hartford Railroad bridge in lieu of furnishing additional right-ofway. On October 28, 1940, the Secretary of War authorized the acceptance of $10,000 from the city of New York to defray the cost of retaining wall. Additional right-of-way required in the section below East 172d Street has not been furnished. Ci- 2-2 NEW YORK, N.Y. DISTRICT ty of New York indicated it does not feel justified in acquiring any additional land along the river. Terminal facilities. See Port Series No. 5, revised 1978, Vol. 2. Operations and results during period. Operations and Maintenance funds in the amount of $59,390 was expended on engineering and design of maintenance dredging specifications for work which will be accomplished in FY 1986. Condition as of September 30. Work under entire existing project is about 82 percent complete. Active portion of existing project was commenced in 1914 and completed in 1941. A channel to project dimensions was completed from deep water in East River up to the Westchester Avenue Bridge in 1926. A channel 10 feet deep and 123 to 65 feet wide from Westchester Avenue Bridge to East 174th Street was completed in 1941. Work remaining under existing project consists of widening reach between Westchester Avenue Bridge and East 172d Street. Channel between 172d Street and the upper limit of authorized project was filled in by City of New York under a Department of the Army permit and is no longer a waterway. 4. BUTTERMILK CHANNEL, N.Y. Location. Connects deep water in Upper Bay, New York Harbor, southwest of Governors Island, with deep water in East River northeast of Governors Island, and, with Bay Ridge and Red Hook Channels, forms an easterly channel along Brooklyn waterfront from Narrows to East River. It lies between Governors Island and Borough of Brooklyn, New York City. (See Coast and Geodetic Survey Charts 12334 and 12335). Previous projects. For details see page 205, Annual Report for 1932. Existing project. A channel 1,000 feet wide, 40 feet deep at mean low water for width of existing 500-foot channel and 35 feet deep for remaining 500-foot width of existing channel. Suitable widening at junctions with East River and Anchorage Channel to 35 feet deep and with Red Hook Channel to 40 feet deep and for additional widening with Anchorage and Red Hook Channels to provide a minimum clear channel width of 2,100 feet to 35 feet deep. Section included in project is 2.25 miles long. Mean tidal range 4.4 feet; mean range of spring tides, 5.3 feet, irregular fluctuations due to wind and atmospheric pressure vary from 3.8 feet mean low Water up to 5.2 feet above mean high water. New work for completed projected cost $4,093,951, exclusive of amounts expended on previous projects. (See Table 2-B for Authorizing Legislation.) Local cooperation. None required. Terminal facilities. See Port Series No. 5, revised 1978. Operations and results during period. A contract was awarded December 4, 1984 for the removal and satisfactory disposal of all material except ledge rock, lying above the planes of 35/40 feet below mean low water in specified sections of Buttermilk Channel, New York. Work commenced January 9, 1985 and was completed February 6, 1985. Removed 113,382 cubic yards, place measurement of material at a total packet cost of $640,000. 2 Condition as of September 30. Work under existing project commenced October 1903 and was completed March 1965. Easterly 500-foot width of channel, from Anchorage Channel to East River, was completed to a 40-foot depth in May 1935. Westerly 500-foot channel, including widening the junction with East River, was completed to a 35-foot depth in July 1961. Widening the junctions with Anchorage and Red Hook Channels was completed in March 1965. Total cost of existing project to September 30, 1982 was $8,971,475, $122,051 piublic works funds and $3,971,900 regular funds, a total of $4,093,951 for new work and $4,877,524 for maintenance. 5. EAST CHESTER CREEK, N.Y. Location. This creek, also known as Hutchinson River, is a small tidal stream emptying into East Chester Bay, and indentation in north shore of Long Island Sound immediately north of Throgs Neck, 12 miles southwest of Connecticut State line and 21 miles by water northeast of the Battery, New York City. (See Coast and Geodetic Survey Chart 12366.) Previous projects. For details see Annual Reports for 1915, 1929, 1938 and 1949, pages 1761, 167, 163, and 208, respectively. Existing project. A channel.10 feet deep at mean low water and generally 150 feet wide from Long Island Sound through East Chester Bay to a point 700 feet below Boston Post Road Bridge, and thence 70 feet wide extending to a point where the creek divides into a Y, thence approximately 1,000 feet into east branch of the Y and approximately 500 feet into west branch of the Y; a passing basin south of Boston Post Road Bridge; widening channel at Boston Post Road Bridge; and construction of a check dam at head of navigation. Section included in project is 5 miles. Mean tidal range, 7.3 feet in the estuary; mean range of spring tides, 8.6 feet; irregular fluctuations due to wind and atmospheric pressure vary from 3.9 feet below mean low water up to 8.1 feet above mean high water. Estimate of cost for new work is $2,550,000 (October 1975) exclusive of amounts expended on previous projects and inclusive of an estimated $40,000 non-Federal cost for lowering utilities, (See Table 2-B for authorizing legislation.) Local cooperation. River and Harbor Act of May 17, 1950, provides that local interests furnish lands, rights-of-way, and suitable areas for disposal of dredged material during construction and future maintenance, and hold the United States free from damages. City of New York has complied with requirements. Assurances are yet to be received from other local interests concerned with improvement. Terminal facilities. See Port Series No. 5, revised 1965, Vol. 2, Part 2. Operations and results during period. A contract for the removal and disposal of all material except ledge rock lying above the planes of 8 feet below mean low water in specified sections of East Chester Creek, New York was awarded February 20, 1985. Work commenced March 25, 1985 and was completed May 11, 1985. Removed 57,451 cubic yards, place measurement, of material for a total cost to project of $716,771. This work was performed under the previous project adopted in 1930 which provided for a channel 8 ft. deep at mean low water and generally 150 ft. wide from Long Island -3 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Sound through East Chester Bay to a point 700 ft. below the Boston Post Road Bridge, and thence 70 ft. wide to the northern terminus of the project, about 300 ft. above the Fulton Avenue Bridge and for a passing basin in the vicinity of the Boston Post Bridge. Work was completed in August 1941. Condition as of September 30. No work has been accomplished under the existing project. Work under the 1930 project was completed in August 1941. 6. EAST RIVER, N.Y. Location. A tidal strait about 16 miles long and 600 to 4,000 feet wide, connecting Hudson River and the Upper Bay at the Battery, New York City, with Long Island Sound at Throgs Neck, New York City, and separating Long Island from Manhattan Island and the mainland. (See National Ocean Survey Charts 12335, 12339, and 12366.) Previous projects. For details see page 210 of Annual Report for 1932. Existing project. Channels of following dimensions (depths refer to mean low water): From deep water in Upper New York Bay to Wallabout Channel, 40 feet deep and 1,000 feet wide; from Wallabout Channel to Throgs Neck, 35 feet deep, with widths varying from about 550 to 1,000 feet according to locality; east of F.D. Roosevelt Island up to English Place (43d Dr.), Long Island City, 30 feet deep and varying in width from 500 to 900 feet, with widening in approach from main channel; between South Brother and Berrian Islands, 20 feet deep and 300 feet wide, with widening in approach from main channel; from East River channel to Astoria waterfront, a flared 0.31 mile entrance channel 1,600 to 400 feet wide, a 0.64 mile channel 400 feet wide, and a turning basin 1,000 feet wide and 1,600 feet long, all 37 feet deep in rock and 35 feet in soft material (South Brother Island Channel); removal of Coenties Reef to a depth of 40 feet, also removal of following rocks and reefs lying outside of limiting lines of main channel to give access to wharves: Along Brooklyn shore, Brooklyn Bridge to Manhattan Bridge (Fulton Ferry Reef), to a depth of 25 feet; Jay Street Reef, 25 feet; Corlears Reef, 35 feet; Shell Reef, 25 feet; Horns Hook, 40 feet; Rhinelander Reef, 26 feet; and reef off Oak Point, 30 feet; and construction of a dike in Pot Cove in Hell Gate. Section included in improvement is about 17.8 miles long. Mean range of tide varies according to locality from 4 feet at North Third Street, Brooklyn, and 4.4 feet at the Battery to 4.9 feet at Hallets Point, 6.3 feet at Port Morris, and 7.1 feet at eastern entrance at Throgs Neck; mean range of spring tides 4.8, 5.3, 5.9, 7.6, and 8.5 feet, respectively; irregular fluctuations due to wind and atmospheric pressure vary according to locality from 3.8 feet below mean low water at the Battery, 2.4 feet at North Third Street, Brooklyn, and 3.8 feet at Throgs Neck up to about 5.2 feet above mean high water at the Battery and 8.4 feet above mean high water at Throgs Neck; extreme fluctuations do not seriously affect navigation. Local cooperation. Resolutions of 1970 require local interests to furnish lands, easements and rights-of-way for construction and maintenance; hold the United States free from damages; provide and maintain depths in berthing areas and local access channels serving the terminals commensurate with project depth; provide upon transfer to the United States, a depth in the existing South Brother Island Channel and turning basin of not less than 30 feet; and establish regulations prohibiting discharge of untreated sewage, garbage, and other pollutants in the waters of the harbor, which shall be in accordance with regulations of Federal, State and local authorities responsible for pollution control. Assurances of local cooperation were furnished by the Port Authority of New York and New Jersey under date of April 9, 1974. Terminal facilities. See Port Series No. 5, revised 1978. Vol. 2. Operations and results during period. A contract for the removal and disposal of all material except ledge rock lying above the plane of 35 feet below mean low water in specified areas of the South Brother Island Channel, East River, N.Y. was awarded April 5, 1985. Work commenced June 3, 1985 and was completed July 13, 1985. Removed 257,102 cubic yards place measurement, of material for a total cost to project of $1,436,030. Condition as of September 30. Work under existing project was commenced June 1916 and was essentially completed in November 1976. Construction of dike at Pot Cove in Hell Gate and a part of widening near pierhead line in Jay Street Reef are considered unnecessary for the needs of current navigation. 7. EAST ROCKAWAY INLET, N.Y. Location. On south shore of Long Island between main body of island and western end of Long Beach. It is 10 miles east of Rockaway Inlet and about 27 miles by water south and east from the Battery, New York City. (See National Ocean Survey Chart 12352.) Existing project. A channel 12 feet deep at mean low water and 250 feet wide from 12-foot contour in Atlantic Ocean for about 0.6 mile to 12-foot contour in Long Beach Channel protected by a jetty. Mean tidal range, 4.3 feet; mean range of spring tides, 5.2 feet; irregular fluctuations due to wind and atmospheric pressure vary from 3.9 feet below mean low water up to 5.6 feet above mean high water. New work for completed project cost $603,969, including $100,000 contributed funds. (See Table 2-B for Authorizing Legislation.) Local cooperation. Complied with. Terminal facilities. There are 39 terminals in Oceanside, Island Park, Long Beach, and East Rockaway. Nine of these are oil terminals, one of which has a railroad spur. Other terminals are repair and mooring docks with a berthage of 7,655 feet. Of these, 21 have marine railways and 1 has mechanicalhandling facilities. There are public wharves at East Rockaway and Woodmere. Waterfront on northside of Long Beach has been bulkheaded. Facilities are considered adequate for existing commerce. Operations and results during period. A continuing contract for the removal and disposal of all material except ledge rock lying above the plane of 14 feet below mean low water in the Inlet was awarded June 28, 1985. Work commenced September 19, 1985 and was continuing at the end of the Fiscal Year. Removed 132,000 cubic yards, place measurement, of material under this contract in FY 1985 at a cost to project of $377,768. 2-4 NEW YORK, N.Y. DISTRICT Condition as of September 30. Work under existing project began February 1933 and is 100 percent complete. East jetty, 4,250 feet long, was completed in July 1934. Project channel was completed in May 1935. 8. FIRE ISLAND TO JONES INLET, N.Y. Location. On south shore of Long Island, about 50 miles by water south and east of the Battery, New York City. Fire Island Inlet is the main entrance into Great South Bay from the Atlantic Ocean. (See Coast and Geodetic Survey Chart 12352) Existing project. A jetty extending generally southwest and south for 5,000 feet from high ground on Democrat Point at the west end of Fire Island and a channel 18 feet deep and 500 feet wide from a littoral reservoir (sediment trap) in the ocean to deep water in the inlet. Mean tidal ranges at the ocean and inlet ends of Democrat Point are 4.1 ft. and 2.4 ft. respectively. Irregular fluctuations due to wind and atmospheric pressure vary from 2.5 feet below mean low water up to 6.2 feet above mean high water on the ocean side. (See Table 2-B for Authorizing Legislation). Local cooperation. Requires cost sharing and lands easements & rights-of-way. Terminal facilities. None within the area immediately adjacent to the Federal improvement. Operations and results during period. At the request of local interests, maintenance dredging was postponed in 1979 until the completion of an Inlet Dymanic Study. The residents of Oak Beach contend that dredging the Inlet exposes Oak Beach to direct wave attack thereby causing an erosion problem. The Inlet Dynamic Study was completed in 1985 and a resumption of the project with provision for possible protection of Oak Beach if necessary is being studied. Condition as of September 30. Work under the existing project was commenced in late 1973. As a result of three consecutive dredging operations completed in 1977, the project channel was brought to the approximate authorized dimension at that time. No maintenance dredging was accomplished in the ensuing time period. Due to the aforementioned local concerns maintenance has been deferred since 1979 which has allowed the complete shoaling of the authorized channel. 9. HUDSON RIVER, N.Y. Location. Originates in Adirondack Mountains, about 250 miles in a direct line and 315 miles along its course from the Battery, New York City, and flows generally southerly into New York Bay. Section under improvement extends from New York City about 156 miles to Waterford. (See National Ocean Survey Charts 12335, 12341, 12343, 12347, 12348, and 14786.) Previous projects. For details see Annual Reports for 1915 and 1938, pages 1764 and 226, respectively. Existing project. A channel 600 feet wide from New York City to Kingston and thence 400 feet wide to Albany, with widening at bends, a turning basin 700 fet wide and 1,200 feet long at Albany, and 2 anchorages, 1 near Hudson and 1 near Stuyvesant, each 400 feet wide and an average length of 2,400 feet; all with depths of 32 feet in soft material and 34 feet in rock to 2,200 feet south of the Mall Bridge; thence 27 feet deep and 400 feet wide to 900 feet south of the Mall Bridge, thence 14 feet deep at lower low water and generally 400 feet wide to Federal lock at Troy; and thence of same depth and 200 feet wide to southern limit of State barge canal at Waterford; and removal of State dam at Troy and construction of a lock and dam about 2.50 miles below Waterford. Channel is to be formed by dredging and rock excavation, and maintained by dredging and constructing new, and raising and repairing old, longitudinal dikes, built partly under previous projects and partly by the State of New York. Mean range of pool elevation above Federal dam at Troy, in seasons of moderate rains, is about 2.2 feet, as determined in 1934. Mean tidal range is about 4.8 feet between May and October and 5.1 feet between July and September at Albany, extreme range due to freshets is 33.1 and 25.9 feet, respectively normal pool level above Federal dam from Troy to Waterford is 14.33 feet above mean sea level. In tidal section of river below dam, assumed lowest low water plane from Troy to Albany is 3 feet below mean sea level. (See Table 2-C for features of lock and dam included in existing project.) New work for completed project cost $39,050,019 exclusive of amounts of expended on previous projects. Widening to form harbors at Albany and Troy, N.Y., to 12 feet deep at a cost of $552,000 (1954) and completion of 27-foot channel at Albany at a cost of $458,000 (1957) are inactive. Construction of dikes at a cost of $642,000 (1957) was placed in deferred for restudy category. All three features of work are excluded from foregoing description of existing project and cost estimate. Construction of mooring facilities has been authorized. (See Table 2-B for Authorizing Legislation.) Local cooperation. Complied with except that local interests must furnish suitable soil disposal areas for future maintenance as required. Terminal facilities. See Port Series No. 6, revised 1979. Operations and results during period. A contract in the amount of $96,500 was awarded August 14, 1985 for construction of rip-rap along the shoreline of the Albany Turning Basin, Hudson River at Rensselaer, New York. Of the contract amount, $80,000 was federal funds, while the remaining $16,500 were contributed funds for the reconstruction of a storm sewer outfall through the rip-rap. Work commenced on 16 September 1985 and was continuing at end of Fiscal Year. Operations and Maintenance funds in the amount of $74,060 was expended on engineering, design and preparation of maintenance dredging specifications for work which will be accomplished in FY1986. By use of Government plant and hired labor, stumps and snags which formed a potential menace to navigation, and other obstructions, were removed from the shores and channel of the river at a cost of $190,055 for maintenance in FY 1985. Government plant and hired labor were employed intermittently through the fiscal year in performing surveys to restore horizontal and vertical controls at a cost of $166,811 for maintenance in FY1985. Government plant and hired labor were employed intermittently through the fiscal year on repairs to Cedar Hill Dike at a cost of $120,079 for maintenance in FY1985. 2-5 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 The lock and dam on the Hudson at Troy, N.Y. were operated and maintained. Operation of Lock for 1985 navigation season was suspended December 10, 1984 and resumed April 26, 1985. Cost incurred was $507,056 for Operation and Maintenance in FY1985. In Fiscal Year 1984, two contracts were let to determine the extent of deterioration and needed repairs to the Troy Lock and Dam. In Fiscal Year 1985, it was decided to defer the recommended concrete repairs to the dam and resurfacing of the lock pending completion of an ongoing investigation of concrete resurfacing surfaces by W.E.S. under R.E.M.R. program. Scopes of work for an interim repair program to ensure continual safe operation of the lock and dam will be prepared in Fiscal Year 1986. Condition as of September 30. Work under existing project began in July 1910 and was substantially completed in November 1965. New lock and dam at Troy, removal of dam at Troy and construction of 15,545 linear feet of dikes also are complete. In reconstruction of old dikes 39,676 linear feet were raised to adopted crest height. Channel from New York City to Albany is complete to a depth of 32 feet except for the 1,500 linear-foot section at the northern end of the 32-foot project which has never been dredged to project depth. Additionally, the 1,300 linear feet of the 27-foot project remains undredged. Channel from Albany to Waterford is complete to a depth of 14 feet except for a small part of the widening to form a harbor at Troy. Work remaining under the project consists of completion of the 12-foot harbor at Troy and dredging the 27-foot and the remainder of the 32-foot channels at Albany which are not deemed necessary at this time; and reconstruction of dikes. Started coordination with State regarding mooring facilities. (See Table 2-D for total costs of existing project to September 30, 1983.) 10. JAMAICA BAY, N.Y. Location. Inside south shore of Long Island, the entrance being about 17 miles by water south and east of the Battery, New York City. (See National Ocean Survey Chart No. 12350). Prev'ous projects. For details see page 1770 of Annual Report for 1915, and page 185 of Annual Report for 1938. Existing project. Provides for an interior channel extending from vicinity of Marine Parkway Bridge along west and north shores of the bay, 18 feet deep at mean low water and 300 feet wide to Mill Basin, with a swinging basin, 1,000 feet wide and 1,000 feet long at the point; thence 12 feet deep and 200 feet wide to Fresh Creek Basin; and interior channel extending from the same locality along south shore to Head of Bay, 15 feet deep and 200 feet wide; a channel in Mott Basin, 15 feet deep and 200 feet wide extending from the channel along south shore, 3,000 feet to junction of the two branches, thence 2,200 feet in north branch (Inwood Creek) and 3,200 feet in south branch; and an entrance channel connecting the two interior channels with deep water in Atlantic Ocean, of suitable hydraulic dimensions to maintain present tidal prism in the bay, but not less than 18 feet deep and 500 feet wide from opposite Barren Island to Rockaway Point, thence enlarging to not less than 200 feet deep and 1,000 feet wide to the sea, protected by one riprap jetty. Length of section included in project is 19.7 miles. Mean tidal range, 4.9 feet at Barren Island, and 5.1 feet at Head of Bay; mean range of spring tides, 5.9 and 6.1 feet, respectively; irregular fluctuations due to wind and atmospheric pressure vary from 4 feet below mean low water to 4.9 feet above mean high water. Cost for new work for completed project is $4,466,421 (July 1961), excluding amounts expended on previous projects. Local cooperation. River and Harbor Act of 1945 provides that in lieu of conditions heretofore prescribed local interests furnish suitable areas for disposal of dredged materials for new work and subsequent maintenance, and hold the United States free from damages. City of New York was notified of conditions of local cooperation in letter dated January 25, 1946. In letter dated February 7, 1946, the Mayor of City of New York advised that disposal areas are available and necessary document "holding the United States free from claim for damages" would be executed. River and Harbor Act of 1950 provides local interests furnish lands, easements, rights-of-way, and suitable areas for disposal of dredged material during construction and subsequent maintenance, hold the United States free from damages and peform all necessary alterations to existing terminals and bulkheads, and dredge adequate approaches thereto. These conditions have been fulfilled. Terminal facilities. See Port Series No. 5 revised 1978. Operations and results during period. A contract was awarded June 21, 1985 for removal and disposal of all material except ledge rock lying above the plane of 20 feet below mean low water in the entrance channel to Jamaica Bay, New York. Work commenced July 1, 1985 and was completed July 26, 1985. Removed, 181,685 cubic yards, place measurement, of material at total cost to project of $1,284,412. Condition as of September 30. Work under existing project was commenced in August 1912 and completed in June 1961. Westerly interior channel from Barren Island to Fresh Creek Basin and swinging basin at Mill Basin were completed in April 1929. Southerly interior channel and channel in Mott Basin, including its two branches were completed in June 1961. No new work dredging of entrance channel was done, since depths provided under previous project were greater than those required under existing project. East jetty was restored to project dimensions in August 1963. 11. JONES INLET, N.Y. Location. A small inlet on south shore of Long Island connecting Hempstead Bay with Atlantic Ocean, 37 miles by water southeast of the Battery, New York City. (See National Ocean Survey Chart 12352). Existing project. An entrance jetty and a channel 12 feet deep and 250 feet wide, from that depth in the ocean through the inlet to Loop Causeway Bridge over Long Creek. Section included in project is about 2.1 miles long. Mean tidal range varies from 4.2 feet at ocean entrance to 3.1 feet at Loop Causeway Bridge; mean range of spring tide varies from 5 to 3.7 feet, respectively; irregular fluctuations due to wind and atmospheric pressure vary from 3.9 feet below mean low 2-6 NEW YORK, N.Y. DISTRICT water up to 8.5 feet above mean high water. (See Table 2-B for Authorizing Legislation.) Local cooperation. Complied with except that local interests must furnish suitable spoil-disposal areas for future maintenance as required, and must maintain a channel 12 feet deep and generally 200 feet wide from Loop Causeway Bridge over Long Creek to head of navigation in Freeport Creek at Mill Road. Terminal facilites. Within area tributary to Jones Inlet there are a number of privately owned small wharves and 40 boat repair and storage yards. The latter are equipped for repair of pleasure craft and fishing vessels. In addition, there are nine public wharves open to the public free of charge, with a total dockage of 2,180 feet. Additional terminals would have to be constructed for receipt of commercial freight in any sizable quantity. Operations and results during period. A contract was awarded June 28, 1985 for removal and disposal of all material except ledge rock lying above the plane of 14 feet below mean low water in specified sections of the Inlet. Work commenced August 17, 1985 and was completed September 14, 1985. Removed, 136,980 cubic yards, place measurement of material at a total project cost of $1,699,398. Condition as of September 30. Work under existing project was commenced August 1953 and completed June 1959. JONES INLET - JETTY REHABILITATION ($34,500.00). The purpose of this study is to develop a feasible and cost effective design for rehabilitation of the Jones Inlet Jetty to insure structural stability and maximize the sand trapping efficiency of the structure. Inlet hydrographic and existing jetty condition surveys have been performed. Preliminary design and cost estimates for alternative schemes have been developed and the superior scheme recommended. Study completion is January 1985. JONES INLET -MAINTENANCE MODIFICATIONS ($49,264.40). The purpose of this study is to develop feasible and cost efficient alternatives which would minimize channel maintenance requirements. Existing tidal/inlet hydraulics, inlet/bay stability, jetty impoundment rates, etc., have been evaluated. Several methods of shoaling analysis were reviewed and the most applicable used. Preliminary design layouts and cost estimates for a deposition basin and navigation channel have been developed and the superior scheme recommended. Study completion is January 1985. 12. KEYPORT HARBOR, N.J. Location. At mouth of Matawan Creek, on south side of Raritan Bay, about 9 miles west of Sandy Hook. (See Coast and Geodetic Survey Chart No. 12327). Existing project. A channel about 1 mile long from Raritan Bay to the steamboat dock at Keyport, 200 feet wide and 8 feet deep. Mean range of tides is 4.9 feet; mean range of spring tides, 5.9 feet. High easterly or westerly winds cause tides to fluctuate from 3.8 feet below mean low water up to 5.9 feet above mean high water. Local cooperation. None required. Terminal facilities. There are two privately owned wharves located at the head of improvement, both in poor condition. Operations and results during period. A contract for maintenance dredging of channel to restore project depths was awarded in FY 84. Work started October 22, 1984 and was completed November 7, 1984. A total of 135,294 cubic yards, place measurement, of material was removed. Expended $30,979 in Fiscal Year 1985 for a total project cost of $603,000. Condition. As of September 30. Work under the existing project was commenced June 1883 and was completed October 1911. 13. MORICHES INLET, N.Y. Location. On the south shore of Long Island, about 80 miles by water east of the Battery, New York City. It is an opening through the narrow sandy barrier beach on the south shore of Long Island which separates the Atlantic Ocean from a series of interconnected bays. (See Coast and Geodetic Survey Chart 12352.) Existing project. Provides for a channel, 10 feet deep at mean low water and 200 feet wide extending from that depth in the Atlantic Ocean to Moriches Bay, a distance of 0.7 mile; thence a channel 6 feet deep and 100 feet wide to the Long Island Intracoastal Waterway, a distance of 1.1 miles; rehabilitation of the existing jetties and revetments. Estimate of cost for work is $10,000,000 (October 1985 P.L.) including $50,000 from Coast Guard and $5,000,000 to be contributed by local interests. (See Table 2-B for Authorizing Legislation.) Local cooperation. In accordance with the project authorization, local interests are required to furnish all easements, rights-of-way including relocations that are necessary for improvements and operate and maintain the project at a cost sharing basis to be negotiated subsequent to the passage of Federal legislation. The annual Operations and Maintenance cost is estimated to be $1,810,000. Local interests have agreed to voluntarily pay 50% of the project cost but not less than that required by the project authorization presently estimated at $5,000,000. The New York State Department of Environmental Conservation, the local sponsor, in a January 6, 1983 letter, indicated its intent of comply with the items of local cooperation and reaffirmed this on November 8, 1985. Terminal facilities. No terminals are within the area immediately adjacent to the Federal improvement. However, numerous public and private terminal facilities are available in Moriches Bay and in the connecting canals. Several yacht clubs, boatyards, and public wharfs and landings, and numerous private landings are located in Moriches Bay. The yacht clubs and boatyards have equipment for servicing boats. There are boat basins open to the public. The facilities existing in the bay are considered adequate for present and probable future needs under present conditions of Moriches Inlet. There is room for expansion should future commerce warrant. Operations and results during period. Preconstruction planning resumed in October 1977. Coordination continued with Federal, State and local agencies on current problems and need for all project purposes (i.e. navigation; beach erosion control; water quality improvement). Formulated plans for single purpose navigation project. 2-7 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 In January 1980, a breach occured adjacent to the eastern jetty. Emergency funds ($11.3 million) were authorized under the authority of PL84-99 to close the breach. About 1,185,000 yards of sand fill were used to effect closure of the breach by March 1981. Condition as of September 30. Construction has not been initiated. Preconstruction planning (advance engineering and design) has been completed and contract plans and specifications are being prepared. 14. NARROWS OF LAKE CHAMPLAIN, N.Y. AND VT. Location. This waterway, 37 miles long, comprises southern end of Lake Champlain and extends from Whitehall to Crown Point, N.Y. at southern extremity of lake, northerly to Benson Landing, Vt. (See National Ocean Survey Chart 14784). Previous projects. For details, see Annual Reports for 1931, and 1963, pages 256 and 177, respectively. Existing project. A channel extending from Whitehall, N.Y., at head of Lake Champlain, to Benson Landing, 12 feet deep at low lake level and generally 150 feet wide, and installation of fender booms at Putts Rock, Putts Leap, Narrows near Dresden Pulpit Point and Cedar Mountain. Reference plane of low lake level is 93 feet above mean sea level. Section included in project is about 13.5 miles. Usual annual variation of lake level is 5.8 feet and extreme variation varies from 0.6 foot below up to 8.8 feet above low lake level. Widening channel throughout its entire length to project width of 20 feet is inactive and excluded from foregoing description of existing project and cost estimate. Estimated cost of this portion, revised in (1954), was $1,573,000. (See Table 2-B for Authorizing Legislation.) Local cooperation. None required. Terminal facilities. In Whitehall Harbor consisting of three timber wharves, aggregating 4,200 feet in length. State of New York constructed a barge canal terminal at Whitehall, just south of terminus of canal, which has been equipped with a 5-ton hand-operated derrick and a storehouse. Facilities are considered adequate for present commerce. Operations and results during period. Government and hired labor were employed intermittently during the fiscal year in removal of stumps and snags at a cost of $10,556. Government plant and hired labor were employed in replacing deteriorated fender booms at a cost of $7,048. Total costs for the project was $25,228. Operations and Maintenance funds in the amount of $4,099 was expended on engineering and design of maintenance dredging specifications for work which will be accomplished in FY1986. Condition as of September 30. Work under the existing project was commenced June 1919 and is about 77 percent complete. A channel 12 feet deep at low lake level and least a width of 150 feet has been excavated throughout the length of the improvement, except at the Elbow (Putts Leap and Putts Rock). (Fender booms opposite the Delaware and Hudson Railroad trestle have been removed as they are no longer considered necessary for navigation). The work remaining to complete the project consists of widening the channel throughout its entire length to the project width of 200 feet. 15. NEWARK BAY, HACKENSACK AND PASSAIC RIVERS, N.J. Location. Newark Bay is an estuary about 1.25 miles wide and 6 miles long extending southerly from confluence of Hackensack and Passaic Rivers to New York and New Jersey Channels. Hackensack River rises near Haverstraw, Rockland County, N.Y. and flows about 45 miles into Newark Bay. Passaic River rises in highlands of northeastern New Jersey and flows about 80 miles into Newark Bay. (See Coast And Geodetic Survey Charts 12333 and 12337.) Previous projects. For details see 1926 Annual Report, pages 265 and 266; and Annual Reports for 1929, 1938, 1954, and 1976, pages 301, 244, 134, and 2-11, respectively. Existing project. A main channel 700 feet wide to the branch channel to Port Newark, thence 500 feet wide to a turning basin 1,300 feet long and 900 feet wide at the junction of the Hackensack and Passaic River channels, length about 4.7 miles;, a maneuvering area south of. the former Central Railroad of New Jersey Bridge 2,200 feet long and 300 feet wide with depths of 38 feet in the south half and 35 feet in the north half; a combined bend cutoff and maneuvering area at the south side of the junction with Elizabeth branch channel; and widening of bends at the Kill Van Kull and Port Newark Channels. (Authorized depth 35 feet except as noted above.) (adopted 1966). At Port Newark-A branch channel 800 feet wide leading to an inshore channel 400 feet wide 1.6 miles (adopted 1945). Authorized depth 37 feet in rock and 35 feet in soft material; a pierhead channel 200 feet wide along the east bulkhead between the Port Newark and Elizabeth branch channels, length 4,100 feet. Authorized depth 35 feet (adopted 1962). At Elizabeth Marine Terminal-A branch channel 500 feet wide, length about 1.4 miles; a pierhead channel along the east bulkhead 290 feet wide, length about 1.1 miles; a south channel along the south bulkhead 290 feet wide, length about 2,600 feet; a southern approach area just above Central Railroad of New Jersey Bridge enlarged for turning and maneuvering, with a maximum length of about 2,700 feet and width (between the pierhead channel and Newark Bay channel) of about 800 feet. Authorized depth 35 feet (adopted 1962). Local cooperation. River and Harbor Act of 1954 provides local interests furnish lands, rights-of-way, and suitable spoil-disposal areas for initial construction and future maintenance; provide depths commensurate with channel depth in approaches and berths at terminals of companies which would use improvement; and hold the United States free from damages. River and Harbor Act of 1962 provides that local interests must provide lands, easements and rightsof- way for maintenance and construction, hold United States free from damages. River and Harbor Act of 1962 provides that local interests must provide lands, easements and rightsof- way for maintenance and construction, hold United States free from damages, provide and maintain adequate public terminal and transfer facilities, and accomplish without cost to the United States, removal or relocation of pipelines, cable and other utilities. Assurances were furnished by Port of New York Authority and accepted June 12, 1964. Local cooperation required by previous modifications is fully complied with. 2-8 NEW YORK, N.Y. DISTRICT Terminal facilities. See Port Series No. 5, revised 1978, Vol. 2. Operations and results during period. Operations and Maintenance funds in the amount of $33,598 was expended on engineering and design of maintenance dredging specifications for work which will be accomplished in FY1986. Condition as of September 30. Work under the active portion of project began June 1976 and is 100 percent complete. Work remaining to complete existing project consists of; deepening the Hackensack River channel to depths of 32 feet and 15 feet. Work was initiated for modification of project consisting of additional widening at junction with Kill Van Kull by deepening to 37 feet a triangular area at the eastern end of the 30 foot channel south of Shooters Island. Two contacts for the removal of all material including ledge rock to 37 feet mean low water were completed at a total cost of $4,402,631. 16. NEW YORK AND NEW JERSEY CHANNELS Location. Extends from deep water northwest of Sandy Hook, through Lower New York bay and Raritan bay, to Perth Amboy, and thence through Arthur Kill, lower Newark Bay, and Kill Van Kull to deep water in Upper New York Bay. This route is appoximately along boundary line between states of New York and New Jersey. (See Coast and Geodetic Survey Charts 12333, 12331, and 12327.) Previous projects. For details see 1963 Annual Report pages 184 and 185. Existing project. A channel through Lower New York Bay, Raritan Bay, Arthur Kill, lower Newark Bay, and Kill Van Kull to Upper New York Bay, depths of 37 feet in rock and 35 feet in soft material throughout, 600 feet wide across Lower New York Bay and Raritan Bay and in Arthur Kill to a point 1,000 feet north of Smith Creek, widened to 800 feet in vicinity of Seguine Point and Wards Point, respectively; thence 500 wide to a point 1,000 feet south of Piles Creek; thence 500 to 600 feet wide and passing north of Shooters Island and protected by a dike on its northern side to junction of channel into Newark Bay; thence 800 feet wide through Kill Van Kull to Constable Hook; thence 1,000 feet wide from a point opposite the east end of Constable Hook to a point near the intersection with the channel along New Jersey pierhead line; and thence 1,400 feet wide through Kill Van Kull to Upper New York Bay; with an anchorage 38 feet deep to accommodate five vessels south of Perth Amboy, all with suitable easing at bends and junctions. Section included in project is 30.8 miles long. In addition, construction of a dike north of Shooters Island and two secondary channels 30 feet deep and 400 feet wide, one south of Shooters Island and the other in Raritan Bay connecting with Raritan River, were completed under previous projects and maintained under existing project. A triangular area at the eastern end of the 30 foot channel south of Shooters Island was deepened to 35 feet in order to provide additional widening in the vicinity of Bergen Point and is included in the Newark Bay project. All depths refer to plane of mean low water. Mean range of tides varies between 4.7 and 5.1 feet; mean range of spring tides, 5.7 to 6.3 feet; irregular fluctuations due to wind and atmospheric pressure vary from 3.9 feet below mean low water up to 6.9 feet above mean high water. Anchorage at Sandy Hook, and cutoff at junction of Main Ship Channel are deferred for restudy and excluded from foregoing description and cost estimate. Estimated cost of this portion (1957) is $2,150,000. (See Table 2-B for Authorizing Legislation.) Local cooperation. Fully complied with except for the middle section of Arthur Kill where local interest must furnish spoil disposal areas for maintenance. Terminal facilities. See Port Series No. 5, revised 1978, Vol. 2. Operations and results during period. U.S. Army Corps of Engineers Dredge "McFARLAND" was employed from April 4, 1985 to May 31, 1985 to restore project dimensions in Wards Point Bend vicinity. Removed 165,298 cubic yards, place measurement, of material at a cost of $1,096,073. Conditions as of September 30. Work under active portion of existing project began in October 1933. Work completed consists of providing authorized project depth and widths throughout entire channel from Lower New York Bay to Upper New York Bay and providing depths of 37 and 25 feet in Perth Amboy Anchorage. In addition to above mentioned work, construction of a dike north of Shooters Island, two secondary channels 30 feet deep and 400 feet wide, one south of Shooters Island, the other in Raritan Bay connecting with Raritan River were completed under previous projects. Work remaining under existing project consists of dredging cutoff at junction of Main Ship Channel to dimensions authorized by River and Harbor Acts of August 30, 1935, and May 17, 1950, dredging anchorage in vicinity of Sandy Hook. (See Table 2-D for total cost for existing project to September 30, 1982.) 17. NEW YORK HARBOR COLLECTION AND REMOVAL OF DRIFT Location. Applies to Lower and Upper Bays, New York Harbor; East River, Harlem River, Hudson River Channel, N.Y., New York and New Jersey Channels, Newark Bay, N.J., and their tributaries. Existing project. Provides for collection, removal and disposal of drift, derelict vessels, deteriorated shore structures and debris along shores of New York Harbor and tributary waters, and for the repair of certain other piers, wharves and shore structures. Work authorized before Act of 1970 was restricted solely to removal of drift from waterways and was funded as a maintenance activity. Estimate of first cost of improvement under Act of 1974 is $77,000,000 (October 1985) including $25,700,000 cash contribution from local interests, plus $51,300,000 to be contributed for repair and disposal of deteriorated shore structures in use. (See Table 2-B for Authorizing Legislation.) Local cooperation. Local cooperation conditions of the plans currently under review by the Chief of Engineers provide that local interests must furnish all lands, easements and rights-of-way required for the improvement; hold the United States free from damages; enact and enforce local legislation to prevent creation of sources of drift, contribute in cash one third of the first cost of the Federal work, and make necessary 2-9 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 repairs to deteriorated structures in use so as to eliminate them as a source of drift. These conditions are subject to approval by the Secretary of the Army and the President, as stipulated in Section 113 of the authorizing law, Public Law 91-611. Operations and results during period. New work: Liberty State Park Contract IVB was completed at a cost of $1,268,000. East River-Manhattan Waterfront contract was completed at a cost of $1,477,806. A contract for the removal of Piers 17 and 18 on the East River was completed at a cost of $219,609. The City of Elizabeth contract was completed at a cost of $791,700. The Stapleton, Staten Island Contract was completed at a cost of $2,820,000. A contract for the City of Hoboken reach was awarded in August 1983 at an estimated cost of $2,165,000. A continuing contract for the Jersey City South Reach was awarded in September 1984 at an estimated cost of $838,000. Engineering and design for the balance of project continued. Maintenance. U.S. Debris Boats Driftmaster, Gelberman and Hayward and auxiliary plant were assigned the work of removing and disposing of drift. Removed and disposed of 560,000 cubic feet (4,379 cords) of driftwood, ranging in size from small blocks to timbers of large dimensions, including piles and pieces of wreckage at a cost of $2,819,538 in FY1985. Conditions as of September 30. Work authorized under River and Harbor Acts of 1915, 1917, and 1930 is continuous maintenance for which no percentage of completion exists. For work authorized by the 1974 Water Resources Development Act, removal of drift sources has been completed in New Jersey at Liberty State Park and the City of Elizabeth. In New York City, work has been completed along the Manhattan side of the East River inclusive of Piers 17 and 18 Stapleton, Staten Island. Removal work is currently underway in Hoboken, Weehawken and Jersey City, NJ. 18. NEW YORK HARBORENTRANCE CHANNELS AND ANCHORAGE AREAS Location. In Upper and Lower bays, New York Harbor is 330 miles southwest by water of Boston Harbor, Mass., and 165 miles northeast of entrance to Delaware Bay, N.J. The Upper Bay extends about 5.5 miles southerly from junction of Hudson and East Rivers opposite the Battery, New York City to the Narrows. Lower Bay extends about 9 miles from the Narrows to the sea. (See National Ocean Survey Charts 12327, 12334, 12335, and 12349.) Existing project. Ambrose Channel 45 feet deep and 2,000 feet wide, extending about 10.2 miles from sea to deep water in the Lower bay; Anchorage Channel, an extension of Am- I brose Channel, with same depth and width, in the Upper bay, opposite anchorage grounds, about 5.7 miles long; a southerly entrance channel, Sandy Hook Channel (East Section) 35 feet deep and generally 800 feet wide extending 3.4 miles from 35-foot ocean contour to Bayside Channel along an alignment generally west of the South Channel; and elimination from authorized project of that portion of Bayside-Gedney Channel east of junction with new southerly entrance channel; for Bayside Channel 35 feet deep and 800 feet wide, extending about 3.7 miles from junction with new southerly entrance to junction with Main Ship Channel; Main Ship Channel 30 feet deep and 1,000 feet wide, extending about 5.3 miles from Bayside Channel to deep water in Lower bay; a channel along New Jersey pierhead line connecting Kill Van Kull with deep water in Anchorage Channel, south of Liberty Island anchorage, 20 feet deep for 500 feet wide with widening at bends to 800 feet and about 3 miles long; an anchorage in vicinity of Liberty (Bedloes) Island (about 160 acres in extent) 20 feet deep; and for removal of Craven Shoal to 30 feet deep; for a channel 16 feet deep, 200 feet wide, and about 2.3 miles long, extending from bell buoy 23 to Hoffman and Swinburne Island; for an anchorage area in Red Hooks Flats to depths of 45, 40 and 35 feet and an anchorage area in Gravesend Bay to 47 feet deep. Project depths refer to mean low water. Mean tidal range is 4.7 feet at Fort Hamilton; mean range of spring tides, 5.7 feet; irregular fluctuations due to wind and atmospheric pressure vary from 3.9 feet below mean low water up to 6.2 feet above mean high water. Local cooperation. Fully complied with. Terminal facilities. See Port Series No. 5, revised Vol. 2, 1978. Operations and results during period. U.S. Army Corps of Engineers Dredge "McFARLAND" was employed from October 20, 1984 to October 23, 1984 to restore present dimensions to Ambrose Channel & from March 7-31 & May 2 - June 1, 1985 to restore project dimensions in Mainship Channel, New York. Removed approximately 720,980 cubic yards, place measurement of material at a cost of $2,388,129. Condition as of September 30. Work under existing project began in 1885 and is 100 percent complete. Main Ship and Bayside-Gedney Channels were completed to 30 feet deep in February 1891. Deepening of Bayside-Gedney Channel to 35 feet for a width of 800 feet was completed in June 1939. Ambrose Channel was completed to a 40 feet deep for a width of 2,000 feet in April 1914 and substantially completed to 45 feet deep for a width of 2,000 feet in 1951. Relocation of Anchorage Channel was completed to 40 feet deep in October 1932. Center 800 feet was dredged to 45 feet in June 1947 and westerly 600-foot strip in April 1948. Easterly 600-foot strip was substantially completed in June 1953. Channel between Staten Island and Hoffman and Swinburne Islands was completed in December 1920 up to within 300 feet of southerly limits of the project. Dredged channel meets all needs of navigation and no further work of improvement is contemplated for the present. Channel along New Jersey pierhead line from Kill Van Kull to Anchorage Channel was completed in March 1939. Widening at bends near southerly and northerly ends authorized in 1948 was completed to depths of 45, 50, and 35 feet in October 1976. Anchorage Channel was relocated to the westward in 1982. Red Hook Flats Anchorage was accordingly increased in area. No dredging was required. Liberty (Bedloes) Island anchorage was completed to 20 feet in October 1944. Sandy Hook Channel (east section) was completed to a depth of 35 feet in June 1963. Gravesend Bay Anchorage was completed to a 47-foot depth in November 1977. 19. PORT CHESTER HARBOR, N.Y. Location. At boundary between States of New York and Connecticut, comprises the tidal mouth, about 1.7 miles long, of Byram River whose source is in Byram Lake about 12 miles north of Port Chester. River empties into Long Island Sound about 32 miles by water east of the Battery, New York City. 2-10 NEW YORK, N.Y. DISTRICT (See Coast and Geodetic Survey Chart 12367.) Previous projects. For details see Annual Report for 1915, page 1758, and Annual Report for 1938, page 157. Existing project. An anchorage basin near breakwater constructed at Byram Point under a prevous project, 12 feet deep, for fenders on east bank opposite southern end of Fox Island, and a channel 12 feet deep at mean low water and 150 feet wide from Long Island Sound to mouth of river at southerly point of Fox Island; thence 10 feet deep and 100 feet wide to 900 feet below fixed bridge at Mill Street in Port chester, including a turning basin opposite steamboat landing; and thence 3 feet deep and 175 to 100 feet wide to 100 feet below fixed bridge. Section included in project is about 1.7 miles long. Mean tidal range, 7.1 feet; mean range of spring tides, 8.5 feet; irregular fluctuations due to wind and barometric pressure vary from 4 feet below mean low water up to 8.6 feet above mean high water. Cost of new work for completed project was $358,475, exclusive of amounts expended on previous projects, and $5,500 to be contributed by local interests. Widening turning basin and construction of fenders on bank opposite southern end of Fox Island, at a cost of $93,000, (1954) is considered inactive and excluded from foregoing description of existing project and cost estimate. Local cooperation. River and Harbor Act of 1930 provides that local interests contribute $5,500 in cash toward widening channel at turning basin. This condition has not been fulfilled and there is no indication as to when compliance may be expected. Terminal facilities. There are 34 terminals in Port Chester Harbor between Fox Island and Mill Street Bridge, with a total berthage of about 5,300 feet, of which 3,120 feet are available for dockage. Village of Port Chester owns several bulkheads which are used as public landings for small pleasure craft. Several boatyards with storage space for 75 boats and equipped with a total of 3 marine railways are available for pleasure craft. Facilities adequate for existing commerce. Operations and results during period. A contract for the removal and disposal of all material except ledge rock lying above the planes of 10 and 3 feet below mean low water in specified sections of Port Chester Harbor, New York was awarded February 4, 1985. Work commenced March 9, 1985 and was completed April 12, 1985. Removed 91,592 cubic yards, place measurement of material at a total cost to project of $616,303. Condition as of September 30. Work on active portion of existing project was completed October 1938. Controlling mean low water depth (June 1952 and Nov. 1965) was 12 feet for a width of 140-50 feet from Long Island Sound to Fox Island, 8 feet in anchorage, thence 10 feet for a width of 90-40 feet to turning basin, 10 feet in turning basin, thence depths varying from 3 to zero feet for full width to upper limit of 3-foot project. Work remaining under existing project consists of widening turning basin and constructing fenders on bank opposite southern end of Fox Island (inactive). 20. RARITAN RIVER, N.J. Location. Rises in north-central part of New Jersey and flows generally southeasterly into Raritan Basin, between Perth Amboy and South Amboy, about 24 miles by water south of the Battery, New York City. (See coast and Geodetic Survey Chart 12332.) Previous projects. For Details see Annual Reports for 1915, 1918, and 1938, pages 1777, 359, and 259 respectively. Existing projects. A channel 25 feet deep and 300 feet wide extending 5.8 miles from turn in New York and New Jersey Channels near Great Beds Light to Government wharf on Main Channel, widened to 600 feet for 1,000 feet long opposite wharf to form a turning basin of same depth; thence a channel 15 feet deep and 200 feet wide 3 miles to Washington Canal; thence 10 feet deep in soft material, 11 feet deep in rock, and generally 100 feet wide with widening at bends 5 miles to Delaware and Raritan Canal entrance at New Brunswick, and a South Channel 25 feet deep and 300 feet wide 0.8 mile from junction with Main Channel at Keasby to upper limit of Titanium Pigment Co. property; thence 15 feet deep and 150 feet wide 0.4 mile to dock of Middlesex County Sewerage Authority; thence 10 feet deep and 150 feet wide 2 miles to a point 1,300 feet below upper junction with Main Channel at Crab Island. Plane of reference is mean low water. Mean range of tides is 5.1 feet at mouth of river and 5.6 feet at New Brunswick; mean range of spring tides, 6.1 and 6.6 feet respectively. Irregular fluctuations due to winds and atmospheric pressure vary from 3.6 feet below mean low water up to 6.9 feet above mean high water. New work for completed portion of project, consisting of channels described above cost $1,237,000, exclusive of amounts expended on previous projects and including $66,000 contributed by local interests. Dredging South Channel to 10 feet deep and 150 feet wide for 1,300 feet to upper junction with Main Channel at Crab Island is inactive and excluded from foregoing description and cost estimate. Cost estimate for this portion is $86,000 (1954). (See Table 2-B for Authorizing Legislation.) Local cooperation. Complied with except local interests must furnish spoil-disposal areas for maintenance to 25-foot channel from New York & Long Branch Railroad bridge to junction of Main and South Channels, and in South Channel to Titanium Pigment Co. property. River and Harbor Act of 1962, provides local interests furnish spoil-disposal areas and necessary retaining dikes, bulkheads and embankments therefore, required for maintenance of improvement, and hold the United States free from damages. Terminal facilities. See Port Series No. 5, revised 1965, Vol. 2, Part 2, pages 274-279 and 281. Operations and results during period. A continuing contract for maintenance dredging to restore project depths was awarded in Fiscal Year 1984. Work commenced November 26, 1984 and was completed January 12, 1985. Removed 281,364 cubic yards, place measurement, of material at a total project cost of $1,119,269. Condition as of September 30. Entire existing project is about 96 percent complete. Work under active portion of existing project was commenced September 1919 and completed 2-11 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 July 1941. A shoal along northerly channel line in vicinity of Victory Bridge was eliminated by relocation of channel in February 1959. Main Channel dredged 25 feet deep and 300 feet wide from junction with New York and New Jersey Channels to and including a turning basin of same depth opposite Government wharf, thence 15 feet deep and 200 feet wide to mouth of Washington Canal, thence 10 and 11 feet deep and 100 feet wide to Delaware and Raritan Canal outlet locks at New Brunswick. South Channel dredged 25 feet deep and 300 feet wide for 3,200 feet, thence 10 feet deep and 150 feet wide for 12,400 feet to within 1,300 feet of junction with Main Channel at Crab Island. Model study of Raritan River was completed in March 1952. Work remaining under existing project is dredging South Channel to 10 feet deep and 150 feet wide for 1,300 feet to upper junction with Main Channel at Crab Island. 21. SANDY HOOK BAY, N.J. Location. This bay is the southern portion of lower New York Bay, west of and adjoining the projecting arm of Sandy Hook, N.J. (See U.S. Coast and Geodetic Survey Charts Nos. 12327 and 12324.) Existing project. This provides for the construction of a continuous rubble-mound breakwater about 4,000 feet in length extending eastward from the New Jersey Central Railroad steamboat dock at Atlantic Highlands, N.J., and dredging of the area in its lee and seaward of the new pierhead line to a depth of 8 feet at mean low water. Mean range of tides, 4.6 feet; mean range of spring tides, 5.6 feet; irregular fluctuations due to wind conditions vary from 1 to 2 feet above or below the mean range. Local cooperation. Fully complied with, except that local interests must furnish easements and rights-of-way necessary for subsequent maintenance as and when required. STerminal facilities. There are 3 piers with a total berthage of 1,330 feet, located along the waterfront at Atlantic Highlands westerly of and adjacent to the anchorage area. One of these terminals has railroad connections. Under the conditions of local cooperation, 5 boat basins with mooring stalls and servicing facilities for pleasure boats were constructed. The existing terminals will be sufficient for present needs. There is ample space for additional wharves and boat basins should future needs warrant their construction. Operations and results during period. A contract for the removal and satisfactory disposal of all material except ledge rock in Sandy Hook Bay at Atlantic Highlands, New Jersey was awarded January 30, 1985. Work commenced February 16, 1985 and was completed May 24, 1985. Removed 639,710 cubic yards, place measurement, of material at a cost of $3,737,763. Condition as of September 30. The existing project was completed in 1941. The breakwater was completed in 1940 and the anchorage area was completed in 1941. 22. SHINNECOCK INLET, N.Y. Location. On the south shore of Long Island, about 95 miles east of the Battery, New York City. It is an opening through the sandy barrier beach, connecting Shinnecock Bay with the Atlantic Ocean. (See USCCT Chart 12352) Existing project. Provides for a channel 10 feet (mlw) and 2-12 200 feet wide extending through the inlet to Shinnecock Bay for a distance of about 0.6 miles; thence a channel 6 feet deep and 100 feet wide to the Long Island Intracoastal Waterway, a distance of about 1 mile; rehabilitation of the existing jetties and revetments. Estimate of coast for work is $18,230,000 (Oct 85 P.L.) including $130,000 from the Coast Guard and $6,600,000 to be contributed by local interests (see Table 2-3 for Authorizing Legislation). Local cooperation. The share of local cooperation is 36.5 percent of the initial coast and 38 percent of maintenance, operating and replacement costs (based on the cost sharing provisions of the 1960 R&H Act). The authorizing document also requires that local authorities: furnish, free of cost to the United States, all lands easements, rights-of-way, and suitable spoil-disposal areas for the initial work and for subsequent maintenance, when and as required; hold and save the United States free from damages due to the construction and maintenance of the project; provide and maintain suitable terminal facilities when and as required for the accommodation of vessels that would navigate the inlet and adjacent bays, open to all on equal terms; maintain, for the duration of the economic life of the project, continued public ownership of the publicly owned shores and their administration for public use, and continued availability for public use of the privately owned shores upon which a portion of the Federal share of the costs is based. The New York State Department of Environmental Conservation expressed their intent to provide required items of local cooperation by letter dated 7 September 1983. Terminal Facilities. Shinnecock Bay, and adjacent ocean area, constitute an important marine fishery. It is part of the Long Island resort region, which affords recreation to thousands of people participating in fishing, pleasure boating, and bathing. Many hotels and tourists homes are located in the area, as well as yacht clubs, boat yards, public wharves and landings, and numerous private landings. Safe access to the ocean is necessary for commercial fishing and recreational craft. Operations and results during period. Work was done on preparation of the Environmental Impact Statement. Condition as of September 30. No.Federal construction has been done. Preconstruction planning is continuing. 23. SHREWSBURY RIVER, N.J. Location. Mainly a large tidal basin in eastern part of New Jersey, the outlet being at the southeast end of Sandy Hook bay, about 4 miles south from the point of Sandy Hook. (See Coast and Geodetic Survey Chart 12324.) Previous Projects. For details see Annual Reports of 1915, 1918, and 1938, pages 1778, 373, and 267, respectively. Existing project. A channel 12 feet deep and 300 feet wide, following the westerly shore, from deep water in Sandy Hook Bay 2.2 miles to a point 500 feet south of former location of railroad bridge at Highlands; then 9 feet deep and generally 150 feet wide, suitably widened at bends and turns, in south branch of river 6.8 miles to Branchport Avenue Bridge in city of Long Branch; and a channel in north branch (Navesink R.) 6 feet deep and 150 feet wide 6.1 miles from the junction to Red Bank. Plane of reference is mean low water. River and Harbor Act of 1965 modified existing project to include an in NEW YORK, N.Y. DISTRICT let channel across base of Sandy Hook Peninsula between Spermaceti Dove and Island Beach connecting the Atlantic Ocean and Shrewsbury River. The ocean channel to be 15 feet deep, 200 feet wide and 830 feet long protected by parallel jetties spaced 500 feet apart and through the land cut to be protected by bulkheads in extension of jetties; thence a bay channel 9 feet deep, 200 feet wide, and 2,860 feet long extending to existing Shrewsbury River channel. Plane of reference is mean low water. New inlet is to be spanned by a 6-lane fixed highway bridge with a vertical clearance of 35 feet above mean high water and a total length of 1,560 feet. Mean range of tide at Highlands, 3.8 feet; at Seabright, 1.7 feet; at Branchport; 1.7 feet; and at Red Bank, 3 feet. Mean range of spring tides is 4.7, 2.1, 2.2, and 3.6 feet, respectively. Irregular fluctuations due to wind and atmospheric pressure vary from 1.9 feet below mean low water up to 6.5 feet above mean high water. Estimate of cost for new work is $12,946,000 (July 1971) including $6,200,000 to be contributed and $36,000 already contributed by local interests and exclusive of amounts expended on previous projects. This work was reclassified to Inactive in December 1973 because of state and local opposition. Dredging turning basin and anchorage in vicinity of Red Bank, 6 feet deep and about 19 acres in area; a channel in Claypit Creek, 6 feet deep and 100 feet wide about 1 mile from 6-foot curve in north branch to head of the creek; a channel in Oceanport Creek, 6 feet deep, 100 feet wide and 2 miles long from channel in south branch to New York and Long Branch Railroad Bridge; and a channel in Little Silver Creek, 6 feet deep, 100 feet wide, and 1.6 miles long from channel in south branch to Seven Bridge Road Bridge is also inactive and excluded from foregoing description and cost estimate. Cost estimate for this portion (1960) is $578,000 exclusive of $86,000 to be contributed by local interests. (See Table 2-B for Authorization Legislation.) Local cooperation. River and Harbor Act of 1950 provides local interests furnish lands, rights-of-way, and spoildisposal areas for construction and future maintenance; hold the United States free from damages; provide and maintain a suitable public wharf on each of the creeks to be improved, which shall be open to all on equal terms; remove Locust Avenue bridge over Claypit Creek; and make cash contributions of $25,000, $33,000, and $27,500 toward cost of improvement of Claypit, Oceanport, and Little Silver Creeks, respectively. Provided further that construction of any unit of proposed improvement may be undertaken independently of the other units when the required local cooperation has been provided. These conditions have not been fulfilled. Requirements under prior acts have been fully complied with. River and Harbor Act of 1965 provides that local interests furnish lands, rights-of-way outside of the Federally owned lands, for construction and future maintenance and for aids to navigation and future maintenance and for aids to navigation upon request of the Chief of Engineers, including suitable spoil-disposal areas, and necessary retaining dikes, bulkheads, and embankments therefore or the costs of such retaining works; hold the United States free from damages; assume all obligations of owning, operating and maintaining highway bridge, with such obligations to be assumed by local interests upon final completion of its construction; assign to a competent and properly constituted public body the power to regulate the use, growth, and free development of adequate boating facilities in the area to be served by the inlet, with the understanding that such facilities will be open to all equally; 2-13 and provide, maintain, and operate necessary mooring and terminal facilities and utilities including an adequate public landing or wharf with provisions for the sale of motor fuel, lubricants and potable water, available to all equally. Requirements under 1965 River and Harbor Act have not been complied with. Terminal facilities. There are 33 terminals with a total berthage of 7,986 feet on the waterway. Eight terminals with a total berthage of 1,000 feet are open to the public. In addition, many private pleasure boat landings have been constructed by owners of riverfront estates. Fifteen boatyards with storage space for 670 craft and equipped with 21 marine railways are available. None of the terminals has direct rail connections. Facilities considered adequate for existing commerce. Operations and results during period. A continuing contract was awarded September 6, 1985 for removal and disposal of all material except ledge rock lying above the planes of 9 and 6 feet below mean low water in specified areas of the Shrewsbury and Navesink Rivers. Expended $79,472 for engineering and design of maintenance dredging specifications. Contractor will commence dredging in Fiscal Year 1986. Condition as of September 30. Work under the active portion of existing project began in October 1919 and is about 10 percent complete. Work completed consisted of providing authorized project dimensions in 12-foot entrance channel, 9-foot channel in South Branch, and a 6-foot channel in North Branch of the river. Work remaining under the existing project consists of dredging an inlet channel across the base f Sandy Hook protected by jetties and bulkheads, a bay channel extending to the existing Shrewsbury River Channel and a six-lane fixed highway bridge to span the new inlet as authorized by the River and Harbor Act of 1965. Preconstruction planning (advance engineering and design) for work under this Act is about 50 percent complete. Planning included a physical model study, which was completed. The remaining work was subsequently reclassified to inactive because of state and local opposition. Close out report underway. Formal close out of this work remains. Under the River and Harbor Act of 1950 work remaining consists of dredging turning basin and anchorage in vicinity of Red Bank and channels in Claypit, Oceanport, and Little Silver Creeks. 24. SUPERVISOR OF NEW YORK HARBOR (Prevention of Obstruction and Injurious Deposits) The District Engineer, New York District, was designated Supervisor of New York Harbor under the provisions of the River and Harbor Act of June 29, 1888 (33 U.S.C. 441-451), as amended July 12, 1952. Under this Act, the Supervisor of New York Harbor is charged with the mission of preventing the deposit of obstructive and injurious materials in New York Harbor and its adjacent and tributary waters, including Long Island Sound. The River and Harbor Act of August 18, 1894 (33 U.S.C. 452) makes it unlawful for any person or persons to engage in fishing or dredging for shellfish in any of the channels leading to and from New York Harbor, or to interfere in any way with the safe navigation of those channels by ocean steamships and ships of deep draft; the River and Harbor Act of March 3, 1899 (33 U.S.C. 403, 307, 409) pro REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 hibits obstructions to navigable waters such as unauthorized structures, unauthorized fill, deposit of refuse, and willful or negligent abandonment of vessels. Other laws relating to the supervision of New York Harbor and its tributary waters are the Clean Water Act, the Marine Protection, Research and Sanctuaries Act of 1972, the Coastal Zone Management Act of 1969, the Fish and Wildlife Act of 1956, the Federal Power Act of 1920, the National Historic Preservation Act of 1966, the Endangered Species Act of 1973, the Deepwater Port Act of 1972, the Wild and Scenic Rivers Act, and the Land and Water Conservation Fund Act. Direct supervision of the waters under jurisdiction of the New York District was accomplished by means of two patrol vessels whose scope of duty includes surveillance of the waterfront for unauthorized construction or fill, surveillance to the 3-mile limit of tows enroute to dumping grounds in the Atlantic Ocean to ensure that material is not illegally desposited in the waters of New York Harbor, and investigation of wrecks and abandoned vessels. In addition to the patrol vessels, whose range of patrol was limited to New York Harbor, inspectors utilizing government vehicles equipped with two-way radios patrolled shorefront facilities and property. These inspectors operate out of field offices located at Riverhead, New York and one inspector working at the New York District Office. Their duties include inspection of authorized construction, fill or excavation in waterways, including wetland areas, to ensure that work is performed in accordance with the Corps permit. The inspectors also patrol all waterways in their respective areas and inform the public of the Corps role and jurisdiction as well as provide assistance in the preparation of permit application. (See Table 2-E at end of chapter.) 25. RECONNAISSANCE AND CONDITION SURVEYS (See Table 2-F at end of chapter.) 26. OTHER AUTHORIZED NAVIGATION PROJECTS (See Table 2-G at end of chapter.) 27. NAVIGATION WORK UNDER SPECIAL AUTHORIZATION Navigation Activities pursuant to Section 3 of Public Law 14, 79th Congress - River and Harbor Act of 2 March 1945. Navigation Activities pursuant to Section 107, Public Law 645, 86th congress as amended (Preauthorization). (See Table 2-N at end of Chapter.) Beach Erosion Control 28. EAST ROCKAWAY INLET TO ROCKAWAY INLET & JAMAICA BAY, N.Y. (PT. 1) " Location. Atlantic coast of New York City, between East Rockaway and Rockaway Inlets, and the lands within and surrounding Jamaica Bay. The coastal area (about 10 miles long) is a peninsula in Queens County separating the ocean and the bay. (See Coast and Geodetic Survey Charts 12327, 12350, and 12326.) Existing project. The project provides for approximately 8.7 million cubic yards of sand fill including the advanced placement of a two year supply of beach nourishment, and Federal participation in the cost of periodic beach nourishment of the shore protection works for 10 years after completion of the initial beach fill. Federal participation (50 percent) includes first cost and periodic beach nourishment, the total estimated at $25,600,000 (Oct. 1985 P.L.) Local cooperation. Local interests must provide lands and rights-of-way, including borrow areas; bear 50 percent of total first cost presently estimated at $25,600,000 consisting of a cash contribution of $8,800,000 the final apportionment of cost to be made after actual costs and values have been determined and $16,800,000 for periodic nourishment, hold the United States free from damages; maintain, during economic life of project, continued public ownership and use of non- Federal publicly-owned shores upon which Federal participation in beach protection is based; maintain and operate all works after completion, control water pollution to the extent necessary to safeguard the health of bathers; local cooperation agreement was executed by the State May 17, 1974 and approved for Secretary of Army May 21, 1974. On May 22, 1974 sent to State an approved Escrow Agreement. Operations and results during period. Periodic Nourishment Contract No. 2 and groin construction at Beach 149th Street completed in August and September 1982, respectively. Condition as of September 30. Advance engineering and design is completed. Final Environmental Impact Statement on file with Council of Environmental Quality on April 16, 1971. Initial beach restoration completed in FY1977. Contract for first increment of periodic nourishment completed in May 1980. Contract for second increment of periodic nourishment was completed in August 1982. Contract for construction of stone groin at Beach 149th Street was completed in September 1982. Contract for third periodic nourishment was completed in August 1984. Periodic nourishment contract No. 4 is scheduled to awarded in May 1986. Completion of 10-year periodic nourishment remains. 29. SEA BRIGHT TO OCEAN TOWNSHIP, N.J. Location. That portion of the Atlantic Coast of New Jersey in Moumouth County extending from Sea Bright southerly to Ocean Township - length about 12 miles. Sea Bright is about 30 miles by water south of the Battery, New York City. Erosion has seriously reduced the width of most beaches in the study area with consequent exposure of the shore to storm damage. Because of this erosion of the shore the area does not provide sufficient recreational beaches for the proper accommodation of the present and prospective tributary population. Existing project. Provides for Federal participation in the restoration and protection of the shore from Sea Bright to Ocean Township by artificial placement of sand to widen the 2-14 NEW YORK, N.Y. DISTRICT beach to a minimum width of 100 feet at an elevation of 10 feet above mean low water and by the construction of 23 new groins and the extension of 14 existing groins in the Sea Bright-Ocean Township section. The project provides for Federal participation in periodic nourishment costs for a period of 10 years from the year that the total quantity of fill placed has equaled that required to restore the beach to project dimensions in that section. Total estimated Federal cost is $86,200,000. Total estimated non-Federal for all requirements of local cooperation is $11,500,000. (See Table 2-B for Authorizing Legislation.) Local cooperation. Reconstruction of the seawall at Sea Bright and Monmouth was funded by the State. In addition the State provided funds in the amount of $100,000 for a limited analysis by the New York District with a view to deferring certain construction elements. Operations and results during period, and Condition as of September 30. Construction has not been initiated, but the project is in an active status. No environmental impact statement was prepared. 30. OTHER AUTHORIZED BEACH EROSION CONTROL PROJECTS (See Table 2-H at end of chapter.) 31. BEACH EROSION CONTROL WORK UNDER SPECIAL AUTHORIZATION Beach Erosion Control activities pursuant to Section 103 Public Law 826, 84th Congress as amended (preauthorization). (See Table 2-0 at end of chapter.) Flood Control 32. ARDSLEY, N.Y. Location. The Village of Ardsley in Westchester County, New York is located on the Saw Mill River approximately 5 miles upstream from its junction with the Hudson River. (See U.S. Geological Survey Map, White Plains, N.Y.) Existing project. The Federal flood control project provides for relocation of the existing channel from the upstream limit of the project downstream for approximately 1,000 feet, and approximately 290 feet of concrete channel upstream of the new Ashford Avenue Bridge. Upstream of the concrete channel along the left bank of the Saw Mill River, 425 feet of floodwall will be constructed along the modified channel with an additional 400 feet of closure wall. Between the Conrail Bridge and the New York State Thruway, a total of 230 feet of floodwall will be constructed on the right bank. A 325 foot closure levee is to be constructed running north of the Conrail Bridge. Ponding areas, drainage ditches and other drainage structures will be provided. The total estimated Federal cost for the project is $4,430,000 exclusive of land, relocations and other work to be provided by local interests at an estimated cost of $l,470,000 (October 1985 P.L.) Local cooperation. In accordance with cost sharing and financing concepts reflected in S.1567, local interests are required to furnish all lands, easements and rights-of-way including relocations that are necessary for flood control improvements presently estimated at $860,000 and operate and maintain the project at an estimated cost of $27,000; interests have agreed to voluntarily pay 25 percent of the costs allocated to flood control for a total cost of $1,470,000 project cost but not less than that required by project authorization presently estimated at $1,470,000. The New York State Department of Environmental Conservation, the local sponsor, in an 11 December 1973 letter, indicated its intent to comply with the items of local cooperation and reaffirmed this on 15 August 1979 and 23 August 1985. The State of New York, in a 18 October 1985 letter, expressed this willingness to assume responsibility as local sponsor in accordance with the Cost Sharing and financing concepts agreed to by the Administration and Senator Majority Leadership Compromise as reflected in S.1567. Operation and results during period. Preconstruction planning continued. Condition as of September 30. Plan of Study approved in March 1979. Construction has not been initiated. 33. ELIZABETH, N.J. Location. In city of Elizabeth, N.J. (Union County), extending 4.2 miles upstream from mouth of Elizabeth River at Arthur Kill. The river continues 7.7 miles northward through Union and Essex counties to its headwaters in East Orange, N.J. (See Geological Surveys quadrangles, Roselle, Elizabeth, Caldwall and Orange; and Army Map Service quadrangles, similarly designated.) Existing project. Includes an improved channel with levees and/or walls where necessary between Bridge Street and Arthur Kill (2.1 miles); a concrete channel between Trotter's Lane and U.S. Highway No. 1 (1.4 miles); closure to high ground at upstream and downstream ends; interior drainage, including 5 pumping stations and 11 ponding areas; reconstruction or replacement of 16 bridges and associated street regrading; and utilities relocations. Total estimated Federal cost is $54,600,000. Total estimated non-Federal cost for all requirements of local cooperation excluding maintenance is $12,900,000 including $1,170,000 cash contribution. (See Table 2-B for Authorizing Legislation.) Local cooperation. Local interests must provide lands and rights-of-way for construction and subsequent maintenance, the costs and values incurred in the interest of hurricane tidal flood protection to be credited to required local contribution to the project firsts costs allocated to hurricane tidal protection; hold the United States free from damages; maintain and operate completed works including all dredging required in the channel to maintain the design depths in the tidal reach; reconstruct all bridges and approaches except railroad bridges, and relocate existing sewerage and drainage facilities, streets, utilities, and other structures, such costs and valued incurred in interest of hurricane tidal flood protection to be credited to required local contribution to protect first costs allocated to hurricane tidal flood protection; bear 30 percent of first costs allocated to hurricane tidal flood protection, including the two items listed above pertaining to lands, 2-15 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 reconstruction and alterations, and a cash contribution now estimated at $1,170,000 to be paid either in a lump sum before starting construction, or in installments before starting construction, or in installments before starting pertinent work items in accordance with construction schedules as required by the Chief of Engineers; take necessary action to protect channels from future obstruction or encroachment including waste disposal that would reduce their flood-carrying capacity; take appropriate measures to control development in partially protected areas and fringe areas not included in the project with a view to preventing an undue increase in flood damage potential; maintain existing natural detention areas along the Elizabeth River between Union Avenue and Trotters Lane free from encroachment so as not to reduce their detention capacity; to provide an additional gravity outlets or pumping station capacities made necessary by any modifications or encroachments on the ponding areas; bear any increased Federal costs for the improvement that may result from any future requirements for parkway developments; and at least annually, notify interests affected that the improvements will not provide complete protection for fluvial floods greater than in July 1897. Agency responsible for local cooperation is City of Elizabeth (with concurrence of Union County and State of New Jersey.) Signed assurances of local cooperation were accepted by the District Engineer on January 9, 1970. Operations and results during period. Construction of the Downstream Section was completed December 17, 1981. The Upstream Section of the project was awarded in March, 1982 at a cost of $22,964,500 and is 99 percent complete. Condition as of September 30. Advance planning (begun January 1966), leading to first construction (Ursino Basin) and the Penn-Central Bridge and downstream dredging contracts, has been completed. General design memorandum and its supplement submitted. Penn-Central Railroad Bridge agreement executed. Environmental Impact Statement submitted to the Council on Environmental Quality on April 20, 1971. Upstream Ursino Basin construction complete. Contract, executed with New Jersey Department of Transportation on June 2, 1977 for placement of 132 foot section of flume: to be accomplished in conjunction with bridge replacement, has been completed. Contract for the Downstream Area Arthur Kill to U.S. Highway 1, was awarded September 29, 1978 and completed in December 1981. Upstream contract was awarded in March 1982. Project scheduled for completion in September 1986. 34. LIBERTY STATE PARK LEVEE AND SEAWALL, N.J. Location. At Liberty Pa:k, in Jersey City, Hudson County, New Jersey, directly behind Ellis Island and the Statue of Liberty, in Upper New York Bay (see Coast chart 12334) Existing project. Construction of a levee, seawall, and walkways; rehabilitation of certain existing structures; landscaping with trees and shrubbery; and a boat basin and marina. The construction of the levee project will allow the creation of a large Greenpark to include a wetlands preserve, an inland watercourse and boatbasin, a marina, an ampitheater, indoor and outdoor recreation facilities, picnic areas, historic areas, community facilities, restaurants, plazas and many other areas for both active and passive recreational and aesthetic benefit to visitors. The stone armored levee will also serve as a settlement-free base for subsequent construction of a tree-lined promenade, the Liberty walk, curving along the water's edge. The Federal cost of construction is estimated at $19,000,000; with an additional $19,000,000 contribution by local interests including lands, certain relocations, utilities, and interior drainage. Local Cooperation. In accordance with the project authorization, local interests are required to furnish all lands easements and rights of way including relocations, save those existing utilities passing through the proposed levee, necessary for the flood control improvements and to operate and maintain the project at an annual cost estimated to total $55,000. The State will assume all costs for construction of an interior drainage system to provide a ten (10) year level of protection estimated to be $5,000,000. Local interests have agreed to voluntary pay 50% of project cost. The New Jersey Department of Environmental Protection, the local sponsor, has indicated its willingness to comply with items of local cooperation in a letter dated 28 October 1985. In relation to the provision for cost sharing, they have indicated that they would negotiate this item subsequent to the passage of appropriate legislation. Operations and results during period, and Conditions as of September 30. Phase I is completed. The District has completed their review of 90% (and final) contract documents for seawall (Area 2) and walkways (Areas 3 and 4) contracts. 35. PASSAIC RIVER BASIN, N.J. & N.Y. Location. The Passaic River Basin, comprising 787 square miles in northeastern New Jersey and 148 square miles in southern New York State, is located in the greater New York City Metropolitan area. The Passaic River Basin is roughly elliptical in shape 26 miles long and 56 miles wide-and contains portions of Bergen, Essex, Morris, Passaic, Hudson, Somerset, Sussex and Union Counties in New Jersey. The Basin also includes parts of Orange and Rockland Counties in New York. Previous Projects. Two Federal flood control projects have been completed by the Corps of Engineers in Passaic River Basin. A $67,400 desnagging, debris removal and channel restoration project was completed in 1951 along Beaver Brook and the Pequannock Township Ditch, tributaries of the Pompton River in Pequannock Township, N.J. Along the Pompton River, a channel clearing project including shoal removal and channel restoration was implemented in the two-mile reach from the Delaware, Lackawanna and Western Railroad Bridge to the Erie Railroad (Greenwood Lake Branch) Bridge. This work, in Pequannock Township, Wayne Township and Lincoln Park Borough, N.J., was completed in 1954 at a cost of $50,000. Existing project. The project was authorized for Phase I advance engineering and design study in Section 101 (a) of the Water Resources Development Act of 1976 in accordance with the February 18, 1976 report of the Chief of Engineers. The estimate of Federal cost under the authorizing legislation is $1,330,000,000 (October 1985 P.L.), plus a $3,120,000 2-16 NEW YORK, N.Y. DISTRICT cash contribution from local interests and $146,880,000 for items of work to be contributed by local interests. The recommended plan for flood protection, navigation, hurricane protection and recreation, included a flood detention reservoir, channel diversions and modifications, levees and floodwalls, and streambank filling and grading. These works would provide protection against storm with a recurrence interval of 235 years, which is 20 percent larger than the October 1903 flood of record. Six independent tributary local protection plans were also recommended. However, because of a lack of public support for structural components of the project in the New Jersey portion of the Basin, the entire project is being reformulated during the Phase I study. The House Public Works Committee Report (94-1702) on the 1976 Water Resources Development Act directed "...the reformulation of the plan for water management and flood control for the entire Passaic Basin." This report further states that local opposition to any plan which relies upon extensive use of dikes, dams and levees, such as those proposed in previous survey reports, mandates that the following alternatives, or any combination thereof, shall be the only ones surveyed and considered: (a) A full range of nonstructural flood control alternatives to include land acquisition, flood plain mapping, flood-proofing, developing early warning systems and relocation of buildings; (b) A tunnel diversion plan; (c) A system of tunnels addressing the needs of the entire basin; (d) Plans that combine local protection works where locally acceptable and nonstructural solutions including improvements to stream carrying capacity in accordance with different needs in the Lower Basin and in the Central basin; (d) Evaluation of fulfilling water supply objectives together with flood control; (f) Aquifer recharge and underground storage; and (g) Reservoir management in the headwaters. The Phase I Study is evaluating these alternatives in the formulation of revised plans. Conditions as of September 30. The reformulation study was initiated in October 1977 under the existing authorization and Congressional Guidance in House Report 94-1702. The Study schedule runs through September 1987 at an estimated cost of $21,000,000. During FY1984, major effort was made to present feasibility basin-wide plan alternatives to the public. These alternatives included plans featuring tunnel diversions, channel improvements, levees and floodwalls, and nonstructural measures. During this period, the basin experienced severe flooding in April which was estimated to be the worst flooding in 40 years. In June the State of New Jersey selected the dual inlet tunnel plan as the local option plan for further study. Study effort is now focused on this plan and the candidate NED plan. Plan formulation has been completed for tributary flood damage areas along the Ramapo and Mahwah Rivers at Mahwah, N.J., and Suffern, N.Y., Molly Ann's Brook at Haledon, Prospect Park and Paterson, N.J., the Ramapo River at Oakland, N.J., and the Lower Saddle River in Bergen County, N.J. These areas have been recommended for early implementation under the interim flood protection guidance provided by the Congress. The Longwood Valley Reservoir plan is now part of the Passaic River basin study as a result of a Congressional resolution. This plan will include water resource development for flood control on the Upper Rockaway River, water supply and proposed storage hydroelectric power. 36. SAW MILL RIVER AT ELMSFORD AND GREENBURGH, N.Y. Location. On the Saw Mill River in the town of Greenburgh, N.Y. One portion known as Babbitt Couirt lies along the river immediately south of the Village of Elmsford. The second portion of the project, known as the Elmsford- Greenburgh area, is north of the Village of Elmsford, separated from Babbitt Court by approximately 4,000 feet. (See U.S. Geological Survey Map, White Plains, N.Y.) Existing project. In the Babbitt Court area, the project provides for approximately 1,450 feet of levees and flood walls with associated ponding and interior drainage facilities. Within the Elmsford-Greenburg area, the existing channel is to be widened and deepened for 2,450 feet with an additional 600 feet of channel modification on the tributary Mine Brook. Levees and flood walls will be constructed on both banks of the Saw Mill River totaling approximately 4,400 feet and extending along Mine Brook to high ground. Ponding areas, a pumping station and other drainage structures will be provided. The total estimated Federal cost (October 1985 P.L.) for the project is $5,580,000 exclusive of land, relocations and other work to be provided by local interests at an estimated cost of $420,000 (See Table 2-B for Authorizing Legislation.) Local cooperation. Local interests must provide lands and rights-of-way for construction, including borrow, ponding, and waste disposal areas; hold the United States free from damages; maintain and operate completed works; provide all alterations, relocations, and necessary replacements of existing facilities, including bridges, highways, sewers, (including those storm sewers and drains required to convey interior drainage to improved channels of ponding areas) utilities, and railroad modifications and relocations other than bridges and bridge approaches; protect the channel and other flood works from future encroachment or obstruction, including waste disposal which would reduce or otherwise impair their flood-carrying capacity, or provide a pumping station or additional gravity outlets, as appropriate, to compensate for any loss in ponding area effectiveness due to modification of or encroachment upon such areas; take appropriate measures to control development in partially protected areas and fringe areas not included in the project with a view toward preventing an undue increase in the flood damage potential; and at least annually, notify those affected that flooding will still be possible from large floods. New York State is Local Cooperating Agency. The New YorkState Department of Environmental Conservation, by letter dated June 12, 1974, indicated the State's intention to cooperate in the proposed plan. Operation and results during period. During Phase I preconstruction planning the authorized project was found to be no longer economically justified. Phase I project reformulation to develop an alternative plan of improvement has been completed. Condition as of September 30. Plan of Study approved January 28, 1977. Preconstruction planning started in February 1977. Indications from Phase I Planning accomplished to date, are that some features of the authorized project are no longer economically justified. The final Phase I General Design Memorandum was completed in Sept. 1985 and transmitted to North Atlantic Division for review. 2-17 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 37. INSPECTION OF COMPLETED FLOOD CONTROL PROJECTS. Inspections of completed flood control works are performed semi-annually to determine the extent of compliance by local interests with the requirements of operation and maintenance. 38. OTHER AUTHORIZED FLOOD CONTROL PROJECTS (See Table 2-I at end of chapter.) 39. DAM SAFETY PROGRAM Beginning in FY1985 the New York District is performing a two phase modification to Waterbury Dam in an attempt to drastically reduce or totally eliminate a long existing seepage problem at the dam. The first phase of construction is the addition of 48 inch pipe to the two existing 54 inch pipes that comprise the existing outlet works of the dam. This work was completed in July 1985 at a cost of $513,400. The second phase of work is the partial rebuilding of the toe of the dam to include a seepage filter and monitoring system and to fill voids by means of sand injection and to fill voids in the river gorge by grouting. A contract for construction of the seepage filter and monitoring system was awarded in July 1985 at an estimated cost of $818,000 and is expected to be completed in Nov. 1985. The sand injection and gorge grouting work was initiated by hired labor in April 1985 at an estimated cost of $780,000. The sand injection and gorge grouting work is being done by the Baltimore District for the New York District. 40. FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION Natural Disaster and Emergency Flood Control Activities. Pursuant to Public Law 84-99 and antecedent legislation -advance preparation, emergency operations, rehabilitation, emergency drinking water, advance measures and drought assistance. Under disaster preparedness, the New York District completed revisions of various emergency manuals and pamphlets, attended meetings and seminars dealing with emergency response and preparation, provided in-house training to District employees in emergency operations activities, and purchased supplies and equipment to maintain its' flood fighting and response capability. Under emergency operations, the New York District monitored the effects of Hurricane Gloria which threatened the coastal regions of southern Long Island and New Jersey in late September 1985. As a result of the severity of this storm, the District dispatched reconnaissance survey team to ascertain the extent and type of damages which had occurred in the affected locations. Technical assistance and sandbags were also provided to local, county and state governmental organizations which requested such aid. It is anticipated that the District will receive mission assignments from the Federal 2-18 Emergency Management Agency (FEMA) under the provisions of PL93-288 to perform preliminary damage assessments and to prepare detailed damage survey reports in Long Island and New Jersey in FY 1986. As a result of continued low precipitation in niorthern New Jersey and southeastern New York State, the New York District has been actively monitoring the water levels of the reservoir systems in these areas on a weekly basis in order to determine possible response measures to assist the States of New York and New Jersey during the on-going drought emergency, although drought restrictions were eventually lifted in New Jersey in late summer, monitoring will continue in New York State until water levels approach the normal reservoir level percentage capacity during FY 1986. 41. EMERGENCY STREAMBANK AND SHORELINE PROTECTION Activities pursuant to Section 14, Public Law 526, 79th Congress as amended (Preauthorization) (See Table 2-Q at end of chapter.) 42. SURVEYS (See Table 2-J at end of chapter.) 43. COLLECTION AND STUDY OF BASIC DATA Costs for the period of $110,300 for flood plain management services are set forth in Table 2-L at the end of chapter. 44. DEAUTHORIZED PROJECTS A total of 23 projects were deauthorized by Congressional Action pursuant to Section 12 of Public Law 93-251, Water Resources Development Act of 1976. (See Table 2-M at end of chapter.) NEW YORK, N.Y. DISTRICT TABLE 2-A COST AND FINANCIAL STATEMENT See Section Funding FY82 FY83 FY84 FY85 Total Cost to in Text Projects September 30, 1985 1. Aquatic Plant Control 2. Bay Ridge & Red Hook Channels, N.Y. 3. Bronx River, N.Y. 4. Buttermilk Channel, N.Y. 5. East Chester Creek, N.Y. 6. East River, N.Y. 7. East Rockaway Inlet 8. Fire Island To Jones Inlet, N.Y. 9. Hudson River, N.Y. 10. Jamaica Bay, N.Y. 11. Jones Inlet, N.Y. 12. Keyport Habor, N.Y. New Work Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost 84,000 105,000 150,771 102,224 1,598,000 1,590,956 1,039,000 988,914 336,000 343,044 -800 45,349 - -. -. -. - -80 -534 - 100,000 5,614 129,779 18 488,000 482,930 1,315,000 1,315,000 100,000 43,973 1,339,000 1,339,000 3,937 21,005 1,838,256 758,400 1,314,247 1,299,002 - - 98,000 98,000 603,000 603,000 185,000 903,806' 176,102 818,5672 - 5,523,297 - 5,523,29727 7,059,000 30,004,988 7,056,993 30,002,981 - 1,149,946 - 1,149,946 60,000 2,007,853 59,390 2,007,2435 - 4,590,201 - 4,590,201' 640,000 4,239,773 640,000 4,239,773 - 592,056 - 592,056 717,000 1,471,042 716,771 1,471,813 - 32,750,745 - 32,723,6621" 1,437,000 4,449,769 1,436,030 4,448,799" - 83,969 - 533,3344 390,034 5,492,736 377,768 5,480,470 - 594,355 - 594,35528 1,695,700 4,700,404 1,681,761 4,742,863 - 44,249,803678 - 44,249,865 673,000 27,582,815 579,097 27,396,426 - 4,545,753 - 4,545,753 1,310,000 3,914,547 1,284,412 3,888,959 - 1,822,53010 - 1,822,53010 1,709,966 11,137,176 1,699,398 11,126,607 - 40,475 - 40,475 31,000 848,148 30,979 848,127 2-19 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 2-A (Continued) COST AND FINANCIAL STATEMENT See Section Funding FY82 FY83 FY84 FY85 Total Cost to in Text Projects September 30, 1985 13. Moriches Inlet, N.Y. (Required Contributed Funds) 14. Narrow of Lake Champlain,N. Y. 15. Newark Bay, Hackensack & Passaic Rivers,N.J. 16. New York and New Jersey Channels 17. New York Harbor- Collection and Removal of Drift (Required Contributed Funds) 18. New York Harbor- Entrance Channel and Anchorage Areas 19. Port Chester Harbor N.Y. 20. Raritan River, NJ. 21. Sandy Hook Bay, NJ. New Work Approp. Cost Maint. Approp. Cost New Work Contrib. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost Rehab. Approp. Cost New Work Approp. Cost Maint. Approp. Cost Maint&Oper Approp. Cost New Work Approp. Cost New Work Approp. Cost Maint. Approp. Cost New York Approp. Cost Maint. Approp. Cost New York Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost 60,390 20,660 - - 43,446 358,855 16,000 25,000 14,453 26,547 - 630,000 - 630,000 2,224,000 7,681,000 2,218,610 2,615,509 - - 100,000 81,283 -, 29,000 28,744 3,866,000 3,936,107 - 3,632,000 680,000 8,704,000 3,623,281 657,732 8,386,840 1,100,000 2,570,000 2,700,000 1,293,239 1,654,623 2,960,800 4,435,000 - - 4,363,879 - - 3,025,000 - 2,700,000 2,850,036 3,245,344 2,960,800 286,222 470,459 1,380,950 727,405 181,077 1,250,972 970 - - - 8,047,000 8,739,000 - 7,525,976 9,132,502 - - 180,000 - - 177,126 15,000 -0- -0- -0- -0- -0- 30,000 29,326 (295,000) (296,200) 1,046,000 1,012,282 9,422 9,422 3,390,000 402,301 681,81112 681,81112 939,695 938,744 29,014,510 9,014,51122,23 27,251,036 22,254,45224 73,053,435 73,052,43515,16,17 1,162,000 4,976,359 1,096,073 39,259,67418 - 454,773 - 454,773 1,930,000 17,229,000 1,801,315 16,220,742 - 42,192,89619 - 42,387,71819 2,820,000 2,786,239 707,096 537,350 18,069,000 17,205,706 6,464,328 5,593,62229 - 45,009,71020 - 45,009,71020 3,419,900 36,349,524 3,508,699 39,071,93830 - 433,470 - 433,470 617,000 1,060,795 616,303 1,060,098 - 1,551,47021 - 1,551,470"25 1,119,000 11,412,70326 1,119,269 11,410,298 - 508,936 - 508,936 3,750,000 3,904,565 3,747,763 3,902,328 2-20 NEW YORK, N.Y. DISTRICT TABLE 2-A (Continued) COST AND FINANCIAL STATEMENT See Section Funding FY82 FY83 FY84 FY85 Total Cost to in Text Projects September 30, 1985 22. Shinnecock Inlet, N.Y. 23. Shrewsbury River,N.J. 24. Supervisor of New York Harbor 28. East Rockaway Inlet to Rockaway Inlet and Jamaica Bay, N.Y. (Part I) (Required Contributed Funds) 29. Sea Bright to Ocean Tnp,N.J. 32. Ardsley, N.Y. 33. Elizabeth, N.J. (Other Contributed Funds) 34. Liberty State Park and Seawall, N.J. 35. Passaic River Basin, N.J.&N.Y., Phase I 3122(516) 36. Sawmill River, Elmsford-Greenburg, N.Y. New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost Maint. Approp. Cost New Work Approp. Cost New Work Contrib Cost New Work Approp Cost New Work Approp. Cost New Work Approp. Cost New Work Approp. Cost New Work Approp. Cost New Work Approp. Cost New Work Approp. Cost 745,000 745,758 3,800,000 3,664,868 3,457,300 3,479,764 48,886 7,650,000 7,841,068 1,136,390 882,918 -6,000 20,519 1,845,076 1,845,076 5,638 832,000 784,221 220,088 127,660 186,169 846 9,663,000 8,841,979 1,214,707 1,635,180 1,634,000 1,635,287 -0- -0- 151 173 - 1,145,457 - 1,145,457 80,000 1,812,880 79,472 1,813,352 483,006 526,571 2,900,000 2,918,123 3,967 45,000 32,325 6,300,000 7,293,978 1,535,000 1,523,696 7,600 560,000 564,738 2,250,000 2,224,852 27,563,447 28,046,393 17,900,356 17,871,469 2,316,000 17,120,961 2,251,199 14,633,942 1,300,000 1,300,000 1,252,310 1,252,310 15,000 360,000 -0- 332,324 3,100,000 54,556,800 2,634,945 54,091,744 990,000 4,353,665 885,914 4,891,004 20,000 200,043 -0- 180,038 37,000 13,557,7003 30,902 13,473,580 - 490,000 - 490,000 2-21 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 1. Of which $12,500 is for North Atlantic Division Accounts. 2. Of which $12,127 is for North Atlantic Division Accounts. 3. Include $1,040,000 for new work and $1,040,000 expended for the portion under construction general. 4. Excludes $100,000 for new work expended from contributed funds and includes $82,600 for new work expended from public work funds. 5. Includes $68,036 for new work and $26,931 for maintenance for previous projects. 6. Includes $5,112,694 for new work for previous project. 7. Includes $238,350 for new work expended from public works funds and $311,461 emergency relief funds. Excludes $81,373 expended from contributed funds. 8. Excludes $454,273 expended between August 18, 1915 and June 30, 1935, for operation and care of lock and dam at Troy, N.Y., under permanent indefinite appropriation. Excludes $23,735 reimbursement for repairs to Troy Lock. 9. Includes $122,051 public works funds and $496,250 for new work for previous projects. 10. Excludes $1,882,530 for new work expended from contributed funds. 11. Includes $6,187,694 for new work and $37,664 for maintenance for previous projects. 12. Includes $115,000 for new work expended from contributed funds. 15. Includes $12,809,975 for new work for previous projects and $6,621 for new work for Lemon Creek, Staten Island, N.Y. 16. Excludes $7,712 for new work expended from contributed funds. 17. Includes $807,000 for new work expended from public works funds and $2,023,308 for new work expended from emergency relief funds. 18. Includes $1,160,380 for maintenance for previous project, and $1,621 for maintenance of Lemon Creek, Staten Island, N.Y. 19. Includes $2,491,206 expended to date for construction of a land-based overfire air pit incinerator ($1,493,393 in maintenance funds and $997,813 in O&M funds). 20. Includes $116,530 applied to removing wrecks authorized by acts prior to adoption of existing project. 21. Includes $673,155 for new work for previous project. 22. Includes $1,836,403 for new work expended from contributed funds. 23. Excludes $285,600 for new work expended from contributed funds. 24. Includes $1,490,715 for maintenance for previous projects. 25. Excludes $292,685 for new work expended from Ordinance funds and $66,000 for new work expended from contributed funds. 26. Includes $111,419 for maintenance for previous projects and $64,560 extended from public works funds. 27. Includes $1,246,100 for new work for previous projects and $64,560 extended from public works funds. 28. Excludes $90,190 for new work expended from contributed funds. 29. Includes $400,000 Jobs Bill funds. 30. Includes $200,000 Jobs Bill funds. 2-22 TABLE 2-A (Continued) COST AND FINANCIAL STATEMENT NEW YORK, N.Y. DISTRICT TABLE 2-B AUTHORIZING LEGISLATION Acts Work Authorized Documents River and Harbor Act of 1958 Section 104 and Harbor Act of 1958 Section 302 River and Harbor act of 1965 Mar. 3,1899 Mar. 2, 1907 July 3, 1930 Mar. 4, 1913 June 13, 1902 May 17, 1950 Mar. 2, 1915 July 27, 1916 Aug. 8, 1917 Do. July 18, 1918 Sept. 22, 1922 E. Pub. Wks. Comm. Res., Dec. 15, 1970 and S. Pub. Wks Comm. Dec. 17, 1970 AQUATIC PLANT CONTROL (See Section 1 of Text) Control and Progressive Eradication of obnoxious Aquatic Plant growths Provided that all research and Planning cost to be borne fully by the United States. Modified project to include control of waterchestnut. BAY RIDGE AND RED HOOK CHANNELS, N.Y. (See Section 2 of Text) Channel 40 feet deep and 1,200 feet wide. Dredging to obtain first a depth of 35 feet, subsequently increasing depth of 40 feet for full width. Widening of Bay Ridge Channel to 1,780 feet. BRONX RIVER, N.Y. (See Section 3 of Text) Channel 10 feet deep and 100 feet wide from East River to Dam at East 177th Street. BUTTERMILK CHANNEL, N.Y. (See Section 4 of Text) Channel 1,200 feet wide and not less than 30 feet deep. EAST CHESTER CREEK, N.Y. (See Section 5 of Text) Channel 10 feet deep and 150 to 70 feet wide. EAST RIVER, N.Y. (See Section 6 of Text) Removal of Coenties Reef to 35 feet, conditioned upon local interests increasing depth to 40 feet Channel across Diamond Reef 35 feet deep and 1,000 feet wide. Channel east of Blackwells Island to 20 feet; channel between South Brother and Berrian Islands, to 20 feet; channel between North and South Brother Islands to 26 feet. Channel 40 feet deep through East River and Hell Gate. Secure a depth of 40 feet in channel through East River and Hell Gate as soon as practicable. Depth limited to 35 feet in through channel between Wallabout Channel and Throgs Neck, Channel east of Blackwells Island, 30 feet to English Pl. and eliminated 20-foot channel north of English Pl. Eliminated channel between North and South Brother Islands except as authorized prior to existing project. Remove certain rocks and reefs and construct dike in pot cove, Hell Gate. Spur channel to Astoria waterfront 37 feet in rock, 35 feet in material, for a length of 0.95 mile for varying widths, and a turning basin. (South Brother Island Channel). EAST ROCKAWAY INLET, N.Y. (See Section 7 of Text) July 3, 1930 Channel 12 feet deep and 250 feet wide, and a jetty. Aug. 26, 1937 May 17, 1950 FIRE ISLAND TO JONES INLET, N.Y. (See Section 8 of Text) Construction of jetty. Channel 10 feet deep. H. Doc. 37, 85th Cong., 1st sess. H. Doc. 337, 54th Cong. 2d Sess. (Annual Report 1899, P. 1177). Rivers and Harbors Committee Doc. 44, 71st Cong. 2d sess. H. Doc. 897, 62d Cong. 2d sess. H. Doc. 122, 56th Cong., 2d sess. (Annual report 1901, p. 1299) H. Doc. 749, 80th Cong., 2d sess. H. Doc. 188, 63d Cong., 1st sess. Do. Do. H. Doc. 140, 65th Cong,, 1st sess. Specified in act Rivers and Harbors Committee Doc. 3, 67th Cong., 2d sess. S. Doc. 91-60, 91st Cong., 2d sess. H. Doc. 19, 71st Cong., 1st sess. Rivers and Harbors Committee Doc. 33, 75th Cong. 1st sess. H. Doc. 762, 80th Cong., 2d sess. 2-23 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 2-B (Continued) AUTHORIZING LEGISLATION Acts Work Authorized Documents June 25, 1910 Mar. 3, 1925 July 3, 1930 Aug. 30, 1935 June 20, 1938 Sep. 3, 1954 P.L. 89-72 June 25, 1910 March 2, 1945 May 17, 1950 Mar. 2, 1945 Aug. 2, 1882 July 14, 1960 Aug. 8, 1917 Mar. 2, 1907 Feb. 27, 1911 July 25, 1912 Jan. 21, 1927 July 3, 1930 Mar 22, 1945 Mar. 2, 1945 Sept. 3, 1954 Oct. 23, 1962 HUDSON RIVER, N.Y. (See Section 9 of Text) Channel 12 feet deep from Hudson to Waterford, remove State lock and dam at Troy and construct a new lock and dam.' Channel 27 feet deep below Hudson to Albany, N.Y. Channel 27 feet below Hudson Operation and care of lock and dam at Troy were included in project July 1, 1935. Relocation of 12-foot channel between Troy and Waterford. Deepen channel between Albany and Waterford to 14 feet with no change in depths for harbors in front of Albany and Troy. Deepen channel between New York City and Albany to 32 feet and construct a turning basin and 2 anchorages. Mooring facilities. JAMAICA BAY, N.Y. (See Section 10 of Text) Construction of 1 jetty Interior channel along. west shore of bay, 18 and 12 feet deep; interior channel along south shore, 15 feet deep; entrance channel 20 and 18 feet deep; and 1 riprap jetty all in lieu of work heretofore authorized. Modified conditions of local cooperation. Channel 15 feet deep in Mott Basin including its 2 branches. JONES INLET, N.Y. (See Section 11 of Text) Construction of jetty and channel 12 feet deep and 250 feet wide. KEYPORT HARBOR, N.J. (See Section 12 of Text) A channel 8 feet deep, 200 feet wide from Raritan Bay to the former Steamboat Dock at Keyport MORICHES INLET, N.Y. (See Section 13 of Text) Channel 10 feet deep and 200 feet wide in inlet and 6 feet deep and 100 feet wide in the Bay, and 2 jetties NARROWS OF LAKE CHAMPLAIN, N.Y. AND VERMONT (See Section 14 of Text) Channel 12 feet deep and 150 feet wide. NEWARK BAY, HACKENSACK AND PASSAIC RIVERS, N.J. (See Section 15 of Text) 16-foot channel in Passaic River Widening 16-foot channel in Passaic River 20-foot channel in Passaic River. 10-foot channel in Passaic River. 30-foot channel in Passaic River. 35 and 37 feet in main channel of Newark Bay and branch channel to an inshore channel at Port Newark terminal and remove portion of rock area at Bergen Point to same depths. Modification of local cooperation for 10-foot channel in Passaic River 34-32 foot channel in Hackensack River including approach channel in Newark Bay from branch channel at Port Newark Terminal and a 25-foot turning basin. 35-foot channels at Port Elizabeth. H. Doc. 719, 61st Cong., 2d sess. H. Doc. 350, 68th Cong., 1st sess. H. Doc. 210, 70th Cong., 1st sess. S. Doc. 155, 72nd Cong., 2d sess. H. Doc. 572, 75th Cong., 3d sess. H. Doc. 228, 83d Cong. 1st sess. H. Doc. 1488, 60th Cong. 2d sess. H. Doc. 700, 76th Cong. 3d sess. H. Doc. 665, 80th Cong., 2d sess. H. Doc. 409, 77th Cong. R&H Act Public Law 42-153 3d. sess. H. Doc. 126, 86th Cong., 1st sess. H. Doc. 1387, 62d Cong., 3d sess. H. Doc. 441, 59th Cong., 2d sess. H. Doc. 441, 59th Cong., 2d sess. H. Doc. 707, 62d Cong., H. Doc. 284, 60th Cong., 2d sess. H. Doc. 156, 71st Cong., 2d sess. S. Doc. 250, 79th Cong., 2d. sess. H. Doc. 430, 76th Cong., 1st sess. H. Doc. 252, 82d Cong., 1st sess. H. Doc. 289, 88th Cong., 2d sess. 2-24 NEW YORK, N.Y. DISTRICT TABLE 2-B (Continued) AUTHORIZING LEGISLATION Acts Work Authorized Documents Nov. 7, 1966 H. Doc. 494, 89th Cong., 2d sess. Report on file in the Office of the Chief of Engineers. Rivers and Harbors Committee Doc. 17, 71st Cong., 2d sess. H. Doc. 133, 74th Cong., 1st sess. H. Doc. 233, 81st Cong., 1st sess. H. Doc. 108, 89th Cong., 1st sess. Widening 35-foot channel in Newark Bay, provision of two maneuvering areas, widening entrance into Port Elizabeth and Port Newark branch channels, deepening and widening Newark Bay 32-foot channel, and provision of a turning basin at junction of Hackensack and Passaic Rivers; and deepening 12 foot channel in Hackensack River to 15 feet. Additional widening at junction with Kill Van Kull by deepening to 35 feet a triangular area at the eastern end of the 30-foot channel south of Shooters Island. NEW YORK AND NEW JERSEY CHANNELS (See Section 16 of Text). Anchorage off Perth Amboy to 35 feet. Channels 35 feet deep from lower bay to upper bay, except between vicinity of Smith Creek and vicinity of Piles Creek to 30 feet with anchorage 38 feet deep at Sandy Hook and Perth Amboy. Channel 35 feet deep from vicinity of Smith Creek to vicinity of Piles Creek. Widen entrance to Kill Van Kull to 1,400 feet narrowing to a minimum width of 1,000 feet. NEW YORK HARBOR, COLLECTION AND REMOVAL OF DRIFT (See Section 17 of Text) Allotment from appropriations made for New York Harbor and its immediate tributaries may be used for collection and removal of drift in these waterways. Carrying on this work as a separate and distinct project. Increase scope of project to include removal and disposal of derelict vessels, some deteriorated shore structures and debris along shores; and the repair of other shore structures; all subject to approval by Secreatry of the Army and the President. Removal and disposal of derelict vessels, some deteriorated shore structures and debris along shores and the repair of other shore structures. NEW YORK HARBOR, ENTRANCE CHANNELS AND ANCHORAGE AREAS (See Section 18 of Text) Main-Ship-Bayside-Gedney to 30 feet for width of 1,000 feet (dimensions fixed by Secretary of War, Dec. 27, 1886 by authority of act of Aug. 5, 1886). Ambrose Channel (East Channel) to 40 feet. Maintenance of entrance channel under 1 head. Anchorage Channel, extension of Ambrose Channel into Upper Bay Removal of Craven Shoal PORT CHESTER HARBOR, N.Y. (See Section 19 of Text) Entrance channel 12 feet deep, thence 10 feet deep to and and including turning basin, thence 3 feet deep to head of improvement. Widening turning basin, dredging anchorage basin, and constructing fenders on east bank. RARITAN RIVER, N.J. (See Section 20 of Text) Channel 15 feet deep and 200 feet wide to Washington 10 feet deep and 150 feet wide to canal locks and 10 feet deep thru South Channel.7 2-25 Sept. 6, 1933 Aug. 30, 1935 May 28, 1935 May 17, 1950 Oct. 27, 1965 Mar. 4, 1915 Aug. 8, 1917 July 3, 1930 Dec. 31, 1970 Mar. 7, 1974 July 5, 1884 Mar. 3, 1899 June 25, 1910 Aug. 8, 1917 Aug. 8, 1917 June 25, 1910 July 3, 1930 Mar. 2, 1919 P.L. 91-611, 91st Cong., H.R. 19877 P.L. 93-251, 93rd Cong., H.R. 10203 Annual Reports 1887, p. 62 and 1888, p. 63 H. Doc. 159, 55th Cong., 3d sess. (Annual Report 1899, p. 1279) H. Doc. 518, 63d Cong., 2d sess. H. Doc. 557, 64th Cong., 1st sess. H. Doc. 1165, 60th Cong., 2d sess. Rivers and Harbors Committee Doc. 23, 70th Cong., 2d sess. (contains published map). H. Doc. 1341, 62d Cong., 3d. sess. REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 2-B (Continued) AUTHORIZING LEGISLATION Acts Works Authorized Documents Jul. 3, 1930 Jul. 3, 1930 Jul. 3, 1930 Aug. 26, 1937 Oct. 17, 1940 Oct. 23, 1962 Aug. 26, 1937 July 14, 1960 Mar. 2, 1919 Aug. 30, 1975 Aug. 30, 1935 May 17, 1950 1965 Flood Control Act 1974 Water Resources Development Act .July 3, 1958 Set tion 201 Flood Control Act of 1965 1965 Flood Control Act 1976 Water Resources Development Act Channel 25 feet deep and 300 feet wide up to New York and Long Branch Railroad bridge. Channel 10 feet deep in earth and 11 feet in rock to New Brunswick. Width reduced to 100 feet. Relocation of lower reach of South Channel. Committee Channel 25 feet deep and 300 feet wide to junction of main and south channels thence of same depth on South Channel to Titanium Pigment Co. Channel 25 feet deep and 300 feet wide from junction of main and south channels to government wharf, including a turning basin. In South Channel, maintenance of 15-foot channel to dock of Middlesex County Sewerage Authority. SANDY HOOK BAY, N.J. (See Section 21 of Text) SHINNECOCK INLET, N.J. (See Section 22 of Text) Channel 10 feet deep and 200 feet wide in Inlet, and 6 feet deep and 100 feet wide in the Bay, and 2 jetties. SHREWSBURY RIVER, NJ. (See Section 23 of Text) Channel 6 feet in North Branch Channel 12 feet deep. Channel 9 feet deep. Turning basin and anchorage 6 feet at Red Bank and Channels 6 feet deep in Claypit, Oceanport, and Little Silver Creeks. EAST ROCKAWAY INLET TO ROCKAWAY INLET AND JAMAICA BAY, N.Y. (PART 1). (See Section 28 of Text) Hurricane barrier, dikes, levees, floodwalls, fill, placement, stoplog structures, stairways, ramps, road raising, fishing platforms, annual nourishment. Authorized beach erosion control aspect to be constructed independent of the hurricane flood protection aspect of the project. SEA BRIGHT TO OCEAN TOWNSHIP, N.J. (See Section 29 of Text) Restoration of beach to minimum width of 100 feet at height of 10 feet above mlw, and construction of 23 new groins and extension of 14 existing groins. ARDSLEY, N.Y. (See Section 32 of text) Channel improvement, concrete flume, flood walls, levees, various drainage structures. ELIZABETH, N.J. (See Sction 33 of Text) Channel improvement, flume, levees, floodwalls, bridges, interior drainage facilites. LIBERTY STATE PARK LEVEE AND SEAWALL, N.J. (See Section 34 of Text) Approxmately 7,000 feet of seawall and elevated pedestrian walkway. H. Doc. 127, 70th Cong., 1st sess. H. doc. 454, 70th Cong., 2d sess. Rivers and Harbors Doc. 31, 71st Congs., 2d sess. Rivers and Harbors Committee Doc. 74, 74th Cong., 2d sess. Report on file in the Office, Chief of Engineers (report not printed) H. Doc. 455, 86th Cong., 2d sess. H. Doc. 292, 75th Cong., 1st sess. H. Doc. 126, 86th Cong. 1st sess. FY83 Supplemental Approp. Act H. Doc. 1296, 62d. Cong., 3d sess. H. Doc. 157, 71st Cong., 2d sess. Rivers & Harbors Committee Do. 31, 74th Cong., H. Doc. 285, 81st Cong., 1st sess. H. Doc. 215, 89th Cong., 1st sess. H. Doc. 332, 85th Cong., 2d sess., modified by Appr. Act for Energy and Water Dev. for FY85 H. Doc. 215/89/1. Doc. 249, 89th Cong., 1st sess. 2-26 NEW YORK, N.Y. DISTRICT TABLE 2-B (Continued) Acts Works Authorized Documents PASSAIC RIVER BASIN, N.J. & N.Y., PHASE I (See Section 35 of Text) 1976 Water Resources Advanced engineering and design study, involving H. Rpt. 94-1702 1 Development Act reformulation of plans for flood control and water resource Section 101 (a) management. SAW MILL RIVER AT ELMSFORD AND GREENBURGH, N.Y. (See Section 36 of Text) 1965 Flood Control Act Levess, floodwalls, channel improvement. H. Doc. 94-465, 94th Cong., 2d sess. 2-27 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 2-C HUDSON RIVER, N.Y. FEATURES OF LOCK AND DAM INCLUDED IN EXISTING PROJECT (See Section 9 of Text) Location: Below Waterford Above Battery, New York City Locks: Clear Width Greatest length available for full width Lift at lowest stages Depth on miter sills: Upper (at normal pool level) Lower (at lowest low water) Character of foundation: Rock Kind of dam: Fixed Crest Type of construction: Concrete Completed: 1917 Cost: $1,463,014 2.2 miles 153.8 miles 44.4 feet 492.5 feet 17.3 feet 16.3 feet 13.0 feet TABLE 2-D TOTAL COSTS FOR EXISTING PROJECT TO SEPTEMBER 30, 1985 See Section Operation of Text Project Funds New York Rehabilitation Maintenance and Cost Total 6. Hudson River, Regular $38,560,839 - $579,097 $512,382 $42,379,312 N.Y. Public Works 238,350 - - - 238,350 Emergency Relief 311,461 - - - 311.461 TOTAL $39,110,650 - $579,097 $512,382 $42,929,123 16. N.Y. and NJ. Regular $57,412,152 - $1,096,073 - $67,901,957 Channels Public Works 807,000 - - - 807,000 Emergency Relief 2,023,308 - - - 2,023,308 Contributed 7,712 - - - 7,712 TOTAL $60,250,172 - $1,096,073 - $70,739,977 TABLE 2-E SUPERVISOR OF NEW YORK HARBOR (See Section 24 of Text) STATEMENT OF ACTIVITIES-FY 1985 1. Number of Patrols a. Shore 310 b. Vessel 350 SAir (helicopter)- Total 660 2. Number of Inspections a. Shore Facilities 4,225 b. Vessels 1.050 Total 5,275 3. Disposition of Cases a. Voluntary Restoration 30 b. After-the-fact Permit Applications Accepted 45 c. Permit not required or already under permit 54 d. Submitted for litigation to OCE or US Attorney 0 e. Cases pending as of October 1, 19828 Total 211 2-28 NEW YORK, N.Y. DISTRICT TABLE 2-F RECONNAISSANCE AND CONDITION SURVEYS FY 1985 NAME OF PROJECT DATE SURVEY CONDUCTED NEW JERSEY Keyport Harbor............................ . ....................... Nov. 1984 Matawan Creek................ ................................. Nov. 1984 Newark Bay, Hackensack & Passaic Rivers .................................... Oct., Nov., 1981-Feb. 1985 Raritan River............................ ............................ Dec., 1984-Feb., 1985 Sandy Hook Bay .................................................. May, June, 1985 Shark R iver ..................................................... * Shrewsbury River ................... .......... ..................... Oct., Dec., 1984-Feb., Apr., June 1985 NEW YORK Bay Ridge & Red Hook Channel ............................................. Mar., Jun., Jul. 1985 Bronx River ............................... ........................ Oct., Nov., 1984 Browns Creek.....................................................* East River............................................................. Dec., 1984-Aug. 1985 East Rockaway Inlet .................. ..................................... M ar., Aug., Sept., Oct. 1985 Eastchester Harbor .................. ...................................... Dec., Nov., 1984-Apr., M ay 1985 Fire Island Inlet .................. ......................................... Nov., Dec., 1984-Apr., Jul. 1985 G reat South Bay .................................................. Hudson River .................. ................................. * H untington H arbor .................. ...................................... * Jamaica Bay................................ ....................... Mar., Jul., Aug., 1985 Jones Inlet ........................... ............................. Aug., Sept. 1985 Long Island Intracoastal Waterway ........................................... Oct., 1984-Apr., May 1985 M am aroneck H arbor ................. ..................................... * Mattituck Harbor ........................................................ June 1985 Moriches Inlet ................. .................................. * Narrows of Lake Champlain ................. ............................... * N ew Rochelle H arbor ................. ...................................... * Newton Creek .............. .................................... * Plattsburg H arbor ................. ........................................ * Port Chester H arbor ................. ...................................... * PortJefferson Harbor ............. ................................. * Rondout Point................. .................................. * Rouses Point ............ .......... **............................ Shinnecock Inlet ................ .......................................... * SumpawanusInlet.............*..................................* *Items for which no date is furnished reflect costs for gathering data only. Total cost of Reconnaissance and Condition Surveys in Fiscal Year 1985 was $789,817. 2-29 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 2-G OTHER AUTHORIZED NAVIGATION PROJECTS Cost to Sept. 30, 1985 For Last Full Report See Annual Operation and Projects Report For Construction Maintenance Burlington Harbor, Vt.' 1966 706,414' 283,556 Channel between North and South Hero Island, Lake Champlain, Vt.1 ,2 1909 31,000 1,288 Coney Island Inlet, N.Y. 1973 111,371 284,109 Echo Bay Harbor, N.Y.1 1953 64,584 11,571 Flushing Bay and Creek, N.Y. 1984 2,102,9057 4,352,089 Glen Cove Creek, N.Y. 1981 29,76012 126,820 Gordons Landing, Lake Champlain, Vt.1 ,2 1892 34,750 115 Gowanus Creek Channel, N.Y. 1972 346,831 255,291 Great Chazy River, N.Y. 1980 18,000 292,919 Great Kills Harbor, N.Y.1,2 1962 137,301" 88,029 Great Lakes to Hudson River Waterway, N.Y. 1976 457 Great South Bay, N.Y.' 1974 266,857 1,290,469 Greenport Harbor, N.Y.' 1953 74,681 21,720 Harlem River, N.Y.' 1969 3,616,119 480,777 Hempstead Harbor, N.Y. 1969 39,468 76,49716 Hudson River Channel, N.Y. 1980 6,771,87027 24,970,637 Jamaica Bay, N.Y. 1981 4,545,753 2,604,547 Lake Montauk Harbor, N.Y. 1984 791,680" 849,709 Larchmont Harbor, N.Y. 1970 76,065 267,768 Lemon Creek, N.Y. (Inactive) 2 ,' 1937 6,621 1,621 Little Neck Bay, N.Y.' 1969 1,741,210"9 537 Long Island Intra Coastal W/W, N.Y. 1984 235,964 3,716,834 Mamaroneck Harbor, N.Y. 1981 513,764 551,677 Manhasset Bay, N.Y. (Inactive)3 1948- 4,636 Matawan Creek, NJ. 1984 21,000 237,097 Mattituck Harbor, N.Y. 1981 177,92532 935,786 Milton Harbor, N.Y. 1984 151,3731* 986,520 New Rochelle Harbor, N.Y.', 2 1971 73,2148 142,411 Newtown Creek, N.Y. (Active)',' 1974 1,168,354 1,626,35122 Northport Harbor, N.Y.' 1956 78,64423 1,487 Orowoc Creek, N.Y.(Inactive) 3 1949 - 4,951 Otter Creek, Vt. 1977 60,254 27,059 Peconic River, N.Y.' 1953 25,000 116,509 Peekskill Harbor, N.Y.' 1951 19,400 66,037 Plattsburgh Harbor, N.Y.' 1972 198,415 229,111 Port Henry Harbor, N.Y.' 1931 69,406"2 1,299 Port Jefferson Harbor, N.Y. 1977 221,128" 359,294 Raritan River to Authur Kill Cutoff Channel, N.J.' 1972 810,500 2,019,141 Rondout Harbor, N.Y.' 1972 142,437 260,441 Rouses Point, Lake Champlain, N.Y.' 1895 98,468 249 Sag Harbor, N.Y.' 1964 121,80526 11,710 St. Albans Harbor, Lake Champlain, Vt.', 2 1917 3,125 385 Sandy Hook Bay at Leonardo, N.J.', 2 1967 56,470 93,964 Saugerties Harbor, N.Y.', 2 1968 81,905 169,18128 Shark River, N.J. 1984 488,048"29 1,129,10029 Sheepshead Bay, N.Y.' 1948 33,828 5,364 Shoal Harbor & Compton Creek, N.J. 1984 124,57220 1,104,94021 Shooters Island, N.Y.&N.J. 1983 100,000 Staten Island Rapid Transit Railway Co. bridge across Arthur Kill, N.Y. 1973 7,730,476 Sumpawanus (Babylon Creek) Inlet, N.Y.', 2 1895 7,000 13 Tarrytown Harbor, N.Y.' 1974 69,836 431199 Wallabout Channel, N.Y.' 1953 18,174 36,312 Wappinger Creek, N.Y.', 2 1950 13,000 44,691 Washington Canal and South River, N.J. 1953 206,116 212,82730 Waycake Creek, N.J.2,' 1949 - 2,781 Woodbridge Creek, N.J.' 1953 49,823 178,398 2-30 NEW YORK, N.Y. DISTRICT OTHER AUTHORIZED NAVIGATION PROJECTS 1. Completed. 2. No commerce reported. 3. Awaiting local cooperation. 5. A portion of this project is classified "inactive." 6. Includes $69,036 for new work and $26,921 for maintenance for previous project. Excludes $10,000 for new work expended from contributed funds. 7. Excludes $419,879 for new work expended from contributed funds and $580,425 contributed funds other and $8,752 expended by the Worlds Fair Corp. for riprap protection of rubble dike. 8. Includes $43,175 for new work for previous projects. 9. Includes cost of maintenance prior to July 1, 1886. Excludes $1,425,133 for rehabilitation. 11. Excludes $82,738 expended for new work from Navy Dept. funds. 12. Excludes $29,774 for new work expended from contributed funds. 13. Includes $4,813,400 for new work expended from emergency relief funds. 14. Excludes $94,366 for rehabilitation. 15. Excludes $104,805 for new work expended from contributed funds. 16. Includes $64,034 for maintenance of previous projects. 17. Excludes $19,546 for new work expended from contributed funds and $31,454 to be contributed. 18. Excludes $119,276 required contributed funds and $72,619 other contributed funds. 19. Excludes $1,741,210 for new work expanded from contributed funds. 20. Includes $17,000 for new work for previous projects. 21. Includes $169,700 for maintenance for previous projects. 22. Includes $421,817 for maintenance for previous projects. 23. Excludes $15,000 for new work expended from contributed funds. 24. Includes $16,369 for maintenance for previous projects. 25. Excludes $10,000 for new work expended from contributed funds. 26. Excludes $66,758 for rehabilitation. 27. Includes $668,820 public works funds. 28. Includes $15,000 for maintenance for previous projects. 29. Includes $338,048 contributed funds. 30. Includes $84,934 for maintenance for previous projects. 31. Includes costs for new work $171,427 and maintenance $20,646 for previous projects. 32. Excludes $34,580 for new work from contributed funds. TABLE 2-H OTHER AUTHORIZED BEACH EROSION CONTROL PROJECTS Cost to Sept. 30, 1985 For Last Full Report See Annual Operation and Projects Report For Construction Maintenance Atlantic Coast of N.J., Sandy Hook to Barnegat Inlets 1959 Fire Island Inlet to Jones Inlet, N.Y. 1981 18,044,667 217,899 North Shore of Long Island, Suffolk County, N.Y. 1979 8,880,000 2 Perth Amboy, N.J. 1966 2-31 TABLE 2-G (Continued) REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 2-I OTHER AUTHORIZED FLOOD CONTROL PROJECTS For Last Construction to Sept. 30, 1985 Full Report See Annual Operation and Projects Report For Construction Maintenance Adams, Hossic River Basin, Mass.' 1964 6,282,3072 - Bennington, Vt. 1974 670,000 - Byram River at Pemberwick, Conn.',' 1959 363,515 - East Barre Dam, Winooski River, Vt.' 1963 2,832,084 - East Rockaway Inlet to Rockaway Inlet and Jamaica Bay, N.Y. (Part II) 1976 1,185,365 - Fire Island to Montauk Point, N.Y. 1984 13,441,8646 143,753 Herkimer, N.Y. 1973 1,201,2759 - Hoosic Falls, Hoosic River Basin, N.Y. 1 1956 1,064,626 - Lamoille River, Vt.: Hardwich Dams +,s,9 1939 -- - Missisquoi River at Richford, Vt. ',s 1965 221,476 - North Adams, Hoosic River Basin, Mass. 1968 15,409,325' - North Ellenville, N.Y. 1978 3,900,650 - RRaahhwwaayy,, N.J. 1971 973,142 - South Branch, N.J. 1979 15,863,723 - Raritan Bay and Sandy Hook Bay, NJ. 1981 11,061,256 262 Rosendale, N.Y. 1975 3,684,966 - Rutland, Otter Creek, Vt.4 1963 211,015 - Sandburg Creek, Spring Glen, N.Y. 1976 109,702 - South Amsterdam, Mohawk River, N.Y.' 1967 1,564,976 - South Ellenville, N.Y. 1984 289,702 - South Orange, NJ. 1981 6,857,484 - Staten Island, N.Y. 1983 644,998 - Wappinger Creek at Pleasant Valley, N.Y.', s 1959 142,075 - Waterbury Reservoir, Winooski River Basin, Vt. 1976 886,769 8,200 Winooski River, Vt.' 1940 5,897,427 - Wrightsville Dam, Winooski River Basin, Vt. 1970 1,549,929 - Yonkers, N.Y. 1984 13,641,77110- 1. Completed. 2. Excludes costs of $913,360 under other contributed funds. 3. Authorized by Chief of Engineers pursuant to Sec. 205, Public Law 858, 80th Cong., as amended. 4. Inactive. 5. Includes $23,507 emergency relief funds. 6. 7. 8. 9. 10. Includes $3,788,341 contributed funds. Excludes cost of $21,000 under other contributed funds. Excludes cost of $51,500 under other contriubted funds. Uncompleted portion has been deauthorized on August 5, 1977. Includes $622,'871 contributed funds. 2-32 NEW YORK, N.Y. DISTRICT TABLE 2-J SURVEYS (See Section 42 of Text) Study Class Cost Navigation Studies Flood Control Studies Beach Erosion Studies Special Studies1 Total Surveys $1,850,738 6,525 0 1,966,311 $3,623,574 'Includes review of Authorized Projects, Inspection of Dams, Coordinations Studies with Other Agencies, Planning Assistance to States, International Water Studies Special Investigations, Review of FERC Licenses, Continuation of Planning and Engineers, Advance Engineering and Design and $3,842 by North Atlantic Division. TABLE 2-K FLOOD PLAIN STUDIES COMPLETED DURING THE PERIOD Location Requesting Agency Date Completed Federal Cost NONE-PROGRAM TERMINATED TABLE 2-L COSTS FOR FLOOD PLAIN MANAGEMENT SERVICES (See Section 43 of Text) Studies and Services Cost Flood Plain Technical Services $50,300 Flood Plain Management Unit 60,000 Total $110,300 2-33 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 2-M DEAUTHORIZED PROJECTS (See Section 44 of Text) For Last Full Report Date Federal Contributed .Operation See Annual And Funds Funds and Projects Report For Authority Expended Construction Expended Maintenance Bronx River, N.Y.*,6 1981 Aug. 1982 1,149,946 1,159,94612 10,000 1,947,853' Brown's Creek, N.Y. 1980 Aug. 1977 33,976 33,9768 - 505,369 Cheesequake Creek, N.J.',' 1953 Aug. 1982 40,000 40,000 - 30,675 Coney Island Creek, N.Y. 4,' 1952 Aug. 1982 69,489 69,489 - 1,622 East Rockaway (DEBS) Inlet, N.Y. 1963 Aug. 1977 503,969 603,96913 100,000 829,421 Elizabeth, N.J. 1948 Aug. 1977 60,481 60,481 - 59,391 Glen Cover Harbor, N.Y. 1966 Aug. 1977 165,882 165,8824,11 - 2,455 Hudson River, NYC to Albany'," 1982 Aug. 1982 - - - - Huntington Harbor, N.Y. 1953 Aug. 1977 49,035 68,581',, '" 19,546 51,566 Irvington Harbor, N.Y. 1947 Aug. 1977 - - - - Lamoille River, Vt. 1939 Aug. 1977 49,837 49,837 - - Newark Bay, Hackensack and Passaic Rivers, N.J.', 1'6 1982 Aug. 1982 - - - - New York and New Jersey4," 1982 Aug. 1982 - - - - Portchester Harbor, N.Y.2,3 1967 Aug. 1977 433,470 433,470' - 441,656 Proctor, Otter Creek, Basin, Vt.6,' 1937 Aug. 1977 - - - - Rahway River, N.J.',' 1948 Aug. 1982 - 37,0004 - 307' Raritan River, N.J.*,' 1981 Aug. 1982 1,551,470 1,617,470"1 66,000 10,113,903 Rome Mohawk River, N.Y.6,' 1959 Aug. 1982 7,000 7,000 - - Swanton Harbor, Vt. (Inactive)6 1888 Aug. 1977 - 70,500* - 235 Ticonderoga River, N.Y.',' 1895 Nov. 1983 17,760 16,500 - 1,260 Waterbury (1941 Act), Vt.',' 1951 Nov. 1981 9,253 9,253 - - Waterford, N.Y.',' 1939 Aug. 1982 - - - - Westchester Creek, N.Y. 1981 Aug. 1982 175,933 175,933 - 2,921,311 No commerce reported. Completed. A portion of this project is classifed "inactive." Uncompleted portion deauthorized. Excludes $19,546 for new work expended from contributed funds and $31,454 to be contributed. Inactive. Entire project deauthorized. Excludes $71,423 for rehabilitation. Deferred. 10. 11. 12. 13. 14. 15. 16. 17. 18. Under Section 12 Public Law 93-251. Includes $93,882 for Rehabilitation. Includes $10,000 expended from contributed funds. Includes $100,000 expended from contributed funds. Includes $19,546 expended from contributed funds. Includes $66,000 expended from contributed funds. 1912 authorization. 1935 authorization. 1910 construction dikes. 2-34 1. 2. 3. 4. 5. 6. 7. 8. 9. NEW YORK, N.Y. DISTRICT TABLE 2-N SECTION 3 CONTINUE DETAILED PROJECT REPORT (See Section 27 of Text) Name of Project Cost to Sept. 30, 1985 Shinnecock Inlet, N.Y. $279,487 SECTION 107 PLANS & SPECIFICATIONS (See Section 27 of Text) Name of Project Cost to Sept. 30, 1985 CONTINUE Sheepshead Bay, N.Y. $20,000 TABLE 2-0 SECTION 103 (See Section 31 of Text) Name of Project Cost to Sept. 30, 1985 CONTINUE DETAILED PROJECT STUDY Orchard Beach, Bronx, N.Y. $215,000 2-35 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 2-P SECTION 205 (See Section 40 of Text) Name of Project Cost to Sept. 30, 1985 COMPLETE RECONNAISSANCE REPORT Lamoille River, Hardwick, Vt. $164 Winooski River, Richmond, Vt. $7,500 Bashbish Brook, Copake, N.Y. $7,500 Clavarack Creek, Stockport, N.Y. $7,500 Lake Champlain, Plattsburgh, N.Y. $7,200 CONTINUE DETAILED PROJECT REPORTS Beaver Brook, Dolgeville, N.Y. $179,000 Elizabeth River, Hillside, N.J. $218,800 Missisquoi River, Vt. $219,300 Ramapo River, Monroe, N.Y. $192,300 Sauquoit Creek, Whitesboro, N.Y. $134,200 Yonkers, Nepera Park, N.Y. $76,000 COMPLETE DETAILED PROJECT REPORTS Esopus Creek, Ulster, N.Y. $50,907 Halesite Area, Huntington, N.Y. $7,264 Sheldon Brook, Tarrytown, N.Y. $19,036 CONTINUE PLANS AND SPECIFICATIONS Sawkill Creek, Kingston, N.Y. $98,800 Passaic River (Field Emergency Preparedness System), NJ. $30,900 CONTINUE CONSTRUCTION Wallkill River (Black Dirt Area), N.Y. $1,127,877 COMPLETE CONSTRUCTION Chappaqua, N.Y. (Saw Mill River) $7,960 TABLE 2-Q SECTION 14 (See Section 41 of Text) Name of Project Cost to Sept. 30, 1985 CONTINUE PLANS AND SPECIFICATIONS Bouquet River, Elizabethtown, N.Y. $12,664 COMPLETE PLANS AND SPECIFICATIONS Chichester Creek, Shandaken, N.Y. $5,623 COMPLETE CONSTRUCTION Sandburg Creek, Ellenville, N.Y. $168,657 2-36 PHILADELPHIA, PA DISTRICT* This district comprises a portion of southeastern New York, eastern Pennsylvania, western and southern New Jersey, northern and southeastern Delaware, and a small part of northeastern Maryland embraced in the drainage basins tributary to the Atlantic Ocean from Manasquan River, N.J. inclusive, to south boundary of Delaware. It also includes Chesapeake and Delaware Canal and approach channel thereto in Chesapeake Bay and Elk River, Md. IMPROVEMENTS Navigation Page 1. Barnegat Inlet, N.J.................... . 3-2 2. Cohansey River, N.J. .................... 3-2 3. Delaware River between Philadelphia, Pa., and Trenton, N.J. ........ 3-2 4. Delaware River, Pa., N.J. and Del. Philadelphia to the Sea .................. 3-3 5. Harbor of Refuge, Delaware Bay, Del........ 3-4 6. Indian River Inlet and Bay, Del ........... 3-4 7. Inland Waterway, Rehoboth Bay to Delaware Bay, Del........................ 3-5 8. Inland Waterway from Delaware River to Chesapeake Bay, Del., and Md .......... 3-5 9. Manasquan River, N.J. .................. 3-6 10. Mispillion River, Del .................... 3-7 11. Navigation Work Under Special Authorization .......................... 3-7 12. New Jersey Intracoastal Waterway ......... 3-7 13. Salem River, N.J........................ 3-8 14. Schuylkill River, Pa...................... 3-9 15. Wilmington Harbor, Del ................. 3-9 Beach Erosion Control 16. Shoreline Erosion Control ......... 17. Beach Erosion Control Work Under Special Authorization ....... Page . . . . . . 3-10 Flood Control Local Protection cont. Page 24. Inspection of Completed Flood Control Projects ....................... 3-13 25. Inspection of Non-Federal Levees ......... 3-13 26. Prompton Lake, Pa . . . . . . . . . . . . . . . . . . . . 3-13 27. Reconnaissance and Conditions Surveys ............................. 3-14 28. National Emergency Preparedness ........ 3-14 General Investigations Page 29. Surveys ............................. 3-14 30. Collection and Study of Basic Data ........ 3-14 31. Advance Engineering & Design ........... 3-14 Tables TABLE 3-A TABLE 3-B TABLE 3-C TABLE 3-D TABLE 3-E TABLE 3-F . 3-10 TABLE 3-G Page Cost and Financial Statement ..... 3-15 Authorizing Legislation .......... 3-18 Other Authorized Navigation Projects ............. 3-21 Other Authorized Beach Erosion Control Projects .......... 3-23 Other Authorized Flood Control Projects ................ 3-23 Multiple Purpose Project Including Power ................ 3-24 Deauthorized Projects ........... 3-24 Flood Control Local Protection Page 18. Beltzville Lake, Pa...................... 3-10 19. Blue Marsh Lake, Pa.................... 3-11 20. Delaware Coast Protection, Del............ 3-11 21. Flood Control Work Under Special Authorization................... 3-12 22. Francis E. Walter Dam, Pa ............... 3-12 23. General Edgar Jadwin Dam and Reservoir, Pa.......................... 3-13 *All costs and financial statemen's for projects are listed at the end of this chapter. All other tables are referenced in text and also appe at the end of this chapter. 3-1 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Navigation 1. BARNEGAT INLET, NJ Location: On the east coast of New Jersey about 50 miles south of Sandy Hook, between Island Beach on the north and Long Beach on the south (See U.S. Coast and Geodetic Chart Nos. 825 and 1216). This inlet is main entrance to Barnegat Bay, largest of the bays on New Jersey coast which are separated from the ocean by narrow barrier beaches. Existing project: Provides for a channel 8 feet deep through inlet and 10 feet through outer bar, channel to be protected by two converging stone jetties extending to 12-foot contour in the ocean and spaced 1,000 feet apart at outer ends; a channel of suitable hydraulic characteristics extending in a northwesterly direction from gorge in inlet to Oyster Creek Channel just northwest of Sunset Shoal, thence via Oyster Creek Channel to deep water in the Bay; and maintenance of a channel 8 feet deep and 200 feet wide to connect Barnegat City harbor with main inlet channel. Total length of section included in project is about 4.5 miles. Plane of reference is mean low water. Extreme tidal range at inlet is from about 2 feet below mean low water to about 3 feet above mean high water. Project was completed in 1940. (For details, see page 203, Annual Report for 1964.) (See Table 3-B at end of chapter for Acts authorizing existing projects.) Recommended modifications: The existing Federal project at the inlet, which was completed in 1940, has failed to maintain a suitable and safe channel for navigation. As a result of the finding of AE&D studies on this matter, the Chief of Engineers decided on 20 January 1983 that modification to the project should be implemented to correct a design deficiency. The recommended modification would serve to correct the design deficiency through the construction of a new south jetty aligned more nearly parallel to the existing north jetty, the dredging and maintenance of a new realigned navigation channel, and the removal of the shoal located between the proposed navigation channel and the north jetty. Local cooperation: Fully complied with. Terminal facilities: There are four docks or terminals in inner harbor at Barnegat Light which furnish adequate facilities for present commerce of locality. Operations during fiscal year: Maintenance, contract: Maintenance dredging at Oyster Creek by Speckard Enterprises from 18 July 1985 to 28 August 1985, removing 38,000 cubic yards at a cost of $147,000. Maintenance, hired labor: Maintenance dredging by U.S. Government Side Casting Dredge FRY was performed from 29 August 1985 to 30 September 1985. Removed an estimated 64,000 cubic yards of material at a cost of $110,000. Work also included subsurface testing, preparation of design deficiency memorandum, general maintenance, engineering surveys on dredging, and supervision and administration. 2. COHANSEY RIVER, NJ Location: Rises in Salem County, N.J., flows southerly and southwesterly 27 miles through Cumberland County, and empties into Delaware Bay about 62 miles below Philadelphia, Pa. (See Coast and Geodetic Survey Chart 1218). Previous projects: For details see page 1785, Annual Report for 1915, and page 348, Annual Report for 1938. Existing project: A channel 12 feet deep, 100 feet wide from that depth in Delaware Bay through a neck of land at the mouth and within the river to the south side of Glass Street in Bridgeton, 19 miles above the mouth; thence a channel 8 feet deep, 100 feet wide to Broad Street; and thence 75 feet wide to Commerce Street Bridge, 19.25 miles above the mouth; and a turning basin 12 feet deep and 800 feet long formed by widening the channel on the south side to a maximum width of 250 feet just below Glass Street. Section included in project is about 19.5 miles long. All depths refer to the plane of mean low water. Extreme tidal range is from about 2 feet below mean low water to about 3 feet above mean high water. Completed project cost $110,756 for new work, exclusive of amounts expended on previous projects. (See Table 3-B at end of chapter for Acts authorizing existing project.) Existing project was completed in 1939. Local cooperation: Complied with except local interests must furnish suitable spoil-disposal areas for required maintenance. Terminal facilities: Twenty wharves, of which 16 are at Bridgeton and 4 at Greenwich. Facilities considered adequate for existing commerce. Operations during fiscal year: Maintenance, contract: Work included Cultural Resource Investigation. Maintenance, hired labor: Work included BCR update, environmental assessment, plans and specifications on maintenance dredging, engineering surveys on dredging, and supervision and administration. 3. DELAWARE RIVER BETWEEN PHILADELPHIA, PA, AND TRENTON, NJ Location: Rises in southeastern New York, flows 3-2 PHILADELPHIA, PA. DISTRICT generally southerly 367 miles, forming boundary line between New York and New Jersey on the east and Pennsylvania and Delaware on the west, and empties into Delaware Bay. (See U.S. Coast and Geodetic Survey Charts 1218, 280, 294, 295, and 296.) Previous projects: For details see page 1778 of Annual Report for 1915, page 311 of Annual Report for 1924, page 220 of Annual Report for 1934, and page 296, Annual Report for 1938. Existing project: A channel from Allegheny Avenue, Philadelphia, 23.5 miles to upstream end of Newbold Island 40 feet deep and 400 feet wide, with suitable widening of bends, including relocation of channel at Delair Railroad bridge, and reconstruction of bridge, thence 5.5 miles to upper end of Trenton Marine Terminal, 35 feet deep and 300 feet wide, with a turning basin 800 feet wide and 1,700 feet long at the terminal; and maintenance of a channel 12 feet deep and 300 feet wide from upper end of 34-foot channel to Penn Central Railroad Bridge at Trenton, dredged under a previous project. Project also provides for an auxiliary channel 20 feet deep and 200 feet wide east of Burlington Island, extending easterly from main channel to upper end of U.S. Pipe and Foundry Co.'s property at East Burlington, with a turning basin 450 feet wide at upper end; for initial excavation, only, of a cross channel 8 feet deep and 200 feet wide through artificial island opposite Delanco, N.J., and for construction such bank protection works as may be necessary. Section included in project is about 30.5 mile long, excluding auxiliary channel east of Burlington Island, which is 1.4 miles long, and cross channel opposite Delanco. Lower end is about 55 miles above river mouth at Liston Point and about 105 miles above Harbor of Refuge at mouth of Delaware Bay. Freshets, which occur usually during February and March, attain a height of 9 to 20 feet above mean low water in vicinity of Trenton. Navigation is occasionally suspended during a portion of winter months due to ice. Existing project is 90 percent complete. A 40-foot channel under the 1954 modification from Allegheny Avenue to upper end of Newbold Island was completed April 1964. Work remaining is dredging from upper end of Newbold Island to Trenton Marine Terminal and widening turning basin at terminal which is in deferred category. (See Table 3-B at end of chapter for Acts authorizing existing project.) (See Table 3-C at end of chapter for total cost for existing project to Sept. 30, 1984.) Local cooperation: Modification authorized by 1954 River and Harbor Act provides local interests must provide suitable terminal facilities, furnish lands and rights-of-way for construction and future maintenance, and hold the United States free from damages. Local interest complied with requirements, except city of Trenton has not provided suitable terminal facilities. Terminal facilities: There are 21 piers, wharves, and docks from Allegheny Avenue, Philadelphia, Pa. to Trenton, N.J. Facilities are considered adequate for existing commerce. (For details see Port Series No. 8 (revised 1966) Corps of Engineers). Operations during fiscal year: Maintenance, contract: Maintenance dredging performed by American Dredging Company during the period of 24 July 1985 through 30 September 1985. Removed a total of 585,000 cubic yards of material at a cost of $3,000,000. Work included environmental monitoring, operation of stream gages in USGS cooperative stream gaging program, maintenance dredging, and aerial survey. Maintenance, hired labor: Work included environmental monitoring, maintenance dredging and surveys, plans and specifications, supervision and administration on maintenance dredging and general engineering and design. 4. DELAWARE RIVER, PA, NJ AND DEL., PHILADELPHIA TO THE SEA Location: See U.S. Coast and Geodetic Survey Charts 1218, 394, 295, and 280. Previous projects: For details see page 1779 of Annual Report for 1915, and page 299, Annual Report for 1938 Existing project: Provides for a channel from deep water in Delaware Bay to a point in the bay, near Ship John Light, 40 feet deep and 1,000 feet wide; thence to Philadelphia Naval Base, 40 feet deep and 800 feet wide, with 1,200-foot width at Bulkhead Bar and 1,000- foot width at other bends; thence to Allegheny Avenue, Philadelphia, Pa., 40 feet deep and 500 feet wide through Horseshoe Bend and 40 feet deep and 400 feet wide through Philadelphia Harbor, along west side of channel; and for anchorages at Reedy Point, Deepwater Point, Marcus Hook, and Mantua Creek, each 40 feet deep and 2,300 feet wide with respective length of 8,000, 5,200, 12,650, and 11,500 feet; anchorage at Gloucester 30 feet deep and about 3,500 feet long. Project also provides for construction of dikes and training works for regulation and control of tidal flow; for maintenance of an area on north side of channel opposite Philadelphia Naval Base between Shipway 3 and Schuylkill River to 40 feet deep and width of 150 feet on Mifflin Range and 200 feet on West Horseshoe Range; and for maintenance of any areas dredged by local interests to 35 feet deep between channel and a line 100 feet channelward of pierhead line between Point House wharf and Philadelphia Naval Base, when in opinion of Chief of Engineers such areas are so located as to be of benefit to generate navigation. Section included in project is about 96.5 miles long. All depths refer to plane of mean low water. Under influence of heavy and long-continued winds extreme tidal range is about 14 feet. Normal maximum velocity of tidal currents in the 3-3 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 dredged channel varies between 2 and 3.5 miles per hour. Storm tides may increase maximum to as much as 4.5 miles per hour. Estimated cost for new work is $71,630,000 (July 1972) exclusive of amounts expended on previous projects. Channel to 37 deep and 500 feet wide through Horseshoe Bend and 37 feet deep and 60 feet wide through Philadelphia Harbor along east side of channel and Port Richmond anchorage to 37 feet deep, except for that portion of channel which forms a part of 40 feet deep and 400 feet wide channel portion is to be restudied and excluded from foregoing cost estimate. Estimated cost (July 1960) of this portion of project is $2,951,000. Existing project, excluding work deferred for restudy, is about 66 percent complete. The 40-foot channel from Naval Base to the sea was completed in 1942. Dredging Naval Base to Allegheny Avenue to 40 feet deep was completed in 1962. Enlarging anchorage at Marcus Hook was completed in 1967. Work remaining is to construct new anchorages at Reedy Point and Deepwater Point, and enlarge Mantua Creek anchorage, channel dredging from 35 to 37 feet deep over a width of 500 feet through Horseshoe Bend and about 600 feet through Philadelphia Harbor, and deepening Port Richmond Anchorage to 37 feet, all of which have been deferred for restudy. (See Table 3-B at end of chapter for Acts authorizing existing project.) (See Table 3-C at end of chapter for total costs for existing project to Sept. 30, 1984.) Local cooperation: Requirements under 1938 River and Harbor Act for maintaining channel and anchorage in Philadelphia Harbor annually by cities of Philadelphia and Camden were removed (see 1962 Annual Report for details). Terminal facilities: There are 217 piers, wharves, and docks between Allegheny Avenue, Philadephia and the sea, 135 on waterfront of Philadelphia, Camden, and Gloucester, and 82 below Philadelphia. Facilities are considered adequate for existing commerce. (For further details see Port Series Nos. 7, revised 1967, and 8, revised 1966-Corps of Engineers.) Operations during fiscal year: Maintenance, contract: Maintenance dredging of Mifflin Range, Mantua Creek Anchorage, and New Castle Range performed by American Dredging Company during period 1 October 1984 through 26 February 1985. Removed a total of 2,654,000 cubic yards of material at a total cost of $6,143,000. Maintenance dredging of Cherry Island, Marcus Hook Anchorage and New Castle Range was performed by American Dredging Company during period of 31 May 1985 through 30 September 1985. Removed a total of 1,860,000 cubic yards of material at a total cost of $9,025,000. Other work included sturgeon studies, lease and maintenance of equipment for disposal areas, construction of dikes and sluices at disposal areas, general maintenance, disposal area groundwater testing, subsurface exploration, bucket dredging study, replaced sluice pipes, maritime practices, air survey, and operation of stream gages by USGS. Maintenance, hired labor: Dredging performed by U.S. Hopper Dredge McFARLAND during the period 1 October 1984 through 27 June 1985. Removed 283,000 cubic yards of material at a cost of $1,286,000. Other work included engineering survey, miscellaneous environmental research coordination, maintenance of disposal area equipment, general maintenance, sturgeon studies, snagging and clearing, debris removal, ditching at disposal areas, groundwater testing, bucket dredging study, environmental assessment, subsurface explorations, handling shore pipe, engineering and design, supervision and administration, plans and specifications on surveys and dredging. 5. HARBOR OF REFUGE, DELAWARE BAY, DEL. Location: At lower end of Delaware Bay, a few miles from Atlantic Ocean on Delaware side of bay. It is about 120 miles south of New York Harbor, about 114 miles north of entrance to Chesapeake Bay and about 101 miles from Philadelphia, Pa. (See Coast and Geodetic Survey Charts Nos. 1218, 1219 and 379.) Previous projects: For details see Annual Reports for 1874, Chart II, page 146; page 330; and 1938, page 330. Existing project: Existing project was completed in 1951. Controlling depth at low water in channel in July 1963 was 16.8 feet. For details see page 229 of Annual Report for 1962. Local cooperation: Fully complied with. Terminal facilities: See page 229 of Annual Report for 1962. Operations during fiscal year: Maintenance, hired labor: BCR update prepared. 6. INDIAN RIVER INLET AND BAY, DEL. Location: Indian River rises in Sussex County, Del., and flows easterly 13 miles into Indian River Bay which is a shallow lagoon 6 miles long and 2 miles wide on the Delaware Coast about midway between Cape Henlopen and the Maryland State line. The inlet is an opening through the barrier beach separating Indian River Bay and the Atlantic Ocean (See U.S. Coast and Geodetic Survey Chart No. 1219.) Previous projects: Adopted by River and Harbor Act of August 2, 1882. For further details see page 744, Annual Report for 1888. Existing project: This provides for the fixation of 3-4 PHILADELPHIA, PA. DISTRICT the inlet by the construction of two parallel jetties of steel-sheet pile and stone design extending to approximately the 14-foot depth curve in the ocean, and for dredging an entrance channel 15 feet deep and 200 feet wide, for a distance of 7,000 feet inshore from the jetties; thence a channel 9 feet deep, 100 feet wide in the bay, and 80 feet wide in the river, to and including a turning basin 9 feet deep, 175 feet wide, and 300 feet long at Old Landing; thence a channel 4 feet deep and 60 feet wide to the highway bridge at Millsboro. The project also provides that the interior channel dimensions may, in the discretion of the Chief of Engineers, be modified as found desirable to increase the hydraulic efficiency of the channel, without increasing the cost. The total length of the section included in the project is about 13.75 miles. All depths refer to the plane of mean low water. The extreme tidal range at the highway bridge is about 6 feet. Existing project was completed in 1951. For details see Annual Report for 1963. The cost for new work for the completed project was $511,210, exclusive of $10,000 expended on previous projects and exclusive of $210,000 contributed funds. (See Table 3-B at end of chapter for Acts authorizing existing project.) Local Cooperation: Fully complied with except that local interest are required to furnish suitable areas for disposal of dredged material during maintenance as and when needed, and provide terminal facilities. Terminal facilities: There is a privately owned basin with berthing facilities for small boats located .75 mile west of the highway bridge near the inlet and .25 mile north of the inlet channel, connected therewith by a channel 6 feet deep and 40 feet wide; a U.S. Coast Guard wharf on the north side of the inlet channel in the same locality; and two wharves at Oak Orchard in Indian River Bay. The facilities are considered adequate for existing commerce. Operations during fiscal year: Maintenance, hired labor: Work included preparing BCR update and project monitoring. 7. INLAND WATERWAY, REHOBOTH BAY TO DELAWARE BAY, DEL. Location: A tidal canal in southeasterly part of Sussex County, Del. It extends 12 miles northward from Rehoboth Bay through high land west of town of Rehoboth to Gordon Lake; thence through marshes back of Cape Henlopen to Lewes River; thence down Lewes River to its junction with Broadkill River near its mouth. An entrance to the waterway from Delaware Bay is about 4 miles above Cape Henlopen. (See U.S. Coast and Geodetic Survey Charts 379,1218, and 1219.) Previous projects: A canal along a slightly different route formed a part of projected waterway from Chincoteague Bay, Va. to Delaware Bay, begun in 1886 and abandoned in 1905. Existing project: This provides for an entrance channel near Lewes 10 feet deep and 200 feet wide protected by two parallel jetties 500 feet apart; thence a channel 10 feet deep and 100 feet wide to South Street Bridge at Lewes, and a basin of the same depth 1,200 feet long and up to 375 feet in width at the latter point; thence a channel 6 feet deep and 50 feet wide (40 feet wide through Deep Cut near Rehoboth Bay) to Rehoboth Bay; a channel 6 feet deep and 100 feet wide from the entrance to Broadkill River; two parallel rubble jetties 725 feet long at the Rehoboth Bay entrance; and the construction of one highway bridge and on railroad bridge at Rehoboth. The total length of the section included in the project is about 12 miles. The cost for new work for the completed portion of the project was $561,514 exclusive of amounts expended on previous projects and $60,000 contributed funds. The extension of the jetties at the Delaware Bay entrance is considered to be inactive and is excluded from the foregoing cost. The cost of the portion was last revised in 1960 and was estimated to be $816,000. Existing project is about 70 percent complete. For details on completed work see page 241 of Annual Report for 1963. Work remaining, extension of existing jetties at Delaware Bay entrance, is considered inactive. (See Table 3-B at end of chapter for Acts authorizing existing project.) Local cooperation: Complied with except local interest must furnish suitable terminal facilities and necessary spoil-disposal areas. Terminal facilities: See page 228, Annual Report 1962. Operations during fiscal year: Maintenance, hired labor: Work included BCR update, engineering and design, and supervision and administration. 8. INLAND WATERWAY FROM DELAWARE RIVER TO CHESAPEAKE BAY, DEL., AND MD. Location: Begins at Reedy Point on Delaware River, about 41 miles below Philadelphia, Pa., and passes through sea level Chesapeake and Delaware Canal, a distance of 14 miles, to Back Creek, at Chesapeake City, Md. It then passes for 5 miles down Back Creek, thence 9 miles down Elk River to Chesapeake Bay and thence 18 miles down Chesapeake Bay to a point near Pooles Island. A branch channel connects Delaware River at Delaware City, Del., with main channel at a point about 1.5 miles west of Reedy Point. (See U.S. Coast and Geodetic Survey Charts 294, 1226, 570, and 572.) 3-5 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Previous projects: For details see Annual Report for 1934, page 242, and Annual Report for 1938, page 312. Existing project: A channel 35 feet deep and 450 feet wide from Delaware River through Elk River and Chesapeake Bay to water of natural 35-foot depth in Chesapeake Bay including a cutoff at Penn Central Railroad crossing, and having a maximum radius of curvature of 7,000 feet at bends; a high-level, fixed railroad bridge with vertical clearance of 135 feet and horizontal clearance of 600 feet at the railroad crossing over the cutoff (economic study of railroad crossing requested by Office of Management and Budget resulted in construction of a single track vertical lift bridge in lieu of a high-level fixed railroad bridge); high-level fixed highway bridges over canal at Reedy Point, St. Georges, Summit, and Chesapeake City; a bascule drawbridge across Delaware City Branch Channel; extension of entrance jetties at Reedy Point; and anchorage in Elk River, 35 feet deep and 1,200 feet wide, with an average length of 3,700 feet; enlargement of anchorage and mooring basin in Back Creek to afford an area about 400 feet wide, 1000 feet long, and 12 feet deep; dredging Delaware City Branch Channel to 8 feet deep and 50 feet wide, and deepening existing basin to same depth; revetment of banks of canal as required between Delaware and Elk Rivers, and on banks of Delaware City Branch Channel east of Fifth Street Bridge; and construction of bulkheads. Total of section included in project, excluding Delaware City Branch Channel, which is about 2 miles long, is about 46 miles. All depths refer to plane of low water in Delaware River. Extreme tidal range is from 6.3 feet above mean high water to 3 feet below mean low water. Existing project is about 89 percent completed. Channel 27 feet deep and 250 to 400 feet wide. Delaware River to Pooles Island, completed in 1938. High-level fixed highway bridges were completed at St. Georges (4-lane) in 1942; at Chesapeake City (2-lane) in 1949; and at Summit (4-lane) in 1960. Relocation of Penn Central Railroad bridge was completed December 21,1965. Enlargement to 35 feet deep and 450 feet wide St. Georges and Summit bridges and Summit and Goose Island was completed on June 20, 1972 and February 18, 1972, respectively. Removing the old Penn Central railroad bridge was completed on January 21, 1972. Channel work for Part II is about 87 percent complete. Work remaining consists of completing channel enlargement to 35 feet deep and 450 feet wide between Reedy Point Bridge and St. Georges Bridge; widening and deepening the channel between Delaware River and Reedy Point Bridge, the completion of recreation facilities, and miscellaneous completion items. Deepening Delaware City Branch Channel from 6 to 8 feet from a point 400 feet east of Fifth Street Bridge to its junction with the canal has been deferred for study. Original cost of canal including purchase was $10,709,755; estimated cost of new work for modifications of 1935 and 1954 is $139,574,000 (October 1977). Total estimated cost of new work including original purchase is $151,683,755. Portion of project comprising completion of Delaware City Branch Channel from a point 400 feet east of Fifth Street Bridge to its junction with canal is to be restudied and excluded from foregoing estimate. Estimated cost of this portion is $145,000 (July 1954). (See Table 3-B at end of chapter for Acts authorizing existing project.) Local cooperation: River and Harbor Act of 1954 provided that local interests furnish lands and rightsof- way required for bridges. Assurances accepted and approved February 16,1955. Requirements for Summit and Reedy Point Bridges have been met. Terminal facilities: Ample mooring facilities at eastern and western ends of canal and bulkheads at Delaware City and St. Georges were constructed by the United States. A small-boat harbor was provided and a wharf constructed at Chesapeake City. Facilities are considered adequate for existing commerce. Operations during fiscal year: Maintenance, contract: Maintenance dredging performed by Norfolk Dredging Company in the Upper Chesapeake Bay during the period 1 October 1984 through 27 November 1984, removing a total of 64,000 cubic yards of material at a cost of $194,000; and during period 19 September 1985 through 30 September 1985 removing 23,000 cubic yards of material at a cost of $440,000. Maintenance dredging was performed by American Dredging Company on the C&D Canal removing a total of 976,000 cubic yards of material at a cost of $3,806,000 during the period 1 October 1984 through 11 April 1985; and during the period 23 September 1985 through 30 September 1985 removing 110,000 cubic yards of material at a cost of $240,000. Other work included maintenance of Chesapeake City, Summit, St. Georges and Reedy Point bridges; general maintenance of disposal areas; maintenance of rip-rap, roadways, night lighting, buildings and grounds, banks, auxiliary works and traffic controlled TV; environmental, dredge and sludge monitoring, drainage of disposal areas, disposal area construction, lease equipment, handling pipe at Courthouse Pt. disposal area, Reedy Pt. bridge overlay, fish and wildlife study, bridge inspection, trash removal, subsurface and testing of disposal areas, and supervision and administration. 9. MANASQUAN RIVER, NJ Location: This small stream flow, in eastern part of New Jersey, rises near Freehold, flows easterly and empties into the Atlantic Ocean, about 26 miles south of Sandy Hook. (See U.S. Coast and Geodetic Survey Chart No. 795.) Previous projects: For details see Annual report for 1909, page 186, and Annual Report for 1938, page 269. Existing project: A channel 14 feet deep and 250 3-6 PHILADELPHIA, PA. DISTRICT feet wide, protected by jetties and other works, extending from the Atlantic Ocean to inner end of north jetty, thence 12 feet deep and 300 feet wide to within 700 feet of New York and Long Branch Railroad bridge, thence of same depth and narrowing to 100 feet wide to within 300 feet of bridge; for a widening on northerly side of channel of 200 feet for 3,150 feet to a depth of 8 feet; for a 19-acre anchorage to 10 feet deep on south side of channel and for a 27.5-acre anchorage to 12 feet deep about 0.5 miles west of Route 35 highway bridge. Section included in project is about 1.5 miles long. Mean tidal range is 3.7 feet at inner end of inlet and 4 feet at ocean end; mean range of spring tides, 4.4 and 4.8 feet, respectively, irregular fluctuations due to wind and barometric pressure vary from 2.7 feet below to 7.5 feet above mean low water at inner end of inlet. Project, excluding 10-and 12-foot anchorages, cost $518,243. Estimated cost (1958) for 10 and 12-foot anchorages portion of project considered inactive is $504,000. Restoration of bulkheads completed 16 August 1965 at a cost of $117,807. Existing project was completed in June 1963. Dredging 19-acre anchorage south of channel and 27.5-acre anchorage west of highway bridge is in the inactive category. (See Table 3-B at end of chapter for Acts authorizing existing project.) Local cooperation: River and Harbor Act of 1945 provides that local interests must furnish lands and rights-of-way for construction and future maintenance and hold the United States free from damages. Assurances to date have been complied with. Terminal facilities: Five landings with a total wharfage of 700 feet used by commercial fishermen, and 7 landings and boat basins for pleasure craft. Existing facilities are considered adequate for present requirements. Operations during fiscal year: Maintenance, contract: Work included CERC and air monitoring, repairs to north Bulkhead, and monitoring jetty. Maintenance, hired labor: Work included engineering and design and supervision and administration. 10. MISPILLION RIVER, DEL. Location: Rises in Kent and Sussex Counties, Del., flows northeasterly 15 miles along the boundary line between the two counties and empties into Delaware Bay about 16 miles above Cape Henlopen. (See Coast and Geodetic Survey Chart 1218). Previous projects: For details see page 1786, Annual Report for 1915, page 448 of Annual Report for 1918, and page 327 of Annual Report for 1938. Existing project: Project is about 31 percent complete. Four cutoffs for 6-foot channel were completed in 1923; 6-foot channel from Delaware Bay to Milford in 1924; and jetties at the mouth in 1939. Work remaining is dredging channel to 9-foot depth, 80 feet wide in Delaware Bay to the mouth, thence 60 feet wide to Milford, with the provision of three cutoffs to eliminate bends, and a turning basin at Milford. Controlling depths at mean low water: In October 1964 from Delaware Bay to mouth 7.1 feet, and thence to fixed highway bridge at Milford, 6.1 feet. For details see page 243 of Annual Report for 1957. Local cooperation: Assurances required by 1954 River and Harbor Act have not been furnished. For details see page 243, Annual Report for 1957. Prior requirements fully complies with. Terminal facilities: For details see page 244, Annual Report for 1957. Operations during fiscal year: Maintenance, contract: Work included rip-rap bank stabilization, supervision and administration on dredging. 11. NAVIGATION WORK UNDER SPECIAL AUTHORIZATION Navigation Activities Pursuant To Section 107, Public Law 86-645 (Preauthorization) Initial Appraisal Name of Project Mispillion River-Conch, Del. Cost to 30 Sep 1985 $ 7,500 Reconnaissance Reports Schuylkill River-Fairmount Park, Pa. Detailed Project Reports Wilmington Harbor, Del. 62,232 69,989 12. NEW JERSEY INTRACOASTAL WATERWAY Location: A sea level inland water route approximately parallel with New Jersey coast, extends from Atlantic Ocean at Manasquan Inlet, about 26 miles south of Sandy Hook, N.J. to Delaware Bay about 3 miles above Cap May point. Waterway extends through inlet and up Manasquan River about 2 miles; thence by Point Pleasant Canal through high ground for 2 miles to head of Barnegat Bay. It then passes through a series of bays, lagoons, and thoroughfares along New Jersey coast to Cape May Harbor; thence across Cape May County to Delaware Bay through a land cut by way of New England Creek basin. (See U.S. Coast and Geodetic Survey Charts, 234, 795, 825, 826, 827, 1216, 1217, 1218, and 1219.) Existing project: This provides for a channel 12 feet deep at mean low water and generally 100 feet 3-7 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 wide, extending from the Atlantic Ocean at Manasquan Inlet, N.J. to Delaware Bay above Cape May, N.J., by the further improvement of Manasquan River and Inlet, N.J., and the present New Jersey Intracoastal Waterway, and by the construction of a canal of similar dimensions from Cape May Harbor to Delaware Bay via the New England Creek basin, with adequate jetties at the Delaware Bay entrance. The total length of the project is about 117 miles. Normal tide range in sections of the waterway remote from inlets is 0.5 foot. Estimated cost for new work is $71,549 (July 1969), exclusive of $1,824,940 Navy Department funds and $99,000 contributed by local interests. Portion of project extending from Manasquan River to Cape May Harbor is to be restudied and excluded from new work costs estimate. Estimated cost of this portion is $6,470,000 (July 1954). Existing project was adopted by 1945 River and Harbor Act (H.Docl33,76th Cong., 1st Sess.) Latest published map is in project document. River and Harbor Act of 1946 (Public Law 525, 79th Cong., 2nd Sess., as extended by Public Law 240,82d Cong.), authorized use for a period not to exceed 6 years, of funds from appropriations heretofore or hereafter made for maintenance and improvement of rivers and harbors, for maintenance of canal from Cape May Harbor to Delaware Bay constructed as an emergency wartime project with Navy Department funds, including cost of maintaining temporary railroad and seashore highway bridges over canal. Existing project is about 25 percent complete. A canal 12 feet deep and 100 feet wide from Cape May Harborto Delaware Bay was completed in 1942; two parallel stone jetties at Delaware Bay entrances and a temporary highway and a railroad bridge in 1944, all with Navy Department funds. Work remaining, dredging a channel 12 feet deep and 100 feet wide from Atlantic Ocean at Manasquan Inlet to Cape May Harbor, has been deferred for restudy; however, the project between Ottens Harbor and Richardson Channel and from that point to Cape May are being maintained to 10 feet and 12 feet, respectively, since they were originally dredged to these depths by the State. Local cooperation: The project is subject to the conditions that the State of New Jersey cede to the United States all right, title, and interest that it has acquired to lands, easements, rights-of-way, and structures other than bridges for the Bayhead- Manasquan Canal; that the State of New Jersey furnish, free of cost to the United States, all lands, easements, rights-of-way, and disposal areas required for construction of the Cape May Canal and for improvement of the proposed waterway and for their subsequent maintenance; that local interests provide, maintain, and operate suitable bridges over the waterway; that the State of New Jersey donate to the United States the navigation aids in use on the present New Jersey Intracoastal Waterway; and that the State of New Jersey hold and save the United States and its agents free from any claims for damages resulting from the work of improvement. Compliance with these conditions was completed January 15,1954, except that local interests are required to furnish disposal areas for the construction and the subsequent maintenance of the proposed improvement. Terminal facilities: See Annual Report for 1962. Operations during fiscal year: Maintenance, contract: Dredging performed by Spickard Enterprises on the Cape May Canal, Great Sound and Shad Islands during the period from 29 August 1985 through 30 September 1985 removing 31,000 cubic yards of material at a cost of $207,000. Other Work included general maintenance, Pt. Pleasant Canal Bulkhead design, erosion report on West End Cape May Canal, and maintenance dredging. Maintenance, hired labor: Work included engineering, plans and specifications, erosion construction, lease plant dredging, engineering and design, and supervision and administration. 13. SALEM RIVER, NJ Location: This river rises in Salem County, N.J., flows through the county westerly 13 miles, thence southerly 7 miles to the City of Salem, and thence westerly 3 miles, emptying into Delaware River about 45 miles below Philadelphia, Pa. It is joined at Salem by Little Salem River, or Fenwick Creek, from the east. (See U.S. Coast and Geodetic Survey Chart No. 294.) Existing project: The River and Harbor Act of July 11, 1870, provided for a survey and the original project was adopted by River and Harbor Act of March 3,1871, and modified in 1878, and a subsequent project adopted by River and Harbor Act of March 2,1907. For further details see page 1784, Annual Report for 1915; page 349 of Annual Report for 1924; and page 346 of Annual Report for 1938. Previous projects: This provides for a channel 12 feet deep at mean low water, 150 feet wide in Delaware River across Salem Cove to the mouth, thence 100 feet wide to the fixed highway bridge in Little Salem River at Salem, 2 1/4 miles above the mouth. It also provides for a cutoff to eliminate a large horseshoe bend between the mouth and Salem. The total length of the section included in the project is about 4 miles. The mean tidal range is 5.4 feet. The extreme tidal range is from about 1 foot below mean low water to about 2 feet above mean high water. The estimate of cost for new work is $51,825 exclusive of amounts expended on previous projects and $51,825 contributed by local interests. The portion of the project comprising the deepening of Little Salem River to 12 feet is to be restudied and is excluded from the foregoing 3-8 PHILADELPHIA, PA. DISTRICT estimate. The estimated cost of this portion revised in 1953 is $28,000 excluding and equal amount to be contributed by local interests. The existing project is about 64 percent complete. The dredging of the channel from Penns Neck Bridge to project dimensions, including the cutoff, was completed in 1928. The channel from Penns Neck Bridge to the fixed highway bridge in Little Salem River was dredged to a depth of 9 feet under a previous project. The work remaining to be done is the deepening of the channel in Little Salem River from 9 feet to 12 feet. The controlling depths at mean low water were as follows: In January 1961, Delaware River to Penns Neck Highway Bridge 12.0 feet; and thence in December 1956 to the fixed highway bridge at Salem, 0.9 feet. The existing project was adopted by the River and Harbor Act of March 3,1925 (H.Doc. 110,68th Cong. 1st Sess.) The latest published map is in the document. Local cooperation: The existing project required local interest contribute 50 percent of the estimated costs of new work and that a right-of-way for the proposed cutoff shall be conveyed to the United States free of cost. The contributions thus far made provided the right-of-way for the cutoff and 50 percent of the cost of the 12-foot channel up to a point 225 feet above the county (Penns Neck) highway bridge, amounting to $51,825. Terminal facilities: There are 9 wharves on the river all at Salem, N.J. Eight wharves are privately owned and one is owned by the City. The facilities are considered adequate for existing commerce. Operations during fiscal year: Maintenance, hired labor: Work included surveys on dredging. 14. SCHUYLKILL RIVER, PA Location: Rises in Schuylkill County, Pa., flows generally southeasterly 150 miles, and empties into Delaware River at Philadelphia, Pa. (See U.S. Coast and Geodetic Survey Charts 295 and 280.) Previous project: For details see page 325, Annual Report for 1932. Existing project: This provides for a channel 33 feet deep and 400 feet wide in Delaware River to the mouth and within the river to 29th Street, .75 mile above the mouth; thence the same depth and 300 feet wide to Passyunk Avenue Bridge, 3.5 miles above the mouth; thence 26 feet deep and 300 feet wide to Gibson Point, 4.5 miles above the mouth; and thence 22 feet deep and 200 feet wide to University Avenue Bridge, 6 miles above the mouth, including widening at bends. The total length of the section included in the project is about 6.5 miles. All depths refer to the plane of mean low water. The extreme tidal range, due to freshets and prolonged heavy winds, is about 14 feet. The cost for new work for the completed existing project was $2,809,007. Existing project was completed in September 1962. For details see Annual Report for 1962. (See Table 3-B at end of chapter for acts authorizing existing project.) Local cooperation: The River and Harbor Act of July 24, 1946, imposed the condition that the City of Philadelphia agree to remove 60,000 cubic yards, place measurement, of material annually from that portion of those portions of the project which the District Engineer may designate until such time as adequate municipal sewage-treatment works are constructed and placed in effective operation. Compliance with this condition has been met through the completion of sewage-treatment works by the City of Philadelphia. All other requirements have been fully complied with. Terminal facilities: There are 38 wharves, piers, and docks within limits of improvement. Facilities are considered adequate for existing commerce. (For further details see Port Series No. 7, Revised 1967, Corps of Engineers.) Operations during fiscal year: Maintenance, contract: Dredging by the American Dredging Company was performed from 8 July 1985 through 10 September 1985 removing 224,000 cubic yards of material at a cost of $1,531,000. Other work included general maintenance, plans and specifications, and supervision and administration. Maintenance, hired labor: Work included environmental monitoring, bucket dredge study, plans and specifications, dredging surveys, and supervision and administration. 15. WILMINGTON HARBOR, DEL. Location: Formed by Christina River, which rises in New Castle County, Del., flows northeasterly 16 miles, passing through the city of Wilmington, Del., and empties into Delaware River about 29 miles below Philadelphia, Pa. (See U.S. Coast and Geodetic Survey Chart 294.) Previous projects: For details see page 1785 of Annual Report for 1915 and page 308 of Annual Report for 1938. Existing project: This provides for a channel 35 feet deep and 400 feet wide from west edge of Delaware River ship channel to Lobdell Canal, a distance of about 1.2 miles; thence 21 feet deep and 250 feet wide for 3-9 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 the distance of .8 mile to the mouth of Brandywine River; thence the same depth and 200 feet wide for a distance of about 2.2 miles to a point approximately 4.2 miles from the Delaware River ship channel; thence decreasing a depth of 10 feet in a distance of 750 feet to Penn Central Railroad bridge No. 4; and thence 7 feet and 100 feet wide for a distance of about 5.6 miles to Newport, Del., approximately 9.9 miles above Delaware River ship channel, including a turning basin 35 feet deep opposite the Wilmington Marine terminal and extending upstream from the mouth to Lobdell Canal, 200 feet wide, 2,900 feet long on the north side of the channel and decreasing to a length of 2,000 feet on the north side of the basin. It also provides for the removal of about 1,200 feet of the outer end of a stone-filled, pile-and-timber crib jetty constructed 2,150 feet long on the north side of the entrance; for a steel sheet-pile jetty 2,300 feet long, with 120-foot inshore wing, on the south side of the entrance, and for a V-shaped stone-filled pile-and-timber jetty at the mouth of Brandywine River 430 feet along the north side of Brandywine and 260 feet long on the Christina. Depths refer to the plane of mean low water. The extreme tidal range, due to prolonged heavy winds, is about 13 feet. Existing project was completed in 1962. (For details see page 222, Annual Report 1962.) (See Table 3-B at end of Chapter for Acts authorizing existing project.) Local cooperation: Fully complied with. Terminal facilities: There are 18 piers, wharves, and docks within improvement. Facilities considered adequate for existing commerce. (For further details see Port Series No. 8, revised 1966-Corps of Engineers.) Operations during fiscal year: Maintenance, contract: Maintenance dredging in the Christina River was performed by the American Dredging Co. during the period 12 November 1984 through 23 November 1984. Removed 68,000 cubic yards of material at a cost of $414,000; during the period 14 June 1985 through 28 June 1985 removing 381,000 cubic yards of material at a cost of $556,000. Maintenance dredging performed by Norfolk Dredging Company from 13 December 1984 through 15 June 1985 removing a total of 524,700 cubic yards at a total cost of $461,000. Other work included cultural resource survey phase II, subsurface testing, general maintenance, artificial reef study, environmental monitoring, construction of dike sluices, environmental and design survey, cultural research, fish and wildlife, miscellaneous real estate action, ditching at Wilmington Harbor south, and Edgemore disposal area, lease of equipment, cross section bank and access, survey maintenance dredging. Maintenance, hired labor: Work included biological surveys, preparation of environmental impact statement, environmental monitoring, general maintenance at Wilmington Harbor South and Edgemoor disposal areas, plans and specifications for dredging, survey on maintenance dredging of the Christina River, ditching, supervision and administration, general maintenance, cultural research, engineering and design, dredging and completion of GDM. Beach Erosion Control: 16. SHORELINE EROSION CONTROL DEMONSTRATION Location: Demonstration projects were undertaken at a total of 16 sites nationwide, 6 of which are located in the Delaware Bay and include Pickering Beach, Kitts Hummock, Slaughter Bowers Beach, Broadkill Beach, and Lewes, Delaware. The latter three sites were only monitored as there are presently Federal and State projects in progress. . Existing project: Section 54 of Water Resources Development Act of 1974 authorized a nationwide, 5 year program to test and evaluate low cost shoreline erosion control measure, both structural and vegetative, which can be implemented by individual private property owners. The emphasis of the program was not to solve individual problems, so much as to explore the effectiveness of various ways to control erosion at different types of shorelines, and provide this information to private and public landowners. The construction and evaluation at all sites are completed and information dissemination has been started. Operations during fiscal year: Maintenance, hired labor: Only costs incurred were in support of information dissemination program. Cost during this period was $3,369.70. 17. BEACH EROSION CONTROL WORK UNDER SPECIAL AUTHORIZATION Beach erosion control activities pursuant to Section 103, Public Law 87-874 (Preauthorization). Name of project Cost to 30 Sep 1985 Detailed Project Reports North Shore-Indian River Inlet South Shore-Indian River Inlet $35,000.00 35,000.00 Flood Control 18. BELTZVILLE LAKE, PA Location: Damsite is on Pohopoco Creek about 4.5 miles upstream from its confluence with Lehigh River and 4 miles east of Lehighton, Pa. (See Geological Survey Quadrangle Map for Lehighton, Pa.-1960.) Existing project: A multiple-purpose development 3-10 PHILADELPHIA, PA. DISTRICT project providing water supply, flood control, and recreation. Plan of improvement provides for an earth and rock fill dam 4,200 feet long rising 170 feet above creekbed; a spillway around north end of dam; and gate control outlet works discharging through a conduit on rock along right abutment. The lake, a unit of comprehensive plan for flood control and other purposes of Delaware River Basin, has a reservoir capacity of 68,250 acre-feet at spillway crest level with 1,390 acre-feet of inactive storage, 39,830 acre-feet for water supply and recreation, and 27,030 acre-feet for flood control. The cost of project was $22,931,400 including $6,100,000 required non-Federal reimbursement for costs allocated to water supply storage during life of project. The construction of the dam and appurtenances was completed in 1971. Local cooperation: Project was approved subject to certain requirements of cooperation by local interests as defined in approved House Document. Resolution of Delaware River Basin Commission providing assurances of repayment of water supply and pollution control costs was accepted June 7, 1965. A contract for repayment of water supply costs was signed October 16, 1966. Operations during fiscal year: Maintenance, contract: Work included reservior operation and maintenance, operation of stream gages in cooperative stream gaging program, snow surveys, correcting electric problems, water quality data collection and monitoring, replacing 16-inch water line valve, finalizing O&M manual, sedimentation survey, and repairing outlet Channel side slope. Maintenance, hired labor: Work included reservoir operation and minor maintenance, annual safety inspection, water quality monitoring, instrumentation survey, snow survey, operation of stream gages in cooperative stream gaging program, finalizing O&M manual, sedimentation survey, inndation mapping, dam safety training, monitoring tower leakage, dam survey, electrical repairs, engineering and design, and supervision and administration. 19. BLUE MARSH LAKE, PA Location: Dam site is on Tulpehocken Creek about 1.5 miles upstream from its confluence with Plum Creek and about 6 miles northwest of Reading, Pa. (See Geological Survey Quadrangle Sheet, Bernville, Pa.) Existing project: This is a multiple-purpose development project providing water supply, flood control, and recreation. Construction started in 1974 and was completed in 1980. The dam is 1,775 feet long and rises 98 feet above creekbed, with at spillway about 1,500 feet south of dam, and gate-controlled outlet works discharging through a conduit on rock along right abutment. The lake, a unit of comprehensive plan for flood control and other purposes of Delaware River Basin, has a capacity of 50,010 acre-feet at spillway crest level, with 3,000 acre-feet of inactive storage, 14,620 acre-feet for water supply and recreation, and 32,390 acre-feet for flood control. (For details see H.Doc 533 87th Cong., 2nd Sess.) Cost of project (October 1984), $63,163,791 includes $16,132,000 required non-Federal reimbursement for costs allocated to water supply storage during life of project after use of this storage is initiated. Existing project was authorized by 1962 Flood Control Act (H. Doc. 533, 87th Cong., 2d Sess., contains latest published maps.) Local cooperation: Project was approved subject to certain requirements by local interests, as prescribed in House Document cited above. Delaware River Basin Commission on December 29, 1964, adopted a preliminary resolution providing for repayment of water supply costs. Operations during fiscal year: Maintenance, contract: Work included reservoir operation and maintenance, drilling well at recreation area, operation and maintenance of recreation area, snow survey, operation of stream gages in cooperative stream gaging program, water quality testing and monitoring, mowing and fertilizing recreation area, janitorial services, trash removal, dam break analysis, maintenance of sewage treatment plant, lawn maintenance, dam survey, and cost incurred for Bern and Heidelberg Township police. Maintenance, hired labor: Work included reservoir operation and maintenance, annual safety inspection, water quality monitoring, instrumentation survey, snow survey, operation of stream gages in cooperative stream gaging program, finalization of O&M manual, sedimentation survey, plans and specifications to correct shoreline erosion, dam break analysis, seasonal employment, dam safety training, emergency planning, repair to pressure condition, dam survey, plans and specifications to reproduce Courtesy Book, improvements to gate house, and engineering and design and supervision and administration. 20. DELAWARE COAST PROTECTION, DEL. Location: The project is located in Sussex County, Delaware, on the Atlantic Ocean and starts immediately south of Delaware Bay extending in a southerly direction a distance of 24.5 miles to Fenwick Island on the Delaware-Maryland border. Existing project: Provides a plan of improvement which consists of the construction of dunes and beach fill; the construction of bulkheads at Rehoboth and Dewey beaches; periodic nourishment of the beaches; placement of sand fences; planting dune grass and maintenance and replacement of existing structures. (For details, see S. Doc. 90, 90th Cong. 2d Sess.) 3-11 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Estimated cost of project (October 1985) $14,300,000 includes $2,700,000 required non-Federal costs. The construction of the feeder beach north of Indian River Inlet was completed in 1973 and nourished in 1978, and 1984. Other work undertaken has been engineering and design associated with the rest of the project. Local cooperation: Assurances of local cooperation were provided by the State of Delaware, January 13, 1981. Operations during fiscal year: New Work, contract: Work included construction of Feeder Beach, aerial topography, study management, fish and wildlife study, and advance engineering and design. New Work, hired labor- Work included environmental studies, hydrology and hydrographic studies, study management, construction of feeder beach, design and cost estimates, engineering and supervision and administration. 21. FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION Flood control activities pursuant to Section 205, Public Law 838, 80th Congress, as amended (Preauthorization). Name of Project Cost to 30 Sept. 1985 Reconnaissance Reports Huntingdon Valley, Pa. $7,500 Sacony Creek-Berks Co, Pa. 7,500 Detailed Project Reports Poquessing Creek, Bucks County, Pa. 27,216 Plans and Specifications Delaware River, Port Jervis, NY 281,078 Construction Wallkill River (Black Dirt Area), N.J. 3,100 Also feasibility study pursuant to Emergency Bank Protection Authority provided by Section 14 of the 1946 Flood Control Act. Name of Project Construction Equinunk Creek, Wayne County, Pa. Cost to 30 Sept 1985 $191,000 Emergency flood control activities-repair, flood fighting, and rescue work (Public Law 99, 84th Congress, and antecedent legislation). Fiscal year costs were $202,850 for disaster preparedness, and $51,278 for emergency operations. 22. FRANCIS E. WALTER DAM, PA Location: Reservoir is in northeastern Pennsylvania on Lehigh River between White Haven and Stoddartsville. Dam is about 0.4 mile below mouth of Bear Creek, about 60 miles above confluence of Lehigh River and Delaware River at Easton, Pa. (See Geological Survey Quadrangle Sheet, Stoddartsville, Pa.) Existing project: Plan of improvement authorized by 1946 Flood Control Act (H. Doc 587, 79th Cong., 2d Sess.) provided for a single-purpose flood control reservoir. Modification of project, authorized by 1962 Flood Control Act (H. Doc. 522, 87th Cong., 2d Sess.), provides for a multiple-purpose development for water supply and recreation in addition to present singlepurpose flood control project. Plan of improvement requires altering spillway increasing height of dam, extending outlet tunnel by addition of a concrete conduit, and constructing new dikes and raising existing dikes. Modified dam will rise 263 feet above riverbed and be 3,500 feet long. Reservoir modification, a unit of comprehensive plan for flood control and other purposes of Delaware River Basin, will have a reservoir capacity of 180,000 acre-feet spillway crest level with 2,000 acre-feet of inactive storage, 70,000 acre-feet for water supply and recreation and 108,000 acre-feet for flood control. Estimated Federal cost of new work (October 1985) is $127,000,000 including $110,700,000 required non-Federal reimbursement for costs allocated to water supply storage during life of project after use of this storage is initiated. Project as authorized under the 1946 Flood Control Act was completed June 1961. Settlement for lands was completed October 1962. The advance engineering and design for the modified project is now underway. Local cooperation: None required under 1946 Flood Control Act. Under 1962 Flood Control Act, project was approved subject to certain requirements by local interests, as defined in House Document 522 cited above. The Delaware River Basin Commission reiterated its sponsorship for the modified project in August 1982. Operations during fiscal year: Maintenance, contract: Work included operation and minor maintenance of reservoirs, fire protection, snow survey, operation of stream gages in cooperative stream gaging program, repair of stream gages, water quality testing, instrumentation survey and general maintenance of equipment. Maintenance, hired labor: Work included reservoir operation and minor maintenance, instrumentation surveillance, minor maintenance of recreation facilities, period inspections, operation of stream gages in USGS cooperative stream gaging program, annual safety inspection, general engineering and design, and supervision and administration. 3-12 PHILADELPHIA, PA. DISTRICT 23. GENERAL EDGAR JADWIN DAM AND RESERVOIR, PA Location: In Dyberry Creek valley in central part of Wayne County, Pa., between borough of Honesdale and village of Tanners Falls. Dam is about 3 miles above confluence of Dyberry Creek and Lackawaxen River in Honesdale and 29 miles above confluence of Lackawaxen and Delaware Rivers. (See Geological Survey Quadrangle Sheet, Honesdale, Pa.) Existing project: A single-purpose flood control reservoir with a capacity of 24,500 acre-feet formed by an earth embankment, about 1,225 feet long at crest and rising 109 feet above creek bed. It also has a tunnel with intake structure and a chute-type spillway with a stilling basin in left abutment. Reservoir controls runoff from a drainage area of 65 square miles which is 91 percent of watershed of Dyberry Creek and 39 percent of Lackawaxen River watershed above Honesdale, Pa. Construction of project was authorized by 1948 Flood Control Act (H. Doc. 113, 80th Cong., 1st Sess.). Federal cost of new work was $4,064,510. Non-Federal funds not required. Project completed in June 1960. Local cooperation: Assurances of Compliance with requirements of local cooperation were accepted July 30, 1956. For details see page 251, Annual Report for 1962. Operations during fiscal year: Maintenance, contract: Work included reservoir operation and maintenance, operation of stream gages in USGS cooperative stream gaging program, and dam survey. Maintenance, hired labor: Work included inundation mapping, reservoir operation and minor maintenance, safety and engineering inspections, operation of stream gages in cooperative stream gaging program, instrumentation and surveillance analysis, general engineering and design, construct trash boom, dam break analysis, dam surveys, and supervision and administration. 24. INSPECTION OF COMPLETED FLOOD CONTROL PROJECTS To ascertain whetherlocal interests were maintaining and operating completed projects as required, inspections were made as follows: PROJECT INSPECTION DATES Lehigh River at Allentown, Pa. Lehigh River at Bethlehem, Pa. Delaware River at East Branch, N.Y. 10 October 1984 1 May 1985 14 November 1984 24 April 1985 7 November 1984 15 May 1985 Rancocas Creek at Mount Holly, N.J. Chester River at Chester, Pa. 30 October 1984 22 April 1985 1 November 1984 15 April 1985 Local interests are satisfactorily maintaining and operating projects in accordance with regulation. Costs during the period were $12,303. Total costs were $104,882. 25. INSPECTION OF NON-FEDERAL LEVEES Inspection of non-Federal levees were conducted at a cost of $1,031 at the following sites: Port Jervis, NY 12 Feb. 1985 26. PROMPTON LAKE, PA. Location: In Lackawaxen River Valley in central part of Wayne County, Pa., between borough of Prompton and village of Aldenville. Dam is within corporate limits of Prompton, 4 miles upstream from Honesdale, Pa., and approximately 30 miles above confluence of Lackawaxen and Delaware River. (See Geological Survey Quadrangle Sheet, Honesdale, Pa.) Existing project: Plan of improvement authorized by 1948 Flood Control Act (H. Doc. 113, 80th Cong., 1st Sess.) provides for a single-purpose flood control reservoir. Modification of project authorized by 1962 Flood Control Act (H. Doc. 522, 87th Cong., 2d Sess.) provides for a multiple-purpose development for water supply and recreation in addition to present singlepurpose flood control project. Plan of improvement requires construction of control tower with gates and service bridge, placing an impervious blanket on valley walls and floor upstream from dam, widening spillway, and clearing land and relocating roads in reservoir. Dam, completed under 1948 Flood Control act which will not be modified, is 1,230 feet long and rises 140 feet above riverbed. Existing spillway, cut into rock of right abutment, will be modified and present uncontrolled outlet works discharging into a concrete conduit along right bank, will be provided with gates and a control tower. Reservoir modification, a unit of comprehensive plan for flood control and other purposes of Delaware River basin has a capacity of 52,000 acre-feet; 3,500 acre-feet for inactive storage, 28,200 acre-feet for water supply and recreation, and 20,300 acre-feet for flood control. Estimated Federal cost of new work (October 1985) is $43,300,000 including $38,100,000 required non-Federal reimbursement for costs allocated to water supply storage during life of project after use of this storage is initiated. Project as authorized under the 1948 Flood Control Act was completed in November 1960. (For details, see page 358, Annual Report for 1963.) Work accomplished under the 1962 Flood Control Act was advance engineering and design. 3-13 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Local cooperation: Project modification was approved subject to certain requirements by local interests, as defined in House Document 522 cited above. Assurances of compliance under Flood Control Act of 1948 have been met. Delaware River Basin Commission on March 18, 1966, gave their view that the need for water supply was not urgent at that time. However recent studies conducted by DRBC have determined that there is now a need for water supply. In August 1983, DRBC expressed their strong support for the project modification. Therefore resumption of planning will take place when funds are made available. Operations during fiscal year: Maintenance, contract: Work included operation and minor maintenance, water quality monitoring, USGS cooperative stream gaging, survey analysis, dam survey, supervision and administration, and engineering and design. Maintenance, hired labor: Work included inundation mapping, dam break analysis, annual safety inspection, dam safety training, water quality data collection, instrumentation and surveillance, dam survey, repair of instrumentation and engineering and design. 27. RECONNAISSANCE AND CONDITION SURVEYS Project Salem River Date Survey Conducted 31 October 1985 Burlington Island Back Channel Salem River Cohansey River Delaware City Br Channel 14-15 January 1985 2 February 1985 21 March to 2 May 1985 19 April 1985 28. NATIONAL EMERGENCY PREPAREDNESS The total fiscal year cost for this category amounted to $131,096. GENERAL INVESTIGATIONS 29. SURVEYS Cost for the period were $618,632 for navigation studies: $298,617 for flood control studies: $115,390 for special studies: a total of $1,082,639. 30. COLLECTION AND STUDY OF BASIC DATA Cost and expenditures during the period for flood plain information studies were $172,018. 31. ADVANCE ENGINEERING AND DESIGN The total costs for this category amount to $2,099. 3-14 PHILADELPHIA, PA. DISTRICT TABLE 3-A COST AND FINANCIAL STATEMENT See Section in Text Projects Funding FY82 FY83 FY84 FY85 Sept. 30, 1985 1. Barnegat Inlet, N.J. (Regular Funds) (Contributed Funds) 2. Cohansey River, N.J. (Regular Funds) 3. Delaware River Between Philadelphia, Pa. and Trenton, N.J. (Regular Funds) (Contributed Funds) 4. Delaware River Pa., N.J. and Del., Philadelphia to the Sea (Regular Funds)* 5. Harbor of Refuge Delaware Bay, Del. (Regular Funds) 6. Indian River Inlet and Bay, Del. (Regular Funds) (Contributed Funds) 7. Inland Waterway Rehoboth Bay to Delaware Bay, Del. (Regular Funds) (Contributed Funds) 8. Inland Waterway from Delaware River to Chesapeake Bay, Del. and Md. (Regular Funds) New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost New Work Approp. Cost Maint. Approp. Cost Rehab. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost Rehab. Approp. Cost New Work Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost New Work Approp. Cost Maint. Approp. Cost 362,500 365,491 3,158,000 3,167,472 13,794,188 13,743,314 -1,091 703,000 680,607 30,000 11,049 967,000 968,187 210,000 206,975 670,000 694,337 -3,000 15,951 289,000 286,860 66,000 65,367 298,125 3,328,000 298,476 3,321,857 16,782,000 21,533,300 25,051,285 16,775,510 21,639,776 25,051,285 9,000 8,706 - -16,000 634 697 11,000 11,175 114,000 112,228 4,000 4,171 30,000 32,572 - - 297 7,078,400 12,045,500 10,488,275 6,836,659 12,225,774 10,667,119 267 22,000 20,617 19,000 16,346 12,068,000 11,940,091 3-15 658,849 655,824 10,010,135 10,007,853 300,000 300,000 146,75623 146,75623 838,931 838,298 72,147,8001 72,147,8001 26,508,8602 26,508,8572 15,000 15,000 57,879,872' 57,879,872 284,583,8674 284,565,0484 508,324 508,324 5,162,2306 5,162,2306 1,147,3637 1,147,0697 511,2105 511,210' 2,763,923 2,762,540 1,323,775 1,323,775 210,000 210,000 561,514 561,514 1,323,978 1,321,324 60,000 60,000 132,535,5916 132,532,598 148,435,705" 148,233,310 ' REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 3-A (continued) COST AND FINANCIAL STATEMENT See Section in Text Projects Funding FY82 FY83 FY84 FY85 Sept. 30, 1985 9. Manasquan New Work River, N.J. Approp. - - - - 577,24916 (Regular Cost - - - - 577,24910 Funds) Maint. * Approp. 100,000 15,000 25,000 273,000 3,394,55717 Cost 4,612 94,659 40,081 264,024 3,384,93317 Rehab. Approp. - - - - 7,410,60020 Cost 1,378,056 177,314 1,028 - 7,343,85820 (Contributed New Work Funds) Approp. - - - - 300,000 Cost - - - - 300,000 10. Mispillion New Work River, Del. Approp. - - - - 377,84818 (Regular Cost - - - - 377,84818 Funds) Maint. Approp. -4,020 - 11,000 111,000 1,364,12719* Cost 1,400 - 11,000 110,600 1,368,72719* Rehab. Approp. - - - - 253,491 Cost - - - - 253,491 11. New Jersey New Work Intracoastal Approp. - - - - 71,54910 Waterway Cost - - - - 71,54910 (Regular Maint. Funds) Approp. 1,446,100 818,000 1,121,000 979,000 19,582,571 " Cost 1,554,708 849,876 1,152,487 981,788 19,582,34211 Rehab. Approp. - - - - 1,196,581 Cost - - - - 1,196,581 (Contributed New Work Funds) Approp. - - - - 99,000 Cost - - - - 99,000 12. Salem, River, N.J. New Work (Regular Approp. - - - - 107,6342' Funds) Cost - - - - 107,63421 Maint. Approp. - 35,000 992,000 45,225 1,317,77922 Cost - 21,181 1,005,818 45,011 1,317,77822 (Contributed New Work Funds) Approp. - - - - 51,825 Cost - - - - 51,825 13. Schuylkill New Work River, Pa. Approp. - - - - 3,334,00712 (Regular Cost - - - - 3,334,007'2 Funds) Maint. Approp. 108,000 770,100 1,241,000 1,693,000 25,942,03325 Cost 104,454 768,856 1,244,884 1,641,466 25,941,38621 14. Wilmington New Work Harbor, Del. Approp. - - - - 1,954,725' (Regular Cost - - - - 1,954,725':1 Funds) Maint. Approp. 1,524,100 2,011,000 2,006,000 3,226,600 30,797,765 Cost 1,501,336 1,980,620 2,069,777 3,215,739 30,779,558 (Contributed New Work Funds) Approp. - - - - 60,000 Cost - - - 60,000 15. Beltzville Lake, New Work Pa. Approp. - - - - 22,931,831 (Regular Cost - - - - 22,931,130 Funds) Maint. Approp. 342,400 721,000 655,800 521,000 4,803,175 Cost 364,321 691,749 713,170 521,407 4,801,389 3-16 PHILADELPHIA, PA. DISTRICT TABLE 3-A (continued) COST AND FINANCIAL STATEMENT See Section in Text Projects Funding FY82 FY83 FY84 FY85 Sept. 30, 1985 16. Blue Marsh New Work Lake, Pa. Approp. - - - - 63,180,300 (Regular Cost -93,855 118,186 3,212 - 63,163,790 Funds) Maint. Approp. 794,200 787,000 1,002,200 1,186,000 5,509,200 Cost 836,190 742,145 1,068,725 1,167,543 5,464,539 17. Delaware Coast New Work Protection Approp. - 50,000 775,000 200,000 2,453,95324 (Regular Funds) Cost - 43,580 455,165 200,000 2,127,64924 (Contributed New Work Funds) Approp. - 85,000 -921 - 84,079 Cost - 69,557 11,538 - 81,095 18. Francis E. New Work Walter Dam, Pa. Approp. - - - - 11,503,432'4 (Regular Cost 91,375 512 - - 11,501,97114 Funds) Maint. Approp. 423,300 331,000 383,700 422,000 4,533,521 Cost 446,749 330,420 388,882 421,975 4,522,653 19. General Edgar New Work Jadwin Dam and Approp. - - - - 4,073,105 Resevoir, Pa. Cost - - - - 4,073,105 (Regular Maint. Funds) Approp. 38,000 104,000 74,200 243,000 1,390,564 Cost 40,266 91,463 88,156 242,742 1,390,236 20. Prompton Lake New Work Pa, Approp. - - - - 4,609,48315 (Regular Cost - - - - 4,609,48315 Funds)* Maint. Approp. 149,300 167,000 298,000 353,000 2,413,162 Cost 147,927 173,611 306,608 348,359 2,401,883 *Total Adjustment to correct discrepancies in prior years. 1. Includes $2,489,173 for new work for previous projects, $105,000 for preauthorization studies and minus $142,015 adjustment (new work) to Delaware River, Philadelphia to Sea project from this project under 1954 modification. 2. Included $552,720 for maintenance for previous projects, and $685,000 Jobs Bill Funds. 3. Excludes $12,976,054 for new work for previous projects and $142,015 adjustment from Delaware River, Philadelphia to Trenton, N.J. under 1954 modification. 4. Includes $1,025,409 for maintenance of previous projects, and $8,000 Jobs Bill funds. 5. Excludes $10,000 for previous project. 6. Includes $2,749,452 for new work for previous projects. 7. Excludes $1,089 for reconnaissance and condition surveys, fiscal year 1963. 8. Includes $10,709,755 for new work for previous projects. 9. Includes $6,903,748 for maintenance for previous projects, and $9,500 Jobs Bill funds. 10. Excludes $1,824,940 Navy Department Funds. 11. Excludes $286,953 Navy Department funds expended for maintenance. 12. 13. 14. 15. 16. 17. 18. 19. 20. 21. 22. 23. 24. 25. Includes $525,000 for previous projects. Includes $402,121 for new work for previous project, and $206,177 emergency relief funds. Includes $40,000 appropriated and expended under Code 710 Recreation Facilities. Includes $63,000 appropriated and $61,551 expended under Code 710 Recreation Facilities, excludes $23,600 preauthorization studies under 1948 modification. Includes $39,000 for new work for previous projects. Includes $2,054 for maintenance for previous projects. Includes $148,798 for new work on previous projects. Includes $61,172 for maintenance on previous projects. Includes $555,600 for previous project. Includes $55,809 new work funds expended on previous project. Includes $1,285 for reconnaissance a offndition survey in fiscal year 1957, $1,792 operation and maintenance cost incurred for preparation of environmental impact statement, and $48,000 expended for maintenance on previous project. Includes $36,000 for new work for previous projects. Includes $438,953 AE&D. Includes $50,000 Jobs Bill Funds. 3-17 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 3-B AUTHORIZING LEGISLATION Acts Work Authorized Documents Aug. 30, 1935 Aug. 26, 1937 July 24, 1946 BARNEGAT INLET, N.J. (See Section 2 of Text) An 8-foot depth through inlet to Oyster Creek Channel across inner bar, 10-foot depth through outer bar and for jetties. A channel of suitable hydraulic characteristics from gorge to Oyster Creek Channel, and thence to deep water in bay. Maintenance dredging of channel to connect main inlet channel with Barnegat City Harbor. COHANSEY RIVER, N.J. (See Section 3 of Text) Mar. 2, 1907 Channel 7 feet deep over entire project. Aug. 26, 1937 Channel 12 feet deep to Glass Street, thence 8 feet to Commerce Street with turning basis. DELAWARE RIVER BETWEEN PHILADELPHIA, PA. AND TRENTON, N.J. (See Section 5 of Text) July 3, 1930 A channel 28 feet deep, 300 feet wide between Alleghney Ave., Philadelphia, PA and Delair Bridge. Aug. 30, 19352 Aug. 30, 19352 Aug. 26, 1937 July 24, 1946 Channel 25 feet deep from Delair Bridge to Trenton, N.J., and maintenance of 12- foot channel from upper end of 25-foot project to Penn Central R.R. Bridge at Ferry St., Trenton. Auxiliary channel, 20 feet deep east of Burlington Island. A cross channel 8 feet deep, opposite Delanco, N.J. Anchorage at mouth of Biles Creek Sept. 3, 1954 A channel 40 feet deep and 400 feet wide between Alleghney Ave., Philadelphia, PA., and upstream end of Newbold Island, thence 35 feet deep to Trenton Marine Terminal and turning basin to 800 feet wide. Relocate channel at railroad bridge at Delair and suitably reconstruct bridge. Construct necessary bank protection works; and eliminate authorized anchorage near mouth of Biles Creek, PA. DELAWARE RIVER, PA., N.J., AND DE, PHILADELPHIA TO THE SEA (See Section 6 of Text) June 25, 1910 Channel 35 feet deep from Allegheny Ave., Philadelphia, PA to Delaware Bay. July 3, 1930 Anchorages 35 feet deep at Port Richmond and Mantua Creek, a 30 foot anchorage at Gloucester, N.J. and extend 1,000 foot channel in Philadelphia Harbor to Horseshoe Bend. Aug. 30, 19353 June 20, 19384 Mar. 2, 19455 Mar. 2, 19455 Mar. 2, 19455 An anchorage 35 feet deep at Marcus Hook, PA. A channel 37 feet deep from Philadelphia - Camden Bridge to Navy Yard, thence 40 feet deep to deep water in Delaware Bay. A 37-foot depth channel from Allegheny Ave., Philadelphia, PA. to Philadelphia- Camden Bridge and A 37-foot depth in an enlargement of anchorage near Mantua Creek and Marcus Hook. Maintain enlarged channel opposite Philadelphia Navy Yard. Sept. 3, 1954 A channel from Allegheny Ave., to Naval Base 40 feet deep, 400 feet wide along side of channel through Philadelphia Harbor and 500 feet wide through Horseshoe Bend. July 3, 1958 Anchorages at Reedy Point, Deepwater Point, Marcus Hook, and Mantua Creek 40 feet deep and 2,300 feet wide with mean lengths of 8,000, 5,200, 13,650 and 11,500 feet respectively. Rivers and Harbors Committee Doc. 19, 73d Con., 2d sess.' Rivers and Harbors Committee Doc. 85, 74th Cong., 2d sess.1 H. Doc. 358, 79th Cong. 2d sess. H. Doc. 645, 59th Cong. 1st sess. Senate Committee print, 75th Cong., 1st sess. Rivers and Harbors Committee Doc. 3, 71st Cong., 1st sess. Rivers and Harbors Committee Doc.11, 73d Cong., 1st sess. Rivers and Harbors Committee Doc. 66, 74th Cong., 1st sess.' Rivers and Harbors Committee Doc. 90, 74th Cong., 2d sess. H. Doc. 679, 79th Cong., 2d sess. H. Doc. 358, 83rd Cong., 2d sess.' H. Doc. 733, 61st Cong. 2d sess. H. Doc. 304, 71st Cong. 2d sess.' Rivers and Harbors Committee Doc. 5, 73d Cong., 1st sess. S. Doc. 159, 75th Cong. 3d sess. 1 H. Doc. 580, 76th Cong. 3d sess.1 H. Doc. 340, 77th Cong. 1st sess.1 Specified in Act. H. Doc. 358, 83rd Cong. 2d sess.1 H. Doc. 185, 85th Cong. 1st sess. 3-18 TABLE 3-B (Continued) PHILADELPHIA, PA. DISTRICT AUTHORIZING LEGISLATION Acts Work Authorized Documents HARBOR OF REFUGE, DELAWARE BAY, DE (See Section 7 of Text) June 3, 1896 Breakwater construction Construction of 10 ice piers Construction of 5 additional ice piers July 3, 1930 Aug. 30, 1935 Aug. 26, 1937 Channel 18 feet deep to Queen Anne pier at Lewes, DE (No work has been done on this channel.) Channel 15 feet deep to pier of Atlantic Fisheries Co. about 0.7 mile east of Queen Anne pier. INDIAN RIVER INLET AND BAY, DE (See Section 8 of text) A 15-foot inlet channel, steel and stone jetties, 6 foot channel from end of inlet channel to deep water in the bay and authority to modify interior inlet channel. Mar. 2, 1945 A 9-foot channel from inlet to Old Landing, including basin, and 4-foot channel to highway bridge at Millsboro. July 25, 1912 Aug. 30, 1935 INLAND WATERWAY, REHOBOTH BAY TO DELAWARE BAY, DE. For a 6-foot depth canal to connect Rehoboth Bay and Delaware Bay. For a 6-foot depth entrance near Lewes, for jetties, for widening the canal from Broadkill River to Lewes and basin. Mar. 2, 1945 For a 10-foot depth from Delaware Bay to Lewes and in basin, and for extending jetties.6 . INLAND WATERWAY FROM DELAWARE RIVER TO CHESAPEAKE BAY, DE & MD. (See Section 10 of Text) Aug. 30, 1935 A sea level channel 27 feet deep, 250 feet wide from Delaware River to Elk River and 400 feet down Elk River and Chesapeake Bay to deep water at or near Pooles Island; alter existing bridges over canal; enlarge Delaware City Branch Channel to 8 feet deep and 50 feet wide, with a basin same depth and revetment of both banks east of Fifth Street; enlarge anchorage and mooring basin in Back Creek to 400 feet wide, 1,000 feet long and 12 feet deep; extend jetties at Reedy Point; and construct bulkheads. Aug. 7, 1939 Construct a 4-lane high-level fixed highway bridge at or near St. Georges. Sept. 3, 1954 A channel 35 feet deep and 450 feet wide from Delaware River through Elk River and Chesapeake Bay at water of that depth in the bay, including a cutoff at Penn Central Railroad crossing, with a minimum radius of curvature of 7,000 feet at bends; a high level fixed railroad bridge over cutoff; high level fixed highway bridge at Reedy Point and Summit; and an anchorage in Elk River 35 feet deep and 1,200 feet wide, averaging 3,700 feet long. MANASQUAN RIVER, N.J. (See Section 11 of Text) July 3, 1930 Channel 8 feet deep and provision of works designed to secure channel. Aug. 30, 1935 Widening channel on northerly side. Mar. 2, 1945 Deepening channel to 12 and 14 feet, 10 and 12 foot anchorages.7 Mar 2, 1919 Aug. 26, 1937 MISPILLION RIVER, DE (See Section 12 of Text) A 6-foot depth and extension of south jetty. Extension of north jetty. Sept. 3, 1954 A channel 9 feet deep, 80 feet wide from like depth in Delaware Bay to the landward end of the jetties and thence 60 feet wide to Milford including 3 cutoffs, with a turning basin at Milford. H. Doc. 112.53rd Cong. 2d sess (subproject, approved by War Department, Apr 23, 1900). Subproject, approved by War Department, June 30, 1902.) River and Harbors Committee Doc. 15, 70th stfV. Rivers and Harbors Committee Doc. 56, 74th Cong., 1st sess. 1 Rivers and Harbors Committee Doc. 41, 75th Cong. 1st sess. H. Doc. 330, 76th Cong., 1st sess.' H. Doc. 823, 60th Cong., 1st sess. and Rivers and Harbors Committee Doc. 51, 61st Cong., 3d sess. Rivers and Harbors Committee Doc. 56, 75th Cong., 1st sess.1 H. Doc. 344, 77th Cong., 1st sess.' H. Doc. 201, 72d Cong., 1st sess. and Rivers and Harbors Committee Docs. 18 and 24, 73d Cong., 2d sess.' Public Law 310, 76th Cong., 1st sess. S. Doc. 123, 83rd Cong. 2d sess.' H. Doc. 482, 70th Cong., 2d sess. Senate Committee Doc., 74th Cong., 1st sess. H. Doc. 356, 77th Cong., 1st sess. H. Doc. 678, 62d Cong., 2d sess.' Rivers and Harbors Committee, Doc. 83, 74th Cong., 2d sess.' S. Soc. 229, 81st Cong., 2d sess.' 3-19 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 3-B (Continued) AUTHORIZING LEGISLATION Acts Work Authorized Documents SCHUYLKILL RIVER, PA. (See Section 17 of Text) Aug. 8, 1917 Depths of 35 feet from mouth to Girard Point thence 30 feet, 26, and 22 feet to H. Doc. 1270, 64th University Avenue Bridge, Philadelphia. Cong., 1st sess. July 3, 1930 A depth of 30 feet instead of 35 feet between the mouth and the conditional restora- Rivers and Harbors tion and maintenance of the channel below Passyunk Ave., by the United States. Committee Doc. 40, 71st Cong., 2d sess. 1 July 24, 1946 A depth of 33 feet from the channel in Delaware River to Passyunk Ave., restora- H. Doc. 699, 79th Cong., tion of the project channel dimensions between Passyunk Ave., and University 2d sess. 1 Ave., and full maintenance of the entire project. SALEM RIVER, N.J. July 3, 1930 A channel of 10-foot depth from Delaware River to Masters Sand Plant. H. Doc. 217, 70th Cong. 1st sess.1 Aug. 30, 1935 Extension of project to Clements Bridge. Rivers and Harbors Committee Doc. 15 73d Cong., 1st sess.' WILMINGTON HARBOR, DE (See Section 18 of Text) June 3, 1896 Depths of 21, 10 and 7 feet and jetties. H. Doc. 66, 54th Cong., 1st sess. Annual Report, 1897 p. 12501 July 25, 1912 Purchase or construct a dredge and auxiliaries including a wharf and depot, and H. Doc. 359, 62d Cong., maintenance of project. 2nd sess. Sept. 22, 1922 Entrance channel and basin with 25-foot depth and construction by local interests H. Doc. 114, 67th Cong., of new south jetty. 1st sess. and S. Committee Print, 68th Cong., 1st sess. July 3, 1930 A 30-foot depth between Delaware River and Lobdell Canal and modification or Rivers and Harbors removal of a portion of north jetty. Committee Doc. 20, 71st Cong. 2d sess. Aug. 30, 1935" Completion of new south jetty by the United States subject to provision that city of Rivers and Harbors Wilmington reimburse the United States for cost, without interest, of any part of Committee Doc. 32 structure that may subsequently be occupied and utilized for city activities. 73d Cong., 2d sess. Oct. 17, 1940 Permit temporary occupancy by city of Wilmington of any part of south jetty for H. Doc. 658, 76th Cong., city activities under revocable license, provided occupied portion of jetty is 3rd sess. properly maintained without expense to the United States. July 14, 1960 A 35-foot depth between Delaware River ship channel and Lobdell Canal including S. Doc. 88, 86th Cong., turning basin of same depth, opposite Wilmington Marine Terminal, 200 feet 2d sess. wide, 2,900 feet long on north side of channel, and 2,000 feet long on north side of basin. 1. Contains latest published maps. 2. Also Public Works Administration, September 6, 1933, and Emergency Relief Administration, May 28, 1935. 3. Also Public Works Administration. 4. Channel 37 feet deep and 600 feet wide from Naval Base to Philadelphia-Camden Bridge, deferred for restudy. 5. Channel 37 feet deep and 600 feet wide from Philadelphia-Camden Bridge to Allegheny Ave. deferred for restudy. 6. Extension of jetties considered to be active. 7. The 10 and 12 foot anchorages are considered inactive. 8. Also May 28, 1935, under Emergency Relief Administration. 3-20 PHILADELPHIA, PA. DISTRICT TABLE 3-C OTHER AUTHORIZED NAVIGATION PROJECTS For Last Cost to September 30, 1985 Full Report See Annual Operation and Completed Projects Status Report for Construction Maintenance Absecon Creek, N.J.' COMPLETED 1969 11,935 167,682* Absecon Inlet COMPLETED 1984 534,209 5,939,362 Appoquinimink River DE COMPLETED 1931 36,973 41,270 Big Timber Creek, N.J.' COMPLETED 1962 58,6652 53,986* Broadkill River, DE COMPLETED 1976 68,228 243,641 Cape May Inlet, NJ COMPLETED 1984 149,995 1,115,354 Cedar Creek, Sussex City, DE COMPLETED - 256,100 - Cold Spring Inlet, NJ COMPLETED 1984 879,275 2,391,507 Cooper River, N.J.' COMPLETED 1962 33,102 379,244* Delaware River at Camden, N.J. COMPLETED 1982 464,906 362,79912 Delaware River, Pennsville, N.J. COMPLETED - 256,624 - Double Creek, N.J.' COMPLETED 1912 7,800 -5 Inland Waterway from Chincoteague Bay to Delaware Bay COMPLETED 1981 168,41218 98,36019 Little River, DE COMPLETED 1980 12,016 288,310 Mantua Creek, N.J. COMPLETED 1966 169,687 339,340* Maurice River, N.J. COMPLETED 1948 - -r Delaware Bay to Millville fixed Bridge COMPLETED - 143,98410 147,050 Millville fixed bridge to upper end of project SEE TABLE 3-G Murderkill River, DE COMPLETED 1984 37,630 1,114,354 **Neshaminy State Park Harbor COMPLETED 1968 128,20321 54,601 Oldmans Creek, N.J. COMPLETED 1941 31,188 32,125 **Pepper Creek, DE' COMPLETED 1965 138,09422 1,797* Raccoon Creek, N.J. COMPLETED 1981 83,66520 341,734 St. Jones River, DE 1961 - - Delaware Bay to Lebanon"" COMPLETED - 207,102 66,093 Jetties and entrance at mouth9 - - - Schuylkill River above Fairmount Dam, PA.' COMPLETED 1955 4,291,810 -5 Smyrna River, DE 1949 - - Delaware River to Wharf at Smyrna Landing'15 COMPLETED - 198,844 197,327 Wharf at Smyrna Landing to fixed bridge SEE TABLE 3-G - - - Toms River, N.J. 1950 - - Channel 5 feet deep' COMPLETED - 10,050 33,311 Channel 12 feet deep9 SEE TABLE 3-G - - - Tuckerton Creek, NJ. COMPLETED 1972 60,242 623,917* Waterway from Indian River Inlet to Reboboth Bay, DE COMPLETED 1981 90,908 241,497 Woodbury Creek, N.J.1 COMPLETED 1940 27,09316 56,474 For Last Cost to September 30, 1985 Full Report See Annual Operation and Inactive Projects Status Report for Construction Maintenance Alloway Creek, N.J.' INACTIVE 1931 21,398 35,761 Aquatic Plant Control 1975 87,594 - Chester River, PA3 INACTIVE 1931 6,000 1,139 Dennis Creek, N.J.' INACTIVE 1897 4,701 - Goshen Creek, N.J.' INACTIVE 1905 15,359 870 Ice Harbor at Marcus Hook, PA.'-6 INACTIVE 1928 208,964 14,336 Ice Harbor at New Castle, DE'-6 INACTIVE 1898 224,704 - Leipsic River, DE1 INACTIVE 1931 36,956 32,345 Little Egg Harbor, N.J. '4 INACTIVE -7 15,048 - Maurice River, N.J. 1948 Channel 8 feet deep, Delaware Bay to mouth INACTIVE - - 3-21 REPORT OF THE CHIEF OF ENGINEERS; U.S. ARMY 1985 TABLE 3-C OTHER AUTHORIZED NAVIGATION PROJECTS (Cont'd) For Last Cost to September 30, 1985 Full Report See Annual Operation and Deferred Projects Status Report for Construction Maintenance St. Jones River, DE 1961 - - Delaware Bay to Lebanon ,1' - 207,102 66,093 Jetties and new entrance at mouth9 DEFERRED - - - 1. Completed. 11. Includes $54,590 new work and $28,935 maintenance funds 2. Excludes $50,000 contributed funds expended for new work. expended on previous projects. 3. Includes $6,000 new work and $63 maintenance funds expended 12. Excludes $15,000 contributed funds. on previous projects. 15. Includes $55,085 new work and $22,723 maintenance funds 4. Abandonment recommended in House Doc. 467, 69th Congress, expended on previous projects. 1st Sess. 16. Includes $2,950 new work funds expended on previous projects. 5. Maintenance assumed by local interests. 18. Entire amount expended on previous projects repealed in 1905. 6. Harbor not now required by commerce. 19. Excludes $2,000 contributed funds and includes $25,330 for 7. Last appropriation for project was in 1852. No information is at maintenance for previous projects. hand relative to work done. 20. Includes $757 new work funds expended on previous projects. 8. Includes $3,000 for new work for previous projects. 21. Excludes $327,957 contributed funds allotted expended for new 9. Deferred work. 10. Includes $43,000 new work funds expended on previous projects. 22. Excludes $38,988 non-Federal Funds. *Operation and maintenance figure includes cost incurred for preparation of environmental impact statements. **Projects authorized by the Chief of Engineers. 3-22 PHILADELPHIA, PA. DISTRICT TABLE 3-D OTHER AUTHORIZED BEACH EROSION CONTROL PROJECTS For Last Cost to September 30, 1985 Full Report See Annual Operation and Project Status Report For Construction Maintenance Corson Inlet and Ludlam Beach, N.J. ACTIVE* 1978 314,400 - Great Egg Harbor Inlet and Peck Beach, N.J. ACTIVE* 1978 387,882 Townsend Inlet and Seven Mile Beach, N.J. ACTIVE* - - - Atlantic City, N.J. INACTIVE 1972 2,083,289 _1 Ocean City, N.J. INACTIVE 1969 395,831 -1 Stone Harbor, N.J. INACTIVE 1961 - -1 Barnegat Light, N.J. DEFERRED 1964 70,908 _1 Cape May City, N.J. DEFERRED 1961 22,9572 _1 Long Beach Island, N.J. DEFERRED 1964 40,665 -2 North Wildwood, N.J. DEFERRED 1961 - Rehoboth Beach to Indian River Inlet, DE4 1965 326,116 -1 Ventnor, Margate and Longport, N.J. DEFERRED 1961 - -1 1. Operation and maintenance required by law to be assumed by 3. Excludes cost of $1,146,325 to local interests and $272,766 Federal local interests. participation expended under Public Works Acceleration Program 2. Excludes $58,585 Accelerated Public Works funds expended for for Extension of five existing groins completed 11 May 1964. extension to two groins. 4. This project was included in and modified by the Delaware Coast project. * NO CURRENT YEA. FUNDS. TABLE 3-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS For Last Cost to September 30, 1985 Full Report See Annual Operation and Project Status Report For Construction Maintenance Allentown, Lehigh River, PA. COMPLETED 1961 1,615,581 _1 Bethlehem, Lehigh River, PA. COMPLETED 1966 4,520,995 _1 Mt. Holly, N.J. COMPLETED 1946 283,655 _1 Hay Creek, Birdsboro, PA ACTIVE 1984 335,299 - Pottstown, PA ACTIVE 1984 487,366 - Tamaqua, PA ACTIVE 1984 524,373 - Trexler Lake, PA.: INACTIVE 1981 Aquashicola Reservoir, PA.2 DEFERRED 1963 - - Maiden Creek Reservoir, PA.2 DEFERRED 1963 - -' 1. Maintenance assumed by local interest as required by authorizing project. 2. New project deferred. 3. $1,316,464 expended for preconstruction planning only. 4. Transferred to Baltimore Dist. in 1982. 3-23 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 3-F MULTIPURPOSE PROJECT INCLUDING POWER For Last Cost to September 30, 1985 Full Report See Annual Operation and Project Report for Construction Maintenance Tocks Island, PA., N.J. and NY2 1979 65,106,2601 - Tocks Island (Relocation of U.S. Route 209 only) PA2 1979 195,223 - 1. Includes $3,489,088 for AE&D. authority to proceed with the project. Legislation would be required 2. National Parks and Recreation Act of 1978 terminated Corps' to proceed with the project. TABLE 3-G DEAUTHORIZED PROJECTS For Last Full Date Federal Contributed Report See Annual And Funds Funds Navigation Projects Report For Authority Expended Expended 3 Oct 78 Appoquinimink River, DE' 1931 HD 95-351 $ 78,243 - 5 Aug 77 Delaware River, Mouth of Neversink 1917 HD 94-192 - - Maurice River, N.J. 1948 Section 12 PL 93-251 Millville fixed bridge to upper end of project 2 2 Nov 79 Oldmans Creek, N.J. 1941 Section 12 PL 93-251 $ 63,313 - 2 Nov 79 Rancocas River, N.J.4 1942 Section 12 PL 93-251 $ 57,590 - 2 Nov 79 Smyrna River, DE5 1949 HD 95-157 $396,169 - Wharf at Smyrna Landing to fixed bridge. 2 Nov 79 Toms River, N.J.6 1950 Section 12 PL 93-251 $ 43,361 - Channel 12 feet deep Flood Control Projects 2 Nov 79 Lehigh River at Bethlehem, PA.7 1966 Section 12 PL 93-251 $4,520,995 1. Includes $36,973 new work, and $41,270 for maintenance. 2. There is no need now for this portion of the project. 3. Includes $31,188 new work, and $32,125 for maintenance. 4. Includes $44,500 new work, and $13,090 for maintenance. 5. Includes $143,759 new work, $55,085 previous project, $174,602 for maintenance, and $22,723 maintenance, previous project. 6. Includes $10,050 new work, and $33,311 for maintenance. 7. Maintenance assumed by local interest. 3-24 BALTIMORE, MD DISTRICT* This district comprises the watershed of Susquehanna River and its tributaries from headwaters in south central New York State through central Pennsylvania to its mouth in Chesapeake Bay; watershed of the Potomac River and its tributaries from headwaters in Maryland, eastern West Virginia, and northern Virginia to its mouth in Chesapeake Bay; District of Columbia; and southwestern portion of Delaware. It includes that portion of Chesapeake Bay and its tributaries north of Smith Point, MD, on western shore of the bay, and includes that portion of Maryland between Chesapeake Bay and Atlantic Ocean. IMPROVEMENTS Navigation Page 1. Baltimore Harbor and Channels, MD and VA ............... 4-3 2. Baltimore Harbor, MD, Collection and Removal of Drift ....... 4-4 3. Claiborne, Harbor, MD ................ 4-4 4. Fishing Bay, MD ................... 4-4 5. Fishing Creek, MD .................... 4-4 6. Herring Bay and Rockhold Creek, MD ....................... . 4-5 7. Honga River and Tar Bay (Barren Island Gaps), MD ............ 4-5 8. Knapps Narrows, MD ................. 4-5 9. Little Wicomico River, VA............. .4-6 10. Lower Thorofare, Deal Island, M D ......................... 4-6 11. Ocean City Harbor and Inlet and Sinepuxent Bay, MD ................ 4-6 12. Parish Creek, MD.................... 4-7 13. Pocomoke River, MD .................. 4-7 14. Potomac and Anacostia Rivers, DC, Collection and Removal of Drift ................ 4-7 15. Prevention of Obstructions and Injurious Deposits, Baltimore Harbor, MD............... 4-8 16. Queenstown Harbor, MD............... 4-8 17. Rhodes Point to Tylerton, MD .......... 4-8 18. St. Georges Creek, MD ................ 4-9 19. St. Patricks Creek, MD ................ 4-9 20. Susquehanna River above and below Havre De Grace, MD........... 4-9 21. Tred Avon, MD .................... 4-9 22. Twitch Cove and Big Thorofare, MD...................... 4-10 23. Upper Thorofare, MD ................. 4-10 24. Washington Harbor, DC ............... 4-10 25. Wicomico River, MD ................. 4-11 Navigation (cont'd) 26. 27. 28. 29. Reconnaissance and Condition Surveys... Navigation work under special authorization ....................... Beach Erosion Control Colonial Beach, VA ........ Beach Erosion Control Work under special authorization . Page 4-11 4-11 .......... 4-11 .......... 4-12 Flood Control 30. Black Walnut Point, MD............... 4-12 31. Bloomington Lake, MD and WV ........ 4-12 32. Cumberland, MD, and Ridgeley, WV .... 4-12 33. Lackawanna River Basin, PA ........... 4-13 33A. Aylesworth Creek Lake, PA ............ 4-13 34. Raystown Lake, Raystown Branch, Juniata River, PA ................... 4-13 35. Southern New York Flood Control Projects .................... 4-13 35A. Addison, NY ....................... 4-13 35B. Almond Lake, NY.................... 4-14 35C. Arkport Dam, NY ................... 4-14 35D. Avoka, NY ......................... 4-14 35E. Binghamton, NY..................... 4-14 35F. Canisteo, NY....................... 4-15 35G. Corning, NY ........................ 4-15 35H. East Sidney Lake, NY ................ 4-15 35I. Elmira, NY ........................ 4-16 35J. Hornell, NY .......................... 4-16 35K. Lisle, NY .......................... 4-16 35L. Oxford, NY ........................ 4-17 35M. Whitney Point Lake, NY .............. 4-17 35N. Whitney Point Village, NY ............. 4-17 36. Stillwater Lake, Lackawanna River, PA .. 4-17 37. Susquehanna River Flood Control Project, NY and PA ................ 4-17 4-1 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Flood Control (cont'd) 37A. Cowanesque Lake, PA ................. 37B. Tioga-Hammond Lakes, PA ............ 38. West Branch of Susquehanna River, PA . 38A. Alvin R. Bush Dam, PA ............... 38B. Curwensville Lake, PA................ 38C. Foster Joseph Sayers Dam, PA ......... 39. Wyoming Valley, PA ................. 40. York, Indian Rock Dam, PA ............ 41. Inspection of Completed Flood Control Projects .................... 42. Scheduling Flood Control Reservoir Operations ........... ............. 43. Flood Control Work under Special Authorization....................... Water Supply 44. Washington Aqueduct ................. General Investigations 45. Surveys ............................. 46. Collection and Study of Basic Data ...... Page General Investigations (cont'd) 4-18 4-18 4-18 4-19 4-19 4-19 4-19 4-20 47. 48. Page Continuation of Planning and Engineering .................... 4-21 Advanced Engineering and Design....................... 4-21 Tables Table 4-A Cost and Financial Statement ...... 4-20 Table 4-B Authorizing Legislation ........... Table 4-C Other Authorized 4-20 Navigation Projects.................. Table 4-D Other Authorized Beach Erosion 4-20 Control Projects ................. Table 4-E Other Authorized Flood Control Projects ................. 4-20 Table 4-F Not Applicable Table 4-G Deauthorized Projects........... Table 4-H Reconnaissance and Condition Surveys ............... 4-21 Table 4-I Inspection of 4-21 Completed Projects .............. 4-22 4-27 4-34 4-35 4-36 4-37 4-38 4-39 4-2 BALTIMORE, MD DISTRICT Navigation 1. BALTIMORE HARBOR AND CHANNELS, MD AND VA Location. Baltimore Harbor is at the head of the navigable portion of Patapsco River about 12 miles from Chesapeake Bay. The Patapsco River rises near the town of Westminster in Carroll County, MD, and flows generally southeast for about 65 miles to enter Chesapeake Bay. (See National Ocean Survey Chart 12278.) Existing Project. a. A uniform main channel depth of 50 feet between Cape Charles, VA, and Fort McHenry at Baltimore, MD, with dimensions as follows: (1) Cape Henry Channel: 50 feet deep and 1,000 feet wide from the 50-foot depth curve in the Atlantic Ocean to that depth in Chesapeake Bay, a distance of 2.3 miles; (2) York Spit Channel: 50 feet deep and 1,000 feet wide connecting the 50-foot depth curves in Chesapeake Bay near York Spit, a distance of 18.2 miles; (3) Rappahannock Shoal Channel: 50 feet deep and 1,000 feet wide connecting the 50-foot depth curves in the Chesapeake Bay opposite the Rappahannock River, a distance of 8.9 miles; and (4) Baltimore Harbor Approach Channels: 50 feet deep and generally 800 feet wide, widened at the approach and bends, from the 50-foot depth curve in Chesapeake Bay opposite the mouth of the Magothy River to Fort McHenry on the Patapsco River, a distance of 19.9 miles. b. Branch channels with dimensions as follows: (1) Connecting Channel to Chesapeake and Delaware Canal Approach Channel: 35 feet deep, 600 feet wide, and 13.0 miles long from the Cutoff-Brewerton Angle in the main channel to the 35-foot depth curves in the natural channel on the east side of Chesapeake Bay which is part of the inland waterway from Delaware River to Chesapeake Bay. The channel includes the Brewerton Extension and Swan Point and Tolchester Sections; (2) Curtis Bay: 50 feet deep, 600 feet wide, and 2.3 miles long from the main channel to and including a turning basin at the head of Curtis Bay; (3) Curtis Creek: (a) a channel, 35 feet deep and generally 200 feet wide, from the 50-foot channel in Curtis Bay to 750 feet downstream of the Pennington Avenue Bridge; (b) a channel, 22 feet deep and generally 200 feet wide, from the 35-foot channel to and along the marginal wharf of the Curtis Bay Ordnance Depot; (c) an irregular shaped 3-acre basin, with a depth of 18 feet, adjacent to the head of the 22-foot channel; (d) a basin, 15 feet deep and 450 feet wide, from the end of the 22-foot channel to the end of the marginal wharf; and (e) a channel, 22 feet deep and 200 feet wide, from the 22-foot channel south of the Baltimore and Ohio Railroad Bridge to the vicinity of Arundel Cove, a distance of 2,800 feet, thence 100 feet wide in Arundel Cove for a distance of 2,100 feet, with an anchorage basin, 700 feet square, adjacent to the channel and southwest of the wharf of the Coast Guard Depot at Curtis Bay; (4) Middie Branch: (a) Ferry Bar East Section: a channel, 42 feet deep and 600 feet wide, from the main channel at Fort McHenry to Ferry Bar, a distance of 1.4 miles; (b) Ferry Bar West Section: a channel, 35 feet deep and 400 feet wide, from the Ferry Bar East Section to Ferry Bar, a distance of 0.8 mile; (c) Spring Garden Section: a channel, 27 feet deep and 250 feet wide, from Ferry Bar to and including a turning and anchorage basin immediately below the Western Maryland Railway Bridge, a distance of 1.0 mile; and (5) Northwest Branch: Federal maintenance of 39-foot or 35-foot deep channels after either depth has been provided by local interests: (a) East Channel: a channel, 49 feet deep, 600 feet wide, and 1.0 mile long with a turning basin at the head of the channel from that depth existing at the time of construction; and (b) West Channel: a channel, 40 feet deep, 600 feet wide, and 1.2 miles long with a turning basin at the head of the channel from that depth existing at the time of construction. c. The following anchorages: (1) Quarantine Anchorage: 35 feet deep, 3,500 feet long, and 600 feet wide; (2) Riverview Anchorage No. 2: 30 feet deep, 2,400 feet long, and 1,300 feet wide; (3) Riverview Anchorage No. 1: 35 feet deep, 4,500 feet long, and 1,500 feet wide; and (4) Fort McHenry Anchorage: 35 feet deep, 3,500 feet long, and 400 feet wide. The mean range of tide is 2.8 feet at the Cape Henry Channel, 2.3 feet at the York Spit Channel, 1.4 feet at the Rappahannock Shoal Channel, 0.8 foot at the Craighill Entrance, 0.9 foot in the Cutoff Section, 1.1 feet at Fort McHenry, and 1.2 feet at Pooles Island in the upper Chesapeake Bay. Depths refer to mean low water. Estimated cost for new work is $412,880,000 which includes: $8,330,000 for completed work through the River and Harbor Act of 1945; $47,350,000 (October 1985 prices) for work authorized by the River and Harbor Act of 1958 of which $42,800,000 is Corps of Engineers, $60,000 is U.S. Coast Guard and $4,490,000 is non- Federal; and $357,200,000 (October 1985 prices) for work authorized by the River and Harbor Act of 1970, of which $400,000 is U.S. Coast Guard and $356,800,000 is Corps of Engineers and non-Federal. Widening 35-foot depth from Port Covington Channel from 150 to 400 feet to Ferry Bar, widening 27-foot depth channel from 150 to 250 feet to Hanover Street Bridge, and providing a channel 27 feet deep by 250 feet wide to Western Maryland Railway Bridge with an anchorage and turning basin at upper end is considered inactive and is excluded from the foregoing estimate. Estimated cost (1954) of this portion is $1,603,000. Local cooperation. Requirements are described in full on page 4-3 of Fiscal Year 1982 Annual Report. Terminal facilities. The Port of Baltimore has 45 miles of waterfront of which 25 miles are industrially developed. There are 94 covered and open overseas piers for the loading and discharging of 173 ships, providing 84 general cargo, 65 specialized cargo, and 24 public bulk cargo berths. The existing ground storage is equivalent to 53,700 railroad cars of cargo. There are 31 public general merchandise warehouses, with 4.9 million square feet of storage space and 4.7 million cubic feet of cold storage space. Eight ship-building, ship repair, and ship dismantling yards are available for handling up to 90 vessels. The three grain elevators in the port have a capacity of about 13 million bushels. Latest description of terminal facilities is in "Port Series No. 10 (revised 1983)" 4-3 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 on Port of Baltimore, MD, (issued by Board of Engineers for Rivers and Harbors). Operations and results during fiscal year. New Work. Remaining work under the River and Harbor Act of 1958 (i.e., deepening and widening the Brewerton Extension) was reactivated 15 May 1985 and preconstruction planning was essentially completed at a cost of $198,183. Preconstruction planning under the River and Harbor Act of 1970 was completed in FY1985 and construction funds of $15,000 were allocated from the 1985 Supplemental Appropriations Act (P.L. 99-88). Maintenance, Baltimore District: Condition surveys of the project channel were made. Maintenance dredging of the Brewerton Channel, Brewerton Angle, Ft. McHenry Channel, and Curtis Bay Channel, by contract, which began on May 15, 1984, was completed on November 2, 1984, a total of 3,908,346 cubic yards of material were removed and deposited in the Hart-Miller Island containment facilities at a cost of $12,079,400. Maintenance dredging of the cutoff Angle, Fort McHenry Channel, Ferry Bar Channel, and Riverview Anchorages, by contract, began on May 18, 1985, and was completed on September 15, 1985. A total of 3,119,482 cubic yards of material were removed and deposited in the Hart-Miller Island containment facilities at a cost of $14,805,591. Maintenance, Norfolk District: Condition surveys of the Cape Henry, York Spit and Rappahannock Shoal Channels were performed at a cost of $75,500. 2. BALTIMORE HARBOR, MD COLLECTION AND REMOVAL OF DRIFT Location. Project applies to Baltimore Harbor, MD, and its tributaries. Existing project. Provides for collection and removal of drift from Baltimore Harbor and its tributary waters, and authorizes the Secretary of the Army to allot such amounts as may be necessary for work from appropriations for maintenance and improvement of existing river and harbor works or other available appropriations, and that this work shall be carried as a separate and distinct project. It is wholly a work of maintenance. Purpose of work is to afford relief from variable conditions of obstruction. Local cooperation. None required. Terminal facilities. See Section 1 of this text. Operations and results during fiscal year. Maintenance: Operations, by hired labor, consisted of collection and disposal of 26,460 cubic feet of driftwood, ranging from small blocks up to timbers of large dimensions. 3. CLAIBORNE HARBOR, MD Location. The harbor is located on the eastern side of Eastern Bay, an arm of Chesapeake Bay, about 42 miles southeast of Baltimore Harbor. (See U.S. Coast and Geodetic Survey Chart No. 1225.) Existing project. This provides for a channel 14 feet deep from the vicinity of the harbor wharves to deep water in Eastern Bay with widths of 100 feet at mean low water for a distance of 1,800 feet to the bend opposite the existing Black Beacon, thence widening in a distance of 260 feet to 150 feet to the 14-foot depth in Eastern Bay, with necessary widening at the bends. The total length of the channel is about 4,400 feet. The project also provides for a 250-foot extension of the jetty built by the railway company. Terminal facilities. There are two solid bulkhead wharves, with open pile piers at their outer ends, served by this improvement. Operations and results during fiscal year. Maintenance: Engineering and design work in connection with the proposed rehabilitation of the jetty was accomplished. 4. FISHING BAY, MD Location. McCreadys, Goose, and Farm Creeks are small tidal estuaries of Fishing Bay, a large estuary at head of Tangier Sound. Fishing Bay is connected by Hooper Strait with Chesapeake Bay to the west about 15 miles above mouth of Potomac River. Goose Creek enters the bay about 3.5 miles above the mouth. Farm Creek enters Fishing Bay about 6 miles above the mouth and approximately opposite mouth of McCreadys Creek. (See Coast and Geodetic Survey Chart 1224.) Existing project. Provides for channels 6 feet deep and generally 60 feet wide at mean low water, suitably widened where necessary to offer adequate sheltered anchorage space from deep water in Fishing Bay to vicinity of county or packing house wharves in McCreadys, Farm, and Goose Creeks. Mean range of tide is about 2 feet. Cost of new work for completed project was $33,874. Terminal facilities. A public wharf built with aid of Federal funds is on McCreadys Creek about 200 feet above the mouth. There is a privately owned pile-andtimber pier about 1,500 feet above the mouth of Goose Creek. There are two privately owned wharves on Farm Creek and a public wharf owned by Dorchester County. Private wharves on each of the waterways are open to the public for transaction of business with the owners. Operations and results during fiscal year. Maintenance: Engineering and design work was accomplished in connection with proposed maintenance dredging. 5. FISHING CREEK, MD Location. A narrow winding tidal stream which enters Chesapeake Bay from the west 56 miles south of Baltimore and about 26 miles south of Annapolis, MD. (See Coast and Geodetic Survey Chart 12266.) Existing project. A channel 7 feet deep with widths of 100 and 60 feet from deep water in the Chesapeake Bay to an anchorage of same depth, 120 feet wide and 400 feet long, located in marsh 500 feet above mouth of creek, and twin stone jetties at entrance; north jetty is 4-4 BALTIMORE, MD DISTRICT about 1,050 feet long, and south jetty about 1,100 feet long. The mean range of tide is about 1 foot. Cost of new work for the completed project was $111,242. Local cooperation. Fully complied with except that local interests are to furnish spoil disposal areas as needed for future maintenance. Terminal facilities. Seven hundred feet of bulkhead wharf are available on the south side of the entrance channel running west from bay shore, and the U.S. Navy Department constructed a pile-and-timber wharf on west side of basin. Operations and results during fiscal year. Maintenance: Engineering and design was accomplished in connection with rehabilitation of the twin stone jetties. 6. HERRING BAY AND ROCKHOLD CREEK, MD Location. Herring Bay is a wide-mouthed indentation on the west side of Chesapeake Bay about 20 miles below Annapolis, MD. It is about 3 miles long from north to south and penetrates the shore for a depth of about 1 mile. Rockhold Creek, which is about 2.5 miles long, is an estuary which extends northward from the northerly end of Herring Bay. (See Coast and Geodetic Survey Chart 1225.) Existing project. Provides for channel 7 feet deep and 60 feet wide from 7-foot contour in Herring Bay to vicinity of county wharf on Rockhold Creek, with turning basin of same depth, 100 feet wide and 150 feet long at head of channel, and a stone breakwater approximately 900 feet long east of entrance channel. Mean range of tide is about 1.5 feet and extreme tidal range about 4 feet. The Federal cost of new work for completed project was $50,591. Local cooperation. Fully complied with except local interests are to furnish disposal areas for future maintenance as needed. Terminal facilities. Consists of a public wharf on Rockhold Creek about 600 feet below the county bridge, open to all, together with a few private landing stages. No freight-handling devices are installed on any of the wharves which are considered adequate for existing commerce. Operations and results during fiscal year. Maintenance: Engineering and design was accomplished in connection with proposed maintenance dredging. 7. HONGA RIVER & TAR BAY (BARREN ISLAND GAPS), MD Location. Honga River is a tidal estuary of Chesapeake Bay and penetrates Dorchester County on Eastern Shore of Maryland between Hooper Islands and the mainlands; Tar Bay lies between Barren Island and the mainland and Hooper Islands. Fishing Creek connects Tar Bay and Honga River. Back Creek is a branch of Honga River extending into Hooper Islands; the mouth is about 2 miles south of Fishing Creek. (See Coast and Geodetic Survey Chart 1224.) Existing project. Provides for a channel 60 feet wide and 7 feet deep at mean low water from the 7-foot contour in Chesapeake Bay, through Tar Bay and Fishing Creek to the 7-foot contour in Honga River, 25,300 feet long, and a channel in Back Creek 7 feet deep and 60 feet wide from the 7-foot depth curve in Honga River to a point near the head of Back Creek with a turning basin of the same depth 150 feet long and 200 feet wide at the head of channel, about 5,500 feet long. Mean range of tide is about 1.4 feet. Federal cost of new work for the completed project was $66,119. Local cooperation. Fully complied with except that local interests are to furnish spoil disposal areas for future maintenance as needed. Terminal facilities. Numerous small private wharves are scattered along Fishing Creek and Back Creek. A public wharf is on Fishing Creek. A public wharf, 4 oyster houses, and a marine railway are on Back Creek. Facilities are adequate for existing and reasonably prospective commerce. Operations and results during fiscal year. Maintenance: A maintenance dredging contract was completed in January 1985. A total of 155,600 cubic yards of material were removed. 8. KNAPPS NARROWS, MD Location. A small channel separating Tilghman Island from mainland of eastern shore of Chesapeake Bay about 40 miles south of Baltimore, MD. (See Coast and Geodetic Survey Chart 1225.) Existing project. A channel 9 feet deep at mean low water, 75 feet wide, widened at the bends from deep water in Chesapeake Bay to deep water in Harris Creek, MD. Mean range of tide is 1.4 feet. Cost of new work for completed project was $46,121. Existing project channel was authorized by the Public Works Administration, September 16, 1933, and later adopted by 1935 River and Harbor Act. Local cooperation. Complied with except local interests must furnish spoil disposal areas as needed for future maintenance. Terminal facilities. A bulkhead wharf exists on each side of the southerly abutment of the bridge across the Narrows. There are several small-boat landings within the Narrows and several marine railways for repairing boats of a few feet in draft. A bulkhead landing is available for public use at the turning basin. Operations and results during fiscal year. Maintenance: A maintenance dredging contract was completed in April 1985. A total of 58,413 cubic yards of material were removed. 4-5 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 9. LITTLE WICOMICO RIVER, VA Location. A tidal estuary 6 miles long in Northumberland County, VA, flowing southeasterly to Potomac River, which it enters on the right bank one-half mile upstream of its mouth and about 108 miles downstream from Washington, DC. (See Coast and Geodetic Survey Chart 12233.) Existing project. A channel 8 feet deep, 150 feet wide, and 4,800 feet long, extending from deep water in the Potomac River to deep water in the Little Wicomico River; two stone jetties, extending to the 8-foot contour in Potomac River; and bulkhead walls from the inner ends thereof extending sufficiently into Little Wicomico River to stabilize the dredged inner channel. Plane of reference is mean low water. Tidal ranges in Potomac River at the entrance are: Mean 1.2 feet; irregular, 2.5 fee*; and extreme, about 7 feet. Mean tidal range within the river is about 1 foot. Federal cost of new work for the completed project was $81,885, exclusive of $5,000 contributed by local interests. Local cooperation. Fully complied with. Terminal facilities. Two wharves open to the public and numerous small wharves and stagings for private use, an oyster shucking, and packing plant, and a marine railway and boat-building yard. Facilities are considered adequate for present commerce. Operations and results during fiscal year. Maintenance: A contract for rehabilitation of the twin stone jetties was awarded on August 20, 1985. A contract for maintenance dredging was completed in April 1985. A total of 85,000 cubic yards of material were removed. 10. LOWER THOROFARE, DEAL ISLAND, MD Location. This is a tidal waterway, about 1.5 miles long and from one-eighth to one-half mile wide, branching off from Tangier Sound between Deal Island and Little Deal Island, Md. It is about 12 miles north of Crisfield Harbor, Md. (See Coast and Geodetic Survey Chart 78.) Previous project. The original project was dated March 3, 1881. For further details see page 1790 of Annual Report for 1915. Existing project. Provides for a channel 60 feet wide and 7 feet deep from that depth in Tangier Sound to and including a mooring basin of the same depth, 100 feet wide and 300 feet long, in the marsh at the head of the cove at Wenona. The cost for new work for the completed project was $39,658, exclusive of amounts expended under previous projects. Local cooperation. Fully complied with except local interests are required to furnish spoil disposal areas for future maintenance as needed. Terminal facilities. There are three packing-house wharves and a small marine railway above the head of the project channel at Wenona. The facilities are privately owned but are open to the public for transaction of business with the owners. Present facilities are adequate for existing commerce. Sufficient areas are available for the construction of additional terminals when and as required. Operations and results during fiscal year. Maintenance: Engineering and design work was accomplished in connection with proposed maintenance dredging. 11. OCEAN CITY HARBOR AND INLET AND SINEPUXENT BAY, MD Location. Ocean City is on a barrier island between Sinepuxent Bay and Atlantic Ocean about 35 miles south of entrance to Delaware Bay. (See Coast and Geodetic Survey Chart 1220.) Existing project. This provides for an inlet channel 300 feet wide and 16 feet deep from the 16-foot depth curve in Atlantic Ocean through the inlet to the channel in the Isle of Wight Bay, protected on the south side by a stone jetty with a top elevation of 8.8 feet above mean low water and a top width of 18 feet, and on the north side by a stone jetty with a top elevation of 9 feet above mean low water and a top width of generally 20 feet, thence generally 200 feet wide and 16 feet deep to the project harbor; a depth of 14 feet and 150 feet wide to the head of the harbor, a length of approximately 3,400 feet; a channel 6 feet deep and 150 feet wide in Sinepuxent Bay from the inlet to Green Point, and thence 100 feet wide in Chincoteague Bay; and for a channel 6 feet deep and 125 feet wide from the inlet channel to a point opposite North Eighth Street in Ocean City, thence 75 feet wide into the Isle of Wight Bay. Depths in the inlet channel and harbor refer to project datum. Depths in the bay channels refer to mean low water. The elevation of mean low water in the bays above mean low water in the ocean at Ocean City varies from about 0.8 foot in the vicinity of the inlet to 1.7 feet at their heads. The mean range of ocean tide is 3.4 feet. The extreme range is from 3 feet below mean low water to about 3.5 feet above mean high water, a total of 9.9 feet. In the bays the mean range of tide varies from approximately 2.5 feet at the inlet to 0.3 foot at their heads. Greater fluctuations are caused by prolonged high winds. Federal cost of new work for the completed project was $1,190,530, exclusive of $500,000 contributed by local interests and exclusive of $3,700,000 for rehabilitating the south jetty. Local cooperation. Fully complied with except local interests must furnish spoil disposal areas for future maintenance as needed. Terminal facilities. On bay side of Ocean City: two storage basins, for pleasure and small commercial craft, and numerous privately owned pile-and-timber piers and bulkhead wharves. At project harbor: a public landing about 1,000 feet long, several privately constructed bulkhead wharves open to the public for transaction of business with the owners, and a boat repair yard with a marine railway capable of handling boats up to about 150 tons. All piers and wharves are accessible by highway. Port facilities have been expanded to include all available space in the Fish Harbor. 4-6 BALTIMORE, MD DISTRICT Operations and results during fiscal year. New Work: Continuing construction for the south jetty rehabilitation. is 95% complete. Maintenance: Filling of scour hole completed. Maintenance dredging of the Isle of Wight Bay was completed in June 1985. A total of 21,000 cubic yards of material were removed. 12. PARISH CREEK, MD Location. A small branch of West River, an estuary of Chesapeake Bay on Maryland western shore, at Shadyside, Md., about 7 miles south of mouth of Severn River. (See U.S. Coast and Geodetic Survey Chart No. 1225.) Existing project. Provides for a channel 8 feet deep and 50 feet wide, widened at ends, from deep water in West River to head of south fork of Parish Creek, and an anchorage basin at junction of north fork having a depth of 6 feet and an area not exceeding 1/2 acres. Mean tidal range is about 2 feet. Cost of new work for completed project was $19,170 exclusive of $1,000 contributed by local interests. Average annual maintenance cost for past 5 years was $6,000. Existing project was adopted by River and Harbor Act of August 30, 1935. (See H. Doc. 185, 72d Cong., 1st sess., which contains latest published map.) Local cooperation. Local interests must contribute $1,000 toward cost of improvement, furnish suitable spoil-disposal areas, and provide a suitable water freight terminal at head of Parish Creek, open to all on equal terms. Total funds required to complete project were provided by Works Progress Administration. Local interests furnished disposal areas. Not fully complied with in that a public wharf has not been provided. Terminal facilities. There are numerous timber piers, one bulkhead wharf, two marine railways, 300 feet of concrete bulkhead and 350 feet of timber bulkhead on Parish Creek. Piers and bulkheads are privately owned, but open to the public for transaction of business with owners. Facilities are considered adequate for existing commerce. Operations and results during fiscal year. Maintenance: Engineering and design work was accomplished in connection with proposed maintenance dredging. 13. POCOMOKE RIVER, MD Location. Pocomoke River is a tributary of Pocomoke Sound, a tidal estuary on the east side of Chesapeake Bay about 40 miles north of Cape Charles, VA. Existing project. Provides for a channel 11 feet deep at mean low water and 150 feet wide from the 11-foot depth in Pocomoke Sound to Tulls Point, thence 100 feet wide to deep water in Pocomoke River above Williams Point, and for construction of a dike along the offshore side of channel between Tulls Point and the end of the existing dike; and a channel 9 feet deep at mean low water and 100 to 130 feet wide from Shad Landing to the bridge at Snow Hill. Length of project is about 8.7 miles from Pocomoke Sound to Williams Point, and about 4.5 miles from Shad Landing to Snow Hill, MD. Shad Landing is about 25.7 miles above the mouth of the river. Mean range of tide is 2.4 feet in Pocomoke Sound and 2.5 feet in the river at Snow Hill. Prolonged high winds on Chesapeake Bay frequently cause greater fluctuations. Estimated cost (1969) for new work is $1,071,458 exclusive of amounts expended under previous projects. Extension of channel above the bridge at Snow Hill, 100 feet wide, 9 feet deep and widened to 150 feet to form a turning basin at upper end, is considered inactive and is excluded from the foregoing estimate. Estimated cost of this portion is $22,000 (1956). Local cooperation. Complied with for section of project from Pocomoke Sound to Pocomoke River and from Shad Landing to the highway bridge at Snow Hill, authorized by acts of June 3, 1896, and August 30, 1935, except local interests must furnish releases from damage to oyster beds and spoil disposal areas as required for future maintenance. Terms for the section of the project above the highway bridge at Snow Hill, authorized by act of March 2, 1945, required local interests to furnish all lands, easements, rights-of-way, and spoil disposal areas for initial work and future maintenance, hold the United States free from damages resulting from the improvement; and contribute one-half the initial cost of that portion of project, but not to exceed $4,250. This portion is considered inactive. Terms for the 11-foot depth channel from Pocomoke Sound to deep water in Pocomoke River above Williams Point, authorized by act of September 3, 1954, require local interests provide all lands, easements, rights-of-way, and spoil disposal areas for construction and future maintenance of the project; and hold the United States free from damages due to construction and maintenance, including such damages as may occur to the public or leased oyster beds. Terminal facilities. Waterfronts at Pocomoke City and Snow Hill are built up principally with earthfilled timber bulkheads, the majority of which are privately owned. A few of the warehouses and factories on the river at these communities have railroad sidings and mechanical freighthandling facilities. Any appreciable increase in commerce at Pocomoke City or Snow Hill would necessitate construction of new facilities and repair of existing structures. Adequate space is available for development of additional terminals. Operations and results during fiscal year. Maintenance: A maintenance dredging contract was completed in February 1985. A total of 45,000 cubic yards of material were removed. 14. POTOMAC AND ANACOSTIA RIVERS, DC COLLECTION AND REMOVAL OF DRIFT Location. Project applies to the Potomac and Anacostia Rivers, Washington, DC and their tributaries. Existing project. Collection and removal of drift from the waters of the Potomac and Anacostia Rivers and their tributaries in the Washington Area from the head 4-7 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 of tidewater to Mount Vernon, VA. Total length of project, considering both sides of the waterway, is about 50 miles. Local cooperation. None required. Terminal facilities. See Section 23 of this text. Operations and results during fiscal year. Maintenance: Operations by hired labor consisted of collection and disposal of 216,270 cubic feet of driftwood, ranging from small blocks up to timbers of large dimensions. 15. PREVENTION OF OBSTRUCTIONS & INJURIOUS DEPOSITS, BALTIMORE, MD Location. Project applies to tidal waters of the harbor of Baltimore and its adjacent and tributary waters and to all tidal waters of Chesapeake Bay and in Maryland. Existing project. Patrol and inspection throughout the project location to detect violations of sections 13 and 15 of the River and Harbor Act of March 3, 1899 and to investigate obstructions to navigation pursuant to Federal regulations (33 CFR 209.109). Local cooperation. None required. Operations and results during fiscal year. Maintanance: Operations, by Supervisor of Harbor of Baltimore included inspections of approximately 75 Federal navigation channels within the project location to insure channels are not obstructed to general navigation by debris, sunken vessels/wrecks and/or fishing appurtenance. There were 7 detailed investigations of sunken vessels/wrecks resulting in no declarations of "Hazards to Navigation" issued. 16. QUEENSTOWN HARBOR, MD Location. Queenstown Creek is an estuary of Chester River about 2 miles long on the easterly side of the Chesapeake Bay about 35 miles southeast of Baltimore. (See U. S. Coast and Geodetic Survey Chart No. 548.) Previous projects. The original project was dated March 3, 1871. The cost and expenditures on it prior to adoption of the existing project in 1902 were $19,000. For further details of previous projects see page 1789 of Annual Report for 1915. Existing project. This provides for a channel 10 feet deep at mean low water and 200 feet wide from that depth in Chester River to the 10-foot contour in Queenstown Creek, a distance of about 4,000 feet; and for a channel 7 feet deep at mean low water and 75 feet wide extending from the 7-foot contour in Queenstown Creek to and including a mooring basin of the same depth and 300 feet square opposite of the town wharf in Little Queenstown Creek. The mean range of tide is about 1.3 feet; however, greater fluctuations frequently result from prolonged or high winds. The cost of new work for the completed project was $53,858. The existing project was adopted by the River and Harbor Acts of June 13, 1902 (H. Doc. 92, 56th Cong., 1st sess.) and September 3, 1954 (H. Doc. 718, 81st Cong., 2d sess.). Maps are published in the project documents. Local cooperation. None required for the 10-foot depth and 200-foot width portion of the project, authorized by the River and Harbor Act of June 13, 1902. Under the remaining portion of the project, authorized by the River and Harbor Act of September 3, 1954 fully complied with except that local interests are to furnish without cost to the United States all lands, easements, rights-of-way, and suitable spoil-disposal areas for subsequent maintenance when and as required; and hold and save the United States free from damages due to maintenance of the project, including such damage as may occur to the public or leased oyster beds. Terminal facilities. There are several small private wharves and bulkheads on Little Queenstown Creek. A public bulkhead wharf has been constructed and dredging to a depth of 7 feet of the area around the wharf has been accomplished by order of the town commissioners of Queenstown, Md. Local interests are planning to install gasoline tanks on the town wharf in the near future. Adequate space is available for the construction of additional private or public wharves. Operations and results during fiscal year. Maintenance: A maintenance dredging contract was completed in June 1985. A total of 36,154 cubic yards of material were removed. 17. RHODES POINT TO TYLERTON, MD Location. Rhodes Point and Tylerton are two settlements about 1.5 miles apart on Smith Island, between Chesapeake Bay and Tangier Sound, about 60 miles north of Virginia Capes and about 110 miles south of Baltimore. (See Coast and Geodetic Survey Chart 1224.) Existing project. Channel 6 feet deep, 50 feet wide from that depth in Tyler Creek to and including an anchorage basin of the same depth 150 feet wide and 400 feet long at Tylerton; channel 6 feet deep and 50 feet wide from that depth in Shanks Creek to and including an anchorage basin of the same depth 100 feet wide and 400 feet long at Rhodes Point; channel 6 feet deep and 50 feet wide from that depth in Big Thorofare River to Tylerton; channel 6 feet deep and 50 feet wide from Rhodes Point to Tylerton. Mean range of tide is 1.7 feet. On January 22, 1982, the Chief of Engineers under authority of Section 107 of the 1960 River and Harbor Act, as amended, authorized a channel 6 feet deep and 50 feet wide a distance of about one mile from the anchorage basin at Rhodes Point through Sheep Pen Gut to deep water in the Chesapeake Bay. Local cooperation. Fully complied with for work authorized by the Chief of Engineers January 22, 1982. See section 19 of 1982 Annual Report for requirement details. Terminal facilities. There are numerous pile-andtimber wharves along waterfronts at Rhodes Point and Tylerton. Facilities are privately owned, but open to the 4-8 BALTIMORE, MD DISTRICT public without charge when not in use by the owners, and are adequate for existing commerce. Sufficient space for construction of additional facilities is available, if required. Operations and results during fiscal year. Maintenance: Engineering and design work was accomplished in connection with proposed maintenance dredging. 18. ST. GEORGE CREEK, MD Location. The project is on a tributary of the Potomac River located about 90 miles south of Baltimore, 60 miles southeast of Washington, DC, and approximately 10 miles from the mouth of the Potomac River. (See National Ocean Survey Chart No. 12233.) Existing project. On April 29, 1983 the Chief of Engineers under authority of Section 107 of the 1960 River and Harbor Act, as amended, authorized a channel 1,500 feet in length, 60 feet wide and 7 feet deep at mean low water, from St. George Creek Island Bridge to deep water in the Potomac River. Local cooperation. Requirements are described in full on page 4-9 of Fiscal Year 1983 Annual Report. Terminal facilities. Many of the shoreline community residents are commercial watermen and seafood processing establishments are located on St. George Island. Recreational boating is abundant and St. Mary's County owns a public boat ramp on the north side of St. George Island. The Harry Lundeberg School of Seamanship, located at St. George Harbor is used to train individuals in the basic seamanship skills required by the United States Maritime Industry. Operations and results during fiscal year. New Work: Construction was physically completed on May 22, 1984, but liquidated damages are still being assessed. 19. ST. PATRICKS CREEK, MD Location. St. Patricks Creek in St. Marys County, MD is a small tidal stream 1 '/2 miles long which flows in a southeasterly direction and enters the west side of St. Clement Bay at its junction with the Potomac River. The creek is 33 miles upstream from the Chesapeake Bay and 83 miles downstream from Washington, DC (See U. S. Coast and Geodetic Survey Chart No. 558). Existing project. Provides for an entrance channel 7 feet deep, 60 feet wide, and approximately 2,450 feet long from deep water in St. Clement Bay to deep water within the creek. The plane of reference is mean low water. The tidal ranges are: mean, 1.9 feet; irregular, 2.5 feet; and extreme, approximately 7 feet. The cost to the Federal Government for new work for the completed project was $15,752, exclusive of $1,000 contributed by local interests. The latest (1950) approved estimate for the annual cost of maintenance is $4,800. Local cooperation. The existing project was approved subject to the provisions that (a) local interests contribute $1,000 in cash toward the cost of new work; (b) hold and save the United States free from any damage resulting from construction and maintenance of the improvement; (c) furnish releases from damages to oyster grounds; (d) furnish free of cost to the United States suitable spoil-disposal areas for new work and subsequent maintenance, when and as required; and (e) agree to provide a suitable public wharf with access road open to all on equal terms. Items (a) through (d) have been fully complied with. Local interests have initiated action to complete item (e). Terminal facilities. There are 41 small wharves and stagings located in the creek. All are privately owned, but one is open to the public. There is also one marine railway in the creek. The terminal facilities are considered adequate for present commerce. Operations and results during fiscal year. Maintenance: Engineering and design work was accomplished in connection with proposed maintenance dredging. 20. SUSQUEHANNA RIVER ABOVE AND BELOW HAVRE DE GRACE, MD Location. The Susquehanna River flows generally southward 400 miles to the head of Chesapeake Bay at Havre de Grace, MD, 8 miles north of the entrance to the Chesapeake and Delaware Canal, and 45 miles northeast of Baltimore, MD. Existing project. A channel 200 feet wide and 15 feet deep from that depth in Chesapeake Bay to Havre de Grace, for removal of a shoal opposite Garrett Island to a depth of 8 feet, and for maintenance of an existing boat basin 400 feet long, 380 feet wide, and 7 feet deep adjacent to the city park at Havre de Grace and the 75 foot wide approach channel to the same depth. Local cooperation. Fully complied with for the active portion of the project. Terminal facilities. A concrete bulkhead 500 feet long along north side of the harbor and a timber breakwater about 1,000 feet along the south side. There are no wharves within limits of the desired improvements. Yachts are charged a nominal fee for use of mooring stalls in the harbor. Space for construction of additional stalls at convenient locations is limited. Commercial wharves at Havre de Grace are on Susquehanna River upstream from Concord Point. Wharves are privately owned, but open to the public for transaction of business with the owners. Operations and results during fiscal year. Maintenance: A maintenance dredging contract was completed in July 1985. A total of 114,000 cubic yards of material were removed. 21. TRED AVON RIVER, MD Location. This stream, formerly called Treadhaven Creek, rises in Talbot County, MD, flows southerly and empties into Choptank River 10 miles above its mouth. It is about 10 miles long and is a tidal estuary with very little natural flow. Draining area is 36 square miles. (See Coast and Geodetic Survey Chart 78.) 4-9 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Previous project. For details see page 397 of Annual Report for 1951. Existing project. Provides for a channel 12 feet deep and 150 feet wide in Tred Avon River from that depth in river near Peach Blossom Creek to Easton Point, thence a channel of same depth and width and about 1,400 feet long in the North Fork, thence a channel of same width and 8 feet deep and about 700 feet deep long with a turning basin of same depth at upper end. Project also provides for a turning basin in South Fork 12 feet deep and 250 feet wide and 600 feet long on east side of main channel at Easton Point Section included in project is about 2 miles long, and its lower end is about 7.5 miles above mouth. Mean range of tide is about 2 feet. Local cooperation. Requirements are described in full on page 4-11 of Fiscal Year 1979 Annual Report. Terminal facilities. Five large terminals for receiving and distributing petroleum products, and a marina with stalls and ships, marine railway, a launching ramp, and a 6-ton travel-lift at Easton Point. These facilities are in good condition. Operations and results during fiscal year. Maintenance: Engineering and design work was completed in connection with proposed maintenance dredging. Work was deferred because locals were unable to provide the required contributed funds. 22. TWITCH COVE AND BIG THOROFARE, MD Location. A tidal waterway about 4 miles long traversing Smith Island, MD, southeasterly from Chesapeake Bay on the west to Tangier Sound on the east. (See Coast and Geodetic Survey Chart 1224.) Existing project. A channel 7 feet deep at mean low water and 60 feet wide from Twitch Cove on Tangier Sound through Big Thorofare, thence through canal at Ewell, MD, thence through Levering Creek and Big Thorofare to vicinity of Swan Point, thence of same depth and 100 feet wide through offshore bar to deep water in Chesapeake Bay, with twin stone jetties at entrance, north jetty is about 2,080 feet long, and south jetty about 1,800 feet long; and anchorage basin 7 feet deep, 100 feet wide, and 700 feet long connecting with west side of existing project channel at Ewell; extension of existing project channel in Levering Creek, 6 feet deep, 60 feet wide, and 1,000 feet long; and a channel 4 feet deep and 25 feet wide around point between Big Thorofare and Tylers River. Mean range of tide is 1.7 feet, and extreme tidal range is 3 feet. Federal cost of new work for completed project was $193,175. Local cooperation. Fully complied with, except that local interests are to furnish spoil disposal areas for future maintenance as needed. Terminal facilities. Numerous privately owned pileand- timber wharves and bulkheads at Ewell are open to the Public for business transactions with the owners. A county wharf is also at west end of town. Five crab houses are on Levering Creek, and one oyster house on project waterway west of Town of Ewell. Operations and results during fiscal year. Maintenance: Engineering and design work was completed in connection with proposed maintenance dredging. 23. UPPER THOROFARE, DEAL ISLAND, MD Location. Natural waterway lying between Deal Island and mainland of Somerset County, Md., on eastern shore of Chesapeake Bay. (See Coast and Geodetic Survey Chart 1224.) Previous project. For details see page 277 of Annual Report for 1962. Existing project. Entrance channel from Tangier Sound 9 feet deep and 100 feet wide, thence of irregular width to and along south shore of Thorofare, protected by two stone breakwaters at entrance, north breakwater is about 410 feet long and South breakwater about 310 feet long, with a turning basin at inner end 9 feet deep on south side of channel to within 50 feet of bulkhead along south shore, an anchorage area 6 feet deep and 150 feet wide extending across waterway parallel to highway bridge to within 50 feet of bulkhead on south shore, and an anchorage area 650 feet long, 300 feet wide, and 9 feet deep on north side of channel between breakwater and 6-foot anchorage. Mean range of tide is about 2 feet. Cost of new work for completed project was $62,116. Local cooperation. Fully complied with. Terminal facilities. A small packing-house wharf on shore of Tangier Sound south of project channel: two small packing houses along approach channel at which seafood is landed; and a public wharf at turning basin with a suitable road connecting it with the road system. Operations and results during fiscal year. Maintenance: Engineering and design was accomplished in connection with proposed maintenance dredging. 24. WASHINGTON HARBOR, DC Location. Within District of Columbia at junction of Anacostia River with Potomac River which flows southeasterly 108 miles to Chesapeake Bay. It is southerly 202 miles by water from Baltimore, MD, and northerly 195 miles from Norfolk, VA. (See Coast and Geodetic Survey Chart 12289.) Existing projects. A combination and extension of latest projects for Potomac River at Washington, DC, and Anacostia River, DC. The Washington Harbor project provides for a channel in the Potomac River from Giesboro Point to Key Bridge, a second channel from Giesboro Point to the end of Washington Channel, and a third channel from the mouth of the Anacostia River to the foot of 15th Street, SE, with turning basins opposite the Naval Weapons Plant (800 feet wide and 2,400 feet long) and at the head of the Anacostia Channel (400 feet square). Channel dimensions are 24 feet deep and 400 feet wide except upstream from Anacostia Bridge where the width is reduced to 200 feet and from Giesboro Point to a point 3,000 feet downstream of Arlington Memorial 4-10 BALTIMORE, MD DISTRICT Bridge and above Easby Point where channel dimensions are 20 feet deep and 200 feet wide. Channel lengths including turning basins are: Virginia Channel, 5,000 feet; Washington Channel, 10,000 feet; and Anacostia River, 15,000 feet; and operation and maintenance of the inlet gates and lock and the outlet gates of the Tidal Basin constructed under a previous project to flush Washington Channel. Plane of reference is low-water datum which is 0.35 foot below mean low tide as observed from 1932 to 1942. Tidal ranges are: mean, 2.9 feet; irregular, 4.5 feet; and extreme, 10.7 feet. Federal cost of new work for the completed project was $162,006. Local cooperation. None required. Terminal facilities. There are four wharves generally of bulkhead type on Virginia Channel that are privately owned and not open to the public except by special arrangement. On Washington Channel there are four piers under jurisdiction of District of Columbia, two of which are open to the public and one open to the public by special arrangement. In Anacostia River there are four privately owned piers and eight governmental piers and slips. None of the piers are open to the public except by special arrangement. Terminal facilities are considered adequate for existing commerce. Operations and results during fiscal year. Maintenance: A contract for maintenance dredging was completed in April 1985. A total of 25,000 cubic yards of material were removed. 25. WICOMICO RIVER, MD Location. Wicomico River has its source in northern part of Wicomico County, MD, and flows generally southwardly emptying into Monie Bay, a tributary of Tangier Sound on the east side of Chesapeake Bay about 85 miles southeast of Baltimore. Webster Cove is site of improved small-boat harbor on southeast bank of Wicomico River about 3 miles above the mouth. (See Coast and Geodetic Survey Charts 567 and 1224.) Existing project. Channel 14 feet deep and 150 feet wide from Chesapeake Bay to Salisbury, section included in project is 37 miles long, including about 12 miles from mouth of river to Chesapeake Bay; 14 feet deep in channels and turning basins in north and south prongs with channel widths of 100 feet, and a channel 6 feet deep and 60 feet wide extending from 6-foot contour in Wicomico River to and including a basin in Webster Cove of same depth, 100 feet wide and 400 feet long; and extension of basin 200 feet long and 100 feet wide on each side. Plane of reference is mean low water. Mean range of tide is about 3 feet and extreme tidal range is 4.4 feet. Cost of new work for completed project was $421,609, exclusive of amounts expended on previous project. Local cooperation. Fully complied with, except that local interests are to furnish spoil disposal areas for future maintenance as needed and hold the United States free from such damages as may occur to public or leased oyster beds. Terminal facilities. Present waterfront at Salisbury consists of pile-and-timber bulkheads with earthfills. Some wharves have warehouses and factories with mechanical freight-handling facilities and rail sidings. All terminals are privately owned. A shipyard, with two marine railways with capacities of 1,200 and 500 tons, respectively, is on right bank of river below prongs. Areas for development of new terminals on north prong are limited. Areas for considerable expansion of terminal facilities are available on main river. There is a pileand- timber wharf about 4 miles above mouth of river at Mount Vernon. A wharf of similar construction is at White Haven. There is a county wharf at head of basin in Webster Cove, a pile-and-timber pier at oyster house on southwest side of basin, a T-shaped pile-and-timber pier at cafe on southwest side of basin and several small timber piers on walkways that local interests constructed around the basin. Fueling facilities are available at the T-shaped pier. Sufficient areas are available for construction of additional facilities when required. Operations and results during fiscal year. Maintenance: Maintenance dredging of the channel near Webster Cove was completed in July 1985. A total of 110,000 cubic yards of material were removed. 26. RECONNAISSANCE AND CONDITION SURVEYS (See Table 4-H at end of chapter.) 27. NAVIGATION WORK UNDER SPECIAL AUTHORIZATION Navigation activities pursuant to Section 107, Public Law 86-645 (preauthorization). Fiscal year costs were $86,196 for Hull Creek, VA; $70,420 for Lower Thorofare, MD; and $10,943 for Coan River, VA. Mitigation of Shore Damages pursuant to Sec. 111 of Public Law 90-483 (preauthorization). Fiscal year costs were $66,918 for Herring Creek, Tall Timbers, MD. Aquatic Plant Control pursuant to Sec. 302 of Public Law 89-298, as amended (preauthorization). Fiscal year costs were $694,703 for Potomac River (Hydrilla), DC. Beach Erosion Control 28. COLONIAL BEACH, VA Location. Colonial Beach, Westmoreland County, VA, is located on the right bank of the Potomac River 40 miles upstream from its mouth at Chesapeake Bay and 69 miles downstream from Washington, DC. (See U.S. Coast and Geodetic Survey Chart No. 558.) Existing project. On May 29, 1980, the Chief of Engineers under authority of Section 103 of the 1960 River and Harbor Act, as amended, authorized construction of the following work: Extending and widening the existing Central Beach area downstream from Hawthorne Street southward to provide an additional beach area of 4-11 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 about 107,200 square feet, stablizing with vegetation about 200 feet of the bank behind the beachfill and constructing four segments of offshore breakwater with estimated lengths of 200 feet each, to stablize the beachfill area; and extending and widening the existing beach at Castlewood Park to provide an additional beach area of about 59,300 square feet; constructing three segments of offshore breakwater with estimated lengths of 200 feet each for two of the segments and 300 feet for the third segment; removing debris in the beachfill area; and constructing a 100-foot long terminal groin at the southern end of the Castlewood Park beachfill. The estimated cost of this work is $1,910,977 of which $1,000,000 is Federal cost and $910,977 is required local cash contribution. The $1,910,977 includes $992,000 for periodic beach nourishment as needed, after FY 1983. Local cooperation. Among other requirements, local interests must provide all lands, easements, and rights-ofway and relocations required for construction including periodic nourishment and provide a cash contribution equal to 50 percent of the final project construction cost (excluding lands and relocations). Operations and results during fiscal year. New Work: Beach nourishment was accomplished in FY 1985 at a total cost of $25,000 of which $12,500 was federally funded. 29. BEACH EROSION CONTROL WORK UNDER SPECIAL AUTHORIZATION Beach Erosion Control pursuant to Sec. 103 of Public Law 727, as amended (preauthorization). Fiscal year costs were $11,000 for Rocky Point Beach, MD, and $7,500 for Isle of Wight Bay, Ocean City, MD. Flood Control 30. BLACK WALNUT POINT, MD Location. The southern end of Tilghman Island, about 17 miles south of the William P. Lane JR. Memorial (Chesapeake Bay) Bridge eastern shore landing. (See National Ocean Survey Chart Numbers 12266 and 12263.) Existing project. On December 22, 1982 the Chief of Engineers under authority of Section 14 of the Flood Control Act of 1946, as amended, authorized construction for 375 linear feet of 43-foot wide stone revetment to stabilize existing shorebank. Local cooperation. Requirements are described in full on page 4-12 of Fiscal Year 1983 Annual Report. Operations and results during fiscal year. New Work: Construction was physically completed May 4, 1984 and project was fiscally closed early FY 1985. 31. BLOOMINGTON LAKE, MD & WV Location. Project is located on the North Branch Potomac River on the state line between Garrett County, MD, and Mineral County, WV. The damsite is located approximately 7.9 miles upstream from the confluence with Savage River at Bloomington, MD. It is also about 5 air miles southwest of the tritowns of Luke and Westernport, MD, and Piedmont, WV. (See Geological Survey quadrangle sheets, "Kitzmiller" and "Westernport," MD.) Existing project. The improvement consists of a rolled earth and rock fill dam with an impervious core and an 800-foot long dike on the left bank. Top of dam is 296 feet above streambed with a total length of 2.130 feet. When filled to spillway crest, the reservoir will extend about 6.6 miles upstream and inundate 965 acres. Flood control storage of 36,200 acre-feet is provided. Storage available for low flow augmentation for water supply and water quality improvement is 92,000 acre-feet. The reservoir controls a drainage area of 263 square miles. Recreation facilities are provided for picnicking, camping and boating. Estimated cost (October 1983) of new work is $174,480,300 of which $57,927,000 is required non-federal reimbursement. Local cooperation. See page 4-15 of the 1977 Annual Report for requirements. A water supply contract between the Federal Government and the Washington Suburban Sanitary Commission in concert with the Fairfax County Water Authority, VA, and the District of Columbia has been executed for repayment of all water supply costs. The first of 50 annual payments began in July 1981. Federally approved water quality standards put into effect by Maryland, Virginia, West Virginia, and the District of Columbia are considered satisfactory assurances of intent to control pollution. Satisfactory assurances have been received from Maryland, West Virginia, and Virginia that they will protect downstream channels from encroachment that would adversely affect operation of the project. Operations and results during fiscal year. New Work: The project became operational for water supply, flood control, and for water quality control in July 1981. Construction for improving the spillway flow was completed. Maintenance: Normal operation and maintenance of the project continued. 32. CUMBERLAND, MD, AND RIDGELEY, WV Location. On North Branch of Potomac River, 21 miles upstream from its junction with the South Branch of the Potomac River and 197 miles upstream from Washington, DC. (See Geological Survey Quadrangles, Frostburg and Flintstone, MD, WV, and PA.) Existing project. Channel improvements of North Branch of Potomac River from the Western Maryland Railway bridge in South Cumberland upstream to the mouth of Wills Creek, with levees and fill along the left bank and levees along the right bank from downstream corporate limits of Ridgeley, WV, to a point about 150 feet above Johnson Street Bridge; channel improvements along Wills Creek from its mouth upstream to a point 4-12 BALTIMORE, MD DISTRICT in the Narrows about 500 feet upstream from the highway bridge on U.S. Highway 40; levee and floodwall in West Cumberland, MD, on the left bank of the North Branch of the Potomac River from the mouth of Wills Creek upstream to Kelly Boulevard; levee and floodwall in Ridgeley, WV, on the right bank of the North Branch of the Potomac River from Carpenter Avenue upstream to Patapsco Street near the upstream corporate limits of Ridgeley, WV; interior drainage facilities in Cumberland and West Cumberland, MD, and Ridgeley, WV; removal of the Chesapeake and Ohio Canal dam and construction of a new industrial dam on the North Branch of the Potomac River immediately above mouth of Wills Creek; and alteration and reconstruction of highway and railroad bridges. Federal costs of new work for the completed project were $15,633,970, which includes $49,998 emergency relief funds and is exclusive of $197,513 public works acceleration funds. Estimated cost to local interests is $2,900,000 of which $1,402,001 is contributed funds and $1,497,999 is for lands and damages. Local cooperation. Fully complied with. Operations and results during fiscal year. Maintenance: Removal of gravel deposits, grass cutting of areas channelward of levees, and removal of brush and debris from channel were accomplished as required in channel area. 33. LACKAWANNA RIVER BASIN, PA Flood Control Act of 1962 authorized construction of Aylesworth Creek Lake, Fall Brook Lake, and local protection works on Lackawanna River at Scranton, PA, substantially as recommended by the Chief of Engineers (S. Doc. 141, 87th Cong., 2d sess). The Basin includes an area of 346 square miles in northeastern Pennsylvania. 33A. AYLESWORTH CREEK LAKE, PA Location. Project is located in Lackawanna County on Aylesworth Creek about one mile above its confluence with the Lackawanna River, near the community of East Jermyn, PA. Existing project. Provides for an earthfill dam with a maximum height of 90 feet above streambed and a top length of 1,200 feet. The spillway located adjacent to the left abutment is an open cut channel 80 feet wide with a concrete sill. The outlet works consist of a 3-foot diameter uncontrolled conduit. Project controls a drainage area of 6.2 square miles and provide flood control storage of 1,700 acre-feet equivalent to 5.1 inches of runoff from the drainage areas. The lake will extend about 4,600 feet and inundate 87 acres when filled to spillway crest. Recreation facilities constructed by local interest include a bathing beach, bathhouse, and picnic area. Federal cost of new work was $2,268,200 of which $2,153,559 was for construction and $114,641 for lands and damages. In addition $52,200 Federal and $52,200 non-Federal funds were expended for construction of bathhouse facilities under the recreation facilities for completed projects program. Local cooperation. None required. The Aylesworth Creek Reservoir Park Authority, representing the Boroughs of Archbald and Jermyn, operate and maintain limited day use facilities including a small beach. In September 1978 a cost sharing agreement for construction of bathhouse facilities was signed. The cost for the facilities which were completed in July 1979 was $104,400 of which $52,200 was Federal and $52,200 was non- Federal. Operations and results during fiscal year. Maintenance: Normal operation and maintenance of the project continued. 34. RAYSTOWN LAKE, RAYSTOWN BRANCH, JUNIATA RIVER, PA Location. Damsite is on Raystown Branch, about 5.5 miles upstream from its confluence with Juniata River. Project is about 10 miles south of Huntingdon, PA. (See Geological Survey Quadrangle sheets, Huntingdon, Mt. Union, Broad Top and Everett, PA.) Existing project. The rock and earthfill dam rises 225 feet above streambed with a gated concrete spillway and auxiliary spillway in the right abutment. The reservoir has a storage capacity of 762,000 acre-feet, of which 248,000 acre-feet are for flood control, 476,000 acre-feet for recreation and water quality control, and the balance for sediment reserve. At full flood control pool elevation, the reservoir would inundate 10,800 acres and extend 34 miles upstream. Recreation facilities are provided for boating, fishing, camping, swimming, hunting, and picnicking. Federal cost for new work was $77,408,700 of which $46,120,931 was for construction and $31,287,769 was for lands and damages including relocations. Local cooperation. None required. Operations and results during fiscal year. Maintenance: Normal operation and maintenance of the project continued. 35. SOUTHERN NEW YORK FLOOD CONTROL PROJECTS Authorized plan provides for construction of reservoirs and related flood control works for protection of towns in New York and Pennsylvania. The improvements are located in the upper watershed of the Susquehanna River to and including the Chemung River. 35A. ADDISON, NY Location. At confluence of Tuscaroroa Creek and Canisteo River in the City of Addison, NY. (See Geological Survey map for Addison, NY.) Existing project. Provides for construction of about 3,100 feet of earth levee and 700 feet of concrete floodwall on the right bank of the Canisteo River, extending from high ground on Steuben Street near the Baltimore & Ohio Railroad to the mouth of Tuscarora Creek; removal of existing dam, mill, and raceway from the 4-13 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 channel; construction of about 2,200 feet of earth levee on the left bank of Tuscarora Creek, extending from Tuscarora Street to Canisteo River; construction of 4,600 feet of earth levee on the right bank of Tuscarora Creek, extending from high ground at the southwest edge of the village to high ground at the southeast edge of the village; and appurtenant drainage structures. Local cooperation. Fully complied with. Operations and results during fiscal year. Maintenance: Normal operation and maintenance of the project continued. 35B. ALMOND LAKE, NY Location. Dam is located two miles upstream from Hornell, NY, on Canacadea Creek, a tributary of the Canisteo River. (See Geological Survey map for Hornell, NY.) Existing project. The dam is an earthfill structure, 1,260 feet long rising 90 feet above the streambed, with a concrete spillway and a gated outlet conduit in the left abutment. The outlet works consist of three 5-foot by 10-foot service gates and three emergency gates of the same size. The reservoir has a storage capacity of 14,640 acre-feet at spillway crest. The project controls a draining area of 56 square miles, 36 percent of the watershed of the Canisteo River upstream from Hornell, NY. Recreation facilities include a boat-launching ramp and dock, bathing beach, picnic area, and tent and trailer camping area. Local cooperation. None required. Local interests have developed recreational facilities at the lake in conjunction with the Federal Government. These facilities are operated and maintained by the Steuben County Board of Supervisors. Operations and results during fiscal year. Maintenance: Normal operation and maintenance of project continued. A debris removal contract was let and a total of 6,000 cubic yards of material was removed. 35C. ARKPORT DAM, NY Location. Dam is located five miles upstream from Hornell, NY, on the Canisteo River, a tributary of the Chemung River which flows into the Susquehanna River. (See Geological Survey map for Arkport, NY.) Existing project. The dam is an earthfill structure, 1,200 feet long, exclusive of spillway, rises 113 feet above the streambed, with a concrete spillway and an ungated outlet in the right abutment. The outlet structure consists of an 8-foot diameter reinforced concrete lined conduit, 660 feet long. A cast iron nozzle is placed in the lower end of the conduit, reducing the outlet size to 4 feet 4 inches. The reservoir has a storage capacity of 7,950 acre-feet at spillway crest. The project controls a drainage area of 31 square miles, 20 percent of the watershed of the Canisteo River upstream from Hornell. Local cooperation. None required. Operations and results during fiscal year. Maintenance: Normal operation and maintenance of the project continued. 35D. AVOCA, NY Location. On the Cohocton River at the Village of Avoca, NY, about 30 miles upstream from the confluence of the Cohocton and Chemung Rivers. (See Geological Survey map for Avoca, NY.) Existing project. Provides for improvement and realinement of about 8,300 feet of Cohocton River channel, extending from above the Erie Railroad to below the junction of Main Street and U.S. Highway 15; construction of about 8,500 feet of earth levee on left bank of the Cohocton River, extending from high ground above Alexander Avenue to about 1,300 feet below the junction of Main Street and U.S. Highway 15; and 4,500 feet of earth levee on the right bank of Salmon Creek, extending from high ground above Alexander Avenue to the Erie Railroad; a new highway bridge for U.S. Highway 15 over Cohocton River, raising of the Erie Railroad bridge 4 feet; and appurtenant drainage structures. Local cooperation. Fully complied with. Operations and results during fiscal year. Maintenance: Normal operation and maintenance of the project continued. 35E. BINGHAMTON, NY Location. At the confluence of the Chenango and Susquehanna Rivers in the City of Binghamton, NY. (See Geological Survey map for Binghamton, NY.) Existing project. Provides for construction of earth levees, concrete floodwalls, and appurtenant drainage structures, consisting of about 850 feet of channel excavation and about 1,375 feet of earth levee along Phelps Creek, Town of Port Dickinson; new concrete wall on the right bank of the Chenango River, extending downstream from high ground near the city limits to an existing floodwall below DeForest Street, a distance of about 520 feet; about 150 feet of concrete wall just below Cutler Dam; about 180 feet of concrete wall at the pumphouse near McDonald Avenue; raising existing earth levees on the right bank of Chenango River, extending from Cutler Dam downstream for about 1,220 feet; about 2,915 feet of earth levee on the left bank of Chenango River north of the city limits in the Village of Port Dickinson, extending from Church Street to high ground just north of the city line; about 3,900 feet of earth levee on the left bank of Chenango River, extending from DeForest Street to Cutler Dam; new concrete floodwalls and riverbank revetment for about 5,570 feet extending on the left bank of Chenango River from Cutler Dam to the junction with the Susquehanna River; about 540 feet of new concrete floodwall and raising about 1,085 feet of concrete floodwall on the right bank of the Susquehanna River, extending from the Delaware, Lackawanna & Western Railroad downstream to Tompkins Street Bridge; about 1,940 feet of earth levee; about 1,940 feet of concrete floodwall and 4-14 BALTIMORE, MD DISTRICT capping about 125 feet of concrete floodwall, on the right bank of the Susquehanna River from Stuyvesent Street to mouth of Chenango River; about 8,380 feet of earth levee, about 2,180 feet of new concrete floodwall and raising about 125 feet of existing floodwall on the left bank of the Susquehanna River extending from Pierce Creek to high ground at State Highway 17; a debris dam and flume between Corbett and Hotchkiss Streets and a concrete pressure conduit, 1,060 feet long to carry flow of Park Creek from Vestal Avenue to the Susquehanna River; about 665 feet of levee extending from the Erie Railroad to high ground along the right bank of Chamberlain Creek near the mouth; closure structures at Erie Railroad and at Court Street; a weir, a drop structure, and about 1,800 feet of earth levee, about 2,235 feet of channel excavation, about 645 feet of channel paving and raising, about 470 feet of existing concrete floodwall, and about 200 feet of new concrete floodwall for improvement of Pierce Creek from its mouth to about 1,000 feet above Conklin Avenue; and appurtenant drainage structures. Improvement, supplemented by authorized flood control dams above the area, will provide protection for the City of Binghamton against a flood discharge about 20 percent greater than the maximum flood of record, which occurred in July 1935 on the Chenango River and in March 1936 on the Susquehanna River. Local cooperation. Fully complied with. Operations and results during fiscal year. Maintenance: Normal operation and maintenance of the project continued. 35F. CANISTEO, NY Location. On Purdy and Bennetts Creeks in the Town of Canisteo, NY, situated along the south side of the Canisteo River, at the confluence of Bennetts Creek and the Canisteo River. (See Geological Survey map for Canisteo, NY.) Existing project. Provides for construction of about 8,000 feet of earth levees on the right bank of the Canisteo River, extending from high ground 1,570 feet west of State Highway Route 21 above the Town to a point at the intersection of Ordway Lane and East Main Street; about 7,400 feet of earth levee on the left bank of Purdy and Bennetts Creeks, extending from the Main Street Bridge to high ground above Greenwood Street; 1,000 feet of earth levee on the right bank of Bennetts Creek extending upstream from the Main Street Bridge; a concrete check dam with wing levees from Greenwood Street; a new highway bridge at Greenwood Street; alterations to existing timber check dams in Bennetts Creek; channel excavation in Bennetts and Purdy Creeks; and appurtenant drainage structures. Local cooperation. Fully complied with. Operations and results during fiscal year. Maintenance: Normal operation and maintenance of the project continued. 35G. CORNING, NY Location. On the Chemung River in the City of Corning, NY, about 44 miles upstream from the confluence of Chemung River and North Branch of Susquehanna River. (See Geological Survey map for Corning, NY.) Existing project. Flood protection for this community was originally authorized by the Flood Control Act of 1936. Plan of improvement provides for construction of a pumping station, earth levees, and concrete floodwalls, consisting of: about 4,300 feet of earth levee, enlargement of about 8,610 feet of existing earth levee and about 3,100 feet of concrete floodwall on the right bank of the Chemung River, extending from the Erie Railroad Bridge to high ground at Park Avenue below the city; about 200 feet of concrete floodwalls; about 2,500 feet of earth levees and enlargement of about 11,500 feet of existing earth levee on the left bank of the Chemung and Cohocton Rivers, extending from the Erie Railroad Bridge over Cohocton River to the mouth of Post Creek; about 2,500 feet of earth levee and enlargement of about 4,700 feet of existing earth levee on the right bank of Post Creek from its mouth to Watkins Street; realignment of about 3,000 feet of channel, about 8,800 feet of earth levee, about 3,000 feet of channel excavation, a pressure conduit about 400 feet long, a drop structure and a weir for improvement of Cutler Creek, extending from its mouth to high ground at Deckertown Road and Hornby Road; and appurtenant drainage structures. Flood protection on Monkey Run was authorized by the Flood Control Act of 1950. Plan of improvement provides for construction of 2,010 feet of open flume, 2,320 feet of pressure conduit storm sewers, and appurtenant facilities between the existing improved channel above Sixth Street and the Chemung River at a point immediately east of Pine Street East. Modified improvement will provide protection for the City of Corning against a flood discharge in Chemung River approximately equal to the maximum flood of record, which occurred in May 1945, and on tributary streams against floods of greater magnitude than known to date. Local cooperation. Fully complied with. Operations and results during fiscal year. Maintenance: Normal operaton and maintenance of the project continued. 35H. EAST SIDNEY LAKE, NY Location. Dam is located near East Sidney, NY, on the Ouleout Creek, about five miles above the confluence of the creek with the Susquehanna River. (See Geological Survey map for Franklin, NY.) Existing project. The dam is an earthfill and concrete structure, 2,010 feet long, including spillway, rises 130 feet above the streambed and consists of a concrete gravity-type section with a compacted earth-dike section at the right abutment. The outlet works consist of five rectangular conduits each 3.5 feet by 5.85 feet and 105 4-15 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 feet long. The reservoir has a storage capacity of 33,500 acre-feet at spillway crest. The project controls a drainage area of 102 square miles which is 93 percent of the Ouleout Creek drainage area, and 5 percent of the watershed of the Susquehanna River upstream from Binghamton, NY, exclusive of the separately controlled Chenango River. Recreation facilities include a bathing beach, picnic and camping areas, and boat-launching and docking facilities. Local cooperation. None required. The Town of Sidney, NY, cooperated in the development of recreation facilities and operates and maintains all the facilities with the exception of the recreational pool, which is the responsibility of the Federal Government. Operations and results during fiscal year. Maintenance: Normal operation and maintenance of the project continued. 35I. ELMIRA, NY Location. On the Chemung River in the City of Elmira, NY, about 27 miles upstream from the confluence of the Chemung River and North Branch of Susquehanna River. (See Geological Survey map for Elmira, NY.) Existing project. Provides for about 17,700 feet of earth levees, and about 4,100 feet of concrete floodwall on the right bank of the Chemung River, extending from South Hoffman Street to a point below the city near the upper end of Big Island; about 12,100 feet of earth levee and about 6,300 feet of concrete wall on the left bank of the Chemung River extending from Durland Avenue to the Delaware, Lackawanna & Western Railroad at the mouth of Newton Creek; about 10,000 feet of earth levee on right bank of Newton Creek, extending from about the intersection of Delaware, Lackawanna & Western Railroad and east Church Street to high ground near intersection of Sullivan and Warren Streets; about 4,300 feet of earth levee on the right bank of Divan Creek; about 2,000 feet of concrete conduit enclosing Hoffman Brook from West Second Street to the Chemung River; clearing islands and riverbanks of trees and brush for about 3.5 miles in the Chemung River; about 14,300 feet of earth levee on the left bank of Seely Creek, extending from the Erie Railroad to high ground approximately 1,000 feet northwest of the intersection of South Broadway and Pennsylvania Avenue; a pumping plant for disposal of interior drainage; an interceptor sewer about 6,000 feet long varying in size from 48 to 96 inches in diameter; and appurtenant structures. Local cooperation. Fully complied with. Operations and results during fiscal year. Maintenance: Normal operation and maintenance of the project continued. 35J. HORNELL, NY Location. On the Canisteo River in the City of Hornell, NY, about 42 miles upstream from the confluence of the Canisteo and Tioga Rivers. (See Geological Survey map for Canisteo, NY.) Existing project. Provides for channel realignment and earth levees, concrete floodwalls, and check dams consisting of: realignment of about 4,600 feet of the Canisteo River channel, and about 5,800 feet of earth levee on its right bank, extending from Seneca Street upstream to the junction of the Pittsburgh, Shawmut & Northern Railroad and the Erie Railroad; about 4,500 feet of earth levee, extending on both sides of Seneca Street from the Canisteo River to Wrightman Avenue and the junction of Cleveland Avenue and Bethesda Drive; about 7,200 feet of earth levee, about 2,500 feet of concrete floodwall, and raising about 1,500 feet of existing concrete floodwall, on the right bank of the Canisteo River, and about 12,000 feet of channel improvement, extending from Seneca Street to the Erie Railroad; about 2,500 feet of earth levee, about 2,100 feet of concrete floodwall on the left bank of the Canisteo River extending from a point opposite Walnut Street to the Erie Railroad; a ring-earth levee about 2,800 feet long around the sewage-disposal plant on the left bank of the Canisteo River; about 4,500 feet of realignment and improvement of the Canisteo River Channel with about 4,500 feet of earth levee on its right bank extending from Cedar Street downstream to about 1,400 feet above East Avenue; about 2,400 feet of channel paving, 1,400 feet of earth levee, raising about 1,900 feet of concrete floodwall, and construction of one check dam on Canacadea Creek; about 1,600 feet of channel paving and construction of three check dams on Chauncey Run with about 300 feet of new wall and about 300 feet of capping; a weir, a check dam, 3,030 feet of channel paving, 4,800 feet of floodwalls and levees, and related work on existing walls, on Crosby Creek; removal of 6 bridges, erection of 4 bridges, miscellaneous bridge structures, and 3 drop structures; and appurtenant drainage structures and small stream control works. Improvement, supplemented by Arkport and Almond Reservoirs above the area, provides protection for the City of Hornell against a flood discharge approximately double the maximum flood of record, which occurred in July 1935. Local cooperation. Fully complied with. Operations and results during fiscal year. Maintenance: Normal operation and maintenance of the project continued. 35K. LISLE, NY Location. On the Tioughnioga River in the Village of Lisle, NY, about 12 miles upstream from the confluence of the Tioughnioga and Chenango Rivers. (See Geological Survey map for Lisle, NY.) Existing project. Provides for channel realignment and construction of earth levees and concrete floodwalls, consisting of: relocation of about 3,000 feet of Dudley Creek Channel, extending from 1,200 feet west of the intersection of Cortland and Main Streets to the confluence with Tioughnioga River, realignment of some 5,700 feet of Tioughnioga River Channel east of the Village; about 4,150 feet of earth levee and 970 feet of concrete wall on the right bank of Dudley Creek and Tioughnioga River; realignment of some 5,700 feet of Tioughnioga Street to 4-16 BALTIMORE, MD DISTRICT the railroad crossing on River Street; raising about 1,860 feet of the Delaware, Lackawanna & Western single track railroad over the levee; relocation of about 1,600 feet of Cortland Street; a new bridge over relocated Dudley Creek; and appurtenant drainage structures. Local cooperation. Fully complied with. Operations and results during fiscal year. Maintenance: Normal operation and maintenance of the project continued. 35L. OXFORD, NY Location. On the Chenango River in the Village of Oxford, NY, about 40 miles upstream from the confluence of the Chenango and Susquehanna Rivers. (See Geological Survey map for Oxford, NY.) Existing project. Provides for earth levees and clearing of Chenango River channel, consisting of about 2,100 feet of earth levees on the left bank of the Chenango River, extending from high ground near Cemetery Drive and running mostly along the railroad to high ground near Main Street; removal of dam and island below Main Street; raising the Delaware, Lackawanna & Western Railroad over the levee; and appurtenant closure and drainage structures. Improvement provides protection for the Village of Oxford on the left bank against a flood discharge substantially larger than the maximum flood of record, which occurred in July 1935. Local cooperation. Fully complied with. Operations and results during fiscal year. Maintenance: Normal operation and maintenance of the project continued. 35M. WHITNEY POINT LAKE, NY Location. Dam is located near Whitney Point, NY, on the Otselic River about 0.7 mile upstream from its confluence with Tioughnioga River. (See Geological Survey map for Whitney Point and Willet, NY.) Existing project. The dam is an earthfill structure, 4,900 feet long, exclusive of a spillway, rises 95 feet above the streambed, with a concrete spillway and gated outlet in the left abutment. The outlet works consist of three 5-foot by 10-foot gates and one emergency gate of the same size. The reservoir has a storage capacity of 86,440 acre-feet at spillway crest. The project controls a drainage area of 255 square miles, the entire watershed of Otselic River, or 16 percent of the Chenango River watershed upstream from Binghamton, NY. Recreation facilities, constructed in cooperation with local interests, provide for swimming, picnicking, camping, boating, fishing, and hunting. Local cooperation. None required. Local interests operate and maintain all of the recreation facilities. Operations and results during fiscal year. Maintenance: Normal operation and maintenance of the project continued. 35N. WHITNEY POINT VILLAGE, NY Location. On the Tioughnioga River at the confluence of the Tioughnioga and Otselic Rivers, tributaries of the Susquehanna River. (See Geological Survey map for Whitney Point, NY.) Existing project. Provides for channel realignment and earth levees, consisting of realignment of about 1,800 feet of Tioughnioga River channel, above the confluence with Otselic River; about 7,100 feet of earth levee along the right bank of the Tioughnioga River, extending from high ground on Main Street above the village to Collins Street just below the Village; and appurtenant drainage structures. Local cooperation. Fully complied with. Operations and results during fiscal year. Maintenance: Normal operation and maintenance of the project continued. 36. STILLWATER LAKE LACKAWANNA RIVER, PA Location. Dam is on the Lackawanna River, 39 miles from the mouth of the stream and about 4 miles upstream from Forest City, Susquehanna County, PA (See Geological Survey Quadrangle sheet: for Honesdale, PA.) Existing project. Dam is earthfill type, rising 77 feet above the streambed, with a controlled outlet conduit and side channel spillway in the left abutment. Reservoir capacity is 12,000 acre-feet, of which 11,600 acre-feet is flood control storage and the remainder utilized to maintain the existing water supply reservoir for Forest City, PA, at this site. Reservoir area is 422 acres,and the pool extends about 2.1 miles upstream. Reservoir controls 52 percent of the watershed above Carbondale, 26 percent above Olyphant, and 17 percent above Scranton. Federal cost of new work, completed in 1965, was $5,725,700 of which $4,500,500 was for construction and $1,225,200 was for lands and damages. Local Cooperation. None required. Section 2, Flood Control Act of June 28, 1938, applies. Operations and results during fiscal year. Maintenance: Normal operation and maintenance of project continued. 37. SUSQUEHANNA RIVER FLOOD CONTROL PROJECTS, NY AND PA Plan of improvement authorized by the 1958 Flood Control Act provides for construction of Cowanesque Lake, PA, Tioga-Hammond Lakes, PA, local protection works at Elkland, PA, and Nichols, NY, and channel improvements at Cortland, NY. This project plan supplemented the comprehensive flood control program for Southern New York and Northern Pennsylvania which included the Southern New York flood control project and Stillwater, Genegantslet, and South Plymouth Reservoirs. 4-17 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 37A. COWANESQUE LAKE, PA Location. Dam is on the Cowanesque River about 2.2 miles above its confluence with Tioga River at Lawrenceville, PA. (See Geological Survey map for Tioga, PA.) Existing project. The project constructed under the Flood Control Act of 1958 provides for an earthfill dam 3,100 feet long and rising 151 feet above the streambed, an uncontrolled spillway in the right abutment, a gated conduit in the Valley floor, and flood control storage is 82,000 acre-feet. Relocation of the Town of Nelson to a new townsite was authorized by Section 121 of the Water Resources Development Act of 1976. The Federal cost of this new work was $106,030,700 of which $61,743,600 was for construction and $44,287,100 was for lands and damages and relocations (which includes $5,755,000 for relocation of the Town of Nelson). Within the discretionary authority of the Chief of Engineers the project was modified in March 1983 in accordance with the Water Supply Act of 1958, as amended, and the Flood Control Act of 1944, as amended. The modification provides for reallocating 25,600 acre-feet of present flood control storage for water supply storage by raising the permanent pool from elevation 1045 to 1080 mean sea level. Other features include modifying the existing intake tower and two access ramps, stablizing the reservoir slope near the relocated Town of Nelson, replacing existing day-use recreation facilities, and expanding both day-and overnight-use recreation facilities to accommodate an expected increase in annual visitation due to the larger pool. Estimated cost (October 1985) of the modification is $61,260,000 of which $970,000 is Federal (for expanded recreation facilities) and $60,290,000 is non- Federal (which includes $47,690,000 for reimbursement of the cost of existing flood control storage reallocated to water supply storage, $11,630,000 cash contribution for the water supply modification, and $970,000 cash contribution for expanded recreation facilities). Local cooperation. The Water Resources Development Act of 1976, which authorized relocation of the Town of Nelson, provides that before the Secretary of the Army acquires any real estate property for the new townsite appropriate non-Federal interests shall furnish binding contractual commitments that all lots in the new townsite will be either occupied when available, will be replacements for open space and vacant lots in the existing town, or will be purchased by non-Federal interests at the fair market value. The required contractual agreement for local cooperation was executed with Nelson Township on August 25, 1977. The March 1983 project modification (discussed above) requires non-Federal interests repay 100 percent of the investment cost of project modifications allocated to water supply, to terrestial wildlife habitat mitigation, and to in-kind replacement recreation, plus the allocated share of the project's original cost (escalated to current price levels). Additionally, they are required to pay annual costs of operation, maintenance, and major replacements allocated to water supply and to provide 50 percent of the cost of expanded recreation facilities, as well as, all operation, maintenance, and replacement costs for the expanded facilities. Operation and results during fiscal year. New Work: Preconstruction planning was completed on the project modification and construction funds of $15,000 were allocated from the 1985 Supplemental Appropriations Act (P.L. 99-88). Maintenance: Normal operation and maintenance of the project continued. 37B. TIOGA-HAMMOND LAKES, PA Location. The dams are located in Tioga County, PA, upstream from the confluence of the Tioga River and Crooked Creek. Tioga Dam is located on the Tioga River and Hammond Dam on Crooked Creek, approximately opposite the Tioga damsite, about 3.3 miles above its mouth and less than one mile from the Village of Brooklyn. (See Geological Survey map for Tioga, PA.) Existing project. Tioga Dam is 2,600 feet long, rising 140 feet above the streambed, with a controlled outlet conduit. Hammond Dam is 5,900 feet long, and has a maximum height of 121.5 feet above the streambed, with a concrete spillway. Both dams are of earth and rockfill construction. The Tioga-Hammond Lakes project controls a total drainage area of 402 square miles, with Tioga Dam controlling 280 square miles of the Tioga River Basin and Hammond Dam controlling 122 square miles of the Crooked Creek Basin. Recreation facilities are provided for swimming, camping, picnicking, boating, and fishing. Estimated Federal cost (October 1985) of new work is $192,540,000 of which $125,029,000 is for completed construction, $60,591,000 is for lands and damages and relocations and $6,920,000 is for construction of the Mill Creek recreation facilities. Local cooperation. None required on the completed portion of the project; however, construction of the Mill Creek Area recreation facilities relies on local interests providing specialized facilities including buildings, lodges, demonstration centers, and non-water oriented equipment and accepting full responsibility for operation and maintenance of the entire recreation area. Operations and results during fiscal year. New Work: Planning for the joint development of the Mill Creek Recreation Area was continued by the Baltimore District and Mansfield University. Maintenance: Normal operation and maintenance of the project continued. 38. WEST BRANCH OF SUSQUEHANNA RIVER, PA A system of three flood control reservoirs, in the headwaters of the West Branch Susquehanna River, PA, are known as Curwensville, Alvin R. Bush, (formerly known as Kettle Creek), and Foster Joseph Sayers (formerly known as Blanchard), on the West Branch about 2.5 miles upstream from Curwensville, PA; on Kettle Creek 8.4 miles above the mouth and 17 miles upstream from Renovo, PA; and on Bald Eagle Creek about one mile upstream from Blanchard, PA, respectively. 4-18 BALTIMORE, MD DISTRICT In accordance with the terms of local cooperation, the Commonwealth of Pennsylvania furnished assurances that it will coordinate operation of George B. Stevenson Reservoir, (formerly known as First Fork Reservoir), with operation of Curwensville, Alvin R. Bush, and Foster Joseph Sayers Reservoirs to secure optimum flood control benefits from system operation. George B. Stevenson Reservoir on the First Fork Sinnemahoning Creek in Cameron and Potter Counties, PA, was constructed by the Commonwealth of Pennsylvania at a first cost of $12,240,000 and an estimated $30,000 annually for operation and maintenance. 38A. ALVIN R. BUSH DAM, PA Location. Alvin R. Bush Dam (formerly Kettle Creek Dam) is located on Kettle Creek about 8.4 miles above the mouth and 15 miles upstream from Renovo, PA. (See Geological Survey map for Keating, PA.) Existing project. Dam is an earthfill structure,about 1,350 feet long, rises 165 feet above the streambed, with an uncontrolled spillway located in rock adjacent to the right abutment, and has a horseshoe-shaped outlet tunnel with 3 service gates. The reservoir has a storage capacity of 75,000 acre-feet at spillway crest. The project controls a drainage area of 226 square miles or about 92 percent of the Kettle Creek watershed. Local cooperation. None required. Operations and results during fiscal year. Maintenance: Normal operation and maintenance of the project continued. 38B. CURWENSVILLE LAKE, PA Location. Dam is on the West Branch of the Susquehanna River approximately 2.5 miles upstream from Curwensville, Clearfield County, PA. (See Geological Survey map for Curwensville, PA.) Existing project. Dam is an earthfill structure, about 1,850 feet long, rises 131 feet above the streambed, and has an open-cut concrete sill 1,750 feet from the left abutment. The outlet works, located in the,left abutment, consist of a 15-foot diameter circular outlet conduit with 3 slide control gates 5.5 feet wide and 12 feet high. The reservoir has a storage capacity of 124,200 acre-feet at spillway crest. The project controls a drainage area of 365 square miles, or about 98 percent of the West Branch Susquehanna River at Curwensville and about 75 percent at Clearfield. Recreation facilities include a seasonal recreational pool of 790 acres, access roads, parking areas, beach area, boat dock, and launching ramp. Local cooperation. None required. Operations and results during fiscal year. Maintenance: Normal operation and maintenance of project continued. 38C. FOSTER JOSEPH SAYERS DAM, PA Location. Dam is located on Bald Eagle Creek in Centre County, PA, about one mile upstream from Blanchard and about 14 miles above the confluence of Bald Eagle Creek with the West Branch Susquehanna River at Lock Haven, PA. (See Geological Survey map for Howard, PA.) Existing project. Dam is an earthfill structure, about 6,835 feet long, rises 100 feet above the streambed, and has an open-cut concrete chute and uncontrolled concrete weir 600 feet wide located in rock in a saddle adjacent to the left abutment. The outlet works, located in the left abutment, consist of a 15-foot diameter circular outlet conduit with two hydraulically-operated wheel gates 7 feet wide and 15 feet high. The reservoir has a storage capacity of 99,000 acre-feet at spillway crest. The project controls a drainage area of 339 square miles or 88 percent of the drainage area above Beech Creek and 43 percent of the Bald Eagle Creek drainage area. Recreation facilities include a summer recreation pool of 1,730 acres, a conservation pool of 630 acres for the preservation of fish life, access roads, parking areas, boat docks and launching ramps, and camping areas. Local cooperation. None required. Operations and results during fiscal year. Maintenance: Normal operation and maintenance of the project continued. 39. WYOMING VALLEY, PA Location. The project is located in Luzerne County, PA, on the Susquehanna River. The project area is limited to the four existing Federal flood control projects. These levee improvements are in Plymouth, Kingston- Edwardsville, Swoyersville-Forty Fort, and Wilkes-Barre and Hanover Township. Existing project. The four projects were constructed during the period 1935 through 1976 and consist of levee, sheet piling, floodwall, and associated interior drainage structures along both banks of the Susquehanna River which provide flood control benefits estimated at $46.1 million annually. Remedial measures to protect against levee failure under future high discharge conditions consist of: weighted filter drains on the landside of the levees to protect against erosion due to seepage in certain areas; stability berms and toe protection on the riverside of the levees in certain areas to stabilize the riverbank and protect against erosion due to river flows; stabilization of sheet piling in certain areas; and additional relief wells to control the underseepage in other areas. Local cooperation. Lands and relocations for construction of the existing projects at an estimated cost of $1,000,000 were provided by the Boroughs of Kingston, Edwardsville, Plymouth, the city of Wilkes-Barre, Hanover Township, and Luzerne County. These entities also operate and maintain the existing projects. Updated assurances were obtained during preparation of the 4-19 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 General Design Memorandum. Additional local costs in connection with the proposed remedial work are expected to be minor. Operations and results during fiscal year. Construction was physically completed for the: sheet piling stabilization at Wilkes-Barre and Forty Fort on February 2, 1985; relief wells at Hanover Township on March 28, 1985; dug toe work at Forty Fort on April 28, 1985; stability berm and dug toe work at Wilkes-Barre on August 2, 1985. Construction contracts were awarded for the filter drain work at Wilkes-Barre, Hanover Township, and Plymouth on September 10, 1984 which is 36% complete, and for filter drain work at Kingston-Edwardsville and Swoyersville-Forty Fort on April 22, 1985 which is 5% complete. 40. YORK, INDIAN ROCK DAM, PA Location. On Codorus Creek 10 miles above its confluence with the Susquehanna River. Codorus Creek has tributary branches in York County in the south and central parts of Pennsylvania. (See Geological Survey Quadrangle sheets: Pennsylvania-York and Hanover.) Existing project. Indian Rock Dam, is an earth and rockfill dam about 1,000 feet long at the top, rising 83 feet above the streambed, with a reservoir providing for control storage of 28,000 acre-feet. Dam is on the main branch of Codorus Creek about 3 miles above York. Outlet works are in the right abutment and the uncontrolled spillway is on the right bank. Reservoir will control entire drainage area of the main branch of Codorus Creek and 41 percent of the drainage area above York. Improvements in Codorus Creek in the vicinity of and through the City of York provide for 22,969 feet of channel extending from 300 feet above Richland Avenue to a point downstream from the Pennsylvania Railroad crossing known as Black Bridge. Improvements, which will increase channel capacity to 24,000 cubic feet per second, include widening and deepening the channel, bank protection, removal of York Roller Mill Dam, and a low water channel about 3,900 feet long in the vicinity of York Roller Mill Dam. Cost of new work for the completed project was $5,061,167, of which $4,566,446 (regular funds) and $11,588 (emergency relief funds) were for construction and $483,133 (regular funds) was for lands and damages. Local cooperation. Section 2, Flood Control Act of June 28, 1938, applies. Operations and results during fiscal year. Maintenance: Normal operation and maintenance of the project continued. 41. INSPECTION OF COMPLETED FLOOD CONTROL PROJECTS Projects in New York, Pennsylvania, Maryland, District of Columbia, and Virginia were inspected during the period by hired labor. See Table 4-I. 42. SCHEDULING FLOOD CONTROL RESERVOIR OPERATIONS Operations and results during fiscal year. The operation of George B. Stevenson Dam, PA, was coordinated with the operation of Alvin R. Bush, Curwensville, and Foster Joseph Sayers Dams in the West Branch Susquehanna River Basin in order to secure optimum flood control benefits from the system operation. Costs during the period were $49,488. Supplemental instructions for the operation of Savage River Dam, MD, were provided, during periods of high water, to insure maximum protection for downstream localities. Costs during the period were $76,632. 43. FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION Emergency flood control activities-repair, flood fighting, and rescue work (Public Law 99, 84th Congress, and antecedent legislation). Cost for the period was $327,247 of which $198,692 was for Disaster Preparedness Program, and $128,555 was for Rehabilitation. Flood control activities pursuant to Section 205, Public Law 858, 80th Congress, as amended (preauthorization). Fiscal year costs were $27,904 for Conklin-Kirkwood, NY. Nonstructural study; $57,306 for Conklin-Broome (Ice Jam) NY; and $37,500 for Hyndmer, PA. Water Supply 44. WASHINGTON AQUEDUCT Location. The diversion dam and raw water supply intakes at Great Falls, the two collecting conduits, part of Dalecarlia receiving reservoir, the booster pumping station and the Little Falls raw water pumping station are located in Maryland. All other structures of the water supply system including parts of the raw water collecting system, two purification plants, pumping stations, storage reservoirs, and transmission mains are in the District of Columbia. Federal owned water mains are maintained in Virginia and Maryland. Existing project. Control of the water supply system is vested in Chief of Engineers (See Acts of March 3, 1859, and March 2, 1867, November 22, 1973 and Sec. 1800 of Revised Statutes). , The project includes: administration; operation and maintenance of the collection, purification, pumping, and transmission facilities; protection of the water supply system; engineering; and construction of major water system additions and improvements. Authority to supply water to Arlington County, the City of Falls Church, and other jurisdictions in Virginia is contained in Public Law 119, 69th Congress, approved April 14, 1926; and Public Law 118, 80th Congress, June 26, 1947. Local cooperation. Requirements are described in full on page 4-19 of the Fiscal Year 1981 Annual Report. 4-20 BALTIMORE, MD DISTRICT Operations and results during fiscal year. New Work: The McMillan Water Treatment Plant Replacement work authorized with "no year" funds is 99% complete. A contract for the new Chlorine Bldg. at Dalecarlia was awarded July 31, 1984 and construction is complete and operational. Maintenance (operation): An uninterrupted and adequate supply of purified water was furnished to the District of Columbia; Arlington County, and Falls Church, Virginia; and to Federal establishments in the District of Columbia, Arlington County, Virginia and Montgomery and Prince Georges Counties in Maryland. Total consumption for Fiscal Year 1985 was 78,695 million gallons; the maximum daily consumption was 273 million gallons and average daily consumption was 216 million gallons. The amount furnished Arlington County and Falls Church, Virginia was 39.4 million gallons per day. The Corps of Engineers was reimbursed in the amount of $3,624,135 for water furnished to the Virginia communities by the Washington Aqueduct. The treated water delivered to the 1.1 million consumers served by the Washington Aqueduct met or surpassed all Water Quality standards promulgated by the U.S. Environmental Protection Agency under the Safe Drinking Water Act (P.I. 93-523.) General Investigations 45. SURVEYS Costs for the fiscal year were $738,682 of which $234 was for flood damage prevention studies, $400,872 for shoreline protection studies, $113,285 for special studies, $4,790 for comprehensive basin studies, $8,000 for project deauthorization program, and $211,501 for coordination with other agencies and non-Federal interests. 46. COLLECTION AND STUDY OF BASIC DATA Costs for flood plain management activities and general planning guidance during the period was $268,926. Providing assistance and guidance to local interests on methods and procedures for preventing and reducing flood damages was in progress at end of fiscal year. 47. CONTINUATION OF PLANNING AND ENGINEERING Susquehanna Basin at Harrisburg, PA-The plan of improvement for the South Harrisburg area recommended in an interim report on the Susquehanna River Basin study includes a floodwall 3,800 feet long, a pump station and floodgates for interior drainage, a dry detention dam along Asylum Run (a small tributary of Paxton Creek), an enlarged earth and concrete channel for Paxton Creek about four miles long, and minor recreation and fish and wildlife facilities. Preparation of a General Design Memorandum continued during the fiscal year. Estimated planning and engineering cost is $2,900,000. Total costs during the fiscal year were $281,482. Lock Haven, PA-The plan of improvement recommended in the Phase I General Design Memorandum includes 24,500 feet of levee, 6,500 feet of floodwall, eight closure structures, four pumping stations, diversion of Lusk Run, and minor recreation facilities. Preparation of a Phase II General Design Memorandum continued during the fiscal year. Estimated planning and engineering cost is $2,025,000. Total costs during the fiscal year were $736,851. Wyoming Valley, PA (Levee Raising)-The plan of improvement in the Phase I General Design Memorandum includes raising the existing levees and floodwalls between five and seven feet, modifying closure structures, relocating utilities, and providing some new floodwalls and levees to maintain the system's integrity. The plan also includes raising five other local protection projects, removing an abandoned railroad bridge, and providing non-structural measures to mitigate any significant induced damages and the potential of a catastrophic failure of an existing project. The estimated planning and engineering cost is $5,700,000 and costs during the fiscal year were $175,498. 48. ADVANCED ENGINEERING AND DESIGN Francis E. Walter Dam, PA-Modification-The authorized project would provide for modifying the existing single purpose flood control project by raising the existing dam 30 feet thereby adding water supply and recreation purposes. Preparation of the combined General Design Memorandum was completed and work was initiated on design memoranda for project features. Estimated preconstruction planning cost is $5,755,000. Total costs during the fiscal year were $738,319. Tamaqua, PA-The authorized project would provide for a 9-foot diameter diversion tunnel 2,930 feet long, that starts at Wabash Creek at the west boundary of Tamaqua and terminates at the Little Schuylkill River. The project also includes an intake structure, a stilling basin, a highway bridge, and a small dry detention reservoir on a tributary of Wabash Creek. Plans and specifications for project construction were completed during the fiscal year. Estimated preconstruction planning cost is $1,750,000. Total costs during the fiscal year were $503,316. 4-21 TABLE 4-A REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 COST AND FINANCIAL STATEMENT See Total Section to in Text Project Funding FY82 FY83 FY84 FY85 Sept. 30, 1985 1. Baltimore Harbor and Channels, MD and VA 2. Baltimore Harbor MD Collection & Removal of Drift 3. Claiborne Harbor, MD 4. Fishing Bay, MD 5. Fishing Creek, MD 6. Herring Bay & Rockhold Creek, MD 7. Honga River and Tar Bay, (Barren Island Gaps), MD 8. Knapps Narrows, MD 9. Little Wicomico River, VA 10. Lower Thorofare Deal Island, MD New Work Approp. Cost Maint. Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost 33,997 33,677 3,626,3492 2,657,4213 248,200 240,536 1,300,000 851,317 5,769,0004 6,568,7555 177,000 186,916 770,000 1,055,174 12,865,0006 13,035,8147 202,000 202,323 455,000 555,821 15,637,0008 15,637,0129 205,000 201,424 95,129 95,127 36,000 36,000 54,000 39,604 276,485 273,267 1,397,000 882,730 318,636 333,032 4,000 4,000 80,450 80,450 19,310 19,310 -48,758 467,475 28,000 28,000 35,000 35,000 277,244 277,499 7,078 7,079 653,000 653,000 237,750 237,750 416,600 416,600 20,000 20,000 46,851,712' 46,779,414' 65,976,86010 65,976,85610 3,051,210 3,047,633 42,974" 42,974" 190,733 190,731 33,874 33,874 705,652 705,652 111,242 111,242 939,650 939,650 50,591 50,591 454,248 454,248 66,11912 66,11912 2,998,926 2,998,926 46,121' 3 46,121' 3 1,553,075 1,553,075 81,885' 4 81,885' 4 1,249,053 1,249,051 44,65815 44,65815 340,942 340,942 4-22 BALTIMORE, MD DISTRICT TABLE 4-A (Continued) COST AND FINANCIAL STATEMENT See Total Section to in Text Project Funding FY82 FY83 FY84 FY85 Sept. 30, 1985 11. Ocean City Harbor New Work and Inlet and Sine- Approp. - - - - 350,19316 puxent Bay, MD Cost - - - - 350,1931'6 Maint. Approp. 557,500 1,343,000 935,000 781,000 9,228,908 Cost 480,186 251,452 2,106,987 709,961 9,157,867 Major Rehab. Approp. - 1,000,000 1,750,000 1,050,000 3,800,000 Cost - - 2,734,267 1,056,190 3,790,457 12. Parish Creek, New Work MD Approp. - - - - 19,17017 Cost - - - - 19,170'7 Maint. Approp. - - - 31,578 94,434 Cost - - - 31,578 94,434 13. Pocomoke River, New Work MD Approp. - - - - 191,72618 Cost - - - - 191,72618 Maint. Approp. - 25,000 32,000 312,500 1,537,535 Cost - 25,000 32,000 312,500 1,537,535 14. Potomac and Maint. Anacostia Rivers, Approp. 459,800 486,000 352,000 410,000 5,803,175 DC, Collection & Cost 467,292 493,074 353,227 394,333 5,787,507 Removal of Drift 15. Prevention of Maint. Obstructions & Approp. 284,000 - 162,000 51,000 4,372,040 Injurious Deposits, Cost 243,179 40,929 162,000 50,949 4,371,989 Baltimore Harbor, MD 16. Queenstown New Work Harbor, MD Approp. - - - - 72,85819 Cost - - - - 72,85819 Maint. Approp. - - - 279,824 321,803 Cost - - - 279,824 321,803 17. Rhodes Point New Work to Tylerton, MD Approp. 335,000 -51,000 - - 304,000 Cost 74,181 213,698 - - 304,000 Maint. Approp. - - - 41,488 312,994 Cost - - - 41,487 312,993 18. St. George New Work Creek, MD Approp. 9,000 138,650 - - 147,650 Cost - 38,137 94,136 577 132,577 19. St. Patricks New Work Creek, MD Approp. - - - - 15,752 Cost - - - - 15,752 Maint. Approp. - 2,934 - 8,354 31,602 Cost - 2,934 - 8,354 31,602 20. Susquehanna New Work River above Approp. - - - - 293,57020 and below Cost - - - - 293,57020 Havre De Maint. Grace, MD Approp. - - 48,000 503,730 928,019 Cost - - 47,999 503,730 928,018 4-23 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 4-A (Continued) COST AND FINANCIAL STATEMENT See Total Section to in Text Project Funding FY82 FY83 FY84 FY85 Sept. 30, 1985 21. Tred Avon, New Work MD Approp. - - - - 523,310 Cost - - - - 523,310 Maint. Approp. - - 17,000 36,000 66,843 Cost - - 17,000 36,000 66,843 22. Twitch Cove & New Work Big Thorofare, Approp. - - - - 193,175 MD Cost - - - - 193,175 Maint. Approp. 767,885 - - 27,569 1,882,811 Cost 768,221 - - 27,569 1,882,811 23. Upper Thorofare, New Work MD Approp. - - - - 62,446 Cost - - - - 62,446 Maint. Approp. - - - 10,000 347,441 Cost - - - 10,000 347,441 24. Washington Harbor, New Work DC Approp. - - - - 3,191,07721 Cost - - - - 3,191,07721 Maint. Approp. 581,750 -19,000 63,000 206,782 4,750,49622.23 Cost 109,910 440,826 77,569 206,782 4,750,4962223 25. Wicomico River, New Work MD Approp. - - - - 471,60924 Cost - - - - 471,60924 Maint. Approp. 822,079 824,730 134,000 681,000 5,913,737 Cost 330,789 547,075 915,074 681,000 5,913,735 28. Colonial Beach, New Work VA Approp. 370,000 - 64,000 - 15,000 519,00025 Cost 350,926 -7,138 - 12,500 516,50025 Contrib. Approp. 480,000 -65,023 - - 414,977 Cost 370,299 44,678 - - 414,977 30. Black Walnut New Work Point, MD Approp. - 227,500 - -27,000 200,500 Cost - 37,679 163,294 -473 200,500 31. Bloomington Lake, New Work MD & WV Approp. 1,750,000 1,688,000 -110,000 1,900,000 176,270,300 Cost 2,928,555 1,856,543 582,603 1,974,750 176,240,105 Maint. Approp. 611,500 893,200 988,978 1,160,200 3,974,978 Cost 599,866 885,166 1,005,530 1,163,471 3,974,920 32. Cumberland, MD New Work and Ridgeley, Approp. - - - - 15,633,97026 WV Cost - - - - 15,633,97026 Maint. Approp. 54,000 64,600 45,000 55,930 578,229 Cost 54,281 66,856 45,000 55,930 578,229 33A. Aylesworth Creek New Work Lake, PA Approp. - - - - 2,320,400 Cost - - - - 2,320,400 Maint. Approp. 55,400 67,000 72,925 113,500 862,602 Cost 48.757 71,631 75,636 113,424 862.524 4-24 BALTIMORE, MD DISTRICT TABLE 4-A (Continued) COST See Section in Text Proiect Funding AND FINANCIAL STATEMENT FY82 FY83 FY84 FY85 Total to Sept. 30, 1985 34. Raystown Lake, Raystown Branch, Juniata River, PA 35A. Addison, NY 35B. Almond Lake, NY 35C. Arkport Dam, NY 35D. Avoca, NY 35E. Binghamton, NY 35F. Canisteo, NY 35G. Corning, NY 35H. East NY Sidney Lake, 351. Elmira. NY New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost - - - - 77,408,700 - - - - 77,408,700 1,934,238 2,423,056 1,741,000 2,125,500 15,659,295 2,053,846 2,447,276 1,778,456 2,077,231 15,610,959 20,600 27,109 233,600 221,471 118,400 126,940 23,400 22,701 11,100 13,726 37,681 38,020 44,300 41,993 187,600 172,623 15,700 16,342 12,900 12,879 221,000 230,101 180,800 178,847 15,900 16,788 34,300 34,283 38,100 40,321 24,800 27,126 347,500 359,826 22,800 26,264 16,049 16,124 160,772 164,920 78,363 87,246 18,300 18,300 28,300 28,398 25,800 25,802 25,600 25,600 300,118 302,918 20,400 20,400 17,200 17,200 379,500 379,362 130,700 130,621 23,526 23,525 18,000 18,000 53,474 53,472 53,900 53,900 262,100 262,095 25,900 25,900 827,050 827,050 164,055 164,055 5,760,211 5,760,211 2,788,840 2,788,699 1,910,00027 1,910,00027 1,443,174 1,443,092 436,37428 436,37428 356,361 356,360 2,952,00029 2,952,00029 378,581 378,581 1,183,11130 1,183,11130 592,235 592,233 3,322,000'31 3,322,00031 603,058 603,058 6,049,504 6,049,504 3,117,319 3,117,308 6,883,305 6,883,305 236,249 236,249 4-25 a------,- REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 4-A (Continued) COST AND FINANCIAL STATEMENT See Total Section to in Text Project Funding FY82 FY83 FY84 FY85 Sept. 30, 1985 35J. Hornell, NY 35K. Lisle, NY 35L. Oxford, NY 35M. Whitney Point Lake, NY 35N. Whitney Point Village, NY 36. Stillwater Lake, Lackawanna River, PA 37A. Cowanesque Lake, PA 37B. Tioga-Hammond Lakes, PA 38A. Alvin R. Bush Dam, PA 38B. Curwensville Lake, PA New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost 148,419 150,972 35,700 33,824 12,400 9,863 235,900 195,765 24,700 25,794 114,500 111,732 270,000 1,040,052 675,350 680,662 -30,000 286,038 1,095,864 1,019,593 330,300 237,872 543,000 546,095 348,200 257,415 22,500 26,382 11,200 13,737 259,500 300,269 26,300 29,273 158,600 161,139 168,891 851,200 833,587 -220,000 79,419 1,269,200 1,331,830 488,800 413,472 360,500 361,923 85,051 176,056 25,400 25,453 15,900 15,900 265,843 266,070 33,200 33,253 201,340 201,680 670,000 722,340 743,904 754,305 -60,000 23,487 1,144,289 1,166,973 403,810 572,896 405,491 405,237 106,170 106.168 19,800 19,800 17,600 17,600 304,800 304,721 20,500 20,500 211,700 211,631 1,065,000 853,691 932,800 938,312 4,558,69832 4,558,69832 2,854,233 2,854,229 661,19933 661,19933 616,022 616,022 131,00014 131,00014 189,432 189,432 5,421,539 5,421,539 3,451,140 3,451,053 424,096 424,096 305,261 305,261 5,725,700 5,725,700 1,842,209 1,842,134 107,765,700 107,539,473 3,775,154 3,771,664 35,000 18,654,800 30,000 18,649,800 1,540,700 1,540,278 427,300 427,275 491,100 492,316 7,124,854 7,124,337 7,103,001 7,103,001 3,667,622 3,667,588 20,396,060 20,396,060 5,361,389 5,361,311 4-26 BALTIMORE, MD DISTRICT TABLE 4-A (Continued) COST AND FINANCIAL STATEMENT See Total Section to in Text Project Funding FY82 FY83 FY84 FY85 Sept. 30, 1985 38C. Foster Joseph New Work Sayers Dam, PA Approp. - - - - 30,887,063 3 Cost - - - - 30,887,063 3 Maint. Approp. 345,547 412,000 446,722 472,300 4,482,084 Cost 342,872 412,339 449,450 472,515 4,482,075 39. Wyoming, Valley, New Work PA Approp. 800,000 2,390,000 2,190,000 6,800,000 25,405,000 Cost 667,635 1,388,786 3,205,348 2,686,198 21,202,967 40. York, Indian New Work Rock Dam, PA Approp. - - - - 5,061,16736 Cost - - - - 5,061,16736 Maint. Approp. 290,700 294,800 373,344 534,000 4,319,217 3 Cost 267,909 312,558 379,530 523,994 4,309,203 3 1. Includes $8,764,003 for previous projects. 18. Unconstructed portion of the project is inactive. In- 2. Includes $1,663,300 for sections of project in Norfolk cludes $20,500 for previous project. District. 19. Includes $19,000 for previous project. 3. Includes $696,090 for sections of project in Norfolk 20. Unconstructed portion of the project was deauthorized District. November 6, 1977. Includes $22,905 Works Progress Adminis- 4. Includes $1,085,000 for sections of project in Norfolk tration funds and $97,390 for previous project. District. 21. Includes $3,029,001 for previous project. 5. Includes $1,891,518 for sections of project in Norfolk 22. Includes $1,831,609 for previous project. District. 23. Excludes $4,000 for emergency dredging under provi- 6. Includes $40,000 for sections of project in Norfolk sions of Section 3, 1945 River and Harbor Act. District. 24. Includes $50,000 for previous project and excludes 7. Includes $200,691 for sections of project in Norfolk $14,000 contributed funds. District. 25. Excludes $414,977 contributed funds. 8. Includes $88,000 for sections of project in Norfolk 26. Includes $49,998 emergency relief funds. District. 27. Includes $62,577 emergency relief funds. 9. Includes $88,001 for sections of project in Norfolk 28. Includes $109,944 emergency relief funds. District. 29. Excludes $163,096 contributed funds. 10. Includes $399,802 for previous projects. 30. Includes $207,520 rehabilitation funds. 11. Project deferred for restudy. 31. Excludes $34,729 contributed funds. 12. Excludes $2,200 contributed and includes $27,668 32. Includes $250,899 emergency relief funds and excludes emergency relief funds. $15,000 contributed funds. 13. Includes $46,121 public works funds. 33. Includes $71,557 emergency relief funds. 14. Excludes $5,000 contributed funds. 34. Includes $73,465 emergency relief funds. 15. Includes $5,000 for previous project. 35. Excludes $263,900 contributed funds in accordance 16. Includes $283,008 public works funds and $67,185 with the Tri-party Agreement for construction of sanitary sysemergency relief funds; excludes $500,000 contributed funds. tem for public use. 17. Includes $19,170 Works Progress Administration 36. Includes $11,588 emergency relief funds. funds. 37. Includes $15,000 for deferred maintenance. TABLE 4-B AUTHORIZING LEGISLATION See Date Section Authorizing in Text Act Project and Work Authorized Documents BALTIMORE HARBOR AND CHANNELS, MD and VA Branch channel 35 feet deep to head of Curtis Bay, and one 35 feet deep and 400 feet wide Fort McHenry to Port Covington entrance channel, thence 150 feet wide to Ferry Bar, and thence 27 feet deep and 150 feet wide to Hanover Street Bridge, widen approaches and bends, and enlarge anchorage basin near entrance. Inclusion of Patapsco River and tributaries into one project for Baltimore Harbor.2 H. Doc. 799, 64th Cong., 1st sess. 4-27 Aug. 8, 1917 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 4-B (Continued) AUTHORIZING LEGISLATION See Date Section Authorizing in Text Act Project and Work Authorized Documents Jan. 21, 1927 Jul. 3, 1930 Change in location of anchorage near upper end of Fort McHenry Channel. Increased anchorage facilities. Jul. 3, For 37-foot depth in that portion of channel to Baltimore lying between 37-foot 1930 depth curve near Baltimore Light to Sparrows Point entrance channel; widen angle between Fort McHenry and Ferry Bar Section; and for width of 400 feet in Curtis Bay section. Oct. 17, For 22-, 18-, and 15-foot channels in Curtis Creek from 22-foot depth below 1940 Pennington Ave. Bridge to upper end of marginal wharf of U.S. Ordnance Depot. Mar. 2, Uniform main channel 39 feet deep from the ocean through York Spit section 1945 and Craighill entrance to Fort McHenry, additional anchorage area, 2,400 feet long, 1,200 feet wide, and 30 feet deep; a connecting channel 400 feet wide and 27 feet deep from Cutoff Brewerton Angle in main channel to Inland Waterway from Delaware River to Chesapeake Bay; a channel in Curtis Creek 200 feet wide and 35 feet deep from head of existing 35-foot project channel in Curtis Bay to a point in the creek about 750 feet below Pennington Ave. Bridge. Mar. 2, A channel 22 feet deep and 200 feet wide from 22-foot depth curve south of 1945 Baltimore & Ohio R.R. bridge about 2,800 feet to vicinity of Arundel Cove, thence 100 feet wide in Arundel Cove for about 2,100 feet; with an anchorage basin about 700 feet square adjacent to channel southwesterly of Coast Guard wharf. July 3, Main channel 42 feet deep and 1,000 feet wide in Cape Henry section at 1958 entrance to Chesapeake Bay and in York Spit section; 42 feet deep and 800 feet wide in Rappahannock Spit section and in approach channel to Baltimore Harbor from Craighill entrance to Fort McHenry, with widening at entrance and bends; channels 42 feet deep and 600 feet wide in Curtis Bay and Ferry Bar sections of harbor; a connecting channel 35 feet deep and 600 feet wide from main channel to approach channel to Chesapeake and Delaware Canal; and for three disjointed sections of channels of same depth and width in Chesapeake Bay leading to Chesapeake and Delaware Canal; and to provide Federal maintenance of 39-foot depth in Northwest Branch, in areas dredged to that depth by local interests. Dec. 31, Deepening of the Cape Henry Channel to 50 feet at the existing width of 1970 1,000 feet, with widening at bends; deepening of the Spit Channel to 50 feet at the existing width of 1,000 feet, with widening at bends; enlargement of the Rappahannock Shoal Channel to a depth of 50 feet and a width of 1,000 feet; deepening of the main ship channel from Chesapeake Bay to Fort McHenry to a depth of 50 feet at the existing width of 800 feet, with widening at bends and at the Craighill Entrance; deepening of the Curtis Bay Channel to a depth of 50 feet at the existing width of 600 feet, and deepening of the 950-foot wide and 980-foot long turning basin at the head of channel to the same depth; deepening of the Northwest Branch-East Channel to a depth of 49 feet from the depth existing at the time of construction at a width of 600 feet, and deepening of the 950-foot wide and 950-foot long turning basin at the head of the channel to the same depth; and deepening and extension of the Northwest Branch-West Channel to a depth of 40 feet from the depth existing at the time of construction, at a width of 600 feet, and with an irregularly shaped turning basin at the head of the channel 40 feet deep and about 2,000 feet long with a maximum width of 1,150 feet. BALTIMORE HARBOR, MD-COLLECTION AND REMOVAL OF DRIFT Jun. 30, Collection and removal of drift from Baltimore Harbor and its tributary 1948 waters. Rivers and Harbors Committee Doc. 11, 70th Cong., 1st sess. H. Doc. 86, 85th Cong., 1st sess. Adopted as a national defense project. (No printed report.) H. Doc. 741, 79th Cong., 2nd sess. In accordance with plans on file in the Office, Chief of Engineers. H. Doc. 86, 85th Cong., 1st sess. H. Doc. 181, 94th Cong., 1st sess. River and Harbor Act of 1948. 4-28 BALTIMORE, MD DISTRICT TABLE 4-B (Continued) AUTHORIZING LEGISLATION See Date Section Authorizing in Text Act Project and Work Authorized Documents 3. 4. 5. 10. Jun. 25, 1910 Mar. 2, 1945 LOWER THOROFARE, DEAL ISLAND, MD A channel 6 feet deep, 80 feet wide, from Tangier Sound to the wharves at Wenona; widening the angles and the end to furnish anchorage basins. Modified to provide a channel 60 feet wide, 7 feet deep from Tangier Sound to and including a mooring basin 7 feet deep, 100 feet wide, 300 feet long, in the marsh at the head of the cove at Wenona. OCEAN CITY HARBOR & INLET & SINEPUXENT BAY, MD Aug. 30, Construction of an inlet between the Atlantic Ocean and Sinepuxent, Bay, 19359 10 feet deep and 200 feet wide, protected by jetties; a channel 8 feet deep and 100 feet wide from the inlet to Ocean City, 6 feet deep and 150 feet wide to Green Point, and 100 feet wide into Chincoteague Bay. Aug. 30, Modification providing a 10-foot by 100-foot channel from the inlet to the 19354 west side of the bay with 2 turning basins; a channel 6 feet deep and 125 feet wide from the inlet channel to opposite North 8th Street, Ocean City, and 75 feet wide into Isle of Wight Bay. CLAIBORNE HARBOR, MD Jun. 13, A channel 12 feet deep and 300 feet wide from deep water to the railroad 1902 pier in the harbor, and thence shoreward along the south side of the pier with a width of 195 feet and a length of 500 feet. An extension of the present jetty. FISHING BAY, MD Aug. 26, Provided for channels 6 feet deep and generally 60 feet wide at mean low 1937 water, suitably widened where necessary to offer adequate sheltered anchorage space from deep water and in Fishing Bay to vicinity of county or packing house wharves in McCreadys, Farm, and Goose Creeks. FISHING CREEK, MD Aug. 26, A channel 7 feet deep with widths of 100 feet and 60 feet from deep water in 1937 Chesapeake Bay to an anchorage of the same depth, 120 feet wide and 400 feet long, located in the marsh 500 feet above the mouth of the creek and twin stone jetties at the entrance. HERRING BAY & ROCKHOLD CREEK, MD Jul. 3, A channel 60 feet wide, 5 feet deep, from the 6-foot contour in Herring Bay 1930 to the 3-foot contour in Rockhold Creek. Jun. 20, For the present project channel dimensions, 7 feet deep and 60 feet wide, 1938 the turning basin 7 feet deep, and a stone breakwater 900 feet long. HONGA RIVER AND TAR BAY (BARREN ISLAND GAPS), MD Aug. 30, Channel 60 feet wide and 7 feet deep from the 7-foot contour in Chesapeake 1935 Bay through Tar Bay and Fishing Creek to the 7-foot contour in Honga River. Jun. 30, Modification providing for a channel in Back Creek 7 feet deep and 60 feet 1948 wide from the 7-foot depth curve in Honga River to a point near the head of Back Creek, with a turning basin of the same depth, 150 feet long and 200 feet wide. KNAPPS NARROWS, MD Aug. 30, A channel 9 feet deep at mean low water, 75 feet wide, widened at the bends 1935 from deep water in Cheseapeake Bay to deep water in Harris Creek, MD, with a turning basin west of the drawbridge, 7 feet deep at mean low water, about 320 feet long and 120 feet wide. Project channel was authorized by the Public Works Administration September 16, 1933 and later adopted by 1935 River and Harbor Act. LITTLE WICOMICO RIVER, VA Aug. 30, A channel 8 feet deep and 150 feet wide from Potomac River to deep water 1935 in Little Wicomico River; two stone jetties 1,000 feet and 1,300 feet long at the entrance; and 1,004 linear feet of timber bulkhead to stabilize the dredged inner channel. 4-29 H. Doc. 81, 56th Cong., 1st sess. H. Doc. 186, 75th Cong., 1st sess. H. Doc. 241, 75th Cong., 1st sess. Rivers and Harbors Committee Doc. 34, 71st Cong., 2nd sess. H. Doc. 595, 75th Cong., 3rd sess.' Rivers and Harbors Committee, Doc. 35, 74th Cong., 1st sess. H. Doc. 580, 80th Cong., 2nd sess.' H. Doc. 308, 72nd Cong., 1st sess. Rivers and Harbors Committee Doc. 24, 74th Cong., 1st sess. H. Doc. 76, 60th Cong., 1st sess. H. Doc. 238, 76th Cong., 1st sess. 1 Rivers and Harbors Committee Doc. 38, 72nd Cong., 1st sess. Rivers and Harbors Committee Doc. 60, 74th Cong., 1st sess. 7. 9. 11. REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 4-B (Continued) AUTHORIZING LEGISLATION See Date Section Authorizing in Text Act Project and Work Authorized Documents Sep. 3, Modification providing for raising the north jetty to an elevation 9 feet 19456 above mean low water, and a channel 300 feet wide and 16 feet deep from the ocean through the inlet to the Isle of Wight Bay channel, thence 200 feet to the project harbor, and a depth of 14 feet in the project harbor. Channel depths refer to project datum. PARISH CREEK, MD Aug. 30, Provide a channel 8 feet deep and 50 feet wide, widened at its ends, from 1935 deep water in West River to the head of the south fork of Parish Creek, and an anchorage basin at the junction with the north fork of Parish Creek, having a depth of 6 feet and an area not exceeding 1.5 acres. 13. Jun. 3, 1896 Aug. 30, 1935 Mar. 2, 1945 Sep. 3, 1954 14. POCOMOKE RIVER, MD A 9-foot channel from Shad Landing to Snow Hill. A channel 7 feet deep and 100 feet wide from Pocomoke Sound to Pocomoke River. Extend channel above bridge at Snow Hill, 100 feet wide, 9 feet deep, widened to 150 feet to form a turning basin at upper end. Channel 11 feet deep by 150 feet wide from Pocomoke Sound to Tulls Point, thence a channel of the same depth and 100 feet wide to deep water in Pocomoke River above Williams Point, and dike construction along south side of channel from existing dike to Tulls Point. POTOMAC & ANACOSTIA RIVERS, DC-COLLECTION & REMOVAL OF DRIFT Oct. 27, Collection and removal of drift from waters of the Potomac and Anacostia 1965 Rivers and their tributaries in the Washington, DC area from the head of the tidewater to Mount Vernon, Virginia. PREVENTION OF OBSTRUCTIONS & INJURIOUS DEPOSITS, BALTIMORE HARBOR, MD Aug. 28, Continuous patrol and inspection of Baltimore Harbor, Chesapeake Bay, 1958 and its tributaries to prevent and detect violations, and issue permits as required for transporting and depositing waste materials in navigable waters. (The project is limited to the tidal waters of Chesapeake Bay and its tributaries that lie within the State of Maryland.) QUEENSTOWN HARBOR, MD Jun. 13, Provides for a channel 10 feet deep at mean low water and 200 feet wide 1902 from that depth in Chester River to the 10-foot contour in Queenstown Creek, a distance of about 4,000 feet; and for a channel 7 feet deep at mean low water and 75 feet wide extending from the 7-foot contour in Queenstown Creek to and including a mooring basin of the same depth and 300 feet square opposite the town wharf in Little Queenstown Creek. Jan. 22, 1982 Sec. 107 Jul. 14, 1960 Sep. 3, 1954 Aug. 1, 1968 Sec. 107 Jul. 14, 1960 RHODES POINT TO TYLERTON, MD A channel 6 feet deep and 50 feet wide at mean low water from the northern limit of existing Rhodes Point to Tylerton Federal navigation channel, a distance of about one mile, through Sheep Pen Gut to deep water in the Chesapeake Bay. A channel 4 feet deep at mean low water and 50 feet wide from Tylerton to Rhodes Point via Rhodes Point Gut. Modification providing for a channel 6 feet deep and 50 feet wide from that depth in Tyler Creek to and including an anchorage basin of the same depth 150 feet wide and 400 feet long at Tylerton; channel 6 feet deep and 50 feet wide from that depth in Shanks Creek to and including an anchorage basin of the same depth 100 feet wide and 400 feet long at Rhodes Point; channel 6 feet deep and 50 feet wide from that depth in Big Thorofare River to Tylerton; channel 6 feet deep and 50 feet wide from Rhodes Point to Tylerton. 12. 4-30 H. Doc. 444, 82nd Cong., 2nd sess. H. Doc. 185, 72nd Cong., 1st sess. Annual Report for 1895, p. 1167. H. Doc. 227, 74th Cong., 1st sess.1 H. Doc. 429, 76th Cong., 1st sess.' H. Doc. 486, 81st Cong., 2nd sess. H. Doc. 286, 89th Cong., 1st sess. River and Harbor Act, June 29, 1888 as amended by Public Law 85-802, dated August 28, 1958. H. Doc. 92, 56th Cong., 1st sess. Detailed Project Report, June 1981 H. Doc. 51, 82nd Cong., 1st sess.' Detailed Project Report, February 1968 15. 16. 17. BALTIMORE, MD DISTRICT TABLE 4-B (Continued) See Date Section Authorizing in Text Act AUTHORIZING LEGISLATION Project and Work Authorized 18. Apr. 29, 1983 Sec. 107 Jul. 14, 1960 ST. GEORGE CREEK, MD A channel 1,500 feet in length, 60 feet wide, and 7 feet deep at mean low water, from the St. George Island Bridge to deep water in the Potomac River. ST. PATRICKS CREEK, MD May 17, Entrance channel 7 feet deep, 60 feet wide and approximately 2,450 feet 1950 long from deep water in St. Clement Bay to deep water within the creek. Aug. 2, 1882 Aug. 26, 1937 Mar. 2, 1945 Jul. 25, 1912 Mar. 2, 1919 Oct. 27, 1965 SUSQUEHANNA RIVER ABOVE AND BELOW HAVRE DE GRACE, MD Channel 200 feet wide and 15 feet deep from Chesapeake Bay to Havre de Grace, and remove shoal opposite Watsons Island. Modifications to provide for maintenance of existing small boat harbor and approach channel below Concord Point. Modification to provide for improvement and maintenance of small boat harbor just below Concord Point for a width of 380 feet and length of 400 feet with an approach channel 100 feet wide, all to a depth of 10 feet. TRED AVON RIVER, MD Restore the channel, formerly dredged from Peach Blossom Creek to Easton Point, to 8 feet deep at mean low water, and 150 feet wide, widening out at the upper end. A channel 8 feet deep and 150 feet wide up the North Fork, with a turning basin at the upper end. A 12-foot channel from a point near Peach Blossom Creek to Easton Point, thence 1,400 feet in North Fork and a turning basin 12 feet deep and 250 feet wide and 600 feet long in the South Fork. TWITCH COVE AND BIG THOROFARE, MD Jul. 25, A channel 4 feet deep and 25 feet wide from Tangier Sound into Big 1912 Thorofare River, and one of same dimensions around point between said river and Tyler River. Jul. 3, A channel 5 feet deep at mean low water and 25 feet wide from Twitch 1930 Cove on Tangier Sound through Big Thorofare River to a point on Levering Creek about 800 feet north of canal at Ewell, MD. Aug. 30, A channel 7 feet deep and 60 feet wide from Twitch Cove through Big 1935 Thorofare River to a point on Levering Creek about 800 feet north of canal at Ewell, MD. Jun. 20, 1938 Present project dimensions of main channel with twin jetties at entrance. May 17, Anchorage basin 7 feet deep, 100 feet wide and 700 feet long on west side 1950 of project channel at Ewell, MD, and an extension of existing project channel in Levering Creek, 6 feet deep, 60 feet wide, and 1,000 feet long. UPPER THOROFARE, DEAL ISLAND, MD Aug. 30, A 9-foot channel 75 feet wide protected by breakwater at entrance, with 1935 turning basin at inner end and anchorage area 6 feet deep and 150 feet wide. Aug. 26, Widen entrance channel to 100 feet, extend 9-foot turning basin and 6-foot 1937 anchorage, and dredging an additional anchorage area on north side of channel. 19. 20. 4-31 Expanded Reconnaissance Report, April 83 H. Doc. 671, 80th Cong., 2nd sess.1 H. Doc. 322, 75th Cong., 1st sess. S. Doc. 67, 76th Cong., 1st sess.' H. Doc. 399, 62nd Cong., 2nd sess.' H. Doc. 26, 63rd Cong., 1st sess. H. Doc. 225, 89th Cong., 1st sess.' H. Doc. 285, 62nd Cong., 2nd sess. H. Doc. 313, 71st Cong., 2nd sess. Rivers and Harbors Committee Doc. 67, 74th Cong., 1st sess. Rivers & Harbors Committee Doc. 49, 75th Cong., 2nd sess.' H. Doc. 340, 81st Cong., 1st sess. Rivers and Harbors Committee Doc. 37, 72nd Cong., 1st sess. H. Doc. 76, 75th Cong., 1st sess.' Documents 21. 22. 23. REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 4-B (Continued) See Date Section Authorizing in Text Act AUTHORIZING LEGISLATION Project and Work Authorized WASHINGTON HARBOR, DC Aug. 30, Provides for: (a) Virginia Channel, from Giesboro Point to area for 25,000 1935 square feet; (b) Washington Channel, from Haines Point to head of Washington Channel, 24 feet deep and 400 feet wide; (c) Anacostia River from Giesboro Point to Anacostia Bridge, 24 feet deep and 400 feet wide, with turning basin 800 feet wide and about 2,400 feet long of same depth opposite Naval Weapons Plant; (d) Anacostia River from Anacostia Bridge 24 feet deep and 200 feet wide to turning basin 400 feet square of same depth at foot of 15th Street S.E. Channel lengths including turning basins are: Virginia Channel, 25,000 feet; Washington Channel, 10,000 feet; and Anacostia River, 15,000 feet; and (e) operation and maintenance of inlet gates and lock and outlet gates of Tidal Basin constructed under a previous project to flush Washington Channel. 24. 25. 28. 30. 31. 32. 33. WICOMICO RIVER, MD Channel 9 feet deep from Main Street Bridge to about 2 miles below. Extend 9-foot depth into north prong from Main Street Bridge to the Salisbury Dam and turning basin. Extend 9-foot depth into south prong to head of navigation at Cathell St., including a turning basin, and extend project down to mouth of river in Monie Bay. A 12-foot channel below the Main Street Bridge. A 14-foot channel, 150 feet wide; depths of 14 feet in the north and south prongs and a basin 6 feet deep at Webster Cove and approach channel thereto of the same depth. Enlarge existing basin at Webster Cove, by dredging an extension 6 feet deep, 100 feet wide, and 200 feet long on each side of existing basin to form a T-shaped harbor. COLONIAL BEACH, VA Sep. 15, Extending and widening the existing Central Beach area, stabilizing the 1980 bank behind the beachfill with vegetation, and constructing four segments of offshore breakwater; and extending and widening of the existing Castle Beach area, constructing three segments of offshore breakwater, removing debris in the beachfill area, and constructing a 100-foot long terminal groin at the southern end of Castlewood Park beachfill. BLACK WALNUT POINT, MD Construct stone revetment from north end of existing (state) shore protection to a point 375 feet north. BLOOMINGTON LAKE, MD & WV Construction of Bloomington Lake project. CUMBERLAND, MD AND RIDGELEY, WV Levees, retaining walls, movable dam, and channel clearing for Cumberland, West Cumberland and South Cumberland, MD and Ridgeley, WV. Levees, wall, channel improvement, remove Chesapeake and Ohio Canal Dam and construct new industrial dam. LACKAWANNA RIVER BASIN, PA Oct. 23, Construction of Aylesworth Creek Lake, Fall Brook Lake, and local pro- 1962 tection works on Lackawanna River at Scranton, Pennsylvania. Rivers and Harbors Committee Doc. 22, 74th Cong., 1st sess.' H. Doc. 20, 51st Cong., 1st sess., and Annual Report 1890, p. 947, H. Doc. 569, 61st Cong., 2nd sess. H. Doc. 1509, 63rd Cong., 3rd sess. Senate Committee Print, 75th Cong., 3rd sess. H. Doc. 619, 81st Cong., 2nd sess.' Detailed Project Report, May 1980 Expanded Reconnaissance Report Sept. 1982 H. Doc. 469, 87th Cong., 2nd sess. H. Doc. 101, 73rd Cong., 1st sess. Report on file in Office, Chief of Engineers. S. Doc. 141, 87th Cong., 2nd sess. 4-32 Documents Sep. 19, 1890 Jun. 25, 1910 Mar. 2, 1919 Jul. 3, 1930 Aug. 26, 1937 Sep. 3, 1954 Dec. 22, 1982 Sec. 14 Jul. 24, 1946 Oct. 23, 1962 Jun. 22, 1936 Jul. 24, 1946 -- BALTIMORE, MD DISTRICT TABLE 4-B (Continued) AUTHORIZING LEGISLATION See Date Section Authorizing in Text Act Project and Work Authorized Documents 34. 35. WYOMING VALLEY, PA Jun. 22, Construction of a levee and floodwall protection system with associated 1936 interior drainage facilities at Plymouth, Kingston-Edwardsville, Swoyersviile- Forty Fort, and Wilkes-Barre and Hanover Township. YORK, INDIAN ROCK DAM, PA Jun. 22, Construction of Indian Rock Dam and channel improvements on Codorus 1936 Creek. Oct.23, 1962 1. Contains latest published maps. 2. Exclusive of portion considered inactive. Inactive portion is widening 35-foot depth channel from 150 to 400 feet from Port Covington to Ferry Bar, widening 27-foot depth channel from 150 to 250 feet to Hanover Street Bridge, and providing a channel 27 feet deep by 250 feet wide to Western Maryland Railway Bridge with an anchorage and turning basin at the upper end. 3. Included in Public Works Administration program September 16, 1933. The site chosen for the inlet under this authorization was that opened just south of Ocean City by natural forces during a severe storm in August 1933. This eliminated the necessity for an 8-foot channel from the inlet to Ocean City. 4. Included in Emergency Relief program 1935. 5. Raising of the north jetty to an elevation of 9 feet above mean low water was accomplished with maintenance funds in 1956. 4-33 RAYSTOWN LAKE, RAYSTOWN BRANCH, JUNIATA RIVER, PA Construction of dam and appurtenant facilities. SOUTHERN NEW YORK FLOOD CONTROL PROJECTS Construction of detention reservoirs and related flood control works for protection of Binghamton, Hornell, Corning and other towns in New York and Pennsylvania. STILLWATER LAKE, LACKAWANNA RIVER, PA Construction of a flood control reservoir. SUSQUEHANNA RIVER FLOOD CONTROL PROJECTS, NY AND PA Construction of Cowanesque and Tioga-Hammond reservoirs, local flood protection works at Elkland, PA, and Nichols, NY and channel improvement at Cortland, NY. Modification in connection with the construction of Cowanesque Lake to relocate the Town of Nelson, PA, to a new townsite. Modification of Cowanesque Lake to include water supply as provided by Section 4 of the Flood Control Act of 1944 (PL 78-534) and Section 301 of Water Supply Act of 1958 (PL 85-500). WEST BRANCH OF SUSQUEHANNA RIVER, PA Construction of three flood control reservoirs. H. Doc. 565, 87th Cong., 2nd sess. H. Doc. 702, 77th Cong., 2nd sess. H. Doc. 702, 77th Cong., 2nd sess. H. Doc. 394, 84th Cong., 2nd sess. H. Doc. 29, 84th Cong., 1st sess. H. Doc. 308, 69th Cong. 1st sess. H. Doc. 702, 77th Cong., 2nd sess. Jun. 22, 1936 modified by Acts of Jun. 28, 1938; Aug. 18, 1941; Dec. 22, 1944; May 17, 1950; and Jul. 3, 1958 Aug. 18, 1941 Jul. 3, 1958 Oct. 22, 1976 Mar. 1, 1983 36. 37. Sep. 3, 1954 38. 39. 40. REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 OTHER AUTHORIZED NAVIGATION PROJECTS TABLE 4-C Cost to September 30, 1985 For Last Full Report See Annual Operation and Project Status Report Construction Maintenance Accotink Creek, VA' Completed 1878 $ 5,000 $ - Anacostia River and Flats2 Deferred 1953 3,910,582 - Annapolis Harbor, MD Completed 1946 34,250' 15,623 Aquia Creek, VA Inactive 1928 52,465' 11,770 Back Creek, MD Completed 1946 23,061 23,072 Betterton Harbor, MD Inactive 1960 3,482 - Black Walnut Harbor, MD Completed 1982 32,631 412,349 Bonum Creek, VA5 Completed 1982 202,0006 144,576 Branson Cove, Lower Machodoc River, VA Completed 1950 15,755 17,675 Breton Bay, MD7 Inactive 1950 47,9248 12,621 Broad Creek River, DE Completed 1964 64,5109 114,373 Broad Creek, MD Completed 1962 28,227 81,219 Cambridge Harbor, MD7 Inactive 1984 195,97410 678,258 Chester River, MD Completed 1984 70,495" 1,339,473 Choptank River, MDI2 Completed 1979 96,796 94,095 Corsica River, MD Completed 1948 39,07113 80,285 Crisfield Harbor, MD Completed 1980 349,1541' 505,393"5 Cypress Creek, MD Completed 1947 3,057 10,528 Duck Point Cove, MD Completed 1982 25,289 293,964 Elk and Little Elk Rivers, MD'6 Completed 1932 90,121" 53,80818 Goose Creek, MD' Completed 1973 75,900 8,312 Herring Creek, MD Completed 1961 284,800"9 66,229 Island Creek, MD Completed 1948 6,230 34,457 Island Creek, St. Georges Island, MD Completed 1981 23,836 328,110 La Trappe, MD Completed 1980 8,064 40,475 Little Creek, Kent Island, MD Completed 1958 23,000's 7,327 Lower Machodoc Creek, VA Completed 1904 9,916 16,485 Lowes Wharf, MD Completed 1984 21,000 275,519 Madison Bay, MD6 Completed 1977 125,550 20,854 Manokin River, MD21 Completed 1919 34,78822 43,534 Middle River and Dark Head Creek, MD Completed 1947 38,71523 23,173 Monroe Bay and Creek, VA Completed 1982 12,460 207,685 Muddy Hook and Tyler Coves, MD' Completed 1984 64,001 360,602 Nan Cove, MD' Completed 1965 34,8612' 22,498 Nanticoke River at Bivalve, MD'6 Completed 1983 240,817 131,878 Nanticoke River (Including Northwest Fork), DE & MD Completed 1984 143,13425 584,777 Nanticoke River, MD Completed 1971 73,243 76,89526 Neabsco Creek, MD Inactive 1978 14,600 - Neale Sound, MD Completed 1982 12,60027 289,770 Neavitt Harbor, MD6 Completed 1968 36,500 28,084 Nomini Bay and Creek, VA 28 Completed 1946 78,446 42,063 Northeast River, MD Completed 1984 28,48929 905,044 Occoquan Creek, VA'16 Completed 1971 66,25330 176,920 Patuxent River, MD' 6 Completed 1905 14,00031 Potomac River and Tributaries at and below Washington, DC, Elimination of Waterchestnut Completed 1977 - 184,394 Potomac River at Alexandria, VA Completed 1965 95,214 506,394 Potomac River at Lower Cedar Point, MD Completed 1920 10,234 6,216 Potomac River at Mt. Vernon, VA'6 Completed 1984 $ 17,000 306,574 Potomac River below Washington, DC Completed 1984 153,836 1,876,673 Potomac River North Side of Washington Channel, DC' Completed 1956 1,744,692"' 27,461" Rock Hall Harbor, MD Completed 1982 1,072,500" 77,113 Shad Landing State Park, MD Completed 1966 33,531"' 6,719 Slaughter Creek, MD Completed 1982 4,140 408,030 St. Catherines Sound, MD Completed 1981 29,947" 253,578 4-34 BALTIMORE, MD DISTRICT OTHER AUTHORIZED NAVIGATION PROJECTS TABLE 4-C (Continued) Cost to September 30, 1985 For Last Full Report See Annual Operation and Project Status Report Construction Maintenance St. George Creek, MD Inactive 1971 - - St. Jeromes Creek, MD Completed 1982 44,35736 371,386 St. Michaels Harbor, MD6 Completed 1964 16,723" 7,742 St. Peters Creek, MD' Completed 1963 46,740 7 17,084 Smith Creek, MD Completed 1936 5,252 3,894 Susquehanna River at Williamsport, PA' Completed 1974 57,03138 41,437 Tilghman Island Harbor, MD Completed 1983 424,80039 378,783 Town Creek, MD Completed 1950 43,220 17,453 Tuckahoe River, MD Completed 1980 9,727 23,489 Tyaskin Creek, MD Completed 1923 16,29740 45,295 Upper Machodoc Creek, VA Completed 1971 20,281 34,777 Warwick River, MD Completed 1984 22,04141 145,911 1. Unconstructed portion of the project was deauthorized 21. Abandonment recommended in 1926 (H. Doc. 467, 69th August 5, 1977. Cong., 1st sess.) 2. Project deferred for restudy. 22. Includes $2,000 expended outside project limits. 3. Includes $8,476 for previous project. 23. Excludes $111,581 expended by Navy Department and 4. Includes $31,065 for previous project. $54,000 from contributed funds. 5. Authorized by Chief of Engineers. 24. Excludes $565 contributed funds. 6. Unconstructed portion of the project is inactive. 25. Includes $5,000 for previous project. 7. Excludes $3,998 contributed funds. 26. Excludes $101,162 Public Health Service funds expend- 8. Includes $37,500 for previous project. ed for waterchestnut removal. 9. Includes $50,000 for previous project. 27. Excludes $1,000 contributed funds. 10. Includes $61,321 for previous project. 28. Unconstructed portion of the project was deauthorized 11. Includes $38,041 for previous project. November 6, 1977. 12. Authorization for the unconstructed portion of the 29. Includes $20,640 for previous project. project was withdrawn by the Chief of Engineers January 30. Includes $25,000 for previous project. 22, 1979. 31. Includes $10,617 for previous project. 13. Includes $30,000 for previous project. 32. Excludes $389,000 contributed funds. 14. Includes $87,740 for previous project. 33. Excludes $672,880 contributed funds. 15. Includes $2,839 for previous project. 34. Excludes $24,125 contributed funds. 16. Unconstructed portion of the project was deauthorized 35. Excludes $600 contributed funds. November 2, 1979. 36. Includes $26,500 for previous project. 17. Includes $79,626 for previous project and excludes 37. Excludes $6,984 contributed funds. $8,414 contributed funds. 38. Excludes $40,000 contributed funds. 18. Includes $24,321 for previous project. 39. Excludes $16,409 contributed funds. 19. Excludes $10,306 contributed funds. 40. Includes $10,158 for previous project. 20. Excludes $1,100 contributed funds. 41. Includes $6,000 for previous project. OTHER AUTHORIZED BEACH TABLE 4-D EROSION CONTROL PROJECTS Cost to September 30, 1985 For Last Full Report See Annual Operation and Project Status Report Construction Maintenance Oxford, MD' Completed 1978 $ 97,7502 - 1. Authorized by Chief of Engineers. 2. Excludes $80,648 contributed funds. 4-35 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 OTHER AUTHORIZED FLOOD CONTROL PROJECTS TABLE 4-E Cost to September 30, 1985 For Last Full Report See Annual Operation and Project Status Report Construction Maintenance Anacostia River and Tributaries, Flood Protection and Navigation Improvements, DC and MD Completed 1980 $ 6,042,325 $1,417,655 Anacostia River and Tributaries, Prince Georges Co., MD2 Completed 1977 1,000,0003 - Bainbridge, NY' Completed 1959 382,000 - Bath, NY5 Completed 1970 638,332 - Bayard, WV' Completed 1965 55,2186 - Bridgewater, VA' Completed 1953 136,500 - Bull Run, PA Completed 1984 2,742,000 - Conklin-Kirkwood, NY' Completed 1955 71,000 - Cortland, NY7 Completed 1970 324,486 - Elkland, PA Completed 1971 1,297,850 - Endicott Johnson City and Vestal, NY Completed 1979 7,034,5348 - Forest Heights, MD' Completed 1964 430,0009 - Fourmile Run, VA Completed 1984 51,780,000 - Greene, NY' Completed 1951 37,000 - Kingston-Edwardsville, PA Completed 1979 4,731,39410 - Kitzmiller, MD' Completed 1965 501,5001 - Latta Brook Rd., NY Completed 1984 115,500 - Lock Haven, PA12 Active 1980 450,00013s - Nichols, NY Completed 1974 1,487,800 - Norwich, NY' Completed 1950 94,500 - Painted Post, NY5 Completed 1970 414,181 - Plymouth, PA Completed 1958 1,911,689" - Savage River Dam, MD Completed 1954 2,271,9391" 33,999 Scranton, PA'6 Completed 1971 2,006,800 - Sunbury, PA Completed 1953 6,063,00017 - Swoyersville-Forty Fort, PA Completed 1968 2,728,113 - Tyrone, PA'8 Deferred 1980 6,401,016 - Unadilla, NY Completed 1970 1,000,00019 - Upper Marlboro, MD' Completed 1965 590,013 - Verona Lake, VA2 0 Deferred 1978 992,000 - Washington, DC and Vicinity Completed 1953 331,92721 - Wilkes-Barre, Hanover Township, PA Completed 1958 3,853,45722 - Williamsport, PA Completed 1979 12,964,89323 - 1. Local interests will not accept operation and maintenance responsibility of the project until the severe erosion and sedimentation of the project caused by tropical storm Eloise is corrected and the project is restored to design condition. 2. Excludes $357,022 contributed funds. 3. Authorized by Chief of Engineers. 4. Unit of Southern New York Flood Control Projects. 5. Excludes $182,672 Public Works Acceleration funds and $4,290 contributed funds. 6. Unit of Susquehanna River Flood Control Projects. 7. Excludes $154,694 contributed funds. 8. Excludes $87,720 contributed funds. 9. Includes $1,162,548 emergency relief funds and excludes $225,877 emergency relief funds expended prior to adoption of project. 10. Excludes $6,616 contributed funds. 11. Authorized for Phase I design memorandum stage of advanced engineering and design. 12. Excludes $481,000 for Phase I funded under General Investigations beginning October 1, 1978. 13. Includes $4,357 emergency relief funds. 14. Includes $200,000 expended from contributed funds. 15. Unit of Lackawanna River Basin Projects. 16. Excludes $140,504 contributed funds. 17. The unconstructed portion of the project was reclassified to the deferred category January 8, 1981. 18. Excludes $132,578 contributed funds. 19. Authorized for the design memorandum stage of advanced engineering and design. 20. Cost of previous project. Includes $106,500 emergency relief funds. 21. Includes $872,715 emergency relief funds. Excludes $36,375 emergency relief funds expended for new work before adoption of project. 22. Includes $1,887 emergency relief funds and excludes $110,835 contributed funds. 4-36 TABLE 4-G Project Almond Village, NY ''2 Broadwater Creek, MD Cadle Creek, MD 2 Channel Connecting Plain Dealing Creek and Oak Creek, MD Coan River, VA Copes Corner Lakes, NY2 Cuckold Creek, MD'4 Cunninghill Cove, MD' Davenport Center Lake, NY 2 Fall Brook Lake, PA5 Genegantslet Lake, NY Governors Run, MD Harpers Ferry, WV Hellens Creek, MD Lake Ogleton, MD Mill Creek, MD Moorefield, WV Sixes Bridge Lake, MD & PA6 -----~-- BALTIMORE, MD DISTRICT DEAUTHORIZED PROJECTS For Last Full Report Date See Annual and Report For Authori 1970 May 26, 1 1941 Flo Control 1949 Nov. 6, 1 1974 Wa Res. Dev. 1949 Nov. 6, 1 1974 Wa Res. Dev. 1940 Aug. 5, 1 1974 Wa Res. Dev. 1937 Aug. 5, 1 1914 Wa Res. Dev. 1970 May 6, 1 1974 Wa Res. Dev. 1978 Jan 22, 1 1960 Riv and Harbor 1977 Jan 22, 1 1960 Riv and Harbo 1970 May 6, 1 1974 Wa Res. Dev. 1970 May 6, 1 1974 Wa Res. Dev. 1954 May 6, 1 1974 Wa Res. Dev. 1950 Aug. 5, 1 1974 Wa Res. Dev. 1937 Aug. 5, 1 1974 Wa Res. Dev. 1950 Nov. 6, 1 1974 Wa Res. Dev. 1950 Nov. 6, 1 1974 Wa Res. Dev. 1949 Nov. 6, 1 1974 Wa Res. Dev. 1941 Oct. 3, 1 1974 Wa Res. Dev. 1974 Dec. 29, 1 1974 Wa Res. Dev. 4-37 Contributed Funds ty Expended 1953 od Act 977 ter Act 977 ter Act 977 ter Act 977 ter Act 981 ter Act 979 ver r Act 979 ver r Act 981 ter Act 981 ter Act 981 ter Act 977 ter Act 977 ter Act 977 ter Act 977 ter Act 977 ter Act 978 ter Act 981 ter Act Federal Funds Expended $ 24,6223 212 112 106,7003 5,720 11,200 286,4003 46,100 214,5783 - 7,9283 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 DEAUTHORIZED PROJECTS TABLE 4-G (Continued) For Last Full Report Date Federal Contributed See Annual and Funds Funds Project Report For Authority Expended Expended South Plymouth Lake, NY 1953 May 6, 1981 100,0363 - 1974 Water Res. Dev. Act Waterway from Little Choptank River to 1939 Aug. 5, 1977 305 - Choptank River, MD 1974 Water Res. Dev. Act West Oneonta Lake, NY2 1970 May 6, 1981 189,1003 - 1974 Water Res. Dev. Act 1. Local cooperation withdrawn, project authorization 5. Unit of Lackawanna River Basin Projects. expired May 26, 1953. * 6. Authorized for the design memorandum stage of ad- 2. Unit of Southern New York Flood Control Projects. vanced engineering and design. 3. Cost for preliminary work only. 4. Project authorization was withdrawn by the Chief of Engineers. RECONNAISSANCE AND CONDITION SURVEYS TABLE 4-H Date Survey Project Completed MARYLAND Cypress Creek August 1985 Herring Creek June 1985 Island Creek September 1985 Nanticoke River (Including Northwest Fork) September 1985 Neavitt Harbor July 1985 Slaughter Creek September 1985 Tilghman Island Harbor April 1985 Town Creek August 1985 Warwick River March 1985 PENNSYLVANIA Williamsport, West Branch, Susquehanna River September 1985 VIRGINIA Monroe Bay and Creek April 1985 Potomac River at Mt. Vernon April 1985 4-38 BALTIMORE, MD DISTRICT INSPECTION OF COMPLETED PROJECTS TABLE 4-I Date Inspected DISTRICT OF COLUMBIA Anacostia River Washington, DC & Vicinity MARYLAND Anacostia River Basin Cumberland Forest Heights Kitzmiller Savage Upper Marlboro NEW YORK Bainbridge Bath Cincinnatus Conklin-Kirkwood Corning-Monkey Run Cortland Endicott-Johnson City & Vestal Greene Nichols Norwich Oneonta Owego Painted Post Port Dickinson Sherburne Unadilla PENNSYLVANIA Elkland Kingston and Edwardsville Loyalsock Milton Plymouth Scranton Sunbury Swoyersville-Forty Fort Tyrone Wilkes-Barre-Hanover Twp. Williamsport S. Williamsport VIRGINIA Bridgewater WEST VIRGINIA Bayard Ridgeley November 1984 November 1984 October 1984 September 1985 October 1984 October 1984 September 1985 October 1984 October 1984 October 1984 October 1984 October 1984 October 1984 October 1984 October 1984 October 1984 October 1984 October 1984 October 1984 October 1984 October 1984 October 1984 October 1984 October 1984 October 1984 September 1985 October 1984 September 1985 September 1985 October 1984 September 1985 September 1985 October 1984 September 1985 October 1984 October 1984 November 1984 September 1985 September 1985 4-39 Project jr NORFOLK, VA DISTRICT* This district comprises the State of Virginia, except the Potomac, Roanoke and Ohio River Basins; the entire area on the eastern shore of Virginia except for the project for Pocomoke River, Maryland and Virginia. On the west shore of Chesapeake Bay, all waterways south of Smith Point, Virginia, at the mouth of the Potomac River except the project for Little Wicomico River, Virginia. North Carolina, only the Chowan River Basin downstream to and including the mouth of the Meherrin River, and the Dismal Swamp Canal Route of the Atlantic Intracoastal Waterway to the Albemarle Sound. West Virginia, only the James River Basin. IMPROVEMENTS NAVIGATION PAGE 1. Atlantic Intracoastal Waterway between Norfolk, VA and St. Johns River, FL .................... 5-2 2. Baltimore Harbor and Channels (Norfolk District)................... 5-2 3. Broad Creek, VA ........................ 5-3 4. Channel to Newport News, VA .............. 5-3 5. Chincoteague Harbor of R efuge, V A .............. .................... 5-3 6. Chincoteague Inlet, VA ................... 5-4 7. Cranes Creek, VA ........................ 5-4 8. Hampton Roads and Harbors of Norfolk and Newport News, VA Collection and Removal of Drift ............... ................. 5-4 9. Hoskins Creek, VA .......................... 5-4 10. Jam es River, VA ............................ 5-5 11. Little Machipongo River, VA ............... 5-5 12. Lynnhaven Inlet, VA ................. .... 5-6 13. Norfolk Harbor, VA .................. .... 5-6 14. Parker Creek, VA ....................... 5-7 15. Supervision of the Harbor of Hampton Roads (Prevention of obstructive and injurious deposits) ....................... .......... 5-7 16. Tangier Channel, VA ..................... 5-8 17. Thimble Shoal Channel, VA ................ 5-8 18. Waterway on the Coast of VA .............. 5-9 19. York River, VA .......................... 5-9 20. Navigation Work Under Special Authorization .......... ............. 5-9 BEACH EROSION CONTROL 21. Virginia Beach, VA ..................... 5-9 22. Beach Erosion Control Work Under Special Authorization ................. 5-9 FLOOD CONTROL PAGE 23. Gathright Dam and Lake Moomaw, VA ...................... 5-10 24. Richmond Filtration Plant, VA ........... 5-10 25. Scottsville, VA ........................... .5-10 26. Virginia Beach Canal Number 2, VA .......................... 5-11 27. Flood Control Work Under Special Authorization ................... 5-11 28. Emergency Flood Control Activities ................. ................. 5-11 GENERAL INVESTIGATIONS 29. Surveys ...................... ......... 5-11 30. Collection and Study of Basic Data ............................. 5-11 31. Continuation of Planning and Engineering ........................... 5-12 TABLES Table 5-A Cost and Financial Statement ..... 5-13 Table 5-B Authorizing Legislation ........... 5-17 Table 5-C Data Relative to the Completed Locks ................. 5-21 Table 5-I) Other Authorized Navigation Control Projects .................. 5-22 Table 5-E Other Authorized Beach Erosion Control Projects .................. 5-23 Table 5-F Other Authorized Flood C ontrol... ............... ......... 5-28 Table 5-G Reconnaissance and Condition Surveys ....................... 5-24 5-1 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Navigation 1. ATLANTIC INTRACOASTAL WATERWAY BETWEEN NORFOLK, VA AND ST. JOHNS RIVER, FL (NORFOLK DISTRICT) Location. Two inland water routes approximately paralleling Atlantic coast south of Norfolk, VA between a point in Southern Branch of Elizabeth River, VA, 2,500 feet upstream of Norfolk & Western Railway bridge and Virginia-North Carolina state line in North Landing River, a distance of 27.2 miles; and 64.6 miles between mouth of Deep Creek, VA and mouth of Pasquotank River, NC. These routes are shown on National Ocean Survey. Chart 12206. Existing project. A channel 12 feet deep at mean low water and 90 to 250 feet wide following Southern Branch of Elizabeth River, 5.2 miles, Virginia Land Cut, 8.3 miles, and North Landing River, 13.7 miles; and construction of tidal guard lock at Great Bridge, VA. It also provides channels 10 feet deep at mean low water and 90 to 100 feet wide in Deep Creek, 3.1 miles, Turners Cut, 4.3 miles and Pasquotank River, 35.1 miles; maintaining Dismal Swamp Canal, 22.1 miles, to about 9 feet deep mean canal level over a width of 50 feet; protection of banks in Turners Cut with sheet piling, and cutting certain sharp points in Pasquotank River to shorten its course. (See Table 5-C at end of chapter on Data Relative to Completed Locks included in Project.) Project includes operating and care of completed locks, dams and bridges, under maintenance. Southern Branch of Elizabeth River and Deep Creek sections of the two routes are tidal, mean range being about 3 feet with extremes of minus 3.5 and plus 9.6 feet. Remaining sections are nontidal with fluctuations of 1 to 2 feet in level due to winds. Cost for new work for completed project was $3,396,276. Protection to canal property at Great Bridge portion is considered inactive and excluded from foregoing cost. Estimated cost of this portion (1954) is $265,000. For details of previous projects, see page 476 of Annual Report for 1938. (See Table 5-B for Authorizing Legislation.) Local cooperation. None required. Terminal facilities. Existing facilities are considered adequate. See Annual Report for 1970. Operations during fiscal year. Maintenance: The following work was accomplished by contract: A five year contract to operate, maintain and repair facilities at the Atlantic Intracoastal Waterway was awarded Feb 83 for $4,117,981. The second year of contract was completed satisfactorily as of Jan 31, 1985. Work was completed on modification 13 to rewire locks at Deep Creek and South Mills. Contract is 70% complete. Total contractor's earnings to date is $2,396,353. Work was completed on a bulk head replacement contract that was awarded in FY 84. Total contractor's earnings reported this. i6al year totalled $300,878. In addition, another bulkhead replacement contract was awarded this FY for $1,004,900. Work is 60% complete and is progressing satisfactorily. Contractor's earnings in FY 85 were $809,000. Maintenance dredging the Dismal Swamp Canal was accomplished during period May 24 - Jun 12, 1985. There were 41,240 cubic yards of credited material removed at a cost of $180,324. Other work performed this fiscal year included engineering and design, supervision and administration, and ordinary operation and maintenance of the project using government plant and hired labor. 2. BALTIMORE HARBOR AND CHANNELS (NORFOLK DISTRICT) Existing project. Provides for deep water approach channels in Baltimore Harbor. Northern portion including Baltimore Harbor is under jurisdiction of Baltimore District. Portion under jurisdiction of Norfolk District is more fully described below. 2A. CAPE HENRY CHANNEL, VA Location. A t mouth of Chesapeake Bay opposite Cape Henry. (See National Ocean Survey Chart No. 12222.) Existing project. A channel about 2.3 miles long, 1,000 feet wide, and 50 feet deep at mean low water through shoal at mouth of Chesapeake Bay opposite Cape Henry. Under ordinary conditions mean range of tide 2.5 feet and extreme 3 feet. Extremes of irregular fluctuation due to combined effect of wind and tides, referred to mean low water, are minus 2 feet and plus 9.5 feet. (See Table 5-B for Authorizing Legislation.) 2B. RAPPAHANNOCK SHOAL CHANNEL, VA Location. In lower Chesapeake Bay opposite mouth of Rappahannock River and about 50 miles northerly from Atlantic Ocean at entrance of Chesapeake Bay. (See National Ocean Survey Chart No. 12225.) Existing project. A channel about 9.9 miles long, 1,000 feet wide, and 50 feet deep at mean low water between contours of that depth in Chesapeake Bay, opposite Rappahannock River. Under ordinary conditions mean tidal range is 2.5 feet and extreme 3 feet. Extremes of irregular fluctuation due to combined effect of wind and tides, referred to mean low water, are minus 2 feet and plus 9.5 feet. (See Table 5-B for Authorizing Legislation.) 2C. YORK SPIT CHANNEL, VA Location. In lower Chesapeake Bay opposite mouth of York River and about 20 miles northerly from Atlantic Ocean at entrance of Chesapeake Bay. (See National Ocean Survey Chart No. 12221). 5-2 NORFOLK, VA DISTRICT Existing project. A channel about 18.2 miles long, 1,000 feet wide, and 50 feet deep at mean low water between contours of that depth in Chesapeake Bay opposite York Spit. Under ordinary conditions mean tidal range is 2.5 feet and extreme 3 feet. Extremes of irregular fluctuation, due to combined effect of wind and tides, referred to mean low water, are minus 2 feet and plus 9.5 feet. For details of previous projects see Annual Report for 1932. (See Table 5- B for Authorizing Legislation.) Local cooperation. None required. Terminal facilities. These three channels form the access between lower and upper Chesapeake Bay. Operations during fiscal year. Maintenance: Condition studies were performed at a cost of $88,000. 3. BROAD CREEK, VA Location. Broad Creek is a small tidal estuary in Middlesex County, VA, 1 mile long, flowing in a northerly direction into the Rappahannock River, which it enters on the right bank about 1 mile upstream of its mouth at Chesapeake Bay. The creek is 61 miles northerly of Norfolk, VA. (See National Ocean Survey Chart No. 12235). Existing project. This provides for a channel 7 feet deep, 100 feet wide and 4,100 feet long from deep water in the Rappahannock River to deep water in Broad Creek. The plane of reference is mean low water. The tidal ranges are: Mean, 1.2 feet; irregular, 2 feet; and extreme, approximately 7.5 feet. The cost to the Federal Government for new work for the completed project was $27,888. The existing project was adopted by the River and Harbor Act of March 2, 1945 (H. Doc. 381, 76th Cong., 1st sess.). The latest published map is in the project document. Local cooperation. Fully complied with except that local interests shall furnish, free of cost to the United States, suitable spoil-disposal areas when and as required for subsequent maintenance, and hold and save the United States free from claims for damages that may result from dredging. Terminal facilities. There are privately owned wharves and landings on the creek, many of which are open to the public by special arrangements. There is one marine railway on the creek. The terminal facilities are considered adequate for present commerce. Operations during fiscal year. Maintenance: A-E contract services totalled $12,000. 4. CHANNEL TO NEWPORT NEWS, VA Location. West of north entrance to Norfolk Harbor Channel connects deep-water and James River with Hampton Roads. (See Coast and Geodetic Survey Chart No. 12245). Existing project. A channel 45 feet deep at mean low water and 800 feet wide from that depth in Norfolk Harbor Channel about 4.5 miles to Newport News and 2 deepdraft anchorage berths opposite Newport News 45 feet deep over 1,200 swing radius. Under ordinary conditions mean tidal range is 2.7 feet and extremes 2.1 and 3 feet. Extremes of regular fluctuations due to combined wind and tides referred to mean low water are minus 2 feet and plus 9.5 feet. For previous project see page 459 of 1938 Annual Report. (See Table 5-B for Authorizing Legislation). Local cooperation. None Required. Terminal facilities. Latest published description of terminal is in Port Series No. 11 revised 1971, part 2 on Ports of Hampton Roads, VA, prepared by Board of Enginers for Rivers and Harbors. Since 1959 piers 3, 4, and 5 have been replaced by a new cargo pier. Container handling facilities have been added and the capability of the port for handling general cargo and coal has increased. Operations during fiscal year. Maintenance: dredging was performed on the 45-ft Anchorages opposite Newport News, VA. There were 176,267 cubic yards of credited material removed at a total cost of $437,185. Ordinary operation and maintenance of the project, including engineering and design, supervision and inspection, was accomplished using government plant and hired labor. 5. CHINCOTEAGUE HARBOR OF REFUGE, VA Location. Chincoteague is located on Chincoteague Island and Accomack County on the Atlantic Coast of Virginia, approximately midway between the entrance to Delaware Bay and the Virginia Capes. Chincoteague Island is separated from the mainland on the west by Chincoteague Channel and from the varying island known as Assateague Island, on the east by Assateague Channel and Assateague Bay. The Harbor of Refuge is at the lower end of Chincoteague Island. (See National Ocean Survey Chart No. 1220.) Existing project. This provides for a channel 8 feet deep, mean low water and 60 feet wide from that depth in the canal at the lower end of Chincoteague Island into an anchorage basin of the same depth 235 feet wide and 650 feet long. The mean range of tide is about 2.6 feet. Greater fluctuations in water level are caused by high wind and storms. (See Table 5-B for Authorizing Legislation). Local cooperation. Fully complied with for initial construction. (See 1962 Annual Report for items of local cooperation.) Terminal facilities. Adequate public terminal facilities have been built by the town of Chincoteague. Additional facilities will be provided as the need develops. 5-3 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Operations during fiscal year. Maintenance dredging was performed, by contract, during Jul 4- 12, 1985. There were 26,205 cubic yards of credited material removed at a total cost of $94,087. Ordinary operation and maintenance of the project, including engineering and design, supervision and inspection were accomplished using government plant and hired labor. 6. CHINCOTEAGUE INLET, VA Location. Chincoteague Inlet at the southern end of Assateague Island provides access to the Atlantic Ocean from the inland waterway near the town of Chincoteague, VA. (See National Ocean Survey Chart No. 12211). Existing project. Provides for a channel 12 feet deep and 150 feet wide across the ocean bar in the Atlantic Ocean and to the mouth of the inlet, a channel 9 feet deep and 100 feet wide from the inlet through the canal and then along Chincoteague Channel to a point approximately 2,000 feet north of the state highway bridge to Chincoteague, a distance of about 6.6 miles. Mean range of tide is about 3 feet. All depths are referred to mean low water. (See Table 5-B for Authorizing Legislation.) Local cooperation. For details see Annual Report for 1974. Terminal facilities. Existing facilities at Chincoteague are considered adequate for current and prospective traffic. Operations during fiscal year. Maintenance dredging was accomplished, by contract, during Apr 21 - May 17, 1985. There were 182,216 cubic yards of credited material removed at a cost of $839,116. Ordinary operation and maintenance, including condition surveys, engineering and design and supervision and inspection, was accomplished with government plant and hired labor. 7. CRANES CREEK, VA Location. Cranes Creek in Northumberland County, Virginia is a small tidal estuary approximately 2 miles long and entering the right bank of the Great Wicomico River 2-1/2 miles upstream to the Chesapeake Bay. The creek is about 76 miles northerly from Norfolk, Virginia. (See Coast and Geodetic Chart No. 12235) Existing project. This provides for a channel 6 feet deep, 80 feet wide, and 1,500 feet long from deepwater in the Great Wicomico River to deepwater within Cranes Creek. The plane of reference is mean low water. The tidal ranges are mean 1.1 feet, irregular 2.0 feet, and extremes approximately 7.2 feet. (See Table 5-B for Authorizing Legislation) Local cooperation. The existing project was approved subject to the conditions that local interest construct and maintain a public wharf with improved approach road, furnish spoil disposal areas for initial dredging, and subsequent maintenance when and as required and hold and save United States free from claims for damages resulting from the improvement. All conditions have been fully complied with. Terminal facilities. There are several small privately owned wharfs and landings on the creek which are considered adequate for present commerce. Operations during fiscal year. A maintenance dredging contract was awarded at the end of fiscal year, with completion scheduled for eary FY 1986. Total contractor's earnings totalled $106,821. Ordinary operation and maintenance of the project, including engineering and design and supervision and inspection, was accomplished. 8. HAMPTON ROADS AND HARBOR OF NORFOLK AND NEWPORT NEWS, VIRGINIA COLLECTION AND REMOVAL OF DRIFT Location. Hampton Roads is a natural harbor 300 miles south of New York and 180 miles south of Washington, D.C. Its principal tributaries are James River, affording a natural deep harbor at Newport News, VA; Elizabeth River, with it Southern, Eastern, and Western Branches providing harbors for Norfolk and Portsmouth, VA; and Hampton Creek, serving the harbor at Hampton, VA. (See National Ocean Survey Charts No. 12248, 12245 and 12253) Existing project. Collection and removal of drift in Hampton Roads and its tributary waters authorizes the Secretary of the Army to allot necessary amounts of work from appropriations for maintenance and improvement of existing river and harbor works or from other available appropriations and that this work shall be carried on as a separate and distinct project. It is wholly a work of maintenance. The purpose of work is to afford relief from variable conditions of obstruction. No advance estimate of the amount of work is required. (See Table 5-B for Authorizing legislation.) Local cooperation. None required. Terminal facilities. See Norfolk Harbor, VA and Channel to Newport News, VA. Operations during fiscal year. Operation of the project resulted in collection and disposal of 73,000 cubic feet of a variety of floating refuse. Total project operations amounted to $178,200. 9. HOSKINS CREEK, VA Location. A tributary 2.5 miles long flowing easterly and entering right bank of Rappahannock River in Essex County, VA, 42 miles upstream from its mouth in Chesapeake Bay and one-half mile downstream from town of Tappahannock, VA. Creek is 102 miles northerly of Norfolk, VA. (See National Ocean Survey Chart 535.) 5-4 NORFPLK, VA DISTRICT Existing project. A channel 10 feet deep from that depth in the Rappahannock River to the highway bridge three-quarters of a mile above the mouth with widths of 100 feet through the bar in Rappahannock River and 80 feet within the creek suitably widened at bends, and a turning basin of same depth 250 feet long and 200 feet wide at public landing one-half mile above the mouth of creek. Improved section is 1.1 miles long. Plane of reference is mean low water. Tidal ranges are: Mean, 1.6 feet; irregular, 2.5 feet; and extreme, about 7.5 feet. (See Table 5-B for Authorizing Legislation.) Local cooperation. Fully complied with. Terminal facilities. There are two bulkhead landings and two wharves. State of VA operates a small boat launching ramp on the creek. Facilities considered adequate for navigation. Operations during fiscal year. Engineering and design for periodic restoration of project dimensions in progress at the beginning of the fiscal year was suspended because an accectable disposal area is not available for maintenance dredging. 10. JAMES RIVER, VA Location. The river is formed by junction of the ('owpasture and ,Jackson Rivers in Botetourt County, VA, flows easterly 34() miles and empties into Hampton Roads at Newport News, VA. (See National Ocean Survey ('harts No. 12248 and 12251.) Existing project. A channel :5 feet deep and :100 feet wide from the mouth to Richmond I)eepwater Terminal. and a channel 18 feet deep and 200 feet wide from the deepwater terminal to Richmond Lock; a mooring basin :5 feet deep, 180 to 220 feet wide and 2,100 feet long along side the channel opposite waterfront at Hopewell: enlargement of the turning basin at Richmond I)eepwater Terminal to 825 feet wide, 2,770 feet long and :15 feet deep: a turning basin in Richmond Harbor 200 feet wide, 600 feet long and 18 feet deep; and construction of spur and training dikes. Depth of channels are referred to mean low water. Total length of channel included in the project is 87 miles, which is the navigable section. Mean tidal ranges under ordinary conditions for different parts of the river are: mouth, 2.6 feet; Jamestown, 2 feet; City Point, 2.6 feet; and Richmond, 3.2 feet. Spring tide ranges under ordinary conditions at the same localities are mouth, 3.1 feet; Jamestown, 2.4 feet; City Point, 3 feet; Richmond, 3.2 feet. Ordinary fluctuations of stage at Richmond, due to floods are 6 to 12 feet above mean low water. Extreme fluctuations are 16 to 32 feet. Flood heights below Richmond diminish rapidly. The extreme according to available information is about 11 feet lower at Dutch gap, 14 miles below and 17 to 18 feet lower, 20 miles below. The estimated (1971) total cost for new work is $71,145,940 including required non-Federal cost for conditions of local cooperation imposed by the River and Harbor Act of 1930, 1945, and 1950, estimated (1939) to be $1,949,700; and by the River and Harbor Act of 1962, estimated (1971) to be $2,950,000. For previous projects, see Annual Report for 1938. (See Table 5-B for Authorizing Legislation). Local cooperation. Fully complied with for conditions imposed by River and Harbor Act of 1930, 1945, and 1950. The conditions imposed by the River and Harbor Act of 1962 have not been complied with. Terminal facilities. River commerce at Richmond is handled by city-owned terminals, city wharves, Richmond dock, and 16 privately-owned wharves within or in the immediate vicinity of Richmond Harbor. The city's Upper Terminal, located on the north bank within the manufacturing section of Richmond, provides for 750 feet of concrete wharf and 80,000 square feet of warehouse and transit shed. The other terminal is located approximately 4 miles downstream from the I'pper Terminal which provides about 1,250 feet of wharf and 2 concrete warehouses with about 190,000 square feet of floor space. This deepwater terminal at the head of the 25-foot deep improved channel serves oceangoing vessels and larger ships engaged in coastwide trading. Below the deepwater terminals the improvement is served by 42 wharves. Richmond terminals and wharves together with wharves between Richmond and the river's mouth are adequate for river's commerce. Operations during fiscal year. Maintenance dredging of the Richmond Deepwater Terminal was completed Sept 1985. There were 105,351 cubic yards of credited material removed at a total cost of $966,000. Dredging the Shoals to Hopewell was in progress at the end of the fiscal year. Engineering and design and supervision and inspection to include condition surveys, was accomplished. 11. LITTLE MACHIPONGO RIVER, VA Location. This river, locally known as Parting Creek, has its source in the marsh of Bell Neck, Northampton County Va., flows in a southerly and easterly direction about 5 miles, and empties into Great Machipongo River, about 12 miles by water from Great Machipongo inlet, and about 28 miles by water from Cape Charles, Va. The drainage area is about 11 square miles. No information is available as to the discharge of this stream. The length of the tidal reach is about 2 miles. The Great Machipongo Inlet and the Great Machipongo River are the waterways connecting with the Atlantic Ocean, and have a controlling depth of 16 feet. Willis Wharf, a town with a population of about 500, is located on the west bank about 1 mile above its junction with the Great Machipongo River. The high-water width varies from about 450 feet at the mouth to 350 feet at Willis Wharf. (See U.S. Coast and Geodetic Survey Chart No. 1221.) Existing project. This project provides for a channel 8 feet deep at mean low water and 80 feet wide from the town 5-5 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 of Willis Wharf to deep water in the river below. The mean .range of tide is about 0.7 foot below mean low water to about 2 feet above mean high water. (See Table 5-B for Authorizing Legislation) Local cooperation: None required. Terminal facilities, at the town of Willis Wharf, there are three wharves with a total wharfage space of about 300 feet, five bulkheads with a total wharfage space of about 1,140 feet, and two marine railways which will accommodate vessels up to 50 feet in length. All facilities are privately owned, being used for packing seafoods and servicing fishing vessels. The wharves have no railroad connections, but are served by local roads connecting with the country and State highway system. The facilities are considered adequate for existing commerce. Operations during fiscal year. Ordinary operation and maintenance, including engineering and design, continued. 12. LYNNHAVEN INLET, VA Location. On south shore of Chesapeake Bay, 5 miles west of Cape Henry, and 10 miles east of Norfolk, VA. Inlet connects Lynnhaven Roads, a part of Chesapeake Bay, with a network of inland waters in northern half of city of VA Beach. (See National Ocean Survey Chart 1222). Existing project. An entrance channel from Chesapeake Bay through Lynnhaven Inlet, 10 feet deep and 150 feet wide; a mooring and turning basin inside of Lynnhaven Inlet, 10 feet deep, 1,100 feet long, and 750 feet wide; a channel 9 feet deep and 90 feet wide to extend from the mooring and turning basin into Broad Bay via Long Creek-Broad Bay Canal and a channel through the Narrows connecting Broad and Ljpkhorn Bays, 6 feet deep and 90 feet wide. Depths are referred to mean low water. Mean ranges of tide in Lynnhaven Inlet is about 2 feet with extreme fluctuations of 1.5 feet below and 9.5 feet above mean low water. Range in Lynnhaven Bay is a little more than 2 feet, in Broad and Linkhorn Bays, fluctuations in water level are caused by local winds. (See Table 5-B for Authorizing Legislation.) Local cooperation. Complied with, except local interests must furnish spoil-disposal areas as needed for future maintenance. For details see page 308 of Annual Report for 1965. Terminal facilities. Existing facilities are considered adequate. For details, see Annual Report for 1970. Operations during fiscal year. Maintenance dredging the Entrance Channel Basin and Long Creek was performed during Sep - Oct, 1985. A total of 198,423 cubic yards of credited material were removed at a total cost of $480,373. Ordinary operation and maintenance of the project, to include engineering and design, was performed. 13. NORFOLK HARBOR, VA Location. Norfolk, Virginia is 187 miles south of Baltimore. Maryland and 30m iles from entrance to Chesapeake Bay at Cape Charles and Cape Henry. Harbor extends 18.: miles from 45-foot contour at Hampton Roads to a point 2.50)0 feet above Norfolk and Western Railway Bridge over Southern Branch of the Elizabeth River. (See National Ocean Survey Charts Nos. 12245 and 12253.) Existing projects. A main channel 45 feet deep, 1,500 feet wide from that depth in Hampton Roads near Fort Wool to a point just south of Norfolk International Terminal Piers; at the same depth 800 feet wide to mouth of Southern Branch of Elizabeth River; and 450 fet wide up this branch to the Belt Line Railroad bridge, including an approach in turning area to same depth and a maximum width of 830 feet opposite Norfolk Naval Shipyard, extending downstream 3,250 feet from Belt Line Railroad bridge 40 feet deep, 375 feet wide and 1 mile long to Norfolk and Western (formerly Virginia Railway bridge); 35 feet deep, 250 feet wide and 3.1 miles long to a point 1,900 feet above Norfolk and Western Railway (Gilmerton's Bridge); 35 feet deep, 250 feet to 500 feet wide to a point 1.6 miles above Interstate 64 high level bridge. A turning basin at the mouth of St. Julian's Creek, 35 feet deep and 400-600 feet square, and a turning basin at the mouth of Main's Creek 35 feet deep and 600 feet square, the upstream end of the project. A channel in Eastern Branch, 25 feet deep, 500feet wide and 1.09 miles long from 40-foot channel to Norfolk and Western Railway bridge; 25 feet deep, 300 feet wide, 0.55 mile long to Campostella Bridge; 25 feet deep, 200 feet wide and 1.2 mile to Norfolk and Western Railway bridge (formerly Virginia Railway bridge); and for maintenance at a depth of 25 feet of existing turning basin and 5.5 acres in extent at head of existing project just below the Norfolk and Western (formerly Virginian) Railway bridge; a channel in Western Branch, 40 foot channel in Elizabeth River, 24 feet deep, 300 feet wide and 0.78 mile long; 24 feet deep and 200 feet wide for 0.37 mile to West Norfolk Highway bridge; 18 feet deep, 150 feet wide, 0.57 mile long. A channel in Scotts Creek between 40-foot channel at mouth and a point 100 feet above former location of Atlantic Coast Line Railroad bridge (about 0.73 miles upstream), 12 feet deep and 100 feet wide. Anchorage areas on west side of 40-foot channel opposite Lamberts Point and south of Craney Island aggregating 173 acres, consisting of 1 anchorage space 1,500 feet square and 38 feet deep; 1 anchorage space 1,500) feet square and 35 feet deep; and 1 anchorage 1,0()00 feet wide, :,000 feet long and 20 feet deep. Another anchorage of 45 acres and 12 feet deep near Pinner Point. Two anchorages opposite Sewells Point 45 feet deep over a swinging radius of 1,200 feet and a trapezoidal shaped disposal area of about 2,500 acres of flats adjacent to the north of Craney Island,enclosed by stonefaced levees, 3 sluiceways in west levee, and an access road. 5-6 NORFOLK, VA DISTRICT -acilities for unloading of hopper dredged material consisting of mooring dolphins: a mooring barge anchorage 10l b (i) , feet . 2 1 feet deel)p, with approach channel 300 to it6 feet; . -feet deep connecting anchorage with Norfolk Harbor 45-foot channel: and a 28-inch discharge pipe line to the leveed area. Facilities for contract rehandling of bucket dredged material consisting of a rehandling basin 1,000 by 1,20 ( feet, 40 feet deep, protected by a spur levee extending 2,:3:50 feet from main levee and provided with approach exit channels, 200 feet wide by 18 feet deep to Norfolk Harbor 45 foot channel and a pipe line trestle from rehandling basin to leveed area. All depths are referred to mean low water. Mean tidal range is 2.7 feet, and extreme is 3.4 feet. Extremes of irregular fluctuations, due to combined effect of tides and winds referred to mean low water on -3.5 feet and +9.6 feet. Eastern Branch, 30-foot channel portion is considered inactive. For details of previous projects see Annual Report for 1938. (See Table 5-B for Authorizing Legislation.) Local cooperation. Fully complied with. Terminal facilities. Latest published description of terminal facilities is in Port Series No. 11 (revised 1971, part II) on Ports of Hampton Roads, prepared by Board of Engineers for River and Harbors. Operations during fiscal year. Maintenance dredging the 45-foot Channel was performed Oct -Dec, 1984. A total of 386,846 cubic yards of material were removed at a total cost of $445,370. In addition, maintenance dredging was also performed on the 45-foot anchorage opposite Newport News during Jul - Aug, 1985. There were 176,267 cubic yards of credited material removed at a total cost of $96,749. Operation and maintenance of the Craney Island portion of the project continued this fiscal year. Work accomplished consisted of continuing raising of division dikes and associated engineering and design and supervision and inspection. Maintenance dredging the Rehandling Basin was completed May 1985. A total of 2,203,1909 cubic yards of credited material were removed. Total Contractor's earnings amounted to $2,644,000 financed from tolls paid by users of the facility. Operation of the Norfolk Harbor portion of the project continued this fiscal year. Condition surveys, report preparation, budgeting and scheduling, engineering and design and supervision and inspection was performed using government plant and hired labor. A bulkhead replacement contract, awarded late FY 1984, was completed. Total contractor's earnings this fiscal year totalled $1,068,170. Maintenance dredging, initiated late FY 1984, was completed on the 45-foot Channel. There were a total of 386,846 cubic yards of credited material removed at a total cost of $445,370. 14. PARKER CREEK, VA Location. Parker Creek empties into the western side of Metompkin Bay in Accomack County, Virginia. It is on the ocean side of Virginia's Eastern Shore, about 20 miles south of Maryland-Virginia State line. Existing project. The existing project, authorized under Section 107 of the 1960 River and Harbor Act, provides for establishment and maintenance of a channel 40 feet wide and 5 feet deep at mean low water from the same depth in Metompkin Bay into the mouth of the creek, a distance of about 2,200 feet or 0.5 mile. The existing project was completed in 1964 at a cost of $15,530 to the Federal Government and $1,350 to local interest. Terminal facilities. There are 9 small privately owned boat landings and two small public landings on the creek. Local cooperation. Fully complied with. Non-Federal contributions amounted to $1,350. Terminal facilities. There are 9 small privately owned boat landings and two small public landings on the creek. Local interests have also constructed a 50-foot public dock with adequate shore facilities. These facilities are deemed adequate for existing and prospective commerce. Operations during fiscal year. Ordinary operation and maintenance of the project, including engineering and design, was accomplished. 15. SUPERVISION OF THE HARBOR OF HAMPTON ROADS (PREVENTION OF OBSTRUCTIVE AND INJURIOUS DEPOSITS) Laws enacted for the preservation of the Harbor of Hampton Roads, VA, is adjacent to the Chesapeake Bay and its tributaries as lies within the State of Virginia and so much of the Atlantic Ocean and its tributaries as lies within the jurisdiction of the United States, within or to the east of the State of Virginia, are administered by the Supervisor of the Harbor of Hampton Roads. Laws relating to the superof waters are the New York Harbor Act of 1888, as amended, the River and Harbor Act of 1899, the Clean Water Act, the Marine Protection, Research and Sanctuary Act of 1972, the Coastal Zone Management Act of 1972, the National Environmental Policy Act of 1969, the Fish and Wildlife Act of 1956, the Federal Power Act of 1966, the Endangered Species Act of 1973, the Deepwater Port Act of 1974, and the Marine Mammal Protection Act of 1972, the Wild and Scenic Rivers Act, the Land and Water Conservation Fund Act. Direct supervision of the harbor was exercised by means of two patrol vessels (376 patrols, 3,008 man-hours) involving debris removal, maintenance of bouys and fish stake limits, investigating reports of sunken vessels and navigational hazards, and providing support for Federal dredging projects. Surveillance of the harbor, the Chesapeake Bay 5-7 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 and its tributaries with respect to the regulatory permit program was conducted by means of three outboard boats, 7- 9 motor vehicles and commercial aircraft for aerial surveys. The outboards were involved in 15 patrols (120 man-hours) involving primarily compliance surveys of permitted dredging projects and evaluating navigational access to proposed pier projects. The motor vehicles were used to conduct environmental evaluations of proposed permit actions, conduct permit compliance inspections, perform jurisdictional determinations, and investigate unauthorized activities. There were unauthorized activities brought to our attention. There were 38 aerial surveys (114 man-hours) for the purpose of photographing proposed project sites, scoping for pre-application meetings and analyzing confirmed violations. An educational program continued in an effort to inform the public of the need and requirements for Department of the Army permits. This program was effected through press releases, public notes , public talks and personal interviews with interested agencies, committees and private industry representatives. Agreements and the monthly joint interagency meeting continued with various Federal, State, and local agencies having related or similar responsibilities and functions to obtain maximum results with minimum costs by eliminating duplication of effort. The joint permit application and the joint public notice adopted between the Norfolk l)istrict and the State of Virginia have continued to result in decreases in the numerous forms of paperwork required to process a permit appliction. The Norfolk D)istrict's Regulatory Branch continued to maintain the Northern Neck Project, the Eastern Shore Project Office, and established an office in Southwest Virginia. Each of the project offices provide readily available (corps personnel to assist waterfront owners, contractors, and the general public with their questions and problems on waterfront construction and the permit requirements of the Corps Regulatory program. D)isposition of leagal actions during the fiscal year: There were 197 complaints of unauthorized activities. Of these, 61 were determined to be valid violations of Federal law. When combined with the remaining 66 carried over from last fiscal year, 263 unauthorized actions were investigated or monitored. Resolution of these violations were as follows: 44 through voluntary restoration; 40 through either the issurance of modified permits or afterthe- fact permits; :13 were referred for legal action; 136 alleged activities were determined not to be violations of Federal law. The remaining 43 are in various stages of resolution or investigation. 16. TANGIER CHANNEL, VA Location. A tidal channel about 2 miles long extending from Tangier Island, Virginia, northeasterly to deepwater in Tangier Sound, Chesapeake Bay and northwesterly to deepwater on Chesapeake Bay. (See Coast and Geodetic Chart No. 12228.) Existing project. A channel 8 feet deep at mean low water and 100 feet wide from 8-foot contour to Tangier Sound to day marker No. 4, and thence 8 feet deep and 60 feet wide to the town of Tangier, with an anchorage basin adjacent of town 400 feet square and 7 feet deep. A channel 7 feet deep and 60 feet wide for about 4,000 feet from the anchorage basin northwesterly across Tangier Island to Chesapeake Bay. Mean range of tide is 1.7 feet and extreme tidal range 4.7 feet. (See Table 5-B for Authorizing Legislation.) Local cooperation. Complied with except that interests must furnish spoil disposal area as needed for future maintenance. Terminal facilities. Accomack County constructed a public dock in 1961. There are four privately owned docks adjacent to existing project and two marine railways. Operations during fiscal year. Maintenance: dredging, by contract, was accomplished during Aug - Sep, 1985. There were 104,841 cubic yards of credited material removed at a total cost of $469,039. Ordinary operation and maintenance of the project to include engineering and design continued using government plant and hired labor. 17. THIMBLE SHOAL CHANNEL, VA Location. In lower portion of ('hesapeake Bay between Hampton Roads and the ocean, 20 miles northeast of center of Norfolk Harbor, extending southeasterly 12 miles from a point 1.25 miles east of Thimble Shoal Lighthouse toward entrance to Chesapeake Bay. (See National Ocean Survey Chart 1222.) Existing project. Provides for dredging a channel 12 miles long, 1,000 feet wide, and 45 feet deep at mean low water with auxiliary channels 450 feet wide and :12 feet deep at mean low water adjoining each side of 1,000-foot channel. Under ordinary conditions mean tidal range is 2.M teet and extreme 3 feet. Extremes of irregular fluctuation, due to combined wind and tides referred to mean low water, and minus 3 feet and plus 7 feet. For details of previous projects see Annual Report for 1932. (See Table 5-B for Authorizing Legislation.) Local cooperation. None required. Terminal facilities. Project serves as an entrance channel to Hampton Roads. See "Norfolk Harbor, VA", "Channel to Newport News, VA", etc. Operations during fiscal year. Ordinary operation and maintenance of the project was accomplished. Engineering and design was accomplished and condition studies were conducted using government plant and hired labor. 5-8 NORFOLK, VA DISTRICT 18. WATERWAY ON THE COAST OF VIRGINIA Location. Between barrier beach along Atlantic Ocean on the east and Virginia portion of mainland peninsula on the west. It extends for 83.7 miles from south end of ('hincoteague Bay through a number of creeks, throughfares, and bays to enter Chesapeake Bay in the vicinity of Fisherman Island, just south of Cape Charles on the southern tip of the peninsula. (See National Ocean Survey ('hart Nos. 12211, 12210, and 12221.) Existing projects. An inland waterway 6 feet deep at mean lo)w water and 60) feet wide from Chesapeake Bay to ('hincoteagute Hay, VA. Mean range of tide is about 3 feet. (;Ireater tfluct uations in water level are caused by high winds and storms. A modification of the project approved during 1970 ) tinder' Section 20)1 of the Flood Control Act of 1965 ait horizes reloc)(ati(on of )portions of the waterway and widening of 10t) feet. (See Table 5-B for Authorizing l egislat io)n. Local cooperation. (Complied with except that local ti te sts are to ifI lrnish spoil disposal areas for future Terminal facilities. Existing facilities are considered id((eqiatc. Fo(r details see Annual Report for 1969. Operations during fiscal year. Ordinary operation and maintenance of the project was accomplished. Engineering and design was accomplished and condition studies were conducted using government plant and hired labor. 19. YORK RIVER, VA Location. This river is formed at West Point, VA, by the confluence of the Mattaponi and Pamunkey Rivers, and flows southeasterly about 41 miles into Chesapeake Bay, which it enters about 20 miles in a northerly direction from Norfolk, VA, and 20 miles in a northwesterly direction from the Atlantic Ocean at Cape Henry. (See National Ocean Survey Chart Nos. 494 and 495.) Existing project. This provides for dredging a channel 22 feet deep at mean low water and 400 feet wide through the bars, and a basin of the same depth at the wharves at West Point, and the construction of a dike on the right bank at West Point to assist in maintaining the channel. The plane of reference is mean low water. Tidal ranges are: Mean 2.2 feet at mouth and 2.9 feet at West Point; and the extreme 3.9 feet at mouth and at West Point; irregular 6 feet at West Point. The existing project was adopted by the River and Harbor Act of June 14, 1880 (Annual Report for 188(), p. 897). It was modified in 1884 and 1887. The latest published map is in the Annual Report for 1894, p. 964. Terminal facilities. There are 18 wharves on the York River of open-pile construction. The facilities are considered adequate for the existing commerce. Operations during fiscal year. Ordinary operation and maintenance of the project was accomplished. Engineering and design was accomplished and condition studies were conducted using government plant and hired labor. 20. NAVIGATION WORK UNDER SPECIAL AUTHORIZATION FY 1985 STUDY/REPORT EXPENDITURE Navigation activities, section 107, Public Law 86-645 There were four Detailed Project Studies in progress at the end of the fiscal year: Bennette Creek, Suffolk, VA ................... $48,501 Jordan Bridge Park, Chesapeake VA .............. 55,066 Kings Creek Northampton Co., VA ............... 83,016 Little Machipongo River, Northampton Co., VA ... 28,579 There were five favorable Appraisal Reports completed during the fiscal year: Nansemond River at Constance Wharf, Suffolk, VA ................................. $7,500 Scotts Creek, Portsmouth, VA ...................... 7,500 Wachapreague Channel, Accomack Co., VA ........ 7,500 Hunting Creek, Accomack Co., VA ................ 7,500 Guilford Creek, Accomack Co., VA ................ 7,500 There were two negative Appraisal Reports completed during the fiscal year: Swift Creek, Colonial Heights, VA ............... $7,500 Eastern Branch of Elizabeth River, VA ............ 7,500 Beach Erosion Control 21. VIRGINIA BEACH, VA Location. On the Atlantic Seaboard, 22 miles north of Virginia-North Carolina State line, 3.5 miles south of Cape Henry, and 19 miles east of Norfolk, VA. (See National Ocean Survey Chart 12207.) Existing project. Federal participation in restoration and protection of shore of Virginia Bea.ch between Rudee Inlet and 49th Street by artificial placement of sand to provide a minimum beach width of 100 feet at elevation 7 feet above mean low water, and maintenance of such beach by periodic replenishment of losses to insure continuous protection; including construction of a groin system to be undertaken at such times as estimated annual charges therewith would be less than the annual cost of beach replenishment alone. The United States shall p)articil)ate in the first cost of the p)roject to the full extent of its p)rol)ortionate share of cost as a landowner, p)lus one third total first cost of restoring and )pro)tectinag llp )tl)liclV-owned sections of the shore. The 1,62 m(dification provided that the 1 nited States shall further )arti(il)ate in periodic beach nourishment of the bieac'h in t he amiunt i)f (ne t hirdt bhec st for 25 years from date of ciomnmne cem(lint ()f iiperat (ion. in placing an initial quantit of nollrishmlent material (((u l to 5-9 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 deficiency in the design beach at that time. Section 102 of the 1962 River and Harbor Act increased Federal participation to one-half of the cost incurred after ()ctober 2: 1962. Estimated Federal cost (1984) is S5,t500,000. Estimated cost to local interests is $5,5)00.000. Construlction of the groin system is not included in the above estimate. T'he 1962 estimate for this work was $549,0()() Federal cost and $531,000 cost to local interests. The 1974 modification provides for structural and nonstructural impro\vements. Structural measures would be p)rovided for the h mile reach of shoreline between Rudee Inlet and 89th street. This would include raising the beach to elevation 10 feet and a width of 100 feet, driving a sheet pile wall just seaward of' t he existing bulkhead from Rudee Inlet to 57th Street: and raising and strengthening sand dunes from 57th to 89th Streets. The estimated cost (1984) of the structural improvements are Federal $28,900,000 and non-Federal $12.800.000. (See Table 5-B for Authorizing Legislation.) Local cooperation. Requirements are described in full on page 5-11 of FY 81 Annual Report. Necessary changes in requirements will be made if the 1974 modification is constructed. - Operations during fiscal year. There were 146,200 cubic yards of material deposited on the project beach. Supervision and administration cost of $16,555 was partially offset by $6,808 received from the cooperating agency for an overpayment in a prior year. Local interests will be reimbursed for the Federal share of fiscal year 1985 costs in fiscal year 1986. 22. BEACH EROSION CONTROL WORK UNDER SPECIAL AUTHORIZATION None this fiscal year. Flood Control 23. GATHRIGHT DAM AND LAKE MOOMAW, VA Location. Gathright Dam is on the Jackson River 43.4 miles upstream of the headwaters of the James River in Allegheny County. The Gathright Dam site is in the reach of the Jackson River known as the Gorge, which is 19 miles upstream of Covington, VA. The Gathright Reservoir extends 12 miles with a full conservation pool (See Falling Spring and Mountain Grove, VA -West VA quadrangles by United States Geological Survey). Existing project. Gathright Dam is a rolled, rock-filled embankment about 1,172 feet in length with a maximum height fo 257 feet. The outlet works consist of a 1,075-footlong tunnel with an inside diameter of 17.5 feet which discharges into a stilling basin 60 feet wide and 144 feet long. A 272-foot-high concrete intake tower is located at the upstream end of the tunnel near the right abutment. An ungated emergency spillway consisting of a chute about 2450 feet long and 100 feet wide is located in a low saddle in the divide at Fortney Branch, about 2.5 miles south of the dam. Discharges through the conservation pool provide water quality. There are 79,900 acre-feet available for flood control located above the conservation pool. (See Table 5-B for Authorizing ILegislation.) Local cooperation. None required. Operations during the fiscal year. Ordinary operation and maintenance of the project continued, which included maintenance of buildings, grounds, service facilities and roads, engineering and design and supervision and administration. 24. RICHMOND FILTRATION PLANT, VA Location. The city of Richmond's Water Filtration Plant lies on the north side of the James River. The plant is separated on the south from the river by the Chesapeake and Ohio Railway embankment. The Old James River and Kanawha Canal forms the plant's northern boundary. The canal is owned by the C & O Railroad Company; however, the city of Richmond has acquired all water rights. (See Richmond and Bon Air, VA quadrangles of geological survey.) Previous projects. None. Existing project. The project will provide for protection of the filtration plant proper. The basic plan provides for enclosing three sides of the plant tying into high ground. The walls will have an average height of about 9 feet with a top elevation of 117.0 m.s.1. The degree of protection provided is equivalent to the Standard Project Flood. A total of 11.5 acres will be protected from the design flood having a recurrence of 360 years over the project economic life of 50 years. Local cooperation. Requirements are described in full on page 5-13 of FY 81 Annual Report. Requirements may change if legislation is enacted regarding new cost-sharing proposals. Operations during fiscal year. Advance engineering and design, in preparation for project construction, was completed. 25. SCOTTSVILLE, VA Location. The town of Scottsville, VA is located in Albemarle and Fluvanna Counties, on the north bank of the James River, 185 miles above its mouth. Previous project. None. 5-10 NORFOLK, VA DISTRICT Existing Project. The town encompasses 130 acres and the 1980 population was 250. It includes small commercial establishments and dwellings including many of historical value. A relatively large tire manufacturing plant is adjacent to the town in Albemarle County and is the largest employer in the area with about 270 employees. Local cooperation. The Town of Scottsville would provide the following: 1. Provide without cost to the United States all lands, easements, rights-of-way, utility relocations and alterations, and highway or highway bridge construction and alterations necessary for project construction. 2. Hold and save the United States free from damages due to the construction works and adjust all claims concerning water rights. 3. Maintain and operate the project after completion without cost to the United States in accordance with regulations prescribed by the Secretary of the Army. 4. Assume full responsibility for all project costs in excess of the Federal cost limitation of $4 million. 5. Prevent future encroachment which might interfere with proper functioning of the project for flood control. This would include the assurances that encroachment on ponding areas inside the wall, or decrease in their storage capacity, will not be permitted. 6. Control future flood damages and exposure to flood hazards by enforcement of ordinances which will permit only uses of the flood plain which are consistent with the flood hazard. This will include areas outside of the proposed protection to be sure other flood problems are not allowed to develop. 7. Establish an ordinance which insures preservation and protection of historic and cultural interests within the town including a responsible local committee interested and knowledgeable in the historic and cultural aspects of Scottsville both within and without the floodplain, which committee will to the best of its powers: a. Arrest deterioration in structures of historic value. b. Assist and encourage future building in the historic district to be of design compatible with the historic structures. c. Assist in the restoration, as occasion exists, some or all of the existing historic structures. Operations during fiscal year. Approval for construction was granted this fiscal year. Engineering and design to include relocation studies, design reviews, and budgeting and scheduling was accomplished. Total contractor's earnings totalled $101,793 by years end. 26. VIRGINIA BEACH STREAMS CANAL NUMBER 2, VA Location. The canal number 2 watershed with a drainage area of about 37 square miles lies within the city of Virginia Beach. The city consists of 255 square miles of primarily low, flat terrain with about 75 percent of the area below elevation 15 feet, mean sea level. The existing canal, from the Eastern Branch of the Lynnhaven River to the North Landing River is about 12 miles long and follows a north-south alignment. (See National Ocean Survey Chart No. 12205.) Existing project. The project will provide for construction of a new canal for a length of 2.6 miles and channelization of an existing canal fro a lenght of 1.1 miles. The canal botom width will range from 45 feet to 80 feet and a depth from -4feet mean sea level to -8 feet mean sea level with a flow capacity great enough to carry a 100 year flood. Its construction will require dredging 741,000 cubic yards of material. Local cooperation. Requirements are described in full on page 5-14 of FY 81 Annual Report. Requirements may change if legislation is enacted regarding new cost-sharing proposals. Operations during fiscal year. Work on plans and specifications, real estate studies and budgeting and scheduling was performed in preparation for construction. 27. FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION None this year. 28. EMERGENCY FLOOD CONTROL ACTIVITIES During FY 85, $75,302 was spent on the National Emergency Preparedness Program. In addition, $726,556 was spent for repairs to the Jamestown Island Seawall. General Investigations 29. SURVEYS Total cost of surveys during the fiscal year amounted to $594,684. Work performed consisted of $216,192 for Navigation Studies; $90,589 for Flood Control Studies; $196,554 for Review of Completed Projects; $7,893 for Deauthorization Review; $35,767 for Projects Authorized for Phase I AE&D; and $47,689 for Coordination Studies with other Agencies. 30. COLLECTION AND STUDY OF BASIC DATA During the fiscal year cost of collection and study of Basic Data was $150,019, consisting of $59,441 for Management Service Unit; $67,513 for Technical Services, and $23,065 for Hurricane Evacuation Study. 5-11 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 31. CONTINUATION OF PLANNING AND ENGINEERING During FY 1985 work continued on the Norfolk Harbor Deepening project. Total project costs amounted to $1,927,525 for this fiscal year. Work continued on the 55-foot channel and anchorage plan. Other work performed included environmental and economic studies, preparation of reports, project management, soils exploration and surveys. Work was accomplished by contract and government plant and hired labor. Completion is scheduled for FY 1986. Work also progressed on the Richmond (Local Protection) Flood Control project. Total project costs amounted to $875,216 for this fiscal year. Work performed included structural and civil engineering, utilities search, hydraulics and hydrology, and geotechnical investigations. 5-12 NORFOLK, VA DISTRICT TABLE 5-A COST AND FINANCIAL STATEMENT See Total Cost Sect. Project Funding FY 82 FY 83 FY 84 FY 85 To 30 Sep 1985 In Tect Atlantic Intracoastal Waterway, between Norfolk, VA and the St. John's River, FL (Norfolk Dist) (Regular Funds) 2. Baltimore Harbor and Channels (Norfolk Dist) (Regular Funds) 3. Broad Creek, VA (Regular Funds) (Contributed Funds) New Work Approp Cost Maint Approp Cost Major Rehab Approp Cost Recreation Approp Cost New Work Approp Cost Maint Approp Cost New Work Approp Cost Maint Approp Cost New Work Approp Cost 2,025,000 2,077,000 1,213,817 2,570,649 1,598,261 1,415,832 2,343,728 2,521,787 1,663,300 1,079,000 696,090 1,885,518 8,198 46,945 8,198 24,945 40,000 200,690 353,314 375,313 88,000 88,001 12,250 12,251 4. Channel to Newport New Work News, VA (Regular Funds) 5. Chincoteague Harbor of Refuge, VA (Regular Funds) 6. Chincoteague Inlet, VA (Regular Funds) (Contributed Funds) Approp Cost Maint Approp Cost New Work Approp Cost Maint Approp Cost New Work Approp Cost Maint Approp Cost New Work Approp Cost 838,964 838,964 - 1,400,715 - 1,400,335 120,377 120,345 639,131 708,366 1,381,182 918,015 620,913 625,959 1,484,896 917,618 5-13 - 3,688,372' - 3,688,372' 43,204,9612 43,152,0222 479,947 479,947 59,871 59,871 8,015,0733 8,015,0733 8,664,4863 8,677,4863 27,888 27,888 494,279 494,279 500 500 8,955,974 8,955,974 5,721,349 5,720,969 49,396 49,396 133,072 132,327 227,000 227,000 5,379,407 5,379,006 3,850 3,850 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 5-A (Cont.) COST AND FINANCIAL STATEMENT See Total Cost to Sect. Project Funding FY 82 FY 83 FY 84 FY 85 30 Sep 1985 In Text 7. Cranes Creek, VA (Regular Funds) 8. Hampton Roads and Harbors of Norfolk and Newport News, VA Collection and Removal of Drift (Regular Funds) 9. Hoskins Creek, VA (Regular Funds) 10. James River, VA (Regular Funds) (Contributed Funds) 11. Little Machipongo River, VA (Regular Funds) 12. Lynnhaven Invet, VA (Regular Funds) (Contributed Funds) New Work Approp Cost Maint Approp Cost Maint Approp Cost New Work Approp Cost Maint Approp Cost New Work Approp Cost Maint Approp Cost New Work Approp Cost New Work Approp. Cost Maint Approp Cost New Work Approp Cost Maint Approp Cost New Work Approp Cost Maint Approp Cost 187,000 175,130 105,493 155,000 169,526 178,241 117,604 120,910 221,568 178,209 - 34,226 - 34,225 59,762 59,763 2,811,254 1,440,000 814,658 1,538,877 2,823,448 1,689,700 1,076,147 1,430,155 50,000 50,000 56,000 19,755 31,512 62,596 62,594 24,629 28,501 472,034 472,033 7,017 2,620 112,358 102,900 28,592 28,593 4,313 9,458 83,414 510,456 83,372 510,498 94,000 84,000 10,000 194,325 182,455 2,755,879 2,755,821 44,100 44,100 671,303 671,303 7,639,9044 7,639,9044 26,211,586 26,102,608 350,456 345,723 5-14 6,274 6,274 15,000 15,000 110,870 110,868 445,354 445,354 2,098,035 2,098,035 98,664 98,580 233,158 233,158 NORFOLK, VA DISTRICT TABLE 5-A (Cont.) COST AND FINANCIAL STATEMENT See Total Cost to Sect. Project Funding FY 82 FY 83 FY 84 FY 85 30 Sep 1985 In Text 13. Norfolk Harbor, VA (Regular Funds) (Contributed Funds) 14. Parker Creek, VA (Regular Funds) 15. Supervision of Harbor of Hampton Roads, VA (Regular Funds) 16. Tangier Channel, VA (Regular Funds) 17. Thimble Shoal Channel, VA (Regular Funds) 18. Waterway on the Coast of VA (Regular Funds) 19. York River, VA (Regular Funds) 20. Virginia Beach, VA (Regular Funds) (Contributed Funds) New Work Approp Cost Maint Approp Cost New Work Approp Cost New Work Approp Cost Maint Approp Cost Maint Approp Cost New Work Approp Cost Maint Approp Cost New Work Approp Cost Maint. Approp Cost New Work Approp Cost Maint Approp Cost New Work Approp Cost Maint Approp Cost New Work Approp Cost New Work Approp Cost 60,811 (-)2,548 6,013 6,310,744 7,305,699 4,627,375 3,816,880 4,777,927 4,648,737 9,369,636 3,739,813 - 21,000 - 20,999 192,000 212,000 230,912 247,759 190,547 176,835 274,501 247,229 434,918 (-)7,881 360,094 66,945 4,211,000 4,791,677 58,731 252,826 39,979 69,860 536,348 536,346 65,729 65,729 1,696,000 1,354,300 175,000 212,000 1,678,264 1,001,236 547,251 211,272 - 16,500 - 16,350 364,000 380,000 430,000 352,585 363,513 384,330 9,747 - 36, 3991,1155 X 639991155 69,528,2566 69,448,1876 179,480 179,480 34,000 15,530 118,644 118,643 4,843,599 4,842,788 116,550 116,550 2,338,430 2,338,428 13,534,967 13,534,967 11,025,733 11,025,732 850,498 850,498 9,862,632 9,861,823 180,904 180,904 194,671 194,521 3,940,195 3,876,013 204,683 204,683 5-15 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 5-A (Cont.) COST AND FINANCIAL STATEMENT See Total Cost to Sect. Project Funding FY 82 FY 83 FY 84 FY 85 30 Sep 1985 In Text 21. Gathright Dam and Lake Moomaw, VA 22. Richmond Filtration Plant, VA (Regular Funds) 23. Scottsville, VA (Regular Funds) 24. Virginia Beach Streams, Canal Number 2, VA New Work Approp Maint Approp Cost New Work Approp Cost New Work Approp Cost New Work Approp Cost (-) 14,000 527,222 729,000 683,273 193,721 833,000 838,172 820,000 914,128 7,000 50,329 - 80,670,527 - 80,670,527 870,000 6,377,000 852,484 6,351,544 - 1,404 - 213,500 3,090,000 - 47,345 151,884 85,000 139,577 33,000 57,446 10,864 15,000 7,088 478,224 478,224 3,303,500 199,229 435,000 420,000 1 Includes $292,096 for previous projects. 2 Includes $52,804 for previous projects. 3 Costs prior to 1942 are included in the project "Baltimore Harbor and Channels, MD (Baltimore District). Costs listed are for York Spit Channel, VA and Cape Henry Channel, VA. SIncludes $763,000 for previous projects. s Includes $2,561,704 for previous projects and new work. 6 Includes $72,039 for previous projects. 5-16 NORFOLK, VA DISTRICT TABLE 5-B AUTHORIZING LEGISLATION Acts Work Authorized Documents ATLANTIC INTRACOASTAL WATERWAY BETWEEN NORFOLK, VA. AND ST. JOHNS RIVER, FLA. (NORFOLK DISTRICT) (See Section 1 of Text) Mar. 3, 1899 Existing project dimensions and original route, waterway from Norfolk, Va. to sounds of North Carolina July 25, 1912 July 25, 1912 Mar. 3, 1925 Original route to Norfolk-Beaufort Inlet section Purchase of Albemarle & Chesapeake Co. Canal Purchase of Lake Drummond Canal (Dismal Swamp Canal) July 3, 1930 Construct a tidal lock at Great Bridge at a cost not to exceed $500,000 June 26, 1934 Operating and care of works of improvement provided for with funds from War Department appropriations for rivers and harbors Mar. 2, 1945 Construct dikes for protection of canal property against floodtides H. Doc. 317, 54th Cong., 1st sess. AR 1896 H. Doc. 131, 55th Congs., 3d sess. AR 1899 H. Doc. 391, 62d Congs., 2d sess. H. Doc. 589, 62d Cong., 2d sess. Rivers & Harbors Comm. Doc. 67th Cong., 2d sess. S. Doc. 23. 71st Cong., 1st sess.' Not available H. Doc. 117, 76th Cong., 1st sess. July 3, 1958 Dec. 31, 1970 July 3, 1958 Dec. 31, 1970 Mar. 3, 1905 Mar. 4, 1913 July 3, 1930 Mar. 2, 1945 July 3, 1958 Dec. 31, 1970 Mar. 2, 1945 June 25, 1910 Aug 8, 1917 Jan 21, 1927 Oct 27th 1965 July 14, 1969 (Sec. 107) BALTIMORE HARBOR AND CHANNELS (NORFOLK DISTRICT) (See Section 2 of Text) CAPE HENRY CHANNEL, VA. (See Section 2 of Text) A channel 42 feet deep, 1,000 feet wide Channel depth increased to 50 feet RAPPAHANNOCK SHOAL CHANNEL, VA. (See Section 2 of Text) Channel 42 feet deep and 800 feet wide Channel width increased to 1,000 feet and depth increased to 50 feet. YORK SPIT CHANNEL, VA. (See Section 2 of Text) Channel 35 feet deep, 600 feet wide Channel width increased to 1,000 feet Channel depth increased to 37 feet Channel depth increased to 39 feet- Channel depth increased to 42 feet Channel depth increased to 50 feet BROAD CREEK, VA. (See Section 3 of Text) Channel 7 feet deep, 100 feet wide CHANNEL TO NEWPORT NEWS, VA. (See Section 4 of Text) Channel 35 feet deep, 400 feet wide Channel 35 feet deep, 600 feet wide Channel 40 feet deep, 600 feet wide Channel 40 feet deep, 800 feet wide, two deep-draft anchorage CHINCOTEAGUE HARBOR OF REFUGE, VA (See Section 5 of Text) Existing Project H. Doc. 86, 85th Cong., 1st sess. Chief of Engineers Report Sept. 21, 1970 H. Doc. 86, 85th Cong., 1st sess. Chief of Engineers Report, Sept. 21, 1970 H. Doc. 186, 57th Cong., .2d sess. H. Doc. 190, 62d Cong., 3d sess. H. Doc. 29, 71st Cong., 1st sess. H. Doc. 741, 79th Cong., 2d sess. H. Doc. 86, 85th Cong., 1st sess. Chief of Engineers Report Sept. 21, 1970 H. Doc. 381, 76th Cong., 1st sess. H. Doc. 550, 61st Cong., 2d sess. H. Doc. 486, 67th Cong., 4th ses. H. Doc. 143, 89th cong., 1st sess. Approved in 1962 5-17 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 5-B (Cont.) AUTHORIZING LEGISLATION Acts Work Authorized Documents July 14, 1960 (Sec. 107) Mar. 2, 1945 May 17, 1950 Mar. 2, 1945 CHINCOTEAGUE INLET, VA (See Section 6 of Text) Existing Project CRANES CREEK, VA (See Section 7 of Text) Entrance Channel 6 fet dep, 80 feet wide HAMPTON ROADS AND HARBORS OF NORFOLK AND NEWPORT NEWS, VA. COLLECTION AND REMOVAL OF DRIFT (See Section 8 of Text) Collection and removal of floating debris in Hampton roads and its tributary waters HOSKINS CREEK, VA. (See Section 9 of Text) A channel 8 feet deep and 100 feet wide in Rappahannock River, 80 feet wide in creek with turning basin 250 feet long and 200 feet wide. Approved in 1972 H. Doc. 687, 76th Cong., 3d sess. Specified in Act Rivers & Harbors Committee Doc. 3,75th Cong., 1 st sess. A channel depth increased to 10 feet and width in creet to 80 feet. H. Doc. 129, 77th Cong., 1 st sess. JAMES RIVER, VA. (See Section 10 of Text) July 5, 1884 Channel 22 feet deep from mouth of Richmond and construct spur and training dikes June 13, 1902 Extension of improvement to Richmond lock gate Mar. 3, 1905 Form a turning basin by widening channel at Richmond July 3, 1930 Channel 25 feet deep mouth to Richmond Deepwater Terminal Aug. 26, 1937 Removal of Trigg cofferdam Mar. 2, 1945 May 17, 1950 Oct. 23, 1962 Turning basin at Richmond Harbor Maintaining turning basin at Richmond Deepwater Terminal Channel depth increased to 35 feet to Richmond Deepwater Terminal LITTLE MACHIPONGO RIVER, VA (See Section 11 of Text) Jul. 3, 1930 Existing Project. Oct. 23, 1962 July 14, 1960 (Sec. 107) Mar. 2, 1907 June 25, 1910 Aug. 8, 1917 Sept. 3, 1954 Oct. 27, 1965 LYNNHAVEN INLET, VA. (See Section 12 of Text) Existing project. Long Creek, Lynnhaven Inlet modification NORFOLK HARBOR, VA. (See Section 13 of Text) Hampton Roads and Elizabeth River Channel 30 feet deep to Navy Yard Depth of 35 feet to Navy Yard. Depth of 40 feet and width of 750 feet to mouth of Southern Branch. Widen 40-foot channel to 1,500 feet from 40-foot contour in Hampton Roads to a point just south of Norfolk International Terminal. 45 feet deep Ft. Wool to Lambert Point, 800 feet wide Norfolk International Terminal to Lambert Point. S. Ex. Doc. 714, 47th Cong., 1st sess. H. Doc. 234, 56th Cong., 1st sess. H. Doc. 234, 56th Cong., 1st sess. H. Doc. 314, 71st Cong., 2d sess. Rivers & Harbors Comm. Doc. 68 74th Cong., 1st sess.2 H. Doc. 738, 77th Cong., 2d sess. H. Doc. 191, 81st Cong., 1st sess. H. Doc. 586, 87th Cong.,2d sess. H. Doc. 260, 71st Cong., 2d sess. H. Doc. 580, 87th Cong., 2d sess Approved in 1982 H. Doc. 381, 59th Cong., 1st sess. H. Doc. 551, 61st Cong., 2d sess. H. Doc. 140, 65th Cong., 1st sess. S. Doc. 122, 83rd Cong., 2d sess. H. Doc. 187, 89th Cong., 1st sess. 5-18 NORFOLK, VA DISTRICT TABLE 5-B (Cont.) AUTHORIZING LEGISLATION Acts Work Authorized Documents June 25, 1910 Aug. 8, 1917 Mar. 30, 1925 Aug. 30, 1935 June 30, 1948 Oct. 27, 1965 Oct. 22, 1976 Mar. 2, 1907 Mar. 3, 1925 July 3, 1930 Mar. 2, 1945 SOUTHERN BRANCH Channel with a depth of 22 and 25 feet. Depth of 40 feet and width of 450 feet from mouth to Belt Line RR Bridge. Channel 30 feet deep and 375 feet wide to Virginia Ry. bridge: thence 25 feet deep and generally 200 feet wide to Norfolk & Western RR Bridge. Depth of 25 feet and width of 200 feet from Norfolk & Western RR bridge to a point 2,500 feet above with a turning basin 500 feet square. Approach and turning area 40 feet deep and a maximum width of 830 feet opposite Norfolk Naval Shipyard: thence a channel 35 feet deep and 375 and 250 feet wide to a point 1900 feet above Norfolk & Western RR bridge and a turning basin 35 feet deep and 600 feet at upstream end. 45 feet deep Belt Line bridge to Old Virginia bridge, 35-foot deep turning basin opposite St. Julians Creek. Extend existing 35-foot project to a channel 35 feet deep and 250 feet wide upstream 1.5 miles to the Norfolk and Portsmouth Belt Line RR bridge and a turning basin at the mouth of Mains Creek 35 feet deep and 800 feet square. EASTERN BRANCH Width of 500 feet and depth of 25 and 22 feet. Removel of shoals at mouth. Depth of 25 feet and width of 200 feet from Norfolk & Western RR bridge to Virginia RR bridge. 30-foot channel to a point opposite terminal of Imperial Tobacco Co. in Berkley. Depth of 25 feet and width of 300 feet from Norfolk & Western RR bridge to Campostella bridge. WESTERN BRANCH Mar. 4, 1913 Channel 24 feet deep and 300 & 400 feet wide to West Norfolk highway bridge. July 3, 1930 For 18-foot channel to a point about 3,000 feet above West Norfolk highway bridge. July 3, 1930 June 25, 1910 Aug. 8, 1917 Sept. 3, 1954 Oct. 27, 1965. SCOTTS CREEK Channel 12 feet deep and 100 feet wide to a point 100 feet above the Atlantic Coast Line RR bridge. ANCHORAGES 30-foot anchorage at Lambert Point 12-foot anchorage at Pinner Point An anchorage 38 feet deep and 1,500 feet square: anchorage 35 feet deep and 1,500 feet square: and an anchorage 20 feet deep, 1,000 feet wide and 3,000 feet long. Two anchorages opposite Sewells Point 45 feet deep with 1,200-foot swinging radius. H. Doc. 551, 61st Cong., 2d sess. H. Doc. 140, 65th Cong., 1st sess. H. Doc. 226, 68th Cong., 1st sess. H. Doc. 182, 73d Cong., 2d sess.2 H. Doc. 545, 80th Cong., 2d sess. H. Doc. 187, 89th Cong., 1st sess. H. Doc. 355, 94th Cong., 2d sess. H. Doc. 373, 59th Cong., 1st sess. Specified in act H. Doc. 226, 68th Cong., 1st sess. H. Doc. 37, 71st Cong., 1st sess.3 H. Doc. 224, 76th Cong., 1st sess. H. Doc. 556, 62nd Cong., 2d sess. H. Doc. 265, 70th Cong., 1st sess. H. Doc. 189, 70th Cong., 1st sess. H. Doc. 551, 61st Cong., 2d sess. H. Doc. 605, 63rd Cong., 2d sess.' S. Doc. 122, 83rd Cong., 2d sess. 1 H. Docs. 187 & 143, 89th Cong., 1st sess. 5-19 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 5-B (Cont.) AUTHORIZING LEGISLATION Acts Work Authorized Documents Jul. 14, 1960 (Sec. 107) Mar. 2, 1919 Jan. 3, 1934 (P.W.A. Act) & Aug. 30, 1935 Mar 2, 1945 Jul. 14, 1960 (Sec. 107) Aug. 8, 1917 Sept. 3, 1954 Oct. 27, 1965 June 25, 1910 Mar. 2, 1945 Oct. 27, 1965 (Sec. 107) June 14, 1880 1884 1887 Sept. 3, 1954 Oct. 23, 1962 Mar. 7, 1974 July 24, 1946 Oct. 22, 1976 1948 (Sec. 205) Oct. 27, 1965 (Sec. 201) PARKER CREEK, VA (See Section 14 of Text) Existing Project TANGIER CHANNEL, VA (See Section 16 of Text) Channel from Tangier Sound and anchorage Modified project dimensions Channel across Tangier Island THIMBLE SHOAL CHANNEL, VA. (See Section 17 of Text) A channel 40 feet deep and 750 feet wide. Channel width increased to 1,000 feet with side channels on either side 32 feet deep and 450 feet wide. Channel 45 feet deep and 1,000 feet wide. WATERWAY ON THE COAST OF VIRGINIA (See Section 18 of the Text) Existing project adopted. Project modified. Project widened to 100 feet, partially relocated, and incorporated in Delaware Bay-Chesapeake Bay Waterway in Delaware-Maryland-Virginia. YORK RIVER, VA (See Section 19 of Text) Project Authorized Project Modified Project Modified VIRGINIA BEACH, VA (See Section 21 of Text) Project authorized. Project modified. Project modification authorized for Phase I Advanced Engineering and Design. GATHRIGHT DAM AND LAKE MOOMAW, VA (See Section 23 of Text) Project authorized. RICHMOND FILTRATION PLANT (See Section 24 of Text) Project Authorized SCOTTSVILLE, VA (See Section 25 of Text) Project Approved VA. BEACH STREAMS, CANAL NO. 2, VA. BEACH, VA. (See Section 26 of Text) Project authorized. Approved in 1964. H. Doc. 107, 63rd Cong., 1st Sess. Rivers and Harbors Comm. Doc. 51, 72nd Cong., 2d sess. H. Doc. 141, 77th Cong., 1st sess. Approved in 1964 H. Doc. 140, 65th Cong., 1st sess. S. Doc. 122, 83d Cong., 2d sess.' H. Doc. 187, 89th Cong., 1st sess. H. Doc. 957, H. Doc. 268, Approved in 60th Cong., 1st sess. 76th Cong., 1st sess. 1970. H. Doc. 186, 83rd Cong., 1st sess. H. Doc. 382, 87th Cong., 2d sess. H. Doc. 365, 92nd Cong., 2d sess. H. Doc. 325, 61st Cong., 2d sess. H. Doc. 543, 94th Cong., 2d sess. H. Doc. 551, 84th Cong., 1st sess. H. Doc. 640, 94th Cong., 2d sess. 1 Contains latest published map. 3 For latest published 2 Included in Emergency Relief Administration Program May 23, 1935. map. See H. Doc. 1246. 62d Cong., 3d Sess. 5-20 NORFOLK, VA DISTRICT TABLE 5-C ATLANTIC INTRACOASTAL WATERWAY BETWEEN NORFOLK VA. AND ST. JOHNS RIVER, FLORIDA: DATA RELATIVE TO THE COMPLETED LOCKS (See Section 1 of Text) Dimensions Greatest Length Depth on Width Avail- Year of able Miter Sills Opened Miles Chain- for Full Character to from Location ber Width Lift Upper Lower of Navi- Cost Norfolk, Va. feet (feet) (feet) (feet) (feet) Foundation gation 12.4 Albemarle and Chesa- 75 600 2.7 1 1 Piles in sand 1932 $499,913 peake Canal (Great and shells Bridge, Va.) 10.7 Dismal Swamp Canal 52 300 12 12 12 Natural earth 1940 $348,879 (Deep Creek) with cutoff walls 33.1 Dismal Swamp Canal 52 300 12 12 13 Natural earth 1941 $372,556 (South Mills, NC.) with cutoff walls '16 feet at mean low water. 5-21 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 5-D OTHER AUTHORIZED NAVIGATION PROJECTS For Last Full Cost to Sept. 30, 1985 Additional Expenditure Project Report, See For New Work Annual Report Expended From For Construction Maintenance Contributed Funds Appomattox River, Va.1 Aberdeen Creek, Va.2 Blackwater River, Va. Active portion2 11 Cape Charles City Harbor, VA2 Carters Creek, Va. Active portion2 3 Channel from Phoebus, Va. to deepwater in Hampton Roads 2 Channel connecting York River, Va. Back Creek to Slaights Wharf 2 Chesconessex Creek, Va. 2 Chincoteague Bay, VA Chowan River, N.C. 2 Cockrells Creek, Va.4 Davis Creek, Va.2 Deep Creek, Accomack Co., Va. Deep Creek, Newport News, Va.2 Dymers Creek, Va. 2 Greenvale Creek, Va.2 Hampton Creek, Va. Horn Harbor, Va.2 Hoskins Creek, Va.2 Jackson Creek, Va.2 Jarvis Creek, Va.4 Kings Creek, Va.4 Lafayette River, Va. 2 Little River (Creek), Va.2 13 Locklies Creek, Va.2 Meherrin River, N.C. 2 Milford Haven, Va.2 Mill Creek, Va.2 Mulberry Creek, Va.2 Nandua Creek, Va. 2 Nansemond River, Va.s Newport News Creek, Va.2 Nottoway River, Va.2 Occohannock Creek, Va. Active portion2 Onancock River, Va.2 Oyster Channel, VA2 Pagan River, Va.2 6 Pamunkey River, Va. Active portion2 Parrotts Creek, Va.2 Portsmouth Harbor, Va. Channel to Nansemond Ordnance Depot2 1980 1975 1975 1984 1951 1944 1950 1968 1984 1975 1949 1971 1974 1980 1953 1980 1981 1964 1977 1971 1979 1957 1982 1966 1928 1950 1950 1937 1950 1950 1978 1962 1981 1951 1963 1984 1950 1964 1957 1947 $870,341 $863,140 109,643 200,893 342,118 622,644 28,398 11,500 14,855 25,516 25,126 107,220 97,612 83,000 288,278 5,582 20,003 186,237 13,987 44,100 8,500 39,259 5,593 242,047 168,623 11,581 47,734 24,568 5,445 2,393 6,988 167,477 135,600 44,295 13,859 187,914 119,117 51,425 151,735 493,708 3,277 32,442 36,874 31,889 371,984 158,323 39,675 2,054,201 4,610 198,420 1,116,952 88,488 622,801 34,437 153,598 442,033 9,560 49,591 32,322 4,346 2,458 39,804 426,777 147,570 78,283 427,233 630,353 284,381 31,376 161,183 37,045 37,771 165,566 66,162 5-22 19,300 1,200 2,500 5,700 4,000 2,910 62,969 500 188,962 16,955 43,000 NORFOLK, VA DISTRICT Queens Creek 2 Quinby Creek, Va. Rappahannock River, Va.9 1012 Rappahannock River at Bowlers Wharf, Va.4 Starlings Creek, Va.2 Taskinas Creek, Va. Totuskey Creek, Va. Tylers Beach, Va.2 Urbanna Creek, Va.2 7 Whitings Creek, Va. Winter Harbor, Va. 2 Willoughby Channel, Va.2 Wishart Point Channel, Va.2 'Includes $22,500 for previous projects. 1979 1983 1983 1950 1981 1975 1970 1982 1963 1971 1981 1953 1975 2Completed. 31n addition, $700 for maintenance was expended from contributed funds. 4Inactive. 5Includes $33,549 for new work and $24,754 for maintenance for previous projects. 61ncludes $20,671 for new work for previous projects. TABLE 5-E 26,949 104,176 414,633 101,803 731,207 1,958,360 66,242 603,632- 7,479 135 - 167,869 450,693 2,000 261,201 404,943- 55,724 106,868- 21,630 112,333 500 171,334 291,048 2,973 8,500 42,485 118,762 102,244 30,625 7In addition, $61,087 was expended for rehabilitation. 8Includes $30,000 for new work and $7,000 for maintenance for previous projects. 91n addition, $168,091 was expended for rehabilitation. 10 lncludes $197,146 for previous new work projects. 1 1 I"n cludes $15,000 for new work for previous projects. 12Includes $113,500 for previous maintenance projects. 13 Federal funds expended by the U.S. Navy for new work. For Last Full Cost to Sept. 30, 1985 Additional Expenditure Project Report, See For New Work Annual Report Expended From For Construction Maintenance Contributed Funds Anderson Park, 1979 $471,474 - $176,671 Newport News, Va. Hampton Institute 1976 $156,906 - $175,845 TABLE 5-F OTHER AUTHORIZED FLOOD CONTROL PROJECTS For Last Full Cost to Sept. 30, 1985 Additional Expenditure Project Report, See For New Work Annual Report Expended From For Construction Maintenance Contributed Funds Buena Vista, Va. 1977 $ 417,900'1- Newmarket Creek, Va. 1970 1,000,000 12,283 $550,097 Norfolk Floodwall, Va. 1973 1,851,933 32,877 516,256 Salem Church Lake, Va. 1976 1,896,7161 2 - - 'Preconstruction planning terminated. 2Includes $144,785 for previous projects. 5-23 OTHER AUTHORIZED BEACH EROSION REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 5-G Name of Project RECONNAISSANCE AND CONDITION SURVEYS Date Survey Conducted CONDITION SURVEYS Chincoteague Inlet Dam Neck Disposal Area Davis Creek Deep Creek - Newport News Hampton Creek James River Richmond Harbor Jordan Point - Harrison Bar - Windmill Point Rocklanding Shoal Weyanoke Point Channel Goose Hill Channel Lafayette River Knitting Mill Creek Appomatox River Little River (Creek) York River - Back Creek to Slaights Wharf Nandua Creek Little Machipongo River Norfolk Harbor Southern Branch of Elizabeth River 35' Channel Eastern Branch of Elizabeth River Sewells Point Anchorage Oyster Channel Whiting Creek Oct 1984 Feb 1985 Oct 1984 Feb 1985 Jan - Feb 1985 Jul 1985 Apr 1985 Apr 1985 Mar 1985 Feb 1985 May 1985 Apr - Jun 1985 Jan - Feb 1985 Jun 1985 Mar 1985 Aug 1985 Aug 1985 Feb 1985 May 1985 Apr 1985 May 1985 RECONNAISSANCE SURVEYS None this fiscal year. 5-24 WILMINGTON, N. C., DISTRICT* This district comprises central and eastern North Carolina and a portion of south-central Virginia, embraced in drainage basins tributary to the Atlantic Ocean from the southern boundary of Virginia to the Shallotte River, inclusive, with exception of the Meherrin River Basin above Murfreesboro, N. C., the Chowan River Basin above the confluence of the Nottaway and Blackwater Rivers, and the Pasquotank River and its tributaries for navigation only. Also included are those portions of the Yadkin- Pee-Dee and Catawba River basins within the state of N. C. as well as a portion of the Atlantic Intracoastal Waterway from the northern boundary of North Carolina to Little River, S. C., and a portion of the waterway from Norfolk, Va., to the Sounds of North Carolina, south of the north shore of Albemarle Sound. IMPROVEMENTS Navigation 1. Aquatic Plant Control (R & H Act of 1965)............. ......... 2. Atlantic Intracoastal Waterway Between Norfolk, Va. and St. Johns River, Fla. (Wilmington District)............ 3. Avon Harbor, N. C..................... 4. Beaufort Harbor, N. C..................... 5. Cape Fear River, N. C. Above Wilmington .... 6. Channel from Back Sound to Lookout Bight, N. C........ .................. 6-5 7. Far Creek, N. C........ ..................... 6-5 8. Lockwoods Folly River, N. C.................6-5 9. Manteo (Shallowbag) Bay, N. C................. 6-6 10. Morehead City Harbor, N. C.. ........... 6-7 11. Ocracoke Inlet, N. C.........................6-7 12. Pamlico and Tar Rivers, N. C.................6-7 13. Silver Lake Harbor, N. C .................... 6-8 14. Waterway Connecting Pamlico Sound and Beaufort Harbor, N. C...................6-8 15. Wilmington Harbor, N. C.....................6-9 Flood Control 16. Ararat River, Mount Airy, N. C...............6-9 17. Cape Fear River Basin, N. C................. 6-10 17A. B. Everett Jordan Dam and Lake............. 6-10 17B. Randleman Lake, N. C.......................6-10 18. Carolina Beach and Vicinity, N. C.............. 6-11 19. Genoa Sewer Facility, Wayne County, N. C........................ 6-11 20. Leesville, Va., Roanoke River, Sec. 32, Demo. Project...................... 6-12 21. Neuse River Basin, N. C....................6-12 21A. Falls Lake, N. C................ ............ 6-12 22. Scuppernong River, N. C....................6-13 Page Page 23. Stuart, Patrick County, Va................6-13 ..6-2 24. Yadkin River Basin, N. C. and S. C............6-13 24A. W. Kerr Scott Dam and Reservoir, N.C................ ............ 6-13 ..6-2 25. Inspection of Completed .6-4 Flood Control Projects.....................6-14 .. 6-4 26. Flood Control Work Under .6-4 Special Authorization....................... 6-14 Multiple-Purpose Projects, Including Power 27. Roanoke River Basin, Va. and N. C........... 27A. John H. Kerr Dam and Reservior, Va. and N. C......................... 27B. Philpott Lake, Va........................ 28. Scheduling Flood Control Reservoir Operations..................... .. 6-14 .. 6-14 .. 6-15 ... 6-15 General Investigations 29. Surveys.................................6-16 30. Collection and Study of Basic Data............ 6-16 Tables Page Table 6-A Cost and Financial Statement.......... 6-18 Table 6-B Authorizing Legislation............... 6-22 Table 6-C Other Authorized Navigation Projects.................. 6-25 Table 6-D Other Authorized Beach Erosion Control Projects....................6-26 Table 6-E Other Authorized Flood Control Projects............................6-27 6-1 REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1985 Page Not Applicable Deauthorized Projects................ 628 Reconnaissance and Condition Surveys.................... 6-29 Page Table 6-I Navigation Work Under Special Authorization.................6-29 Table 6-J Dams and Reservoirs................. 6-30 Table 6-K Special Authorization................. 6-31 Navigation 1. AQUATIC PLANT CONTROL (RIVER AND HARBOR ACT OF 1965) Location. Navigable waters, tributary streams, connecting channels, and other allied waters in Wilmington District. Existing project. The existing project provides for control and progressive eradication of water-hyacinth, alligatorweed, Eurasian watermilfoil, and other obnoxious aquatic plant growths from navigable waters, tributary streams, connecting channels, and other allied waters of the United States, in the combined interest of navigation, flood control, drainage, agriculture, fish and wildlife conservation, public health, and related purposes, including continued research for development of the most effective and economic control measures in cooperation with other Federal and State agencies in accordance with the report of the Chief of Engineers, House Document 251, 89th Congress, 1st session. The project was authorized by Section 302, 1965 River and Harbor Act (H.D. 25, 89th Cong., 1st sess.). The Act provides that research and planning costs shall be borne fully by the United States. Local cooperation. Local interests must agree to hold the United States free from damages that may occur from operations performed in connection with this project, and participate to the extent of 30 percent of the cost of the program. Requirements are being met. Operations and results during fiscal year. New work: Herbicides were applied to two lakes in William B. Umstead State Park, Wake County, North Carolina, to control hydrilla and in the Scuppernong River Basin, in Washington and Tyrrell Counties and the Little River Basin in Pasquotank County, for alligatorweed control. Twelve acres of hydrilla were treated with Aquathol-K in Reedy Creek Lake. Fourteen acres of hydrilla in Sycamore Lake were treated with Fenatrol. No applications were made in Big Lake so that any residual control provided by FY84 Sonar applications could be observed. Successful FY84 alligatorweed control efforts reduced the area which required treatment on the Scuppernong River to 5 acres in 1985. Herbicide application was expanded in 1985 to include navigable tributaries to the Scuppernong River with an additional 3 acres treated in those areas. Three acres of alligatorweed in the Little River Basin were also treated in FY85. Planning efforts included the preparation of a reconnaissance study and report for the inclusion of major drainage canals in the program, initial studies for the inclusion of Elodea as a new problem plant species and investigation of aquatic weed problems in response to requests by others. Control work was accomplished for $15,257. Planning was accomplished at a Federal Cost of $35,183. Studies to develop a cold-tolerant strain of fleabeetle (for control of alligatorweed) were conducted by the NC Department of Agriculture under contract to the Wilmington District. Conditions at end of fiscal year. Two applications of Aquathol-K were required to provide seasonal control in Reedy Creek Lake. Only one herbicide treatment was made on Sycamore Lake. Sonar did not provide satisfactory residual control at Big Lake as expected. It appears that all three lakes in Umstead State Park will require herbicide treatment in FY86. Sterile triploid grasscarp will be stocked in Lake Wheeler for hydrilla control. Other potable water reservoirs will be investigated for stocking in FY85. Alligatorweed control in the Scuppernong and Little River Basins will be required in FY86 but the treatment area within those basins is expected to be less than in FY85. New alligatorweed treatment sites identified in FY84 were added to the program in FY85. Investigations of aquatic weed problems, in response to requests by county governments and municipalities, may result in the addition of new treatment sites and species in future years. 2. ATLANTIC INTRACOASTAL WATERWAY BETWEEN NORFOLK, VA. AND ST. JOHNS RIVER, FLA. (WILMINGTON DISTRICT) Location. The project is located on the east coast of the United States, between Norfolk, Va., and St. Johns River, Florida. The section within Wilmington District begins at the Virginia-North Carolina State line and extends generally southerly and southwestwardly to Little River, S. C., a total of 308 statute miles. (See Coast and Geodetic Survey Charts 830 to 842, inclusive.) Previous projects. For details see Annual Reports for 1915, 1926, 1932, and 1938. Existing project. The authorized project provides for a waterway, 12 feet deep, with widths varying from 90 feet in land cuts to 300 feet in open waters; the construction, operation and maintenance of suitable bridges; saltwaterintrusion preventive measures in the vicinity of Fairfield, N. C.; a channel in Peltier Creek, 6 feet deep and 50 feet wide from the Intracoastal Waterway in Bogue Sound to and including a basin in Peltier Creek, 6 feet deep, 200 feet wide, and 600 feet long; a channel, 6 feet deep and 90 feet wide between the Intracoastal Waterway and the gorge in Bogue Inlet; a channel, 12 feet deep and 90 feet wide to a turning basin, 200 feet wide and 350 feet long, at 6-2 Tables Table 6-F Table 6-G Table 6-H WILMINGTON, N. C., DISTRICT Swansboro; a channel, 6 feet deep and 90 feet wide in New River Inlet, and a connecting channel of the same dimensions to the Intracoastal Waterway near the mouth of New River; a channel, 10 feet deep, and 90 feet wide in New River, between the Intracoastal Waterway and the Seaboard Coastline Railroad bridge at Jacksonville, N. C.; a channel through New Topsail Inlet, 8 feet deep and 150 feet wide and a channel from New Topsail Inlet to the Intracoastal Waterway by way of Old Topsail Creek, 7 feet deep and 80 feet wide; a channel, 7 feet deep and 80 feet wide, in Banks Channel, from New Topsail Inlet, paralleling the barrier beach, to the Atlantic Intracoastal Waterway; a channel, 14 feet deep and 400 feet wide, across the ocean bar at Masonboro Inlet, with suitable jetties at the entrance, thence 12 feet deep and 90 feet wide to the channel of the Intracoastal Waterway at Wrightsville by way of Banks and Motte Channels; a turning basin, 15 feet deep, 300 feet wide, and 700 feet long, on the east side of Banks Channel near Masonboro Inlet, with three 15-pile dolphins therein; a channel, 6 feet deep, 80 feet wide, and 8,000 feet long, to and including a turning basin of the same depth, 130 feet wide and 180 feet long, at Carolina Beach; a yacht basin, 230 feet wide, 450 feet long, and 12 feet deep, at the town of Southport, connected to the waterway by a suitable channel of the same depth; and maintenance of the general navigation features of the North Carolina State Ports Authority Small-Boat Harbor at Southport, consisting of an entrance channel, 150 feet wide and 400 feet long, an eastern harbor-access channel, 70 feet wide and 430 feet long, a western harbor-access channel, 60 feet wide and 185 feet long, to a turning basin, 180 feet wide and 550 feet long, all to a depth of 6 feet. A modification providing for the replacement of five Federally owned and operated highway bridges was authorized in December 1970. A modification providing for 100 percent Federal funding for Walter B. Jones (formerly Wilkerson Creek) and Coinjock bridges was authorized in October 1976. Estimated Federal Cost is $45,800,000 (1985). The six mooring basins along the AIWW were deauthorized August 5, 1977 under authority of Sec. 12, PL 93-251.The south jetty at Masonboro Inlet has an estimated Federal cost of $9,110,000 (1985) and is complete except for the training wall. A Section 111 project to mitigate damages caused by the north jetty was authorized in October 1980 and was completed in April 1981. A modification to provide for a channel 150 feet wide and 8 feet deep extending from the seaward side of the ocean bar at Carolina Beach Inlet to the intersection of the inlet with the AIWW channel was approved by the Chief of Engineers on February 18, 1982, under Section 107 of the 1960 River and Harbor Act. A modification to provide for a channel 150 feet wide and 8 feet deep extending from the seaward side of the ocean bar at Bogue Inlet to the inlet gorge was approved by the Chief of Engineers on September 7, 1983, under Section 107 of the 1960 River and Harbor Act. Length of channels and basins total 347.7 miles. Plane of reference is mean low water. In the waterway north of Neuse River, variations in water surface due to winds seldom exceed 2 feet above or below mean stage. Between Beaufort and the Cape Fear River, normal tidal range varies from 3.5 feet at the inlets to 1 foot at points between. Average range of tide is 4 feet on the ocean side of Bogue Inlet and 2.5 feet just inside the inlet. At New River, tidal range varies from 3.5 feet at the inlet to 1 foot at the head of the marshes and zero at Tar Landing, 31 miles above. From Cape Fear River, N. C., to Little River, S. C., mean tidal range varies between 4.7 feet in Cape Fear River and 4 feet at the intermediate inlets, and 2 feet at points midway between the inlets. On October 15, 1954 (Hurricane Hazel), the tide at Holden Beach reached an elevation of 17.6 feet. (See Table 6-B for Authorizing Legislation.) Local cooperation. Fully complied with to date except for the uncompleted modifications. The State of North Carolina has agreed to keep the bridges toll free and upon completion of each bridge, accept maintenance, replacement, and ownership responsibilities thereof. They have withdrawn their offer to contribute 25 percent of the first cost. The Water Resources Act of 1976 modified the terms of local cooperation to delete the non-Federal cost-sharing requirement for the Walter B. Jones (formerly Wilkerson Creek) and Coinjock bridges. The three remaining bridges were not included in this modification and are awaiting additional authorization to reflect 100 percent Federal funding. Operations and results during fiscal year. New work: Work on replacement of highway bridges cost $4,057,998. Maintenance: During intermittent periods the U. S. sidecasting dredge Merritt removed 48,438 cubic yards from shoals in New Topsail Inlet at a cost of $175,050; 2,240 cubic yards from shoals in Bogue Inlet at a cost of $23,961; 50,960 cubic yards from shoals in New River Inlet at a cost of $88,654; and 62,664 cubic yards from shoals in Carolina Beach Inlet at a cost of $130,211. During intermittent periods the U. S. hopper dredge Currituck removed 54,500 cubic yards from shoals in Bogue Inlet at a cost of $107,265; 96,877 cubic yards from shoals in New River Inlet at a cost of $130,593; and 152,768 cubic yards from shoals in Carolina Beach Inlet at a cost of $247,339. During intermittent periods the U. S. sidecasting dredge Fry removed 45,423 cubic yards from shoals in New Topsail Inlet at a cost of $160,748 and 71,891 cubic yards from shoals in Bogue Inlet at a cost of $184,608. The Fry incurred cost of $958 at Carolina Beach Inlet. During intermittent periods the U. S. debris boat Snell conducted clearing and snagging operations and maintained dredging ranges and mooring facilities at a cost of $181,313. Between October 1,1984 and May 17,1985, the contract dredges Marion and Clinton removed 525,170 cubic yards from shoals in the through channel between the Neuse River and the South Carolina line at a cost of $1,916,574. Between February 26 and April 6, 1985, the contract dredge Hampton Roads removed 176,224 cubic yards from shoals in the through channel in the Alligator - Pungo Rivers at a cost of $553,358. Design costs for dredging in fiscal year 1986 was $58,330. Design costs for deferred dredging was $629. Divers in connection with pipeline dredging at Camp Lejeune cost $3,987. Marking of easements along the AIWW cost $32,865. Mosquito control in disposal areas cost $35,032. Masonboro Inlet 6-3 REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1985 monitoring program cost $20,948. Structural repairs to four remaining highway bridges cost $42,185. Inspection of highway bridges cost $17,478. Preparation of a report on the Masonboro Inlet training wall cost $1,488. Trash removal at Snow's Cut cost $4,876. Archeological investigations of sounds and inlets cost $9,863. Installation of traffic signals at Hobucken and Fairfield and paving at Core Creek cost $21,119. Easement and boundary surveys in New Hanover County cost $242,331. Archeological work at Carolina Beach Inlet, Bear Inlet and Brown Inlet cost $3,776. Waterbird surveys cost $4,026. Reimbursement for damage to bridges was -$154,085. Condition and operation studies cost $485,277. Four highway bridges and utilities were operated and maintained at a cost of $614,405. Condition at end of fiscal year. The project was completed in September 1983 except for the training wall and three tie-up dolphins at Masonboro Inlet and the bridge replacement program. A construction contract for Coinjock Bridge was awarded on September 15,1983 and is scheduled for completion in June 1986. Total cost for existing project to September 30, 1985 was $98,270,555, of which $34,299,771 was for new work including $86,851 in contributed funds and $63,970,784 was for maintenance. 3. AVON HARBOR, N. C. Location. The project is located on the east coast of North Carolina, 9 miles north of Cape Hatteras. (See Coast and Geodetic Survey Chart 1232.) Existing project. The authorized project provides for a direct channel 6 feet deep, 100 feet wide, and 3.5 miles long from the depth in Pamlico Sound southeast to a basin of the same depth, 100 feet wide and 300 feet long at Avon. Plane of reference is mean low water. Variations in the water surface of Pamlico Sound due to winds, seldom range as much as 2 feet above or below mean stage; however, severe windstorms will double or triple that variation. The original project was authorized by the 1945 River and Harbor Act (H.D. 316, 76th Cong., 1st sess.) and modification for direct channel authorized May 5, 1965, under Section 107, River and Harbor Act of 1960. Local cooperation. Fully complied with. Terminal facilities. There are five wharves in the basin at Avon, with a total frontage of about 300 feet. These facilities are considered adequate for present commerce. Operations and results during fiscal year. Maintenance: Engineering and design for pipeline dredging cost $7,474. Project condition surveys cost $1,370. Condition at end of fiscal year. The project was completed July 1965. (For further details, see Annual Report for 1962.) 4. BEAUFORT HARBOR, N. C. Location. The project is just inside Beaufort Inlet, adjacent to Morehead City Harbor. (See Coast and Geodetic Survey Chart 420.) Previous projects. For details see Annual Reports for 1915 and 1938. Existing project. The authorized project provides for stopping erosion at Beaufort Inlet by jetties and sand fences at Fort Macon and Shackleford points and other shore protection; channels 15 feet deep at mean low water and 100 feet wide in Bulkhead and Gallants Channels, except for a depth of 12 feet in the upper 5,000 feet of Gallants Channel; a harbor of refuge in Town Creek 12 feet deep, 400 feet wide, and 900 feet long connected to Gallants Channel by a channe 12 feet deep, 150 feet wide, and 1,400 feet long; a basin 12 feet deep, 600 feet wide in front of the town of Beaufort except for a channel 15 feet deep, 100 feet wide through the basin; a stone bulkhead from Town Marsh across Bird Shoal to the west end of Carrot Island; and a channel in Taylors Creek 15 feet deep, 100 feet wide, extending about 2.6 miles easterly from about opposite Marsh Street in Beaufort to Lennoxville Point at North River, except for an 800-foot-long section at the east end which is 12 feet deep. Total length of channels is 7.3 miles. A modification to provide for a channel 14 feet deep, 70 feet wide, and 1,900 feet long from Bulkhead Channel to a turning basin 14 feet deep, 150 feet wide and 300 feet long near the upper end of Morgan Creek was approved by the Chief of Engineers on August 12, 1983, under Section 107 of the 1960 River and Harbor Act. Average tidal range is 2.5 feet at Beaufort and 3.5 feet at the inlet. (See Table 6-B for Authorizing Legislation.) Local cooperation. Fully complied with to date. Terminal faellities. There are fifty waterfront facilities with a total frontage of 2,000 feet. These facilities are adequate for present commerce. Operations and results during fiscal year. Maintenance: Between May 31 and June 14, the contract dredge Clinton removed 25,697 cubic yards from shoals in Bulkhead Channel at a cost of $64,081. Condition and operation studies cost $12,298. Condition at end of fiscal year. The project was completed in October 1965 except for the Morgan Creek modification which was completed November 12, 1983. (For further details see Annual Report for 1962.) Costs under existing project to September 30, 1985, were $827,040 for new work,including $34,000.contributed funds and $3,003,672 for maintenance, including $168,833 contributed funds, a total of $3,830,712. 5. CAPE FEAR RIVER, N. C. ABOVE WILMINGTON Location. The river is formed by confluence of the Deep and Haw Rivers at Moncure, Chatham County, N. C., and empties into the Atlantic Ocean at Cape Fear, near the southern extremity of the State. (See Coast and Geodetic Survey Chart 426.) Previous projects. For details see Annual Reports for 1915 and 1938. Existing project. The authorized project provides for a 6-4 WILMINGTON, N. C., DISTRICT channel 25 feet deep and 200 feet wide from Wilmington to a turning basin 400 feet wide and 550 feet long at Navassa (2.9 miles); a channel 12 feet deep and 140 feet wide from Navassa to mileboard 30 at Acme, with five channel cutoffs, 12 feet deep and 150 feet wide to eliminate sharp bends; a channel 8 feet deep from mileboard 30 to Fayetteville by constructing three locks and dams and by dredging river shoals; and recreational facilities at the locks and dams. Total length of the project channels is 118.9 miles. 'The project was authorized by River and Harbor Acts of June 25, 1910; June 26, 1934; August 30, 1935; August 26, 1937; October 27, 1965; and Section 4, Flood Control Act of 1944. For further details see Annual Reports for 1962 and 1970. Local cooperation. Fully complied with. Terminal facilities. There are twelve waterfront facilities on the river, with a total frontage of 1,190 feet. Operations and results during fiscal year. Maintenance: During intermittent periods the U. S. debris boat SneUll snagged and cleared and maintained the buoy systems at the locks at a cost of $100,806. Design of portages at the locks cost $4,549. Between December 20,1984 and January 7, 1985, the contract dredge Marion removed 44,069 cubic yards from shoals in the river channel at a cost of $167,694. A feasibility study on spillway repairs cost $1,984. Periodic inspections and evaluation of the three locks and dams cost $22,989. Condition and operation studies cost $33,696. Operation and maintenance of three locks and dams cost $187,477. Condition at end of fiscal year. The project was completed in June 1970. Total costs of existing project to September 30, 1985, were $15,736,502 of which $3,610,454 (including $1,226,385 public works) was for new work and $12,126,048 for maintenance. 6. CHANNEL FROM BACK SOUND TO LOOKOUT BIGHT, N. C. Location. The project is located on the coast of North Carolina, 8 miles east of Beaufort Inlet. (See Coast and Geodetic Survey Chart 420.) Existing project. The authorized project provides for a channel 100 feet wide and 7 feet deep from Back Sound, through Shackleford Banks to Lookout Bight. The project was authorized by River and Harbor Acts of August 26, 1937, and March 2,1945. For details see Annual Report for 1959. Local cooperation. Fully complied with. Terminal facilities. Not required. Operations and results during fiscal year. Maintenance: The dredge Currittck incurred cost of $1,970. Between January 30 and March 6, 1985, the contract dredge Richmond removed 34,615 cubic yards from shoals in the channel at a cost of $137,701. Condition and operation studies cost $6,914. Condition at end of fiscal year. The project was completed in May 1965. 7. FAR CREEK, N. C. Location. Flows easterly from Englehard into Pamlico Sound, about 95 miles south of Norfolk, Va. (See Coast and Geodetic Survey Chart 1232). Existing project. A channel 12 feet deep and 80 to 100 feet wide from Pamlico Sound to highway bridge at Engelhard, with a turning basin 12 feet deep, 200 feet wide and 900 feet long at the head. Project was authorized by River and Harbor Acts of July 3, 1930, and May 17, 1950. For further details see Annual Report for 1962. Local cooperation. Fully complied with. Terminal facilities. Project is served by 12 waterfront facilities with a total frontage of 2,300 feet, all privately owned. Existing facilities are adequate for present commerce. Operations and results during fiscal year. Maintenance: Between March 12 and April 27,1985, the contract dredge Richmond removed 267,516 cubic yards from shoals at a cost of $636,140. Condition at end of fiscal year. Project completed June 1957. 8. LOCKWOODS FOLLY RIVER, N. C. Location. The project is located on the south coast of North Carolina about 12 miles west of Cape Fear River. (See Coast and Geodetic Survey Chart 1236 and Geological Survey Map of North Carolina.) Existing project. The authorized project provides for a channel 100 feet wide and 6 feet deep at low water from the ocean to the bridge at Supply 12.5 miles above, to be obtained by dredging through oyster rocks and mudflats. The completed river portion of the project above the waterway was reclassified to the active category in 1971. Lunar tidal ranges in Lockwoods Folly River are 4.5 feet at the inlet and 2 feet at the head of navigation at Supply. The existing project was authorized by the 1890 River and Harbor Act. (See Annual Report for 1887, page 1099.) A modification to enlarge the channel from 6 to 12 feet deep and from 100 to 150 feet wide across the ocean bar for distance of 4,700 feet was approved by the Chief of Engineers on June 3, 1980, under Section 107 of the 1960 River and Harbor Act. During dredging operations it became apparent that establishment of the 12-foot project would not be possible with currently available equipment. Therefore, the Chief of Engineers, on December 20, 1983, approved the District's recommendation that further construction activity for the Lockwoods Folly Inlet project be suspended until suitable equipment becomes available and that the project be maintained at an 8-foot project depth in the interim. Local cooperation. For the new modification local interest must: (a) pay, contribute in kind, or repay with interest, one-half of the first costs of construction allocated to recreational boating, an amount presently estimated at $23,500; (b) hold and save the United States free from damages resulting from changes in groundwater levels, saltwater intrusion, or wave action due to the construction 6-5 REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1985 works, except damages due to the fault or negligence of the United States or its contractor; (c) provide without cost to the United States all lands, easements, and rights-ofway necessary for the construction and subsequent maintenance of the project and for aids to navigation upon the request of the Chief of Engineers and, (d) provide depths in berthing areas commensurate with the project depths, and provide service facilities. Terminal facilities. Thirty-one piers and wharves on the Atlantic Intracoastal Waterway at Holden Beach, about 1.25 miles west of Lockwoods Folly Inlet, with a total frontage of about 1,980 feet available. At Dixons Landing, about 2 miles upstream of the inlet, there are five wharves with a total frontage of 240 feet. Numerous natural landings are used for loading and unloading small boats. Berthing space in the vicinity of Lockwoods Folly Inlet totals about 2,220 feet. Facilities are considered adequate for present commerce. Operations and results during fiscal year. Maintenance: During intermittent periods the U. S. hopper dredge Curritusck removed 92,236 cubic yards from shoals in Lockwoods Folly Inlet at a cost of $143,028. During intermittent periods the U. S. sidecasting dredge Merritt removed 25,200 cubic yards from shoals in Lockwoods Folly Inlet at a cost of $58,012. The U. S. debris boat Snell repaired dredge moorings at a cost of $12,600. Archeological investigations of the blockade runner Bendigo cost $9,889. Condition and operation studies cost $8,762. Condition at end of fiscal year. The active portion of the project was completed in June 1965 except for the latest modification. Work was initiated on the latest modification on September 23, 1982, with a depth of 8 feet being reached in October 1982. The project will be maintained at the 8-foot depth until suitable equipment for deepening to 12 feet becomes available. 9. MANTEO (SHALLOWBAG) BAY, N. C. Location. The project is located on the northeastern side of Roanoke Island, North Carolina. (See Coast and Geodetic Survey Chart 1229.) Existing project. The authorized project provides for a channel 14 feet deep and 400 feet wide from the Atlantic Ocean through Oregon Inlet with connecting 12-foot channels, 100 feet wide, to Pamlico Sound, Manteo, arid Wanchese; and a channel 6 feet deep and 100 feet wide connecting the Manteo-Oregon Inlet Channel with Albemarle Sound. Length of channels is 25.4 miles. A newly authorized modification provides for stabilization of Oregon Inlet with a dual rubble-mound jetty system, including means for sand transfer to the downdrift beach; a channel, 20 feet deep and 400 feet wide, through the ocean bar at Oregon Inlet; a channel, 14 feet deep and 120 feet wide, from the gorge in Oregon Inlet to and through Roanoke Sound to and including a 15-acre basin of the same depth at Wanchese; and a channel 10 feet deep and 100 feet wide from the 12 foot deep channel in Manteo (Shallowbag) Bay through Roanoke and Albemarle Sounds to deepwater near the northern end of Croatan Sound. The 12 foot Croatan Sound channel has been deferred due to lack of economic justification. The estimated Federal cost for the modification is $103,000,000 (1985). The project was authorized by River and Harbor Acts of June 25, 1910; October 17, 1940; May 17, 1950; and December 31, 1970; and under Section 107 of the 1960 River and Harbor Act. Local cooperation. For the new modification, local interests must: (a) provide all lands, easements, and rightsof- way for construction and subsequent maintenance of the project, including suitable areas required for initial and subsequent disposal of spoil and also necessary retaining dikes, bulkheads, and embankments therefor, or the cost of such retaining works; (b) hold and save the United States free from damages due to the construction works and subsequent maintenance; (c) continue to provide and maintain adequate terminal and transfer facilities, open to all on equal terms, in accordance with plans approved by the Chief of Engineers; (d) provide and maintain necessary mooring and berthing facilities in any enlarged basin, open to all on equal terms, in accordance with plans approved by the Chief of Engineers; (e) provide and maintain depths in berthing areas and local access channels serving the terminals commensurate with depths provided in the related project areas; (f) accomplish such alterations as required in sewer, water supply, drainage, electrical powerlines, telephone lines, or other utility facilities as well as their maintenance; (g) establish a competent and properly constituted public body empowered to regulate the use, growth, and free development of the harbor facilities, with the understanding that said facilities will be open to all on equal terms; (h) and establish regulations prohibiting the discharge of untreated sewage, garbage, and other pollutants in the water of the harbor by the users thereof, which regulations shall be in accordance with applicable laws or regulations of Federal, State, and local authorities responsible for pollution prevention and control. Reasonable assurances have been received. The State of N. C. has constructed the Wanchese Harbor portion and was reimbursed under Sec. 215, PL 90-483. Terminal facilities. The project is served by 33 waterfront facilities with a total frontage of 3,320 feet. Additional wharves and facilities will be provided with the enlarged basin at Wanchese. Operations and results during fiscal year. New work: Engineering and design for the modification cost $169,188. Maintenance: During intermittent periods the U.S. sidecasting dredge Schweizer removed 377,790 cubic yards from shoals in Oregon Inlet at a cost of $774,465. During intermittent periods the U.S. sidecasting dredge Merritt removed 305,466 cubic yards from shoals in Oregon Inlet at a cost of $540,806. During intermittent periods the U.S. debris boat Snell repaired dredging ranges and moorings at a cost of $34,735. The Fry incurred cost of $958. Between March 16 and May 17, 1985, the contract dredge Marion removed 18,934 cubic yards from shoals in the channel from Manteo to Wanchese at a cost of $138,845. Between December 6,1984 and January 20,1985, the contract dredge Richmond removed 133,487 cubic 6-6 WILMINGTON, N. C., DISTRICT yards from shoals in Old House Channel at a cost of $384,949. Between October 1, 1984 and January 5, 1985, the contract dredge Mermentau removed 456,321 cubic yards from shoals in Oregon Inlet at a cost of $2,637,837. Between August 4 and 27, 1985, the contract dredge Northerly Island removed 283,507 cubic yards from shoals in Oregon Inlet at a cost of $491,592. Cost in connection with prior year hopper dredging was $1,137. Engineering and design for expansion of disposal islands cost $2,550. Litigation cost on the lawsuit brought by the owners of the fishing vessels Brothers Pride and Lois Joyce was $52,584. Condition and operation studies cost $106,087. Contributed funds of $54,000 were expended for diking in connection with pipeline dredging. Between March 16 and May 17, 1985, the contract dredge Marion removed 166,358 cubic yards from shoals in the channel from Manteo to Wanchese to allow passage of the vessel Elizabeth II. This work was accomplished with contributed funds from the State of N. C. at a cost of $911,826. Condition at end of fiscal year. The project is complete except for the latest modification. (For further details, see Annual Report of 1962.) 10. MOREHEAD CITY HARBOR, N. C. Location. The project is located on the northern shore of Bogue Sound, adjacent to Beaufort Inlet. (See Coast and Geodetic Survey Chart 420.) Previous project. For details see page 470 of Annual Report for 1935. Existing project. The authorized project provides for deepening of the channel, from the 42-foot-depth contour in the Atlantic Ocean through the ocean bar to the gorge in Beaufort Inlet, to 42 feet over a bottom width of 450 feet, thence to a depth of 40 feet in the east leg of the turning basin including the 1,200-foot diameter turning area, with widths of 600 feet in the cutoff channel, and 400 feet wide to the turning basin and connecting shallow-draft channels. Project deepening was completed on August 2, 1978. Jetties at Beaufort Inlet were reclassified to the "active" category on March 8, 1972. The estimated Federal cost is $54,700,000 (1985) for the jetties. In general the project as it now exists was authorized by the 1958 River and Harbor Act (S.D. 54, 84th Cong., 1st sess.) and the River and Harbor Act of December 31, 1970. For further details see Annual Report for 1962. Local cooperation. Fully complied with except for construction of the jetties which requires that all lands needed for construction be provided without cost to the United States. Terminal facilities. Twenty-six waterfront facilities serve the port, with a total frontage of 1,250 feet. Marine terminals provide 5,300 feet of berthing space, with a depth alongside of 35 feet, and facilities for transfer of cargoes between rail and water carriers. Improvements to facilities were completed in 1969. For further details see Port Series No. 12, revised 1980, Corps of Engineers. Operations and results during fiscal year. Maintenance: Between March 8 and 28, 1985, the contract dredges Cherokee and Clinton removed 153,625 cubic yards from shoals in the harbor at a cost of $361,169. Between June 10 and July 19,1985, the contract dredge Sugar Island removed 583,181 cubic yards from shoals in the ocean bar at a cost of $1,074,775. Cost in connection with prior year hopper dredging was $131,768. Engineering and design for beach disposal of Brandt Island cost $27,029. Environmental studies for designation of ocean dredged material site cost $2,818. Condition and operation studies cost $148,117. Contributed funds of $55,000 were expended for diking on pipeline dredging. Condition at end of fiscal year. The existing project is complete except for the jetties. (For further details, see Annual Report for 1962.) Total cost of the existing project to September 30,1985, was $40,961,615 of which $6,501,569 was for new work (including $553,477 public works funds) and $34,460,046 for maintenance, including $751,711 contributed funds. 11. OCRACOKE INLET, N. C. Location. The inlet connects Pamlico Sound with the Atlantic Ocean, about 30 miles southwest of Cape Hatteras and 43 miles northeast of Cape Lookout. (See U.S. Coast and Geodetic Survey Chart No. 1232.) Existing project. The authorized project provides for a channel across the ocean bar 18 feet deep and 400 feet wide, and construction of a jetty extending from Ocracoke Island to the Atlantic Ocean. Construction of the jetty has been deferred for restudy. The project was authorized by the River and Harbor Act of July 14, 1960. For further details, see Annual Report for 1962. Local cooperation. Fully complied with. Terminal facilities. None required. Operations and results during fiscal year. Maintenance: The U.S. sidecasting dredge Schweizer incurred cost of $450. The U. S. sidecasting dredge Fry incurred cost of $1,289. Condition and operation studies cost $13,002. Condition at end of fiscal year. Construction was completed in August 1971. 12. PAMLICO AND TAR RIVERS, N. C. Location. The two names apply to the same river, known as the Tar above and as the Pamlico below Washington, N. C. This stream rises in Person County, flows southeasterly 180 miles to Washington, thence 38 miles to Pamlico Sound. (See Coast and Geodetic Survey Chart 537.) Previous project. For details see page 502 of Annual Report for 1938. Existing project. A channel 12 feet deep at mean low water and 200 feet wide from 12-foot contour in the river below Washington to Atlantic Coastline Railroad bridge at Washington; thence 12 feet deep and 100 feet wide to a turning basin of same depth, 200 feet wide, 300 feet long, in Hardee Creek, 1,500 feet above its mouth; thence 6 feet 6-7 REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1985 deep, 75 feet wide to Greenville; thence 20 inches deep, 60 feet wide to Tarboro; and thence to clear the natural channel to Little Falls. Project was authorized by River and Harbor Acts of August 14,1876; March 3,1879; August 11, 1888; March 2,1907; July 25,1912; July 3,1930; and August 26, 1937. For further details see Annual Report for 1962. Local cooperation. Fully complied with. Terminal facilities. There are 54 wharves on the portion of this river under improvement, of which 34 are along the waterfront at Washington, 19 between Washington and the mouth, and only 1 in usable condition above Washington. They have a frontage of 3,570 feet. Facilities are considered adequate for existing commerce. Operations and results during fiscal year. Maintenance: The U. S. debris boat Snell conducted clearing and snagging operations at a cost of $44,100. An environmental assessment and a report to determine the economic justification of the project cost $68. Condition at end of fiscal year. Project is complete. (For details see Annual Report for 1962.) 13. SILVER LAKE HARBOR, N. C. Location. The project is located at the southwest end of Ocracoke Island, a portion of the Outer Banks on the southeast coast of North Carolina, separating Pamlico Sound from the Atlantic Ocean. (See Coast and Geodetic Survey Chart No. 1232.) Existing project. The authorized project provides for basin depths of 12 feet in Silver Lake Harbor; an entrance channel 12 feet deep and 60 feet wide, from the basin to Teaches Hole Channel; a channel, 12 feet deep and 150 feet wide, from the entrance channel through Big Foot Slough Bar to the 12-foot contour in Pamlico Sound; a channel, 12 feet deep and 150 feet wide, from the entrance channel through Teaches Hole Channel to the gorge in Ocracoke Inlet; a channel, 12 feet deep and 150 feet wide, across Bluff Shoal; and for rubble-mound training walls on the north and south sides of the entrance channel, 300 feet and 400 feet long, respectively. Mean tidal ranges are 1.9 feet in the throat of Ocracoke Inlet and 1 foot at Ocracoke. Variations in the water surface of Pamlico Sound are generally due to winds and seldom exceed 1 or 2 feet above or below mean stage. Severe storms have raised the water surface as much as 7 feet above normal water level at Ocracoke. (See Table 6-B for Authorizing Legislation.) Local cooperation. Fully complied with. Terminal facilities. Twelve waterfront facilities serve the harbor. These facilities are adequate for existing commerce. Operations and results during fiscal year. Maintenance: Between December 8, 1984 and January 22,1985, the U. S. sidecasting dredge Fry removed 34,210 cubic yards from shoals in the harbor at a cost of $122,309. Between August 5 and 22, 1985, the contract dredge Richmond removed 51,271 cubic yards from shoals in Big Foot Slough Channel at a cost of $205,982. Condition and operation studies cost $9,964. Condition at end of fiscal year. The project was com pleted July 28, 1970. (For further details see Annual Report for 1961.) 14. WATERWAY CONNECTING PAMLICO SOUND AND BEAUFORT HARBOR, N. C. Location. The project is located in Core Sound, west of the outer banks of eastern North Carolina. (See Coast and Geodetic Survey Charts Nos. 420 and 1233.) Existing project. The authorized project provides for a through channel to Core Sound 7 feet deep and 75 feet wide from Pamlico Sound to Beaufort Harbor; an alter native route of the same dimensions through Back Sound by way of channels at the east and west ends of Harkers Island; a channel 7 feet deep and 70 feet wide from the through channel to the local harbor at Cedar Island, in cluding the authorized passage and future maintenance of a channel through the existing private basin, and an access channel 6 feet deep, 50 feet wide and about 400 feet long tc a basin the same depth, 60 feet by 100 feet; a channel 7 feet deep and 75 feet wide from the through channel to Atlan tic; a channel 7 feet deep and 75 feet wide, with a basin 200 feet by 500 feet, the same depth, at Sealevel; a channel 1 feet deep and 75 feet wide, with basin 150 feet by 130 feet the same depth, at Davis; a channel 6 feet deep and 60 feet wide with a basin 100 feet by 600 feet, the same depth, at Marshallberg; an entrance channel 6 feet deep and 60 feel wide, from Back Sound to harbor of refuge 120 feet by 250 feet, the same depth in Brooks Creek at the west end of Harkers Island; and a channel 7 feet deep and 70 feet wide, from the existing side channel at Atlantic, N.C., to the mouth of Little Port Brook; thence 7 feet deep and 50 feel wide, along the Brook to a basin 600 feet long, 180 feel wide, and 7 feet deep, with a breakwater, beginning at a point between the mouth of Little Port Brook and White Point, running along the channel approximately 2,000 feet The project is complete except for 7-foot modification tc Davis, N. C., which was deauthorized April 6,1982, by the Chief of Engineers due to the inability of local interest tc provide the terms of local cooperation. Plane of reference is mean low water. The length of the authorized channels is about 50.6 miles. (See Table 6-B for authorizing legisla tion.) Local cooperation. Fully complied with to date for comn pleted portion. Terminal facilities. Sixteen small wharves serve the waterway. Additional facilities are needed along Core Sound. Operations and results during fiscal year. Maintenance Between January 30 and March 6, 1985, the contrac dredge Richmond removed 48,512 cubic yards from shoalh in Atlantic Harbor at a cost of $188326. Engineering and design for pipeline dredging cost $7,278. Project conditior surveys cost $3,233. Condition at end of fiscal year. The project was com pleted in September 1972 except for the modification tc Davis, N. C., which has been deauthorized. (For furthe details, see Annual Report for 1961.) 6-8 WILMINGTON, N. C., DISTRICT 15. WILMINGTON HARBOR, N. C. Location. The project is located on the Cape Fear River, on southeast coast of North Carolina, between the Atlantic Ocean and Wilmington, North Carolina. (See Coast and Geodetic Survey Chart No. 426.) Previous projects. For details, see page 1804 of Annual Report for 1915 and page 533 of Annual Report for 1938. Existing project. The authorized project provides for a channel 40 feet deep and 500 feet wide from the Atlantic Ocean through the ocean bar and entrance channels to Southport, thence 38 feet deep and 400 feet wide to the upper end of the anchorage basin (foot of Castle Street) at Wilmington, thence 32 feet deep and 400 feet wide, to Hilton Bridge over Northeast (Cape Fear) River; a 38-footdeep anchorage basin at Wilmington; a 32-foot-deep turning basin opposite the principal terminals; a channel 12 feet deep and 100 feet wide, about 3 miles long, in Cape Fear River; and a channel 25 feet deep and 200 feet wide from Hilton Bridge over Northeast (Cape Fear) River to a point 1.66 miles above, including a turning basin of the same depth, 700 feet wide and 500 feet long, at a point 1.25 miles above the bridge. The project was authorized by River and Harbor Acts of July 3,1930; March 2,1945; May 17, 1950; October 23, 1962; and March 10, 1964; under Section 107 of the 1960 River and Harbor Act. A modification to widen the existing anchorage basin by 100 feet was authorized on July 13, 1982, under Sec. 5 of the Cong. Appro. Act of March 4, 1915. (For further details of authorization, see 1962 Annual Report.) Localcooperation. Fully complied with to date. Terminal facilities. Forty-three principal wharves, piers, and docks at port of Wilmington, with a berthing space of about 20,000 linear feet serve the harbor. These facilities handle general cargo and petroleum products. For further details, see Port Series No. 12, revised 1980, Corps of Engineers. Operations and results during fiscal year. Maintenance: During intermittent periods the U.S. debris boat Snell repaired survey and dredging ranges at a cost of $152,992. Between October 1 and November 11, 1984, the contract dredges Dodge Island and Sugar Island removed 937,659 cubic yards from shoals in the ocean bar at a cost of $2,602,884. Between December 12, 1984 and February 25, 1985, the contract dredges Clinton and Cherokee removed 901,653 cubic yards from shoals in the anchorage basin at a cost of $728,035. Mobilization for contract dredging in the river channel cost $136,410. Cost in connection with prior year dredging was $115. Engineering and design for future year dredging cost $4,672. Investigations in connection with a ship grounding cost $1,819. Environmental analysis of proposed dredge disposal sites cost $27,966. Condition and operation studies cost $342,470. Contributed funds of $450,000 were expended for diking on pipeline dredging. Contributed funds of $43,500 were expended for dredging of the state ports. A refund of $60,000 in contributed funds was made to the State of N. C. Condition at end of fiscal year. The active portion of the project completed July 1973 except for latest modification which was completed on October 26, 1982,with maintenance funds. (For further details, see Annual Report for 1962.) Total cost of the existing project to September 30, 1985, was $65,440,562 of which $14,089,612 was for new work and $51,350,950 was for maintenance, including $3,299,205 contributed funds. Flood Control 16. ARARAT RIVER, MOUNT AIRY, N. C. Location. Ararat River is a tributary of the Yadkin River and is located in Surry County, N. C. The river flows through Mount Airy, N. C., to its confluence with the Yadkin River. The entire project borders Mt. Airy. (See USGS quadrangle sheets, Mount Airy, North, Va. and N. C. and Mount Airy, South, N. C.) Existing project. The project consists of approximately 5,100 feet of industrial area dike construction, approximately 6,700 feet of channel improvement, approximately 1,800 feet of floodwall/dike at the Pine Street commercial area, and a flood warning system. The project was approved by the Chief of Engineers on August 10, 1983, under Section 205, 1948 Flood Control Act, as amended. The estimated Federal construction cost is $4,000,000 (1985). Local cooperation. Local interest must: (a) provide without cost to the United States all lands, easements, and rights-of-way, including suitable borrow and spoil disposal areas and suitable conservation lands to partially compensate for loss of fish and wildlife resources as determined by the Chief of Engineers, necessary for the construction of the project; (b) accomplish without cost to the United States all alterations and relocations of buildings, transportation facilities, storm drains, utilities, and other structures and improvements made necessary by the construction; (c) hold and save the United States free from damages due to the construction works, except damage due to the fault or negligence of the United States or its contractors; (d) maintain and operate the project after completion in accordance with regulations prescribed by the Secretary of the Army; (e) prescribe and enforce regulations to prevent obstruction or encroachment on channels and interior ponding areas which would reduce their flood-carrying capacity or hinder maintenance and operation, and control development in the project area to prevent an undue increase in the flood damage potential; and (f) assume full responsibility for all project costs in excess of the Federal cost limitation of $4 million. Formal assurances have been received. Operations and results during fiscal year. New work: Project construction cost $280,590. Contributed funds of $22,366 were expended for installation of a flood warning system. Condition at end of fiscal year. A construction contract was awarded on May 29, 1985, with completion scheduled for February 1987. 6-9 REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1985 17. CAPE FEAR RIVER BASIN, N. C. Location. Work covered by this project consists of a series of dams and reservoirs on tributaries of the Cape Fear River in North Carolina within a radius of 100 miles from Raleigh, North Carolina. (See Geological Survey Map of North Carolina.) Existing project. Public Law 88-253, approved December 30, 1963, authorized three principal dams and reservoirs and a series of smaller reservoirs on tributaries of the Cape Fear River in accordance with the comprehensive plans in House Document 508, 87th Congress, 2d session. The act also provides that the appropriate agencies of the Departments of the Army and Agriculture shall conduct joint investigations and surveys and prepare a report on the upper tributaries of the Cape Fear River in the interest of watershed protection and flood prevention, and the conservation, development, utilization, and disposal of water. The report is to be prepared and submitted in compliance with provisions of Public Law 87-639. A list of the dams and reservoirs included in the comprehensive plan follows. (See Table 6-J on Dams and Reservoirs). Estimates of cost as given are based on 1960 price levels, except the ones for B. Everett Jordan Dam and Lake, and Randleman Lake, which were revised in 1985, and Howards Mill Lake in 1980. These three projects have been authorized for construction in accordance with the above authorization. Howards Mill Lake was reclassified to the "deferred" category in October 1980 due to the current lack of economic justification. The joint study, accomplished by the Departments of the Army and Agriculture was unfavorable and has been submitted to Congress. No further action will be taken. Local cooperation. Requirements are given in the individual project reports. 17A. B. EVERETT JORDAN DAM AND LAKE, N. C. Location. The project is located on the Haw River, N. C., 4.3 miles above its mouth, and 2.5 miles north of Moncure, N.C. Existing project. The project provides for an earth dam 1,330 feet long with a maximum height of 112 feet above the streambed, an uncontrolled, unpaved chute spillway, and a controlled 19-foot diameter outlet structure. Some saddle dikes are required beyond the spillway. The reservoir will have a gross storage capacity of 753,600 acre-feet, of which 538,500 acre-feet will be for flood control and a conservation pool of 215,100 acre-feet for water-quality control, water supply, and sedimentation. The reservoir will be operated as a unit of a coordinated system for control of floods in the Cape Fear River Basin and for water supply, water-quality control, and other purposes. Estimated cost for new work is $136,000,000 (1985), consisting of $77,672,800 for construction, and $58,327,200 for lands and damages, including highway, railroad, and utility relocations. The existing project was authorized by Public Law 88-253 approved December 30, 1963 (H.D. 508, 87th Cong., 2d sess.) Local cooperation. Local interests must protect downstream channels from encroachments and obstructions which would adversely affect operation of the project; reimburse the Federal Government for all costs allocated to municipal and industrial. water supply, presently estimated at $3,900,000 and bear all annual costs for operation, maintenance, and major replacements allocated to municipal and industrial water supply, an amount presently estimated at $38,000 annually. Assurances that these obligations for water storage would be assumed have been received from the Department of Natural and Economic Resources, State of North Carolina. In addition, the State of N. C. has leased the project for public park, recreational, fish, wildlife, and other natural resource management purposes and the estimated cost to the State for O&M under this lease is $772,000 annually. Operations and results during fiscal year. New work: Modifications to the dam were completed at a cost of $41,002. Construction of wildlife subimpoundments were initiated at a cost of $712,885. Parkers Creek recreation area was continued at a cost of $3,657,355. Vista Point recreation area and N. C. Forestry Sites were completed at a cost of $85,696. Paving of wildlife recreation areas and Poe's Ridge recreation area cost $240,631. Construction of a breakwater at Crosswinds Marina cost $284,634. Total Federal expenditures were $6,145,290, including the above items. Status of plans and specs: Ebenezer Church recreation area, 85 percent; and Poe's Ridge Tailwater access, 85 percent. Maintenance: Water quality studies were conducted at a cost of $105,974. Repairs to dam access road cost $29,501. Normal operation and maintenance cost $654,177, for a total of $789,652. Condition at end of fiscal year. Relocations complete except for Public Service Gas Co. Recreation facilities and wildlife subimpoundments are underway. Impoundment was completed in February 1982 with dedication on May 1, 1982. Project completion is scheduled for March 1989. 171B. RANDLEMAN LAKE, N. C. Location. The project is located on Deep River, N. C., about 15 miles south of Greensboro and about 2 miles upstream from the town of Randleman. The damsite and about two-thirds of the reservoir would lie in Randolph County. The upper one-third of the reservoir would lie in Guilford County. Existing project. The authorized project provides for construction of an earth dam 2,400 feet long with a maximum height of 110 feet above the streambed to create a reservoir with gross storage of 108,000 acre-feet, consisting of 46,000 acre-feet for flood control and a conservation pool of 62,000 acre-feet for water supply, water-quality control and sedimentation. Randleman Lake is the second project of the comprehensive plan of development for the Cape Fear River Basin, providing reservoir storage for flood control, water supply, and recreation. Estimated cost of new work is $112,000,000 (1985), consisting of $52,902,000 for construction and $59,098,000 for lands and damages, including relocations. The existing project was 6-10 WILMINGTON, N. C., DISTRICT authorized by the 1968 Flood Control Act (H.D. 343, 90th Cong., 2d sess.). Local cooperation. Local interests must: (1) In accordance with the Federal Water Project Recreation Act (P.L. 89-72): (a) Administer project land and water areas for recreation and fish and wildlife and to assure access to such development to all on equal terms; (b) pay, contribute in kind, or repay (which may be through user fees) with interest, one-half of the separable first cost allocated to recreation presently estimated at $8,736,000; and (c) bear all the costs of operation, maintenance, and replacement of recreation facilities, presently estimated at $234,000 annually; (2) In accordance with the Water Supply Act of 1958, as amended, assure payment to the United States of all costs allocated to water supply, presently estimated at $51,064,000 for construction and $444,000 annually for operation, maintenance, and major replacement; (3) Hold and save the United States free from damages due to water-rights claims resulting from construction and operation of the project; (4) Prevent encroachment on downstream channels to the extent needed to provide effective reservoir operation; and (5) Exercise to the full extent of their legal capability control against removal of streamflow made available for preservation of downstream fishery habitat. These assurances are subject to the provision that Federal participation in measures required to safeguard the quality of water in Randleman Reservoir shall not be provided as a substitute for the responsiblity of local interests to provide adequate treatment in accordance with water quality standards established pursuant to the Water Quality Amendments of 1972 (P.L. 92-500). Reasonable assurances that the requirements will be fulfilled have been received. With the advent of innovative financing under the current administration, the terms of local cooperation may change. Operations and results during fiscal year. New work: Advance engineering and design cost $86,195. Condition at end of fiscal year. Preconstruction planning was completed in FY 1982. Currently awaiting a new construction start. 18. CAROLINA BEACH AND VICINITY, N. C. Location. The project is in New Hanover County, about 15 miles southeast of Wilmington, N. C., on the peninsula which separates lower Cape Fear River from the Atlantic Ocean. (See Coast and Geodetic Survey Map 834.) Existing project. The authorized project provides for construction of a dune with a base generally bordering at or near the building line, with a crown width of 25 feet at an elevation of 15 feet above mean low water, together with integral construction of a beach berm with a crown width of 50 feet at elevation 12, extending about 25,800 feet from the northern limits of Carolina Beach to the southern limits of Kure Beach; initial deposition of sufficient material north of Carolina Beach to serve as a feeder beach; and Federal participation in the cost of beach nourishment for a period not to exceed 10 years from the year of completion of initial placement. The area south of Carolina Beach was reclassified to the active category, June 1985. Approved estimated Federal cost for new work is $15,111,000 (1985). The project was authorized by the 1962 Flood Control Act (H.D. 418, 87th Cong. 2d sess.). Local cooperation. Local interests must: (a) Provide lands, easements, and rights-of-way for construction; (b) make required relocations and alterations of streets, utilities, or structures; (c) contribute 37.9 percent of the total first cost, with credit allowed for (a) and (b); (d) hold the United States free from damages; (e) maintain all works after completion; (f) maintain continued public ownership of the shore; (g) adopt and enforce appropriate ordinances to provide for preservation of improvement and its protective vegetation; (h) control water pollution to extent necessary to safeguard health of bathers; and (i) at least annually inform interests affected that project will not provide any substantial protection from ocean surges higher in elevation than that of Hurricane Hazel, October 15, 1954. Requirements have been fulfilled to date for the town of Carolina Beach portion of the project only. Operations and results during fiscal year. New work: Between April 19 and June 4, 1985, the contract dredge Ozark excavated 764,162 cubic yards to renourish the Carolina Beach project at a Federal cost of $835,817. Contributed funds of $816,187 were expended on the project. A refund of $82,600 in contributed funds was made to the sponsor. Condition at end of fiscal year. Project construction was completed August 12,1982, except for grassing which was completed in September 1983. A contract for the first increment of renourishment was awarded on March 8, 1985 and was completed on June 10, 1985. 19. GENOA SEWER FACILITY, WAYNE COUNTY, N.C. Location. The facility is located on the south bank of the Neuse River across from the City of Goldsboro, N. C., and about 1/2 mile downstream from the U. S.117 bridge over the Neuse River. (See USGS quadrangle sheet, Southwest Goldsboro, N. C.) Existing project. The purpose of the project is to provide emergency bank protection at the Genoa sewer facility. The project consists of grading the Neuse River bank to a 2 horizontal to 1 vertical slope along the 200 linear feet of eroded bank, filling the slope as necessary to achieve grade, filling the hole in the riverbed at the toe of the eroded bank to match existing river grade, placing a 6-inch-thick layer of crushed stone filter bed from the toe to the top of the slope, and providing a 1Va-foot-thick layer of riprap armor slope protection. The project was approved by the Chief of Engineers on August 30, 1983, under Section 14 of the Flood Control Act of 1946, as amended. Local cooperation. Fully complied with to date. Operations and results during fiscal year. New work: Project construction cost $94,942. 6-11 REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1985 Condition at end of fiscal year. A construction contract was awarded on November 22,1983, and was completed on December 20,1984. 20. LEESVILLE, VA., ROANOKE RIVER, SEC. 32, DEMO. PROJECT Location. The project is located on the Roanoke (Staunton) River in southwest Virginia near the Town of Leesville in Campbell and Pittsylvania counties. (See USGS quadrangle sheet, Leesville, Va.) Existing project. The project provides for a total of about 2,200 linear feet of streambank protection on two separate sites along a 3-mile segment of the river between Leesville Dam and the town of Leesville. Three methods of erosion control were used, they were: stone rubble with vegetation, rubber tire mattress and rock windrow. The project was funded for construction by the Chief of Engineers in February 1978, under Section 32, P.L. 93-251. Local cooperation. Fully complied with to date. Operations and results during fiscal year. New work: Monitoring of Leesville and Little Rockfish Creek cost $322. Condition at end of fiscal year. Construction was completed in March 1981. The project is functioning as designed. 21. NEUSE RIVER BASIN, N. C. Location. Works covered by this project consist of a series of dams and reservoirs in the Neuse River Basin in North Carolina within a radius of 50 miles from Raleigh, North Carolina. (See Geological Survey Map of North Carolina.) Existing project. The Flood Control Act of 1965 authorized construction of the Falls project as the key project in the recommended general plan of development of the Neuse River Basin. The plan will serve as a guide for immediate and future development of the basin's water resources as set forth in House Document 175, 89th Congress, 1st Session. A list of projects included in the general plan of development follows. (See Table 6-J on Dams and Reservoirs.) Estimated costs as given are based on 1963 price levels, except for Falls Lake which was revised in 1985. 21A. FALLS LAKE, N. C. Location. The project is on the Neuse River about 10 miles north of the city of Raleigh, North Carolina. Existing project. The authorized project provides for an earth dam 1,900 feet long with a maximum height of 92 feet above streambed. The dam will have a 30-foot top width. An uncontrolled chute spillway, 100-feet wide, will be located in the east abutment. The reservoir will have a gross storage capacity of 335,600 acre-feet, of which 220,900 acre-feet will be for flood control, 45,000 acre-feet for water supply for the city of Raleigh, 44,600 acre-feet for water-quality control, and 25,100 acre-feet for sediment storage. The reservoir will be operated as the initial unit of a coordinated system for control of floods in the Neuse River Basin for water supply, water quality control, recreation, and other purposes. Estimated cost of new work is $167,000,000, (1985) consisting of $76,070,600 for construction and $90,929,400 for lands and damages, including highway, railroad, and utility relocations. The project was authorized by the 1965 Flood Control Act (H.D. 175, 89th Cong., 1st sess.) Local cooperation. Local interests must prevent encroachment on downstream channels that would interfere with the operation of the reservoir; pay the United States in accordance with the Water Supply Act of 1958, as amended, the entire amount of construction cost allocated to water supply, presently estimated at $12,400,000 and entire amount of operation, maintenance, and replacement costs allocated to water supply, presently estimated at $89,000 annually, the final amounts to be determined after actual costs are known; administer project land and water areas for recreation and fish and wildlife enhancement; pay, contribute in kind, or repay (which may be through user fees), with interest, one-half of the separable cost of the project allocated to recreation and one-fourth of the separable cost allocated to fish and wildlife enhancement, the amount involved currently being estimated at $20,600,000, and, bear all costs of operation, maintenance, and replacement of recreation and fish and wildlife lands and facilities, the amount involved currently being estimated at $1,224,000 on an average annual basis. Formal assurances have been received. The N. C. Department of Natural and Economic Resources has been authorized by an act of legislation to assure payment of all non- Federal costs allocable to water supply in all Federal projects as required by law. The State will require repayment of water supply costs, by the users. A contract between the city of Raleigh and the United States for water-supply storage space was approved by the Secretary of the Army on September 11, 1972. A contract agreement for cost sharing of recreational lands and facilities in accordance with P.L. 89-72 was approved by the Secretary of the Army on September 11, 1972. A contract agreement in accordance with Section 221 of P.L. 91-611 was executed on October 10, 1972. Operations and results during fiscal year. New work: Litigation on the Servidone dam contract continued at a cost of $322,702. The Corps management center was completed at a cost of $900,603. Miscellaneous items on Highway 50 and Rolling View recreation areas were completed at a cost of $90,982. Sandling Beach recreation area continued at a cost of $1,734,971. Total Federal expenditures were $4,388,394, including the above items. Status of plans and specs: Tailwater access area, 10 percent; and N. C. Park Headquarters, 10 percent. Maintenance: Water quality studies were conducted at a cost of $79,062. Repairs to the dam cost $14,334. Borrow area repairs cost $57,637. Normal operation and maintenance cost $750,306, for a total of $901,339. Condition at end of fiscal year. Reservoir filling was completed on December 7, 1983. Dedication ceremonies 6-12 WILMINGTON, N. C., DISTRICT were held on April 30, 1983. The Corps O&M area is complete and Sandling Beach recreation area is underway. The fish and wildlife facilities and remaining recreation facilities are the major items remaining to be constructed. 22. SCUPPERNONG RIVER, N.C. Location. The stream rises in the east-central portion of Washington County, N. C., flows east into Tyrrell County, and thence north into Albemarle Sound, a total distance of about 22 miles. (See Geological Survey quadrangle sheet, Creswell, N. C.) Existing project. The project provides for excavating a 70-foot-bottom-width channel, with depths ranging from 9 feet to 12 feet, along Scuppernong River from Spruills Bridge to the confluence with Mauls Creek, a distance of 2.0 miles, and excavating a 45-foot-bottom-width channel, with depths ranging from 6 feet to 8 feet, along Mauls Creek from Scuppernong River to County Road 1163, a distance of 1.8 miles. Total project length is 3.8 miles. Estimated Federal cost of construction is $509,000 (1984). Project was approved by the Chief of Engineers, October 31, 1966 (with modification adding Mauls Creek approved June 16, 1967), under Section 205, 1948 Flood Control Act, as amended. Local cooperation. Local interests must provide lands, easements, rights-of-way, utility relocations and alterations, and highway or highway-bridge construction and alterations necessary for construction; hold the United States free from damages; maintain and operate project after completion; contribute, in cash, 31.4 percent of construction costs, currently estimated at $141,000; and prevent future encroachment. Formal request has not been made. Operations and results during fiscal year. New work: Project reanalysis cost $39,767. Condition at end of fiscal year. Project reanalysis and environmental studies are underway with completion scheduled in 1986. A smaller channel on Scuppernong River and deletion of Mauls Creek are anticipated. 23. STUART, VA. Location. The project is located on the South Mayo River at Stuart, Va. above and below Route 8 highway. (See USGS quadrangle sheet, Stuart, Va.) Existing project. The recommended plan consists of a 100-foot bottom width high flow diversion channel combined with downstream river widening. A wier will be placed across the entrance to the diversion channel and a bench channel design will be used for the downstream river widening. The South Mayo River above Route 8 highway will be widened to a 50-foot bottom width, using a trapezoidal channel design and the commercial site northwest of Route 8 wrn be filled to the elevation of approximately the 200-year frequency flood. All river widening, except for a short distance above Route 8, will be done on the north bank. Estimated Federal cost of construction is $3,198,000. The project was approved by the Chief of Engineers on February 1, 1985, under Section 205, 1948 Flood Control Act, as amended. Local cooperation. Local interests must provide all lands, easements, rights-of-way, including suitable borrow and spoil disposal areas, and all alterations and relocations of buildings, transportation facilities, storm drains, utilities, and other structures and improvements necessary for construction; hold and save the United States free from damages; maintain and operate the project after completion; assume full responsibility for all project costs in excess of the Federal cost limitation of $4 million; presribe and enforce regulations to prevent obstruction or encroachments; continue to enforce flood plan regulations that comply with FEMA guidelines; and at least annually, inform affected interests regarding the limitations of the protection afforded by the project. Formal assurances have been received. Operations and results during fiscal year. New work: Engineering and design for project construction cost $127,330. Condition at end of fiscal year. A construction contract is scheduled for award in May 1986. This is the first report since authorization. 24. YADKIN RIVER BASIN, N. C. AND S. C. Location. The river rises on the eastern slope of the Blue Ridge Mountains in western North Carolina, flows generally easterly about 100 miles to the vicinity of Donnaha, North Carolina, thence southeasterly 104 miles to its confluence with Uwharrie River near Badin, North Carolina, where its name changes to Great Pee Dee River. (See U.S. Geological Survey map of North Carolina.) Existing project. The Flood Control Act of July 24,1946, authorized construction of four flood control dams in the Upper Yadkin River Basin, two on the Yadkin River above Wilkesboro, North Carolina, and two on Reddies River, a tributary stream. Studies made subsequent to authorization established the economic advantage of providing needed flood-control storage in only two reservoirs, one on the Reddies and one on the Yadkin. Present planning considers only the two-reservoir plan, W. Kerr Scott Dam and Reservoir constructed 1962 and Reddies River Lake. W. Kerr Scott was transferred to the Wilmington District from Charleston in fiscal year 1980. Any future work on Reddies River will also be done by the Wilmington District. (See Table 6-J on Dams and Reservoirs.) 24A. W. KERR SCOTT DAM AND RESERVOIR, N. C. Location. W. Kerr Scott Dam and Reservoir is on Yadkin River, North Carolina, about 6 miles upstream from Wilkesboro. At full flood-control pool elevation (1,075 feet mean sea level), the reservoir extends 15.7 miles upstream to the Wilkes-Caldwell County line. Existing project. The project consists of a rolled earthfill dam 1,740 feet long, with top of dam at elevation 1,107.5 feet mean sea level or about 148 feet above streambed elevation; a spillway near the north abutment of the dam 6-13 REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1985 in a rock cut with crest elevation 1,075; and outlet works consisting of an intake structure, control tower, and a circular concrete conduit 12.25 feet in diameter through the base of the dam near the south abutment. The reservoir has a gross capacity of 153,000 acre-feet of which 112,000 acre-feet are reserved for flood control, 33,000 acre-feet will be used as required for water supply, and 8,000 acrefeet being contained in the minimum pool. Estimated cost is $9,110,000 (1983) for new work. The existing project was authorized by the 1946 Flood Control Act. Local cooperation. Requirements fully satisfied. For details, see page 413 of Annual Report for 1963. Operations and results during fiscal year. Maintenance: Siesmic studies of the dam cost $7,236. Engineering and design for rip-rap protection cost $2,718. Rehabilitation of campsites was accomplished at a cost of $166,781. Normal operation and maintenance cost $950,971 for a total of $1,127,706. Recreation user fees of $2,379 were expended for operation, maintenance and construction of recreation facilities. Condition at end of fiscal year. The project was commenced in August 1960 and placed in operation for flood control and water storage purposes in August 1962. 25. INSPECTION OF COMPLETED FLOOD CONTROL PROJECTS To determine the extent of compliance with approved regulations for maintenance and operation, inspections were made for the following projects during fiscal year 1985: Ellis Swamp, Gates County, N. C.; Gapway Swamp, Columbus County, N. C.; Old Field Swamp, Robeson County, N. C.; Gardners Creek, Martin County, N. C.; New River, Onslow County, N. C.; Pungo Creek, Beaufort County, N. C.; South Creek, Beaufort County, N. C.; Pungo River, Beaufort County, N. C.; and Filberts Creek, Edenton, N. C.; Pantego and Cucklers Creek, Beaufort County, N. C.; White Oak Dike, Bladen and Pender Counties, N. C.; Ellerbe Creek, Durham County, N. C.; Pasquotank Dike, Pasquotank County, N. C.; Perquimans River, Perquimans County, N. C.; Core Creek, Craven County, N. C.; Princeville Dike, Edgecombe County, N. C.; Swift Creek, Pitt County, N. C.; Carolina Beach, New Hanover County, N. C.; Wrightsville Beach, New Hanover County, N. C.; Goldsboro, Neuse River, Wayne County, N. C.; Broad Creek, Beaufort County, N. C.; Little Rockfish Creek, Hope Mills, N. C.; Black River, Harnett County, N. C.; Lick Run, Roanoke, Va.; and Leith Creek, Scotland County, N. C. Responsible local officials were advised of inadequacies in maintenance and operation on local flood protection works where appropriate. Cost for the period was $30,000. Total cost to September 30, 1985, was $305,559, charged to operations. 26. FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION Flood control activities pursuant to Section 205, Public Law 858, 80th Congress, as amended (preauthorization). (See Table 6-K.) Emergency flood control activities and hurricane flood and shore-protection activities at Federally authorized projects (Public Law 99, 84th Congress, and antecedent legislation). National Emergency Preparedness Program cost $128,468. Disaster Preparedness Program cost $101,219. Hurricane disaster reconnaissance cost $10,673. Multiple-Purpose Projects, Including Power 27. ROANOKE RIVER BASIN, VA. AND N. C. Location. The project is on the Roanoke River and its tributaries in Virginia and North Carolina within a radius of 100 miles from Danville, Virginia. Existing project. The Flood Control Act of 1944 approved a general plan for the comprehensive development of the Roanoke River Basin for flood control and other purposes, and authorized construction of John H. Kerr and Philpott Reservoirs. (See Table 6-J for a list of dams and reservoirs included in the comprehensive plan.) Local cooperation. None required. John H. Kerr and Philpott Reservoirs are the only projects in the comprehensive plan that have been authorized for construction. (See Table 6-J on Dams and Reservoirs.) 27A. JOHN H. KERR DAM AND RESERVOIR, VA. AND N. C. Location. The project is on Roanoke River, about 178.7 river miles above its mouth, in Mecklenburg County, Virginia, and 20.3 miles downstream from Clarksville, Virginia. The reservoir extends upstream on Roanoke River 56 miles and on Dan River 34 miles. Existing project. The authorized project provides for a concrete gravity dam with wing and saddle dikes on the right and left banks, with a total length of about 22,285 feet. The reservoir is operated as a unit of a coordinated system of reservoirs in the Roanoke River Basin for control of floods, generation of hydroelectric power, regulation of low-water flow, and for other purposes. The power installation is 204,000 kilowatts. (For further details see Annual Report for 1962.) Estimated cost is $67,529,000 (1983) for construction and $24,521,000 for lands and damages, including relocation of highways, railroads, and utilities, a total of $92,050,000 for new work. The existing project was authorized by the 1944 Flood Control Act. Local cooperation. None required. Operations and results during fiscal year. New work: Cost in connection with construction of two comfort stations at Palmers Point and Rudds Creek was $14,293. Construction of a washhouse at Longwood and a dump station and washhouse at Northbend Park was initiated at a cost of $29,152. Settlement of the South Boston claim cost $4,500,000. Cost-sharing with the State of N. C. at various sites cost $35,558. Maintenance: Design for upgrading of the powerhouse lobby cost $4,394. Modification of the 6-14 WILMINGTON, N. C., DISTRICT highway intersection of the powerhouse cost $5,048. Preservation of archeological sites at Satterwhite Point was initiated at a cost of $17,449. Stability analysis of the dam cost $292,436. Plans and specs for the management center were completed at a cost of $154,526. Investigation of shoreline erosion cost $11,368. Interim repairs on the right wing dike were completed at a cost of $62,447. Rehabilitation of campsites at Northbend Park was completed at a cost of $154,549. Design for highway bridge repairs cost $963. Study on impact of water withdrawals cost $22,734. Work on the South Boston litigation cost $120,218. Work on the fire detection and alarm system for the powerhouse continued at a cost of $14,302. Dam break model analysis cost $14,303. Work on the fire extinguishing and suppression system continued at a cost of $153. Paving of recreation access roads cost $10,000. Engineering and design for replacement of the powerhouse computer cost $1,204. Normal operation and maintenance cost $3,276,956, for a total of $4,163,050. Recreation user fees of $5,149 were expended for operation and maintenance of recreation facilities. Condition at end of fiscal year. Project is complete except for additional recreational facilities. Production of power and protection from floods are provided by project. 27B. PHILPOTT LAKE, VA. Location. On Smith River, Virginia, 44.3 miles above its junction with Dan River, and 35 miles upstream from Virginia-North Carolina State line in Franklin and Henry Counties. Existing project. The authorized project provides for a concrete gravity dam 892 feet long and with a maximum height of 220 feet. Reservoir is operated as a unit of a coordinated reservoir system for flood control in the Roanoke River Basin, generation of hydroelectric power, regulation of low-water flow, and for other purposes. The powerhouse has a total installation of 14,000 kilowatts. (For further details see Annual Report for 1962.) Federal cost estimate is $13,933,000 (1983) for construction and $1,157,000 for lands and damages, a total of $15,090,000. Existing project was authorized by 1944 Flood Control Act. Local cooperation. None required. Operations and results during fiscal year. New work: Cost in connection with construction of a washhouse at Goose Point and a comfort station at Salthouse Branch was $20,337. A comfort station at Philpott Park was completed at a cost of $9,885. Maintenance: Design of a powerhouse fire protection system cost $2,268. Engineering and design for the management and visitors center cost $146,330. The sluice bulkhead was initiated at a cost of $12,442. Investigation of deterioration of the powerhouse control room floor cost $6,821. A chlorinator for the project office water supply cost $16,457. Rehabilitation of recreation areas cost $19,898. Normal operation and maintenance cost $1,110,879, for a total of $1,315,095. Condition at end of fiscal year. The project is complete except for additional recreational facilities, and is providing power and flood protection. 28. SCHEDULING FLOOD CONTROL RESERVOIR OPERATIONS B. Everett Jordan Dam and Lake, located in the Cape Fear River Basin, North Carolina, began fiscal year 1985 at elevation 215.10 feet, MSL or 0.9 feet below normal pool. Below average rainfall caused the lake to be gradually drawndown to the minimum elevation of the fiscal year on November 28, which was 212.55 feet, MSL or 3.45 feet below normal pool. Heavy rainfall produced three major lake level peaks, two of which were 219.00 and 219.75 feet, MSL on January 6 and August 22, respectively. The third lake level peak of 224.40 feet, MSL on February 4 was the maximum elevation for fiscal year 1985. Jordan Lake ended the fiscal year at elevation 214.85 feet, MSL or 1.15 feet below normal pool. Flood damages prevented for fiscal year 1985 and since impoundment were equal to $680,000 and $3,405,000, respectively. Total cost of functional operation for the period was $97,550. Falls Lake, a relatively new project, is located in the Neuse River Basin, North Carolina. During installation of the sedimentation ranges, substantial differences were noted in the storage capacity of Falls Lake as determined during the planning process in the mid-1960's. Because of these storage differences, part of the lake area was remapped which closely confirmed the most recent storage determination. Conservation pool storage was found to be 89,670 acre-feet or a reduction of 22.3 percent from the initial storage determined during the planning process. Controlled flood storage was found to be 220,878 acre-feet or a reduction of 9.1 percent from the initial storage determination. Because of the impacts primarily to water supply and water quality storage resulting from this storage deficit, a committee consisting of Corps, State and local officials was formed to address the resulting problems and formulate solutions. An interim solution was to adopt a lake level rule curve. The Falls Lake level is to be 0.9 feet above the normal pool elevation or at 251.0 feet, MSL during the months of May through September and at the normal pool level of 250.1 feet, MSL during the months of November through March. Water quality target flows were also reduced on an interim basis during the months of July through September from 404 to 254 cubic feet per second to aid in counteracting drought conditions and the reduced storage capacity. Final solutions have not been finalized. Falls Lake began fiscal year 1985 at elevation 247.80 feet, MSL or 2.30 feet below normal pool. Below normal rainfall caused a gradual drawdown to elevation 245.74 feet, MSL on November 28. Periods of excessive rainfall then caused the lake level to rise to elevation 251.45 feet, MSL on January 7, 1985 and then to the maximum elevation of the fiscal year at elevation 255.83 feet, MSL on February 7. Falls Lake returned to normal pool on February 28 and then remained near that level through May. Below normal rainfall caused a gradual drawdown in lake level to elevation 245.71 feet, MSL on August 16 which was the minimum elevation of the fiscal year. Heavy rainfall caused a lake level rise to elevation 249.38 feet, MSL on September 6. Releases from Falls of approximately 60 6-15 REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1985 CFS, were made from August 30 to October 4 at the request of the State of North Carolina Department of Natural Resources and Community Development to complete low flow water quality studies. However, below normal rainfall and low inflows caused a gradual drawdown to elevation 248.87 feet, MSL at the end of the fiscal year or 2.13 feet below normal pool. Flood damages prevented in fiscal year 1985 were $419,000 and the cumulative flood damages prevented since the project began were $6,342,000. Total cost of functional operation for the period was $88,284. John H. Kerr Dam and Reservior, located in the Roanoke River Basin, Virginia and North Carolina, began fiscal year 1985 at elevation 296.89 feet, MSL or 2.61 feet below rule curve. The reservoir level rose slightly and remained near rule curve through December 1984. During this period, Kerr Reservoir fell to 295.12 feet, MSL on December 31 which was the minimum elevation for the fiscal year. Excessive rainfall in early January caused a rise in the reservoir level to elevation 300.63 feet, MSL, or 5.13 feet above rule curve on January 8. The resevoir level gradually fell to near rule curve by the end of January when excessive rainfall on February 1, 2 and 12 caused a rise to elevation 301.25 feet, MSL or 5.75 feet above rule curve on February 15. Record low rainfall for the month of March caused the reservoir level to fall below rule curve on March 11. Kerr Reservoir remained one to three feet below rule curve through mid-June. A decreasing rule curve elevation caused the reservoir level to remain closer to rule curve through mid-August. Heavy rains produced the maximum elevation of the fiscal year at 304.46 feet, MSL on August 23. Kerr Reservoir ended the fiscal year 1.41 feet below rule curve or at elevation 298.09 feet, MSL. The 13 foot minimum stage required in the lower Roanoke River at Weldon for striped bass spawning did not begin as planned due to below average rainfall and low streamflows into Kerr Reservoir. However, storage was available in Kerr Reservoir to provide necessary releases for three weeks during the spawning period which ended on June 7. All inflows to Kerr Reservoir were controlled without having to spill water over the spillway or through the sluices. Gross generation for the fiscal year amounted to 293,999,400 kilowatt-hours and power revenue was $4,595,848 making a cumulative total since inception of $115,757,708. Flood damages prevented during the fiscal year amounted to $8,500,000 and the cumulative flood damages prevented since the project began amounts to $72,107,000. The total cost of functional operations for the fiscal year was $123,251. Philpott Lake, located on the Smith River in the Dan River Basin, Virginia, was at elevation 971.50 feet, MSL or at rule curve at the start of fiscal year 1985 and remained near rule curve through mid-May 1985. Above normal rainfall in May caused a rise in the lake level to elevation 975.97 feet, MSL on May 25. Below normal rainfall and drying conditions in June produced a gradual draw down in the lake level. Even with near normal rainfall in July through mid-August, Philpott Lake continued to drawdown because of dry ground conditions to elevation 968.97 feet, MSL on August 16 which was the minimum elevation of the fiscal year. Excessive rainfall then caused a rapid rise to the maximum lake elevation of the fiscal year at elevation 977.76 feet, MSL on August 19. Philpott Lake was drawndown to rule curve on September 6 and remained near this level through September at elevation 971.22 feet, MSL or 0.28 feet below rule curve. Flood damages prevented during the fiscal year and since inception of the project amounted to $2,500,000 and $21,470,000, respectively. Gross generation amounted to 20,585,010 kilowatt-hours and power revenue was $547,900, making a total $13,748,013 since inception. Total cost of functional operation for the period was $53,993. W. Kerr Scott Dam and Reservoir ,located in the Yadkin-Pee Dee River Basin, North Carolina, began fiscal year 1985 at elevation 1,028.05 feet, MSL, or 1.95 feet below normal pool. The reservoir level fluctuated near elevation 1,028.00 feet , MSL and gradually fell to elevation 1,027.00 feet, MSL on January 30. Normal rainfall during February produced lake levels near normal pool through early March. The lake level gradually fell to elevation 1,027.50 feet MSL on April 14. Mid-April rainfall caused the lake level to rise back to near normal pool by the end of May. Below average rainfall during late June and early July caused a gradual draw down to elevation 1,023.69 feet, MSL on July 22 which was the minimum elevation of the fiscal year. Excessive rains in mid-August caused the lake level to rise above normal pool to elevation 1,033.75 feet, MSL on August 19 which was the maximum level for the fiscal year. The reservoir level again fell and ended the fiscal year at elevation 1,024.30 feet, MSL. Flood damages prevented during the fiscal year were $800,000, which makes the cumulative total since inception of the project equal to $59,951,000. Total cost of functional operation for the period was $45,407. General Investigations 29. SURVEYS Cost for the period was $1,631,024, of which $861 was for navigation studies, $1,455,716 was for flood control studies, $8,770 was for beach erosion studies, $16,105 for review of authorized projects, $80,938 for Special Investigations, $13,345 for FERC licenses review, $3,000 for soil conservation service, $7,289 for hydrologic studies, and $45,000 for cooperation with states. 30. COLLECTION AND STUDY OF BASIC DATA Flood plain information studies, as authorized by Section 206, 1960 Flood Control Act, as amended, comprise compilation and dissemination, upon the request of a State or a political subdivision thereof, of information on floods and flood damages, including identification of areas subject to inundation by floods of various magnitudes and frequen- 6-16 WILMINGTON, N. C., DISTRICT cies, and general criteria for guidance of Federal and non- Federal interests and agencies in the use of flood plain areas; and provide advice to other Federal agencies and local interests for their use in planning to ameliorate the flood hazard. Total costs for the period were $247,069. Total costs to September 30, 1985 were $3,612,891. 6-17 REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1985 TABLE 6-A COST AND FINANCIAL STATEMENT See Section Total Cost to in Text Project Funding FY 82 FY 83 FY 84 FY 85 Sept. 30, 1985 1. Aquatic Plant Control (R&H Act of 1965) (Regular Funds) (Contributed Funds) 2. Atlantic Intracoastal Waterway between Norfolk, Va. & St. Johns River, Fla. (Regular Funds) (Contributed Funds) 3. Avon Harbor, N.C. 4. Beaufort Harbor, N.C. (Regular Funds) (Contributed Funds) 5. Cape Fear River, N. C. above Wilmington 6. Channel from Back Sound to Lookout Bight, N. C. 7. Far Creek, N.C. 8. Lockwoods Folly River, N. C. (Regular Funds) (Contributed Funds) New Work: Approp. Cost New Work: Contrib. Cost New Work: Approp. Cost Maint: Approp. Cost New Work: Contrib. Cost Maint: Contrib. Cost New Work: Approp. Cost Maint: Approp. Cost New Work: Approp. Cost Maint: Approp. Cost New Work: Contrib. Cost Maint: Contrib. Cost New Work: Approp. Cost Maint: Approp. Cost New Work: Approp. Cost Maint: Approp. Cost New Work: Approp. Cost Maint: Approp. Cost New Work: Approp. Cost Maint: Approp. Cost New Work: Contrib. Cost 7,000 22,261 2,369 725,000Z 545,577 3 3,025,300 3,136,098 11,560 18,000 13,184 3,644,477'4 703,951'5 3,783,937 3,914,751 73,740 57,800 70,000 43,591 876,080 3,934,987 3,760,711 4,011,260 1,551 29,051' 14,000 44 44 340,000 297,597 58,755 58,755 331,000 311,479 195,000 190,448 400 260 327,000 57,655 507,000 502,490 243,500' 50,880"10 32,000 73,559 34,000 414,000 434,800 7,000 11,069 -93,477 125,319 363,000 360,874 92,650 -23,849 186,771 43,500 44,344 34,000 424,400 423,514 136,200 138,455 -156,545 -78,833 361,000 356,941 92,650" 46,000 50,440 4,800,000 4,057,998 5,205,000 5,345,207 14,000 8,870 8,844 76,400 76,379 517,800 519,195 146,400 146,585 636,000 636,140 235,600 232,291 253,400 225,570 31,809 31,809' 35,382,9731 34,411,627' 64,307,060' 64,078,418' 86,851 86,851 14,000 14,000 74,096 74,096 98,649 98,623 818,040" 818,040" 2,847,714'2 2,847,69312 34,000 34,000 168,833 168,833 3,759,5733 3,759,57313 12,135,614" 12,134,226" 88,328 88,328 2,256,171 2,254,976 164,642 164,642 1,181,904 1,181,904 241,272" 241,272" 2,639,646 2,624,192 92,650 92,650 6-18 WILMINGTON, N. C., DISTRICT TABLE 6-A (Continued) COST AND FINANCIAL STATEMENT See Section Total Cost to in Text Project Funding FY 82 FY 83 FY 84 FY 85 Sept. 30, 1985 9. Manteo (Shallowbag) Bay, N. C. (Regular Funds) (Contributed Funds) 10. Morehead City Harbor, N. C. (Regular Funds) (Contributed Funds) 11. Ocracoke Inlet, N. C. 12. Pamlico and Tar Rivers, N. C. 13. Silver Lake Harbor, N. C. (Regular Funds) (Contributed Funds) 14. Waterway Connecting Pamlico Sound and Beaufort Harbor, N.C. (Regular Funds) (Contributed Funds) 15. Wilmington Harbor, N. C. (Regular Funds) (Contributed Funds) 16. Ararat River, N.C. (Regular Funds) (Contributed Funds) New Work: Approp. Cost Maint: Approp. Cost Maint: Contrib. Cost New Work: Approp. Cost Maint: Approp. Cost Maint: Contrib. Cost New Work: Approp. Cost Maint: Approp. Cost New Work: Approp. Cost Maint: Approp. Cost New Work: Approp. Cost Maint: Approp. Cost Maint: Contrib. Cost New Work: Approp. Cost Maint: Approp. Cost New Work: Contrib: Cost New Work: Approp. Cost Maint: Approp. Cost Maint: Contrib. Cost New Work: Approp. Cost New Work: Contrib. Cost 820,000 1,066,908 2,723,000 2,204,476 44,000 41,800 1,000,000 1,037,405 4,941,000 4,270,169 2,200 500,000 407,323 3,004,500 3,981,556 10,000 1,906 59,000 169,188 5,145,900 5,166,545 963,940 965,826 7,484,945" 7,365,072" 29,941,907 29,731,660 1,071,940 1,065,732 - 6,546,053" - 6,546,053" 3,097,000 3,307,415 60,962 221,540 16,000 13,740 3,418,000 3,347,194 40,080 40,080 18,000 20,420 1,700 1,700 645,000 433,285 287,921 72,810 2,661,000 2,346,392 210,535 429,572 309,000 407,288 52,608 265,750 5,354,000 5,847,149 354,367 280,371 - 450,00024 - 418,48425 3,459,011 1,794,000 3,554,083 1,745,676 - 270,954 - 55,000 5,000 5,435 7,700 7,700 40,000 154,087 6,259 8,224 14,100 14,741 44,200 44,168 391,400 338,255 198,833 198,837 2,521,850 3,90 2,513,647 3,99 - 58 255,004 55 260,000 2 226,74626 12,300 2,00 28 1,00 2 34,041,27320 33,992,89220 967,665 751,711 346,240 346,240 897,144 894,505 674,651 674,651 822,578 822,546 184,284 184,284 3,482,618 3,429,473 75,000 75,000 502,567 502,567 2,156,589 2,156,589 2,452 2,452 - 18,715,22621 - 18,715,226" 2,000 48,657,32022 7,363 48,654,35922 0,284 3,329,98523 3,500 3,299,2053 0,000 2,710,000 0,590 925,820 0,000 1,012,300 2,366 22,366 6-19 REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1985 TABLE 6-A (Continued) See Section in Text Project 17A. B. Everett Jordan Dam and Lake, N. C. (Regular Funds) (Contributed Funds) 17B. Randleman Lake, N. C. 18. Carolina Beach and Vicinity, N. C. (Regular Funds) (Contributed Funds) 19. Genoa Sewer Facility Wayne County, N. C. 20. Leesville, Va. - Roanoke River, See. 32, Demo Project 21A. Falls Lake, N. C. 22. Scuppernong River, N.C. 23. Stuart, Va. 24A. W. Kerr Scott Dam and Reservoir, N. C. 27A. John H. Kerr Dam and Reservoir, VA & N.C. 27B. Philpott Lake, Va. COST A1ND FINANCIAL STATEMENT Total Cost to Funding FY 82 FY 83 FY 84 FY 85 Sept. 30, 1985 New Work: Approp. Cost Maint: Approp. Cost New Work: Contrib. Cost New Work: Approp. Cost New Work: Approp. Cost New Work: Contrib. Cost New Work: Approp. Cost New Work: Approp. Cost New Work: Approp. Cost Maint: Approp. Cost New Work: Approp. Cost New Work: Approp. Cost New Work: Approp. Cost Maint: Approp. Cost New Work: Approp. Cost Maint: Approp. Cost New Work: Approp. Cost Maint: Approp. Cost 3,384,941 2,087,925 559,000 561,223 27,000 147,365 5,128,000 5,247,893 3,951,800 3,136,513 1,382 12,420,000 12,317,839 404,000 385,530 35,000 16,845" 813,040 807,774 393,000 390,505 3,314,160 3,165,210 315,000 156,313 1,289,240 1,302,184 2,500,000 2,407,679 589,000 571,995 455,000 276,193 49,483 571,40827 115,80030 31,960"' 1,279 7,700,000 6,189,542 605,000 576,848 20,00733 45,000 42,496 1,167,000 989,327 9,000 127,362 3,747,759 3,542,191 184,000 224,709 1,116,000 1,025,106 5,800,000 5,304,189 632,900 601,634 250,000 298,513 -295,000 -120,714 267,7962" 63,000 40,898 1,654 1,450,000 4,688,430 601,000 584,999 33,776 30,81233 60,000 35,771 1,172,716 1,268,670 225,000 76,081 4,001,091 4,128,796 80,000 118,049 1,158,300 1,223,739 6,041,000 6,145,290 822,400 789,652 86,195 803,000 835,817 992,200 898,78729 -11,000 94,942 322 5,200,000 4,388,394 917,200 901,339 43,000 39,767" 115,000 127,330 1,103,200 1,130,085 4,550,000 4,579,003 4,047,200 4,168,199 -50,000 30,222 1,368,100 1,315,095 6-20 106,048,641 103,131,210 3,511,956 3,385,090 1,721,389 1,721,389 4,170,588 4,116,830 7,898,533 7,889,831 5,747,589 5,654,176 167,800 167,800 367,75532 364,40232 132,320,996 130,422,712 2,527,200 2,448,716 234,682 218,281 220,000" 205,5973" 8,841,326 8,841,326 11,350,4483 11,246,150" 94,397,527 94,198,576 52,995,042* 52,584,272' 14,801,784 14,773,614 16,856,306 0 16,649,957" WILMINGTON, N. C., DISTRICT TABLE 6-A (Continued) COST AND FINANCIAL STATEMENT See Section Total Cost to in Text Project Funding FY 82 FY 83 FY 84 FY 85 Sept. 30, 1985 1. Includes $2,369 refund to local interests in FY 82. 2. Includes preauthorization study funds for Carolina Beach Inlet: FY 80, $10,000; FY 81, $4,275; and preconstruction and construction funds; FY 81, $2,725; FY 82, $133,000. 3. Includes preauthorization study costs for Carolina Beach Inlet: FY 80, $6,614; FY 81, $6,906; FY 82, $755; and preconstruction and construction costs: FY 82, $62,196. 4. Includes preauthorization study funds for Bogue Inlet: FY 82, $14,000; FY 83, $38,490; and preconstruction and construction funds: FY 83, $38,510. 5. Includes preauthorization study costs for Bogue Inlet: FY 82, $7,174; FY 83, $45,316; and preconstruction and construction costs: FY 83, $21,368. 6. Includes $198,707 for previous projects. 7. Includes $107,634 for previous projects. 8. Includes $13,934 refund to local interests. 9. Includes preauthorization study funds for Morgan Creek: FY 82, $15,000; FY 83, $18,822; and preconstruction and construction funds: FY 83, $209,678. 10. Includes preauthorization study costs for Morgan Creek: FY 82, $8,790; FY 83, $25,032; and preconstruction and construction costs: FY 83, $17,058. 11. Includes $25,000 for previous projects. 12. Includes $12,854 for previous projects. 13. Includes $149,119 for previous projects. 14. Includes $8,178 for previous projects. 15. Includes preauthorization study funds: FY 64, $3,000; FY 65, -$2,755; FY 71, $8,000; FY 72, $2,000; FY 74, $9,000; FY 75, $25,000; FY 76 & 76T, $20,000; FY 77, $2,500; FY 78, $8,800; FY 79, $3,000; FY 81, $1,680; and preconstruction planning funds: FY 80, $15,000 and FY 81, $19,320. 16. Includes preauthorization study costs: FY 64, $219; FY 65, $26; FY 71, $8,000; FY 72, $1,448; FY 73, $552; FY 74, $9,000; FY 75, $11,925; FY 76 & 76T, $27,977; FY 77, $7,598; FY 78, $7,449; FY 79, $4,351; FY 81, $1,680; and preconstruction planning costs: FY 80, $5,686 and FY 81, $1,471. 17. Includes $69,145 refund to local interests. 18. Adjusted by $6,361 to reflect actual cost. 19. Includes $44,484 for previous projects. 20. Includes $284,557 for previous projects. 21. Includes $4,625,614 for new work on previous projects. 22. Includes $602,614 for previous projects. 23. Includes refunds to local interests: FY 78, $92,374; FY 79, $8,000; FY 80, $14,007; FY 81, $1,847; FY 82, $2,823; FY 85, $60,000. 24. Includes preauthorization study funds: FY 81, $153,000; FY 82, $128,000; FY 88, $62,487; and preconstruction funds: FY 83, $106,513. 25. Includes preauthorization study costs: FY 81, $116,322; FY 82, $162,793; FY 83, $64,372; and preconstruction costs: FY 83, $74,997. 26. Includes $6,924 preauthorization costs. 27. Includes $400,000 refund to local interests. 28. Includes $128,345 refund to local interests. 29. Includes $82,600 refund to local interests. 30. Includes preauthorization study funds: FY 82, $12,500; FY 83, $3,291; and preconstruction and construction funds: FY 83, $100,009. 31. Includes preauthorization study costs: FY 82, $12,500; FY 83, $3,291; and preconstruction costs: FY 83, $16,169. 32. Includes monitoring costs: FY 80, $7,414; FY 81, $10,842; FY 82, $1,382. 33. Preauthorization cost. 34. Includes preauthorization study funds: FY 83, $45,000; FY 84, $9,986; and preconstruction funds: FY 84, $50,014; FY 85, $115,000. 35. Includes preauthorization study costs: FY 83, $42,496; FY 84, $12,490; and preconstruction costs: FY 84, $23,281; FY 85, $127,330. 36. Includes Special Recreation Use Fees funds: FY 74, $4,000; FY 75, $5,500; FY 76 & 76T, $3,600; FY 77, $5,800; FY 78, $7,200; 'Y 79, $8,000; FY 80, $10,000; FY 81, $10,000; FY 82, $11,040; FY 83, $7,000; FY 84, $9,000. 37. Includes Special Recreation Use Fees costs: FY 74, $4,000; FY 75, $4,400; FY 76 & 76T, $4,666; FY 77, $5,193; FY 78, $6,824; FY 79, $7,506; FY 80, $11,312; FY 81, $9,688; FY 82, $9,727; FY 83, $7,000; FY 84, $8,444; FY 85, $2,379. 38. Includes Special Recreation Use Fees funds: FY 74, $35,000; FY 76 & 76T, $48,000; FY 77, $51,400; FY 78, $115,100; FY 79, $63,000; FY 80, $60,000; FY 81, $80,000; FY 82, $67,160; FY 83, $77,759; FY 84, $73,000; and maintenance and operation of Dams funds: FY 79, $167,646. 39. Includes Special Recreation Use Fees costs: FY 75, $35,000; FY 76 & 76T, $13,606; FY 77, $85,692; FY 78, $114,604; FY 79, $1,120; FY 80, $118,718; FY 81, $83,760; FY 82, $67,160; FY 83,$77,759; FY 84, $67,850; FY 85, $5,149; and maintenance and operation of Dams costs: FY 79, $167,350; FY 80, $296. 40. Includes Special Recreation Use Fees funds: FY 75, $47,000; FY 78, $40,400; FY 79, $22,000; FY 80, $25,000; FY 81, $20,000; FY 82, $20,240; FY 83, $21,000; FY 84, $19,000. 41. Includes Special Recreation Use Fees costs: FY 75, $13,741; FY 76 & 76T, $31,666; FY 77, $1,593; FY 78, $39,771; FY 79, $22,629; FY 80, $24,619; FY 81, $20,381; FY 82, $20,240; FY 83, $21,000; FY 84, $19,000. 6-21 REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1985 TABLE 6-B AUTHORIZING LEGISLATION Acts Work Authorized Documents July 25, 1912 July 25, 1912 August 8, 1917 July 18, 1918 Jan. 21, 1927 July 3, 1930 March 4, 19332 June 26, 19343 August 26, 1937 August 26, 1937 June 20, 1938 June 20, 1938 March 2, 1945 June 30, 1948 May 17, 1950 May 17, 1950 September 3, 1954 Nov. 29, 1963, sec. 107 July 14, 1960 April 7, 1966, sec. 107 July 14, 1960 Nov. 7, 1966 Nov. 7, 1966 Dec. 31, 1970 ATLANTIC INTRACOASTAL WATERWAY BETWEEN NORFOLK, VA., and ST. JOHNS RIVER, FLA. (See Section 2 of text) Original route of the Norfolk-Beaufort Inlet section. Purchase of canal. Change in route; following changes approved by Secretary of War, April 14, 1919: Albemarle Sound-Pamlico Sound section: Changed from "Alligator River-Rose Bay route" to "Alligator River- Pungo River route." Pamlico Sound-Neuse River Section: Changed from "Pamlico Sound-Brant Shoal Neuse River route" to "Goose Creek-Bay River route." Alligator River-Pungo route (proposed land cut connecting the rivers): Changed from a straight line to a bent line approaching nearer town of Fairfield, N. C. A 12-foot channel 90 feet wide from Beaufort to Cape Fear River, N. C., including highway bridge and tidal lock.' An 8-foot channel 75 feet wide from Cape Fear River to Winyah Bay, S. C. Construct a suitable bridge near Fairfield, N. C. Operating and care of works of improvements provided for with funds from War Department appropriations for rivers and harbors. Increasing dimensions of waterway to 12 feet deep and 90 feet wide. A 12-foot side channel 90 feet wide to Swansboro. A yacht basin near Southport, 12 feet deep, 230 feet wide, and 450 feet long, with connecting channel. A 6-foot channel 90 feet wide from New River Inlet to Inland Waterway. Six mooring basins. A 12-foot channel in New River.5 Vicinity of Fairfield -drainage. Masonboro Inlet and connecting channels, including jetties at the inlet.' A 12-foot channel and basin in Peltier Creek.' A 6-foot channel 90 feet wide from Intracoastal Waterway to Bogue Inlet gorge. An 8-foot channel 150 feet wide through New Topsail Inlet, thence a 7-foot channel 80 ft. wide to Intracoastal Waterway by way of Old Topsail Creek; and a 7-foot channel 80 feet wide in Banks Channel from New Topsail Inlet, paralleling barrier beach, to Intracoastal Waterway. Maintenance of a channel, 6 feet deep, 80 feet wide, and 8,000 feet long, from the through channel of the waterway to and including a basin of the same depth, 130 feet wide and 180 feet long at Carolina Beach. Maintenance of general navigation features of N. C. State Ports Authority Small Boat Harbor at Southport. Replacement of Federally-owned and operated highway bridges at Coinjock, Fairfield, Wilkerson Creek, Hobucken, and Core Creek. H. D. 391, 62d Cong., 2d sess. H. D. 589, 62d Cong., 2d sess. H. D. 1478, 63d Cong., 3d sess. and H. D. 1136, 64th Cong., 1st sess.1 Approved by Secretary of War, May 15, 1919. H. D. 450, 69th Cong., 1st sess. H. D. 41, 71st Cong., 1st sess. Rivers and Harbors Committee Doc. 5, 72d Cong., 1st sess. Rivers and Harbors Committee, Doc. 6, 75th Cong., 1st sess.' Rivers and Harbors Committee Doc. 16, 75th Cong., 1st sess.' H. D. 549, 75th Cong., 3d sess.1 H. D. 691, 75th Cong., 3d sess.' H. D. 660, 76th Cong., 3d sess.' H. D. 421, 80th Cong., 1st sess.' H. D. 723, 80th Cong., 2d sess.' H. D. 341, 81st Cong., 1st sess.' H. D. 379, 81st Cong., 1st sess.' Detailed Project Report April 1963. Detailed Project Report July 1965 H. D. 515, 89th Cong., 2d sess.1 H.D. 514, 89th Cong., 2d sess.1 H. D. 142, 92nd Cong., 1st sess. 6-22 WILMINGTON, N. C., DISTRICT TABLE 6-B (Continued) AUTHORIZING LEGISLATION Acts Work Authorized Documents October 22, 1976 August 13, 1968 February 18, 1982, sec. 107 July 14, 1960 September 7, 1983, sec. 107 July 14, 1960 March 3, 1881 March 2, 1907 March 3, 1925 July 3, 1930 March 2, 1945 May 17, 1950 May 21, 1965, sec. 107 July 14, 1960 August 12, 1983, sec. 107 July 14, 1960 July 3, 1930 Oct. 17, 1940 Feb. 7, 1967 sec. 107 July 14, 1960 August 30, 19358 August 26, 1937 March 2, 1945 March 2, 1945 Modification of terms of local cooperation to allow for full Federal funding of Wilkerson Creek and Coinjock Bridges. Mitigation of damages caused by north jetty at Masonboro Inlet. An 8-foot channel 150 feet wide through Carolina Beach Inlet to the Intracoastal Waterway. An 8-foot channel 150 feet wide from the gorge in Bogue Inlet through the ocean bar. BEAUFORT HARBOR, N. C. (See Section 4 of text) A 9-foot channel 200 feet wide through Bulkhead Channel to Beaufort; a 6-foot channel 100 feet wide to North River and Core Sound; and construct jetties on Shackleford Point. Repairs to Fort Macon jetties and additional jetties and shore protection. Bulkhead across Bird Shoal. Increase in depth to 12 feet in Bulkhead Channel, Gallants Channel, and in front of Beaufort. Increase in width and length of basin in front of Beaufort, all to 12 feet deep. Increase in depth to 12 feet and in width to 100 feet in Taylors Creek; transfer to Beaufort Harbor project. Channels 15 feet deep, 100 feet wide in Bulkhead, Gallants and Taylors Creek channels, and through turning basin in front of Beaufort; and harbor of refuge in Town Creek, 12 feet deep, 400 feet wide, and 900 feet long connected to Gallants Channel by channel 12 feet deep, 150 feet wide, and 1,400 feet long. A channel 14 feet deep, 70 feet wide, and 1,900 feet long, from Bulkhead Channel to a turning basin 14 feet deep 150 feet wide, and 300 feet long near the upper end of Morgan Creek. SILVER LAKE HARBOR, N. C. (See Section 13 of text) Entrance channel, 5 feet deep and 50 feet wide, from Pamlico Sound to the 3-foot contour in the lake, and training wall at entrance. Channel, 10 feet deep, and anchorage basin of same depth, 100 feet wide across Big Foot Slough and 60 feet wide in entrance. Basin depth of 12 feet in Silver Lake Harbor; channels 12 feet deep, 150 feet wide, in Teaches Hole and Big Foot Slough Channels and across Bluff Shoal; entrance channel, same depth, 60 feet wide; and training wall on south side of entrance channel. WATERWAY CONNECTING PAMLICO SOUND AND BEAUFORT HARBOR, N. C. (See Section 14 of text) A 7-foot channel 75 feet wide from Pamlico Sound to Beaufort Harbor via Wainright Channel. A 7-foot channel 74 feet wide to Atlantic. Channels 7 feet deep, 75 feet wide, at east and west ends of Harkers Island and side channel 5 feet deep, 75 feet wide, with basin 150 by 130 feet, same depth, at Davis. A 7-foot side channel 75 feet wide, with basin 200 feet by 500 feet, same depth, at Sealevel. H. D. 597, 94th Cong., 2d sess. Approved by OCE Oct. 2, 1980 Detailed Project Report June 1980 Detailed Project Report May 1983 Annual Report, 1881, p. 1013 Specified in act. Rivers and Harbors Committee Doc. 8, 68th Cong., 2d sess.' H. D. 776, 69th Cong., 2d sess.' H. D. 334, 76th Cong., 1st sess.' H. D. 111, 81st Cong., 1st sess.' Detailed Project Report April 1965 Detailed Project Report June 1983 Rivers and Harbors Committee Doc. No. 3, 70th Cong., 1st sess. H. D. 325, 76th Cong., 1st sess.' Detailed Project Report July 9, 1965 H. D. 485, 72d Cong., 2d sess.' Rivers and Harbors Committee Doc. 92, 74th Cong., 2d sess.' H. D. 99, 77th Cong., 1st sess.' S. D. 247, 77th Cong., 2d sess.' 6-23 REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1985 TABLE 6-B (Continued) AUTHORIZING LEGISLATION Acts Work Authorized Documents May 17, 1950 A 6-foot side channel 60 feet wide, with basin 100 feet by H. D. 68, 81st Cong., 1st sess.' about 600 feet, same depth, at Marshallberg. July 11, 1963, A side channel 7 feet deep, 70 feet wide to local harbor at Detailed Project Report sec. 107 Cedar Island and an access channel 6 feet deep, 60 feet Dec. 12, 1968 July 14, 1960 wide and about 400 feet long to a basin same depth, 60 by 100 feet. Sept. 22, 1967, An entrance channel 6 feet deep, 60 feet wide, from Back Detailed Project Report sec. 107 Sound to harbor of refuge 120 by 250 feet, same depth, at March 13, 1967 July 14, 1960 west end of Harkers Island in Brook Creek. Feb. 24, 1969, A channel 7 feet deep, 70 feet wide, from existing side Detailed Project Report sec. 107 channel at Atlantic to a basin 600 by 180 feet, same depth, Dec. 21, 1967 July 14, 1960 with a breakwater, between mouth of Little Port Brook and White Point. April 3, 1975, Deepening the existing 5-foot channel and basin at Davis Detailed Project Report sec. 107 to 7 feet. Feb. 8, 1974 July 14, 1960' 1. Contains latest published maps. 2. Public Law No. 443, 72d Cong. 3. Permanent Appropriations Repeal Act. 4. Tidal lock in land cut between Myrtle Sound and Cape Fear River. 5. A 12-foot by 90-foot channel in New River from Intracoastal Waterway to and including a basin at Jacksonville, N. C. 6. Jetties on each side of Masonboro Inlet. 7. A 6- by 50-foot channel provided under Section 3, River and Harbor Act of March 2, 1945; 12 by 90-foot project classified as inactive. 8. Included in the Public Works Administration Program, Jan. 3, 1934. 9. Deauthorized by the Chief of Engineers March 31, 1982. 6-24 WILMINGTON, N. C., DISTRICT TABLE 6-C OTHER AUTHORIZED NAVIGATION PROJECTS For Last Cost to September 30, 1985 Full Report See Annual Operation and Project Report for Construction Maintenance Aquatic Plant Control1 (R & H Act of 1958 and 1962) 1969 70,664 - Atlantic Beach Channels, N. C. 1976 29,1014 66,630 Bay River, N. C.1 1950 44,382 49,627 Belhaven Harbor, N. C.' 1982 126,687 40,606 Black River, N. C. 1969 12,358 124,846 Cashie River, N. C. 1950 40,403 15,905 Channel Connecting Thoroughfare Bay with Cedar Bay, N. C.' 1975 69,610 25,615 Channel from Pamlico Sound to Rodanthe, N. C.' 1975 42,029 5,685 Chowan River, N. C. 1950 - - Contentnea Creek, N. C.' 1941 64,395 32,247 Drum Inlet, N. C.' 1979 166,119 1,050,579 Edenton Harbor, N. C.' 1960 73,750 47,642 Fishing Creek, N. C.' 1922 22,715 8,633 Knobb's Creek, N. C.', 2 19613 80,500 47,664 Mackay Creek, N. C.' 19383 13,375 6,273 Neuse River, N. C.' 1982 477,2238 328,607 Newbegun Creek, N. C. 19283 4,802 247 Northeast (Cape Fear) River, N. C.' 1950 10,688 61,139 Pembroke Creek, N. C. 1976 60,000 - Perquimans River, N. C.' 19103 13,750 414 Roanoke River, N. C.' 19833 404,584 550,364 Rollinson Channel, N. C.' 1984 589,105 944,602 Scuppernong River, N. C.' 1950 81,164 80,682 Shallotte River, N. C.' 1984 18,181 169,768 Smith Creek, Pamlico County, N. C.' 1984 113,273 36,387 Smiths Creek (Wilmington), N. C.' 1950 8,507 18 South River, N. C.' 1936 12,452 23,686 Stumpy Point Bay, N. C.' 1984 268,381 736,815 Swift Creek, N. C.' 1940 1,600 5,422 Trent River, N. C.', s 1968 115,199 143,579 Wallace Channel, Pamlico Sound, N. C. 1965 132,834 85,221 Waterway - Norfolk, Va. to Sounds of N. C. 1976 751,196 2,893,812 Waterway Connecting Swanquarter Bay with Deep Bay, N. C. 1984 911,099 182,725 Wrights Creek, N. C.' 1984 68,325 166,602 1. Completed. 2. Transferred from Norfolk District (FY 1970); Meherrin River, N. C., Transferred to Norfolk District. 3. Report of Norfolk District. 4. Includes $2,055 refund to local interests. 5. 8-foot modification deauthorized August 5, 1977, under authority of Sec. 12, PL 93-251. 6. Includes $1,959 refund to local interests on Dawson Creek, N.C. 6-25 REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1985 OTHER AUTHORIZED BEACH EROSION CONTROL PROJECTS TABLE 6-D For Last Cost to September 30, 1985 Full Report Project See Annual Operation and Report For Construction Maintenance Fort Fisher and Vicinity, N. C. 1984 490,000 - Fort Macon Park, N. C. 1973 620,000 - 6-26 WILMINGTON, N. C., DISTRICT OTHER AUTHORIZED FLOOD CONTROL PROJECTS TABLE 6-E For Last Cost to September 30, 1985 Full Report See Annual Operation and Project Report For Construction Maintenance Black River, Harnett County, N. C.' Broad Creek, Beaufort County, N. C.' Brunswick County Beaches, N. C. (Cape Fear to North Carolina - South Carolina State Line)" Conetoe Creek, N. C.' Contentnea Creek, N. C.' Core Creek, N. C.' Deep Creek, Edgecombe County, N. C.' Ellerbe Creek, Durham County, N. C.' Ellis Swamp, Gates County, N. C.' Filberts Creek, N. C.' Gapway Swamp, N. C. & S. C.',' 0 Gardners Creek, N. C.' Goldsboro, Neuse River, N. C. Howards Mill Lake, N. C.' 2 Joyce Creek, Camden County, N. C.' Leith's Creek, Scotland County, N. C.', '5 Lick Run, Roanoke, Va.' Little Rockfish Creek, Hope Mills, N. C.' Little Sugar Creek, Charlotte, N. C.','o New River, N. C.' New River, Onslow County, N. C.' Northeast (Cape Fear) River, N. C.' Ocracoke Island, N. C.'3 Old Field Swamp, N. C.','0 Pantego Creek and Cucklers Creek, N. C. Pasquotank River, N. C. Perquimans River, N. C.' Pungo Creek, N. C.' Pungo River, N. C.' Reddies River Lake, N. C. 5 Roaring River Lake, N. C.' s Simmons Bay, N. C.' 0 South Creek, N. C.' Swift Creek, Pitt and Craven Counties, N. C.' Tar River, N. C Tar River, N. C.' Tar River and tributaries, N. C.' Tar River, Princeville, N. C. Trent River, N. C.'1 Waccamaw River & Seven Creeks, N.C. & S.C.', 10 White Oak Dike, Bladen and Pender Counties, N. C.' Wrightsville Beach, N.C. 1984 1972 1976 1960 1939-1943 & 1958 1965 1984 1963 1971 1970 1969 1972 1984 1980 1984 1982 1974 1978 1979 1950 & 1956 1972 1961 1975 1969 1963 1960 1961 1972 1971 1980 1978 1963 1971 1966 1964 1947 1943 1967 1953 1961 1963 1983 1. Project authorized by Chief of Engineers under special continuing authority. 2. Includes $17,356 refund to local interests. 3. Adjusted to reflect actual cost. 4. Includes $3,081 refund to local interests. 5. Includes $116,508 refund to local interests. 6. Includes $1,519 refund to local interests. 7. Includes $387 refund to local interests. 8. Includes $338 refund to local interests. 9. Adjusted $3,000 to include preauthorization cost prior to FY 1960. 10. Transferred from Charleston District, FY 1980. 11. Reclassified to inactive category February 3, 1976. 12. Reclassified to deferred category October 2, 1980. 13. Reclassified to inactive category November 25, 1974. 14. Includes $61,585 refund to local interests. 15. Transferred from Charleston District, FY 1984. 16. Includes $1,057 refund to local interests. 6-27 475,574 283,846 572,114 s 29,867 50,889 236,223' 394,055 223,413 138,117'6 37,7773 374,005 54,597' 50,430 698,400 606,18916 430,151 1,280,317 113,657 763,022 51,896 580,977 95,873 129,592 86,600 517,948 80,931 6,366 582,270 296,6022,3 985,800 370,000 186,435 194,3677 611,096 81,266 18,624 22,660 390,249 64,769 67,821 214,286 3,013,188" 623,687 61,473 - - - - - - 623,687 - -147 REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1985 DEAUTHORIZED PROJECTS TABLE 6-G For Last Full Report Federal Contributed See Annual Report Date Funds Funds Project For Deauthorized Expended Expended Adkin Branch, N. C. 1982 8 Sep. 812 219,477 - AIWW - Mooring Basins None 5 Aug. 77' - - Bodie Island, N. C. None 5 Aug. 77' - - Cape Lookout, N. C. None 5 Aug. 77' - - Conoho Creek, N. C. 1974 31 Mar. 782 79,782 - Contentnea Creek, N. C. 1972 31 Mar. 783 4,250 - Davis, N. C. 1982 31 Mar. 824 25,419 - Harbor of Refuge, N. C. 1934 1 Nov. 81' 1,396,653 - Hominy Swamp, N. C. 1973 31 Mar. 782 107,472 - Hyde County Dike, N. C. None 5 Aug. 77' - - MacKay Creek, N. C. 1976 31 Mar. 782 130,900 - Mann's Harbor, N. C. 1973 31 Mar. 78' 7,265 - Mill Creek, N. C. 1973 31 Mar. 782 116,395 - Mocassin Swamp, N. C. 1973 31 Mar. 782 36,680 - Moyock Creek, N. C. 1973 31 Mar. 782 64,416 - Nahunta Swamp, N. C. 1973 31 Mar. 782 65,673 - Neuse River, N. C. None 31 Mar. 78' 30,911 - Neuse River Barrier, N. C. None 5 Aug. 77' - - Neuse River, 300 ft.-wide None 5 Aug. 77' - - channel in front of New Bern North River Dike, N. C. None 5 Aug. 77' - - Rockfish Creek, N. C. 1976 31 Mar. 782 157,721 - Six Runs Creek, N. C. 1971 31 Mar. 782 64,977 - Sweetwater Creek, N. C. 1973 31 Mar. 782 64,584 - Thoroughfare Swamp, N. C. 1976 31 Mar. 782 132,767 - Topsail Beach and None 5 Aug. 77' - - Surf City, N. C. Tranters Creek, N. C. 1974 11 Jan. 852 139,339 - Trent River, Basins and None 5 Aug. 77' - - Access Channels at New Bern, N. C. 1. Deauthorized under authority of Sec. 12, PL 93-251. 2. Deauthorized pursuant to the continuing authority provided the Chief of Engineers under Sec. 205 of the 1948 FC Act, as amended. 3. Deauthorized pursuant to the continuing authority provided the Chief of Engineers under Sec. 208 of the 1954 Flood Control Act. 4. Deauthorized pursuant to the continuing authority provided the Chief of Engineers under Sec. 107 of the R&H Act of 1960 as amended. 6-28 WILMINGTON, N. C., DISTRICT TABLE 6-H RECONNAISSANCE AND CONDITION SURVEYS Project Date Survey Conducted Avon Harbor, N. C. July 1985 Neuse River, N. C. June 1985 Rollinson Channel, N. C. July 1985 Waterway Connecting Pamlico Sound and Beaufort Harbor, N. C. September 1985 NAVIGATION WORK UNDER SPECIAL AUTHORIZATION Navigation Activities Pursuant to Section 107, Public Law 86-645 (preauthorization) TABLE 6-I Study Identification Fiscal Period Cost Atlantic Beach Channels, N. C. 1,907 Harkers Island Harbor,N. C. 12,304 Walters Slough, N. C.1 13,416 White Oak River, N. C. 16,655 1. Includes $7,223 reimbursement to revolving fund. 6-29 TABLE 6-J DAMS AND RESERVOIRS See Miles Height Reservoir Power Estimated Section Project Name Nearest City River Above of Type Capacity Development Construc- Cost Lands Total n rext Mouth Dam (ft) (acre-feet) (kilowatts) tion and Damages 17. Cape Fear River Basin, N.C. 21. Neuse River Basin, N.C. 24. 27. Yadkin River Basin, N.C.&S.C. Roanoke River Basin, Va. and N.C. B. Everett Jordan 2 Howards Mill 2, 14 Randleman 2 Small reservoirs Fals2 Wilson Mills Beulahtown Bakers Mills Little Buffalo Buckhorn Wiggins Mill Stantonsburg Great Swamp Black Creek Aycock Swamp Hillsboro Orange W. Kerr Scott. N.C. John H. Kerr, Va., and N.C. 2 Philpott, Va. 2 Gaston, Va. and N.C. 6 Roanoke Rapids, N.C. 7 Smith Mountain. Va. 8 Leesville, Vs.9 Taber, Va. Melrose, Va. Randolph, Va. Stuart, Va. and N.C. Schoolfield. Va. and N.C. Moncure, N.C. Carthage, N.C. Randleman, N.C. Falls, N.C. Wilson Mills, N.C. Kenly, N.C. Princeton, N.C. Kenly, N.C. Wilson, N.C. Wilson, N.C. Stantonsburg, NC. Fremont, N.C. Wilson, N.C. Fremont, N.C. Durham, N.C. Durham, N.C. Wilkesboro, N.C. Boydton, Va. Bassett. Va. Roanoke Rapids. N.C. Roanoke Rapids, N.C. Altavista, Va. Altavista, Va. Altavista, Va. Brookneal, Va. Chase City, Va. Spray, N.C. Danville, Vs. Haw Deep Deep Various Neuse Neuse Little Little Little Buffalo Creek Contentnea Creek Contentnea Creek Tisnot Swamp Great Swamp Black Creek Aycock Swamp Eno Little Yadkin-Pee Dee Roanoke Roanoke Roanoke Roanoke Roanoke Roanoke Roanoke Roanoke Roanoke Roanoke Roanoke 4.3 55.0 85.0 404.0 178.7 336.2 144.9 137.0 314.2 293.7 275.0 262.9 227.8 297.2 265.9 112 106 110 20 to 70 + 92 81 50 53 51 63 42 36 39 33 37 136 107 148 E E E E E CG,E E E E E E E E E E E E E 778,000 233,000 108,000 923,000 397,000 201,000 81,000 36,000 13,000 119,000 35,000 48.000 18,000 17,000 7.000 123,000 57,.000 153,000 144 CGE 2.808,000 204,000 220 108 75 244 95 54 110 147 138 126 CGll CG.E CG CG CG,E CG CG.E CG,E E CG.E 249.800 432.000 59,300 825,000 76,900 34,000 120,000 350.000 163,000 248,000 14,000 54.000 83,000 41.000 20.000 12,000 43,000 48,000 15.000 80,000 77,672,800 58,327,200 18,874,000 14,726,000 52.902,000 59,098,000 76,070,600 90,929,400 5,749,343 3,360,657 67,529,000 24,521,000 13,933.000 27,000,000 31,300,000 28.000.000 9,100,000 8.000,000 17,700.000 22,100,000 9,000.000 27.800,000 1,157,000 3,500,000 800,000 3,800,000 1,000,000 1,700,000 6,000,000 4.700.000 1.100,000 6,400,000 1. Includes highway, railroad, and utility relocations. 2. For details, see individual report. 3. Includes $3,900,000 presently allocated to water supply to be reimbursed in the future by local interests. 4. Includes $12,400,000 presently allocated to water supply and $20,600,000 recreation and fish and wildlife to be reimbursed in the future by local interests. 5. Exclusive of transmission lines. 6. Construction completed in 1963 by Virginia Electric and Power Co. 7. Based on modified plan developed in fiscal year 1949. Construction completed June 1955 by Virginia Electric and Power Co. 8. Construction completed in February 1966 by Appalachian Power Co. 9. Construction completed in June 1963 by Appalachian Power Co. 10. Includes cost of earth dam on Whipping Creek. 11. Authorizing legislation provided for earth dam; concrete gravity dam constructed. 12. Includes $1,600,000 presently allocated to recreation and fish and wildlife. 13. Includes $51,064,000 presently allocated to water supply, and $21,479,000 allocated to recrea tion and $4.257.000 to flood control to be reimbursed in the future by local interests. 14. Reclassified to the deferred category October 2. 1980. Key E - Earth CG - Concrete Gravity O OE 0 0 bid 136,000,000' 33,600,0002 112,000,000" 38,454,000 167,000,000' 13,000,000 9.300,000 6,600,000 1,100,000 17,300,000 6,700.000 5.100,000 1.800.000 1.500,000 550,000 8,100,000 3,500,000 9,110,000 92,050,000' 15,090,000 30.500.000 32,100,000 31,800,000 10,100,000 9,700,000 23,700,000 ' 26,800,000 10,100,000 36.000.000 WILMINGTON, N. C., DISTRICT FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION Flood Control Activities Pursuant to Section 205, Public Law 858, 80th Congress, as amended TABLE 6-K IPreauthorization) Study Identification Fiscal Period Cost Carvins Creek, Roanoke, VA. 7,500 Chapel Hill, N. C.' 7,500 Crabtree Creek & Trib., Wake County, N. C. 58,135 Danville, Va. 23,917 Falling Creek, Rockingham, N. C. 7,500 Great Coharie Creek, N. C. 41,994 Little Gunpowder Creek, N. C. 6,300 Lower Creek, N. C. 18,492 Silas Creek, N. C.' 6,000 1. Reimbursement to revolving fund. 6-31 CHARLESTON, S.C., DISTRICT* This district comprises all of South Carolina (except local watersheds draining into the Savannah River). It embraces the drainage basins tributary to the Atlantic Ocean between Little River and Port Royal Sound, except watersheds of Mackey and Skull Creeks, and excluding Hilton Head Island. IMPROVEMENTS Navigation Page 1 Aquatic Plant Control, SC ................... 7-2 2 Atlantic Intracoastal Waterway Between Norfolk, VA and St. Johns River, FL........ 7-2 3 Charleston Harbor, SC ...................... 7-2 4 Cooper River, Charleston Harbor, SC ......... 7-3 5 Cooper River Seismic Modification, Charleston Harbor, SC .................... 7-4 6 Folly River, SC.............................7-4 7 Georgetown Harbor, SC ..................... 7-4 8 Jeremy Creek, SC...........................7-5 9 Little River Inlet, NC & SC..................7-5 10 Murrells Inlet, SC...........................7-5 11 Port Royal Harbor, SC ...................... 7-6 12 Shipyard River, SC..........................7-6 13 Town Creek, SC............................7-6 14 Village Creek, SC ............................ 7-6 15 Reconnaissance and Condition Surveys........7-7 16 Other Authorized Navigation Projects ......... 7-7 17 Navigation Work Under Special Authorization .............................. 7-7 Beach Erosion Control 18 Other Authorized Beach Erosion..............7-7 Control Projects Page 20 Eagle Creek, SC ............................ 7-7 21 Wilson Branch, SC ........................... 7-7 22 Inspection of Completed Flood Control Projects...........................7-8 23 Other Authorized Flood Control Projects....... 7-8 24 Flood Control Work Under Special Authorization.............................7-8 General Investigations 25 Active Investigations ........................ 7-8 Tables Table 7-A Cost and Financial Statement............7-9 Table 7-B Authorizing Legislation ................ 7-11 Table 7-C Other Authorized Navigation Projects..... 7-14 Table 7-D Navigation Work Under Special Authorization ........................ 7-15 Table 7-E Other Authorized Beach Erosion Projects ... 7-15 Table 7-F OtherAuthorized Flood Control Projects .... 7-16 Table 7-G Flood Control Work Under Special Authorization ........................ 7-16 Table 7-H Active General Investigations .......... 7-17 Flood Control 19 Cow Castle Creek, SC.......................7-7 *All costs and financial statements for projects are listed at the end of this chapter. All other tables are referenced in text and also appear at the end of this chapter. 7-1 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Navigation 1. AQUATIC PLANT CONTROL, S.C. Location. The project areas include navigable water, tributary streams, connecting channels, and other allied waters in the State of South Carolina. Existing Project. The project provides for control and progressive eradication of water hyacinth, alligator weed, Eurasian watermilfoil, and other noxious aquatic plant growths from navigable waters, tributary streams, connecting channels, and other allied waters of the United States, in combined interest of navigation, flood control, drainage, agriculture fish and wildlife conservation, public health and related purposes, including continued research for development of most effective and economic control measures in cooperation with other Federal and State agencies in accordance with report of Chief of Engineers. The act provides that research and planning cost shall be borne fully by the United States. (See table at end of chapter for acts authorizing existing project.) Local Cooperation. Local interests must agree to hold the United States free from damages that may occur from operations performed in connection with this project and contribute 30 percent of the cost of field operations. The South Carolina Water Resources Commission (WRC) is designated as the State's lead agency for aquatic plant management and meets the local interest requirement of paying 30 percent of the cost of field operations. The project provides for a comprehensive plan of chemical, biological, and integrated control measures for managing noxious aquatic plants within the state waters of South Carolina. Operations and results during fiscal year. Aquatic plants now infest approximately 40,000 acres, with the worst problems being in Lake Marion. During FY 85 5,500 acres of aquatic plants in 40 water bodies were treated with herbicides. Grass carp was purchased and stocked in 19 lakes having a total surface area of 2,500 acres. Condition at end of fiscal year. The cost of field operations in FY 85 was $595,000 and included $458,500 for the application of herbicides, $75,600 for the purchase and stocking of grass carp, $38,500 for aquatic plant surveys, and $22,400 for program management by the contractor. The cost of planning and reconnaissance surveys was $62,623. 2. ATLANTIC INTRACOASTAL WATERWAY BETWEEN NORFOLK, VA AND ST. JOHNS RIVER, FL (CHARLESTON DISTRICT) Location. The project starts at Little River at the North Carolina-South Carolina state line and extends generally south along the coast of South Carolina 62 miles to Winyah Bay; thence 63.5 miles to Charleston; thence 84.5 miles to and including Port Royal Sound; a total of 210 miles. (See National Ocean Survey Charts Nos. 11512, 11521, 11531, 11534, and 11535.) Previous Projects. For further details see page 613 of Annual Report for 1932. Existing project The project provides for a waterway twelve feet deep and not less than 90 feet wide with a branch channel of the same dimensions to McClellanville and construction of three bridges crossing the waterway in Horry County, South Carolina. (See table at end of chapter for acts authorizing existing project.) Local cooperation. Requirements fully satisfied. Terminal facilities. There are rail-water terminals at Georgetown, Charleston, Johns Island, and Port Royal and numerous open-pile wharves mostly for shipping agricultural products, fish, oysters, pulpwood, wood products, and petroleum products. Marinas are located at convenient intervals along the waterway where limited supplies and repair facilities are available for both commercial vessels and pleasure craft. Facilities are considered adequate for existing commerce and recreation requirements. Operations and results during fiscal year. Maintenance: Contract maintenance dredging was performed by pipeline dredge in the Cove Inlet Area during June 1985, removing 85,843 cubic yards of material, and between Winyah Bay and Charleston, S.C. during July-August 1985, removing 878,513 /cubic yards at a total cost of $985,798. Bank stabilization costs for the Myrtle Beach, S.C. area were $659,000 and the mosquito abatement control contract costs were $83,680. The cost of operating the Snagboat Snell in the Winyah Bay to Little River area was $178,968. Costs of $687,664 were also incurred for contract dike management. Condition and operations studies, natural resource management, water control management, engineering and design, and supervision and administration costs were $656,073. Condition at end of fiscal year. Existing project was completed in 1940; three bridges were completed in 1936. Federal costs of existing project to date have been $7,345,888 for new work and $41,904,494 for maintenance for a total of $49,250,382. 3. CHARLESTON HARBOR, S.C. Location. The harbor is located on the coast of South Carolina about 15 miles south of the midpoint of the coastline, 50 miles southwest of Winyah Bay, S.C., and 80 miles northeast of the mouth of Savannah River. (See National Ocean Survey Charts Nos. 11521 and 11524.) Previous projects. For further details see page 1808 of Annual Report for 1915; page 579 of Annual Report for 1926; and page 562 of Annual Report for 1938. Existing project. The authorized project provides for a channel 35 feet deep with varying widths from the Atlantic Ocean to the mouth of Goose Creek, a total of 26.3 miles, together with a 35-foot depth by 500-foot width channel via Town Creek. Also, a ten foot depth by 110-foot width channel on the Mount Pleasant side of the harbor into Shem Creek to U.S. Highway 17 Bridge, and a 30-foot anchorage basin in the lower harbor between Castle 7-2 CHARLESTON, S.C., DISTRICT Pinckney and Fort Moultrie. A 40-foot channel estimated to cost $6,060,000 (1960) was authorized to be executed when found necessary in the interest of national defense from the 40-foot contour in Atlantic Ocean to U.S. Naval Base. For futher details see page 425 of Annual Report for 1962. The Phase I Design Memorandum stage of Advance Engineering and Design for deepening of the 35-foot channel to 40 feet (42 feet in the ocean bar and entrance channel) from the 42-foot ocean contour to Goose Creek, a total distance of 26.9 miles, construction of one turning basin, modification of existing turning basins, deepening and modification of the anchorage basin, and deepening Shipyard River to 38 feet have been authorized. (See table at end of chapter for acts authorizing existing project.) Local cooperation. Local interests have fully complied with their responsibility to date but are experiencing difficulty securing disposal areas for dredged material for continued future maintenance. Terminal facilities. Piers and slips extend for about one mile along the eastern waterfront of the City of Charleston with an additional mile of marginal wharves. The South Carolina State Ports Authority operates eight piers for fruit, wood, cold storage facilities and general cargo, a grain elevator and a beltline railway which serves the entire Cooper River waterfront. Modern facilities are also at wharves of seven major petroleum companies including storage tank farms. Modern facilities for marine repairs and servicing are available at Detyens Shipyard, located approximately ten miles northeast of Charleston on the Wando River. The U.S. Navy Department has modern facilities for construction and maintenance of naval vessels including nuclear-powered submarines. Loading docks and storage areas for missile-carrying type vessels have also been constructed and are being operated by the U.S. Navy. For further details see Port Series No. 13, 1970, Corps of Engineers. Operations and results during fiscal year. Maintenance: Contract maintenance dredging was performed in (a) the Lower Harbor by pipeline dredges during October 1984- February 1985 and July-August 1985 removing 1,539,676 cubic yards of material, (b) in the Anchorage Basin during September 1985 removing 450,401 cubic yards of material, and (c) in the Upper Harbor during January-April 1985 and May-September 1985 removing 508,285 cubic yards, resulting in an overall total FY 85 dredging cost of $3,444,682. Funds of $46,935 for work performed in FY 1984 were also expended this fiscal year. Government furnished materials for dike management cost $1,471. Contract dike management costs were $892,634. Costs of Riverine Utility Craft operation were $16,707. Condition and operations studies, water control management, engineering and design, and supervision and administration costs were $798,585. Condition at end of fiscal year. Jetties protecting the entrance channel across the bar were completed in 1985. The existing project was completed in October 1962 except for the national defense portion. Federal costs under the existing project to date have been $3,328,349 for new work and $86,138,046 for maintenance, a total cost of $89,466,395. 4. COOPER RIVER, CHARLESTON HARBOR, S.C. Location. Cooper River is located in Charleston and Berkeley Counties, S.C., and empties into the Atlantic Ocean at Charleston (See National Ocean Survey Charts Nos. 11521 and 11524.) Existing project The major cause of the shoaling problem in Charleston Harbor was the diversion of fresh water from the Santee River through Pinopolis Dam into the salt water of Charleston Harbor, which caused density currents which traps sediments resulting in a phenomenal rate of deposition. The most practical solution of the shoaling problem was to redivert most of the Santee River waters above Pinopolis Dam back into the lower Santee River through a canal beginning at Lake Moultrie and extending to the Santee River in the vicinity of St. Stephen, South Carolina. The project for Cooper River as authorized by the 1968 River and Harbor Act provided that the discharge through the existing Pinopolis Hydroplant be reduced to a weekly average of 3,000 cubic feet per second. This flow will not establish a density current in the harbor. The excess water impounded in Lake Moultrie is being directed through a new canal above St. Stephen, South Carolina, to enter the Santee River at a point well below the Lake Marion Spillway (Wilson Dam). A new hydroelectric facility has been constructed on the new canal at the edge of the swamp adjacent to the Santee River. This plant replaces those features made less effective at Pinopolis through curtailment of flows. The average flow of 12,600 cfs at the new powerplant, plus the proposed 3,000 cfs average release planned for Pinopolis, approximates the existing average Pinopolis flow. The three generators at the new plant are rated at 28,000 kilowatts each, for a total of 84,000 kilowatts. In the interest of fish and wildlife resources of the area, the plan includes a herring lift at the new powerhouse site and a relocated fish hatchery. Estimated cost of the project (1985) is $191,500,000, all Federal. (See table at end of chapter for acts authorizing existing project.) Local cooperation. None required. Operations and results during fiscal year. New Work: Funds were received for initiation of construction during FY 75. Costs during FY 85 were $9,733 for lands and damages, $19,899 for relocations, $6,650,175 for power plant, $1,710 for fish and wildlife facilities contract, $28,000 for turbines, $1,995,643 for the scour hole contract, $33,316 for the piezometer installation, $209,208 for generators, $11,080 for governors, -$85,957 for the entrance canal, $850,251 for the intake canal, $4,042 for main control switchboards, $282,891 for cooling water facilities-towers, -$1,687 for cooling water facilities-general construction, $9,315 for buildings, grounds and utilities, $1,230 for cultural resources preservation, -$10,718 for permanent operating equipment, and supervision and administration costs were $1,327,954. Maintenance. Funds of $1,839,765 were spent for maintenance of completed work. 7-3 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Condition at end of fiscal year. Preconstruction planning was completed at the end of FY 74. The General Design Memorandum was completed in January 1972 and work is proceeding on schedule on other phases of the project. Construction was initiated March 1977. The project is 99% complete. The power-on-line date was March 1985. 5. COOPER RIVER SEISMIC MODIFICATION Location. The Cooper River Seismic Project is located in Berkeley County, South Carolina, about 50 miles north of Charleston, South Carolina. Existing project The Santee-Cooper Project was constructed in the early 1940's using the latest state-of-theart design for that time. The project is currently licensed by the Federal Energy Regulatory Commission (FERC) as project No. 199. The FERC requires that the project receive independent inspections at least once every five years. It was during the 1977 inspection that the seismic deficiency of both the West and North Dams was noted. This was confirmed again in the 1982 inspection. As a result of studying the possible consequences of the loss of both dams, the S.C. Congressional Delegation introduced legislation which was approved in the 1983 Supplemental Appropriations Act to provide $2 million for design and $22 million for construction of remedial measures. The design and construction responsibility was assigned to the U.S. Army Corps of Engineers. The Corps began in August 1983 to study various alternatives to provide a closure structure in the canal between the two lakes of the project and to provide remedial measures for the liquifiable foundation of the West Dam. Current estimated cost of the project is $22,000,000, all Federal. Local cooperation. None required Condition at end of fiscal year. At the end of FY 85, the initial evaluation report had been submitted to SAD and OCE for approval and additional subsurface testing was ongoing at the West Dam. Additional stability analysis of the West Dam was completed and a compaction grouting test program was completed which indicated that compaction grouting was technically feasible. A contract for deformation analysis was awarded at the end of the fiscal year. 6. FOLLY RIVER, S.C. Location. The project begins in Folly River and Folly Creek north of the Town of Folly Beach and follows a southwesterly course into the Atlantic Ocean. (See National Ocean Survey Chart No. 11521.) Existing project. The project provides: an entrance channel, eleven feet deep by 100 feet wide extending from the Stono River one mile through the ocean bar; a channel within Folly River nine feet deep and 80 feet wide, extending three miles downstream from U.S. Highway 171 to the confluence of Folly and Stono Rivers; and a channel within Folly Creek nine feet deep by 80 feet wide extending three miles downstream from Highway 171 to the confluence with Folly River. Local cooperation. Requirements fully satisfied. Operations and results during fiscal year. Maintenance: Maintenance dredging was performed (a) in the entrance bar by the sidecaster dredge, Merritt, removing 24,738 cubic yards at a cost of $92,419, (b) and on Folly Rives (inside) by contract, removing 33,586 cubic yards at a cost of $129,324. Condition and operations studies, water control management, engineering and design, and supervisions and administration costs were $35,616. Condition at end of fiscal year. The existing projeci was completed in FY 1979. Federal costs for the existing project to date have been $337,736 for new work and $844,688 for maintenance, a total of $1,182,424. 7. GEORGETOWN HARBOR, S.C. Location. The harbor is located on the coast of Soutt Carolina 50 miles northeast of Charleston Harbor and 9C miles southwest of the entrance to Cape Fear River, Norti Carolina. (See National Ocean Survey Chart No. 11532.) Previous projects. For further details see page 1806 of Annual Report for 1915; page 549 of Annual Report for 1938; and page 442 of Annual Report for 1944. Existing project. The authorizations provide for a channel 27 feet deep with varying widths of 600 feet to 400 feet from the Atlantic Ocean to and including a turning basin at the U.S. Highway 17 bridge over Sampit River, with a side channel 2,400 feet long and not less than 200 feet wide leading to a turning basin at the upper end of the built-up portion of the city waterfront, a total of 17.9 miles. The project also provides for the continued maintenance tc a depth of 18 feet and a width of 400 feet for the bypassed portion of Sampit River opposite the City of Georgetown. (See table at end of chapter for acts authorizing existing project.) Local cooperation. Fully satisfied. Terminal facilities. Terminal facilities at the Port ol Georgetown, suitable for oceangoing vessels, consist of one marginal concrete pier and one of creosoted-timber construction. For intracoastal waterway traffic there are a number of smaller wharves and landings along the Georgetown waterfront on the old channel. For further details, see Port Series No. 13, 1970, Corps of Engineers. Operations and results during fiscal year. Maintenance: Maintenance dredging was performed in the Sampit Rive from October-December 1984 and August-Septembel 1985 removing a total of 1,194,338 cubic yards of materia at a cost of $1,091,704. Contract dike management costs were $379,855. Costs for the Riverine Utility Craft wert $8,691, and the cost of government furnished materials foi dike management were $10,025. Condition surveys, wate control management, engineering and design and supervisior and administration costs were $323,949. 7-4 CHARLESTON, S.C., DISTRICT Condition at end of fiscal year. The existing project was completed in 1951. The jetties were completed in 1903-04. Federal costs for the existing project to date have been $4,615,903 for new work and $39,567,301 for maintenance, a total of $44,183,204. 8. JEREMY CREEK, S.C. Location. Jeremy creek is located at McClellanville, S.C. approximately 40 miles northeast of Charleston and 20 miles southwest of Georgetown. (See National Ocean Survey Charts Nos. 11531 and 11518). Existing project The dredging of Jeremy Creek or "Side Channel to McClellanville" was authorized as a part of the channel from Charleston to McClellanville (or part of what is now the Atlantic Intracoastal Waterway) by the River and Harbor Act of 2 March 1907. The project provides for a waterway twelve feet deep at mean low water and a width of not less than 90 feet. Local cooperation. Local requirements have been met by the S.C. Coastal Council. Terminal facilities. There are three shrimping facilities, one oyster packing shed, a crabbing operation, an icehouse, a fuel dock, and a public launching ramp located on Jeremy Creek. The commercial facilities are privately owned, but are open to all on an equal basis. The existing facilities are considered adequate for present and near future commerce. There are areas along the east bluff shore available for the expansion of existing facilities or the construction of new ones. Operations and results during fiscal year. Engineering and design costs were $343. Condition at end of fiscal year. Federal costs of existing project to date have been $49,297 for new work and $3,000 for maintenance, a total of $52,297. 9. LITTLE RIVER INLET, N.C. AND S.C. Location. The project is located near the North Carolina-South Carolina state line. Little River enters the Atlantic Ocean at Little River Inlet at the state line and affords the only connection between the Atlantic Intracostal Waterway and the ocean along 68 miles of coastline from Shallotte, N.C. to Georgetown, S.C. (See National Ocean Survey Chart No. 11535.) Existing project. The project provides for an entrance channel twelve by 300 feet across the ocean bar; thence a ten by 90-foot inner channel to the Atlantic Intracoastal Waterway. The entrance channel is stabilized by jetties extending seaward 3,200 feet and 3,000 feet long on the north and south sides of the inlet, respectively. Emergency dredging on an annual basis was authorized by the Water Resources Act of 1974. Previous work was done under the authority of the River and Harbor Act of 1945, Section 3, P.L. 79-14. Local cooperation. Requirements fully satisfied. Terminal facilities. There are eight marinas, numerous private docks, and several public boat ramps located in or near Little River. It is expected that existing facilities will expand and new ones will be added as demands for services exceed current capacity. Operations and results during fiscal year. Condition and operation studies, water control management, and supervision and administration costs were $124,428. Condition at end of fiscal year. The initial construction contract was awarded 14 January 1981. The project is complete. Federal costs for the existing project were $17,036,991 for new work and $2,126,445 for maintenance, a total of $19,163,436. 10. MURRELLS INLET, S.C. Location. The project is located on the coast of South Carolina, in Georgetown County, about 13 miles southwest of the City of Myrtle Beach. The inlet is the ocean entrance through a barrier beach to several tidal streams in the Murrells Inlet-Garden City estuarine area. (See National Ocean Survey Chart No. 11535.) , Existing project The project provides for an entrance channel twelve by 300 feet across the seaward bar; thence a ten by 90-foot inner channel to a turning basin at the old Army crashboat dock. The entrance channel will be stabilized by ocean jetties extending seaward 3,445 feet and 3,319 feet on the north and south sides of the inlet, respectively. The recreational project includes a walkway on the south jetty with access road and parking area. Emergency dredging on an annual basis was authorized by the Water Resources Act of 1974. Previous work was done under the authority of the River and Harbor Act of 1945, Section 3, P.L. 79-14. Local cooperation. A letter of intent to provide local cooperation dated 4 November 1975 has been received from the Georgetown County Board of Commissioners. Local interests have met their responsibilities to date. Terminal facilities. There are five marinas and numerous private docks located about the Murrells Inlet Harbor. There are several public boat ramps in the area. Facilities are expected to be expanded and new ones added as demands for services outstrip capacity. Operations and results during fiscal year. New Work: Costs of $4,127 were incurred. Maintenance: No maintenance dredging performed. Condition and operation studies, water control management costs and supervision and administration costs were $83,886. Condition at end of fiscal year. The jetty construction contract was awarded 2 September 1977. The recreational facilities (comfort station and parking lot) contract was awarded 25 July 1980 and physically completed 7 August 1981. Federal costs for the existing project to date have been $13,403,020 for new work and $985,332 for maintenance, a total of $14,343,142. 7-5 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 11. PORT ROYAL HARBOR, S.C. Location. The harbor is located on the coast of South Carolina 47 miles southwest of Charleston Harbor and 23 miles northeast of Savanah River, Georgia. (See National Ocean Survey Chart No. 11516.) Existing project The authorized project provides for a channel from the ocean through Port Royal Sound to Port Royal, South Carolina, 27 feet deep and 500 feet wide across the ocean bar and in Port Royal Sound for approximately 12.7 miles, thence 24 feet deep and 300 feet wide in Beaufort River and Battery Creek for approximately 8.3 miles to and including a turning basin 27 feet deep and 600 feet wide opposite the wharf of the South Carolina State Ports Authority. (See the table at the end of the chapter for acts authorizing the existing project.) Local cooperation. Requirements fully satisfied. Terminal facilities. The South Carolina State Ports Authority constructed a marginal concrete wharf and operates modern terminal facilities which are considered adequate for present commerce of the port. Operations and results during fiscal year. Maintenance: Condition and operations studies and water quality management costs were $3,814. Condition at end of fiscal year. The existing project was completed in 1959. 12. SHIPYARD RIVER, S.C. Location. This waterway is a tidal tributary of Charleston Harbor, South Carolina. It has its source about one-half mile below the U.S. Naval Base, whence it flows southerly about three miles and empties into the Cooper River about threefourths miles above Drum Island. (See National Ocean Survey Chart No. 11524.) Previous projects. For details, see page 610 of Annual Report for 1932 and page 463 of Annual Report for 1944. Existing project The authorized project provides for a channel 30 feet deep from Cooper River to Airco Alloys' plant, including two turning basins, one opposite Gulf Oil Corporation Terminal and another at the upper end of project. (See table at end of chapter for acts authorizing existing project) Local cooperation. Requirements fully satisfied. Terminal facilities. In the lower three-quarters of a mile of the channel are large marginal wharves of the Gulf Oil Corporation and Shipyard River Terminal Company. These wharves accomodate deep-draft, oceangoing vessels for handling petroleum products and fertilizer materials. In the upper channel is Airco Alloys' wharf for handling ores. For further details see Port Series No. 13, 1970, Corps of Engineers. Operations and results during fiscal year. Maintenance: Maintenance dredging was performed to remove 415,053 cubic yards of material during February and September 1985 at a cost of $417,131. Contract diking costs were $199,511. Condition and operation studies, water control management, supervision and administration, and engineering and design costs were $90,997. Condition at end of fiscal year. The existing project was completed in 1951. Federal costs under the existing project to date have been $487,824 for new work and $8,779,685 for maintenance for a total of $9,267,509. 13. TOWN CREEK, S.C. Location. Town Creek Channel begins at the AIWW directly south of the Town of McClellanville in Charleston County, S.C. The channel follows Five Fathom Creek in a southerly direction to the Atlantic Ocean. (See National Ocean Survey Chart No. 11531.) Existing project The project provides a channel ten feet deep by 80 feet wide from the AIWW to the mouth of Five Fathom Creek, a distance of 6.2 miles. The project includes an entrance channel twelve feet deep by 100 feet wide across the ocean bar, a distance of 4.0 miles. (See table at end of chapter for acts authorizing existing projects.) Local cooperation. Requirements fully satisfied. Operations and results during fiscal year. Maintenance: No maintenance dredging performed. Adjustments in charges for work performed by the Schweizer in FY 1984 resulted in a credit of $15,963 and a total expenditures of -$2,201. Condition at end of fiscal year. The existing project was completed in 1975. Federal costs under the existing project to date have been $219,521 for new work and $1,689,152 for maintenance, a total of $1,908,673. 14. VILLAGE CREEK, S.C. Location. Village Creek is located on the northeastern end of St. Helena in Beaufort County, approximately twelve miles from the Town of Beaufort. This creek, which is about 600 feet wide at its confluence with Morgan River and St. Helena Sound at a point seven miles from the Atlantic Ocean, extends in a southwesterly direction a distance of 6.8 miles to its headwaters. (See National Ocean Survey Chart No. 11513.) Existing project The authorized project provided for a channel eight feet deep and 80 feet wide from the mouth of Village Creek upstream to the Porpoise Fish Company Terminal for a distance of 2.2 miles. (See table at end of chapter for acts authorizing existing project.) Local cooperation. All items of local cooperation have been complied with except the present requirement that a diked disposal area be furnished. In the past, a deep water disposal area has been used and may be used in the future. An environmental assessment of these areas is being prepared. If this assessment supports a negative determination for both areas, all items of cooperation will be fully satisfied. 7-6 CHARLESTON, S.C., DISTRICT Operations and results during fiscal year. Maintenance: No maintenance dredging was performed. Condition operation studies costs and supervision and administration costs were $390. Condition at end of fiscal year. The project was completed in April 1966. Federal costs under the existing project to date have been $26,500 for new work and $100,473 for maintenance, a total of $126,973. 15. RECONNAISSANCE AND CONDITION SURVEYS Costs of $17,284 were incurred for condition surveys. Adams, Creek, S.C. Ashley River, S.C. Santee River, S.C. Village Creek, S.C. Waccamaw River, S.C. $4,372 5,710 2,089 4,643 470 16. OTHER AUTHORIZED NAVIGATION REPORTS (See Table 7-C.) 17. NAVIGATION WORK UNDER SPECIAL AUTHORIZATION Navigation Work Under Special Authorization Pursuant to Section 107, Public Law 86-645, as amended (Preauthorization) and Section III, Public Law 90-433, as amended. (See Table 7-D) Snagging and clearing for navigation (Sec. 3 of 1984 River and Harbor Act, Public Law 14, 79th Congress.) Beach Erosion Control 18. OTHER AUTHORIZED BEACH EROSION CONTROL PROJECTS (See Table 7-E). Flood Control 19. COW CASTLE CREEK, S.C. Location. Cow Castle Creek is located entirely within the limits of Orangeburg County, South Carolina. The creek flows from its headwaters in the City of Orangeburg to its confluence with Four Hole Swamp. The authorized project consists of clearing and snagging approximately 8,000 feet of the channel located near Bowman, S.C. The project was authorized under general authority contained in Section 208 of the Flood Control Act of 1954, as amended. Local cooperation. Local interest must provide lands, easements, and rights-of-way; clean-out approximately 1.7 miles of the Even Branch tributary to Bowman; hold and save the United States free from damages; maintain the project after completion; prevent future encroachments; notify affected interests annually that improvements will not provide complete flood protection; and prevent unwise future flood plain development. Operations and results during fiscal year. The contract was awarded on 22 September 1983 in the amount of $178,000. Funds in the amount of $96 were expended toward the Cow Castle Project this FY. The contract was completed on 2 May 1984. Condition at end of fiscal year. Project included in Completed Flood Control inventory for inspection. 20. EAGLE CREEK, S.C. Location. The Eagle Creek Project is located entirely within the limits of Dorchester County, South Carolina. The creek flows from its headwaters in the subdivisions near Summerville to the Ashley River. Existing project The authorized project consists of clearing and channel excavation of approximately four miles of Chandler Bridge Creek and Eagle Creek. The project was authorized under general authority contained in Section 205 of the 1948 Flood Control Act, as amended. Local cooperation. Local interests must provide lands, easements, rights-of-way, utility relocations and alternations and highway bridge alterations necessary for construction; hold and save the United States free from damages; maintain and operate the project after completion; prevent future encroachments; notify affected interests annually that improvement will not provide complete flood protection; and prevent unwise future flood plain development. Operations and results during fiscal year. Contract was awarded on 28 September 1983 in the amount of $1,245,063. Construction period was 646 calendar days. Funds in the amount of $624,586 were expended toward the Eagle Creek Project, of which, $549,350 was provided by the Productive Appropriations Act of 1983 (PL 97-8). Condition at end of fiscal year. Project was physically completed on 14 August 1985 and will be fiscally completed in December 1985. 21. WILSON BRANCH, S.C. Location. Wilson Branch is located almost entirely within the corporate limits of the Town of Cheraw in Chesterfield County, South Carolina. The creek flows from its headwaters in a residential area to its confluence with Huckleberry Branch, then to the Pee Dee River approximately 1 miles away. Existing project. The authorized project consists of a "non-structural" solution of removing six houses from the flood plain. The project was authorized under general 7-7 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 authority contained in Section 205 of the 1948 Flood Control Act, as amended. Local cooperation. Local interest must provide a cash or in-kind contribution equal to 20% of the project first cost; hold and save the United States free from damages; maintain the project after completion; prevent future encroachments; notify affected interests annually that improvements will not provide complete flood protection; and prevent unwise future flood plain development. Operations and results during fiscal year. The last two houses were purchased, residents relocated, and the houses were removed from the flood plain. Funds in the amount of $7,121 were expended. Condition at end of fiscal year. The project was physically complete on 27 December 1984 and fiscally complete in January 1985. 22. INSPECTION OF COMPLETED FLOOD CONTROL PROJECTS To determine the extent of compliance with approved regulations for maintenance and operations, inspections were made of the following projects during the period: Cowpens Swamp, S.C., Crabtree Swamp, S.C., Gapway Swamp, S.C., Simpson Creek, S.C., Todd Swamp, S.C., Buck Creek, S.C. and N.C., Edisto River, S.C., Sawmill Branch, S.C., Shot Pouch Creek, S.C., Turkey Creek, S.C., Kingstree Branch, S.C., Wilson Branch, S.C., and Cow Castle Creek, S.C. Responsible local officials were advised of inadequacies in maintenance and operation on local flood protection works when appropriate. Cost for the period was $12,710. 23. OTHER AUTHORIZED FLOOD CONTROL PROJECTS (See Table 7-F.) 24. FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION Flood Control Activities Pursuant to Section 205, Public Law 858, 80th Congress, as amended (Preauthorization). (See Table 7-G) Emergency Flood Control Activities-Repair, Flood Fighting and Rescue Work (Public Law 99, 84th Congress, and Antecedent Legislation). (See Table 7-G) Federal costs for FY 1985 were $169,405 for Flood Control and Coastal Emergencies and $184.717 for the National Emergency Preparedness Program. General Investigations 25. ACTIVE INVESTIGATIONS See Table 7-H which covers: Surveys, Collections, and Study of Basic Data, and Research and Development Activities. 7-8 CHARLESTON, S.C., DISTRICT TABLE 7-A COST AND FINANCIAL STATEMENT See Sect. Total Cost to in Text Project Funding FY 82 FY 83 FY 84 FY 85 Sept. 30, 1985 1 Aquatic Plant Control, SC (Regular Funds) (Contributed Funds) 2 Atlantic Intracoastal Waterway Between Norfolk, Va. and the St. Johns River, FL 3 Charleston Harbor, SC 4 Cooper River, Charleston Harbor, SC 5 Cooper River Seismic Modification, Chas Hbr, SC 6 Folly River, SC 7 Georgetown Harbor, SC 8 Jeremy Creek, McClellanville, SC 9 Little River Inlet, NC and SC (Regular Funds) (Contributed Funds) New Work: Approp. Cost Approp. Cost New Work: Approp. Cost Maint: Approp. Cost New Work: Approp. Cost Maint: Approp. Cost New Work: Approp. Cost Maint: Approp. Cost New Work: Approp. Cost Maint: Approp. Cost New Work: Approp. Cost Maint: Approp. Cost New Work: Approp. Cost Maint: Approp. Cost New Work: Approp. Cost Maint: Approp. Cost New Work: Approp. Cost Maint: Approp. Cost New Work: Approp. Cost 80,605 78,122 ---- 186,000 190,974 -- ---- 196,000 193,631 ---- 658,000 657,623 ---- 1,529,605 1,526,825 52,028 52,028 - -- - - 7,455,378' - -- - - 7,455,378' 2,316,000 1,742,000 2,055,000 3,224,700 42,068,0042 1,973,663 2,109,254 2,099,453 3,251,183 41,974,112 -- -- - - 10,165,564' - -- - - 10,165,564' 4,498,000 3,921,200 4,796,500 5,366,000 86,804,587' 4,215,123 2,710,142 6,994,476 5,201,014 86,540,035' 33,780,000 26,563,000 11,270,000 12,910,000 186,782,583 31,588,183 29,835,958 11,657,195 11,336,085 183,529,710 -- 295,000 480,000 2,556,000 3,331,000 -- 85,345 511,898 1,839,765 2,437,008 -- 100,000 1,300,000 900,000 2,300,000 - 39,925 1,174,744 894,513 2,108,832 -- 337,736 -- 337,336 157,000 262,368 152,000 110,000 259,000 20,776 250,173 257,359 854,000 844,688 - 7,061,755' - 7,061,755' 4,577,805 1,315,400 1,945,000 1,796,500 39,751,780' 3,868,776 1,490,161 2,495,612 1,814,224 39,681,857' 23,987 27,945 - 49,987 690 - 49,987 -- 3,000 - 848 1,809 7,120,000 5,800,000 331,000 7,112,543 5,300,996 863,027 115,000 148,798 400,000 849,999 7-9 585,000 24,988 640,000 499,994 -180,000 344,186 140,000 343 3,000 3,000 - 17,070,428 -29,255 17,036,991 78,552 124,428 31,920 31,927 2,138,676 2,216,445 1,521,920 1,521,920 TABLE 7-A (Cont'd) REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 COST AND FINANCIAL STATEMENT See Sect. Total Cost to in Text Project Funding FY 82 FY 83 FY 84 FY 85 Sept. 30, 1985 10 Murrells Inlet, SC (Regular Funds) (Contributed Funds) 11 Port Royal Harbor, SC 12 Shipyard River, SC 13 Town Creek, SC (Regular Funds) (Contributed Funds) 14 Village Creek, SC 18 Cow Castle Creek, SC 19 Eagle Creek, SC 20 Wilson Branch, SC New Work: Approp. Cost Approp. Cost Maint: Approp. Cost New Work: Approp. Cost Maint: Approp. Cost New Work: Approp. Cost Maint: Approp. Cost New Work: Approp. Cost Approp. Cost Maint: Approp. Cost New Work: Approp. Cost Maint: Approp. Cost New Work: Approp. Cost New Work: Approp. Cost New Work: Approp. Cost -175,000 27,346 279,000 128,593 32,452 12,758 - 104,225 - 104,225 99,637 38,647 - 13,419,240 4,127 13,407,147 - 1,380,000 - 1,379,148 78,000 83,886 1,058,569' 1,052,332' - 1,786,100 -- 1,786,100 -642 917 - 8,000 5,914,408 - 3,814 5,910,222 - 491,9748 -- 491,9748 430,000 254,613 316,000 65,943 15,000 691,000 8,786,192 420,227 707,639 8,779,685 -- 219,521 -- 219,521 -- 8,600 -- 8,600 218,000 280,000 345,000 166,443 243,580 420,739 - -6,300 1 3,171 51,500 25,568 50,000 64,846 197,600 34,616 1,258,000 12,222 100,000 293,000 73,614 114,700 - 400 900 188,72010 178,000 1,904,000 -2,201 1,689,152 390 26,500' 26,500' 100,473 100,473 -- 250,000 96 250,000'o 114,000 166,000 726,549" 624,586 -115,000 51,109 -31,700 7,121 1,755,372 1,573,649" 277,111 277,111 'Includes $109,490 for new work for previous project. 2Includes $69,422 for maintenance of previous projects. 'Includes $6,586,455 for previous projects. $3,328,349 for the existing project, and $250,760 for Phase I to deepen harbor. 'Includes $401,989 for maintenance of previous projects. In addition, $600 for maintenance expended from contributed funds. 'Includes $2,445,852 for new work for previous projects. 'Includes $114,556 for maintenance of previous projects. 'Includes $67,000 accomplished under authority of Section 3, P.L. 79-11 incurred through FY 73. 'Includes $4,150 for new work on previous projects. 'Excludes $3,000 in FY 69 for reconnaissance study to determine economic feasibility of modifying the existing project. "Includes $174,000 jobs bill money. "Includes $1,192,914 jobs bill money. 7-1.0 CHARLESTON, S.C., DISTRICT TABLE 7-B AUTHORIZING LEGISLATION Acts Work Authorized Documents R&H Act of Oct. 27, 1965 R&H Act of Sep. 19, 1890 R&H Act of June 13, 1902 R&H Act of Mar. 2, 1907 R&H Act of Mar. 2, 1907 R&H Act of Mar. 3, 1925 R&H Act of Mar. 3, 1925 R&H Act of July 3, 1930 R&H Act of Aug. 30, 1935' R&H Act of Aug. 30, 19352 R&H Act of Aug. 30, 19352 R&H Act of Aug. 26, 1937 R&H Act of Mar. 2, 1945 R&H Act of June 18, 1878 R&H Act of Aug. 8, 1917 R&H Act of July 18, 1918 R&H Act of Jan. 21, 1927 AQUATIC PLANT CONTROL (See Section 1 of text.) Provides for control and progressive eradication of water hyacinth, alligatorweed, Eurasian water-milfoil and other obnoxious aquatic plant growths from navigable waters, tributary streams, connecting channels, and other allied waters of the U.S., in combined interest of navigation, flood control, drainage, agriculture, fish and wildlife conservation, public health and related purposes, including continued research for development of most effective and economic control measures in cooperation with other Federal and state agencies. ATLANTIC INTRACOASTAL WATERWAY BETWEEN NORFOLK, VA., AND ST. JOHNS RIVER, FL (See Section 2 of text.) Channel from Minim Creek to Winyah Bay. Channel from Charleston to a point opposite McClellanville. Branch channel to McClellanville. Extending the channel to Minim Creek, thence through the Esterville-Minim Canal to Winyah Bay. Cut across the Santee Delta at Four Mile Creek. Widening and deepening the waterway from Charleston to Beaufort. A waterway eight feet deep and 75 feet wide from Cape Fear River to Winyah Bay. Construction of bridges across the waterway in Horry County, S.C. Cutoff between Ashepoo and Coosaw Rivers. Enlarging the channel from Winyah Bay to Charleston including the branch channel to McClellanville to depth of ten feet and bottom width of 90 feet. Increasing dimensions of waterway to twelve feet deep and 90 feet wide. Anchorage Basin 125 feet wide, 335 feet long, twelve feet deep, near Myrtle Beach, S.C." CHARLESTON HARBOR, S.C. (See Section 3 of text.) 2 jetties. I Increase in depth to 30 feet with width of 500 feet between the jetties and 1,000 feet seaward thereof. The 40-foot channel to the Naval Base. Act provided that the 40-foot channel should not be undertaken "until the proposed new drydocks at this navy yard, carrying a depth of 40 feet of water over the blocks, has been authorized." This dock was authorized in the Naval Appropriations Act approved July 1, 1918 (40 Stat. L. 725) A 30-foot channel from the sea to Goose Creek via Cooper River, together with a 30-foot channel through Town Creek for commercial purposes. The act also provided that the 40-foot channel be prosecuted only as found necessary for national defense. Sec. 302, 1965 River and Harbor Act (H.D.251, 89th Cong., 1st sess.) Annual Report, 1889, p. 1184. H.D. 84, 56th Cong., 1st sess. and Annual Report 1900, p. 1908 Annual Report 1903, p. 1133. H.D. 178, 63rd Cong., 1st. sess. H.D. 237, 68th Cong., 1st sess. S.D. 178, 68th Cong., 2nd sess. H.D. 41, 71st Cong., 1st sess. River and Harbor Committee Doc. 14, 72nd Cong., 1st sess. H.D. 129, 72nd Cong., I1st sess. River and Harbor Committee, Doc. 11, 72nd Cong., 1st sess. River and Harbor Committee, Doc. 6, 75th Cong., I1st sess. 3 H.D. 327, 76th Cong., 1st sess. Annual Report 1878, pp. 553-572. H.D. 288, 62nd Cong., 2nd sess. H.D. 1946, 64th Cong., 2nd sess., pt. 1, 21-29, 57, 58 and 61-63. H.D. 249, 69th Cong. 1st sess. 7-11 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 7-B (Cont'd) AUTHORIZING LEGISTLATION Acts Work Authorized Documents R&H Acts of Oct 17, 1940 R&H Act of Mar. 2, 1945 R&H Act of Sep. 3, 1954 R&H Act of July 14, 1960 Water Resources Development Act of Oct. 22, 1976 R&H Act of Aug. 13, 1968 Authorized by ChiefofEngrs. on Dec. 23, 1977 under authorization of Section 107 R&H Act of 1960, as amended. R&H Act of Aug. 5, 1886 R&H Act of June 25, 1910 R&H Act of Mar. 2, 1945 R&H Act of June 30, 1948 R&H Act of Mar. 2, 1907 The 35-foot channel depth fromthe sea tothe head ofthe project via Cooper River and Town Creek, also a channel in Shem Creek to Mount Pleasant, 110 feet wide and ten feet deep, including a turning basin at the upper end. An anchorage area 30 feet deep in the water area between Castle Pinckney and Fort Moultire.' Deepen the 30-foot channel north and east ofDrum Island to 35 feet. Shem Creek Channel modified by extending 1,150 feet upstream and downstream from mouth to Alantic Intracoastal Waterway. Project is authorized for the Phase I design memorandum stage of Advanced Engineering and Design. COOPER RIVER, CHARLESTON, S.C. (ST. STEPHEN PROJECT) (See Section 4 of text.) Redivert most of the Santee River waters above Pinopolis dam into the lower Santee River through a canal beginning at Lake Moultrie and extending to the Santee River in the vicinity of St. Stephen, South Carolina. COOPER RIVER SEISMIC MODIFICATION. CHARLESTON HARBOR, S.C. (See Section 5 of text.) Install a closure structure in the diversion canal between Lake Marion and Lake Moultrie and construct such measures as necessary to improve the seismic stability of the Pinopolis West Dam on the Cooper River. FOLLY RIVER, S.C. (See Section 6 of text.) Consists of stable all-tide channel nine feet deep and 80 feet wide in Folly River and an entrance channel at Stono Inlet 100 feet wide and eleven feet deep. GEORGETOWN HARBOR, S.C. (See Section 7 of text.) Jetties and earthen dike to protect south jetty. Previous project channel dimensions and training wall. 27-foot channel from ocean, including a turning basin in Sampit River. Cutoff and side channel in Sampit River. JEREMY CREEK, MeCLELLANVILLE, S.C. (See Section 8 of text.) To provide a waterway twelve feet deep at mean low water and a width of not less than 90 feet. H.D. 259, 76th Cong., 1st sess. H.D. 156, 77th Cong., I1st sess. S.D. 136, 83rd Cong., 2nd sess. H.D. 35, 86th Cong., I1st sess. H.D. 436, 94th Cong. 2nd sess. River and Habor Act of 1968 S.D. 88, 90th Cong. H.D. 3069, 98th Cong., 1st sess. Detailed Project Report H. Ex. Doc. 258 48th Cong., 2nd sess., and Annual Report 1885, pp. 1154-1170, and H Ex. Doc. 117, 50th Cong., 2nd sess., and Annual Report 1889, pp. 1110-1111. H.D. 395, 58th Cong., 2nd sess. and Annual Report 1904, pp. 1591-1605. H.D. 211, 76th Cong., 1st sess. H.D. 21, 81st Cong., I1st sess. Detailed Project Report 7-12 CHARLESTON, S.C., DISTRICT TABLE 7-B (Cont'd) AUTHORIZING LEGISLATION Acts Work Authorized Documents R&H Act of 1945, Sec. 3 Auth. by Senate Public Works Comm. and the House Public Works Comm. on Oct 12, 1972 under auth. of Sec. 201, PL 89-298, 1965 FC Act. Water Resources Development Act of 1974. R&H Act of 1945, Sec. 3 Auth. by the House Committee on Public Works on Nov. 10 1971 and the Senate Committee on Public Works on Nov. 18, PL 89- 298, 1965 FC Act. Water Resources Development Act of 1974. R&H Act of Sept. 3, 1954 R&H Act of July 25, 1912 R&H Act of Mar. 3, 1925 R&H Act of July 3, 1930 R&H Act of Aug. 30, 1935 R&H Act of Aug. 26, 19372 R&H Act of Mar. 2, 1945 Auth. by Chief of Engrs. on Feb. 12, 1974 under Auth. of Sec. 107 of R&H Act of 1960, as amended. Auth. on Nov. 24, 1965 by Chief of Engrs. under the Auth. of Sec. 107 of R&H Act of 1960, as amended. LITILE RIVER, INLET, N.C. AND S.C. (See Section 9 of text.) Provides for an entrance channel twelve feet by 300 feet across the ocean bar, thence ten feet by 90-foot inner channel to the Atlantic Intracoatal Waterway. P.L. 79-14 H.D. 362, 92nd Cong. Authorized emergency dredging operations as the Chief of H.D. 10203, 93rd Cong. 2nd sess. Engineers determines necessary to maintain channel depths sufficient to permit free and safe movement of vessels until such time as the authorized project is constructed. MURRELLS INLET, S.C. (See Section 10 of text.) Provides for an entrance channel twelve feet by 300 feet across the seaward bar, thence ten-foot by 90-foot inner channel to a turning basin at the Old Army crash boat dock. Authorized emergency dredging operations as the Chief of Engineers determines necessary to maintain channel depths sufficient to permit free and safe movement of vessels until such time as the authorized project is constructed. PORT ROYAL HARBOR, S.C. (See Section 11 of text.) A channel from the ocean through Port Royal Sound to Port Royal, S.C. 27 feet deep and 500 feet wide across the ocean bar and in Port Royal Sound for approximately 12.7 miles thence 24 feet deep and 300 feet wide in Beaufort River and Battery Creek for approximately 8.3 miles to and including a turning basin 27 feet deep and 600 feet wide opposite wharf of the S.C. State Ports Authority. SHIPYARD RIVER, S.C. (See Section 12 of text.) Channel depth of 15 feet and width of 100 feet. Deepening of channel to 18 feet from deep water in Cooper River upstream 1-1/16 miles. Channel depths of twelve to twenty feet. 28-feet from Cooper River to Gulf Oil Corp's terminal, and the deepening of the channel above that point to twenty feet from the depth of twelve feet previously authorized without local cooperation. Enlargement of the channel to a depth of 30 feet and a width of 200 feet up to the Gulf Oil Corp's terminal, with a turning basin 30 feet deep at the latter point. Extension of the existing 30-foot channel to vicinity of the Pittsburg Metallurgical Co. Plant, with a turning basin at the upper end. TOWN CREEK, S.C. (See Section 13 of text.) An entrance channel twelve feet deep by 100 feet wide across the ocean bar a distance of 4.0 miles and a channel ten feet deep by 80 feet wide from the mouth of Five Fathom Creek to the AIWW, a distance of 6.2 miles. VILLAGE CREEK, S.C. (See Section 14 of text.) A channel eight feet deep and 80 feet wide from the mouth of Village Creek upstream to Porpoise Fish Company terminal for a distance of 2.2 miles. 7-13 P.L. 79-14 H.D. 137, 92nd Cong. H.D. 10203, 93rd Cong. 2nd sess. River and Harbor Act, H.D. 469, 81st Cong., 2nd sess. S.D. 350, 62nd Cong., 2nd sess. H.D. 288, 68th Cong., 1st sess. River and Harbor Committee Doc. River and Harbor Committee Doc. 43, 73rd Cong& 2nd sess. River and Harbor Committee Doc. 38, I1st sess. H.D. 93, 79th Cong., 1st sess. Detailed Project Report. Detailed Project Report. REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 7-B (Cont'd) AUTHORIZING LEGISLATION Acts Work Authorized Documents COW CASTLE CREEK, S.C. (See Section 19 of text.) Auth. under Sec. 208 of the Provides for clearing and snagging approximately 8,000 feet of Reconnaissance Report. 1954 Flood Control Act, as channel. amended. EAGLE CREEK, S.C. (See Section 20 of text.) Auth. under Sec. 205 of the Provides for clearing and channel excavation of four miles of Detailed Project Report. 1948 Flood Control Act, as Chandler Bridge Creek and Eagle Creek. amended. WILSON BRANCH, S.C. (See Section 21 of text.) Auth. under Sec. 205 of the Provies for nonstructural solution of removing six homes Detailed Project Report. 1948 Flood Control Act, as from the flood plain. amended. 'Included in Public Works Administration Program September 3Contains latest published maps. 6, 1933. 'Inactive. 'Included in Emergency Relief Administration Program May 28, 'Completed under previous projects. 1935. 'For national defense. 7-14 CHARLESTON, S.C., DISTRICT TABLE 7-C OTHER AUTHORIZED NAVIGATION PROJECTS (See Section 16 of Text) For Last Full Report See Annual Operation & Project Report For Construction Maintenance Adams Creek, S.C. ' 1978 $125,697 $ 18,280 Aquatic Plant Control, N.C. and S.C.' ' 1968 379,680 -- Archers Creek, S.C. 1914 20,646 - Ashley River, S.C.' 1955 260,996 530,852 Edisto River, S.C.' 2 1938 33,103 900 Great Pee Dee River, S.C.'3 1950 183,712 269,673 Lynches River and Clark Creek, S.C.' 1982 9,500 84,170 Mingo Creek, S.C.' 2 1950 29,050 7,150 Salkahatchie River, S.C.' 4 1896 15,841 - Santee River, N.C. & S.C. ' 1950 99,750 180,633 Village Creek, S.C. 1984 26,500 105,116 Waccamaw River, N.C. & S.C.' 1978 262,814 278,170 Wateree River, S.C.' 1940 60,000 151,784 'Completed. 4Abandonment recommended in 1926 (H.D., 69th Cong., 1st 2No commerce reported. Sess.) 3Curtailment recommended in 1926 (H.D. 467, 69th Cong., 'Pilot Program 1st session). TABLE 7-D NAVIGATION WORK UNDER SPECIAL AUTHORIZATION (See Section 17 of Text) Study Identifications Section Fiscal Year Costs Calabash Creek, N.C. 107 $19,453 Charleston Harbor, S.C. 111 70,607 TABLE 7-E OTHER AUTHORIZED BEACH EROSION PROJECTS (See Section 18 of the text) For Last Full Report See Annual Operation & Project Report for Construction Maintenance Hunting Island Beach, S.C. 1984 $2,872,717' 'Excludes $1,249,336 contributed funds 7-15 TABLE 7-F REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 OTHER AUTHORIZED FLOOD CONTROL PROJECTS (See Section 23 of Text) For Last Full Report See Annual Operation & Project Report For Construction Maintenance Buck Creek, N.C. & S.C. 1 2 1970 $298,167 -- Cowpens Swamp, S.C.' 2 1960 18,679 -- Crabtree Swamp, S.C. '2 1969 97,000 -- Edisto River, S.C. ' ' 1947 6,379 -- Edisto River, North Fork, S.C.' 2 1969 127,660 - Edisto River, Vicinity Canadays Landing, S.C.' 1958 3,160 - Leith's Creek, S.C. 1 2 3 1982 430,951 -- Kingstree Branch, Williamsburg County, SC' 1978 247,242 -- Reddies River Lake, N.C. 1980 985,800 -- Reedy River, S.C. ' 1974 4,500 -- Roaring River, Wilkes County, N.C.'' 1978 370,000 -- Saluda River, S.C. ' 2 1963 99,000 -- Sawmill Branch, S.C.' 2 1971 248,605 -- Shot Pouch Creek, Sumter, Co., S.C.' 2 1971 77,400 -- Simpson Creek, S.C.' 2 1957 81,000 -- Todd Swamp, S.C.' 2 1964 29,000 -- Turkey Creek, Sumter County, S.C.' 2 1974 319,669 -- 'Authorized by Chief of Engineers 'Phase I only. 'Completed 'Revised 3Discontinued due to lack of interest TABLE 7-G FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION Preauthorization studies (See Section 24 of Text) Study Identification Section Fiscal Year Costs Bear Swamp, Lakeview, S.C. 205 $ 7,548 Brushy Creek, Greenville, S.C. 205 8,000 Brushy Creek, Greenville, S.C. 208 6,618 Camp Branch/Lynches Lake, Lake City, S.C. 205 1,760 Crabtree Swamp Canal, S.C. 205 8,724 Cramerton, S. Fork, Catawba River, N.C. 205 23 Crooked Creek, Bennettsville, S.C. 205 28,426 Devils Ditch, Richland County, S.C. 205 4,473 Goose Creek, Berkeley County, S.C. 205 42,917 Kinley Creek, Lexington County, S.C. 205 5,686 Lawsons Fork, Spartanburg, S.C. 205 4,247 Scotts Creek, S.C. 205 4,297 Smiths Branch, S.C. 205 3,850 Socastee Creek, Horry County, S.C. 205 63,393 Stoop Creek, S.C. 205 38,978 7-16 CHARLESTON, S.C., DISTRICT ACTIVE GENERAL INVESTIGATIONS (See Section 25 of Text) ITEM NAVIGATION (110) Charleston Harbor, S.C. FLOOD DAMAGE PREVENTION STUDIES (CATEGORY 120) Gills Creek, S.C. Little Pee Dee & Pee Dee Rivers, N.C. & S.C. Lumber River, N.C. & S.C. Sugar Creek Basin, N.C. & S.C. SHORELINE PROTECTION STUDIES (CATEGORY 130) Myrtle Beach, S.C. COORDINATION STUDIES WITH OTHER AGENCIES (CATEGORY 180) Department of Agriculture, SCS Planning Assistance to States SUPPLEMENTAL PRE-AUTHORIZATION STUDIES (CATEGORY 190) COLLECTION AND STUDY OF BASIC DATA (CATEGORY 200) Inspection of Dams (Category 230) FLOOD PLAIN MGMT SERVICES (CATEGORY 250) HYDROLOGIC STUDIES (CATEGORY 260) Hydrologic Studies TOTA FISCAL YEAR COSTS $ 11 $ 331,291 7,498 0 287 $ 151,501 $ 1,961 18,197 TOTAL (CATEGORY 100) $ 510,746 $ 205 $ 201,255 3,025 TOTAL (CATEGORY 200) 204,485 .L GENERAL INVESTIGATIONS $ 715,231 7-17 TABLE 7-H SAVANNAH, GA, DISTRICT* The District comprises drainage basins that flow into the Atlantic Ocean between Port Royal Sound, SC, and Cumberland Sound, GA and FL, and includes the Atlantic Intracoastal Waterway between these points. This area covers the headwaters of the Savannah River in southwestern North Carolina, a considerable portion of western South Carolina, eastern Georgia, and a small portion of northeastern Florida. IMPROVEMENTS Navigation 1. Altamaha, Oconee, and Ocmulgee Rivers, ........................... 2. Aquatic Plant Control ............. 3. Atlantic Intracostal Waterway Between Norfolk, VA, and St. Johns River, FL (Savannah District) ...... 4. Brunswick Harbor, GA ............ 5. Savannah Harbor, GA ............. 6. Savannah River Below Augusta, GA ..................... 7. Reconnaissance and Condition Surveys ......................... 8. Other Authorized Navigation Projects ......................... 9. Navigation Work Under Special Authorization .................... Beach Erosion Control 10. Beach Erosion Control Work Under Special Authorization 11. Tybee Island, GA ................. Flood Control 12. Broadway Lake, Anderson County, SC ............................. 13. Inspection of Completed Flood Control Projects ................. 14. Other Authorized Flood Control Projects ......................... 15. Flood Control Work Under Special Authorization .................... Page Multiple-Purpose Projects Including Power 8-1 16. Savannah River Basin, GA 8-2 and SC ...... ............... . 16A. Clarks Hill Lake, GA and SC ........ 16B. Hartwell Lake, GA and SC ......... 8-2 16C. Richard B. Russell Dam and Lake, 8-3 GA and SC (Formerly Trotters 8-4 Shoals Lake, GA and SC) .......... 17. West Point Lake, Chattahoochee 8-5 River Basin, GA and AL ............ 8-6 General investigations 18. Surveys .......................... 8-6 19. Collection and Study of Basic Data ....................... 8-6 20. Research and Development ........ 21. Continuation of Planning and Engineering ................. Tables 8-6 Table 8-A Cost and Financial Statement ..... Table 8-B Authorizing Legislation ....... Table 8-C Other Authorized Navigation Projects ................... 8-7 Table 8-D Other Authorized Flood Control Projects ....... .. ....... 8-7 Table 8-E Savannah River Basin, GA and SC Dams and Lakes ........ 8-7 8-7 Navigation 1. ALTAMAHA, OCONEE, AND OCMULGEE RIVERS, GA Location. These Rivers are entirely within the State of Georgia. (See National Oceanic and Atmospheric Administration Survey Map of Georgia, formerly U.S. Geological Survey map of Georgia.) For full description of these rivers, see page 636, Annual Report for 1932. Previous projects. Prior projects for the Altamaha River have been adopted, and expenditures made under them, by River and Harbor Acts of March 3, 1881, and September 19, 1890; for the Oconee River by River and Harbor Acts of June 18, 1878, September 19, 1890, and March 3, 1905; for the Ocmulgee River, by River and Harbor Acts of August 14, 1876, and September 19, 1890. For further details, see page 1815, Annual Report for 1915, and page 589, Annual Report for 1938. Existing project. The authorized project provides for an appropriation of $40,000 annually for the Altamaha, Oconee, and Ocmulgee Rivers, to maintain a 3-foot depth 8-1 Page 8-8 8-8 8-8 8-9 8-9 8-9 8-9 8-10 8-10 8-11 8-12 8-16 8-16 8-17 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 during ordinary summer low water and to gradually increase channel depth, so far as practicable without sacrificing the maintenance work. This project covers the entire Altamaha River (including a channel between the river and Darien, GA), a length of 137 miles, the lower 139 miles of the Oconee River, and the lower 199 miles of the Ocmulgee River. The Altamaha River has a mean tidal range of 6.4 feet at its mouth which gradually decreases to mile 33, where there is no perceptible tidal effect. At Doctortown, mile 59, ordinary floods attain a height of about 10 feet above low water, and at extreme floods, a height of about 15 feetabove low water. On the Oconee River at Dublin the ordinary fluctuations attain a height of 22 feet, and the extreme fluctuations a height of 32 feet, above low water. On the Ocmulgee River at Macon the ordinary fluctuations attain a height of 15 feet, and the extreme fluctuations a height of 25 feet, above low water. There is no approved estimated cost for improvement or for maintenance. Published maps of these rivers are in the following documents: Altamaha River, House Executive Document 283, Fifty-first Congress, second session; Oconee River, House Executive Document 211, Fifty-first Congress, first session; Ocmulgee River, House Executive Document 215, Fifty-first Congress, first session; and Lower Altamaha River and Darien Harbor, GA, House Document 610, Seventy-seventh Congress, second session. (See Table 8-B for Authorizing Legislation.) Local cooperation. Fully complied with. Terminal facilities. Along these rivers there are numerous natural shore landings which are considered ample for existing commerce. Facilities for recreational boats have been constructed at several points. Operations and results during fiscal year. Maintenance: No maintenance was performed during the fiscal year. (See Table 8-A for Cost and Financial Statement.) Condition at end of fiscal year. The existing project is such that the percentage of completion cannot be stated. Channel depths have been increased by excavating rock shoals and sandbars, by constructing contraction and bank-protection works, and by closing cutoffs. Navigation has been rendered safer by removing obstructions. Many of the closing dams and contractions and bankprotection works need repairs. The notice of availability on the Final Environmental Statement appeared in the Federal Register October 21, 1977. To September 30,1985, costs under the existing project were $60,847 for new work and 1,871,657 for maintenance, of which $69,356 were contributed funds, a total of $1,932,504. (See Table 8-A for Cost and Financial Statement.) 2. AQUATIC PLANT CONTROL Location. Navigable waters, tributary streams, connecting channels, and other allied waters in Savannah District. Existing project. The project provides for control and progressive eradication of water-hyacinth, alligatorweed, Eurasian water milfoil, and other noxious aquatic plants from navigable waters, tributary streams, connecting channels, and other allied waters of the United States, in the combined interests of navigation, flood control, drainage, agriculture, fish and wildlife conservation, public health, and related purposes. The project provides for continued research for developing the most effective and economic control measures in cooperation with other Federal and State agencies in accordance with report of Chief of Engineers, House Document 251,89th Congress, 1st session. The authorizing act provides that research and planning costs shall be borne fully by the United States. (See Table 8-C for Authorizing Legislation.) Local cooperation. Local interests must agree to hold the United States free from damages that may occur from operations performed in connection with this project and participate to the extent of 30 percent of the cost of the program. Requirements are being met. Operations and results during fiscal year. Georgia Game and Fish Division, Department of Natural Resources, who maintain surveillance of potential aquatic plant problem areas, reported aquatic plant infestation in the Satilla River and in other river basins in the State of Georgia. Actual control work under the Aquatic Plant Control Cost Sharing Program with the Georgia Game and Fish Division was not accomplished in FY 85. Actual control work under the Aquatic Plant Control Cost Sharing Program with the Georgia Game and Fish Division was not accomplished in FY 85. Substantial progress was made on implementing a new cost-sharing agreement. This agreement will be fully implemented during the FY 86 plant control season. The District assisted the public in FY 85 by answering inquiries about the program and providing contacts with the State. Cost during the fiscal year was $11,433. The Final Environmental Statement was filed with EPA on August 6, 1979, and its notice of availability appeared in the Federal Register August 17, 1979. (See Table 8-A for Cost and Financial Statement.) 3. ATLANTIC INTRACOASTAL WATERWAY BETWEEN NORFOLK, VA, AND THE ST. JOHNS RIVER, FL (SAVANNAH DISTRICT) Location. This 161-mile section of waterway connects Port Royal Sound, SC, with Cumberland Sound, GA and FL (See NOAA charts 11489- 11507, formerly Coast and Geodetic Survey Charts 838 - 841, inclusive.) Previous project. (Between Savannah, GA, and Fernandina, FL.) For details see pages 1814, 1821-1823 of Annual Report for 1915 and page 585 of Annual Report for 1938. 8-2 SAVANNAH, GA, DISTRICT Existing project. The project provides for a waterway 12" feet deep at mean low water and not less than 90 feet wide between Port Royal Sound, SC, and Savannah, GA; 12 feet deep at mean low water, with widths of 90 feet in land cuts and narrow streams and 150 feet in open waters between Savannah, GA, and Cumberland Sound, GA and FL; and a suitable anchorage basin at Thunderbolt, GA. Mean tidal range between Port Royal, SC, and Cumberland Sound, GA and FL, is from 6 to 8 feet with fluctuations from 1.5 to 2.5 feet, due to winds and lunar phases. (See Table 8-B for Authorizing Legislation.) Local cooperation. Fully complied with. Terminal facilities. Exclusive of adequate terminal facilities at ports of entry, this improvement serves numerous wharves, some of which are open to the public on equal terms. Facilities are considered ample for existing commerce. Operations and results during fiscal year. Maintenance: A contract for maintenance dredging was awarded on July 3, 1985. The contract dredge Clarendon removed 24,063 cubic yards from the Wilmington River from August 31 to September 4, 1985. The following week it removed 66,359 cubic yards from Hell Gate. From September 17 to September 26,1985 the dredge removed 124,169 cubic yards from Creighton Narrows and another 39,880 cubic yards from Rockdedundy from September 27 thru September 30, 1985. The expenditures for the dredging were $800,000. Total cost including inspection, administration, and other government cost was $110,848. The government cost for surveys and inspection reports, and condition and operation studies amounted to $39,108. Real estate inspection cost and administration activities cost amounted to $334. Total cost for the fiscal year amounted to $950,290. (See Table 8-A for Cost and Financial Statement.) Condition at end of fiscal year. The main channel of the existing project, completed in 1941, is maintained at 12 feet. The former main channel, now an alternate route through the westerly end of the south channel and northerly end of Wilmington River, will be maintained to a depth of 7 feet mean low water for traffic points north and south of Savannah Harbor. Relocation of the main channel from the Frederica to Mackay River near St. Simons Island, GA, is accomplished after construction of the new bridges for the Torras Causeway. The notice on the Final Environmental Impact Statement appeared in the Federal Register October 29, 1976 Costs of the existing completed project to September 30, 1985, were $763,599 for new work and $15,645,053 for maintenance, a total of $16,408,652. (See Table 8-A for Cost and Financial Statement.) 4. BRUNSWICK HARBOR, GA Location. The harbor entrance is 70 statute miles south of the entrance to Savannah Harbor, GA, and 25 statute miles north of the entrance to Fernandina Harbor, FL. (See NOAA Chart 11215, formerly Coast and Geodetic Survey Chart 447.) Previous projects. For details see page 1818 of Annual Report for 1915 and page 591 of Annual Report for 1938. Existing project. The project provides for a stone jetty 4,350 feet long at the entrance to East River and the following channels: 32 feet deep and 500 feet wide across the bar; 30 feet deep and 400 feet wide through St. Simons Sound, Brunswick River, and East River to the foot of Second Avenue; 30 feet deep and 300 feet wide in Turtle River to the Allied Chemical Co. wharf, formerly the Atlantic Refining Co.; 27 feet deep and 350 feet wide in East River from Second Avenue to its confluence with Academy Creek; 24 feet deep and 150 feet wide in Academy Creek; a channel in Back River 20 feet deep and 150 feet wide from St. Simons Sound to the mouth of Mill Creek; and a channel in Terry Creek 10 feet deep and 80 feet wide from its mouth to a point immediately above the wharf of Glynn Canning Company. All depths refer to mean low water. Mean tidal range on the bar is 6.5 feet, at the city of Brunswick 7.3, and 7.6 feet at the upper end of the harbor. For further details see Annual Report for 1962. Local cooperation. Complied with to date. Terminal facilities. Eighteen wharves and piers, almost all privately owned, have a berthing space of 7,530 linear feet. The Port of Brunswick and the State of Georgia have a transit shed and modern docks with 1,640 feet of berthing space (three general cargo berths) on East River. For further details see Port Series No. 14, Corps of Engineers (revised 1982). Operations and results during fiscal year. Maintenance: A contract for maintenance dredging was awarded March 19, 1985. The dredge Cherokee worked in three parts of the harbor. From April 11 thru April 29, 1985 they removed 557,125 cubic yards from the East River, followed by dredging in Mayor's Point Terminal from May 10, 1985 to May 15, 1985 by removing 16,424 cubic yards, and finally removing 47,288 cubic yards from Turtle River between May 16 and May 22, 1985. Under the same contract, the dredge Illinois removed 129,548 cubic yards from the Turning Basin. Expenditures for surveys totaled $178,360, for dikes $9,999 for S&I $93,278, and miscellaneous expenses $21,196. The District received a credit of $61,877 for maintenance dredging in the East River under a 1983 contract. Also a contractor received $158,097 for 1984 emergency dredging in the East River. Expenditures for Brunswick Ocean Disposal Dump were $90,772. 8-3 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Mosquito control in disposal areas cost amounted to $81,096. Engineering and design costs totaled $233,374. We received a $61,877 credit on one East River Dredging contract. Total operation and maintenance cost amounted to $9,641,199. (See Table 8-A for Cost and Financial Statement.) Condition at end of fiscal year. The existing project was completed in December 1960. General condition of the harbor works is satisfactory, providing maintenance dredging continues. The notice on the Final Environmental Impact Statement appeared in the Federal Register October 3, 1975. Costs for existing completed project to September 30, 1985, were $50,699,185, of which $3,929,968 was for new work and $46,769,217 for maintenance. (See Table 8-A for Cost and Financial Statement.) 5. SAVANNAH HARBOR, GA Location. Harbor entrance is 75 statute miles south of Charleston Harbor, SC, and 70 statute miles north of Brunswick Harbor, GA (See NOAA Chart 11512, formerly Coast and Geodetic Survey Chart 440.) Previous projects. For details see page 1810 of Annual Report for 1915 and page 578 of Annual Report for 1938. Existing project. The project provides for a channel 40 feet deep and 600 feet wide across the ocean bar about 7.0 miles; 38 feet deep and 500 feet wide to the Seaboard Coast Line terminal; 38 feet deep and 400 feet wide to the vicinity of Garden City (Georgia Ports Authority terminal); and 36 feet deep and 400 feet wide to the vicinity of Savannah Sugar Refinery of Savannah Foods and Industries, Inc. about 22.6 miles; and 30 feet deep and 200 feet wide to a point 1,500 feet below the Atlantic Coastal Highway bridge, about 1.5 miles, a total length of 31.1 miles; Fig Island and Marsh Island Turning Basins 34 feet deep by 900 feet wide by 1,000 feet long in the vicinity of the Seaboard Coast Line terminal, and American Oil Company terminal; Kings Island Turning basin 38 feet deep by 1,500 feet wide by 1,600 feet long in the vicinity of Garden City terminal of the Georgia Ports Authority; Argyle Island and Port Wentworth Turning Basins 30 feet deep by 600 feet wide by 600 feet long near Savannah Sugar Refinery terminal and at the extreme upper limit of the project near Continental Can Company terminal; and Oyster Bed Island Turning Basin in the vicinity of Georgia Ports Authority LASH facility. The project also provides for sediment control works consisting of a tide gate structure across Back River; a sediment basin 40 feet deep, 600 feet wide, about 2 miles long, with an entrance channel 38 to 40 feet deep and 300 feet wide; a drainage canal across Argyle Island 15 feet deep and 300 feet wide; control works and canals for supplying fresh water to the Savannah National Wildlife Refuge; and facilities to mitigate damages to presently improved areas other than refuge lands. Mean range of tide is 7.9 feet at the upper end of the harbor and 6.9 feet at the lower end. Extreme ranges are about 11.1 and 10.7 feet, respectively. Local cooperation. Local interests must provide suitable spoil areas and retaining dikes for construction and future maintenance of the project. The Chatham County Commissioners, as local assurers, have met all requirements to date. Terminal facilities. Sixty-one piers and wharves adequately serve existing waterborne commerce of the port. These facilities, with use of dolphins, have a combined berthing space of 46,930 linear feet with water depths alongside ranging up to 38 feet at mean low water. Included in the berthing space are six container berths with 271 acres of handling area. All have railway and highway connections. LASH facilities are located at the entrance to the harbor and have depths ranging up to 38 feet mean low water. The berthing space of LASH facilities is included in the above combined berthing space. For further details, see Port Series No. 14, Corps of Engineers (revised 1982) and Annual Report for 1962. Maintenance: Several dredging contracts awarded in FY 83 and FY 84 continued in FY 85 and dredging was accomplished under another contract awarded in FY 85. Under a FY 83 contract the dredge Clinton removed 1,165,986 cubic yards from the sedimment basin and the dredge Dauntless removed 77,453 cubic yards from the lower harbor. Under FY 84 contracts the dredge Enterprise removed 1,684,138 cubic yards in the lower harbor while the dredge Arlington removed 250,322 cubic yards and the dredge Clarendon removed 437,734 cubic yards in the upper harbor. The Clarendon removed 8,617 cubic yards in emergency dredging work and the Stuyvesant worked in the bar channel removing 1,212,478 cubic yards of material. Four dredges including the Arlington, Clarendon, Florida, and Dauntless worked on the Bend Wideners, removing 597,397 cubic yards. Total yardage removed in FY 85 was 5,434,125. 8-4 SAVANNAH, GA, DISTRICT Mosquito control in disposal areascost $201,331. (Credits received from agitation dredging of private shipping interest slips amounted to $63,791.) Distribution of Engineer Yard cost amounted to $76,748. Condition surveys, water quality monitoring, water and air pollution studies, environmental studies, testing, inspection and reports, and government supervision and administration costs were $1,263,833. Total operation and maintenance costs for the fiscal year amounted to $10,084,654. (See Table 8-A for Cost and Financial Statement.) Condition at end of fiscal year. The existing project is incomplete. Training walls, jetties, and other structures are in fair condition. Authorized channels are maintained by a planned dredging program with work at critical areas when necessary. The notice on the Final Environmental Impact Statement appeared in the Federal Register June 25,1976. Notices of availability on two Final Supplements to the Environmental Impact Statement appeared in the Federal Register September 25, 1978, and January 8, 1980. Costs of existing project to September 30, 1984, were $177,834,569, of which $38,925,359 was for new work and $138,909,210 for maintenance. (See Table 8-A for Cost and Financial Statement.) 6. SAVANNAH RIVER BELOW AUGUSTA, GA Location. Savannah River is formed by the confluence of the Tugaloo and Seneca Rivers on the boundary line between South Carolina and Georgia. It flows southeast 314 miles, forming the boundary line between the two states, and empties into the Atlantic Ocean 16.6 miles below Savannah, GA (See NOAA Charts 11514 and 11515, formerly Geological Survey maps of South Carolina and Georgia.) Previous project. For details see page 1813 of Annual Report for 1915 and page 581 of Annual Report for 1938. Existing project. The authorized project provides for a channel 9 feet deep and 90 feet wide (at ordinary summer flow of 5,800 second-feet at Augusta, GA) from the upper end of Savannah Harbor to the head of navigation at Augusta, 3 miles above Fifth Street Bridge, a total distance of about 181 miles. A lock and dam is located approximately 15 miles below the upper limit of the project at New Savannah Bluff. Improvement is to be obtained by construction of contraction works, closure of cutoffs, bank protection, dredging, removal of snags, overhanging trees and wrecks, and open-river regulation. Mean tidal variation at the mouth of the river is 7 feet. Freshet variation above the normal pool level (elevation 114.5 mean sea level) of New Savannah Bluff Lock and Dam at miles 187 is ordinarily about 13 feet with an extreme of 34 feet. Latest approved project cost estimate for providing a 9-foot channel (September 1963) is $6,576,000 exclusive of amounts expended on previous projects. For further details see Annual Report for 1962. Local cooperation. Complied with to date. Terminal facilities. The only water terminals served by this improvement are at Augusta, Sylvania, and at or near Savannah. Augusta provided a municipal dock valued at $50,000 and Georgia Ports Authority constructed a State port at Augusta, GA, costing about $418,000. These facilities were expanded in 1965 at an additional cost of about $250,000. These are supplemented by natural landings along the river and extensive facilities at Savannah. Operations and results during fiscal year. Maintenance: Routine maintenance and operation of the New Savannah Bluff Lock and Dam and its recreational area, which accommodated 340,000 visitors, amounted to $759,005. Activity during the year included lock and dam operations totaling $105,359 and operation of facilities, roads, and equipment at $32,710. Preparation of mobilization plans, district office support, and miscellaneous management expenses cost $9,519. Periodic inspections and continuing evaluation and data gathering expenses were $11,557 with hydrographic surveys and preparation of navigations charts costing another $129,055. Substantial maintenance activity in the recreation area cost $467,826. These expenses were offset by $2619 in credits for sale of property and collection of recreation use fees. (See Table 8-A for Cost and Financial Statement.) Condition at end of fiscal year. In general, openchannel works are in good condition. The notice on the Final Environmental Impact Statement appeared in the Federal Register February 18, 1977. Costs of the existing project to September 30, 1985, were $22,125,309 of which $6,646,551 was for new work and $15,478,758 for maintenance. (See Table 8-A for Cost and Financial Statement.) 8-5 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 7. RECONNAISSANCE AND CONDITION SURVEYS Survey Section performed project condition surveys on the following active O&M navigation projects: Savannah Harbor - - monthly Brunswick Harbor - - monthly AIWW -- 12-13 Aug. 85, 14-20 Feb. 85, 5-13 Nov. 84 Savannah River Below Augusta - -19-26 Aug 85 and 14-17 May 85 8. OTHER AUTHORIZED NAVIGATION PROJECTS (See Table 8-C.) 9. NAVIGATION WORK UNDER SPECIAL AUTHORIZATION Costs for preauthorization studies totaled $102,017. A Detailed Project Report on Bellville Point, GA, was submitted in April, 1984. Plans and specifications were prepared in January 1985. Costs for Bellville totaled $68,037. The Valona, GA, detailed project study was continued in FY 85 at a cost of $20,638. Work included surveys to obtain data on shoaling patterns, evaluation of an upland disposal site, and updating of project benefits. The Torras Causeway project was approved in FY 82. Plans and specifications were completed in FY 85 at a cost of $13,342. Consequently, the main channel of the AIWW in the vicinity of the Torras Causeway was relocated from the Frederica River to the MacKay River. Beach Erosion Control 10. BEACH EROSION CONTROL WORK UNDER SPECIAL AUTHORIZATION Erosion control activities pursuant to Section 103, Public Law 87-874, as amended (Preauthorization Studies). An initial draft appraisal report on Gould's Inlet, Glynn County, GA, was completed in September 1984. FY 85 costs for coordination efforts totaled $1,054. The study was terminated because the estimated local share of project construction costs was beyond the sponsor's ability to participate. An initial appraisal was conducted on the shoreline erosion problems at Crooked River State Park, GA, at an FY 85 cost of $6,750. In June 1985 OCE approved further reconnaissance investigation so the cost for preauthorizations studies was $7,804. 11. TYBEE ISLAND, GA Location. Tybee Island is located directly south of Savannah River entrance, about 17 miles east of the City of Savannah, GA (See NOAA Charts 11512, 11513 and 11509, formerly U.S. Coast and Geodetic Survey Charts Nos. 440, 1240, and 1241, and on maps included in H.D. 92-105, 92d Cong.) The only portion of the island that has been developed is bounded on the north by the south channel of the Savannah River, on the east by the Atlantic Ocean, and on the south and west by Tybee Creek and other small tidal streams. This area, hereinafter referred to as "Tybee Island," is occupied by the City of Tybee Island. The ocean face of this area has had a wide sandy beach. Tybee Island is about 3.5 miles long from its northerly tip to the mouth of Tybee Creek with an average width of about 0.5 mile. Behind the beach lies a line of sand dunes, a number of which have been removed during the years to make room for improvements and for various other reasons. Those that remain are from 10 to 20 feet high. The ground elevation west of the dunes is from 10 to 18 feet and slopes westward to the salt marsh. Existing project. The approved project plan of improvement provides for an 800-foot rock groin at the north end of the island, with a 225-foot tie-in to high ground. An additional 1,200-foot extension of this groin is deferred, as are two additional, intermediate groins (480 feet long); these will be added at a later date, if needed. The plan also provides for the initial restoration of approximately 13,300 feet of beach, from the vicinity of 18th Street to the terminal groin located at the northern end of the island. Periodic nourishment will be provided as needed to maintain suitable beach dimensions. In 1981, the plan was modified and now calls for the addition of a groin at the south end and modification and rehabilitation of the north rock groin and renourishment. Local cooperation. Local interests must: (a) contribute in cash the required percentage of the first cost, including costs for construction, engineering, and design, and administration; and excluding the cost of lands, easements, rights-of way; and relocations; of all items of work to be provided by the Corps of Engineers, presently estimated at 51.0 percent to be paid in a lump sum prior to start of construction or in installments prior to the start of pertinent work items in accordance with construction schedules as required by the Chief of Engineers, the final apportionment of cost to be made after the actual costs have been determined; (b) provide maintenance and repair of the groins, and provide, after the first 10 years of project life, periodic nourishment of the restored beach as may be required to serve the intended purpose during the life of the project, (c) provide without cost to the United States all lands, easements, rights-of-way, and relocations required for construction and subsequent nourishment of the project; (d) hold and save the United States free from claims for damages that may result from construction, maintenance, and nourishment of the project; (e) control water pollution to the extent necessary to safeguard the health of bathers; and (f) provide without cost to the United States access and facilities necessary for realization of the public benefits upon which Federal participation is based, and maintain continued public use of the beach and 8-6 SAVANNAH, GA, DISTRICT administer it for public use during the life of the project; and provided further, that construction on the project shall not be started until local interests furnish lands for beach access and parking, satisfactory to the Chief of Engineers, for the reach from 1st Street to the terminal groin. To date, local cooperation is being provided as required. Condition at end of fiscal year. The Final Environmental Impact Statement was filed with CEQ on November 13, 1973. The initial construction contract for the terminal groin was awarded September 13, 1974 in the amount of $980,642. The groin was completed and formally accepted on June 17,1975. The second contract, for initial beach fill and advance nourishment, was awarded June 18, 1975 in the amount of $2,175,000. This resulted in the placement of 2.3 million cubic yards of sandfill along most of the entire length (13,300 feet) of ocean beach front. The sand was removed by hydraulic pipeline dredge from a massive sandbar borrow area off the south end of Tybee Island. Completed in March 1976, the project provides approximately 124 feet of beach seaward of the seawall (accessible at average high tide), doubling the public beach area. Erosion has occurred along the beach front. Results of prior years beach monitoring indicate a decreasing or stabilizing erosion rate. The southernmost section south of 13th Street has experienced the most critical erosion. Total project cost is estimated to be $11,500,000, which includes $5,865,000 in non-Federal, contributed funds. Costs to date of existing project were $2,527,095 (Federal funds) and $2,032,856 (contributed funds). (See Table 8-A Cost and Financial Statement.) Flood Control 12. BROADWAY LAKE, ANDERSON COUNTY, SC Location. The Broadway Lake is located about 4 miles of Anderson, South Carolina. It is formed at the junction of Broadway Creek and Neals Creek in the headwaters of Rocky River, a tributary of the Savannah River. Existing project. The authorization provides for the of Engineers to undertake a demonstration project for the removal of silt and aquatic growth from an existing lake known as Broadway Lake, owned by Anderson County, South Carolina. This lake has a surface area of about 1 square mile and a tributary area of about 44 square miles with an existing dam and concrete spillway. The spillway is 50 feet wide, about 19 feet high, and flanked by an earth on the west side. The total length of the dam is about 610 The National Dam Safety Inspection Program determined that the dam did not meet the safety criteria. Since the repairs of the dam, spillway, and low-level outlet are not the authority of the demonstration project, the U.S. Army Corps of Engineers will withhold implementation of the project pending repairs to the dam by State or local authorities. Local cooperation. The local interests are now making the necessary repairs to the dam. Local interests have expressed a willingness to provide necessary easements, and rights-of-way for removal of silt and aquatic weeds, as well as provide lands for disposal areas. They will be required to hold and save the United States free from damages due to the construction works other than damages due to the fault or negligence of the United States or its contractors. The United States should be relieved of any liability due to dam failure from construction activity in the lake. The local assurer is Anderson County. Operations and results during fiscal year. The project is inactive, pending completion of repairs to the dam by local interest. The Office of the Chief of Engineers is preparing a Significant Post Authorization Change Report for submittal to Congress. Draft Environmental Impact Statement appeared in the Federal Register August 29, 1977. (See Table 8-A for Cost and Financial Statement.) 13. INSPECTION OF COMPLETED FLOOD CONTROL PROJECTS Physical inspections of Dunn Branch, Augusta and Peacock Creek were completed during the fiscal year. The total cost of the fiscal year amounted to $15,387. The Macon levee was not inspected. 14. OTHER AUTHORIZED FLOOD CONTROL PROJECTS (See Table 8-D) 15. FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION Flood control activities pursuant to section 205, Public Law 858, 80th Congress, as amended (preauthorization studies). Preauthorization studies continued through FY 85 on Federal Prison Creek, GA; Placentia Canal, GA; and Springfield Canal, GA. The DPR on Federal Prisonn Creek was commpleted in July 1985 at a FY cost of $9,023. A draft DPR on Placentia Canal was submitted to SAD in September 1985 at a FY cost of $67,722. Detailed project studies continued in FY 85 on Springfield Canal at a cost of $40,851. The total cost for preauthorization studies in FY 85 was $117,596. Emergency flood control activities - repair, flood fighting, and rescue work, (Public Law 99, 84th Congress and antecedent legislation). Revisions to emergency manuals, emergency planning, inspection, supplies, emergency operations, and other expenditures costs for coastal emergencies were $443,584. Rehabilitation of the seawall at Tybee Island by placement of riprap constituted $305,512 or about 69% of the funding. This work was necessary due to beach erosion caused by a hurricane. National emergency preparedness cost amounted to $307,308. 8-7 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Multiple-Purpose Projects Including Power 16. SAVANNAH RIVER BASIN, GA AND SC Location. Works covered by this project consist of a series of 11 dams and lakes on Savannah River and its tributaries in Georgia and South Carolina. (See Geological Survey maps of GA and SC.) Existing project. The Flood Control Act of 1944 approved the general plan for comprehensive development of the Savannah River Basin for flood control and other purposes (H.D. 657, 78th Cong., 2d sess.) and authorized construction of the Clarks Hill Project on the Savannah River in Georgia and South Carolina as the initial step of this development. The Flood Control Act of 1950 authorized construction of Hartwell Lake under the general plan. Trotters Shoals which will replace Goat Island and Middleton Shoals was authorized for construction by the Flood Control Act of 1966 at an estimated cost of $84,900,000. Clarks Hill and Hartwell Lakes are the only projects in the comprehensive plan that have been constructed. (See Table 8-E on Dams and Lakes at end of chapter.) Duke Power Company has completed construction on the Keowee-Toxaway power complex on the Keowee River in the headwaters of Hartwell Lake and construction of the Jocassee pump-storage power project in the headwaters of the Keowee-Toxaway project. The Keowee-Toxaway power complex is located on the Newry - Old Pickens site identified in the approved comprehensive plan. Individual reports on Clarks Hill, Hartwell, and Richard B. Russell (formerly Trotters Shoals) Lake follow. Local cooperation. None required. 16A. CLARKS HILL LAKE, GA AND SC Location. Clarks Hill Lake is located at mile 237.7 on Savannah River about 22 miles upstream from Augusta, GA (See Geological Survey maps of Georgia and South Carolina.) Existing project. The authorized project provides for construction of Clarks Hill Dam and Lake, the final cost of which was $79,156,300. The dam has a concrete section 2,282 feet long with a maximum height of 200 feet, and a controlled spillway 1,096 feet long. The concrete section is flanked on the west side by a rolled-earth embankment of 2,069 feet, and on the east side by a similar embankment of 1,329 feet. Total length of the dam is 5,680 feet. At maximum power pool elevation 330, the lake covers 70,000 acres. It provides a total storage capacity of 2,900,000 acre-feet allocated as follows: flood control 390,000 acre-feet; hydroelectric power 1,045,000 acrefeet; and dead storage 1,465,000 acre-feet. Seven 40,000- kilowatt generators have a combined generating capacity of 280,000 kilowatts, with an average annual output of 700 million kilowatt-hours of electrical energy. Local cooperation. None required. Operations and results during fiscal year. New work: Cost of recreational activities during the period from Construction General funds (Code 710) amounted to $5,447. Under the 1983 Job Bill Act $165 was expended for temporary employment. The total fiscal year cost for new work amounted to $5,612. Gross generations of electric energy for the period was 476,105,700 kilowatt-hours, most of which was delivered to the Southeastern Power Administration. Flood damages prevented amounted to $1,138,000. Maintenance: Operation and maintenance costs during the fiscal year amounted to $7,746,134. The notice of availability on the Final Environmental Impact Statement on Clarks Hill Lake Operation and Maintenance appeared in the December 18, 1981 Federal Register. Condition at end of fiscal year. Construction is complete except for providing additional recreational development. (See Table 8-A for Cost and Financial Statement.) 16B. HARTWELL LAKE, GA AND SC Location. Hartwell Lake is on the Savannah River 305 miles above its mouth and 89 miles upstream from Augusta, Georgia. (See Geological Survey maps of GA and SC.) Existing project. The dam is a concrete gravity-type structure, 1,900 feet long with a maximum height of 204 feet and a controlled spillway 568 feet in length. The concrete section is flanked on the east and west abutments by earth embankments totaling 13,390 feet in length and by a saddle dike 2,590 feet long also on the west side. Total length of the dam is 17,880 feet. At maximum power pool elevation of 660 feet the lake covers 55,950 acres. Total capacity of the lake is 2,843,000 acrefeet of storage allocated as follows: flood control 293,000 acre-feet; hydroelectric power 1,416,000 acre-feet; and dead storage 1,134,000 acre-feet. Four 66,000-kilowatt generators having generating capacity of 264,000 kilowatts were installed initially with provisions for a future unit. A fifth 80,000-kilowatt generating unit has been installed which increased the rated capactiy to 344,000 kilowatts. Local Cooperation. None required. Operations and results during fiscal year. Cost of activities during the fiscal year amounted to $7,076,686. Of this amount $48,892 was expended from (Code 713) for cost sharing at the 1-85 Destination Park. 8-8 SAVANNAH, GA, DISTRICT The fiscal year upper diversion dam rehabilitation cost amounted to $138,899. Gross generation of electrical energy for the period amounted to 358,671,000 kilowatthours, most of which was delivered to the Southeastern Power Administration. Flood damages prevented during the fiscal year amounted to $302,000. Maintenance: Operation and maintenance costs during the fiscal year amounted to $6,863,402. The notice on the Final Environmental Impact Statement on the operation and maintenance of Hartwell Dam and Lake appeared in the Federal Register August 21, 1978. Condition at end of fiscal year. Construction is complete except for providing additional recreational development. (See Table 8-A for Cost and Financial Statement.) 16C. RICHARD B. RUSSELL DAM AND LAKE, GA AND SC, (FORMERLY TROTTERS SHOALS LAKE, GA AND SC) Location. Richard B. Russell Dam is on the Savannah River 275.1 miles above its mouth, 29.9 miles below Hartwell Dam and about 37.4 miles above Clarks Hill Dam. (See NOAA Survey maps of GA and SC.) Existing project. The authorized project provides for construction of Richard B. Russell Dam and Lake substantially in accordance with the recommendations of the Chief of Engineers at an estimated cost of $84,900,000. The latest approved (FY 85) cost estimate for the project is $539,000,000, of which $423,877,000 is for construction, $28,127,000 for lands and damages, $4,683,000 is for cultural resources, and $73,313,000 for engineering and design and supervision and administration. Approval was received January 1977 to include minimum provisions for pumped storage. A notice of availability of a Final Environmental Impact Statement covering pumped storage was published in the Federal Register February 18, 1977, and October 26, 1979. A notice of availability on the Final Supplement to the Environmental Impact Statement on Fish and Wildlife Mitigation for the Russell project appeared in the Federal Register on December 11, 1981. Operations and results during fiscal year. Contracts were awarded during FY 85 as follows: (1) Construction of Resources Management Office, awarded October 4,1984 at $1,340,000; (2) Supply Liquid Oxygen and Cryogenic Equipment, awarded March 4, 1985 at $1,516,120. All remaining pump storage supply contracts, consisting of Generators/Motors, Transformers, Governors, Main Control Switchboard, and also Phase Bus are 100% design complete and ready for advertisement. The general construction contract is approximately 40% complete. Continued water quality monitoring by Waterways Experiment Station is being requested to extend their contract thru FY 92. Fish entrainment studies relating to future pumpback were initiated in FY 84, with basic Phase I study and conceptual protection system design completed in early FY 85. Maintenance: The operation and maintenance cost for the fiscal year amounted to $3,055,270. Condition at end of fiscal year. The project is 77.2 percent complete. Costs of project to September 30, 1984, were $421,390,556 of which $416,659,829 is for new work and $4,730,727 for maintenance. (See Table 8-A for Cost and Financial Statement.) 17. WEST POINT LAKE CHATTAHOOCHEE RIVER The West Point Lake located on the Chattahoochee River, 2.8 miles upstream from West Point, GA, was authorized by the Flood Control Act of 1962 (H. D. 570, 87th Cong., 2d sess.). The project was designed and constructed for flood control, power, recreation, fish and wildlife development and streamflow regulation for downstream navigation. Design and construction was accomplished by Savannah District for Mobile District. For complete information see Mobile District. General Investigation 18. SURVEYS Fiscal year cost was $1,678,239, of which $395,763 was for navigation studies; $1,151,108 for flood control studies; $64,864 for special investigations; and $51,881 for coordination with other agencies, and $2,265 for coordinating FERC Licenses. 19. COLLECTION AND STUDY OF BASIC DATA Work continued under the Flood Plain Management Services on the compilation of flood information, potential flood damages, and identification of those areas subject to inundation. Fiscal year expenditures for these activities were as follows: flood plain management services, $82,392; and technical servicer, $72,188. Flood plain management services included responses to other Federal agencies to aide them in fulfilling the requirements of Executive Order 11988 (Management of Base Flood Area). Through the Technical Services Program, flood problems in several areas were analyzed and possible improvements were identified. During the fiscal year, the Flood Plain Management Services Branch completed the Atlanta, Georgia, Flood Insurance Study for the Federal Emergency Management Agency. The total cost of the study was $313,000 and took 18 months to complete. The national program for inspection of non-Federal dams cost $2,061. The cost for hydrologic studies was $11,435. The total fiscal year cost for collection and study of basic data was $168,078. 8-9 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 20. RESEARCH AND DEVELOPMENT No funds were expended for research and development during the fiscal year. 21. CONTINUATION OF PLANNING AND ENGINEERING The Savannah Harbor Widening Study under Continuation of Planning and Engineering continued during the fiscal year and the cost amounted to $139,625. The recommended plan provides for modification of the harbor by widening the navigation channel between the present upstream limit of the 500-foot channel (Fig Island Turning Basin) and the Kings Island Turning Basin from 400 to 500 feet. This will decrease the hazard of handling large vessels and reduce shipping transit time. Cost of the study to September 30, 1985, was $813,855. In FY 85, the Lake Lanier Reregulation Dam Study continued under Continuation of Planning and Engineering. The cost amounted to $410,895. The recommended project is the construction of a reregulation dam on the Chattahoochee River, 6.3 miles downriver of Buford Dam. Project benefits are hydropower and water supply. Oates Creek is a major drainage outlet for flood waters from an urban area of Augusta, Georgia. A flood control study of Oates Creek was authorized and completed as part of the Savannah River Basin study. The Oates Creek study area is located just south of Augusta in Richmond County. The recommended plan is a channel and bridge modification flood control plan and has received support from Federal, State and local governmental agencies with no environmental opposition. The local sponsor, Richmond County, expressed support for the project and intent to participate financially. The plant consists of improvements to approximately 12,300 feet of channel and consists of concrete-lined channels, grass-lined channels, a low levee, modifications of bridges and culverts, and relocation of utilities. The CP&E effort began in October 1983 and consists of preparation of a General Design Memorandum estimated to cost about $780,000 and is scheduled for completion in September 1986. FY 85 expenditures were $337,888. 8-10 SAVANNAH, GA, DISTRICT TABLE 8-A COST AND FINANCIAL STATEMENT See Section Total Cost to in Text Project Funding FY 82 FY 83 FY 84 FY 85 Sept. 30, 1985 1. Altamaha, Oconee and Ocmulgee Rivers, GA 2. Aquatic Plant Control (1965 R&H ACT) 3. Atlantic Intracoastal Waterway between Norfolk, VA, and the St. Johns River, FL 4. Brunswick Harbor, GA 5. Savannah Harbor, GA 6. Savannah River below Augusta, GA 11. Tybee Island, GA 12. Broadway Lake, SC 13. Inspection of Completed Flood Control Works 16.A Clarks Hill Lake, GA and SC New Work: Approp. Cost Maint. Approp. Cost New Work: Approp. Cost New Work: Approp Cost Maint. Approp. Cost New Work: Approp. Cost Maint. Approp. Cost New Work: Approp. Cost Maint. Approp. Cost New Work: Approp. Cost Maint. Approp. Cost New Work: Approp.- Cost New Work: Approp. Cost Maint. Approp. Cost New Work: Approp. Cost Maint. Approp. Cost - - 6,000 - 5,821 191 18,800 40,000 64,801 36,731 894,000 493,921 5,691,000 3,339,781 1,100,000 1,938,034 6,636,000 5,642,853 404,000 362,725 1,000 1,838 727,000 332,011 4,885,360 5,397,853 75,000 481,164 3,491,000 5,221,253 -319,000 -112,480 9,418,000 6,986,914 348,000 171,452 4,542 85,000 4,731 1,050,000 593,200 6,397,700 5,629,293 - - - 4,000 - 269 9,000 30,000 11,488 11,433 934,000 914,900 8,636,350 9,605,206 4,207,000 8,049,868 1,088,000 950,290 1,800,000 1,896,159 10,238,200 10,084,654 672,000 804,000 884,597 759,000 - 386,949 - 307,887 13,000 -15,000 59,775 15,387 932,843 6,673,800 7,040,063 5,612 7,554,000. 7,746,130 8-11 821,4571 821,457' 1,917,98223 1,914,2512'3 291,159 268,557 958,0964 958,0964 15,948,9215 15,779,851s 4,573,6086 4,573,4336 46,935,4517 46,823,6317 46,187,7218 46,185,7438 139,456,1409 139,208,1049 6,740,03110 6,740,03110 15,577,492 15,478,758 2,917,249'13 2,834,982'13 99,000 99,000 165,518 162,085 84,841,29011 84,840,26311 62,709,35415 62,030,03015 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 8-A COST AND FINANCIAL STATEMENT See Section Total Cost to in Text Project Funding FY 82 FY 83 FY 84 FY 85 Sept. 30, 1985 16B. Hartwell Lake, GA New Work: and SC Approp. 8,950,000 5,334,000 -450,000 270,000 115,906,3071214 Cost 8,232,445 4,489,519 1,282,815 213,284 114,918,8461214 Maint. Approp. 4,768,760 4,411,359 4,803,000 6,986,600 55,892,22616 Cost 4,471,416 4,938,210 5,031,036 6,863,402 55,331,19916 Major Rehab. Approp. 3,500,000 1,700,000 1,450,000 -100,000 6,550,000 Cost 1,974,609 1,893,576 2,463,415 138,899 6,470,499 16C. Richard B. Russell New Work: Dam and Lake, GA Approp. 75,030,000 78,469,000 36,300,000 21,400,000 417,489,509 and SC (Formerly Cost 75,048,353 77,939,501 35,491,655 22,368,222 416,659,829 Trotters Shoals) Maint. Approp. 328,000 396,000 1,231,300 2,870,000 4,825,300 Cost 298,132 371,704 1,005,621 3,055,270 4,730,727 1. Includes $760,610 for previous projects. 11. Does not include $395,634 accelerated Public Works 2. Includes $111,950 for previous projects. Funds. Includes $4,558,613 appropriated under Code 710 of 3. Does not include $69,356 contributed funds. which $4,556,958 has been expended. Also includes 4. Includes $194,497 for previous projects. $1,000,000 expended under the '83 Job Bill Act. 5. Includes $134,798 for previous projects. 12. Does not include $276,200 accelerated Public Works 6. Includes $643,465 for previous projects and includes Funds. Includes $4,861,000 appropriated under Code 710 of $97,521 expended from Public Works Funds for existing project. which $4,504,543 has been expended. Also includes $545,000 Does not include $10,000 contributed funds. expended under the '83 Job Bill Act. 7. Includes $54,414 for previous projects. Includes 13. Does not include $2,036,057 contributed funds. $4,995 expended from Public Works Funds for existing project. 14. Includes $17,550,000 appropriated for construction of Excludes $350,427 contributed by Brunswick and Ga. Port 5th Unit of which $17,407,236 has been expended. Authorities. Also includes $2,150,000 under '83 Job Bill Act. 15. Includes $316,760 appropriated and $315,513 8. Includes $7,260,384 for previous projects. Does not expended under special recreation use fees. Also includes include $46,847 for removal of sunken vessles and $1,886,413 $736,000 under the '83 Job Bill Act. contributed funds. 16. Includes $575,019 appropriated and $550,122 9. Includes $298,894 for previous projects. Does expended special recreation use fees. include $855,941 contributed funds. 10. Includes $93,480 for previous projects. Includes $1,634,562 from Public Works Fund. TABLE 8-B AUTHORIZING LEGISLATION See Date of Section Authorized in Text Act Project and Work Authorized Documents 1. July 25, 1912 and March 2, 1945 2. Oct. 27, 1965 Section 302 ALTAMAHA, OCONEE AND OCMULGEE HIVERS, GA. Channel 3 feet deep and 60 to 100 feet wide. Provides for control and progressive eradication of noxious aquatic plant growths. HD 443, 62d Cong., 2d sess. HD 610, 77th Cong., 2d sess. HD 251, 89th Cong., 1st sess. 8-12 SAVANNAH, GA, DISTRICT TABLE 8-B (continued) AUTHORIZING LEGISLATION See Date of Section Authorized in Text Act Project and Work Authorized Documents 3. June 3, 1896 Mar. 3, 1899 July 13, 1892 Mar. 3, 1905 July 25, 1912 Aug. 8, 1917 Mar. 2, 1919 Mar. 2, 1919 Mar. 3, 1925 July 3, 1P30 Aug. 26, '37 Aug. 26, 1937 June 20, 1938 Mar. 2, 1945 Oct. 15, 1981 4. Mar. 3, 1879 Mar. 2, 1907 Mar. 2, 1919 July 3, 1930 July 3, 1930 June 20, 1938 May 17, 1950 Oct. 22, 1976 ATLANTIC INTRACOASTAL WATERWAY BETWEEN NORFOLK, VA., AND ST. JOHNS RIVER, FLA., (SAVANNAH DISTRICT) Section from Beaufort, S.C. to Savannah, Ga. Route No. 2 adopted. Route No. 1 adopted. Section from Savannah, Ga. to Fernandina, Fla. Original 7-foot channel. Provided for Skidaway Narrows. Incorporated alternative routes previously improved as separate projects and the auxiliary channels. Section fromm Cumberland Sound, Ga. and Fla. to St. Johns River, Fla. Consolidation of the 3 sections shown above, into "Waterway between Beaufort, S.C. and St. Johns River, Fla." Section from Beaufort, S.C. to Cumberland Sound, Ga. and Fla. Removing logs and snags from Generals Cut. Improving Back River to provide a channel 7 feet deep and 150 feet wide. Channel 75 feet wide between Beaufort, S.C., and Savannah, Ga. Channel from Baileys Cut to Dover Creek. A 7-foot protected channel around St. Andrews Sound. A 12-foot channel between Beaufort, S.C., and Savannah, Ga. via Beaufort River and Port Royal Sound. A 12-foot channel between Savannah, Ga., and Fernandina, Fla., various cutoffs; and anchorage basin at Thunderbolt, Ga. An alternate route 9 feet deep and 150 feet wide in that part of Frederica River, Ga., not now traversed by the main route, at no additional cost to the United States. Main channel relocated from Frederica River to Mackay River in the vicinity of Torras Causeway. BRUNSWICK HARBOR, GA Construction of East River jetty. Channels in the inner and outer harbors of 30-foot depth at mean high water, with widths varying from 150 feet in Academy Creek to 400 feet across the outer bar, extension of training wall in East River and construction of two spurdikes. Channels 27 feet deep at mean low water over the bar and at Brunswick point; and 24 feet deet at mean low water in the inner harbor and provides for a cut from Academy Creek to Turtle River, if deemed advisable. A channel in Back River 230 feet deep and 150 feet wide. Increased Channel dimensions of the bar, Brunswick Point, East River, and Turtle River, as given in the then existing project. A 10-foot channel in Terry Creek. Increased channel dimensions of the bar, St. Simons Sound, Brunswick River, East River, and Turtle River, as given in the existing project. Provides for Phase I AE&D studies for deepening portions of existing harbor (East River and Entrance Channel) and for provision of a navigation channel to Colonels Island. HD 295, 53d Cong., 3d sess. HD 295, 53d Cong., 3d sess. HD 41, 52d Cong., 1st sess. HD 450, 58th Cong., 2d sess. HD 1236, 60th Cong., 2d sess. HD 581, 63d Cong., 2d sess. HD 1391, 62d Cong., 3d sess.1 SD 178, 68th Cong., 2d sess. SD 43, 71st Cong., 2d sess.' Senate committee print, 74th Cong., 1st sess. Rivers and Harbors Committee Doc. 6, 75th Cong., 1st sess. HD 618, 75th Cong., 3d sess. HD 114, 77th Cong., 1st sess. Project authorized by Chief of Engineers under the Small Navigation Project Authority, Sec. 107, PL 86-645 as amended. Annual Report, 1880, p. 959 HD 407, 59th Cong., 1st sess. HD 393,64th Cong., 1st sess. SD 57, 71st Cong., 2d sess.' SD 132, 71st Cong., 2d sess.' HD 690, 75th Cong., 3d sess.' HD 110, 81st Cong., 1st sess.' Report of Chief of Engineers dated Aug. 18, 1976. 8-13 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 8-B (continued) AUTHORIZING LEGISLATION See Date of Secon Autheried In Text Act Project and Work Authorlzed Documents SAVANNAH HARBOR, GA. 5. Mar. 2, 1907 Tentative provisions for a 26-foot channel from the Quarantine Station to the Seaboard Air Line Ry. Bridge June 25, 1910 Definite provision for the 26-foot channel. July 25, 1912 A 21-foot channel from the Seaboard Air Line Ry. Bridge to the foot of Kings Island. Aug. 8, 1917 A 30-foot depth from the sea to the Quarantine Station. Jan. 21, 1927 A 21-foot channel above Kings Island. Jan. 21, 1927 Channel 30 feet deep, with general width 50 feet, from the ocean to the Quarantine Station, thence 26 feet deep, general width 400 feet, to the Seaboard Air Line Ry. Bridge, thence 21 feet deep and 300 feet wide to Kings Island. Widening at West Broad and Barnard Streets; anchorage basin; mooring dolphins; regulating dam across South Channel; relocation of the Inland Waterway; dredging Drakies Cut to 13 feet; widening to 525 ft. at Kings Island; extension of training walls, revetments, and jetties. Consolidation of projects relating to Savannah Harbor. July 3, 1930 Channel 26 feet deep and 300 feet wide from the Seaboard Air Line Ry. Bridge to the foot of Kings Island. Aug. 30, 1935 Authorized the 30-foot project and eliminated from the project (a) the relating dam across South Channel; (b) the relocation of the Inland Waterway; and (c) the further extension of training walls, revetments, and jetties. Mar. 2, 1945 Deepening the channel and turning basin above the Seaboard Air Line Ry. Bridge from 26 to 30 feet and widening the channel opposite the Atlantic Coast Line Terminals to a maximum of 550 feet for a length of 5,000 feet. Nov. 7, 1945 Deepening the channels to 36 feet deep and 500 feet wide across the ocean bar; 34 feet deep and generally 400 feet wide, increased to 550 feet opposite the Atlantic Coast Line Terminals, with a tumrning basin 34 feet deep at the Mexican Petroleum Corp. Refinery; and with such modifications thereof as the Secretary of War and the Chief of Engineers may consider desirable. July 24, 1946 Extending channel 30 feet deep, 200 feet wide, upstream from Atlantic Creosoting Terminal to a point 1,500 feet below the Atlantic Coastal Highway Bridge, with turning basin 30 feet deep at upper end. Sep. 3, 1954 Deepening the channel to 34 feet and widening to 400 feet from the upper end of the presently authorized 34-foot channel in the vicinity of the American Oil Company Refinery wharf, to the Savannah Sugar Refining Corp. with a turning basin at the upper end of the proposed improvement, made by widening the channel to 600 feet for a length of 700 feet and providing approaches. Oct. 23, 1962 Enlargement of turning basin near Kings Island to a width of 900 feet and a length of 1,000 feet, with suitable approaches, at a depth of 34 feet. Oct 27, 1965 Deepening the bar channel from 36 feet to 40 feet, the channel between the bar channel and Garden City Terminal from 34 feet to 38 feet, and the channel from the Garden City Terminal to the vicinity of the Savannah Sugar Refining Corp., from 30 feet to 36 feet; widening the bar channel from 500 feet to 600 feet, the channel between Fort Pulaski and Atlantic Coast Line Terminal from 400 feet to 500 feet, and the channel between Garden City Terminal and the Savannah Sugar Refining Cbrp. from 200 feet to 400 feet; providing necessary wideners of the bends; constructing a new turning basin 900 feet wide by 1,000 feet long by 34 feet deep opposite the Atlantic Coast Line Terminals; and enlargement of existing turning basin at the American Oil Company Terminal from 600 feet wide by 600 feet long to 900 feet wide by 1,000 feet long. HD 181, 59th cong., 1st sess. HD 563, 62d Cong., 2d sess. HD 1471, 64th Cong., 2d sess. HD 261, 69th Cong., 1st sess. HD 262, 69th Cong., 1st sess. SD 39, 71st Cong., 1st sess. HD 276, 73d Cong., 2d sess. HD 283, 76th Cong., 1st sess.1 HD 227, 79th Cong., 1st sess.1 HD 678, 79th Cong., 2d sess.1 HD 110, 83d Cong., 1st sess.' SD 115, 87th Cong., 2d sess. HD 226, 89th Cong., 1st sess. 8-14 SAVANNAH, GA, DISTRICT TABLE 8-B (continued) See Section in Text AUTHORIZING LEGISLATION Date of Authorized Act Project and Work Authorized Documents Oct. 27, 1965 SPWC Resolution June 15, 1976 and HPWTC of June 9, 1976 under authority of Sec. 201 of Flood Control Act of 1965 6. Sep. 19, 1890 June 25, 1910 July 3, 1930 Aug. 30, 1935 Aug. 26, 1937 May 17, 1950 10. SPWC Resolution June 22, 1971 and HPWC of June 23, 1972 under authority of Sec. 201 of FC Act of 1965 11. Water Resources Development Act of March 7, 1974. 15A. Flood Control Act of Dec. 22, 1944 15B. Flood Control Act of May 17, 1950. Flood Control Act of July 3, 1958. Water Resources Development Act of 1976. 15C. Flood Control Act of Nov. 7, 1966. Providing sediment control works consiting of tide gate structure across Back River; sediment basin 40 feet deep, 600 feet wide about 2 miles long, with entrance channel 38 to 40 feet deep and 300 feet wide; drainage canal across Argyle Island 15 feet deep and 300 feet wide; control works and canals for supplying fresh water to Savannah National Wildlife Refuge; and facilities to mitigate damages to presently improved areas other than refuge lands. Provided for modification of the existing project to include (1) incorporation of the LASH Turning Basin as an element of the existing Federal navigation project for maintenance purposes, (2) enlargement of Kings Island Turning Basin to 1,500 feet by 1,600 feet by 38 feet. SAVANNAH RIVER BELOW AUGUSTA, GA. For a 5-foot channel. Special improvement by bank protection work of 20 or 25 miles of the river immediately below Augusta. The present 6-foot channel project and Lock and Dam. Provision made for locating the lock and dam at New Savannah Bluff. Conditions of local cooperation modified. Provides for a 9-foot channel. TYBEE ISLAND, GA. Project will provide for beach erosion control, consisting of beach restoration, groin system, and periodic beach nourishment. BROADWAY LAKE, S.C. Provided for undertaking a demonstration project for the removal of silt and aquatic growth from Broadway Lake. CLARKS HILL LAKE, GA. AND S.C. Approved the general plan for the comprehensive development of the Savannah River Basin and provided for construction of the Clarks Hill Project HARTWELL LAKE, GA. AND S.C. Provided for construction of Hartwell Project. Provided for the completion of the Hartwell Project. Provides for installation of 5th unit. RICHARD B. RUSSELL DAM AND LAKE, GA. Provided for construction of the Trotters Shoals Project. HD 223, 89th Cong., 1st sess. HD 94-520, 94th Cong. dated June 8, 1976. HD 255, 51st Cong., 2d sess. and Annual Report. 1890; p. 1328 HD 962, 60th Cong., 1st sess. HD 101, 70th Cong., 1st sess. Senate Committee Print, 73d Cong., 2d sess. Rivers and Harbors Com., Doc. 39, 75th Cong., 1st sess. SD 6, 81st Cong., 1st sess. HD 105, 92d Cong. PL 93-251, 93d Cong. HD 657, 78th Cong., 2d sess. PL 534, 78th Cong., 2d sess. HD 657, 78th Cong., 2d sess. PL 516, 81st Cong., 2d sess. PL 85-500, 85th Cong., 2d sess. PL 94-587, Sec. 182b. 85th Cong. SD 52, 89th Cong., 1st sess. 1. Contains latest published maps. 8-15 TABLE 8-C REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 OTHER AUTHORIZED NAVIGATION PROJECTS (See Section 8 in text) For Last Cost to Sep. 30, 1985 Full Report See Annual Operation and Project Status Report for Construction Maintenance Aquatic Plant Control (R&H Act 1962) Completed 1968 25,700 - Cedar Point, GA Completed 1982 656,233 - Darien Harbor, GA Completed 1975 199,723 185,433 Fancy Bluff Creek, GA' Completed 1935 8,000 7,200 St. Marys River, GA and FL, and Completed 1951 15,688 69,936 North River, GA Sapelo Harbor, GA2'3 Completed 1929 17,906 19,594 Satilla River, GA' Completed 1951 9,452 57,172 Savannah River above Augusta, GA 2 3'4 See Notes 1929 69,600 5,870 Savannah River at Augusta, GA2 3'5 See Notes 1929 200,556 17,444 1. Channel adequate for commerce. of two power dams which submerged much of the work under 2. Project recommended for abandonment in H.D. 467, the present and former projects, this improvement cannot be 69th Cong., 1st sess. completed as originally planned. 3. No commerce reported. 5. Excludes $185,000 contributed funds ($172,151 for 4. About 84 percent completed. Owing to construction construction and $12,849 for operation and maintenance). TABLE 8-D OTHER AUTHORIZED FLOOD CONTROL PROJECTS (See Section 14 In text) For Last Cost to Sep. 30, 1985 Full Report See Annual Operation and Project Status Report for Construction Maintenance Augusta, Savannah River, GA Completed 1941 643,016 38,242 Curry Creek Dam and Lake, GA' See Note 1974 - - Dunn Branch, Woodbine, Camden Completed 1977 132,640 5,219 County, GA Macon, GA Completed 1955 380,043 38,243 Peacock Creek, Liberty County, GA Completed 1976 582,163 5,219 1. Feasibility report completed. Project not authorized for construction. 8-16 SAVANNAH, GA, DISTRICT SAVANNAH RIVER BASIN, GA AND SC DAMS AND LAKES (See Section 16 In text) Estimated Cost Name River Federal Non-Federal Total Clarks Hill, GA and SC Savannah $79,156,0004 $79,156,000" Hartwell, GA and SC Savannah 89,240,000 89,240,0002 Goat Island, GA and SC5 Savannah 36,400,000 36,400,0003 Middleton Shoals, GA and SCs Savannah 16,500,000 16,500,0003 Chattooga Units (4), GA and SC Chattoga 41,700,000 41,700,0003 Tallow Hill, GA Broad 39,000,000 39,000,000 Anthony Shoals, GA Broad 18,100,000 18,100,0003 Newry-Old Pickens, SC6 Keowee 29,500,000 29,500,0003 1. Final cost. (Excludes $127,000 for preauthorization study.) 2. Approved Aug. 1963. (Excludes $73,000 for preauthorization study.) 3. Approved July 1954. 4. Exludes Code 710 funds. 5. Replaced by Richard B. Russell Dam and Lake (formerly Trotters Shoals Lake). 6. Site of Duke Power Co. Keowee-Toxaway Project. 8-17 TABLE 8-E JACKSONVILLE, FLA. DISTRICT* JACKSONVILLE, FLA. DISTRICT With the exception of a small area in the northeastern section of Florida, his district comprises a portion of south-central Georgia and all of peninsular Florida, embracing the watersheds tributary to the Atlantic Ocean and the Gulf of Mexico from, and including the harbor at Fernandina, Florida, to and including the Aucilla River. It also includes Puerto Rico and the Virgin Islands. IMPROVEMENTS Navigation Page 1. Aquatic Plant Control (R&H Act of 1965) ........................... 2 2. Arecibo Harbor, P.R................... 2 3. Atlantic Intracoastal Waterway between Norfolk, Va. and St. Johns River, Fla...................... 2 4. Bakers Haulover Inlet, Fla............. 3 5. Canaveral Harbor, Fla ................ 3 6. Channel from Naples to Big Marco Pass ..................... 4 7. Charlotte Harbor, Fla ................ 4 8. Cross Florida Barge Canal............. 4 9. Eau Gallie Harbor, Fla................ 5 10. Fernandina Harbor, Fla................ 5 11. Fort Myers Beach, Fla................. 5 12. Fort Pierce Harbor, Fla................ 6 13. Intracoastal Waterway, Caloosahatchee River to Anclote River, Fla............. 6 14. Intracoastal Waterway, Jacksonville to Miami, Fla. ....................... 7 15. Jacksonville Harbor, Fla .............. 7 16. John's Pass, Fla ..................... 8 17. Longboat Pass, Fla .................. 8 18. Mayaguez Harbor, P.R ................ 9 19. Melbourne Harbor, Fla................ 9 20. Miami Harbor, Fla .................. 9 21. New Pass, Sarasota, Fla .............. 10 22. Okeechobee Waterway, Fla ............. 10 23. Oklawaha River, Fla ................. 11 24. Palm Beach Harbor, Fla. .............. 11 25. Ponce de Leon Inlet, Fla.............. 12 26. Ponce Harbor, P.R ................... 12 27. Port Everglades Harbor, Fla........... 13 28. Removal of Aquatic Growth From Navigable Waters in the State of Florida. 13 29. St. Augustine Harbor, Fla ............. 14 30. St. Johns River, Jacksonville to Lake Harney, Fla................... 14 31. St. Lucie Inlet, Fla................... 15 32. San Juan Harbor, P.R ................ 15 33. Tampa Harbor, Fla................... 16 34. Navigation Projects on which Reconnaissance and Condition Surveys only were Conducted during Period ..... 17 Navigation (cont.) Page 35. Other Authorized Navigation Projects ........................... 17 36. Navigation Work under Special Authorization ...................... . 17 Beach Erosion Control 37. Brevard County, Fla................... 17 38. Broward County, Fla. Beach Erosion Control and Hillsboro Inlet, Fla., Navigation Project.................... 18 39. Dade County, Fla .................... 18 40. Dade County, N. of Haulover Beach, Fla................... 19 41. Duval County, Fla.................... 19 42. El Thque Beach, P.R................... 20 43. Fort Pierce, Fla. ..................... 20 44. Palm Beach County, Fla. from Martin Country line to Lake Worth Inlet and from South Lake Worth Inlet to Broward County line.................. 21 45. Pinellas County, Fla................... 21 46. Other Authorized Beach Erosion Control Projects ..................... 22 47. Beach Erosion Control Activities under Special Authorization............ 22 Flood Control 48. Central and Southern Florida .......... 22 49. Four River Basins, Fla................. 23 50. Portugues and Bucana Rivers, P.R....... 24 51. Inspection of Completed Flood Control Projects ..................... 24 52. Other Authorized Flood Control Projects ........................... 24 53. Flood Control Work under Special Authorization........................ 24 General Investigations 54. Surveys............................ 25 55. Collection and Study of Basic Data...... 25 *All cost and financial statements for projects are listed at the end of this chapter. All other tables are referenced in text and also appear at the end of this chapter. 9-1 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Navigation 1. AQUATIC PLANT CONTROL (R&H ACT OF 1965) Location. Navigable waters, tributary streams, connecting channels, and other allied waters in Florida. Existing project. The authorized project provides for control and progressive eradication of water hyacinth, alligatorweed, Eurasian water-milfoil, and other noxious aquatic plant growths from navigable waters, tributary streams, connecting channels, and other allied waters of the United States, in combined interest of navigation, flood control, drainage, agriculture, fish and wildlife conservation, public health, and related purposes, including continued research for development of most effective and economical control measures in cooperation with other Federal and State agencies in accordance with report of Chief of Engineers, House Document 251, 89th Congress, 1st session. The authorizing act provides that research and planning costs shall be borne fully by the United States. (See Table 9-B for Authorizing Legislation.) Local cooperation. Local interests must hold the United States free from damages that may occur from operations performed in connection with this project and contribute 30 percent of cost of operations. Compliance with requirements of local cooperation is on schedule. Operations and results during fiscal year. New work: There were 12,939 acres of hyacinth and/or water lettuce, 4,197 acres of hydrilla and 1,092 acres of minor plant controlled during the period. Costs incurred were $144,314 for engineering and $2,478,271 for operations. Condition at end of fiscal year. Operations by the Corps and the State of Florida are in progress, water hyacinths within Florida are under maintenance control. Hydrilla is continuing to spread throughout the state and is causing major problems in some areas. 2. ARECIBO HARBOR, P. R. Location. The harbor is located on the north shore of Puerto Rico about 40 miles west of San Juan Harbor. (See Coast and Geodetic Survey Chart No. 903.) Previous project. For details see page 504 of 1956 Annual Report. Existing project. The project provides for a channel 25 feet deep and 400 feet wide, with flare at entrance and widening at inner end to form a maneuvering area, and a stone breakwater 1,200 feet long. Place of reference is mean low water. Mean tidal range is 1.1 feet. (See Table 9-B for Authorizing Legislation.) Local cooperation. Fully complied with to date. Non Federal contribution for new work was $288,000. Terminal facilities. A bulkhead wharf 688 by 220 feet providing a deep water berthing space of approximately 500 feet, and a 300 by 100 foot transit shed. Facilities are considered adequate for existing commerce. Operations and results during fiscal year. Maintenance: Condition and operation studies for the year cost $344. District communications network for the year cost $10,000. Jetty repair by contract amounted to $92,770. Engineering and design and supervision and administration costs were $45,193 and $42,187 respectively. Condition at end of fiscal year. Project was completed in 1944. Breakwater was repaired in 1952. Wave action has since caused damage. Tbtal Federal costs under existing project through September 30, 1985 were $1,128,075 for new work and $3,920,697 for maintenance, a total of $5,048,772. 3. ATLANTIC INTRACOASTAL WATERWAY BETWEEN NORFOLK, VA. AND ST. JOHNS RIVER, FLA. (JACKSONVILLE DISTRICT) Location. That part of Intracostal Waterway between southerly limit of Fernandina Harbor, Florida, at junction of Lanceford Creek and Amelia River, and St. Johns River, Fla. (See Coast and Geodetic Survey Chart No. 841-SC.) Previous project. For Details see page 605 of 1938 Annual Report. Existing project. Channel 12, 90 to 150 feet wide from Fernandina Harbor to St. Johns River about 22 miles long. Plane of reference is mean low water. Mean tidal range is 6 feet at Fernandina and 3.8 feet at St. Johns River. (See Table 9-B for Authorizing Legislation.) Existing project was authorized by River and Harbor Acts of 1913 (HD 898/62/2) and 1938 (HD 618/75/3). Local cooperation. Fully complied with to date. Terminal facilities. There is a commercial marina located at Sisters Creek. No other facilities exist along this section of the waterway and none are currently required. Operations and results during fiscal year. Maintenance: Condition and operation studies for the year cost $1,850. Supervision and administrative costs were $4,806. Condition at end of fiscal year. Project was completed in 1941. Total costs under the existing project to September 30, 1985, have been $263,659 for new work and $5,292,112 for maintenance, a total of $5,555,771. 9-2 JACKSONVILLE, FLA. DISTRICT 4. BAKERS HAULOVER INLET, FLA. Location. The Harbor connects the Intracoastal Waterway and the Atlantic Ocean and is located 2 miles north of Miami Beach in Dade County, Florida. Existing project. The authorized project provides for an entrance channel 11x200 feet, thence 8x100 feet to the Intracoastal Waterway, and a marina basin 8x200 feet. The length of the project is 1.02 miles. Plane of reference is mean low water. Operations and results during fiscal year. Maintenance: Dredging cost $-2,159. Engineering and design and supervision and administration costs were $1,180 and $10,510, respectively. Condition at end of fiscal year. The project was completed in December 1964. Project depths have been restored. 5. CANAVERAL HARBOR, FLA. Location. The harbor is located on the east coast of Florida in Canaveral Bight, about 146 miles south of the entrance to Jacksonville Harbor and 69 miles north of the entrance to Fort Pierce Harbor. (See Coast and Geodetic Survey Charts Nos. 456 and 1245.) Existing project. The authorized project provides for maintenance of the 44-foot-deep entrance channel and 35-foot-depth turning basin; construction and operation of a sand transfer plant; relocation of the perimeter dike about 4,000 feet westward and extension of the harbor westward; two entrance jetties 100 feet long (constructed of native stone core and granite sides and cap); a lock; a channel and turning basin 31 feet deep near the relocated dike; and a barge canal 12 by 125 feet from the turning basin to the Atlantic Intracoastal Waterway. Plane of reference is mean low water (ocean) for harbor dike and lock, and mean low water (Banana River) for barge canal. The project is about 11.5 miles long. Mean tidal range is 3.5 feet at the entrance and practically non-tidal in Banana and Indian Rivers. (See Table 9-C for Data Relative to Lock.) Estimated cost (Oct. 1984 price levels) of the 1962 modification to the project is $25,800,000 Federal cost and $4,249,000 non-Federal cost ($235,000 contributed funds and $4,014,000 other costs); $700,000 costs to NASA and $84,000 costs to U.S. Coast Guard. (See Table 9-B for Authorizing Legislation.) Local cooperation. Local interests must: provide all lands, rights-of-way, spoil-disposal areas, retaining dikes, and embankments; hold United States free from damages; provide and maintain four-lane bridge and roadway subject to Federal contribution of 65.3 percent of cost of constructing bridge and 51.2 percent of constructing roadway; provide public terminal and transfer facilities; and make alterations as required in berthing facilities. For further details see Senate Document 140, 87th Congress, 2d session. Non-Federal contribution for new work is $1,106,000. Terminal facilities. Canaveral Harbor has 27 commercial waterfront facilities. The General Cargo Facilities consist of 1,900 feet of usable berthing space and 5 transit sheds with a total shed storage space capacity of 168,000 square feet. The Oil Handling Facilities operate with 3,760 feet of usable berthing space and 22 storage tanks providing a total of 1,195,620 barrels of tank storage. Available warehouse storage includes 28,000 square feet of dry storage and 2,500,000 cubic feet of cold storage. Two hundred sixty-six acres of open storage is also available. Two cruise ship berths totaling 1200 feet long by 41-foot depth and two 8800 square foot cruise terminals are also located on the south side The western cruise ship berth is equipped with a roll on/off ramp and is adjacent to 20 acres of trailer storage area. Hoisting facilities consist of one 45-ton floating crane and crawler and mobile cranes, with capacities from 70 to 200 tons, available from local crane rental services There are two water-front marine repair facilities with the nearest drydock facilities located at Port Everglades and Jacksonville. Two tugs with ratings of 1,600 and 2,250 horsepower are also available. There is no rail service available at the port. The nearest rail service is the Florida East Coast Railway located 9 miles away. Facilities are considered adequate for existing commerce. (See Port Series #16, Rev. 1982.) Operations and results during fiscal year. New Work: Engineering and design costs were $241,023 for the harbor extension. Maintenance: Maintenance and operation of locks amounted to $262,987 for the fiscal year. Operation and maintenance of district communications network cost $24,000. Condition and operation studies for the year cost $123,690. Dredging of the Canaveral Harbor Entrance Channel by hopper dredge amounted to $4,984,447. Costs for the Natural Resource study were $56,654. Cost for operation of service facilities amounted to $5,271. Real estate management costs were $3,037. Costs for permanent operating equipment were $956. Administrative Activities costs were $2,269. Engineering and design and supervision and administration costs were $150,352 and $14,646, respectively. Condition at end of fiscal year. The existing project is about 80 percent completed. The perimeter dike and jetties are in good condition. Work remaining to complete the project is completion of the harbor extension and construction of the sand transfer plant. 9-3 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 6. CHANNEL FROM NAPLES TO BIG MARCO PASS, FLA. Location. Naples Bay is on the southwestern side of the Florida peninsula about 35 miles south of the mouth of the Caloosahatchee River and approximately 1 mile inland and parallel to the Gulf of Mexico coastline. (See Coast and Geodetic Survey Chart No. 1254.) Existing project. The authorized project provides for an interior channel 6 by 70 feet from Naples to Big Marco Pass; a channel 12 by 150 feet from the Gulf of Mexico to Gordon Pass, thence 10 by 100-70 feet to a 10-foot-depth turning basin in the upper Naples Bay; and an 8-foot-depth turning basin at the municipal yacht basin. Plane of reference is mean low water. Mean tidal range is 2.1 feet. (See Table 9-B for Authorizing Legislation.) For further details see Annual Report of 1962. Local cooperation. Fully complied with to date. Contributed funds for new work were $159,975. Terminal facilities. Four seafood packing houses, 4 marine repair yards; a municipal pier and basin for use by recreational boats; and numerous private piers and slips for both commercial and recreational craft are available. Facilities are considered adequate for existing commerce Operations and results during fiscal year. Maintenance: Engineering and design and supervision and administration costs were $52,630 and $1,600, respectively. Condition at end of fiscal year. The project is complete. 7. CHARLOTTE HARBOR, FLA. Location. The Harbor is located on the west coast of Florida about 68 miles south of the entrance to Tampa Bay and 150 miles north of Key West. (See Coast and Geodetic Survey Chart No. 1255.) Previous projects. For details, see page 457 of 1959 Annual Report. Existing project. The authorized project provides for a channel 32 by 300 feet, increased to 700 feet at the bend, from the Gulf of Mexico to Port Boca Grande, thence 10 by 100 feet from deep water at Port Boca Grande to and including a turning basin 200 feet square at the municipal terminal at Punta Gorda. Plane of reference is mean low water. The project is about 29.5 miles long. Mean tidal range is one foot at Port Boca Grande and 1.4 feet at Punta Gorda. Extreme range is about 3 feet at Port Boca Grande and 3.8 feet at Punta Gorda. Strong southwesterly winds raise water level about 1.5 feet; strong northerly and easterly winds lower it about one foot. (See Table 9-B for Authorizing Legislation.) Local cooperation. Local cooperation is fully complied with to date. Non-Federal contribution for new work was $15,563. Terminal facilities. Existing facilities consist of a phosphate wharf at Port Boca Grande and a municipal earthfill pier about 850 feet long at Punta Gorda, both open to the public, Railway connections are available at Port Boca Grande, and highway and railway connections are available at Punta Gorda. There is a tank farm at Port Boca Grande for storage and rehandling of bunker fuel oil and numerous facilities are available in the area for docking and servicing small craft. Facilities are considered adequate for existing commerce. Operations and results during fiscal year. Maintenance: Dredging amounted to $1,884,794. Condition and operation studies cost $7,048. Engineering and design and supervision and administration costs were $83,587 and $30,295, respectively. Condition at end of fiscal year. The project was completed in 1959. Total costs under existing project through September 30, 1985, have been $533,169 for new work and $11,587,744 for maintenance, a total of $12,120,913. In addition, $15,563 was expended from contributed funds for new work in Boca Grande entrance channel. 8. CROSS FLORIDA BARGE CANAL Location. The proposed canal extends up the St. Johns River, past Palatka, thence up the valley of the Oklawaha River across the divide south of Ocala, and down the valley of the Withlacoochee River to the Gulf of Mexico, about 95 miles north of Tampa, Florida. Existing project. The authorized project provides for a lock canal with project depth of 12 feet and a minimum bottom width of 150 feet, with five locks and two earth dams. Project including the section in the St. Johns River is 184 miles long. (See Table 9-D for Locks and Dams.) Operation and maintenance of the locks and dams is a Federal responsibility. Estimated cost of new work (1970) is $179,000,000 Federal, and $19,500,000 non-Federal for lands, rights-of-way, and other costs. (See Table 9-B for Authorizing Legislation.) Local cooperation. Local interests must furnish lands and rights-of-way for construction of canal; hold the United States free from damages; and operate and maintain all highway bridges and roadways built in connection with project. Terminal facilities. None. Operations and results during fiscal year. (See Table 9-E for work accomplished.) 9-4 JACKSONVILLE, FLA. DISTRICT Regulation. a. Lake Ocklawaha. During the period the lake continued to be regulated at 18.0 feet, NGVD by discharging through the Rodman spillway. b. Lake Rousseau. During the period, the lake continued to be regulated at 27.5 ft., NGVD by discharging through the Inglis Main and Bypass Spillways. Condition at end offiscal year. Construction of project commenced February 25, 1964, and is 36 percent completed. Inglis Lock, Dam, and Spillway; Rodman Dam and Spillway, Eureka Lock, Dam, and Spillway; Henry H. Buckman Lock; and canal from Palatka to Lake Ocklawaha and from Withlacoochee River to Gulf of Mexico, including Inglis Bypass Channel, are completed. Construction work on the project was terminated in FY 1971 by order of the President. A restudy report and environmental impact statement were completed in February 1977. 9. EAU GALLIE HARBOR, FLA. Location. The Harbor is located on Indian River about midway of the State of Florida, 176 miles south of Jacksonville Harbor and 174 miles north of Miami Harbor. Existing project. The authorized project provides for a channel 8 x 100 feet from Indian River to and including a 300 x 600-foot turning basin in Eau Gallie. The project is about 2,700 feet long. Plane of reference is mean low water. The harbor is almost non-tidal. Local cooperation. Fully complied with to date. Terminal facilities. A privately owned boatyard in Eau Gallie Harbor provides more than 600 feet of docking space used chiefly by pleasure boats. There are also two marine railways and repair and storage facilities available. The facilities are considered adequate for the present needs of navigation. Operations and results during fiscal year. Maintenance: Dredging by contract cost $332,238. Engineering and design and supervision and administration costs were $4,731 and $8,088, respectively. Condition at end of fiscal year. The project was completed in 1939. In December 1982, the controlling depth of the channel was 5 feet. 10. FERNANDINA HARBOR, FLA. Location. Entrance to the harbor is located on the northeast coast of Florida about 95 miles south of the entrance to Savannah Harbor, Georgia, and 22 miles north of the entrance to Jacksonville Harbor, Florida. (See Coast and Geodetic Survey Chart No. 453.) Existing project. The authorized project provides for a 32-foot-depth channel (maximum channel in active status: 28 feet) generally 300-400 feet wide from deep water in the ocean to the junction of Lanceford Creek with Amelia River; an 800-foot-wide turning basin at the first bend below Lanceford Creek; and two jetties, 19,150 and 11,200 feet long. Plane of reference is mean low water. The project is 7 miles long. Mean tidal range is 5.8 feet on the bar and 6 feet in the inner harbor. (See Table 9-B for Authorizing Legislation.) Local cooperation. Fully complied with to date. Non-federal contribution for new work was $812,000. Terminal facilities. There are two large wharves operated by industrial plants; twelve wharves serving fishing boats, recreational craft, and other vessels; three oil handling wharves with pipelines; and a Municipal Marina and Sportsman's Wharf with public facilities for small craft. Total berthing space is approximately 4,065 feet. Most terminals are served by rail, and all have highway access. Facilities are considered adequate for existing commerce. (See Port Series No. 16 (Part 2), 1964.) Operations and results during fiscal year. Maintenance: Dredging cost $1,960,300. Condition and operation studies cost $133,830. Engineering and design and supervision and administration costs were $59,650 and $91,130, respectively. Condition at end of fiscal year. The active portion of the existing project is complete Jetties are in poor condition and are badly in need of repair. Remaining work is to deepen the inner harbor channel and turning basin to 32 feet when and if the presently inactive 1950 authorization is reactivated. The entrance channel has been deepened to 40 feet for the Kings Bay project. 11. FORT MYERS BEACH, FLA. Location. Fort Myers Beach is on Estero Island near the mouth of the Caloosahatchee River, about 20 miles below Fort Myers and 110 miles south of Tampa, Florida. (See Coast and Geodetic Survey Charts Nos. 855-SC and 1255.) Existing project. The authorized project provides for a channel 12 by 150 feet from that depth in San Carlos Bay into Matanzas Pass, thence 11 by 125 feet in Matanzas Pass to and including a turning basin 2,000 feet upstream from the upper shrimp terminals. Plane of reference is mean low water. Project is 2.5 miles long. Mean tidal range is 1.7 feet. Spring range is about 2.3 feet. Strong northerly winds lower the water surface 1 to 2 feet; strong southerly winds have an opposite effect. (See Table 9-B for Authorizing Legislation.) Local cooperation. Fully complied with to date. Non-Federal contribution for new work was $1,095. Terminal facilities. There are three shrimp- 9-5 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 packing houses and several fish-packing houses, two marine railways, a fuel terminal and an ice manufacturing plant in the area. There are several commercial facilities for servicing shrimp boats. Recreationalcraft facilities include nine marinas, a boat motor testing laboratory which is closed, and numerous privately owned piers and wharves. All terminals have highway access. Facilities are considered adequate for existing commerce. Operations and results during fiscal year. Maintenance: Engineering and design and supervision and administration costs were $42,047 and $2,864, respectively. Condition at end of fiscal year. The project is complete. 12. FORT PIERCE HARBOR, FLA. Location. On east coast of Florida, about 218 miles south of entrance to St. Johns River and about 124 miles north of entrance to Miami Harbor. (See Coast and Geodetic Survey Chart No. 582.) Existing project. A channel 350 feet wide at the 27-foot contour in the ocean, tapering to a width of 200 feet at Sta. 100+00, thence 200 feet wide to Sta. 30+ 00, and thence flaring to a turning basin 900 feet wide. Entrance channel is 27 feet deep to Sta. 130+00 and thence 25 feet deep to and including the turning basin. Project includes the maintenance of two jetties and shore revetments at the inlet. Length of project is about 3.5 miles. Mean tidal range is 2.6 feet at the entrance and 0.7 foot at terminals. (See Table 9-B for Authorizing Legislation.) For further details see 1961 Annual Report. Local Cooperation. Fully complied with to date. Non-Federal contribution for new work was $18,574. Terminal facilities. Two earth-filled piers forming a slip 200 feet by 300 feet, with bulkhead wharf at inner end, affording berthing space of about 1,653 feet. The south pier and bulkhead wharf are municipally owned. Facilities also include a cooling plant, a warehouse and a fruit packing house. The north pier is served by railway and both piers by highway connnections. North of the turning basin local interests have provided deep-draft berthing and pier facilities. Also available is a bulkhead wharf with a depth of 25 feet with ample room for open storage and with tank storage for petroleum in the rear. Facilities are considered adequate for existing commerce. Operations and results during fiscal year. Maintenance: Condition and operation studies cost $15,131. Engineering and design and supervision and administration costs were $40,938 and $108, respectively. Condition at end of fiscal year. The project was completed in 1938 except for the fishing walkway atop the south jetty which was completed by local interests in 1968. Local interests installed lighting atop the jetty in 1969. The south jetty and revetments are in good condition. The north jetty is scheduled for repair in FY 86. 13. INTRACOASTAL WATERWAY, CALOOSAHATCHEE RIVER TO ANCLOTE RIVER, FLA. Location. The Waterway extends from the mouth of the Caloosahatchee River at Punta Rassa, Florida, to the mouth of Anclote River, Florida, following in general an almost continuous series of protected inside waterways along the gulf coast of Florida. (See Coast and Geodetic Survey Charts Nos. 856-SC, 857-SC, and 858.) Previous projects. For details see page 767 of 1945 Annual Report. Existing project. The authorized project provides for a channel 9 by 100 feet from Caloosahatchee River to Anclote River; deepening the existing channel at Caseys Pass to 9 feet; a channel 6 by 80 feet (Cats Point Channel) along the southeastern side of Boca Ciega Bay past Frenchman Creek and Gulfport; maintenance of bulkheads, revetments, and two jetties built at Caseys Pass under previous project; and improvement and maintenance of Sunshine Skyway Channel. Plane of reference is mean low water. The project includes about 160 miles of channels. Mean ranges of tide are 1.7 feet at Punta Rassa, 1 foot at Port Boca Grande, 1.4 feet in Tampa Bay at Anna Maria, and 2 feet at entrance to Anclote River. Extreme ranges are about 4.5 feet at Punta Rassa, about 3 to 4 feet between Port Boca Grande and Corey Causeway over Boca Ciega Bay, and about 5.5 feet at entrance to Anclote River. Southerly winds over the area generally raise water level by 1 to 1.5 feet; northerly winds lower water level by 1 to 2 feet. (See Table 9-B for Authorizing Legislation.) Local cooperation. Fully complied with to date Non-Federal contribution for new work was $14,473. Terminal facilities. Existing facilities include one municipal concrete pier, one railway pier, one freight wharf, one marginal wharf 500 feet long on terminal island, and eleven privately owned landings, all at Sarasota. Municipal pier and freight wharf are open to the public. All piers have highway connections. There are six wharves along Boca Ciega Bay and a number of small privately owned piers and wharves at various points along waterway for use of commercial fishing boats and recreational craft. Facilities are considered adequate for existing commerce. Operations and results during fiscal year. Maintenance: Maintenance of channel slopes and berms cost $6,523. Removal of sunken vessels by 9-6 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 hired labor cost $800. Operation and maintenance of district communications network cost $18,000. Condition and operation studies cost $70,729. Engineering and design and supervision and administration costs were $31,843 and $11,144, respectively. Condition at end of fiscal year. Existing project is complete. A contract to maintain the jetties at Casey's Pass was completed in 1983. Total Federal costs under existing project through September 30, 1985 were $7,597,078 for new work and $5,328,140 for maintenance, a total of $12,925,218. In addition, $14,473 contributed funds were expended for Sunshine Skyway and Boca Ciega Bay channels. 14. INTRACOASTAL WATERWAY, JACKSONVILLE TO MIAMI, FLA. Location. The waterway extends from Jacksonville to Miami, Florida, following the St. Johns River to the mouth of Pablo Creek and thence following in general an almost continuous series of protected inside waterways along the Atlantic coast of Florida to Miami. (See Coast and Geodetic Survey Charts Nos. 841-SC, 843-SC, 845-SC, and 847-SC.) Previous projects. For details, see pages 618-619 of 1938 Annual Report. Existing project. The authorized project provides for a channel 12 by 125 feet from Jacksonville to Miami, modified to 10-foot-depth from Fort Pierce to Miami by Chief of Engineer's report of July 22, 1960; side channels at Sebastian and Daytona Beach and turning basins at Sebastian and Vero Beach, all to an 8-foot-depth; and operation and maintenance of the Palm Valley highway bridge. Project is 370 miles long, including 21 miles in Jacksonville Harbor. Mean range of the tide is 3.8 feet at St. Johns River, 0.7 foot in the Indian River at Fort Pierce, 1.8 feet in Lake Worth at Port of Palm Beach terminals, 2.3 feet at the Port Everglades terminals, and 2 feet in Biscayne Bay. The extreme range is about 7 feet at St. Johns River, 1.5 feet at Fort Pierce, and 3 feet in Biscayne Bay. Plane of reference is mean low water. Tidal effect is imperceptible at points along waterway distant from inlets. (See Table 9-B for Authorizing Legislation.) Local cooperation. Fully complied with to date. Terminal facilities. There are a number of privately owned piers, wharves, and landings at various points along waterway. Terminals with railway connections are available at Jacksonville, Fort Pierce, West Palm Beach, Port Everglades, and Miami. Municipal piers or wharves have been constructed at Titusville, Cocoa, Melbourne, and Vero Beach for handling general freight and at St. Augustine, Daytona Beach, New Smyrna Beach, Eau Gallie, West Palm Beach, Delray Beach, Fort Lauderdale, and Miami for use of recreational craft. Yacht basins, open to the public, have been provided at Jacksonville Beach, Daytona Beach, Titusville, Eau Gallie, Vero Beach, Fort Pierce, West Palm Beach, Fort Lauderdale, Hollywood, and Miami. Facilities are considered adequate for existing commerce. (For further details on facilities at Jacksonville, see Port Series No. 15, 1969, and at Palm Beach, Port Everglades, and Miami, see Port Series Na 16, Revised 1972.) Operations and results during fiscal year. Maintenance: The cost of dredging was $335,843. Lock maintenance cost was $18,072. Cost of hired labor to remove sunken vessel was $2,000. Condition and operation studies cost $75,376. Real estate management cost $25,034. Engineering and design and supervision and administration costs were $295,752 and $2,228, respectively. Operation and care: The highway bridge near Palm Valley was operated and maintained at a cost of $78,308. Condition at end of fiscal year. The existing project as modified by the Chief of Engineers is complete except for construction of the channel and turning basin at Sebastian, Florida, which is in an inactive status. Total Federal costs under existing project through September 30, 1985, were $19,251,598 for new work: $23,437,835 for maintenance and $2,246,506 for operation and care, a total of $45,152,340, regular funds. In addition, $2,199,842 has been expended from public works funds for new work. 15. JACKSONVILLE HARBOR, FLA. Location. The authorized project comprises the lower 24.9 miles of St. Johns River which empties into the Atlantic Ocean near the northeasterly corner of the Florida peninsula. (See Coast and Geodetic Survey Chart No. 636-SC.) Previous projects. For details, see page 607 of Annual Report, 1938. Existing project. The authorized project provides for a channel 38 by 400-1,200 feet from the ocean to mile 20 via Dame Point-Fulton Cutoff, thence 34 feet to Commodore Point, and thence 30 feet deep to the F.E.C. Railway bridge at Jacksonville, including a 30-foot channel in Arlington Cut and in the Old Dame Point-Fulton Channel; maintenance of the existing 42 and 40-foot-depth entrance channel; maintenance of jetties at channel entrance; and construction of training walls and revetments. Plane of reference is mean low water. The project is about 26.8 miles long. Mean tidal range is 5.3 feet on the bar, 4.9 feet at Mayport, 2.6 feet at Dame Point, and 1.1 feet at Jacksonville. The extreme range varies from about 9 feet on the bar to about 1.5 feet at Jacksonville. Strong northeasterly winds raise the water level 9-7 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 about 2 feet at Mayport and Jacksonville. Strong southwesterly winds lower the water about 1.5 feet at Mayport and 1 foot at Jacksonville. (See Table 9-B for Authorizing Legislation.) Local cooperation. Local interests have fully complied with requirements of local cooperation for work performed to date. For work authorized by the 1965 River and Harbor Act, local interests were required to contribute 2.6 percent of the contract price plus supervision and administration for work provided by the Corps; provide all lands and rights-of-way; save the United States free from damages; and provide and maintain public terminal and transfer facilities. Assurances of local cooperation for this work were accepted February 11, 1966. Terminal facilities. Jacksonville Harbor has 84 waterfront facilities. Available at the General Cargo Facilities are 11,140 feet of usable berthing space and 12 transit sheds with a total storage space of 1,009,800 square feet. The Oil Handling Facilities consist of 7,843 feet of usable berthing space and 179 storage tanks providing a total of 8,478,900 barrels of tank storage. Warehouse storage at the port includes 3,266,900 square feet of dry storage and 4,071,100 cubic feet of cold storage. Available open storage is 223 acres. Four fixed cranes with capacities from 40 to 100 tons are located at the port. Available locally are crawler and truck cranes with capacities up to 100 tones. Various phases of marine repair work are accomplished by 7 waterfront repair facilities and numerous other companies located offwater. Drydock Facilities consist of 6 floating drydocks with capacities from 800 to 33,000 tons. Floating equipment includes 25 tugs with up to 3,300 horsepower and 16 tank barges with capacities up to 20,700 barrels. Three major railroads furnish rail service from port docks to all points outside of Jacksonville. Facilities are considered adequate for existing commerce. (See Port Series #15, Rev. 1978.) Maintenance: Operation and maintenance of district communications network cost $11,000. Condition and operation studies cost $308,138. Maintenance dredging costs were $6,599,677. Jetty maintenance costs were $194,080. Engineering and design and supervision and administration costs were $141,620 and $107,865, respectively. Condition at end of fiscal year. Construction of the modification to the project, authorized by 1965 River and Harbor Act, is completed. The north jetty is in fair condition and partially submerged at high tide The south jetty was repaired in FY 1985 to prevent further damage to the Mayport Naval Station. Revetments and retaining walls were in poor condition. Total Federal costs under existing project through September 30, 1985, were $43,786,128 for new work, $54,175,779 for maintenance, a total of $97,961,907 regular funds. In addition $290,013 has been expended from public works funds for new work. 16. JOHNS PASS, FLA. Location. A natural inlet on the west coast of Florida connecting Boca Ciega Bay with Gulf of Mexico. The pass is located about 8 miles northwest of lower Tampa Bay directly across Boca Ciega Bay from St. Petersburg, Fla. (See Coast and Geodetic Survey Chart No. 1257.) Existing project. Channel 10 by 150 feet in the gulf, thence 8 by 100 feet inside pass, and 6 by 100 feet to the Intracoastal Waterway, and suitable protective measures over a frontage of approximately one thousand linear feet of shore along the north end of Treasure Island. Plane of reference is mean low water. Mean range of tide is 1.5 feet. Project is about 2.6 miles long. Project was authorized December 2, 1964 by Chief of Engineers under Section 107 of the 1960 River and Harbor Act and by Section 110 of the 1966 River and Harbor Act. Local cooperation. Fully complied with to date. Non-Federal contribution for new work was $53,732. Terminal facilities. Only small marinas and repair yards for recreational craft in the general vicinity. Facilities are considered adequate for existing commerce. Operations and results during fiscal year. Maintenance: Dredging costs were $285,448. Engineering and design and supervision and administration costs were $44,706 and $1,596, respectively. Condition at end of fiscal year. Project was completed in 1968. 17. LONGBOAT PASS, FLA. Location. Longboat Pass is located on the west coast of Florida about 11 miles northwest of Sarasota and 23 miles south of St. Petersburg. Located in Manatee County, it is one of several natural inlets connecting Sarasota Bay, a tidal estuary, with the Gulf of Mexico. (See Coast and Geodetic Survey Chart No. 1256.) Existing project. The authorized project provides for an entrance channel 12 by 150 feet from the Gulf to Longboat Pass Bridge, thence a channel 10 by 100 feet from Longboat Pass Bridge along a north to northeasterly alinement to the Intracoastal Waterway and extending along Intracoastal Waterway to Cortez Bridge The mean tidal range is 2.2 feet and the maximum tidal range is about 5 feet. Currents are predominantly tidal. (See Table 9-B for Authorizing Legislation.) 9-8 JACKSONVILLE, FLA. DISTRICT Local cooperation. Fully complied with. See 1978 Annual Report for detailed local cooperation requirements. Contributed funds for new work were $172,324. Terminal facilities. From Sarasota north to Tampa Bay there are about 28 small craft facilities including marinas, boat repair yards, and boat basins along the Intracoastal Waterway. Nine of them are located within 2 miles of Longboat Pass. Numerous private mooring piers and wharves also exist in the area. The marina and repair facilities appear adequate for the general boating needs of the area. Operations and results during fiscal year. Maintenance: Dredging costs were $289,048. Engineering and design and supervision and administration costs were $29,547 and $8,529, respectively. Condition at end of fiscal year. Construction of the project is complete. 18. MAYAGUEZ HARBOR, P.R. Location. The project is on the west cost of Puerto Rico, about 110 miles by water from San Juan Harbor. (See Coast and Geodetic Survey Chart Na 931.). Existing project. The authorized project provides for a 30 by 1,000 foot approach channel to the deep water terminal, decreasing to a 500 foot width opposite westerly end of terminal, thence the same width to easterly end of terminal. (See Table 9-B for Authorizing Legislation.) Local cooperation. Fully complied with to date. Terminal facilities. A modern deep water terminal is located in the northeast section of the harbor consisting of a bulkhead wharf about 1,270 feet long with a storage transit shed 800 by 60 feet immediately shoreward. The Puerto Rico Industrial Development Company, an agency of the Commonwealth of Puerto Rico, owns a bulkhead wharf of about 200 feet in line with the existing deep water terminal plant located within the industrial harbor area. In addition, Bumble Bee Packing Company, Inc., owns and operates a dock of about 200 feet for docking tuna fish boats. Facilities are considered adequate for existing commerce Operations and results during fiscal year. Maintenance: Condition and operation studies cost $541. Engineering and design costs were $2,482. Condition at end of fiscal year. Project was completed in 1934. 19. MELBOURNE HARBOR, FLA. Location. The project is on Indian River about midway of the State of Florida, 179 miles south of Jacksonville Harbor and 171 miles north of Miami Harbor. Existing project. The authorized project provides for a channel 8 x 100 feet from Indian River to a 400- x 800-foot turning basin in Crane Creek. Project is about 3,150 feet long. Plane of reference is mean low water. The harbor is almost non-tidal. Local cooperation. Fully complied with to date. Terminal facilities. The Municipal Marina on the north end of the turning basin has a 350-foot steel bulkhead with eleven finger piers about 40 feet long each. There are also two privately owned storage and repair facilities and several privately owned boathouses and docks. The facilities are considered adequate for existing commerce. Operations and results during fiscal year. Maintenance: Dredging costs $214,800. Engineering and design and supervision and administration costs were $12,655 and $6,112, respectively. Condition at end of fiscal year. The project was completed in 1938. As of September 1984 channel depths as authorized were available throughout the project. 20. MIAMI HARBOR, FLA. Location. Miami is near the northern end of Biscayne Bay, about 71 miles south of the entrance to Palm Beach Harbor. Miami River has its source in the Everglades and flows southeasterly to enter Biscayne Bay at Miami. (See Coast and Geodetic Survey Charts Nos. 547 and 1248.) Existing project. The authorized project provides for a 38 by 500-foot channel from the ocean to the outer end of the north jetty, thence 36 by 400 feet through the entrance and across Biscayne Bay to and including a turning basin at the municipal terminals; a 36-foot depth turning basin at Fisher Island; two rubblestone jetties at the entrance; a channel 15 by 200 feet from the mouth of Miami River to the turning basin at the municipal terminals; a channel 8 by 200 feet from the mouth of Miami River to the Intracoastal Waterway and thence 100 feet wide to Government Cut; a channel 15 deep in Miami River varying in width from 250 feet at mouth to 90 feet inland; and a channel 12 by 100 feet from Miami to a harbor of refuge in Palmer Lake Plane of reference is mean low water, except for 15-foot channel in Miami River where depths are based on flood conditions. Total length of the project is about 15.3 miles. Mean tidal variation is 2.5 feet at entrance and 2 feet in the bay. Extreme variation is about 4.5 feet at entrance and 3 feet in Biscayne Bay. Strong easterly winds raise the water level about 1.5 feet at entrance and 1 foot in the bay. Strong westerly winds lower water level about 1 foot at entrance and about 0.5 foot in the bay. (See Table 9-B for Authorizing Legislation.) Local cooperation. Fully complied with. See 1978 9-9 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Annual Report for detailed local cooperation requirments. Assurances of local cooperation for the 1968 modification to the project were accepted December 18, 1968. Terminal facilities. There are 91 commercial waterfront facilities serving the port. The General Cargo Facilities include 21,373 feet of usable berthing space, 13 transit sheds with a total capacity of 474,300 square feet, and 9 freight stations with a total storage capacity of 270,400 square feet. Oil Handling Facilities consist of 2,714 feet of usable berthing space and 36 storage tanks with a total storage capacity of 744,475 barrels. Available sharehouse storage includes dry storage at 1,450,500 square feet and cold storage at 11,204,000 cubic feet. There are 117.1 acres of open storage at the port. Hoisting Facilities located at the port include two 40-ton cranes and cranes with capacities up to 200 tons available thru local rental. Twelve waterfront repair yards and two offwater yards serve the port. Drydock facilities available include 7 marine railways and 4 boat lifts with haulout capacities ranging from 40 to 1,000 tons and lifting capacities ranging from 70 to 500 tons. Nine tugs, with ratings up to 3,000 horsepower, and thirteen tank barges, with capacities up to 35,000 barrels, are also available Rail Facilities at the port are served by the Seaboard Coast Line and the Florida East Coast Railway. Facilities are considered adequate for existing commerce. (See Port Series #16, Rev. 1982.) Operations and results during fiscal year. New work: Contract for recreation facilities at Bay Front Park underway cost $75,000. Engineering and design and supervision and administration costs were $180,532 and $13,522, respectively. Maintenance: Condition and operations studies cost $51,844. Removal of sunken vessels cost $2,500. Condition at end of fiscal year. Construction of the modification to the project, authorized by River and Harbor Act of 1968, is complete South and north jetties are in good condition. NiEW PASS, SARASOTA, FLA. Location. Sarasota Bay is a tidal lagoon along the west coast of Florida immediately south of Tampa Bay. New Pass is a gulf inlet across the bay from Sarasota, Fla. (See Coast and Geodetic Survey Chart No. 857-SC.) Existing project The authorized project provides for an entrance channel 10 feet deep and 150 feet wide in the Golf of Mexico diminishing to 8 by 100 feet through New Pass and extending across Sarasota Bay to the Intracoastal Waterway with side channels to and turning basins at, Payne Trminal and city pier. Place of reference is mean low water. Mean range of tide is 1.3 feet in Sarasota Bay; mean spring range is 1.7 feet. Project is about 4 miles long. (See Table 9-B for Authorizing Legislation.) Local cooperation. Fully complied with to date. Non-Federal contribution for new work amounted to $45,811. Terminal facilities. Consist of Payne Tbrminal, a slip 200 by 650 feet, and city pier, 400 feet long with two finger piers equipped with adequate facilities at each location. Operations and results during fiscal year. Maintenance: Removal of sunken vessels cost $354. Dredging costs were $851,499. Engineering and design and supervision and administration costs were $29,734 and $10,857, respectively. Condition at end of fiscal year. Project was completed in 1964. 22. OKEECHOBEE WATERWAY, FLA. Location. The waterway traverses the southern part of the Florida peninsula via the Caloosahatchee River, Lake Okeechobee, and St. Lucie Canal, connecting coastal waterways along the Gulf and Atlantic Shores. (See Coast and Geodetic Survey Charts Nos. 11428 and 11427.) Previous projects. For details, see page 785 of 1949 Annual Report. Existing project. The authorized project provides for replacing the old locks on the St. Lucie Canal by a single new lock; a channel 10 by 100 feet from Ft. Myers for about 5 miles upstream, thence 8 by 80 to 100 feet to the Intracoastal Waterway, Jacksonville to Miami; near Stuart; an 8-foot depth basin at Stuart; a side channel at Ft. Myers; operation and care of St. Lucie Lock; and maintenance of features completed under previous projects as follows: a 12 by 200-foot channel from the Gulf to Punta Rassa, thence 10 by 100 feet to Fort Myers with a 10-foot depth basin at Fort Myers; a 6 by 80-foot channel along the south shore of Lake Okeechobee from Clewiston to St. Lucie Canal; a 6 by 60-foot channel in Taylor Creek from the town of Okeechobee to the Lake; and operation and care of Moore Haven and Ortona Locks. (See Table 9-B for Authorizing Legislation.) For further details see 1962 Annual Report. Local cooperation. Fully complied with for completed portion of project. Non-Federal contribution amounted to $503,700. Terminal facilities. There are 3 freight piers, 1 municipal recreation pier, 4 privately owned piers, and a municipal yacht basin on the Caloosahatchee River near Fort Myers. The Corps has provided a boat basin, launching ramp, and a 120-foot wharf on the Caloosahatchee River about one-quarter mile 9-10 JACKSONVILLE, FLA. DISTRICT below Ortona Lock. There are tie-up dolphins above and below all 5 locks. Commercial yacht basins are provided on the south side of the Caloosahatchee River about halfway between Ortona and Moore Haven Locks and about 3 miles east of LaBelle. A commercial/municipal yacht basin is provided on the north side of the St. Lucie Canal at Indiantown. There are numerous small wooden-pile landings along the Caloosahatchee River on St. Lucie Canal, and on the St. Lucie River, including one railroad terminal pier, a municipal pier, and a pier for handling petroleum products at Stuart. Also, 550 feet of wharves have been provided on the west side of Taylor Creek immediately landward of Hurricane Gate Na. 6 and 150 feet on the east side of the creek. A yacht basin has been provided on the west side of the creek immediately landward of the hurricane gate. The installations of Taylor Creek are privately owned, but are open to the public A breakwater protected harbor is available at Pahokee. There is a 440-foot marginal wharf on the Industrial Canal at Clewiston; a 125-foot wharf at LaBelle; a 150-foot wharf at Belle Glade; a 125-foot wharf at Moore Haven; a 50-foot wharf at Alva; and a 30-foot wharf on Taylor Creek at the town of Okeechobee. A docking facility for loading raw sugar was constructed in 1967 on Herbert Hoover Dike near Belle Glade. All have highway and/or railway connections. Facilities are considered adequate for existing commerce. Operations and results during fiscal year. (See Table 9-F for work accomplished.) Condition at end of fiscal year. The project is complete except for providing the 8-foot depth basin at Stuart, which is inactive. Total Federal costs under the existing project through September 30, 1985, were $5,178,215 for new work, $22,100,400 for maintenance ($67,558 excluded which represents services rendered without reimbursement), a total of $27,278,615. 23. OKLAWAHA RIVER, FLA. Location. The river has its source in a system of large lakes in the central part of the Florida peninsula and flows generally northerly, then easterly, emptying into St. Johns River 22 miles above Palatka. The extreme head of the system is considered to be Lake Apopka, 120 miles above the river's mouth. Previous projects. For details, see page 613 of 1938 Annual Report. Existing project. The authorized project provides for a channel 6 feet deep from the river mouth to the head of Silver Springs Run; clearing a channel to Lake Griffin; maintaining dikes to obtain a navigable depth of about 4 feet to Leesburg and construction of a lock and dam at Moss Bluff. The project length is about 85.7 miles in the river and 5.4 miles in Silver Springs Run. (See Table 9-B for Authorizing Legislation.) Local cooperation. Fully complied with to date. Terminal facilities. Several private and public landings and boat-launching ramps are located along the river. Public recreation-craft basins and boat launching ramps are near Silver Springs and State Road 40 and 316 bridges. There is a municipal wharf on Lake Griffin at Leesburg. A dam has created Lake Ocklawaha (13,000 acres) with egress to the St. Johns River through Buckman Lock. Along the lake are 4 launching ramps; Payne's Landing, Orange Springs, Kenwood Landing, and Rodman Recreation Area. Access below the dam is at the Oklawaha Boat launch ramp and at State Road 19. Facilities are considered adequate for existing commerce Operations and results during fiscal year. Maintenance: Real estate management costs were $5,697. Engineering and design costs were $1,835. Condition at end of fiscal year. The project is complete except for providing a 6-foot depth channel from the mouth of the river to the head of Silver Springs run, which is in an inactive status. The Moss Bluff lock and dam structure was replaced under the Four River Basins, Fla., flood control project. Tobtal Federal costs under the existing project through September 30, 1985 have been $311,352 for new work and $1,984,933 for maintenance (excluding $11,414 under provisions of the permanent indefinite appropriation), a total of $2,296,285. 24. PALM BEACH HARBOR, FLA. Location. The authorized project is located on the east coast of Florida about 71 miles north of the entrance to Miami Harbor and about 264 miles southeasterly from the entrance to Jacksonville Harbor. (See Coast and Geodetic Survey Charts Nos. 291 and 1248). Existing project. The authorized project provides for an entrance channel 35 by 400 feet merging with an inner channel 33 by 300 feet to and including a turning basin; tank revetment; and restoring jetties. Plane of reference is mean low water. The project is about 1.6 miles long. Mean range of tide in the ocean at the entrance is 2.8 feet and at the turning basin, 2.2 feet. Extreme range of tide is about 4.5 feet at the inlet and 3 feet at the terminals. Seven-foot tidal ranges have occurred during storms. For details, see 1962 Annual Report. (See Table 9-B for Authorizing Legislation.) Local cooperation. Fully complied with to date. For requirements, see 1961 Annual Report. Non-Federal contribution for new work was $509,506. Terminal facilities. The port has 13 commercial 9-11 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 waterfront facilities. The General Cargo Facilities include 5,156 feet of usable berthing space and 6 transit sheds with a total of 118,030 square feet storage capacity. The Oil Handling Facilities consist of 10 storage tanks with a total capacity of 2,029,600 barrels. Usable berthing space in not available at the Oil Handling Facilities. Dry storage is available at 150,500 square feet, cold storage at 19,200 cubic feet and open storage at 27.1 acres. Seven cranes with capacities from 15 to 230 tons are located at the port. There are no floating cranes, repair facilities or drydock facilities located at the port. A 100 ton vertical boat lift is located on the Intercoastal Waterway south of the port for heavy lifts. Two tugs with ratings of 900 and 1000 horsepower are available. The Palm Beach Belt Line which connects with the Florida East Coast Railway serves the port. Facilities are considered adequate for existing commerce. (See Port Series #16, Rev. 1982.) Operations and results during fiscal year. Maintenance: Dredging cost $1,922,120. Hired labor for repairs to jetty cost $1,599,999. Condition and operation studies for the project totaled $40,120. Engineering and design and supervision and administration costs were $50,249 and $109,074, respectively. Condition at end of fiscal year. The Project was completed in 1967. Jetties and revetment are in need of repair. The south jetty is scheduled for completion FY 86. 25. PONCE DE LEON INLET, FLA. Location. Ponce de Leon Inlet is on the Atlantic coast of Florida about 65 miles south of St. Augustine Harbor and 57 miles north of Canaveral Harbor. (See Coast and Geodetic Survey Chart No. 1245.) Existing project. The authorized project provides for an entrance channel 15 by 200 feet across the ocean bar, thence 12 by 200 feet and 12 by 100 feet through the inlet; thence southward in Indian River North, 12 by 100 feet, and northward in Halifax River, 7 by 100 feet, each leg continuing to the Intracoastal Waterway; ocean jetties on the north and south of the inlet 4,200 and 2,700 feet long, respectively, and a weir in the north jetty with an impoundment basin inside the jetty. Plane of reference is mean low water. Mean range of tide is 4.1 feet in the ocean and 2.3 feet inside the inlet. The project is about 5 miles long. Local cooperation. Fully complied with to date Non-Federal contribution for new work was $2,415,600. Terminal facilities. None in the immediate area. Operations and results during fiscal year. Maintenance: Repair of jetty cost $1,867,335. Dredging cost $4,452,052. Condition and operation studies cost $13,780. Engineering and design and supervision and administration costs were $40,104 and $102,905, respectively. Condition at end of fiscal year. Construction of the project is complete Repair of the north jetty should be completed in F.Y. 86. 26. PONCE HARBOR, P. R. Location. Ponce Harbor is an open bay about midway on the south coast of Puerto Rica From the center of the city of Ponce, the harbor is about 3 miles south. (See Coast and Geodetic Survey Chart Nos. 927 and 902.) Previous project. For details, see page 12 of Annual Report for 1975. Existing project. The authorized project provides for a seawall 362 feet long extending northwesterly across the rock reef from near the landward end of the municipal pier; dredging an area off the municipal pier, 30 feet deep and containing about 18 acres; a breakwater 2400 feet long extending southwesterly from Punta Carenero; a channel 36 feet deep by 600 feet wide extending from the Caribbean Sea approximately 2.8 miles up to the port, thence a channel 400 feet wide by 36 feet deep into the harbor, and a 36-foot-deep, irregularly shaped turning basin with a diameter of 950 feet. Plane of reference is mean low water. Mean tidal range is 0.6 foot, extreme varies between about 1 foot below and 2 feet above mean low water. Estimated cost of new work (Oct. 1984 price levels) is $9,150,000 Federal ($9,140,000 Corps and $10,000 U.S. Coast Guard) and $550,000 non-Federal (other costs). (See Table 9-B for Authorizing Legislation.) Local cooperation. Should provide all lands, easements and rights-of-way; provide and maintain at local expense depths in berthing areas and local access channels; hold United States free from any damages resulting from construction and maintenance of the project; relocate without cost to the United States all cables, sewer mains, water supply, drainage and other utility installations as required; provide adequate public terminal and transfer facilities open to all on equal terms. A letter has been received from mayor of Ponce, assuring compliance with local requirements and to cost share the project. A 50% contribution is required from locals. Terminal facilities. The municipality of Ponce owns and operates the only deep-draft terminal facilities in Ponce Harbor, which consist of a municipal pier 515 feet long and 108 feet wide, and a bulkhead wharf 3,811 feet long. Both are equipped for transfer and storage of freight. A 40 ton container lift shore crane is available for the handling of loaded containers. The municipal pier has a steel transit shed 386 by 85 feet. The bulkhead wharf has 9-12 JACKSONVILLE, FLA. DISTRICT four steel transit sheds totaling over 103,000 square feet. Three concrete and steel warehouses are available providing 800,000 square feet for general storage. Open storage areas for structural steel, lumber, and other bulk and package commodities are also provided. Bulk cement is handled and loaded into cement cargo ships by the use of a private pipeline loading facility. A tuna fish processing and canning factory is located on the premises, with direct access to the bulkhead wharf. Existing facilities are open to the public. Facilities are considered adequate for existing commerce. Operations and results during fiscal year. New Work: Engineering and design costs were $6,187. Maintenance: Engineering and design cost was $2,369. Condition at end of fiscal year. Construction of the 1976 modification of the project has not commenced. South and north jetties are in fair condition. 27. PORT EVERGLADES HARBOR, FLA. Location The h.rbor is on the east coast of Florida about 23 miles north of Miami and about 48 miles south of Palm Beach Harbor, Florida. (See Coast and Geodetic Survey Chart No. 546.) Existing project. The authorized project provides for an ocean entrance channel 45 by 500 feet through an ocean bar tapering to 42 by 450 feet between rubblestone entrance jetties, and continuing at that depth to an irregularly flared entrance and turning basin of same depth; enlarging Pier 7 channel to 36 by 400 feet for distance of about 1,600 feet; maintenance of the locally dredged channel opposite Berth 18 to 36 feet deep over a length of 700 feet with varying widths of 200 to 150 feet; construction of a south jetty fishing walkway; and, maintenance of the jetties. Plane of reference is mean low water. The project is about 1.9 miles long. Mean range of tide is 2.5 feet at the entrance and 2.3 feet at the terminals; extreme range is about 4.5 feet with storm tides of about 6.5 feet. Estimated cost of new work (Oct. 1980 price levels) of the 1974 authorization is $33,800,000 Federal (Corps of Engineers) cost and $7,062,000 non-Federal cost, $160,000 contributed funds and $6,902,000 other costs). (See Table 9-B for Authorizing Legislation.) Local cooperation. Local Cooperation has been fully complied with for work completed to date For work under House Document 144/93/1, local interest must: provide all lands, easements, and rights-of-way; save United States free from damages; accomplish utility and other relocations or alterations; provide depths in berthing areas and local access channels serving the terminals commensurate with depths provided in the related project areas; establish regulations prohibiting discharge of pollutants into waters of the channel by users thereof; prohibit erection of any structure within 100 feet of project channel as authorized at time of construction; provide and maintain public terminal and transfer facilities; contribute 50 percent of total first costs of recreational jetty fishing facility; and operate and maintain jetty fishing facility. Assurances of local cooperation for the 1974 authorization have been furnished by the local sponsor. Terminal facilities. There are 22 commercial waterfront facilities serving the port. The General Cargo Facilities include 13,807 feet of usable berthing space, 7 transit sheds with a total capacity of 393,870 square feet, and 6 container yards with space for 3,965 containers. Oil Handling Facilities consist of 232 storage tanks with a total storage capacity of 9,564, 800 barrels. There is no usable berthing space located at the Oil Handling Facilities. Dry storage is available at 225,000 square feet, cold storage at 2,098,000 cubic feet and open storage at 100.3 acres. Hoisting facilities available from a local firm include 5 cranes with capacities from 20 to 155 tons. No floating cranes or derricks for heavy lifts are available at the port. There are 2 marine repair yards. Drydock facilities include 2 drydocks with capacities of 2,200 and 3,200 tons and a 4,270-ton vertical boat lift. Three tugs with ratings up to 4,290 horsepower serve the port. The Port Everglades Belt Line connects with the Seaboard Coast Line railroad to serve the port. Facilities are considered adequate for existing commerce. (See Port Series #16, Rev. 1982,) Operations and results during fiscal year. New work: Dredging channel at Pier 7 was constructed at a cost of $239,675. Dredging for Section 2 was performed by contract at a cost of $3,742,490. Recreation facilities were constructed at a cost of $134,267. Engineering and design and supervision and administration costs were -$27,969 and $77,462, respectively. Maintenance: Maintenance of breakwaters cost $153,519. Condition and operation studies cost $21,704. Supervision and administration costs were $1,848. Condition at end of fiscal year. Work required to complete the project is construction authorized in House Document 144/93/1. 28. REMOVAL OF AQUATIC GROWTH FROM NAVIGABLE WATERS IN THE STATE OF FLORIDA. Location Water hyacinth, hydrilla and water lettuce are found in freshwater streams and lakes in various parts of the district. 9-13 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Existing project. The authorized project provides for destruction or removal of aquatic growth in navigable waters of the State so far as they constitute an obstruction to navigation and commerce, using any mechanical, chemical or other means not injurious to cattle, and use of log booms to close sloughs and backwaters as an auxiliary means. No estimate of the final cost of work has been made (See Table 9-B for Authorizing Legislation.) For further details, see 1962 Annual Report. Local cooperation. None required. Operations and results during fiscal year. Maintenance: Operations continued during the year. (See Table 9-B for Authorizing Legislation.) (See Table 9-G for spraying operations.) Condition at end of fiscal year. The project is for maintenance of navigable waterways. During the year 24,655 acres of floating vegetation (water hyacinths and/or water lettuce), 2,926 acres of hydrilla and 1,640 acres of minor plants were controlled in approximately 2,200 miles of waterways. Hyacinths in Lake Okeechobee and in St. Johns River Watershed are under maintenance control. 29. ST. AUGUSTINE HARBOR FLA. Location The harbor is on the east coast of Florida, about 35 miles south of the entrance to St. Johns River and about 180 miles north of Fort Pierce Harbor. (See Coast and Geodetic Survey Charts Nos. 1243 and 1244.) Previous project For details see page 412 of Annual Report for 1958. Existing project. The authorized project provides for a channel 16 feet by 200 feet along the best natural alinement as may exist from time to time across the new inlet bar, thence 12 feet deep to the Intracoastal Waterway;, a sandtrap groin on the north side of the inlet extending seaward from the shore of Vilano Beach, and a sand-tight jetty on the south side of the channel extending seaward from the shore of Conch Island parallel to and coextensive with the groin, future landward extension of the groin and jetty; and a channel 10 by 100 feet in San Sebastian River from the Intracoastal Waterway to King Street Bridge, with a turning basin near the upper end. Length of the inlet channel is about 1.5 miles, and length of the San Sebastian River channel is about 2.6 miles. Plane of reference is mean low water. The mean tidal range is 4.5 feet in the ocean at St. Augustine Inlet and 4.2 feet at the city waterfront. Strong northerly winds, mostly in the winter, lower the water surface about 1 foot. (See Table 9-B for Authorizing Legislation.) Local cooperation. Fully complied with to date Non-Federal contribution for new work amounted to $137,500. Terminal facilities. There are several timber docks on the Matanzas waterfront of St. Augustine In this area of the harbor is a concrete dock which serves as a municipal yacht pier. It has fuel facilities, 19 slips and accommodates boats up to 60 ft. in length. A large public boat ramp is also available The principal terminals are the numerous shrimp docks in the San Sebastian River which flows southward through the city into the Matanzas River south of the bridge; these consist of timber wharves, with frame and corrugated iron warehouses thereon, and 9 marine railways for small boats. There is also a marine supply facility and several boat yards. The present terminals have highway connections and several of the shrimp docks have rail connections. They are considered adequate for existing commerce and recreational craft. Operations and results during fiscal year. Maintenance: Condition and operation studies cost $18,325. Engineering and design and supervision and administration costs were $56,131 and $536, respectively. Condition at end of fiscal year. Project is completed except for the North Jetty which is in a deferred status. The groin is in good condition except for the 300 feet which has subsided to about elevation 3.0 feet, mean low water. The jetty is in good condition, but is submerged at high tide. Total Federal costs under the existing project through September 30, 1985 were $1,405,131 for new work and $4,326,335 for maintenance, a total of $5,731,466. 30. ST. JOHN'S RIVER, FLA., JACKSONVILLE TO LAKE HARNEY Location. Rises in marshes of Brevard County, Fla., near east coast, and flows northwesterly to Jacksonville, thence easterly into the Atlantic Ocean, 122 miles south of Savannah River. River is about 285 miles long, of which 161.5 miles are included in project. (See U.S. Coast and Geodetic Survey Charts Nos. 685-688.) Previous projects. Adopted by River and Harbor Acts of June 14, 1880 and July 5, 1884. For further details see Annual Reports for 1915 and 1938. Existing project. Channel 13 feet deep and 200 feet wide from Florida East Coast Railway bridge at Jacksonville to Palatka, thence 12 by 100 feet to Sanford, and thence 5 by 100 feet to Lake Harney, with side channel to Enterprise and maintenance of two jetties. Existing project was authorized by River and Harbor Acts of March 2, 1945 (H. Doc. 445, 78th Cong., 2d sess.) and July 24, 1946 (S. Doc. 208, 79th Cong., 2d sess.). For further details see Annual Report for 1962. Terminal facilities. There are 36 piers and wharves along project, including municipal piers and wharves 9-14 JACKSONVILLE, FLA. DISTRICT at Green Cove Springs and Palatka, 12 Navy piers at Green Cove Springs, a municipal recreational pier at Sanford, and 19 privately owned piers, 5 of which have nearby tank storage facilities for petroleum projects. Facilities are considered adequate for existing commerce. Operations and results during fiscal year. Maintenance: Condition and operation studies cost $4,479. Removal of sunken vessel cost $91. Maintenance of breakwater cost $310,618. Engineering and design and supervision and administration costs were $148 and $2,652, respectively. Condition at end of fiscal year. Active portion is complete. Condition of project as a whole is adequate for present needs of navigation. (For more detailed information refer to Annual Report for F.Y. 1963). 31. ST. LUCIE INLET, FLA. Location. The inlet is on the east coast of Florida about 19 miles south of the entrance to Fort Pierce Harbor, Florida, and 100 miles north of the entrance to Miami Harbor, Florida. (See Coast and Geodetic Survey Chart No. 1247.) Previous project. For details see page 764 of Annual Report for 1949. Existing project. The authorized project provides for extending the north jetty about 500 feet and modifying existing jetty to provide a sand bypass weir section about 500 feet long;, excavation of a sand impoundment basin adjacent to the bypass weir in the north jetty; construction of a south jetty consisting of a rubblemound structure about 2,400 feet long with a walkway for recreational fishing;, channel between existing bar cut and the Intracoastal Waterway 10 by 500 feet through the bar cut, tapering to 150 feet through the inlet, and 100 feet wide and 7 feet deep to the Intracoastal Waterway; and transfer of 380,000 cubic yards of material to the south beach during each two year maintenance period. Plane of reference is mean low water. Total project length is about 1.9 miles. Mean tidal range is 2.6 feet on the ocean side and about 1 foot on the land side of the inlet. The estimated cost of the 1974 modification (Oct. 1979 price levels) to the project is $6,290,000 Federal cost and $2,525,000 non-Federal cost ($2,260,000 contributed funds and $265,000 other costs). (See Table 9-B for Authorizing Legislation.) Local cooperation. Local interests must: contribute 19.9 percent of construction cost allocated to navigation in the combined project, 23.2 percent allocated to beach erosion, and 50 percent of construction cost of jetty fishing walkway; provide 39.8 percent of the annual maintenance cost allocated to navigation and 23.2 percent of the annual costs for maintenance dredging allocated to beach erosion control for periodic beach nourishment and 100 percent of the annual jetty maintenance costs allocated to beach erosion control; maintain jetty fishing walkway; agree that each five years the amount of local cost sharing for maintenance is to be adjusted; provide all lands, easements, and rights-of-way; hold United States free from damages; provide marina with mooring facilities and utilities; provide and maintain depths in berthing area and local access and feeder channels commensurate with the depths provided in the project; accomplish such alterations as required in sewer, water supply, drainage, and other utility facilities, and take action to place in effect statutes and/or regulations which will protect the water quality for the authorized uses of the project. Assurances of local cooperation for the 1974 modification were signed by the local sponsor on August 24, 1978. Terminal facilities. A municipal pier provides facilities for docking and servicing charter fishing and small recreational craft. At Stuart there is a dock for handling bulk petroleum products and several marinas which provide facilities for mooring, servicing and minor repair of small craft. Facilities are considered adequate for existing commerce. Operations and results during fiscal year. New work: A dredging and jetty construction contract underway at a cost of $290,254. Engineering and design and supervision and administration costs were $64,950 and $27,873, respectively. Maintenance: Condition and operation studies cost $12,319. Engineering and design and supervision and administration costs were - $29,015 and $44,617, respectively. Condition at end of fiscal year. Work required to complete the project is construction authorized in House Document 294/93/1. Total Federal costs under existing project through September 30, 1985 were $10,813,497 for new work (including $3,011,854 contributed funds) and $4,646,641, for maintenance, a total of $15,460,138. 32. SAN JUAN HARBOR, P. R. Location. San Juan Harbor is on the north coast of Puerto Rico about 35 miles from the island's east end and 1100 miles southeast of Miami, Florida. (See Coast and Geodetic Survey Chart No. 908.) Previous projects. For details see Annual Reports for 1915, 1916, 1938. Existing project. Provides for a bar channel 48 by 800 feet, shifting the centerline 350 feet west; deepening Anegado Channel in steps from 46 to 40 feet while reducing its width to 800 feet; deepening Army 'brminal Channel and turning basin to 40 feet while widening the channel to 450 feet; deepening Puerto Nuevo Channel to 40 feet and widening it to 400 feet; deepening Graving Dock Channel to 40 feet at existing 400 foot width; an advance maintenance area 500 feet wide, 1,200 feet long and 44 feet deep 9-15 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 at the mouth of Cano de Martin Pena.; deepening San Antonio Channel to 38 feet at varying widths, minimum of 500 feet; deepening cruise ship basin to 36 feet at an irregular width; maintaining Sabana Approach Channel at 30 by 250 feet; provide a 38-foot depth in Anchorage Area "E" with irregular width and six mooring dolphins for vessels using the area. Mean tidal range is 1.1 feet. (See Table 9-B for Authorizing Legislation.) Local cooperation. Should provide all lands, easements and rights-of-way; hold the United States free from any damages; provide and maintain depths in berthing areas and local access and feeder channels; provide alterations as required in sewer water supply, and other utility facilities. It is further recommended that local interests be reimbursed for work performed by them on the project subsequent to project authorization. Local interests have complied with authorization requirements to date. There was no non-Federal contribution required. Terminal facilities. There are 28 piers and bulkhead wharves in the harbor capable of docking deep-draft vessels, which have an aggregate berthing length of about 23,700 feet. Eleven piers and bulkhead wharves are on the north shore, two piers and a three-level ramp facility for roll-on/roll-off operations at Front Graving Dock turning basin and channel, nine at the eastern side and three at the western side of the Army Trminal basin and channel, and three on the south shore of San Antonio Channel. One pier and bulkhead wharf are privately owned, seven are U.S. Government property, and 24 owned by the Commonwealth of Puerto Rico. Twenty piers and wharves are equipped with mechanical crane transfer facilities. Five wharves are equipped with a special crane for the handling of loaded containers. Twenty-four are open to general public. Pier No. 6 has been repaired and improved in 1985. There is an aggregate length of about 1,339 feet of berthing space at Catano Point used principally by small vessels within the 18-foot draft range This space is also open to the public. In addition, there are 10 piers and bulkhead wharves with approximately 6,910 feet of berthing space owned and operated by different agencies of the Federal Government. This space is not open to the public. Facilities are considered adequate for existing commerce Operations and results during fiscal year. Maintenance: Maintenance of breakwaters cost $3,723. Engineering and design and supervision and administration costs were $143,871 and $2,578, respectively. Condition at end of fiscal year. Remaining work to complete project is modification authorized in 1976. Total Federal costs under the existing project through September 30, 1985 were $13,027,284 for new work and $11,919,793 for maintenance, a total of $24,947,077 regular funds. In addition, $747,684 was expended for new work and $44,730 for maintenance from public works funds and $100,000 for new work from contributed funds. Existing project includes the entrance channel and turning basin to Army Terminal which cost $1,543,712; this expenditure was made from military appropriations and is not included in above costs. 33. TAMPA HARBOR, FLA. Location. Tampa Harbor is in a large natural indentation of the Gulf of Mexico about midway of the west coast of Florida. The entrance is about 220 miles north of Key West and about 330 miles southeast of Pensacola. (See Coast and Geodetic Survey Charts Nos. 586, 587, and 1257.) Previous projects. For details see page 665 of 1938 Annual Report. Existing project. The authorized project provides for a channel from the Gulf of Mexico to Port Sutton and Tampa; 46 by 700 feet from the Gulf of Mexico to Mullet Key; 44 by 600 feet in Mullet Key Cut Channel; 44 by 500 feet in Tampa Bay from Mullet Key Cut to Hillsborough Bay and Port Tampa Channels; 44 by 500 feet in Hillsborough Bay from junction with Tampa Bay and Port Tampa Channels to the junction with Port Sutton entrance channel, thence 42 by 400 feet to the junction with Seddon and Garrison Channels; 44 by 400 feet in Port Sutton entrance channel; 42 by 400 feet in Sparkman Channel; 40 by 300 feet in Ybor Channel; 42 by 400 feet in Port Tampa Channel; 44 by 400-500 feet in East Bay entrance channel; 44 by 300 feet in East Bay approach channel; 30 by 300 feet in Seddon and Garrison Channels; 30 by 200 feet in Alfia River; 9 by 100 feet in Hillsborough River to a point 2,000 feet above Columbus River bridge; a breakwater; turning basins at Port Sutton, Ybor Channel, Port Tampa, East Bay, mouth of Hillsborough River, and in Alafia River, and maintenance of a channel 12 by 200 feet in Hillsborough River, 44 by 200 feet in Port Sutton terminal channel, and 34 x 300 in East Bay Channel. (The 46-foot and 44-foot depth portions of the project include a 5-foot underkeel clearance Special studies on the project concluded that a 4-foot underkeel is sufficient. Therefore, a 1-foot overdepth has been placed in an inactive status, resulting in active project depths of 45 and 43 feet, respectively.) Plane of reference is mean low water. The project is about 67 miles long, including 10 miles in Hillsborough River and 3.6 miles in Alafia River. Mean range of tide is 1.3 feet at the lower end of the bay, 1.6 feet at Port Tampa, and 1.8 feet at Tampa. Extreme range is about 3.8 feet at the lower end of the bay and 4.8 feet at Tampa. Strong south- 9-16 JACKSONVILLE, FLA. DISTRICT westerly winds raise the water level about 1.5 feet. Strong northerly winds, which usually occur in the winter, lower the water level about 2 feet. Estimated cost of new work (Oct. 1984 price levels) of the 1970 modification to the project is $230,570,000. Federal ($222,700,000 Corps and $2,117,000 U.S. Coast Guard) cost and $5,753,000 non-Federal cost ($1,400,000 contributed funds and $4,353,000 other costs). (See Table 9-B for Authorizing Legislation.) For further details, see 1962 Annual Report. Local cooperation. Local cooperation has been fully complied with for work completed to date. See 1978 Annual Report for requirements for work authorized by the River and Harbor Act of 1970, HD 401/91/2 and HD 150/91/1. Assurances of local cooperation for the 1970 authorization were approved by the Secretary of the Army on January 10, 1973. Terminal facilities. There are 102 commercial waterfront facilities serving Tampa Harbor. The General Cargo Facilities consist of 7,226 feet of usable berthing space and 15 transit sheds with a total of 585,200 square feet of shed storage space. The Oil Handling Facilities include 16,440 feet of usable berthing space and 316 storage tanks for a total capacity of 11,610,350 barrels. Dry storage is available at 1,904,750 square feet, cold storage at 14,309,000 cubic feet, and open storage at 59.4 acres. There are 2 wharves available for coal storage at 750,000 tons total storage and grain elevators with a 3,400,000 bushel total capacity. One elevator on Ybor Channel is a 1,000,000 bushel capacity. Hoisting Facilities include 13 cranes, fixed and mobile; with capacities from 45 to 150 tons and other crawler and mobile craces available locally. Marine repair yards include 9 waterfront repair facilities and numerous other offwater companies engaged in various phases or marine repair. There are 4 floating and 4 graving docks available at the port with capacities ranging from 548 to 5,400 long tons. Floating equipment includes 24 tugs with up to 3,350 horsepower and 4 companies with tank barges of capacities up to 14,000 barrels. The Seaboard System Railroad serves the port. Facilities are considered adequate for existing commerce. (See Port Series #17 revised 1979.) Operations and results during fiscal year. New work: Charge off cost on purchased transponder for offshore disposal positioning -$8,566. Construction of the 43-foot project from Mangrove Point to Alafia River completed at a cost of $2,906,136. Contract for Tampa Bay Egmont and Mullet Key completed at a cost of -$673,801. Construction of 43-foot project cuts C, D, and E and Section 2C (Part) completed at a cost of $16,245,450. Engineering and design and supervision and administration costs were $263,215 and $217,497, respectively. Maintenance: Condition and operation studies cost $91,746. Engineering and design costs were $73,697. Condition at end of fiscal year. Work authorized by the River and Harbor Act of 1970 (HD 401/91/2 is 60 percent complete.) Tbtal Federal costs under the existing project through September 30, 1985 were: Main project: $193,264,619 for new work and $18,938,664 for maintenance, a total of $212,203,283 regular funds. In addition, $853,050 was expended for new work from public works funds, $1,463,000 from emergency relief funds, and $1,017,637 from contributed funds. On Hillsborough River $270,466 was expended for new work. 34. NAVIGATION PROJECTS ON WHICH RECONNAISSANCE AND CONDITION SURVEYS ONLY WERE CONDUCTED DURING PERIOD. (See Table 9-H.) 35. OTHER AUTHORIZED NAVIGATION PROJECTS (See Table 9-I.) 36. NAVIGATION WORK UNDER SPECIAL AUTHORIZATION Navigation Activities Pursuant to Section 107, Public Law 86-645 (Preauthorization) Fiscal year costs for Aguadilla Harbor, PR, $54,210; Benner Bay - Mangrove Lagoon, V.I., $44,111; Blount Island, Florida, $43,961; Cedar Island-Keaton Beach Channel, Florida, $3,587; North Lake Channel, Hollywood, Florida, $16,676; Pahokee Harbor, Florida, $92; Pasco County, Small Boat Channel, Florida, $1,810; and Rockhous Creek, Florida $40,179. Snagging and clearing for navigation (Sec. 3 of 1945 River and Harbor Act, Public Law 14, 79th Congress.) No costs incurred. Beach Erosion Control 37. BREVARD COUNTY, FLA. Location. The project is on the east coast of Florida at approximately the midpoint of the peninsula. (See Coast and Geodetic Survey Charts Nos. 1245 and 1246.) Existing project The authorization provides for a protective and recreational beach with a berm 50 feet wide at elevation 10 feet above mean low water and a natural seaward slope as would be shaped by wave action, along 14,600 feet of beach at the city of Cape Canaveral and 10,600 feet of beach at Indialantic and 9-17 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Melbourne beach, and for periodic nourishment of the restored beach at Indialantic and Melbourne Beach limited initially to a period of 10 years. Nourishment of the restored beach at the city of Cape Canaveral would be provided by the authorized sand-transfer plant for construction at Canaveral Harbor. The project also provides for improvement of the Federally owned shores for beach erosion control or hurricane protection to be accomplished by the Federal agencies involved, subject to their own determination of economic justification. The areas involved include 4.9 miles of shore at Kennedy Space Center, 4.0 miles at Cape Kennedy Air Force Station, and 2.3 miles at Patrick Air Force Base. Mean tidal range in the area is 3.5 feet. Estimated cost of the project (Oct. 1984 price levels) is $8,220,000 Federal costs and $8,315,000 non-Federal cost ($8,220,000 cash contribution and $95,000 for lands). (See Table 9-B for Authorizing Legislation.) Local cooperation. Local interests must contribute 50 percent of all first costs of the work and 50 percent of the nourishment cost at Indialantic and Melbourne Beach for the first 10 years of the project life; provide lands and rights-of-way; provide, after the first 10 years of project life, periodic nourishment of the restored beach at Indialantic and Melbourne Beach during project life; maintain continued public ownership of the shore upon which the amount of Federal participation is based; control water pollution; and hold the United States free from damages. Assurances of local cooperation were approved by the Secretary of the Army on July 9, 1973. Operations and results during fiscal year. New work: Engineering and design cost $16,148. Condition at end of fiscal year. Initial beach fill has been provided at Indialantic and Melbourne beaches. 38. BROWARD COUNTY, FLA. BEACH EROSION CONTROL AND HILLSBORO INLET, FLA., NAVIGATION PROJECT Location. Broward County is on lower east coast of Florida, 300 miles south of Jacksonville and about 30 miles north of Miami. Hillsboro Inlet is in northern part of Broward County. (See Coast and Geodetic Survey Chart No. 1248.) Existing project. The authorization provides for Federal participation toward cost of a shore restoration and protection project and a project to provide and maintain a channel adequate for small craft navigation. Plan provides for restoration of a protective and recreational beach at four locations generally 100 feet wide with berm elevation of 10 feet above mean low water, a navigation channel 8 by 100 feet from the Intracoastal Waterway to a point 1,500 feet oceanward in Hillsboro Inlet, thence 10 by 150 feet in the ocean; jetties on north and south sides of ocean entrance; a permanently based floating dredge; and on a deferred basis, a trestle-mounted sand-transfer plant, if needed. Navigation portion of the project is in an inactive status. Mean range of tide in areas is 2.5 feet. Plane of reference is mean low water. Cost estimate for new work (Oct. 1984 price levels) is $13,800,000 Federal and $20,100,000 non-Federal contribution. (See Table 9-B for Authorizing Legislation.) Local cooperation. Local interests must contribute 90.5 percent of the first cost of beach restoration in the reach between north county line and Hillsboro Inlet, 90 percent of first cost allocated to beach restoration, and 50 percent of first cost allocated to navigation for reach between Hillsboro Inlet and Port Everglades and 72.4 percent of beach restoration in reach between Port Everglades and south county line; provide all lands and rights-of-way; obtain approval of Chief of Engineers of plans and specifications if local interests construct beach erosion features; and furnish assurances that they will hold the United States free from damages, provide and maintain adequate public landing or wharf at Hillsboro Inlet, establish a public body to cooperate financially and to provide and operate local facilities for navigation, control water pollution, maintain ownership of publicly owned shores, and maintain all project works except the jetties (maintenance of the channel to revert to the United States if sandtransfer plant is constructed). Assurances of local cooperation were accepted November 22, 1968. Operations and results during fiscal year. None. Condition at end of fiscal year. Project was constructed by local interests and is complete. 39. DADE COUNTY, FLA. Location. Dade County is on the southeast coast of Florida. Project area consists of that part of the Atlantic shoreline of the county from Government Cut north to Bakers Haulover Inlet and at Haulover Beach Park. (See Coast and Geodetic Survey chart No. 1248.) Existing project. Project provides for a protective and recreational beach having a dune at elevation 11.5 feet and a level berm 50 feet wide at elevation 9 feet, mean low water, for beach erosion control and hurricane protection between Government Cut and Bakers Haulover Inlet; a protective and recreational beach with a berm elevation of 9 feet for beach erosion control at Haulover Beach Park; and Federal participation in the initial construction and in periodic nourishment of both the above reaches for the first 10 years of project life. Plane of reference is mean low water. Mean range of tide in the area is 2.5 feet. Estimated cost of the project (Oct. 1984 price levels) is $48,200,000 Federal cost and $41,086,000 non-Federal cost ($39,200,000 cash contribution and $1,886,000 other costs). 9-18 JACKSONVILLE, FLA. DISTRICT Project was authorized by Flood Control Act of 1968 (HD 335/90/2). Local cooperation. Local interests must (a) contribute for the first cost of the work: between Government Cut and Bakers Haulover Inlet amounts ranging from 60.2 percent of the cost of the fill within the project limit with existing shorefront ownership, and 100 percent of the cost of fill required landward of the project limit; and for the work at Haulover Beach Park, contribute 21.3 percent of the entire first cost excluding costs for lands, easements, rightsof- way, relocations, and preproject work, but including credit for preproject work; (b) contribute in cost for the first 10 years of project life, amounts ranging from 88.9 percent of the nourishment cost for the beach, with existing ownership, to 60.7 percent with public ownership, and the entire maintenance cost for the dune, all between Government Cut and Bakers Haulover Inlet; (c) provide all lands and rights-of-way; (d) hold United States free from damages; (e) assure continued public ownership and use of the shore upon which the amount of Federal participation is based; (f) assure maintenance of the groin, and after the first 10 years of project life, periodic nourishment of the protective beach and maintenance of the dune during the economic life of the project; (g) assure that water pollution will not be permitted; (h) prevent removal or relocation by man of fill from the beach berm and dune; (i) prevent the erection of barriers to the littoral movement of material that would interfere with the nourishment of the beach; (j) maintain at the parks qualifying for 70 percent Federal participation a zone that excludes permanent human habitation; (k) at least annually inform interests affected that the project will not provide complete protection from a hurricane tide level equal to or higher in elevation than that of the hurricane of September 1926; and (1) establish in public ownership for public use the beaches within project limits as a requirement for Federal participation in the allocated beach erosion control costs of improvement of shores presently in private ownership. Assurances of localcooperation were accepted January 16, 1973. A supplemental agreement for Bal Harbour portion was approved 30 June 1976. Operations and results during fiscal year. New work: A contract for Jetty Rehabilitation and Extension continued at a cost of $100,000. Engineering and design and supervision and administration costs were $172,260 and $40,337, respectively. 40. DADE COUNTY, NORTH OF HAULOVER BEACH, FLA. Location. On the southeast coast of Florida. Project area consists of that part of the Atlantic shoreline extending 2.5 miles north of Haulover Beach Park. (see Coast and Geodetic Survey Chart No. 1248.) Existing project. The existing shore protection project for Dade County provides for Federal participation in the cost of construction of a beach fill for the purpose of erosion control and hurricane protection along 9.3 miles of shore between Government Cut and Bakers Haulover Inlet and for the construction of a beach fill for the purpose of erosion control along the 1.2 miles of shore fronting Haulover Beach Park and provides for protection and nourishment of 2.5 miles of beach shore north of Haulover Beach Park and for extension of the period of Federal participation in the nourishment of the existing project from 10 years to the life of the project. Cost estimate for new work (Oct. 1983 price levels) was $6,900,000 Federal and $7,500,000 non-Federal cash contribution and $96,000 other costs. (See Table 9-B for Authorizing Legislation.) Local cooperation. Consistant with the costsharing and financing concepts agreed to by the administration and the Senate Majority Leadership, local interests will be required to provide lands, easements and rights-of-way and relocations, pay 50% of the separable and joint costs allocated to recreation, pay 35% of the cost allocated to storm damage prevention, hold the United States free from damages, control water pollution and furnish assurances that they will maintain continued public ownership of the shore upon which the amount of Federal participation is based during economic life of project. Assurances of local cooperation have been requested from local sponsors. Operations and results during fiscal year. None. Condition at end of fiscal year. Continuation of planning and engineering. 41. DUVAL COUNTY, FLA. Location. On upper east coast of Florida, within 20 miles of Florida-Georgia line. Ocean shoreline is about 16 miles long. (See Coast and Geodetic Survey Chart No. 1243.) Existing project. Provides for Federal participation toward cost of constructing with artificial fill, a beach 60 feet wide at elevation 11 feet above mean low water with a natural slope seaward, and for periodic nourishment for 10 years. Federal participation to be 100 percent of the first cost of construction applicable to the Federal shore and 50 percent applicable to the other publicly owned shore and 55.5 percent of periodic nourishment cost for first 10 years of project life Mean tidal range at south jetty in St. Johns River is 4.9 feet Estimated cost of new work (Oct. 1984 price levels) $13,600,000 Federal and $12,024,000 non-Federal ($9,690,000 contributed funds and $2,334,000 for other costs). Project was authorized by River and Harbor Act of 1965 (HD 273/89/1). 9-19 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Local cooperation Local interests must contribute 50 percent of first cost of constructing non-Federal publicly owned shores; contribute 44.5 percent of periodic nourishment costs for first 10 years of project life; provide all lands, rights-of-way, and relocations; hold the United States free from damages; control water pollution; and furnish assurances that they will maintain continued public ownership of the shore upon which the amount of Federal participation is based during economic life of project. Assurances of local cooperation were accepted on November 29, 1973. Operations and results during fiscal year. New work: A contract for beach nourishment continued at a cost of $1,673,680. Engineering and design and supervision and administration costs were $154,530 and $194,434, respectively. Condition at end of fiscal year. Initial beach fill and four year advance nourishment has been completed. 42. EL TUQUE BEACH, P.R. Location The project area is located at El Thque Beach on the south coast of Puerto Rico about 5 miles west of the city of Ponce. Existing project. The authorization provides for a protective and recreational beach by the placement of about 60,000 cubic yards of fill material along the eroded shoreline of El1 Tque Beach. The new fill will be stabilized by the construction of a shore-connected rubble breakwater at the south end of the beach fill and by an offshore breakwater parallel to the northerly section of shore under consideration. The shore-connected breakwater would extend seaward a distance of about 900 feet from a point on the shore 300 feet north of the south-west corner of the park. The offshore breakwater would be located about 500 feet offshore, be 1,000 feet in length, and run generally parallel to the northwestern shore. Estimated cost of the project (Jul. 1981 price level) is $968,800 Federal costs and $415,200 non-Federal constribution. (See Table 9-B for Authorizing Legislation.) Local cooperation. Local interests must (a) provide without cost to the United States all necessary lands, easements, rights of way, and relocations required for construction and subsequent mainenance of the project. (b) Hold and save the United States free from all claims for damanges which may result from construction and subsequent mainenance of the project, except damages due to the fault or negligence of the United States or its contractors. (c) Provide without cost to the United States appropriate access and facilities including parking and sanitation, necessary for realization of the public benefits upon which Federal participation is based, and administer and maintain the beach for continued public use during the economic life of the project. (d) Assume maintenance and repair during the economic life of the project as required to serve the intended purpose. (e) Provide a cash contribution for beach erosion control equal to the appropriate percentage of the final construction cost allocated. This function exclusive of lands, easements, rights-of-way, alterations, and relocations. The percentage to be in accordance with existing law and based on shore ownership and existing at the time of construction, which contribution is presently estimated at 30 percent. (f) Assume full responsibility for all project costs in excess of the Federal cost limitations of $1,000,000 for the Corps of Engineers portion of the work. (g) Comply with the provisons of the Uniform Relocation Assistance and Real Property Acquisition Policies Act of 1970 (Public Law 91-646). Operations and results during fiscal year. New work: Contract for beach restoration, groin and breakwater was completed. Costs were $1,361. Engineering and design and supervision and administration costs for the year were $-4,843 and -$2,075, respectively. 43. FORT PIERCE, FLA. Location. Fort Pierce Beach erosion project fronts the Atlantic Ocean and is on coastal barrier island in St. Lucie County which separates Indian River from the ocean. Area is 120 miles north of Miami and about 225 miles south of Jacksonville. (See Coast and Geodetic Survey Chart 582.) Existing project. Provides for Federal participation in the cost of a shore restoration and protection project which involves construction and periodic nourishment for 10 years. Federal participation amounts to one-half such costs for that part of the ocean shoreline extending 1.2 miles southward of Fort Pierce navigation inlet, and 70 percent of such costs for the adjacent 0.1 mile shoreline known as Lions Club Beach Park. Mean range of tide in area is 2.6 feet. Cost estimate (Oct. 1984 price levels) is $3,370,000 Federal and $3,150,000 non-Federal. Project was authorized by 1965 River and Harbor Act (HD 84/89/1) as modified by section 102 of 1968 River and Harbor Act. (See Table 9-B for Authorizing Legislation.) Local cooperation. Local interests must contribute one-half the costs of protecting and periodically nourishing for 10 years the reach of shoreline starting at and extending 1.2 miles south of Fort Pierce Inlet and 30 percent of cost of protecting and periodically nourishing 0.1 mile of shoreline known as Lions Club Beach Park; obtain approval by Chief of Engineers of detailed plans and specifications for the project; establish in public ownership and beach within project limits prior to reimbursement; furnish all lands and rights-of-way; furnish assurances that they will maintain continued public ownership of the publicly owned shores; exclude permanent human habitation and provide full park facilities at the Lions Club Beach Park; provide periodic nourishment of 9-20 JACKSONVILLE, FLA. DISTRICT the beach; control water pollution; hold United States free from damages; and execute such further assurances and agreements as may be necessary to carry out the intent of Congress expressed in the acts authorizing or modifying the project. River and Harbor Act of 1965 authorized construction of the project by local interests. Section 102 of 1968 River and Harbor Act modified the project to provide for construction by Secretary of Army and section 215 of the same act permitted construction by local interests. Local interests have elected to construct the project. Assurances of local cooperation were accepted January 2, 1969. Operations and results during fiscal year. None. Condition at end of fiscal year. Initial beach nourishment has been completed. 44. PALM BEACH COUNTY, FLA., FROM MARTIN COUNTY LINE OF LAKE WORTH INLET AND FROM SOUTH LAKE WORTH INLET TO BROWARD COUNTY LINE. Location Palm Beach County is on east coast of Florida about 300 miles south of Jacksonville and 70 miles north of Miami. Northerly reach of the project is separated from the southerly reach by Palm Beach Island. Project consists of about 12.2 miles of ocean coastline. (See Coast and Geodetic Survey Charts 1247 and 1248.) Existing project. Provides for Federal participation toward the cost of local shore project for restoration of beaches to a general width of 100 feet with a berm elevation of 10 feet above mean low water, and periodic nourishment for 10 years from the year of initial nourishment, as follows: 4.8 percent of the cost for the Martin County line-Jupiter Inlet segment; 11.6 percent of cost for Jupiter Inlet-Lake Worth Inlet segment; and 5.1 percent for South Lake Worth Inlet-Boca Raton Inlet segment. Mean range of tide is 2.8 feet in the Atlantic Ocean at Palm Beach and 2.3 feet at Boca Raton Inlet. Estimated cost (Oct. 1984 price levels) is $7,300,000 Federal and $21,100,000 cash contribution. (See Table 9-B for Authorizing Legislation.) Local cooperation. Local interests must obtain approval by Chief of Engineers of plans and specifications prior to commencement of work and furnish assurances that they will maintain public ownership of publicly owned shores, maintain protective measures and provide periodic nourishment of protective beaches, and control water pollution. Operations and results during fiscal year. New work: Reimbursement of beach replenishment contract was $1,831,342. Engineering and design costs were $52,692. Condition at end of fiscal year. Local interests provided initial beach fill at Delray Beach which was completed in August 1973. A periodic nourishment contract at Delray Beach was awarded in FY1978 by local interests and the contract has been completed. 45. PINELLAS COUNTY, FLA. Location. Pinellas County is on the Gulf coast of Florida, about midway of the peninsula. It extends northerly about 39 miles from the main entrance to Tampa Bay to the vicinity of the mouth of Anclote river. (See Coast and Geodetic Charts Nos. 858 and 1257.) Previous project. For details see page 429 of Annual Report for 1965. Existing project. The authorized project provides for Federal participation in preserving and protecting the shores of Pinellas County, Florida, by: restoration of 5,000 feet of beach at Clearwater Beach Island; restoration of 49,000 feet of beach at Sand Key; restoration of 9,200 feet of beach at Treasure Island; construction of 600 feet of revetment at Long Key; and advance nourishment of Long Key and periodic nourishment of each island. Estimated cost (Oct. 1984 price levels) is $17,700,000 Federal funds and $19,162,000 non-Federal funds ($19,100,000 contributed funds and $62,000,000 other costs). (See Table 9-B for Authorizing Legislation.) Local cooperation. Local interests must: (a) contribute in cash the required percentages of the first costs of work provided by the Corps of Engineers, the percentages varying with the type of beach ownership; 94.1 to 50 percent of the beach restoration at Clearwater Beach; 98.1 to 50 percent of the improvement at Sand Key; 94.3 to 50 percent of the improvement at Treasure Island; and 50 percent of the first cost of the revetment at Long Key; (b) contribute in cash an amount computed in accordance with the cost sharing provision contained in P.L. 826, 84th Congress as amended by P.L. 87-874, for beach nourishment cost for the first 10 years of the project life; (c) provide lands, easements, and rights-ofway; (d) assure maintenance and repair of the stone revetment of Long Key; (e) assure periodic nourishment of the restored beaches; (f) assure public ownership of beaches; (g) assure against water pollution; (h) hold the United States free from damages; and (i) provide beach for public use. Assurances of local cooperation were accepted March 22, 1967. Operations and results during fiscal year. New work: Contract for Redington shore breakwater and groin cost $100,000. Completed contract for the rehabilitation of the Pass-A-Grille Groin cost $-28,329. Engineering and design and supervision and administration costs for the fiscal year were $290,860 and $4,181, respectively. Condition at end of fiscal year. Construction of the project commenced in 1969 and is 25 percent com- 9-21 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 pleted. Total costs under existing project through September 30, 1985 were $2,671,225 Federal funds and $2,198,056 contributed funds for new work and $5,625 for maintenance 46. OTHER AUTHORIZED BEACH EROSION CONTROL PROJECTS (See Table 9-J.) 47. BEACH EROSION CONTROL ACTIVITIES UNDER SPECIAL AUTHORIZATION Beach erosion control activities pursuant to section 103, Public Law 87-874 (preauthorization) Reports incurring costs during the fiscal year were Boca de Congrejos, P.R., $20,919; Dorado Public Beach, P.R., $28,361; Dunedin Shores, Florida, $27,246; E. G. Simmons Park, Hillsborough Co., Florida, $193; Fort Clinch State Park, Florida, $41,820; Guanica Public Beach, P.R., $16,101; Isla de Cabras, P.R., $19,307; Key Biscayne, Fla., $67,912; and Puerto Nuevo Beach, P.R., $26,492. Beach erosion control activities pursuant to section III, Public Law 90-483 Mitigation of Shore Damages Attributable to Navigation Projects No costs were incurred under the above authorization. Beach erosion control activities pursuant to Shoreline Erosion Control Act of 1974, Public Law 98-251. No costs were incurred under the above authorization. Flood Control 48. CENTRAL AND SOUTHERN FLORIDA Location. The project is located generally within the southeastern eighteen counties of Florida covering an area of about 15,200 square miles. It is comprised of the Upper St. Johns River basin in the northeastern section of project, Kissimmee River basin in central section above the Lake Okeechobee- Everglades area in the central and southwestern section, and the east coast Everglades area in southeastern section. Previous projects. Completed works for control of Lake Okeechobee were included in and constructed under the navigation project for Okeechobee Waterway, Fla. (formerly Caloosahatchee River and Lake Okeechobee drainage area, Fla.) and under provisions of River and Harbor Acts of July 3, 1930, and August 30, 1935. For further information, see Annual Reports, 1948 and 1949. Existing project. The authorized project is for flood relief and water conservation and provides principally for: an east coast protective levee extending from the Homestead area north to the eastern shore of Lake Okeechobee near the St. Lucie Canal; three conservation areas for water impoundment in the Everglades area west of the east coast protective levee with control structures to effect transfer of water as necessary; local protective works along the lower east coast; encirclement of the Lake Okeechobee agricultural area by levees and canals; enlargment of portions of Miami, North New River, Hillsboro, and West Palm Beach Canals; enlargement of the existing Lake Okeechobee levees and construction of new levees on the northeast and northwest shore of the lake; increased outlet capacity for improved control of Lake Okeechobee; floodway channels in the Kissimmee River basin, with suitable control structures to prevent over-drainage; an interrelated system of canals, levees, pumping stations, and structures in southwest Dade County to control water levels; and facilities for regulating floods in the Upper St. Johns River basin; a system of canals and control structures for gravity drainage of Martin County and distribution of available water supplies to portions of Martin and St. Lucie Counties; and works to improve the supply, distribution, and conservation of water resources in central and southern Florida, including the Lake Okeechobee agricultural area, Everglades National Park, and other related areas. The project will provide water control and protection from recurrence of the devastating floodwaters from the Everglades and local sources, for the highly developed urban area along the lower east coast of Florida and for the productive agricultural areas around Lake Okeechobee (including towns around lake), in the Upper St. Johns and Kissimmee River basins, and in South Dade County. Project also provides for navigation improvements suitable for recreational craft, consisting of locks and channel dredging in the upper Kissimmee and St. Johns basins. The project includes a total of 990 miles of levees, 978 miles of canals, 30 pumping plants, 212 floodway control and diversion structures, 56 railroad bridge relocations, and 2 highway bridge relocations. The project also provides that upon completion, local interests assume operation and maintenance of all completed works except levees, channels, locks, and control works for regulation of Lake Okeechobee and the main control structures of conservation areas, which will be operated and maintained by the United States. The principal features of the hurricane gates, constructed under previous projects for Okeechobee Waterway and maintained under existing project since July 1, 1950, are set forth in Table 9-K. See also Table 9-L for principal features of locks and dams. Estimate of cost for new work (Oct. 1984 price 9-22 JACKSONVILLE, FLA. DISTRICT levels) is $807,256,000 Federal funds ($805,000,000 Corps and $2,256,000 U.S. Coast Guard) and $215,000,000 contributed funds, exclusive of river and harbor funds expended on previous projects. Local interests' costs in reviewing plans and specifications are expected to be $680,000. In addition, estimated cost to local interests of lands, rights-of-way, and relocations is $206,184,000. (See Table 9-B for Authorizing Legislation.) Local cooperation. (See Table 9-M for local cash contribution.) Local interests must also: provide lands, rights-of-way, and spoil disposal areas; hold the United States free from damages; bear the cost of maintenance and operation of all works except those having to do with regulation of Lake Okeechobee and the main control structures of conservation areas; construct and maintain lateral drainage facilities; prohibit encroachment on flood-carrying capacity of the improved channels; and assume cost of all new highway bridges, relocations of existing bridges and alterations to utilities incident to construction of the project. In addition, for small boat navigation channels, local interests must provide, maintain, and operate adequate public landings, sanitary and access facilities, and establish regulations prohibiting discharge of pollutants into the waters of the locks and channels by users thereof. Assurances of local cooperation have been accepted by the District Engineer for all items of work authorized to date except those for the Small Boat navigation feature added in 1970 under Section 201 of the Flood Control Act of 1965. Operations and results during fiscal year. (See Table 9-N for work accomplished.) Operations and care. a. Features completed under previous navigation project for Okeechobee Waterway and being maintained under this project are: a levee about 70 miles long following in general the south shore of Lake Okeechobee and a north shore levee 15.8 miles long; spillways at Ortona and St. Lucie locks; 5 hurricane gates; 20 gated drainage culverts through the levee; and 16 spillways along St. Lucie Canal. b. Features completed under existing project that are to be maintained with operation and maintenance funds are: (1) Levees 47, 48, 49 and 50- total length 63 miles and enlargement of existing levees L-D1, L-D2, L-D3, L-D4, and L-D9, (2) spillway structures S-10, S-11, S-12, S-18C, S-77, and S-78 (3) C-43, Sec. 4 (Caloosahatchee River), and (4) W. P. Franklin Lock and Dam. In addition to the actual facilities listed above it is necessary under operation and maintenance to continue meteorological studies, water level records, stream gaging stations, etc, for proper regulation of the level of Lake Okeechobee and storage of water in Conservation Areas 1, 2 and 3. REGULATION Corps of Engineers - The Corps of Engineers operates and maintains the major outlets to Lake Okeechobee and Water Conservation Area Nos. 1, 2A and 3A in central and southern Florida. South Florida Water Management District - SFWMD is responsible for operation and maintenance of the remainder of the project facilities, including major pumping stations, spillways, locks (except on Okeechobee Waterway), levees and culverts. Condition at end offiscal year. The scheduled work of project is 77 percent complete. Planning for the entire project began in November 1948 and has been continued. For construction completed prior to Fiscal Year 1980 see Annual Reports for 1960-1979. Construction completed under existing project during the fiscal year is set forth in Table 9-0. All Federally maintained features of the project were generally in good condition at the end of the fiscal year. (For status of work under contract at end of fiscal year see Table 9-P.) Total Federal costs under the existing project through September 30, 1985 were $283,315,672 for new work, $46,264,205 for maintenance, a total of $329,579,877. In addition, $51,748,673 has been expended from contributed funds for new work. 49. FOUR RIVER BASINS, FLA. Location. The Four River Basins area covers about 6,000 square miles within 14 counties in central and southwest peninsular Florida. Project includes all or part of the four main stream basins-the Hillsborough, Oklawaha, Withlacoochee, and Peace Rivers-and all of three smaller coastal basins north of Tampa, Florida, drained by the Pithlachascotee and Anclote Rivers and Lake Tarpon. Existing project. The authorized project provided for improvements for control of floods and drainage, and for water conservation through construction of necessary canals, levees, reservoirs, and control structures. More specifically, the project provided for: Green Swamp Area-a conservation area and three storage reservoirs with necessary canals and control structures; Hillsborough River-four flood-storage reservoirs, with necessary channels, control structures, and levees; Oklawaha River-a levee on the north shore of Lake Apopka, improvement of part of the river channel and a west bank levee below Moss Bluff lock and dam, and replacement of the lock and dam; Withlacoochee River-one flood-storage reservoir with outlet canals and control structures; Peace River-Peace Creek canal and control structures and improvements to the existing water control and drainage features; Gulf Coastal Areas-Lake Tarpon: outlet canal and control structure; Anclote River: control structure and channel improvement; 9-23 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Pithlachascotee River: reservoir with outlet canals and control structures. (See Table 9-Q on Moss Bluff Lock.) Estimated cost for new work (Oct. 1984 price level) is $197,000,000 Federal funds and $131,500,000 non- Federal cost. ($40,700,000 contributed funds; $53,530,000 for lands and damages; and $37,270,000 for relocations.) (See Table 9-B for Authorizing Legislation.) Local cooperation. Local interests must furnish all lands, and rights-of-way; provide all alterations or replacements of public and private utilities, roads, bridges (except railroad bridges), etc; hold the United States free from damages; operate and maintain all project works after completion; construct and maintain such associated works as are necessary to realize benefits made available by the project works; and contribute in cash 17 percent of the first cost of construction and 50 percent of recreation costs. Operations and results during fiscal year. New work: Contract for Morris Bridge and Flint Creek recreation sites continued at a cost of $40,435 and the modification to landscape disposal areas cost $25,596. Contract for Tampa Bypass Shoal removal and cleanup cost was $446,681. Contract for Dead River recreation sites continued at a cost of $181,860. Engineering and design and supervision and administration costs were $132,641 and $97,029, respectively. Condition at end of fiscal year. Construction of the project commenced April 18, 1966 and the scheduled work is 96 percent complete. See Table 9-R for construction of major features of the project completed to date 50. PORTUGUES AND BUCANA RIVERS P.R. (This project authorized as Lago de Cerrillos, Lago de Portugues, and Channel Improvement at Ponce.) Location. Portugues and Bucana Rivers originate on the southern slopes of Cordillera Central divide of Puerto Rico and flow from this central ridge of the island to the Carribean Sea. Their drainage areas are 22.6 and 31.4 square miles, respectively. Ponce, the second largest city in Puerto Rico, is located in the lower coastal area along Portugues River and is the only urban community in the two basins. Existing project. The authorized project provides for two multiple-purpose reservoirs for flood control, water supply, general recreation, and fish and wildlife enhancement-one on Portugues River and the other on Cerrillos River, a tributary to the Bucana River; enlargement of about 5.7 miles of the Bucana River, with an additional 0.2-mile tieback levee at the upstream terminus of the improvement; enlargement of 2.1 miles of the Portugues River, with an additional 0.5 mile of tieback levee at the upstream terminus of the improvement; and a 1.3 mile diversion channel connecting Portugues River to lower Bucana River. Estimated cost of the project (Oct. 1984 price level) is $301,000,000 Federal cost and $80,140,000 non-Federal cost ($57,311,000 for lands and damages; $14,759,000 for relocations; and $8,070,000 for highway bridges and approaches). (See Table 9-B for Authorizing Legislation.) Local cooperation. Local interests must provide all lands, easements and rights-of-way; hold the United States free from damages; operate and maintain all project works after completion; repay construction cost allocated to water supply in accordance with Water Supply Act of 1958; pay one-half of the separable cost allocated to recreation and fish and wildlife enhancement; prohibit discharge of inadequately treated sewage and other pollutants into the reservoir; and prevent encroachment on downstream channels. Assurances of local cooperation have not been completed, except for Cerrillos Reservoir which was signed March 15, 1982. Operations and results during fiscal year. New work: Contract for Cerrillos Dam & Spillway continued at a cost of $15,609,044 hired labor costs were $162,190. Contract for Cerrillos Dam diversion tunnel and foundation preparation continued at a cost of $899,626. Completed contract for Upper Portugues Channel Section 6C and Cerrillos dam and spillway site work at a cost of $538,502. Contract for Section 7 continued at a cost of $483,845. Contracts for Bucana Debris Basin excavation and Portugues Channel improvement and debris control basin has respective costs of $1,731,532 and $761,020. Contract for Section 6D cost $50,000. Cultural resource investigations cost $132,512. Area office equipment cost $31,553. Engineering anddesign and supervision and administration costs were $2,602,115 and $1,208,168 respectively. Condition at end of fiscal year. Construction of the project commenced in September 1975 and is 35 percent complete. 51. INSPECTION OF COMPLETED FLOOD CONTROL PROJECTS Features transferred to the Central and Southern Florida Flood Control District and Southwest Florida Water Management District were inspected quarterly during the fiscal year at a total cost of $12,541. 52. OTHER AUTHORIZED FLOOD CONTROL PROJECTS (See Table 9-S.) 53. FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION Flood control activities pursuant to section 205, Public Law 685, 84th Congress, as amended (preauthorization). 9-24 JACKSONVILLE, FLA. DISTRICT (See Thble 9-T.) Emergency flood control activities-repairf,l ood fighting, and rescue work (Public Law 99, 84th Congress and antecedent legislation). Federal costs for the fiscal year were $133,805 for the Disaster Preparedness Program, and $139,028 for national emergency and mobilization readiness plans. Emergency streambank and shoreline protection activities pursuant to Section 14, Public Law 526, 79th Congress as amended (preauthorization.) Federal costs for the fiscal year were $12,073 for Barrio Barrero, Rincon, Puerto Rico; $62 for Black Point Hill, St. Thomas, Virgin Islands; and $19,452 for Highway 187, El Trraplan, Puerto Rico. General Investigations 54. SURVEYS Hired labor costs during the fiscal year (all Federal funds) were: navigation studies, $570,027,. flood damage prevention studies $1,864,173, shoreline protection studies, $127,916 and special studies $212,275 for a total of $2,774,391. 55. COLLECTION AND STUDY OF BASIC DATA The requirement for preparation of regular flood plain information studies has been rescinded. FPI studies that deal with land use changes will continue to be prepared. FPMS Unit Jacksonville, Fla., $65,146. Gold coast hurricane evacuation study, $625. Thchnical services, $100,109. 9-25 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 9-A COST AND FINANCIAL STATEMENT See Section Total Cost to in 'Txt Project Funding FY 82 FY 83 FY 84 FY 85 Sept. 30, 1985 1. Aquatic Plant Control (R&H Act of 1965) (Federal Funds) Arecibo Harbor, P.R. (Federal Funds) Atlantic Intracoastal Waterway between Norfolk, Va. and St. John's River, Fla. (Federal Funds) Bakers Haulover Inlet, Fla. (Federal Funds) Canaveral Harbor, Fla. (Federal Funds) (Contrib. Funds) Channel from Naples to Big Marco Pass, Fla. (Federal Funds) (Contrib. Funds) Charlotte Harbor, Fla. (Fbderal Funds) Cross-Florida Barge Canal (Federal Funds) Eau Gallie Harbor, Fla. (Federal Funds) 1,415,400 1,991,000 2,106,000 2,626,000 19,494,670 1,329,420 2,074,745 2,134,771 2,622,586 19,423,859 48,153 451,914 1,564,000 586,784 42,308 1,960,302 New Work: Approp. Cost New Work: Approp. Cost Maint: Approp. Cost New Work: Approp. Cost Maint: Approp. Cost New Work: Approp. Cost Maint: Approp Cost New Work: Approp. Cost Maint: Approp. Cost New Work: Approp. Cost New Work: Approp. Cost Maint: Approp. Cost New Work: Approp. Cost New Work: Approp. Cost Maint: Approp. Cost New Work: Approp. Cost Maint: Approp Cost New Work: Approp. Cost Maint: Approp. Cost 1,073,000 3,121,103 200,000 132,655 4,924,000 5,014,000 -70,000 453,802 149,329 122,033 500,000 246,727 1,120,000 1,114,598 2,642,645 63,907 80,000 79,956 554,990 445,286 1,837 3,146 2,613,000 2,642,802 20,000 1,655 1,655,000 1,407,447 82,438 6,884 20,685 2,240,347 1,995,672 972,087 1,048,073 858 1,531,000 1,949,141 76,370 73,073 200,253 190,474 6,656 -8,290 16,241 3,300,000 241,023 5,790,500 5,628,309 103,000 83,296 62,526 2,024,000 2,005,725 310,000 242,145 1,593,000 1,578,798 375,000 345,057 1,128,0751 1,128,0751 3,945,699 3,920,950 361,2252 361,2252 5,292,313 5,292,112 243,2353 243,2353 178,163 175,398 11,421,9104 8,042,2714 32,788,321 32,591,954 1,106,000 1,003,000 305,290 305,290 1,004,994 984,224 159,975 159,975 533,1696 533,1696 11,606,051 11,578,744 63,172,473 63,103,813 17,881,4636 17,778,1426 9,627 9,627 536,284 503,044 9-26 9,063 9,324 3. 4. 5. 6. 8. JACKSONVILLE, FLA. DISTRICT TABLE 9-A (Continued) COST AND FINANCIAL STATEMENT See Section Total Cost to in Text Project Funding FY 82 FY 83 FY 84 FY 85 Sept. 30, 1985 10. Fernandina Harbor, Fla. (Federal Funds) (Contrib. Funds) 11. Fort Myers Beach Channel, Fla. (Federal Funds) 12. Fort Pierce Harbor, Fla. (Federal Funds) (Contrib. Funds) 13. Gulf Intracoastal Waterway, Caloosahatchee River to Anclote River, Fla. (Federal Funds) 14. Intracoastal Waterway, Jacksonville to Miami, Fla. (Federal Funds) Jacksonville Harbor, Fla. (Federal Funds) (Contrib. Funds) 16. Johns Pass, Fla. (Federal Funds) 17. Longboat Pass, Fla. (Federal Funds) (Contrib. Funds) New Work: Approp. Cost Maint: Approp. Cost New Work: Approp. Cost New Work: Approp. Cost Maint: Approp. Cost New Work: Approp. Cost Maint: Approp. Cost New Work: Approp. Cost New Work: Approp. Cost Maint: Approp. Cost New Work: Approp. Cost Maint: Approp. Cost New Work: Approp. Cost Maint: Approp. Cost Rehab. Approp. Cost New Work: Approp. Cost New Work: Approp. Cost Maint: Approp. Cost New Work: Approp. Cost Maint: Approp. Cost New Work: Approp. Cost 325 2,323,000 1,474,260 7,116 229 229 7,141 716,000 965,781 7,000 7,141 -2,000 - 116 3,768,928 4,368,503 116 13,521 13,654 92,262 1,215,646 58,026 985,514 69,127 60,139 761,000 668,579 1,923,000 2,754,261 338,000 342,621 687,000 721,506 -134,834 125,783 773,000 170,300 115,111 810,601 - 709 1,207,620 939,046 1,284,573 936,138 3,007,099 5,365,700 339,545 8,048,812 6,657 8,136 342 37,419 37,419 -414 3,229 - 4,147,8167 -35 4,094,9317 2,261,000 22,156,367 2,244,910 22,137,955 - 812,000 35 811,054 56,464 46,375 77,214 63,391 125,000 139,039 929,962 852,580 7,355,000 7,362,380 1 342,839 341,589 340,000 327,124 158,1408 158,1408 718,885 708,796 356,056 356,056 3,654,160 3,633,483 18,574 18,574 8,112,5579 8,112,5579 5,791,53810 5,778,88910 19,251,59811 19,251,59811 26,034,43112 25,920,70412 47,596,27813 47,596,278s13 54,730,38514 54,719,17814 102,813 102,813 927,65415 927,65415 82,09816 82,09816 1,139,815 1,138,565 1,020,233 1,020,233 1,167,962 1,155,086 172,324 172,324 9-27 15. REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 9-A (Continued) Se4 Se( in COST AND FINANCIAL STATEMENT e ction Total Cost to Text Project 18. Mayaguez Harbor, P.R. (Federal Funds) 19. Melbourne Harbor, Fla. (Federal Funds) 20. Miami Harbor, Fla. (Federal Funds) (Contrib. Funds) 21. New Pass Sarasota, Fla. (Federal Funds) 22. Okeechobee Waterway, Fla. (Federal Funds) (Contrib. Funds) 23. Oklawaha River, Fla. (Federal Funds) 24. Palm Beach Harbor, Fla. (Federal Funds) 25. Ponce de Leon Inlet, Fla. (Federal Funds) (Contrib. Funds) Funding New Work: Approp. Cost Maint: Approp. Cost New Work: Approp. Cost Maint: Approp. Cost New Work: Approp. Cost Maint: Approp. Cost New Work: Approp. Cost New Work: Approp. Cost Maint: Approp. Cost New Work: Approp. Cost Maint: Approp. Cost New Work: Approp. Cost New Work: Approp. Cost Maint: Approp. Cost New Work: Approp. Cost Maint: Approp. Cost New Work: Approp. Cost Maint: Approp. Cost New Work: Approp. Cost Maint: Approp. Cost FY 82 FY 83 FY 84 FY 85 Sept. 30, 1985 54,205 294,822 150,000 123,913 32,663 32,663 695,000 755,574 18,805 1,953,000 1,792,820 41,000 32,912 447,000 431,138 110,084 139,086 15,624 -708 711 130,000 271,416 29,868 29,868 8,239 9,119 80,000 77,577 1,387,000 1,690,333 40,000 31,430 875,000 702,717 323,000 161,230 41,025 33,523 76,000 69,582 100,000 93,539 57,259 57,259 2,439 1,746,300 1,720,400 10,000 18,107 45,697 208,803 2,600,000 2,742,016 -3,984 3,039 228,000 233,567 1,000,000 269,054 116,512 60,856 894,000 892,444 262 2,084,000 2,022,254 4,062 7,594 3,725,000 3,721,562 6,465,846 6,477,022 168,187 168,187 1,021,520 1,021,042 17,696 17,696 383,526 382,675 25,796,06617 25,048,27017 2,382,614 2,326,958 2,262,71018 2,262,71018 45,81119 45,81119 3,032,411 3,030,855 21,400,59020 21,400,59020 29,861,96621 29,681,55021 503,700 503,700 315,26422 315,26422 2,002,74823 1,996,40923 6,904,02124 6,904,02124 8,524,90625 8,496,33025 1,953,277 1,953,277 15,128,394 15,109,181 2,415,600 2,415,600 1,379,000 612,663 9-28 JACKSONVILLE, FLA. DISTRICT TABLE 9-A (Continued) COST AND FINANCIAL STATEMENT See Section Ibtal Cost to in Text Project Funding FY 82 FY 83 FY 84 FY 85 Sept. 30, 1985 26. Ponce Harbor, P.R. (Federal Funds) 27. Port Everglades Harbor, Fla. (Federal Funds) 28. Removal of Aquatic Growth (Federal Funds) 29. St. Augustine Harbor, Fla. (Federal Funds) 30. St. Johns River, Fla. Jacksonville to Lake Harney (Federal Funds) 31. St. Lucie Inlet, Fla. (Federal Funds) (Contrib. Funds) 32. San Juan Harbor, P. R. (Federal Funds) 33. Tampa Harbor, Fla. (Main Project) (Federal Funds) (Contrib. Funds) 37. Brevard County, Fla. (Federal Funds) (Contrib. Funds) New Work: Approp Cost Maint: Approp. Cost New Work: Approp. Cost Maint: Approp. Cost Maint: Approp. Cost New Work: Approp Cost Maint: Approp. Cost New Work: Approp. Cost- Maint: Approp. Cost New Work: Approp. Cost Maint: Approp. Cost New Work: Approp. Cost New Work; Approp. Cost Maint: Approp. Cost New Work: Approp. Cost Maint: Approp. Cost New Work: Approp. Cost New Work: Approp. Cost Maint: Approp. Cost New Work: Approp. Cost -8,000 16,029 62,000 281,654 13,982,000 10,733,178 11 11 50,000 5,977 -21,388 622 3,641,995 212 212 25,025 32,771 38,000 35,020 1,533,415 350,000 304,179 25,000 6,187 131 2,500 3,500,000 4,165,925 170,889 216,660 482,90726 426,90326 1,304,364 1,303,753 44,255,77327 43,963,53227 1,561,670 1,561,620 2,022,000 2,092,000 2,622,000 2,465,000 25,537,370 1,981,456 2,192,273 2,803,286 2,450,831 25,499,709 24,431 24,431 17,329 17,371 700,000 864,477 62,262 46,604 507,000 386,512 -220,000 1,129,302 29,899,000 31,755,233 2,656,000 5,113,608 165,000 187,912 3,109 308 308 19,990 8,112 8,128 9,968 9,977 900,000 758,819 32,094 71,798 136,000 250,909 -60,159 23,539 21,502,000 19,855,010 1,290,000 1,036,867 135,000 116,418 1,321 576 80,000 74,285 33,615 33,589 514,688 286,610 273,332 394,043 176,942 168,086 150,725 9,870,000 9,352,559 210,700 463,233 60,000 63,490 -3,315 3,637 90,000 74,992 324,991 320,979 585 2,075,000 2,079,004 233,983 382,492 170,229 150,401 1,476,43428s 1,476,4348 4,347,058 4,326,335 1,171,24329 1,171,24329 1,284,260 s0 1,280,222 s0 7,863,60281 7,828,332 3s1 4,655,915 4,646,641 3,086,026 3,011,854 13,774,96832 13,774,96832 12,001,94033 11,964,752$$ 17,015,000 194,504,64334 18,838,450 194,117,66984 170,000 18,967,52286 165,443 18,955,77186 100,000 1,029,962 111,481 1,017,637 17,945 -1,797 2,346,492 2,271,151 29,001 29,001 2,262,000 2,257,081 9-29 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 9-A (Continued) See Section in Text Project 38. Broward County. Fla. Beach Erosion Control and Hillsboro Inlet, Fla., Navigation Project (Federal Funds) (Contrib. Funds) 39. Dade County, Fla. (Federal Funds) (Contrib. Funds) 40. Dade County, N. of Haulover Beach, Fla. Federal Funds) Contrib. Funds) 41. Duval County. Fla. (Federal Funds) Contrib. Funds) 42. El 'Thque Beach Ponce, Puerto Rico (Federal Funds) (Contrib. Funds) 43. Ft. Pierce, Fla (Federal Funds) (Contrib. Funds) 44. Palm Beach County, Fla. from Martin County line to Lake Worth Inlet to Broward County line (Federal Funds) 45. Pinellas County, Fla. (Federal Funds) (Contrib. Funds) COST AND FINANCIAL STATEMENT I 9-30 Funding New Work: Approp. Cost Maint: Approp. New Work: Approp. Cost New Work: Approp Cost New Work: Approp. Cost New Work: Approp. Cost New Work: Approp. Cost New Work: Approp. Cost New Work: Approp. Cost New Work: Approp. Cost New Work: Approp. Cost New Work: Approp. Cost Maint: Approp. Cost New Work: Approp. Cost New Work: Approp. Cost Maint: Approp. Cost New Work: Approp. Cost Maint Approp. Cost New Work: Approp. Cost FY 82 13,347 7,974 7,974 8,195,000 7,509,369 5,050,000 4,707,158 200,000 -1,331 23,132 360,000 -19,246 520,000 40,364 -333 6,012 16,950 1,000,000 54,950 69 69 900,000 FY 83 4,334 614 614 510,000 -487,351 230,000 1,221,775 100,000 55,449 29,159 330,000 378,703 96,620 69 40,000 44,904 542,817 505,218 FY 84 4,730,000 4,773,650 246,200 50,000 59,751 1,000,000 258,970 200,000 23,089 158,500 483,920 270,610 4,969 7,107 300,000 48,942 700,000 290,475 -140,706 217,566 FY 85 50,000 -300,000 279,393 360,000 33,204 15,000 2,350,000 1,096,216 2,370,000 926,428 -8,789 -3,482 -114,481 -2,075 -415 415 2,050,000 1,884,034 -130,000 316,002 368,342 50,710 'btal Cost to Sept. 30, 1985 11,033,100 10,982,868 26,884 26,884 1,758,84136 1,758,84186 32,343,95637 31,406,87737 22,834,08538 22,503,00438 15,000 9,418,900 7,160,282 6,712,400 5,063,947 991,211 991,211 405,519 405,519 1,175,44889 5151,021 9 31,734 31,734 773,000 769,412 4,220,834 3,803,810 13,621 13,621 3,109,693 2,671,225 5,625 5,625 2,553,391 2,198,056 TABLE 9-A (Continued) JACKSONVILLE, FLA. DISTRICT COST AND FINANCIAL STATEMENT See Section Ibtal Cost to in Text Project Funding FY 82 FY 83 FY 84 FY 85 Sept. 30, 1985 48. Central and New Work: Southern Florida Approp. 6,780,000 9,000,000 8,600,000 8,400,000 286,056,39740 (Federal Funds) Cost 4,859,723 6,865,717 11,422,711 7,439,279 283,315,67240 Maint: Approp. 3,774,000 3,980,000 4,292,000 4,073,000 46,500,961 Cost 3,213,709 3,953,714 4,550,595 4,254,980 46,264,205 (Contrib. Funds) New Work: Approp. 200,000 1,271,700 2,179,837 1,770,263 54,051,375 Cost 622,179 756,016 1,652,885 1,030,971 51,748,673 49. Four River New Work: Basins, Fla. Approp. 1,420,000 3,595,000 -1,600,000 1,050,000 71,477,09541 (Federal Funds) Cost 1,332,526 1,076,456 764,489 564,734 70,527,07041 Contrib. Funds) New Work: Approp. 115,000 352,148 335,412 647,000 12,386,860 Cost 191,461 389,206 335,379 359,508 12,023,474 50. Portugues and New Work: Bucana Rivers, Approp. 14,600,000 18,990,000 18,700,000 22,600,000 120,425,568 P. R. Cost 13,535,452 19,476,203 16,702,794 24,210,107 118,463,581 (Federal Funds) 9-31 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 1. Excludes $288,000 contributed funds for new work. 2. Includes $97,566 for previous project. 3. Excludes $243,235 contributed funds for new work. 4. Excludes $700,000 contributed by NASA in connection with construction of lock. 5. Includes $113,000 for new work on previous project; excludes $15,563 expended for new work on existing project from contributed funds. 6. Excludes $113,744 for maintenance and operation of dams. 7. Includes $142,792 expended for recreation facilities. 8. Includes $10,128 cost for reconnaissance and detailed project report prepared under Sec. 107 modification to the project. Excludes $1,095 contributed funds for new work. 9. Includes $515,479 for new work for previous projects: $8,472 for new work on Sunshine Skyway Channel; and $9,707 for new work for Cats Point Channel. Excludes $14,473 contributed funds for new work. 10. Includes $450,749 for maintenance for previous project. 11. Includes $94,776 for work for previous projects. 12. Includes $213,222 for maintenance on previous projects and $3,179 operating and care under provisions of permanent indefinite appropriation. 13. Includes $3,520,137 new work on previous project and $290,013 for new work expended from public works funds. 14. Includes $543,399 maintenance on previous projects. 15. Includes unused contributed funds of $64,136 returned to local interests. 16. Project authorized December 2, 1964, by Chief of Engineers under Section 107 of 1960 R&H Act and by Section 110 of the 1966 R&H Act. Cost of new work excludes $53,732 contributed funds. 17. Includes $2,202,126 expended from public work funds for new work. Includes costs of $1,086,509 for recreation facilities. 18. Includes $343,479 work-in-kind and $160,429 in costs for north jetty recreation facility. 19. Excludes $45,811 contributed funds for new work. 20. Includes $16,222,275 for new work under previous project, $626,925 for recreational facilities (Code 710), and $27,574 for reconnaissance and detailed project report prepared under Section 107 modification to the project. 21. Includes $7,581,150 for maintenance for previous projects. Excludes $1,000 for maintenance from contributed funds on previous projects, $67,558 which represents services rendered without reimbursement, and $113,744 for maintenance and operations of dams. 22. Includes $3,912 for new work for previous projects. 23. Includes $11,414 for operating and care under provisions for the permanent indefinite appropriation. 24. Includes $80,000 new work from public works funds. Excludes $509,506 contributed funds. 25. Includes $30,000 for maintenance from public works funds. 26. Includes $11,588 expended for restudy, but excludes $21,960 expended for new work from contributed funds. 27. Excludes $928,443 contributed funds. 28. Includes $71,303 for new work on previous project. Excludes $137,500 contributed funds. 29. Baresford cutoff and completion of cutoffs and easing of bends in Putnam Lake and Volusia Counties in inactive status were deauthorized by Public Law 93-251 section 12. Includes $29,566 for new work under previous project. 30. Includes $25,838 under previous project. 31. Includes $26,689 for new work under previous project. 32. Includes $747,684 for new work under previous project. Excludes $100,000 expended for new work from contributed funds. 33. Includes $44,730 in maintenance under previous project. 34. Includes $853,050 for new work under previous project. Excludes $270,466 for new work for Hillsborough River and $13,939 for new work from contributed funds. Includes $15,000 Appropriation for new work East Bay Channel. 35. Includes $17,107 for maintenance under previous project. 36. Excludes work-in-kind. 37. Includes $2,282,213 for reimbursement costs to Bal Harbor. 38. Excludes unused contributed funds of $17,969 returned to local interests. 39. Excludes $300,083 in property for services furnished by local interests in lieu of cash contribution. 40. Excludes $15,543 for property received without reimbursement and R&H Funds, expended on previous projects (see cost and financial statement for Okeechobee Waterway, Fla., project for these costs). Excludes $100,000 advanced by local interests toward federal costs. 41. Includes costs of $89,691 for recreation facilities at Moss Bluff and $2,638,272 at Lake Thrpon. 9-32 JACKSONVILLE, FLA. DISTRICT TABLE 9-B AUTHORIZING LEGISLATION Acts Work Authorized Documents October 27, 1965 August 26, 1937 March 4, 1913 June 20, 1939 July 14, 1960 March 2, 1945 October 23, 1962 June 20, 1938 July 14, 1960 July 25, 1912 March 3, 1925 July 3, 1930 August 26, 1937 May 17, 1950 P.L. 675/77 July 23, 1942 June 20, 1938 June 14, 1880 July 13, 1892 March 2, 1907 June 25, 1910 AQUATIC PLANT CONTROL (See Section 1 of Text) Control and progressive eradication of obnoxious aquatic plants, and continued research to develop best method of control ARECIBO HARBOR, P.R. (See Section 2 of Text) Construction of breakwater 1,200 feet long and dredging channel 25 feet deep and 400 feet wide with flare at entrance and widening at inner end to form a maneuvering area. ATLANTIC INTRACOASTAL WATERWAY BETWEEN NORFOLK, VA. AND THE ST. JOHNS RIVER, FLA. (See Section 3 of Text) Channel 7 x 100 feet Channel 12 feet deep and 90-150 feet wide with cut-offs BAKERS HAULOVER (See Section 4 of Tebxt) Channel 11 x 200 feet in ocean entrance, thence 8 x 100 feet to Intracoastal Waterway; Marina basin 8 x 200 feet; reconstruction of jetties and protection of inlet shores. CANAVERAL HARBOR, FLA. (See Section 5 of Text) Entrance channel jetties, a turning basin enclosed by a dike, and a barge canal with a lock Maintain improved channel, turning basin, enlarge barge channel and lock, relocate dike, provide channel and turning basin west of 35-foot turning basin, construct and operate sand-transfer plant CHANNEL FROM NAPLES TO BIG MARCO PASS, FLA. (See Section 6 of Text) Interior channel 6 x 70 feet Channel 12 x 150 feet from the Gulf to Gordon Pass, thence 10 x 100 feet to a point 400 feet south of U.S. Highway 41 Bridge thence 10 x 70 feet to bridge and two turning basins CHARLOTTE HARBOR, FLA. (See Section 7 of Text) Channel 24 x 300 feet through Gulf through Boca Grande entrance Depth of 27 feet at entrance and width of 500 feet at the bend Channel 10 x 100 feet to Punta Gorda and a turning basin Depth of 30 feet at entrance and width of 700 feet at bend Depth of 32 feet in entrance channel CROSS-FLORIDA BARGE CANAL (See Section 8 of Text) Barge Canal 12 x 150 feet EAU GALLIE HARBOR, FLA. (See Section 9 of Text) Channel 8 x 100 feet and a turning basin FERNANDINA HARBOR, FLA. (See Section 10 of lbxt) Entrance jetties Raising and extending jetties to provide 19-foot depth Improvement of inner harbor to obtain 20- to 24-foot depth and 400- to 600-foot channel width Combining improvement of Fernandina Harbor and Cumberland Sound under the general heading of Fernandina Harbor H. Doc 251, 89th Cong., 1st sess. Rivers & Harbors Committee Doc 43, 75th Cong., 1st ses. H.Doc 898, 62nd Cong., 2d sess. H.Doc. 618, 75th Cong., 3d sess. H.Doc 189, 86th Cong., 1st sess. H.Doc 367, 77th Cong., 1st sess. S.Dos 140, 87th Cong., 2d sess. H.Do. 596, 75th Cong., 3d sess. H.Doc 183, 86th Cong., 1st ses. H.Doe. 699, 62nd Cong., 2d sess. H.Doc 113, 66th Cong. 1st sess. Rivers and Harbors Committee Doc 1, 70th Cong., 1st ses. Rivers and Harbors Committee Doc 95, 74th Cong., 2d ses. H.Doc 186, 81st Cong., 1st ses. H.Doc. 109, 79th Cong., 1st ses. H.Doc 497, 75th Cong., 3rd sess. Annual Report 1879 Annual Report 1891 & 1896 H.Dos 388, 59th Cong., 1st sess. 9-33 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 9-B (Continued) AUTHORIZING LEGISLATION* Acts Work Authorized Documents March 3, 1925 June 20, 1938 March 2, 1945 May 17, 1950 July 14, 1960 Auth. by Chief of Engineers December 6, 1968, under Sec. 107 of 1960 R&H Act. Def. Act of March 4, 1931 War Dept. Approp. Act, March 4, 1933 August 30, 1935 March 2, 1945 June 30, 1948 May 17, 1950 September 3, 1954 May 10-16, 1957 Auth. March 1, 1962 By Senate and House Public Works Committee Auth. by Chief of Engineers March 1, 1963, under Sec. 107 of 1960 R&H Act January 21, 1927 July 3, 1930 PARA June 26, 1934 August 26, 1937 March 2, 1945 Do. Provided for a 26-foot channel Provided for the 28-foot channel and turning basin Provided for reducing the maximum width of turning basin from 1,000 to 800 feet, for shifting channel line in this vicinity 50 feet northwesterly and for including in authorized project small area dredged by Rayonier, Inc Provided for 32-foot channel and turning basin FORT MYERS BEACH, FLA. (See Section 11 of Tbxt) 12- x 150 foot channel in San Carlos Bay, thence 11 x 125 feet in Matanzas Pass to upper shrimp terminals Extension of 11- x 125-foot channel easterly about 2,000 feet to and including a turning basin adjacent to natural deep water in Matanzas Pass FORT PIERCE HARBOR, FLA. (See Section 12 of Text) Expenditure of $20,000 for dredging channel, maintenance by local interests Expenditure of up to $30,000 for dredging channel Maintaining channels, jetties, and revetments, and enlarging channels and turning basin to existing project dimensions INTRACOASTAL WATERWAY, CALOOSAHATCHEE RIVER TO ANCLOTE RIVER, FLA. (See Section 13 of Text) 9- x 100-foot channel; deepening channel at Caseys Pass to 9 feet and construction of highway bridge at Venice Original route may be modified at no excess cost to U. S. Any route in Venice-Lemon Bay area may be used Use of alternate Route C-1 in Venice-Lemon Bay area Local interests to bear costs of Venice Avenue highway bridge and any other necessary crossing over Route C-1 Sunshine Skyway Channel to be improved and maintained to 9 x 100 feet H.Doc. 227, 68th Cong., 1st sess. H.Doc. 284, 77th Cong., 1st sess. H.Doc. 284, 87th Cong., 1st sess. H.Doc. 662, 80th Cong., 2d sess. H.Doc. 183, 86th Cong., 1st sess. Specified in Act Specified in Act H. Doc. 252, 72nd Cong., 1st sess. and Rivers and Harbors Committee Doc. 21, 74th Cong., 1st sess. H. Doc. 371, 76th Cong., 1st sess. Specified in Act Specified in Act Specified in Act H.Doc. 109, 85th Cong., 1st sess. 6- x 80-foot channel in Boca Ciega Bay INTRACOASTAL WATERWAY, JACKSONVILLE TO MIAMI, FLA. (See Section 14 of 'Text) Channel 8 x 75 feet from Jacksonville to Miami Channel width of 100 feet Operation and care of Palm Valley Bridge Thrning basin at Jacksonville Beach Channel 12 x 125 feet Side channel and turning basin at Sebastian H.Doc. 586, 69th Cong., 2d sess. S.Doc. 71, 71st Cong., 2d sess. Specified in Act H.Doc. 180, 75th Cong., 1st sess. H.Doc. 740, 79th Cong., 2d sess. H.Doc. 336, 76th Cong., 1st sess. 9-34 TABLE 9-B (Continued) JACKSONVILLE, FLA. DISTRICT AUTHORIZING LEGISLATION Acts Work Authorized Documents hrning basin at Vero Beach July 3, 1958 Chief of Engineers Report of July 22, 1960, Mod. 12-foot channel March 2, 1907 Auth. by Chief of Engmneers December 2, 1964 Under Sec 107 of 1960 R&H Act and Sec 110 of 1966 R&H Act. Auth. by Chief of Engineers April 20, 1976 under Sec. 107 of 1960 R&H Act, as amended August 30, 1935 August 20, 1937 July 3, 1930 PWA Program September 6, 1933 June 13, 1902 March 2, 1907 March 4, 1913 March 3, 1925 July 3, 1930 August 30, 1935 Maintenance of side channel at Daytona Beach Channel 10 x 125 feet from Ft. Pierce to Miami JACKSONVILLE HARBOR, FLA. (See Section 15 of Tebxt) ST. JOHNS RIVER, FLA. OPPOSITE THE CITY OF JACKSONVILLE The 24-foot area from Hogan Creek to Florida East Coast Railroad bridge JOHN'S PASS, FLA. (See Section 16 of Thxt) Channel 10 x 150 feet in the gulf, 8 x 100 feet inside pass, 6 x 100 feet to IWW2.6 miles long LONGBOAT PASS, FLA. (See Section 17 of 'ext) 12- x 150-foot entrance channel from Gulf of Mexico to Longboat Bridge; 10- x 100-foot channel from Longboat Bridge northeasterly to IWW; channel from north channel to Cortez Bridge MAYAGUEZ HARBOR P.R. (See Section 18 of Text) Approach channel 30 feet deep to and along deep water terminal MELBOURNE HARBOR, FLA. (See Section 19 of Text) Channel 8 x 100 feet and a turning basin MIAMI HARBOR, FLA. (See Section 20 of Text) MIAMI RIVER The 15-foot channel in Miami River, 150 feet wide at the mouth The channel at the Dinner Key Airport An 18-foot channel in a landcut across the peninsula and construction of the north jetty Construction of the south jetty and increase of channel width to 100 feet Modification of local cooperation requirements imposed by the Act of July 25, 1912 A channel 25 feet deep with present widths from the ocean to Biscayne Bay, thence 200 feet wide across the bay to but not including the municipal turning basin, and extension of both jetties A channel width of 300 feet across the bay and enlarging the municipal turning basin, with expenditures thereon limited to $200,000 A depth of 30 feet from the ocean to and in the turning basin, with the existing authorized project widths, including the 300-foot width in the channel across the bay H.Doc. 261, 76th Cong., 1st sess. H.Doc. 222, 85th Cong., 1st sess. H.Doc. 663, 59th Cong., 1st sess. H.Doc. 215, 72nd Cong. 1st sess. & River and Harbor Committee Doc. 1, 73rd Cong., 1st sess. H.Doc. 390, 74th Cong., 2nd sess. Specified in Act S.Doc. 95, 72d Cong., 1st sess. and specified in Act H.Doc. 622, 56th Cong., 1st sess. (Annual Report 1900, p. 1987) Specified in Act Specified in Act H.Doc. 516, 67th Cong., 4th sess. Rivers and Harbors Committee Doc. 15, 71st Cong., 2d sess. Sen. Comm. Print. 73d Cong., 2d sess. 9-35 TABLE 9-B (Continued) REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 AUTHORIZING LEGISLATION Acts Work Authorized Documents August 26, 1937 March 2, 1945 March 2, 1945 July 14, 1960 August 13, 1968 Auth. by Chief of Engineers April 20, 1964 under Sec. 107 of 1960 R&H Act PARA June 26, 1934 August 26, 1937 March 2, 1945 Do. March 2, 1945 Do. Auth. by Chief of Engineers November 5, 1968, under Sec. 107 of 1960 R&H Act September 19, 1890 March 2, 1907 June 25, 1910 July 25, 1912 July 27, 1916 PARA June 26, 1934 March 13, 1934 Extending the turning basin 200 feet to the southward The Virginia Key improvement For incorporation of the project for Miami River in that for Miami Harbor, the widening at the mouth of Miami River to existing project widths; the channels from the mouth of Miami River to the turning basin and to Government Cut; and the channel from Miami River to the harbor of refuge, provided that local interest contribute one-third of the cost Deletion of Virginia Key development and the Dinner Key approach channel, widening the existing ship channel by easing the ocean bend and increasing the width of the 300-foot-wide section to 400 feet, enlarging the existing turning basin 300 feet along both the south and northeasterly sides, and dredging a turning basin along the north side of Fisher Island about 39 acres in extent and 30 feet in depth Enlarging existing entrance channel to 38 x 500 feet, deepening existing 400-foot-wide channel across Biscayne Bay to 36 feet; deepening existing turning basins at Biscayne Blvd. terminal and Fisher Island to 36 feet NEW PASS, SARASOTA, FLA. (See Section 21 of Text) 10- x 150-foot entrance channel; 8- x 100-foot inner channels; and 8-foot-deep turning basins at Payne Terminal and City Pier OKEECHOBEE WATERWAY, FLA. (See Section 22 of Text) Operation and care of locks and dams provided for with funds from R&H appropriations New lock and weir structure in St. Lucie Canal Deepening to 8 feet from Ft. Myers to Jacksonville-Miami waterway near Stuart via channel across lake from Clewiston Channel to yacht basin at Ft. Myers and a basin at Stuart Deepening to 8 feet from Ft. Myers to Jacksonville-Miami waterway near Stuart via channel across lake from Clewiston Channel to yacht basin at Ft. Myers and a basin at Stuart Enlarge existing 8- x 90-foot section of Okeechobee Waterway for about 5 miles upstream from Ft. Myers to 10 x 100 feet OKLAWAHA RIVER, FLA. (See Section 23 of Text) Clearing obstructions for channel 4 feet deep from mouth to Leesburg Channel 6 feet deep from mouth to head of Silver Springs Run Maintenance of levels in the lakes at head of river Acceptance of certain artificial waterways in lieu of portions of natural river bed Operation and care of lock and dam provided for with funds from appropriations for rivers and harbors PALM BEACH HARBOR, FLA. (See Section 24 of Text) Maintenance of improvement previously constructed by local interests Rivers and Harbors Committee Doc. 86, 74th Cong., 2d sess. S.Doc. 251, 79th Cong., 2d sess. H.Doc. 91, 79th Cong., 1st sess. S.Doc. 71, 85th Cong., 2d sess. S.Doc. 93, 90th Cong., 2d sess. Specified in Act Rivers and Harbors Committee Doc. 28, 75th Cong., 1st sess. H.Doc. 696, 76th Cong., 3d sess. H.Doc. 736, 79th Cong., 2d sess. H.Doc. 696, 76th Cong., 3d sess. H.Doc. 736, 79th Cong., 2d sess. Annual Report 1889, p. 1360 H.Doc. 782, 59th Cong., 1st sess. Specified in Acts Specified in Act Specified in Act H.Doc. 185, 73d Cong., 2d sess. 9-36 TABLE 9-B (Continued) JACKSONVILLE, FLA. DISTRICT AUTHORIZING LEGISLATION Acts Work Authorized Documents December 10, 1934 August 30, 1935 March 2, 1945 May 17, 1950 July 14, 1960 October 27, 1965 March 3, 1925 August 30, 1935 March 2, 1945 H.R. September 23, 1976 S.R. October 1, 1976 July 3, 1930 August 30, 1935 June 20, 1938 July 24, 1946 July 3, 1958 H.R. May 9, 1974 S.R. May 31, 1974 March 3, 1899 Deepening the channels and turning basin, as constructed by local interests, to 20 feet Authorized the work previously approved by Public Works Administration, and widening the channels to existing project dimensions, enlarging the 700-foot-square turning basin eastward removing the obstructive point on south side of the inlet, revetting the banks of the inlet, and restoring existing jetties Deepening the channels and turning basin to 25 feet Extending the turning basin 550 feet southward over a 900-foot width, with a flare to the east; provided that local interests may be reimbursed not to exceed $305,000 for work done by them on this modification subsequent to July 1, 1949 An entrance channel 35 feet deep, 400 feet wide, and 0.8 mile long, merging with an inner channel 33 feet deep, 300 feet wide and 0.3 mile long, thence flaring into a turning basin, 1,400 feet north-south by a mimnimum of 1,200 feet east-west PONCE DE LEON INLET, FLA. (See Section 25 of Tbxt) Widening and deepening channels; jetties on north and south side of inlet; a weir in the north jetty and an impoundment basin inside the weir PONCE HARBOR, P.R. (See Section 26 of Text) Dredging 3 continuous areas, aggregating 153 acres, to depths of 30, 18, and 9 feet, and construction of a seawall, costs to be shared by U.S. and local interests Modified conditions of local cooperation to provide that U.S. undertake all dredging at Federal expense and return local funds previously contributed for dredging, all other portions of the improvement hereafter to be at the expense of local interests Eliminate previously authorized 9-foot dredging area, and provided for dredging 30-foot-depth area and 18 acres off the municipal pier and for construction of the breakwater off Punta Carenero Eliminate previously authorized 18-foot and a portion of the 30-foot project outside the proposed 36-foot and a portion of the adjacent to the municipal bulkhead. Channel 36 x 600 feet from Caribbean Sea to harbor; channel 36 x 400 feet into harbor; and a 36-foot turning basin. PORT EVERGLADES HARBOR, FLA. (See Section 27 of Text) Maintenance of harbor constructed by local interests Enlarge entrance channel and complete turning basin to 1,200 feet square Widen turning basin 350 feet on north side Widen turning basin 200 feet on north side, 500 feet on south side and enlarge flare at entrance channel Deepen and widen entrance channel on a new alinement and increase turning basin in size and depth Deepen and widen entrance channel, enlarge turning basin, widen Pier 7 channel, maintenance of Berth 18 channel, and planning for a south jetty fishing walkway with construction contingent upon need as developed by detailed postauthorization studies REMOVAL OF AQUATIC GROWTH FROM NAVIGABLE WATERS IN THE STATE OF FLORIDA (See Section 28 of 'lbxt) Construction and operation of a suitable vessel and use of log booms for removal of water hyacinths in the navigable waters of the State Recommended by Chief of Engineers to Public Works Administration October 17, 1934 H.Doc. 185. 73d Cong., 2d sess. and Rivers and Harbors Committee Doc 42, 74th Cong., 1st sess. H.Doc. 530, 78th Cong., 2d sess. H.Doc 704, 80th Cong., 2d sess. H.Doc 283, 86th Cong., 1st sess. (contains latest published map) H.Doc 74, 89th Cong., 1st sess. H.Doc 532, 67th Cong., 4th sess. Rivers and Harbors Committee Doc. 18, 72d Cong., 1st sess. H.Doc. 745, 79th Cong., 2d sess. H.Doc. 532, 94th Cong., 2d sess. H.Doc 357, 71st Cong., 2d sess. Rivers and Harbors Committee Doc. 25, 74th Cong., 1st sess. H.Doc. 545, 75th Cong., 3d sess. H.Doc. 768, 78th Cong., 2d sess. H.Doc. 346, 85th Cong., 2d sess. H.Doca 144, 93d. Cong., 1st sess. Annual Report 1899 9-37 TABLE 9-B (Continued) REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 AUTHORIZING LEGISLATION Acts Work Authorized Documents June 13, 1902 March 3, 1905 June 20, 1938 May 17, 1950 March 3, 1899 March 2, 1919 June 14, 1880 June 25, 1910 July 3, 1930 March 2, 1945 March 2, 1945 July 24, 1946 March 2, 1945 November 7, 1966 H.R. May 9, 1974 S.R. May 31, 1974 August 8, 1917 September 22, 1922 July 3, 1930 August 30, 1935 August 26, 1937 Extermination and removal of water hyacinths by any mechanical, chemical, or other means Prohibits use of any chemical process injurious to cattle ST. AUGUSTINE HARBOR, FLA. (See Section 29 of Text) Channel 27 x 200 feet protected by a groin Channel 16 x 200 feet across bar, and thence 12 feet deep to Intracoastal Waterway; jetty on south side of inlet; future landward extension of groin and jetty; and channel 10 x 100 feet in San Sebastian River ST. JOHNS RIVER, FLA., JACKSONVILLE TO LAKE HARNEY (See Section 30 of LText) A channel 13 feet deep and 200 feet wide from Jacksonville to Palatka The improvement of Deep Creek Two jetties at Volusia Bar (Maintenance only; new work completed under previous project.) A channel 100 feet wide, 8 feet deep from Palatka to Sanford with a side channel to Enterprise, and thence 5 feet deep to Lake Harney Cutoffs at Butcher Bend, Shake Creek, and Starks Landing, and easing bends at other points A channel 10 feet deep and 100 feet wide from Palatka to Sanford, with a side channel to Enterprise and with cutoffs and easing of bends Combining the two projects above into a single project for St. Johns River, Fla., Jacksonville to Lake Harne, and for a cutoff 5 feet deep and 75 feet wide between Lake Monroe and the vicinity of Osteen Bridge (Woodruff Creek Cutoff) A channel 12 feet deep and 100 feet wide from Palatka to Sanford, and in the branch to Enterprise ST. LUCIE INLET, FLA. (See Section 31 of Tebxt) Channel 10 x 200 feet Modification to maintain existing channel 6 x 100 feet Extending north jetty and modifying existing jetty to provide a sand bypass weir section; excavation of sand impoundment basin; construction of south jetty with walkway for recreational fishing; channel 10 x 500 feet thru bar cut, tapering to 150 feet thru the inlet, and 100 feet and 7 feet deep to the Intracoastal Waterway; and transfer of 380,000 cubic yards of material to the south beach during each two-year maintenance period SAN JUAN HARBOR, P.R. (See Section 32 of Text) Anchorage (inner harbor) area of 206 acres and San Antonio Channel to 30-foot depth Substitution of a 68-acre area 30 feet deep along southeasterly side of anchorage area, for one 25 acres in extent and of same depth extending easterly from eastern end of the San Antonio project channel Modified condition of local cooperation Entrance channel across outer bar 38 feet deep and 800 feet wide, and thence across bay to anchorage area (Anegado Reach Channel) 30 feet deep and 700 feet wide and increasing anchorage area to 239 acres to 30-foot depth Widening Anegado Reach Channel and increasing anchorage area to 329 acres Specified in Act Specified in Act H.Doc. 555, 75th Cong., 3d sess. H.Doc 133, 81st Cong., 1st sess. H.Doc. 523, 55th Cong., 2d sess. and Annual Report for 1989, p. 1343 H.Doc. 699, 63rd Cong., 2d sess. Annual Report for 1879, pp. 795-798 H.Doc 1111, 60th Cong., 2d sess. H.Doc. 691, 69th Cong., 2d sess. H.Doc. 603, 76th Cong., 3d sess. H.Doc. 445, 78th Cong., 2d sess. S.Doc. 208, 79th Cong., 2d sess. H.Doc. 391, 77th Cong., 1st sess. H.Doc. 508, 89th Cong., 2d sess. H.Doc. 294, 93rd Cong., 1st sess. H.Doc 865, 63d Cong., 2d sess. Specified in Act H.Doc. 45, 71st Cong., 2d sess. R&H Comm. Doc. 38, 74th Cong., 1st sess. R&H Comm. Doc. 42, 75th Cong., 1st sess. 9-38 TABLE 9-B (Continued) JACKSONVILLE, FLA. DISTRICT AUTHORIZING LEGISLATION Acts Work Authorized Documents October 17, 1940 March 2, 1945 July 3, 1958 August 4, 1976 March 3, 1899 March 3, 1905 June 25, 1910 August 8, 1917 March 3, 1899 September 22, 1922 July 3, 1930 August 30, 1935 June 20, 1938 Do. Removal to 8-foot depth of Anegado, Largo, and Capitanejo Shoals, and dredging to 30-foot depth the entrance channel and turning basin to the Graving Dock Maintenance of the 30-foot depth entrance channel and turning basin to the Army Terminal Deepening portions of entrance and approach channels and basins to Army Terminal and San Antonio Pier areas to 35-45 feet; new 32-foot depth Puerto Nuevo Channel; new 36-foot depth anchorage A bar channel 48 by 800 feet, shifting the centerline 350 feet west; deepening Anegado Channel in steps from 46 to 40 feet while reducing width to 800 feet; deepening Army Terminal Channel and turning basin to 40 feet while widening the channel to 450 feet; deepening Puerto Nuevo Channel to 40 feet and widening it to 400 feet; deepening Graving Dock Channel to 40 feet at existing 400-foot width; deepening San Antonio Channel to 38 feet at varying widths, minimum of 500 feet; deepening cruise ship basin to 36 feet at an irregular width; maintaining Sabana Approach Channel at 30 by 250 feet- provide a 38-foot depth in Anchorage Area "E" with irregular width; six mooring dolphins for vessels using the area. TAMPA HARBOR, FLA. (See Section 33 of Text) TAMPA BAY For a channel 27 feet deep from the Gulf of Mexico to Port Tampa, 500 feet wide across the bar and 300 feet wide in the bay For a channel depth of 26 feet with sufficient width from the Gulf of Mexico to Port Tampa TAMPA AND HILLSBOROUGH BAYS For a depth of 24 feet in Hillsborough Bay For a 27-foot depth from Gulf of Mexico up to and in the several channels of Hillsborough Bay, the widths to be 500 feet on the bar, 300 feet in Tampa Ba, Ybor, and Garrison Channels, and 200 feet in Hillsborough Bay, Sparkman, and Seddon Channels, with turning basins at the mouth of Hillsborough and at Ybor Estuary HILLSBOROUGH RIVER For a 12-foot channel to within 100 feet of the Lafayette St. highway bridge (maintenance only; new work completed under a previous project under the title Improving Hillsborough Bay, Fla.) TAMPA HARBOR Consolidation of the above projects to form a single project for Tampa Harbor Increasing the depth of Egmont Channel to 29 feet and the width of Sparkman Channel to 300 feet For a depth of 32 feet and a width of 600 feet on Egmont Bar, a depth of 30 feet and a width of 400 feet in Mullet Key Cut, and a depth of 30 feet and a width of 300 feet in all other project channels in Tampa Harbor (except in Hillsborough River and in the channel leading to Alafia River); and for a turning basin 2,000 feet long and 500 feet in maximum width at the entrance to the Port Tampa terminals For widening the bend between Sparkman Channel and Cut D of Hillsborough Bay Channel by 250 feet; widening Ybor Channel to 400 feet and extending the turning basin at the west end of Garrison Channel (mouth of Hillsborough River) easterly for 300 feet For construction of a breakwater at Peter O. Knight Field, Davis Islands, its maintenance to be assumed by local interest H.Doc. 364, 76th Cong., 1st sess. Specified in Act H.Doc. 38, 85th Cong., 1st sess. H.Doc. 574, 94th Cong., 2d sess. H.Doc 52, 55th Cong., 3d sess. (Also printed in Annual Report 1899, p. 1640) Channel dimensions specified in Act Specified in Act H.Doc. 634, 61st Cong., 2d sess. H.Doc 634, 61st Cong., 1st sess. H.Doc. 545, 55th Cong., 2d sess. and Annual Report 1898, pp. 1357-1360 Specified in Act H.Doc 100, 70th Cong., 1st sess. S.Doc. 22, 72d Cong., 1st sess. S.Doc 164, 75th Cong., 3d sess. Sen. Comm. Print. 76th Cong., 1st sess. 9-39 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 9-B (Continued) AUTHORIZING LEGISLATION Acts Work Authorized Documents March 2, 1945 Do. Do. May 17, 1950 September 3, 1954 October 23, 1962 December 31, 1970 Do. Do.- Do. Do. Do. Do. Do. Do. Do. Do. Do. Do. Do. Do. For widening Sparkman Channel to 400 feet and Ybor Channel to 500 feet; widening the bend between Sparkman and Garrison Channels an additional 250 feet to extend the turning basin westerly; and widening the bend between Seddon and Garrison Channels by 150 feet (in lieu of 300 feet previously authorized) to extend the turning basin easterly For a channel 9 feet deep and 100 feet wide in the Hillsborough River for about 2.4 miles above the upper end of the existing 12-foot channel, and for the removal of obstructions thence to the Florida Avenue Bridge For a channel 25 feet deep and 150 feet wide from the Hillsborough Bay channel to and including a turning basin in the Alafia River (Revoked by Act of May 17, 1950) For deepening Egmont Channel to 36 feet; enlarging Mullet Key Cut, Tampa Bay Channel, Hillsborough Bay Channel, Port Tampa Channel and Port Tampa turning basin to present project dimensions; deepening Sparkman Channel and Ybor turnig basin to 34 feet; a channel 30 feet deep and 200 feet wide from Hillsborough Bay Channel to and including a turning basin in Alafia River, 700 feet wide and 1,200 feet long (in lieu of the improvement previously authorized); and substantial widening at entrance, bends, and turns Extended removal of obstructions in Hillsborough River to City Water Works Dam. Maintenance of cleared channel to be assumed by local interests Channel and turning basin at Port Sutton 30 feet deep, Ybor Channel 34 x 400 feet For federal maintenance of Port Sutton Channel, 280 feet wide and an irregularly shaped turning basin both to a depth of 34 feet Enlarge entrance channel across Egmont Bar to 46 x 700 feet from the Gulf to Mullet Key Enlarge Mullet Key Cut Channel to 44 x 600 feet Enlarge Tampa Bay Channel to 44 x 500 feet from Mullet Key Cut through Tampa Bay to the junction of Hillsborough Bay and Port Tampa Channels Enlarge Hillsborough Bay Channel to 44 x 500 feet from the junction with Tampa Bay and Port Tampa Channels to the junction with Port Sutton entrance channel, and thence deepening to a depth of 42 feet at the existing width of 400 feet to the junction with Seddon and Sparkman Channels Enlarge Port Sutton entrance channel to 44 x 400 feet Enlarge Port Sutton turning basin to a depth of 44 feet and a turning diameter of 1,200 feet Deepening Sparkman Channel to 42 x 400 feet Deepening Ybor Channel to 40 x 300 feet Enlarge turning basin at the entrance to Ybor Channel to a depth of 42 feet and an additional width of 200 feet on the southwest edge of the present basin Deepening Port Tampa Channel to 42 feet at its existing width from the junction with Hillsborough and Tampa Bay Channels to the turning basin Deepening the Port Tampa turning basin to 42 feet over its existing length of 2,000 feet and width of 900 feet An entrance channel in East Bay 44 x 400 feet and 500 feet north from the Port Sutton turning basin for a distance of about 2,000 feet A turning basin in East Bay at a depth of 44 feet and with a turning diameter of 1,200 feet An approach channel in East Bay 44 x 300 feet north from the East Bay turning basin for a distance of about 2,500 feet S.Doc. 183, 78th Cong., 2d sess. H.Doc 119, 77th Cong., 1st sess. S.Doc. 16, 77th Cong., 1st sess. H.Doc 258, 81st Cong., 1st sess. H.Doc. 567, 81st Cong., 2d sess. H.Doc 529, 87th Cong., 2d sess. H.Doc 150, 91st Cong., 1st sess. H.Doc 401, 91st Cong., 2d sess. Do. Do. Do. Do. Do. Do. Do. Do. Do. Do. Do. Do. Do. 9-40 TABLE 9-B (Continued) JACKSONVILLE, FLA. DISTRICT AUTHORIZING LEGISLATION Acts Work Authorized Documents Do. August 15, 1985 BEACH EROSION CONTROL PROJECTS August 13, 1968 October 27, 1965 August 13, 1968 August 15, 1985 October 27, 1965 December 19, 1979 By Chief of Engineers under section 103 of the 1962 River and Harbor Act October 27, 1965 October 23, 1962 November 7, 1966 FLOOD CONTROL PROJECTS June 30, 1948 September 3, 1954 July 14, 1960 October 23, 1962 Maintenance of Port Sutton Terminal channel to 44 x 200 feet for a distance of 4,000 feet Maintenance of East Bay channel to 34 x 300 feet for a distance of 5,500 feet BREVARD COUNTY, FLA. (See Section 37 of Text) Federal participation in cost of shore protection project BROWARD COUNTY, FLA., BEACH EROSION CONTROL AND HILLSBORO INLET, FLA., NAVIGATION PROJECT (See Section 38 of Text) Improvement for beach erosion control in Broward County, Fla. and a combined beach erosion and navigation improvement to Hillsborough Inlet and the shore south thereof to Port Everglades DADE COUNTY, FLA. (See Section 39 of Text) Federal participation in cost of shore protection and hurricane-flood control project DADE COUNTY-NORTH OF HAULOVER BEACH, FLA. (See Section 40 of Text) Federal participation in cost of shore protection and hurricaneflood control project. DUVAL COUNTY, FLA. (See Section 41 of Text) Federal participation in cost of shore protection project EL TUQUE BEACH, PONCE, P. R. (See Section 42 of ext) Placement of about 60,000 cubic yards of fill material along eroded shoreline. Build a shore connected rubble breakwater and offshore breakwater to stabilize the fill material FORT PIERCE, FLA. (See Section 43 of lText) Federal participation in cost of local shore protection projects PALM BEACH COUNTY, FLA., FROM MARTIN COUNTY LINE TO LAKE WORTH INLET AND FROM SOUTH LAKE WORTH INLET TO BROWARD COUNTY LINE (See Section 44 of Text) Federal participation in cost of local shore protection project and sand-transfer plant PINELLAS COUNTY, FLA. (See Section 45 of Text) Federal participation in cost of shore protection project CENTRAL AND SOUTHERN FLORIDA (See Section 48 of ext) First phase of comprehensive plan for flood control and other purposes Modification and expansion of authorization to include entire comprehensive plan of improvement Canals, levees, and water-control and drainage structures in the Nicodemus Slough area, Glades County Flood protection on Boggy Creek, near Orlando Do. H.Doc. 236, 99th Cong., 1st. sess. H.Doc. 352, 90th Cong., 2d sess. H.Doc. 91, 89th Cong., 1st sess. H.Doc. 335, 90th Cong., 2d sess. H.Doc. 236, 99th Cong., 1st sess. H.Doc. 273, 89th Cong., 1st sess. H.Doc. 84, 89th Cong., 1st sess. H.Doc. 164, 87th Cong., 1st sess. H.Doc. 519, 89th Cong., 2d sess. H.Doc. 643, 80th Cong., 2d sess. (Contains latest published map) H.Doc. 643, 80th Cong., 2d sess. S.Doc. 53, 86th Cong. 1st sess. S.Doc. 125, 87th Cong., 2d sess. 9-41 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 9-B (Continued) AUTHORIZING LEGISLATION Acts Work Authorized Documents Do. Do. Do. Do. October 27, 1965 Do. August 13, 1968 Do. Approved December 17, 1970 under the provisions of Section 201 of the Flood Control Act of 1965 October 23, 1962 December 31, 1970 Flood protection in the Cutler Drain area, near Miami Flood control and drainage works for South Dade County Project for Shingle Creek between Clear Lake and Lake lbhopekaliga for flood control and major drainage, including development of Reedy Creek Swamp Improvement of easterly section of West Palm Beach Canal for flood control and major drainage Primary works for flood control and major drainage in southwest Dade County Primary works for flood control and major drainage in Hendry County Gravity drainage in Martin County and distribution of available water supplies to portions of Martin and St. Lucie Counties Improvement of supply distribution, and conservation of water resources in Central and Southern Florida, including Lake Okeechobee agricultural area, Everglades National Park and other related areas. Navigation improvements suitable for recreational craft FOUR RIVER BASINS, FLA. (See Section 49 of Text) Control of floods and improvement of drainage, and for water conservation through construction of necessary canals, levees, reservoirs, and control structures PORTUGUES AND BUCANA RIVERS, P.R. (See Section 50 of Text) LAGO de CERRILLOS, P.R. Multiple purpose dam and lake for flood control, water supply, and recreation LAGO de PORTUGUES, P.R. Multiple purpose dam and lake for flood control, water supply and recreation PONCE, P.R. Diversion and enlargement of existing channels through Ponce for flood control S.Doc. 123, 87th Cong., 2d sess. S.Doc 138, 87th Cong., 2d sess. S.Doc 139, 87th Cong., 2d sess. S.Doc. 146, 87th Cong., 2d sess. S.Dos 20, 89th Cong., 1st sess. H.Doc 102, 88th Cong., 1st sess. S.Doc. 101, 90th Cong., 2d sess. H.Doc. 369, 90th Cong., 2d sess. H.Doc. 394, 91st Cong., 2d sess. H.Doc. 585, 87th Cong., 2d sess. H.Doc. 422, 91st Cong., 2d sess. 9-42 JACKSONVILLE, FLA. DISTRICT TABLE 9-C CANAVERAL HARBOR, FLA. PROJECT DATA RELATIVE TO LOCK (See Section 5 of 'ext) Distance to nearest town 9.9 miles via 12-foot barge canal and Intracoastal Waterway Name of nearest town Cocoa, Fla. Distance from Intracoastal Waterway 6.5 miles Lock Dimensions 90' wide; 600' long Lift Varies with tide Depth of sills (mlw, ocean) 14 feet Character of foundation Piles in sand Year completed and opened to navigation 1965 Contract cost $2,966,539 156 x 400 feet authorized. At request of NASA lock was constructed increased to 600 feet to be compatible with increased width. Opera- 90 feet wide with NASA bearing additional cost ($700,000). Length tion and maintenance of lock is a Federal responsibility. TABLE 9-D CROSS-FLORIDA BARGE CANAL PROJECT LOCKS AND DAMS (See Section 8 of Text) R. N. Henry H. Buckman Eureka Lock Bert Dosh Dunnellon Inglis Lock Lock and Dam Lock Lock and Dam Nearest town Palatka, Sparr, Ocala, Dunnellon, Inglis, (miles) 11.2 15.8 8.9 2.5 3.2 Miles from Atlantic Intracoastal Waterway 90.4 111.4 127.7 156.5 168.6 Lock dimensions (ft.)1 84 x 600 84 x 600 84 x 600 84 x 600 84 x 600 Normal lift (ft.) 20 20 0-152 12-272 28 Depth over sills at normal pool levels: Upper (ft.) 14 17 16-312 16-312 18 Lower (ft.) 15 14 16 18 15 Character of Piles in Piles in Piles in Rock Rock foundation sand sand sand Kind of dam Movable Movable None None Movable Type const. Earths Earths - - Earths Percent complete 100 100 0 0 100 Estimated contract cost $6,094,000 $7,975,000 $7,430,000 $9,500,000 $7,800,000 1Clear width and greatest available length. 2Pool 'level varies with natural ground water profile from minimum elevation of 40 feet to maximum elevation of 55 feet. $With concrete spillway and movable gates. 9-43 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 9-E CROSS-FLORIDA BARGE CANAL OPERATIONS AND RESULTS DURING FISCAL YEAR (See Section 8 of Text) Work Performed Cost New Work: Recreation Facilities $ 80,000 Engineering and Design 162,145 lTotal 242,145 Operation and Maintenance: Operations of locks, operations and maintenance of dams, spillways reservoirs and bypasses, debris removal, performance monitoring system 467,616 Contract maintenance of locks, grounds maintenance, trash removal, potable water testing 67,165 Visitor Assistance 17,811 Operation and maintenance of recreation facilities, sanitary facilities, service and maintenance of traffic counters and contract mainenance of grounds 264,246 Condition and operations studies and periodic inspections 88,996 Water quality studies, data collection and processing, reimbursement to USGS, water control analysis, Lake Oklawaha and Inglis Bypass, and water management control 111,797 Supervision and Administration 26,170 Total 1,043,801 Maintenance: Maintenance of dams and spillways, contracts for dewatering Buckman Lock and Inglis Spillway Gate Repair 126,627 Maintenance of roads, bridges 11,170 Maintenance of permanent operating equipment (other than recreation) 197,751 Bank stabilization-maintenance of slopes and berms, Rodman and Inglis dams, and bank stabilization contract. 84,189 Maintenance of canals, clearing and snagging 51,242 Engineering and Design 62,361 Supervision and Inspection 5,268 Real Estate 1,347 539,955 Income Credits -4,958 Total $1,578,798 Income from Recreation Fees $ 20,188 9-44 JACKSONVILLE, FLA. DISTRICT TABLE 9-F OKEECHOBEE WATERWAY OPERATIONS AND RESULTS DURING FISCAL YEAR (See Section 22 of Text) Work Performed Cost New Work: Engineering and Design $ 262 Operations: Operations of Locks, Real Estate Management and Performance Monitoring System 650,103 Contract maintenance buildings grounds, potable water testing, repair and replacement of project signs, operation and maintenance of District communications network 301,971 Visitor Assistance, operation of recreation facilities, service and maintenance of traffic counters 170,370 Operation and maintenance of slope protection, St. Lucie Lock 99,457 Condition and operation studies, periodic inspections 36,018 Supervision and Administration 33,339 Sub-Ibtal 1,291,258 Maintenance: Maintenance of locks, roads, levees and contract maintenance of locks 168,505 Natural Resource Facilities 19,221 Maintenance of permanent operating equipment 352,298 Bank Stabilization, St. Lucie Lock 53,399 Snagging and Clearing and Excavation 87,387 Engineering and Design 18,925 Supervision and Inspection 32,018 Real Estate administrative activities 29,868 Sub-ZIbtal 761,621 Income Credits -30,625 lbtal $2,022,254 Income from Recreation Fees 11,087 9-45 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 9-G REMOVAL OF AQUATIC GROWTH FROM NAVIGABLE WATERS IN THE STATE OF FLORIDA CONTROL OPERATIONS (See Section 28 of 'bxt) Locality Acres Controlled Cost St. John's River and tributaries and Withlacoohee, Kissimmee and Crystal Rivers 19,729 $2,128,612 Okeechobee Waterway and tributaries 9,492 99,000 Acquisition and maintenance of airboats, engines, and work tools 65,686 Income credits -642 Operation of communications network 20,000 Engineering design 38,586 Supervision and Administration 99,589 'Ibtal 29,221 2,450,831 TABLE 9-H NAVIGATION PROJECTS ON WHICH RECONNAISSANCE AND CONDITION SURVEYS ONLY WERE CONDUCTED DURING FISCAL YEAR (See Section 34 of 'Txt) Date Cost Incurred Survey During Project Conducted Period Arecibo Harbor, P.R. FY 1985 $ 253 Bakers Haulover Inlet, Fla. FY 1985 6,710 Channel from Naples to Big Marco Pass, Fla. FY 1985 8,296 Christiansted Harbor, V.I. FY 1985 6,285 Crystal River, Fla November 1984 9,771 Everglades Harbor, Fla. FY 1985 115 Fort Myers Beach, Fla. FY 1985 1,464 Fort Pierce Harbor FY 1985 7,214 Homosassa River, Fla. FY 1985 86 Horseshoe Cove, Fla. October 1984 685 Intracoastal Waterway, Jacksonville to Miami FY 1985 19,962 Intracoastal Waterway, Miami to Key West August 1984 294 Johns Pass FY 1985 9,839 Key West Harbor, Fla. August 1985 2,408 Mayaguez Harbor, P.R. FY 1985 16 Melbourne Harbor, Fla. FY 1985 1,994 Miami Harbor, Fla FY 1985 6,512 Oklawaha River, Fla. December 1984 62 Orange River, Fla. May 1985 961 Ozona, Fla. May 1985 306 Pass-A-Grille Pass, Fla. FY 1985 16 Ponce De Leon Inlet, Fla. July 1983 846 Ponce Harbor, P.R. FY 1985 131 Port Everglades Harbor, Fla. January 1985 39,589 Rice Creek, Fla. May 1985 1,037 St. Johns River, Jacksonville to Lake Harney, Fla. FY 1985 2,991 St. Petersburg, Fla. FY 1985 24 San Juan Harbor, P.R. FY 1985 229 Withlacoochee River, Fla. June 1985 4,447 Engineering and Design 360 Supervision and Administration 195,459 9-46 JACKSONVILLE, FLA. DISTRICT OTHER AUTHORIZED NAVIGATION PROJECTS (See Section 35 of 'bxt) For Last Cost to Sept. 30, 1985 Full Report See annual Operation and Project Report For Construction Maintenance Anclote River, Fla. 1974 267,427 607,465 Aquatic Plant Control, Fla.' H Acts of 1958 & 1962) 1968 2,619,7002 - Aantic Gulf Ship Canal, Fla. 1939 5,099,153 - Bayport, Flas 1972 58,4954 - Cedar Keys Harbor, Fla 1977 168,5696 60,362 Christiansted Harbor. St. Croix. V.I.,6 1964 303,317 50,872 Clearwater Pass, Fla.2 1 1980 46,3497 1,209,505 Courtenay Channel, Fla.1 1940 22,846 18,808 Crystal River, Fla? 1941 25,000 103,309 Everglades Harbor Fla.' 1964 221,5098 50,919 Fjardo Harbor, PR.3 1945 - - Guayanes Harbor, P.R.8 1945 -- Gulf Intracoastal Waterway St. Marks to Tampa Bay, Fla.8 1974 38,850 - Homosassa River, Fla.? 1937 3,9999 23,248 Horseshoe Cove, Fla. 1977 347,521 136,808 Hudson River, Fla.8 1974 9,889 - Intracoastal Waterway, Miami to Key West, Fla.3 1963 243,079 27,752 Key West Harbor, Fla.' 1972 1,548,89210 531,366 Kissimmee River, Fla.' 1931 23,479 89,113 Lake Crescent and Dunns Creek, Fla."1 1931 10,276 9,035 Largo Sound Channel, Fla. 1, 12 1966 117,44313 41,340 Little Manatee River, Fla. 8, 11 1949 11,90314 - Manatee River, Fla.' 1970 123,350 184,221 New River Fla? 1956 36,518 23,582 Orange River, Fla.' 1962 2,000 23,567 Ozona, Fla., channel and turning basin' 1963 105,527 14,783 Palm Beach, Fla., side channel and basin3 1946 - - Pass-A-Grille Pass. Fla. 1, e16 1966 41,29717 53,669 Pithlachascotee River, Fla. 1973 400,00018 253,516 Rice Creek, Fla.' 1957 85,20819 17,777 St. Petersburg Harbor, Fla. 1983 255,60820 1,536,60621 St. Thomas Harbor. V.I.3 1949 1,989 - Steinhatchee River, Fla.' 1940 135,053 43,329 Suwannee River, Fla.' 1977 76,41822 195,972 Withlacoochee River, Fla 15 1969 614,91228 365,858 1. Complete. 2. Excludes $918,205 contributed funds. 3. Inactive. 4. Includes $41,222 for reconnaissance and detailed project reports under Section 107 of the R&H Act of 1960. 5. Includes $82,500 expended under previous project. Excludes $1,473 contributed funds. 6. Project as modified by Chief of Engineers in report of June 30, 1961, is complete. Previously authorized depth of 25 feet in inactive status. 7. Excludes $42,783 contributed funds. 8. Excludes $36,000 contributed funds. 9. In addition, $1,000 expended from contributed funds. 10. Includes $27,500 for new work under previous project. Excludes $35,371 contributed funds. 11. Deauthorized by Public Law 93-251, Section 12. 12. Authorized April 20, 1964 by Chief of Engineers under Section 107 of 1960 R&H Act. 13. Includes $25,008 for detailed project report but excludes $86,716 expended from contributed funds. 14. Expended on restudy. 15. Inactive portion of project deauthorized by Public Law 93-251, Section 12. 16. Authorized November 19, 1964 by Chief of Engineers under Sections 107 of R&H Act of 1960. 17. Excludes $41,297 contributed funds. 18. Excludes $215,728 contributed funds. 19. Excludes $93,000 contributed funds. 20. Includes $32,689 under previous project. 21. Includes $20,532 under previous project. 22. Includes $10,154 expended under previous project. 23. Includes $30,000 expended under previous project. 9-47 TABLE 9-I REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 9-J OTHER AUTHORIZED BEACH EROSION PROJECTS (See Section 46 of Text) For Last Cost to Sept. 30, 1985 Full Report See annual Operation and Project Report For Construction Maintenance Cape Florida State Park 1969 34,8621 - Key West, Fla. 1963 96,3402 3,794 Lee County, Fla. 1971 - - Lido Key, Fla. 1971 - - Mullet Fla. 1973 436,2013 1,656 Manatee County, Fla. 1983 217,600 - Punta Salinas P.R. 1984 855,5114 - Palm Beach County Fla., from Lake Worth Inlet to South Lake Worth Inlet 1970 195,1406 6,257 San Juan Puerto Rico 1965 - - Virginia key and Key Biscayne, Fla. 1978 1,667,2206 1,022 1. Includes $2,462 cost of reconnaissance and detailed project 4. Excludes $360,000 contributed funds. reports but excludes $13,818 contributed funds. 5. Excludes $781,188 in property or services furnished by local 2. Excludes $192,168 contributed funds. interests in lieu of cash contribution. 3. Excludes $187,133 contributed funds. 6. Excludes $714,522 contributed funds. TABLE 9-K CENTRAL AND SOUTHERN FLORIDA PROJECT PRINCIPAL FEATURES OF HURRICANE GATES (See Section 48 of Text) Depth Character Over of Year Gate' Nearest 'bwn Distance Sills Founda- Com- Actual No. Name (miles) (ft.) tion pleted Cost 2. Clewiston Fla. 0.5 10 Pile 1935 $309,748 3. Lake Harbor, Fla. 0.5 10 Rock 1935 316,938 4. Belle Glade, Fla. 4.0 10 Rock 1935 350,025 5. Canal Point, Fla. 0.0 10 Rock 1935 262,465 6. Okeechobee, Fla. 0.5 7 Pile 1936 373,273 1All are 50 feet wide with available length unlimited. They are constructed of concrete with steel sector gates and have no lift. Gate No. 6 has an auxiliary culvert spillway with automatic control. Moore Haven Lock serves as Hurricane Gate Structure 1. 9-48 CENTRAL AND SOUTHERN FLORIDA PROJECT PRINCIPAL FEATURES OF LOCKS AND DAMS (See Section 48 of Tebxt) Miles Elevation From Lock Normal of Normal Character Kind Kind Nearest Nearest Dimensions lift Pool Depth of of of of -Percent Contract Tolbwn Tbwn (ft.) (ft.) surface (ft.) sills (ft.) foundation Dam Construction Complete Cost W.P. Franklin At Olgya 0 56 x 400 2.5 3.0 14 Piles in - -I- - -3 _ - -I _1_ Lock and Dam" S-65 Lock S-65A Lock S-65B Lock S-65C Lock S-65D Lock S-65E Lock Moore Haven Lock (HGS-1 Mod.) S-310 (HGS-2 Mod.) S-193 (HGS-6 Mod.) S-308B (Port Mayaca) S-57 S-58 S-59 S-60 S-61 S-62 S-63 S-63A S-96 S-96A S-53 S-55 S-157 S-158 Frostproof Avon Park Sebring Sebring Okeechobee Okeechobee Hoore Haven Clewiston Okeechobee Pahokee Ashton Ashton Kissimmee Ashton St. Cloud Ashton Ashton Ashton Sebastian Sebastian Eau Gallie Christmas Sebastian Titusville 23 26 20 25 14 10 0.5 0.5 0.5 11 9 5666 10 12 14 14 16 8 12 4 15 30 x 90 30 x 90 30 x 90 30 x 90 30 x 90 30 x 90 50 x 250 50 x 60 50 x 60 56 x 400 20 x 90 20 x 90 20 x 90 20 x 90 30 x 90 20 x 90 20 x 90 20 x 90 20 x 60 20 x 60 20 x 60 20 x 60 20 x 60 20 x 60 4.2 6.3 6.0 7.2 5.8 4.6 9.4 5.0 7.5 4.0 1.0 2.0 3.0 2.0 2.0 3.0 5.0 4.5 4.0 7.5 3.5 10.0 20.0 4.5 48.5-52.33 46.3 40.0 34.0 26.8 21.0 15.5-17.5- 15.5-17.53 15.5-17.53 15.5-17.53 62.0 64.0 58.0 64.0 55.0 61.0 62.0 57.0 24.0 25.0 17.5 14.0 20.0 4.0 6 6 6 6 6 6 11 12.9 7.5 18 6 6666666666666 clay Earth foundation, sand Earth foundation, sand Earth foundation, sand Earth foundation, sand Earth foundation, sand Earth foundation, sand Piles in sand Slab on sand Piles in sand and slab on sand Slab on sand Earth foundation, sand Da Doa Da Da Da Da Da Da Da Da Da Da Do. Operation and care of W.P. Franklin Lock and Dam (S-79) is a Federal responsibility. 'The normal pool level varies seasonally between the two elevations. 2Estimated (Oct 1984). TABLE 9-L Movable Reinforced concrete None Reinforced concrete rigid frame None Reinforced concrete rigid frame None Reinforced concrete rigid frame None Reinforced concrete rigid frame None Reinforced concrete rigid frame None Reinforced concrete None Steel sheet pile lockwalls None Reinforced concrete None Reinforced concrete Fixed Reinforced concrete None Concrete and steel sheet pile None Do. None Do. None Do. None Do.a None Do. None Do. None Do. None Do. None Do. None Do. None Do. None Do. None Do. CD e 100 100 100 100 100 100 100 0 100 0 100 0 000 100 00000000 0 $3,803,655.00 $1,191,574.70 $1,513,693.91 $1,050,600.69 $1,326,073.12 $1,213,248.51 $1,320,039.84 $360,0002 $3,448,406 $511,300.002 $8,308,700.00 $1,957,000.002 $1,957,000.002 $1,953,000.002 $1,957,000.002 $689,217.00 $1,957,000.002 $1,957,000.002 $1,916,000.002 $1,716,000.002 $1,633,000.002 1,585,000.002 1,625,000.002 $2,066,000.002 $1,868,000.002 Cn z v TABLE 9-M REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 CENTRAL AND SOUTHERN FLORIDA PROJECT LOCAL COOPERATION (See Section 48 of Text) Flood Control Act Work Authorized Cash Contributions1 June 30, 1948 First phase of comprehensive plan 15.0 Sept. 3, 1954 Second phase of comprehensive plan 20.0 July 14, 1960 Nicodemus Slough area 31.5 Oct. 23, 1962 West Palm Beach Canal 12.8 Boggy Creek Basin 29.7 Shingle Creek Basin 25.9 South Dade County area 19.2 Reedy Creek Swamp 50.0 Oct. 27, 1965 Southwest Dade County 46.0 Hendry County area 19.5 Aug. 13, 1968 Martin County Flood Control Features 34.0 Irrigation Features 49.0 Backflow Features 20.0 PL 89-72 Recreation Features 50.0 Water Resources - St. Lucie 20.0 Recreation Features 50.0 Approved Dec. 17, 1970 Navigation improvements suitable for 50.0 under Provisions of recreational craft Section 201 of 1965 Flood Control Act 'Computed on total contract cost and supervision and administration except for Reedy Creek Swamp and Recreation Features which are computed on all costs, including engineering and design and land. 9-50 JACKSONVILLE, FLA. DISTRICT TABLE 9-N CENTRAL AND SOUTHERN FLORIDA PROJECT OPERATIONS AND RESULTS DURING FISCAL YEAR (See Section 48 of Text) Work Performed Cost New Work: Construction of: Channels and canals $ 171,428 Levees 3,870,624 Floodway control and diversion structures 1,338,925 Pumping Plants 293,182 Cultural Resource Preservation 4,068 Depreciation -830 Engineering and design 2,296,043 Supervision and administration 496,810 'Ibtal applied cost 8,470,250 Operations: Operation of locks, real estate management, performance monitoring system 559,782 Maintenance of buildings and grounds, operation and maintenance of District communications network, repair and replacement of project signs 209,350 Patrol, inspection and maintenance of Herbert Hoover Dike, HGS 3, 4, and 5, operation and maintenance of drainage ditches, culverts and 16 spillways, mowing of levees 520,289 Visitor Assistance 57,358 Operation and Maintenance of recreation facilities, service and maintenance of traffic counters, master planning 152,896 Condition and operation studies, periodic inspections, NOAA, dam safety 189,731 Regulation of Lake Okeeshobee and three conservation areas, water control analysis, water quality studies, and data collection 667,632 Supervision and Administration 55,648 Sub-Ibtal 2,412,686 Maintenance: Contract maintenance of locks 240,000 Contract maintenance of roads 79,491 Repair and stabilization of Crown Road, Herbert Hoover Dike, removal of weeds, rebuilding and regrading of levee slopes, modification and maintenance of safety barriers, HGS 3, 4 and 5, cleaning landslide toe ditches, repair of culverts, replacement of fences, removal of trees, topping of trees, control of Melaleuca, rip rapping of slopes and berms 536,632 Maintenance of hydrometrological network, maintenance of permanent operating equipment 774,652 Maintenance of berms, fences and shrubs 26,894 Clear landslide entrance channel to culverts, approach channels, hurricane gate structures and floodway channels 149 Engineering and Design 115,014 Supervision and Inspection 74,944 Real estate administration 2,412 Sub-Ibtal 1,850,188 Income Credits - 7,894 'Ibtal 4,254,980 Income from recreation fees 23,074 9-51 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 9-0 CENTRAL AND SOUTHERN FLORIDA PROJECT CONSTRUCTION COMPLETED UNDER EXISTING PROJECT DURING FISCAL YEAR (See Section 48 of Text) Date transferred to Flood Control District Construction for Operation and Feature Period Maintenance Channels and Canals: C-103 March 1979 - February 1983 Feb. 1983 Pumping Plants: S-331 March 1979 - February 1983 Feb. 1983 TABLE 9-P CENTRAL AND SOUTHERN FLORIDA PROJECT STATUS OF WORK UNDER CONTRACT AT END OF FISCAL YEAR (See Section 48 of Tebxt) Construction Approx. % Feature Started Complete Bridges: B-127 (C-51) April 1983 100 Channels and Canals: C-51 East End May 1982 100 Levees: Herbert Hoover Dike Revetment 1st Contract (4 miles) March 1983 99 2nd Contract (4.5 miles) September 1983 99 3rd Contract March 1985 15 4th Contract August 1985 10 Structures: S-155 May 1982 100 S-65 A, B, C & D Baffle Blocks & Riprap Repair September 1983 99 9-52 JACKSONVILLE, FLA. DISTRICT FOUR RIVER BASINS, FLORIDA PROJECT MOSS BLUFF LOCK (See Section 49 of Text) Nearest town Name of nearest town Distance above mouth of River Lock dimensions Normal lift Elevation of normal pool surface Depth of sills Character of foundation Kind of dam ITyrpe of construction Percent complete Estimated Cost (including dam and spillway) 20 miles Ocala, Fla. 65.5 miles 30 x 125 feet 18.0 feet 58 feet 12 feet Piles in sand None Reinforced concrete 100 $1,990,138 TABLE 9-R FOUR RIVER BASINS, FLORIDA PROJECT CONDITION AT END OF FISCAL YEAR (See Section 49 of Text) Date transferred to Construction Southwest Florida Feature Period for Operation and Maintenance Bridges: B-194 July 1968 - Mar. 1970 Not transferred Alteration of Facilities B-195 May 1971 - Jan. 1973 Do. B-594 Jan. 1973 - Jan. 1974 Do. Alteration of Facilities B-196 Oct. 1972 - Jan. 1975 Do. SCL RR Br., B-196 Dec 1972 - July 1975 July 1975 Channels and Canals: C-135 May 1967 - Dec. 1968 Dec. 1968 C-135, Sec. 1A July 1966 - Aug. 1967 Oct. 1967 C-135, Sec. lB May 1968 - Sep. 1972 Not transferred C-135, Sec. 1C & 2 Jan. 1971 - Dec. 1973 Not transferred C-135, Sec. 3A Dec. 1972 - Apr. 1975 Oct. 1977 C-135, Sec. 3B Feb. 1975 - Aug. 1977 Not transferred C-135, Sec. 4A Apr. 1976 - Jan. 1979 Not transferred C-136 Aug. 1975 - May 1977 Nov. 1977 C-231, Phase I July 1973 - Apr. 1975 Dec. 1975 C-231, Phase II July 1973 - Jan. 1974 Dec. 1975 C-331 July 1967 - Sep. 1968 Sep. 1968 C-531 Apr. 1966 - Jan. 1969 Apr. 1969 C-534 June 1970 - July 1971 Nov. 1971 C-135 March 1977 - Oct. 1980 Structures: S-160 May 1967 - Dec. 1968 Dec. 1968 S-161 Aug. 1975 - May 1977 Nov. 1977 S-162 Apr. 1975 - June 1977 Apr. 1977 S-353 July 1967 - Sep. 1968 Nov. 1968 Moss Bluff Lock and Spillway Apr. 1967 - Mar. 1969 Dec. 1975 S-551 July 1970 - Feb. 1972 Not transferred Levees: L-212, Sec. 1 June 1968 - July 1970 Dec. 1975 L-212, Sec. 2 July 1970 - Sep. 1971 Dec. 1975 L-112 March 1977 - Oct. 1980 Oct. 1980 L-112 & Floodway May 1978 - July 1981 Jan. 1983 S-155 May 1978 - July 1981 Jan. 1983 S-163 May 1978 - July 1981 Jan. 1983 S-159 Middle & Lower April 1979 - Aug. 1981 Oct. 1981 S-159 Upper June 1979 - Sep. 1981 Recreation: Morris Bridge & Flint Creek Sites December 1982 - August 1984 Jan. 1985 9-53 TABLE 9-Q TABLE 9-S REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 OTHER AUTHORIZED FLOOD CONTROL PROJECTS (See Section 52 of Text) For Last Cost to Sept. 30, 1985 Full Report See Annual Operation and Project Report For Construction Maintenance Arch Creek, Dade County, Fla. 1960 $66,4851 Biscayne Bay, Fla., Hurricane Protection2 1966 - - Hillsborough Bay, Fla.2 1969 Phillippi Creek Basin, Fla.2 1966 - - 1. Excludes $11,734 cost of preauthorization studies. Project was 2. Deauthorized by Public Law 93-251, Section 12. authorized February 20, 1959, by Chief of Engineers under Section 205 of the 1948 Flood Control Act as Modified by P.L. 685, 84th Congress. TABLE 9-T FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION PURSUANT TO SECTION 205, PUBLIC LAW 685, (PREAUTHORIZATION) (See Section 53 of Text) Study Identification Period Costs Detailed Project Report: Alligator Creek Basin, CL Fla. $ 51,598 Bear Creek, Pinellas County, Fla. 63,945 Estate Mon Bijou, V.I. 11,091 Naquabo River, P.R. 3,616 Rio Cibuco, Vega Baja, PR. 42,918 Rio Tallaboa-Penuelas, P.R. 9,948 Sabana Grande, P.R. -833 Savan Gut-St. Thomas, V.I. 80 Seminole Basin-Largo, Fla. 29,654 Thrpentine Run, St. Thomas, V.I. 146 Wares Creek, Bradenton, Fla. 52,715 Whitaker Bayou, Sarasota, Fla. 7,223 9-54 MOBILE, AL., DISTRICT* This district comprises a small portion of southeastern Tennessee, western Georgia, western Florida, all of Alabama south of Tennessee River Basin, eastern Mississippi, and a small portion of southeastern Louisiana embraced in drainage basins tributary to the Gulf of Mexico, west of Aucilla River Basin, to and including the Pascagoula River Basin. The Pearl River Basin, Mississippi was included as part of the Mobile District until 1 October 1981, when responsibilities were transferred to Vicksburg District, Lower Mississippi Valley Division. A section of the Gulf Intracoastal Waterway from St. Marks, Florida, to Lake Borgne Light No. 29, Louisiana is also within Mobile District. IMPROVEMENTS Navigation 1. Apalachicola Bay, FL .................. 2. Aquatic Plant Control (R&H Act of 1965) ............................. 3. Bayou Coden, AL ..................... 4. Bayou La Batre, AL ................... 5. Biloxi Harbor, MS .................... 6. Biloxi Harbor, East Harrison County Canal, MS, County Canal, MS .......... 7. Black Warrior and Tombigbee Rivers, AL .......................... 8. Bon Secour River, AL ................ 9. Dauphin Island Bay, AL ............... 10. Dog and Fowl Rivers, AL ............. 11. East Pass Channel from Gulf of Mexico into Choctawhatchee Bay, FL .......... 12. Fly Creek, Fairhope, AL .............. 13. Gulf Intracoastal Waterway between Apalachee Bay, FL and Mexican Border (Mobile D istrict) ............................. 14. Gulfport Harbor, MS................. . 15. Mobile Harbor, AL .................. 16. Panama City Harbor, FL ............. 17. Pascagoula Harbor, MS .............. 18. Pensacola Harbor, FL ................ 19. Perdido Pass Channel, AL........... 20. Waterway Connecting Tombigbee and Tennessee Rivers, AL and MS ......... 21. Other Authorized Navigation Projects ............................. 22. Navigation Work Under Special Authorization....................... 23. Reconnaissance and Condition Surveys ............................. Deauthorized Projects 24. Deauthorized Projects ................ Page Beach Erosion Control 10-3 25. Other Authorized Beach Erosion Control Project ...................... 10-3 10-3 10-4 10-4 26. Beach Erosion Control Projects Under Special Authorization ........... Flood Control 27. Okatibbee Lake, MS ................. 10-5 28. Tallahala Creek Lake, Pascagoula River, MS ......................... 10-5 29. Airport Road Bridge, 10-6 Frankstown, MS ..................... 10-6 30. Biloxi River at Lorraine Road 10-6 Harrison County, MS ................ 31. Gordons Creek, 10-7 Hattiesburg, MS ..................... 10-7 32. Murder Creek, East Brewton, AL ................... . 33. Noxubee River Relief Bridge, Shuqualak, MS ...................... 10-8 34. Pumpkinvine Creek, Emerson, GA ..... 10-8 35. Sewerline Protection, 10-9 Valley, AL .......................... 10-10 36 Sope Creek, 10-10 Marietta, 10-11 GA ........................ 10-11 37. Tombigbee River (East Fork), M S and AL ......................... 10-11 38. Tombigbee River Tributaries, M S and AL ......................... 10-12 39. US Highway 11 Bridge, Fosters, AL ......................... 10-12 40. US Highway 43 Bridge, Chickasaw Bogue Creek, Linden, AL ... 10-12 41. Wolf Creek, US Highway 45 Bridge, Prentiss County, MS ................. 42. Old Highway 82 Bridge, 10-12 Columbus, MS ..................... 10-1 Page 10-12 10-12 10-13 10-13 10-13 10-13 10-14 10-14 10-14 10-14 10-14 10-15 10-15 10-15 10-16 10-16 10-16 10-16 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 43. Wolf Creek, Highway 362 Bridge, Prentiss County, MS ................. 44. Osborne Creek, Highway 362 Bridge, Prentiss County, MS ................. 45. Interstate 20 Bridges over Pearl River, Jackson, MS ............. 46. Interstate 59 Bridges, Fosters, AL......................... 47. Inspection of Completed Flood Control Projects .................... 48. Other Authorized Flood Control Projects .................... 49. Flood Control Work Under Special Authorization ................ . Multiple Purpose Projects Including Power 50. Alabama-Coosa Rivers, AL and GA ........................ 50A. Carters Lake, GA' ................... 50B. Claiborne Lock and Dam, A L .. .............................. 50C. Robert F. Henry Lock and Dam, AL .................. Page 50D. Millers Ferry Lock and Dam, 10-16 AL ................................ 50E. Coosa River Navigation ............... 10-17 51. Allatoona Lake, Coosa River Basin, GA ........................... 10-17 52. Apalachicola, Chattahoochee, and Flint Rivers, 10-17 AL, GA, and FL ..................... 52A. Buford Dam, GA .................... 10-18 52B. George W. Andrews Lock and Dam, AL and GA .................... 10-18 52C. Jim Woodruff Lock and Dam, GA and FL ............................. 10-1852D. Spewrell Bluff Lake, GA .............. 52E. Walter F. George Lock and Dam, AL and GA ......................... 52F. West Point Lake, Chattahoochee River Basin, GA and AL .............. 53. Scheduling Flood Control n Q Reservoir Operations ................. --1I0 10-19 10-19 54. 55. 10-20 General Investigations Surveys ............................. Collection and Study of Basic D ata ............................... Tables Table 10-A Cost & Financial Statement .................. Table 10-B Authorizing Legislation ....... Table 10-C Other Authorized Navigation Projects ........... Table 10-D Other Authorized Beach Erosion Control Projects ...... Table 10-E Other Authorized Flood Control Projects ............. . Table 10-G Deauthorized Projects ......... Table 10-H Navigation Work Under Special Authorization ......... Table 10-I Beach Erosion Control Projects Under Special Authorization ............... . Table 10-J Flood Control Work Under Special Authorization ......... 10-26 10-32 10-42 10-42 10-43 10-43 10-43 Table 10-K Table 10-L Table 10-M Table 10-N Table 10-0 10-44 Table 10-P 10-44 Reconnaissance and Condition Surveys ............ 10-45 Alabama-Coosa Rivers, AL and GA Development Proposed Under Existing Project ........ 10-45 Apalachicola, Chattahoochee, and Flint Rivers, AL, GA and FL, Locks and Dams and Multiple- Purpose Development Included in Existing Project ............ 10-46 Black Warrior and Tombigbee Rivers, AL ........ 10-47 Tennessee-Tombigbee Waterway, MS and AL ........ 10-48 Completed Flood Insurance Studies and Flood Hazard Information Reports .......... 10-49 10-2 Page 10-20 10-20 10-21 10-21 10-22 S10-22 10-23 10-23 10-24 10-24 10-25 10-25 10-25 MOBILE, ALABAMA DISTRICT Navigation 1. APALACHICOLA, BAY, FL. Location. The project is on the coast of northwest Florida 160 miles east of Pensacola Harbor. (See Coast and Geodetic Survey Chart 11401.) Previous project. For details, see page 1833, Annual Report for 1915, and page 689, Annual Report for 1938. Existing project. The authorized project provides for: (a) A channel 10 feet deep and 100 feet wide from the 10-foot depth in Apalachicola Bay, across St. George Island, to within 300 feet of the gulf shore, thence increasing uniformly in width to 200 feet at the shore and continuing with that width to the 10-foot depth in the Gulf of Mexico, with twin jetties extending from the dune line to the outer end of the channel; (b) an inner bar channel, 10 feet deep and 100 feet wide, in Apalachicola Bay; (c) a boat basin 200 feet by 880 feet and nine feet deep at Apalachicola, Florida, with a connecting channel 9 feet deep and 80 feet wide through Scipio Creek to Apalachicola River; (d) a channel known as Link Channel, 10 feet deep and 150 feet wide, in Apalachicola Bay; (e) a channel generally parallel to the shore at Eastpoint, Florida, 6 feet deep, 100 feet wide, and about 6,000 feet long, and a connecting channel 6 feet deep and 100 feet wide to water at the same depth in St. George Sound, with twin breakwaters on either side parallel to the shore and having a total length of 5,300 feet; (f) a channel 10 feet deep and 100 feet wide through Bulkhead Shoals, connecting Apalachicola Bay with St. George Sound; and (g) a 6-foot by 100-foot channel about one mile long, generally parallel to the shore at Two Mile, Florida, with a 6-foot by 100-foot connecting channel to water of the same depth in Apalachicola Bay. Mean range of tide throughout this harbor is 1.6 feet. Extreme range, except during storms, is about three feet. Plane of reference is mean low water. (See Table 10-B for authorizing legislation.) Local cooperation. Requirements have been fully complied with. Terminal facilities. Facilities consist of pile-andtimber wharves which are considered adequate for existing commerce. Operations and results during fiscal year. New work: None. Maintenance: Work on channels and canals and miscellaneous costs amounted to $77,296. Condition at end of fiscal year. The existing project, authorized by the 1954 River and Harbor Act, was completed in 1959, including reimbursement to local interests for approved work, as authorized by the 1958 River and Harbor Act. Improvements at Two Mile except for modifications authorized in 1975 were completed in September 1964. Construction of the breakwater and channel improvements authorized in 1975 at Two Mile was completed in September 1977. Construction of breakwaters at Eastpoint authorized in 1983 was completed in March 1984. Total Federal costs under existing project as of September 30, 1985 were $1,898,848 for new work and $2,727,442 for maintenance, a total of $4,626,290. 2. AQUATIC PLANT CONTROL (RIVER AND HARBOR ACT OF 1965) Location. Navigable water, tributary streams, connecting channels and other allied waters in Mobile District. Existing project. The authorized project provides for management and control of water hyacinth, alligatorweed, Eurasian watermilfoil, hydrilla, and other obnoxious aquatic plant growths from navigable water, tributary streams, connecting channels, and other allied waters of the United States, in the combined interest of navigation, flood control, drainage, agriculture, fish and wildlife conservation, public health, and related purposes, including continued research for development of the most effective and economical control measures to be administered by the Chief of Engineers, under the direction of the Secretary of the Army, in cooperation with other Federal and State agencies. Research and planning cost prior to construction shall be borne fully by the United States. (See Table 10-B for authorizing legislation.) Local cooperation. Local interests shall agree to hold and save the United States free from claims that may occur from control operations and to participate to the extent of 30 percent of such operations. Requirements are being met in the state of Alabama. Operations and results during fiscal year. Planning, engineering and design, and contract administration cost $41,082. Condition at end of fiscal year. Total Federal costs under the existing project as of September 30, 1985 were $491,688. Contributed funds for maintenance amount to $21,225. 3. BAYOU CODEN, AL Location. The project is located in a small tidal stream on the southern coast of Mobile County, Alabama. emptying into Mississippi Sound about 7.6 miles northwest of Cedar Point, the southern tip of western mainland shore of Mobile Bay. (See Coast and Geodetic Survey Chart 11376.) Previous project. For details see Annual Report for 1945, page 843. Existing project. The project provides for a channel eight feet deep by 60 feet wide extending from La Belle Avenue bridge south for about 3,000 feet through the bayou to Portersville Bay, thence eight feet deep by 100 feet wide extending about 2.3 miles westward across Portersville Bay to connect with the Bayou La Batre channel, and a turning basin eight feet deep by 60 feet 10-3 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 wide by 100 feet long on the west side of the bayou channel about 500 feet south of the La Belle Avenue bridge. Mean tidal range is 1.75 feet, and extreme, except during storms, is 3.5 feet. Plane of reference is mean low water. (See Table 10-B for authorizing legislation.) Local cooperation. Fully complied with. Terminal facilities. Small privately-owned pile-andtimber piers used in connection with fishing industry in this locality are adequate for existing commerce. A marina which will accommodate about 12 small recreational craft, and a slip with facilities for loading oyster shells are located near the mouth of the bayou, and are maintained by the Alabama Department of Conservation. Operations and results during fiscal year. New work: None. Maintenance: Surveys and miscellaneous costs amounted to $22,778. Condition at end of fiscal year. That portion of the project authorized prior to the 1969 modification was completed in 1956. Construction authorized in 1969 was initiated 31 March 1975 and completed 26 March 1976. Total Federal costs under existing project as of September 30, 1985 were $325,051 for new work and $404,409 for maintenance, a total of $729,460. Contributed funds expended for new work amount to $100,000 and $50,000 for maintenance. 4. BAYOU LA BATRE, AL Location. Bayou La Batre is a tidal stream about 10 miles long, emptying into Mississippi Sound on the southern coast of Mobile County, Al., about 10 miles northwest of Cedar Point, the southern tip of the western mainland shore of Mobile Bay. (See Coast and Geodetic Survey Chart 11373.) Previous project. For details see Annual Report for 1945, page 844. Existing project. The authorized project provides for a 12-foot by 100-foot channel from the 12-foot depth in Mississippi Sound to a point about 2,800 feet south of the highway bridge, thence a channel 12 feet deep by 75 feet wide to the bridge, an overall distance of about 33,500 feet, with the channel widened at a point 0.6 mile below the bridge to provide a turning basin 12 feet deep and about 2.6 acres in area. Mean tidal range is 1.75 feet, and extreme, except during storms, is 3.75 feet. Plane of reference is mean low water. (See Table 10-B for authorizing legislation.) Local cooperation. Fully complied with. Terminal facilities. Wooden wharves have been provided at seafood processing plants and public launching ramps are available. Facilities are considered adequate for existig commerce. Operations and results during fiscal year. Condition surveys, water control management and other costs amounted to $22,460. Condition at end of fiscal year. The existing project was modified December 30, 1966 under the discretionary authority of the Chief of Engineers to include a turning basin. The project was completed in March 1967. Total Federal costs under existing project as of September 30, 1985 were $311,095 for new work and $2,689,074 for maintenance, a total of $3,000,169. Contributed funds from local interests for new work amount to $10,500. 5. BILOXI HARBOR, MS Location. The project is located on Mississippi Sound in southeastern Mississippi, 32 miles by water west of Pascagoula Harbor, Mississippi, and 14 miles east of Gulfport Harbor, Mississippi (See Coast and Geodetic Survey Chart 11373.) Previous project. For details see page 584, Annual Report for 1962. Existing project. The authorized project provides for a continuous channel 12 feet deep, 150 feet wide and 23 miles long from the Gulf Intracoastal Waterway through Mississippi Sound east of Deer Island, Biloxi Bay, Back Bay, Cranes Neck, and a land cut to Gulfport Lake, including a 500-foot by 2,600-foot basin in the lake, thence a 12-foot deep by 100-foot wide channel for about two miles westward from the west end of the lake, terminating in a 300-foot by 500-foot basin; a 12-foot by 100-foot channel from the main channel in Big Lake to and up Bayou Bernard to the Air Force oil terminal at about mile 2.6; a 12-foot by 150-foot spur channel from the main channel in Biloxi Bay for about one mile, terminating in a 400-foot by 600-foot turning basin opposite Ott Bayou; continuation of maintenance of the 12- by 150-foot lateral channel westward about 2.2 miles to Biloxi's south waterfront; a 10-foot by 150-foot channel from Mississippi Sound, passing west of Deer Island to a point where it connects to the 12-foot by 150-foot lateral channel at Biloxi's south waterfront. Construction for the modifications lateral channel authorized by River and Harbor Act of Nov. 7, 1966 was commenced in FY 1974 and completed in Feb. 1975. Further modifications to the project were authorized by the Chief of Engineers on 28 March 1979, which provided for a channel 10 feet deep, 100 feet wide and 300 feet long extending northward from the Biloxi Lateral Channel, and into a rectangular basin, approximately 300 by 370 feet. This work was completed in April 1980. Cost of modification as authorized by the 1966 River and Harbor Act was $664,390. That portion of the project providing for an entrance channel 6 feet deep, 50 feet wide, and about 1,800 feet long into Old Fort Bayou, as authorized by the 1945 River and Harbor mated Act, is inactive. Estimated cost (1954) of this portion was $6,000. (See Table 10-B for authorizing legislation.) Local cooperation. Fully complied with. Terminal facilities. A number of wooden piling-and- 10-4 MOBILE, ALABAMA DISTRICT timber piers for small craft and fishing boats, a bulk gasoline terminal, several boat ways, and concrete products plant are available. Operations and results during fiscal year. New work: None. Maintenance: Condition and operation studies, engineering and design, and other miscellaneous costs amounted to $151,489. Condition at end of fiscal year. The existing project, prior to the modification authorized in 1966, was commenced in 1931 and completed in 1962. The 1966 modification was completed in FY 1975. The 1979 modification was completed in FY 1980. Total Federal costs under existing project as of 30 September 1985 were $1,171,054 for new work and $5,578,538 for maintenance, a total of $6,749,592. Contributed funds for new work amount to $102,600. 6. BILOXI HARBOR, EAST HARRISON COUNTY CANAL, MS Location. Biloxi Harbor is located on Mississippi Sound in southeastern Mississippi, approximately 75 miles east of New Ori ais, Louisiana, and 45 miles west of Mobile Bay, Alabama. The City of Biloxi is situated on a peninsula bounded by Mississippi Sound on the south, Biloxi Bay on the east, and Back Bay of Biloxi on the north. Existing project. The project provides for the improvement and maintenance of the East Harrison County Canal to a 12-foot project depth, 130 feet wide, and about 2,100 feet long, and a 300- by 300-foot turning basin also to a 12-foot project depth. (See Table 10-B for authorizing legislation.) Local cooperation. Fully complied with. Operation and results during fiscal year. New work: Engineering and Design costs amounted to $35,225. Condition at end of fiscal year. Plans and specifications were essentially complete in 1985. Anticipate project construction in FY 1986. 7. BLACK WARRIOR AND TOMBIGBEE RIVERS, AL Location. Black Warrior River rises in northern Alabama above Birmingham and flows generally southwesterly to unite with the Tombigbee River at Demopolis, Alabama. Thence the Tombigbee flows south, uniting with the Alabama River to form the Mobile River 45 miles above the head of Mobile Bay. Distance by water from Mobile to the vicinity of Birmingham is about 415 miles. Previous project. For details see page 732, Annual Report for 1938. Existing project. The authorized project provides essentially for a channel 9 feet deep and 200 feet wide from the mouth of the Tombigbee River, 45 miles above Mobile, to the vicinity of Birmingham, via the Tombigbee and Black Warrior Rivers, to mile 430.4 on Sipsey Fork, mile 429.6 on Mulberry Fork and mile 407.8 on Locust Fork, and for maintenance by snagging of Mobile River above the mouth of Chickasaw Creek, a total waterway distance of about 408 miles. The total lift of 255 feet is accomplished by six locks and dams. The original construction program, consisting of 17 dams with 18 lifts, was completed in 1915. Replacement of the original structures with new locks and dams, under the modernization program is as follows: William Bacon Oliver replaced locks 10, 11, and 12; Demopolis replaced locks 4, 5, 6, and 7; Warrior replaced locks 8 and 9; Coffeeville (Jackson) replaced locks 1, 2, and 3; and Holt replaced locks 13, 14, 15, and 16. Thus, 16 of the original locks have been replaced by five new locks. Bankhead Lock and Dam (Lock 17) rehabilitation to replace the original double lift lock with a single lift lock was completed in 1980. The Jackson Lock and Dam wildlife refuge, authorized in 1960, includes 4,250 acres within the reservoir area and along its boundaries. It is proposed to replace Oliver Lock with a lock located 2,300 feet downstream. The replacement lock would have dimensions of 110' x 600'. A fixed crest spillway would extend 815 feet across the river. Minimum provision will be provided to allow construction of a hydropower plant. (See Table 10-B for authorizing legislation.) Tidal influence extends upstream from Mobile 101.6 miles to the old lock 1, where tidal effect is apparent only at low stages of the river. At Mobile the mean and extreme tidal ranges are 1.5 and 3.6 feet, respectively. These are at times slightly increased by the effect of winds. The greatest fluctuation of river stages is at Demopolis, Ala., the maximum being 59.7 feet. Maximum fluctuations at other points are 40 feet at lock 1,100.6 miles from Mobile; 57.8 feet at Tuscaloosa, 346.1 miles from Mobile; 13 feet at Birmingport, 404.9 miles from Mobile; and 27 feet at Cordova, 424.3 miles from Mobile. Ordinary fluctuations at these points are at old lock 1, 20 feet; at Demopolis, 35 feet; at Tuscaloosa, 40 feet; at Birmingport, four feet; and at Cordova, seven feet. Works of improvement reduced the amount of fluctuations at different points by three to 10 feet. Local cooperation. Requirements of local cooperation have been fully complied with to date. Terminal facilities. Docks, storage facilities, and handling equipment have been provided as required at most loading and unloading points along the waterway. These include facilities for handling petroleum and petroleum products, coal, ores, sand and gravel, pulpwood, manufactures, and various other commodities. While most terminal facilities are privately owned, many are available for use by the general public. Facilities are considered adequate for existing commerce. (See Table 10-N for existing locks and dams.) Operations and results during fiscal year. New work: Engineering and design for replacement span on Franklin Ferry Bridge across navigation chan- 10-5 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 nel cost $1,565,844. Recreation facilities cost $231,606 at Demopolis Lock and Dam. Recreation attendance during CY 1984 totaled 5,656,700 user days. Maintenance: Contractors' dredges removed 3,123,100 cubic yards of material from the river system at a cost of $4,486,760. Other general charges for the overall river project totaled $4,789,885. Other maintenance costs for the system include: Coffeeville Lock and Dam, $346,777; Demopolis Lock and Dam, $479,461; Warrior Lock and Dam, $400,623; Oliver Lock and Dam, $479,098; Bankhead Lock and Dam, $377,968; Holt Lock and Dam, $400,188; and reservoir operation, $1,796,848. Condition at end of fiscal year. Work on the project, commenced in 1887, was essentially completed in 1915. Since then three of the original locks and dams (10, 11 and 12) were replaced by William Bacon Oliver (Tuscaloosa) Lock and Dam which was opened to navigation in August 1939; four original locks and dams (4, 5, 6 and 7) were replaced by Demopolis Lock and Dam which was opened to navigation in August 1954; two original locks and dams (8 and 9) were replaced by Warrior Lock and Dam which was opened to navigation in October 1957; three original locks and dams (1, 2 and 3) were replaced by Coffeeville Lock and Dam which was opened to navigation in August 1960; and four original locks and dams (13; 14, 15, and 16) were replaced by Holt Lock and Dam which was opened to navigation in June 1966. Rehabilitation of the spillway at John Hollis Bankhead Lock and Dam commenced in 1966, and physically completed 6 February 1970. Replacement of the double lift lock with a single lift lock at John Hollis Bankhead Lock and Dam commenced in April 1970 and was completed in 1980. The cost to September 30, 1985 for replacement of the lock was $47,258,169. The power plant at John Hollis Bankhead Lock and Dam was built and is operated by the Alabama Power Co. Total Federal costs under existing project as of September 30, 1985 were $107,817,289 for new work and $165,521,499 for maintenance, and $47,258,169 for major rehab, a total of $323,596,957. 8. BON SECOUR RIVER, AL Location. Rises 2 miles south of Foley, Ala., and flows southerly about 8 miles, emptying into Bon Secour Bay, an arm of Mobile Bay in southwest Alabama. Existing project. A 10- by 80-foot channel from Gulf Intracoastal Waterway through Bon Secour Bay to mouth of Bon Secour River and extending up river to vicinity of Swifts Landing, thence 6 by 80 feet up river to a point about 600 feet above Oak Landing with two turning and maneuvering areas 150 feet wide and 1,100 to 1,200 feet long opposite Swifts Landing and ice loading dock. Plane of reference is mean low water. Overall length of improvement is about 4.7 miles. Mean tidal range is about 1.5 feet and extreme, except during storms, is 3.5 feet. Existing project was authorized by Chief of Engineers, May 16, 1963, under authority in Section 107, River and Harbor Act of 1960. Local cooperation. Fully complied with. Terminal facilities. A number of pile-and-timber marginal wharves used by the seafood industry and a marine ways are located along the existing project. These, together with numerous privately owned piers, are considered adequate for existing commerce. Operations and results during fiscal year. Mainte-nance: Operation studies, surveys, and supervision and administration cost $22,452. Condition at end of fiscal year. Project was commenced in July and completed in October 1964. Total Federal costs under existing project as of September 30, 1985 were $118,615 for new work and $171,038 for maintenance, a total of $289,652. Contributed funds for new work amounted to $9,700. 9. DAUPHIN ISLAND BAY, AL Location. The project is located between Dauphin and Little Dauphin Island on the west side of the entrance to Mobile Bay, about 30 miles south of Mobile, Alabama and 55 miles west of Pensacola, Florida. (See Coast and Geodetic Survey Chart 11376.) Existing project. The authorized project provides for: (a) A channel seven feet deep and 150 feet wide from Mobile Bay to an anchorage basin of the same depth, and about seven acres in area, in the marsh just north of Fort Gaines on Dauphin Island; a channel four feet deep and 40 feet wide from the anchorage basin to Dauphin Island Bay; and a jetty and revetment to protect the entrance channel; and (b) an anchorage basin seven feet deep and 500 feet square at Dauphin Island Village, with an entrance channel of like depth, 100 feet wide and about 8,300 feet long, extending to the 7-foot hydrographic contour in Mississippi Sound. Mean tidal range is 1.1 feet, and extreme, except during storms is about four feet. Plane of reference is mean low water. (See Table 10-B for authorizing legislation.) Local cooperation. Requirements of local cooperation have been fully complied with to date. Terminal facilities. Several privately-owned wharves for handling seafood, a public dock and mooring slip, and a pier for recreational craft are located on the village basin. A marina, public launching ramp, and a number of private piers are located on the bay. Facilities are considered adequate for existing commerce. Operations and results during fiscal year. New Work: None. Maintenance: Condition and operation studies and supervision and administration cost $39,417. Condition at end of fiscal year. The project was completed in July 1959. Total Federal costs under existing project as of September 30, 1985 were $292,864 for new work and $1,148,631 for maintenance, a total of $1,441,495. 10. DOG AND FOWL RIVERS, AL Location. Dog and Fowl Rivers are primarily tidal streams emptying into the west side of Mobile Bay, 8.5 and 17 miles, respectively, south of central Mobile. (See 10-6 MOBILE, ALABAMA DISTRICT Coast and Geodetic Survey Chart 11376). Existing project. The Dog River project provides for an 8-foot deep by 150-foot wide channel from about 3,000 feet east of the Mobile Bay ship channel to and up Dog River, a total distance of 26,200 feet, thence six feet by 100 feet for 12,300 feet to a point about 2,400 feet above the mouth of Halls Mill Creek, and a 6-foot by 100-foot spur channel from the main channel to the mouths of Perch and Halls Mill Creeks. Overall length of the proposed improvement is about 7.8 miles. This portion of the project has not been constructed due to local interest's inability to comply with cost-sharing responsibilities. The Fowl River project provides for a channel eight feet deep and 100 feet wide from Mobile Bay into and up Fowl River to deep water about 6,700 feet above its mouth. Total length of the channel is about 2.6 miles. Plane of reference is mean low water. Mean range of tide is about 1.5 feet in Dog River. Extreme range during storms is about 3.6 feet. This segment of the project was completed in November, 1973. (See Table 10-B for authorizing legislation.) Local cooperation. Fully complied with for the Fowl River portion. Terminal facilities. Existing facilities consist of a boatyard for fabricating steel vessel hulls, nine marinas, four marine ways, a yacht basin on Dog River; two marinas on Fowl River, and numerous timber piers and docks on both rivers. Facilities are considered adequate for existing commerce. Operations and results during fiscal year. Maintenance: Contract dredging removed 69,100 cubic yards of material in Fowl River at a cost of $143,500. Condition and maintenance costs amounted to $44,026. Condition at end of fiscal year. The existing Fowl River portion of the project was commenced in August 1973 and completed in November 1973. No work has been done on the Dog River portion. Total Federal costs on the existing project as of September 30. 1985 were $1,070,000; $190,695 for new work and $879,305 for maintenance. Contributed funds for new work amounted to $116.300. 11. EAST PASS CHANNEL FROM GULF OF MEXICO INTO CHOCTAWHATCHEE BAY, FL Location. East Pass Channel is located in the entrance from the Gulf into Choctawhatchee Bay at eastern end of Santa Rosa Island, 48 miles east of the entrance into Pensacola Bay and 49 miles west of the new entrance to St. Andrews Bay. (See Coast and Geodetic Survey Chart 11388.) Previous project. For details see page 672 of Annual Report for 1937. Existing project. The authorized project provides for a 12-foot by 180-foot channel from the Gulf of Mexico into Choctawhatchee Bay, and a 6-foot by 100-foot channel from East Pass Channel into Old Pass Lagoon. The project consists also of two converging jetties spaced 1,000 feet apart at the seaward end. The west jetty is provided with a low weir section 1,000 feet long to permit passage of littoral drift into a dredged deposition basin 500 feet by 1,500 feet located between the west jetty and the navigation channel. Mean range of tide is 1.3 feet; extreme range, except during storms, is 2.5 feet. Plane of reference is mean low water. (See Table 10-B for authorizing legislation.) Local cooperation. Responsibilities of local cooperation have been complied with to date. Terminal facilities. Small privately-owned pile-andtimber piers used in connection with the fishing industry in this locality are considered adequate for existing commerce. Operations and results during fiscal year. Maintenance: Contractor's dredges operating in the entrance channel to Old Pass Lagoon and East Pass removed 69,700 cubic yards of material at a cost of $121,341. Other work on channels and canals cost $399,136. Hired labor costs for condition studies, contract administration, engineering, design, supervision, administration and other costs amounted to $107,082. Condition at end of fiscal year. Construction of the 1965 modification was commenced October 1967 and completed January 1969. Total Federal costs under existing project as of September 30, 1985 were $916,715 for new work and $6,200,825 for maintenance, a total of $7, I 17,540. Contributed funds for new work from local interests amount to $398,000. 12. FLY CREEK, AL Location. Fly Creek (Volanta Bayou) is a small stream about 4.5 miles long rising in Baldwin County, Ala., 3 miles east of town of Fairhope, from whence it flows northerly, thence westerly and southerly, to form an estuary on eastern shore of Mobile Bay just north of Fairhope and about 13 miles southeast of Mobile, Ala. (See U.S. Coast and Geodetic Survey Chart No. 11376.) Existing project. Provides for a channel 6 feet deep, 80 feet wide, and about 1,650 feet long from 6-foot depth in Mobile Bay to a turning basin of same depth, 100 feet wide and 350 feet long, in Fly Creek. Mean tidal range in vicinity of project is about 1.3 feet, and extreme, except during storms, is 3.5 feet. Existing project was authorized by the River and Harbor Act of May 17, 1950, (H. Doc 194, 81st Cong., I st Sess.). The project document contains the latest published map. Local cooperation. Fully complied with. Terminal facilities. Fairhope Yacht Club has facilities for small recreational craft on both banks near mouth of creek, consisting of a small pile-and timber service wharf, several sheet metal boat sheds, boat slips, and other mooring facilities. There is also a marginal timber wharf and shed for commercial fishing boats on right 10-7 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 bank of creek immediately above first bend. Operations and results during fiscal year. Maintenance: Project condition surveys, supervision and administration, and other miscellaneous costs amounted to $2,835. Condition at end of fiscal year. Project was commenced in August and completed in October, 1957. Total project costs as of September 30, 1985 amounted to $337,005 of which $29,000 was for new work and $308,006 for maintenance. 13. GULF INTRACOASTAL WATERWAY BETWEEN APALACHEE BAY, FL AND MEXICAN BORDER (MOBILE DISTRICT) Location. The project extends westward from Apalachee Bay, Florida, along the Gulf coast to the Rigolets, Louisiana, via a series of coastal lakes, bays, sounds, and land cuts. (For further details see Annual Report for 1962.) Previous project. For details see page 906, Annual Report for 1930. Existing project. The authorized project provides for a waterway 12 feet deep and 125 feet wide at mean low water from Apalachee Bay, Florida, to Mobile Bay, Alabama, and 12 feet deep and 150 feet wide from Mobile Bay, Alabama to Rigolets, Louisiana (Lake Borgne Light No. 29), and for a tributary channel (Gulf County Canal), 12 feet deep, 125 feet wide and about six miles long connecting Intracoastal Waterway at White City, Florida, with St. Joseph Bay. The waterway between the 12-foot depth contours in Apalachee Bay and Lake Borgne Light No. 29 at the Rigolets is 379 miles long. (See Table 10-B for authorizing legislation.) Local cooperation. Responsibilities of local cooperation have been fully complied with for the work authorized prior to 1966. For modification of the Gulf County Canal which was authorized by the 1966 River and Harbor Act, local interests must provide without cost to the United States all lands, easements, and rights-of-way required in connection with disposal of spoil, or the costs of such retaining works; hold and save the United States free from all damages due to construction and maintenance of the project including damages to wharves, piers, bridges, and other structures; provide and maintain at local expense adequate terminal and transfer facilities open to all on equal terms; provide and maintain without cost to the United States depths in berthing areas commensurate with depths provided in related project area; and accomplish without cost to the United States such alterations as required in sewer, water supply, drainage, and other facilities as well as their maintenance. Terminal facilities. Facilities are available for public use at Carrabelle, Apalachicola, Panama City, and Pensacola, Florida; Mobile and Bayou LaBatre, Alabama; and Pascagoula, Biloxi, Gulfport, Pass Christian, and Bay St. Louis, Mississippi. Facilities are considered adequate for existing commerce. Operations and results during fiscal year. Maintenance: Carrabelle-Apalachicola Bay section: Condition and operation studies, supervision and administration, and miscellaneous work cost $95,409. Apalachicola Bay - St. Andrew Bay section: There was a total of 953,802 cubic yards of maintenance dredging performed at a cost of $1,211,329. Engineering and design, condition and operation stduies, and miscellaneous work cost $178,043. St. Andrew Bay - Choctawhatchee Bay section: There was a total of 1,275,698 cubic yards of maintenance dredging performed at a cost of $1,636,274. Hired labor cost for the year included: bank stabilization, engineering and design, supervision and administration, in the amount of $469,274. Choctawhatchee Bay - Pensacola Bay section: Costs for the year include condition and operation studies and miscellaneous work of $54, 114. Pensacola Bay - Mobile Bay section: Costs for the year included condition and operation studies, channels and canals, engineering and design, supervision and administration, and bank stabilization, $1,148,296. Mobile Bay - Rigolets section: Hired labor costs included $35,948 for condition and operation studies and supervision and administration. In addition, compliance inspections cost $185,198; direct charges to Mobile Area Office cost $135,365; and direct charges to Panama City Area Office were $26,275. Condition at end of fiscal year. The existing project is complete except for the portion between Apalachicola Bay and St. Marks, Florida, which is deferred for restudy. Modification of the Gulf County Canal to provide a 12-foot by 125-foot channel was commenced July 1968 and completed June 1969. Total costs of the existing project to September 30, 1985 were $48,073,393, of which $6,434,694 was for new work and $41,638,699 for maintenance. 14. GULFPORT HARBOR, MS Location. The project is located on Mississippi Sound in southeastern Mississippi, about 35 miles west of Pascagoula, Mississippi, and 60 miles east of New Orleans. (See Coast and Geodetic Survey Chart 11373.) Previous project. For details see page 747, Annual Report for 1938, and page 995, Annual Report for 1948. Existing project. The authorized project provides for: (a) A channel 32 feet deep, 300 feet wide, and about eight miles long across Ship Island Bar, a channel 30 feet deep, 220 feet wide, and about 1 1 miles long through Mississippi Sound, and an anchorage basin at Gulfport 30 feet deep, 1,320 feet wide, and 2,640 feet long; and (b) maintenance of the existing commercial smallboat harbor about 26 acres in area, and a straight-approach channel, 100 feet wide and about 4,300 feet long, from 10-8 MOBILE, ALABAMA DISTRICT deep water in Mississippi Sound to a small-boat basin, all at a depth of eight feet. Under ordinary conditions mean tidal range is about 1.75 feet, and extreme range, except during storms, is about 3.5 feet. Plane of reference is mean low water. It is proposed to modify the existing ship channel to 36 x 600 feet in Mississippi Sound, and 38 x 400 feet across the bar, with changes in the channel alignment and the entrance to the anchorage basin for safe and unrestricted navigation. (See Table 10-B for authorizing legislation.) Local cooperation. Conditions of local cooperation have been fully complied with to date. Terminal facilities. Existing modern rail-connected terminal facilities at this port are considered adequate for existing commerce. (See Port Series 19, revised in 1979.) Operations and results during fiscal year. Maintenance: Contract dredging removed a total of 3,021,000 cubic yards of material from the harbor channel at a cost of $2,096,795. Hired labor included condition and operation studies, and engineering, design, supervision and administration, all at a cost of $266,415. Condition at end of fiscal year. The main harbor was commenced 1932 and completed April 1950. Maintenance for small boat harbor and approach channel, constructed by local interests in 1950, was authorized by 1958 River and Harbor Act. Total Federal costs under existing project as of September 30, 1985 were $635,758 for new work and $29,189,492 for maintenance, a total of $29,825,250. 15. MOBILE HARBOR, AL Location. The project is located along the lower five miles of Mobile River, in southwestern Alabama, 91 miles by water west of Pensacola Harbor, Florida, 90 miles east of Gulfport Harbor, Mississippi, and 144 miles by water northeast of mouth of Mississippi River. (See Coast and Geodetic Survey Chart 11376.) Previous project. For details see page 503, Annual Report for 1963. Existing project. The authorized project provides for: (a) A 42-foot by 600-foot channel about 1.5 miles long across Mobile Bar; (b) a 40-foot by 400-foot channel in Mobile Bay to mouth of Mobile River; (c) a 40-foot channel in Mobile River to highway bridge, varying from 500 to 775 feet wide; (d) a 25-foot channel from highway bridge to and up Chickasaw Creek to a point 400 feet south of mouth of Shell Bayou, widths being 500 feet in Mobile River and 250 feet in Chickasaw Creek; (e) a turning basin 40 feet deep, 2,500 feet long, and 800 to 1,000 feet wide, opposite Alabama State Docks; (f) a turning basin 40 feet deep, 1000 feet wide, and 1,600 feet long opposite Magazine Point; (g) a 27-foot by 150-foot channel from Mobile Bay Channel along Arlington pier to a turning basin 800 feet long and 600 feet wide opposite Brookley Complex ocean terminal, and continuing thence to a turning basin 250 feet wide and 800 feet long in Garrows Bend, thence a 22- foot by 150-foot channel to the causeway linking McDuffie Island to the mainland; (h) a channel 40 feet deep and 400 feet wide from the main ship channel in Mobile Bay and extending northwesterly for about 5.3 miles to the shore of Mobile Bay, including an anchorage and turning basin near the shoreline, thence a land cut 40 feet deep, 300 feet wide and 1.9 miles long to and including a 42 acre trapezoid turning basin 40 feet deep, and a barge channel 12-by 100-feet, extending 6500 feet and terminating in a 300-by 300-foot turning basin; and (i) maintenance of Three Mile Creek by snagging, from its intersection with Industrial Canal to Mobile River. The project provides also for an anchorage area 32 feet deep, 100 feet wide, and 2,000 feet long opposite site formerly occupied by the U. S. Quarantine Station at McDuffie (Sand) Island. Prior to widening the Mobile Bay Channel as authorized in 1954, the Quarantine Station anchorage area was maintained to a project width of 200 feet. Construction by local interests of a solid-fill causeway across Garrows Bend Channel between McDuffie Island and the mainland is also provided for under existing project. Total length of the bay and river channels is about 41.7 miles. Plane of reference is mean low water. Under ordinary conditions mean tidal range at the lower end of the improvement is 1.2 feet and at the upper end 1.5 feet. Extreme tidal range is 3.4 feet at the lower end and 3.6 feet at the upper end. Further authorization provides for future development to deepen and widen entrance channel over the bar to 57 feet by 700 feet about 7.4 miles long, deepen and widen bay channel to 55 feet by 550 feet about 27.0 miles long, deepen and widen an additional 4.2 miles of bay channel to 55 feet by 650 feet, provide 55 foot deep anchorage area and turning basin in vicinity of Little Sand Island, and construct a 1710 acre disposal area adjacent to the Brookley Industrial Complex. (See Table 10-B for authorizing legislation.) A General Design Memorandum has been approved at the Division level modifying the project dimensions which would provide an entrance channel of 57 feet by 600 feet about 7.8 miles long and a bay channel of 55 feet by 400 feet about 29 miles long. Local cooperation. Requirements of local cooperation have been fully complied with to date. Terminal facilities. Modern rail-connected terminal facilities at this port are considered adequate for existing commerce. (See Port Series No. 18, revised in 1979.) Operations and results during fiscal year. New work: Work on Theodore Channel cost $19,448. Maintenance: Contract dredging removed 2,210,200 cubic yards of material from Mobile River Channel, Outer Bar Channel, and from Mobile Bay, and Theodore Channel, all at a cost of $3,016,200. Hired labor cost for surveys, engineering, design, supervision and administration, and diking work amount to $1,803,496. Condition at end of fiscal year. The existing project was commenced in 1931 and completed in July 1965 10-9 REPORT TO THE CHIEF OF ENGINEERS, U.S. ARMY 1985 except for the Theodore Channel portion, which was essentially completed in August 1982. For details see Annual Report for 1965. Total Federal costs under existing project as of September 30, 1985 were $61,418,380 for new work and $69,575,380 for maintenance, a total of $130,993,760. Contributed funds expended amounted to $4,164,969 for new work and $846,706 for maintenance. 16. PANAMA CITY HARBOR, FL Location. The project is located on the northwest coast of Florida, 102 miles east of entrance to Pensacola Harbor. (See Coast and Geodetic Survey Chart 11389.) Previous project. For details see page 710, Annual Report for 1938. Existing project. The authorized project (as modified) provides for a channel about 3.7 miles long extending from deep water in St. Andrew Bay to the Gulf of Mexico, 300 feet wide and 40 feet deep in the bay and 450 feet wide, 42 feet deep and about 1. I miles long in the approach channel in the Gulf, protected by two jetties, each about 700 feet long; branch channels 38 feet deep and 300 feet wide, leading from the inner end of the main entrance channel westward to the Port Authority terminal at Dyers Point and eastward to the Bay Harbor terminal, about 3.4 and 3.6 miles in length, respectively; turning and maneuvering areas comprising about 55 acres opposite Dyers Point, and 42 acres opposite Bay Harbor, both at a depth of 38 feet; and an anchoring and loading basin for LASH type intermodal carriers, 40 feet deep and containing about 177 acres in St. Andrew Bay near the inner end of the main entrance channel; a channel in Watson Bayou, 100 feet wide and 10 feet deep from that depth in St. Andrew Bay to the highway bridge, about 1.75 miles; channel 100 feet wide and 8 feet deep in Grand Lagoon to a point about 2,400 feet east of State Highway 392 Bridge, with branches to serve terminal facilities. The east and west jetties have been reworked and are presently about 2,075 and 2,896 feet long, respectively. Mean tidal range is about normally 1.3 feet and 3.0 feet extreme. (See Table 10-B for authorizing legislation.) Local cooperation. Fully complied with. Terminal facilities. Available terminal facilities are considered adequate for existing commerce. (See Port Series No. 19.) Operations and results during fiscal year. New work: None. Maintenance: Dredging of Entrance Channel of 207,000 cubic yards of material amounted to $379,800. Condition and operation studies, supervision and administration, and, other miscellaneous costs amounted to $51,555. Condition at end of fiscal year. The existing project (prior to modifications) was completed in November 1949. Repairs to jetties were commenced in June 1961 and completed October 1968. Modifications to the project at Grand Lagoon were completed in January 1972. Total Federal costs under existing project as of September 30, 1985 were $1,434,485 for new work and $5,952,391 for maintenance, a total of $7,386,876. Contributed funds expended for new work amount to $80,000. 17. PASCAGOULA HARBOR, MS Location. The project is located along lower 6.8 miles of Pascagoula River, the lower six miles of Dog River, and in Bayou Casotte (about four miles east of the mouth of Pascagoula River), in southeastern Mississippi, about 38 miles west of Mobile, Alabama, and about 100 miles east of New Orleans, Louisiana. (See Coast and Geodetic Survey Chart 11373.) Previous project. For details see page 741, Annual Report for 1938. Existing project. The authorized project provides for (a) An entrance channel 40 feet deep and 350 feet wide from the Gulf of Mexico through Horn Island Pass, including an impounding area for littoral drift, 40 feet deep, 200 feet wide, and about 1,500 feet long adjacent to the channel at the west end of Petit Bois Island; (b) a channel 38 feet deep and 350 feet wide in Mississippi Sound and Pascagoula River to the railroad bridge at Pascagoula, including a turning basin 2,000 feet long and 950 feet wide (including channel area) on the west side of the river below the railroad bridge; (c) a channel 38 feet deep and 225 feet wide from the ship channel in Mississippi Sound to the mouth of Bayou Casotte, thence 38 feet deep and 300 feet wide for about one mile to a turning basin 38 feet deep, 1,000 feet wide, and 1,750 feet long; (d) a 22-foot deep by 150-foot wide channel up Pascagoula River from the railroad bridge to the mouth of Escatawpa (or Dog) River, then up Escatawpa River to Highway 613 (formerly 63) bridge; (e) a 12-foot by 125-foot channel from the highway bridge, via Robertson and Bounds Lakes, to mile 6 on Escatawpa River; and (f) a 12-foot by 80-foot channel extending from deep water in the Pascagoula River (about one-half mile north of the railroad bridge) to a turning basin in Krebs Lake a distance of about 1,500 feet, then along the south bank of the lake a channel 10-foot by 60-foot and terminating at a second turning basin, a distance of 2,700 feet from the first. Under ordinary conditions mean tidal range is 1.75 feet, and extreme range is 3.75 feet. Plane of reference is mean low water. (See Table 10-B for authorizing legislation.) Local cooperation. Fully complied with. Terminal facilities. Modern rail-connected terminal facilities at this port are considered adequate for existing commerce. (See Port Series No. 19.) Operations and results during fiscal year. Maintenance: Contract dredging removed 2,072,000 cubic yards of material from Horn Island Bar and the Sound Channel at a total cost of $2,839,900. Hired labor costs for surveys, supervision and administration and other miscellaneous work amounted to $310,530. Condition at end of fiscal year. The existing project 10-10 MOBILE, ALABAMA DISTRICT was completed in August 1965 and the Krebs Lake project was completed in November 1983. Total Federal costs of existing project to September 30, 1985 were $5,668,543 for new work and $32,758,012 for maintenance, a total of $38,426,555. Contributed funds expended for maintenance amounted to $1,680,970. 18. PENSACOLA HARBOR, FL Location. The project is located in a landlocked bay on the coast of northwest Florida about 50 miles east of the entrance to Mobile bay. (See Coast and Geodetic Survey Charts 490 and 11382.) Previous project. For details see Annual Report for 1938. Existing project. The authorized project provides for: (a) A 35-foot by 500-foot entrance channel about five miles long, from the Gulf of Mexico to lower Pensacola Bay; (b) a 33-foot by 300-foot bay channel; (c) two 33-foot by 300-foot parallel approach channels to opposite ends of the inner-harbor channel; (d) an innerharbor channel 500 feet wide, 33 feet deep, and 3,950 feet long; (e) a 30-foot by 250-foot approach channel to the pierhead line south of Muscogee wharf; and (f) a 15-foot by 100-foot entrance channel into Bayou Chico, thence a channel 14 feet deep, 75 feet wide, and about 4,400 feet long to a turning basin 14 feet deep and 500 feet square. Mean range of tide throughout the harbor is about 1.1 feet near the entrance and about 1.6 feet at the head of bay. Extreme tidal range, except during storms, is about three feet. Plane of reference is mean low water. Modification of the Bayou Chico project to provide for enlarging the entrance channel to 21 by 100 feet, the bayou channel to 20 feet by 100 feet, and deepening the turning basin to 20 feet has been deferred for restudy. (See Table 10-B for authorizing legislation.) Local cooperation. Fully complied with. Terminal facilities. Modern rail-connected terminal facilities at this port are considered adequate for existing commerce. (See Port Series No. 19, revised in 1979.) Operations and results during fiscal year. Maintenance: Contract dredging removed 68,800 cubic yards of material from the entrance channel at a cost of $78,400. Condition and operation studies and miscellaneous costs amounted to $67,498. Condition at end of fiscal year. New work is completed except those features which are deferred for restudy. The modification authorized in 1962 was commenced in March and completed in May 1965. Total Federal costs of the existing project to September 30, 1985 were $875,005 for new work and $6,029,294 for maintenance, a total of $6,904,299. 19. PERDIDO PASS CHANNEL, AL Location. The project is located about midway between Pensacola, Florida and Mobile, Alabama. (See Coast and Geodetic Chart I1378.) Existing project. The existing project provides for a channel 12 feet deep and 150 feet wide for about 1,300 feet from the Gulf of Mexico into the inlet, thence nine feet deep and 100 feet wide for about 2,200 feet to the highway bridge, where the channel branches into two arms, each having dimensions of 9 by 100 feet, one of which extends about 3,400 feet into Terry Cove and the other about 3,200 feet into the southern arm of Perdido Bay. The project also provides for two jetties spaced 600 feet apart at the seaward end. The east jetty has a low weir section, 1,000 feet long to permit passage of littoral drift into a dredged deposition basin 800 feet by 1,200 feet located between the east jetty and the navigation channel. Mean tidal range is 1.1 feet and extreme is 2.8 feet. (See Table 10-B for authorizing legislation.) Local cooperation. Requirements of local cooperation have been fully complied with to date. Terminal facilities. Six marinas, numerous timber piers, docks, and several launching ramps are available. These facilities are considered adequate for existing commerce. Operations and results during fiscal year. Maintenance: Cost of surveys, supervision and ad-ministration and miscellaneous work amounted to $51,595. Condition at end of fiscal year. The existing project was commenced in May 1968 and completed in March 1969. Total Federal costs of the existing project to September 30, 1985 were $629,860 for new work and $5,002,728 for maintenance, a total of $632,589. Contributions from local interest amount to $510,000 for new work and $10,325 for maintenance. 20. WATERWAY CONNECTING TOMBIGBEE AND TENNESSEE RIVERS, AL AND MS Location. The waterway extends from mile 215 in Pickwick pool on the Tennessee River, southerly through northeastern Mississippi and western Alabama, a total of 234 miles, to the confluence of the Black Warrior and Tombigbee Rivers at Demopolis, Alabama. Location. For details see Annual Report for 1953. Existing project. The authorized project provides for a waterway 234 miles long, connecting the Tennessee and Tombigbee Rivers via the East Fork of Tombigbee River and Mackeys and Yellow Creeks. The plan of improvement consists of three sections. (1) the river section, a 9-foot by 300-foot channel for 149 miles between Demopolis and Amory, Mississippi; (2) the lateral canal section, 12 feet by 300 feet for 46 miles from A12m-fooroyt btoy 3B0a0y- foSoptr icnhgasn; naenl d( e(x3c) eptht ei nd tihveid 2e7 smecilteio-lno,n ga divide cut in which the bottom width would be 280 feet) for 39 miles from Bay Springs through the dividing ridge to the Tennessee River; the total lift of 341 feet to be accomplished by 10 locks. Estimated (1984) Federal cost for new work is $1,839,000,000, including $9,600,000 for work by the U.S. Coast Guard, and $9,400,000 for National Park Service; plus, $153,000,000 non-Federal cost for relocations. (See Table 10-B for authorizing 10-11 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 legislation. Local cooperation. Local interests must make and maintain alterations in highways and highway bridges and in sewer, water-supply, and drainage facilities and provide and maintain suitable and adequate river and canal terminals. Officials of the State of Mississippi were notified of these requirements on December 13, 1949, and officials of the State of Alabama were notified on December 20, 1949. Legislation enabling boards of supervisors of the various counties concerned to enter into agreements with the United States relative to navigation projects was adopted by the State of Mississippi in 1950. A compact between the States of Alabama, Mississippi, Tennessee, Kentucky and Florida has been formed for the purpose of promoting the project. The name of this organization is the Tennessee-Tombigbee Waterway Development Authority. During its 1962 session the Mississippi Legislature authorized the formation of the Tombigbee River Valley Water Management District. The District was organized in accordance with the enabling legislation and is empowered to fulfill the requirements of local coooperation for the portion of the project in Mississippi. A satisfactory resolution has been furnished. Durings its 1967 session the Alabama Legislature authorized formation of a public corporation to be named the Tombigbee Valley Development Authority for the purpose of further development of the Tombigbee River and tributary streams. The organization was formed in accordance with the enabling legislation and in a referendum held 5 December 1967 the voters of Alabama authorized a bond issue not to exceed $10,000,000 to finance participation in this project and the Tombigbee River and Tributaries project. A satisfactory resolution has been furnished. Terminal facilities. Docks, storage facilities and handling equipment are still being developed along this new waterway. As of September 30, 1985, only six such facilities were operational, while eight were under construction, and 10 more are planned. The operational facilities are handling grain, wood chips, and logs. When all facilities are complete, about half will be publicly owned and operated. Additional ports and terminals must be completed before the waterway can achieve its full potential. (See Table 10-N for existing locks and dams. Operations and results during fiscal year. New work: Total cost of new work during the fiscal year was $43,785,515 of which $282,146 was for work on Demopolis Lake; $2,610,353 for Gainesville Lock and Dam; $6,299,179 for Aliceville Lock and Dam; $7,475,541 for Columbus Lock and Dam; $3,210,040 for Aberdeen Lock and Dam. Canal section cost included: Lock A, $8,289,615: Lock B, $4,488,444; Lock C, $1,527,700; Lock D, $1,943,001; Lock E, $1,414,797. Other costs associated with the overall project amounted to $6,244.699. Contributed funds amounted to $2,345. Maintenance: Contract dredging removed 2,365,000 cubic yards of material from the river system at a cost of $2,751,593. Cost for operation of the completed portion of the project during the year amounted to $11,170,456, which included general charges ,/of $1,958,717; Gainesville Lock and Dam, $401,824;Aliceville Lock and Dam, $360,999; Columbus Lock and Dam, $418,824; Aberdeen Lock and Dam, $442,550; Lock A, $281,157; Lock B, $346,601; Lock C, $310,456; Lock D, $253,060; Lock E, $283,318; Bay Springs, $332,959; lake charges of $3,028,398. Recreation attendance for CY 1984 totaled 2,603,300 user days. Condition at end of fiscal year. Total Federal costs under the existing project as of September 30, 1985 were $948,955,800 for new work, and $33,892,335 for maintenance for a total of $982,848,135. Construction formally began December 12, 1972 and overall project is about 92 percent complete. The waterway was opened for navigation in January 1985. 21. OTHER AUTHORIZED NAVIGATION PROJECTS (See Table 10-C.) 22. NAVIGATION WORK UNDER SPECIAL AUTHORIZATION Navigation activities pursuant to Section 107, Public Law 86-645, as amended (Preauthorization). Studies conducted under this authority amounted to $115,877. (See Table 10-H.) 23. RECONNAISSANCE AND CONDITION SURVEYS (See Table 10-K.) 24. DEAUTHORIZED PROJECTS Projects deauthorized under Section 12, Public Law 251, 93rd Congress, as amended. (See Table 10-G.) Beach Erosion Control 25. OTHER AUTHORIZED BEACH EROSION CONTROL PROJECT (See Table 10-D.) 26. BEACH EROSION CONTROL PROJECTS UNDER SPECIAL AUTHORIZATION Studies conducted under Section 103, 1962 River and Harbor Act, as amended, amounted to $39,619. (See Table 10-1.) Flood Control 27. OKATIBBEE LAKE, MS Location. The project is located on Okatibbee Creek 37.7 miles above its mouth, in Lauderdale County, Mississippi, seven miles northwest of Meridian. 10-12 MOBILE, ALABAMA DISTRICT Existing project. The project provides for a dam and reservoir for flood control, water supply, water quality control, fish and wildlife, and recreation. The dam consists of a compacted earth fill 6,540 feet long with the top elevation 369.8 feet above national geodetic datum, with top width of 18 feet. The spillway, which is located 1,500 feet east of the east end of the dam, is an unpaved free overflow type, 1,500 feet long with a fixed crest at elevation 359. A sluice intake structure near the center of the dam serves a 9.0-foot diameter concrete conduit. Storage allocated for water supply and water quality control varies seasonally from 21,400 acre-feet to 34,300 acre-feet between a minimum elevation of 328 and topof- conservation-pool elevation varying from 339 to 343. Storage varying from 46,500 acre-feet to 59,500 feet between the top of the conservation pool and elevation 352 has been reserved exclusively for storage of flood waters. (See Table 10-B for authorizing legislation.) Local cooperation. Complied with to date. Operations and results during fiscal year. New Work: Engineering and design of public use facilities cost $421,348. Maintenance: Costs for the year for ordinary maintenance and recreational management amount to $813,827. Benefits attributed to flood control storage and regulation amounted to $130,900. Recreation attendance at the reservoir during CY -1984 totaled 1,286,706 recreational user days. Condition at end of fiscal year. Construction began in June 1965, and was completed in November 1968. Total Federal costs of the existing project as of September 30, 1985 were $9,169,266 for new work and $7,395,566 for maintenance, a total of $17,014,832. 28. TALLAHALA CREEK LAKE, PASCAGOULA RIVER, MS Location. The project is on Tallahala Creek, 81.1 miles above its mouth, in Jasper County, Mississippi, 13 miles north of Laurel. Existing project. The project provides for a dam and reservoir for flood control, water supply, water quality control, recreation, and fish and wildlife enhancement. The dam will consist of a compacted earth fill 8,000 feet long, with top elevation 343.5 feet above national geodetic datum, or a maximum 71.5 feet above streambed elevation, with a top width of 18 feet, and a 300-foot long saddle dike with maximum height of 15 feet in the left abutment. The spillway which is 6,000 feet northeast of the left abutment, will consist of an unpaved, freeoverflow type, 500 feet long, with fixed crest at elevation 335.0. A sluice intake structure near the center of the dam will serve an 8-foot diameter, horseshoeshaped concrete conduit. The reservoir at maximum pool elevation 306.5 will have an area of 4,000 acres and a total capacity of 63,000 acre-feet of which 35,900 acrefeet between elevations 288.5 and 302.0 will be used for water supply, 20,000 acre-feet between elevations 302.0 and 306.5 will be used for water quality improvement, and 7,100 acre-feet below elevation 288.5 will consist of dead storage. A volume varying seasonally from 50,000 to 70,000 acre-feet between elevations 306.5 and 315.0 will be reserved for flood storage. Estimated Federal cost (1984) is $120,000,000. (See Table-B for authorizing legislation.) Local cooperation. Local interests will be required to reimburse the United States for all costs allocated to water supply in accordance with the Water Supply Act of 1958, as amended; and one-half of the separable first cost of the project allocated to general recreation and fish and wildlife enhancement. In addition, local interests are required to reimburse the United States for the annual operation, maintenance and replacement cost allocated to water supply, and bear all cost of operation, maintenance and replacement of recreation and fish and wildlife areas and facilities for initial development. Operations and results during fiscal year. New work: Land and damages and engineering and design cost $593. Condition at end of fiscal year. Construction has not been initiated. 29. AIRPORT ROAD BRIDGE, FRANKSTOWN, MS Location. The project is in northeastern Mississippi. The Airport Road Bridge crosses Twenty Mile Creek and is located about 0.5 mile north of Frankstown, in Prentiss County, Mississippi. Existing Project. The project provides for streambank protection along a 300-foot reach of the stream. The creek's banks and bottom were graded and protected with 24 inches of riprap on 6 inches of bedding material and filter fabric. A 3-foot-high weir was placed just downstream from the bridge. (See Table 10-B for authorizing legislation.) Local cooperation. Fully complied with. Project has been turned over to local sponsor to maintain. Operations and results during fiscal year. New Work: Construction of the project during fiscal year cost $195,665. Condition at end of fiscal year. Project completed December 21, 1984. 30. BILOXI RIVER AT LORRAINE ROAD, HARRISON COUNTY, MS Location. The Biloxi River originates in Stone County approximately 10 miles northwest of Harrison County. The river has a drainage area of 271 square miles, flows generally south to southeast through De Soto National Forest before it enters the Back Bay of Biloxi. The streambank protection is located at two sites on the left descending bank of Lorraine Road. Existing Project. The project provided for the protection of the streambank in two areas where bank erosion was threatening to undermine or erode Lorraine Road. At Site No. I the work consisted of regrading the streambank to a slope of I vertical on 2 horizontal and 10-13 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 placement of filter fabric, bedding material, and riprap protection. At Site No. 2 the work consisted of the placement of fill material, topsoil, and grass sod. (See Table 10-B for authorizing legislation.) Local cooperation. Fully complied with and turned over to local sponsor to maintain. Operation and results during fiscal year: None. Condition at end of fiscal year. Project completed in October 1983. 31. GORDONS CREEK, HATTIESBURG, MS Location. The project is located along the lower 12,320 feet of Gordons Creek between its mouth at Leaf River and Broad Street Bridge, within the city limits of Hattiesburg, Ms. Existing project. The authorized project provides for flood damage reduction along and upstream of the project limits by channel clearing, snagging, widening and the removal of debris. (See Table 10-B for authorizing legislation.) Local cooperation. Fully complied with. Project has been turned over to local interest to maintain. Operations and results during fiscal year. New work: Miscellaneous costs amounted to $1,327. Flood control benefits attributed to the project through FY 1985 amounted to $2,085,300. Condition at end of fiscal year. Construction commenced in June 1979 and was essentially completed in June 1980. Total Federal costs for the project as of September 30, 1985 were $802,026 all for new work. 32. MURDER CREEK, EAST BREWTON, AL Location. The project is located in the city of East Brewton along the left bank of Murder Creek in the vicinity of Forrest and Snowden Avenues. Existing project. The project consists of non-structural measures of flood plain evacuation and flood proofing of selected buildings for the reduction of flood damages. Local cooperation. Fully complied with. Project turned over to local sponsor to maintain. Operations and results during fiscal year. New work: Miscellaneous costs amounted to -$3,911. Condition at end of fiscal year. This non-structural plan was completed June 1984 and entire project completed September 1985. Total costs to date have amounted to $902,944. 33. NOXUBEE RIVER RELIEF BRIDGE, SHUQUALAK, MS Location. The Noxubee River relief bridge is located on the Shuqualak-Mahorner Road near Shuqualak, Mississippi. The Noxubee River at this location flows through Noxubee County, which is located in east central Mississippi. The project is about 48 miles south of Columbus, Mississippi. Existing project. The project provides for streambank protection at Noxubee River relief bridge consisting of grading and protecting of banks with 24 inches of riprap on 6 inches of bedding material and filter fabric. This would preclude any erosion from high velocities or from sudden drawdown associated with receding floodwaters. (See Table 10-B for authorizing legislation.) Local cooperation. The local sponsor has not obtained necessary rights-of-ways for project construction. Operation and results during fiscal year. New work: Miscellaneous costs amounted to $14,543. Condition at end of fiscal year. Project to be advertised for construction when necessary rights-of-ways have been obtained by local sponsor. 34. PUMPKINVINE CREEK, EMERSON, GA Location. Emerson, Georgia is located in south Bartow County approximately 50 miles northwest of Atlanta. Allatoona Dam and Lake is about 5 miles northwest of Emerson with the Etowah River flowing east to west just north of the town. In 1972, a wastewater treatment pond was built on the right descending bank to handle the raw sewage in the surrounding area. Approximately 3,500 homes and small businesses in Emerson are served by the pond and is the only wastewater treatment for the area. Existing project. The project consists of protection of the streambank along Pumpkinvine Creek where bank erosion was threatening to erode the wastewater treatment pond dike. The protection was achieved by construction of a stone revetment along the streambank adjacent to the dike. The work consisted of placing quarry run stone along the streambank to a slope of I vertical on 1.5 horizontal, and placement of a 10-foot thick stone toe at the base of the streambank for added stability. (See Table 10-B for authorizing legislation.) Local cooperation. Fully complied with and project turned over to local sponsor to maintain. Operation and results during fiscal year. New work: None. Condition at end of fiscal year. Project completed in November 1983. 35. SEWERLINE PROTECTION, VALLEY, AL Location. Valley, Alabama is located on the west bank of the Chattahoochee River in the southeast corner of Chambers County. The West Point Lake and Dam is located approximately 11 miles up river from Valley and controls a drainage area of approximately 3600 square miles. A sanitary sewage line and pumping station were built in 1972 to provide service from approximately 200 homes and several businesses located near Valley. This line serves as the only sewage 10-14 MOBILE, ALABAMA DISTRICT transport for this area. Existing project. The project provides for the restoration of approximately 1600 linear feet of streambank. This will consist of placing approximately 1550 cubic yards of No. 5 riprap on 4445 square yards of filter fabric. Any reshaping of the bank will be done by placing backfill material as opposed to cutting the existing streambank. The reshaped bank will then be grassed. (See Table 10-B for authorizing legislation.) Local cooperation. Fully complied with. Operation and results during fiscal year. New work: Engineering and design costs amounted to $17,387. Condition at end of fiscal year. Construction contract was awarded on 17 September 1985. Anticipate construction to be completed by January 1986. 36. SOPE CREEK, MARIETTA, GA Location. The project is located in Marietta, Georgia in Cobb County which is in the north-central section of Georgia, just north-northwest of Atlanta. Sope Creek is a small tributary of the Chattahoochee River and flows generally from northwest to southeast from its beginning in the city of Marietta. Existing project. The project provides for flood control measures along Sope Creek in Cobb County, Georgia. The project provides for both a structural and nonstructural component. The structural component provides for clearing and snagging of the creek. This would involve the clearing of all material, trees, shrubs and any underbrush less than 12 inches in diameter from a strip 30 feet wide on each side of the creek and removing all trees, shrubs and underbrush within the creek banks. Snagging would involve the removal of all fallen trees and debris which are in the creek. The nonstructural component provides for the evacuation of 13 structures located on the west side of the creek within the Fox Hill subdivision. The project provides for purchase and removal of the structures. (See Table 10-B for authorizing legislation.) Local cooperation. Fully complied with, except non- Federal were unable to obtain easement in FY 1985 for structural clearing and snagging. Operation and results during fiscal year. New Work: Engineering and design and real estate acquisition costs amounted to $833,383. Condition at end of fiscal year. The nonstructural component as of 30 September 1985, 10 structures were acquired and removed. The structural portion, clearing and snagging, will be readvertised in March 1986. 37. TOMBIGBEE RIVER (EAST FORK), MISS. AND ALA. Location. The project is located on the Tombigbee River and its tributaries between the junction of Browns and Mackeys Creek in Itawamba County, Mississippi, for a distance of 53 miles along the East Fork of the Tombigbee River, from Walkers Bridge at the junction of Browns and Mackeys Creeks to the Monroe County line, by clearing the banks of trees and underbrush to flood stage, the removal of drift jams and the excavation of 13 cutoff channels; and for additional channel improvements and related works for flood control of the Tombigbee River and tributaries above the mouth of and including the Noxubee River in accordance with plans approved by the Chief of Engineers, to protect people and valuable agricultural property from overflow waters of the Tombigbee River. (See Table 10-B for authorizing legislation.) Local cooperation. Fully complied with on work done under the 1936 Flood Control Act. Work to be done under authority of the 1941 Flood Control Act requires local interest to provide all lands, easements, and rights-of-way for project construction; hold and save the United States free from damages due to construction of the project; and maintain and operate all the works after completion in accordance with regulations prescribed by the Secretary of the Army. Operations and results during fiscal year. Maintenance: Ordinary maintenance cost $452,213. Condition at end of fiscal year. The project for Itawamba County, as authorized in the 1936 Flood Control Act, was completed during fiscal year 1940. No work has been done on the extension of the project authorized in the 1941 Flood Control Act. The over-all project, as modified, is about 55 percent completed. Total Federal costs of the existing project as of September 30, 1985 were $134,801 for new work and $2,213,996 for maintenance, a total of $2,348,797. 38. TOMBIGBEE RIVER TRIBUTARIES, MS AND AL Location. The Tombigbee River rises in extreme northeast Mississippi and flows southerly through eastern Mississippi and western Alabama, emptying into the Mobile River about 45 miles above its mouth at Mobile, Alabama. Tributaries to be improved for flood control are all in northeast Mississippi and northwest Alabama. Existing project. The authorized project provides for improvement of 22 tributaries of the Tombigbee River by means of channel clearing and snagging. Approved estimate of cost (1984) for new work is $52,446,900; consisting of $50,000,000 Federal funds, and $2,446,900 non-Federal funds. (See Table 10-B for authorizing legislation.) Local cooperation. Local interests must furnish lands and rights-of-way for construction; make all roads, highway bridge, and utility changes, alterations, additions, and relocations necessary for the project; hold the United States free from damages; prevent future encroachments along the improved channels; maintain all works after completion; and contribute $12,146,600 in cash or equivalent work. Operations and results during fiscal year. Engineer- 10-15 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 ing and design costs for Luxapalila and Twenty Mile Creeks, and Tibbee River Basin were $556,135; work on channels and canals cost $335,996; land and damages, $59,998 and miscellaneous, $33,200. Condition at end of fiscal year. Construction commenced in July 1965. and is proceeding stream by stream as funds are made available. Federal cost of existing project as of September 30, 1985 was $14,925,774 for new work. Contributed funds for new work amounted to $63,281. 39. U.S. HIGHWAY 11 BRIDGE, FOSTERS, AL Location. The U.S. Highway 11 Bridge is located near the community of Fosters, in Tuscaloosa County, 'Alabama and crosses over the Black Warrior River at navigation mile 321.0 The bridge is about 10 miles southwest of Tuscaloosa, Alabama. Existing project. The project provides for slope protection by placing riprap along a 240-foot reach of the left descending bank at the bridge. (See Table 10-B for authorizing legislation.) Local cooperation. Fully complied with. Operations and results during fiscal year. New Work: Engineering and design costs amounted to $18,829. Condition at end of fiscal year. Construction contract was awarded on 13 September 1985. Anticipate construction to be completed by January 1986. 40. U.S. HIGHWAY 43 BRIDGE, CHICKASAW BOGUE CREEK, LINDEN, AL Location. Chickasaw Bogue Creek originates in eastcentral Marengo County and flows southwest for about 10 miles to enter the Tombigbee River from its east bank 145.4 miles above its mouth. The creek has a total drainage area of 353 square miles of which 258 square miles lie above the U.S. Highway 43 bridge. The bridge is located 0.5 mile north of the Linden City limits. Existing project. The project consists of restoration of the channel and streambanks of Chickasaw Bogue Creek to the alignment which existed at the time the bridge was constructed in 1951, and the stabilization of the channel under that alignment. The work consisted of excavation of a sand bar located immediately upstream of the bridge and protruding from the left bank, the construction of an embankment under the bridge extending from the right top bank to the right concrete bridge support and a dike along the right side of the channel beginning at the embankment and extending upstream for a distance of 360 feet. (See Table 10-B for authorizing legislation.) Local cooperation. Fully complied with and turned over to local sponsor to maintain. Operations and results during fiscal year. New work: None. Condition at end of fiscal year. Project completed in December 1980. 41. WOLF CREEK, U.S. HIGHWAY 45 BRIDGE, PRENTISS COUNTY, MS Location. The U.S. Highway 45 bridge is located in Prentiss County, Mississippi in the northeastern part of the state. The project is located approximately 75 miles north of Columbus, Mississippi. The U.S. Highway 45 bridge crosses Wolf Creek at mile 0.9 above the mouth of its mouth. Existing project. The project provides for slope protection under the U.S. 45 bridge. The banks would be graded and protected with 24-inches of riprap on 6-inches of bedding material and filter fabric. Threefoot high weirs would be placed just downstream from the bridge to provide a backwater effect and a section of riprap at the weir would be grouted. (See Table 10-B for authorizing legislation.) Local cooperation. Fully complied with and turned over to local sponsor to maintain. Operations and results during fiscal year. New Work: Miscellaneous costs amounted to $138,706. Condition at end of fiscal year. Project completed 21 December 1984. 42. OLD HIGHWAY 82 BRIDGE, COLUMBUS, MS Location. The Old Highway 82 bridge is located at Columbus, Mississippi in east-central Mississippi and crosses the Tombigbee River at river mile 364.96. It is about 131 miles northeast of Jackson, Mississippi. Existing project. The project provides protection along the right descending bank. The slope protection would consist of 24 inches of riprap on 6 inches of bedding material and a filter fabric. The riprap placement would begin approximately 140 feet downstream of the centerline of the bridge and extend upstream along the right descending bank for 330 feet. (See Table 10-B for authorizing legislation.) Local cooperation. Fully complied with. Operations and results during fiscal year. New Work: Engineering and design and miscellaneous costs amounted to $35,117. Condition at end of fiscal year. Construction contract was awarded on 25 July 1985. Anticipated construction to be completed in early FY 1986. 43. WOLF CREEK, HIGHWAY 362 BRIDGE, PRENTISS COUNTY, MS Location. The Highway 362 bridge is located in Prentiss County, Mississippi, connecting the towns of Frankstown and Wheeler. Prentiss County is in northeast Mississippi. Highway 362 spans three water 10-16 MOBILE, ALABAMA DISTRICT courses, crossing Twenty-Mile Creek at mile 20.7, Wolf Creek at mile 0.1 and Osborne Creek at mile 0.5. Existing project. The project provides restoration and stabilization of the banks of the creek under and around the bridges to remove the danger of bridge failure due to erosion. The banks were graded to I vertical on 2 horizontal and protected with 18 inches of riprap placed on 6 inches of bedding material and filter fabric. Three-foot high weirs placed just downstream from each bridge provides a backwater effect and encourage small amounts of deposition in these areas where erosion must be prevented. (See Table 10-B for authorizing legislation.) Local cooperation. Fully complied with and turned over to local sponsor to maintain. Operations and results during fiscal year. New Work: None. Condition at end of fiscal year. Construction commenced in June 1983 and was completed in October 1983. Federal expenditures as of September 30, 1985 were $114,743. 44. OSBORNE CREEK, HIGHWAY 362 BRIDGE, PRENTISS COUNTY, MS Location. The Highway 362 bridge is located in Prentiss County, Mississippi, connecting the towns of Frankstown and Wheeler. Prentiss County is in northeast Mississippi. Highway 362 spans three water courses, crossing Twenty-Mile Creek at mile 20.7, Wolf Creek at mile 0.1 and Osborne Creek at mile 0.5. Existing project. The project provides restoration and stabilization of the banks of the creek under and around the bridges to remove the danger of bridge failure due to erosion. The banks were graded to 1 vertical and 2 horizontal and protected with 18 inches of riprap placed on 6 inches of bedding material and filter fabric. Three-foot high weirs placed just downstream from each bridge provides a backwater effect and encourage small amounts of deposition in these areas where erosion must be prevented. (See Table 10-B for authorizing legislation.) Local cooperation. Fully complied with and turned over to local sponsor to maintain. Operations and results during fiscal year. New Work: None. Condition at end of fiscal year. Construction commenced in June 1983 and was completed in October 1983. Federal expenditures as of September 30, 1985 were $250,000. 45. INTERSTATE 20 BRIDGES OVER PEARL RIVER JACKSON, MS Location. The Pearl River drains an 8,760 square mile area covering most of the south central Mississippi and a small part of southeastern Louisiana. From its source in Neshoba County, Mississippi, the Pearl River flows southwesterly about 130 miles to Jackson, Mississippi, where it is crossed by Interstate 20 at mile 286.6, the location of the streambank erosion protection project. Existing project. The project provided for the protection of the bridge which was endangered by erosion occurring on both banks of the river. The right overbank was being eroded primarily by flood flows. During high water flow cut across the inside of a small bend in the river at the bridge and was developing what appeared to be a small chute cut-off. Piers in the overbank near the main rive span were in the path of the developing cut-off and would have been endangered if left unprotected. Protective works constructed on the right bank consist of two dikes, one located about 270 feet upstream of the westbound lane and second about 410 feet upstream of this lane. These dikes are designed to direct flow toward the opposite bank. They are rockfill structures with side slopes of I vertical to 1.5 horizontal and top widths of three feet. The two dikes were placed on filter cloth and extend perpendicular to the bank about 90 feet and 175 feet, respectively. Protection against scour at the landward end of the dikes is provided by a 24-inch layer of riprap on a 12-inch bedding layer underlain by filter cloth. Direct protection of piers in the path of the developing cut-off is provided by a 24-inch layer of riprap on bedding material and filter cloth. The riprap blanket is approximately 100 feet by 125 feet and protects three bridge bents. Additional protection is provided for these bents by a small 60-foot long dike placed perpendicular to an overbank drain downstream of the developing cut-off and adjacent to the bridge pier riprap. The left bank was already suffering some erosion because it is on the outside of a natural bend in the river, and the dike construction was expected to increase the local left bank velocities. Erosion on the left bank was prevented by construction of a 24-inch layer of riprap on a layer of bedding material and filter cloth. The riprap is about 750 feet long and extends from about 200 feet upstream of the westbound lane to 110 feet downstream of the eastbound lane. Construction of the streambank erosion protection project was performed by the Mississippi State Highway Department with U.S. Government furnished materials. (See Table 10-B for authorizing legislation.) Local cooperation. Fully complied with and project turned over to local sponsor to maintain. Operation and results during fiscal year. New work. None. Condition at end of fiscal year. Project completed in October 1981. 46. INTERSTATE 59 BRIDGES, FOSTERS, AL Location. The Interstate 59 bridges are located near 10-17 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 the community of Fosters in Tuscaloosa County, Alabama and crosses over the Black Warrior River at navigation mile 320.5 The bridges are about 10 miles southwest of Tuscaloosa, Alabama. Existing project. The project provides streambank protective measures at the bridges. Bank stabilization would consist of placing riprap along a 195-foot reach of the left descending bank at the bridge. (See Table 10-B for authorizing legislation.) Local cooperation. Fully complied with. Operation and results during fiscal year. New Work: Engineering and design costs amounted to $15,179. Condition at end of fiscal year. Construction contract was awarded on 13 September 1985. Anticipate construction to be completed by January 1986. 47. INSPECTION OF COMPLETED FLOOD CONTROL PROJECTS Local flood protection works for which inspection is performed under this heading consist of levee projects at West Point, Georgia, on the Chattahoochee River; Beaver Creek at Montezuma, Georgia, in the Flint River Basin; Elba and Geneva, Alabama in the Choctawhatchee River Basin; Rome, Georgia, and Little Wills Creek at Collinsville, Alabama, in the Alabama-Coosa River Basin. Channel rectification projects include Little Cove Creek, Glencoe, Alabama, Black Creek, Gadsden, Alabama and Armuchee Creek, Floyd and Chattooga Counties, Georgia in the Alabama-Coosa River Basin; Big Brown Creek, Donivan Creek, Twenty Mile Creek and Mantachie Creek, near Fulton, Mississippi, Stanifer Creek near Amory, Mississippi, Houlka Creek and Sakatonchee Creek in Chickasaw and Clay Counties, Mississippi, James Creek in Monroe County, Mississippi, Sun and Trim Cane Creeks, Oktibbeha County, Mississippi, and Luxapalila Creek, Lowndes County, Mississippi, all in the Tombigbee River Basin; Gordon's Creek, Hattiesburg, Mississippi and Sowashee Creek, Meridian, Mississippi in the Pascagoula River Basin; Burnt Corn and Murder Creeks, Brewton, Alabama in the Conecuh River Basin; Autauga Creek, Prattville, Alabama; Poley Bridge, Goose Pond and Walnut Creeks, Clanton, Alabama; Pinchgut Creek, and Cahaba River, Trussville, Alabama; Yellow Jacket Creek, Hogansville, Georgia; Town Creek, Americus, Georgia; and Lake Douglas in Bainbridge, Georgia. Shore protection and erosion control projects include Valparaiso, Florida; Harrison County, Mississippi; Lorraine Road, Biloxi, Mississippi; Leaf River, Mahned, Mississippi; Pumpkinvine Creek, Emerson, Georgia; and Chickasawbogue Creek, US Highway 43 Bridge, Linden, Alabama. A local drainage project in Jackson County, Florida is also inspected under this program. The project at Rome and Montezuma, Georgia and Collinsville, Alabama include pumping stations. Inspections were made during FY 85 to determine the extent of compliance with approved regulations for maintenance and operation of the project. Responsible local officials were advised of inadequacies in the maintenance and operation of the local flood protection works under their jurisdiction where appropriate. Followup for compliance of the deficient projects continued during the year. Fiscal year costs were $25,892. Total cost to September 30, 1985, was $351,601 charged to maintenance. 48. OTHER AUTHORIZED FLOOD CONTROL PROJECTS (See Table 10-E) 49. FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION Flood Control activities pursuant to Section 205, Public Law 858, 80th Congress, as amended (Pre-authorization). Snagging and Clearing for flood control pursuant to Section 208 of Flood Control Act of 1954, as amended. Emergency streambank and shoreline protection pursuant to Section 14 of the Flood Control Act of 1946, as amended. (See Table 10-J) Emergency flood control activities-repair, flood fighting, and rescue work under Public Law 99, 84th Congress, and antecedent legislation, and disaster relief and assistance under Public Law 288, 93d Congress. (See Table 10-J) Multiple-Purpose Projects Including Power 50. ALABAMA-COOSA RIVERS, AL AND GA Location. Alabama River is formed 18 miles above Montgomery, Alabama, by the junction of the Coosa and Tallapoosa Rivers. It then flows southwesterly through Alabama 318 miles and unites with the Tombigbee River about 45 miles north of Mobile, in southwestern Alabama, to form the Mobile River. (See Geological Survey maps for central and southwest Alabama.) The Coosa River is formed at Rome, Georgia, in northwest Georgia, by the junction of the Oostanaula and Etowah Rivers, which have their sources in southeastern Tennessee and northern Georgia. From Rome the Coosa River flows southwesterly through Georgia and Alabama 286 miles and unites with the Tallapoosa River near Montgomery, Alabama, at about the center of the State, to form the Alabama River. (See Geological Survey maps for northeast Alabama, southeast Tennessee, and northwest Georgia.) Previous project. Projects for Alabama River: for details see page 1837, Annual Report for 1915; page 725, Annual Report for 1938; and page 592, Annual Report for 1944. Projects for Coosa River: for details see page 1837, Annaul Report for 1915; page 728, Annual Report for 1938; and page 594, Annual Report for 1944. Existing project. The authorized project provides for 10-18 MOBILE, ALABAMA DISTRICT full development of the Alabama-Coosa Rivers and tributaries for navigation, flood control, power, recreation, and other purposes, in accordance with plans under preparation by Chief of Engineers, subject to modifications thereof which may be advisable for increasing development of hydroelectric power. (See Table 10-B for authorizing legislation.) Public Law 436, 83rd Congress, suspended authorization of the comprehensive plan, insofar as it provides for development of hydroelectric power for Coosa River, to permit non- Federal interests to develop the Coosa River by construction of a series of dams in accordance with conditions of a license issued pursuant to Federal Power Act and in accordance with certain other provisions and requirements of the aforementioned public law. The present phase of improvement provides for construction of Robert F. Henry and Millers Ferry multiplepurpose improvements, Claiborne Lock and Dam, and supplemental channel work providing for a nine-foot deep navigation channel from the mouth of the Alabama River to Montgomery, Alabama, and for construction of Carters Dam, a multiple-purpose improvement on Coosawattee River, Georgia. Local cooperation. Requirements of local cooperation will be determined as formulation of plans for development of projects progress. No. action in the matter of local cooperation has been initiated. Terminal facilities. On the east bank of the river a natural landing connects with city streets at Montgomery. Wofford Oil Company has a small wharf about 10 miles below Montgomery equipped for handling petroleum products. There are also various natural landings along the river. Facilities and natural landings on Alabama River are considered adequate for existing commerce. Operations and results during fiscal year. New work: Recreation facilities and engineering, design, supervision and administration at Robert F. Henry Lock and Dam cost $12,150. Public use areas at Millers Ferry Lock and Dam cost $51,806. Engineering and design for Coosa River navigation segment amounted to $20,520. Total cost of new work amounted to $84,476. Maintenance: Contract dredging removed 714,100 yards cubic of material from the river system at a cost of $1,414,686. General charges for recreation, supervision and administration and miscellaneous costs amounted to $2,351.453. Coosa River Reservoir operations cost $26,862 and lock operations $319,792. In addition, operation of Robert F. Henry Lock and Dam cost $1,776,575, Millers Ferry Lock and Dam, $2,544,735; Carters Lake, $2,361,379; all for a total maintenance cost of $10,795,482. Condition at end of fiscal year. Construction was initiated on Carters Dam in April 1962 on Millers Ferry Lock and Dam in April 1963, Claiborne Lock and Dam in May 1965, and Robert F. Henry Lock and Dam in March 1966. Carters Dam was essentially completed in FY 1980. The authorized nine-foot navigation channel to Montgomery, Alabama was opened to traffic in January 1972. Overall construction is essentially complete at Millers Ferry Lock and Dam. Construction of Robert F. Henry Lock and Dam is essentially complete. Total Federal costs of the existing project as of September 30, 1985 are $403,161,995, including $305,687,174 for new work and $97,474,821 for maintenance. (See Table 10-L.) 50A. CARTERS LAKE, GA Location. The damsite is in Murray County, Georgia, on the Coosawattee River 26.8 miles above its junction with Conasauga River, one of the headwater tributaries of the Alabama-Coosa system. It is 60 miles north of Atlanta near the town of Carters, Georgia. The reservoir is in both Murray and Gilmer Counties. Existing project. The authorized project consists of a 1,950-foot long rockfill dam across the river, three saddle dikes on the left bank, a 258-foot long high-level, gated spillway on the left bank, a power house on the right bank having two conventional units with a generating capacity of 125,000 kilowatts each and two pumpgenerating units of the same size, and a regulating dam 2,855 feet long with a gated spillway 208 feet long 1.5 miles downstream from the main dam. The lake has an area of 3,220 acres, at maximum power pool elevation 1,072, total capacity of 472,800 acre-feet, of which 134,900 acre-feet is usable for power and 95,700 acrefeet reserved for flood control and 242,200 acre-feet dead storage. For other information see description of Alabama-Coosa project. Operations and results during fiscal year. New Work: None. Maintenance: Operation and ordinary maintenance of the dam, reservoir, powerhouse, service and recreational activities and administration incidental thereto cost $2,361,379. Gross power generation amounted to 480,683,000 kilowatt hours during FY 1985, of which 477,445,000 were delivered to Southeastern Power Administration. Recreation attendance during CY 1984 totaled 824,000 recreational user days. Condition at end of fiscal year. Construction which commenced in April 1962 was essentially completed in September 1980. Total Federal costs of the existing project as of September 30, 1985 are $129,982,773, including $111,139,474 for new work and $18,843,299 for maintenance. 50B. CLAIBORNE LOCK AND DAM, AL Location.The site is in Monroe County at mile 81.8 on the Alabama River, 15 miles northwest of Monroeville and 5.7 miles upstream from the U.S. Highway 84 bridge. Existing project. The authorized project consists of a short earth dike on the right bank, a combination of a fixed-crest and gated spillway extending across the river channel and into the left bank, a navigation lock and mound on the left bank, and an earth dike extending across the left overbank to high ground. Normal upper 10-19 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 pool is at elevation 35 and the minimum pool will be elevation 32 to provide storage for reregulation of Millers Ferry powerplant releases. The 60-mile long reservoir has an area of 5,850 acres and a volume of 96,360 acre-feet. For other information see description of Alabama-Coosa projects. Operations and results during fiscal year. New work: none. Maintenance: none. Recreation attendance during CY 1984 totaled 682,500 user days. Condition at end of fiscal year. Construction began in May 1965 and was completed in FY 1976 at a total cost of $27,997,450. 50C. ROBERT F. HENRY LOCK AND DAM, AL Location. The site is in Lowndes and Autauga Counties at mile 245.4 on the Alabama River, 26 miles west of Montgomery. Existing project. The authorized project provides for a navigation lock, a gated spillway, and a power plant located at mile 245.4. The normal upper pool is at elevation 125.0 and the minimum lower pool due to the Millers Ferry Lock and Dam is at elevation 80.0. The structures consist of earth dikes and a power plant on the right bank, a gated spillway in the river channel, a lock and mound on the left bank, and an earth dike extending upstream parallel to the Western Railway of Alabama. The total length of the structures is about 14,962 feet with maximum height above the foundation at the power plant intake about 101 feet. The power plant contains four 17,000-kw. units. The 88-mile long reservoir has an area of 12,300 acres at normal pool level and a total capacity of 234,200 acre-feet. The lock has a chamber 84 feet wide and 600 feet long and provides a 12-fo6t depth over the lower miter sill. For other information see description of Alabama-Coosa project. Operations and results during fiscal year. Total cost of new work amounted to $12,150 for recreation facilities and engineering, design, supervision and administration. Maintenance: Operation and maintenance cost amounted to $1,776,575. Gross power generation amounted to 289,685,000 kilowatt-hours during FY 1985, of which 287,953,000 were delivered to Southeastern Power Administration. Recreation attendance at R.E. "Bob" Woodruff Lake during CY 1984 totaled 2,231,200 user days. Condition at end of fiscal year. Construction began in March 1966 and is essentially complete. The first powerhouse unit was placed in operation in June 1975, with the last unit on line in November 1975. Total Federal costs of the project as of September 30, 1985 were $98,331,795, including $83,360,007 for new work and $14,971,788 for maintenance. 50D. MILLERS FERRY LOCK AND DAM, AL Location. The site is in Wilcox County at mile 142.2 on the Alabama River, 10 miles northwest of Camden, Alabama, and 30 miles southwest of Selma. Existing project. The project consists of an earth dike on the right bank, a concrete, gravity-gated spillway in the river channel, a lock and mound on the left bank, an earth dike extending downstream paralleling the lock, to the powerhouse intake structure; a powerhouse, and an earth dike extending to high ground on the left bank. Normal upper pool is at elevation 80. The powerplant contains three 25,000 kilowatt units. The 103-mile long reservoir has an area of 17,200 acres at normal pool level and a total capacity of 331,800 acre-feet. The lock chamber is 84 by 600 feet with a 13-foot depth over the miter sills. For other information see description of Alabama-Coosa project. Operations and results during fiscal year. Total cost of new work amounted to $51,806 for public use facilities. Maintenance: Operation and maintenance of lock, dam, powerhouse, reservoir, and administration incidental thereto cost $2,544,735. Gross power generation amounted to 368,952,000 kilowatt-hours during FY 1985, of which 365,768,000 kilowatt-hours were delivered to Southeastern Power Administration. Recreation attendance at William "Bill" Dannelly Reservoir during CY 1984 totaled 2,347,000 user days. Condition at end of fiscal year. Construction began in April 1963. The lock was placed in temporary operation in June 1968 and opened to full use in November 1969. The powerhouse units were placed on line during April and May 1970. The project was essentially completed in 1980. Total Federal costs of the project as of September 30, 1985 were $63,083,731 for new work and $26,434,707 for maintenance, a total of $92,518,438. 50E. COOSA RIVER NAVIGATION Location. The Coosa River is one of the two major tributaries forming the Alabama River approximately 18 miles northeast of Montgomery, Alabama. From its source at the juncture of the Etowah and Oostanaula Rivers in northwest Georgia, it flows southwesterly about 286 miles to join with the Tallapoosa River in forming the Alabama River. Existing project. The improvement of the Alabama- Coosa River for navigation to Rome, Georgia was authorized by Congress in the River and Harbor Act of 1945. A report in House Document 320, transmitted to Congress on 27 January 1960, recommended that the navigation project for the Coosa River from Montgomery to Gadsden be accomplished after the waterway to Montgomery was assured. The plan of improvement identified in House Document 320 provided for a waterway 9 feet deep with widths of 200 feet to Montgomery, Alabama, and 150 feet to Rome, Georgia. The water-way to Montgomery has essentially been completed. The estimated 1985 cost for the waterway from Montgomery to Gadsden is $1,359,000,000 of which $1,304,000,000 is Federal and $55,000,000 non- Federal. 10-20 MOBILE, ALABAMA DISTRICT Operations and results during fiscal year. Funding was initiated in FY 1978 for preconstruction planning. FY 1985 costs were $20,520 for engineering, design, supervision and administration. In addition, general investigations funds expended amounted to $13,062 for advanced engineering and design. 51. ALLATOONA LAKE, COOSA RIVER BASIN, GA Location. The project is on Etowah River in Bartow County, Georgia, about 48 miles upstream from Rome, Georgia, about five miles due east of Cartersville, Georgia, and about 2,000 feet downstream from mouth of Allatoona Creek. The reservoir extends about 28 miles up the Etowah River at maximum power-pool elevation of 840 feet above mean sea level. Existing project. The authorized project provides for a dam and reservoir for flood control, regulation of streamflow for navigation, and development of hydroelectric power. Height above the river bottom of the concrete, gravity-type dam is about 190 feet, from elevation 690 feet to 880 feet national geodetic datum. The spillway, with crest at elevation 835, is controlled by nine tainter gates, 40 feet wide by twenty-six feet high, and two tainter gates, 20 feet wide by twenty-six feet high; having a combined discharge capacity of 321,000 cubic feet per second with the water surface at elevation 870.3. One 48-inch diameter sluicing conduit with a free discharge valve and four sluices, 5 feet-8 inches wide by 10 feet high, are included in dam. Installed generating capacity consists of two 36,000 kilowatt units and one 2,000 kilowatt unit, or a total of 74,000 kilowatts. Ultimate installed capacity will be 110,000 kilowatts. The reservoir, covering 19,200 acres at elevation 860, has a storage capacity of 670,000 acre-feet. The initial construction cost was $31,424,738, excluding the addition of recreation facilities at the completed project. (See Table 10-B for authorizing legislation.) Local cooperation. None required (Sec. 2, Flood Control Act of June 28, 1938, applies). Operations and results during fiscal year. New work: Engineering and design of public use facilities cost $65,389. Maintenance: Operation and ordinary maintenance of the dam, reservoir, powerhouse, service and recreational activities, and administration incidental thereto cost $4,816,217. Gross power generation at Allatoona Reservoir amounted to 100,773,400 kilowatt-hours during FY 1985 of which 99,187,500 kilowatt-hours were delivered to Southeastern Power Administration. Recreational attendance at Allatoona Lake during CY 1984 totaled 9,751,400 recreational user days. Condition at end of fiscal year. Construction of the existing project began in March 1944 and was completed in October 1955. Total Federal costs under existing project as of September 30, 1985 were $35,701,413 for new work and $47,087,353 for maintenance, a total of $82,788,766. 52. APALACHICOLA, CHATTAHOOCHEE, AND FLINT RIVERS, AL, GA, AND FL Location. The Apalachicola River is formed at the southwest corner of the State of Georgia by the junction of the Chattahoochee and Flint Rivers and flows south 108 miles emptying into Apalachicola Bay. Florida River enters the Apalachicola River from the east at mile 45.4 and the River Styx also enters from the east at mile 36.7 and Chipola River enters from the west at mile 28.2. (See Coast and Geodetic Survey Chart 11401.) The Chattahoochee River, 418 miles long, rises in northeast Georgia and flows southwesterly to West Point, and thence southerly to join the Flint River at the southwest corner of Georgia, forming the Apalachicola River. (See Geological Survey maps for northwest Georgia.) The Flint River, 330 miles long, rises in west central Georgia, flows generally southeasterly to Albany, and thence southwest to the southwest corner of the State, where it joins the Chattahoochee River to form the Apalachicola River. (See Geological Survey maps for southwest Georgia.) Previous project. For details see page 484 of Annual Report for 1963. Existing project. The authorized project provides for development of the Apalachicola, Chattahoochee, and Flint Rivers for navigation, flood control, hydropower, and recreation. Navigation features of the existing project consist of a continuous 9-foot by 100-foot channel in the Apalachicola River from the intersection of the Gulf Intracoastal Waterway to the confluence of the Chattahoochee and Flint Rivers, 104 miles, thence to Columbus, Georgia, on the Chattahoochee River, 164 miles, and to Bainbridge, Georgia, on the Flint River, 29 miles, and a 3-foot by 100-foot channel on the Flint River from Bainbridge to Albany, Georgia, 74 miles, thence a channel suitable for light draft vessels at moderate stage to Montezuma, Georgia, 79 miles, to be accomplished by dredging, contraction works, and construction of three locks and dams (Jim Woodruff, George W. Andrews, and Walter F. George) along the 9-foot depth channel, two multipurpose dams (West Point and Buford) on the Chattahoochee River, three multipurpose dams (Lower Auchumpkee Creek, Lazer Creek, and Spewrell Bluff) on the Flint River, and minor improvements of certain streams tributary to the Apalachicola River, including a 9-foot by 100-foot side channel, approximately 2,000 feet long, from Apalachicola River to Apalachicola River Industrial Park at Blountstown, Fla. Plane of reference is mean low water. Hydropower and flood control storage is provided at Sidney Lanier, Walter F. George, and West Point, and hydropower is provided at Jim Woodruff. The authorized but unconstructed projects of Lazer Creek, Lower Auchumpkee Creek and Spewrell Bluff would have storage for hydropower and flood control. For further details see Annual Report for 1962. (See Table 10-B for authorizing legislation.) 10-21 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Mean range of tide at the mouth of Apalachicola River is 1.6 feet. At the point where the river is formed the variation between low and high water is about 37 feet. On the Chattahoochee River, variation between average low and high water is about 20 feet, and extreme fluctuation is 65.3 feet at Eufaula. On the Flint River the extreme fluctuation of stage due to flood is 40 feet, while average variation between low and high water is about 21.5 feet. Local cooperation. Fully complied with to date. Terminal facilities. About 200 feet of public docks, in addition to private wharves, are available at Apalachicola, Florida. There are numerous constructed and natural landings along the entire system for launching small craft. For details of other terminal facilities, which are considered adequate for existing commerce, see individual project descriptions. See also Table 10-M on locks and dams and multiple-purpose development included in existing project. Operations and results during fiscal year. New work: Construction of cut off wall under Walter F. George Dam to correct seepage cost $4,105,313. Recreation facilities for various reservoirs cost $28,177. Maintenance: The contractor's dredge removed 487,000 cubic yards (net) of material from the river system at a cost of $2,235,044. Other costs incidental to the overall project amounted to $2,718,732. Operation of George W. Andrews Lock and Dam cost $335,185. Operations and maintenance locks and dams: Buford Dam cost $6,879,884; Jim Woodruff Lock and Dam, $4,154,005; Walter F. George Lock and Dam, $5,947,570; and West Point Lake, $3,958,108. Total FY 1985 cost for entire project was $30,362,018, of which $28,177 was for new work, and $26,228,528 was for operation and maintenance. Detailed information on operations and costs applicable to the individual dam projects is presented under their respective project titles elsewhere in this report. Condition at end of fiscal year. Improvement of Apalachicola River channel by dredging to provide project dimensions throughout is complete. All major construction on Lake Sidney Lanier Dam, George W. Andrews Lock and Dam, Jim Woodruff Lock and Dam, and Walter F. George Lock and Dam, is complete. West Point is essentially complete with the exception of adding recreation facilities. Channel rectification in Apalachicola River was completed December 1970. More detailed information concerning condition at the end of fiscal year for individual locks and dams and multiple-purpose developments comprising the system is presented under their respective project titles elsewhere in this report. Work remaining to complete the project consists of completion of recreational facilities at Lake Sidney Lanier, George W. Andrews Lock and Dam, Jim Woodruff Lock and Dam, and Walter F. George Lock and Dam; design and construction of Lazer Creek, Spewrell Bluff and Lower Auchumpkee Creek Dam; and completion of construction of West Point Dam. (See Tables 10-A and 10-L for fiscal year costs and summaries of overall project. 52A. BUFORD DAM, GA Location. Buford Dam is on the Chattahoochee River about 348.9 miles above its mouth, 50 miles above Atlanta and five miles northwest of Buford, Georgia. The reservoir, Lake Sidney Lanier, extends about 47 miles upstream along the Chattahoochee River, and about 21 miles up the Chestatee River, which enters the Chattahoochee River 14.5 miles above the dam. Existing project. The authorized project provides for a rolled-earth dam 1,630 feet long with crest at elevation 1,106 feet national geodetic datum, or about 192 feet above streambed elevation; three earth saddle dikes with a total length of 5,406 feet; a chute spillway with crest at elevation 1,085; a powerhouse in a deep cut with steel penstocks in tunnels, and concrete intake structure at the upstream end of the tunnels; and a flood control sluice tunnel paralleling the power tunnels. The Lake Sidney Lanier reservoir has a gross capacity of 2,554,000 acre-feet of which 637,000 acre-feet of storage is reserved for flood control storage. The power installations consist of one generating unit of 6,000 kilowatts and two units of 40,000 kilowatts each, or a total of 86,000 kilowatts. (See Table 10-B for authorizing legislation.) Local cooperation. None required. Operations and results during fiscal year. New work: Construction of recreational facilities at the completed project cost $10,398, including engineering, design, supervision, and administration. Maintenance: Operation and maintenance cost $6,879,884. Gross power generation amounted to 137,235,000 kilowatt-hours during FY 1985, of which 135,397,000 were delivered to Southeastern Power Administration. Recreational attendance at Lake Sidney Lanier during CY 1984 totaled 15,876,200 recreational user days. Condition at end of fiscal year. Construction commenced in March 1950 and was completed in June 1960. The reservoir was in useful operation for flood control in February 1956. The first power generating unit was placed on the line June 19, 1957; the second on July 26, 1957; and the third on October 10, 1957. The project is essentially complete except for adding additional recreational facilities. 52B. GEORGE W. ANDREWS LOCK AND DAM, AL AND GA Location. The project is on the Chattahoochee River about 46.5 miles above its mouth and about one mile below the town of Columbia, Alabama, near the head of Jim Woodruff Reservoir. (See Geological Survey maps for southeast Alabama). The pool extends up the navigation channel about 28 miles upstream to Walter 10-22 MOBILE, ALABAMA DISTRICT F. George Lock and Dam. Existing project. This single-purpose project provides for a concrete fixed-crest spillway 340 feet long extending into the right bank with a crest at elevation 102 feet national geodetic datum, a concrete gate spillway adjacent to the lock 280 feet long with crest at elevation 82 feet national geodetic datum, a single-lift lock with usable chamber dimensions of 82 feet by 450 feet, and a maximum lift of 25 feet. Depths are 13 feet over the lower sill and 19 feet over the upper sill at normal pool elevation. The underlying foundation is limestone. The project provides for maintenance and care. The House Committee on Public Works, by resolution adopted May 19, 1953, approved the plan as proposed by the Chief of Engineers for a high dam at Walter F. George site and a low dam at the Fort Benning site and a high dam at the upper Columbia site, construction of which was authorized by the 1946 River and Harbor Act as the initiation and partial accomplishment of the plan for full development of the Apalachicola, Chattahoochee, and Flint River system. (See Table 10-B for authorizing legislation.) Local cooperation. Local interests must operate all movable span bridges, provide suitable public terminals, and hold the United States free from damages. These conditions are being complied with. Terminal facilities. At Columbia, Alabama, there is a public wharf with concrete deck for handling general cargo and a bulk petroleum terminal with an unloading dock. Facilities are considered adequate for existing commerce. Operations and results during fiscal year. Recreational attendance at George W. Andrews Lock and Dam during CY 1984 totaled 334,800 recreational user days. Maintenance: Operation and maintenance cost included under overall Apalachicola, Chattahoochee and Flint project. Condition at end of fiscal year. Construction of the lock and dam began in March 1959 and was completed in November 1963. Work remaining consists of construction of recreational facilities. 52C. JIM WOODRUFF LOCK AND DAM, GA AND FL Location. The project is located on the Apalachicola River 107.6 miles above its mouth, about 1,000 feet below confluence of the Chattahoochee and Flint Rivers, and 1.5 miles northwest of Chattahoochee, Florida. Reservoir extends about 46.5 miles upstream along the Chattahoochee River to the vicinity of Columbia, Alabama, and about 47 miles upstream along Flint River, or 17 miles above Bainbridge, Georgia. (See Geological Survey maps for southwest Georgia.) Existing project. The authorized project provides for a concrete open-crest spillway 1,634 feet long on the right bank, with a crest at elevation 79 feet national geodetic datum; a single-lift lock with usable chamber dimensions of 82 by 450 feet, a maximum lift of 33 feet, and depth over the sills of 14 feet; a gated spillway 766 feet long with the bridge at elevation 107 feet national geodetic datum, or about 67 feet above the streambed elevation; a powerhouse with an intake section constituting a portion of the dam; an earth section 506 feet long to accommodate the switchyard and substation; and an overflow dike section 2,130 feet long on the left bank, with a crest at elevation 85. The underlying foundation is limestone. At the normal pool elevation of 77, the reservoir has a total capacity of 406,160 acrefeet. The power installation consists of three units of 10,000 kilowatts each, or a total of 30,000 kilowatts. (See Table 10-B for authorizing legislation.) Local cooperation. Required cooperation is being fulfilled. Easements for rights-of-way and spoildisposal areas were provided as required along the Apalachicola River. Adequate public terminals were constructed by local interests at Bainbridge, Georgia, on the Flint River; and at Columbia, Alabama, on the Chattahoochee River. Facilities are being planned for other localities on the project. Terminal facilities. A public wharf with concrete deck for handling general cargo, a bulk storage terminal for petroleum, a grain elevator, and private riverside facilities at Bainbridge, Georgia, on the Flint River, are considered adequate for existing commerce. Operations and results during fiscal year. New work: Miscellaneous costs at completed project amounted to $3,505. Maintenance: Operation and maintenance cost $4,154,005. Gross power generation amounted to 237,258,000 kilowatt-hours during FY 1985, of which 235,217,000 were delivered to Southeastern Power Administration. Recreational attendance at Lake Seminole during CY 1984 totaled 4,315,000 recreational user days. Condition at end of fiscal year. Construction of the lock was commenced in 1947, and completed in 1957. The lock was opened to navigation in May 1954, and the pool was raised to project level in January 1957. The first power-generating unit was placed on-the-line on February 1, the second on March 1, and the third on April 26, 1957. 52D. SPEWRELL BLUFF LAKE, GA. Location. The dam site is on the Flint River in Talbot and Upson Counties, Georgia, about nine miles west of Thomaston. The lake will extend into Meriwether, Pike, and Spalding Counties. Existing project. The authorized project provides for: a dam 2,475 feet long with maximum height of 211.0 feet, a 326-foot long gated spillway with six tainter gates 38 feet high and 45 feet wide, concrete non-overflow abutments 1,149 feet across the main channel including 268 feet for the power intake, with an earth-rock fill dike 580 feet long to high ground on the left bank, a 420-foot saddle dike on the left bank, and a power plant with three 50,000-kw units located in the left bank. The reservoir would have an area of 13,330 acres at max- 10-23 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 imum power pool elevation of 695 national geodedic datum. Usable storage of 241,510 acre-feet would be provided for power generation between elevations 665 and 695 and 195,010 acre-feet would be reserved between elevations 695 and 706.5 for flood storage. Approved estimated (1985) cost is $426,000,000, of which $302,920,000 is for construction and design, and $123,080,000 for lands, damages, and relocations. (See Table 10-B for authorizing legislation.) Local cooperation. Local interest must maintain and operate all utility and highway facilities which may be relocated or otherwise altered as part of the improvement, provide suitable public terminal facilities, and hold the United States free from damages. Operations and results during fiscal year. None. Condition at end of fiscal year. Construction has not been initiated. 52E. WALTER F. GEORGE LOCK AND DAM, AL. AND GA. Location. The project is on the Chattahoochee River about 75.2 miles above its mouth and about 1.5 miles above Fort Gaines, Georgia. (See Geological Survey maps for southwest Georgia.) Existing project. The authorized project provides for a concrete dam, gated spillway, and single-lift lock, with earth embankments at either side. The non-overflow section of the dam includes a powerhouse and an intake structure. The gated spillway is 708 feet long with a fixed crest at elevation 163 feet national geodetic datum. The two earth embankments, of almost equal lengths, have a total length of 12,128 feet, with a crest elevation at 215, and a maximum height of about 68 feet. The nonoverflow section of the concrete dam is 200 feet long, with the deck of the powerhouse section at elevation 208. The lock, with usable chamber dimensions of 82 feet by 450 feet, has a lift of 88 feet with the normal upper pool elevation at 190. Depths are 13 feet over the lower sill and 18 feet over the upper sill at normal pool elevation. The underlying foundation is limestone. Total reservoir capacity is 934,400 acre-feet, with 244,400 acre-feet reserved for power. The power installation consists of four units of 32,500 kilowatts each, ora total of 130,000 kilowatts. The project provides for maintenance, including operation and care. The approved (1984) estimate for rehabilitation work to control seepage is $15,000,000. (See Table 10-B for authorizing legislation.) Local cooperation. Local interests must maintain and operate all utility and highway facilities which may be relocated or otherwise altered as part of the improvement, provide suitable public terminal facilities, and hold the United States free from damages. Local agencies and other organizations have indicated their willingness and ability to comply. Terminal facilities. Public wharves at Eufaula and Phenix City, Alabama, and Columbus, Georgia, are considered adequate for existing commerce. Operations and results during fiscal year. New work: Continuing work on construction of cutoff wall under dam to correct seepage cost $4,105,313. Recreation facilities cost $14,274. Maintenance of the project for operation and care was $5,947,570. Gross power generation amounted to 300,601,000 during FY 1985, of which 298,666,000 were delivered to Southeastern Power Administration. Recreational attendance during CY 1984 totaled 7,130,300 recreational user days. Condition at end of fiscal year. Construction was completed in 1963. The lock was opened to navigation in June 1963. The first power generating unit was placed on-the-line in March, the second in May, the third in September, and the fourth in November 1963. 52F. WEST POINT LAKE, CHATTAHOOCHEE RIVER BASIN, GA AND AL Location. The damsite is on the Chattahoochee River 2.8 miles upstream from West Point, Georgia, 201.4 miles above the mouth of the Chattahoochee River, and 309.2 miles above the mouth of the Apalachicola River. At the full power pool elevation of 635 feet above national geodetic datum, the reservoir would lie in Troup and Heard Counties, Georgia, and in Chambers and Randolph Counties, Alabama (See Geological Survey maps of Georgia and Alabama.) Existing project. The authorized project provides for flood control, power, recreation, fish and wildlife development, and streamflow regulation for downstream navigation. The project provides for a gravitytype concrete dam 896 feet long with earth embankments at either end 1, 111 feet long on the east end and 5,243 feet long on the west end. The total length of the dam and spillway is 7,250 feet. The main dam consists of a concrete non-overflow section, 185 feet long on the west side and an earth embankment retaining wall on the east side; a gravity concrete spillway 390 feet long, including piers and abutments, with six tainter gates, each 50 feet by 41 feet. A monolith intake-powerhouse section and erection bay 321 feet long is constructed directly west and adjacent to the spillway. At the full power-pool elevation of 635 the reservoir provides a total storage of 605,000 acre-feet of which 307,000 acrefeet is usable. During the critical flood season the reservoir is operated with maximum power pool elevation at 625 feet to provide flood storage between elevations 625 and 635. The initial power installation of 73,375 kilowatts consisting of units 1, 2 and 3 were placed on operation in March and April, 1975. The ultimate installation is 108,375 killowatts. Approved estimated cost of new work (1985) is $133,900,000, of which $91,755,000 is for construction and design; $19,420,000 for lands and damages; and $22,725,000 for relocations. (See Table 10-B for authorizing legislation.) Local cooperation: None required. 10-24 MOBILE, ALABAMA DISTRICT Operations and results during fiscal year. New work: None. Maintenance: Operation and care of the project cost $3,958,108. Gross power generation amounted to 151,066,000 kilowatt-hours during FY 1985 of which 148,867,000 were delivered to Southeastern Power Administration. Recreational attendance during CY 1984 totaled 6,193,400 recreational user days. Condition at end of fiscal year. Construction of the project, which was initiated in June 1966, was essentially complete at the end of FY 1984. 53. SCHEDULING FLOOD CONTROL RESERVOIR OPERATIONS Mobile District monitors flood control operations of Alabama Power Company's Weiss, H. Neely Henry, and Logan Martin Dams on Coosa River, Alabama, and their Lewis Smith Dam on Sipsey Fork (headwaters of Black Warrior River, Alabama), for compliance with regulation plans prepared in accordance with Public Law 436, 83rd Congress, and Federal Power Commission licenses. Fiscal year cost for these activities on the Weiss, H. Neely Henry, and Logan Martin Dams are included under operation and maintenance costs for the Alabama-Coosa Rivers. Fiscal year cost for the Lewis Smith Dam is included under the overall operation and maintenance costs for the Black Warrior-Tombigbee Rivers System. General Investigations 54. SURVEYS Fiscal year cost was $2,104,370 of which $562,418 was for navigation studies, $743,798 for flood control studies, $800 for shoreline studies, $509,782 for special studies, $51,023 for special investigations, $19,431 for coordination with the Federal Energy Regulatory Commission, $44 for coastal zone management, and $217,074 for supplemental pre-authorization studies (Dalton, Georgia and Sowashee Creek, Meridian, Mississippi). Continuation of planning and engineering included $744,075 for Mobile Harbor; $1,231,464 for Oliver Lock and Dam; $114,348 for Panama City Beaches; $82,538 for Three Mile Creek; $178,099 for Village Creek; and $317,023 for Sowashee Creek, for a total of $2,667,547. Advance engineering and design for the Montgomery to Gadsden, Coosa River Channel navigation project cost $13,062. 55. COLLECTION AND STUDY OF BASIC DATA Collection and study of basic data continued during the fiscal year with the initiation of Flood Insurance studies, the cost of which was reimbursable by FEMA. In addition, Flood Plain Management services were performed at a cost of $159,737. (See Table 10-P for listings of studies completed during FY 1985.) For listing of previous reports see page 10-50 Annual Report for 1974, page 10-44 of FY 1975 Annual Report, page 10-46 of FY 1977 Annual Report, and page 10-48 of FY 1978 Annual Report, and page 10-43 of 1983 Annual Report. The National Program for inspection of non-Federal dams cost $274. 10-25 TABLE 10-A REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 COST AND FINANCIAL STATEMENT See Section Total Cost to in Text Project Funding FY82 FY83 FY84 FY85 Sept. 30, 1985 1. Apalachicola Bay New Work: FL Approp. Cost Maint: Approp. Cost 2. Aquatic Plant New Work: Control Approp. (Regular Funds) Cost (Contributed Funds) Maint: Contrib. Cost 3. Bayou Coden, AL New Work: Approp. Cost Maint: Approp. Cost (Contributed Funds) New Work: Contrib. Cost (Contributed Funds Maint: Contrib. Cost 4. Bayou La Batre, AL New Work: (Regular Funds) Approp. Cost Maint: Approp. Cost (Contributed Funds) New Work: Contrib. Cost 5. Biloxi Harbor, MS New Work: Approp. Cost Maint: Approp. Cost (Contributed Funds) New Work: Contrib. Cost Biloxi Harbor, New Work: East Harrison Approp. County Canal, MS Cost Black Warrior & New Work: Tombigbee Rivers, Approp. AL Cost Maint: Approp. Cost Major Rehab Approp. Cost Bon Secour River, New Work: AL Approp. Cost Maint: Approp. Cost (Contributed Funds) New Work: Approp: Cost 51,000 48,810 20,400 26,938 214,155 205,111 32,000 55,370 44,000 -3,884 25,000 15,357 455,000 455,263 5,000 41,048 75,000 96.785 85 77 60 41 25 22 50,000 50,000 1,300,466 550,156 84,000 81,142 265,000 126,352 10,277,901 9,534,333 26,270 39,000 16,837 4,000 753,896 52,000 50,089 704,505 195,823 14,137,473 13,862,619 17,891 220,000 224,570 501,000 514,885 3,605,000 153,586 15,962,000 16,904,377 - 2,033,461' - 2,033,461' ,000 2,904,8072 ,296 2,896,2092 ,000 522,687 ,082 491,688 - 21,225 - 21,225 - 330,7013 - 330,7013 ,000 409,533 ,778 404,409 - 100,000 - 100,000 - 50,000 - 50,000 - 311,095 - 311,095 ,000 2,690,852 ,460 2,689,074 - 10,5004 - 10,5004 - 1,215,436 s - 1,215,4365 ,000 5,689,1066 ,489 5,675,0476 - 102,600 - 102,600 ,300 61,300 ,225 35,225 ,000 110,028,9427 ,450 108,424,2207 ,000 169,659,4978 ,608 168,571,4998 - 48,127,300 895 47,258,169 - 118,615 - 118,615 20,000 175,478 22,452 171,038 - 9,700 - 9,700 24 22 165 151 61 35 35 1,797 14,087 13,558 19 10,000 16,632 10-26 6. 7. 8. MOBILE, ALABAMA DISTRICT TABLE 10-A (Continued) COST AND FINANCIAL STATEMENT See Section Total Cost to in Text Project Funding FY82 FY83 FY84 FY85 Sept. 30, 1985 9. Dauphin Island, New Work: Bay, AL Approp. Cost Maint: Approp. Cost 10. Dog and Fowl New Work: Rivers, AL Approp. (Regular Funds) Cost Maint: Approp. Cost (Contributed Funds) New Work: Contrib. Cost 11. East Pass Channel New Work: From Gulf of Approp. Mexico into Chocta- Cost whatchee Bay, FL (Regular Funds) Maint: (Contributed Funds) 12. Fly Creek, AL 13. Gulf Intracoastal Waterway between Apalachee Bay, FL and Mexican Border 14. Gulfport Harbor, MS Approp. Cost New Work: Approp. Cost New Work: Approp. Cost Maint: Approp. Cost New Work: Approp. Cost Maint: Approp. Cost New Work: Approp. Cost Maint: Approp. Cost 15. Mobile Harbor, AL New Work: Approp. Cost (Contributed Funds) New Work: Approp. Cost (Regular Funds) (Contributed Funds) 16. Panama City Harbor, FL Maint: Approp. Cost Maint: Approp. Cost New Work: Approp. Cost Maint: Approp. Cost 292,864 - 292,864 54,000 26,852 44,000 1,385 926,000 854,843 38,000 66,153 -32,000 16,930 625,000 606,764 96,000 93,672 2,037 626,000 610,614 109,000 - 106,550 1,673,000 1,663,687 1,465,000 1,126,519 230.000 843,794 850,000 235,456 6,294,000 6,422,224 2,914,000 1,400,841 1,418,000 982,529 84,000 723,834 280,000 553.,146 4,793,000 2,941,782 3,009,000 4,536,371 2,293,300 3,281,516 31.404 485,000 717,401 2,908,700 5,172,873 36,000 39,417 191,000 187,526 2,20 695,00 627,55 15,00 2,83 5,141,00 5,175,52 15,00 1,152,026 1,148,632 190,695 190,695 883,593 879,305 - 114,100 0 116,300 - 916,715 - 916,715 0 6,381,160 9 6,200,825 - 398,000 - 398,000 - 29,000 - 29,000 )0 322,621 5 308,006 - 6,480,2999 - 6,480,2999 )0 41,726,72210 !5 41,703,83610 0 919,775" - 904,775" 2,285,000 31,545,80812 2,363,210 31,501,78912 15,000 68,117,93713 19,448 68,101,48413 - 4,332,500 - 4,164,969 4,805,000 73,880,183' 4 4,819,696 73,672,05114 805,000 - 834,706 817,000 846,706 1,638,0451s - 1,638,045 s 1,323,000 979,049 -8,000 343,829 761,000 761,668 435,000 431,355 6,470,33416 6,465,995 ' 16 10-27 i REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 10-A (Continued) COST AND FINANCIAL STATEMENT See Section Total Cost to in Text Project Funding FY82 FY83 FY84 FY85 Sept. 30, 1985 (Contributed Funds) New Work: Contrib. Cost 17. Pascagoula Harbor, New Work: MS Approp. Cost (Regular Funds) Maint: Approp. Cost (Contributed Funds) Maint: Contrib. Cost 18. Pensacola Harbor, New Work: FL Approp. Cost Maint: Approp. Cost 19. Perdido Pass New Work Channel, AL Approp. Cost (Regular Funds) Maint: Approp. Cost (Contributed Funds) New Work: Contrib. Cost Maint: Contrib. Cost 20. Waterway Con- New Work: necting Tombigbee Approp. and Tennessee Rivers Cost AL, and MS Maint: Approp. Cost 27. Okatibbee Lake, New Work: MS Approp. Cost 28. Tallahala Creek Lake, Pascagoula River, MS 29. Airport Road Bridge, Frankstown, MS 30. Biloxi River at Lorraine Road, Harrison Co., MS 31. Gordon's Creek, MS 32. Murder Creek, East Brewton, AL 33. Noxubee River Relief Bridge, Shuqualak, MS 34. Pumpkinvine Creek, Emerson, GA Maint. Approp. Cost New Work: Approp. Cost New Work: Approp. Cost New Work: Approp. Cost New Work: Approp. Cost New Work: Approp. Cost New Work: Approp. Cost New Work: Approp. Cost 2,203,174 2,555,403 25,000 67,000 33,226 427,000 413,904 118,490,000 118,990,981 4,624,000 3,598,169 14,000 39,926 691,000 573,918 100,313 10,000 8,725 670 215,000 207,920 4,143,000 1,986,816 196,590 565 42,145 1,271,000 484,340 120,684,000 103,645,625 5,474,000 5,430,959 20,000 22,505 874,000 825,795 60,967 145,000 97,217 9,000 1,713 542,500 404,471 89,802 19,818 2,066,00 4,587,96 300,00 496,02 2,032,00 1,967,59 -62,00 743,60 155,107,00 88,011,30 7,456,00 7,447,34 620,00 86,83 1,008,00 1,184,14 1,80 0 3,127,00 8 3,150,43 0 770,02 !4 735,83 0 68,00 3 145,89 0 60,00 )1 51,59 0 -19,750,00 )1 43,785,51 0 10,291,00 15 11,170,45 0 -10 9 421,34 0 859,00 15 813,82 )9 59 - -5,44 - 195,66 -22,826 26,232 17,402 25,061 -31,089 108,490 27,500 10,341 -4,773 65,211 1,32 -5,00 -3,91 14,54 - 80,000 - 80,000 - 6,572,98517 - 6,572,98517 0 32,987,42018 1 32,970,63618 8 1,735,968 1 1,680,970 - 1,469,69319 - 1,469,69319 0 6,158,23820 8 6,155,94320 - 629,860 - 629,860 0 5,012,217 5 5,002,729 - 510,000 - 510,000 - 10,325 - 10,325 0 973,782,20021 5 949,068,00621 0 34,523,33122 6 34,126,66622 0 9,739,528 8 9,619,266 0 7,494,892 !7 7,395,566 - 3,945,757 3 3,922,695 0 -5,440 5 195,665 - 132,174 - 132,174 - 802,025 7 802,026 0 907,385 1 902,944 - 27,500 '3 24,884 - 85,029 - 85,029 10-28 MOBILE, ALABAMA DISTRICT TABLE 10-A (Continued) COST AND FINANCIAL STATEMENT See Section Total Cost to in Text Project Funding FY82 FY83 FY84 FY85 Sept. 30, 1985 35. Sewerline Protection New Work: 36. 37. Valley, AL Approp. Cost Sope Creek, New Work: Marietta, GA Approp. Cost Tombigbee River New Work: (East Fork), Approp. MS & AL Cost Maint: Approp. Cost 38. Tombigbee River Tributaries, MS and AL (Regular Funds) (Contributed Funds) 39. U.S. Hwy 1 Bridge, Fosters, AL 40. U.S. Hwy 43 Bridge, Chickasaw Bogue Creek, Linden, AL 41. U.S. Hwy 45 Bridge. Prentiss County, MS 42. Old Hwy 82 Bridge, Columbus, MS 43. Wolf Creek., Highway 362 Bridge, Prentiss County, MS 44. Osborne Creek, Highway 362 Bridge, Prentiss County, MS 45. Interstate 20 Bridges over Pearl River, Jackson, MS 46. Interstate 59 Bridges, Fosters, AL 50. Alabama-Coosa Rivers. AL and GA 50A. Carters Dam and Reservoir, GA 50B. Claiborne Lock and Dam. AL New Work: Approp. Cost New Work: Contrib. Cost New Work: Approp. Cost New Work: Approp. Cost New Work: Approp. Cost New Work: Approp. Cost New Work: Approp. Cost New Work: Approp. Cost New Work: Approp. Cost New Work: Approp. Cost New Work: Approp. Cost Maint: Approp. Cost New Work: Approp. Cost Maint: Approp. Cost New Work: Approp. Cost 227,000 - 71,996 800,000 1,669,031 1,495,000 1,289,170 312,000 463,701 1,400,000 2,494,136 14,000 13,165 210,00 - 18,82 -282 -265 - -60,35 - 141,7(0 - 135,0(0 - 35,11 17,343 8,021 17,059 8,195 94,000 14,564 232,000 223,163 14,657 92,158 941 23,642 185,000 185,000 17,387 17,387 1,110,000 1,1 10,000 833,383 833,383 - 134,801 - 134,801 449,000 2,227,100 452,213 2,213,996 2,000,000 16,309,225 985,330 14,925,774 - 94,700 4 63,281 )0 210,000 Z9 18,829 - 121,718 - 121,718 59 -60,000 )6 141,706 )0 135,000 7 35,117 - 126,000 - 114,753 - 250,000 - 250,000 - 250,000 - 250,000 )0 160,000 79 15,179 - 309,790,63023 84,476 309,399,65723 1,000 1,528 160,0( 15,1 1 2,651,400 5,261,664 9,898,480 9,549,915 37,053 2,010,000 1,991,853 514,522 474,340 100,000 608,670 9,775,000 11,741,500 11,224,006 101,297,96024 9,034,561 13,176,904 10,795,482 100,249,15124 -84,000 43,083 2,235,000 1,952,950 312 2,522,500 2,806,966 - 111,246,340 - 111,139,474 2,321,000 19,029,300 2,361,379 18,843,299 - 27,997,450 - 27,997,450 10-29 36 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 10-A (Continued) COST AND FINANCIAL STATEMENT See Section Total Cost to in Text Project Funding FY82 FY83 FY84 FY85 Sept. 30, 1985 50C. Robert F. Henry Lock and Dam, AL 50D. Millers Ferry Lock and Dam, AL 50E. Coosa River, Montgomery to Gadsden, AL 51. Allatoona Lake, Coosa River Basin, GA 52. Apalachicola, Chattahoochee., and Flint Rivers, AL and GA 52A. Lake Sidney Lanier, GA 52B. George W. Andrews Lock and Dam, AL and GA 52C. Jim Woodruff Lock and Dam, GA and FL 52D. Spewrell Bluff Lake GA 52E. Walter F. George Lock and Dam, AL and GA New Work: Approp. Cost Maint: Approp. Cost New Work: Approp. Cost Maint: Approp. Cost New Work: Approp. Cost New Work: Approp. Cost Maint: Approp. Cost New Work: Approp. Cost Maint: Approp. Cost Major Rehab: Approp. Cost New Work: Approp. Cost Maint: Approp. Cost New Work: Approp. Cost Maint: Approp. Cost New Work: Approp. Cost Maint: Approp. Cost New Work: Approp. Cost New Work: Approp. Cost Maint: Approp. Cost Major Rehab: Approp. Cost 2,660,000 600,000 -300,000 - 83,547,800 2,703,377 1,876,000 1,693,988 6,000 4,422 2.687,480 2,615,655 -14,600 2,516,812 972,000 836,857 3,813,480 3,070,212 917,000 1,101,493 164,544 1.891,000 1.843,208 -1,478 22,500 2,302,000 2,364,854 244,213 201,000 668,140 4,298,000 3,996,293 208,973 923,386 20,870,960 19,006,000 20,440,078 18,162,136 - 4,800,000 - 1,234,848 386,000 155,782 502,277 471,532 5,009,480 5,078,500 4,685,414 4,553,188 30 30 -3,000 19,902 3,049,000 2,707,678 30 30 -1.500 40,247 3,062,000 3,205,787 239,173 1,755,000 1,994,862 400,000 306,625 3,450,000 3,774,011 62,560 70,000 169,716 4,776,000 5,666,044 1,702,000 1,959,105 22.362,000 24,142,063 6,400,000 4,439,449 3,000 166,190 5,342,000 6,298,978 30 30 -1,000 292 3,810,000 4,057,310 1,7 1,7 12,150 83,360,007 759,000 15,079,778 76,575 15,691,788 - 63,125,300 51,806 63,083,731 2,499,000 26,600,000 2,544,735 29,434,707 - 15,035,400 20,520 14,980,655 -7,000 35,709,08525 65,389 35,701,41325 5,149,000 47,811,523 4,816,217 47,087,353 -1,500 339,094,09326 28,177 338,993,14626 26,743,000 247,795,36427 26,228,528 245,419,99127 - 11,200,000 4,105,313 9,779,610 -1,500 53,030,03828 10,398 53,037,41628 6,948,000 55,691,907 6,879,884 55,284,169 - 13,038,4272 - 13,038,42729 30 30 30 30 - 48,017,85831 3.505 47,977,95331 4,119.000 45,484,08 I 4,154,005 45,208,173 -10,948 527,00 508.51 6,825,44 7,440,47 54,691 402,094 10 3,583,000 75 3,561,801 - 4,800,000 - 1,234,848 8,483 4,620,000 4,544,659 6,400,000 4,439,449 2,158,652 2.,158,652 - 88,295,77932 14,274 88,295,77332 5,779,000 55,106,564 5,947,570 54,620,490 - 11,200,000 4,105,313 9,779,610 10-30 )0 I0 MOBILE, ALABAMA DISTRICT TABLE 10-A (Continued) COST AND FINANCIAL STATEMENT See Section Total Cost to in Text Project Funding FY82 FY83 FY84 FY85 Sept. 30, 1985 52F. West Point Lake, New Work: Chattahoochee River Approp. - 1,700,000 10,948 131,557,359 Basin, GA and AL Cost 51,922 9,513 1,784,140 - 131,499,928 Maint: Approp. 2,573,000 3,040,500 3,103,000 3,934,000 24,365,300 Cost 2,452,152 2,952,188 3,130,304 3,958,108 24,077,935 I. Includes $134,613 for previous projects and $28,500 for DPR on Two-Mile. 2. Includes $ 68,766 for previous projects. 3. Includes $5,650 for previous projects. 4. Cost for providing spoil dikes for work authorized by 1965 River and Harbor Act. 5. Includes $44,382 for previous projects of which $5,000 was contributed funds. 6. Includes $96,509 for previous projects of which $10,200 was contributed funds. 7. Includes $606,931 for previous projects and $1,046,211 for recreational facilities on completed projects. 8. Includes $50,000 for previous projects. 9. Includes $45,605 for previous projects. 10. Includes $65,137 for previous projects. 11. Includes $269,017 for previous projects. 12. Includes 2,312,297 for previous projects and $442,836 Special O and M funds. 13. Includes $6,683,104 for previous projects, $14,000 Public Work funds, and $41,242 Emergency Relief funds. 14. Includes $4,096,681 for previous projects and $494,136 Special O and M funds. 15. Includes $203,560 for previous projects, $581,959 Public Works funds, $457,467 rehabilitation of jetties under existing project and $48,001 for Grand Lagoon modification. 16. Includes $513,604 for previous projects. 17. Includes $904,442 for previous projects. 18. Includes $412,624 for previous projects, $124,565 Special O and M funds, and $829,472 Emergency Work Funds. 19. Includes $594,688 for previous projects. 20. Includes $126,649 for previous projects. 21. Includes $2,100,000 transferred to National Park Service; $210,249 GI funds expended during FY 1957 thru FY 1961. Previous project cost amounted to $197,651. 22. Includes $234,331 for previous projects. 23. Includes $3,692,483 for previous projects. 24. Includes $2,978,050 for previous projects. 25. Includes $3,339,756 for recreational facilities. 26. Includes $1,883,193 Federal funds, $1,924 contributed funds for previous projects; and $809,553 for Lazer Creek design and $301,310 for Rysco Channel. 27. Includes $2,246,233 for previous projects. 28. Includes $833,321 for recreational facilities. 29. Includes $84,014 for recreational facilities. 30. Included under maintenance for overall Apalachicola, Chattahoochee and Flint Rivers project. 31. Includes $1,515,026 for recreational facilities. 32. Includes $2,441,022 for recreational facilities. 10-31 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 10-B AUTHORIZING LEGISLATION Acts Work Authorized Documents Mar. 2, 1907 Jan. 21, 1927 Sept. 3, 1954 Sept. 3, 1954 July 3, 1958 Nov. 21, 1963' Feb. 5, 1975' Aug. 11, 1983' July 3, 1958 Oct. 23, 1962 Oct. 27, 1965 Mar. 2, 1945 June 2, 1969' Oct. 27, 1965 APALACHICOLA BAY, FL. (See Section I of Text) Channel 18 feet deep through West Pass and Link Channels, 10 feet deep across the inner bar, and 9 feet deep through Bulkhead Shoals. Modify project to provide for channel 10 feet deep from mouth of inner bar channel to Gulf via Link and West Pass Channels, and 10-foot depth in Bulkhead Shoals Channel. At Eastpoint, Fl., a channel 6 feet deep, 100 feet wide, and about 6,000 feet long, parallel to shore, with connecting channel 6 feet deep and 100 feet wide to St. George Sound, and at Apalachicola, Fl., a small-boat basin 200 feet and 9 feet deep, with a connecting channel 9 feet deep and 80 feet wide through Scipio Creek to the Apalachicola River. Modify project to provide for a channel 10 feet deep and 100 feet wide from the 10-foot depth in Apalachicola Bay across St. George Island to within 300 feet of the Gulf shore, thence increasing uniformly in width to 200 feet at shore and continuing at this width to the 10-foot deptlt in the Gulf, with two jetties extending from the dune line on St. George Island to the outer end of channel, and for abandonment of West Pass Channel upon completion of channel through St. George Island. Modify improvement of-Apalachicola Bay, Fl., authorized by River and Harbor Act of Sept. 3, 1954 to provide that the Secretary of the Army shall reimburse local interests for such approved work as they may have done based upon the reduction in the amount of material which will have to be removed to provide project dimensions at such time as Federal dredging of the channels is undertaken. A channel 6 feet deep, 100 feet wide and about I mile long, parallel to shore at Two Mile, Fl., with a 6-by 100-foot connecting channel to water of the same depth in Apalachicola Bay. A channel 6 feet deep and 100 feet wide extending from the eastern end of the existing Two Mile channel and generally paralleling the shoreline for a distance of about 9,000 feet to intersect with the Gulf Intracoastal Waterway about 1,650 feet south of Gorrie Bridge at Apalachicola, and a breakwater built to elevation 4.0 feet above mean low water along the seaward side of the existing channel parallel to the shore at Two Mile. The total length of the breakwater of about 6,150 feet, includes two 860-foot legs paralleling the existing entrance channel. Modify Eastpoint project to include breakwaters with a total length of 5,300 feet. AQUATIC PLANT CONTROL (See Section 2 of Text) Aquatic plant control for N.C., S.C., Ga., Fl., Al., Ms., and La. Research and planning costs to be borne by U.S. Provided for continued research. BAYOU CODEN, AL. (See Section 3 of Text) Channel 4 by 40 feet. Channel 8 by 60 feet to connect with Bayou La Batre channel. BAYOU LA BATRE, AL. (See Section 4 of Text) A 12- by 100-foot channel from that depth in Mississippi Sound to a point about 2,800 feet south of the highway H. Doc. 422, 59th Cong., 1st Sess. H. Doc. 106, 69th Cong., Ist Sess. H. Doc. 156, 82d Cong., Ist Sess. H. Doc. 557, 82d Cong., 2d Sess. DPR(Sec. 107) DPR(Sec. 107) DPR(Sec. 107) H. Doc. 37, 85th Cong., 1st Sess. Public Law 87-874 87th Cong. H. Doc. 251, 89th Cong., Ist Sess. H. Doc. 824, 77th Cong., 2d Sess. DPR (Sec. 107) H. Doc. 327, 88th Cong., 2d Sess. 10-32 MOBILE, ALABAMA DISTRICT TABLE 10-B (Continued) AUTHORIZING LEGISLATION Acts Work Authorized Documents July 3, 1930 June 20, 1938 Mar. 2. 1945 Mar. 2, 1945 May 17, 1950 July 14. 1960 Nov. 7, 1966 Mar. 28, 1979' August 8. 1985' July 5. 1884 Mar. 3. 1899 Sept. 19, 1890 Sept. 19, 1890 Mar. 2, 1907 Mar. 3, 1909 bridge, thence a channel 12 by 75 feet to the bridge, an overall distance of about 33,500 feet. BILOXI HARBOR, MS. (See Section 5 of Text) Channel 10 feet deep and 150 feet wide from Mississippi Sound west and north of Deer Island to deep water in Back Bay of Biloxi. Relocation of channel. Entrance channel 6 feet deep and 50 feet wide into Old Fort Bayou. Entrance channel 8 feet deep and 100 feet wide through Cranes Neck into Bayou Bernard. Maintain channel 6 feet deep and 40 feet wide from Biloxi Harbor to Ott Bayou. Continuous channel 12 feet deep from Mississippi Sound the Air Force terminal on Bayou Bernard via Back Bay and Cranes Neck. A 23-mile-long through channel 12 feet deep and 150 feet wide from the Gulf Intracoastal Waterway through: Mississippi Sound, Biloxi Bay (east of Deer Island), Back Bay. Big Lake, and via land cut to Gulfport Lake, including a 500- by 2,600-foot turning basin in the lake, thence, a channel 12 by 100 feet from the western end of Gulfport Lake for about 2 miles to a 300- by 500-foot turning basin: adoption for maintenance of a 12- by 150- foot spur channel from the main channel in Biloxi Bay, westward about I mile to a 400- by 600-foot turning basin opposite Ott Bayou, and abandonment of the existing 6- by 40-foot channel into Ott Bayou: continuation of maintenance of the 12- by 150-foot lateral channel westward about 2.2 miles from the main channel in Biloxi Bay to a point opposite Oak Street: continuation of maintenance of the channel west of Deer Island. A channel 10 feet deep: 100 feet wide and 300 feet long extending northward from the Biloxi Lateral Channel, and, into a rectangular basin approximately 300 feet by 370 feet. BILOXI HARBOR, EAST HARRISON COUNTY CANAL, MS (See Section 6 of Text) The project provides for the improvement and maintenance of the East Harrison County Canal. BLACK WARRIOR AND TOMBIGBEE RIVERS, AL. (See Section 7 of Text) Original appropriation for improving Black Warrior River. Original project for slack-water improvement authorized by Secretary of War, Apr. 19, 1887. Construction of the first locks between Tuscaloosa and Demopolis. (Maintenance of the section of Tombigbee River below lock I to its mouth (66 miles) included in the existing project.) Construction of locks and dams 12., and 3. Merging of the individual project for the Black Warrior and Warrior Rivers and the Tombigbee River below Demopolis. Construction of locks and dams 14. 15, 16. and 17. Provides for reconstruction of obsolete structures, modified in plan and location, to provide efficient and economical maintenance and operation. H. Doc. 754, 69th Cong., 2d Sess. H. Doc. 639, 75th Cong., 3d Sess. H. Doc. 258, 76th Cong., 1st Sess. H. Doc. 326, 76th Cong., 1st Sess. H. Doc. 256, 81st Cong., 1st Sess. H. Doc. 271, 86th Cong., 2d Sess. H. Doc. 513, 89th Cong., 2d Sess. DPR (Sec. 107) DPR (Sec. 107) Annual Report, 1887, pt. 2. p 1302. H. Doc. 178. 56th Cong., 2d Sess.. and Annual Report, 1901, pt. 3, p. 1858 H. Doc. 165, 57th Cong., Ist Sess., and Annual Report, 1902, p. 1293 Public Law 317 10-33 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 10-B (Continued) AUTHORIZING LEGISLATION Acts Work Authorized Documents Aug. 22, 1911 Mar. 2, 1919 Aug. 30, 1935 Aug. 30, 1935 Aug. 30, 1935 June 26, 1934 Dec. 22, 1944 Mar. 2. 1945 Mar. 2. 1945 July 14, 1960 Dec. 21, 1982 July 30, 1983 Aug. 15, 1985 May 16, 1963' Mar. 2, 1945 Sept. 3, 1954 May 19, 1969' July 3, 1930 Lift of lock 17 changed to 63 feet, and construction of locks and dams 18 and 19 eliminated from the project. Extension of slack-water improvement to Sanders Ferry on Mulberry Fork and Nichols Shoal on Locust Fork. Raising of various dams 2 feet and raising the lock walls 2 feet at lock I to provide a minimum depth of 8 feet at low water, widening the channel to 150 feet where practicable. For snagging Mobile River from the mouth of Chickasaw Creek to the junction of the Alabama and Tombigbee Rivers. Increase channel dimensions to 9 by 200 feet; construct crest gates at lock and dam 17: add flashboards at all dams: Sunflower Bend Cutoff. Construction of a lock and dam below Tuscaloosa to replace original locks and dams 10, I1 , and 12 Operation and care of locks and dams provided for with funds from War Department appropriations for rivers and harbors. Recreation facilities. Construction of a lock and dam near Demopolis to replace existing dams 4, 5, 6, and 7. Provide increased spillway capacity at dam 1. Coffeeville Lock and Dam Wildlife Refuge. Provides for a wider navigation opening at the Franklin Ferry Bridge, Jefferson County, Al. Authorized to widen, as necessary for safe passage, the navigation opening of Franklin Ferry Bridge, Jefferson County, Al. Construction and land acquisition for Oliver Lock Replacement BON SECOUR RIVER, AL. (See Section 8 of Text) A 10- by 100-foot channel from Gulf Intracoastal Waterway through Bon Secour Bay to mouth of Bon Secour River and extending up river to vicinity of Swift's Landing, thence 6 by 80 feet up river to a point 600 feet above Oak Landing, with two turning and maneuvering areas 150 feet wide and 1,100 to 1,200 feet long opposite Swift'Landing and ice loading dock. Overall length of improvement is about 4.7 miles. DAUPHIN ISLAND BAY, AL. (See Section 9 of Text) A channel 7 feet deep and 150 feet wide from Mobile Bay to an anchorage basin of same depth, about 7 acres in area, in marsh just north of Fort Gaines on Dauphin Island; a channel 4 feet deep and 40 feet wide from anchorage basin to Dauphin Island Bay; and a jetty and revetment to protect entrance channel; and (b) an anchorage basin 7 feet deep and 500 feet square at Dauphin Island Village, with an entrance channel of like depth, 100 feet wide and about 8,300 feet long, extending to 7-foot hydrographic contour in Mississippi Sound. DOG AND FOWL RIVERS, AL. (See Section 10 of Text) To provide small craft navigation on west side of Mobile Bay. EAST PASS CHANNEL FROM GULF OF MEXICO INTO CHOCi AWHATCHEE BAY, FL. (See Section II of Text) Maintenance of 6-foot channel by 100-foot channel from Choctawhatchee Bay into Gulf. H. Doc. 72, 62d Cong., 1st Sess. Annual Report, 1918, p. 876 H. Doc. 728, 71st Cong., 3d Sess. H. Doc. 56, 73d Cong., Ist Sess., and Rivers and Harbors Committee Doc.45, 73d Cong. Rivers and Harbors Committee Doc. 26, 74th Cong., Ist Sess. H. Doc. 276, 76th Cong., 1Ist Sess. H. Doc. 382, 76th Cong., Ist Sess. S. Doc. 50, 86th Cong., Ist Sess. Public Law 97-377 Public Law 98-63 The Energy and Water Development Appropriation Act 1985 (P.L. 99-88) DPR (Sec. 107) H. Doc. 333, 76th Cong., Ist Sess. H. Doc. 394, 82d Cong., 2d Sess. DPR (Sec. 107) H. Doc. 209, 70th Congress Ist Sess. 10-34 MOBILE, ALABAMA DISTRICT TABLE 10-B (Continued) AUTHORIZING LEGISLATION Acts Work Authorized Documents Oct. 24, 1951 Oct. 27, 1965 Oct. 1, 1980 May 17, 1950 Aug. 26, 1937 June 25, 1910 Aug. 30, 1935 June 25, 1910 Aug. 30, 1935 July 3, 1930 July 3, 1930 July 3, 1930 July 23, 1942 June 17, 1943 Mar. 2, 1945 May 17, 1950 Nov. 7, 1966 Maintenance of 12-foot channel from Choctawhatchee Bay into Gulf, and maintenance of 6-foot channel into Old Pass Lagoon. Construction of twin jetties. (Present piroject dimensions.) Modifications to provide a channel length of approximately 3,800 feet in lieu of 2,000 feet from the East Pass Channel into Old Pass Lagoon, with no changes in width and depth. FLY CREEK, FAIRHOPE, AL (See Section 12 of Text) A channel 6 feet deep, 80 feet wide, and about 1,650 feet long from 6-foot depth in Mobile Bay to a turning basin of same depth, 100 feet wide and 350 feet long, in Fly Creek. GULF INTRACOASTAL WATERWAY BETWEEN APALACHEE BAY, FL., AND MEXICAN BORDER (Mobile District) (See Section 13 of Text) APALACHICOLA BAY TO ST. MARKS RIVER, FL. A channel 9 feet deep and 100 feet wide at mean low water from Apalachicola Bay, Fl., via St. George Sound, Carrabelle, Crooked, and Ochlockonee Rivers and Ochlockonee and Apalachee Bays to St. Marks River, Fl. APALACHICOLA RIVER TO ST. ANDREW BAY, FL. A channel 5 feet deep at mean low water and 65 feet wide at the bottom. A channel 9 feet deep at mean low water and 100 feet wide at the bottom. CHOCTAWHATCHEE BAY TO WEST BAY, FL. A channel 9 feet deep at mean low water and 100 feet wide at the bottom. A channel 6 feet deep at mean low water, with no reference to width. CHOCTAWHATCHEE BAY TO PENSACOLA BAY, FL. A channel 9 feet deep at mean low water and 100 feet wide at the bottom. PENSACOLA BAY, FL., TO MOBILE BAY, AL. A channel 9 feet deep at mean low water and 100 feet wide at the bottom. MOBILE BAY, AL., TO NEW ORLEANS, LA. A channel 300 feet wide and 10 feet from the 10 foot contour in Mobile Bay to the 10-foot contour in Mississippi Sound. A channel 100 feet wide and 9 feet deep from Lake Pontchartrain to Mississippi Sound. APALACHEE BAY, FL., TO NEW ORLEANS, LA. A channel 12 feet deep and 125 feet wide at mean low water, except in the section between Mobile, Al., and New Orleans, La., where the width is to be 150 feet. Conditional acquisition of Gulf County Canal, Fl. and enlargement of the canal to 9 feet deep and 100 feet wide. Construction of a movable span in the Georgia, Florida & Alabama R.R. bridge crossing the Ochlockonee River. Abandonment and closure of original channel between Big Lagoon and Pensacola Bay and construction of a new channel to enter the bay north of original entrance. Authorized enlargement of Gulf County Canal to 12 by 125 feet. H. Doc. 470, 81st Cong., 2d Sess. H. Doc. 194, 88th Cong., 2d Sess. Energy and Water Development Appropriation Act, 1981 (P.L. 96-367) H. Doc. 194, 81st Cong., 1st Sess. H. Doc. 291, 75th Cong., Ist Sess. H. Doc. 670, 61st Cong., 2d Sess. Rivers and Harbors Committee Doc. 52, 72d Cong., 2d Sess. H. Doc. 259, 72d Cong., 1st Sess. H. Doc. 565, 61st Cong., 2d Sess. Rivers and Harbors Committee Doc. 42, 73d Cong., 2d Sess. H. Doc. 42, 71st Cong., Ist Sess. Rivers and Harbors Committee Doc. 4, 71st Cong., I1st Sess. H. Doc. 341, 71st Cong., 2d Sess. Public Law 675, 77th Cong., 2d Sess., and H. Doc. 96, 79th Cong., 1st Sess. H. Doc. 257, 76th Cong., 1st Sess., and Public Law 75, 78th Cong. 1st Sess. H. Doc. 442, 76th Cong., Ist Sess. H. Doc. 325, 81st Cong., Ist Sess. Public Law 89-789, 89th Cong. 2d Sess. 10-35 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 10-B (Continued) AUTHORIZING LEGISLATION Acts Work Authorized Documents Mar. 3, 1899 Mar. 2, 1907 Feb. 27, 1911 Jan. 21, 1927 July 23, 1930 June 30, 1948 July 3, 1958 Aug. 15, 1985 Aug. 26, 1937 Mar. 2, 1945 Sept. 3, 1954 Sept. 3, 1954 July 26. 1970 (SR) Dec. 15, 1970 (HR) GULFPORT HARBOR, MS. (See Section 14 of Text) A channel 19 feet deep and 300 feet wide from the anchorage basin at Ship Island to Gulfport, Ms., and an anchorage basin next to the shore end 19 feet deep and not less than 2,640 feet by 1,320 feet in area. Combined Ship Island Pass with Gulfport Harbor project. Increased depth to 26 feet and width to 300 feet across Ship Island Bar and depth to 19 feet in channel from anchorage basin at Ship Island to anchorage basin at Gulfport. Authorized relocation of channel across Ship Island Bar. Increased depth to 27 feet and width to 300 feet across Ship Island Bar, 26 feet deep and 220 feet wide through Ms. Sound and depth of 26 feet in the anchorage basin at Gulfport. Increased depth of 32 feet and width to 300 feet across Ship Island Bar, 30 feet deep and 220 feet wide through Ms. Sound, and a depth of 30 feet in the anchorage basin at Gulfport. Maintenance of the existing commerccial small-boat harbor and an approach channel 100 feet wide and 4,300 feet long, from deep water in Ms. Sound to the small-boat basin, all at a depth of 8 feet. Modify the existing Ship Channel to 36 x 300 feet in Mississippi Sound, and 38 x 400 feet across the bar, with changes in the channel alignment and the entrance to the anchorage basin for safe and unrestricted navigation. MOBILE HARBOR, AL. (See Section 15 of Text) For improvement of Threemile Creek by snagging from Mobile River to the Industrial Canal. Adoption of existing channel through Garrows Bend from Choctaw Point to Arlington pier, 27 feet deep and 150 feet wide, with 2 turning basins. Adoption of the existing channel alongside Arlington pier from the Mobile Bay Channel to turning basin at the inner end of Garrows Bend Channel, 27 feet deep and 150 feet wide. A channel 25 feet deep and generally 500 feet wide in Mobile River from the highway bridge to the mouth of Chickasaw Creek, then 25 feet deep and 250 feet wide in Chickasaw Creek to a point about 400 feet below Shell Bayou. Enlarging Mobile Bay Channel to 42 by 600 feet, Enlarging Mobile Bay Channel to 40 by 400 feet. Deepening Mobile River Channel below highway bridge to 40 feet over present widths, including existing turning basins and anchorage areas. Widening river channel opposite Magazine Point to provide a 40- by 800- by 1,400-foot turning basin. The turning basin was further modified for maintenance by SAD letter of 27 November 1973 under authority contained in ER-1130-2-307 to increase the turning basin's dimensions to 1000' x 1600'. Closure of Garrows Bend Channel by construction and operation of an earth-filled causeway across said channel (work to be done by local interests). To pr'wide a channel 40 feet deep and 400 feet wide from the main ship channel in Mobile Bay and extending northwesterly for about 5.3 miles to the shore of Mobile Bay including an anchorage and turning basin nea the shoreline, thence a land-cut 40 feet deep, 300 feet wide and about 1.9 miles long to and including a trapezoidal turning basin 40 feet deep and H. Doc. 120, 55th Cong., 3d Sess. H. Doc. 2, 60th Cong., Ist Sess. H. Doc. 692, 69th Cong., 2d Sess. H. Doc. I112, 81st Cong., Ist Sess. S. Doc. 123, 84th Cong., 2d Sess. The Energy and Water Development Approp. Act, 1985 (P.L. 99-88) Rivers and Harbors Committee Doc. 69, 74th Cong., I1st Sess. H. Doc. 739, 79th Cong., 2d Sess. H. Doc. 74, 83d Cong., 1st Sess. H. Doc. 74, 83d Cong., 2d Sess. (Under provision of Section 201 of the 1965 Flood Control Act) 10-36 MOBILE, ALABAMA DISTRICT TABLE 10-B (Continued) AUTHORIZING LEGISLATION Acts Work Authorized Documents approximately 42 acres, 40 feet deep; a barge channel 12- by 100-feet extending 6500-feet and terminating in a 300-foot by 300-foot terminal basin Aug. 15, 1985 Aug. 30. 1935 Mar. 2, 1945 June 30, 1948 Mar. 23. 1967i June 14, 1972 Mar. 4, 1913 Mar. 4. 1915 May 17. 1950 Sept. 3. 1954 July 3. 1958 July 14. 1960 July 14, 1967 Oct. 23. 1962 Deepen and widen entrance channel over the bar to 57 by 700 feet, a distance of about 7.4 miles, deepen and widen Mobile Bay Channel from mouth of bay to south of Mobile River, 55 by 550 feet a distance of about 27.0 miles, deepen and widen an additional 4.2 miles of Mobile Bay Channel to 55 by 650 feet, provide 55 foot deep anchorage area and turning basin in vicinity of Little Sand Island, and construct a 1710 acre disposal area adjacent to the Brookley Industrial Complex. PANAMA CITY HARBOR, FL. (See Section 16 of Text) Channels 27 and 29 feet deep. Abandonment of project adopted by act of June 25, 1910. Maintenance of a channel in Watson Bayou 100 feet wide and 10 feet deep from that depth in St. Andrew Bay to the highway bridge. Channels 32 and 34 feet deep. A channel 8 by 100 feet in Grand Lagoon from St. Andrew Bay to a point about 2,400 feet east of State Highway 392. Bridge with branches to serve shore facilities which terminate at the bridge. Channels 38. 40, 42 feet deep. PASCAGOULA HARBOR, MS. (See Section 17 of Text) Provides for through channel from the Gulf to mile 4 on Dog River, 25 by 300 feet through Horn Island Pass, thence 22 by 225 feet across Mississippi Sound and up Pascagoula River to the railroad bridge, thence 22 by 150 feet in Pascagoula River above bridge, and up Dog River to mile 4, all subject to financial participation by local interests. Waived requirement for financial participation by local interests. Cutoff channel, 12 by 125 feet, from State Highway 63 bridge to mile 4 on Dog River, via Robertson and Bounds Lakes. Modification to provide for channel dimensions of 35 by 325 feet through Horn Island Pass, thence 30 by 275 feet across Mississippi Sound and up Pascagoula River to the railroad bridge, and a turning basin just below the bridge. Reimbursement of local interests for work done on Dog River cutoff ($44,000). Modification to provide for maintenance of 12- by 125-foot channel to mile 6 on Dog River, and maintenance of 30- by 225-foot side channel from main ship channel in Mississippi Sound to the mouth of Bayou Casotte, thence 30 by 300 feet in Bayou Casotte to a turning basin of the same depth I mile above the mouth. Deepening the Horn Island Pass channel to 38 feet and deepening the main ship channel in Mississippi Sound, the river channel to the railroad bridge, and the turning basin all to 33 feet. Enlarging Horn Island Pass Channel to 40 by 350 feet provision of an impounding area adjacent to and east of channel 40 feet deep. 200 feet wide, and about 1.500 feet long, enlarging main channel in Mississippi Sound and river channel to railroad bridge to 38 by 350 feet, and The Energy and Water Development Approp. Act 1985 (P.L. 99-88) H. Doc. 33, 73d Cong., 1st Sess. H. Doc. 555, 76th Cong., 3d Sess. H. Doc. 559, 80th Cong., 2d Sess. DPR (Sec. 107) H. Doc. 196, 92d Cong., 2d Sess. H. Doc. 682, 62d Cong., 2d Sess. River and Harbor Committee Doc. 12, 63d Cong., 2d Sess. H. Doc. 188, 81st Cong., Ist Sess. H. Doc. 98, 86th Cong., 1st Sess. H. Doc. 98, 86th Cong., Ist Sess. Chief of Engineers Report dated Nov. 3, 1960. H. Doc. 560, 87th Cong., 2d Sess. 10-37 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 10-B (Continued) AUTHORIZING LEGISLATION Acts Work Authorized Documents July II, 1983' June 13. 1902 Aug. 30, 1935 Aug. 26, 1937 Mar. 2, 1945 Aug. 27, 1962 Oct. 27, 1965 July 24, 1946 Oct. 23, 1962 June 7, 1968 deepening turning basin in river and Bayou Casotte channels and basin to 38 feet. Modification to provide for channel dimensions 12 x 80 feet extending about 2,750 feet from deep waters in the Pascagoula River into Krebs Lake to a turning basin. thence, along the south bank of the lake a channel with dimensions of 10 x 60 feet terminating at a second turning basin, a distance of about 2,750 feet. The project was constructed by hydraulic dredging with the disposal placed in an upland diked area. PENSACOLA HARBOR, FL. (See Section 18 of Text) A channel 30 feet deep at mean low water and 500 feet wide from the Gulf of Mexico to the dock line at the east end of the city of Pensacola. and also provided that $150,000 may be used in constructing or purchasing a seagoing suction dredge. Modified the existing project for the present inner channels and the deepening of the entrance channel to 32 feet. Improvement of Bayou Chico. Modified improvement of Bayou Chico, FL. Maintenance of the entrance channel from the Gulf of Mexico to lower Pensacola Bay, a distance of about 5 miles to dimensions of 35 feet deep and 500 feet wide: maintenance of a channel along the south side of the aircraft carrier mooring basin, a distance of about 2.5 miles, to dimensions of 33 feet deep and 300 feet wide: a bay channel 33 feet deep, 300 feet wide, and about 2.1 miles long: parallel approach channels to opposite ends of the inner-harbor channel, about 1.3 and 1.4 miles in length, each 33 feet deep, 300 feet wide, and flared at the junctions with the inner-harbor channel: and deepening the existing 500-foot wide inner-harbor channel to a depth of 33 feet and lengthening it to 3,950 feet. PERDIDO PASS CHANNEL, AL. (See Section 19 of Text) A 12- by 150-foot channel stabilized by twin rubblemound jetties, from the Gulf of Mexico into Perdido Pass, thence 9 by 100 feet into Perdido Bay with a spur channel of the same dimensions into Terry Cove. WATERWAY CONNECTING TOMBIGBEE AND TENNESSEE RIVERS, AL. AND MS. (See Section 20 of Text) A waterway connecting Tennessee and Tombigbee Rivers via East Fork of Tombigbee River, Mackeys and Yellow Creeks. Plan of improvement consists of three sections: river section, 9- by 300-foot channel for 149 miles between Demopolis and Amory, Ms.: canal section, 12 by 300 feet for 46 miles from Amory to Bay Springs: divide section 12 by 300 feet (except in the 27 mile-long divide cut in which bottom width would be 280 feet) for 39 miles from Bay Springs through dividing ridge to Tennessee. Total lift of 341 feet to be accomplished by 10 locks. Total length of project is 234 miles. OKATIBBEE LAKE, MS. (See Section 27 of Text) Provides for a dam and reservoir for flood control. water supply, water quality control, and recreation. TALLAHALA CREEK LAKE, PASCAGOULA RIVER, MS. (See Section 28 of Text) Provides for a dam and reservoir for flood control, water supply, water quality control, recreation, and fish and wildlife enhancement. 10-38 DPR (Sec. 107) H. Doc. 253. 72d Cong., 1st Sess. Rivers and Harbors Committee Doc. 96, 74th Cong., 2d Sess. H. Doc. 743, 79th Cong., 2d Sess. H. Doc. 528, 87th Cong., 2d Sess. S. Doc. 94, 88th Cong., 2d Sess. H. Doc. 486, 79th Cong., 2d Sess. H. Doc. 549, 87th Cong., 2d Sess. H. Doc. 143, 90th Cong., Ist Sess. MOBILE, ALABAMA DISTRICT TABLE 10-B (Continued) AUTHORIZING LEGISLATION Acts Work Authorized Documents April 9, 19844 Aug. 30, 19824 Feb. 20, 19772. February 17, 1982; May 7, 19854 May 5, 19834 April 18, 1985 August 23, 19842 Aug. 18, 1941 July 23, 1958 July 8, 1980 August 9, 19854 Sept. 24, 19794 AIRPORT ROAD BRIDGE, FRANKSTOWN, MS. (See Section 29 of Text) The project provides for placing riprap protection on the sides and bottom of the channel at the bridge and constructing a grouted riprap weir section just downstream of the bridge. BILOXI RIVER AT LORRAINE ROAD, HARRISON COUNTY, MS (See Section 30 of Text) The project provided for the protection of the streambank in two areas of bank erosion. Construction of a stone revetment at Site No. I and placement of fill and vegetative cover at Site No. 2 GORDON'S CREEK, HATTIESBURG, MS (See Section 31 of Text) Flood control improvements along Gordon's Creek consisting of channel enlargement by excavation to a bottom width of 40 feet for a distance of 6,489 feet, and, clearing and snagging of an additional 5,831 feet for a total project length of 12,320 feet. MURDER CREEK, EAST BREWTON, AL (See Section 32 of Text) Provides for nonstructural measures for the reduction of flood damages by flood plain evacuation and flood proofing of selected buildings along the left bank of Murder Creek. NOXUBEE RIVER RELIEF BRIDGE, SHUQUALAK, MS (See Section 33 of Text) The proposed project for streambank protection at Noxubee River relief bridge would consist of grading and protecting of banks with 24 inches of riprap on 6 inches of bedding material and filter fabric. PUMPKINVINE CREEK, EMERSON, GA (See Section 34 of Text) Protection of the streambank along Pumpkinvine Creek was achieved by construction of a stone revetment along the streambank adjacent to the dike. SEWERLINE PROTECTION, VALLEY, AL (See Section 35 of Text) The project provides for the restoration of approximately 1600 linear feet of streambank. This will consist of placing 1550 cubic yards of riprap on 4445 square yards of filter fabric. SOPE CREEK, MARIETTA, GA (See Section 36 of Text) The project provides for flood control measures along Sope Creek in Cobb County, Georgia, by clearing and snagging and evacuation of 13 structures. TOMBIGBEE RIVER (EAST FORK), MS AND AL (See Section 37 of Text) Provides for alleviation of floods from the Tombigbee River by clearing, snagging, and excavation of 13 cut-off channels, and other related channel improvements. TOMBIGBEE RIVER TRIBUTARIES, MS AND AL (See Section 38 of Text) Provides for improvement of 22 tributaries of Tombigbee River. Extends project limits on Twenty Mile Creek and eliminates local cooperation for this remedial work. U.S. HIGHWAY 11 BRIDGE, FOSTERS, AL (See Section 39 of Text) The project provides for stabilization of the banks by placing riprap along a 240-foot reach of the left descending bank at the bridge. U.S. HIGHWAY 43 BRIDGE, CHICKASAW BOGUE CREEK, LINDEN, AL (See Section 40 of Text) Restoration of the channel and streambank of Chickasaw Bogue DPR (Sec. 14) DPR (Sec. 14) DPR (Sec. 205) DPR (Sec. 205) DPR (Sec. 14) DPR (Sec. 14) DPR (Sec. 14) DPR (Sec. 205) Special Report on Record in OCE. (Public Law 222, 77th Cong., I1st Sess. H. Doc. 167, 84th Cong., Ist Sess. PL (96-304) DPR (Sec. 14) DPR (Sec. 14) 10-39 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 10-B (Continued) AUTHORIZING LEGISLATION Acts Work Authorized Documents December 6, 19834 July 19, 19844 December 17, 19814 December 17, 19814 Dec. 24, 19804 August 9, 19854 Mar. 2, 1945 June 28, 1954 Creek to the alignment which existed at the time the bridge was constructed in 1951 and excavation of a sand bar located immediately upstream of the bridge and protruding from the left bank, construction of an embankment under the bridge, and a dike along the right side of the channel. WOLF CREEK, U.S. HIGHWAY 45 BRIDGE, PRENTISS COUNTY, MS (See Section 41 of Text) The project provides for stabilization of the banks under each of the bridges. The banks would be graded and protected with 24-inches of riprap on 6 inches of bedding material and filter fabric. OLD HIGHWAY 82 BRIDGES, COLUMBUS, MS (See Section 42 of Text) The project provides restoration and stabilization along the right descending bank of the bridge. The stabilization would consist of 24 inches of riprap on 6 inches of bedding material and a filter fabric. The riprap placement would begin approximately 140 feet downstream of the centerline of the bridge and extehd upstream along the right descending bank for 330 feet. WOLF CREEK, U.S. HIGHWAY 362 BRIDGE, PRENTISS COUNTY, MS (See Section 43 of Text) Provides restoration and stabilization of the banks of the creek under and around the bridges. The banks were graded to I Vertical and 2 Horizontal and protected with 18 inches of riprap placed on 6 inches of bedding material and filter fabric. Three-foot high weirs were placed just downstream of each bridge. OSBORNE CREEK, U.S. HIGHWAY 362 BRIDGE, PRENTISS COUNTY, MS (See Section 44 of Text) Provides restoration and stabilization of the banks of the creek under and around the bridges. The banks were graded to I Vertical and 2 Horizontal and protected with 18 inches of riprap placed on 6 inches of bedding material and filter fabric. Three-foot high weirs were placed just downstream of each bridge. INTERSTATE 20 BRIDGES OVER PEARL RIVER JACKSON, MS (See Section 45 of Text) Two dikes were constructed on the right bank which are designed to direct flow toward the opposite bank. They are rock-fill structures with side slopes of I vertical on 1.5 horizontal and top widths of 3 feet. They are placed on filter cloth. Erosion on the left bank was prevented by construction of a 24-inch layer of riprap on a layer of beddint material and filter cloth. INTERSTATE 59 BRIDGES, FOSTERS, AL (See Section 46 of Text) The project provides streambank protective measures at the bridges. Bank stabilization would consist of placing riprap along a 195-foot reach of the left descending bank at the bridge. MULTIPLE PURPOSE PROJECTS INCLUDING POWER ALABAMA-COOSA RIVERS, AL. AND GA. (See Section 50 of Text) Provides for full development of Alabama-Coosa Rivers and tributaries for navigation, flood control, power, recreation, and other purposes. Authorized construction of Carters Lake, GA Claiborne Lock and Dam, AL, Jones Bluff Lock and Dam, AL, and Millers Ferry Lock and Dam, AL. Suspended comprehensive plan to permit non-Federal interests to develop Coosa River by constructing series of dams. 10-40 DPR (Sec. 14) DPR (Sec. 14) DPR (Sec. 14) DPR (Sec. 14) DPR (Section 14) DPR (Sec. 14) H. Doc. 414, 77th Cong., Ist Sess. Public Law 436, 83rd Cong. MOBILE, ALABAMA DISTRICT TABLE 10-B (Continued) AUTHORIZING LEGISLATION Acts Work Authorized Documents May 25. 1982 Aug. 18. 1941 Dec. 22. 1944 Mar. 2. 1945 July 24. 1946 Dec. 22. 1944 Jan. 27. 1981' July 24. 1944 July 24. 1946 Dec. 22. 1944 Dec. 22. 1944 Dec. 30. 1965 May' 19. 1953 October 23. 1963 Designated change of name from Jones Bluff to Robert F. Henry Lock and Dam. ALLATOONA LAKE, COOSA RIVER BASIN, GA (See Section 51 of Text) Provides for dam and reservoir for flood control, regulation of stream flow for navigation, development of hydroelectric power and recreation. APALACHICOLA, CHATTAHOOCHEE, AND FLINT RIVERS, AL., GA. AND FL. (See Section 52 of Text) Development of Apalachicola. Chattahoochee, and Flint Rivers for navigation, flood control, hydropower, and recreation. Modified general plan for full development of Apalachicola, Chattahoochee, and Flint River System and authorized construction of Lake Sidney Lanier multipurpose reservoir. Authorized recreation facilities. Modified the existing project to provide for nine foot deep by 100-foot wide side channel into the Apalachicola River Industrial Park, Blountstown, Fl. LAKE SIDNEY LANIER, GA. (See Section 52A of Text) Provision of recreation facilities. GEORGE W. ANDREWS LOCK AND DAM, AL. AND GA. (See Section 52B of Text) Construction of high dam at Walter F. George site and low dam at George W. Andrews site. Provided recreation facilities. JIM WOODRUFF LOCK AND DAM, GA. AND FL. (See Section 52C of Text) Provided recreation facilities. SPEWRELL BLUFF LAKE, GA. (See Section 52D of Text) Authorized construction. WALTER F. GEORGE LOCK AND DAM, AL., AND GA. (See Section 52E of Text) Authorized construction of high dam at Walter F. George site and low dam at Columbia site. WEST POINT LAKE, CHATTAHOOCHEE RIVER BASIN, GA. AND AL. (See Section 52F of Text) Authorized construction for flood control, power recreation, fish and wildlife development, and streamflow regulation for downstream navigation. S.2034 97th Cong., 2d Sess. Public Law 228, 77th Cong., Ist Sess. H. Doc. 674, 76 Cong., 3d Sess. H. Doc. 342, 76th Cong., Ist Sess. H. Doc. 300, 80th Cong., Ist Sess. DPR (Sec. 107) H. Doc. 300, 80th Cong., Ist Sess. H. Doc. 567. 87th Cong., 2d Sess. H. Comm. on Public Works H. Doc. 570, 87th Cong., 2d Sess. I. Authorized by Chief of Engineers under Section 107 of 1960 River and Harbor Act. 2. Authorized by Chief of Engineers under Section 205 of Flood Control Act of 1948. 3. Authorized by Chief of Engineers under Section 208 of Flood Control Act of 1954. 4. Authorized by Chief of Engineers under Section 14 of Flood Control Act of 1946. 10-41 TABLE 10-C REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 OTHER AUTHORIZED NAVIGATION PROJECTS (See Section 21 of Text) Blackwater River, FL Bluff Creek, MS' Bon Secour River, AL 2 Cahaba River, AL 2 Cadet Bayou, MS Carrabelle Bar and Harbor, FL Choctawhatchee River, FL and AL Escambia-Conecuh Rivers, AL and FL Holmes Creek, FL LaGrange Bayou. FL Leaf and Chickasawhay River, MS2 Noxubee River, MS I ' Ochlockonee (Ochlockney) River, GA and FL' 2 Old Town Creek, MS' 2 Oostanaula and Coosawattee River, GA' 2 Panacea Harbor, FL Pascagoula River, MS Pass Christian Harbor, MS Port St. Joe Harbor, FL Removing Water Hyacinths St. Marks River, FL Tallapoosa River. AL2 Upper Chipola River, FL, from Marianna to its mouth' 2 Wolf and Jordan Rivers, MS 1. Abandonment recommended in H. Doc. 467, 69th Cong. 2. Uncompleted portion of project deauthorized by H. Doc. For Last Full Report See Annual Report For 1981 1963 1979 1894 1984 1979 1973 1981 1931 1972 1919 1902 1900 1887 1907 1979 1956 1976 1984 1984 1965 1893 1941 1979 Cost to September 30, 1985 Construction $41,650 1,000 118,615 45,000 87,921 481,627 171,885 208,499 8,562 289,496 23,090 47,528 5,000 3,000 32,656 122,383 15,000 59,313 1,960,862 1,710,809 43,972 36,781 29,195 Operation and Maintenance $266,368 6,883 148.586 705,118 379,413 291,694 1,092,223 36,800 78,974 42,676 14,472 92,352 179,535 139,653 2,215,089 1,100,471 84,115 63,193 481,515 96-157, 1st Session. TABLE 10-D OTHER AUTHORIZED BEACH EROSION CONTROL PROJECT (See Section 25 of Text) For Last Cost to September 30, 1985 Full Report See Annual Operation and Report For Construction Maintenance2 Harrison County, MS. shore protection' 1953 $1,133,000 I. Completed. 2. Operation and maintenance is the responsibility of local interests. 10-42 T _ MOBILE, ALABAMA DISTRICT TABLE 10-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS (See Section 48 of Text) For Last Cost to September 30, 1985 Full Report See Annual Operation and Report For Construction Maintenance Alabama River at Montgomery, AL 1965 $144,194 -2 Armuchee Creek, GA 1966 115,547 -2 Beaver Creek, Montezuma, GA 1958 149,815 -2 Black Creek, Gadsden, AL 1953 125,389 -2 Burketts Creek, Amory, MS 1984 1,366,454 -2 Clanton, AL 1964 274,024 -2 Collinsville, AL 1940 71,119 -2 Houlka Creek, Chickasaw & Clay Counties, MS 1982 238,219 -2 Jackson and East Jackson, MS 1979 7,190,200 -2 Lake Douglas, Decatur County, GA 1970 164,998 -2 Little Cove Creek, Glencoe, AL 1965 113,849 -2 Murder and Burnt. Corn Creeks, Brewton, AL 1980 190,974 -2 Prattville, Autauga Creek, AL 1946 649,280 -2 Rome, Coosa River, GA 1955 384,550 -2 Sowashee Creek, Meridian, MS 1956 142,637 -2 Sun Creek, Oktibbeha County, MS 1984 55,569 -2 Town Creek, Americus, GA 1965 340,409-2 TrimCaannee Creek, Oktibbeha County, MS 1984 145,519-2 Trussville, AL 1965 141,334 -2 West Point, Chattahoochee River, GA 1955 599,637-2 Yellow Jacket Creek, Hogansville, GA 1966 330,734-2 1. Engineering, design,dessuipgenr, vision, and administration (no con- 2. Operation and maintenance is the responsibility of local struction work has been done. Includes $17,000 for pre- interests. authorization studies. TABLE 10-G DEAUTHORIZED PROJECTS (See Section 24 of Text) Year of Last Deauthorization Date Project Type Full Report Document' Deauthorized Bayou Galere, MS Navigation 1946 H. Doc. 192, 94th Cong., 5 Aug. 1977 1st Sess., as amended. I. H. Doc. 96-157 deauthorized uncompleted portions of certain projects as shown in Table 10-E. TABLE 10-H NAVIGATION WORK UNDER SPECIAL AUTHORIZATION (See Section 22 of Text) Fiscal Year Study Authority 1985 Costs Bayou Cumbest, Jackson County, MS 107 $12,351 Carrabelle Harbor, FL 107 14,262 Dog River Channel, AL 107 8,816 East Point, FL 107 1,897 Old Pass Lagoon, FL 107 371 Shell Point, Wakulla County, FL 107 354 Tombigbee River, Columbus, MS 107 23,377 Total $61,428' 1. Excludes construction costs of $1,064,748 for East Point $18,082 contributed funds under Section 107 authority. Break-water, FL; and $199,016 for Lake Krebs, MS including 10-43 REPORT TO THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 10-I BEACH EROSION CONTROL PROJECT UNDER SPECIAL AUTHORIZATION (See Section 26 of Text) Fiscal Year Study Authority 1985 Costs Boggy Bayou Shoreline, Valparaiso, FL 103 $ 1,888 Santa Rosa Island, FL 103 9,378 Total $11,266' TABLE 10-J FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION (See Section 49 of Text) Fiscal Year Study Authority 1985 Costs Big Escambia Creek, Flomaton, AL 205 $ 1,061 Bishop Creek, Pelham, AL 205 3,404 Chattahoochee River, Vinings, GA 205 30,080 Cribbs Mill Creek, Tuscaloosa, AL 205 15,980 Eslava Creek, Mobile, AL 205 33,861 Five Mile Creek, Brookside, AL 205 38,040 Five Mile Creek, Tarrant City, AL 205 7,400 Greens Creek, Petal, MS 205 75,806 Leaf & Bowie Rivers, Hattiesburg, MS 205 48,534 Magby Creek, Columbus, MS 205 50,653 Mill Creek, Dalton, GA 205 25,323 Mixons Creek, Lamar County, MS 205 6,240 Murder Creek, Brewton, AL 205 86,182 Orange Grove Community, MS 205 25,848 Racoon Creek, Bacontown, GA 205 27,630 Sellers Creek, Mendenhall, MS 205 2,931 Silver Creek, Rome, GA 205 45,607 Sougahatchee Creek, Auburn, AL 205 7,336 Tibbee Creek, Reform, AL 205 19,588 Toulmins Spring Branch, Prichard, AL 205 26,645 Upper Gordons Creek, Hattiesburg, MS 205 25,297 Valley Creek, Birmingham, AL 205 6,400 Alligator Point, Franklin County, FL 14 8,790 County Road 25, West Point, MS 14 7,200 Leaf River, Merrill, MS 14 3,300 West Churchhill Road, West Point, MS 14 800 Boligee Canal, Boligee, MS 208 1,370 Total $631,306 10-44 MOBILE, ALABAMA DISTRICT TABLE 10-K RECONNAISSANCE AND CONDITION SURVEYS (See Section 23 of Text) Cost During Project Date of Survey Fiscal Year Apalachicola Bay, FL September, 1985 1,920 Bayou La Batre, MS September, 1985 6,021 Biloxi Harbor, MS July, 1985 700 Blackwater River, FL June, 1985 18,258 Bon Secour, AL April, 1985 8,247 Cadet Bayou, MS August, 1985 12,736 Carrabelle, FL September, 1985 2,053 Dauphin Island, AL September, 1985 12,338 Escambia and Conecuh Rivers, AL and FL July, 1985 24,121 Fly Creek, AL April, 1985 35 Fowl River, AL September, 1985 7,740 Panacea Harbor, FL September, 1985 5,286 Pascagoula River, MS July, 1985 740 Pass Christian, MS August, 1985 9,842 Pensacola Harbor, FL September, 1985 10,424 Port St. Joe Harbor, FL September, 1985 65,259 St. Marks River, FL September, 1985 3,074 Wolf and Jordan Rivers, MS August, 1985 10,791 Total $199,585 TABLE 10-L ALABAMA-COOSA RIVERS, ALA. AND GA. DEVELOPMENT PROPOSED UNDER EXISTING PROJECT (See Sections 50 and 51 of Text) Claiborne Millers Ferry Robert F. Henry Carters Allatoona Proposed Structures Lock and Dam Lock and Dam Lock and Dam Lake Dam3 Dam Miles above mouth of river 81.11 42.2' 245.41 26.82 47.84 Nearest town Claiborne, Ala. Camden, Ala. Benton, Ala. Carters, Ga. Cartersville, Ga Distance (miles) 7 10 3 2 4 Greatest lock length available for full width (feet) 600 600 600 -- Width of lock chamber (feet) 84 84 84 - - Maximum lift (feet) 30 48 47- Elevation of normal pool surface (mean sea level) 35 80 125 1072 Varies seasonally Depth over sills at low water 13 Upper 15 Upper 15 -- (feet) Lower 13 Lower 12 Character of foundation Rock Rock Rock Rock Rock Kind of spillway Gated and Gated Gated Gated Gated Fixed Crest Height of dam (feet) 95.5 99.5 94 451 190 Type of construction Concrete Concrete Concrete Rock-fill Concrete Earth Core Total reservoir capacity (acre-feet) 96,360 331,800 234,200 472,800 670,050 Power development (kw) - 75,000 68,000 500,000 74,000 Percent complete 100 100 100 100 100 Cost to date:5 $27,997,450 $63,083,731 $83,360,007 $1 11,139,474 $35,701,413 1. Above mouth of Alabama River (river miles). 2. Above mouth of Coosawattee River (river miles). 3. Reregulation dam (Carters) 25.3 (river miles). 4. Above mouth of Etowah- River (rive miles). 5. Includes cost of added recreation facilities as shown in Table 10-A. 10-45 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 10-M APALACHICOLA, CHATTAHOOCHEE, AND FLINT RIVERS, ALA., GA., AND FLA., LOCKS AND DAMS AND MULTIPLE-PURPOSE DEVELOPMENT INCLUDED IN EXISTING PROJECT (See Section 52 of Text) Existing Projects Authorized Projects Jim George W. Walter F. Buford Dam Lower Woodruff Andrews George Lake Auchumpkee Lazer Spewrell Lock Lock Lock West Point Sidney Creek Creek Bluff Miles above mouth 107.6' 46.52 75.02 201.42 348.32 233.43 255.83 263.8 Nearest town Chattahoochee, Columbia, Al. Ft. Gaines, West Point, Buford, Ga. Roberta, Ga. Thomaston, Manchester, Fl. Ga. Ga. Ga. Ga. Ga. Distance (miles) 1 1 2 2.8 5 7 8 8 Greatest lock length 450 450 450 - - - - - available for full width (feet) Width of chamber (feet) 82 82 82 - - - - - Maximum lift (feet) 33 25 88 - - - - - Elevation of normal pool 77 102 190(Summer) 635(Summer) 1070 417 543 700 surface (msl) 185(Winter) 625(Winter) Depth over sills at low 14 13 13 - - - - - water (feet) Character of foundation Limestone Limestone Limestone Rock Rock Rock Rock Rock Kind of spillway Fixed-gated Fixed-gated Gated Gated Fixed Gated Gated Gated Height of dam (feet) 67 62 114 95 192 130 142 180 Type of construction Concrete Concrete Concrete Concrete Earth Concrete Concrete Concrete and Earth and Earth and Earth and Earth and Earth and Earth Total reservoir capacity 367,300 18,180 934,400 604,500 2,554,000 548,000 342,000 486,200 (acre-feet) Power development 30,000 - 130,000 73,875 86,000 81,000 87,000 150,000 (kilowatts) Percent complete 100 100 100 100 100 - - - Year opened to navigation 1954 1962 1963 - - - - - Estimated cost: - - - - - $222,000,000 $258,000,000 $360,000,000 Cost to date:4 $47,975,749 $13,038,427 $98,075,3835 $131,499,928 $53,037,416 - - $2,158,652 1. Above the mouth of Apalachicola River (river miles). 2. Above mouth of Chattahoochee River (river miles). 3. Above mouth of Flint River (river miles). 4. Includes cost of added recreational facilities as shown in Table 10-A. 5. Includes $333,198 cost of land for wildlife refuge. 10-46 MOBILE, ALABAMA DISTRICT TABLE 10-N BLACK WARRIOR AND TOMBIGBEE RIVERS, ALA. (See Section 7 of Text) Armistead I. William John Hollis Coffeeville Demopolis Selden Bacon Oliver Holt Bankhead Lock Lock Lock Lock Lock Lock and Dam and Dam and Dam and Dam and Dam and Dam' Miles above Mobile2 116.7 213.2 261.1 338.2 347.0 365.5 Nearest town (Alabama) Coffeeville Demopolis Eutaw Tuscaloosa Tuscaloosa Oak Grove Distance (miles) 3)within city) 6 15 Lock: Greatest length available for full width (feet) 600.0 600.0 600.0 450.0 600.0 600.0 Width of chamber (feet) 110 110 110 95 110 110 Maximum lift (feet) 34 40 22 28 64 68 Depth over sills at low water (feet) 13.0 13.0 13.2 12.0 13.0 14.0 Character of foundation Rock Rock Sand, clay Hard shale Shale, Sandstone sandstone Kind of spillway Fixed-Gated Fixed Gated Fixed Gated Gated Type construction Lock Concrete Concrete Concrete Concrete Concrete Concrete Dam Concrete Concrete Earth- Concrete Concrete Concrete Concrete Year completed 1965 1962 1962 1940 1969 1985 Year opened to navigation 1960 1954 1957 1939 1966 1975 Actual cost of lock and dam $21,597,2643 $19,774,5833 $13,295,5533 $4,450,874 $28,100,0003 $49,828,6724 1. Single lift lock. 2. Navigation mileage from foot of Government Street, Mobile, Al. 3. Excludes cost of adding recreation facilities. 4. Cost to date (FY 85) for replacement of single lift lock which was essentially completed in FY 80. Excludes $1,435,636 cost of land submerged, damage to structures, and cost of spillway. Also excludes $3,824,859 cost of original double lift lock. 10-47 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 10-0 TENNESSEE-TOMBIGBEE WATERWAY, ALABAMA AND MISSISSIPPI (See Section 20 of Text) Existing Projects Gainesville Aliceville Columbus Aberdeen Lock A Lock B Lock C Lock D Lock E Bay Springs Lock Lock Lock Lock and and and and and Lock and and Dam and Dam and Dam and Dam Spillway Spillway Spillway Spillway Spillway and Dam Miles above mouth' 266 307 335 358 371 376 39 398 407 412 Nearest town Gainesville. AL Aliceville. AL Columbus. MS Aberdeen. MS Amory. MS Smithville. AL Fulton, MS Fulton. MS Belmont, MS Tupelo, MS Greatest lock length 600 600 600 600 600 600 600 600 600 600 available for full width (feet) Width of Chamber (feet) 110 Maximum lift (feet) 36 Elevation of normal 109 pool surface (msl) Depth over sills at 15 low water (feet) Character of foundation Mooreville Chalk Kind of spillway Fixed & Gated Height of dam (feet) 56 Type of construction Concrete Total reservoir capacity 45.290 (acre-feet) Percent complete Year opened to navigation Estimated Cost Cost to date 100 1978 I10 27 136 15 110 27 163 15 110 27 190 15 110 30 220 15 110 25 245 18 110 25 270 18 110 30 300 18 110 30 330 18 I10 84 (Summer)414 (Winter)409 18 Eutaw Form. Eutaw Form. Eutaw Form. Eutaw Form. Eutaw Form. Gordo Form. Eutaw Form. Gordo Form. Sandstone Sand & Clay Sand & Clay Sand Lam. Sand Sand & Clay Clay Sand Clay and Shale. Fixed & Gated Gated Gated Gated Gated Gated Gated N/ A Gated 57 Concrete & Earth 655 100 1979 57 57 46 48 53 52 44.5 103 Concrete Concrete Concrete Concrete Concrete Concrete Concrete Concrete & Earth & Earth & Earth & Earth & Earth & Earth & Earth & Earth 59.483 31.564 4,400 19.000 13,300 24,900 6,900 (Summer)180,000 (Winter) 143,000 100 1981 100 1984 100 1985 100 1985 100 1985 100 1985 100 1985 100 1985 103,214,000 151,255,000 182,650,000 128,262,000 102,685,000 96,905,000 71,375,000 98,205,000 88,173.000 147,000.000 99.331.000 131.772.000 166.885.000 107,779.000 88.955.000 89,233.000 58,458,000 88,167,000 74.463,000 126.470,000 I. Miles above Mobile. Alabama (Mile 0.00 is at Bankhead Tunnel on U.S. Highway 90) 10-48 !O O0 MOBILE, ALABAMA DISTRICT TABLE 10-P COMPLETED FLOOD INSURANCE STUDIES AND FLOOD HAZARD INFORMATION REPORTS FOR FY 1979 THRU FY 19851 (See Section 55 of Text) Date Federal Study Requesting Agency Completed Cost Flood Insurance Studies Montgomery Co., Alabama Roanoke, Alabama Wedowee, Alabama Heflin, Alabama Randolph County, Alabama Hobson City, Alabama Oxford, Alabama Weaver, Alabama Flood Insurance Studies Anniston, Alabama Calhoun County, Alabama Cave Springs, Georgia Columbus, Mississippi Lowndes County, Mississippi Aberdeen, Mississippi Amory, Mississippi Cherokee County, Georgia Floyd County, Georgia Special Flood Hazard Information Dowling Branch, Ala. Gum Creek, Ga. Choctawhatchee River, Fla. Chattahoochee River, Supplefor Buford to Whitesburg Report Oothcalooga Creek Canton Creek, Ga. . Oktasasi Creek, Ala. Cordele Creek & Malcolm Branch, Ga. Hull Branch, MS Percosin Creek & Tribs., GA (Prepared for Federal Insurance Administration, HUD) (Prepared for Federal Insurance Administration, HUD) (Prepared for Federal Insurance Administration, HUD) (Prepared for Federal Insurance Administration, HUD) (Prepared for Federal Insurance Administration, HUD) (Prepared for Federal Insurance Administration, HUD) (Prepared for Federal Insurance Administration, HUD) (Prepared for Federal Insurance Administration, HUD) FEMA FEMA FEMA FEMA FEMA FEMA FEMA FEMA FEMA City of Hartford, Ala. Housing Authority, Cordele, Ga. Board of County Commissioners Holmes County, Fla. Atlanta Reg. Planning Commission Gordon Co., GA Board of Commissioners City of Canton, Ga. Alexander City, Ala. City of Cordele, Ga. East Central Planning and Development District City of Albany, GA 1. For list of reports completed by Mobile District for FY 1965 thru FY 1974, see FY 1974 Annual Report, page 10-50; reports completed in FY 1975 see FY 1975 Annual Report, page 10-44; and for reports completed in FY 1976 and FY 1977, see FY 1977 Annual Report, page 10-46. See page 10-48 FY 1978 Annual Report for FY 1978 reports, and see page 10-43 FY 1985 Annual Report for FY 1979 reports. 10-49 Apr 80 Feb 81 Feb 81 Mar 81 Mar 81 Sep 81 Sep 8 I1 Sep 81 Apr 82 Apr 82 Jan 84 Feb 85 Feb 85 May 85 May 85 July 85 Dec 85 Jan 80 Sep 80 Jan 81 Mar 82 Jun 82 Dec 82 Jan 83 May 83 Jun 84 Nov 84 104,600 19,400 21,900 20,700 34,400 14,200 30,000 6,400 80,900 61,200 22,500 36,000 229,000 35,000 50,000 168,000 330,000 10,000 10,000 10,000 5,000 10,000 3,000 3,000 4,000 7,000 14,000 NEW ORLEANS, LA, DISTRICT* District comprises a portion of Louisiana, including drainage area of Red River south of Fulton, AR, embraced in drainage basins tributary to Mississippi River and Gulf of Mexico, except Mississippi River above mile 325.5 above Head of Passes, drainage area of Ouchita-Black River Basin, and small eastern and western portions of Louisiana tributary to Pearl River and Sabine River and Lake. It includes sections of the Gulf Intracoastal Waterway from Lake Borgne Light 29 at the mouth of Pearl River to Sabine River, and the Passes of the Mississippi River. It exercises jurisdiction over flood control work on Mississippi River from mile 325.5 AHP to Gulf of Mexico; Atchafalaya River; and in Atchafalaya Basin; and maintenance of project navigation channel of Mississippi River below mile 325.5 AHP, under supervision of President, Mississippi River Commission (MRC), and Division Engineer, Lower Mississippi Valley Division. IMPROVEMENTS Navigation 1. Gulf Intracoastal Waterway between Apalachee Bay, Fla., and Mexican Border (New Orleans Dist.) ............ 2. Leland Bowman Lock, LA (Replacement of Lock) (Formerly Vermilion Lock, LA ......... 3. Mermentau River, LA ................ 4. Mississippi River, Baton Rouge to Gulf of Mexico, LA ................. 5. Mississippi River-Gulf Outlet, LA ...... 6. Mississippi River Outlets, Venice, LA ........................... 7. Tangipahoa River, LA ................ 8. Waterway from Intracoastal Waterway to Bayou Dulac, LA (Bayous Grand Caillou and LeCarpe, LA .............. 9. Navigation work under special authorization ................. Flood Control 10. Grand Isle & vicinity, LA ............. 11. Lake Pontchartrain and vicinity, LA, (hurricane protection) ............ 12. Larose to Golden Meadow, LA (hurricane protection) ................. Page Flood Control (cont.) 11-2 11-4 11-4 11-5 11-7 11-8 11-8 11-8 11-9 11-9 11-9 11-10 13. Morgan City and vicinity, LA (hurricane protection) ................. 14. New Orleans to Venice, LA, (hurricane protection) ................. 15. Inspection of completed flood control projects ............... ....... 16. Flood control work under special authorization ........................ General Investigations 17. Active Investigations ................. Tables Table 11-A Table 11-B Table 11-C Table 11-D Table 11-E Table 11-F Cost and Financial Statement .. Authorizing Legislation ........ Gulf Intracoastal Waterway Between Apalachee Bay, FL and Mexican Border (New Orleans Dist.)-Locks .................. Other Authorized Navigation Projects ....................... Other Authorized Flood Control Projects ............... Active General Investigations .. Page 11-11 11-11 11-12 11-12 11-12 11-13 11-15 11-18 11-20 11-22 11-24 11-1 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Navigation 1. GULF INTRACOASTAL WATERWAY BETWEEN APALACHEE BAY, FL, AND MEXICAN BORDER (NEW ORLEANS DIST.) Location. Section of Gulf Intracoastal Waterway within New Orleans District extends from Lake Borgne Light 29 near mouth of Rigolets, to Sabine River, LA, and TX. Section from Lake Borgne Light 29 to Mississippi River follows Rigolets and Lake Pontchartrain to lake end of State-owned Inner Harbor Navigation Canal, thence via this canal to Mississippi River, a distance of 40.5 miles. Public Law 675, 77th Cong., modified project to provide for a land cut through marsh from Rigolets to a point on Inner Harbor Navigation Canal about 22.5 miles from Mississippi River, eliminating passage through Lake Pontchartrain and five drawbridges, a distance of 30.8 miles to Mississippi River by this route. From Inner Harbor Navigation Canal to entrance of Harvey Lock, route follows Mississippi River for 5.5 miles. Section from Mississippi River to Atchafalaya River, LA, leaves Mississippi River through Harvey Lock about 3.3 miles above Canal Street and follows Harvey Canal No. 1 and Bayou Barataria to Bayou Villars, a land cut south of Lake Salvador to Harvey Canal No. 2, Harvey Canal No. 2 to Larose, LA, and a land cut to Houma, LA, thence over a land cut south of Bayous Black and Cocodrie, thence through Bayou Cocodrie and a land cut to Bayou Black; thence through Bayous Black, Chene, and Boeuf to Atchafalaya River, about 0.5 mile south of Morgan City, LA, a total of 95.5 miles. Alternative connection with Mississippi River near Algiers, LA, about 10.3 miles below Harvey Lock, consisting of a lock and land cut about 9 miles long intersecting Intracoastal Waterway at about mile 6 is complete. An alternative route from Mississippi River follows Bayou Plaquemine passing Indian Village, LA, and continuing on through lower Grand River to and through a lock at Bayou Sorrel in East Atchafalaya Basin protection levee, thence through levee borrow pit to Berwick Bay; and thence through Berwick Bay to Morgan City, LA, a total of 56 miles. This alternative route was enlarged from vicinity of Morgan City to Indian Village, LA, and extended from Indian Village, LA, through Bayou Grosse Tete and a new land cut to and through a new terminal lock and entrance channel to Mississippi River near Port Allen, LA, a total of 65 miles. Section from Atchafalaya River to Vermilion River, LA, begins at western end of Mississippi-Atchafalaya section and follows Atchafalaya River about 2.5 miles, portions of Little Wax Bayou, Possum Bayou, cutoffs, a land cut passing through North Bend Plantation to Bayou Bartholomew, Bayou Bartholomew to Little Bay, a land cut skirting north edge of Cote Blanche Island and west edge of Weeks Island to Vermilion River, about 24 miles below Abbeville, LA, a total of about 63.6 miles. Franklin Canal, St. Mary Parish, LA, extends southwesterly from Franklin, LA, on Bayou Teche, for 5.5 miles to Bayou Portage, a section of "The Inland Waterway from Franklin to the Mermentau River, LA," and through bayou for 0.75 mile to Gulf Intracoastal Waterway, 121 miles west of Harvey Lock. Section from Vermilion River to Mermentau River, LA, begins at western end of Atchafalaya-Vermilion section and follows Vermilion River 1.3 miles, a part of Schooner Bayou Cutoff canal, and a land cut running generally northwesterly to Mermentau River at a point about 0.5 mile above its entrance into Grand Lake and about 16 miles below town of Lake Arthur, LA, a total of about 42.7 miles. Vermilion Lock was constructed about 1.75 miles west of Vermilion River to prevent ingress of saltwater from Vermilion Bay. Section from Mermentau River to Calcasieu River, LA, begins at western end of Vermilion-Mermentau section and follows Mermentau River upstream for about 1.5 miles, a land cut running west-southwesterly to Lake Misere, passing north of lake and Bayou Misere, westerly to Sweet Lake, south and west of Sweet Lake, northwesterly to Bayou Tete Bois, through Bayou Tete Bois, Black Bayou, and cutoffs to a point on Calcasieu River about 16.6 miles below city of Lake Charles, LA, a total of about 37.1 miles. Calcasieu Lock was constructed near intersection of Calcasieu River and Intracoastal Waterway, mile 238 west of Harvey Lock, Calcasieu Parish, about 16.6 miles below Lake Charles, LA. Section from Calcasieu River to Sabine River, LA and TX, begins at western end of Mermentau-Calcasieu section, and follows Calcasieu River upstream about 1.6 miles, a land cut running southwesterly 2.8 miles, thence west 22 miles to Sabine River at a point about 3 miles below Orange, TX, a total of about 27.1 miles. (Refer to MRC alluvial valley map and Rigolets, Chef Menteur, St. Bernard, New Orleans, Barataria, Baton Rouge, Grosse Tete, Chicot Lake, Foster, Napoleonville, Morgan City, Belle Isle, Bayou Sale, Jeanerette, and Derouen quadrangles; Geological Survey maps, Cutoff, Houma, Gibson, Abbeville, Forked Island, Grand Lake East, Grand Lake West, Lake Charles, Sulphur, and Orange quadrangles; and NOAA Small-Craft Charts of Intracoastal Waterway, gulf section, Galveston Bay, TX, to Waveland, MS) Previous projects. For details see page 544 of 1963 Annual Report. Existing project. Provides for a waterway, within the district, from Lake Borgne to Sabine River by the following improvements; a channel 16 feet deep and 150 feet wide, from Mississippi River to Atchafalaya River, except in vicinity of Houma, miles 50.5 to 63.5, which is to be maintained at 12 by 125 feet; a channel 16 by 150 feet through bypass route around Houma, LA, miles 50.5 to 63.5, and through alternative connection in Mississippi River below Algiers, LA, about 9 miles long, a channel 16 by 200 feet from Atchafalaya River to Sabine River; a channel 12 by 150 feet in section between Lake Borgne Light 29 and New Orleans (via land cut through marsh and Inner Harbor Navigation Canal), 33.1 miles long; an alternative route 9 feet deep and 100 feet wide between Lake Borgne Light 29 and New Orleans (via Rigolets, Lake Pontchartrain, and Inner Harbor Navigation Canal), 40.5 miles long; a 11-2 NEW ORLEANS, LA, DISTRICT channel 12 feet deep and 125 feet wide for Plaquemine- Morgan City alternative route from Mississippi- Atchafalaya section of waterway, in vicinity of Morgan City, through lower Atchafalaya River (Berwick Bay) and borrow pit of East Atchafalaya protection levee to and through Bayou Sorrel Lock which was constructed under existing project "Flood Contol, Mississippi River and Tributaries," thence through Lower Grand River to Indian Village, anrd thence by way of Bayou Grosse Tete and a new land cut to and through a new terminal lock and entrance channel to Mississippi River near Port Allen, LA, opposite lower limit of Port Baton Rouge; a channel 9 feet deep and 100 feet wide from Indian Village on Plaquemine-Morgan City alternative route through Bayou Plaquemine and Plaquemine Lock to Mississippi River at Plaquemine, LA, improvement of Franklin Canal as a connecting channel from Gulf Intracoastal Waterway (mile 121) to Franklin, LA, to afford a channel 8 feet deep and generally 60 feet wide with a width of 100 feet in its upper 300 feet; and a saltwater guard lock (Calcasieu Lock) in waterway at mile 238 west of Harvey Lock. Project also provides for: widening at bends; passing places, mooring basins; locks or guard locks; such railroad bridges over artificial cuts as are necessary; purchase of pipeline dredge; construction and operation of new drainage canals and pumping facilities to restore parish drainage systems where intercepted; construction of movable bridges at Missouri Pacific Railroad and State Highways 31 and 996 (in lieu of State Highway Bridge 31, a tunnel was constructed, and additional cost over estimated cost of bridge was borne by local interest); fixedtrestle bridges for crossing proposed landside drainage canals; lift bridges at Louisiana Highway 168, Port Allen, LA, at Texas & Pacific Railway, Port Allen, LA, and at Texas & Pacific Railway, Morley, LA; and for annual payments to Board of Commissioners of Port of New Orleans for use of a portion of Inner Harbor Navigation Canal. Length of waterway within district is 384.1 miles via northerly or Port Allen route, and 299.4 miles via southerly or Harvey Canal route. Normal range of tide, 10 inches; extreme range, 14 inches. A severe storm may cause a high tide of from 6 to 9 feet. Estimated cost for new work, exclusive of amounts expended on previous projects, is $157,833,827 Federal and $27,535,000 non-Federal, divided as follows; Algiers Lock and canal, completed June 1961, $15,895,924 Federal and $2,185,000 non-Federal; Plaquemine- Morgan City route, completed October 1963, $26,869,372 Federal and $2,250,000 non-Federal; and remainder of waterway (October 1980), $115,068,531 Federal and $23,100,000 non-Federal, including $73,700,000 Federal and $21,500,000 non-Federal for modification (authorized by Public Law 87-874), October 1962. In addition, the Coast Guard is to provide navigation aids at an estimated cost of $32,000. Construction of bulkheads and jetties at Lake Borgne and Chef Menteur, LA, is considered inactive and excluded from foregoing cost estimate. Estimated cost (1956) of this item is $440,000. Construction of a doubleleaf bascule, four-lane highway bridge provided for under this project has become unnecessary because portion of project over which bridge was to be constructed was incorporated in project "Mississippi River- Gulf Outlet" which provides for a larger bridge. Bayou Sorrel and Bayou Boeuf Locks were constructed and are being maintained and operated with "Flood Control, Mississippi River and Tributaries" funds. Therefore, construction, maintenance, and operation costs are not included in approved estimates referred to heretofore. (See Table 11-C for locks on Gulf Intracoastal Waterway in New Orleans District.) Local cooperation. Algiers Lock and Canal: All assurances required for construction were furnished. Local agency has failed to convey all fee and easement tracts with acceptable title evidence to the United States. However, authority has been received to accept the interests conveyed as best available from local agency with the understanding that the United States rely upon assurances of local cooperation should any claims against the United States occur as a result of failure of local agency to complete transfer of title. Plaquemine-Morgan City alternative route: All assurances required for construction were furnished. Title by United States has been acquired to all but 35 tracts, for which local agency failed to comply fully with curative requirements in title certificate. Authority was given to accept the tracts conveyed as best available from local interests and to rely upon assurances of local cooperation furnished by local agency should any claims against the United States occur as a result of failure of local agency to complete transfer of title. Louisiana Office of Public Works has furnished assurances for maintenance and improvement. Modification authorized by River and Harbor Act of 1962: Local interests must furnish lands, rights-of-way, and spoil-disposal areas for enlargement and future maintenance of project, make alterations to utilities; construct, maintain, and operate all bridges desired in connection with bypass channel around Houma, LA, and hold the United States free from damages. Assurances were requested in April 1963; however, none of the 11 local agencies involved has furnished assurances requested. Main objection to participation is requirement that local interests be responsible for alteration of utilities. Replacement of Vermilion Lock: The Vermilion Parish Police Jury was requested to execute an Agreement of Local Cooperation on Oct. 26, 1972, agreeing to provide without cost to the United States all lands, easements, and rights-of-way required for construction. and subsequent maintenance of the replacement lock and approach channels thereto, and hold and save the United States free from damages due to construction and maintenance of the project, including erosion of the channel beyond the rights-of-way furnished for the replacement lock and the approach channels thereto and comply with the provisions of Public Law 91-646 and Sec. 221 of Public Law 91-611. They furnished formal assurances covering all requirements of local cooperation, including Public Law 91-611 and Public 11-3 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Law 91-646, on Mar. 19, 1975. These assurances were in the process of being accepted by the United States, when the Water Resources Development Act of 1976 was enacted authorizing the 110-foot-wide lock. The assurances were executed by the Police Jury on Dec. 6, 1976, and were accepted by the District Engineer on behalf of the United States on Feb. 8, 1977. The Acting Director of Real Estate for the Secretary of the Army approved the assurances on Jul. 5, 1977. The project was renamed "Leland Bowman Lock (Replacement)" by House Resolution 4284 dated Sep. 21, 1981 (House Report 97-234). Terminal facilities. Large terminal and transfer facilities, suitable for receiving and shipping commodities by barge, are available at principal cities in Louisiana; namely, New Orleans, Baton Rouge, Harvey, Morgan City, and Lake Charles. Facilities at New Orleans are on Inner Harbor Navigation Canal. Canal and facilities were leased from Board of Commissioners, Port of New Orleans, Apr. 1, 1944, and are now operated by the United States, toll free, 24 hours per day. The Board of Commissioners has stated that it is willing to negotiate the transfer of the Inner Harbor Navigation Canal and Lock to the United States on a date earlier than that of the lease termination. The Government is considering their proposal. At Morgan City, on Atchafalaya River, there are two large and three small wharves open to all without charge. Otherwise, facilities are considered adequate for existing commerce. Operations and results during fiscal year. Maintenance by hired labor: Real estate activities, condition and operation studies, condition surveys, stream gaging, and channel patrol. Locks, bridges, and waterways were operated and maintained. Fender systems were repaired at Algiers, Calcasieu, Harvey, Port Allen, and Vermilion Locks. Work by hired labor consisted of major repairs to the Algiers Lock. Miscellaneous repairs were made to the Florida Avenue Bridge, Vermilion, Harvey, and Port Allen Locks. Dredge operations were required at Harvey, Industrial, Port Allen and Bayou Sorrel locks. The main stem channel was dredged in the Atchafalaya - Vermilion River section and at Wax Lake Crossover by two contracts. Channel maintenance included the removal of 2,784,511 cubic yards of material at a cost of $16,523,717. Construction was initiated on Oct. 15, 1981 for replacement of Leland Bowman Lock (Vermilion) and is 100 percent complete. Condition as of Sep. 30. Construction was initiated July 1929 and project, as modified, is 55 percent complete. For information on completion of segments of waterway, see 1965 Annual Report, pages 523 and 524. Work remaining to complete the project consists of enlarging waterway as provided by 1962 River and Harbor Act. Construction of bulkheads at Lake Borgne and Chef Menteur are inactive features as this work has not been necessary. President Carter, as a result of his review of water resource projects in April 1977, changed the site of the proposed new shiplock to the Industrial Canal in Orleans Parish and recommended that the existing lock be replaced and expanded at the existing site. This is a new concept and requires reinstitution of General Design planning with attendant slips in the schedule components. 2. LELAND BOWMAN LOCK, LA (REPLACEMENT OF LOCK) (FORMERLY VERMILION LOCK, LA) Location. In the Louisiana section of the Gulf Intracoastal Waterway near Abbeville, Vermilion Parish, LA, about 163 miles west of Harvey Lock. Existing project. The present Leland Bowman Lock, located in the most heavily utilized section of the Gulf Intracoastal Waterway, is the controlling structure in both width and depth. The lock is used for navigation and flood control (prevention of salt water intrusion). The tumbler-type gates are unsatisfactory for the dual purpose. (Flood Control-Navigation) operation required, since once the gates are lowered to pass flood flows, they cannot be safely raised until the differential stage across the lock is reduced to about 0.5 foot. The replacement lock also will provide a larger and more efficient outlet for floodwaters. Estimated cost for new work (October 1982) is $32,200,000 Federal and $240,000 non-Federal. The project was renamed "Leland Bowman Lock (Replacement)" by House Resolution 4284 dated Sep. 21, 1981 (House Report 97-234.) Local cooperation. Provide all lands, easements and rights-of-way for construction of the project and hold and save the United States free from damages due to construction and maintenance works. The Vermilion Parish Police Jury furnished assurances covering all requirements of local cooperation, including PL 91-611 and PL 91-646, on Mar. 19, 1975. These assurances were in the process of being accepted by the United States, when the Water Resources Development Act of 1976 was enacted authorizing the 110-foot-wide lock. Amended assurances of local cooperation were accepted on behalf of the United States by the Secretary of the Army on Jul. 5, 1977. The Vermilion Parish Police Jury on May 26, 1981 granted right of entry for construction of project. Terminal facilities. None. Operations and results during fiscal year. Construction was initiated Oct. 15, 1981. Condition as of Sep. 30. The project is 99 percent complete. 3. MERMENTAU RIVER, LA Location. Work covered by this project is 35 to 70 miles southeast of Lake Charles, LA, along lower 11-4 NEW ORLEANS, LA, DISTRICT Mermentau River below Grand Lake, mile 25, to Gulf of Mexico; Inland Waterway from Vermilion Bay to White Lake, White Lake to Grand Lake, and from Schooner Bayou to Intracoastal Waterway-Gulf section (Schooner Bayou Cutoff); North Prong of Schooner Bayou; and waterway from White Lake to Pecan Island, LA, and artificial canal, extending from 5-foot-depth contour in White Lake, almost due south for about 1.8 miles to Pecan Island. (Refer to Coast Charts Nos. 11344 and 11349, NOAA Small-Craft Chart No. 11348 on the Intracoastal Waterway, Geological Survey maps, Sweet Lake, Hog Bayou, Grand Lake West, Grand Lake East, Constance Bayou, Forked Island, Pecan Island, and Abbeville quadrangles.) Existing project. Flood control, navigation, irrigation, and salinity control in coastal marsh of lower Mermentau River Basin and channel enlargement of lower Mermentau River below Grand Lake, mile 25, to a minimum section of 3,000 square feet below mean low gulf level for discharge of flood flows; construction of a sector-gated control structure at Catfish Point, mile 24 above mouth of Mermentau River, for discharge of flood flows and control of tidal flows and saltwater intrusion in Mermentau River; channel enlargement and realinement of Inland Waterway from Vermilion Bay to White Lake, 12.04 miles, and from White Lake to Grand Lake, 6.14 miles, to a minimum section of 3,000 square feet below mean low gulf level or interflow between lakes and discharge of flood flows; construction of a sector-gated control structure in enlarged channel immediately north of abandoned Schooner Bayou Lock reservation for discharge of flood flows and control of tidal flows and saltwater intrusion; channel enlargement of North Prong of Schooner Bayou and Schooner Bayou Cutoff, 6.69 miles, to 6 by 60 feet, mean low gulf level, for navigation purposes; and maintenance of existing 5- by 40-foot, mean low gulf level, waterway from White Lake to Pecan Island, LA, 1.8 miles long, for navigation. In addition, project provides for incorporation of that section of project, "Inland Waterway from Franklin, LA, to Mermentau River," west of Vermilion Bay, a waterway that includes Schooner Bayou Lock. Project was reclassified as an "Operation and Maintenance, General" project under category, "Navigation (Locks, Dams, Reservoirs, and Canals)" by authority of Chief of Engineers, Apr. 23, 1956. Because of failure of both east and west gates, Schooner Bayou Lock was closed by a dike across east approach channel and traffic routed through new control structure. Under ordinary conditions mean range of tide on Mermentau River near mouth is 1.6 feet and near head about 3 inches. Variation of water surface near the mouth may be as much as 7 or 8 feet, due to hurricanes on the gulf, and near head from 8 to 12 feet, due to freshets. New work was completed in 1956. Estimated cost for new work (October 1982) is $6,570,000 Federal and $840,000 non-Federal, including $250,000 contributed funds. Local cooperation. Fully complied with. For details see page 1022, Annual Report FY 1948. Terminal facilities. Privately-owned and operated facilities are adequate along the Mermentau River and Bayous Nezpique and des Cannes for the principal commodities transported, which are petroleum and its products. A public wharf is located at Lake Arthur, LA, but due to insufficient use it has not been maintained and in its present condition is not usable. Sites for future expansion of these facilities are available and will be provided by non-Federal interests as required. Operations and results during fiscal year. Hired labor continued operation and maintenance of Schooner Bayou and Catfish Point Control Structures, condition and operation studies, reconnaissance surveys, channel patrol, and water quality studies. Maintenance dredging in the gulf entrance channel was completed Jan. 27, 1985, with the removal of 695,536 cubic yards of material at a cost of $1,981,824. Condition as of Sep. 30. Construction of project began April 1947 and completed July 1952. New work dredging was accomplished from April 1947 to June 1952. Catfish Point Control Structure was constructed from November 1948 to August 1951. Reservation comprises 9.7 acres. Schooner Bayou Lock and Control Structures: Schooner Bayou Lock and Dam were completed in 1913 and 1914, respectively, and the Lockmaster's house in 1917. Lock was closed to navigation May 7, 1951, and abandoned by authority of Chief of Engineers on Oct. 9, 1951. Permanent closure of lock channel and tie-in dikes was completed September 1951. Construction of control structures was accomplished from August 1949 to May 1951. Reservation comprises 6.9 acres. 4. MISSISSIPPI RIVER, BATON ROUGE TO GULF OF MEXICO, LA Location. This reach of the river flows southeasterly through southeastern portion of Louisiana. At Head of Passes, approximately 233.1 miles below Louisiana Highway Commission bridge at Baton Rouge, river branches into three main passes: Southwest Pass, South Pass, and Pass a Loutre, two of which, Southwest Pass and South Pass, are improved under existing project. Head of Passes to mouths of Southwest and South Passes are 20.1 and 13.5 miles, respectively. Mouth of Southwest Pass is 141 miles west of Mobile, AL, and 349 miles east of Galveston, TX. Mouth of South Pass is 18.5 miles northeast of mouth of Southwest Pass. (Refer to NOAA Coast Charts Nos. 11361, 11364, and 11369; MRC alluvial valley map, and Zachary, Baton Rouge, White Castle, Donaldsonville, Thibodaux, Mount Airy, Bonnet CarrY, Hahnville, New Orleans, St. Bernard, Barataria, Pointe a la Hache, Black Bay, Empire, Forts, West Delta, East Delta, and Southwest Pass quadrangles and 1980 (48th edition) folio of flood control and navigation maps, Mississippi River, Cairo, IL, to Gulf of Mexico, LA, published by the MRC.) Previous projects. For details see page 552 of Annual Report for 1963. 11-5 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Existing project. Provides for channel dimensions as follows: Between a line one-tenth mile below Louisiana Highway Commission bridge at Baton Rouge 129.3 miles to upper port limits of New Orleans, 40 by 500 feet mean low water; within limits of port of New Orleans, where that authority has jurisdiction over both banks of river, a distance of 17.8 miles, 35 by 1,500 feet, measured from a line generally 100 feet from face of left bank wharves, but not closer than 100 feet to wharves on right bank; within 35- by 1,500-foot channel in port limits of New Orleans, 40 by 500 feet; from lower limits of port of New Orleans 86.7 miles to Head of Passes, 40 by 1,000 feet; Southwest Pass, 17.5 miles' from Head of Passes to jetty channel, 40 by 800 feet; 4.1 miles in the Southwest Pass bar and jetty channel, 40 by 600 feet; South Pass from Head of Passes to outer ends of jetties, 13.5 miles, 30 by 450 feet; and 1.2 miles in the South Pass bar channel, 30 by 600 feet. Plane of reference below New Orleans is mean low gulf. Plane of reference above and through New Orleans is low water reference plane. General plan of improvement of Southwest Pass provides for constructing pass to uniform cross section with about 1,420-foot surface width by means of jetties, spur dikes, and bulkheads; for channel maintenance by dredging from Cubits Gap, mile 3.5 AHP through the gulf entrance channel, mile 21.5 BHP; for construction of small revetted openings through narrow portions of banks of pass for purpose of strengthening and nourishment of banks; for closure of minor outlets not required for maintenance of banks; for construction of sills to prevent enlargement of the Venice Jump and Cubits Gap; for repairs to sill across Pass a Loutre and bank revetment at Head of Passes; for construction of dikes with a view to reducing width of river above Head of Passes; for construction of a submerged deflecting dike above Head of Passes; and for other minor work. East jetty is about 24,950 feet long and west jetty 19,699 feet. Jetties are composed of a substructure of brush mattresses, orginally built to about elevation of mean low gulf, surmounted with a superstructure of concrete blocks and large riprap and/or stone rubble mound of core and cover stone. Spur dikes are constructed of round timber piles and/or triangular prestressed concrete piles, with riprap at the landward ends to connect the dikes to the bank line. General plan of improvement of South Pass provides for construction and maintenance of jetties and spur dikes; for channel maintenance by dredging from Head of Passes through the Gulf Entrance Channel beyond mile 13.5 BHP; maintenance of a sill across Pass a Loutre, and for seaward extension of east jetty at mouth of pass; removal of west dike and construction of spur dikes and bank revetment at Head of Passes; removal of false point at head of South Pass to bottom elevation of minus 45 feet and revetment of new bank line and construction and maintenance of east and west headland structure at Head of Passes. East jetty foundation is 12, 070 feet long; inner east jetty is 11,170 feet long; west jetty is 7,820 feet long; and inner west jetty is 4,710 feet long. Jetties are composed of a substructure of brush mattresses surmounted by a superstructure of stone and/or concrete blocks and large riprap. Plane of reference is mean low gulf. Variation of water surface is 16 inches at mouths and 10 inches at head of the passes, due to tides. Extreme range of tides at mouths of passes due to hurricanes in about 10 feet. At New Orleans extreme range of water surface is about 20 feet due to floods. At Baton Rouge extreme range is about 45 feet due to floods. Estimated cost of existing project (October 1984) is $291,700,000 Federal. In addition, Coast Guard is to provide navigation aids at an estimated cost of $1,222,800. Local cooperation. None required, except for modification of project in connection with Mississippi River- Gulf Outlet, which is reported separately. Terminal facilities. Piers, wharves, or docks serve the Port of New Orleans. Most wharves on east or left bank parallel riverbank forming nearly a continuous covered quay about 10 miles long. Public wharves controlled by Board of Commissioners, Port of New Orleans (the Dock Board), cover 62 percent of improved waterfront. These facilities include a shipside grain elevator, general cargo and cotton wharves, fruit landings, bunkering facilities, terminal warehouses, railroad terminals, marine railways, and drydocks. (For further details see Port Series No. 20, "The Port of New Orleans, LA" revised 1977.) A foreign trade zone is located in Port of New Orleans. City of Baton Rouge has a reinforced concrete dock for deep-sea vessels with mechanical-handling facility. Attached to downstream end of wharf is a floating wharf boat 231 by 40.5 feet, of 2,000-ton capacity. Facilities are served by a transfer boat and municipal terminal having a capacity of 40 cars per day. Private terminals for handling oil, grain, bauxite ore, and other products are at points on both sides of river between New Orleans and Baton Rouge. Facilities are considered adequate for existing commerce. (For further details, see "Port Facilities" included in "Flood Control and Navigation Maps of the Mississippi River, Cairo, IL, to the Gulf of Mexico, LA," published annually by the MRC, and Port Series No. 19, vol. 1, "Port St. Joe, FL, Pensacola, FL, Baton Rouge, LA, and Lake Charles, LA," revised 1979.) Operations and results during fiscal year. The Supplement II to the GDM and the environmental impact statement (EIS) for this supplement are scheduled to be completed in January 1985. Maintenance: (a) Baton Rouge to New Orleans: Two dustpan dredges removed 10,733,695 cubic yards of shoal material at a cost of $8,132,850. (b) New Orleans Harbor: One leased dredge contract removed 2,597,623 cubic yards of material at a cost of $1,019,790. (c) Cubit's Gap (mile 3 AHP) through Southwest Pass: Four hopper dredges and two cutterhead dredges removed 26,919,553 cubic yards of shoal material at a cost of $26,398,330. (d) Southwest Pass: Work was completed on one contract for pile dike repairs between miles 10.2 BHP 11-6 NEW ORLEANS, LA, DISTRICT and 20.1 BHP on the left descending bank at a total cost of $5,609,700. Hired labor units performed repairs to various pile dikes, dredging targets, and the east headland crib dike at a total cost of $500,060. (e) Wheeler Wharf at Venice: Modification and repairs to the wharf were performed by hired labor units at a cost of $345,180. Condition as of Sep. 30. The existing project is 50 percent complete. Deepening Southwest Pass to 40 feet mean low gulf, as authorized by the modification of Mar. 2, 1945, was completed in September 1963. Deepening the channel to 40 feet mean low water from Baton Rouge to New Orleans and to 40 feet mean low gulf in New Orleans Harbor, as authorized by the modifications of Oct. 23, 1962, was completed in August 1963. The initial contract for the foreshore dike between Mile 0.5 and Mile 3.0 on the right descending bank above Head of Passes is 7 percent complete. 5. MISSISSIPPI RIVER-GULF OUTLET, LA Location. In State of Louisiana and extends from existing Inner Harbor Navigation Canal at a point 7,500 feet north of existing lock and about 11,000-feet from Mississippi River, to a turning basin south of Michoud, LA, and then as a land and water cut from turning basin south of Michoud, LA, southeasterly to and along south shore of Lake Borgne and through marshes to and through Chandeleur Sound to 38-foot contour in Gulf of Mexico. (Refer to NOAA Coast Charts Nos. 11340, 11360, 11363, 11369, 11371, and 11373. Also see MRC 1980 (48th edition) folio of maps, Mississippi River-Cairo, IL, to Gulf of Mexico, LA.) Existing project. Provides for a seaway canal, 36 by 500 feet, extending 76 miles as a land and water cut from Michoud southeasterly to and along south shore of Lake Borgne, and across Chandeleur Sound to Chandeleur Island and increasing gradually to 38 by 600 feet in Gulf of Mexico, with protective jetties at entrance, a permanent retention dike through Chandeleur Sound, and a wing dike along islands as required. It also provides for an inner tidewater harbor consisting of 1,000- by 2,000-foot turning basin 36 feet deep at landward end of seaway canal, and a connecting channel 36 by 500 feet wide extending westerly along Gulf Intracoastal Waterway from turning basin to Inner Harbor Navigation Canal, including construction of a suitable highway bridge with approaches to carry Louisiana State Highway 47 (formerly 61) over channel. Plan further provides for future construction of a channel and lock in the vicinity of Meraux to furnish an additional connection between tidewater harbor and Mississippi River. Estimated cost for new work (October 1985) is $489,000,000 Federal and $225,300,000 non-Federal. This does not include modification for Mississippi River-Gulf Outlet, Michoud Canal, which is reported separately. The Federal cost excludes $45,000 for aids to navigation by U.S. Coast Guard. Local cooperation. Original assurances furnished and accepted. Local agency has furnished Supplemental Assurance covering Public Law 91-646. Rights-of-entry for entire project were furnished by local agency which is in process of conveying to the United States title to remaining tracts. Supplemental assurances reflecting the changes made necessary by enactment of the Water Resources Development Act of 1976 were requested on Jan. 12, 1977. The Board of Commissioners of the Port of New Orleans, by letter dated Sep. 18, 1978, stated that they are unable to provide the required supplemental assurances at this time. They are concerned about the possible effects of the proposed new Inner Harbor Navigation Canal Lock on this project and pending legislation concerning local assurances for the Inner Harbor Navigation Canal project. Local interests have provided right of entry for construction for the Baptiste Collette Bayou portion of this project. Terminal facilities. The only facility on the waterway is the Public Bulk Terminal of New Orleans constructed by Board of Commissioners, Port of New Orleans, on left descending bank at mile 63. Two newcontainer ship berths have begun operation at the Industrial Canal end of the seaway. Operations and results during fiscal year. New work by hired labor: Engineering environmental and economic studies were completed for the new lock and connecting channels feature. One contract for foreshore protection, south bank, Chalmette Area, station 367 to 1007 was awarded in June 1985. Maintenance dredging under three contracts in the Gulf Entrance Channel, Breton Sound and Michoud Canal include the removal of 6,072,091 cubic yards of material at a cost of $4,515,392. Condition as of Sep. 30. Construction was initiated Mach 1958 and entire project is 75 percent complete. The channel was opened to navigation Jul. 25, 1963, and completed Jan. 20, 1968. Paris Road Bridge was opened to traffic Jul. 21, and completed Nov. 14, 1967. Approximately 3 miles of first- and second-lift stone dikes have been constructed on north side of channel and approximately 8.27 miles of first-lift and 7.34 miles of second-lift stone dikes have been constructed on south side of channel in Breton Sound. Principal work required to complete project, construction of new ship lock, raising and extending dikes, is in a deferred status and construction of foreshore protection is scheduled to be initiated in June 1985. The site for the lock remained the major problem. President Carter, as a result of his review of water resource projects in April 1977, changed the site for the proposed shiplock to the Industrial Canal in Orleans Parish and recommended that, if justified, the existing lock should be replaced and expanded in place and that care should be taken to minimize dislocation of residents living adjacent to the site. These recommendations are being addressed in an Evaluation Report scheduled for completion in FY 1986. The foreshore protection is one percent complete. 11-7 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 6. MISSISSIPPI RIVER OUTLETS, VENICE, LA Location. In the coastal marsh area and in the vicinity of the Mississippi River at about miles 10 to 11 above the Head of Passes. (Refer to NOAA Coast Chart No. 1361.) Existing project. Provides for additional navigation outlets in the vicinity of Venice, LA, by enlargement of the existing channels of Baptiste Collette Bayou and Grand-Tiger Passes to 14 by 150 feet with entrance channels in open water 16 by 250 feet and jetties to the 6-foot-depth contour, if and when justified, to reduce cost of maintenance dredging. Existing project was completed at a cost of $10,008,400. Local cooperation. For details see page 11-17, Annual Report, FY 1980. Assuring Agency: Plaquemines Parish Commission Council. Basic assurances for the project have been furnished. Amended assurances covering Public Laws 91-646 and 91-611 were received on Aug. 5, 1977. Terminal facilities. In the Venice area, each operator of a construction, repair, or supply facility provides dock and transfer facilities to meet his own needs or arranges to use those of another. These facilities are considered adequate for the anticipated traffic. If new industry or supply facilities are established, they would provide any needed terminal facilities for their use. Ample areas for future expansion are available. Operations and results during fiscal year. Hired labor work consisted of reconnaisance surveys, condition and operation, stream gaging and engineering studies. One contract for maintenance dredging at Baptiste Collette Bar Channel, was completed Oct. 13, 1985, and one at Tiger Pass completed Oct. 16, 1985, included the removal of 3,102,679 cubic yards at a cost of $2,881,422. Condition as of Sep. 30. The project is 100 percent complete. 7. TANGIPAHOA RIVER, LA Location. The river originates in the State of Mississippi and flows southerly to Lake Pontchartrain, LA, about 119 miles. (Refer to NOAA Coast Chart No. 11369 and MRC alluvial valley map, Ponchatoula quadrangle.) Existing project. Improvement by removing overhanging trees, snags, and obstructions to navigation for 53.5 miles above mouth, and provide an 8- by 100- foot entrance channel from the 8-foot depth contour in the lake to the 8-foot depth in the river. Variation in water surface is from 3 to 20 feet in the upper reaches due to freshets and from 2 to 5 feet in the lower reach due to winds and tides. The cost of existing project was $61,211, Federal (including $11,500 for previously completed portion and $49,711 for preauthorization studies and modification adopted under Sec. 107, 1960 River and Harbor Act, as amended) and $29,346 contributed funds for the modification. Local cooperation. Fully complied with for completed work. Terminal facilities. None required. Operations and results during fiscal year. Hired labor forces conducted reconnaissance surveys and prepared plans and specifications. 8. WATERWAY FROM INTRACOASTAL WATERWAY TO BAYOU DULAC, LA (Bayous Grand Caillou and LeCarpe, LA) Location. Bayou LeCarpe is a tidal stream which rises about 1.5 miles southeast of Houma in Terrebonne Parish and flows southerly into Bayou Pelton, thence into Bayou Grand Caillou, which flows southwesterly into Caillou Bay, a total distance of about 40 miles. (Refer to Coast and Geodetic Survey Chart, No. 1116 and Geological Survey maps of Houma, Dulac, Bayou DuLarge, and Dog Lake quadrangles.) Existing project. As modified, provides for a 10- by 45-foot channel in Bayou LeCarpe from Gulf Intracoastal Waterway 2.6 miles to Houma navigation canal; a 5- by 40-foot channel through Bayou Pelton and Bayou Grand Caillou to Bayou Dulac, a distance of about 13.7 miles. Between miles 2.6 and 5, this project coincides with or is adjacent to 15- by 150-foot Houma navigation canal. Normal range of tide is 3 to 10 inches; from winds, 1 to 3 feet. Cost of new work, completed in August 1964, was $129,662. Local cooperation. Local interests must furnish lands, easements, and rights-of-way necessary for enlargement and subsequent maintenance of Bayou LeCarpe and of aids to navigation, and provide alterations to facilities, and hold the United States free from damage. Assurances were furnished and accepted. Local agency made available spoil areas for maintenance dredging of Bayou LeCarpe. None of these areas will be transferred to the United States. Meeting are continuing with local interests to resolve problems with their required cash contribution on total project cost. Terminal facilities. Many terminal and transfer facilities are in Houma and along waterways which flow through area between Houma and Gulf of Mexico. All facilities are privately owned and operated. Facilities are adequate for existing commerce and for reasonably prospective commerce. Ample space exists for expansion of existing facilities or for construction of new wharves and appurtenances. Operations and results during fiscal year. Hired labor consisted of real estate activities, reconnaissance surveys, and water quality studies. Condition as of Sep. 30. The 5- by 40-foot channel was constructed from January 1938 to August 1938, and modification of October 23, 1962, for enlargement of 2.54 miles of Bayou LeCarpe to 10 feet by 45 feet was initiated in May and completed August 1964. 11-8 NEW ORLEANS, LA, DISTRICT 9. NAVIGATION WORK UNDER SPECIAL AUTHORIZATION Navigation activities pursuant to Sec. 107, Public Law 86-645, as amended (preauthorization.) Preauthorization studies costs as of Sep. 30, 1985, were $456,072 for Bayou Grand Caillou. Flood Control 10. GRAND ISLE AND VICINITY, LA Location. In south Jefferson Parish, LA, along the Gulf of Mexico, about 50 miles south of New Orleans and 45 miles northwest of southwest pass (Mississippi River). Existing project. The project provides protection from waves driven by hurricanes that have a frequency of recurrence of up to once in every 50 years. The plan consists of a berm and vegetated dune extending the length of Grand Isle's gulf shore and a jetty to stabilize the western end of the island at Caminada Pass. The dune would have a 10-foot-wide crown at an elevation of 11.5 feet mean sea level, 1 on 5 side slopes, and protective vegetation. The sandfill berm would slope from an elevation of 8.5 feet mean sea level at the toe of the dune 180 feet gulfward to an elevation of 3 feet mean sea level and, from this point, would assume its natural slope to the offshore bottom. The jetty provided by the plan has a top width of 6 feet at an elevation of 4 feet mean sea level, 1 on 2 side slopes, and extends approximately 2,600 feet along the western end of the island at Caminada Pass. Estimated cost of project (October 1985) is $9,090,000 Federal and $7,761,000 non-Federal, including $2,110,000 contributed funds. Local cooperation. Local interests have the responsibility of providing rights-of-way, 30 percent of hurricane protection costs, 75 percent of beach erosion costs, and operation and maintenance of the completed work. The Louisiana Legislature, by Act 833 of 1982, authorized the Office of Public Works of the Louisiana Department of Transportation and Development to provide the non-Federal assurances for the Grand Isle Hurricane Protection and Beach erosion project. On Jan. 11, 1983, the Louisiana State Government authorized the Office of Public Works to execute the required assurance's as a co-sponsor with the Town of Grand Isle. The required assurances were executed on Mar. 16, 1983, the construction rights-of-way were provided on May 4, 1983, and local interest provided a cash contribution of $2,110,000 on Jun. 1, 1983. Maintenance of the project is the responsibility of the local assurer. The local assurer will receive Federal aid for repairing erosion and other damage to the project for a period of 15 years. The average annual Federal maintenance cost identified in the Act of Assurances is $44,000; however, this is not a fixed amount. Periodic nourishment to repair erosion will not necessarily be conducted every year, but as needed, with an estimated frequency of one in eight years on the average. It is estimated that the Federal share of the maintenance cost will be 25 percent for the 15-year period. Operations and results during the fiscal year. The dredging contract for beach erosion was completed Aug. 26, 1985, with the placing of 2,970,000 cubic yards of hydraulic fill at a total cost of $8,640,000. Condition as of Sep. 30. The project is 100 percent complete. 11. LAKE PONTCHARTRAIN AND VICINITY, LA (HURRICANE PROTECTION) Location. In southeastern Louisiana, vicinity of New Orleans, in St. Charles, Jefferson, Orleans, St. Bernard, and St. Tammany Parishes, comprising lower land and water area between Mississippi River alluvial ridge and the Pleistocene escarpment to north and west. The dominant topographic feature is Lake Pontchartrain, a shallow landlocked tidal basin, about 640 square miles in area and averaging 12 feet deep, connecting with lesser Lake Maurepas to the west and through Lake Borgne and Mississippi Sound to the gulf to the east. The lake drains about 4,700 square miles of tributary area. (Refer to Geological Survey quadrangles Yscloskey and Malheureaux Point, Drum Bay, Door Point, Lake Eugenie, Oak Mound Bayou, Mitchell Keys, Lake Eloi, and Morgan Harbor; Engineer quadrangles Slidell, Covington, Ponchatoula, Springfield, Denham Springs, Donaldsonville, Mt. Airy, Bonnet Carr6, Spanish Fort, Chef Menteur, Rigolets, St. Bernard, New Orleans, and Hahnville; and Coast and Geodetic Survey Charts No. 1115 and 1116. Existing project. Provides protection to the greater New Orleans area and other communities bordering Lake Pontchartrain from the effects of hurricanegenerated floods. The project is comprised of two major features: The Chalmette Area Plan and the High Level Plan. The Chalmette Area Plan consists of a levee and floodwall system around the Chalmette area and along the Mississippi River Gulf Outlet, with connections to the Mississippi River levees. The High Level Plan will provide for heightening and strengthening the existing hurricane protection levee systems in Orleans Parish and the east bank of Jefferson Parish, repairing and rehabilitating the Mandeville Seawall in St. Tammany Parish; building a new mainline hurricane levee on the east bank of the St. Charles Parish just north of US Highway 61 (Airline Highway); raising and strengthening the existing levee which extends along the Jefferson-St. Charles Parish boundary between Lake Pontchartrain and Airline Highway; and deferring construction of the proposed Seabrook lock until its feasibility as a feature of the Mississippi River Gulf Outlet navigation project can be determined. Areas which will be enclosed by the levee and floodwall construction will be provided protection against tidal surge resulting from the Standard Project Hurricane (SPH). The estimated project cost for work (October 11-9 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 1985) is $483,000,000 Federal and $207,000,000 non- Federal. Local cooperation. Provide all rights-of-way; bear 30 percent of the first cost, consisting of fair market value of providing all lands, easements, and rights-ofway, including borrow and spoil disposal areas for construction, accomplish alteration and relocation of roads, railroads, pipelines, cables, wharves, drainage structures, and other facilities; maintain and operate all works after completion; and hold and save the United States free from damages. See H. Doc. No. 231, 89th Cong., 1st sess. for more detailed requirements of local cooperation. Assuring Agency: The Orleans Levee District, Lake Borgne Basin Levee District, St. Bernard Parish Police Jury, Louisiana Office of Public Works, and Pontchartrain Levee District. The State of Louisiana formed the Jefferson Levee District and assigned to it the parish levees, previously the responsibility of the Pontchartrain Levee District. Basic assurances were received from the following: Orleans Levee District for the entire barrier plan and that portion of the Chalmette area plan in Orleans Parish; Pontchartrain Levee District for the barrier plan; Lake Borgne Levee District and St. Bernard Parish Police Jury for the Chalmette area plan in St. Bernard Parish. Supplemental assurances covering Public Law 91-646 have been received from the Orleans Levee District and the Pontchartrain Levee District. Lake Borgne Basin Levee District and St. Bernard Parish Police Jury have executed the supplemental assurance. The St. Tammany Parish portion of the project has been placed in an inactive status since the local sponsors have not provided acceptable assurances. Operations and results during fiscal year. Preparation of design memorandums and plans and specifications continued by hired labor. Citrus Lakefront GDM was submitted to higher authority in July 1984. Preparation of three design memorandums is underway. All are scheduled for completion in FY 85. A Draft Reevaluation Report (including Draft Environmental Impact Statement) recommending the tentatively selected high level plan (lieu of Barrier Plan) was submitted by New Orleans District to the Lower Mississippi Valley Division in December 1983. The final Reevaluation Report was submitted to LMVD on Aug. 8, 1984. A Record of Decision is expected to be signed in the 2nd Quarter of FY 85 by the Office, Chief of Engineers. Condition as of Sep. 30. Construction started May 1967 and is 68 percent complete. Contract work continued on six contracts. Construction was initiated on four more contracts: Bayou Bienvenue to Bayou Dupre levee closures; Chalmette area, second enlargement; Inner Harbor Canal, east and west levee and Citrus Back levee to Paris road, capping floodwall; Chalmette extension, first enlargement. 12. LAROSE TO GOLDEN MEADOW, LA (HURRICANE PROTECTION) Location. In coastal section of Louisiana, along Bayou Lafourche, and includes lands on both banks of the bayou from Larose to 2 miles south of Golden Meadow. (Refer to Geological survey quadrangles Cut-off, Lake Felicity, Bay Dosgris, Golden Meadow Farms, Bay Tambour, Mink Bayou, Caminada Pass, Leeville, Belle Pass, Pelican Pass, and Calumet Island; Engineer quadrangles New Orleans, Hahnville, Point-a-la-Hache, Barataria, and Fort Livingston; and Coast and Geodetic Survey Charts Nos. 1115 and 1116. Existing project. Provides a loop levee about 40 miles long along both banks of Bayou Lafourche from Larose to South Golden Meadow; enlargement of 3 miles of existing levee at Golden Meadow; floodgates for navigation and hurricane protection in Bayou Lafourche at upper and lower bayou crossings; about 8 miles of low interior levees to regulate intercepted drainage and seven multibarreled culverts controlled by flapgates. Estimated cost for new work (October 1985) is $64,000,000 Federal and $27,400,000 non-Federal. Local cooperation. Provide without cost to the United States all lands, easements, and rights-of-way, including borrow areas and spoil disposal areas, and accomplish alterations to roads, pipelines, cables, wharves, oil wells, and any other facilities necessary for the construction of the project; all at an estimated cost of $13,540,000; bear 30 percent of the total project cost, a sum presently estimated at $27,400,000 consisting of the items listed above, and a cash contribution presently estimated at $13,860,000 or equivalent work specifically undertaken as an integral part of the project after authorization and in accordance with construction schedules as required by the Chief of Engineers; hold and save the United States free from damages due to the construction works; maintain and operate all the works after completion in accordance with regulations prescribed by the Secretary of the Army; and prevent any encroachment on ponding areas unless substitute storage capacity or equivalent pumping capacity is provided promptly without cost to the United States; comply with the provisions of the Uniform Relocations Assistance and Real Property Acquisition Policies Act of 1970 (Public Law 91-646) and with the provisions of Section 221 of the Flood Control Act of 1970 (Public Law 91-611) in acquiring real property. The Board of Commissioners of the South Louisiana Tidal Water Control Levee District executed the required Agreement of Local Cooperation on Nov. 13, 1972, which was executed by the United States on Jul. 10, 1973 and approved on behalf of the Secretary of the Army on Aug. 29, 1973. Section 38, Paragraph 1051 et seq., Louisiana Revised Statutes created the South Lafourche Levee District. The South Lafourche Levee District assumed the rights and obligations of the South Louisiana Tidal Water Control Levee District with respect to this project. Local interests have requested and received funds from the State of Louisiana 11-10 NEW ORLEANS, LA, DISTRICT for right-of-way acquisition and relocations required to support construction work. Operations and results during fiscal year. Work continued on design memorandums and plans and specifications by hired labor forces. Two contracts were awarded during the year; Secton E-South (first lift) on Dec. 17, 1984, and the Larose Floodwall on Sept. 25, 1985. Condition as of Sep. 30. Construction commenced in February 1975 and is 49 percent complete. 13. MORGAN CITY AND VICINITY, LA (HURRICANE PROTECTION) Location. In south-central Louisiana, Morgan City proper, and the adjacent areas. It includes the land south of Grand Lake, Six Mile Lake, and Lake Palourde extending from Morgan City westward to Charenton drainage and navigation, canal. Lower Atchafalaya River and Wax Lake Outlet, the principal outlets for Atchafalaya Basin Floodway, traverse the area. Gulf Intracoastal Waterway crosses the area in an east-west direction. Numerous bayous and artificial canals excavated for drainage purposes or for access to oil developments exist throughout the area. (See Engineer quadrangles Bayou Sale, Jeanerette, Foster, Belle Isle, Point Au Fer, Morgan City, and Lake Decade; and Coast and Geodetic Survey Chart 1116.) Existing project. Morgan City: Construction of about 5.6 miles of new levees along shore of Lake Palourde and west bank of Bayou Ramos and about 0.5 mile of new levee from Southern Pacific railroad embankment near Wyandotte to tie in with Bayou Boeuf lock levee, and construction of three gravity drainage structures. Franklin and vicinity: Enlargement of about 21.6 miles of back levee and construction of about 3.5 miles of new levees to effect a complete closure of area to be protected, construction of one floodgate and eight gravity drainage structures, and alteration of existing drainage facilities where necessary. Normal range of tide is 1.6 feet. Storm and hurricane tide have produced elevations up to 10 feet while northerly storms during winter depress the gulf level as much as 3 feet below mean sea level. During low water periods on Atchafalaya River, generally September through November, the effect of tide extends about 35 miles above Morgan City. Estimated cost for total project (October 1985) is $27,700,000 Federal and $14,950,000 non-Federal. Local cooperation. Local interest must furnish lands, easements, and rights-of-way for construction and future maintenance, provide relocations and alterations required for project; provide all interior drainage and pumping plants required for reclamation and development of protected areas; maintain and operate all project works after completion including levees, drainage structures, floodgates and drainage ditches or canals, in accordance with regulations prescribed by the Secretary of the Army; provide assurances that encroachment on existing ponding areas will be prevented unless substitute storage capacity or equivalent pumping capacity is provided promptly, without cost to the United States; contribute in cash or equivalent work not less than 30 percent of project cost, the final determination to be made after construction is complete; and hold and save the United States free from damages due to construction works. Assuring Agency: The act of assurance and supporting resolution from the St. Mary Parish Police Jury were accepted for and on behalf of the United States on Jul. 18, 1968. Supplemental assurances were furnished by the St. Mary Parish Police Jury for the Morgan City Area separable feature of the project. These supplemental assurances include the additional items of local cooperation required by PL 91-611 and PL 91-646 and were accepted on behalf of the United States on Jul. 23, 1980. The Franklin Area feature was specifically excluded in the supplemental assurances. Operations and results during period. The GDM for the Morgan City area was completed in FY 1985. Condition as of Sep. 30. Construction has not commenced. 14. NEW ORLEANS TO VENICE, LA, HURRICANE PROTECTION Location. Includes land subject to inundation by hurricane tides extending along both banks of the Mississippi River below New Orleans from vicinity of Phoenix to Venice, LA. Existing project. Provides for improvements along Mississippi River below New Orleans, LA, for prevention of hurricane tidal flood damages by increasing heights of existing back levees and modifying existing drainage facilities where necessary in three separate reaches: Reach A, on the west bank from City Price to Empire, 15 miles, 4,340 acres protected; Reach B, on the west bank from Empire to Venice, 21 miles, 4,900 acres protected; and Reach C, on the east bank from Phoenix to Bohemia (construction recently completed by local agency with credit given as equivalent work), 16 miles, 5,470 acres protected, and construction of a barrier levee on the east bank of the Mississippi River from Bohemia to mile 10 AHP with enlargement of the west bank Mississippi River levee from Fort Jackson to Venice, generally called the East Bank Barrier Levee plan. Reach B was later divided into two units, Reach B-1 from Empire to Fort Jackson and Reach B-2 from Fort Jackson to Venice, LA, as a result of a request made by the local agency. Estimated cost of new work (October 1985) is $164,000,000 Federal and $70,000,000 non-Federal, including $57,550,000 cash contributions or equivalent work. Local cooperation. Provide all lands, easements and rights-of-way including borrow areas and spoil disposal 11-11 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 areas necessary for the construction of the project, at costs presently estimated at $4,768,000; accomplish all necessary alterations and relocations to roads, pipelines, cables, wharves and other facilities required by the construction of the project at costs presently estimated at $7,682,000; bear 30 percent of the first cost, a sum presently estimated at $234,000,000, and cash contribution presently estimated at $57,550,000 to be paid either in a lump sum prior to initiation of construction or in installments prior to start of pertinent work items, in accordance with construction schedules as required by the Chief of Engineers, or as a substitute for any part of the cash contribution, accomplish in accordance with approved construction schedules items of work of equivalent value as determined by the Chief of Engineers, the final apportionment of costs to be made after actual costs and values have been determined; hold and save the United States free from damages due to the construction works; maintain and operate all works after completion in accordance with regulations prescribed by the Secretary of the Army; prevent any encroachment on ponding areas unless substitute storage capacity or equivalent pumping is provided promptly; and at least annually, notify those affected that the project will not provide complete protection from tidal flooding and that further local actions must be taken during hurricane emergencies. Local interests are also required to comply with the provisions of the Uniform Relocation Assistance and Real Property Acquisition Policies Act of 1970 (PL 91- 646), in acquiring real property. PL 91-611. Not applicable. Construction started prior to Jan. 1, 1972. PL 91-646. A constitutional amendment was provided by the Louisiana legislature on Feb. 1, 1972 allowing local interests to comply. The estimated cost to local interests is $48,000. Assurances of local cooperation for Reaches A, B-1, B-2 and C, requested on Jan. 7, 1963, were furnished by the Plaquemines Parish Commission Council on Mar. 6, 1964. Required supporting papers were furnished on Mar. 16, 1965 and accepted. Supplemental assurances covering the requirements of PL 91-646 were received from Plaquemines Parish Commission Council on May 23, 1973 and accepted on Jun. 20, 1973. Assurances for the entire project have been furnished and accepted, although they do not specifically mention the East Bank Barrier Levee Plan. The scope of the project has not changed; however, local interests were requested to furnish separate assurances for the East Bank Barrier Levee. These assurances have not yet been received. There was a delay of approximately 26 months in the furnishing of assurances by local interests primarily because they desired that agreement on levee alignment be consummated as fully as possible before giving their assurance. Problems of assurance of local cooperation have been resolved and rights-of-way were furnished for the first two Reach B-1 items of work on Aug. 23, 1968 and May 20, 1970, respectively. All negotiations for relocations are the responsibility of local interests. These mainly consist of raising several petroleum and natural gas pipelines to the levee configuration and relocation of privately owned frame structures used as fishing and boating camps. To assure that there will be no delay in construction of levees, local interests are notified well in advance so that the owners of the pipelines can be advised. Assuring Agency: Plaquemines Parish Commission Council. Assurances for all reaches of the project, except the East Bank Barrier levee, have been furnished. Operations and results during fiscal year. A GDM for the East Bank Barrier levee was initiated during FY 1985. Plans and specifications in Reaches B-2, C, and the Barrier were initiated and are continuing. Reach B-1, Sta. 0+00 to Sta. 100+00 was awarded Apr. 24, 1985. Condition as of Sep. 30. Construction began on the project in September 1968 and the total project is approximately 32 percent complete. By letter dated Feb. 5, 1985, the local sponsor requested the Corps of Engineers to defer further work on the design of Reach A and direct efforts toward construction of the East Bank Barrier levees. 15. INSPECTION OF COMPLETED FLOOD CONTROL PROJECTS Various hurricane protection projects, as well as small flood control projects, were inspected during FY 1985. Also, periodic inspection and continuing evaluation of completed civil works structures was conducted in accordance with ER 1110-2-100, at various times during the year on an as-needed basis. Fiscal year costs for the period were $226,156. Total costs to Sep. 30, 1985, were $1,712,627. 16. FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION Disaster preparedness, FY costs for the period were $153,681. Emergency Operations: Total costs to Sep. 30,1985, were $596,859. General Investigations 17. ACTIVE INVESTIGATIONS See Table 11-J which covers: Surveys, Collections and study of basic data, and Research and Development activities. 11-12 NEW ORLEANS, LA, DISTRICT TABLE 11-A COST AND FINANCIAL STATEMENT See Section Total Funds to in Text Project Funding FY 82 FY 83 FY 84 FY 85 . Sep. 30, 1985 1. Gulf Intracoastal Waterway between Apalachee Bay, FL & Mexican Border (New Orleans Dist.) 2. Leland Bowman Lock, LA (Replacement of lock) 3. Mermentau River, LA 4. Mississippi River, Baton Rouge to the Gulf of Mexico, LA 5. Mississippi River-Gulf Outlet, LA (Regular Funds) (Contrib. Funds) 6. Mississippi River Outlets, Venice, LA 7. Tangipahoa River, LA 8. Waterway from Intracoastal Waterways to Bayou Dulac, LA (Bayou Grand Caillou & LeCarpe, LA) 10. Grand Isle and Vicinity, LA (Contrib. Funds) New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Contrib. Cost New Work Approp. Cost Maint. Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost New Work Contrib. Cost $ 63,654,5351, 2, 3 63,284,4701, 2,3 15,876,100 10,524,486 9,269,000 10,649,100 13,242,263 12,391,442 8,796,692 11,522,717 6,029,800 14,000,000 10,325,000 6,058,840 12,697,628 8,341,621 1,050,900 1,013,415 555,000 562,024 - 900,000 - 1,545,117 2,578,556 600,000 1,972,500 623,870 1,981,824 800,000 4,000,000 878,037 1,192,445 30,268,000 45,611,260 48,510,600 39,039,920 29,826,943 43,786,783 47,713,135 41,229,463 1,235,200 1,472,670 8,754,000 7,134,791 -578 926,000 863,216 130,000 86,341 200,000 201,472 105,000 41,937 2,005,000 1,027,035 11,048,000 14,717,186 -2,900 340 2,196,000 2,227,642 75,000 111,102 500,000 1,664,718 9,705,000 10,169,620 2,200,000 1,286,205 4,429,000 4,515,392 121,500 77,500 1,423,000 2,832,000 1,394,421 2,881,422 - 40,000 - 28,419 40,000 228,000 43,223 177,151 3,000,000 4,161,000 226,231 6,714,791 - 2,110,000 - 2,000,000 -21,000 -21,000 432,000 653,469 100,000 100,000 167,980,8324 6 167,524,9665, 6 32,200,0107 31,449,8217 4,561,9108 4,672,5798 14,906,8129 14,898,6979 44,911,79710 42,601,88810 443,046,84411,' 13 442,002,06412,13 81,340,200 80,382,090 95,650,580 95,430,824 1,240,47714 1,196,47714 10,008,093 10,008,100 8,650,800 8,631,973 608,154 595,970 637,622 584,681 867,762 867,762 8,342,500 8,270,350 2,210,000 2,100,000 11-13 TABLE 11-A (Continued) REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 COST AND FINANCIAL STATEMENT See Section Total Funds to in Text Project Funding FY 82 FY 83 FY 84 FY 85 Sep. 30, 1985 11. Lake Pontchar- New Work train and vicinity, Approp. 13,000,000 13,716,000 8,800,000 11,158,000 161,238,000 LA (Hurricane Cost 13,720,371 13,510,392 7,937,422 10,382,763 158,400,628 Protection) (Regular Funds) (Contrib. Funds) New Work Contrib. 166,000 313,124 325,000 195,000 3,810,184 Cost 186,400 356,602 260,000 260,000 3,851,676 12. Larose to Golden New Work Meadow, LA Approp. 2,100,000 9,870,000 5,700,000 5,865,000 37,967,000 (Hurricane Cost 1,407,390 7,734,710 6,901,800 7,441,971 36,680,725 Protection) (Contrib. Funds) New Work Contrib. - - - 182,000 2,271,721 Cost 6,139 - - 182,000 2,243,268 13. Morgan City and vicinity, LA Approp. 250,000 384,000 387,000 280,000 2,032,000 Hurricane Cost 71,500 541,000 367,606 221,260 1,953,866 Protection) 14. Mississippi New Work River Delta at Approp. 1,535,000 3,450,000 2,830,000 1,920,000 53,389,000 and below New Cost 1,864,215 2,515,286 3,581,564 1,630,947 52,870,457 Orleans, LA (New Orleans to Venice, LA, Hurricane Protection) (Regular Funds) (Contrib. Funds) New Work Contrib. - 3,050,000 - - 3,416,430 Cost - 2,600,000 450,000 - 3,416,430 1. Includes $4,320,698 for new work on previous project. Included in these totals are $353,541 N.I.R.A. funds (new work); and $1,070,433 permanent indefinite appropriation. Included is repayment of advance funds for construction of Franklin Canal in the amount of $35,103. In addition, $1,413,133 was expended for transfer to drainage district of ownership of Plaquemines Parish pumping station, and drainage canals and all drainage responsibility and obligations vested in the United States by Public Law 14, 79th Cong., 1st sess. 2. Excludes contributed funds of $340,159. 3. Inner Harbor Navigation Canal Lock was constructed at a cost of $8,648,492 (non-Federal). 4. Does not include allotment of $60,000 (9613123). 5. Does not include expenditures of $36,630 (9613123). 6. Includes $454,259 for maintenance and $548,948 for operation and care for previous project, including $75,000 from appropriation for maintenance and operation of dam and other improvements of navigable waters. Excludes $7,005 contributed funds. 7. Includes AE&D funds for replacement of Vermilion Lock. 8. Excludes $10,904 for new work on White Lake to Pecan Island section of existing project. 9. Excludes $10,742 for maintenance on White Lake to Pecan Island section of existing project. Excludes $2,000 contributed funds. Includes $13,163 of R&H funds and $109,714 accelerated Public Works Act funds. 10. Includes $1,729,989 for previous project. 11. Does not include allotment of $40,000 (9613123). 12. Does not include expenditures of $63,370 (9613123). 13. Includes $169,055 for previous projects and $3,379,676 from permanent indefinite appropriation. 14. Contributed by Board of Commissioners, Port of New Orleans, for providing fill for future industrial sites adjacent to turning basin and for dredging cable and pipeline crossings. 11-14 NEW ORLEANS, LA, DISTRICT TABLE 11-B AUTHORIZING LEGISLATION Acts Work Authorized Documents Mar. 3, 1925 Jan. 21, 1927 Jul. 3, 1930 Jun. 26, 19343 Jul. 23, 1942 Mar. 2, 1945 Jul. 24, 1946 Jul. 24, 1946 Jul. 24, 1946 Oct. 23, 1962 Oct. 22, 1976 WRD Act of 1976, dated Oct. 22, 1976 (PL 94-587) Aug. 18, 1941 Jul. 24, 1946 GULF INTRACOASTAL WATERWAY BETWEEN APALACHEE BAY, FL, AND MEXICAN BORDER (NEW ORLEANS DISTRICT) (See Sec. 1 of Text) Construct waterway from New Orleans, LA, to Galveston Bay, TX Extension of waterway to Corpus Christi, TX A channel 9 by 100 feet from Lake Pontchartrain to Mississippi Sound. Operation and care of locks and dams provided for with funds from War Department appropriations for rivers and harbors. Enlarge waterway from 9 by 100 feet to 12 by 125 feet from Apalachee Bay, FL, to Corpus Christi, TX, and its extension to vicinity of Mexican border, except between Mobile Bay, AL, and New Orleans, LA, where width shall be 150 feet; and rental of Inner Harbor Navigation Canal facilities. Alternative connection with Mississippi River in vicinity of Algiers at New Orleans. Enlarge and extend Plaquemine-Morgan City route from Mississippi-Atchafalaya section of waterway, in vicinity of Morgan City, to and through a new terminal lock and entrance channel to Mississippi River in vicinity of Port Allen, opposite lower limit of Port of Baton Rouge. Restore, improve, and maintain Franklin Canal as a terminal branch channel, 8 by 60 feet, from its confluence with Gulf Intracoastal Waterway to Franklin, LA. A salt-water guard lock in waterway at mile 238 west of Harvey Lock. Enlarge waterway to 16 by 150 feet from Mississippi River to Atchafalaya River, except in vicinity of Houma mile 50.5 to 63.5); of Houma bypass (mile 50.5 to 63.5) and of Algiers alternative canal; and enlarge waterway from Atchafalaya River to Sabine River to 16 by 200 feet. Replacement of Vermilion Lock, in accordance with the recommendations of the Chief of Engineers in the report dated Aug. 3, 1976, recommending a lock size of 110 feet wide by 1,200 feet long by 15 feet deep. LELAND BOWMAN LOCK, LA (REPLACEMENT OF LOCK) (FORMERLY VERMILION LOCK) (See Sec. 2 of Text) A replacement lock, 110 feet wide and 1,200 feet long, to accommodate present and projected marine traffic. MERMENTAU RIVER, LA (See Sec. 3 of Text) Channel enlargement, lower Mermentau River, from mile 15 to Gulf of Mexico, and construction of a lock and control spillway at Catfish Point, mile 24. Channel enlargement; lower Mermentau River below Grand Lake, mile 25; construct a gated-control structure at or near Grand Cheniere, mile 7; enlarge and realine Inland Waterway from Franklin, LA, to Mermentau River, LA, from Vermilion Bay to White Lake, via new channel, and from White Lake to Grand Lake; enlarge channel of North Prong of Schooner Bayou; construct a gated-control structure in new channel near Schooner Bayou lock; and include project "Waterway from White Lake to Pecan Island, LA," and portion of project "Inland Waterway from Franklin, LA, to Mermentau River," west of Vermilion Bay in modified project "Mermentau River, LA." H. Doc. 238, 68th Cong., 1st sess. H. Doc. 238, 68th Cong., 1st sess. H. Doc. 341, 71st Cong., 2d sess. H. Doc. 96, 79th Cong., 1st sess.; H. Doc 230, 76th Cong., 1st sess.5 S. Doc. 188, 78th Cong., 2d sess. S. Doc. 242, 79th Cong., 2d sess. S. Doc. 189, 79th Cong., 2d sess. S. Doc. 231, 79th Cong., 2d sess. H. Doc. 556, 87th Cong., 2d sess. Approved by Secretary of the Army, May 1967, under authority of the R&H Act of 1909. S. Doc. 94, 77th Cong., 1st sess. S. Doc. 231, 79th Cong., 2d sess. 11-15 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 11-B (CONTINUED) AUTHORIZING LEGISLATION Acts Work Authorized Documents Mar. 2, 1945 Oct. 23, 1962 Mar. 29, 1956 Oct. 22, 1976 Aug. 13, 1968 Jun. 10, 1872 Jun. 14, 1880 Jun. 14, 1960 Aug. 30, 1935 Oct. 23, 1962 Adopted by Committee Resolutions Sep. 23, 1976, and Oct. 1, 19763 Oct. 27, 1965 MISSISSIPPI RIVER, BATON ROUGE TO GULF OF MEXICO, LA (See Sec. 4 of Text) Combines projects of Mississippi River, Baton Rouge to New Orleans, Mississippi River, South Pass, and Southwest Pass, adding thereto project for Mississippi River from New Orleans to Head of Passes, to provide a single project, "Mississippi River, Baton Rouge to the Gulf of Mexico," with channel dimensions as follows: Baton Rouge to New Orleans, 35 by 500 feet; port limits of New Orleans, 35 by 1,500 feet; New Orleans to Head of Passes, 40 by 1,000 feet, Southwest Pass, 40 by 800 feet; Southwest Pass Bar Channel, 40 by 600 feet; South Pass, 30 by 450 feet; South Pass Bar Channel 30 by 600 feet. Deepen existing channel from 35 to 40 feet by 500 feet wide from one-tenth mile below Louisiana Highway Commission bridge at Baton Rouge to upper limits of Port of New Orleans, and also 40 by 500 feet within presently authorized 35- by 1,500-foot channel in port limits of New Orleans. MISSISSIPPI RIVER-GULF OUTLET, LA (See Sec. 5 of Text) Construct a seaway canal 36 feet deep and 500 feet wide from Michoud to 38-foot contour in gulf and an inner tidewater harbor consisting of a 1,000- by 2,000-foot turning basin 36 feet deep and a connecting channel 36 feet deep and 500 feet wide to Inner Harbor Navigation Canal and provides, when economically justified, for construction of a lock to Mississippi River in the vicinity of Meraux, LA. Amends above Act making the construction of bridge relocations a Federal responsibility when required by the construction of the Mississippi River-Gulf Outlet channel. MISSISSIPPI RIVER OUTLETS, VENICE, LA (See Sec. 6 of Text) Enlargement of existing channels of Baptiste Collette Bayou and Grand-Tiger Passes to 14 by 150 feet with 16 by 250-foot entrance channels in open water and jetties, if justified. TANGIPAHOA RIVER, LA (See Sec. 7 of Text) Improvement, without dredging, by removing overhanging trees, snags, and obstructions to navigation from Wells to mouth. Present project above entrance channel. 8- by 100-foot entrance channel from 8-foot depth contour in Lake Pontchartrain to 8-foot depth in River. WATERWAY FROM INTRACOASTAL WATERWAY TO BAYOU DULAC, LA (Bayous Grand Caillou and LeCarpe, LA) (See Sec. 8 of Text) Channel 5 by 40 feet from Intracoastal Waterway at Houma through Bayou LeCarpe, Bayou Pelton, and Bayou Grand Caillou to Bayou Dulac, about 16,3 miles. Channel 10 by 45 feet in Bayou LeCarpe from Gulf Intracoastal Waterway to Houma navigation canal. GRAND ISLE AND VICINITY, LA (See Sec. 10 of Text) To provide hurricane protection by placement of a berm and vegetated dune extending the length of Grand Isle's gulf shore and a jetty to stabilize the western end of the island at Caminada Pass. LAKE PONTCHARTRAIN AND VICINITY, LA (HURRICANE PROTECTION) (See. Sec. 11 of Text) Contl 1 of hurricane tides by construction of two independent units, the Lake Pontchartrain Barrier plan and the Chalmette Area plan. H. Doc. 215, 76th Cong., 1st sess.1 S. Doc. 36, 87th Cong., 1st sess. H. Doc. 245, 82d Cong., 1st sess. Sec. 186, Water Resources Development Act of 1976 (PL 94-587) 2d sess. H. Doc. 304, 90th Cong., 2d sess. H. Ex. Doc. 54, 46th Cong., 2d sess., and Annual Report, 1871, p. 553. Annual Report, 1879, p.946. Aauthorized by Chief of Engineers Jul. 28, 1967, under Sec. 107 of 1960 River and Harbor Act, as amended. H. Doc. 206, 72d Cong., 1st sess. H. Doc. 639, 94th Cong., 2d sess. H. Doc. 231, 89th Cong., 1st sess. 11-16 NEW ORLEANS, LA, DISTRICT TABLE 11-B (CONTINUED) AUTHORIZING LEGISLATION Acts Work Authorized Documents LAROSE TO GOLDEN MEADOW, LA (HURRICANE PROTECTION) (See Sec. 12 of Text) Oct. 27, 1965 A loop levee about 36 miles long along both banks of Bayou H. Doc. 184, 89th Cong., 1st Lafourche from Golden Meadow to Larose; enlargement of 3 sess. miles of existing levee at Golden Meadow; floodgates for navigation and hurricane protection in Bayou Lafourche at upper and lower bayou crossings; about 8 miles of low interior levees to regulate intercepted drainage; and seven multibarreled culverts controlled by flapgates. MORGAN CITY AND VICINITY, LA, HURRICANE PROTECTION (See Sec. 13 of Text) Oct. 27, 1965 Construction of new levees along Lake Palourde and Bayou H. Doc. 167, 89th Cong., 1st Ramos, levee to tie-in with Bayou Boeuf lock levee and three sess. gravity drainage structures in Morgan City unit and enlargement of bank levee, construction of new levee, and construction of one floodgate and five gravity drainage structures in Franklin and vicinity unit. NEW ORLEANS TO VENICE, LA, HURRICANE PROTECTION (See Sec. 14 of Text) Oct. 23, 1962 Improvements along Mississippi River below New Orleans, LA, H. Doc. 550, 87th Cong., 2d for prevention of hurricane tidal flood damages by increasing sess. heights of existing back levees and modifying existing drainage facilities where necessary in five separate reaches. 1. Contains latest published map. 2. For latest published map, see H. Doc. 288, 66th Cong., 1st sess. 3. Permanent Appropriation Repeal Act. 4. Authorized under provision of Sec. 201 of Flood Control Act of 1965. 5. Not mentioned in authorizing act. 11-17 TABLE 11-C GULF INTRACOASTAL WATERWAY BETWEEN APALACHEE BAY, FL, AND MEXICAN BORDER (NEW ORLEANS DIST.)-LOCKS (See Sec. 1 of Text) Pertinent Data Pertinent Data Inner Bayou Bayou Harbor Plaque- Algiers Boeuf Sorrel Calcasieu Harvey Navigation mine Port Allen Vermilion Lock Lock Lock Lock Lock Canal Lock Lock Lock Lock Miles from New Orleans, LA (Canal St.) Miles below Lake Charles, LA Miles from Abbeville, LA Miles from Mississippi River Miles from Calcasieu River Miles from Vermilion River 96.6 (via Har- 135 (via Harvey Lock) vey Lock) 16.6 26 0.38 56.7 (via Plaquemine Lock) 18 (via Plaquemine Lock) 0.5 1.75 Width of chamber Width between abutments Length available for full width Lift Depth on sill at 13 feet mean low gulf level Character of foundation Timber piles 75 feet 800 feet 56 feet 75 feet 75 feet 75 feet - 84 feet 75 feet 1,156 feet 797 feet 0-18 feet 0-11.3 feet 0-21 feet 13 feet Concrete slab on medium of stiff clay 14 feet Timber piles 56 feet 1,206 feet 425 feet 0-4 feet 13 feet Concrete slab on preconstructed stiff clay 640 feet 0-19.6 feet 0-17.4 feet 12 feet 13.5 feet (miter sill) (miter sill) Timber piles Timber piles 1,202 feet 1,182 feet -0-45 feet 0-5 feet (either direction) - 13.75 feet (miter sill) - Concrete slab on clay 11.3 feet Timber piles 3.3 2.9 132.5 0.13 0.6 0.23 0 0 0 zN z Old 0 HL+-aa N Type of construction Kind of dam Reinforced Reinforced concrete concrete gate bays and earth chamber Opened to April navigation 1956 Reinforced concrete gate bays and earth chamber September June 1954 1951 $5,215,700 $2,754,000 $4,700,948 (Flood Control (Flood Control MR&T Funds) MR&T Funds) - - October 1952 Reinforced concrete gate bays and earth chamber December 1950 Reinforced Reinforced concrete concrete 1934 February 1923 $2,133,527 $1,775,132 $8,648,492 (non- Federal) - 1935 - - Reinforced Reinforced - concrete concrete 19091 July 1961 $1,302,006 $13,902,222 1909 July 1961 Reinforced concrete spillway dam, vertical cast steel gates, timber pile foundation 1933 $330,7652 19343 Cost Completed 1. Closed permanently September 29, 1961. 2. Replacement of lock approved by the Secretary of Army, May 16, 1967; estimated Federal cost $25,900,000. 3. Transferred to project status. Contruction of replacement lock, scheduled for January 1980. 0 z 0 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 11-D OTHER AUTHORIZED NAVIGATION PROJECTS Cost to Sep. 1985 For Last Mo. and Yr. Full Report Operation Completed See Annual and Deauthorized Project Status Report For: Construction Maintenance or Reclassified Alteration of Berwick Bay Bridge' Amite River and Bayou Manchac, LA Aquatic Plant Control Program, LA Atchafalaya River Bayous Chene Boeuf, and Black, LA Atchafalaya River, Morgan City to Gulf of Mexico, LA Baton Rouge Harbor, Segment between Mi. 2.5 and 5.02 Barataria Bay Waterway, LA Bayou Bonfouca, LA Bayou Dorcheat, Loggy Bayou and Lake Bisteneau, LA3' 4, 5, 6 Bayou Dupre, LA7 Bayou Grosse Tete, LA8 Bayou Lacombe, LA Bayou Lafourche and Lafourche Jump Waterway, LA Bayou La Lautre, St. Malo, and Yscolskey, LA Bayou Plaquemine Brule, LA Bayou Queue de Tortue, LA Bayou Segnette Waterway, LA Bayou Teche, LA Bayou Teche & Vermilion River, LA Bayou Terrebonne, LA4' 9 Bayou Vermilion, LA4 Big Pigeon and Little Pigeon Bayous, LA 3 Calcasieu River and Pass, LA Calcasieu River at Coon Island, LA'� Calcasieu River at Devil's Elbow, LA Cascasieu River Salt Water Barrier, LA" Cane River, LA3 ' 6 Chefuncte River and Bogue Falia, LA Cypress Bayou and Waterway between Jefferson, TX, and Shreveport, LA' 2 Freshwater Bayou, LA Grand Bayou Pass, LA Houma Navigation Canal, LA Inland Waterway from Franklin to Mermentau River, LA 1 'a Intracoastal Waterway from the Mississippi River to Bayou Teche, LA' 4 Lake Borgne and Chef Menteur- Bulkheads and Jetties Lake Charles Deep Water Channel, LA' 5 Little Caillou Bayou, LA Mermentau River, Bayou Nezpique, and Bay Des Cannes, LA Mississippi River-Gulf Outlet, Michoud Canal, LA Complete Complete Complete Complete Complete Deauthorized Complete Complete Complete Deauthorized Complete Complete Complete Complete Complete Complete Complete Complete Complete Complete Complete Complete Complete Complete Complete Complete Complete Deauthorized Complete Complete Complete 1967 1978 1984 1984 1981 19462 1984 1974 1887 1968 1967 1984 1970 1950 1970 1958 1984 1983 1961 1947 1936 1984 1976 1981 1973 1910 1967 1971 1984 1950 1984 1960 1956 19422 1950 1973 1977 1976 11-20 $ - 28,234 10,607,745 69,087 69,087 30,353,236 34,019,415 501,963 1,572,685 30,997 5,000 38,915 1969 4,716 1,624,424 96,916 33,410 33,355 238,828 754,330 2,891,822 120,089 34,900 16,247,990 313,037 104,1877 123,454 111,471 829,756 223,616 36,780 28,315 213,455 4,203,441 1,668,036 251,691 200,169 - 37,169 27,807,310 91,588,783 1,015,81410 - 5,856,200 4,197,262 2,500 58,342 202,817 7,116,224 7,676 249,052 77,761 5,197,97516 2,499,555 2,000 192,011 452,611 14,470,030 14,48012 17,212,890 552,780 11,699 241,896 751,485 114,519 1928 1914 Nov. 1979 Nov. 1963 1931 1939 May 1981 1938 May 1956 1915 March 1923 March 1957 1916 1896 3 Oct. 1968 April 1974 Sep. 1978 Jan. 1968 1959 Dec. 1914 Aug. 1968 1939 Nov. 1979 1929 Nov. 1974 NEW ORLEANS, LA, DISTRICT TABLE 11-D OTHER AUTHORIZED NAVIGATION PROJECTS (CONTINUED) Cost to Sep. 1985 For Last Mo. and Yr. Full Report Operation Completed See Annual and Deauthorized Project Status Report For: Construction Maintenance or Reclassified Navigation work under special authorization (Calcasieu Pass channel in Old River Bend at Cameron, LA)17 - 1957 - 139,755- Pass Manchac, LA Complete 1950 1,374 13,545 1912 Petite Anse, Tigre, and Carlin Bayous, LA Inactive 1981 - 920,152 Nov. 1980 Removal of Aquatic Growth, LA 1984 - 21,561,341 Sulphur River, AR and TX3' 6 - 1919 45,989 -- Tickfaw, Natalbany, Ponchatoula, and Blood Rivers, LA4 Complete 1973 8,115 92,163 1921 Vinton Waterway, LA21 Deauthorized 1950 - - Nov. 1979 Waterway from White Lake to Pecan Island, LAl3 - 1948 10,904 0,742 Waterway from Empire, LA, to Gulf of Mexico Complete 1981 1,068,142 835,252 Jun. 1950 1. Transferred to Department of Transportation. Authorized under Truman-Hobbs Act. 2. Date authorized. 3. Completed. Date will be furnished when available. 4. Includes previous project costs. 5. No commerce reported. 6. Abandonment recommended in H. Doc. 467, 69th Cong., 1st sess. 7. Includes $56 cost incurred in 1969. 8. Completed except that portion above mile 10.3 providing for widening from 40 feet to 60 feet, which is inactive. 9. By Public Law 88-404, that portion of Bayou Terrebonne between point where Barrow Street crosses said stream and a line determined by prolonging and extending eastern right-of-way line of New Orleans Boulevard southerly to south bank of said stream was declared nonnavigable. 10. Includes $66,000 contributed funds. 11. Operation and maintenance of the structure reported under project "Calcasieu River and Pass, LA." 12. Excludes $50,000 contributed funds. 13. Not completed; incorporated in navigation project "Mermentau River, LA." * 14. Not completed; superseded for most of its length by present 12- by 125-foot Gulf Intracoastal Waterway, which coincides with or parallels it. 15. Maintenance project; no future work schedules. 16. Includes $57,555 ($29,974 of which was from Public Works funds) for new work on previous project. Includes $114,519 for maintenance of previous project. 17. Work is under continuing authority. 11-21 TABLE 11-E REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 OTHER AUTHORIZED FLOOD CONTROL PROJECTS For Last Cost to Sep. 1985 Full Report Operation Mo. and Yr. See Annual and Mo. and Yr. Project Deauthorized Report For: Construction Maintenance Completed Aloha-Rigolette Area, Grant and Rapides Parishes, LA1 Amite River and Tributaries, LA Bayou Bodcau, Red Chute, and Loggy Bayou, LA1 12 Bayou Choupique, LA3 Bayou Nicholas, Coushatta, LA3 Bayou Pierre in vicinity of Shreveport, LA 1 2, 12 Bayou Rapides, LA3 Black Bayou Reservoir, LA1, 4, 5. 12 Black Bayou-Pine Island Area, LA3 Campti-Clarence Area in Natchitoches Parish, LA Choctaw Bayou and Tributaries, LA1 7,12 Colfax, Grant Parishes, LA1"' Cooper Lake and Channels, TX8 East Point, LA Ferrells Bridge Dam-Lake O' the Pines, TX 8 9 Garland City, AR.' 2 Grant Parish below Colfax, LA1, 9 Harvey Canal, Bayou Barataria Levee, LA Hempstead County Levee District No. 1, AR.1, , 12 Maniece Bayou, AR.1, 2' 12 McKinney Bayou Finn Bayou Segment, AR.' 12 Natchitoches Parish, LA1, 2 Pineville, Red River, LA1, 3, 12 Posten Bayou, AR.1"1' 12 Red River Parish, LA1, 9,12 Red River in vicinity of Shreveport, LA1, 12 Saline Point, LA1, 9 Aug. 1977 1956 1964 1948 1954 1964 1951 1952 1945 1963 1978 1977 1938 1979 1969 1979 1976 1941 1979 1941 1970 196310 1956 1953 1973 1939 1953 1945 $ 1,653,189 3,034,2552 319,200 129,930 70,717 243,3362 95,179 336,063 1,655,700 741,892 70,348 20,839,300 486,069 14,175,197 1,335,842 38,809 1,018,005 88,006 970,9322 1,529,478 232,426 149,435 3,908,000 124,111 $ - Apr. 1955 - Feb. 1964 - Jan. 1948 - Mar. 1954 - Jun. 1964 Jun. 1939 - Dec. 1951 - May 1963 - Jul. 1978 - Apr. 1976 - Aug. 1968 8,301,021 Jul. 1974 9 - A9 - Aug. 1969 - Aug. 1955 - Dec. 1951 - M9 - Mar. 1953 11-22 NEW ORLEANS, LA, DISTRICT TABLE 11-E (CONTINUED) OTHER AUTHORIZED FLOOD CONTROL PROJECTS For Last Cost to Sep. 1985 Full Report Operation Mo. and Yr. See Annual and Mo. and Yr. Project Deauthorized Report For: Construction Maintenance Completed Twelvemile Bayou, LA3 - 1966 335,433 - May 1965 Wright Patman Dam and Lake, TX S - 1979 35,659,176 11,195,021 1. Authorized under project "Red River Below Denison Dam." 2. In addition, the following was expended from contributed funds: Amite River and tributaries .............. $ 430 Bayou Pierre in vicinity of Shreveport, LA ......................... 89,047 Choctaw Bayou and Tributaries, LA ...... 170,799 Harvey Canal, Bayou Barataria Levee, LA ............................. 425,209 Maniece Bayou, AR.................... 39,293 Natchitoches Parish, LA ............... .. 250,000 3. Authorized by Chief of Engineers. (Sec. 205, 1948 Flood Control Act, as amended.) 4. Construction not initiated. 5. Inactive. 6. Includes $92,000 for preauthorization studies. 7. Completed under provisions of Sec. 7, Flood Control Act 1928, as amended by Sec. 9, Flood Control Act 1936, and included in 1939 Annual Report of President, Mississippi River Commission, p. 2214. 8. These projects transferred to the Fort Worth District, Southwestern Division, during FY 1979. 9. Completed. Date will be furnished when available. 10. Date authorized. 11. Posten Bayou Project, authorized by Senate and House Resolutions, Dec. 17 and 15, 1970, deleted the plan authorized by the Flood Control Act dated Aug. 3, 1955. 12. These projects transferred to the Vicksburg District during FY 1983. 11-23 TABLE 11-F REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 ACTIVE GENERAL INVESTIGATIONS (96x3121) Federal Cost Totals by Item and CWIS Number FY 85 Categories SURVEYS (Category 100) Navigation (110) GIWW LA & TX Section -10032 Flood Control Studies (120) Aloha-Rigolette Area, LA -12123 Amite River & Tributaries, LA -50100 Lake Pontchartrain-West Shore, LA -79700 Louisiana Coastal Area, LA -61610 Louisiana Coastal Area, LA, Land Loss & Marsh Creation -12348 Louisiana Coastal Area, LA, Shore & Barrier Island Erosion -12354 Louisiana Coastal Area, LA, Water Supply -12355 Mermentau, Vermilion & Calcasieu Rivers & Bayou Teche, LA -34014 Review of Authorized Projects (160) Deauthorization Review -77000 Miscellaneous Activities (170) Special Investigations -17250 Coordination Studies with Other Agencies (180) Planning Assistance to States (186) -51850 Planning Assistance to States (186) -14822 $ 352,647 352,647 139,783 326,861 69,947 6,752 183,865 153,835 194,728 610,047 1,685,818 9,783 13,315 30,676 29,975 60,651 TOTAL (Category 100) COLLECTION AND STUDY OF BASIC DATA (Category 200) Flood Plain Management Services (250) Flood Plain Management Services Hydrologic Studies (260) Hydrologic Studies -53820 TOTAL (Category 200) CONTINUATION OF PLANNING AND ENGINEERING (Category 400) Lake Pontchartrain-North Shore, LA -12349 Mississippi River-Ship Channel, Gulf to Baton Rouge, LA (55270) TOTAL (Category 400) ADVANCE ENGINEERING AND DESIGN (Category 600) Flood Control Projects (650) McKinney Bayou, AR and TX (75353) West Agurs Levee, LA (75345) TOTAL (Category 600) GRAND TOTAL GENERAL INVESTIGATIONS 175,472 227 175,999 44,991 659,094 704,085 16 2,046 2,062 $3,004,360 11-24 $2,122,214 VICKSBURG, MS, DISTRICT* This district comprises western and Central Mississippi, southern Arkansas, northern Louisiana, and a very small portion of southwestern Tennessee, embraced in drainage basins of eastern tributaries of Mississippi River south of Horn Lake Creek to and including Buffalo River; Pearl River Basin in Mississippi; independent tributaries of the Gulf of Mexico south of the Buffalo River Basin to the Mississippi- Louisiana state line; western tributaries of Mississippi River between White and Atchafalaya Rivers including Arkansas River Basin below a point 3 miles upstream from Pine Bluff and Arkansas River below mile 36.1 near Pendleton, Arkansas; Ouachita and Black Rivers in Arkansas and Louisiana; and Red River in Louisiana and Arkansas to the Texas-Louisiana state line. IMPROVEMENTS Navigation 1. Claiborne County, MS ............. 2. Lake Providence Harbor, LA ....... 3. Madison Parish Port, LA ........... 4. Ouachita and Black Rivers below Camden, AR .................... 5. Overton-Red River Waterway, LA . .. 6. Pearl River, MS and LA ........... 7. Red River emergency bank protection ....................... 8. Red River Waterway-Mississippi River to Shreveport, LA ........... 9. Rosedale Harbor, MS .............. 10. Yazoo River, MS ................. 11. Navigation work under special authorization .................... Flood Control 12. Bayou Bartholomew and tributaries, AR and LA ............ 13. Bayou Bodcau and tributaries, AR and LA ..................... 14. Bayou Bodcau Reservoir, LA ........ 15. Bayou Pierre, LA ................. 16. Blakely Mountain Dam-Lake Ouachita, Ouachita River, AR ....... 17. Caddo Lake, LA .................. 18. DeGray Lake, Caddo River, AR ..... 19. Lead Bayou, MS ................. 20. Narrows Dam-Lake Greeson, Little Missouri River, AR ............... 21. Ouachita River Levees, LA ......... 22. Ouachita River and tributaries AR and LA ..................... 23. Pearl River Basin, MS and LA ...... 24. Porter Bayou, MS ................ 25. Poverty Point State Commemorative Area, LA ........................ Page Flood Control (cont) 12-2 26. Red River Below Denison Dam 12-2 (Vicksburg Dist.) ................. 12-2 27. Red River below Denison Dam, levees and bank stabilization 12-2 (Vicksburg District) .............. 12-3 28. Red River Waterway-Shreveport, 12-3 LA, to Index, AR ................. 29. Wallace Lake, AR ................ 12-4 30. Inspection of completed Flood Control Projects ................... 12-4 31. Flood control work under 12-5 special authorization .............. 12-5 12-5 Tables Table 12-A Cost and Financial Statement .................. Table 12-B Authorizing Legislation ....... Table 12-C Ouachita and Black Rivers, 12-5 AR and LA (9-Foot Project), Locks and Dams ............. 12-6 Table 12-D Locks in Pearl River Project .... 12-6 Table 12-E Other Authorized Navigation 12-7 Projects .................. Table 12-F Ouachita River and Tributaries 12-7 Existing Project ............. 12-7 Table 12-G Reservoir Operations 12-7 Fiscal Year 1984 ............ 12-8 Table 12-H Red River Below Denison Dam (Vicksburg Dist.) 12-8 New Projects ............... 12-8 Table 12-I Red River Below Denison Dam (Vicksburg Dist.) 12-8 Incorporated Projects ........ 12-9 Table 12-J Other Authorized Flood 12-9 Control Projects ............. Table 12-K Active General Investigations ... 12-10 12-1 Page 12-10 12-10 12-11 12-11 12-11 12-11 12-13 12-16 12-19 12-20 12-21 12-22 12-22 12-23 12-24 12-25 12-26 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Navigation 1. CLAIBORNE COUNTY PORT, MS Location. A slack-water harbor on the east bank of the Mississippi River at mile 405 above Head of Passes, and about 4 miles west of Port Gibson, MS. Existing project. A dredged access channel 800 feet long and 150 feet wide with a 400- by 800-foot turning basin and an additional 50 feet of fleeting and berthing on the north and south bank. Local cooperation. Fully complied with. Operations and results during fiscal year. No maintenance dredging was performed during FY 85. Condition as of Sep. 30. No major navigation problems exist at this present time. 2. LAKE PROVIDENCE HARBOR, LA Location. In Hagaman Chute, a secondary channel of the Mississippi River at mile 483.4 above Head of Passes, and about 3 miles south of Lake Providence, LA. Existing project. A dredged harbor channel about 0.7 mile long and 150 feet wide with a project depth of 9 feet in Hagaman Chute from the Mississippi River. Channel was widened to 400 feet in front of and upstream from port area, a distance of 800 feet, to provide a turning basin. Local interests constructed retaining dikes to provide the disposal area for material excavated from channel and turning basin. Resulting hydraulic fill provides a raised port area. Federal cost of completed work was $198,859, excluding preauthorization study costs of $9,678. Total non- Federal cost was $233,400, including cost of retaining dikes, and a cash contribution of $35,000. In addition, local interests have spent $1,022,000 for port facilities. Restudy of port for expansion, completed under continuing authority program. No further expansion is recommended. Local cooperation. Fully complied with. Terminal facilities. Local interests provided port facilities. Operations and results during fiscal year. The contract dredge George D. Williams and the Dredge Jadwin removed 683,000 cubic yards of material during FY 85. Condition as of Sep. 30. No major navigation problems exist at the present time. 3. MADISON PARISH PORT, LA Location. A "fast-water" dredged channel located near the right descending bank of the Mississippi River at mile 457.2 above Head of Passes, and about 6 miles north of Tallulah, Louisiana. Existing project. A dredged harbor channel about 0.5 mile long and 150 feet wide with a project depth of 9 feet. A turning basin within this channel was constructed by widening the harbor channel to 350 feet for a distance of 1,000 feet. Dredged material was used in construction of two hydraulic fills on property owned by the Madison Parish Port Commission for future development. Channel construction was completed in October 1980. Local cooperation. Fully complied with. Terminal facilities. Madison Parish Port Commission has constructed a multipurpose loading dock, rail facilities, and storage building on hydraulic fill. Two private interests are engaged in grain handling facilities on adjacent properties. Operations and results during fiscal year. No maintenance dredging was performed during FY 85. Condition as of September 30. No major navigation problems exist at the present time. 4. OUACHITA AND BLACK RIVERS BELOW CAMDEN, AR Location. Ouachita River rises in Polk County, AR, and flows southeasterly and southerly about 600 miles. Below its confluence with the Tensas and Little Rivers at Jonesville, LA, it is called Black River, which enters Red River 35.5 miles from the Mississippi River. Previous projects. See page 683 of Annual Report for 1962 for details. Existing project. See page 684 of Annual Report for 1962 for details of existing 6.5-foot navigation project. New work for completed project costs $4,574,551, exclusive of amounts expended under previous projects. Modified project and project for Red River below Fulton, AR, provide for a channel 9 feet deep and 100 feet wide in Red River between Old River and mouth of Black River, and in Black and Ouachita Rivers from mouth of Black River to Camden, AR. This is being accomplished by construction of four new locks, 84 feet by 600 feet; new dams; channel realinement to accommodate the 9-foot draft tow; and measures to preserve Catahoula Lake for migratory waterfowl. Jonesville Lock and Dam replaced Lock and Dam No. 2; Columbia Lock and Dam and Dams Nos. 3, 4, and 5; Felsenthal Lock and Dam replaced Lock and Dam No. 6; and Calion Lock and Dam replaced Lock and Dam No. 8. The Felsenthal Canal was deauthorized as of Aug. 5, 1977, in accordance with Section 12 of the Water Resources Development Act of 1974. The River and Harbor Act of 1970 authorized establishment of wildlife refuges along Bayou D'Arbonne (14,700 acres) in connection with Columbia Lock and Dam and at Felsenthal Lock and Dam (65,000 acres). The Bayou D'Arbonne refuge was increased to 18,000 acres at the request of the Bureau of Sport Fisheries and Wildlife. Estimated cost for new work for 9-foot navigation project is $279,150,000 including $269,000,000 Federal and $10,150,000 non-Federal for lands, damages, and relocations. Local cooperation. Local cooperation for all completed work in Louisiana has been furnished in a 12-2 VICKSBURG, MS, DISTRICT timely manner. It is anticipated that local interests in Louisiana will be able to supply the necessary rightsof- way for construction of the cutoffs and bend widenings. Local interests in Arkansas have furnished the rights-of-way for the Felsenthal and Calion Locks and Dams and it is anticipated that the remaining rights-of-way will be furnished when needed. The city of Camden, AR, has furnished land for the Sandy Beach recreation area. All assurances from local interests including supplemental assurances (Public Law 91-646) have been accepted. Terminal facilities. Public loading docks are at Columbia, LA, and Camden and Crossetts, AR. Privately owned docks and loading and unloading facilities are at Columbia, Monroe, and Sterlington, LA, and El Dorado, Calion, and Camden, AR. Two grain-handling facilities and a petroleum-loading facility are in the vicinity of Jonesville, LA, and a grain-handling facility is in the vicinity of Acme, LA. Operations and results during fiscal year. Construction of all the locks and dams in the project are now complete. Constructionof the Felsenthal Access Channel and Closure Dam was completed in FY 85. The construction of Calion Access Channel was discontinued due to changed site conditions: A decision was made to issue a new construction contract to complete the access channel. The plans and specification to finish this work were completed in FY 85 and construction should begin in early FY 86. The demolition contracts for removal of Lock #6 and Lock #8 are substantially complete. The federally funded portion of Crossett Harbor, AR, was completed in FY 85. Redesign of the channel alignment feature was initiated in FY 85 with completion scheduled for FY 86. The George D. Williams and Armadillo II removed 1,418,900 cubic yards of material from the Ouachita-Black Waterway. The Armadillo II removed 158,100 cubic yards of material from Crossett Harbor during construction. Condition as of Sep. 30. The 6.5-foot project was complete and has been maintained to Camden, AR, since 1925. Planning and design for the 9-foot navigation project started in FY 62 are continuing. Construction at Columbia Lock and Dam started in February 1964. The dam was completed in November 1968, and the lock was completed in January 1970 and was placed in service in May 1972. Construction at Jonesville Lock and Dam started in May 1967. The lock and dam were completed in January 1972 and were placed in service in March 1972. A 9-foot navigation channel along the existing project alignment was established from the Red River to Sterlington, LA, in June 1972. (See Table 12-C on locks and dams, Ouachita and Black Rivers, AR and LA). Demolition of Lock and Dam. No. 6 is under way and Lock and Dam No. 8 will begin soon. The contract for removal of four abandoned locks and dams which proved hazardous to navigation in the Columbia and Jonesville pools is completed. Construction of Felsenthal Lock and Dam is complete. Calion Lock and Dam has opened for navigation. There have been 17,421 acres acquired for the Bayou D'Arbonne Wildlife Refuge and 64,976 acres acquired for the Felsenthal Wildlife Refuge. Acquisition of the lands for both refuges is complete. Acquisition of mineral interest and relocations assistance in the Felsenthal Wildlife Refuge are continuing. 5. OVERTON-RED RIVER WATERWAY, LA Location. In the State of Louisiana between junction of the Old and Mississippi Rivers and Shreveport, LA, along the Old and Red Rivers, through land cuts and natural channels on the south bank of Red River. (Refer to Geological Survey State maps and the MRC alluvial valley quadrangle maps.) Existing project. Provides for a navigation route from the Mississippi River at its junction with Old River, through Old River to mile 35.5 of the Red River; developing a channel about 35.5 miles long, 100 feet wide, and 9 feet deep. Improvements consist of revetments, dikes, and dredging designed to preserve favorable and correct unfavorable channel alignment and depth. In addition to the existing project, the authorized work included a navigation route from mile 35.5 of the Red River to Shreveport, LA, via a lateral canal excavated along the south bank of the Red River. However, the portion of the authorized project above mile 35.5 was reclassified to inactive status as approved by Office of the Chief of Engineers, letter dated Oct. 18, 1971, and has been identified as eligible for deauthorization. Local cooperation. Fully complied with. For details see page 11-18, Annual Report FY 80. Terminal facilities. None. Will be furnished if necessary. Operations and results during fiscal year. Maintenance of waterway from Old River to Black River funded under project Red River Waterway, Mississippi River to Shreveport, LA. Condition as of Sep. 30. Construction of the lower 31 miles was initiated Nov. 12, 1968, and is 100 percent complete with 68,923 linear feet of bank protected. 6. PEARL RIVER, MS AND LA Location. Pearl River rises in east central Mississippi and flows southwest about 130 miles to Jackson, Mississippi, thence southeast about 235 miles to the head of its delta, where it divides into West Pearl and East Pearl Rivers. West Pearl River flows about 50 miles to the Rigolets, a tidal pass connecting Lake Pontchartrain with Lake Borgne, an arm of the Gulf of Mexico. Previous project. For details see page 750, Annual Report for 1938 and page 463, Annual Report for 1965. Existing project. The authorized project provides for a channel from the mouth of West Pearl River for 58 miles to the mouth of Bogalusa Creek at Bogalusa, LA, 7 feet deep at low water with a bottom width of 100 feet in the river sections and 80 feet in the canal 12-3 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 section, with locks 65 by 310 feet clear inside dimensions. The plan of improvement may be divided into three sections as follows: the river section from the mouth of West Pearl River to mile 28.5 at Holmes Bayou with a channel 7 feet deep and 100 feet wide to be obtained by dredging, snagging, and construction of cutoffs and easement of critical bends at eight locations below Lock One along Pearl River in its reach from its mouth to mile 26, all at a depth of 7 feet; the canal section from mile 28.5 to 48.7 at Pools Bluff with a channel 7 feet deep and 80 feet wide to be obtained by construction of three locks in the canal with sills across Bogue Chitto at mile 44 and across the river at mile 48.7; the river section from mile 48.7 to 58 at the mouth of Bogalusa Creek to be obtained by dredging, snagging, and easing of bends. At Bogalusa the mean variation of water surface is 10 feet and extreme, 23 feet. Plane of reference is mean low water. (See Table 12-D for features of locks included in existing projects.) Local cooperation. Fully complied with. Terminal facilities. The city of Bogalusa provides a barge terminal consisting of a wharf, transit shed, and access road at Richardson's Landing at the head of the project. Only natural landings exist at various locations on the river. Operations and results during fiscal year. Routine maintenance was performed at each of the three lock sites during the year. Condition at end of fiscal year. The existing project, prior to adoption of modifications authorized by the 1966 River and Harbor Act, was begun in October 1938 and completed in January 1956. All locks were opened to navigation in November 1953. No work has been initiated on modifications (cutoffs and easements of bends below Lock 1) authorized by the 1966 Act. Total Federal costs under existing project as of Sep. 30, 1985 were $8,562,908 for new work and $5,791,122 for maintenance, a total of $14,354,030. Contributed funds for new work amount to $65,000. The responsibility of this project was transferred to Vicksburg District, Lower Mississippi Valley Division, on Oct. 1,1981. 7. RED RIVER EMERGENCY BANK PROTECTION Location. In northwest Louisiana, southwest Arkansas, and northeast Texas, along the Red and Old Rivers between the Mississippi River and the head of the levee system above Index, TX. Existing project. Provides for realigning the banks by means of cutoffs and training works and for stabilizing banks by means of revetments, dikes, and other methods as emergency conditions may require in advance of developing the design for the entire Red River Waterway project. Estimated cost for new work (October 1984) is $63,846,000 Federal and $2,182,000 non-Federal, including a cash contribution of $7,000. Local cooperation. Fully complied with. For details see pages 11-19 to 11-20, Annual Report FY 80. Operations and results during fiscal year. Work by hired labor consisted of preparing plans and specifications, surveys, and general engineering. Stabilization work was completed at Swan Lake, river mile 356.4-L. Construction of the Maniece Revetment, river mile 353-L, was initiated and completed. Construction of the Goose Lake realignment, river miles 348 to 352 is continuing. A construction contract for Horseshoe Revetment, river mile 407-L, was awarded on September 17, 1985. Condition as of Sep. 30. Construction was initiated in October 1972 and is 95 percent complete. 8. RED RIVER WATERWAYMISSISSIPPI RIVER TO SHREVEPORT, LA Location. From east central to northwest Louisiana along the Red and Old Rivers between the Mississippi River and Shreveport, LA. Existing project. Provide a navigation route from the Mississippi River at the junction with Old River via Old and Red River to Shreveport, LA, developing a channel approximately 236 miles long, 9 feet deep, and 200 feet wide. The development will include five locks and dams, realignment and contraction of the river as necessary to develop an efficient channel, and bank stabilization as necessary to hold the newly developed channel in position. Facilities to provide opportunities for recreation and for fish and wildlife development are an integral part of the project. Estimated cost for new work (October 1985) is $1,550,350,000 Federal and $67,728,000 non-Federal, including $35,058,000 contributed funds. The Federal cost excludes $294,000 for aids to navigation by U.S. Coast Guard. Local cooperation. For details see page 11-21, Annual Report FY 80. The Red River Waterway Commission, governing body of the Red River Waterway District, executed an act of assurance for all project features in Louisiana on Feb. 26, 1969, supported by resolution dated Jan. 30, 1969. The assurances were accepted for and on behalf of the United States on Apr. 15, 1969. The Commission furnished amended assurances covering the provisions of Public Law 91-646 on May 23, 1973, for the portion of the project within Louisiana which were accepted for and on behalf of the United States on Nov. 14, 1973. Terminal facilities. Local interests are to provide adequate terminal facilities along the waterway. The Corps entered into an agreement with the City of Alexandria, LA, whereby material excavated from the proposed Philip Bayou Realignment could be used as fill for port construction at mile 109. Construction of the realignment began in FY 85. Operations and results during fiscal year. Hired labor continued work on Design Memoranda, preparation of Plans and Specifications, Surveys, General Engineering, and Model Studies, Phase III construction at Lock and Dam 1 was completed and the structure was dedicated on Nov. 9, 1984. Construction of the John 12-4 VICKSBURG, MS, DISTRICT H. Overton Lock and Dam reached 70 percent completion with a scheduled contract completion of May 27, 1987. A construction contract for preparatory sitework at Lock & Dam #3 was awarded on Sep. 11, 1985. Construction of channel realignment and stabilization works in Pools 1 and 2 consisted of the completion of four items, initiation of five items, and construction was continuing on nine items. The contract dredges George D. Williams and Armadillo II removed 426,600 cubic yards of material in FY 85. Condition as of Sep. 30. Construction was initiated in July 1973, and project is 40 percent complete. 9. ROSEDALE HARBOR, MS Location. In Log Loader Chute, a secondary channel of the Mississippi River at mile 584.5 above Head of Passes, and about 2 miles south of Rosedale, MS. Existing project. A dredged harbor channel about 2.4 miles long and 150 feet wide with a project depth of 9 feet. A turning basin consists of a dredged channel 1,000 feet long and 400 feet wide. Local interests constructed retaining dikes to provide the disposal area for material excavated from the channel and turning basin. Resulting hydraulic fill provides a 20- acre port area. Channel construction was completed in February 1978 at a cost of $2 million. Local interests are continuing construction on port terminal, dock facilities, and additional dredging. Local cooperation. Fully complied with. Terminal facilities. Local interests provided port facilities. Operations and results during fiscal year. The contract dredge, George D. Williams removed 402,000 cubic yards of material during FY 85. Condition as of September 30. No major problems were experienced with navigation. 10. YAZOO RIVER, MS Location. Formed by junction of Tallahatchie and Yalobusha Rivers in Leflore County, MS, flows about 169 miles southerly and southwesterly, and enters Mississippi River at Vicksburg, MS. (See Mississippi River alluvial valley quadrangle maps.) Previous projects. See page 681 of Annual Report for 1961 for details. Authorized project. The Yazoo River Navigation project consists of a 9-foot channel from its mouth to Greenwood, MS, mile 164.9 (present mileage), with a minimum width of 150 feet. The project includes a single lock (84 feet by 600 feet) and a dam located near Vicksburg, dredging and channel realinement; 600,000 acre-feet of additional storage in Sardis Lake to augment low flows in the Yazoo River, and recreation features. Total estimated (1985) Federal cost of 9-foot project is $225,425,000 which includes. $425,000 for the U.S. Coast Guard. Total estimated non-Federal cost is $2,786,000. These figures do not include the total estimated (1985) Federal cost of Belzoni Bridge relocation which is $8,570,000 and the total estimated non- Federal cost which is $252,000. Local cooperation. Requirements of local cooperation are fully described on page 12-3 of FY 80 Annual Report. Terminal facilities. At Greenwood there is a privately owned dock and a grain-loading facility. There are privately owned facilities for loading grain at Belzoni and Satartia. At Yazoo City there is a privately owned grain-loading facility, a private logloading facility, a private dock to handle dry and liquid fertilizer, and a public terminal. Operations and results during fiscal year. Construction of the Belzoni Bridge has been completed. Condition as of Sep. 30. Entire river is navigable. No work done on new authorization. Phase I studies are being deferred on the nine foot project due to lack of economic justification. 11. NAVIGATION WORK UNDER SPECIAL AUTHORIZATION Navigation activities pursuant to Sec. 107, Public Law 87-645, as amended (preauthorization). During FY 85, detailed project studies continued on Union County Port, AR, at a cost of $22,757; completed studies on Yellow Bend Port, AR, at a cost of $1,476; and initiated some on Greenwood Port, MS, at a cost of $119,376. Reconnaissance studies were completed on Two Bayou Port, AR, at a cost of $10,738. Plans and specifications were initiated at Bastrop Port at a cost of $3,125. Flood Control 12. BAYOU BARTHOLOMEW AND TRIBUTARIES, AR AND LA Location. Bayou Bartholomew rises in Jefferson County, AR, about 10 miles northwest of Pine Bluff and flows southerly about 370 miles to join the Ouachita River upstream from Sterlington, LA. Authorized project. Project includes ten waterretention lakes in the western tributaries of Bayou Bartholomew in Arkansas and six local levee units along the main stem of Bayou Bartholomew in Louisiana. However, because of public opposition to construction of the loop levees, preconstruction planning of the six loop levees has been deferred until such time as there is sufficient support for such levees by local interests. Channel improvements previously authorized are deferred until it is determined that the quality and quantity of water downstream will not be adversely affected. Latest approved (1979) estimated cost of new work is $46,913,000 including $44,800,000 Federal and $2,113,000 non-Federal. 12-5 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Local cooperation. Requirements of local cooperation are fully described on page 12-5 of Fiscal Year 80 Annual Report. Operations and results during fiscal year. Preconstruction planning and design have been deferred pending favorable benefit-cost ratios. Condition as of Sep. 30. Preparation of general design memorandum has been deferred due to lack of economic justification. Status of studies: A re-evaluation study is underway to determine if there are any feasible alternatives. 13. BAYOU BODCAU AND TRIBUTARIES, AR AND LA Location. In east bank flood plain of Red River. Bayou Bodcau rises in vicinity of Hope, AR, and flows southerly through Bayou Bodcau Reservoir and Bodcau Lake to join Cypress Bayou apd form Red Chute Bayou, continues through Red Chute Bayou, Flat River, and Loggy Bayou to Red River, about 40 miles below Shreveport, LA. Authorized project. Cypress Bayou-Red Chute Bayou levee: Extend existing levee from about 8 miles southeast of Benton, LA, proceeding southerly 'to junction of Cross and Red Chute Bayous, and then parallel to Red Chute Bayou on the right descending bank to its junction with Cutoff Bayou for a total distance of approximately 25 miles; construct landside drainage channel and several culverts with flap gates to Red Chute Bayou; construct approximately 5 miles of levee on left descending bank of Red Chute Bayou extending south from Louisiana Highway 612, and relocate utility lines as needed. Flat River-Loggy Bayou levee: Extend from lower end of existing Red River levee in vicinity of Ninock, LA, along high (left descending) bank of Red River to a point on right descending bank of Loggy Bayou, about 1 mile above its mouth, thence generally along right descending bank of Loggy Bayou, Red Chute, Cutoff Bayou, and Flat River to Taylortown to tie into existing Red River levee; close Flat River near its junction with Cutoff Bayou and install one 36-inch round corrugated metal pipe with automatic flap gate to drain isolated pockets and provide uninterrupted drainage; construct drainage structures on Flat River near its junction with Red Chute Bayou and along alignment of the Loggy Bayou in the vicinity of Grassy Lake; and make necessary utility relocations. Flat River channel improvement: Enlarge to average bottom width of 50 feet with flat side slopes and deepen by 2 to 6 feet from the confluence with Cutoff Bayou to junction with Cooper Bayou, 11.6 miles, including required relocations and modifications of utilities. Estimated cost for new work (October 1984) is $25,100,000 Federal and $7,600,000 non-Federal; however, this is subject to change pending outcome of the reevaluation study currently under way. The subject project was one of the Water Resources projects reviewed in March 1977 in accordance with the President's request. As a result of this review, the President Recommended to deauthorize this project. Congress subsequently directed the Corps to take the following two actions: Construct levees on Red Chute Bayou below Cutoff Bayou that are required to prevent induced flood damage that would otherwise result from the abandonment of partly completed project. Initiate studies to determine if modifications to the authorized project would permit its completion in a form consistent with the current executive policy. Engineering and design work for the induced flood prevention plan below Cutoff Bayou and project modification studies were being conducted when President Reagan signed, on Dec. 4, 1981, the Energy and Water Development Appropriations Bill of 1982, which contained language that "reconfirmed without further study and analysis" the plan for flood control for the project as approved by the Flood Control Act of 1965. Additional documents concerning environmental and socioeconomic impacts are currently being prepared and will be available to the public prior to further construction. There is clear evidence of a marked shift in land use within the project area over the past several years, from rural to urban-suburban. Because of this shift, we now find it necessary to expand our studies beyond those initially envisioned. The expanded studies will cover the areas of alternatives and economics, in addition to the natural environment. A scheduled date for resuming construction on the project has not been set. Local cooperation. For details see pages 11-24 and 25, Annual Report for FY 80. Operations and results during fiscal year. New work by hired labor forces consisted of preparation of plans and specifications, for design deficiency, and engineering studies. Condition as of Sep. 30. Construction was initiated in October 1974 and is 17 percent complete. 14. BAYOU BODCAU RESERVOIR, LA Location. In Red River Basin on Bayou Bodcau in Bossier Parish, LA, 72 miles above mouth of Loggy Bayou and 35 miles northeast of Shreveport, LA. (Refer to Geological Survey State map, scale 1:500,000.) Existing project. An earthfill dam rising 76 feet above streambed with a reservoir providing a flood damage prevention storage capacity of 357,000 acrefeet. Outlet works are in south abutment, and an uncontrolled spillway is on north abutment. Reservoir controls 656 square miles, or 53 percent, of entire drainage area of Bayou Bodcau. Construction of a floodway for diversion of Bayou Bodcau and Cypress Bayou to improve flood protection was authorized by 1936 Flood Damage Prevention Act. This authorization was modified by 1938 Flood Control Act, which authorized construction of a reservoir and other flood damage prevention works in lieu of construction of a floodway for diversion of Bayou Bodcau and Cypress Bayou, LA to improve protection, and further modified 12-6 VICKSBURG, MS, DISTRICT by War Department Civil Appropriation Act of 1939 which provided that reservoir and other flood control works on Bayou Bodcau and Cypress Bayou, LA, authorized by Flood Control Act of 1938 shall be constructed in accordance with revised plans and cost estimates in Office, Chief of Engineers. New work was completed in 1961. Local cooperation. None required. Operations and results during fiscal year. Hired labor forces continued operation and ordinary maintenance of the dam and reservoir, real estate activities, stream gaging, surveys and economic studies. Maximum pool elevation was 172.4 feet NGVD on Apr. 5-7, 1985, when storage in the flood control pool was 37,154 acre-feet. On September 30, 1985, the pool elevation was 158.3 feet NGVD, and storage in the flood control pool was 278 acre-feet. Condition as of Sep. 30. Construction was initiated April 1947 and completed April 1961. 15. BAYOU PIERRE, LA Location. In Red River Basin below Shreveport, LA, along channel of Bayou Pierre from its mouth at Grand Ecore, LA, upstream 30 miles to its confluence with Bayou Wincy. (Refer to Geological Survey State map, scale 1:500,000.) Existing project. Provides for widening channel at intervals, totaling 12.9 miles and snagging of 29.7 miles, to reduce flood damage and improve sanitary and living conditions over a wide area. Cost of new work, completed in 1939, was $229,529. Local cooperation. Fully complied with. Operations and results during fiscal year. Hired labor forces continued willow control and drift removal activities as required. Condition as of Sep. 30. Construction was initiated in FY 38 and completed in FY 39. 16. BLAKELY MOUNTAIN DAM-LAKE OUACHITA, OUACHITA RIVER, AR Location. This project is on Ouachita River, AR, at head of Lake Hamilton (pool of Carpenter Dam), 486 miles above mouth of Black River, and approximately 10 miles northwest of Hot Springs, AR. Previous project. See page 693 of Annual Report for 1962 for details. Existing project. A lake of 2,768,500 acre-feet storage capacity for flood control and other purposes with an installed power capacity of 75,000 kilowatts. Latest approved (1983) estimated project cost is $44,100,000. Local cooperation. None required. Operations and results during fiscal year. Power production totaled 155,907,000 kilowatt-hours of which 154,082,000 kilowatt-hours were delivered to Arkansas Power and Light Co., under contract between that company and Southwestern Power Administration. The maximum pool elevation of 580.0 feet above NGVD, or 2.4 feet above the maximum power pool, occurred on Apr. 1, 1985. Storage in the flood control pool at this time amounted to 49,300 acre-feet. Peak 24-hour inflow of 30,090 cubic feet per second occurred on Mar. 31, 1985. On Sep. 30, 1984, the pool elevation was 568.76 feet NGVD and storage in the power pool was 909,800 acre-feet. Condition as of Sep. 30. Project was started in August 1947 and was completed for beneficial use in October 1955, except for public-use facilities. Remote control equipment has been installed and is operating the power plants at DeGray Lake and Narrows Dam- Lake Greeson. Power generation, operation, and maintenance activities are continuing. 17. CADDO LAKE DAM, LA Location. In Caddo Parish, about 19 miles northwest of Shreveport, LA, at the eastern end of Caddo Lake and at head of Twelve Mile Bayou. Existing project. Replacement of the original dam was completed in June 1971, having same flow characteristics and located as near as practicable downstream of the old dam, built under navigation project "Cypress Bayou and Waterway between Jefferson, TX, and Shreveport, LA." New dam is capable of being raised in the future if desirable and justified. Estimated cost of new work (October 1976) was $3,587,800 Federal and $28,000 non-Federal. Local cooperation. Fully complied with. Public law 94-587, Section 174, amended the Flood Control Act of 1965 (Public Law 89-298) to provide that operation and maintenance of Caddo Lake Dam be the responsibility of the Secretary of the Army, acting through the Chief of Engineers. Conveyance of title to the United States from the Caddo Levee District is being reviewed. Operations and results during fiscal year. Maintenance by hired labor consisted of condition and operation studies, stream gaging, and water quality studies. Maximum pool elevation was 171.0 feet NGVD on Mar. 4-5, 1985, when storage in the flood control pool was 0 acre-foot. On Sep. 30, 1985, the pool elevation was 168.1 feet NGVD and storage in flood control pool was 0 acre-foot. A feasibility study investigating enlarging the lake for M&I water supply is currently under way. A report is scheduled to be submitted to LMVD in Nov. 1985. 18. DEGRAY LAKE, CADDO RIVER, AR Location. On Caddo River (mile 8), a tributary of Ouachita River, in a narrow, rocky gorge in Clark and Hot Springs Counties, approximately 7 miles north of Arkadelphia, AR. 12-7 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Existing project. Provides for a lake of 881,900 acre-feet storage capacity for flood control, water supply, pollution abatement, and power with an installed power capacity of 68,000 kilowatts (one conventional 40,000-kilowatt generating unit and one 28,000-kilowatt generating unit with reversible pumptype turbine). Latest approved (1980) estimated first cost is $72,034,000, including $5,800,000 for water supply, to be reimbursed by local interests, exclusive of interest. Local cooperation. None required for flood control and power features. Fully complied with for water supply feature. Operations and results during fiscal year. Power production totaled 82,420,000 kilowatt-hours, of which 81,175,000 kilowatt-hours was delivered to Arkansas Power and Light Co., under contract between that company and Southwestern Power Administration. The maximum pool elevation of 410.69 feet NGVD, or 2.7 feet above the maximum power pool, occurred on Feb. 25, 1985. Storage in the flood control pool at this time amounted to 36,900 acre-feet. Peak 24-hour inflow of 15,264 cubic feet per second occurred on Feb. 23, 1985. On Sep. 30, 1985, the pool elevation was 400.72 feet NGVD and storage in the power pool was 562,800 acre-feet. Condition as of Sep. 30. Construction started in June 1962 and was essentially complete in December 1971. All major construction is complete including the remote control for the power plant from Blakely Mt. Dam-Lake Ouachita. Power generation, operation, and maintenance are continuing. 19. LEAD BAYOU, MS Location. Lead Bayou is a tributary of the Sunflower River in Bolivar and Sunflower Counties, MS, approximately 30 miles from the Mississippi River near Cleveland, MS. Existing project. The plan of improvement calls for enlarging the existing Lead Bayou channel to provide a 1.5-year degree of protection to agricultural areas and a 10-year degree of protection to the small developed area near Cleveland, MS. Total estimated Federal cost is $1,526,000. Local cooperation. Fully complied with. Condition as of Sep. 30. The construction contract was completed Sep. 14, 1983. The stabilization of (1) bridge remains and will be accomplished under separate contract. 20. NARROWS DAM-LAKE GREESON, LITTLE MISSOURI RIVER, AR Location. Narrows Dam is on the Little Missouri River, AR, 105 miles above the mouth and 5 miles northwest of Murfreesboro, AR. Existing project. Provides a lake of 407,900 acrefeet storage capacity for flood control and other purposes with power installation of 25,500 kilowatts in three units of 8,500 kilowatts each. Latest approved (1983) estimated cost is $20,900,000, excluding $1,738,700 for third generating unit and remote control equipment. Local cooperation. None required. Operations and results during fiscal year. Power production totaled 31,759,540 kilowatt-hours, of which 31,046,110 kilowatt-hours was delivered to Texas- Louisiana Electric Cooperative, Inc., under contract between that company and Southwestern Power Administration. The maximum pool elevation of 550.6 feet NGVD, or 2.6 feet above the maximum power pool, occurred on Apr. 29, 1985. Storage in the flood control pool at this time amounted to 0 foot. Peak 24-hour inflow of 10,640 cubic feet per second occurred on Feb. 23, 1985. On Sep. 30, 1985, the pool elevation was 534.37 feet NGVD and storage in the power pool was 116,300 acre-feet. Condition as of Sep. 30. Project was started in May 1947 and was completed for beneficial use in May 1950. The third power generating unit was completed in January 1970. Installation of remote control equipment was completed in June 1972. Power generation, operation, and maintenance are continuing. 21. OUACHITA RIVER LEVEES, LA Location. East bank of Ouachita River between Bastrop, LA, and Sandy Bayou. Loop levees on the west bank at West Monroe, Columbia, and Bawcomville. Existing project. There are 105.8 miles of levee on the east bank and 11.6 miles of levee in the three loops on the west bank. A letter report, approved by the Chief of Engineers, authorized gravel surfacing 40.3 miles of levee, enlargement of 40.4 miles of levee, and a 5.7-mile southward extension of the east bank levee. Approved (1979) estimated Federal cost is $9,400,000. Estimated non-Federal cost is $25,000. Local cooperation. Requirements and assurances of local cooperation are fully described on page 12-6 of FY 80 Annual Report. Condition as of Sep. 30. Item I of the Monroe to Sandy Bayou Levee enlargement project was completed July 7, 1978. Additional work was deferred pending results of a comprehensive study of the entire Ouachita Levee System. Initial indications show that it is economically feasible to raise portions of the existing levee to authorized grade and that complete rehabilitation of the levee system is necessary. 22. OUACHITA RIVER AND TRIBUTARIES, AR AND LA Location. Improvements comprising comprehensive projects are on main stem Ouachita River, AR and LA, 12-8 VICKSBURG, MS, DISTRICT on its tributaries, Caddo and Little Missouri Rivers, and in Pine Bluff, AR. Description of Ouachita River Basin is presented in greater detail on page 690 of Annual Report for 1962. Existing project. The authorized general plan for flood control and other purposes in the Ouachita River Basin includes the projects listed in Table 12-F. The 1966 Flood Control Act modified the Bayou Bartholomew and Tributaries, AR and LA, project to include ten water-retention lakes in the western tributaries of Bayou Bartholomew in Arkansas and six local levee units along the main stem of the bayou in Louisiana. Local cooperation. Fully complied with for completed features of comprehensive project. (See individual statements for further details.) Operations and results during fiscal year. Operations for Blakely Mt. Dam-Lake Ouachita, DeGray Lake, Narrows Dam-Lake Greeson, Bayou Bartholomew and Tributaries, Monroe Floodwall, and Ouachita River Levees are shown in individual reports herein. Condition as of Sep. 30. Pertinent data on those features which are complete or not started are in Table 12-F. Conditions of Blakely Mt. Dam-Lake Ouachita, DeGray Lake, and Narrows Dam-Lake Greeson are given in the individual reports. An overall basin study including interim studies of the Monroe-West Monroe area, the Ouachita River Levees, the Arkansas Lakes is ongoing. 23. PEARL RIVER BASIN, MS AND LA Location. Jackson, MS, is located in Hinds County along the west bank of the Pearl River in central Mississippi. Communities adjacent to Jackson (i.e., Pearl, Flowood, and Richland) are located in Rankin County along the east bank of the Pearl River. Existing projects. The Jackson-East Jackson Flood Control Project provides for improvements of the Pearl River at Jackson, MS. This project includes two levee systems totaling 13.1 miles in length, with two pumping stations, four gated outlets, and 5.34 miles of channel rectification including three cutoffs with a total length of 2.2 miles in the Pearl River. This project was authorized by the Flood Control Act of July 14, 1960. Construction began in July 1964 and work was completed in FY 68. Total Federal cost of the project was $7,190,200. Public Law 98-63, dated July 29, 1983, authorized design and construction of additional measures to prevent recurring flood damages along the Pearl River at Jackson. Under this authority clearing approximately 3.3 miles of floodway, and enlarging the opening at the Highway 25 Bridge is essentially complete. A construction contract on the clearing work was awarded in August 1984 and was basically to be completed in FY 85. One bridge is to be stabilized by separate contract in FY 86. Improvements at the Highway 25 Bridge were made by the local sponsor in 1982, and the Corps has reimbursed the local sponsors to cover the Federal cost of this project. Also included in the authorized improvements in the Jackson area is the extension of the west bank levee at Fortification Street under the Jackson-East Jackson Flood Control Project. The Fortification Street Levee Extension was initiated and completed in FY 84 under the Jobs Bill Authority. Authorized projects. Public Law 99-88, dated Aug. 15, 1985, authorized planning, design, engineering, and construction of a levee system in Slidell, LA, pending binding cost-sharing agreements. Acceptable to the Secretary of the Army or under terms and conditions provided in subsequent legislation when enacted into law. Local cooperation. Requirements are provided as prescribed in Section 3 of the Flood Control Act of 1936, as amended. Section 3 of that Act stipulates easements, and rights-of-way necessary for construction of the project; hold and save the United States free from damages due to the construction works; and maintain and operate all works after completion in accordance with regulations prescribed by the Secretary of the Army. The local sponsors for these projects are as follows: - Jackson-East Jackson Flood Control Project including the Fortification Street Levee Extension - Rankin-Hinds Pearl River Flood Control Drainage District - Vicinity of Jackson including Clearing the Floodway and Highway 25 Bridge - Pearl River Basin Development District- Slidell, LA Flood Control Project- St. Tamany Parish Gravity Drainage District #3. Condition as of Sep. 30. Construction has been completed on the Jackson-East Jackson Flood Control Project and the Highway 25 Bridge improvements. A construction contract was awarded in Aug. 1984 for the 3.3-mile clearing of the Pearl River floodway in Jackson, MS. This work was completed on Jan. 17, 1985. Mitigation lands for the clearing were purchased by the local sponsor in May 1985 and the Corps has reimbursed the local sponsor to cover the Federal costs of these lands. Total Federal cost including mitigation was approximately 1.8 million. 24. PORTER BAYOU, MS Location. Porter Bayou is located in Bolivar and Sunflower Counties, MS. It lies approximately 25 miles east of the Mississippi River, is approximately 5 miles south of Cleveland, MS, and travels through the town of Shaw, MS. Existing project. The plan of improvement calls for selective snagging and clearing of Porter Bayou from mile 12.5 to mile 32.3. This plan provides a 0.5-year frequency protection for the Porter Bayou area. All construction is being performed from one side of the 12-9 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 stream, leaving the other side undisturbed. The total estimated Federal cost of the project is $1,214,000. Local cooperation. Fully complied with. Condition as of Sep. 30. The construction contract was completed November 16, 1983. A separate contract is to be let to biologically remove alligatorweed at Shaw, Mississippi. 25. POVERTY POINT, LA Location. The project area is located on the west bank of Bayou Macon approximately 4.5 miles northeast of Epps, LA, in West Carroll Parish and is referred to as Poverty Point on Bayou Macon. Existing project. The project provides for erosion protection to prevent bank failure along a 340 foot length of the west bank of Bayou Macon adjacent to Poverty Point Museum. The project involved bank grading, construction of a stone toe and stone tiebacks, sand fill covered by engineer fabric and stone paving over the length of the project. Top of the stone paving is approximately the 100-year flood elevation on Bayou Macon. Local cooperation. The Department of Culture, Recreation, and Tourism, State of Louisiana, Office of State Parks, by Agreement dated Mar. 26, 1985, furnished assurances that they would: provide without cost to the United States all lands, easements, and rights-of-way necessary for the construction and maintenance for the project; provide without cost to the United States all necessary relocations and alterations of utilities, highways, and highway bridges, sewers, related and special facilities; hold and save the United States free from all damages due to construction, operation, and maintenance of the project, and, if applicable, adjust all claims concerning water rights, except due to the fault or negligence of the United States or its contractors; maintain, including major replacements, and operate without cost to the United States, the completed works in accordance with regulations prescribed by the Secretary of the Army; prevent future encroachment which might interfere with the proper functioning of the project; make a cash contribution to cover all costs in excess of the $250,000 Federal cost limitation; comply with the applicable provisions of the "Uniform Relocation Assistance and Land Acquisition Policies Act of 1970" (Public Law 91-646, Stat. 1894); comply with the provisions of Section 221 of the Flood Control Act of 1970, Public Law 91-611. Acceptance by United States. The Agreement of assurances was accepted by the U.S. Army Engineer District, Vicksburg, Vicksburg, Mississippi, by letter dated Apr. 12, 1985. Condition of project. Work on this project was initiated Aug. 5, 1985, and was completed Oct. 4, 1985. 26. RED RIVER BELOW DENISON DAM (VICKSBURG DISTRICT) Location. On Red River and its tributaries below Denison Dam, in Oklahoma, Arkansas, Texas, and Louisiana. (Refer to Geological Survey State maps and folio "Maps of Red River"-1958 edition.) Existing project. Flood Control Act of 1946 approved general plan for flood control on Red River below Denison Dam, TX and OK, which provides for construction of six flood control reservoirs in combination with existing or authorized Federal and non-Federal levee improvements, modified as required, and channel stabilization at locations where levee setbacks are impossible or uneconomical. This act further authorized incorporation of several separate existing projects for flood damage prevention along Red River below Denison, above jurisdiction of the MRC, into this project. By Public Law 780, 83d Cong., 2d sess., as amended by Public Law 218, 84th Cong., 1st sess., and Public Law 645, 86th Cong., 1st sess., plan of improvement was amended to include additional projects as indicated in following lists of reservoirs and local protection works considered in general flood control plan for the Red River below Denison Dam, and existing flood control projects incorporated into project in Vicksburg District. (See Table 12-H for new projects and Table 12-I for incorporated projects.) Local cooperation. See individual reports herein. 27. RED RIVER BELOW DENISON DAM, LEVEES AND BANK STABILIZATION (VICKSBURG DISTRICT) Location. Along the main stem of the Red River from the head of the levee system immediately above Index, Ar, through the southwest corner of Arkansas to the vicinity of Boyce, LA, on the right bank, and Pineville, LA, on the left bank. Existing project. Raising and strengthening existing and authorized Red River levees to provide protection against flooding and bank protection works at locations where levee setbacks are impossible or uneconomical. The plan consists of raising and strengthening existing and authorized Red River levees to provide against a flood approximately 20 percent greater than the flood of 1945, the flood of record, as modified by authorized reservoirs. Bank protection works are to be constructed at locations where levee setbacks are impossible or uneconomical. Estimated cost for new work (October 1984) is $59,650,000 Federal and $1,560,000 non-Federal. Local cooperation. Requirements of local cooperation are fully described on page 12-10 of FY 1984 Annual Report. Operations and results during fiscal year. Hired labor forces continued investigations, surveys, and preparation of plans and specifications. The Belcher 12-10 VICKSBURG, MS, DISTRICT realignment, river miles 209-307, was initiated and the Gahagos revetment, mile 225-L was initiated. Condition as of Sep. 30. Construction was initiated in February 1948 and the levees are complete and bank stabilization is 95 percent complete. 28. RED RIVER WATERWAY SHREVEPORT, LA, TO INDEX, LA Location. In northwest Louisiana, southwest Arkansas, and northeast Texas, along the Red River between Shreveport, LA, and Index, AR. Existing project. To provide for realigning the channels of Red River from Shreveport, LA, to the levee system near Index, AR, by means of dredging, cutoffs, and training works and for stabilizing its banks by means of revetments, dikes, and other methods. Facilities to provide opportunities for recreation and for fish and "wildlife development are an integral part of the project. Estimated cost for new work (October 1985) is $193,062,000 Federal and $27,500,000 non-Federal. Local cooperation. Requirements and assurances of local cooperation are fully described on pages 12-10 and 12-11 of Fiscal Year 1984 Annual Report. Operations and results during fiscal year. Advanced engineering and design work was accomplished by hired labor forces. Condition as of Sep. 30. Construction has not been initiated. Completion of a General Re-evaluation Study will be required prior to construction of the project. The engineering and economic feasibility of constructing the authorized project must be reviewed in light of changed conditions within the project area. The Re-evaluation studies are inactive at this time, as a result of a lack of FY 86 funding. 29. WALLACE LAKE, LA Location. In Red River Basin on Cypress Bayou, Caddo and DeSoto Parishes, LA, 66 miles above mouth of Bayou Pierre and about 14 miles southeast of Shreveport, LA. (Refer to Geological Survey map, scale 1:500,000.) Existing project. An earthfill dam 4,940 feet long at top, including 644 feet of spillway and outlet works, rising 48 feet above streambed, with a reservoir providing storage of 96,100 acre-feet, including a conservation pool of 7,800-acre feet. Outlet works and uncontrolled spillway are centered about 1,250 feet north of south abutment. Reservoir controls 260 square miles, or about 20 percent of total drainage area of Bayou Pierre, Cypress Bayou, and tributaries combined, and affords protection against floods for an area of about 90,000 acers of valley below dam. Cost for new work completed in 1946 was $1,219,371, including $17,164 for Code 711. Local cooperation. Fully complied with. For details see page 1024, Annual Report FY 1946. Operations and results during fiscal year. Hired labor work consisted of condition and operation studies, stream gaging, and.operation and maintenance of the dam as required. Maximum pool elevation in the lake was 146.4 feet NGVD on Feb. 13, 1985, when storage in the flood control pool was 21,794 acre feet. On Sep. 30, 1985, the pool elevation was 141.00 feet NGVD and storage in the flood control pool was 0 acre-feet. Condition as of Sep. 30. All construction work on project was completed in December 1946. Main portion of dam was constructed during Fiscal Year 1943; stabilization of railroad embankment was accomplished from June to November 1946; and placing of fill in closure section of dam was accomplished from November to December 1946. Recreational facilities at the lake were closed in May 1972. 30. INSPECTION OF COMPLETED FLOOD CONTROL PROJECTS Inspection of completed work was accomplished at a cost of $195,781 for the fiscal year. Total cost as of Sep. 30, 1985, is $1,642,561. 31. FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION Emergency flood control activities-repair, flood fighting, and rescue work. (Public Law 99, 84th Cong., and antecedent legislation.) Disaster preparedness, FY costs for the period were $174,121. Rehabilitation, total expenditures during FY 85 amounted to $171,992 which included work on the Red River below Denison Dam. Advance measures, total expenditures in FY 85 amounted to $573,228 which included work on the following: Ouachita River & Levees, $540,648; and Red River below Denison Dam, $32,580. Total Public Law 99 costs through Sep. 30, 1985, were $919,341. Snagging and clearing of navigable streams and tributaries in the interest of flood control (Sec. 208 of 1954 Flood Control Act, Public Law 780, 83d Cong.). No activity during the period. Emergency bank protection (Sec. 14 of 1956 Flood Control Act, Public Law 780, 83d Cong.). Total FY 85 costs for emergency bank protection work was $3,961. This consisted of studies performed at St. Regis and Ouachita River for bank stabilization purposes at a cost of $2,300 and $1,661, respectively. Flood control activities pursuant to Sec. 205, 12-11 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Public Law 858, 80th Cong., as amended (preauthorization). During FY 1985, initial appraisal studies were completed on Batupan Bogue, Grenada, MS, at a cost of $7,500; Piney Creek, Pine Bluff, AR, at a cost of $7,500; Delhi, LA, at a cost of $3,200; Felsenthall, AK, at a cost of $4,500; and Jackson Caney Creek, MS, at a cost of $7,500. Detailed studies on Canal 43, Desha and Lincoln Counties, AR, at a cost of $66,023; and Bayou Natchitoches, LA, at a cost of $36,480. Reconnaissance studies on Calion Lake, Union County, AR, at a cost of $649; Pearl-Flowood, Pearl, MS, at a cost of $169,090; and By-Way Ditch, Montgomery Co., MS, at a cost of $100,616. 12-12 VICKSBURG, MS, DISTRICT TABLE 12-A COST AND FINANCIAL STATEMENT See Section Total Funds to in Text Project Funding FY 82 FY 83 FY 84 FY 85 Sep. 30, 1985 1. Claiborne County Port, MS 2. Lake Providence Harbor, LA 3. Madison Parish Port, LA 4. Ouachita and Black Rivers below Camden, AR (6.5-foot navigation project) Ouachita and Black Rivers below Camden, AR (9-foot navigation project) 5. Overton-Red River Waterway, LA 6. Pearl River, MS 7. Red River Emergency Bank Protection (Contrib. Funds) 8. Red River Waterway Mississippi River to Shreveport, LA (Contrib. Funds) 9. Rosedale Harbor, MS New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost New Work Approp. Cost. Approp. Cost New Work Approp. Cost Maint Approp. Cost New Work Approp. Cost New Work Contrib. Cost New Work Approp. Cost Maint. Approp. Cost New Work Contrib. Cost New Work Approp. Cost Maint. Approp. Cost $ 480,000 $ 1,305,000 32,297 1,717,787 160,000 252,518 -111,000 -10,579 -29,000 -129,000 66,247 44,500 18,211,000 13,939,425 Maint. 2,849,000 3,211,608 -350.500 161,000 182,196 $ 0 34,870 50,000 50,000 86,000 105,800 $ $ 2,000,000 2,000,000 50,000 50,000 291,000 291,113 208,5371 208,5371 1,997,500 1,997,504 656,000 655,999 408,000 407,224 66,000 69,600 20,406,000 12,700,000 13,638,600 14,599,659 4,232,756 4,486,300 4,035,654 4,962,300 4,000,000 8,662,235 4,962,000 4,855,884 00 587,000 209,676 38,400 414,600 325,000 301,982 - 3,362,000 5,630,000 7,000,000 - 2,942,895 3,779,352 5,878,490 - 60,736,000 91,313,000 - 58,456,160 91,266,477 545,000 510,042 164,273 103,139 97,000 101,815 78,000 212,185 -122,000 169,900 142,171 186,237 133,400 183,800 87,090,000 81,574,966 1,892,000 1,537,703 1,602,515 861,437 300,000 333,087 5,248,6192 5,248,6192 210,524,000 205,176,741 65,763,467 65,569,564 0 -350,500s 1,111,4003 1,058,423 15,992,0006 12,600,737 6,825 6,825 239,139,0007 231,297,603' 2,315,0007 2,217,645' 2,392,4207 1,634,274' 2,000,000 2,000,000 1,395,500 1,395,249 12-13 TABLE 12-A (CONTINUED) REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 COST AND FINANCIAL STATEMENT See Section Total Funds to in Text Project Funding FY 82 FY 83 FY 84 FY 85 Sep. 30, 1985 10. Yazoo River, MS New Work Approp. Cost Maint. Approp. Cost 3,900,000 4,000,402 50,000 26,624 916,000 465,295 48,000 7,700 80,000 80,927 -66,000 10,000 64,744 12. Bayou Bartholomew New Work and Tributaries Approp. AK and LA Cost 13. Bayou Bodcau and Tributaries, AR and LA 14. Bayou Bodcau Reservoir, LA 15. Bayou Pierre, LA New Work Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost 16. Blakely Mt. Dam- New Work Lake Ouachita, Oua- Approp. chita River, AK Cost Maint. Approp. Cost Code 713 Funds New Work Approp. Cost 489,000 982 400,000 331,125 265,000 445,448 9,679,661 9,267,044 1,128,315 1,128,102 974,000 974,000 1,154,0007 777,5557 00 231,000 11,815 19,400 13,434 870,000 890,722 2,958,000 3,188,349 652,300 404,300 30,000 14,257 105,484 3,309,000 3,290,852 470 1,798 217,300 653,100 -5,300 367 -5,500 147 2,969,100 3,068,800 29,000 404,000 413,910 -8,000 7,150 -754 3,531,000 3,399,347 20,210 1,504,6007 1,483,1257 00 36,1007 35,2417 34,039,444 34,023,108 40,490,192 40,320,820 474,095 494,256 17. Caddo Lake LA 18. DeGray Lake Caddo River, AR 19. Lead Bayou, MS 20. Narrows Dam-Lake Greeson, Little Missouri River, AK Code 713 Funds New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost 321,800 56,955 2,254,000 2,351,889 1,000,000 436,009 625,000 579,042 1,660,000 1,986,615 132,200 231,437 -144,400 48,200 177,000 187,221 - - -_ 12,611 - - 2,608,000 2,597,500 2,873,000 2,457,043 2,783,500 2,847,595 358,000 685,325 147,786 2,433,700 2,284,608 -470 15,000 162,003 -12,000 193 2,055,200 2,205,600 -9,000 200,000 234,820 10 2,302,000 2,279,532 12-14 00 486,600 466,858 72,033,992 72,033,992 25,551,183 25,454,599 1,945,685 1,750,436 16,545,229 16,516,689 29,014,637 28,942,578 331,505 308,088 VICKSBURG, MS, DISTRICT TABLE 12-A (CONTINUED) COST AND FINANCIAL STATEMENT See Section Total Funds to in Text Project Funding FY 82 FY 83 FY 84 FY 85 Sep. 30, 1985 21. Ouachita River New Work Levees, LA Approp. 54,000 -6,000 - - 2,682,000 Cost - 48,000 - - 2,682,000 23. Pearl River New Work Vicinity of Approp. - - 710,000 1,195,000 1,905,000 Jackson Cost - - 43,737 1,820,453 1,864,190 Jackson-East New Work Jackson Approp. - - 350,000 -60,000 290,000 Cost - - 290,515 -515 290,000 24. Porter Bayou, New Work MS Approp. 355,000 500,000 -15,000 - 1,035,278 Cost 52,273 506,187 270,363 5,391 1,029,257 25. Poverty Point New Work State Commemora- .Approp. - - 47,500 202,500 250,000 tive Area, LA Cost - - 47,500 207,500 250,000 27. Red River below New Work Denison Dam, Approp. 110,700 550,000 1,600,000 1,000,000 8,260,7007 Levees and Bank Cost - 1,505,639 1,356,651 1,871,520 4,733,810' 28. Red River Water- New Work way, Shreveport, Approp. - - 90,000 50,000 140,0007 LA, to Index, AR Cost - 4,335 88,730 48,736 141,8017 29. Wallace Lake, LA New Work Approp. - - - -0' Cost - - - 0' Maint. Approp. 22,200 142,300 -64,200 45,000 145,300' Cost - 44,113 46,600 39,470 130,1837 1. Actual costs include $198,859 Public Works Acceleration Act funds and $9,678 expended for planning and design; excludes $35,000 contributed funds, $198,400 cost of retaining dikes, and $1,022,000 local interests' cost for port facilities. 2. Includes $674,068 for new work on previous projects. 3. Excludes $21,884 carryover from Mobile District. 4. Includes $359,661 for previous projects. Present appropriations include funds for Advance Participation on Belzoni Bridge. 5. $350,500 cost credit from Memphis on New Orleans District expenditures. 6. Includes $3,312,000 PL 98-8 Jobs Bill. Excludes $47,828,000 previously allocated to New Orleans District. 7. Excludes New Orleans District allocation and cost. 12-15 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 12-B AUTHORIZING LEGISLATION Acts Work Authorized Documents Jul. 14, 1960, as amended Jul. 14, 1960, as amended Jul. 14, 1960, as amended May 17, 1950 Jul. 14, 1960 Dec. 31, 1970 Jul. 24, 1946 May 17, 1950 Aug. 13, 1968 June 14, 1880 Apr. 21, 1900 Aug. 30, 1935 Nov. 7, 1966 Aug. 13, 1968 Aug. 13, 1968 CLAIBORNE COUNTY PORT, MS (See Section 1 of Text) A dredged slack-water harbor 800 feet long and 150 feet wide with a 400 by 800 foot turning basin. LAKE PROVIDENCE HARBOR, LA (See Section 2 of Text) Dredging 0.7-mile channel and turning basin in an old chute of the Mississippi River, with the dredged material used to fill in a port area provided by local interests. MADISON PARISH PORT, LA (See Section 3 of Text) The project consists of constructing a navigation channel 150 feet wide and 1,000 feet long, transitioning into a 200-foot-wide channel 400 feet long with a 350- by 1,100-foot turning basin adjacent to the port area. Dredged material will be disposed into lands furnished by local interests. OUACHITA AND BLACK RIVERS BELOW CAMDEN, AR (See Section 4 of Text) Modification of existing project toprovide for 9-foot channel and deepening canal to Felsenthal, AR. Modification of 9-foot project to provide four new locks and dams and channel improvements. Migratory waterfowl refuges on Bayou D'Arbonne in connection with the pool of the Columbia Lock and Dam and in the pool of the Felsenthal Lock and Dam. OVERTON-RED RIVER WATERWAY, LA (See Sec. 5 of Text) Construct 9- by 100-foot channel for 206 miles from Mississippi River, mile 301 AHP, through Old and Red Rivers to mile 31, thence by lateral canal through land cuts and existing waterways across Mississippi-Red River backwater area along south bank of Red River floodplain to Shreveport, and construct nine locks and pumping plant on Red River near Shreveport. Extend Overton-Red River Waterway 9- by 100-foot channel from Mississippi River to north bank of Black River, mile 35.5. Provides for the navigation channel to be 200 feet wide. PEARL RIVER, MS AND LA (See Section 6 of Text) Provided for a 5-foot channel. Legalized construction of a fixed highway bridge at Rockport A channel from the mouth of West Pearl River for 58 miles to the mouth of Bogalusa Creek at Bogalusa, LA, 7 feet deep at low water with a bottom width of 100 feet in the river sections and 80 feet in the canal section; with locks 65 by 310 feet clear inside dimensions. Construction of cut-offs and easement of critical bends at eight locations below lock 1 with no increase in project depth. RED RIVER EMERGENCY BANK PROTECTION (See Sec. 7 of Text) Realining the banks by dredging cut-offs and training works and stabilizing banks by means of revetments and dikes. RED RIVER WATERWAY-MISSISSIPPI RIVER TO SHREVEPORT, LA (See Sec. 8 of Text) Develop a 9 by 200 feet, approximately 236 miles long from Mississippi River at junction of Old River via Old River and Red River to Shreveport, LA, consisting of realinement, bank stabilization, and construction five locks and dams. Approved Sep. 11, 1978, under authority of Sec. 107 of the River and Harbor Act of 1960, as amended Approved Sep. 12, 1962, under authority of Sec. 107 of the River and Harbor Act of 1960, as amended Approved Sep. 12, 1962, under authority of Sec. 107 of the River and Harbor Act of 1960, as amended S. Doc. 117, 81st Cong., 1st sess. S. Doc. 112, 86th Cong., 2d sess. Report of the Chief of Engineers dated Nov. 25, 1970, and H. Doc. 92-109, 92d Cong., 1st sess. H. Doc. 320, 80th Cong., 1st sess. S. Doc. 117, 81st Cong., 1st sess. H. Doc. 304, 90th Cong., 2d sess.' H. Doc. 98, 45th Cong., 3d Sess. H. Doc. 145, 65th Cong., 1st Sess. H. Doc. 408, 75th Cong., 2d sess. H. Doc. 482, 89th Cong., 2d sess. H. Doc. 304, 90th Cong., 2d sess. H. Doc. 304, 90th Cong., 2d sess. 12-16 VICKSBURG, MS, DISTRICT TABLE 12-B (Continued) AUTHORIZING LEGISLATION Acts Work Authorized Documents Jul. 14, 1960, as amended Mar. 3, 1875 Aug. 13, 1968 May 17, 1950 Nov. 7, 1966 Oct. 27, 1965 Jun. 28, 1938 Jun. 22, 1936 Dec. 22, 1944 Oct. 27, 1965 Jun. 30, 1948, as amended Aug. 18, 1941, as amended ROSEDALE HARBOR, MISS. (See Section 9 of Text) The harbor channel is 150 feet wide and 2.7 miles long with a turning basin 1,000 feet long and 400 feet wide. A minimum operating depth of 9 feet below the lowest water of record (102.5 feet, NGVD) was maintained in both the channel and turning basin and provided a 20-acre landfill to a net elevation of 162.9, NGVD. The landfill is 1,250 feet long and 700 feet wide. An access roadfill was constructed from Mississippi Highway 1 to the port site. YAZOO RIVER, MS (See Section 10 of Text) Removal of obstructions to navigation from mouth to Greenwood, MS, 189 miles. Nine-foot channel from mouth to Greenwood, mile 154.9 (present mileage), with a lock and dam near Vicksburg, channel improvements, alteration of bridges, additional storage space in Sardis Lake to augment low river flows, and recreation features. BAYOU BARTHOLOMEW, AR AND LA (See Section 12 of Text) Authorized channel improvements on Bayou and Tributaries (see above). Modified 1950 authorization to include 10 lakes in the west escarpment in Arkansas and 6 local levees in Louisiana, and acquisition of lands for mitigation of fish and wildlife losses. The previously authorized channel improvement was deferred until it is determined that the quality and quantity of water downstream will not be adversely affected. BAYOU BODCAU AND TRIBUTARIES, AR AND LA (See Sec. 13 of Text) Extend Cypress Bayou-Red Chute Bayou levee, construct stream closure landside drainage channel and three culverts on Red Chute Bayou, and clearing and snagging channel; extend Flat River-Loggy Bayou levee, close Flat River near junction with Cutoff Bayou, and construct control structures on Flat River near junction with Red Chute Bayou; and enlarge Flat River channel to 20 to 35 feet, a distance of 11.6 miles. BAYOU BODCAU RESERVOIR, LA (See Sec. 14 of Text) Provides for construction of a reservoir and other flood control works. BAYOU PIERRE, LA (See Sec. 15 of Text) Widening channel at intervals totaling 12.9 miles, and snagging of 29.7 miles. BLAKELY MOUNTAIN DAM-LAKE OUACHITA, OUACHITA RIVER, AR (See Sec. 16 of Text) Construction of an earth-fill dam and lake for combined power and flood contol. CADDO LAKE, LA (See Sec. 17 of Text) Maintenance Work. LEAD BAYOU, MS (See Section 19 of Text) Channel enlargement. NARROWS DAM-LAKE GREESON, LITTLE MISSOURI RIVER, AR (See Section 20 of Text) A concrete gravity type structure 941 feet long and 190 feet high which controls the flow from a 237 square mile drainage area - for flood control, hydroelectric power, fish and wildlife conservation and recreational purposes. Approved Sep. 12, 1962, under authority of Sec. 107 of the River and Harbor Act of 1960, as amended. H. Doc. 342, 90th Cong., 2d sess. S. Doc. 117, 81st Cong., 1st sess. H. Doc. 506, 89th Cong., 2d sess. H. Doc. 203, 89th Cong., 1st sess. H. Doc. 378, 74th Cong., 2d sess. H. Doc. 378, 74th Cong., 2d sess. H. Doc. 647, 78th Cong., 2d sess. S. Doc 39, 89th Cong., 1st sess. Sec. 205 of the Flood Control Act of 1948, as amended. Authorized by Chief of Engineers Jun. 10, 1980. H. Doc. 837, 76th Cong., 3d sess. 12-17 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 12-B (CONTINUED) AUTHORIZING LEGISLATION Acts Work Authorized Documents May 17, 1950 Jul. 14, 1960 Jun. 13, 1983 Jul. 29, 1983 Aug. 15, 1985 Jun. 30, 1948, as amended Jul. 24, 1946, as amended Jul. 24, 1946 Aug. 13, 1968 Aug. 13, 1968 Jun. 22, 1936 OUACHITA RIVER AND TRIBUTARIES, AR AND LA (See Section 22 of Text) Authorized DeGray Lake; Murfreesboro Lake; extension of floodwall at Monroe to partially close the existing gap; local protection at Bawcomville, LA (subsequently constructed under Sec. 6, Act of May 15, 1928, with local interests contributing one third of cost); Bayou Bartholomew channel improvement, including Deep Bayou and Overflow Creek; Pine Bluff local protection; local protection at Calion, AR; and incorporation, into the Ouachita River and Tributaries project, of all existing projects and portions thereof in the basin above the lower end of the levees on the east bank of the Ouachita River. In addition, the Chief of Engineers authorized on Nov. 14, 1966, additional work on the levees. PEARL RIVER MS, AND LA (See Section 23 of Text) Construction of levee system and channel rectification, Pearl River, vicinity of Jackson, MS Accomplish the clearing and channel improvements at Hwy 35 bridge on the Pearl River in the vicinity of Jackson, MS. Design and construct protection to prevent flooding along the Pearl River in the vicinity of Jackson, MS Planning, design, engineering and construction of a levee system for Slidell, LA, pending binding cost-sharing arrangements acceptable to the Secretary of the Army or under terms and conditions provided in subsequent legislation when enacted into law. PORTER BAYOU, MS (See Section 24 of Text) Selective snagging and clearing of Porter Bayou, MS from mile 12.5 to mile 32.3 POVERTY POINT STATE COMMEMORATIVE AREA, LA (See Section 25 of Text) Provides for erosion protection against bank failure along a 340 foot length of the west bank of Bayou Macon by means of grading, constructing tie backs, and stone paving. RED RIVER BELOW DENISON DAM LEVEES AND BANK STABILIZATION (VICKSBURG DIST.) (See Section 27 of Text) Levee and bank stabilization. Deauthorization of Morringsport Dam and Reservoir on Cypress Creek; realining and stabilizing the banks of the Red River; and recreational facilities from the Mississippi River to Denison Dam, OK and TX. RED RIVER WATERWAY-SHREVEPORT, LA, TO INDEX, AR (See Section 28 of Text) Provides for realinement of the channels of the Red River from Shreveport, LA, to Index, AR. WALLACE LAKE, LA (See Section 29 of Text) Construction of an earth-fill dam and a reservoir. S. Doc. 117, 81st Cong., 1st sess. H. Doc. 441, 86th Cong., 1st sess. S. Doc. 153, 98th Cong., 1st sess. Public Law 98-63, 98th Cong., 1st sess. Public Law 99-88, 99th Cong., 2nd sess. Sec. 205 of the Flood Control Act of 1948, as amended. Authorized by Chief of Engineers, Feb. 18, 1982. Public law 526, 79th Cong., 2d sess. H. Doc. 602, 79th Cong., 2d sess. H. Doc. 304, 90th Cong., 2d sess. H. Doc. 304, 90th Cong., 2d sess. H. Doc. 378, 74th Cong., 2d sess. 1. Portion of existing project above mile 31 was reclassified to inactive status as approved by Office, Chief of Engineers, letter dated Oct. 18, 1971. 12-18 TABLE 12-C OUACHITA AND BLACK RIVERS, AR AND LA (9-FOOT PROJECT), LOCKS AND DAMS (See Section 4 of Text) Min. Depth Greatest on Available Lower Miles Length Max. Elev. Miter Above Width for Full Lift Normal Sill at Miles Mouth of Width at Pool Normal Pre- Total from of Lock of Lock Low Surface Pool Character cent Estimated Nearest Black Chamber Chamber Water (feet Level or Kind of Type of Con- Project Location Town River (feet) (feet) (feet) msl) (feet) Foundation Dam Construction plete Cost Jonesville, LA 10 25 84 600 30 34 14 Piling Moving Tainter gated dam; 992 $ 51,700,000 bascule gated nagivation pass; steel mitering lock gates Columbia, LA 5 117 84 600 18 52 13 do do Tainter gated dam; 952 45,600,000 fixed crest navigation pass; steel mitering lock gates Felsenthal, AR 1 227 84 600 18 701 13 Earth do Tainter gated dam; 852 95,800,000 navigation pass with inflatable dam on crest; steel mitering lock gates. Calion, AR 7 283 84 600 12 77 13 do do Tainter gated dam; 852 75,900,000 hinged crest gated navigation pass; steel mitering lock gates. Estimated Federal Cost $269,000,000 Estimated Non-Federal Cost 10,150,000 Total Estimated Cost $279,150,000 1. Fish and wildlife impoundment level. Navigation pool elevation .65. 1!Z1 C,, 2. The percent complete reflects all work within the TABLE 12-D REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 LOCKS IN PEARL RIVER PROJECT (See Section 6 of Text) Lock Miles above mouth Nearest town Miles to nearest town Width of Chamber Greatest length available for full width (feet) Lift (feet) Depth over sills at low water (feet) Character of foundation Type of construction Year completed Date opened for navigation Actual cost of lock Pearl River Lock No. 1 29.7 Pearl River, LA 65 310 26.7 10 Sand, gravel, silt, clay Concrete and steel 1949 November 1958 $2,119,100 Pearl River Lock No. 2 40.8 Bush, LA 3 65 310 14 10 Sand, gravel, silt, clay Concrete and steel 1950 November 1958 $1,967,537 Pearl River Lock No. 3 44.0 Sun, LA 2 65 310 11 10 Sand, gravel, silt, clay Concrete and steel 1950 November 1958 $1,497,539 Note: The responsibility of maintaining this project was transferred to the Vicksburg District, Lower Mississippi Valley Division on Oct. 1, 1981. District boundaries have been changed. 12-20 VICKSBURG, MS, DISTRICT TABLE 12-E OTHER AUTHORIZED NAVIGATION PROJECTS Cost to Sep. 1985 For Last Full Report Operation See Annual and Mo. and Yr. Project Status Report For: Construction Maintenance Completed Bayou Bartholomew, LA and AR1' 2 3, 4 - 1931 $ 45,874 $ 42,857 1 Bayous D'Arbonne and Corney, LA1, 2, 4 - 1941 19,000 37,804 1 Big Black River, MS 1 4.5' - 1895 15,000 - 1 Big Sunflower River, MS1, 4'6, 7 - 1942 560,027 459,328 1 Boeuf River, LA 1 34, 7, 8 9- 1949 30,000 103,737 1 Cypress Bayou and Waterway between Jefferson, TX, and Shreveport, LA 5 Complete 1971 202,817 452,611 Dec. 1914 Homochitto River, MS 4 - 1910 15,482 8,518 1 Little Missouri River, AR1 4.5 - 1873 19,992 - Little River, LA 1, 4, 5,10 - 1890 1,500 - 1 Little Tallahatchie River, MS1"' - 1913 19,000 - Mouth of Yazoo River, MS 1,7,1 - 1953 1,179,211 217,266 1 Ouachita and Black Rivers, AR and LA, Felsenthal Canal - 193712 - - 1 Red River below Fulton, AR1, 16,17, 18 - 1978 1,963,806 2,147,890 1 Red River Waterway LA, AR, OK, and TX, '17, 18 - 1969 - - 1 Red River Waterway, Shreveport, LA to Daingerfield, TX' 1976 70,000 - 1 Removing snags and wrecks from - 1948 - 272,500 1 Mississippi River below mouth of MissouriRiver and from Old and Atchafalaya Rivers 1 Saline River, AR1 3' .4.5 - 1931 26,900 12,7921 Tallahatchie and Coldwater Rivers, MS 1, 3, 4 1939 43,481 173,066 Tensas River and Bayou Macon, LA" 8, 12 - 1949 38,367 85,3521 Yalobusha River, MS 1, 4'5, 14 - 1937 7,000 15,9361 1. Status and Date unavailable. 2. Abandonment recommended in H. Doc. 1962, 64th Cong., 2d sess., and H. Doc. 467, 69th Cong., 1st sess. 3. Channels adequate for existing commerce. 4. Inactive project. No commerce. 5. Abandonment recommended in H. Doc. 467, 69th Cong., 1st sess. 6. Project curtailment recommended by elimination of work between Pentecost and mouth of Hushpuckena River. (Abandonment of entire project erroneously recommended in H. Doc. 467, 69th cong., 1st sess.) 7. See report of Mississippi River Commission for operations in connection with Yazoo Basin. 8. Report of New Orleans District, pp. 919-920 for Fiscal Year 1949. 9. Project curtailment recommended by elimination of work above Girard, LA (Abandonment of entire project recommended erroneously in H. Doc. 467, 69th Cong., 1st sess.) 10. Due to decline of traffic, local interests not sufficiently interested to provide rights-of-way and dumping privileges. 11. No additional funds available under this project. Work is being carried on under appropriation flood control, Mississippi River and tributaries. 12. Year authorized. 13. Inactive. Channel adequate for commerce. 14. See report of Mississippi River Commission for operations in connection with Yazoo Basin flood 'control Grroejneacdt ai ncluding channel clearing and rectification and Lake on Yalobusha River. 15. Excludes $50,000 contributed funds. 16. Includes $1,553,878 for previous projects. 17. Incorporated in the project "Red River Waterway- Mississippi River Shreveport, LA" Sept. 30, 1976. 18. Emergency bank protection on this project is reported separately as "Red River Emergency Bank Protection." Two reaches, "Red River Waterway-Mississippi River to Shreveport, LA" and "Red River Waterway-Shreveport, LA, aingerfield, TX," are also reported separately. 12-21 TABLE 12-F REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 OUACHITA RIVER AND TRIBUTARIES: EXISTING PROJECT (See Section 23 of Text) For Last Estimated Full Report Federal See Annual New Work Project Report for: Cost Blakely Mt. Dam-Lake Ouachita, AR (1) $ 44,100,000 DeGray Lake, AR (1) 72,034,0002 Narrows Dam-Lake Greeson, AR (1) 20,900,000 Calion, AR 1960 970,9963 Columbia, LA 1941 204,7403 Existing levees and extensions thereto from Bastrop, LA, to mouth of Boeuf River and at West Monroe, LA 1961 3,025,1813 Little Missouri River below Murfreesboro, AR 1957 354,8023 Ozan Creek, AR 1957 57,7423 Terre Noire Creek, AR 1948 123,7003 Pine Bluff, AR, local protection 1954 172,5823 Monroe, LA, floodwall extension (Plan B) (1) 2,561,0003 Bayou Bartholomew and Tributaries, AR and LA (1) 44,800,000 Ouachita River Levees (additional work) (1) 9,400,000 Total $198,704,7434 1. See individual reports herein. 4. Excludes the authorized Murfreesboro Lake, AR, 2. Includes $5,800,000 for water supply, to be reimbursed project, which is inactive. The latest estimated cost (1954) by local interests, was $4,190,000. 3. Actual cost of completed project. TABLE 12-G RESERVOIR OPERATIONS FISCAL YEAR 1984 See Section Storage in Text Project (acre feet) Inflow1 Outflow 24. Bayou Bodcau2 Oct. 1, 1981 249 - - Reservoir, LA Sep. 30, 1982 310 - - Jul. 2, 1982 (Max) 11,340 - - Jun. 29, 1982 (Max) - 1,664 - Jul. 2, 1982 (Max) - - 1,125 36. Wallace Lake, LA Oct. 1, 1981 7,655 - - Sep. 30, 1982 7,319 - - Apr. 24, 1982 (Max) 11,739 - - Apr. 23, 1982 (Max) - 1,013 - Apr. 24, 1982 (Max) - - 634 1. Cubic feet per second. 12-22 VICKSBURG, MS, DISTRICT TABLE 12-H RED RIVER BELOW DENISON DAM (VICKSBURG DISTRICT): NEW PROJECTS (See Sec. 26 of Text) Drainage Conserva- Flood Area tion Control Estimated (square Storage (acre- Federal Project Stream miles) (acre-feet) feet) Cost Bayou Bodcau and tributaries, AR2 and LA - 1,158 - - $ 25,100,0003 Bayou Nicholas-Coushatta, LA - - - - 70,7174 Bayou Pierre in vicinity of Shreveport, LA5 - - - - 243,336 Caddo Lake, LA' Caddo Lake - - - 3,587,8002 Campti-Clarence Area in Natchitoches Parish, LA Red River - - - 1,950,0003 Garland City, AR1'" 6 - - - - 1,450,000 Maniece Bayou, AR - - - - 970,0323 McKinney Bayou, AR7' 8 - - - - 5,610,000 Posten Bayou, AR and LA2 ' 6, 9 - - - - 560,000 Red River below Denison Dam levees and bank stabilization, TX, AR, and LA' - - - - 59,650,0003 Total 99,191,885 1. Details presented in individual report herein. 2. Construction on this project not started. 3. In addition, non-Federal funds are: Bayou Bodcau and tributaries, AR and LA ...................................................... $5,300,000 Bayou Pierre in vicinity of Shreveport, LA (cash conitribution) ...................................... 89,047 Caddo Lake, LA ................................................................................ 28,000 Campti-Clarence Areain NatchitochesParish, LA ................... ......... ....... .............. 480,000 E ast Point .................................................................................... 67,000 Garland City, A rk ............................................................................. 6,000 Maniece Bayou, AR (cash contribution) ......................................................... 18,000 McKinney Bayou, AR (cash contribution) ....................................................... 508,000 Red River below Denison Dam, levees and bank stabilization, TX, AR, and LA ...................... 1,560,000 4. For last full report, see Annual Report for 1964. 5. For last full report, see Annual Report for 1951. 6. Inactive. 7. Includes $4,330,200, Code 711, and $399,739 accelerated Public Work funds. 8. Joint-use pool (sediment). 9. Deauthorized by resolution Dec. 17, 1970, which also authorized new project "Posten Bayou, AR," under provision of Sec. 201 of Flood Control Act of 1965. 12-23 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 12-I RED RIVER BELOW DENISON DAM (VICKSBURG DISTRICT): INCORPORATED PROJECTS (See Sec. 26 of Text) For Last Flood Estimated Full Report Control Federal See Annual Project Type of Work Act Cost Report For Aloha-Rigolette Area, Grant and Rapides Parishes, LA Levee and appurtenances 1941 $ 1,653,2371 1956 Bayou Bodcau Reservoir, LA2 Flood-control reservoir 1938 5,120,7401, 3 4 Bayou Bodcau, Red Chute, and Loggy Bayou, LA Channel improvement 1941 319,2001 1948 Bayou Pierre, LA Channel enlargement 1936 299,5291 4 Black Bayou Lake, LA5' 6 Flood-control reservoir 1936 714,000 1945 Colfax, Grant Parish, LA Cutoff 1938 70,3481 7 1938 Grant Parish, below Colfax, LA Levees 1938 38,8091 1941 Hempstead County levee district No. 1, AR Levee enlargement 1938 88,0061 1941 Natchitoches Parish, LA Levee and appurtenances 1936 1,529,9271 8 1956 Pineville, Red River, LA Levee and appurtenances 1941 232,4261 1953 Red River in vicinity of Shreveport, LA Bank protection 1944 3,908,0001 1953 Red River Parish, LA Levee enlargement 1936 149,4351 1939 Saline Point, LA Cutoff 1936 124,1111 1945 Wallace Lake, LA Flood-control reservoir 1936 1,219,3711, 3 4 Total $15,467,134 1. Actual cost. 2. Project transferred to Vicksburg District August, 1982. 3. Includes amounts indicated for recreational facilities under Code 711, Bayou Bodcau Reservoir, LA, $1,027,000; Wallace Lake, LA, $17,164. 4. Included in this report. 5. Work not started. 6. Inactive. 7. Completed under provisions of Sec. 7 of Flood Control Act of 1928, as amended by Sec. 9 of Flood Control Act of 1936, and included in .1939 Annual Report of President, Mississippi River Commission, p. 2214. 8. In addition, $25,000 was expended from contributed funds. 12-24 VICKSBURG, MS, DISTRICT TABLE 12-J OTHER AUTHORIZED FLOOD CONTROL PROJECTS For Last Cost to Sep. 1985 Mo. and Yr. Full Report Operation Mo. and Yr. If See Annual and If Project Deauthorized Report For: Construction Maintenance Completed Aloha-Rigolette Area, Grant and Rapides Parishes, LA'- Bayou Bodcau, Red Chute, and Loggy Bayou, LA' Bayou Pierre in vicinity of Shreveport, LA 2 - Big Black River, MS3 - Big Choctaw Bayou, LA3' 4 - Black Bayou Reservoir, LA1, 5,6 - Buffalo River, MS7 - Campti-Clarence Area in Natchitoches Parish, LAColfax, Grant Parishes, LA1 8 - East Point, LAGarland City, ARGrant Parish below Colfax, LA"3 - Hempstead County Levee District No. 1, AR1, 3 Homochitto River, MS3 - Maniece Bayou, AR" 2 - McKinney Bayou, Finn Bayou Segment, AR 9 Aug. 1977 Monroe Floodwall, LAMurfreesboro Dam and Lake4 - Natchez Port Area, MS3' - Natchitoches Parish, LA1, 2- Pineville, Red River, LA3' 34 - Posten Bayou, AR'0 - Red River Parish, LA1, 3 - Red River in vicinity of Shreveport, LA'- Saline Point, LA" 3 - Twelvemile Bayou, LA4 - 1. Authorized under project "Red River Below Denison Dam." 2. In addition, the following was expended from contributed funds: Amite River and tributaries ............ $ 430 Bayou Pierre in vicinity of Shreveport, LA ..................... 89,047 Choctaw Bayou and Tributaries, LA .... 170,799 Harvey Canal, Bayou Barataria Levee, LA ............................... 425,209 Maniece Bayou, AR .................... 39,293 Natchitoches Parish, LA ............... 250,000 3. Completion Date Unavailable. 1956 1948 1951 1956 1966 1945 1940 1978 1938 1969 1976 1941 1941 1956 1970 19639 1984 1951 1969 1956 1953 1973 1939 $ 1,653,189 319,200 243,3362 910,185 248,823 1,655,700 70,348 286,069 1,335,841 38,809 88,006 205,000 970,9322 2,560,000 538,000 1,529,478 232,426 149,435 Apr. 1955 Jan. 1948 Jun. 1939 670,750 144,650 Jul. 1978 Aug. 1968 Jul. 1974 3 3 3 Aug. 1969 5 Aug. 1955 Dec. 1951 3 1953 3,908,000 - Mar. 1953 1945 124,111 - - 1966 335,433 - May 1965 4. Authorized by Chief of Engineers under authority of Sec. 205, Flood Control Act of 1948, as amended. 5. Construction not initiated. 6. Inactive. 7. Deferred indefinitely because of insufficient justification under present conditions. 8. Completed under provisions of Sec. 7 Flood Control Act of 1928, as amended by Sec. 9, Flood Control Act 1936, and included in 1939 Annual Report of President, Mississippi River Commission, p. 2214. 9. Date authorized. 10. Posten Bayou Project, authorized by Senate and House Resolutions, Dec. 17 and 15, 1970, deleted the plan authorized by the Flood control Act dated Aug. 3, 1955. 12-25 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 12-K ACTIVE GENERAL INVESTIGATIONS (96x3121) Federal Cost Totals by Item and CWIS Number FY 85 Categories ($) ($) SURVEYS (Category 100) Flood Control Studies (120) Ouachita River Basin, AR & LA -12046 $ 548,164 Pearl River Basin, MS and LA -12234 1,073,495 Pine Bluff Metro, AR -12015 32,695 Subtotal 1,654,354 Comprehensive Studies (150) Red River Below Denison Dan (153) -81129 454,024 Miscellaneous Activities (170) Special Investigations (171) -17250 13,043 Review of FERC Licenses (172) -53857 21,728 Subtotal 34,711 Coordination Studies with Other Agencies (180) Department of Agriculture, Soil Conservation Service (181) -51840 4,834 Planning Assistance to States (186) -51850 1,896 Technical and Engineering Assistance on Shoreline and Streambank (188) -51731 0 Subtotal 6,730 TOTAL (Category 100) 2,149,879 COLLECTION AND STUDY OF BASIC DATA (Category 200) Inspection of Dams (230) 0 Inventory of Dams Flood Plain Management Services (250) Flood Plain Management Services 170,464 Hydrologic Studies (260) Hydrologic Studies (260) -53820 7,719 Subtotal 178,183 TOTAL (Category 200) 178,183 ADVANCE E&D (Category 600) Navigation Projects (620) Locks and Dams, Yazoo River, MS (622) 00083 64,744 Flood Control Projects (650) Local Protection, Red River Waterway, Shreveport to Index (651) -75023 48,736 Local Protection, Pearl River Vicinity of Jackson, MS (651) -75426 3,704 Subtotal 117,184 TOTAL (Category 600) 171,184 GRAND TOTAL GENERAL INVESTIGATIONS $2,445,246 12-26 MEMPHIS, TN, DISTRICT* This district comprises a portion of southeastern Missouri and southern Illinois, western portions of Kentucky and Tennessee, a small, portion of northern Mississippi, and the northeastern portion of Arkansas; includes area embraced in drainage basins of eastern tributaries of the Mississippi River south of Ohio River Basin to Nonconnah and Horn Lake Creeks, inclusive, and those of western tributaries south of Little River diversion channel and Commerce, MO, including St. Francis River Basin and White River and tributaries below Peach Orchard Bluff, AR, on the right bank and below Augusta, AR, on the left bank; also includes left bank Mississippi River levee from vicinity of Memphis south to about mile 620, and right bank levees from Cape Girardeau, MO, to about mile 605. IMPROVEMENTS Navigation 1. Navigation work under special authorization ......................... Page Flood Control (cont.) 9. Flood control work under special 13-1 authorization ........................ Flood Control Grays Creek Canal, Shelby Co, TN ..... Hatchie River, Alcorn Co, MS ......... Humboldt, TN ....................... Nonconnah Creek Interceptor Sewer, Memphis, TN ....................... Sandy Creek, Jackson, TN ........... St. Francis River-Highway No. 90, AR. Inspection of completed flood control projects ............................. Tables 13-1 Table 13-A 13-2 Table 13-B 13-2 Table 13-C 13-2 13-3 13-3 13-3 Table 13-D Table 13-E Cost & Financial Statement .... Authorizing Legislation ....... Other Authorized Navigation Projects ....................... Other Authorized Flood Control Projects ...................... Active General Investigations ................. Navigation 1. NAVIGATION WORK UNDER SPECIAL AUTHORIZATION Navigation activities pursuant to Sec. 107, Public Law 86-645, as amended (preauthorization). During the period $7,500 was expended for studies on DeValls Bluff, AR. Flood Control 2. GRAYS CREEK CANAL, SHELBY CO., TN Location. The project site is located along the left descending bank of Grays Creek Canal just downstream of Raleigh-LaGrange Road and near the Memphis Light, Gas and Water electrical transmission tower in East Shelby County, Tennessee. Existing project. Authorized under the authority of Section 14 of the Flood Control Act of 1946. This project provides protection for the transmission tower from streambank caving. The improvements consist of the placement of stone along approximately 350 linear feet of the eroding bank. Local cooperation. Provide without cost to the United States all lands, easements, and rights-of-way necessary for construction of the project; provide without cost to the United States all necessary relocations and alterations of buildings and utilities, sewers, related and special facilities; to the extent of the legal authority of the Memphis Light, Gas and Water Division, hold and save the United States free from all damages due to construction, operation, and maintenance of the project, and, if applicable, adjust all claims concerning water rights, except damages due to the fault or negligence of the United States or its contractors; to the extent of the legal authority of the Memphis Light, Gas and Water Division, maintain and 13-1 2. 3. 4. 5. 6. 7. 8. Page 13-3 13-4 13-5 13-6 13-7 13-8 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 operate the project works after completion without cost to the United States in accordance with regulations prescribed by the Secretary of the Army; comply with the provisions of the Uniform Relocation Assistance and Real Property Acquisition Policies Act of 1970, Public Law 91-646; comply with provisions of Section 221 of the Flood Control Act of 1970, Public Law 91- 611; assume any construction costs in excess of $250,000, the monetary limit established in Section 27, Public Law 93-251; prevent future encroachment which might interfere with proper functioning of the project; comply with the provisions of Section 601 of Title VI of the Civil Rights Act of 1964, Public Law 88-352. The Memphis Light, Gas and Water Division executed the required Agreement of Local Cooperation on May 8, 1985. The Agreement was approved for the United States on May 15, 1985, by the Memphis District Engineer. Condition as of Sep. 30. A contract for construction of the project was awarded on June 26, 1985, and work was completed on August 12, 1985. 3. HATCHIE RIVER, ALCORN COUNTY, MISSISSIPPI Location. The project is located in Alcorn County in northeast Mississippi, along the Hatchie River 5 miles upstream of U.S. Highway 72. Existing project. Authorized under the authority of Section 208 of the 1954 Flood Control Act. The project consists of removal of a 1,000-foot-long massive logjam where the Hatchie River channel was completely blocked and stream flows were diverted into the adjacent bottomland hardwood forests. Timber will be restored or preserved on over 1,100 acres of valuable forests. Local cooperation. Provide without cost to the United States all lands, easements, and rights-of-way necessary for the construction, operation and maintenance of the project and all necessary modifications or relocations of roads, bridges, and utilities other than railroad bridges and bridge approaches; to the extent of the legal authority of the Hatchie Drainage District of Alcorn County, hold and save the United States free from all damages arising from the construction and operation of the completed works, except those damages due to the sole fault or negligence of the United States or its contractors; to the extent of the legal authority of the Hatchie Drainage District of Alcorn County, maintain and operate the completed works without cost to the United States in accordance with regulations prescribed by the Secretary of the Army; prevent future encroachment which might interfere with proper functioning of the project for flood control after project construction; pay all costs associated with project features designated to be local interest responsibilities; assume full responsibility for all project costs in excess of the Federal cost limitation of $250,000; comply with the provisions of the Uniform Relocation Assistance and Real Property Acquisition Policies Act of 1970, Public Law 91-646; comply with the provisions of Section 221 of the Flood Control Act of 1970, Public Law 91-611; comply with the provisions of Section 601 of Title VI of the Civil Rights Act of 1964 (Public Law 88-352) that no person shall be excluded from participation in, denied the benefits of or subjected to discrimination in connection with the project on the grounds of race, creed, or national origin. Local interests have furnished the required assurances. Condition as of Sep. 30. The channel blockage was removed in August 1985. Remaining minor cleanup work is scheduled for the second quarter of fiscal year 1986. 4. HUMBOLDT, TN Location. Humboldt is located in Gibson County, TN. Existing project. Authorized July 23, 1984, under the authority of Section 205 of the 1948 Flood Control Act, as amended. The project consists of clearing and snagging approximately 2,200 feet of existing channel and the construction of 2,600 feet of enlarged channel. The project will provide a 10-year level of protection for area residents and is expected to reduce average annual flood damages by 64 percent. The current estimated construction cost for the project is $1,110,000. Plans and specifications for the project have been completed and the assurances of local cooperation have been furnished. The construction contract is scheduled to be awarded in March 1985. It has been determined that no adverse environmental impacts will result from construction of the project. Local cooperation. Requirements of local cooperation are fully described on page 13-4 of FY 1984 Annual Report. Condition as of Sep. 30. The local sponsor is currently acquiring necessary project easements and relocating utilities and expects to be completed with these tasks by November 1985. 5. NONCONNAH CREEK INTERCEPTOR SEWER, MEMPHIS, TENNESSEE Location. The project is located in southeastern Memphis, Tennessee, along the right (north) bank of Nonconnah Creek through a reach extending from about 600 feet upstream to 100 feet downstream of the Highway 78 (Lamar Ave.) bridge. Existing project. Authorized under the authority of Section 14 of the Flood Control Act of 1946. The project consists of providing bank protection along a 700 foot reach of eroding creek bank to protect a major interceptor sewer line and the U.S. Highway 78 13-2 MEMPHIS, TN, DISTRICT bridge. Protection is to be provided via grading and shaping the bank and armoring it with riprap stone. Local cooperation. Provide without cost to the United States all lands, easements, and rights-of-way necessary for construction of the project; provide without cost to the United States all necessary relocations and alterations of buildings and utilities, sewers, related and special facilities; to the extent of the legal authority of the City of Memphis, Tennessee; hold and save the United States free from all damages due to the construction, operation, and maintenance of the project, except damages due to the fault or negligence of the United States or its contractors; to the extent of the legal authority of the City of Memphis, Tennessee, maintain and operate the project works after completion without cost to the United States in accordance with regulations prescribed by the Secretary of the Army; comply with provisions of the Uniform Relocation Assistance and Real Property Acquisition Policies Act of 1970, Public Law 91-646; comply with the provisions of Section 221 of the Flood Control Act of 1970, Public Law 91-611; assume any construction costs in excess of $250,000, the monetary limit established in Section 27, Public Law 93-251; prevent future encroachment which might interfere with proper functioning of the project; if applicable, adjust all claims covering water rights; comply with the provisions of Section 601 of Title VI of the Civil Rights Act of 1964, Public Law 88-352. The city of Memphis, Tennessee, has indicated an intent to provide the required local cooperation assurances. Condition as of Sep. 30. Construction of the project is scheduled for the first quarter of FY 1986. 6. SANDY CREEK, JACKSON, TN Location. The project site is located along the left descending bank of Sandy Creek immediately downstream from the Westwood Avenue bridge. Existing project. Authorized under the authority of Section 14 of the Flood Control Act of 1946. This project will provide protection for public facilities adjacent to the stream which consists of a city fire station and a Boys and Girls Club with attendant swimming pool. The improvements consist of filling and grading the bank and providing protection for the bank via rock-filled gabions. Local cooperation. Requirements of local cooperation are fully described on page 13-4 of FY 1984 Annual Report. Condition as of Sep. 30. Construction was completed in December 1984. 7. ST. FRANCIS RIVERHIGHWAY NO.90 AR Location. The project site is located approximately three miles west of Kennett, MO, along the right descending bank of a channel in the St. Francis floodway on the south side of the Arkansas Highway 90 approach embankment to the St. Francis River bridge. Existing project. Authorized under the authority of Section 14 of the Flood Control Act of 1946. This project will provide, protection for the Arkansas Highway 90 approach from streambank caving. The improvements consist of placing stone along approximately 500 linear feet of the approach embankment. Local cooperation. Requirements of local cooperation are fully described on page 13-4 of FY 1984 Annual Report. Condition as of Sep. 30. Construction was completed in September 1985. 8. INSPECTION OF COMPLETED FLOOD CONTROL PROJECTS Inspected completed projects at a cost of $83,104 in the period. Total cost as of Sep. 30, 1985, was $1,050,258. This included in-depth inspection of projects. 9. FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION Flood control activities pursuant to Sec. 205, Public Law 858, 80th Cong., as amended (preauthorization). During this period $14,021 was expended for detailed studies on Caney Creek, AR; $39,700 on Laconia Circle, AR; $48,581 on Tuscumbia River, MS & TN; $34,639 on Cane Creek, Martin, TN, and $153 on Martin Branch, Clarendon, AR. During FY 1985 $7,500 was expended for detail studies on Nonconnah Interceptor Sewer, Memphis, TN; $10,238 on Turner Creek, Corinth, MS; and $3,900 on Phillips Creek, Corinth, MS. Emergency flood control activities - repair, flood fighting, and rescue work (Public Law 99, 84th Cong., and antecedent legislation). Federal cost was $6,373.67 for rehabilitation eligibility inspection for Dyer County Private Levee, $197,878 for disaster preparedness, and $3,405 for emergency operations. Flood control activities pursuant to Sec. 208, Public Law 780, 83d Cong., as amended. During this period $2,800 was expended for detailed studies on Fourth and Polk Streets, Corinth, MS; $7,500 on Unnamed Street, Forrest City, AR; and $13,000 on Hatchie River, MS. 13-3 TABLE 13-A REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 COST AND FINANCIAL STATEMENT See Section Total Funds to in Text Project Funding FY 82 FY 83 FY 84 FY 85 Sep. 30, 1985 2. Grays Creek New Work Canal, Shelby Approp. $ - $ - $ 29,000 $126,000 $ 155,000 Co., TN Cost - - 8,843 111,642 120,485 3. Hatchie River, New Work Alcorn Co., MS Approp. - - - 62,676 62,676 Cost - - - 62,673 62,673 4. Humboldt, TN New Work Approp. - - 155,000 - 155,000 Cost - - 124,150 11,539 135,689 5. Nonconnah Creek New Work Interceptor Approp. - - - 30,000 30,000 Sewer, Memphis, Cost - - . 29,435 29,435 TN 6. Sandy Creek, New Work Jackson, TN Approp. - - 196,000 42,000 238,000 Cost - - 41,694 196,306 238,000 7. St. Francis New Work River Hwy #90, Approp. - - 35,000 125,825 160,825 AR Cost - - 24,223 135,707 159,930 1. Excludes $25,000 expenditures for early construction; includes $20,245 for preauthorization studies on Sec. 107 Project. 2. Excludes $17,500 contributed funds expended. 13-4 MEMPHIS, TN, DISTRICT TABLE 13-B AUTHORIZING LEGISLATION Acts Work Authorized Documents GRAYS CREEK (See Sec. 2 of Text) Jul. 24, 1946, Stabilization - stream bank caving. Approved Nov. 15, 19854 as amended HATCHIE RIVER (See Sec. 3 of Text) Sep. 24, 1954, Clearing and snagging within channel. Approved Jul 24, 19856 as amended HUMBOLDT, TN (See Sec. 4 of Text) June 30, 1948, Channel improvement within the city of Humboldt. Approved Jul. 23, 1984.2 as amended NONCONNAH INTERCEPTOR SEWER AND U.S. HIGHWAY 78 (See Sec. 5 of Text) Jul. 24, 1946, Stabilization - stream bank caving. Approved Oct. 18, 19854 as amended SANDY CREEK (See Sec. 6 of Text) Jul. 24, 1946, Stabilization - stream bank caving. Approved Nov. 3, 1983. 4 as amended ST. FRANCIS RIVER-HIGHWAY 90, AR (See Sec. 7 of Text) Jul. 24, 1946, Stabilization - stream bank caving. Approved Aug. 29, 1984. 4 as amended 1. Authorized under authority of Sec. I07 of the River and Harbor Act, as amended. 2. Authorized under authority of Sec. 205 of the 1948 Flood Control Act, as amended. 3. Contains latest published map. 4. Authorized under authority of Sec. 14 of the 1946 Flood Control Act. 5. Authorized under authority of Sec. 208 of the 1954 Flood control Act, as amended. 13-5 TABLE 13-C REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 OTHER AUTHORIZED NAVIGATION PROJECTS For Last Cost to Sep. 1985 Full Report Operation Mo. and Yr. See Annual and Mo. and Yr. Project Deauthorized Report For: Construction Maintenance Completed Caruthersville Harbor, MO - 1984 $768,992 $ 1,291,900 Dec 80 Forked Deer River, TN, including South Fork 1 2 - 1912 25,000 12,818 - Helena Harbor, AR - 1984 90,847 3,066,345 Sep 63 Hickman Harbor, KY - 1984 149,827 3,137,675 Jan 63 New Madrid Harbor, MO - 1984 196,373 385,509 Oct 70 Obion River, TN"" 3 - 1911 28,716 -- Osceola Harbor, AR - 1984 269,115 4,524,888 Nov 74 Removing snags and wrecks from Mississippi River below mouth of Missouri River and from Old and Atchafalaya Rivers4' 5 - 1948 - 318,833 4 St. Francis and L'Anguille Rivers and Blackfish Bayou, AR 2 - 1942 92,000 300,449 - White River, AR (below Newport) - 1984 169,994 14,462,571 - Wolf River (Memphis Harbor), TN - 1984 586,500 7,638,486 1959 1. No commerce. 2. Existing project is for maintenance only. 3. Recommended for abandonment in H. Doc. 467, 69th Cong., 1st sess. 4. Completion date not available. 5. No funds available under this project. Work being carried on under "Appropriation, Flood Control, Mississippi River and tributaries. 13-6 MEMPHIS, TN, DISTRICT TABLE 13-D OTHER AUTHORIZED FLOOD CONTROL PROJECTS For Last Cost to Sep. 1985 Full Report Operation Mo. and Yr. See Annual and Mo. and Yr. Project Deauthorized Report For: Construction Maintenance Completed Big Creek Canal, Millington, TN - 1977 $ 70,363 $ - Big Creek and L'Anguille River, White River Basin, AR1 6 May 81 1937 -- Bradford, TN - 1984 95,061 - Dec 1983 Clarendon to Laconia Circle, White River Basin, AR' 6 May 81 - - Cottonwood Slough pumping plant, IL2 - 1964 147,000 - Feb 1964 Drinkwater Sewer, MO - 1984 1,494,828 Jun 1980 Dyersburg, TN2 - 1962 229,6493 - Jun 1962 Dyersburg, TN (SW) - 1981 1,820,869 - Oct 1976 Huntingdon, TN Sep 1980 1983 2,900,281 -- Long Lake Area Helena, AR Jul 1983 1983 61,281- Memphis, Wolf River, and Nonconnah Creek, TN - 1960 11,141,199 - May 1959 Mounds and Mound City, Ohio River Basin, IL4 - 1955 1,132,704 - Oct 19596 Nixon Creek, TN2 - 1952 62,821 - Dec 1951 Nonconnah Blvd., Nonconnah Creek, TN - 1983 249,999 - Nov 1981 N. Second St., Memphis, TN (Wolf River Bridge) - 1983 249,999 - Sep 1980 Treasure Island, MO - 1981 861,528 - Mar 1978 US Hwy 51, Nonconnah Creek, TN - 1984 369,200 - Mar 1983 W. Hickman, Area, Hickman, KY - 1983 1,674,180 - Oct 1976 1. Inactive, awaiting local cooperation. 2. Authorized by Chief of Engineers under small project authority, Sec. 205, Flood Control Act of 1948, as amended. 3. Includes $21,863 contributed funds. 4. Work being completed under Mississippi River and Tributaries project. 5. Exclusive of Cache River Pumping Station. 13-7 TABLE 13-E REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 ACTIVE GENERAL INVESTIGATIONS (96x3121) Federal Cost Totals by Item and CWIS Number FY 85 Categories SURVEYS (Category 100) Miscellaneous Activities (170) Special Investigations (171) -17250 $ 23,953 COLLECTIONS AND STUDY OF BASIC DATA (Category 200) Flood Plain Management Services (250) Flood Plain Management Services 203,084 TOTAL (Category 200) $203,084 GRAND TOTAL GENERAL INVESTIGATIONS $227,037 13-8 ST. LOUIS, MO, DISTRICT* This district comprises those portions of southwestern Illinois and eastern Missouri embraced in drainage basin of Mississippi River and its western tributaries, exclusive of the Missouri River, from the mouth of the Ohio River to mile 300, and of its eastern tributaries to Hamburg Bay at mile 261 on left bank, exclusive of tributary basin of Illinois Waterway upstream of new La Grange Lock and Dam at mile 80.15 above confluence of the Illinois and Mississippi Rivers. District also includes drainage basin in Missouri tributary to the Little River diversion channel. Report on the Mississippi River between the Missouri River and mile 300 is included in separate report on the Mississippi River between the Missouri River and Minneapolis, MN. Report on the portion of the Illinois River downstream of new La Grange Lock and Dam is included in report of the Chicago District on the Illinois Waterway, Illinois and Indiana. IMPROVEMENTS Navigation 1. Illinois Waterway, IL (St. Louis Dist.) .................. 2. Kaskaskia River, IL .............. 3. Mississippi River between Missouri and Minneapolis, MN (St. Louis Dist.) (Includes L&D 26 Replacement) ..... 4. Mississippi River between Ohio and Missouri Rivers, MO, and IL .... Flood Control 5. East St. Louis and vicinity, IL ....... 6. Eldred and Spankey Drainage and Levee District, IL ................ 7. Hartwell Drainage and Levee District, IL ..................... 8. Hillview Drainage and Levee District, IL ..................... 9. Kaskaskia Island Drainage and Levee District, IL ................ 10. Mauvaise Terre Drainage and Levee District, IL ............. 11. Meramec River Basin, MO ......... 11A. Meramec Park Lake, MO .......... 11B. Pine Ford Lake, MO .............. 12. McGee Creek Drainage and Levee District, IL ..................... 13. Meredosia, IL, and Meredosia, Willow Creek, and Coon Run Drainage and Levee District, IL ..... 14. Meredosia Lake and Willow Creek Drainage and Levee District, IL ..... 15. Mississippi River Agricultural Area8,MO ..................... Page Flood Control (cont.) 16. Nutwood Drainage and Levee 14-2 District, IL ..................... 14-2 17. Perry County Drainage and Levee Districts Nos. 1, 2, and 3, MO ....... 18. Rend Lake, Big Muddy River, IL .... 14-2 19. Wood River Drainage and Levee District, IL ................ 14-2 20. Inspection of completed flood control projects .................. 21. Navigation work under 14-3 special authorization ............ . 22. Flood control work under 14-3 special authorization .............. 14-3 Multiple-Purpose Project Including Power 14-4 23. Clarence Cannon Dam and Mark Twain Salt River, MO .................. 14-4 14-4 14-4 General Investigations 24. Active investigations ................ 14-5 Tables 14-5 Table 14-A Table 14-B 14-5 Table 14-C 14-5 14-6 14-6 Table 14-D Table 14-E Table 14-F Cost and Financial Statement Authorizing Legislation ...... Other Authorized Navigation Projects ......... Lakes, Levees, and Recreational Facilities ....... Other Authorized Flood Control Projects........... Active General Investigations (96X3121) ..... Page 14-6 14-6 14-7 14-7 14-7 14-7 14-7 14-8 14-8 14-9 14-11 14-13 14-13 14-14 14-16 14-1 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Navigation 1. ILLINOIS WATERWAY, IL (ST. LOUIS DIST.) See report on Illinois Waterway, IL and IN, under Rock Island District. 2. KASKASKIA RIVER, IL Location. The river rises in Champaign County, IL, about 5 miles northwest of Urbana, in east-central part of State. It flows southwesterly about 325 miles and empties into Mississippi River about 8 miles above Chester, II, or about 118 miles above mouth of Ohio River. (See Cincinnati sheet of maps of United States published by Army Map Service, scale 1:500,000.) Previous project. For details see Annual Report for 1896, page 171. Existing project. Improvement for navigation provides a channel 9 feet deep and 225 feet wide from mouth to Fayetteville, IL. Improvement consists of enlarging present channel where required, making overbank cutoffs to eliminate sharp bends, and construction of a dam at mile 0.8 with a single lock 84 feet wide and 600 feet long, at an estimated total Federal project cost (1984) of $145,060,000. Non-Federal project cost is $7,665,000, of which $1,500,000 is local contribution. Local cooperation. State of Illinois passed legislation authorizing Illinois Department of Public Works and Buildings to enter into assurances of local cooperation with the United States. These assurances have been furnished and were accepted on behalf of the United States on Sept. 10, 1965; these assurances were supplemented on Aug. 7, 1972, to incorporate the provisions of PL 91-646. Operations and results during fiscal year. Work is complete on the lock and dam, railroad relocations, and the grade control structure. Engineering and design continued on remaining construction items. Project is about 92 percent complete. Maintenance. Hired labor performed operation and maintenance of the project. 3. MISSISSIPPI RIVER BETWEEN MISSOURI RIVER AND MINNEAPOLIS, MN. (ST. LOUIS DIST.) (INCLUDES L&D 26 REPLACEMENT) See separate section entitled "Mississippi River between Missouri River and Minneapolis, MN," printed in the Annual Report of the Chief of Engineers. 4. MISSISSIPPI RIVER BETWEEN OHIO AND MISSOURI RIVERS, MO AND IL Location. Mississippi River rises in Lake Itasca, MN, and from that lake flows southerly about 2,340 miles and empties into the Gulf of Mexico. Portion included in this report embraces the 195-mile section known as middle Mississippi, between tributary Ohio and Missouri Rivers about 974 to 1,169 miles from the gulf. See folder by Corps of Engineers of Navigation Charts, Middle and Upper Mississippi River, Cairo, IL, to Minneapolis, MN. Previous projects. For details see page 1879 of Annual Report for 1915, and page 1014 of Annual Report for 1938. Existing project. The existing project provides for obtaining and maintaining a minimum channel depth of not less than 9 feet, a minimum width of not less than 300 feet at low water, with additional widths in bends from mouth of Ohio River (about 974 miles from gulf) to northern boundary of city of St. Louis, mile 191, thence 200 feet wide, with additional width in bends to mouth of Missouri River, mile 195; to be obtained: (1) by regulating works, for closing secondary channels, contracting river by building new banks where river width is excessive and protecting new and old banks from erosion where necessary to secure permanency at an estimated total Federal cost (1985) of $181,000,000; (2) by dredging to maintain project channels; (3) by construction of works authorized for Chain of Rocks reach in 1945 River and Harbor Act, which approved a comprehensive plan for development of the river at Chain of Rocks to provide for construction of a lateral canal at a cost of $59,720,600; and (4) by construction of a fixed-crest rock-fill dam about 900 feet below Chain of Rocks Bridge, authorized by 1958 River and Harbor Act, at cost of $4,353,000, excluding $7,000 costs to Coast Guard for aids to navigation. Estimated total Federal project cost (1985) is $245,073,600. A small boat harbor opposite Chester, IL, was deauthorized and excluded from foregoing cost estimate. See H. Doc. 669 (76th Cong., 3d sess.) for report of Chief of Engineers dated Feb. 27, 1940, containing a general plan for improvement of Mississippi River between Coon Rapids Dam and mouth of Ohio River for purposes of navigation, power development, flood control, and needs of irrigation. Local cooperation. None required. Terminal facilities. Existing facilities are considered adequate for existing commerce. Operations and results during fiscal year. Regulating Works: Contract was continued on stone dike and revetment construction as was engineering and design and supervision and administration. Construction on existing project began in 1881 and project has been in beneficial use practically from its inception. Projects on Dam 27 and Chain of Rocks are complete. Work on the project is about 70 percent complete. Channel as a whole has been greatly improved by the work completed to date. Dredging is required at low stages to remove temporary shoals and maintain required channel depths. River is generally above 10-foot stage, St. Louis gage, from latter part of February to the latter part of August, during which time project channel depths generally prevail without dredging. Maintenance. Work consisted of 1,964 feet of dike and 20,812 feet of revetment repair. U.S. plant and 14-2 ST. LOUIS, MO, DISTRICT hired labor performed channel dredging removing 4,191,000 cubic yards of material from main channel. Condition and operation studies, recreation planning, engineering and design, and operation and maintenance of Lock and Dam 27 continued. Flood Control 5. EAST ST. LOUIS AND VICINITY, IL Location. Project is in St. Clair and Madison Counties, IL, on the left bank of the Mississippi River between river miles 175 and 195 above the Ohio River. Project includes all bottomlands between bluffs on the east and Mississippi River and Chain of Rocks Canal on the west, and extends from Cahokia diversion channel on the north to Prairie du Pont Creek on the south. (See Corps of Engineers Navigation Charts, Middle and Upper Mississippi River, Cairo, IL, to Minneapolis, MN.) Existing project. The 1936 Flood Control Act authorized raising and enlarging existing levee systems by construction or reconstruction of 19.8 miles of levee, including 3.1 miles of floodwall, together with necessary appurtenant works consisting of gravity drainage structures, highway and railroad closure structures, alterations and reconstruction of existing pumping plants, alterations to railroad bridges and approaches at levee crossings, service roads on levee crown, and seepage control measures. Work under this authorization provides the area protection against a flood of about 200-year frequency. The completed 10 miles of levee along Chain of Rocks Canal and Lock 27 provide flood protection on the landward side integral with and to the same degree as the East St. Louis levee. Final cost of work under this authorization is $22,550,100. The Flood Control Act of 1965 modified existing project to provide for channel improvements, diversion ditches, flood plain detention areas, a reservoir on Little Canteen Creek, and a pumping plant to considerably reduce damages resulting from interior flooding. This act also authorized reconstruction of a channel stabilization dam in Cahokia Creek diversion channel to provide protection to adjacent levees and bridges from scour and eventual loss. Estimated total Federal project cost of work under this authorization is $33,600,000 (1985), $22,020,000 for Cahokia-Harding Ditch Area, and $11,580,000 for Blue Waters Ditch. Non-Federal cost is $20,770,000. Local cooperation. Local interests have fully complied with the requirements of local cooperation for work under the 1936 authorization. For work authorized by Flood Control Act of 1965 requirements of local cooperation are fully described on page 14-4 of Fiscal Year 1980 Annual Report. Formal assurances were accepted on the Blue Waters Ditch area on Jun. 25, 1981. Formal assurances for the Cahokia-Harding Areas will be requested upon approval of the plan of improvement currently scheduled after FY 89, due to lack of funding for FY 85 through FY 89. Operations and results during fiscal year. Planning was continued on project modifications authorized by Flood Control Act of 1965 and construction was continued on ditching contracts and on the pumping station. Work authorized by Flood Control Act of 1936 is complete. 6. ELDRED AND SPANKEY DRAINAGE AND LEVEE DISTRICT, IL Location. The levee district is in Greene County, II, on the left bank of the Illinois River between miles 23.8 and 32.3 above the Mississippi River. (See Quincy, ILMO, sheet of maps of the United States, published by Army Map Service, scale 1:250,000.) Existing project. Project provides for raising and enlarging 15.9 miles of levees, altering discharge line of pumping station, and construction of two highway closure structures and seepage control measures. Project will provide protection to 10,470 acres of land, 9,735 of which are highly productive agricultural lands, against a flood of 50-year frequency. Estimated total Federal project cost (1985) is $6,380,000. Non- Federal cost is $953,000. Project was authorized by the 1962 Flood Control Act (H. Doc. 472, 87th Cong., 2nd sess.). Local cooperation. Requirements of local cooperation are fully described on page 14-4 of Fiscal Year 1980 Annual Report. Local interests have indicated a willingness to meet the terms of local cooperation. Operations and results during fiscal year. Preconstruction planning was continued under the general investigation appropriation. Construction has not begun. 7. HARTWELL DRAINAGE AND LEVEE DISTRICT, IL Location. The levee district is in Greene County on the left bank of the Illinois River between miles 38.2 and 43.1 above the Mississippi River. (See Quincy, ILMO, sheet of maps of the United States, published by Army Map Service, scale 1:250,000.) Existing project. Project provides for construction of 12.3 miles of new or enlarged levees, altering discharge line of pumping station and construction of seepage control measures. Project will provide protection to 9,630 acres of land, 8,955 of which are highly productive agricultural lands against a flood of 50-year frequency. Estimated total Federal project cost (1985) is $12,400,000. Non-Federal cost is $1,120,000. Project was authorized by the 1962 Flood Control Act (H. Doc. 472, 87th Cong., 2d sess.) Local cooperation. Requirements of local cooperation are fully described on page 14-5 of Fiscal Year 1980 Annual Report. Local interests have indicated a willingness to meet the terms of local cooperation. Operations and results during fiscal year. Preconstruction planning was continued under the general 14-3 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 investigation appropriation. Construction has not begun. 8. HILLVIEW DRAINAGE AND LEVEE DISTRICT, IL Location. The levee district is in Greene and Scott Counties, IL, on the left bank of the Illinois River between miles 43.2 and 50.0 above the Mississippi River. (See Qunicy, IL-MO, sheet of maps of the United States, published by Army Map Service, scale 1:250,000.) Existing project. Project provides for construction of 14.3 miles of levee, alteration of discharge lines for three existing pumping stations, construction of a railroad closure structure, and seepage control measures. Project will provide protection to the Village of Hillview and to 13,070 acres of agricultural land against a flood of 50-year frequency. Estimated total Federal project cost (1985) is $12,300,000. Non-Federal cost is $1,220,000. Project was authorized by the 1962 Flood Control Act (H. Doc. 472, 87th Cong., 2d sess.) Local cooperation. Requirements of local cooperation are fully described on page 14-6 of Fiscal Year 1980 Annual Report. Local interests have indicated a willingness to meet the terms of local cooperation. Operations and results during fiscal year. Preconstruction planning was continued under the general investigation appropriation. Construction has not begun. 9. KASKASKIA ISLAND DRAINAGE AND LEVEE DISTRICT, IL Location. In Randolph County, IL, on the right bank of the Mississippi River between miles 111 and 116 above the mouth of the Ohio River. (See Paducah, KY, IL, MO, IN, map published by Army Map Service, scale 1:250,000.) Previous project. For details, see page 1375 of Annual Report for 1950. Existing project. Project area contains about 9,460 acres only partially protected against flood stage of 38.5 feet on the Chester, IL, gage. Flooding occurs about once in every 7.3 years with an average duration of 26 days, causing substantial damage. The 1962 Flood Control Act (H. Doc. 519, 87th Cong., 2d sess.) provides for enlarging and raising the existing levee about 8 feet to provide protection against a flood having a frequency of once in 50 years. Estimated total Federal project cost (1985) is $13,200,000. Non-Federal cost is $2,100,000. Local cooperation. Requirements of local cooperation are fully described on page 14-6 of Fiscal Year 1980 Annual Report. Formal assurances from the Kaskaskia Island Drainage and Levee District were accepted on behalf of the United States on Jan. 23 1980. Operations and results during fiscal year. Preconstruction planning is complete. Construction is complete on the gravity drains. Plans and specifications for raising and enlarging the levee are complete and construction was continued on this item. 10. MAUVAISE TERRE DRAINAGE AND LEVEE DISTRICT, IL Location. The levee district is in Scott County, IL on the left bank of the Illinois River between miles 63.5 and 67.0 above the Mississippi River. (See Quincy, ILMO, sheet of maps of the United States, published by Army Map Service, scale 1:250,000). Existing project. Project provides for raising a portion of the existing levee and construction of two railroad closure structures. Project will provide protection to 5,700 acres of land against a flood of 100- year frequency. Estimated total Federal project cost (1985) is $800,000. Non-Federal cost is $167,000. Project was authorized by the Energy and Water Development Appropriation Act of 1985, Public Law 98-360, 98th Cong., 2nd Session. Local cooperation. The village of Naples, IL, signed a letter of intent, dated March 13, 1985, indicating a willingness to comply with the terms of local cooperation including provisions of the Uniform Relocations and Real Property Acquisition Policy Act of 1970 (PL 91-646) and Section 221 of the Flood Control Act of 1970 (PL 91-611). Local Cooperation requirements are: furnish without cost to the United States all lands, easements, and rights-of-way necessary and accomplish all relocations necessary for the construction of the project; hold and save the United States free from damages due to the construction works, save and except damages due to the fault or negligence of the United States or its contractor; and maintain and operate all the works after completion in accordance with regulations prescribed by the Secretary of the Army. Operations and results during fiscal year. Planning was initiated on design memorandum. 11. MERAMEC RIVER BASIN, MO Location. The basin lies within the State of Missouri and comprises 3,980 square miles. The river is a west bank tributary of the Mississippi River at mile 161 above mouth of Ohio River. Major streams in the basin include the Meramec, Big, and Bourbeuse Rivers. The basin extends about 100 miles southwesterly from St. Louis into the Ozark Highlands. (See St. Louis, MO, and Rolla sheets of maps of the United States, published by Army Map Service, scale 1:250,000.) Existing project. The project provides for the construction of Meramec Park and Union Lakes, authorized by the 1938 Flood Control Act; and Pine Ford, Irondale, and 1-38 Lake projects, and 19 angler-use sites, authorized by the 1966 Flood Control Act. Under the plan, Irondale and 1-38 Lakes will reduce flood damages in the upper Big and Bourbeuse Rivers. Meramec Park, Union, and Pine Ford Lakes will 14-4 ST. LOUIS, MO, DISTRICT substantially reduce flooding in the lower basin area and will lower flood crests on the Mississippi River. Project will also provide water supply, water quality control, recreation, and fish and wildlife conservation. (See Table 14-D for additional data on this comprehensive project.) 11A. MERAMEC PARK LAKE, MO Location. Dam will be at mile 108.7 on Meramec River in Franklin County near Sullivan, MO. Reservoir will be mainly in Crawford, Franklin, and Washington counties, MO. (See St. Louis, MO, sheet of maps of the United States, published by Army Map Service, scale 1:250,000.) Existing project. Project as authorized by 1938 Flood Control Act provides for construction of an earth dam about 167 feet high with a crest length of 3,000 feet. Reservoir will provide 1 million acre-feet of storage and provide flood protection for 11,862 acres of flood plain in the Meramec River valley above the mouth of Bourbeuse River, and partial protection for 20,209 acres of land below the Bourbeuse. Project will also provide water supply, water quality control, storage, and recreation, and fish and wildlife benefits. Estimated total project cost (1981) is $220,000,000, including $22,506,000 local reimbursement for water supply. Local cooperation. Local interest must contribute toward cost of project for storage allocated to water supply in accordance with the Water Supply Act of 1958. State of Missouri, acting through its State Water Resources Board and under authority of the General Assembly of State of Missouri, executed assurances for water supply on Aug 23, 1967. The assurances were reviewed by the Office of the Attorney General, State of Missouri, and it is his opinion that the State of Missouri has the legal authority and financial capability to execute said assurances. These assurances have been approved by the Chief of Engineers. A water-supply contract will be entered into with the sponsor before any use of the water-supply storage provided under this contract. Operations and results during fiscal year. Project was deauthorized by Public Law 97-128. Land is being disposed of in accordance with deauthorizing act. Maintenance. Hired labor forces performed operations and maintenance of existing facilities. liB. PINE FORD LAKE, MO Location. Dam is on Big River at mile 43.8, about 45 miles southwest of St. Louis. The Big River is a tributary of the Meramec. Lake will extend about 34 miles up Big River. (See St. Louis, MO, sheet of maps of the United States, published by Army Map Service, scale 1:250,000.) Existing project. Project provides for construction of a compacted earth-fill dam with a concrete chute spillway. Dam will be 141 feet high and 2,070 feet long. Construction of new roads, improvements of existing roads, alterations to pipeline, power and telephone lines, and construction of recreational facilities are included. Maximum storage capacity will be 285,000 acre-feet. Estimated total project cost (1984) is $147,000,000, of which $8,173,200 and $22,900,000 are local reimbursements for water supply and recreation and fish and wildlife respectively. Local cooperation. Local interests must contribute toward cost of project for storage allocation to water supply in accordance with the Water Supply Act of 1958. Operations and results during fiscal year. Preconstruction planning previously funded but not completed. 12. McGEE CREEK DRAINAGE AND LEVEE DISTRICT, IL Location. The levee district is in Brown and Pike Counties, IL, on the right bank of Illinois River between miles 67.2 and 75.1 above the Mississippi River. (See Kansas City sheet of maps of United States, published by Army Map Service, scale 1:500,000.) Existing project. Project provides for reconstruction of 14.7 miles of levee, construction of a new pumping plant, closure structure, and seepage control measures. Project will provide protection to about 12,080 acres of agricultural land against a flood of about 50-year frequency. Estimated total Federal project cost (1983) is $25,500,000. Non-Federal cost is $930,000. Project was authorized by 1962 Flood Control Act (H. Doc. 472, 87th Cong., 2d sess.). Local cooperation. Requirements of local cooperation are fully described on page 14-9 of Fiscal Year 1980 Annual Report. Local interests have executed assurances in compliance with Public Law 91-611 and Public Law 91-646. Operations and results during fiscal year. The pumping station, and the lower flank levee are under construction. Construction is complete on the upper flank levee and the river front levee. The project is 97 percent complete. 13. MEREDOSIA, IL, AND MEREDOSIA, WILLOW CREEK, AND COON RUN DRAINAGE AND LEVEE DISTRICTS, IL Location. The levee district is in Morgan and Scott Counties, IL, on the left bank of the Illinois River between miles 67.0 and 72.2 above the Mississippi River. (See Quincy, IL-MO sheet of maps of the United States, published by Army Map Service, scale 1:250,000.) Existing project. Project provides for construction of 11.0 miles of new or enlarged levee, a pumping plant, closure structure, and seepage control measures. Project will provide protection to 8,215 acres of land, 14-5 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 7,640 of which are highly productive agricultural lands, and 575 acres of noncrop and farmsteads against a flood of 50-year frequency. Estimated total Federal project cost (1985) is $12,100,000. Non-Federal cost is $1,030,000. Project was authorized by the 1962 Flood Control Act (H. Doc. 472, 87th Cong., 2d sess.). Local cooperation. Requirements of local cooperation are fully described on page 14-9 of Fiscal Year 1980 Annual Report. Local interests have indicated a willingness to meet the terms of local cooperation. Operations and results during fiscal year. Preconstruction planning was continued under the general investigation appropriation. Construction has not begun. 14. MEREDOSIA LAKE AND WILLOW CREEK DRAINAGE AND LEVEE DISTRICT, IL Location. The project is in Cass and Morgan Counties, IL, on the left bank of the Illinois River between miles 72.2 and 79.0 above the Mississippi River. (See Qunicy, IL-MO sheet of maps of the United States, published by Army Maps Service, scale 1:250,000.) Existing project. Project provides for construction of 15.9 miles of new or enlarged levee, closure structure, drainage facilities, and seepage control measures. Project will provide protection to 7,510 acres of land, 6,980 of which are highly productive agricultural lands, and 530 acres of non crop and farmsteads against a flood of 50-year frequency. Estimated total Federal project cost (1985) is $10,000,000. Non-Federal cost is $560,000. Project was authorized by the 1962 Flood Control Act (H. Doc. 472, 87th Cong., 2d sess.). Local cooperation. Requirements of local cooperation are fully described on page 14-10 of Fiscal Year 1980 Annual Report. Local interests have indicated a willingness to meet the terms of local cooperation. Operations and results during fiscal year. Preconstruction planning was continued under the general investigation appropriation. Construction has not begun. 15. MISSISSIPPI RIVER AGRICULTURAL AREA 8, MO Location. Area 8 is in Lincoln and Pike Counties, MO, on west bank of Mssissippi River between river miles 249 and 261 above the Ohio River. Small community of Elsberry lies within the area. (See Quincy sheet of maps of the United States, published by Army Map Service, scale 1:250,000.) Existing project. The 1966 Flood Control Act (H. Doc. 510, 89th Cong., 2d sess.) authorized the raising and enlarging of existing levees to provide 24.4 miles of riverfront, flank, and back levees and construction of appurtenant works consisting of drainage structure, highway and railroad closure structures, and alterations to existing pumping plants. The project has been reduced in scope to consist of replacing one existing drainage structure, replacing an obsolete stream driven pump unit with a new one of 150 cubic feet per second capacity, and rehabilitation of the pump station. Project will afford protection to the area against a flood of 50-year frequency. Estimated total Federal project cost (1980) is $2,400,000. Non-Federal cost is $20,000. Local cooperation. Fully complied with. See page 14-10 of FY 1980 Annual Report. Operations and results during fiscal year. Project is complete. Operation and maintenance manual was completed. 16. NUTWOOD DRAINAGE AND LEVEE DISTRICT, IL Location. The levee district is in Greene and Jersey Counties, IL, on the left bank of the Illinois River between miles 15.2 and 23.7 above the Mississippi River. (See Quincy, IL-MO, sheet of maps of the United States, published by Army Map Service, scale 1:250,000.) Existing project. Project provides for raising and enlarging 11.4 miles of levee, construction of 1.0 mile of new levee, altering discharge line of pumping station, and construction of seepage control measures. Project will provide protection to 10,360 acres of land, 9,635 of which are highly productive agricultural lands against a flood of 50-year frequency. Estimated total Federal project cost (1985) is $6,500,000. Non-Federal cost is $450,000. Project was authorized by the 1962 Flood Control Act (H. Doc. 472, 87th Cong., 2d sess.). Local cooperation. Requirements of local cooperation are fully described on page 14-11 of Fiscal Year 1980 Annual Report. Local interests have indicated a willingness to meet the terms of local cooperation. Operations and results during fiscal year. Preconstruction planning was continued under the general investigation appropriation. Construction has not begun. 17. PERRY COUNTY DRAINAGE AND LEVEE DISTRICTS NOS. 1, 2, & 3, MO Location. Districts are in Perry County, MO, and Randolph County, IL, on the right bank of the Mississippi River between river miles 95 and 111 above the mouth of the Ohio River. (See Paducah, KY, IL, MO, IN, map published by Army Map Service, scale 1:250,000.) Previous project. For details, see 475 of Annual Report for 1968. Existing project. Project area contains about 26,881 acres protected from floods of the Mississippi River by levees. However, when Mississippi River stage exceeds 13 feet on the Chester, IL, gage, substantial damage results from impoundment of precipitation or seepage, or a combination thereof. Authorized project provides 14-6 ST. LOUIS, MO, DISTRICT for construction of four pumping stations to reduce interior flooding. Estimated total Federal project cost (1982) is $8,812,000. Local cooperation. Requirements of local cooperation are fully described on page 14-11 of Fiscal Year 1980 Annual Report. Assurances were furnished by local interests (presently, Boil Brule Levee District, MO). on Nov. 16, 1978, and were accepted Nov. 27, 1978, by the District Engineer under delegated authority. Operations and results during fiscal year. Construction is essentially complete on all four pumping stations. 18. REND LAKE, BIG MUDDY RIVER, IL Location. The lake is in Franklin and Jefferson Counties in southern Illinois. The dam is on Big Muddy River, 103.7 miles upstream from its confluence with the Mississippi River, and about 3 miles northwest of Benton, IL. (See Belleville sheet of maps of United States, published by Army Map Service, scale 1:250,000, and Geological Survey quadrangle maps, 1:62,500.) Existing project. The project provides for construction of an earth dam, ungated concrete spillway, relocation of roads and utilities, recreational facilities, access roads, and service facilities. In addition, two subimpoundment dams were constructed on upper arms of reservoir to enhance fish and wildlife value of project. Reservoir has an area of 24,800 acres, and a storage capacity of 294,000 acre-feet. Project provides flood control, water supply, low-flow regulations, conservation of fish and wildlife, recreation, and area development. Estimated total Federal project cost (1983) is $43,100,900, of which $12,197,700 is for lands and damages. Non-Federal local contribution for water supply is $9,941,300. Federal cost for code 711 recreation facilities is $1,060,900. Local cooperation. Requirements of local cooperation are fully described on page 14-12 of Fiscal Year 1980 Annual Report. Assurance of local cooperation and water supply contract have been executed and approved by the Secretary of the Army. Operations and results during fiscal year. Real estate activities in connection with project completion were performed. Lands acquired to date are 39,819 acres in fee and 906 acres in easements. Project is essentially complete. Maintenance. Hired labor forces performed operation and maintenance of Rend Lake Reservoir. 19. WOOD RIVER DRAINAGE AND LEVEE DISTRICT, IL Location. In Madison County, IL, on left bank of Mississippi River between river miles 195 and 203 above Ohio River. District includes bottom lands between river and bluffs and extends from Cahokia diversion channel on the south to opposite lock and dam No. 26 at Alton, IL, on the north. Small industrial cities of Hartford, Wood River, Roxana, and East Alton and part of Alton riverfront, lie within the district. (See Corps of Engineers Navigation Charts, Middle and Upper Mississippi River, Cairo, IL, to Minneapolis, MN.) Existing project. The 1938 Flood Control Act authorized raising, enlarging, and extending existing levee system to provide 20.8 miles of levees and construction of appurtenant works consisting of gravity drainage structures, highway and railroad closure structures, alterations to existing or construction of new pumping plants; surfacing service road on levee crown, making necessary alterations to railroad tracks and bridges at levee crossings, seepage corrective measures and construction of a low-water dam at mouth of Wood River. Project will afford protection to this district against a flood of about 200-year frequency. Estimated total construction cost (1982) is $18,600,000 (excluding $23,000 contributed funds). Flood Control Act of 1965 modified 1938 Flood Control Act to provide for construction of a pumping station with collector ditches and necessary appurtenant facilities for removal of water impounded by existing levee. This portion of the project has been declared inactive. Local cooperation. Fully complied with for work authorized by 1938 Flood Control Act. Operation and results during fiscal year. Work authorized by the 1938 Flood Control Act is complete except for a closure structure. Construction was initiated on this item. 20. INSPECTION OF COMPLETED FLOOD PROJECTS CONTROL Inspection of completed work was accomplished at a cost of $293,042 for the fiscal year. Total cost as of end of fiscal period is $5,050,349. 21. NAVIGATION WORK UNDER SPECIAL AUTHORIZATION Navigation activities pursuant to Sec. 107, Public Law 86-645, as amended (preauthorization). Preauthorization studies cost for fiscal year were $1,978 for Southeast Missouri Port study. 22. FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION Flood control activities pursuant to Sec. 205, Public Law 858, 80th Cong., as amended (preauthorization). Preauthorization study costs for fiscal year were $13,134 for Columbia Levee and Drainage District, Monroe County, IL; $75,819 for Crooked Creek, Bollinger County, MO; $79,349 for E. Cape Girardeau 14-7 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Main Ditch, IL; $7,500 for Illinois River, Kampsville, IL; $6,000 for Marion, IL; $21 for Meramec River, Jefferson County, MO; $43,244 for St. Peters, MO; and $6,000 for Mississippi River, Thebes, IL. Emergency Bank Protection. Costs for fiscal year were $7,500 for Cuivre River, Old Monroe, MO; and $12,493 for Illinois River, Hardin, IL. Emergency flood control activities-repair, flood fighting, and rescue work (Public Law 99, 84th Cong., and antecedent legislation). Federal costs for the fiscal year were $160,567 for disaster preparedness, $493,543 for emergency operations, and $454,575 for rehabilitation, $8,594 for advance measures and $3,513 for hazard mitigation. Multiple-Purpose Project Including Power 23. CLARENCE CANNON DAM AND RESERVOIR SALT RIVER, MO Location. Salt River rises in Schuyler County, about 12 miles south of Missouri-Iowa State line. It flows southeasterly about 192 miles and empties into Mississippi River about 2 miles above Louisiana, MO, or about 284 miles above mouth of Ohio River. (See Kansas City and Quincy sheets of maps of United States published by Army Map Service, scale 1:500,000, and Geological Survey quadrangle maps, 1:250,000.) Previous project. For details, see page 645 of Annual Report for 1968. Existing project. Project provides for construction of a multiple-purpose reservoir, including power, flood control, water supply, navigation storage, pollution abatement, fish and wildlife conservation, and recreation. Dam consists of a compacted earth embankment with a concrete spillway controlled by tainter gates. Dam and spillway are about 1,700 feet long. Spillway structure consists of an ogee overflow section surmounted by four 50- by 30-foot tainter gates. Reservoir will have a storage capacity of 1,428,000 acre-feet for use of flood control, future domestic and industrial water supply, sediment storage, and power generation. Project plan provides for installation of one 27,000 KW c6nventional unit and one 31,000 KW reversible unit for pumped storage operations. Total Federal project cost estimate (1984) is $330,000,000 of which $22,420,000 is for lands and damages; $14,300,000 for water supply; $76,000,000 for hydropower. Local cooperation. Requirements of local cooperation are fully described on page 14-13 of Fiscal Year 1980 Annual Report. Assurances have been received from the State of Missouri and approved by the Chief of Engineers. Operations and results during fiscal year. Work is complete on all major items. Work remaining consists of minor items on recreation facilities. Lands acquired to date are 55,277 acres in fee and 10,068 acres in easements. Project is essentially complete. General Investigations 24. ACTIVE INVESTIGATIONS See Table 14-F which covers: Surveys, Collection and study of basic data, and Research and development activities. 14-8 TABLE 14-A See Section in Text Project 2. Kaskaskia River IL (Regular Funds) (Contrib. Funds) 4. Mississippi River Between Ohio and Missouri Rivers (Includes Chain of Rocks) 5. East St. Louis and Vicinity, IL (Contrib. Funds) 6. Eldred & Spankey Drainage and Levee District, IL 7. Hartwell Drainage & Levee District, IL 8. Hillview Drainage & Levee District IL 9. Kaskaskia Island Drainage & Levee District, IL 10. Mauvaise Terre Drainage & Levee District, IL 11A. Meramec Park Lake, MO 11B. Pine Ford Lake, MO 12. McGee Creek Drainage & Levee District, IL 13. Meredosia, IL, and Meredosia, Willow Creek and Coon Run Drainage & Levee Districts, IL ST. LOUIS, MO, DISTRICT COST AND FINANCIAL STATEMENT Total Funds to Funding FY 82 FY 83 FY 84 FY 85 Sep. 30, 1985 New Work Approp. Cost Maint. Approp. Cost New Work Contrib. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost New Work Approp. Cost New Work Approp. Cost New Work Approp. Cost New Work Approp. Cost New Work Approp. Cost New Work Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost New Work Approp. Cost New Work Approp. Cost $1,800,000 1,883,090 1,200,000 973,968 0 42,000 2,000,000 1,759,811 9,269,000 8,443,093 275,000 515,776 150,000 10,000 0 64,620 0 137,251 0 58,771 725,000 797,320 00 0 28,285 567,000 415,026 15,000 120,033 2,285,000 1,134,848 70,1660 $400,000 388,140 1,131,856 1,036,248 00 2,437,000 1,574,639 8,010,656 10,191,370 950,000 1,011,724 180,000 161,250 00 0 10,021 0 572 500,000 375,659 00 0 -42,325 595,000 670,277 0 -5,815 8,012,900 8,793,102 $5,209,000 3,885,032 587,000 911,518 -104,348 0 2,610,000 3,440,369 7,490,000 7,157,647 2,597,000 2,167,981 0 158,733 00 00 00 1,057,000 451,595 00 0 16,897 326,000 412,597 0 366 5,420,000 5,366,819 0 1,408 00 $5,300,000 6,419,905 1,370,000 1,345,081 00 4,197,000 4,571,548 12,264,000 12,217,020 3,450,000 2,858,126 512,750 16,250 00 0 0 00 2,750,000 2,807,469 600,000 149,447 0 36,346 379,000 362,268 0 721 1,780,000 2,674,729 14-9 $133,100,000' 132,785,036' 10,359,256 10,307,588 1,139,730 1,118,160 170,963,6002 170,851,4602 205,411,1333 204,689,2903 15,069,3264 13,959,7695 643,080 346,233 875,000 875,000 622,000 622,000 433,000 433,000 7,750,000 6,821,346 600,000 149,447 30,568,0006 30,515,9076 3,089,600 3,047,020 3,680,001 3,643,659 24,920,300 24,670,107 370,000 370,000 TABLE 14-A (Continued) REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 COST AND FINANCIAL STATEMENT See Section Total Funds to in Text Project Funding FY 82 FY 83 FY 84 FY 85 Sep. 30, 1985 14. Meredosia Lake New Work and Willow Creek Approp. -15,000 0 0 0 345,000 Drainage & Levee Cost 121,430 845 0 0 345,000 District, IL 15. Mississippi River New Work Agricultural Area Approp. 172,000 0 0 0 2,137,000 No.8, IL Cost 173,441 6,190 5,634 4,063 2,136,831 16. Nutwood Drain- New Work age & Levee Approp. 0 0 0 0 670,000 District, IL Cost 50,079 8,993 120 0 670,000 17. Perry County New Work Drainage & Levee Approp. 1,558,000 1,503,000 -270,300 16,000 7,968,7007 DistrictNos.1, Cost 943,491 1,807,562 266,200 47,146 7,967,8417 2, &3, MO 18. Rend Lake, Big New Work Muddy, IL Approp. 0 0 0 - 43,700,900 (Regular Funds) Cost 19,141 81,753 35,976 24,820 43,654,562 Maint. Approp. 2,203,000 2,537,900 1,958,000 3,302,500 23,257,2008 Cost 2,107,010 2,533,327 2,072,978 3,103,736 22,945,8888 Code 711 Funds New Work Approp. 0 0 0 0 1,060,900 Cost 0 0 0 0 1,060,900 (Contrib. Funds) New Work Contrib. 0 0 0 0 9,941,2789 Cost 0 0 0 0 9,941,2789 Maint. Contrib. 0 0 304,348 300,000 3,186,303 Cost 140 0 293,485 305,279 3,180,719 19. Wood River New Work Drainage & Levee Approp. 285,000 450,000 1,000,000 0 16,589,82110 District, IL Cost 354,171 386,143 424,513 362,773 16,250,75410 23. Clarence Cannon New Work 23,500,000 33,849,700 10,240,300 3,622,000 311,199,02811 Dam and Reservoir, Approp. 24,029,076 34,463,424 8,922,842 2,948,571 307,868,20211 Salt River, MO Cost Maint. Approp. 1,426,000 1,891,100 2,074,000 3,260,500 12,151,060 Cost 1,285,921 1,937,491 2,127,691 3,190,444 11,955,044 1. Excludes $10,461 expended on previous project. 2. Excludes previous project cost of $1,416,620. 3. In addition $3,109 was expended for rehabilitation. 4. Includes $8,072,326 for work authorized by Flood Control Act of 1965. 5. Includes $7,921,939 for work authorized by Flood Control Act of 1965. 6. Includes $200,000 for definite project under 1938 Flood Control Act. 7. Excludes $6,800,700 for previous project. 8. Excludes $550,000 Area Development Administration Funds allotted to the State of Illinois for increased construction costs of Interstate Highway 57 to meet project requirements, and excludes $449,093 Area Redevelopment Administration Funds allotted to the Corps. 9. Includes $6,103,711 credit to State of Illinois for work in kind. 10. Funds are for work authorized by Flood Control Act of 1938. 11. Includes $216,628 for definite project study under 1938 Flood Control Act. 14-10 ST. LOUIS, MO, DISTRICT TABLE 14-B AUTHORIZING LEGISLATION Acts Work Authorized Documents Oct. 23, 1962 Jun. 3, 1896 Jun. 13, 1902 Mar. 2, 19071 Mar. 3, 19051 Jun. 25, 1910 Jan. 21, 1927 Jul. 3, 1930 Mar. 2, 1945 Sep. 3, 19543 Jul. 3, 19584 Jun. 22, 1936 Oct. 27, 1965 Oct. 22, 1976 Oct. 23, 1962 Oct. 23, 1962 Oct. 23, 1962 Oct. 23, 1962 Jul. 14, 1984 KASKASKIA RIVER, IL (See Section 2 of Text) Construct canal, lock, and dam to provide a 9-foot navigation channel from mouth to Fayetteville, IL. MISSISSIPPI RIVER BETWEEN OHIO AND MISSOURI RIVERS (See Section 4 of Text) Project for regulating works in 1881. (To obtain a minimum depth of 8 feet.) Dredging introduced as part of the project. These acts practically abrogated that part of project for middle Mississippi which proposed regulating woirks. Regulating works restored to project and appropriations begun with a view to completion of improvement between Ohio and Missouri Rivers within 12 years at an estimated cost of $21 million, exclusive of amounts previously expended. For 9 feet deep and 300 feet wide from Ohio River to northern Rivers and Harbors boundary of city of St. Louis. Project between northern boundary of St. Louis and Grafton (mouth of Illinois River) modified to provide a channel 9 feet deep and generally 200 feet wide with additional width around bends. Modified to provide construction of a lateral canal with lock at Chain of Rocks. Modified to provide construction of a small-boat harbor opposite Chester, IL. Modified to provide construction of a fixed crest rockfill dam 900 feet below Chain of Rocks Bridge. EAST ST. LOUIS AND VICINITY, IL (See Section 5 of Text) Raise and enlarge existing levee. Construct pumping plant and other modifications to reduce interior flooding. Construct Blue Waters Ditch as independent section. ELDRED AND SPANKEY DRAINAGE AND LEVEE DISTRICT, IL (See Section 6 of Text) Raise and enlarge existing levee and other modifications. HARTWELL DRAINAGE AND LEVEE DISTRICT, IL (See Section 7 of Text) Raise and enlarge existing levee and other modifications. HILLVIEW DRAINAGE AND LEVEE DISTRICT, IL (See Section 8 of Text) Raise and enlarge existing levee and other modifications. KASKASKIA ISLAND DRAINAGE AND LEVEE DISTRICT, IL (See Section 9 of Text) Raise and enlarge existing levee. MAUVAISE TERRE DRAINAGE AND LEVEE DISTRICT, IL (See Section 10 of Text) Raise and enlarge existing levee and other modifications. S. Doc. 44, 87th Cong., 1st sess. Annual Report, 1881, p. 1536. Committee Doc. 9, 69th Cong., 2d sess. Rivers and Harbors Committee Doc. 12, 70th Cong., 1st sess. H. Doc. 231, 76th Cong., 1st sess. H. Doc. 230, 83d Cong., 1st sess. Special report on record in OCE. H. Doc. 329, 88th Cong., 2d sess. Public Law 94-587, 94th Cong. H. Doc. 472, 87th Cong., 2d sess. H. Doc. 472, 87th Cong., 2d sess. H. Doc. 472, 87th Cong., 2d sess. H. Doc. 519, 87th Cong., 2d sess. Energy and Water Development Approp. Act of 1985, 98th Cong., 2nd sess. 14-11 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 14-B (Continued) AUTHORIZING LEGISLATION Acts Work Authorized Documents Jun. 28, 1938 Nov. 7, 1966 Oct. 23, 1962 Oct. 23, 1962 Oct. 23, 1962 Nov. 7, 1966 Oct. 23, 1962 Adopted by Senate and House Committee resolutions, Oct. 12, 19725 Oct. 23, 1962 Jun. 28, 1938 Oct. 23, 1962 Oct. 27, 1965 MERAMEC RIVER BASIN, MO (See Section 11 of Text) Construct reservoirs and local protection project. Construct Pine Ford, Irondale, and 1-38 dams and 19 Angler-use sites. MCGEE CREEK DRAINAGE AND LEVEE DISTRICT, IL (See Section 12 of Text) Reconstruct existing levee and construct pumping plant to reduce flooding. MEREDOSIA, IL, AND MEREDOSIA, WILLOW CREEK AND COON RUN DRAINAGE AND LEVEE DISTRICTS, IL (See Section 13 of Text) Raise and enlarge existing levee and other modifications. MEREDOSIA LAKE AND WILLOW CREEK DRAINAGE AND LEVEE DISTRICT, IL (See Section 14 of Text) Raise and enlarge existing levee and other modifications. MISSISSIPPI RIVER AGRICULTURAL AREA 8, MO (See Section 15 of Text) Raise and enlarge existing levee and alter pumping plant to reduce flooding. NUTWOOD DRAINAGE AND LEVEE DISTRICT, IL (See Section 16 of Text) Raise and enlarge existing levee and other modifications. PERRY COUNTY DRAINAGE AND LEVEE DISTRICTS NOS. 1, 2, & 3, MO (See Section 17 of Text) Construct pumping plants and other modifications to reduce interior flooding. REND LAKE, BIG MUDDY RIVER, IL (See Section 18 of Text) Construct dam at Benton, Ill., and subimpoundment dams on upper arms of reservoir. WOOD RIVER DRAINAGE AND LEVEE DISTRICT, IL (See Section 19 of Text) Construct reservoirs and local protection projects. CLARENCE CANNON DAM AND RESERVOIR, SALT RIVER, MO (See Section 23 of Text) Modified act of 28 Jun. 1938 by deleting the reservoir therefrom and reauthorizing it as a separate multiple-purpose project. Changes name of project from Joanna Dam to present designation. Flood Control Committee Doc. 1, 75th Cong., 1st sess. H. Doc. 525, 89th Cong., 2d sess. H. Doc. 472, 87th Cong., 2d sess. H. Doc. 472, 87th Cong., 2d sess. H. Doc. 472, 87th Cong., 2d sess. H. Doc. 472, 87th Cong., 2d sess. H. Doc. 360, 92nd Cong., 2d sess. H. Doc. 541, 87th Cong., 2d sess. Flood Control Committee Doc. 1, 75th Cong., 1st sess. H. Doc. 507, 87th Cong., 2d sess. Public Law 89-298, 89th Cong. 1. Also joint resolution, Jun. 29, 1906. 2. Contains latest published map. 3. Inactive. 4. All work completed. 5. Authorized under provision of Sec. 201 of the Flood Control Act of 1965. 14-12 ST. LOUIS, MO, DISTRICT TABLE 14-C OTHER AUTHORIZED NAVIGATION PROJECTS For Last Cost to Sep. 1985 Full Report Operation Mo. and Yr. See Annual and Mo. and Yr. Project Deauthorized Report For: Construction Maintenance Completed Cuivre River, MO' - 1883 $ 12,000 $ - Grafton Small Boat Harbor, IL Nov. 1977 19622 - Mississippi River at Alton, IL Small Boat Harbor Nov. 1977 19582 - - Moccasin Springs, MO - 1969 76,4363- Small Boat Harbor opposite Chester, IL Nov. 1977 19542-- Small Boat Harbor opposite Hamburg, IL Nov. 1977 19502 - - Wabash Railroad Bridges, Illinois River, Meredosia, and Valley City, IL - 1961 2,653,194 1961 1. Inactive. River declared nonnavigable by act of Mar. 2. Year authorized. 23, 1900. 3. Excludes $56,605 contributed funds. TABLE 14-D LAKES, LEVEES, AND RECREATIONAL FACILITIES Estimated See Required Total Estimated Section Estimated Non-Federal Cost (Date to in Text Project Name Federal Cost Cost Revision) 10. Meramec River Basin, MO Lakes: Meramec Park' 197,494,000 22,506,000 220,000,000 (1981) Union2 101,305,000 11,695,000 113,000,000 (1982) Pine Ford' 115,926,800 31,073,200 147,000,000 (1984) Irondale3 8,744,370 66,700,000 (1982) I-382 27,294,000 2,306,000 29,600,000 (1982) Recreation facilities: Angler-use sites2 2,140,000 2,140,000 4,280,000 (1982) 1. Separate reports are included herein. 2. See 1979 Annual Report for details. 3. See 1967 Annual Report for details. 14-13 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 14-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS Cost to Sep. 1985 For Last Full Report Operation Mo. and Yr. See Annual and Mo. and Yr. Project Deauthorized Report For: Construction Maintenance Completed Angler-use sites, Meramec Basin, MO Big Swan Drainage and Levee District, Illinois River, IL 1 Cache River Diversion, IL Cape Girardeau, MO, reaches Nos. 1, 3, and 4 Cape Girardeau, MO, No. 2 Carlyle Lake, IL Chouteau, Nameoki, and Venice Drainage and Levee District, IL Clear'Creek Drainage and Levee District, IL 2 Columbia Drainage and Levee District No. 3, IL Degognia and Fountain Bluff Levee and Drainage District, IL Dively Drainage & Levee District, IL East Cape Girardeau and Clear Creek Drainage District, IL Eldrid, IL Emergency bank protection for certain highway and railroad facilities at Price Landing, MO (see Flood Control Act of 1944)4 Emergency repairs to levees on Mississippi, Illinois, and Kaskaskia Rivers and flood fighting and rescue work (Sec. 5, Flood Control Act of 1941, as amended)4 Emergency protection for certain highway and railroad facilities at Chester, IL, bridge (Sec. 12, Flood Control Act of 1944) Emergency protection for Illinois approach, Chain of Rocks Bridge (Sec. 12, Flood Control Act of 1944) Fort Chartres and Ivy Landing Drainage District No. 5, IL Fort Chartres and Ivy Landing Drainage District No. 5 and Stringtown Drainage and Levee District No. 4, IL Grand Tower Drainage and Levee District, IL Harrisonville Levee and Drainage District IL Indian Creek Area, Illinois River, IL 1 Kaskaskia Island Drainage and Levee District, IL Keach Drainage and Levee District, IL' Lake Shelbyville, IL Levee Districts between Carlyle and New Athens, IL, Nos. 2, 5, 6, and 7 Levee Districts between Carlyle and New Athens, IL, Nos. 3, 4, 8, 10, and 13 Levee Districts between Cowden and Vandalia, IL Meredosia Lake and Willow Creek Drainage and Levee District, IL Miller Pond Drainage District, IL 1967 1953 1953 $ 2,837,114 22,000 5,157,805 42,819,400 185,700 4,984,500 2,818,000 5,889,500 1,720,000 1,920,600 35,464,295 1964 Oct. 1976 1955 1963 Oct. 1978 Nov. 1979 Nov. 1979 Nov. 1979 Oct. 1978 1959 1965 1981 1955 1964 1981 1959 1976 1963 19623 1950 1953 1952 1946 1970 1971 1959 1981 1959 1981 1979 1979 1978 1944 1955 55,415 1,033,279 50,000 25,000 1,154,800 Aug. 1981 1959 1976 1963 Oct. 1949 1951 Jan. 1952 Aug. 1945 1958 1959 Mar. 1981 1949 Sep. 1978 4,677,900 5,829,000 297,460 44,000,000 33,217,828 496,000 249,738 164,183 14-14 1944 1955 ST. LOUIS, MO, DISTRICT TABLE 14-E (Continued) OTHER AUTHORIZED FLOOD CONTROL PROJECTS Cost to Sep. 1985 For Last Full Report Operation Mo. and Yr. See Annual and Mo. and Yr. Project Deauthorized Report For: Construction Maintenance Completed Mississippi River at St. Louis, MO - 1980 79,265,166 - Jan. 1980 Mississippi River Agricultural Area No. 10, MO Nov. 1979 1967 - - Mississippi River Agricultural Area No. 12, MO - 1967 - - Mississippi River, Alton to Gale, IL, underseepage measures - -85,422 - Oct. 1962 North Alexander Drainage and Levee District, IL - 1957 939,569 - 1957 Prairie du Pont Levee and Sanitary District, IL 5 - 1970 6,005,127 - 1970 Prairie du Rocher and vicinity, IL - 1959 3,882,600 - 1959 Preston Drainage and Levee District, IL - 1959 1,866,910 - 1959 Richland Creek, IL - 1969 401,000 -- Riverland Levee District, MO Aug. 1977 19363 - - Scott County Drainage and Levee District, Illinois River, IL' - - - - Ste. Genevieve County Drainage and Levee District No. 1, MO Nov. 1977 19363 - - St. Louis County Drainage and Levee District No. 1, MO Nov. 1977 19363 - - Strington, Ft. Chartres and Ivy Landing, IL - 1957 2,123,700 - Aug. 1956 Union Lake, MOs - 1979 4,917,359 -- Urban areas at Alton, IL - 1960 192,000 -- Village of New Athens, IL - 1981 1,983,000 - Sep.1981 Valley City Drainage & Levee District, IL7 - 1967 91,952 - 1967 Wiedmer Chemical Drainage and Levee District, MO Nov. 1977 19363 - - 1. Projects authorized or modified by Flood Control Act of Oct. 23, 1962 (see H. Doc. 472, 87th Cong., 2d sess., for details). 2. Completed except for seepage control measures, which are inactive. 3. Year authorized. 4. Work complete, now performed under Public Law 99. 5. Includes $5,235,927 for previous project. 6. Includes $183,638 for definite project study under 1938 Flood Control Act. Includes Highway 185 funds. 7. Authorized by Chief of Engineers (Sec. 205, 1948 Flood Control Act, as amended). 14-15 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 14-F ACTIVE GENERAL INVESTIGATIONS (96x3121) Federal Cost Totals by Item and CWIS Number FY 85 Categories SURVEYS (Category 100) Flood Control Studies (120) Alexander and Pulaski Counties, IL -12217 $ 359 Cape Girardeau-Jackson Metropolitan Area, MO -12053 55 St. Louis Metropolitan Area, MO & IL -55040. 946,328 Ste. Genevieve, MO -80061 69,002 Richland Creek, IL -12174 12,773 Sub-total 1,028,517 Special Studies (140) Meramac R. Basin Water Supply, Mo. -14056 62,322 Miscellaneous Activities (170) Special Investigations -17250 23,987 Review of FERC Licenses -53857 9,632 Sub-total 33,619 Coordination Studies with Other Agencies (180) Dept. of Agric. - Soil Cons. Service -51840 2,058 Plan Assist to State of Ill. -14817 4,517 Plan Assist to State of Mo. -14829 4,313 Sub-total 10,888 TOTAL (Category 100) $1,135,346 COLLECTION AND STUDY OF BASIC DATA (Category 200) Flood Plain Management Services (250) -82030, and 82040 230,983 Hydrology Studies (260) -53820 16,838 TOTAL (Category 200) $ 247,821 CONTINUATION OF PLANNING & ENGINEERING (Category 400) St. Louis Harbor, Mo. & Il. -10184 569,068 Maline Creek, Mo. -12297 225,971 TOTAL (Category 400) $ 795,039 ADVANCE ENGINEERING AND DESIGN (Category 600) Eldred & Spankey D&LD, IL -00071 4,541 Hartwell D&LD, IL -00073 8,107 Hillview D&LD, IL- 00075 171,709 Meredosia Lake & Willow Creek D&LD, IL -00079 3,255 Meredosia, IL, and Meredosia, Willow Creek & Coon Run D&LD, IL -00069 21,758 Meremac River Basin, MO -75412 276,832 Nutwood D&LD, IL -00623 - 389 TOTAL (Category 600) $ 485,813 GRAND TOTAL GENERAL INVESTIGATIONS $2,664,019 14-16 GALVESTON, TX DISTRICT* Galveston District comprises drainage basins of all short streams arising in coastal plain of Texas and flowing into the Gulf of Mexico, including the entire basin of Buffalo Bayou, San Jacinto, San Bernard, Lavaca, Navidad, Mission, and Aransas Rivers. It embraces Agua Dulce, San Fernando, and Olmos Creek Basins draining into Baffin Bay, and coastal area south thereof to the Rio Grande and east of western Boundary of Starr County, Texas. It includes lower basins of major streams flowing into the Gulf of Mexico: Sabine River, Texas and Louisiana, downstream from U.S. Highway 190 crossing at Bon Wier, Texas; Neches River downstream from Town Bluff gaging station; Trinity River downstream from Texas State Highway 19 crossing at Riverside, Texas; Brazos River downstream from confluence with Navasota River; Colorado River downstream from northern boundary of Fayette County; Guadalupe River downstream from confluence with San Marcos River; San Antonio River downstream from confluence with Escondido Creek; Nueces River downstream from confluence with Frio and Atascosa River. IMPROVEMENTS Navigation 1. Aquatic Plant Control (Southwestern Division) ................ 2. Brazos Island Harbor, TX ............. 3. Corpus Christi Ship Channel, TX ........ 4. Freeport Harbor, TX .................. 5. Galveston Harbor and Channel, TX ...... 6. Gulf Intracoastal Waterway between Apalachee Bay, FL, and the Mexican Border ............................. 7. Houston Ship Channel, TX ............. 8. Matagorda Ship Channel, TX ........... 9. Sabine-Neches Waterway, TX........... 10. Texas City Channel, TX .............. 11. Trinity River and Tributaries, TX ........ 11A. Anahuac Channel, TX ................. 11B. Channel to Liberty, TX ................ 11C. Wallisville Lake, TX .................. 12. Reconnaissance and Condition Surveys .. . 13. Navigation Work Under Special Authorization ........................ Beach Erosion Control 14. Corpus Christi Beach, TX .............. 15. Beach Erosion Work Under Special Authorization ........................ Flood Control 16. Arroyo Colorado, Rio Hondo, TX ......... 17. Buffalo Bayou and Tributaries, TX, ...... Page Flood Control (cont) 18. Port Arthur and Vicinity, TX 15-2 Hurricane-Flood Protection ............. 15-2 19. Taylors Bayou, TX ................... 15-2 20. Texas City and Vicinity, TX, 15-3 Hurricane-Flood Protection ............. 15-3 21. Vince and Little Vince Bayous, TX ...... 22. Inspection of Completed Flood Control Works ............................. 15-4 23. Flood Control Work Under Special 15-5 Authorization ....................... 15-6 15-6 15-6 15-7 15-7 15-7 15-8 General Investigations 24. Surveys ............................ 25. Advance Engineering and Design ........ 26. Planning and Engineering ............. 27. Collection and Study of Basic Data ....... 15-8 Tables Table 15-A 15-8 Table 15-B Table 15-C 15-8 Table 15-D 15-8 Table 15-E 15-9 15-9 Table 15-F Table 15-G Table 15-H Table 15-I Page 15-9 15-9 15-10 15-10 15-10 15-10 15-11 15-11 15-11 15-11 Cost and Financial Statement ... 15-12 Authorizing Legislation ........ 15-15 Other Authorized Navigation Projects ...................... 15-26 Other Authorized Flood Control Projects ...................... 15-26 Total Cost of Existing Projects ...................... 15-27 Channel Dimensions ........... 15-28 Channel Dimensions, GIWW Tributary Channels ............ 15-31 Dredging Operations ........... 15-33 Jobs Act ..................... 15-35 15-1 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Navigation 1. AQUATIC PLANT CONTROL (SOUTHWESTERN DIVISION) 1965 ACT Location. Navigable waters, tributary streams, connecting channels, and other allied waters in Texas and the Sabine River Watershed of Louisiana. Previous project. For details see page 699 of Annual Report for 1963. Existing project. A comprehensive project to provide for control and progressive eradication of water-hyacinth, alligatorweed, Eurasian watermilfoil, and other obnoxious aquatic plant growths, from navigable waters, tributary streams, connecting channels, and other allied waters in Texas in the combined interest of navigation, flood control, drainage, agriculture, fish and wildwife conservation, public health, and related purposes, including continued research for development of the most effective and economic control measures. Eradication work continues in the Nueces River Basin, North Coastal Area, Guadalupe River Basin, Sabine River Basin, Trinity River Basin, Cypress Creek Basin, Neches River Basin, South Coastal Area, San Jacinto River Basin and Rio Grande Basin. Planning, to include hydrilla control in the existing program, is underway. Estimated cost for new work is $2,019,000 Federal (Corps) and $693,000 non-Federal. Local cooperation. Sec. 302, 1965 River and Harbor Act, applies. Operations during fiscal year. Eradication work by the State of Texas continued. A supplemental General Design Memorandum and environmental assessment for the inclusion of submerged species, hydrilla and Eurasian watermilfoil, were completed. Monitoring of the biological control nursery areas was continued during the year. 2. BRAZOS ISLAND HARBOR, TX Location. At extreme south end of coast of Texas, about 7 miles north of mouth of Rio Grande and about 5 miles east of Brownsville, Texas. (See National Ocean Survey Chart 11301.) Previous project. For details see page 1017 of Annual Report for 1932. Existing project. Provides for channel dimensions in various sections of the waterway as shown in Table 15F. Project also provides for dual jetties at the gulf entrance, a north jetty 6,330 feet long, a south jetty 5,092 feet long, and 1,000-foot extension to existing north jetty and for maintenance of 3rd fishing harbor constructed by local interests. Under ordinary conditions, mean tidal range is about 1.5 feet, and extreme range is about 2 feet. All depths refer to mean low tide. To some extent, height of tides is dependent on the wind, and during strong "northers" in winter season, water surface in southern end of Laguna Madre may be raised 4 feet or more above mean low tide in the gulf. Widening Brownsville Channel from Goose Island to Brownsville turning basin and deepening southeast corner of Brownsville turning basin to 36 feet was completed in April 1980. The 1,000-foot extension to existing north jetty was placed in the inactive category in 1980. (See Table 15-E for total cost of existing project to September 30, 1985.) Local cooperation. Complied with. Terminal facilities. Numerous terminal facilities for bulk and liquid cargo are available. (See Port Series No. 26, revised 1980.) Facilities are adequate for existing commerce. Operations during fiscal year. Routine maintenance. 3. CORPUS CHRISTI SHIP CHANNEL, TX Location. This project, formerly known as the Port Aransas-Corpus Christi Waterway, Texas, was changed to Corpus Christi Ship Channel, Texas, by 1968 River and Harbor Act. This is a consolidation of old improvements of Port Aransas, Texas, and channel from Aransas Pass to Corpus Christi, Texas. Aransas Pass is on southern portion of Texas Coast, 180 miles southwest of Galveston and 132 miles north of mouth of Rio Grande. Aransas Pass connects Corpus Christi Bay with the gulf. Waterway extends from deep water in the gulf through Aransas Pass jettied entrance, thence westerly 20.75 miles to and including a turning basin at Corpus Christi, thence westerly 1.75 miles through Industrial Canal to and including turning basin at Avery Point, thence westerly 4.25 miles to and including a turning basin near Tule Lake, thence northwesterly 1.8 miles to and including a turning basin at Viola, Texas. (See National Ocean Survey Charts 11308, 11309, 11311, and 11314.) Previous project. For details see page 1861 of Annual Report for 1915. Existing project. (See Table 15-F for existing project dimensions provided for in various channels and basins comprising this waterway.) Project also provides for two rubblestone jetties at Aransas Pass entrance, extending into the gulf from St. Joseph and Mustang Islands, project lengths of which are 11,190 and 8,610 feet, respectively. Project further provides for a stone dike on St. Joseph Island about 20,991 feet long, connecting with north jetty and extending up this island to prevent a channel being cut around jetty. Project also provides for a breakwater at the entrance to the harbor area at Port Aransas, and for the realignment of the existing 12-foot by 100-foot project channel to Port Aransas. The breakwater consists of two overlapping sections. The one on the east side of the realigned entrance channel has a length of 830 feet and the second, located on the west side of the entrance channel, has a length of 1,290 feet. The channel to Port Aransas was relocated in the 300-foot clear distance between the overlapping sections. The portion of the channel remaining inside the breakwaters was widened to 150 feet. Under ordinary conditions, mean tidal range at Aransas Pass is about 1.1 feet and extreme range about 2 feet, and at Corpus Christi mean range about 1 foot and extreme about 1.5 feet. Heights of tides are dependent largely on strength and directions of winds, and during strong "northers" in the winter season water surface may be depressed as much as 3 feet below mean low tide. Estimated cost for new 15-2 GALVESTON, TEXAS DISTRICT work is: Federal (Corps) $69,424,515, including $456,515 for Port Aransas Breakwaters and exclusive of amount expended on previous projects; and non-Federal $17,630,068 (includes $768 for Pbrt Aransas Breakwaters) including $6,297,840 contributed funds and value of useful work performed, $3,320,228 lands, $6,027,000 relocations and $1,985,000 other cost. (October 1, 1985 base price.) The Port Aransas-Corpus Christi 40-foot project was completed in 1966. The Jewel Fulton Canal was completed in 1963. The Port Aransas Breakwaters were completed in July 1973. Work remaining consists of deepening deepdraft channels to 45 feet from Beacon 82 through Viola Turning Basin; widening of channels and basins; and constructing a mooring area at Port Ingleside with dolphins. Entrance and jetty channels have been dredged to project depth and width, and dredging of channel from Harbor Island to Beacon 82 at 45-foot depth has been completed. Initial mooring dolphins were completed in May 1979. Disposal area levees, Area 1 and Rincon were completed in August 1984. Disposal area levees, South Shore, were completed in September 1984. (See Table 15-E for total cost of existing project to September 30, 1985.) Local cooperation. Fully complied with except for provisions of Sec. 101 of 1968 River and Harbor Act and Sec. 124 of Water Resources Development Act of 1976. Terminal facilities. Terminal facilities on Harbor Island at head of Aransas Pass, Ingleside, Corpus Christi, La Quinta, Avery Point, and Viola, are considered adequate for existing commerce. (See Port Series, No. 25, revised 1979, Corps of Engineers.) Operations during fiscal year. New Work: Construction of disposal area levees, Area 1 and Rincon, financially completed at a fiscal year cost $154,229. Construction of disposal area levees, South Shore, financially completed at a fiscal year cost $316,560. Contract for vegetation establishment, South Shore levees, cost $68,719. (See Table 15-H for dredging operations.) Maintenance: Routine maintenance. (See Table 15-H for dredging operations.) 4. FREEPORT HARBOR, TX Location. Formed by improvement of Brazos River, Texas, from mouth to about 6 miles upstream to Freeport, Texas. (See National Ocean Survey Charts 11321 and 11322.) Previous projects. For details see page 1860 of Annual Report for 1915, and page 872 of Annual Report for 1938. Existing project. Existing project dimensions for various channels and basins are shown in Table 15-F on channel dimensions at end of chapter. Existing project also provides for: Dual jetties and a diversion canal for the Brazos River, including a dam, a lock in the dam and necessary auxiliary equipment. Also provides for rehabilitation of southwest jetty and the relocation of the northeast jetty (about 640 feet to the northeast); realignment of the channel between the Jetty Channel and Brazosport Turning Basin; realignment of the channel between Brazosport Turning Basin and Upper Turning Basin; relocation of Upper Turning Basin; and public use facilities adjacent to the Freeport Jetties. The 30-foot channel from Upper Turning Basin to Stauffer Chemical Plant, including the turning basin, was deauthorized by Sec. 12 of PL 93-251. Construction of lock in diversion dam at local expense is considered inactive. The 38-36 foot project was completed in 1962. Work remaining consists of realigning, deepening and widening the Outer Bar and Jetty Channels; relocating the northeast jetty; rehabilitating the southwest jetty; realigning and deepening the harbor channel between the jetty channel and the Upper Turning Basin; relocating and enlarging the Upper Turning Basin; constructing a turning point near the northwesterly end of the jetty channel; enlarging Brazosport Turning Basin; deepening Brazos Harbor Channel; and enlarging and deepening Brazos Harbor Turning Basin. Preconstruction planning on this remaining work is complete. (See Table 15-E for total cost of existing project to September 30, 1985.) Under ordinary conditions mean tidal range is about 1.5 feet and extreme range is about 2.5 feet. Except under extreme conditions, rises on river and in diversion channel do not cause greater variations in water surface than those caused by tidal action. Estimated cost of new work is: $85,449,000 Federal (Corps); and $10,877,000 non- Federal, including $1,118,303 contributed funds, $360,249 contributed work, $6,198,448 lands, $2,668,000 levees and spillways, and $532,000 relocations. (October 1, 1985 base price.). Local cooperation. Fully complied with except for Section 101 of River and Harbor Act of 1970. River and Harbor Act of 1970 requires local interests provide necessary lands, easements, and rights-of-way required for public use facilities; and when the appraised value of land, easements, and rights-of-way amounts to less than 50 percent of the total first cost of the development, make additional contributions sufficient to bring the non- Federal share to at least that level. The cash contribution is presently estimated at $360,000 which combined with land, estimated at $695,000 is 50 percent of the cost of public use facilities. Cash contribution at time of authorization estimated at $95,000 in addition to providing land estimated at $70,000. Terminal facilities. Small privately owned wharves, two oil docks, one acid dock, two shell unloading docks and one caustic dock. Brazos River Navigation District has one large dock with four transit sheds over rail facilities permitting all-weather work. Facilities considered adequate for existing commerce. (See Port Series No. 26, revised 1980, for additional facilities.) Operations during fiscal year. New Work: Preconstruction planning continued on the 45-foot project. Maintenance: Routine maintenance. Jetty repairs cost $370,258. (See Table 15-H for dredging operations.) 5. GALVESTON HARBOR AND CHANNEL, TX Location. A consolidation of authorized improvements at Galveston, Texas, which includes projects formerly identified as Galveston Harbor, Texas; Galveston Channel, Texas; and Galveston seawall extension. Entrance to 15-3 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Galveston Harbor is on Gulf of Mexico on the northern portion of the Texas Coast. Galveston Channel extends from a point in Galveston Harbor between Bolivar Peninsula and Fort Point to and along wharf front of Galveston, Texas, and is about 5 miles long and 1,200 feet wide. (See National Ocean Survey Chart 11324/5.) Previous projects. For details see page 1854 of Annual Report for 1915. Existing project. Provides for channel dimensions in sections of the waterway shown in Table 15-F. Also provided are: two rubble-mound jetties, the south one extending from Galveston Island and the north one extending from Bolivar Peninsula, for distances of 35,900 feet and 25,907 feet, respectively, into the Gulf of Mexico; a concrete seawall from the angle at Sixth Street and Broadway, in the city of Galveston, to the south jetty, and a 16,300-foot extension of the concrete seawall in a southwesterly direction from 61st Street; for 11 groins along the gulf shore between 12th Street and 61st Street; and for maintenance of seawall from the angle at 6th Street and Broadway to the south jetty. Under ordinary conditions, mean tidal range in Galveston Harbor is 1.6 feet on outer bar and 1.4 feet on inner bar with extreme ranges of 2.3 and 2.1 feet, respectively. Mean range in Galveston channel is about 1.3 feet and extreme range about 2 feet under ordinary conditions. Height of tides in both Galveston harbor and channel is dependent largely on the wind, and during strong "northers" water surface may be depressed 2 feet below mean low tide. Existing project is complete. Dredging of Galveston channel to 36 foot depth was completed in November 1966. Dredging of the realigned entrance and Outer Bar Channel was completed in October 1967. Rehabilitation of the Beach Front Groins was completed June 1970. Dredging of Galveston channel to 40 feet was completed in March 1976. (See Table 15-E for total cost of existing project to September 30, 1985.) Local cooperation. Complied with. Terminal facilities. None on Galveston Harbor, which is entrance channel leading to terminal facilities on Galveston, Texas City, and Houston Ship Channels. Galveston Channel terminal facilities are mostly on south side of channel. Principal wharves, owned by the city of Galveston, extend from 10th to 41st Street (see Port Series No. 23, revised 1979). A containership terminal equipped with a crane capable of stacking containers three units high on the deck of any normal containership has been completed and placed into operation by the city of Galveston at Piers 10 and 11, on the south side of Galveston Channel. The city of Galveston has also placed into operation a barge terminal equipped with two 35-ton and one 5-ton cranes for loading and unloading barges on Lash and Seabee ships at Pier 35 and a docking and holding area for Lash and Seabee barges on Pelican Island, directly across the channel from Piers 35 and 36. Present facilities are considered adequate for existing commerce. Operations during fiscal year. Routine maintenance. (See Table 15-H for dredging operations.) 6. GULF INTRACOASTAL WATERWAY BETWEEN APALACHEE BAY, FL, AND MEXICAN BORDER (GALVESTON DIST.) Location. Extends from a point on Sabine River about 3 miles below Orange, Texas, to Brownsville, Texas, about 421 miles; a navigation channel, about 7 miles long, in Colorado River, extending from Matagorda, Texas, to Gulf of Mexico; a tributary channel in San Bernard River, extending from Intracoastal Waterway crossing to State highway bridge some 30 miles above crossing; a tributary channel in Colorado River extending from Intracoastal Waterway upstream 15.5 miles; a tributary channel extending about 14 miles from Intracoastal Waterway to Palacios, Texas; a tributary channel extending about 2 miles from Intracoastal Waterway to Rockport, Texas; a tributary channel extending about 6 miles from Intracoastal Waterway near Port Aransas, Texas, to town of Aransas Pass, Texas; a tributary channel about onefourth mile long extending from Intracoastal Waterway near Port O'Connor, Texas, into Barroom Bay; a tributary channel extending about 38.8 miles from Intracoastal Waterway via Seadrift to a point in Guadalupe River 5.5 miles below Victoria, Texas; a harbor of refuge for small craft at Seadrift; a channel extending from gulf to Port Mansfield, Texas, about 11 miles; and a tributary channel in Arroyo, Colorado extending from Intracoastal Waterway to a point near Harlingen, Texas, about 31 miles; side channels in vicinity of Port Isabel, Texas, and a small boat basin at Port Isabel, Texas, and a tributary channel extending from Intracoastal Waterway main channel at a point in West Galveston Bay into Offatts Bayou about 2.2 miles with a west turnout (wye connection) 12 feet deep and 125 feet wide between Offatts Bayou Channel and the Gulf Intracoastal Waterway. (See National Ocean Survey Charts 11302, 11303, 11305, 11306, 11308, 11309, 11314, 11315, 11317, 11319, 11322, 11326, and 11331.) Previous project. For details see page 1859 of Annual Report for 1915. (West Galveston Bay and Brazos River Canal, Texas.) Existing project. Existing project dimensions provided for in main channel of waterway: A channel 12 feet deep (below mean low tide) and 125 feet wide from the Sabine River to Brownsville, Texas. Relocation of channel 12 feet deep by 125 feet wide in Matagorda Bay, miles 454.3 to 471.3, relocation of channel 12 feet deep by 125 feet wide in Corpus Christi Bay, miles 539.4 to 549.7 (mileage is west of Harvey Lock, Louisiana); and alternate channel, 12 feet deep (below mean low tide) and 125 feet wide via Galveston Channel and Galveston Bay to the Galveston causeway; maintenance of existing channel 12 feet deep by 125 feet wide through Lydia Ann Channel, between Aransas Bay and Aransas Pass; provisions of such passing places, widening of bends, locks and guard locks, railway bridges over artificial cuts as are necessary, and the tributary channels shown in tabulation. The authorized channel 16 feet deep and 125 feet wide from Sabine River to Houston Ship Channel and the 9 feet deep and 100 feet wide channel from mile 8.2 to mile 13.2 in Chocolate Bayou are inactive. (See Table 15-G on existing project dimensions provided for in tributary channels.) 15-4 GALVESTON, TEXAS DISTRICT Removal of the railroad bridge across the canal at Mud Bayou was completed and operation and care of the facility was discontinued on April 14, 1969. Deepening the existing 6 foot by 60 foot side channels at Port Isabel to 12 feet was completed February 22, 1972, Offatts Bayou channel was completed January 1974. Relocation of main channel across Corpus Christi Bay was completed in September 1976. The 14 foot by 175 foot Channel to Aransas Pass was completed in April 1979. Dredging Chocolate Bayou Channel was completed in January 1981. Construction of a saltwater barrier in Chocolate Bayou was completed in February 1981. The 12 foot by 125 foot channel relocation route in Matagorda Bay has been placed in the inactive category. The Harbor of Refuge at Seadrift, Texas, has been placed in the inactive category. Active authorized work remaining consists of the following: construction of jetties at mouth of Colorado River; dredging a navigation channel from gulf to the GIWW; constructing a turning basin at Matagorda, Txas; construction of a diversion dam and channel; construction of an oyster cultch; and recreation facilities. (See Table 15-E for total cost of existing project to September 30, 1984.) Mean tidal variation is 0.5 foot at Orange, 1 foot at Port Arthur, 1.3 feet in Galveston Bay, 1.5 feet at Freeport, 1 foot in Matagorda Bay, 1 foot in San Antonio Bay, 1 foot at Corpus Christi, 1.5 feet at Port Isabel, and 1.5 feet at Brownsville. Extreme ranges of tide under ordinary conditions are 1 foot at Orange, 1.5 feet at Port Arthur, 2 feet in Galveston Bay, 2 feet at Freeport, 1.5 feet in Matagorda and San Antonio Bays, 1.5 feet at Corpus Christi, 2 Feet at Port Isabel, and 1.5 feet at Brownsville. Height of tides is dependent largely on wind. Strong north winds have depressed water surface as much as 2 feet below mean low tide. Estimated cost for new work is: $76,364,000, Federal (Corps), including $8,414 for Port Isabel Side Channel, $46,559 for Port Isabel Small Boat Basin, $356,466 for Offatts Bayou, and $658,573 for Channel to Aransas Pass and excluding expenditures on previous projects; non-Federal $17,661,174 ($395,000 voluntarily expended on Gulf Intracoastal Waterway, $46,559 contributed funds for Port Isabel, $49,665 contributed funds for Offatts Bayou, $347,950 contributed funds for channel to Aransas Pass, $3,658,000 contributed funds for Mouth of Colorado River, $5,666,000 lands for Gulf Intracoastal Waterway, $11,000 lands for Port Isabel, $4,242,000 relocations for Gulf Intracoastal Waterway and $3,245,000 other costs Gulf Intracoastal Waterway). (October 1, 1985 base price.) Local cooperation. Fully complied with except for inactive portions, and provisions of Section 101, 1968 River and Harbor Act. Non-Federal contributions are $395,000 for Gulf Intracoastal Waterway, $46,559 for Port Isabel, rxas, $49,665 for Offatts Bayou, Texas, $347,950 for Channel to Aransas Pass, Texas, and $3,658,000 for Mouth of Colorado River, Texas. Aermina facilities. There are terminal facilities at Aransas Pass, Port Arthur, Galveston, Port Isabel, and Brownsville. See Port Series No. 22 (revised 1981), Port Series No. 23 (revised 1979), Port Series No. 25 (revised 1979) and Port Series No. 26 (revised 1980), Corps of Engineers. Local interests constructed terminal facilities at Port Mansfield and Port Harlingen. There are numerous privately owned piers and wharves along the waterway. A 330-foot navigation district owned general cargo dock, a 770-foot private dock and a 760-foot private timber trestle have recently been completed at the upper end of the Channel to Victoria. Facilities are adequate for existing commerce. Operations during fiscal year. New work: Contract for construction of jetties at the Mouth of the Colorado River continued at a fiscal year cost of $8,434,230. Maintenance: The Brazos River Floodgates were operated and maintained at a cost of $507,599, including engineering and design, supervision and administration, and real estate activities. In addition, rehabilitation of guidewalls and mooring facilities cost $46,462. The Colorado River Locks were operated and maintained at a cost of $689,122, including engineering and design and supervision and administration. In addition, repairs of the guidewalls cost $297,946. Erosion control on channel to Victoria cost $57,980. (See Table 15-H for dredging operations.) 7. HOUSTON SHIP CHANNEL, TX Location. Connects Galveston Harbor, at a point opposite Port Bolivar, with city of Houston, Texas, extending 50 miles northwesterly across Galveston Bay through San Jacinto River and Buffalo Bayou to a turning basin at head of Long Reach with light-draft channel 7 miles long from turning basin to Main Street, Houston. (See National Ocean Survey Charts 11324/5, 11327, 11328, and 11329.) Previous project. For details see page 1856 of Annual Report for 1915. Existing project. Provides for channel dimensions in sections of the waterway shown in Table 15-F. Also provides for certain cut-offs, for easing sharp bends, an earthen dam across the upper end of Turkey Bend, and for off-channel silting basins as deemed necessary by the Chief of Engineers. Construction of 26,000 linear feet of pile dike to protect the channel in upper Galveston Bay was deauthorized by Sec. 12 of PL 93-251. The 40-foot project was completed in March 1966. Dredging a channel in Greens Bayou to Mile 1.57 was completed in 1970. Only work remaining is dredging Greens Bayou, Mile 1.57 to Mile 2.73, which is in the inactive category. (See Table 15-E for total cost of existing project to September 30, 1985.) Mean tidal range under ordinary conditions is 0.6 foot to 1.3 feet in lower part of Galveston Bay; 0.6 foot to 1.3 feet in upper bay; and 0.5 to 1 foot in San Jacinto River and Buffalo Bayou. Extreme ranges under ordinary conditions are about 2 feet, 1.2 feet and 1 foot, respectively. Freshets caused rises of over 12 feet in Buffalo Bayou; however, this condition has not occurred since completion of Addicks and Barker Dams for flood control on upper watershed of Buffalo Bayou. Height of tides is dependent largely on the wind, and during strong "northers" in winter season the water surface may be depressed 2 feet below mean low tide. Local cooperation. Complied with except for inactive portions of Greens Bayou. 15-5 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Terminal facilities. City of Houston and Port of Houston Authority operate modern terminals which supplement privately owned wharves, piers, and docks, as described in Port Series No. 24 (revised 1980), Corps of Engineers. Facilities are considered adequate for existing commerce. Operations during fiscal year. Routine maintenance. Rehabilitation of disposal area levees cost $47,777. (See Table 15-H for dredging operations.) 8. MATAGORDA SHIP CHANNEL, TX Location. This is a consolidation of shallow draft channel improvements of "Channel from Pass Cavallo to Port Lavaca, Texas" and deep draft channel improvements authorized under "Matagorda Ship Channel, Texas." Bar at Pass Cavallo is 125 miles southwest of Galveston entrance and 54 miles north of Aransas Pass. It connects Matagorda Bay with the gulf. Project extends across Matagorda Bay and Lavaca Bay to towns of Port Lavaca and Point Comfort. These two towns are on opposite sides of Lavaca Bay and both are about 26 miles northwest from Pass Cavallo. (See National Ocean Survey Chart 11316.) Existing project. Existing project dimensions provided for in various channels and basins are listed in Table 15-F on channel dimensions. Project also provides for dual jetties at entrance, south jetty extending 6,000 feet to 24-foot depth in the gulf and north jetty extending 5,900 feet to 24-foot depth. Under ordinary conditions mean tidal range is about 1 foot and extreme range about 2 feet. Height of tide is dependent largely on the wind, and during strong "northers" in winter season the water surface may be depressed 2 feet below mean low tide. Estimated cost for new work is: $18,058,777 Federal (Corps), and $12,859,000 non-Federal, including $12,259,619 contributed funds, $182,000 for lands, $220,000 for relocations, and $196,581 other costs. The project was completed in March 1967 Local cooperation. Fully complied with. Terminal facilities. Privately owned facilities at Port Lavaca, municipally owned facilities at mouth of Lynn bayou, privately owned and publicly owned facilities at Point Comfort, Texas. These facilities are considered adequate for present commerce. Facilities at Point Comfort consist of a channel, turning basin with wharfs, oil dock and loading equipment, all owned by Aluminum Company of America; and a wharf built by local interest at Point Comfort turning basin. Operations during fiscal year. Routine maintenance. (See Table 15-H for dredging operations.) 9. SABINE-NECHES WATERWAY, TX Location. This is a consolidation of old improvements of "Harbor at Sabine Pass and Port Arthur Canal" and "Sabine-Neches Canal, including Sabine River to Orange and Neches River to Beaumont, Texas." Sabine Pass is on Gulf of Mexico about 58 miles east of Galveston and 280 miles west of Southwest Pass, Mississippi River. It connects Sabine Lake with gulf. Port Arthur canal extend- 7 miles from near upper end of Sabine Pass to Port Arthur docks at mouth of Taylors Bayou. Near its upper end, Sabine-Neches canal joins and extends to mouths of Neches and Sabine Rivers. Waterway next extends up Neches River to Beaumont and up Sabine River to Orange. (See National Ocean Survey Charts 11341, 11342, and 11343.) Previous projects. For details see page 1863 of Annual Report for 1915, page 985 of Annual Report for 1916, and page 873 of Annual Report for 1926. Existing project. Existing project dimensions provided for in various channels and basins are set forth in Table 15-F on channel dimensions. Project also provides for two stone jetties at Sabine Pass entrance from the gulf, western jetty to be 21,905 feet long and eastern jetty 25,310 feet long. Project further provides for removal of guard lock in Sabine-Neches Canal, construction of suitable permanent protective works along Sabine Lake frontage owned by city of Port Arthur to prevent dredged material from entering Sabine Lake and to prevent erosion of material deposited, reconstruction of Port Arthur Bridge, and relocation of Port Arthur field office. Mean tidal variation at entrance is about 1.5 feet, at Port Arthur about 1 foot, and at Orange and Beaumont about 0.5 foot. Prolonged north winds during winter season have depressed water surface as much as 3.4 feet below mean low tide while tropical disturbances have caused heights as much as 8 feet above mean low tide. Existing project is complete except for inactive portions. Removal of obstructive bridge at Port Arthur was completed May 1969. The high level fixed bridge across Sabine-Neches Canal was completed October 1970. Deepening project to 40 feet was completed April 1972. (See Table 15-E for total cost of existing project to September 30, 1985.) Local cooperation. Complied with except for inactive portions. Terminal facilities. See volume 2, Port Series No. 22 (revised 1981), Corps of Engineers. Facilities are considered adequate for present commerce. Operations during fiscal year. Routine maintenance. (See Table 15-H for dredging operations.) 10. TEXAS CITY CHANNEL, TX. Location. Texas City is on the mainland of Texas on west side of Galveston Bay, about 10 miles northwest of city of Galveston. (See National Ocean Survey Charts 11324/5.) Previous projects. For details see page 1856 of Annual Report for 1915. Existing project. Provides for channel 40 feet deep, 400 feet wide and about 6.75 miles long, from Bolivar Roads to a turning basin at Texas City, 40 feet deep, 1,000 feet to 1,200 feet wide and 4,253 feet long; and an Industrial Canal, 40 feet deep and 300-400 feet wide extending a distance of 1.7 miles southwestward from the south end of Texas City Turning Basin, and a turning basin, 40 feet deep, 1,000 feet wide and 1,150 feet long. Project also provides for easing the approach to the turning basin; a pile dike 28,200 feet long, parallel to and north of the channel; and a rubble-mound dike, 27,600 feet long, along the southerly side of the pile dike. 15-6 GALVESTON, TEXAS DISTRICT The 40-foot channel was completed in June 1967. Widening the Texas City Turning Basin; realigning the Texas City Turning Basin to a location 85 feet easterly from its present position; and enlargement through widening and deepening of the Industrial Canal and basins was initiated in July 1980 and completed in June 1982. The only work remaining is deferred construction consisting of widening the Industrial Canal from 250 feet to 300 feet at 40 foot depth. (See Table 15-E for total cost of existing project to September 30, 1985.) Under ordinary conditions mean tidal range is about 1.3 feet and extreme range is about 2 feet. Height of tide is dependent largely on the wind and during strong "northers" water surface may be depressed 2 feet below mean low tide. Estimated cost for new work is $14,300,000 Federal (Corps), excluding expenditures on previous projects, and $1,793,700 non-Federal, including $127,741 contributed funds, $248,000 work contribution, $427,959 lands, $984,000 levees and spillways and $6,000 for removal of barge mooring facilities from Snake Island. Local cooperation. Fully complied with. Terminal facilities. Privately owned terminal facilities are on the mainland at inner end of this channel and are considered adequate for existing commerce. A deep-draft channel and turning basin extend about 1.9 miles southwestward from south end of Texas City Turning Basin have been constructed by local interests. See Port Series No. 23 (revised 1979), Corps of Engineers. Operations during fiscal year. Maintenance: Levee rehabilitation cost $25,000. (See Table 15-H for dreding operations.) 11. TRINITY RIVER AND TRIBUTARIES, TX Location. The main stem of the Trinity River is formed at Dallas by the confluence of the West Fork and the Elm Fork at river mile 505.5. The mouth of the Trinity is about one-half mile west of Anahuac, Texas. (See Geological Survey base map, Texas, scale 1:500,000.) Previous project. For details of abandoned locks and dam construction see page 986 of Annual Report for 1932. Existing project. See individual detailed reports on Anahuac Channel, Channel to Liberty and Wallisville Lake. Project includes the existing Federal project designated as "Mouth of Trinity River, Texas," which was completed in 1907 at a cost of $80,000 (no cost to local interest). Project is not being maintained. (See Table 15-E for total cost of existing project to September 30, 1985.) Local cooperation. See individual detailed reports on Channel to Liberty and Wallisville Lake. There is no local cooperation required for Anahuac Channel. Terminal facilities. Privately owned wharves and piers at Anahuac, Moss Bluff, Wallisville, and Liberty, Texas, are adequate for existing commerce. 11A. ANAHUAC CHANNEL, TX Location. Extends from 6-foot depth in Galveston Bay to Anahuac, Texas, opposite mouth of Trinity River 38 miles north of Galveston, Texas. (See National Ocean Survey Chart 11323.) Existing project. No project dimensions authorized by 1905 River and Harbor Act. A 6- by 80-foot channel, 16,000 feet long was dredged in 1905. At present a 6- by 100-foot channel is maintained. Under ordinary conditions tidal range is 0.6 to 1.2 feet. Height of tide is dependent largely on wind. Strong north winds depress water surface 1.5 feet below mean sea level. Latest published map is in House Document 440, 56th Congress, 1st Session. Project was completed in 1911. Local cooperation. None required. Terminal facilities. Privately owned wharves and piers are the only terminal facilities at Anahuac. Operations during fiscal year. Routine maintenance. An FY 1984 contract for dredging Anahuac Channel was financially completed at a fiscal year cost of $22,496. Mobilization cost on dredging contract awarded late in fiscal year was $8,860. 11B. CHANNEL TO LIBERTY, TX Location. Improvement is located in Galveston Bay and tidal reach of lower Trinity River. (See Geological Survey Maps for Anahuac, Cove, Moss Bluff, and Liberty, Texas.) Previous projects. For details see page 986 of Annual Report for 1932. Existing project. Provides for a 6-foot channel from Anahuac to 'Liberty which was completed in 1925. A navigable channel from the Houston Ship Channel near Red Fish Bar in Galveston Bay to Liberty, Texas, with depth of 9 feet and width of 150 feet, extending along the east shore of Trinity Bay to the mouth of the Trinity River at Anahuac, thence in the river channel to a turning basin at Liberty, Texas, and a protective embankment along the west side of the channel in Trinity Bay. The 6-foot Channel to Liberty was completed in 1925. The 9-foot Channel to Liberty has been dredged from junction with Houston Ship Channel to a point one mile below Anahuac, Texas. Work remaining consists of dredging a 9- by 150-foot channel from one mile below Anahuac, Texas to Liberty, Texas. Local cooperation. Fully complied with for portion of "Channel to Liberty" between Houston Ship Channel and 1 mile below Anahuac, Texas, as required by 1946 River and Harbor Act (H. Doc. 634, 79th Cong., 2nd Sess.), but not complied with for remaining portion of "Channel to Liberty" as required by River and Harbor Act of 1945 (H. Doc. 403, 77th Cong., 1st Sess.) at an estimated total cost of $550,000, of which $460,000 is for lands and rights-ofway and $90,000 for pipeline relocations for 9- by 150-foot channel. Terminal facilities. Privately owned wharves and docks at Anahuac, Wallisville, Texas Gulf Sulphur Co.'s slip, Moss Bluff and Liberty, Texas, are adequate for existing commerce. Operations during fiscal year. Routine maintenance. Mobilization cost on dredging contract awarded late in fiscal year was $24,440. 15-7 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 11C. WALLISVILLE LAKE, TX Location. Dam is at river mile 3.9, about 4 miles northwest of Anahuac, Texas. (See National Ocean Survey Chart 11323.) Existing project. Provides for construction of a dam and overflow spillway approximately 8 miles long to prevent salinity intrusion and create a 5,600-acre reservoir. The maximum pool elevation will be 4 feet above National Geodetic Vertical Datum. Project provides for an 84 foot by 600-foot navigation lock to facilitate navigation on Channel to Liberty. The sill has a depth of minus 16 feet below National Geodetic Vertical Datum. Project also provides for two recreational areas. Dam controls a drainage area of 1,262 square miles below Livingston Dam (non-Federal project at channel mile 99.2) and has a storage capacity of 58,000 acre-feet. Under ordinary conditions mean tidal range in bay is from 0.6 foot to 1.2 feet. Height of tide is dependent largely on wind. Strong northerly winds depress water surface 1.5 feet below mean sea level. Tobtal estimated cost of authorized project is $67,700,000 Federal (Corps). (October 1, 1985 base price.) A contract for construction of access road, Big Hog intake structure, intake canal and access bridge was completed in October 1968. Work started in July 1970 on construction of the lock and dam, roads, diversion channel, and navigation channel. Work was suspended in February 1973 because of an injunction halting construction. Protective work on the lock and dam was permitted and was completed in April 1973. An exception to the injunction was granted for plugging oil wells which was completed in August 1973. Notice of appeal to the Court of Appeals for the Fifth Circuit was filed in April 1973. In August 1974, the Court of Appeals reversed the judgment and remanded the case with directions that a revised or supplemental statement be prepared and judged anew. Final supplement to the Environmental Impact Statement for the modified project authorized in the Supplemental Appropriations Act, 1983 (PL 98-63) was submitted to the Environmental Protection Agency on September 21, 1983. The schedule for the completion of construction for the modified project is dependent on the time required to coordinate with the courts to lift the injunction, and the availability of construction funds. Local cooperation. Local interest must contribute an amount equal to cost allocated to water supply, one-half of cost allocated to salinity control and cost allocated to recreation less cost of basic facilities and less 15 percent of total project cost. Local interest contribution is estimated at $9,268,000. Operations during fiscal year. New Work: Planning for the non-overflow dam, Interstate 10 to the Lock site, is underway. Maintenance: Ranger surveillance, administration of project, and administration of duck blind permit program was conducted. Mosquito control spraying cost $10,488. 12. RECONNAISSANCE AND CONDITION SURVEYS Reconnaissance and Condition Surveys were conducted on the following projects: Project Date of Survey Brazos Island Harbor Cedar Bayou Clear Creek & Clear Lake Trinity River & Tributaries bTotal October 1984 November 1984 November & December 1984 & April 1985 March - June 1985 Fiscal Year Cost $6,485 216 1,983 45,326 $54,010 13. NAVIGATION WORK UNDER SPECIAL AUTHORIZATION Navigation activities pursuant to Section 107, Public Law 86-645 (preauthorization). Reconnaissance study to investigate dredging the mouth of the Brazos River Diversion Channel for use by commercial navigation was continued at a fiscal year cost of $61,102. Reconnaissance study to investigate shorter alignments and bend easing on Lydia Ann Channel to Cove Harbor was initiated at a fiscal year cost of $47,191. Beach Erosion 14. CORPUS CHRISTI BEACH, TX (RESTORATION PROJECT) Location. Corpus Christi Beach, a shore area having a length of about 2 miles, is located on the west side of Corpus Christi Bay in Nueces County at Corpus Christi, Texas. (See National Ocean Survey Charts 11309 and 11311.) Existing project. The plan of improvement provided for initial restoration of eroded areas of Corpus Christi Beach, over a shore length of 1.4 miles, located on the easterly side of Rincon Peninsula, with periodic nourishment as required. Construction was completed in March 1978. Estimated cost of new work is $2,150,000 Federal (Corps) and $2,265,000 non-Federal consisting of $2,150,000 contributed funds, $43,000 relocations, and $72,000 lands. (October 1,1985 base price.) Local cooperation. Fully complied with except for periodic nourishment. Operations during fiscal year. A contract for periodic nourishment and construction of sand retention groin was awarded in April 1985. Fiscal year cost for the contract was $175,470. 15. BEACH EROSION WORK UNDER SPECIAL AUTHORIZATION Beach erosion activities pursuant to Section 103, Public Law 87-874. Initial appraisal reports on erosion along the Gulf shores of Jefferson and Chambers Counties, Texas, and along the bay shores at Palacios, Texas, were initiated and completed at cost of $7,500 and $7,100, respectively. Both studies were terminated. An initial appraisal of bay shore erosion at Shoreacres, Texas, was completed at a cost of $7,500. A feasible project was identified at Shoreacres, and further studies await funding of the Section 103 program. 15-8 GALVESTON, TEXAS DISTRICT Flood Control 16. ARROYO COLORADO, RIO HONDO, TX Location. The project is located on Arroyo Colorado at Rio Hondo, Texas which is approximately ten miles northeast of Harlingen, Texas and 30 miles north northwest of Brownsville, Texas. Existing project. The project provides for bank protection to 400 feet of the east bank of Arroyo Colorado downstream of Farm-to-Market Road 106. Estimated cost for new work is $201,300 Federal (Corps) and $7,000 non- Federal. Project was completed in 1984. Local cooperation. Fully complied with. Operations during fiscal year. Operation and maintenance instruction manual for the city of Rio Hondo was prepared. 17. BUFFALO BAYOU AND TRIBUTARIES, TX Location. Improvements are on Buffalo Bayou watershed, a part of San Jacinto River watershed, in Harris County, west and northwest of city of Houston, Texas. (See Geological Survey quadrangle sheets for Harris County.) Existing project. Provides for improvement of Buffalo Bayou and its tributaries above turning basin of Houston Ship Channel to control floods for protection of city of Houston, and prevent deposition of silt in turning basin of ship channel by construction of detention reservoirs, enlargement and rectification of channels and construction of control works. Estimated cost of new work is $138,900,000 Federal (Corps) including $11,900,000 for recreational facilities at completed projects (Code 713 funds), and $98,791,000 non-Federal, consisting of $86,891,000 for lands and relocations, and $11,900,000 contributions for recreational facilities. (October 1, 1985 base price.) Construction of Barker Dam was completed in February 1945. Construction of Addicks Dam and 7.4 miles of channel rectification downstream from Addicks and Barker Dams was completed in October 1948. Modification of Barker and Addicks Dams consisting of gating of two uncontrolled conduits in each dam, was completed in 1969. Channel rectification on White Oak Bayou was completed in 1976. Major rehabilitation of Addicks and Barker Dams to prevent seepage through the embankment was completed in 1982. Work remaining consists of rectification of approximately 22 miles of main stem of Buffalo Bayou. A contract with the city of Houston for cost-sharing in the construction of recreation facilities at Cullen Park was entered into in November 1981. The lease for approximately 10,534 acres of land and water areas was approved in February 1983. Local cooperation. Section 203, 1954 Flood Control Act applies. Local interests have accomplished all required local cooperation on Brays Bayou and White Oak Bayou. On Buffalo Bayou, local interests purchased interests that the United States had in 7 miles of rectified channel below Barker and Addicks Dams for $256,651. Of the remaining required rights-of-way on Buffalo Bayou, local interests have acquired about 40 percent. About 53 percent of required bridge relocations and 3 percent of the required utility relocations have been accomplished. Advance of $4,400,000 by the Harris County Flood Control District was refunded in September 1956. Public Law 86-53 authorized reimbursement of $38,726 to Galveston, Houston and Henderson Railroad Company for bridge alterations at Brays Bayou. Non-Federal contributions totaled $63,661 for project betterments. Recreation development is subject to conditions of non-Federal costsharing under Federal Water Project Recreation Act of 1965. Operations during fiscal year. Recreation: Construction of picnic areas, access roads, parking areas, and rough grading of ball fields for the Community Park West (Phase 1A) were completed. The city of Houston awarded a contract in August 1985 for construction of additional access, parking, restrooms, group shelters, and completion of ball fields for the Community Park West. The fiscal year Federal cost of cost-shareable items was $161,826. Maintenance: Routine operations and maintenance at Addicks and Barker Dams. 18. PORT ARTHUR AND VICINITY, TX, (HURRICANE-FLOOD PROTECTION) Location. Port Arthur is on west shore of Sabine Lake in extreme southeast part of Texas, about 14 miles from the gulf. Area under consideration is comprised of about 38,500 acres, and includes cities of Port Arthur and Groves, towns of Griffing Park, Pearl Ridge, and Lakeview, and adjacent industrial areas. Existing project. Authorized plan provides for raising and reconstructing 6.3 miles of existing concrete and steel sheet-pile seawall; constructing 0.3 mile of new concrete and sheet-pile seawall; raising and improving 3.0 miles of existing earth levees; constructing 20.3 miles of new earth levees and constructing five interior drainage pumping plants. Raising and strengthening of levees surrounding Gulf Oil Company's fresh water reservoir was placed in the "inactive" category in December 1980. The project was initiated in March 1966 and the active portion of the project was completed in 1984. Estimated cost for new work, excluding "inactive" portion, is $59,703,000 Federal (Corps) and $26,036,000 non-Federal consisting of $16,016,000 cash contributions, $3,403,000 for lands, $6,168,000 for relocations, and $449,000 for pumping station betterments and levee realignment betterments. Local cooperation. Fully complied with. Operation during fiscal year. Investigation of levee settlement was performed. 19. TAYLORS BAYOU, TX Location. Watershed of Taylors Bayou is in extreme southeast corner of Texas adjoining basins of Neches River and Sabine Lake on the east. City of Port Arthur is about 8 miles from the main stream of Taylors Bayou. 15-9 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Existing project. Improvement consists of enlarging and rectifying approximately 53 miles of natural and artificial channels on Taylors Bayou and tributary water courses. Phase I consists of constructing a gated structure to prevent saltwater intrusion and 2.9 miles of new diversion channel and enlarging 1.8 miles of Gulf Intracoastal Waterway and a 1.9 mile section of the Outfall Canal. Phase II consists of enlarging 6.0 miles of Taylors Bayou, 14.3 miles of Hillebrandt Bayou, 1.5 miles of Pivotot Bayou, 2.3 miles of Bayou Din, and 3.5 miles of Willow Marsh Bayou. Phase III consists of enlarging 7.0 miles of North Fork Thylors Bayou, 7.8 miles of South Fork Taylors Bayou and 4.4 miles of Mayhaw Bayou. The Phase III portion of the project was placed in the "inactive" category in November 1980. Initial contract on the "active" portion of the project was awarded in August 1982. Estimated cost for new work, excluding inactive portion, is $51,700,000 Federal (Corps) and $25,690,000 non-Federal, including $17,630,000 cash contribution, $4,331,000 lands, and $3,729,000 for relocations. (October 1, 1985 base price.) Local cooperation. Section 204, 1965 Flood Control Act, applies. Operation during fiscal year. A contract for construction of the Salt Water Gate was continued at a fiscal year cost of $830,000. Dredging of the Taylors Bayou Diversion Channel, Station -1+40 to 135+00, was completed at a fiscal year cost of $3,451,732. 20. TEXAS CITY AND VICINITY, TX (HURRICANE-FLOOD PROTECTION) Location. On the west and southwest shore of Galveston Bay, about 9 miles northwest of Galveston, Texas. Project fronts on the west side of Galveston Bay and protects a land area of about 36 square miles. Existing project. Plan provides for construction of improvements for control of storm tides. Improvements consist of 15.9 miles of new levees, 1.3 miles of concrete floodwall, related drainage and stoplog structures, one tide control structure, and two pumping plants. The project was initiated in 1962. All work is complete except for the La Marque Pumping Plant and drainage structures. Construction of the La Marque Pumping Plant was initiated in September 1982. Estimated cost for new work is $37,982,000 Federal (Corps) and $16,627,000 non- Federal, including $13,937,000 cash contribution, $1,071,000 work contribution, and $1,363,000 for lands, and $256,000 for ramps in lieu of closure structures and increased low flow pumping capacity for La Marque Pumping Plant. Local cooperation. Fully complied with. Operations during fiscal year. Supply contract for the La Marque Pumping Plant cost $15,041. Contract for construction of La Marque Pumping Plant was continued at a fiscal year cost of $921,270. Contract for interior drainage structures was initiated at a fiscal year cost of $172,900. 21. VINCE AND LITTLE VINCE BAYOUS, TX Location. Watershed of Vince Bayou and tributary, Little Vince Bayou, has an area of about 17 square miles and lies entirely within Harris County. Vince Bayou is a minor tributary of Buffalo Bayou in San Jacinto River Basin on upper gulf coast of Texas. Existing project. Project provides for enlarging and rectifying channel of Vince Bayou from mouth to a point about 7.3 miles upstream and Little Vince Bayou from mouth to a point about 4.2 miles upstream, a total distance in both streams of about 11.5 miles. The project was initiated in 1968. All work on Vince Bayou is complete. Planning is in progress on Little Vince Bayou. Estimated cost for new work is $19,500,000 Federal (Corps) and $17,275,000 non-Federal, consisting of $5,075,000 for lands and $12,200,000 for relocations. (October 1, 1985 base price.) Local cooperation. Sec. 203, 1962 Flood Control Act, applies. Local interests have acquired all real estate and accomplished all required relocations on Vince Bayou. On Little Vince Bayou, local interests have acquired 80 percent of the real estate and accomplished 10 percent of the required relocations. Operations during fiscal year. Fiscal year cost for channel rectification on Little Vince Bayou, mile 0.7 to 2.7, was $1,318,720. 22. INSPECTION OF COMPLETED FLOOD CONTROL WORKS Inspections of completed projects operated and maintained by local interests were made on the following projects. Fiscal year cost was $88,099. Project Brays Bayou, Channel Rectification Highland Bayou Diversion Channel White Oak Bayou, Channel Rectification Port Arthur and Vicinity, Hurricane- Flood Protection Project Freeport and Vicinity, Hurricane- Flood Protection Project Texas City and Vicinity, Hurricane- Flood Protection Project Galveston Seawall Extension, Galveston, TX Colorado River, Flood Protection at Matagorda, TX Date of Inspection January 1985 March 1985 April 1985 June 1985 June 1985 June 1985 August 1985 August 1985 23. FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION Flood control activities pursuant to Section 205 of 1970 Flood Control Act, Public Law 858, 80th Congress, as amended. 15-10 GALVESTON, TEXAS DISTRICT Initial appraisal reports on flood problems at Cedar Bayou, Aransas and Calhoun Counties, Texas, and at Petronila Creek, Driscoll, Texas were completed at a cost of $7,500 each. Both studies were terminated. Preparation of plans and specifications for a flood control project at Kirbyville, Texas was initiated at a fiscal year cost of $68,293. Emergency flood control activities-repair, flood fighting, and rescue work (Public Law 99, 84th Congress and antecedent legislation). Costs were $129,210 for disaster preparedness and $16,365 for emergency operations. Rehabilitation work for Brays and White Oak Floodways was $558,646 and for Texas City Hurricane-Flood protection project $51,838. General Investigations 24. SURVEYS Fiscal year costs were $2,223,969 of which $350,301 was for navigation studies, $1,708,236 was for flood damage prevention studies, $65,087 was for shoreline protection studies, $69,241 was for coordination with other agencies, $22,867 was for Special Investigations, and $8,237 was for Deauthorization review. 25. ADVANCE ENGINEERING AND DESIGN Clear Creek, Texas - The project will provide for enlargement and rectification of the existing Clear Creek channel from the upper end of Clear Lake at Mile 3.8 to improved channel Mile 26.05, a distance of approximately 22 miles; and an additional outlet with a gated structure from Clear Lake to Galveston Bay. A number of bridges, pipelines and other structures which now obstruct flood flows will require relocation or alteration. Estimated preconstruction planning cost is $2,836,000. Preconstruction planning was initiated in 1972. The Combined General Design Memorandum and the Final Environmental Impact Statement were completed in 1982. A Feature Design Memorandum for channel rectification between mile 3.8 and 7.3 was approved in May 1985. Fiscal year costs were $58,330. 26. PLANNING AND ENGINEERING Upper White Oak Bayou and Tributaries, vicinity of Houston, Texas - The project will provide for channel improvements on White Oak Bayou from Mile 10.7 to Mile 19.9; on Cole Creek from Mile 0 to Mile 4.9; and on Vogel Creek from Mile 0 to Mile 4.5, for a total of 18.6 miles. Project also provides for flood plain zoning and regulation on the residual 100-year flood plains on White Oak Bayou from Mile 19.9 to near Mile 25.5; on Cole Creek form Mile 4.9 to near Mile 6.9; and on Vogel Creek from Mile 4.5 to near Mile 6.5; and includes recreational development along White Oak Bayou from near Mile 14.6 to near Mile 18.3. Estimated planning and engineering estimate is $3,700,000. Planning and engineering studies were initiated in 1982. Fiscal year costs were $431,347. 27. COLLECTION AND STUDY OF BASIC DATA Flood plain management and technical services were performed at a cost of $29,927 and $87,934, respectively. Anticipated studies cost $1,072. Hydrologic studies cost $7,819. 15-11 TABLE 15-A REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 COST AND FINANCIAL STATEMENT See Section in Text Project 1. Aquatic Plant Control (Southwestern Division) 1965 Act 2. Brazos Island Harbor, TX 3. Corpus Christi Ship Channel, TX (Regular Funds) (Contributed Funds) 4. Freeport Harbor, TX Galveston Harbor and Channel, TX 6. Gulf Intracoastal Waterway between Apalachee Bay, FL and the Mexican Border (Galveston Dist.) Total Cost To FY 82 FY 83 FY 84 FY 85 Sep. 30, 198524 60,000 97,972 (-)3,877 (-)3,877 1,518,000 1,510,837 Funding New Work: Approp. Cost New Work: Approp. Cost Maint. Approp. Cost Major rehab. Approp. Cost New Work: Approp. Cost Maint. Approp. Cost Major rehab. Approp. Cost New Work: Contrib. Cost New Work: Approp. Cost Maint. Approp. Cost Minor rehab. Approp. Cost New Work: Approp. Cost Maint. Approp. Cost Major rehab. Approp. Cost New Work: Approp. Cost Maint. Approp. Cost Major rehab. Approp. Cost Minor rehab. Approp. Cost 140,000 180,000 95,390 130,816 4,593,000 2,961,443 3,500,000 2,081,707 3,306,300 1,972,610 - 400,000 6,735 682 - 100,000 19,853 8,628 2,080,000 4,243,200 2,070,483 3,742,067 448,100 2,091,003 3,100,000 4,943,296 5,514,200 6,826,376 1,300,000 1,397,580 (-)25,000 29,224 1,891,650 2,061,605 2, 3,( 3, 3,( 5, 6,( 6,165,000 381,000 12,061,900 2,] 6,708,009 105,968 12,337,285 2,] (-)1,491 125,098 12,081,000 9,693,675 600,000 114,177 17,523,000 16,141,134 2,300,000 2,218,220 9,878,800 13,015,122 6,c 261,000 1,598,1001 209,089 1,449,4291 - 11,857,5022 - 11,857,5022 90,000 34,851,4853 85,612 34,846,6443 - 2,170,080 - 2,170,080 980,000 53,452,3594 024,206 53,152,8504 242,650 79,275,8785 087,727 79,074,080 s - 3,576,684 - 3,576,684 250,000 3,442,088 395,274 3,267,446 115,000 2,957,1526 63,743 2,859,3706 752,000 41,449,1157 079,286 41,435,203' - 8,935 - 8,935 - 29,096,3928 - 29,096,3928 149,920 73,660,8239 129,284 73,634,1009 - 7,969,329 - 7,969,329 920,000 59,808,30310 515,223 59,733,50610 388,525 181,246,75511 152,810 180,919,08011 - 434,638 - 434,638 - 835,873 - 835,873 15-12 2,191,491 1,441,665 7,300,000 7,372,185 TABLE 15-A GALVESTON, TEXAS DISTRICT COST AND FINANCIAL STATEMENT See Section in Text Project 7. Houston Ship Channel, TX (Regular Funds) 8. Matagorda, Ship Channel, TX (Regular Funds) 9. Sabine-Neches Waterway, TX (Regular Funds) 10. Texas City Channel, TX 11. Trinity River and Tributaries, TX (Includes Wallisville) 14. Corpus Christi Beach, TX (Restoration Project) (Contributed Funds) 15. Arroyo Colorado, Rio Hondo, TX 16. Buffalo Bayou and Tributaries, TX Funding New Work: Approp. Cost Maint. Approp. Cost New Work: Approp. Cost Maint. Approp. Cost New Work: Approp. Cost Maint. Approp. Cost New Work: Approp. Cost Maint. Approp. Cost Major rehab. Approp. Cost New Work: Approp. Cost Maint. Approp. Cost New Work: Approp. Cost New Work: Approp. Cost New Work: Approp. Cost New Work: Approp. Cost Recreation Approp. Cost Maint. Approp. Cost Major rehab. Approp. Cost Total Cost To FY 82 FY 83 FY 84 FY 85 Sep. 30, 198524 15-13 - - - - 35,760,38212 - - - - 35,760,38212 1,150,000 6,945,000 6,640,880 3,912,500 94,872,52313 1,100,243 5,090,215 8,161,017 4,302,086 94,840,94313 - - - - 18,058,77714 - - - - 18,058,77714 1,770,000 1,677,000 2,745,800 434,000 33,359,043 3,958,543 1,360,493 3,055,463 438,273 33,351,531 - - - - 56,136,81515 - - - - 56,136,81515 5,873,000 4,560,200 13,419,700 6,028,900 125,041,02016 6,191,822 3,267,663 14,438,456 6,216,929 124,938,980'6 282,000 - - - 13,325,47217 843,251 7,733 - - 13,325,47217 3,260,000 - 583,700 1,353,000 19,252,3611's 3,867,333 25,864 393,238 1,554,590 19,244,72218 - - - - 726,158 - - - - 726,158 255,000 300,000 640,000 70,000 28,909,67619 212,946 156,232 564,548 312,119 28,858,57219 903,000 165,000 399,500 444,000 7,845,80320 902,018 138,496 430,108 358,725 7,755,4742o - - 595,000 0 2,150,641 - 5 53,377 123,491 1,731,903 - - 50,000 475,000 2,098,345 - 5 53,377 111,499 1,719,912 - 201,300 - - 201,300 - 24,712 169,132 7,398 201,242 - - - - 57,206,32421 - - - - 57,206,32421 115,600 250,204 - - 377,804 413 4,160 2,953 167,072 185,433 1,461,000 1,702,000 1,924,600 1,038,000 15,786,113 1,304,922 1,566,899 1,966,162 1,358,579 15,730,354 - - - - 12,475,000 17,137 (-)91 127 - 12,475,000 TABLE 15-A REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 COST AND FINANCIAL STATEMENT See Section Total Cost To in Text Project Funding FY 82 FY 83 FY 84 FY 85 Sep. 30, 198524 18. Port Arthur and New Work: Vicinity, TX Hurricane Approp. 1,600,000 - (-)276,000 - 59,702,509 Flood Protection Cost 1,937,833 (-)8,648 151,068 10,902 59,684,639 (Regular Funds) (Contributed Funds) New Work: Contrib. 430,000 230,000 - - 16,291,97522 Cost 668,456 130,069 64,957 2,293 16,236,12722 19. Taylors Bayou, TX New Work: (Regular Funds) Approp. 1,175,000 1,900,000 2,650,000 3,550,000 10,943,198 Cost 400,587 2,574,097 1,943,612 3,933,121 10,510,956 (Contributed Funds) New Work: Contrib. 400,000 600,000 500,000 1,099,000 2,599,000 Cost 55,872 614,494 425,850 1,284,523 2,380,739 22. Texas City and New Work: Vicinity, TX Hurricane- Approp. 2,960,000 2,870,000 - 122,000 37,682,400 Flood Protection Cost 1,703,584 1,419,324 1,558,750 941,301 37,171,297 (Regular Funds) (Contributed Funds) New Work: Contrib. 700,000 700,000 900,000 200,000 14,035,10023 Cost 729,981 608,280 669,567 446,234 13,727,13623 21. Vince and Little Vince New Work: Bayous, TX Approp. 450,000 1,500,000 1,300,000 2,340,000 12,008,100 Cost 274,907 420,002 2,499,132 1,953,848 11,561,158 I Excludes $322,884 credit for contributed work. 2 Includes $675,855 for previous projects. In addition, $1,806,619 expended from contributed funds, of which $123,361 was for previous projects. 3 In addition, $14,692 expended from contributed funds. 4 Includes $1,372,534 for previous projects. Includes $456,515 for Sec. 107 project for Port Aransas Breakwaters. In addition $768 expended from contributed funds for Port Aransas Breakwaters. 5 Includes $62,452 for previous projects. In addition, $443,702 expended from contributed funds. 6 Includes $147,098 for previous projects. In addition, $758,303 expended from contributed funds. 7 In addition, $229,311 expended from contributed funds. 8 Includes $8,421,996 for previous projects. In addition, $3,648,932 expended from contributed funds. * Includes $86,126 for previous projects. In addition, $2,058,280 expended from contributed funds. O1In0 cludes $706,709 for previous projects. Includes Sec. 107 projects for Port Isabel Small Boat Basin ($46,559); Port Isabel Side Channel ($8,414); Offatts Bayou ($356,466); and Channel to Aransas Pass ($658,573). In addition contributed funds expended for Port Isabel Small Boat Basin ($46,559); Offatts Bayou ($49,665); Channel to Aransas Pass ($347,950); Chocolate Bayou ($658,310); and Mouth of Colorado River ($2,172,428). 11 Includes $1,526,564 for previous projects. In addition, $22,672 expended from contributed funds. 12 Includes $4,105,157 for previous projects. In addition, $2,591,939 expended from contributed funds, of which $1,209,179 was for previous projects. 13 Includes $1,213,142 for previous projects. In addition, $363,360 expended from contributed funds, of which $200,000 was for previous projects. 14 In addition, $12,259,619 expended from contributed funds and $182,800 for contributed lands. 15 Includes $5,180,832 for previous projects. In addition, $2,680,942 expended from contributed funds, of which $577,507 was for previous projects. 16 Includes $2,379,677 for previous projects. In addition, $2,552,804 expended from contributed funds. 17 Includes $366,823 for previous projects. In addition, $1,023,819 expended from contributed funds, of which $99,000 was for mitigation measures. 18 Includes $195,083 for previous projects. 19 Includes $1,966,306 for previous projects. in addition, $66,000 expended from contributed funds. 20 Includes $543,662 for previous projects. 21 Includes $4,400,000 of advanced funds repaid to Harris County Flood Control District. In addition, $63,661 contributed funds expended for Brays Bayou and $12,900 Federal funds and $19,104 contributed funds expended for enlargement of Clodine Ditch. 22 Excludes $3,402,588 estimated value of contributed lands, $6,168,360 for relocations, and $217,000 credit given local sponsor for work-in-kind. 23 Excludes $1,349,069 estimated value of contributed lands and $1,070,959 credit given local sponsor for work-in-kind. 24 Includes funds provided by the Jobs Act (P.L. 98-8, dated March 24, 1983) for projects listed in Table 15-I. 15-14 GALVESTON, TEXAS DISTRICT TABLE 15-B AUTHORIZING LEGISLATION See Date Section Authorizing in Text Act Project and Work Authorized Documents 1. 2. Mar. 3, 1899 Jun. 13, 1902 Mar. 3, 1905 Mar. 2, 1907 Feb. 27, 1911 Mar. 4,19132 Sep. 23, 1922 Jul. 3, 19303 Oct. 27,1965 Ju. 3, 1930 May 24, 1934 (PWA) Aug. 30, 1935 Aug. 26, 1937 Mar. 2, 1945 Mar. 2, 1945 Jul. 24, 1946 May 17, 1950 Jul. 14, 1960 AQUATIC PLANT CONTROL Provides for control of progressive eradication of aquatic plant growth from the navigable waters and streams in the U.S. BRAZOS ISLAND HARBOR, TX Jetties and jetty channel, inside channels and basins. Local cooperation requirement modified to provide contribution of funds to cover cost of original dredging of all inside channels and basins. Deepen jetty channel to 31 feet and inner channels and Brownsville and Port Isabel turning basins to 28 feet. Enlarge Port Isabel turning basin. Deepen entrance channel to 35 feet; deepen to 33 feet channel across Laguna Madre; deepen to 32 feet channels from Laguna Madre to turning basins at Brownsville and Port Isabel; widen turning basins; and dredging present shallow-draft channel south of Port Isabel from railroad bridge to Laguna Madre and connecting channel to Port Isabel turning basin. Additional connecting channel between Port Isabel and Brownsville channels; and transfer shallow-draft channels at Port Isabel to GIWW. Deepen to 38 feet in outer bar channels and 36 feet in all other authorized channels and basins; extend existing turning basins at Brownsville and Port Isabel; and construct small-boat basin with a connecting channel next to Brownsville ship channel. Widen Brownsville Channel to 300 feet at a depth of 36 feet from former Goose Island passing basin to turning basin extension, thence at a width of 500 feet and same depth to turning basin proper, deepen to 36 feet in area in southeast corner of turning basin, maintain two existing basins of fishing harbor, and a connecting channel, and construct a third basin, with necessary connecting channel and extend Brazos Island Harbor north jetty seaward 1,000 feet. 27 CORPUS CHRISTI SHIP CHANNEL, TX Acquisition of old curvey portion of north jetty previously constructed by private parties. Complete north jetty in accordance with builder's plans. Complete north jetty in accordance with builder's plans. Connect old curve to St. Joseph Island, and construct south jetty. Dredge roadstead in Harbor Island Basin to 20 feet deep and construct 10,000 linear feet of stone dike on St. Joseph Island. Channel between jetties and Harbor Island Basin to 25 feet deep, extend jetties seaward, extend dike on St. Joseph Island 9,100 feet, and dredge approach channel 12 feet deep to town of Port Aransas. Dredging channel from Aransas Pass to Corpus Christi, 25 feet deep, 200 feet bottom wideth. Deepen entrance channel from gulf to Harbor Island and provide an inner basin at Harbor Island of reduced area but greater depty. Specified in Act. Specified in Acts. Specified in Act. Rivers and Harbors Committee Doc. 5, 59th Cong., 2nd Sess. H. Doc. 1094, 61st Cong., 3rd Sess. H. Doc. 1125, 62nd Cong., 3rd Sess. H. Doc. 321, 67th Cong., 2nd Sess. H. Doc. 214, 70th Cong., 1st Sess. 15-15 H.Doc. 251,89th Cong., 1st Sess. Rivers and Harbors Committee Doc. 16, 71st Cong., 2nd Sess. Rivers and Harbors Committee Doc. 10, 71st Cong., 1st Sess. Rivers and Harbors Committee Doc. 32 75th Cong., 1st Sess. H.Doc. 335, 76th Cong., 1st Sess. H.Doc. 347, 77th Cong., 1st Sess. H.Doc. 627, 79th Cong., 2nd Sess. H.Doc. 192, 81st Cong., 1st Sess. H.Doc. 428, 86th Cong., 2nd Sess.' 3. REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 15-B AUTHORIZING LEGISLATION See Date Section Authorizing in Text Act Project and Work Authorized Documents Jul. 3, 1930 Aug. 30, 19354 Aug. 30, 1935 Aug. 30, 1935 Aug. 30, 1935 Jun. 20, 1938 Mar. 2, 1945 Jun. 30, 1948 Sep. 3, 1954 Sep. 3, 19545 Sep. 3, 1954 Jul. 3, 1958 Jul. 3, 1958 Jul. 3, 1958 Jul. 3, 1958 Channel from Aransas Pass to Corpus Christi Channel with depth 30 feet. Enlarge all channels from gult to western end of basin dredged by Humble Oil and Refining Co., at its docks on Harbor Island Maintain channel and maneuvering basin between breakwater and western shoreline of Corpus Christi Bay. Maintain 30-foot depth of approach channel, turning basin at Corpus Christi, Industrial Canal and turning basin at Avery Point. Maintain and deepen to 32 feet channel from deep water at Port Aransas to and including turning basin at Corpus Christi. Extend main turning basin at Corpus Christi westward 2,500 feet at its present width and depth, deepen existing Industrial Canal and turning basin to 32 feet and extend this canal at a depth of 32 feet and general width of 150 feet, westward along Nueces Bay shore to a turning basin 32 feet by 900 feet, and 1,000 feet long near Tule Lake. Provide depth of 34 feet in all project channels and basins from Port Aransas to and including Tule Lake turning basin, for a width of 250 feet from Port Aransas to breakwater at Corpus Christi, for a width of 200 feet in Industrial Canal and in channel between Avery Point and Tule Lake turning basins, and widen Avery Point turning basin to 1,000 feet. Deepen entrance channel to 38 feet from gulf to outer end of jetty; 38 feet decreasing to 36 feet thence to station 90 north jetty; and 36 feet in all other deep water channels and basins except 2,000-foot undredged part of inner basin at Harbor Island, and a width of 400 feet in channel from Port Aransas to Maneuvering basin at Corpus Christi. An anchorage basin 12 feet deep, from 300 to 400 feet wide, and 900 feet long in Turtle Cove at Port Aransas, Texas. Branch channel 32 feet by 150 feet, extending northerly from main channel in vicinity of Port Ingleside, along north shore of Corpus Christi Bay to Reynolds Metals Co. plant and turning basin 32 feet deep and 800 feet square near plant in general vicinity of LaQuinta, Texas. An entrance channel 36 by 400 feet on a tangent alignment from 400-foot channel in Corpus Christi Bay, near Corpus Christi breakwater to flared approach channel to Corpus Christi turning basin. Deepen and widen LaQuinta Channel to 36 by 200 feet; enlarge LaQuinta turning basin to 36 by 800 by 1,000 feet; a flared entrance to channel; and widening at curves. Deepen entrance channel to 42 feet from gult to outer end of jetty; 40 feet in all other deep-water channels and basins except undredged northward extension to inner basin at Harbor Island and branch channel to LaQuinta; and widen Industrial Canal to 400 feet with flared entrances to Corpus Christi and Avery Point turning basins. Channel 40 by 200 feet extending 2.2 miles from Tule Lake turning basin to a turning basin 40 feet deep, 700 to 900 feet wide, 1,000 feet long at Viola, Texas. Depth of 12 feet and a width of 100 feet in locally dredged Jewel Fulton Canal from LaQuinta Channel to a turning basin 12 by 200 by 400 feet, and assumption of maintenance by United States. Rivers and Harbors Committee Doc. 9, 71st Cong., 1st Sess. Rivers and Harbors Committee Docs. 35, 72nd Cong., 1st Sess., and 40, 73rd Cong., 2nd Sess. H. Doc. 130, 72nd Cong., 1st Sess. Rivers and Harbors Committee Doc. 13, 74th Cong., 1st Sess. Rivers and Harbors Committee Doc. 63, 74th Cong., 1st Sess. H. Doc. 574, 75th Congr., 3rd Sess. H. Doc. 544, 78th Cong., 2nd Sess. H. Doc. 560, 80th Cong., 2nd Sess. H. Doc. 654, 81st Cong., 1st Sess. H. Doc. 89, 83rd Cong., 1st Sess. H. Doc. 487, 83rd Cong., 2nd Sess. S. Doc. 33, 85th Cong., 1st Sess. H. Doc. 361, 85th Cong., 2nd Sess. H. Doc. 361, 85th Cong., 2nd Sess. H. Doc. 361, 85th Cong., 2nd Sess. 15-16 GALVESTON, TEXAS DISTRICT TABLE 15-B AUTHORIZING LEGISLATION See Date Section Authorizing in Text Act Project and Work Authorized Documents Jul. 14, 1960 (As amended by Dec. 31, 1970) Aug. 13, 1968 Oct. 22, 1976 Mar. 3, 1899 Mar. 2, 1907 Feb. 27, 1911 Mar. 4, 1913 Aug. 8, 1917 Mar. 3, 19256 Jul. 3, 1930 Aug. 30, 19357 Aug. 30, 1935 May 17, 1950 Jul. 3, 1958 Oct. 5, 1961 Dec. 31, 1970 Construction of a breakwater at entrance to harbor area at Port Aransas, and realignment of existing 12-foot by 100-foot project channel. Provides for a project depth of 45 feet in the existing deep-draft channels and basins, for construction of a new deep-draft turning point, for construction of a deepdraft mooring area and mooring facilities and for widening of the channels and basins at certain locations. The Act also deauthorized the undredged northward extension of Inner Basin at Harbor Island and the undredged west turnout (Wye connection) between the LaQuinta Channel and the main channel of the waterway. Modified local cooperation requirements for 1968 Act. Shifted responsibility for cost of disposal areas and confinement works from sponsor to joint 75 percent Federal and 25 percent non-Federal responsibility FREEPORT HARBOR, TX Dredging and other work necessary in judgment of Secretary of War for improving harbor; for taking over jetties and privately built works at mouth of river. Examination authorized. Work later confied to maintenance of jetties. Repairs to jetties and dredging. Construct seagoing hopper dredge. Purchase of one 15-inch pipeline dredge and equipment, its operation of 3 years, operation of seagoing dredge one-half time for 3 years, and repairs to jetties. Diversion dam, diversion channel, and necessary auxiliary works. Maintenance of diversion channel at expense of local interest. Deepening channels and basins. Maintenance of present project dimensions of channels and basins at Federal expense. Deepen outer bar channel to 38 feet from gulf to a point within jetties, thence 36 feet in authorized channels to and including upper turning basin. Relocate outer bar channel on straight alignment with jetty channel and maintain Brazos Harbor entrance channel and turning basin (constructed by local interests). Modification of HD 1469. Revoking certain provisions of local cooperation. Relocation of entrance channel and deepen to 47 feet; enlargement to a depth of 45 feet and relocation of jetty channel and inside main channel; deepening to 45 feet of channel to Brazosport; enlargement of the widened area of Quintana Point to provide a depth of 45 feet with a 750-foot diameter turning area; Brazosport turning basin to 45 feet deep with a 1,000 foot turning area; a new turning basin with a 1,200 foot diameter turning area and 45 feet deep; deepening Brazosport channel to 36 by 750 feet diameter; flared approaches from Brazos Harbor Channel; relocation of north jetty and rehabilitation of south jetty. Sec. 107, PL 86-645 S. Doc. 99, 90th Cong., 2nd Sess.' Sec. 124, PL 94-587 Specified in Act. H. Doc. 1087, 60th Cong., 2nd Sess. Specified in Act. Specified in Act. Specified in Act. Rivers and Harbors Committee Doc. 10, 68th Cong., 2nd Sess. Rivers and Harbors Committee Doc. 18, 70th Cong., 1st Sess. Rivers and Harbors Committee Doc. 15, 72nd Cong., 1st Sess. Rivers and Harbors Committee Docs. 15, 72nd Cong., 1st Sess., and 29, 73rd Cong., 2nd Sess. H. Doc. 195, 81st Cong., 1st Sess. H. Doc. 433, 84th Cong., 2nd Sess. PL 394, 87th Cong. H. Doc. 289, 93rd Cong., 2nd Sess.2 15-17 4. REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 15-B AUTHORIZING LEGISLATION 5. in Text Act Aug. 5, 1886 Jun. 13, 1902 Mar. 3, 1905 Mar. 2, 1907 Mar. 2, 1907 Jun. 25, 19109 Jul. 27, 1916 Jul. 18, 1918 Sep. 22, 1922 Jan. 21, 1927 Aug. 30, 193511 Aug. 30, 1935 Aug. 30, 1935 Aug. 30, 1935 Apr. 4, 1938 Jun. 30, 1948 May 17, 1950 Jul. 3, 1958 Jun. 23, 1971 (House Res.) (Nov. 18, 1971 (Sen. Res.) Mar. 2, 1907 Mar. 3, 1925 Jan. 21, 1927 15-18 See Date Section Authorizing Project and Work Authorized GALVESTON HARBOR AND CHANNEL, TX Construct 2 rubblestone jetties at entrance to Galveston Harbor. A channel 1,200 by 30 feet from Bolivar Roads (outer end of old inner bar near Fort Point) at 51st Street.8 Purchase or construct hydraulic pipeline dredge. Extension of jetties to present project length and construction and operation of a dredge. Extension of Galveston Channel from 51st to 57th Sts., with depth of 30 feet and width of 700 feet. Conditional extension of Galveston Channel between 51st and 57th Sts., 30 feet deep and 1,000 feet wide. Extend seawall at Galveston from angle at 6th St. and Broadway to vicinity of Fort San Jacinto. Deepen harbor channel to 35 feet and widen to 800 feet. Further extension of seawall at Galveston to a junction with south jetty; and repairing seawall in front of Fort Crockett reservation. Deepen Galveston Channel to 32 feet; and maintain Galveston Harbor channels to dimensions of 800 feet wide, 35 feet deep on outer bar and 34 feet deep in inner bar.'o Maintain State Highway Ferry Landing Channels to dimensions of 12 by 100 feet. Construct 13 groins along gulf shore from 12th to 61st Sts. in city of Galveston at a limited cost of $234,000 (10 groins constructed). Deepen Galveston Channel to 34 feet (Bolivar Roads to 43rd St.). Deepen Galveston entrance channel to 36 feet. Completion of project for construction of 13 groins. Deepen Glaveston Harbor to 38 feet from gulf to a point 2 miles west of seaward end of north jetty; thence 36 feet to Bolivar Roads; revoking authority for maintenance of ferry channels; and Galveston channel to 36 feet deep from Bolivar Roads to 43rd Street. Construct extension of Galveston Seawall from 61st Street, southwesterly 16,300 feet along gulf shore. Deepen Galveston Harbor to 42 feet from gulf to point 2 miles west of seaward end of north jetty and 40 feet thence to Bolivar Roads. Deepen Galveston Channel to 40 feet from Bolivar Roads to 43rd Street. GULF INTRACOASTAL WATERWAY BETWEEN APALACHEE BAY, FL AND MEXICAN BORDER 12 Channel 4 by 100 feet from West Galveston Bay across Chocolate Bay to 4 feet of water in Chocolate Bay. Channel 9 by 100 feet, Sabine River to Galveston Bay, and a 20-inch pipeline dredge. Such passing places, widening at bends, locks or guard locks and railway bridges over artificial cuts as are necessary. Channel 9 by 100 feet, Galveston Bay to Corpus Christi. Documents H. Doc. 85, 49th Cong., 1st Sess., and Annual Report, 1886, p. 1311. H. Doc. 264, 56th Cong., 2nd Sess. Specified in Act. H. Doc. 340, 59th Cong., 2nd Sess., and Rivers and Harbors Committee Doc. 11, 59th Cong., 2nd Sess. H. Doc. 768, 59th Cong., 2nd Sess. H. Doc. 328, 61st Cong., 2nd Sess. H. Doc. 1390, 62nd Cong., 3rd Sess. H. Doc. 758, 65th Cong., 2nd Sess. H. Doc. 693, 66th Cong., 2nd Sess. H. Doc. 307, 69th Cong., 1st Sess. River and Harbors Committee Doc. 31, 72nd Cong., 1st Sess. H. Doc. 400, 73rd Cong., 2nd Sess. Rivers and Harbors Committee Doc. 61, 74th Cong., 1st Sess. Rivers and Harbors Committee Doc. 57, 74th Cong., 1st Sess. PL 463, 75th Cong. H. Doc. 561, 80th Cong., 2nd Sess. H. Doc. 173, 81st Cong., 1st Sess. H. Doc. 350, 85th Cong., 2nd Sess. H. Doc. 121, 92nd Cong., 1st Sess. (Sec. 201, PL 89-298) H. Doc. 445, 56th Cong., 1st Sess. H. Doc. 238, 68th Cong., 1st Sess. H. Doc. 238, 68th Cong., 1st Sess. 6. GALVESTON, TEXAS DISTRICT TABLE 15-B AUTHORIZING LEGISLATION See Date Section Authorizing in Text Act Project and Work Authorized Documents Aug. 26, 1937 Jun. 20, 193813 Jun. 20, 1938 Jun. 20, 1938 Jun. 20, 1938 Jun. 20, 1938 Mar. 23, 1939 Jul. 23, 1942 Mar. 2, 1945 Mar. 2, 19459 Mar. 2, 1945 Mar. 2, 1945 Mar. 2, 194514 Jul. 24, 1946 Jul. 24, 1946 May 17, 1950 May 17, 1950 May 17, 1950 Jul. 12, 1952 Sep. 3, 195415 Sep. 3, 1954 Sep. 9, 1959 Maintenance of a flood-discharge channel in Colorado River. Channel 9 by 100 feet in San Bernard River, Texas. Channel in Colorado River, 9 by 100 feet, with basin. Channel 9 by 100 feet from Palacios through Trepalacios and Matagorda Bays. Channel 9 by 200 feet from main channel to harbor at Rockport and improve harbor to 9-foot depth. Channel 6 by 100 feet from main channel to Aransas Pass, Texas. Enlarge waterway to depth of 12 feet and a width of 125 feet from Sabine River to Corpus Christi. Enlarge waterway from Corpus Christi to vicinity of Mexican border to provide a depth of 12 feet and width of 125 feet throughout. Channel 6 by 60 feet from GIWW to a point in Chocolate Bayou near Liverpool. Channel 6 feet deep and 60 feet wide from main channel near Port O'Connor, Texas, into Barroom Bay. Enlarge channel from main channel to Aransas Pass, Texas, providing a depth of 9 feet and width of 100 feet. Channel 12 by 125 feet from main channel to Red Fish Landing, Texas, with basin. Channel 12 feet deep and 125 feet wide from main channel to vicinity of Harlingen, Texas, via Arroyo Colorado with basin. Fill a portion of shallow-draft channel adjacent to Port Isabel Turning Basin, construct a channel to connect shallow-draft channel with main channel near shoreline of Laguna Madre, and enlarge shallow-draft channel west of this connection, all to 12-foot depth and bottom width of 125 feet. Reroute main channel to north shore of Red Fish Bay between Aransas Bay and Corpus Christi Bay; deepen tributary channel from Port Aransas to Aransas Pass, Texas, 12 feet and extended basin at same depth. Deauthorized 6 by 60 foot channel in Chocolate Bayou and reauthorized the 4 by 100-foot channel. Alternate channel across South Galveston Bay between Port Bolivar and Galveston causeway. "Red Fish Landing" changed to "Port Mansfield, Texas." Incorporate as part of Intracoastal Waterway a channel 9 by 100 feet from main channel via Seadrift to point on Guadalupe River 3 miles above Victoria, Texas, authorized by River and Harbor Act of 1945. Small craft harbor 9 by 200 by 1,000 feet at Seadrift with an entrance channel 9 by 100 feet. Widen tributary channel between Port Aransas and Aransas Pass, Texas, to 125 feet; straighten and widen to 125 feet connecting channel to Conn Brown Harbor, and maintain Conn Brown Harbor at Federal expense, all to 12 feet deep. Improve channels and basins comprising channel to Port Mansfield constructed in part by Federal Government and in part by local interest; constructing turnout curves at Gulf Intracoastal Waterway intersection and bend easing at entrance to turning basin; construct parallel jetties at gulf entrance; maintenance of locally dredged jetty channel 16 by 250 feet; and maintenance of small craft basin. S. Committee print, 75th Cong., 1st Sess. H. Doc. 640, 75th Cong., 3rd Sess. H. Doc. 642, 75th Cong., 3rd Sess. H. Doc. 564, 75th Cong., 3rd Sess. H. Doc. 641, 75th Cong., 3rd Sess. H. Doc. 643, 75th Cong., 3rd Sess. H. Doc. 230, 76th Cong., 1st Sess. PL 675, 77th Cong. H. Doc. 337, 76th Cong., 1st Sess. H. Doc. 428, 76th Cong., 1st Sess. H. Doc. 383, 77th Cong., 1st Sess. S. Doc. 248, 78th Cong., 2nd Sess. H. Doc. 402, 77th Cong., 1st Sess. (See Public Law 14, 79th Cong.) H. Doc. 627, 79th Cong., 2nd Sess. H. Doc. 700, 79th Cong., 2nd Sess. H. Doc. 768, 80th Cong., 2nd Sess. H. Doc. 196, 81st Cong., 1st Sess. PL516, 81st Cong. PL 527, 82nd Cong., 2nd Sess. H. Doc. 478, 81st Cong., 2nd Sess. H. Doc. 376, 83rd Cong., 2nd Sess. S. Doc. 11, 86th Cong., 1st Sess. 15-19 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 15-B AUTHORIZING LEGISLATION See Date Section Authorizing in Text Act Project and Work Authorized Documents Jul. 14, 1960 Jul. 14, 1960 (As amended Dec. 31, 1970) Jul. 14, 1960 (As amended Dec. 31, 1970) Jul. 14, 1960 (As amended Dec. 31, 1970) Oct. 23, 196216 Oct. 23, 1962 Oct. 23, 1962 Oct. 27, 196517 Aug. 13, 1968 Mar. 5, 1905 Mar. 2, 1919 Mar. 3, 1925 Jul. 3, 1930 Entrance channel 7 feet deep by 75 feet wide from main channel to Gulf of Mexico to inside shoreline at Port Isabel, Texas, an inner channel 6 feet deep by 50 feet wide from entrance channel to East Harbor Basin, and an irregular-shaped harbor basin 6 feet deep having a surface area of about 7 acres. Deepen the existing 6-foot channel at Port Isabel to 12 feet and removing the submerged bars at each end of the island to a depth of -12 feet MLT. Deepening the existing channel to 12 by 125 feet, and extend southeasterly from the Gulf Intracoastal Waterway main channel in West Galveston Bay, into Offatts Bayou, a distance of 2.2 miles, and a west turnout 12 by 125 feet between the proposed Offatts Bayou Channel and the Gulf Intracoastal Waterway. Deepening Aransas Pass tributary channel to 14 feet from mile 0 at Harbor Island to mile 6.1 at the city of Aransas Pass; widening to 175 feet between miles 3.5 and 4.6; and deepening Conn Brown Harbor, turning basin and connecting channel between Conn Brown Harbor and turning basin. Improve main channel 16 feet deep and 150 feet wide from Sabine River to Houston Ship Channel; with two relocations; relocate main channel in Matagorda Bay and Corpus Christi Bay; and maintaining existing Lydia Ann Channel. Deepen and widen channel to Palacios; construct two protective breakwaters; maintain and deepen existing basins; and deepen, enlarge and maintain existing approach channel to basin No. 2. Eliminates requirement of local interest to construct bridge at mile 29.2 turning basin at Victoria, and maintain turning basins at Victoria and Seadrift; provide: Federal construction of vertical-lift railroad bridge at Missouri- Pacific Railroad mainline crossing, mile 29.2; construction and future maintenance of basin near Victoria, Texas, and maintenance of basin constructed by local interests at Seadrift, Texas. Modify existing Federal navigation project to provide a channel extending from Gulf Intracoastal Waterway through Chocolate Bay and Chocolate Bayou to project channel mile 8.2, thence to a turning basin near channel mile 13.2 and for salt water barrier in Chocolate Bayou about 3.7 miles upstream from basin (channel mile 16.9). Entrance channel 15 feet deep and 200 feet wide at the mouth of Colorado River Channel protected by an east jetty 3,500 feet long extending to 12-foot depth and a west jetty 2,900 feet long extending to 5-foot contour; make channel 12 feet by 100 feet from gulf shore to Matagorda, including recreation facility, a turning basin 12 feet by 300 feet wide and 1,450 feet long, and a new diversion channel 250 feet wide and varying in depth from 20 to 23 feet including a closure dam across the present river channel. HOUSTON SHIP CHANNEL, TX Easing or cutting off sharp bends and construction of a pile dike.' A channel 30 feet deep, widen bend at Manchester and enlarge turning basin. A light-draft extension of channel to mouth of White Oak Bayou.1 ' Widen channel through Morgan Point and to a point 4,000 feet above Baytown and widen certain bends. Sec. 107, PL 645, 86th Cong. Sec. 107, PL 86-645 Sec. 107, PL 86-645 Sec. 107, PL 86-645 H. Doc. 556, 87th Cong., 2nd Sess. H. Doc. 504, 87th Cong., 2nd Sess. H. Doc. 288, 87th Cong., 2nd Sess. H. Doc. 217, 89th Cong., 1st Sess. S. Doc. 102, 90th Cong., 2nd Sess. Rivers and Harbors Committee Doc. 35, 61st Cong., 2nd Sess. H. Doc. 1632, 65th Cong., 3rd Sess. H. Doc. 93, 67th Cong., 1st Sess. H. Doc. 13, 71st Cong., 1st Sess. 15-20 7. GALVESTON, TEXAS DISTRICT TABLE 15-B AUTHORIZING LEGISLATION See Date Section Authorizing in Text Act Project and Work Authorized Documents Aug. 30, 193511 Aug. 30, 1935 Mar. 2, 1945 Mar. 2, 1945 Mar. 2, 1945 Jun. 30, 1948 Jul. 3, 195820 Jul. 14, 1960 Oct. 27, 1965 Jun. 25, 1910 Aug. 30, 1935 Aug. 26, 1937 Mar. 2, 1945 Mar. 2, 1945 Jul. 3, 1958 Jul. 3, 1958 Jul 25, 1912 Sep. 22, 1922 Sep. 22, 1922 Deepen to 32 feet in main channel and turning basin, and a 400-foot width through Galveston Bay. Deepen to 34 feet in main channel and widen from Morgan Point to turning basin. Branch channel 10 by 60 feet behind Brady Island. Widen channel from Morgan Point to lower end of Fidelity Island with turning points at mouth of Hunting Bayou and lower end of Brady Island. Widen channel from lower end of Fidelity Island to Houston turning basin and dredge off-channel silting basins. Deepen to 36 feet from Bolivar Roads to and including main turning basin at Houston, Texas, including turning points at Hunting Bayou and Brady Island. Deepen to 40 feet from Bolivar Roads to Brady Island, construct Clinton Island turning basin, a channel 8 by 125 feet at Five Mile Cut, and improve shallow-draft channel at Turkey Bend. Barbour Terminal at Morgan Point. Restoring existing locally dredged channel from mile 0 to 0.34 to 36 feet deep and dredging a 15-12 ft. channel from mile 0.34 to 2.81, in Greens Bayou.21 MATAGORDA SHIP CHANNEL, TX Channel to Port Lavaca, Texas 7 feet deep and 89 feet bottom width. Extend 7-foot channel to shoreline of Lavaca Bay at mouth of Lynns Bayou. Deepen and widen channel to present project dimensions. Extend channel 6 by 100 feet from Port Lavaca via Lavaca Bay, Lavaca and Navidad Rivers to Red Bluff, a distance of 20 miles. A harbor of refuge 9 feet deep near Port Lavaca and an approach channel 100 feet wide and equal depth. Deepen to 12 feet and widen to 125 feet Port Lavaca Channel and approach channel to harbor of refuge; deepen to 12 feet Port Lavaca turning basin and basins at harbor of refuge. An entrance channel 38 by 300 feet, a channel 36 by 200 feet, 22 miles long across Matagorda and Lavaca Bays to Point Comfort, Texas, a turning basin 36 feet deep and 1,000 feet square at Point Comfort, and dual jetties at entrance from gulf. SABINE-NECHES WATERWAY, TX Existing project dimensions of jetties, a 26-foot channel through Sabine Pass, Port Arthur Canal and Port Arthur turning basin; and a 26-foot turning basin at Port Arthur. A depth of 25-feet in Sabine-Neches Canal, Neches River to Beaumont and Sabine River to Orange, including cutoffs and widening channels. Deepen channels to 30 feet from gulf to Beaumont, with increased widths and an anchorage basin in Sabine Pass. Deepen Port Arthur east and west turning basins and approach channel to 30 feet. Take over and deepen to 30 feet channel connecting west turning basin with Taylors Bayou turning basin. For a 30-foot depth in channel from mouth of Neches River to cutoff in Sabine River near Orange. Rivers and Harbors Committee Doc. 28, 72nd Cong., 1st Sess. Rivers and Harbors Committee Doc. 58, 74th Cong., 1st Sess. H. Doc. 226, 76th Cong., 1st Sess. H. Doc. 256, 76th Cong., 1st Sess. H. Doc. 737, 79th Cong., 2nd Sess. H. Doc. 561, 80th Cong., 2nd Sess. H. Doc. 350, 85th Cong., 2nd Sess. 1 Sec. 107, PL 86-645 R. Doc. 257, 89th Cong., 1st Sess. H. Doc. 1082, 60th Cong., 2nd Sess. Rivers and Harbors Committee Doc. 28, 74th Cong., 1st Sess. Rivers and Harbors Committee Doc. 37, 75th Cong., 1st Sess. H. Doc. 314, 76th Cong., 1st Sess. H. Doc. 731, 79th Cong., 2nd Sess. H. Doc. 131, 84th Cong., 1st Sess. H. Doc. 388, 84th Cong., 2nd Sess.1 H. Doc. 773, 61st Cong., 2nd Sess. H. Doc. 975, 66th Cong., 3rd Sess. S. Doc. 152, 67th Cong., 2nd Sess. 15-21 8. 9. REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 15-B AUTHORIZING LEGISLATION See Date Section Authorizing in Text Act Project and Work Authorized Documents Mar. 3, 1925 Jan. 21, 1927 Aug. 30, 193511 Aug. 30, 193511 Aug. 30, 1935 Aug. 26, 1937 Aug. 26, 1937 Jun. 20, 193822 Oct. 17, 1940 Mar. 2, 1945 Mar. 2, 1945 Mar. 2, 1945 Jul. 24, 194623 Jul. 24, 194624 Jul. 24, 1946 May 17, 1950 Removal of guard lock in Sabine-Neches Canal. Widen Sabine Pass and jetty channel, Port Arthur Canal, and Sabine-Neches Canal. For dredging 2 passing places in Sabine-Neches Canal, easing of bends, removal and reconstructing Port Arthur field office, extending Beaumont turning basin upstream 200 feet above new city wharves, and an anchorage basin in Sabine Pass. A depth of 32 feet in channels from gulf to Beaumont turning basin, including all turning basins at Port Arthur. Deepen channels to 34 feet with increased widths from gulf to Beaumont turning basin. Construct suitable permanent protective works along Sabine Lake. Maintain Taylors Bayou turning basin. Maintain channel from Sabine River to Orange Municipal wharf. Dredging 500 feet from eastern end of Harbor Island and abandonment of channel south and west of Harbor Island. Increased widths of channels from gulf to Beaumont turning basin and channel connecting Port Arthur west turning basin and Taylors Bayou turning basin, deepen Beaumont turning basin and Beaumont turning extension to 34 feet; and dredge a new cutoff from Smith's Bluff cutoff to McFadden Bend. Abandon Orange turning basin; dredge a channel 25 by 150 feet, suitably widened on bends to highway bridge, and dredge a cutoff channel opposite Orange. Extend Beaumont turning basin upstream 300 feet. Widen Port Arthur west turning basin to 600 feet. Dredge a channel from Beaumont turning basin to vicinity of Pennsylvania Shipyard. Deepen Sabine Pass outer bar channel to 37 feet, Sabine Pass jetty channel to 36 feet at inner end, deepen to 36 feet Sabine Pass Channel, Port Arthur Canal, Port Arthur east and west turning basins, Taylors Bayou turning basin and channel from Port Arthur west turning basin to Taylors Bayou turning basin, deepen to 36 feet and widen to 400 feet Sabine-Neches Canal from Port Arthur Canal to mouth of Neches River except through Port Arthur Bridge; deepen Neches River channel from mouth to Beaumont turning basin to 36 feet widening to 350 feet from Smith's Bluff to Beaumont turning basin; deepen junction area on Neches River at Beaumont turning basin to 36 feet; and widen Sabine-Neches Canal between Neches and Sabine Rivers to 150 feet. Improve Cow Bayou, Texas, by construction of a channel 100 feet wide and 13 feet deep extending from navigation Channel in Sabine River to a point 0.5 mile above county bridge at Orangefield, Texas, with a turning basin. Improve Adams Bayou, Texas, to provide a channel 12 feet deep and 100 feet wide extending from 12-foot depth in Sabine River to first county highway bridge across bayou. Deepen to 36 feet and widen to 400 feet the Sabine- Neches Canal near Port Arthur bridge; reconstruct Port Arthur Bridge and relocate Port Arthur field office. H. Doc. 234, 68th Cong., 1st Sess. H. Doc. 287, 69th Cong., 1st Sess. Rivers and Harbors Committee Doc. 27, 72nd Cong., 1st Sess. Rivers and Harbors Committee Doc. 12, 74th Cong., 1st Sess. Specified in Act. Rivers and Harbors Committee Doc. 3, 75th Cong., 1st Sess. Rivers and Harbors Committee Doc. 20, 75th Cong., 1st Sess. H. Doc. 581, 75th Cong., 3rd Sess. S. Doc. 14, 77th Cong., 1st Sess. H. Doc. 685, 76th Cong., 3rd Sess. S. Doc. 60, 77th Cong., 1st Sess. S. Doc. 158, 77th Cong., 2nd Sess. H. Doc. 571, 79th Cong., 2nd Sess. H. Doc. 702, 79th Cong., 2nd Sess. H. Doc. 626, 79th Cong., 2nd Sess. H. Doc. 174, 81st Cong., 1st Sess. 15-22 GALVESTON, TEXAS DISTRICT TABLE 15-B AUTHORIZING LEGISLATION See Date Section Authorizing in Text Act Project and Work Authorized Documents Sep. 3, 195425 Oct. 23, 196226 Mar. 4, 1913 Jul. 3, 1930 Aug. 30, 193511 Aug. 30, 1935 Aug. 30, 1935 Aug. 26, 1937 Jun. 30, 1948 Jul. 14, 1960 Oct. 12, 1972 (Sen. Res.) Oct. 12, 1972 (House Res.) Mar. 3, 1905 Jul. 25, 1912 Sep. 22, 1922 Mar. 2, 1945 Rectification of certain reaches of existing Sabine Pass Channel, Sabine-Neches Canal, and Neches River and Sabine River Channel; widen to 350 feet entrance channel to Port Arthur turning basins; widen curve at junction of Port Arthur and Sabine-Neches Canals; relocate and enlarge Sabine Pass anchorage basin to 34 by 1,500 by 3,000 feet; widen to 200 feet Sabine-Neches Canal from mouth of Neches River to mouth of Sabine River and Sabine River Channel to upper end of existing project at Orange, except for channel around Harbor Island at Orange; deepen to 30 feet Sabine River Channel from cutoff near Orange municipal slip to upper end of project, except around Harbor Island; and enlarge area at entrance to Orange municipal slip to provide a maneuvering basin. Improve outer bar channel to 42 and 40 feet for all inland' channels to Port Arthur and Beaumont; width of 500 feet in Port Arthur Canal and 400 feet in Neches River Channel to Beaumont with three turning points in Neches River; a channel, 12 by 125 feet, extending in Sabine River to Echo; and replace an obstructive bridge at Port Arthur, Texas. Deauthorization of uncompleted portion of channel between Port Arthur west turning asin and Taylors Bayou turning basin and enlargement of entrance channel to Port Arthur turning basins. TEXAS CITY CHANNEL, TX A channel 300 by 30 feet and construct a pile dike 28,200 feet long north to channel. A harbor 800 by 30 feet at Texas City, and construct a rubblemound dike. Extension of rubblemound dike to shoreline. Deepen channel and harbor to 32 feet. Deepen channel and harbor to 34 feet. Extend harbor 1,000 feet southward, 800 by 34 feet. Deepen channel and harbor to 36 feet, widen channel to 400 feet and harbor to 1,000 feet and changing name of project to "TEXAS CITY CHANNEL, TEXAS." Deepen channel and turning basin to 40 feet and construct 16-foot Industrial Barge Canal. Widen the existing main turning basin to 1,200 feet including relocation of the basin 85 feet to the east; providing a 40-foot deep channel in the Industrial Canal at widths of 300-400 feet, with a turning basin at the head of the canal 40 feet deep, 1,150 feet long, and 1,000 feet wide, and easing of the bend at the entrance to the canal, and deauthorization of shallow-draft Industrial Barge Canal not incorporated in the plan of improvement above. TRINITY RIVER AND TRIBUTARIES, TX Anahuac Channel. Six-foot channel to Liberty. Abandon improvements above Liberty and terminate all improvements by lock and dam, leaving a 6-foot channel from Liberty to mouth. Provides for a navigable channel from the Houston Ship Channel near Red Fish Bar in Galveston and Trinity Bays to the mouth of Trinity River and 9 feet deep and S. Doc. 80, 83rd Cong., 2nd Sess. H. Doc. 553, 87th Cong., 2nd Sess.1 H. Doc. 1390, 62nd Cong., 3rd Sess. H. Doc. 107, 71st Cong., 1st Sess. Rivers and Harbors Committee Doc. 4, 73rd Cong., 1st Sess. Rivers and Harbors Committee Doc. 46, 73rd Cong., 2nd Sess. Rivers and Harbors Committee Doc. 62, 74th Cong., 1st Sess. Rivers and Harbors Committee Doc. 47, 75th Cong., 1st Sess. H. Doc. 561, 80th Cong., 2nd Sess. 1 H. Doc. 427, 86th Cong., 2nd Sess. H. Doc. 199, 92nd Cong., 2nd Sess. (Sec. 201, PL 89-298) H. Doc. 989, 66th Cong., 3rd. Sess. H. Doc. 403, 77th Cong., 1st Sess. 15-23 10. 11. REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 15-B AUTHORIZING LEGISLATION See Date Section Authorizing in Text Act Project and Work Authorized Documents Jul. 24, 1946 Oct. 23, 1962 Oct. 27, 1965 Jul. 30, 1983 Dec. 15, 1970 (House Res.) Dec. 17, 1970 (Sen. Res.) Jul. 24, 1946 (As amended) Jun. 20, 1938 Sep. 3, 1954 Oct. 27, 1965 Oct. 23, 1962 Oct. 27, 1965 Jul. 3, 1958 Oct. 23, 1962 150 feet wide in the river section, with a turning basin at Liberty. Modification of the project to provide for a channel 9 feet deep and 150 feet wide from the Houston Ship Channel near Red Fish Bar in Galveston Bay extending along the east shore of Trinity Bay to the mouth of the Trinity River at Anahuac, including protective spoil embankment on the bay side of the channel in lieu of the 9 by 200-foot channel in Galveston and Trinity Bays. Provides for the multiple-purpose Wallisville Reservoir, including a navigation lock in the Wallisville Dam at Channel Mile 28.30 and advancement of the Channel to Liberty from one mile below Anahuac (Mile 23.2) to the Texas Gulf Sulphur Company's slip at Channel Mile 35.8, and incorporation into existing project Anahuac Channel and mouth of Trinity River projects. Reevaluation of navigation benefits. Modified Wallisville Reservoir by reducing the size to 5,600 acres and confining the reservoir to east side of Trinity River. CORPUS CHRISTI BEACH, TX (RESTORATION PROJECT) Restoration and periodic nourishment of 1.4 miles of beach. ARROYO COLORADO, RIO HONDO, TX Bank protection of 400 feet of east bank of Arroyo Colorado downstream of Farm-to-Market Road 106. BUFFALO BAYOU AND TRIBUTARIES, TX Barker and Addicks Reservoirs, Texas. Clearing, straightening, enlarging and lining of Buffalo Bayou, Brays, and White Oak Bayous. Extend upper limits of White Oak Bayou upstream about 2.1 miles from BRI RR bridge to mouth of Cole Creek. PORT ARTHUR AND VICINITY, TX (HURRICANE-FLOOD PROTECTION) Raising and reconstructing 6.3 miles of existing seawall; constructing 0.3 mile of new seawall, 20.3 miles new levees and five pumping plants; and raising and improving 7.5 miles of existing levees. 28 TAYLORS BAYOU, TX Enlarging and rectifying channels; construction of diversion channel; a salt water gate; enlargement of GIWW 1.3 miles and alteration of State Highway 87 bridge.29 TEXAS CITY AND VICINITY, TX (HURRICANE-FLOOD PROTECTION) Construction of improvements for control of storm tides, consisting of new and enlarged levees and floodwalls approximately 14.1 and 2.1 miles in length; related drainage and stoplog structures; a navigation opening and pumping plants. VINCE AND LITTLE VINCE BAYOUS, TX Enlarging and rectifying channel of Vince Bayou and Little Vince Bayou upstream for a total of 11.5 miles for both streams. H. Doc. 634, 79th Cong., 2nd Sess. H. Doc. 215, 87th Cong., 1st Sess. H. Doc. 276, 89th Cong., 1st. Sess. PL 98-63 H. Doc. 415, 91st Cong., 2nd Sess. (Sec. 201, PL 89-298) Sec. 14, PL 79-526 H. Doc. 456, 75th Cong., 2nd Sess. H. Doc. 250, 83rd Cong., 2nd Sess. 1 H. Doc. 169, 89th Cong., 1st Sess. H. Doc. 505, 87th Cong., 2nd Sess. 1 H. Doc. 206, 89th Cong., 1st Sess. 1 H. Doc. 347, 85th Cong., 2nd Sess. 1 H. Doc. 441, 87th Cong., 2nd Sess.1 15-24 14. 16. 17. 18. 19. 20. 21. TABLE 15-B GALVESTON, TEXAS DISTRICT AUTHORIZING LEGISLATION I Contains latest published maps. 2 Extension of north jetty 1,950 feet and south jetty 1,265 feet considered inactive 3 Dredging 2,000 by 650-foot northerly extension of inner basin deauthorized. 4 Included in Public Works Administration program September 6, 1933 and February 16, 1935. 5 West leg of Wye junction with main channel deauthorized. 6 Construction of lock in diversion dam at local expense considered inactive. 7 Dredging upper .5 mile of channel to vicinity of Stauffer Chemical plant was deauthorized under Sec. 12 of PL 93-251. Included in Public Works Administration program September 6, 1933. 8 Dredging 43rd to 51st Streets was deauthorized under Sec. 12 of PL 93-251. o Deauthorized under Sec. 12 of PL 93-251. o1D0e epening 43rd to 57th Streets was deauthorized under Sec. 12 of PL 93-251 11 Previously authorized September 6, 1933 by Public Works Administration. 12 H. Doc. 230, 76th Cong., 1st Sess. and project documents contain latest published maps. 13 Dredging upper 3.5 miles was deauthorized under Sec. 12 of PL 93-251. 14 Dredging upper 5 miles is inactive. 15isI nactive. 16 Portion of 16-foot by 150-foot channel from Sabine River to Houston Ship Channel and relocation of channel in Matagorda Bay are in inactive category. 17 The 9 feet by 100 feet channel from Mile 8.2 to Mile 13.2 in Chocolate Bayou is inactive. 18 Construction of pile dike was deauthorized under Sec. 12 of PL 93-251. 19 Hill Street Bridge to mouth of White Oak Bayou was deauthorized under Sec. 12 of PL 93-251. 20 Deepening channel to 40 feet from Southern Pacific Slip to Brady Island was deauthorized under Sec 12 of PL 93-251. 21 The 12-foot channel from mile 1.65 to mile 2.81 is inactive. 22 Complete widening of channel between Port Arthur west turning basin and Taylors Bayou turning basin authorized by 1962 R&H Act. 23 Complete deepening of channel between Port Arthur west turning basin and Taylors Bayou turning basin deauthorized by 1962 R&H Act. 24 Channel extension above Cow Bayou turning basin near Orangefield was deauthorized under Sec. 12 of PL 93-251. 25 Widening to 350 feet entrance channel to Port Arthur turning basin deauthorized by 1962 R&H Act. 26 The 12-foot channel in Sabine River from Orange to Echo, Texas is inactive. 27 Jetty extension inactive. 28 Raising and strengthening of levees surrounding Gulf Oil Company's fresh water reservoir is inactive. 29 Enlarging 7.0 miles of North Fork Taylors Bayou, 7.8 miles of South Fork Taylors Bayou and 4.4 miles of Mayhaw Bayou are inactive. 15-25 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 OTHER AUTHORIZED NAVIGATION PROJECTS TABLE 15-C For Last Cost To September 30, 1985 Full Report See Annual Operation and Project Report For Construction Maintenance Aquatic Plant Control (1958 and 1962 River and Harbor Acts)6 1967 38,2521 - Bastrop Bayou, TX2 3 1931 9,920 27,129 Brazos River, TX, Velasco to Old Washington3 1924 216,9894 223,010 Cedar Bayou, TX 1984 681,2636 2,089,3166 Channel to Port Bolivar, TX 1983 133,925' 1,071,9548 Double Bayou, TX 1983 226,558 1,121,978' Clear Creek and Clear Lake, TX 1982 66,934 537,139 Corpus Christi, TX, Channel to Navy Seaplane Base Encinal Peninsula 1968 1,194,344 26,467 Dickinson Bayou, TX 1954 33,942 57,553 East Bay (Hanna Reef), TX10 1922 2,476 847 Johnson Bayou, LA11 1933 2,261 54,042 Little Bay, TX 12 1979 - 252,728 Neches River and Trib., Salt Water Barrier at Beaumont, TX (Advance Engineering & Design) 1984 1,503,843 - Oyster Creek, TX 1922 6,942 7,556 Sabine River and Tributaries, TX (Echo to Morgan Bluff)3 1971 - - 1 Excludes $1,672 work contribution. * Includes $46,101 for previous projects.. 2 Widening from 60 feet to 100 feet at 4-foot depth was 9 In addition, $5,366 expended from contributed funds. deauthorized under Sec. 12 of PL 93-251. 10 In inactive category for maintenance. 3 Inactive. 11 Channel adequate for existing commerce. 4 Includes $123,676 for previous projects. 12 Aransas County Navigation District, Rockport, TX., s Includes $39,087 for previous projects. In addition, $25,000 constructed project as authorized by 1950 River and Harbor Act expended from contributed funds. (H.D. 114, 81st Cong., 1st Sess.) in 1955 under Department of 6 Includes $69,784 for previous projects.. Army permit. 7 Includes $48,711 for previous projects. OTHER AUTHORIZED FLOOD CONTROL PROJECTS TABLE 15-D For Last Cost to September 30, 1985 Full Report See Annual Operation and Project Report For Construction Maintenance Baytown, Texas' 1980 245,400 - Colorado River, Matagorda, Texas 2 1963 273,757 - Freeport and Vicinity, Texas, Hurricane- Flood Protection 2 1984 29,285,0423- Guadalupe River (Remove Log Jams), Texas2 1978 505,749 - Highland Bayou, Texas 2 1984 12,254,390 - Lavaca-Navidad River, Texas: Hallettsville Project 1961 256,043 - General channel project 1952 21,086 - Liberty Local Protection Project, Texas 1971 98,517 - Mill Creek, Texas 1952 24,753 - Peyton Creek, Texas 1975 66,377 - San Diego Creek, Alice, Texas2 1963 135,175 - Tranquitas Creek, Kingsville, Texas2 1956 130,239 - 1 Inactive. 15-26 2 Completed. 3 In addition, $8,695,438 expended from contributed funds, $1,126,905 estimated value of contributed lands, and $2,726,446 for relocations by local interests. GALVESTON TEXAS DISTRICT TOTAL COST OF EXISTING PROJECTS TO SEPTEMBER 30, 1985 TABLE 15-E See Section in Text Project Funds New Work Maintenance Rehabilitation Total 2. Brazos Island Harbor, TX 3. Corpus Christi Ship Channel, TX 4. Freeport Harbor, TX 5. Galveston Harbor and Channel, TX 6. Gulf Intracoastal Waterway between Apalachee Bay, FL and the Mexican Border (Galveston District) 7. Houston Ship Channel, TX 8. Sabine-Neches Waterway, TX 9. Texas City Channel, Tx 10. Trinity River and Tributaries, TX Regular Public Works Contributed Total cost of project Regular Public Works Contributed Total Value of useful work performed Contributed land Total cost of project Regular Public Works Contributed Total Value of useful work performed Total cost of project Regular Channel Seawall Public Works Contributed Total cost of project Regular Public Works Contributed Total Value of useful work performed Contributed land Total cost of project Regular Public Works Contributed Total cost of project Regular Public Works Contributed Total Value of useful work performed Contributed land Total cost of project Regular Public Works Contributed Total cost of project Regular Contributed Total cost of project $ 8,333,087 2,848,560 1,683,258 12,864,905 51,456,029 324,287 3,268,214 55,048,530 1,716,695 276,720 57,041,945 2,595,697 116,575 758,303 3,470,575 360,249 3,830,824 11,920,187 8,754,209 3,648,932 24,323,328 58,560,320 466,477 3,274,912 62,301,709 395,000 139,776 62,836,485 29,042,293 2,612,932 1,382,760 33,037,985 49,592,331 1,363,652 2,103,435 53,059,418 32,000 116,760 53,208,178 12,822,353 136,296 1,023,819 13,982,468 26,892,266 66,000 26,958,266 $ 34,846,644 14,692 34,861,336 79,011,628 443,702 79,455,330 79,455,330 41,435,203 229,311 41,664,514 41,664,514 73,095,317 439,537 13,121 2,058,280 75,606,255 179,392,516 22,672 179,415,188 179,415,188 93,627,801 163,360 93,791,161 122,559,303 2,552,804 125,112,107 125,112,107 19,049,639 19,049,639 7,211,812 7,211,812 $ 2,170,080 2,170,080 3,576,684 3,576,684 3,576,684 8,935 8,935 8,935 7,373,356 595,973 7,969,329 1,270,511 1,270,511 1,270,511 726,158 726,158 $ 45,349,811 2,848,560 1,697,950 49,896,321 134,044,341 324,287 3,711,916 138,080,544 1,716,695 276,720 140,073,959 44,039,835 116,575 987,614 45,144,024 360,249 45,504,273 92,388,860 9,789,719 13,121 5,707,212 107,898,912 239,223,347 466,477 3,297,584 242,987,408 395,000 139,776 243,522,184 122,670,094 2,612,932 1,546,120 126,829,146 172,151,634 1,363,652 4,656,239 178,171,525 32,000 116,760 178,320,285 32,598,150 136,296 1,023,819 33,758,265 34,104,078 66,000 34,170,078 15-27 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 15-F CHANNEL DIMENSIONS Adopted Project Dimensions Improved Project Dimensions See Depth in Feet Bottom Depth in Feet Bottom Section (Below Mean Width (Below Mean Width Length in Text Project Section of Waterway Low Tide) (Feet) Low Tide) (Feet) Feet Miles 2. Brazos Island Harbor, TX 4. Corpus Christi Ship Channel, TX 5. Freeport Harbor, Tx 6. Galveston Harbor and Channel, TX Outer Bar and Jetty Channel Padre Island to Long Island Long Island to Goose Island Goose Island to Turning Basin Extension Turning Basin Extension Brownsville Turning Basin Port Isabel Channel via East Turnout West Wye, from Brownsville Channel Port Isabel Turning Basin Fishing Boat Harbor: West Basin Middle Basin East Basin Connecting Channel Entrance Channel Aransas Pass Outer Bar Channel Aransas Pass Jetty Channel Inner Basin at Harbor Island Channel to Port Aransas Port Aransas Turning Basin Anchorage Basin at Port Aransas Inner Basin to Mile 8.5 Mile 8.5 to LaQuinta Junction LaQuinta Junction to Corpus Christi Turning Basin Corpus Christi Turning Basin Industrial Canal Avery Point Turning Basin Channel to Chemical Turning Basin Chemical Turning Basin Tule Lake Channel Tule Lake Turning Basin Viola Channel Viola Turning Basin Channel to LaQuinta LaQuinta Turning Basin Turning Point at LaQuinta Channel Junction Jewel Fulton Canal Jewel Fulton Turning Basin Mooring Area at Ingleside: Mooring Area (a) Mooring Area (b) Outer Bar Channel Jetty Channel Quintana Turning Basin Channel to Brazosport Turning Basin Brazosport Turning Basin Channel to Upper Turning Basin Upper Turning Basin Channel to Stauffer Chemical Plant Stauffer Turning Basin Brazos Harbor Channel Brazos Harbor Turning Basin Entrance Channel Outer Bar Channel Inner Bar Channel Anchorage Basin Bolivar Roads Channel 38-36 36 36 36 36 36 36 36 36 15 15 15 15 15 47 45 45 12 12 12 45 45 45 45 45 45 45 45 45 45 45 45 45 45 45 12 12 45 45 47 45 45 45 45 45 45 30 30 36 36 42 42 40 36 40 300 200 200 300 500 1,000 200 200 1,000 370-305 370-305 370 270 100 700 600-730 730-1,720 100-150 200-4002 300-400 600-500 500 400 800 400 975 400 1,200 s 300 1,200 300-350 1,200 300-400 1,200 1,2503 100 200 150 150 400 400 7504 400 1,0004 375 1,2004 200 500 200 7504 800 800 800 2,8751 800 38-36 36 36 36 36 36 36 36 36 15 15 15 15 15 47 45 45 12 12 12 45 45 40-45 40 40 40 40 40 40 40 40 40 45 45 45 12 12 45 38 36 36 36 36 36 30 25 30 30 42 42 40 36 40 300 200 200 200 500 1,000 200 200 1,000 370-305 370-305 370 265 100 700 600 Irregular 100 2002 300-400 600-500 500 400 1,000 400 1,000 350 1,050 s 200 900 200-250 700-900 300-400 1,200 1,2503 100 200 150 300 200 200-350 744-800 350-375 600 200 500 200 525-675 800 800 800 2,875 800 2.5 2.1 9.6 3.2 1.3 2,670 0.5 1.4 0.8 1,300 0.2 1,470 0.3 1,200 0.2 1,470 .03 1,230 0.2 770 0.1 1.8 1.0 1,550 - 0.1 200 - 900 0.2 8.5 3.6 8.6 5,423 1.0 1.1 1,150 0.2 0.6 1,690 0.3 3.1 1,000 0.2 1.8 1,000 0.2 5.6 800 0.1 1,250 0.2 - 0.8 400 0.1 - 0.8 - 3.0 - 0.8 - 1.2 667 0.1 - 1.4 600 0.1 - 1.1 500 0.1 - 0.5 675 0.1 - 4.7 - 1.7 - 3.2 - 1.81 - 1.0 15-28 GALVESTON TEXAS DISTRICT CHANNEL DIMENSIONS Adopted Project Dimensions Improved Project Dimensions See Depth in Feet Bottom Depth in Feet Bottom Section (Below Mean Width (Below Mean Width Length in Text Project Section of Waterway Low Tide) (Feet) Low Tide) (Feet) Feet Miles Galveston Harbor and Channel, TX (cont'd) Bolivar Roads Channel to 43rd St. 8. Houston Ship Bolivar Roads to Morgan Point Channel, TX Morgan Point to Boggy Bayou Boggy Bayou to Greens Bayou Greens Bayou to Sims Bayou Hunting Bayou Turning Point Clinton Island Turning Basin Sims Bayou to Southern Pacific Slip Southern Pacific Slip to Houston Turning Basin Houston Turning Basin Upper Turning Basin Brady Island Channel Barbour Terminal Channel Turning Basin Five-Mile Cut Channel Light-Draft Channel: Upper Turning Basin to Jensen Drive Turkey Bend Channel Greens Bayou Channel: Mile 0 to Mile 0.36 Mile 0.36 to Mile 1.57 9. Matagorda Ship Outer Bar and Jetty Channel Channel, TX Channel to Point Comfort Approach Channel to Turning Basin Turning Basin Channel to Port Lavaca Lynn Bayou Turning Basin Channel to Harbor of Refuge North-South Basin East-West Basin Channel to Red Bluff 10. Sabine-Neches Sabine Bank Channel Waterway, TX Sabine Pass Outer Bar Channel Sabine Pass Jetty Channel Sabine Pass Anchorage Basin Sabine Pass Channel Port Arthur Canal Entrance to Port Arthur Turning Basins Port Arthur East Turning Basin Port Arthur West Turning Basin Channel connecting Port Arthur West Turning Basin and Taylors Bayou Turning Basin Taylors Bayou Turning Basin Sabine-Neches Canal, Port Arthur Canal to Neches River Turning Point at Mile 19.5 Neches River, Mouth to Maneuvering Area at Beaumont Turning Basin Turning Point, Mile 31.1 Turning Point, Mile 36.6 Turning Point, Mile 40.3 Channel Extension, Mile 40.3 40 40 40 40 40 40 40 40 36 36 36 10 16 16 8 10 10 36 15 38 36 36 36 12 12 12 12 12 6 42 42 40 40 40 40 40 40 40 40 40 40 40 40 40 40 40 36 1,125 400 400 300 300 900-1,0009 8009 300 300 400-1,000 150 60 100 1,100 125 60 60 175 100 300 300-2006 200-300 1,000 125 27-340 125 300 250 100 800 800 800-500 1,500 500 500 275-678 420 600 200-250 150-1,000 400 9004 40 1,125 40 40 40 40 40 40 40 36 36 36 10 16 16 8 10 10 36 15 38 36 36 36 12 12 12 12 12 6 42 42 40 40 40 40 40 40 40 40 40 40 40 40 40 40 40 36 400 1,0004 1,0004 1,000 4 350 400 400 300 300 948-1,0009 965-1,0709 300 300 400-1,000 150 60 100 1,100 125 60 60 175 100 300 300-2006 200-300 1,000 125 27-340 125 300 250 100 800 800 800-500 1,500 500 500 275-678 370-547 350-550 200-250 90-1,233 400 9004 400 1,000 1,000 1,300 350 15-29 TABLE 15-F - 3.9 - 26.2 - 12.8 - 2.4 - 5.3 1,375 - 1,592 - - 0.6 - 2.9 3,100 0.6 1,000 0.2 - 0.9 - 1.5 1,000 0.2 - 1.9 - 4.1 - 0.8 - 0.3 - 1.3 - 3.2 - 20.9 - 1.1 1,000 0.2 - 4.1 532 0.1 - 1.9 1,682 0.3 1,750 0.3 - 20.2 - 14.7 - 3.4 - 4.1 3,000 - - 5.6 - 6.2 - 0.3 1,765 0.3 1,610 0.3 - 0.6 3,470 0.7 - 11.2 8 - 18.3 700 * 930 8 1,530 8 1,265 0.2 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 15-F CHANNEL DIMENSIONS Adopted Project Dimensions Improved Project Dimensions See Depth in Feet Bottom Depth in Feet Bottom Section (Below Mean Width (Below Mean Width Length in Text Project Section of Waterway Low Tide) (Feet) Low Tide) (Feet) Feet Miles Sabine-Neches Maneuvering Area at Waterway, Beaumont Turning Basin 40 Irregular 40 Irregular 1,300 0.2 TX (cont) Beaumont Turning Basin 34 500 34 160-535 1,500 0.3 Beaumont Turning Basin Extension 34 350 34 300 - 0.4 Beaumont Turning Basin Extension to End of Project Channel Vicinity Bethlehem Steel Company 30 200 30 200 - 0.7 Sabine-Neches Canal, Neches River to Sabine River 30 200 30 200 - 4.4 Sabine River Channel, Mouth to Foot of Green Ave. 30 200 30 200 - 9.5 Orange Turning Basin 30 Irregular 30 Irregular 1,550 0.3 Orange Municipal Slip 30 200 30 150-200 2,435 0.5 Old Channel Around Harbor Island 25 150-200 25 150-200 - 2.4 Channel to Echo7 12 125 - - - - Adams Bayou 12 100 12 100 - 1.7 Cow Bayou 13 100 13 100 - 7.0 Orangefield Turning Basin 13 300 13 300 500 0.1 SAverage. 2 Includes 100-foot channel width. 3 Includes 450-foot channel to Corpus Christi. 4 Diameter. 5 Includes 350-foot channel width. * 300-foot width through Matagorda Peninsula. 7 Inactive Category. * Included in channel length. 9 Includes 300-foot channel width. 15-30 GALVESTON, TEXAS DISTRICT GULF INTRACOASTAL WATERWAY APALACHEE BAY, FLORIDA TO MEXICAN BORDER EXISTING PROJECT DIMENSIONS, PROVIDED FOR IN TRIBUTARY CHANNELS Tributary Channel Offats Bayou Main Channel West Wye Chocolate Bayou Channel 12-Foot Channel via East Turnout West Turnout 9-Foot Channel Turning Basin San Bernard River Channel Colorado River Channel Turning Basin Silting Basin Mouth of Colorado River Navigation Channel, GIWW to Gulf Turning Basin at Matagorda Channel to Palacios Turning Basin No. 1 Turning Basin No. 2 Connecting Channel Channel to Barroom Bay Channel to Victoria Main Channel via east Turnout Turning Basin West Turnout Channel Channel to Seadrift via South Turnout Turning Basin North Turnout from Channel to Victoria Harbor of Refuge at Seadrift Channel Basin Channel to Rockport Turning Basin Channel to Aransas Pass Turning Basin Channel to Conn Brown Harbor Conn Brown Harbor Channel to Port Mansfield Entrance Channel Approach Channel to Hopper Dredge Turning Basin Hopper Dredge Turning Basin Channel Across Padre Island and Laguna Madre Turnout Channels, East Side of Main Channel, GIWW North Turnout South Turnout Channel West Side of Main Channel, GIWW, to P.T. of Turnout Channels Turnout Channels, West Side of Main Channel, GIWW North Turnout South Turnout Authorized Improved Project Dimensions Project Dimensions Depth Depth (Feet Below Bottom (Feet Below Bottom Mean 'Width Mean Width Length Low Tide) (Feet) Low Tide) (Feet) Miles Feet 12 12 12 12 99 9 999 15-12 12 12 12 12 12 6 999 99 9 9999 14 14 14 14 16 16 16 14 12 12 14 12 12 125 125 125 125 100 600 100 100 400 150 200-100 350 125 200 300 150-480 60 100 600(avg) 100 100 250 100 100 200 200 475 175 300 125 300 250 100 300 100 100 100 100 200 200 12 12 12 12 9 999 12 12 12 12 999 99 9 9 14 14 14 14 2613 2613 2613 14 12 12 14 12 12 125 125 125 125 100 100 400 150 125 200 300 130-400 100 500(avg) 100 100 200 100 200 342(avg) 125-175 300 125 300 250 100 300 100 100 100 100 200 200 2.3 0.4 8.2 0.8 26.0 15.5 0.1 1.0 16.1 0.1 0.2 0.1 34.8 0.1 0.8 2.0 0.5 2.1 0.2 6.1 0.4 0.2 0.3 0.8 0.4 0.1 7.7 0.6 0.6 0.3 0.6 0.6 2,200 500 635 1,130 800(avg) 230 - - - 1,225 2,212 1,800 300 15-31 TABLE 15-G TABLE 15-G REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 GULF INTRACOASTAL WATERWAY APALACHEE BAY, FLORIDA TO MEXICAN BORDER EXISTING PROJECT DIMENSIONS, PROVIDED FOR IN TRIBUTARY CHANNELS Authorized Improved Project Dimensions Project Dimensions Depth Depth (Feet Below Bottom (Feet Below Bottom Mean Width Mean Width Length Tributary Channel Low Tide) (Feet) Low Tide) (Feet) Miles Feet Channel from P.T. of Turnout Channels to Approach Channel to Main Turning Basin 14 125 14 125 0.6 - Approach Channel to Main Turning Basin 14 200 14 200 0.3 - Main Turning Basin 14 400 14 400 0.2 1,250 Turning Basin Extension 14 1,000 14 1,000 0.1 580 Small Craft Basin 8 160 8 160 0.2 860 Shrimp Basin 12 350 12 350 0.3 1,450 Channel to Harlingen via South Turnout from Main Channel, GIWW 12 125 12 12511 25.812 - Turning Basin near Rio Hondo 12 400 12 400 0.1 500 North Turnout from Main Channel 12 200 12 200 0.7 - Port Isabel Side Channels Main Channel 12 125 12 125-90 0.6 - Main Channel 12 233-60 12 233-60 0.4 - South Leg 12 125 12 125 0.2 - Port Isabel Small Boat Harbor Entrance Channel 7 75 7 75 1.4 - Harbor Channel 6 50 6 50 0.3 - Boat Basin 6 Variable 6 72-501 0.2 1,308 1 Includes the construction of a salt water barrier at Mile 16.9. 2 Constructed 10 feet deep by 100 feet wide by local interests. East turnout channel constructed 150 feet wide. 3 Constructed by local interests. 4 Authorized to mile 13.2. Mile 8.2 to Mile 13.2 is in inactive category. s Authorized to Mile 31 above mouth (channel mile 29.41). Upper 3.4 miles was deauthorized under Section 12 of PL 93-251. 6 Includes a discharge channel from Matagorda, Texas, to the gulf which was dredged by local interests in 1939. (Maintenance will be discontinued upon completion of improvements authorized by R&H Act of 1968.) ? Authorized by R&H Act of 1968. Also provides for a dam across the present discharge channel, a new 250-foot wide by 20 to 23-feet deep discharge channel into Matagorda Bay, and a 15-foot by 200-foot wide entrance channel with parallel jetties from the gulf shoreline into the Gulf of Mexico. East jetty to be 3,500 feet long and west jetty 2,900 feet long. S Includes two protective breakwaters at entrance to turning basins. 9 In the inactive category for maintenance. o1A0 lso provides for two stone jetties at the gulf entrance about 1,000 feet apart. (North jetty constructed 2,300 feet long and south jetty constructed 2,270 feet long.) " South turnout is 200 feet wide. 12 Authorized to mile 31. Mile 25.8 to Mile 31 is in inactive category. - 15-32 GALVESTON, TEXAS DISTRICT TABLE 15-H DREDGING OPERATIONS See Section in Text Project Period Description Cubic Yards of Material Cost Corpus Christi Ship Channel, TX (New Work) Dredging Beacon 82 thru and including Chemical Turning Basin March 22 to September 30, 1985 960,360 1,474,200 Corpus Christi Ship Channel, TX (Maintenance) Dredging La Quinta Junction to Beacon 82 May 6 to August 2, 1985 4,473,808 1,638,223 Dredging channel to La Quinta and Turning Basin and Jewel Fulton Canal and Basin August 3 to September 30, 1985 1,273,990 547,5992 Freeport Harbor, TX (Maintenance) Dredging Entrance Channel October 5 to November 29, 1984 1,186,000 2,141,615 Dredging Inside Channel and Turning Basins January 8 to August 14, 1985 1,370,478 2,321,810 Dredging Entrance Channel August 19 to September 30, 1985 1,000,000 880,000 Galveston Harbor and Channel, TX (Maintenance) Dredging Galveston Channel May 14 to September 30, 1985 4,368,370 1,764,8943 Gulf Intracoastal Waterway between Apalachee Bay, FL, and Mexican Border (Galveston District)(Maintenance) Dredging main channel, Mile 297 to High Island October 1 to October 28, 1984 659,244 371,034 Dredging main channel, Colorado River to Matagorda Bay October 4 to December 17, 1984 1,988,752 672,041 Dredging main channel, Port Isabel to Mud Flats October 1, 1984 to January 23, 1985 1,433,857 398,506 Dredging main channel across Aransas Bay January 23 to February 18, 1985 942,584 232,819 Dredging main channel, High Island to Port Bolivar and Port Bolivar Channel March 27 to September 30, 1985 2,223,600 1,643,800 Dredging Tributary Channel to Harlingen and Channel to Port Mansfield April 14 to September 30, 1985 2,759,900 2,043,225 Dredging main channel, San Antonio Bay to Aransas Bay May 6 to August 3, 1985 1,246,438 992,201 Houston Ship Channel, TX (Maintenance) Dredging Redfish Reef to Morgan Point and Shallow Draft Channels October 1, to November 1, 1984 947,103 671,035 Dredging Sims Bayou to and including Turning Basin October 1 to December 19, 1984 444,992 179,881 Dredging Morgan Point to Carpenter Bayou October 6, 1984 to March 24, 1985 3,252,658 2,622,030 Matagorda Ship Channel, TX (Maintenance) Dredging Channel to Port Lavaca and Harbor of Refuge February 21 to March 18, 1985 921,934 282,892 Sabine-Neches Waterway, TX (Maintenance) Dredging Upper Reach Sabine Pass Channel and Port Arthur Canal October 1 to December 17, 1984 1,553,679 378,5674 Dredging Middle Reach Sabine Pass Channel January 16 to March 29, 1985 887,658 315,952 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Sabine-Neches Waterway, TX (Maintenance) Dredging Port Arthur Turning Basins and Junction Area, Port Arthur and SabineNeches Canals August 19 to September 30, 1985 1,439,490 738,700 Dredging Outer Bar and Outer Bank Channels (Hopper Dredge WHEELER) June 13 to September 7, 1985 5,353,000 4,624,000 Texas City Channel, TX (Maintenance) Dredging Texas City Channel October 1, 1984 to April 8, 1985 2,840,649 1,370,883 15-34 GALVESTON, TEXAS DISTRICT JOBS ACT (P. L. 98-8, March 24, 1983) TABLE 15-I Total Cost to Project Funding FY 83 FY 84 FY 85 Sep. 30, 1985 Arroyo Colorado River, Rio Hondo, TX Brazos Island Harbor, TX Buffalo Bayou and Tributaries, TX Corpus Christi Ship Channel, TX Freeport Harbor, TX Galveston Harbor and Channel, TX Sabine Neches Waterway, TX Gulf Intracoastal Waterway, TX Matagordo Ship Channel, TX New Work Approp. Cost Maint. Approp. Cost Maint. Approp. Cost Maint. Approp. Cost Maint. Approp. Cost Maint. Approp. Cost Maint. Approp. Cost Maint. Approp. Cost Maint. Approp. Cost $170,000 0 2,800,000 2,473,028 254,000 42,132 31,000 27,308 2,516,200 2,030,076 281,000 30,219 1,547,200 324,325 4,940,000 3,498,040 5,000 3,205 $ 0 162,545 (-)500 326,472 (-)1,400 210,468 (-)3,600 92 (-)300 465,528 (-)100 250,681 (-)489,600 733,275 497,200 1,911,401 $ 0 7,434 0 0 0 0 0 0 0 20,296 0 27,759 $170,000 169,979 2,799,500 2,799,500 252,600 252,600 27,400 27,400 2,515,900 2,515,900 280,900 280,900 1,057,600 1,057,600 5,437,200 5,437,200 (-)1,700 95 3,300 3,300 15-35 FORT WORTH, TX DISTRICT* District includes that portion of Texas south of Red River drainage basin exclusive of drainage basin of Rio Grande and its tributaries above and including Pecos River; exclusive of drainage basins to all short streams arising in coastal plain of Texas and flowing into the Gulf of Mexico, including entire basins of Buffalo Bayou, San Jacinto, San Bernard, Lavaca, Navidad, Mission, and Arkansas Rivers; exclusive of lower basins of major streams flowing into the gulf as follows: Sabine River, Texas and Louisiana, downstream from U.S. Highway 190 crossing at Bon Wier, Texas; Neches River downstream from Town Bluff gaging station; Trinity River downstream from Texas State Highway 45 crossing at Riverside, Texas; Brazos River downstream from confluence with Navasota River; Colorado River downstream from gaging station at Austin; Guadalupe River downstream from confluence with San Marcos River; San Antonio River downstream from confluence with Escondido Creek; Nueces River downstream from confluence with Frio and Atascosa Rivers; and exclusive of Agua Dulce, San Fernando, and Olmos Creek basins draining into Baffins Bay; coastal area south thereof to Rio Grande and south to the northern boundaries of Newton, Jasper, Tyler, Polk, Trinity, Walker, Waller, Austin, Fayette, Gonzales, Karnes, Live Oak, Jim Hogg, Zapata; the northern and western boundaries of McMullan; and the western boundaries of Montgomery and Duval Counties, Texas. District also includes those portions of the Sulphur River and Cypress Creek Watershed located in the State of Texas; that portion of western Louisiana in Sabine River drainage basin upstream from U.S. Highway 190 crossing at Bon Wier, Texas. IMPROVEMENTS Navigation 1. Trinity River Project, TX ................ Flood Control 2. Aquilla Lake, TX ...................... 3. Bardwell Lake, TX.................... 4. Belton Lake, TX ....................... 5. Benbrook Lake, TX .................... 6. Big Sandy Lake, TX................... 7. Boggy Creek, TX.................... 8. Canyon Lake, TX ...................... 9. Cooper Lake and Channels, TX .......... 10. Elm Fork Floodway, TX................ 11. Ferrells Bridge Dam-Lake O'The Pines, TX .................................. 12. Grand Prairie, TX (Landfill)............. 13. Grand Prairie, TX (Meyers Road)........ 14. Grapevine Lake, TX................... 15. Hords Creek Lake, TX.................. 16. Joe Pool Lake, TX (formerly Lakeview Lake)................................ 17. Lavon Lake, TX...................... 18. Lavon Lake Modification and East Fork 19. 20. 21. 22. 23. 24. 25. 26. 27. 28. 29. Channel Improvement, TX ............... Lewisville Dam, TX .................... Millican Lake, TX ..................... Navarro Mills Lake, TX................. O. C. Fisher Dam and Lake, TX .......... Proctor Lake, TX....................... Ray Roberts Lake, TX (Aubrey) .......... San Antonio Channel Improvement, TX .... San Gabriel River, TX .................. Somerville Lake, TX ................... Stillhouse Hollow Dam, TX .............. Waco Lake, TX...................... Page 16-2 16-2 16-3 16-3 16-3 16-3 16-4 16-4 16-4 16-5 16-5 16-6 16-6 16-6 16-7 Flood Control (cont.) 30. Wright Patman Dam and Lake, TX ....... 31. Inspection of completed flood control projects............................. 32. Scheduling flood control reservoir operations ... ........................ 33. Other authorized flood control projects ..... 34. Flood control work under special authorization......................... Multiple-Purpose Projects Including Power 35. Belton Lake Modification, TX ............ 36. Dam "A" Lake, TX.................... 37. Rockland Lake, TX ..................... 38. Sam Rayburn Dam and Reservoir, TX..... 39. Town Bluff Dam-B. A. Steinhagen Lake, T X ... .............................. 40. Town Bluff Hydropower, TX............. 41. Whitney Lake, TX.................... 16-7 General Investigations 16-7 42. Surveys ............................. 43. Collection and study of basic data ......... 16-8 16-8 16-8 16-9 16-9 16-9 16-9 16-10 16-10 16-10 16-11 16-11 Tables Table Table Table 16-A 16-B 16-C Table 16-D Table 16-E Table 16-F Cost and Financial Statement ..... Authorizing Legislation........... Other Authorized Flood Control Projects.. ..................... Inspection of Completed Flood Control Projects................. Flood Control Work Under Special Authorization ............ Jobs Act, Special Authorization PL 98-8...................... Page 16-11 16-11 16-11 16-12 16-12 16-12 16-12 16-12 16-12 16-12 16-13 16-13 16-13 16-13 16-14 16-18 16-21 16-21 16-22 16-23 16-1 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Navigation 1. TRINITY RIVER PROJECT, TX The project authorized by the River and Harbor Act of 1965 (H. Doc 276, 89th Cong., 1st Sess.) consists of five major components: Multiple-Purpose Channel, Tennessee Colony Lake, Dallas Floodway Extension, West Fork Floodway, and Water Conveyance Facilities. For the last full report on the project as authorized, see Annual Report of 1978. The project information present herein is based on the tentatively selected project plan presented in the Draft General Design Memorandum. The plan consists of three structural components: Dallas Floodway Extension, Tennessee Colony Lake, and a Channel to Liberty in the lower basin. The estimated cost of the improvements is $1,225,000,000 including $81,000,000 non-Federal cost for land acquisition and relocation required for the local protection features (Oct. 1, 1984, base price). Operations during fiscal year. Preconstruction planning continued. CHANNEL TO LIBERTY: Location. The Channel to Liberty begins at the Houston ship channel, crosses the bay area in an easterly direction to intersect the existing Double Bayou channel turns northward along the coastline to Wallisville Lake and then continues northward through the lake area along the course of the Trinity River to RM 45 above Liberty, Texas. Existing project. The navigation portion of the channel will have a width of 200 feet with a depth of 12 feet and will extend from the Houston ship channel in Galveston Bay to the port of Liberty, Texas. The flood control portion of the channel will have a bottom width of 200 feet with a depth of 30 feet, and will extend from Wallisville Lake to RM 45 above Liberty, Texas. Estimated Federal cost of the improvements is $166,000,000 and estimated non- Federal cost is $9,200,000 for a total estimated cost of $175,200,000 (Oct. 1, 1985, base price.) Local cooperation. Local interests are required to: (a) provide, without cost to the Federal Government, all lands, easements and rights-of-way required for construction, operation and maintenance of the project, (b) accomplish, without cost to the Federal Government, all relocations and alterations to existing improvements, other than highway bridges over new land cuts and railroad bridges required for the construction of the project, (c) maintain and operate the flood control portion of the channel upstream of Liberty, Texas, and (d) reimburse the Federal Government for onehalf of the separable costs allocated to recreation and fish and wildlife enhancement. This reimbursement is presently estimated at $245,000, exclusive of interest. TENNESSEE COLONY LAKE: Location. The Tennessee Colony dam site is located at River Mile 341.7 on the Trinity River about 22 miles west of Palestine, Texas. The lake would extend into Freestone, Anderson, Henderson, and Navarro Counties, and would control a drainage area of 12,302 square miles. Existing project. The plan of improvement provides for the constructinn of an earthfilled dam with a maximum height of 123 feet above the streambed and a total embankment ]ngth of 42,350 feet with a gated concrete spillway. The lake will have a total controlled storage of 3,455,000 acre-feet and a water surface area of 114,400 acres at the top of the flood control pool and 68,100 acres at the top of the conservation pool. The total storage includes 2,269,500 acre-feet for flood control, 1,040,000 acre-feet for conservation, and 145,500 acre-feet for sediment reserve. Estimated Federal cost of the improvement is $913,000,000 (Oct. 1, 1983, base price). Local cooperation. Local interests are required to reimburse the Federal Government for costs allocated to water supply storage and one-half of the separable cost allocated to recreation and fish and wildlife enhancement. This reimbursement is presently estimated at $461,754,000 for water supply and $9,533,000, for recreation (excluding future recreation facilities), for a total cost of $471,287,000, exclusive of interest. DALLAS FLOODWAY EXTENSION; Location. Dallas Floodway Extension is located on the Trinity River in the City of Dallas, Dallas County, Texas. Existing project. The plan of improvement provides for extending the existing Floodway downstream about 9 miles to the confluence of the Trinity River and Five Mile Creek. The plan consists of a leveed floodway and flood conveyance improvement (channel) along the main stem, Five Mile Creek and White Rock Creek. Maintained free of encroachments, the levees and channels would provide Standard Project Flood protection for approximately 7,300 acres of urban lands currently subject to flooding. The estimated Federal cost is $68,000,000 and estimated non-Federal cost is $63,000,000 for a total estimated cost of $131,000,000 for the improvement (Oct. 1, 1983, base price). Local cooperation. Local interests are required to: (a) provide, without cost to the Federal Government, all lands, easements and rights-of-way necessary for construction, maintenance and operation of the project, (b) accomplish, without cost to the Federal Government, all alterations to existing improvements, other than railroad bridges required for the construction of the project, (c) maintain and operate the project after completion, and (d) reimburse the Federal Government for one-half of the separable costs allocated to recreation and fish and wildlife enhancement. This reimbursement is presently estimated at $1,878,000 (excluding future recreation) exclusive of interest. Flood Control 2. AQUILLA LAKE, TX Location. On Aquilla Creek in Hill County, Texas, with the dam at River Mile 23.3, about 6.8 miles southwest of Hillsboro, Texas, and about 24.0 miles north of Waco, Texas. (See U.S. Geological Survey maps, Aquilla and Peoria, Texas, quadrangle scale 1:24,000.) Existing project. Plan of improvement provides for an earthfill dam 104.5 feet high and 11,800 feet long with an uncontrolled concrete spillway 1,200 feet long on the left abutment, creating a lake with a total storage capacity of 146,000 acre-feet, including 86,700 acre-feet for flood control, 33,600 acre-feet for water supply, and 25,700 acre-feet for sediment reserve. Drainage area above damsite is 294 square miles. Estimated cost is $46,100,000. Construction was started March 1977, and project was ready for beneficial use April 29, 1983. 16-2 FORT WORTH, TEXAS DISTRICT Local cooperation. The Water Supply Act of 1958, as amended, and the Federal Water Project Recreation Act of 1965 and Section 221, Flood Control Act of 1970 apply. A contract with the Brazos River Authority for water supply storage was approved by the Secretary of the Army, June 29, 1976. To date, the Authority has paid $66,948 toward principal and $7,255 to operation and maintenance. Benefits accrued to Aquilla project: Accumulated flood damages prevented through FY1985 were $1,084,000. Operations during fiscal year. Routine operation and maintenance continue. 3. BARDWELL LAKE, TX Location. Dam is on Waxahachie Creek, 5 river miles upstream from its confluence with Chambers Creek, a tributary of the Trinity River, and about 5 miles south of Ennis, Ellis County, Texas. Existing project. For a description of completed improvement and authorizing act see Annual Report of 1969. Construction of project was started August 1963 and completed for beneficial use in November 1965. Estimated cost of project is $12,941,000. Local cooperation. Local interests must reimburse the Federal Government for costs allocated to increased water supply storage under the terms of the Water Supply Act of 1958. A Contract was approved by the Secretary of the Army on June 24, 1963, and the Trinity River Authority, a State agency, agreed to fulfill all requirements of local cooperation. To date the authority has paid $269,411 toward principal and $402,778 toward annual cost of operation and maintenance of project, including cost of operating 10-foot conduit. Operations during fiscal year. Routine operation and maintenance continued. Recreation facilities under Code 710 remain. Benefits accrued to Bardwell project: Accumulated flood damages prevented through FY 1985 were $9,032,900. 4. BELTON LAKE, TX Location. Dam is on Leon River about 16.7 miles above confluence of Leon and Lampasas Rivers and about 3 miles north of Belton, Texas. (See Geological Survey base map, scale 1:500,000 and Geological Survey, Belton sheet, scale 1:62,500.) Existing project. For a description of completed improvement and authorizing acts see Annual Report of 1962. Estimated cost of project is $18,410,000. Construction started June 1949 and project and was ready for beneficial use in March 1954. Raising water supply pool: Construction started in July 1970 and the pool raise is complete. Local cooperation. Section 2, Flood Control Act of 1938, applies. A contract with Brazos River Authority, a State agency, for remaining water supply storage in reservoir was approved by Secretary of the Army on January 15, 1958, at an estimted cost of $1,602,822. To date $1,014,623 has been paid. Under the contract Brazos River Authority must also pay annually 11.2 percent of actual annual cost of operation and maintenance. To date $908,243 has been paid. An interim contract with Brazos River Authority for emergency use of water supply storage in project was approved by Secretary of the Army on January 2, 1957. Amount of $152,435 paid by authority on March 21, 1957 for use of these facilities was credited to interest and principal payable under formal water supply contract. Operations during fiscal year. Routine operation and maintenance continued. Recreation facilities under Code 710 remain. Benefits accrued to Belton project: Accumulated flood damages prevented through FY 1985 were $105,983,100. 5. BENBROOK LAKE, TX Location. Dam is in Tarrant County, Texas, on Clear Fork of Trinity River 15 river miles upstream from its confluence with West Fork of Trinity River about 10 miles southwest of downtown Fort Worth, Texas. Existing project. For description of completed improvement and authorizing acts see Annual Report for 1962. Estimated cost of project is $14,544,000. Construction of project was started May 1947 and ready for beneficial use in September 1952. Local cooperation. Section 2, Flood Control Act of 1938, applies. No water supply storage is included in project. In 1956, Congress passed legislation enabling the city of Fort Worth to purchase conservation storage space in Benbrook lake. Contracts have been negotiated with the city of Fort Worth and the Benbrook Water and Sewer Authority for the use of portions of the navigation storage for water supply purposes until such storage is required for Trinity River Navigation. To date $72,110 has been paid by the city of Fort Worth and $55,249 by Benbrook Water and Sewer Authority. A cost sharing contract with the city of Benbrook for Recreation Development was approved by the Secretary of the Army May 20, 1977. To date, $15,707 has been paid. Operations during fiscal year. Routine operation and maintenance continued. Recreation facilities under Code 710 remain. Benefits accrued to system consisting of Benbrook Lake, Clear Fork and West Fork Floodways: Accumulated flood damages prevented through FY 1985 are estimated at $48,313,200. 6. BIG SANDY LAKE, TX Location. The project is located on Big Sandy Creek, a tributary of the Sabine River, and is virtually contained in Wood County, with a small area extending into Upshur County. The damsite is located at River Mile 15.3 about 6 miles northwest of Big Sandy, Texas. Existing project. The project provides for construction of an earth and rock fill dam with a maximum height of 94.5 feet above streambed and a total length of 6,200 feet, including the concrete spillway. Big Sandy Lake would have a total controlled storage of 418,200 acre-feet and a water surface area of 16,580 acres at elevation 382.0, top of flood control pool. At elevation 367.5, top of conservation pool, the lake would have an area of 10,810 acres and a storage capacity of 221,200 acre-feet. Project was authorized by the Flood Control Act of 1970 (PL 91-611) and is a unit in the comprehensive base-wide plan of water resource development. Estimated cost of project is $99,100,000. Local cooperation. Water Supply Act of 1958, as amended, and the Federal Water Project Recreation Act of 1965 apply. The Sabine River Authority of Texas and the 16-3 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Texas Water Development Board are the local project sponsors. Operations during fiscal year. March 25, 1982, Ph I GDM was recommended for termination due to lack of present Federal interest in the project. Project was recommended to be reclassified to inactive status December 29, 1982, based on the infeasibility of the project. 7. BOGGY CREEK, TX - COLORADO RIVER AND TRIBUTARIES Location. In southeast portion of the city of Austin, Texas, which is about 160 miles north of Houston and approximately 200 miles south of Dallas-Fort Worth area. Existing project. The recommended plan consists of concrete trapezoidal channel on Boggy Creek beginning just above Webberville Road and extending downstream about 2.2 miles to just below Jain Lane. From there, a grass lined channel would extend further downstream and transition into the natural channel at Ed Bluestein Boulevard, a distance of about 0.7 miles. New bridges would be required at four street crossings and two railroad crossings. The plan calls for acquisition of 54 acres of land adjacent to the lower end of the channel to mitigate habitat losses and also to provide for environmental quality enhancement. About 3.25 miles of trails along the channel and 0.95 miles in the EQ/mitigation area will also be provided. Estimated Federal cost is $16,200,000 and $8,800,000 non-Federal cost (Oct. 1, 1985 base price). The proposed flood control channel will provide capacities for the 100 year flood. Design will provide for containment of flows within the banks of the improved channels. Bottom widths for the concrete channel will vary from 60 feet to 90 feet, and top widths from 80 feet to 120 feet. Local cooperation. In accordance with the President's 1978 Cost Sharing Policy and the recommendations contained in the reporting document, the State of Texas is required to make a cash contribution of 5 percent of construction costs associated nonvendible outputs. The city of Austin is required to provide a cash or in-kind contribution equal to 20 percent of the project first costs associated with flood control benefits and 20 percent of the associated mitigation lands. The city is also required to provide 50 percent of the recreational development cost and 25 percent of the EQ enhancement lands. The city will also be required to hold and save the United States free from damages due to the construction work, operate and maintain all works after completion, prevent any obstruction or encroachment that would reduce the flow capacity of the project, provide and maintain adequate lateral drains and channels, publicize flood plain information for all streams in the watershed and adopt and enforce regulations to minimize damages to future developments within the 100-year flood plain, and administer and assure access to the recreational facilities and lands to all on an equal basis. Operations during fiscal year. A reevaluation of the Interim Survey Report was submitted May 5, 1982, and approved May 18, 1982. The Phase II GDM was submitted in January 1984. Specific authorization for construction of Boggy Creek is pending. Preconstruction planning continued. 8. CANYON LAKE, TX Location. Dam is on Guadalupe River, 303 miles above its mouth, and about 12 miles northwest of New Braunfels, Comal County, Texas. Existing project. For a description of completed improvement and authorizing act see Annual Report of 1969. Construction started April 1958 and project completed for beneficial use June 1964. Estimated cost of project is $21,732,000, including $1,400,000 contributed by local interests. Local cooperation. Local interests (Guadalupe-Blanco River Authority) will utilize water impounded for water supply and streamflow regulation for development of electric power. In a formal contract approved by Chief of Engineers on October 24, 1957, Guadalupe-Blanco River Authority agreed to fulfill all requirements of local cooperation. Required contribution of $1,400,000 was made in full by Guadalupe-Blanco River Authority. The estimated cost of the Water Storage contract is about $9,000,000. To date $1,113,626 has been paid. In addition, $22,848 was contributed for installation and operation of reservoir leakage gages. Under the contract the authority must pay 34.8 percent of actual annual cost of operation and maintenance. To date $822,187 has been paid. Operations during fiscal year. Regular funds: Routine operation and maintenance continued. Recreation facilities under Code 710 remain. Benefits accrued to Canyon project: Accumulated flood damages prevented through FY 1985 were $54,507,700. 9. COOPER LAKE AND CHANNELS, TX Location. Cooper Dam and Reservoir is located in northeast Texas about 4 miles southeast of Cooper, 13 miles north of Sulphur Springs, and is at river mile 23.2 on the South Sulphur River. The South Sulphur River rises in Fannin County, Texas, and flows gennerally east for about 80 miles to its confluence with the North Sulphur River to form the Sulphur River. Existing project. The authorized plan of improvement consists of a multipurpose reservoir with levee and channel improvements on the Sulphur River. The reservoir consists of a rolled earthfill dam with a maximum height of about 73 feet, 28,070 feet long at its crest, an uncontrolled Ogee Weir Spillway and a separate Outlet Works structure. The reservoir surface area will be 22,740 acres at the top of the flood control pool, 19,305 acres at the top of the water supply pool, and 5,084 acres at the top of the sediment pool. The reservoir will contain 131,400 acre-feet of flood control storage, 273,000 acre-feet of municipal and industrial water supply storage, and 37,000 acre-feet of sediment storage. Construction of the project began in July 1958 and, to date, approximately 98 percent of the lands required for project construction have been acquired and 98 percent of the levees and 100 percent of the channel work have been completed. Approximately 14.8 miles of the South Sulphur River and 6.3 miles of the Middle Sulphur River channels have been excavated. Approximately 3.4 miles of levee embankment on the South Sulphur River and 7.3 miles on the Middle Sulphur River have been constructed upstream of the Cooper Reservoir. About 10.5 miles of levee on the 16-4 FORT WORTH, TEXAS DISTRICT North Sulphur River, 8.2 miles of levee on the Sulphur River, 14 miles of levee on Cuthand Creek, and 4.2 miles of levee on Brushy Creek were strengthened; 0.5 mile of levee on Kickapoo Creek was enlarged; and 15.3 miles of new channel in Cuthand Creek, 0.8 mile of new channel in Brushy Creek, and 0.2 mile of cutoff channel in Kickapoo Creek were excavated; all downstream from Cooper Reservoir. Lack of funds and spending limitations prevented construction of the levees and channel work between April 1964 and Februrary 1971. Construction was started again, however, in May 1971. The Texas Committee on Natural Resources, et al, secured an injunction to halt construction on the project pending preparation of an Environmental Impact Statement (EIS), required by the National Environmental Policy Act of 1969. A statement was prepared and filed on June 24, 1977. The plan recommended, in the Final EIS, minimized further construction of the authorized channels and provided for construction of the reservoir and downstream levees. The sufficiency of the Final EIS was challenged in the court and in December 1978 the U.S. District Court for the Eastern District of Texas ruled the statement inadequate, citing five deficiencies and halting all further construction. A Supplemental EIS to comply with the court's decision was prepared and filed with the Environmental Protection Agency in March 1981. The recommended plan of improvement consists of the multipurpose lake, 0.9 mile of levee, and the acquisition of 25,500 acres of wildlife mitigation lands. All remaining channel and levee work was deleted from the recommended plan. The Supplemental EIS was filed with the court in July 1981 and numerous motions, documents, affidavits, and briefs were subsequently filed. Estimated Federal cost (Oct. 1, 1985 base price) is $129,000,000, non-Federal cost for land for the levees is $227,000 and in addition $50,425,000 is to be reimbursed by water supply users over a 50-year period. The project was transferred to the Fort Worth District at the end of FY 1979. Local cooperation. Except for Cooper Reservoir, local interest must furnish lands and rights-of-way and alter and relocate highways and related facilities and utilities, except railroads, for construction; hold and save the United States free from damages; maintain and operate all works after completion, and preserve channel capacities by preventing encroachment. Local agencies furnished rights-of-way for the first two phases of work on the levees and channel downstream from Cooper Dam. Right-of-way acquisition for the second phase was also essentially complete when construction was halted. Assuring agencies are the following counties in Texas: Delta, Hunt, Franklin, Lamar, Morris, Hopkins, Titus, and Red River. Basic assurances have been received. Supplemental assurances covering Public Law 91-646 have not been received from Delta, Lamar, Morris, or Hunt Counties. Operations during fiscal year. After the Supplemental EIS was filed in July 1981, numerous motions, documents, affidavits, and briefs were filed through October 1982. On December 30, 1982, the U.S. District Court issued a 95-page order continuing the permanent injunction. On March 22, 1983, the order was revised and Judge William Wayne Justice issued an Amended Memorandum Opinion and a Permanent Injunction against the construction of Cooper Lake. The Government filed a Notice of Appeal with the court in May 1983. Since that time, several briefs have been filed with the New Orleans Fifth Circuit Court of Appeals. Current action centers on the Appeal and resolution of the litigation. On July 16, 1984, litigation was resolved and the injunction was released. Contracts awarded during FY1985 include the following: Reloc. Lone Star Gas Pipeline and Alteration for S. Access Rd, awarded July 24, 1985; and S. Access Rd., awarded April 17, 1985. Through FY1985 the following is approximately complete: Levees and channels, 98 percent; Real Estate, 97 percent; Embankments, Spillway and Outlets, 0 percent. 10. ELM FORK FLOODWAY, TX Location. The project is located in Dallas and Denton Counties, Texas. A portion of the improvement will be in and adjacent to the Cities of Dallas, Irving and Farmers Branch, Texas. Existing project. Improvement of the Elm Fork of the Trinity River from the mouth to Lewisville Dam and along Denton Creek, a tributary of the Elm Fork to Grapevine Dam. The plan of improvement provides for enlargement and realignment of about 22 miles of the Elm Fork, enlargement and realignment of about 20 miles of tributary channels, construction of about 39 miles of new levee, rehabilitation of about 2 miles of existing levees, modification of 14 street and highway bridges, 4 railroad bridges and alteration of utilities. Estimated Federal cost of these modifications is $60,700,000, and non-Federal estimated cost is $88,600,000, a total of $149,300,000 (Oct. 1, 1983, base price). Local cooperation. Local interests are required to provide (without cost to the Federal Government) except for the main channel thereof, all lands, easements, utilities and bridge relocations (except railroad bridges) necessary for construction and operation of the project. Assurances were signed March 20, 1969 by the Trinity River Authority, a State agency, that they would provide items required of local interest. Operations during fiscal year. Preconstruction planning was suspended in 1973. Further studies have been delayed until a definite plan has been accepted by local interests. 11. FERRELLS BRIDGE DAM-LAKE O' THE PINES, TX Location. On Cypress Creek in Marion, Harrison, Upshur, Morris, Camp, and Titus Counties, Texas, 8 miles west of Jefferson, Texas. Existing project. An earth-fill dam 10,600 feet long and 77 feet high includes a 200-foot spillway with a capacity of 68,200 cubic feet per second. Reservoir controls runoff from 850 square miles of drainage area, and has a gross storage capacity of 842,100 acre-feet, including 587,200 acrefeet flood control storage, 3,800 acre-feet conservation storage, and 251,100 acre-feet for municipal and industrial water supply. Reservoir extends 28 miles upstream. Project affords substantial flood protection of Cypress Creek Valley from damsite to confluence with Red River and, together with operation of other reservoirs proposed in Red River Basin, will provide flood protection along main stem of Red River below Denison Dam. Construction commenced in January 1955 and was completed in June 1960. Estimated 16-5 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Federal cost of project is $17,231,700 (Oct. 1, 1983, base price), including $4,349,200 for Code 711 and $399,739 accelerated Public Works fund. This project transferred to the Fort Worth District as of the end of FY 1979. Local cooperation. None required. Operations during fiscal year. Routine operation and maintenance continued. Recreation facilities under Code 710 remain. Benefits accrued to Ferrells Bridge Dam-Lake O' The Pines project: Accumulated flood damages prevented through FY 1985 were $6,139,000. 12. GRAND PRAIRIE, TX, SANITARY LANDFILL Location. The project is located at a bend of the West Fork of the Trinity River, Texas, approximately 19,500 feet upstream of the confluence of the West Fork and Elm Fork of the Trinity River. This bend in the river is adjacent and north of the city of Grand Prairie sanitary landfill which lies within Dallas County and is located in northeast Grand Prairie. Existing project. The project provides for the construction of a cutoff channel which will eliminate an oxbow in the river, and prevent future damage to the city's sanitary landfill. The cutoff channel will have a bottom width of 30 feet with side slopes of 1 vertical to 3 horizontal. Excavated material from the cutoff channel will be used to plug each end of the oxbow and to restore the damaged levee at the sanitary landfill. Culverts placed through the plugs will allow for minor flows through the oxbow thus maintaining the water quality. The total Federal and non-Federal cost of the project is $595,000 (Oct. 1, 1983, base price). Local cooperation. In accordance with Section 14 of the Flood Control Act of 1946 as amended, the city of Grand Prairie is required to assume full responsibility for all project costs in excess of the Federal cost limitation of $250,000. In addition, the city is required to provide without cost to the United States all lands, easements, and rightsof- way necessary for construction and maintenance; bear the cost of all alteration and relocations of utilities, storm drains, roads, highway bridges, and community services; hold and save the United States free from damages due to construction work; operate and maintain all works after completion and prevent any obstruction or encroachment that would reduce the flow capacity of the project; publicize and notify all interested parties that the project will not provide protection from the occurrence of storms greater than the project design flood; comply with Public Law 91-646, approved January 2, 1971, and with the requirements of Section 221, Public Law 91,611, approved December 31, 1970, as amended. Operation during fiscal year. Contract for Channel Realignment and Fence Restoration at Sanitary Landfill was awarded September 29, 1983. Construction for the project was completed in 1985. 13. GRAND PRAIRIE, TX, STREAMBANK EROSION AT MEYERS ROAD Location. The project is located at a bend of the West Fork of the Trinity River approximately 6.1 miles upstream of the confluence of the West Fork and Elm Fork of the Trinity River. This bend in the river is adjacent to Meyers Road which lies within Dallas County and is located in northeast Grand Prairie. More specifically Meyers Road is north of Interstate Highway 30 and west of the city's sanitary landfill. Existing project. The project consists of slope restoration with riprap sideslopes, one verticle on two horizontal, and a riprap toe. The improvement will extend a distance of approximately 500 feet along the streambank adjacent to Meyers Road. This improvement will maintain the natural course of the river and will ensure the integrity of the roadway. The total Federal and non-Federal estimated cost of the project is $300,000 (Dec. 1, 1983, price level). Local cooperation. In accordance with Section 14 of the Flood Control Act of 1946 as amended, the city of Grand Prairie is required to assume full responsiblity for all project costs in excess of the Federal cost limitation of $250,000. In addition, the city is required to provide without cost to the United States all lands, easements, and rights-of-way necessary for construction and maintenance; bear the cost of all alteration and relocations of utilities, storm drains, roads, highway bridges, and community services; hold and save the United States free from damages due to construction work; operate and maintain all works after completion and prevent any obstruction or encroachment that would reduce the flow capacity of the project; publicize and notify all interested parties that the project will not provide protection from the occurrence of storms greater than the project design flood; comply with Public Law 91-646, approved January 2, 1971, and with the requirements of Section 221, Public Law 91-611, approved December 31, 1970, as amended. Operation during fiscal year. Contract for Streambank Erosion at Meyers Road was awarded January 25, 1984. 14. GRAPEVINE LAKE, TX Location. Dam is in Tarrant County, Texas, on Denton Creek, 11.7 river miles upstream from its confluence with Elm Fork of Trinity River and about 20 miles northwest of City of Dallas, Texas. Existing project. For description of completed improvement and authorizing act, see Annual Report for 1962. Estimated cost of project is $18,896,000, including $2,040,000 contributed by local interests. Construction of project was started December 1947 and ready for beneficial use in July 1952. Local cooperation. A contract with Dallas County Park Cities Water Control and Improvement District No. 2 for 50,000 acre-feet of water supply storage was approved by Secretary of the Army on March 21, 1955. Park Cities paid the required $607,000. A contract with City of Dallas for 85,000 acre-feet of water supply storage was approved by Secretary of the Army on March 17, 1954. Dallas paid the required $1,433,026. A contract with City of Grapevine, Texas, for 1,250 acre-feet of water was approved by Secretary of the Army on September 14, 1953, at an estimated cost of $22,654. A contract for Interim Use of Navigation Storage with city of Grapevine was approved by Secretary of the Army on February 27, 1981, at an estimated cost of $684,000. To date $59,430 has been paid. Above contracts include payment of operation and maintenance costs as follows: Dallas County Park Cities Water Control and Improvement District No. 2, a pro rata 16-6 FORT WORTH, TEXAS DISTRICT part of the actual annual cost, which part to be not less than $2,000 nor more than $3,000; Dallas, 9.2 percent of actual anuual cost; and Grapevine, its pro rata part of actual annual cost (estimated at $79.55 annually and included in total annual payment). Following operation and maintenance payments have been made: Park Cities $99,939, Dallas $453,290 and Grapevine $77,459. Operations during fiscal year. A contract for modification of Embankment and Spillway was awarded September 30, 1983 and continues. The proposed plan of improvement provides for spillway modification by construction of spillway chute and stilling basin and a berm on the downstream side of the main embankment, and completion in FY 1986. Recreation facilities under Code 710 remain. Benefits accrued to system comprised of Lewisville Lake, Grapevine and Dallas Floodway: Accumulated flood damages prevented through FY 1985 were $804,444,800. 15. HORDS CREEK LAKE, TX Location. On Hords Creek, a tributary of Pecan Bayou, about 13.5 miles west of Coleman, Texas and about 27.8 miles upstream from mouth of Hords Creek. (See Geological Survey sheets, Grosvenor and Zephyr, scale 1:62,500.) Existing project. For description of completed improvement and authorizing acts see Annual Report for 1962. Estimated cost of project is $4,337,000 including $105,000 contributed by local interests. Construction of project was started January 1947 and completed for beneficial use in April 1948. Local cooperation. Fully complied with. Operations during fiscal year. Routine operation maintenance continued. Recreation facilities under Code 710 remain. Benefits accrued to Hords Creek project: Accumulated flood damages prevented through FY 1985 were $937,200. 16. JOE POOL LAKE, TX (formerly Lakeview Lake) Location. Dam site is located at River Mile 11.2 on Mountain Creek, a right bank tributary of the West Fork of the Trinity River, and is adjacent to the city limits of Grand Prairie, Dallas County, Texas, which is one of the rapid growing cities in the Dallas-Fort Worth Metropolitan area. Existing project. The project provides for construction of an earthfill dam with a maximum height of 108.5 feet above the streambed and a total length of 24,200 feet, including 50-foot uncontrolled ogee type spillway, which will control 232 square miles of drainage area. The reservoir will have a total controlled storage of 304,000 acre-feet and a water surface area of 10,940 acres at the top of the flood control pool and 7,470 acres at the top of the conservation pool. The total storage includes 123,100 acre-feet for flood control, 142,900 acre-feet for conservation and 38,000 acrefeet for sediment reserve. Estimated cost of the project is $199,200,000 (Oct. 1, 1985, base price) including $10,200,000 non-Federal first cost. Project is a unit in the general comprehensive plan for development and control of the water resources of the Trinity River basin. Local cooperation. The Water Supply Act of 1958 as amended, and the Federal Water Project Recreation Act of 1965 apply. Contracts for water supply storage and recreation with the Trinity River Authority were approved by the Acting Secretary of the Army, June 15, 1977. The recreation contract with Trinity Valley Authority was modified March 28, 1979, to allow the Corps to participate with the State of Texas and approved by the Assistant Secretary of the Army March 21, 1980. Recreation development contract with the State of Texas was approved by the Assistant Secretary of the Army March 21, 1980. Reimbursement is currently estimated at $46,636,000 for supply and $9,512,000 for recreation (excluding future recreation facilities) for a total of $56,148,000 exclusive of interest. Operations during fiscal year. The project has been under construction since FY 1975 and through FY 1985 is approximately 91 percent complete overall. Contracts awarded during FY 1985 include the following: Reloc City Streets and County Rds., Pt IV, awarded May 17, 1985; and Reloc. of Electrical Distribution Lines, awarded March 25, 1985. Land Acquisition and Engineering and Design continue. Public Law 97-400, H.R. 7377, 97th Congress, effective December 31, 1982, changed the name of Lakeview Lake to Joe Pool Lake. Engineering and design continues. 17. LAVON LAKE, TX Location. Dam is in Collin County, Texas, on East Fork of Trinity River 55.9 miles above its confluence with Trinity River and about 22 miles northeast of Dallas, Texas. Existing project. For description of completed improvement and authorizing acts see Annual Report for 1962. Estimated cost of project is $15,470,000. For information concerning Lavon Lake Modification and East Fork Channel Improvement project, see individual project. Construction of project was started January 1948 and ready for beneficial use in September 1953. Project is complete. See following section for Lavon Lake Modification and East Fork Channel Improvement authorized by Flood Control Act of 1962. Local cooperation. Section 2, Flood Control Act of 1938, applies. A contract with North Texas Municipal Water District for water supply storage, including cost of intake structure, was approved by Secretary of the Army July 8, 1954, at an estimated cost of $1,405,753. Contract was revised in 1973 and final revised contract amount is $1,445,261.67. To date the district has paid $647,778. Under the contract North Texas Municipal Water District must pay annually 13.6 percent of actual annual cost of operation and maintenance. To date the district has paid $539,505. Operations during fiscal year. Routine operation and maintenance continued. Benefits accrued to Lavon project: Accumulated flood damages prevented through FY 1985 were $84,008,300. 18. LAVON LAKE MODIFICATION AND EAST FORK CHANNEL IMPROVEMENT, TX Location. Existing dam is in Collin County, Texas, on East Fork of Trinity River, 55.9 miles above its confluence 16-7 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 with Trinity River and about 22 miles northeast of Dallas, Texas. Channel improvement of East Fork extends from its mouth to River Mile 31.8. Existing project. Reservoir modification provides for raising top of existing dam from elevation 502.0 to 514.0 and lengthening existing dam from above 9,499 feet to about 19,493 feet; modification of existing concrete spillway structures; enlargement of existing reservoir area, involving acquisition of additional rights-of-way; relocation and alteration of highways, county roads, railroads and utilities; and provision of recreational facilities. East Fork Channel and floodway improvements consist of 25 miles of channel enlargement and straightening of the East Fork between River Mile 0.0 and 31.8; replacement of inadequate leveesluice structures; rehabilitation of existing levees; acquisition and clearing of land areas as required for rightsof- way along improved channel and existing levees; alteration of existing railroad, highway and county road bridges crossing the improved channel as well as relocation of existing utility lines; and strengthening and raising about 202,400 linear feet of levees of seven existing levee districts. Reservoir will provide a total storage capacity of 748,200 acre-feet (275,600 are for flood control, 380,000 for water supply storage, and 92,600 for sedimentation reserve.) Estimated Federal cost of the modification and improvement is $69,750,000 and estimated cost to local interests is $220,000 for lands and damages and relocations, a total of $69,970,000. Construction was initialed in May 1970 and ready for beneficial use in December 1975. Local cooperation. Local interests must reimburse the Federal Government for costs allocated to increase water supply storage under the terms of the Water Supply Act of 1958. The North Texas Municipal Water District has contracted for 43 percent of the water supply (approved September 22, 1967, by the Secretary of the Army) and to date $1,430,257 has been paid. North Texas Municipal Water Supply District has submitted assurance to contract for the 57 percent for future water supply. Reimbursement is currently estimated at $37,572,113. Levee Districts 4 and 5, which comprise the lower 10 miles of the East Fork Channel, entered into agreements as required by Section 221 of the Flood Control Act of 1970 on January 28, 1972 and have furnished all necessary construction easements. Levee Districts 6, 8, 10, 13, and 15, which comprise the upper 15 miles of the East Fork Channel, have declined to provide the necessary assurances. On December 8, 1972, this portion of the project was reclassified from "active" to "inactive" category. Operations during fiscal year. A construction contract for Levee Improvement, Increment I, East Fork was awarded May 1, 1981, and continues. Improvement of the lower ten miles of the East Fork Channel and Levees and total project are 99 percent complete. 19. LEWISVILLE DAM, TX Location. In Denton County, Texas, on Elm Fork of Trinity River 30 river miles above its confluence with Trinity River and about 22 miles northwest of City of Dallas, Texas at a site downstream from old Garza Dam. Existing project. For description of completed improvement and authorizing acts see Annual Report for 1962. Estimated cost of project is $25,902,000 (Oct. 1, 1983, base price), including $3,677,000 contributed by local interests. Construction of project was started November 1948 and ready for beneficial use in November 1954. Local cooperation. A contract with City of Dallas for 415,000 acre-feet of water supply storage land rights and interests to Garza Dam and Reservoir was approved by the Secretary of the Army on July 16, 1953. Local contributions have been made in full. A contract with city of Denton, Texas, for remaining 21,000 acre-feet of water supply storage was approved by the Secretary of the Army on May 20, 1954, with an estimated cost of $250,064. To date Denton has paid $250,064. Under above contracts, cities of Dallas and Denton must pay annually 21.9 and 1 percent, respectively, of actual annual cost of operation and maintenance. To date Dallas has paid $2,599,463 and Denton $122,555. Operations during fiscal year. Routine operation and maintenance continued. Recreation facilities under Code 710 remain. Benefits accrued to system comprised of Lewisville Lake, Grapevine Lake, and Dallas Floodway: Accumulated flood damages prevented through FY 1985 were $804,444,800. 20. MILLICAN LAKE, TX Location: Dam is on the Navasota River at mile 24.1, approximately 7 miles north of Navasota, Texas in Grimes and Brazos Counties, Texas. This project would be the first of a two-stage development consisting of Millican and Navasota Dams, both of which would be units in the overall plan of, improvement for the Brazos River Basin. Existing Project. The project provides for construction of a concrete and earthfill dam 25,300 feet long including a 472-foot-gate-controlled spillway, rising 83 feet above the streambed. Without Navasota Lake in operation, the top of flood control pool (elevation 234.0) would provide 1,557,400 acre-feet of storage space and cover a surface area of 66,000 acres. There would be 784,800 acre-feet of flood control; 680,200 acre-feet for water supply (surface area 42,400 acres), and 92,400 acre-feet for sediment reserve. With Navasota Lake in operation, the top of flood control elevation and total storage would remain the same. The flood control pool would be 359,600 acre-feet, water supply storage would be 1,125,800 acre-feet (surface area 55,500 acres) and sediment reserve would be 72,000 acre-feet. Estimated Federal cost of the project is $362,000,000. (Oct. 1, 1985 base price). Local cooperation. The Water Supply Act of 1958 as amended and the Federal Water Project Recreation Act of 1965. By letter dated December 9, 1974, the Brazos River Authority stated that they would be the state agency to cost share for both water supply and recreation. Operations during the fiscal year. Preconstruction planning continued, and is scheduled to complete in October 1989. 21. NAVARRO MILLS LAKE, TX Location. Dam is in Navarro County, Texas, at River Mile 63.9 on Richland Creek, a tributary of Trinity River, about 16 miles southwest of Corsicana, Texas. 16-8 FORT WORTH, TEXAS DISTRICT Existing project. For description of completed improvement and authorization acts see Annual Report for 1965. Estimated cost of project is $13,154,000 (Oct. 1, 1983, base price), including $300,000 contributed by local interests. Construction started December 1959 and project completed for beneficial use March 1963. Local cooperation. The Water Supply Act of 1958, as amended applies. A formal contract with the Trinity River Authority was approved March 3, 1966, by the Secretary of the Army at an estimated cost of $2,260,800. To date the Authority has paid $631,649 for water supply and 663,623 for operation and maintenance. Operations during fiscal year. Routine operation and maintenance continued. Recreation facilities under Code 710 remain. Benefits accrued to Navarro Mills project: Accumulated flood damages prevented through FY 1985 were $25,977,400. 22. O. C. FISHER DAM AND LAKE, TX Location. Dam is on North Concho River, a tributary of Concho River, about 6.6 miles above mouth of North Concho River near city of San Angelo, Texas. (See Geological Survey base map, Texas, scale 1:500,000, and sheet Wall, scale 1:62,500.) Existing project. For description of completed improvement and authorizing acts see Annual Report for 1962. Name was changed from San Angelo Dam and Reservoir January 3, 1975 by Public Law 93-634. Estimated cost of project is $17,111,000. Construction of project was started May 1947 and ready for beneficial use February 1952. Local cooperation. Section 2, Flood Control Act of 1938, applies. A water-supply contract with Upper Colorado River Authority for water-supply storage in reservoir was approved by Secretary of the Army on October 11, 1948. The Authority has contributed $860, 444 toward cost of project and $64,324 toward operation and maintenance for a 50-year period. The Authority must pay additional consideration of $1 a year for useful life of project, beginning January 1, 1965. Operations during fiscal year. Regular funds: Routine operation and maintenance continued. Recreation facilities under Code 710 remain. Benefits accrued to O. C. Fisher Dam and Lake project: Accumulated flood damages prevented through FY 1985 were $2,375,600. 23. PROCTOR LAKE, TX Location. Dam is at River Mile 238.9 on Leon River, a tributary of Brazos River, about 8 miles northeast of Comanche in Comanche County, Texas. Existing project. For description of completed improvement and authorization act see Annual Report of 1969. Estimated cost of project is $16,249,000. Construction of project was started July 1960 and completed for beneficial use 1963. Local cooperation. The Water Supply Act of 1958 applies. A formal contract with the Brazos River Authority, a State agency, was approved by Secretary of the Army, July 1, 1960, and was modified and was approved May 9, 1966, at an estimated cost of $1,707,900. To date the Authority has paid $296,219 for water supply and $257,363 for operation and maintenance. Operations during fiscal year. Routine operation and maintenance were continued. Recreation facilities under Code 710 remain. Benefits accrued to Proctor project: Accumulated flood damages prevented through FY 1985 were $5,166,700. 24. RAY ROBERTS LAKE, TX (formerly Aubrey Lake) Location. Damsite is located at River Mile 60.0 on the Elm Fork of the Trinity River, Denton County, between Sanger and Aubrey, Texas and 30 miles upstream from Lewisville Dam. Existing project. The plan of improvement provides for construction of an earthfilled dam with a maximum height of 141 feet above the streambed, a length of 15,250 feet including an uncontrolled broadcrested spillway 100 feet long, controlling 682 square miles of drainage area. The lake will have a total controlled storage of 1,064,600 acrefeet with a water surface area of 36,900 acres. The total storage includes 260,800 acre-feet for flood control 749,200 acre-feet for water supply, and 54,600 acre-feet for sediment reserve. Estimated Federal cost of the project is $279,000,000 (Oct. 1, 1985, base price). Public Law 96-384, 96th Congress, H.R. 8024, effective January 4, 1981, changed the name of Aubrey Lake to Ray Roberts Lake. Local cooperation. The Water Supply Act of 1958 as amended and the Federal Water Project Recreation Act of 1965 and Section 221, Flood Control Act of 1970 apply. Contracts with the cities of Dallas and Denton, Texas, for water supply storage and recreation were approved by the Secretary of the Army September 16, 1980. Operations during fiscal year. The project is about 53 percent complete overall. Acquisition of real estate continues. FY1985 funds were used to award the following contracts: County Rds, Pt I, awarded April 1, 1985; County Rds., Pt II, awarded June 7, 1985; County Rd. 29 and Mopac Railroad, awarded May 31, 1985; and Lewisville Emb- Riprap, awarded June 5, 1985. At the request of the city of Denton and the approval of the Secretary of the Army, the penstock was added to the embankment as a minimum facility for future hydropower. Engineering and design continue. 25. SAN ANTONIO CHANNEL IMPROVEMENT, TX Location. Floodway is in city of San Antonio, Bexar County, Texas, on San Antonio River and San Pedro, Apache, Alazan, Martinez Creeks, and Espada Acequia Aqueduct located in vicinity of Six Mile Creek. Existing project. Provides for clearing, widening deepening, and straightening about 34.9 miles of river and creek channels to carry standard project flood discharges, construction of channel walls, and paving, conduit, and construction and alteration of railroad bridges. Estimated Federal cost of these modifications is $85,400,000 (Oct. 1, 1985, base price), and estimated cost to local interests is $68,200,000 which includes $2,200,000 cash contributions 16-9 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 and $66,000,000 for lands, damages, and construction, a total of $153,600,000. Existing project was authorized by 1954 Flood Control Act. Latest published map is in project document. The Water Resources Act of 1976 added authorization to the existing project for construction of flood control measures needed to preserve and protect the Espada Acequia Aqueduct located in the vicinity of Six Mile Creek. Construction was started in October 1957 and the project is about 80 percent complete. Local cooperation. Local interests must furnish lands and rights-of-way for construction, including purchase and removal of buildings, relocation or reconstruction of bridges (exclusive of railway bridges), channel dams where applicable, and utility lines; hold the United States free from damages; maintain and operate all works after completion; and provide a cash contribution for enhancement benefits of 2.65 percent of actual Federal construction cost. San Antonio River Authority furnished assurances that it will comply with all requirements of local cooperation. These assurances were accepted by the District Engineer on April 15, 1957. To date $999,525 has been contributed by San Antonio River Authority. In addition, $30,000 has bee contributed and accepted, under the authority of Civil Functions Appropriations Act of 1958, for vehicular crossings over the San Antonio channel. Operations during fiscal year. Engineering and design studies continued. Benefits accrued to San Antonio project: Accumulated flood damages prevented through FY 1985 were $44,055,500. 26. SAN GABRIEL RIVER, TX Location. System of three reservoirs in Williamson County in the central portion of Brazos River Basin. Granger Dam at River Mile 31.9 on San Gabriel River, about 7 miles east of Granger, Texas; North San Gabriel Dam at River Mile 4.3 on North Fork of San Gabriel River, about 3.5 miles northwest of Georgetown, Texas; and South Fork Dam at River Mile 4.7 on South Fork of San Gabriel River, about 3 miles southwest of Georgetown, Texas. Existing project. Granger Lake was authorized by 1954 Flood Control Act, and North (North San Gabriel Dam and Lake Georgetown) and South Fork Lakes were authorized by 1962 Flood Control Act. Estimated total Federal cost of project $160,000,000 (Oct. 1, 1985, base price). Plan of improvement provides for the following: Granger: An earthfilled dam 16,320 feet long, including spillway with maximum height of 115 feet above streambed, which controls 709 square miles of drainage area. Reservoir provides a total storage capacity of 244,200 acre-feet, of which 162,200 acre-feet are for flood control, 37,900 acrefeet for water supply storage, and 44,100 acre-feet for sediment reserve. Estimated cost of project is $62,062,000. North San Gabriel Dam: A rockfill dam 6,700 feet long, including spillway with maximum height of 164 feet above streambed, which controls 246 square miles of drainage area. Reservoir provides a total storage capacity of 130,800 acre-feet of which 87,600 acre-feet are for flood control, 29,200 acre-feet for water supply storage, and 14,000 acrefeet for sediment reserve. Estimated cost of project is $38,765,000. South Fork: A rockfill dam 5,620 feet long, including spillway with maximum height of 152 feet above streambed, which controls 123 square miles of drainage area. Reservoir provides a total storage capacity of 82,600 acre-feet (45,700 for flood control, 28,900 for water supply storage, and 8,000 for sediment reserve). Estimated cost of project is $59,173,000. Public Law 96-575, 96th Congress, H.R. 4941 effective January 4, 1981, changed the name of North Fork Lake to North San Gabriel Dam and Lake Georgetown. Local cooperation. Construction is subject to condition that local interests reimburse the Federal Government for costs allocated to water supply at Granger, Lake Georgetown, and South Fork Lakes. Reimbursement currently estimated at $13,308,000 for Granger, $6,404,000 for Lake Georgetown, and $17,399,000 for South Fork, for a total of $37,111,000 exclusive of interest. Brazos River Authority, a State agency, is the local interests' sponsor of project, and by letter dated April 18, 1966, indicated its acceptance of the proposed plan of development and its willingness to pay for the costs allocated to water supply in each reservoir in the ultimate plan. Such water supply assurances for Granger and Lake Georgetown Lakes were approved May 24, 1968 as satisfactory in accordance with requirements of the Water Supply Act of 1958, as amended. Contract negotiations for South Fork Lake will be deferred until the need for water supply develops and the reservoir is scheduled for construction. Operations during fiscal year. Through 1983 all work has been completed. Deliberate impoundment of water commenced at Granger and Lake Georgetown Lakes on January 21, 1980 and March 3, 1980, respectively. In FY 1982, studies on South Fork Lake were resumed in preparation of General Design Memorandum to provide reaffirmation prior to construction. This reaffirmation is currently scheduled for submission in July 1986 and to be fully coordinated by February 1987. Benefits accrued to project consisting of Granger and Lake Georgetown: Accumulated flood damages prevented through FY 1985 were $12,344,400. 27. SOMERVILLE LAKE, TX Location. Dam is on Yegua Creek 20 miles upstream from its confluence with Brazos River and about 2 miles south of Somerville, Texas. Existing project. For description of completed improvements and authorization act see Annual Report of 1969. Estimated cost of project is $30,227,000. Construction started in June 1962 and project was ready for beneficial use in January 1967. Local cooperation. The Water Supply Act of 1958, as amended, applies. A contract with the Brazos River Authority, a State agency, for water supply storage approved May 10, 1962, by the Secretary of the Army, to date, $824,587 has been paid. Also under the contract, the authority must pay annually 28.655 percent of the actual annual cost of operation and maintenance. Operations during fiscal year. Routine operation and maintenance continued. Recreation facilities under Code 710 remain. Benefits accrued to Somerville project: Accumulated flood damages prevented through FY 1985 were $30,436,700. 16-10 FORT WORTH, TEXAS DISTRICT 28. STILLHOUSE HOLLOW DAM, TX Location. Dam is on Lampasas River 16 miles upstream from its confluence with Little River, a tributary of the Brazos River, and about 5 miles southwest of Belton, Texas. Existing project. For description of completed improvements and authorization act see Annual Report of 1969. Estimated cost of project is $23,670,000. Construction was initiated in July 1962 and the project was ready for beneficial use in February 1968. Local cooperation. The Water Supply Act of 1958 applies. A contract with the Brazos River Authority, a State agency, for water supply storage was approved April 13, 1962, by the Secretary of the Army, at an estimated cost of $6,912,430. To date the Authority has paid $1,016,395. Also under the contract the Authority must pay annually 27.748 percent of the actual cost of operation and maintenance. To date the Authority has paid $504,708. Operations during fiscal year. Routine operation and maintenance continued. Recreation facilities under Code 710 regular were constructed. Benefits accrued to Stillhouse Hollow project: Accumulated estimate of flood damages prevented through FY 1985 is $20,596,800. 29. WACO LAKE, TX Location. Dam is on Bosque River, 4.6 river miles above its confluence with Brazos River, at City of Waco, McLennan County, Texas. Existing project. For description of completed improvements and authorization act see Annual Report of 1969. Estimated cost of project is $50,853,000 including $250,000 contributed by local interests and $2,500,000 other non-Federal cost. Construction was started in July 1958, and project was ready for beneficial use in February 1965. Local cooperation. Section G of the Flood Control Act of December 1944 applies. A contract with the Brazos River Authority, a State agency, for water supply storage and the contract with the City of Waco transferring the existing Lake Waco to the Government for their water storage, was approved by the Secretary of the Army on April 15, 1958. To date the Authority for their portion of the water supply storage has paid $1,437,901. Also under the contract the Authority and the City must pay 14.706 and 2.087 percent respectively of the actual cost of operation and maintenance. To date the Authority has paid $651,505 and the City has paid $104,992. A contract with the Brazos River Authority, for additional storage for municipal and industrial water supply, was approved by the Acting Assistant of the Army, September 28, 1984. Operations during fiscal year. Regular funds: Routine operations and maintenance continued. Recreation facilities under Code 710 remain. Benefits accrued to Waco project: Accumulated flood damages prevented through FY 1985 were $58,731,900. 30. WRIGHT PATMAN DAM AND LAKE, TX Location. On Sulphur River in Cass and Bowie Counties, Texas. Dam is 45 miles above mouth of Sulphur River, and about 8 miles southwest of Texarkana, Texas. Existing project. An earth-fill dam 18,500 feet long and 100 feet high, including a spillway 200 feet wide and outlet works with a capacity of 27,600 cubic feet per second. Reservoir controls runoff from 3,400 square miles of drainage area, and has a storage capacity of 2,654,300 acrefeet, of which 145,300 acre-feet are for conservation and remainder for flood control. Estimated cost for work (October 1978) is $51,945,000 which includes $5,449,100 Code 711, $399,939 accelerated public works funds, and $13,138,004 to be reimbursed by local interests, over a period not to exceed 50 years, for water supply storage, and including $2,092,040 for pro rata share of original reservoir cost. Construction was initiated in August 1948 and completed in March 1962, except real estate activities, construction under Code 711, and conversion of 120,000 acre-feet to water supply storage after completion of Cooper Reservoir. This project transferred to the Fort Worth District as of the end of FY 1979. Local cooperation. A contract with the city of Texarkana, Texas, for Reserving Water Supply Storage Space was approved by the Secretary of the Army December 17, 1968. To date the City has paid $323,577. Operations during fiscal year. Routine operation and maintenance continued. Recreation facilities under Code 710 remain. Benefits accrued to Wright Patman project: Accumulated flood damages prevented through FY 1985 were $13,697,000. 31. INSPECTION OF COMPLETED FLOOD CONTROL PROJECTS Inspection of completed local flood protection projects is made periodically in compliance with section 208.10, of title 33, Code of Federal Regulations, which contains regulations for operation and maintenance of local flood-protection works approved by Secretary of the Army in accordance with authority in section 3. Flood Control Act of June 22, 1936. See Table 16-D for inspections made this fiscal year. Inspection costs for FY from regular funds for maintenance were $51,883. Total costs to September 30, 1985 were $565,651. 32. SCHEDULING FLOOD CONTROL RESERVOIR OPERATIONS In accordance with Flood Control Act of 1944 expenditures were made for scheduling flood control reservoir operations and preparation of reservoir regulation manual for Marshall Ford Dam, on the Colorado River, near City of Austin, Texas, and for preparation of reservoir regulation manual for Twin Buttes Dam, on Middle and South Concho Rivers near City of San Angelo, Texas. Marshall Ford Dam was authorized by 1937 River and Harbor Act. Project was constructed jointly by Bureau of Reclamation and Lower Colorado River Authority and was completed during FY 1942. Twin Buttes Reservoir was authorized for construction by Department of Interior by Public Law 152, 85th Congress. Construction was initiated in June 1960; closure of dam started in June 1962; deliberate impoundment was started January 23, 1963. Accumulated damages prevented by Marshall Ford Reservoir through FY 1985 were $183,482,600 and by Twin Buttes through FY 1985 were $417,500. Twin Buttes 16-11 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Reservoir consists of two separate pools, one on South Concho River and the other on Middle Concho River and Spring Creek. Equalizing channel between these two pools is at elevation 1925.0. Costs for fiscal year from regular funds for operation of both reservoirs were $46,475. 33. OTHER AUTHORIZED FLOOD CONTROL PROJECTS (See Table 16-C.) 34. FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION (See Table 16-E) Flood control activities pursuant to section 205, Public Law 858, 80th Congress, as amended (preauthorization); emergency streambank protection under section 14, Public Law 526, 79th Congress, as amended. Emergency flood control, hurricane-flood, and shore protection activities (Public Law 99, 84th Congress, and antecedent legislation). Fiscal year costs were $230,313 for disaster preparedness; no levee repair. Multi-Purpose Projects Including Power 35. BELTON LAKE MODIFICATION, TX Location. For location of completed dam see Belton Lake, Texas in this chapter. Existing project. The modification of Belton Lake to provide installation of hydroelectric power generating facilities was authorized by the Flood Control Act of 1954 (H.Doc. 535, 81st Cong., 2nd Sess.). The plan of improvement provides for reallocation of the gross storage capacity in Belton Lake to provide a power pool and the installation of hydroelectric power generating facilities. Operations during fiscal year. The modification is classified as deferred until the Chief of Engineers determines it is advisable. 36. DAM A LAKE, TX Location. The dam would be located approximately 18 miles west of Jasper and about 4 miles west of Horger, Texas. Existing project. The project is designed to be used as a run-of-river plant for the generation of power and to regulate power surges from the proposed Rockland Lake. The last estimate of project cost was $3,220,000 in 1954. For last full report see Annual Report of 1952. Operations during fiscal year. The project is classified as deferred. 37. ROCKLAND LAKE, TX Location. The dam would be located approximately 3 miles west of Rockland, Texas, on the Neches River. Existing project. The project would control floods, generate hydroelectric power, and provide water supply for various uses. The last estimate of project cost was $767,000,000 (Oct. 1, 1985 base price). For the last full report see Annual Report of 1952. Operations during fiscal year. The project was reclassified to active status December 2, 1982. 38. SAM RAYBURN DAM AND RESERVOIR, TX Location. Dam is on Angelina River 25.2 miles upstream from its confluence with Neches River and about 10 miles northwest of Jasper, Texas. Existing project. For description of completed improvements and authorization act see Annual Report 1969. Estimated cost of project is $68,863,000 including $3,000,000 contributed by local interests. Construction was started August 1956 and project was ready for beneficial use in March 1965. Local cooperation. A contract with the Lower Neches Valley Authority, a State agency, to contribute $3,000,000 toward the first cost and an additional $200,000 annually for 50 years after completion of the project was approved by the Secretary of the Army on January 22, 1957. Contribution of $3,000,000 was made in full and annual payments to date of $3,800,000 have been made by the Authority. A contract with the City of Lufkin for water supply storage was approved May 27, 1969 by the Secretary of the Army at an estiamted cost of $525,600. To date the City has paid $105,511. Also under the contract the City of Luikin must pay annually 0.692 percent of the annual cost of operation and maintenance. To date the City has paid $109,061. Operations during fiscal year. Continued routine operation and maintenance. Recreation facilities under Code 710 continued. Benefits accrued to Sam Rayburn project: Accumulated flood damages prevented through FY 1985 were $76,262,900. 39. TOWN BLUFF DAM - B. A. STEINHAGEN LAKE, TX Location. Dam is on Neches River about 12.4 miles below mouth of Angelina River, one-half mile north of Town Bluff, Texas, and 93 river miles north of Beaumont, Texas. Existing project. For description of completed improvement and authorizing acts see Annual Report for 1962. Estimated cost of project is $9,888,000, including $2 million contribution by local interests. Construction started March 1947 and project was ready for beneficial use in April 1951. Local cooperation. Completed as required. Operations during fiscal year. Regular funds: Routine operation and maintenance continued. Recreation facilities under Code 710 remain. 40. TOWN BLUFF HYDROPOWER, TX Location. For location of completed dam see Town Bluff Dam - B.A. Steinhagen Lake, TX in this chapter. Existing project. Installation of hydroelectric power generating facilities at Town Bluff Dam was authorized by the River and Harbor Act of 1945 (Public Law 79-14), March 2, 1945, but deferred in the original construction. Town Bluff Dam was completed and placed in operation in 1951. A Feasibility Report was approved September 9, 1983 and a Design Analysis Report completed in April 1982 indicated that installing hydropower at this project is now eco- 16-12 FORT WORTH, TEXAS DISTRICT nomically feasible. The hydropower facilities will include a 6,000 kilowatt power plant (two units at 3,000 kilowatts each), intake and outlet facilities, and necessary switchgear equipment to be located in the main embankment at the old diversion channel and will be operated remotely from the Sam Rayburn project. The installation and operation of hydropower facilities will not result in the altering of the existing operation at Town Bluff. The project will produce an estimated 35,900 megawatt hours of energy per year. There is no Federal cost on this project. It is completely funded by Non-Federal funds. The estimated non-Federal cost is $16,700,000. Local cooperation. A contract with the Sam Rayburn Municipal Power Authority was approved by Secretary of the Army, June 28, 1985, relative to financing, escrow agreement, and power sales agreement. Operation during fiscal year. Plans and specifications are scheduled for completion in FY 1986. Planning and Engineering - studies continue. Project completion date is scheduled for 1988. 41. WHITNEY LAKE, TX Location. Dam is on Brazos River, about 442 miles above mouth of river, 5.5 miles southwest of Whitney, Texas, and about 38 miles upstream from City of Waco, Texas. (See Geological Survey sheets: Waco, Cleburne, and Granbury scale 1:125,000, and Whitney, Blum, and Morgan scale 1:62,500.) Existing project. For description of completed improvement and authorizing acts see Annual Report for 1962. Estimated cost of project is $46,306,000. Construction of project was started June 1946 and ready for flood control use in December 1951. First power was placed on-the-line in June 1953. Raise power pool is complete. Local cooperation. Section 2, Flood Control Act of 1938, applies. A contract with the Brazos River Authority; a State Agency, for Water Supply Storage was approved by the Secretary of the Army November 3, 1982. To date the authority has paid $110,901. Operations during fiscal year. Continued routine operation and maintenance. Recreation facilities under Code 710 remain. Benefits accrued to Whitney project: Accumulated flood damages prevented through FY 1985 were $131,516,200. General Investigations 42. SURVEYS Fiscal year costs were $898,647 for flood damage prevention studies, $146,612 for coordination with other agencies, and $34,897 for preauthorization studies Phase I for a total of $1,201,896. 43. COLLECTION AND STUDY OF BASIC DATA Work was continued under the Flood Plain Management Services on the compilation of information on floods and potential flood damages, including identification of those areas subject to inundation. Fiscal year expenditures for these activities totaled $276,913. Fiscal year costs were $4,187 for hydrologic studies. The national program of inspection of dams, authorized by Public law 92-367, was continued in FY 1984. 16-13 TABLE 16-A REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 COST AND FINANCIAL STATEMENT See Section Total Cost To in Text Project Funding FY 82 FY 83 FY 84 FY 85 Sept. 30, 198517 1. Trinity River Project, TX Includes Channel to Liberty, Tennessee Colony Lake, and Dallas Floodway Extension 2. Aquilla Lake, TX 3. Bardwell Lake, TX 4. Belton Lake, TX 5. Benbrook Lake, TX 6. Big Sandy Lake, TX 7. Boggy Creek, TX 8. Canyon Lake, TX (Federal Funds) 9. Cooper Lake and Channels, TX 10. Elm Fork Floodway, TX 11. Ferrells Bridge Dam Lake O'The Pines, TX 12. Grand Prairie, TX Landfill (Contributed Funds) 13. Grand Prairie, TX Myers Road New Work: Approp. Cost New Work: Approp. Cost Maint. Approp. Cost New Work: Approp. Cost Maint. Approp. Cost New Work: Approp. Cost Maint. Approp. Cost New Work: Approp. Cost Maint. Approp. Cost New Work: Approp. Cost New Work: Approp. Cost New Work: Approp. Cost Maint. Approp. Cost New Work: Approp. Cost New Work: Approp. Cost New Work: Approp. Cost Maint. Approp. Cost New Work: Approp. Cost New Work: Approp. Cost New Work: Approp. Cost 500,000 248,000 212,999 (-)20,000 22,380,865 678,572 94,078 216,206 53,412 22,138,748 13,300,000 3,049,000 12,441,014 5,261,404 - 136,000 - 75,109 0 325,069 249,000 287,859 0 58,974 329,000 327,291 45,506,300 45,483,784 714,000 690,259 - 10,934,505 - 10,934,505 633,800 608,922 60,000 9,765 1,064,700 673,632 20,904 55,035 561,200 972,137 57,000 63,661 790,000 9,084,78718 789,322 9,037,09618 0 16,969,549 3,162 16,963,1081 1,161,400 1,169,000 1,236,000 1,278,600 13,625,84318 865,249 1,039,194 1,533,021 1,308,974 13,502,20218 92,000 15,649 1,020,360 904,363 65,000 77,041 - (-)5,160 13,647 2,457 - 13,144,126 - 13,069,9912 1,807,500 2,357,000 1,355,200 15,116,41418 1,489,685 2,098,363 1,970,936 15,029,19418 1,000 1,792 270,000 350,000 100,000 245,452 373,933 79,858 0 741,000 0 741,000 0 13,559 720,000 712,802 - - - - 19,088,5243 - - - - 19,088,524 747,520 1,162,600 635,000 1,113,000 10,384,80418 735,787 713,806 1,065,277 1,122,862 10,356,911 '8 700,000 1,000,00 205,401 95,448 175,000 792,000 24,620,000 319,458 1,901,072 24,359,640 - - - - 662,400 - - - - 662,400 - - - - 14,175,1974 - - - - 14,175,197 6 1,023,080 2,973,684 1,458,080 1,424,500 18,154,63118 1,758,669 1,995,078 2,502,913 1,425,959 18,083,14618 - 250,000 - 25,826 - 345,000 218,800 (-)24,666 218,800 (-)24,666 311,164 - 38,400 211,600 - 12,603 234,587 0 1,247 0 858 250,000 219,960 345,000 312,411 250,000 248,048 16-14 FORT WORTH, TEXAS DISTRICT COST AND FINANCIAL STATEMENT See Section Total Cost To in Text Project (Contributed Funds) 14. Grapevine Lake, TX 15. Hords Creek Lake, TX 16. Joe Pool Lake, TX 17. Lavon Lake, TX 18. Lavon Lake Modification & East Fork Channel Improvement, TX 19. Lewisville Dam, TX 20. Millican Lake, TX 21. Navarro Mills Lake, TX 22. O.C. Fisher Dam and Lake, TX 23. Proctor Lake, TX 24. Ray Roberts Lake, TX 38. Sam Rayburn Dam and Reservoir, TX Funding New Work: Approp. Cost New Work: Approp. Cost Maint. Approp. Cost New Work: Approp. Cost Maint. Approp. Cost New Work: Approp. Cost New Work: Approp. Cost Maint. Approp. Cost New Work: Approp. Cost New Work: Approp. Cost Maint. Approp. Cost New Work: Approp. Cost New Work: Approp. Cost Maint. Approp. Cost New Work: Approp. Cost Maint. Approp. Cost New Work: Approp. Cost Maint. Approp. Cost New Work: Approp. Cost New Work: Approp. Cost Maint. Approp. Cost FY 82 FY 83 FY 84 FY 85 Sept. 30, 198517 1,400,0 333,8 2,034,6 1,323,7 1,140,6 601,4 27,800,01 29,007,0 (-)23,01 19,7 2,507,3 1,618,8 76,01 709,2 1,155,600 1,105,071 477,280 454,801 17,324,000 14,890,100 64,096 38,949 1,294,240 1,162,432 2,413,000 1,729,262 - 40,000 00 5,500,000 95 5,165,510 00 2,024,550 28 2,730,034 - 20,000 - 18,076 50 1,370,000 09 1,792,382 00 17,200,000 40 14,842,702 00 (-)14,000 91 812 19 1,691,150 13 2,742,378 00 220,000 86 221,839 63 755,160 32 1,151,615 47 2,928,000 06 3,839,707 00 70,000 15 24,566 67 - 00 480 00 788,400 70 1,129,622 2,9 122,4 4,274,5 2,043,4 36,9 1,074,3 1,095,3 704,900 1,428,0 1,142,469 1,436,9 821,000 1,522,872 46,000,000 44,353,854 143 3,126,800 3,844,076 1,083,9 1,107,1 41,500,0 40,690,9 2,594,5 2,739,7 12 25,517,988 69 25,330,4599 00 22,692,86810 18 28 20,964,58910 18 - 3,627,000 93 3,603,992 - 9,846,759 - 9,846,75911 00 9,504,32618 63 9,886,58518 - 16,027,467 - 16,027,467 00 9,853,93118 '60 9,812,03018 - 14,469,585 - 14,455,476 '00 9,723,93218 98 9,649,67318 00 153,594,700 '56 149,307,225 - 60,670,957 -- 60,670,95612 00 29,308,51418 58 29,290,78718 - 40,000 8,040 8,040 4,200,000 21,067,790 5,371,807 20,839,0027 1,758,000 16,919,3681'8 1,743,680 16,826,90318 - 2,731,0898 - 2,729,165 951,000 8,229,18818 1,055,580 8,176,12418 15,550,000 157,838,000 14,593,636 151,873,946 - 12,864,796 - 12,864,796 1,552,800 16,711,01818 1,515,928 16,609,18618 - 69,796,862 105,939 69,796,678 1,409,000 (-)13,6 226,286 498,7 1,564,120 2,585,5 1,309,654 1,835,31 315,000 232,0' 375,026 234,7 5,904 7' 5,891 31 734,520 1,036,5 702,201 648,1 481,100 964,776 456,610 506,566 30,000 23,000 11,556 27,335 746,060 1,445,300 699,811 752,711 18,600,000 37,700,000 17,530,776 37,414,850 89,000 (-)1,300 39,529 48,471 1,779,720 2,468,500 3,298,701 2,250,027 16-15 TABLE 16-A TABLE 16-A REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 COST AND FINANCIAL STATEMENT See Section Total Cost To in Text Project Funding FY 82 FY 83 FY 84 FY 85 Sept. 30, 1985 '7 25. San Antonio Channel Improvement, TX (Federal Funds) (Contributed Funds) 26. San Gabriel River, TX Granger Lake Georgetown 27. Somerville Lake, TX 28. Stillhouse Hollow Dam, TX 39. Town Bluff Dam- B.A. Steinhagen Lake, TX 29. Waco Lake, TX 40. Whitney Lake, TX 30. Wright Patman Dam and Lake, TX New Work Approp. Cost New Work: Contrib. Cost New Work: Approp. Cost Maint. Approp. Cost Maint. Approp. Cost New Work: Approp. Cost Maint. Approp. Cost New Work: Approp. Cost Maint. Approp. Cost New Work: Approp. Cost Maint. Approp. Cost New Work: Approp. Cost Maint. Approp. Cost New Work: Approp. Cost Maint. Approp. Cost New Work: Approp. Cost Maint. Approp. Cost 4,750,000 3,300,000 (-)425,000 808,000 - 38,101,048 4,212,286 . 2,631,768 989,645 548,801 37,807,156 141,775 172,975 71,550 71,550 - 999,525 - 999,525 2,080,000 2,150,000 (-)20,000 200,000 101,582,100 2,158,550 2,216,366 72,540 338,897 101,577,723 627,860 621,113 676,200 629,153 1,278,600 661,833 1,050,436 772,455 709,900 1,357,865 475,000 783,364 151,000 (-)1,337 110,000 137,380 4,588 102,184 1,211,700 1,222,310 939,000 960,670 4,918,7F891 8 4,891. ,3'18 4,095,73218 4,067,115 ' 18 0 27,790,438 17,545 27,786,868 1,397,080 2,060,109 2,266,800 1,816,500 15,937,03618 1,097,053 1,226,952 3,254,200 1,838,950 15,793,69218 20,000 (-)1,960 12,319 5,721 - 20,522,084' 3 - 20,510,642 1,006,900 831,500 745,300 844,000 9,379,42618 789,532 794,558 1,037,452 843,990 9,305,40818 - - - - 6,602,737 - - - - 6,602,73714 610,540 1,059,315 1,011,100 762,000 10,556,86918 597,704 583,762 1,464,428 788,253 10,516,11118 - - - - 49,521,1211s - - - - 49,521,121 1,112,020 1,926,412 1,825,300 2,087,100 14,888,25818 1,052,675 1,244,780 2,428,338 2,093,703 14,748,56318 - (-)18,411 7,723 (-)588 - 42,952,938 - 42,952,93816 1,806,400 2,609,300 2,078,000 2,079,900 26,686,68018 1,687,658 1,973,166 2,807,910 2,035,349 26,530,73818 41,000 - - - 35,731,626 41,000 - - - 35,731,626 1,544,200 1,829,000 856,600 1,736,500 19,163,09018 1,406,388 1,479,911 1,379,767 1,744,716 19,106,81118 1 Excludes $47,309 receipts from reconveyance of land deposited to miscellaneous receipts. 2 Excludes $322,346 receipts from reconveyance of land deposited to miscellaneous receipts. 3 Excludes $1,422,848 expended for new work from contributed funds, including $22,848 "Contributed Funds Other" for installation and operation of gages for leakage study. Includes $1,378,486 for Code 711, $52,808 for Code 713, and $399,739 accelerated Public Works Act funds. Excludes $1,711,200 contributed funds. 5 Includes $1,376,322 for Code 711, $52,808 for Code 713, and $399,739 accelerated Public Works Act funds. Excludes $4,137 reimbursed in Fiscal Year 1973. 6 Claim Northeast Texas Municipal Water District $16,546. Three payments of $12,410 less real estate charges of $1,325, making a total of $2,811 reimbursed in Fiscal Year 1972, Fiscal Year 1973, and Fiscal Year 1974. 7Excludes $146,795 receipts from reconveyance of land deposited to miscellaneous receipts, and $2,040,026 for new work expended from contributed funds. 8 Excludes $105,079 expended from contributed funds. 9 Excludes receipts from reconveyance of land of $426,606 which were deposited to miscellaneous receipts, and $3,676,661 for new work expended from contributed funds. 10 Includes $130,000 under appropriation 96X5125. 16-16 FORT WORTH, TEXAS DISTRICT TABLE 16-A COST AND FINANCIAL STATEMENT 11 Excludes $300,000 expended from contributed funds. 12 Excludes $3 million expended from contributed funds. 13 Includes receipts from disposals and revocation of funds related thereto. 14 Excludes $2,000,000 contributed funds expended. 15 Excludes $2,750,000 expended for contributed funds. 16 Excludes $188,282 receipts from reconveyance of lands deposited to miscellaneous receipts. 17 Includes funds provided by the Jobs Act (PL 98-8, dated March 24, 1983) for projects listed in Table 16-F. 18 Beginning fiscal year 1985 data shown on Table A includes Special Recreation Use Fees. Data for previous fiscal years have been changed to conform to the new procedure. 16-17 TABLE 16-B REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 AUTHORIZING LEGISLATION See Date Section Authorizing in Text Act Project and Work Authorized Documents 2. AQUILLA LAKE, TX Construction of a dam on Aquilla Creek about 6.8 miles southwest of Hillsboro, Texas and about 24 miles north of Waco, Texas. BARDWELL LAKE, TX Construction of a dam on Waxahachie Creek about 5 miles south of Ennis, Texas. BELTON LAKE, TX Construction of a dam on the Leon River about 3 miles north of Belton, Texas. Modification (see Sec. 36 of Text) of the dam to provide for generation of hydroelectric power. BENBROOK LAKE, TX Construction of a dam on the Clear Fork of the Trinity River about 10 miles southwest of Fort Worth, Texas. BIG SANDY LAKE, TX Construction of a dam on Big Sandy Creek about six miles northwest of Big Sandy, Texas. S. Doc. 52, 90th Cong., 1st Sess. H. Doc. 424, 82nd Cong., 2nd Sess. H. Doc. 88, 81st Cong., 1st. Sess. H. Doc. 535, 81st Cong., 2nd Sess. H. Doc. 403, 77th Cong., 1st Sess. H. Doc. 429, 91st Cong., 2nd Sess. 4. Aug. 13, 1968 Mar. 31, 1960 Jul. 24, 1946 Sep. 3, 1954 Mar. 2, 1945 Dec. 31, 1970 Jun. 22, 1936 Mar. 2, 1945 Sep. 3, 1954 Aug. 3, 1955 Mar. 2, 1945 Oct. 27, 1965 Jul. 24, 1946 Jul. 24, 1946 Jul. 24, 1946 Mar. 2, 1945 H. Doc. 247, 76th Cong., 1st Sess. H. Doc. 488, 83rd Cong., 2nd Sess. S. Doc. 98, 76th Cong., 1st Sess. H. Doc. 276, 89th Cong., 1st Sess. H. Doc. 602, 79th Cong., 2nd Sess. Flood Control Act of 1946 Flood Control Act of 1946 H. Doc. 403, 77th Cong., 1st Sess. 16-18 BOGGY CREEK, TX Interim Survey Report. Flood Control Act of 1936 (PL 738) CANYON LAKE, TX Construction of a dam on the Guadalupe River about 12 miles northwest of New Braunfels, Texas. COOPER LAKE AND CHANNELS, TX Construction of earth-fill dam and reservoir area; channel clearing, realignment, and enlargement; enlargement and extension of existing levees; construction of appurtenant drainage works along main stem of Sulphur River above mile 126; channel clearing, realignment, and enlargement and levee enlargement and modification of appurtenant drainage works on Cuthand Creek below mile 24, on Sulphur River below mile 70, except in proposed Cooper Reservoir, miles 29 to 42, and on Middle Sulphur River below mile 8; channel clearing and realignment of Brushy Creek below mile 5; and levee enlargement on North Sulphur River between miles 1 and 5. DAM "A" LAKE, TX Construction of a dam on the Neches River about 18 miles west of Jasper, Texas. ELM FORK FLOODWAY, TX Realignment and enlargement of the Elm Fork of the Trinity River and Denton Creek, and a parallel levee system from the existing Dallas levee system upstream to near the Dallas and Denton county lines. FERRELLS BRIDGE DAM-LAKE O' THE PINES, TX Provides for construction of an earth-fill dam and reservoir area. GRAND PRAIRIE LANDFILL, TX Construction of a cutoff channel to eliminate an oxbow in the West Fork of the Trinity River. GRAND PRAIRIE, MEYERS RD, TX Slope Restoration with riprap side slopes along streambank of West Fork Trinity River, adjacent to Meyers Road. GRAPEVINE LAKE, TX Construction of a dam on Denton Creek, a tributary of the Trinity River, about 20 miles northwest of Dallas, Texas. 5. 8. 9. 36. 10. 11. 12. 13. 14. TABLE 16-B FORT WORTH, TEXAS DISTRICT AUTHORIZING LEGISLATION See Date Section Authorizing in Text Act Project and Work Authorized Documents 15. 16. 17. 18. Aug. 18, 1941 Oct. 27, 1965 Mar. 2, 1945 Oct. 23, 1962 Mar. 7, 1974 Mar. 2, 1945 Aug. 13, 1968 Sep. 3, 1954 Dec. 31, 1970 Aug. 18, 1941 Sep. 3, 1954 Oct. 27, 1965 Mar. 2, 1945 Mar. 2, 1945 Sep. 3, 1954 Sep. 3, 1954 Jan. 3, 1975 Sep. 3, 1954 HORDS CREEK LAKE, TX Construction of a dam on Hords Creek, a tributary of Pecan Bayou, near the city of Coleman, Texas. JOE POOL LAKE, TX Construction of a dam on Mountain Creek, adjacent to the city limits of Grand Prairie, Texas, about 3 miles above the existing Mountain Creek Dam. LAVON LAKE, TX Construction of a dam on the East Fork of the Trinity River about 22 miles northeast of Dallas, Texas. LAVON LAKE MODIFICATION AND EAST FORK CHANNEL IMPROVEMENT, TX Enlarge Levon Dam and enlargement and realignment of the lower 25 miles of the East Fork of the Trinity River, including rehabilitation of existing levees. Improvement of Collin County Road 115. LEWISVILLE DAM, TX Construction of a dam on the Elm Fork of the Trinity River near the city of Lewisville, Texas. MILLICAN LAKE, TX Construction of a dam on the Navasota River about seven miles north of Navasota, Texas. NAVARRO MILLS LAKE, TX Construction of a dam on Richland Creek, a tributary of the Trinity River, about 16 miles southwest of Corsicana, Texas. Alteration of FM Highway 3164 in Wolf Creek Park. O.C. FISHER DAM AND LAKE, TX Construction of a dam on the North Concho River just above San Angelo, Texas. PROCTOR LAKE, TX Construction of a dam on the Leon River about 8 miles northeast of Comanche, Texas. RAY ROBERTS LAKE, TX Construction of a dam on the Elm Fork of the Trinity River between Sanger and Aubrey, Texas, about 30 miles upstream from the existing Lewisville Dam. ROCKLAND LAKE, TX Construction of a dam on the Neches River approximately three miles west of Rockland, Texas. SAM RAYBURN DAM AND RESERVOIR, TX Construction of a dam on the Angelina River about 10 miles northwest of Jasper, Texas. SAN ANTONIO CHANNEL IMPROVEMENT, TX Channel improvement of the San Antonio River and tributaries in and near the city of San Antonio, Texas. SAN GABRIEL RIVER PROJECT, TX Construction of: (1) a dam (Granger Dam and Lake) on the San Gabriel River about 7 miles east of Granger, Texas, (2) a dam (North Fork Lake) on the north Fork of the San Gabriel River about 3.5 miles northwest of Georgetown, Texas and (3) a dam (South Fork Lake) on the South Fork of the San Gabriel River about 3 miles southwest of Georgetown, Texas. SOMERVILLE LAKE, TX Construction of a dam on Yegua Creek about 2 miles south of Somerville, Texas. H. Doc. 535, 81st 2nd Sess., and H. Doc. 591, 87th 2nd Sess. Cong., Cong., H. Doc. 535, 81st Cong., 2nd Sess. 16-19 H. Doc. 370, 76th Cong., 1st Sess. H. Doc. 276, 89th Cong., 1st Sess. H. Doc. 533, 78th Cong., 2nd Sess. H. Doc. 554, 87th Cong., 2nd Sess. H. Doc. 403, 77th Cong., 1st Sess. H. Doc. 341, 90th Cong., 2nd Sess. H. Doc. 498, 83rd Cong., 2nd Sess. H. Doc. 315, 76th Cong., 1st Sess. H. Doc. 535, 81st Cong., 2nd Sess. H. Doc. 276, 89th Cong., 1st Sess. S. Doc. 98, 76th Cong., 1st Sess. S. Doc. 98, 76th Cong., 1st Sess. H. Doc. 344, 83rd Cong., 2nd Sess. 19. 20. 21. 22. 23. 24. 37. 38. 25. 26. 27. TABLE 16-B REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 AUTHORIZING LEGISLATION See Date Section Authorizing in Text Act Project and Work Authorized Documents 28. 39. Sep. 3, 1954 Mar. 2, 1945 Oct. 27, 1965 Sep. 3, 1954 Mar. 2, 1945 Aug. 18, 1941 Jul. 24, 1946 STILLHOUSE HOLLOW DAM, TX Construction of a dam on the Lampasas River about 5 miles southwest of Belton, Texas. TOWN BLUFF DAM-B. A. STEINHAGEN LAKE, TX Construction of a dam on the Neches River near Jasper, Texas. TRINITY RIVER PROJECT, TX Construction of Tennessee Colony Dam located at river mile 339.2 on the Trinity River about 16 miles west of Palestine, Texas; a multiple purpose channel from the Houston, Texas ship channel to Fort Worth, Texas; a distance of approximately 363 miles, an extension of the existing Dallas, Texas, Floodway downstream aproximately 9.0 miles; a realignment and enlargement of the West Fork of the Trinity River from the mouth of the West Fork to the existing Fort Worth, Texas, Floodway, a distance of approximately 31 miles; and water conveyance facilities involving construction of about 98 miles of pipeline from Tennessee Colony Lake to the existing Benbrook Lake. WACO LAKE, TX Construction of a dam on the northwest edge of Waco, Texas, below the confluence of the North, South, and Middle Bosque Rivers. TOWN BLUFF HYDROPOWER, TX Construction of two units at 3,000 kilowatts each of hydroelectric power generating facilities connected with Town Bluff Dam - B.A. Steinhagen Lake, Tx. WHITNEY LAKE, TX Construction of a dam on the Brazos River, about 19 miles southwest of Hillsboro, Texas. Raise the power pool 13.0 feet. WRIGHT PATMAN DAM AND LAKE, TX Construction of an earth-fill dam and reservoir. 16-20 H. Doc..535, 81st Cong., 2nd Sess. S. Doc. 98, 76th Cong., 1st Sess. H. Doc. 276, 89th Cong., 1st Sess., and H. Doc. 364, 90th Cong., 2nd Sess. H. Doc. 535, 81st Cong., 2nd Sess. S. Doc. 98, 76th Cong., 1st Sess. H. Doc 390, 76th Cong., 1st Sess. H. Doc. 602, 79th Cong., 2nd Sess. 1. 29. 40. 41. 30. TABLE 16-C FORT WORTH, TEXAS DISTRICT OTHER AUTHORIZED FLOOD CONTROL PROJECTS (See Section 33 of Text) For Last Cost to September 30, 1985 Full Report See Annual Operation and Project Report For Construction Maintenance Big Fossil Creek, TX3 1969 - - Big Spring, TX2 1979-- Brownwood Channel Improvement, TX' -- - Carl L. Estes Dam and Lake, TX2 1979 -- Duck Creek Channel Improvement, TX4 1983 -- Fort Worth Floodway (Clear Fork), TX3 1971 -- Fort Worth Floodway (West Fork), TX3 1971 -- Greenville, TX3 1983 -- Lake Brownwood Modification, TX4 1983 -- Lake Fork Lake, Sabine River, TX4 - - - Navasota Lake, Navasota River, TX4 - - - Pecan Bayou Lake, Pecan Bayou, TX4 - - - Plainview Local Flood Protection Project, TX4 1979 - - Roanoak Lake, TX4 1979 - - Rutledge Hollow Creek Channel Improvement, Poteet, TX3 1969 - - Three Rivers, TX3 1983 - - Zacate Creek Channel, TX3 1983 - - ' Deauthorized 1 Nov. 81. 2 Inactive. Completed. 4 Recommended for deauthorization, H.R. 3678, August 23, 1983, 98th Congress, 1st Session. INSPECTION OF COMPLETED FLOOD CONTROL PROJECTS TABLE 16-D (See Section 31 of Text) Location Dates of Inspection Big Fossil Creek Nov. 29, 1983 Dallas Floodway Sep. 23, 1985 East Fork Aug. 25, 1985 Fort Worth Floodway Dec. 1, 1983 Greenville Oct. 10, 1984 Munday Nov. 30, 1983 Pleasanton Aug. 14, 1985 Poteet Aug. 14, 1985 San Antonio Floodway Aug. 14, 1985 Sulphur River Levees Aug. 23, 1985 Zacate Creek Aug. 14, 1985 16-21 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION TABLE 16-E (See Section 34 of Text) Project Cost Burton Creek, Bryan, TX $ 21,191 California Creek, Hamlin, TX 43,221 Calloway Branch, Hurst, TX 268,409 Chacon Creek, Laredo, TX 0 Elm Fork, Gainsville, TX 105,860 Hickory Creek, Balch Springs, TX 27,639 Lake Creek, Round Rock, TX 3,009 Lorean Branch, Hurst, TX 135,237 Lower Peaks Branch, Dallas, TX 1,021 Munday, TX 495 Pecan Creek, Gainesville, TX 45,431 Roscoe, TX 266 Walnut Creek, Sequin, TX 25,387 Wheeler Creek, Gainesville, TX 2 16-22 TABLE 16-F FORT WORTH, TEXAS DISTRICT JOBS ACT (PL 98.8 March 24, 1983) Total Cost to Project Funding FY 1984 FY 1985 SSeepp.. 3300,, 11998855 Bardwell Lake, TX Belton Lake, TX Benbrook Lake, TX. Canyon Lake, TX San Gabriel River, TX Grapevine Lake, TX Hords Creek, TX North San Gabriel Dam, Lake Georgetown, TX Ferrell's Bridge Dam- Lake O' The Pines, TX Lavon Lake, TX Lewisville Lake, TX Navarro Mills Lake, TX O.C. Fisher Dam & Lake, TX Proctor Lake, TX Sam Rayburn Dam & Reservoir, TX Somerville Lake, TX Stillhouse Hollow Dam Town Bluff Dam, TX Waco Lake, TX Maint. Approp. Cost Maint. Approp. Cost Maint. Approp. Cost Maint. Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost Maint. Approp. Cost Maint. Approp. Cost Maint. Approp. Cost Maint. Approp. Cost Maint. Approp. Cost Maint. Approp. Cost Maint. Approp. Cost Maint. Approp. Cost Maint. Approp. Cost Maint. Approp. Cost Maint. Approp. Cost Maint. Approp. Cost Maint. Approp. Cost (-)54,220 351,151 (-)17,985 215,041 (-)34,135 154,567 (-)5,323 234,775 (-)3,778 485,604 1,400,000 1,066,105 (-)44,604 617,293 (-)11,960 535,485 (-)8,366 0 (-)1,143 598,649 98,416 1,013,015 (-)61 879,439 (-)3,844 302,236 (-)51 390,884 (-)101 630,259 (-)323 770,536 (-)2,035 792,094 (-)10,550 106,309 353,480 353,480 274,115 274,115 706,856 706,856 240,177 240,177 514,822 514,822 - 1,400,000 - 1,400,000 (-)28,257 (-)8,855 (-)6,900 (-)6,900 (-)100 (-)65 (-)412 438,160 (-)949 578,617 680,156 660,700 567,690 567,690 76,070 76,070 620,857 620,857 1,177,666 1,177,666 951,239 951,239 304,656 304,656 394,949 394,949 679,099 679,099 893,177 893,177 885,065 885,065 138,450 138,450 450,688 450,688 623,351 623,351 16-23 TABLE 16-F REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 JOBS ACT (PL 98.8 March 24, 1983) Project Funding FY 1984 FY 1985 TSoe.t3a,l1 8Cost to Sep. 30, 1985 Whitney Lake, TX Wright Patman Lake, TX Grand Prairie Lake, TX Maint. Approp. Cost Maint. Approp. Cost New Work Approp. Cost (-)3,025 437,555 (-)216 303,147 0 218,800 521,692 521,692 315,784 315,784 250,000 (-)24,666 250,000 16-24 ALBUQUERQUE, NM, DISTRICT* The district comprises watershed of Canadian River and tributaries and the watershed of Arkansas River and tributaries in Colorado and New Mexico; the watershed of Rio Grande and tributaries including Pecos River and its tributaries upstream of Amistad Lake; and watershed of Mimbres River and its tributaries in New Mexico. Note: The district watershed boundaries were revised in July 1982 to include all of New Mexico west of the Texas state line and the southwest corner of Colorado west of the Kansas state line. IMPROVEMENTS FloQod Control 1. Albuquerque Diversion Channels, NM .... 2. Conchas Lake, NM ...................... 3. ElPaso,TX........................... 4. Highway 12, CO ......................... 5. H olly, C O ............................... 6. John Martin Reservoir, CO................ 7. Rio Grande Basin, NM................... 7A. Abiquiu Dam, NM ....................... 7B. Cochiti Lake, NM ....................... 7C. Galisteo Dam, NM ....................... 7D. Jemez Canyon Dam, NM ................. 7E. Rio Grande Floodway, NM............... 7F. Truth or Consequences (Hot Springs) Unit, NM .................. 8. Santa Rosa Dam and Lake, NM ........... Page 17-1 17-2 17-2 17-2 17-3 17-3 17-3 17-4 17-4 17-4 17-5 17-5 Flood Control 1. ALBUQUERQUE DIVERSION CHANNELS, NM Location. In an area which comprises watersheds of ephemeral streams entering a 15-mile reach of Rio Grande from the east at Albuquerque, NM, and vicinity. Combined drainage area of tributaries is about 276 square miles. Sandia range of the Rocky Mountains, which is about 12 miles east of Rio Grande, forms eastern border of watersheds. Crest of mountain range rises more than a mile over river to elevation of 10,692 feet above mean sea level. (See Geological Survey Map, Albuquerque, NM, quadrangle, scale 1:62,500.). 9. Smith Creek, CO ...................... . 17-6 10. Trinidad Lake, CO ...................... 17-6 11. Two Rivers Dam, NM ................... 17-7 12. Inspection of completed flood control projects .......................... 17-7 13. Scheduling flood control reservoir operations .................... 17-7 14. Other authorized flood control projects .......................... 15. Flood control work under special authorizations.................... 17-8 17-8 General Investigations 17-5 16. Surveys....... .......................... 17-8 17-5 17. Collection and study of basic data ......... 17-8 Existing project. Plans for improvement consist of north and south diversion channels on high ground east of and parallel to valley. Channels are designed to carry floods equal in magnitude to standard project flood from all tributaries. For description of complete improvement and authorizing legislation see page 17-15 of Annual Report for FY 1973. Local cooperation. Section 2 Flood Control Act of 1938 applies. For details of local cooperation requirements see page 17-2 of Annual Report for FY 1973. Operations and results during fiscal year. The North Diversion Channels prevented $6,481,400 in flood dam- *All cost and financial statements for projects are listed at the end of this chapter. All other tables are referenced in text and also appear at the end of this chapter. 17-1 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 ages during FY 1985. The estimated total accumulated flood damages prevented were $46,228,200. Peak flood flows recorded during FY 1985 were North Diversion Channel near Alameda, 2,570 c.f.s. on April 28, 1985, and South Diversion Channel 220 c.f.s. on April 28, 1985. Condition at end of fiscal year. Construction of the north and south diversion channels began in March 1965, and was completed in March 1972. Channels are in good condition and well maintained by local interests. 2. CONCHAS LAKE, NM Location. Dam is in San Miguel County, NM, on Canadian River, about one-fourth mile downstream from confluence of Canadian and Conchas Rivers. (See Geological Survey State map of New Mexico, scale 1:500,000, and Geological Survey topographic map. Thcumcari quadrangle, scale 1: 125,000). Existing project. A concrete gravity main dam section 1,250 feet long with a maximum height of 200 feet above streambed located in Canadian River Canyon together with earth dikes on each side having an overall length of about 3.7 miles. Main section contains conduits in its base for release of water to maintain low flows and for drainage of reservoir, and an overflow, ungated spillway 300 feet long. Earth dikes vary in height up to 100 feet and north dike contains a concrete ogee-type emergency spillway 3,000 feet long. Reservoir has a gross storage capacity of 529,000 acre-feet (198,900 for flood control, 259,600 for water conservation and irrigation, and 70,500 dead storage). Dam controls 7,409 square miles of drainage area. (See page 17-16 of Annual Report of 1973 for authorizing legislation.) Local cooperation. None required. Operations and results during fiscal year. Operation of reservoir continued. Reservoir was operated for storage of floodwaters and releases for irrigation purposes. $243,000 in sediment damages were prevented during FY 1985 while no flood damages were prevented. Estimated total accumulated flood and sediment damages prevented by project through FY 1985 were $2,451,800. Estimated irrigation benefits for FY 1985 were $259,100. Estimated total accumulated irrigation benefits through FY 1985 were $8,804,500. Pool elevation at start of FY 1985 was 4,184.28 feet with corresponding storage of 198,839 acre-feet. Total releases for reporting period were 73,885 acre-feet. Releases of 71,874 acre-feet were made to Arch Hurley Conservancy District and 2,147 acre-feet to Bell Ranch. Pool elevation on September 30, 1985, was 4,194.46 feet with corresponding storage of 271,660 acre-feet. Sediment deposition during the fiscal year was 2,170 acre-feet. Condition at end of fiscal year. Existing project was essentially complete in 1940. Reservoir and appurtenances are in good condition and in operation. Irrigation of some lands under project was begun in November 1945. A cost sharing agreement between the Government and the State of New Mexico for additional Recreation Development at Conchas Lake was approved in August 1977. Costs of the facilities are 50 percent State of New Mexico and 50 percent Federal. Construction of recreation facilities was initiated in FY 1978 and completed in FY 1983. 3. EL PASO, TX Location. At El Paso, El Paso County, TX, which is on left bank of Rio Grande in the reach that forms part of international boundary between United States and Republic of Mexico. (Geological Survey map for El Paso, TX; New Mexico quadrangle, scale 1:250,000.) Existing project Consists of a single-purpose flood control system of detention dams, diversion dikes, conduits and channels to collect, regulate and discharge arroyo runoff into Rio Grande. Runoff from tributary arroyos on eastern, southern, and western slopes of adjacent Franklin Mountains often inundates sections of city and its outlying suburban developments. Project is divided into three independent elements: Northwest area, Central area, and Southeast area. The project plan satisfies the 1933 U.S. and Mexico agreement on limited tributary discharge into the Rio Grande in El Paso, Texas. (See Table 17-B for authorizing legislation.) Local cooperation. Section 2 Flood Control Act of June 28, 1938 applies. Operations and results during fiscal year. Flood control dams in operation during FY 1985 and dates of completion of construction are as follows: Northgate and Range Dams (February 1973); Sunrise and Mountain Park Dams (October 1974); and Pershing Dam (March 1977); Fort Bliss Diversion Channel (November 1978); Oxidation Pond and Buena Vista Diversion and Oxidation Pond Outlet Conduit (November 1980); Mulberry and Thorn Drive Dams (June 1982); Mesa Dam (September 1982); McKelligon Canyon Dam (October 1982) Keystone Dam (September 1983); Keystone Outlet Conduit was completed in March 1984 and Highway Diversion Channel (May 1985). During FY 1985 flood flows and flood control storage were minimal; however, damages which would have resulted from these flows were prevented. The estimated total flood damages prevented since completion of Northgate and Range Dams in 1973 through FY 1985 were $22,700. Condition at end of fiscal year. Construction has temporarily ended in the Central Area. Remaining projects include the Fillmore-Van Buren Dams System and Dam Safety Assurance Program modifications to the existing Range and Northgate Dams. The Central Area of the project is about 79 percent complete. In the Northwest Area, construction of Keystone Dam Outlet Conduit was awarded in March 1983 and was 100 percent complete at the end of the FY 1985. Remaining works consist of the Borderland Diversion project. The Northwest Area is approximately 67 percent complete. The Reconnaissance Report on the Southwest Area was completed in December 1982 and the preparation of the General Design Memorandum is approximately 75 percent complete. 4. HIGHWAY 12, CO Location. Highway 12, along the Purgatoire River, Las Animas County, CO approximately 7 miles above Tinidad, CO to Weston, CO. (See Geological Survey Map, Madrid, CO quadrangle, scale 1:24,000.) 17-2 ALBUQUERQUE, NM, DISTRICT* Existing project. Three locations on the left bank of the Purgatoire River are protected from bank erosion during flood flows by an approximate total of 1950 feet of Kelner jacks spaced at 12.5 feet on centers. Local cooperation. Section 3 of FC Act of June 22, 1936 applies. Local interests are in compliance with Section 221 1970 FC Act and PL 91-646 Uniform Relocation Act of 1970. Operation and results. Operation by local sponsor. Condition of the end of the year. Construction was started in September 1982 and was completed in January 1983. 5. HOLLY, CO Location. Holly, CO, Cheyenne County, is situated on the north bank of the Arkansas River at the confluence of Wild Horse Creek, a north bank tributary, and Two Butte Creek, a south bank tributary and the Arkansas River at river mile 1,105. (See Geological Survey map, Holly East, CO & KS quadrangle, scale 1:24,000). Existing project. A levee 4.3 miles in length begins at a high point north of Holly extending south along the left bank of Wild Horse Creek to its junction with the Arkansas River then east 4,300 feet below the confluence. Appurtences consist of 2 gravity flow drainage structures for interior ditches and ponding areas with closure structures at the railroad and highway crossings. Contributing drainage area is 5,508 square miles with design flows of 62,000 c.f.s. for Wild Horse Creek and a peak flow of 160,000 c.f.s. for the combined flows on the Arkansas River at Holly, CO. Local cooperation. Section 3, Flood Control Act of June 22, 1936 applies. Local interests are in compliance with Section 221, 1970 FC Act and Public Law 91-646 Uniform Relocation Act of 1970. Operations and results. Operations by local interests. Condition at the end of the year. Construction was started in June 1979 and placed in operation in 1982. Project structures are in good condition. 6. JOHN MARTIN RESERVOIR, CO Location. On Arkansas River 1,159 miles upstream from its mouth, 300 miles downstream from its source, in Bent County, about 18 miles upstream from city of Lamar, CO. (See Geological Survey maps for Lamar and Las Animas, CO quadrangles, scale 1:125,000.) Existing project. A concrete and earthfill structure about 2.6 miles long with a maximum height of 106 feet above streambed and an overflow, gated spillway 1,174 feet long. Total capacity of reservoir at spillway crest is 615,500 acre-feet (270,200 for flood control and 345,300 for conservation and recreation storage). Reservoir controls a contributing drainage area of 18,130 square miles and is operated as a unit of coordinated reservoir system for flood control in Arkansas River Basin. Public Law 89-298 modifled the act of June 22, 1936 (49 Stat. 1570) to authorize 10,000 acre-feet of reservoir flood control storage space for fish and wildlife and recreation purposes. For detail of completed improvement and authorizing legislation see page 17-16 of Annual Report for FY 1973. Local cooperation. Section 3 Flood Control Act of June 22, 1936, applies. Operations and results during fiscal year. Routine maintenance and operation continued. Regulation of conservation storage continued under rules and regulations of Arkansas River Compact. No flood damages were prevented during FY 1985; however, $295,700 sediment damages were prevented. Estimated total flood and sediment damages prevented by project through FY 1985 were $75,299,300. Estimated irrigation benefits for FY 1985 were $472,800. Estimated total accumulative irrigation benefits were $22,065,200. Maximum pool elevation of 3,852.40 feet with corresponding storage of 211,123 acre-feet occurred on June 7, 1985. 'Total releases for FY 1985 were 329,653 acrefeet. Releases attributed to irrigation benefits amounted to 120,293 acre-feet. Sediment deposition was 2,640 acrefeet. Condition at end of fiscal year. Storage and operation of reservoir for irrigation began in March 1943. Resevoir and appurtenances are in good condition and in operation. 7. RIO GRANDE BASIN, NM Location. Improvements are on Rio Grande and tributaries in New Mexico. More definite locations and descriptions of individual projects are in following paragraphs and individual reports by projects. Existing project. Flood Control Act of 1948 authorized flood control phase of comprehensive plan of development of water resources of Rio Grande basin in New Mexico (H. Doc. 243, 81st Cong., 1st sess.) with exception of Chiflo Dam and Reservoir and spillway gate structure at Chamita Dam. Although recommended, Chiflo Dam and Reservoir was deleted from authorized plan. It was excluded without prejudice to future consideration by Congress. It was requested at that time, by States of Colorado and Texas, that project be deferred for restudy regarding required storage and methods of operation. By same act, Congress also authorized for construction irrigation phase of comprehensive plan as recommended by Bureau of Reclamation (H. Doc. 653, 81st Cong., 2nd sess.). The act also stipulated that work should be prosecuted in accordance with joint agreement approved by Secretary of the Army and Acting Secretary of the Interior on November 21, 1957. In addition, under that agreement Bureau of Reclamation was given responsibility for construction, operation, and maintenance of channel rectification, and drainage rehabilitation and extension phases of unified plan of improvement. Authority for Chamita Dam and Reservoir was abrogated when Cochiti Dam and Reservoir was authorized. (See Table 17-B for authorizing legislation and Table 17-C for existing projects.) All operations and costs for projects in authorized plan are in individual reports on the following pages. 17-3 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 7A. ABIQUIU DAM, NM Location. Project is one unit of flood control phase of comprehensive plan for Rio Grande and tributaries, New Mexico. Abiquiu Dam is on Rio Chama near town of Abiquiu, NM, about 32 miles upstream from confluence of Rio Chama and Rio Grande. (See Geological Survey Map for plan and profile of Rio Chama, NM, from mouth to mile 103, sheet 1, and Army Map Service, Aztec, NM; Colorado NJ 13-10, scale 1:250,000.) Existing project. An earthfill dam 1,540 feet long, 325 feet high, with a 12-foot diameter controlled outlet, and an uncontrolled spillway in a natural saddle about one mile north of left abutment. Reservoir provides 565,000 acre-feet of flood control and sediment storage. Total capacity at spillway crest is 1,212,000 acre-feet. For detail description of completed improvements and authorizing legislation see Annual Report of 1973. A major rehabilitation project was completed in September, 1980 and the recreation facilities were completed in FY 1981. Local cooperation. None required. Operations and results during fiscal year. Routine maintenance and operation continued. Storage and flows were regulated in accordance with Section 203, Flood Control Act of 1960. On October 1, 1985, the pool elevation was 6,244.83 feet. The maximum pool (6,256.22 feet) and storage (382,720 acre-feet) occurred on May 29, 1984. On September 30, 1985, the pool elevation was 6,244.81 feet with a corresponding storage of 317,860 acre-feet. There was 2,488 acre-feet of sediment deposition during FY 1985. There were $47,242,000 in flood damages prevented during FY 1985. Sediment damages prevented were $278,700. Accumulated flood and sediment damages prevented by the project since completion were $159,028,000 through FY 1985. Condition at end of fiscal year. Project was placed in operation in February 1963. Project structures are in good condition and in operation. 7B. COCHITI LAKE, NM Location. Dam is at river mile 340 on Rio Grande (river mile 0 being at intersection of New Mexico-Texas State line with international boundary at El Paso, TX), near Pueblo de Cochiti, which is about 50 miles upstream from Albuquerque, NM. (See Geological Survey Maps, Cochiti Dam, NM, quadrangle and Santo Domingo Pueblo, NM, quadrangle, scale 1:24,000.) Existing project. Consists of an earthfill dam about 5.4 miles long with a maximum height of 251 feet above streambed. Project extends generally in an east-west line across Rio Grande to a point about 2 miles east of Rio Grande and then southward across Santa Fe River. An uncontrolled spillway with a 460-foot-long ogee-weir and a 160-foot notch 10.5 feet deep in the center is at the embankment on south side of Santa Fe River. Operational releases for flood control and irrigation are made through a 3-barrel gated conduit in left abutment on Rio Grande.. Reservoir has a storage capacity of 492,500 acre-feet for flood control, 103,800 acre-feet for sediment and 45,700 acre-feet for recreation within the sediment space, for a total of 596,300 acre-feet. The project controls flood waters from a 11,695 square mile drainage area. For more improvements details see page 17-7 of Annual Report for 1980. See page 17-14 of fiscal year 1981 Annual Report for Authorizing Legislation. Local cooperation. None required. Operations and results during fiscal year. The project was completed in June 1975. On October 1, 1984, the pool elevation was 5,327.61 feet with a corresponding storage of 47,371 acre-feet. The maximum pool elevation was 5,413.47 feet with a storage of 282,716 acre-feet on May 28, 1985. On September 30, 1985, the pool elevation was 5,387.34 feet with a corresponding storage of 178,473 acrefeet. There was 1,968 acre-feet of sediment deposition during FY 1985. There were $70,585,000 in flood damages prevented during FY 1985. Sediment damages prevented were $220,400. Accumulated total damages prevented are $143,589,300. Conditions at end of fiscal year. The dam and appurtenances were placed in operation in 1975. The Cochiti Recreation area was completed in 1976, with the Visitors Center completion in 1977. The Tetilla Peak Recreation area was re-advertised and awarded in 1980 and completed in 1981. Project structures are in good condition and in operation. 7C. GALISTEO DAM, NM Location. Dam is at river mile 12 on Galisteo Creek, a tributary of Rio Grande. Definite project site is about 8 miles upstream of project document site. Reservoir will extend upstream from dam for about 4 miles to near village of Waldo, NM. (See Geological Survey Map, San Pedro 1, NM quadrangle, scale 1:24,000.) Existing project. Consists of an earthfill dam 2,820 feet long with a maximum height of 158 feet above streambed. The outlet works consist of a 10-foot diameter uncontrolled outlet with a discharge capacity of 4,980 cubic feet per second with pool at spillway crest elevation. The spillway is a broad crested weir 250 feet long in right abutment. The flood control storage is 89,000 acre-feet. For more details of completed improvements and authorizing legislation see page 17-17 of Annual Report for 1973. Local cooperation. None required. Operations and results during fiscal year. Routine operation and maintenance continued. Operation of the project began on October 11, 1970. The reservoir was empty on October 1, 1985. No storage occurred during FY 1985. Peak inflow was 110 c.f.s. and maximum outflow was 110 c.f.s. There was 56 acre-feet of sediment deposition during the year and the reservoir was empty on September 30, 1985. Sediment damages prevented during the FY were $6,300 totaling $105,900 through FY 1985. Condition at end of fiscal year. Project was placed in operation in October 1970. Project structures are in good condition and in operation. 17-4 ALBUQUERQUE, NM, DISTRICT 7D. JEMEZ CANYON DAM, NM Location. In Sandoval County, NM, on Jemez River about 2 miles upstream from confluence of Jemez River and Rio Grande, about 5 miles northwest of Bernalillo, NM (See Geological Survey map for Bernalillo quadrangle, scale 1:125,000.) Existing project. An earthfill dam 780 feet long with a maximum height of 135 feet above streambed, and offchannel uncontrolled saddle spillway 400 feet wide, and a 13-foot diameter gated outlet in left abutment with discharge capacity of 8,340 cubic feet per second with pool at spillway crest elevation. Reservoir has a capacity of 106,100 acre-feet (73,000 acre-feet for flood control and 33,100 acre-feet for sediment control). For more detailed description of completed improvements and authorizing legislation see page 17-17 of Annual Report for 1973. Local cooperation. None required. Operations and results during fiscal year. On October 1, 1984, the pool elevation was 5,161.44 feet with a corresponding storage of 2,418 acre-feet. The maximum pool elevation was 5,197.05 feet with a storage of 29,862 acre-feet on June 9, 1985. On September 30, 1985 the pool elevation was 5,194.67 feet with a corresponding storage of 26,621 acre-feet. The reservoir was regulated for sediment control during FY 1985. Sediment deposition during FY 1985 was 1,419 acre-feet. There were $1,679,000 in flood damages prevented during FY 1985. Sediment benefits during FY 1985 were $158,900. Estimated total accumulated flood and sediment damages prevented by the project through FY 1985 were $8,453,000. Condition at end of fiscal year. Project was placed in operation in October 1953. Project structures are in good condition and in operation. 7E. RIO GRANDE FLOODWAY, NM Location. Project is one unit of flood control phase of comprehensive plan of improvement for Rio Grande Basin in New Mexico. It is on the Rio Grande and covers a section of the river commencing near Truth or Consequences (formerly Hot Springs) at about river mile 123 and extends upstream to Espanola, NM, about river mile 394. (See Table 17-D on Rio Grande Floodway.) Existing project. Consists of flood protection and major drainage improvements by channel rectification, levee enlargement and construction, and bank stabilization work where needed to protect levees. Construction of project is a joint undertaking by Bureau of Reclamation and the Corps. Portions to be done by Corps will consist of levee enlargement, construction, and bank protection work, with channel-rectification and drainage-rehabilitation work the responsibility of Bureau of Reclamation. Levees constructed by local interests exist through reach of river involved, but are not uniform as to grade, section, or standard of construction, and in many places are threatened by meandering river. (See Table 17-D on existing project and Table 17-B for authorizing legislation.) Local cooperation. In addition to usual requirements, local interests are responsible for all highway, bridge, and public utility relocations or replacements required in construction of project. Local interests will also be required to comply with requirements of Section 221, 1970 Flood Control Act and PL 91-646 Uniform Relocation Assistance Act of 1970. Total costs for all requirements for completed Albuquerque unit under terms of project authorization were $75,000. There were no non-Federal costs in connection with construction of Cochiti to Rio Puerco unit of floodway. Espanola Valley unit is in the deferred category. The city of Espanola or Santa Clara Pueblo has not given indication they plan positive action to solve the flooding problem. For more details see page 17-8 of Annual Report for 1980. Operations and results during fiscal year. There were $1,230,700 in flood damages prevented by the completed floodway project during FY 1985. Estimated total accumulated flood damages prevented by the floodway project through FY 1985 amounted to $42,116,600. The peak flow of the Rio Grande through the middle valley was 9,380 c.f.s. at Albuquerque on April 24, 1985. The peak at San Acacia was 10,010 c.f.s. on May 30, 1985. Condition at end of fiscal year. Construction of Albuquerque unit and Cochiti to Rio Puerco units of Rio Grande Floodway project is complete. San Acacia to Bosque del Apache unit is deferred for restudy. The Truth or Consequences (Hot Springs) unit was reclassified to the active category on July 18, 1973, based on a letter of intent to cooperate from the city of Truth or Consequences dated May 31, 1973. The Espanola Valley unit was reclassified to deferred category on 17 October 1973. 7F. TRUTH OR CONSEQUENCES UNIT, NM Location. Vicinity city of Truth or Consequences, New Mexico. Existing project. Authorized plan of improvement includes 4 miles of 20-foot-high levees with positive seepage control, an interior drainage system, and 5 miles of diversion channels. The diversion channels would be required for control of floods on tributary arroyos at and in the vicinity of Truth-or Consequences. Estimated Federal cost is not available pending project reformulation. (See Table 17-B for authorizing legislation.) Location cooperation. Section 2 Flood Control Act of 1938 applies. Letters of intent have been received from the City of Truth or Consequences (dated June 8, 1983) and the County of Sierra (dated June 8, 1983). Operations and results during fiscal year. Preconstruction planning was initiated in FY 1979 and continued during FY 1985. 8. SANTA ROSA DAM AND LAKE, NM Location. Lake is in Guadalupe County, on Pecos River, at river mile 766.4 approximately 7 miles north of Santa Rosa, NM (See U.S. Geological Survey map, Corazon, NM, sheet, scale 1:125,000.) 17-5 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Existing project. Project operation began in November 1979. Authorized plan of improvement consists of an earth and rock fill dam 1,950 feet long and 212 feet maximum height above the streambed. Project purposes are flood control, irrigation and sediment retention. An unlined, open rock cut about 1,000 feet back from the left abutment serves as an uncontrolled spillway. The outlet works, located in the left abutment, consists of a control tower, intake structure with gates, and a 10-foot diameter concrete lined tunnel with a terminal flip bucket energy dissipater. Storage capacity at the spillway crest is 447,100 acre-feet which includes 80,100 acre-feet sediment reserve, 200,000 acre-feet irrigation and 167,000 acre-feet flood control storage. Surface area of the reservoir at the spillway crest is 10,685 acres. Contributing drainage area at the dam site is 2,434 square miles. For a more detailed report of the authorized project including the modification to existing Summer Lake see page 17-8 of fiscal year 1981 Annual Report. For authorizing legislation see page 17-14 of fiscal year 1981 Annual Report. Local cooperation. In addition to first costs, operation and maintenance of both reservoirs will be responsibility of Federal Government; however, Carlsbad Irrigation District will be required to contribute to operation and maintenance costs an annual amount equal to what they now pay toward Sumner Lake. Carlsbad Irrigation District also has agreed to use Sumner Lake for floodcontrol. Because they will realize equivalent benefits from storage capacity in Santa Rosa Dam and Lake, they will continue to fulfill their repayment obligation. The New Mexico Division of Parks will be required to manage the recreation facilities. Activities include camping, picnicking, boating and hiking. For more requirements and details on final approval in 1974 for transfer of irrigation storage from Sumner Lake to Santa Rosa Dam and Lake (formerly Los Esteros Lake) see page 17-5 of Annual Report for 1980. Operations and results during fiscal year. The project was completed in late 1979 and reservoir operation for irrigation was started in March 1980. Pool elevation at start of fiscal year was 4,706.28 feet with storage of 16,701 acre-feet. Total releases for the fiscal year were 45,279 acre-feet. Pool elevation on September 30, 1985 was 4,743.02 feet with a storage of 94,811 acre-feet. The maximum elevation was 4,746.65 feet with a storage of 108,242 acre-feet on July 20, 1985. There was 922 acre-feet of sediment deposition during the fiscal year. Sediment damages prevented during the fiscal year were $103,300. Releases attributed to irrigation benefits were 21,265 acre-feet. Irrigation benefits for the fiscal year were $89,000 with an accumulative total of $895,800 through FY 1985. Condition at end of fiscal year. Construction contract for the recreation area was awarded in September 1979 and completed in October 1980. Design studies for spillway modification were initiated in FY 1979 and construction was completed in FY 1982. 9. SMITH CREEK, CO Location. Smith Creek, Pleasant View Estates, El Paso County, CO is located 15 miles north of Colorado Springs, CO. (See Geological Survey Map, Monument, CO quadrangle, scale 1:24,000.) Existing project. The construction of 8 gabion weirs in the channel on Smith Creek to protect existing sewage lagoons for the Pleasant View Estates during flood flows. The upper most gabion weir, 35 feet in width, would act as a collection structure. The remaining 7 weirs, 15 feet in width, would reduce flood flows to about 3 feet per second during flood design stage. Local cooperation. Section 3 FC Act of June 22, 1936 applies. Local Interests are in compliance with Section 221, 1970 FC Act and PL 91-646 Uniform Relocation Act of 1970. Operations and results. N/A Condition at the end of the year. Construction was started in June 1982 and was completed in December 1982. 10. TRINIDAD LAKE, CO Location. On Purgatoire River about 161 miles above its junction with Arkansas River. Project is about 4 miles upstream from city of Trinidad, CO. (See Geological Survey map. Trinidad, CO, quadrangle, scale 1:24,000.) Existing project. Consists of an earthfill dam 6.610 feet long, with a maximum height of 200 feet above streambed, an uncontrolled spillway 1,000 feet wide in left abutment, and a 10-foot diameter, gate-controlled conduit in right abutment with discharge capacity of 5,870 c.f.s. with water surface at top of flood control pool. Reservoir provides for storage of 60,000 acre-feet for flood control, 39,000 acre-feet for sediment, 20,000 acre-feet irrigation, and 4,500 acre-feet for recreation, a total of 123,500 acre-feet. Reservoir controls a drainage area of 671 square miles and will be operated for flood and sediment control, irrigation, and recreation purposes. For authorizing legislation see page 17-14 of fiscal year 1981 Annual Report. Local cooperation. Assurances of local cooperation received from City of Trinidad and Purgatoire River Water Conservancy District were formally accepted May 11, 1967, after execution of irrigation repayment contract. For complete details of requirements and costs pertaining to the execution of the irrigation repayment contract and the addition of permanent storage for recreation facilities see page 17-9 of fiscal year 1980 Annual Report. Operations and results during fiscal year. The reservoir was operated for flood control and irrigation releases during the fiscal year. On October 1, 1984 the pool elevation was 6,182.78 feet with a corresponding storage of 23,000 acre-feet. The maximum pool elevation was 6,200.24 feet with a corresponding storage of 37,018 acre-feet on May 19, 1985. On September 30, 1985, the pool elevation was 6,172.87 feet with a corresponding storage of 16,936 acre-feet. Sediment deposition during FY 1985 was 531 acre-feet. Sediment damages prevented during FY 1985 was $198,600. Accrued sediment benefits are $1,533,800. Irrigation benefits for FY 1985 were $83,600. Accrued irrigation benefits through FY 1985 were $899,700. Irrigation releases for the year were 25,424 acre-feet. 17-6 ALBUQUERQUE, NM, DISTRICT Conditions at end of fiscal year. The project was placed in operation in 1977. The recreation facilities were completed in 1980. The Dam Safety Assurance Contract was awarded in September 1982. Project features are in good condition and in operation. 11. TWO RIVERS DAM, NM Location. About 14 miles southwest of Roswell, NM, on Rio Hondo and Rocky Arroyo. Rio Hondo is formed at confluence of Rio Ruidoso and Rio Bonito, near village of Hondo, NM, in foothills region of Sierra Blanca in southeastern part of Lincoln County, NM, and flows generally easterly to its confluence with Pecos River near Roswell, NM (See Geological Survey map, Hondo Reservoir quadrangle, scale 1:24,000.) Existing project. Diamond "A" Dam is an earthfill structure, 4,885 feet long and 98 feet high, with a gated outlet. Rocky Dam is an earthfill structure 2,940 feet long and 118 feet high with an uncontrolled outlet. No provision is made for storage except for flood control. Flood releases will be controlled so that flows through Roswell will not exceed Rio Hondo channel capacity which is about 1,000 c.f.s. Capacity of Two Rivers Reservoir at spillway crest is 168,000 acre-feet, of which 18,000 acre-feet are provided for sediment reserve. Together these dams regulate runoff from 1,027 square miles of drainage area. For details of completed improvement and authorizing legislation see page 17-18 of Annual Report for 1973. Local cooperation. Section 2 Flood Control Act of 1938 applies and compliance is satisfactory. Operations and results during fiscal year. Routine maintenance and operation continued. The reservoir was empty on October 1, 1984. The maximum pool elevation of 3,985.44 feet with a corresponding storage of 714 acrefeet occurred on 13 August 1985. There were $141,900 in flood damages prevented during 1985. Sediment damages prevented were $85,900. Estimated total accumulated flood and sediment damages prevented through FY 1985 were $6,619,000. There were 313 acre-feet of sediment deposition during FY 1985. The accrued sediment benefits through FY 1985 are $554,000. Condition at end of fiscal year. Project is complete and was placed in operation July 1963. Project features are in good condition and in operation. 12. INSPECTION OF COMPLETED FLOOD CONTROL PROJECTS Included under this heading is inspection of completed flood control projects transferred to local interests for operation and maintenance. Projects in Texas, Colorado, and New Mexico were inspected. Federal costs for the fiscal year were $170,631. An appropriation of $250,000 was provided through the Inspection of Completed Works program in FY 1984 to evaluate the performance of the Albuquerque North Diversion Channel project. 17-7 13. SCHEDULING FLOOD CONTROL RESERVOIR OPERATIONS Pursuant to Section 7, Flood Control Act of 1944, three projects are operated by others for flood control. These projects are Platoro, Pueblo, and Sumner. Platoro Dam on Conejos River above the town of Platoro, Conejos County, CO controls runoff from 40 square miles of high mountain area. Authorized purposes are irrigation storage and flood control. ToIbtal storage is 60,000 acrefeet with the top 6,000 acre-feet for flood control. The 54,000 acre-feet is joint use storage with flood-control on a forecast basis during spring runoff. Platoro Dam was authorized by Interior Appropriation Act of 1941 (see H Doc 693, 76th Cong., 3rd Sess.) Construction of project was completed by Water and Power Resources Service (Bureau of Reclamation) in FY 1952. On October 1, 1984, storage in Platoro reservoir was 34,025 acre-feet, elevation 10,004.2 feet. During the period April 27 through May 9 a total of 10,413 acre-feet of storage was evacuated in anticipation of required flood space due to forecasted spring runoff. Maximum storage of 57,216 acre-feet, elevation 10,031.5 feet occurred on June 27, 1985. On September 30, 1985, storage was 53,506 acrefeet, elevation 10,027.5 feet. Peak flow at Mogote gage was 2,920 c.f.s. on June 25, 1985. $104,400 in flood damages were prevented by the project during FY 1985. Total flood damages prevented to date are at $3,312,900. Total cost for activity during FY 1985 was $12,414. Pueblo Dam is part of the Fryingpan-Arkansas project which was authorized under Public Law 87-590, 87th Congress, HR 2206 on August 16, 1962. The project was completed in August 1975. Pueblo is operated by the U.S. Bureau of Reclamation and is located at river mile 1,293.7 on the Arkansas River in Pueblo County Colorado. Pueblo reservoir has 27,000 acre-feet exclusive flood space and 66,000 acre-feet joint use space. Operation of Pueblo Reservoir began on February 10, 1974. Storage on October 1, 1984 was 221,181 acre-feet, elev. 4,870.61 feet. Maximum storage during the year was 283,207 acre-feet, elev 4,884.45 feet on March 14, 1985. Storage on September 30, 1985 was 242,549 acre-feet, elev. 4875.64 feet. There were $233,500 in flood damages prevented in FY 1985. Total cost for FY 1985 activity was $14,212. Total flood damages prevented to date are $2,761,900. Sumner Dam is located on the Pecos River at river mile 710.8 in DeBaca County, New Mexico. Sumner Dam was authorized aS Alamogordo Dam by the Secretary of the Interior under a Finding of Feasibility approved by the President of the USA on 6 November 1935, under the Federal Reclamation laws. The original project was completed in 1937. Modification work of raising the dam 16 feet, adding a spillway and limiting the service spillway floor to 56,000 c.f.s. was completed in 1957. A twenty-four inch bypass line was installed in 1977 to pass flows less than 100 c.f.s. Storage on October 1, 1984 was 21,044 acre-feet, elevation 4,247.0 feet. Maximum storage for FY 1985 was 46,203 acre-feet, elevation 4,259.1 feet on March 6, 1985. Storage on September 30, 1985 was 9,685 acre-feet, elevation 4,237.0 feet. Total cost for FY 1985 activity was $9,803. REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 14. OTHER AUTHORIZED FLOOD CONTROL PROJECTS See Table 17-E. 15. FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION Flood control activities pursuant to section 205, Public Law 858, 80th Congress, as amended (preauthorization). Costs during FY 1985 were: San Vicente Arroyo, Silver City NM, $35,546 and Santo Domingo Pueblo, NM, $1,104. Emergency flood control activities repair, flood fighting, and rescue work. (Public Law 99, 84th Cong., and antecedent legislation.) Federal costs for fiscal year 1985 were $155,453 for advance preparation, and $56,938 for flood emergency operations, and $538,327 for repair and restoration. Emergency bank protection (Sec. 14, 1946 Flood Control Act, Public Law 526, 79th Cong.) Federal costs during FY 1985 were: Canipa Cr. Acoma Pueblo, NM $7,500; ST HWY 115 Florence, CO $7,500; Rio Grande at Pilar, NM $6,000; Rio Lucero-El Prado, NM $7,500; Rio Pueblo at Taos, NM $7,500; Rio Ruidoso, NM, TABLE 17-A at County Road B-015 Bridge $15,487; Cimarron Rodeo Grounds, NM $7,500; Fountain Creek at Security, CO $325; Fountain Creek at Colo Springs, CO $11,000; Fountain Creek at Pifion Bridge, Pueblo, CO $6,269; Rio Costilla Amalia, NM $13,339. General Investigations 16. SURVEYS Costs for the fiscal year were $527,292 for flood damage prevention studies, $21,153 for special studies (coordination studies with other agencies), and $241,745 for preauthorization studies, Arkansas River and Tributaries above John Martin Dam, Colorado, Phase I. 17. COLLECTION AND STUDY OF BASIC DATA Fiscal year costs were $164,000 for flood plain management and technical services. Hydrologic studies involving collection and study of basic data, such as stream flow data, collection of suspended sediment samples, recording rain gage data, hydrometeorological studies, and sedimentation studies continued. Costs during the fiscal year were $11,000. See Total Cost5 Section to In Text Project Funding FY 82 FY 83 FY 84 FY 85 Sept. 30, 1985 1. Albuquerque New Work Diversion Channels Project, NM (Federal Funds) (Contributed Funds) (Other Contributed Funds) 2. Conchas Lake, NM 3. El Paso, TX 4. Highway 12, CO 5. Holly, CO Approp. Cost New Work Approp. Cost New Work Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost New Work Approp. Cost New Work Approp. Cost 14,589 58,423 2,648 31,900 - 17,268,450 - 17,268,450 - 518,356 - 518,356 - 854,644 - 854,644 2,912 13,821,4991 542 13,821,4991 691,000 1,364,200 696,200 805,000 11,625,372 602,238 710,414 366,107 838,774 11,574,940 6,878,000 5,150,000 4,100,000 7,350,000 54,479,294 5,542,583 6,026,141 4,267,354 9,062,333 54,046,342 15,000 9,102 68,454 90,500 102,319 44,000 68,804 119 3,059 - 120,500 - 120,500 - 2,021,400 - 2,021,400 17-8 COST AND FINANCIAL STATEMENT ALBUQUERQUE, NM, DISTRICT TABLE 17-A (Continued) COST AND FINANCIAL STATEMENT See Total Cost5 Section to In Text Project Funding FY 82 FY 83 FY 84 - FY 85 Sept. 30, 1985 S Jo.hn Martin New Work Reservoir, CO Rio Grande Basin, NM Abiquiu Dam, NM 7B. Cochiti Lake, NM 7C. Galisteo Dam, NM 7D. Jemez Canyon Dam, NM 7E. Rio Grande, 7F. Floodway, T. or C. Unit, NM 8. Santa Rosa Dam & Lake, NM 9. Smith Creek, CO 10. Trinidad Lake, CO 11. Two Rivers Dam, NM - 39,000 - 3,601 859,000 712,500 793,550 684,579 7. 7A. Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost New Work Approp. Cost Maint. Approp. Cost NeW Work Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost 70,000 95,377 797,800 875,971 128,771 1,270,600 1,292,150 -9,600 53,404 706,900 1,148,752 5,000 13,177 100,000 106,851 -775 36 193,600 342,025 155,000 164,711 -60,000 138,593 500,000 561,101 1,461 60,000 369,297 290,000 311,317 -3,625 1,014 156,700 198,258 10,022 1,000,000 1,020,695 -135,000 1,771 2,231,000 2,368,302 154 1,014,000 1,083,745 9,287 124,000 142,277 245,000 269,016 200,000 162,971 49,734 622,000 680,429 384,730 535,000 598,337 183,000 188,678 %.j VVllil LVil.ll Vlli ;14 %, v" fTVl l1 'Includes $3,492,696 maintenance and improvement costs and $869,978 for emergency relief, excludes $2,279,326, cost of initiating project under the authority of Emergency Relief Appropriation Act of 1935 and $222,669, the cost for work performed with funds transferred to the Corps under Public Works acceleration Act of 1962. 2 Excludes $59,977 emergency relief funds for new work. Includes $30,000 for Code 710. 3 Includes funds for completed Albuquerque and Cochiti to Rio Puerco units and for preconstruction planning of Espanola Valley unit. Excludes $1,000,011 appropriated funds transferred to Bureau of Reclamation under memorandum agreement between that agency and the Corps. 4 Starting in FY 1982, AE&D programs are funded through GI appropriations. 5 Includes funds provided by Jobs Act (PL 98-8 March 24, 1983) for projects listed in Table 17-F. 17-9 134,000 33,519 997,100 771,334 109,900 415,245 1,578,500 1,273,598 10,000 20,565 129,000 123,904 -20,400 9,731 331,100 320,473 45,000 37,505 108,000 320,612 507,200 395,478 9,500 123,364 3,592,000 4,122,547 420,000 390,795 -2,000 10,927 158,100 137,317 28,162 593,000 508,427 84,000 94,303 925,000 883,462 40,000 136,000 106,041 35,000 4,059 374,000 206,379 92,000 100,886 2,300,000 1,898,670 416,000 386,535 192,000 83,664 1,516,000 298,985 383,000 323,109 20,000 2,434 160,000 148,098 15,555,3582 15,555,3582 13,582,500 13,538,434 26,745,028 26,730,710 11,316,806 11,145,663 97,084,559 97,084,559 8,713,700 8,688,214 14,275,053 14,275,053 1,400,477 1,388,497 4,226,972 4,226,972 5,125,051 5,115,722 5,541,8683-4 5,504,585 3-4 41,041,562 40,989,986 2,661,200 2,622,106 219,000 219,000 55,774,758 55,730,493 3,404,500 3,380,302 4,847,244 4,847,244 1,958,712 1,946,718 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 17-B AUTHORIZING LEGISLATION See Date Section Authorizing In Text Act Project and Work Authorized Documents 3. Oct. 27, 1965 4. July 24, 1946 5. June 30, 1948 as amended. 7. June 30, 1948 May 17, 1950 July 14, 1960 7. June 30, 1948 and May 17, 1950 7. June 30, 1948 May 17, 1950 9. July 24, 1946 EL PASO, TX A single-purpose flood control system of detention dams, diversion dikes and channels to collect, regulate and discharge arroyo runoff in the Rio Grande. Consists of four independent units (NW Area, Central Area, and two units, Copper System and Bluff Channel of the SE Area.) HIGHWAY 12, CO Three locations on left bank of Purgatoire River are protected from peak flows by Kelner Jacks. HOLLY, CO Consists of a levee 4.3 miles in length along the left bank of Wild Horse Creek to its junction with the Arkansas River thence 4,300 feet below the confluence. Appurtences include interior drainage re structures at RR and highway crossings. RIO GRANDE BASIN, NM Authorized to be appropriated $3,500,000 to be expended by the Dept. of the Army for partial accomplishment of approved general comprehensive plan for the Rio Grande Basin in NM and Colorado. Authorized to be appropriated an additional $39,000,000 for Dept. of the Army for prosecution of comprehensive plan for the Rio Grande Basin. Authorized Cochiti Dam on Rio Grande and Galisteo Dam on Galisteo Creek as additions to authorized comprehensive plan for Rio Grande Basin (Cochiti Dam was authorized in lieu of Low Chamita Dam of Chamita Reservoir Project on Rio Chama under "substitute plan"). Also authorized to be appropriated an additional $58,300,000 for Dept. of the Army for this addition to comprehensive plan for the Rio Grande Basin. RIO GRANDE FLOODWAY, NM Channel rectification, levee enlargement and construction, and bank stabilization on Rio Grande between river mile 123 and 394 (See Table 17D.) TRUTH OR CONSEQUENCES (HOT SPRINGS), NM Approved comprehensive plan for Rio Grande Basin is set forth in the Report of the Chief of Engineers dated April 15, 1948, for flood control of Rio Grande Basin. In addition to previous authorizations, the completion of the plan approved in the Flood Control Act of 1948, for the Rio Grande Basin, at an estimated cost of $39,000,000. SMITH CREEK, CO Consists of 8 gabion weirs on Smith Creek to protect two sewage lagoons from erosion during flood flows on Smith Creek. H. Doc. 207, 89th Cong., 1st sess.1 Sec. 14, PL 79-526 of 1946 FC Act. Authorized by C of E April 22,1981. Sec. 205, PL 858, 80th Cong. as amended. Authorized by C of E Sept. 9, 1977. H. Doc. 243, 81st Cong., 1st sess. Public Law 516, 81st Cong., 2nd sess. S. Doc. 94, 86th Cong. H. Doc. 243, 81st Cong., 1st sess.' and Public Law 516, 81st Cong., 2nd sess. H. Doc. 243, 81st Cong., 1st sess. H. Doc. 243, 81st Cong., 1st sess. Sec. 14, PL 79-526 of 1946 FC Act. Authorized by C of E April 22, 1981. 1Contains latest published maps. 17-10 ALBUQUERQUE, NM, DISTRICT TABLE 17-C RIO GRANDE BASIN, NM RIO GRANDE BASIN, NM: EXISTING PROJECT (See Section 9 of Text) Drainage Miles Area Total Above Nearest (square Estimated Project River Mouth Town mile) Description Cost Abiquiu Dam Rio Chama 32 Espanola, 2,147 Earthfill 325 feet high, 1,212,000 26,797,0963 NM acre-feet capacity Jemez Canyon Jemez 2 Bernalillo, 1,034 Earthfill 136 feet high, 106,100 4,217,206 .Dam NM acre-feet capacity Rio Grande Rio Grande 123 to 3941 - - Channel rectification, levee 25,744,0002 Floodway enlargement and construction Cochiti Lake Rio Grande 3401 Cochiti, 11,695 Earthfill 251 feet high, 596,300 96,900,000 NM acre-feet capacity Galisteo Dam Galisteo Creek 8 Waldo, 596 Earthfill 158 feet high, 89,000 14,340,280 NM acre-feet capacity 1River mile 0 is at intersection of New Mexico-Texas State Line with international boundary at El Paso, Texas. 2Does not include non-Federal costs. 3Includes $5,383,000 major rehabilitation, $138,900 for recreation facilities. RIO GRANDE FLOODWAY, NM: TABLE 17-D EXISTING PROJECT (See Section 9E of Text) Location Estimated Reach (river miles)' Cost Truth or Consequences unit (formerly Hot Springs) 123 to 129 $8,200,000 San Acacia to Bosque del Apache unit 155 to 226 6,200,000 (1960)2 Cochiti to Rio Puerco unit (not including Albuquerque unit) 236 to 340 2,658,0003 Albuquerque unit 286 to 305 3,130,000' Espanola Valley unit 366 to 394 456,0002 (1970) 5 1River mile 0 being at intersection of New Mexico-Texas State line with international boundary at El Paso, Texas. 2Deferred for restudy. 3In addition, $1,650,000 incurred by the Bureau of Reclamation in this reach. 4In addition, $75,000 incurred by local interest in this reach. In addition, estimated cost to local interests is $69,000 (1970). TABLE 17-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS For Last Cost to September 30,1985 Full Report See Annual Operation & Project Report For Construction Maintenance2 Alamogordo diversion channel, Tularosa (closed) Basin, New Mexico4 1966 189,356 - Alpine, Texas3 1977 130,488 - Cibolo Creek, Texas' 1983 829,500 - Colorado Springs, Fountain que Bouille River, Colorado (Templeton Gap Floodway) 1959 881,262 - Creede, Willow Creek, Colorado (floodway) 1 1952 219,789 - Las Animas, Colorado2 1980 4,956,000 - Las Cruces, New Mexico 2 1980 4,752,310 - Pecos, Texas3 1977 480,273 - Pinon Canyon Dam, Trinidad, Colorado (Sec. 212)1 - 130,678 - Pueblo Arkansas River, Colorado (floodway levee extension)' 1954 201,958 - Santa Fe River and Arroyo Mascaras, New Mexico3 1983 1,123,900 - Socorro diversion channel, tributaries of Rio Grande, New Mexico' 1965 2,259,328 - ICompleted. 2Responsibility of local interests. 3Inactive. 4Deferred. 17-11 TABLE 17-F REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 JOBS ACT (PL 98-8, 24 MARCH 1983) Project Alamosa, CO - Rio Grande, Sec. 14 Canon City, CO - Four mile Cr., Hwy 9, Sec. 14 Canon City, CO - Raynolds Ave. Bridge, Sec. 14 CO Springs, CO - Stratmoor Hills, Sec. 14 CO Springs, CO - U.S. Hwy 25, Sec. 14 Ft. Sumner, NM - Truchas Cr., Sec. 14 Fountain, CO -Fountain Cr., Sec. 14 La Junta, CO - King Arroyo, Sec. 14 Las Animas, CO - St. Hwy 101, Sec. 14 Security, CO - Fountain Cr., Sec. 14 Abiquiu Dam, N.M. Cochiti Lake, N.M. Conchas Lake, NM Galisteo Dam, NM Jemez Canyon Dam, NM John Martin Reservoir, CO Santa Rosa Dam and Lake, NM Two Rivers Dam, NM Funding New Work Approp. Cost New Work Approp. Cost New Work Approp. Cost New Work Approp. Cost New Work Approp. Cost New Work Approp. Cost New Work Approp. Cost New Work Approp. Cost New Work Approp. Cost New Work Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost Maint. Approp. Cost Maint. Approp. Cost 17-12 FY 1983 113,000 2,781 75,000 1,288 35,000 34,988 97,000 0 218,546 1,044 88,000 1,786 170,000 26,716 45,000 44,562 81,000 1,001 177,000 24,812 134,000 5,204 383,100 196,295 50,000 0 537,500 358,517 33,000 1,751 721,200 89,670 15,000 124 58,100 11,640 39,000 3,601 59,500 23,927 41,200 14,861 8,100 2,714 FY 1984 -2,000 108,219 0 61,812 0 12 0 97,000 0 217,502 15,000 101,214 -6,000 136,759 0 438 0 79,999 0 152,188 0 127,367 -400 186,405 -1,100 48,758 - 16,100 162,883 0 30,708 -800 630,763 0 11,855 -6,400 40,060 0 32,801 - 7,200 28,373 - 2,000 24,339 -3,416 1,970 FY 1985 525 1,429 142 541 3,021 2,598 Total Cost to Sept. 30, 1985 111,000 111,000 75,000 75,000 35,000 35,000 97,000 97,000 218,546 218,546 103,000 103,000 164,000 164,000 45,000 45,000 81,000 81,000 177,000 177,000 134,000 134,000 382,700 382,700 48,900 48,900 521,400 521,400 33,000 33,000 720,433 720,433 15,000 15,000 51,700 51,700 39,000 39,000 52,300 52,300 39,200 39,200 4,684 4,684 s LITTLE ROCK, AR, DISTRICT* This District comprises northern, western, and southwestern portions of Arkansas and a portion of southern Missouri embraced in drainage basins of Arkansas River and tributaries above and exclusive of Pine Bluff, AR, and below mouth of Poteau River, near Fort Smith, AR, drainage basins of the Arkansas portion of Little River and tributaries above its mouth near Fulton, AR, and drainage basins of White River and tributaries above Peach Orchard Bluff, AR. In addition, Little Rock District has responsibility for planning, design, construction, and operation and maintenance of that portion of McClellan-Kerr Arkansas River Navigation System below Pine Bluff. Memphis District is responsible for navigation maintenance on White River below Newport, AR, and mouth of Wild Goose Bayou. White River downstream from mouth of Wild Goose Bayou is a part of McClellan-Kerr Arkansas River Navigation System. IMPROVEMENTS Navigation Page 1. Arkansas River Basin, AR, OK, and KS .... 18-2 2. Bank Stabilization & Channel Rectification AR .......................... 18-2 3. David D. Terry Lock and Dam (No. 6), AR ............................... 18-2 4. Lock and Dam No. 2, AR ................. 18-3 5. Lock and Dam No. 3, AR ................. 18-3 6. Lock and Dam No. 4, AR ................. 18-3 7. Lock and Dam No. 5, AR ............... .. 18-3 & Lock and Dam No. 9, AR ................. 18-3 9. Lock and Dam No. 13, AR ................ 18-3 10. Maintenance and Repair Fleet and Marine Terminals, AR .................... 18-3 11. Murray Lock and Dam (No. 7), AR ........ 18-3 12. Norrell Lock and Dam (No. 1) and Entrance Channel, AR .................... 18-3 13. Toad Suck Ferry Lock and Dam (No. 8), AR ................................ 18-4 14. Other Authorized Navigation Projects ..... 18-4 Flood Control 15. Little River Basin (Little Rock District), A R ....................................... 18-4 16. White River Basin (Little Rock District) AR & MO ................................ 18-4 17. Blue Mountain Lake, AR .................. 18-5 18. Clearwater Lake, MO ..................... 18-5 19. DeQueen Lake, AR ....................... 18-5 20. Dierks Lake, AR ......................... 18-5 21. Gillham Lake, AR ........................ 18-6 22. Millwood Lake, AR ....................... 18-6 23. Nimrod Lake, AR ........................ 18-6 24. Pine Mountain Lake, AR .................. 18-6 25. Inspection of Completed Flood Control Projects ........................... 18-6 26. Other Authorized Flood Control Projects .... 18-7 Floor Control (cont) 27. Flood Control Work under Special Authorization ............................. 18-7 Multiple-Purpose Projects Including Power 28. Beaver Lake, AR ......................... 18-7 29. Bull Shoals Lake, AR ..................... 18-7 30. Dardanelle Lock and Dam (No. 10), AR ..... 18-7 31. Greers Ferry Lake, AR .................... 18-8 32. Norfork Lake, AR ......................... 18-8 33. Ozark-Jeta Taylor Lock and Dam (No. 12), AR 1..............8.........34. Table Rock Lake, MO ...................... 18-8 General Investigations 35. Surveys ................................... 18-8 36. Collection and Study of Basic Data ......... 18-9 37. Continuation of Planning and Engineering...18-9 Tables Table 18-A Cost & Financial Statement ....... 18-10 Table 18-B Authorizing Legislation ........... 18-13 Table 18-C Other Authorized Navigation Projects .............. 18-15 Table 18-D Not Applicable Table 18-E Other Authorized Flood Control Projects ................ 18-16 Table 18-F Not Applicable Table 18-G Deauthorized Projects ............ 18-17 Table 18-H Arkansas River Basin; AR, OK, and KS: Navigation .............. 18-18 Table 18-I Arkansas River Basin; AR, OK, and KS: Lakes .................. 18-21 Table 18-J Little River Basin, AR: Lakes ..... 18-22 Table 18-K White River Basin, AR and MO: Lakes ........................... 18-23 Table 18-L Flood Control Work Under Special Authorization ............ 18-24 Table 18-M Jobs Act ......................... 18-25 18-1 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Navigation 1. ARKANSAS RIVER BASIN, AR, OK, AND KS Location. Arkansas River rises in Rocky Mountains near Leadville, CO, and flows southeastward 1,396 miles through Colorado, Kansas, Oklahoma, and Arkansas to join Mississippi River 559 miles above Head of Passes, LA. (See Geological Survey state maps, 1:24,000, and flood control and navigation maps of Mississippi River, Cairo, IL, to Gulf of Mexico, 1970 edition scale 1:62,500.) Previous projects. For details see page 1066, Annual Report for 1932, and pages 744, 864, and 881, Annual Report for 1943. Existing project. Provides for improvement of Arkansas River Basin by construction of coordinated developments for navigation, hydroelectric power, flood control, water supply, sediment control, recreation, and fish and wildlife propagation. McClellan-Kerr Arkansas River Navigation System provides a channel of 9 feet deep and 445.3 miles long, beginning at mouth of White River, which enters Mississippi River 599 miles above Head of Passes, LA, thence 9.8 miles upstream to mouth of Wild Goose Bayou; thence 9.2 miles by a land cut, designated as Arkansas Post Canal to mile 42 (1943 survey) on Arkansas River; thence 376.0 miles along channel of latter stream to mouth of Verdigris River at navigation mile 395.0; thence 50.3 miles up Verdigris River to head of navigation at Catoosa, OK Waterway is canalized throughout its length by 17 locks and dams with total lift of 420 feet. Dardanelle, Ozark-Jeta Taylor, Robert S. Kerr, and Webbers Falls are multiple-purpose projects including power. Lock chambers are 110 by 600 feet. A minimum channel width of 150 feet is provided for Verdigris River, 225 feet for San Bois Creek, 250 feet for Arkansas River, and 300 feet for Arkansas Post Canal and White River. Other coordinated developments consist of 15 lakes, of which 13 are in Tulsa District, Kansas and Oklahoma, and two in Little Rock District. Pertinent data and estimated Federal cost are summarized in Tables 18-H and 18-I, and Arkansas River Basin; AR, OK, and KS: Navigation Lakes. For authorization see Table 18-B, Authorizing Legislation. Local cooperation. For McClellan-Kerr Arkansas River Navigation System, local interests must provide adequate terminal and transfer facilities and bear increased cost of maintenance and operation of all altered rail and highway routes, including bridges and appurtenances, utilities, and other existing improvements, other than federally owned. For lakes see requirements for each individual lake. Terminal facilities. Public port facilities were in operation at Pine Bluff-Jefferson County, Little Rock, and Fort Smith, AR, and Muskogee and Catoosa (Tulsa- Rogers County), OK. Port authorities have been organized to develop public facilities at North Little Rock, Dardanelle-Russellv:lle, Morrilton, Clarksville, Ozark and Van Buren, AR, and Sallisaw, OK. Terminal facilities are in operation or being built at 30 locations in Arkansas and at 25 locations in Oklahoma along the improved waterways. Operations and results during fiscal year. Blue Mountain, Canton, Dardanelle Lock and Dam (No. 10), Dardanelle Marine Terminal, David D. Terry Lock and Dam (No. 6), Elk City, Eufaula, Fall River, Fort Gibson, Keystone, W. D. Mayo Lock and Dam (No. 14), Chouteau Lock and Dam (No. 17), Newt Graham Lock and Dam (No. 18), Robert S. Kerr Lock and Dam and Reservoir (No. 15), Webbers Falls Lock and Dam (No. 16) and Oologah; Locks and Dams Nos. 2, 3, 4, 5, 9, and 13. Markham Ferry, Murray Lock and Dam (No. 7), Nimrod, Norrell Lock and Dam (No. 1), Ozark-Jeta Taylor Lock and Dam (No. 12), Pensacola, Pine Bluff Marine Terminal, Robert S. Kerr Marine Terminal, Tenkiller Ferry, Toad Suck Ferry Lock and Dam (No. 8), Toronto, and Wister were in operation. Construction is complete on bank stabilization. For details of McClellan- Kerr Arkansas River Navigation System and lakes in Oklahoma and Kansas, see report of Tulsa District. Details of McClellan-Kerr Arkansas River Navigation System and lakes in Arkansas are shown on following pages. Condition at end of fiscal year. See Tables 18-H and 18-I, Arkansas River Basin; AR, OK, and KS: Navigation/ Lakes for status for individual items, navigation project, lakes, and basin plan. The overall project is 99 percent complete. Remaining work in this District is the Holla Bend closure structure, rock excavation, Pool 7, land acquisition, and detailed engineering studies of the entrance channel, meander cutoff in the entrance channel, Dam No. 2, and the North Little Rock floodwall and levee. 2. BANK STABILIZATION & CHANNEL RECTIFICATION, AR Location. Several bank stabilization and channel rectification projects are laid out in various reaches extending from fixed point to fixed point on Arkansas River from 33.7 to 362 miles above mouth and across the Arkansas-White cutoff, a 4- to 5-mile natural channel joining Arkansas and White Rivers about 18 and 12 miles above their respective mouths. Existing project. Bank stabilization and channel rectification is a part of McClellan-Kerr Arkansas River Navigation System. For a complete description of reach and location of each bank stabilization and channel rectification project, see the Annual Report FY 81. Total Federal cost to date is $119,300,184 for existing project in Little Rock District. For authorization see Table 18-B, Authorizing Legislation. 3. DAVID D. TERRY LOCK AND DAM (NO. 6), AR Location, existing project, local cooperation, and terminal facilities. See Section 1. Operations and results during fiscal year. Operation and maintenance continued. 18-2 LITTLE ROCK, AR, DISTRICT Condition at end of fiscal year. Construction began in January 1965 and lock and dam was placed in operation in August 1968. 4. LOCK AND DAM NO.2, AR Location, existing project, local cooperation, and terminal facilities. See Section 1. Operations and results during fiscal year. Emergency repairs to the scour protection features and tainter gates at Dam 2 that resulted from the barge accident in December 1982 were completed in FY 85. Operation and maintenance continued. Condition at end of fiscal year. Construction began in May 1963. Lock was placed in operation in April 1967 and dam was placed in operation in March 1968. 5. LOCK AND DAM NO.3, AR' Location, existing project, local cooperation, and terminal facilities. See Section 1. Operations and results during fiscal year. Operation and maintenance continued. Condition at end of fiscal year. Construction began in May 1963 and lock and dam was placed in operation in December 1968. 6. LOCK AND DAM NO. 4, AR Location, existing project, local cooperation, and terminal facilities. See Section 1. Operations and results during fiscal year. Operation and maintenance continued. Condition at end of fiscal year. Construction began in May 1964 and lock and dam was placed in operation in December 196&8. 7. LOCK AND DAM NO. 5, AR Location, existing project, local cooperation and terminal facilitles. See Section 1. Operations and results during fiscal year. Operation and maintenance continued. Condition at end of fiscal year. Construction began in November 1964 and lock and dam was placed in operation in December 1968. & LOACK AND DAM NO. 9, AR Loeation, existing project, local cooperation, and terminal faci1tles. See Section 1. Operations and results during fiscal year. Operation and maintenance continued. Condition at end of fiscal year. Construction began in April 1965 and lock and dam was placed in operation in July 1969. 9. LOCK AND DAM NO. 13, AR Location, existing project, local cooperation, and terminal facilities. See Section 1. Operations and results during fiscal year. Operation and maintenance continued. Condition at end of fiscal year. Construction began in October 1965 and lock and dam was placed in operation in April 1969. Bridge across dam was completed in July 1968. 10. MAINTENANCE AND REPAIR FLEET AND MARINE TERMINALS, AR Location, existing project, local cooperation, and terminal facilities. See Section 1. Operations and results during fiscal year. Operation and maintenance continued. Condition at end of fiscal year. Construction of Pine Bluff Marine Terminal began March 1968 and it was placed in operation in April 1969. Construction of Dardanelle Marine Terminal began June 1968 and it was placed in operation in November 1969. 11. MURRAY LOCK AND DAM (NO. 7), AR Location, existing project, local cooperation, and terminal facilities. See Section 1. Operations and results during fiscal year. Recreation facilities are complete except for cost sharing items under the 710 program. Operation and maintenance continued. Condition at end of fiscal year. Construction began in November 1964 and lock and dam was placed in operation in October 1969. 12. NORRELL LOCK AND DAM (NO. 1) AND ENTRANCE CHANNEL, AR Location, existing project, local cooperation, and terminal facilities. See Section 1. Recommended modification. A Supplement to the General Design Memorandum on the Entrance Channel presenting the results of design and planning studies to modify the existing entrance channel was submitted in June 1981 and approved in August 1981. The recommended modification would consist of construction of additional contraction works to relieve restrictions to navigation in this reach of the waterway during low-flow conditions on the White River and low stages on the Mississippi River. The project is estimated to cost $6 million. Model study of this reach is being tested to determine alternatives. Operations and results during fiscal year. Operation and maintenance continued. Condition at end of fiscal year. Construction began in May 1963 and lock and dam was placed in operation in June 1967. 183 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 13. TOAD SUCK FERRY LOCK AND DAM (NO. 8), AR Location, existing project, local cooperation, and terminal facilities. See Section 1. Operations and results during fiscal year. A dam, spillway, and outlet works for a reservoir was constructed to provide a source of water supply for the city of Conway, AR, to replace the existing source adversely affected by construction of the McClellan-Kerr Arkansas River Navigation System. Estimated cost of the reservoir was $32,944,000. The project was completed and transferred to the city for operation and maintenance in July 1983. The relocation of the roads was completed and transferred to Conway County for operation and maintenance in July 1984. Condition at end of fiscal year. Construction began in July 1965 and lock and dam was placed in operation in November 1969. 14. OTHER AUTHORIZED NAVIGATION PROJECTS See Table 18-C, Other Authorized Navigation Projects. Flood Control 15. LITTLE RIVER BASIN (LITTLE ROCK DISTRICT), AR Location. Improvements are on Little River and tributaries, Arkansas. More definite location of individual items is shown in Table 18-J, Little River Basin. Existing project. Part of a six-lake system for flood control and other purposes in the Little River Basin. The system consists of four lakes in Arkansas: Millwood on the main stem, Dierks on the Saline River, DeQueen on the Rolling Fork River, and Gillham on the Cossatot River, and two lakes in Oklahoma: Broken Bow on the Mountain Fork River and Pine Creek on the Little River. Under a District boundary change, effective in October 1980, the four projects in this system in Arkansas were reassigned from the Tulsa District to the Little Rock District. Local cooperation. Section 2, Flood Control Act of 1938, and Section 301, Water Supply Act of 1958, as amended, apply. Tri-Lakes (DeQueen, Gillham, and Dierks) Water District furnished a resolution of intent to repay costs allocated to water supply storage. The Southwest Arkansas Water District is currently repaying costs allocated to water supply storage at Millwood Lake. Operations and results during fiscal year. Operation and maintenance of projects continued. See individual projects for details. Condition at end of fiscal year. Millwood, DeQueen, Gillham, and Dierks Lakes are complete and in operation. 16. WHITE RIVER BASIN (LITTLE ROCK DISTRICT), AR & MO Location. Improvements are on White River and tributaries, Arkansas and Missouri. More definite location of individual items is shown in Table 18-K, White River Basin. Existing project. A general comprehensive plan for flood control and other purposes in White River Basin. Plan now includes seven lakes, of which two are flood control only projects and five are multiple-purpose projects. Beaver, Table Rock, Bull Shoals, Norfork, Clearwater, Greers Ferry and Bell Foley Lakes were selected and approved for construction by Chief of Engineers, and individual reports on these seven lakes are presented on subsequent pages. Bell Foley Lake was reclassified to inactive in June 1977; reviewed for the purpose of deauthorization and placed in a deferred status in May 1985. Lakes in plan are listed in Table 18-K, White River Basin. For authorization see Table 18-B. Local cooperation. Section 2, Flood Control Act of 1938 applies, Water Supply Act of 1958, as amended, applies to Beaver, Greers Ferry, and Norfork. Operations and results during fiscal year. Operation and maintenance of projects continued. Estimated monetary flood control benefits for fiscal year attributed to Beaver ($2,688,000), Table Rock ($6,504,000), Bull Shoals ($18,710,000), Norfork ($6,322,000), Greers Ferry ($1,677,000), and Clearwater ($16,046,000) lakes totaled $51,947,000. Flood damages prevented by the lakes through September 30, 1985, totaled $226,819,000: Beaver, $14,760,000;, Table Rock, $39,049,000, Bull Shoals, $68,161,000;, Norfork, $23,964,000; Greers Ferry, $16,372,000; Clearwater, $64,513,000. Electric energy delivered to Southwestern Power Administration for marketing during the fiscal year totaled 3,218,349,900 kilowatt-hours: Beaver, 222,538,- 400; Table Rock, 886,034,000; Bull Shoals, 1,397,880,000, Norfork, 396,125,900; Greers Ferry, 315,771,600. Water releases for fish hatcheries were: 28,960 acrefeet from Norfork Lake for Fish and Wildlife Service trout hatchery, 14,480 acre-feet from Table Rock Lake for Missouri Conservation Commission trout hatchery, and 14,480 acre-feet from Greers Ferry Lake for U.S. Fish and Wildlife Service trout hatchery. Withdrawals for water supply purposes were: Beaver Water District, 29,110 acre-feet from Beaver Lake; Water and Sewer Improvement District No. 3 of Mountain Home, AR, 2,099 acre-feet from Norfork Lake; the Community Water System, Cleburne County, AR, and the city of Clinton, AR, 1,890 acre-feet from Greers Ferry Lake. Condition at end of fiscal year. Beaver, Table Rock, Bull Shoals, Norfork, Clearwater, and Greers Ferry Lakes are complete and in operation. Progress on these lakes is in individual reports. Preconstruction planning has been discontinued on Bell Foley. Water Valley and Lone Rock Lakes have been deauthorized. 18-4 LITTLE ROCK, AR, DISTRICT The White River Fish Hatchery authorized by the Water Resources Development Act of 1976 would be located on White River in Carroll County, AR, about 9 miles northwest of the city of Eureka Springs to provide a plan of improvement for construction of trout production facilities including a fish hatchery downstream from Beaver dam. Total estimated cost is $6,000,000. The project was placed in an inactive status in November, 1983. 17. BLUE MOUNTAIN LAKE, AR Location. See Table 18-I, Arkansas River Basin, AR, OK, and KS: Lakes. Existing project. Estimated cost is $5,069,974. For further information see pages 906 and 907 of 1962 Annual Report. For authorization see Table 18-B. Local cooperation. Section 2, Flood Control act of 1938 applies. Operations and results during fiscal year. Operation and maintenance of project continued. Estimated monetary benefits at end of fiscal year attributed to Blue Mountain Lake for prevention of flood damages were $3,080,000 for a total of $18,266,000 through September 30, 1985. Condition at end of fiscal year. Project is complete except for additional recreation sanitary facilities. Construction of project began in May 1940, and it was ready for beneficial use in March 1947. 18. CLEARWATER LAKE, MO Location. See Table 18-K. White River Basin, AR & MO. Existing project. Estimated cost is $11,395,000. For further information see pages 897 and 898 of 1962 Annual Report. For authorization see Table 18-B, Authorizing Legislation. Recommended modification. A reconnaissance report under the Dam Safety Assurance Program was submitted in August 1979 and approved subject to comment in April 1980. The report recommends further planning and design to lengthen the emergency spillway by 350 feet at an estimated cost of $23,200,000 and to continue studies to determine the extent of the underseepage problem and seismic stability. A Feature Design Memorandum, submitted in September, 1983, recommended modification of the spillway and raising the height of the dam. Plans and specifications were prepared in FY 85 for the spillway modification. Local cooperation. Section 2, Flood Control Act of 1938 applies. Operations and results during fiscal year. Operation and maintenance of project continued. Estimated monetary benefits attributed to Clearwater Lake for prevention of flood damages were $16,046,000, for a total of $64,513,000 through September 30, 1985. Releases made from lake during low-water periods were sufficient to supply municipal water for Poplar Bluff and other usages. Condition at end of fiscal year. Project is complete except for addition and improvement to existing sanitary recreational facilities. Construction of project began in June 1940 and was ready for beneficial use in March 1948. 19. DEQUEEN LAKE, AR Location. On Rolling Fork River, river mile 22.8, a tributary of Little River, in Sevier County, about 6 miles northwest of DeQueen, AR. (See Geological Survey map for Chapel Hill, AR, quadrangle, scale 1:24,000.) Existing project. An earthfill dam, 2,360 feet long, constructed to 160 feet above streambed. An uncontrolled spillway, 200 feet wide, is about 1,400 feet east of main embankment. Outlet works consist of a gated conduit, 12 feet in diameter. The lake controls 169 square miles of drainage area and provides a total storage of 136,100 acre-feet (101,200 for flood control storage and 34,900 for conservation and sedimentation reserve). Federal cost of project is $19,623,752. (See Table 18-B for authorizing legislation.) Local cooperation. Section 2, Flood Control Act of 1938, and Section 301, Water Supply Act of 1958, as amended, apply. Operations and results during fiscal year. Routine operation and maintenance continued. Estimated monetary benefits attributed to DeQueen Lake for prevention of flood damages were $214,000 for a total of $4,307,000 through September 30, 1985. Condition at end of fiscal year. Construction began April 1966 and project placed in useful operation in August, 1977. 20, DIERKS LAKE, AR Location. On Saline River, river mile 56.6, a tributary of Little River, about 5 miles northwest of Dierks, Howard County, AR. (See Geological Survey map for Dierks Dam, AR, quadrangle, scale 1:24,000.) Existing project. An earthfill dam, 2,760 feet long, about 153 feet above streambed. An uncontrolled spillway 800 feet wide is in a saddle at west end of dam. Outlet works consisting of a gated 6- by 9-foot oblong conduit, one 24-inch low-flow pipe, and one 30-inch water supply pipe are provided. The lake controls a drainage area of 114 square miles and provides for storage of 67,100 acrefeet for flood control and 29,700 acre-feet for water supply, conservation, and sedimentation reserve, a total of 96,800 acre-feet. Federal cost of project is $16,002,781. (See Table 18-B for authorizing legislation.) Local cooperation. Section 2, Flood Control Act of 1938, and Water Supply Act of 1958, as amended, apply. Operations and results during fiscal year. Routine operation and maintenance continued. A total of 228 acre-feet was made available for water supply for Tri- 18-5 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Lakes Water District. Estimated monetary benefits attributed to Dierks Lake for prevention of flood damages were $108,000, for a total of $2,670,000 through September 30, 1985. Condition at end of fiscal year. Construction began in June 1968. The embankment closure was made on May 8, 1975 and the project placed in useful operation. 21. GILLHAM LAKE, AR Location. Damsite is on Cossatot River, river mile 49.0, in Howard County, about 5 miles northeast of Gillham, Sevier County, AR. (See Geological Survey map for Gillham Dam, quandrangle, AR, quandrangle, scale 1:24,000.) Existing project. For description of completed improvement see Page 19-12 of Annual Report for 1977 (Tulsa District). Federal cost of project is $17,826,703.& (See Table 18-B for authorizing legislation.) Local cooperation. Section 2, Flood Control Act of 1938, and Water Supply Act of 1958, as amended, apply. Tri-Lakes Water District furnished a resolution of intent to repay costs allocated to water supply storage. Operations and results during fiscal year. Routine operation and maintenance continued. A total of 607 acre-feet of water was released from the lake for water supply to Tri-Lakes Water District. Estimated monetary benefits attributed to Gillham Lake for prevention of flood damages for the fiscal year were $241,000, for a total of $4,610,000 through September 30, 1985. Condition at end of fiscal year. Construction began in June 1963. The embankment closure was made on May 8, 1975 and the project placed in useful operation. 22. MILLWOOD LAKE, AR Location. On Little River, river mile 16.0, approximately 7 miles east of Ashdown, Little River County, AR, and about 2 miles northeast of Millwood, Little River County, AR. (See Geological Survey map for Red Bluff, AR, quadrangle, scale 1:24,000.) Existing project. For description of completed improvement and authorizing legislation see Annual Report for 1969 (Tulsa District). Federal cost of project is $46,100,082. (See Table 18-B for authorizing legislation.) Local cooperation. Completed as required. Operations and results during fiscal year. Routine operation and maintenance continued. A total of 49,045 acre-feet of water was released from the lake for water supply to Southwest Arkansas Water District. Estimated monetary benefits attributed to Millwood Lake for prevention of flood damages for the fiscal year were $256,000, for a total of $5,866,000 to September 30, 1985. Condition at end of fiscal year. Construction began in September 1961 and the project was placed in full flood control operation in August 1966. Work required to complete project consists of additional recreational facilities under the cost sharing program. 23. NIMROD LAKE, AR Location. See Table 18-I, Arkansas River Basin, AR, OK, and KS: Lakes. Existing project. Estimated cost is $4,005,627. For further information see pages 908 and 909 of 1962 Annual Report. For authorization see Table 18-B. Local cooperation. Section 2, Flood Control Act of 1938 applies. Operations and results during fiscal year. Operation and maintenance of project continued. Addition and improvement to existing recreation sanitary facilities were continued. Flooding was prevented on an average of 1,978 acres of improved land during fiscal year. Estimated monetary benefits at end of fiscal year attributed to Nimrod Lake for prevention of flood damages were $1,519,000 making a total of $10,284,000 through September 1985. Eighty-five acre-feet of water were withdrawn by the city of Plainview, AR, from Nimrod Lake. Condition at end of fiscal year. Project is complete except for addition and improvement to existing sanitary recreation facilities. Construction of project began in January 1940 and was ready for beneficial use in January 1942. 24. PINE MOUNTAIN LAKE, AR Location. Damsite is at mile 35.7 on Lee Creek and 12 miles north of Van Buren, AR. (See Geological Survey map Rudy NE, AR, quandrangle, scale 1:24,000.) Existing project. Provides for construction of a lake for flood control, water supply, and recreation. The lake would control runoff from 168 square miles. Capacity would be 261,000 acre-feet, of which 93,100 would be for flood control, 168,000 for water supply, fish and wildlife mitigation and recreation. Estimated cost is $71.200,000, of which local interests would repay $50,900,000 for water supply storage. Project was authorized by Flood Control Act of 1965. Local cooperation. Section 2, Flood Control Act of 1938, Water Supply Act of 1958, as amended, and Federal Water Project Recreation Act apply. Operations and results during fiscal year. Preconstruction planning was suspended pending receipt of local assurance for cost sharing. Condition at end of fiscal year. All planning has been suspended. The project has been placed in an inactive status. 25. INSPECTION OF COMPLETED FLOOD CONTROL PROJECTS Approved regulations for operation and maintenance of flood control works, Part 208 of Title 33, Code of Federal Regulations, provide for periodic inspection of completed projects transferred to local interests for operation and maintenance. Inspections of local flood protection projects, shown in Section 26 as completed 18-6 LITTLE ROCK, AR, DISTRICT projects, were made to determine extent of compliance with approved regulations for maintenance and operation of these projects. Responsible officials of improvement districts concerned were advised of inadequacies in maintenance and operation of local flood protection works under their jurisdiction where appropriate. Cost for fiscal year was $58,858. Total cost through September 30, 1985, was $958,350. 26. OTHER AUTHORIZED FLOOD CONTROL PROJECTS See Table 18-E, Other Authorized Flood Control Projects. 27. FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION Emergency streambank protection (Section 14of 1946 Flood Control Act, Public Law 526, 79th Cong). A bank caving problem along the Black River at County Road 607, Butler County, MO, was corrected in FY 85. Two other bank caving problems were investigated under this authority this fiscal year. Work will be accomplished during FY 86. Small navigation projects (Section 107, River and Harbor and Flood Control Act of 1960). The development of two slack water harbors on the Arkansas River at Little Rock and North Little Rock, AR, is being studied. Reconnaissance reports were completed in FY 1985. FY 1985 costs totaled $112,775. Small flood control projects (Section 205, Flood Control Act of 1948, as amended). Two new studies were initiated under this authority during FY 1985. Three appraisal reports were completed during the fiscal year. There were 14 studies in the reconnaissance stage, three projects in the detailed project report (DPR) and plans and specifications stage, and two projects under construction. (For more details, see Table 18-L) A total of $2,164,243 was expended on the Section 205 program in FY 1985. Multiple-Purpose Projects Including Power 28. BEAVER LAKE, AR Location. See table 18-K. White River Basin. Existing project. Estimated cost is $50,797,000. For further information see pages 788 and 789 of 1966 Annual Report. For authorization see Table 18-B. Local Cooperation. Section 2, Flood Control Act of 1938 and Water Supply Act of 1958, as amended, apply. Operations and results during fiscal year. Estimated monetary benefits attributed to the project for prevention of flood damages during FY 85 were $2,688,000 for a cumulative total of $14,760,000 through September 30, 1985. During FY 85, 222,538,400 kilowatt- hours of electric energy were delivered to the Southwestern Power Administration. Condition at end of fiscal year. Project is complete except for addition and improvement to existing recreation sanitary facilities. Construction of project began in October 1959 and was placed in operation for flood control in December 1963, hydroelectric power generation with both units in May 1965, and water supply in January 1966. 29. BULL SHOALS LAKE, AR Location. See Table 18-K, White River Basin, AR & MO. Existing project. Estimated cost with eight generating units is $96,356,000. For further information see pages 725 and 726 of 1965 Annual Report. For authorization see Table 18-B. Local cooperation. Section 2, Flood Control Act of 1938 applies. Operations and results during fiscal year. Operation and maintenance of project continued. Results of operation of Bull Shoals Lake are shown in Section 16. Condition at end of fiscal year. Project is complete except for addition and improvement to existing recreation sanitary facilities. Construction of project began in April 1946 and was ready for beneficial use for flood control in June 1951 and generation of electrical energy in September 1952. Units 1 through 8 were placed in operation September 1952, September 1952, December 1952, June 1953, January 1962, February 1962, August 1963, and September 1963, respectively. 30. DARDANELLE LOCK AND DAM (NO. 30), AR Location. See Table 18-H, Arkansas River Basin; AR, OK, and KS: Navigation. Existing project. Project is a unit of McClellan-Kerr Arkansas River Navigation System. Dam is 2,683 feet long and 68 feet high. It has a spillway with 20 tainter gates 50 feet long and 39 feet high. Navigation lock is 110 by 600 feet with a lift of 54 feet. Powerhouse contains four 31,000 kilowatt generators. Lake has a storage capacity of 486,200 acre-feet. Estimated cost is $86,507,000. (See Table 18-B for authorizing legislation.) Local cooperation. See Section 1. Operations and results during fiscal year. Pool fluctuated within 2-foot power pondage, elevation 336.00 to 338.00. Power generation continued. Installed capacity is 124,000 kilowatts. Delivered 824,610,200 kilowatt hours of electrical energy to Southwestern Power Administration for marketing. Operation and maintenance continued at cost of $3,263,110. Construction of an information center and resident office was completed in FY 85. Condition at end of fiscal year. Project is complete except for addition and improvement to existing recrea- 18-7 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 tion sanitary facilities. Construction began June 1957. Power units were placed on line April, May, and September 1965, and January 1966. Lock was placed in operation in December 1969. Lock was unwatered, inspected, and repaired September 14-23, 1981. 31. GREERS FERRY LAKE, AR Location. See table 18-K, White River, AR & MO. Existing project. Estimated cost is $55,125,000. For further information see page 740of 1964 Annual Report. (See Table 18-B for authorizing legislation.) Local cooperation. Section 2, Flood Control Act of 1938 and Water Supply Act of 1958, as amended, apply. Operations and results during fiscal year. Operation and maintenance continued. Results of operation of Greers Ferry Lake are shown in Section 16. Condition at end of fiscal year. Project is complete except for addition and improvement to existing recreation sanitary facilities. Construction of project began in June 1957, was ready for beneficial use for flood control in January 1962, and power units 1 and 2 were placed in operation in March and May 1964, and water supply was placed in operation in April 1971. The visitors center was completed in June 1984 at a cost of $922,340. 32. NORFORK LAKE, AR Location. See Table 18-K, White River Basin, AR & MO. Existing project. Total estimated cost is $111,624,000, including $38,700,000 for addition of power units 3 and 4, and $40,000,000 for highway bridge construction. For further information see page 896of 1962 Annual Report. (See Table 18-B for authorizing legislation.) Local cooperation. Section 2, Flood Control Act of 1938 and Water Supply Act of 1958, as amended, apply. Operations and results during fiscal year. Operation and maintenance of project continued. Results of operation of Norfork Lake are shown in Section 16. Condition at end of fiscal year. Project is complete except for addition and improvement to existing recreation sanitary facilities, and addition of power units 3 and 4. Construction of project began in October 1940, ready for beneficial use for flood control in June 1943, and for generation of electrical energy with one unit in June 1944. Second unit was added in February 1950. Water supply was added as a purpose in December 1969. Construction of two highway bridges over Norfork Lake to replace ferries was completed in November 1982. The bridges were transferred to the Arkansas Highway and Transportation Department for operation and maintenance in July 1984. 33. OZARK-JETA TAYLOR LOCK AND DAM (NO. 12), AR Location. See Table 18-H, Arkansas River Basin, AR, OK, and KS: Navigation. Existing project. Project is a unit Qf McClellan-Kerr Arkansas River Navigation System. Dam is 2,480 feet long and 58 feet above streambed. It has a spillway with 15tainter gates 50 feet long and 46 feet high. Navigation lock is 110 by 600 feet with a lift of 34 feet. Powerhouse contains five 20,000 kilowatt generators. Lake has a storage capacity of 148,400 acre-feet. In addition, I foot of power pondage is provided in Pool No. 13 between elevations 391.00 and 392.00. Estimated cost is $86,167,000. For authorization see Table 18-B. Local cooperation. See Section 1. Operations and resultsduring fiscal year. Delivered 437,084,300 kilowatt-hours of electrical energy to Southwestern Power Administration for marketing. Continued operation and maintenance. Condition at end of fiscal year. Construction began in December 1964 and is complete. Project is complete except for addition and improvement to existing recreation sanitary facilities. Lock and dam was placed in operation in November 1969. Power units were placed on line as follows: Unit 1, November 1972; unit 2, August 1973; unit 3, October 1973; unit 4, December 1973, and unit 5, May 1974. Work remaining consists principally of modifications to powerplant. 34. TABLE ROCK LAKE, MO Location. See Table 18-K, White River Basin, AR & MO. Existing project. Estimated cost is $71,233,000. For further information see page 893 of 1962 Annual Report. For authorization see Table 18-B. Local cooperation. Section 2, Flood Control Act of 1938 applies. Operations and results during fiscal year. Operation and maintenance continued. Results of operation of Table Rock Lake are shown in Section 16. Condition at end of fiscal year. Project is complete except for addition and improvement to existing recreation sanitary facilities. Construction of project began in October 1954, was ready for beneficial use for flood control in November 1958, and for generation of electrical energy with units 1 and 2 in May 1959. Units 3 and 4 were added in April and June 1961. General Investigations 35. SURVEYS The total costs for the fiscal year were $788,579: special navigation studies (Arkansas River and Tributaries Hydropower Studies and Arkansas River Basin), $186,429; flood damage prevention studies (White River Basin Lakes, Clarksville, AR, Fort Smith-Van Buren, AR, and County Line, MO), $237,207; comprehensive basin studies (White River Basin, AR and MO), $123,436; review of completed projects (Village Creek, Taylor Bay), $123,165; special investigations $37,784; planning 18-8 LITTLE ROCK, AR, DISTRICT assistance to states and other agencies, $80,55&8 36. COLLECTION AND STUDY OF BASIC DATA Costs for these services for the fiscal year were $243,002. Flood plain management services (FPMS). The FPMS program is under Section 206 of the 1960 Flood Control Act, PL 86-645, as amended. Through technical services and planning guidance, the program encourages comprehensive flood plain management planning at all levels to reduce the potential for losses to life and property from floods. Federal and non-Federal agencies and the private sector are assisted with planning and development information for flood hazard areas. This assistance is in the form of local flood plain regulations, Federal Insurance Program requirements, and Executive Order 11988 guidelines. Such assistance may include factual flood information (available or determined) and interpretation on flood frequencies, extent of flooding, flood-water velocity, duration of flooding and floodway limits. Services accomplished during fiscal year: Technical services and planning guidance responses furnished totaled 10,100. This total included services to Federal and non-Federal agencies, individuals, realtors, corporations, lending institutions, engineers, architects, and others. Costs for providing these services during FY 1985 totaled $238,072. Hydrologic studies. During the fiscal year, 108 stations were operated, 76 cooperatively with USGS and 32 by the Corps. The total cost for streamflow and some sediment data from all sources of funding for FY 1985 was $515,160, of which $385,160 was transferred to USGS. The District also participated in a cooperative program with National Weather Service for rainfall and/or river reporting stations for use in forecasting streamflow for flood warning and operation of lake projects. Records were also collected at certain hydroclimate rainfall stations under a cooperative program between the two agencies. For these services, $34,975 was transferred to the National Weather Service. 37. CONTINUATION OF PLANNING AND ENGINEERING During this fiscal year, a total of $683,107 was expended: Fourche Bayou - vicinity of Little Rock, AR ($659,720), and North Little Rock (Dark Hollow), AR ($23,388). 18-9 TABLE 18-A REPORT OF THE CHIEF OP ENGINEERS, U.S. ARMY 1985 COST AND FINANCIAL STATEMENT1 2 See Section Total to in Text Project Funding FY 82 FY 83 FY 84 FY 85 Sept. 30, 1985 1. Arkansas River Basin, Ark., Okla., & Kans. 2 Bank Stabilization & Channel Rectification, AR 3-13. Navigation Locks & Dams, AR 15. Little River Basin, (Little Rock Dist.) 16. White River Basin (Little Rock District) New Work Approp. ams Navigation Cost Dams Navigation Maint. Approp. Dams Navigation Cost Dams Navigation Rehab. Approp. Cost. New Work Contrib. Cost Spial Funds ot Other Contrib. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Contrib. Cost. Other Contrib. Cost New Work Approp. Cost Maint. Approp. Costp New Work Approp. Cost Maint. Approp. Cost $ 9,614,000 253,000 9,361,000 7,508,211 121,201 7,387,010 38,403,821 9,036,800 29,367,021 35,266,411 7,967,122 27,299,289 9,310,000 7,365,152 11,132,201 11,119,636 205,000 40,526 3,170,520 2,968,342 12,195,000 11,342,114 16,732,380 15,456,133 $ 2,872,052 138,052 2,734,000 5,024,761 120,404 4,904,357 42,620,015 9,051,008 33,569,007 42,359,344 9,316,208 32,998,136 2,652,000 4,868,815 14,043,848 13,179,192 122,753 3,370,900 3,175,154 2,601,500 2,390,010 17,974,850 18,315,445 $ 2,144,000 -72,000 2,216,000 2,456,752 71,746 2,385,006 40,244,566 8,849,697 31,394,869 42,894,970 8,881,670 34,013,300 2,220,000 2,331,168 13,711,000 15,282,239 -2,700 56,371 3,513,000 4,181,253 20,700 936,207 15,455,000 16,641,871 3,450,0 3,450,0 2,464,2 7,3 2,456,9 52,292,4 10,730,5 41,561,9 53,144,2 10,637,8 42,506,3 2,600,0 2,419,2 15,996,0 16,019,1 3,539,5 3,577,9 28897 16,366,5 16987599 00 $1,460,235,127 - 150,318,533 00 1,309,916,594 83 1,458,394,990 66 150,279,504 17 1,308,115,486 56 548,181,8793 00 121,377,5903 156 426,804,2893 41 545,400,9013 199 120,309,3493 42 425,091,5523 - 291,106 - 291,106 - 1,609,842 - 1,609,842 - 19,926,755 - 19,926,755 - 531,336 - 531,336 - 119,300,184 - 119,300,184 - 4,561,666 - 4,561,666 )00 421,529,473 !72 420,631,856 )00 174,966,802 97 174,306,647- - 973,385 - 963,567 - 531,336 - 531,336 - 99,959,850 335 99,543,257 00 31,000,280; )91 30,539,573" - 335,031,873 '99 334,589,364 00 219,305,479; )75 218,959,219; 18-10 LITTLE ROCK, AR, DISTRICT TABLE 18-A (Continued) COST AND FINANCIAL STATEMENT'2 See Section in Text Project Funding FY 82 FY 83 FY 84 Total to FY 85 Sept. 30, 1985 17. Blue Mountain Lake, AR 18. Clearwater Lake, MO 19. DeQueen Lake, Little River Basin, AR 20. Dierks Lake, Little River Basin, AR 21. Gillham Lake, Little River Basin, AR 22. Millwood Lake, Little River Basin, AR 23. Nimrod Lake, AR 24. Pine Mountain Lake, AR 28. Beaver Lake, AR 29. Bull Shoals Lake, AR New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New York Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost 755,400 621,400 659,376 642,803 53,000 - 3,469 49,781 1,485,000 1,520,100 1,308,667 1,632,220 85,000 12,000 3,322 92,539 671,180 576,200 585,951 623,408 71,000 -12,000 26,415 19,388 496,520 613,500 542,477 468,756 4,000 - 10,789 361 529,260 527,700 421,892 473,013 32,300 - - 10,465 1,474,560 1,653,500 1,418,022 1,609,977 25,000 - 1,228 23,623 652,260 772,200 589,633 790,927 43,000 -16,500 9,834 10,675 1,744,120 2,415,650 1,725,379 2,295,790 1,100 - 3,630 385 4,300,480 4,656,300 3.640.569 4.813.600 18-11 - - 5,069,974 - - 5,069,974 627,000 656,000 9,196,2943 675,029 652,016 9,176,2813 - - 10,453,403 - - 10,440,204 1,469,000 1,342,000 19,116,5223 1,633,639 1,366,720 19,126,6883 -1,100 - 19,629,753 37 - 19,623,752 515,000 671,000 4,299,030; 585,145 674,275 4,274,6223 - - 16,002,904 14,770 195 16,002,781 510,000 685,000 4,856,703; 595,000 721,135 4,820,4293 -1,600 - 17,827,111 2,006 - 17,826,703 495,000 626,000 3,804,485& 642,099 574,264 3,726,8523 - - 46,087,382 39,558 7,640 46,090,021 1,993,000 1,557,500 17,540,062- 2,358,113 1,608,317 17,717,670 - - 4,092,826 147 - 4,005,627 705,000 812,000 10,546,738 ' 747,627 820,871 10,536,3643 - - 1,432,331 - - 1,432,331 -4,300 - 46,183,033 3,933 4,039 46,112,072 2,200,000 2,555,500 28,130,8293 2,326,174 2,563,211 28,051,7543 - - 88,858,711 - - 88,858,707 3,386,000 3,889,500 45,154,7533 3.625.680 4,210.600 49.665.345 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 18-A (Continued) COST AND FINANCIAL STATEMENT',2 See Section Total to in Text Project Funding FY 82 FY 83 FY 84 FY 85 Sept. 30, 1985 30. Dardanelle Lock New Work & Dam (No. 10), Approp. - - - - 84,270,124 AR Cost - - - - 84,261,240 Maint. Approp. 2,825,600 3,027,056 3,198,000 3,541,000 39,694,869 Cost 2,799,419 2,939,073 3,372,791 3,575,685 39,627,294; 31. Greers Ferry New Work Lake, AR Approp. 77,000 - - - 48,865,512 Cost 1,290 77,853 - - 48,865,512 Maint. Approp. 3,537,620 3,554,700 3,061,000 3,197,500 38,912,5383 Cost 3,346,252 3,710,151 3,230,760 3,256,122 38,818,8033 32. Norfork Lake, New Work AR Approp. 11,959,000 2,618,000 25,000 - 70,997,929 Cost 11,288,966 2,231,986 847,235 - 70,555,810 Maint. Approp. 2,501,300 2,544,900 2,264,000 2,238,500 36,914,5913 Cost 2,651,245 2,572,873 2,394,031 2,310,590 36,748,7163 33. Ozark-Jeta Taylor New Work Lock & Dam (No. Approp. 2,000 - - - 85,629,412 12), AR Cost - 10,532 89 - 85,629,412 Maint. Approp. 3,104,180 3,823,256 2,923,000 2,608,000 33,296,4783 Cost 4,202,056 3,771,288 3,537,134 2,839,221 33,243,8603 34. Table Rock New Work Lake, MO Approp. 39,000 - - - 67,224,000 Cost - 19,330 - - 67,224,000 Maint. Approp. 3,163,860 3,283,200 3,075,000 3,143,500 46,583,7653 Cost 2,906,521 3,294,812 3,431,587 3,168,732 46,535,0343 1. For more details on project funds, see text for individual projects. 23. F.or distribution of Jobs Bill funds, see Table 18-M. Beginning this fiscal year, data shown in Table 18-A includes special recreation use fees. Data for previous fiscal years have been changed to conform to the new procedure. 18-12 LITTLE ROCK, AR, DISTRICT TABLE 18-B AUTHORIZING LEGISLATION Acts Work Authorized Documents ARKANSAS RIVER BASIN, AR, OK, & KS (See Section 1 of Text) Approved General comprehensive plan: Mannford Reservoir, OK Oologah Lake, OK Canton Lake, OK Tenkiller Ferry Lake, OK Wister Lake, OK Blue Mountain Lake, AR Nimrod Lake, AR Flood Control Com. Doc. 1, 75th Cong., 1st sess. Modified comprehensive plan to include reservoirs in Grand (Neosho) River Basin, OK, and MO, and in Verdigris River Basin: Markham Ferry Reservoir, OK Fort Gibson Lake, OK Pensacola Reservoir Lake O' The Cherokees, OK Fall River Lake, KS Elk City Lake, KS Toronto Lake, KS Neodosha Lake, KS Authorized Chief of Engineers to provide in the Canton Lake 69,000 acre-feet of irrigation storage, subject to certain conditions. H. Doc. 107 and 440, 76th Cong. 1st sess. H. Doc. 758, 79th Cong., 2d sess. Approved multiple-purpose plan: Oologah Lake, OK Markham Ferry Reservoir, OK Fort Gibson Lake, OK Blackburn Reservoir, OK Mannford Reservoir, OK Taft Reservoir, OK Bank stabilization Dardanelle Lock and Dam, AR Eufaula Lake, OK Navigation locks and dams Ozark Lock and Dam, AR Short Mountain Lock and Dam, OK Webbers Falls Lock and Dam, OK Tenkiller Ferry Lake, OK June 30, 1948 May 17, 1950 July 14, 1960 Modified Arkansas River navigation comprehensive plan to include bank protection works at Bradens Bend, OK. Modified comprehensive plan authorized in 1938 Flood Control Act and multiple-purpose plan authorized in River and Harbor Act of 1946 to provide for substituting Keystone Lake for Mannford, Blackburn and Taft Reservoirs. Authorized incorporation of River and Harbor and Flood Control plans into a single plan of development and made all previous authorizations applicable to combined plan of development. S. Doc. 107, 81st Cong., 1st sess. 'Pine Mountain Dam and Lake authorized for construction. H. Doc. 270, 89th Cong., Flood Control Act of 1965 (Title II, Public Law 89-298) 18-13 June 28, 1938 August 18, 1941 July 24, 1946 July 24, 1946 1965 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 18-B (Continued) AUTHORIZING LEGISLATION Acts Work Authorized June 22, 1936 December 22, 1944 October 27, 1965 June 28, 1938 August 18, 1941 September 3, 1954 1960 October 23, 1962 March 1, 1974 October 22, 1976 June 22, 1936 July 14, 1960 October 23, 1962 July 24, 1946 July 3, 1958 LITTLE ROCK LEVEE, AR (EAST END-FOURCHE BAYOU Levees to provide flood protection to people and city property. Modified local flood protection project to raise grade and protect additional areas. Authorized 45,000 g.p.m. pump station and excavated storage area of 164 acre-feet WHITE RIVER BASIN (LITTLE ROCK DISTRICT) (See Section 16 of Text) Approved comprehensive plan for White River Basin: LColenaer wRaotcekr Lake, AR, Norfork Lake, AR, Lake, MO, Water Valley Lake, AR, Bell Foley Lake, AR, Greers Ferry Lake., AR, and White River emergency. Modified comprehensive plan to include Bull Shoals Lake, AR, and MO, Table Rock Lake, MO, and AR, and Norfork Lake, AR, and MO (power). Authorized power in Greers Ferry Reservoir and added Beaver Lake to the plan. Jacksonport State Park in Jackson County, Arkansas. Improvements along the White River for recreation and navigation and the protection of the park which is historically significant. Authorizing clearing and straightening of channel for Village Creek, Jackson and Lawrence Counties. Authorizing highway bridge construction across Norfork Lake. White River Fish Hatchery, Arkansas provides for trout production facilities downstream from Beaver Dam. VILLAGE CREEK, WHITE RIVER, AND MAYBERRY LEVEE DISTRICT, AR Approved levee protection. Modified existing project to add interior drainage in accordance with plan I, and directed study of plan III. Modified project to provide a pumping plant. RED RIVER BELOW DENISON DAM INCLUDING LITTLE RIVER BASIN, OK AND AR (See Section 15 of Text) Construct Boswell, Hugo, and Millwood Lakes, and Bank Stabilization. Modified Millwood: Construct Pine Creek, Lukfata, Broken Bow, DeQueen, Gillham, Dierks Lakes H. Doc. 308, 74th Cong., 1st sess. H. Doc. 447, 78th Cong., 2d sess. S. Doc. 55, 89th Cong., 1st sess. Flood Control Com. Doc. 1, 75th Cong., 1st sess. H. Doc. 917, 76th Cong., 3d sess. H. Doc. 290, 77th Cong., 1st sess. H. Doc. 499, 83d Cong. 2d sess. River and Harbor Act of 1960 as amended Section 107 H. Doc. 352, 87th Cong., 2d sess. Flood Control Com. Doc. 1, 75th Cong., 1st sess. Water Resources Development Act of 1976, P.L. 94-587, Sec. 105 H. Doc. 102, 73d Cong., '1st sess. H. Doc. 225, 86th Cong., 1st sess. H. Doc. 577, 87th Cong. 2d sess. H. Doc. 602, 79th Cong., 2d sess. H. Doc. 170, 85th Cong., 1st sess 18-14 Documents LITTLE ROCK, AR, DISTRICT TABLE 18-C OTHER AUTHORIZED NAVIGATION PROJECTS For Last Cost to Sept. 30, 1985 Full Report See Annual Operation and Project Report For Construction Maintenance Black River, AR, and MO 1 1950 $ 80,000 $ 930,324 Current River, AR, and MO ' 1964 17,0002 132,178 Upper White River, AR 3 4 1952 813,197 1,788,374 White River, AR, (above Peach Orchard Bluff) 5 1950 - 785,666 1. Channel adequate for existing commerce. Completion not contemplated. 2. Includes $7,000 for previous project. 3. Federal operation and maintenance terminated June 30, 1952, due to lack of commerce. Facilities at Locks and Dams Nos. 1, 2, and 3 disposed of in accordance with authority in Public Law 996, 84th Cong. 4. Completed. 5. Responsibility for maintenance of project downstream from Newport, AR, transferred to Memphis District in FY 62. 18-15 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 18-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS For Last Cost to Sept. 30, 1985 Full Report See Annual Opration and Project Status Report For Construction Maintenance Bell Foley Lake, White River, AR' Inactive 1975 $1,407,116 - Black River, Poplar Bluff, MO, to Knobel, AR Completed 1958 584,315 - Carden's Bottom Drainage District No. 2, Arkansas River, AR Completed 1951 919,955 - Clarksville, AR Completed 1962 271,717 - Conway County Drainage and Levee District No. 1, Arkansas River, AR Completed 1959 187,440 - Conway County Levee Districts Nos. 1, 2, and 8, Arkansas River, AR Completed 1952 1,018,840 - Conway County Levee District No. 6, Arkansas River, AR Completed 1952 390,952 - Crawford County Levee District, Arkansas River, AR Completed 1954 2,001,820 - Crooked Creek, Lake and Levee, AR2 Inactive 1969 - - East Poplar Bluff and Poplar Bluff, MO Completed 1958 304,699 - Faulkner County Levee District No. 1, Arkansas River, AR Completed 1941 99,511 - Fort Smith, Arkansas River, AR Completed 1951 1,077,546 - From North Little Rock to Gillett, AR (above Plum Bayou) Completed 1954 845,300 - Fourche Creek, Little Rock, AR -1973 22,890 - Little Rock Levee, AR, East End Fourche Bayou -1975 1,901,899 - McLean Bottom Levee District No. 3, Arkansas River, AR Completed 1950 422,549 - Near Dardanelle, Arkansas River, AR Completed 1953 198,069 - Newport, White River, AR Completed 1941 314,276 - North Little Rock, Arkansas River, AR Completed 1958 512,001 - Petit Jean River, AR Completed 1966 84,350 - Roland Drainage District, Arkansas River, AR Completed 1950 269,907 - Skaggs Ferry, Black River, AR Completed 1941 81,023 - South Bank Arkansas River (Head Fourche Island to Pennington Bayou), AR Completed 1964 1,404,852 - South Bank, Arkansas River, Little Rock to Pine Bluff, AR, Tucker Lakes Completed 1961 409,115 - Van Buren, Arkansas River, AR Completed 1952 438,222 - Village Creek, White River, and Mayberry Levee Districts, AR3 1972 1,567,156 - Village Creek, Jackson and Lawrence Counties, AR' Inactive 1977 510,217 - West of Morrilton, Arkansas River, AR Completed 1962 1,269,959 - 1. Reclassified as inactive in June 1977. . 3. See H Doc. 577, 87th Cong., 2d sess., for description of 2. Recommended to continue in deferred category in project. August 1977. 4. Authorized by Chief of Engineers. 18-16 LITTLE ROCK, AR, DISTRICT TABLE 18-G DEAUTHORIZED PROJECTS For Last Funds Expended Full Report See Annual Date Federal Contributed Project Authority Report For Deauthorized Funds Funds Lone Rock, Buffalo River, AR 1938 FCA - 1977 Water Valley, Eleven Point River, AR & MO 1983 FCA - 1977 18-17 TABLE 18-H ARKANSAS RIVER BASIN; AR, OK, AND KS: NAVIGATION (See Section 1 of Text) Miles Elevation Char- Year Up- U r Depth on Miter ater Opened stream Lock of Kind to Total from Miles to Dimension Lift (feet, Upper Lower Founda- of Type of Navi- Estimated Feature Mouth - Nearest Town (feet) (feet) MSL) (feet) (feet) tion Dam Construction gation Cost I LEROCK DISTRICT Norrell L&D No. 1 Lock No. 2 Dam No. 2 LAD No. 3 LAD No. 4 L&D No. 5 David D. Terry L&D No. 6 Murray LAD No. 7 Toad Suck Ferry LAD No. 8 LAD No. 9 10.3 13.3 40.5 50.2 66.0 86.3 108.1 125.4 155.9 8 east of Arkansas Post, AR 6 east of Arkansas Post, AR 3 southeast Arkansas Post, AR 5 north of Grady, AR 7 east of Pine Bluff, AR 4 southeast of Redfield, AR 12 southeast of Little Rock, AR 6 northwest of Little Rock, AR 6 west of Conway, AR 176.9 3 southwest of Morrilton, AR 110 by 600 110 by 600 110 by 600 110 by 600 110 by 600 110 by 600 110 by 600 110 by 600 30 max. 20 nom. 28 max. 20 14 17 18 18 16 142 162 182 196 213 231 249 265 110 by 600 19 -287 16 18 18 18 18 18 18 18 15 14 14 14 14 14 14 14 Piles in sand Piles in sand Piles in sand Piles in sand Piles in sand Clay Piles in sand Shale Shale Fixed overflow Movable Movable Movable Movable Movable Movable Movable Concrete Gsaptielldw caoyn cwreitthe embankint ends Gated concrete spillw with embankment ends Gated concrete sepmilblwa n witth ends Gated concrete spillway with embankment ends Gated concrete spillway with embankment ends Gated concrete spillway with embankment ends Gated concrete spillway with eenmdbsankment 18 14 Shale Movable Gated concrete spillway with eenmdbsankment 1967 1967 1968 1968 1968 1968 1968 1969 1969 1969 $34,265,000 43,869,000 33,791,000 40,831,000 29,568,000 62,585,000 37,492,000 56,912,000 34,357,000 0 0 10 tl I-' P" C-- No I TABLE 18-H (Continued) ARKANSAS RIVER BASIN; AR, OK, AND KS: NAVIGATION (See Section 1 of Text) Mile Elevation Char- Year Up U r pton Mi acter Opened lock - of Kind to Total frm Miles t.o Dhnsion Ifft (feet, Upper Lower Founda- of Tpe of Nvi- Estim ated Feature Mouth - Nearest Town (feet) (feet) MSL) (feet) (feet) tion Dam Conruction ation Cost Drdanelle 20.5 2 northwest of 110 by 600 54 338 18 14 Movable Sandstone Gated conrete 199 $84270124 DL No. 1U IAD No. 11 OzsrkJeta Talor IAD (No. 12) IAD No. 13 TULSA DISTRICTx IAD No. 13 (part) W. D.Mayo IAD No. 14 Robert S. Kerr IAD No. 15 Webbers Falls IAD No. 16 Chouteau LAD No. 17 Newt Graham IAD No. 18 LDrcanelle, AK Deleted 1 east of Ozark, AR 7 east of Fort Smith, AR ..- 4 east of Redland, OK 1 north of Cowlington, OK 1 northwest of Gore, OK 4 northwest of Okay, OK 8 southwest of Inola., OK 110 by 600 110 by 600 110 by 600 110 by 600 110 by 600 110 by 600 111100 bbyy 660000 34 20 20 48 30 21 21 370 392 412 460 490 511 532 18 18 14 18 19 15 15 15 14 15 14 16 14 14 Sandstone and shale Sandstone and shale Rock Rock Rock Rock Rock em t ends Movable Gated concrete esmpi llwa kweitth ends Movable Gated concrete spilway with ends Movable Gsaptielldw acoyn, cwreitthe embankment ends Movable Gated concrete spillway with embankment ends Movable Gated concrete spillway with embankment ends Movable Gated concrete I is spillway it emban nnt ends Movable Gated concrete spiw with eenmd s t 1969 1969 1970 1970 1970 1970 1970 1970 85,629,412 46,187,000 6,858,000 32,655,000 94,578,237 83,738,277 31,619,000 44,355,000 0 OE A Co, xE 0 2E co a 256.8 29L8 319.6 336.2 366.6 401.4 421.6 I I TABLE 18-H (Continued) ARKANSAS RIVER BASIN; AR, OK, AND KS: NAVIGATION (See Section 1 of Text) Additional features entering into cost of project Little Rock District:- Bank stabilization and channel rectification, mile 33.7 to 362 and Arkansas-White Cutoff, 100 per cent complete ............... $119,300,184 Maintenance and repair fleet and marine terminals, 99 per cent complete ....................................... 7,500,000 Total, Little Rock District ................................ 716,556,720 Navigation aids (US Coast Guard) ............................ 2,268,000 Tulsa District: Bank stabilization and channel rectification, Short Mountain to Fort Smith, complete .................................... 12,700,038 Maintenance and repair fleet and marine terminals, complete .................................................. 2,750,000 Subtotal ................................................ $309253,552 Upstream Lakes: Oologah, 90.2 miles upstream from mouth, Verdigris River complete ................................................ $ 46,722,329 Keystone, 638.8 miles upstream from mouth, Arkansas River, complete ................................................ 123,171,173 Eufaula, 27 miles upstream from mouth, Canadian River, complete ............................................. 122,680,747 Subtotal ............................................... 292,574,249 Total, Tulsa District.................................... 601,827,801 Total Project Cost 99.8 percent complete ............... $1,318,384,521 0A x C tl cE TABLE 18-I ARKANSAS RIVER BASIN; AR, OK, AND KS: LAKES (See Section 1 of Text) Miles Drainage HReservoir POwer Year or Ttal Above Area of Capacity Development rcent Eimatd Lake and State River Mouth Nearest Town (sq mi) (feet) Type (acre-feet) (kiwatis) Complete Cost Blue Mountain, AR Petit Jean 74.4 Paris, AR 488 115 Earthfill 257,900 - 1947 $ 5,069,974 Canton, OK North Canadian 384.3 Canton, OK 12,483 68 Earthfill 383,300 - 1948 11,209,834 Elk City KS Elk 8.7 Independence, KS 634 (Table Mound) 107 Earthfill 284,300 - 1966 19,062,990 Eufaula, OK I2' Canadian 27.0 Eufaula, OK 47,522 114 Earthfill 3,798,000 90,000 1964 122,680,747 Fall River, KS Fall 54.2 Fall River, KS 585 94 Earthfill 256,400 - 1949 10,550,873 Fort Gibson, OK 17 Grand (Neosho) 7.7 Fort Gibson, OK 12,492 110 Concrete-gravity 1,284,400 45,000 1963 4,713,78 Keystone, OK1 2 3 Arkansas 538.8 Sand Springs, OK 74,506 121 Earthfill 1,886,500 70,000 1964 128,171,173 Markham Ferry, OK' 4 Grand (Neosho) 47.4 Pryor, OK 11,533 90 Earthfill 444,500 100,000 1968 6,908,756 Neodesha, KS" Verdigris 222.8 Neodesha, KS 1,152 74 Earthfill 90,000 - 0 97,910 Nimrod, AR Fourche La Fave 62.6 Plainview, AR 680 103 Concrete-gravity 336,010 - 1942 4,092,826 Oologah, OK2 Verdigris 90.2 Claremore, OK 4,339 137 Earthfill 1,519,000 - 1974 46,722,829 Pensacola, OK' S Grand (Neosho) 77.0 Disney, OK 10,298 147 Concrete arch 2,197,000 86,400 1940 52,126 Tenkiller Ferry, OK' Illinois 12.8 Gore, OK 1,610 197 Earthfill 1,230,800 34,000 1963 24,115,719 Toronto, KS Verdigris 271.5 Toronto, KS 730 90 Earthfill 199,700 - 1960 13,896,324 Wister, OK Poteau 60.9 Wister, OK 993 99 Earthfill 427,900 - 1949 10,501,226 Subtotal, exclusive of Eufaula, Keystone, and Oologah, 93 percent complete 149,261,936 Total, Arkansas River Basin, 98 percent complete 1,467,646,457 1. Project includes facilities for production of hydroelectric power. 2. Cost included in navigation project. 3. Estimate includes Code 710 funds. 4. Constructed by State of Oklahoma under the name of Robert S. Kerr Dam (Lake Hudson). Estimate shown is for Federal participation. 5. Inactive. Estimate is based on 1954 price levels. 6. Constructed by State of Oklahoma under the name Grand River Dam (Lake O' The Cherokees). Estimate shown is for Federal participation. 7. Estimate includesCode 710funds and presentestimate cost of power units. e s0 TABLE 18-J REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 LITTLE RIVER BASIN AR: LAKES (See Section 15 of Text) Project River Site' Nearest Town DeQueen Lake' Rolling Fork River 22.8 DeQueen, AR Gillham Lake' Cossatot River 49.0 Gillham, AR Dierks Lake' Saline River 56.6 Dierks, AR Millwood Lake' Little River 16.0 Millwood, AR 1. Project is reported separately herein. 18-22 TABLE 18-K WHITE RIVER BASIN; AR, AND MO: LAKES (See Section 16 of Text) Miles Drainage Reservoir Pwer Total Above Area Height of Dam Above Streambed Capacity Developmnt Estimated Lake River Mouth Nearest Town (sq mi) and Type (acre-feet) lowatts) Cost- Beaver2 White 609.0 Eureka Springs, AR 1,186 228 feet concretegravity and earthfill 1,952,000 112,000 $ 50,797,000 Bell Foley3 Strawberry 27.2 Poughkeepsie, AR 519 136 feet concrete-gravity and earthfill 518,000 - 98,700,000 Bull Shoals2 White 41&6 Mountain Home, AR 6,036 258 feet concrete-gravity 5,408,000 340,000 96,356,000 Clearwater2 Black 257.4 Piedmont, MO 898 154 feet earthfill 413,000 - 11,395,000 Greers Ferry2 Little Red 79.0 Heber Springs, AR 1,146 243 feet concrete-gravity 1,844,000 96,000 55,125,000 Norfork2 North Fork 4.8 Norfork, AR 1,806 216 feet concrete-gravity 1,983,000 80,550 111,624,000 Table Rock2 White 523.8 Branson, MO 4,020 252 feet concrete-gravity and earthfill 3,462,000 200,000 71,233,000 Total 1,580,000 828,550 490,230,000 1. Current FY price levels unless otherwise noted. 2. For details of this project, see individual report. 3. Inactive-placed in a deferred status in May 1985 Estimate based on 1982 price levels. I A REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 18-L FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION (Section 205, PL 858, 80th Cong., as amended (Preauthorization) (See Section 27 of Text) Total Costs Study Identification Initiation Status Completion FY 85 through Date Date Costs Sept. 30, 1985 Bentonville, Southeast AR' Aug 1983 Appraisal *Apr 1984 $ 7,500 $ 7,500 Black River, South Poplar Bluff, MO' Aug 1983 Recon' *Oct 1985 30,314 144,000 Black River, Leeper, MO' Aug 1983 1 *Aug 1983 - 7,500 Blossom Way Creeks, Rogers, AR' Aug 1983 Recon' *Sep 1985 45,803 112,239 Clear Creek, Washington Co., AR' Sep 1983 ' *Sep 1983 - 5,777 Crooked & Dry Jordan Creeks, Harrison, AR Aug 1983 Recon Mar 1986 54,414 68,843 Holly & Dierks Creeks, Dierks, AR Aug 1983 Recon May 1986 19,474 19,474 Howell Creek & Tributaries, West Plains, MO Sep 1982 DPR' *Sep 1985 21,448 250,027 Hurricane Creek, Ashdown, AR Sep 1983 Recon Jul 1986 16,520 16,520 Kelley Creek, Monett, AR Sep 1983 Recon Feb 1986 20,184 38,615 Little Massard Creek, Fort Smith, AR2 Sep 1983 Construction *Jun 1984 1,138 90,622 Little Red River Tributaries, Clinton, AR Feb 1983 Construction May 1987 777,627 1,066,337 Logan & Dickson Creeks, Ellington, MO3 Feb 1983 DPR Feb 1985 8,421 145,000 McKenzie Creek, Piedmont, MO Sep 1983 Recon *Sep 1985 55,045 63,331 Mill Spring, MO' Aug 1983 ' *Aug 1983 - 7,500 Mine & Dodson Creeks, Nashville, AR Jan 1983 Recon Jan 1986 66,613 84,005 Newport, Eastside Drainage, AR' Dec 1982 ' *Dec 1982 - 4,000 Otter Creek & Trib., Shannon Hills, AR Sep 1983 Construction *Jun 1985 26,350 250,976 Pike Creek, Poplar Bluff, MO' Feb 1983 DPR' *Mar 1985 14,708 179,389 Polk Bayou, Batesville, AR Jan 1983 ' *Jun 1983 - 7,500 Prairie Creek, Russellville, AR Nov 1983 Recon *May 1985 - 55,964 Rose City, North Little Rock, AR' Sep 1983 ' *Sep 1983 - 7,500 Spring River, Hardy, AR' Aug 1983 Appraisal *Jun 1984 6,600 6,600 Sulphur Creek, Heber Springs, AR Aug 1983 Appraisal *May 1984 - 7,200 Tributary 2, Bentonville, AR Mar 1983 Recon *Feb 1985 4,968 101,961 White River, Batesville, AR Aug 1983 DPR Jan 1986 32,649 100,440 White River, Jacksonport, AR Sep 1983 Construction Oct 1986 864,801 1,182,645 White River, Norfork, AR' Mar 1983 1 *Apr 1983 - 4,000 Lost & Little Lost Creeks, Seneca, MO 3 Aug 1983 DPR *Apr 1985 3,542 75,000 Cloverdale Drain, Little Rock, AR Dec 1983 Recon *Aug 1985 63,109 63,109 Piney and Tucker Creeks, Alton, MO Jun 1984 Recon *Aug 1985 - - Jam Up & Tributary A, Mountain View, MO Jun 1984 Recon Feb 1986 - - Current River & Tributary A, Van Buren, MO Jun 1984 Recon Dec 1986 8,280 8,280 Caney Bayou, Whitehall, AR' Jun 1984 Appraisal' *Mar 1985 7,500 7,500 Tucker Creek, Conway, AR Sep 1984 Appraisal *Aug 1985 - - Mayflower, AR' y Apr 1985 Appraisal' *Aug 1985 - - White River, St. Paul, AR Aug 1985 Appraisal Dec 1985 -- *Accomplished. 1. No further studies recommended. 2. Project evolved from the Fort Smith/Van Buren general investigation study. 3. City unable to provide assurances. 18-24 LITTLE ROCK, AR, DISTRICT TABLE 18-M JOBS ACT (P.L. 98-8, March 24, 1983) Total through Project Funding FY 83 FY 84 FY 85 95 McClellan-Kerr Arkansas River Navigation System (Little Rock Maint. District) Approp. $1,048,200 - - $1,842,000 Cost 1,037,700 $793,800 - 1,842,000 Dardanelle Lock & Dam, Arkansas River Basin, Arkansas Maint. Approp. 159,000 - - 159,000 Cost 89,800 69,200 - 159,000 Ozark-Jeta Taylor Lock & Dam, Arkansas River Basin, Arkansas Maint. Approp. 139,000 - - 139,000 Cost 139,000 - - 159,000 Blue Mountain Lake, Arkansas River Basin, Arkansas Maint. Approp. 37,400 - - 37,400 Cost 34,600 2,800 - 37,400 Nimrod Lake, Arkansas River Basin, Arkansas Maint. Approp. 45,000 - - 45,000 Cost 45,000 - - 45,000 Beaver Lake, White River Basin, Arkansas Maint. Approp. 53,000 - - 53,000 Cost 53,000 - -. 53,000 Bull Shoals Lake, White River Basin, Arkansas and Missouri Maint. Approp. 403,600 - - 403,600 Cost 129,300 274,300 - 403,600 Clearwater Lake, White River Basin, Missouri Maint. Approp. 45,000 - - 45,000 Cost 45,000 - - 45,000 Greers Ferry Lake, White River Basin, Arkansas Maint. Approp. 128,000 - - 128,000 Cost 106,700 21,300 - 128,000 Norfork Lake, White River Basin, Arkansas Maint. Approp. 75,900 - - 75,900 Cost 75,900 - - 75,900 Table Rock Lake, White River Basin, Missouri Maint. Approp. 460,800 - - 460,800 Cost 165,300 295,500 - 460,800 DeQueen Lake, Little River Basin, Arkansas Maint. Approp. 26,000 - - 26,000 Cost 26,000 - - 26,000 Dierks Lake, Little River Basin, Arkansas Maint. Approp. 120,000 - - 120,000 Cost 29,600 90,400 - 120,000 Gillham Lake, Little River Basin, Arkansas Maint. Approp. 143,000 - - 143,000 Cost 56,900 86,100 - 143,000 Millwood Lake, Little River Basin, Arkansas Maint. Approp. 162,000 - - 162,000 Cost 52,100 109,900 - 162,000 Little Massard Creek, Arkansas River Basin, Fort Smith, New Work Arkansas Approp. 80,000 - - 80,000 Cost 1,100 77,400 1,100 79,600 Otter Creek & Tributaries, Arkansas River Basin, Shannon Hills, New Work Arkansas Approp. 257,000 (70,000) - 187,000 Cost 0 147,100 10,000 157,100 18-25 TULSA, OKLAHOMA, DISTRICT* The civil works portion of this District covers an area of approximately 160,000 square miles including Oklahoma and parts of Kansas and Texas within the Arkansas and Red River Basins. The District's responsibilities within the Arkansas River Basin cover southern Kansas, northern Oklahoma, and the Txas Panhandle. These areas are embraced in the drainage basin of the Arkansas River and its tributaries above the mouth of the Poteau River, extending to the Kansas-Colorado state line, exclusive of that portion of the South Canadian River Basin and its tributaries west of the Texas-New Mexico state line. The District's responsibilities within the Red River Basin cover the northern portion of Texas, and the southern portion of Oklahoma embraced in the Red River drainage basin and its tributaries above Fulton, AR. The District also has responsibility for the operation and maintenance of the McClellan-Kerr Arkansas River Navigation System in Oklahoma. IMPROVEMENTS Navigation Page 1. McClellan-Kerr Arkansas River Navigation System, OK ................ 19-2 2. Other Authorized Navigation Projects.... 19-2 Flood Control 3. Arcadia Lake, OK ..................... 19-2 4. Arkansas-Red River Basins Chloride Control Projects, KS, OK, and TX ........ 19-2 4a. Area V, Estelline Springs . . . . . ... ..... 19-3 4b. Area VIII ............................. 19-3 5. Birch Lake, OK ........................ 19-3 6. Candy Lake, OK ....................... 19-3 7. Canton Lake, OK ..................... 19-3 8. Copan Lake, OK ....................... 19-3 9. Council Grove Lake, KS ................ 19-3 10. El Dorado Lake, KS .................... 19-4 11. Elk City Lake, KS ..................... 19-4 12. Fall River Lake, KS.................... 19-4 13. Fort Supply Lake, OK.................. 19-4 14. Great Salt Plains Lake, OK ............. 19-4 15. Heyburn Lake and Polecat Creek, OK .... 19-4 16. Hugo Lake, OK........................ 19-4 17. Hulah Lake,OK ........................ 19-4 18. John Redmond Dam and Reservoir, KS ... 19-4 19. Kaw Lake, OK ....................... 19-5 20. Lake Kemp, TX ....................... 19-5 21. Marion, KS ............................ 19-5 22. Marion Lake, KS ...................... 19-5 23. Oologah Lake,OK ...................... 19-5 24. Optima Lake, OK...................... 19-5 25. Pat Mayse Lake, TX ................... 19-5 26. Pearson-Skubitz Big Hill Lake, KS ....... 19-5 27. Pine Creek Lake, OK .................. 19-5 28. Sardis Lake, OK ........................ 19-6 29. Skiatook Lake, OK .................... 19-6 30. Toronto Lake, KS ....................... 19-6 31. Waurika Lake, OK .................... 19-6 32. Wister Lake, OK ...................... 19-6 33. Other Authorized Flood Control Projects . 19-6 34. Inspection of Completed Local Flood Protection Projects ...................... 19-6 35. Flood Damages Prevented by Corps and Non-Corps Projects .................... 19-6 36. Flood Control Work under Special Authorization .......................... 19-7 Multiple-Purpose Projects Including Power 37. Broken Bow Lake, OK ................. 38. Eufaula Lake, OK ..................... 39. Fort Gibson Lake, OK .................. 40. Grand Lake O' the Cherokees OK ........ 41. Keystone Lake, OK ..................... 42. Lake Texoma (Denison Dam), OK and TX ............................... 43. Robert S. Kerr Lock and Dam and Reservoir, OK ......................... 44. Tenkiller Ferry Lake, OK .............. 45. Webbers Falls Lock and Dam, OK ........ 19-7 19-7 19-7 19-7 19-7 19-7 19-7 19-8 19-8 General Investigations 46. Surveys............................... 19-8 47. Collection and Study of Basic Data ....... 19-8 48. Continuation of Planning and Engineering .......................... 19-8 49. Advanced Engineering and Design ....... 19-8 Tables 19-A Cost and Financial Statement............ 19-9 19-B Authorizing Legislation ................ 19-13 19-C Other Authorized Navigation Projects .... 19-15 19-D Not Applicable 19-E Other Authorized Flood Control Projects . 19-15 19-F Not Applicable 19-G Not Applicable 19-H Arkansas River Basin Multiple Purpose Plan .................................. 19-16 19-1 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 19-I Inspection of Completed Local Flood Protection Projects..................... 19-16 19-J Flood Damages Prevented by Corps and Non-Corps Projects .................... 19-17 19-K Flood Control Work Under Special Authorization ......................... 19-19 19-L General Investigations ................. 19-20 19-M Jobs Act (P.L. 98-8) .................... 19-21 Navigation 1. MC CLELLAN-KERR ARKANSAS RIVER NAVIGATION SYSTEM (Ililsa District Portion), OK. Location. The Tulsa District portion of the McClellan-Kerr Arkansas River Navigation System provides a navigation route up the Arkansas River from the Oklahoma-Arkansas state line to the head of navigation at Catoosa, OK, near Tulsa, OK. The total length of the Tulsa District portion of the system is 137 navigation miles. Descriptions and costs for the entire navigation system can be found in the Little Rock District's entry in this Annual Report. Existing projects. The McClellan-Kerr Arkansas River navigation project is a component of the multipurpose plan for the Arkansas River Basin which provided for the improvement of the basin through the construction of coordinated developments for navigation, hydroelectric power, flood control, water supply, water quality control, sediment control, recreation, and fish and wildlife propagation. The McClellan-Kerr project consists of bank stabilization, channel straightening, and cutoffs as required. The navigation channel has a minimum depth of 9 feet and a minimum width of 250 feet. The Tulsa District portion of the navigation system consists of the: Arkansas River Bank Stabilization and Channel Rectification, Chouteau Lock and Dam, Newt Graham Lock and Dam, Robert S. Kerr Lock and Dam, Robert S. Kerr Marine Tebrminal, Sans Bois Navigation Channel, W.D. Mayo Lock and Dam, Webbers Falls Lock and Dam, and the pool in Oklahoma which was created by Lock and Dam 13 in Arkansas. The other parts of the multiple-purpose plan for the Arkansas River Basin are listed in table 19-H. Tbrminal facilities. Public port facilities are in operation at Muskogee and Catoosa, OK. At Sallisaw, OK, a port authority has been active in seeking development of public facilities at that location. Other private commercial port facilities are complete and in operation at eight Oklahoma locations. Local cooperation. Fully complied with. Operations during fiscal year. Operation and maintenance continued. 2. OTHER AUTHORIZED NAVIGATION PROJECTS. See table 19-C. Flood Control 3. ARCADIA LAKE, OK. Location. On the Deep Fork River, river mile 213.8, in the metropolitan area of Oklahoma City and Edmond, OK, about 1.5 miles west of Arcadia, in Oklahoma County, OK. (See Arcadia, OK, Geological Survey map, scale 1:24,000.) Existing project. The plan of improvement provides for flood control, water supply, and recreation by construction of an earthfill dam approximately 104 feet high and 5,200 feet long with a high-level uncontrolled spillway Outlet works will consist of gated tower and conduit. The lake will have a total capacity of 92,000 acre-feet (27,380 for conservation, 64,430 for flood control, and 190 for sedimentation reserve) and will control a drainage area of 105 square miles. Construction began in October 1980. Local cooperation. Section 2, Flood Control Act of 1938, Water Supply Act of 1958, Federal Water Project Recreation Act of 1965, and Section 221, Flood Control Act of 1970 apply. Operations and results during fiscal year. The project is 72 percent complete. Estimated cost is $84,000,000 (October 1985 price level). Work to complete the relocation of the Turner Turnpike; to complete the embankment and spillway and recreation facilities; and the clearing of some project land was performed during the fiscal year. 4. ARKANSAS-RED RIVER BASINS CHLORIDE CONTROL PROJECTS, KS, OK, AND TX. Location. On certain tributary streams of the Arkansas and Red Rivers in the western half of the Thlsa District. Existing project. Provided for studies involving the control of the natural water pollution caused by the fifteen natural salt sources identified in 1957 by the US Public Health Service. The Arkansas and Red Rivers represent a major national and regional water resource which is severely limited because of poor water quality primarily caused by the natural pollutant, sodium chloride. The Arkansas River is polluted by five naturally occurring salt sources located in northwestern Oklahoma and southwestern Kansas. The Red River Basin is polluted by ten naturally occurring salt sources located in northwestern Tbxas and southwestern Oklahoma. These studies included the construction and subsequent maintenance of an injection well and a ring dike used for data collection. Preauthorization studies were completed in 1966 and 1970 and recommended construction of project features at thirteen of the fifteen sites. For a detailed discussion of the chloride control projects, see page 19-4 of the Annual Report for 1983. Local cooperation. Descriptive text concerning local cooperation requirements is given on page 19-5 of the Annual Report for 1983. 19-2 TULSA, OKLAHOMA DISTRICT 4a. AREA V, ESTELLINE SPRINGS. Location. Chloride control Area V is located about 0.5 mile east of Estelline, TX, on the Prairie Dog lbwn Fork of the Red River. Existing Project. The plan of improvement consisted of an earthen dike, 9 feet high and 340 feet in diameter, around Estelline Springs. The springs were a salt water source which decreased the usability of the surface water in the area. Construction was started in 1963 and the structure was completed in 1964. 4b. AREA VIII. Location. Chloride control Area VIII is located at river mile 74.9 of the South Fork of the Wichita River in King County, TX, about five miles east of Guthrie, TX. Existing Project. The plan of improvement consists of two low-flow collection dams with attendant pumping stations and pipeline facilities. These two structures (the Bateman Low Flow Dam and the Ross Ranch Low Flow Dam) will be equipped with an inflatable fabric-type weir located in the spillway section which would be deflated to pass relatively good quality high flows. The collected brines will be pumped to the storage reservoir behind the fruscott Brine Dam. This brine dam, located at river mile 3.6 on Bluff Creek (a tributary of the North Fork of the Wichita River) about three miles northwest of 'ruscott, TX, would contain the collected brines from this area as well as the future collections from Area X. Preconstruction planning for Area X is essentially complete and construction is awaiting approval from the Secretary of the Army and funding from Congress. Local cooperation. See page 19-5 of the Annual Report for 1983. Operations and results during fiscal year. Construction was initiated at Area VIII and Truscott Brine Dam in 1976 and the project is 98 percent complete. Estimated cost of the Area VIII project and Stage I development of 'uscott Brine Dam is $50,325,000 (October 1985 price level). 5. BIRCH LAKE, OK. Location. On Birch Creek, river mile 0.8, about 1.5 miles south of Barnsdall in Osage County, OK. (See Barnsdall, OK, Geological Survey map, scale 1:24,000.) Existing project. For a description of the completed improvement see Annual Report for 1979. Construction began in November 1973 and the project was placed in useful operation in March 1977. Local cooperation. Fully complied with. Operations and results during fiscal year. Routine operation and maintenance continued. 6. CANDY LAKE, OK. Location. On Candy Creek, river mile 1.9, a tributary of Bird Creek in the Verdigris River Basin. The damsite is about 1.5 miles northeast of Avant, Osage County, OK. (See Avant, OK, Geological Survey map, scale 1:24,000.) Existing project. The plan of improvement provides for an earthfill dam about 4,200 feet long, including an uncontrolled concrete spillway, with a maximum height of 103 feet above streambed. Outlet works will consist of a gated intake structure, a 10- by 11.25-foot conduit, and a stilling basin. An 18- by 24-inch low-flow pipe and an 18-inch water supply pipe will be provided. The lake will have a total capacity of 75,420 acre-feet (44,160 for conservation and sediment reserve and 31,260 for flood control). Drainage area above the damsite is 43 square miles. Candy Lake will be operated as a unit of a seven-lake system for flood control in the Verdigris River Basin in Oklahoma. Construction began in September 1976. Local cooperation. Section 2, Flood Control Act of 1938, Water Supply Act of 1958, and Section 221 of the Flood Control Act of 1970 apply. Operations and results during fiscal year. The project is about 13 percent complete but construction has been delayed because of the US Justice Department's decision to withdraw condemnation proceedings to acquire mineral rights. Estimated cost of the project is $38,300,000 (October 1984 price level): Project was deferred in January 1984. 7. CANTON LAKE, OK. Location. On the North Canadian River, river mile 394, and about 2 miles north of Canton, Blaine County, OK. (See Canton, OK, Geological Survey map, scale 1:24,000.) Existing project. For a description of the completed improvement see page 590 of Annual Report for 1969. Construction began in December 1940 and the project was placed in useful operation in April 1948. Local cooperation. Fully complied with. Operations and results during fiscal year. Routine operation and maintenance continued. 8. COPAN LAKE, OK. Location. On Little Caney River, river mile 7.4, a tributary of the Caney River in the Verdigris River Basin, about 2 miles west of Copan, Washington County, OK. (See Copan, KS, Geological Survey map, scale 1:24,000.) Existing project. For a description of the completed improvement see page 19-7 of the Annual Report for 1983. Copan Lake is operated as a unit of a seven-lake system for flood control in the Verdigris River Basin in Oklahoma. Construction began in November 1972 and the project was placed in useful operation in April 1983. Local cooperation. Fully complied with. Operations and results during fiscal year. Copan Lake is physically complete. There are some real estate deficiencies remaining to be settled and some final contract payments. 9. COUNCIL GROVE LAKE, KS. Location. On the Grand (Neosho) River, river mile 450, and about 1.5 miles northwest of Council Grove, Morris County, KS. (See Council Grove Lake, KS, Geological Survey map, scale 1:24,000.) Existing project. For a description of the completed improvement see page 519 of Annual Report for 1969. Construction began in June 1959 and project was placed in useful operation in July 1964. Local cooperation. Fully complied with. 19-3 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Operations and results during fiscal year. Routine operation and maintenance continued. 10. EL DORADO LAKE, KS. Location. On the Walnut River, river mile 100.2, a tributary of the Arkansas River, about 4 miles northeast of El Dorado, Butler County, KS. (See El Dorado, KS, Geological Survey map, scale 1:24,000.) Existing project. For a description of the completed improvement see page 19-7 of the Annual Report for 1983. El Dorado Lake was authorized as a unit of a three lake system for flood control in the Walnut River Basin. Construction began in October 1973 and impoundment began in June 1981. Local cooperation. Fully complied with. Operations and results during fiscal year. The project is 99 percent complete. Work to complete the real estate activities and recreational facilities was performed during the fiscal year. 11. ELK CITY LAKE, KS. Location. On Elk River, river mile 8.7, about 7 miles northwest of Independence, Montgomery County, KS. (See Table Mound, KS, Geological Survey map, scale 1:24,000.) Existing project. For a description of the completed improvement see page 593 of Annual Report for 1969. Construction began in February 1962 and the project was placed in useful operation in March 1966. Local cooperation. Fully complied with. Operations and results during fiscal year. Routine operation and maintenance continued. 12. FALL RIVER LAKE, KS. Location. On Fall River, river mile 54.2, about 4 miles northwest of Fall River, Greenwood County, KS. (See Severy, KS, Geological Survey map, scale 1:24,000.) Existing project. For a description of the completed improvement see page 953 of Annual Report for 1969. Construction of the dam began in May 1946 and the project was placed in full operation in April 1949. Local cooperation. Fully complied with. Operations and results during fiscal year. Routine operation and maintenance continued. 13. FORT SUPPLY LAKE, OK. Location. On Wolf Creek, river mile 5.5, a tributary of the North Canadian River, about 12 miles northwest of Woodward, Woodward County, OK. (See Fort Supply, OK, Geological Survey map, scale 1:24,000.) Existing project. For a description of the completed improvement see page 594 of Annual Report for 1969. Construction began in October 1938 and the project was placed in fill flood control operation in May 1942. Local cooperation. Fully complied with. Operations and results during fiscal year. Routine operation and maintenance continued. 14. GREAT SALT PLAINS LAKE, OK. Location. On Salt Fork of the Arkansas River, river mile 103.3, about 12 miles east of Cherokee, Alfalfa County, OK. (See Jet, OK, Geological Survey map, scale 1:24,000.) Existing project. For a description of the completed improvement see page 594 of Annual Report for 1969. Construction of the dam was initiated September 1938 and was completed July 1941. The project was placed in full flood control operation in May 1941. Local cooperation. Fully complied with. Operations and results during fiscal year. Routine operation and maintenance continued. 15. HEYBURN LAKE AND POLECAT CREEK, OK. Location. On Polecat Creek, a minor tributary to the Arkansas River at river mile 48.6, about 11 miles west of Sapulpa, Creek County, OK. (See Lake Heyburn, OK, Geological Survey map, scale 1:24,000,) Existing project. For a description of the completed improvement see page 599 of Annual Report for 1969. Construction was started in March 1948 and the project was placed in useful operation in October 1950. Channel improvements below the lake were completed in September 1952. Local cooperation. Fully complied with. Operations and result during fiscal year. Routine operation and maintenance continued. 16. HUGO LAKE, OK. Location. On the Kiamichi River, river mile 17.6, about 7 miles east of Hugo, Choctaw County, OK. (See Hugo Dam, OK, Geological Survey map, scale 1:24,000.) Existing project. For a description of the completed improvement see page 19-12 of the Annual Report for 1977. Construction began in October 1967 and the project was placed in useful operation in January 1974. Local cooperation. Fully complied with. Operations and results during fiscal year. Routine operation and maintenance continued. 17. HULAH LAKE, OK. Location. On the Caney River, river mile 96.2, about 15 miles northwest of Bartlesville, near Hulah, Osage County, OK. (See Bowring, OK, Geological Survey map, scale 1:24,000.) Existing project. For a description of the completed improvement see page 595 of the Annual Report for 1969. Construction began in May 1946 and was completed in June 1950. Project was placed in full flood control operation in September 1951. Local cooperation. Fully complied with. Operations and results during fiscal year. Routine operation and maintenance continued. 18. JOHN REDMOND DAM AND RESERVOIR, KS. Location. The dam is located on the Grand (Neosho) River, river mile 343.7, about 2 miles northwest of Burlington, Coffey County, KS. (See John Redmond Dam, KS, Geological Survey map, scale 1:24,000.) Existing project. For a description of the completed improvement see page 581 of the Annual Report for 1970. 19-4 TULSA, OKLAHOMA DISTRICT Construction was initiated in July 1959 and was completed in December 1965. The project was placed in flood control operation in July 1964. Local cooperation. Fully complied with. Operations and results during fiscal year. Routine operation and maintenance continued. 19. KAW LAKE, OK. Location. On the Arkansas River, river mile 653.7, about 8 miles east of Ponca City, Kay County, OK. (See Charley Creek West, OK, Geological Survey map, scale 1:24,000.) Existing project. For a description of the completed improvement see page 19-13 of the Annual Report for 1977. Construction began in June 1966 and the project was placed in operation in May 1976. Local cooperation. Fully complied with. Operations and results during fiscal year. Routine operation and maintenance continued. 20. LAKE KEMP, TX. Location. On the Wichita River, river mile 126.7, about 40 miles southwest of Wichita Falls, TX. (See Northeast Lake Kemp, TX, Geological Survey map, scale 1:24,000.) Existing project. For a description of the completed improvement see page 19-14 of the Annual Report for 1977. Construction began in May 1970 and the project was placed in useful operation in October 1972. Local cooperation. Fully complied with. Operations and results during fiscal year. Routine operation and maintenance continued. 21. MARION, KS. Location. On Mud Creek at Marion, the county seat of Marion County, KS. Existing project. For a description of the completed improvement see page 19-6 of the Annual Report for 1984. Construction began in June 1975 and was completed in May 1980. Local cooperation. Fully complied with. Operations and results during fiscal year. None. The city of Marion, KS, is responsible for project operation and maintenance. 22. MARION LAKE, KS. Location. On the Cottonwood River, river mile 126.7, about 3 miles northwest of Marion, Marion County, KS. (See Pilson, KS, Geological Survey map, scale 1:24,000.) Existing project. For a description of the completed improvement see page 597 of the Annual Report for 1969. Construction began in June 1964 and the project was placed in flood control operation in February 1968. Local cooperation. Fully complied with. Operations and results during fiscal year. Routine operation and maintenance continued. 23. OOLOGAH LAKE, OK. Location. On the Verdigris River, river mile 90.2, about 2 miles southeast of Oologah, Rogers County, OK. (See Oologah, OK, Geological Survey map, scale 1:24,000.) Existing project. For a description of the completed improvement see page 19-15 of the Annual Report for 1972. Construction began in July 1950 and was placed in standby status in October 1951. Construction was resumed in December 1955 and was completed in May 1963 for initial development. Construction for ultimate (second stage) development was initiated July 1967 and was completed in 1974. Local cooperation. Fully complied with. Operations and results during fiscal year. Routine operation and maintenance continued. 24. OPTIMA LAKE, OK. Location. On the North Canadian River, river mile 623.2, about 4.5 miles northeast of Hardesty, Texas County, OK. (See Optima Dam, OK, Geological Survey map, scale 1:24,000.) Existing project. For a description of the completed improvement see page 19-16 of the Annual Report for 1979. Construction began in March 1966. Impoundment began in October 1978, and construction was completed in 1981. Local cooperation. Fully complied with. Operations and results during fiscal year. Routine operation and maintenance continued. 25. PAT MAYSE LAKE, TX. Location. On Sanders Creek, river mile 4.6, a tributary of the Red River, about 12 miles north of Paris, Lamar County, TX. (See Grant, TX, Geological Survey map, scale 1:24,000.) Existing project. For a description of the completed improvement see page 584 of the Annual Report for 1970. Construction began in March 1965 and the project was placed in full flood control operation in September 1967. Local cooperation. Fully complied with. Operations and results during fiscal year. Routine operation and maintenance continued. 26. PEARSON-SKUBITZ BIG HILL LAKE, KS. Location. On Big Hill Creek, river mile 33.3, about 4.5 miles east of Cherryvale, KS. (See Dennis, KS, Geological Survey map, scale 1:24,000.) Existing project. For a description of the completed improvement see page 19-11 of the Annual Report for 1983. Construction began in April 1974 and impoundment began in March 1981. Local cooperation. Fully complied with. Operations and results during fiscal year. Routine operation and maintenance continued. 27. PINE CREEK LAKE, OK. Location. On Little River, river mile 145.3, about 5 miles northwest of Wright City, McCurtain County, OK. (See Wright City, OK, Geological Survey map, scale 1:24,000.) Existing project. For a description of the completed improvement see page 584 of the Annual Report for 1970. Construction began in February 1963 and the project was placed in useful operation in June 1969. 19-5 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Local cooperation. Fully complied with. Operations and results during fiscal year. Routine operation and maintenance continued. Workto complete sanitary facilities at the park was conducted during the fiscal year. 28. SARDIS LAKE, OK. Location. On Jackford Creek, river mile 2.8, a tributary of the Kiamichi River, about 2.5 miles north of Clayton, Pushmataha County, OK. (See Yanush, OK, Geological Survey map, scale 1:24,000.) Existing project. For a description of the completed improvement see page 19-11 of the Annual Report for 1983. Sardis Lake will be operated as a unit of a threelake system for flood control in the Kiamichi River Basin, including Hugo and Tskahoma Lakes. Construction began in August 1975 and the project became operational in January 1983. Local cooperation. Fully complied with. Operations and results during fiscal year. Estimated cost of the project is $65,928,000 (October 1985 price level). The project is 80 percent complete. Work to complete the recreation facilities at the project was performed during the fiscal year. 29. SKIATOOK LAKE, OK. Location. On Hominy Creek, river mile 14.3, a tributary of Bird Creek, in the Verdigris River Basin about 5 miles west of Skiatook, Osage County, OK. (See Avant S.E., OK, Geological Survey map, scale 1:24,000.) Existing project. Provides for an earthfill dam 3,590 feet long, 143 feet high with a crown width of 32 feet. The uncontrolled 100-foot spillway will be located in the right abutment. Outlet works will consist of a controlled intake structure, a 10.5-foot diameter tunnel stilling basin, a 2.5-foot by 5-foot low-flow sluice, and a 36-inch water supply pipe. The lake will provide a total storage of 513,500 acre-feet (319,400 for conservation storage, 182,300 for flood control, and 11,800 for sedimentation), and will control a drainage area of 354 square miles. Skiatook Lake will be operated as a unit of a seven-lake system for flood control in the Verdigris River Basin in Oklahoma. Construction began in January 1974, impoundment began October 1984, and the project became operational November 1984. Local cooperation. Fully complied with. Operations and results during fiscal year. The project is 92 percent complete. Estimated cost of the project is $112,595,000 (October 1985 price level), including deferred recreational development at $8,805,000. Work to plug oil and gas wells, complete real estate activities, and construct embankment, access roads, and recreation facilities was performed during the fiscal year. 30. TORONTO LAKE, KS. Location. On the Verdigris River, river mile 271.5, about 4 miles southeast of 'bronto, Woodson County, KS. (See Fredonia, KS, Geological Survey map, scale 1:24,000.) Existing Project. For a description of the completed improvement see page 600 of the Annual Report for 1969. Construction began November 1954 and project was placed in full operation March 1960. Local cooperation. Fully complied with. Operations and results during fiscal year. Routine operation and maintenance continued. 31. WAURIKA LAKE, OK. Location. On Beaver Creek, river mile 27.0, a tributary of the Red River, about 6 miles northwest of Waurika, Jefferson County, OK. (See Hastings, OK-TX, Geological Survey map, scale 1:24,000.) Existing project. For a description of the completed improvement see page 19-12 of the Annual Report for 1983. Waurika Lake is operated as a unit of a coordinated lake system for flood control in the Red River Basin. Construction began in July 1971 and impoundment began in August 1977. Local cooperation. Fully complied with. Operations and results during fiscal year. Routine operation and maintenance continued. 32. WISTER LAKE, OK. Location. On the Poteau River, river mile 60.9, about 2 miles south of Wister, LeFlore County, OK. (See Wister, OK, Geological Survey map, scale 1:24,000.) Existing project. For a description of the completed improvement see page 601 of the Annual Report for 1969. Construction began April 1946 and was completed May 1949. The project was placed in full flood control operation in October 1949. Local cooperation. Fully complied with. Operations and results during fiscal year. Routine operation and maintenance continued. 33. OTHER AUTHORIZED FLOOD CONTROL PROJECTS. See table 19-E. 34. INSPECTION OF COMPLETED LOCAL FLOOD PROTECTION PROJECTS. Inspections of the completed local flood protection projects operated and maintained by local interests are made to determine the extent of compliance with approved regulations for operations and maintenance. The inspections assist the Corps of Engineers to determine if the project provides the flood protection for which it was constructed. See table 19-I for a list of projects inspected in Fiscal Year 1985. Fiscal year cost was $122,896. 35. FLOOD DAMAGES PREVENTED BY CORPS AND NON-CORPS PROJECTS. The Corps is authorized to prescribe regulations for the use of flood control and navigation storages at all reservoirs constructed wholly or in part with Federal funds by the Flood Control Act of 1944. Through this act, operation of Corps and non-Corps reservoirs results in the prevention of flood damages. Flood damages are also prevented by Local Flood Protection Projects constructed by the Corps. Table 19-J lists these reservoirs and local protection projects and presents their fiscal year and cumula- 19-6 TULSA, OKLAHOMA DISTRICT tive flood damage prevented amounts. Fiscal year cost for the maintenance of flood control works at non-Corps projects totaled $381,403. 36. FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION. See table 19-K for tabulations concerning the Fiscal Year 1985 expenditures for: Small Flood Control Projects Not Specifically Authorized by Congress (Section 205); Emergency Streambank and Shoreline Projects; Snagging and Clearing; and Flood Control and Coastal Emergencies - Rehabilitation Projects. Multiple-Purpose Projects Including Power 37. BROKEN BOW LAKE, OK. Location. On the Mountain Fork River, river mile 20.3, about 9 miles northeast of Broken Bow, McCurtain County, OK. (See Broken Bow, OK, Geological Survey map, scale 1:24,000.) Existing project. For a description of the completed improvements see page 19-17 of the Annual Report for 1971. Construction began in November 1961 and the project was placed in useful operation in October 1969. Power units 1 and 2 were placed in operation in January and June 1970, respectively. Local cooperation. Fully complied with. Operations and results during fiscal year. Routine operation and maintenance continued. 38. EUFAULA LAKE, OK. Location. On the Canadian River, at river mile 27.0, about 12 miles east of Eufaula, McIntosh County, OK. (See Porum, OK, Geological Survey map, scale 1:24,000.) Existing project. For a description of the completed improvement see page 588 of the Annual Report for 1970. Construction began in December 1956 and the project was placed in full flood control operation in February 1964. Local cooperation. Fully complied with. Operations and results during fiscal year. Routine operation and maintenance continued. Work to plan, design, and construct a replacement bridge over Piney Creek was performed during the fiscal year. 39. FORT GIBSON LAKE, OK. Location. On the Grand (Neosho) River, river mile 7.7, about 5 miles north of Fort Gibson, Muskogee County, OK. (See Fort Gibson Dam, OK, Geological Survey map, scale 1:24,000). Existing project. For a description of the completed improvement see page 604 of the Annual Report for 1969. Construction began in March 1942 but construction was held in abeyance during World War II. Construction of the concrete dam and spillway started in May 1946 and was completed in June 1950. The fourth generator was installed and the project was placed in full operation in September 1953. Local cooperation. Fully complied with. Operations and results during fiscal year. Routine operation and maintenance continued. 40. GRAND LAKE O' THE CHEROKEES, OK. Location. On the Grand (Neosho) River, river mile 77.0, near the town of Disney, Mayes County, OK. (See Spavinaw, OK, Geological Survey map, scale 1:24,000). Existing project. Grand Lake O' the Cherokees is a Grand River Dam Authority project. For a description of the completed improvement see page 606 of the Annual Report for 1969. Operations and results during fiscal year. Grand Lake O' the Cherokees flood control operations is controlled by the Corps. See Section 35 and Table 19-J for additional details. 41. KEYSTONE LAKE, OK. Location. On the Arkansas River, river mile 538.8, near Sand Springs, OK, and about 15 miles west of Thilsa, OK. (See Keystone Dam, OK, Geological Survey map, scale 1:24,000.) Existing project. For a description of the completed improvement see page 589 of the Annual Report for 1970. Construction began in January 1957 and the the project was placed in flood control operation in September 1964. Local cooperation. Fully complied with. Operations and results during fiscal year. Routine operation and maintenance continued. 42. LAKE TEXOMA (DENISON DAM), OK AND TX. Location. On the Red River, river mile 725.9, about 5 miles northwest of Denison, TX. (See Denison Dam, OK, Geological Survey map, scale 1:24,000.) Existing project. For a description of the completed improvement see page 603 of the Annual Report for 1969. Lake 'Tbxoma is operated as a unit of a coordinated lake system for flood control in the Red River Basin. Construction was started in August 1939 and was completed for the dam, spillway, and outlet works in February 1944. Commercial power generation was started in March 1945. Authorized work is completed except for installation of the third and fourth power units, and additional perimeter access roads which have been recommended for deferral. Local cooperation. Fully complied with. Operations and results during fiscal year. Routine operation and maintenance continued. 43. ROBERT S. KERR LOCK AND DAM AND RESERVOIR, OK. Location. On the Arkansas River at navigation mile 336.2, about 8 miles south of Sallisaw, LeFlore County, OK. (See Robert S. Kerr, OK, Geological Survey map, scale 1:24,000.) Existing project. For a description of the completed improvement see page 19-21 of the Annual Report for 1972. Robert S. Kerr Lock and Dam and Reservoir is a unit of the McClellan-Kerr Arkansas River Navigation 19-7 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 System. Construction began in April 1964 and closure was completed in October 1970. The lock and dam became operational for navigation in December 1970. Generating Units number 1, number 2, number 3, and number 4 were placed in operation in October, July, September, and November 1971, respectively. Local cooperation. See section 1 of this report. Terminal facilities. Seven sites have been developed for handling coal, grain, construction aggregates, and miscellaneous cargo. The facilities are considered adequate for present traffic. Operations and results during fiscal year. Routine operation and maintenance continued. 44. TENKILLER FERRY LAKE, OK. Location. On the Illinois River, river mile 12.8, 7 miles northeast of Gore, Sequoyah County, OK. (See Gore, OK, Geological Survey map, scale 1:24,000.) Existing project. For a description of the completed improvement see page 606 of the Annual Report for 1969. Construction began in June 1947 and was completed in July 1953. Local cooperation. Fully complied with. Operations and results during fiscal year. Routine operation and maintenance continued. 45. WEBBERS FALLS LOCK AND DAM, OK. Location. On the Arkansas River at navigation mile 366.6, about 5 miles northwest of Webbers Falls, Muskogee County, OK. (See Webbers Falls, OK, Geological Survey map, scale 1:24,000.) Existing project. For a description of the completed improvement see page 19-23 of the Annual Report for 1977. Webbers Falls Lock and Dam is a unit of the McClellan-Kerr Arkansas River Navigation System. Construction began in January 1965, and the project was placed in useful operation in November 1970. The lock and dam became operational for navigation in December 1970. Generating Units number 1, number 2, and number 3 were placed in operation in August, September, and November 1973, respectively. Local cooperation. See section 1 of this report. Tbrminal facilities. Cargo pier, mooring dolphins, warehouse, terminal building, and fuel facility were built by the Muskogee City-County Port Authority. Liquid cargo loading facility and steel unloading facility were built by Frontier Steel Company to serve existing traffic. Operations and results during fiscal year. Generating Unit number 3 was returned to full service after repairs to cracked turbine shaft welds were completed. General Investigations 46. SURVEYS Fiscal year cost was $2,404,374 which included one navigation study, seven flood damage prevention studies, the Arkansas-Red River Basins Solar Energy Investigation, three comprehensive studies, two restudies of deferred studies, two reviews of completed projects, two reviews for deauthorization studies, inventory of dams, coordination with both Federal and non-Federal agencies, and an investigation on a flood control reservoir. Table 19-L provides a specific list and respective fiscal year expenditures. 47. COLLECTION AND STUDY OF BASIC DATA. Fiscal year cost was $275,228 which includes the items concerning flood plain management services and hydrologic studies. Table 19-L provides a specific list and respective fiscal year expenditures. 48. CONTINUATION OF PLANNING AND ENGINEERING. Fiscal year cost was $1,352,595 which includes four local protection projects and one flood control reservoir. Table 19-L provides a specific list and respective fiscal year expenditures. 49. ADVANCED ENGINEERING AND DESIGN. Fiscal year cost was $553,240 which included one local protection project and one flood control reservoir. Table 19-L provides a specific list and respective fiscal year expenditures. 19-8 TULSA, OKLAHOMA DISTRICT TABLE 19-A COST AND FINANCIAL STATEMENT See Section in TIxt Project Funding 1. McClellan-Kerr Arkansas New Work River Navigation System, Approp. OK. (Tulsa District Cost Portion)* Maint. Approp. Cost 3. Arcadia Lake, OK New Work Approp. Cost 4. Arkansas-Red River Basins New Work Chloride Control, OK Approp. and TX Cost Maint. Approp. Cost 4a. Area V, Estelline Springs New Work Approp. Cost Maint. Approp. Cost 4b. Area VIII New Work Approp. Cost 5. Birch Lake, OK New Work Approp. Cost Maint. Approp. Cost 6. Candy Lake, OK New Work Approp. Cost 7. Canton Lake, OK New Work Approp. Cost Maint. Approp. Cost 8. Copan Lake, OK New Work Approp. Cost Maint. Approp. Cost 9. Council Grove Lake, New Work KS Approp. Cost Maint. Approp. Cost 10. El Dorado Lake, New Work KS Approp. Cost Maint. Approp. Cost FY 82 FY 83 FY 84 2,710 6,758,140 6,333,691 17,989,780 15,600,626 252,245 61,000 59,985 3,000 2,574 10,840,000 9,791,605 -735 601,100 576,002 6,905 5,776 867,400 864,623 11,900,000 7,832,339 202,500 196,999 544,880 536,921 2,550,000 3,075,030 247,500 245,029 7,571,632 8,227,217 20,430,000 12,765,430 49,104 2,000 2,703 3,000 3,650 4,923,000 5,317,748 1,006 583,200 564,174 27,026 -1,000 508 933,000 811,568 300,000 3,801,718 207,000 179,008 120 11,652 672,500 650,417 6,700,000 6,806,749 330,000 302,618 6,540,500 6,403,180 3,800,000 8,967,266 5,215 6,000 5,425 5,500 4,791 1,829,000 1,527,050 177 529,200 489,132 2,908 120 1,048,700 1,072,826 -104,440 316,200 305,573 66 615,866 565,348 5,300,000 2,096,205 319,000 312,064 'Ibtal to FY 85 Sep 30,19851 - 296,553,114 - 296,553,538 7,600,266 101,719,2112 7,865,411 96,768,0812 9,330,000 66,894,289 9,687,358 62,008,756 - 25,705,208 437 25,704,510 43,000 3,521,247 42,891 3,633,308 - 300,028 - 300,028 4,600 131,076 4,233 144,637 -33,000 45,550,000 562,003 45,028,503 - 13,549,170 - 13,549,296 658,700 4,288,4012 735,047 7,571,3092 - 4,949,922 1,663 4,863,567 - 11,209,834 - 10,918,727 1,695,800 14,575,3722 1,766,592 14,541,5552 8,663,000 85,134,999 8,531,025 87,729,871 516,700 1,039,900 507,386 991,967 -2,940 11,810,509 S-2,940 11,810,509 864,200 7,883,6322 899,513 7,805,3502 2,370,000 90,371,468 3,491,995 88,016,736 355,700 1,326,300 371,549 1,302,227 19-9 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 19-A COST AND FINANCIAL STATEMENT (Continued) See Section in 'Ibtal to FY 82 FY 83 FY 84 FY 85 Sep 30,1985' 15,000 8,033 461,500 499,174 34,000 38,491 534,800 526,590 I Tbxt Project Funding 11. Elk City Lake, KS New Work Approp. Cost Maint. Approp. Cost 12. Fall River Lake, KS New Work Approp. Cost Maint. Approp. Cost 13. Fort Supply Lake, OK New Work Approp. Cost Maint. Approp. Cost 14. Great Salt Plains Lake, New Work OK Approp. Cost Maint. Approp. Cost 15. Heyburn Lake, OK New Work Approp. Cost Maint. Approp. Cost 16. Hugo Lake, OK New Work Approp. Cost Maint. Approp. Cost 17. Hulah Lake, OK New Work Approp. Cost Maint. Approp. Cost Minor Rehab. Approp. Cost 18. John Redmond Dam New Work and Reservoir, KS Approp. Cost Maint. Approp. Cost 19. Kaw Lake, OK New Work Approp. Cost Maint. Approp. Cost 20. Lake Kemp, TX New Work Approp. Cost Maint. Approp. Cost 21. Marion, KS New Work Approp. Cost -5,000 - - 19,052,990 1,226 741 - 19,052,990 605,708 689,066 601,700 7,462,906 560,188 734,948 532,204 7,347,410' -520 - - 10,550,873 - - - 10,550,873 643,900 651,020 791,600 7,710,7952 604,595 640,445 587,760 7,611,0812 - - - 7,724,134 - - - 7,723,127 503,500 476,000 624,000 7,479,073' 475,974 487,499 634,882 7,448,647! - - - 4,626,270 - - - 4,626,270 331,000 272,900 458,000 4,686,107 314,860 291,510 307,513 4,522,945 2,800 -1,900 - 2,560,572 219 3,971 - 2,560,572 449,300 461,170 463,100 6,172,1232 421,774 431,927 600,987 6,230,1472 - 20,000 - 37,759,742 1,848 3,128 -279,088 37,425,243 1,360,582 985,721 1,186,900 9,089,5282 911,554 1,447,283 1,103,885 8,900,0322 20,000 -2,400 - 11,388,150 27,990 15,130 2,500 11,182,433 629,400 615,970 878,300 8,845,279 587,292 484,631 835,107 8,583,669' - - - 135,718 - - - 135,718 - - - 28,151,515 - - - 28,151,515 823,000 1,202,000 3,776,066 13,653,0552 752,018 850,643 4,123,729 13,545,269' 490,000 -71,900 - 109,430,750 361,641 214,312 -4,518 109,277,682 1,529,400 1,145,800 1,454,800 11,287,4682 1,312,594 1,165,463 1,407,293 10,875,5882 - - - 7,637,702 - - - 7,637,702 119,000 141,000 148,600 1,410,234 116,978 130,672 136,531 1,372,087 -81,000 - - 5,519,200 - 339 7,227 5,455,434 19-10 537,300 547,926 333,000 336,770 41,000 37,710 608,648 610,517 35,000 40,642 890,800 854,045 31,500 3,480 511,116 508,371 642,036 645,602 200,000 173,051 1,298,860 1,186,045 146,900 134,656 11,474 TULSA, OKLAHOMA DISTRICT TABLE 19-A (Continued) See Section in 'bxt Project 22. Marion Lake, KS 23. Oologah Lake, OK 24. Optima Lake, OK 25. Pat Mayse Lake, TX 26. Pearson-Skubitz Big Hill Lake, KS 27. Pine Creek Lake, OK 28. Sardis Lake, OK 29. Skiatook Lake, OK 30. Toronto Lake, KS 31. Waurika Lake, OK 32. Wister Lake, OK COST AND FINANCIAL STATEMENT Funding New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost TIbtal to FY 82 FY 83 FY 84 FY 85 Sep 30,19851 20,000 10,644 639,680 631,475 937,800 923,660 20,000 47,431 453,200 430,439 596,760 595,201 2,113,000 2,247,338 355,400 350,650 623,300 620,846 3,565,000 4,707,433 15,806,000 19,991,981 314,600 306,165 489,000 734,340 652,700 648,991 403,100 405,482 -5,500 3,781 662,900 644,828 37,000 2,951 1,241,395 1,199,023 141 512,000 488,318 762,667 710,873 275,827 498,000 519,559 630,930 607,598 1,050,000 2,159,987 305,000 286,000 9,355,000 7,730,104 256,500 239,636 122,799 759,630 751,347 468,000 445,128 71,000 70,236 797,434 730,648 -4,000 30,049 1,154,400 1,074,913 -10,000 1,201 420,368 455,925 848,900 620,839 45,090 548,000 504,413 188,400 100,486 865,870 645,695 1,288,000 -27,969 395,000 378,047 10,000,000 8,804,556 264,000 268,588 1,314 776,500 730,723 500,614 468,971 A A A A A A A A w A 19-11 - 13,420,817 839 13,420,817 986,600 8,663,1462 1,028,180 8,561,3812 - 46,722,3298 - 46,721,5563 1,168,900 14,489,1042 1,200,842 14,324,5802 - 47,173,438 - 47,273,438 442,400 2,717,522 455,332 2,705,157 - 9,310,661 - 9,310,661 1,185,400 7,843,3092 1,347,577 7,696,7772 -241,000 16,879,166 -147,645 16,879,125 603,900 2,103,3002 590,428 2,057,4822 134,740 20,628,049 154,343 20,559,738 927,600 7,492,8582 1,008,083 7,284,0912 -122,000 53,303,479 696,504 52,685,852 451,100 1,151,100 451,528 1,115,575 2,375,000 103,518,282 5,499,255 102,117,426 218,400 218,400 202,153 202,153 - 13,896,324 - 13,896,324 188,000 4,059,503 213,803 4,055,332 - 67,080,050 -12,313 66,903,328 727,100 4,663,1442 770,961 4,630,9622 - 10,501,226 - 10,501,226 735,900 7,716,059 742,409 7,650,845 TABLE 19-A (Continued) See Section in Tbxt REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 COST AND FINANCIAL STATEMENT Project Funding FY 82 FY 83 FY 84 Ibtal to FY 85 Sep 30,19851 37. Broken Bow Lake, OK 38. Eufaula Lake, OK 39. Fort Gibson Lake, OK 40. Grand Lake O' the Cherokees, OK 41. Keystone Lake, OK 42. Lake Texoma (Denison Dam), OK and TX 43. Robert S. Kerr Lock & Dam & Reservoir, OK 44. Tenkiller Ferry Lake, OK 45. Webbers Falls Lock & Dam, OK New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost Minor Rehab. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost 1,102,100 1,073,248 29,000 17,625 2,475,000 2,411,469 5 2,643,400 2,576,560 11,500 8,892 1,897,680 1,928,184 8,000 17,726 3,643,780 3,557,594 1,775,880 1,734,857 154,000 27,114 2,523,900 2,104,934 1,577 2,595,060 2,366,428 2,030,000 1,213,463 1,5 1,229,088 1,809,738 1,6 - - 8 11,203 200 2,697,400 2,495,070 2,7 2,596,323 2,619,134 2,8 70,000 23,146 2,504,900 2,759,933 -14,000 35,489 2,378,281 2,391,757 2,6 2,6 - 41,222,692 - 41,222,692 27,500 12,604,319 29,880 12,455,964 50,000 122,680,7475 37,645 121,857,1896 37,100 35,579,9442 49,316 32,410,9412 - 42,591,2986 6,625 43,497,7916 85,400 32,899,866 45,762 33,955,3662 - - - 52,126 - - - 52,126 9,000 5,500 1,800 226,508 10,933 4,222 1,877 224,474 45,000 - - 123,171,173' 21,000 23,500 - 123,170,675' 2,197,000 2,148,600 2,953,264 27,446,5302 2,106,790 2,163,686 3,041,800 27,348,9072 92,319 54,400 - 68,168,960' 10,591 128,434 15,512 68,019,109' 4,954,242 5,006,165 6,254,300 61,118,0482 3,943,331 5,444,478 6,640,360 60,771,4002 - - - 46,237 - - - 46,237 - - - 94,578,237 - - - 94,578,237 2,114,832 2,234,200 2,562,400 28,847,8362 2,083,891 2,014,661 2,669,319 28,265,2452 - -58,000 - 24,017,7208 40,575 35,249 - 24,057,7188 2,508,500 2,194,416 2,392,800 27,128,1762 2,660,198 2,110,520 2,674,605 26,890,159' - - - 83,738,277 - - - 83,738,701 2,933,256 1,869,900 2,282,026 28,557,2642 3,530,602 2,252,816 2,445,589 28,327,0062 *These figures represent the total'investment for the Thlsa District in the McClellan-Kerr Arkansas River Navigation System in Oklahoma. These values include all features of the navigation system as listed in Section 1 of the text. Projects which include power are also shown in their respective section of this report. 1. Includes funds provided by the Jobs Act (P.L. 98-8, dated March 24,1983) for projects listed in Table 19-M. 2. Beginning this fiscal year, data shown on Table A includes special recreation use fees. Data for previous fiscal years have been changed to conform to the new procedure. 19-12 TULSA, OKLAHOMA DISTRICT COST AND FINANCIAL STATEMENT 3. Excludes $81,460 contributed funds and $1,348,816 special funds. 4. Includes $433,539 Emergency Relief funds. Exchange $1,256,068 from special contributed funds. 5. Excludes $299,803 contributed funds and $13,211,728 special funds. TABLE 19-B 6. Excludes $134,919 contributed funds. Includes $49,581 Public Works acceleration funds. 7. Excludes $5,366,231 special funds. 8. Excludes $946 contributed funds. Includes $39,999 Public Works acceleration funds. AUTHORIZING LEGISLATION See Date of Section Authorizing Project and in T'xt Acts Work Authorized Documents 1. Jul 24, 1946 3. Dec 31,1970 Oct 22, 1976 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. 16. 17. 18. 19. 20. 21. 22. 23. Oct 23, 1962 Nov 7,1966 Dec 31, 1970 Oct 23, 1962 Oct 23,1962 Jun 28,1938 Jul 24,1946 Jun 30,1948 Oct 23,1962 May 17,1950 Oct 27,1965 Aug 18,1941 Aug 18,1941 Jun 22,1936 Jun 22,1936 Jul 24,1946 Jul 24, 1946 Jun 22,1936 May 17,1950 Feb 15,1958 Oct 23,1962 Oct 23,1962 Section 201 May 17,1950 Jun 28,1938 MC CLELLAN-KERR ARKANSAS RIVER NAVIGATION SYSTEM ARCADIA LAKE Change water quality to water supply ARKANSAS-RED RIVER BASINS CHLORIDE CONTROL Authorized Area V (Estelline Springs) Authorized Areas VII, VIII and X Authorized Areas I, II-III, VI, IX, XIII, XIV, and XV BIRCH LAKE CANDY LAKE CANTON LAKE Approved Irrigation Storage Approved Water Supply Storage COPAN LAKE COUNCIL GROVE LAKE EL DORADO LAKE ELK CITY LAKE FALL RIVER LAKE FORT SUPPLY LAKE GREAT SALT PLAINS LAKE HEYBURN LAKE AND POLECAT CREEK HUGO LAKE HULAH LAKE JOHN REDMOND DAM AND RESERVOIR Authorized name change KAW LAKE LAKE KEMP MARION, KS MARION LAKE OOLOGAH LAKE HD 79-758, PL 525 HD 91-299 PL 94-587 SD 87-107 PL 89-789, SD 110 PL 91-611 HD 87-563 HD 87-563 HD 75-569 HD 87-563 HD 80-442 HD 89-232 HD 76-440 HD 76-440 HD 74-308 HD 74-308 HD 80-290 HD 79-602 HD 74-308 HD 80-442 PL 85-327 HD 87-143 HD 87-144 HD 91-256 HD 80-442 Committee Doc. No. 1, 75th Cong, 1st Session 19-13 TABLE 19-A (Continued) REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 19-B (Continued) AUTHORIZING LEGISLATION See Date of Section Authorizing Project and in Ibxt Acts Work Authorized Documents 24. Jun 22,1936 25. Oct 23,1962 26. Oct 23,1962 Nov 10,1978 27. Jul 3,1958 28. Oct 23,1962 Dec 4,1981 29. Oct 23,1962 30. Aug 18,1941 31. Dec 30,1963 32. Jun 28,1938 Jul 30,1983 37. Jul 3,1958 Oct 23,1962 38. Jul 24,1946 39. Aug 18,1941 Jul 24,1946 40. Aug 18,1941 Jul 24,1946 41. 42. May 17, 1950 Jun 28,1938 Oct 17, 1940 Sep 30,1944 Aug 14,1953 43. Jul 24,1946 Jul 8, 1963 44. Jun 28,1938 Jun 24,1946 45. Jul 24, 1946 OPTIMA LAKE PAT MAYSE LAKE PEARSON-SKUBITZ BIG HILL LAKE Authorized name change PINE CREEK LAKE SARDIS LAKE Authorized name change SKIATOOK LAKE TORONTO LAKE WAURIKA LAKE WISTER LAKE Conservation pool elevation changed BROKEN BOW LAKE EUFAULA LAKE FORT GIBSON LAKE Incorporated into the multiple purpose plan for the Arkansas River Basin GRAND LAKE O' THE CHEROKEES Incorporated into the multiple purpose plan for the Arkansas River KEYSTONE LAKE LAKE TEXOMA (Denison Dam) Flood control and power Navigation and regulating flows Authorized name Water supply ROBERT S. KERR LOCK AND DAM AND RESERVOIR Authorized name change TENKILLER FERRY LAKE Power WEBBERS FALLS LOCK AND DAM HD 74-308 HD 88-71 HD 87-472 PL 95-265 HD 85-170 SD 87-145 PL 97-88 HD 87-563 HD 76-440 PL 77-228 SD 88-33 PL 88-253 Committee Doc. No.1, 75th Cong, 1st Session PL 98-63 HD 85-170 SD 87-137 HD 79-758 HD 76-107 HD 76-107 PL 76-228 SD 81-07 HD 75-541 PL 76-868 PL 78-454 PL 83-273 HD 79-758 PL 88-62 Committee Doc. No. 1, 75th Cong, 1st Session HD 79-758 HD 79-758 19-14 TULSA, OKLAHOMA DISTRICT TABLE 19-C OTHER AUTHORIZED NAVIGATION PROJECTS For Last Cost to September 30,1985 Full Report See Annual Operation and Project Status Report For Construction Maintenance Poteau River Navigation Project, OK and AR Complete 1983 536,952 - Red River from Fulton, AR, to Mouth of Washita River Complete 1924 378,574 182,157 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 19-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS For Last Cost to September 30,1985 Full Report See Annual Operation and Project Status Report For Construction Maintenance Augusta L.P.P., KS1 Complete 1938 - 84,217 Big Pine Lake, TX Deferred 1984 1,701,670 - Boswell Lake, OK Deferred 1952 - - Cedar Point Lake, KS Deferred 1980 - - Cherry and Red Fork Creeks, L.P.P., OK Complete 1970 261,448 - Cow Creek, L.P.P., KS Deferred 1971 363,720 - Crutcho Creek, L.P.P., OK Deferred 1972 213,016 - El Dorado, L.P.P., KS Inactive 1977 92,319 - Enid, L.P.P., OK Complete 1963 743,612 14,599 Flat Rock Creek, Tulsa, L.P.P., OK2 Complete 1975 1,741,000 - Florence, L.P.P., KS Complete 1965 369,782 - Hutchinson, L.P.P., KS Complete 1956 3,497,718 - Iola, L.P.P., KS Complete 1939 22,290 - Jenks, L.P.P., OK Complete 1950 344,797 - Lukfata Lake, OK Inactive 1983 1,424,685 - Neodesha Lake, KS Inactive 1952 97,910 - Oklahoma City, L.P.P., OK Complete 1960 8,047,512 - Red River Bank Stabilization, Below Denison Complete 1953 222,105 - Sand Creek, L.P.P., KS Complete 1968 545,996 - Sand Lake, OK Deferred 1963 - - Shidler Lake, OK Deferred 1983 568,191 - Towanda Lake, KS Inactive 1981 392,361 - Tulsa/West Tulsa, L.P.P., OK Complete 1954 2,785,070 - Turtle Creek, L.P.P., Yukon, OK Deferred 1975 144,853 - Tuskahoma Lake, OK Inactive 1963 - - West Branch Chisholm Creek, L.P.P., KS Complete 1965 364,200 - Wichita and Valley Center, L.P.P., KS Complete 1960 12,247,379 - Winfield, L.P.P., KS1 Complete 1937 - - L.P.P. - Local Protection Project. 1. Completed by Kansas Works Progress Administration. 2. Federal cost limited to $1,000,000. 19-15 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 19-H ARKANSAS RIVER BASIN MULTIPLE-PURPOSE PLAN (See Section 1 of Thxt) River River Mile Nearest 'bwn LAKES Canton North Canadian Elk City Elk River Eufaula Canadian Fall River Fall River Fort Gibson Grand (Neosho) Grand Lake O' the Cherokees Grand (Neosho) Keystone Arkansas Lake Hudson (Markham Ferry) Grand (Neosho) Neodesha Verdigris Oologah Verdigris 'Tebnkiller Ferry Illinois 'bronto Verdigris Wister Poteau MC CLELLAN-KERR ARKANSAS RIVER NAVIGATION SYSTEM, OK' (Thlsa District Portion) Bank Stabilization and Channel Rectification Verdigris and Arkansas Chouteau Lock and Dam (17), OK Lock and Dam 13, AR Newt Graham Lock and Dam (18), OK Robert S. Kerr Lock and Dam (15), OK Robert S. Kerr Marine Thrminal, OK Sans Bois Navigation Channel, OK W.D. Mayo Lock and Dam (14), OK Webbers Falls Lock and Dam (16), OK Verdigris Arkansas Verdigris Arkansas Arkansas Sans Bois Creek Arkansas Arkansas 394.3 8.7 27.0 54.2 7.7 77.0 538.8 47.4 222.8 90.2 12.8 271.5 60.9 N/A2 401.5 292.8 421.6 339.0 336.2 341.0 319.6 366.6 Canton, OK Elk City, KS Eufaula, OK Fall River, KS Fort Gibson, OK Disney, OK Sand Springs, OK Locust Grove, OK Neodesha, KS Oologah, OK Gore, OK Ibronto, KS Wister, OK Fort Smith, AR to Catoosa, OK Okay, OK Fort Smith, AR Inola, OK Sallisaw, OK Cowlington, OK Keota, OK Redland, OK Gore, OK 1. Navigation miles - McClellan-Kerr Arkansas River Navigation System. 2. As required for channel 9 feet deep. TABLE 19-I INSPECTION OF COMPLETED FLOOD CONTROL PROTECTION PROJECTS (See Section 34 of Txt) Projects Inspected in Fiscal Year Inspection Date Cherry and Red Fork Creeks, OK Deep Fork River, OK Dodge City, KS Enid, OK Flat Rock Creek, OK Florence, KS Hutchinson, KS Iola, KS Jenks, OK Joe Creek, OK Lamed, KS October 1984 November 1984 October 1984 November 1984 October 1984 October 1984 November 1984/September 1985 October 1984 October 1984 October 1984 October 1984 19-16 Feature TULSA, OKLAHOMA DISTRICT INSPECTION OF COMPLETED FLOOD CONTROL PROTECTION PROJECTS (See Section 34 of Text) Projects Inspected in Fiscal Year Marion, KS, Oklahoma City, OK Park City, KS Sand Creek, Newton, KS South Deer Creek, OK Thlsa/West Thisa, OK Wichita and Valley Center, KS Inspection Date October 1984 November 1984 September 1985 October 1984 October 1984 October 1984 November 1984/September 1985 TABLE 19-J4 FLOOD DAMAGES PREVENTED BY CORPS AND NON-CORPS PROJECTS (See Section 35 of 'Txt) Cumulated Damages Name/Owner Fiscal Year Prevented CORPS PROJECTS Birch Lake, OK Broken Bow Lake, OK Canton Lake, OK Copan Lake, OK Council Grove Lake, OK El Dorado Lake, KS Elk City Lake, KS Eufaula Lake, OK Fall River Lake, KS Fort Gibson Lake, OK Fort Supply Lake, OK Great Salt Plains Lake, OK Heyburn Lake, OK Hugo Lake, OK Hulah Lake, OK John Redmond Dam and Reservoir, KS Kaw Lake, OK Keystone Lake, OK Lake Kemp, TX Lake Texoma, OK & TX Marion Lake, KS Oologah Lake, OK Optima Lake, OK Pat Mayse Lake, TX Pearson-Skubitz Big Hill Lake, KS Pine Creek Lake, OK Sardis Lake, OK Skiatook Lake, OK Tenkiller Ferry Lake, OK Toronto Lake, KS Waurika Lake, OK Wister Lake, OK TABLE 19-I (Continued) 1,664,000 3,814,000 5,310,000 2,548,000 25,000 838,000 678,000 938,000 449,000 1,842,000 1,379,000 12,096,000 7,200,000 656,000 8,161,000 105,000 4,701,000 4,084,000 4,058,000 149,000 1,234,000 1,469,000 5,574,000 99,000 2,671,000 3,221,000 5,017,000 4,500,000 15,046,000 6,713,000 13,974,000 14,860,000 208,000 38,876,000 45,961,000 31,029,000 34,083,000 3,064,000 13,246,000 6,381,000 7,092,000 84,599,000 64,368,000 14,287,000 99,386,000 3,129,000 63,276,000 31,367,000 50,934,000 7,000 3,868,000 63,000 10,112,000 2,795,000 11,240,000 12,027,000 28,000,000 15,617,000 65,406,000 19-17 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 19-J FLOOD DAMAGES PREVENTED BY CORPS (Continued) AND NON-CORPS PROJECTS (See Section 35 of Tbxt) Cumulated Damages Name/Owner Fiscal Year Prevented NON-CORPS PROJECTS Altus Reservoir, OK -3,295,000 Bureau of Reclamation Arbuckle Reservoir, OK 52,000 426,000 Bureau of Reclamation Cheney Reservoir, KS 18,000 7,266,000 Bureau of Reclamation Fort Cobb Reservoir, OK -629,000 Bureau of Reclamation Foss Reservoir, OK - 1,272,000 Bureau of Reclamation Grand Lake O' the Cherokees, OK 504,000 39,370,000 Grand River Dam Authority Lake Meredith, TX -6,000 Bureau of Reclamation Lake Hudson, OK 179,000 5,751,000 (Markham Ferry Reservoir) Grand River Dam Authority Mountain Park Reservoir, OK 11,000 535,000 Bureau of Reclamation Norman Reservoir, OK 3,444,000 7,153,000 Bureau of Reclamation LOCAL PROTECTION PROJECTS Cherry and Red Fork Creeks, OK - 1,500,000 Enid, OK - 2,532,000 Flat Rock Creek, OK - 1,000,000 Florence, KS - 7,397,000 Hutchinson, KS - 9,450,000 Iola, KS 549,000 6,197,000 Jenks, OK - 1,126,000 Joe Creek, OK - 11,200,000 Maron, KS -- Oklahoma City, OK - 11,845,000 Sand Creek, Newton, KS - 623,000 Tulsa and West Tulsa, OK 6,160,000 77,422,000 West Branch Chisholm Creek, KS - 4,000 Wichita and Valley Center, KS - 123,557,000 19-18 TULSA, OKLAHOMA DISTRICT TABLE 19-K FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION (See Section 36 of Tbxt) Fiscal Year Study Identification/Name Cost SMALL FLOOD CONTROL PROJECTS NOT SPECIFICALLY AUTHORIZED BY CONGRESS (Section 205) Blackboy Creek, Tulsa, OK 22,063 Box Elder Creek, Apache, OK 9,266 Cat Creek, Claremore, OK 2,222 Coal Creek, Henryetta, OK 27,036 E. Cache St. Lawton, OK 15,942 Haikey Creek, Tulsa, OK 691,185 Kingfisher Creek, OK 53,429 Lamed, KS 148,586 Line Creek and Washita River 37,500 Lil Wichita River, Clay County, TX 1,030 Main Branch Chisholm, Park City, KS 10,090 Merkle Creek, Norman, OK 111,067 North Canadian River Wastewater Plant, Okla City, OK 52,694 Stink/Driftwood Creeks, Burlington, OK 50,608 Whiskey and Rock Creeks, Independence, KS 11,255 TOTAL SMALL FLOOD CONTROL PROJECTS 1243,973 EMERGENCY STREAMBANK AND SHORELINE PROTECTION (Section 14) Camp Creek, Pawnee City, OK 9,933 Carnegie (WWTP), Carnegie, OK 6,300 County Bridge, Washita County, KS 1,519 County Bridge, Washita County, KS 1,038 Deer Creek, Custer County, OK 16,412 Fourth Street Bridge, Florence, KS 37 Neosho River, Emporia, KS 6,600 Neosho River, Lyon County, KS 4,905 North Canadian River, Canadian County, Yukon, OK 4,300 North Canadian River, Pottawatomie County, OK 2,708 Red River, County FM-410, TX 3,308 Red River, Wilbarger County, TX 5,400 Salt Fork, Red River, Elmer, OK 16,436 Sewage Lagoon, Washita River, OK 12,625 STP Falls River, Neodesha, KS 587 Verdigris River, Coffeyville, KS 5 Washita River, Anadarko, OK 12,885 TOTAL EMERGENCY STREAMBANK AND SHORELINE PROTECTION 104,998 SNAGGING AND CLEARING Cottonwood Creek, Guthrie, OK 11,187 FLOOD CONTROL AND COASTAL EMERGENCIES, REHABILITATION 2 Creek Channel and Drainage Ditch 1,256 Billy J. Walck Private Levee 8,940 F. W. Swaney Private Levee 2,605 Flat Rock Valley View Channel Improvement 1,953 Flood Control and Coast Emergency 1,663 Joe Creek Channel Improvement, Tulsa County, OK 36,785 Nation Private Levee, Neosho County, KS 4,584 19-19 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 19-K FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION (Continued) (See Section 36 of Txt) Fiscal Year Study Identification/Name Cost Ruben Abiltz Private Levee 4,960 Skinner Evers Long Private Levee 2,453 Southwest Oklahoma Private Levee Invest (Var) 117,822 Tulsa/West Tulsa Levee, OK 117,544 TOTAL FLOOD CONTROL AND COASTAL EMERGENCIES 300,565 TABLE 19-L GENERAL INVESTIGATIONS (See Sections 46, 47, 48, and 49 of Tbxt) Fiscal Year Study Identification/Name Cost SURVEYS Navigation Studies Arkansas River and Tributaries Hydropower 5,749 Flood Damage Prevention Studies Arkansas River, Great Bend, KS, to Tulsa, OK 263,403 Arkansas River Basin, AR and OK 135,552 Canadian River Basin, OK, TX, and NM 207,551 Poteau River, OK 8,551 Red River Above Denison, TX and OK 162,867 Verdigris River Basin 110,249 Verdigris River, KS and OK 8,908 Arkansas-Red River Basins Solar Energy Investigations 1,161 Comprehensive Studies Arkansas River and Tributaries South-Central Southeast Areas, OK 236,126 East Cache Creek, OK 28,513 Red River Basin, AR, TX, LA, and OK 459,259 Restudy of Deferred Projects Lukfata Lake, OK 69,224 Winfield, KS 198,877 Review of Completed Projects Hugo Lake, OK 126,251 Pine Creek Lake, OK 113,087 Review for Deauthorization Crutcho Creek, OK 4,653 El Dorado, West Branch, Walnut River, KS 6,999 Inventory of Dams - Special Investigations 37,569 Coordination with Other Federal and Non-Federal Agencies and States Soil Conservation Service 5,598 Bureau of Reclamation 6,957 Cooperation with States - Kansas 15,912 Cooperation with States - Oklahoma 8,700 Planning Assistance to States - Texas 28,110 Planning Assistance to States - Kansas 54,589 Planning Assistance to States - Oklahoma 99,949 TOTAL SURVEYS 2,404,364 19-20 TULSA. OKLAHOMA DISTRICT TABLE 19-L GENERAL INVESTIGATIONS (Continued) (See Section 46, 47, 48, and 49 of Thxt) Fiscal Year Study Identification/Name Cost COLLECTION AND STUDY OF BASIC DATA Flood Plain Management Services Flood Plain Management Services 100,266 Technical Services General 166,898 Hydrologic Studies Storm Studies 8,064 TOTAL COLLECTION AND STUDY OF BASIC DATA 275,228 CONTINUATION OF PLANNING AND ENGINEERING Local Protection Arkansas River, Great Bend to Tulsa, Halstead 2,431 Lake Wichita, Holliday Creek, McGrath Creek, TX 103,663 Lake Wichita, Holliday Creek, TX 208,324 Mingo Creek, OK 517,353 Flood Control Reservoirs Parker Lake, OK 520,824 TOTAL CONTINUATION OF PLANNING AND ENGINEERING 1,352,595 ADVANCED ENGINEERING AND DESIGN Navigation Project Big and Little Sallisaw Creeks, OKLocal Protection Great Bend, KS 447,815 Flood Control Reservoirs Douglass Lake, KS 105,425 TOTAL ADVANCED ENGINEERING AND DESIGN 553,240 TABLE 19-M JOBS ACT (P.L. 98-8) See Type Cost Section of to in 'lbxt Project Funding FY 83 FY 84 FY 85 Sep 30,1985 5. Birch Lake New Work Approp. 4,000 - - 4,000 Cost - 4,000 - 4,000 7. Canton Lake Maint. Approp. 25,000 - - 25,000 Cost 18,000 7,000 - 25,000 9. Council Grove Lake Maint. Approp. 15,500 - - 15,500 Cost 12,700 2,800 - 15,500 11. Elk City Lake Maint. Approp. 63,700 - - 63,700 Cost 31,100 32,600 - 63,700 12. Fall River Lake Maint. Approp. 52,500 - - 52,500 Cost 31,500 21,000 - 52,500 19-21 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 19-M (Continued) See Section in TIbxt Project 15. Heyburn Lake 17. Hulah Lake 18. John Redmond Dam and Reservoir 19. Kaw Lake 21. Marion, KS 23. Oologah Lake 24. Optima Lake 30. Toronto Lake 31. Waurika Lake 36. Main Branch Chishom Creek 36. Fourth Street Bridge Florence, KS (Sec 14) 38. Eufaula Lake 39. Fort Gibson Lake 41. Keystone Lake JOBS ACT (P.L. 98-8) Type of Funding New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost New Work Approp. Cost Maint. Approp. Cost Maint. Approp. Cost Maint. Approp. Cost Maint. Approp. Cost New Work Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost 6,000 200 19,000 11,200 20,000 15,000 4,800 75,000 2,400 28,000 3,600 15,500 15,500 37,000 3,000 119,000 67,600 20,000 7,900 12,500 500 41,600 28,100 351,800 45,200 43,000 12,000 110,900 36,600 70,000 30,900 51,000 42,000 45,000 21,500 -1,900 3,900 7,800 -2,400 17,600 10,200 -71,900 700 24,400 -4,000 30,000 15,800 12,100 12,000 13,500 273,300 25,000 74,300 -14,000 21,800 9,000 23,500 3 1 - - 4,100 - 4,100 - 19,000 - 19,000 - 17,600 - 17,600 - 15,000 - 15,000 - 3,100 - 3,100 - 28,000 - 28,000 - 15,500 - 15,500 - 33,000 - 33,000 - 119,000 5,600 119,0001 - 20,000 - 20,000 - 12,500 - 12,500 - 41,600 - 41,600 - 351,800 0,100 328,600 6,000 37,000 - 37,000 - 110,900 - 110,900 - 56,000 3,300 56,000 - 51,000 - 51,000 - 45,000 - 45,000 19-22 Cost to FY 83 FY 84 FY 85 Sep 30,1985 TULSA, OKLAHOMA DISTRICT TABLE 19-M JOBS ACT (Continued) (P.L. 98-8) See Type Cost Section of to in bText Project Funding FY 83 FY 84 FY 85 Sep 30,1985 42. Lake Texoma New Work Approp. 100,000 - - 100,000 Cost - 100,000 - 100,000 Maint. Approp. 625,700 - - 625,700 Cost 49,200 576,500 - 625,700 43. Robert S. Kerr Lock and Dam Maint. Approp. 207,600 - - 207,600 Cost 191,600 16,000 - 207,600 44. Tenkiller Ferry Lake Maint. Approp. 27,000 - - 27,000 Cost 19,500 7,500 - 27,000 1. Work for fiscal year 1984 was completed in fiscal year 1985 after the default of the contractor in September 1984. 19-23 KANSAS CITY, MO., DISTRICT* The district comprises a portion of southwestern Iowa; northwestern, central, and western Missouri; northern Kansas; southern Nebraska; and a portion of northeastern Colorado embraced in drainage basin of the Missouri River and tributaries from Rulo, Nebraska, to the mouth. Report on navigation project for section of Missouri River from Sioux City, Iowa, to Rulo, Nebraska, is in report of Omaha District. IMPROVEMENTS Navigation 1. Missouri River, Sioux City, IA, to Mouth (Rulo, NE, to Mouth)........ Page 20-2 Flood Control 2. Blue River Channel, Kansas City, MO ....... 20-2 3. Clinton Lake, Wakarusa River, KS ......... 20-2 4. Harlan County Lake, Republican River, N E .............................. 20-3 5. Hillsdale Lake, Big Bull Creek, KS ......... 20-3 6. Kanopolis Lake, Smoky Hill River, KS ...... 20-3 7. Lawrence, Kansas River, KS.............. 20-3 8. Little Blue River Channel Improvement, Little Blue River, MO .................... 20-4 9. Little Blue River Lakes, MO .............. 20-4 10. Long Branch Lake, Little Chariton River, MO ........................... 20-4 11. Melvern Lake, Marais des Cygnes (Osage) River, KS ..................... . 20-5 12. Milford Lake, Republican River, KS ........ 20-5 13. Missouri River Levee System, IA, NE, KS, and MO (Rulo, NE to Mouth) .......... 20-5 14. Perry Lake, Delaware River, KS ........... 20-5 15. Pick-Sloan Missouri Basin Program (Kansas City Dist.) ..................... . 20-6 16. Pomme de Terre Lake, Pomme de Terre River, MO ........................ 20-6 17. Pomona Lake, One Hundred Ten Mile Creek, KS ......................... 20-6 18. Rathbun Lake, Chariton River, IA .......... 20-6 19. Smithville Lake, Little Platte River, MO .... 20-7 20. Tuttle Creek Lake, Big Blue River, KS ...... 20-7 21. Wilson Lake, Saline River, KS ............. 20-7 22. Scheduling Flood Control Reservoir Operations ................... 20-7 Flood Control (cont.) 23. Inspection of Completed Flood Control Projects.............. 24. Inspection of Non-Federal Levees .... 25. Flood Control Work Under Special Authorization .................... Page ...... 20-7 ...... 20-8 ...... 20-8 Multiple Purpose Projects Including Power 26. Harry S. Truman Dam and Reservoir, Osage River, MO ............... 20-9 27. Stockton Lake, Sac River, MO ............. 20-9 General Investigations 28. General Investigations ...... ............. 20-10 Tables Table 20-A Cost & Financial Statement ....... 20-11 Table 20-B Authorizing Legislation ........... 20-14 Table 20-C Other Authorized Navigation Projects ..................... . 20-18 Table 20-D Not Applicable Table 20-E Other Authorized Flood Control Projects .............. ......... 20-19 Table 20-F Not Applicable Table 20-G Deauthorized Projects ............ 20-20 Table 20-H Missouri River Levee System ...... 20-20 Table 20-I Kansas City District Projects Included in Pick-Sloan Missouri Basin Program ................. 20-21 Table 20-J Inspection of Completed Flood Control Projects ................. 20-22 Table 20-K Active General Investigations ...... 20-23 Table 20-L Flood Control Activities Under Special Authorization ............. 20-24 20-1 . ..... REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Navigation 1. MISSOURI RIVER, SIOUX CITY, IA, TO MOUTH (RULO, NE, TO MOUTH) Location. Jefferson, Madison, and Gallatin Rivers conjoin at Three Forks, Mont., to form the Missouri River, which flows southeasterly 2,315 miles (1960 mileage) across or along seven states to the Mississippi River, 17 miles above St. Louis. For description see page 1149, Annual Report for 1932. The river is commercially navigable from Sioux City, Iowa to the mouth, a distance of 732 miles. The portion of project in Kansas City District extends from Rulo, Nebraska to the mouth, a distance of 498 miles. Previous projects. For details see page 1891 of Annual Report for 1915, and pages 1153 and 1175 of Annual Report for 1938. Existing project. A channel of 9-foot depth and width not less than 300 feet, obtained by revetment of banks, construction of permeable dikes to contract and stabilize the channel, cutoffs to eliminate long bends, closing minor channels, removal of snags, and dredging as required. The improved reach within the Kansas City District extends from the mouth to the upper end of Rulo Bend, a distance of 498.4 miles. The Bank Stabilization and Navigation features of the project were completed in September 1980. For the reach from Rulo, Nebraska to the mouth, the total construction cost was $237,942,190 including $8,665,594 for previous project. River access sites have been completed at 11 locations. Ordinary and extreme fluctuations of stage are 16 and 38 feet, respectively. Local cooperation. Cooperation from benefited localities may be required where any improvement may confer special benefit. The receipt of contributions from private parties are to be expended along with Government funds upon authorized work where such work would be in the interest of navigation, as authorized by 1915 Rivers and Harbors Act. Secretary of the Army approved general principle of cooperative construction on Missouri River below Kansas City on basis that 25 percent of cost of any special installation shall be paid by the United States and 75 percent by local interests. Total contributed by local interests in cooperation with the United States from 1918 to June 30, 1964, was $675,663, of which $8,647 was returned to contributors. Local interests must share in cost of recreation facilities in accordance with provisions of the Federal Water Project Recreation Act of 1965. Local interests have contributed $171,816 for cost sharing on construction of recreation in addition to constructing portions of the facilities. Terminal facilities. A listing of terminal facilities are included in Missouri River Navigation Charts and can be obtained from Kansas City District Engineers for a small fee. Operations during fiscal year. The 1974 Base Line Study of the reach of the Missouri River in the Kansas City District estimated recreation use on the river at 1,250,000 recreation days annually. The projected tonnage on the river for FY 1985 is approximately 2.0 million. Maintenance: Repair of dikes and revetments by contract. In addition, following work was accomplished by hired labor: Construction of environmental gaps and dike and revetment repair, real estate management, channel reconnaissance, condition studies, surveys and mapping, stream gaging, environmental studies and special working data, engineering and design, surveys and layout of construction, and supervision and administration. There was no dredging because no significant bars or shoals developed. Flood Control 2. BLUE RIVER CHANNEL, KANSAS CITY, MO Location. Along the Blue River and tributaries in Jackson County, Missouri. Existing project. Preliminary plans consist of 12.5 miles of improved channel along the Blue River within Kansas City, Missouri. Estimated Federal cost through construction of the project (1985) is $141,000,000 and estimated non-Federal cost of lands, damages and relocations is $21,100,000. Local cooperation. Section 2, Flood Control Act of June 22, 1936, applies. The city of Kansas City, Missouri, passed a resolution of intent on December 9, 1975 to provide the required assurances of local cooperation when requested. The Section 221 agreement was signed by the Kansas City District Engineer on September 8, 1983. Operations during fiscal year. Preconstruction planning is complete and final designs are underway. Construction of the first and second channel contracts were nearing completion and negotiations with railroad companies were underway. 3. CLINTON LAKE, WAKARUSA RIVER, KS Location. Damsite is on Wakarusa River about 4 miles southwest of Lawrence, Kansas, in Douglas County. Lake extends into Shawnee and Osage Counties, Kansas. Existing project. An earthfill dam about 9,250 feet long constructed to a height of about 114 feet with an uncontrolled spillway in left abutment. Total reservoir storage capacity 397,200 acre-feet (258,300 for flood control, 28,500 for sediment reserve, and 110,400 of multipurpose storage for municipal and industrial water supply and recreation). Cost of constructing the completed project was $57,415,433. Construction was initiated in January 1972 and the project was placed in operation in November 1977. Local cooperation. Section 2, Flood Control Act of June 28, 1938, applies. Reimbursement in the estimated amount of $6,768,000 is required for water supply storage in accordance with Water Supply Act of 1958. A contract was signed by the State on September 6, 1978 and was approved by the Secretary of the Army on Oc- 20-2 KANSAS CITY, MO., DISTRICT tober 30, 1978. Utilization of storage was initiated in December 1979. Repayment also began at that time. Operations during fiscal year. Visitation for FY 1985 was 1,252,600 visitor days. Maintenance: Activities consisted of forestation and ordinary operation and maintenance. 4. HARLAN COUNTY LAKE, REPUBLICAN RIVER, NE Location. Dam is on main stem of Republican River about 235 miles above confluence of stream with Smoky Hill River. Site is in Harlan County, about 3 miles east of Republican City and 13 miles west of Franklin, Nebraska. Existing project. An earthfill dam about 107 feet above streambed with a total length of 11,827 feet, including a gate-controlled, concrete, gravity-type spillway section near center of dam. Reservoir provides storage capacity of 850,000 acre-feet (500,000 for flood control and 350,000 for irrigation and sedimentation allowance). Initial cost of constructing the project was $45,279,532. Total Federal cost of project , including $1,017,623 for major rehabilitation work and $1,832,394 supplemental recreation development (Code 710), is $48,129,549. Construction of the project was initiated in August 1946. Project was placed in operation in December 1952. Major rehabilitation work was completed in FY 1968. Local cooperation. Section 2, Flood Control Act of 1938, applies. Operations during fiscal year. Visitation for FY 1985 was 919,500 visitor days. Maintenance: Activities included forestation and other ordinary operation and maintenance activities. 5. HILLSDALE LAKE, BIG BULL CREEK, KS Location. The project is located approximately 12 miles above the mouth of Big Bull Creek, a tributary of the Marais des Cygnes River and about 15 miles southwest of the Kansas City metropolitan area in Miami County, Kansas. Existing project. An earthfill embankment about 11,600 feet long (including approximately 3,300 feet of dike section) about 75 feet above rising valley flood plain. The spillway is gravity type uncontrolled and the outlet works are controlled. The total reservoir storage capacity is 160,000 acre-feet (81,000 for flood control, 11,000 for sediment reserve, and 68,000 for multipurpose storage for water supply, water quality control, and recreation). Construction was initiated in December 1974 and project was placed in operation in October 1981. Federal cost of construction is $64,021,400. Local cooperation. Section 2, Flood Control Act 1938, applies. Local interests must make reimbursement of $23,342,756 for water supply storage in accordance with Water Supply Act of 1958. The Kansas Water Resources Board signed a contract in January 1974, approved by the Secretary of the Army in April 1974, for the entire 53,000 acre-feet of water supply storage. Local interests have shown no interest in sponsoring recreational development at this time. Therefore, only minimum recreational facilities have been built. Operations during fiscal year. Visitation for FY 1985 was 375,900 visitor days. Maintenance: Activities included road resurfacing work and ordinary operation and maintenance. 6. KANOPOLIS LAKE, SMOKY HILL RIVER, KS Location. Dam is on Smoky Hill River about 19 miles west and 16 miles south of Salina, Kansas, and about 205 river miles above mouth of stream. Existing project. An earthfill dam about 131 feet above streambed, having a total length of 15,360 feet, including 4,070 feet of dike section on left abutment and 2,550 feet of dike section on right abutment. The reservoir provides storage capacity of 450,000 acre-feet, (400,000 for flood control and 50,000 for recreation and streamflow regulation). Outlet works and spillway are in right abutment. Initial cost of constructing the project was $12,327,735. Total Federal cost of project, including $249,492, supplemental recreational development (Code 710), is $12,577,227. Construction was initiated in June 1940 and project was placed in operation in May 1948. Local cooperation. Section 2, Flood Control Act of 1938, applies. Operations during fiscal year. Visitation for FY 1985 was 516,400 visitor days. Maintenance: Activities included alignment monument repair, replacement of piezometer tubes, and ordinary operation and maintenance. 7. LAWRENCE, KANSAS RIVER, KS Location. On Kansas River about 50 miles above its mouth at Lawrence, Douglas County, Kansas. Existing project. Levees along both banks of Kansas River and right bank of Mud Creek, channel improvement for Mud Creek, bank protection and appurtenant facilities for protection of North Lawrence, Kansas. Since the city of Lawrence is no longer interested in sponsoring the South Lawrence unit, this unit was deleted from the project cost estimate and reclassified to an inactive status. By letter dated 9 January 1970, the city of Lawrence indicated an interest in developing a recreational facility on lands obtained for the Lawrence Flood Protection Project. Federal cost of construction is $8,620,111 and estimated non-Federal cost of lands, damages, and relocations is $2,130,000. Construction of the project was initiated July 31, 1967. The Kansas River portion was completed in March 1972 and the Mud Creek portion in July 1978. Government construction of the riverfront recreation facilities was completed on 9 July 1981. The city of Lawrence completed their portion of construction on this recreation area in the summer of 1984. 20-3 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Local cooperation. Section 3, Flood Control Act of June 22, 1936, applies, Board of Commissioners of city of Lawrence furnished required assurances June 8, 1965. The city of Lawrence signed a Section 221 agreement for recreation development on September 13, 1979. The agreement stated Government costs to be $204,305 and city costs to be $88,901 for construction. 8. LITTLE BLUE RIVER CHANNEL IMPROVEMENT, LITTLE BLUE RIVER, MO Location. The project is located along the Little Blue River and extends from the head of Missouri River Levee Unit R 351, 22 miles upstream to the vicinity of Wildwood Creek in Jackson County, Missouri. Existing project. The improvements consist of straightening and enlarging the Little Blue River channel from the head of Missouri River Levee Unit R 351, near Blue Mills Road, upstream to the vicinity of Wildwood Creek, reducing the length of this section from 20.4 to about 15 miles. Alteration of six highway bridges and construction of five new highway bridges and one railroad bridge were required. Improvements in the vicinity of Lake City Army Ammunition Plant consists of diversion of West Fire Prairie Creek into the Little Blue River and construction of a levee. Estimated Federal cost through construction of the project (1984) is $26,200,000 and estimated non-Federal cost is $3,390,000. Construction was initiated in December 1974. Local cooperation. Section 3, Flood Control Act of June 22, 1936, applies to the Little Blue River channel improvement works. Jackson County, Missouri, passed a bond issue for sponsorship of the project. Assurances of local cooperation were furnished July 31, 1973. Operations during fiscal year. Project is 97 percent complete. Stage 5, Phase II, Lake City, is nearing completion. 9. LITTLE BLUE RIVER LAKES, MO Location. This project consists of two lakes in Jackson County, Missouri, located in Kansas City, Missouri, and suburban communities. The Blue Springs Lake site is on the East Fork of the Little Blue River about one-half mile south of U.S. Highway 40 and the Longview Lake site is on the main stem at approximately 109th Street. Existing project. The Blue Springs dam will be an earthfill embankment about 2,500 feet long and rising about 78 feet above the streambed, with an uncontrolled service spillway and uncontrolled outlet conduit. The total reservoir storage capacity will be 26,600 acre-feet (15,700 for flood control, 10,600 for multipurpose storage for water quality and recreation, and 300 for sedimentation). The Longview dam will be an earthfill embankment about 1,900 feet long and rising about 120 feet above the streambed, with an uncontrolled service spillway and an uncontrolled outlet conduit. The total reservoir storage capacity will be 46,900 acre-feet (24,300 for flood control and 20,600 for multipurpose storage for water quality and recreation and 2,000 for sedimentation). Estimated Federal cost (1985) for both lakes through construction of the project is $137,000,000. Construction was initiated in September 1977. Local cooperation. Section 2 of the Flood Control Act of June 28, 1938, applies. Local interests must share in separable cost allocated to recreation in accordance with Federal Water Project Recreation Act of 1965. The Jackson County Legislature approved a recreation costsharing contract on July 5, 1974 which was approved by the Secretary of the Army on June 24, 1976. A supplemental agreement, signed by Jackson County officials on June 5, 1978, and approved by the Secretary of the Army January 10, 1979, revised the existing contract to include additional costs involved in raising the multipurpose pool elevation at the Blue Springs Lake. Estimated reimbursement for recreation is $14,870,000, of which $340,000 will be accomplished during construction by local interests. Operations during fiscal year. Contracts were underway for Longview and Blue Springs Lakes for relocation of roads, utilities, access roads, recreation facilities, and dam construction. Project is 90 percent complete. Land acquisition is complete. 10. LONG BRANCH LAKE, LITTLE CHARITON RIVER, MO Location. Damsite is on East Fork of Little Chariton River in north-central Missouri about 1 mile west of Macon in Macon County. Existing project. An earthfill dam about 3,800 feet long and about 71 feet high with an uncontrolled outlet conduit and an uncontrolled service spillway in right abutment. Total reservoir storage capacity will be 65,000 acre-feet (29,000 for flood control, 4,000 for sediment reserve, and 32,000 of multipurpose storage for water supply, water quality control, fish and wildlife, and recreation). Estimated Federal cost (1985) is $20,453,000, and estimated non-Federal cost is $3,747,000. Construction was initiated in March 1973. Project was placed in useful operation for flood control on September 1, 1980. Local cooperation. Section 2, Flood Control Act of June 28, 1938, applies. Local interests must make reimbursement of $5,586,000 for water supply storage in accordance with Water Supply Act of 1958 and share in separable cost of $3,747,000 allocated to recreation in accordance with Federal Water Project Recreation Act of 1965. On September 15, 1972 the Secretary of the Army approved a contract signed by the city of Macon, Mo. for water supply and recreation development. Missouri State agencies indicated their intent to sponsor future water supply and signed a contract on June 17, 1977 to sponsor recreational development in lieu of city of Macon. After review by the Office of the Secretary of the Army, the state signed the contract in December 1979 and it was approved by the Secretary of the Army on April 18, 1980. 20-4 KANSAS CITY, MO., DISTRICT Operations during fiscal year. Visitation for FY 1985 was 568,100 visitor days. Stage 3 recreation facilities were essentially completed. Project is 97 percent complete on scheduled work. The remaining work is construction of recreation facilities. Maintenance: Activities consisted of repair of the service bridge and ordinary operation and maintenance. 11. MELVERN LAKE, MARAIS DES CYGNES (OSAGE) RIVER, KS Location. Damsite is on Marais des Cygnes (Osage) River in Osage County, Kansas, about 2 miles west of Melvern, Kansas. Existing project. An earthfill dam about 9,700 feet long and about 98 feet high with an uncontrolled chutetype spillway in left abutment. Total reservoir storage capacity is 363,000 acre-feet (200,000 for flood control, 26,000 for sediment reserve, and 137,000 of multipurpose storage for water quality control and recreation). Cost of constructing the completed project was $37,436,530. Construction was initiated in July 1967 and the project was placed in operation in August 1972. Local cooperation. Section 2, Flood Control Act of 1938, applies. Operations during fiscal year. Visitation for FY 1985 was 970,400 visitor days. Maintenance: Activity consisted of construction of breakwater and ordinary operation and maintenance. 12. MILFORD LAKE, REPUBLICAN RIVER, KS Location. Damsite is on Republican River near village of Alida and about 8 miles downstream from Milford, Geary County, Kansas, and about 10 miles above confluence of Republican and Smoky Hill Rivers which form Kansas River near Junction City, Kansas. Existing project. An earthfill dam about 6,300 feet long and 126 feet high with an uncontrolled servicechute spillway in a saddle on right abutment. Total reservoir storage capacity is 1,160,000 acre-feet (700,000 for flood control, 160,000 for sediment reserve and 300,000 of multipurpose storage for water supply, water quality control, and recreation). Water supply storage is included in project at request of Governor of Kansas under provisions of Federal Water Supply Act of 1958. Initial cost of constructing the completed project was $48,268,843. Total Federal cost of project, including $1,297,649 supplemental recreational development (Code 710), is $49,566,492. Construction was initiated in July 1961. Project was placed in operation in June 1965. Local cooperation. Section 2, Flood Control Act of 1938, applies. Local interests must make reimbursement of $13,045,576 for water supply storage in accordance with Water Supply Act of 1958. Utilization of storage has not been initiated. Reimbursement was initiated, at the option of the State, in September 1976. Operations during fiscal year. Visitation for FY 1985 was 1,315,100 visitor days. Maintenance: Activities included continuation of seismic reevaluation, completion of repair of gates, and ordinary operation and maintenance. 13. MISSOURI RIVER LEVEE SYSTEM, IA, NE, KS, AND MO (RULO, NE, TO MOUTH) Location. On both banks of Missouri River from Sioux City, Iowa, about 760 miles to mouth near St. Louis, Missouri. Portion of project in Kansas City District extends from Rulo, Nebraska, 498 miles to mouth. Existing project. A series of levee units and appurtenant works along both sides of Missouri River from Sioux City, Iowa, to the mouth, for protection of agricultural lands and small communities against floods. Estimated Federal cost (1985) for the active portion of the project from Rulo, Nebraska to mouth is $242,500,000. Costs of $25,400,000 for lands and damages to be borne by local interests. Remaining portion of project consists of units on which planning and construction are being delayed pending completion of restudy to assure that additional levee construction is economically justified. Cost estimate for deferred and inactive portion of project Rulo, Nebraska, to mouth is $253,558,000 (1964 price level), of which $233,412,000 is Federal cost for construction and $20,146,000 for lands and damages to be borne by local interests. Construction of the project was initiated in June 1948. Local cooperation. Section 3, Flood Control Act of 1936, applies. Fully complied with for all completed units and units under construction. Sponsor for Unit L 345-330 has optioned the major part of lands for rightsof- way. Because of anticipated changes as a result of the National Environmental Policy Act of 1969, the District advised the sponsor to suspend condemnation proceedings for remaining requirements pending development of an alternate plan. Local sponsors provide all operation and maintenance. Operations during fiscal year. Status of individual units of active portion of project at end of fiscal year is shown in Table 20-H on Missouri River levee system. Remedial work on L 246 was deferred pending submission and approval of reconnaissance report. Unit L15 was reclassified to the active category. Planning on remaining active units continued. 14. PERRY LAKE, DELAWARE RIVER, KS Location. Damsite is on Delaware River about 5 miles above mouth in Jefferson County, Kansas, and about 3 miles north of Perry, Kansas. Existing project. An earthfill dam about 7,750 feet long constructed to an elevation about 95 feet above valley floor with gated-outlet works and an uncontrolled spillway in left abutment. Total reservoir storage capacity is 770,000 acre-feet (480,000 for flood control, including 140,000 for sediment reserve and 150,000 of multipurpose storage for water supply, water quality 20-5 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 control, and recreation). Water supply storage is included in project plan at request of State of Kansas under provisions of Federal Water Supply Act of 1958. Initial cost of constructing the completed project was $48,371,706. Total Federal cost of project, including $724,212 supplemental recreational development (Code 710), is $49,095,918. Construction was initiated in March 1964 and the project was placed in operation in January 1969. Local cooperation. Section 2, Flood Control Act of 1938, applies. Local interests must make reimbursement of $9,208,342 for water supply storage in accordance with Water Supply Act of 1958. Utilization of storage has not been initiated. Reimbursement was initiated at the option of the State in September 1978. Operations during fiscal year. Visitation for FY 1985 was 1,401,100 visitor days. Maintenance: Activity included alignment monument repair, renovation of Slough Creek PUA, and ordinary operation and maintenance. 15. PICK-SLOAN MISSOURI BASIN PROGRAM (KANSAS CITY DIST.) Location. Flood control improvements included in this project are on and along the Missouri River and several of its principle tributaries, in States comprising the Missouri River Basin. Existing project. The Pick-Sloan Missouri Basin program for flood control and other purposes in Missouri River Basin provides for levees along Missouri River between Sioux City, Iowa, and the mouth, floodprotection works at certain municipalities, and reservoirs on main stem of Missouri River and on tributaries for control of flooding. (See Table 20-B for authorizing legislation and Table 20-I on Kansas City District projects included in Pick-Sloan Missouri Basin program.) See individual project reports. 16. POMME DE TERRE LAKE, POMME DE TERRE RIVER, MO Location. Dam is on main stem of Pomme de Terre River, about 44 miles above mouth of stream in Hickory County, Missouri. The lake extending upstream into Polk County, Missouri. Site is about 3 miles south of Hermitage, Missouri, and 20 miles north of Bolivar, Missouri. Existing project. An earth and rockfill dam about 4,630 feet long constructed to about 155 feet above riverbed and a dike section on left abutment about 2,790 feet long, providing storage capacity of 650,000 acre feet (407,000 for flood control and 243,000 for sedimentation and multi-purpose). Initial cost of constructing the completed project was $14,946,784. Total estimated Federal cost of project, including $329,140 area redevelopment and $2,089,522 supplemental recreational development (Code 710), is $17,365,452. Construction was initiated in January 1957 and the project was placed in useful operation in October 1961. Local cooperation. Section 2, Flood Control Act of 1938, applies. Operations during fiscal year. Visitation for FY 1985 was 1,159,100 visitor days. Maintenance: Activities included completion of construction of maintenance building, and ordinary operation and maintenance. 17. POMONA LAKE, ONE HUNDRED TEN MILE CREEK, KS Location. Dam is on One Hundred Ten Mile Creek, a tributary of Marais des Cygnes (Osage) River, 7 miles above mouth of stream in Osage County, Kansas, about 7 miles northwest of Pomona, Kansas, and 34 miles upstream from Ottawa, Kansas. Existing project. An earthfill dam 7,750 feet long constructed to an average height of about 85 feet above streambed, with gated-outlet works and an ungated chute-type spillway near left abutment. Total reservoir storage capacity is 230,000 acre-feet (160,000 for flood control, 14,000 for sediment reserve, and 56,000 of multipurpose storage for water quality control and recreation). Initial cost of constructing the completed project was $13,272,108. Total estimated Federal cost of project, including supplemental recreational development $731,130 (Code 710), is $14,003,238. Construction began in July 1959 and the project was placed in operation in October 1963. Local cooperation. Section 2, Flood Control Act of 1938, applies. Pomona has water supply reimbursement under Water Supply Act of 1958 totaling $71,018. Operations during fiscal year. Visitation for FY 1985 was 623,400 visitor days. Maintenance: Activities consisted of ordinary operation and maintenance. 18. RATHBUN LAKE, CHARITON RIVER, IA Location. Damsite is on Chariton River about 7 miles north of Centerville and 1 mile north of town of Rathbun, Appanoose County, Iowa. Existing project. An earthfill dam 10,600 feet long constructed to an elevation about 86 feet above valley floor, with gated-outlet works and an uncontrolled service chute with paved sill spillway about a mile upstream from left abutment. Total reservoir storage capacity is 552,000 acre-feet (339,000 for flood control, 24,000 for sediment reserve and 189,000 of multipurpose storage for navigation, water quality control, and recreation). Initial cost of constructing the project was $27,033,210. Total Federal cost of project, including $588,948 supplemental recreation development (Code 710), is $27,622,158. Construction of the project was initiated in September 1964 and completed in November 1969. The operating plan for this project was revised to reduce flood control releases during critical times of the year to allow local farmers better access during planting and harvesting and to facilitate field drainage and drying out. The revised plan has resulted in more frequent high pool elevations than anticipated, which has inun- 20-6 KANSAS CITY, MO., DISTRICT dated roads and recreation facilities. A shoreline erosion study was accomplished and a supplement to the master plan has been approved recommending relocation of recreation facilities and bank stabilization affected by the higher lake levels. Local cooperation. Section 2, Flood Control Act of 1938, applies. Operations during fiscal year. Visitation for FY 1985 was 1,136,200 visitor days. Maintenance: Activities included resurfacing road across dam, relocation of recreation facilities, modification of the administration building, and ordinary operation and maintenance activities. 19. SMITHVILLE LAKE, LITTLE PLATTE RIVER, MO Location. Damsite is on Little Platte River about 1 mile northeast of Smithville and about 5 miles north of Kansas City, in Clay and Clinton Counties, Missouri. Existing project. Earthfill dam about 4,200 feet long and 95 feet high with an uncontrolled service spillway. A dike about 2,400 feet long crosses a saddle in left abutment. Total reservoir storage capacity is 246,500 acre-feet (92,000 for flood control, 52,300 for sediment reserve, and 102,200 of multipurpose storage for water supply, water quality control, and recreation). Estimated Federal cost (1985) through construction of the project is $87,651,315. Construction was initiated in November 1973 and the project was placed in operation in March 1982. Local cooperation. Section 2, Flood Control Act of June 28, 1938, applies. Reimbursement of $24,000,000 will be required for water supply storage in accordance with Water Supply Act of 1958 and reimbursement of $7,500,000 will be required for recreation development in accordance with Federal Water Project Recreation Act of 1965. Additional non-Federal contribution for recreation amounts to $737,000. All contracts for local cooperation were approved by the Secretary of the Army on November 27, 1972. Operations during fiscal year. Visitation for FY 1985 was 1,407,600 visitor days. Project is 99 percent complete. Project is' complete except for road resurfacing in the recreation areas.Maintenance: Activities consisted of installation of relief wells and ordinary operation and maintenance. 20. TUTTLE CREEK LAKE, BIG BLUE RIVER, KS Location. Dam is on main stem of Big Blue River, about 12 miles above mouth of stream in Riley and Pottawatomie Counties, Kansas. Site is about 12 miles northwest of Manhattan, Kansas. Existing project. An earth and rock dam 7,500 feet long and 157 feet high. Total reservoir storage capacity is 2,346,000 acre-feet (1,933,000 for flood control, 228,000 for sediment reserve and 185,000 for multipurpose storage, for low flow regulation, navigation, and recreation). Initial cost of constructing the completed project was $80,051,031. Total Federal cost of project, including $533,048 supplemental recreational development (Code 710), is $80,584,079. Construction began in October 1952. Project was placed in operation in July 1962. Local cooperation. Section 2, Flood Control Act of 1938, applies. Operations during fiscal year. Visitation for FY 1985 was 925,000 visitor days. Maintenance: Activity included boundary monumentation and ordinary operation and maintenance. 21. WILSON LAKE, SALINE RIVER, KS Location. Dam is on Saline River about 130 miles above its mouth, near eastern edge of Russell County, Kansas, about 50 miles west of Salina, 10 miles north of Wilson, and 20 miles east of Russell, Kansas. Existing project. An earthfill dam about 5,600 feet long and 160 feet high with a gated-outlet works, chute spillway, and structural provision for irrigation. Total reservoir storage capacity is 776,000 acre-feet (511,000 for flood control, 40,000 for sediment reserve and 225,000 multipurpose storage for irrigation, navigation, and low flow regulation). Initial cost of constructing the project was $20,015,023. Total Federal cost of project, including $448,344 supplemental recreational development (Code 710), is $20,463,367. Construction began in April 1961 and the project was placed in operation in December 1964. Local cooperation. Section 2, Flood Control Act of 1938, applies. Operations during fiscal year. Visitation for FY 1985 was 691,600 visitor days. Maintenance: Activity consisted of ordinary operation and maintenance. 22. SCHEDULING FLOOD CONTROL RESERVOIR OPERATIONS Under sections 7 and 9, 1944 Flood Control Act, the Corps is responsible for detailed scheduling of operations concerning storage capacity reserved for or assigned to flood control in reservoirs constructed by Bureau of Reclamation as well as those constructed by the Corps. 23. INSPECTION OF COMPLETED FLOOD CONTROL PROJECTS Flood Control Act of June 22, 1936, P.L. 738, and subsequent acts require local interests to furnish assurances that they will maintain and operate certain local protection projects after completion in accordance with regulations prescribed by the Secretary of the Army. District Engineers are responsible for administration of these regulations within boundaries of their respective district. (See table 20-J on inspection of completed flood control projects.) 20-7 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 24. INSPECTION OF NON-FEDERAL LEVEES Non-federal flood protection works constructed or rehabilitated under PL 84-99 must be inspected by the Corps of Engineers to assure compliance with local cooperation agreements. 25. FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION Emergency flood control activities-repair, flood fighting, and rescue work (Public Law 99, 84th Congress, and Antecedent Legislation). Operations for period October 1, 1984 thru September 30, 1985 were as follows: Disaster Preparedness Program, includes planning, training, inspection, supplies and equipment and personnel. Flood Fighting and Rescue Work, for one flood event on the Missouri River and tributaries. Rehabilitation of both non-federal farm levees, and federal authorized levees and control works damaged as a direct result of flooding. (See Table 20-L for costs.) Emergency Bank Protection (Sec. 14, 1946 Flood Control Act, Public Law 526, 79th Cong., July 24, 1946) as amended. Each project must be complete in itself, economically and environmentally justified, and limited to a Federal cost of not more than $250,000. The local sponsor must agree to provide without cost to the United States, all lands, easements, and rights-of-way; Hold and save the United States free from damages; Maintain and operate the project after completion; and assume all project costs in excess of the Federal cost limitation of $250.000 Construction activity during this period under this heading were as follows: South Fork Big Nemaha River, Dubois Bridge, Pawnee County, NE - Construction was completed in May 1985 on a project to protect a county road and bridge. Project consisted of stone fill revetments, dikes, and bank paving. North Fork Big Nemaha River, Elk Creek Sewage Lagoons, Johnson County, NE - Construction was completed in April 1985 on a project to protect the city's sewage lagoons. The project consisted of a minor alteration of one of the existing sewage lagoons, grading the eroding riverbank and paving with stone. West Fork Grand River, Isadora Bridge, Worth County, MO - Construction was completed in February 1985 on a project to protect a county road and bridge. The project consisted of a stone fill revetment with tieback dikes. North Fork Big Nemaha River, County Road, Richardson County, NE - Construction was completed October 1984 on a project to protect a county road. The project consisted of a revetment with baffle dikes. Little Blue River, Fike Bridge, Clay County, NE -Construction was completed in December 1984 on a project to protect a county road and bridge. The project consisted of board fence dikes, hardpoints, and stone fill. Little Blue River, Pawnee Ranch Bridge, Clay County, NE - Construction was completed in December 1984 on a project to protect a county road and bridge. The project consisted of board fence dikes placed at 50-foot intervals along the eroding bankline. Little Blue River, Spring Ranch Bridge, Clay County, NE - Construction was completed in December 1984 on a project to protect a county road and bridge. The project consisted of board fence dikes placed at 50-foot intervals along the eroding bankline. Little Blue River, Lipovsky Bridge, NE, Clay County, NE - Construction was completed in December 1984 on a project to protect a county road and bridge. The project consisted of stone fill and a revetment. Tarkio River, Coin Sewage Lagoons, Page County, IA - Construction was completed in September 1984 on a project to protect the city's sewage lagoons. The project consisted of a revetment, baffle dikes, and hardpoints. South Fork Wolf River, County Bridge, Brown County, KS - Construction was completed in September 1985 on a project to protect a county road and bridge. The project consisted of a stone fill revetment with a baffle dike and stone bank paving. Little Blue River, Gilead Bridge, Thayer County NE -Construction was completed in September 1985 on a project to protect a county road and bridge. The project consisted of a stone fill revetment with baffle dikes. Marais des Cygnes, Quenemo Sewage Lagoons, Osage County, KS - Construction was completed in July 1985 on a project to protect the city's sewage lagoons. The project consisted of stone fill revetments with tieback dikes and a grouted drainway. Snagging and Clearing (Sec. 208, 1954 Flood Control Act, Public Law 780, 83d Cong.) September 3, 1954, as amended. No operations during this period. Small Flood Control Projects Not Specifically Authorized by Congress (Sec. 205, 1948 Flood Control Act, Public Law 858, 80th Cong., June 30, 1948, as amended). Each project selected must be complete in itself, economically and environmentally justified, and limited to a Federal cost of not more than $4 million. The local sponsoring agency must agree to provide without cost to the United States, all lands, easements, and rightsofway, including highway, highway bridge, and utility relocations and alterations; hold and save the United States free from damages; maintain and operate the project after completion; assume all project costs in excess of the Federal cost limit; and prevent future encroachments on improved channels. (Railroad relocations are a Federal cost.) Under proposed cost-sharing revisions, the local sponsor could be required to pay 50% of the cost of detailed 20-8 KANSAS CITY, MO., DISTRICT project studies which would then be applicable to the local share of construction costs totalling up to 35% of first costs, if that amount is greater than traditional requirements. Traditional cost-sharing would apply for projects where those costs exceed 35%. There were no Section 205 projects under construction in FY 1985. See Table L for other expenditures under Section 205 during FY 1985. Multiple Purpose Projects Including Power 26. HARRY S. TRUMAN DAM AND RESERVOIR, OSAGE RIVER, MO Location. Damsite is on main stem of Osage River about 1.5 miles northwest of Warsaw, Benton County, Missouri. Reservoir extends into Bates, Henry, Hickory, St. Clair, and Vernon Counties, Missouri. Existing project. An earthfill dam about 5,000 feet long constructed to an average height of about 96 feet above streambed,including a gate-controlled overfall spillway section and a power installation consisting of six inclined pump-generating units with total capacity of 160,000 kilowatts. Total reservoir storage capacity is 5,202,000 acre-feet (3,918,000 for flood control, 244,000 for sediment reserve, and 1,040,000 multipurpose storage for power, low-flow regulation, and recreation). Public Law 91-267, approved May 26, 1970, authorized a change in project name from Kaysinger Bluff Dam and Reservoir, Osage River Basin, Missouri to the Harry S. Truman Dam and Reservoir. Estimated cost (1985) is $550 million. Construction of relocation of Missouri Highway M-13 was initiated September 1964 and completed May 1966. Construction of the dam and reservoir was initiated in October 1964. The embankment has been completed including paving the top of the dam roadway. The spillway was completed in October 1979. The Southwestern Power Admimistration powerline needed for final testing and commercial operation of the generators was completed in December 1979. The first power unit was placed on line on 22 December 1979. Subsequent problems with the turbine bearing required remedial design on the bearing. Restricted commercial power production began in April 1982. Through September 1985, power generation totaled 1,432,450,800 kilowatt hours. Of the gross income from the sale of power by Southwestern Power Administration, $11,006,863 was allocated to the Corps of Engineers for project power operating costs, interest, investment recovery. Local cooperation. Section 2, Flood Control Act of 1938 applies. Operation during fiscal year. Visitation for FY 1985 was 2,447,500 visitor days. Work was continued on acquisition of land and rights-of-way; relocation of utilities and municipal facilities; construction of the powerplant; construction of public use facilities; cultural resources preservation; and additional exhibitry for the powerhouse and visitor center. Construction of measures to protect downstream areas from power operation were continued. Project is 95 percent complete. During FY 1985 461,496,000 kilowatt-hours of electrical power were generated. Maintenance: Activities consisted of installation of pressure cells in the powerhouse, road resurfacing, and ordinary operation and maintenance. 27. STOCKTON LAKE, SAC RIVER, MO Location. Damsite is on Sac River about 49.5 miles above its confluence with Osage River, and about 2 miles east of Stockton, Cedar County, Missouri, lake extending into Dade and Polk Counties. Existing project. A rock-shell dam with impervious core about 5,100 feet long constructed to an average height of about 128 feet, with a gated overfall spillway and a 45,200-kilowatt power installation. Total reservoir storage capacity is 1,674,000 acre-feet (774,000 for flood control, 25,000 for sediment reserve and 892,000 multipurpose storage for power and recreation). Initial cost of constructing the completed project was $75,721,000. Estimated cost of the project, including $4,179,000 for downstream channel work and $502,057 for supplemental recreational development (Code 710), is $80,402,057 (1985). Construction was initiated in October 1963 and the project was placed in operation in December 1969. Power operation problems were encountered with the initial operation in March 1973 because the downstream channel did not have the capacity which earlier observations and computations indicated. As a result, it has been necessary to restrict the power operation to about the 30,000 kilowatt level. Right-of-way for construction of a channel cutoff and bridge at Horseshoe Bend has been acquired and construction has been completed. Remaining work consisting of completing acquisition of the sloughing easements downstream to Caplinger Mills is underway. Completion will assure downstream channel capacity to Caplinger Mills of 8,000 c.f.s. for powerplant operation. Discharge in this range will accommodate power operations at a 39,500 kilowatt level. Through September 1985 power generation totaled 722,427,800 kilowatt-hours. Of the gross income from the sale of power by Southwestern Power Administration, $14,510,122 was allocated to the Corps of Engineers for project operating costs, interest, investment recovery. Local cooperation. Section 2, Flood Control Act of 1938, applies. Operations during fiscal year. Visitation for FY 1985 was 1,798,800 visitor days. The project is complete and in operational status. Acquisition of sloughing easements downstream to Caplinger Mills was continued. The net amount of power marketed with Southwestern Power Administration was 88,766,000 kilowatt-hours. Maintenance: Activities consisted of ordinary operation and maintenance. 20-9 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 General Investigations 28. GENERAL INVESTIGATIONS Fiscal year 1985 costs totaled $1,184,056 for all General Investigation activities. See Table 20-K which covers Surveys, Collection and Study of Basic Data, Research and Development, Continuation of Planning and Engineering, Planning and Engineering under Proposed Program Legislation, and Advance Engineering and Design. 20-10 TABLE 20-A KANSAS CITY, MO., DISTRICT COST AND FINANCIAL STATEMENT See Section Total Cost to in Text Project Missouri River, Sioux City, Iowa to Mouth (Rulo, Nebr., to Mouth) (Federal Funds) (Contributed Funds) (Consolidated Summary) 2. Blue River Channel Kansas City, Mo. Blue River Channel (Contributed Funds) (Consolidated Funds) 3. Clinton Lake, Wakarusa River, Kans. (Contributed Funds) (Consolidated Summary) 4. Harlan County Lake, Republican River, Nebr.' 5. Hillsdale Lake, Big Bull Creek, Kans. 6. Kanopolis Lake, Smoky Hill River, Kans. 1. 20-11 Funding New Work: Approp. Cost Maint. Approp. Cost New Work: Approp. Cost Maint. Approp. Cost New Work: Approp. Cost Maint. Approp. Cost New Work: Approp. Cost New Work: Approp. Cost New Work: Approp. Cost New Work: Approp. Cost Maint. Approp. Cost New Work: Approp. Cost New Work: Approp. Cost New Work: Approp. Cost Maint. Approp. Cost Rehab. Approp. Cost New Work: Approp. Cost Maint. Approp. Cost New Work: Approp. Cost Maint. Approp. Cost FY 82 FY 83 FY 84 FY 85 Sept. 30, 1985 - - - - 237,942,1901 - - - - 237,942,1901 5,157,500 6,098,600 5,045,700 6,757,700 263,494,2142. 4,797,635 6,380,386 5,044,483 6,827,686 263,456,2832. 8 - - - - 816,190 - - - - 816,190 - - - - 22,642 - - - - 22,642 - - - - 238,758,380$ - - - - 238,758,3803 5,157,500 6,098,600 5,045,700 6,757,700 263,516,8564. 4,797,635 6,380,386 5,044,483 6,827,686 263,478,9254' 300,000 8,200,000 -2,225,000 2,028,000 11,748,171 244,266 170,989 1,255,250 6,563,575 11,671,698 - - 70,000 - 70,000 - - - 27,162 27,162 300,000 8,200,000 -2,155,000 2,028,000 11,818,171 244,266 170,989 1,255,250 6,590,737 11,698,860 1,628,000 - -106,100 - 57,415,433 872,952 540,171 148,626 - 57,415,433 951,500 1,114,900 1,310,500 1,104,500 6,246,300 952,396 1,112,529 1,315,435 1,104,848 6,246,266 - - - - 118,805 - - - - 118,805 1,628,000 - - - 57,534,238 872,952 540,171 - - 57,534,238 174,000 -26,000 -8,000 - 47,111,9266 41,942 98,058 0 - 47,111,926 1,000,400 1,594,000 1,077,100 1,246,400 15,962,461' 1,077,446 1,572,440 1,114,088 1,247,941 15,962,385' - - - - 1,017,623 - - - - 1,017,623 3,355,000 1,900,000 39,600 - 64,021,400 4,089,541 2,115,958 203,412 14,766 64,021,400 349,500 445,300 669,100 585,600 2,049,500 348,860 445,047 669,879 585,618 2,049,404 - - - - 12,577,2276 4 - - - 12,577,2276 945,400 1,533,400 1,069,800 1,452,400 12,282,0108 958,933 1,530,989 1,075,270 1,427,289 12,254,926 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 20-A (Continued) COST AND FINANCIAL STATEMENT See Section in Text Project 7. Lawrence, Kansas River, Kans. (Contributed Funds) (Consolidated Summary) 8. Little Blue River Channel Improvement, Little Blue River, Mo. 9. Little Blue River Lakes, Little Blue River, Mo. (Contributed Funds) (Consolidated Summary) 10. Long Branch Lake Little Chariton River, Mo. (Contributed Funds) (Consolidated Summary) 11. Melvern Lake, Osage (Marais des Cygnes) River, Kans. 12. Milford Lake, Republican River, Kans. 13. Missouri River Levee System, Iowa, Nebr., Kans., and Mo. 14. Perry Lake, Delaware River, Kans. Total Cost to Funding FY 82 FY 83 FY 84 FY 85 Sept. 30, 1985 New Work: Approp. Cost New Work: Approp. Cost New Work: Approp. Cost New Work: Approp. Cost New Work Approp. Cost New Work: Approp. Cost New Work: Approp. Cost New Work: Approp. Cost Maint. Approp. Cost New Work: Approp. Cost New Work: Approp. Cost New Work: Approp. Cost Maint. Approp. Cost New Work: Approp. Cost Maint. Approp. Cost New Work: Approp. Cost New Work: Approp. Cost Maint. Approp. Cost 19,123 63,663 19,123 63,663 2,300,000 4,095,833 16,761 16,761 3,258,000 3,287,641 -16,000 -16,000 16,761 -16,000 761 667,000 562,410 8,620,111 8,620,111 153,377 153,377 8,773,488 8,773,488 25,450,083 25,315,205 -1,653 10,056 8,403 2,259,000 520,777 21,243,000 18,968,228 892,500 97,475 21,243,000 19,003,228 350,000 279,820 341,100 345,045 17,566 39,966 367,566 319,786 891,300 900,932 15,000 28,014 1,067,700 1,077,854 656,000 955,769 -24,340 1,156,100 1,252,008 433,100 431,597 -4,682 6,056 270,318 334,401 1,151,300 1,153,735 26,000 10,995 1,193,300 1,201,212 320,000 569,816 -26,000 .. - 1,734,000 1,723,160 413,000 415,036 108,750 -20,074 79,350 60,500 1,361,900 1,364,012 15,805 1,399,800 1,405,505 196,000 209,080 567,800 567,851 98,799 150,000 219,942 1,532,000 1,533,795 1,396,400 1,397,076 512,000 516,711 2,450,500 2,450,471 640,52210 574,07111 18,446,69912 18,330,09411 37,436,530 37,436,530 10,310,7608 10,310,6988 49,566,492 49,566,492 14,268,524' 14,267,433' 56,302,851 56,302,217 - - 49,095,918 - - 49,095,918 1,874,900 2,419,500 16,110,4848. s13 1,888,451 2,376,085 16,066,6898 1 20-12 17,795,000 13,085,000 12,600,000 124,488,200 18,471,209 15,720,359 11,917,433 123,744,916 - - - 1,187,500 268,645 264,070 96,113 986,304 17,500,000 13,085,000 12,600,000 125,675,700 18,176,209 15,984,429 12,013,546 124,731,220 275,000 -29,400 150,000 17,806,177 328,345 80,574 121,143 17,756,023 SSeeection KANSAS CITY, MO., DISTRICT TABLE 20-A (Continued) COST AND FINANCIAL STATEMENT See Section in Text Project 16. Pomme de Terre Lake, Pomme de Terre River, Mo. 17. Pomona Lake, One Hundred Ten Mile Creek, Kans. 18. Rathbun Lake, Chariton River, Iowa 19. Smithville Lake, Little Platte River, Mo. 20. Tuttle Creek Lake, Big Blue River, Kans. 21. Wilson Lake, Saline River, Kans. 22. Scheduling Flood Control Reservoir Operations 23. Inspection of Completed Flood Control Projects 24. Inspection of Non-Federal Levees 26. Harry S.Truman Dam & Reservoir Osage River, Mo. Total Cost to Funding FY 82 FY 83 FY 84 FY 85 Sept. 30, 1985 New Work: Approp. Cost Maint. Approp. Cost New Work: Approp. Cost Maint. Approp. Cost New Work: Approp. Cost Maint. Approp. Cost New Work: Approp. Cost Maint. Approp. Cost New Work: Approp. Cost Maint. Approp. Cost New Work: Approp. Cost Maint. Approp. Cost Maint. Approp. Cost Maint. Approp. Cost Maint. Approp. Cost New Work: Approp. Cost Maint. Approp. Cost - 15,000 - 15,000 1,630,600 1,578,400 1,621,547 1,589,591 54,417 54,417 1,004,200 1,006,162 5,000 4,735 952,100 962,341 69,000 56,439 1,074,800 1,133,069 2,963,000 1,437,562 569,900 566,805 -13,389 154,395 673,500 688,167 -27,028 256,050 746,600 758,161 164,000 165,340 241,000 241,170 14,500,000 13,549,322 2,928,600 2,935,717 1,818,200 1,830,355 -15,000 336,702. 1,898,500 2,203,430 1,193,000 924,469 1,080,500 1,081,351 1,429,500 1,428,495 1,038,200 1,039,549 2,541,300 2,503,486 774,661 879,000 875,127 1,198,900 1,539,900 1,476,700 1,194,485 1,546,437 1,477,840 1,257,600 1,246,720 149,000 149,401 300,000 299,731 73,000 72,999 14,923,000 12,929,266 3,834,200 3,836,394 995,300 1,012,121 161,700 162,014 338,100 338,301 95,000 94,997 12,425,000 16,710,978 4,039,900 4,061,256 1,109,900 1,110,138 173,000 174,032 365,000 364,917 153,000 152,458 9,200,000 8,860,644 4,859,300 4,870,785 265 1,304,000 1,296,852 441,000 101,859 2,019,300 1,734,316 357,877 1,476,459 584,800 589,584 20-13 17,365,452" 17,365,452 15,135,5128 15,134,4148 14,003,238 14,003,238 12,918,3338 12,918,3118. 9 27,622,159 27,622,159 14,828,2188 14,790,3418 87,651,315 87,242,194 4,110,000 4,106,076 80,584,079 80,584,079 14,363,7798 14,362,0618 20,463,367 20,463,367 10,367,0468 10,366,9998 4,819,3237 4,819,3237 3,643,075 3,642,925 321,000 320,454 521,489,900 520,974,785 20,717,20018 20,716,100 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 20-A (Continued) COST AND FINANCIAL STATEMENT See Section Total Cost to in Text Project Funding FY 82 FY 83 FY 84 FY 85 Sept. 30, 1985 27. Stockton Lake, New Work: Sac River, Mo. Approp. - 2,820,000 -269,000 105,000 79,658,357 Cost 370,441 1,276,067 855,969 132,582 79,248,878 Maint. Approp. 1,483,800 1,786,300 2,690,900 1,876,800 19,338,3008s s1 Cost 1,542,330 1,789,410 2,699,062 1,868,147 19,325,3668 18 1. Includes $8,665,594 costs of new work for previous 8. Includes funds from Maintenance and Operation of project. Dams and Other Improvements of Navigable Waters ap- 2. Includes $738,109 for maintenance of previous project. propriation for FY 1979. 3. Includes $8,665,594 for new work for previous project 9. Reflects $10 expenditure of undelivered order after and $816,190 from contributed funds. close of 1978 cost records. 4. Includes $738,190 for maintenance of previous project 10. Correct total is $635,841, which includes $31,664 in- $22,642 from contributed funds and $200,000 Fiscal Year terest during construction. Correction pending. 1968 Supplemental Appropriation Funds. 11. Unable to verify. 5. Excludes cost of materials furnished without charge in 12. Overstated by $4,681. Correction pending. the amount of $24,198. 13. Includes funds from Maintenance and Operation of 6. Excludes cost of materials furnished without charge in Dams and Other Improvements of Navigable Waters apthe amount of $7,885. propriation for FY 1985. 7. Covers 96X3123 operation and maintenance, general funds allotted to 'Scheduling of Flood Control Reservoir Operations.' TABLE 20-B AUTHORIZING LEGISLATION See Section Date of in Text Act Project and Work Authorized Documents July 25, 1912 Aug. 8, 1917 Mar. 3, 1925 Jan. 12, 1927 July 3, 1930 Aug. 30, 1935 Mar. 2, 1945 MISSOURI RIVER, SIOUX CITY, IA TO MOUTH (RULO, NE, TO MOUTH) Project adopted for securing a permanent navigable channel of 6-foot depth from Kansas City, MO to mouth. Fixed upstream limit of improvement at upper end of Quindaro Bend (374.8 miles from mouth) and provided for dredging. For a minimum width of 200 feet, with a reasonable additional width around bends. Appropriation of $12 million authorized for existing project. Appropriation of $15 million additional authorized; additional allotments totaling $29,153,108 were made by Public Works Administration under provisions of National Industrial Recovery Act of 1938, and $9,669,791 allotted under provisions of Emergency Relief Appropriation Act of 1935. Completion of improvement from mouth to Sioux City, Iowa. Securing a navigable channel of 9-foot depth and a minimum width of 300 feet. H. Doc. 1287, 61st Cong., (contains latest published map). P.L. 24162 H. Doc. 463, 64th Cong., (contains latest published map). P.L. 58568 H. Doc. 1120, 60th Cong., P.L. 560-70. H. Doc. 238, 73d Cong., (contains latest published map). H. Doc. 214, 76th Cong., (contains latest published map) P.L. 14-79. 20-14 1. KANSAS CITY, MO., DISTRICT TABLE 20-B (Continued) AUTHORIZING LEGISLATION See Section Date of in Text Act Project and Work Authorized Documents 2. June 28, 1938 Aug. 18, 1941 Dec. 22, 1944 Sep. 3, 1954 Aug. 13, 1968 Aug. 13, 1968 Oct. 27, 1965 Dec. 31, 1970 Oct. 23, 1962 June 28, 1938 Aug. 18, 1941 Dec. 22, 1944 Sep. 3, 1954 3. BLUE RIVER CHANNEL, KANSAS CITY, MO Adopted plan for Blue River Basin and authorized $40,000,000 for initiation and partial accomplishment. CLINTON LAKE, WAKARUSA RIVER, KS The project for the Kansas River, KS, NE, and CO is authorized at an estimated cost of $88,070,000. HARLAN COUNTY LAKE, REPUBLICAN RIVER, NE Adopted general comprehensive plan for Missouri River Basin and authorized $9 million for initiation and partial accomplishment. Modified general comprehensive plan to include Harlan County Dam and Reservoir on Republican River, NE, other supplemental flood control works on upper Republican River, and authorized $7 million additional expenditure. Expanded general comprehensive plan for Missouri River Basin and authorized $200 million additional expenditure. HILLSDALE LAKE, BIG BULL CREEK, KS The comprehensive plan for the Missouri River Basin, approved by the Act of June 28, 1938, and as amended and supplemented is further modified to include the project for flood protection on the Kansas River and tributaries. It is further modified to include the project for flood protection on the Osage River and tributaries. KANOPOLIS LAKE, SMOKY HILL RIVER, KS Adopted general comprehensive plan for Missouri River Basin and authorized $9 million for initiation and partial accomplishment. Modified general comprehensive plan to include Harlan County Dam and Reservoir on Republican River, NE, other supplemental flood control works on upper Republican River, and authorized $7 million additional expenditure. Expanded general comprehensive plan for Missouri River Basin and authorized $200 million additional expenditure. LAWRENCE, KANSAS RIVER, KS Expanded general comprehensive plan for Missouri River Basin and authorized $217,710,000 additional expenditure. LITTLE BLUE RIVER CHANNEL Additional $38,000,000 for prosecution of general comprehensive plan for Missouri River Basin. LITTLE BLUE RIVER LAKES, MO Additional $38,000,000 for prosecution of general comprehensive plan for Missouri River Basin. LONG BRANCH LAKE, LITTLE CHARITON RIVER, MO The project for flood protection on the Chariton and Little Chariton Rivers and tributaries, Iowa and Missouri, is authorized at an estimated cost of $9,167,000. 20-15 H. Doc. 91-332, 91st Cong. 1962 Flood Control Act S. Doc 122, H. Doc. 578, 87th Cong., P.L. 87-874. Flood Control Committee Doc. 1, 75th Cong., P.L. 761. H. Doc. 842, 76th Cong., P.L. 228. H. Doc. 475 and S. Docs. 191 and 247, 78th Cong., P.L. 534. P.L. 780, 83rd Cong., H. Doc. 549, 81st Cong. Flood Control Committee Doc. 1, 75th Cong., P.L. 761. H. Doc. 842, 76th Cong., P.L. 228. H. Doc. 475 and S. Docs. 191 and 247, 78th Cong., P.L. 534. H. Docs. 642,5491, and 561, 83rd Cong., P.L. 780. P.L. 90-483 (H. Doc. 169, 90th Cong. P.L. 90-483 (H. Doc. 169, 90th Cong. 1965 Flood Control Act, P.L. 89-298, (H. Doc. 238, 89th Cong. 4. 5. 6. 7. 8. 9. 10. REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 20-B AUTHORIZING LEGISLATION See Section Date of in Text Act Project and Work Authorized Documents Sep. 3, 1954 Sep. 3, 1954 Aug. 18, 1941 Dec. 22, 1944 Sept. 3, 1954 June 28, 1938 Aug. 18, 1941 Dec. 22, 1944 July 24, 1946 May 17, 1950 Sept. 3, 1954 May 2, 1956 July 3, 1958 July 14, 1960 Dec. 30, 1963 June 18, 1965 May 12, 1967 11. 12. 20-16 MELVERN LAKE, MARAIS DES CYGNES (OSAGE) RIVER, KS Expanded general comprehensive plan for Missouri River Basin and authorized $217,710,000 additional expenditure. MILFORD LAKE, REPUBLICAN RIVER, KS Expanded general comprehensive plan for Missouri River Basin and authorized $217,710,000 additional expenditure. MISSOURI RIVER LEVEE SYSTEM, IA, NE, KS, AND MO Levees along both sides of river from Sioux City to Kansas City. Extended project from Kansas City to the mouth provided for increased protection. PERRY LAKE, DELAWARE RIVER, KS Expanded general comprehensive plan for Missouri River Basin and authorized $217,710,000 additional expenditure. PICK-SLOAN MISSOURI BASIN PROGRAM (KANSAS CITY DIST.) Adopted general comprehensive plan for Missouri River Basin and authorized $9 million for initiation and partial accomplishment. Modified general comprehensive plan to include Harlan County Dam and Reservoir on Republican River, NE, other supplemental flood control works on upper Republican River, and authorized $7 million additional expenditure. Expanded general comprehensive plan for Missouri River Basin and authorized $200 million additional expenditure. Additional expenditure of $150 million for prosecution of general comprehensive plan for Missouri River Basin. Additional expenditure of $250 million for prosecution of general comprehensive plan for Missouri River Basin. Expanded general comprehensive plan for Missouri River Basin and authorized $217,710,000 additional expenditure. Modified general comprehensive plan for Missouri River Basin by deletion of construction of Red Willow Dam and Reservoir, NE, and addition of construction of Wilson Dam and Reservoir, KS. Expanded general comprehensive plan for Missouri River Basin and authorized $200 million additional expenditure. Additional expenditure of $207 million for prosecution of general comprehensive plan for Missouri River Basin. Additional expenditure of $80 million for prosecution of general comprehensive plan for Missouri River Basin and modified plan to include bank protection or rectification works below Garrison Dam. Additional $116 million for prosecution of general comprehensive plan for Missouri River Basin. Additional $20 million for prosecution of general comprehensive plan for Missouri River Basin. H. Docs. 642, 5491, and 561, 83rd Cong., P.L. 780. H. Doc. 5491, 83rd Cong., P.L. 780. H. Doc. 821, 76th Cong. H. Doc. 475 and S. Docs. 191 and 247, 78th Cong. H. Docs. 642, 5491, and 561, 83rd Cong., P.L. 780. Flood Control Committee Doc. 1, 75th Cong. H. Doc. 842, 76th Cong. H. Doc. 475 and S. Docs. 191 and 247, 78th Cong. H. Docs. 642 and 5491 83rd Cong. H. Doc. 409, 84th Cong. 13. 14. 15. KANSAS CITY, MO., DISTRICT TABLE 20-B (Continued) AUTHORIZING LEGISLATION See Section Date of in Text Act Project and Work Authorized Documents Aug. 13, 1968 Dec. 24, 1970 Dec. 23, 1971 Mar. 7, 1974 June 28, 1938 Dec. 22, 1944 Sep. 3, 1954 Sept. 3, 1954 Sept. 3, 1954 Oct. 27, 1965 June 28, 1938 Aug. 18, 1941 Dec. 22, 1944 Dec. 22, 1944 July 14, 19602 Sept. 3, 1954 Additional $38,000,000 for prosecution of general comprehensive plan for Missouri River Basin. Change comprehensive plan name to Pick-Sloan Missouri Basin program. Additional $101,000,000 for prosecution of general comprehensive plan for Pick-Sloan Missouri Basin program. Additional $72,000,000 for prosecution of general comprehensive plan for Pick-Sloan Missouri Basin program. POMME DE TERRE LAKE, POMME DE TERRE RIVER, MO Adopted general comprehensive plan for Missouri River Basin and authorized $9 million for initiation and partial accomplishment. Expanded general comprehensive plan for Missouri River Basin and authorized $200 million additional expenditure. Expanded general comprehensive plan for Missouri River Basin and authorized $217,710,000 additional expenditure. POMONA LAKE, ONE HUNDRED TEN MILE CREEK, KS Expanded general comprehensive plan for Missouri River Basin and authorized $217,710,000 additional expenditure. RATHBUN LAKE, CHARITON RIVER, IA Expanded general comprehensive plan for Missouri River Basin and authorized $217,710,000 additional expenditure. SMITHVILLE LAKE, LITTLE PLATTE RIVER, MO The project for flood protection on the Platte River and tributaries, MO and IA is authorized at an estimated cost of $26,889,000. TUTTLE CREEK LAKE, BIG BLUE RIVER, KS Adopted general comprehensive plan for Missouri River Basin and authorized $9 million for initiation and partial accomplishment. Modified general comprehensive plan to include Harlan County Dam and Reservoir on Republican River, NE, other supplemental flood control works on upper Republican River, and authorized $7 million additional expenditure. Expanded general comprehensive plan for Missouri River Basin and authorized $200 million additional expenditure. WILSON LAKE, SALINE RIVER, KS Expanded general comprehensive plan for Missouri River Basin and authorized $200 million additional expenditure. Additional expenditure of $207 million for prosecution of general comprehensive plan for Missouri River Basin. HARRY S. TRUMAN DAM AND RESERVOIR, OSAGE RIVER, MO Expanded general comprehensive plan for Missouri River Basin and authorized $217,710,000 additional expenditure. S. Doc. 91-1100, 91st Cong. S. Doc. 92-222, 92nd Cong. Flood Control Committee Doc. 1, 75th Cong., P.L. 761. H. Doc. 475 and S. Docs. 191 and 247, 78th Cong. P.L. 534. H. Docs. 642, 5491, and 561, 83rd Cong., P.L. 780. H. Doc. 5491, 561, 83rd Cong., P.L. 780. H. Doc. 561 83rd Cong., P.L. 780. 1965 Flood Control Act, P.L. 89-298 (H. Doc. 262, 89th Cong.) Flood Control Committee Doc. 1, 75th Cong., P.L. 761. H. Doc. 842, 76th Cong., P.L. 228 H. Doc. 475 and S. Docs. 191 & 247, 78th Cong., P.L. 534 H. Doc. 475 and S. Docs. 191 & 247, 78th Cong., P.L. 534 S. Doc. 96, 86th Cong. P.L. 645. H. Doc. 5491, 83rd Cong., P.L. 780. 20-17 16. 17. 18. 19. 20. 21. 26. REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 20-B (Continued) AUTHORIZING LEGISLATION See Section Date of in Text Act Project and Work Authorized Documents Oct. 23, 1962 The Kaysinger Bluff Reservoir is hereby modified in 1962 Flood Control Act, accordance with recommendations of the Chief of H. Doc. 578, 87th Cong., Engineers in H. Doc. 578, 87th Cong., at an estimated P.L. 87-874. additional cost of $43,245,000: provided, that nothing in this Act shall be construed as authorizing the acquisition of additional lands for the establishment of a national wildlife refuge at the reservoir. STOCKTON LAKE, SAC RIVER, MO 27. Sept. 3, 1954 Expanded general comprehensive plan for Missouri H. Doc. 5491, River Basin and authorized $217,710,000 83rd Cong., additional expenditure. P.L. 780. 1. Contains latest published maps of Missouri River. 2. Report of Chief of Engineers on justification of Wilson Dam and Reservoir, submitted in compliance with Public Law 505, 84th Congress, published as Senate Document 96, 86th Congress, was approved July 14, 1960 (Public Law 645). TABLE 20-C OTHER AUTHORIZED NAVIGATION PROJECTS For Last Cost To September 30, 1985 Full Report See Annual Operation and Project Status Report For Construction Maintenance Fort Leavenworth Bridge removal Complete 1965 270,393 - Gasconade River, MO1- 2 Complete 1931 139,003 85,077 Kansas River Navigation Inactive 1980 259,900 - Osage River, MO, lock and dams Complete 1952 658,076 850,495 1. Improvement adequate for existing needs. Project for maintenance only. 2. Curtailment of project in H. Doc. 467, 69th Cong. 3. Operation of lock and dam placed in standby status. 20-18 KANSAS CITY, MO., DISTRICT TABLE 20-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS For Last Cost To September 30, 1985 Full Report See Annual Operation and Project Status Report For Construction Maintenance Abilene, KS. Atchison, KS. Barnard, KS1 Bartley, NE Bedford, East Fork, 102 River, IA1 Big Blue River, Seward, NE1 Big Stranger Creek, KS1 Blue River Basin, Vicinity of Kansas City4 Braymer Lake, Shoal Creek, MO Brookfield Lake, Yellow Creek, MO Chariton-Little Chariton Basin, MO (1965 Act)2 Chariton River, MO (1944 Act) Dry Fork and East Fork Lakes, Fishing River, MO East Muddy Creek, MO Elk Creek, Clyde, KS1 Fairbury, Little Blue River, NE Fort Scott Lake, Marmaton River, KS Frankfort, Black Vermillion River, KS Garnett Lake, Pottawatomie Creek, KS Grove Lake, Soldier Creek, KS Gypsum, Gypsum Creek, KS1 Indian Lake, Blue River, KS Indianola, NE Kansas City, Kansas River, KS (62 Mod) Kansas Citys on MO and KS Rivers, MO and KS3 Lower Grand River, MO Manhattan, Kansas River, KS Mercer Lake, Weldon River, MO Mill Lake, Blue River, MO Missouri River at New Haven, MO1 Onaga Lake, Vermillion Creek, KS Osawatomie, Pottawatomie Creek, KS Ottawa, Osage (Marais des Cygnes) River, KS Pattonsburg Lake, Grand River, MO Pattonsburg Lake, Grand River, MO (Advance Highway Relocation) Pattonsburg Lake, Grand River, MO (Advance Town Relocation) Perry Lake Area (Road Improvements), KS Platte River, MO, Channel Improvement Rathbun Lake Fish Hatchery Salina, Smoky Hill River, KS Salt Creek, Barnard, KS1 Seward, NE1 Smithville Channel, Little Platte River, MO Stonehouse Creek, Jefferson Co., KS1 Tomahawk Lake, Blue River, KS Topeka, Kansas River, KS Trenton Lake, Thompson River, MO Upper Grand River, MO Wolf-Coffee Lake, Blue River, KS Completed Completed Completed Completed Completed Completed Completed Inactive Inactive Complete Deferred Inactive Completed Completed Active Completed Inactive Inactive Completed Inactive Completed Completed Active Completed Inactive Deferred Completed Inactive Completed Completed Inactive Inactive Inactive Completed Deferred Completed Completed Completed Completed Deferred Completed Inactive Completed Inactive Inactive Inactive 1965 1973 1953 1974 1984 1966 1976 1977 1973 1974 1966 1984 1973 1976 1966 1973 1977 1984 1976 1950 1984 1980 1966 1967 1976 1971 1982 1973 1966 1976 1976 1976 1982 1973 1975 1967 1973 1972 1976 1974 1966 1966 1976 1,099,350 4,099,590 127,860 118,269 652,414 126,887 337,131 451,400 692,706 8,052,990 51,989 989,015 726,966 757,500 1,271,025 71,466 1,754,019 2,782,793 127,297 67,275 25,010,500 42,434,197 2,488,585 432,245 139,883 2,178,261 2,036,624 4,462,661 390,763 91,929 5,315,168 222,193 700,000 3,878,668 127,860 126,887 6,896 246,995 77,189 21,174,593 1,095,019 1. Authorized by the Chief of Engineers under section 205, Public Law 858, 80th Congress, as amended. 2. Little Chariton River (East and Middle Fork) and Mussell Fork classified inactive. Construction cost includes $481,106 cost of completed Shoal Creek Unit and $211,600 cost for inactive units, Little Chariton River and Mussell Fork. 3. Includes $619,787 non-Federal contributions for work desired by local interests, but not required under the project. The project as a whole is complete except for Turkey Creek facilities in Central Industrial District Unit. 4. Three lakes inactive and one lake deferred. 20-19 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 20-G DEAUTHORIZED PROJECTS For Last Full Report Federal Contributed See Annual Funds Funds Project Report For Date and Authority . Expended Expended Arlington Lake, MO 1948 Flood Control Act approved $8,651 June 28, 1938, as modified by Flood Control Act approved August 18, 1941, and expanded by Flood Control Act approved December 22, 1944 Beatrice, Big Blue River, NE 1965 Flood Control Act approved 16,317 September 3, 1954 Hackleman Corners Lake, - Authorized by Flood Control Act - Cedar Creek, MO approved September 3, 1954 Hays, Big Creek, KS1 1974 Flood Control Act of 1965 499,200 approved October 27, 1965 Marysville, KS - Flood Control Act of 133,682- September 3, 1954 Merriam, Turkey Creek, KS 1970 Flood Control Act approved 39,708 September 3, 1954 Pioneer Lake, KS 1952 Flood Control Act approved 95,692- June 28, 1938, as modified by Flood Control Act of August 18, 1941, and expanded by Flood Control Act approved December 22, 1944 Richland Lake, MO 1948 Flood Control Act approved 8,548- June 28, 1938, as modified by Flood Control Act approved August 18, 1941, and expanded by Flood Control Act approved December 2, 1944 1. A study of water supply and flood problems at Hays, KS, is being studied under Section 205, Public Law 858, 80th Congress, as amended. TABLE 20-H MISSOURI RIVER LEVEE SYSTEM (See Section 13 of Text) Miles of Unit Levee Status R 513-512 Richardson Co. D. D. #7 R 500 Iowa Point D. D. #4 Kimsey Holly Creek L 497 Forest City L. D. L 488 Holt Co. D. D. #7 R 482 Burr Oak D. D. #3 L 476 Amazonia L. D. R 471-460 Elwood-Gladden L. D. L 455 S. St. Joseph L. D. L 448-443 Halls L. D. R 440 Atchison & Doniphan Co. D. D. L 408 Farley-Beverly D. D. L 400 Waldron L. D. L 385 Riverside-Quindaro D. D. R 351 Atherton L. D. L 345-330 Orrick L. D. L 325-319 Henrietta-Crooked River D. D. L 246 Brunswick-Dalton D. D. L 15 North County L. D. Remaining units 19.1 4.1 4.4 16.0 11.5 8.2 10.8 13.8 15.6 17.3 10.7 12.2 7.6 6.5 15.9 43.4 35.0 20.0 40.0 Complete-1958 Complete-1954 Complete-1970 Complete-1962 Complete-1955 Complete-1954 Complete-1956 Complete-1968 Complete-1967 Complete-1957 Complete-1959 Complete (Levee raise modification)-1972 Complete-1957 Planning underway Complete-1966 Planning underway Planning underway Complete- 1983 Planning underway Detailed planning not initiated 20-20 KANSAS CITY, MO., DISTRICT TABLE 20-I KANSAS CITY DISTRICT PROJECTS INCLUDED IN PICK-SLOAN MISSOURI BASIN PROGRAM (See Section 15 of Text) Estimated Estimated Project Federal Non-Federal Cost Cost Abilene, Smoky Hill River, Kansas $ 1,099,350 $ 287,000 Bartley, Republican River, Nebraska 118,269 9,500 Fort Scott Lake, Marmaton River, Kansas 82,800,000 41,200,000 Garnett Lake, Pottawatomie Creek, Kansas2 38,600,000 - Harlan County Lake, Republican River, Nebraska 48,129,549 - Harry S. Truman Dam and Reservoir, Osage River, Missouri 549,000,000 132,861,000 Hillsdale Lake, Big Bull Creek, Kansas 64,021,400 21,091,814 Indianola, Republican River, Nebraska 67,275 7,592 Kanopolis Lake, Smoky Hill River, Kansas 12,577,227 - Lawrence, Kansas River, Kansas 8,620,111 2,130,000 Manhattan, Kansas River, Kansas 2,488,585 265,000 Melvern Lake, Osage (Marais des Cygnes) River, Kansas 37,436,530- Melvern Lake and Pomona Lake (Road Improvement), Kansas (1974 Authorization) 500,000 214,300 Milford Lake, Republican River, Kansas 49,566,492 - Missouri River Levee System, Rulo to the Mouth' 242,500,000 25,400,000 Osawatomie, Osage (Marais des Cygnes) River, Kansas 2,036,624 348,300 Ottawa, Osage (Marais des Cygnes) River, Kansas 4,462,661 876,000 Perry Lake, Delaware River, Kansas 49,095,918 - Pomme de Terre Lake, Pomme de Terre River, Missouri3 17,365,453 - Pomona Lake, Osage River Basin, Kansas 14,003,238 - Salina, Smoky Hill River, Kansas 3,878,668 1,960,000 Stockton Lake, Sac River, Missouri 80,902,057 17,391,000 Topeka, Kansas River, Kansas 21,174,593 10,383,492 Tuttle Creek Lake, Big Blue River, Kansas 80,584,079 - Tuttle Creek Lake, Kansas-Road and Bridge (1976 Act) 630,000 580,000 Tuttle Creek Lake (Road Improvement), Kansas (1974 Modification) 500,000 214,300 Wilson Lake, Saline River, Kansas 20,463,367 - 1. Active portion of project. Deferred portion of project is currently estimated to cost (1985) $27,130,000 Federal and $2,047,000 non-Federal. Inactive portion of project is currently estimated to cost (1985) $206,282,000 Federal and $18,099,000 non-Federal. 2. 1969 Estimate. 3. Active portion of project. Inactive portion of the project for power modification is currently estimated to cost (1954) $7,300,000. 20-21 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 20-J INSPECTION OF COMPLETED FLOOD CONTROL PROJECTS (See Section 23 of Text) Location Month Inspected Missouri River Main Stem Missouri River Levees: R 513-512, R 500, Kimsey Holly Creek, L 497, L 488, Sep-Oct 85 R 482, L 476, R 471-460, L 455, L 448-443, R 440, L 408, L 400 and R 351, L 246 Kansas Citys, Missouri and Kansas: Argentine, Armourdale, Sep-Oct 85 Birmingham, CID (Mo & Kans), East Bottoms, Fairfax-Jersey Creek, North Kansas City Units, and GSA Federal Complex Osage River, Kansas and Missouri Ottawa, Kansas Oct 85 Osawatomie, Kansas Oct 85 Kansas River and Minor Tributaries Topeka, Kansas; Auburndale, North Topeka, Oakland, Soldier Oct 85 Creek, South Topeka, and Waterworks Units Republican River, Nebraska and Kansas Bartley, Nebraska Apr 85 Smoky Hill, Saline, and Solomon Rivers Abilene, Kansas Nov 85 20-22 KANSAS CITY, MO., DISTRICT TABLE 20-K ACTIVE GENERAL INVESTIGATIONS (See Section'28 of Text) Federal Cost Totals By Item and CWIS Number FY 85 Categories SURVEYS (Category 100) Flood Damage Prevention Studies (120) Kansas and Osage Rivers, Kansas - 12204 $276,276 Osage River above Harry S. Truman- 14063 241,774 Republican River, NE & KS - 12383 199,978 Subtotal $718,028 Review of Authorized Projects (160) Fort Scott Lake, Kansas - 06470 $ 1,001 Platte River and Little Platte River Channels, MO - 14160 70,915 Grove Lake Deauthorization Review - 77000 6,680 Subtotal $ 78,596 Miscellaneous Activities (170) Special Investigations - 17250 56,062 FERC Licensing - 53857 2,536 Subtotal $ 58,598 Coordination Studies with Other Agencies (180) Soil Conservation Service, Dept. Agric. (181) - 51840 $ 6,899 Bureau of Reclamation, Dept. Interior (182) - 51820 19,887 Missouri Basin States Association (183) - 53847 2,651 Planning Assistance to States (186) - 51850 & 14820 48,472 Technical Assistance for Streambank Erosion (188) - 51731 15,740 Subtotal $ 93,649 Supplemental Preauthorization Studies (190) Wears Creek, Jefferson City, Missouri - 75299 $ 59,516 TOTAL (Category 100) $1,008,387 COLLECTION AND STUDY OF BASIC DATA (Category 200) Flood Plain Management Services (250) - 82030/40 153,093 Hydrologic Studies (260) - 53820 22,576 TOTAL (Category 200) $ 175,669 RESEARCH AND DEVELOPMENT (Category 300) None CONTINUATION OF PLANNING AND ENGINEERING (Category 400) None PLANNING AND ENGINEERING UNDER PROPOSED LEGISLATION (Category 500) None ADVANCE ENGINEERING AND DESIGN (Category 600) None GRAND TOTAL GENERAL INVESTIGATIONS $1,184,056 20-23 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 20-L FLOOD CONTROL ACTIVITIES UNDER SPECIAL AUTHORIZATION (See Section 25 of Text) Fiscal Year Study Stage1 Cost (Flood Control Activities Pursuant to Section 205, Public Law 858, 80th Congress, as amended) Rossville, Cross Creek, KS D $105,787 Hays, Lincoln Draw, KS D 46,802 Big Creek, Pleasant Hill, MO R 50,766 Davis Creek, Mound City, MO R 29,466 TOTAL $232,821 2 Negative Appraisals, studies terminated totaled $8,500 TOTAL ALL PROJECTS $241,321 (Emergency Bank Protection - Sec. 14, 1946 Flood Control Act, Public Law 526, 79th Cong., July 24, 1946, as amended) South Fork Big Nemaha River, Dubois Bridge, Pawnee County, NE O $136,000 North Fork Big Nemaha River, Elk Creek Sewage Lagoons, Johnson County, NE O 80,727 West Fork Grand River, Isadora Bridge, Worth County, MO O 56,402 North Fork Big Nemaha River, County Road, Richardson County, NE O 73,494 Little Blue River, Fike Bridge, Clay County, NE O 49,982 Little Blue River, Pawnee Ranch Bridge, Clay County, NE O 33,492 Little Blue River, Spring Ranch Bridge, Clay County, NE O 24,585 Little Blue River, Lipovsky Bridge, NE, Clay County, NE O 24,414 Tarkio River, Coin Sewage Lagoons, Page County, IA O 9,462 South Fork Wolf River, County Bridge, Brown County, KS C 57,048 Little Blue River, Gilead Bridge, Thayer County, NE C 60,277 Marais des Cygnes, Quenemo Sewage Lagoons, Osage County, KS C 36,076 Nodaway River, Road T, Andrew County, MO P 29,463 Osage River, Road HH, Miller County, MO P 19,382 Beaver Creek, Br. 43430, Webster County, NE P 5,490 West Branch Indian Creek, Br. 21505, Webster County, NE P 8,120 Elm Creek, Br. 33425, Webster County, NE P 6,959 Elm Creek, Br. 23015, Webster County, NE P 6,964 Beaver Creek, Br. 23025, Webster County, NE P 9,287 Beaver Creek, Br. 14710, Webster County, NE P 5,649 Yankee Creek, West Tecumseh Bridge, Johnson County, NE P 13,106 Yankee Creek, Vesta Bridge, Johnson County, NE P 16,153 Kimsey Creek, Casteel Bridge, Holt County, MO P 15,324 Nodaway River, Fillmore Bridge, Andrew & Holt Counties, MO P 14,221 Big Blue River, Tuxedo Park Road & Bridge, Saline County, NE P 18,876 Wakarusa River, Baldwin City Waterline, Douglas County, KS I 10,253 TOTAL FOR 26 ACTIVE PROJECTS: $821,206 7 studies were terminated in FY 85 totaling $38,660 TOTAL ALL PROJECTS: $859,866 (Emergency Flood Control Activities - Repair, Flood Fighting, and Rescue Work - Public Law 99 84th Congress and Antecedent Legislation) Disaster Preparedness Program $245,888 Flood Fighting and Rescue Work 427,575 Rehabilitation 1,432,438 TOTAL $2,105,901 1. Stage: I= Initial Appraisal; R=Recon; D=DPS; P=P&S; C=Construction; O=Operational 20-24 OMAHA, NE, DISTRICT* This district comprises portions of Montana, Wyo- drainage basin of Missouri River along main stem and ming, North Dakota, South Dakota, Minnesota, Colo- tributaries to Rulo, NE. rado, Nebraska, Iowa, and Missouri, all embraced in IMPROVEMENTS Navigation 1. Missouri River, Sioux City, IA to Rulo, NE....................... 2. Navigation Work Under Special Authorization ................... . Flood Control 3. Bear Creek Lake, CO .................... 4. Bowman-Haley Lake, ND ................ 5. Chatfield Lake, CO ...................... 6. Cherry Creek Lake, CO .................. 7. East Nishnabotna River atRedOak,IA ...................... 8. Fall River Basin, SD ................... 9. Great Falls, MT ..................... 10. Indian Creek at Emerson, IA ............. 11. Little Sioux River, IA .................. 12. Lost Creek at Columbus, NE .............. 13. Missouri National Recreational River, NE and SD .................... 14. Missouri River, Garrison Dam to Lake Oahe, ND ....................... 15. Missouri River, Kenslers Bend, NE to Sioux City, IA .................. 16. Missouri River Levee System, Sioux City, IA to Rulo, NE.............. 17. Papillion Creek and Tributaries Lakes, NE ............................. 18. Pick-Sloan Missouri River Basin Program (Omaha Dist).................. 19. Pipestem Lake, ND ................... 20. Salt Creek & Tributaries, NE ............. 21. South Platte River Basin, CO ............ 22. Inspection of Completed Flood Control W orks ........................ 23. Scheduling Flood Control Reservoir Operations .................... 24. Flood Control Activities Under Special Authorization .................. . Page Multiple Purpose Projects Including Power Page 25. Big Bend Dam-Lake Sharpe, .21-2 Missouri River Basin, SD .............. .. 21-7 26. Fort Peck Lake, MT .................... . 21-7 .21-2 27. Fort Randall Dam-Lake Francis Case, Missouri River Basin, SD ................ 21-7 .21-2 28. Garrison Dam-Lake Sakakawea, .21-2 Missouri River Basin, ND.................21-8 . 21-2 29. Gavins Point Dam-Lewis and Clark Lake, . 21-3 Missouri River Basin, NE and SD .......... 21-8 30. Oahe Dam-Lake Oahe, Missouri .21-3 River Basin, SD and ND .................. 21-8 .. 21-3 .. 21-4 .. 21-4 ... 21-4 .. 21-4 ... 21-4 .. 21-5 .21-5 .21-5 .. 21-5 .. 21-5 .. 21-5 .. 21-6 .. 21-6 ..21-6 S..21-6 ... 21-6 Miscellaneous 31. Streambank Erosion Control Evaluation and Demonstration Project General Investigations, 32. SeeTable21-K ................. ...... 21-9 ...... 21-9 Tables 21-A Cost and Financial Statement ........... 21-10 21-B Authorizing Legislation................21-12 21-C Other Authorized Navigation Projects .... 21-16 21-D Not Applicable 21-E Other Authorized Flood Control Projects.. 21-16 21-F Other Multiple Purpose Projects Including Power ..................... 21-18 21-G Deauthorized Projects ................ 21-18 21-H Missouri River Levee System, Sioux City, IA to Rulo, NE ............. 2 1-18 21-I Pick-Sloan Missouri Basin Program ...... 21-19 21-J Inspection of Completed Local Protection Projects .................... 21-19 21-K Active General Investigations ......... .. 21-21 21-L Flood Control Activities Under Special Authorization ............ 21-22 21-1 . . . . . . . . REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Navigation 1. MISSOURI RIVER, SIOUX CITY, IA TO MOUTH (SIOUX CITY, IA TO RULO, NE) Location. Channel of the Missouri River extending from Sioux City, IA to Rulo, NE. Previous projects. For details see page 1893, Annual Report for 1915, and page 1175, Annual Report for 1938. Existing project. Provides for a navigation channel of 9-foot depth and width not less than 300 feet, obtained by revetment of banks, rock dikes to contract and stabilize waterway, cutoffs to eliminate long bends, closing minor channels, and removal of snags and dredging as required. Construction was initiated on this section of the project (Sioux City to Rulo) in fiscal year 1928, the bank stabilization work was completed in April 1979, and the navigation feature was completed in September 1980. Work remaining to complete this section of the project consists of construction of fish and wildlife facilities. A reliable channel suitable for navigation is available through this section. Controlling depth at ordinary stages of the river is 9 feet, with additional depths available during high stages. Commercial navigation was inaugurated on this section in May 1939, and common carrier transportation service was inaugurated in October 1946. Seven riverside recreation sites are complete and in operation. Estimated total cost of new work Sioux City, IA to Rulo, NE is $189,632,000 (1984), of which $188,045,000 is the Federal cost of construction and $1,587,000 is the non-Federal cost, exclusive of amounts expended on previous projects. Local cooperation. Local interests must share in cost of recreation facilities in accordance with provisions of the Federal Water Project Recreation Act of 1965. Local interests have contributed for cost sharing on construction of recreation by constructing portions of the facilities. Terminal facilities. Terminal facilities for loading and unloading grain, liquids and dry bulk products are maintained by private interests at various locations on this section of the river. A complete list of terminal facilities are included in the Missouri River Navigation Maps and can be obtained from the Omaha District for a small fee. Operations during fiscal year. Maintenance: Contract maintenance work consisted of revetment and dike repair. Work by hired labor forces included repairing dikes and revetments. Local interests operate and maintain the recreation sites. 2. NAVIGATION WORK UNDER SPECIAL AUTHORIZATION Small Navigation Projects Not Specifically Authorized by Congress (Sec. 107 of the River and Harbor Act of 1960, as amended, Public Law 645, 86th Congress). No work during the period. Flood Control 3. BEAR CREEK LAKE, CO Location. Damsite is on Bear Creek in Jefferson County, CO about 8 miles above the.confluence of Bear Creek with the South Platte River at Denver. Existing project. Earthfill dam 180 feet high, with a crest length of about 5,300 feet, and a supplementary earthfill dike with a height of 65 feet and a crest length of 2,100 feet, to the south of the main dam, and an uncontrolled earth and rock-cut emergency spillway. The lake provides storage capacity of 28,831 acre-feet for flood control and 1,979 acre-feet for sediment and recreation. Construction of the project was initiated in October 1973 and was completed in September 1982, exclusive of recreation facilities. The total cost of construction was $61,503,600. Recreation facilities were developed utilizing cost sharing funds at an additional cost of $500,000. Local cooperation. Requirements are described in full on page 21-3 of fiscal year 1981 Annual Report. Operations during fiscal year. Maintenance: Work by hired labor included miscellaneous items of ordinary repair and maintenance. Annual project visitation was estimated at 116,900. 4. BOWMAN-HALEY LAKE, ND Location. Damsite is on North Fork of Grand River in southwestern North Dakota, about 6 miles above Haley, ND. Existing project. A dam 79 feet high, with a crest length of 5,730 feet, and reservoir with a storage capacity of about 19,780 acre-feet for sediment storage, fish and wildlife conservation, recreation, and future water supply for communities of Bowman, Reeder, Scranton, and Gascoyne, ND. Construction was initiated in July 1964, and the project was completed in 1970. (See Table 21-A for total cost of construction.) Local cooperation. Local interests must prevent encroachment on capacity of North Fork channel below reservoir; obtain water rights for storage; pay the United States for costs allocated to water supply; and hold the United States free from daimages. Assurances of local cooperation were approved June 19, 1964. With respect to water rights, requirements have been complied with. A contract with the Bowman County Water Management District for water storage space was signed November 10, 1981. Operations during fiscal year. Maintenance: Operation and maintenance activities included sedimentation and reservoir regulation studies and intermittent inspections of the dam and structures. Annual project visitation was estimated at 35,200. 5. CHATFIELD LAKE, CO Location. On the South Platte River, just below the mouth of Plum Creek, about eight miles upstream from Denver, CO. Existing project. Consists of rolled earth-fill dam 21-2 OMAHA, NE, DISTRICT with a maximum height of 148 feet, a crest length of 12,500 feet, and a reservoir with flood control capacity of 204,737 acre-feet and sediment capacity of 26,692 acre-feet, which will be used for recreation, and an enlarged channel from the dam downstream to Denver to accommodate reservoir flood releases. The Corps is participating with local interests in acquisition of lands and development of recreation facilities immediately downstream of the Chatfield Dam in lieu of a portion of the channel improvement. Construction of the project was initiated in August 1967 and is 97 percent complete, with a scheduled completion date in FY 1988. Construction is essentially complete at the project with the exception of the downstream channel improvement, associated recreation facilities and fish and wildlife mitigation measures. Estimated cost through construction of the project is $105,130,000 (1985) of which $95,600,000 is the Federal cost for construction, $6,630,000 local cost in connection with the downstream channel improvement, and $2,900,000 is the local cost for acquisition of water for the recreation pool. Local cooperation. Section 3, Flood Control Act of June 22, 1936 applies to the downstream channel improvement. The Colorado Water Conservation Board provided assurances of local cooperation for the downstream improvement on December 13, 1967. Local interests must provide water for filling the sediment reserve pool for recreation use which the state agreed to on April 25, 1967. Operations during fiscal year. Continued design by hired labor. Completed construction on Stage I of the downstream channel improvements. Initiated construction on Union Avenue Weir and Stage II of the downstream channel improvements. Maintenance: continued routine operation and maintenance activities. Annual project visitation was estimated at 1,207,600. 6. CHERRY CREEK LAKE, CO Location. Damsite is on Cherry Creek in Arapahoe County, CO, approximately 6 miles southeast of Denver, CO just outside of city limits. Cherry Creek joins South Platte River within city limits of Denver. Existing project. A rolled-earthfill dam with maximum height of 141 feet above streambed and 14,300 feet long. Project includes a reinforced concrete outlet works and an uncontrolled side channel spillway canal discharging into adjacent Toll Gate Creek. Cherry Creek project provides reservoir storage capacity of 93,920 acre-feet below spillway canal invert and, in addition, a surcharge storage of 134,470 acre-feet. Plan of operation in ultimate development for multiple-purpose uses includes 13,960 acre-feet for sediment storage and 79,960 acre-feet for conservation purposes. Construction began in fiscal year 1946 and was completed in June 1961, exclusive of recreation facilities. Federal cost of the project was $15,338,000. Local cooperation. None required except for recreation cost-sharing. Operations during fiscal year. New work: Recreational development was continued. Maintenance: Operation and maintenance activities include administration of project area, completion of emergency gate installation, and miscellaneous items of ordinary repair and maintenance. Annual project visitation was estimated at 1,607,200. 7. EAST NISHNABOTNA RIVER AT RED OAK, IA Location. On the East Nishnabotna River on the western edge of Red Oak in Montgomery County, IA. Existing Project. The work on the original project was initiated in April 1962 and completed in October 1962. The work consisted of 10,500 feet of levee along the west edge of Red Oak. The cost when completed (1962) was $443,000, of which $400,000 was Federal and $43,000 non-Federal. Flooding subsequent to completion of the project raised concerns about the adequacy of the project. A study was made and the recommendation to raise the existing project to standard project flood protection was approved February 1981. This work is currently estimated at $1,854,000, of which $1,754,000 is the Federal cost and $100,000 is the non-Federal cost for necessary rights of way and utility relocations. Local cooperation. A 221 contract to sponsor the project was furnished by the City of Red Oak and was approved on September 21, 1981. Operations during fiscal year. O&M manuals were completed in July 1985. 8. FALL RIVER BASIN, SD Location. In Custer and Fall River Counties, in and near the town of Hot Springs, SD. Hot Springs unit is in the town of Hot Springs, immediately south of the junction of Cold Brook and Hot Brook which combine to form the Fall River. Cold Brook Lake unit is approximately 1.25 miles north of the town of Hot Springs on Cold Brook; and Cottonwood Springs Lake unit is approximately 4.5 miles west of the town of Hot Springs on Cottonwood Springs Creek, one-half mile upstream from its confluence with Hot Brook. Existing project. The general plan of improvement provides flood protection for Hot Springs, SD. The Hot Springs channel improvement unit consisted of widening, deepening and straightening 6,000 feet of channel of Fall River. The Cold Brook Lake unit, an earth-fill dam with appurtenant structures, controls an area of 70.5 square miles. The Cottonwood Springs Lake unit consists of an earth-fill dam with appurtenant structures and controls an area of 26 square miles. Construction of Hot Springs unit was completed during fiscal year 1951. Construction of Cold Brook unit dam and appurtenances was completed in fiscal year 1953 with exception of a road and parking area which were completed in fiscal year 1955. Construction of the Cottonwood Springs unit dam was completed in fiscal year 1970, with the exception of the recreation facilities which were completed in fiscal year 1972. (See Table 21-A for total cost of construction.) For last funding see FY 1981 Annual Report. 21-3 REPORT OF THE CHIEF OF ENGINEERS. U.S. ARMY 1985 Local cooperation. Local cooperation requirements have been fully complied with. Operations during fiscal year. Maintenance: Routine operation and maintenance activities were continued on the Cottonwood Springs and Cold Brook Dams and structures. Annual project visitation was estimated for Cold Brook Lake and Cottonwood Springs Lake at 48,600 and 11,100 respectively. 9. GREAT FALLS, MT Location. In Great Falls, Cascade County, MT at confluence of the Sun and Missouri Rivers. Existing project. Provides for levees along the left bank of the Sun River and an interceptor ditch and closed conduit to collect and convey side-hill runoff to the Sun River. Estimated cost through construction of the project is $13,957,000 of which $11,907,000 is the Federal cost of construction and $2,050,000 is the local cost for lands, relocations and a cash contribution for replacement of a storm sewer conduit desired by local interests. Local cooperation. Section 3. Flood Control Act of June 22, 1936 applies. In addition local interests must zone the unleveed portion of the flood channel through the damage area to preserve its capacity and to prevent further encroachments and contribute in cash $179,000 representing the estimated cost of replaced storm drainage facilities which will be incorporated into the closed conduit of the Watson Coulee Interceptor. West Great Falls Flood Control and Drainage District provided assurances on January 17, 1968. State Supreme Court decision on assessments required a change in state law, which was enacted in 1973. The final court ruling on compliance was made April 1, 1981, and the local sponsor was instructed to proceed toward project construction Operations during fiscal year. Work continued on the Sun River left bank levees and channels contract. Initiated work on flood proof sewer and on O&M manuals. Engineering and design continued by hired labor. 10. INDIAN CREEK AT EMERSON, IA Location. The project is located in Mills County along the right bank of Indian Creek just east of the city of Emerson, Iowa. Existing project. This project consists of raising old Highway 34 and constructing a levee 180 feet long. This project provides protection to commercial and residential areas. The estimated project cost is $333,000 (1985). Local cooperation. The local sponsor is responsible for all necessary rights-of-way and utility relocations. The city of Emerson, IA is the local sponsor. Assurances of local cooperation were provided by the local sponsor on June 24, 1983. Operations during fiscal year. Installation of a flood warning system was completed. Initiated work on O&M manuals. 11. LITTLE SIOUX RIVER, IA Location. The project is located in the lower portion of the Little Sioux River Basin in Harrison and Monona Counties, IA, near the confluence of the Little Sioux and Missouri Rivers. Previous Project. For details see page 646, Annual Report for 1970. Existing project. Construction of the original project was completed in June 1966. Sill No. 4 was identified as a design deficiency in a June 17, 1981 report by the Omaha District, approved by OCE. Based on that report, design studies for a permanent solution to the problem were completed. Estimated cost of the new work is $5,017,000 (1985). Local cooperation. The Little Sioux Inter-County Drainage District was sponsor of that portion of the original project where the remedial work is being accomplished. Remedial work was 100 percent Federally funded. Operations during fiscal year. A construction contract was awarded on August 3, 1984 and work was completed on September 18, 1985, with the exception of seeding. 12. LOST CREEK AT COLUMBUS, NE Location. On Lost Creek just north of the City of Columbus in Platte County, NE. Existing project. This project provides levee and channel improvements on the north side of Columbus and provides protection to commercial and residential areas. The estimated cost of the construction is $4,260,000 (1985) of which $3,400,000 is the Federal cost, and $860,000 is non-Federal contributed funds - other, that provides for all necessary right of way, utility, and bridge relocations. Local cooperation. A contract with the City of Columbus to sponsor the project was approved on February 18, 1982. Operations during fiscal year. Construction continued on Stage 2. Initiated work on O&M manuals. 13. MISSOURI NATIONAL RECREATIONAL RIVER, NE, AND SD Location. NE and SD. The Missouri River between Gavins Point Dam and Ponca State Park, NE. This includes Cedar and Dixon Counties in Nebraska, and Yankton, Clay, and Union Counties in South Dakota. Existing project. The designation as a National Recreational River will preserve outstanding and important scenic values and will provide additional opportunities for river access and recreation use. Erosion control, consisting of bank stabilization and river management techniques designed to preserve the existing environment, will at the same time preserve high bank flood plain lands. Estimated total cost of construction is $21,000,000. (See Table 21-A for total costs.) Local cooperation. Requirements of local cooperation 21-4 OMAHA, NE, DISTRICT will be determined in accordance with administrative policy. Operations during fiscal year. Continued coordination with the National Park Service. 14. MISSOURI RIVER, GARRISON DAM TO LAKE OAHE, ND Location. Along the channel of Missouri River between Garrison Dam and headwaters of Oahe Reservoir in North Dakota. Existing project. Consists of bank stabilization and rectification works required to stabilize banks of Missouri River in specific areas and prevent further loss of agricultural lands through erosion. Construction was initiated January 1965 and project is complete. Estimated total cost is $9,711,000 (1985) of which $9,441,000 is the Federal cost of construction and $270,000 is the non- Federal cost for all lands, easements, and rights of way. Local cooperation. Section 3, Flood Control Act of June 22, 1936, applies. Operations during fiscal year. All work is complete. Contractor claim remains unresolved. 15. MISSOURI RIVER, KENSLERS BEND, NE, TO SIOUX CITY, IA Location. Project is along Missouri River between Ponca Bend, NE, and combination bridge at Sioux City, IA. Existing project. Construction of dikes, revetments and channel improvement along Missouri River from Miners Bend and vicinity, SD and NE, to Sioux City, IA. Project was started in June 1946 and completed in June 1961. (See Table 21-A for total costs.) Local cooperation. Fully complied with. Operations during fiscal year. Maintenance consisted of dike and revetment repair. 16. MISSOURI RIVER LEVEE SYSTEM, IOWA, NEBRASKA, KANSAS AND MISSOURI (SIOUX CITY, IA TO RULO, NE) Location. On both banks of the Missouri River from Sioux City, IA to St. Louis, MO. Active portion of the project in Omaha District extends from Council Bluffs, IA to Rulo, NE. Existing project. A series of levee units and appurtenant works along both sides of Missouri River from Sioux City, IA, to mouth, for protection of agricultural lands and small communities against floods. Construction was initiated June 1948. (See Table 21-H for status of active units). Construction was initiated on Levee Unit L-611-614 in September 1980 and is 98 percent complete. Construction of Unit R-616 was initiated in May 1983 and is 98 percent complete. Cost estimate for active portion of project from Council Bluffs, IA to Rulo, NE is $42,100,000 (1985) of which $37,500,000 is Federal cost for construction and $4,600,000 local costs for lands and damages. Local cooperation. Section 3, Flood Control Act of June 22, 1936 applies. Fully complied with for all completed units. Local interests have furnished assurances of their willingness and ability to fulfill local cooperation requirements for the remaining active units. Operations during fiscal year. Construction of Levee Unit L-611-614, Stage 3 and Unit R-616 continued. Initiated work on Stage 1 Fish & Wildlife Facilities and drainage improvements to L-611-614. 17. PAPILLION CREEK AND TRIBUTARIES LAKES, NE Location. The Papillion Creek basin is located in Washington, Douglas, and Sarpy Counties, NE. Big Papillion Creek rises west of Blair, flows southeasterly through metropolitan Omaha area where it is joined by the Little Papillion Creek just above Offutt AFB, forming Papillion Creek. The combined creek flows along the side of Offutt AFB to its confluence with the Missouri River. Existing project. The active project consists of a series of four dams and reservoirs on tributaries of Papillion Creek. Construction was initiated in FY 1972. Completed projects include Standing Bear Lake (Site 16) December 1978 and Glenn Cunningham Lake (Site 11) December 1979. Construction of the dam portions of Sites 18 and 20 are complete. Remaining work includes construction of recreational facilities at both sites. A restudy of remaining flood problems in the Papillion Creek Basin, as directed by the Appropriations Committee for FY 1982, is complete. Estimated total costs for the project are $48,000,000 Federal funds with $3,272,000 non-Federal reimbursement. Local cooperation. Requirements are described in full on page 21-6 of fiscal year 1981 Annual Report. Operations during fiscal year. Design for Sites 18 and 20 continued by hired labor. Construction continued at Sites 18 and 20. Maintenance: Routine operations and maintenance activities continued at Sites 11 and 16. Annual project visitation was estimated at 1,367,800. 18. PICK-SLOAN MISSOURI BASIN PROGRAM (OMAHA DISTRICT) Location. Flood control improvements in this project are along Missouri River and several of its principal tributaries and in states comprising Missouri River Basin. Existing project. A general comprehensive plan for flood control and other purposes in Missouri River Basin provides for levees along Missouri River between Sioux City, IA, and mouth and reservoirs on main stem of Missouri River and tributaries. See individual reports and Table 21-I for projects in the Omaha District included in the program. 19. PIPESTEM LAKE, ND Location. On Pipestem Creek in Stutsman County, ND, 3 miles upstream from where Pipestem Creek joins the James River at Jamestown, ND. 21-5 REPORT OF THE CHIEF OF ENGINEERS. U.S. ARMY 1985 Existing project. The project consists of a rolled earth-fill dam approximately 108 feet high with a crest length of 4,000 feet and outlet works of a gated reinforced concrete conduit. The reservoir provides 146,880 acre-feet of storage. The multipurpose pool provides space for silt storage and 885 acres of water surface for fish, wildlife and recreation needs. Construction of the project was initiated in FY 1970 and completed in FY 1977. (See Table 21-A for total construction costs.) Local cooperation. Local interests are required to administer project land and water areas for recreation and fish and wildlife enhancement and to bear the first cost of associated improvements in the wildlife management area; pay, contribute in kind, or repay, with interest, one-half of the separable cost of the project allocated to recreation and fish and wildlife enhancement; and bear all costs of operation, maintenance, and replacement of recreation and fish and wildlife lands and facilities. Operations during fiscal year. Routine operation and maintenance activities continued. Annual project visitation was estimated at 119,700. 20. SALT CREEK AND TRIBUTARIES, NE Location. Salt Creek Basin comprises an area of about 1,627 square miles in and around Lincoln in southeastern Nebraska. Existing project. The authorized project consists of a system of 10 dams and reservoirs, channel clearing, enlarging and realignment, levees and necessary bridge alterations. Pursuant to Senate Resolution adopted August 7, 1964, which authorized a review of Salt Creek survey report, remaining units were placed in "inactive" classification. Construction of the project beganin the spring of 1962. All work under the active portion of the project, consisting of the 10 dams and reservoirs and the channel improvements and levees through Lincoln, was completed in 1969. Funds were transferred to the project in FY 1980 with concurrence of Congressional Committees. These funds were used to determine an effective method of correction for the dispersive clay problem in the completed downstream levees through Lincoln. Local cooperation. Fully complied with for the completed levee and channel improvement part of the project. For the dams, local interests are required to operate and maintain the permanent pools for fish and wildlife conservation and assume all costs related to utilization of the permanent pools for recreational purposes and insure public access to the pools. Operations during fiscal year. The interim reports forwarded during FY 1983, to higher authorities were inconclusive and another report was submitted in September 1985 utilizing further testing results. A Final Report was submitted in October 1985. Maintenance: Operation and maintenance activities included sedimentation and reservoir regulation studies, intermittent inspections of the dams and structures. Annual visitation to the system of dams was estimated at 4,383,100. 21. SOUTH PLATTE RIVER BASIN, CO Location. Flood control improvements in this project are along the South Platte River and its tributaries in Colorado. Existing project. General plan for flood control and other purposes provides for construction of Chatfield Lake on the South Platte River, Bear Creek Lake on Bear Creek, and levee and channel improvements on the South Platte River. (See individual reports and Table 21-B for authorizing legislation). 22. INSPECTION OF COMPLETED FLOOD CONTROL WORKS Flood Control Act of June 22, 1936, and subsequent acts require local interests to furnish assurances that they will maintain and operate certain local protection projects after completion, in accordance with regulations prescribed by Secretary of the Army. District Engineers are responsible for administration of these regulations within the boundaries of their respective districts. Inspections of completed local protection projects which have been turned over to local interests for maintenance and operation during the fiscal year are set forth in Table 21-J, Inspections of Completed Local Protection Projects. Fiscal year costs were $232,800. - Inspection of Non Federal flood protection works was initiated in FY 1984. The cost incurred for FY 1985 was $44,500. 23. SCHEDULING FLOOD CONTROL RESERVOIR OPERATIONS Under sections 7 and 9, Flood Control Act of December 22, 1944, Corps of Engineers is responsible for detailed scheduling of operations involving storage capacity reserved for or assigned to flood control in reservoirs constructed by Bureau of Reclamation as well as those constructed by Corps of Engineers. Costs for FY 1985 were $269,355 and total costs to September 30, 1985 were $4,536,697. 24. FLOOD CONTROL ACTIVITIES UNDER SPECIAL AUTHIORIZATION Emergency Flood Control Activities - Repair, Flood Fighting and Rescue Work (Public Law 99, 84th Cong., and antecedent legislation). Federal costs for FY 1985 were $154,041 for disaster preparedness, and $622,471 for repair and restoration. Small Flood Control Projects Not Specifically Authorized by Congress (Sec. 205, 1948 Flood Control Act as mended, Public Law 858, 80th Cong., June 30, 1948). Stage II construction continued on Lost Creek at Columbus, NE. Installation of a flood warning system was completed on Indian Creek at Emerson, IA. O&M manuals were completed on East Nishnabotna River at Red Oak, IA. Work continued in preparation for the construction stage for projects on Pebble Creek, Scribner, 21-6 OMAHA, NE, DISTRICT NE; Platte River, Cedar Creek, NE; Lodgepole Creek, Sidney, NE; and Lower Heart River, Mandan, ND. Five negative Initial Appraisal Studies were submitted during FY 85 at a total cost of $36,300. Emergency Bank Protection (Sec. 14,1946 Flood Control Act, Public Law 526, 79th Cong., July 24, 1946). Operations under this heading were as follows: Construction of revetment and windrow refusals was initiated at two sites on the South Platte River at Kersey and Merino, CO. Construction was completed on four projects in Colorado; one project on the Big Thompson River at Johnstown, two projects on the South Platte River at Platteville and Iliff, and one project on the Cache La Poudre River at Windsor. Construction of streambank protective measures along the Yellowstone River near Glendive, MT was completed and O&M manuals are currently underway. On the Vermillion River near Vermillion, SD (Sewer Line) construction of a stone-fill revetment with windrow refusals was initiated. O&M manuals were completed for the erosion control project on the Shoshone River at Byron, WY. Construction was completed at three county road bridges on Elm Creek southwest of Decatur in Burt County, NE and at the Broadway Street Bridge in Decatur. Work on O&M manuals is underway for these projects. O&M manuals are currently underway for a bank stabilization project along Muddy Creek near Syracuse, NE. O&M manuals were completed on Middle Pebble Creek, Waste Water Treatment Plant at Snyder, NE. Construction on the West Papillion Creek was initiated to provide protection to a county road and a sanitary sewer line in Douglas County, NE. The project along Salt Creek in Lincoln, NE was completed this FY and will now provide protection to the Lincoln Sewage Treatment Facility. Construction was completed and O&M manuals have been initiated for a project located on the left bank of the Platte River adjacent to the sewage lagoons near Brady, NE. Multiple-Purpose Projects Including Power 25. BIG BEND DAM-LAKE SHARPE, MISSOURI RIVER BASIN, SD Location. On Missouri River, 987.4 miles above mouth, near Fort Thompson, SD, and approximately 20 miles upstream from Chamberlain, SD. Dam is located in the upstream reach of Fort Randall Reservoir. Big Bend Reservoir extends upstream to Pierre, SD. Existing project. A rolled-earthfill dam 95 feet high, with a crest length of 10,570 feet, a hydroelectric generating plant consisting of eight 58,500 kilowatt units, and a chute-type gated spillway. Reservoir provides gross storage of 1,883,000 acre-feet. Federal cost of the project was $107,523,000. Construction began in September 1959 and was completed in September 1977, except for Code 710 recreation facilities. On September 30, 1985, reservoir pool was at elevation 1420.8 feet mean sea level and a total volume of 1,747,000 acre-feet of water was impounded. Local cooperation. None required except for recreation cost-sharing. Operations during fiscal year. Public use facilities were constructed with Code 710 funds. Maintenance: Project was operated in conjunction with other Missouri River reservoirs for flood control, power production and other multiple uses. During the period, 1,058,964,000 net kilowatt-hours of electricity were produced. Installation of a power plant controller system for the Missouri River dams continued. Initiated work on the reservoir boundary survey. Annual project visitation was estimated at 906,600. 26. FORT PECK LAKE, MT Location. Reservoir is in Missouri River Valley in Mc- Cone, Valley, Garfield, Phillips, Petroleum, and Fergus Counties, MT. Dam is approximately 1,771.6 miles above mouth of Missouri River. Nearest towns are Glasgow, 17 miles northwest, and Nashua, 9 miles north. Existing project. A hydraulic earthfill dam with a maximum height of 251 feet, with a crest length of 21,026 feet, and a reservoir for flood control, irrigation, navigation, hydroelectric power, and other purposes, with a gross storage capacity of 18,909,000 acre-feet at maximum operating pool. Work started on original project in October 1933 and on second power plant in August 1956. The project was completed in 1965. The power installations at the project were uprated in FY 1979. The 5 generators have a total output of 185,250 KW, 2 generators at 40,000 KW each, 2 generators at 43,500 KW each and 1 generator at 18,250 KW. See page 818 of 1965 Annual Report and page 905 of 1958 Annual Report for project details. Federal cost of the project was $158,428,000. Local cooperation. None required except for recreation cost-sharing. Operations during fiscal year. Maintenance: Installation of a powerplant controller system for the six Missouri River dams and installation of the fire detection and security system continued. Initiated work on rehab. of spillway storm drain, rehab. 13.8 KV bussing and cables, rehab. townsites streets and sidewalks and sewage system improvements. Fort Peck Lake was operated in conjunction with the other Missouri River reservoirs for flood control, navigation, power production, and other multi-purpose uses. Generating facilities produced 1,274,096,000 net kilowatt hours of electricity. Total cost of Operation and Maintenance during the period was $6,242,400, however, reimbursement from the Western Area Power Administration for the prorata share of Operation and Maintenance cost of the power plant, reimbursement for furnishing operator's village facilities, and property disposals reduced net cost to $3,968,100. Annual project visitation was estimated at 605,400. On September 30, 1985, the pool was at elevation 2228.7 and 14,141,000 acre-feet of water was impounded in the reservoir. 27. FORT RANDALL DAM-LAKE FRANCIS CASE, MISSOURI RIVER BASIN, SD Location. On Missouri River in Charles Mix and 21-7 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Gregory Counties, SD, about 82 miles above Yankton, SD. Site is 880 miles above mouth of Missouri River and 148 miles above Sioux City, IA. Existing project. A rolled-earthfill dam with a maximum height of 165 feet, a crest length of 10,700 feet, and a reservoir for flood control, irrigation, navigation, hydroelectric power, and other purposes, with a gross storage capacity of 5,574,000 acre-feet at maximum op.- erating pool. The power installation consists of eight units rated at 40,000 kilowatts each. Construction began in May 1946 and was completed in 1969, except for Code 710 recreation facilities. On September 30, 1985, reservoir pool was at elevation 1353.4 feet mean sea level, and a total volume of 3,557,000 acre-feet of water was impounded. Federal cost of the project was $199,066,000. Non-Federal contribution for constructing approaches to the Platte-Winner Bridge was $720,000. Local cooperation. None required except for recreation cost-sharing. Operations during fiscal year. Maintenance: Project was operated in conjunction with other Missouri River reservoirs for flood control, navigation, power production, and other multiple uses. Generating facilities produced 1,892,554,000 net kilowatt-hours of electricity. Installation of a power plant controller system for the Missouri River dams and installation of the fire detection and security system continued. Initiated work on protective coating power penstock #1, West Chamberlin erosion repair and painting transformers C & D. Annual project visitation was estimated at 2,123,200. 28. GARRISON DAM-LAKE SAKAKAWEA, MISSOURI RIVER BASIN, ND Location. On Missouri River in McLean and Mercer Counties, ND, about 11 miles south of Garrison, ND, and 9 miles west of Coleharbor, ND. 1,389.9 miles above mouth of river and 75 miles above Bismarck, ND. Existing project. A rolled-earthfill dam 11,300 feet long with a maximum height of 210 feet and a reservoir for flood control, irrigation, navigation, hydroelectric power, and other purposes, with a gross storage capacity of 24,137,000 acre-feet. It provides five power units, three units rated at 80,000 kilowatts each, and two units rated at 95,000 kilowatts each, three flood control tunnels and a gated spillway. Federal cost of the project was $299,938,000 including $4,208,000 for major rehabilitation. Non-Federal contribution in connection with widening Snake Creek Embankment was $687,000. Construction of the project was initiated in April 1946 and completed in 1966, except for recreational development using Code 710 funds. On September 30, 1985, pool elevation was 1838.4 and 18,495,000 acre-feet of water was impounded. Local cooperation. None required except cost sharing with the State of North Dakota for widening the Snake Creek Embankment and recreation cost-sharing. Operations during fiscal year. Maintenance: Project was operated in conjunction with the other Missouri River reservoirs for flood control, navigation, power production, and other multiple purpose uses. Normal operation and maintenance procedures were accomplished during the fiscal year. Generating facilities produced 2,379,343,000 net kilowatt-hours of electricity. Installation of a power plant controller system for the Missouri River dams continued. Rehabilitation of stator windings and installation of fire detection & security system continued. Initiated work on rehab. of spillway and emergency gates, crest road lighting replacement, and boundary rectification. Annual project visitation was estimated at 2,481,100. 29. GAVINS POINT DAM-LEWIS AND CLARK LAKE, MISSOURI RIVER BASIN, NE AND SD Location. On Missouri River in Yankton County, SD, and Knox County, NE, about 4 miles upstream from Yankton, SD, and 811.1 miles above mouth of river. Existing project. A concrete and rolled-earth-fill dam with a maximum height of 74 feet and a reservoir for flood control, irrigation, navigation, hydroelectric power, and other purposes with a gross storage capacity of 504,000 acre-feet at maximum operating pool. The power installation consists of three units rated at 33,333 kilowatts each. Federal cost of the project was $49,539,000. Construction of original project was initiated in March 1952 and was completed in 1964. Project is providing its multiple purpose benefits for flood control, navigation, power, and other uses. On September 30, 1985, pool elevation was 1208.3 and a total volume of 451,000 acre-feet of water was impounded. Local cooperation. None required except for recreation cost-sharing. Operations during fiscal year. Maintenance: Project was operated in conjunction with other Missouri River reservoirs for flood control, navigation, power production and other multiple purpose uses. Generating units produced 791,739,000 net kilowatt-hours of electricity during fiscal year. Installation of a power plant controller system for the Missouri River dams continued and rehabilitation of spillway gates and bulkheads was initiated., Annual project visitation was estimated at 2,523,000. 30. OAHE DAM-LAKE OAHE, MISSOURI RIVER BASIN, SD AND ND Location. Dam is on Missouri River in Hughes and Stanley Counties, SD, about 6 miles northwest of Pierre, SD, and 1,072.3 miles above mouth of river. Existing project. A rolled-earthfill dam with maximum height of 245 feet, a crest length of 9,300 feet, and reservoir for flood control, irrigation, navigation, hydroelectric power, and other purposes, with a gross storage capacity of 23,337,000 acre-feet at maximum operating pool. It contains seven power units rated at 85,000 kilowatts each. Federal cost of the project was $346,521,000. Construction was initiated August 1948 and project placed in operation June 1963. Land acquisition is 99 percent complete. On September 30, 1985, pool eleva- 21-8 OMAHA, NE. DISTRICT tion was 1601.7 and a total volume of 17,335,000 acrefeet of water was impounded. Local cooperation. None required except for recreation cost-sharing. Operations during fiscal year. Maintenance: Project was operated in conjunction with the other Missouri River reservoirs for flood control, navigation, power production and other multiple purpose uses. Generating facilities produced 2,965,612,000 net kilowatt-hours of electricity. Installation of a power plant controller system on the Missouri River dams continued. Annual project visitation was estimated at 2,997,400. Miscellaneous 31. STREAMBANK EROSION CONTROL EVALUATION AND DEMONSTRATION PROJECT Location. Along the Missouri River between Garrison Dam and Lake Oahe, ND and between Fort Randall Dam and Sioux City, IA; along the Yellowstone River in Montana and North Dakota; and along undesignated rivers and streams in the Omaha District. Existing project. The project provides for development of new methods and techniques for bank protection. It consists of various experimental bank stabilization structures designed to stabilize the river banks and prevent further loss of land through erosion. Construction was initiated in November 1976 on the Missouri River between Garrison Dam and Lake Oahe and between Gavins Point Dam and Sioux-City, IA. Construction was initiated in August 1978 on the Missouri River between Fort Randall Dam and Lewis & Clark Lake. Construction was initiated in October 1980 on the Yellowstone River between Intake, MT and the mouth. Construction has been completed at a total Federal cost of $17,485,000. Local cooperation. Requirements are described in full on page 21-9 of Fiscal Year 1983 Annual Report. Operations during fiscal year. Project completed based on OCE guidelines. 32. GENERAL INVESTIGATIONS Fiscal Year 1985 costs totaled $2,197,632 for all General Investigation activities. See Table 21-K which covers Surveys, Collection and Study of Basic Data, Research and Development, Continuation of Planning and Engineering, Planning and Engineering under Proposed Program Legislation, and Advance Engineering and Design. 21-9 TABLE 21-A See Section in Text Project Missouri River, Sioux City, IA to Rulo, NE 3. Bear Creek Lake, CO 4. Bowman-Haley Lake, ND 5. Chatfield Lake., CO (Required Contributed Funds) (Consolidated Summary) 6. Cherry Creek Lake, CO 7. East Nishnabotna River at Red Oak, IA 8. Fall River Basin, SD 9. Great Falls, MT (Required Contributed Funds) (Consolidated Summary) 10. Indian Creek, Emerson, IA 11. Little Sioux River and Tributaries, IA REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 COST AND FINANCIAL STATEMENT 1. Total Thru FY 82 FY 83 FY 84 FY 85 Sep 30, 1985 i i Funding New Work: Approp. Cost Maint. Approp. Cost New Work: Approp. Cost Maint. Approp. Cost New Work: Approp. Cost Maint. Approp. Cost New Work: Approp. Cost New Work: Approp. Cost New Work: Approp. Cost Maint. Approp. Cost New Work: Approp. Cost Maint. Approp. Cost New Work: Approp. Cost New Work: Approp. Cost Maint. Approp. Cost New Work: Approp. Cost New Work: Approp. Cost New Work: Approp. Cost New Work: Approp. Cost New Work: Approp. Cost 83 1,691,000 1,697,737 242,000 254,530 197,000 209,971 177,000 189,624 633,000 608,748 633,000 608,748 262.000 270,880 282,000 305,660 1,207,000 1.145,430 207,000 203,571 3,250,000 2,858,217 129,600 179,000 3.379,600 3,037,217 30 3.045,000 2,569,622 48,323 274.000 171,428 150,000 139,705 442,000 509,808 442,000 509,808 291,000 291,525 744,000 421,538 344,000 402,380 316.000 288,836 6,950,000 6,217,952 1,660 1,544,000 2,018,572 470,000 501,369 332,000 440,291 99,000 112,048 1,600,000 889,677 530,250 2.130,250 889,677 456,000 451,280 285,000 284,444 831,000 1,150,517 14.000 8,995 296,000 326.557 200,000 1,235,141 200,000 1,235,141 -42,000 228.337 1,300,000 1,291,413 2,330,000 2,306,324 1,073 261,000 258,363 168,000 168,693 2,022,000 2,573,718 150.980 492,748 2,172,980 3,066,466 625,000 623,240 -177,023 373,000 374,702 -3,000 13,792 253,000 260,565 92,375 129,600 221,975 50,506 3,467,000 3,288,990 21.10 189,225.9911 189,225,9911 102.131,419 102,103,771 62,003,600 62,003,583 1.365,000 1,357,789 4,372,174 4.372,174 1,543,043 1,542,588 90,598,700 90,402,291 681,230 492,748 91,279,930 90,895,039 2,301,800 2,292,409 15,338,364 15,160,785 5,022,511 5,020,357 2,154.016 2,153,155 5,538,432 5,538,432 2,778,141 2,775,774 11,192,1124 11,183,0454 308,600 308,600 11,500,7124 11,491.6454 I 333,000 326,119 20,499,920 20,308,804 6,950,000 6.217,952 375,000 47,276 250,000 245,482 OMAHA, NE, DISTRICT TABLE 21-A (Continued) See Section in Text Project 12. Lost Creek, Columbus, NE !Required Contributed Funds) (Consolidated Summary) 13. Missouri National Recreational River NE & SD 14. Missouri River, Garrison Dam to Lake Oahe, ND 15. Missouri River, Kenslers Bend, NE, to Sioux City, IA 16. Missouri River, Levees, IA, NE, KS & MO (Required Contributed Funds) (Consolidated Summary) 17. Papillion Creek and Tributaries Lakes, NE 19. Pipestem Lake, ND 20. Salt Creek and Tributaries. NE 22. Inspections of Completed Local Protection Projects 22. Inspection of Non-Federal Levees 23. Scheduling Flood Control Reservoir Operations COST AND FINANCIAL STATEMENT Total Thru Funding FY 82 FY 83 FY 84 FY 85 Sep 30, 1985 New Work: Approp. Cost New Work: Approp. Cost New Work: Approp. Cost New Work: Approp. Cost Maint. Approp. Cost New Work: Approp. Cost New Work: Approp. Cost Maint. Approp. Cost New Work: Approp. Cost New Work: Approp. Cost New Work: Approp. Cost New Work: Approp. Cost Maint. Approp. Cost New Work: Approp. Cost Maint. Approp. Cost New Work: Approp. Cost Maint. Approp. Cost Maint. Approp. Cost Maint. Approp. Cost Maint. Approp. Cost 225,000 144,535 14,000 13.494 239,000 158,029 800 16,260 120,000 144,138 53,000 57,358 2,830,000 2,263,149 2,830,000 2,263,149 4.186,000 4,343,351 171,000 192,609 229,000 234,438 22,456 462,000 472,104 239,000 226.095 199,000 212,738 1,367,000 - 703,300 610,869 5,000 - - 8.345 1,372,000 - 703,300 619.214 - 20,000 6,698 215 - 200.000 - 32,073 1,300.000 1.,165,133 128,300 392 1,428,300 1,165,525 8,957 35,650 30,000 29,873 4,233,000 2,581,157 38,810 4.271,810 2.581,157 7,230,000 4,786,701 209,000 187.375 332,000 261,478 13,539 495,000 493.631 202,000 203.197 27,000 26,099 222,000 220,935 -. 40,000 37,996 495,000 1,269,792 495,000 1,269,792 3.655,000 6,943,608 198,000 205,100 -_ 310,000 375,541 10,045 457,000 444,306 311,000 276,596 46,000 46,094 209,000 208,870 34,000 36,231 1,462,000 3,076,518 38,810 1,462,000 3,115,328 2,428,000 2,524,245 306,000 312,244 345,000 349,945 5,302 537,000 549,826 183,000 232,834 44,000 44,525 268,000 269,355 3.190,518 2.882,488 147.300 22.231 3,337,818 2,904,719 620,800 600,800 200,000 32,073 9,441,000 9,377,438 11,294,414 11,294,414 4,351,000 4,350,396 39,502,388 39,448,561 38,810 38,810 39,541,198 39,487.371 41,990,7625 41,961,6515 1,476,000 1,467,634 9,277,545 9,277,545 2,372,000 2,371,097 12,197,6222 12,197,4092 6,316,475 6,314,492 2,321,348 2,321,346 117,000 116,718 4,536,976 4,536,697 21-11 -- 2,883 1 Ie REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 21-A (Continued) See Section in Text Project 25. Big Bend Dam- Lake Sharpe, Missouri River Basin, SD Fu Nei Ma 26. Fort Peck Lake, Nei MT Ma 27. Fort Randall Ne Dam-Lake Francis Case, Missouri River Basin, SD Ma 28. Garrison Dam- Nei Lake Sakakawea, Missouri River Basin, ND Ma (Federal Funds) Ma (Contributed Ma Funds) 29. Gavins Point Nei Dam-Lewis & Clark Lake, Missouri River Ma Basin, SD and NE 30. Oahe Dam-Lake Nei Oahe, Missouri River Basin, SD & ND Ma 31. Streambank Nei Erosion Control Evaluation and Demonstration Proiect mnding w Work: Approp. Cost int. Approp. Cost w Work: Approp. Cost int. Approp. Cost w Work: Approp. Cost int. Approp. Cost w Work: Approp. Cost int. Approp. Cost jor Rehab Approp. Cost jor Rehab Contrib. Cost w Work: Approp. Cost int. Approp. Cost w Work: Approp. Cost int. Approp. Cost w Work: Approp. Cost COST AND FINANCIAL STATEMENT Total Thru FY 82 FY 83 FY 84 FY 85 Sep 30, 1985 -6,000 181 2,898,400 2,871,804 98,000 76.531 2,998,844 3,005,514 4,803.960 4.758,168 512,000 488,465 5,629,880 5,662,105 - 8,000 8,000 4,147,676 4,126,591 13,912 5,752,920 5,682,119 436,000 678,286 59,000 59.000 3,669,400 3,304,557 145 5.558,000 4.460,663 433,000 420,623 7,996,000 7,021,679 29,163 8,639,300 7,157,839 7,000 7,000 5,408,659 5,291.305 1,501,000 1,496,536 7,886,700 6,386,350 15,000 577.115 243,000 243,000 3,066.000 3.396,128 -22,000 1,694 2,391,000 3,470,461 455,000 464,367 6,379,000 7,162,997 287,000 296,675 6.083,000 7,543,117 130,000 130,000 3,699,000 3,817,338 737,000 746,523 7,723,000 9,237,595 31,073 33 32 3.420 3,482 -4 4,327 4.300 112 114 5,701 5,896 9,166 9,179 163 163 3,641 3,602 -308 -307 8,119 8,062 -4 .000 107,522,597 .979 107,522,576 ,000 38,910,9743 ,368 38,881,2863 - 158,428,080 ,091 158,423,880 ,000 49,408.5543 ,604 49,315,8113 ,000 199,065,883 ,700 199,065,572 ,000 73,520,8523 ,791 73,400,5473 - 295,729,613 6 295,729,613 ,000 84.773,7003 ,213 84,683,7973 - 4,208,310 - 4,208,310 - 686,961 - 686,961 ,000 49,539,239 ,000 49,539,239 ,000 55,047,1503 ,668 54,953,6113 ,000 346,520,603 ,758 346,520,588 ,000 75,890,1453 ,707 75,691,5703 - 17,485,000 ,689 17,474,568 1. Includes $18.325,581 National Industrial Recovery carried in a deferred status. Act funds, $8,625,718 Emergency Relief Funds, and 3. Includes Special Recreation Use Fees. $1,181,125 for previous project. 4. Includes $110,000 transferred to inactive portion 2. Includes $123,000 of government cost applicable for planning cost. to that portion of the project which is currently being 5. Does not include $1,854.338 cost of inactive sites. TABLE 21-B AUTHORIZING LEGISLATION See Date of Section Authorizing Project and Work in Text Act Authorized Documents 1. MISSOURI RIVER, SIOUX CITY, IA TO RULO, NE Jan 12, 1927 Appropriation of $12 million authorized for H. Doc. 1120, 60th Cong. securing a 6 foot depth from Quindaro Bend PL 75-560 (Kansas City, MO to Sioux City, IA). 21-12 OMAHA, NE, DISTRICT TABLE 21-B (Continued) AUTHORIZING LEGISLATION See Date of Section Authorizing Project and Work in Text Act Authorized Documents July 3, 1930 Aug 30, 1935 Mar 2, 1945 Aug 13, 1968 Flood Control Act of 1962 Flood Control Act of 1950 Aug 18, 1941 Dec 22, 1944 Dec 22, 1944 June 30, 1948 Aug 18, 1941 Flood Control Acts of 1955, 1965 June 30. 1948 Flood Control Act of 1954 June 30, 1948 National Parks and Recreation Act of 1978 Flood Control Acts of 1963, 1968 Appropriation of $15 million additional allotments totaling $29,153,108 made by Public Works Administration under provisions of National Industrial Recovery Act of 1938, and $9,669,791 allotted under provisions of Emergency Relief Appropriations Act of 1935. For completion of project from mouth to Sioux City, IA. For a channel of 9-foot depth and 300-foot width. BEAR CREEK LAKE, CO A flood control reservoir for protection of metropolitan Denver, CO. BOWMAN-HALEY LAKE, ND Flood control reservoir and water supply. CHATFIELD LAKE, CO Flood control reservoir and channel improvements to provide downstream protection for Denver, CO. CHERRY CREEK LAKE, CO Initiation and partial accomplishment of project. Completion of plan approved in Act of Aug 18, 1941. General comprehensive plan, Missouri River Basin. EAST NISHNABOTNA RIVER AT RED OAK, IA Levee and appurtenant structures on left bank of the East Nishnabotna River at Red Oak, IA. Section 205. FALL RIVER BASIN, SD Provide flood control to the town of Hot Springs, SD. GREAT FALLS, MT Levees and channel improvement for local protection. INDIAN CREEK AT EMERSON, IA Levee and channel improvement for local protection - Section 205. LITTLE SIOUX RIVER, IA Correction of design deficiency. LOST CREEK AT COLUMBUS, NE Levee and channel improvement for local protection - Section 205. H. Doc. 238, 73rd Cong. H. Doc. 214, 76th Cong. PL 79-14 S. Doc. 87, 90th Cong. PL 90-483 H. Doc. 574, 87th Cong. PL 87-874 H. Doc. 669, 80th Cong. PL 81-516 H. Doc. 426, 76th Cong. PL 77-228 H. Doc. 426, 76th Cong. PL 78-534 H. Doc. 475, and S. Docs. 191 and 247, 78th Cong. PL 78-534 PL 858, 80th Cong. H. Doc. 655, 76th Cong. PL 77-228 H. Doc. 343, 85th Cong. PL 85-500 PL 89-298 PL 858, 80th Cong. PL 341, 80th Cong. PL 83-780 PL 858, 80th Cong. MISSOURI NATIONAL RECREATIONAL RIVER, NE AND SD Preservation and enhancement of the Missouri PL 95-625 River between the reaches from Gavins Point Dam, NE & SD to Ponca State Park, NE. MISSOURI RIVER, GARRISON DAM TO LAKE OAHE, ND Bank stabilization and rectification. H. Doc. 343, 85th Cong. PL 88-253 PL 90-843 21-13 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 21-B (Continued) AUTHORIZING LEGISLATION See Date of Section Authorizing Project and Work in Text Act Authorized Documents 15. Aug 18, 1941 June 30, 1948 16. Aug 18, 1941 Dec 22, 1944 Flood Control Act of 1968 June 28, 1938 Aug 18, 1941 Dec 22, 1944 July 24, 1946 May 17, 1950 Sep 3, 1954 Sep 3, 1954 May 2, 1956 July 3, 1958 July 14, 1960 Dec 30. 1963 June 18, 1965 May 12, 1967 Aug 13, 1968 MISSOURI RIVER, KENSLERS BEND, NE TO SIOUX CITY, IA Construction of dike, revetments. H. Doc. 821. 76th Cong. PL 77-228 PL 80-858 MISSOURI RIVER LEVEE SYSTEM, IA, NE, KS, AND MO. Levees along both sides of river from H. Doc. 821. 76th Cong. Sioux City. IA to Kansas City, MO. PL 77-228 Extended project from Kansas City, MO to mouth H. Doc. 475, 78th Cong. and provided for increased protection. PL 78-534 S. Docs. 191 and 247, 78th Cong. PAPILLION CREEK AND TRIBUTARIES LAKES, NE Series of flood control reservoirs, providing pro- H. Doc. 349, 90th Cong. tection for the metropolitan areas of Omaha, NE. PL 90-485 17. 18. Al Committee Cong. 76th Cong. and S. Docs. 191 th Cong. and 642, 81st 3-780 84th Cong. 21-14 PICK-SLOAN MISSOURI BASIN PROGRAM (OMAHA DIST.) Adopted general comprehensive plan for Missouri Flood Contrc River Basin and authorized $9 million for Doc. 1, 75th initiation and partial accomplishment. PL 75-761 Modified general comprehensive plan to include H. Doc. 842, Harlan County Dam and Reservoir on PL 77-228 Republican River, NE and authorized additional $7 million. EMxpisasnoduerdi Rgeivneerr aBl acsoimn parnedh eanustihvoe ripzleadn afdord itional Ha.n Dd o2c4. 74, 7758,1 $200 million. PL 78-534 Authorized additional $150 million for prosecution PL 79-526 of general comprehensive plan for Missouri River Basin. Authorized additional $250 million for prosecution PL 81-516 of general comprehensive plan for Missouri River Basin. Expanded general comprehensive plan for Missouri H. Docs. 549 River Basin and authorized additional Cong. PL 8 $217,710,000. Authorized $5,384,014 to compensate Sioux PL 83-776 Indians for reservation lands required for Oahe, South Dakota project. Modified general comprehensive plan for Missouri PL 84-505 River Basin by deletion of construction of Red Willow Dam and Reservoir, NE, and addition of construction of Wilson Dam and Reservoir, KS. Expanded general comprehensive plan for Missouri H. Doc. 409, River Basin and authorized additional $200 PL 85-500 million Authorized additional $207 million for prosecution PL 86-645 of general comprehensive plan for Missouri River Basin. Authorized additional $80 million for prosecution of PL 88-253 general comprehensive plan for Missouri River Basin and modified the plan to include work protection and rectification works below Garrison Dam. Authorized additional $116 million for prosecution PL 89-042 of general comprehensive plan for Missouri River Basin. Authorized additional $20 million for prosecution PL 90-17 of general comprehensive plan for Missouri River Basin. Authorized additional $38 million for prosecution PL 90-483 of general comprehensive plan for Missouri River Basin. OMAHA, NE, DISTRICT TABLE 21-B (Continued) AUTHORIZING LEGISLATION See Date of Section Authorizing Project and Work in Text Act Authorized Documents June 19, 1970 Dec 24, 1970 Dec 31, 1970 Dec 23, 1971 Mar 7, 1974 July 8, 1976 Nov 16, 1977 Flood Control Act of 27 Oct 1965 July 3, 1958 May 17, 1950 May 12, 1967 Aug 13, 1968 June 19, 1970 Dec 23, 1971 Mar 7, 1974 July 8, 1976 Nov 16, 1977 Dec 22, 1944 Aug 30, 1935 May 18, 1938 Dec 22, 1944 June 3, 1948 Dec 22, 1944 Authorized additional $109 million for prosecution of general comprehensive plan for Missouri River Basin. Changed comprehensive plan name to Pick-Sloan Missouri Basin Program. Oahe Dam and Reservoir, ND. Authorized additional $101 million for prosecution of Pick-Sloan Missouri Basin Program. Authorized additional $72 million for prosecution of Pick-Sloan Missouri Basin Program. Authorized additional $85 million for prosecution of Pick-Sloan Missouri Basin Program. Authorized additional $59 million for prosecution of Pick-Sloan Missouri Basin Program. PIPESTEM LAKE, ND Provide flood control for Jamestown, ND and downstream areas. H. Doc. 91-748 and S. Doc. 91-895 PL 91-282 S. Doc. 91-1100. 91st Cong. PL 91-576 H. Doc. 91-23 and PL 91-611 PL 92-222 PL 93-251 PL 94-347 PL 95-189 H. Doc. 266, 89th Cong. PL 89-298 SALT CREEK AND TRIBUTARIES, NE Series of dams and channel improvements for flood H. Doc. 396, 84th Cong. control around Lincoln, NE. PL 85-500 SOUTH PLATTE RIVER BASIN, CO Adopted plan of improvement for South Platte H. Doc. 669, 80th Cong. River Basin and authorized $26.3 million for PL 81-516 initiation and partial accomplishment. Authorized additional $2 million for prosecution of plan. PL 90-17 Authorized additional $12 million for prosecution of plan PL 90-843 Authorized additional $21 million for prosecution of plan. PL 91-282 Authorized additional $37 million for prosecution of plan. PL 92-222 Authorized additional $15 million for prosecution of plan. PL 93-251 Authorized additional $22 million for prosecution of plan. PL 94-347 Authorized additional $3 million for prosecution of plan. PL 95-189 BIG BEND DAM - LAKE SHARPE, SD Expanded general comprehensive plan for flood H. Doc. 475, S. Doc. 247, control and other purposes in the Missouri 78th Cong. PL 78-534 River Basin. FORT PECK LAKE, MT Construction of earth dam. Included in Public Works Administration program in 1933. Completion, maintenance, and operation of a phryodvrioseiolencst ric powerplant, subject to certain in act respecting transmission and sale of electric energy. Also authorizes installation oSfe cardedtaitriyo nal power-generating facilities by of War when deemed necessary in judgment of Bureau of Reclamation. Modified authorization to provide for full multiple purpose operation. Payments to be made to school districts serving project as reimbursement for educational facilities (including transportation to and from school) for pupils who are dependents of persons engaged in construction, operation, and maintenance of projects. H. Doc. 238, 73rd Cong. PL 73-409 PL 75-529 H. Doc. 475 and S. Docs. 191 and 247, 78th Cong. PL 78-534 PL 80-586 FORT RANDALL DAM - LAKE FRANCIS CASE, SD Expanded general comprehensive plan for flood H. Doc. 475 and S. Docs. 191 control and other purposes in the Missouri and 247, 78th Cong. River Basin. PL 78-534 21.15 19. 20. 21. 25. 26. 27. REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 21-B (Continued) AUTHORIZING LEGISLATION See Date of Section Authorizing Project and Work in Text Act Authorized Documents 28. GARRISON DAM - LAKE SAKAKAWEA, ND Dec 22, 1944 Expanded general comprehensive plan for flood H. Doc. 475, S. Doc. 247. PWA 1968 control and other purposes in the Missouri 78th Cong. PL 78-534 River Basin. 29. GAVINS POINT DAM - LEWIS AND CLARK LAKE, NE & SD Dec 22, 1944 Expanded general comprehensive plan for flood H. Doc. 475, S. Doc. 247, control and other purposes in the Missouri 78th Cong. PL 78-534 River Basin. 30. OAHE DAM - LAKE OAHE, SD & ND Dec 22, 1944 Expanded general comprehensive plan for flood H. Doc. 475 and S. Docs. 191 control and other purposes in the Missouri and 247, 78th Cong. River Basin. PL 78-534 31. STREAMBANK EROSION CONTROL EVALUATION AND DEMONSTRATION PROJECT Mar 7, 1974 Experimental bank stabilization methods to PL 93-251 prevent losses due to erosion. TABLE 21-C OTHER AUTHORIZED NAVIGATION PROJECTS For Last Full Report Cost to September 30, 1985 See Annual Operation and Project Status Report For Construction Maintenance Missouri River, Sioux City, IA to Fort Benton, MT Complete 1948 3,123,141 644,863 Small Navigation Project at Sioux City. IA Complete 1970 43,582- TABLE 21-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS Full Report Cost to September 30, 1985 See Annual Operation and Project Status Report For Construction Maintenance Belle Fourche, Cheyenne River, SD 1 Complete 1940 37,410 - Big Sioux River at Sioux City, IA Complete 1982 7,458,934 - Blackbird Creek Near Macy, NE 2 Complete 1970 262,479 - Boulder Creek, Boulder, CO Inactive 1976 142,666 - Buffalo Creek, Meadow Grove, NE 2 Complete 1974 293,016 - Buffalo Creek, Scranton, ND 2 Complete 1960 102,980 - Buffalo, WY Inactive 1961 - - Cache La Poudre. Ft. Collins, CO Complete 1977 46,000 - Castlewood Lake, Cherry Creek and Tributaries, CO Inactive 1943 - - Cedar Canyon Dam, Rapid City, SD Complete 1960 120,482 - City of Aurora, Westerly Creek, CO Complete 1955 150,000 - Clarkson, NE, Maple Creek Complete 1967 191,282 - Council Bluffs, IA (Act of 1936) Complete 1939 - - Council Bluffs. IA (Act of 1944) Complete 1954 2,557,680 - Davids Creek Lake, IA (Act of 1968) Inactive 1972 - - Dry Creek. Hawarden, IA Complete 1964 400,000 - Eagle Bay and Fort Yates Highway Bridges, N.D. Active 1978 ti16,639 21-16 OMAHA, NE, DISTRICT TABLE 21-E (Continued) OTHER AUTHORIZED FLOOD CONTROL PROJECTS For Last Cost to September 30, 1985 Full ReportSarAat ion and See Annual Operation and Project Status Report For Construction Maintenance Floyd River, Sioux City, IA Complete 1970 11.556,667 - Forsyth, MT Complete 1950 255,177 - Frazer-Wolf Point, MT Complete 1982 435,000 - Gering Valley, NE Complete 1971 5,989,663 - Glasgow, MT Complete 1939 16,832 - Greybull, WY Complete 1960 248.507 - Havre, MT Complete 1958 1,825.881 - Herreid, Spring Creek, SD Complete 1954 50,216 - Hooper, NE 2 Complete 1968 326,667 - Ida Grove, IA 2 Complete 1972 522.344 - Jamestown Reservoir, ND Complete 1950 - - Linton, ND 2 Inactive 1973 - - Little Papillion Creek, NE Complete 1976 3,643,111 - Little Nemaha River, NE Inactive 1973 - - Loup River, Columbus, NE 2 Complete 1973 1,000,000 - Lower Big Sioux River, IA and SD Inactive 1966 - - Lower Heart River, ND Complete 1964 1,961,173 - Madison, NE, Union and Taylor Creeks2 Complete 1967 234,839 - Mandan, Heart River, ND Complete 1960 676,916 - Marmarth, ND Complete 1960 169,498 - McCook Lake, SD Complete 1958 147,627 - Miles City, MT Inactive 1956 - - Missouri River, Aten, NE Complete 1951 578,791 - Missouri River, Niobrara, NE Complete 1945 99,370 5.633 Mott, ND Deferred - - - Mud Creek, Broken Bow, NE 2 Complete 1976 1,000,000 - Nishnabotna River at Hamburg, IA Complete 1948 236,000 - Norfolk, NE Complete 1971 3,400,504 - Omaha, NE Complete 1954 5,903,640 - Pierce, NE Complete 1967 296,597 - Platte River Near Schuyler, NE 2 Complete 1948 74,940 - Platte River and Lost Creek, Schuyler. NE Complete 1971 257,398 - Platte River and Tributaries, NE Inactive - 1,538,269 - Plum Creek, Douglas County, CO Complete 1970 38,600 Rapid Creek, Rapid City, SD Complete 1980 1,004,000 Saco, MT Complete 1958 67,793 - Sacred Heart Hospital. Yankton, SD Complete 1978 184,380 - Sheridan, WY3 Complete 1976 2,618,809 - Shields River, Near Clyde Park, MT 2 Complete 1951 25,747 - Shoshone River, Lovell, WY Complete 1963 40,706 - Sioux Falls. SD Complete 1966 5,288,707 - South Platte River Levees and Channel Improvements, Chatfield Lake to Ft. Morgan. CO Inactive 1957 South Platte Near Denver, No. Wash. Sanitary District, CO Complete 1971 26,000 Vaughn, MT, Sun River2 Complete 1971 457,582 - Waterloo, NE Complete 1970 237,883 - West Point, NE Complete 1966 149,596 - Yellowstone River, W. Glendive. MT Complete 1960 230,294 1. Completed as a Public Works Administration project. 2. Authorized by Chief of Engineers. 3. Includes inactive segment. 21-17 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 21-F OTHER MULTIPLE PURPOSE PROJECTS INCLUDING POWER Fulorl Report Cost to September 30, 1985 See Annual Operation and Project Status Report For Construction Maintenance Gavins Point Dam-Lewis and Clark Lake, Relocation of Niobrara, NE Complete 1980 13,516,459 - Springfield, SD Water Intake Active - - - Williston, ND Water Intake Complete 1981 988,583 - TABLE 21-G DEAUTHORIZED PROJECTS For Last Full Report Authority Federal Contributed See Annual and Funds Funds Project Report For Date Expended Expended Billings, MT 1976 Sec. 201, FC Act 1950 75,000 - 23 Mar 81 Dayton, WY 1956 Sec. 12, PL 93-251 - - WRDA of 1974 5 Aug 77 Giles Creek, Elkhorn, NE 1952 Sec. 12, PL 93-251 - - WRDA of 1974 6 Nov 77 Indian Creek Lake, IA 1969 Sec. 12, PL 93-251 135,000 - WRDA of 1974 4 Jan 74 Morrison, Bear Creek, CO 1950 Sec. 12, PL 93-251 30,000 - WRDA Of 1974 5 Aug 77 Redwater River and 1966 Sec. 12, PL 93-251 1,000 - Hay Creek, Bell Fourche, SD WRDA of 1974 4 Jan 74 Shell Creek, NE 1962 Sec. 12, PL 93-251 71,000 - WRDA of 1974 3 Oct 78 Vermillion River and Tribs, SD 1968 Sec. 12, PL 93-251 208,000 - WRDA of 1974 4 Jan 74 TABLE 21-H MISSOURI RIVER LEVEE SYSTEM, SIOUX CITY, IA TO RULO, NE (See Section 16 of Text) Miles of Unit Levee Status L627-624 Mosquito Creek Levee 14.2 Complete 1950 L601 Watkins-Waubonsie Ditch Levees 15.0 Complete 1966 L594 Pleasant Valley Levee 11.4 Complete 1964 R580 Nebraska City Levee 0.2 Complete 1950 L575 Thurman-Hamburg Levee 45.8 Complete 1950 R573 Otto County Drainage District No. 2 5.9 Complete 1950 R562 Peru Dike 7.6 Complete 1950 L561-550 Atchison County Levee District No. 1 41.3 Complete 1952 R548 Brownville-Nemaha Levee 19.5 Complete 1952 L536 Mill Creek Levee 13.6 Complete 1952 R520 Richardson County Drainage Dist. No. 8 6.3 Complete 1960 R613 Papillion Creek-Platte River Levee 14.0 Complete 1971 R616 Bellevue-Papillion Creek Levees 4.5 Under Construction L611-614 Mosquito-Keg Creek Levees 22.0 Under Construction L627, L624, Remedial Studies on Completed Units Studies Complete L561-550 21-18 OMAHA, NE, DISTRICT TABLE 21-I PICK-SLOAN MISSOURI BASIN PROGRAM (See Section 18 of Text) Estimated Estimated Project Federal Cost Non-Federal Cost Fort Peck Lake, MT1, 2 158,428,000 1,103,000 Garrison Dam, Lake Sakakawea, ND1, 2 299,938,000 1,516,000 Missouri River Levee System, IA, NE, KS and MO (Sioux City, IA to Rulo, NE)1 ,3 37,500,000 4,600,000 Oahe Dam-Lake Oahe SD and NDI,2 346,521,000 2,320,000 Big Bend Dam-Lake Sharpe, SD1,2 107,523,000 302,000 Fort Randall Dam, Lake Francis Case, SDI,2 199,066,000 1,609,000 Gavins Point Dam, Lewis & Clark Lake, SD & NE1,2 49,539,000 137,000 Gavins Point Dam, Lewis & Clark Lake, SD & NE-Relocation of Niobrara, NE 2 13,516,000 - Omaha, NE 2 5,904,000 362,000 Council Bluffs, IA2 2,558,000 146,000 Missouri River, Garrison Dam to Lake Oahe, ND1, 2 9,441,000 270,000 Cherry Creek Lake. CO1.2 15,338,000 285,000 1 Details presented on individual report. 2 Completed. 3 Active portion of project. INSPECTION OF COMPLETED LOCAL PROTECTION PROJECTS TABLE 21-J (See Section 22 of Text) Location Month Inspected Montana Glasgow, Milk River Jun 85 Saco, Beaver Creek Jul 85 Havre, Milk River Jul85 Havre, Scott Coulee-Bull Hook Dam Jul 85 Clyde Park, Shields River Jul85 Three Forks, Lower Madison River Jun 84 Forsythe, Yellowstone River Jun 84 West Glendive, Yellowstone River May 85 Vaughn, Sun River Jun 84 *Yellowstone River, Water Plant, Livingston Sep 85 *Yellowstone River, Reedpoint Bridge Inactive *Yellowstone River, Greycliff Bridge Sep 85 *Yellowstone River, Springdale Bridge Inactive *Yellowstone River, Near Miles City Water Intake & Sewage Lagoon Inactive *Yellowstone River, Bank Protection, Billings Inactive *Yellowstone River, Yellowstone Co. Bridge, Near Billings Jun 84 *Yellowstone River, Voges Bridge, Near Big Timber Jun 84 *Jefferson River, Willow Creek Bridge, Near Three Forks Sep 85 *Jefferson River, Bank Protection, Near Waterloo Sep 85 *Big Hole River, Pennington Bridge, Near Twin Bridges Sep 85 *Ruby River, Wheatly Bridge, Near Twin Bridges Sep 85 *Big Horn River, Two Leggin Bridge. Near Hardin Inactive *Missouri River, Bank Stabilization, Fort Benton Sep 85 Wyoming Greybull, Big Horn River Jun 84 Sheridan. Big and Little Goose Creeks Jun 84 *Shoshone River, Bank Protection, Lovell Jun 84 21-19 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 INSPECTION OF COMPLETED LOCAL PROTECTION PROJECTS TABLE 21-J (Continued) (See Section 22 of Text) Location Month Inspected North Dakota Mandan, Lower Heart River Jul85 Marmarth, Little Missouri River Jul 85 Scranton. Buffalo Jul 85 South Dakota Sioux Falls, Big Sioux River Sep 85 Belle Fourche, Belle Fourche River Aug 85 Rapid City, Cedar Canyon Dam Sep 85 Hot Springs. Fall River Channel Sep 85 Herreid, Spring Creek Sep 85 *Missouri River, Bank Protection, Greenwood Aug 84 *Bad River, Bank Protection, Fort Pierre Jun 85 *Big Sioux River, Schofield Bridge, Near Flandreau Jun 85 *Big Sioux River, Fink Bridge, Near Flandreau Jun 85 Rapid Creek. Rapid City Sep 85 Sacred Heart Hospital, Yankton Jun 85 Colorado Aurora, Westerly Creek-Kelley Road Dam Jul85 *Plum Creek, Bank Stabilization, Aurora Jul 84 *South Platte River, Bank Protection, Denver Aug 84 *Cache La Poudre River, Ft. Collins Jul84 Nebraska Omaha, Missouri River Sep 84 Waterloo, Elkhorn River Aug 85 West Point. Elkhorn River Jun 85 Pierce, Elkhorn River May 85 Clarkson. Middle Fork, Maple Creek Jun 85 Hooper. Elkhorn River Jul85 Norfolk, North Fork, Elkhorn River May 85 Madison, Union & Taylor Creeks Apr 85 *Platte River, M.U.D. Protection, Cedar Island Aug 85 *Platte River, Bank Protection, Louisville Aug 85 *Elkhorn River, Q Street Bridge, Near Gretna Aug 85 *Elkhorn River, Ray Bridge, Near Norfolk May 85 *North Platte River, Bank Stabilization, Minatare Jul 84 *Logan Creek, Bank Protection, Near Bancroft Apr 85 *Battle Creek, Bank Protection, Battle Creek May 85 Schuyler, Platte River Apr 85 Schuyler, Lost Creek & Platte River Apr 85 Little Papillion, Little Papillion Creek Sep 85 Gering Valley, Gering Drain & Tributaries Aug 84 Macy. Blackbird Creek Aug 85 Lincoln, Salt Creek & Tributaries Aug 85 Meadow Grove, Buffalo Creek May 85 Columbus, Loup River May 85 Broken Bow, Mud Creek Jul85 *Tangeman, Little Nemaha River Mar 85 *Julian, Rock Creek Mar 85 21.20 OMAHA, NE, DISTRICT INSPECTION OF COMPLETED LOCAL PROTECTION PROJECTS TABLE 21-J (Continued) (See Section 22 of Text) Location Month Inspected Iowa Council Bluffs, Missouri River Sep 84 Ida Grove, Maple River-Odebolt Creek Apr 85 Sioux City, Floyd River Jun 85 Hawarden, Dry Creek Jun 85 Hamburg L575, Nishnabotna River May 85 Intercounty D.D., Little Sioux River Aug 85 Nagel D.D., Little Sioux River Aug 85 Bennett-McDonald-Smithland D.D., Little Sioux River Aug 85 *West Nishnabotna River, Mills Co. Bridge. Near Malvern Apr 85 *West Nishnabotna River, Mills Co. Bridge, Near Hastings Apr 85 *East Nishnabotna River, Page Co. Bridge, Near Essex May 85 *Missouri River, Marina, Sioux City Jun 85 *West Nishnabotna River, Near Hancock Apr 85 *East Nishnabotna River, Near Griswold Apr 85 Missouri River Levees L624 & L627, Mosquito Creek & Sieck Levees May 85 L601, Watkins Levee District May 85 L601, Miller-Sturgeon Levee District May 85 L601, Missouri River Levee District # 1 May 85 L594, Waubansie Drainage District Sep 85 L594, Pleasant Valley Levee District Sep 85 L575, Benton-Washington Levee District Aug 85 L575, Northwest Atchison Levee District May 85 L575, McKissock Island Levee District May 85 L575, Buchannan Levee District May 85 L561, L550, L536, Atchison County Levee District Jun 85 R613, Sarpy Co. Soil & Water Cons. D. Sep 85 R562, Peru Levee District May 85 R548, Brownville-Nemaha Levee District Jun 85 R548, Little Nemaha Levee District Jun 85 R520, Richardson Co. Levee Dist. #8 Jun 85 R573, Otoe County Drainage Dist. #2 May 85 *Denotes Section 14 Projects ACTIVE GENERAL INVESTIGATIONS TABLE 21-K (See Section 32 of Text) Federal Cost Totals By Item FY 85 Categories SURVEYS (Category 100) Flood Damage Prevention Studies (120) Eastern SD and Upper Big Sioux River. SD, IA 339,212 Missouri River, SD, NE, ND, MT 925,752 Western Dakotas Region of SD 159,055 Subtotal 1,424,019 21-21 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 21-K (Continued) ACTIVE GENERAL INVESTIGATIONS (See Section 32 of Text) Federal Cost Totals By Item FY 85 Categories Review of Authorized Projects (160) Salt Creek and Tributaries, NE Miscellaneous Activities (170) Special Investigations FERC Licensing Subtotal Coordination Studies with Other Agencies (180) Soil Conservation Service, Dept. Agric. (181) Bureau of Reclamation, Dept. Interior (182) Missouri River Basin Commission (183) Planning Assistance to States (186) Technical Assistance for Streambank Erosion (188) Subtotal TOTAL (Category 100) COLLECTION AND STUDY OF BASIC DATA (Category 200) Flood Plain Management Services (250) Hydrologic Studies (260) TOTAL (Category 200) 3,170 56,703 10,992 67,695 12,228 11,206 4,559 54.236 176,193 258,422 205,526 20,230 1,753,306 225,756 RESEARCH AND DEVELOPMENT (Category 300) None CONTINUATION OF PLANNING AND ENGINEERING (Category 400) Perry Creek. IA (450) 120,920 Gregory County Hydroelectric Pumped Storage Facility (460) 97,650 TOTAL (Category 400) PLANNING AND ENGINEERING UNDER PROPOSED LEGISLATION (Category 500) None ADVANCE ENGINEERING AND DESIGN (Category 600) None GRAND TOTAL GENERAL INVESTIGATIONS 218,570 2,197,632 FLOOD CONTROL ACTIVITIES UNDER SPECIAL AUTHORIZATION TABLE 21-L (See Section 24 of Text) Fiscal Year Project Name Stage Cost Section 107: 2 Negative Appraisals $14,900 Total (Section 107) $14,900 Section 205: Indian Creek. Emerson, IA - Jobs Act C $ 50,506 Lower Heart River, Mandan, ND D 151,687 Lost Creek, Columbus, NE C 610,869 Pebble Creek, Scribner, NE P 24,945 Platte River, Cedar Creek, NE R 15,960 East Nishiabotna River, Red Oak, IA C 13,792 Lodgepole Creek. Sidney, NE D 12,095 5 Negative Appraisals 36,300 Total (Section 205) 8916,154 21.22 OMAHA, NE, DISTRICT FLOOD CONTROL ACTIVITIES UNDER SPECIAL AUTHORIZATION TABLE 21-L (See Section 24 of Text) Fiscal Year Project Name Stage Cost Section 14: County Rd. Bridge, Elm Creek, Decatur, NE C 630 Elm Creek, Sec. 15, Burt County, NE C 1,544 Elm Creek, Sec. 16, Burt County, NE C 1.470 Muddy Creek, Syracuse, NE - Jobs Act C 122,418 Shoshone River, Byron, WY - Jobs Act C 2,537 Muddy Creek, Syracuse, NE C 73 Shoshone River, Byron, WY C 1,012 Middle Pebble Creek, Snyder, NE C 47,924 Big Sioux River, Plymouth County, IA - Site 2 P 13,629 Big Thompson River, Johnstown, CO C 14,873 Cache La Poudre River, Windsor, CO C 44,348 Elk Creek, Jackson, NE P 15.196 Elm Creek, Decatur, NE C 151,289 Platte River, Brady, NE C 170,445 Platte River, Hansen Lake, NE P 14,814 Redbird Creek, Holt County, NE P 14,966 Salt Creek, Lincoln, NE C 53,071 So. Platte River, Kersey, CO C 20,452 So. Platte River, Platteville, CO C 39,428 So. Platte River, Weldona, CO P 14,033 So. Platte River, Iliff, CO C 117,537 So. Platte River, Merino, CO C 15,639 So. Platte River. Balzac. CO P 10,799 So. Platte River, Goodrich, CO P 14.399 So. Platte River, Morgan County, CO P 14,510 Vermillion River, Waste Water Treatment Plant P 13,593 Vermillion River, Vermillion, SD - Sewer Line C 21,664 West Papillion Creek, Douglas County, NE C 18,216 Wigle Creek, Homer, NE P 12,181 Yellowstone River. Glendive, MT C 163,971 15 Negative Appraisals 69,100 Total (Section 14) $1,215,761 Total Continuing Authorities $2,146,815 R= Recon D=Detailed Project Study P Plans & Specs C Construction 21.23 OHIO RIVER For actual construction of locks and dams, and operation and care of completed stuctures, river is divided into three sections under immediate supervision and direction of District Engineers at Pittsburgh, Huntington and Louisville. Pittsburgh section extends 127 miles from head of river at Pittsburgh, Pa., to a point immediately upstream from New Martinsville, W. Va., and includes Emsworth, Dashields, Montgomery, New Cumberland, Pike Island and Hannibal locks and dam. Huntington section extends 311 miles from mile 127 to 438 immediately upstream from Foster, Ky., and includes Willow Island, Belleville, Racine, Gallipolis, Greenup and Captain Anthony Meldahl locks and dams. Louisville section extends 543 miles from mile 438 to mouth of river, and includes Markland and McAlpine locks and dams (with Louisville and Portland Canal) Cannelton, Newburgh, Uniontown, and Smithland locks and dams and Locks and Dams 52 and 53. IMPROVEMENTS Navigation 1. Construction of locks and dams on Ohio River ................................. 22-1 2. Open channel work, Ohio River............ 22-4 Tables Table 22-A Cost and Financial Statement......22-5 Table 22-B Authorizing Legislation............ 22-6 Table 22-C Not Applicable Table 22-D Not Applicable Table 22-E Not Applicable Navigation 1. CONSTRUCTION OF LOCKS AND DAMS ON OHIO RIVER Location. Ohio River is formed by junction of Allegheny and Monongahela rivers at Pittsburgh, Pa., and flows generally southwesterly for 981 miles to join Mississippi River near Cairo, Ill. For description of river see page 1227, 1932 Annual Report. Previous projects. For details see page 1907 of Annual Report for 1915. Existing project. Provides for improvement of entire river by construction of locks and dams to provide a channel depth of 9 feet and for widening Louisville and Portland Canal at Louisville, Ky. Project provides for a lock with usable dimensions of 110 by 600 feet at each of the dams and, in addition, an auxiliary lock 56 by 360 feet is available at Emsworth, Dashields, Montgomery, and McAlpine locks and dams with an auxiliary lock at Gallipolis being 110 by 360 feet. Dashields is a fixed dam, while Emsworth, Montgomery, and Gallipolis are fixed dams with movable crests. Remaining dams are movable Table 22-F Table 22-G Table 22-H Table 22-I Table 22-J Not Applicable Not Applicable Construction of Locks and Dams on Ohio River, 'Total Cost of Existing Project.........................22-6 Federal Energy Regulatory Commission Licenses of Locks and Dams, Ohio River ............ 22-6 Ohio River Locks and Dams Statistics ........... ............ . 22-7 type, with navigable pass varying in width from 600 to 1,248 feet. In addition to navigable pass, movable-type dams are also provided with one or more regulating weirs. At McAlpine Locks and Dam, a canal (Louisville and Portland) extends along left bank for 2 miles, with locks at lower end. Modifications to existing project under purview of Section 6, March 3, 1909 Act, provide for fixed dams with movable crests with two locks (110 by 1200 feet and 110 by 600 feet) at New Cumberland, Pike Island, Hannibal, Willow Island, Belleville, Racine, Greenup, Captain Anthony Meldahl, Markland, Cannelton, Newburgh, and Uniontown; two locks 110 by 1200 feet at Smithland; 110 by 1,200 foot temporary locks in addition to the existing locks at Locks and Dams 52 and 53, and reconstruction to provide a 110 by 1200-foot lock in addition to existing locks and a fixed dam with two sections of movable crest at McAlpine Locks and Dam; widening Louisville and Portland Canal to 500 feet. Auxiliary lock 56 by 360 feet at McAlpine Locks and Dam has been inoperative since failure of downstream lock gates in December 1972. Rehabilitation of existing Locks and Dams 52 and 53 was started in September 1979 under the purview of Section 6, March 1909 Act. Mound City was also considered authorized under purview of 1909 Act, 22-1 REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1985 and preconstruction planning was performed in the period 1965 to 1972.'The ruling of the U.S. District Court, District of Columbia, on September 6, 1974, with reference to Lock and Dam 26, Mississippi River, would also apply to this project. Consequently, it is no longer considered authorized. Operation and care of locks and dams were included in project July 1, 1935, under provisions of Permanent Appropriations Repeal Act of June 26, 1934. Estimated Federal cost of new work (existing project, 1983), exclusive of Gallipolis Locks and Dam reported under Kanawha River project is $1,778,840,999, estimated non-Federal cost is $14,999,000. Foregoing estimate does not include expenditures on previous projects. Various items previously included in this project are considered inactive or unnecessary and are excluded from foregoing cost estimate. See page 693, Annual Report, 1968 for items and estimated cost. Under authority of 1910 River and Harbor Act, Louisville and Portland Canal was widened to 200 feet; Locks and Dams 40 and 42 eliminated; Locks and Dams 1 and 2 replaced by Emsworth Locks and Dam; Lock and Dam 3 replaced by Dashields Locks and Dam; and Locks and Dams 4, 5, and 6 replaced by Montgomery Locks and Dam. Locks and Dams 24, 25, and 26 were replaced by Gallipolis Locks and Dam authorized by August 30, 1935 Act, and constructed under project for improving lower Kanawha River. Locks and Dams 7, 8, and 9 were replaced by New Cumberland Locks and Dam; Locks and Dams 10 and 11 were replaced by Pike Island Locks and Dam; Locks and Dams 12, 13, and 14 were replaced by Hannibal Locks and Dam; Locks and Dams 15, 16, and 17 were replaced by Willow Island Locks and Dam; Locks and Dams 18, 19, and 20 were replaced by Belleville Locks and Dam; Locks and Dams 21, 22, and 23 were replaced by Racine Locks and Dam; Locks and Dams 27, 28, 29, and 30 were replaced by Greenup Locks and Dam; Locks and Dams 31, 32, 33, and 34 were replaced by Captain Anthony Meldahl Locks and Dam; Locks and Dams 35, 36, 37, 38, and 39 were replaced by Markland Locks and Dam; the Louisville and Portland Canal at McAlpine Locks and Dam was widened to 500 feet. Locks and Dams 43, 44, and 45 were replaced by Cannelton Locks and Dam; Locks and Dams 46 and 47 were replaced by Newburgh Locks and Dam; Locks and Dams 48 and 49 were replaced by Uniontown Locks and Dam, presently under construction; and Locks and Dams 50 and 51 were replaced by Smithland Locks and Dam, presently under construction, as modifications to existing project under purview of Section 6, March 3, 1909 Act, reducing total number of structures to 20. The Water Resources Development Act of 1974 combined the Newburgh Bank Protection Works project with the Newburgh Locks and Dam project. A December 1981 Act established the Falls of the Ohio National Wildlife Conservation Area near McAlpine Locks and Dam to protect and preserve existing fossilized coral and a diversity of wildlife. Table 22-J contains data relative to various features of locks and dams included in existing projects. For list of principal towns and cities along Ohio River with their mileage below Pittsburgh, PA, see page 1060, 1962 Annual Report. See Table 21-I for licenses. Navigation system of 21 locks and dams is in operation and 9-foot navigation throughout length of river is generally available at all times. At certain unstable bars project depth is maintained by dredging, supplemented by contraction works. (See "Open Channel Work, Ohio River.") Table 22-J shows cost and year completion of locks and dams now in operation. Existing project does not provide adequate facilities for present day navigation due to obsolescence ,of structures. Since repair and modernization of these facilities would be extremely costly, replacement and reconstruction is being accomplished as rapidly as funds are made available for the purpose. Construction of lock and dam replacement program was initiated in fiscal year 1955. New Cumberland, Pike Island, Hannibal, Willow Island, Belleville, Racine, Greenup, Captain Anthony Meldahl, Markland, McAlpine, Cannelton, Newburgh, Uniontown, and Smithland replacement locks and dams are in operation, replacing 39 old low-lift locks and dams. For total cost of existing project, see Table 22-H. Terminal facilities. Modern public terminals, with warehouses, equipped with operating machinery for transferring materials, have been constructed by private interests at some of the larger cities and towns. A list of terminals on Ohio River is revised annually and can be obtained from Division Engineer, U.S. Army Engineer Division, Ohio River, Cincinnati, Ohio. Operations during fiscal year. New work by contract and hired labor: Emsworth Locks and Dam (Rehabilitation): Upper lock miter gates, 110-foot chamber, were installed by hired labor in October 1981. Contract for Locks and Dams Rehabilitation, awarded October 15, 1981, was completed on November 9, 1984. Dam work included: placing stone erosion protection downstream of both back channel and main channel, structurally rehabilitating all 14 dam gates, painting of the service bridge on main channel dam and painting dam gates on the back channel. Lock work included: rehabilitation of the river chamber and land chamber including all lock machinery. Contract for modernizing electrical system of main and back channel dams, awarded August 6, 1984 for $1,543,000 (progressed to 45% completion). Contract for shotcrete repairs consisting of placing shotcrete coating, repairing damaged areas with reinforced shotcrete and repairing monolith joints on the lock walls with reinforced shotcrete, awarded on February 28, 1985, for $377,830 was completed on August 9, 1985. Contract for miscellaneous painting and sealing concrete surfaces, awarded April 17, 1985 for $289,270 is 15% complete. Expenditures during FY 1985 for real estate acquisition and coordination, construction, and engineering and design of remaining project was $2,165,562. Montgomery Locks and Dam (rehabilitation): Contracts awarded include: Fabrication of lock miter gates, 110-foot chamber, August 12, 1983, for $1,354,116; upper guard wall cells, awarded on July 2, 1984, for $766,010; and was completed on September 25, 1985; emergency dam bulkheads, August 13, 1984, for $321,274; fabrication of 56-foot lock miter gates, September 14, 1984, for $345,644; and installation of 56-foot lock miter gates and major rehabilitation of locks and dam, July 29, 1985, for 22-2 OHIO RIVER $22,193,960. Installation of 110-foot lock miter gates completed by hired labor. Overall scheduled completion date is March 1989. Expenditures during FY 1985 for real estate coordination, construction, engineering and design of remaining project was $3,461,316. Willow Island Locks and Dam: Construction was initiated in January 1967. All work is complete. Belleville Locks and Dam: Construction was in May 1962. All work is complete. Racine Locks and Dam: Construction initiated in June 1964 is complete. Gallipolis Lock and Dam: The existing project, constructed under project for improving lower Kanawha River, was placed in operation in August 1937. The dimensions of the existing locks chambers and poor approach conditions, particularly to downstream traffic, have created a higher than normal accident rate to the structure with corresponding hazards and delays to traffic. The Water Resources Development Act of 1976 authorized Phase I studies for a single 1200-foot lock in a bypass canal. These studies are complete. Initial construction, General funds for the continuation of Engineering activities were received in September 1985. Greenup Locks and Dam: Construction was initiated in October 1954. All work is complete. During the period $71,779 was expended under the recreation at completed projects program. Captain Anthony Meldahl Locks and Dam: Construction work complete. Markland Locks and Dam: Project is complete including a public highway bridge across the navigation structure, as authorized by the Federal-Aid Highway Act of 1970 (Public Law 91-606). For details of bridge see page 22-3 of Annual Report for 1978. Falls of the Ohio National Wildlife Connservation Area was authorized by Public Law 97-137 on December 29, 1981. The Conservation Area will protect 1,000 acres which consists of birdlife and other wildlife. Planning, initiated in September 1983, was continued. Master Plan and Real Estate Design Memorandum is completed. Acquisition of one tract of land of approximately 600 acres encompassing most of the exposed fossil beds was accomplished. $150,478. McAlpine Locks and Dam: Project is complete except for alteration of lift section of railroad bridge that spans the upper end of the Louisville and Portland Canal which work is presently deferred. Cannelton Locks and Dam: Project is complete, except for payment of settlement for an inverse condemnation: $6,540. Newburgh Locks and Dam: Project is complete except added work to the centralized remote control and surveillance system and extended warranty therefor: $106,116. Uniontown Locks and Dam: Project remained at 99 percent complete. Land acquisition is complete except for continuing action on Declarations of Taking on several tracts. A contract for repairs to Parking Area and Bank at Atkinson Park was awarded and completed. $114,118. Smithland Locks and Dam: All major construction features are complete and the project was advanced to 98 percent completion. Land acquisition is complete except for outstanding condemnation actions and acquisition of one recreation site. Final payment on the completed dam contract has not been made pending settlement of contractor's claim. Two relocation contracts for electric and telephone lines are being delayed for rights-of-way problems. Alteration to Rosiclare, IL drainage and water structures was advanced to 97 percent complete. A contract for additional work on the Tainter Gates was awarded in June 1985 and advanced to 52 percent complete. Contracts for boat ramps, roads and parking areas at Lock and Dam 50, KY and Dyer Creek, KY recreation sites were advanced to 99 percent and 90 percent, respectfully. A contract for boat ramp, road, and parking area at Blackburn, KY, Site 8 was awarded in April 1985 and advanced to 86 percent complete. Engineering and design of remaining project features was continued: $2,008,761. Locks and Dam No. 52 (New Lock): Construction initiated in December 1967 is complete. Locks and Dam No. 53 (Temporary Lock): Construction initiated in December 1972 is complete. Locks and Dam No. 52 (Rehabilitation): Project is 94 percent complete. Final payment has been made on completed contract for fabrication of miter gates. Contract for storage building was completed. Contract to restore dam pier No. 1 and lock structures was advanced to 99 percent completion. Hired labor installation of dam wicket assemblies and lock miter gates advanced to 86 percent and 100 percent completion respectively. A contract to repair the beartrap piers and dam sill was awarded in July 1985 and advanced to 38 percent complete. A contract to purchase piston rods to replace existing deteriorated piston rods was awarded in March 1985. A contract to repair miter gates and piston was awarded in August 1985. Engineering and design of remaining project features was continued: $381,413. Locks and Dam No. 53 (Rehabilitation): Project is 42 percent complete. Contract to restore machinery and equipment for 600-foot lock was completed. Hired labor installation of dam wicket assemblies and lock miter gates advanced to 35 percent and 100 percent completion, respectively. Contract to inspect the beartraps for the dam was completed. A contract to reinforce and grout beartrap piers and install piston rods was awarded in August 1985 and advanced to 24 percent complete: $476,629. Operation and maintenance, general. Locks and dams operated as required and necessary repairs and improvements made thereto and to operator's quarters, grounds and esplanades. Feature Design Memorandum for Major Rehabilitation of Dashields Locks and Dam was completed on September 17, 1985. Costs were $9,834,629 for Pittsburgh District, $9,310,392 for Huntington District and $14,597,830 for Louisville District. 22-3 REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1985 2. OPEN CHANNEL WORK, OHIO RIVER Location. Under jurisdiction of district engineer in whose district the work is located. Portion of river included in project extends 974.7 miles from head of river at Pittsburgh, PA, to mouth of Cache River (Mound City, IL). Open channel improvement from mouth of Cache River to mouth 'f Ohio River is under jurisdiction of Mississippi River Commission. Existing projects. Before completion of canalization project, no project depth had been fixed by Congress under project for open channel work, but in order to properly aid packet and barge navigation it was necessary to secure a low-water channel with a minimum depth of 4 to 6 feet, and a width, depending upon difficulty of running channel, of 400-600 feet; also to permit movemment of large coal tows, which movement occurred at stages of water exceeding 10 feet, it was necessary to remove points of projecting bars which formed at various locations along river. Accomplishment of this purpose involved concentration of current by closing back channels at islands with low dams, contraction and straightening wide open channels by low dikes, dredging bars and shoals, and removal of snags and wrecks. Incidental to direct improvement of Ohio River is construction and maintenance of ice piers as required for protection of river craft. Stage of extreme high water on Ohio River varies from 46 feet at Pittsburgh, Pa., to 80 feet at Cincinnati, Ohio, with 57.2 feet at Louisville, Ky. (head of falls), 53.8 feet at Evansville, Ind., and 59.5 feet at Cairo, Ill. (mouth of river). Estimated cost of new work (1960) is $16,160,000, exclusive of following items which are considered inactive: Ice piers authorized by 1927 River and Harbor Act; reforestation of sloughs on Kentucky Peninsula near Evansville, Ind., authorized by 1930 River and Harbor Act; dredging to widen channel at certain points; and placing revetment at various points. Estimated cost of these items (1954) is $6,565,000. Operation of snag boats on Ohio River below Pennsylvania State line was included in project July 1, 1935, under provisions of Permanent Appropriations Repeal Act of June 26, 1934. See Table 22-B for authorizing legislation. New work under this project is substantially complete, since it is not anticipated that work on inactive portion of project will be accomplished. In addition to dredging, local stabilization of channel has been effected at various points by construction of dikes and revetment. Work which remains consists of dredging to widen channels at certain points to project depth. Local cooperation. River and Harbor Act of January 21, 1927 authorizing construction of ice piers for general open channel work, imposes condition that before work is begun on any pier, local interests convey to the United States free of cost such riparian rights as may be deemed necessary in connection with the improvements at locality (H. Doc. 187, 67th Congr., 2nd sess.). Existing ice piers are adequate for present purposes and local cooperation is not needed since no additional construction is under consideration. River and Harbor Act of July 3, 1930, provides for reforestation of sloughs of Kentucky Peninsula and bank protection and that no expense shall be incurred by the United States for acquiring lands required for purpose of this improvement (H. Doc. 409, 69th Cong. 1st sess.). However, since no serious overbank erosion has occurred since bank revetment in 1933-34, reforestation is not considered justifiable at this time and no local cooperation is required. Operations during fiscal year. Operation and maintenance, general: Dredging was done where required to provide an adequate and dependable channel of project depth at minimum pool conditions. Dikes and revetments were maintained and routine work of maintaining navigation aids, removing snags, making channel studies, hydrographic surveys and mapping was performed as required. Channel soundings, hydrographic surveys, stream gaging operations, channel inspections and aids to navigation, and miscellaneous inspections and reports cost $470,906. There was no dredging by hired labor on the Ohio River in FY 85. Dredging by contract: Pittsburgh District - Contract in the amount of $483,721 was awarded on February 1, 1985 for approximately 171,100 cubic yards of dredging Dashields Pool, Neville Island Back Channel, Pennsylvania (award of contract made by Louisville District for contract dredging work for Pittsburgh, Huntington and Louisville Districts). Huntington District 934,800 cubic yards at $2,518,000 and Louisville District 920,497 cubic yards at $1,625,598. 22-4 OHIO RIVER TABLE 22-A COST AND FINANCIAL STATEMENT See Section Total Cost to in Text Project Funding FY 82 FY 83 FY 84 FY 85 Sep 30, 1985 1. Construction of New Work Locks and Dams Approp. $7,457,298 $2,350,759 $1,801,200 $1,814,000 $1,383,654,7721 3 5 10 17 on Ohio River Cost 6,156,450 4,099,831 2,573,878 2,518,511 1,382,711,9591 3 6 11 12 5 16 18 Maint. Approp. 28,416,500 31,744,300 30,976,373 31,056,817 557,348,960 24 19 Cost 27,648,805 30,311,071 30,961,371 33,742,851 556,281,8252 3 13 14 19 20o Rehab. Approp. 15,400,000 15,897,572 10,189,000 4,605,000 57,364,572 Cost 15,059,290 17,335,848 7,502,809 6,484,920 54,067,396 2. Open Channel New Work Work, Ohio River Approp. - - - - 15,962,2608 Cost - - - - 15,962,2608 Maint. Approp. 5,378,100 4,440,300 5,265,000 5,029,763 104,108,4267 9 Cost 5,759,040 4,479,208 5,799,647 5,098,325 104,039,4397 9 Rehab. Approp. - - - - 944,649 Cost - - - - 944,649 1 Includes $17,003,761 for previous 6-foot canalization project. 2 Includes $36,943,217 expended from 1885 to 1937 on operation and care of work of improvement under provisions of permanent indefinite appropriations for such purposes. 3 Includes $215,812 public works acceleration, executive 1963. 4 Includes $38,766 public works acceleration, executive 1963. S Excludes $251,769 contributed funds for new work. 6 Excludes $250,102 contributed funds for new work. 7 Excludes $1,621,349 expended in operation of snag boats under provisions of permanent indefinite appropriation for such purposes, and $267 transferred to project without reimbursement. 8 Includes $1,040,236 Public Works funds. 9 Includes $1,000 for removal of obstructions in Licking River under authority of Section 3, R&H Act of 1930. 10 Includes $100,000 placed in FY 1971 Budget Reserve. " Excludes $3,899 transferred from project without reimbursement. "12 Surplus property valued at $3,553 transferred to project without reimbursement. 13 Excludes $2,140 transferred to project without reimbursement. 14 Excludes surplus property valued at $73,832 transferred to project without reimbursement. 15 Includes $87,724,158 prior construction cost. 16 Excludes surplus property valued at $297,385 transferred to project without reimbursement. 17 Includes $549,392 Code 710 Funds, $572,162 Code 711 Funds, $532,677 Code 712 Funds and $1,759,812 Code 713 Funds. I Includes $549,392 Code 710 Funds, $342,162 Code 711 Funds, $532,677 Code 712 Funds and $1,989,812 Code 713 Funds. 19 Includes $2,158,073 Funds provided from The Productive Employment Appropriations Act of 1983 (PL 98-8). 20 Includes $920,945 cost for operations and care of previous projects. 22-5 REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1985 TABLE 22-B AUTHORIZING LEGISLATION See Date of Section Authorizing In Text Act Project and Work Authorized Documents 2. Open Channel Work, Ohio River March 3, 1827 Project adopted by this act originally covered entire length of Ohio River from its mouth near Cairo to Pittsburgh, a distance of 981 miles. It provided for removal of all obstructions which tend to endanger steamboat navigation. January 21, 1927 Construct ice piers as a part of project, with funds H. Doc. 187, 67th Cong., 2nd sess. allotted from appropriations for general open channel work. July 3, 1930 Reforestation of sloughs on Kentucky Peninsula near H. Doc., 409, 69th Cong., 1st sess. Evansville, Ind., and a 200-foot strip along bank and for bank protection, at an estimated cost of $200,000. July 3, 1958 Act of March 3, 1827 modified to include maintenance H. Doc., 434, 84th Cong., 2nd sess. of existing Licking River Channel within lower 3-mile limit of River slack water, at an estimated increase of $1,000 in cost of average annual maintenance. Locks and Dams, Ohio River December 29, 1981 Act of December 29, 1981 established the 1,000 H.R. 2241, PL 97-137, Title II, acre Falls of the Ohio National Wildlife Conser- 95 Stat. 1710 vation Area, at a cost not to exceed $300,000. CONSTRUCTION OF LOCKS AND DAMS ON OHIO RIVER TOTAL COST OF EXISTING PROJECT TO SEPTEMBER 30, 1985 TABLE 22-H (See Section 1 of Text) Operations and Maintenance Funds New Work General Rehabilitation Total Regular 1,290,314,784 515,320,108 54,067,396 1,859,702,288 Public Works 3,258,368 - - 3,258,368 Emergency Relief 1,198,837 19,000- 1,217,837 Maintenance & Operation 3,039,789- 3,039,789 Public Works Acceleration 215,812 38,766 - 254,578 Executive 1963 Total 1,294,987,8013 518,417,663' 2 54,067,396 1,867,472,860 ' Excludes $36,943,217 expended from 1885 to 1937 under Note: All other cost variations are listed in the Footnotes permanent indefinite appropriation, of Table 22-A. 2 Excludes $920,945 cost for operation and care of previous projects. 3 Excludes $87,724,158 prior construction cost. FEDERAL ENERGY REGULATORY TABLE 22-I AT LOCKS AND DAMS, COMMISSION OHIO RIVER LICENSES Markland Dam McAlpine Dam Racine Dam Greenup Dam F.E.R.C. License 2,211 289:1,000 2,570 2,614 License Public Service Co. Louisville Gas and Ohio Power Co. City of Vanceburg, of Indiana Electric Co. Kentucky Annual Charge $45,950.00 $95,000.00 $50,000.00 $227,900.00 Collections to end of Fiscal Year 1985 $779,261.64 $7,305,893.16 $235,673.00 $720,983.00 22-6 TABLE 22-J OHIO RIVER LOCKS AND DAMS (See Section 1 of Text) Lock Dimensions Upper Normal Greatest Pool Length Elevation Depth on Width Available (feet, Miter Sills Actual Cost Lock Miles of For Full mean Year to Date of and Below Distance From Chamber Width Lift sea Upper Lower Character of Foundation Percent Opened to Each Lock Dam Pittsburgh Nearest Town (feet) (feet) (feet) level) (feet) (feet) Lock Dam Complete Navigation and Dam 1 - Replaced 6.2 Emsworth Locks and Dam, Emsworth, PA 2 - Replaced 3 - Replaced 13.3 Dashields Locks and Dam 1.6 miles below Sewickley, PA 4 - Replaced 5 - Replaced 6 - Replaced 31.7 Montgomery Locks and Dam, 1.4 miles above Industry, PA 7 - Replaced 8 - Replaced 54.4 New Cumberland Locks and Dam, Stratton, OH 9 - Replaced 10 - Replaced 11 - Replaced 84.3 Pike Island Locks and Dam, 2 miles upstream from Warwood, WV 12 - Replaced 13 - Replaced 14 - Replaced 126.4 Hannibal Locks and Dam, 1.6 miles upstream from New Martinsville, WV 15 - Replaced 16 - Replaced 161.7 Willow Island Locks and Dam, 2.7 miles above Waverly, WV 110 56 110 56 110 56 110 110 110 110 600 18.0 710.0 17.0' 12.9' Rock Rock and piles 100 360 15.5' 12.9' 600 360 10.0 692.0 13.4' 17.5' Rock Rock - $ 870,034 1921 42,048,260" - 976,767 - 1,144,588 100 1929 600 360 17.5 682.0 16.0' 14.6' Rock and piles Rock and piles 100 1,200 600 20.5 664.5 7.0' 14.8' Rock Rock 100 1,200 600 21.0 644.0 17.0' 18.0' Rock Rock 100 110 1,200 110 600 21.0 623.0 38.0 17.0 110 110 Rock 1,200 600 20.0 602.0 35.0 15.0 Rock and piles Rock Rock 3,533,076 - 1,071,472 - 1,080,132 - 1,123,442 1936 11,272,381"* - 1,075,000 - 1,167,456 1959 39,099,688 - 1,177,100 - 1,138,000 - 1,162,165 1968 56,623,946 1,166,104 1,222,389 1,133,371 99 1972 87,648,953 - - 1,180,478 - - 1,275,532 100 1972 76,520,876 0 0 Oa c TABLE 22-J (Continued) OHIO RIVER LOCKS AND DAMS (See Section 1 of Text) Lock Dimensions Upper Normal Greatest Pool Length Elevation Depth on Width Available (feet, Miter Sills Actual Cost Lock Miles of For Full mean Year to Date of and Below Distance From Chamber Width Lift sea Upper Lower Character of Foundation Percent Opened to Each Lock Dam Pittsburgh Nearest Town (feet) (feet) (feet) level) (feet) (feet) Lock Dam Complete Navigation and Dam - Replaced - Replaced - Replaced - Replaced 103.9 Belleville Locks and Dam, 0.3 mile below Reedsville, OH - Replaced - Replaced - Replaced 237.5 Racine Locks and Dam, 1.5 miles below Letart Falls, OH - Replaced - Replaced - Replaced 279.2 Gallipolis Locks and Dam, 0.7 mile below Hogsett, WV Gallipolis Modernization -- Replaced - Replaced - Replaced - Replaced 341.0 Greenup Locks and Dam, 4.9 miles below Greenup, KY - Replaced - Replaced - Replaced - Replaced 436.2 Captain Anthony Meldahl Locks and Dam, 2.2 miles above Foster, KY 110 110 110 110 110 110 110 110 110 110 1,200 600 22.0 582.0 37.0 15.0' Rock and piles 1,200 600 22.0 560.0 18.0 15.0 Rock and piles 600 360 26.0 538.0 18.0 12.0 Rock 1,200 600 30.0 515.0 18.0' 13.0 Rock 1,200 600 30.0 485.0 18.0' 15.0 Rock Rock Rock Rock Rock Rock - - $ 1,362,591 - - 927,091 - - 1,213,848 - - 936,696 100 1968 62,591,255 - - 1,484,562 - - 1,218,798 - - 1,851,488 98 1971 64,922,680 1,187,542 1,925,205 1,307,241 100 1937 1,436,465 - - 2,015,601 - - 1,063,133 - - 1,088,802 - - 1,579,618 100 1959 57,464,191 100 1962 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 1,359,231 2,951,216 1,937,166 3,437,057 74,188,216 OT< 0 P4 0 zl TABLE 22-J (Continued) OHIO RIVER LOCKS AND DAMS (See Section 1 of Text) Lock Dimensions Upper Normal Greatest Pool Length Elevation Depth on Width Available (feet, Miter Sills Actual Cost Lock Miles of For Full mean Year to Date of and Below Distance From Chamber Width Lift sea Upper Lower Character of Foundation Percent Opened to Each Lock Dam Pittsburgh Nearest Town (feet) (feet) (feet) level) (feet) (feet) Lock Dam Complete Navigation and Dam 35 - Replaced 36 - Replaced 37 - Replaced 38 - Replaced 531.5 Markland Locks and Dam, 1 mile above Markland, IN 39 - Replaced 40 - Eliminated 41 - - Falls of the Ohio, 1 mile above McAlpine 604.0 McAlpine Locks and Dam (Reconstruction of Locks and Dam 41) 42 - Eliminated 43 - Replaced 44 - Replaced 45 - Replaced 720.7 Cannelton Locks and Dam 3 miles above Cannelton, IN 46 - Replaced 776.1 Newburgh Locks and Dam, 16 miles above Evansville, IN 47 - Replaced 48 - Replaced 49 - Replaced 846.0 Uniontown Locks and Dam, 3.5 miles below Uniontown, KY 50 - Replaced 51 - Replaced 918.5 Smithland Locks and Dam, 2 miles above Smithland, KY 110 110 N/A 110 110 56 110 110 110 110 110 110 110 110 1,200 600 35.0 455.0 50.0 15.0 N/A N/A N/A N/A N/A 1,200 49.0 12.0 600 37.0 420.0 19.0 11.0 360 19.0 11.0 1,200 25.0 383.0 38.0 13.0 600 1,200 600 16.0 358.0 32.0 16.0 1,200 600 22.0 342.0 34.0 12.0 1,200 1,200 22.0 324.0 34.0 12.0 Rock N/A Rock Rock Rock Rock Rock Piles N/A Rock Rock 100 0 1963 N/A $ 1,894,942 3,704,535 1,297,924 2,857,040 63,019,403 2,222,448 - 7,658,134' 260,164 100' 1961 45,726,189' 99 1972 2,592,242 2,819,930 3,202,890 96,747,28810 -- 3,129,028 Pile 99 1975 104,448,521 Rock - - 4,415,526 - - 3,062,710 - - 3,325,964 99 1975 100,268,139 - - 3,751,762 - - 4,370,566 Rock 95 1980 270,102,445 0 TABLE 22-J (Continued) OHIO RIVER LOCKS AND DAMS (See Section 1 of Text) Lock Dimensions Upper Normal Greatest Pool Length Elevation Depth on Width Available (feet, Miter Sills Actual Cost Lock Miles of For Full' mean Year to Date of and Below Distance From Chamber Width Lift sea Upper Lower Character of Foundation Percent Opened to Each Lock Dam Pittsburgh Nearest Town (feet) (feet) (feet) level) (feet) (feet) Lock Dam Complete Navigation and Dam 52 938.9 1.4 miles below Brookport, IL 110 600 12.0 302.0 15.4 11.0 Pile Pile 100 1928 12,892,7611 938.9 1.4 miles below Brookport, Il 110 1,200 12.0 302.0 15.4 11.0 Pile Pile 100 1969 10,197,516 (New lock) 53 962.6 10.8 miles above 110 600 13.4 290.0 15.4 9.6' Pile Pile 100 1929 9,325,7852 Mound City, IL 962.6 10.8 miles above 110 1,200 13.4 290.0 15.4 9.6 Pile - 100 1982 38,570,920 Mound City, IL (New lock) 974.2 Mound City Lock and Dam - - - - - - - - -1,539,470" 1 mile below Mound City, IL TOTAL $1,427,565,145" 0 ' Depths are on emergency dam foundation and are controlling depths. 2 Change from fixed dam to lift-gate dam completed in 1938. SDepths are on poiree dam foundation and are controlling depths. 4 Land chamber. S River chamber. SRoller-gate dam. Cost not included in total. Constructed under project for improving lower Kanawha River. 7 Lock and Dam 41 completed with 110- by 600-foot lock in 1921. Completed with new dam and raised canal and lock wall in 1928. Auxiliary 56- by 360-foot lock constructed in 1929-30. Reconstruction and modernization began 1956, renamed McAlpine Locks and Dam in 1960. Operation of auxiliary lock suspended in 1971. " Completed except for deferred alteration of railroad bridge. * Dam below not yet constructed. Depth on lower miter sill at lower water. 1o Reflects reduction of $2,219,975 payment for settlement of damage to dam caused by barge accident in April 1978. " Includes $8,431,014 for major rehabilitation project initiated in FY 1979. 12 Includes $3,915,117 for major rehabilitation project initiated in FY 1979. 1 For preconstruction planning 1965 to 1972. No longer considered authorized. See Section 1 of text. 1' Includes $36,186,495 for major rehabilitation initiated in FY 1980. 14* Includes $5,534,770 for major rehabilitation initiated in FY 1983. 1 Exclusive of $6,994,235 details below. Additional Features Entering into Cost of Project Louisville and Portland Canal and Indiana chute $ 5,359,203 (under previous project) Examinations, survey contingencies, plants and miscellaneous 966,232 Recreation facilities, pool area, Gallipolis Locks and Dam 668,800 TOTAL 6,994,235 GRAND TOTAL 'Ti O y Oq yq x 0 z toil $1,434,559,380 NASHVILLE, TN, DISTRICT* This district comprises portions of southern Ken- western portion, and embraces drainage basins of tucky, southwestern Virginia, western North Caro- Tennessee and Cumberland Rivers and their tribulina, northern Georgia and Alabama, northeastern taries. Mississippi and practically all of Tennessee except IMPROVEMENTS Navigation Page General Investigations Page 1. Cumberland River, TN and KY ........ 23-2 2. Tennessee River, TN, AL and KY ...... 23-3 3. Tennessee-Tombighee Waterway, AL and MS ........................... 23-4 4. Navigation Work Under Special Authorization ....................... 23-4 Alteration of Bridges 5. Authorized Alteration of Bridges ...... 23-4 Flood Control 6. Big South Fork National River and Recreation Area, KY and TN .......... 23-4 7. Martins Fork Lake, KY ............. .23-5 8. Middlesboro, Cumberland River Basin, KY ......................... 23-5 9. Tug and Levisa Forks of the Big Sandy River and Cumberland River, W VA, VA and KY.......................23-6 10. Ohio River Basin (Nashville Dist.) .... 23-6 11. Inspection of completed flood control projects .................... 23-6 12. Flood control work under special authorization ...................... 23-6 Multiple-Purpose Projects, Including Power 13. Center Hill Lake, Ohio River Basin, TN ........................ . 23-6 14. Dale Hollow Lake, Ohio River Basin, TN and KY ......................... 23-7 15. J. Percy Priest Dam and Reservoir, Ohio River Basin, TN ................ 23-7 16. Laurel River Lake, Ohio River Basin, KY ......................... 23-7 17. Wolf Creek Dam-Lake Cumberland, Ohio River Basin, KY ................ 23-8 18. Surveys ............................ 23-8 19. Collection and study of basic data ....... 23-8 Tables Table 23-A Table 23-B Table 23-C Table Table 23-D 23-E Table 23-F Table Table 23-G 23-H Table 23-I Table 23-J Table 23-K Table Table 23-L 23-M Table 23-N Cost & Financial Statement ..... 23-9 Authorizing Legislation ........ 23-11 Other Authorized Navigation Projects ...................... 23-13 Not Applicable Other Authorized Flood Control Projects ...................... 23-13 Other Authorized Multiple- Purpose Projects, Including Power ...................... . 23-14 Deauthorized Projects .......... 23-14 Cumberland River, TN & KY, Principle Features ............. 23-15 Tennessee River Lock Dimensions ................... 23-17 Tennessee River Total Cost of Existing Project ............... 23-18 Ohio River Basin (Nashville District) Local Protection ...... 23-18 Reservoirs .................... 23-18 Inspection of Completed Flood Control Projects ............... 23-19 Flood Control Work Under Special Authorization .......... 23-19 23-1 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Navigation 1. CUMBERLAND RIVER, TN AND KY Location. Formed by junction of Poor and Clover Forks in Harlan- County, Ky., about 694.2 miles above its mouth, and flows west to Burnside, Ky., from whence it makes a locp southwestward into Tennessee, passes Nashville, and returns northwestward to Kentucky, emptying into Ohio River near Smithland, Ky. (See Geological Survey base maps of Tennessee and Kentucky.) Previous projects. For details see pages 1898 and 1901 of Annual Report for 1915, and page 1208 of Annual Report for 1938, and pages 1069 and 1070 of Annual Report for 1962. Existing project. Below Nashville: Improvement of Cumberland River between mouth and Nashville was authorized for 9-foot navigation; increased project depth to be obtained by construction of three moderate height dams with lockage facilities, designated as Kuttawa (Eureka), Dover, and Cheatham, to replace existing locks A to F inclusive below Nashville and lock 1 above Nashville. (See table 23-B for authorizing legislation.) Subsequent authorities provided for construction of hydroelectric power-generating facilities at Cheatham Dam, river mile 148.7, and modification of project for navigation on Cumberland River, Tenn. and Ky., to provide, in lieu of previously authorized works at Kuttawa, mile 32.2, and Dover, mile 100.1, for construction of a multiple-purpose improvement consisting of a dam, lock, and powerplant near mile 30.6 on lower Cumberland River and a canal for navigation and other purposes connecting this reservoir with reservoir formed by Kentucky Dam on the Tennessee River. The project is known as Barkley Dam and Lake Barkley. Provision of interconnecting canal, involving excavation of a channel through narrow watershed divide about 2.5 miles upstream from damsite, permits alternative routes available for navigation between either Cumberland or Tennessee Rivers and Ohio River, and affords integrated operation of Barkley and Kentucky Reservoirs through diversion of flows in interests of flood control and power production. Estimated cost of modified project for 9-foot navigation and multiple-purpose development is $178,000,000 Federal funds and $102,966 non- Federal funds for recreation facilities under the completed projects program (October 1985). (See table 23-H for listing of principal features.) Under flood conditions as regulated by upstream reservoirs, extreme fluctuation in stage of river below Nashville, Tenn., varies at different localities from about 16 to 55 feet above minimum pool levels. Ordinary fluctuations vary with power flows from as much as the allowable 3-foot drawdown below normal pool elevation 385 at Cheatham Lock and Dam to a range of about 7 feet at Nashville. Seasonal variation in normal headwater levels at Lake Barkley is 5 feet, which in combination with power flows produces fluctuations up to 10 feet below Cheatham Lock and Dam. Above Nashville: See pages 1693 thru 1696 of Annual Report for 1950 for information including statistical data on locks and dams 1 to 17 and 21. Completion information is shown on pages 1454 of the report for 1951. See Table 23-B for Authorizing Legislation. Construction of Old Hickory, Carthage, and Celina Dams above Nashville was also authorized for navigation and power. The dam and reservoir authorized for construction on Cumberland River near Carthage, Tenn., has been redesignated as Cordell Hull Dam and Reservoir. Cost of Old Hickory and Cordell Hull projects, including locks, is estimated at $132,135,100 (October 1985). Estimated cost of Celina Dam (1985) is $213,000,000. (See table 23-H at end of chapter for listing of principal features.) Under flood conditions as presently regulated, including effect of surcharge operation of Old Hickory project, extreme fluctuations of stage in this section of river vary from a range of 35 feet at Nashville (mile 191) to a maximum of 46 feet immediately below Old Hickory Dam (mile 216.2), and from an 8-foot variation in headwater at dam to 36 feet in vicinity of Carthage, Tenn., (mile 313.5), present head of navigation; with variations up to 35 feet at Celina, Tenn. (mile 380.8) and 29 feet in tailwater at Wolf Creek Dam (mile 460.9). Maximum fluctuations under ordinary conditions from power flows vary from about 7 feet at Nashville to 14 and 3 feet, respectively, in tailwater and headwater of Old Hickory Dam, and at other key points as follows: 13 feet at Carthage; 18 feet at Celina; and 19 feet at Wolf Creek Dam. Further details on project authorization for river sections below and above Nashville are shown on Table 23-B. Local cooperation. Under modified project for 9- foot navigation and multiple-purpose development, recreation features of reservoir components are subject to certain conditions of non-Federal cost-sharing under Federal Water Project Recreation Act of 1965. Terminal facilities. There are 42 terminals on the Cumberland River (1 municipally owned and open for public use; 6 government owned facilities and 35 privately owned facilities). A total of 24 terminals have 23-2 NASHVILLE, TN, DISTRICT railroad connections. Principal commodities handled are petroleum products, stone, sand, gravel, coal, coke, iron, steel, chemicals, and grain. Eleven terminals are set up to handle various types of commodities. Facilities considered adequate for existing commerce. For further information see page 695 of Annual Report for 1969. Operations during fiscal year. New work: Below Nashville: Recreation facilities provided at Barkley project under (Code 711) cost $3,870 and at Barkley and Cheatham projects under (Code 713) cost $230,816 and $487,438, respectively. Maintenance: Barkley, Cheatham, Cordell Hull, and Old Hickory locks and dams were operated as required. Operation and Maintenance improvements at Barkley included earthquake studies and improving entrance to Kuttawa Harbor. Contract was awarded for paving Bumpus Mill recreation area. Work at Cheatham included construction at Riverfront Park, Phase II. Contract was awarded for dredging below Old Hickory. Work at Cordell Hull included as built drawings, water to Wartrace and Salt Lick recreation areas, and comfort station at Wartrace. Contract awarded for Evaluation of Effectiveness of Roaring River Fish Barrier. Work at Old Hickory included replacing powerhouse roof and completing Resource Management Base. Contracts were awarded for paying Rockland Recreation Area and Interpretive Materials Exhibit. Total net energy generated at Barkley Dam (663,710,172 kw-hr) was made available through Department of the Interior to the Tennessee Valley Authority, Southern Illinois power Cooperative, Big Rivers Rural Electric Cooperative Corporation, and Indiana Statewide Rural Electric Cooperative, Inc., Hoosier Energy Division. Total net energy generated at Cheatham Dam (175,356,743 kw-hr), Cordell Hull (309,387,499 kw-hr), and Old Hickory (429,995,360 kw-hr) was made available for distribution. Activities under reservoir management program comprising malaria control, shoreline sanitation, land management and disposal, and maintenance of public-use facilities continued. 2. TENNESSEE RIVER, TN, AL AND KY Location. Formed by junction of French Broad and Holston Rivers in eastern Tennessee, 4.4 miles above Gay Street Bridge at Knoxville, flows southwest into northern Alabama, thence in a generally westerly course across north Alabama, to northeast boundary of Mississippi, thence nearly due north across Tennessee and Kentucky, entering Ohio River at Paducah, 652.1 miles from junction of French Broad and Holston Rivers. (See Geological survey base map of Tennessee River Basin.) Previous projects. For details see pages 1902-1906, Annual Report for 1915; pages 1190-1194, 1196-1216, and 1220-1222, Annual Report for 1929; and page 1216, Annual Report for 1938. Existing project. Originally provided for permanent improvement of river for a navigable depth of 9 feet at low water from mouth about 650 miles to Knoxville, Tenn. Only work performed by the Corps was construction of lock at General Joe Wheeler Dam and miscellaneous appurtenant improvements at a new work cost of $2,244,236. Tennessee Valley Authority program provided for obtaining authorized 9-foot project by construction of high dams and locks and utilization of certain locks and dams previously constructed under jurisdiction of the Corps. (See Table 23-B for Authorizing Legislation.) Subsequent construction by that agency of Melton Hill Dam extends navigable channel of Tennessee River system up the Clinch River about 38 miles above damsite (mile 23.1) to vicinity of Clinton, Tenn. (See table 23-I on Tennessee River.) In accordance with general navigation laws placing control and supervision over navigable waters under direction of Secretary of the Army, the Corps of Engineers operates and maintains all locks, and maintains navigation channels and safety harbors by performing all necessary maintenance dredging and snagging operations. For information concerning other functions of the Corps under division of responsibilities for Tennessee River since adoption of Tennessee Valley Authority Act of 1933, see page 1084 of Annual Report for 1962. Local cooperation. Authorization requires no local cooperation in construction of alternate system of low dams. It does, however, provide that if high dams are built before the United States builds projected locks and low dams which are to be replaced, the United States shall contribute to cost of substituted structures an amount equal to estimated cost of works of navigation for which substitution is made. Terminal facilities. There are 165 terminals on the Tennessee River (12 municipally owned, 20 government owned facilities and 133 privately owned facilities). A total of 87 terminals have railroad connections. Principal commodities handled are petroleum products, stone, sand, gravel, coal, coke, grain, chemicals, iron, and steel. Sixty-five terminals handle various types of commodities. Facilities considered adequate 23-3 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 for existing commerce. A list of terminals is revised annually and can be obtained from Division Engineer, Ohio River Division, Corps of Engineers, Cincinnati, Ohio. For further information see page 698 of Annual Report for 1969. Operations during fiscal year. Channel work by government plant and hired labor consisted of dredging and snagging at various locations, and maintenance of mooring facilities and safety harbors. Cost of channel maintenance was $224,399. Maintenance: All locks were operated and lock appurtenances and standby plant maintained as required. Major maintenance work items were unwatering Pickwick and Watts Bar locks, and overhauling operating machinery at Chickamauga lock. Contracts were awarded for storage building at Nickajack, Pickwick lock rehabilitation and painting miter gates at Guntersville. See table 23-J for total cost of existing project to September 30, 1985. 3. TENNESSEE-TOMBIGBEE WATERWAY, AL AND MS Location. West Central Alabama and Northeastern Mississippi; in Marengo, Sumter, Greene and Pickens Counties, Alabama, and Noxubee, Lowndes, Clay, Monroe, Itawamba, Prentiss and Tishomingo Counties, Mississippi. Existing project. Provides for a waterway 234 miles in length, connecting the Tombigbee and Tennessee Rivers by way of the East Fork of Tombigbee River, Mackeys and Yellow Creeks, affording a channel not less than 9 feet deep and 280 feet in bottom width, with 10 locks each having clear chamber dimensions of 110x600 feet. Construction of the divide section, including Bay Springs lock and dam, is assigned to the Nashville District; whereas, the prosecution of work on the river and canal sections is tinder the jurisdiction of the Mobile District. Only activities of the Nashville District are reported hereon. Estimated Federal cost of new work under jurisdiction of the Nashville District is $753,000,000. (See 23-B for authorizing legislation.) Local cooperation. Authorization requires local interests to construct, maintain and operate all highway bridges, construct and maintain all highway relocations or alterations, make and maintain alterations as required to sewer, water supply and drainage facilities, assume cost of operation and maintenance of utility crossings, provide and maintain as required suitable and adequate river and canal terminals in accordance with plans approved by the Secretary of the Army and the Chief of Engineers. Operations during fiscal year. Engineering and design continued. Work continued on contracts for Dredging Pickwick Pool, Access Road Repair and Maintenance, and the Reservoir Management and Maintenance Facility. The claim was settled for the DC4/2A/Plug contract. Contract awarded and work initiated on Channel Improvements at Yellow and Berea Creeks. The project is 99% complete. Navigation features are 100% complete. 4. NAVIGATION WORK UNDER SPECIAL AUTHORIZATION Navigation activities pursuant to Sec. 107, Public Law 86-645, as amended (preauthorization). During the period $106,788 was expended for a study of Port of Florence, AL., $37,382 for Tennessee River at Calvert City, TN., and $105,321 for Tennessee River at Morgan City Port, AL. Alteration of Bridges 5. AUTHORIZED ALTERATION OF BRIDGES Work on Woodland Street bridge, under Truman- Hobbs Act, was initiated in 1965 and completed in 1966. Costs were $987,632. For details see page 922 of Annual Report for 1967. Flood Control 6. BIG SOUTH FORK NATIONAL RIVER AND RECREATION AREA, KY AND TN Location. The proposed project is located in Northeastern Tennessee and Southeastern Kentucky along the Big South Fork River and its tributaries in Pickett, Scott, Fentress, and Morgan Counties, Tennessee, and McCreary County, Kentucky. Existing project. A National Recreation Area will be established in accordance with the concept included in the interagency report prepared pursuant to section 208 of Flood Control Act of 1968. Total acreage is not to exceed 125,000 acres. The act specifically establishes the National Area for the purpose of preserving and interpreting the scenic, biological, archaeological 23-4 NASHVILLE, TN, DISTRICT and historical resources of the river gorge area and developing the natural recreational potential of the area. The area is divided into two categories, gorge and adjacent areas, with no construction permitted except limited clearing for establishment of day-use facilities, historical sites, primitive campgrounds and access roads. Lodges and other facilities will be provided in the adjacent areas. The project was authorized by the Water Resources Development Act of 1974 as amended by Water Resources Development Act of 1976. (See table 23-B for authorizing legislation.) The present authorized cost (ceiling) for the project is $103,522,000. The National Park Service will operate and maintain the useable units of the area upon completion of land acquisition and construction of basic facilities by the Corps of Engineers. The first construction contract was awarded in June 1981. The project is 78% complete. Local cooperation. None required. Operations during fiscal year. Engineering and design continued. Acquired 2,079.16 acres fee. Construction continued on Blue Heron Road-Part I, Bandy Creek Road and Recreation Facility, and Charit Creek Lodge---TVA. Contracts awarded for Blue Heron Access-Part II and Recreation I, Blue Heron Campground, and Blue Heron Overlook. 7. MARTINS FORK LAKE, KY Location. Dam located at mile 15.6 on Martins Fork of Clover Fork, Cumberland River, about 10 miles southeast of city of Harlan, with reservoir extending about 6 miles upstream within Harlan County, southeastern Kentucky. Existing project. Multiple-purpose improvement combining flood control with water quality control and recreation development adopted by 1965 Flood Control Act (H. Doc. 244, 89th Cong.), in general accordance with recommendations. Dam will be concrete type, about 504 feet long and rising 97 feet above streambed. Outlet works provide fcr release of water from reservoir at varying levels. Drainage area above damsite is 55.7 square miles. At full pool level, spillway crest at elevation 1341 above mean sea level, reservoir will cover 578 acres and contain 21,120 acrefeet of storage capacity. Provision is made for 17,450 acre-feet of reservoir capacity between elevations 1341 and 1300 for control of floods in winter and spring season, and 14,360 acre-feet (El. 1341-1310) during summer and fall, in conjunction with which storage of 3,090 acre-feet would be available on a seasonal basis to meet streamflow requirements for water quality control and fish life below the dam. A minimum permanent pool of 3,670 acre-feet, 274 acres in extent, will thus be provided during potential flood seasons; and during late spring and summer when flood storage can be reduced, the lake is to be operated generally at a higher level (El. 1310) to maintain a larger surface area of 340 acres for recreation and to provide the required seasonal storage for releases of water during critical low-flow periods. Project will prevent major portion of average annual flood losses at Harlan and result in significant stage reductions with related benefits along rural reaches and at other urban areas downstream. Actual cost of project including $95,000 code 710 funds is $20,486,676 (October 1985). First construction contract awarded in December 1972. Project completed for beneficial use in September 1978. Local cooperation . Federal Water Project Recreation Act of 1965 (P.L. 89-72) applies in regard to non-Federal participation in recreation development, in addition to which local interests are to provide certain safeguards to ensure functioning of reservoir as intended. In May 1981 a final recreation cost-sharing contract with Harlan County was approved and certain recreation facilities have been jointly developed by the Corps and the County. These facilities, consisting of a swimming beach and a picnic area are now operated and maintained by Harlan County. Recreation investment to date (Corps and Local) is about $100,000. Operations during fiscal year. New work: None. Maintenance: Dam was operated and structures operated as required. 8. MIDDLESBORO, CUMBERLAND RIVER BASIN, KY Location. At Middlesboro, Ky., on Yellow Creek, a tributary entering Cumberland River about 660 miles above its mouth. Existing project. A system of canals and levees around one side of town, arranged so as to divert most headwaters of Yellow Creek away from present channel through heart of city. Protection is thus afforded in large measure to life and property within business district and a large part of residential section. For project details, see page 1088 of Annual Report for 1962. Local cooperation. None required. Operations during fiscal year. Maintenance: Work on levees, canals, and appurtenances was accomplished by hired labor. 23-5 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 9. TUG AND LEVISA FORKS OF THE BIG SANDY RIVER AND UPPER CUMBERLAND, WV, VA AND KY Location. The project is located in the State of West Virginia and the Commonwealths of Kentucky and Virginia. The Cumberland portion consists of the Upper Cumberland River Basin, above Cumberland Falls, Ky. The basin is approximately 100 miles in length, averaging 30 miles in width at the lower portion and 10 miles in width upstream at Harlan, Ky. The Big Sandy Basin is within the Huntington District and the Cumberland within the Nashville District. Existing project. Provides for flood control measures for communities in the Tug and Levisa Forks and Upper Cumberland River Basins. The Cumberland portion has been assigned to the Nashville District. Only activities of the Nashville District are reported hereon. Estimated Federal cost of new work under jurisdiction of the Nashville District is currentby being formulated. The project was authorized by the Energy and Water Development Appropriation Act of 1981, Section 202 of PL 96-367. Local cooperation. Authorizing legislation requires that non-federal interests shall hold and save the United States free from damages due to construction works and maintain and operate all such works after their completion in accordance with regulations by the Secretary of the Army. Operations during fiscal year. Engineering and design continued. Construction continued on the Pine Street Bridge and Approaches. Construction was initiated on the Pineville Levee and Ball Park Pumping Station, the Pineville Relocation Utility contracts, and Barbourville Cutoff contract. Acquired 56.14 acres fee at Pineville and 48.52 acres fee at Barbourville. The project is 31% complete. 10. OHIO RIVER BASIN (NASHVILLE DISTRICT) Location. A series of levees, floodwalls, channel improvements, and reservoirs in Ohio River Basin within Nashville District. Existing project. The general comprehensive plans approved for flood control and other purposes in Ohio River Basin is set forth in legislation listed in Table 23-B. Individual projects, local protection projects and lakes, considered in comprehensive plan within Nashville District are listed in Table 23-K. 11. INSPECTION OF COMPLETED FLOOD CONTROL PROJECTS Flood Control Act of June 22, 1936, and subsequent acts, requires local interests furnish assurances they will maintain and operate certain local protection projects after completion in accordance with regulations prescribed by Secretary of the Army. District Engineers are responsible for administration of these regulations within their respective districts. Maintenance inspections were made during fiscal year of completed protective works in localities transferred to local interests for maintenance and operation. Local interests were advised, as necessary, of measures required to maintain projects in accordance with standards prescribed by regulations. Fiscal year cost was $20,224. Total cost to September 30, 1985 was $272,138. For project inspection data see table 23-M. 12. FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION Flood control and coastal emergencies (Public Law 99, 84th Cong., and antecedent legislation). Actual Federal cost for fiscal year were $202,409 for disaster preparedness. Multiple-Purpose Projects, Including Power 13. CENTER HILL LAKE, OHIO RIVER BASIN, TN Location. Dam is on Caney Fork River, 26.6 miles above its confluence with Cumberland River (mile 309.2) at Carthage, Tenn. It is in DeKalb County, Tenn., about 55 miles east of Nashville, and 14 miles southeast of Carthage, Tenn. Reservoir extends about 64 miles up main stream and about 10 miles up Falling Water River and lies within DeKalb, Putnam, White, and Warren Counties, Tenn. Existing project. A combination earth and concrete gravity-type dam, hydroelectric powerplant, and reservoir for primary purposes of flood control and power production, with a permanent pool for public use and conservation purposes. In addition to main dam structure, provision was made for a rolled-earth dike to close a saddle in reservoir rim near damsite. For further details, see page 1099 of 1962 Annual Report. Actual cost of project including $8,940,642 code 710 funds is $53,412,022 (October 1985). Local cooperation. None required on completed project. Recreation development subject to certain conditions of non-Federal cost-sharing under Federal Water Project Recreation Act of 1965. Operations during fiscal year. New work: Recreation facilities provided under (Code 711) cost $2,209. Maintenance: Dam was operated and structure and its appurtenances maintained as required. Operation of powerplant was continuous except for normal inter- 23-6 NASHVILLE, TN, DISTRICT ruptions and necessary shutdowns for inspection and maintenance purposes. Major maintenance work items were line surveys and property line marking, and repairing roadway expansion joints. Total net energy generated (264,139,069 kw-hr) was made available through Department of the Interior to Tennessee Valley Authority for distribution. Activities under reservoir management involved land management, public relations, and maintenance of public use facilities. 14. DALE HOLLOW LAKE, OHIO RIVER BASIN, TN AND KY Location. Dam is on Obey River, 7.3 miles above its confluence with Cumberland River (mile 380.9) at Celina, Tenn. It is in Clay County, Tenn., and about 80 miles northeast of Nashville, Tenn., 28 miles north of Cookeville, Tenn., and 3 miles east of Celina, Tenn. Reservoir extends about 51 miles up main stream, 10 miles up East Fork, and 6 miles up West Fork of Obey River, and lies within Cumberland and Clinton Counties, Ky., and Clay, Pickett, Overton, and Fentress Counties, Tenn. Existing project. A concrete gravity-type dam, hydroelectric powerplant, and reservoir for primary purposes of flood control and power production with a permanent pool for public use and conservation purposes. See page 1096 of 1962 Annual Report for project details. Estimated cost of project including $2,195,600 code 710 funds and $150,000 non-Federal funds for recreation facilities under the completed projects program is $28,317,746 (October 1985). Local cooperation. None required on completed project; future recreation development subject to certain conditions of non-Federal cost-sharing under Federal Water Project Recreation Act of 1965. Operations during fiscal year. New work: Recreation facilities provided under (Code 711) cost $5,509. Maintenance: Dam was operated and structures and appurtenances maintained as required. Operation of powerplant was continuous except for normal interruptions and necessary shutdowns for inspection and maintenance purposes. Total net energy generated (75,228,200 kw-hr) was made available through Department of the Interior to Tennessee Valley Authority for distribution. Activities under reservoir management program involved public relations, land management, and maintenance of public-use facilities. Contracts were awarded for Washhouse and Fish Cleaning Station, Oil Circuit Breakers, and Paving at Horse Creek and Wolf Creek. 15. J. PERCY PRIEST' DAM AND RESERVOIR, OHIO RIVER BASIN, TN Location. Damsite is on Stones River, 6.8 miles above its confluence with Cumberland River (mile 205.9); in Davidson County, Tenn.; and about 7 miles east of Nashville, Tenn. Reservoir extends southeasterly from dam about 32 miles along main stream, 10 miles up East Fork, 6.5 miles up West Fork, and for shorter distances up other tributaries of Stones River; and lies within Davidson, Rutherford, and Wilson Counties, Tenn. Existing project. A combination earth and concrete gravity-type dam, hydroelectric powerplant, and reservoir for primary purposes of flood control, power production and recreation. For further details see page 703 of 1969 Annual Report. Estimated cost of project including $3,260,400 under code 710 funds and $46,000 non-Federal funds for recreation facilities under the completed projects program is $56,914,039 (October 1985). Local cooperation. Recreation development subject to certain conditions of non-Federal cost-sharing under Federal Water Project Recreation Act of 1965. Operations during fiscal year. New work: None. Maintenance: Dam was operated and structures and appurtenances maintained as required. Total net energy generated (58,492,100 kw-hr) was made available through Department of the Interior to Tennessee Valley Authority for distribution. Activities under reservoir management program involved public relations, fish and wildlife management, and maintenance of public-use facilities. Contracts were awarded to Pave Parking Areas and Road, and for Utility System at Anderson Road Recreation Area. 16. LAUREL RIVER LAKE, OHIO RIVER BASIN, KY Location. Damsite is at mile 2.3 on Laurel River, a tributary of Cumberland River, in southcentral Kentucky. The two streams meet about 9 miles below Cumberland Falls, a prominent physiographic feature at head of Lake Cumberland which is formed by Wolf Creek Dam. Reservoir extends 19.2 miles upstream to site of Corbin, Ky. water-supply dam and lies within Laurel and Whitley Counties. Existing project. Project approved in general accordance with recommendations of House Document 413, 86th Congress, by 1960 Flood Control Act, as amended by Public Law 88-253, was designed for purposes of flood control, power, and recreation as an integral unit of a coordinated plan for development of 23-7 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 water resources of Cumberland River Basin. With the view of a net gain in power potential on a system basis, the plan of improvement incorporated appropriate flood control storage in the proposed project and corresponding adjustment in operations of Wolf Creek Dam-Lake Cumberland for flood control and power, which in effect constituted a transfer of reservoir capacity without entailing a change in flood control benefits. Further detailed study giving full consideration to power capabilities and marketing arrangements indicated the advantage of maintaining present storage allocation at Wolf Creek and use of all available storage capacity of Laurel River Lake for power. The power plant is complete. Recreation is under construction. Total estimated cost is $56,683,232 (October 1985). Local cooperation. None required. Operations during fiscal year. New work: Contract awarded for Resource Management Office. Forest Service continued work on recreation sites under agreement. The project is 99% complete. Maintenance: Dam was operated and structures and appurtenances maintained as required. Total net energy generated (52,647,000 kw-hr) was made available through Department of the Interior for distribution. 17. WOLF CREEK DAM-LAKE CUMBERLAND, OHIO RIVER BASIN, KY Location. Wolf Creek Dam is on Cumberland River at mile 460.9 (above mouth) in Russell County, Ky., about 10 miles southwest of Jamestown and 12 miles north of Albany, Ky. Lake Cumberland extends 101 miles up main stream, 48 miles up South Fork of Cumberland River, in Russell, Clinton, Wayne, Pulaski, McCreary, Laurel, and Whitley Counties, Ky. Existing project. A combination earth and concrete gravity-type dam, hydroelectric powerplant, and reservoir for primary purposes of flood control and power production, with a permanent pool for publicuse and conservation purposes. See page 1094 of 1962 Annual Report for project details. Estimated cost of project is $188,267,195 (October 1985). This estimate includes $3,259,372 code 710 funds, $880,000 non-Federal funds for recreation facilities under the completed program, and $104,999,237 for major rehabilitation. Local cooperation. None required on completed project; future recreation development subject to certain conditions of non-Federal cost-sharing under Federal Water Project Recreation Act of 1965. Operations during fiscal year. New work: Activity involving the integrity of the structure began in 1968 when a leak or seepage developed in the embankment. The major rehab embankment contract was physically completed in September 1982. Maintenance: Dam was operated and structures and appurtenances maintained as required. Operation of powerplant was continuous except for normal interruptions and necessary shutdowns for inspection and maintenance purposes. Contracts were awarded for Sanitary Facility at Kendall Recreation Site, and for Oil Circuit Breakers. Total net energy generated (667,127,000 kw-hr) was made available through Department of the Interior for distribution. Activities under reservoir management program involved land management activities, public relations, and maintenance of public-use facilities. General Investigations 18. SURVEYS Costs for this period were $1,572,988 for which $795,501 was for navigation, $670,544 for flood damage prevention studies, $1,431 for review of completed projects, $39,960 for special investigations, and $65,552 for coordination studies with other agencies. 19. COLLECTION AND STUDY OF BASIC DATA - Costs for this period were $39,227 for technical services to others, and $35,739 for flood plain management services, totalling $74,966. 23-8 NASHVILLE, TN, DISTRICT TABLE 23-A COST AND FINANCIAL STATEMENT See Section Total to in Text Project 1. Cumberland River, TN and KY 2. Tennessee River, TN, AL and KY 3. Tenn.-Tombigbee Waterway, AL and MS 5. Big South Fork National River and Rec. Area, KY and TN 6. Martins Fork Lake, KY 7. Middlesboro, Cumberland River Basin, KY 8. Tug & Levisa Forks of the Big Sandy & Cumberland River, WV, VA and KY 11. Cumberland, KY 12. Center Hill Lake, Ohio River Basin, TN 13. Dale Hollow Lake, Ohio River Basin, TN and KY 14. J. Percy Priest Dam and Reservoir, Ohio River Basin, TN 15. Laurel River Lake, Ohio River Basin, KY Funding New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost Rehab. Approp. Cost New Work Approp. Cost New Work Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost New Work Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost FY 82 FY 83 FY 84 FY 85 Sep 30, 1985 466,319 417,163 14,079,949 13,918,143 390,000 65,642 12,715,140 11,954,181 - - 7,027,000 7,153,000 6,958,972 7,004,232 11 104,390,000 105,650,243 8,958,124 15,036,650 26,876 100,729 357,000 354,482 55,000 70,428 2,200,000 1,733,344 14,200 21,715 2,155,880 2,178,280 2,529,880 2,584,143 68,000 71,607 1,756,880 1,847,366 3,650,000 3,735,017 773,000 811,751 65,516,000 65,822,382 10,975,000 10,731,095 100,000 64,253 491,000 500,189 39,000 36,553 8,270,000 2,854,007 146,947 8,767 3,605,000 3,268,063 365,441 30,437 2,988,000 2,828,213 - 6,907 3,902 1,985,000 1,959,925 2,170,000 2,522,143 773,000 716,769 929,000 - 7,800 320,168,316 1,2.s 523,103 722,194 320,092,192 1,2.4 L4,670,200 18,453,000 179,268,037 5 L5,494,335 18,461,695 178,331,253 6 - - 16,251,428 7 - - 16,251,428 6,848,500 9,855,000 101,487,951 8 6,978,158 9,755,161 101,124,823 9 - - 400,000 - - 400,000 25,000,000 19,755,000 724,755,050 L7,837,084 27,688,233 723,457,974 10,300,000 8,405,000 81,059,155 10 9,432,902 9,183,262 80,240,524 11 - 50,000 - 20,486,676 244 - 20,486,676 406,000 545,000 2,750,000 401,981 523,757 2,707,631 - - 817,830 12 - - 817,83012 22,000 65,000 1,695,844 27,384 60,309 1,687,453 4,000,000 13,684,000 30,654,000 18 8,286,077 14,504,087 28,785,60814 - - 66,642 - - 66,642 9,000 - 53,412,02215 153,247 2,209 53,412,022 1e 3,790,000 3,198,000 37,197,96717 4,078,470 3,195,628 37,081,883 1s 30,000 - 17,700 28,317,746 19 341,796 5,509 28,317,746 20 2,554,000 3,180,000 36,024,807 21 2,732,605 2,966,610 35,789,525 22 - - 56,914,039 28 3,810 471 56,914,039 24 2,290,500 2,553,000 22,762,586 25 2,173,573 2,489,352 22,522,01226 545,000 - 56,683,232 379,374 219,221 56,599,550 771,000 864,000 5,157,000 828,369 840,428 5,119,662 23-9 1 1 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 23-A COST AND FINANCIAL STATEMENT (Continued) See Section Total to in Text Project Funding FY 82 FY 83 FY 84 FY 85 Sep 30, 1985 16. Wolf Creek Dam and New Work Lake Cumberland, Approp. 223,000 - 28,051 - 12,300 77,800 83,267,958 27 Ohio River Basin, KY Cost 271,052 13,994 2,615 79,000 83,258,768 27 Maint. Approp. 2,403,880 3,059,000 3,894,000 5,360,000 50,499,441 28 Cost 2,358,456 2,858,455 4,097,459 5,066,321 50,097,629 " Rehab. Approp. - 90,000 - - 35,000 - 104,999,237 s Cost 765,037 22,686 7,249 - 104,999,237 sO 1. Includes $9,707,354 for abandoned and/or replaced works under the old Cumberland River system. (Amount includes $826,253 for new work and $3,266,706 for maintenance on previous projects.) 2. Includes $61,733 public works acceleration funds, and $102,966 contributed by the State of Kentucky and $6,750 contributed by Metropolitan Nashville, TN. 3. Includes $298,000 funds provided from the Productive Employment Appropriation Act (PL 98-8) of 1983. 4. Includes $32,040 funds provided from the Productive Employment Appropriation Act (PL 98-8) of 1983. 5. Includes $955,889 for special recreation use fees, and $1,601,079 for maintenance and operation of dams and other improvements of navigable waters, and $1,892,000 funds provided from the Productive Employment Appropriation Act (PL 98-8) of 1983. 6. Includes $955,889 for special recreation use fees and $1,601,079 for maintenance and operation of dams and other improvements of navigable waters, and $1,892,000 funds provided from the Productive Employment Appropriation Act (PL 98-8) of 1983. 7. Includes $14,007,193 for new work and $4,005,175 for maintenance on previous projects. 8. Includes $495,763 for maintenance and operation of dams and other improvements of navigable waters, and $764,000 funds provided from the Productive Employment Appropriation Act (PL 98-8) of 1983. 9. Includes $495,763 for maintenance and operation of dams and other improvements of navigable waters, and $764,000 funds provided from the Productive Employment Appropriation Act (PL 98-8) of 1983. 10. Includes $300,000 funds provided from the Productive Employment Appropriation Act (PL 98-8) of 1983. 11. Includes $300,000 funds provided from the Productive Employment Appropriation Act (PL 98-8) of 1983. 12. Includes $33,876 Emergency Relief Funds. 13. Includes $6,470,000 contributed by the State of Kentucky. 14. Includes $5,336,932 contributed by the State of Kentucky. 15. Includes $35,896 public works acceleration funds, and $148,000 funds provided from the Productive Employment Appropriation Act (PL 98-8) of 1983. 16. Includes $35,896 public works acceleration funds, and $148,000 funds provided from the Productive Employment Appropriation Act (PL 98-8) of 1983. 17. Includes $292,280 funds for special recreation use fees, and $56,500 for maintenance and operation of dams and other improvements of navigable waters, and $91,000 funds provided from the Productive Employment Appropriation Act (PL 98-8) of 1983. 18. Includes $292,280 funds for special recreation use fees, and $56,500 for maintenance and operation of dams and other improvements of navigable waters, and $91,000 funds provided from the Productive Employment Appropriation Act (PL 98-8) of 1983. 19. Includes $51,789 public works funds and $150,000 contributed by the State of Tennessee, and $341,000 funds provided from the Productive Employment Appropriation Act (PL 98-8) of 1983. 20. Includes $51,789 public works funds and $150,000 contributed by the State of Tennessee, and $341,000 funds provided from the Productive Employment Appropriation Act (PL 98-8) Sof 1983. 21. Includes $339,480 funds for special recreation use fees, and $56,500 for maintenance and operation of dams and other improvements of navigable waters, and $482,000 funds provided from the Productive Employment Appropriation Act (PL 98-8) of 1983. 22. Includes $339,480 funds for special recreation use fees, and $56,500 for maintenance and operation of dams and other improvements of navigable waters, and $482,000 funds provided from the Productive Employment Appropriation Act (PL 98-8) of 1983. 23. Includes $46,000 contributed by the Metropolitan Government, Nashville, TN. 24. Includes $46,000 contributed by the Metropolitan Government, Nashville, TN. 25. Includes $260,680 for special recreation use fees, $40,000 funds provided from the Productive Employment propriation Act (PL 98-8) of 1983. and Ap- 26. Includes $260,680 for special recreation use fees, and $40,000 funds provided from the Productive Employment Appropriation Act (PL 98-8) of 1983. 27. Includes $96,920 public works acceleration funds, and $880,000 contributed by the State of Kentucky. 28. Includes $82,048 public works acceleration funds, and $56,500 for maintenance and operation of dams and other improvements of navigable waters, and $278,780 funds for special recreation use fees, and $293,000 funds provided from the Productive Employment Appropriation Act (PL 98-8) of 1983. 29. Includes $82,048 public works acceleration funds, and $56,500 for maintenance and operation of dams and other improvements of navigable waters, and $278,780 funds for special recreation use fees, and $293,000 funds provided from the Productive Employment Appropriation Act (PL 98-8) of 1983. 30. Includes $203,757 for claim paid on initial construction of switchyard. 23-10 NASHVILLE, TN, DISTRICT AUTHORIZING LEGISLATION See Section Date of in Text Authorized Act Project and Work Authorized Documents 1. CUMBERLAND RIVER BELOW NASHVILLE Jul 13, 1892 Jun 25, 1910 Aug 30, 1935 Jul 24, 1946 Jun 19, 1952 Sep 3, 1954 Jul 14, 1960 Aug 5, 1886 Mar 2, 1907 Mar 2, 1919 Jun 5, 1920 Jul 3, 1930 Jun 26, 1934 2 Jul 24, 1946 Oct 1, 1980 Jul 3, 1930 May 18, 1933 Provision made for lock A Provision made for locks B to F, and for dredging below lock F. Repairing dams A to F, inclusive, and surmounting same with movable crests. Provision of 9-foot channel by the construction of 3 moderate height dams below Nashville; via, Kuttawa (Eureka), Dover, and Cheatham. Provision for hydroelectric power production as a function of Cheatham Dam. Construction of Barkley (Lower Cumberland) dam and reservoir project for navigation, flood control, hydroelectric power, and related purposes in lieu of Kuttawa and Dover navigation-only structures. Authorized change in alignment of Illinois Central Railroad. CUMBERLAND RIVER ABOVE NASHVILLE Provision made for locks and dams; the Secretary of War to determine the final plan of improvement. Dimensions of the locks fixed in accordance with reports of Mar. 30, 1887, and Nov. 25, 1890. Adoption of the report of the Board of Engineers, dated Feb. 26, 1906, limiting the lock and dam construction to locks and dams 1 to 7, and 21. Provision made for locks and dams 8 to 17. Authorizes work to proceed in Tennessee without waiting for action of local interests in Kentucky. Raising dam 1, 3 feet. Operation and care of locks and dams provided for with funds from War Department appropriations for rivers and harbors. Construction of Old Hickory, Cordell Hull (Carthage), and Celina Dams above Nashville for navigation and the development of power resources. Design and construct flood control measures for communities in the Upper Cumberland River basins. TENNESSEE RIVER Authorized navigable depth of 9 feet from mouth about 650 miles to Knoxville, Tennessee to be obtained by construction of low dams. Authorized TVA to construct such dams in the Tennessee River as will provide a 9 foot channel. Annual Report, 1890, p. 2151 H. Does. 758, 60th Cong., 1st sess.; and 1481, 60th Cong., 2d sess. 1 H. Doc. 38, 73d Cong., 1st sess. H. Doc. 761, 79th Cong., 2d sess. S. Doc. 81, 83d Cong., 2d sess. H. Doc. 56, 86th Cong., 2d sess. Annual Report 1884, p. 1663. Annual Report 1888, p. 1622, and Annual Report 1892, p. 1933. H. Doe. 699, 59th Cong., 1st sess. Rivers and Harbors Committee Doc. 10, 63d Cong., 2d sess. Rivers and Harbors Committee Doc. 26, 70th Cong., 2d sess. H. Doe. 761, 79th Cong., 2d sess. Sec. 202, PL 96-367 H. Doc. 328, 71st Cong., 2d sess. 23-11 TABLE 23-B 2. REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 23-B (Continued) AUTHORIZING LEGISLATION See Section Date of in Text Authorized Act Project and Work Authorized Documents 9. OHIO RIVER BASIN, NASHVILLE DISTRICT Construct levees, floodwalls, and drainage structures for protection of cities and towns in Ohio River Basin. Project to be selected by Chief of Engineers with approval of Secretary of War at a cost not to exceed $24,877,000 for construction. Approved general comprehensive plan for flood control and other purposes in Ohio River Basin as may be advisable at discretion of Secretary of War and Chief of Engineers, and for initiation and partial accomplishment of plan, authorized $75 million for reservoirs and $50,300, for local flood protection works. Additional $45 million for prosecution of comprehensive plan for Ohio River Basin. Dec 22, 1944 Additional $70 million for further prosecution of comprehensive plan for Ohio River Basin. Jul 24, 1946 Additional $125 million for further prosecution of comprehensive plan. Flood Control Committee Doc. 1, 75th Cong., 1st ses. Flood Control Committee Doc. 1, 75th Cong., 1st sess. H. Doc. 762, 77th Cong., 2d sess. H. Doc. 506, 78th Cong., 1st sess. Additional $100 million for prosecution of comprehensive plan for Ohio River Basin. Additional $150 million for further prosecution of comprehensive plan for flood control and other purposes in Ohio River Basin. Jun 18, 1965 Additional $89 million for further prosecution of comprehensive plan for Ohio River Basin. Aug 13, 1968 Additional $35 million for further prosecution of comprehensive plan for Ohio River Basin. Jun 19, 1970 Additional $69 million for further prosecution of comprehensive plan for Ohio River Basin. Mar 7, 1974 Authorized establishing Big South Fork National River and Recreation Area, KY and TN. Total area not to exceed 125,000 acres. Mar 7, 1974 Additional $120 million for further prosecution of comprehensive plan for Ohio River Basin. TENNESSEE-TOMBIGBEE WATERWAY Jul 24, 1946 Construction of waterway to connect above rivers and provide a 9 foot channel and minimum bottom width of 170 feet in river and canal sections and 150 feet in the divide cut, with locks 110 by 600 feet clear inside dimensions. Subsequent studies determined most practical plan consists of channel with bottom width of 300 feet (280 feet in divide cut), fewer locks with higher lifts resulted in reducing number of lifts from 18 to 10 and reduced length from 260 to 253 miles. H. Doc. 6755, 89th Cong., 1st seas. S. 3710, 90th Cong., 2d sess. H. R. 15166 91st Cong., 2d sess. H. R. 10203 93rd Cong. Water Resources Develop. Act of 1974 Amended by PL 94-587, 94th Cong. H. R. 10203 93rd Cong. River Basin Monetary Authorization Act of 1974. H. Doc. 486, 79th Cong., 2d sess. Page 1343, Part I, FY 1968 House Hearings. 1. Contains latest published maps. Included in Public Works Administration program Sept. 6, 1933. 2. Permanent Appropriation Repeal Act. 23-12 Aug 28, 1937 Jun 28, 1938 Aug 18, 1941 May 17, 1950 Dec 30, 1963 3. NASHVILLE, TN, DISTRICT TABLE 23-C OTHER AUTHORIZED NAVIGATION PROJECTS (All Projects not Specifically Identified in Text) For last Full Cost to Sep 30, 1985 Report see Operation and Project Status Annual Report Construction Maintenance Caney Fork River, TN abandoned 1895 $ 27,828 - Clinch River, TN and VA abandoned 1923 53,949 $ 7,873 Duck River, TN abandoned 1887 13,000- Elk River, AL and TN abandoned 1904 4,000 - French Broad and Little Pigeon Rivers, TN abandoned 1931 249,605 33,554 Hiwassee River, TN abandoned 1923 113,311 9,754 Holston River, TN abandoned 1911 5,714 Little Tennessee River, TN abandoned 1888 5,510 - Obey River, TN abandoned 1887 11,500- Red River, TN abandoned 1884 5,000- South Fork of Cumberland River, KY abandoned 1892 11,967 - TABLE 23-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS (All Projects not Specifically Identified in Text) For last Full Cost to Sep 30, 1985 Report see Operation and Project Status Annual Report Construction Maintenance Barbourville, KY completed 1963 $2,088,147 - Chattanooga, TN and Rossville, GA completed 1949 180,997 - Coal Creek and Tributaries (Lake City), TN completed 1962 460,134- Corbin (Lynn Camp Creek), KY completed 1969 567,703 - Middlesboro (Yellow Creek), KY completed 1949 26,309 - Paint Rock River, AL completed 1967 544,173 - Pineville, KY completed 1963 1,679,126 - 1 Rossview Reservoir, Ohio River Basin, TN and KY inactive - 6,779 - 1. Includes $9,950 contributed funds. 23-13 TABLE 23-F REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 OTHER AUTHORIZED MULTIPLE-PURPOSE PROJECTS INCLUDING POWER For last Full Cost to Sep 30, 1985 Report see Operation and Project Status Annual Report Construction Maintenance Barkley Dam and Lake Barkley, KY and TN beneficial use - $146,423,058 $51,660,1101 Celina Dam, KY active 222,575 - 1 Cheatham Lock and Dam, TN beneficial use - 31,682,224 36,508,088 1 Cordell Hull Lock and Dam, TN beneficial use - 79,874,492 24,462,2771 Old Hickory Lock and Dam, TN beneficial use - 52,266,412 48,422,417 1 1. Details given under "Cumberland River, TN and KY." See Table 23-H. TABLE 23-G DEAUTHORIZED PROJECTS For last Full Federal Contributed Report see Funds Funds Project Annual Report for Date and Authority Expended Expended Three Islands Reservoir, Ohio 1970 Authorized: FC Act 1938, PL 761, 75 $111,855 - River Basin, TN Cong., 3rd sess.; FC Act 1946, PL 525, 79th Cong., 2d sess. Deauthorized: 5 Aug 1977. 23-14 NASHVILLE, TN, DISTRICT TABLE 23-H CUMBERLAND RIVER, TN AND KY: PRINCIPLE FEATURES (See Section 1 of Text) Dam and Reservoir Barkley Cheatham Old Hickory Nearest town Miles above mouth of river Lock dimensions (feet) 1 Lift at normal pool levels (feet) Depths on guardsills at minimum pool levels (feet) Character of foundation Dam: Type Height Length, exclusive of lock section (feet) Spillway: Gross length (feet) Net length opening (feet) Crest gates: Type Number Size (feet) Operating levels at dam (feet, mean sea level) : Maximum regulated Normal operation: Full pool Minimum pool Minimum pool in advance of floods Reservoir area (acres) Reservoir capacity (acre-feet) : Flood control Power drawdown Dead storage Total Canal: Length (miles) Bottom width (feet) Depth at minimum pool level (feet) Power development: Number of units Generator rating (kilowatts) Total installation (kilowatts) Kuttawa, KY, 11 miles. 30.6 110 by 800 57 11, upper; 13, lower Rock Concrete gravity and earthfill 157 9,959 804 660 Tainter 12 55 by 50 Ashland City, TN, 9 miles. 148.7 110 by 800 26 14, upper; 17, lower Rock Concrete gravity 75 800 480 420 Tainter 7 60 by 27 375 359 354 346 93,430 1,213,000 s.4 259,000 610,000 2,082,000 385 382 7,450 19,800 7 84,200 104,000 Old Hickory, TN, 3 miles. 216.2 84 by 400 60 14, upper; 13, lower Rock Concrete gravity and earthfill 98 3,605 2 325 270 Tainter 6 45 by 41 450 8 442 27,450 125,000 5 63,000 357,000 545,000 Carthage, TN, 5 miles. 313.5 84 by 400 59 14, upper; 13, lower Rock Concrete gravity and earthfill 93 1,138 2 291 225 Tainter 5 45 by 41 508 8 508 501 499 13,920 85,600 5,6 20,500 204,800 310,900 1.75 400 11 4 32,500 130.000 3 12,000 36.000 4 25,000 100,000 3 33,333 100,000 23-15 Cordell iull Celina Celina, TN, 5 miles. 385.4 Rock Concrete gravity and earthfill 86 2,298 290 250 Tainter 5 50 by 37 564 560 559 559 16,960 55,950 s 14,700 287,300 357,950 3 36,000 108,000 -r - - REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 23-H CUMBERLAND RIVER, TN AND KY: PRINCIPLE (Continued) (See Section 1 of Text) FEATURES Dam and Reservoir Barkley Celina Cheatham Cordell Hull Old Hickory Percent of project completion 8 - 8 8 8 Year opened to navigation 1964 - 1952 1973 1954 Estimated cost 9 $146,300,000 $213,000,000 $31,700,000 $79,874,500 $52,260,600 1. Clear width and length available for full width. 2. Exclusive of lock section. 3. Surcharge. 4. Normal operation (elev. 375-359) during nonflood season; flood control allowance to be increased to 1,472,000 acrefeet (elev. 375-354) during season of major floodflows. 5. Surcharge storage. 6. During flood season (elev. 508-501); minimum 51,800 acre-feet (elev. 508-504) with normal operation during nonflood season. 7. Daily pondage allowance; run-of-river project. 8. Completed for full beneficial use. 9. Includes recreation facility costs. 23-16 TABLE 23-I TENNESSEE RIVER (See Section 2 of Text) Lock Dimensions Length Minimum Depth Width Avail. Lift on Guard Sills of able for Year Miles Cham. Full Nor- Maxi- Opened Cost of Above Miles from her Width mal mum Lower Upper Character Navi- Kind Type of Each Lock Project ' Mouth Nearest Town (feet) (feet) (feet) (feet) (feet) (feet) of Foundation gation of Dam Construction and Dam Kentucky Pickwick Landing: Auxiliary lock Main lock Wilson: Auxiliary lock Main lock General Joe Wheeler: Auxiliary lock Main lock Guntersville: Auxiliary lock Main lock Nickajack: Auxiliary lock Main lock Chickamauga Watts Bar Fort Loudon Melton Hill (Clinch R.) to C4z 22.4 0.5 above Gilbertsville, KY 206.7 4.4 above Hamburg, TN 206.7 4.4 above Hamburg TN 259.4 2.9 above Florence, AL 259.4 2.9 above Florence, AL 274.9 18.4 above Florence AL 274.9 18.4 above Florence, AL 349.0 9.1 below Guntersville, AL 349.0 9.1 below Guntersville, AL 424.7 39.4 below Chattanooga, TN 424.7 39.4 below Chattanooga, TN 471.0 6.9 above Chattanooga, TN 529.9 6.8 above Breedenton, TN 602.3 1.3 above Lenoir City, TN 23.1 22.1 above Kingston, TN 110 600 56 73.3 110 600 55 63.0 110 1000 55 63.0 60 292 94 100.0 300 110 600 94 100.0 60 400 48 51.5 110 600 48 51.5 60 110 110 110 60 60 60 75 360 39 45.0 600 39 45.0 600 800 360 360 360 400 39 41.0 39 41.0 49 53.0 58 70.0 72 80.0 54 60.0 12.7 11.0 Limestone 12.8 10.0 Limestone 12.8 10.0 Limestone 11.0 4 11.2 Limestone 13.0 13.0 Limestone 13.2 14.7 Limestone 13.0 13.0 Limestone 11.8 13.0 Limestone 12.7 13.0 Limestone 13.0 13.0 Limestone 13.0 13.0 Limestone 13.0 10.0 Limestone 11.8 12.0 Shale 11.8 12.0 Limestone 13.0 13.0 Limestone 1942 Fixed Concrete and 2 earthfill 1937 Fixed Concrete and 8 earthfill 1984 Fixed Concrete and 8 earthfill 1927 Fixed Concrete and $46,973,540 earthfill 1959 - - 7 1934 Fixed Concrete and earthfill 1963 Fixed Concrete and earthfill 1937 Fixed - 1965 Fixed Concrete and earthfill 1967 Fixed Concrete Fixed Concrete 1939 Fixed - 1941 Fixed Concrete and earthfill 1943 Fixed Concrete and earthfill 1963 Fixed Concrete 1,796,295 6 7 3&7 7 7 7 3&7 1. H. Doc. 328, 71st Cong., 2d sess., contains table, pp. 98 and 99, giving pertinent information concerning low dams contemplated under 1930 project. Annual Report for 1938, pp. 1218 and 1219, contains similar information pertaining to low dams in addition to existing locks and dams, including those constructed or under construction by Tennessee Valley Authority. 2. Lock and dam constructed by Tennessee Valley Authority. 3. Lock and dam constructed by Tennessee Valley Authority. Design for lock prepared with Corps forces and funds. 4. Tailwater in canal; flight of 2 locks. 5. Constructed by the Corps under authority of sec. 124, National Defense Act of June 3, 1916 (H. Doc. 1262, 64th Cong., 1st sess.). Actual cost of lock and dam. 6. Actual cost of lock only as constructed by the Corps; dams constructed by Tennessee Valley Authority. 7. Constructed by Tennessee Valley Authority. ti REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TENNESSEE RIVER, TN, AL, AND KY TOTAL COST OF EXISTING PROJECTS TO (See Section 2 of Text) SEP 30, 1985 Channel Operation & Funds New Work Maintenance Maintenance Total Regular $2,244,236 $6,968,669 $90,139,309 $99,352,214 1,2 Maintenance - - 11,665 11,665 Increase of compensation, - 5 - 5 rivers and harbors, 1919 (certified claims) Total $2,244,236 $6,968,674 $90,150,974 $99,363,884 1.2 1. In addition, surplus property value at $54,336 was tion and care of works of improvement under provisions of transferred from the project without reimbursement. Excludes appropriation for such purposes. $4,005,175 expended between 1890 and June 30, 1935, on opera- 2. Excludes $14,007,192 previous construction cost. TABLE 23-K OHIO RIVER BASIN (NASHVILLE DISTRICT) LOCAL PROTECTION PROJECTS Estimated Cost Type of Location Protection Federal Non-Federal Total Middlesboro Levees $581,000 $161,000 $742,000 1 (Yellow Creek, KY) Cumberland, KY Channel 520,000 240,000 760,000 1 Improvement 1. Deferred. TABLE 23.L RESERVOIRS Total Estimated Tributary Basin and Reservoir Stream Cost Center Hill Lake, TN Caney Fork River $53,412,000 1 Dale Hollow Lake, TN and KY Obey River 28,167,700 1 J. Percy Priest Dam & Reservoir, TN Stones River 59,038,200 1. Laurel River Lake, KY Laurel River 56,683,200 8 Martins Fork Lake, KY Martins Fork 20,486,700 Rossview, TN & KY Red River 12,590,000 4.5 1. Details of this project are in individual report. 2. Formerly Stewarts Ferry Reservoir. 3. See "Other authorized multiple-purpose projects." 4. See "Other authorized flood control projects." 5. Deferred. 23-18 TABLE 23-J NASHVILLE, TN, DISTRICT TABLE 23-M INSPECTION OF COMPLETED FLOOD CONTROL PROJECTS (See Section 10 of Text) Project Date of Inspection Barbourville, KY Apr. 1985 and Sep. 1985 Corbin, KY Apr. 1985 and Sep. 1985 Lake City, TN May 1985 and Oct. 1985 Middlesboro, KY (Yellow Creek) May 1985 and Sep. 1985 Middlesboro, KY (Diversion Canal) May 1985 and Sep. 1985 Paint Rock River, KY May 1985 and Oct. 1985 Pineville, KY May 1985 and Sep. 1985 Spring City, TN May 1985 and Oct. 1985 TABLE 23-N FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION Flood Control activities pursuant to Section 205 P.L. 858, 80th Congress, as amended Project FY 85 Cost Browns Creek, Nashville, TN $92,891 Dry Creek, Goodlettsville, TN 37,991 East Fork, Yellow Creek, TN 1,041 Gainesboro, TN 5,000 Little Harpeth River, Brentwood, TN 9,603 Richland and Sugartree Creeks, TN 63,351 Todd's Lake, Murfreesboro, TN 7,500 Whiteoak Creek, Sunbright, TN - 22,061 Emergency Bank Protection (Section 14 of the 1946 Flood Control Act, P.L. 526, 79th Congress) Project FY 85 Cost Concord Park, Fort Loudoun, TN $ 1,752 1 Metro Center Levee, TN 288,314 Piney River, Rhea County, TN 25,888 1. Includes $20 contributed funds from the city of Fort Loudoun, TN. 23-19 LOUISVILLE, KY. DISTRICT* This district comprises a portion of southwestern Ohio, Rivers) from mile 438 (below Pittsburgh) immediately west central Kentucky, a small portion of north central upstream from Foster, KY. to mouth. Tennessee, Indiana except northern part, and southeastern Illinois except Cairo-Mounds-Mound City All cost and financial statements for projects are listed area, all included in drainage basin of Ohio River and its at the end of this chapter. All other tables are referenced tributaries (exclusive of Tennessee and Cumberland in text and also appear at the end of this chapter. IMPROVEMENTS Navigation - Locks and Dams Page 1. Construction of Locks and Dams, Ohio River..............................24-2 2. Green and Barren Rivers, KY............ 24-2 3. Kentucky River, KY....................24-2 4. Open Channel Work, Ohio River........... 24-3 5. Other Authorized Navigation Projects ............................... 24-3 6. Navigation Work Under Special Authorization .......................... 24-3 Flood Control - Local Protection 7. Dayton, KY............................24-3 8. Evansville, IN .......................... 24-3 9. Levee Unit No. 5, W abash River, IN...................... .24-4 10. Mason J. Niblack Levee, Wabash River, IN........................ 24-4 11. Mill Creek, OH.........................24-4 12. Southwestern Jefferson County, KY ............................ 24-5 Flood Control - Reservoirs 13. Barren River Lake, KY ................... 24-5 14. Brookville Lake, IN................ ..... 24-5 15. Buckhorn Lake, KY ...................... 24-6 16. Caesar Creek Lake, OH...................24-6 17. Cagles Mill Lake, IN....................24-6 18. Carr Fork Lake, KY .................... 24-7 19. Cave Run Lake, KY.....................24-7 20. Cecil M. Harden Lake, IN................. 24-7 21. Clarence J. Brown Dam & Reservoir, OH........................24-8 22. Green River Lake, KY.................... 24-8 23. Huntington Lake, IN....................24-8 24. Mississinewa Lake, IN.................... 24-9 25. Monroe Lake, IN.......................24-9 26. Nolin Lake, KY......................... 24-9 27. Ohio River Basin (Louisville Dist.)........................24-10 28. Patoka Lake, IN........................24-10 29. Rough River Lake and Channel Improvement, KY......................24-10 30. Salamonie Lake, IN....................24-11 31. Taylorsville Lake, KY..................24-11 Page 32. Wabash River Basin....................24-12 33. West Fork of Mill Creek Lake, OH........ 24-12 34. William H. Harsha Lake, OH............24-12 35. Inspection of Completed Flood Control Projects........................ 24-13 36. Other Authorized Flood Control Projects.............................. 24-13 37. Flood Control Works Under Special Authorization...................24-13 General Investigations 38. Surveys .............................. 24-13 39. Collection and Study of Basic Data........ 24-13 40. Continuation of Planning and Engineering...........................24-13 41. Advance Engineering and Design........ 24-13 Tables Table 24-A Cost and Financial Statement .................... . 24-14 Table 24-B Authorizing Legislation.......... 24-18 Table 24-C Other Authorized Navigation Projects.......................24-19 Table 24-D Not Applicable Table 24-E Other Authorized Flood Control Projects................24-20 Table 24-F Not Applicable Table 24-G Deauthorized Projects...........24-22 Table 24-H Principal Features of Green and Barren Rivers and Kentucky River Navigation Systems........24-23 Table 24-I Ohio River Basin - Total Cost of Basin Plan..............24-24 Table 24-J Wabash River Basin - Total Cost of Basin Plan..............24-28 Table 24-K Inspection of Completed Flood Control Projects............ 24-29 Table 24-L Flood Control Work Under Special Authorization............ 24-31 24-1 REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1985 Navigation - Locks and Dams 1. CONSTRUCTION OF LOCKS AND DAMS, OHIO RIVER For report on this improvement, see the heading under Ohio River. 2. GREEN AND BARREN RIVERS, KY. Location. Green River rises in Casey County, KY, flows northwesterly 370 miles, and empties into Ohio River about 8 miles above Evansville, IN. Barren River rises in Monroe County, KY, flows northwesterly 130 miles, and empties into Green River 1/2 mile above Lock 4 and 149.5 miles above mouth of Green River. Existing project. Six locks and dams on Green River and one on Barren River to give, with channel work in pools of dams, a navigable depth of 9 feet and width of 200 feet from Ohio River to mile 103 Green River, 3.2 miles upstream from Paradise, KY; a navigable depth of 5.5 feet from mile 103 Green River to Mammoth Cave, KY, mile 197.8 Green River, and from mouth of Barren River mile 149.5 Green River, to Bowling Green, KY, mile 30.1, Barren River. Fluctuations in stage vary considerably at different locks. At Lock 3, Green River, ordinary high stages are from 12 to 15 feet above pool level, and at Lock 1, Barren River, from 7 to 10 feet above pool. Maximum stages of record are 34 feet above normal pool stage at Lock 3, Green River, and 29 feet at Lock 1, Barren River, obtained during floods of 1937 and 1913, respectively. (See Table 24-B for authorizing legislation and Table 24-H for principal features of the locks and dams.) Local cooperation. Fully complied with. Terminal facilities. Coal handling facilities located on the Green River between miles 81.5 and 108.1 near South Carrollton, Rockport, Paradise and Rochester, Kentucky, are considered adequate for existing commerce. Operations during fiscal year. Consisted of operation and maintenance of Locks and Dams 1 and 2, Green River, and removal of shoals, snags, and slides as required to maintain adequate channel for existing traffic between mouth of Green River and Dam 3 at mile 108.5 Green River. Maintenance: Routine maintenance was performed. Locks and Dams 1 and 2, Green River, and Lock and Dam 1, Barren River, are in good condition. Lock and Dam 3, Green River, is in fair condition, and Lock 4, Green River, is in poor condition. Dam 4, Green River, failed May 24, 1965, when 120 feet washed out. Breach later widened, and repairs are deferred pending completion of survey report for navigation on Green River. Pool of Dam 1, Barren River, is maintained for local small boat use, but navigation through lock is suspended because of loss of lower pool. Operation activity was discontinued at Lock 4 Green River and Lock and Dam 1 Barren River in January 1974 and at Lock 3, Green River in September 1981. The residences and associated buildings and certain real estate at Lock 4 Green River and Lock and Dam 1 Barren River were disposed of in January 1975. Operation of Locks 5 and 6, Green River, was discontinued August 1951, as they were no longer used by river traffic. Controlling project depth in lower 103 miles of Green River is 9 feet; controlling depth from mile 103 to Bowling Green, KY, is 5.5 feet. Under permit issued by District Engineer on August 20, 1963, private interests dredged channel of Green River to extend 9-foot depth to coal loading teminal at mile 105.7. Channel of Green River above Lock 3 is no longer maintained. 3. KENTUCKY RIVER, KY Location. Formed by confluence of its North and Middle Forks about 4 miles east of Beattyville in east central Kentucky, (South Fork joins the main stream at that location), flows northwesterly and empties into Ohio River at Carrollton, KY, mile 545.8 below Pittsburgh, PA. Existing project. Provides for 14 locks and fixed dams to give, in connection with improvement of Ohio River, slack water navigation of 6 feet minimum depth from Ohio River to places on the three forks that are short distances above Beattyville, KY. Length of 6-foot-depth project on main stem of Kentucky River is 258.6 miles to confluence of Middle and North Forks. Cost of completed new work is $4,176,749. River frequently rises to 35 feet or higher. Extreme height at Lock 1 due to flood backwater from Ohio River is 60.3 feet, while extreme floods reach height of 47.6 feet at Lock 4, and 35.5 feet at Lock 14. At some intermediate locks extreme height of floods exceeds 40 feet. All flood heights refer to upper pool gages. Existing project was adopted by 1879 River and Harbor Act (H. Ex. Doc. 47, 45th Cong., 3d Sess., and Annual Report, 1879, p. 1398). Operation and care of locks and dams were included in project July 1, 1935, under provision of Permanent Appropriations Repeal Act of June 26, 1934. (See Table 24-H for principal features of the locks and dams.) On December 19, 1976 the lock operation schedules for commercial traffic and recreational craft on the Kentucky River System were reduced from continuous 24-hour yearround operation to two shift year-round operation of Locks 1 through 4, intermittent daily operation of Locks 5 through 10, and intermittent operation five days weekly of Locks 11 through 14. Since that time the hours for operation of Locks 5 through 14 have been reduced in several increments. On 1 October 1981 Locks 5 through 14 were closed to traffic and placed in caretaker status. Locks 5, 6, 8, 9, and 10 were in operation for 15 weekends during fiscal year 1982 and was again closed at the end of this period. Locks 5 through 14 were leased to the State of Kentucky on 21 May 1985. The State of Kentucky plans to operate these locks on weekends during the summer boating seasons. During the fiscal year Locks 1 through 4 continued a two shift, year-round operation. Licenses. Federal Regulatory Commission License No. 539, to Kentucky Utilities Co., at Dam 7, Kentucky River, Annual charge, $4,400; total collections through September 30, 1985, $266,805. 24-2 LOUISVILLE, KY. DISTRICT Terminal facilities. Facilities for bulk commodities and gasoline are considered adequate for existing traffic. Operations during fiscal year. Consisted of operation and maintenance of Locks and Dams 1 through 4 and removal of shoals, snags, and slides as required to maintain an adequate channel for existing traffic between mouth of river and Dam 5 at mile 82.2 Kentucky River. Maintenance: Routine maintenance was performed. Existing project was completed in 1917. Work accomplished was rehabilitation of the five old State locks and dams and construction of new Locks and Dams 6 to 14 inclusive. Repairs have been made to deteriorated locks and dams as required to keep locks in operation and maintain pool levels above dams except in extreme dry weather, when some pools fall below normal levels, details in Annual Reports for 1963, 1964 and 1965. Channel work was performed as required to provide for existing river traffic. Controlling navigable depth in length of river covered by existing project was 6 feet at end of fiscal year. 4. OPEN CHANNEL WORK, OHIO RIVER For report on this improvement, see this heading under Ohio River. 5. OTHER AUTHORIZED NAVIGATION PROJECTS See Table 24-C. 6. NAVIGATION WORK UNDER SPECIAL AUTHORIZATION None. Flood Control - Local Protection 7. DAYTON, KY Location. In Campbell County, KY, on left bank of Ohio River from mile 467.0 to mile 469.2 and across the river from Cincinnati, Ohio. (See U. S. Geological Survey map of Newport, KY.) Existing project. Provides for construction of 8,170 feet of levee, two pumping stations with gravity drainage structures, and major relocations of storm and sanitary sewers serving the community. Estimated cost of new work (1985) is $13,010,000 Federal and $2,043,000 non-Federal. Local cooperation. Section 3 of the Flood Control Act of June 22, 1936 applies. Formal assurances of cooperation were executed by City of Dayton, KY, on November 1969. City has acquired all rights-of-way for the project. Operations during fiscal year. Contract for stairs, walkways, overlook areas and landscaping was completed. Levee, floodwall, and pumping plants are physically complete and were transferred to the City of Dayton for operation and maintenance December 30, 1982. Project is about 99 percent complete overall and operational for flood control purposes. Remaining work involves settlement of a claim by one contractor. 8. EVANSVILLE, IN Location. In Vanderburgh County, IN, on right bank of Ohio River, 792.2 miles below Pittsburgh, PA. (See U.S. Geological Survey map of Evansville-South, IN.) Existing project. Construction of a system of levees and concrete floodwalls, together with pumping plants for disposal of interior drainage, at Evansville. For further details, see Annual Report for 1962, page 1127. Project will provide protection for City of Evansville, IN, against Ohio River floods equal to 1937 flood (maximum of record), with a 3-foot freeboard. Estimated total cost of new work (1985) is $56,940,500 Federal, including $7,900,000 (Oct 1977) for Howell Section, Unit 2, that is in "inactive" category, and $7,982,000 non-Federal, including $352,000 (Oct 1977) for the said Howell Section, Unit 2. Existing project selected for construction under general authorization for Ohio River Basin in 1937 Flood Control Act. Howell Section, Unit 2, was reclassified from the "active" category to the "inactive" category July 7, 1977 based on current studies that indicated this part of the project is not economically justified. Local cooperation. Section 3 of Flood Control Act of June 22, 1936, as amended, applies. Fully complied with for Howell Unit 1 and Knight Township sections. Assurances for Pigeon Creek Section, Unit 1, were executed February 11, 1963. Authorizations-of-entry for Pigeon Creek Section, Unit 2, Parts 1 and 2 have been furnished. Operations during fiscal year. Engineering and design studies continued. Plans and specifications for landscaping at Garvin Park were completed and construction contract of same was awarded. Plans and specifications for levee and floodwall Stringtown Road to U.S. Highway 41 advanced to about 35% completion. Contract for design of North 1st Avenue, Diamond Avenue and Stringtown Road pumping plants was awarded and advanced to about 35% completion. Plans and specifications for levee and floodwall U.S. Highway 41 to Southern Railroad and Power Service for 1st Avenue, Diamond Avenue and Stringtown Road were begun and advanced to about 35% and 50% completion, respectively. Contract for levee and floodwall Cedar Street to Stringtown Road remains at about 99% complete. Flood damages estimated at $13,000 were prevented during the 1985 flood season. Knight Township, Howell, Unit 1 and Pigeon Creek, Unit 1 Sections are complete. Howell Section, Unit 2, is in the "inactive" category. Construction of Pigeon Creek Section, Unit 2, was started in April 1974 and is about 43 percent complete. General Design Memorandum and Supplement on Pigeon Creek Unit 2, and Design Memorandum and plans and specifications for Delaware, Dresden and North 6th Avenue pumping plants are approved. Design Memorandum for North 1st Avenue, Diamond Avenue, and Stringtown Road pumping plants is complete. Project is about 56 percent complete overall. 24-3 REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1985 9. LEVEE UNIT NO. 5, WABASH RIVER, IN Location. In Gibson and Posey Counties, IN, on left bank of Wabash River, from 58 to 94.5 miles above mouth. Existing project. Provides for construction of 41.9 miles of earth levee, drainage structures, pumping plants, together with alterations to three railroad bridges crossing Wabash River. Project provides protection for 44,000 acres of farm land and towns of Lyle, Skelton, and Griffin, IN, against a flood equal to that expected on an average of 7 times in each 100-year period. Estimated total cost of new work (1985) is $8,396,500 of which $905,500 is non-Federal cost for lands and damages and road utility relocations. Project was authorized by Flood Control Acts of 1936 and 1946. Local cooperation. Section 3, Flood Control Acts of June 22, 1936, applies. Assurances were executed by Superintendent of Levee District on January 8, 1962. Completed portions of project (levees) were transferred to the Levee District for operation and maintenance October 15, 1969. Emerson Ditch pumping plant was transferred to the Levee District for operation and maintenance November 24, 1975. Operations during fiscal year. Construction contract for Coffee Bayou pumping plant was advanced to 99 percent completion. Flood damages estimated at $2,429,000 were prevented during the 1985 flood season. All sections of levee, Emerson Ditch pumping plant, and required alterations of the Penn Central Railroad, Southern Railroad, and Illinois Central Railroad are complete. Construction is in progress on the Coffee Bayou pumping plant. Project is about 99 percent complete overall. 10. MASON J. NIBLACK LEVEE, WABASH RIVER, IN Location. In Knox and Sullivan Counties, IN, on left bank of Wabash River, between miles 134.8 and 151.8 above mouth. Existing project. Construction of two sections of earth levee totaling 18 miles in length, three pumping plants for disposal of interior drainage, and other necessary appurtenances. Length of protection, including high ground between the two levee sections, is 18.9 miles long. Project protects 15,900 acres of agricultural land against a flood equal to that expected to occur 7 times in a 100-year period. Cost of the completed pumping plants was $2,782,905 all Federal cost and cost of the completed levee was $1,663,912 of which $109,200 was non-Federal cost and $1,554,712 was Federal cost. The levee project was authorized by the 1946 Flood Control Act; pumping facilities were authorized by the 1968 Flood Control Act. Local cooperation. Section 3 of the Flood Control Act of June 22, 1936, as amended, applies. Fully complied with for levees and pumping plants. Operations during fiscal year. Operation by local interests for flood control prevented damages estimated at $562,000 during 1985 flood season. Construction of levees complete and .transferred to Mason J. Niblack Levee District in January 1965 for operation and maintenance. Construction of the pumping plants and channel improvements complete and transferred to the local sponsor in May 1980. 11. MILL CREEK, OH Location. Proposed project is located along the 18-mile length of Mill Creek and three-fourths mile length of East Fork in Hamilton County, OH. Lower Mill Creek is in the commercial and industrial heart of the Cincinnati metropolitan area in the southwestern portion of the State. Existing project. Eighteen miles of channel improvement, 2 miles of levees, two pumping plants, modification of 29 bridges, and the addition of two pumping units at the present Mill Creek Barrier Dam, located near the Ohio River, are included in the project. Acquisition and development with appropriate landscaping of 620 acres along the creek will be provided for high-density urban oriented recreational use. Estimated cost of new work (1985) is $183,952,000, of which $40,377,000 is non-Federal. Local cooperation. Section 3, Flood Control Act of 1936 as amended, applies. In addition, local interests must provide without cost to the United States all modifications and relocations of buildings, utilities, street and foot bridges, sewers, and related and special facilities as necessary for construction of project; prevent encroachment on improved channels and on ponding areas which would impair capacities; at least annually inform interests affected as to degree of protection afforded by project, and provide guidance and leadership in preventing unwise and uneconomical development of flood plain areas by encouraging prudent use of floodproofing, land regulation planning, or other flood plain management techniques to reduce flood losses. Further, with respect to the recreational aspects of the project, local interests are required to furnish assurances that they will, if necessary, pay or contribute in kind, a portion of the cost of recreational facilities which, when added to the cost of recreation land, would amount to at least 50 percent of the total first cost of the recreation land and recreational facilities, and assure access to the recreation facilities to all on equal terms. An assurance agreement covering local cooperation requirements for the project consistent with Section 221 of the 1970 Flood Control Act and the Uniform Relocation Assistance and Real Property Acquisition Policies Act of 1970 was executed by the Millcreek Valley Conservancy District February 6, 1975, and for the Secretary of the Army March 28, 1975. A recreation cost sharing contract was executed by the Conservancy District February 25, 1975, and approved by the Secretary of the Army May 28, 1975. 24-4 LOUISVILLE, KY. DISTRICT Operations during fiscal year. Engineering studies continued. Construction contract for channel Section 2 was advanced to 73 percent completion. Flood damages estimated at $816,000 were prevented during the 1985 flood season. Design Memoranda, Hydrology & Hydraulics, Concrete Aggregate and Stone Protection Sources, and Railroad Relocations, General Design Memoranda, Phase I and Phase II, Design of Channel - Sections 5 and 7 are complete. Construction of channel and levee- Sections 3 and 7A, Phase I, is complete. Project is about 19 percent complete overall. 12. SOUTHWESTERN JEFFERSON COUNTY, KY Location. In Jefferson County, KY, on left bank of Ohio River from mile 616 to 628.6. Existing project. Provides for the construction of 68,500 feet of levee, 1,550 feet of concrete wall, four pumping plants, and other necessary appurtenances. Project will provide protection fo 24,100 acres against Ohio River floods equal to 1937 flood of record with 3-foot freeboard. Estimated cost of new work (1985) is $71,328,000, of which $61,411,000 is Federal, and $9,917,000 is non-Federal. Project was authorized under Flood Control Act of August 1968. Recreation as a project purpose has been deferred until such time as a water quality problem on Pond Creek is corrected. Local cooperation. Section 3 Flood Control Act of 1936 as amended applies. In addition, local interests must agree to administer project land and water areas for recreation and fish and wildlife enhancement; and to pay, contribute in kind or repay (which may be through user fees) with interest, one-half of the separable first cost of the project allocated to recreation and fish and wildlife enhancement; and bear all costs of operation, maintenance and replacement of lands and facilities for recreation and fish and wildlife enhancement. Jefferson County Fiscal Court expressed intent to fulfill requirement by resolution dated April 4, 1967. Formal assurances of local cooperation for the flood protection portion of the project was executed by resolution of Jefferson County Fiscal Court, adopted September 17, 1971, and assurances for the recreation portion of the project were executed by similar resolution, adopted September 14, 1971. Authorization-of-entry for levee and floodwall sections 1, 2, 3, 4, 4A and 5 have been furnished. Operations during fiscal year. Engineering studies continued. Two contracts for construction of railroad closure at levee Section 4 and for construction of levee and floodwall Section 4 were both advanced to 99 percent complete. Contract for Pond Creek Pumps and Motors, awarded in May 1985, was advanced to one percent completion. Contract for Levee Section 5 and Pond Creek Pumping Station was awarded in September 1985. Engineering studies are about 98 percent complete. Construction of levee and floodwall Sections 1, 2, 3 and 4A; electric service for gatewells; Riverport and Upper and Lower Mill Creek pumping plants; rehabilitation of pump stations; and relocation of Texas Gas pipeline are complete. Project is 59 percent complete overall. Flood Control - Reservoirs 13. BARREN RIVER LAKE, KY Location. Dam is on Barren River, 79.5 miles above its confluence with Green River and 10 miles northeast of Scottsville, KY. At flood control pool reservoir extends upstream about 40 miles in Barren and Allen Counties, KY. (See U.S. Geological Survey map of Lucas, KY.) Existing project. A reservoir for flood control and allied purposes. Dam is rolled earth and rockfill, 146 feet high and 3,970 feet long, with gate-controlled outlet works and uncontrolled open-cut spillway. Total storage capacity is 815,200 acre-feet (768,000 for flood control and 46,600 for water supply storage). For further details, see page 1125 of Annual Report for 1962. Cost of the completed project is $27,479,717 including $2,335,055 Federal funds and $108,418 non-Federal funds for construction of recreation facilities under the completed projects program. Project was authorized by Flood Control Act of 1938. Local cooperation. None required by authorizing act. Under provision of Water Supply Act of 1958, contract with City of Glasgow for water supply storage was approved by Secretary of Army on October 4, 1965. Terms require City to pay $23,433, which is project cost allocated to water storage plus capitalized prepayment of proportionate share of operation, maintenance, and major replacement costs. A contract, with the Commonwealth of Kentucky for development of additional campsites, shoreline protection and breakwater extension at Barren River Lake State Park under the cost-sharing category of the completed projects program was approved by the Secretary of the Army November 4, 1977. Operations during fiscal year. New work: None. Maintenance: Routine maintenance was performed. Operation for flood control during the 1985 flood season prevented damages of $23,000. Construction started in March 1960 and all major construction and relocation items were completed in October 1964. Project was placed in operation in March 1964. Land acquisition is complete. 14. BROOKVILLE LAKE, IN Location. Damsite is on East Fork of Whitewater River, 2.4 miles above confluence with West Fork, and about 1-1/2 miles north of Brookville, Indiana. The reservoir lies in Franklin and Union Counties, Indiana. (See U.S. Geological Survey map of Brookville, IN.) Existing project. A reservoir for flood control and allied purposes. Dam is earthfill, 182 feet high and 3,004 feet long, with gate-controlled outlet works, and uncontrolled open spillway. Total storage capacity is 359,600 acre-feet (214,700 for flood control, 89,300 for water supply, and 35,500 for conservation). A minimum pool of 20,100 acre-feet is maintained. Estimated cost of new work (1985) is $45,483,162 of which $37,904,424 is Federal cost and $7,578,738 is non-Federal contribution 24-5 REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1985 for water supply storage. Project was authorized by 1938 Flood Control Act. Local cooperation. None required by authorizing act. Contract with State of Indiana for water supply storage under provisions of Water Supply Act of 1958 was approved by Secretary of Army, August 5, 1965. Under terms of contract, State paid initial costs allocated to water supply feature of project plus capitalized prepayment of proportionate share of operation and maintenance costs. Operation during fiscal year. New work: None. Maintenance: Installation of hydropower unit was completed but is not in operation pending finalization of contract with Southeastern Power Administration for purchase of surplus power. Routine maintenance was performed. Construction was started in November 1965 and project was placed in operation January 1974. Construction and land acquisition are complete. 15. BUCKHORN LAKE, KY Location. Dam is on Middle Fork of Kentucky River, 43.4 miles above mouth, and 0.5 mile upstream from Buckhorn, Perry County, KY. Reservoir extends upstream about 34 miles and lies in Leslie and Perry Counties, Kentucky. (See U.S. Geological Survey map of Buckhorn, KY.) Existing project. A reservoir for flood control and recreation. Dam is earth and rockfill type, with gate controlled outlet works. Total storage capacity is 168,000 acre-feet, of which 157,600 is for flood control. For further details, see page 1120 of Annual Report for 1962. Cost of completed new work is $11,766,206 including $386,707 for construction of recreation facilities under the completed projects program. Existing project was authorized by general authorization for Ohio River Basin in 1938 Flood Control Act. Local cooperation. Department of Parks of the Commonwealth of Kentucky has undertaken management of lands and recreational facilities in accordance with license granted by Secretary of the Army on June 29, 1962. Operations during fiscal year. New work: None. Maintenance: Routine maintenance was performed. Construction started in September 1956 and project was placed in operation in August 1960. All construction and land acquisition is complete. 16. CAESAR CREEK LAKE, OH Location. Damsite is on Caesar Creek, about 3.0 miles above its confluence with Little Miami River, in Warren County, OH, about 3.5 miles southeast of Waynesville, OH, and 10.5 miles northeast of Lebanon, OH. Reservoir lies in Warren, Clinton, and Green Counties, OH. (See U.S. Geological Survey map of Oregonia, OH.) Existing project. Provides for construction of a reservoir for flood control and allied purposes. It includes an earth and rockfill dam, four saddle dams, outlet works and an uncontrolled saddle spillway. Total storage capacity of reservoir is 242,200 acre-feet, of which 148,500 acrefeet is reserved for flood control storage. Estimated cost of new work (1985) is $64,781,000 including $5,037,000 non-Federal reimbursement for water supply storage. Existing project was authorized by general authorization for Ohio River Basin in 1983 Flood Control Act. Local cooperation. None required. However, the State of Ohio requested inclusion in the project of storage for future municipal and industrial water supply uses. Contract with State of Ohio for water supply storage under provisions of Water Supply Act of 1958, as amended, was approved by Secretary of the Army, May 20, 1970. Under terms of contract, State will reimburse the Federal Government for costs allocated to water supply storage over a period not to exceed 50 years after use of this storage is initiated plus estimated annual amount for cost of operation, maintenance and major capital replacements required for the water supply facilities. Operations during fiscal year. New work: Engineering and design studies continued. Final condemnation action for land acquisition on one tract continued. Contract for sewer connection charge with Warren County as modified to include enlargement of waste water treatment plant at Waynesville was advanced to completion. Contract for Warren County water connection charge was advanced to completion. Contract for remedial work on the control tower was advanced to completion. Contract for Tailwater Conversion was awarded in September 1985. Maintenance: Routine maintenance was performed. Flood damages estimated at $4,423,000 were prevented during the 1985 flood season. Construction was started in January 1968 and the project was placed in operation January 1978. Land acquisition is commplete except for outstanding condemnation action on one real estate tract. All relocation and construction features are complete except final utility connections to the recreation facilities, remedial work on the control tower and construction of a lift station to connect chemical comfort stations to regional system. Project is about 97 percent complete overall. 17. CAGLES MILL LAKE, IN Location. Dam is on Mill Creek, 2.8 miles above its confluence with Eel River, in Putnam County, IN, and about 25 miles east of Terre Haute, IN. Reservoir extends upstream about 11 miles and is in Putnam and Owen Counties, IN. (See U.S. Geological Survey map of Poland, IN.) Existing project. A reservoir for flood control and recreation. Dam is earth and rockfill embankment. Total storage capacity is 228,100 acre-feet, of which 201,000 acre-feet are for flood control. For details see Annual Report for 1962, page 1136. Estimated cost of new work (1985) is $4,369,772 including $155,189 Federal funds and $106,813 non-Federal funds for construction of recreation facilities under the completed projects program. Existing project was selected for construction under general authorization for Ohio River Basin in 1938 Flood Control Act. Local cooperation. None required. State of Indiana 24-6 LOUISVILLE, KY. DISTRICT has undertaken development and management of recreation facilities for use of the public in reservoir area in accordance with license granted by Secretary of the Army on January 17, 1952. A contract with the Indiana Department of Natural Resources for expanding the boat ramp and parking area at Site 3, Lieber State Park, under the cost sharing category of the completed projects program was signed by the State of Indiana on August 26, 1981 and approved by the Deputy Chief of Engineers on March 26, 1982. Operations during fiscal year. New Work: Construction contract for expanding the boat ramp and parking area at Site 3, Lieber State Park, awarded in November 1983, was completed under the cost sharing category of the completed projects program. Maintenance: Contracts were awarded and completed for erection of new radio tower and resurfacing roads and parking areas. Routine maintenance was performed. Operation for flood control during the 1985 flood season prevented damages of $3,497,000. Construction started in July 1948 and completed in June 1953. 18. CARR FORK LAKE, KY Location. Damsite is 8.8 miles above mouth of Carr Fork, a tributary of North Fork of Kentucky River, 16 miles upstream from Hazard, KY. The reservoir lies entirely within Knott County. (See U.S. Geological Survey maps of Carrie and Vicco, KY.) Existing project. Provides for construction of a reservoir for flood control and allied purposes. Dam is rock and earth fill with impervious core, 720 feet long and 130 feet high, with uncontrolled open cut spillway through left abutment. Outlet works has two control gates and 8-foot diameter conduit to stilling basin. Total storage capacity is 47,700 acre-feet (31,600 for flood control and 4,300 for water quality control). A higher level seasonal pool for recreation is provided. Estimated Federal cost of new work (1985) is $50,854,826 including $76,724 for recreation facilities under the completed projects program. Project was authorized by the 1962 Flood Control Act. Local cooperation. None required for reservoir project. Division of Flood Control and Water Usage of Commonwealth of Kentucky gave assurance that encroachments on downstream channel capacity will be prevented. Operations during fiscal year. New work: Real estate administrative action required for condemnation of remaining tracts was continued. Maintenance: Contract was awarded for modification of hydraulic system. Routine maintenance was performed. Operation for flood control during the 1985 flood season prevented damages of $15,000. Condition at end of fiscal year. Project was placed in operation January 1976. Construction started in January 1966 is complete. All land required for the project has been acquired; however, a number of condemnation actions remain unsettled. 19. CAVE RUN LAKE, KY Location. Damsite is on Licking River, about 4 miles upstream from U. S. Highway 60 near Farmers, KY, and 7 miles southwest of Morehead, KY. Reservoir will be in Rowan, Bath, Morgan, and Menifee Counties, KY. (See U.S. Geological Survey maps of Salt Lick and Morehead, KY.) Existing project. Plan provides for construction of a reservoir for flood control and allied purposes. Dam is rolled earthfill, with gate controlled outlet works and uncontrolled open spillway. Total storage capacity is 614,700 acre-feet (438,500 for flood control and 28,300 for water quality control). Estimated Federal cost of new work (1985) is $114,826,300 of which $35,213,000 is U. S. Forest Service cost. Project was authorized by Flood Control Acts of June 22, 1936 and June 28, 1938. Local cooperation. None required. Operations during fiscal year. New work: Engineering and design studies continued. Real estate administrative action required for acquisition of remaining tracts was continued. Contract for Zilpo recreation buildings, part I (4 bathhouses) was advanced to 99 percent completion. Contract for tailwater comfort station conversion was awarded in August 1985 and advanced to 57 percent completion. Maintenance: Routine maintenance was performed. Operation for flood control during the 1985 flood season prevented damages of $1,402,000. Project has been in operation since February 1974. Construction was started in June 1965 and is about 92 percent complete overall. Land acquisition is complete except for outstanding condemnation actions. All relocation and construction features are complete except recreation facilities. 20. CECIL M. HARDEN LAKE, IN Location. Dam is on Raccoon Creek, 32.4 miles above its confluence with Wabash River, and 25 miles northeast of Terre Haute, IN. At flood control pool, reservoir extends upstream about 15 miles in Parke and Putnam Counties, Indiana. (See U. S. Geological Survey Map of Mansfield, IN.) Existing project. A rolled earth dam and reservoir, for flood control and allied purposes. Total storage capacity is 132,800 acre-feet of which 116,600 acre-feet are for flood control. For details, see Annual Report for 1962, page 1132. Cost of completed new work is $6,987,807 made up of $6,260,134 for the initial project and $373,678 Federal cost and $353,995 non-Federal contribution in kind for recreation facilities under the completed projects program. Project was selected for construction under general authorization for Ohio River Basin in 1938 Flood Control Act. Project name was changed from Mansfield Lake to Cecil M. Harden Lake by Public Law 93-521, December 14, 1974. Local cooperation. State of Indiana has undertaken management of lands and recreational facilities in accordance with license granted by Secretary of the Army 24-7 REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1985 on April 19, 1961. A contract with the Indiana Department of Natural Resources, approved by the Secretary of the Army in May 1974, provided for that agency to design and construct certain additional recreation facilities at Cecil M. Harden, Huntington, Mississinewa, Monroe and Salamonie Lakes under the cost sharing category of the completed projects program. Operations during fiscal year. New work: None. Maintenance: Contract was awarded for replacement of control tower roof. Routine maintenance was performed. Flood damages of $13,307,000 were prevented during the 1985 flood season. Construction started in October 1956 and all major items of work were completed December 1961. Land acquisition is complete. Project has been in operation since August 1960. Cost shared recreation facilities constructed by the State of Indiana under the completed projects program are completed. 21. CLARENCE J. BROWN DAM & RESERVOIR, OH Location. Damsite is just east of Springfield, Clark County, OH, at mile 7.3 of Buck Creek, a tributary of Mad River. (See U. S. Geological Survey maps of New Moorefield and Springfield, OH.) Existing project. A reservoir for flood control and allied purposes. It includes an earthfill dam, 6,620 feet long and 72 feet high, with gated outlet works and open cut spillway with concrete chute through right abutment. Total storage capacity of reservoir is 63,700 acre-feet (32,900 for flood control and 20,800 for water quality control). Federal cost of completed project is $22,083,660. Project was authorized by 1962 Flood Control Act. Project name was changed from Buck Creek Dam and Reservoir to Clarence J. Brown Dam and Reservoir by Public Law 90-46, July 4, 1967. Local cooperation. Assurances from City of Springfield, Springfield Conservancy District, and Clark County, Ohio, covering protection against detrimental channel encroachment below dam to mouth of Buck Creek, were accepted March 5, 1964. Operations during fiscal year. New work: None. Maintenance: Routine maintenance was performed. Construction started in September 1966. Land acquisition and all major project features were completed in November 1973. The project was placed in operation in January 1974. 22. GREEN RIVER LAKE, KY Location. Damsite is 305.7 miles above mouth of Green River in Taylor County, KY, about 8 miles south of Campbellsville. Reservoir lies in Taylor and Adair Counties. (See U. S. Geological Survey map of Cane Valley, KY.) Existing project. A reservoir for flood control and allied purposes. Dam is earth and rock-fill, 141 feet high and 2,350 feet long. Outlet works is slide gate-controlled and spillway open and uncontrolled. Total storage capacity is 723,200 acre-feet (560,600 for flood control and 64,500 for low-flow augmentation). Cost of completed new work is $33,606,061, including $317,145 Federal funds and $183,732 non-Federal funds for construction of recreation facilities under the completed projects program. Existing project was authorized under general authorization for Ohio River Basin in 1938 Flood Control Act. Local cooperation. None required by authorizing act. Taylor County, by lease approved by Secretary of Army February 15,1968, undertook operation and maintenance of Smith Ridge public access area. In May 1980, the lease was amended to turn back responsibility for maintenance, and operation of 99 percent of the site to the Corps, with the County retaining responsibility for the marina area. Under provision of Water Supply Act of 1958, contract with City of Campbellsville for water supply storage was approved by Secretary of Army April 23, 1969. Terms require city to repay, with interest and annual charges for operation, maintenance and major replacement, the investment cost of $85,765 allocated to its water supply storage space. Total payments received through fiscal year 1984 was $21,504. The Department of Parks of the Commonwealth of Kentucky, by lease approved by Secretary of Army, October 4, 1971, has undertaken the management of the Lone Valley public access area. Operations during fiscal year. New work: None. Maintenance: Contract for construction of new office building was awarded in December 1984; Contracts for installation of new boiler and roof replacement of visitor's center and shop were awarded in August 1985. Routine maintenance was performed. Operation for flood control prevented damages estimated at $358,000 during the 1985 flood season. Construction began in August 1965 and all major construction and relocation items were completed in 1972. Project has been in operation since February 1969. Project including all land acquisition complete in 1973. Construction of sanitary dump station for boats at Dam Site in conformance with EPA and State standards and rehabilitation of sewage treatment facilities, washhouses and restrooms at Smith Ridge site is complete. 23. HUNTINGTON LAKE, IN Location. Damsite is on Wabash River, about 2 miles from Huntington, IN, and 411.4 miles above mouth. Reservoir is in Huntington and Wells Counties, IN. (See U. S. Geological Survey maps of Majenica and Mt. Etna, IN.) Existing project. A reservoir for flood control and recreation. Dam consiste of a rolled earth embankment 4,700 feet long and 89 feet high, a concrete spillway and outlet section 155 feet long, and a concrete gravity section 310 feet long. Spillway is controlled by three gates, and outlet works by six sluices. Project also provides local flood protection for Markle, IN. Total storage capacity of reservoir is 153,100 acre-feet, of which 149,000 acre-feet is reserved for flood control storage. Estimated cost for new work (1985) is $19,777,863 made up of $19,273,252 Federal cost for the initial project and $193,903 non- Federal contributed funds for low flow augmentation 24-8 LOUISVILLE, KY. DISTRICT storage, and $155,354 Federal cost and $155,354 non- Federal contribution in kind for recreation facilities under the completed projects program. Project was authorized by Flood Control Act of 1958. Local cooperation. Local interests must contribute in cash an amount equal to one percent of project first cost. State of Indiana has met this obligation. Contract with the Indiana Department of Natural Resources, approved by the Secretary of the Army May 17, 1974, provided for that agency to design and construct certain additional recreational facilities at Cecil M. Harden, Huntington, Mississinewa, Monroe and Salamonie Lakes under the cost shared category of the completed projects program. Operations during fiscal year. New work: None. Maintenance: Routine maintenance was performed. Operation for flood control prevented damages estimated at $5,320,000 during the 1985 flood control season. Land acquisition and all major construction complete. Project was placed in operation January 9, 1969. Cost shared recreation facilities constructed by the State of Indiana under the completed projects program are complete. 24. MISSISSINEWA LAKE, IN Location. Damsite is 7.1 miles above mouth of Mississinewa River, which flows into Wabash River about 2 miles upstream from Peru, IN. At flood control pool level, reservoir extends upstream about 28 miles, in Wabash, Grant, and Miami Counties, IN. (See U.S. Geological Survey map of Peoria, IN.) Existing project. Provides for construction of a reservoir for flood control and allied purposes. It includes an earthfill dam 137 feet high and 8,100 feet long, gatecontrolled outlet works, and an uncontrolled open spillway through right abutment. Total storage capacity of reservoir is 368,400 acre-feet, of which 345,100 acrefeet are reserved for flood control storage. Estimated project cost for new work (1985) is $24,596,109 made up of $23,578,145 Federal cost for the initial project and $239,200 non-Federal contributed funds for low flow augmentation storage and $389,392 Federal cost and $389,382 non-Federal contribution in kind for recreation facilities under the completed projects program. Project was authorized by the Flood Control Act of 1958. Local cooperation. Local interests must contribute in cash an amount equal to 1 percent of project first cost. State of Indiana assumed this obligation. A contract with the Indiana Department of Natural Resources, approved by the Secretary of the Army in May 1974, provided for that agency to design and construct certain additional recreation facilities at Cecil M. Harden, Huntington, Mississinewa, Monroe and Salamonie Lakes under the cost sharing category of the completed projects program. Operations during fiscal year. New work: None Maintenance: Routine maintenance was performed. Operation for flood control prevented damages of $20,120,000 during 1985 flood season. Construction and land acquisition is complete. Project was placed in operation in May 1968. Cost shared recreation facilities cconstructed by the State of Indiana under the completed projects program are complete. 25. MONROE LAKE, IN Location. Dam is on Salt Creek, a tributary of White River, 25.9 miles above mouth, and 2 miles each of Harrodsburg, Monroe County, IN. At flood control pool level, reservoir will extend upstream 44 miles in Monroe, Brown, and Jackson Counties. (See U.S. Geological Survey map of Clear Creek, IN.) Existing project. A reservoir for flood control and allied purposes. Dam is earth core and rock shell, with gate-controlled outlet works and uncontrolled open spillway. Total storage capacity is 441,000 acre-feet (258,800 for flood control and 159,900 for low flow augmentation.) Cost of completed new work is $16,569,589 made up of $7,032,484 Federal cost for the initial project and $7,797,604 non-Federal contributed funds for low-flow regulation storage and $870,343 Federal cost and $869,158 non-Federal contribution in kind for recreation facilities under the completed projects program. Project was authorized by 1958 Flood Control Act, modifying comprehensive plan for Ohio River Basin. Local cooperation. Section 3, 1944 Flood Control Act applies. Local interests must contribute 54.1 percent of project cost, this being the proportion allocated to low-flow regulation feature, plus a capitalized amount representing that part of average annual maintenance and operation cost allocated to low-flow regulation. State of Indiana assumed this cost sharing obligation. A contract with the Indiana Department of Natural Resources, approved by the Secretary of the Army in May 1974, provided for that agency to design and construct certain additional recreation facilities at Cecil M. Harden, Huntington, Mississinewa, Monroe and Salamonie Lakes under the cost sharing category of the completed projects program. Operations during fiscal year. New work: None. Maintenance: Routine maintenance was performed. Operation for flood control prevented damages of $1,005,000 during 1985 flood season. Project is complete and was placed in operation in February 1965. Cost shared recreation facilities constructed by the State of Indiana under the completed projects program are complete. 26. NOLXN LAKE, KY Location. Dam is on Nolin River 7.8 miles above its confluence with Green River, about 70 air miles southwest of Louisville, KY. Reservoir extends upstream about 57 miles and is in Edmonson, Grayson, Hart, and Hardin Counties, KY. (See U.S. Geological Survey maps of Nolin Reservoir and Dickeys Mill, KY.) Existing project. A reservoir for flood control and allied purposes. Dam is rockfill-earth core type with gatecontrolled outlet works, and uncontrolled open spillway. Total storage capacity is 609,400 acce-feet, of which 545,600 acre-feet is for flood control. For further details 24-9 REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1985 of project see Annual Report for 1962, page 1124. Estimated Federal cost of new work (1985) is $17,193,372 including $2,596,308 for construction of recreation facilities. Project was selected for construction under general authorization for Ohio River Basin in 1938 Flood Control Act. Local cooperation. None required for authorized project. State of Kentucky contributed $18,195 for increased width of dam for public road. Operations during fiscal year. New work: None. Maintenance: Rountine maintenance was performed. Operation for flood control during the 1985 flood season prevented damages estimated at $682,000. Construction started in January 1959. Project was completed and placed in operation in March 1963. 27. OHIO RIVER BASIN (Louisville District) Location. Works covered by this project are a series of levees, floodwalls, channel improvements, and reservoirs in Ohio River Basin within Louisville District. Existing project. Individual projects considered in comprehensive plan within the Louisville District. (See Table 24-B for authorizing leglsiation, and Table 24-I for cost and listing of projects in the basin plan.) Operations during fiscal year. No costs were incurred except for these projects for which individual reports are given. 28. PATOKA LAKE, IN Location. Damsite is in Dubois County, IN, 118.3 miles above mouth of Patoka River, and 50 miles westnorthwest of New Albany, IN. Reservoir extends into Dubois, Orange and Crawford Counties. (See Geological Survey map of Cuzco, IN.) Existing project. Reservoir for flood control and allied purposes. Dam is earth and rock fill, 1,550 feet long and 85 feet high, with gate-controlled outlet works and uncontrolled open spillway. Total storage capacity is 301,600 acre-feet (121,000 for flood control and 167,500 for water supply and water quality control). Estimated cost of new work (1985) is $78,417,700 of which $1,361,200 is Federal cost for emergency remedial measures and to clear and snag the Patoka River downstream of Patoka Lake, which work was directed by Congress in 1981; $51,507,800 is Federal cost for other construction, and $25,548,700 is non-Federal contribution for water supply storage and recreation facilities. Project was authorized by 1965 Flood Control Act, and emergency measures and snagging and clearing the Patoka River downstream of Patoka Lake to insure effective operation of the project for flood control was directed by 1981 Appropriation Act for Energy and Water Development. Local cooperation. Local interests are required to reimburse the Federal Government for costs allocated to water supply storage over a period not to exceed 50 years after use of this storage is initiated, presently estimated at 29.316 percent of the joint-use facilities cost, exclusive of interests, plus $287,000 for the cost of operating and maintaining water supply storage for a period of 50 years, plus $42,000 for the cost of major capital replacements required for water supply storage space for a period of 50 years. Local interests are also required to pay, contribute in kind, or repay (which may be through user fees) with interest, one-half of the separable first cost of the project allocated to recreation. Present laws of the State of Indiana require that agency to make cash contributions during construction of the project. Local interests must also agree to prevent encroachments on channel of Patoka River from dam to mouth, and to pay allocated initial and annual maintenance and operation costs for water supply storage. Formal assurances of local cooperation, executed by the Indiana Natural Resources Commission, were accepted August 27, 1970. Contracts with State of Indiana for water supply and recreation were approved by the Secretary of the Army November 2, 1970. Operations during fiscal year. New work: Engineering studies and land acquisition continued. Contract for repairs to Highways 145 and 164 was completed. Contract for resurfacing Highway D-1 and dam access road, awarded in May 1984, was completed. Contract for construction of Jackson Site Access Road, awarded in November 1983, was advanced to 55 percent completion. Maintenance: Routine maintenance was performed. Operation for flood control during the 1985 flood season prevented damage estimated at $2,037,000. Construction was started in July 1972. Engineering studies are about 99 percent complete. Land acquisition is about 99 percent complete. Construction of all relocations are complete, except minor repairs to a relocated road. All other major features with the exception of recreation facilities are also complete. Permanent impoundment was started in February 1978 and the project was placed in operation about August 1980. The project is about 99 percent complete overall. 29. ROUGH RIVER LAKE AND CHANNEL IMPROVEMENT, KY Location. Dam is on Rough River, 89.3 miles above its confluence with Green River 160.3 miles above Ohio River, and about 60 miles southwest of Louisville, KY. Reservoir extends upstream about 30 miles and is in Breckinridge, Hardin, and Grayson Counties, KY. Channel improvement work is on Rough River, Barnett Creek, and West Fork of Barnett Creek. (See U.S. Geological Survey maps of McDaniels and Falls of Rough, KY.) Existing project. Reservoir is for flood control and allied purposes. Dam is rolled earthfill type, with gatecontrolled outlet works. Storage capacity is 334,380 acrefeet, of which 314,210 acre-feet is for flood control. Project also includes channel clearing of lower Rough River, and channel improvement on Barnett Creek, a tributary of Rough River. For further details see page 1126 of Annual Report for 1962. Cost of completed new work is $10,643,001 including $890,008 Federal funds and $22,612 non-Federal funds for construction of recreation facilities under the completed projects program. Existing project was selected for construction under general authorization for Ohio River Basin in 1938 Flood Control Act. Modification of previously approved plan to in- 24-10 LOUISVILLE, KY. DISTRICT clude channel improvement items was authorized by the 1944 Flood Control Act. Local cooperation. None required for construction of reservoir unit. Provisions of Section 3, Flood Control Act of 1936, are applicable to channel improvements. Assurances were obtained from Ohio County for channel improvement. Department of Parks, Commonwealth of Kentucky, has undertaken management of certain lands and recreation facilities in accordance with license granted by Secretary of the Army on August 18, 1961. A contract with the Commonwealth of Kentucky to improve and pave road at the Below Dam Area - State Park under the cost sharing category of the completed projects program was approved by the Secretary of the Army November 4, 1977. Operations during fiscal year. New work: None. Maintenance: Routine maintenance was performed. Operation for flood control during the 1985 flood season prevented damages estimated at $851,000. Construction started in November 1955 and reservoir was placed in operation in June 1959. Land acquisition and all major items of construction and relocation are complete. 30. SALAMONIE LAKE, IN Location. Damsite is 3.1 miles above mouth of Salamonie River which enters Wabash River about 6 miles upstream from Wabash, IN. Reservoir extends upstream about 27 miles at flood control pool and lies in Wabash and Huntington Counties, IN. (See U. S. Geological Survey maps of Lagro and Majenica, IN.) Existing project. Provides for construction of a reservoir for flood control and allied purposes. It includes an earthfill dam with a maximum height of 133 feet and and length of 6,100 feet, gate-controlled outlet works with a 16-foot diameter conduit and an uncontrolled open spillway through right abutment. Total storage capacity of reservoir is 263,600 acre-feet, of which 250,500 acrefeet is for flood control storage. Estimated project cost for new work (1985) is $17,046,151 made up of $16,244,356 Federal cost for the initial project and $170,697 non- Federal contributed funds for low-flow augmentation storage and $315,549 Federal cost and $315,549 non- Federal contribution in kind for recreation facilities under the completed projects program. Project was authorized by Flood Control Act of 1958. Local cooperation. Local interests must contribute in cash an amount equal to one percent of project first cost. State of Indiana assumed this obligation. A contract with the Indiana Department of Natural Resources, approved by the Secretary of the Army in May 1974, provided for that agency to design and construct certain additional recreation facilities at Cecil M. Harden, Huntington, Mississinewa, Monroe, and Salamonie Lakes under the cost sharing category of the completed projects program. Operations during fiscal year. New work: None. Maintenance: Routine maintenance was performed. During the 1985 flood season, operation for flood control prevented damages of $12,031,000. Land acquisition and all major construction and relocation contracts are complete. Reservoir was placed in operation in spring 1967. Cost shared recreation facilities constructed by the State of Indiana under the completed projects program are complete. 31. TAYLORSVILLE LAKE, KY Location. Damsite is in Spencer County, KY, 60.0 miles above the confluence of Salt River and Ohio River, 4 river miles above Taylorsville and 36.9 river miles above Shepherdsville, KY. (See U. S. Geological Survey map of Taylorsville, KY.) Existing project. A reservoir for flood control and allied purposes. Dam will be an earth and rock fill structure, 164 feet high and 1,280 feet long. Outlet works will be slide gate controlled and spillway will be uncontrolled open cut. Total storage capacity will be 291,670 acre-feet (211,230 for flood control, winter months), and 52,245 for water quality and fish and wildlife. Estimated cost of new work (1985) is $119,262,000 made up of $92,225,000 Federal cost for the initial project and $16,025,000 non- Federal contributed funds for initial recreation facilities and $5,506,000 Federal cost and $5,506,000 non-Federal contributed funds for recreation facilities under the completed projects program. Project was authorized by 1966 Flood Control Act. Local cooperation. Local interests must agree to administer project land and water areas for recreation; pay, contribute in kind, or repay (which may be through user fees) with interest one-half of the separable first costs of the project allocated to recreation; bear all costs of operation, maintenance, and replacement of recreation lands and facilities. Local interests must also agree to prevent encroachments on flow-carrying capacities of stream channels below the reservoir to the extent needed to provide reasonably effective reservoir operation. Commonwealth of Kentucky has indicated intent to fulfill requirements for recreation cost sharing and has assumed responsibility for channel encroachments and pollution control. The Commonwealth furnished assurance agreements covering prevention of encroachment on capacity of stream channels in April and May 1973 and executed the recreation cost sharing contract in April 1973. On April 2, 1980 the U. S. District Court for the Western District of Kentucky ruled that the 1973 recreation cost sharing contract between the Commonwealth and the United States that provded for repayment after completion was invalid under the Kentucky Constitution which prohibits one General Assembly from obligating future appropriations that would be binding on a subsequent legislature. In response to the Court's ruling, the Commonwealth and the United States entered into a new contract providing for cash contributions. Contract was approved by the Secretary of the Army June 11, 1980. The contract was found to be valid and enforceable by the Court July 14, 1980. Operations during fiscal year. New work: Engineering and design studies and land acquisition continued. Contract for Ashes Creek, Possum Ridge and Chowning Lane, Phase II recreation facilities, two road relocation contracts for Anderson County road, Site A-2, and Nelson- 24-11 REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1985 Anderson counties road, Site NA-1, and Kentucky Highway 44, Site K-1, and one paving contract for Chowning Lane and VanBuren recreation roads and parking areas and Spencer County road, Site 3-A were completed. Contract for final paving of relocated state highways advanced to 4 percent completion. During the 1985 flood season operation for flood control prevented damages of $506,000. Engineering and design studies are about 88 percent complete and land acquisition is about 96 percent complete. Construction was started in June 1974. All major construction items are complete except utility relocations, final paving of state highways and recreation facilities. The dam gates were closed in January 1983 for permanent impoundment. Dedication ceremony was May 28, 1983. The project is about 75 percent complete overall. 32. WABASH RIVER BASIN Location. Works covered by this project are located in the Wabash River Basin, a drainage area of 33,100 square miles, covering parts of Indiana, Illinois and Ohio. Existing project. One local protection project and five reservoir projects were authorized for this basin plan. (See Table 24-B for authorizing legislation and Table 24-J for project list and total cost of basin plan.) 33. WEST FORK OF MILL CREEK LAKE, OH Location. Dam is on West Fork of Mill Creek 6.5 miles above its junction with Mill Creek and 2 miles northeast of Mount Health, OH, and 10 miles north of downtown Cincinnati. Reservoir extends upstream about 3 miles and is in Hamilton County, OH. (See U. S. Geological Survey map of Glendale, OH.) Existing project. An earth embankment dam and a reservoir for flood control, recreation, and reduction of pumping requirements at Mill Creek barrier dam in Cincinnati. Total storage capacity of reservoir is 11,300 acre-feet, of which 9,850 acre-feet is for flood control. For further details see page 1119 of Annual Report for 1962. Cost of completed new work is $4,722,463 made up of $3,092,941 Federal cost for the initial project, $520,800 non-Federal cost for sewer relocation and dam, $50,000 non-Federal contributed funds in fulfillment of project authorization and $529,361 Federal cost and $529,361 non-Federal contribution in kind for recreation facilities under the completed projects program. Existing project selected for construction under additional authorization for Ohio River Basin in 1946 Flood Control Act. Local cooperation. Local interests were to release necessary land under their control and give assurance that future channel encroachment below damsite would be prevented. For enlargement of reservoir to include a conservation pool, local interests would contribute onehalf additional cost of such pool, including one-half cost of relocation of sanitary sewer, and agree to hold the United States free from damages resulting from its provision. Board of County Commissioners of Hamilton County, Ohio, adopted a resolution October 8, 1947, signifying willingness to fulfill requirements including provision of conservation pool. Assurances were executed on same date. A contract with the United States for relocation of sanitary sewer outside reservoir area in order to include conservation pool in project was accepted by Hamilton County, in which the United States paid onehalf cost of such relocation work. Hamilton County Commissioners furnished $50,000, required as a local contribution toward additional cost of providing conservation pool. Hamilton County Park District has undertaken development and management of recreation facilities in reservoir area for use of the public in accordance with the license granted by Secretary of the Army on October 31, 1951. Contract for cost shared recreation development under the completed works program was executed by the Board of Park Commissioners, Hamilton County Park District, Ohio, in September 1975 and approved by the Chief of Engineers in December 1975. Operations during fiscal year. New work: None. Maintenance: Routine maintenance was performed. Operation for flood control during 1985 flood season prevented damages estimated at $350,000. Construction started in March 1949 and reservoir was placed in operation in December 1952. Project is complete. Cost shared recreation development under the completed projects program is complete. 34. WILLIAM H. HARSHA LAKE, OH Location. Damsite is on East Fork of Little Miami River between Batavia and Williamsburg, OH, about 6.0 miles above Batavia and 32.6 miles above mouth of the Little Miami River. Entire project lies in Clermont County, OH. (See U. S. Geological Survey map of Batavia, OH.) Existing project. A reservoir for flood control and allied purposes. It includes an earthfill dam, outlet works, an uncontrolled saddle spillway, and a dike to close a saddle north of spillway. Total storage capacity of reservoir is 294,800 acre-feet, of which 210,600 acre-feet is reserved for flood control storage. Estimated cost of new work (1985) is $54,940,900 including $3,484,500 non-Federal reimbursement for water supply storage. Existing project was authorized by general authorization for Ohio River Basin in 1938 Flood Control Act. Project name was changed from East Fork Lake to William H. Harsha Lake effective January 4, 1981 by Public Law 96-383, October 6, 1980. Local cooperation. None required. However, the State of Ohio requested inclusion in the project of storage for future municipal and industrial water supply uses. Contract with State of Ohio for water supply storage under provisions of Water Supply Act of 1958, as amended, was approved by Secretary of the Army, May 20, 1970. Under terms of contract, State will reimburse the Federal Government for costs allocated to water supply storage over a period not to exceed 50 years after use of this storage is initiated plus estimated annual amount for cost of operation, maintenance and major capital replacements required for the water supply facilities. Operations during fiscal year. New work: Engineer- 24-12 LOUISVILLE, KY. DISTRICT ing and design studies continued. Contracts for sewer connection at Tate Site, electric service to Tate Site, and Tate bathhouse with landscaping were completed. Maintenance: Routine maintenance was performed. Operation for flood control during 1985 flood season prevented damages of $422,000. Construction was started in May 1970. Engineering studies are 94 percent complete. All land required for project has been acquired. Major relocation and construction features are complete, except two recreation items. Project is about 95 percent complete overall and was placed in operation in February 1978. 35. INSPECTION OF COMPLETED FLOOD CONTROL PROJECTS Flood Control Act of June 22, 1936, and subsequent acts require local interests to maintain and operate local protection projects in accordance with regulations prescribed by Secretary of the Army. Inspections were made to determine extent of compliance and to advise interests as necessary to measures required to correct deficiencies. (See Table 24-K for local protection projects and channel improvements inspected.) Fiscal year costs were $96,395. Total costs to September 30, 1985 were $2,676,302. 36. OTHER AUTHORIZED FLOOD CONTROL PROJECTS See Table 24-E. 37. FLOOD CONTROL WORKS UNDER SPECIAL AUTHORIZATION Emergency flood control activities pursuant to Public Law 99, 84th Congress, and antecedent legislation. Costs for fiscal year were $190,127 for disaster preparedness, $4,461 for emergency operations, $140,706 for repair work on Russell and Allison Levee, IL and $48,273 for repair work on eight other local protection project. Flood control activities pursuant to Section 205, 1948 Flood Control Act, Public Law 858, 80th Congress, as amended. Costs for fiscal year were $264,528 for preparation of initial appraisals, summary fact sheets, and detailed project reports on 10 projects, and $65,287 for plans and specifications and construction on three projects. See Table 24-L. Snagging and clearing navigable streams and tributaries in interest of flood control (Section 208, 1954 Flood Control Act, Public Law 780, 83rd Congress). Costs for fiscal year were $13,403 for preparation of plans and specifications on two projects, and $3,988 for one initial appraisal. See Table 24-L. Emergency bank protection (Section 14, 1946 Flood Control Act, Public Law 526, 79th Congress). Costs for fiscal year were $32,802 for preparation of initial appraisals on eight projects, $31,035 for plans and specifications on two projects and $375 for construction on three projects. See Table 24-L. General Investigations 38. SURVEYS. Fiscal year costs were $2,367,372 consisting of $2,299 for one navigation study, $1,906,235 for four flood damage prevention studies, $118,316 for the Wabash River Basin Authorization Report, $89,910 for Special Investigations, $25,134 for review of Federal Energy Regulatory Commission licenses, $225,460 for planning assistance to states, and $18 for one pre-authorization study, Phase I. 39. COLLECTION AND STUDY OF BASIC DATA Fiscal year costs were $153,837 for flood plain management services. 40. CONTINUATION OF PLANNING AND ENGINEERING Fiscal year costs were $269,729 for plan formulation and continuation of detailed planning studies on Fairfield, OH. 41. ADVANCE ENGINEERING AND DESIGN Fiscal year costs were $30,919 for General Design Memorandum studies on Frankfort, KY (South Frankfort Section) and $19,979 for review of economic feasibility of Falmouth Lake, KY. 24-13 TABLE 24-A REPORT OF THE CHIEF OF ENGINEERS, U. 8. ARMY 1986 COST AND FINANCIAL STATEMENT See Section Total to in Text Project Funding 1982 1983 1984 1985 Sep 30, 1985 Navigation - Locks and Dams 2 Green and Barren New Work Rivers, KY Approp. Cost Maint. Approp. Cost 3 Kentucky River, KY New Work Approp- Cost Maint. Approp. Cost Minor Rehab. Approp. Cost Flood Control - Local Protection 7 Dayton, KY New Work Approp. Cost 8 Evansville, IN New Work Approp. Cost 9 Levee Unit No. 5, Wabash River, IN 10 Mason J. Niblack Levee, IN 11 Mill Creek, OH 12 Southwestern Jefferson County, KY New Work Approp. Cost New Work Approp. Cost New Work Approp. Cost New Work Approp. Cost Flood Control - Reservoirs 13 Barren River Lake, KY New Work Approp. Cost Maint. Approp. Cost (Contributed Funds) New Work Contrib. Cost $ - 1,279,000 1,106,928 $ - 2,069,000 1,695,152 $ - 1,516,927 1,926,628 $ - 1,987,840 2,154,447 $13,808,2221 13,808,2221 26,863,612' * 26,820,519 ' - - - - 4,176,749 - - - - 4,176,749 790,000 1,049,000 1,161,700 1,411,000 46,449,789' 6 772,727 881,140 1,168,626 1,609,460 46,438,063' - - - - 556,956 - - - - 556,956 350,000 1,542,969 3,500,000 2,113,939 153,953 2,381,000 3,691,346 207,000 510,989 1,800,000 1,664,831 15,100 76,533 716,000 757,338 13,012,3457 13,006,660' 28,465,856' 27,939,9048 600,000 790,000 -59,600 -89,000 7,530,987 175,535 362,983 175,279 473,628 7,470,989 3,080 10,825 8,112 16,453 -1,000 673 - 4,337,617 - 4,337,617 6,536,000 2,683,600 7,639,900 9,586,000 30,757,742 2,839,732 5,252,537 6,083,545 10,952,631 29,169,869 2,995,000 7,028,710 1,420,000 2,430,000 38,861,183 4,348,890 5,883,989 2,552,857 1,286,893 36,561,365 - - - - 27,371,299' - - - - 27,371,299' 895,800 1,030,000 1,077,000 1,268,000 12,227,42610 11o 875,375 1,054,768 1,015,488 1,322,216 12,182,81710 11 - - - - 108,41812 S . 108,41812 14 Brookville Lake, IN (Contributed Funds) 15 Buckhorn Lake, KY New Work Approp. Cost Maint. Approp. Cost New Work Contrib. Cost New Work Approp. Cost Maint. Approp, Cost 12,100 5,208 321,000 358,813 134,096 123,811 360,000 373,597 -23,000 28,440 329,000 334,843 166 - 37,918,889 -56 37,904,424 409,000 3,401,189 418,991 3,395,105 - 7,592,000 - 7,578,738 - - - - 11,766,20613 - - - - 11,766,20613 586,840 569,000 663,000 640,000 8,075,41014 654,627 577,485 672,,955 651,327 8,047,40214 24-14 LOUISVILLE, KY. DISTRICT TABLE 24-A COST AND FINANCIAL STATEMENT CONTINUED See Section Total to in Text Project Funding 1982 1983 1984 1985 Sep 30, 1985 Flood Control - Reservoirs 16 Caesar Creek Lake, OH 17 Cagles Mill Lake, IN (Contributed Funds) 18 Carr Fork Lake, KY 19 Cave Run Lake, KY 20 Cecil M. Harden Lake, IN 21 Clarence J. Brown Dam & Reservoir, OH 22 Green River Lake, KY 23 Huntington Lake, IN (Contributed Funds) New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint Approp. Cost New Work Contrib Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Contrib. Cost $1,436,000 $ 804,600 $ -268,000 169,000 $62,893,882 1,585,052 1,421,753 1,080,039 320,283 62,681,487 362,000 539,000 561,000 579,000 3,221,463 354,471 557,474 515,619 618,053 3,206,024 - 210,701 -100,000 - 32,054 77,972 320,000 259,000 317,000 288,677 286,789 317,164 - - 205,000 - - 106,813 267,600 316,881 719,040 663,000 3,026,000 2,990,290 405,000 375,755 636 335,000 321,031 -40 -40 386,000 364,421 63,915 839,780 886,496 -8,614 2,730 310,000 261,496 1,279,469 1,196,546 676,114 752,337 1,704,800 1,525,688 420,000 450,667 -24,994 285,000 294,817 2,627,600 2,697,307 781,000 776,283 1,332,000 543,867 588,000 583,073 327,700 330,662 - 4,263,18415 447 4,262,95616 506,000 4,586,506 489,109 4,556,304 - 205,000 - 106,813 -40,000 50,854,82617 4,993 50,815,28717 803,000 5,894,90018 768,785 5,827,25218 724,500 73,862,282 1,381,479 72,762,612 562,000 3,870,546 557,164 3,843,017 - 6,633,81219 - 6,633,81219 312,000 5,079,096 313,930 5,073,759 - - - 22,083,660 - - - 22,083,660 291,000 420,000 374,000 3,257,347 318,305 373,189 419,925 3,249,943 -87 5,557 955,000 967,808 -53,594 -402 419,000 387,059 - - 33,422,32920 - - 33,422,32920 915,500 1,183,000 10,621,74921 908,362 1,177,646 10,551,74221 -251 522,000 584,133 -92 - - 19,428,60622 - 19,427,9532 359,000 4,212,012 381,804 4,206,802 - 193,903 - 193,812 24-15 TABLE 24-A CONTINUED REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1985 COST AND FINANCIAL STATEMENT See Section Total to In Text Project Funding 1982 1983 1984 1985 Sep 30, 1985 Flood Control - Reservoirs 24 Mississinewa Lake, IN (Contributed Funds) 25 Monroe Lake, IN (Contributed Funds) 26 Nolin Lake, KY 27 Ohio River Basin, Louisville District 28 Patoka Lake, IN (Contributed Funds) 29 Rough River Lake & Channel Improvement, KY (Contributed Funds) 30 Salamonie Lake, IN (Contributed Funds) New Work Approp. Cost Maint. Approp. Cost New Work Contrib. Cost New Work Approp. Cost Maint. Approp. Cost New Work Contrib. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Contrib. Cost New Work Approp. Cost Maint. Approp. Cost New Work Contrib. Cost New Work Approp. Cost Maint. Approp. Cost New Work Contrib. Cost $ -8,987 -7,458 334,000 300,547 $-4,914 $ - $ - - - -3,003 275,000 364,000 399,000 322,806 345,812 331,851 -13 217,150 234,343 -24,373 352,000 391,000 340,491 349,406 - -217,719 -217,719 - 338 920,920 944,754 -5,336 -969 1,050,000 1,052,033 383,270 48,200 1,340,798 -2,240 330,000 257,000 294,910 285,712 - 325,639 433,719 214,515 1,489 996,240 967,164 896 -1,079 315,000 257,736 -8 18 1,213,000 1,280,131 -208 1,956 302,000 349,336 -46 $23,967,53723 23,964,53423 4,068,105 3,971,358 239,200 237,871 - - 7,902,82724 - - 7,902,82724 416,300 308,160 4,542,82525 449,356 341,747 4,524,35825 - - 7,797,604 - - 7,797,604 -1,503 1,222,500 1,196,882 43,400 399,647 320,000 312,123 447,150 339,137 -2,460 -966 1,320,000 1,323,666 17,193,38126 17,193,37227 14,019,915" 13,925,230"28 - 1,526,142 - 1,526,142 - 53,080,790 90,216 53,050,321 311,000 2,036,131 313,500 2,016,520 - 20,676,289 76,114 20,292,203 . - 10,620,38929 S. 10,620,389"2 1,304,000 1,288,000 14,419,81030 1,279,021 1,320,794 14,365,80730 S. 22,61212 S. 22,61212 S- 16,559,90531 S. 16,559,90531 362,000 304,000 4,143,313 325,759 349,873 4,137,886 - - 170,697 S- 163,867 24-16 TABLE 24-A CONTINUED LOUISVILLE, KY. DISTRICT COST AND FINANCIAL STATEMENT See Section Total to in Text Project Funding 1982 1983 1984 1985 Sep 30,1985 Flood Control - Reservoirs 31 Taylorsville Lake, KY New Work Approp. $14,282,000 $8,140,081 $3,200,000 $ 844,400 $81,296,478 Cost 16,510,393 7,486,233 4,433,310 1,838,703 80,011,700 Maint. Approp. - 290,000 379,000 468,000 1,137,000 Cost - 257,702 373,917 489,253 1,120,872 (Contributed Funds) New Work Contrib. 437,000 816,838 - - 1,771,838 Cost 381,940 370,071 448,100 118,180 1,486,304 33 West Fork of Mill New Work Creek Lake, OH Approp. - - -86,600 - 3,622,30232 Cost 55,786 -55,000 78 - 3,622,30232 Maint. Approp. 380,000 280,000 294,000 264,000 3,473,889 Cost 218,997 428,961 288,634 289,713 3,469,499 (Contributed Funds) New Work Contrib. - - - - 50,000 Cost - - - - 50,000 34 William H. Harsha New Work Lake, OH Approp. 1,330,485 - 37,500 -15,000 52,023,15733 Cost 673,045 550,103 665,689 69,624 51,892,415" Maint. Approp. 378,000 428,000 381,000 422,000 2,698,366 Cost 361,394 440,066 378,829 425,414 2,678,870 1 Includes $85,000 public works funds. 2 Includes $2,000 emergency relief funds, $204,444 "maintenance and operation of dams and other improvements of navigable waters" and $3,842,667 expended from 1888 to 30 June 1936, for operation and care from permanent indefinite appropriation. s Includes $736,767 from Productive Employment Appropriation Act (PL 98-8) of 1983. ' Includes $720,850 from Productive Employment Appropriation Act (PL 98-8) of 1983. s Includes $316,871 under "maintenance and operation of dams and other improvements of navigable waters," and $6,405,372 expended between July 5, 1885 and June 30, 1937 on operation and care from permanent indefinite appropriation. * Includes $149,700 from Productive Employment Appropriation Act (PL 98-8) of 1983. ' Includes $12,426 allotted to Bellevue-Dayton and used in study of that project. * Includes $11,812 emergency relief funds. * Includes $2,224,948 Code 711 funds and $110,107 Code 713 funds. 10 Includes $100,000 Supplemental funds. 11 Includes $326,900 Special Recreation Use Fees. 12 Cost sharing for Code 713 recreation facilities. 1 Includes $61,451 public work acceleration executive 1963 funds, $143,088 Code 711 funds, and $243,619 Code 712 funds. 14 Includes $52,240 Special Recreation Use Fees. 1 Includes $35,814 Code 711 funds and $119,602 Code 713 funds. 16 Includes $35,814 Code 711 funds and $119,375 Code 713 funds. "17 Includes $76,724 Code 711 funds. 18 Includes $51,854 Special Recreation Use Fees. 1 Includes $19,683 Code 711 funds and $353,995 Code 713 funds. 20 Includes $133,413 Code 711 funds and $183,732 Code 713 funds. 21 Includes $114,280 Special Recreation Use Fees. 22 Includes $155,354 Code 713 funds. 23 Includes $389,392 Code 713 funds. 24 Includes $1,185 Code 711 funds and $869,158 Code 713 funds. 25 Includes $54,460 from Productive Employment Appropriation Act (PL 98-8) of 1983. " Includes $21,897 public works acceleration executive 1963 funds and $2,596,317 Code 711 funds. 2? Includes $21,897 public works acceleration executive 1963 funds and $2,596,308 Code 711 funds. * Includes $204,920 Special Recreation Use Fees and includes $52,000 Supplemental Funds. 2 Includes $196,306 public works acceleration executive 1963 funds, $867,396 Code 711 funds, and $22,612 Code 713 funds. S Includes $236,640 Special Recreation Use Fees. 31 Includes $315,549 Code 713 funds. 32 Includes $529,361 Code 713 funds. 33 Includes $58,571 for preconstruction planning, engineering and design completed before FY 1953. 24-17 REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1985 TABLE 24-B AUTHORIZING LEGISLATION Acts Work Authorized Documents GREEN AND BARREN RIVERS, KY (See Section 2 of Text) Purchase of original improvement Construction of Lock 2, Green River Construction of Lock 5, Green River Construction of Lock 6, Green River Appropriated $5,000 for continuing improvements of Green River above mouth of Big Barren River, with provision "That the Secretary of War may, in his discretion, expend such portion of said amount as may be necessary for removal of snags in Nolin River" Construct new Lock 1 and new Lock and Dam 2, Green River Construct new locks at Dam 5, Green River and Dam 1, Barren River; modification of Dam 5, Green River, widens bends in Bear Creek, KY Operation and care of locks and dams with War Department Appropriations for rivers and harbors Improvement of Nolin River Channel enlargement of lower 103 miles of Green River Recovation of authorities for improvement of Bear Creek and Nolin River OHIO RIVER BASIN (Louisville Dist.) (See Section 27 of Text) Aug 28, 1937 Construct levee, floodwalls, and drainage structures for protection of cities and towns in Ohio River Basin, projects to be selected by Chief of Engineers with approval of Secretary of War, at a cost not to exceed $24,877,000 for construction Jun 28, 1938 Approved general comprehensive plan for flood control and other purposes in Ohio River Basin as may be advisable in discretion of Secretary of War and Chief of Engineers, and for initiation and partial accomplishment of plan, authorized $75 million for reservoirs and $50.3 million for local protection works, individual projects to be selected and approved by Chief of Engineers subject to provision that authorization shall include diversion of Cache River above Cairo, Illinois, and protection of area north of Cairo drainage district by levees at an estimated cost of $2 million Aug 18, 1941 Additional $45 million for further prosecution of comprehensive plan for Ohio River Basin Dec 22, 1944 Additional $70 million for further prosecution of comprehensive plan for Ohio River Basin, including plan of improvement for flood control and other purposes in Kentucky River Basin Flood protection works at Taylorsville, Kentucky at an estimated cost of $129,350 Channel improvement of lower Rough River and Barnett Creek at an estimated cost of $360,000 Jul 24, 1946 Additional $125 million for further prosecution of comprehensive plan, including plan of improvement for flood control in Wabash River Basin, Illinois and Indiana, at an estimated cost of $9,629,000 Also, West Fork of Mill Creek at an estimated cost of $1,527,000. May 17, 1950 Additional $100 million for prosecution of comprehensive plan for Ohio River Basin, including necessary bank stabilization measures at New Harmony Bridge, Indiana, at an estimated cost of $500,000 Jul 3, 1958 Flood control Act of 1958 modified comprehensive plan to provide for Monroe Reservoir on Salt Creek, White River Basin, Indiana, at an estimated cost to the United States of $4,350,000; cost to local interests, $5,141,000 Oct 23, 1962 Flood Control Act of 1962 deleted Jessamine Creek Reservoir on Kentucky River, Kentucky, from comprehensive plan for Ohio River Basin Dec 30, 1963 Additional $150 million for further prosecution of comprehensive plan for Ohio River Basin Jun 18, 1965 Additional $89 million for further prosecution of comprehensive plan for Ohio River Basin May 12, 1967 Additional $38 million for further prosecution of comprehensive plan for Ohio River Basin Aug 13, 1968 Additional $35 million for further prosecution of comprehensive plan for Ohio River Basin Aug 11, 1888 Mar 3, 18931 Jul 13, 1892 Jul 13, 1902 Mar 3, 19052 Mar 3, 1909 Jul 3, 19302 Jun 26, 19343 Aug 30, 19352 Sep 3, 1954 24-18 H. Ex. Doc 111, 49th Cong., 2d Sess., Annual Report 1887, p. 1903 Annual Report, 1891, p. 2 4 3 9 Annual Report, 1891, p.2 4 7 8 S. Doc. 82, 83d Cong., 2d Sess. Rivers and Harbors Committee Doc. 2, 71st Cong., 1st Session, and H. Doc. 685, 69th Cong., 2d Session H.D. 480, 72d Congress, 2d Sess. S.D. 82, 83d Congress, 2d Sess. Flood Control Committee Document 1, 75th Congress., 1st Session Flood Control Committee Document 1, 75th Cong., 1st Session H. Doc. 504, 78th Congress, 2d Session S.D. 105, 78th Congress, 1st Session H. D. 535, 78th Congress, 2d Session H. D. 197, 80th Congress, 1st Session H.D.198, 80th Congress, 1st Sess H. D. 192, 85th Congress, 1st Session H. D. 423, 87th Congress, 2d Session Public Law 88-253, 88th Cong., 1st Session Public Law 89-42, 89th Cong. 1st Session Public Law 90-17, 90th Cong., 1st Session Public Law 90-483, 90th Cong., 2d Session TABLE 24-B CONTINUED LOUISVILLE, KY. DISTRICT AUTHORIZING LEGISLATION Acts Work Authorized Documents OHIO RIVER BASIN (Louisville Dist.) (Cont'd.) Jun 19, 1970 Additional $69 million for further prosecution of comprehen- Public Law 91-282, 91st Congress, sive plan for Ohio River Basin 2d Session Mar 7, 1974 Additional $120 million for further prosecution of comprehen- Public Law 93-251, 93rd Congress, sive plan for Ohio River Basin 2d Session Mar 7, 1974 Fifty-four local protection projects and one reservoir project in Public Law 93-251, 93rd Congress, comprehensive plan for Ohio River Basin were deauthorized 2d Session August 5, 1977, under Section 12, Water Resources Development Act of 1974 Two additional local protection projects in comprehensive plan for Ohio River Basin were deauthorized November 6, 1977, under Section 12, Water Resources Development Act of 1974 WABASH RIVER BASIN (See Section 32 of Text) Aug 13, 1968 Construction of five multiple purpose reservoirs and one S.D. 96, 90th Congress, 2d Session local protection project in Wabash River Basin, IL & IN, with proviso that construction of Big Walnut Lake, IN, project must be approved by the President. Authorization of $50 million for initiation and partial accomplishment of project. Dec 29, 1981 Two multiple purpose reservoirs in Wabash River Basin were Public Law 97-128, 97th Congress, deauthorized 2d Session SDeficiency act. 2 Authorization for Nolin River and Bear Creek revoked by Act of Sep. 3, 1954. 3 Permanent Appropriations Repeal Act. TABLE 24-C OTHER AUTHORIZED NAVIGATION PROJECTS (See Section 5 of Text) For Last Cost to Sep 30, 1985 Full Report See Annual Operation and Name of Project Status Report Construction Maintenance Licking River Rough River, KY Tradewater River, KY White River, IN Completed Completed Completed Completed 1901 1951 1858 1909 $ 13,045 105,500 18,568 119,312 $- 101,196 33,331 24-19 TABLE 24-E REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1985 OTHER AUTHORIZED FLOOD CONTROL PROJECTS For Last Cost to Sep 30, 1985 Full Report See Annual Operation and Project and Status' Report For Construction Maintenance Local Protection: Completed: Boone County, KY (Bank Protection & Repair Roads) Brevoort Levee, IN (Wabash River) Brookport, IL Cannelton, IN Chaplin River, Perryville, KY' Cincinnati, OH Covington, KY Delphi, IN (Wabash River) England Pond Levee, IL (Wabash River) English, IN (Little Blue River)2 Frankfort, KY (North Frankfort) (Kentucky River)' Gill Township Levee, IN (Wabash River) Golconda, IL Grassy Creek, Jackson County, IN (Muscatatuck River)' Harrisburg, IL Hawesville, KY Indianapolis, IN (Fall Creek Section) (White River) Indian Creek, Corydon, IN' Jackson, KY (Kentucky River) Jeffersonville-Clarksville, IN Lawrenceburg, IN Lebanon Junction, KY (Salt River)' Levee Unit 8, IN (White River) Louisville, KY'4 Lyford Levee Unit, IN (Wabash River) Mason J. Niblack Levee, IN (Wabash River) Mill Creek, Jefferson County, KY'2 Mount Carmel, IL (Wabash River) Muncie, IN (White River) Neon-Fleming, KY (Kentucky River) New Albany, IN New Harmony Bridge, IL & IN (Wabash River)2' Newburgh, IN' Newport, KY Paducah, KY Panther Creek, KY (Green River)' Portland, IN (Salamonie River)' Reevesville, IL (Cache River) Rochester & McCleary's Bluff Levee, IL (Wabash River) Rosiclare, IL Saline River & Tribs, IL Sturgis, KY Taylorsville, KY (Salt River) Tell City, IN Terre Haute (Conover Levee), IN (Wabash River)6 Town Creek, Harrodsburg, KY'2 Triplett Creek, Morehead, KY (Licking River)' Uniontown, KY Vincennes, IN (Wabash River)7 West Terre Haute, IN (Wabash River) Active: Canoe Creek, Henderson, KY' Frankfort, KY (South Frankfort) (Kentucky River)' Russell & Allison Levee, IL (Wabash River) 1977 1954 1958 1959 1957 1965 1953 1972 1965 1979 1948 1960 1953 1952 1955 1953 1964 1957 1959 1953 1967 1952 1975 1944 1965 1973 1972 1956 1963 1957 1959 1974 1959 1959 1970 1962 1954 1972 1954 1981 1972 1952 1956 1965 1967 1972 1956 1964 1977 1979 $ 392,443 1,240,299 597,493 2,068,391 832,700 10,150,935 7,862,937 144,563 734,498 372,353 2,960,970 561,200 565,333 70,304 870,015 969,318 1,788,840 300,143 130,952 4,226,361 2,473,414 130,417 700,534 26,721,438 267,391 1,554,712 292,710 1,980,675 887,835 86,532 5,375,471 297,624 52,061 7,512,987 4,761,551 254,031 237,657 600,300 1,079,236 622,544 7,826,219 1,826,778 378,050 932,229 14,91h 56,505 893,094 1,070,926 3,308,940 1,095,704 515,783 52,088 24-20 LOUISVILLE, KY. DISTRICT TABLE 24-E CONTINUED OTHER AUTHORIZED FLOOD CONTROL PROJECTS For Last Cost to Sep 30, 1985 Full Report See Annual Operation and Project and Status' Report For Construction Maintenance Inactive: Anderson, IN (White River) Caseyville, KY Cloverport, KY Concordia, KY Frankfort, KY (Benson Creek) (Kentucky River) Greenfield Bayou Levee, IN (Wabash River) Indianapolis, IN (Warfleigh Section) (White River) Island Levee, IN (Wabash River) Levee Unit 1, IL (Wabash River) Lewisport, KY Marion, IN (Wabash River) Metropolis, IL New Harmony Bridge, IL & IN (Wabash River)2 Newport-Wilder, KY Owensboro, KY Salyersville, KY (Licking River) Shawneetown, IL Smithland, KY Tolu, KY West Point, KY Reservoirs: Active - no FY 1985 expenditure Camp Ground Lake, KY (Salt River) Downeyville Lake, IN (Wabash River) Louisville Lake, IL (Wabash River) Inactive: Big Pine Lake, IN (Wabash River) Big Walnut Lake, IN (Wabash River) Booneville Lake, KY (Kentucky River) Eagle Creek Lake, KY Falmouth Lake, KY (Licking River) Lafayette Lake, IN (Wabash River) Mining City Lake, KY (Green River) Red River Lake, KY (Kentucky River) 1940 1979 1979 1976 1979 1973 1979 1959 1946 1983 1983 1977 1980 1976 1975 1981 1977 1976 $ 5,724 157,935 153,410 355,963 60,000 209,975 10,575 12,000 25,367 4,490 160,773 2,335,812 1,270,590 1,009,188 1,038,595 702,471 944,386 1,200,920 350,474 1,794,308 ' All projects are on Ohio River unless otherwise noted. * Authorized by Chief of Engineers under Section 205, 1948 Flood Control Act, as amended. 3 Cost includes $161,098 cash contribution consisting of $105,118 from the City of Frankfort, KY and $55,980 from the Commonwealth of Kentucky. ' Cost includes $1,716,301 cash contribution from City of Louisville, KY. s The Water Resources Development Act of 1974 modified the Newburgh Locks & Dam project to include the bank protection works at Newburgh, IN. 6 Partially completed to form a useful unit. Remaining portion of project deauthorized. Partially completed to form a useful unit. Remaining portion of project deferred. 8 Advance Engineering and Design funded with General Investigations Appropriation. 24-21 REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1985 TABLE 24-G DEAUTHORIZED PROJECTS For Last Full Report Federal Contributed See Annual Date Funds Funds Project Report For Deauthorized Expended Expended Flood Control - Local Protection Adams Levee, IN (Wabash River) - 1978 $ -- Alton, IN - 1977 - - Aurora, IN - 1977 35,420- Bellevue, KY - 1977 19,023- Bonpas Creek, IL (Wabash River) - 1981 - - Bromley, KY - 1977- California (Cincinnati) OH - 1977 16,465- Carrollton, KY - 1977 9,713- Cave-in-Rock, IL - 1977- Cincinnati, OH (Unit 2) - 1977 - - Cincinnati, OH (Unit 4) - 1977 - - Cleves, OH -1977 6,343- Clinton, IN - 1977 6,848- Deer Creek, Prairie, Levee, IN - 1977 - - Derby, IN - 1977 - - Elizabethtown,, IL - 1977 - - Fletcher & Sunshine Gardens Levee, IN - 1977 3,361- Grandview, IN - 1977 8,497- Honey Creek Levee, IN - 1977 - - Leavenworth, IN - 1977 - - Levee Unit 1, Eel River, IN - 1977 - - Levee Unit 2, Eel River, IN - 1977 - - Levee Unit 2, East Fork White River, IN - 1977 - - Levee Unit 3, East Fork White River, IN 1938 1977 275- Levee Unit 1, Little Wabash River, IL - 1977 - - Levee Unit 2, Little Wabash River, IL - 1977 - - Levee Unit 2, Wabash River, IL - 1977 - - Levee Units 3 and 4, Wabash River, IL 1938 1977 216- Levee Unit 6, Wabash River, IL - 1977 9,922- Levee Unit 17, Wabash River Basin, IN - 1977 - - Levee Unit 1, White River, IN - 1977 - - Levee Unit 7, White River, IN - 1977 - - Levee Unit 9, White River, IN - 1977 - - Levee Unit 10, White River, IN - 1977 - - Ludlow, KY - 1977 14,503- Madison, IN - 1977 - - Mauckport, IN - 1977 - - McGinnis Levee, IN 1950 1977 71,049- Milton, KY - 1977 - - Moscow, OH - 1977 - - New Amsterdam, IN - 1977 - - New Harmony, IN - 1977 - - New Richmond, OH - 1977 7,104- Orleans, IN 1972 1977 13,158- Patriot, IN - 1977 - - Prestonville , KY - 1977 - - Raccoon Creek Levee, IN - 1977 - - Rising Sun, IN - 1977 - - Rockport, IN - 1977- Rome, IN - 1977-- Shoals, IN (East Fork White River) 1938 1977 Shufflebarger Levee, IN 1950 1977 64,487 Sugar Creek Levee, IN 1961 1977 28,061 Terre Haute, IN - 1977 Tri Pond Levee, IL 1972 1977 65,510 Troy, IN 1977 Utica, IN - 1978 Vevay, IN - 1977 Westport, KY - 1977 Flood Control - Reservoirs Big Blue Lake, IN 1980 1981 1,079,867- Clifty Creek Lake, IN 1979 1981 1,016,358- Helm Lake, IL 1976 1981 41,616- Lincoln Lake, IL 1979 1981 1,331,844- Metamora Lake, IN- 1977- 24-22 TABLE 24-H NAVIGATION LOCKS AND DAMS PRINCIPAL FEATURES - GREEN & BARREN RIVERS AND KENTUCKY RIVER NAVIGATION SYSTEMS Lock Dimensions Miles Greatest Length Lock above Available Upper Depth of Year and Mouth of Distance from Width of For Full Normal Pool Miter Sills Character of Percent Opened to Cost of Dam River Nearest Town Chamber Width Lift Elevation Upper Lower Foundation Complete Navigation Lock and Dam (feet) (feet) (feet mal) (feet) (feet) CONSTRUCTION OF LOCKS AND DAMS, OHIO RIVER -For report on this improvement see this heading under Ohio River. GREEN AND BARREN RIVERS, KY (See Section 2 of Text) Green River New 1 9.1 Spottsville, KY 84.0 600.0 11.8' 349.1 12.1 11.3 Shale and Coal 100 1956' $5,101,978' New 2 63.1 0.3 miles below 84.0 600.0 14.3 363.4 15.0 11.7 Shale 100 1956' 4,799,271' Calhoun, KY 3 108.5 0.3 miles below 35.8 137.5 17.0 380.4 7.3 5.6 Rock 100 1836 121,377 Rochester, KY 4 149.0 Woodbury, KY 35.8 138.0 16.4 396.8 7.1 6.5 Rock 100 1839' 125,718 5 168.1 0.3 miles below 56.0 360.0 15.2 412.0' 12.0 9.3 Piles and Rock 100 1905' 1,020,868'" Glenmore, KY 6 181.7 2.8 miles above 36.0 145.0 9.2 421.1 8.0 8.8 Gravel 100 1905' 168,415 Brownsville, KY Barren Barren River River 1 15.0 " 0.3 miles above 56.0 360.0 15.2 412.0 12.0 9.3 100 1934 871,565' Greencastle, KY KENTUCKY RIVER, KY (See Section 3 of Text) Kentucky River Kentucky River 1 4.0 3.8 miles above 38.0 145.0 8.2 430.0 8.2" 14.8 Rock and Clay 100 1839" - Carrollton, KY 2 31.0 Lockport, KY 38.0 145.0 13.9 443.9 7.6 6.1 Rock 100 1839" - 3 42.0 Gest, KY 38.0 145.0 13.2 457.1 8.6 6.5 Rock 100 1844" 1,350,385" 4 65.0 1.0 mile below 38.0 145.0 13.2 470.3 6.4 7.4 Rock 100 1844" - Frankfort, KY 5 82.2 2.8 miles below 38.0 145.0 15.0 485.3 10.0 6.5 Rock 100 1844" " Tyrone, KY 6 96.2 21.6 miles below 52.0 147.0 14.0 499.3 9.4 6.4 Rock and Piles 100 1894" 314,847 High Bridge, KY 7 117.0 0.8 mile below 52.0 147.0 15.3 514.6 9.1 6.9 Rock 100 1897" 290,788 High Bridge, KY 8 139.9 4.7 miles above 52.0 146.0 18.7 533.6 10.6 6.0 Rock 100 1900" 275,463 Camp Nelson, KY 9 157.5 Valley View, KY 52.0 148.0 17.3 550.6 10.0 6.6 Rock 100 1907" 237,646 10 176.4 1.0 mile below 52.0 148.0 17.0 567.6 9.0 6.0 Rock 100 1907" 221,500 Ford, KY 11 201.0 17.2 miles below 52.0 148.0 18.0 585.6 10.0 6.0 Rock 100 1906" 296,593 Irvine, KY 12 220.0 Ravenna, KY 52.0 148.0 17.0 602.6 9.6 6.0 Rock 100 1910" 425,693 13 239.9 2.2 miles below 52.0 148.0 18.0 620.6 9.6 6.0 Rock 100 1915" 461,476 Willow, KY 14 249.0 Heidelberg, KY 52.0 148.0 17.0 637.6 8.6 6.0 Rock 100 1917" 392,902 Co ' At normal pool Dam 48, Ohio River, Elev. 337.3, Green River datum (Elev. 338.0 Ohio River datum). SNew Lock 1 placed in operation May 25, 1956; old Dam 1, completed 1835-40, replaced with new cellular concrete masonry dam constructed 1970-71 with O&M General funds at cost of $822,000. SDoes not include $179,110 cost of old Lock and Dam 1. SNew Lock and Dam 2, placed in operation June 18,1956. Does not include $296,696 cost of old Lock and Dam 2. * Operation discontinued September 30, 1981. Breaching of dam on May 24, 1965, stopped through traffic to Bowling Green, KY. * With movable A frame crest 3 feet high. * Operation discontinued Aug. 1, 1951. * Does not include $179,434 cost of old Lock and Dam 5. SDistance from mouth of Green River is 164.5 miles. Lock closed to navigation as the result of loss of pool at Green River Lock and Dam 4 on May 24, 1965. " Includes $729,269 for new large lock completed in 1934. " At normal pool McAlpine Dam, Ohio River elev. 421.8 Kentucky River datum (Elev. 420 Ohio River datum). " Reconstruction completed by United States in 1882. " Built by State of Kentucky. Cost given is for repairs by United States to Locks and Dams 1 through 5. Original construction costs to State were: L&D 1, $220,300; L&D 2, $151,983; L&D 3, $135,857; L&D 4, $131,607; and L&D 5, $137,436. * Lock was closed to traffic and placed in caretaker status in September 1982. 0 ' VS yJ REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1985 OHIO RIVER BASIN TOTAL COST OF BASIN PLAN (See Section 27 of Text) LOCAL PROTECTION Type of Estimated Cost' Project and Status' Construction Federal Non-Federal Total Completed: Barnett Creek, KY (Rough River? ' Brookport, IL' 6 Cannelton, IN5 ' Cincinnati, OH5 8 Covington, KY5 ' Delphi, IN (Wabash River?') England Pond Levee, IL (Wabash River)1' Frankfort, KY (Kentucky River?) North Frankfort' Golconda, IL5 "1 Harrisburg, IL 5 10 Hawesville, KY ' "1 Jackson, KY (Kentucky River? ' Jeffersonville-Clarksville, IN 7 Lawrenceburg, IN5 Louisville, KY5 " Mason J. Niblack Levee, IN (Wabash River?' New Albany, IN'" New Harmony Bridge, IL and IN (Wabash River)? ' Newport, KY5' Paducah, KY5' Reevesville, IL (Cache River)? 15 Rochester and McCleary's Bluff Levee, IL (Wabash River)" Rough River, KY" 4 Sturgis, KY (Tradewater River)" Taylorsville, KY (Salt River?) 16 Tell City, INS 1" Uniontown, KY5 '1 Vincennes, IN (Wabash River?) West Terre Haute, IN (Wabash River) Active: Dayton, KY' Evansville, IN' Frankfort, KY (Kentucky River?)' South Frankfort5 Russell & Allison Levee, IL (Wabash River)' Inactive: Caseyville, KY' Cloverport, KY5 Concordia, KY5 Frankfort, KY (Kentucky River?) Benson Creek5 Greenfield Bayou Levee, IN (Wabash River?) Island Levee, IN (Wabash River?) Lewisport, KY' Metropolis, IL5 New Harmony Bridge, IL and IN (Wabash River? ' Owensboro, KY5 Shawneetown, IL5 Smithland, KY5 Tolu, KY5 West Point, KY'5 Wilders, KY Channel improvement Wall and levee Wall and levee Wall and barrier dam Wall and levee Levee Levee Wall and levee Wall and levee Wall and levee Levee Cutoff channel Wall and levee Wall and levee Wall and levee Levee and pump plants Wall and levee Bank Protection Wall and levee Wall and levee Levee Levee Channel improvement Levee Levee Wall and levee Levee Wall and levee Levee Wall and levee Wall and levee Wall Levee Levee Wall and levee Levee Wall and levee Levee Levee Wall and levee Wall and levee Bank protection Wall and levee Wall and levee Wall and levee Levee Wall and levee Wall and levee $ - 597,493 2,068,391 10,150,935 7,862,937 144,563 734,498 2,960,970 565,333 870,015 969,318 130,952 4,226,361 2,473,414 2,540,000 4,337,617 5,375,471 297,624 7,512,987 4,761,551 600,300 1,079,236 1,826,778 378,050 932,229 1,070,926 6,426,000 1,095,704 13,010,000 56,940,500 7,120,000 ', - 8,500 29,105 1,309,146 1,051,102 17,164 107,000 272,100 10,900 20,000 42,593 3,000 590,888 284,725 745,000 $ 605,993 2,097,496 11,460,081 8,914,039 161,727 841,498 3,233,070 576,233 890,015 1,011,911 133,952 4,817,249 2,758,139 3,285,000 109,200 4,446,817 740,000 6,115,471 - 297,624 298,506 7,811,493 232,000 4,993,551 40,000 640,300 100,000 1,179,236 93,000 1,919,778 63,309 441,359 32,707 964,936 72,153 1,143,079 285,000 6,711,000 150,000 1,245,704 2,043,000 7,982,000 660,000 15,053,00018 64,922,500"18 7,780,000"1 19,400,000 2,340,000 21,740,00020 396,000 728,000 590,000 3,340,000 4,600,000 4,630,000 610,000 3,070,000 664,376 886,000 1,810,000 864,000 303,000 3,283,000 10,800,000 35,000 193,000 55,000 1,150,000 1,087,000 528,000 243,000 431,000 99,000 195,000 361,000 414,000 35,000 400,000 959,000 431,000 921,000 645,000 4,490,00021 5,687,000" 5,158,00022 853,000" 3,501,000 763,376" 1,081,000 2,171,000 1,278,000 338,000 3,683,000" 11,759,0005 24-24 TABLE 24-I LOUISVILLE, KY. DISTRICT TABLE 24-I CONTINUED OHIO RIVER BASIN TOTAL COST OF BASIN PLAN (FLOOD CONTROL) (See Section 27 of Text) LOCAL PROTECTION Type of Estimated Cost' Project and Status' Construction Federal Non-Federal Total Deauthorized August 5, 1977 under Section 12, Water Resources Development Act of 1971 (Public Law 93-251): Alton, IN Bellevue, KY Bromley, KY Carrollton, KY Cave-in-Rock, IL Cincinnati, OH (Unit 2) Cincinnati, OH (Unit 4) Cleves, OH Clinton, IN (Wabash River) Deer Creek Prairie Levee, IN (Wabash River) Derby, IN Elizabethtown, IL Fletcher and Sunshine Gardens Levee, IN (Wabash River) Grandview, IN Honey Creek Levee, IN Leavenworth, IN Levee Unit 1, Eel River, IN Levee Unit 2, Eel River, IN Levee Unit 1, Little Wabash River, IL Levee Unit 2, Little Wabash River, IL Levee Unit 6, Wabash River, IL Levee Unit 17, IN Levee Unit 1, White River, IN Levee Unit 2, White River, IN Levee Unit 7, White River, IN Ludlow, KY Madison, IN Mauckport, IN McGinnis Levee, IN (Wabash River) Milton, KY Moscow, OH New Amsterdam, IN New Harmony, IN (Wabash River) New Richmond, OH Patriot, IN Prestonville, KY Raccoon Levee, IN (Wabash River) Rising Sun, IN Rockport, IN Rome, IN Shufflebarger Levee, IN (Wabash River) Sugar Creek Levee, IN (Wabash River) Tri-Pond Levee, IL (Wabash River) Troy, IN Vevay, IN Westport, KY Levee Wall and Levee Wall and Levee Wall and Levee Levee Wall and Levee Wall Levee Levee Levee Wall and Levee Wall and Levee Levee Levee Levee Wall and Levee Levee Levee Levee Levee Levee Levee Levee Levee Levee Wall and Levee Levee Levee Levee Wall Levee Levee Levee Wall and Levee Levee Wall and Levee Levee Wall and Levee Wall and Levee Levee Levee Levee Levee Wall and Levee Levee Wall $ 255,000 1,570,000 1,250,000 2,220,000 661,000 16,800,000 14,900,000 1,240,000 77,000 213,000 553,000 559,000 548,000 580,000 653,000 1,470,000 204,000 2,090,000 2,850,000 3,410,000 1,160,000 1,580,000 2,180,000 724,000 1,490,000 2,540,000 3,820,000 506,000 1,820,000 2,480,000 1,170,000 476,000 616,000 3,200,000 753,000 1,710,000 426,000 896,000 466,000 359,000 2,380,000 418,000 2,050,000 502,000 1,170,000 1,610,000 $ 40,000 400,000 925,000 97,000 125,000 2,900,000 621,000 67,000 9,000 10,000 67,000 153,000 26,000 133,000 32,000 266,000 40,000 715,000 164,000 136,000 56,000 118,000 116,000 73,000 88,000 745,000 360,000 105,000 104,000 41,000 372,000 13,000 25,000 720,000 372,000 55,000 37,000 280,000 133,000 67,000 90,000 29,000 191,000 133,000 146,000 41,000 $ 295,000 1,970,000 2,175,000 2,317,000 786,000 19,700,000 15,521,000 1,307,000 86,000 223,00023 620,000 712,000 574,00023 713,000 685,000 1,736,000 244,000 2,805,000 3,014,000"6 3,546,00027 1,216,000 1,698,000" 2,296,000"6 797,00026 1,578,00026 3,285,000 4,180,000 611,000 1,924,000 2,521,000 1,542,000 489,000 641,000 3,920,000 1,125,000 1,765,000 463,000" 1,176,000 599,000 426,000 2,470,000 447,00023 2,241,000" 635,000 1,316,000 1,651,000 24-25 REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1985 TABLE 24-I CONTINUED OHIO RIVER BASIN TOTAL COST OF BASIN PLAN (FLOOD CONTROL) (See Section 27 of Text) LOCAL PROTECTION Type of Estimated Cost' Project and Status' Construction Federal Non-Federal Total Deauthorized November 6, 1977 under Section 12, Water Resources Development Act of 1974 (Public Law 93-251) Aurora, IN Wall and Levee $4,300,000 $1,190,000 $5,490,000 California (Cincinnati), OH Wall and Levee 1,750,000 720,000 2,470,000 Deauthorized October 3, 1978 under Section 12, Water Resources Development Act of 1974 (Public Law 93-251) Adams Levee, IN (Wabash River) Levee 292,000 14,000 306,00027 Utica, IN' Levee 1,570,000 120,000 1,690,000 Deauthorized May 6, 1981 under Section 12, Water Resources Development Act of 1974 (Public Law 93-251) Bonpas Creek, IL (Wabash River)5 Channel 1,080,000 630,000 1,710,0002" improvement SAll projects are on an Ohio River unless otherwise noted. 2 Latest cost estimate revision 1954 unless otherwise noted. 3 Part of Rough River Reservoir and Channel Improvement Project, KY. 4 Details of this project are in individual report. 5 Also see "Other authorized flood control projects." 6 See Annual Report for 1958 for details. ' See Annual Report for 1959 for details. ' See Annual Report for 1957 for details. 9 See Annual Report for 1965 for details. o10S ee Annual Report for 1953 for details. 1 See Annual Report for 1972 for details. 1 See Annual Report for 1960 for details. " See Annual Report for 1955 for details. 14 See Annual Report for 1962 for details. 15 Substitute project for Belknap, Karnak, and Ullin, IL, complete. See Annual Report for 1954 for details. 16 See Annual Report for 1952 for details. 17 See Annual Report for 1956 for details. "1 Latest cost estimate revision 1985. 1' Latest cost estimate revision 1984. 20 Latest cost estimate revision 1983. 21 Latest cost estimate revision 1976. 2 Latest cost estimate revision 1978. " Latest cost estimate revision 1960. 4 Latest cost estimate revision 1971. 25 Latest cost estimate revision 1977. SLatest cost estimate revision 1961. 27 Latest cost estimate revision 1973. 24-26 LOUISVILLE, KY. DISTRICT TABLE 24-I CONTINUED OHIO RIVER BASIN TOTAL COST OF BASIN PLAN (FLOOD CONTROL) (See Section 27 of Text) RESERVOIRS Tributary Basin Estimated Cost' Reservoirs Status Stream Federal Non-Federal Total Great Miami River: Brookville Lake, IN 2 Metamora Lake, IN Green River: Barren River Lake, KY'2 Green River Lake, KY2 Mining City Lake, KY Nolin Lake, KY 2 Rough River Kentucky' Kentucky River Booneville Lake, KY Buckhorn Lake, KY2 Carr Fork Lake, KY2 Licking River Cave Run Lake, KY2 Falmouth Lake, KY Little Miami River: Caesar Creek Lake, OH2 William H. Harsha Lake, OH 2 Mill Creek: West Fork of Mill Creek Lake, OH 2 Wabash River: Cagles Mill Lake, IN' Cecil M. Harden Lake, IN'2 Monroe Lake, IN 2 Patoka Lake, IN 2 Active Deauthorized Complete Complete Inactive Active Complete Inactive Complete Active Active Inactive Active Active Complete Active Complete Complete Active East Fork of Whitewater River West Fork of Whitewater River Barren River Green River Green River Nolin River Rough River South Fork of Kentucky River Middle Fork of Kentucky River North Fork of Kentucky River Licking River Licking River Caesar Creek East Fork of Little Miami River West Fork of Mill Creek Mill Creek Raccoon Creek Salt Creek Patoka River $37,904,424 35,300,000 27,371,299 33,422,329 69,100,000 17,193,372 10,620,389 60,700,000 11,766,206 50,854,826 114,826,300 125,000,000 $7,578,7383 $ 45,483,162 - 35,300,0004 108,4186 183,732'5 22,612'5 27,479,717 33,606,061 69,100,000' 17,193,372 10,643,001 60,700,0006 11,766,206 50,854,826 114,826,300' 125,000,0008 59,744,000 5,037,0009 64,781,000 51,456,400 3,484,5008 54,940,900 3,622,302 1,100,16110 4,262,956 6,633,812 7,902,827 106,8165 353,995'5 8,666,76211 52,869,000 25,548,70012 4,722,463 4,369,772 6,987,807 16,569,589 78,417,700 Latest cost estimate revision 1985 unless otherwise noted. Details of this project given in individual report. Cash contributions for water supply storage. Latest cost estimate revision 1954. For Code 713 recreation development. Latest cost estimate revision 1975. Includes $35,213,000 United States Forest Service cost. Latest cost estimate revision 1979. Reimbursement for water supply storage. 10 Includes $520,800 for non-Federal cost for sewer relocation and dam, $50,000 for contributed funds in fulfillment of project authorization, and $529,361 for Code 713 recreation development. " Includes $7,797,604 cash contribution for storage for low-flow regulation and $869,158 for Code 713 recreation development. " Includes $14,173,500 cash contribution for water supply storage, and $11,375,200 for initial recreation development. 24-27 REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1985 TABLE 24-J WABASH RIVER BASIN TOTAL COST OF BASIN PLAN: (FLOOD CONTROL) (See Section 32 of Text) Type of Construction Estimated Cost Project or Stream Status Federal Non-Federal Total LOCAL PROTECTION Marion, IN Wall and Levee Inactive $ 3,900,000 $ 854,000 $ 4,754,0002 RESERVOIRS Big Blue Lake, IN Big Blue River Deauthorized 87,200,000 53,846,0003 141,046,0004 Big Walnut Lake, IN Big Walnut Creek Inactive 81,800,000 45,069,0005 126,869,0004 Downeyville Lake, IN Flatrock and Little Flatrock Rivers Active 74,200,000 64,448,000 138,648,000' Helm Lake, IN Skillet Fork Deauthorized 25,171,000 14,829,0007 40,000,0008 Louisville, Lake, IL Little Wabash River Inactive 113,000,000 14,435,0009 127,435,00010 1 Latest cost revision 1984 unless otherwise noted. 2 Latest cost estimate revision 1977. 3 Includes $38,190,000 reimbursable by non-Federal interests for water supply and $15,656,000 reimbursable for initial recreation facilities. 4 Latest cost estimate revision 1979. S Includes $26,663,000 reimbursable by non-Federal interests for water supply and $18,406,000 reimbursable for initial recreation facilities. 6 Includes $53,084,000 reimbursable by non-Federal interests for water supply, $8,749,000 reimbursable for initial recreation facilities. ' Includes $12,696,000 reimbursable by non-Federal interests for water supply and $2,133,000 for recreation facilities. ' Latest cost estimate revision 1975. 9 Includes $8,402,000 reimbursable by non-Federal interests for water supply and $6,033,000 reimbursable for initial recreation facilities. o10 Latest cost estimate revision 1982. 24-28 LOUISVILLE, KY. DISTRICT TABLE 24-K INSPECTION OF COMPLETED FLOOD CONTROL PROJECTS (See Section 35 of Text) Date of Local Protection Projects Inspection' Brevoort Levee, IL Jun 1985 Brookport, IL Oct 1984 Cannelton, IN Oct 1984 Cincinnati, OH May 1985 Covington, KY Oct 1984 Dayton, KY May 1985 Delphi, IN Apr 1985 England Pond Levee, IL Jun 1985 Evansville, IN Jun 1985 Frankfort, KY, North Frankfort Oct 1984 Gill Township Levee, IN Apr 1985 Golconda, IL Nov 1984 Harrisburg, IL Nov 1984 Hawesville, KY Oct 1984 Indianapolis, IN Apr 1985 Jeffersonville-Clarksville, IN Nov 1984 Lawrenceburg, IN May 1985 Lebanon Junction, KY Nov 1984 Levee Unit No. 5, Wabash River, IN Oct 1984 Levee Unit No. 8, IN Apr 1985 Louisville, KY Oct 1984 Lyford Levee, IN May 1985 Mason J. Niblack Levee, IN Jun 1985 Mt. Carmel, IL Oct 1984 Muncie, IN Apr 1985 New Albany, IN Nov 1984 Newport, KY Oct 1984 Paducah, KY Oct 1984 Reevesville, IL Oct 1984 Rochester-McCleary's Bluff Levee, IL Oct 1984 Rosiclare, IL Nov 1984 Shawneetown, IL Nov 1984 Sturgis, KY Jun 1985 Taylorsville, KY Nov 1984 Tell City, IN Oct 1984 Terre Haute (Conover Levee), IN May 1985 Uniontown, KY Jun 1985 Vincennes, IN Jun 1985 West Terre Haute, IN May 1985 1 FY 85 funding limitations provided for annual inspections in lieu of semi-annual inspections on local protection projects. 24-29 REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1985 TABLE 24-K INSPECTION OF COMPLETED CONTINUED FLOOD CONTROL PROJECTS (See Section 35 of Text) Dates of Channel Improvements Inspection Chaplin River, Perryville, KY Cypress Creek, McLean County, KY Jul 1985 Eel River, Brazil Waterworks, IN May 1985 English, IN (Little Blue River) Aug 1985 Grassy Creek, Jackson County, IN Feb 1984 Harrodsburg, KY (Town Branch) Feb 1985 Indian Creek, Corydon, IN Aug 1985 Jackson, KY (North Fork Kentucky River) Jul 1985 Mill Creek, Jefferson County, KY Jun 1985 Muscatatuck River, Crothersville, IN Aug 1985 Neon-Fleming, KY Jul 1985 Nicholasville (Town Fork) Vicinity, KY Feb 1985 Panther Creek, Curdsville, KY Jul 1985 Plum Creek, Spencer County, KY Aug 1985 Portland, IN (Salamonie River) Apr 1985 Rough River, Hartford, Ohio County, KY Jul 1985 Saline River and Tributaries, IL Nov 1984 Triplett Creek, Morehead, KY Jul 1985 Troublesome Creek, Hindman, KY Jul 1985 Whitesburg, KY (North Fork Kentucky River) Jul 1985 Bank Revetments Eighteen Mile Island, Oldham Co., KY Aug 1985 Great Miami River, Sidney, OH Mar 1985 Licking River, Butler, KY Oct 1984 Lusk Creek, Golconda, IL Nov 1984 Little Miami River, Indian Hills, OH May 1985 Ohio River, Brandenburg, KY Jun 1985 Ohio River, Cloverport, KY Jul 1985 Ohio River, Daviess Co., KY Jul 1985 Ohio River, Hawesville, KY Jul 1985 Ohio River, Lewisport, KY Jul 1985 Ohio River, Madison, IN Aug 1985 Ohio River, Newburgh, IN Jun 1985 Ohio River, Ohio Street, Evansville, IN May 1984 Ohio River, Otter Creek Park, KY Jun 1985 Ohio River, Rabbit Hash, Boone Co., KY May 1985 Ohio River, Rockport Landing, IN Jun 1985 Ohio River, Sellersburg, IN Jan 1984 Ohio River, SR 66, Cannelton, IN Dec 1983 Ohio River, Troy, IN Jun 1985 Ohio River, Upper River Rd., Jefferson Co., KY Jun 1985 Ohio River, Vanderburg Co., IN May 1984 Patoka River at Jasper, IN Apr 1985 Patoka River, Winslow, IN Jun 1985 Stoner Creek, North Middletown, KY Jul 1985 Wabash River near Merom, IN Apr 1985 Wabash River, New Harmony, IN Jun 1984 White River, Brownstown, IN Apr 1985 White River, Pike Co., IN Apr 1985 Whitewater River, Levee Rd., IN Nov 1984 WTP, Great Miami River, Ross, OH May 1985 24-30 LOUISVILLE, KY. DISTRICT TABLE 24-L FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION (See Section 37 of Text) Fiscal Year Cost Jobs Bill' Total Flood Control: Canoe Creek at Henderson, KYs 6 $20,266 $44,526 Camp Run, Sellersburg, IN3 -34,660 Chaplin River, Perryville, KY' 18,559 18,570 Duck Creek, Elwood, IN'4 - 5,622 Kentucky River, Letcher Co., KY' -12,500 Lancassage Creek, Clark Co., IN4 - 9,296 Little Beaver Creek, Kettering, OH4 -64,653 Lyford Levee, IN3 -25,152 Old Sulphur Cr., Orleans, IN' -33,471 Pipe Creek, Alexandria, IN' -33,505 Salyersville, KY' -2,191 Sugar Creek, Bellbrook, OH3 -39,556 Whitewater River, Hagerstown, IN4 6,113 Snagging and Clearing for Flood Control: E.F. White River, Medora, IN' - 3,988 Lick Creek, Hartford City, IN 5 - 3,364 Salamonie River, Montpelier, IN' - 10,039 Emergency Bank Protection: Dry Run Creek, South Lebanon, OH' - 2,484 E.F. White River, New Elizabethtown, IN' - 7,486 E.F. White River, Portersville, IN' - 7,492 Ft. Massac State Park, IL' - 21,522 Green River, Calhoun, KY5 - 9,513 Little Wabash River, Louisville, IL' - 278 Ohio River, Daviess Co., KY6 ' 18 18 Ohio River, Owensboro, KY6 7 53 53 Ohio River, Vanderburgh Co., IN2 - 7,499 Skillet Fork, Wayne Co., IL' - 28 Whitewater River, Honeytown, IN2 - 7,499 Whitewater River, Levee Rd., IN6 7 - 304 Whitewater River, St. Marys Road, IN' - 36 Productive Employment Appropriation Act (PL 98-8) of 1983 Initial Appraisal Summary Fact Sheet Detail Project Report Plans and Specifications Construction Funds Received Construction Completed 24-31 HUNTINGTON, WV, DISTRICT* All cost and financial statements for projects are listed at the end of this chapter. All other tables are referenced in the text and also appear at the end of this chapter. The Huntington District includes central and southeastern Ohio, all of West Virginia except the northern panhandle and northeastern portion, the eastern portion of Kentucky, a portion of midwestern Virginia, a very small portion of midwestern Virginia, a very small portion of northwestern North Carolina, embraced in the drainage basin of the Ohio River and its tributaries from approximate river mile 127 (below Pittsburgh, Pa.) to approximate river mile 438, immediately upstream from Foster, KY. The drainage area of the Huntington District is approximately 44,914 square miles. IMPROVEMENTS Page 1. Construction of Locks and Dams on Ohio River ......................................... 25-2 2. Kanawha River, WV ........................................ 25-2 3. Open Channel Work, Ohio River .................... 25-2 4. Other Authorized Navigation Projects .......................................... 25-2 Flood Control 5. Alum Creek Lake, OH ..................................... 25-2 6. Beech Fork Lake, WV ...................................... 25-2 7. Bluestone Lake, Ohio River Basin, W V .............................................. 25-3 8. Burnsville Lake, Ohio River Basin, W V .............................................. 25-3 9. Chillicothe, OH ................................................ 25-3 10. Deer Creek Lake, Ohio River Basin, OH ...................................... 25-4 11. Delaware Lake, Ohio River Basin, OH .............................................. 25-4 12. Dewey Lake, Ohio River Basin, KY .............................................. 25-4 13. Dillon Lake, Ohio River Basin, OH .............................................. 25-5 14. East Lynn Lake, Ohio River Basin, WV ...................................... 25-5 15. Fishtrap Lake, Ohio River Basin, KY ............ 25-5 16. Grayson Lake, KY ............................................ 25-5 17. John W. Flannagan Dam and Reservoir, Ohio River Basin,VA ...................... 25-6 18. Levisa and Tug Forks of the Big Sandy River and Cumberland River, KY, WV and VA .................................... 25-6 19. M assillon, OH .................................................. 25-6 20. Muskingum River Lakes, OH .......................... 25-7 21. N ewark, OH ..................................................... 25-7 22. North Branch of Kokosing River Lake, OH ................................................ 25-7 23. North Fork of Pound River Lake, VA ............ 25-8 24. Ohio River Basin (Huntington District) ........ 25-8 25. Paint Creek Lake, Ohio River Basin, Ohio ............................................ 25-8 26. Paintsville Lake, KY ........................................ 25-8 27. R.D. Bailey Lake, WV ...................................... 25-9 28. Roseville, OH ................................................... 25-9 29. Summersville Lake, Ohio River Basin, W V .............................................. 25-9 30. Sutton Lake, Ohio River Basin, W V ....................................................... 25-10 31. Tom Jenkins Dam, Ohio River Basin, OH ............................................ 25-10 32. Yatesville Lake, KY ....................................... 25-10 33. Inspection of Completed Flood Control Projects .................................... 25-11 34. Flood Control Work Under Special Authorization ..................................... 25-11 General Investigations 35. Surveys ........................................................... 25-11 36. Collection and Study of Basic Data ............... 25-11 Tables Table Table Table 25-A 25-B 25-C Table 25-D Table 25-E Table Table Table 25-F 25-G 25-H Cost & Financial Statement .......... 25-12 Authorization Legislation .............. 25-16 Other Authorized Navigation Projects ........................ 25-19 Not Applicable Other Authorized Flood Control Projects .............................. 25-20 Not Applicable Deauthorized Projects ..................... 25-21 Inspection of Flood Control Projects .............................. 25-22 25-1 Navigation Page REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Navigation 1. CONSTRUCTION OF LOCKS AND DAMS ON THE OHIO RIVER See this heading under Chapter 22 - Ohio River 2. KANAWHA RIVER, WV Location. The Kanawha River is approximately 97 miles in length and is formed by the junction of the New and Gauley Rivers, a short distance above Kanawha Falls, WV, and flows generally northwesterly to the confluence with the Ohio River at Point Pleasant, WV. Previous projects. For details of previous projects see the Annual Reports for 1875,1915 and 1938. Existing project. The existing project consists of three navigation structures on the Kanawha River. London Locks and Dam are located approximately 83 miles above the mouth of the Kanawha River and approximately two miles downstream from Montgomery, WV. Marmet Locks and Dam are located approximately 68 miles above the mouth of the Kanawha River at Marmet, WV. Winfield Locks and Dam are located approximately 31 miles above the mouth of the Kanawha River at Winfield, WV. Each structure has twin locks with usable dimensions of 56 feet by 360 feet. Another structure is located on the Ohio River at approximate river mile 279 and approximately nine miles below Gallipolis, OH. This structure has two parallel locks, the main lock is 110 feet by 360 feet. This system of locks and dams provides a navigable depth of nine feet from the mouth of the Kanawha River to a point approximately 91 miles upstream. The existing project was completed at a cost of $23,403,201. Construction was initiated in 1931 and completed in 1937. For further cost details see Table 25-B, see also, Appendix C. Local cooperation. None required. Terminal facilities. There are 79 terminals along the Kanawha River located from the mouth of the river to 30 miles east of Charleston, WV. These terminals are constructed principally of steel and wood mooring piles and steel pile mooring cells. Seventeen ofthese terminals have railroad connections. One terminal, a paved wharf, is owned by the City of Charleston, WV. The remaining terminals are privately owned. The principal commodities handled are coal, chemicals, acids, cement, gasoline and oil, and sand and gravel. For further details see the 1962 Annual Report. Operations during the fiscal year. The Locks and Dams were operated as required and necessary repairs and improvements were made to the locks and dams as well as to the appurtenant structures and grounds. Channel inspections were conducted periodically. 3. OPEN CHANNEL WORK, OHIO RIVER See this heading under Chapter 22 - Ohio River. 4. OTHER AUTHORIZED NAVIGATION PROJECTS See Table 25-C. 5. ALUM CREEK LAKE, OH Location. The damsite is located in Delaware County, OH, on Alum Creek, a tributary of Big Walnut Creek, approximately 26 miles above the mouth of Alum Creek and 15 miles north of Columbus, OH, and approximately 157 miles above the mouth of the Scioto River. Existing project. The existing project consists of a rolled earthfill dam 93 feet in height and 10,000 feet in length with a gate controlled spillway located in the right abutment. The reservoir provides a total storage of 134,800 acre-feet and controls a drainage area of approximately 123 square miles. See also Appendix A. Construction of the dam and appurtenant works was initiated in August 1970 and completed in July 1974. The 405 tracts of land required for the project have been acquired. The estimate for new work is $56,335,000 which is to be appropriated and expended by the Federal Government. The Sponsor will reimburse the Government an estimated $27,880,000, exclusive of interest, for cost allocated to water supply. Local cooperation. For details of required local cooperation see the 1981 Annual Report. Operations during the fiscal year. New Work: Engineering activities for the remaining work items continued. The project is essentially complete, except for minor work items such as landscaping and cleanup. Operations and Maintenance. The project was operated for the benefit of flood control as required, and necessary repairs were made to the structure and appurtenances. During the fiscal year the project prevented flood damages estimated to be $254,000. To date, the project has prevented an estimated $37,087,000 in flood damages. 6. BEECH FORK LAKE, WV Location. The damsite is located in Wayne County, WV., on Beech Fork Creek, a tributary of Twelvepole Creek, approximately four miles above the mouth of Beech Fork Creek and 20 miles above the confluence of Twelvepole Creek and the Ohio River. 25-2 HUNTINGTON WEST VIRGINIA DISTRICT Existing project. The existing project consists of a rolled earth-fill dam 86 feet in height and 1,080 feet in length, an uncontrolled spillway landward of the left abutment of the dam with a control structure at the upstream end. The reservoir provides a total storage of 37,540 acre-feet and controls a drainage area of approximately 78 square miles. Construction of the dam was initiated in December 1972 and completed in February 1977. See also Appendix A. The 485 tracts of land required for the project have been acquired. The full funding estimate for new work is $42,400,000. Local cooperation. None required. Operations during the fiscal year. New Work: Engineering activities for remaining work items continued. The project is essentially complete, except for remaining recreation facilities, landscaping and cleanup. Operations and maintenance. The project was operated for flood control as required and necessary repairs were made to the structure and appurtenances. To date the project has prevented an estimated $2,678,000 in flood damages. 7. BLUESTONE LAKE, OHIO RIVER BASIN, WV Location. The damsite is located on the New River in Summers County, WV., approximately three miles above Hinton, WV and one mile from the confluence of the New and Greenbrier Rivers. The reservoir is located in Summers County, WV and Giles County, VA. Existing project. The existing project consists of a concrete gravity dam 180 feet in height and 2,048 feet in length. Appurtenant structures consist of a gated spillway 790 feet in length located in the channel section of the dam. The stilling pool is formed by a 23 foot highweir located 364 feet downstream of 16 gated sluices through the spillway section and discharging into the stilling pool. Penstocks were installed at the time of construction to permit the future installation of hydropower. The reservoir provides for a total storage of 631,000 acre-feet. See also Appendix A. Construction of the dam was initiated in January 1942 and completed in April 1952. A total of 338 tracts of land was acquired for the project. The Federal cost of the project was $29,458,652, which includes expenditures under the recreation at completed projects program. For further details see the 1939 and 1962 Annual Reports. Local cooperation. None required. Operations during the fiscal year. Operations and Maintenance. The entire project is complete. The reservoir was operated for flood control as required and necessary repairs were made to the structure and appurtenances. The project prevented flood damages estimated to be $117,000 during the fiscal year. To date, the project has prevented an estimated $534,351,000 in flood damages. 8. BURNSVILLE LAKE, OHIO RIVER BASIN, WV Location. The damsite is located in Braxton County WV, on the LIttle Kanawha River, approximately two miles above Burnsville, WV, and 124 miles above the confluence of the Little Kanawha River and the Ohio River. Existing project. The existing project consists of an earth embankment dam 80 feet in height and 1,000 feet in length with a gated spillway in the left abutment. The outlet works is an integral part of the spillway, consisting of five sluice gates and one low flow sluice. The reservoir provides for a total storage of 65,400 acre-feet and controls a drainage area of approximately 165 square miles. Construction of the dam was initiated in June 1973 and completed in February 1976. See also Appendix A. The 357 tracts of land required for the project have been acquired. The estimate for new work is $56,200,000. Local cooperation. None Required. Operations during the fiscal year. The project is essentially completed except for remaining recreation facilities, landscaping and cleanup. The project was operated for flood control as required and necessary repairs were made to the structure and appurtenances. To date, the project has prevented an estimated $16,687,000 in flood damage. 9. CHILLICOTHE, OH Location. The project is located in Ross County, OH, along the right bank of the Scioto River, approximately 69 miles above the confluence with the Ohio River. Existing project. The existing project provides for the construction of 10,805 feet of earth levee, four gate openings and four pump stations. The estimate for new work is $20,330,100 which is to be allocated and expended by the Federal Government. The project is complete except for landscaping and final clean up. The estimated non-Federal cost is $2,430,000. Construction of the project was initiated in June 1975 and became operational for flood control in May 1983. Local cooperation. All requirements for local cooperation are complete. For further details see the 1978 Annual Report. 25-3 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Operations during the fiscal year. New Work: The final contract for Local Protection (Part IV) and Landscape Planting is complete. To date the project has prevented an estimated $10,000 in flood damages. 10. DEER CREEK LAKE, OHIO RIVER BASIN, OH Location. The damsite is located in Pickaway County, approximately seven miles south of Mount Sterling, OH on Deer Creek, a tributary of the Scioto River, approximately 21 miles above the mouth of Deer Creek and approximately 106 miles above the mouth of the Scioto River. Existing project. The existing project consists of a rolled earth-filled dam 93 feet in height and 3,880 feet in length, a 741 foot concrete gravity channel section controlled by three tainter gates, an outlet works consisting of five gated sluices through a concrete spillway section discharging into a stilling basin and an earth dike 15 feet by 4,600 feet in a saddle located approximately four miles southwest of the damsite. The reservoir provides a total storage of 102,540 acre-feet and controls a drainage area of approximately 278 square miles. Construction of the dam was completed in May 1968. The 138 tracts of land required for the project have been acquired. For further project details see the 1965 Annual Report. See also Appendix A. The Federal cost of the project is $20,406,545, including expenditures under the recreation at completed projects program. Local cooperation. For details of required local cooperation see the 1981 Annual Report. Operations during the fiscal year. Operations and Maintenance. All construction work is complete. The reservoir was operated for flood control as required and necessary repairs were made to the structure and appurtenances. The project prevented an estimated $357,000 in flood damages during the fiscal year. To date, the project has prevented an estimated $16,208,000 in flood damages. 11. DELAWARE LAKE, OHIO RIVER BASIN, OH Location. The damsite is located on the Olentangy River, approximately six miles above and north of Delaware, OH, and approximately 32 miles above the confluence of the Olentangy and Scioto Rivers at Columbus, OH. The reservoir is located in Delaware, Marion and Morrow Counties, OH. Existing project. The existing project consists of a rolled earth-fill dam with a gate controlled ogee type spillway and five outlet conduits in the channel. The dam is 18,600 feet in length and 92 feet in height. The project provides for storage of 132,800 acre-feet and controls a drainage area of approximately 381 square miles. Construction of the dam was initiated in April 1946 and completed in July 1948. For further details see the 1962 Annual Report. See also Appendix A. Total real estate requirements of 7,703 acres of fee acquisition and 2,428 acres of flowage easements have been completed. The Federal cost for the project was $7,631,821. Local cooperation. None required. Operations during the fiscal year. Operations and Maintenance. All construction work is complete. The reservoir was operated for the benefit of flood control as required, and necessary repairs were made to the structure and appurtenances. The project prevented an estimated $1,134,000 in flood damages during the fiscal year. To date, the project has prevented an estimated $53,811,000 in flood damages. 12. DEWEY LAKE, OHIO RIVER BASIN, KY Location. The damsite is located on Johns Creek, approximately seven miles southeast of Paintsville, KY and approximately six miles above the confluence of Johns Creek and the Levisa Fork of the Big Sandy River. Existing project. The existing project consists of an earthfill dam 118 feet in height and 913 feet in length, a controlled outlet works discharging through a channel excavated in the left abutment, and a rolled earth-fill dike blocking a low divide to Brandykeg Creek and the Levisa Fork. The reservoir provides a total storage of 93,300 acre-feet and controls a drainage area of approximately 207 square miles. Construction of the dam was initiated in March 1946 and completed in July 1949. For further project detail see the 1965 Annual Report. See also Appendix A. Total real estate requirements for the project were 12,458 acres in fee and 1,170 acres in flowage easements. The Federal cost of the project was $7,845,547, including expenditures for recreation under the completed project program. Local cooperation. None required. Operations during the fiscal year. Operations and Maintenance. All construction activities are complete. The reservoir was operated for the benefit of flood control as required and necessary repairs were made to the structure and appurtenances. The project prevented an estimated $39,000 in flood damages during the fiscal year. To date, the project has prevented an estimated $52,319,000 in flood damages. 25-4 HUNTINGTON WEST VIRGINIA DISTRICT 13. DILLON LAKE, OHIO RIVER BASIN, OH Location. The damsite is located on the Licking River, approximately six miles above the confluence of the Licking and Muskingum Rivers at Zanesville, Ohio. Existing project. The existing project consists of a rolled earth-fill dam 118 feet in height and 1,400 feet in length, a controlled outlet works discharging through a 20-foot conduit in the right abutment, and an ungated 280-foot spillway adjacent to the left abutment of the dam, and two rolled earthfill dikes. The reservoir provides for a total storage of 261,110 acre-feet and controls a drainage area of approximately 748 square miles. Construction of the dam was completed in July 1959. For further project details see the 1962 Annual Report. See also Appendix A. Total real estate required for the project consists of 8,232 acre in fee and 5,380 acres of flowage easements. See also Appendix A. Federal cost of the project was $30,218,135. Local cooperation. None required. Operations during the fiscal year. Operations and Maintenance. All construction work is complete. The project was operated as required for flood control, and necessary repairs were made to the structure and appurtenances. The project prevented an estimated $5,931,000 in flood damages during the fiscal year. To date, the project has prevented an estimated $97,971,000 in flood damages. 14. EAST LYNN LAKE, OHIO RIVER BASIN, WV Location. The damsite is located in Wayne County, WV approximately six miles southeast of Wayne, WV, 10 miles above the mouth of East Fork and 42 miles above the confluence of Twelvepole Creek and the Ohio River. Existing project. The existing project consists of an earth-fill dam 113 feet in height and 638 feet in length, an uncontrolled spillway near the left abutment of the dam, and a 13-foot reinforced concrete tunnel in the right abutment with a control structure at the upstream end. The reservoir provides for a total storage of 82,500 acre-feet and controls a drainage area of approximately 133 square miles. The required 552 tracts of land have been acquired. See also Appendix A. The Federal costs of the project was $37,025,968. Local cooperation. None required. Operations during the fiscal year. Operations and Maintenance. All construction work is complete. The project was operated for flood control as required and necessary repairs were made to the structure and appurtenances. To date, the project has prevented an estimated $33,766,000 in flood damages. 15. FISHTRAP LAKE, OHIO RIVER BASIN, KY Location. The damsite is located in Pike County, KY, on the Levisa Fork of the Big Sandy River, approximately 15 miles upstream from Pikeville, KY, approximately three miles above the confluence of Levisa and Russell Forks and 103 miles above the mouth of the Levisa Fork. Existing project. The existing project consists of a rock-fill dam 195 feet in height and 1,100 feet in length, a controlled spillway containing four tainter gates located in the valley wall adjacent to the left abutment of the dam, the outlet works consists of an intake structure with three conduits controlled by slide gates and discharging into a horseshoe shaped tunnel. The reservoir provides for a total storage of 164,360 acre-feet and controls a drainage area of approximately 395 square miles. The dam was completed in February 1969. The 1,301 tracts of land required for the project have been acquired. See also Appendix A. The Federal costs for new work, to date, has been $54,670,126, which includes expenditures under the recreation at completed projects program. Local cooperation. None required. Operations during the fiscal year. Operations and Maintenance. All construction work is complete. The project was operated for flood control as required, and necessary repairs wer made to the structure and appurtenances. During the fiscal year the project prevented flood damages estimated to be $25,000. To date, the project has prevented an estimated $263,222,000 in flood damages. 16. GRAYSON LAKE, KY Location. The damsite is located in Carter County, Kentucky on the Little Sandy River approximately 49 miles above the confluence with the Ohio River, and 11 miles upstream from Grayson, KY. Existing project. The existing project consists of a random earthfill dam 120 feet in height and 1,460 feet in length, a controlled outlet works discharging through a 14-foot spillway beyond the left abutment. The reservoir provides for a total storage of 119,000 acre-feet and controls a drainage area of approximately 196 square miles. The dam was completed in January 1968. The 484 tracts of land required for the project have been acquired. See also Appendix A. Federal costs for the project to date have been $19,162,741, which includes expenditures for recreation facilities under the completed projects program. 25-5 REPORT OF THE CHIEF ENGINEERS, U.S. ARMY 1985 Local cooperation. None required. Operations during the fiscal year. Operations and Maintenance. All construction work is complete. The reservoir was operated for flood control as required and necessary repairs were made to the structure and appurtenances. During the fiscal year the project prevented flood damages estimated to be $1,000. To date, the project has prevented an estimated $30,236,000 in flood damages. 17. JOHN W. FLANNAGAN DAM AND RESERVOIR, OHIO RIVER BASIN, VA Location. The damsite is located in Dickenson County, VA, approximately four miles northwest of Haysi, VA, on the Pound River approximately two miles above the confluence of the Pound River and Russell Fork and approximately 150 miles above the mouth of the Big Sandy River. Existing project. The existing project consists of a rock-fill dam 252 feet in height and 970 feet in length, an outlet tunnel located near the left abutment of the dam with a control structure at the upstream end, a spillway controlled by six tainter gates located in a saddle just upstream from the damsite. The reservoir provides for a total storage of 145,700 acre-feet and controls a drainage area of approximately 222 square miles. The project was modified to include water quality control by adding control gates to the previously uncontrolled spillway, which increased the total storage capacity by 39,000 acre-feet. The dam was completed in December 1963. The 382 tracts of land required for the project have been acquired. See also Appendix A. The Federal cost for the project, to date has been $20,444,383, which includes expenditures for recreation under the completed projects program. Local cooperation. None required. Operations during the fiscal year. Operations and Maintenance. All construction work is complete. The project was operated for flood control as required and necessary repairs were made to the structure and appurtenances. During the fiscal year the project prevented flood damages estimated to be $32,000. To date, the project has prevented an estimated $137,628,000 in flood damages. 18. LEVISA AND TUG FORKS OF THE BIG SANDY AND CUMBERLAND RIVERS, WV, VA, AND KY Location. The Levisa and Tug Forks form the Big Sandy River at Louisa, KY. The Cumberland portion is the Upper Cumberland River Basin above Cumberland Falls, KY. The basin is approximately 100 miles in length and averages approximately 30 miles in width in the lower portion and approximately 10 miles in width above Harlan, KY. The Big Sandy Basin is within the Huntington District, and the Cumberland Basin is within the Nashville District. This report covers that portion of the project located in the Huntington District. Existing project. The authorization language directs the Corps of Engineers to design and construct, at full Federal expense, such flood control measures as are determined to be necesssary and advisable for the communities in the Tug and Levisa Forks and Upper Cumberland River basins. The authorization further states that such flood control measures would be located at or in the vicinity of Pikeville, KY; and Grundy, VA on the Levisa Fork; Pineville, KY, on the Cumberland River; and Williamson and Matewan on the Tug Fork, in order to afford the named communities and other flood damaged locations and their immediate environs a level of protection against flooding at least sufficient to prevent any future losses from the likelihood of flooding such as occurred in April 1977. The full funding estimate for that portion of the authorized areas consisting of the Williamson, WV area, Pineville, KY, Barboursville, KY and other detailed studies is $221,500,000. Which includes $14,500,000 non-Federal contributions. Local cooperation. None required. Operations during the fiscal year. Additional engineering studies are now underway to determine what is necessary and advisable to address the flooding problems in both the Levisa Fork Basin and in the Tug Fork tributary stream areas. The contract for construction of the Pump Station at West Williamson, WV was awarded in April 1983 and is 65% complete. The overall project is 22% complete. 19. MASSILLON, OH Location. The project is located in Stark County, on the Tuscarawas River, approximately 200 miles above the mouth ofthe Muskingum River. Existing project. The existing project consists of channel improvement to the Tuscarawas River, combined with the construction of drainage facilities, levees and pump stations. For further details see the 1962 Annual Report. Construction was initiated in July 1940 and completed in October 1951. Local cooperation. None required. See the 1962 Annual Report for details of local contribution of work beyond the scope of the project. Operations during the fiscal year. Routine inspections were conducted to determine that the 256 HUNTINGTON WEST VIRGINIA DISTRICT improved channel was maintained in satisfactory condition. 20. MUSKINGUM RIVER LAKES, OH Location. The Muskingum River lies in Southeast Ohio and including tributaries, drains approximately 8,000 square miles. The headwaters rise about 25 miles south of Lake Erie and flow into the Ohio River at Marietta, OH, 172 miles below Pittsburgh, PA. Existing project. The existing project consists of the construction and operations and maintenance of 14 reservoirs and appurtenant works in the Muskingum River Basin. The existing project originally authorized by the Public Works Administration in February 1934. Construction of the system was initiated in January 1935 and completed in November 1938. The system was initially operated and maintained by the Muskingum Watershed Conservancy District of Ohio, the sponsoring agency, from July 1938 to August 1939 when operation and maintenance became the responsibility of the Corps of Engineers in accordance with the provisions of the 1939 Flood Control Act. For further project details, see the 1962 Annual Report. See also Appendix A. The cost of new work to date is $41,247,815, which includes expenditures for recreation facilities under the completed project program. A significant Major Rehabilitation program was approved in December 1977 in order to assure the integrity of the existing 14 structures under the originally designed maximum pool conditions. Underseepage and abutment seepage problems are being corrected through the installation of downstream blankets and/or relief wells and grouting. The estimated full funding cost of the rehabilitation program is $24,900,000. A related but separate program entitled Dam Safety Assurance has been initiated. Under current hydrologic design standards, deficiencies exist in the spillways at all the 14 projects in the system. Corrective measures include widening present spillways, constructing new spillways and installing parapet walls on top the dams. The full funding estimate for the Dam Safety Assurance Program is $72,900,000. Local cooperation. All requirements for local cooperation have been met. For further details see the 1942 Annual Report. Operations during the fiscal year. New Work. The Major Rehabilitation is continuing as scheduled. Thus far, twenty contracts have been awarded and the program is 74% complete. The Dam Safety Assurance program was initiated during FY 1982. Thus far five contracts have been awarded and the Dam Safety Assurance program is 9% complete. Operations and Maintenance. The reservoirs were operated for flood control as required, and the necessary repairs were made to the structures and appurtenances. The system prevented an estimated $57,276,000 in flood damages during the fiscal year. To date, the system has prevented an estimated $1,054,053,000 in flood damages. 21. NEWARK, OHIO Location. The project is located in Licking County at the junction of the North and South Forks of the Licking River, approximately 29 miles above the confluence with the Muskingum River at Zanesville, OH. Existing project. For details of the existing project see the 1981 Annual Report. Construction of the existing project was initiated in July 1940 and completed in November 1941. As a result of the 1968 Flood Control Act the existing project was modified to include improvement of the interior drainage facilities, construction of Log Pond Run diversion channel and modification of the North Fork Channel. Construction of the Log Pond Run diversion channel was awarded in September 1980 and completed in December 1981. The full funding estimate for the project is $9,600,000 Federal cost and $4,215,000 non-Federal. Local cooperation. For details of required and completed local cooperation see the 1981 Annual Report. Operations during the fiscal year. New Work: North Fork Channel - As a result of withdrawal of State support for the Utica Lake project (now inactive) and the interdependency of the operation of Utica with the North Fork Channel, the North Fork Channel portion of the project required re-formulation. A reanalysis is complete. Engineering studies for a contract award continued. Operations and Maintenance: Routine inspections were conducted to determine that the improved channel was maintained in satisfactory condition. 22. NORTH BRANCH OF KOKOSING RIVER LAKE, OH Location. The damsite is located in Knox County, OH, on the North Branch of Kokosing River, approximately nine miles above the confluence of the Kokosing and North Branch Rivers, and two miles northwest of Fredericktown, OH. Existing project. The existing project consists of a rolled-earth dam, 70 feet in height and 1,400 feet in length with an uncontrolled spillway adjacent to the right abutment, and an uncontrolled, reinforced concrete outlet work located in the right abutment of the dam. The reservoir provides for a total storage of 14,885 acre-feet and controls a drainage area of approximately 45 square 25-7 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 miles. the 56 tracts of land required for the project have been acquired. Construction of the dam was completed in May 1972. See also Appendix A. The Federal cost for new work to date is $6,665,985, which includes expenditures under the recreation at completed projects program. Local cooperation. None required. Operations during the fiscal year. Operations and Maintenance. All construction work is complete. Necessary repairs were made to the structure and appurtenances. 23. NORTH FORK OF POUND RIVER LAKE, VA Location. The damsite is located in Wise County, VA, on the North Fork of Pound River, approximately one mile upstream from the confluence of the North and South Forks which form the Pound River and approximately three miles upstream from Pound, VA. Existing project. The existing project consists of a rockfill dam, 130 feet in height and 600 feet in length, an uncontrolled spillway in a saddle upstream from the dam, and an outlet tunnel in the right abutment with a control structure at the upstream end. The reservoir provides a total storage of 11,300 acre-feet and controls a drainage area of approximately 17 square miles. The 127 tracts of land required for the project have been acquired. Construction of the dam was completed in January 1966. See also Appendix A. The Federal costs for the project to date is $6,186,901, which includes expenditures for recreation under the completed projects program. Local cooperation. None required. Operations during the fiscal year. Operations and Maintenance. All construction is complete. The project was operated as required for flood control and the necessary repairs were made to the structure and appurtenances. During the fiscal year the project prevented flood damages estimated to be $6,000. To date, the project has prevented an estimated $4,605,000 in flood damages. 24. OHIO RIVER BASIN (HUNTINGTON DISTRICT) Location. The work covered by this project consists of a series of levees, floodwalls, channel improvements and dams and lakes in the Ohio River Basin within the Huntington District. Existing project. The existing project consists of the individual projects considered in the Ohio River Basin comprehensive plan within the Huntington District. Operations during the fiscal year. The completed local protection pojects, which are operated and maintained by local interest, except for those local protection projects for which individual reports have been included, prevented flood damages of an estimated aggregate total of $7,988,000. 25. PAINT CREEK LAKE, OHIO RIVER BASIN, OH Location. The damsite is located in Ross County, Ohio, on Paint Creek, a tributary of the Scioto River, approximately 37 miles above the mouth of Paint Creek and 100 miles above the mouth of the Scioto River and approximately four miles east of New Parkersburg, OH. Existing project. The existing project consists of a rock and random earth fill dam, 118 feet in height and 700 feet in length, a gale controlled spillway located near the right abutment, an outlet tunnel located in the right abutment with a control structure at the upstream end, and a random rockfill dike located at the right abutment of the spillway. The reservoir provides for a total storage of 145,000 arcre-feet and controls a drainage area of approximately 576 square miles. Construction of the dam was completed in July 1973. The 257 tracts of land required for the project have been acquired. See also Appendix A. Federal costs for the project to date have been $26,969,962, which includes expenditures under the recreation at completed projects program. Local cooperation. For details of required local cooperation see the 1981 Annual Report. Operations during the fiscal year. Operations and Maintenance. All construction work is complete. The reservoir was operated for flood control as required and the necessary repairs were made to the structure and appurtenances. During the fiscal year the project prevented an estimated $660,000 in flood damages. To date, the project has prevented flood damages estimated to be $35,979,000. 26. PAINTSVILLE LAKE, KY Location. The damsite is located in Johnson County, KY, on Paint Creek, a tributary of the Levisa Fork of the Big Sandy River, approximately eight miles above the mouth of Paint Creek, and four miles west of Paintsville, KY. Existing project. The existing project consists of a rockfill dam 153 feet in height and 1,560 feet in length, an uncontrolled spillway located southwest of the right abutment of the dam, and an outlet tunnel in the right abutment with a control structure at the upstream end. The reservoir provides for a total storage of 76,642 acrefeet and controls a drainage area of approximately 93 25-8 HUNTINGTON WEST VIRGINIA DISTRICT square miles. The 635 tracts of land required for the project have been acquired. Construction of the dam was initiated in September 1976 and was completed in September 1980. See also Appendix A. The full funding estimate for new work is $60,450,000, which is to be appropriated and expended by the Federal Government. The local sponsor has reimbursed the Government $298,222 for the cost sharing portion of recreation development. Operations during the fiscal year. New Work: Construction of the project is well advanced. The remaining work items include minor highway relocations, landscaping and final cleanup. Operations and Maintenance: The reservoir was operated for flood control as required and necessary repairs were made to the structure and appurtenances. During the fiscal year the project prevented flood damages estimated to be $19,000. To date, the project has prevented flood damages estimated to be $5,586,000. 27. R. D. BAILEY LAKE, WV Existing project. The damsite is located in Wyoming County, WV, on the Guyandotte River approximately 108 miles above the confluence with the Ohio River and one mile east ofJustice, WV. Existing project. The existing project consists of a rolled rockfill dam with a concrete face, 305 feet in height and 1,330 feet in length, an uncontrolled spillway located in a saddle in the right abutment of the dam, and an outlet tunnel in the left abutment with a control structure located at the upstream end. The reservoir provides for a total storage of 203,700 acre-feet and controls a drainage area of approximately 540 square miles. Construction of the dam was initiated in November 1973 and completed in December 1979. See also Appendix A. The estimate for new work is $216,600,000. Local cooperation. None required. Condition at the end of the fiscal year. New Work: Construction of the project is well advanced. The remaining work items include remaining recreation, landscaping and cleanup. Operations and Maintenance. The reservoir was operated for flood control as required and necessary repairs were made to the structure and appurtenances. During the fiscal year the project prevented flood damages estimated to be $1,000. To date, the project has prevented flood damages estimated to be $55,808,000. 28. ROSEVILLE, OH Location. The project is located in Muskingum and Perry Counties, on Moxahala Creek, approximately six miles the confluence with Jonathan Creek, a tributary of the Muskingum River. Existing project. The existing project consists of 7,291 feet of channel improvement; 6,400 feet of levee and railroad embankment enlargements; and the necessary appurtenances for interior drainage. Total Federal cost of the project was $910,785. Construction was initiated in August 1959 and completed in October 1960. Local cooperation. All requirements for local cooperation have been completed. See also the 1962 Annual Report. Total costs of local requirements were $62,000. Operations during the fiscal year. Routine inspections of the improved portion of the project were conducted to determine that the project was maintained in satisfactory condition. 29. SUMMERSVILLE LAKE, OHIO RIVER BASIN, WV Location. The damsite is located at Ruckers Bend in Nicholas County on the Gauley River approximately 35 miles above the confluence of the Gauley and New River at Gauley Bridge, WV. Existing project. The existing project consists of a rockfill dam having a height of 357 feet and a length of 2,280 feet, an outlet tunnel in the right abutment with a control structure located at the upstream end, an uncontrolled spillway located west of the right abutment and two earthfill dikes. The reservoir provides for a total storage of 413,800 acre-feet and controls a drainage area of 803 square miles. See also Appendix A. Construction of the dam was initiated in March 1960 and completed in March 1966. A total of 9,346 acres of land were acquired for the project. The Federal costs of the project, to date, have been $48,375,884, which includes expenditures under the recreation at completed projects program. Local cooperation. None required. Operations during the fiscal year. All construction work is complete, except for minor sanitary facilities under the recreation at completed projects program. The project was operated for flood control as required and necesssary repairs were made to the structures and appurtenances. The project prevented an 25-9 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 estimated $97,000 in flood damages during the fiscal year. To date, the project has prevented an estimated $220,196,000 in flood damages. 30. SUTTON LAKE, OHIO RIVER BASIN, WV Location. The damsite is located on the Elk River in Braxton County approximately one mile above Sutton, WV and 101 miles above the mouth of the Elk River. Existing project. The existing project consists of a concrete gravity dam having a height of 220 feet and a length of 1,178 feet, a gated spillway in the channel section of the dam, comprised of six tainter gates supported by piers, an outlet works comprised of five gate sluices through the spillway section. The reservoir provides for a storage of 265,300 acre-feet and controls a drainage area of 537 square miles. See also Appendix A. Construction of the dam was initiated in September 1956 and completed in June 1960. A total of 13,154 acres of land were acquired for the project. The Federal costs of the project, to date, have been $37,034,961, which includes expenditures under the recreation at completed projects program. Local cooperation. None required. See the 1981 Annual Report for contributed funds. Operations during the fiscal year. All construction work is complete. The project was operated for flood control as required and necessary repairs were made to the structure and appurtenances. The project prevented an estimated $72,000 in flood damages during the fiscal year. To date, the project has prevented an estimated $143,375,000 in flood damages. 31. TOM JENKINS RESERVOIR, OHIO RIVER BASIN, OH Location. The damsite is located in Athens County, on the East Branch of Sunday Creek, a tributary of the Hocking River, approximately three miles north of Glouster, Ohio and 57 miles above the mouth of the Hocking River. Existing project. The existing project consists of a rolled-earth dam, 84 feet in height and 944 feet in length, a controlled works discharging through a tunnel in the left abutment, and an uncontrolled spillway in the ridge running south from the damsite. The reservoir, known as Burr Oak Lake, provides for a total storage of 26,900 acre-feet and controls a drainage area of approximately 33 square miles. See also Appendix A. Construction of the project was initiated in March 1948 and completed in February 1950. A total of 100 acres of land were acquired for the project. The Federal costs of the project were $2,086,503, which includes expenditure for recreation at completed project. Local cooperation. All requirements of local cooperation have been met, see also the 1962 Annual Report. Contributed funds in the amount of $575,000 have been received from the State of Ohio. Operations during the fiscal year. All construction work is complete. The project was operated for flood control as required and necessary repairs were made to the structure and appurtenances. During the fiscal year the project prevented flood damages estimated to be $199,000. To date, the project has prevented an estimated $9,236,000 in flood damages. 32. YATESVILLE LAKE, KY Location. The damsite is located in Lawrence County, on Blaine Creek, a tributary of the Big Sandy River, approximately five miles west of Louisa, KY and 18 miles above the mouth of Blaine Creek. Existing project. The existing project provides for the construction of an earthfill dam, 104 feet in height and 770 feet in length, an uncontrolled spillway located approximately one-half mile east of the right abutment of the dam, and an outlet tunnel through the left abutment of the dam with a control structure at the upstream end. The reservoir will provide a total storage of 86,951 acre-feet and control a drainage area of 208 square miles. The full funding estimate for new work is $90,100,000, which will be allocated and expended by the Federal Government. The sponsor will reimburse the Government an estimated $6,615,000 for the cost sharing portion of the recreation development. To date, 290 of the required 499 real estate tracts have been acquired. A contract for construction of the dam was awarded in January 1977 and was terminated for the convenience of the Government in August 1977. Operations during the fiscal year. New Work: Congress appropriated funds in fiscal year 1981 to resume project construction and work progressed until March 1981 when administration directed a deferral action which resulted in a substantial reduction in project funds and the elimination of any recommendation for funding in fiscal years 1982 and 1983. Congressional action provided fiscal year 1982, 1983, 1984 and 1985 funding for the project. The contract for Construction of Dam and Appurtenant Works, Phase I, was awarded in March 1984 and is 84% complete. Contracts with the Commonwealth and the County for relocation and/or abandonment of roads affected by the project are complete. Engineering studies for Construction of Dam, Phase II, and for Highway Relocations are well advanced. 25-10 HUNTINGTON WEST VIRGINIA DISTRICT 33. INSPECTION OF COMPLETED FLOOD CONTROL PROJECTS The flood control act of June 22, 1936 and subsequent acts require local interest to furnish assurances that they will operate and maintain certain local protection projects after completion in accordance with regulations prescribed by the Secretary of the Army. District Engineers are responsible for the administration of these regulations within their respective districts. Maintenance inspections were made during the fiscal year of those completed units transferred to local interests for operation and maintenance. Local interests were advised, as necessary, of measures required to maintain the projects in accordance with the standards prescribed by regulations. Total costs for fiscal year 1985 were $74,749. Total cost to September 30, 1985 were $1,201,067. The flood control works inspected and the dates of inspection are tabulated in Table H. 34. FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION Emergency bank protection activities pursuant to Section 14 of the 1946 Flood Control Act, Public Law 526, 79th Congress are tabulated as follows: FY 1985 Cost Kanawha River, Pt. Pleasant, WV Little Kanawha River, Glenville, WV Little Stillwater Creek, Urichsville, OH Marietta, OH $3,400 9,617 9,315 4,300 Flood control activities pursuant to Section' 205 of the 1948 Flood Control Act, Public Law 853, 80th Congress are tabulated as follows: Location Blacklick Creek, Franklin County, OH Hughes Creek, Hugheston, WV Landis Ditch, Rittman, OH Laurel Fork, Matheny, WV Leatherwood Creek, Quaker City, OH Little Hood Creek, Ashland, KY Marsh Fork, Fairdale, WV Shope Creek, Ashland, KY Spring Creek, Spencer, WV Sterling Run, Mt. Orab, OH Upper Scioto River, Marion County, OH White Road, Gallipolis, OH FY 1985 Cost $ 3,153 53,317 31,042 6,873 7,500 7,500 50,864 10,370 13,500 7,500 16,244 3,600 Snagging and clearing activities pursuant to Section 208 of the 1954 Flood Control Act, Public Law 780,83 Congress are tabulated as follows: Location FY 1985 Cost Wolf Creek, Proctorville, OH $4,075 Flood control activities pursuant to Emergency Bank Protection, Public Law 98-181 are tabulated as follows: Location Russell, KY FY 1985 Cost $268,759 Flood control and coastal emergency activities pursuant to Public Law 99, 84th Congress were conducted as required during FY 1985 at a cost of $151,221. National emergency management activities were accomplished by the district as required. The costs for these activities during FY 1985 were $149,949. 35. SURVEYS Fiscal year 1985 costs were $4,396,897 itemized as follows: Navigation Studies Flood Damage Prevention Studies Comprehensive Basin Studies Review for Deauthorization Miscellaneous Activities Coordination Studies Continuation of Planning and Engineering 36. COLLECTION AND STUDY OF BASIC DATA Fiscal year costs were $152,834. $ 665,991 1,095,817 326,277 1,969 89,583 182,870 2,034,390 25-11 Location TABLE 25-A REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 COST AND FINANCIAL STATEMENT See Total Cost Section to In Text Project Funding FY 82 FY 83 FY 84 FY 85 Sept. 30, 1985 2. Kanawha River, WV 5. Alum Creek Lake, OH 6. Beech Fork Lake, WV 7. Bluestone Lake, Ohio River Basin, WV 8. Burnsville Lake, Ohio River Basin, WV 9. Chillicothe, OH 10. Deer Creek Lake, Ohio River Basin, OH 11. Delaware Lake, Ohio River Basin, OH New Work Approp. Cost Maint. Approp. Cost Rehab. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost 619,317 63,936 4,290,000 3,945,120 2,130,000 266,351 493,900 489,002 1,245,000 1,084,855 562,000 562,079 -9,461 669,000 660,586 7,000,000 6,816,907 622,000 613,160 0 430,292 4,996,000 5,156,126 165,591 1,265,550 462,000 466,979 1,700,000 1,812,526 486,000 502,334 22,000 155,886 5,631,000 5,522,048 719,142 450,000 438,273 1,950,000 1,839,500 490,000 484,504 - 1,049 763,000 1,033,000 749,878 953,694 4,200,000 3,394,211 565,000 575,697 5,600,000 696,000 5,134,146 385,470 445,000 407,829 433,000 440,228 621,000 633,824 650,000 1,399,214 745,000 726,644 -290,000 406,093 470,000 489,691 884,000 975,000 561,287 1,150,611 - 27,853,699' - 27,853,699' 6,271,000 66,291,5842 7,008,174 66,241,2762 130,394' 130,394$ -20,300 146,538 691,000 698,086 1,200,000 1,382,433 554,000 545,316 56,313,355 56,262,081 3,839,065 3,805,846 41,841,500 41,593,765 3,924,039 3,904,384 - 29,458,6524 - 29,458,6524 1,055,000 10,980,078 1,181,993 10,958,017 -110,000 413,697 989,000 1,014,583 56,245,265 56,183,117 4,795,505 4,775,070 -85,000 20,375,099 11,278 20,360,935 447,960 446,813 334,000 481,846 20,406,5456 20,406,5455 5,255,3256 5,225,2526 7,631,821 7,631,821 6,036,7197 6,013,121' 25-12 HUNTINGTON WEST VIRGINIA DISTRICT TABLE 25-A (cont'd) COST AND FINANCIAL STATEMENT See Total Cost Section to In Text Project Funding FY 82 FY 83 FY 84 FY 85 Sept. 30, 1985 12. Dewey Lake, Ohio River Basin, KY 13. Dillon Lake, Ohio River Basin, OH 14. East Lynn Lake, Ohio River Basin, WV 15. Fishtrap Lake, Ohio River Basin, KY 16. Grayson Lake, KY New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost 17. John W. Flannagan New Work Dam & Reservoir, Approp. Ohio River Basin, Cost VA Maint. Approp. Cost 18. Levisa & Tug Forks New Work of the Big Sandy & Approp. Cumberland Rivers, Cost KY,WV, & VA 19. Massillon, OH New Work Approp. Cost Maint. Approp. Cost - - - 7,845,5478 - - - - 7,845,5478 624,200 774,500 920,000 1,235,000 10,535,9769 646,564 794,093 848,817 1,281,093 10,505,5589 - - - - 30,218,135 - - - 30,218,135 228,000 425,000 380,000 597,000 4,104,84310 225,591 373,508 376,678 631,304 4,098,12810 201,205 809,920 791,773 106,000 22,818 685,000 658,909 7,143 75,556 630,000 624,091 147,000 44,791 798,200 712,410 2,200,000 2,348,307 83,884 37,025,968 27 37,025,968 850,100 837,000 973,000 8,168,90711 855,404 811,006 984,952 8,110,36011 73,410 945,000 861,546 -1,967 7,805 1,175,000 1,140,831 - 54,670,12612 - 54,670,12612 869,000 5,330,198' 3 992,134 5,290,93113 0 - - 13 - - 649,400 720,000 694,000 682,100 606,442 785,280 87,234 753,010 807,226 -14,215 759 681,000 677,713 19,162,741' 4 19,162,74114 7,334,070 7,297,363 - 20,444,383 ' 5 - 20,444,38315 674,000 8,513,86216 732,210 * 8,498,86216 3,800,000 8,800,000 1,600,000 5,140,000 23,340,000 2,548,242 3,595,244 4,744,091 8,063,946 21,942,915 - - - 8,139,406' 7 - - - - 8,139,40617 11,000 11,004 17,000 16,988 12,000 12,013 18,000 17,999 280,508 280,507 25-13 REPORT OF THE CHIEF OF ENGINEERS U.S. ARMY 1985 TABLE 25-A (cont'd) COST AND FINANCIAL STATEMENT See Total Cost Section to In Text Project Funding FY 82 FY 83 FY 84 FY 85 Sept. 30, 1985 20. Muskingum River Dams & Lakes, OH 21. Newark, OH (Previous Project) (Existing Project) 22. North Branch of Kokosing River Lake, OH 23. North Fork of Pound River Lake, Ohio River Basin, VA 24. Ohio River Basin 25. Paint Creek Lake, Ohio River Basin, OH 26. Paintsville Lake, KY 27. R. D. Bailey Lake, WV New Work Approp. Cost Maint. Approp. Cost Rehab. Approp. Cost Dam Safety Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost -2,879 - - 1,501 - - 4,459,300 3,750,000 4,380,000 4,613,985 3,950,351 4,067,444 3,720,000 1,425,000 1,550,000 4,182,532 1,144,622 1,344,317 1,430,000 2,950,000 1,600,000 1,293,342 2,240,704 1,673,128 16,000 23,000 15,997 23,001 760,000 291,352 785,454 272,524 - - 131,000 126,000 144,677 109,505 331,200 199,000 329,040 206,535 6,891 439,000 433,330 -15,591 15,182 496,700 457,113 4,080,000 6,285,000 3,401,394 7,019,206 314,000 420,500 314,166 416,231 6,000,000 5,793,813 642,000 643,987 5,800,000 6,017,764 735,000 759,759 26,000 26,002 300,000 350,514 94,000 103,989 313,000 296,015 425,000 475,195 3,790,000 3,273,809 505,000 486,911 15,600,000 14,817,521 1,575,000 1,541,382 4,118,000 4,347,427 1,636,000 2,248,347 900,000 1,312,092 17,377 17,377 134,000 251,472 103,000 109,710 255,000 268,505 415,000 435,438 1,721,000 1,693,268 573,000 579,651 9,250,000 10,295,735 1,034,000 1,042,399 41,247,81518 41,247,81518 52,934,07019 52,761,88219 18,542,9452o 18,299,1082 6,880,000 6,519,267 845,916 845,916 702,142 702,142 5,474,727 5,472,982 6,665,98521 6,665,98521 1,285,017 1,281,291 6,186,90122 6,186,90122 4,641,35923 4,631,83123 355,86124 355,86124 26,969,96225 26,969,9625 4,182,95626 4,169,28426 57,782,788 57,111,366 1,955,500 1,936,598 215,972,23327 215,686,47227 5,540,81428 5,496,31128 25-14 HUNTINGTON WEST VIRGINIA DISTRICT TABLE 25-A (cont'd) COST AND FINANCIAL STATEMENT See Total Cost Section to In Text Project Funding FY 82 FY 83 FY 84 FY 85 Sept.30, 1985 28. Roseville, OH New Work Approp. - - - - 910,785 Cost - - - - 910,785 Maint. Approp. 6,000 5,000 7,000 10,000 128,968 Cost 5,998 4,999 7,003 9,998 128,966 29. Summersville Lake, New Work Ohio River Basin, Approp. 42,879 - 7,183 -10,000 48,375,88429 WV Cost 81,223 11,682 7,598 17,895 48,375,88429 Maint. Approp. 1,789,920 1,940,000 1,119,000 982,000 12,405,91430 Cost 1,667,124 2,103,955 1,087,885 1,046,276 12,359,47230 30. Sutton Lake, New Work Ohio River Basin, Approp. - - 185,000 10,000 37,034,96131 WV Cost - - 29,016 147,803 37,016,78032 Maint. Approp. 969,920 1,377,700 1,228,000 1,526,000 16,389,487"3 Cost 921,281 1,272,293 1,360,473 1,496,687 16,257,27533 31. Tom Jenkins Dam, New Work OH Approp. - - - - 2,086,503"3 Cost - - - - 2,086,503"3 Maint. Approp. 231,000 243,000 225,000 268,000 3,266,475 Cost 293,149 243,648 228,745 258,014 3,247,976 32. Yatesville Lake, New Work KY Approp. 4,000,000 4,000,000 10,000,000 15,000,000 45,044,500 Cost 481,415 1,401,135 3,508,186 5,921,767 23,097,036 1Includes $4,294,612 for new work for previous projects, $4,498,636 Emergency Relief funds, $9,004,800 Public Works funds and $686,317 Code 713 funds. 2Includes $3,883,513 for maintenance of previous projects and $546,090 Maintenance and Operation funds. 3Public Works Acceleration funds. 4lncludes $543,960 Emergency Relief funds, $9,698 Public Works Acceleration funds, $211,850 Code 711 funds and $75,000 Code 713 funds. 5Excludes $225,090 contributed funds. Includes $590,000 Code 711 funds. 6Includes $130,000 provided by the Productive Employment Act of 1983. 7Includes $240,000 provided by the Productive Employment Act of 1983. 'Includes $23,087 Public Works Acceleration funds, $1,089,94 Code 711 funds and $231,105 Code 713 funds. 9Includes $82,900 special recreation use fee funds. 10 lncludes $100,000 provided from the Productive Employment Act of 1983. 11Includes $209,918 special recreation use fee funds. 12Includes $362,649 Code 711 funds and $10,000 Code 712 funds. 13lncludes $38,000 special recreation use fees. 14Includes $406,919 Code 711 funds and $2,317 Code 713 funds. 15Includes $422,983 Code 711 funds. 16Includes $88,710 special recreation use fees. 17Includes $477,813 contributed funds. 18Includes $27,190,000 National Industrial Recovery funds and $528,288 Code 711 funds. 19lncludes $56,500 Maintenance and Operations funds. 2 includes $61,945 Public Works Acceleration funds. 2 1Includes $45,177 Code 711 funds. 22 lncludes $64,233 Code 711 funds. 23Includes $68,200 special recreation use fees. 24Includes $10,920 Emergency Relief funds. 25Includes $14,153 Code 711 funds. 26Includes $31,496 special recreation use fee funds. 27Includes $5,534 Consolidated Army funds. 'Includes $60,000 provided from the Productive Employment Act of 1983. 2Includes $300,062 Code 711 funds. 3"Includes $214,112 special recreation use fee funds and $300,000 provided from the Productive Employment Appropriations Act of 1983. slncludes $1,842,713 Code 711 funds and $287,843 Accelerated Public Works funds. Excludes $62,800 contributed funds. 32lncludes $1,824,532 Code 711 funds and $287,843 Accelerated Public Works funds. Excludes $62,800 contributed funds. 33Includes $267,634 special recreation use fee funds and $215,000 provided from the Productive Employment Appropriations Act of 1983. 'Includes $8,064 Code 711 funds and $30,000 Public Works Acceleration funds. Excludes $575,000 contributed funds. 25-15 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY, 1985 TABLE 25-B AUTHORIZING LEGISLATION See Date Section Authorizing In Text Act Project and Work Authorized Documents 2. 5. Jun. 28,1938 Dec. 22,1944 Jun. 28,1938 Dec. 22,1944 Jun. 28,1938 Dec. 22,1944 Aug. 30,1935 Oct. 23,1962 Oct. 23,1962 Jun. 28,1938 Dec. 22,1944 Jun. 28,1938 Dec. 22,1944 Oct. 23,1962 Jun. 28,1938 KANAWHA RIVER LOCKS AND DAMS, WV Construction of three locks and dams on the Kanawha River and one on the Ohio River. ALUM CREEK LAKE, OH Construction of Flood Control Reservoir. BEECH FORK LAKE, WV Construction of Flood Control Reservoir. BLUESTONE LAKE, OHIO RIVER BASIN, WV Construction of Flood Control Reservoir. Added Recreation Deleted Power BURNSVILLE LAKE, OHIO RIVER BASIN, WV Construction of Flood Control Reservoir. Added Recreation CHILLICOTHE, OH Construction of Levees and Pump Stations. DEER CREEK LAKE, OHIO RIVER BASIN, OH Construction of Flood Control Reservoir. DELAWARE LAKE, OHIO RIVER BASIN, OH Construction of Flood Control Reservoir. Added Recreation DEWEY LAKE, OHIO RIVER BASIN, OH Construction of Flood Control Reservoir. Added Recreation DILLON LAKE, OHIO RIVER BASIN, OH Construction of Flood Control Reservoir. Added Recreation 25-16 H. Doc. 31, 73rd Cong., 1st Sess. H. Doc. 587, 87th Cong., 2ndSess. H. Doc. 520, 87th Cong., 2ndSess. H. Doc. 91, 74th Cong., 2ndSess. P.L. 534, 78th Cong., 2nd Sess. Flood Control Comm. Doc. 1, 75th Cong., 1st Sess. P.L. 534 '8th Cong., 2nd. Sess. H. Doc. 587, 8th Cong., 2ndSess. Flood Control Comm. Doc. 1, 75th Cong., lstSess. Flood Control Comm. Doc. 1, 75th Cong., 1st Sess. P.L. 534, 78th Cong., 2nd Sess. Flood Control Comm. Doc. 1, 75th Cong. 1st Sess. P.L. 534, 78th Cong., 2ndSess. Flood Control Comm. Doc. 1, 75th Cong., 1st Sess. P.L. 534, 78th Cong., 2ndSess. 8. 9. 10. 11. 12. 13. TABLE 25-B (cont'd) HUNTINGTON WEST VIRGINIA DISTRICT AUTHORIZING LEGISLATION See Date Section Authorizing In Text Act Project and Work Authorized Documents 14. Jun. 28,1938 Dec. 22,1944 15. Jun. 28,1938 Dec. 22,1944 16. Jul. 14,1960 17. Jun. 28,1938 Dec. 22,1944 18. Oct. 1, 1980 19. Jun. 28,1938 20. Feb. 20,1934 Jun. 28,1938 Aug. 11, 1939 21. Jun. 28,1938 Aug. 13,1968 22. Oct. 23,1962 23. Jul. 14, 1960 EAST LYNN LAKE, OHIO RIVER BASIN, WV Construction of Flood Control Reservoir. Added Recreation FISHTRAP LAKE, OHIO RIVER BASIN, KY Construction of Flood Control Reservoir. Added Recreation GRAYSON LAKE, KY Construction of Flood Control Reservoir. JOHN W. FLANNAGAN DAM AND RESERVOIR, OHIO RIVER BASIN, VA Construction of Flood Control Reservoir. Added Recreation LEVISA AND TUG FORKS OF THE BIG SANDY RIVER, AND CUMBERLAND RIVER, KY, WV Construction of such Flood Control Measures as deemed Necessary and Advisable. MASSILLON, OHIO Construction of Channel Improvement Project. MUSKINGUM RIVER LAKES, OH Construction of 14 Flood Control Reservoirs. Reimbursement to the Muskingum Conservancy District a sum not to exceed actual expenditures for project construction. Operations and Maintenance assigned to the Corps of Engineers. NEWARK, OHIO Construction of Channel Improvement Project. Modification to Existing Project and Additional Channel Improvement and Drainage Facilities. NORTH BRANCH OF KOKOSING RIVER LAKE, OH Construction of Flood Control Reservoir. NORTH FORK OF POUND RIVER LAKE, VA Construction of Flood Control Reservoir. Flood Control Comm. Doc. 1, 75th Cong., 1st Sess. P.L. 534, 78th Cong., 2nd Sess. Flood Control Comm. Doc. 1, 75th Cong., 1st Sess. P.L. 534, 78th Cong., 2nd Sess. H. Doc. 440, 86th Cong., 2nd Sess. Flood Control Comm. Doc. 1, 75th Cong., lstSess. P.L. 534, 78th Cong., 2nd Sess. Sect. 202, P.L. 367, 96th Cong., 2nd Sess. Flood Control Comm. Doc. 1, 75th Cong., 1st Sess. Public Works Admin. Flood Control Comm. Doc. 1, 75th Cong., 1st Sess. P.L. 396, 76th Cong., 1st Sess. Flood Control Comm. Doc. 1, 75th Cong., 1st Sess. H. Doc. 337, 90th Cong., 2nd Sess. H. Doc. 220, 87th Cong., 2nd Sess. H. Doc. 645, 86th Cong., 2nd Sess. 25-17 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY, 1985 TABLE 25-B (cont'd) AUTHORIZING LEGISLATION See Date Section Authorizing in Text Act Project and Work Authorized Documents 25. Jun. 28,1938 Dec. 22,1944 Oct. 27,1965 Oct. 23,1962 Jun. 28,1938 Jun. 28,1938 Dec. 22,1944 Jun. 28,1938 Dec. 22,1944 Dec. 22,1944 Oct. 27,1965 Jun. 22,1936 PAINT CREEK LAKE, OHIO RIVER BASIN, OH Construction of Flood Control Reservoir. Added Recreation PAINTSVILLE LAKE, KY Construction of Flood Control Reservoir. R. D. BAILEY LAKE, WV Construction of Flood Control Reservoir. ROSEVILLE, OH Construction of Channel Improvement Project. SUMMERSVILLE LAKE, OHIO RIVER BASIN, WV Construction of Flood Control Reservoir. Added Recreation SUTTON LAKE, OHIO RIVER BASIN, WV Construction of Flood Control Reservoir. Added Recreation TOM JENKINS DAM, OHIO RIVER BASIN, OH Construction of Flood Control Reservoir. YATESVILLE LAKE, KY Construction of Flood Control Reservoir. INSPECTIONS OF COMPLETED FLOOD CONTROL PROJECTS Inspection of Local Maintenance of Federally Constructed Local Protection Projects. 25-18 Flood Control Comm. Doc. 1, 75th Cong., 1st Sess. P.L. 534, 78th Cong., 2nd Sess. H. Doc. 246, 89th Cong., 1st Sess. H. Doc. 569, 87th Cong., 2nd Sess. Flood Control Comm. Doc. 1, 75th Cong., 1st Sess. Flood Control Comm. Doc. 1, 75th Cong., 1st Sess. P.L. 534, 78th Cong., 2nd Sess. Flood Control Comm. Doc. 1, 75th Cong., 1st Sess. P.L. 534, 78th Cong., 2ndSess. H. Doc. 762, 78th Cong., 2ndSess. H. Doc. 246, 89th Cong., 2nd Sess. P.L. 738, 74th Cong., 1st Sess. 26. 27. 28. 29. 30. 31. 32. 33. HUNTINGTON WEST VIRGINIA DISTRICT TABLE 25-C OTHER AUTHORIZED NAVIGATION PROJECTS For Last Full Report Operation Contributed See Annual and Funds Project Report For Construction Maintenance Expended Big Sandy River WV and KY including Levisa and TugForks 1952 1,586,236 1,569,8111 131,473 Elk River, WV . 1903 30,259 Gauley River, WV4 1903 14,761 Guyandotte River, WV5 1915 27,500 Little Kanawha River, WV6 1960 470,536 1,023,854 Muskingum River, OH7 1955 301,912 6,171,897 6,041 New River, WA and VA5 1899 109,691 Scioto River at Portsmouth, OH 8 1953 10,951 16,593 In addition, $140,068 expended from funds transferred from Department of Commerce, under accelerated public works program, for repairs of eroded bank at lock 3 on Big Sandy River, at Louisa, KY. 2Operation and Maintenance suspended June 30,1952. 'Work closed September 1902. Property transferred to Kanawha River improvements. 4Work closed September 1902. Abandonment recommended in H. Doc. 467, 69th Congress. 5Work suspended. 6Operation and maintenance suspended June 30, 1951. 7Collections from license non-Federal hydroelectric utilities for use of dams on Muskingum River for fiscal years 1923-1953 were $79,154. 8Private Law 954, August 31, 1954, authorized Secretary of Treasury to pay Portsmouth sand and Gravel Co. $75,000 in full settlement of claims against Government for damages resulting from change in Scioto River Channel. 25-19 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY, 1985 TABLE 25-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS For Last Full Report Operation Contributed See Annual and Funds Project Report For Construction Maintenance Expended Completed Local Protection Projects Ashland, KY 1954 3,718,839 - - Athens, OH 1979 5,313,700 - - Cattletsburg, KY 1963 3,854,361 - - Ceredo-Kenova, WV 1955 2,753,551 - - East Rainelle, WV 1962 614,598 - - Galax, VA 1953 480,536 - - Huntington, WV 1956 7,172,840 - - Ironton, OH 1952 2,604,646 - - Maysville, KY 1959 6,493,747 - - Parkersburg, WV 1955 6,652,827 - - Pt. Pleasant, WV 1955 2,919,578 - - Portsmouth-New Boston, OH 1956 9,806,424 - - Princeton, WV 1962 808,750 - - Russell, KY 1953 552,493 - - Williamson, WV 1964 1,056,166 - - Inactive Local Protection Projects Augusta, KY - 11,577 - - Burlington, OH - - - - Chesapeake, OH - - - - Coal Grove, OH - 3,389 - - Coal River, WV 1979 472,229 - - Dover, KY - - - - Fullerton, KY - - - - Greenup, KY - 4,962 - - Lower Guyandotte River Basin, WV - 17,721 - - Miller, OH - - - - Normal, KY - - Proctorville, OH - - - - Ravenswood, WV - - - - South Point, OH - - - - South Portsmouth, KY - - - - Vanceburg, KY - - - Deferred Local Protection Projects Newark, OH (Interior Drainage) 1983 - - - Oceana, WV 1981 611,000 - - Inactive Reservoirs and Lakes Haysi, VA - 2,656 - - Leading Creek, WV 1974 272,880 - - Panther Creek, WV 1976 22,879 - - Salt Creek, OH 1975 1,089,943 - - Utica, OH 1975 757,550 - - West Fork, WV 1974 663,192 - - Deferred Reservoir and Lakes Birch, WV .... Kehoe Lake, KY 1981 1,272,740 - - Logan, OH -... Moores Ferry, WV -... Active Authorized Projects with no current year expenditures. Martin, KY 1983 212,048 25-20 HUNTINGTON WEST VIRGINIA DISTRICT TABLE 25-G DEAUTHORIZED PROJECTS All projects listed in this table have been deauthorized in accordance with Section 12 of the Water Resources Development Act of 1974, P.L. 251, 93rd Congress. For Last Full Report Federal Contributed See Annual Funds Funds Local Protection Projects Report For Date Expended Expended Aberdeen, OH - May 1981 1,334 - Athalia, OH - Aug 1977 - - Belpre, OH - Nov 1977 - - Brooklyn, WV - Nov 1979 - - Buena Vista, OH - Aug 1977 - - Chambersburg, OH - Aug 1977 - - Cheshire, OH - Nov 1977 - - Chilo, OH - Aug 1977 - - Clifton, WV - Aug 1977 11,237 - Columbus, OH - Aug 1977 - - Friendly, WV - Aug 1977 - - Gallipolis, OH - Aug 1977 - - Hanging Rock, OH - Aug 1977 - - Hartford, WV - Aug 1977 - - Henderson, WV - Aug 1977 - - Higginsport, OH - Oct 1978 - - Hockingport, OH - Aug 1977 - - Letart, WV - Aug 1977 - - Letart Falls, OH - Aug 1977 - - Manchester, OH - May 1981 - - Mapleshade, OH - Oct 1978 - - Marietta, OH - Nov 1981 - - Mason, WV - Aug 1977 - - Middleport, OH - May 1981 9,783 - Millwood, WV - Aug 1977 - - New Martinsville, WV - Nov 1979 - - New Matamoras, OH - Aug 1977 - - Newport, OH - Aug 1977 - - Pomeroy, OH - Aug 1977 - - Portland, OH - Aug 1977 - - Racine, OH - Aug 1977 - - Ripley, OH - Oct 1978 7,523 - Riverview, WV - Aug 1977 - - St. Mary's, WV - Aug 1977 - - Sardis, OH - Aug 1977 - - Sciotoville, OH - Aug 1977 - - Sistersville, OH - Aug 1977 - - Syracuse, OH - Aug 1977 - - Waverley, WV - Aug 1977 - - Williamstown, WV - Nov 1979 - - Zanesville, OH - May 1981 - - Reservoirs and Lakes Big Bend, WV - Aug 1977 - - Big Darby, OH 1969 Nov 1979 3,349,568 - Frazeysburg, OH - May 1981 5,000 - Millersburg, OH - May 1981 - - Mill Creek, OH 1981 Nov 1981 1,602,702 - Mud River, WV - Nov 1979 - - Poca, WV - May 1981 - - Rocy Fork, OH 1950 Aug 1977 91,321 - White Oak Creek, OH - Nov 1981 - - 25-21 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY, 1985 TABLE 25-H INSPECTION OF FLOOD CONTROL PROJECTS - See Section 33 of Text Flood Control Works Inspected Dates of Inspection Ashland, KY Oct 85 Apr 85 Athens, OH May 85 Bramwell, WV Aug 85 Cairo, WV Aug 85 Canton (Nimishillen), OH Oct 84 Cattletsburg, KY Sep 84 Apr 85 Ceredo-Kenova, WV Apr 85 Oct 85 Chillicothe, OH Nov 84 May 85 East Rainelle, WV Aug 85 Fishing Creek, Pine Grove, WV Aug 85 Fourpole Creek, WV Jul 85 Galax, VA Aug 85 Grahn, KY Oct 84 Griffithsville-Yawkey, WV Dec 84 Hutchins, KY Oct 84 Huntington, WV Nov 84 May 85 Inez, KY Jun 84 Ironton, OH Nov 84 Jacksonsburg, Fishing Creek, WV Aug 85 Maysville, KY May 85 Oct 85 Montcalm, WV Aug 85 Newark, OH Dec 84 Olive Hill, KY Mar 84 Oct 84 Paint Creek at Chillicothe, OH Oct 84 Paint Creek at Washington Court House, OH Dec 84 Parkersburg, WV Apr 85 Oct 85 Pax, WV Aug 84 Point Pleasant, WV Apr 85 Portsmouth-New Boston, OH Apr 85 Prestonsburg, KY Jan 85 Jun 85 Princeton, WV Aug 85 Richwood and Fenwick, WV Aug 85 Right and Left Forks of Beaver Creek, KY Mar 85 Ripley, WV Aug 84 Roseville, OH Dec 84 Jul 85 Russel, KY Apr 85 Oct 85 Smithfield, WV Aug 85 South Williamson, KY May 85 Oct 85 Utica, OH Oct 84 West Union, Middle Island, WV Aug 85 Williamson, WV May 85 Oct 85 25-22 PITTSBURGH, PA DISTRICT* This District comprises part of eastern Ohio, western Pennsylvania, southwestern New York, northern West Virginia, and northwestern Maryland embraced in drainage basin of Ohio River and tributaries above mile 127 (below Pittsburgh), immediately upstream from New Martinsville, W. Va. IMPROVEMENTS Navigation- Locks and Dams 1. Allegheny River, PA ................ 2. Construction of locks and dams, Ohio River..................... 3. Monongahela River, PA and WV ..... 4. Open-channel work, Ohio River ........ 5. Tygart Lake, WV ................ 6. Other authorized navigation projects ... Flood Control - Local Protection 7. Allegheny River, Oil City, PA ......... 8. Chartiers Creek, PA .............. 9. Elkins,WV .................... 10. Girty's Run, Millvale, PA ............ 11. Johnstown, PA .................. 12. Punxsutawney, Ohio River Basin, PA ..................... 13. Root Creek, Bolivar, NY ............. Flood Control- Reservoirs 14. Berlin Lake, Ohio River Basin, OH .............. 15. Conemaugh River Lake, Ohio River Basin, PA ...... 16. Crooked Creek Lake, Ohio River Basin, PA ....... Page Flood Control (Continued) Page ...... 26-2 25. Stonewall Jackson Lake, Ohio River Basin, W V .............................. 26-9 ...... 26-2 26. Tionesta Lake, Ohio ...... 26-2 River Basin, PA.......................26-10 ...... 26-2 27. Union City Dam, Ohio River ...... 26-3 Basin, PA .......................... 26-10 ...... 26-3 28. Woodcock Creek Lake, Ohio River Basin, PA ............................. 26-11 ..... 26-3 29. Youghiogheny River Lake, Ohio River .. 26-3 Basin, PA and MD .................... 26-11 30. Inspection of completed flood control ...... 26-4 ...... 26-4 projects .............................. 26-12 ..... 26-4 31. Other authorized flood control projects ...... 26-12 26 32. Flood control work under special AM _ authorization ......................... 26-12 .26-5 .26-5 .. .......... 26-5 .............. 26-6 17. East Branch, Clarion River Lake, Ohio River Basin, PA .................... 26-6 18. Kinzua Dam and Allegheny Reservoir, Ohio River Basin, PA and NY..............26-7 19. Loyalhanna Lake, Ohio River Basin, PA .......................... 26-7 20. Mahoning Creek Lake, Ohio River Basin, PA .................... 26-7 21. Michael J. Kirwan Dam and Reservoir, Ohio River Basin, OH ............ 26-8 22. Mosquito Creek Lake, Ohio River Basin, OH ........................ 26-8 23. Ohio River Basin (Pittsburgh District)............................26-9 24. Shenango River Lake, Ohio River Basin, PA and OH.................26-9 General Investigations 33. Surveys ......... .... ............. 34. Collection and study of basic data ........ . 35. Research and development .............. . 26-12 . 26-12 . 26-12 Tables Table 26-A Cost & Financial Statement ......... 26-13 Table 26-B Authorizing Legislation ............ 26-17 Table 26-C Other Authorized Navigation Projects 26-21 Table 26-D Not Applicable ........................ Table 26-E Other Authorized Flood Control Projects ....................... 26-22 Table 26-F Not Applicable ........................ Table 26-G Deauthorized Projects ............. 26-23 Table 26-H Allegheny River Statistics .......... 26-24 Table 26-I Monongahela River Statistics ........ 26-25 Table 26-J Monongahela River Total Costs ....... 26-26 Table 26-K Ohio River Basin Local Protection Projects ........................ 26-26 Table 26-L Ohio River Basin Reservoirs ........ 26-27 Table 26-M Inspection of Completed Flood Control Projects ....................... 26-28 Table 26-N Flood Control Work Under Special Authorization..................26-29 26-1 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Navigation - Locks and Dams 1. ALLEGHENY RIVER, PA Location. The Allegheny River is 325 miles long. It rises in northern Pennsylvania, flows northwestward into New York, thence generally southwestward to Pittsburgh, PA, where it joins with Monongahela River to form the Ohio. (See Geological Survey Charts for western Pennsylvania and southwestern New York.) Existing project. The project consists of eight locks and dams to afford slack-water navigation for a length of 72 miles from Pittsburgh, PA to above East Brady, PA. Controlling depth through canalized portion is 9 feet at normal pool level. Channel width varies from a minimum of 200 feet to full width of river at mouth. Existing project is complete, the last lock, No. 9, was placed in service in 1938. All locks and dams are in fair condition. Navigation channel has been widened at certain points and, in general, maintained to project depth, thus affording adequate depth for passage of commercial tows. Local cooperation. Fully complied with. Terminal facilities. City of Pittsburgh constructed a modern wharf for river freight. There are numerous privately maintained terminals and docks, consisting of tipples, various types of hoists, chutes, and pipelines for use in loading and unloading coal, stone, sand, gravel, petroleum products, steel products, and other commodities. Transshipment of freight between river and railroads is handled at privately owned river-to-rail terminals. Existing private terminals are adequate for shipments and receipt in Pittsburgh District of type of commerce now in existence. Operations during fiscal year. Operation and maintenance, general: Locks were operated as required and necessary repairs were made to structures to maintain them in a serviceable condition. 2. CONSTRUCTION OF LOCKS AND DAMS, OHIO RIVER See this heading under Ohio River portion. 3. MONONGAHELA RIVER, PA AND WV Location. Formed by junction of Tygart and West Fork Rivers about 1 mile south of Fairmont, WV, and flows northerly for 128.7 miles to its junction with Allegheny River, forming Ohio River at Pittsburgh, PA (See Geological Survey Charts for southwestern Pennsylvania and northern West Virginia.) Previous project. For details see Annual Report for 1963, page 1070. Existing project. Provides for improvement of river by 9 locks and dams to afford slack-water navigation for its entire length from Pittsburgh to above Fairmont, WV. Original locks and dams 7, 8 and 9 were replaced by new locks and dams 7 and 8 in 1925. Increased traffic necessitated enlargement and improvement of locks and dams 1 to 6 between Pittsburgh and Rices Landing, PA, by building two parallel chambers and fixed concrete dams during 1905 and 1932. Locks and dam 1 were eliminated in 1938 by raising Emsworth Dam, Ohio River. Reconstruction of lock 2 was completed in 1953 to provide two modern navigation chambers. The existing locks and dam 2 were originally completed in 1907; major modifications were made in 1923 and 1924, and in 1926 the upper guard and guide walls were extended. Construction of Maxwell locks and dam and the reconstruction of dam 4 have allowed for removal of obsolete locks and dams 5 and 6. Small and antiquated original locks and dams 10 to 15, inclusive, have been replaced by three modern structures. Morgantown lock and dam, initial step in replacement program, was completed in 1950 replacing locks and dams 10 and 11. Hildebrand lock and dam, next upstream, was completed in 1959 replacing locks and dams 12 and 13. Raising crest of dam 8 was also completed in 1959 as part of upper river improvement and eliminates restricted depth in upper reach of pool. Opekiska lock and dam was completed in 1967 replacing locks and dams 14 and 15. Completion of this link in upper river replacement program provides for entire river length of minimum channel depth of 9 feet, varying in width from a minimum of 250 feet to practically full width at mouth. Locks and dam 3 showed advanced stages of deterioration and, because of its strategic location and its importance to industry throughout the Greater Pittsburgh area and the nation, emergency remedial work had to be done in 1977. Major rehabilitation of locks and dam 3 was completed on Oct. 27, 1980. Local cooperation. None required. Terminal facilities. City of Pittsburgh constructed a modern wharf for freight. Boat landings are maintained by some municipalities along the river. A large number of tipples at mines and various types of hoists at manufacturing plants and sand and gravel supply companies are maintained for private use in loading and unloading coal, coke, billets, steel products, sand, gravel, and other commodities. These terminals and docks are not available for general commerce. A number of docks and pipelines are also privately maintained for petroleum and acid products. Marine ways are maintained by some of the larger industries. There are also several terminals for rail-to-river and river-to-rail transfer. Facilities are considered adequate for existing commerce. Operations during fiscal year. New work: Study for replacement of locks and dams for middle and lower reach of river is being conducted as part of the continuing study of the entire Monongahela River Basin. The Reconnaissance Report on the Monongahela River Navigation System, Stage I Studies was submitted in Jan. 1981. A Feasibility Study Interim Report on the Monongahela River Navigation System was submitted in Jan. 1984. A public meeting was held in Oct. 1983. A General Design Memorandum for the replacement of Lock and Dam 7 on the Monongahela River will be submitted in October 1985. Operation and maintenance, general: Locks were operated as required and necessary repairs were made to structures to maintain them in a serviceable condition. 4. OPEN-CHANNEL WORK, OHIO RIVER See this heading under Ohio River portion. 26-2 PITTSBURGH, PA., DISTRICT 5. TYGART LAKE, WV Location. Tygart Lake is located on the Tygart River in Taylor and Barbour Counties, northcentral WV. The lake is approximately 26 road miles due east of Clarksburg, WV and 30 road miles south of Morgantown. The dam is situated 22.7 river miles above the mouth of the Tygart River at Fairmont, or 2.25 miles upstream from Grafton, WV, and about 78 miles south of Pittsburgh, PA. (See Geological Survey Charts for Fairmont, Thornton, and Belington, WV.) Existing project. A reservoir for low water regulation and flood control. Dam is concrete gravity type with an uncontrolled center spillway flanked by abutment sections joining valley sides. Project was authorized by Public Works Administration January 11, 1934, and adopted by 1935 River and Harbor Act. For further project description see Annual Report for 1962. Authorized project is complete. Reservoir is in operation for low water control in Monongahela River and for purpose of flood protection in Monongahela and Ohio Valleys. Construction of dam was started in 1935 and placed in operation in 1938. Land acquired for project consists of 2,662.9 acres in fee, flowage easements over 1,216.9 acres and 1,731.9 acres of other easements. Actual cost of recreation facilities at completed project through fiscal year 1985 was $1,055,710 of which $409,622 were non-Federal costs. Local cooperation. The State of West Virginia has assumed responsibility for the development and operation of hunting and fishing areas as well as the Tygart Lake State Park. Controlled releases for downstream navigation and recreation are also coordinated with others to the extent feasible. No local cooperation is required at completed project; however, future recreational developments are subject to certain conditions of non-Federal costsharing under Federal Water Project Recreation Act of 1965. A cost-sharing agreement was executed with the West Virginia Department of Recreation in May 1981. Operations during fiscal year. Operation and maintenance, general: Reservoir was operated for benefit of flood control and low water regulation, as required, and project structures were operated and maintained in a serviceable condition throughout the year. Estimated flood control benefits achieved by this reservoir for this period were $3,269,000. Total flood control benefits for this reservoir through September 30, 1985 are $233,330,000. Activities under reservoir management program comprising sanitation measures, conservation, land management, and operation and maintenance of public-use facilities continued. This work was limited in scope as State of West Virginia has jurisdiction over recreation in reservoir area. 6. OTHER AUTHORIZED NAVIGATION PROJECTS See Table 26-C on other authorized navigation projects. Flood Control - Local Protection 7. ALLEGHENY RIVER, OIL CITY, PA Location. Oil City is located in Venango County, PA at the junction of Oil Creek and the Allegheny River (Allegheny river mile 132.1). (See Geological Survey Chart for Oil City, PA.) Existing project. To alleviate the long-standing ice jam flooding problems in Oil City, a floating ice control structure has been located on the Allegheny River about one-half mile upstream from the mouth of Oil Creek. It consists of a series of 23 floating steel pontoons (each 20' x 3' x 1.25') and 24 steel cylindrical floats connected together by 2 1/4 inch diameter corrosion resistant steel cables. The cables are attached to a junction plate in the center of the Allegheny River and four anchors (two on each side) on the river banks. During non-winter months, one half of the structure is disengaged from its anchor to permit navigation. A Detailed Project Report Supplement addressing the ice formation problem on Oil Creek was submitted in September 1985. Estimated first cost for project is $1,143,000 of which $1,122.000 is Federal cost and $21,000 is non-Federal cost. Local cooperation. The City of Oil City is responsible for the acquisition of required project land interests and the operation and maintenance of the ice control structures. By early Sep. 1982, the City had acquired all the necessary rights-of-way for the Allegheny River structure. Operations during fiscal year. Installation of Allegheny River structure with all new additional components included was completed in Oct. 1983. 8. CHARTIERS CREEK, PA Location. Within Washington and Allegheny Counties, southwestern Pennsylvania, a tributary of Ohio River. (See Geological Survey Chart for Carnegie, PA) Existing project. Provides for channel widening, deepening and realignment, construction of a major channel cutoff, and relocations in two separate and independent reaches. James G. Fulton project in Allegheny County would be about 13.4 miles long and Canonsburg-Houston reach in Washington County about 4.7 miles long. Completed improvements would contain within banks, all floods up to the 1912 maximum of record, but with some residual damage, and would greatly reduce flood stages and damages resulting from higher floods. James G. Fulton Flood Control Project-Construction of Unit 1 was started in July 1968, completed in September 1970, and turned over to local interests for operation and maintenance on June 25, 1971. Construction of Unit 2 (vas started in April 1970, completed in April 1973, and turned over to local interests on November 22, 1974. Construction of Unit 3 was started in July 1971 and was completed in December 1974. Construction of Unit 5 was started in June 1972 and was Completed in December 1973. Construction of Unit 4 channel improvement was started in July 1978 and was completed in June 1981. A contract for Environmental Improvement, Unit 4, James G. Fulton, was awarded in Sep 1981 and completed in Dec 1981. Canonsburg-Houston Reach-Construction of Unit 1 was started in December of 1968, completed in March 1970, and turned over to local interests for operation and maintenance on August 10, 1970. Construction of Unit 2A 26-3 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 was started January 17, 1976, completed December 16, 1976, and turned over to local interests on June 9, 1977. Construction plans and specifications for Unit 2B, the remaining unit of the reach, are 99% complete. Remaining work on project has been delayed due to the inability of local cooperating agency to provide the necessary rightsof- way. Project was authorized by Flood Control Act of 1965. Estimated cost for new work (1985) is $41,850,000 of which $32,750,000 is Federal cost and $9,100,000 non- Federal cost. Local cooperation. Requirements are described in full on page 26-3 of FY 1981 Annual Report. Local cooperating agency (Washington County) has been unable to provide the necessary rights-of-way for the remaining Unit 2B. Direct non-Federal contributions have been made in the amount of $4,225,188. Operations during fiscal year. Regular inspections were made at completed units. Estimated flood control benefits achieved by the Chartiers Creek project through September 30, 1985, totaled $12,431,000. 9. ELKINS, WV Location. On Tygart River in north-central Randolph County, WV, about 155 miles south of Pittsburgh, PA. It is at downstream end of a long, broad reach of upper Tygart Valley, about 75 miles above mouth of river. (See Geological Survey Chart for Elkins, WV) Existing project. Provides flood protection by diverting flood discharges from upstream arm of loop of natural river channel into an artificial cutoff channel, thereby bypassing City of Elkins. Improvement is designed to accommodate discharges equivalent to maximum flood of reasonable expectancy. Project construction was started May 1946 and completed May 1949. Completed works, except that portion of channel maintained by Federal Government, has been operated and maintained by City of Elkins since March 31, 1949. Land acquired for project consists of 32.04 acres in fee and 526.01 acres in easements. Project was authorized by 1938 Flood Control Act. For further project description see Annual Report for 1962, page 1222. Federal cost of completed project was $1,772,627; estimated non-Federal cost for lands, easements, and rights-of-way was $40,000. Local cooperation. Fully complied with. Operations during fiscal year. Operation and maintenance, general: Routine inspections were made. Cumulative total flood damages prevented to September 30, 1985, totaled $4,156,000. 10. GIRTY'S RUN, MILLVALE, PA Location. Girtys Run rises in the Fox Ridge area of the southern portion of McCandless Township, Allegheny County, and flows generally southeast through Ross and Shaler Townships and the Borough of Millvale to enter the Allegheny River from the right bank at River Mile 3.6 above the "Point" at Pittsburgh. (See U.S Geological Survey chart for Pittsburgh, PA, East.) Existing project. To decrease flooding conditions in the Borough of Millvale area, project consists of lowering the existing channel bottom within the limits of the existing walls. The lowering was accomplished by a 16-foot average bottom width of cut in rock or overburden averaging 4 feet in depth in the lower 2,750 feet of the project and 2 1/2 feet in depth for the remaining portion. Existing masonry walls of the channel were replaced and/or stabilized where required. Construction of project complete on June 26, 1980. Project was authorized for construction by the Chief of Engineers under authority of Section 205 of the 1948 Flood Control Act as amended. Federal cost is $2,000,000; estimated non-Federal cost of lands, easements and rights-of-way, utility adjustments, and amount in excess of $2 million limitation established by Section 205 of the 1948 Flood Control Act as amended, is estimated at $1,361,722. Local cooperation. Requirements are described in full on page 26-4 of FY 1981 Annual Report. The Commonwealth of Pennsylvania and the County of Allegheny, Pennsylvania, have each agreed to provide to the Borough of Millvale 50% of all estimated non-Federal costs, currently estimated at $1,361,722. To date, nonfederal contributions have totaled $701,722; a formal request for the additional $660,000 has been presented to the Borough of Millvale. Operations during fiscal year. Work on the project started July 11, 1976 with a scheduled completion date of November 22, 1977; however, by that date the contract work had progressed to only about 50% of completion and it was found necessary to terminate that contract for default due to unsatisfactory and untimely performance. Subsequently, a new contract for completion of the remaining work was made on May 4, 1978 and work was completed July 26, 1980 at a cost of $2,091,522.95. Formal hearings were held on July 26, 1978 before the Division Engineer and July 8-15, 1980, inclusive, before the Engineer Board of Contract Appeals regarding the appeal of the defaulted contractor. In July 1982, an agreement was reached with the surety and default contractor regarding the liability resulting from the termination. Modification effecting settlement and release stipulation was finalized, resulting in payment to Government of $464,340.66. 11. JOHNSTOWN, PA Location. Project is located in southwestern Cambria County, PA, about 58 miles east of Pittsburgh, PA. It is in a deep and comparatively narrow valley at junction of Stoney Creek and Little Conemaugh River, which unite to form Conemaugh River. (See Geological Survey Chart for Johnstown, PA.) Existing project. Provides for increased channel capacity by enlarging and realigning channels and protecting banks with concrete pavement. Improvement designed to accommodate discharges equivalent to those of March 1936 flood, maximum natural flow of record, minimum of overbank flow and to practically eliminate damages therefrom. Project construction began in August 1938 and was completed November 1943. Footer protection for Unit 4 26-4 PITTSBURGH, PA., DISTRICT was completed in November 1949. Land acquired for project consists of easements over 192 acres. Project was authorized by Flood Control Acts of 1936 and 1937. For further project description see Annual Report for 1962, page 1215. Local cooperation. Section 2, Flood Control Act of June 28, 1938, applies. Operations during fiscal year. Operation and maintenance, general: Operation activities and routine investigations and inspections were made. Cumulative flood damages prevented by project were estimated to be $417,470,000 to end of September 1985. 12. PUNXSUTAWNEY, OHIO RIVER BASIN, PA Location. Borough of Punxsutawney is on Mahoning Creek in Jefferson County, PA, about 85 miles northeast of Pittsburgh, PA. It is on a comparatively wide, alluvial flood plain about 52 miles above mouth of stream and 30 miles above Mahoning Creek flood control dam. (See Geological Survey Charts for Punxsutawney and Smicksburg, PA.) Existing project. Provides flood protection by channel enlargement, dikes, and walls. Improvement is designed to accommodate discharges 20% greater than that of maximum flood of record. Construction was accomplished by construction of four units. Construction started May 1946 and was completed June 1950. Land acquired for project consists of perpetual easements over 72.6 acres. Completed works, except that portion of channel maintained by the Federal Government, have been operated and maintained by Borough of Punxsutawney since July 31, 1950. Project was authorized by 1938 Flood Control Act. For further project description see Annual Report for 1962, page 1209. Local cooperation. Fully complied with. Operations during fiscal year. Operation and maintenance, general: Operation activities and routine investigations and inspections were made. Cumulative flood damages prevented by project were estimated to be $28,738,000 to end of September 1985. 13. ROOT CREEK, BOLIVAR, NY Location. The problem area was located in the southwestern portion of the State of New York in the Village of Bolivar, Allegany County, about 17 road miles east of Olean, New York. (See Geological Survey Chart of Olean, NY.) Existing project. Flooding of the Village of Bolivar from Root Creek causes estimated annual damages in the amount of about $53,000. The project consists of 3,230 feet of Root Creek channel modification, including moderate widening, deepening and slope protection. The plan provides Bolivar with protection against a flood having a frequency of once in 100 years. Total first cost of the plan is estimated to be $1,250,000. Project was authorized for construction by the Chief of Engineers under authority of Section 205 of the 1948 Flood Control Act as amended. Final EIS filed with CEQ on March 11, 1976. The Detailed Project Report was approved April 29, 1976. Local cooperation. Requirements are described in full on page 26-5 of FY 1981 Annual Report. Assurances were executed by the State of New York Department of Environmental Conservation and accepted by the Department of the Army on March 23, 1977. All interests in real estate required for project construction are available. Utility adjustments were completed by NYDEC. Land acquired for project consists of 7.809 acres. Operations during fiscal year. Contract for construction of Bolivar Flood Protection Project was awarded Sep 17, 1979 for $945,077.71. Construction was completed on July 6, 1982. Flood Control - Reservoirs 14. BERLIN LAKE, OHIO RIVER BASIN, OH Location. Dam is on Mahoning River about 73 miles above its confluence with Shenango River. It is about 10 miles above existing Milton Reservoir Dam and 35 miles upstream from Warren, Ohio. Reservoir is in Portage, Mahoning and Stark Counties, OH. (See Geological Survey charts for Warren, Ravenna, and Alliance, OH.) Existing project. A reservoir for flood control and water supply. Dam consists of a partially controlled, concrete gravity, center spillway flanked by rolled-earthfill abutment sections joining valley sides. Authorized project is complete and in operation for flood control and low water regulation purposes in industrialized Mahoning Valley below. Construction of dam was started January 1942 and completed June 1943. Present project lands consists of 6,885.3 acres in fee and 1,098.7 acres in easements. For further project description, see Annual Report for 1962, page 1233. Actual cost of recreation and sanitary facilities at completed project through fiscal year 1985 was $2,451,311. Local cooperation. None required at completed project; however, future recreational developments are subject to certain conditions of non-Federal cost-sharing under Federal Water Project Recreation Act of 1965. Operations during fiscal year. Operation and maintenance, general: Reservoir was operated as required and necessary repairs were made to structures and appurtenances. Estimated flood control benefits achieved by this reservoir for this period were $21,051,000; total benefits through September 30, 1985, $216,917,000. Activities under reservoir management program comprising sanitation measures, conservation, land management, and operation and maintenance of public-use facilities continued. 26-5 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 15. CONEMAUGH RIVER LAKE, OHIO RIVER BASIN, PA Location. Dam is on Conemaugh River in Indiana and Westmoreland Counties, PA, 7.5 miles above junction of Conemaugh River and Loyalhanna Creek, which form the head of the Kiskiminetas River. It is about 2 miles northeast of Tunnelton, PA, and about 42 miles east of Pittsburgh, PA. Reservoir is in Westmoreland and Indiana Counties, PA. (See Geological Survey Charts for Latrobe, New Florence, and Elders Ridge, PA.) Existing Project. A flood control reservoir dam of concrete gravity type with 4 gate-controlled center spillway flanked by abutment sections joining valley sides and an earth embankment ending in right abutment. Authorized project is complete. Reservoir system designed for protection of Pittsburgh and reduction of flood heights in upper Ohio Valley, generally. Land acquired for dam, reservoir and railroad relocation consists of 7,618.1 acres in fee and 518.5 acres in easements. Project authorized by Flood Control Acts of 1936 and 1938. For further project description see Annual Report for 1962, page 1217. Actual cost of sanitary facilities, required to upgrade area and comply with sanitary codes through fiscal year 1985 was $328,000. Local cooperation. None required by law. Operations during fiscal year. Operation and maintenance, general: Reservoir was operated for benefit of flood control as required, and necessary repairs were made to structures and appurtenances. Estimated flood control benefits achieved by this reservoir for this fiscal year were $3,861,000; total flood control benefits through September 30, 1985 are $540,780,000. Activities under reservoir management program comprising sanitation measures, conservation, land management and operation and maintenance of public-use facilities were continued. 16. CROOKED CREEK LAKE, OHIO RIVER BASIN, PA Location. Dam is on Crooked Creek 6.7 miles above junction of creek with Allegheny River near Ford City, PA, and about 32 miles northeast of Pittsburgh, PA. (See Geological Survey Charts for Freeport and Elders Ridge, PA.) Existing project. A flood control reservoir dam of earthfill type with separate uncontrolled saddle spillway and tunnel outlet works. Authorized project is complete. Reservoir is in operation as a unit of a coordinated reservoir system designed for protection of Pittsburgh and reduction of flood heights in upper Ohio Valley, generally. Construction of dam was started in March 1938 and completed October 1940. Present project lands consist of 2,563.6 acres in fee and 99.98 acres in easements. Project was authorized by Flood Control Acts of 1936 and 1938. For further project description see Annual Report for 1962, page 1213. Actual cost of sanitary facilities required to upgrade area and comply with state sanitary codes through fiscal year 1985 was $226,634. Local cooperation. None required by law. Operations during fiscal year. Operation and maintenance, general: Master Plan Design Memorandum No. 2 progressed to 75% completion. Reservoir was operated for benefit of flood control, as required, and necessary repairs were made to structures and appurtenances. Estimated flood control benefits achieved by this reservoir for this period were $370,000; total benefits through September 30, 1985 are $120,215,000. Activities under reservoir management program comprising sanitation measures, conservation, land management, and operation and maintenance of certain public-use facilities continued. By letter dated Aug 14, 1981, the Commonwealth of PA relinquished their lease having jurisdiction over recreation in reservoir area effective Oct 1, 1981. 17. EAST BRANCH, CLARION RIVER LAKE, OHIO RIVER BASIN, PA Location. Dam is in Elk County, PA, on East Branch of Clarion River above Middle Fork, 7.3 miles above junction of East and West branches of Clarion River at Johnsonburg, PA, and about 105 miles northeast of Pittsburgh, PA. Reservoir is in Elk County, PA. (See Geological Survey Chart for Mount Jewett, PA.) Existing project. A reservoir for flood control and lowwater regulation. Dam is rolled-earthfill type with gatecontrolled concrete tunnel under right abutment and a paved uncontrolled spillway on left abutment slope. Authorized project is complete. Reservoir is in operation for low-water regulation purposes in Clarion River Valley below and for flood control as a unit of a coordinated reservoir system for protection of Pittsburgh and upper Ohio Valley, generally. Construction of dam was started in June 1947 and completed in July 1952. Present project lands consist of 287.2 acres in fee and 1,296.7 acres in easements. Project was selected for construction under general authorization for Ohio River Basin in Flood Control Acts of 1938 and 1944. For further project description see Annual Report for 1962, page 1206. Actual cost of recreation and sanitary facilities at completed project through fiscal year 1985 was $156,812. Local Cooperation. None required by law. Operations during fiscal year. Operations and maintenance, general: Reservoir was operated for flood control and low-water regulation, as required; and necessary repairs were made to structures and appurtenances. Estimated flood control benefits achieved by this reservoir during this fiscal year were $356,000; total benefits through September 30, 1985 are $31,411,000. Some reservoir management activity was performed throughout the year comprising sanitation measures, conservation, land management and operation of public-use facilities. Work was limited in scope as bulk of reservoir lands are owned by Commonwealth of Pennsylvania. 26-6 PITTSBURGH, PA., DISTRICT 18. KINZUA DAM AND ALLEGHENY RESERVOIR, OHIO RIVER BASIN, PA AND NY Location. Dam site is on Allegheny River 9 miles above Warren, PA, and 198 miles above mouth of river at Pittsburgh, PA. Reservoir is in Warren and McKean Counties, PA., and Cattaraugus County, NY. (See Geological Survey Charts for Warren and Kinzua, PA -NY, and Randolph and Salamanca, NY.) Existing project. Reservoir provides flood control, low water regulation, and recreation. Dam consists of a combination concrete gravity structure and rolled earth embankment with gate-controlled spillway and discharge conduits controlled by slide-gates in gravity section. Construction of project, initiated in February 1960, is complete. Construction of dam was started in September 1960 and completed in December 1965. Development of recreation area at Onoville under a cost-sharing agreement with Cattaraugus County was completed in June 1978. Land acquired for project consists of 2,646.6 acres in fee and easements over 22,420.4 acres. For further details see Annual Report for 1962, page 1202. Project was authorized by Flood Control Acts of 1936, 1938 and 1941. Actual cost of recreation and sanitary facilities at completed project through fiscal year 1985 was $582,887. Local cooperation. None required by law. Licenses. The Federal Power Commission granted a license th Pennsylvania Electric Company and Cleveland Electric Illuminating Company on December 28, 1965, for the joint construction, operation and maintenance of a 325-megawatt pumped-storage installation (FPC Project No. 2280). The project is complete. Operation during fiscal year. New Work: Stilling Basin Rehabilitation contract awarded Jul 6, 1983 for $1,278,600 was completed on Dec 10, 1983. Operation and maintenance, general: Reservoir was operated for benefit of flood control and low water regulation, as required, and necessary repairs were made to structures and appurtenances. Estimated flood control benefits achieved by this reservoir for this period were $5,255,000; total to end of this fiscal year, $322,809,000. Of 2,212 surface tracts authorized for acquisition, all have been acquired but are subject to a final audit. Activities under reservoir management program comprising sanitation measures, conservation, land management, and operation and maintenance of public-use facilities continued. 19. LOYALHANNA LAKE, OHIO RIVER BASIN, PA Location. Dam is on Loyalhanna Creek, 4.5 miles above junction of creek with Conemaugh River at Saltsburgh, PA, and about 29 miles east of Pittsburgh, PA. Reservoir is in Westmoreland County, PA. (See Geological Survey Chart for Latrobe, PA). Existing project. A flood control reservoir dam of concrete gravity type with a gate-controlled center spillway flanked by abutment sections joining valley sides, and an earth embankment section ending in left abutment. Authorized project is complete. Reservoir is in operation as a unit of a coordinated reservoir system designed for protection of Pittsburgh and reduction of flood heights in upper Ohio Valley, generally. Construction of dam was started in October 1939 and completed in June 1942. Land acquired for project consists of 3,334.7 acres in fee and easements over 86.7 acres. Project was authorized by Flood Control Acts of 1936 and 1938. For further project description see Annual Report for 1962, page 1219. Actual cost of sanitary facilities, required to upgrade area and comply with sanitary codes, through fiscal year 1985 was $274,669. Local cooperation. None required by law. Operations during fiscal year. Operation and maintenance, general: The draft of Master Plan Design Memorandum No. 1 was submitted on September 13,1985. Reservoir was operated for benefit of flood control, as required, and necessary repairs were made to structures and appurtenances. Estimated flood control benefits achieved by this reservoir for this fiscal year were $532,000; total benefits to September 30, 1985, $160,363,000. Activities under reservoir management program comprising sanitation measures, conservation, land management and operation and maintenance of public-use facilities continued. 20. MAHONING CREEK LAKE, OHIO RIVER BASIN, PA Location. Dam is on Mahoning Creek in Ainstrong County, Pa, 21.6 miles above junction of crdk with Allegheny River. It is about 6.50 miles southeast of New Bethlehem, PA, and about 51 miles northeast of Pittsburgh, PA. Reservoir is in Armstrong, Indiana, and Jefferson Counties, PA. (See Geological Survey Charts for Rural Valley and Smicksburg, PA). Existing project. A flood control reservoir dam of concrete gravity type with a gate-controlled center spillway flanked by abutment sections joining valley sides. Authorized project is complete. Reservoir is in operation as a unit of a coordinated reservoir system designed for protection of Pittsburgh and reduction of flood heights in upper Ohio Valley, generally. Construction of dam was started in February 1939 and completed in June 1941. Land acquired for project consists of 2,519.36 acres in fee and easements over 83.5 acres. Project was authorized by Flood Control Acts of 1936 and 1938. For further project description see Annual Report for 1962, page 1210. Actual cost of recreation and sanitary facilities at completed project through fiscal year 1985 was $717,469. Local cooperation. None required at completed project. On November 4, 1977 a contract for wildlife development at Mahoning Creek Lake was executed between the U.S. Government and the Pennsylvania Game Commission. Each party will pay or contribute in kind 50% of the first cost of initial wildlife development. On June 7, 1979, a contract for fishing and boating development at Mahoning Creek Lake was executed between the U.S. Government 26-7 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 and the Pennsylvania Fish Commission. Each party will pay or contribute in kind 50% of the first costs of initial fishing and boathing development. On September 9, 1980, a contract for camping and day-use recreational development was executed between the U.S. Government and the County of Armstrong. Each party will pay or contribute in kind 50% of the first costs of initial camping and day-use recreational development and 50% of the costs for future development. Each cooperating authority is responsible for operation, maintenance and replacement without cost to the Government of all facilities developed with their support. Operations and results during fiscal year. New work: Cost-sharing for Construction of Fishing Access Area awarded in Sep 1980 was completed in Jul 1981 for $335,405.75. Cost-sharing contract for Construction of Hunting Access Areas awarded Jul 30, 1980 was completed on Nov 25, 1981 at a final cost of $44,540. Costsharing contract for Construction of Milton Loop Recreation Area awarded Jul 29, 1981 was completed on Sep 17, 1982 for $467,842. $500,086 has been contributed by local interests towards cost-sharing developments. Operations and maintenance, general: Reservoir was operated for benefit of flood control as required, and necessary repairs were made to structures and appurtenances. Estimated flood control benefits achieved by this reservoir for this fiscal year were $1,050,000; total to September 30, 1985, $151,036,000. Activities under reservoir management and maintenance for public-use facilities continued. 21. MICHAEL J. KIRWAN DAM AND RESERVOIR, OH Location: Dam site is on West Branch of Mahoning River which joins Mahoning River at Newton Falls, OH. It is 11 miles above mouth of branch and about 15 miles upstream from Warren, OH. Reservoir is in Portage County, OH. (See Geological Survey Charts for Ravenna, Garrettsville, Chagrin Falls, and Kent, OH.) Existing project. Reservoir provides flood control, lowwater regulation and recreation. Dam consists of a rolledearth embankment structure with gate-controlled outlet works and an uncontrolled side-hill spillway through left abutment. Authorized project is completed and in operation for flood control and low water regulation purposes. Construction of dam and access road was started in May 1963 and completed in November 1966. land acquired for project consists of 6,298.9 acres in fee and easements over 27.9 areas. For further description see Annual Report for 1962, page 1231 (West Branch Reservoir, Mahoning River, Ohio). Project was authorized by 1958 Flood Control Act (H. Doc. 191, 85th Cong. 1st sess.), with local contribution requirements modified by Flood Control Act of 1960. Federal cost of completed project was $17,370,000. Local interests contributed $3,230,000 during period of construction bringing initial project cost to $20,600,000. Local Cooperation. Local interests must contribute $5,200,000 for water pollution abatement and for municipal and industrial water supply purposes, of which $3,230,000 was paid in cash during construction. Unpaid balance at time project is placed in operation, $1,970,000, will be paid in cash at that time or on an annual basis. Of the unpaid balance of contributed funds due and payable, payment in full of Trumbull County's share in the amount of $663,040 has been received. Mahoning County elected to pay their share ($1,306,960) in 50 annual installments of $50,323.32, including interest, and has paid $470,505.60 toward principal to date. Local interests have now contributed $4,363,545.60 towards total of $5,200,000 non-Federal costs. Actual cost of recreation and sanitary facilities at completed project through fiscal year 1985 was $74,900. Operations during fiscal year. Operation and maintenance, general: Contract for Master Plan Design Memorandum No. 8 was completed in Dec 1982 and approved by division in Jan 1983. Reservoir was operated for benefit of flood control and low-flow augmentation, as required, and necessary repairs were made to structures and appurtenances. Estimated flood control benefits achieved by this dam for this fiscal year were $8,314,000. Total flood control benefits for this reservoir through September 30, 1985 are $75,439,000. Activities under reservoir management program comprising sanitation measures, conservation, land management, and operation and maintenance of public-use facilities continued. 22. MOSQUITO CREEK LAKE, OHIO RIVER BASIN, OH Location. Dam is on Mosquito Creek, 9 miles above junction of creek with Mahoning River at Niles, OH, and about 18 miles northwest of Youngstown, OH. (See Geological Survey Charts for Bristolville and Kinsman, OH, and Pennsylvania.) Existing project. A reservoir for flood control, low-water regulation and water supply storage. Dam is rolledearthfill type with outlet facilities through dam, and an uncontrolled natural wasteway to discharge overflow from reservoir. Authorized project is complete and in operation for flood control and low-water regulation purposes in industrialized Mahoning and Beaver Valleys below. Construction of dam was started in July 1943 and was ready for beneficial use in January 1944. Land acquired for project consists of 11,180.6 acres in fee and easements over 276.0 acres. State of Ohio has a license from Secretary of the Army for development and operation of recreation facilities in reservoir area. Project was selected for construction under general authorization for Ohio River Basin in 1938 Flood Control Act. For further project description see Annual Report for 1962, page 1228. Actual cost of recreation and sanitary facilities at completed project through fiscal year 1985 was $217,629. Local cooperation. None required at completed project; however, future recreational developments are subject to certain conditions of non-Federal cost-sharing under Federal Water Project Recreation Act of 1965. Operations results during fiscal year. Operation and maintenance, general: Reservoir was operated for benefit of flood control and low-flow regulation as required, and 26-8 PITTSBURGH, PA., DISTRICT necessary repairs were made to structures and appurtenances. Estimated flood control benefits achieved by this dam for this fiscal year were $3,750,000. Total flood control benefits for this reservoir through September 30, 1985 are $58,670,000. Activities under reservoir management program comprising sanitation measures, conservation, land management and operation and maintenance of certain public-use facilities continued. This work was limited in scope as State of Ohio has jurisdiction over recreation in reservoir area. 23. OHIO RIVER BASIN (PITTSBURGH DISTRICT) Location. A series of dikes, floodwalls, channel improvements, and reservoirs/lakes in Ohio River Basin within Pittsburgh District. Existing project. Individual projects considered in comprehensive plan within Pittsburgh District. (See Tables 26-B, 26-K and 26-L on Acts authorizing existing projects, local protection projects and reservoirs.) Operations during fiscal year. New work: None by the United States except as stated in individual projects. Completed local protection projects operated and maintained by local interests, including those projects for which individual reports have been included, prevented flood damages of an estimated $4,049,000 during this fiscal year. Total flood damages prevented through September 30, 1985 are $670,139,000. 24. SHENANGO RIVER LAKE, OHIO RIVER BASIN, PA AND OH Location. Dam is on Shenango River about 0.8 mile above Sharpsville, PA, and about 33 miles above junction of river with Mahoning River, which unite near New Castle, PA, to form Beaver River. Reservoir is in Mercer County, PA, and Trumbull County, Ohio. (See Geological Survey Chart for Kinsman, Ohio, and Shenango, PA.) Existing project. A reservoir for flood control, low-flow augmentation and recreation. Dam consists of a concrete gravity structure with gate-controlled outlet works and an uncontrolled center spillway section. Authorized project is complete. Reservoir is in operation for low-water regulation purposes in Shenango River valley below and for flood control as a unit of a coordinated reservoir system for protection of Shenango River valley and the Beaver and upper Ohio River Valley, generally. Construction of dam was started in March 1963 and completed May 1965. Land acquired for project consists of 14,632.2 acres in fee and easements over 197.7 acres. Future work consists of completion of project lands of any additional recreation facilities as required to serve the public needs. For further project description, see Annual Report for 1962, page 1230. Project was authorized by 1938 Flood Control Act. Actual cost of recreation and sanitary facilities at completed project through fiscal year 1985 was $3,348,400. Local cooperation. None required by law. Operations during fiscal year. Operation and maintenance, general: Reservoir was operated for benefit of flood control and low-flow augmentation, as required, and necessary repairs were made to structures and appurtenances. Estimated flood control benefits achieved by this reservoir for this period were $1,680,000. Total flood control benefits for this dam through September 30, 1985 are $16,678,000. Activities under reservoir management program comprising sanitation measures, conservation, land management and operation and maintenance of public-use facilities continued. 25. STONEWALL JACKSON LAKE, WV Location. In Lewis County, North Central West Virginia, on the West Fork River, which joins the Tygart River at Fairmont, West Virginia to form the Monongahela River. Damsite is located at Brownsville, West Virginia, about 4 miles south of Weston and 72 miles above mouth of West Fork River at Fairmont, WV. (See Geological Survey Charts for Weston and Crawford, WV.) Existing project. Provides for construction of a reservoir for flood control, water supply, water quality control, area redevelopment and recreation. Dam would be of the concrete gravity type, 95 feet high and 620 feet long. Outlet works will consist of five multi-level sluices, spillway will be uncontrolled. Storage capacity will be 74,650 acre-feet controlling an area of 102 square miles. Project was authorized by 1966 Flood Control Act. Estimated initial Federal cost for new work (1985) is $206,000,000 (includes $19,155,000 reimbursement by non-Federal interests.) Local cooperation. Local interests are required to make arrangements for repayment, under the provisions of the Water Supply Act of 1958, as amended, of that part of the construction cost and annual operation, maintenance and replacement costs allocated to municipal and industrial water supply, an amount presently estimated at $4,200,000 for construction; and $15,000 annually for operations, maintenance and replacements. Also, in accordance with Federal Water Project Recreation Act, local interests are required to administer project land and water areas for recreation and fish and wildlife enhancement, pay, contribute in kind or repay (which may be through user fees) with interest, one-half of the separable first cost of the reservoir project allocated to recreation and fish and wildlife enhancement, an amount presently estimated at $14,955,000; bear all costs of operation, maintenance and replacement of recreation and fish and wildlife land and facilities, the amount involved being currently estimated on an average annual basis to be $1,117,500, exercise to the full extent of their legal capability, control against removal of streamflow made available for water quality control; and contribute to the control of pollution of streams subject to low-flow augmentation by adequate treatment or other methods of controlling wastes at their source. The requirements of Section 221 were amended in 1971 to exempt assurances for future demands for water supply pursuant to the Water Supply Act of 1958 from the contractual requirements of the Act. Accordingly, the City of Weston, West Virginia, has provided assurances that it will enter into a 26-9 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 water supply contract with the Department of the Army within a period of time which will permit paying out the costs allocated to the water supply storage within the life of the project. A recreation cost-sharing contract, in accordance with the requirements of the Federal Water Project Recreation Act, P.L. 89-72, was executed by the State of West Virginia on March 27, 1977. Local cooperation assurances for recreation cost-sharing were executed by the Governor and Attorney General of West Virginia on May 29, 1973. In this connection, Section 8 of P.L. 92-222 deleted the requirement that the State of West Virginia "hold and save the United States free from damages resulting from water rights claims due to construction and operation of the project." Legislation relieving Stonewall Jackson Lake, WV, project of the requirements of Section 221, P.L. 96-611 was contained in Water Resources Development Act of 1974 signed by the President on March 7, 1974. Operations during fiscal year. New work: Relocation of US Rt. 19, Section 3 contract, awarded Nov 16, 1982, was completed on Nov 28, 1984. Relocation of US Rt. 30, Section 2 contract, awarded Sep 12, 1984, progressed to 65%. completion. Relocation of US Rt. 30, Section 3 Scontract, awarded Mar 26, 1985 for $5,926,755, progressed to 16% completion. Supply contract for Slide Gates, Hydraulic Cylinders, Sluice Liners, and Deflector Plates, awarded Sep 20,1982, for $996,732, progressed to 99% completion. Contract for construction of Dam, awarded Jul 29, 1983 for $15,985,064, scheduled for completion by Sep 5, 1987, progressed to 78% completion. Construction of Equitable Gas Company Access Roads, Phase II, awarded May 31, 1985 for $1,267,138, progressed to 23% completion. Cost-reimbursable contract with Equitable Gas Company for Phase II Piping Work was negotiated and awarded on March 8, 1985, for an estimated amount of $4,276,808, progressed to 35% completion. Contract for Relocation of Baltimore and Ohio Railroad Track and Appurtenances, awarded Jun 18, 1985 for $3,496,215, progressed to 12% completion. Costreimbursable contract with Baltimore and Ohio Railroad for Track Raise and Communication Lines was negotiated and awarded on January 22, 1985, for an estimated amount of $405,000, progressed to 2% completion. Cost-reimbursable contract with Consolidated Gas Transmission Corporation for Relocation, Removal or Abandonment and Subordination of Gas Pipelines, Gas Production Wells and Access Roads was negotiated in Jul 1984, for an estimated amount of $2,725,000, is scheduled to be completed by July 1986. Roanoke Elementary School construction contract, awarded Aug 1, 1984 for $3,193,000, progressed to 53% completion. Contract for Plugging Gas Storage Wells, awarded Jun 14, 1984 for $165,557, was completed on Nov 25, 1984. All 893 surface tracts have been acquired. Land acquisition, detailed engineering work and construction continued and all items of work were progressing on schedule. 26. TIONESTA LAKE, OHIO RIVER BASIN, PA Location. Dam is on Tionesta Creek, 1.25 miles above junction of creek with Allegheny River at Tionesta, PA, and about 78 miles northeast of Pittsburgh, PA. Reservoir is entirely in Forest County, PA. (See Geological Survey Charts for Tionesta, Tidioute and Sheffield, PA.) Existing project. A flood control reservoir dam of earthfill type with separate uncontrolled saddle spillway and tunnel outlet works. Authorized project is complete. Reservoir is in operation as a unit of a coordinated reservoir system designed for protection of Pittsburgh and reduction of flood heights in upper Ohio Valley, generally. Construction of dam was started in May 1938 and completed January 1941. Land acquired for project consists of 2,797.3 acres in fee and easements over 13.1 acres. Future work consists of provision on project lands of additional recreational facilities as required to serve public needs. Project was authorized by Flood Control Acts of 1936 and 1938. For further project description see Annual Report for 1962, page 1203. Actual cost of recreation facilities at completed project through fiscal year 1985 was $2,574,977. Local Cooperation: None required by law. Operations during fiscal year. New work: Contract awarded Aug 29, 1983 for an estimated $187,207.50 for Construction of Sanitary Facilities, Spillway Boat Launching Area, is 99% completed at end of fiscal year. Operation and maintenance general: Reservoir was operated for benefit of flood control and low-flow augmentation, as required, and necessary repairs were made to structures and appurtenances. Estimated flood control benefits achieved by this reservoir for this period were $1,796,000. Total flood control benefits for this reservoir through September 30, 1985 are $167,075,000. Activities under reservoir management program comprising sanitation measures, conservation, land management and operation and maintenance of public-use facilities continued. 27. UNION CITY DAM, PA Location. In Erie County, northwestern Pennsylvania, on French Creek, a tributary of Allegheny River. Damsite is 24 miles upstream from Cambridge Springs, PA, and 41 miles upstream from Meadville, PA. (See Geological Survey Chart for Union City, PA - NY.) Existing project. A flood control reservoir dam of earth cehmabnannekl mspeinlltw anyo. nOgautteldet wtyoprek s cwointhsi stu nocf oan trloowlleedr ousitdleetlocated in valley floor constructed of reinforced concrete conduit 8 feet by 4.5 feet and an upper outlet consisting of an uncontrolled slot 9.5 feet wide through the north end of the ogee weir in the spillway. Dam is 1,420 feet long at top rising 88 feet above streambed and provides gross capacity of 47,640 acre-feet from a drainage area of 222 square miles. Project authorization was modified to provide for a conservation pool and addition of recreation facilities. On November 5, 1974, a referendum proposal was defeated by the constituents of Erie County in regard to the cost-sharing for construction of recreation facilities. 26-10 PITTSBURGH, PA., DISTRICT In view of the foregoing, all action toward implementation of the authorized project modification was discontinued. Reservoir is operated as one of a two-reservoir system for reduction of flood stages in French Creek Basin between damsite and mouth, Allegheny River from Franklin, PA, to Pittsburgh, PA, inclusive, and upper Ohio River Valley. Initial highway relocations were completed in October 1968 and remaining highway relocations were completed in May 1972. Construction of the dam was started in July 1968 and completed in September 1971. Land acquired for project consists of 161.4 acres in fee and easements over 2,458.4 acres. Existing project was authorized by 1962 Flood Control Act. Local cooperation. Local interests are required to inform affected interests in French Creek Basin at least annually, that the system of reservoirs of which Union City Dam is a part, will not provide protection against maximum floods. November 10, 1964 the Department of Forests and Waters of the Commonwealth of Pennsylvania furnished formal assurances of local cooperation in respect to notifying local interests at least annually that the system of reservoirs will not provide protection against maximum floods. A referendum on the ballot during the November 1974 election regarding the approval to cost-share the maintenance of a summer pool was defeated by the local voters. Operations during fiscal year. Operation and maintenance, general: Maintenance of the structure and appurtenances was performed as required. This dam acted as an uncontrolled detention type dam during the fiscal year. Estimated flood control benefits achieved by this reservoir for this period were $3,223,000. Total flood control benefits for this reservoir through September 30, 1985 are $13,869,000. 28. WOODCOCK CREEK LAKE, PA Location. In Crawford County, northwestern Pennsylvania, on Woodcock Creek, a tributary of French Creek. Damsite is about 4.1 miles above mouth of Woodcock Creek and about 5 miles northeast of Meadville, PA. (See Geological Survey Chart for Meadville, PA.) Existing project. A flood-control reservoir dam of rolledearth embankment type, gate-controlled outlet works with a 6 foot-wide by 7.75 foot-high conduit and uncontrolled saddle spillway on the left abutment. Dam is 4,650 feet long at top rising 90 feet above streambed and provides for gross capacity of 20,000 acre-feet from a drainage area of 46 square miles. Reservoir is operated as one of a tworeservoir system for reduction of flood stages in French Creek Basin between damsite and mouth, Allegheny River from Franklin, PA, to Pittsburgh, PA, inclusive, and upper Ohio River Valley. Authorized project is complete. Construction of dam was started in July 1970 and completed in July 1973. Land acquired for project consists of 1,731.4 acres in fee and easements over 1.2 acres. Project was authorized for flood control and recreation by 1962 Flood Control Act. Storage for water quality control was added to the project during the preconstruction planning stage. Actual cost of recreation and sanitary facilities at completed project through fiscal year 1985 was $1,527,023. Local cooperation. Local interests must inform affected interests in French Creek Basin at least annually, in a manner satisfactory to District Engineer, that a system of reservoirs of which Woodcock Creek Lake is a part, will not provide protection against maximum floods. Pennsylvania Department of Forests and Waters assumed responsibility of local cooperation for project. Operations during fiscal year. New work: Contract for Construction of Sanitary Tie-In, Saegertown Authority, awarded Sep 14, 1984 for $549,549, is scheduled for completion by Jan 18, 1986. Operation and maintenance, general: Maintenance of the structure and appurtenances was performed as required. Estimated flood control benefits achieved by this reservoir for this period were $120,000; total through September 30, 1985 is $1,422,000. 29. YOUGHIOGHENY RIVER LAKE, OHIO RIVER BASIN, PA AND MD Location. Dam is on Youghiogheny River about 74.2 miles above its junction with Monongahela River at McKeesport, PA. It is 1.2 miles upstream from Confluence, PA, and about 57 miles southeast of Pittsburgh, PA. Reservoir is in Fayette and Somerset Counties, PA, and Garrett County, MD. (See Geological Survey Charts for Confluence, PA, Accident, MD, West Virginia and Pennsylvania.) Existing project. Reservoir for flood control, low-flow augmentation, and pollution abatement purposes. Dam is rolled-earthfill type with separate uncontrolled side channel spillway and tunnel outlet works. Authorized project is complete. Reservoir is in operation for flood control, low-flow augmentation, and pollution abatement purposes. For flood control, reservoir is operated as a unit of a coordinated reservoir system designed for protection of Pittsburgh and reduction of flood heights in upper Ohio Valley, generally. Construction of dam was started in June 1940 and completed May 1944. Land acquired for project consists of 3,914.9 acres in fee and easements over 0.62 acre. A license was issued Commonwealth of Pennsylvania covering fish conservation and management in Pennsylvania portion of reservoir. Future work consists of provision on project lands of additional recreational and sanitary facilities as required to serve public needs. Project was selected for construction under general authorization for Ohio River Basin in 1938 Flood Control Act. For further project description see Annual Report for 1962, page 1223. Actual cost of recreation and sanitary facilities at completed project through fiscal year 1985 was $2,843,930. Local cooperation: None required. Operations during fiscal year. New work: A contract awarded Aug 10, 1983 for $221,617.40 for Construction of Comfort Station #3 and Sanitary Trailer Station was completed on Aug 16, 1984. Operation and maintenance, general: Design Memorandum No. 1, Master Plan was completed in Aug 1981 and approved by division on Nov 15, 1982. Reservoir was operated for benefit of flood control, as required, and necessary repairs were made to structures and appurtenances as required. Estimated flood control benefits achieved by this reservoir for this 26-11 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 period were $2,997,000. Total flood control benefits for this dam through September 30, 1985 are $131,976,000. Activities under reservoir management program comprising sanitation measures, conservation, land management, and operation and maintenance of public-use facilities were continued. 30. INSPECTION OF COMPLETED FLOOD CONTROL PROJECTS Flood Control Act of June 22, 1936, and subsequent acts require local interests to furnish assurances that they will maintain and operate certain local protection projects after completion in accordance with regulations prescribed by Secretary of the Army. District Engineers are responsible for administration of these regulations within boundaries of their respective districts. Inspections were made of completed units transferred to local interests for maintenance and operation and local interests were advised, as necessary, of measures required to maintain these projects in accordance with standards prescribed by regulations. (See Table 26-M for dates of inspections.) Costs for this fiscal year, $67,444. Total cost to September 30, 1985 was $929,217. 31. OTHER AUTHORIZED FLOOD CONTROL PROJECTS See Table 26-E on other authorized flood control projects. 32. FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION For flood control activities pursuant to Section 205, Public Law 858, 80th Congress, as amended (preauthorization) See Table 26-N. For emergency bank protection (Sec. 14 of 1946 Flood Control Act, Public Law 526, 79th Cong.) See Table 26-N. For Streambank Erosion Control Evaluation and Demonstration Act of 1974 (Sec. 32, Public Law 251, 93rd Cong.) See Table 26-N. For Shoreline Erosion Control Demonstration Act of 1974 (Sec. 54, Public Law 251, 93rd Congress) See Table 26-N. Flood control and coastal emergencies (Public Law 99, 84th Cong., and antecedent legislation). Advance preparation $132,909 Rehabilitation: Brookville, PA. 147 Meyersdale, Somerset, PA. 46,080 Total cost for fiscal year: General Investigations 33. SURVEYS Flood control studies Review of authorized projects Coordination with other agencies Special investigations Federal Energy Regulatory Commission Continuation of Planning and Engineering: Grays Landing Lock and Dam (Lock and Dam 7), Monongahela River, PA. Point Marion Lock and Dam (Lock and Dam 8), Monongahela River, PA and WV Total cost for fiscal year: $179,136 $1,372,668 1,853 268 81,157 69,979 1,183,182 190,316 $2,899,423 34. COLLECTION AND STUDY OF BASIC DATA Costs this fiscal year were $147,570 for flood plain management services and $1,019 for related hydrologic studies. 35. RESEARCH AND DEVELOPMENT None. 26-12 PITTSBURGH, PA., DISTRICT TABLE 26-A COST AND FINANCIAL STATEMENT See Total Cost to Section Funding FY 82 FY 83 FY 84 FY 830, SeProject In Text Project Funding FY 82 FY 83 FY 84 FY 85 1985 Navigation - Locks and Dams 1. Allegheny River New Work PA Approp. Cost Maint. Approp. Cost 3. Monongahela New Work River, PA and Approp. WV Cost Maint. Approp. Cost Major Rehab. Approp. Cost 5. Tygart Lake, New Work WV Approp. Cost Maint. Approp. Cost Flood Control - Local Protection 7. Allegheny River New Work Oil City, PA Approp. Cost 8. Chartiers New Work Creek, PA Approp. (Federal Funds) Cost New Work (Contributed Contrib. Funds) Cost 9. Elkins, WV New Work Approp. Cost Maint. Approp. Cost 10. Girty's Run, New Work Millvale, PA Approp. (Federal Funds) Cost New Work (Contributed Contrib. Funds) Cost 11. Johnstown, PA New Work Approp. Cost Maint. Approp. Cost 12. Punxsutawney, New Work Ohio River Approp. Basin, PA Cost Maint. Approp. Cost 13. Root Creek, New Work Bolivar, NY Approp. Cost. Flood Control - Reservoirs 14. Berlin Lake, Ohio River Basin, OH New Work Approp. Cost Maint. Approp. Cost - - - - 18,157,860' - - - - 18,157,860' 2,693,000 3,270,300 3,788,000 3,971,500 53,361,362' 3,100,425 3,248,945 3,762,006 4,037,823 53,325,647' 2,657 6,290,000 5,968,529 115,139 489,000 584,004 583,500 583,113 80 - 7,665,440 8,496,900 7,260,530 8,375,983 - -120,000 66,402 44,567 - -417,500 103,046 -195,337 710,000 689,500 642,587 700,570 8,9 9,6 67 620,000 349,000 98,000 215,428 620,143 244,784 82,727 1,329 6,000 6,597 -470,000 -451,892 -18,376 5,221 5,221 5,488 26,508 6,000 4,181 - 129,203,085' 39 129,203,085' 60,000 136,434,554' 13,100 135,980,345' - 15,857,000 1,698 15,856,772 - 19,077,932' 12 19,077,932' 42,000 8,036,8397 05,320 7,996,5197 69,000 1,191,000 68,648 1,188,368 - 26,586,186 41,764 26,555,053 - 4,225,188 - 4,204,498 8,000 9,619 -3,000 19 - 83,000 376,000 131,000 74,974 127,912 314,450 6,000 5,081 100,000 157,472 2,708 902,600 897,342 308,000 28,711 -5,000 102,047 -2,500 56 1,048,000 1,110,833 -6,000 263,795 18,426 -56,591 19,281 1,988 12,104 2,172 1,772,627 1,772,627 228,487 227,961 2,662,000 2,648,849 701,722 701,722 8,865,3888 8,865,3888 3,803,205 3,802,907 3,586,107' 3,586,107' 1,014,88810 1,014,43410 1,597,385 1,590,649 - - 8,739,987" - - 8,739,987" 1,259,000 1,425,500 13,522,28312 1,025,185 1,610,473 13,425,1691 26-13 TABLE 26-A (Continued) REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 COST AND FINANCIAL STATEMENT See Total Cost to Section Sep30, In Text Project Funding FY 82 FY 83 FY 84 FY 85 1985 15. Conemaugh River Lake, Ohio River Basin, PA 16. Crooked Creek Lake, Ohio River Basin, PA 17. East Branch, Clarion River Lake, Ohio River Basin, PA 18. Kinzua Dam and Allegheny Reservoir, Ohio River Basin, PA and NY 19. Loyalhanna Lake, Ohio River Basin, PA 20. Mahoning Creek Lake, Ohio River Basin, PA 21. Michael J. Kirwan Dam and Reservoir, Ohio River Basin, OH 22. Mosquito Creek Lake, Ohio River Basin, OH 23. Ohio River Basin, Pittsburgh, PA District Consolidated 24. Shenango River Lake, Ohio River Basin, PA New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost Major Rehab. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost Minor Rehab. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost New Work Approp. Cost Maint. Approp. Cost 280,000 78,631 529,000 519,823 190,398 476,000 529,107 - 33,500 - 1,041 1,166,300 1,125,000 1,221,024 1,217,561 574,700 560,055 -50 958,600 951,570 185,000 104,826 175,000 52,647 1,031,500 809,831 -8,238 99,952 662,900 705,652 21,000 3,584 506,100 498,645 892,617 703,184 -5,162 1,129,000 1,120,473 1,050,000 948,001 -20,000 100,519 i,131,100 1,146,746 84,066 531,000 540,383 42 765,000 455,236 -4,000 7,405 670,100 460,055 63,000 68,849 1,236,200 1,186,299 742,091 768,355 26,610 1,726,000 1,713,527 804,423 452,500 915,649 586,993 1,214 1,203,000 1,163,944 2,000,000 1,399,020 -5,000 411 826,577 1,001,587 -- 190,000 -95,443 584,000 546,449 8,286 1,065,500 1,138,420 5,000 229,472 940,705 919,272 30,160 30,160 780,500 803.900 659,100 580,807 808,210 768,377 394,400 536,000 523,000 514,500 385,562 513,256 531,555 538,675 :- 1,411,400 1,367,677 72 1,357,000 1,391,237 1,239,000 1,270,706 -10,500 2,089,000 2,117,222 46,012,41119 46,012,4111s 6,548,904 6,354,672 4,431,52314 4,431,52314 9,761,92115 9,629,49015 9,539,58616 9,539,58616 6,698,37517 6,683,59917 109,309,07618 109,298,2058 13,412,278 13,357,527 3,240,000 2,681,319 5,727,53119 5,727,53119 9,318,55620 9,242,17420 7,144,97321 7,138,81422 6,728,316 6,681,268 47,033 47,033 17,376,09723 17,376,09723 6,329,796"4 6,312,072" 4,253,02925 4,253,02925 5,761,864 5,732,984 985,19726 985,19726 40,227,20127 40,209,894" 1144,,652018,,6014722"88 26-14 PITTSBURGH, PA., DISTRICT TABLE 26-A (Continued) COST AND FINANCIAL STATEMENT See Total Cost to Section Sep30, In Text Project Funding FY 82 FY 83 FY 84 FY 851985 25. Stonewall Jack- New Work son Lake, Ohio Approp. 20,455,000 21,500,000 22,300,000 25,300,000 135,610,200 River Basin, WV Cost 20,917,297 20,229,662 21,414,527 26,553,633 133,704,886 26. Tionesta Lake, New Work Ohio River Approp. 350,000 278,000 17,000 -17,286 7,824,42129 Basin, PA Cost 106,733 436,326 218,519 41:048 7,788,37930 Maint. Approp. 729,120 898,000 1,025,000 811,000 10,203,9533" Cost 698,626 785,005 895,102 1,049,901 10,152,03191 27. Union City New Work Dam, Ohio Approp. - - - - 14,559,800 River Basin, PA Cost - - - - 14,559,800 Maint. Approp. 215,000 246,000 345,000 417,000 2,510,668 Cost 209,590 244,224 288,948 445,085 2,463,875 28. Woodcock Creek New Work Lake, Ohio Approp. 1,068,000 - 540,000 23,398 20,548,09832 River Basin, PA Cost 583,988 313,216 194,349 392,820 20,400,72233 Maint. Approp. 454,100 538,500 582,900 592,000 4,429,27134 Cost 435,069 537,291 555,237 613,235 4,388,06434 29. Youghiogheny New Work River Lake, Approp. - 277,000 5,000 -6,112 12,532,12636 Ohio River Cost 18,679 27,096 279,125 7,397 12,518,83436 Basin, PA and Maint. MD Approp. 1,239,100 1,527,500 1,229,200 1,253,000 13,930,38937 Cost 1,224,065 1,119,522 1,561,741 1,312,586 13,866,26437 1. Includes $2,453,737 from emergency relief funds and $1,250,049 from public works funds. 2. Includes $64,365 public works acceleration, executive funds (1963) and $191,400 provided from the Productive Employment Appropriations Act (PL 98-8) 1983 funds. 3. Includes $5,420,541 for new work for previous projects. 4. Includes $22,549 public works acceleration, executive funds (1963), $742 for maintenance for previous project and $582,000 provided from the Productive Employment Appropriations Act (PL 98-8) 1983 funds. 5. Includes $22,549 public works acceleration, executive funds (1963), $742 for maintenance for previous project and $461,466 provided from the Productive Employment Appropriations Act (PL 98-8) 1983 funds. 6. Includes $1,999,995 emergency relief funds, $10,000,000 public works funds, $234,000 Code 711 funds and $412,088 Code 713 funds; excludes $409,622 contributed by local interest. 7. Includes $89,000 provided from the Productive Employment Appropriations Act (PL 98-8) 1983 funds. 8. Includes $33,423 from emergency relief funds. 9. Excludes $180,485 for new work expended from contributed funds. 10. Includes $283,988 provided from the Productive Employment Appropriations Act (PL 98-8) 1983 funds. 11. Includes $1,542,500 Code 711 funds, $809,700 Code 712 funds and $99,111 Code 713 funds; excludes $100,000 contributed by local interest. 12. Includes $40,000 provided from the Productive Employment Appropriations Act (PL 98-8) 1983 funds. 13. Includes $5,351 from emergency relief funds and $328,000 Code 711 funds. 14. Includes $63,788 from emergency relief funds and $226,634 Code 711 funds. 15. Includes $45,000 provided from the Productive Employment Appropriations Act (PL 98-8) 1983 funds. 16. Includes $156,812 Code 711 funds. 17. Includes $322,000 provided from the Productive Employment Appropriations Act (PL 98-8) 1983 funds. 18. Includes $2,791 from emergency relief funds, $14,622 Code 711 funds and $568,265 Code 713 funds; excludes $389,370 contributed by local interest. 19. Includes $7,339 from emergency relief funds and $274,669 Code 711 funds. 20. Includes $256,000 provided from the Productive Employment Appropriations Act (PL 98-8) 1983 funds. 21. Includes $25,671 emergency relief funds, $162,381 Code 711 funds and $561,247 Code 713 funds; excludes $500,086 contributed by local interests. 22. Includes $25,671 emergency relief funds, $162,3$1 Code 711 funds and $555,088 Code 713 funds; excludes $456,611 contributed by local interests. 23. Includes $74,900 Code 711 funds; excludes $4,337,406.40 for new work contributed by local interest. 24. Includes $315,500 provided from the Productive Employment Appropriations Act (PL 98-8) 1983 funds. 25. Includes $122,729 Code 711 funds and $94,900 Code 713 funds. 26. Includes $8,914 from emergency relief funds. 27. Includes $1,730,100 Code 711 funds and $1,618,300 Code 713 funds. 28. Includes $152,000 provided from the Productive Employment Appropriations Act (PL 98-8) 1983 funds. 26-15 TABLE 26-A (Continued) REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 COST AND FINANCIAL STATEMENT 29. Includes $2,335,119 Code 711 funds ($273,000 provided from the Productive Employment Appropriations Act PL 98-8, 1983 funds), $275,900 Code 712 funds, and $24,201 emergency relief funds. 30. Includes $2,299,077 Code 711 funds, ($252,761 provided from the Productive Employment Appropriations Act PL 98-8, 1983 funds), $275,900 Code 712 funds, and $24,201 emergency relief funds. 31. Includes $203,000 provided from the Productive Employment Appropriations Act (PL 98-8) 1983 funds. 32. Includes $1,674,398 Code 711 funds. 33. Includes $1,527,023 Code 711 funds. 34. Includes $85,000 provided from the Productive Employment Appropriations Act (PL 98-8) 1983 funds. 35. Includes $2,857,222 Code 711 funds ($293,000 provided from the Productive Employment Appropriations Act (PL 98-8) 1983 funds). 36. Includes $2,843,930 Code 711 funds ($290,666 provided from the Productive Employment Appropriations Act (PL 98-8) 1983 funds). 37. Includes $591,000 provided from the Productive Employment Appropriations Act (PL 98-8) 1983 funds. 26-16 PITTSBURGH, PA., DISTRICT TABLE 26-B AUTHORIZING LEGISLATION See Date Section Authorizing in Text Act Project and Work Authorized Documents ALLEGHENY RIVER, PA. (See Section 1 of Text) Aug 5, 1886 For lock and dam 1. (Fixed dam contemplated. Sep 29, 1891 Secretary of War authorized change to a movable dam.) June 3, 1896 For locks and dams 2 and 3. July 25, 1912 For locks and dams 4 to 8, inclusive. July 3, 1930 For a depth of 9 feet in the lower 61 miles. Aug 30, 19351 Aug 30, 1935' June 26, 19342 Replace lock and dam 1 by a dredged channel, 9 feet deep and 200 feet wide up to lock 2, and construct new locks and dams 2 and 3, to replace existing locks and dams 2 and 3. Construct lock and dam 9, raising crest of dam 8, and dredging a navigable channel to head of pool 8. Operation and care of locks and dams provided for with funds from War Department appropriation for rivers and harbors. MONONGAHELA RIVER, PA AND WV Mar 3, 1899 Enlarge and improve lock and dam 6; additional works at lock 3; new repair steamer and new dredge boat with equipment; all at an estimated cost of $185,556. June 13, 1902 Rebuild lock and dam 2 at estimated cost of $655,961. (Estimate increased in 1910 to $698,961.) Mar 3, 1905 Acquisition of land and additional improvements at 5 and 6 at a cost of $7,850. Mar 3, 1905 Rebuild lock and dam 3 at estimated cost of $589,196. Mar 2, 1907 Reconstruct lock and dam 5 at esth.-iated cost of $756,042. Mar 4, 1913 Reconstruct lock and dam 6 at estimated cost of $356,400. (Estimate increased in 1916 to $418,860.) Sep 22, 1922 Additional improvements at estimated cost as follows: Guide walls and guard walls, 1 to 6, $1,255,130; Lengthen land chamber of lock 3 to 720 feet, $787,722; New chamber (360 feet long), lock 4, $699,786; Lock and dam 7, $1,161,241; Lock and dam 8, $1,165,758; Lock and dam 7 (second chamber), $419,126; Lock and dam 8 (second chamber), $504,465; Reconstruct dam 4, $397,211; Marine ways, repair plant, office and warehouse, $250,000, for a total of $6,640,439. July 3, 1930 Construct new locks and dam 2.5 miles below existing structure, at estimated cost of $2,175,000 in lieu of work authorized at old lock and dam 4. Jan 31, 19318 Chief of Engineers authorized to locate new locks and dam 4 above existing structure and on such site as they may deem most desirable. June 26, 1934' Operation and care of locks and dams provided for with funds from War Department appropriations for rivers and harbors. 3. May 17, 1950 Modification of existing project as follows: Provide 2 new locks and dams similar to Morgantown lock and dam to replace existing locks and dams 12 to 15, inclusive. Provide a movable crest on existing dam 8 to raise existing pool-full elevation 4 feet. Provide a navigation channel of 300-foot minimum bottom width and a 9-foot project depth above lock and dam 8. Provide an extension of navigable channel of upper Monongahela River, into lower Tygart River for 2.1 miles at a maximum bottom width of 200 feet and a 9-foot project depth. Annual Report 1886, p. 1545, Annual Report 1891, p. 2366 H. Doc. 204, 54th Cong., 1st sess., and Annual Report 1896, p. 2212 H. Doc. 540, 62d Cong., 2d sess. H. Doc. 356, 71st Cong., 2d sess. Rivers and Harbors Committee, Doc. 16, 72d Cong., 1st sess. H. Doc. 721, 71st Cong., 3d sess., and Rivers and Harbors Committee, Doc. 27, 73d Cong., 2d sess. Annual Report 1897, p. 2423 Annual Report 1909, p. 1756 Annual Report 1904, p. 460 H. Doc. 209, 58th Cong., 2d sess. H. Doc. 209, 58th Cong., 2d sess. H. Doc. 1217, 62d Cong., 3d sess. H. Doc. 288, 67th Cong., 2d sess. Rivers and Harbors Committee, Doc 22, 70th Cong., 2d sess. S. Doc. 100, 81st Cong., '1st sess. 26-17 1. 3. REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 26-B AUTHORIZING LEGISLATION (Continued) See Date Section Authorizing in Text Act Project and Work Authorized Documents 5. Jan 11, 1934 Aug 30, 1935 9. Jun 28, 1938 11. 12. 14. 15. 16. 17. 18. Jun 28, 1938 Jun 28, 1938 Jun 28, 1938 Dec 22, 1944 as amended Jun 22, 1936 amended by Jun. 28, 1938 Dec 22, 1944 as amended Jun 22, 1936 amended by Jun. 28, 1938 Dec 22, 1944 as amended Jun 28, 1938 Dec 22, 1944 as amended Jun 22, 1936 amended by Jun 28, 1938 modified by Aug 18, 1941 Dec 22, 1944 as amended TYGART RIVER LAKE, WV Construction of a dam and reservior for low water regulation and flood control ELKINS, WV For construction of local flood protection projects. JOHNSTOWN, PA For construction of local flood protection projects. PUNXSUTAWNEY, OHIO RIVER BASIN, PA For construction of local flood protection projects. BERLIN LAKE, OHIO RIVER BASIN, OH Construction of a dam and reservoir for flood control and low water regulation. Construction, operation & maintenances of recreation facilities. CONEMAUGH RIVER LAKE, OHIO RIVER BASIN, PA Construction of a dam and reservoir for flood control. Construction, operation & maintenance of recreation facilities. CROOKED CREEK LAKE, OHIO RIVER BASIN, PA Construction of a dam and reservoir for flood control. Construction, operation & maintenance of recreation facilities. EAST BRANCH CLARION RIVER LAKE, OHIO RIVER BASIN, PA Construction of a dam and reservoir for flood control and low water regulation. Construction, operation & maintenance of recreation facilities. KINZUA DAM AND ALLEGHENY RESERVOIR, OHIO RIVER BASIN, PA AND NY Construction of a dam and reservoir for flood control and low water regulation and recreation. Construction of a dam and reservoir for flood control, pollution abatement, low water regulation and recreation. Construction, operation & maintenance of recreation facilities. 26-18 H. Doc. 1792, 64th Cong. 2nd Sess. H. Doc. 106, 76th Cong. 1st Sess. H. Doc. 306, 74th Cong. 1st Sess. FCC Doc. No. 1, 75th Cong. 1st Sess. H. Doc. 306, 74th Cong. 1st Sess. FCC Doc. No. 1, 75th Cong. 1st Sess. H. Doc. 306, 74th Cong. 1st Sess. FCC Doc. No. 1, 75th Cong. 1st Sess. H. Doc. 306, 74th Cong. 1st Sess. FCC Doc. No. 1, 75th Cong. 1st Sess. Sec. 4, Flood Control Act of 1944 H. Doc. 306, 74th Cong. 1st Sess. FCC Doc. No. 1, 75th Cong. 1st Sess. Sec. 4, Flood Control Act of 1944 H. Doc. 306, 74th Cong. 1st Sess. FCC Doc. No. 1, 75th Cong. 1st Sess. Sec. 4, Flood Control Act of 1944 H. Doc. 306, 74th Cong. 1st Sess. FCC Doc. No. 1, 75th Cong. 1st Sess. Sec. 4, Flood Control Act. of 1944 H. Doc. 306, 74th Cong. 1st Sess. FCC Doc. No. 1, 75th Cong. 1st Sess. H. Doc. 300, 76th Cong. 1st Sess. Sec. 4, Flood Control Act of 1944 PITTSBURGH, PA., DISTRICT AUTHORIZING LEGISLATION See Date Section Authorizing in Text Act Project and Work Authorized Documents 20. 19. LOYALHANNA LAKE, OHIO RIVER BASIN, PA Construction of a dam and reservoir for flood control. Construction, operation & maintenance of recreation facilities. MAHONING CREEK LAKE, OHIO RIVER BASIN, PA Construction ofa dam and reservoir for flood control. Construction, operation & maintenance of recreation facilities. MICHAEL J. KIRWAN DAM AND RESERVOIR, OH Construction of a dam and reservoir for flood control, water supply, low water, regulation and recreation. To define cost-sharing arrangement for municipal & industrial water supply & water for pollution abatement purposes. MOSQUITO CREEK LAKE, OHIO RIVER BASIN, OH Construction of a dam and reservoir for flood control, low water regulation and water supply storage. Construction, operation & maintenance of recreation facilities. Jun 22, 1936 amended by Jun 28, 1938 Dec 22, 1944 as amended Jun 22, 1936 amended by Jun 28, 1938 Dec 22, 1944 as amended Jul 3, 1958 Jul 14, 1960 Jun 28, 1938 Dec 22, 1944 as amended Aug 28, 1937 Jun 28, 1938 Aug 18, 1941 Dec 22, 1944 Jul 24, 1946 May 17, 1950 Dec 30, 1963 Jun 18, 1965 May 12, 1967 Aug 13, 1968 Jun 19, 1970 Mar 7, 1974 Oct 22, 1976 TABLE 26-B (Continued) H. Doc. 306, 74th Cong. 1st Sess. FCC Doc. No. 1, 75th Cong. 1st Sess. Sec. 4, Flood Control Act of 1944 H. Doc. 306, 74th Cong. 1st Sess. FCC Doc. No. 1, 75th Cong. 1st Sess. Sec. 4, Flood Control Act of 1944 H. Doc. 191, 85th Cong. 1st Sess. Pub. Law 86-645 H. Doc. 306, 74th Cong. 1st Sess. FCC Doc. No. 1, 75th Cong. 1st Sess. Sec. 4, Flood Control Act of 1944 OHIO RIVER BASIN- Pittsburgh District Construct levees, floodwalls, and drainage structures for protection Flood Control Committee, of cities and towns in. Ohio River Basin. Projects to be selected by Doc. 1, 75th Cong., 1st sess. Chief of Engineers with approval of Secretary of War at a cost not to exceed $24,877,000 for construction. Approved general comprehensive plan for flood control and other Flood Control Committee, purposes in Ohio River Basin as may be advisable in discretion of Doc. 1, 75th Cong., 1st sess. Secretary of War and Chief of Engineers, and for initiation and partial accomplishment of plan, authorized $75 million for reservoirs and $50,300,000 for local flood protection works. Additional $45 million for prosecution of comprehensive plan for H. Doc. 300, 76th Cong. Ohio River Basin. 1st Sess. Additional $70 million for further prosecution of comprehensive H. Doc. 762, 77th Cong., plan for Ohio River Basin, including additional projects in 2d sess. tributary basins. Additional $125 million for further prosecution of comprehensive H. Doc. 506, 78th Cong., plan including additional projects mintr ibutary basins. 1st sess. Additional $100 million for prosecution of comprehensive plan for S. Doc. 20, 81st Cong. Ohio River Basin. 1st Sess. Additional $150 million for further prosecution of comprehensive Public Law 88-253, plan for flood control and other purposes in Ohio River Basin. 88th Cong., 1st sess. Additional $89 million for further prosecution of comprehensive H. Doc., 6755, 89th Cong., plan for Ohio River Basin. 1st sess. Additional $38 million for further prosecution of comprehensive Public Law 90-17, plan for Ohio River Basin. 90th Cong., 1st sess. Additional $35 million for further prosecution of comprehensive Public Law 90-483, plan for Ohio River Basin. 9)th Cong., 2d sess. Additional $69 million for further prosecution of comprehensive H. Doc. 15166, 91st Cong., plan for Ohio River Basin. 2d sess. Additional $120 million for further prosecution of comprehensive H. Doc. 10203, 93rd Cong., plan for Ohio River Basin. River Basin Monetary Authorization Act of 1974. Authorized phase I design memorandum stage of advanced Water Resources Development engineering and design of the project for abatement of acid mine Act of 1976; Public Law drainage in the Clarion River Basin, Pa. 94-587, Sec. 101(a). 26-19 21. 22. 23. REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 26-B (Continued) AUTHORIZING LEGISLATION See Date Section Authorizing in Text Act Project and Work Authorized Documents 24. SHENANGO RIVER LAKE, OHIO RIVER BASIN, PA AND OH Jun 28, 1938 Construction of a dam and reservoir for flood control, low water H. Doc. 306, 74th Cong. regulation and recreation. 1st Sess. FCC Doc. No. 1, 75th Cong. 1st Sess. Dec 22, 1944 Construction, operation & maintenance of recreation facilities. Sec. 4, Flood Control Act as amended of 1944 25. STONEWALL JACKSON LAKE, WV Nov 7, 1966 Construction of a dam and reservoir for flood control, water supply, S. Doc. 109, 89th Cong. water quality control, area redevelopment and recreation. 2nd Sess. 26. TIONESTA LAKE, OHIO RIVER BASIN, PA Jun 22, 1936 Construction of a dam and reservoir for flood control and low H. Doc. 306, 74th Cong. amended by water regulation. 1st Sess. Jun 28, 1938 FCC Doc. No. 1, 75th Cong. 1st Sess. Dec 22, 1944 Construction, operation & maintenance of recreation facilities. Sec. 4, Flood Control Act as amended of 1944 17. UNION CITY DAM, PA Oct 23, 1962 Construction of a dam and reservoir for flood control. S. Doc. 95, 87th Cong. 2nd Sess. 28. WOODCOCK CREEK LAKE, PA Oct 23, 1962 Construction of a dam and reservoir for flood control, recreation S. Doc. 95, 87th Cong. and storage for water quality control. 2nd Sess. 29. YOUGHIOGHENY RIVER LAKE, OHIO RIVER BASIN, PA AND MD Jun 28, 1938 Construction of a dam and reservoir for flood control, low-flow H. Doc. 306, 74th Cong. augmentation, and pollution abatement purposes. 1st Sess. FCC Doc. No. 1, 75th Cong. 1st Sess. Dec 22, 1944 Construction, operation & maintenance of recreation facilities. Sec. 4, Flood Control Act as amended of 1944 1. Included in the Emergency Relief Administration program April 8, 1935. 2. Permanent Appropriations Repeal Act. 3. Public Res. 117, 71st Cong., 3d Sess. 26-20 PITTSBURGH, PA., DISTRICT TABLE 26-C OTHER AUTHORIZED NAVIGATION PROJECTS (See Section 6 of Text) For Last Cost to September 30, 1985 Full Report See Annual Operation and Project Status Report For Construction Maintenance Allegheny River, PA, open-channel work Completed 1934 197,000 133,940 Beaver and Mahoning Rivers, PA and OH' ' Inactive 1938 - - Buckhannon River, WV2 3 Completed 1893 5,500 - Cheat River, WV2 Completed 1895 12,997 - Pittsburgh Harbor, PA Completed 1922 110,663 81,613 Youghiogheny River, PA and MD6 Inactive 1971 47,195' 185,6686 1. January 23, 1939, Chief of Engineers recommended constructing a waterway from Ohio River through Beaver, Mahoning, and Grand River Valleys to Lake Erie (H. Doc. 178, 76th Cong., 1st Sess.) 2. Abandonment recommended in H. Doc. 467, 69th Cong., 1st Sess. 3. No Commerce reported. 4. Previous project data. 5. Includes $1,700 expended under previous project. 6. Eligible for deauthorization. 26-21 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 26-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS (All Projects Not Specifically Identified in Text) For Last Cost to September 30, 1984 Full Report See Annual Operation and Project Status Report For Construction Maintenance Allegany, NY, unit I (Allegheny River) Deferred - 4,100 - Allegany, NY, unit II (Five Mile Creek Area) Deferred 1975 64,851 - Amsterdam, OH' Completed 1964 183,072 - Benwood, WV2 Deferred 1954 81,028 - Big Run, PA' Completed 1965 364,208 - Black Fork at Hendricks, WV' Completed 1972 6,800 - Brackenridge, Tarentum and Natrona, PA Inactive - - - Bradford, PA Completed 1962 7,601,763 - Brookville, PA Completed 1963 964,976 - Buckhannon, WV Completed 1972 1,568,661 - Burgettstown, PA' Completed - 83,129 - Butler, PA Completed 1970 1,556,181 - Dubois, PA Completed 1979 4,465,200 - Eagle Creek Reservoir, OH2 Inactive - 100,000 - Empire-Stratton, OH 2 Inactive - 33,031 - Friendsville, MD' Completed - 41,529 - Granville, PA' Completed - 75,908 - Johnsonburg, PA Completed 1958 674,664 - Kittanning, PA, part I Completed 1949 130,317 - Latrobe, PA Completed 1951 207,659 - Latrobe, PA Completed 1970 2,556,652 - Leetonia, OH' Completed - 89,299 - Leetsdale, PA Inactive - - - Martins Ferry, OH2 Inactive 1941 25,164 - Moundsville, WV2 Inactive - - - Muddy Creek Dam, PA2 4 Inactive 1977 402,459 - Neville Island, PA Inactive - - - New Kensington and Parnassus, PA Inactive - - - Oakdale, PA' Inactive - 14,127 - Oil City, PA' Completed - 43,595 - Olean, NY Completed 1954 3,217,531 - Portage, PA Completed 1965 150,386 - Portville, NY Completed 1954 2,070,484 - Powhatan Point, OH 2 Inactive - - - Proctor, WV2 Inactive - - - Reynoldsville, PA Completed 1959 385,494 - Ridgway, PA (Elk Creek) Completed 1964 628,888 - Ridgway and vicinity, PA (on Clarion River)' 4 Active 1979 132,464 - Rochester, PA Inactive - - - Rouseville, PA' Inactive - 1,642 - Rowlesburg Lake, WV3 Inactive 1977 2,857,575 - Salamanca, NY Completed 1972 2,880,535 - Slovan, PA' Completed - 57,811 - Sykesville, PA' Completed - 184,246 - Tarentum, PA' Completed 1964 136,591 - Tenmile Creek at Marianna, PA' Completed 1981 1,554,428 - Turtle Creek, PA Completed 1972 15,350,552 - Uniontown, PA2 Inactive 1956 - - Wallace, WV' * Inactive - 11,035 - Warwood, WV2 Inactive - - - Washington, PA Completed 1964 789,093 - Wellsville, OH, Sec. I Completed 1956 483,910 - Wellsville, OH, Sec. II Completed 1956 157,633 - Weston Mills, Olean, NY' * Active - 50,100 - Weston Mils, Portville, NY' x Active - 52,100 - Wheeling, WV (North Wheeling) Inactive - - - Wheeling, WV (Wheeling Island)2 Inactive - 21,700 - Wheeling, WV2 Inactive 1954 189,067 - Wilmore, PA' Completed - 96,853 - Woodlands, WV2 Inactive - - - Youngstown, OH Completed 1976 3,621,134 - 26-22 1. Authorized by Chief of Engineers. 3. Lacks local support. 2. Eligible for deauthorization. 4. No longer economically justified. PITTSBURGH, PA., DISTRICT TABLE 26-G DEAUTHORIZED PROJECTS For Last Full Report Federal Contributed See Annual Date Funds Funds Project Report For Deauthorized Expended Expended Adena, OH (Short Creek) - Aug 5, 1977 13,452 - Bellaire, OH - May 6, 1981 76,487 - Brilliant, OH - Aug 5, 1977 - - Brockway, PA (Allegheny River Basin) - Aug 5, 1977 194 - Buckhannon, WV' - Feb 20, 1951 37,488 - Clarington, OH - Aug 5, 1977 - - Coraopolis, PA - Aug 5, 1977 - - Dillonvale, OH (Short Creek) - Aug 5, 1977 16,884 - Follansbee, WV - Aug 5, 1977 - - Freeport, PA (Allegheny River) - Aug 5, 1977 - - KInitdtaunstnriyn,g P, AP A, - Aug 5, 1977 - - part II (Allegheny River) - Nov 6, 1977 - - Lake Chautauqua and Chadakoin River, NY2 1965 Mar 2, 1970 190,722 - Lake Erie,-Ohio Canal, OH and PA 1972 May 6, 1981 1,342,000 - McKees Rocks, PA - Oct 3, 1978 - - Mingo Junction, OH - Aug 5, 1977 - - New Cumberland, WV - Aug 5, 1977 - - Pittsburgh, PA (Golden Triangle) - Oct 3, 1978 - - Pittsburgh, PA (North Side) - Oct 3, 1978 - - Pittsburgh, PA (The Strip) - Oct 3, 1978 - - Redbank Creek Lake, PA - Aug 5, 1977 156,337 - St. Marys, PA (Allegheny River Basin) - Aug 5, 1977 13,529 - Smith Ferry, PA - Aug 5, 1977 - - Wellsburg, WV - Aug 5, 1977 6,387 - West Bridgewater, PA - Aug 5, 1977 - - Wilcox, PA3 - Mar 5, 1955 16,761 - 1. Local interests failed to meet requirements of cooperation, authority for project expired Feb. 20, 1951. 2. Local interests failed to meet requirements of cooperation, authority for project expired Mar. 2, 1970. 3. Local interests failed to meet requirements of cooperation, authority for project expired Mar. 5, 1955. 26-23 TABLE 26-H ALLEGHENY RIVER, PA.: LOCKS AND DAMS (See Section 1 of Text) Dimensions Upper Avail- Normal Depths on Miter Width able Lift at Pool Sills at Normal Character of Type of Year of Length Normal Elevation Pool Level- Foundation Construction Per- Opened Miles Cham- to Full Pool (feet, cent to Above her Width Level mean sea Lower Upper Kind of Com- Navi- No. Mouth Nearest Town (feet) (feet) (feet) level) (feet) (feet) Lock Dam Dam Lock Dam plete gation Actual Cost 2 6.7 Aspinwall, PA 56 360 11.0 721.0 12.0 10.9 Rock Rock Fixed Concrete Concrete 100 19342 $ 1,763,485 3 14.5 Cheswick, PA 56 360 13.5 734.5 10.8 11.8 Rock Pile-rock Fixed Concrete Concrete 100 19342 1,875,665 4 24.2 Natrona, PA 56 360 10.5 745.0 10.0 8.5 Rock Rock Fixed Concrete Concrete 100 1927 1,707,690 5 30.4 Freeport, PA 56 360 11.8 756.8 10.5 10.3 Piling Crib-Pile Fixed Concrete Concrete 100 1927 1,940,537 6 36.3 Clinton, PA 56 360 12.2 769.0 10.6 10.8 Rock Crib-Pile Fixed Concrete Concrete 100 1928 1,523,959 7 45.7 Kittanning, PA 56 360 13.1 782.1 9.8 10.9 Piling Steel Sheet Fixed Concrete Concrete 100 1930 1,460,008 Piling 8 52.6 Templeton, PA 56 360 17.9 800.0 10.4 13.8 Rock Rock Fixed Concrete Concrete 100 1931 2,848,920 9 62.2 Rimer, PA 56 360 22.0 822.0 10.5 11.3 Rock Rock Fixed Concrete Concrete 100 1938 2,510,373 Total $15,630,637 Abandoned lock and dam 1 591,187 Abandoned lock and dam 2 544,929 Abandoned lock and dam 3 310,103 Demolishing old dam 1 26,001 Dredging channel 1,055,003 Total $18,157,860 1. All depths as shown are on guard sills and 2. Dates shown represent replacement structures. are controlling depth. t~j 0 0 0 0 iz0 TABLE 26-I MONONGAHELA RIVER, PA. AND W. VA.: LOCKS AND DAMS (See Section 3 of Text) Dimensios Upper Avail- Normal Depths on Miter Width able Lift at Pool Sills at Normal Character of Type of Year of Length Normal Elevation Pool Level- Foundation Construction Per- Opened Miles Cham- to Full Pool (feet, cent to Above her Width Level mean sea Lower Upper Kind of Com- Navi- No. Month Nearest Town (feet) (feet) (feet) level) (feet) (feet) Lock Dam Dam Lock Dam plete gation Actual Cost 2 11.2 Braddock, PA 56 360 8.7 718.7 16.0 15.95 Rock Crib pile Fixed Concrete Concrete 100 1953' $17,872,212' 110 720 3 23.8 Elizabeth, PA 56' 360 8.2 726.9 16.0 15.95 Rock Crib Pile Fixed Concrete Concrete 100 1953' 17,538,308" 720 4 41.5 Monessen, PA 56' 360 16.6 743.5 10.7 20.0 Piles Piles Movable Concrete Concrete 100 1932' 17,254,071" 720 - 61.2 Maxwell locks and dam. 84' 720 19.5 763.0 15.0 20.5 Rock Rock Movable Concrete Concrete 100 1964 30,110,889' Maxwell, PA - 82.2 Grays Landing lock 84 720 15.0 778.0 15.0 26.0 Rock Rock Fixed Concrete Concrete - - 803,000' and dam, Grays Landing, PA 7 85.0 Greensboro, PA 56 360 15.0 778.0 10.0 10.5 Rock Rock Fixed Concrete Concrete 100 1925' 2,639,804 8 90.8 Point Marion, PA 56 360 19.0 797.0 10.0 14.5 Rock Rock Movable Concrete Concrete 100 1925' 6,027,253' - 102.0 Morgantown lock and 84 600 17.0 814.0 14.5 17.8 Rock Rock Movable Concrete Concrete 100 1950 8,778,000 dam, Morgantown, WV - 108.0 Hildebrand lock and 84 600 21.0 835.0 15.0 14.0 Rock Rock Movable Concrete Concrete 100 1959 12,506,829 dam, 6 miles above Morgantown, WV - 115.4 Opekiska lock and dam, 84 600 22.0 857.0 14.0 17.75 Rock Rock Movable Concrete Concrete 100 1964 25,179,622 13.4 miles above Morgantown, WV Marine ways, etc. 250,000 Abandoned lock and dam 1 1,019,907 Abandoned lock and dam 4 780,816 Abandoned lock and dam 5 1,074,812 Abandoned lock and dam 6 770,449 Abandoned lock and dam 7 213,776 Abandoned lock and dam 8 245,900 Abandoned lock and dam 9191,000 Abandoned lock and dam 10 210,445 Abandoned lock and dam 11 227,668 Abandoned lock and dam 12 200,550 Abandoned lock and dam 13190,691 Abandoned lock and dam 14 210,127 Abandoned lock and dam 15 175,829 Dredging 587899 Total 145,059,857 1. All depths as shown are on guard sills and are controlling depths. 2. Dates shown for locks and dams Ne. 2 to 8, inclusive, represent reconstruction. 3. 2 Chambers 4. Includes $3,322,057 for raising crest of dam, (1958-9), $2,086,438 for original reconstruction (1923-1926) and $618,758 AE&D costs for replacement of lock. 5. Actual cost; may include estimated costs which have been footnoted as necessary. 6. Includes $2,173,767 for original reconstruction (1931-2), and $15,080,304 for reconstruction of dam (1977). 7. Includes $16,967,114 for reconstruction of locks. 8. Includes $15,856,772 for major rehabilitation. 9. AE&D costs for proposed lock. 9U wl y 'U Mo cm w~ CA REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 26-J MONONGAHELA RIVER, PA AND WV: TOTAL COSTS OF EXISTING PROJECT TO END OF FISCAL YEAR (See Section 3 of Text) (eration and Maintenance, Funds New Work General Total Regular $139,639,316'" $115,057,8442 $254,697,1601 " Maintenance and operation 452,623 452,623 Public Works acceleration, executive (1963) - 22,549 22,549 Total $139,639,316'" $115,533,0162 $255,172,3321 ' 1. Excludes $5,420,541 for new work for previous projects. TABLE 26-K 2. Excludes $20,446,587 expended between July 7, 1897 and June 30, 1937, on operation and care of works of improvement under provisions of permanent appropriation for such purposes and excludes $742 for maintenance of previous projects. 3. Includes $15,856,772 for major rehabilitation OHIO RIVER BASIN (PITTSBURGH DISTRICT): LOCAL PROTECTION PROJECTS (See Section 23 of Text) Estimated Cost8 Federal Non-Federal Allegany, NY, unit I (Allegheny River)2 Allegany, NY, unit II (Five Mile Creek area)2 Benwood, W V2 7 14 Brackenridge, Tarentum and Natrona, PA (Allegheny (River)2 Elkins, W V (Monongahela River Basin)4 5 Empire-Stratton, OH 21 Johnsonburg, PA (Allegheny River Basin)2 5 Johnstown, PA (Allegheny River Basin) ' 5 Kittanning, PA, part I (Allegheny River)'5 Latrobe, PA (Allegheny River Basin) ' 5 Leetsdale, PA2 Martins Ferry, OH2 6 14 Moundsville, WV2 "14 Neville Island, PA2 New Kensington and Parnassus, PA (Allegheny River)2 Olean, NY (Allegheny River)2 5 Portville, NY (Allegheny River)2' Powhatan Point, OH 2 " Proctor, WV2 14 Punxsutawney, PA (Allegheny River Basin)4 5 Ridgway, PA (Allegheny River Basin)2 ' Rochester, PA2 Uniontown, PA (Monongahela River Basin)2 " Warwood, WV1 , Wellsville, OH, sec. I 2 5 Wellsville, OH, sec. 112 Wheeling, WV2 7 14 Levee Channel and levee Wall Wall Channel diversion Internal drainage facilities Wall Channel Wall Channel Levee Wall and levee Wall and levee Wall and levee Wall Levee Levee Levee Levee Channel and levee Channel Wall Channel and wall Wall Wall and levee Wall and levee Wall and levee 697,000 980,000 8,500,000 11,800,000 1,772,6278 933,000 674,664' 8,865,3888 130,317$ 207,6598 1,270,000 8,630,000 3,070,000 3,210,000 7,900,000 3,217,5318 2,070,484' 4,720,000 334,000 3,586,1078 628,8888 3,350,000 5,820,000 1,740,000 483,9108 157,633'8 19,700,000 65,000 133,000 3,180,000 3,080,000 762,00010 1,113,000" 11,680,000' 14,880,000 40,000 1,812,627 28,000 961,000"1 130,000 804,664 - 8,865,388' 2,000 132,317 44,400 252,059 141,000 1,411,000 836,000 9,466,000 605,000 3,675,000 1,830,000 5,040,000 148,000 8,048,000 597,000 3,814,531 353,000 2,423,484 397,000 5,117,000 121,000 455,000 180,485' 3,766,592' 72,000 700,888 622,000 3,972,000 980,000 6,800,00012 376,000 2,116,000 113,000 596,910 - 157,633' 3,460,000 23,160,000' 26-26 Location' Type of Protection Total PITTSBURGH, PA., DISTRICT TABLE 26-K (Continued) OHIO RIVER BASIN (PITTSBURGH DISTRICT): LOCAL PROTECTION PROJECTS (See Section 23 of Text) Estimated Cost Type of Location- Protection Federal Non-Federal Total Wheeling, WV (North Wheeling)' "14 Wall 11,700,000 2,700,000 14,400,000 Wheeling, WV (Wheeling Island)2 14 Wall and levee 13,300,000 2,470,000 15,770,000 Woodlands, WV2 14 Levee 206,000 28,000 234,000 1. All projects are on the Ohio River unless otherwise 8. Latest cost estimate revision 1954 unless otherwise noted. noted. 2. Also see "Other authorized flood control projects." 9. Latest cost estimate revision 1960. 3. Actual cost. 10. Latest cost estimate revision 1966. 4. Reported in detail in an individual report. 11. Latest cost estimate revision 1974. 5. Completed. 12. Latest cost estimate revision 1977. 6. Reported in detail in Annual Report for 1941. 13. Latest cost estimate revision 1978. 7. Reported in detail in Annual Report for 1954. 14. Eligible for deauthorization. TABLE 26-L OHIO RIVER BASIN (PITTSBURGH DISTRICT): RESERVOIRS (See Section 23 of Text) Total Estimated Tributary Basin and Reservoir Stream Cost Allegheny: Conemaugh River, PA' Conemaugh River $ 46,012,411 ' s Crooked Creek, PA' Crooked Creek 4,571,500 ' East Branch Clarion River, PA' Clarion River 9,539,586 ' 3 Kinzua Dam and Allegheny Reservoir, PA and NY' Allegheny River 112,549,087 ' 56 Loyalhanna, PA' Loyalhanna Creek 5,727,531 ' 3 Mahoning Creek, PA' Mahoning Creek 7,138,814 Tionesta, PA' Tionesta Creek 7,788,379 ' Union City, PA' French Creek 14,559,800 ' ' Woodcock Creek, PA' Woodcock Creek 20,400,722 ' 3 Beaver: Berlin, OH' Mahoning River 8,739,987 3 Eagle Creek, OH2 Eagle Creek 12,700,000 24 Michael J. Kirwan, OH' Mahoning River 17,376,097 ' 3 Mosquito Creek, OH' Mosquito Creek 4,253,029 3 Shenango River, PA and OH' Shenango River 40,209,894 3 Monongahela: Stonewall Jackson Lake, WV' West Fork River 206,000,000 ' 5 Youghiogheny River, PA and MD' Youghiogheny River 12,518,834 ' 3 1. Reported in detail in an individual report. 2. Also see "Other authorized flood control projects." 3. Actual cost. 4. Latest cost estimate revision 1954. 5. Latest cost estimate revision in 1985. 6. Includes $3,240,000 cost estimate for Dam Rehabilitation. 26-27 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 26-M INSPECTION OF COMPLETED FLOOD CONTROL PROJECTS (See Section 30 of Text) Project Dates of Inspection Project Dates of Inspection Amsterdam, OH October 1985 Leetonia, OH May 1984 Big Run, PA October 1984 Oil City, PA April 1983 Bradford, PA August 1985 Olean, NY September 1985 Brookville, PA October 1985 Portage, PA August 1982 Buckhannon, WV September 1985 Portville, NY September 1985 Burgettstown-Slovan, PA March 1976 Reynoldsville, PA May 1985 Butler, PA May 1983 Ridgway, PA May 1984 Chartiers Creek, PA Salamanca, NY September 1985 Cannonsburg-Houston Reach April 1985 Stonewood-Nutter Fort, James G. Fulton Reach October 1983 WV July 1983 Colliers, WV October 1982 Sykesville, PA October 1985 Dubois, PA October 1985 Tarentum, PA November 1976 Eldred, PA June 1983 Turtle Creek, PA August 1983 Friendsville, MD October 1985 Washington, PA March 1976 Granville, PA March 1982 Wellsville, OH April 1984 Johnsonburg, PA May 1984 Weston, WV July 1985 Kittanning, PA August 1983 Wilmore, PA August 1982 Latrobe, PA July 1984 Youngstown, PA October 1985 26-28 PITTSBURGH, PA., DISTRICT TABLE 26-N FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION (See Section 32 of Text) Flood Control Activities pursuant to Section 205, Public Law 858, 80th Congress, as amended (preauthorization) Project/Study Identification Fiscal Year Costs Allegheny River, Oil City, PA (plans, specifications and construction) $ 68,648 Robinson Run, Oakdale, PA (detailed project report) 3,063 Root Creek, Bolivar, NY (construction) 2,172 West Little Pine Creek, Etna, PA (detailed project report and plans and specifications) 127,761 Total cost for current fiscal year: $201,644 Emergency Bank Protection - Section 14 of the 1946 Flood Control Act, Public Law 526, 79th Congress Project/Study Identification Fiscal Year Costs Allegheny River, Tionesta, PA (construction) $ 39,997 Beaver River, Bridgewater, PA (initial appraisal report and plans and specifications) 19,905 Elks Creek, Clarksburg, WV (initial appraisal report) 8,485 Greene County, Route 88, PA (initial appraisal report) 3,321 Mahoning River, Highway 139A, Trumbull Co., OH (construction) 129,113 Mahoning River, Warren Townsip, OH (initial appraisal report) 7,424 Ohio River, Chester, WV (construction) 420 Ohio River, McMechen, WV (real estate investigation) 1,525 Plum Creek, Penn Hills, PA (construction) 23 Roberto Clemente Park, PA (construction) 907 Trout Run, Portage, PA (construction) S0 Total cost for current fiscal year: $211,420 Streambank Erosion Control, Evaluation and Demonstration - Section 32, of the 1974 Water Resources Development Act, Public Law 251, 93rd Congress Project/Study Identification Fiscal Year Costs Evaluate Streambank Erosion, Nationwide $ 1 Ohio River Main Stem Demonstration Projects 57 Ohio River Off Main Stem Demonstration Project 77 Rehabilitation of Streambank Demonstration Projects, Ohio River 16 Total cost for current fiscal year: $151 Shoreline Erosion Control Demonstration- Section 54, of the 1974 Water Resources Development Act, Public Law 251, 93rd Congress Fiscal Year Costs Activity $ 8,706 Architect/Engineer Contract for Preparation of Three Reports for the Purpose of Disseminating Information on the Section 54 Program. Three Guides to Low Cost Shore Protection for: 1. Engineers and Contractors 2. Local government officials 3. Property owners 26-29 ST. PAUL, MN DISTRICT* District comprises western Wisconsin, major portion of Minnesota, northern and eastern North Dakota, and small portions of northeastern South Dakota and northern and northeastern Iowa embracing drainage basins of Mississippi River and tributaries from its source to mile 614 above mouth of Ohio River; Red River of the North and tributaries; those streams north of Missouri River Basin in North Dakota; and U.S. waters of Lake of the Woods and its tributaries. That section of Mississippi River above mile 614 is included in report on Mississippi River between Missouri River and Minneapolis, Minnesota. IMPROVEMENTS Navigation Page 1. Minnesota River, MN ..................... 27-2 2. Mississippi River between Missouri River and Minneapolis, MN ..................... 27-2 3. Reservoirs at Headwaters of Mississippi River, MN ....................... 27-2 4. St. Croix River, MN & WI..................27-3 5. Warroad Harbor and River, MN ........... 27-3 Flood Control 6. Bassett Creek, MN ........................ 27-3 7. Big Stone Lake and Whetstone River, MN and SD.........................27-4 8. Black Bear and Miller Lakes, Crow Wing County, MN ................... 27-4 9. Bonnes Coulee, Velva, ND ................. 27-5 10. Chaska, M N ............................... 27-5 11. Devils Lake, ND ........................... 27-6 12. Eau Galle River, WI ....................... 27-6 13. Enderlin, Maple River, ND ................ 27-6 14. Homme Lake and Dam, ND ............... 27-7 15. Irving Township at Nicols Road, Jackson County, WI.......................27-7 16. Lac qui Parle Lake, Minnesota River, MN... 27-8 17. La Farge Lake and channel improvement, WI..........................27-8 18. Lake Ashtabula and Baldhill Dam, Sheyenne River, ND.......................27-8 19. Lake Darling, Souris River, ND ............ 27-9 20. Lake Traverse and Bois de Soiux River, SD and MN.........................27-9 21. Mankato and North Mankato, MN.........27-9 22. Middle River at Argyle, MN ............... 27-10 23. Minnesota River at Le Sueur, MN.........27-11 24. Prairie du Chien, WI ..................... 27-11 25. Red Lake River, MN, including Clearwater River, MN ................... 27-11 26. Red River of the North at Argusville, ND... 27-12 27. Red River of the North drainage basin, MN, SD & ND ............................ 27-12 28. Red River of the North at Halstad, MN.....27-13 29. Redwood River at Marshall, MN..........27-13 30. Rochester, MN ............................ 27-14 31. Roseau River, MN........................27-14 32. Shepard Road, Mississippi River, St. Paul, M N ............................. 27-14 33. Sheyenne River, ND......................27-15 34. State Road and Ebner Coulees, WI.........27-15 35. Twin Valley Lake, Wild Rice River, MN .... 27-16 36. Veteran's Memorial Levee, Mississippi River, Hastings, MN..........27-16 37. Wild Rice River, Mahnomen County, MN . .27-17 38. Wild Rice River-South Branch and Felton Ditch, MN ........................ 27-17 39. Winona, MN ............................. 27-17 40. Inspection of completed flood control projects...........................27-18 Miscellaneous 41. Other work under special authority ....... 27-18 General Investigations 42. Surveys..................................27-18 43. Collection and study of basic data ........ 27-18 44. Continuation of planning and engineering ............................. 27-18 45. Advance engineering and design ......... 27-18 Tables Table 27-A Table 27-B Table 27-C Table 27-D Table 27-E Table 27-F Table 27-G Table 27-H Table 27-I Table 27-J Table 27-K Table 27-L Cost & Financial Statement ..... .. 27-19 Authorizing Legislation .......... 27-22 Other Authorized Navigation Projects .............. 27-23 Not Applicable Other Authorized Flood Control Projects .................. 27-24 Not Applicable Deauthorized Projects ............. 27-25 Reservoirs at Headwaters of Mississippi River.................27-26 Navigation Work Under Special Authorization ............ 27-27 Red River of the North Drainage Basin: Active Units in Comprehensive Basin Plan.......................27-27 Inspection of Completed Flood Control Projects..................27-28 Flood Control Work Under Special Authorization ............ 27-29 27-1 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Navigation 1. MINNESOTA RIVER, MN Location. Rises in Big Stone Lake, MN and SD, and flows southeasterly about 224 miles to Mankato, MN, thence northeasterly about 106 miles to join the Mississippi River opposite St. Paul, MN. (For general location see Geological Survey map of Minnesota.) Previous projects. For details see page 1890 of Annual Report for 1915, and page 1105 of Annual Report for 1938. Existing project. Provides 9-foot depth below flat pool level of Mississippi River lock and dam 2 from mouth to mile 14.7, one-half mile above the railway bridge at Savage, MN, and 4-foot depth from mile 14.7 to 25.6 at Shakopee, MN. For details see page 1018 of Annual Report for 1965. (See table 27-B for authorizing legislation.) Local cooperation. Fully complied with. See also page 1074 of Annual Report for 1967. Terminal facilities. There are privately-owned terminals at miles 9, 13.1, 14.5, and two at mile 14.7. Operations and results during fiscal year. Maintenance: Condition surveys cost $5,969. Engineering and administrative costs amounted to $636. Condition at end of fiscal year: Work on project for 4-foot depth was completed in 1931. The United States owns 10 acres of land in fee 2 miles east of Savage, MN, and easements on 123.08 acres of land. 46.20 acres have been transferred from the Department of the Army and Department of the Air Force to the project. Navigation from mouth to Shakopee was practicable for drafts not in excess of 3 feet. A contract for work under 1958 authorization for a 9-foot channel started in May 1966 was terminated in January 1967 when 56 percent complete. A channel dredging contract awarded in June 1967 was completed in August 1968. Total costs for existing project to September 30, 1985, were $4,210,481, of which $1,940,180 was for new work and $2,270,301 for maintenance. In addition, cost from contributed funds was $139,671 for dredging to 9-foot depth undet provisions of section 4, River and Harbor Act of 1915, and $219,531 for work done for the State of Minnesota relative to modification of the project. 2. MISSISSIPPI RIVER BETWEEN MISSOURI RIVER AND MINNEAPOLIS, MN For report on this improvement see chapter on Mississippi River between Missouri River and Minneapolis, Minnesota. 3. RESERVOIRS AT HEADWATERS OF MISSISSIPPI RIVER, MN Location. Reservoirs are on the Mississippi River and several of its tributaries in Itasca, Beltrami, Hubbard, Aitkin, Cass and Crow Wing Counties, MN. (See table 27-H on reservoirs.) Previous projects. For details see page 1888 of Annual Report for 1915, and page 1098 of Annual Report for 1938. Existing project. Provides for reconstruction from timber to concrete at Winnibigoshish, Leech Lake, Pokegama, Sandy Lake and Pine River Dams, and construction of a concrete dam at Gull Lake. Pokegama was built on bedrock and the others on pile foundations. A portion of Leech Lake Dam from piers 26 to 39 was replaced with an earth fill. Constructed three dikes at Winnibigoshish, four at Pokegama, two at Sandy Lake, and 16 at Pine River. Sandy Lake Dam includes a lock 160 feet long, 30 feet wide, with a maximum lift of 9.5 feet and a depth of 2.5 feet on lower sill at low water which was converted to use as a spillway. (See table 27-B for authorizing legislation.) Local cooperation. Fully complied with. Terminal facilities. None. Operations and results during fiscal year. Maintenance: Reservoirs were operated as required, recreation facilities were maintained, and surveys, repairs, and reports were made by hired labor at a cost of $921,737. Reservoirs were operated by contract at a cost of $119,346. Physical security cost $7,069 by hired labor and $10,213 by contract. Periodic inspection and dam safety costs were $13,553 by hired labor and $9,098 by contract. Cultural resource investigation cost $16,838 by hired labor and $43,386 by other Corps of Engineers districts. Discharge observation, gage reading and pool regulation cost $122,367 by hired labor. Miscellaneous engineering and design cost $53,951. A seal coat roads contract at Gull Lake and Lake Winnibigoshish cost $30,000. An archeological survey contract cost $153, and discharge observation contracts, $720. Work by other Corps of Engineer districts for a recreation use workshop, a centennial celebration and dam stability and safety analysis cost $476, $6 and $9,942, respectively. Real estate was managed by other Corps of Engineers districts at a cost of $15,227 by contract, $9,328, and by hired labor, $5,498. Cooperative stream gaging with U.S. Geological Survey cost $28,130. Supervision and administration and other miscellaneous costs were $256,929. Condition at end of fiscal year: Existing project was completed in 1937. Flowage rights were acquired on all lands affected by construction, maintenance, and operation of reservoirs. A total of 1,672.26 acres in fee are owned by the United States. The United States has easements, flowage rights, and other rights of use on another 296,334.44 acres. Structures are in fair condition. Recreation facilities for public use are being constructed intermittently at all reser- 27-2 ST. PAUL MINNESOTA DISTRICT voir areas. (See table 27-H for capacities and costs by reservoir.) 4. ST. CROIX RIVER, MN & WI Location. From source in northwestern Wisconsin, flows southwesterly and then southerly about 164 miles to Mississippi River at Prescott, WI, about 41.7 miles below lower Burlington Northern railway bridge, Minneapolis, MN. For its greater part, forms boundary between Minnesota and Wisconsin. (See Geological Survey map of Minnesota.) Existing project. Provides for maintenance of a channel, 9 feet in depth and of suitable width from mouth to Stillwater, MN, 24.5 miles, created by improvement of upper Mississippi River; a channel 3 feet deep at mean low water between Stillwater and Taylors Falls (27.3 miles); improvement of harbor and waterfront at Stillwater; and a small-boat harbor at Hudson, WI, currently classified "inactive." Estimated (1981) Federal cost of new work is $820,400. Latest authorization (1954) for maintenance work on reach between Stillwater and Taylors Falls is limited to an expenditure not exceeding $5,000 per year. (See table 27-B for authorizing legislation.) Local cooperation. Fully complied with for completed portion. For Hudson Harbor, see the Annual Report of 1970 for requirements. Terminal facilities. At Stillwater there is a concrete paved levee and a piling-and-timber trestle wharf on right bank. At other points along river, landing may be made on banks. Facilities are considered adequate for existing commerce. Operations and results during fiscal year. Maintenance: Channel dredging with the government pipeline dredge WILLIAM A. THOMPSON removed 60,581 cubic yards of material at a cost of $161,546. Condition at end of fiscal year: All new work was completed in 1930, except subsequently authorized harbor at Hudson which was reclassified to "inactive" on April 20, 1982. The United States owns 2.75 acres of land in fee at Taylors Falls and has easements over 7.57 acres of land at Bayport, MN. Extension to provide a 9-foot channel from mouth to Stillwater was completed August 12, 1938, when full pool at dam 3 of Mississippi River canalization project was reached. Minimum draft from Stillwater to Taylors Falls is about 1 foot at extreme low water, and from mouth to Stillwater, 9 feet. Maintenance of the 3-foot channel is limited to requests by the National Park Service which manages this reach under the Wild and Scenic Waterways classification. 5. WARROAD HARBOR AND RIVER, MN Location. At southwestern extremity of Lake of the Woods, 36 miles west of mouth of Rainy River. (See NOAA Nautical Chart 14999). Existing project. Provides for a channel 8 feet deep from landing at Warroad to deep water in lake, channel being 9,200 feet long, 200 feet wide within harbor, and 300 feet wide out in lake; for a turning basin 500 by 900 feet to a depth of 8 feet; and for a pile-brush stone jetty on north side of channel extending from shore 700 feet into the lake. For additional details see page 1027 of Annual Report for 1965. Portion of dredging of entrance channel and turning basin to complete project width and depth was considered unnecessary to meet present navigation requirements, and classified inactive was deauthorized on August 5, 1977, under Section 12 of Public Law 93-251. Estimated cost (1954) of this portion was $355,200. (See table 27-B for authorization legislation.) Local cooperation. None required. Terminal facilities. There is one publicly owned wharf. There are two commercial fish wharves, one of which is served by a spur track, and a number of minor wharves, all privately owned. Facilities are adequate for existing commerce. Operations and results during fiscal year. Maintenance: Environmental review cost $2,848 by hired labor. Administrative costs were $143. Condition at end of fiscal year: Project is complete. Prospective jetty completed in 1910 and reconstructed as a rubble mound in 1929 is in good condition. Turning basin at Warroad wharves was completed in 1911, and a channel 200 feet wide and 8 feet deep in 1915. Controlling depth in river channel and lake approach channel was 6 feet below low-water datum for a minimum width of 100 feet. A walkway on the jetty is provided for public use. A revetment wall, constructed under Section 2 of Public Law 269, 69th Congress, in accordance with Article VIII of the Lake of the Woods Treaty, has deteriorated and will require future maintenance. Flood Control 6. BASSETT CREEK, MN Location. In Hennepin County and Minneapolis, Minnesota, on Bassett Creek, a tributary of the Mississippi River. (For general location, see Geological Survey map of Minnesota.) Existing project. The proposed project consists of nonstructural and structural flood control measures. Nonstructural measures include continuation of existing floodplain regulations, flood insurance and forecasting, and flood warning. Principal structural measures consist of six small control structures in the upper watershed to temporarily impound floodwaters and a new tunnel (part of which is being constructed on a cooperative basis with the Minnesota Department of Transportation) in a highly urbanized area of Minneapolis to replace the existing tunnel outletting Bassett Creek to the Mississippi River. Also included in the plan are a limited reach of channel widening, bridge removals, culvert replacements, a weir structure, a flood storage area, and a railroad bridge replacement. Estimated Federal cost (1985) for new 27-3 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 work is $20,800,000 and $6,185,000 is to be contributed by local interests. Project was authorized by the 1976 Water Resources Development Act. Local cooperation. See Annual Report for 1977 for requirements. A local assurance agreement will be required after determination of cost sharing policies. By resolutions approved September 12, 1974, October 31, 1975, and December 11, 1981, the City of Minneapolis has indicated its willingness and intention to meet the requirements of local cooperation. By letter dated October 29, 1982, the City of Minneapolis indicated its intent to participate in innovative project financing. Operations and results during fiscal year. New Work: Preconstruction planning was continued at a cost of $14,668. Condition at end of fiscal year: Preconstruction planning is in progress. 7. BIG STONE LAKE AND WHETSTONE RIVER, MN AND SD Location. On Minnesota River near Ortonville and Odessa, MN, and Big Stone City, SD, at the outlet of Big Stone Lake and in Big Stone and Lac qui Parle Counties, MN, and Grant County, SD. (For general location, see Geological Survey map of Minnesota.) Existing project. Provides for a dam and reservoir on Minnesota River above U.S. Highway 75, modification of Big Stone Lake outlet dam and silt barrier, bank stabilization along lower reach of Whetstone River, channel improvement on Minnesota River for 3 miles below outlet control dam at Big Stone Lake along with necessary relocations and acquisition of lands. These improvements would be made for wildlife conservation and development, flood control, and recreation. For additional details see Annual Report for 1970. Estimated Federal cost (1983) for new work is $12,300,000 and $153,000 to be contributed by local interests. Project was authorized by 1965 Flood Control Act (H. Doc. 579, 87th Cong., 2d sess., contains latest map; and H. Doc. 193, 88th Cong., 2d sess.). Local cooperation. See Annual Report for 1968 for requirements. The project requires sponsorship from both the States of Minnesota and South Dakota. Formal resolution of assurances adopted by the Upper Minnesota River Watershed District on June 10, 1969, arid accepted by the District Engineer on November 3, 1969. Formal resolution of assurances adopted by the East Dakota Conservancy Sub-District for South Dakota on October 23, 1969, was furnished on November 18, 1969, and accepted by the District Engineer on November 19, 1969. Supplemental assurances covering the requirements of Public Law 91-646 were provided by the Upper Minnesota Watershed District on August 13, 1974, and by the East Dakota Conservancy Sub-District on April 15, 1976. Rights-of way for construction on the Whetstone River and the entire cash contribution of $153,000 for the project were furnished by the local sponsors on December 21, 1981. Operations and results during fiscal year. New Work: Minnesota River channel construction contract costs were $460,028. A Big Stone Lake outlet and silt barrier contract cost $180,000. Engineering and design, supervision and administration and other miscellaneous costs were $160,060. Maintenance: Structure was operated and maintained and inspections and evaluations performed at a cost of $115,443 by hired labor. Discharge observation gages and pool regulation cost $28,442. Coop stream gaging by other government agencies cost $36,990. Real estate management by the North Central Division cost $3,739. Periodic inspection and dam failure planning cost $2,365 by other districts and $16,034 by hired labor. Engineering and design and supervision and administration cost $5,749 and $18,656, respectively. Condition at end of fiscal year: Construction of the new dam above Highway 75 and roads are completed. Surveys for land lines are complete, and the land acquisition program is complete. The first land payment was made on November 28, 1969, and 128 tracts have been purchased. A general plan between the Secretary of the Army and the Secretary of the Interior for administrating the use of waters, land, or interests therein has been consummated, and a cooperative agreement between the Corps of Engineers and the U.S. Fish and Wildlife Service was approved. On March 31, 1975, the Secretary of the Army transferred lands in the project not required for Corps of Engineers operation and maintenance to the Department of Interior. The transfer of property was accepted by the Department of the Interior on May 21, 1975. Construction on the Whetstone River portion of the upstream works is complete. The final construction contract for the Minnesota River work was awarded in May 1983 and work is in progress. 8.BLACK BEAR AND MILLER LAKES, CROW WING COUNTY, MN Location. Black Bear and Miller Lakes are near the center of the State, 20 miles north of Brainerd, Minnesota. The two lakes lie adjacent to the left (east) side of the Mississippi River. Miller Lake is linked to Black Bear Lake by a very short channel. In turn, Black Bear Lake is joined to the Mississippi River by a one-half mile creek. Existing project. Spring high water on the Mississippi River backs up the creek channel, flooding shoreline properties and causing damages to buildings and related facilities. Some flooding is experienced here every 3 to 5 years. The proposed project consists of an embankment across the creek approximately 300 feet upstream of its juncture with the Mississippi River. This structure will have a culvert extending through it which would be closed off during periods of high flow on the Mississippi 27-4 ST. PAUL MINNESOTA DISTRICT River. Residences around the two lakes would be protected up to the 500-year flood evaluation on the Mississippi River with 3 feet of freeboard. Total Federal cost for the project is estimated at $350,000. The project was approved by the Chief of Engineers for construction in March 1985 under the authority contained in Section 205 of the 1948 Flood Control Act, as amended. Local cooperation. A local assurance agreement was adopted by Crow Wing County, the local sponsor, in July 1985. Local interests are required to provide without cost to the United States all lands, easements, and rights-of-way, including ponding and borrow areas, necessary for the construction, operation, and maintenance of the project; accomplish all alterations and relocations of buildings, streets, and utilities, except for those utilities which are an integral part of project structures; hold and save the United States free from damages caused by the construction and subsequent operation and maintenance of the project, except damages due to the fault or negligence of the United States or its contractors; provide all costs in excess of the $4,000,000 Federal cost limitation; maintain and operate the project after completion without cost to the United States in accordance with regulations prescribed by the Secretary of the Army; prevent any encroachment on constructed works and ponding areas that would interfere with the proper functioning of the project; and, if ponding is impaired, provide promptly and without cost to the United States, substitute storage or equivalent pumping capacity; comply with the applicable provisions of the "Uniform Relocations Assistance and Real Property Acquisition Policies Act of 1970", Public Law 91-646, approved January 2, 1971; comply with Section 601 of Title VI of the Civil Rights Act of 1964 (Public Law 88-352) and Department of Defense Directive 5500.11. Operations and results during fiscal year. New Work: Engineering and design and study costs were $59,680. Condition at end of fiscal year: A contract for flood protection at Black Bear and Miller Lakes was awarded in September 1985. 9. BONNES COULEE, VELVA, ND Location. In McHenry County adjacent to the City of Velva in north central North Dakota about 24 miles southeast of Minot. Existing project. Provides for erosion control along an approximate 375 footlong reach of Bonnes Coulee extending through a township road bridge near the westerly city limits of Velva. The project consisted of realigning and reshaping the channel and placing rock-fill and sand and gravel bedding along both banks of the channel. Total Federal cost of the project is $58,500. The project was approved by the Chief of Engineers for construction on September 6, 1984, under the authority contained in Section 14 of the 1946 Flood Control Act, as amended. Local cooperation. Local cooperation agreements were adopted by McHenry County in July 1985. Local interests are required to provide without cost to the United States all lands, easements, and rights-of-way necessary for construction, operation, and maintenance to the project; accomplish without cost to the United States all required alterations and relocations in sewer, water supply, drainage, and other utility facilities; hold and save the United States free from damages due to the construction, operation, and maintenance of the project except where such damages are due to the fault or negligence of the United States or its contractors; maintain the project after completion; assume full responsibility for all project costs in excess of the Federal cost limit of $250,000; provide a cash contribution for project costs in proportion to any special benefits to non-public property; comply with applicable provisions of the Uniform Relocations Assistance and Real Property Acquisition Policies Act of 1970, Public Law 91-646, approved January 2, 1971,,in acquiring lands, easements, and rights-of-way for construction and subsequent maintenance of the project and inform affected persons of pertinent benefits, policies and procedures in connection with said Act; comply with the Section 601 of Title VI of the Civil Rights Act of 1964 (Public Law 88-352) and Department of Defense Directive 5500.11 issued pursuant thereto and published in Part 300 of Title 32, Code of Federal Regulations, in connection with the construction and subsequent maintenance and operation of the project. Operations and results during fiscal year. New Work: A bank protection contract cost $29,001. Engineering and design, and supervision and administration cost $11,377. Condition at end of fiscal year: Construction of the project was completed in January 1985 and responsibility for operation and maintenance of the project was officially transferred to McHenry County in March 1985. 10. CHASKA, MN Location. In Carver County in south-central Minnesota on the Minnesota River. (For general location, see Geological Survey map of Minnesota.) Existing project. The plan of improvement consists of a levee and interior drainage works along the Minnesota River, flood diversion and bypass channels on Chaska Creek and East Creek, and appropriate floodplain regulation measures. Principal project features include: approximately 1.1 miles of upgraded levee, 0.6 mile of new levee, and one pumping station on the Minnesota River; 0.9 mile of diversion channel on Chaska Creek; and 0.5 mile of flood bypass channel, 0.3 mile of channel improvement, and a 1,500-foot conduit on East Creek. Approximately 1.6 miles of paved recreation trails on top of the levee and around Courthouse Lake are also included in the proposed plan. Estimated Federal cost (1985) for new work is $16,600,000 and $4,965,000 is to be contributed by local interests. Project was authorized by the 1976 27-5 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Water Resources Development Act. (H. Doc. 644, 94th Congress, 2d sess., contains latest published map.) Local cooperation. See Annual Report for 1977 for requirements. A local assurance agreement will be required prior to the start of construction. By letter of August 19, 1982, the City of Chaska indicated its willingness and intention to meet the requirements of local cooperation. By letter of October 16, 1985, the City of Chaska indicated its intent to participate voluntarily in project financing as proposed in legislation being considered by Congress. Operations and results during fiscal year. New Work: Preconstruction planning was continued at a cost of $316,949. Condition at end of fiscal year: Preconstruction planning is in progress. Plans and specifications for the first state of construction are substantially complete. 11. DEVILS LAKE, ND Location. In Ramsey County in north central North Dakota about 80 miles west of Grand Forks, North Dakota. (For general location, see Geological Survey Map of North Dakota.) Existing project. Provides for a system of levees and interior flood control facilities at the head of Creel Bay. The main embankment across Creel Bay will be 1,810 feet long and vary from 0 to 27 feet high. The south Creel Bay tieback embankment will be 1,030 feet long and vary from 0 to 3 feet high. The north Creel Bay tieback embankment will be 2,400 feet long and would vary from 0 to 8.5 feet high. The south embankment will be 3,100 feet long and vary from 0 to 9.5 feet high. The interior flood control system will consist of large holding ponds immediately north and south of the city's sewage lagoons, a 16,000 gallon per minute pumping station and a system of ditches and culverts linking the ponds to the pumping station. Total Federal cost (1984) for the proposed project is estimated at $2,130,000. The project was approved by the Chief of Engineers for construction August 15, 1983, under the authority contained in Section 205 of the 1948 Flood Control Act, as amended. Local cooperation. See Annual Report for 1983 for requirements. A local assurance agreement required by Public Law 91-611 was adopted by the City of Devils Lake in August 1983. Operations and results during fiscal year. New Work: Stage II construction contract cost $1,277,213. Engineering and design cost $38,517 by hired labor. North Central Division real estate management cost $1,535. Supervision and administration costs were $95,802. Condition at end of fiscal year: Construction for the remaining features of the project was continued. 12. EAU GALLE RIVER, WI Location. At and in vicinity of Spring Valley, WI, on Eau Galle River 30 miles above its mouth at Chippewa River, and its tributary, Mines Creek, which flows through the village. Spring Valley is about 45 miles east of St. Paul, MN, and 36 miles west of Eau Claire, WI. (See Geological Survey map for Wisconsin for general location.) Existing project. Authorized plan of improvement as modified by further studies includes a retarding dam and reservoir on Eau Galle River immediately upstream from Spring Valley, and remedial works on Mines Creek including channel enlargement, a low levee, and a drop structure. Project provides for earth and rockfill dam, an uncontrolled outlet and an uncontrolled spillway emerging above Mines Creek. See page 1030 of Annual Report for 1965 for further details. Proposed improvements on Burghardt Creek were eliminated. Improvements provide complete protection near Spring Valley for standard project flood, and below that point in decreasing value in proportion to distance from reservoir. Permanent conservation pool will serve a local need for a recreational area. Project was authorized by 1958 Flood Control Act (S. Doc. 52, 84th Cong., 1st sess., contains latest published map.) Local cooperation. Fully complied with. See page 1083 of Annual Report for 1967. Operations and results during fiscal year. Maintenance: Structure and recreation facilities were operated and maintained, and inspections, investigations and evaluations were performed at a cost of $306,268 by hired labor and $23,487 by contract. A recreational maintenance road repair contract cost $74,000. Real estate management by the North Central Division cost $2,924 and dam failure planning by other Corps districts, $530. Discharge observation and pool regulation cost $15,287. Cooperative stream gaging cost $7,150. Administrative and other miscellaneous engineering costs were $73,339. Condition at end of fiscal year: Mines Creek improvements were substantially completed in 1964: minor work was accomplished in 1966. A contract for dam, spillway, and discharge channel, started July 1, 1965, was completed in October 1968. Recreational facilities have been provided. Remedial work to repair eroded gutters and road ditches was completed in September 1973. Repair of failing discharge conduit by installing a steel liner was completed in April 1982. 13. ENDERLIN, MAPLE RIVER, ND Location. In Ransom County in southeastern North Dakota on the Maple River about 45 miles southwest of Fargo, North Dakota. (For general location, see Geological Survey Map of North Dakota.) Existing project. The project at Enderlin involves a system of levees along the right bank of the main 27-6 ST. PAUL MINNESOTA DISTRICT stem and the left bank of the South Branch of the Maple River. The total levee system would be about 1.2 miles long and would have an average height of about 8 feet. Other features of the project include channel improvements on the south branch, replacement of the Soo Line railroad bridge, and interior drainage facilities consisting of three ponding areas with gated outlet conduits. To prevent failure of the channel and levee by erosion, rip-rapping would be provided in selected reaches. Total Federal cost (1984) for the proposed project is estimated at $4,000,000. The project was approved by the Chief of Engineers for construction August 11, 1982, under the authority contained in Section 205 of the 1948 Flood Control Act, as amended. Local cooperation. See page 27-5 of Annual Report for 1982 for requirements. A local assurance agreement required by Public Law 91-611 was adopted by the City of Enderlin in July 1982. Operations and results during fiscal year. New Work: A main stem Phase II levee contract cost $10,359. A Phase III Highway 46 frontage road levee contract cost $296,637. A Phase IV contract on the south branch of the Maple River cost $1,459,162. A relocations contract with the Soo Line RR cost $60,000. Engineering and design by contract and hired labor cost $68,542. North Central Division real estate costs were $134. Supervision and administration cost $3,521. Condition at end of fiscal year: Work on Phase II is completed. A contract for Phase III involving floodbarrier facilities in the northern sector of the city was substantially completed in August 1985. Phase IV which includes all of the facilities on the south branch of the Maple River was awarded in September 1984. Work on Phase IV, the final phase of the project, is 82 percent complete. 14. HOMME LAKE AND DAM, ND Location. Dam is on South Branch of Park River about 4 miles upstream from Park River, ND, and 62.1 miles above mouth of Park River. South, Middle, and North Branches, headwater streams of Park River, rise in Cavalier County in northeastern North Dakota and flow easterly to an almost common confluence near Grafton, ND, forming main stream which flows easterly 35 miles to join Red River of the North about 35 miles south of the international boundary. (For general location, see Geological Survey map of North Dakota.) Existing project. See page 1285 of Annual Report for 1962. Project was authorized as Park River Reservoir by 1944 Flood Control Act (S. Doc. 194, 78th Cong., 2d sess.), and redesignated Homme Reservoir and Dam by Public Law 435, 80th Congress, 2d session. Latest published map is in project document. Local cooperation. Fully complied with. Total costs for all requirements of local cooperation under terms of project authorization, including required non-Federal contributions, were $62,800. In addition, local interests contributed $16,220 for construction of a water supply outlet through dam and incurred other costs of $19,600. Operations and results during fiscal year. Maintenance: Structure was operated and maintained, and inspections and evaluations performed at a cost of $99,956. Condition at end of fiscal year: Project completed in June 1956 except for additional recreational facilities which have been done intermittently since that time. Construction began in April 1948 and major structures completed in May 1951. Structures are in good condition. Government has acquired 395 acres of land in fee and easements over 7.8 acres of land for project. An additional 6.3 acres of land have been donated for recreational development and 3.75 acres have been acquired due to bank erosion bordering the project. 15. IRVING TOWNSHIP AT NICOLS ROAD, JACKSON COUNTY, WI Location. In Jackson County in west central Wisconsin on the Black River, approximately 6 miles south of Black River Falls. The project site is near Nicols Road. Existing project. Erosion is threatening Nicols Road in Irving Township, Wisconsin. The proposed project would protect the road and consists of the placement of rockfill at the toe of the eroding bank and revegetation of the upper part of the river bank. Total Federal cost (1985) for the project is estimated at $155,200. The project was approved for construction in May 1985, under the authority contained in Section 14 of the 1946 Flood Control Act, as amended. Local cooperation. Local cooperation agreements were adopted by Irving Township in July 1985. Local interests are required to provide without cost to the United States all lands, easements, and rights-of-way necessary for construction, operation, and maintenance to the project; accomplish without cost to the United States all required alterations and relocations in sewer, water supply, drainage, and other utility facilities; hold and save the Unites States free from damages due to the construction, operation, and maintenance of the project except where such damages are due to the fault or negligence of the United States or its contractors; maintain the project after completion; assume full responsibility for all project costs in excess of the Federal cost limit of $250,000; provide a cash contribution for project costs in proportion to any special benefits to non-public property; comply with applicable provisions of the Uniform Relocations Assistance and Real Property Acquisition Policies Act of 1970, Public Law 91-646, approved January 2, 1971, in acquiring lands, easements, and rights-of-way for construction and subsequent maintenance of the project and inform affected persons of pertinent benefits, policies and procedures in connection with said Act; comply with 27-7 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 the Section 601 of Title VI of the Civil Rights Act of 1964 (Public Law 88-352) and Department of Defense Directive 5500.11 issued pursuant thereto and published in Part 300 of Title 32, Code of Federal Regulations, in connection with the construction and subsequent maintenance and operation of the project. Operations and results during fiscal year. New Work: Engineering and design and study costs were $14,290. Condition at end of fiscal year: Plans and specifications for the proposed project were completed in July 1985. A contract was awarded in September 1985. 16. LAC QUI PARLE LAKE, MINNESOTA RIVER, MN Location. Works covered by this project lie along Marsh Lake and Lac qui Parle and the Minnesota River between head of Marsh Lake and Granite Falls, MN. (For general location, see Geological Survey map of Minnesota.) Existing project. See page 1291 of Annual Report for 1962. Local cooperation. None required. Operations and results during fiscal year. Maintenance: Project was operated and maintained, and inspections and evaluation performed at a cost of $417,262. A recreational maintenance contract cost $40,011 and a bank stability contract for the Chippewa Diversion cost $60,000. Condition at end of fiscal year: Project has been operated by the Government since transfer from State of Minnesota to the United States in September 1950. The United States owns fee title to 517.62 acres of land and easements on 19,859.47 acres of land. In 1957, 60.1 acres were withdrawn from public lands for use by the Department of the Army. Land acquisition is complete. Construction under present plan of improvement was started in September 1941 and completed in December 1951 except for recreational facilities. All structures are in good condition. 17. LA FARGE LAKE AND CHANNEL IMPROVEMENT, WI Location. Rises in Monroe County in southwestern Wisconsin and flows south and southwest through Vernon, Richland, and Crawford Counties emptying into Wisconsin River about 16 miles above junction of latter stream with Mississippi River. (For general location see Geological Survey map of Wisconsin.) Existing project. Provides for a dam and impoundment of the Kickapoo River about 1 mile upstream from village of La Farge, operated for flood control, fish and wildlife conservation, general recreation, and a reduction of aggradation downstream from the dam, and supplemental protection at Soldiers Grove and at Gays Mills by means of levees, supplementary channel improvement, and interior drainage facilities. See Annual Report for 1975 for details. Estimated Federal cost (1976) for new work is $55,400,000. Project was authorized by 1962 Flood Control Act (H. Doc. 557, 87th Cong., 2d sess., contains latest published map.) Local cooperation. None required for construction of La Farge Lake. See page 1087 of Annual Report for 1967 for requirements for local protection works. Local interests have not been requested to furnish assurances. Operations and results during fiscal year. New Work: Engineering and Design by hired labor cost $14,299 and by contract, $22,706. Administrative and miscellaneous costs were $1,367. Maintenance: Project was operated and maintained at a cost of $27,484. Condition at end of fiscal year: General and Real Estate design memorandums and detailed plans for the La Farge Dam and spillway and for relocations have been completed. Land acquisition negotiations began in December 1968. The first land payment was made on January 15, 1969, and the land acquisition program is 80 percent complete. Contracts for excavation of the left abutment, for test wells, and for construction of the outlet works and right abutment have been completed. A study of alternatives has been completed. Funds to complete the authorized project have been withheld and all further construction has been indefinitely suspended. Work has been accomplished to provide for completion of relocation work left partially completed when construction was suspended. Soldiers Grove has relocated out of the floodplain area after receiving funds from other agencies. A study of a modified dry dam was completed early FY 1985. On the basis of the study results, it was recommended that no further work be done to establish the economic feasibility of a dry or wet dam at La Farge and that the La Farge Lake and channel improvement project be deauthorized. 18. LAKE ASHTABULA AND BALDHILL DAM, SHEYENNE RIVER, ND Location. Baldhill Dam is on the Sheyenne River, 16 miles upstream from Valley City, ND, and about 271 miles above mouth. Sheyenne River rises in central North Dakota and flows 500 miles generally southeast to enter Red River of the North about 10 miles north of Fargo, ND. (For general location see Geological Survey map of North Dakota.) Existing project. See page 1287 of Annual Report for 1962. Project was authorized by Flood Control Act of 1944 (S. Doc. 193, 78th cong., 2d sess., contains latest published map). Reservoir above Baldhill Dam was designated as Lake Ashtabula by Public Law 772, 81st Congress, 2d session. Local cooperation. See page 1288 of Annual Report for 1962. Complied with except for construction of Fargo diversion dam and ditch for which 27-8 ST. PAUL MINNESOTA DISTRICT assurances furnished by the City of Fargo were approved by the Secretary of War on June 26, 1947. Necessity for this feature will be reviewed. Operations and results during fiscal year. Maintenance: Project was organized and maintained, and inspections, investigations, monitoring and evaluations were performed at a cost of $410,512 by hired labor and $128,106 by contract. Dam instrumentation, stability and safety assurance cost $205,875. Real Estate Management by the North Central Division cost $11,391. Dam failure, planning and periodic inspection by other Corps' districts cost $3,552. Missouri River Division soils testing cost $47,884. U.S. Fish and Wildlife Service coordination and cooperative stream gaging with U.S. Geological Survey cost $5,511 and $49,080, respectively. Administrative and other miscellaneous costs were $93,820. Condition at end of fiscal year:Project completed in March 1956 except construction of recreational facilities which is being accomplished intermittently. United States owns 7,816.5 acres of land in fee and easements on 666.2 acres. Construction initiated in July 1947 and major features completed in November 1950. Dam was placed in permanent operation in spring of 1951. Structures are in good condition. 19. LAKE DARLING, SOURIS RIVER, ND Location. On the Souris River in Ward, Renville, McHenry, and Bottineau Counties in northwestern North Dakota. The existing Lake Darling Dam, which is to be raised, is located about 20 miles northwest of Minot, North Dakota. The project also includes features at the communities of Sawyer and Velva and at various locations along the 358-mile U.S. portion of the Souris River. (For general location see Geological Survey Map of North Dakota.) Existing project. The Lake Darling project provides for raising Lake Darling design pool by approximately 4 feet. The project also provides for other work on the Souris River such as levee improvements at Velva, Sawyer, and six subdivision areas between Burlington and Minot, floodproofing of rural residences, modification of refuge structures in the Upper Souris and J. Clark Salyer Refuges, and bridge stabilizations relocations in the reservoir. The work is a portion of the Burlington Dam project which required post-authorization approval prior to construction. However, Congress has directed the Corps not to take further actions to construct the Burlington Dam until expressly directed to do so. Estimated Federal cost (1985) for new work is $56,000,000. Project was authorized by 1982 Energy and Water Development Appropriations Act, Public Law 97-88 approved De- .cember 4, 1981. Local cooperation. See Annual Report for 1983 for requirements. Representatives of the water resource districts from Ward, Renville, McHenry, and Bottineau Counties and the Oak Creek drainage area agreed to become members of a Souris River Joint Board for flood control, which would serve as local sponsor for the project. A local cooperation agreement for construction at Velva was signed in November 1984 and other local cooperation agreement will be prepared for the remainder of the Lake Darling project after a decision has been made on cost sharing for the entire project. Operations and results during fiscal year. New Work: Preconstruction planning for the Lake Darling unit was continued at a cost of $1,134,176. Construction costs for improvements at Velva were $357,306. Engineering and design, supervision and administration, and value engineering at the Velva Unit cost $103,023, $72,307 and $13,069, respectively. Condition at end of fiscal year: Preconstruction planning for the Lake Darling unit and construction on the Velva unit are in progress. 20. LAKE TRAVERSE AND BOIS DE SIOUX RIVER, SD AND MN Location. Works covered by this project lie along Lake Traverse and Bois de Sioux River between upper end of Lake Traverse at Browns Valley, MN, and the mouth of Bois de Sioux River at Breckenridge, MN. Lake drains through river to Red River of the North, and the two waters form a portion of boundary between State of Minnesota and States of North and South Dakota. (For general location, see Geological Survey map of Minnesota.) Existing project. See page 1289 of Annual Report for 1962. Existing project was authorized by Flood Control Act of June 22, 1936. Local cooperation. None required. Operations and results during fiscal year. Maintenance: Project and related facilities were operated and maintained, and inspections and evaluations performed at a cost of $187,906. Condition at end of fiscal year: Existing project was completed in June 1948, except for minor recreational facilities. Fee title to 1,144.13 acres and easements on 6,172.25 acres of land have been acquired. White Rock Dam and Reservation control structures are in operation, and structures and appurtenances are in good condition. Remedial work for repair of apron at White Rock Dam was completed in November 1968. Roadways across structure are open to public travel. 21. MANKATO AND NORTH MANKATO, MN Location. Along Minnesota River between miles 103.5 and 109.5 near Mankato, North Mankato, and Le Hillier, in south-central Minnesota. (For general location see Geological Survey map of Minnesota.) Existing project. As modified as a result of severe 1965 flood, provides for protection of communities of Mankato, North Mankato, and Le Hillier by means of 27-9 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 leveeland floodwalls with pumping plants and interior drainage facilities. See page 1090 of Annual Report for 1967 for further details. Additional channel improvement, levees, pumping, and interior drainage features have been included in the Mankato unit of the project for protection from the high flows of Indian Creek. Expansion of Indian Creek improvements were made during detailed studies as a result of updated hydrologic data. Highway bridge relocations made necessary by the project have been authorized at Federal expense. Estimated Federal cost (1985) for new work is $94,400,000. Project was authorized by 1958 Flood Control Act (H. Doc. 437, 84th Cong., 2d sess., contains latest published map.) Project was modified by 1965 Flood Control Act, and by the Water Resources Development Acts of 1974 and 1976. Local cooperation. Fully complied with for work under contract. See Annual Report for 1973 for requirements. Resolutions agreeing to provide formal assurances of local cooperation, when requested, were passed by the city council of North Mankato, Mankato, and South Bend Township (Le Hillier), respectively, on November 12, 1968. Operations and results during fiscal year. New Work: Construction of the T.H. 60/Main Street bridge relocation continued and Stage 3C-1 construction was essentially completed. Preparation of plans and specifications for the C&NW railroad bridge relocation was completed. Construction costs for improvements at Mankato were $2,432,778, at North Mankato were $4,951,772 and at Le Hillier were $20,108. Engineering and design by contract cost $365,060 and by hired labor cost $410,581, North Central Division Real Estate cost $288,246. Supervision and administration cost $243,055 by hired labor, $191,324 by contract, and $8,811 by other Corps. Other miscellaneous costs were $16,358. Condition at end of fiscal year: Construction of the pumping stations, interior drainage facilities and the diversion channel are complete. The flood barriers are essentially complete except for construction of a short segment of floodwall at the Main Street bridge. Construction for relocation of the Main Street bridge continued. Remaining work consists of relocating the T.H. 169 bridge, raising two reaches of levee in Le Hillier 5 feet, concurrently with relocations of the C & NW railroad bridge over the Blue Earth River. 22. MIDDLE RIVER AT ARGYLE, MN Location. In Marshall County in northwestern Minnesota on the Middle River within the city limits of Argyle, Minnesota. Existing project. The plan of protection includes a system of levees, roadraises along with interior drainage facilities to provide main developed parts of the City of Argyle with one percent chance flood protection. Also included is the evaluation of 12 residences which are located outside of the line of flood barrier protection. Total Federal cost of the project is estimated at $1,013,000 (March 1985 Detailed Project Report). The project was approved for construction on August 1, 1985, by the Chief of Engineers. The project is being constructed under the authority of Section 205 of the 1948 Flood Control Act, as amended. Local cooperation. Local interests are required to hold and save from damages caused by the construction and subsequent maintenance of the Project, except damages due to the fault or negligence of the United States or its contractors; provide without cost to the United States all real estate interests, including suitable borrow, ponding, and disposal areas as determined by the Chief of Engineers to be necessary for the construction and subsequent maintenance of the Project; provide all real estate interests necessary for the non-structural measures of the project, with the only cost to the United States being reimbursement to the City of 80 percent of the payment for such real estate interests and relocation assistance costs approved by the Contracting Officer, subject to the availability of Federal funds for such reimbursement. The Government shall receive credit for 80 percent of the proceeds received by the City for salvage, sale or use of the structures acquired with 80 percent Government reimbursement; accomplish without cost to the United States all relocations of buildings, utilities, highways, and highway bridges necessary for the construction and maintenance of the project except relocation of utility lines passing through or under the line of protection and considered to be integral parts of the improvement within the right-of-way of the project; and further excepting the proposed road relocations and ramping raises of County Highway 108, Cemetery Road and U.S. Highway 75, in the event that legislation passed by the Congress and approved by the Administration subsequent to the execution of this agreement directs that the cost of construction of said road relocation and ramping raises be borne by the Federal Government; provide all costs in excess of the $4 million Federal cost limitation; maintain and operate the project after completion without cost to the United States in accordance with regulations prescribed by the Secretary of the Army; prevent encroachment of any of the flood protection structures, including ponding areas, and if ponding areas are impaired, provide substitute storage capacity of equivilent pumping capacity promptly without cost to the United States; comply with the provisions of the "Uniform Relocation Assistance and Real Property Acquisition Policies Act of 1970," Public Law 91-646, approved January 2, 1971, in the acquisition of lands, easements, and rights-of-way for the project and advise affected persons of pertinent procedures, policies, and benefits in connection with said Act; comply with section 601 of Title VI of the Civil Rights Act of 1964 (Public Law 88-352) and Department of Defense Directive 5500.11 issued pursuant thereto and published in part 300 of Title 32, Code of Federal Regulations, in connection. with the construction, operation, and maintenance of 27-10 ST. PAUL MINNESOTA DISTRICT the project; contribute in cash 20 percent of the cost of non-structural measures except the cost of the real estate interests and relocation assistance provided by the City. A local assurance agreement required by Public Law 91-611 was adopted by the City of Argyle in August 1985. Operations and results during fiscal year. New Work: Completion of the Detailed Project Report and work on plans and specifications was accomplished at total cost for the year of $41,884 by contract and $46,841 by hired labor. North Central Division real estate and Fish and Wildlife Service cost $3,992 and $377 respectively. Supervision and administration cost $5,891. Condition at end of fiscal year: Construction contract for Stage I was awarded. Work on plans and specifications for Stage II was about 70 percent complete. 23. MINNESOTA RIVER AT LE SUEUR, MN Location. In Le Sueur County in north central Minnesota on the Minnesota River about 60 miles southwest of Minneapolis-St. Paul. Existing project. Provides for erosion control along the east bank of the Minnesota River near downtown Le Sueur immediately downstream of the State Highway 93 bridge recently replaced by the Minnesota Department of Transportation. Beginning at the downstream terminals of the zone of protection for the bridge the project provides for the excavation of all unstable channel bank material and the placement of rockfill along an approximate 300 foot reach of eroding bank. Total Federal cost for the project is estimated at $250,000. The City of Le Sueur has contributed $130,000 to the project. The project was approved by the Chief of Engineers for construction in March 1985 under the authority contained in Section 14 of the 1946 Flood Control Act, as amended. Location cooperation. Local cooperation agreements were adopted by Le Sueur County in July 1985. Local interests are required to provide without cost to the United States all lands, easements, and rights-ofway necessary for construction, operation, and maintenance to the project; accomplish without cost to the United States all required alterations and relocations in sewer, water supply, drainage, and other utility facilities; hold and save the United States free from damage due to the construction, operation, and maintenance of the project except where such damages are due to the fault or negligence of the United States or its contractors; maintain the project after completion; assume full responsibility for all project costs in excess of the Federal cost limit of $250,000; provide a cash contribution for project costs in proportion to any special benefits to non-public property; comply with applicable provisions of the Uniform Relocations Assistance and Real Property Acquisition Policies Act of 1970, Public Law 91-646, approved January 2, 1971, in acquiring lands, easements, and rights-ofway for construction and subsequent maintenance of the project and inform affected persons of pertinent benefits, policies and procedures in connection with said Act; comply with the Section 601 of Title VI of the Civil Rights Act of 1964 (Public Law 88-352) and Department of Defense Directive 5500.11 issued pursuant thereto and published in Part 300 of Title 32, Code of Federal Regulations, in connection with the construction and subsequent maintenance and operation of the project. Operations and results during fiscal year. New Work: A construction contract cost $30,184. Engineering and design, and supervision and adminstration cost $32,293. Condition at end of fiscal year. A construction contract for the recommended work was awarded in August 1985. Construction has been delayed due to existing high water. 24. PRAIRIE DU CHIEN, WI Location. In Crawford County in southwestern Wisconsin on the left bank of the Mississippi River. (For general location, see Geological Survey map of Wisconsin.) Existing project. Combines total evacuation with flood proofing and land use control measures to provide the desired reduction of potential flood damages within design limits. Evacuation was accomplished by purchase and relocation of structures in lowest portions of the floodplain. Estimated cost to the United States for new work is $3,700,000. Project was authorized by Water Resources Development Act of 1974. Local cooperation. See Annual Report for 1974 for requirements. A local assurance agreement in accordance with Section 221 of the Flood Control Act of 1970 was entered into with the City of Prairie du Chien on May 2, 1978, and signed by the Chief of Engineers on September 11, 1978. Operations and results during fiscal year. New Work: Costs for property acquisition and relocation activities were $177,579. A contract for site restoration cost $7,915. Engineering and design cost $7,391 by hired labor and supervision and administration cost $917. Contributions in lieu of cash were $-89,926. Condition at end of fiscal year: Project is essentially complete: One residence remains to be acquired. 25. RED LAKE RIVER, MN, INCLUDING CLEARWATER RIVER, MN Location. Works covered by this project lie along upper reach of Red Lake River and also along Clearwater River, a tributary of Red Lake River, between a point near Plummer, MN, and a point just above the mouth of Ruffy Brook. Red Lake River, principal tributary of Red River of the North, has its source at the outlet of Lower Red Lake in northwestern portion of 27-11 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Minnesota and flows westerly about 196 miles to its junction with Red River of the North at East Grand Forks, MN. Clearwater River has a general westerly course from its source near Ebro, MN, about 205 miles to its junction with Red Lake River at Red Lake Falls, MN. (For general location, see Geological Survey map of Minnesota.) Existing project. See page 1281 of Annual Report for 1962. Project was authorized by 1944 Flood Control Act (H. Doc. 345, 78th Cong., 1st sess., contains latest published map.) Local cooperation. Fully complied with. Operations and results during fiscal year. Maintenance: Structures were operated and maintained and inspections and evaluations performed at a cost of $72,031. Condition at end of fiscal year: Construction of major improvements on Red Lake River initiated in February and the Clearwater River initiated in Oc.- tober 1948 were completed in June 1956. Replacement of rock and brush dam on Red Lake River at Indian boundary with a concrete structure and appurtenant work was completed in June 1959 to restore marshes in the area to better wildlife conditions. Construction of a bridge on Clearwater Road was completed by the Indian Service in July 1965. A contract for improvements on Red Lake River was completed in November 1966, and a contract for restoration of water levels in Red Lake River marshes was completed in November 1968. Operation of Red Lake Dam was assumed by the Corps on April 1, 1951. Channels are in good condition and indicate effectiveness of project as a flood control measure. 26. RED RIVER OF THE NORTH AT ARGUSVILLE, ND Location. In Cass County in eastern North Dakota near the confluence of the Red River of the North and the Sheyenne River about 15 miles northwest of Fargo, North Dakota. (For general location, see Geological Survey map of Minnesota.) Existing project. The project involves a levee encircling the City of Argusville with associated interior flood control facilities. The total levee system would be about 1.9 miles long and would have an average height of about 8 feet. Interior flood control facilities consist of interceptor ditches and pipes, two temporary ponding areas and a pumping station to periodically discharge impounded water. Total Federal cost (1984) for the proposed project is estimated at $957,000. The project was approved by the Chief of Engineers for construction July 5, 1985, under the authority contained in Section 205 of the 1948 Flood Control Act, as amended. Local cooperation. A local assurance agreement was adopted by the City of Agusville, the local sponsor, in July 1985. Local interests are required to provide without cost to the United States all lands, easements, and rights-of-way, including ponding and borrow areas, necessary for the construction, operation and maintenance of the project; accomplish all alterations and relocations of buildings streets, and utilities, except for those utilities which are an integral part of project structures; hold and save the United States free from damages caused by the construction and subsequent operation and maintenance of the project, except damages due to the fault or negligence of the United States or its contractors; provide all costs in excess of the $4,000,000 Federal cost limitation; maintain and operate the project after completion without cost to the United States in accordance with regulations prescribed by the Secretary of the Army; prevent any encroachment on constructed works and ponding areas that would interfere with the proper functioning of the project; and, if ponding is impaired, provide promptly and without cost to the United States, substitute storage or equivalent pumping capacity; comply with the applicable provisions of the "Uniform Relocations Assistance and Real Property Acquisition Policies Act of 1970", Public Law 91-646, approved January 2, 1971; comply with Section 601 of Title VI of the Civil Rights Act of 1964 (Public Law 88-352) and Department of Defense Directive 5500.11. Operations at end of fiscal year. New Work: Construction contracts cost $69,754. North Central Division real estate cost $2,183. Engineering and design cost $32,533 and supervision and administration costs were $4,288. Condition at end of fiscal year: A Construction contract for Stage 1 involving the west levee was awarded in September 1985. Plans and specifications for State 2 involving the remainder of the project are 90 percent complete. 27. RED RIVER OF THE NORTH DRAINAGE BASIN, MN, SD & ND Location. Red River of the North Basin, within the United States, includes northeastern corner of South Dakota and much of eastern North Dakota and northwestern Minnesota. Red River of the North, formed by confluence of Otter Tail and Bois de Sioux Rivers, flows northward through this region, forming boundary between North Dakota and Minnesota. (For general location of basin, see Geological Survey maps of Minnesota and South Dakota.) Previous project. See page 1?78 of Annual Report for 1962 for navigation and flood control projects in the basin, not part of this project. Existing project. Project includes improvements for local protection in interests of flood control and major drainage accomplished by channel improvement, levees, etc., in addition to construction of a multiple purpose reservoir on Otter Tail River to control floods and, in conjunction with previously authorized Federal reservoir project at Baldhill site of Sheyenne River and at Red Lake, to increase low flows for water supply and pollution abatement. (See 27-12 ST. PAUL MINNESOTA DISTRICT table 27-J for active units in comprehensive basin plan.) Project was authorized by Flood Control Acts of 1948 and 1950. Public Works Authorization Act, 1957, authorized Chief of Engineers to acquire such lands as were beyond legal authority of the City of Grand Forks to acquire. Section 205 of the Flood Control Act of 1970 provided for extension of the expiration date for the East Grand Forks project. Authorization of the Sheyenne River (Kindred Lake) project by the 1970 Flood Control Act provided for the deletion of channel improvement on the lower 48.8 miles of the Sheyenne River authorized under the Flood Control Acts of 1948 and 1950. Latest published map is in House Document 185, 81st Congress, 1st session. Local cooperation. See page 1039 of Annual Report for 1965. Following the flood of 1965, the City of East Grand Forks requested reactivation of the project and furnished a resolution adopted May 11, 1965, indicating its willingness to meet the requirements of local cooperation. Expiration date for the East Grand Forks project was extended to April 17, 1975, permitting local interests additional time to furnish assurances of local cooperation. A local assurance agreement was passed by the city on March 27, 1975, and accepted by the acting Director of Real Esate, OCE for the Secretary of the Army on April 9, 1975. Operations and results during fiscal year. New Work: Preconstruction planning was continued for the East Grand Forks project at a cost of $241,385. Maintenance: Orwell Lake and Dam were operated as required and miscellaneous inspections, reports, and repairs were made at a cost of $153,044 by hired labor, and $25,607 by contract. Physical security cost $790 by hired labor and $1,465 by contract. Periodic inspection by other Corps districts cost $894. Real estate management by the North Central Division cost $2,827. Discharge observation and gages, occurrence of reservoir sedimentation and pool regulation cost $62,358. Cooperative stream gaging with the U.S. Geological Survey cost $13,320. Water quality monitoring cost $107,238 by hired labor, $30,896 by U.S. Geological Survey and $971 by contract. Supervision and administration, engineering and design and other miscellaneous costs were $44,074, $3,684 and $-2,111. Condition at end of fiscal year: Major construction for all active units except for East Grand Forks, MN, is complete. Preconstruction planning is underway at East Grand Forks. A total of 1,985 acres of land for Orwell Lake and Dam is owned in fee by the United States. See page 1281 of Annual Report for 1962 for periods of completion at active units of project other than Fargo. Work at Fargo, ND, started in May 1959, was completed in July 1963. (See table 27-J at end of chapter for total costs of new work to date.) Costs to date for operation and maintenance of Orwell Lake and Dam are $2,939,890. Total costs for active portion of project are $10,526,632. In addition, $350,034 was expended from contributed funds for work done for local interests. 28. RED RIVER OF THE NORTH AT HALSTAD, MN Location. In Norman County in western Minnesota on the Red River of the North about 36 miles north of Moorhead, Minnesota. (For general location see Geological Survey Map of Minnesota.) Existing project. Provides for a system of levees and interior flood control facilities along the right bank of the Red River of the North. The total levee system is about 2.4 miles long and varies from 0 to over 20 feet high. Most of the levee is 5 to 12 feet high. The levee rings the city except for about 0.6 mile of high ground. Other features include 4 ponding areas and a system of gatewells, pipes and ditches to provide interior flood control. Total Federal cost (1985) for the project is estimated at $1,989,500. The project was approved by the Chief of Engineers for construction April 5, 1983, under the authority contained in Section 205 of the 1948 Flood Control Act, as amended. Local cooperation. Fully complied with. See Annual Report for 1983 requirements. A local assurance agreement required by Public Law 91-611 was adopted by the city of Halstad in April 1983. Operations and results during fiscal year. New Work: Construction contracts cost $467,548. Engineering and design cost $144,075 by hired labor. NCD real estate management cost $532. Supervision and administration costs were $78,217. Condition at end of fiscal year: Construction of the flood control project at Halstad was substantially completed in May 1985. 29. REDWOOD RIVER AT MARSHALL, MN Location. In Lyon County in southwestern Minnesota along the Redwood River about 68 miles above its confluence with the Minnesota River at the City of Marshall, Minnesota. (For general location see Geological Survey map for Minnesota.) Existing project. See page 1059 of Annual Report for 1964 for completed channel improvement project authorized by 1960 Flood Control Act. Federal costs amounted to $1,802,866. The plan contained in June 1979 feasibility report provides for improvements upstream and downstream of the existing channel project at Marshall which is affected by limited channel capacity in both reaches. The upstream measures would include 1.9 miles of levee, 0.7 mile of channel improvement, an overflow structure, and 71 acres of floodway acquisition. The downstream improvements would consist of 1.5 miles of levee, 0.3 mile of channel improvement, and interior drainage facilities. Recreation facilities would include multi-use trails and limited picnic facilities. The pro- 27-13 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 ject would provide protection against a flood having an occurrence interval of about once in 133 years. Estimated Federal cost (1985) for new work is $3,550,000 and $360,000 is to be contributed by local interests. Local cooperation. Fully complied .with for completed work. See page 1150 of Annual Report for 1963 for requirements. Project was transferred to local interests on December 23, 1963. For new work, local interests are required to provide lands, easements, and rights-of-way, including relocations, and to operate and maintain the project. In addition, local interests are to provide the necessary lands for recreation development, subject to the condition that, where the appraised value of those lands is less than 50 percent of the total first cost of recreation development, a cash contribution will be made to bring the non-Federal share to at least 50 percent of the total first cost of recreation development. By resolution approved April 2, 1979, the City of Marshall agreed to assume non-Federal responsibilities for the proposed project. By letter dated July 8, 1982, the City of Marshall indicated its willingness to financially participate in construction of a project consistent with the current administration's proposed upfront financial and cost sharing policies. Operations and results during fiscal year. New Work: Preconstruction planning was continued at a cost of $118,804 Condition at end of fiscal year: Construction of completed work was initiated August 1962 and completed December 1963. Preconstruction planning for the new work is in progress. The project is not yet authorized for construction. 30. ROCHESTER, MN Location. In Olmstead County in southeastern Minnesota on the South Fork of the Zumbro River. (For general location, see Geological Survey map of Minnesota.) Existing project. Provides for stream channel modifications and levees functioning in combination with a system of seven headwaters reservoirs. Principal features, in addition to the reservoirs, include 0.5 mile of grass-sloped channels, 6.1 miles of riprapped or gabion-lined channels, 0.9 mile of architecturally- treated concrete channels, 0.5 mile of dredged channel, six drop structures, 2.4 miles of levee, and hiking and biking trails. Estimated cost (1985) to the United States for new work is $52,400,000. Project was authorized by the Water Resources Development Act of 1974 (H. Doc. 156, 93rd Cong., 1st sess., contains latest published map.) Local cooperation. See Annual Report for 1974 for requirements. By resolution approved on September 29, 1981, the City of Rochester, the local sponsor, indicated a willingness and intention to meet the requirements of local cooperation for flood control and recreation. Formal assurances will be requested prior to initiation of construction. Operations and results during fiscal year. New Work: Preconstruction planning was continued at a cost of $402,047. Condition at end of fiscal year: Phase I design memorandum stage of preconstrtction planning was completed and forwarded to Congress on April 27, 1979, which was the basis for authority to proceed with the Phase II design memorandum stage of advance engineering and design. Phase II studied the plans and specifications for the first stage of project construction (Stage lA) have been completed. 31. ROSEAU RIVER, MN Location. In Roseau County and northeastern Kittson County, in northwestern Minnesota, and in south-central Manitoba, Canada. (For general location of the works in the United States see Geological Survey map of Minnesota.) Existing project. Provides for improvement of Roseau River for flood control consisting of 44.4 miles of channel improvement, two sections of earth levees with lengths of 1.9 and 5.9 miles, respectively, 76 side ditch inlet transitions; remedial works along 16.6 miles of channel in Canada or an acceptable alternative therefor; one new bridge; and alteration of the existing dam in Roseau Village. Remedial works will be constructed in Canada at the expense of the United States. Estimated cost (1985) to the United States for new work is $29,700,000 including $6,624,00 for cost or work in Canada to be accomplished with United States funds. Project was authorized by Flood Control Act of 1965 (H. Doc. 282, 89th Cong., 1st sess., contains latest published map.) Local cooperation. See Annual Report for 1968 for requirements. Local interests have formed a Roseau River Watershed District to provide local cooperation requirements and acquire rights-of-way. Operations and results during fiscal year. New Work: Planning activities were continued relative to coordination of the project plan with Canadian interests. Engineering and design and supervision and administration cost, $19,271. Condition at end of fiscal year: Planning is in progress and coordination with Canadian interests is underway. The general design memorandum was submitted in October 1971 and approved in March 1972. Design memorandum supplements which contain dimensions of environmental features added to the project were submitted in October 1975 and June 1980 and approved in November 1975 and July 1980, respectively. An EIS supplement was filed with the EPA in October 1981. 32. SHEPARD ROAD, MISSISSIPPI RIVER, ST. PAUL, MN Location. In Ramsey County along the Mississippi River in downtown St. Paul, Minnesota. 27-14 ST. PAUL MINNESOTA DISTRICT Existing project. The project to protect the streambank from erosion which threatens Shepard Road is authorized under Section 14 of the 1946 Flood Control Act, as amended. A reconnaissance report dated March 1983 recommended breaking existing grouted slope protection, placing approximately 6,700 cubic yards of rock-fill and modifying existing storm sewer outfalls along the left bank of the Mississippi River from Wabasha Street to 300 feet above Robert Street, a distance of about 900 linear feet. The project was approved by the Chief of Engineers for construction on June 6, 1983. The project was modified during the summer of 1984 to include 300 additional feet of bank protection upstream from Wabasha Street. Total Federal cost for the project was $250,000 which is the maximum permissible under Section 14. The City of St. Paul contributed $62,600 to the project. Local cooperation. Fully complied with. See Annual Report for 1983 for requirements. A local cooperation agreement required by Public Law 91-611 was adopted by the City of St. Paul in July 1983. The project was officially transferred to the City of St. Paul for operation and maintenance by letter dated January 22, 1985. Operations and results during fiscal year. New Work: Construction of bank protection by contract cost $46,658. Supervision and administration cost $37. The project, as modified, was completed and transferred to the City of St. Paul for operation and maintenance. 33. SHEYENNE RIVER FLOOD CONTROL, ND (Formerly Kindred Lake) Location. The Sheyenne River Basin is included in 16 counties in the southeastern portion of North Dakota and drains an area of 7,140 square miles into the Red River of the North near Fargo, North Dakota. The principal area of flood damages in the basin is located at the lower end within Cass County and the City of West Fargo. The authorized Kindred Lake project is in Richland County, ND, on the Sheyenne River, about 70 miles above its mouth and 5 miles above Kindred, ND. (For general location, see Geological Survey map of North Dakota.) Existing project. The authorized project provides for a multiple-purpose impoundment for flood control, water quality control, recreation, and fish and wildlife purposes to control the runoff from 3,014 square miles. The improvements would be coupled with a revised operating plan for the existing Baldhill Dam and with appropriate flood plain management measures at communities along the river. See Annual Report for 1973 for details. Project was authorized by 1970 Flood Control Act (H. Doc. 330, 91st Cong., 2d sess., contains latest published map.) Due to local concerns, a changed set of planning criteria, and potential changed conditions, a complete reformulation and reevaluation of alternatives was undertaken during preconstruction planning. The reevaluation studies showed that another alternative plan is more favorable than the authorized project. The General Reevaluation Report, completed in 1982, recommends implementation of a plan other than the authorized plan. The plan recommended in the General Reevaluation Report includes levees and diversions at West Fargo/Riverside, a flood diversion channel from Horace to West Fargo, and a five foot raise of the flood control pool at Baldhill Dam. Other actions are also identified that could be taken by non-Federal interests to enhance the degree of flood damage reduction provided by the overall plan. This new plan represents a significant change from the authorized project and recommends deauthorization of the Kindred Lake project and reauthorization of the new plan. The estimated Federal cost (1985) of the plan, based on traditional cost-sharing requirements is $26,600,000. Local cooperation. See Annual Report for 1971 for requirements of the project as authorized. On July 7, 1982, and May 20, 1983, the North Dakota State Water Commission furnished a letter of support for the recommended plan for flood control in the lower Sheyenne River Basin and also expressed its willingness to act as a non-Federal sponsor. On August 2, 1982, and July 30, 1982, respectively, the City of West Fargo and the Southeast Cass Water Resource District furnished letters of support and indicated their willingness to cooperate with the North Dakota State Water Commission. The Southeast Cass Water Resource District reiterated its support of the project by letter dated March 30, 1984. Formal assurances of local cooperation will be requested after completion of the General Design Memorandum. Operations and results during fiscal year. New Work: Preconstruction planning was continued at a cost of $245,105. Condition at end of fiscal year: Preconstruction planning is in progress. 34. STATE ROAD AND EBNER COULEES, WI Location. In La Crosse County in west-central Wisconsin, on the south side of the City of La Crosse. (For general location, see Geological Survey map of Wisconsin.) Existing project. The plan of improvement for local protection (flood control) consists of channel deepening and enlarging downstream from Hagen Bridge to the mouth of Pammel Creek and includes 10,200 feet of concrete-lined rectangular channel, a drop chute inlet structure, a side channel inlet structure, a stilling basin, a terminus structure, and three new street bridges. The upper 4,000 feet of rectangular channel is designed for supercritical flow and the remaining 6,200 feet of channel is designed for subcritical flow. Wh en completed, the project will provide Standard Proje~t Flood (SPF) protection. The city replaced a fourth bridge in 1980 that was previously included in the authorized plan. The city also 27-15 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 replaced a railroad bridge in 1985 that was also included in the authorized plan. Estimated cost (1985) to the United States for new work, exclusive of the Ebner Coulee portion of the project which was deleted due to lack of economic feasibility, is $30,300,000. Project was authorized by 1968 Flood Control Act (H. Doc. 360, 90th Cong., 2d sess., contains published map.) Local cooperation. See page 826 of Annual Report for 1969. The local sponsor withdrew support for the project in 1976 citing increased non-Federal costs and lack of agreement on local cost sharing between three local units of government located within the project area. The project was reclassified as inactive on April 7, 1977, but was reactivated on November 8, 1978, after the La Crosse County Board of Supervisors, the La Crosse City Council, and the Town of Shelby passed separate resolutions on September 17, 1978, July 13, 1978, and July 10, 1978, respectively, which requested continuance of the project. All three groups reaffirmed their support by letter in July 1981. On October 4, 1982, the City of La Crosse furnished a letter in further support for the project and acknowledged that it would serve as the local sponsor. The City sent a letter of intent again on December 13, 1984, and furnished letter of assurance September 17, 1985. Operations and results during fiscal year. New Work: Preconstruction planning was continued at a cost of $323,466. Condition at end of fiscal year: Preconstruction planning is completed. Plans and specifications for the first stage of construction are complete. Ebner Coulee has been recommended for reclassification to "inactive" due to lack of economic feasibility. 35. TWIN VALLEY LAKE, WILD RICE RIVER, MN Location. In Norman County in west-central Minnesota, northeast of the City of Moorhead, on the Wild Rice River about 2 miles east of Twin Valley, MN. The Wild Rice River is a tributary of the Red River of the North. (For general location, see Geological Survey map of Minnesota.) Existing project. The project authorization provides for reservoir development on the Wild Rice River near Twin Valley, Minnesota, for flood damage reduction, recreation, and fish and wildlife enhancement. The principal features include an 84 foot high, 7,700 foot long, earthen dam, a gated concrete spillway with concrete chute and stilling basin, a 10 foot diameter gated circular conduit for low flow outlet works, and recreation development on the created 540-acre reservoir. Storage capacity would provide 7,500 acre-feet for recreation and sedimentation and 44,700 acre-feet for flood control. The proposed works include development of three recreation areas along the margin of the lake for public use. The Federal Government would acquire about 3,500 acres of land necessary for carrying out the purposes of the project. Approximately 2,200 additional acres will be acquired to offset fish and wildlife habitat losses associated with project construction. Estimated Federal cost (1985) for new work is $30,100,000. Project was authorized by 1970 Flood Control Act (H. Doc. 366, 90th Congress, 2d sess., contains latest published map.) Local cooperation. See Annual Report for 1971 for requirements. Local interests have not been requested to furnish assurances. The Norman County Board of Commissioners, by resolutions dated November 7, 1974, September 19, 1978, and August 26, 1981, has declared its intention to provide local cooperation for recreation and fish and wildlife enhancement. By letters dated August 17, 1982, and August 31, 1984, the Wild Rice Watershed Board expressed their support and intent to provide local cooperation requirements and participate in innovative financing for flood control. The Norman County Board of Commissioners has also indicated the capability to provide assurances of local cooperation relating to flood control improvments. Operations and results during fiscal year. New Work: Preconstruction planning was continued at a cost of $45,983. Condition at end of fiscal year: Preconstruction planning is in progress. Project requires further authorization for mitigation lands. 36. VETERAN'S MEMORIAL LEVEE, MISSISSIPPI RIVER, HASTINGS, MN Location. In Dakota County on the Mississippi River approximately 20 miles southeast of St. Paul, Minnesota. Existing project. In the early 1980's, a section of bank along the Mississippi River between Highway 61 and Milwaukee Railroad bridges in Hastings was threatened by erosion. Located within this reach is a park (Veteran's Memorial Levee) which is historically significant because of the role the area played during the riverboat era. Part of the park is occupied by a road which is an alternate route for emergency vehicles. In order to provide protection to this area, an erosion control project consisting of the placement of a 15-inch thick layer of riprap over 9 inches of bedding was constructed. The project was approved by the Chief of Engineers for construction June 29, 1983, under the authority contained in Section 14 of the 1946 Flood Control Act, as amended and completed in July 1984. Total Federal cost for the proposed project was $182,000. Local cooperation. Fully complied with. See Annual Report for 1983 for requirements. A local assurance agreement required by Public Law 91-611 was adopted by the City of Hastings in August 1983. 27-16 ST. PAUL MINNESOTA DISTRICT Operations and results during fiscal year. New Work: Engineering and design and supervison and administration costs were $7,253. Condition at end of fiscal year: The operation and maintenance manual for the project was completed in October 1984. The project was transferred to the city of Hastings, the local sponsor, during the same month. 37. WILD RICE RIVER, MAHNOMEN COUNTY, MN Location. In Mahnomen County, in west central Minnesota on the Wild Rice River about 1.4 miles southwest of the City of Mahnomen. Existing project. The project to protect the streambank from erosion which threatens County-State Aid Highway (CSAH) #5 is authorized under Section 14 of the 1946 Flood Control Act as amended. The initial appraisal report, dated September 1984, recommended protection with 320 cubic yards of gravel bedding and 660 cubic yards of riprap along about 450 feet of eroding riverbank. The project was approved for construction by the Office Chief of Engineers on June 18, 1985. Total Federal cost of the the project is estimated at $58,500. Local cooperation. A local cooperation agreement required by Public Law 91-611 was adopted by the County of Mahnomen, Minnesota, in August 1985. Local interests are required to provide without cost to the United States all lands, easements, and rights-ofway necessary for construction, operation, and maintenance to the project; accomplish without cost to the United States all required alterations and relocations in sewer, water supply, drainage, and other utility facilities; hold and save the United States free from damages due to the construction, operation, and maintenance of the project except where such damages are due to the fault or negligence of the United States or its contractors; maintain the project after completion; assume full responsibility for all project costs in excess of the Federal cost limit of $250,000; provide a cash contribution for project costs in proportion to any special benefits to non-public property; comply with applicable provisions of the Uniform Relocations Assistance and Real Property Acquisition Policies Act of 1970, Public Law 91-646, approved January 2, 1971, in acquiring lands, easements, and rights-ofway for construction and subsequent maintenance of the project and inform affected persons of pertinent benefits, policies and procedures in connection with said Act; comply with the Section 601 of Title VI of the Civil Rights Act of 1964 (Public Law 88-352) and Department of Defense Directive 5500.11 issued pursuant thereto and published in Part 300 of Title 32, Code of Federal Regulations, in connection with the construction and subsequent maintenance and operation of the project. Operations and results during fiscal year. New Work: A construction contract cost $30,000. North Central Division real estate cost $500. Engineering and design and other study costs were $12,719. Condition at end of fiscal year: A contract for slope protection was awarded in August 1985. Project was 85 percent complete at the end of the fiscal year. 38. WILD RICE RIVER-SOUTH BRANCH AND FELTON DITCH, MN Location. In Clay and Norman Counties in westcentral Minnesota northeast of the City of Moorhead, MN. The South Branch of the Wild Rice River and Felton Ditch drain areas of 253 and 122 square miles and enter the Wild Rice River at points 29.5 and 20.5 miles, respectively, above its confluence with the Red River of the North. (For general locations, see Geological Survey map of Minnesota.) Existing project. Provides for increasing the capacities of the South Branch and Felton Ditch channels by widening the existing channels through the floodplain. Debris removal would be accomplished in the lower reaches of both streams. In addition, short reaches of low dikes would be constructed on both banks of Felton Ditch near the upper limit of improvement. The plan also includes bridge and culvert structure alterations, new bridges, multiplate pipe arches, side ditch inlet and lateral ditch entry modifications, and a drop inlet structure. The project would provide flood protection in both watersheds for a 6-percent chance flood and outlets necessary for removal of crop-damaging surface waters from lateral and on-farm drainage systems. Project was authorized by 1968 Flood Control Act (H. Doc. 98, 90th Cong., 1st sess., contains latest published map.) Local cooperation. See page 826 of Annual Report for 1969 for requirements. A local assurance agreement in accordance with Section 221 of the Flood Control Act of 1970 was executed by the Wild Rice Watershed District on October 18, 1978. Operations and results during fiscal year. New Work: Engineering and design cost $5,465 and supervision and administration cost $2,351. Condition at end of fiscal year: Construction of the project is complete, and the project has been transferred to the Watershed District for operation and maintenance. 39. WINONA, MN Location. At Winona County in southeastern Minnesota on the right bank of the Mississippi River about 725 miles above mouth of the Ohio River. (For general location see Geological Survey map of Minnesota.) Existing project. See page 833 of Annual Report for 1968 for completed upstream improvements authorized by the Flood Control Act of 1958 providing for a continuous flood barrier about 6.1 miles long with related pumping and interior drainage facilities. Federal costs amounted to $2,147,131 of which $111,500 was expended for the portion then deferred 27-17 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 for restudy and $17, 316 was contributed by local interests. Improvement authorized in 1971 under Section 201 of the Flood Control Act of 1965 (H. Doc. 152, 92d Cong., 1st sess., contains latest published map) provides for levee and floodwall protection with necessary interior drainage works for the riverfront and the Lake Winona closure reaches, as well as a sound floodplain management program to prevent unwise development of the area bordered by U.S. Highway 61 and Burns Valley and Pleasant Valley Creeks. The plan would also provide the downstream flood barrier needed to prevent Mississippi River backup flows from entering Lake Winona and inundating the area now only partially protected by the completed segment of the project authorized by the 1958 Flood Control Act. The selected plan would also provide control of Burns Valley Creek by means of channel improvement, raising and extending the existing levee system, a drop structure, an erosion control structure, alteration of two highway bridges, and a sewer line modification. Earth levees averaging 10 feet in height total approximately 3.1 miles in length. Concrete floodwalls, also averaging about 10 feet in height, total about 2,025 feet in length. Estimated Federal cost (1985) for new work is $30,429,000 and $572,000 was contributed by local interests. Resolutions authorizing the project were adopted by the Public Works Committees of the House on July 29, 1971, and the Senate on November 18, 1971. Local cooperation. Fully complied with for completed work. See page 833 of Annual Report for 1968 for requirements. For improvements authorized in 1971 see Annual Report of 1972 for requirements. A local cooperation agreement required under Section 221 of the 1970 Flood Control Act was executed by the City of Winona on October 6, 1978. Operations and results during fiscal year. New Work: Construction contracts for Reaches B, C, and E cost $121,640, $5,208 and $2,335,298, respectively. A dredge fill contract cost $42,313. Engineering and design cost $9,115 by contract and $120,856 by hired labor. Real estate management by NCD cost $291. A switch gear replacement contract cost $31,717. Supervision and administration and other miscellaneous costs were $104,227. Condition at end of fiscal year: The upstream improvement except for a portion of the project raising and extending the existing levee downstream from the Lake Winona outlet was completed in August 1967. All work authorized in 1971 is complete except the final clean up of bridge relocation on Burns Valley Creek. Project was formally dedicated by the city on October 13, 1985. 40. INSPECTION OF COMPLETED FLOOD CONTROL PROJECTS Flood control projects turned over to local interests were inspected to determine that project channels are kept clean and unobstructed, dikes and revetments are in good condition, and structures are in good repair and operable. Deficiencies, if any, were minor unless noted (See table 27-K on inspection of completed flood control projects.) Cost for the period was $51,499. Total cost to September 30, 1985, is $766,010. Miscellaneous 41. OTHER WORK UNDER SPECIAL AUTHORITY In the Aquatic Plant Control program (Section 302, Public Law 298, 89th Congress) a contract for aquatic plant harvesting cost $47,500, coordination with the state of Wisconsin cost $17,387, administrative and other miscellaneous costs were $3,735. General Investigations 42. SURVEYS Flood control studies continued at a cost of $2,189,711. Coordination studies with other agencies and miscellaneous activities cost $213,369. Review for deauthorization, Warroad River at Bulldog Creek and Hudson Harbor cost $2,505 and $10,000 respectively. Total cost of surveys for the period was $2,415,585. 43. COLLECTION AND STUDY OF BASIC DATA Costs during the period were $7,762 for International Water Studies and $186,756 for Flood Plain Management Services. Costs were $50,095 for stream flow data obtained by Corps gaging beyond cooperative stream-gaging program, and for hydraulic laboratory work in measurement and analysis of sediment load in streams. Total cost for collection and study of basic data was $244,613. 44. CONTINUATION OF PLANNING AND ENGINEERING Cost during the period was $118,804 for Redwood River at Marshall, MN. For detail of the individual project see section 29 in text. 45. ADVANCE ENGINEERING AND DESIGN Costs during the period were $1,589,602 for advance engineering and design projects. For details of individual projects see sections 6, 10, 27, 30, 33, 34, and 35 in text. 27-18 ST. PAUL MINNESOTA DISTRICT COST AND FINANCIAL STATEMENT See Section In Text Project Funding 1. Minnesota River, MN New Work: Approp. Cost Maint: Approp. Cost 3. Reservoirs at New Work: Headwaters of Approp. Mississippi River, MN Cost Maint: Approp. Cost Maj. Rehab: Approp. Cost 4. St. Croix River New Work: MN and WI Approp. Cost Maint: Approp. Cost 5. Warroad Harbor New Work: and River, MN Approp. Cost Maint: Approp. Cost 6. Bassett Creek, MN New Work: Approp. Cost 7. Big Stone Lake New Work: and Whetstone River, Approp. MN and SD Cost Maint: Approp. Cost 8. Black Bear and New Work: Miller Lakes, MN Approp. Cost 9. Bonnes Coulee, New Work: Velva, ND Approp. Cost 10. Chaska, MN New Work: Approp. Cost 11. Devils Lake, ND New Work: Approp. Cost 12. Eau Galle River, WI New Work: Approp. Cost Maint: Approp. Cost 13. Enderlin, Maple New Work: River, ND Approp. Cost Total Cost to September 30 FY82 FY83 FY84 FY85 1985 434,000 37,251 4,000 4,218 1,172,600 1,131,104 106,000 9,025 221,020 48,225 425,000 415,765 490,000 365,467 803,000 189,512 200,000 183,115 60,000 54,547 219,000 468,855 160,000 33,900 420,000 419,039 1,600,588 1,544,335 -97,000 -7,956 44,000 199,906 435,000 416,333 575,000 473,040 208,000 800,572 225,000 242,018 275,000 159,656 263,000 261,079 910,000 386,927 44,000 439,098 1,361,800 1,485,496 7,385 17,000 30,503 25,000 41,949 1,450,000 904,550 128,000 147,247 50,000 32,045 18,500 18,122 373,000 364,914 1,767,000 570,621 331,000 285,094 2,600,000 861,589 - $ 2,057,7221 - 2,057,7221 59,000 2,326,186 6,605 2,270,301 - 4,398,6282 - 4,398,6282 1,785,000 21,558,646- 1,673,967 21,398,687 3 - 425,000 - 425,000 - 150,410 - 150,410 161,000 1,108,255 161,546 1,108,255 - 86,105 - 86,105 24,0004 1,086,400 22,7204 1,080,828 15,000 1,715,000 14,668 1,697,583 205,000 12,045,000 800,088 11,848,5095 302,000 2,004,200 227,418 1,924,243 147,000 197,000 59,680 91,725 40,000 58,500 40,378 58,500 346,000 1,828,000 316,949 1,789,083 213,000 2,470,000 1,413,067 2,334,023 - 9,039,250 - 9,039,250 575,000 4,355,105 502,985 4,210,790 -72,000 4,000,000 1,898,355 3,580,555 27-19 TABLE 27-A REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 27-A (Continued) COST AND FINANCIAL STATEMENT See Total Cost to Section September 30 In Text Project Funding FY82 FY83 FY84 FY85 1985 14. Homme Lake and Dam, ND 15. Irving Township at Nicols Road, Jackson County, WI 16. Lac qui Parle Lake, MN 17. La Farge Lake and Channel Imp., WI 18. Lake Ashtabula and Baldhill Dam Sheyenne River, ND 19. Lake Darling, Souris River, ND 20. Lake Traverse and Bois de Sioux River, SD and MN 21. Mankato and North Mankato, MN 22. Middle River at Argyle, MN 23. Minnesota River at Le Sueur, MN 24. Prairie du Chien, WI 25. Red Lake River, MN, including Clearwater River, MN 26. Red River of the North at Argusville, ND New Work: Approp. Cost Maint: Approp. Cost New Work: Approp. Cost New Work: Approp. Cost Maint: Approp. Cost New Work: Approp. Cost Maint: Approp. Cost New Work: Approp. Cost Maint: Approp. Cost New Work: Approp. Cost New Work: Approp. Cost Maint: Approp. Cost New Work: Approp. Cost New Work: Approp. Cost New Work: Approp. Cost New Work: Approp. Cost New Work: Approp. Cost Maint: Approp. Cost New Work: Approp. Cost -_. .- - 113,000 97,000 102,000 133,026 57,991 108,738 83,000 99,956 1,396,0976 1,396,0976 2,135,421 2,118,192 158,500 158,500 14,290 14,290 203,000 184,000 176,117 168,297 - 550,000 12,810 336,849 18,000 22,000 15,864 17,656 18,000 1,551 514,840 933,197 800,000 660,376 16,268 845,000 788,978 1,150,000 1,176,694 180,000 190,000 143,241 186,053 6,016,000 5,950,000 6,316,353 5,169,491 - 60,000 22,149 46,394 - - 964,873 - - 964,873 263,000 1,139,000 4,610,163 312,230 517,273 3,977,575 175,614 21,000 25,439 180 881,200 898,714 38,372 42,000 27,484 18,642,000 18,642,000 103,000 86,443 - 3,325,6387 - 3,325,6387 1,241,000 11,974,152 955,731 11,571,414 1,100,000 3,000,000 6,050,000 1,113,594 1,679,881 4,630,545 - - 1,339,727 - - 1,339,727 179,000 203,000 2,847,619 210,966 187,906 2,818,671 7,645,000 9,176,000 65,970,500 7,835,568 8,928,093 64,965,832 40,000 215,000 380,000 52,937 98,985 259,996 250,000 62,477 250,000 62,477 1,050,000 161,000 -140,000 -125,000 3,755,000 888,843 29,549 -171,891 103,876 3,631,600 - - - - 3,120,0791 - - - - 3,120,0791 50,000 54,000 26,000 123,000 840,802 41,747 34,383 52,072 72,031 787,944 55,000 60,000 54,880 55,178 45,000 44,994 259,000 108,758 479,000 323,388 27-20 ST. PAUL MINNESOTA DISTRICT TABLE 27-A -Continued) COST AND FINANCIAL STATEMENT See Total Cost to Section September 30 In Text Project Funding FY82 FY83 FY84 FY85 1985 27. Red River of the North Drainage Basin, MN, SD and ND 28. Red River of the North at Halstad, MN 29. Redwood River at Marshall, MN 30. Rochester, MN 31. Roseau River, MN 32. Shepard Road, Mississippi River, St. Paul, MN 33. Sheyenne River, ND (formerly Kindred Lake) 34. State Road & Ebner Coulees, WI 35. Twin Valley Lake, Wild Rice River, MN 36. Veteran's Memorial Levee, Mississippi River, Hastings, MN 37. Wild Rice River, Mahnomen County, MN 38. Wild Rice River, South Branch and Felton Ditch, MN 39. Winona, MN New Work: Approp. Cost Maint: Approp. Cost New Work: Approp. Cost New Work: Approp. Cost New Work: Approp. Cost New Work: Approp. Cost New Work: Approp. Cost New Work: Approp. Cost New Work: Approp. Cost New Work: Approp. Cost New Work: Approp. Cost New Work: Approp. Cost New Work: Approp. Cost New Work: Approp. Cost 124,000 175,000 255,000 275,000 7,628,9849 121,593 174,255 250,178 241,385 7,586,7429 139,000 152,000 200,000 481,000 2,999,534 159,738 152,388 183,822 445,057 2,939,890 75,000 296,000 1,273,000 200,500 1,989,500 67,370 156,373 890,478 690,372 1,948,418 535,000 515,705 500,000 354,867 316,000 259,351 114,116 - 250,000 - 33,132 178,000 142,475 34,565 195,000 202,000 238,956 178,742 887 - - 182,000 - 27,548 ..- -. _ 1,859,000 225,000 1,826,389 706,144 150,000 235,000 2,187,86610 149,998 118,804 2,071,66810 100,000 149,589 250,000 53,911 400,000 2,880,000 402,047 2,852,944 - 2,128,000 19,271 1,900,590 170,173 46,695 250,00011 250,000"1 165,000 265,000 2,705,000 152,862 245,105 2,671,547 350,000 344,756 30,000 1,680 315,000 323,466 20,000 45,983 - - 147,199 7,253 - 58,500 - 43,219 28,506 1,772,000 1,751,913 1,961,700 1,959,363 182,000 182,000 58,500 43,219 - 4,534,700 7,815 4,534,700 7,844,000 6,850,000 2,210,000 2,772,000 32,576,131 7,858,873 6,470,128 2,354,380 2,770,665 32,310,84812 'Includes $117,542 for new work for previous project. Excludes $359,202 contributed funds. 32Includes $681,805 for new work for previous projects. Includes $100,857 for maintenance for previous projects. 4Includes $24,000 appropriated and $19,729 expended in FY 1985 for condition surveys. 5Excludes $152,223 contributed funds. In addition, $408,846 in other contributed funds have been expended for work under Government contract paid for by the Ottertail Power Company. 6Excludes $56,220 contributed funds. 7Excludes $208,000 contributed funds. "Excludes $30,020 contributed funds. 9Includes cost of the Wahpeton-Breckenridge unit, $11,239, which is classed as "inactive" and the units on which authorization has expired: Maple River, $1,241; Moorhead, $27,700; Sheyenne, $37,956. In addition, $203,874 special deposit funds and $146,160 in other contributed funds have been expended for work under Government contract paid for by local interests. 1oIncludes $1,802,866 for new work for previous project. "Excludes $62,620 contributed funds. 12Excludes $497,547 contributed funds. In addition, $615,174 in other contributed funds have been expended for work under Government contract paid for by local interests. 27-21 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 27-B AUTHORIZING LEGISLATION See Sec. Date of in Authorizing Text Act Project and Work Authorized Documents 1. July 13, 1892 July 3, 1958 3. Mar. 3, 1889 Mar. 2, 1907 June 25, 1910 July 27, 1916 June 26, 19342 4. June 18, 1878 June 3, 1896 Jan. 21, 1927 Aug. 30, 1935 May 17, 1950 5. Mar. 3, 1899 June 6, 1900 June 13, 19023 Mar. 3, 1905 June 25, 1910 July 25, 1912 MINNESOTA RIVER, MN Open-channel improvement from mouth to Shakopee to obtain a channel of 4-foot depth to accommodate vessels with 3-foot draft. Dredging to provide channel of 9-foot depth from mouth to mile 14.7 RESERVOIRS AT HEADWATERS OF MISSISSIPPI RIVER, MN Reconstruct 4 of the 5 original dams and surveys to determine extent of lands overflowed by reservoirs. Reconstruct Sandy Lake Dam and construct Gull Lake Reservoir. Construct an equalizing canal between Winnibigoshish and Leech Lake Reservoirs (no work was done and this part of the project abandoned in Act of Mar. 4, 1915.) Abandonment of ditches connecting Long Lake, Round Lake, and Gull Lake. Operation and maintenance provided for with funds from War Department appropriations for rivers and harbors. ST. CROIX RIVER, MN AND WI Dredging, etc., for a 3-foot channel between mouth and Taylors Falls. Harbor and waterfront at Stillwater. A 6-foot channel to Stillwater. The 9-foot channel from mouth to Stillwater. Small-boat harbor at Hudson. WARROAD HARBOR AND RIVER, MN Dredging bar at mouth of Warroad River. Entrance channel 300 feet wide and 7 feet deep. Enlarging turning basin Annual Report 1891. p. 2209 S. Doc. 144. 84th Cong., 2d sess.' H. Doc. 363, 61st Cong., 2d sess. H. Doc. 413, 64th Cong., 1st sess.' H. Ex. Doc. 75, pt. 6, 43rd Cong., 2d Sess;4 Annual Report 1875, p. 372. H. Doc. 378, 69th Cong., 1st sess.4 H. Doc. 184, 72nd Cong., 1st sess.4 H. Doc. 184, 81st Cong., 1st sess.4 Specified in Act. H. Doc. 92, 56th Cong., 2d sess. 5 H. Doc. 703, 61st Cong., 2d sess.5 Deepening to 8 feet. 'Contains latest published map. 2Permanent Appropriations Repeal Act. 3Appropriation. 4See H. Doc. 462, 71st Congress, 2d sess., for latest published map. 5Latest published map is opposite p. 1984 in Annual Report for 1911. 27-22 ST. PAUL MINNESOTA DISTRICT TABLE 27-C OTHER AUTHORIZED NAVIGATION PROJECTS For Last Cost To September 30, 1985 Full Report See Annual Operation And Project Status Report For Construction Maintenance Baudette Harbor, MN Completed 1961 $36,415 $57,768 Black River, WI 1 1950 67,585 - Lake Traverse, MN and SD 34 1921 92 - Mississippi and Leech Rivers, MN Completed3 1929 277,615 40,251 Mississippi River between Brainerd and Grand Rapids, Mn 5 1925 47,794 3,891 Pine Creek, Angle Inlet, MN Completed 1978 38,700 102,196 Red Lake and Red Lake River, MN Completed3 1923 9,070 - Red River of the North, MN and ND 3,6 1921 293,344 76,209 Wisconsin River, WI 2,3 1888 - - Zippel Bay Harbor, WI Inactive5 1928 27,941 11,139 'Existing channel adequate for commerce (see table 27- G for deauthorized portion of project). 2Originally included in project 'Fox and Wisconsin Rivers, WI'. Abandonment of improvement of Wisconsin River by channel contraction works recommended in 1886 and 1887 (H. Doc. 65, 49th Cong., 2d sess.). Expenditures included under 'Fox and Wisconsin Rivers, WI'. No breakdown available. 3No commerce reported. 4Abandonment recommended in 1915 (H. Doc. 439, 64th Cong., 1st sess.) and June 24, 1926 (H. Doc. 467, 69th Cong., 1st sess.). 5Abandonment recommended June 24, 1926 (H. Doc. 467, 69th Cong., 1st sess.). 6Abandonment recommended in 1915 (H. Doc. 1666, 63d Cong., 3d sess.). 27-23 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 27-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS For Last Cost To September 30, 1985 Full Report See Annual Operation And Project Status Report For Construction Maintenance Burlington Dam, Souris River, ND Deferred 1983 $5,568,5001- Dry Run, IA Completed 1966 1,790,7592- Elk River, MN Completed 1970 259,7003 - Grafton, ND Active4 1983 -- Guttenberg, IA Completed 1974 2,361,915 - Irving Township, Jackson County, WI5 Completed 1984 189,600 - LaCrosse, WI Active6 1983 -- Lost River, MN Completed 1967 517,5197 - Lower Branch Rush River, ND8 Completed 1974 1,000,0009 - Minneota, MN8 Completed 1963 161,545 - Minot, ND Completed 1983 21,479,50010- Mississippi River near Aitkin, MN Completed 1957 1,675,835 Pembina River, ND Active4 1983 -- Pembina River Lake, ND Inactive 1' 1950 50,000 - Red Lake River at Huot, MN5 Completed 1984 64,500 - Red Lake River at Red Lake Falls, MN 5 Completed 1984 131,000 - Red River of the North at Oslo, MN8 Completed 1984 1,960,200 - Red River of the North at Pembina, ND8 Completed 1979 2,000,000 - Redwood River below Marshall, MN8 Completed 1960 202,400 - Rushford, MN Completed 1980 3,192,333 - St. Paul and South St. Paul, MN Completed 1974 8,476,01212- Tongue River Lake, ND Inactive" 1950 23,695 - Upper Iowa River, IA Completed 1964 888,445 - Velva, ND7 Completed 1970 334,628 - Vermillion River, Hastings, MN8 Completed 1980 999,900 - Warroad River and Bull Dog Creek, MN Inactive13 1974 182,000 - Zumbro River, MN Completed 1975 1,284,100 - 'Advance engineering and design costs only. Project deferred with authorization of Lake Darling project. Additional authorization required for implementation of recommended plan. The Senate Report 97-256 states that the Corps is to take no further action to construct Burlington Dam until directed to do so by Congress. 23EInx cludes $42,766 contributed funds. addition $87,878 was expended from Public Law 99 funds in the spring of 1969 for emergency protection and incorporation into the permanent project. 4Preconstruction planning has not started. Phase I completed under General Investigations. 5Project authorized by Chief of Engineers under small project authority, Section 14, Flood Control Act of 1946, as amended. 6Preconstruction planning has not started. 7Excludes $46,034 for the Ruffy Brook unit for which authorization expired in April 1966 (see table 27-G). Excludes $246,911 contributed funds. 8Project authorized by Chief of Engineers under small project authority, Section 205, 1948 Flood Control Act, as amended. 9Excludes $35,000 contributed funds. "0Excludes $4,167 contributed funds. "1Further work deferred pending review of project document (inactive). 12Excludes $545,637 contributed funds for new work and $38,000 expended by South St. Paul for work in lieu of required cash contribution. Excludes an additional $206,629 expended for work done at request of local interests. ' 3Preconstruction planning suspended. Local interests requested the project be reclassified to inactive due to a limitation of their funding capability. The project was classified inactive on April 5, 1974. 27-24 TABLE 27-G ST. PAUL MINNESOTA DISTRICT DEAUTHORIZED PROJECTS For Last Full Report Federal Contributed See Annual Date Funds Funds Project Report For Deauthorized Expended Expended Black River, WI' 1950 Aug. 5, 1977 - - Black River Lake, WI 1950 Aug. 5, 1977 - - Maple River, ND2 1981 Oct. 6, 1961 $1,241 - Moorhead, MN2 1981 Oct. 30, 1961 27,700 - Ruffy Brook, MN 1967 Apr. 1966 46,034 Sheyenne River, ND2 1981 Dec. 31, 1970 37,956 - Warroad Harbor and River, MN3 1981 Aug. 5, 1977 - 'Portion of project for removal of obstructions at various points outside the dredged area to clear channel to full project width (see table 27-C for costs for completed portion of project). 2Part of Red River of the North Drainage Basin (see Section 27 in text and table 27-J for costs for active units of the project). 3Portion of dredging of entrance channel and turning basin to complete project width and depth (see table 27-A for costs for completed portion of project). 27-25 RESERVOIRS AT HEADWt MISSISSIPPI RIVI (See Section 3 of Te: Outlet Watershed Area (square miles) Cal Minimum Above Watershed Mai Stages St. Paul (square Original S1 Reservoir (feet)' River (miles) miles) Lake Reservoir (acr Winnibigoshish 6 Mississippi Leech Lake 0 Leech Pokegama 6 Mississippi Sandy Lake 7 Sandy Pine River 9 Pine Gull Lake 5 Gull 408 410 344 267 199 168 1,442 1,163 6602 421 562 117 173 24 8 18 287 20 Surveys and flowage rights Recreational facilities 179.4 96 250.9 74 35.0 12 16.6 7 23.7 17 20.5 7 Total new work Total operating and care Permanent indefinite appropriation for operation and care, Feb. 1, 1985 to end of fiscal year 1936 Rehabilitation Total ALTERS OF JR xt) pacity Previous Projects Existing Projects at timum tage Com- Com- Total x e-feet) pleted Cost pleted Cost Cost 7,930 1884 $214,000 1900 $173,470 $387,470x 3,320 1884 171,805 1902 84,380 256,185 t 0,750 1884 85,000 1904 126,030 211,0300 2,500 1895 114,000 1909 117,020 231,020 i 7,520 1886 97,000 1907 133,320 230,320M 0,820 - - 1913 86,826 86,8260 - - - - 160,939 160,939 - - - - 2,834,838 2,834,838 M - - 681,805 - 3,716,823 4,398,628 p - - 100,857 - 20,330,633 20,431,490 - 2,152,840 - - - 967,197 967,197 - - - 425,000 425,000 - $782,662 - $25,439,653 $26,222,315 1Lower operating limits by regulations approved February 4, 1936, as modified December 29, 1944. 2Exclusive of area controlled by Winnibigoshish and Leech Lake Dams. TABLE 27-H ST. PAUL MINNESOTA DISTRICT TABLE 27-I NAVIGATION WORK UNDER SPECIAL AUTHORIZATION Navigation Activities Pursuant to Section 107 Public Law 86-645 (preauthorization) Study identification Fiscal Year Costs Zippel Bay, Lake of the Woods Co., MN $25,752 TABLE 27-J RED RIVER OF THE NORTH DRAINAGE BASIN: ACTIVE UNITS IN COMPREHENSIVE BASIN PLAN (See Section 27 of Text) Total Cost to Estimated Name of Unit State Type September 30, 1985 Federal Cost Orwell Reservoir (Otter Tail River) Minnesota Reservoir $1,916,753 $1,916,7001 Wild Rice and Marsh Rivers Minnesota Channel improvement 405,056 405,100 Rush River North Dakota Channel improvement 287,686 287,000 Sand Hill River Minnesota Channel improvement 548,778 548,800 Mustinka River Minnesota Channel improvement 440,788 440,800 Otter Tail River Minnesota Channel improvement 174,768 174,800 Red River at Grand Forks North Dakota Levees and floodwall 948,895 948,900 Red River at East Grand Forks Minnesota Levees, floodwall, pumping plants 1,145,958 23,400,000 Red River at Fargo North Dakota Channel improvement, levees 1,639,924 1,639,9002 Total cost to date 7,508,606 Total estimated cost 29,762,000 'Includes $181,713 for lands and $25,045 for recreation facilities. 2Includes $67,900 for lands. 3Costs of $11,239 for the Wahpeton-Breckenridge inactive unit not included. Authorization of the Sheyenne River, Moorhead, and Maple River units has expired. Cost of these units also not included total $66,897. 4The Wahpeton-Breckenridge unit of the project is classed as 'inactive' and is excluded from the estimate. The cost of this unit, last revised in 1955, was estimated to be $996,000. The Flood Control Act approved December 31, 1970 (H. Doc. 330-91-2) provided for deletion of the Sheyenne River unit, and authorization of the Maple River and Moorhead units expired at the end of the 5-year period within which local interests were required to furnish assurances of local cooperation. Authorization of these units, not included, expired on the dates indicated in table 27-G. 27-27 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 27-K INSPECTION OF COMPLETED FLOOD CONTROL PROJECTS (See Section 40 of Text) Project, Date Inspected Arcadia, W I ....................................................................... October 1984 Blackl River (North Bend), WI ..................................................... October 1984 Breckenridge, MN .............................................................. September 1985 ClearWater River, MN .......................................................... November 1984 Cochrane, W I .................................................................... October 1984 Elk River, M N .................................................................. Novem ber 1984 Enderlin, ND .................................................................. September 1985 Fargo, ND .................................................................... Septem ber 1985 Forest River, ND ............................................................... November 1984 Grand Forks, ND .............................................................. September 1985 Huot, M N ..................................................................... Septem ber 1985 Irving Township, W I.............................................................. October 1984 Lost River, M N ....................... .......................................... Novem ber 1984 Lower Branch Rush River, ND..................................................November 1984 M ahonmen, M N ............................................................... September 1985 M ankato, M N ................................................................. September 1985 M arsh River, M N ............................................................... November 1984 M arshall, M N ................................................................. September 1985 Minneota, M N ................................................................. September 1985 M inot, N D .......................................................................... July 1985 Mustinka River, MN.............................................................November 1984 Oslo, M N ...................................................................... Septem ber 1985 Otter Tail River, M N ............................................................ November 1984 Park River, ND ................................................................. Novem ber 1984 Pembina, ND .................................................................. September 1985 Red Lake Falls, MN ........................................................... September 1985 Red Lake River, MN ......................... ..................................... November 1984 Redwood River, MN ............................................................................. November 1984 Rush River, ND ................................................................. November 1984 Sand Hill River, MN............................................................November 1984 Sheyenne River, ND ........................................................... November 1984 St. Paul, M N .................................................................. September 1985 Velva, N D ............................................................................ July 1985 Wild Rice River, M N ............................................................ November 1984 Zumbro, River, MN ............................................................ September 1985 27-28 ST. PAUL MINNESOTA DISTRICT TABLE 27-L FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION Flood control activities pursuant to Section 205, Public Law 858, 80th Congress, as amended (preauthorization) Study Identification Crow River, Rockford, MN Emerson, Manitoba-Noyes, MN English Coulee, Grand Forks, ND Fridley, MN Gilmore Creek, Winona, MN Jordan, MN Kickapoo River, Viola, WI Lake Altoona, WI Lake Pulaski, Buffalo-Wright County, MN Minnesota River, Henderson, MN Neche, ND Root River, Hokah, MN Sand Hill River, Winger, MN Sanders Creek, Boscobel, WI School Section Lake, Maine Prairie, MN Snake River, Alvarado, MN Wild Rice River, Ada, MN Fiscal Year Costs $ 7,500 35,065 70,668 22,903 53,112 29,084 7,500 7,500 68,764 93,601 65,476 32,451 7,500 27,994 7,500 21,482 27,651 Emergency bank protection (Section 14 of the 1946 Flood Control Act, Public Law 526, 79th Congress) Project and Location Fiscal Year Costs Black River, Van Loon Lane, Holland Township, WI $ 3,500 Warner Road, Mississippi River, St. Paul, MN 23,049 Emergency flood control activities - repair, flood fighting, and rescue work (Public Law 99, 84th Cong., and antecedent legislation) Project Fiscal Year Costs Disaster preparedness $335,611 Emergency operatons .1,291 Total emergency flood control activities 336,902 27-29 ROCK ISLAND, IL, DISTRICT* This district comprises most of the northern half of Illinois, portions of southern Wisconsin, southern and southwestern Minnesota, eastern and central Iowa, and northeastern Missouri, embraced in drainage basin of Mississippi River and its eastern and western tributaries between mile 300 (above mouth of Ohio River) and 614, and of its eastern tributaries only, between Hamburg Bay, at mile 261 and 300. This district also includes the Illinois Waterway above mile 80 with its tributaries and drainage basins. The section of the Mississippi River between river miles 300 and 614 is included in the report on Mississippi River between Missouri River and Minneapolis, MN. IMPROVEMENTS Navigation Page 1. Illinois and Mississippi Canal, IL ........... 28-2 2. Illinois Waterway, IL and IN ............. 28-2 3. Mill Creek and South Slough at Milan, IL .... 28-3 4. Mississippi River between Missouri River and Minneapolis, MN ..................... 28-3 5. Muscooten Bay, Illinois River, IL ........... 28-3 6. Upper Mississippi River Environmental Management Program, IL, IA, MN, MO, WI. 28-3 7. Other Authorized Navigation Projects ....... 28-3 Flood Control 8. Ames Dam and Reservoir, Skunk River, IA .. 28-3 9. Bettendorf, IA ......................... . 28-4 10. Coralville Lake, IA ....................... 28-4 11. Davenport, IA ............................ 28-4 12. Des Moines Recreational River and Greenbelt, IA .......................... . 28-4 13. Farm Creek, IL ......................... 28-5 14. M ilan, IL .............................. 28-5 15. Red Rock Dam and Lake Red Rock, IA ...... 28-5 16. Rockford, IL . . . . . . . . ................. 28-5 17. Saylorville Lake, IA ..................... 28-5 18. W aterloo, IA ......................... .. 28-6 19. Inspection of Completed Flood Control Projects ........................ . 28-6 20. Other Authorized Flood Control Projects ..... 28-6 21. Flood Control Work Under Special Authorization ........................... 28-6 General Investigations Page 22. Surveys ................................. 28-6 23. Collection and Study of Basic Data ......... 28-6 24. Continuation of Planning and Engineering ... 28-6 25. Advance Engineering and Design ........... 28-7 Tables Table 28-A Cost and Financial Statement ....... 28-8 Table 28-B Authorizing Legislation ........... 28-10 Table 28-C Other Authorized Navigation Projects ...................... . 28-13 Table 28-D Not Applicable Table 28-E Other Authorized Flood Control Projects ................ 28-14 Table 28-F Not Applicable Table 28-G Deauthorized Projects ............ 28-16 Table 28-H Inspection of Completed Flood Control Projects ................ 28-16 Table 28-I Flood Control Work Under Special Authorization ................... 28-18 Table 28-J Illinois Waterway: Existing Locks and Dams ................ 28-20 Table 28-K Illinois Waterway: Lock and Dam Construction, Foundations, Cost .... 28-20 Table 28-L Illinois Waterway: Additional Features Entering into Cost. ....... 28-21 Table 28-M Illinois Waterway: Existing Project ....................... . 28-22 Table 28-N Illinois Waterway: Total Cost of Existing Project .................. 28-22 28-1 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Navigation 1. ILLINOIS AND MISSISSIPPI CANAL, IL Location. This canal extends for 75 miles from the Illinois River near LaSalle, IL, to the Mississippi River at Rock Island, IL. A feeder canal, 29 miles in length, extends from the summit level of the canal to the Rock River at Rock Falls, IL. Existing project. See pages 1306-1308 of Annual Report for 1962 for details regarding project. The canal was constructed in the period 1892-1918. The canal has not been operated for navigation since June 1951 in accordance with Corps policy to discontinue operation of waterways affording little or no benefit to navigation. The River and Harbor Act of 1958 authorized the appropriation of $2,000,000 for the purpose of placing the canal in proper condition for public recreational use and to convey and transfer the canal to the State of Illinois as part of the State park system. The repair and modification program was initiated in 1961, and a number of canal features have been repaired or modified. In connection with this program, fee title to 1,062 acres and recreational flowage easements over 309 acres of land in Rock River at Rock Falls, formerly under navigation flowage easement, have been acquired. The State of Illinois accepted title to the canal as of August 1, 1970. The River and Harbor Act of 1970 authorized the additional appropriation of $6,528,000 to be expended for the repair, modification, and maintenance of bridges, title transfer, modification or rehabilitation of hydraulic structures, fencing, clearing auxiliary ditches, and for the repair and modification of other canal property appurtenances. Local cooperation. None required. Operations during fiscal year. During FY 1982, a judgment of the Court of Appeals, 7th Circuit, directed that a fund of $2,812,658 plus interest at 12 percent per annum computed from February 23, 1979, be established by the United States in the District Court from which payments are to be made to plaintiffs for required repairs to Illinois and Mississippi Canal bridges. Actual payment for the judgment award was $3,722,572, which included interest at 12 percent through November 4, 1981. Engineering and design work in connection with this matter cost $330,888 during FY 1985. 2. ILLINOIS WATERWAY, IL AND IN Location. Illinois River (entirely within State of Illinois), formed by confluence of Kankakee and Des Plaines River, flows southwesterly and enters Mississippi at Grafton, IL, about 38 miles above St. Louis. Illinois Waterway comprises Illinois River from its mouth to confluence of Kankakee and Des Plaines Rivers (273 miles); Des Plaines River to Lockport (18.1 miles) and Chicago Sanitary and Ship Canal and South Branch of Chicago River to Lake Street, Chicago (34.5 miles). Also from a point 12.4 miles above Lockport, IL, waterway comprises Calumet-Sag Channel and Little Calumet and Calumet Rivers to turning basin 5, near entrance to Lake Calumet (23.8 miles); and Grand Calumet River from junction to 141st Street, deep (lake) draft navigation (9 miles) and to Clark Street, Gary, IN (4.2 miles). Previous projects. For details, see page 1945 of Annual Report for 1915 and page 1172 of Annual Report for 1932. Existing project. See table 28-K and page 1255 of Annual Report for 1963. Cost of new work is $124,041,436 and includes $445,000 for Recreation Facilities under Code 711. Calumet-Sag Modification, Part II, placed in the inactive category in June 1973, cost of $132,000,000 (July 1972) Federal and $16,300,000 (July 1972) non-Federal; Calumet- Sag Modification, Part III, placed in the deferred-for-restudy category in March 1972, cost of $33,000,000 (July 1971) Federal and $20,700,000 (July 1971) non-Federal; widen Pekin Bend, a portion of work authorized by River and Harbor Act of 1935, placed in the inactive category, cost of $1,360,700 (July 1972) Federal; and widen Marseilles Canal to 300 feet, a portion of work authorized by River and Harbor Act of 1935, placed in the deferred category, cost of $1,859,300 (July 1972) Federal, are all excluded from present cost estimate. (See also tables 28-J through 28-N on authorizing legislation; existing locks and dams; lock and dam construction, foundations, cost, and additional features entering into cost of project.) Local cooperation. Complied with for completed modifications and Part I of Calumet-Sag Modification. All pools above Alton Pool: Maintenance: Channel dredging by the Dredge DUBUQUE was performed at various locations in LaGrange pool at a cost of $442,600, with a total of 241,510 cubic yards of material being removed. Strike removal and snagging and clearing was accomplished in various locations by hired labor at a cost of $250,200. Environmental concerns in connection with dredging activities cost $55,100. Maintenance of the Lucas-Berg Disposal Facility cost $11,900, and contractor earned $30,000 on a construction mitigation contract at this facility. Deflection dikes to prevent siltation and to reduce dredging requirements were constructed by hired labor at a cost of $361,400 in Dresden Island and Peoria pools. Structural repairs to locks and dams were performed by hired labor at a cost of $1,420,300. Contractor earned $7,300 on completion of installation of standby generators at Dresden and Starved Rock Locks. Contractor earned $171,400 for modification of miter gate machinery at Marseilles Lock. High pressure sodium vapor lighting and protective piers were completed by contractor at Peoria and LaGrange Locks at a cost of $11,800. Resurfacing of access roads at Starved Rock and Peoria Locks and Dams were completed by contract at a cost of $48,300. Buildings, grounds, and utility maintenance at the locks and dams and Illinois Waterway Project Office at Peoria totaled $59,200. Permanent operating equipment costs were $75,100, and other maintenance work items totaled $22,600. Engineering and design work including preparation of design memorandums cost $548,800, and supervision and administration for the maintenance features totaled $183,900. Total maintenance costs were $3,699,900. Net credits to the project were $361,900, primarily as a result of collection of damages from towboat companies to lock and dam structures. Operation and Care: Operation of the locks and dams and routine maintenance and minor repairs thereto were made at a cost of $4,884,400. Illinois Waterway Project 28-2 ROCK ISLAND, IL, DISTRICT* Office at Peoria was continued at a cost of $534,200. Real estate management services were provided at a cost of $44,500. Visitor's Center at Starved Rock Lock and Dam was operated at a cost of $155,200, with contract law enforcement provided at a cost of $5,300. Surveys, studies, and other inspections were performed at a cost of $234,400; natural resource activities cost $16,300; and water control management costs were $908,800; other operation activities totaled $31,500. Supervision and administration for the operation features totaled $225,400. Total operation costs were $7,040,000. Total operation and maintenance costs were $10,378,009 for all pools above Alton Pool. Rehabilitation: Rehabilitation work at Dresden Island, Brandon Road, Starved Rock, and Lockport Lock Locks and Dams was in progress. Costs at Dresden Island were $7,545; at Brandon Road, $3,151,646; at Starved Rock, $1,515,260; at Lockport, $5,310,535; and at Marseilles, $404,733; for a total of $10,389,719. Alton Pool Operation: Costs by hired labor for condition and operation studies were $175,356; water control management $48,277; and supervision and administration $7,988. Alton Pool Maintenance: Costs for the year were $44,615 for dredging and $764 for supervision and administration. Total cost for work in Alton Pool was $277,000. Total operation and maintenance costs for all pools above Alton Pool were $10,378,009; Alton Pool operation and maintenance costs were $277,000; for a total operation and maintenance cost of $10,655,009. 3. MILL CREEK AND SOUTH SLOUGH AT MILAN, IL Location. Mill Creek and South Slough are small streams, tributary to the Rock River, at Milan, Rock Island County, IL. Existing project. The existing project provided for flood protection at the village of Milan necessitated by the construction of the Illinois and Mississippi Canal. The project consisted of diversion of Mill Creek into South Slough, floodgates in the walls of the Illinois and Mississippi Canal to carry Mill Creek flood waters across the canal right-ofway into Rock River, levees, and other works for flood protection. The project was constructed in 1931-1932. In 1962-1963, $73,366 was expended from Illinois and Mississippi Canal maintenance funds for restoration of the Mill Creek outlet into Rock River. See Table 28-B for authorizing legislation. Local cooperation. Fully complied with. Operations during fiscal year. Minor channel maintenance was performed at a cost of $11,895. 4. MISSISSIPPI RIVER BETWEEN MISSOURI RIVER AND MINNEAPOLIS, MN For report on this improvement, see chapter on "Mississippi River between Missouri River and Minneapolis, MN." 5. MUSCOOTEN BAY, ILLINOIS RIVER, IL Location. Muscooten Bay is located along the left bank of the Illinois River at the northeast edge of the city of Beardstown, IL. The Beardstown Community Boat Harbor occupies part of the bay. Existing project. Sedimentation in the bay restricted the use of the boat harbor, particularly at the entrance. The existing project provided for the construction of a bedload diversion rock dike to reduce sedimentation and the dredging of a 1,700-foot navigation channel. Local cooperation. Section 107 of the River and Harbor Act of 1960 applies. In addition, local interests must comply with applicable provisions of the Uniform Relocation Assistance and Real Property Acquisition Policies Act of 1970; comply with Section 601 of Title VI of the Civil Rights Act of 1964; contribute all project costs in excess of the Federal statutory limitation of $2,000,000; provide and maintain berthing areas, floats, piers, slips, and similar facilities; provide utilities, relocations, and alterations; and grant the Federal Government the right to enter upon project lands. Local interests must also bear one-half the first cost of the general navigation features. Assurances of local cooperation were approved on August 18, 1983. Operations during fiscal year. Project construction was completed. Costs during the year were $18,414. 6. UPPER MISSISSIPPI RIVER ENVIRONMENTAL MANAGEMENT PROGRAM, IL, IA, MN, MO, WI Location. The project is located in the Mississippi River Basin encompassing a 5-State area including IL, IA, MN, MO, and WI. Existing project. The project represents the initial implementation of the master plan prepared by the Upper Mississippi River Basin Association (report dated January 1982). Project features include long-term resources monitoring, habitat rehabilitation and enhancement, recreation improvement and studies, traffic monitoring, and computerized inventory and analysis. The project will be initiated in FY 1986 utilizing funds provided by the FY 1985 Supplemental Appropriation Act. The execution of the project will be closely coordinated with the Upper Mississippi River Basin Association, other Federal agencies, affected States, and local communities. Local cooperation. Local cooperation agreements will be sought as required. Operations during fiscal year. No activity. Funds were received September 30, 1985. 7. OTHER AUTHORIZED NAVIGATION PROJECTS See Table 28-C. Flood Control 8. AMES DAM AND RESERVOIR, SKUNK RIVER, IA Location. The Ames Lake project is located on the Skunk River in Story County, IA, about 5 miles upstream from the city of Ames, IA. 28-3 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Existing project. Major project features would include a dam constructed of compacted impervious earth with gated outlet works and spillway; a subimpoundment forming a 30-acre lake by blocking a ravine with embankment for access road crossing the dam; relocations consisting of roads, telephone and power lines; and remedial protection for Story City by levee and street raises. The conservation pool would have a surface area of 2,100 acres and the full flood control pool would have a surface area of 5,000 acres. The project was authorized to store water for flood control, water quality control, recreati6n, and fish and wildlife benefits. Local cooperation. By letter dated October 26, 1973, the Governor of IA advised "There is general agreement that the project provides definite flood control benefits to the downstream landowner. However, the costs associated with it and the values to be foregone as a result of the project outweigh the benefits. Therefore, at this time, the State's position must be that of general opposition to the project." Due to the State's position in regard to the project, it was reclassified from the "active" to the "inactive" category on June 20, 1974. Recently, there has been renewed congressional and local interest in this project. By letter dated March 6, 1984, the city of Ames, IA, provided a copy of a resolution that the City Council adopted February 28, 1984, requesting reactivitation of the project. The project was approved for reactivation on July 2, 1984. Operations during fiscal year. New work: Effort wasinitiated on a General Reevaluation Report (GRR). Costs totaled $194,053. 9. BETTENDORF, IA Location. The city of Bettendorf is located on the right bank of the Mississippi River 485.7 miles above the mouth of the Ohio River, in Scott County, IA. Existing project. Local flood protection from the Mississippi River to be provided by construction of 3 miles of earth levee, railroad raises, closure structures, and street raises and ramps. Construction was started in July 1982. Estimated project cost is $16,010,000 including $1,510,000 non-Federal cost for lands and relocations. See Table-28B for authorizing legislation. Local cooperation. Fully complied with. Operations during fiscal year. New work: Construction continued. The project is 65 percent completed. Costs were $2,952,322. 10. CORALVILLE LAKE, IA Location. Coralville Lake is formed by the Coralville Dam on the Iowa River, several miles upstream from Iowa City, Johnson County, IA, about 83 miles above the confluence of the Iowa River with the Mississippi River. Existing project. See page 28-4, Annual Report for 1981, for project details. Construction began in July 1949 and the project has been in operation since February 1958. About 24,389 acres of land were acquired in fee, and flowage easements obtained for 9,494 acres. The project was modified to provide for construction of a highway bridge crossing the lake at the Mehaffey site, which was begun in June 1964 and completed in October 1966. See Table 28-B for authorizing legislation. Local cooperation. None required, except in connection with the Mehaffey Bridge, which has been fully complied with. Operations during fiscal year. New work: Additional land acquisition to provide for the present plan of reservoir operation performed at a cost of $3,656,994. Maintenance: Routine maintenance activities continued at a cost of $2,524,087. Expenditures from return of recreation use fees: $103. 11. DAVENPORT, IA Location. The city of Davenport is located on the right bank of the Mississippi River, 482.4 miles above the mouth of the Ohio River, in Scott County, IA. Existing project. Local protection to the city from floods on the Mississippi River to be provided by construction of levees, floodwall, interior drainage facilities and pump plants, closure structures, and recreational facilities. The project also provides for the enhancement and preservation of Nahant Marsh at the downstream edge of the city as a wetland area with important contribution to environmental quality. Estimated project cost is $40,600,000, including $15,100,000 non-Federal cost for land and relocations. See Table 28-B for authorizing legislation. Local cooperation. The city has withdrawn support for the project because of high costs and public opposition. Operations during fiscal year. New work: Preconstruction planning and engineering were discontinued. Costs during the year were $2,240. 12. DES MOINES RECREATIONAL RIVER AND GREENBELT, IA Location. The greenbelt area is located along both banks of the Des Moines River in central IA and extends from a point at which relocated U.S. Highway 92 crosses the Des Moines River near Harvey, upstream approximately 169 river miles to U.S. Highway 20 at Fort Dodge, IA. It includes the Corps' operated Lake Red Rock and Saylorville Lake projects. Existing project. The project will include, but not be limited to: (1) the construction, operation, and maintenance of recreational facilities and streambank stabilization structures; (2) the operation and maintenance of all structures constructed before the date of authorization of this project (other than any such structure operated and maintained by any person under a permit or agreement with the Secretary); (3) such tree plantings, trails, vegetation, and wildlife protection and development and other activities as will enhance the natural environment for recreational purposes; and (4) the prohibition or limitation by the Secretary of the killing, wounding, or capturing at any time of any wild bird or animal in such areas as may be directed by the Secretary. In carrying out the project, the Secretary may acquire by purchase, donation, exchange, or otherwise, land and interests therein, as the Secretary determines are necessary to carry out such project. The authorization requires that an Advisory Committee will be established for consultation with the Department of the Army consisting of three Corps of Engineers 28-4 ROCK ISLAND, IL, DISTRICT appointees, one person from the city of Des Moines, and one from each other incorporated municipality within the greenbelt, two from each of eight counties in the greenbelt, and five from the State of IA. Local cooperation. There is strong local support for the project by recreational and environmental interests. These interests were instrumental in developing and supporting the authorization for the project. However, since cost-sharing requirements have not been developed for elements of the project or coordinated with respective sponsors, it is unknown how many of the potential 20 or more sponsors are willing or able to participate in the project under terms and conditions acceptable to the Secretary of the Army. Operations during fiscal year. No activity. Funds were received September 30, 1985. 13. FARM CREEK, IL Location. Farm Creek watershed in Tazewell County, IL, is 60 square miles in extent. Stream empties into Illinois Waterway at mile 162 above mouth. Existing project. See page 28-5, Annual Report for 1983 for description of project. Local cooperation. Fully complied with. Operations during fiscal year. Maintenance: Routine maintenance activities were continued at a cost of $98,920. 14. MILAN, IL Location. The village of Milan is located on the south bank of the Rock River several miles upstream from the confluence of that stream with the Mississippi River at mile 479.1 above the mouth of the Ohio River, in Rock Island County, IL. Existing project. Local protection against direct flooding from Rock River and Mill Creek and against backwater flooding from the Mississippi River to be provided the community by construction of levees, floodwalls, closure structure, bridges, pumping stations, drainage facilities, and street ramps. Construction was initiated in March 1981. The estimated project cost is $17,800,000, including $3,440,000 non-Federal cost for land and relocations. See Table 28-B for authorizing legislation. Local cooperation. Fully complied with. Operations during fiscal year. New work: Construction of the project continued at a cost of $2,464,332. The principal work items were levee construction and utilities relocations. The project is about 90 percent completed. 15. RED ROCK DAM AND LAKE RED ROCK, IA Location. The site of this project is on the Des Moines River, chiefly in Marion County, but extending into Jasper, Warren, and Polk Counties. The dam is 142.9 miles above the mouth of the Des Moines River, which empties into the Mississippi River at mile 361.4 above the mouth of the Ohio River. The city of Des Moines lies northwesterly from the site, about 60 miles upstream. Existing project. See page 28-6, Annual Report for 1981 for description of the project. Construction began in May 1960, and the dam was placed in beneficial use for storage of flood water in January 1969. Land acquired for the project consisted of 47,610 acres in fee and 28,214 acres in flowage easement. See Table 28-B for authorizing legislation. Local cooperation. None required. Operations during fiscal year. Maintenance: Routine maintenance activities were continued at a cost of $3,263,730. Expenditures from the return of recreation use fees were $36. 16. ROCKFORD, IL Location. The city of Rockford is located along both banks of the Rock River, in Winnebago County, IL. Kent Creek is a small stream, tributary to the Rock River, which flows through the right-bank portion of the city. Existing project. The project provides flood protection for the right-bank portion of the city from floods on Kent Creek. It consists of a rolled earth dam with outlet works and spillway on North Branch Kent Creek in Page Park; 12,000 feet of channel cleanout and straightening on North Branch Kent Creek; raise of Levings Lake Dam on South Branch Kent Creek and construction of spillway and diversion channel; 10,800 feet of channel cleanout and straightening on South Branch Kent Creek; and relocations. Construction was initiated in October 1978. The estimated project cost is $16,570,000, including $6,430,000 for land and relocations. See Table 28-B for authorizing legislation. Local cooperation. Fully complied with. Operations during fiscal year. New work: Construction of the project was continued at a cost of $883,485. The principal work items were channel cleanout and straightening on North Branch Kent Creek and construction of the diversion channel on South Branch Kent Creek. The project is about 80 percent completed. 17. SAYLORVILLE LAKE, IA Location. The project site is chiefly in Polk County, IA, but portions extend into Dallas and Boone Counties. The dam is about 213.7 miles above the mouth of the Des Moines River and about 5 miles upstream from the city of Des Moines, IA. Existing project. The dam is an earth embankment 6,750 feet long at crest with a height of 120 feet. Outlet works are a single circular concrete conduit, 22 feet in diameter, located at the toe of the west bluff. Control structure is at upstream end of conduit and houses three gates. A stilling basin is provided to dissipate energy of discharge from outlet conduit. Spillway is in west bluff, weir 430 feet long. Water flowing over the spillway weir discharges into a paved chute and thence into an escavated earth channel to the Des Moines River. Top of spillway is about 31 feet below top of earth embankment section, and flow over weir is uncontrolled when water in reservoir reaches its crest. Watershed area above dam site is 5,823 square miles. With pool at spillway crest elevation, lake area is 16,700 acres and contains about 676,000 acre-feet of water at that height (602,000 for flood control and 74,000 for a conservation pool to maintain minimum flows at downstream points). 28-5 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Lake supplements capacity of downstream Lake Red Rock at river mile 142.9.. The two lakes provide a high degree of flood protection to the lower Des Moines River Valley. Reaches along the Mississippi River downstream from the mouth of the Des Moines River are also benefited. A project modification plan to minimize the adverse environmental effects at Ledges State Park, located upstream from the dam, was authorized in 1976. The project modification includes relocation of affected park facilities, acquisition of additional park land, and the development of a floodway corridor, with recreational facilities, from the dam downstream to Sixth Avenue in Des Moines. Construction began in June 1965, and the dam was placed in operation for the storage of flood water in April 1977. Remedial work in Big Creek Valley, consisting of a diversion dam and channel and a barrier dam, for the protection of the town of Polk City was completed in December 1974. The land acquisition program involved 25,924 acres acquired in fee, flowage easements for 1,858 acres, and roadway easements for 40 acres. The estimated project cost is $126,056,000, including $2,660,000 non-Federal cost as a cash contribution from the State of Iowa toward recreational development. See Table 28-B for authorizing legislation. Local cooperation. Fully complied with. Operations during fiscal year. New work: The principal work item was the construction of recreational facilities. Work was also continued on the archeological program and on engineering and design work for the downstream floodway corridor. New work costs were $6,404,697. Maintenance: Routine maintenance activities were continued at a cost of $2,724,425. Expenditures from return of recreation use fees were $865. The project is about 84 percent completed. 18. WATERLOO, IA Location. The city of Waterloo is located along both banks of the Cedar River in Black Hawk County, IA. Existing project. The project provides local protection to the city of Waterloo from floods on the Cedar River, Black Hawk Creek, Virden Creek, and Blowers Creek. It consists of 15.4 miles of earth levee, 2 miles of floodwall, 11,330 feet of channel improvement, an impounding dam on Virden Creek, and interior drainage facilities including 8 pumping plants. Extensive urban renewal, undertaken by the city, has been coordinated with the flood control project. Construction was initiated in August 1972. The estimated project cost is $64,100,000, including $15,000,000 non-Federal cost for land and relocations. See Table 28-B for authorizing legislation. Local cooperation. Fully complied with. Operations during fiscal year. New work: Construction of the project was continued at a cost of $895,506. The principal work items were continuation of construction of levees and floodwalls along the Cedar River. The project is about 99 percent completed. 19. INSPECTION OF COMPLETED FLOOD CONTROL PROJECTS Federal flood control regulations (part 208 of title 33, Code of Federal Regulations) provide that the structures and facilities constructed by the United States for local flood protection shall be continuously maintained in such a manner and operated at such times and for such periods as may be necessary to obtain the maximum benefits. Costs during the period for inspections of projects turned over to local interests to ascertain compliance with Federal requirements were $165,784. (See Table 28-H for list of completed flood control projects inspected.) 20. OTHER AUTHORIZED FLOOD CONTROL PROJECTS See Table 28-E. 21. FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION Flood Control Activities, Section 205, Public Law 84-685. See Table 28-I. Snagging and Clearing of Navigable Streams and Tributaries in Interest of Flood Control, Section 208, Public Law 83-780. See Table 28-I. Emergency Flood Control Activities, Public Law 99, 84th Congress. See Table 28-I. General Investigations 22. SURVEYS Flood control studies in progress included the Fox River and Tributaries, WI; the Mississippi River, Coon Rapids to Ohio River; the Illinois River from Henry to Naples, IL; Quincy Bay, IL; the Mackinaw River Basin, IL; and the Vermilion River Basin, IL. Total cost of flood control studies was $576,349. Review of completed projects cost $28,646. Review for deauthorization, special investigations, FERC review, SCS coordination, and planning assistance to States efforts totaled $124,320. Total cost of surveys was $729,314. 23. COLLECTION AND STUDY OF BASIC DATA Flood plain management services cost $203,289. Hydrologic studies, including general studies, sedimentation studies, streamflow studies, and rainfall studies cost $2,355. Total cost for collection and study of basic data was $205,644. 24. CONTINUATION OF PLANNING AND ENGINEERING The Loves Park, IL, project, part of an authorized study of the Rock River in the vicinity of Rockford, IL, lies in Winnebago County, IL, on the northeast boundary of the city of Rockford, 17 miles south of the IL-WI State line. The project would provide local flood protection (100-year level) for the city of Loves Park, IL, against flooding of Loves Park Creek (formerly called the Large Unnamed Creek). Protection measures would consist of 17,900 feet of channel improvements, a 75,000 GPM pump plant, and ponding. Congress has appropriated funds for preconstruction planning and engineering studies at Loves Park. A General Reevaluation Study was initiated on October 17, 1984. FY 1985 cost for initiation of work on the General 28-6 ROCK ISLAND, IL, DISTRICT Reevaluation Report (GRR) was $187,644. The South Quincy, IL, project is located in the South Quincy Drainage and Levee District in Adams County, IL. The existing project protects 5,800 acres of agricultural, commercial, industrial, and residential lands from floods up to a 50-year chance of occurrence. The proposed plan would raise the level of protection to a 500-year chance of occurrence. The levee is about 8.8 miles long and starts in the vicinity of Curtis Creek and Highway 57 on the north, runs along the south bank of Curtis Creek, along the east bank of the Mississippi River, and along the north bank of Mill Creek, and ends in the area of Mill Creek and Highway 57. Fiscal 1985 work on the project includes a General Reevaluation Report (GRR) and initiation of a General Design Memorandum (GDM) at a cost of $138,466. Total cost for continuation of planning and engineering was $326,110. 25. ADVANCE ENGINEERING AND DESIGN The Hannibal, MO, project area is on the right bank of the Mississippi River at the city of Hannibal, MO, 309 miles above the mouth of the Ohio River. The project would provide flood protection to the business and industrial area of the city of Hannibal by the construction of a system of levees and floodwalls. The plan also included a pumping plant, closure structures for railroads and streets, alteration of the existing sewage system, and a tainter gate closure at the mouth of Bear Creek. Advance planning on the project was begun in 1962; however, in 1965 further work was discontinued because of lack of local support. Local interest revived in 1979, and the project was reclassified from "inactive" to the "active" category. A study has been undertaken to reformulate the project to meet existing needs of the project area and to reflect current Federal and State criteria for water resources projects. No action toward fulfillment of local cooperation requirements has been taken. Detailed studies for reformulation of the project and evaluation of alternatives were continued at a cost of $80,692. The Moline, IL, project is located on the left bank of the Mississippi River, 485.7 miles above the mouth of the Ohio River, in Rock Island County, IL. Local protection at Moline from Mississippi River floods to be provided by construction of 4 miles of earth levee and floodwall, closure structures, aesthetic and recreational development, and interior drainage facilities consisting of gravity outlets, storm sewer interceptors, and pumping plants. Construction has not yet been initiated due to gaps in Federal funding. Local interests will be requested to furnish assurances after a firm project plan is established. Preconstruction planning continued at a cost of $48,410. Total cost for advance engineering and design was $129,102. 28-7 TABLE 28-A REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 COST AND FINANCIAL STATEMENT See Section Total Cost to in Text Project Funding FY 82 FY 83 FY 84 FY 85 September 1985 10. Coralville Lake, IA 11. Davenport, IA 12. Des Moines Recreational River and Greenbelt, IA 13. Farm Creek, IL Approp. Cost Contributed Funds Approp. Cost New Work: Approp. Cost Maint: Approp. Cost New Work: Approp. Cost New Work: Approp. Cost New Work: Approp. Cost Maint: Approp. Cost 3,722,572 1,100,000 3,724,915 2,423 1. Illinois and New Work: Mississippi Canal, Approp. IL Cost Maint: Approp. Cost 2. Illinois Waterway, New Work: IL and IN Approp. Cost. Maint: Approp. Cost Rehab: Approp. Cost 3. Mill Creek and New Work: South Slough at Approp. Milan, IL Cost Maint: Approp. Cost 5. Muscooten Bay, New Work: Illinois River Approp. Cost Contributed Funds Approp. Cost 6. Upper Mississippi New Work: River Environmental Approp. Management Program, Cost IL, IA, MN, MO, WI 8. Ames Dam and New Work: Reservoir, Skunk Approp. River, IA Cost 9. Bettendorf, IA New Work: 10,402,185 11,471,710 1,735,000 5,681,952 1,000 1,500 27,500 143,000 36,610 15,238 - 137,870 - 8,026 - 800,000 57,049 13,673,299 13,738,078 17,025,000 18,248,288 35,000 24,184 111,465 108,661 - 7,605,1431 - 7,605,1431 99,000 17,195,8102 330,888 17,184,5732 - 126,707,7513 - 126,706,4193 10,476,000 10,655,009 15,270,000 10,389,719 10,000 11,895 18,414 21,182 30,000 214,901,3964 211,515,0064 61,709,625 56,327,255 63,719 s 63,719 s 394,553 386,874 256,500 265,499 137,870 137,869 30,000 250,000 2,041,800 194,053 1,985,853 620,000 2,440,000 3,315,000 2,800,000 539,682 1,859,754 3,701,200 2,952,322 - - - 289,121 2,183,000 2,056,279 1,653,000 1,579,421 3,491,700 1,199,040 2,715,000 2,420,201 - 200,000 89,162 100,458 1,965,000 2,086,884 2,101,000 2,329,008 95,717 2,037,000 3,656,994 2,453,500 2,524,087 2,240 15,000 66,000 107,000 98,838 109,008 142,000 70,314 9,881,980 9,734,184 289,121 29,969,4886 29,070,4206 21,120,505 20,997,316 1,689,717 1,687,833 15,000 9,859,0207 9,859,0207 52,000 2,605,421 98,920 2,578,125 28-8 10,709,000 12,686,905 9,520,000 5,094,245 2,900 3,509 ROCK ISLAND, IL, DISTRICT TABLE 28-A (Continued) COST AND FINANCIAL STATEMENT See Section Total Cost to in Text Project Funding FY 82 FY 83 FY 84 FY 85 September 1985 14. Milan, IL 15. Red Rock Dam and Lake Red Rock, IA 16. Rockford, IL 17. Saylorville Lake, IA 18. Waterloo, IA 24. Loves Park, IL South Quincy, IL 25. Hannibal, MO Moline, IL I 1,500,000 3,400,000 1,527,638 3,522,286 - 12,000 1,750,000 1,397,449 1,633,000 1,966,265 1,400,000 117,433 229,032 85,125 50,000 489,056 2,968,500 2,927,214 400,000 866,122 -84,262 40,448 3,530,000 3,263,505 213,950 2,875,000 13,120,400 2,464,332 12,186,235 - 225,950 201,554 201,554 - - 95,302,484 - - 95,302,484 2,712,000 3,018,300 22,208,493 2,518,900 3,263,730 22,018,810 New Work: Approp. Cost Contributed Funds Approp. Cost New Work: Approp. Cost Maint: Approp. Cost New Work: Approp. Cost Contributed Funds Approp. Cost New Work: Approp. Cost Maint: Approp. Cost Contributed Funds Approp. Cost New Work: Approp. Cost Contributed Funds Approp. Cost New Work: Approp. Cost New Work: Approp. Cost New Work: Approp. Cost New Work: Approp. Cost 1,100,000 8,403,736 883,485 8,145,286 391 249,361 981 244,160 2,499,000 1,960,000 2,500,000 5,313,000 2,305,398 491,088 1,590,361 6,404,697 1,788,000 3,953,837 3,173,000 2,681,500 1,632,312 2,703,132 4,451,959 2,724,425 - 1,532,500 - 395,229 221,989 408,352 820,558 593,869 106,195,200 104,692,0658 19,330,038 19,162,810 2,162,841 1,809,656 5,060,000 1,253,000 1,750,000 820,000 48,770,000 4,664,103 1,124,975 2,149,558 895,506 48,717,447 - - - 83,300 - - - 83,300 50,000 150,000 150,000 41,217 153,304 134,787 - 281,000 209 172,217 106,759 200,000 187,644 150,000 138,466 60,000 80,692 90,000 48,410 200,000 187,644 150,000 138,466 520,933 520,933 1,440,000 1,394,900 1. Includes $25,000 Emergency Relief Funds. 2. Includes $4,143,282 for Operating and Care under the "Permanent Indefinite Appropriation." 3. Includes $2,569,102 for previous projects. 4. Includes $1,028,468 for previous projects. 5. Includes $85 for previous project. 6. Includes cost of Mehaffey Bridge, $1,365,074 (excluding $100,000 contributed funds). 7. Excludes $161,813 contributed funds. 8. Excludes $950,000 non-Federal cost. 28-9 475,000 1,309,129 104,200 117,606 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 28-B AUTHORIZING LEGISLATION See Date Section Authorizing in Text Act Project and Work Authorized Documents 2. January 21, 1927 July 3, 1930 June 26, 19341 August 30, 1935 August 30, 19353 June 14, 1937 June 20, 1938 October 23, 1943 March 2, 1945 Rivers and Harbors " Committee Doc. 69th Cong., 1st sess., and S. Doc. 130, 69th Cong., 1st sess. S. Doc. 126, 71st Cong., 2nd sess. ILLINOIS WATERWAY, IL AND IN Channel 9 feet deep and 200 feet wide from mouth of Illinois River to Utica, 231 miles, modification of 2 U.S. locks and dams, removal of 2 State dams. (Act authorized appropriation of not to exceed $3,500,000 for carrying on work.) Channel 9 feet deep from Utica, IL, to heads of present Federal projects on Chicago and Calumet Rivers 94.6 miles to Lake Street, and 96.3 miles to turning basin 5, respectively, to be secured by means of completed dams, locks, lateral canals, and dredging begun by State of Illinois in general accordance with present plans of State for that work. Act adopting project authorized appropriation of not to exceed $7,500,000 for carrying on work. Operation and care of locks and dams provided for with funds from War Department appropriation for rivers and harbors. Construct modern locks and dams at LaGrange and Peoria and a channel 9 feet deep and 300 feet wide below Lockport, exact location and details of design of all structures to be left to discretion of Chief of Engineers, and, for time being, that no change be made in water authorized for navigation of Illinois River by act of July 3, 1930. Also provides for 3 passing places along Sag Channel and authorized channel in Calumet-Sag route to turning basin 5, and dredging at entrance of Lake Calumet. Realign portion of Calumet River and abandonment of bypassed section of Calumet River. Modifies local cooperation requirements in 1935 act. Pay damages to levee and drainage districts due to seepage and other factors, not to exceed $503,500. Enlarge Calumet-Sag Channel to 160 feet wide and a usable depth of 9 feet. Dredge a barge channel 160 feet wide with a usable depth of 9 feet in Grand Calumet and Little Calumet River Branch of Indiana Harbor Canal to deep (lake) draft through 141st St., East Chicago, IN. Construct in Little Calumet River a lock of suitable dimensions for large navigation. Rebuild or otherwise alter at Federal expense all obstructive railroad bridges across Calumet-Sag Channel, Little Calumet River, Calumet River, Grand Calumet River, and Indiana Harbor Canal, so as to provide suitable clearance, except that no Federal funds shall be expended for removal or alteration of Illinois Central RR. bridge at mile 11.20 of Little Calumet River. 28-10 H. Doc. 184, 73rd Cong., 2nd sess.2 H. Doc. 180, 73rd Cong., 2nd sess. Rivers and Harbors Committee Doc. 19, 75th Cong., 1st sess. H. Doc. 711, 77th Cong., 2nd sess. H. Doc. 145, 76th Cong., 1st sess. ROCK ISLAND, IL, DISTRICT TABLE 28-B (Continued) AUTHORIZING LEGISLATION See Date Section Authorizing in Text Act Project and Work Authorized Documents July 24, 1946 July 24, 1946 July 17, 1953 July 3, 1958 August 18, 1968 0 3. July 3, 1930 0 5. July 14, 1960 (Section 107) 6. August 15, 1985 (P.L. 99-88) Substitute following work for that authorized by act of March 2, 1945; replace emergency dam in Chicago Sanitary and Ship Canal; enlargement of that canal thence to Sag Junction and of Calumet-Sag Channel to afford channels 225 feet wide and usable depth of 9 feet; construct along general route depth of 9 feet to 225 feet wide between Little Calumet River and junction with Indiana Harbor Canal and 160 feet wide thence to Clark St., Gary, IN, with a turning basin at Clark St., enlarge Indiana Harbor Canal to 225 feet wide and usable depth of 9 feet between Grand Calumet River and vicinity of 141st St., inclusive; remove Blue Island lock and construct a lock and control works in Calumet River near its head, and similar structures in proposed Grand Calumet Channel west of Indiana Harbor Canal; alter or eliminate railroad bridges across three channels lakeward of Chicago Sanitary and Ship Canal, or construct new railroad bridges to provide suitable clearance. A small-boat harbor in vicinity of Peoria, IL, by construction of a basin 510 by 250 feet, dredged to 7 feet deep. $48,933 to reimburse Nutwood Drainage and Levee District for additional pumping operation; supplementing $58,750 authorized in October 1943 act. Federal participation in alteration of highway bridges, Calumet-Sag Modification, Part I, which constitute unreasonable obstructions to navigation, in accordance with Public Law 647, 76th Cong., as amended. Federal participation in .alteration of highway bridges, Calumet-Sag Modification, Part II, which constitute unreasonable obstructions to navigation, in accordance with Public Law 647, 76th Cong., as amended. MILL CREEK AND SOUTH SLOUGH AT MILAN, IL Channel diversion, floodgates, and other work for flood protection. MUSCOOTEN BAY, ILLINOIS RIVER, IL Rock dike and dredging for navigation. UPPER MISSISSIPPI RIVER ENVIRONMENTAL MANAGEMENT PROGRAM, IL, IA, MN, MO, WI Provide for a 10-year environmental program to include habitat rehabilitation and enhancement; longterm resource monitoring with computerized inventory and analysis; recreational development; assessment of economic benefits from recreational activities; and navigation system traffic monitoring. H. Doc. 677, 79th Cong., 2nd sess. H. Doc. 698, 79th Cong., 2nd sess. H. Doc. 144, 81st Cong., 1st sess. H. Doc. 45, 85th Cong., 1st sess. 4 Specified in Act. Also H. Doc. 45, 85th Cong., 1st sess. Rivers and Harbors Committee Doc. 19, 71st Cong., 2nd sess. None H. Doc. 2577, 99th Cong., 1st sess. 28-11 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 28-B (Continued) AUTHORIZING LEGISLATION See Date Section Authorizing in Text Act Project and Work Authorized Documents 8. October 27, 1965 (P.L. 89-298) 9. August 13, 1968 10. June 28, 1938 July 14, 1960 11. December 31, 1970 12. August 15, 1985 (P.L. 99-88) 13. 1944 Flood Control Act 14. August 13, 1968 15. June 28, 1938 16. October 23, 1962 17. July 3, 1958 October 22, 1976 18. October 27, 1965 AMES DAM AND RESERVOIR, SKUNK RIVER, IA Reservoir for flood control, water quality control, recreation, and fish and wildlife. BETTENDORF, IA Levees, railroad raises, closure structures, and street raises and ramps for flood control. CORALVILLE LAKE, IA Reservoir for flood control and recreation. Highway bridge across Coralville Lake at or near the Mehaffey site. DAVENPORT, IA Levee, floodwall, and pumping plants. DES MOINES RECREATIONAL RIVER AND GREENBELT, IA Recreational development; environmental enhancement; and related streambank stabilization. FARM CREEK, IL Two flood detention dams and channel improvements. MILAN, IL Levee closure structures, gravity drainage outlets, ditches, ponding areas, and pumping plants for flood control. RED ROCK DAM AND LAKE RED ROCK, IA Reservoir for flood control and recreation. ROCKFORD, IL Channel enlargement and realignment, levees, and appurtenant works for flood control. SAYLORVILLE LAKE, IA Reservoir for flood control and recreation. Modification to minimize adverse project impact on Ledges State Park. WATERLOO, IA Levees, floodwalls, pumping plants, and closure structures for flood control. H. Doc. 267, 89th Cong., 1st sess. H. Doc. 348, 89th Cong., 2nd sess. Flood Control Committee Doc. 1, 75th Cong., 1st sess. None H. Doc. 161, 92nd Cong., 1st sess. H. Doc. 2577, 99th Cong., 1st sess. H. Doc. 802, 78th Cong., 2nd sess. H. Doc., 348, 90th Cong., 2nd sess. Flood Control Committee Doc. 1, 75th Cong., 1st sess. S. Doc. 142, 87th Cong., 2nd sess. S. Doc. 9, 85th Cong., 1st sess. H. Doc. 487, 94th Cong., 2nd sess. H. Doc. 166, 89th Cong., 1st sess. 28-12 ROCK ISLAND, IL, DISTRICT TABLE 28-B (Continued) AUTHORIZING LEGISLATION See Date Section Authorizing in Text Act Project and Work Authorized Documents HANNIBAL, MO 25. October 23, 1962 Levee, floodwall, closure structures, and pumping H. Doc. 564, 87th Cong., plant for flood control. 2nd sess. MOLINE, IL October 27, 1965 Levee, closure structures, and interior drainage H. Doc. 161, 92nd Cong., (Section 201) facilities for flood control, and aesthetic and 1st sess. Approved by recreational development. Committees on Public Works of House of Representatives and Senate, June 14, 1972, and June 21, 1972, respectively. 1. Permanent Appropriations Repeal Act. 3. Included, in part, in Public Works Administration Program 2. Contains latest published map of Illinois and Des Plaines October 31, 1934, and February 28, 1935. Rivers. 4. Contains latest published maps of Calumet-Sag portion. TABLE 28-C OTHER AUTHORIZED NAVIGATION (See Section 7 of Text) PROJECTS For Last Cost To September 30, 1985 Full Report See Annual Operation and Project Status Report For Construction Maintenance Squaw Chute at Quincy, IL Completed 1967 70,9791 9,345 Quincy, IL, Harbor Access Channel Completed 1970 35,4772 37,700 1. Excludes $25,851 contributed funds. 2. Excludes $35,350 contributed funds. 28-13 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 28-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS (See Section 20 of Text) Cost To September 30, 1985 For Last Full Report Operation Contributed See Annual and Funds Project Report For Construction Maintenance Expended Completed Projects Banner Special Drainage and Levee Districts, IL 1943 274,822 - - Bear Creek Dam (City of Hannibal, MO) 1962 1,679,056 - - Big Lake Drainage and Levee District, IL 1943 144,910 - - Canton, MO' 1964 1,496,555 - - Clinton, IA 1981 26,001,996 - 761,050 Coal Creek Drainage and Levee District, IL 1954 1,923,145 - - Crane Creek Drainage and Levee District, IL 1941 68,898 - - Des Moines and Mississippi Levee District No. 1, MO 1969 1,492,016 - - Des Moines, IA 1972 4,993,224 - 23,323 Drury Drainage District, IL 1964 1,144,875 - - Dubuque, IA 1974 10,861,170 - 145,415 East Liverpool Drainage and Levee District, IL 1941 207,826 - - East Moline, IL 1984 9,683,300 - - East Peoria Drainage and Levee District, IL 1946 279,963 - - Elkport, IA 1951 34,200 - - Evansdale, IA 1983 4,409,088 - - Fabius River Drainage District, MO 1941 60,500 - - Fabius River Drainage District, MO 1963 1,621,841 - - Farmers Levee and Drainage District, IL 1942 155,562 - - Fulton, IL 1984 18,017,200 - - Galena, IL 1952 844,100 - 118,000 Green Bay Levee and Drainage District No. 2, IA 1949 299,000 - - Green Bay Levee and Drainage District No. 2, IA 1967 1,727,711 - - Gregory Drainage District, MO 1940 77,100 - - Gregory Drainage District, MO 1972 1,538,963 - 20,626 Henderson County Drainage District No. 1, IL 1968 1,453,217 - - Henderson County Drainage District No. 2, IL 1968 1,043,902 - - Henderson County Drainage District No. 3, IL 1949 42,700 - - Hennepin Drainage and Levee District, IL 1940 109,593 - - Hunt Drainage District and Lima Lake Drainage District, IL 1972 4,772,498 - - Indian Grave Drainage District, IL 1972 3,551,961 - - Iowa River-Flint Creek Levee District No. 16, IA 1972 6,044,693 - - Kishwaukee River at DeKalb, IL' 1957 123,300 - - Lacey Langellier, West Mantanzas and Kerton Valley Drainage and Levee District, IL 1954 1,290,000 - - Liverpool Drainage and Levee District, IL 1943 117,731 - - Lost Creek Drainage and Levee District, IL 1938 152,000 - - Marengo, IA' 1981 2,447,001 - - Marion County Drainage District, MO 1967 873,748 - - Marshalltown, IA 1978 8,437,511 - 252,136 Mason and Menard Drainage District, IL 1940 93,808 - - Meredosia Levee and Drainage District, IL 1977 1,995,322 - 269,739 Muscatine, Mad Creek, IA' 1983 1,129,800 - - Muscatine Island Levee District and Muscatine- Louisa County Drainage District No. 13, IA 1970 3,293,276 - 220,000 Near Springfield on Sangamon River, IL 1941 - - - Oakford Special Drainage District, IL 1940 38,417 - - Okabena Creek at Worthington, MN' 1957 72,432 - 28-14 ROCK ISLAND, IL, DISTRICT TABLE 28-E (Continued) OTHER AUTHORIZED FLOOD CONTROL PROJECTS (See Section 20 of Text) Cost To September 30, 1985 For Last Full Report Operation Contributed See Annual and Funds Project Report For Construction Maintenance Expended Ottumwa, IA 1977 233,145 -- Pekin and La Marsh Drainage and Levee District, IL 1955 158,383 - - Penny Slough, Rock River, IL 1940 85,800 - - Rock Island, IL 1979 7,582,373 - - Rocky Ford Drainage and Levee District, IL 1941 108,797 - - Sabula, IA 1958 411,915 - - Sangamon River (Mouth), IL 1980 1,048,990 272,848 15,122 Seahorn Drainage and Levee District, IL 1945 32,281 - - Sid Simpson Project, IL 1968 5,789,800 - - Sny Basin, IL 1972 14,003,560 - - Sny Island Levee Drainage District, IL 1942 61,400 - - Sny Island Levee Drainage District, IL 1968 4,956,749 - - South Beardstown and Valley Drainage and Levee District, IL 1942 220,729 - - South Beardstown Drainage and Levee District, IL 1942 171,839 - - South Quincy Drainage and Levee District, IL 1940 61,200 - - South Quincy Drainage and Levee District, IL 1968 1,231,243 - - South River Drainage District, MO 1941 55,300 - - South River Drainage District, MO 1966 1,106,056 - - Spring Lake Drainage and Levee District, IL 1941 185,980 - - Subdistrict No. 1 of Drainage Union No. 1 and Bay Island Drainage and Levee District No. 1, IL 1967 3,306,695 - - Union Township Drainage District, MO 1947 116,576 - - Van Meter, IA' 1965 113,842 - - Authorized Projects Not Constructed Farmers Levee and Drainage District, IL - - - - Freeport, IL 1979 286,000 - - Peoria, IL 1973 534,580 - - Rock River Agricultural Levees, IL 1984 858,000 - - South Beloit, IL 1979 270,000 - - William L. Springer Lake, IL 1979 4,911,310 - - 1. Authorized by Chief of Engineers (Sec. 205, 1948 Flood Control Act). 28-15 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 28-G DEAUTHORIZED PROJECTS For Last Full Report Federal Contributed See Annual Date Funds Funds Project Report For Deauthorized Expended Expended Campbells Island Mississippi River, IL 1969 1979 $ 76,664- Carroll County Levee and Drainage District, IL 1938 1977 - - Central City Lake, Wapsipinicon River, IA 1970 1977 55,664 - Green Island Levee and Drainage District, IA 1938 1977 -- Henderson River, IL 1964 1977 102,310 - Illinois Waterway, IL and IN Duplicate Locks 1982 1981 - - Janesville and Indian Ford Dams, WI 1938 1977 - - Keithsburg Drainage District, IL 1938 1977 - - Pecatonica River at Darlington, WI - 1977 - - Rochester Lake, Cedar River, IA - 1977 - - TABLE 28-H INSPECTION OF COMPLETED FLOOD CONTROL PROJECTS (See Section 19 of Text) Date Project Inspected Alpine Dam and Page Park Dam, Rockford, IL Banner Special Drainage and Levee District, IL Bear Creek Reservoir, Hannibal, MO Big Lake Drainage and Levee District, IL Canton, MO Clinton, IA Coal Creek Drainage and Levee District, IL Crane Creek Drainage and Levee District, IL DeKalb, IL Des Moines, IA Des Moines and Mississippi Levee District No. 1, MO Drury Drainage District, IL Dubuque, IA East Liverpool Drainage and Levee District, IL East Moline, IL East Peoria Drainage and Levee District, IL East Peoria Sanitary District, IL Elkport, IA Evansdale, IA Fabius River Drainage District, MO Farmers Drainage and Levee District, IL Fulton, IL October 1984 November 1984 December 1984 November 1984 November 1984 October 1984 November 1984 November 1984 October 1984 November 1984 November 1984 October 1984 October 1984 November 1984 December 1984 November 1984 December 1984 September 1985 November 1984 December 1984 November 1984 September 1985 28-16 ROCK ISLAND, IL, DISTRICT TABLE 28-H (Continued) Project INSPECTION OF COMPLETED FLOOD CONTROL PROJECTS (See Section 19 of Text) Date Inspected Galena, IL Green Bay Levee and Drainage District, No. 2, IA Gregory Drainage District, MO Henderson County Drainage District No. 1, IL Henderson County Drainage District No. 2, IL Hennepin Drainage and Levee District, IL Hergot Drainage and Levee District, IL Hunt Drainage District & Lima Lake Drainage District, IL Indian Grave Drainage District, IL Iowa River-Flint Creek Levee District No. 16, IA Kerton Valley Drainage and Levee District, IL Lacey Drainage and Levee District, IL Langellier Drainage and Levee District, IL Liverpool Drainage and Levee District, IL Lost Creek Drainage and Levee District, IL Mad Creek, Muscatine, IA Marengo, IA Mason and Menard Drainage District, IL Marion County Drainage District, MO Marshalltown, IA Meredosia Levee and Drainage District, IL Milan, IL1 Muscatine Island, L&DD, & Louisa DD No. 13, IA Oakford Special Drainage and Levee District, IL Pekin-La Marsh Drainage and Levee District, IL Penny Slough Drainage and Levee District, IL Rock Island, IL Sabula, IA Sanitary District of Beardstown, IL Seahorn Drainage and Levee District, IL Sny Island Levee Drainage District, IL South Beardstown Drainage and Levee District, IL South Quincy Drainage and Levee District, IL South River Drainage District, MO Spring Lake Drainage and Levee District, IL Subdistrict No. 1 of Drainage Union No. 1, and Bay Island Levee and Drainage District No. 1, IL The Sny Basin, IL Valley Drainage and Levee District, IL Van Meter, IA Volga, IA Waterloo, IA' West Matanzas Drainage and Levee District, IL Worthington, MN October 1984 October 1984 November 1984 November 1984 November 1984 November 1984 November 1984 December 1984 December 1984 November 1984 December 1984 December 1984 December 1984 December 1984 November 1984 October 1984 November 1984 November 1984 December 1984 October 1984 December 1984 December 1984 October 1984 November 1984 December 1984 October 1984 December 1984 September 1985 October 1984 November 1984 December 1984 November 1984 December 1984 December 1984 December 1984 October 1984 May 1984 November 1984 October 1984 September 1985 November 1984 December 1984 October 1984 1. Project partially completed. 28-17 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 28-I FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION Flood Control Activities Pursuant to Section 205, Public Law 858, 80th Congress, as Amended (Preauthorization) (See Section 21 of Text) Study Identification Fiscal Year Costs Burlington, IA Cedar River, Waverly, IA Couler Valley, Dubuque County, IA Decatur, IL DeKalb, IL Des Moines River, East Fork, IA Des Moines River, West Fork, Palo Alto County, IA Illinois River, Liverpool, IL Illinois River, Pekin, IL Iroquois River, Sugar Creek, Watseka, IL Morton, IL North River, Marion County, MO Oelwein, Fayette County, IA Ottawa High School, IL Ottawa, IL Panther Creek, Sangamon River, Chandlerville, IL Plainfield, IA Raccoon River, Des Moines, IA Tama, IA Vermilion River, Pontiac, IL $ -8,231 40,143 44,590 42,915 67,466 7,500 7,500 81,892 22,876 52,159 39,583 1,240 16,152 7,500 67,446 41,615 32,013 56,698 47,957 12,810 TABLE 28-I Snagging and Clearing Navigable Streams and Tributaries in the Interest of Flood Control (Preauthorization) (Section 208, 1954 Flood Control Act, Public Law 780, 83rd Congress) Project and Location Fiscal Year Costs Des Moines River, East Branch, Kossuth County, IA $ 4,019 Little Volga River, Maynard, IA 3,550 Rails County, MO 7,100 Stark County, IL 7,500 Steward Creek, Steward, IL 7,500 TABLE 28-I Emergency Bank Protection (Section 14 of the 1946 Flood Control Act, Public Law 526, 79th Congress) Project and Location Fiscal Year Costs County Road, Mahaska County, IA $ 3,323 County Road 90, Knox County, MO 31,585 Des Moines River, Boone, IA 22,921 Des Moines River, Eldon, IA 24,466 Illinois River, Riverside Park, Havana, IL 7,500 McLean County, IL 6,100 North Fabius River, Lewis County, MO 34,356 North River, Marion County Road 152, MO 7,229 28-18 ROCK ISLAND, IL, DISTRICT FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION Emergency Flood Control Activities - Repair, Flood Fighting, and Rescue Work (Public Law 99, 84th Congress and Antecedent Legislation) (See Section 21 of Text) Project and Location Federal Cost Advance Preparation Emergency Operations Rehabilitation: Barrett-Swain, IL Below London Mills-Parker, IL Big Lake DD, Illinois River, IL Blackburn Levee, IL Blout-Lundry Levee, IL Cullinane-Zempel-Evans, IL David Winters, Sugar River, IL Dickson, IL Dobey Levee, IL Erie Township Levee, IL Ermeling-Strode, IL Formhals Levee, IL Globe, IL Green Island Levee and Drainage District 1, IA Hager Slough, IL Hennepin Levee, Illinois River, IL Herman, IL Ingersol, IL Irvin-Blackburn Levee, IL LL WM & KV Drainage and Levee, IL Louisa County Levee District 8, Iowa River, IA Lower Pleasant Valley Levee, IL Miscellaneous Invest FY 85, IL Old Canal Levee-Des Moines River, Lee, IA St. Francisville Levee, MO Stevenson, IL Zempel-Mutual, IL 28-19 TABLE 28-I (Continued) $ 183,513 91,830 42,261 30,310 37,649 21,620 14,388 3,064 16,323 16,774 37,472 17,068 31,791 89,285 67,325 70,000 14,447 10,994 35,472 18,370 15,017 10,323 81,193 28,884 29,443 55,262 49,601 19,987 67,297 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 28-J ILLINOIS WATERWAY: EXISTING LOCKS AND DAMS (See Section 2 of Text) Depth on Dimensions Miter Sills at Low Water Available Lift at Miles Width of Length for Low Above Chamber Full Width Water' Lower Upper Lock Mouth Miles to Nearest Town (feet) (feet) (feet) (feet) (feet) LaGrange Lock 80.2 7.8 below Beardstown, IL 110 600 10.0 13.0 15.5 Peoria Lock 157.7 4.1 below Peoria, IL 110 600 11.0 12.0 15.5 Starved Rock Lock 231.0 Utica, IL 110 600 18.5 14.0 16.8 Marseilles Lock 244.6 Marseilles, IL 110 600 24.45 14.0 18.6 Dresden Island Lock 271.5 8 above Morris, IL 110 600 21.75 12.25 16.85 Brandon Road Lock 286.0 Joliet, IL 110 600 34.0 13.8 17.85 Lockport Lock 291.1 Lockport, IL 110 600 30.5-39.52 15.0 11.0-20.02 T.J. O'Brien Lock 326.5 Chicago, IL 110 1,000 - 14.0 14.0 1. Lifts and depth on miter sills are those obtained with flat 2. Variation in lift and depth on upper miter sill at Lockport pools. is due to fluctuation of water surface in the sanitary district canal. TABLE 28-K ILLINOIS WATERWAY, IL AND IN LOCK AND DAM CONSTRUCTION, FOUNDATIONS, COST (See Section 2 of Text) Lock Dam Estimated Federal Cost Under Type of Character of Type of Character of Year Existing Name Construction Foundation Kind Construction Foundation Complete Project Illinois River, mouth to Utica; channel improvement by dredging in Illinois River below Starved Rock modification of two U.S. locks and dams, and removal of two State dams. LaGrange Peoria Starved Rock Marseilles Concrete Piles in sand Concrete Piles in sand Concrete Rock Concrete Rock $ 2,733,4991 Movable (wicket with Aframe- crest) Movable (wicket type) Movable (tainter gates) Movable (tainter gates) Concrete and timber Concrete and timber Concrete and structural steel Concrete and structural steel Piles in sand Piles in sand Rock Rock 1939 1939 1933 1933 2,744,5921 3,381,0301 885,3151 1,853,7251 28-20 ROCK ISLAND, IL, DISTRICT TABLE 28-K (Continued) ILLINOIS WATERWAY, IL AND IN LOCK AND DAM CONSTRUCTION, FOUNDATIONS, COST (See Section 2 of Text) Lock Dam Estimated Federal Cost Under Type of Character of Type of Character of Year Existing Name Construction Foundation Kind Construction Foundation Complete Project Dresden Island Concrete Rock Movable Concrete Rock 1933 $ 2,503,3761 (tainter and gates) structural steel Brandon Road Concrete Rock Movable Concrete Rock 1933 2,031,6831 (tainter and gates) structural steel Lockport Concrete Rock Movable Concrete Rock 1933 133,6081 (Bear trap) and structural steel T.J. O'Brien Concrete Piles in clay Fixed Concrete Piles in clay 1960 6,954,7001 and sheet and sheet piling piling Lock and dam - - - - - - 1,250,3041 equipment Total locks - - - - - - $ 24,471,832 and dams 1. Actual cost. TABLE 28-L ILLINOIS WATERWAY, IL AND IN ADDITIONAL FEATURES ENTERING INTO COST (See Section 2 of Text) Dredging: Little Calumet and Calumet Rivers $ 2,135,3581 Calumet-Sag, 3 passing places 813,4181 Starved Rock to Lockport 3,650,635 Starved Rock to Grafton 2,686,307 Calumet-Sag Channel 19,238,200 Peoria small boat harbor 24,9371 Protection piers at all locks 77,6131 Calumet-Sag modification engineering and design 5,141,474 Calumet-Sag modification, supervision and administration 5,466,804 Rebuild highway bridges 19,327,850 Rebuild railway bridges: Calumet-Sag Channel 20,828,4351 Little Calumet and Calumet Rivers 18,362,0411 Recreation Facilities, Code 711 445,000 Removal of Blue Island lock 288,6001 Grand Calumet River controlling works St. Louis District 1,081,6001 Total additional features $ 99,569,604 Total existing project $124,041,436 1. Actual cost. 2. Placed in inactive status November 19, 1974. 28-21 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 28-M EXISTING PROJECT See Section in Text Project Item Length (feet) Width (feet) Depth (feet) 1. Illinois Waterway, Nine locks and six dams - - IL and IN Grafton to Lockport, IL 291.1 miles 300 9 Lockport to controlling works 2.0 miles 200-300 9 Controlling works to junction with 10.0 miles 225 9 Calumet-Sag Channel Calumet-Sag Channel to lock in Blue 16.0 miles 225 9 Island Calumet and Little Calumet Channel, 7.7 miles 300 9 from Blue Island to turning basin 5 Grand Calumet River Channel from 9.0 miles 9 - junction with Little Calumet River to and in Indiana Harbor Canal to 141st, East Chicago, IN Also, Grand Calumet River Channel 4.2 miles 160 9 from junction of Indiana Harbor Canal and Grand Calumet River to Clark St. in Gary, IN, with a turning basin at Clark St. A channel in Chicago Sanitary and 22.1 miles 175-300 9 Ship Canal and South Branch Chicago River from Sag-Junction to Lake St. in Chicago, IL TABLE 28-N ILLINOIS WATERWAY, IL AND IN TOTAL COST OF EXISTING PROJECT TO SEPTEMBER 30, 1985 (See Section 2 of Text) New Work Maintenance Rehabilitation Total Regular Funds $118,317,646 $210,486,538 $56,327,255 $385,131,439 Public Works Funds 3,960,735 - - 3,960,735 Emergency Relief Funds 1,858,936 - - 1,858,936 Total $124,137,317 $210,486,538 $56,327,235 $390,951,110 1. Includes $1,735,890 expended between 1927 and 1936 on the operation and care of the works of improvement under the provisions of the permanent indefinite appropriation for such purposes. 28-22 MISSISSIPPI RIVER BETWEEN MISSOURI RIVER AND MINNEAPOLIS, MN Section of river covered in this report is divided into three reaches, under supervision and direction of District Engineers at St. Louis, Rock Island, and St. Paul. Section in St. Louis District extends 105 miles from Mouth of Missouri River to Upper Mississippi River mile 300 above Location. Mississippi River rises in northern part of Minnesota, flows about 2,360 miles southerly and empties into Gulf of Mexico. Portion included in this report extends about 663 miles from mouth of Missouri River to Soo Line Railroad bridge, Minneapolis. Latest map and profile showing this section of river is in House Document 669, 76th Congress, 3d session. A map showing Lake Pepin is in House Document 511, 79th Congress, 2d session. A map of section Minneapolis to Dubuque is in House Document 515, 79th Congress, 2d session. A map showing location of drainage districts (Bellevue, Iowa, to Missouri River) is in River and Harbors Committee Document 34, 75th Congress, 1st session. Previous projects. See page 1199 of Annual Report for 1963. Existing project. Provides for a channel of 9-foot depth and adequate width between mouth of Missouri river (1,179 miles from the gulf) and Soo Line Railroad at Minneapolis, by construction of a system of locks and dams, supplemented by dredging. Project also provides for further improvements at St. Paul to provide a basin extending downstream from Robert Street Bridge of 2.7 miles, and at Minneapolis to provide adequate terminal facilities, and for other harbor improvements and miscellaneous work. Pertinent data on locks and dams, harbor improvements, additional features entering into cost of project, and authorizing legislation are given in Tables 29-C, 29-D, 29- E and 29-G. All dams are concrete. Three dams (Upper St. Anthony Falls, 1 and 19) are fixed, remainder are movable. Estimated cost for new work (1982) is $894,157,300 exclusive of amounts expended on previous projects. See House document 669, 76th Congress, 3d session, for a report of Chief of Engineers dated February 27, 1940, containing a general plan for improvement of Mississippi River between Coon Rapids Dam and mouth of Ohio River for purposes of navigation, power development, flood control, and irrigation needs. Local cooperation. Small-boat harbors authorized in the River and Harbor Act of 1962 are subject to conditions that local interests make a cash contribution toward cost of construction (except in case of Quincy Harbor which involves maintenance only of an existing harbor); furnish lands and rights-of-way for construction and future maintenance; hold the United States free from damages; provide and maintain mooring facilities and utilities; reserve accommodations for transient small boats; accomplish all necessary relocations and alterations; and establish public Ohio River; Rock Island District extends about 314 miles from mile 300 to 614; and St. Paul District ex "nds about 244 miles from mile 614 to Soo Line Railroad bridge, Minneapolis (mile 857.6). bodies empowered to regulate use, growth and development of the harbors. Rectification of seepage damages to privately owned lands in the Sny Island Levee Drainage District, IL, is subject to the conditions that local interests acquire all lands, easements, and rights-of-way necessary for construction and maintenance of the project; comply with applicable provisions of the Uniform Relocation Assistance and Real Property Acquisition Policies Act of 1970; accept, operate, and maintain the project upon its completion; and hold and save the United States free from damages arising from the construction and operation of the completed project; provided further that the local public entity shall be reimbursed by the Government in the amounts actually expended by it in the acquisition of real estate and for payments required under Public Law 91-646 if said amounts have been previously submitted to and approved by the Government. Local cooperation requirements for improvement of commercial harbor at Dubuque, IA; for improvement of Beaver Slough at Clinton, IA, for navigation; and for general navigation facilities at small-boat harbors at Rock Island, IL; Hannibal, MO; Fort Madison, IA, Davenport (Lindsay Park); IA; Muscatine, IA (including freight terminal approach channel); Andalusia, IL; Warsaw, IL; Moline, IL; Clinton, IA; and Savanna, IL, have been complied with. Licenses. Federal Energy Regulatory Commission collects from non-Federal licensees annually to recompensate the United States for use of government dams for generation of hydroelectric power. Amounts collected are returned to U.S. Treasury. (See table at end of chapter for license fees collected through the end of the fiscal year.) Operations during fiscal year. St. Paul District. New Work: Under Section 107 authority, initial appraisals were completed at Guttenberg, Iowa and Maiden Rock, Wisconsin at a cost of $7,500 each. Studies were continued under Section 107, small navigation project authority, for establishment of a small-boat harbor at Pike Island, Minnesota at a cost of $1,000. Construction of the Lake City small-boat harbor was completed and final adjustment in cost was made for -$30,244. In addition, $37,903 was expended from funds contributed by Lake City. Maintenance: Channel dredging to remove shoal areas was performed. Government pipeline dredge WILLIAM 29-1 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 A. THOMPSON removed 877,044 cubic yards of material at 13 locations at a cost of $2,060,644. Government derrick barge HAUSER removed 60,863 cubic yards of material at 3 locations for $362,279. Mechanical dredging contract costs were $1,109,831. Contracts for dredging and material removal at Reads Landing, for dredged material removal at Wilds Bend and for the Lansing wing dam modification cost $1,436,279, $1,329 and $65,010, respectively. Culvert construction at Blackhawk Park by hired labor cost $254,926. Hydrographic and miscellaneous surveys cost $574,465. Other dredging and snagging cost $75,479. Water quality testing and environmental evaluations for dredging cost $94,008. In addition, $764,670 was expended from funds contributed by the City of Winona on a contract for relocating dredged material from an area near Fountain City, Wisconsin, to an area near Winona, Minnesota. Planning, engineering and design work for long term management of dredged material disposal cost $522,600. Supervision and administration of the channel maintenance program cost $284,000. Painting at locks and dams cost $1,096,224. Scour repair contracts at Locks and Dams 2, 3, 5, 5A, 7, 9 and 10 cost $49,999, $129,254, - $31,152, $185,624, $4,608, - $39,120 and $390,464, respectively. Contracts for spillway resurfacing and straightening and painting bulkheads at Lock and Dam No. 10 cost $479,274 and $9,850, respectively. Contracts for spot dike repair at Lock and Dam No. 3, for boundary surveys, for replacing grating at Lock and Dam No. 5A, for general lock maintenance, for construction of a new communications center at Lock and Dam No. 2, for rebuilding esplanade road at Lock and Dam No. 7, modification of incoming power at Lock and Dam No. 5 and grating at Lock and Dam No. 9 cost $40,025, $79,558, $34,938, $11,245, $3,040, $21,000, $10,000, and $14,988, respectively. Engineering work and miscellaneous surveys, reports, and other work were carried on by hired labor for $1,796,675, by contract for $111,554, and by other Corps for $14,434. Contracts and work by other Corps for rehabilitation of auxiliary gates at Locks and Dams 4 and 5 and Lock and Dam 9, construction of loading docks at Locks and Dams 2, 3, 5, 6, 8, and 9 cost $259,995, $160,961, $157,548, $555,561, $164,490, $10,429, $3,941, and $10,598, respectively. Contracts for the installation of high mast lighting at Locks and Dams 2 and 10, replacement of high mast lighting assembly, mechanical and electrical supply at Locks and Dams 2-10, miscellaneous road maintenance, revision of the radio backbone system and equipment replacement cost $13,809, $10,134, $40,363, $63,563, $175,000 and $38,273, respectively. The total cost of maintenance was $15,348,161. Net credits to the project were $26,526, primarily as a result of damages from towboat companies to lock and dam structures. Rehabilitation: Miscellaneous construction was accomplished by contract at a cost of $1,716 and by hired labor at a cost of $74. Engineering and design and supervision and administration cost $7. Total rehabilitation costs were $1,797. Operating and care: Locks and dams were operated as required, and necessary repairs were made to those and appurtenant structures. Other studies, reports, and miscellaneous engineering work were also accomplished. Total cost of operating and care was $8,170,547. Costs to St. Paul District were $14,244 for new work, $23,492,182 for operation and maintenance, and $1,797 for rehabilitation, for a total of $23,479,735. Rock Island District. New Work: Recreational improvements at public use aireas along the Mississippi River cost $155,504. Costs in connection with commercial harbor at Dubuque, IA, were $14,122. Total new work costs were $169,626. Maintenance: Channel dredging by Government cutterhead pipeline Dredge WILLIAM A. THOMPSON was performed at various locations in Pools 12, 14, 16, 17, 18, and 19 at a cost of $951,100 with 355,278 cubic yards of material being removed. Snagging, clearing and excavation was performed by hired labor at various locations at a cost of $151,500. Dredged material disposal activities and other environmental concerns in connection with dredging and channel maintenance activities cost $184,300. Small boat harbor dredging was performed by contract at Rock Island Harbor, IL, Andalusia Harbor, IL, and Fort Madison Harbor, IA, at a cost of $26,100. Repair of channel regulating works structures was performed at a cost of $1,741,400. Structural repairs, including sandblasting and painting were performed by hired labor at locks and dams at a cost of $1,590,600. Contractor earned $131,900 for painting dam roller gates and Lock and Dam 15, and another contractor earned $145,500 for painting dam roller an tainter gates and service bridge at Lock and Dam 17. Installation of bulkhead recesses at Lock and Dam 20 was started by contractor, who earned $50,000. Lock and Dam 18 access road improvements were completed by contract at a cost of $76,400. Contractors earned $134,400 for road surfacing at two free public use areas. Energy rehab of the central control stations at Lock and Dams 11, 12, 13, 16, and 18 was completed by contract at a cost of $709,700, and five radio equipment buildings were completed by contract at a cost of $47,000. Contractor earned $1,035,200 on construction of new crane barge. Maintenance of roads and bridges was performed at a cost of $400, and maintenance of buildings, grounds, and utilities totaled $8,600. Maintenance of public use areas was performed at a cost of $569,800, and maintenance and purchase of permanent operating equipment cost $433,300. Maintenance of levees cost $8,400 and boundary monumentation was performed by contract at a cost of $69,600. Engineering and design work including preparation of design memorandums totaled $952,200. Supervision and administration for the maintenance features cost $428,600. Total maintenance costs were $9,446,000. Net credits to the project were $1,583,700, primarily as a result of collection of damages from towboat companies to lock and dam structures. Operating and care: Operation of the locks and dams and routine maintenance and minor repairs thereto were performed at a cost of $7,322,100. Real estate management services were performed at a cost of $145,100. Natural resource activities cost $156,300, and public use areas were operated at a cost of $921,900, with contract law enforcement provided at a cost of $55,200. Surveys, various condition and operation studies and structural inspections cost $1,210,200. Water control management costs were $829,400; amount of $179,200 was expended on 29-2 MISSISSIPPI RIVER BETWEEN MISSOURI AND MINNEAPOLIS, MN Master Plans; and $37,200 was expended on various investigations and reports. Supervision and administration for operations features cost $241,300. Total operation costs were $11,097,900. Total operation and maintenance costs were $18,960,208. St. Louis District. New work: Costs incurred for new Lock and Dam 26 were $153,383 for real estate acquisition, $252,617 for relocations, $24,302,936 for the dam, $51,351,756 for the lock, $49,340 for channels and canals, $15,413 for levers and floodwalls, $17,741 for permanent operating equipment, $4,732,687 for engineering, and $3,560,709 for supervision and administration. Total cost of new work was $84,436,582. Operating and care: The locks and dams were operated as required, and necessary repairs were made thereto and to appurtenant structures at a cost of $4,056,000. Costs to St. Louis District were $84,436,582 for new work and $10,598,905 for operation and maintenance for a total of $95,035,487. Condition at end of fiscal year: For information pertaining to locks, dams and harbors, see tables at end of chapter. St. Paul district. Work completed: Locks and Dams at St. Anthony Falls and Nos. I to 10, inclusive, except for relatively minor appurtenant work; major improvements of channels and harbors at St. Paul and Minneapolis; commercial harbors at Lake City; Red Wing, and Winona, MN; and Prairie du Chien, WI; small-boat harbors at St. Paul, Hastings, Red Wing, Wabasha, and Winona, MN; Lansing, IA; and Bay City, Pepin, and Prairie du Chien, WI; a remedial drainage ditch at Cochrane, WI; miscellaneous channel dredging and realignment; channel markers; pool clearing; and construction of various facilities for recreation use. Seepage damages totalling $90,027 were paid to 210 claimants. Status of land and flowage acquisition: Approximately 50,293.54 acres of land in fee, including 47,305 acres used by the Department of the Interior in accordance with a cooperative agreement and general plans, and easements of $15,549.63 acres of land are owned or controlled in pools 1 to 10, inclusive, at end of fiscal year. In addition, fee title to 12.46 acres and perpetual easements on 2.98 acres of land for St. Anthony Falls and perpetual easements over 244.39 acres of land for harbors have been obtained and Department of the Army holds special rights over 62,954.74 acres owned by Department of the Interior in pool Nos. 3 to 10, inclusive. Land acquisition is complete. Work remaining to complete portion of project in St. Paul District: Guidewall extension at Lock No. 3 (the uncompleted guidewall extensions at Lock Nos. 4, 5, 5A, 7, 8, 9, and 10 were reclassified from the "active" to the "inactive" category on April 13, 1973); realignment of channel at Wilds Bend; construction of small-boat harbor at St. Paul (Harriet Island), MN; and construction of additional recreational facilities. Condition of channel at end of fiscal year was such that controlling depths of 9 feet at low water and minimum widths for long-haul common carrier service were available in all pools. Structures are in good condition. Rock Island District. Work completed: Major construction items, including all locks and dams, are completed and in operation. The following related work has also been completed: Construction of small-boat harbors at Rock Island, IL; Moline, IL; Andalusia, IL; Warsaw, IL; Fort Madison, IA; Davenport (Lindsay Park), IA; Muscatine, IA; Clinton, IA; and Hannibal, MO; improvement of Beaver Slough at Clinton, IA, for navigation; improvement of commercial harbor at Dubuque, IA; rehabilitation of Locks and Dams 11 through 14; rehabilitation of old auxiliary lock at Lock and Dam 14; permanent closure of old Lock 19 and drydock; rock and conglomerate excavation in Pool 16; rectification of seepage damage in the Sny Island Levee Drainage District, IL; recreational facilities; and construction of visitor center at Lock 15. Work remaining to complete portion of project in Rock Island District: construction of guidewall extension at 16, 18, and 21: mooring facilities at 11, 12, 14, 15, 16, 17, and 18; upper approach improvement at 19 and 20; rock and/or conglomerate excavation in Pools 14, 15, 18, and 21; and construction of small-boat harbors at Keokuk, IA, and New Boston, IL, and commercial harbor at Fort Madison, IA. Planning for the small-boat harbor at Savanna, IL, is currently under way. Small-boat harbors at Bellevue, IA, Cassville, WI, and Davenport (Credit Island), IA, are inactive or have been deauthorized. Status of land and flowage acquisition: Acquisition of land in Pools 11 to 22, inclusive, consisting of 93,601 acres in fee and 10,541 acres in flowage easement, has been completed. Condition of the channel at end of fiscal year, was such that controlling depths of 9 feet at low water and widths suitable for long-haul common carrier service were being maintained in all pools. St. Louis District. Work completed: Locks and Dams Nos. 24, 25, and 26 (Henry T. Rainey Dam), except for guidewall extensions at Locks Nos. 24 and 25, have been completed as have recreation facilities at the three pools. Payments for rectification of damages have been completed. Other work remaining consists of construction guidewall extensions at Locks Nos. 24 and 25. Replacement of Lock and Dam 26 is under construction. Status of land and flowage acquisition: Acquisitions of lands in Pools Nos. 24, 25, and 26, involving 41,448 acres of land in fee and flowage easements over 6,600 acres, is complete. A total of 1,742 acres have been acquired for Lock and Dam No. 26 replacement project. Condition of channel at end of fiscal year was such that controlling depth of nine feet at low water and generally suitable widths for long-haul common carrier services were maintained in all pools and between Locks and Dam, No. 26 and Missouri River. Total Federal cost of existing project to end of fiscal year for the three Districts was $1,130,356,074 of which $468,584,862 was for new work, ($393,838,558 regular funds, $51,895,959 public work funds and $22,850,345 emergency relief funds), $604,239,812 regular funds for maintenance and $57,531,400 regular funds for rehabilitation. 29-3 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 29-A COST AND FINANCIAL STATEMENT Total Cost to Project Funding Fy 82 Fy 83 Fy 84 Fy 85 Sept. 30, 1985 Mississippi River New work' between Missouri River Approp.2 79,335,000 70,105,398 38,441,000 85,052,000 566,861,133 and Minneapolis, Costs 81,990,422 67,081,730 42,157,597 84,591,964 565,469,506 Minnesota (Federal Maint.4 Furids) Approp. 43,504,800 58,960,456 51,692,401 52,296,749 667,203,036 Cost 41,302,359 50,986,450 60,514,185 53,051,295 658,107,408 Rehab. Approp. 8,040,000 0 0 0 57,533,197 Cost 6,927,351 1,214,556 99,623 1,797 57,535,197 (Contribu&d funds) New Work Approp. 0 400,000 512,160 - 99,561 2,041,140 Cost 0 0 774,696 37,903 2,041,140 1. Includes $41,469,956 for new work on previous projects. 2. Includes replacement Lock and Dam 26 funds $338,113,000 appropriation. 3. Includes replacement Lock and Dam 26 funds $336,621,365 cost. 4. Includes $6,554,725 for maintenance on previous project. TOTAL COSTS OF EXISTING PROJECT TABLE 29-B TO SEPTEMBER 30, 1985 Regular Public Work Emergency District Cost Funds Funds Relief Funds Total St. Paul New Work' $ 60,107,2472 $ 24,210,071 $ 9,071,214 $ 93,388,532 Maintenance3 264,598,562- - 264,598,562 Rehabilitation 44,600,000 - - 44,600,000 Total 369,305,809 24,210,071 9,071,214 402,587,094 Rock New Work4 65,247,4665 17,403,322 11,338,865 93,989,653 Island Maintenance6 234,310,633 - - 234,310,633 Rehabilitation 12,933,197- - 12,933,197 Total 312,491,296 17,403,322 11,338,865 341,233,483 St. Louis New Works 365,798,6387 10,282,566 2,440,266 378,521,470 Maintenance 158,381,912 158,381,912 Total 524,180,550 10,282,566 2,440,266 536,903,382 1. Excludes $2,041,140 contributed funds. Includes $7,673 expended in pool No. 11. 2. Includes $159,359 transferred from Rock Island District covering pro rata share of cost of derrick boat Hercules. 3. Includes $762,196 expended between 1930 and 1936 on operating and care of works of improvement under provisions of permanent indefinite appropriation for such purposes. Excludes $797,670 contributed funds. 4. Excludes $58,999 contributed funds. 5. $687,709 was transferred to St. Louis District in fiscal year 1958. Excludes $201,167 transferred to St. Paul and St. Louis Districts covering their pro rata share of cost of derrick boat Hercules. 6. Costs subsequent to FY 1953 included with operating and care. Includes the sum of $395,442, expended between 1930 and 1934 on the operating and care of the works of improvement under the provisions of the permanent indefinite appropriation for such purposes. 7. Includes $47,800 transferred from Rock Island District covering pro rata cost of derrick boat Hercules and $687,709 transferred from Rock Island District. 8. Includes $336,621,365 for replacement of Lock and Dam 26. 29-4 TABLE 29-C Miles Above Ohio Miles from Lock and Dam River Nearest Town St. Anthony 853.9 In city of Falls, upper Minneapolis, Lock MN St. Anthony 853.3 In city of Falls, lower Minneapolis, Lock and dam MN Lock and dam 847.6 Minneapolis- I St. Paul Lock and dam 815.2 1.3 above 2 Hastings, MN Lock and dam 796.9 6.1 above Red 3 Wing, MN Lock and dam 752.8 Alma, WI 4 Lock and dam 738.1 Minneiska, MN 5 Lock and dam 728.5 3 above 5A Winona, MN Lock and dam 714.3 Trempealeau, 6 WI Lock and dam 702.5 Dresbach, MN 7 Lock and dam 679.2 Genoa, WI 8 Lock and dam 647.9 3.3 below 9 Lynxville, WI Lock and dam 615.1 Guttenberg, IA 10 Lock and dam 583.0 3.7 above 11 Dubuque, IA Lock and dam 556.7 Bellevue, IA 12 Lock and dam 522.5 4.3 above 13 Clinton, IA Lock and dam 493.3 3.7 below 14 Le Claire, IA Le Claire lock 493.1 3.9 below (Canal) Le Claire, IA Lock and dam 482.9 Foot of Arsenal 15 Island Rock Island, IL Lock and dam 457.2 1.8 above 16 Muscatine, IA LOCKS AND DAMS Lock Dimensions Greatest Depth on Character of Foundation Percent Width Lenth Upper Miter Sill Complete of Av'lble Normal Locs, Year Estimated Cost of Chain- for Full Pool Dams, and Opened Each Lock and ber Width Lift Eleva- Upper Lower Work in to Navi- Dam Including (feet) (feet) (feet) tion' (feet) (feet) Lock Dam Pool gation Work in Pool 56 400 49.2 799.2 56 400 26.94 750.0 56 56 110 1109 110 110 110 110 110 400 400 500 6008 600 600 600 600 600 35.94 725.1 35.9 - 12.2 - 12.2 687.2 8.0 675.0 7.0 667.0 9.0 660.0 .5.5 651.0 6.5 645.5 110 600 8.0 639.0 110 600 11.0 631.0 110 110 110 600 600 600 9.0 620.0 8.0 611.0 11.0 603.0 110 600 9.0 592.0 110 600 11.0 583.0 110 80 110 110 110 600 320 600 360 600 11.0 527.0 11.0 - 16.0 561.0 16.0 - 9.0 545.0 15.7 13.7 Some lime- Limestone. stone, mainly sandstone. No piles 13.7 10.3 Sandstone. No Sandstone. piles. 13.54 10.1 Rock and piles Piles in gravel. 12.5' 7.6 in gravel. 16.0 15.1 Piles minsa nd, Piles in sand, 22.2 13.0 silt and clay. silt and clay. 17.0 14.0 Piles in sand, Piles in sand. silt and clay. 17.0 13.0 Piles in sand Piles in sand and gravel, and gravel. 18.0 12.0 Piles in sand Piles in sand. and gravel. 18.0 12.5 Piles in sand. Piles in sand. 17.0 12.5 Piles in sand, Piles in sand gravel and and clay. silt. 18.0 12.0 Piles in sand Piles in sand. and gravel. 22.0 14.0 Piles in sand, Piles in sand gravel, and and gravel. broken rock. 16.0 13.0 Piles in sand. Piles in sand. 15.0 12.0 Piles in sand. Piles in sand. 18.5 12.5 Piles in sand, Piles in sand. gravel and silt. 17.0 13.0 Piles in sand Piles in sand and gravel, and gravel. 19.0 13.0 Piles in sand, Piles in sand clay and and gravel. gravel. 20.5 13.5 Rock. Rock. 17.6 10.9 Rock. Rock. 24.0" 11.0 Rock. Rock. 17.0" 11.0 17.0 12.0 Piles in sand Piles in sand and gravel, and gravel. 1002 - $ 18,203,0003 100 1959 100 100 100 64 100 100 57 100 1917 1930 1948 1938 1935 1935 1936 1936 100 1937 100 1937 100 100 99 99 100 92 100 95 1938 1936 1937 1938 1938 1939 1922 1934 98 1937 12,382,0005 2,358,0006 6,492,0009 8,706,000 w M 4,865,000* 5,081,000* z 8.009,000* 4,874,000 0 5,574,000* 6,061,000* 6,539,000* i 4,750,000* z 7,428,000 0 5,580,000 7,502,000 z 6,284,000 __10 10,525,000 9,788,000 x 004 TABLE 29-C (Cont'd) LOCKS AND DAMS Lock Dimensions Greatest Depth on Character of Foundation Percent Width Length Upper Miter Sill Complete Miles of Available Normal Locks, Year Estimted Cost of Above Cham- for Full Pool Dams, and Opened Each Lock and Ohio Miles from ber Width Lift Eleva- Upper Lower Work in to Navi- Dam Including Lock and Dam River Nearest Town (feet) (feet) (feet) tion1 (feet) (feet) Lock Dam Pool gation Work in Pool Lock and dam 437.1 4.2 above New 110 600 8.0 536.0 16.0 13.0 Piles in sand Piles in sand. 99 1939 5,843,000 17 Boston, IL and gravel. Lock and dam 410.5 6.5 above 110 600 9.8 528.0 16.5 13.7 Piles in sand. Piles in sand. 90 1937 10,308,000 18 Burlington, IA Lock and dam 364.2 Keokuk, IA 110 358 38.2 518.2 4.5 9.2 Rock. Rock. 100 1913 19 110 1,200 5.0 13.0 99 1957 14,813,0002 Lock and dam 343.2 0.9 above 110 600 10.0 480.0 15.0 12.0 Rock. Rock and 97 1936 6,281,000 20 Canton, MO piles in sand and gravel. Lock and dam 324.9 2.1 below 110 600 10.5 470.0 16.5 12.0 Piles in sand Piles in sand 95 1938 8,065,000 21 Quincy, IL and gravel. and gravel. Lock and dam 301.2 1.5 below 110 600 10.2 459.5 18.0 13.8 Rock. Rock. 99 1938 5,275,000 22 Saverton, MO Lock and dam 273.4 Clarksville, MO 110 600 15.0 449.0 19.0 12.0 Rock and piles. Piles in sand. 99'4 1940 10,337,000 24 Lock and dam 241.4 Cap Au Gris, 110 600 15.0 434.0 19.0 12.0 Piles in sand Piles in sand 9914 1939 13,694,000 25 MO and gravel. and gravel. Lock and dam 202.9 Alton, IL 110 600 24.0 419.0 19.0 10.0 Piles in sand. Piles and 100 1938 12,824,000 26 (Henry T. 110 360 24.0 - 16.0 10.0 sand. Rainey Dam) New Lock and 200.8 Alton, IL 110 1,200 24.0 419.0 23.0 18.0 Piles to Piles to 45 - 751,660,000 dam 26 bedrock. bedrock. New Lock and 200.8 Alton, IL 110 600 24.0 419.0 42.0 18.0 Piles to Piles to 0 - 280,000,000 dam 26 (2nd bedrock. bedrock. Lock) Total, Locks and dams$1,260,101,000 1. Elevation of pools I to 22 and at St. Anthony Falls are mean sea level 1912 adjustment; pools 24, 26 are mean sea level 1929 adjustment. 2. Includes existing dam, owned by Northern States Power Co. 3. Includes dredging above upper lock. (Federal cost only.) 4. Based on epoolelevation 723.1 in pool 1 which is crest of dam. Pool is riormally maintained at elevation 725.1 by flashboards. 5. Includes lower approach dredging and dredging between upper and lower rock. (Federal cost only.) 6. In addition $1,948,000 expended from previous projects and $1,349,600 from O & C appropriation for first of twin locks. Excludes lock and dam rehabilition program. 7. Old upper guard sill. 8. Land ward lock. 9. In addition, $1,965,300 expended from previous projects. 10. Existing Le Claire Canal lock is used as auxiliary to lock 14: previous project cost $540,000. 1 Depth over uper poiree sill. Depth over upper miter sill is 27 feet, at lock 15. 12. $640,868 for first lock was reported by Mississippi River Power Company, transferred to Government free in lieu of improvements destroyed. (Annual Report, 1928, pp. 1118-1119.) Present estimate includes $13,132,600 for main lock and appurtenant work. 13. Includes cash contribution of $3,950.000 14. Complete except for guidewall extensions. * Excludes uncompleted guidewall extensions $10,339,000 (1972) reclassified from active to inactive on April 13, 1973. 0 0 zz U' Miles above Project Approximate size (feet) Actual or Name ONOahhmiieoo Rivveer (feetL) ocation Type depth Percent Estimated Width Length Complete Cost Harriet Island Harbor, 840.2 In city of St. Paul, MN Small-boat 5 70 925 0 $ 280,000 St. Paul, MN St. Paul Harbor, MN Hastings Harbor, MN Red Wing Harbor, MN Red Wing Harbor, MN Bay City Harbor, WI Lake City Harbor, MN Pepin Harbor, WI Wabasha Harbor, MN Alma Harbor, WI Winona Harbors, MN Lansing Harbor, IA Prairie du Chien Harbor, WI Cassville Harbor, WI Dubuque Harbor, IA Savanna Harbor, IL Clinton Harbor, IA Moline Harbor, IL Davenport Harbor, IA (Lindsay Park) Rock Island Harbor, IL Andalusia Harbor, IL Muscatine Harbor, IA New Boston Harbor, IL Fort Madison Harbor, IA Fort Madison Harbor, IA 836.5-839.2 In city of St. Paul, MN 839.7 Channel improvement, Small-boat harbor and channel enlargement. 813.2 Lower end of city of Hastings, MN 791.4 In city of Red Wing, MN 791.1 In city of Red Wing, MN 785.9 Uper end of Bay ity, 773.0 In city of Lake City, MN 767.1 760.0 751.3 726.0 726.2 663.3 635.5 635.0 606.6 579.4 537.3 519.0 488.0 484.2 479.8 473.0 455.5 455.6 433.1 383.7 In city of Pepin, WI Upper end of city of Wabasha, MN Upper end of Alma, WI In city of Winona, MN Latsch Island Crooked Slough Upper end of city of Lansing, IA Upperend of city of Prairie du Chien, WI In Marais de St. Friol East Channel below Hwy bridges. At Cassville, WI At Dubuque, IA At Savanna, IL At Clinton, IA At Moline, IL At Lindsay Park At Rock Island, IL Andalusia Slough At Muscatine, IA In Boston Bay At Fort Madison, IA 378.3 At Fort Madison, IA Commercial Small-boat Small-boat Commercial Small-boat Small-boat Small-boat Commercial4 Small-boat 4 Small-boat Small-boat Small-boat Small-boat Commercial Small-boat Small-boat Commercial Small-boat Commercial Small-boat Small-boat Small-boat Small-boat Entrance channel small-boat harbor Small-boat Small-boat Freight terminal approach channel Small-boat Small-boat 9 400-1,000 2.7(mile) 100 300 400 100 55 95 59 5 12 5555 6 559 55 Commercial 9 200 300 450 50-100 400 500 500 50 175-400 300 200 200 400 400 120 340 280 400 230 200 100 40 150 200 90-135 250 200 500 100 1,200 800 5,990 600 1,000 850 600 800 100 100 100 100 100 100 100 100 500 100 1,000 100 6,000 100 800 100 800 1,000 frontage 565 1,500 910 1,400 660 1,150 1,100 435 950 1,890 600 900 100 100 0 100 0 78 100 100 100 100 100 0 100 217,100 230,200 74,300 146,8002 r 8,700 39,500 93,500 1,225,0005 205,5006 41,700 56,300 89,800 84,700 95,300 85,000 W 93,100 178,000 55,200 310,000 101,912 110,328 262,100 31,000 21,000 353,000 23,000 184,200 o z z 10,300 0 1,070,000 TABLE 29-D HARBOR IIMPROVEM~ENTS TABLE 29-D (Cont'd) HARBOR IMPROVEMENTS Miles above Project Approximate size (feet) Actual or Name Ohio River Location Type depthPercent Estimated (feet) Width Length Complete Cost Keokuk Harbor, IA 363.5 At Keokuk, IA Small-boat 5 100-600 1,015 0 394,000 Warsaw Harbor, IL 359.1 At Warsaw, IL Small-boat 5 100 600 100 73,000 Quincy Harbor, IL 327.3 In Quincy Bay Small-boat 5 200-300 9,000 0 _ Hannibal Harbor, MO 308.8 At Hannibal, MO Small-boat 5 180-260 600 100 129,000 Total $5,132,740 1. In addition, local interests will contribute $280,000. 2. In addition, local interests contributed $3,455. 3. In addition, local interests contributed $9,533. 4. Commercial harbor converted to small-boat harbor under authority of Section 107 of 1960 River and Harbor Act, as amended. Primary use is small-boat, although some commercial activity exists. 5. In addition, local interests contributed $912,160. 6. In addition, local interests contributed $32,344. 7. Maintenance only, estimated at $5,000 annually. 00 O O1 tot tOl zD MISSISSIPPI RIVER BETWEEN MISSOURI AND MINNEAPOLIS, MN TABLE 29-E ADDITIONAL FEATURES ENTERING INTO COST OF PROJECT Facilities for public use, convenience and safety Rectification of damages caused by seepage and backwater Regulating works between lock and dam 26 (Henry T. Rainey Dam) and Missouri River Improvement of Beaver Slough at Clinton, Iowa, for navigation Miscellaneous Total additional features Total existing project (new work) 1. Includes a lump-sum payment of $2,146,800 (O&M appropriation) paid to the Sny Island Levee Drainage District, IL, for rectification of seepage damages. Also includes $140,000 Construction General funds for project studies, evaluation, and report preparation. 2. Includes $686,500 for repairs to Stone Arch bridge, Minneapolis, MN. (FY 1969) 3. Excludes $227,000 (1965) for inactive remedial measures at Sandy Slough, MO. $ 3,359,600 8,046,000 545,000 193,600 1,312,9002 13,457,1003 $468,584,858 LICENSE FEES COLLECTED THROUGH FISCAL YEAR 1985 Annual Collections to Dam Licensee Charge Sept. 30, 1985 St. Anthony Falls Lower Northern States Power $ 3,300 $ 76,777 Lock and Dam Co. (No. 2056) Lock and Dam No. 1 Ford Motor Co. 95,400 5,726,040 Total project (No. 362) $5,802,817 29-9 TABLE 29-F " 4 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 29-G AUTHORIZING LEGISLATION Acts Work Authorized Documents Sep. 22, 1922 July 3, 1930 as amended by P.R. No. 10, Feb. 24, 1932 June 26, 1934 Aug. 30, 1935 Aug. 26, 1937 Aug. 30, 1935 Aug. 26, 1937 Dec. 22, 1944 Mar. 2, 1945 Mar. 2, 1945 Mar. 2, 1945 Mar. 2, 1945 None Mar. 2, 1945 Mar. 2, 1945 Mar. 2, 1945 July 24, 1946 July 24, 1946 July 24, 1946 July 24, 1946 July 24, 1946 June 30, 1948 May 17, 1950 May 17, 1950 May 17, 1950 May 17, 1950 May 17, 1950 May 17, 1950 May 17, 1950 May 17, 1950 Sep. 3, 1954 Sep. 3, 1954 July 3, 1958 July 3, 1958 MISSISSIPPI RIVER BETWEEN MISSOURI RIVER AND MINNEAPOLIS, MN Dredging channels to landing places. Project adopted from Illinois River to Minneapolis; Chief of Engineers granted discretionary authority to make such modification in plan as may be deemed advisable. Operation of snag boats and operation and care of locks, and dams to be provided for with funds from Department of the Army appropriations for rivers and harbors. Missouri River established as lower limit of project. Extension of 9-foot channel above St. Anthony Falls, MN, including adequate terminal facilities for Minneapolis, MN St. Paul, MN, harbor. Determine damages to drainage and levee districts caused by seepage and backwater, and cost of making rectification thereof. Public park and recreational facilities. Red Wing., MN, harbor. Remedial works to correct damages caused by seepage and backwater at Cochrane, WI Such changes or additions to payments, remedial works, or land acquisitions authorized by River and Harbor Act of Aug. 26, 1937 (River and Harbor Committee Doc. 34, 75th Cong., 1st sess.), as Chief of Engineers deems advisable. St. Paul, MN, channel enlargements small boat harbor, and roadway. Vertical bridge clearance at Minneapolis to 26 feet above estimated stage for discharge of 40,000 c.f.s. Winona, MN, basin. Future modification of lock and dam No. 2 for power development. Provides for cash contribution by local interests in lieu of alteration of privately owned bridges and utilities for St. Anthony Falls project. Lake City, MN harbor. Wabasha, MN harbor. Payment of damages caused by backwater and seepage, pools 3 to Hastings, MN, harbor. Lansing, IA, harbor. Fort Madison, IA, harbors. Payment of damages caused by pool No. 14 at Clinton, IA Davenport, IA, harbor. Muscatine, IA, harbor. Alma, WI, harbor. Hannibal, MO, harbor. Prairie du Chien, WI, harbors. Opposite Hamburg, IL, harbor.1 Permits such change in location of Winona, MN, Small boat basin authorized by River and harbor Act of Mar. 2, 1945 (H. Doc. 263, 77th Cong., 1st sess.), as Chief of Engineers deems advisable. Construction of Crooked Slough Harbor at Winona, MN, in lieu of previously authorized commercial harbor. Payment of damages caused by pool No. 24 at Louisiana, MO. Permits modification of vertical bridge clearances and authorizes completion of St. Anthony Falls project. Small boat and commercial harbors at Alton, IL.2 None H. Doc. 290, 71st Cong., 2d sess. None H. Co. 137, 72nd Cong., 1st sess. H. Doc. 137, 72nd Cong., 1st sess. Rivers and Harbors Committee Doc. 44, 74th Cong., 1st sess. Rivers and harbors Committee Doc. 34, 75th Cong., 1st sess. None H. Doc. 103, 76th Cong., 1st sess. H. Doc. 137, 76th Cong., 1st sess. None H. Doc. 547, 76th Cong., 3rd sess. S. Doc. 54, 77th Cong., 1st sess. H. Doc. 263, 77th Cong., 1st sess. H. Doc. 432, 77th Cong., 1st sess. H. Doc. 449, 78th Cong., 2d sess. H. Doc. 511, 79th Cong., 2d sess. H. Doc. 514, 79th Cong., 2d sess. H. Doc. 515, 79th Cong., 2d sess. H. Doc. 559, 79th Cong., 2d sess. S. Doc. 192, 79th Cong., 2d sess. H. Doc. 661, 80th Cong., 2d sess. S. Doc. 197, 80th Cong., 2d sess. H. Doc. 642, 80th Cong., 2d sess. H. Doc. 733, 80th Cong., 2d sess. H. Doc. 66, 81st Cong., 1st sess. H. Doc. 67, 81st Cong., 1st sess. H. Doc. 71, 81st Cong., 1st sess. H. Doc. 254, 81st Cong., 1st sess. None H. Doc. 347, 83rd Cong., 2d sess. H. Doc. 251, 82nd Cong., 1st sess. H. Doc. 33, 85th Cong., 1st sess. H. Doc. 136, 84th Cong., lstsess. 29-10 MISSISSIPPI RIVER BETWEEN MISSOURI AND MINNEAPOLIS, MN TABLE 29-G (Cont'd) AUTHORIZING LEGISLATION Acts Work Authorized Documents July 3, 1958 Payment of lump sum amounts for damages to drainage and levee H. Doc. 135, 84th Cong., 1st districts caused by operation of navigation pools. sess. July 3, 1958 Improvement and maintenance of Beaver Slough at Clinton, IA. H. Doc. 345, 84th Cong., 2d sess. Mar. 3, 1909 Reconstruction of structures as may be necessary to provide None adequate facilities for existing navigation. July 14, 1960 Construction of Industrial Harbor at Red Wing., MN. H. Doc. 32, 86th Cong., 1st sess. Oct. 23, 1962 Construction of small-boat harbors at Savanna,' Moline, H. Doc. 513, 87th Cong., 2d sess. Andalusia, New Boston,' Warsaw, Quincy, and Grafton, IL; Bellevue,' Clinton, Davenport, and Keokuk, IA; St. Paul (Harriet Island), MN; and Bay City, Pepin, and Cassville,' WI. Oct. 23, 1962 Payment of damages caused by pool 24 at Clarksville, MO. H. Doc. 552, 87th Cong., 2d sess. Oct. 23, 1962 Remedial works at Sandy Slough, MO. H. Doc. 419, 87th Cong., 2d sess. Nov. 7, 1966 Repair of Stone Arch bridge at Minneapolis, MN. None Nov. 7, 1966 Commercial Harbor facilities at Fort Madison, IA.2 H. Doc. 507, 89th Cong., 2d sess. Oct. 21, 1978 Replacement of Lock and Dam 26 Public Law 95-502 1. Deffered. 2. Inactive. 29-11 CHICAGO, ILLINOIS, DISTRICT* This district comprises Cook, McHenry, Lake, Kane, DuPage and Will Counties in Illinois, and Lake and Porter Counties in Indiana, including a portion of LaPorte County along Lake Michigan. IMPROVEMENTS Navigation Page 1. Burns Waterway Harbor, IN ......................... 30-2 2. Calumet Harbor and River, IL and IN ......... 30-2 3. Chicago Harbor, IL ........................................ 30-2 4. Chicago River, IL ........................................... 30-3 5. Indiana Harbor, IN ........................................ 30-3 6. Michigan City Harbor, IN .............................. 30-4 7. Waukegan Harbor, IL .................................... 30-4 8. Reconnaissance and Condition Surveys ......... 30-5 9. Navigation Work Under Special Authorization .............................................. 30-5 Alteration of Bridges 10. Other Authorized Bridge Alteration ............. 30-5 Beach Erosion Control 11. Indiana Dunes National Lakeshore Bank Protection Beverly Shores, IN ...................................... 30-5 Page 12. Other Authorized Beach Erosion Control Projects ......................................................... 30-6 13. Beach Erosion Control Under Special Authorization .............................................. 30-6 Flood Control 14. Chicago River, IL (North Branch) .................. 30-6 15. Other Authorized Flood Control Projects ...... 30-6 16. Flood Control Work Under Special Authorization ............................................... 30-7 General Investigations 17. Surveys ............................................................ 18. Collection and Study of Basic Data ............... 19. Research and Development ............................. 20. National Emergency Preparedness ................. 30-7 30-7 30-7 30-7 30-1 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Navigation 1. BURNS WATERWAY HARBOR, IN Location. Northwestern Indiana, on the southern shore of Lake Michigan in Porter County, 28 miles south-east of Chicago harbor. (see NOAA Nautical Charts Numbers 14905 and 14926). Existing Project. Provides for (a) north breakwater 4,646 feet long; (b) an outer west bulkhead 1,176 feet long; (c) a west bulkhead shore connection 2,300 feet long; (d) an approach channel 30 feet deep and 400 feet wide; (e) an outer harbor 28 feet deep; (f) an east harbor arm 27 feet deep and 620 feet wide; (g) a west harbor arm 27 feet deep and 620 feet wide. The project was authorized by the River and Harbor Act of 27 October 1965 (Public Law 89-298; House Document Number 160, 88th Congress, 1st Session). The authorizing act also provided the Secretary of the Army to reimburse The State of Indiana for expenditure of funds used to construct such portions of the project as approved by the Chief of Engineers and constructed under supervision of the Chief of Engineers. See table 30-C. Local Cooperation. Fully complied with. Terminal Facilities. Seven berths and docks are available, three on the west harbor arm, one on the harbor basin, and three on the east harbor arm. One dock on the west harbor arm is used for shipment and receipt of steel products. One dock on the east harbor arm is used for receipt of iron ore pellets and limestone and shipment of steel products. Five facilities are administered by the Indiana Port Commission and are used for handling general cargo. Operations and results during period. Maintenance: Condition surveys were performed by Detroit District at a cost of $17,611. A shore erosion study was initiated by hired labor at a cost of $7,970. Plans and specifications were developed by hired labor for an emergency stone placement at the north breakwater at a cost of $44,041. Project management for these activities was performed by hired labor at a cost of $684. Condition at end of fiscal year. The existing project is complete. Total costs of existing project to September 30, 1985 were $17,385,089, of which $13,599,990 was for new work ($13,584,000 Federal and $15,990 non-Federal), and $3,785,099 for maintenance. 2. CALUMET HARBOR AND RIVER, IL AND IN Location. Northeastern Illinois, on the southwest shore of Lake Michigan in Cook County, 15 miles south of Chicago Harbor, within corporate limits of the city of Chicago, except for breakwaters, an approach channel, and an anchorage area which are in Illinois and Indiana. (See NOAA Nautical Charts Numbers 14926 and 14929). Previous projects. For details see page 1400 of Annual Report for 1962. Existing Project. Provides for (a) a stone filled timber crib breakwater 6,714 feet long; (b) a stone filled double row steel sheet pile detached breakwater 5,007 feet long; (c) a north pier 2,450 feet long; (d) an approach channel 29 feet deep and 3,200 feet wide; (e) an outer harbor anchorage area 28 feet deep and 3,000 wide; (f) an entrance channel 27 feet deep and 230 to 290 feet wide; (g) a channel in the Calumet River 27 feet deep and at least 200 feet wide to the north side of 130th street; (h) three turning basins designated as numbers 1, 3 and 5; (i) a channel extending into Lake Calumet at a width of about 1,000 feet. The project was authorized by the River and Harbor Acts of 3 March 1899, 13 June 1902, 30 August 1935, 14 July 1960, 23 October 1962, and 27 October 1965. See table 30-C. Local Cooperation. Fully complied with. Terminal facilities. Thirty six docks, wharves, and terminals are available. The Chicago Regional Port District owns four wharves, two grain elevators, one dock, and one terminal. The United States Government owns one stone dock. The most important cargoes handled are iron ores and concentrates, coal, and lignite. Operations and results during period. Maintenance: Condition surveys were performed by Detroit District at a cost of $57,346. An engineering investigation of the damaged southerly exterior breakwater was conducted by hired labor at a cost of $45,236. A Detroit District breakwater survey was credited $1,662 for prior year work. Breakwater stone was purchased from Detroit District at a cost of $69,563. Emergency placement by Detroit District (cranebarge MANITOWOC) of 3,938 tons of stone at the damaged breakwater was completed at a cost of $125,561. A major rehabilitation reconnaissance report was initiated at a cost of $14,950. A dredging contract was completed with removal of 86,304 cubic yards of shoal material from the river at a cost of $604,420. Supervision and contract administration for this contract was performed by hired labor at a cost of $26,924. Engineering and design for a dredging project was performed by hired labor at a cost of $64,907. A contract was awarded to dredge a portion of the river with removal of 107,825 cubic yards of shoal material at a cost of $1,054,201. Supervision and contract administration for this contract was performed by hired labor at a cost of $21,164. Water quality work was performed by contract at a cost of $3,941 and by hired labor at a cost of $18,973. A groundwater monitoring program was continued at the Chicago Area Confined Disposal Facility by hired labor at a cost of $3,415. An O & M manual was continued for the CDF by hired labor at a cost of $362. A boundary survey was initiated by hired labor at a cost of $12,811. A demonstration dredging project was initiated by St. Paul District (hydraulic dredge DUBUQUE) at a cost of $124,400. Project management for these activities was performed by hired labor at a cost of $6904. Under the dike disposal program: engineering services were completed at a cost of $24,577. A design engineering contract was completed at a cost of $39,986. Construction of the Chicago Area Confined Disposal Facility was completed with a credit of $65,790. A separate contract for a sand blanket along the stone dike was completed at a cost of $1,680. Supervision and contract administration for 30-2 CHICAGO, IL, DISTRICT these contracts was performed by hired labor at a cost of $22,333. An O & M manual was continued by hired labor at a cost of $6,907. A groundwater monitoring program was completed by contract at a cost of $18,608 and by hired labor at a cost of $16,574. As-built drawings of the completed CDF were completed at a cost of $11,866. Condition at end of fiscal year. The existing project is 79% complete. Work remaining to be accomplished consists of widening and straightening the Calumet River in the vicinity of 106th Street, and the inactive portion which consists of closing the gap between the breakwaters, and dredging minor shoals in the outer harbor. Total costs of existing project to September 30, 1985 were $45,677,404, of which $21,722,594 was for new work ($18,685,991 regular funds and $3,036,603 public works funds), $22,429,142 regular funds for maintenance, $836,667 non-Federal funds for maintenance, and $689,001 regular funds for rehabilitation. 3. CHICAGO HARBOR, IL Location. Northeastern Illinois, on the southwest shore of Lake Michigan in Cook County, within the corporate limits of the City of Chicago. (See NOAA Nautical Charts Numbers 14926, 14927, and 14928). Previous projects. See page 1396 of Annual Report for 1962. Existing Project. Provides for (a) a stone filled timber crib shore arm extension breakwater 2,250 feet long; (b) a stone filled timber crib exterior breakwater 5,421 feet long; (c) a rubble-mound and stone filled concrete caisson southerly extension to the exterior breakwater 4,944 feet long, exclusive of 582 foot entrance gap inclosing an outer basin of about 970 acres; (d) a stone filled timber crib north pier 960 feet long; (e) a stone filled timber crib north inner breakwater 4,034 feet long with a 304 foot shore return, and a 754 foot gap; (f) a stone filled timber crib south inner breakwater 2,544 feet long inclosing an inner basin of approximately 224 acres; (g) a lake approach channel 29 feet deep and 800 feet wide; (h) a channel and maneuver area inside the exterior breakwater and exterior breakwater southerly extension 28 feet deep with a maximum width of 1,300 feet; (i) an inner basin 21 feet deep; (j) an entrance channel 21 feet deep. The project was authorized by the River and Harbor Acts of 11 July 1870, 14 June 1880, 3 March 1899, 25 July 1912, 2 March 1919 and 23 October 1962. See table 30-C. The Chicago Lock was constructed in 1938 by the Metropolitan Sanitary District of Greater Chicago. The deep draft lock is 600 feet long, 80 feet wide, and 23 feet deep and uses a steel cellular design. Operation and maintenance responsibilities in the interests of navigation were transferred to the Federal Government, pursuant to Public Law 98-63, approved 30 July 1983, Section 107 of the Public Law 97-88, and Memorandum of Agreement between the Department of the Army and the Metropolitan Sanitary District of Greater Chicago. Local Cooperation. Fully complied with. Terminal facilities. There are three docks, two for passenger excursion boats and one for cargo. The most important cargoes handled are sugar and non-metallic minerals. Operations and results during period. Maintenance: A project breakwater planning appraisal study was initiated by hired labor at a cost of $8,279. A boundary survey was initiated by hired labor at a cost of $11,930. Engineering and design for a dredging project was performed by hired labor at a cost of $20,566. Project management of these activities was performed by hired labor at a cost of $11,282. Previous years deferred costs were corrected at a cost of $62,130. Operations and care of lock: Prior year Support Agreement with MSDGC was completed with a credit of $64,197. The lock operations contract was continued for another year to the same contractor at a cost of $382,572. Lock supplies were purchased at a cost of $10,906. A lock inspection report was completed by hired labor at a cost of $42,161. An engineering lock study group was initiated at a cost of $93,223. Engineering and design for replacement of the bubbler system was initiated by hired labor at a cost of $13,109. Other Corps support for operations of the lock were performed at a cost of $2,999. Supervision and contract administration for these activities was performed by hired labor at a cost of $48,578. Under the dike disposal program: engineering services were completed at a cost of $1,478. Construction of the Chicago Area Confined Disposal Facility at Calumet Harbor and River was completed with a credit of $21,930. A separate contract for a sand blanket along the stone dike was completed with a credit of $727. An O & M manual was continued by hired labor at a cost of $24,132. A groundwater monitoring program was completed by hired labor at a cost of $6,668. Condition at end of fiscal year. The existing project is complete. Total costs of existing project to September 30, 1985 were $14,366,495, of which $4,342,822 was for new work, $8,697,073 for maintenance, and $1,326,600 for rehabilitation. 4. CHICAGO RIVER, IL Location. Northeastern Illinois, in Cook County within the corporate limits of the city of Chicago. (See NOAA Nautical Charts Numbers 14926, 14927 and 14928). Previous projects. See page 1394 of Annual Report for 1962. Existing Project. Provides for (a) a channiel 21 feet deep in the main river from its mouth at Rush Street to the junction of the North and South Branches (0.7 miles); (b) a channel 21 feet deep in the North Branch from the junction to North Avenue (2.22 miles); (c) a channel 21 feet deep in the North Branch Canal (1.04 miles); (d) a 21 foot deep North Branch Turning Basin just south of North Avenue; (e) a channel 9 feet deep in the North Branch from North Avenue to Addison Street. All dredging to within 20 feet of existing docks. The project was 30-3 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 authorized by the River and Harbor Acts of 3 March 1899, 13 June 1902, 2 March 1907, and 24 July 1946. Portion of project authorized by River and Harbor Act of 1946 is in deferred-for-restudy category. See table 30-C. Local Cooperation. Fully complied with for completed modifications. River and Harbor Act of 24 July 1946 provided improvement of channel is subject to condition that local interests furnish assurances they will hold the United States free from damages which may result from construction and maintenance of improvement. Requirement has not been complied with. Terminal Facilities. Six docks are available. The most important cargoes handled are sand, gravel and crushed rock. Operations and results during period. Maintenance: Condition surveys from prior year were credited at a cost of $1,253. Under the Lake Michigan Water Diversion Monitoring Program, engineering work was performed by hired labor at a cost of $235,886 and by other Corps at a cost of $61,703. Engineering and design for a dredging project was performed by hired labor at a cost of $26,801. Project management of these activities was performed by hired labor at a cost of $2,487. Under the dike disposal program: engineering services were completed at a cost of 333. Construction of the Chicago Area Confined Disposal Facility at Calumet Harbor and River was completed with a credit of $21,930. A separate contract for a sand blanket along the stone dike was completed with a credit of $727. Engineering services for a special confined disposal facility for the North Branch were performed by hired labor at a cost of $3,263. Engineering services studying the sediment analysis of the North Branch were completed at a cost of $78,270. Supervision and contract administration of these activities were performed by hired labor at a cost of $413. Condition at end of fiscal year. The project is complete except for dredging the channel between North Avenue and Addison Street as authorized by 1946 River and Harbor Act. Head of navigation for deep draft vessels are North Avenue, 5.97 miles from Michigan Avenue Bridge. Total costs of existing project to September 30, 1985 were $8,038,003, of which $544,679 was for new work and $7,493,324 was for maintenance. 5. INDIANA HARBOR, IN Location. Northwestern Indiana, on the southwest shore of Lake Michigan in Lake County, 19 miles southeast of Chicago Harbor. (See NOAA Nautical Charts Numbers 14926 and 14929). Previous projects. For details see page 1943 of Annual Report for 1915, and page 1520 of Annual Report for 1938. Existing Project. Provides for (a) northerly rubblemound breakwater 1,120 feet long; (b) an easterly concrete capped concrete caisson breakwater 201 feet long with a rubble mound extension 2,324 feet long; (c) a lake approach channel 29 feet deep and 800 feet wide; (d) an anchorage and maneuver basin 28 feet deep; (e) a canal entrance channel 27 feet deep and 280 feet wide; (f) a main canal 22 feet deep; (g) a turning basin 22 feet deep; (h) the Forks Turning Basin 22 feet deep; (i) the Lake George Branch 22 feet deep; (j) the Calumet River Branch 22 feet deep. The project was authorized by the River and Harbor Acts of 4 March 1913, 2 March 1919, 20 March 1922, 3 July 1930, 30 August 1935, 26 August 1937, and 14 July 1960. See table 30-C. Local cooperation. Act of 1937 provides enlargement of Indiana Harbor Canal shall not be undertaken until local interests furnish a right-of-way 300 feet wide and construct substantial bulkheads along channel on established lines shown on map accompanying Rivers and Harbors Committee Document 13, 75th Congress, 1st session, provided that improvement on one side may proceed in any section on fulfillment of conditions for that side of section, and provided further, that south of turning basin at The Forks (beginning 450 feet south of intersection of present Calumet Branch and mainstem bulkhead lines), widening and deepening by the United States shall be done only as rights-of-way and bulkheads on at least one side of the channel are continuously provided southward from above limit of turning basin at The Forks. To provide for 300-foot channel, a parcel of land (of about 4.6 acres), generally 100 feet wide, lying on east side of Calumet River Branch, commencing at north side of 141st Street and extending northward toward The Forks for about 2,170 feet, has been conveyed to and accepted by the United States. Local interests constructed about 1,350 feet of bulkhead along east side of Calumet River Branch, and reconstructed bulkhead on west side from The Forks to 141st Street. Defense Plant Corp. built a bulkhead along east side of canal between Pennsylvania Railroad Co.'s bridge and Dickey Place Bridge; the United States widened and deepened east side of this portion of widening. Youngstown Sheet and Tube Co. constructed a bulkhead along west side of canal between Indiana Harbor Belt Railroad Co. bridge and the Pennsylvania Railroad Co. bridge, and the United States widened and deepened west side of this portion of widening. All prior requirements fully complied with. Terminal Facilities. Fifteen docks and wharves are available. Six docks for handling iron ore and limestone. Six docks for handling petroleum products. Three docks for handling gypsum, scrap metal and steel, and bulk products. Operations and results during period. Maintenance: Engineering services to study a hazard to navigation at Canal Street and the Indiana Harbor Canal were continued by hired labor at a cost of $4202 and by other Corps at a cost of $187. Engineering services for an Environmental Impact Statement associated with a confined disposal facility were performed at a cost of $39,757. Engineering and design for a confined disposal facility were continued by hired labor at a cost of $166,672, by other Corps and Government Agencies at a cost of $8,765. Supervision and inspection of this activity was performed by hired labor at a cost of $6,575. A research and development program was initiated with the Waterways Experiment Station at a cost of $685,356. Monitoring of this activity was performed by hired labor at a cost of $58,852. 30-4 CHICAGO, IL, DISTRICT Project management of these activities was performed by hired labor at a cost of $336. Previous years deferred costs were corrected at a cost of $100,000. Under the dike disposal program: site selection studies and engineering and design were continued by hired labor at a cost of $8,106, by contract at a cost of $800, by other Corps and Government Agencies at a credit of $3,749. Supervision and inspection of these activities were performed by hired labor at a cost of $1,682. Condition at end of fiscal year. The existing project is complete. Total costs of existing project to September 30, 1985 were $11,838,689, of which $10,208,148 was Regular Funds, $1,618,041 was Public Works Funds, and $12,500 was Contributed Funds. Of the total cost, $4,848,980 was for new work and $6,989,709 was for maintenance. 6. MICHIGAN CITY HARBOR, IN Location. Northwestern Indiana, on the southeast shore of Lake Michigan in La Porte County, 38 miles southeast of Chicago Harbor. (See NOAA Nautical Charts Numbers 14905 and 14926.) Previous projects. See page 1407 of Annual Report for 1962. Existing Project. Provides for (a) a stone filled timber crib detached breakwater 1,304 feet long; (b) a pile and steel sheeting west pier 835 feet long; (c) a stone filled timber crib, pile and steel sheeting east pier 2,276 feet long; (d) a stone filled timber crib east breakwater 1,000 feet long; (e) an entrance channel 18 feet deep and 425 feet wide; (f) a turning basin 18 feet deep; (g) a channel in Trail Creek 18 feet deep; (h) a turning basin 18 feet deep; (i) an outer basin 12 feet deep; (j) an outer basin 8 feet deep; (k) a channel in Trail Creek 6 feet deep and 50 feet wide. The project was authorized by the River and Harbor Acts of 3 March 1889, 3 March 1905, 21 January 1927, 30 August 1935, and Section 107 of 14 July 1960 approved on 30 September 1966. See table 30-C. Local Cooperation. Fully complied with. Terminal Facilities. There are several marinas in the lower mile of Trail Creek. The commodity handled at this harbor is fresh fish. Operations and results during period. Maintenance: Prior year condition surveys performed by Detroit District were credited for $2,962. Project management for these activities were performed by hired labor at a cost of $4,277. Condition at end of fiscal year. The existing project is complete. Total costs of existing project to September 30, 1985 were $7,546,239, of which $1,287,057 was for new work ($1,256,257 Federal and $30,800 non-Federal funds), $4,640,512 for maintenance, and $1,618,670 for rehabilitation. 7. WAUKEGAN HARBOR, IL Location. Northeastern Illinois, on the southwest shore of Lake Michigan in Lake County, 38 miles north of Chicago Harbor. (See NOAA Nautical Charts Numbers 14904 and 14905). Previous projects. See page 1392 of Annual Report for 1962. Existing Project. Provides for (a) a northerly stone filled timber crib breakwater 588 feet long; (b) a stone filled reinforced concrete caisson shore connection 270 feet long; (c) a stone filled double row steel sheeting shore connection 640 feet long; (d) a single row steel sheeting shore connection 398 feet long; (e) a stone filled timber crib north pier 998 feet long; (f) a single row steel sheet piling north pier 444 feet long; (g) a steel piling revetment 632 feet long; (h) a stone filled timber crib south pier 1,399 feet long; (i) a stone filled double row pile and sheeting south pier 1,712 feet long; (j) an entrance channel 22 feet deep and 390 feet wide; (k) a channel between the piers 18 feet deep and 200 feet wide; (1) an inner basin 13 feet deep; (m) an anchorage area in the southwest corner of the inner basin 8 feet deep. The project was authorized by the River and Harbor Acts of 13 June 1902, 3 July 1930, and 2 March 1945. See table 30-C. Local Cooperation. Fully complied with. Terminal Facilities. Four docks are available. The commodities handled at this harbor are gypsum and building cement. Operations and results during period. Maintenance: A prior year condition survey performed by Detroit District was credited for $13,498. A harbor planning appraisal study was initiated by hired labor at a cost of $6,014. A dredging contract was completed with removal of 72,255 cubic yards of shoal material from the outer harbor at a cost of $110,915. Liquidated damages were assessed against the contractor in the amount of $34,000. Supervision and contract administration were performed by hired labor for this contract at a cost of $42,962. Engineering services for plans and specifications were completed by hired labor for a dredging project at a cost of $10,905. Water quality activities were completed by hired labor at a cost of $17,023. A dredging contract was awarded with mobilization of contractor plant at a cost of $7,462. A north breakwater repair contract was terminated with a credit of $31,051. Supervision and contract administration were performed by hired labor for this contract at a cost of $9,767. Engineering and design were completed by hired labor for the readvertisement of the north breakwater repair at a cost of $13,046. Supervision and contract administration were performed by hired labor for this contract at a cost of $78. Engineering and design were completed by hired labor for a north pier repair project at a cost of $53,946 and by other Corps at a cost of $3,000. Supervision and contract administration were performed by hired labor for this contract at a cost of $103. Engineering services for a south pier inspection report were performed by hired labor at a cost of $8,609. Project management was performed for these activities by hired labor at a cost of $383. Under the dike disposal program: site selection studies and engineering and design were continued by hired la- 30-5 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 bor at a cost of $82,037 and by other Corps and Government Agencies at a credit of $3,034. Project management of these activities was performed by hired labor at a cost of $24,789. Condition at end of fiscal year. The existing project is complete except for the 1970 modification which is inactive. Total costs of existing project to September 30, 1985 were $5,593,913, of which $604,793 was for new work and $4,989,120 was for maintenance. 8. RECONNAISSANCE AND CONDITION SURVEYS A District project map book is being published at a cost of $25,389. Condition surveys were performed by the Detroit District at a cost of $29,526 (See table 30-G for projects and cost). A project survey was performed by real estate at a cost of $3,444. Engineering services were performed by hired labor at a cost of $48,920. Project management for these activities was performed by hired labor at a cost of $83,982. Previous years deferred costs were corrected at a cost of $78,180. 9. NAVIGATION WORK UNDER SPECIAL AUTHORIZATION Small Navigation Projects Not Specifically Authorized by Congress (Sec. 107 of the River and Harbor Act of 1960, as amended, Public Law 645, 86th Congress). Project and Location SBH Burns Waterway, IN Calumet Park, SBH, IL IL Beach State Park, SBH, IL Lake Calumet SBH, IL Michigan City Harbor, IN Fiscal Year Costs to September 30, 1985 $573,128 8,500 17,862 6,774 12,204 Alteration of Bridges 10. OTHER AUTHORIZED BRIDGE ALTERATION See table 30-D. Beach Erosion Control 11. INDIANA DUNES NATIONAL LAKESHORE BANK PROTECTION, BEVERLY SHORES, IN Location. Northwestern Indiana, on the southeast shore of Lake Michigan in Porter County, approximately 35 miles southeast of Chicago Harbor. (See NOAA Nautical Charts Numbers 14905 and 14926). Existing Project. Provides for 13,000 feet of stone revetment and periodic repair of rip rap to maintain the full length of beach front at Beverly Shores, Indiana. The current project was authorized by Public Law 97-88 and Public Law 98-63. Local Cooperation. Fully complied with. Operations and results during period. No work was performed in FY 85. Condition at end of fiscal year. Total costs of existing project to 30 September 1985 were $660,000 for new work. 12. OTHER AUTHORIZED BEACH EROSION CONTROL PROJECTS See table 30-E. 13. BEACH EROSION CONTROL UNDER SPECIAL AUTHORIZATION Beach erosion control activities pursuant to section 103 of the River and Harbor Act of 1962, as amended. Fiscal Year Costs Project and Location to September 30, 1985 Greenwood Beach, Evanston, IL Langdon Park, Wilmette, IL Lloyd Park, Winnetka, IL $ 4,705 21,600 36,969 Flood Control 14. CHICAGO RIVER, IL (NORTH BRANCH) Location Northern Illinois, in Cook and Lake Counties. Existing Project. Provides for clearing the channel of the North Branch of the Chicago River, Illinois, of fallen trees, roots, and other debris and objects which contribute to the flooding, unsightliness, and pollution of the river. The project extends from Wolf Point in Chicago Illinois, to its source just south of Rockland Road east of Libertyville, Illinois. The project was authorized by the River and Harbor Act of 31 December 1970 (Section 116) and amended by the River and Harbor Act of 7 March 1974. Local Cooperation. The 1970 Act provided that local interests furnish without cost to the United States all lands, easements, rights-of-way, and disposal areas necessary for construction of the project; hold and save the United States free from damages due to construction; maintain and operate all works after completion without cost to the United States; and agree to bear all cost in excess of $200,000 for completing construction. Assurance of local cooperation for this act was approved on 31 July 1972. The 1974 Act provided that the United States will maintain the channel free of trees, roots, debris and objects at a cost not to exceed $150,000 per year with non-Federal interests paying 25 per centum of the cost of maintenance. Operations and results during period. Maintenance: A contract was completed for the 1983 debris removal project and awarded for the 1985 debris removal project for snagging and clearing at the bridges along the main stem of the North Branch Chicago River between the junction with the North Shore Channel north to Golf Road in Morton Grove, the middle fork between Win- 30-6 CHICAGO, IL, DISTRICT netka Road to 2,000 feet north of Old Willow Road in Northbrook, and the west fork from the confluence with the middle fork northward to Lake-Cook County Line Road in Morton Grove, Glenview, and Northbrook. Federal funds in the amount of $93,812 were expended for the removal of 1,250 cubic yards of debris for the 1983 project. Engineering and design for the 1983 work was performed by hired labor at a cost of $737. Real estate services were performed at a cost of $645. Supervision and contract administration for this portion was performed by hired labor at a cost of $9,169. Federal funds in the amount of $95,348 were expended for the removal of 1,500 cubic yards of debris for the 1985 project. Engineering and design for the 1985 work was performed by hired labor at a cost of $10,994. Supervision and contract administration for this portion was performed by hired labor at a cost of $5,860. For the 1984 project: a mapping contract was completed at a cost of $4,950; engineering and design were performed by hired labor at a cost of $3,847; and real estate services were performed at a cost of $810. The local sponsor, the Metropolitan Sanitary District of Greater Chicago, expended $41,063 for the 1983 project and $33,352 for the 1985 project. A project to perform channel excavation and bank stabilization at the North Branch, Chicago River, Niles Park District, was undertaken with engineering and design being performed by hired labor at a cost of $16,976 and real estate services at a cost of $627. Condition at end of fiscal year. Total cost of existing project to September 30, 1985 were $1,763,456, of which $231,884 was for new work ($191,884 regular funds and $40,000 contributed funds) and $1,531,572 was for maintenance ($1,169,041 Federal funds and $362,531 contributed funds). 15. OTHER AUTHORIZED FLOOD CONTROL PROJECTS See table 30-F. 16. FLOOD CONTROL UNDER SPECIAL AUTHORIZATION Emergency flood control activities-repair, flood fighting and rescue work (Public Law 99, 84th Cong. and antecedent legislation). Project and Location Fiscal Year Costs to September 30, 1985 Lincoln Park Gun Club, Chicago, IL $ 885 Rosewood Beach Bath House, Highland Park, IL 27,657 Flood control activities pursuant to section 205 of Flood Control Act of 1945, as amended. Project and Location Fox River, McHenry County, IL Glen Ellyn, IL Libertyville Estates, IL Valleyview, IL Wilmington, IL General Investigations 17. Fiscal Year Costs to September 30, 1985 $59,214 2,500 21,435 41,486 11,074 SURVEYS Fiscal year costs were $2,127,334 itemized as follows: Navigation Studies $ 0 Flood Damage Prevention Studies 264,513 Shoreline Protection Studies 82,216 Special Studies 0 Special Investigations 20,000 Coordination Studies 9,131 Supplemental Pre-authorization 886,311 Review for Deauthorization 2,922 Continuation of Planning and Engineering 862,241 18. COLLECTION AND STUDY OF BASIC DATA Fiscal year costs of $85,034 were for: Flood Plain Management Services $85,034 19. RESEARCH AND DEVELOPMENT Cost for hydrologic studies during the fiscal year was $1,931. Project and Location Disaster Preparedness Rehabilitation Fiscal Year Costs to September 30, 1985 $92,661 9,154 Emergency bank protection (Sec. 14 of the 1946 Flood Control Act Public Law 526, 79th Cong). 20. NATIONAL EMERGENCY PREPAREDNESS Fiscal year costs of $165,645 were for: Training and Exercises Management and Mobilization Planning 30-7 $75,791 89,854 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 30-A See Section in Text Project 1. Burns Waterway Harbor, IN (Federal Funds) (Contributed Funds) 2. Calumet Harbor and River, IL and IN (Federal Funds) (Contributed Funds) 3. Chicago Harbor, IL (Federal Funds) 4. Chicago River, IL 5. Indiana Harbor, IN 6. Michigan City Harbor, IN (Contributed Funds) 7. Waukegan Harbor, IL 11. Indiana Dunes National Lakeshore Beverly Shores, IN COST AND FINANCIAL STATEMENT Funding New Work: Approp. Cost Maint.: Approp. Cost New Work: Contrib. Cost New Work: Approp. Cost Maint.: Approp. Cost Rehab.: Approp. Cost Maint.: Contrib. Cost New Work: Approp. Cost Maint.: Approp. Cost Rehab.: Approp. Cost New Work: Approp. Cost Maint.: Approp. Cost New Work: Approp. Cost Maint.: Approp. Cost New Work: Approp. Cost Maint.: Approp. Cost Rehab.: Approp. Cost New Work: Contrib. Cost New Work: Approp. Cost Maint.: Approp. Cost New Work: Approp. Cost Total to FY 82 FY 83 FY 84 FY 85 September 30, 1985 325,000 -64,000 300,624 -44,353 0 4,732 90,000 70,306 1,519,000 4,431,000 639,000 2,679,000 683,175 3,340,642 2,478,072 2,330,158 793,000 1,499,000 842,500 685,000 563,031 1,080,124 1,446,975 653,159 545,000 1,994,000 530,000 431,000 339,980 1,486,071 1,225,815 385,246 80,000 510,000 236,123 1,365,000 81,383 304,630 434,483 1,075,541 15,000 17,299 765,000 606,698 660,000 88,514 -13,000 20,000 -7,573 18,685 90,000 182,567 0 571,486 0 1,315 566,671 507,000 504,344 309,456 00 13,584,000 13,584,000 3,804,793 3,785,099 15,900 15,900 22,578,567' 22,578,567 22,880,7742 22,429,142 689,001s 689,001 836,667 836,667 4,788,8274 4,788,827 8,773,286 8,697,073 1,326,600 1,326,600 1,500,565, 1,500,565 7,665,7576 7,602,7876 4,897,148;9 4,897,148' 7,288,7888 6,992,2188 1,543,64610 1,543,6460 4,640,512 4,640,512 1,618,670 1,618,670 30,800 30,800 823,02611 823,026 5,387,98012 5,004,83112 660,000 660,000 30-8 CHICAGO, IL, DISTRICT TABLE 30-A (Cont'd) COST AND FINANCIAL STATEMENT See Section Total to in Text Project Funding FY 82 FY 83 FY 84 FY 85 September 30, 1985 14. Chicago River, IL New Work: North Branch Approp. 191,884 (Federal Funds) Cost 191,884 Maint.: Approp. 150,000 150,000 50,000 230,000 1,277,000 Cost 107,010 133,907 78,167 243,775 1,169,041 (Contributed New Work: Funds) Approp. 40,000 Cost 40,000 Maint.: Approp. 60,000 0 60,000 60,000 420,000 Cost 47,344 63,367 5,956 74,415 362,531 1. Includes $855,973 for previous projects. 2. Excludes contributed funds in settlement pursuant to decree [No.' 54-C-1608] regarding removal of flue-dust and includes $45,230 for previous projects. 3. In settlement pursuant to decree [No. 54-C-1608] regarding removal of flue-dust. 4. Includes $446,005 for previous projects. 5. Includes $955,886 for previous projects. 6. Includes $109,463 for previous projects. 7. Includes $60,668 for previous projects. 8. Includes $2,509 for previous projects. 9. Excludes $12,500 contributed funds. 10. Includes $287,389 for previou projects. 11. Includes $218,233 on previous projects. 12. Includes $15,711 on previous projects. 30-9 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 30-B AUTHORIZING LEGISLATION Acts Work Authorized Documents Oct. 27, 1965 BURNS WATERWAY HARBOR, IN Public Law 89-298, H. Doc. 160, Mar. 3, 1899 June 13, 1902 Mar. 3, 1905 June 25, 1910 Sept. 22, 1922 Aug. 30, 19351 2 Aug. 30, 19351 2 Mar. 2, 19453 July 14, 1960 Oct. 23, 1962 Oct. 27, 1965 July 11, 1870 June 14, 1880 Mar. 3, 1899 July 25, 1912 Mar. 2, 1919 Mar. 3, 1931 Mar. 2, 1945 Oct. 23, 1962 Dec. 4, 1981 July 30, 1983 Mar. 3, 1899 June 13, 1902 (See Section 1 of Text) Provides for breakwater and channel to present dimensions and depths: North Breakwater, West Bulkhead, Approach Channel and Outer Harbor, East and West Harbor Arms. CALUMET HARBOR AND RIVER, IL AND IN (See Section 2 of Text) Outer harbor protected by breakwaters. Five turning basins. Provided for shape and dimensions of turning basins. Consolidated the 2 projects for Calumet Harbor and Calumet River. Detached breakwater, dredging outer harbor to existing project depth and dimensions; deepen river-entrance channel and river to existing project depths; widen and straighten river channel; 5 turning basins to same depth as adjacent channel. Dredging area A and B in south end of Lake Calumet and an entrance channel 300 feet wide to 21 feet deep. An approach channel to harbor 3,200 feet wide and 28 feet deep through shoals outside breakwater and closing existing gap between breakwaters. Depth of 29 feet in lake approach to 28 feet in outer harbor; and 27 feet in river entrance up to E.J.&E. Ry. Bridge. Dee n, widen, and straighten channel in Calumet River from E. .&E. Ry. Bridge, to an including turning basin 5, to a depth of 27 feet in earth and 28 feet in rock; deepen turning basins 1, 3 and 5 to 27 feet; enlarge turning basins 3 and 5; a channel into Lake Calumet to 27 feet deep for 3,000 feet and a width of 1,000 feet; and eliminate turning basins 2 and 4 from project. Modification of Act of Oct. 23, 1962. Protection for Elgin, Joliet and Eastern Railway Bridge over the Calumet River, to permit dredging to full width of the south draw to depth of 27 feet, and temporary protection for center pier and south abutment of the New York, Chicago, and St. Louis Railroad Bridge [Nickel Plate] to permit dredging of full width of south bridge draw to depth of 27 feet prior to its replacement. CHICAGO HARBOR, IL (See Section 3 of Text) Inner breakwaters and inner basin. Exterior Breakwater. Present project depth in basin, and entrance to Chicago River. Shore-arm and southerly extension of exterior breakwater. Modification of area to be dredged in inner basin. Shore-arm extension of exterior breakwater transferred to Lincoln Park Commissioners. Resumption of jurisdiction over shore-arm extension breakwater and over certain navigable waters in Lake Michigan which lie in northwestern part of outer harbor. Deepen a lake approach channel to 29 by 800 feet wide for 6,600 feet; and deepen a channel and maneuver area inside harbor entrance to 28 by 1,300 feet wide. Provides for lock operations and maintenance responsibilities in the interests of navigation. CHICAGO RIVER, IL (See Section 4 of Text) For project depth of 21 feet in lieu of that fixed by act of June 3, 1896. Turning basins. 88th Cong., 1st sess. Annual Report, 1896 pp. 2584 et seq., and H. Doc. 277, H. 54th Cong., 1st sess. H. Doc. 172, 54th Cong., 2d sess. H. Doc. 349, 60th Cong., 1st sess. H. Doc. 494, 72d Cong., 2d sess. H. Doc. 180, 73rd Cong., 2d sess. H. Doc. 233, 76th Cong., 1st sess. H. Doc. 149, 86th Cong., 1st sess.4 H. Doc. 581, 87th Cong., 2d sess. 5 H. Report No. 973, 89th Cong., 1st sess. H. Ex. Doc. 114, 41st Cong., 2d sess., and Annual Report 1879, pp. 1562-1567 Annual Report, 1870, pp. 1562- 1567 Annual Report 1897, pp. 2790- 2791 H. Doc. 710, Cong., 2d sess. H. Doc. 1303, 64th Cong., 1st sess. Public Law 797, 71st Cong. Public Law 14, 79th Cong. H. Doc. 485, 87th Cong. 2d sess. Section 107 of Public Law 97-88 Public Law 98-63 Specified in act. Specified in act. 30-10 CHICAGO, IL, DISTRICT AUTHORIZING LEGISLATION Acts Work Authorized Mar. 2, 1907 Interpreted by Chief of Engineers, April 11, 1908 as adopting new work of the then existing project for 21-foot depth. Mar. 2, 1919 July 24, 1946 June 25, 1910 Mar. 4, 1913 Mar. 2, 1919 Mar. 20, 1922 Mar. 3, 1925 Mar. 2, 1929 July 3, 19301t0 June 30, 1932 Aug. 30, 19351" Aug. 26, 1937 July 14, 1960 Oct. 27, 196512 Mar. 3, 1889 Mar. 3, 1905 Jan. 21, 1927 Aug. 30, 1935 Sept. 30 1966 Sec. 107 July 14, 1960 June 14, 1880 Aug. 3,1882 Eliminated all work except maintenance of main river. Dredging channel 9 feet deep to within 30 feet of existing bulkheads and river banks from North Ave. to Belmont Ave., thence 9 feet deep and 50 feet wide to Addison St. INDIANA HARBOR, IN (see Section 5 of Text) Maintenance of outer harbor. Maintenance of inner harbor channel when deeded free of cost to and accepted by the United States. Breakwaters. Lighthouse crib, present length and alignment easterly and northerly breakwaters. Reduce length of channel to be maintained in extension to Lake George. Authorized Secretary of War to modify project so far as relates to length and alignment of breakwaters and to sell Youngstown Sheet and Tube Co. about 1,180 linear feet of shoreward end of existing north breakwater. Accept 2.3 acres of land for construction of the Forks Turning Basin. Existing project channel width and depth in Lake George Branch and turning basin at the Forks. Authorized Secretary of War to sell Inland Steel Co. about 1,903 linear feet of southerly end of existing east breakwater. Extended easterly breakwater, dredge entrance channel and outer harbor, deepen channel between bulkhead fills, widen main stem of canal and portion of Calumet River Branch to 141st St. Modified conditions of local cooperation required before enlargement of Indiana Harbor Canal is undertaken by United States. Increase authorized depths to 29 feet in outer harbor entrance channel; 28 feet in outer harbor, and 27 feet in canal entrance channel to first E.J.&E. Ry. Bridge. Deepen main canal from landward end of canal entrance channel to a point lakeward of Dickey Place Bridge over a modified channel width of 190 feet, except through bridge openings. MICHIGAN CITY HARBOR, IN (See Section 6 of Text) East breakwater and old east pier inclosing the outer basin. Extension of east pier. Extend east pier and construct detached breakwater. Lower turning basin. Rebuild west pier as at present located. Present project dimensions of entrance channel. Existing project depth in channel, and in lower and middle turning basins, eliminated improvement of Trail Creek above middle turning basin and uncompleted portion of detached breakwater, abandonment of old east breakwater and old east pier inclosing outer basin. Restore and repair westerly 1,000 feet of east breakwater, dredging outer basin, and enlarging entrance to basin through east pier. Dredge river channel 50 feet wide and 6 feet deep from upper turning basin to E Street bridge. WAUKEGAN HARBOR, IL (See Section 7 of Text) Parallel piers and basins.9 Modified location of harbor entrance. Documents H. Doc. 95, 56th Cong., 1st sess. [Annual Report, 1900, p. 3863 and Annual Report, 1909, p. 709]. H. Doc. 1294, 64th Cong., 1st sess. H. Doc. 767, 78th Cong., 2d sess. 6 7 H. Doc. 1113, 60th Cong., 2d sess. H. Doc. 690, 62d Cong. 2d sess. Rivers and Harbors Committee Doc. 6, 65th Cong., 2d sess. Public Law 176, 67th Cong. Rivers and Harbors Committee Doc. 21, 71st Cong., 2d sess. Public Law 219, 72d Cong. Rivers and Harbors Committee Doc. 29, 72d Cong., 1st sesss. Rivers and Harbors Committee Do. 13, 75th Cong., 1st sess. H. Doc. 195, 86th Cong., 1st sess. H. Doc. 227, 89th Cong., 1st sess. 8 Recommendation of a Board of Engineers, Annual Report, 1870, p. 123. Reports of Boards of Engineers, Annual Report, 1851, pp. 2187-2189; Annual Report 1882, pp. 2264-2266. Annual Report, 1897, pp. 2903- 2904. Joint resolution of Congress approved May 13, 1908. Public Law 23. H. Doc. 279, 69th Cong., 1st sess. Rivers and Harbors Committee Doc. 34, 74th Cong., 1st sess. Detailed Project Report June 1965.8 Annual Report, 1880, p. 1942. Annual Report, 1882, pp. 277, 2162. 30-11 TABLE 30-B (Cont'd) REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 30-B (Cont'd) AUTHORIZING LEGISLATION Acts Work Authorized Documents June 13, 1902 Detached breakwater, extend piers, increase width of harbor at H. Doc. 343, 56th Cong., 1st inner end of north pier, and dredge channel and basin to depth sess. of 20 feet. July 3, 1930 Extension of breakwater to shore, dredging near outer end of Rivers and Harbors Committee north pier, and enlarging inner basin. Doc. 27, 71st Cong., 2d sess. Mar. 2, 1945 Dredge an entrance channel to existing project dimensions from H. Doc. 116, 77th Cong., 1st outer end of north pier to project depth in lake, and dredge an sess. anchorage area in southwest corner of inner basin to existing project depth. Abandonment of dredging triangular area in southwest corner of inner basin to 18 feet deep. Dec. 17, 1970 Provides for deepening the existing entrance channel in the outer H. Doc. 368, 90th Cong., 2d Sec. 201 harbor to 25 feet and extending it to the depth in Lake sess.8 Oct. 27, 1965 Michigan, at widths varying from 380 feet to 500 feet; deepening the channel between piers to a depth of 23 feet at a width of 180 feet, and deepening the inner basin to 23 feet and extending its limits approximately 275 feet northward. INDIANA DUNES NATIONAL LAKESHORE, IN, BEVERLY SHORES, IN Dec. 4, 1981 Provides for emergency shore protection repairs to stone Public Law 97-88. revetment initially constructed in 1973. July 30, 1983 Provides for operations and maintenance of the shore protection Public Law 98-63. measures. 1. Included in Public Works Administration Program Sept. 6, 1943, and Dec. 16, 1933. 2. Uncompleted portion was deauthorized in 1977 [dredgingin front of U.S. Steel Corp.]. 3. Uncompleted portion was deauthorized in 1977 [breakwater closure.] 4. Contains latest map of harbor. Uncompleted portion is inactive. 5. Contains latest map of river. 6. Latest published map is in Annual Report for 1914, opposite p. 2928. 7. Contains latest published map of North Branch above North Ave. 8. Contains latest published map. 9. Completed under previous project. 10. Uncompleted portion was deauthorized in 1977 [widen and deepen Lake George Branch.] 11. Included in Public Works Administration Program Sept. 6, 1933, and July 25, 1934. Uncompleted portion was deauthorized in 1977 [widen and deepen main canal and Calumet River Branch.] 12. Project deauthorized in 1977. 30-12 CHICAGO, IL, DISTRICT EXISTING PROJECTS See Section Length Width Depth in Text Project Item (feet) (feet) (feet) 1. Burns Waterway North Breakwater 4.646 - - Harbor, IN 2. Calumet Harbor and River, IL and IN 3. Chicago Harbor, IL 4. Chicago River, IL 5. Indiana Harbor, IN 6. Michigan City Harbor, IN 7. Waukegan Harbor, IL Outer West Bulkhead Approach Channel Outer Harbor East Harbor Arm West Harbor Arm Northerly Crib Breakwater Southerly Steel Breakwater North Pier Approach channel Outer harbor River entrance Elgin, Joliet & Eastern Railway Bridge to turning basin No. 3 Turning basin No. 3 to turning basin No. 5 Approach into Lake Calumet Extension into Lake Calumet Turning basins 1, 3, and 5 Shore arm extension Exterior breakwater Exterior breakwater southerly ext. North inner breakwater South inner breakwater North pier Approach channel Channel and maneuver area Lock Inner basin Entrance channel Main Branch of Chicago River North Branch of Chicago River North Branch Canal North Branch Turning Basin Northerly Breakwater Easterly Breakwater Approach Channel Outer Harbor Entrance Channel Main Canal Turning Basin Lake George Branch Calumet River Branch Detached breakwater West pier East Pier East breakwater Entrance channel Main channel Outer basin Trail Creek Trail Creek North breakwater and Shore Connection North pier and North Revetment South pier Entrance Channel Channel to inner basin Inner basin Anchorage Area 'Area of about 6 acres. 30-13 TABLE 30-C 3,476 2,200 3,700 2,100 3,800 6,714 5,007 2,450 9,700 10,500 3,000 21,100 8,000 4,000 3,000 2,250 5,421 4,944 4,034 2,544 960 6,600 2,200 600 1,270 7,300 3,800 11,100 5,500 1,120 2,525 7,200 4,200 3,600 7,400 3,700 2,500 1,304 835 2,276 1,000 1,900 2,400 900 3,000 2,300 1,896 2,074 3,111 3,250 1,700 1,650 -1 400 Varies 620 620 3,200 3,000 290 200 and variable Variable 400 1,000 800 1,30800 740 190-470 190-390 91-390 56-210 800 Varies 65-280 61-210 64-160 160-260 150-425 120-150 50-190000 50 230900 375-500 30 28 27 27 29 28 27 27 earth 28 rock 27 27 27 27 29 28 23 21 21 21 21 21 21 29 28 27 22 22 22 22 18 8-1128 86 22 18 18 8 Area of about 6 acres. TABLE 30-D REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 OTHER AUTHORIZED BRIDGE ALTERATION (See Section 10 of Text) For Last Cost to September 30, 1985 Full Report See Annual Operation and Project Report For Construction Maintenance Calumet River Bridges' 1967 $1,625,068 - 'Transferred to Department of Transportation in accordance with Section 6[g] of the Act of October 15, 1966, P.L. 89-670. TABLE 30-E OTHER AUTHORIZED BEACH EROSION PROJECTS (See Section 12 of Text) For Last Cost to September 30, 1985 Full Report See Annual Operation and Project Report For Construction Maintenance Mt. Baldy, Indiana Dunes National Lakeshore, IN 1984 $1,500,000- Hollywood-Ardmore Beach Chicago, IL 19.82 $237,271 - Evanston, IL. 1979 766,052- Lake Michigan-Lake Bluff, IL 1976 244,889- Lake Michigan-Lake Forest, IL' 1975 65,611- 'Authorized by River and Harbor Act of 1954. OTHER AUTHORIZED TABLE 30-F FLOOD CONTROL PROJECTS (See Section 15 of Text) For Last Cost to September 30, 1985 Full Report See Annual Operation and Project Report For Construction Maintenance KANKAKEE RIVER, IL AND IN Levee between Shelby Bridge and Baum's Bridge in IN 1938 - - LITTLE CALUMET RIVER, IL AND IN Little Calumet River and Tributaries, IL and IN' 1968 53,136- Little Calumet River, IL 1984 $583,000 - 'Classified inactive to November 1971. TABLE 30-G RECONNAISSANCE AND CONDITION SURVEYS (See Section 8 of Text) Date Reconnaissance or Condition Survey Project Conducted Cost Burns Waterway Harbor, IN Sept. 1985 $17,578 Calumet Harbor & River, IL and IN June 1985 -17,206' Chicago Harbor, IL June, April 1985 11,726 Indiana Harbor, IN Oct. 1985 4,558 Michigan City Harbor, IN Aug. 1985 4,402 Waukegan Harbor, IL July, Aug. 1985 8,468 'Cost reflects an adjustment as a result of condition surveys performed in 1984. 30-14 DETROIT, MI DISTRICT* The district is composed of the upper and lower peninsulas of Michigan and portions of Indiana, Wisconsin and Minnesota, which border the lakes. It includes U. S. waters of Lakes Superior, Michigan, Huron, St. Clair and western Lake Erie. Unless otherwise indicated, all depths stated in this report are referred to low water datum as follows: Lake Superior, 600 feet; Lake Michigan-Huron, 576.8 feet; Lake Erie, 568.6 feet; and Lake St. Clair, 571.7 feet. Elevations in feet are above mean water level at Father Point, Quebec (International Great Lakes Datum-1955). IMPROVEMENTS Navigation Page 1. Alpena Harbor, MI ........................ 31-2 2. Arcadia Harbor, MI ....................... 31-3 3. Ashland Harbor WI ....................... 31-3 4. Au Sable Harbor, (Oscoda) MI ............. 31-3 5. Black River (Port Huron) MI...............31-4 6. Black River, (U. P.) MI .................... 31-4 7. Bolles Harbor, MI ......................... 31-4 8. Charlevoix Harbor, MI .................... 31-5 9. Cheboygan Harbor, MI .................... 31-5 10. Clinton River, MI.......................... 31-6 11. Cornucopia Harbor, WI....................31-6 12. Detour Harbor, MI ........................ 31-6 13. Detroit River, MI..........................31-6 14. Duluth-Superior Harbor, MN and WI ...... 31-7 15. Eagle Harbor, MI ......................... 31-8 16. Fox River, W I.............................31-8 17. Frankfort Harbor, MI .................... 31-9 18. Grand Haven Harbor and Grand River, MI ........................... 31-9 19. Grand Marais Harbor, MN .............. 31-10 20. Grand Traverse Bay Harbor, MI .......... 31-10 21. Green Bay Harbor, WI................. 31-10 22. Hammond Bay Harbor, MI .............. 31-11 23. Harbor Beach Harbor, MI ............... 31-11 24. Harrisville Harbor, MI .................. 31-12 25. Holland Harbor, MI ................... 31-12 26. The Inland Route, MI.................... 31-13 27. Kenosha Harbor, WI.................... 31-13 28. Kewaunee Harbor, WI................... 31-13 29. Keweenaw Waterway, MI................. 31-14 30. Knife River Harbor, MN................. 31-14 31. LaPointe Harbor, WI .................... 31-15 32. Lac La Belle Harbor, MI................ 31-15 33. Lake St. Clair, MI Channels............... 31-15 34. Leland Harbor, MI ..................... 31-16 35. Lexington Harbor, MI....................31-16 36. Little Lake Harbor, MI .................. 31-16 37. Ludington Harbor, MI................... 31-17 38. Mackinaw City Harbor, MI .............. 31-17 39. Manistee Harbor, MI .................... 31-17 Navigation (cont.) Page 40. Manistique Harbor, MI .................. 31-18 41. Manitowoc Harbor, WI .................. 31-18 42. Marquette Harbor, MI.................... 31-19 43. Menominee Harbor and River, MI and W I.............................. 31-19 44. Milwaukee Harbor, WI .................. 31-20 45. Monroe Harbor, MI...................... 31-20 46. Muskegon Harbor, MI................... 31-21 47. New Buffalo Harbor, MI.................. 31-21 48. Oconto Harbor, WI ...................... 31-22 49. Ontonagon Harbor, MI ................. 31-22 50. Pentwater Harbor, MI................. 31-22 51. Petoskey Harbor, MI .................... 31-23 52. Point Lookout Harbor, (Au Gres River) MI...................... 31-23 53. Port Austin Harbor, MI................ 31-23 54. Portage Lake Harbor, MI................ 31-23 55. Port Sanilac Harbor, MI ................. 31-24 56. Port Washington Harbor, WI ............ 31-24 57. Port Wing Harbor, WI................. 31-24 58. Presque Isle Harbor, MI................. 31-25 59. Racine Harbor, WI ...................... 31-25 60. Rouge River, MI........................ 31-25 61. Saginaw River, MI ...................... 31-26 62. St. Clair River, MI ...................... 31-27 63. St. Joseph Harbor, MI ................... 31-27 64. St. Marys River, MI ..................... 31-28 65. Saugatuck Harbor and Kalamazoo River, MI ................................ 31-29 66. Saxon Harbor, WI....................... 31-29 67. Sheboygan Harbor, WI ............... 31-29 68. South Haven Harbor, MI ................. 31-30 69. Sturgeon Bay and Lake Michigan Ship Canal, WI......................... 31-30 70. Two Rivers Harbor, WI................. 31-30 71. White Lake Harbor, MI................. 31-31 72. Reconnaissance and Condition Surveys .... 31-31 73. Other Authorized Navigation Projects ..... 31-31 74. Navigation Work Under Special Authorization............................ 31-31 31-1 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Beach Erosion Control Page 75. Authorized Beach Erosion Control Projects......................... 31-32 76. Emergency Shore Protection .............. 31-32 77. Beach Erosion Work Under Special Authorization ........................... 31-32 78. Mitigation of Shore Damages ............ 31-32 Flood Control 79. Kawkawlin River, MI.................... 31-32 80. Saginaw River, MI ...................... 31-33 81. Sebewaing, Sebewaing River, MI........3. 1-34 82. Inspection of Completed Flood Control Projects......................... 31-34 83. Other Authorized Flood Control Projects ............................... 31-34 84. Flood Control Under Special Authorization ............................ 31-34 85. Surveillance of Northern Boundary W aters ................................. 31-35 General Investigations 86. Surveys................................. 31-37 General Ipvestigations (cont.) Page 87. Continuation of Planning and Engineering ........................ 31-37 88. Advanced Engineering and Design........ 31-38 89. Collection and Study of Basic Data.................................... 31-38 Tables Table 31-A Table 31-B Table 31-C Table 31-D Table 31-E Table 31-F Table 31-G Table 31-H Table 31-I Cost & Financial Statement ...... 31-39 Authorizing Legislation ......... 31-55 Features of Existing Project ......................... 31-73 St. Marys River, MI: Existing Project ................ 31-74 Fox River, WI: Locks & Dams.... 31-75 Reconnaissance & Condition Surveys.......................... 31-76 Other Authorized Navigation Projects ............. 31-77 Other Authorized Flood Control Projects.................. 31-78 Deauthorized Projects ........... 31-79 Navigation 1. ALPENA HARBOR, MI Location. At mouth of Thunder Bay River which empties into Thunder Bay, Lake Huron. Harbor is 100 miles southeast of Cheboygan Harbor, MI. River has its source in Montmorency and Alpena Counties, MI. (See NOAA Nautical Chart 14864.) Previous project. For details see page 1957 of Annual Report for 1915 and page 1548 of Annual Report for 1938. Existing project. Provides for a bay channel 200 feet wide and 25 feet deep from deep water in Thunder Bay to a point 300 feet lakeward of the Alpena Light; thence an entrance channel 24 feet deep, narrowing to a width of 100 feet at a point 700 feet upstream from the light; a river channel 100 feet wide, 23 feet deep to Second Avenue Bridge; thence 18.5 feet deep and 75 feet wide for 1,600 feet to upper limit of Federal project; a turning basin at upstream end of project, basin at river mouth 19 feet deep, trapezoidal in shape, with a maximum width of 700 feet including the channel width and a maximum length of 900 feet along the channel line, including removal of existing rubble breakwater; and a breakwater about 550 feet long paralleling lakeward side of new turning basin. Work authorized by the 1965 River and Harbor Act is considered inactive. Estimated cost of this portion (1969) is $1,100,000 (Federal) and $48,000 (non-Federal). (See Table 31-B for authorizing legislation.) Local cooperation. Act of October 27, 1965 is subject to condition that responsible local interests give assurances that they will provide lands, easements, rights-of-way for construction and future maintenance of project and aids to navigation upon request of the Chief of Engineers, including suitable spoil disposal areas and necessary retaining dikes, bulkheads and embankments therefor, or the costs of such retaining works; hold the United States free from damages; provide necessary terminal facilities at Abitibi Corp; dredge and maintain areas between Federal improvement and terminal facilities to depths commensurate with improved Federal channel. Local cooperation from previous River and Harbor Acts is fully complied with. Terminal facilities. Several commercial docks along Thunder Bay River used primarily for receipt of coal and petroleum products. Also a municipal marina basin about 0.25 mile southwest of river mouth. Facilities are considered adequate for existing commerce. Operations during fiscal year. Maintenance: Condition surveys, miscellaneous inspections and reports were performed by Government forces at a cost of $16,086. A contract for maintenance dredging was awarded and completed this FY at a cost of $503,290. A total of 93,169 cubic yards of shoal material was removed by mechanical dredge. Engineering, design, supervision and administration cost $39,727. 31-2 DETROIT, MICHIGAN DISTRICT Existing project was completed in 1939. The modification of existing project at Alpena Harbor, as authorized by the 1966 River and Harbor Act, was reclassified into an inactive status May 22, 1969 based on an unfavorable benefit-cost ratio. In 1975 the modification was recommended and reviewed for deauthorization, which was withdrawn by Congressional Resolution the same year. Project features are in good condition. Total costs to end of FY for existing project were $1,307,610, of which $337,394 was for new work and $970,216 for maintenance. 2. ARCADIA HARBOR, MI Location. On east shore of Lake Michigan, 193 miles northeasterly from Chicago, IL, and 15 miles northerly from Manistee, MI. (See NOAA Nautical Chart No. 14907). Existing project. Provided for maintenance dredging of the existing harbor built by private interests for a period of five years. The five years covered by this project were the calendar years 1905 to 1909, inclusive. Funds were also appropriated and maintenance was performed in calendar years 1911,1912,1913 and 1915, inclusive. There is at present no approved project for the improvement of this harbor. (See Table 31-B for authorizing legislation.) Local cooperation. None required. Terminal facilities. Dock facilities are considered adequate for existing recreational traffic. Operations during fiscal year. Maintenance: Condition surveys, environmental studies, miscellaneous inspections and reports were performed by Government forces at a cost of $14,390. A contract was awarded and completed for maintenance dredging at a cost of $43,730, removing approximately 6,919 cubic yards of shoal material by hydraulic dredge. Repairs to navigation structures were performed by hired labor using the cranebarge MANITOWOC at a cost of $138,648. An adjustment of $15,000 was made this FY in prior years cost for repairs to navigation structures. Engineering and design for repair to breakwater was continued at a cost of $36,117. Engineering, design, surveys, supervision and administration cost $15,678. Existing project was completed in 1909. Varying depths of 5-12 feet exist in the channel at present. Future maintenance of the harbor will be based on providing a 9-foot depth. Piers and revetments are in good condition with some sections in need of major repair. Total cost at the end of FY for existing project was $1,110,199. 3. ASHLAND HARBOR, WI Location. At head of Chequamegon Bay, on south shore of Lake Superior, about 65 miles east of Duluth, MN. (See NOAA Nautical Chart 14974.) Existing project. A west channel 20 and 21 feet deep and an east basin 25 and 27 feet deep, both all protected by an 8,000-foot breakwater. For additional details see page 1008 of Annual Report for 1965. (See Table 31-B for authorizing legislation) Local cooperation. Fully complied with. Terminal facilities. City of Ashland owns 4,150 feet of waterfront for future public needs. Wharves for handling coal, ore, limestone, logs, and pulpwood are served by railroads. Facilities are considered adequate for existing commerce. Handling of ore and logs has been discontinued for the present. Operations during fiscal year. Maintenance: Condition surveys, environmental studies and miscellaneous inspections and reports were performed by Government forces at a cost of $15,687. Work authorized prior to 1960 Act was completed in 1950. Work authorized by 1960 Act was completed in November 1962. Total cost of existing project to end of FY was $4,176,390, of which $1,695,645 was for new work and $2,480,745 for maintenance. 4. AU SABLE HARBOR AT AU SABLE RIVER (OSCODA), MI Location. Au Sable River and Village of Oscoda, MI, are on west shore of Lake Huron, 8 miles north of Au Sable Point, northeast limit of Saginaw Bay. (See NOAA Nautical Chart 14863.) Previous project. For details see pages 336 and 2453 of Annual Report for 1892. Existing project. Riprapping outer 200 feet of north pier at mouth of Au Sable River, dredging an entrance channel 12 feet deep and dredging between piers and upstream to State highway bridge 10 feet deep. (See Table 81-B for authorizing legislation.) Local cooperation. Fully complied with. Terminal facilities. Several small timber pile wharves used primarily by commercial fishermen and pleasure craft operators; also a private marina basin east of U.S. Highway 23 Bridge. Facilities are considered adequate for existing commerce. Operations during fiscal year. Maintenance: Condition surveys and miscellaneous reports were performed by Government forces at a cost of $11,014. Existing project was completed in 1962. Controlling depths are 10 feet in entrance channel, 8 feet between the jetties, and 6 feet in river to upstream limits of project. Total costs to end of FY for existing project were $2,678,390, of which $209,776 was new work (including $16,400 contributed funds) and $2,468,614 for maintenance. 31-3 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 5. BLACK RIVER (PORT HURON), MI Location. This river has its source in the northern part of Sanilac County, MI, is about 60 miles long, and flows in a southeasterly direction into the St. Clair River. (See NOAA Nautical Chart 14852.) Previous project. For details see page 1441 of Annual Report for 1916, and page 1554 of Annual Report for 1938. Existing project. Provides for a channel 20 feet deep from deep water in St. Clair River to the Grand Trunk Western Railroad Bridge, 160 feet wide at the mouth, decreasing to 100 feet, about 800 feet fromdhe mouth, thence 100 feet wide for 2,600 feet, decreasingto 75 feet for a distance of 4,800 feet; widening two bends to 100 feet, one at the foot of 12th Street, and the other below the Grand Trunk Western Railroad Bridge; for a settling basin 75 feet wide and 20 feet deep, beginning at the Grand Trunk Western Railroad Bridge in Port Huron and extending upstream a distance of about 2,300 feet; and then for a distance of 2.6 miles as a 100-foot wide river channel, 8 feet deep to the 1-94 bridge where it decreases to 6 feet deep and continues to the vicinity of the Black River Drainage Canal with suitable widening where required at bends in the channel. The project modification authorized by the Act of August 30, 1935 is considered to be inactive and is excluded from the foregoing cost for new work. The cost of this modification was last revised in 1954 and was estimated to be $194,000 exclusive of $194,000 to be contributed by local interests. (See Table 31-B for authorizing legislation.) Local cooperation. Fully complied with. Terminal facilities. There are docks on both sides of Black River, near its mouth, and between these docks and the upper limit of improvement there are 5 other docks varying in length from 100 to 500 feet. All docks are privately owned and are restricted to the use of the owners. The facilities are considered adequate for existing commerce. Public recreational boating facilities constructed by the State and local agencies are available as are privately owned and operated marinas. Operations during fiscal year. Maintenance: Condition surveys, miscellaneous inspections and reports were performed by Government forces at a cost of $2,233. All work, except that authorized by Act of August 30, 1935 and the latest modification, has been completed. Total costs for existing project to end of FY were $1,338,298, of which $830,165 was for new work (includes $349,921 contributed funds) and $508,133 for maintenance. 6. BLACK RIVER HARBOR (UPPER PENINSULA), MI Location. At mouth of Black River on south shoreof Lake Superior 39 miles westerly from Ontonagon, MI, and 47 miles easterly from Ashland, WI. (See NOAA Nautical Chart 14965.) Existing project. Two converging breakwaters, an entrance channel between breakwaters, an inner channel, and an irregular harbor basin. For additional details see page 1092 of Annual Report for 1966. Project depths are 12 feet in the approach channel and 8 feet in the river channel and basin. (See Table 31-B for authorizing legislation.) Local cooperation. Fully complied with. Local interests furnished easements on 0.85 acre of land. Terminal facilities. Wharves constructed on both sides of river. Wharf on east bank has frontage of 400 feet; on west bank, a frontage of 750 feet. Operations during fiscal year. Maintenance: Condition surveys, miscellaneous inspections and reports were performed by Government forces at a cost of $8,827. Minor structure repairs were performed by hired labor using the cranebarge MANITOWOC at a cost of $44,674. Supervision and inspection costs were $11,532. Project was completed in June 1958. A triangularshaped rock shoal 50 feet wide at easterly end extends along southerly side of channel. Total cost for existing project to end of FY was $951,718, of which $383,350 was for new work and $568,368 for maintenance. 7. BOLLES HARBOR, MI Location. On west shore of Lake Erie at mouth of La Plaisance Creek, 7 miles southwest of Monroe, MI. (See NOAA Nautical Chart 14846.) Existing project. Provides for an entrance channel in Lake Erie, 8 feet deep and 80 feet wide from deep water to a point opposite the outer end of existing jetty, thence widening to. 100 feet at creek mouth; an access channel in La Plaisance Creek, 6 feet deep and 100 feet wide at the mouth widening to 120 feet and extending to the first bend, thence narrowing to 50 feet wide and continuing at that width to the La Plaisance Road bridge; a steel sheet pile revetment, about 200 feet long, located along Michigan State Conservation Department property on west side of channel at creek mouth. Project also provides for inclusion of existing 400-foot long steel sheet pile jetty constructed by Michigan State Waterways Commission at the mouth of La Plaisance Creek. (See Table 31-B for authorizing legislation.) Local cooperation. Fully complied with. Terminal facilities. The Monroe Boat Club and three marinas provide facilities adequate for existing recreational boat traffic. There is also a public launching ramp and parking area at Conservation Department fishing site at creek mouth. 31-4 DETROIT, MICHIGAN DISTRICT Operations during fiscal year. Maintenance: Condition surveys and all miscellaneous inspections and reports were performed by hired labor at a cost of $6,412. Engineering and design for repairs of diked disposal facility to be performed by contract next FY cost $12,230. The existing project was completed in 1970 (Adequate depths exist over the project length except for the upstream 800 feet). Total costs to the end of FY were $2,512,070, of which $426,413 was for new work ($255,000 contributed funds) and $2,085,657 for maintenance. 8. CHARLEVOIX HARBOR, MI Location. On east shore of Lake Michigan, 276 miles northeasterly from Chicago, IL, and 75 miles northerly from Frankfort, MI. (See NOAA Nautical Chart 14942.) Existing project. A channel 24 feet deep in Lake Michigan and a river channel 23 feet deep in the lower and upper channels connecting Lake Michigan with Lake Charlevoix via Round Lake. The channels are protected where needed by piers and revetments. For additional details see page 1476 of Annual Report for 1962. (See Table 31-B for authorizing legislation.) Local cooperation. None required except the latest project modification is subject to the following: Provide without cost to the United States, all lands, easements, and rights-of-way required for construction and subsequent maintenance of the modified project upon the request of the Chief of Engineers, including suitable areas determined by the Chief of Engineers to be required in the general public interest for initial and subsequent disposal of excavated materials and any necessary retaining dikes, bulkheads, and embankments, therefor, or the cost of such retaining works; hold and save the United States free from damages due to the construction and maintenance of the modified project, except for damages due to the fault or negligence of the United States or its contractors; provide and maintain without cost to the United States depths in berthing areas and local access channels serving the terminals commensurate with the depths provided in the related project areas; accomplish, without cost to the United States, such alterations of submarine utility crossing as are required by the modified project; establish regulations prohibiting discharge of pollutants into the waters of the harbor by users thereof which regulations shall be in accordance with applicable laws or regulations of Federal, State and local authorities responsible for pollution prevention and control; if acquiring lands, easements and rights-of-way for construction of the project, local interests will comply with the applicable provisions of the Uniform Relocation Assistance and Real Property Acquisition Policies Act of 1970; Public Law 91-646, approved January 2,1971; contribute all costs in excess of $1,000,000 should the total cost of construction of the general navigation facilities exceed that amount, in accordance with provisions of Section 107 of the 1960 River and Harbor Act, as amended. The total first cost of construction (1975) is estimated at $652,000. Terminal facilities. Several small landing places in Round Lake at Charlevoix for handling fish and miscellaneous commodities, a wharf for petroleum products at west end of Lake Charlevoix, and coal wharves at Advance and Boyne City. Charlevoix, Boyne City, and East Jordan provide public docks for small craft. Facilities considered adequate for existing commerce. Operations during fiscal year. Maintenance: Condition surveys, environmental studies, miscellaneous inspections and reports were performed at a cost of $30,046. An adjustment of $10,000 was made this FY for prior year costs of repairs to navigation structures. An adjustment of $1,199 was made in the dredging contract completed last FY. Engineering and design for revetment repair at Park Island was performed at a cost of $10,438. Engineering, design and supervision cost $1,296. Existing project was completed in 1939 except for the latest modification. A controlling depth of 18 feet is available throughout the entire project, except for minor shoaling along the channel limits. Total costs to end of FY were $6,169,691, of which $180,623 was for new work, $4,859,672 for maintenance (Bank Stabilization $46,352) and $1,129,396 for rehabilitation. 9. CHEBOYGAN HARBOR, MI Location. At mouth of Cheboygan River which empties into Western Lake Huron about 16 miles southeast of the Straits of Mackinac Bridge. (See NOAA Nautical Charts 14881 and 14886.) Previous project. For details see page 1956 of Annual Report for 1915, and page 1546 of Annual Report for 1938. Existing project. A channel 21 feet deep and 200 feet wide from 21-foot contour in Lake Huron to outer end of west pier; thence, between lines parallel to and 25 feet from the docks, 21 feet deep from this point to East First Street and thence 18.5 feet deep and 60 feet wide from this bridge to the lock in Cheboygan River; a turning basin 21 feet deep, 400 feet wide, and 420 to 770 feet long on east side of existing project channel just below East First Street; and rubblemound breakwater about 775 feet long on the site of existing west pier at mouth of river. Improvement is 12,000 feet long, on which about 6,000 feet are in Straits of Mackinac. Local cooperation. Fully complied with. Terminal facilities. Several privately owned wharves used for receiving coal, stone and petroleum products. Public recreational boating facilities constructed by the State and local agencies are available. These facilities satisfy existing commerce and vessel traffic. 31-5 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Operations during fiscal year. Maintenance: Condition surveys and miscellaneous inspections and reports were performed by hired labor at a cost of $2,798. Total costs to end of FY were $1,379,814, of which $504,236 was for new work and $875,578 for maintenance. 10. CLINTON RIVER, MI Location. Has its source in Oakland County, MI, flows easterly about 60 miles and empties into Anchor Bay in northwestern part of Lake St. Clair. (See NOAA Nautical Chart 14850.) Previous project. For details see page 1958 of Annual Report for 1915, and page 1556 of Annual Report for 1938. Existing project. An entrance channel in Anchor Bay 8 feet deep, 300 feet wide at 8-foot depth contour in the bay, gradually decreasing to 50 feet wide at about 1,000 feet upstream from mouth of Clinton River, a length of about 4,600 feet; a channel 8 feet deep and 50 feet wide in the river about 38,700 feet long from entrance channel upstream to Mt. Clemens at Cass Avenue; closing old channel and making a cutoff at Shoemakers Bend; closing Catfish Channel; construction of revetments as needed in the river; and a harbor basin, 5 feet deep and 11 acres in area at entrance along bay channel, protected by breakwaters on north and south sides. (See Table 31-B for authorizing legislation.) Local cooperation. Fully complied with. Terminal facilities. River is used exclusively by recreational craft. There are numerous public and private piers and wharves along the river below the City. They are considered adequate. Operations during fiscal year. Maintenance: Condition surveys, environmental studies, miscellaneous inspections and reports were performed by Government forces at a cost of $6,539. Engineering and design for a confined disposal area for polluted dredged material was continued at a cost of $62,567. Existing project was completed in 1966. Total costs to end of FY were $1,946,633, of which $549,798 (including $289,752 contributed funds) was for new work, and $1,396,835 for maintenance. 11. CORNUCOPIA HARBOR, WI Location. At mouth of Siskiwit River on south shore of Lake Superior, 49 miles east from Duluth, MN. (See NOAA Nautical Chart 14973.) Existing project. Provides for an entrance channel between piers; an irregular-shaped turning basin; two inner channels, and reconstruction and Federal maintenance of deflection dike and entrance piers constructed by local interests. Project depths are 10 feet between piers and 8 feet in turning basin and inner channels. For additional details see page 1010 of Annual Report for 1965. (See Table 31-B for authorizing legislation.) Local cooperation. Fully complied with. Terminal facilities. About 1,000 linear feet of privately owned docking space is availabe. Operations during fiscal year. Maintenance: Condition surveys, miscellaneous inspections and reports were performed by hired labor at a cost of $15,032. A contract for maintenance dredging was awarded and completed this FY at a cost of $77,820 removing approximately 6,564 cubic yards of material. Engineering, design, surveys, supervision and administration cost $19,665. Work authorized by earlier Act was completed in 1939. Work authorized in 1954 was completed in 1963. Total costs to end of FY were $1,283,044, of which $462,653 was for new work and $820,391 for maintenance. 12. DETOUR HARBOR, MI Location. On the west side of DeTour Passage, about 2 miles upstream from Lake Huron. The passage forms the mouth of the St. Marys River which connects Lakes Huron and Superior. (See NOAA Nautical Chart 14882.) Existing project. Provides for small boat harbor and harbor of refuge by dredging a 10-foot deep entrance channel and providing an 8-foot deep access channel protected by a 1,305-foot breakwater. The total estimated (October 1981) project cost is $2,650,000; the Federal cost is $1,400,000 and the non-Federal cost is $1,250,000 which is a cash contribution. Local cooperation. Fully complied with. Terminal facilities. Public docking, landing, parking and sanitary facilities will be provided by the State of Michigan. Operations during fiscal year. New Work: An adjustment was made on federal project at a cost of $5,975 contributed funds. Maintenance: Condition surveys were performed by Government forces at a cost of $3,900. Existing project is complete. Total cost to end of FY is $2,565,004, of which $5,658 was for maintenance and $2,559,346 for new work. 13. DETROIT RIVER, MI Location. One of the Great Lakes connecting channels, 31 miles long and flows south from Lake St. Clair to Lake Erie. (See NOAA Nautical Chart 14848.) Previous project. For details see page 1958 of Annual Report for 1915, and page 1541 of Annual Report for 1938. Existing project. Improving Detroit River main channels to provide 25.5-foot draft navigation; improving certain auxiliary and side channels; and construction of various water level and crosscurrent 31-6 DETROIT, MICHIGAN DISTRICT control structures. Details are in accompanying Table 31-C. Project depths are referred to local low water datum planes which correspond to low water datums for Lakes St. Clair and Erie, 571.7 and 568.6 feet above mean water level at Father Point, Quebec (International Great Lakes Datum-1955.) (See Table 31-B for authorizing legislation.) Estimated 1978 Federal cost for new work, exclusive of amounts expended on previous projects, is $159,300,- 000. Local cooperation. Fully complied with. No local cooperation is required for modifications authorized by Acts of July 1946 and March 1956. The Trenton Channel modification approved August 13, 1968 is considered inactive. Terminal facilities. Numerous commercial installations used for handling coal, iron ore, limestone, steel products, petroleum products, and other items such as overseas general cargo. Detail on actual port and harbor facilities is in Port Series No. 45 (revised 1972) prepared and published as part 2 by Board of Engineers for Rivers and Harbors. Information on port and steamship services is prepared and published as part I by Port Development Staff, U.S. Department of Commerce. Facilities are considered adequate for existing commerce. Operations during fiscal year. Maintenance: Condition surveys, support of water control center, Hi-Fix surveys, environmental studies, miscellaneous inspections and reports were performed by Government forces at a cost of $1,078,418. Studies, plans and specifications were completed for construction of. a wetland marsh under Section 150 of the Water Resources Development Act of 1967 at a cost of $87,351. Studies continued under extended navigation season at a cost of $327,179. Maintenance of disposal areas by hired labor cost $226,460. Location and removal of obstructions cost $1,304,895. The contract awarded last FY for dredging East Outer Channel was completed at a cost of $2,701,040, removing approximately 394,533 cubic yards, bin measure, of shoal material. The contract for dredging Pointe Mouillee Access Channel, N & S Interior Channel and N & S Turning Basin awarded last FY was completed, removing approximately 44,777 cubic yards of shoal material at a cost of $611,998. A contract for dredging Pointe Mouillee Access Channel and interior channels was awarded and completed this FY removing 48,052 cubic yards of shoal material at a cost of $481,356. A contract for dredging the East Outer and Lower Livingstone Channels was awarded and completed this FY removing 235,000 cubic yards of material at a cost of $1,96,061. Plans and specifications were completed for repair of the Pointe Mouillee disposal area at a cost of $7,763. A contract was awarded for this work late in the FY in the amount of $182,796. No work was performed this FY. Engineering, design, surveys, supervision and administration cost $249,559. Review of contractor's claim under the dike disposal program continued at a cost of $22,256. Latest modification of connecting channels project in the Detroit River is complete except for compensating works. All work in Trenton Channel is complete. Pertinent data concerning channels covered by project at end of FY are set forth in Table 31-C. Costs for existing project were $184,587,690, of which $74,780,103 was for new work ($72,969,197 regular funds and $1,530,688 Public Works Funds) and $109,807,587 for maintenance. 14. DULUTH-SUPERIOR HARBOR, MN AND WI Location. At extreme western end of Lake Superior. Cities of Duluth, MN, and Superior, WI, are on north and south sides, respectively. (See NOAA Nautical Chart 14975.) Previous projects. See page 1246 of Annual Report for 1962. Existing project. Provides for rebuilding canal piers at Duluth entry, replacement or construction of piers and breakwater at Superior entry and dredging approaches and channels within harbor, St. Louis Bay, and St. Louis River. Channels vary in depth from 32 to 28 feet in entrances, are 27 feet deep in iron-ore route channels, and are from 20 to 23 feet in inner channels. (See Table 31-B for authorizing legislation.) For details of authorized channel dimensions and dimensions of structures, see pages 1246 and 1247 of Annual Report for 1962 and page 1011 of Annual Report for 1965. Portion of project for deepening Twenty-first Avenue West channel is inactive. Estimated cost (1967) of this portion was $577,000. Local cooperation. Fully complied with for active portion of project. Terminal facilities. There are 113 docks or terminals including some 54 major ones; all but one are privately owned. Facilities for handling iron ore, coal, limestone, petroleum, steel and scrap iron, cement, general cargo, and grain are believed adequate for most existing commerce. Operations during fiscal year. Rehabilitation: A contract was awarded for rehabilitation of North and South Piers Sections O, N-1, N and M in the amount of $10,456,625. The contract is approximately 21% complete at a cost of $2,260,000. Supervision and administration cost $31,677. Maintenance: Condition surveys, environmental studies, support of water control center, cooperative stream gaging, miscellaneous inspections and reports were performed by Government forces at a cost of $245,877. Engineering and design for major rehabilitation of N. Pier Sections O, N-i, N and M and S Pier Sections O, N-i, N, and M was completed this FY at a cost of $218,182. Operation and maintenance of the 31-7 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 museum was performed by Government forces at a cost of $259,021. Operation and maintenance of service facilities and pier was performed at a cost of $74,493. Repairs to breakwater and seawalls were performed by the COLEMAN and MARKUS at a cost of $1,044,766. Maintenance of disposal area was performed by hired labor at a cost of $12,886. Minor hired labor for obstructions removal was performed by the MARKUS at a cost of $26,374. The contract for maintenance dredging awarded last FY was completed with 108,510 cubic yards removed this FY at a cost of $694,240. A contract for maintenance dredging was awarded this FY in the amount of $1,228,725. The contract is approximately 55% complete with 57,375 cubic yards of material removed at a cost of $750,000. Engineering, design, supervision and administration were performed at a cost of $167,936. Work authorized prior to 1960 Act was completed in June 1956. Under the 1960 Act, work on the outer harbor, included in House Document 150, was completed in June 1965. Work on the inner harbor, included in House Document 196, started in May 1963, was completed in November 1968 except for the 21st Avenue West channel portion which is inactive. The United States owns 34.90 acres of land in fee in Minnesota and Wisconsin of which 2.15 acres are used for a vessel yard. Total cost of existing project was $53,257,521, of which $16,109,258 was for new work, $34,856,586 for maintenance, and $2,291,677 for rehabilitation. 15. EAGLE HARBOR, MI Location. On the south shore of Lake Superior on the North Face of Keweenaw Point, 31 miles northeasterly from the Upper Entrance to Keweenaw Waterway. (See NOAA Nautical Chart 14964.) Existing project. Provides for a short entrance channel, a guide pier marking the entrance on the west side, and a harbor basin. Project depths are 14 feet in the entrance channel and 12 feet in the harbor basin. For additional details see page 1182 of Annual Report for 1959. (See Table 31-B for authorizing legislation.) Local cooperation. Fully complied with. Terminal facilities. An old L-shaped timber wharf is available but is in poor condition. A dock and launching ramp constructed by the State is located on the north side of the Harbor Basin. Operations during fiscal year. Maintenance: Condition surveys and environmental studies were performed at a cost of $593. The original project was completed in 1879. The modification for a small boat harbor was completed in 1959. Total cost to end of FY was $280,864, of which $205,164 was for new work and $75,700 for maintenance. 16. FOX RIVER, WI Location. Rises in Columbia County, WI, and flows about 176 miles northerly into Green Bay. Wolf River, physically a main river but by designation a tributary of Fox River, rises in central part of Fort County, WI, and flows southerly. (See NOAA Nautical Chart 14916 for Lake Winnebago and lower Fox River.) Previous projects. See page 1368 of Annual Report for 1962. Existing project. Deepening and widening channel of Fox River from DePere 7 miles above mouth to confluenceof Wolf River, a total length of 59 miles, to 6 feet, with 9.6 feet in rock cut below DePere lock and 7 feet in other rock cuts on lower river below Menasha lock; construction and reconstruction of 19 locks and 9 dams; a concrete retaining wall at Kaukauna; construction and maintenance of harbors having depths of 6 feet on Lake Winnebago; widening Neenah Channel to 100 feet, with a 6-foot depth for about 1 mile; and dredging, snagging, and otherwise improving Wolf River 47 miles from its mouth to New London, depth to be 4 feet. Cost of completed portion of project is $513,424 for the lower river exclusive of previous projects. River and Harbor Act of 1925 portion of project is considered inactive and excluded from cost estimate. Estimated cost (1924) of this portion is $2,886,000. (See Table 31-B for authorizing legislation.) Local cooperation. None required. Terminal facilities. Wharf and landing facilities are, in general, adequate for existing needs. (See Table 31-E on locks and dams, Fox River, WI.) Operations during fiscal year. Maintenance: Condition surveys, boundary monumentation, miscellaneous inspections and reports, safety training and plans for flood emergencies were performed at a cost of $12,984. The spillway at the Menasha Dam was resurfaced at a cost of $232,569. Federal canal banks at various locations were repaired at a cost of $42,454. The operation and maintenance of nine dams and ten overflow weirs and caretakers status maintenance of seventeen locks and two guard locks totaled $511,877. Tainter gates and seals were reconditioned at Kaukauna Dam and Cedars Dam at a cost of $89,452. Fox River O.S.H.A. Program and major miscellaneous items of supply totaled $6,106. Water control studies, and monitoring and regulation of water levels were performed at a cost of $179,643. Engineering and design costs were $9,463. Supervision and administration cost was $162,526. Existing project is complete except for the inactive portion. Nineteen original locks and nine original dams have been rebuilt. (See Table 31-E for year of completion of each). Structures and dredging in pools have increased original depths generally about 2 feet. 31-8 DETROIT, MICHIGAN DISTRICT Work remaining to complete project consists of dredging in upper portion of Wolf River, and rock removal and deepening of Neenah Channel on lower Fox River, which are no longer considered necessary. Existing lock and dams are generally in fair to good condition. Costs for existing project to end of FY were $8,753,334 for new work and $35,790,218 for operation and maintenance; a total of $39,543,552. Funds in the amount of $3,706,187 were expended between July 5, 1884, and June 30,1935, on operation and care of works of improvement under provisions of permanent indefinite appropriation for such purposes. 17. FRANKFORT HARBOR, MI Location. On east shore of Lake Michigan, 204 miles northeasterly from Chicago, IL, and 28 miles northerly from Manistee, MI. (See NOAA Nautical Chart 14907). Existing project. Provides for constructing an exterior basin in Lake Michigan formed by two breakwaters, 450 feet apart at the outer ends, diverging at an angle of about 90 degrees, the main arm and shore connection on north breakwater are 972 and 1,000 feet long, respectively, and the main arm and shore connection of south breakwater 1,188 and 1,400 feet long, respectively; for removing 801 feet of north and 1,172 feet of south pier; dredging basin 20 feet deep and 800 feet wide at entrance, decreasing toward new pier heads to 600 feet wide, dredging approach and entrance channel through outer basin to a depth of 24 feet from deep water in Lake Michigan to a point 500 feet landward of opening between breakwaters, over the entire width outside the breakwaters and to a maximum width of 500 feet inside the breakwaters; thence to 28 feet deep through inner portion of outer basin to outer end of north pier, over widths decreasing from 500 to 160 feet; and thence to 22 feet deep between the piers to the inner basin in Lake Betsie; dredging an 18-foot deep interior basin in Lake Betsie from within 50 feet of existing structures on the west and extending eastward about 1,550 feet to easterly boundary and from within 50 feet of existing structures on the north and extending southward 800 feet to the southerly boundary; dredging a recreational craft anchorage area 10 feet deep and 300 feet wide, extending 600 feet eastward of the east limit of the interior basin, with its north side in line with the north limit of the basin. Breakwaters and shore connections are built of concrete caissons and piling capped with concrete. Inner piers and revetments are built of stonefilled timber cribs and piling, all capped with concrete, except for 476 feet of south revetment which consists of steel sheet piling. (See Table 31-B for authorizing legislation.) Local cooperation. Fully complied with. Terminal facilities. Two car ferry slips on south shore and several docks along north shore of Lake Betsie. The City and State provide a recreational docking facility on north side of Lake Betsie which is open to all on equal terms. There is also a marine railway capable of handling small craft. Facilities are considered adequate for existing commerce. Operations during fiscal year. Maintenance: Condition surveys, environmental studies, miscellaneous inspections and reports were performed by Government forces at a cost of $34,806. The reconnaissance report for major rehabilitation of N. & S. Breakwater Sections A, B, C, D & E was completed at a cost of $8,262. An adjustment of $10,000 was made in prior years cost for repairs to navigation structures. Miscellaneous soil borings of the structures were taken at a cost of $17,056. Supervision and administration of the project cost $5,119. Close-out of the dike disposal project was performed at a cost of $23. Existing project was completed in 1939, with exception of the latest modification which was completed in 1969. Navigation structures are in good condition and programmed for major repair on an as needed basis. For additional details on completion of existing project see page 1474 of Annual Report for 1962. Total costs for existing project to end of FY were $9,661,155, of which $1,955,159 (including $31,709 contributed funds) was for new work, $7,431,220 for maintenance, and $274,776 for rehabilitation. 18. GRAND HAVEN HARBOR AND GRAND RIVER, MI Location. Harbor is on east shore of Lake Michigan, 108 miles northeasterly from Chicago, IL, and 23 miles northerly from Holland, MI. River rises in Jackson County, MI, and flows 260 miles westerly into Lake Michigan. (See NOAA Nautical Chart 14933, and Geological Survey Grand Rapids quadrangle.) Previous project. For details see page 1949 of Annual Report for 1915, and page 1481 of Annual Report for 1938. Existing project. An entrance channel protected by parallel piers and revetments at mouth of Grand River, a deep draft channel in river extending to Spring Lake, a turning basin, and a shallow draft channel in river extending 14.5 miles upstream to Bass River. Project depths are 23 feet in entrance channel, 21 feet in river to turning basin, 18 feet in turning basin and channel to Spring Lake, and 8 feet in upper Grand River channel. For additional details see page 1461 of Annual Report for 1962. Dredging on northerly side of inner channel is considered inactive. Estimated cost of this portion (1954) is $38,600. (See Table 31-B for authorizing legislation.) Local cooperation. Fully complied with. Terminal facilities. Several wharves exist for handling coal, limestone, sand and gravel, petroleum products, fish and miscellaneous commodities. There is also a car ferry slip which is inactive. The State and 31-9 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 local agencies provide recreational boating facilities which are open to all on equal terms. Facilities are considered adequate for existing commerce. Operations during fiscal year. Maintenance: Condition surveys, environmental studies, safety studies, miscellaneous inspections and reports were performed by Government forces at a cost of $105,899. The wave monitoring study initiated last FY was continued at a cost of $14,848. The U.S. Cranebarge MANITOWOC performed repairs to the navigation structures at a cost of $130,085. An adjustment of $10,000 was made for prior years cost for repairs to navigation structures. The contract awarded in FY 83 for repair to North Revetment Section C-1 and D and South Revetment Section L, M, N, O, and P was completed. Repairs of a portion of Sections D, E, and F were added by modification. Costs for this FY were added by modification. Cost for this FY for this work was $775,076 of which $251 was contributed by the City of Grand Haven. Maintenance of the disposal area was performed by hired labor at a cost of $289. An adjustment of -$2,342 was made to the maintenance dredging contract completed last FY. Two contracts for maintenance dredging were awarded and completed this FY. The first contract dredging the outer harbors removed approximately 39,710 cubic yards of shoal material at a cost of $184,788. This contract was also for beach nourishment. The second contract for dredging the inner harbor removed 14,306 cubic yards at a cost of $96,049. Engineering, design, surveys, supervision and administration cost $183,531. Contract cost for mitigation under Section 111 of P.L. 90-483 was $206,757. Monitoring activities cost $21,670. Engineering, design, surveys, supervision and administration cost $8,337. Existing project was substantially completed in 1949. For additional details on completion of existing project see page 1463 of Annual Report for 1962. Structures are generally in good condition; repairs are made on an as needed basis. Total costs of existing project to end of FY were $23,359,265, of which $1,458,469 was for new work, $21,087,183 for maintenance, and $813,613 for rehabilitation. 19. GRAND MARAIS HARBOR, MN Location. On north shore of Lake Superior, 106 miles northeasterly from Duluth, MN. (See NOAA Nautical Chart 14967.) Existing project. Provides breakwater piers to narrow the entrance; concrete seawalls across ledge at southeast corner of harbor; an anchorage area and a small-boat basin protected by a rubblemound breakwater. Project depths are 16 feet in anchorage area increasing to 20 feet near entrance and 8 feet in smallboat basin. For additional details see page 1014 of Annual Report for 1965. (See Table 31-B for authorizing legislation.) Local cooperation. Fully complied with. Terminal facilities. Two inactive pulpwood wharves and several fish wharves, all privately owned. Facilities are considered adequate for existing commerce. Operations during fiscal year. Maintenance: Condition surveys, and environmental studies were performed by Government forces at a cost of $23,117. Engineering and design for repairs to East & West Breakwater was completed at a cost of $67,677. A contract for repair of the East and West Breakwater was awarded this FY in the amount of $1,393,650. Approximately 12% of the contract was completed this FY at a cost of $170,473. Supervision and administration of this contract cost $10,922. Minor maintenance to navigation structures was performed by hired labor at a cost of $1,234. Existing project is complete. Total costs of existing project to end of FY were $2,576,737. 20. GRAND TRAVERSE BAY HARBOR, MI Location. At mouth of Traverse River on eastern shore of Keweenaw Peninsula about 20 miles northeasterly from Portage entry to Keweenaw Waterway. (See NOAA Nautical Chart 14964.) Existing projects. Provides two parallel piers, an entrance channel between piers and a harbor basin. Project depths are 12 feet between piers and 10 feet in basin. Project area extended 200 feet upstream in 1966. For additional details see page 1015 of Annual Report for 1965. (See Table 31-B for authorizing legislation.) Local cooperation. Fully complied with. Local interests furnished easements on 5.1 acres of land. Terminal facilities. Several privately owned fishing wharves. Facilities are considered adequate for existing commerce. Operations during fiscal year. Maintenance: Condition surveys, environmental studies, miscellaneous inspections and reports were performed by Government forces at a cost of $11,724. Supervision and administration of financial closeout of contract for repair of the South Revetment completed last FY cost $106. Existing project was completed in 1950 except for extension of north pier completed in 1964. Steel cells and piers are in good condition. Total cost of existing project to end of FY was $1,809,147. 21. GREEN BAY HARBOR, WI Location. At mouth of Fox River, at head of Green Bay, about 180 miles from Milwaukee, WI, via Sturgeon Bay Canal, and about 49 miles southwest of Menominee Harbor, MI, and WI. (See NOAA Nautical Chart 14918.) Previous projects. See page 1366 of Annual Report for 1962. 31-10 DETROIT, MICHIGAN DISTRICT Existing project. See Chicago District 1979 Annual Report, Table 30-C, p. 30-30. For more detailed description of project see page 1216 of Annual Report for 1963. Cost of completed portion of project is $9,335,000, Federal, and non-Federal cost is $490,000 including $100,000 contributed funds. Local interests requested that the inactive portion of the 1962 River and Harbor Act, consisting of dredging the reach from 150 feet downstream of the C.&N.W. Railway Bridge to 1,700 feet upstream of this bridge, be reactivated and the authorization modified to include deepening the adjacent turning basin and modifying the C.&N.W. Railway Bridge to provide increased horizontal clearance. Estimated cost of this portion (1984) is $5,110,000 Federal and $112,000 non-Federal. (See Table 31-B for authorizing legislation.) Local cooperation. Fully complied with. Terminal facilities. There are 16 wharves for handling coal, petroleum products, cement, limestone, general overseas cargo and miscelleneous commodities. Facilities are considered adequate for existing commerce. Operations during fiscal year. Maintenance: Condition surveys, environmental studies, miscellaneous inspections and reports were performed at a cost of $170,863. An adjustment of $20,000 was made in prior years cost for maintenance of navigation structures. Maintenance of the disposal area was performed by hired labor at a cost of $22,876. The contract.for maintenance dredging awarded last FY was completed this FY at a cost of $144,433 removing approximately 54,344 cubic yards of shoal material. A contract for maintenance dredging of the Bay Section was awarded and completed at a cost of $583,267 removing approximately 102,143 cubic yards of material. A contract was awarded for maintenance dredging of the Fox River in the amount of $908,200. No work was performed this FY. Engineering, design, surveys, supervision and administration cost $128,107. Engineering and design for construction of a confined disposal facility continued at a cost of $390,568. Existing project is complete. The 1962 modification was started in November 1966 and completed in September 1973. Dredging turning basin above Chicago & Northwestern Railways Bridge was commenced in August 1938. The turning basin was enlarged under authority of Section 5 of the River and Harbor Act of March 4,1915, in order to provide sufficient area for the large ships that use it. The work was performed as part of a maintenance dredging contract in September and October 1973. East revetment at Grassy Island was entirely removed in July 1935. Dredging Fox River and entrance channel to Tail Point Light was completed in September 1967. The total costs of the existing project were $30,454,274, of which $18,005,884 were regular funds and $940,800 Public Works funds; $10,016,806 for new work and $20,437,468 for maintenance. The new work costs do not include $100,000 contributed funds. 22. HAMMOND BAY HARBOR, MI Location. On northwest shore of Lake Huron, 35 miles southeast of Straits of Mackinac. (See NOAA Nautical Chart 14881.) Existing project. Provides for aharbor of refuge, protected by breakwater structures, extending to 12-foot depth contour in the lake; for dredging a harbor basin 10 feet deep; and for dredging an entrance channel 12 feet deep. Local cooperation. Fully complied with. Terminal facilities. Public facilities being planned by State and local agencies. Plans and specifications are complete, but construction has not started. Operations during fiscal year. Maintenance: Condition surveys, miscellaneous inspections and reports were performed by Government forces at a cost of $9,318. An adjustment of $10,000 was made in prior years cost for repairs to navigation structures. Repairs to navigation structures were performed by hired labor using the U.S. Cranebarge MANITOWOC at a cost of $37,675. Supervision and administration cost $1,848. Environmental studies in connection with the Section 111 project were performed at a cost of $2,669. The existing project was completed in 1965. Total costs of existing project to end of FY were $1,529,823, of which $1,092,366 was for new work and $437,457 for maintenance. 23. HARBOR BEACH HARBOR, MI Location. On west shore of Lake Huron about 60 miles north of Port Huron, MI. (See NOAA Nautical Chart 14862.) Existing project. Harbor of refuge protected by three breakwaters; a main entrance 23 feet deep; and an anchorage area 21 feet deep. For additional details see page 1485 of Annual Report for 1962. (See Table 31-B for authorizing legislation.) Local cooperation. None required. Terminal facilities. Coal and limestone are received at a private wharf. In addition, there is a public recreational craft pier, a Coast Guard pier, and several small installations engaged in docking and servicing light-draft commercial and recreational vessels. These facilities satisfy current commerce and traffic requirements. Operations during fiscal year. Maintenance: Condition surveys, miscellaneous inspections and reports were performed by Government forces at a cost 31-11 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 of $18,588. Engineering and design for major structure repairs to the main breakwater was performed at a cost of $60,109. A contract for lease of equipment with operating personnel to dredge the new marina was awarded and completed at a cost of $411,440 removing approximately 30,000 cubic yards of material. Engineering, design, surveys, supervision and administration cost $35,444. Existing project was completed in 1928. For additional details on completion of existing project see page 1485 of Annual Report for 1962. Total costs to end of FY were $7,354,529, of which $1,200,598 was for new work, $5,959,427 for maintenance, and $194,504 for rehabilitation. 24. HARRISVILLE HARBOR, MI Location. On the west shore of Lake Huron, 20 miles north of Oscoda and 30 miles south of Alpena. (See NOAA Nautical Chart 14864.) Existing project. A harbor of refuge protected by breakwater structures, and dredging an entrance channel 12 feet deep and a harbor basin 10 feet deep. (Sel Table 31-B for authorizing legislation.) Local cooperation. Fully complied with. Terminal facilities. Dockage facilities built by State and local agencies for recreational craft; considered adequate for existing commerce. Operations during fiscal year. Maintenance: Condition surveys, environmental studies, miscellaneous inspections and reports were performed by Government forces at a cost of $3,376. Condition surveys and environmental studies in conjunction with the Section 111 project cost $11,137. Total costs of project to end of FY were $3,429,453, of which $2,666,877 was for new work (includes $263,239 contributed funds) and $762,576 for maintenance. 25. HOLLAND HARBOR, MI Location. On east shore of Lake Michigan 95 miles northeasterly from Chicago, IL, and 23 miles southerly from Grand Haven, MI. (See NOAA Nautical chart 14932.) Previous project. For details see page 1948 of annual Report for 1915 and page 1478 of Annual Report for 1938. Existing project. An outer breakwater protected approach channel in Lake Michigan, an entrance channel to Lake Macatawa protected by piers and revetments, a channel through Lake Macatawa into Black River, and a turning basin. Project depths are 23 feet in outer portion of approach channel decreasing to 21 feet at outer end of inner piers, 21 feet to upper end of project, and 18 feet in turning basin. For additional details see page 1458 of Annual Report for 1962. Widening bend of entrance channel into Lake Macatawa is in an active category as a result of a reclassification recommendation approved by the Office of the Chief of Engineers on August 20,1981. Estimated cost of this portion (1984) is $3,370,000 Federal and $100,000 non-Federal. (See Table 31-B for authorizing legislation.) Local cooperation. Fully complied with for completed portions of project. Work authorized by Act of 1954 is subject to condition that work on either or both proposed modifications may be undertaken by the United States provided local interests furnish all lands except 1.5 acres of Federal lands, easements, rights-ofway, and suitable spoil disposal areas for initial work and future maintenance; remove buildings and other structures, except existing revetments, from lands to be furnished; and hold the United States free from damages. Terminal facilities. Wharves are at inner end of Lake Macatawa, and used for handling coal, building materials, petroleum products, and miscellaneous commodities. Two shipbuilding yards are on south shore of the lake. Holland provides a public wharf for small craft. Facilities are considered adequate for existing commerce. Operations during fiscal year. Maintenance: Condition surveys, environmental and safety studies, miscellaneous inspections and reports were performed by Government forces at a cost of $72,951. An adjustment of $20,000 was made for repairs to navigation structures from prior years. Repairs to navigation structures were performed this FY by hired labor at a cost of $106,421. An adjustment of -$10,001 was made in the maintenance dredging contract terminated last FY due to lack of shoaling. A contract for maintenance dredging was awarded and completed this FY at a cost of $240,170 removing approximately 141,789 cubic yards of material. Another contract for maintenance dredging of the inner harbor was awarded and completed at a cost of $408,248 with approximately 55,000 cubic yards of material removed. An adjustment of $14,182 was made to the contract completed last FY for repairs to North & South Breakwaters and the North Pier. Maintenance of the disposal area was performed by hired labor at a cost of $4,295. Engineering, design, surveys, supervision and administration cost $78,297. Surveys, environmental studies, and miscellaneous inspections in connection with Section 111 were performed at a cost of $23,980. Beach nourishment in conjunction with above maintenance dredging contract cost $40,000. A contract for mitigation of shore damage was awarded this FY and is 75% complete at a cost of $336,750. Engineering, design, supervision and administration cost $21,127. . Existing project, with exception of widening bend in revetted entrance channel authorized by Act of September 3, 1954, was completed in 1957. For 31-12 DETROIT, MICHIGAN DISTRICT additional details on completion of existing project, see page 1460 of Annual Report for 1962. Costs of existing projecttoendofFYwere$1,392,827fornewwork($1,180,502 regular funds, $176,620 for previous project and $35,705 contributed funds), $14,185,165 regular funds for maintenance, and $502,452 regular funds for rehabilitation, for a total of $16,080,444. 26. THE INLAND ROUTE, MI Location. A series of interconnected lakes and streams stretching across northern tip of Lower Peninsula of Michigan, and extends from Conway near Lake Michigan to Cheboygan on Lake Huron; a distance of 35 miles. Crooked and Indian Rivers are connecting channels in the waterway. (See NOAA Nautical Chart 14886.) Existing project. Provides for a channel 30 feet wide and 5 feet deep, with necessary widening at bends, through Crooked and Indian Rivers, and Crooked, Burt, and Mullett Lakes, and from Conway (west end of Crooked Lake) to navigation lock at Cheboygan; in Pickerel Channel from Pickerel Lake to Crooked Lake. It also provides for suitable jetties at head of Indian River. The addition of a lock and dam was approved by the Chief of Engineers on September 2, 1964, to correct a design deficiency. (See Table 31-B for authorizing legislation.) Local cooperation. Fully complied with. Terminal facilities. None exist for commercial cargo-handling along the Crooked and Indian Rivers. Numerous small privately owned timber piers and wharves, some equipped with covered boat wells for serving and storing recreational craft, have been constructed. Landings maintained by hotel and resort operators are open to the public for transfer of passengers. Public docks are at Conway and Oden on Crooked Lake; the Village of Indian River, Topinabee, and Mullett Lake Village on Mullett Lake; and at Cheboygan. About 30 highways dead end at the water's edge, permitting public access for various marine activities. Dock facilities are considered adequate for existing traffic. Operations during fiscal year. Maintenance: The navigation lock was operated and maintained by the Village of Alanson at a cost of $58,498. An adjustment of -$2,437 was made in the cost during FY 84 by the Village of Alanson. Close-out cost for operation of the lMocikch idguanri nwga sp $r2ev2,i5o5u4s. Ifnis c1a9l8 5y ethare sl obcky wthaes oSptaertea teodf only on weekends from April 21 through April 29 from 93:00 0it a w.ma.s toop 5e:n0 0f rpo.mm. ;9 f:r0o0m a .Mm.a y 5 through September to 9:00 p.m. Condition 'surveys, cooperative stream gaging, miscellaneous inspections and reports were performed by Government forces at a cost of $12,108. The existing project was completed in 1958. The lock and dam was completed in FY 1968. For additional details see page 1382 of Annual Report for 1960. Total costs to end of FY were $3,463,690, of which $770,222 was for new work and $2,545,468 for maintenance, with $148,000 contributed by local interests. 27. KENOSHA HARBOR, WI Location. On west shore of Lake Michigan about 35 miles south of Milwaukee and about 54 miles north of Chicago. (See NOAA Nautical Chart 14904.) Previous projects. See page 1390 of Annual Report for 1962. Existing project. For detailed description see page 1237, Annual Report for 1963. Estimated (1984) Federal cost is $693,000 exclusive of amounts expended on previous projects and $43,000 non-Federal which includes $3,000 local contribution. (See Table 31-B for authorizing legislation.) Local cooperation. Fully complied with. Terminal facilities. Three wharves used for miscellaneous foreign overseas commodities and autos, and also several fishing wharves. While these facilities are considered generally adequate for existing commerce, more efficient use of existing terminals and utilization of available frontage for development of additional terminals should be made. Operations during fiscal year. Maintenance: Condition surveys, environmental studies, miscellaneous inspections and reports were performed by Government forces at a cost of $47,678. Maintenance of the disposal area was performed by hired labor at a cost of $48,451. Engineering, design, supervision and administration cost $11,276. Existing project is complete except for dredging 25- foot strips adjacent to the north and south piers which will be completed after rehabilitation of the piers. The north and south piers were completed in 1900 and the breakwater in 1909. The north pier is in excellent condition. The south pier and breakwater are in generally good condition. The total costs of the existing project to end of FY were $8,902,826, of which $7,907,899 were regular funds and $27,658 Emergency Relief funds; $524,355 being for new work, $7,108,196 for maintenance, and $1,270,275 for rehabilitation. The new work costs do not include $3,000 contributed funds. 28. KEWAUNEE HARBOR, WI Location. On west shore of Lake Michigan, about 105 miles north of Milwaukee, W, and about 78 miles fmroomut hG orfe eKne Bwaayu,n veeia RSitvuerrg. e(oSnee B NaOy ACAan aNla. uHtiacrabl oCr hisa artt 14908.) Previous projects. See page 1375 of Annual Report for 1962. 31-13 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Existing project. See Chicago District 1979 Annual Report, Table 30-C, p. 30-31. Costs of completed project are $603,021, Federal, and $9,000 non-Federal, exclusive of amount expended on previous projects. Uncompleted portion (estimated $200,000-July 1965) of 1935 River and Harbor Act is considered inactive, and excluded from present cost estimate. The portion authorized by the 1960 River and Harbor Act was deauthorized in 1977. (See Table 31-B for authorizing legislation.) Local cooperation. Fully complied with. Terminal facilities. Two car-ferry slips, a petroleum tank farm, a Corps of Engineers project office, and several fishing wharves. Facilities are considered adequate for existing commerce. Operations during fiscal year. Maintenance: Condition surveys, miscellaneous inspections and reports were performed by Government forces at a cost of $28,600. An adjustment of $20,000 was made in prior years cost for repairs to navigation structures. Repairs to diked disposal area were performed by hired labor at a cost of $101,382. Minor repairs to navigation structures were performed by hired labor at a cost of $4,096. An adjustment of $10,544 was made to the contract completed last FY for repairs to the confined disposal facility. An adjustment of -$114 was made to the maintenance dredging contract completed last FY. A dye tracer study was performed by Government forces at the confined disposal facility at a cost of $5,000. Engineering, design, surveys, supervision and administration cost $48,624. Active portion ofexisting project is complete. The north pier was completed in 1897 and the remaining portion is in generally good condition. Rehabilitation of the south pier was completed in June 1967. Construction of north breakwater and shore connection, except for a gap of 150 feet about 830 feet from shoreward end, and removal of outer 706.5 linear feet of north pier was commenced in September 1935 and completed in June 1937. Removed 500 linear feet of north pier in April/ May 1963 and widened and deepened the adjacent channel in 1965. Outer end of the north pier was struck and severely damaged by car ferry vessel in October 1973 and a 24-foot section at outer end was subsequently removed, thus reducing the structure to a length of 626 feet. Dredging entrance channel in interior basin to existing project depth was commenced in April and completed in October 1938. Kewaunee River is navigable to about 6.5 miles above mouth for craft drawing not more than 4 feet. Total cost of existing project to end of FY was $7,641,399, of which $758,333 was for new work ($183,021 regular and $420,000 Emergency Relief funds) $6,271,766 regular funds for maintenance, and $617,300 regular funds for rehabilitation. 29. KEWEENAW WATERWAY, MI Location. In Lake Superior across Keweenaw Peninsula in upper peninsula of Michigan. The west entrance is 169 miles east of Duluth, MN. (See NOAA Nautical Chart 14972.) Existing project. A navigable channel, minimum width 300 feet, 25 miles long, partially natural and partially artificial, across Keweenaw Peninsula via Portage Lake. For details see page 1121 of Annual Report for 1963. Completed cost for new work is $5,967,700. Portion of project providing for extension of lower entrance breakwater and necessary alteration or replacement of structures due to deepening channels is inactive and excluded from foregoing cost. Estimated cost (1957) of this portion was $3,315,000. (See Table 31-B for authorizing legislation.) Local cooperation. None required. Terminal facilities. Six coal docks, a petroleum dock, and several general merchandise and miscellaneous wharves, all privately owned. Facilities are considered adequate for existing commerce. Also present is a government constructed recreational area with facilities to include a picnic area and small boat landing range. Operations during fiscal year. Maintenance: Condition surveys, safety studies, and miscellaneous inspections and reports were performed by Government forces at a cost of $36,260. Engineering and design for major repairs of the upper entry revetment was continued at a cost of $121,585. Safety maintenance was performed by hired labor at a cost of $51,200. The derrickbarge COLEMAN performedbreakwaterrepairs at a cost of $212,989. Engineering, design, surveys, boundary monumentation, supervision and administration cost $16,251. Engineering and design for construction of a confined disposal facility continued at a cost of $70,506. Active portion of the project is complete. Breakwaters are in generally good condition except for a weakness occurring in about 300 feet of substructure of breakwater lower entrance, and major storm damage repairs needed for stone-covered portions of breakwater at upper entrance. Mooring pier at Lily Pond requires repairs to halt movement and permit dredging to project depth adjacent thereto. The flared revetment at the upper entry should be modified to restrict wave action from the stilling basin entrance. Total costs of existing project to end of FY were $17,073,402, of which $5,974,141 was for new work, and $11,099,261 for maintenance. 30. KNIFE RIVER HARBOR, MN Location. Near mouth of Knife River on north shore of Lake Superior, 19 miles northeasterly from 31-14 DETROIT, MICHIGAN DISTRICT Duluth, MN, and 7 miles southwest of Two Harbors, MN. (See NOAA Nautical Chart 14966.) Existing project. Provides for an entrance channel with a system of overlapping breakwaters, using the existing breakwater and anew breakwater constructed of 731 feet of rock rubblemound. The entrance channel is 9 feet deep and an inner straight channel is 8 feet deep, 50 feet wide, and 600 feet long with a public marina and side channel at its inner end. For additional details see page 1110 of Annual Report for 1963. A modification to correct a design deficiency was authorized in 1974. (See Table 31-B for authorizing legislation.) Total estimated approved Federal cost (1984) is $2,521,700 and $21,700 non-Federal cost. Local cooperation. Local interests are to furnish easements on 15.08 acres of land. Terminal facilities. Local interests have installed pile-and-timber docks on both sides of straight channel. Lake County has completed construction by contract of a marina along the east wing of the inner harbor. Operations during fiscal year. Maintenance: Condition surveys, miscellaneous inspections and reports were performed by Government forces at a cost of $9,432. Minor structure repairs were performed by hired labor using government plant at a cost of $22,678. Project was completed in June 1958. Breakwater and spending beach are in good condition. The existing breakwater does not effectively prevent waves caused by northeasterly winds from entering the entrance channel. This results in unsatisfactory and unsafe harbor entrance conditions during storms. Mooring conditions in the main channel and Y-branches of the inner harbor are also adversely affected. Plans and specifications for the construction of a breakwater to correct a design deficiency to reduce wave damage and improve navigation conditions were completed and approved by NCD in 1982. Total project costs to end of FY were $695,146, of which $412,945 was for new work and $282,201 for maintenance. 31. LA POINTE HARBOR, WI Location. At westerly end of Madeline Island in the Apostle Island group off the south shore of Lake Superior. (See NOAA Nautical Chart 14973.) Existing project Provides for reconstruction of 73.5 feet of the existing breakwater, extending the breakwater 126.24 feet with 5 new steel sheet pile cells, harbor dredging and related work. The harbor is 10 feet deep in the entrance and 8 feet deep in the basin. Project was authorized by Section 107 of the 1960 River and Harbor Act (Public Law 645, 86th Cong., as amended.) Local cooperation. Fully complied with. Terminal facilities. A 400-foot L-shaped dock was constructed and rehabilitated by local interests, not as a part of the Federal project. Operations during fiscal year. Maintenance: Condition surveys, environmental studies, miscellaneous inspections and reports were performed by Government forces at a cost of $11,572. The existing project was completed in 1967. Total cost of existing project at end of FY is $216,859. 32. LAC LA BELLE HARBOR, MI Location. On south shore of Lake Superior on eastern shore of Keweenaw Peninsula, 41 miles northeasterly from Portage entry to Keweenaw Waterway. Lac La Belle, Bete Grise Bay, and Mendota Ship Canal combine to form the harbor. (See NOAA Nautical Chart 14964.) Existing project. Provides for construction of two parallel piers at the entrance having lengths of 584 and 682 feet for north and south piers, respectively; for an entrance channel between the piers 50 feet wide and 12 feet deep, about 820 feet long with a flared approach; and for an inner canal 50 feet wide and 10 feet deep, about 730 feet long. For additional details see page 1039, Annual Report for 1964. (See Table 31-B for authorizing legislation.) Local cooperation. Fully complied with. Terminal facilities. Several small, privately owned wharves are available in the harbor for use of small craft engaged in fishing and recreational activities. A state owned dock for small craft is located at northwest corner of Lac La Belle Bay. Operations during fiscal year. Maintenance: Condition surveys and environmental studies were performed by Government forces at a cost of $542. Minor structure repairs were performed by hired labor at a cost of $4,738. The existing project was completed in 1960. Controlling depths are about 11 feet in the approach channel and 10 feet in the inner channel. Total costs of existing project to end of FY were $742,191, of which $269,270 was for new work and $472,921 for maintenance. 33. LAKE ST. CLAIR, MI CHANNELS Location. Lake St. Clair, a section of Great Lakes connecting channels, is an expansive shallow basin having a vessel track length of about 15 miles from mouth of St. Clair River to head of Detroit River. (See NOAA Nautical Chart 14850.) Previous project. For details see page 2882, Annual Report for 1896; pages 1957-58, Annual Report for 1915; and page 1539, Annual Report for 1938. Existing project. An improved channel through Lake St. Clair 800 feet wide, 27.5 feet deep, and about 14.5 miles long; extending from mouth of Southeast Bend cutoff channel at lower end of St. Clair River to 31-15 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 head of Detroit River Channel. (See Table 31-B for authorizing legislation.) Local cooperation. None required. Terminal facilities. None. Operations during fiscal year. Maintenance: Condition surveys, Hi-Fix surveys, support of Water Control Centers, environmental studies, inspections and reports were performed atacostof $143,342. Environmental studies in connection with the extended navigation season cost $139,235. Maintenance of disposal area was performed by hired labor at a cost of $11,867. Engineering and design for removal of the trestle at Dickinson Island disposal area was contracted at a cost of $4,651. Total costs for existing project at end of FY were $19,669,286, of which $7,675,357 was for new work ($6,010,582 regular funds and $1,008,595 public works funds) and $11,993,929 for maintenance. 34. LELAND HARBOR, MI Location. A light-draft harbor on eastern shore of Lake Michigan at mouth of Carp River, about 40 miles north of Frankfort, MI, and 40 miles southwest of Charlevoix, MI. (See NOAA Nautical Chart 14912.) Existing project. Provides for a harbor of refuge consisting of a breakwater about 1,200 feet long, a protected anchorage and maneuver area about 3 acres in extent and 10 feet deep, a 12-foot deep flared approach channel decreasing in width to 90 feet, an existing south pier 440 feet long, a 35-foot long cellular extension to south pier, an entrance channel 6 feet deep and 40 feet wide extending to mouth of Carp River, and for elimination of existing north pier. (See Table 31-B for authorizing legislation.) Local cooperation. Fully complied with. Terminal facilities. Privately owned wharves on each side of river below the dam which is 400 feet above the river mouth. These wharves serve the local fishing interests and recreational craft. Public facilities are operated by the State and local agencies. All available dockage space is utilized. Operations during fiscal year. Maintenance: Condition surveys, environmental studies, miscellaneous inspections and reports were performed by Government forces at a cost of $7,480. An adjustment of -$565 was made for the dredging contract awarded and completed last FY. A contract was awarded and completed for maintenance dredging this FY removing approximately 15,384 cubic yards of shoal material at a cost of $48,966. Engineering, design, surveys, supervision and administration cost $6,383. The existing project was completed in 1932 except for the 1962 authorization which was completed in 1967. The total costs to end of FY were $2,506,002, of which $1,027,089 was for new work, $1,408,235 for maintenance, and $70,678 for rehabilitation. 35. LEXINGTON HARBOR, MI Location. On southwest shore of Lake Huron, 20 miles north of Port Huron, MI. (See NOAA Nautical Chart 14862.) Existing project. Provides for two offshore breakwaters opening to the southeast and totaling about 2,400 feet long with provisions for recreational fishing on the main breakwater; an anchorage and maneuver area of about 5 acres, 8 feet deep; and a flared approach channel 10 feet deep, decreasing to 160 feet in width through the breakwaters. Project also provides for recreational fishing facilities. Estimated (1979) Federal cost for new work is $1,647,306 excluding $1,088,888 to be contributed by local interests. (See Table 31-B for authorizing legislation.) Local cooperation. Assurances of local cooperation were furnished by Michigan Department of Natural Resources to the Secretary of the Army. The cash contribution was $1,088,888. Terminal facilities. An existing public fishing pier of open pile construction is not adequate for existing and prospective commerce. Complete boating facilities are planned by State and local agencies in connection with the harbor construction. Operations during fiscal year. Maintenance: Condition surveys, inspections and reports were performed by Government forces at a cost of $4,125. Monitoring, inspection and reports under Section 111 were performed by Government forces at a cost of $27,091. A contract for beach nourishment was awarded this FY and is approximately 16% complete at a cost of $60,777. Engineering, design, supervision and administration were performed at a cost of $14,116. The existing project was completed during FY 1977. Total costs of existing project were $3,533,009, of which $3,107,192 (includes $1,088,888 contributed funds) was for new work and $425,817 for maintenance. 36. LITTLE LAKE HARBOR, MI Location. On south shore of Lake Superior 21 miles west of Whitefish Point and 30 miles east of Grand Marais, MI. (See NOAA Nautical Chart 14962.) Existing project. Provides for a small-craft harbor of refuge by dredging an entrance channel 12 feet deep from Lake Superior into Little Lake, suitably protected by breakwaters and revetments. (See Table 31-B for authorizing legislation.) Local cooperation. Fully complied with. Terminal facilities. Only terminal facility at project site consists of a public dock built by State of Michigan for light-draft craft. 31-16 DETROIT, MICHIGAN DISTRICT Operations during fiscal year. Maintenance: Condition surveys and environmental studies were performed by Government forces at a cost of $8,190. The design deficiency study continued at a cost of $950. An adjustment of -$1,304 was made in cost for maintenance dredging contract completed last FY. A maintenance dredging contract was awarded and completed this FY for $226,218, with approximately 38,368 cubic yards of shoal material removed. Engineering, design, surveys, supervision and administration cost $22,932. This project is considered complete; however, because of shifting sand, the harbor entrance shoals rapidly with the result that full project depth is not usually available. An analysis for the Design Deficiency Report was submitted to North Central Division in March 1978 and approved. Total cost at end of FY is $3,081,364. 37. LUDINGTON HARBOR, MI Locaton. On east shore of Lake Michigan, 156 miles northeasterly from Chicago, IL, and 67 miles northerly from Grand Haven, MI. (See NOAA Nautical Chart 14937.) Previous project. For details see page 1951 of Annual Report for 1915, page 1491 of Annual Report for 1938, and page 1307 of Annual Report for 1963. Existing project. Provides for an exterior basin in Lake Michigan protected by north and south breakwater, north breakwater is 1,800 feet long and south breakwater 1,700 feet long, 550 feet apart at outer ends, diverging at an angle of 90 degrees, with shore connections, 1,103 and 2,004 feet long, respectively; for dredging exterior basin to 18 feet deep with a maximum width of 1,500 feet; for a channel with a depth of 29 feet from deep water in Lake Michigan decreasing to 27 feet at the westt heen d of the north pier, over a maximum width of 600 feet; thence a channel with a depth of 27 feet, over a minimum width of 230 feet with necessary widening at Pere Marquette Lake; and for inner piers and revetments 1,649 feet long on north and sufficiently long on the south for turn at Pere Marquette Lake. The estimated (1977) Federal cost for new work is $8,250,000. Estimated total costs for local interests is $147,000. (See Table 31-B for authorizing legislation.) Local cooperation. Has been complied with. Terminal facilities. In addition to main terminal of Chesapeake & Ohio Railway Co., consisting of three car ferry slips, a wharf, and warehouses, there are several wharves which handle coal, limestone, and miscellaneous commodities. Facilities adequate for existing commerce. Operations during fiscal year. Maintenance: Condition surveys, environmental studies, miscelleneous inspections and reports were performed by Government forces at a cost of $37,329. An adjustment of $20,000 was made for hired labor repairs to navigation structures for previous years. Hired labor structure repairs were performed this FY using the cranebarge MANITOWOC at a cost of $67,166. Maintenance of safety features was performed at a cost of $7,124. A contract for dredging the outer portion was awarded and completed at a cost of $172,900 removing approximately 175,000 cubic yards of material. Engineering and design for structure repairs to Section D and E South Breakwater was performed at a cost of $65,883. Engineering, design, surveys, supervision and administration cost $50,320. Under the Section 111 program, $650,539 was expended on the above contract for beach nourishment. Surveys, monitoring, supervision and administration cost $42,257. Existing project was completed in 1918. For additional details on completion of existing project see page 1469 of Annual Report for 1962. Total costs for existing project to end of FY were $17,637,540, of which $8,532,202 was for new work, $8,747,425 for maintenance, and $357,913 for rehabilitation. 38. MACKINAW CITY HARBOR, MI Location. On east shore of extreme northern tip of Lower Peninsula of Michigan, on southerly shore of Straits of Mackinac. (See NOAA Nautical Chart 14881.) Existing project. Provides for a breakwater, about 430 feet long, perpendicular to existing railroad pier; wave absorbing slope protection for about 300 feet along harbor side of railroad pier; an entrance channel 10 feet deep with a minimum width of 100 feet, and a protected anchorage and maneuver area about 3.3 acres in extent with depths varying from 6 to 8 feet; and maintenance of outer 200-foot portion of existing north breakwater. (See Table 31-B for authorizing legislation.) Local cooperation. Fully complied with. Terminal facilities. Additional public facilities are being planned by State and local agencies in addition to existing facilities owned by the Village of Mackinaw City but leased to a private marina operator. Operations during fiscal year. Maintenance: Condition surveys were performed by Government forces at a cost of $2,525. Minor repairs to structures were performed by hired labor at a cost of $13,490. Supervision and administration cost $837. Existing project is completed. Total costs of existing project to end of FY are $333,014, of which $272,572 (includes $136,286 contributed funds) was for new work and $60,442 for maintenance. 39. MANISTEE HARBOR, MI Location. On east shore of Lake Michigan, 179 miles northeasterly from Chicago, IL, and 26 miles 31-17 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 northerly from Ludington, MI (See NOAA Nautical Chart 14938.) Previous project. For details see page 1952 of Annual Report for 1915, and page 1493 of Annual Report for 1938. Existing project. An entrance channel in Lake Michigan protected by a breakwater, piers, and revetments; a channel in Manistee River to Manistee Lake; and Federal participation in cost of replacing Maple Street Bridge. Project depths are 25 feet in entrance channel and 23 feet in river channel. For additional details see page 1470 of Annual Report for 1962. (See Table 31-B for authorizing legislation.) Local cooperation. Fully complied with. Terminal facilities. Installations are on both sides of river and on Manistee Lake. Commerce handled includes coal, sand, salt, and general cargo. In addition, there is a Government wharf and a State and City owned recreational craft pier which is open to the public. These facilities satisfy current commerce requirements. Operations during fiscal year. Maintenance: Condition surveys, safety studies, inspection and reports were performed by Government forces at a cost of $26,102. Repairs to navigation structure were performed by hired labor at a cost of $2,483. Engineering and design for repair of N. revetment, Sec. F, G and H were performed at a cost of $7,579. Supervision and administration costs were $90. Existing project was completed in August 1967. For additional details on completion of existing project see page 1470 of Annual Report for 1962. Total costs for existing project from regular funds to end of FY were $8,406,039, of which $2,696,522 was for new work, $4,335,353for maintenance, and $1,374,164 for rehabilitation. 40. MANISTIQUE HARBOR, MI Location. On north shore of Lake Michigan, 135 miles northeasterly from Green Bay Harbor, WI, and 220 miles northerly from Milwaukee, WI. (See NOAA Nautical Chart 14908.) Previous project. For details see page 1933 of Annual Report for 1915, and page 1422 of Annual Report for 1938. Existing project. A breakwater protected entrance channel in Lake Michigan, a channel in Manistique River, and a pier at river mouth. Project depths are 19 feet in outer portion of entrance channel, 18 feet in inner portion of entrance channel, and 18 feet in river channel. For additional details see page 1451 of Annual Report for 1962. (See Table 31-B for authorizing legislation.) Local cooperation. Fully complied with. Terminal facilities. A car ferry slip, two coal and building material wharves, two fishing wharves, and numerous lumberyard slips. Facilities are considered adequate for existing commerce. Operations during fiscal year. Maintenance: Environmental studies, miscellaneous inspections and reports were performed by Government forces at a cost of $5,000. Total costs to end of FY were $3,477,333, of which $1,299,355 was for new work, $1,861,645 for maintenance and $316,333 for rehabilitation. 41. MANITOWOC HARBOR, WI Location. On west shore of Lake Michigan about 79 miles north of Milwaukee and about 106 miles from Green Bay via Sturgeon Bay Canal. (See NOAA Nautical Chart 14922.) Previous projects. See page 1379 of Annual Report for 1962. Existing project. The total estimated (Oct 1981) project cost is $3,080,000; the Federal cost is $1,085,000 and the non-Federal cost is $1,995,000, which is a cash contribution. See Chicago District Annual Report for 1979, Table 30-C. For detailed description see page 1228 of Annual Report for 1963. Estimated costs (1970) of new work for 1968 modification are $81,000 Federal and $30,000 non- Federal which includes a cash contribution of $18,000. Work on the 1968 modification was postponed until 1982. The portion authorized by the 1962 River and Harbor Act is inactive and estimated (1970) at $1,150,- 000, Federal, and $105,000 non-Federal. (See Table 31- B for authorizing legislation.) Construction of a small boat harbor within the existing harbor was authorized by the Chief of Engineers, June 26, 1979, and 720-foot channel extension reaffirmed in July 1982, under authority of Section 107, 1960 River and Harbor Act, as amended. Local cooperation. Fully complied with for complete modifications. For 1968 modification local interests must make an annual cash contribution equivalent to 50% of the annual costs associated with construction and maintenance of the channel extension until such time that a second user utilizes the channel extension. Such a contribution is presently estimated at $14,200; provide without cost to the United States all lands, easements, and rights-of-way required for construction and subsequent maintenance, including suitable areas determined by the Chief of Engineers to be required in the general public interest for initial and subsequent disposal of dredged materials, and the necessary retaining dikes, bulkheads, and embankments therefor or the costs of such retaining works; hold and save the United States free from damages due to the construction works and subsequent use, operation, and maintenance of the project, not including damages due to the fault or negligence of the United States or its contractors; provide and maintain without cost to the 31-18 DETROIT, MICHIGAN DISTRICT United States adequate berthing areas at the docks adjacent to the improvement; accomplish at no cost to the United States all relocations and alterations of utilities necessary for the project; assume full responsibility for all project first costs in excess of the Federal cost limitation of $2,000,000; and comply with the Uniform Relocation Assistance and Real Property Acquisition Policies Act of 1970. Terminal facilities. Three car-ferry slips, a grain elevator, one shipbuilding yard, and three other wharves used for handling coal, building materials, cement, and miscellaneous commodities. While these facilities are considered adequate for existing commerce, it is believed the City should provide a suitable wharf with warehouse and railway connection open to the general public. Operations during fiscal year. Maintenance: Condition surveys, environmental studies, miscellaneous inspections and reports were performed by Government forces at a cost of $113,781. Structure repairs were performed by hired labor at a cost of $7,230. An adjustment of -$47,682 was made for the South Breakwater repair contract completed last FY. Hired labor repairs to the disposal area were performed at a cost of $13,413. Dye tracer studies were performed at the disposal area at a cost of $2,811. Engineering and design for repairs to the confined disposal facility was initiated at a cost of $24,851. A contract for repairs to the confined disposal facility was awarded this FY at a cost of $199,550. Engineering, design, supervision and administration cost $11,489. Existing project is completed except for the 1962 modifications. The 1962 modification is inactive. The Federal modification, adopted July 15, 1985, included the expansion of the new entrance channel to the Section 107 project and extension of the rubblemound breakwater. The breakwater, completed in 1910, is in generally fair condition. Dredging a channel through the outer basin to existing project depth and removal of a portion of old north stub pier at the river entrance were completed in December 1937. Dredging river channel was completed in July 1942. Cost of existing project was $3,959,990 for new work (includes $1,911,076 contributed funds) and $7,682,655 for maintenance, a total of $11,642,645. 42. MARQUETTE HARBOR, MI Location. In Marquette Bay on south shore of Lake Superior, 160 miles west of Sault Ste. Marie, MI, and 265 miles east from Duluth, MN. (See NOAA Nautical Chart 14970.) Existing project. Provides for a breakwater, and a harbor basin 26.5 feet deep, giving a protected area of 350 acres. Project was modified in 1960 to provide a 27-foot depth in harbor area. (See Table 31-B for authorizing legislation.) Local cooperation. None required for earlier authorizations. Fully complied with for the 1960 Act. Terminal facilities. One ore dock, unused at present; two coal docks; one petroleum dock; and three other unused docks. There are also several small fish wharves without railroad connections. Facilities are considered adequate for existing commerce. Operations during fiscal year. Maintenance: Condition surveys, inspections and reports were performed by Government forces at a cost of $7,360. Repairs to navigation structures were performed by hired labor at a cost of $14,196. Total costs of existing project to end of FY were $3,350,655. 43. MENOMINEE HARBOR AND RIVER, MI AND WI Location. On west shore of Green Bay, about 49 miles northeast of Green Bay Harbor, and about 155 miles from Milwaukee via Sturgeon Bay Canal. (See NOAA Nautical Chart 14917.) Previous projects. See page 1361 of Annual Report for 1962. Existing project. See Chicago District Annual Report 1979, Table 30-C, page 30-26. For detailed description see page 1214, Annual Report for 1963. The portion authorized by 1960 River and Harbor Act is inactive and estimated (1964) at $442,000 Federal, and $105,000 non-Federal. Costs of completed new work exclusive of inactive work and amount expended on previous projects are $221,053 Federal and $50,762 non-Federal, which includes a cash contribution of $36,762. (See Table 31-B for authorizing legislation.) Local cooperation. Fully complied with for completed work. Terminal facilities. There are 9 wharves for handling coal, limestone, pulp and miscellaneous commodities. City of Marinette, WI, provided a public wharf. Facilities are considered fairly adequate for existing commerce, except that there is need for a public wharf owned by City of Menominee, with warehouse and railway connection. Operations during fiscal year. Maintenance: Condition surveys, miscellaneous inspections and reports were performed by Government forces at a cost of $30,447. Minor repairs to navigation structures were performed by hired labor at a cost of $2,029. A contract for repairs to South pier Section D was awarded and completed at a cost of $72,300. Engineering, design, supervision and administration cost $18,506. Engineering and design for construction of a confined disposal facility was performed at a cost of $101,568. The project in effect prior to the modification of March 2, 1945 was completed in 1938. No additional work was necessary under the modification of March 2, 31-19 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 1945 to provide a depth of 12 feet in the extension of the channel to the vicinity of the Marinette Yacht Club, as project depth or more was available. The entrance piers were completed in 1884, were rehabilitated (1954-1964) and are in excellent condition. Dredging of the channel below the Marinette municipal wharf, together with enlarging the turning basin to existing project depth, was commenced in May 1938. Modification of the project authorized by the 1960 River and Harbor Act is inactive. Construction for the 1967 modifications was started August 17,1968 and completed in October 1968. The costs of the existing project were $570,238 for new work (includes $36,762 contributed funds), $2,257,348 for maintenance and $1,351,852 for rehabilitation, a total of $4,179,438. 44. MILWAUKEE HARBOR, WI Location. On west shore of Lake Michigan about85 miles north of Chicago, IL, and about 83 miles west of Grand Haven, MI. (See NOAA Nautical Chart 14924.) Previous projects. See page 1385 of Annual Report for 1962. Existing project. See Chicago District Annual Report for 1979, Table 30-C, page 30-26. For detailed description see page 1282 of Annual Report for 1963. Completed new work costs are $6,937,804 Federal and $478,000 non-Federal, exclusive of amount expended on previous projects. The uncompleted portion authorized by the 1935 River and Harbor Act was placed in the inactive category in June 1973. Estimated costs are $119,000 (July 1972) Federal and $1,170,000 (July 1972) non-Federal for this portion. Uncompleted portion 1945 River and Harbor Act was deauthorized in 1977. (See Table 31-B for authorizing legislation.) Local cooperation. Complied with for Acts of March 2, 1945, October 23, 1962, and July 14, 1960, except inactive portion of 1945 Act. Act of August 30, 1935, provided that original dredging of outer harbor area be done by City of Milwaukee and City of Milwaukee be reimbursed at actual cost but not to exceed 10 cents per cubic yard, place measurement, for original dredging done subsequent to authorization of work by Congress. Agreement covering dredging was executed by Secretary of Way, February 23,1934, after this work was originally authorized as part of public works program. City was reimbursed for 10 percent of dredging. Terminal facilities. Four car-ferry slips, and 57 other wharves, private and municipal, used for handling coal, grain, building materials, cement, petroleum products, and miscellaneous commodities. As facilities in inner harbor were inadequate for existing commerce, Milwaukee Harbor Commission has constructed nine docks in the outer harbor for handling general cargo. Operations during fiscal year. Rehabilitation: A contract for major rehabilitation of the North Pier and North Breakwater was awarded this FY at a cost of $5,540,000. The contractor began mobilizing and receiving steel sheet piling and work is 31% complete at a cost of $1,900,427. Engineering and design during construction, supervision and administration cost $40,325. Maintenance: Condition surveys, environmental studies, support for the water control center, miscellaneous inspections and reports were performed by Government forces at a cost of $171,284. The General Design Memorandum for major rehabilitation of the Inner North Revetment and the detached North Breakwater was completed at a cost of $404,689. An adjustment of $19,785 was made for hired labor structure repairs from previous years. A reimbursement of - $564,373 was made by the Scinida Steam Navigation Company, Ltd., for contract repairs costs. Hired labor maintenance of the diked disposal facility was performed at a cost of $12,542. A dye tracer study at the confined disposal facility cost $5,199. Engineering and design, leading to award of a contract for major rehabilitation of the Inner North Revetment and North Breakwater, was completed at a cost of $100,399. Other engineering, design, surveys, supervision and administration cost $18,792. Existing project is complete except for inactive portions. The 1962 modification was completed in July 1967. North breakwater and shore connection,- 9,954 feet long, was completed in August 1925. North pier was completed in 1905 and construction of south pier was completed in November 1910. Construction of south breakwater and shore connection was completed in October 1929. Before modification of August 30, 1935, City of Milwaukee also dredged most of the area in the outer harbor south of inner entrance piers and lakeward of pierhead line to more than 21 feet below datum without cost to the United States. City of Milwaukee also dredged a portion of the area of the outer harbor north of inner entrance piers to provide an approach channel to the passenger and auto pier opposite East Claybourn Street. Work on the 1945 modification was completed in August 1957, except for the inactive portion which consists of dredging the Milwaukee River from Buffalo Street to upper limit of the project at Humbolt Avenue. In recent years, some repairs were completed on the north shore breakwater; however, additional repairs are required. South breakwater and shore connections are in generally good condition. Costs of existing project were $8,231,024 for new work, $30,533,998 for maintenance, and $3,832,562 for rehabilitation; a total of $42,597,584. 45. MONROE HARBOR, MI Location. On lower reach of River Raisin, which empties into Lake Erie and is 36 miles south of Detroit, 31-20 DETROIT, MICHIGAN DISTRICT MI. (See NOAA Nautical Chart 14830.) Existing project. Provides for a channel in Lake Erie and River Raisin to City of Monroe, for a turning basin, and for riprapping protecting dikes at river mouth. Project depths are 21 feet to turning basin, 18 feet in turning basin, and 9 feet to upstream end of project. For additional details see page 1490 of Annual Report for 1962. Project feature for riprapping protecting dikes is considered inactive. Estimated costs of this feature (1954) is $90,000. (See Table 31-B for authorizing legislation.) Local cooperation. Fully complied with. Terminal facilities. Several privately owned docks and a municipal terminal. Port of Monroe Authority built a steel and concrete wharf on southeast side of turning basin for commercial use. Facilities are considered adequate for existing commerce. Operations during fiscal year. Maintenance: Condition surveys, environmental studies, miscellaneous inspections and reports were performed by Government forces at a cost of $70,154. Maintenance of the disposal facility was performed by hired labor at a cost of $30,237. The maintenance dredging contract awarded last FY was completed at a cost of $209,530 removing approximately 63,593 cubic yards. A contract for maintenance dredging was awarded this FY in the amount of $2,597,149. It is approximately 50% completed with 390,758 cubic yards being removed at a cost of $1,506,345. Engineering, design surveys, supervision and administration cost $119,794. The contract for construction of a confined disposal facility was completed this FY at a cost of $816,410. Engineering during construction, supervision and administration cost $208,047. Total costs to end of FY were $50,711,914, of which $987,340 was for new work (including $300,000 contributed by the Port Commission of Monroe), and $49,724,574 for maintenance including $166,667 contributed funds. ($125,000 by Consolidated Paper Company and $41,667 by River Raisin Company.) 46. MUSKEGON HARBOR, MI Location. On east shore of Lake Michigan, 114 miles northeasterly from Chicago, IL, and 80 miles easterly from Milwaukee, WI (See NOAA Nautical Chart 14934.) Previous project. For details see page 1950 of Annual Report for 1915; page 1399, Annual Report for 1924; and page 1484, Annual Report for 1938. Existing project. A breakwater protected outer basin in Lake Michigan and an entrance channel from Lake Michigan to Muskegon Lake protected by piers and revetments. Project depths vary from 29 feet in the lakeward portion of the outer basin to 27 feet in the channel between the inner piers to Muskegon Lake. For additional details see page 1303 of Annual Report for 1963. (See Table 31-B for authorizing legislation.) Local cooperation. Fully complied with. Terminal facilities. Several privately owned wharves primarily for commercial use. Details on actual port and harbor facilities are in Port Series, No. 48 (revised 1973) prepared and published as part 2 by Board of Engineers for Rivers and Harbors. Information on port terminal services and charges, and steamship services is prepared and published as part I by the Port Development Staff, U.S. Department of Commerce. Facilities are considered adequate for existing commerce. Operations during fiscal year. Rehabilitation: The contract awarded last FY for major rehabilitation of the North and South Breakwater and South Revetment is 83% complete at a cost of $4,799,308. Engineering, design, supervision and administration cost $196,821. Maintenance: Condition surveys, environmental studies, miscellaneous inspections and reports were performed by Government forces at a cost of $78,746. Hired labor repairs to navigation structures were performed at a cost of $9,897. An adjustment of -$8,229 was made for the maintenance dredging contract completed last FY. Engineering, design, surveys, supervision and administration cost $10,178. Condition surveys and environmental monitoring were performed in conjunction with the authorized Section 111 project at a cost of $34,955. Existing project, including latest project modification, was completed in 1965. For additional details on completion of existing project see page 1465 of Annual Report for 1962. Total costs to end of FY were $20,920,476, of which $3,017,110 was for new work, $5,640,392 for maintenance, and $12,262,974 for rehabilitation. 47. NEW BUFFALO HARBOR, MI Location. At mouth of Galien River on southeast shore of Lake Michigan in Berrien County, about 45 miles easterly from Chicago, IL. (See NOAA Nautical Chart 14905.) Local cooperation. Fully complied with. Existing project. Provides for an entrance channel 10 feet deep by 80 feet wide and 850 feet long, to mouth of Galien River; new north and south breakwaters 1,305 and 740 feet long, respectively, and deepening inner channel to Galien River to 8 feet wide and 1,250 feet long. (See Table 31-B for authorizing legislation.) Terminal facilities. One village owned boat ramp and three privately operated marinas, and a private boat club facility. Operations during fiscal year. Maintenance: Condition surveys, environmental studies, miscellaneous inspections and reports were performed at a cost of $20,993. A contract for maintenance dredging was 31-21 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 awarded and completed this FY at a cost of $62,604 removing approximately 9,795 cubic yards of material. A contract for beach nourishment was awarded this FY. The contract is approximately 9% complete at a cost of $60,000. Engineering, design, surveys, supervision and administration cost $29,418. Existing project is complete. Total costs to end of FY were $3,593,921, of which $1,285,716 was for new work and $2,308,205 for maintenance. Contributed funds were in the amount of $1,186,467. 48. OCONTO HARBOR, WI Location. On the west shore of Green Bay, about 31 miles northeasterly from Green Bay Harbor, WI, and about 25 miles southwesterly from Menominee Harbor, MI and WI, at mouth of Oconto River. (See NOAA Nautical Chart 14910.) Previous project. For details see page 1187 of Annual Report for 1958. Existing project. See Chicago District Annual Report 1979, Table 30-C, page 30-27. For detailed description see page 1187, Annual Report for 1958. (See Table 31-B for authorizing legislation.) Local cooperation. Fully complied with. Terminal facilities. Two municipally owned wharves of 400 and 100 foot frontage, respectively,; for miscellaneous freight, open to general public use. Facilities considered adequate for existing commerce. Operations during fiscal year. Maintenance: Condition surveys and environmental studies were performed at a cost of $26,473. Total costs for existing project to end of FY were $1,217,575, of which $130,754 was for new work and $1,086,821 for maintenance. 49. ONTONAGON HARBOR, MI Location. On south shore of Lake Superior. It consists of improvement of mouth of Ontonagon River. (See NOAA Nautical Chart 14965.) Previous project. For details see page 1931 of Annual Report for 1915, and page 1406 of Annual Report for 1938. Existing project. Provides for approach channel 16 feet deep, a channel between piers with 17 and 15- foot depths, an inner basin 12 feet deep, and maintenance of channels, basin, and entrance piers. Completed 1p9r6o6je cfto cro sdte $ta1i9l,s6.1 9A. Smeeo dpiafgicea 1ti1o0n0 oafu Athnonruizael dR ebpyo r1t9 f6o2r River and Harbor Act provides for increasing depths of channels, construction of an inner basin and a sedimentmaatitoend bcoassti n(.1 9T6h5i)s opf othrtiiso wn oorfk p irs o$j6e,c0t4 i0s ,0in00a.c t(iSveee. (TEasbtlie- 31-B for authorizing legislation.) Local cooperation. None required for earlier authorization. See page 1020 of Annual Report for 1965 for requirements of 1962 Act. Terminal facilities. There are no publicly owned wharves. There are three coal wharves, an oil receiving facility, and a few small fish wharves. Facilities are considered adequate for existing commerce. Operations during fiscal year. Maintenance: Condition surveys and environmental studies were performed by Government forces at a cost of $22,835. The reconnaissance report of the East Pier and revetment was completed at a cost of $1,079.. Engineering and design for major repairs to navigation structures was performed at a cost of $48,739. Repairs to navigation structures were performed by hired labor using the derrickbarge COLEMAN at a cost of $119,753. A contract for maintenance dredging was awarded and completed this FY at a cost of $293,689, removing approximately 71,800 cubic yards of shoal material. Engineering, design, surveys, supervision and administration cost $55,570. All work authorized under previous Acts was completed in 1938. Work authorized under the 1962 Act is in an inactive status. Total costs of existing project to end of FY were $7,302,638, of which $532,348 was for new work and $6,770,290 for maintenance. 50. PENTWATER HARBOR, MI Location. On east shore of Lake Michigan, 146 miles northeasterly from Chicago, IL, and 14 miles southerly from Ludington, MI. (See NOAA Nautical Chart 14907.) Existing project. Provides for widening old entrance channel to 150 feet between parallel piers and revetments, channel to extend from Lake Michigan to Pentwater Lake, with a depth of 16 feet. Piers and revetments are built of stonefilled timber cribs and piling and capped with concrete. The 200-foot extension to south pier portion of project is considered inactive. Estimated cost (1954) of this portion is $65,100. (See Table 31-B for authorizing legislation.) Local cooperation. None required. Terminal facilities. Several small privately owned wharves on west end of Pentwater Lake. The City and Michigan Waterways Commission jointly constructed a dock on northwest side of Pentwater Lake for public use. Facilities are considered adequate for existing commerce. Operations during fiscal year. Maintenance: Condition surveys, environmental studies, inspections and roef p$o1r7t,2s 1w1e. reS opiel rbfoorrminegds boyf nGaovviegrantmionen st tfrourccteus raets aw ceorset cpoenrftorramcte wda as ta aw coasrtd oefd $ a4n8d,9 c2o2m. Apl meteadin tthenisa FnYce rdermedovgiinngg approximately11,242 cubic yards of shoal material at a cost of $90,230. Engineering, design, supervision and administration cost $12,976. 31-22 DETROIT, MICHIGAN DISTRICT Existing project was completed in 1959 except for a 200-foot extension to the south pier which is not considered necessary under present conditions. For additional details see page 1468 of Annual Report for 1962. Total costs for existing project at end of FY were $3,004,761, of which $179,899 was for new work, and $2,824,862 for maintenance. 51. PETOSKEY HARBOR, MI Location. This harbor is on the east shore of Lake Michigan about 50 miles south of the Straits of Mackinac. (See NOAA Nautical Chart 14913.) Previous project. For details see page 1954 of Annual Report for 1915, page 1547 of Annual Report for 1931, and page 2024 of Annual Report for 1949. Existing project. Provides for a breakwater extending from shore 1,345 feet long of stone-filled timber crib, concrete capped, and rubblestone construction which protects the municipal pier. (See Table 31-B for authorizing legislation.) Local cooperation. None required. Terminal facilities. There is a municipal pier which is about 635 feet long plus several recreational craft piers. These installations satisfy current commerce and traffic requirements. Operations during fiscal year. Maintenance: Condition surveys, environmental studies, inspection and reports were performed by Government forces at a cost of $9,189. Repairs to navigation structures were performed using the cranebarge MANITOWOC at a cost of $195,065. Supervision and inspection cost $9,551. Existing project was completed in 1908. Total costs to end of FY were $655,390. 52. POINTE LOOKOUT HARBOR (AU GRES RIVER), MI Location. At Au Gres River on westerly shore of Lake Huron at entrance to Saginaw Bay, about 17 miles northeast of mouth of Saginaw River. (See NOAA Nautical Chart 14868.) Existing project. Provides for construction of a small boat harbor having a 12-foot deep, 100-foot wide, 2,800-foot long outer entrance channel; a 5,600-foot long, 100-foot wide inner entrance channel having a 10-foot depth; an 8,270-foot long 6-foot deep river channel ending just downstream from U.S. 23 highway bridge and having a width of 60 feet; a 4,000-foot long north breakwater and a 3,800-foot long south breakwater. (See Table 31-B for authorizing legislation.) Local cooperation. Fully complied with. Terminal facilities. Small boat marina facilities are under construction by the State of Michigan. Operations during fiscal year. Maintenance: Condition surveys, environmental studies, miscellaneous inspections and reports were performed by Government forces at a cost of $11,354. An adjustment of $30,000 was made for hired labor structure repairs from previous years. Minor maintenance to navigation structures was performed at a cost of $173. A contract for repair of East and West Breakwater was awarded for $1,894,000. The contract is 10.3% complete at a cost of $195,082. An adjustment of $167 was made to the dredging contract completed last FY. Engineering, design, value engineering, supervision and administration cost $54,921. Existing project was completed in 1974. Total costs to end of FY were $3,824,059, of which $2,642,584 was for new work and $1,181,475 for maintenance. 53. PORT AUSTIN HARBOR, MI Location. On west shore of Lake Huron at extreme southeastern limit of Saginaw Bay, and 29 miles south of Au Sable River (Oscoda). (See NOAA Nautical Chart 14863.) Existing project. A harbor of refuge at the mouth of Bird Creek, consisting of a harbor basin dredged to a depth of 10 feet protected by a breakwater structure, and for dredging an entrance channel to the harbor basin to a depth of 12 feet. (See Table 31-B for authorizing legislation.) Local cooperation. Fully complied with. Terminal facilities. A number of docks near mouth of Bird Creek and a State-owned dock inside breakwater. Facilities accommodate recreational craft and are considered adequate for existing traffic. Operations during fiscal year. Maintenance: Condition surveys, miscellaneous inspections and reports were performed by Government forces at a cost of $2,717. Engineering and design for addition of shore connection to breakwater was performed this FY at a cost of $43,609. A contract for the Breakwater Access was awarded at a cost of $441,173. No work was performed this FY. Supervision and administration cost $2,202. Total costs of existing project to end of FY were $2,361,923, of which $1,128,334 was for new work (includes $172,100 contributed funds) and $1,233,599 for maintenance. 54. PORTAGE LAKE HARBOR, MI Location. On east shore of Lake Michigan about 186 miles northeasterly from Chicago, IL, and about 37 miles northerly from Ludington, MI. (See NOAA Nautical Chart 14939.) Existing project. Provides for a harbor of refuge with an entrance channel from Lake Michigan to Portage Lake protected by piers and revetments. Project depth is 18 feet. For additional details see page 1297 of Annual Report for 1958. (See Table 31-B for authorizing legislation.) 31-23 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Local cooperation. None required. Terminal facilities. There are landing places and marinas at inner end of Portage Lake. Facilities are considered adequate for existing commerce. Operations during fiscal year. Maintenance: Condition surveys, inspectons and reports were performed by Government forces at a cost of $8,554. Existing project was substantially completed in 1912. For additional details on completion of existing project see page 1298 of Annual Report for 1958. The structures are generally in fair condition. Total cost of existing project to end of FY is $1,681,049. 55. PORT SANILAC HARBOR, MI Location. On southwest shore of Lake Huron, 30 miles north of Port Huron, MI. (See NOAA Nautical Chart 14862.) Existing project. Provides for a harbor of refuge protected by breakwater structures extending to 12- foot depth contour in lake; for dredging a harbor basin 10 feet deep; for dredging an entrance channel 12 feet deep; a 70-foot extension of the south breakwater; a 300-foot arm added to the north breakwater; and riprap placed at the lakeward side of the breakwater additions. (See Table 31-B for authorizing legislation.) Local Cooperation. Fully complied with. Terminal facilities. There is one privately owned dock used principally as a fishing terminal by owner and a municipally owned pier for recreational craft. Facilities are considered adequate for existing commerce. Operations during fiscalyear. Maintenance: Condition surveys, environmental studies, inspections and reports were performed by Government forces at a cost of $4,182. Minor repairs to navigation structures were performed by hired labor at a cost of $5,370. Inspection and reports under Section 111 mitigation were performed at a cost of $54,539. A contract for beach nourishment was awarded this FY and is approximately 16% complete at a cost of $7,984. Engineering and design, supervision and inspection of this contract cost $8,798. The project was completed in 1951 except for latest modification which was completed in FY 76. The breakwaters are in good condition. Total costs of existing project to end of FY were $4,037,453 (includes $2,120,593 contributed funds). 56. wPOIRT WASHINGTON HARBOR, Location. On the west shore of Lake Michigan, about 53 miles south of Manitowoc and about 29 miles north of Milwaukee, WI. (See NOAA Nautical Chart 14904.) Previous project. For details, see page 1938 of Annual Report for 1915, page 1459 of Annual Report for 1938, and page 30-14 of Chicago District Annual Report for 1975. Existing project. See Chicago District Annual Report for 1979, Table 30-C, page 30-27. Construction of a small boat harbor within the existing harbor was authorized by the Chief of Engineers, June 12, 1975, under authority of Section 107, 1960 River and Harbor Act, as amended. Local cooperation. Fully complied with. Terminal facilities. There is one coal wharf, a petroleum tank farm and several fishing wharves. City provided a wharf which is open to public use. Facilities considered adequate for existing commerce. Operations during fiscal year. Maintenance: Condition surveys, environmental studies, inspections and reports were performed by Government forces at a cost of $14,443. Minor repairs to navigation structures by hired labor were performed at a cost of $6,584. The existing project was completed in 1936. The 1958 modification was deauthorized in 1977. Total costs to end of FY were $6,436,302, of which $4,017,709 was for new work, and $2,418,593 for maintenance. 57. PORT WING HARBOR, WI Location. On south shore of Lake Superior, 34 miles easterly from Duluth, MN. (See NOAA Nautical Chart 14966.) Existing project. Provides for two parallel piers at entrance, 835 and 1,017 feet long, respectively, 200 feet apart; an entrance channel between piers 150 feet wide with 15-foot depth; an irregular-shaped turning basin 15 feet deep at inner end of piers from which two inner channels with 8-foot depth extend. One of these is 60 feet wide extending southerly for 340 feet and one 70 feet wide extending easterly 1,170 feet. Portion of dredging of entrance channel to complete project width and depth is considered unnecessary to meet present navigation requirements. (See Table 31-B for authorizing legislation.) Local cooperation. Fully complied with. Terminal facilities. There are four privately owned fishing wharves which are considered adequate for existing conditions. Operations during fiscal year. Maintenance: Condition surveys, miscellaneous inspections and reports were performed by Government forces at a cost of $31,434. A contract for maintenance dredging was awarded and completed this fiscal year at a cost of $180,229 removing approximately 15,500 cubic yards of shoal material. Engineering, design, surveys, supervision and administration cost $25,199. Existing project is complete except channel between piers and has been dredged to only a 100-foot width. 31-24 DETROIT, MICHIGAN DISTRICT Widening the channel an additional 50 feet was considered unnecessary to meet present navigation requirements. That work was classified inactive and deauthorized on August 5, 1977 under Section 12 of Public Law 93-251. Piers are in good condition. At end of FY, controlling depth was 12 feet in lake approach, 10 feet between piers in northerly portion of turning basin, and 8 feet in easterly inner channel. Lands owned by the United States total 7.80 acres. Total costs to end of FY are $894,284. 58. PRESQUE ISLE HARBOR, MI Location. On south shore of Lake Superior at Marquette, MI. It is an indentation about 1.5 miles long and one-half mile wide in shore behind Presque Isle Point. (See NOAA Nautical Chart 14970.) Existing project. A breakwater off Presque Isle Point and dredging harbor to depth of 28 feet at inner portion with 30 feet at entrance. For details see page 1021 of 1965 Annual Report. (See Table 31-B for authorizing legislation.) Local cooperation. Fully complied with. Terminal facilities. One merchandise and petroleum receiving wharf and one ore dock. Facilities are considered adequate for existing commerce. Operations during fiscal year. Maintenance: Condition surveys, environmental studies, inspections and reports were performed by Government forces at a cost of $6,904. An adjustment of -$2,173 was made in the dredging contract completed last FY. Engineering, design, supervision and administration cost $2,601. Project authorized by earlier Acts was completed in 1939. A contract for harbor deepening authorized by 1960 Act was completed in April 1962, except for a section where rocks were encountered in southeast portion of harbor. Rock removal has been accomplished intermittently by hired labor and the project is completed. Breakwater is in good condition. A Section 111 project was approved byChief of Engineers in October 1981 providing a rock groin, beach restoration and nourishment program at vicinity of Shiras Park and 3,000 feet west of park. Total costs of existing project to end of FY are $2,050,895. 59. RACINE HARBOR, WI Location. On west shore of Lake Michigan about 26 miles south of Milwaukee, WI, and about 64 miles north of Chicago, IL, (See NOAA Nautical Chart 14925.) Previous project. See page 1389 of Annual Report for 1962. Existing project. See Chicago District Annual Report for 1979, Table 30-C, page 30-27. For detailed description see page 1235, Annual Report for 1963. New work for project as completed cost $777,775, exclusive of amounts expended on previous projects and exclusive of inner 300 linear feet of pile pier and 450 linear feet of rubblemound originally part of south breakwater but no longer considered necessary. (See Table 31-B for authorizing legislation.) Construction of a small boat harbor within the existing harbor was authorized by the Chief of Engineers, June 26, 1979, under authority of Section 107, 1960 River and Harbor Act, as amended; however has not been constructed. Local cooperation. Fully complied with. Terminal facilities. Five wharves used for handling coal, limestone, petroleum products, and fish. City provided a public wharf. Operations during fiscal year. Maintenance: Condition surveys, inspection and reports were performed by Government forces at a cost of $23,324. Miscellaneous maintenance was performed by hired labor at a cost of $759. Environmental studies, inspections and reports for Section 111 were performed at a cost of $18,075. A contract for dredging in connection with Section 111 was awarded and completed at a cost of $22,582 removing approximately 1,245 cubic yards of material. Surveys, supervision and administration cost $3,263. Existing project was substantially completed in 1946. Construction of north breakwater and shore connection was completed in November 1918. Removal of old north pier was completed in 1913. Construction of south breakwater and shore connection and removal of old south pier were commenced in June 1916 and completed in December 1924. Removal of outer shoals, widening and deepening channels through outer basin to existing project depth and width, and dredging of river channel began in July, and was completed in November 1946. Total costs of existing project to end of FY were $9,566,030, of which $1,332,315 was for new work, $6,980,070 for maintenance, and $1,253,645 for rehabilitation. 60. ROUGE RIVER, MI Location. Rises in Oakland and Washtenaw Counties, MI, 30 miles long, flows southeasterly through Wayne County, and joins Detroit River at westerly limit of City of Detroit. (See NOAA Nautical Chart 14854.) Previous project. For details see page 1530 of Annual Report for 1932, and page 1558 of Annual Report for 1938. Existing project. Provides for: (a) Main channel from Detroit River through Short Cut Canal extending to upstream limit of the project, a distance of 3.5 miles. Project depths are 25 and 21 feet in navigation channel, 21 feet in turning basin, and 13 feet in upper reach of project. (b) Old channel from Detroit River extending to junction of Old Channel with Short Cut Canal. Project depths are 25, 18, 17, and 21 feet. For additional details see page 1324 of Annual Report for 1963. In 1973, work authorized by the 1962 River and Harbor Act was reclassified from the active to inactive category. Esti- 31-25 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 mated cost (1972) of this work is $880,000. Except for dredging 25-foot channel 1,150 feet upstream from mouth of Old Channel, work authorized in Act of August 30,1935, is considered inactive. Estimated cost (1958) of inactive portion is $255,000. Work authorized by Act of July 3,1958 is considered inactive. Estimated cost (1960) of this work is $210,000. (See Table 31-B for authorizing legislation.) Local cooperation. Act of October 23, 1962, requires local interests to provide lands and rights-of-way for construction upon request of the Chief of Engineers; hold the United States free from damages; provide terminal facilities to accommodate prospective commerce considered in report of District Engineer; dredge and maintain areas between the Federal improvement and terminal facilities to depths commensurate with improved Federal channel; make alterations in docks, bulkheads and other structures, and take such other measures as may be necessary to assure stability of banks adjacent to channel; and provide bridge protection. The assurances of local cooperation for the River and Harbor Act of 1962 were furnished by the Michigan State Waterways Commission and accepted on January 7,1965. Fulfillment of all items of local cooperation has not been accomplished. Terminal facilities. Numerous large commercial docks for handling various type cargo. Details on actual port and harbor facilities are contained in the Port Series No. 45 (revised 1972) prepared and published as part 2 by the Board of Engineers for Rivers and Harbors. Information on port administration and Federal services, port and terminal services and charges, and steamship services is prepared and published as part 1 by the Port Development Staff, U.S. Department of Commerce. Facilities are considered adequate for existing commerce. Operations during fiscal year. Maintenance: Condition surveys, environmental studies, inspections and reports were performed by Government forces at a cost of $68,168. An adjustment was made for the maintenance dredging contract completed last FY in the amount of $26,209 and 6,165 cubic yards. A contract was awarded and completed this FY for maintenance dredging, removing approximately 40,412 cubic yards of shoal material at a cost of $633,449. Engineering, design, supervision and administration was performed at a cost of $108,936. Review of the claim for the dike disposal contract was continued at a cost of $4,885. Work authorized before 1962 modification is complete or deauthorized. For additional details on completion of existing project see Annual Report for 1962. Total costs for existing project to end of FY were $30,213,255, of which $675,251 was for new work and $29,538,004 for maintenance. In addition, $29,563 was expended for new work from Emergency Relief Act Funds. 61. SAGINAW RIVER, MI Location. Formed by union of Tittabawassee and Shiawassee Rivers, 22 miles long, and flows northerly into extreme inner end of Saginaw Bay, Lake Huron. Cities of Saginaw and Bay City are on the river. (See NOAA Nautical Chart 14867.) Previous project. For details, see page 1957 of Annual Report for 1915, and page 1550 of Annual Report for 1938. Existing project. Provides for an entrance channel 27 feet deep and 350 feet wide from 27-foot contour in Saginaw Bay to river mouth; thence a channel 26 feet deep and 200 feet wide to New York Central Railroad Bridge at Bay City; thence 22 feet deep and 200 feet wide to C&O Railroad Bridge in Saginaw; thence 16.5 feet deep and 200 feet wide to upstream limit at Green Point. Project also provides for five turning basins; one 25 feet deep at Essexville, 600 feet wide with a maximum length of 1,850 feet; one 22 feet deep on east side of channel about 1 mile upstream from Cass Avenue in Bay City, 650 feet wide and 1,000 feet long, one 20 feet deep at Carrollton, 100 to 300 feet wide and 900 feet long; one 20 feet deep just downstream from C&O Bridge in Saginaw, 650 feet wide and 1,000 feet long; and one 15 feet deep between Bristol Street Bridge and New York Central Railroad Bridge in Saginaw. (See Table 31-B for authorizing legislation.) Local cooperation. Fully complied with. Terminal facilities. Numerous large commercial docks for handling a great variety of cargo. Details on actual port and harbor facilities are in Port Series No. 45 (revised 1972) prepared and published as part 2 by Board of Engineers for Rivers and Harbors. Information on port administration and Federal services, port and terminal services and charges, and steamship services is prepared and published as part 1 by Port Development Staff, U.S. Department of Commerce. Facilities are considered adequate for existing commerce. Operations during fiscal year. Maintenance: Condition surveys, Hi-Fix surveys, environmental studies, support of Water Control Center, inspections and reports were performed by Government forces at a cost of $350,933. Maintenance of disposal area was performed by hired labor at a cost of $26,484. An adjustment of $97,137 was made to the contract for dredging the Bay Section completed last FY. The contract awarded last FY for repair to the dike disposal facility was completed at a cost of $93,604. A contract for maintenance dredging was awarded and completed this FY at a cost of $2,162,575 with approximately 365,275 cubic yards of material being removed. Engineering, design, surveys, supervision and administration cost $98,865. Engineering and design for construction of a diked disposal area for upper Saginaw 31-26 DETROIT, MICHIGAN DISTRICT was continued at a cost of $256,689. Existing project is complete except for a small part of the work authorized by the Act of October 23, 1962. Section D (Sixth Street Turning Basin) of the 1962 Act is complete except for the channel portion, which is pending modification. Total costs for existing project to end of FY were $64,978,240, of which $13,968,171 was for new work and $51,010,069 for maintenance. 62. ST. CLAIR RIVER, MI Location. A 40 mile long section of Great Lakes connecting channels which flows southerly from Lake Huron and discharges into Lake St. Clair. (See NOAA Nautical Chart 14852.) Existing project. Provides for channels through St. Clair River, which, at low water datum, are suitable for vessels drawing 25.5 feet. Project also provides for improvement of North Channel outlet, 100 feet wide and 10 feet deep, for recreational craft. Project depths are referred to low water datums for Lakes Huron and St. Clair, 576.8 and 571.7 feet above mean water level at Father Point, Quebec; International Great Lakes Datum 1955. (See Tables 31-B and 31-C for authorizing legislation and features of existing project.) Act of July 24, 1946 provides for widening and deepening of southeast bend and improvement of outlet of north channel. Estimated cost (1984) is $850,000. Local cooperation. None required. Terminal facilities. This improvement serves through commerce, between upper and lower Great Lakes, and has not materially influenced terminal facilities along its route. A number of privately owned piers and wharves are at Port Huron, Marysville, St. Clair, and Marine City, MI, which handle coal, limestone, petroleum products, woodpulp, salt and general cargo. These installations satisfy present commerce requirements. Operations during fiscal year. Maintenance: Condition surveys, environmental studies, and miscellaneous inspections and reports were performed by Government forces at a cost of $278,961. Environmental studies in connection with the extended navigation season cost $605,181. Location and removal of obstructions cost $141,166. A contract for maintenance dredging was awarded and completed this FY at a cost of $382,497 removing approximately 71,629 cubic yards of material. Engineering, design, surveys, supervision and administration cost $54,724 Existing project is complete. Total cost of existing project to end of FY was $33,155,176, of which $19,213,246 was for new work and $13,941,930 for maintenance. 63. ST. JOSEPH HARBOR, MI Location. On east shore of Lake Michigan, 60 miles easterly from Chicago, IL, and 24 miles southerly from South Haven, MI. (See NOAA Nautical Chart 14930.) Previous project. For details see page 1945 of Annual Report for 1915, and page 1470 of Annual Report for 1938. Existing project. Provides for protecting mouth of St. Joseph River by two piers, 250 to 325 feet apart at their inner and outer ends, respectively, having lengths of 2,758 feet on north side and 2,603 feet on south side; for a channel 21 feet deep from Lake Michigan to mouth of Benton Harbor Canal, a length of about 6,900 feet with widths of 265 feet at outer end of piers, 190 feet at inner end of piers and revetments, thence generally 215 feet to lower end of turning basin, increasing to 250 feet above the turning basin to mouth of Paw Paw River, thence generally 110 feet in Paw Paw River to mouth of Benton Harbor canal; for dredging channel in Benton Harbor canal up to west line of Riverview Drive extended northerly, to 18 feet deep and 80 feet wide; and a turning basin 18 feet deep on north side of channel above mouth of Morrison Channel and a turning basin 18 feet deep near mouth of Paw Paw River. Public Law 88-88th Congress declared a portion of Benton Harbor Canal a non-navigable stream. (See Table 31-B for authorizing legislation.) Local cooperation. Fully complied with. Terminal facilities. Several commercial wharves for handling coal, building materials, petroleum products, and miscellaneous commodities. A package freight terminal and a public docking facility is also available. Facilities considered adequate for existing commerce. Operations during fiscal year. Maintenance: Condition surveys, safety and environmental studies, miscellaneous inspections and reports were performed by Government forces at a cost of $66,829. Hired labor cost for maintenance of disposal area was $7,309. An adjustment of -$8,868 and -1,900 cubic yards was made to the contract completed last FY for dredging contaminated material in the inner harbor. Approximately 41,467 additional cubic yards of material was removed to complete the maintenance dredging contract awarded last FY (see mitigation for balance of cost.) A contract for maintenance dredging was awarded and completed this FY at a cost of $213,899 with approximately 37,701 cubic yards of material removed. A contract for maintenance dredging the inner harbor was awarded and completed this FY at a cost of $89,998, with approximately 15,466 cubic yards of material removed. A contract for trucking dredged material from the disposal area was awarded and completed at a cost of $74,082. Engineering, design, surveys, supervision and administration cost $63,398. Under the Section 111 program, $99,000 was expended to complete a dredging contract awarded last FY to place dredged material on the beach. Monitoring, surveys, engineering, supervision and administration cost 31-27 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 $53,156. Engineering and design for confined disposal area for polluted dredged material was continued at a cost of $127,783. Existing project was completed in 1956. The structures are in generally good condition. For additional details on completion of existing project see page 1454 of Annual Report for 1962. Total costs of existing project to end of FY were $12,995,269, of which $1,301,372 was for new work, $10,731,681 for maintenance and $962,216 for rehabilitation. 64. ST. MARYS RIVER, MI Location. A Great Lakes connecting channel about 63 miles long, flows southeasterly between State of Michigan and Province of Ontario, Canada, from eastern end of Lake Superior into northern end of Lake Huron. (See NOAA Nautical Charts 14882,14883, and 14884.) At. Sault Ste. Marie, MI, about 14 miles downstream from Lake Superior, there are four parallel locks and a hydroelectric powerplant. Previous project. For details see page 1955, Annual Report for 1915; and page 1529, Annual Report for 1938. Existing project. Channels permitting 25.5-foot draft navigation in St. Marys River and Lake Superior and Lake Huron approaches thereto; constructing and operating four locks and two canals; constructing an electric plant of 14,000 kilowatt capacity (45,000 kilowatt ultimate capacity) constructing anchorage areas in river above and below locks; and constructing various other works in conjunction with project. Subsequently, in 1932, the Unit 10 powerhouse was installed raising the capacity to 18,400 kilowatts (45,000 ultimate capacity). Original State locks were operated and maintained under permanent indefinite appropriation from June 9,1881, to November 2,1886, after which they were destroyed by excavation for the Poe Lock in 1896. Weitzel Lock, destroyed in 1942 by excavation for MacArthur Lock, was operated and maintained under the same appropriation from September 1,1881, to June 30,1935. Poe Lock was operated and maintained under the same appropriation from August 3,1896, Davis Lock from October 21, 1914, and Sabin Lock from September 18,1919, to end of FY 1935. The 1,200 foot by 110 foot new Poe Lock was authorized in 1962 and put into operation in 1968. Details of existing project are set forth in Table 31-D. Project depths are referred to low water datum corresponding to sloping surface of river as follows: Above locks: When water surface of Lake Superior is at elevation 600 feet and at upstream side of locks is 577.8 feet above mean water level at Father Point, Quebec (International Great Lakes Datum 1955). Estimated (1973) cost for new work is $164,630. (See Table 31-B for authorizing legislation.) Local cooperation. Fully complied with. Terminal facilities. This improvement serves through commerce between Lake Superior and lower lakes and has not materially influenced terminal facilities at localities along its route. Three piers at Sault Ste. Marie receive coal and petroleum products. Limestone is shipped from a pier at Drummond Island. Vessel refueling stations are at Lime Island and Village of Detour; they receive coal and petroleum products. Present terminals satisfy current traffic requirements. Operations during fiscal year. Operation, maintenance, and care of locks: Two canals and four locks were operated as required. Necessary repairs and improvements were made thereto and to appurtenant structures and equipment. Canals were open to navigation 293 days from October 1, 1984 through September 30, 1985. Cost for operation, maintenance, and care of the locks for this FY was $5,105,358, which includes $108,358 for extended season operation and maintenance and $350,210 for the modernization of the Gatelifter PAUL BUNYAN. Powerhouse and Equipment: Two hydroelectric powerhouses were operated and maintained at a cost of $587,570 during the FY less a deduction of $35,048 for interdepartmental electricity sold. Other operation and care items: Buildings and grounds were maintained, condition surveys, operation studies, miscellaneous inspections and reports were performed at a cost of $596,955, which includes a custodial, snow removal, and ground upkeep contract for $176,429. Environmental studies were made at a cost of $34,425. Security measures were performed at a cost of $431,182 which included a contractfor $371,426. Janitorial service of the facilities was done by a contract at a cost of $42,884. A study on winter and extended navigation season, ice measurements and weather monitoring was performed at a cost of $641,519. The ice boom was installed and removed at a cost of $45,928. Channels and canals: St. Marys River channels and canal approaches were examined by sweeping. Removal of shoals in St. Marys River channels and canal approaches was accomplished by hired labor and U.S. Derrickboats NICOLET and HARVEY at a cost of $1,343,518, including engineering and design. A total of $61,934 has been expended this year in the procurement of an electronic survey system. Recreational facilities: Information center, comfort stations, park fountain, observation and overlook platforms were maintained at a cost of $117,177, which includes a janitorial contract for the information center at a cost of $20,641, and Government personnel uniforms at a cost of $9,525. A total of 489,799 visitors used the observation platforms and 586,611 visitors visited the information center during the 1985 fiscal year. (Total costs: $8,973,402). Project in effect prior to modification of March 21, 1956 is complete and work authorized by 1956 modifi- 31-28 DETROIT, MICHIGAN DISTRICT cation to provide a safe draft of 25.5 feet for both upbound and downbound traffic is also complete. Public Works Acceleration Funds used for maintenance were $118,000. Total costs to end of FY were $160,657,070 for new work and $166,262,928 for maintenance, for a grand total of $326,919,998. 65. SAUGATUCK HARBOR AND KALAMAZOO RIVER, MI Location. Harbor is on east shore of Lake Michigan, 90 miles northeasterly from Chicago, IL, and 22 miles northerly from South Haven, MI. (See NOAA Nautical Chart 14906.) Previous project. For details see page 1947 of Annual Report for 1915, and page 1475 of Annual Report for 1938. Existing project. Entrance channel protected by parallel piers at mouth of Kalamazoo River and a river channel to Village of Saugatuck, MI. Project depths: 16 feet in entrance channel, 14 feet in river channel. Additional details on page 1456, 1962 Annual Report. (See Table 31-B for authorizing legislation.) Local cooperation. None required. Terminal facilities. At Village of Saugatuck, MI, there are several landing places for recreational craft and one for small commercial vessels. At Village of Douglas, MI, there is a landing pier. Facilities are considered adequate for present traffic. Operations during fiscal year. Maintenance: Condition surveys, safety studies, inspections and reports were performed by Government forces at a cost of $13,153. The reconnaissance report for major rehabilitation of north and south piers and revetments was completed at a cost of $473. Repairs to navigation structures were performed by hired labor using the cranebarge MANITOWOC at a cost of $62,472. A contract for maintenance dredging was awarded and completed at a cost of $107,495 removing approximately 19,880 cubic yards of shoal material. Engineering and design for repairs to the north and south piers and revetments was performed at a cost of $48,225. Engineering, design, surveys, supervision and administration cost $18,157. Existing project was completed in 1903. Total costs to end of FY were $3,271,511, of which $364,527 was for new work and $2,906,984 for maintenance. 66. SAXON HARBOR, WI Location.On south shore of Lake Superior in Wisconsin at mouth of Oronto Creek, 27 miles southeast of harbor at Bayfield, WI, and 21 miles westerly of harbor at Black River, MI; 99 miles east of Duluth-Superior Harbor and 60 miles west of Ontonagon Harbor, MI. (See NOAA Nautical Chart 14965.) Previous project: For details see page 1254 of Annual Report for 1962. Existing project. Provides for east and west breakwaters, an outer channel 10 feet deep, an inner basin and side channel 8 feet deep, and diversion of Oronto Creek to Parkers Creek by three short reaches of channel excavation and a levee. For detailed dimensions of features see page 1025 of Annual Report for 1965. (See Table 31-B for authorizing legislation.) Local cooperation. Fully complied with. Terminal facilities. One wharf 300 feet long on east side of present harbor basin constructed by local interests. Operations during fiscal year. Maintenance: Condition surveys, environmental studies, inspections and reports were performed by Government forces at a cost of $12,259. Repair to navigation structures were performed by hired labor at a cost of $24,139. The project was fully completed in March 1968. A reconnaissance report was completed in August 1971 concerning erosion of the shoreline west of the harbor. A detailed project report is being prepared to develop an acceptable plan for mitigation measures. Total cost of existing project to end of FY is $1,534,559 (Includes $50,193 Contributed Funds). 67. SHEBOYGAN HARBOR, WI Location. On west shore of Lake Michigan about 26 miles south of Manitowoc and about 55 miles north of Milwaukee, WI. (See NOAA Nautical Chart 14922.) Previous project. See page 1381 of Annual Report for 1962. Existing project. See Chicago District Annual Report for 1979, Table 30-C, page 30-27. For detailed description see page 1230, Annual Report for 1963. New Work for project as completed cost $648,271, exclusive of amounts expended on previous projects. (See Table 31-B for authorizing legislation.) Local cooperation. Fully complied with. Terminal facilities. Three wharves for handling coal, petroleum products and miscellaneous commodities. City provided a public wharf. Facilities considered adequate for existing commerce. Operations during fiscal year. Maintenance: Condition surveys, environmental studies, inspections and reports were performed by Government forces at a cost of $57,008. An adjustment of -$1,283 was made to the FY 83 repair contract completed last FY. An adjustment of -$3,185 was made in the hired labor structure repairs performed last FY. A maintenance dredging contract was awarded in the amount of $147,920. No work was performed this FY. Engineering, design, supervision and administration cost $72,100. Engineering and design for construction of a confined disposal facility was performed at a cost of $68,476. Existing project was completed in 1904. Construction of north breakwater was commenced in October 1913 31-29 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 and completed in October 1915. Dredging turning basin was commenced in October 1928 and completed in September 1931. Dredging entrance channel to existing project depth was commenced in June and completed in July 1938. Work on 1954 modification was completed in December 1956. Piers and breakwaters are in generally good condition. Inner 260 feet of south pier was replaced with revetment by private interests under permit granted July 16,1931, by the Secretary of War. Piers, therefore, are maintained only for a length of about 2,490 feet. Sheboygan River is navigable about 2.4 miles above its mouth for craft drawing not more than 2 feet. Costs of existing project are $5,345,233 for maintenance, $609,028 for rehabilitation and $1,136,088 for new work; a total of $7,090,349. 68. SOUTH HAVEN HARBOR, MI Location. On east shore of Lake Michigan, 77 miles northeasterly from Chicago, IL, and 24 miles northerly from St. Joseph, MI. (See NOAA Nautical Chart 14906.) Previous project. For details see page 1947 of Annual Report for 1915, and page 1473 of Annual Report for 1938. Existing project. An entrance channel protected by parallel piers and revetments at mouth of Black River, a river channel and a turning basin. Project depths are 21 feet in entrance channel and 19 feet in river channel and turning basin. For additional details see page 1455 of Annual Report for 1962. (See Table 31-B for authorizing legislation.) Local cooperation. Fully complied with. Terminal facilities. Several wharves for handling coal, building materials, woodpulp, fish, and miscellaneous commodities will have warehouses. Facilities satisfy current commerce requirements. Operations during fiscal year. Maintenance: Condition surveys, safety studies and inspections were performed by Government forces at a cost of $19,982. An adjustment of $10,000 was made for hired labor structure repairs from previous years. Hired labor structure repairs were performed this FY at a cost of $99,473. Supervision and administration cost $3,869. Condition surveys, environmental studies and monitoring in conjunction with Section 111 cost $34,918. A contract for beach nourishment was awarded at a cost of $645,603. Approximately 10%,of the contract was completed at a cost of $66,690. Engineering, design, supervision and administration cost $23,992. Existing project was completed in 1960. Project now being maintained to 14-foot and 12-foot depths, respectively, in lieu of the 21 feet and 19 feet authorized, which is adequate for current usage. For additional details on completion of existing project see page 1456 of Annual Report for 1962. Total costs for existing project to the end of FY were $6,504,946, of which $984,426 was for new work, $3,888,444 for maintenance, and $1,632,076 for rehabilitation. 69. STURGEON BAY AND LAKE MICHIGAN SHIP CANAL, WI. Location. On west shore of Lake Michigan about 52 miles northeast of Green Bay and about 128 miles north of Milwaukee, WI. (See NOAA Nautical Chart 14919.) Previous projects. See page 1373 of Annual Report for 1962. Existing project. See Chicago District Annual Report for 1979, Table 31-C, page 30-27. For detailed description, see page 1223, Annual Report for 1963. (See Table 31-B for authorizing legislation.) Local cooperation. Fully complied with. Terminal facilities. As the canal and connecting channel is a through waterway, only terminal facilities are in City of Sturgeon Bay, 4 miles from west end of revetted portion of canal. These facilities consist of two wharves for handling coal, petroleum products and miscellaneous commodities and four shipbuildingyards. City of Sturgeon Bay provided a public wharf about 5 miles northwesterly from City of Sturgeon Bay. Two major shipyards are located in Sturgeon Bay where repair facilities are available including dry docks, marine railways and hoists. Facilities are considered adequate for existing commerce. Operations during fiscal year. Maintenance: Condition surveys, environmental studies, miscellaneous inspections and reports were performed by Government forces at a cost of $69,677. Breakwater repairs were performed by hired labor using the cranebarge MANITOWOC at a cost of $40,705. A contract for maintenance dredging was awarded this FY at a cost of $249,396. The contract is approxiamtely 35% complete at a cost of $88,035 removing approximately 11,000 cubic yards of material. Engineering, design, surveys, supervision and administration cost $36,402. Engineering and design for construction of a diked disposal facility was continued at a cost of $25,485. Total cost of existing project is $1,059,722 for new work, $7,046,215 for maintenance and $884,899 for rehabilitation: a total of $8,990,836. In addition, $235,940 was expended between April 25, 1893 and June 30, 1917 on operating and care of works of improvements under provision of permanent indefinite appropriations for such purposes. 70. TWO RIVERS HARBOR, WI Location. On west shore of Lake Michigan about 82 miles north of Milwaukee and about 101 miles from Green Bay, WI, via Sturgeon Bay Canal. (See NOAA Nautical Chart 14903.) Previous projects. See page 1377, Annual Report for 1962. 31-30 DETROIT, MICHIGAN DISTRICT Existing project. See Chicago District Annual Report for 1979, Table 30-C, page 30-28. For detailed description see page 1226 of Annual Report for 1963. Completed project cost $147,463, exclusive of the amount expended on previous projects. The 1935 River and Harbor Act portion of project is considered inactive. Estimated cost of this portion (1954) is $14,000. (See Table 31-B for authorizing legislation.) Local cooperation. Fully complied with. Terminal facilities. A coal wharf and several fishing wharves. City provided a wharf for receipt of petroleum products and public use. Facilities considered adequate for existing commerce. Operations during fiscal year. Maintenance: Condition surveys, environmental studies, miscellaneous inspections and reports were performed by Government forces at a cost of $16,680. Repairs to navigation structures were performed by hired labor using the cranebarge MANITOWOC at a cost of $70,051. Engineering and design for structure repairs to Section E and F South Revetment cost $26,752. Surveys, supervision and administration cost $6,431. Existing project is complete except for inactive portion of project which consists of dredging a 10-foot width along east side of lakeward portion of entrance channel between the piers. This dredging was omitted to avoid removal of necessary riprap along entrance piers. Present width of channel is considered adequate for present and reasonably prospective commerce. South pier was completed in 1883 and is in generally good condition. North pier was completed in 1908. North revetment, completed in 1917, was rebuilt in May to August 1962. Dredging entrance channel and inner basin to existing project depth was commenced in March and substantially completed in May 1937. Total costs of existing project were $147,463 for new work and $6,496,265 for maintenance; a total of $6,643,738. In addition, $58,057 was expended for minor rehabilitation. 71. WHITE LAKE HARBOR, MI Location. On east shore of Lake Michigan 120 miles northeasterly from Chicago, IL, and 45 miles southerly from Ludington, MI. (See NOAA Nautical Chart 14935.) Existing project. Parallel piers, revetments, and a channel 16 feet deep, 200 feet wide, 1,950 feet long, extending from Lake Michigan to White Lake. For additional details see page 1465 of Annual Report for 1962. (See Table 31-B for authorizing legislation.) Local cooperation. None required. Terminal facilities. A privately owned chemical shipping dock on north side of lake about 3 miles from inner end of revetted entrance channel. Across lake, at Village of Whitehall, there are several installation: serving light draft vessels. These terminals satisfy present recreational and commercial traffic require ments. Operations during fiscal year. Maintenance Condition surveys, environmental and safety studies miscellaneous inspections and reports were performer by Government forces at a cost of $13,247. An ad justment of $15,000 was made for repairs to navigatioi structures from previous years. Repairs to navigatioi structures were performed by hired labor using the Cranebarge MANITOWOC at a cost of $109,084 Engineering and design for major structure repairs tA the North and South Piers was performed at a cost o $45,301. Supervision and administration cost $7,285 Under the Section 111 program, a contract for beacd nourishment was awarded in the amount of $222,300 The contract is approximately 75% complete at a cost o $190,000. Surveys, monitoring, engineering, supervi sion and administration cost $24,040. Existing project was completed in 1908. Stone wa placed on the north and south revetments in FY 1972 The structures that are not in generally good conditioi are programmed for major repair as needed. Projec now being maintained to 14-foot depth authorized which is adequate for current usage. Total cost to end o FY is $2,728,183, of which $457,563 was for new worl and $2,270,620 for maintenance. 72. RECONNAISSANCE AND CONDITION SURVEYS See Table 31-F. 73. OTHER AUTHORIZED NAVIGATION PROJECTS See Table 31-G. 74. NAVIGATION WORK UNDER SPECIAL AUTHORIZATION Navigation activities pursuant to Section 10 Public Law 86-645 (pre-authorization.) Expander reconnaissance studies were continued for Dougla County, WI ($38,731) and Two Harbors, MN ($46,955 Detailed project studies were continued for Bayfielc WI ($18,063) to respond to OCE comments on fins report, and continued for Kenosha, WI ($3,726). A unfavorable Initial Appraisal Report was completes for Kewaunee, WI ($6,000). Financial closeout wa accomplished on Harrisville, Harbor, MI (-$63,98 Federal and -$24,214 non-Federal), and Manitowo Small Boat Harbor, WI (-$137,173 Federal an< $114,139 non-Federal). Surplus "Required Contribute< Funds" ($84,121) for the Manitowoc Small Boat Harbo project were returned to the City of Manitowoc. 31-31 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Beach Erosion Control 75. AUTHORIZED BEACH EROSION CONTROL PROJECTS Beach erosion control projects are authorized at Berrien County Shore (St. Joseph) MI, and the Shore of Manitowoc County, WI. For last full report see Annual Report for 1963 (Berrien County). Both projects are in the inactive category. 76. EMERGENCY SHORE PROTECTION Authority for emergency streambank and shoreline protection of public works and non-profit public services. (Section 14 Flood Control Act of 1946, as amended.) Barkers Island, WI -A contract for erosion protection of Marina Drive and a high pressure gas line was awarded in July 1985 in the amount of $103,528. Approximately 96 percent of the work was completed at a cost of $101,227. Engineering and design and supervision and administration costs were $52,125. Total FY 85 costs were $153,352. Bayshore Drive, N. Shoemaker Road, WI -A contract for erosion protection of Bayshore Drive was initiated and completed at a cost of $21,704. Engineering and design, and supervision and administration costs were $9,649. Total FY 85 costs were $31,353. Charlevoix Harbor, MI - The contract for erosion protection of the north bank of the Pine River, which was awarded in FY 84, was completed at a cost of $40,025 Federal and $6,514 non-Federal. Engineering and design, and supervision and administration costs were -$5,355. Total FY 85 costs were $34,670. Elkhart River, Elkhart, IN - The contract for streambank erosion protection of Waterfall Drive, which was awarded in late FY 84, was initiated and completed at a cost of $188,822. Engineering and design, and supervision and administration costs were $11,312. Total FY 85 costs were $200,134. Lake Michigan Shoreline, Port Washington, WI - A contract for shoreline erosion protection of the Water Filtration Plant Intake System, two storm sewer outfalls and a sanitary sewer outfall was awarded in late September 1985. No work was performed this FY. Reimbursement of the Appraisal Report, preparation of plans and specifications and advertisement and award costs in FY 85 were $47,750. Manistee, MI - A contract for shoreline erosion protection of Lakeshore Road, a local road endangered by erosion along Lake Michigan shoreline, was awarded in November 1984 and completed in June 1985 at a cost of $157,003. Negotiations are underway with the contractor for 20 additional feet of bank protection work to prevent possible undermining and failure of the completed protection work. Engineering and design, and supervision and administration costs were $15,564. Total FY 85 costs were $172,567. Zoological Gardens, Racine, WI - Preparation of the O&M Manual and financial closeout of the project was initiated. Costs for FY 85 were -$2,266. Contributed funds by the City of Racine for Section 14 were -$3,346. Bridgeport Charter Township, MI - Final costs for the positive appraisal report were $385. Project has been placed on the backlog to await funding for plans and specifications. 77. BEACH EROSION WORK UNDER SPECIAL AUTHORIZATION Beach erosion activities pursuant to Section 103 of the 1962 River and Harbor Act. Plans and specifications were completed and approved for Escanaba, MI ($35,819). Detailed project studies were continued at Ontonagon, MI ($10,401). Negative appraisal report was completed and reimbursed for Town Lake Michigan Park, Caledonia. WI ($7,500). 78. MITIGATION OF SHORE DAMAGES Mitigation of Shore Damages pursuant to Section 111 of the River and Harbor Act of 1968. Expanded Reconnaissance Report efforts were initiated on Algoma, WI ($17,280), Marinette, WI ($9,257), and Sturgeon Bay, WI ($1,588). Detailed project study was completed at Saxon, WI ($4,685), while coordination was completed at Grand Traverse Harbor, MI ($51) and Presque Isle Harbor, MI ($600). Negative appraisal reports were completed and reimbursed for Kenosha, WI ($5,100), Kewaunee, WI ($6,000), Oconto Harbor, WI ($6,800), Port Wing, WI ($7,500), Racine, WI ($6,000), and Two Rivers, WI ($7,000). Flood Control 79. KAWKAWLIN RIVER, MI Location. River drains an irregularly shaped area of about 220 square miles in Bay, Gladwin, Midland, and Saginaw Counties in east-central Michigan and discharges into Saginaw Bay 2 miles northwest of Saginaw River. (See Geological Survey Bay City quadrangle and NOAA Nautical Charts 14867 and 14863.) Existing project. Provides for deepening about 1.8 miles of river channel between the river mouth and Euclid Street Bridge; altering Detroit and Mackinac Railway Bridge by addition of two 45.9-foot spans; protecting by riprapping the channel bottom through Euclid Street Bridge, existing piers at Henry Street Bridge and Detroit and Mackinac Railway Bridge; and a number of utility relocations. (See Table 31-B for authorizing legislation.) Local cooperation. Fully complied with. Operations during fiscal year. Maintenance: 31-32 DETROIT, MICHIGAN DISTRICT Environmental studies were performed by Government forces at a cost of $5,412. An adjustment of $214 was made on contract awarded and completed last FY. Supervision and administration of final closeout cost $1,645. 80. SAGINAW RIVER, MI Location. Saginaw River basin including its tributaries, Tittabawassee, Shiawassee, Flint and Cass Rivers, drains an area of 6,260 square miles in the east central part of Michigan and empties into Saginaw Bay, an arm of Lake Huron. Bay City, near mouth of river, and Saginaw, 22 miles upstream from mouth, are on Federally improved deep-draft Saginaw River navigation channel. (See Saginaw and Flint Geological quadrangles and NOAA Nautical Chart 14867.) Existing project. Provides for improvements in Saginaw River Basin for flood control and other purposes: (a) at Middle Branch and South Branch, Cass River, to provide for major drainage improvements by channel improvements on Middle and South Branches, including a short reach of East Branch, at an estimated U.S. cost (July 1961) for construction of $1,448,000 for Middle and South Branches; provided local interests contribute in cash 42 percent of first cost of major drainage project on Middle Branch, and 38 percent of first cost of major drainage project on South Branch, exclusive of cost of rights-of-way and other work required as local cooperation, and give assurances satisfactory to Secretary of the Army they will construct and maintain local drainage work required to fully and effectively utilize improvements to be provided under the Federal projects; (b) at Vassar on Cass River, to provide for flood protection of areas on north and south sides of river by channel improvement, levee construction, floodwalls, modification of Moore Drain, and related work at an estimated U.S. cost (Oct 1984) of $8,620,000 and non-Federal cost of $579,000 for construction; (c) at Frankenmuth on Cass River, to provide for flood protection of areas on north side of river by channel improvement, levee construction, and related work, at an estimated U.S. cost (Jul 1974) of $410,900 for construction; (d) at Flint on Flint River, to provide for flood protection of areas on both sides of main stem of Flint River and its tributaries, Swartz and Thread Creeks by channel improvement, bridge alterations, floodwall and levee construction, and related work, at an estimated U.S. cost (Oct 1984) of $18,251,600 and non-Federal cost of $2,580,000 for construction; provided local interests contribute in cash 1 percent of first cost of project, exclusive of costs of rights-of-ways (e) at Corunna on Shiawassee River, to provide for flood protection by channel improvement, levee construction, and related work at an estimated U.S. cost (July 1961) of $48,000 for construction; provided local interests modify spillway of mill dam at Corunna at their own expense, substantially in accordance with plan of District Engineer and subject to approval of Chief of Engineers, or in lieu thereof, contribute to the United States actual cost of modification to be performed by the United States; (f) at Owosso on Shiawassee River, to provide for flood protection by channel improvement at an estimated U.S. cost (July 1961) of $425,000 for construction; (g) at Midland on Tittabawassee River, to provide for flood protection through non-structural (permanent evacuation) measures at an estimated U.S. cost (Apr 1982) of $5,125,000 and non-Federal cost of $1,611,500 for implementation; however, project was reclassified to the "inactive" category on December 15, 1982; (h) at Shiawassee Flats along lower reaches of the four principal tributaries of Saginaw River, to provide for flood protection, including fish and wildlife areas; by channel improvement, levees, lateral reservoirs with control structures and related work at an estimated U.S. cost (Oct 1984) of $23,417,500 Federal, and a non- Federal cost of $2,705,000 which includes a cash contribution of $1,237,000; provided local interests contribute in cash 5 percent of cost of rights-of-way for flood control and other work required as local cooperation, and furnish one-half of land required for fish and wildlife areas; provided that the Federal allocation for conservation does not exceed amount obtained by taking 28 percent of project cost for Shiaw~ssee Flats "unit and subtracting therefrom one-half cost of lands for conservation; and provided further that before starting works for flood control to Shiawassee Flats, Chief of Engineers and Director, Fish and Wildlife Service, prepare a plan mutually acceptable to Secretary of the Army and Secretary of the Interior for operation of fish and wildlife areas to required degree of controlled storage of flood-waters while preserving the maximum fish and wildlife benefits. Total estimated cost for new work, for active portion (1984) is $50,700,000 Federal and $1,421,000 to be contributed by local interests. Total estimated cost (1984) to local interests is $5,870,000. Local cooperation. Responsible local interests must make cash contributions as called for above; furnish lands, and rights-of-way, including removal of buildings, for construction; hold the United States free from damage; maintain and operate all works after completion; establish and enforce regulations designed to prevent encroachments in improved channels; and bear expense of constructing highway relocations and highway bridges, alter bridge approaches and existing highway bridge approaches and existing highway bridges (except underpinning and bridge raising), and alter utilities. Required assurances for Flint River at Flint were furnished by City of Flint and accepted by the United States on November 23, 1962. Estimated required cash contribution for Flint ($56,000) was furnished February 20, 1963. An additional $117,000 31-33 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 was furnished by the City to cover increased construction costs. Required assurances for Cass River at Frankenmuth were accepted on September 8,1964. All necessary lands, easements, and rights-of-way have been provided. The Midland City Council adopted a resolution on June 7, 1982 declaring its intent not to sponsor the Flood Control project on the Tittabawassee River at Midland. The Vassar City Council, in a letter dated January 26, 1982, indicated a willingness and capability to provide the assurances of local cooperation for the Vassar Flood Control Project. Saginaw County, in a resolution dated August 11, 1982, indicated a willingness and capability to provide the assurances of local cooperation for the Shiawassee Flats Flood Control Project. Operations during fiscal year. New Work: Shiawassee: Work on preparing a General Design Memorandum, initiated in FY 83, continued in FY 85. Total cost for Shiawassee this FY is $9,649. Flint: Investigations of claims for contract completed in FY 80 cost $91,811 in FY 85. Vassar: Work on preparing a General Design Memorandum, initiated in FY 83, continued in FY 85. Total cost for Vassar this FY is $7,207. The Frankenmuth and Flint portions of the project are complete. Total costs for this project in FY 85 were $108,667. 81. SEBEWAING, SEBEWAING RIVER, MI Location. Sebewaing River drains an area of 105 square miles in Huron and Tuscola Counties on the westerly side of Thumb area of Lower Peninsula of Michigan and discharges into Saginaw Bay, an arm of Lake Huron, 20 miles northeast from mouth of Saginaw River. Village of Sebewaing is near mouth of River. (See NOAA Nautical Chart 14863.) Existing project. Enlarging present channel of Sebewaing River through Village of Sebewaing, MI, to a capacity of 7,500 cubic feet per second from junction of Columbia and State drains to a point 4,500 feet lakeward from railroad bridge near mouth; altering railroad bridge and three highway bridges to permit free passage of ice; and removal of present dike on south side of channel lakeward from railroad bridge. Project is designed to provide protection for Village of Sebewaingr from floods with a frequency of once in 15 years oafn dr ewciothrd a. m(Saegen iTtuadbel eg r3e1a-Bte r ftohra na uthteh omraizxiinmgu mleg filsoloadtion.) . Local cooperation. Complied with except for furnishing easements and rights-of-way for removal of remaining portion of dike on south side of channel lakeward from railroad bridge. Operations during fiscal year. Maintenance: Condition surveys, inspections and reports were performed by Government forces at a cost of $7,332. 82. INSPECTION OF COMPLETED FLOOD CONTROL PROJECTS The listed projects were inspected during this period. Battle Creek, Kalamazoo River, MI; Kawkawlin, Kawkawlin River, MI; Sebewaing, Sebewaing River, MI; Flint, Flint River, MI; Frankenmuth, Cass River, MI; Mount Clemens Spillway and Cutoff Canal, Clinton River, MI; Red Run, Clinton River, MI; Estral Beach, Lake Erie, MI; Fort Wayne Mechanic St. Dike, St. Marys River, IN; Rouge River, MI; Burr Oak, Prairie River, MI. Fiscal year costs were $122,077. Total costs to end of FY year were $1,022,669. 83. OTHER AUTHORIZED FLOOD CONTROL PROJECTS See Table 31-H. 84. FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION Emergency Flood Control Activities, Flood Fighting (Public Law 84-99 and P.L. 93-288 and Antecedent Legislation). 1. The pattern for enhanced flow of moisture from the Gulf of Mexico into the Great Lakes area was particularly strong and persistent in the past year and especially in the 1984 fall season. This pattern continued through early winter (December 84) which was mild and wet. Although January turned much colder and drier, heavy snows in February built-up a moisture- laden snowpack that would be vulnerable to a sudden thaw. Thus, the stage was set for a series of flood events which beset the District throughout 1985. a. January 22-24, 1985. The District was requested, by FEMA, Region V, to furnish seven engineer- inspectors to perform preliminary damage assessments (PDA's) for an ice storm event that caused severe power outage and tree damage in 13 counties across southern Michigan. FEMA did not approve Federal subsidy of damage claims. Incurred costs: $8,409. b. February 24-March 5,1985. Rapid snowmelt caused widespread flooding in northern Indiana and southern Michigan. The District's EOC was activated Ianndd iaa nflao,o tdo adrierae cotf fCicoer pwsa ssu epsptalebmlieshnetadl aati dF otor tt hWisa ycnitey, which was severely impacted upon again. At the height of activities, 58 District employees were involved in flood-fight efforts. Incurred costs: $410,453. c. March 31-April 6, 1985, Southeastern Michigan. High easterly winds drove record Great Lakes water levels onshore inundating many coastal communities in Monroe, Wayne, and Macomb Counties. The Detroit District helped local communities in their flood 31-34 DETROIT, MICHIGAN DISTRICT protection efforts by supplying pumps (6), polyethylene sheeting (586 rolls), and sandbags (741,450). Corps personnel involved totaled 21 at maximum effort. Local damages as a result of shoreline flooding were estimated at $21,523,400. Costs incurred for flood-fighting: $162,533. On April 15th, the Governor of Michigan requested the Corps to initiate an Advance Measures program of flood protection for shoreline communities. Twenty-five project areas were approved for temporary flood protection facilities under P.L. 84-99's Advance Measures feature. Since the program was inaugurated, twenty-one communities elected not to participate in the protection program. Flood protection facilities are being enhanced at Luna Pier, Monroe County, and Milliman Island, Brownstown Twp., Wayne County, under the Advance Measures program. Three other shoreline areas remain under consideration for flood protection projects at this time. Costs incurred for Advance Measures letter reports: $175,347; costs incurred for Advance Measures program studies: $759,406; and Rehab studies: $1,345. Current Federal work allowances for Advance Measures project construction: $1,190,000. d. The Rehabilitation Levee Project under P.L. 84-99 at Fort Wayne, Indiana, started September 12, 1985, with completion scheduled for November 2,1985. These repairs were required as a result of flood events during February 24-March 5, 1985. Incurred costs for Rehab studies: $10,000. Current Federal work allowances for project construction: $290,000. e. During period of September 6-8, 1985, heavy rains totaling 8-10 inches caused flash floods in Flint, Michigan, and adjoining areas in Genessee, Saginaw, and Lapeer Counties. Significant flood damage was experienced in these areas. Overall damages incurred in this tri-county area are estimated at $37 million: $4 million public; $16 million private; $17 million agriculture. Since the flood waters rose and receded so rapidly, the Corps was not called upon for flood-fight activities. A Presidential Disaster was declared and the District contributed personnel at the request of FEMA to participate in the Hazard Mitigation Team Evaluations, Preliminary Damage Assessments, and Damage Survey Reports, including surveys of private agricultural levee damages. The Corps has a flood protection project in the City of Flint, maintained and operated by the City. Preliminary investigations indicated the project functioned as designed and minimal flood damage was experienced by the project facilities or to areas adjoining the project, even though record flood stages occurred. Incurred costs for FEMArelated activities: $3,432. Flood Control activities pursuant to Section 205 of the 1948 Flood Control Act. Expanded reconnaissance studies were terminated on LaCrosse, IN ($24,008) and Pigeon Creek, Steuben County, IN ($25,000) when the stream discharge for a 10-year frequency event fell below the minimum level of 800 cfs. required for Federal participation. The expanded reconnaissance report was completed on the Thread River Burton, MI project at a cost of $15,086. However, economic benefits did not justify the cost of the project; therefore, the project was terminated. A Detailed Project Report was initiated on the Ontonagon, MI project ($135,445) and a Feature Design Memorandum, plans and specifications and contract award were completed for Paw Paw Lake, MI ($139,660). Flood Control activities pursuant to Section 208 of the 1954 Flood Control Act. A negative appraisal report was completed and funds reimbursed for Bridgeport Charter Township, MI ($7,500). The construction contract for Maple River, MI was financially completed and preparation of the O&M manual was initiated ($12,981). Aquatic Plant Control activities pursuant to Section 302 of the River and Harbor Act of 1965 (PL 89-298). An aquatic plant control reconnaissance study was initiated for Houghton Lake and Lake St. Helen within Roscommon County, MI. Funds in the amount of $3,997 were expended in FY 1985. 85. SURVEILLANCE OF NORTHERN BOUNDARY WATERS Field Operations. The following field operations, which were complemented by office activities in support of basic mission, were conducted during the current period: In support of the development and calibration of Detroit District mathematical models of the Connecting Channels, soundings and discharge measurements were conducted on the St. Clair and Detroit Rivers. Discharge measurements were made in the Welland Canal and analyzed, in support of Water Survey of Canada. Additional measurements are scheduled for FY 86. During the winter months, the District observes the presence of ice in the St. Marys, St. Clair, and Detroit Rivers as an ongoing mission. The District monitors key water level gages in these rivers for continuous updating of the hydrograph for detection of possible ice jams and associated potential for flooding. This provides advance warning to area residents and other governmental agencies (in support of respective Flood Alert Plans). In the past, this monitoring was accomplished utilizing telemark gaging. The District has updated six of these gages by installing Data Collection Platforms (DCP's) on the St. Clair and Detroit Rivers. These platforms utilize Geostationary Operational Environmental Satellite (GOES) transmission equipment to provide round-the-clock real-time water level data monitoring. Installation of eight additional DCP's to replace the remaining telemark gages is expected to be completed by FY 86. 31-35 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 International Activities. The following activities were conducted specifically for the International Joint Commission (IJC) Boards and Committees: Members of the Detroit District staff attended the spring and fall semi-annual appearances of the International Great Lakes Boards before the Commission in Zion, Illinois, and Winnipeg, Manitoba, respectively. a. International Lake Superior Board of Control. The Detroit District Engineer is the United States Regulation Representative for the Board of Control. In support of the U.S. Section of the Board, the District provided monthly Lake Superior outflow recommendations based upon a review of the hydrologic factors which influence the future regulation of Lake Superior. These recommendations were based on the use of probability forecasts of water supplies routed through the lakes, rendering outflows under Plan 1977, the currently approved operating rule. On April 25, 1985, the International Joint Commission directed the Board to deviate from Plan 1977 and to implement a flow reduction from Lake Superior beginning in May. This action was intended to alleviate high water conditions on Lakes Michigan, Huron, St. Clair and Erie, each of which experienced record high water levels during the spring. The Commission's instructions also included limiting the flow through the Compensating Works at Sault Ste. Marie as well as imposing a reduction in water available for power production. In response to this directive, the Board authorized flow reductions in May, June, July and August, amounting to an accumulation on Lake Superior of 119,000 cfs/month. In September 1985, due to a continuing rise in the water level of Lake Superior, several increases in the Lake Superior outflow were made, resulting in an average September outflow of 102,000 cfs. The Board continues to closely monitor lake levels and will advise the Commission if and when additional flow changes are warranted. In June 1984, the Ontario Ministry of Natural Resources was identified as the proponent for the development of remedial measures for the St. Marys Rapids fishery at Sault Ste. Marie, Ontario. Construction began in July 1985 and the project was completed in September 1985. If all the requirements of the fishery are met, it is expected that the Board will request the IJC that they be allowed to discontinue the use of condition 1.(b) in Plan 1977 for the monthly regulation of Lake Superior. b. International Niagara Board of Control and International Niagara Working Committee. A member of the Great Lakes Hydraulics and Hydrology staff is on the U.S. Section of the Working Committee. The District was involved in the engineering and development of a revised rating curve for the Ashland Avenue gage. In October 1984, a series of discharge measurements were made in the American Falls Channel by personnel from the Detroit District. These measurements are part of the on-going program to periodically verify the stage-discharge relationship for the American Falls Channel flow. Additional measurements are scheduled in the American Falls Channel in early FY 87. Also scheduled in FY 87, is a series of measurements at the Cableway Section for further verification of the Ashland Avenue Rating Curve. c. International St. Lawrence River Board of Control. When requested, the Detroit District supported the Buffalo District in its activities. d. International Great Lakes Diversions and Consumptive Uses Study Board. The IJC submitted its recommendations, based on the Board's report and subsequent public hearings, to the governments of the United States and Canada, in a report dated January 1985. A former Detroit District Engineer was Chairman of the U.S. Section of the Working Committee. Until such time as the Board is either dissolved or continued, certain personnel within the District continue to hold membership on the Diversions and Environmental Evaluation Subcommittees and on the Public Involvement Ad Hoc Group. e. International Lake Erie Regulation Study Board. The former Chief of the Detroit District's Great Lakes Hydraulics and Hydrology Branch was Chairman of the U.S. Section of the Regulation Subcommittee. Staff members also provided input to the other subcommittees. The Board completed its report in July 1981 and submitted it to the IJC. The IJC submitted its recommendations, based on the Board's report and subsequent public hearings, to the governments of the United States and Canada in a report dated November 1983. This Board was disbanded in 1985. f. International Great Lakes Technical Information Network Board. The former Chief of the Great Lakes Hydraulics and Hydrology Branch was U.S. Chairman of this Board. The Chief of the Lake Hydrology Section remains the Secretary to the U.S. Section of this Board, as well as a member on the Hydraulics and Hydrology Committees. A "Directive" concerning the future activities of the Board was sent to the IJC in June 1984. The Board provided the Commission with an advance copy of the main report, including executive summary findings, conclusions and recommendations, in July 1984. Published copies of the main report and appendices were completed in December 1984. In January 1985, the IJC informed the governments of the United States and Canada of the findings of the Board. Furthermore, the Commission recommended that a committee be established to provide an international mechanism for institutional coordination between the operational Boards of the IJC and agencies making studies, gathering and providing data on the Great Lakes System. This Board would assume the functions of the "Coordinating Committee on Great Lakes Basic Hydraulic and Hydrologic Data." 31-36 DETROIT, MICHIGAN DISTRICT Coordinating Committee on Great Lakes Basic Hydraulic and Hydrology Data. The Chief of the Lake Hydrology Section of the Great Lakes Hydraulics and Hydrology Branch is the U.S. Secretary to this committee, as well as a member of its subcommittees. Operations continued pertaining to the coordination of basic hydraulic and hydrologic data with Canada. A Coordinating Committee report, being worked on in the Branch, documents the discharge measurements made on the Great Lakes Connecting Channels and St. Lawrence River during the period 1900-1978. Through the auspices of the Coordinating Committee, the Corps of Engineers provided funds to Canada, in the amount of $215,000, to aid in completion of precise leveling in the International Section of the St. Lawrence River. This survey, as well as similar surveys conducted in the U.S. by NOAA, are part of a program to update the International Great Lakes Datum (IGLD). The new IGLD will evolve around the epic year 1980 and is expected to be published in FY 86. NCD Master Plan for Water Control Data System. In FY 85 the District acquired a Harris-800 minicomputer, dedicated to water control activities. The computer will be used to collect data from the District's data collection platforms (DCP's), Automation of Field Operational Service (AFOS), NOAA-NOS and Canada. The District currently has 16 DCP's active and plans to install as many as 17 additional DCP's in FY 86. Great Lakes Information Management. The District purchased a stand-alone image processing system to process and display satellite and aircraft derived data. This minicomputer system will eventually be the cornerstone of a fully automated mapping and analysis facility within the District. Besides processing remotely-sensed data, the system will provide capabilities for generating multi-parameter data bases and thematic maps for basin-wide hydrologic models, and for generating high-resolution graphics and drafting products. The image processing facility will be integrated with the water control minicomputer in FY86 to promote information transfer with NCD for the Great Lakes. Hydraulics and Hydrology of the Great Lakes. Studies to improve the existing Great Lakes water level forecasting system, including investigations into the factors affecting the Great Lakes water balance relationship (i.e., runoff, precipitation over water, evaporation, ice retardation, etc.) and use of real-time hydrologic data were continued by Great Lakes Hydraulics and Hydrology Branch staff members. Several conceptual hydrologic models have been studied and are being calibrated for eventual use in future forecasts of lake levels and outflows. District personnel are participating in the third year of a five-year program to assess water supplies on the Lake Superior Basin through use of automated hydromet stations, airborne snow and soil moisture surveys, and satellite imagery. Levels of the Great Lakes. The Branch provided technical information and expertise regarding lake levels and long range still water forecasts to many interested parties, such as Congressmen, State and local officials, news media, navigation and power interests, and concerned property owners. Explanation of the water levels was supplied to the public in the form of direct answers to numerous inquiries, addresses to various civic groups, and interviews with news media. The publication of an international (U.S. and Canada) forecast of Great Lakes water levels, under the auspices of the Coordinating Committee on Great Lakes Basic Hydraulic and Hydrologic Data, was continued during the period. In support of these forecasts and to assist in lake regulation, funds have been provided to the Department of Commerce for maintenance of eleven telemetric water level gages at selected sites throughout the Great Lakes to obtain more real-time data. Costs for FY 85 are $1,587,312. General Investigations 86. SURVEYS Fiscal year costs were $1,173,053 for navigation studies on the Great Lakes Connecting Channels and Harbors ($1,108,509) and for the review of the authorized Fox River, WI project ($64,544). Flood control studies cost $1,040,254. A feasibility study at Fort Wayne, IN, was initiated at a cost of $292,361. Funds in the amount of $504,052 were spent on the continuation of the Ecorse Creek Basin, Wayne Co., Flood Protection Study. In addition, $32,432 were expended in support of work efforts on a Summary Report dealing with the overall study authority for the Great Lakes, Particularly Lake Ontario and Lake Erie, of which Ecorse Creek Basin is an Interim study. Continuation of planning on the Saginaw River, MI, Basin Study was accomplished at a cost of $211,408. 87. CONTINUATION OF PLANNING AND ENGINEERING FY 85 costs for the continuation of planning and engineering for Monroe Harbor, MI, were $131,681. A Final Survey Report recommending structural modifications was completed in February 1980. The report recommendations are: to deepen the River Raisin portion of the project to 27 feet; to widen to 500 feet and deepen to 28 feet the entrance channel from Lake Erie; to provide a new turning basin able to accommodate 1,000 foot vessels; and to construct a confined disposal facility that would create a 700 acre marsh and provide shoreline protection behind the disposal facility. Although the project has not been authorized by Congress, the Monroe Harbor Study was included in the FY 1984 and FY 1985 budgets under the category "Continuation of Planning and Engineering" for the purpose of collecting updated and detailed project data, 31-37 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 reevaluating project channel dimensions and dredged material disposal requirements, reaffirming project economic and environmental feasibility, and preparing preliminary project design. Although no major change in the scope of the recommended plan is anticipated at this time, a reduction in recommended channel width and alternative dredge material disposal options were considered. Work in FY 85 consisted of the evaluation of several alternative channel designs, detailed dredge quantity estimates, and cost estimates for dredging and alternative disposal options. The District conducted a survey of prospective harbor users to update and confirm the projected waterborne commerce that would benefit from the project. Comprehensive benefit evaluation of project users was also accomplished. A preliminary benefit-cost analysis was completed to update the economic evaluation of the project. The user survey confirmed the Monroe project as a multi-user project, with Detroit Edison continuing to be the predominant user; however, it also identified a significant reduction in the projected waterborne commerce by Detroit Edison in the near future. Consequently, the benefit-tocost evaluation indicated that the project is not now needed by 1994, and suspension of the project under the C.P.&E. category was recommended on July 8, 1985. 88. ADVANCED ENGINEERING AND DESIGN Continuing AE&D costs for Green Bay Harbor were $17,430. 89. CQLLECTION AND STUDY OF BASIC DATA a. Coordination Studies with Other Agencies. These studies include Special Investigations $15,000; F.E.R.C. $3,000; Soil Conservation Service $2,000; Coordination with States (Section 22) $60,009; International Water Studies $24,000; and Flood Plain Management Services $157,711. A special hydrologic study to develop a regional flood frequency study for the Saginaw River Basin was initiated in FY 80, and the preparation of a final report was initiated in FY 85. Costs for this project in FY 85 were $2,000. b. Flood Insurance Studies. Four Michigan Flood Insurance Studies were completed in FY 85. They were Taylor City, Wayne County; Huron Township, Wayne County; Litchfield City, Hillsdale County; and Manistee City, Manistee County. The studies were completed at a total cost of $183,266. The FY 85 costs were $168, $5,523, $10,211, and $15,024, respectively, Flood Insurance Studies for the Township of Hamlin, Mason County; City of Sault Ste. Marie, Chippewa County; Township of Summit, Mason County; and City of Blissfield, Lenawee County, will be completed in FY 86, at a total cost of $103,860. The FY 85 costs associated with these studies were $21,234, $20,190, $23,143, and $9,530, respectively. Work was initiated on the Allen County, Indiana ($19,057); and City of Bangor, Van Buren County ($672) Flood Insurance Studies at a total FY 85 cost of $19,729. 31-38 DETROIT, MICHIGAN DISTRICT TABLE 31-A COST AND FINANCIAL STATEMENT See Total Cost Section to in Text Project Funding FY 82 FY 83 FY 84 FY 85 Sept. 30, 1985 1. Alpena Harbor, MI 2. Arcadia Harbor, MI 3. Ashland Harbor, WI 4. AuSable Harbor, MI 5. Black River Harbor, MI (P.H.) Contributed Funds 6. Black River Harbor, MI (U.P.) 7. Bolles Harbor, MI New Work Approp. Cost Maint. Approp. Cost Diked Disposal Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost Diked Disposal Approp. Cost - - - 559,103 - - - 559,103 56,800 153,800 62,514 291,000 48,350 155,998 67,248 263,563 193,000 88,000 238,000 211,002 77,490 246,921 -31,318 6,856 - 30,292 7,173 - 2,900 11,098 654 2,900 10,203 - 11,000 11,000 - 11,000 10,912 1,435 5,710 27,552 15,687 10,305 11,014 1,338 2,233 81,000 65,033 26,412 18,642 31-39 337,3941 337,3941 912,692 912,692 57,524 57,524 1,138,362 1,110,199 1,695,645 1,695,645 2,495,348 2,480,745 209,7762 209,7762 2,468,614 2,468,614 480,244$ 480,2448 349,921 349,921 508,1324 508,1324 383,350 383,350 584,423 568,368 426,4136 426,4136 902,877 895,107 1,190,550 1,190,550 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 31-A (Continued) COST AND FINANCIAL STATEMENT See Total Cost Section to in Text Project Funding FY 82 FY 83 FY 84 FY 85 Sept. 30, 1985 8. Charlevoix New Work 9. Cheboygan Harbor, MI 10. Clinton River MI 11. Cornucopia Harbor, WI 12. Detour Harbor, MI Contributed Funds 13. Detroit River, MI 14. Duluth-Superior Harbor, MN and WI Harbor, MI 1,329,000 314,000 272,000 63,000 1,320,896 310,454 288,220 , 52,979 Approp. Cost Maint. Approp. Cost Rehab. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost Diked Disposal Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost Diked Disposal Approp. Cost New Work Approp. Cost 26,881 12,660 16,001 26,898 12,660 16,001 25,000 33,000 115,000 20,444 33,412 88,419 98,766 - 108,168 - 250,000 - 214,981 -864 250,000 -45,564 312,101 -30,626 2,396 2,798 6,539 6,539 40,000 62,567 - 118,086 - 112,517 -34,600 - 1,455 - -975 - 280 1,478 - 280 1,478 5,515,500 8,675,000 3,894,546 4,798,059 8,530,302 4,546,281 982,000 964,292 - -14,000 3,610 5,459 5,975 4,266 3,900 9,438,900 8,932,080 25,000 22,256 180,623 180,623 4,871,900 4,859,672 1,129,396 1,129,396 504,236 504,236 877,258 875,578 549,7986 549,7986 1,014,797 1,014,797 390,200 382,038 462,653 462,653 825,960 820,391 1,354,910 1,354,910 1,204,436 1,204,436 6,024 5,658 76,877,3577 76,877,3577 69,147,024 68,411,360 41,400,694 41,396,227 16,109,2588 16,109,2588 31-40 357,455 15,000 10,000 358,180 12,608 10,585 DETROIT, MICHIGAN DISTRICT TABLE 31-A (Continued) COST AND FINANCIAL STATEMENT See Total Cost Section to in Text Project Funding FY 82 FY 83 FY 84 FY 85 Sept. 30, 1985 15. Eagle Harbor, MI 16. Fox River, WI 17. Frankfort Harbor MI 18. Grand Haven Harbor, MI Section 111 Section 111 Contributed Funds 19. Grand Marais Harbor, MN Maint. Approp. Cost Diked Disposal Approp. Cost Rehab. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost Rehab. Approp. Cost Diked Disposal Approp. Cost New Work Approp. Cost New Work Approp. Cost Maint. Approp. Cost Rehab. Approp. Cost Diked Disposal Approp. Cost Maint Approp. Cost Maint. Approp. Cost New Work Approp. Cost 1,581,000 2,348,000 2,431,000 1,584,912 1,886,071 2,687,668 3,377,400 3,493,775 - 2,410,000 - 2,291,677 33,408,570 33,300,337 1,556,249 1,556,249 2,410,000 2,291,677 205,164' 205,164' 14,348 7,000 13,353 7,402 1,571,000 1,780,000 1,782,000 1,582,634 1,752,331 1,603,620 1,891,000 -476,000 372,500 415,288 994,733 367,153 736,000 35,000 699,539 82,950 983,000 3,747,000 887,546 1,007,378 1,024,174 3,551,803 15,000 145,000 125,000 15,000 139,860 70,860 - 27,200 - - - 15,334 593 1,018,000 1,247,075 72,000 75,243 75,700 75,700 3,753,33410 3,753,33410 35,832,67311 35,790,21811 1,955,15912 1,955,15912 6,233,897 6,226,720 274,776 274,776 - 1,204,500 23 1,204,500 1,442,616 1,497,972 203,184 236,764 251 1,283,46913 1,283,46918 175,000 175,000 19,768,45514 19,764,71414 813,613 813,613 780,400 780,400 552,184 526,484 27,200 15,585 450,972 450,972 31-41 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 31-A (Continued) COST AND FINANCIAL STATEMENT See Total Cost Section to in Text Project Funding FY 82 FY 83 FY 84 FY 85 Sept. 30, 1985 20. Grand Traverse, MI Section 111 21. Green Bay Harbor, WI 22. Hammond Bay Harbor, MI Section 111 Section 111 23. Harbor Beach Harbor, MI 24. Harrisville Harbor, MI Maint. Approp. Cost Rehab. Approp. Cost New Work Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost Diked Disposal Approp. Cost New Work Approp. Cost New Work Approp. Cost Maint. Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost Rehab. Approp. Cost Diked Disposal Approp. Cost New Work Approp. Cost - 34,910 50,000 292,000 - 19,174 44,199 273,423 935,879 895,765 1,230,000 1,230,000 197,771 197,771 3,000 5,000 31,000 2,717 5,153 31,167 113,000 253,800 18,000 135,611 52,038 229,186 10,000 75,000 1,909 78,574 1,066,500 1,605,000 656,535 1,904,126 51 11,000 11,830 917,350 1,035,672 961,792 1,069,546 10,000 104,000 230,000 395,000 9,740 101,122 211,613 390,568 87,000 -10,000 63,513 10,243 3,244 200,000 -9,180 4,000 139,629 51,191 3,683 - - 25,000 - - 19,202 68,875 58,841 2,669 634,000 130,000 60,000 532,200 634,000 73,791 113,766 525,580 40 31-42 340,000 -90,000 -15,000 17,633 232,368 -63,981 68,300 68,266 1,574,283 1,574,283 10,021,39515,16 10,016,80615,16 14,202,23517 14,169,61817 6,293,807 6,267,850 1,015,366 1,015,366 77,000 77,000 425,937 415,586 25,000 21,871 1,200,598 1,200,598 5,725,390 5,716,327 194,504 194,504 243,100 243,100 1,886,638 1,837,657 DETROIT, MICHIGAN DISTRICT TABLE 31-A (Continued) COST AND FINANCIAL STATEMENT See Total Cost Section to in Text Project Funding . FY 82 FY 83 FY 84 FY 85 Sept. 30, 1985 Section 111 Contributed Funds Section 111 25. Holland Harbor, MI Section 111 Section 111 26. Inland Route, MI 27. Kenosha Harbor, WI 28. Kewaunee Harbor, WI - 250,000 70,000 - 3,794 259,445 45,000 430,000 22,000 25,246 152,128 320,813 - 136,097 4,000 - 131,724 8,239 Maint. Approp. Cost New Work Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost New Work Approp. Cost Maint. Approp. Cost Maint. Approp. Cost Rehab. Approp. Cost Diked Disposal Approp. Cost New Work Approp. Cost Maint. Approp. Cost Diked Disposal Approp. Cost New Work Approp. Cost Maint. Approp. Cost Rehab. Approp. Cost Diked Disposal Approp. Cost New Work Approp. Cost 13,000 11,137 -32,516 24,215 6,401 3,376 571,720 934,563 25,000 39,000 35,000 558,000 25,875 36,665 33,713 421,857 399,000 333,000 2,400 367,917 349,018 12,934 245,000 -44,000 195,901 5,330 - 100,000 - 90,467 267,000 100,000 265,840 79,795 30,000 38,658 368,000 380,004 90,000 90,723 12,000 3,726 94,491 107,405 6,000 6,000 13,000 11,137 287,454 287,454 502,000 502,000 754,598 751,439 771,82718,19 771,82718,19 621,000 621,000 11,899,712 11,895,430 766,200 626,435 502,452 502,452 1,663,300 1,663,300 918,22220 918,22220 2,145,888 2,141,167 404,300 404,300 988,969s21,22 979,82021,s 2,752,8682 2,751,4142 1,270,275 1,270,275 4,378,600 4,378,600 758,33324 758,33324 31-43 437,000 3,021,100 1,422,760 448,559 2,320,232 1,758,195 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 31-A (Continued) COST AND FINANCIAL STATEMENT See Total Cost Section to in Text Project Funding FY 82 FY 83 FY 84 FY 85 Sept. 80, 1985 29. Keweenaw Waterway, MI 30. Knife River Harbor, MN 31. LaPointe Harbor, WI 32. Lac La Belle Harbor, MI 33. Lake St. Clair, MI, Channels 34. Leland Harbor, MI Maint. Approp. Cost Rehab. Approp. Cost Diked Disposal Approp. Cost New Work Approp. Cost Maint. Approp. Cost Diked Disposal Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost Diked Disposal Approp. Cost New Work Approp. Cost Maint. Approp. Cost 359,000 625,400 406,250 189,000 354,382 607,019 400,880 218,132 781,000 786,462 747 7,000 7,000 3,310,591w 3,310,305w 617,300 617,300 2,961,461 2,961,461 5,974,141 5,974,141 393,000 410,000 309,000 410,000 10,870,6842 400,985 345,687 329,088 438,285 10,852,720m 7,000 101,000 70,000 7,000 78,172 90,863 72,000 70,506 17,233 4,203 24,638 824 4,203 23,808 1,654 - - 9,794 - - 9,669 40,000 75,000 170,000 29,475 50,745 204,780 37,432 32,110 13,551 11,572 5,280 5,280 701,000 346,000 745,400 297,000 697,332 323,961 767,954 299,095 75,000 70,671 31-44 189,000 236,466 177,087 251,778 66,600 62,264 250,000 246,541 412,945 412,945 287,523 282,201 130,874 130,874 88,089 85,985 269,270 269,270 472,921 472.921 7,675,357V 7,675,357V" 6,892,484n 6,874,129" 5,119,800 5,119,800 1,027,089n 1,027,0892 1,413,511 1,408,235 DETROIT, MICHIGAN DISTRICT TABLE 31-A (Continued) COST AND FINANCIAL STATEMENT See Total Cost Section to in Text Project Funding FY 82 FY 83 FY 84 FY 85 Sept. 30, 1985 35. Lexington Harbor, MI Contributed Funds Section 111 Section 111 36. Little Lake Harbor, MI 37. Ludington Harbor, MI Section 111 Section 111 38. Mackinaw City Harbor, MI 39. Manistee Harbor, MI Rehab. Approp. Cost New Work Approp. Cost New Work Approp. Cost New Work Approp. Cost Maint. Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost New Work Approp. Cc3t Maint. Approp. Cost Rehab. Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost Rehab. Approp. Cost 70,678 70,678 -7,000 541 35,000 25,000 12,000 35,000 24,973 11,033 180,000 - 20,000 135,425 44,575 19,789 3,131 4,125 254,000 101,984 168,000 129,000 165,283 229,458 168,012 106,875 135,253 256,986 85,000 - - - 89,058 - - - 618,000 549,500 564,366 427,900 432,231 726,766 544,182 420,722 15,000 15,000 710,540 692,796 27,525 16,852 402,000 190,000 474,300 393,114 195,904 466,666 29,000 36,254 1,646,304 1,646,304 1,088,888 1,088,888 372,000 372,000 124,044 124,044 454,000 301,773 600,478 s 600,4788 2,505,515 2,480,886 7,912,20281 7,912,20281 620,000 620,000 8,077,566w 8,039,629N 357,913 357,913 725,540 707,796 136,286m 136,2868 71,115 60,442 2,696,522M 2,696,522M 4,338,733" 4,335,3538. 1,374,164 1,374,164 31-45 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 31-A (Continued) COST AND FINANCIAL STATEMENT See Total Cost Section to in Text Project Funding FY 82 FY 83 FY 84 FY 85 Sept. 80, 1985 40. Manistique New Work Harbor, MI 41. Manitowoc Harbor, WI Contributed Funds 42. Marquette Harbor, MI 43. Menominee Harbor & River MI & WI Contributed Funds 44. Milwaukee Harbor, WI Approp. Cost Maint. Approp. Cost Rehab. Approp. Cost New Work Approp. Cost Maint. Approp. Cost Diked Disposal Approp. Cost New Work Approp. Cost New Work Approp. Cost Maint. Approp. Cost Rehab. Approp. Cost New Work Approp. Cost Maint. Approp. Cost Rehab. Approp. Cost Diked Disposal Approp. Cost New Work Contrib. Cost New Work Approp. Cost Maint. Approp. Cost 176,279 169,000 -27,000 165,758 147,738 4,784 745,000 250,000 664,971 324,112 468,000 753,000 463,988 297,937 5,000 5,000 10,000 -141,950 22,154 -137,174 309,690 736,277 1,423,000 381,800 9,206 995,914 799,140 1,883 120,000 119,105 477 73,192 987 73,577 57,367 33,000 113,000 53,835 33,898 36,520 124,000 125,891 -74,718 114,139 22,448 21,556 55,000 123,282 40,000 46,000 47,000 110,000 37,653 24,427 64,434 101,568 1,243,000 410,000 1,106,700 1,237,384 412,327 1,027,490 1,299,355 1,299,355 1,861,645 1,861,645 316,333 316,333 2,048,91487 2,048,9148 4,631,515 4,600,8998 3,081,756 3,081,756 1,939,288 1,911,076 1,282,893 1,282,893 1,602,897 1,602,005 465,757 465,757 533,476" 533,4768 1,680,454 0 1,668,62240 1,351,862 1,351,852 603,660 588,726 36,762 36,762 - 8,231,02441 - 8,231,02441 74,000 24,156,2744 168,317 24,153,0732 31-46 I DETROIT, MICHIGAN DISTRICT TABLE 31-A (Continued) COST AND FINANCIAL STATEMENT . See Total Cost Section to in Text Project Funding FY 82 FY 83 FY 84 FY 85 Sept. 30, 1985 45. Monroe Harbor, MI Contributed Funds 46. Muskegon Harbor, MI Section 111 Section 111 47. New Buffalo Harbor, MI Contributed Funds Rehab. Approp. Cost Diked Disposal Approp. Cost New Work Approp. Cost Maint. Approp. Cost Diked Disposal Approp. Cost Diked Disposal Approp. Cost New Work Approp. Cost New Work Approp. Cost Maint. Approp. Cost Maint. Approp. Cost Rehab. Approp. Cost New Work Approp. Cost New Work Approp. Cost Mainit. Approp. Cost Diked Disposal Approp. Cost - 2,010,000 - 1,940,752 872,000 398,000 777,450 1,873,000 864,138 380,264 656,686 1,936,061 11,599,000 22,268,000 2,850,000 11,508,018 19,021,218 6,152,561 85,000 77,130 995,000 1,024,457 3,901,810 3,832,562 6,380,925 6,380,925 987,340 987,3404 11,137,2204 11,042,7538 38,638,900 38,604,081 85,000 610 77,740 409,000 207,000 579,000 396,535 209,364 574,185 20,000 40,000 20,000 20,000 33,785 16,028 - 3,800,000 -350,000 - 74,251 3,315,594 81,000 90,592 48,000 34,955 5,100,000 4,996,129 10,650 204,870 112,000 311,600 12,650 204,085 105,922 173,015 5,000 - - - 6,419 - - - 2,912,110" 2,912,110" 105,000 105,000 5,358,115' 5,352,624,6 311,000 287,768 12,421,000 12,262,974 1,285,716 1,285,716 1,186,467 1,186,467 2,272,153 2,126,705 181,500 181,500 31-47 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 31-A (Continued) COST AND FINANCIAL STATEMENT See Total Cost Section to in Text Project Funding FY 82 FY 83 FY 84 FY 85 Sept 30, 1985 48. Oconto Harbor, New Work 49. Ontonagon Harbor, MI 50. Pentwater Harbor, MI 51. Petoskey Harbor, MI 52. Point Lookout Harbor, MI Contributed Funds 53. Port Austin Harbor, MI WI - 12,278 11,018 - 12,278 10,207 25,662 26,473 - 100,000 157,000 150,000 - 91,417 162,633 145,546 556,000 215,000 359,300 544,000 552,932 211,013 353,444 541,664 6,000 - - - 6,000 - - - Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost Diked Disposal Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost Diked Disposal Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost Diked Disposal Approp. Cost - 218,074 - 213,805 26,528 419,721 124,734 441,522 28,633 244,539 263,875 291,697 - 12,000 -- 8,651 540 15,658 17,272 540 15,658 9,795 531,472 48,528 130,754" 130,7544 1,086,82147 1,086,82147 803,903" 796,799" 6,764,55349 6,749,29049 21,000 21,000 179,899 179,899 2,830,589 2,824,862 118,239 118,239 541,420 537,151 2,642,584 2,642,584 1,237,090 1,051,224 121,600 121,600 12,000 8,651 1,128,33450 1,128,3345 1,565,020 1,074,599 159,000 159,000 31-48 131,000 82,000 97,533 174,004 128,583 81,223 99,697 169,340 DETROIT, MICHIGAN DISTRICT TABLE 31-A (Continued) COST AND FINANCIAL STATEMENT See Total Cost Section to in Text Project Funding FY 82 FY 83 FY 84 FY 85 Sept. 30, 1985 54. Portage Lake, MI 55. Port Sanilac Harbor, MI Contributed Funds Section 111 Contributed Funds Section 111 56. Port Washington Harbor, WI Contributed Funds 57. Port Wing Harbor, WI 58. Presque Isle Harbor, MI Section 111 New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost New Work Approp. Cost New Work Approp. Cost Maint. Approp. Cost Maint. Approp. Cost Diked Disposal Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost Diked Disposal Approp. Cost New Work Contrib. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost New Work Approp. Cost -6,000 4,185 1,340 -8,258 5,102 1,584 52,000 3,738 16,522 74,219 6,476 16,065 13,336 8,554 16,000 9,552 177,000 15,000 230,000 249,000 147,833 41,228 222,335 71,321 -21,000 806 106,000 10,000 157,000 103,856 12,147 157,000 24,313 21,027 9,000 4,000 245,717 8,999 4,001 236,862 - 5,000 30,700 30 2,474 32,626 600 31-49 256,129 256,129 1,430,832 1,424,920 909,963 909,963 487,108 487,108 336,000 336,000 1,573,412 1,566,507 115,000 115,000 9,158 9,158 802,000 613,717 2,582,20451 2,582,20451 2,426,381 u 2,423,0955 10,621 10,621 1,624,000 1,624,000 63,393 63,393 839,746 830,891 1,190,492 1,190,492 61,700 61,700 i i i REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 31-A (Continued) COST AND FINANCIAL STATEMENT See Total Cost Section to in Text Project Funding FY 82 FY 83 FY 84 FY 85 Sept. 80, 1985 59. Racine Harbor, WI Section 111 Section 111 60. Rouge River, MI 61. Saginaw River, MI (Federal Funds) (Contributed Funds) Maint. Approp. Cost Rehab. Approp. Cost Diked Disposal Approp. Cost New Work Approp. Cost New Work Approp. Cost Maint. Approp. Cost Rehab. Approp. Cost Diked Disposal Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost Diked Disposal Approp. Cost New Work Approp. Cost New Work Approp. Cost Maint. Approp. Cost Diked Disposal Approp. Cost 4,999 34,830 203,347 4,999 33,128 134,363 11,000 - - 10,333 697 - 2,000 1,999 -63,355 7,331 1 - 168,000 16,636 95,011 168,026 16,636 93,011 - 35,000 20,000 - 26,698 28,178 22,083 24,083 51,000 43,920 568,000 394,000 859,615 776,500 236,548 675,053 835,802 836,762 420,000 395,630 -1,210 24,085 2,305,000 2,333,400 5,531,140 2,303,739 2,030,316 5,729,604 10,000 4,885 2,781,675 2,829,598 570,000 90,000 223,000 260,000 560,815 89,284 184,873 256,689 31-50 705,702 705,702 76,500 76,500 16,500 16,500 1,297,315" 1,297,315" 35,000 35,000 2,932,520M 2,932,520" 1,253,645 1,253,645 3,948,754 3,948,754 106,000 98,796 675,251" 675,2516 15,035,903" 15,021,303" 14,523,823 14,516,701 14,917,12767 14,917,12767 13,600 13,600 32,123,095 32,058,088 19,003,400 18,951,981 DETROIT, MICHIGAN DISTRICT TABLE 31-A (Continued) COST AND FINANCIAL STATEMENT See Total Cost Section to in Text Project Funding FY 82 FY 83 FY 84 FY 85 Sept. 30, 1985 62. St. Clair River, New Work MI 63. St. Joseph Harbor, MI Section 111 Section 111 64. St. Marys River, MI Saugatuck Harbor, MI and Kalamazoo River, MI Saxon Harbor, WI Section 111 Approp. Cost Maint. Approp. Cost New Work Approp. Cost New Work Approp. Cost Maint. Approp. Cost Rehab. Approp. Cost Diked Disposal Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost Diked Disposal Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost New Work Approp. Cost Maint. Approp. Cost 895,000 1,781,000 1,224,256 839,687 1,792,998 1,259,444 1,510,000 1,462,529 272,000 448,000 413,616 511,900 270,089 434,728 423,156 506,647 42,000 58,000 21,000 135,000 41,801 19,428 51,533 127,783 481,000 361,000 333,000 114,000 480,999 323,946 258,348 152,156 8,394,000 8,818,256 10,006,700 8,368,270 8,329,035 10,323,209 9,221,000 8,973,402 19,213,246m 19,213,246" 14,004,813 13,941,930 976,485 9 976,4850 828,000 828,000 7,573,465 7,561,620 962,216 962,216 643,776 628,313 2,615,300 2,541,748 160,657,071W 160,657,0706 166,862,308 166,249,828 13,100 13,100 180,000 182,000 -15,000 173,866 151,739 19,969 - 45,000 41,500 - 44,008 39,200 - 7,767 6,649 - 7,767 6,649 265,100 249,974 3,000 4,685 59,259 36,398 364,52761 364,52761 2,923,727a2 2,906,9848 426,5076 426,469U 669,000 667,393 413,365 390,504 31-51 65. 66. REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 31-A (Continued) COST AND FINANCIAL STATEMENT See Total Cost Section to In Text Project Funding FY 82 FY 83 FY 84 FY 85 Sept 80, 1985 67. Sheboygan New Work Harbor,WI 68. South Haven Harbor, MI Section 111 Section 111 69. Sturgeon Bay, WI & Lake MI Ship Canal, WI 70. Two Rivers Harbor, WI Approp. Cost Maint. Approp. Cost Rehab. Approp. Cost Diked Disposal Approp. Cost New Work Approp. Cost New Work Approp. Cost Maint. Approp. Cost Rehab. Approp. Cost Diked Disposal Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost Diked Disposal Approp. Cost Rehab. Approp. Cost New Work Approp. Cost Maint. Approp. Cost 54,000 843,000 775,000 216,036 167,298 1,449,627 47,000 66,000 203,000 33,557 71,290 200,475 157,000 124,641 82,000 68,476 257,000 121,881 -10,000 148,868 252,484 100,849 15,372 133,324 -15,000 -11,670 25,000 483,000 14,741 125,600 160,000 93,000 72,000 406,000 161,681 105,873 68,069 234,819 7,000 28,000 -9,000 5,716 10,823 9,057 37,000 25,485 -40,191 10,987 27,000 131,000 25,313 10,987 26,890 119,914 1,136,088" 1,136,088' 4,484,3926 4,446,7368 609,028 609,028 922,792 898,497 452,4266 452,4268 532,000 532,000 3,397,46667 3,381,72267 1,632,076 1,632,076 42,381 42,381 832,000 464,341 1,059,7226 1,059,7224 6,922,615� 6,747,050" 311,119 299,165 884,899 884,899 360,32070 360,32070 5,364,08871 5,352,89271 31-52 DETROIT, MICHIGAN DISTRICT TABLE 31-A (Continued) COST AND FINANCIAL STATEMENT See Total Cost Section to in Text Project Funding FY 82 FY 83 FY 84 FY 85 Sept. 80, 1985 71. White Lake Harbor, MI Section 111 Section 111 79. Kawkawlin River, MI 80. Saginaw River, MI (Federal Funds) (Contributed Funds) 81. Sebewaing River, MI 85. Surveillance of North Boundary Waters Diked Disposal Approp. Cost Rehab. Approp. Cost New Work Approp. Cost New Work Approp. Cost Maint. Approp. Cost Maint. Approp. Cost Maint. Approp. Cost New Work Approp. Cost New Work Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost 100,000 45,000 -5,300 - 98,292 39,731 1,678 - 129,000 96,000 -20,000 193,000 127,145 63,364 13,691 189,917 - 262,000 - 214,040 - 250,000 - 234,889 686,000 1,855,000 689,949 1,523,178 658,400 957,427 26,000 32,000 -10,500 26,000 9,533 11,411 1,091,700 1,165,000 1,234,000 1,104,894 1,092,046 1,281,669 7,271 180,000 108,667 17,000 7,332 1,596,000 1,587,312 1,187,472 1,187,472 58,057 58,057 207,862 207,862 249,700 249,700 2,060,463 2,056,580 262,000 214,040 250,000 242,160 24,553,359 24,444,900 173,000 172,997 365,64272 365,64272 382,644 372,420 38,894,33478 38,833,4168 'Includes 18,889 for previous projects. 'Includes 114,786 for previous projects. 'Includes 5,849 for previous projects. 4Includes 12,008 for maintenance previous projects. 'Includes 255,000 Contributed Funds. 'Includes $25,500 for previous projects and $289,752 Contributed Funds for existing projects. 'Includes $2,097,254 for previous projects. 'Ineludes $1,547,195 for new work for previous projects. 'Excludes 27,800 for previous projects. "Includes ,239,910 for previous projects. "Includes 89,309 for previous projects. "Includes 1,709 Contributed Funds. q"Includes 311,329 for previous projects. "Includes 13,487 for previous projects. 16Includes $396,974 for previous projects. 1lqncludes 109,463 for previous projects. 17Includes 8,918 for previous projects. "aIncludes 176,620 for new work, $127,598 for maintenance. 1qncludes $35,705 Contributed Funds. 20Includes $148,000 Contributed Funds for existing project. "Includes $453,839 for previous projects. Excludes $3,000 Contributed Funds. "24Includes $21,818 for previous projects. Ulncludes 149,312 for previous projects. "Includes $88,364 for previous projects. "Includes $402,242 for previous projects. "Includes 656,000 for previous projects. 31-53 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 31-A (Continued) COST AND FINANCIAL STATEMENT See Section in Text Project Funding FY "Includes 235,346 for previous projects. "Includes $34,139 Contributed Funds. "Includes 7,670 Contributed Funds. "Includes $491,416 for previous projects. Includes $126,451 for previous projects. "Excludes $136,286 Contributed Funds. "Includes 54,999 for previous projects. "Includes 150,910 for previous projects. "Includes ,955 for previous projects. 'Includes 00,126 for previous projects. "Includes ,288 for previous projects. "Includes 312,423 for previous projects. 'lncludes 6,194 for previous projects. 41Includes 1,293,220 or previous projects. alncludes 59,305 for previous projects. "Includes ontributed Funds of $300,000 for new work and $166 667 for maintenance Contributed by: Port Commission of Monroe $300,000; Consolidated Paper Co. $125,000 and River Raisin taper Co., $41,667. "Includes 613,408 for previous projects. "Includes $446,183 for previous projects. "Includes $84,569 for previous projects. '7 Includes $8,161 for previous projects. "Includes 284,802 for previous projects. 4Includes 113,326 for previous projects. Total Cost to 82 FY 83 FY 84 FY 85 Sept. 30, 1985 "Includes ,172,100 Contributed Funds. '1Includes 188,495 for previous projects. "Includes 15,123 for previous projects. "lncludes 27,240 for previous projects. "Includes 79,537 for previous projects. WIncludes ,084 for previous projects. "Includes 56,608 for previous projects. 7lIncludes 962,556 for previous projects. "Includes 1,671,660 Public Works Funds and $49,419 Emergency Relief Funds. "Includes 503,113 for previous projects. "Includes $2,904,807 for previous projects. 'Includes 90,232 for previous projects. "Includes $117,554 for previous projects. Excludes $50,193 Contributed Funds. "Includes 87,817 for previous projects. "Includes 7,131 for previous projects. "Includes 187,233 for previous projects. "Includes 131,239 for previous projects. "Includes 323,419 for previous projects. "Includes 219,730 for previous projects. 70lncludes 212,857 for previous projects. 7721Includes 33,113 for previous projects. Includes 15,000 for previous projects. nIncludes 3,973,897 for previous projects. 31-54 TABLE 31-B DETROIT, MICHIGAN DISTRICT AUTHORIZING LEGISLATION Acts Work Authorized Documents Sep. 19,1890 Mar. 2, 1919 Sep. 2, 1919 Aug. 30, 1935 Oct. 27, 1965 Mar. 3, 1905 Aug. 5, 1886 Aug. 11, 1888 Mar. 3, 1899 Jun. 6,1900 Aug. 8, 1917 Jul. 3, 1930 Aug. 30, 1935 Mar. 2, 1945 Jul. 14, 1960 Mar. 2, 1945 Sep. 19,1890 Jul. 13, 1892 Sep. 22,1922 Jul. 8, 1930 ALPENA HARBOR, MI (See Section 1 of Text) Channel depth of 16% feet Rubblemound breakwater for protecting channel on south side and widening entrance channel. 21 and 18% foot channel depths and turning basin Present project dimensions, New turning basin Removal of old breakwater, and construction of new breakwater. ARCADIA HARBOR, MI (See Section 2 of Text) Maintenance of existing 12-foot channel. ASHLAND HARBOR, WI (See Section 3 of Text) Breakwater 7,900 feet long and dredging to remove a shoal. Appropriation of $60,000 for 'Continuing improvement on enlarged project.' (On completion of Poe Lock in 1896, with available depth of 20 feet, dredging at Ashland Harbor was carried to a similar depth.) Detached breakwater extending 4,700 feet out from shore at a point 2,600 feet east of main breakwater (prolonged) and parallel thereto. Project modified by omitting detached breakwater and defining depth and extent of channel to be dredged. Widening part of present channel for entrance channel and for basin in eastern part of harbor. Deepening east basin to 25 feet and west channel, as far as 8th Ave. West extended to 21 feet. Widening west channel to 750 feet at its westerly end. Deepening portions of East Basin and West Channel to 27 and 21 feet, respectively. AU SABLE HARBOR AT AU SABLE RIVER (OSCODA), MI (See Section 4 of Text) Dredging channels 12 and 10 feet deep and riprapping North Pier. BLACK RIVER (PORT HURON), MI (See Section 5 of Text) Channel from mouth of Grand Trunk R.R. Bridge. Channel from Grand Trunk R.R. Bridge to Washington Ave. Consolidation of projects for Black River at Port Huron and Mouth of Black River. Settling Basin. Annual Report, P. 2288, H. Doc. 830, 65th Cong., 2d Sess., and Rivers Committee Doc. 1, 67th Cong., 1st Sess. Rivers and Harbors Comm. Doc. 42, 72d Cong., 1st Sess. H. Doc, 151, 88th Cong.,lst Sess.1 H. Doc. 194, 58th Cong., 2d Sess. H. Ex. Doc. 89, 48th Cong., 2d Sess. Annual Reports, 1886, p. 1674; and 1887, p. 1966. H. Doc. 1698,64th Cong., 2d Sess. S. Doc. 133, 71st Cong., 2d Sess. Rivers and Harbors Committee Doc. 46, 82d Cong., 1st Sess. H. Doc. 337, 77th Cong., 1st Sess. H. Doc. 165, 86th Cong.,lst Seas.1 H. Doc. 446, 78th Cong., 2d Sess.1 Annual Report 1889, p. 2291 No Printed Report H. Doc. 436, 64th Cong., 1st Sess. H. Doc. 162, 71st Cong., 2d Sess. 31-55 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 31-B (Continued) AUTHORIZING LEGISLATION Acts Work Authorized Documents Aug. 30, 1935 Apr. 23, 1970 Mar. 2, 1945 Jul. 6, 1965 Aug. 14, 1876 Aug. 2, 1882 Jun. 13, 1902 Jun. 20, 1938 Mar. 29, 1977 Jun. 3, 1896 Mar. 2, 1907 Aug. 26, 1937 May 17,1950 Oct. 21, 1964 Aug. 5,1886 Jul. 19, 1963 Aug. 26, 1937 Deepening channel and settling basin to 20 feet, and widening to 100 feet 2 bends; 1 at the foot of 12th St., the other below the Grand Trunk R.R. Bridge. Extension of existing channel. BLACK RIVER HARBOR, MI (UPPER PENISULA) (See Section 6 of Text) Two converging breakwaters, an entrance channel between breakwaters, an inner channel, and an irregular harbor basin. Project depths 12 feet in approach channel and 8 feet in the river channel and basin. BOLLES HARBOR, MI (See Section 7 of Text) Entrance channel in Lake Erie, Access channel in LaPlaisance Creek, Steel sheet pile revetment. CHARLEVOIX HARBOR, MI (See Section 8 of Text) Channel from Lake Michigan to Round Lake protected where needed by piers and revetments. Channel from Round Lake to Lake Charlevoix. Project depth increased to 15 feet. Project depth increased to 18 feet. Project depth increased to 24 and 23 feet, and construction of revetment upstream of Highway Bridge. CHEBOYGAN HARBOR, MI (See Section 9 of Text) 18% foot channel. 8% foot channel. Turning Basin. 21-foot channel to East 1st St., Enlarge Turning Basin, deepen to 21 feet. Breakwater. CLINTON RIVER, MI (See Section 10 of Text) Channel in River and Lake St. Clair, Pile Dike, Closing channels and making Cutoff, and revetments as needed. Widening entrance channel and constructing protected harbor basin CORNUCOPIA HARBOR, WI (See Section 11 of Text) Entrance channel 50 feet wide and 10 feet deep between existing piers from bay to a turning basin 200 feet long, 8 feet deep, with maximum width of 180 feet, with 150 and 300-foot inner channels each 50 feet wide and 8 feet deep. Rivers and Harbors Committee Doc. 54, 72d Cong., 2d Sess. Section 107, 1960 River and Harbor Act. H. Doc. 446, 78th Cong., 2d Sess.1 Section 107,1960 River and Harbor Act. S. Ex. Doc. 16, 44th Cong., 1st Sess., and Annual Report 1876, p. 523 No Prior Survey of Estimates. No Prior Survey of Estimates. S. Doc. 163, 75th Cong., 3rd Sess.x Section 107, 1960 River and Harbor Act. Annual Report, 1895, p. 2823 H. Doc. 357, 59th Cong., 1st Sess. H. Doc. 134, 75th Cong., 1st Sess. H. Doc. 269, 81st Cong., 1st Sess.1 Section 107, 1960 River and Harbor Act. S. Doc. 199, 46th Cong., 2d Sess. Annual Report 1880, p. 2062 and H. Doc. 210, 44th Cong., 2d Sess. and Annual Report 1886, p. 219 Section 107, 1960 River and Harbor Act. S. Committee, 75th Cong., 1st Seas. 31-56 DETROIT, MICHIGAN DISTRICT TABLE 31-B (Continued) AUTHORIZING LEGISLATION Acts Work Authorized Documents Sep. 3, 1954 Jun. 3, 1969 Jun. 13, 1902 Mar. 3, 1905 Jun. 25, 1910 Mar. 4, 1913 Mar. 2, 1907 Jun. 25, 1910 Mar. 2, 1910 Jul. 3, 1930 Aug. 30, 19358 Aug. 26, 1937 Mar. 2, 1945 Jul. 24, 1946 May 17, 19504 Mar. 21, 1956 Reconstruction and Federal maintenance of east and west entrance piers, a 25-foot extension of west pier and a 300-foot extension of existing westerly inner channel at a depth of 8 feet and a width of 50 feet. DETOUR HARBOR, MI (See Section 12 of Text) Small boat harbor and harbor of refuge, 10-foot channel, 8-foot deep access channel protected by 1,000-foot breakwater. DETROIT RIVER, MI (See Section 13 of Text) Amherstburg Channel and Removal of Grosse Ile Shoal. Fighting Island Channel. Livingstone Channel. Channel Depths of 26 and 25 Feet. Channel to Wyandotte 21 Feet Deep and 300 Feet Wide Through Middle Ground Opposite Head of Fighting Island. Trenton Channel and Turning Basin (West of Grosse Ile). American Channel North of Belle Isle Between Windmill Point and Fairway Slip, Detroit. Deepen Westerly 300 Feet of Amherstburg Channel and Ballards Reef Channel Below Livingstone Channel to 27 Feet to Provide Depths Adequate for 24-Foot Draft Navigation When Governing Lakes are at Datum, with Necessary Widening at Approaches and Bends and Construction of Necessary Compensating Works. Detroit River. Extend Turning Basin in Trenton Channel 600 Feet. Dredge Through East Draw of Lower Grosse Ile Bridge, and Extend 300-Foot Width of Channel North of Lower Grosse Ile Bridge. Channel Depth of 28.5 Feet Throughout Downbound and Two-Way Channels, Except in Upper (27.7-Foot Depth) and Lower, (29-Foot Depth) Livingstone Channel, and in Upbound Channel; 27-Foot Depth in Ballards Reef Channel Below Junction with Livingstone Channel. 27.5-Foot Depth in Westerly 300-Foot Width of Limekiln Crossing and Amherstburg Reaches, and 28.5- Foot Depth in Westerly 300-Foot Width of Hackett Beach, with Necessary Compensation Works. Also 28.5-Foot Depth in Lake Erie from Detroit River to Pelee Passage Shoal. Inclusive. H. Doc. 434, 83rd Cong., 2d Sess.' Section 107, 1960 River and Harbor Act. H. Doc. 712, 56th Cong., 1st Sess. and 40, 58th Cong., 3rd Sess. H. Doc. 17, 62d Cong., 1st Sess. H. Doc. 266, 59th Cong., 2nd Sess. 676, 61st Cong., 2d Sess, and 32, 65th Cong., 1st Sess. H. Doc. 253, 70th Cong., 1st Sess. Rivers and Harbors Committee Doc. 1, 72nd Cong., 1st Sess.' H. Doc. 205, 75th Cong., 1st Sess. H. Doc. 734, 79th Cong., 2d Sess. H. Doc. 335, 80th Cong., 1st Sess. S. Doc. 30, 81st Cong., 1st Sess.' S. Doc. 71, 84th Cong., 1st Sess.' 31-57 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 31-B (Continued) AUTHORIZING LEGISLATION Acts Work Authorized Documents Jul. 14, 1960 Aug. 13, 1968 Jun. 3, 1896 Jun. 13, 1902 Mar. 2, 1907 May 28, 19086 Jul. 27, 1916 Mar. 2, 1919 Jan. 21, 1927 Jul. 30, 1930' Aug. 30, 1930 Jul. 16, 19526 Jul. 14, 19607 Oct. 4, 1961 Mar. 2, 1867 Trenton Channel; Deepen to 27 Feet, Where Necessary, Wyandotte Reach from Detroit River to Upper Grosse lie Bridge, About 5.5 Miles, Deepen to 28 Feet and Widen to 300 Feet Below Upper Grosse Ile Bridge to and Including a Turning Basin 28 Feet Deep and 15 Across in Area Outside Project Limits. Trenton Channel: Deepen to 28 Feet and Widen to 300 Feet from the Upper Turning Basin at Trenton to Gibraltar, about 20,500 Feet Downstream: Construct a Turning Basin at Gibraltar at a Depth of 28 Feet. Width of 830 Feet, and Length of 1,500 Feet: Build Compensating Works to Maintain Water Levels. DULUTH-SUPERIOR HARBOR, MN AND WI (See Section 14 of Text) Dredging. Rebuilding piers at Superior Entry. Enlarge plan for Superior Entry and additional dredging near draw span of Burlington Northern railway bridge. Dredging additional area for basin inside Duluth entrance to 22-foot depth. Enlarging Superior Harbor Basin. Removal of shoal point at southerly end of East Gate Basin. Howards Bay Channel, 20 feet deep. Deepening and widening channels and basins. Deepen Superior Front Channel and a portion of East Gate Basin to 25 feet. Present project dimensions of channels and basin. Abandons northerly portion of 21st Avenue West Channel. EAGLE HARBOR, MI (See Section 15 of Text) Breakwater and dredging of entrance channel 130 feet wide to depth of 14 feet. Project modified by reduction of channel width from 130 feet to 80 feet. Project modified by increasing width of breakwater from 20 feet to 30 feet and increasing the channel from 80 to 130 feet. Project modified by omitting breakwater and constructing guide piers. H. Doc. 319, 86th Cong., 2d Sess.1 H. Doc. 338, 90th Cong., 2d Sess.i H. Ex. Doc. 59, 53d Cong., 3d Sess. and Annual Report, 1895, p. 2538. H. Doc. 82, 59th Cong., 2d ess. H. Doc. 221, 60th Cong., 1st Sess. H. Doc. 651, 64th Cong., 1st Sess. H. Doc. 1018, 64th Cong., 1st Sess H. Doc. 145, 69th Cong., 1st Sess. and Rivers and Harbors Committee, Doc. 32, 71st Cong., 2d Sess. H. Doc. 482, 72d Cong., 2d Sees. H. Doc. 374, 82d Cong., 2d Sess. H. Doc. 150, 86th Cong., 1st Sess. H. Doc. 196, 86th Cong., 1st Seas. Annual Report for 1868, p. 89. Annual Report for 1874, pp. 36, 135, and 136. Annual Report for 1877, p. 98. 31-58 TABLE 31-B (Continued) DETROIT, MICHIGAN DISTRICT AUTHORIZING LEGISLATION Acts Work Authorized Documents Mar. 2, 1945 Aug. 5,1886 Sep. 19, 1890 Jun. 3, 1896 Jun. 3, 1896 Jun. 18, 1902 Mar. 2, 1907 Mar. 3, 19258 Jun. 26, 19349 Jul. 3, 195810 Jun. 23, 186611 Mar. 3, 1925 Aug. 26, 1937 Oct. 27, 1965 Jun. 23, 1866 Jun. 14, 1880 Sep. 19, 1890 Jul. 13, 1892 Jul. 3, 1930 Aug. 26, 1937 Inner harbor basin and breakwaters and removal of east guide pier. FOX RIVER, WI (See Section 16 of Text) Improvement of Fox River Dredging Fond du Lac Harbor on Lake Winnebago. Improvement of Wolf River Improvement of Stockbridge, of Calumet and Miller Bay, and of Brothertown Harbor, on Lake Winnebago. Increased depth in rock cuts on lower river, widen Neenah Channel, and a concrete retaining wall at Kaukauna. Operation and care of locks and dams provided for with funds from War Department appropriations for rivers and harbors. Sec. 108. That Federal project structure, appurtenances, and real property of Upper Fox River, WI, be disposed of to State of Wisconsin. FRANKFORT HARBOR, MI (See Section 17 of Text) A New Outlet 12 feet deep protected by . Piers and Revetments. Exterior Breakwaters, Removal of Portions of Piers, Project Dimensions of Outer Basin. Dredge the Area in Lake Betsie Deepen Approach and Entrance Channels, Extend Inner Basin, and Dredge Recreational Anchorage Area. GRAND HAVEN HARBOR, MI (See Section 18 of Text) Piers and Revetments. Piers and Revetments. Piers and Revetments. Piers and Revetments. Present Project Dimensions of Harbor Channel to Grand Trunk Car Ferry Slip and River Channel, Eliminating all of that portion of Grand River above Bass River, Consolidation of Projects for Harbor and River. Channel to Spring Lake H. Doc. 446, 78th Cong., 2d Sess.1 Annual Report, 1885, pp. 2041-2045 [plan of a board approach Dec. 10, 1884, as modified by Corps of Engineers, May 14, 1886]. H. Ex. Doc. 24, 51st Cong. 1st Sess. Annual Report, 1890, p. 2390. No prior survey or estimates. No prior survey or estimates. No prior survey or estimates. H. Doc. 294, 68th Cong., 1st Sess.1 S. Bill 3910, 85th Cong., 2d Sess. H. Doc. 482, 55th Cong., 2d Sess. H. Doc. 208, 68th Cong., 1st Sess. H. Doe. 511, 74th Cong., 2d Sess. S. Doc. 16, 89th Cong., 1st Sess. 1 S. Ex. Doc. 42, 35th Cong., 1st Sess. S. Ex. Doc. 42, 35th Cong., 1st Sess. S. Ex. Doc. 42, 35th Cong., 1st Sess. S. Ex. Doc. 42, 35th Cong., 1st Sess. S. Doc. 88, 71st Cong., 2d Sess. Rivers and Harbors Committee Doc. 1, 75th Cong., 3d Ses.1 31-59 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 31-B (Continued) AUTHORIZING LEGISLATION Acts Work Authorized Documents Mar. 2, 1945 Mar. 3, 1879 Aug. 30, 1935 May 17, 1950 Mar. 2, 1945 Jun. 23, 1866 Jul. 13, 1892 Jun. 26, 1910 Aug. 8, 1917 Mar. 3, 1925 Aug. 30, 19352 Aug. 26, 1937 Mar. 2, 1945 Oct. 23, 1962 Mar. 2, 1945 Mar. 3, 1871 Present Project Dimensions of Harbor Channel from Car Ferry Slip to Grand Trunk Railway Bridge and Turning Basin GRAND MARAIS HARBOR, MN (See Section 19 of Text) Breakwaters and dredging of anchorage area of 26 acres to 16 feet. Seawalls across ledge in southeast corner of harbor, enlarging anchorage basin and deepening of entrance. Small-boat basin with breakwater. GRAND TRAVERSE BAY HARBOR, MI (See Section 20 of Text) Two Parallel piers, and entrance channel between piers and a harbor basin. Project depths are 12 feet between piers and 10 feet in basin. Project area extended 200 feet upstream in 1966. GREEN BAY HARBOR WI (See Section 21 of Text) Outer Channel and revetment at Grassy Islands. 2s Inner channel.' s Turning basin at DePere. Maintenance of turning basin at DePere. Increasing depth of inner channel and turning basin to 18 feet. Deepen outer channel to 22 feet with widening and straightening inside of Tail Point Bend, widen channel in Fox River through city of Green Bay to 22 feet. Turning basin above Chicago & North Western Ry. Bridge. Turning basin at mouth of East River. Deepen and widen 9 miles of entrance channel to 26 by 500 feet; 3.6 miles of entrance channel to 24 by 300 feet; and 8.2 miles of existing Fox River to 24 feet deep. HAMMOND BAY HARBOR, MI (See Section 22 of Text) Harbor of Refuge, breakwaters 10-foot depth in harbor basin 12-foot depth in entrance channel. HARBOR BEACH, LAKE HURON, MI (See Section 23 of Text) Adopted Site and made provision for harbor. H. Doc. 661, 76th Cong., 3d Sess.' H. Ex. Doc. 75, 43d Cong., 2d Seas. Annual Report, 1875, p. 184. Rivers and Harbors Committee Doc. 22, 72d Cong., 1st Sess. H. Doc. 187, 81st Cong., 1st Sess.' H. Doc. 446, 78th Cong., 2d Sess. Annual Report, 1867, p. 70. Unpublished report approved Aug. 3, 1892. H. Doc. 222, 61st Cong., 2d Sess. H. Doc. 1017,64th Cong., 1st Sess. H. Doc. 294, 68th Cong., 1st Sess. Rivers and Harbors Committee De. 40, 72d Cong., 2d Sess. Rivers and Harbors Committee Doc. 73, 74th Cong., 2d Sess. H. Doc. 95, 76th Cong., 1st Sess. H. Doc. 470, 87th Cong., 2d Sess. 1 H. Doc. 446, 78th Cong., 2d Sess. Annual Report 1873, p. 292 31-60 DETROIT, MICHIGAN DISTRICT TABLE 81-B (Continued) AUTHORIZING LEGISLATION Acts Work Authorized Documents Jan. 21, 1927 Jul. 16, 1984 Mar. 2, 1945 Aug. 30, 1852 Mar. 2, 1867 Mar. 3, 1899 Mar. 3, 1905 Jul. 8, 1930 Aug. 80, 1935 Sep. 3, 1954 Sep. 3, 1954 Sep. 2,1964 Mar. 3, 1899 Mar. 2, 1907 Aug. 80, 1935 May 17, 1950 Oct. 23, 1962 Closing North Entrance and Dredging Main Entrance and Anchorage Area. Removal of Portion of Breakwater in interest of sanitation. Deepen the waterway within the Marina facility. HARRISVILLE HARBOR, MI (See Section 24 of Text) Harbor of Refuge, Breakwaters, 12-foot depth entrance channel 10-foot depth in harbor basin. HOLLAND HARBOR, MI (See Section 25 of Text) Artificial channel between Lakes Macatawa and Michigan.12 Piers and Revetments. 12 Extending Inner Piers. Converging Breakwater. Channel to Holland and Turning Basin at Holland. Present Project Dimensions of Channels and Turning Basin. Widen Bend in Reveted Entrance Channel into Lake Macatawa, Dredge Channel in Black River, and Widen and Extend Turning Basin. THE INLAND ROUTE, MI (See Section 26 of Text) Channel 30 feet wide and 5 feet deep through Lakes and Rivers with suitable jetties. Lock and Dam. KENOSHA HARBOR, WI (See Section 27 of Text) Parallel piers and 600 feet of breakwater. 2s Extending breakwater 200 feet. Present project dimensions of entrance channel and basin. Channel northwesterly from basin. Deepen lake approach channel to 27 feet and 800 feet wide; deepen approach channel to 26 feet, entrance channel and inner basin to 25 feet. H. Doc. 1700, 64th Cong., 2d Sess H.R. 5653, 98th Cong., 2d Sess., P.L. 98-360 (98 Stat. 405) Sec. 105. H. Doc. 446, 78th Cong., 2d Sess. S. Ex. Doc. 42, 35th Cong., 1st Sess. Annual Report 1866, p. 106. H. Doc. 272, 51st Cong., 2d Sess., and Annual Report 1887, p. 2950. Annual Report 1905, p. 2176. H. Doc. 588, 69th Cong., 2d Sess. Rivers and Harbors Committee Doc. 48, 74th Cong., 1st Sess. H. Doc. 282, 83rd Cong., 2d Sess. H. Doc. 142, 82nd Cong., 1st Sess.1 Chief of Engineers. H. Doc. 328, 54th Cong., 2d Sess. Annual Report, 1897, p. 2772, H. Doc. 164, 55th Cong., 3d Sess. Annual Report, 1899, p. 1817. H. Doc. 62, 59th Cong., 2d Seas. and Rivers and Harbors Committee Doc. 3, 59th Cong., 2d Sess. Rivers and Harbors Committee Doc. 19, 74th Cong., 1st Sess. H. Doc. 750, 80th Cong., 2d Seas. H. Doc. 496, 87th Cong., 2d Seas. 31-61 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 31-B (Continued) AUTHORIZING LEGISLATION Acts Work Authorized Documents Mar. 3, 1881 Jun. 25, 1910 Aug. 30, 19352, 14 Jul. 14, 1960 Sep. 19, 1890 Jun. 25, 1910 Mar. 2, 1919 Aug. 30, 19361s5 Mar. 2, 1945 Sep. 3, 1954 Mar. 7, 1974 KEWAUNEE HARBOR, WI (See Section 28 of Text) Entrance piers. Turning basin. North breakwater, remove old north pier, widen and deepen entrance channel and turning basin to 20 feet and remove outer south shoal. Enlarge existing turning basin, extend existing project into north basin, and increase depth of north basin to 20 feet at a maximum width of 500 feet and eliminate removal of outer shoal. KEWEENAW WATERWAY, MI (See Section 29 of Text) Acquisition of waterway; for a 16-foot channel of 70-foot bottom width, renew canal revetments, reconstruct and extend piers at upper entrance to 30-foot depth of water, and at proper time for increase of channel depth to 20 feet with bottom width of not less than 120 feet (increase in width and depth of channel approved Mar. 15, 1898). Anchorage basin just within lower entrance about one-half mile long, 800 feet wide; a mooring pier on its westerly side 2,000 feet in length, and for purchase of necessary land. Princess Point Cutoff channel. General deepening, widening and straightening of channels and basins to provide 25-foot depth with additional overdepth at entrances, extend lower entrance breakwater, and necessary alteration or replacement of structures due to deepening channels. KNIFE RIVER HARBOR, MN (See Section 30 of Text) Dredging. Breakwater and modified channels. Construction of measures to correct the design deficiencies which results in unsatisfactory entrance and mooring conditions. LA POINTE HARBOR, WI (See Section 31 of Text) Provides for reconstruction of 73.5 feet of the existing breakwater, extending the breakwater 126.24 feet with 5 new steel sheet pile cells, harbor dredging and related work. The harbor is 10 feet deep in the entrance and 8 feet deep in the basin. Annual Report, 1881, p. 2082. H. Doc. 324, 60th Cong., 1st Sess. Rivers and Harbors Committee Doc. 43, 72d Cong., 1st Sess. S. Doc. 19, 86th Cong., 1st Sess. x H. Ex. Doc. 105 49th Cong., 2d Sees. and Annual Report 1887, p. 1977. H. Doc. 325, 60th Cong., 1st Ses. H. Doc. 835, 63rd Cong., 2d Sess. H. Doc. 55, 73rd Cong., 1st Sess. x H. Doc. 686, 77th Cong., 2d Seas. and Annual Report for 1949. H. Doc. 463, 83d Cong., 2d Sees. 1 Section 107 of the 1960 River and Harbor Act. P.L. 645, 86th Cong., as amended. 31-62 DETROIT, MICHIGAN DISTRICT TABLE 31-B (Continued) AUTHORIZING LEGISLATION Acts Work Authorized Documents Mar. 2, 1945 H. Doc. 446, 78th Cong., 2d Sess. Annual Report, 1961, p. 1039. LAC LA BELLE HARBOR, MI (See Section 32 of Text) Two parallel piers at the entrance, 584 and 682 feet; an entrance channel between the piers 50 feet wide and 12 feet deep, 820 feet long with a flared approach and inner canal 50 feet wide and 10 feet deep and 730 feet long. LAKE ST. CLAIR, MI, CHANNELS(See Section 33 of Text) Two Dikes. Deepening Canal and Dredging Channel at Grosse Point. Second Canal for Downbound Vessels. 21-Foot Depth in Grosse Pointe Channel for About 5.25 miles. 25-Foot Depth Through Canals and Channel Through Lake St. Clair. Removal of Center Dike and Widening Channel to 700 Feet. Deepening Channel to 27.5 Feet and Abandonment of Channel above Mouth of Southeast Bend Cutoff Channel. LELAND HARBOR, MI (See Section 34 of Text) Entrance Channel Protected by Piers. Outer Breakwater, Anchorage Area. Approach Channel and Removal of North Pier. LEXINGTON HARBOR, MI (See Section 35 of Text) Approach Channel and Maneuver Area Protected by Breakwaters.' LITTLE LAKE HARBOR, MI (See Section 36 of Text) 12-Foot Deep Channel From Lake Superior into Little Lake Breakwaters and Revetments. LUDINGTON HARBOR, MI (See Section 37 of Text) Entrance Piers. Pier Extension Reconstruction and Repairs to Existing Structures and Present Project Dimensions of Channel. Breakwaters, Shore Connections, and Removal of Outer Ends of the Two Inner piers. Deepen Channels and Widen Opening Between Breakwaters. MACKINAW CITY HARBOR, MI (See Section 38 of Text) Breakwater 430 feet long;, slope protection for about 300 feet; entrance channel 10 feet deep with minimum width of 100 feet; protected anchorage and maneuver area 3.3 acres with depth 6 to 8 feet. Rivers and Harbors Committee Doc. 23, 74th Cong., 1st Sess. H. Doc. 413, 87th Cong., 2d Sess. H. Doc. 301, 88th Cong., 2d Sess.1 H. Doc. 446, 78th Cong., 2d Sess. Annual Report 1867, p. 114 z16 H. Doc. 273, 54th Cong., 2d Sess. and Annual Report 1897, p. 2951. H. Doc. 62, 59th Cong., 1st Sees., and Rivers and Harbors Committee Doc. 3, 59th Cong., 2d Sess. z6 H. Doc. 342, 91st Cong., 2d Sess.1 Section 107, 1960 River and Harbor Act. 31-63 Annual Report 1885, p. 2150. H. Doc. 297, 51st Cong., 2d Sess. H. Doc. 234, 56th Cong., 2d Sess. H. Doc. 188, 65th Cong., 1st Sess. H. Doc. 253, 70th Cong., 1st Sess. Rivers and Harbors Committee Doc. 3, 72nd Cong., 1st Sess. S. Doc. 71, 84th Cong., 1st Sess.1 Aug. 5,1886 Jul. 13, 1892 Jun. 13, 1902 Mar. 2, 1919 Jul. 3, 1930 Aug. 30, 1933' Mar. 21, 1956 Aug. 30, 1935 Oct. 23, 1962 Oct. 27, 1965 Mar. 2, 1945 Mar. 2, 1867 Mar. 3, 1899 Mar. 2, 1907 Dec. 31, 1970 Jan. 15, 1965 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 31-B (Continued) AUTHORIZING LEGISLATION Acts Work Authorized Documents Mar. 2, 1867 Sep. 19, 1890 Jul. 25, 1912 Jul. 3, 1920 Mar. 2, 1945 Jul. 14, 1960 Mar. 3, 1905 Mar. 2, 1907 Mar. 2, 1907 Aug. 30, 193517 Aug. 26, 1937 Oct. 23, 1962 Dec. 31, 1968 (Sec. 107 of 1960 R& H) Mar. 2, 1867 Aug. 11, 1888 Jun. 25, 1910 Aug. 30, 19351 MANISTEE HARBOR, MI (See Section 39 of Text) Entrance Piers. Extending Channel 8,000 Feet to Connect with Manistee Lake, and Further Pier Extension. Depth of 20 Feet in Outer Harbor 570 Feet Wide to Outer End of South Pier 18 Feet Deep in River, South Breakwater with Shore Connection, and Extend North Pier if Required. 23-Foot Depths in Entrance Channel and 21-Foot Depths in River Channel. Remove Old South Revetment, Construct New South Pier and Revetment, and Widen River Entrance Channel. Present Project Dimensions of Channel Through Outer Basin and River and Federal Participation in Cost of Replacing Maple Street Bridge. MANISTIQUE HARBOR, MI (See Section 40 of Text) Breakwaters and Outer Harbor. Present Location of West Breakwater and Pier at River Mouth. MANITOWOC HARBOR, WI (See Section 41 of Text) Breakwaters. Present project dimensions of channel through outer basin, removal of old north stub pier, and approach channel to a proposed city terminal south of shore end of south breakwater. Channel in river. Deepen Lake approach to 25 feet by 800 feet wide, deepen outer harbor to 25 feet, river channel to 23 feet to 8th St., and Upper River Channel to 22 feet to Soo Line R.R. Dredge River Channel to 12 feet from Soo Line R.R. 720 feet upstream. MARQUETTE HARBOR, MI (See Section 42 of Text) Breakwaters, 2,000 feet long. Extending the breakwater 1,000 feet. Additional 1,500-foot extension to breakwater and and removing a shoal in northerly part of harbor. Deepening harbor to 25 feet. Annual Report 1867, p. 115. Annual Report 1891, p. 2678. H. Doc. 599, 62d Cong., 2d Sess. S. Doe. 131, 71st Cong., 2d Sess. H. Doc. 380, 77th Cong., 1st Sess. H. Doc. 358, 86th Cong., 2d Seas. H. Doc. 429, 58th Cong., 2d Seas. Annual Report 1908, p. 648, and Unpublished Report of Mar. 13, 1908. Approved by Secretary of War, Apr. 3, 1908. H. Doc. 62, 59th Cong., 1st Sess., as modified by Rivers and Harbors Committee Doc. 3, 59th Cong., 2d Sems. Rivers and Harbors Committee Doc. 39, 73d Cong., 2d Sess. Rivers and Harbors Committee Doc. 80, 74th Cong., 2d Sess. H. Doc. 479, 87th Cong., 2d Seas. Jun 1967 Detailed Project Report; Apr 1982 Supplement. H. Ex. Doe. 56, 39th Cong., 2d Sess. pts. 1 and 2, and Annual Report, 1866, pp. 8 and 77. Annual Report, 1889, pp. 272 and 2021. H. Doc. 573, 61st Cong., 2d Sems. Rivers and Harbors Committee 31-64 DETROIT, MICHIGAN DISTRICT TABLE 31-B (Continued) AUTHORIZING LEGISLATION Acts Work Authorized Documents Jul. 11, 1960 Mar. 3, 1871 Jun. 13, 1902 Mar. 4, 1913 Jul. 3, 1930 Aug. 30, 1935 Mar. 2, 1945 Jul. 14, 1960 Jun. 27,1967 Sec. 107 Aug. 30, 1852 Mar. 3,1883 Mar. 2, 1907 Sep. 22, 1922 Aug. 30, 1935 Mar. 2, 194511 Jul. 14, 1960 Oct. 23,1962 Feb. 24, 183519 Jul. 3, 1930 Deepening harbor to 27 feet. MENOMINEE HARBOR AND RIVER, MI AND WI (See Section 43 of Text) Entrance piers. Consolidation of project for harbor and river, and a channel 18 feet deep. Partial restoration of work above bridge which had been eliminated by act of May 3,1905. 20-foot depth in channel and 18-foot depth in turning basin. 21-foot depth in channel and turning basin and enlarge turning basin. Extend channel 12 feet deep to vicinity of Marinette Yacht Club. Deepen existing approach channel to 26 feet, entrance and river channels to 24 feet and enlarge turning basin. Deepen 1,100 feet of river channel generally north of Marinette Corp. facilities to 19 feet. MILWAUKEE HARBOR, WI (See Section 44 of Text) North pier.12 Inner 7,600 feet of breakwater.2 South pier. Extending north breakwater 1,000 feet. Extend north breakwater; a south breakwater; present project dimensions of inner entrance channel. Dredging a portion of outer harbor to 21-foot depth. Dredging river channels to 21-foot depth. Deepen South Menominee and Burnham Canals to 21 feet. Deepen an approach channel to 30 feet by 800 feet wide and 300 feet wide through breakwater; deepen entrance channel 28 feet through piers, outer harbor to28 feet south of entrance channel, and a channel to 27 feet in Milwaukee River to Buffalo St., and in Kinnickinnic River to Chicago & North Western Ry. bridges. MONROE HARBOR, MI (See Section 45 of Text) 9-foot channel, Protecting Revetments and Piers. 21-foot channel, dikes and Turning Basin.3 Doc. 20, 72d Cong., 1st Seas. H. Doc. 154, 86th Cong., 1st Sess. x Annual Report, 1867, P. 132. H. Doc. 419, 56th Cong., 1st Sess. H. Doc. 171, 70th Cong., 1st Seas. Rivers and Harbors Committee Doc. 28, 73d Cong., 2d Sess. H. Doc. 228, 76th Cong., 1st Sess. H. Doe. 112, 86th Cong., 1st Sess. Detailed Project Report Dec. 1960.1 S. Doe. 175, 25th Cong., 2d Sess. Annual Report 1881, p. 2122. Annual Report 1906, p. 1752. [No prior survey or estimate affecting breakwater extensions.] H. Doc. 804, 66th Cong., 2d Sess. H. Doc. 289, 72d Cong., 1st Sess. S. Doc. 29, 76th Cong., 1st Sees. H. Doc. 285, 86th Cong., 2d Sess. H. Doc. 134, 87th Cong., 1st Sess.1 Annual Report 1872, p. 237. Rivers and Harbors Comm. Doe. 22, 71st Cong., 1st Ses., 31-65 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 31-B (Continued) AUTHORIZING LEGISLATION Acts Work Authorized Documents Jul. 14, 193221 Jun. 13, 1902 Mar. 3, 1925 Aug. 30, 1935 Oct. 23, 1962 Oct. 23, 1962 Aug. 2, 1882 Jun. 25, 1910 Jun. 25, 1910 Aug. 26, 1937 Mar. 2, 1867 Mar. 3, 1873 Jul. 5, 1881 Jul. 13, 1892 Mar. 25, 1907 Aug. 18, 1894 Jun. 13, 1902 Modified Conditions of Local Cooperation Imposed by Act of Jul. 3, 1930 MUSKEGON HARBOR, MI (See Section 46 of Text) Piers and Revetments. Breakwaters. Repairing Revetments around Car Ferry Slip. Channel deepening and present project dimensions of channel. Piers and Revetments. NEW BUFFALO HARBOR, MI (See Section 47 of Text) Entrance channel 10 feet deep by 80 to 180 feet wide and 850 feet long to mouth of Galien River, new no. and so. breakwaters 1,305 and 740 feet, respectively, deepening inner channel to Galien River to 8 feet and 80 feet wide and 1,250 feet long. OCONTO HARBOR, WI (See Section 48 of Text) Piers, except for inner 300 feet of south pier and 250 feet of north pier built by city.2 Present project dimensions of channel and turning basin. ONTONAGON HARBOR, MI (See Section 49 of Text) Channel 17 feet deep and 150 feet wide through bar and 15 feet deep and 100 feet wide between piers, and pier maintenance. Modified project widths and provide inner basin. PENTWATER HARBOR, MI (See Section 50 of Text) Piers and revetments, dredging. Piers and revetments, dredging. Piers and revetments, dredging. Piers and revetments, dredging. Present project depth of channel PETOSKEY HARBOR, MI (See Section51 of Text) Breakwaters according to larger of two projects. Removal of north breakwater and extension of west breakwater if cost did not exceed $170,000 Rivers and Harbor Comm. Doc. 12, 72d Cong., 1st Sess. 45, 75th Cong., 1st Sess.1 H. Doc. 104, 56th Cong., 2d Sess. H. Doc. 494, 67th Cong., 4th Sess. Rivers and Harbor Comm. Doc. 64, 75th Cong., 1st Sess. H. Doc. 474, 87th Cong., 2d Sess.1 H. Doc. 474, 87th Cong., 2d Sess. Annual Report 1881, p. 2066. H. Doc. 538, 61st Cong., 2d Sess. Plan C.' H. Doc. 602, 61st Cong., 2d Sess. S. Committee print, 74th Cong., 2d Sess. H. Ex. Doc. 70, 39th Cong., 2d Sess. H. Ex. Doc. 70, 39th Cong., 2d Sess. H. Ex. Doc. 70, 39th Cong., 2d Sess. H. Ex. Doc. 70, 39th Cong., 2d Sess. H. Doc. 181, 39th Cong., 2d Sess.' Annual Report 1890, p. 2673 Annual Report 1895, p. 2819 Annual Report 1896, p. 2722 31-66 DETROIT, MICHIGAN DISTRICT TABLE 31-B (Continued) AUTHORIZING LEGISLATION Acts Work Authorized Documents Mar. 2, 1945 Mar. 2, 1945 Jul. 16, 1984 Mar. 3, 1879 Mar. 2, 1945 Jul. 11, 1870 Aug. 14, 1876 Aug. 30, 19352 Jul. 3, 1958U Jun. 13, 1902 Jun. 80, 1948 Aug. 5, 1977 Jun. 3, 1896 Jun. 13, 1902 Aug. 30, 1985 Jul. 14, 1960 Mar. 2,1907 Aug. 26, 1987 POINT LOOKOUT HARBOR (AU GRES RIVER), MI (See Section 52 of Text) Breakwater, Anchorage Area, Channel Dredging. PORT AUSTIN HARBOR, MI (See Section 53 of Text) Breakwater, Anchorage Basin, Channel Dredging. Construct a breakwater access for recreation purposes. PORTAGE LAKE HARBOR, MI (See Section 54 of Text) Entrance Channel 18 Feet Deep Protected by Piers and Revetments. PORT SANILAC HARBOR, MI (See Section 55 of Text) Entrance Channel 12 Feet Deep, Anchorage Basin, Breakwater. PORT WASHINGTON HARBOR, WI (See Section 56 of Text) North pier and south basin.? North basin. North breakwater, removal of 650 feet of north pier, outer turning basin, present project dimensions of channel and basin and extension of south breakwater. Extending and raising of north breakwater and placing rubble along sides; removing 456 feet of south breakwater and dredging in outer basin. PORT WING HARBOR, WI (See Section 57 of Text) Construction of parallel piers and dredging. Dredging inner channels and abandonment of certain revetments and channels. Deauthorization of 50 feet of entrance channel widening. PRESQUE ISLE HARBOR, MI (See Section 58 of Text) Breakwater, 1,000 feet long. Shore extension, 216 feet long. For dredging and rubblemound extension to breakwater 1,600 feet long. Changed designation of project. Deepening harbor from 26 and 28 feet to 28 and 30 feet, respectively. RACINE HARBOR, WI (See Section 59 of Text) Breakwaters. Remove shoals lakeward of harbor entrance, enlarge H. Doc. 446, 78th Cong., 2d Sess. H. Doc. 446, 78th Cong., 2d Sess. H.R. 5653, 98th Cong., 2d Sess., P.L. 98-360 (98 Stat. 405) Sec. 106. Annual Report 1879, p. 16342 H. Doc. 446, 78th Cong., 2d Sess. H. Ex. Doc. 28, 41st Cong., 2d Sess., and Annual Report, 1879, p. 119. Annual Report, 1876, pt. 2, p. 379 H. Doc. 168, 72d Cong., 1st Sess. and Rivers and Harbors Committee Doc. 41, 74th Cong., 1st Sess. H. Doc. 446, 83d Cong., 2d Sess.1 H. Doc. 114, 56th Cong., 1st Sess. H. Doc. 668, 80th Cong., 2d Sess. H. Doc. 318, 54th Cong., 1st Sess., Annual Report for 1903, pp. 474, 1823. H. Doc. 473, 72d Cong., 2d Sess. H. Doc. 145, 86th Cong., 1st Sess. H. Doc. 62, 59th Cong., 1st Sess., and Annual Report 1909, p. 1973. Rivers and Harbors 31-67 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 31-B (Continued) AUTHORIZING LEGISLATION Acts Work Authorized Documents Mar. 2, 1945 Aug. 8, 1917 Aug. 80, 19352,",v Jul. 3, 19582 Oct. 23, 19622 Jun. 25, 1910 Jul. 3, 1930 Aug. 26, 1937 Jun. 20, 1938 Sep. 3, 1954 Oct. 23, 1962 Oct. 27, 1965 Jul. 13, 1892 Jul. 8, 1930 Mar. 2, 1945 19-foot channel through outer basin and 19-foot channel in river. Present project dimensions of channel through outer basin and in river. ROUGE RIVER, MI (See Section 60 of Text) 21-foot channel via the Shortcut Canal. 25-foot channel at mouth of Old Channel, 1,425 feet long and adjacent to latter, and 21-foot channel extending from junction of Old Channel and Shortcut Canal into Old Channel to Detroit, Toledo & Ironton R.R. Bridge. Old Channel; 100 feet wide from Peerless Cement Corp. to Junction with Shortcut Canal widened to 150 feet at 2 bends. 25-foot channel over modified limits from Detroit River to Jefferson Ave. (via Shortcut Canal). SAGINAW RIVER, MI (See Section 61 of Text) Channel 200 feet wide, with depth of 18.5 Feet in Bay and 16.5 Feet in River. Project Depth of 18.5 Feet Extended Up River to Saginaw Turning Basin. Present Project Channel Dimensions from Bay to Sixth Street Bridge in Saginaw. New Channel in Bay, 350 Feet Wide and 24 Feet Deep from 24-Foot Contour to River Mouth, Project Depth of 24 Feet in River Channel Up to Detroit & Mackinac Railway Bridge, Project Depth of 22 Feet in River Channel Up to Sixth Street Bridge, Turning Basins at Essexville and Carrollton, and Elimination of Present Channel in Bay. Deepen Bay Channel, Deepen River Channel to Detroit & Mackinac Bridge, Extend 22-Foot Project Above 6th St. Bridge, Deepen Essexville Turning Basin, and Construct 2 New Turning Basin.' Deepen River Channel to 25 Feet, from Detroit & Mackinac Bridge to New York Central Railroad Bridge. ST. CLAIR RIVER, MI (See Section 62 of Text) 20-Foot Channel in the River. Deepen Channel to 25 and 26 Feet, and Compensating Works. Widening Channel at Southeast Bend to 700 Feet. Committee Doc. 46, 75th Cong., 1st Seas. H. Doc. 816, 77th Cong., 2d Sess., and H. Doc.255, 78th Cong., 1st Sess.' H. Doc. 1063, 64th Cong., 2d Sess." H. Doc. 125, 85th Cong., 1st Sess. H. Doc. 509, 87th Cong., 2d Sess.1 H. Doc. 740, 61st Cong., 2d Sess. Rivers and Harbors Committee Doc. 30, 71st Cong., 2d Sess. Rivers and Harbors Comm Doc. 21, 75th Cong., 1st Sess. H. Doc. 576, 75th Cong., 3d Sess. H. Doc. 500, 83rd Cong., 2d Sess. H. Doc. 554, 87th Cong., 2d Sess. H. Doc. 240, 89th Cong.,lst Sess.1 H. Doc. 207, 51st Cong., 2d Sess. H. Doc. 253, 70th Cong., 1st Sess. H. Doc. 309, 77th Cong., 1st Sess. 31-68 TABLE 31-B (Continued) DETROIT, MICHIGAN DISTRICT AUTHORIZING LEGISLATION Acts Work Authorized Documents Jul. 24, 1946 Mar. 21, 1956 Mar. 3, 1875 Jun. 14, 1880 Mar. 3, 1899 Aug. 30, 1935 Jun. 2, 1937 Mar. 2, 1945 Jul. 3, 1958 Jul. 11, 1870 Aug. 5,1886 Jul. 18, 1892 Jun. 13, 1902 Jun. 13, 1902 Mar. 3, 1907 Mar. 3, 1909 Jul. 25, 1912 Mar. 4, 1915 Sep. 22, 1922 Widen and Deepen Southeast Bend and Improve Outlet of North Channel, St. Clair River. Deepen and Further Improve Channels in St. Clair River Between Limits of 27.1 to 30 Feet to Provide Safe Navigation by Vessels with Drafts of 25.5 Feet. A Cutoff Channel in Canada of Southeast Bend and Abandon Old Southeast Bend Channels. ST. JOSEPH HARBOR, MI (See Section 63 of Text) Interior Revetments." Benton Harbor Canal." Present Project Dimensions of Piers and a Turning Basin. Present Project Dimensions of Paw Paw River. Abandon Easterly 1,000 Feet of Channel Above West Line of 9th St. Turning Basin Above Mouth of Morrison Channel and Eliminate Turning Basin Near Mouth of Paw Paw River. Maintenance of Turning Basin Near Mouth of Paw Paw River. ST. MARYS RIVER, MI (See Section 64 of Text) Weitzel Lock (Replaced in 1943 by Mac Arthur Lock), Widen and Deepen Existing State Channel." Poe Lock.1 Dredging Through Shoals Above Falls and Shoals Below Falls Between Lower End of Canal and Upper Entrance Channel into Lake Nicolet (Formerly Hay Lake). Enlarging the Old Channel. Lake Nicolet and Neebish Channels Work in that Section of River Below Locks. David Lock Second Canal, and Emergency Dam. Lease of Waterpower at Ealls. Lease Entered Into with Michigan Northern Power Co. Provided for Construction of Remedial and Compensating Works. Fourth Lock (Renamed 'Sabin' Lock in 1943). Deepen Tailrace of Power Plant. Widen Upper Approach to Canals Through Vidal Shoals, Extend Anchorage and Maneuver Area Below Locks. H. Doc. 335, 80th Cong., 1st Sess. S. Doc. 71, 84th Cong., 1st Sess. H. Ex. Doc. 160, 43rd Cong., 2d Sess., and Annual Report 1875, pt. 1, p. 162. Annual Report 1880, pp. 2030, 2031 and 2049, 2055. H. Doc. 307, 55th Cong., 2d Sess., and Annual Report 1898, p. 2496. Rivers and Harbors Comm. Doc. 52, 74th Cong., 1st Sess. H. Doc. 129, 76th Cong., 1st Sess. S. Doc. 95, 84th Cong., 2d Sess. 1 Report by Maj. O. M. Poe, Corps of Engineers, Not Published. H. Ex. Doc. 72, 49th Cong., 2d Sess. H. Ex. Doc. 207, 51st Cong., 2d Sess., and Annual Report 1891, p. 2810 H. Doc. 138, 56th Cong., 2d Sess., and 215, 58th Cong., 3d Sess. H. Doc. 128, 56th Cong., 2d Sess. H. Doc. 333, 59th Cong., 2d Sess. (Plan 3) H. Doc. 65, 62d Cong., 1st Sess. District Engineer Report, Oct. 29, 1920. 31-69 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 31-B (Continued) AUTHORIZING LEGISLATION Acts Work Authorized Documents Jan. 21, 1927 Jul. 3, 1930 Jun. 26, 1934' Aug. 30, 1935 Mar. 7, 1942 Jun. 15, 1943 Mar. 2, 1945 Jul. 24, 1946 Mar. 21, 1956 Jul. 9, 1956 Jun. 3, 1896 Mar. 2, 1907 Jun. 25, 1910 Jul. 3, 1958 Remove Round Island, Middle Ground Extension of Northwest Canal Pier, and Widen Channels Middle Neebish Route. Deepen Channels Throughout Downbound Route. Operation and Care of Canal and Locks Provided from War Department Appropriations for Rivers and Harbors. Widen Brush Point Turn and Channel from Brush Point to Point Louise. Construct New (Mac Arthur) Lock on Site of Former Weitzel Lock, Deepen Approach Channels to 27 Feet, and Reconstruct Approach Piers. Name 'Mac Arthur' Lock and Changed Name of 'Fourth' Lock to 'Sabin' Lock. Remove Bridge Island and Construct New Hydroelectric Power Plant. Replace Poe Lock at St. Marys Falls Canal with a New Structure 800 Feet Long, 100 Feet Wide and 32 Feet Deep, with Necessary Construction of Nose and Center Piers, and Widen and Deepen Channel Across Point Iroquois Shoals and in Lake Nicolet to Provide Wider Anchorage and Maneuver Areas in St. Marys River. Deepen to Provide a Project Safe Draft of 25.5 Feet Over Full Width to Downbound and 2-Way Channels (Including Anchorage Areas) and Over Westerly 300-Foot Width of Upbound Middle Neebish Channel, When Levels of Lake Superior and Huron are at Their Respective Low-Water Datum. Repeal Authorization of Bridge as a Part of Project, Authorize Alteration With Cost to be Apportioned by Sec. 6, Truman Hobbs Act, June 21, 1940. SAUGATUCK HARBOR AND KALAMAZOO RIVER, MI (See Section 65 of Text) Entrance Channel, Piers and Revetments. Deepening Entrance to 16 feet. Deepening Channel in River to 14 feet. SAXON HARBOR, WI (See Section 66 of Text) Provides for east and west breakwaters, an outer channel 10 feet deep, an inner basin and side channel 8 feet deep, and diversion of Oronto Creek to Parkers Creek by three short reaches of channel excavation and a levee. H. Doc. 270, 69th Cong., 1st Sess. H. Doc. 253, 70th Cong., 1st Sess. River and Harbor Comm. Doc. 53, 74th Cong., 1st Seas. H. Doc. 218, 77th Cong., 1st Sess. H. Doc. 679, 78th Cong., 2d Sess. and H. Doc. 339, 77th Cong., 1st Sess. H. Doc. 335, 80th Cong., 1st Sess. S. Doc. 71, 84th Cong., 1st Sess.1 None H. Doc. 912, 54th Cong., 1st Sess. Annual Report 1896, Vol. 2. Pt. 5, p. 2739 Annual Report 1907, p. 6416 H. Doc. 635, 61st Cong., 2d Sess. River and Harbor Act H. Doc. 169, 85th Cong., 1st Sess., Annual Report for 1965, p. 1025. 31-70 TABLE 31-B (Continued) DETROIT, MICHIGAN DISTRICT AUTHORIZING LEGISLATION Acts Work Authorized Documents Mar. 2, 1907 Jan. 21, 1927 Aug. 30, 1935 Sep. 3, 1954 Aug. 11, 1888 Mar. 3, 1905 Aug. 30, 1935 Mar. 3, 1873 Jul. 13, 1892 Mar. 3, 1871 Mar. 2, 1907 Aug. 30, 1935 Jul. 3, 1958 Mar. 2, 1867 Mar. 3, 1873 Jul. 5, 1884 Jul. 13, 1892 Mar. 2, 1907 SHEBOYGAN HARBOR, WI (See Section 67 of Text) North breakwater. Preserving south pier as part of project, providing turning basin, and elimination of proposed south breakwaters. Present project dimensions of channel. Widen and deepen outer harbor entrance channel to 450 feet, widen and deepen river channel from present project limit to north side of Jefferson Ave. SOUTH HAVEN HARBOR, MI (See Section 68 of Text) Channel from Inner End of Piers to Highway Bridge.12 Present Dimensions of Piers and for a Turning Basin. Present Project Dimensions of Channel and Turning Basin STURGEON BAY AND LAKE MICHIGAN SHIP CANAL, WI (See Section 69 of Text) Breakwaters. 2s Acquisition of the canal. TWO RIVERS HARBOR, WI (See Section 70 of Text) South pier, 750 feet of north pier, and about 44 feet of north revetment.'2 Remainder of north pier and stilling basin. Deepening entrance channel and inner basin to 18 feet. Extend existing project in West Twin River to 18 feet deep and in East Twin River to 10 feet deep to 22d Street Bridge. WHITE LAKE HARBOR, MI (See Secti6n 71 of Text) New Channel, with Piers and Revetments. New Channel, with Piers and Revetments. New Channel, with Piers and Revetments. New Channel, with Piers and Revetments. Present Project Depth of Channel. H. Doe. 62, 59th Cong., 1st Sess. H. Doc. 475, 68th Cong., 2d Sess. Rivers and Harbors Committee Doc. 47, 74th Cong., 1st Sess. H. Doc. 554, 82d Cong., 2d Sess.' No Prior Survey or Estimate. H. Doc. 119, 58th Cong., 2d Sess. Rivers and Harbors Comm. Doc. 9, 73d Cong., 1st Sess.' and Unpublished review Report of Chief of Engineers, Dated Dec. 21, 1934. H. Ex. Doc. 34, 42d Cong., 2d Sess. Annual Report, 1872, p. 171. H. Ex. Doc. 106, 49th Cong., 2d Sess. Annual Report, 1871, p. 123 [as modified by Chief of Engineers, Feb. 27, 1897]. H. Doc. 730, 59th Cong., 1st Sess. Modification of Plan A. Rivers and Harbors Committee Doc. 25, 73d Cong., 2d Sess. H. Doc. 362, 84th Cong., 2d Sess.' Unpublished Survey Report of 1868. Unpublished Survey Report of 1868. Unpublished Survey Report of 1868. No Prior Survey or Estimate." 31-71 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 31-B (Continued) AUTHORIZING LEGISLATION Acts Work Authorized Documents KAWKAWLIN RIVER, MI (See Section 79 of Text) Apr. 7, 1966 Deepening River Channel, Altering Railway Bridge, Section 205, 1948 Flood Control Riprapping Portions of Channel Bottom, and Utility Act. Relocations. SAGINAW RIVER, MI FLOOD CONTROL (See Section 80 of Text) Jul. 3, 1958 Flood Control Improvements to Saginaw River H. Doc. 346, 84th Cong., 2d Sess.1 and its Tributaries Including Tittabawassee, Shiawassee, Flint, and Cass Rivers. SEBEWAING, SEBEWAING RIVER, MI (See Section 81 of Text) Aug. 18, 1941 Enlarging Present Channel of Sebewaing River, H. Doc. 286, 76th Cong., 1st Sess' Altering Railroad and Highway Bridges, Removal of Dike. 'Contains latest published map. I2lncluding Emergency Relief Administration Work authorized May 28, 1935. Included in Public Works Administration Program September 6, 1933. 'This modification deauthorized August 5, 1977 under Section 12, Public Law 93-251. 5Administrative Act, Section 4. 6Public Law 568, 82d Congress. 7Public Law 388, 87th Congress. This portion inactive. 9Permanent Appropriations Repeal Act. 10Transfer completed June 1962. "Amended 1868, 1879, 1892. 1cCompleted under previous project. 18lIncluded in Public Works Administration Program January 3, 1934. "4Inactive portion; removal of 200 linear feet of north pier, widening inner 200 feet of channel through outer basin, and closing gap in north shore connection of breakwater. 15Latest published map is in Annual Report 1914, p.2974. '6Latest published map in Annual Report 1914, p. 2914. 17Superceded by Act of October 23, 1962. s1 8Uncompleted portion was deauthorized in 1977 (dredging Milwaukee River from Buffalo St. Bridge to North Humboldt Ave. Bridge). l9Modified by Act of June 10, 1872. ORiprapping of protecting dikes portion of project is inactive. 21War Department Appropriations Act. "Latest published map is in House Document 588, 64th Cong., 1st Sess. "Work recommended in H. Doc. 588, 64th Cong., 1st Sess. 24Deauthorized in 1977. "52Contains latest published maps. See also map with Rivers and Harbors Committee Doc. 19, 72d Cong., 1st Seas. "2 6Except for dredging 25-foot channel to 1,150 feet upstream of mouth in old channel, work authorized in this Act is considered inactive. ="This modification deauthorized August 5, 1977 under Section 12, Public Law 93-251. "Completed under previous projects. Public Law 130, 75th Cong., 1st Sess. "Latest published map is in H. Doc. 2053, 64th Cong., 2d Seas. 31-72 TABLE 31-C DETROIT, MICHIGAN DISTRICT FEATURES OF EXISTING PROJECT Project Datum Planes Length Miles Used by Above Mean of from Upbound Water Level Channel Mouth or Down- Project Project at Father of bound Width Depth Point, Quebec Year Name of Channel (Feet) River Vessels (Feet) (Feet) (Feet) Complete DETROIT RIVER, MI (SEE SECTION 13 OF TEXT) Channel North of Belle Islel 22 Channel at Head of Detroit River Miscellaneous Shoals and Obstructions, Belle Isle to Fighting Island Channel Fighting Island Channel Ballards Reef Channel North of Junction with Livingstone Channel Livingstone Channel Upper Livingstone Channel Lower: CS 260+00 to 368+87 CS 368+87 to 492+00 East Outer Channel Misc., Shoals and Obstructions, Detroit River to Pelee Passage Pelee Passage Shoal Amherstburg Channel: Upper Section, Ballards Reef Channel Middle Section Lower Section, Hackett Range West Outer Channel Trenton Channel: Wyandotte Reach Trenton Reach (Upper) Trenton Reach (Lower) Grosse Ile Shoal .30 38,800 32 44,500 25 24,800 17 12,200 12 Both Both Both Both Both 26,000 10 Down 10,887 12,313 42,000 6,500 12,000 24,000 21,000 31,500 5,100 600 600 10 17 14 14. Down Both Both Both Both Up Up Up Down Local Local Local Local 200 21.0 571.3 800 28.5 571.5-570.9 - 28.5 570.9-570.3 800 600 450 450,800 800-1,200 1,200 28.5 28.5 1964 1964 1964 569.8 1962 569.8 1963 27.7 569.8-568.6 1964 29.0 29.0 28.5 - 28.5-29.53 - 29.5 600 600 6000 800 300 300 250-300 27.5 21.27.54 21.28.51 22.0 27.0 28.0 28.0 20.0 568.6 568.6 568.6 1961 1961 1964 568.6 1962 568.6 1964 569.8-569.5 569.5-568.9 568.9-568.6 568.6 569.9-569.7 569.7-569.6 569.6-568.8 569.8 1960 1960 1960 1929 19644 1964 1941 1904 ST. CLAIR RIVER, MI (SEE SECTION 62 OF TEXT) Channel at Foot of Lake Huron Channel North of Blue Water Bridge Port Huron to Stag Island Widening at Upper and Lower Ends of Stage Island St. Clair to Russel Island Russel Island to Southeast Bend Southeast Bend CS 324+00 to 250+00 Cutoff Channel North Channel Outlet 26,500 44 4,100 39 38,000 37,600 77,000 20,600 7,400 30,300 8,000 39 31 24 11 5 Both Both Both Both Both Both Both Both Small Craft 800 800 800 900-1,000 1,000 700-1,000 700 700 100 30.0 576.8-576.5 1961 30.0 576.4-576.1 1962 30.0 27.4 27.3 17.2 576.4-576.1 574.9-573.8 573.8-572.4 572.4-572.1 27.1 573.1-572.0 27.1 572.1-571.7 10.0 571.7 1961 1962 1962 1962 1962 1962 1962 ''TThhiiss iiss aa SSiiddee CChhaannnneell.. 'Extends from Deep Water Near Windmill Point to a Point Opposite Fairview Slip, about 3,000 Feet. 'Project Depth 29.5 Feet over Rock Shoals and 28.5 Feet over other than Rock Shoals. 'Project Depth 21 Feet in Easterly 300-Foot Width of Channel and 27.5 Feet in Westerly 300-Foot Width. 'Project Depth 21 Feet in Easterly 300-Foot Width of Channel and 28.5 Feet in Westerly 300-Foot Width. 'Project Complete Except for Work Authorized by River and Harbor Act of 1950. 31-73 TABLE 31-D REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 ST. MARYS RIVER, MI: EXISTING PROJECT (See Section 64 of Text) Lock Davis Sabin MacArthur New Poe Miles Above Mouth 47 47 47 47 Clear Width of Chamber Feet 80 80 80 110 Length Between Gate Quoins Feet 1,350 1,350 800 1,200 Lifts Feet 21.7 21.7 21.7 21.7 Depth Over Upper Breast Walls Feet 24.3 24.3 31 32 Depth Over Lower Breast Walls' Feet 23.1 23.1 31 32 Foundation Rock Rock Rock Rock Type of Construction Concrete Concrete Concrete Concrete Estimated Cost $6,200,002 $3,275,0008 $12,909,440 $39,000,000 Actual Cost $2,200,0006 $1,750,0008 $12,718,806', 7 $34,813,066 Completed (Open to Commerce) Oct. 21, 1914 Sep. 18, 1919 Jul. 11, 1943 Jun. 26, 1969 Emergency Dam for South Canal North Canal Miles Above Mouth 47 47 Estimated Cost -* $300,000 Type Steel Stoplogs Recessed Steel Stoplogs Recessed Into Lock Masonry Into Lock Masonry Cost Completed - $169,2248 Year Completed 1943 1922 (Modified 1963) 'At low water datum 599.5 above and 577.8 below. 'Includes Cost of North Canal. 'Includes cost of canal excavations to provide necessary approaches to lock, canal walls, piers, and emergency dam, $662,919. 4Excludes cost of deepening and enlarging South Canal, $1,653,378. 5Excludes cost of North Canal, $2,572,611. 6Excludes cost of canal excavations to provide necessary approaches to lock, canal walls, piers, and emergency dam, $662,919. 7Excluding cost of lower guard gates which were never installed. *Including engineering office, and inspection. 'Not separable from cost of locks. Note: Limiting draft to locks is determined by depth over breast walls. 31-74 DETROIT, MICHIGAN DISTRICT FOX RIVER, WI: LOCKS AND DAMS TABLE 31-E (See Section 16 of Text) Depth At Normal Pool Miles Avail- Lower from Dis- Clear able Breast Miter Character Kind Year Green Nearest tance Width Length Lift Wall' Sill of of Type of Com- Name of Lock and Dam Bay Town (miles) (feet) (feet) (feet) (feet) (feet) Foundation Dam Construction plete DePere lock- 7.1 DePere - DePere dams 72 DePere - Little Kaukauna locks 13.0 DePere 6 Little Kaukauna dams 13.1 DePere 6 Rapide Croche locks 19.2 Wrightstown 2 Rapide Croche Dame 19.3 Wrightstown 2 Kaukauna fifth locks 22.8 Kaukauna - Kaukauna fourth lock s 23.1 Kaukauna - Kaukauna third lock s 23.3 Kaukauna - Kaukauna second lock2 23.4 Kaukauna - Kaukauna first lock s 23.6 Kaukauna - Kaukauna Dams 24.0 Kaukauna - Kaukauna guard lock 24.0 Kaukauna - w Little Chute combined lock: -4 Lower 24.4 Little Chute 1 m Upper 25.4 Little Chute 1I Little Chute second lock2 26.4 Little Chute - Little Chute first (guard) lock' 26.5 Little Chute - Little Chute Dams 26.6 Little Chute - Cedars locks 27.3 Little Chute 1 Cedars Dam2 27.4 Little Chute 1 Appleton fourth locks 30.7 Appleton 1 Appleton lower dams 30.9 Appleton 1 Appleton third locks 31.3 Appleton - Appleton second locks 31.6 Appleton - Appleton first lock2 31.9 Appleton - Appleton upper dam 32.2 Appleton - Menasha locks 37.0 Menasha - Menasha Dam2 37.8 Menasha - 36.0 146.0 8.9 36.0 146.0 7.2 36.0 146.0 8.3 35.6 144.0 9.1 36.6 144.1 10.2 30.6 144.0 10.2 35.0 144.0 9.6 35.1 144.4 11.0 -- - - 40.0 - - 35.4 146.5 10.9 36.3 144.1 10.6 35.0 144.2 13.8 35.4 - - 35.0 144.0 9.8 35.0 144.0 7.6 35.0 144.0 7.67 35.0 144.0 8.7 35.1 144.6 9.6 35.0 144.7 10.0 35.4 144.0 8.5 --- .- .- 10.3 12.0 8.0 9.5 8.8 9.3 6.7 9.3 6.9 6.0 6.9 6.3 6.0 6.0 6.9 6.0 - -. 9.4 - 6.0 8.6 7.6 6.0 8.0 6.1 6.6 - 6.8 7.3 8.1 7.9 6.0 8.6 6.9 6.0 6.6 6.0 7.2 8.0 -.. .- Rock - Concrete 1936 $229,308 Rock Fixed'4 Concrete 1929 209,536 Clay - Concrete 1938 362,427 Clay and gravel Fixed3* Piers and concrete 1926 179,398 Rock - Concrete 1934 228,738 Rock Fixed3' Concrete 1930 118,975 Rock - Composite 1898 13,3106 Rock - Stone masonry 1879 37,536 Rock - Stone masonry 1879 39,948 Rock - Stone masonry 1903 24,313 Rock - Stone masonry 1883 38,704 Rock Fixed'* Concrete 1931 123,763 Rock - Stone masonry 1891 12,630 Rock Hardpan Rock Rock Rock Rock Rock Rock Rock Rock Clay Rock Rock Clay Hardpan - Stone masonry 1879 102,304 - Stone masonry 1879 - - Stone masonry 1881 48,555 - Stone masonry 1904 7,8175 Fixed3' Concrete 1932 82,554 - Stone masonry 1888 34,972 Fixed"* Concrete 1933 84,973 - Stone masonry 1907 40,893 Fixed"* Concrete 1934 73,903 - Stone masonry 1900 32,238 - Stone masonry 1901 22,940 - Stone masonry 1884 36,004 Fixed' Concrete 1940 151,558 - Composite 1899 19,3266 Fixeds Concrete 1937 84,686 'Depth shown is on breast wall, which is controlling depth for upper pool. Original structure built prior to assumption of control by United States on Sep. 18, 1872. sProvided with sluices. 'Flash boards used. 5Partially rebuilt. Actual Cost TABLE 31-F REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 RECONNAISSANCE & CONDITION SURVEYS Name of Project Date Survey Conducted Algoma Harbor, MI Bayfield Harbor, MI Bayport Harbor, MI Belle River, MI Big Bay Harbor, MI Big Suamico River, WI Caseville Harbor, MI Grand Marais Harbor, MI Pensaukee Harbor, WI Pine River, MI Tawas Bay Harbor, MI Traverse City Harbor, MI Two Harbors, MN Washington Island, WI. Whitefish Pointe, MI July 1985 August 1985 February 1985 April 1985 May 1985 February 1985 February 1985 April 1985 February 1985 April 1985 November 1984 September 1985 October 1984 June 1985 May 1985 31-76 DETROIT, MICHIGAN DISTRICT TABLE 31-G OTHER AUTHORIZED NAVIGATION PROJECTS For Last Cost To September 30, 1985 Full Report See Annual Operation and Project Report For Construction Maintenance Algoma Harbor, MI 1981 205,0101 905,404 Bayport Harbor, MI 1975 93,597 46,887 Bayfield Harbor, WI 1979 183,855 73,077 Belle River, MI 1980 24,301 72,544 Beaver Bay, MN 1982 293,000 2,818 Big Bay Harbor, MI 1984 390,4332 1,008,861 Big Suamico River, WI 1975 20,243 166,605 Black River (Alcona Co.), MI 1907 - - Caseville Harbor, MI 1981 587,314 99,011 Cedar River Harbor, MI 1982 215,000- Chippewa Harbor, Isle Royale, MI 1959 125,629 8,871 Forestville, MI 1969 - - Grand Marais Harbor, MI 1980 1,055,871 1,683,009 Grays Reef Passage, MI 1970 190,521 647,987 Les Cheneaux Islands Channels MI 1980 399,478 284,533 Little Bay De Noc, Gladstone Harbor, MI 1966 332,832 64,869 Lutsen Harbor, MN 1982 357,000- Mackiac Island Harbor, MI 1969 229,0858 71,470 Northprt Harbor, MI - - - Pensaukee Harbor, WI 1983 34,035 193,314 Pine River, MI 1980 13,649 32,071 St. James, Beaver Island, MI 1957 49,1714 50,292 St. Joseph River, MI 1975 54,555 19,185 Sebewaing River, MI 1982 35,573 2,280,526 Tawas Bay Harbor, MI 1978 1,954,821 19,190 Traverse City Harbor, MI 1976 366,579 121,793 Two Harbors, MN 1984 4,170,7106 1,901,055 Washington Island, WI 1950 62,838 67,084 Whitefish Pointe, MI 1981 771,639 221,527 'Includes $92,774 for previous projects. 2Excludes $56,500 Contributed Funds. 8Excludes Contributed Funds of $105,004. 'Excludes Contributed Funds of $7,500. "Includes $48,404 National Industrial Recovery Act for new work funds. 31-77 TABLE 31-H REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 OTHER AUTHORIZED FLOOD CONTROL PROJECTS For Last Cost To September 30, 1985 Full Report See Annual Operation and Project Report For Construction Maintenance Grand River, Grandville, MI' 1966 Grand River, Lansing, MI 1971 7,300 Kalamazoo River (Battle Creek) MI2 1975 4,471,235 Kalamazoo River (Kalamazoo) MI 1975 421,466 Mount Clemens, Clinton River, MIP 1953 1,136,0084 Upper River Rouge, MI5 1968 7,935 Red Run Drain-Lower Clinton River, MI 1983 3,823,000 River Rouge, MI 1981 31,960,332 'Awaiting Appropriation of Funds. 2Includes $108,335 Contributed Funds. 2Completed. 'Includes $202,996 Contributed Funds. 5Planning indefinitely suspended due to lack of local cooperation. 31-78 TABLE 31-I D Project Black River Harbor, MI (Aug 30, 1935 R&H Act) Detroit River, Trenton Chnl., MI (May 17, 1950 R&H Act) Grand Haven Harbor, MI (Mar 2, 1945 R&H Act) Grand River at Grandville, MI (Oct 27, 1965 Flood Control Act) Kewaunee River, WI (1960 R&H Act) Lansing, (Grand River), MI (Jul 3, 1958 Flood Control Act) Pentwater Harbor, MI (Jul 13, 1892 R&H Act) Rogers City Harbor, MI (Jun 25, 1910 R&H Act) Rouge River, MI (Oct 23, 1962 R&H Act) Rouge River, MI (Jul 3, 1958 R&H Act) Rouge River, MI (Aug 30, 1935 R&H Act) St. Clair River Compensating Works, MI (Jul 3, 1930 R&H Act) South Milwaukee Harbor, WI (1836 Flood Control Act) St. Marys River (MacArthur Lock Guard Gates), MI (Mar 7, 1942 R&H Act) 0 DETROIT, MICHIGAN DISTRICT EAUTHORIZED PROJECTS For Last Full Report See Annual Date Report For Deauthorized 1976 Nov 1977 1976 Aug 1977 1976 Nov 1977 1966 Nov 1977 1976 Aug 1977 1971 Jun 1981 1976 Nov 1977 1926 Aug 1977 1976 Aug 1977 1976 Aug 1977 1976 Aug 1977 1976 Aug 1977 1906 Aug 1977 1977 Oct 1978 31-79 . . I Federal Funds Expended 0 0 0 0 0 7,000 0 5,892 22,000 12,000 0 0 0 0 Contributed Funds Expended 0 0 0 0 0 0 0 0 0 0 0 0 0 0 BUFFALO, N.Y., DISTRICT* The district comprises northern Ohio, northwestern Pennsylvania and western and northern New York, embracing U.S. waters of Lake Erie exclusive of small portion of western end, Lake Ontario, and St. Lawrence River, with their tributary basins drainage from boundary between the states of Ohio and Michigan to international boundary line east of Frontier, New York. IMPROVEMENTS Page 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. 16. 17. 18. 19. 20. 21. 22. 23. 24. 25. 26. 27. 28. Ashtabula Harbor, Ohio ...................... 32-2 Barcelona Harbor, N.Y ....................... 32-2 Black Rock Channel and Tonawanda Harbor, N.Y ...................... 32-2 Buffalo Harbor, N.Y..........................32-3 Cattaraugus Harbor, N.Y.....................32-3 Cleveland Harbor, Ohio ...................... 32-4 Conneaut Harbor, Ohio...................... 32-4 Dunkirk Harbor, N.Y........................ 32-5 Erie Harbor, Pa............................. 32-5 Fairport Harbor, Ohio....................... 32-5 Geneva-on-the-Lake, Ohio................... 32-6 Great Sodus Bay Harbor, N.Y............. .. 32-6 Huron Harbor, Ohio ........................ 32-6 Irondequoit Bay, N.Y........................ 32-7 Little Sodus Bay Harbor, N.Y ................ 32-7 Lorain Harbor, Ohio........................32-7 Oak Orchard Harbor, N.Y................ 32-8 Ogdensburg Harbor, N.Y.....................32-8 Olcott Harbor, N.Y..........................32-8 Oswego Harbor, N.Y ......................... 32-9 Port Clinton Harbor, Ohio...................32-9 Port Ontario Harbor, N.Y ..................... 32-9 Rochester Harbor, N.Y....................... 32-10 Rocky River Harbor, Ohio...................32-10 Sandusky Harbor, Ohio ....................... 32-10 Toledo Harbor, Ohio........................32-10 Vermilion Harbor, Ohio ..................... 32-11 W est Harbor, Ohio ......................... 32-11 34. Presque Isle Peninsula, Erie, Pa .............. .32-12 35. Other authorized beach erosion control projects...........................,.32-13 36. Beach erosion work under special authorization ....................... 32-13 Flood Control 37. Cuyahoga River Basin, Ohio ................ 32-13 38. Dansville and vicinity, Canaseraga Creek, N.Y..................... 32-14 39. Ellicott Creek, N.Y........................ 32-14 40. Euclid Creek, Cleveland Ohio ............... 32-14 41. Mt. Morris Lake, N.Y., Genesee River ............................ 32-14 42. Ottawa, Ohio............................... 32-15 43. Point Place, Toledo, Ohio................... 32-16 44. Reno Beach- Howard Farms Area, Ohio ................. 32-15 45. Scajaquada Creek, N.Y ..................... 32-16 46. Inspection of completed flood control projects.......................32-16 47. National Emergency Preparedness ........... 32-16 48. Other authorized flood control projects............................ 32-16 49. Flood control work under special authorization........................ 32-16 Deauthorized projects 29. Wilson Harbor, N.Y.........................32-11 50. Deauthorized Projects...................... 32-16 30. Reconnaissance and condition surveys ......... 32-12 General Investigations 31. Other authorized navigation projects............ 32-12 51. Surveys .................................... 32-16 32. Navigation work under 52. Collection and study of basic data ............ 32-16 special authorization ........................ 32-12 53. Advance Engineering & Design..............32-16 Beach Erosion Control 54. Continuation of Planning and Engineering...... 32-16 33. Lakeview Park, Lorain, Ohio.................32-12 32- 1 Navigation Page REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Navigation 1. ASHTABULA HARBOR, OHIO Location. On south shore of Lake Erie, at mouth of Ashtabula River, 59 miles easterly from Cleveland, Ohio. (See NOAA Nautical Chart 14836.) Previous Projects. For details see page 1963 of Annual Report for 1915, and page 1593 of Annual Report for 1938. Existing Project For description see pages 1297-99 of Annual Report for 1966. Federal cost of completed project is $12,240,147. Non-Federal costs of $5,743,000, including contribution of $47,000, were for construction of access roads, docks, storage and handling facilities and dockside dredging. See Table 32-B for authorizing legislation. Local cooperation. Fully complied with. Local interests contributed $47,000 for work authorized by 1936 and 1970 acts. Terminal facilities. There are 16 piers and wharves. One facility is owned by city of Ashtabula and one is owned by Coast Guard. Ten facilities are along banks of Ashtabula River and six are on southside of outer harbor. Eleven terminals have railroad connections and six have mechanical-handling facilities. Facilities are considered adequate for existing commerce. (See Port Series No. 42, revised 1972, Corps of Engineers.) Operations and results during fiscal year. Maintenance: Miscellaneous inspection services and condition surveys by Government plant and hired labor cost $52,466. Contracts for EIS and dewatering sediments cost $2,735. Subsurface exploration at Diked Disposal facility, by contract cost $10,611. Repairs to 250 1.f. of the west breakwater by U.S. derrickboat Tonawanda cost $529,708. Snagging and clearing to remove logs in lower river by government plant and hired labor cost $2,252. Expenditure of $15,000 was attributed to the permanent layup of U.S. hopper dredge Hoffman. Engineering effort, to include economics study and continued environmental and water quality analyses, cost $144,866. 2. BARCELONA HARBOR, N.Y. Location. On south shore of Lake Erie about 17 miles southwesterly of Dunkirk, N.Y., and 29 miles northeasterly of Erie, Pa. (See NOAA Nautical Chart 14823.) Previous projects. Adopted by July 4, 1936, River and Harbor Act. Only information available is in index to report of Chief of Engineers under title "Portland Harbor, N.Y." Existing Project For description of existing project see page 1506 of Annual Report for 1961. Actual costs for work new work for completed project were $1,124,286. Non-Federal costs of $60,000 were incurred by local interests. Of this amount, $7,500 was a cash contribution and remainder was for providing necessary lands and construction of public wharf. Existing project was authorized by the 1945 River and Harbor Act (H. Doc. 466, 78th Cong., 2nd sess.). Local cooperation. Fully complied with. Local interests contributed $7500 for existing project. Terminal facilities. Facilities consist of private docks for recreational craft and privately owned servicing and storage handling facilities for recreational and other small craft. Operations and results during fiscal year. Maintenance: Miscellaneous inspection services and condition surveys by Government plant and hired labor cost $13,697. Project modification to improve the harbor to its authorized standards by constructing a 250-foot long extension of the west breakwater, a series of four 100-foot long rubblemound wave absorbers on the harbor side of the west breakwater, and a 150-foot long landward extension of the east breakwater, was completed. Finalization of construction contract resulted in a credit of $48,454, Federal funds. Non-Federal funds expended were $127,604 for construction contract and $31,396 for in-house engineering effort. 3. BLACK ROCK CHANNEL AND TONAWANDA HARBOR, N.Y. Location. Improvement is essentially that of upper 13.5 miles of Niagara River from its head at Lake Erie, Buffalo, N.Y., to and including Tonawanda Harbor, N.Y. It comprises improvements formerly designated by three titles; viz, Lake Erie entrance to Black Rock Harbor and Erie Basin, N.Y., Black Rock Harbor and Channel, N.Y., and Tonawanda Harbor and Niagara River, N.Y. (See NOAA Nautical Chart 14832.) Previous projects. For details see item 5 and 7, page 1970 of Annual Report for 1915, and page 1612 of Annual Report for 1938. Existing project. For description of existing project and Federally owned Black Rock ship lock, see page 1548 of Annual Report for 1962. Improvement of guide pier at Black Rock Lock, as authorized by 1935 act was deauthorized by Congress in August 1977. Cost for completed portion of new work is $10,457,093. Enlarging of existing 21-foot turning basin and deepening lower 1,500 feet of Tonawanda inner harbor from 16 to 21 feet, authorized by the 1954 act, was deauthorized by Congress in May 1981, and is excluded from foregoing cost. Estimated cost (1961) of this portion is $339,000. Non- Federal costs are estimated at $1,540,000 for costs incurred by New York State for construction of Erie Basin and protecting breakwater, and construction and extension of Bird Island Pier, and by other local interests for relocation of utilities. See Table 32-B for authorizing legislation. 32-2 BUFFALO, NY DISTRICT Local cooperation. Fully complied with for existing project. Contract for cost-shared recreation development at completed projects (Code 713 program) was executed by the New York State Department of Environmental Conservation, Albany, NY, on April 16, 1985, and approved by the Assistant Secretary of the Army and Chief of Engineers on May 3, 1985. Terminal facilities. Two facilities are along upstream end of channel. Below Black Rock Lock and at Tonawanda Harbor there are 13 privately owned terminals. There are two State-owned barge canal terminals at Tonawanda, N.Y., and several marine service and supply docks for recreational and other small craft. The Corps owns a wharf adjacent to Black Rock Lock which is private. Ten terminals have railroad connections and six mechanicalhandling facilities. Facilities considered adequate for existing commerce. (Port Series No. 41, revised 1971, Corps of Engineers.) Operations and results during fiscal year. New Work: Construction of an elevated concrete walkway with railing and three refuge platforms on Bird Island Pier, under cost-shared recreation development at completed projects, was initiated in June 1985 and cost $310,000 Federal funds and $250,000 non-Federal funds. Operation and care (Black Rock Lock): Lock was in operation 197 days and closed for underwater cleaning and repairs from December 7, 1984 through May 23, 1985. Ordinary maintenance and repair of structures and grounds was accomplished throughout the year by Government plant and hired labor. Total costs of $2,463,804 were distributed as follows: Operation and care: operation of lock, ordinary maintenance and repair $533,100; security service by contract and maintenance of grounds $95,963; miscellaneous inspection and condition surveys, project supervision, real estate, and support of Water Control Center $87,038. Rehabilitation of the miter gate by U.S. derrickboats McCauley and Ohio cost $104,237 and $244,702, respectively. Rehabilitation of the lower guard gate cost $58,363. Rehabilitation of upper guard gate by U.S. derrickboat Ohio and hired labor cost $342,950. Rehabilitation of the butterfly valves of gates, by contract, cost $64,000. Engineering effort in association with rehabilitation of gates and operation of locks cost $140,516. Snagging and clearing in project channels by Government plant and hired labor cost $58,067. Repairs to Bird Island Pier (within project channel) by contract, were initiated in June 1985 and cost $632,454. Construction will repair approximately 6800 1.f. of existing pier and provide a concrete walkway and three refuge platforms (Code 713 work). Engineering effort in association with the Bird Island Pier repair cost $102,414. 4. BUFFALO HARBOR, N.Y. Location. At eastern end of Lake Erie, at head of Niagara River, 176 miles easterly from Cleveland, Ohio. (See NOAA Nautical Charts 14820 and 14833.) Previous projects. For details see page 1967 of Annual Report for 1915 and page 1606 of Annual Report for 1938. Existing project. For description see page 1368 of Annual Report for 1963. In addition, on 15 December 1980, OCE authorized the removal of bridge abutments of South Michigan Avenue Bridge. New work for completed project cost $18,837,601. Estimated non-Federal costs were $9,188,000 for deepening, widening, and improving Buffalo River and ship canal, constructing piers, retaining walls, and dikes and performing dockside dredging. See Table 32-B for authorizing legislation. Local Coopertion. Fully complied with. Terminal facilities. There are 45 wharves and piers of which 4 piers, owned by Niagara Frontier Port Authority, and 9 privately owned and operated facilities are on outer harbor and along sides of Lackawanna and Union ship canal, 4 are along banks of Buffalo ship canal, and 26 along Buffalo River. Coast Guard facilities are at mouth of Buffalo River along left bank. City of Buffalo owns a slip on right bank of Buffalo River just north of Michigan Avenue Bridge for mooring city fireboat. Thirty-four terminals have railroad connections and 29 mechanicalhandling facilities. Facilities considered adequate for existing commerce. (See Port Series No. 41, revised 1971, Corps of Engineers.) Operations and results during fiscal year. Maintenance: Miscellaneous inspection services, condition surveys by Government plant and hired labor, water control management, and real estate activities cost $123,777. Repairs to about 590 1.f. of south breakwater by U.S. derrickboat McCauley cost $473,813. Removal of 121,500 cubic yards of shoaled material, by contract, cost $1,190,176. In-house engineering costs for preparation of plans and specifications for all harbor work and water quality studies of Times Beach cost $256,170. 5. CATTARAUGUS HARBOR, N.Y. Location. At mouth of Cattaraugus Creek on south shore of Lake Erie about 12 miles northeasterly from Dunkirk Harbor, N.Y. and 24 miles southwesterly from Buffalo Harbor, N.Y. (See NOAA Nautical Chart 14823.) Existing projects. For details of the existing project, see page 32-4 of Annual Report for 1983. Construction was completed in January 1983. Federal cost for new work was $4,797,821 (Oct. 1981). Non-Federal cost for new work was $2,566,529 (Oct. 1981). Existing project was authorized by 1968 River and Harbor Act (H. Doc. 97, 90th Cong., I st sess.). Local cooperation. See page 32-5 of Annual Report for 1976 for details of requirements of local cooperation. The cash contribution paid was $2,566,529. The State of New York executed local cooperation agreement in July 1981. Terminal facilities. Facilities consist of private docks for recreational craft and privately owned servicing and storage handling facilities for recreational and other small craft. 32- 3 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Operations and results during fiscal year. New work: Expenditure of $422 was attributed to in-house engineering effort. Maintenance: Project condition surveys were conducted at a cost of $1,425. 6. CLEVELAND HARBOR, OHIO Location. On south shore of Lake Erie, at mouth of Cuyahoga River, 176 miles westerly from Buffalo, N.Y. (See NOAA Nautical Chart 14839). Previous projects. For details see page 1962, Annual Report for 1915, and page 1585, Annual Report for 1938. Existing project. For description of existing project, as authorized thru the 1966 modification, see page 1269 of Annual Report for 1967. Further improvements were recommended in the Cleveland Harbor, OH Reformulation Phase I General Design Memorandum (Jul 84, revised Dec 84) consisting of: (a) enlarging and deepening to 31 feet LWD the east entrance channel; (b) deepening the east basin to 27 feet LWD; and (c) expanding the capacity of Dike Site 14 to contain the polluted dredged material resulting from the project. Estimated total Federal cost of the existing project is $33,022,100 (Oct 1984) exclusive of inactive and deferred portions of the project. The amount of $29,315,100 is for completed work and the balance of 3,707,000 is for new work proposed in the 1984 Reformulation Phase I GDM. Estimated non-Federal cost is $9,804,000 (Oct 1984) of which $9,203,000 is actual cost for completed work and the balance of $601,000 is required cash contribution for work proposed in the. 1984 Reformulation Phase I GDM. Remaining work authorized by 1946 River and Harbor Act, consisting of widening and deepening the right bank of Cuyahoga River at the downstream end of Cut 4, is considered inactive and excluded from foregoing cost estimate. Estimated Federal cost (1966) of this poriton is $85,600 and non-Federal cost (1966) is $5,000,000. Remaining work authorized by 1958 R & H Act, consisting of planning and replacement of bridges number 19 (E.L.R.R.) and 32 (B.&O.RR.) and widening Cuyahoga and Old River channels, and remaining work authorized by the 1960 R & H Act, consisting of deepening the remainder of Cuyahoga River from bridge number 1 to and including the Old River to a depth of 27 feet, has been classified as deferred and is also excluded from foregoing cost estimate. Estimated Federal Cost (Oct. 1976) of this portion is $18,033,300 and estimated non- Federal cost (Oct. 1976) is $21,251,000. See Table 32-B for authorizing legislation. Local cooperation. Fully complied with for completed portion of project. Items of local cooperation for work recommended in the 1984 Reformulation Phase I GDM consist of: (a) Provide without cost to the United States all lands, easements, and rights-of-way required for construction and maintenance of the harbor improvements, including suitable areas determined by the Chief of Engineers to be required in the general public interest for the initial and subsequent disposal of dredged material, and also necessary retaining dikes, bulkheads, and embankments therefor, or the cost of such retaining works; (b) Accomplish without cost to the United States all alterations and relocations of transportation systems, storm drains, sewer outfalls, utilities, and other relocations and alterations made necessary by the project; (c) Hold and save the United States free from damages due to the construction and maintenance of the project, not including damages due to the fault or negligence of the United States or its contractors; and (d) Provide and maintain without cost to the United States adequate depths in berthing areas and local access channels. Assurances will be requested upon completion of Phase II General Design Memorandum. Terminal facilities. There are 65 piers and wharves. Fourteen are on outer harbor, 11 on banks of Old River and 40 along the deep-draft section of Cuyahoga River. Forty-one terminals have both railroads connections and mechanicalhandling facilities. The Corps owns a wharf at the foot of East 9th Street. Facilities are considered adequate for existing commerce. (See Port Series No. 43, revised 1981, Corps of Engineers). Operations and results during fiscal year. New work: Preparation of Reformulation Phase I General Design Memorandum, as authorized by 1976 WRD Act, was completed under the General Investigation Appropriation at a cost of $26,076. Maintenance: Miscellaneous inspection services and condition surveys by Government plant and hired labor cost $256,119. Repairs to 40 1.f. of the east break water by U.S. derrickboat Ohio cost $249,209 and 121 l.f. of the west arrowhead breakwater by U.S. derrickboat Tonawanda cost $577,618. Removal of shoaled material: 215,146 cubic yards from Cuyahoga River and entrance channel cost $1,767,983. Expenditure of $52,273 was attributed to permanent layup of U.S. hopper dredge Hains In-house engineering costs for preparation of plans and specifications on contract dredging, major repairs to east breakwater, letter report on new confined disposal facility and structure inspections were $361,948. Major Rehabilitation: Repairs to 3,300 1.f. of the east breakwater, by contract, were initiated in July 1985, is 43% complete, and cost $2,100,674. Aerial photography, to establish pre-construction conditions, by contract, cost $8,436. 7. CONNEAUT HARBOR, OHIO Location. On south shore of Lake Erie, at mouth of Conneaut River, 73 miles easterly from Cleveland, Ohio. (See NOAA Nautical Chart 14824.) Previous projects. For details see page 1964, Annual Report for 1915. Existing projects. For description see page 1274 of Annual Report for 1967. Actual costs for new work for completed portion of the project were $7,541,369. See page 1274, Annual Report 1967, for complete description of project modification authorized by 1966 R&H Act. Estimated cost (1970) of this modification is $717,000. For completed work non-Federal costs were $200,000 for dockside dredging and removal of existing dolphins. Estimated non-Federal cost of $2,877,000 (1970) includes cash contribution of $717,000 and the remainder is for construction of service facilities for the 1966 project modification. See Table 32-B for authorizing legislation. 32 - 4 BUFFALO, NY DISTRICT Local Cooperation. Fully complied with for completed portion of project. See page 32-6 of Annual Report for 1971 for requirements of local cooperation for project modification as authorized by the River and Harbor Act of 1966. Terminal facilities. There are seven piers and wharves. Six are privately owned and operated and located in inner harbor. Remaining facility is city owned on the south side of outer harbor. Six terminals have railroad connections and four mechanical-handling facilities. (See Port Series No. 42, revised 1972, Corps of Engineers.) Operations and results during fiscal year. Maintenance: Miscellaneous inspection services and condition surveys were done by Government plant and hired labor at a cost of $25,811. Completion of repairs initiated in FY 84 by U.S. derrickboat McCauley cost $50,735. Expenditure of $23,687 was attributed to permanent layup of U.S. hopper dredge Hoffman. Finalization of FY 84 dredging contract resulted in a credit of $49,774. Snagging and clearing by government plant and hired labor cost $3,606. Particle size and specific gravity analysis of dredged material, by contract, cost $24,077. Engineering effort, to include in-house economics study, cost $19,369. 8. DUNKIRK HARBOR, N.Y. Location. On south shore of Lake Erie, 37 miles southwesterly from Buffalo, N.Y. (See NOAA Nautical Chart 14823.) Previous projects. For details see page 1966 of Annual Report for 1915, and page 1604 of Annual Report for 1938. Existing project For description of completed portion of existing project see page 32-8 of Annual Report for 1976. For description of small boat harbor project as authorized under Section 201 of Flood Control Act of 1965, see page 32-8 of Annual Report for 1978. Actual costs for completed work are $3,010,024. Actual non-Federal costs are $1,961,000. See Table 32-B for authorizing legislation. Local cooperaiton. Fully complied with. Terminal facilities. Facilities consist of private docks for recreational craft and privately owned servicing and storage handling facilities for recreational and other small craft. Operations and results during fiscal year. Maintenance: Miscellaneous inspection services and condition surveys by Government plant and hired labor cost $9,338. In-house economics study initiated in FY 84 was completed at a cost of $4,185. 9. ERIE HARBOR, PA. Location. On southerly side of bay formed by Presque Isle Peninsula, on south shore of Lake Erie, 78 miles westerly from Buffalo, N.Y. (See NOAA Nautical Chart 14835.) Previous projects. For details see page 1965 of Annual Report for 1915 and page 1600 of Annual Report for 1938. Existing projects. For description see pages 1363-64 of Annual Report for 1963. Entire project modification authorized by 1945 River and Harbor Act, providing for deepening channel and basin, both 23 feet deep, to Penn Central Company coal docks at westerly end of harbor, was deauthorized by Congress in August 1977. Actual costs for new work for completed portion of project were $2,860,906. Extension of north pier portion as authorized by 1899 act was deauthorized in November 1981. Estimated cost (1955) of this portion is $1,071,000. A portion of work authorized by 1960 act, deepening strips adjacent to north and south piers, was deauthorized in August 1982. Estimated cost (July 1962) of this portion is $78,000. Non-Federal costs for completed work were $51,000 for providing ore dock and dredging slip adjacent thereto. See Table 32-B for authorizing legislation. Local cooperation. Fully complied with. Terminal facilities. Sixteen piers and wharves, of which 12 are privately owned and operated. Erie International Marine Terminal No. 1 owned by Port Commission, city of Erie, is along main waterfront on south side of Presque Isle Bay and Coast Guard facilities are on north side. Two offshore oil docks are on Lake Erie. Eight terminals have railroad connections and six mechanical-handling facilities. Facilities are considered adequate for existing commerce. (See Port Series No. 42, revised 1972, Corps of Engineers.) Operations and results during fiscal year. Maintenance: Miscellaneous inspection services and condition surveys by Government plant and hired labor cost $29,182. Pumpout unit maintenance cost $5,682. Finalization of pier repair contract initiated in FY 83 under Jobs Bill cost $253,376. Engineering effort, including plant analysis program, cost $12,868. 10. FAIRPORT HARBOR, OHIO Location. On south shore of Lake Erie at mouth of Grand River, 33 miles easterly from Cleveland, Ohio. (See NOAA Nautical Chart 14837.) Previous projects. For details see page 1963 of Annual Report for 1915, and page 1590 of Annual Report for 1938. Existing project For description of existing project as authorized thru the 1960 modifications, see page 1526 of Annual Report for 1962; for description of small boat harbor as authorized by Sec. 201 of 1965 Flood Control Act, see page 32-10 of Annual Report for 1977. Estimated total Federal cost of new work is $4,931,000 (Oct. 1980) of which $2,591,000 is actual cost for completed portion of project and the balance of $2,340,000 is for proposed work authorized by Sec. 201 of 1965 FC Act which is deferred. Entire project modification authorized by 1960 River and Harbor Act, providing for deepening lake approach 32-5 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 channel, 800-foot wide channel through outer harbor and channel in Grand River, and enlargement of turning basin, is classified inactive and is excluded from foregoing cost. Estimated cost of this modification is $3,170,000 (1963). Estimated non-Federal cost is $4,991,000 of which $101,000 were for bulkheads and dockside dredging for completed portion of project and $2,560,000 which includes cash contribution of $2,330,000, is for work authorized by Sec. 201 of 1965 FC Act. For the inactive 1960 project modification, estimated non-Federal cost of $3,821,000 (1963) is for lands, relocations, utility changes, dock dredging and dock and bulkhead modifications. See Table 32B for authorizing legislation. Local cooperation. See page 32-11 of 1976 Annual Report regarding assurances of local cooperation for work authorized by R&H Acts of 1927 and 1960 and page 32- 11 of 1977 Annual Report for requirements of local cooperation for work authorized by Sec. 201 of 1965 Flood Control Act. Terminal facilities. Sixteen piers and wharves, all along banks of Grand River. One facility is owned by Coast Guard. Nine terminals have railroad connections and ten mechanical-handling facilities. Facilities considered adequate for existing commerce. (See Port Series No. 42, revised 1972, Corps of Engineers.) Operations and results during fiscal year. Maintenance: Miscellaneous inspection services and condition surveys by Government plant and hired labor cost $32,949. U.S. derrickboat Ohio performed pumpout unit maintenance at cost of $18,262. Removal of 59,383 cubic yards of shoaled material from the river and 92,611 cubic yards of shoaled material from the entrance channel cost $697,973. Inhouse engineering effort cost $15,116. 11. GENEVA-ON-THE-LAKE, OHIO Location. On south shore of Lake Erie about 17 miles east of Fairport Harbor, Ohio and 12 miles west of Ashtabula Harbor, Ohio (See NOAA Nautical Chart 14826.) Existing project Small boat harbor project provides for: (a) breakwaters in Lake Erie aggregating about 1,350 feet in length; (b) entrance channel about 730 feet long, 100 feet in width, 9 feet deep; (c) inner channels, 100 feet wide totaling 1,500 feet in length and 6 feet deep; (d) a mooring area 0.5 acres in area with a depth of 6 feet, (e) development of recreational facilities and (f) development of wetland mitigation features. Estimated Federal costs for new work is $4,770,000 (Oct. 1984). Non-Federal cost estimate of $5,000,000 (Oct. 1984) is cash contribution toward first cost of construction. Existing project was authorized under provision of Section 201 of Flood Control Act of 1965. (H.D. 409, 91st Cong., 2d sess.) Local Cooperation. See page 32-11 of 1978 Annual Report for requirements of local cooperation for work authorized by Sec. 201 of 1965 Flood Control Act. By letters dated November 10, 1977, April 15, 1981 and September 10, 1982 the State of Ohio Department of Natural Resources (ODNR) the responsible agency, has indicated its willingness and ability to furnish the assurances. By letter dated October 31, 1984, ODNR offered the Corps "advanced" Non-Federal funds of $1,000,000 to permit initiation of project construction in FY85. In consideration of ODNR's request, the Corps could not accept the offer because the proposed project did not meet New Start Construction criteria. The Corps must wait for specific direction by the Congress and the appropriation of necessary funds. Assurances of local cooperation will be requested upon approval of a draft Local Cooperation Agreement in FY 86. Terminal facilities. There are no commercial or recreational facilities at the harbor. Operations and results during fiscal year. New York: In FY 85, Plans and Specifications were approximately 90 percent completed. In-house engineering effort cost $31,967. Total costs including Construction, General, funds are $999,056. 12. GREAT SODUS BAY HARBOR, N.Y. Location. On Sodus Bay, which is a nearly landlocked indentation on south shore of Lake Ontario, 29 miles westerly from Oswego, N.Y. (See NOAA Nautical Chart 14814.) Previous projects. For details see page 1972 of Annual Report for 1915 and page 1526 of Annual Report for 1938. Existing project For description, see page 1380 of Annual Report for 1963. Improvements authorized by 1962 act, consisting of deepening lake approach channel, entrance channel and inner approach channel were deauthorized by Congress in August 1977. Actual costs of new work for completed portion of project were $249,187. Costs incurred by local interests are not available. See Table 32-B for authorizing legislation. Local cooperation. Fully complied with. Terminal facilities. Facilities consist of private docks for recreational craft and privately owned servicing and storage handling facilities for recreational and other small craft. Operations and results during fiscal year. Maintenance: Miscellaneous inspection services and condition surveys by Government plant and hired labor cost $706. In-house economics study was completed at cost of $3,425. 13. HURON HARBOR, OHIO Location. On south shore of Lake Erie at mouth of Huron River, 47 miles westerly from Cleveland, Ohio. (See NOAA Nautical Chart 14843.) Previous project For details, see page 1961 of Annual Report for 1915, and page 1576 of Annual Report for 1938. 32 -6 BUFFALO, NY DISTRICT Existing project For description see page 1347 of Annual Report for 1963 and page 32-12 of Annual Report for 1978. Cost of completed portion of existing project was $4,834,006. Construction of detached breakwater as authorized by 1962 R&H act is deferred. Estimated cost of construction of breakwater is $12,970,000 (July 1972). Non-Federal costs of $163,000 were incurred by local interests in 1963 for dockside dredging of areas between Federal improvement and terminal facilities. See Table 32B for authorizing legislation. Local cooperation. Fully complied with. Terminal facilities. Six privately owned wharves and docks, one along left bank of Huron River and remainder along right bank. Four terminals have railroad connections and four mechanical-handling facilities. Facilities are regarded as adequate for existing commerce. (See Port Series No. 42, revised 1972, Corps of Engineers.) Operations and results during fiscal year. Maintenance: Miscellaneous inspection services and condition surveys by Government plant and hired labor cost $25,738. Maintenance dredging, by contract, cost $454,102, for removal of 46,021 cubic yards from lake approach, river entrance channel, and turning basin. Plans and specs for maintenance dredging, by contract, cost $2,073. Particle size and specific gravityanalysis, by contract, cost $24,077. Engineering effort cost $24,991. 14. IRONDEQUOIT BAY, N.Y. Location. On south shore of Lake Ontario, 4 miles east of Rochester, N.Y. at month of Irondequoit Creek, Monroe County, N.Y. (See NOAA Nautical Charts 14804 and 14815.) Existing project Provides for: (a) entrance channel 9 feet deep and 100 feet wide, extending from 9-foot depth in Lake Ontario to junction with inner bay channels a distance of about 1,300 feet; (b) inner channel, 8 feet deep and 100 feet wide, from entrance channel to deep water in bay, a distance of about 3,035 feet; (c) access channel, 8 feet deep, 100 feet wide, and 500 feet in length from the inner bay channel to the west, (d) two stone rubblemound stuctures 1,350 feet and 750 feet in length at the natural entrance; and (e) recreational facilities of parking area, two comfort stations, concrete walkways and hand railings on the breakwater and jetty. The local sponsor (New York State Office of Parks, Recreation and Historic Preservation) requested that the comfort stations and parking areas be constructed under a separate contract from that for the navigation features. A contract for construction of the breakwaters, jetty, navigation channel and highway bridge removal was awarded in June 1984 for $3,333,000. Total project cost is $14,390,000 (Oct. 1984) including $2,903,000 Federal (which includes the CoE $2,852,000 and the USCG $51,000) and 11,478,000 non- Federal, including a cash contribution of $2,367,000, lands and damages $290,000, and the cost of a movable highway bridge $8,830,000. Existing project was authorized by 1958 River and Harbor Act (H. Doc 332, 84th Cong., 2nd sess.) Local cooperation. The Buffalo District has a properly executed Local Cooperation Agreement with New York State, executed April 20, 1983. Terminal facilities. Facilities consist of private docks for recreational craft and privately owned servicing and storage handling facilities for recreational and other small craft. Operations and results during fiscal year. Construction of the breakwaters, jetties and recreational facilities were continued at a Federal cost of $1,568,675 and a non-Federal cost of $779,471. In-house engineering effort cost $178,643, Federal funds and $8,898 non-Federal funds. No dredging work was done in FY 85 because a group of private individuals filed a suit against the U.S. on the removal of the Route 18 bridge. A motion for a preliminary court injunction against bridge removal was filed on April 12, 1985. A Notice of Appeal was filed on May 16, 1985. The court heard the appeal and found in favor of the Government on July 30, 1985. The Route 18 bridge was removed August 15, 1985. Costs of bridge removal are included in the above non-Federal construction costs. 15. LITI'LE SODUS BAY HARBOR, N.Y. Location. Little Sodus Bay, on south shore of Lake Ontario, 15 miles west of Oswego, N.Y. (See NOAA Nautical Chart 14803.) Previous projects. For details see page 1973 of Annual Report for 1915, and page 1628 of Annual Report for 1938. Existing project For description see page 1378 of Annual Report for 1958. New work for completed project cost $69,066. Non-Federal costs of $6,000 were incurred for channel dredging. See Table 32-B for authorizing legislation. Local cooperation. Non required Terminal facilities. Facilities consist of private docks for recreational craft and privately owned servicing and storage handling facilities for rereational and other small craft. Operations and results during fiscal year. Maintenance: In-house economics study was completed at cost of $11,044. 16. LORAIN HARBOR, OHIO Location. On south shore of Lake Erie at mouth of Black River, 28 miles westerly from Cleveland, Ohio. (See NOAA Nautical Chart 14841.) Previous projects. For details, see page 1961 of Annual Report for 1915, and page 1580 of Annual Report for 1938. Existing project for description see pages 1319-22 of Annual Report for 1966. Estimated Federal cost of new work is $26,246,000 (Oct. 1976.) Deepening and widening remainder of Black River Channel at Cut 1 and construction of bank stabilization as authorized by 1960 act and modified by 1965 act is classified deferred. The estimated cost of 32- 7 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 $5,317,000 for this work is included in the above estimate. A portion of work authorized by 1960 act, dredging of 15-to-25- foot wide strips adjacent to the U.S. East and West piers is also deferred and estimated cost of $60,200 (July 1966) is excluded from foregoing cost estimate. Total non-Federal cost estimate is $8,853,000 (Oct. 1976) including $3,000 contributed by local interests toward construction of west breakwater shorearm. For work authorized by 1960 act, including deferred portion, non-Federal costs are estimated to be $8,805,000 for lands, relocations of utilities, modifications of existing dock and bulkheads, construction of new bulkheads and dockside dredging. For work authorized by 1965 act, classified as deferred, local interests must make a cash contribution presently estimated at $45,000. See Table 32-B for authorizing legislation. Local cooperation. For completed work, local interests contributed $3,000. Work authorized by 1960 act (and modified by 1965 act) is deferred. All other conditions fully complied with. Terminal facilities. There are 23 piers and wharves, of which three are on outer harbor and remainder are along banks of Black River. Two are owned by the city. Eight terminals have railroad connections and 15 mechanicalhandling facilities. Facilities are considered adequate for existing commerce. (See Port Series No. 42, revised 1972, Corps of Engineers.) Operations and results during fiscal year. Maintenance: Miscellaneous inspection services and condition surveys by Government plant and hired labor cost $46,881. Repairs to 96 1. f. of the east breakwater by the U.S. derrickboat Ohio cost $299,888. Removal of an estimated 163,540 cubic yards of shoaled material from Black River Channel and upper turning basin, by contract, cost $682,019. In-house engineering costs were $35,307. 17. OAK ORCHARD HARBOR, N.Y. Location. On south shore of Lake Ontario at mouth of Oak Orchard Creek, 33 miles westerly of Rochester, N.Y. (See NOAA Nautical Chart 14805.) Previous project For details see page 628 of Annual Report for 1905. Existing project. For description of completed existing project see page 32-14 of 1975 Annual Report. Actual Federal cost for completed project was $1,613,500. Estimated non-Federal cost is $270,000 (July 1971) including cash contribution of $170,700 and $54,002 for recreational facilities and remainder for lands and construction of wharf. Existing project was authorized by the 1945 River and Harbor Act (H. Doc. 446, 78th Con., 2nd sess.). Local cooperation. Fully complied with. Local interests contributed $224,702. Terminal facilities. There is no commercial navigation at Oak Orchard Harbor. Terminal facilities consist of private docks for recreational craft. Operations and results during fiscal year. Maintenance: Miscellaneous inspection and condition surveys cost $76. Maintenance dredging was intiated by contract and removed an estimated 1,670 cubic yards of shoaled material at a cost of $19,594. Engineering effort cost $4,392. 18. OGDENSBURG HARBOR, N.Y. Location. On south shore of St. Lawrence River, 62 miles by water from Lake Ontario. (See NOAA Nautical Chart 14764.) Previous projects. For details see page 1975 of Annual Report for 1915, and page 1635 of Annual Report for 1938. Existing project For description see page 1568 of Annual Report for 1962. Actual cost for new work for completed portion of project was $375,086. Removal of hard material shoals from lower basin portion of project as authorized by 1935 act, at an estimated cost of $183,000 (1954) is classified inactive. See Table 32-B for authorizing legislation. On April 20, 1983, the Chief of Engineers under authority provided by Section 107 of the 1960 River and Harbor Act, as amended, authorized an extension of Lower East Entrance Channel, 600 feet west of the existing pier to a depth of 27 feet below LWD. Dredged material is to be disposed of in dredged disposal area Site 5, owned by Ogdensburg Bridge and Port Authority and previously used for this purpose. Estimated costs for this work (Aug. 82) are $870,000 Federal and $4,280,000 non-Federal. Local cooperation. For details of local cooperation requirements see page 32-8 of Annual Report for 1983. Operations and results during fiscal year. New Worck: Dredging to depth authorized by Section 107 was completed. Contract costs for dredging were $688,267 Federal funds and $5,597 non-Federal funds. In-house engineering effort cost $15,469 Federal funds and $608 non-Federal funds. Maintenance: Project condition surveys were completed at a cost of $3,801. 19. OLCOTT HARBOR, N.Y. Location. On south shore of Lake Ontario at mouth of Eighteen Mile Creek about 18 miles east of mouth of Niagara River and 63 miles by water west of Rochester, N.Y. (See NOAA Nautical Chart 14806.) Previous project. For details see page 1971 of Annual Report for 1915 and page 1621 of Annual Report for 1938. Existing project. For description see page 1555 of Annual Report for 1962. Cost of new work for completed project was $1,500 exclusive of amounts expended on previous projects, all of which was contributed by local interests. See Table 32-B for authorizing legislation. 32 - 8 BUFFALO, NY DISTRICT Local cooperation. Fully complied with. Local interests contributed $1,500. Terminal facilities. Facilities consist of private docks for recreational craft and privately owned servicing and storage handling facilities for recreational and other small craft. Operations and results during fiscal year. Maintenance: Miscellaneous inspection services and condition surveys by Government plant and hired labor cost $7,342. Maintenance dredging was performed by contract and removed 5,315 cubic yards of material at a cost of $60,243. Engineering effort cost $1,434. 20. OSWEGO HARBOR, N.Y. Location. On south shore of Lake Ontario, at mouth of Oswego River, 59 miles easterly from Rochester, N.Y. (See NOAA Nautical Chart 14813.) Previous projects. For details see page 1973 of Annual Report for 1915, and page 1630 of Annual Report for 1938. Existing project. For description see pages 1383-84 of Annual Report for 1963. Completed portion of project cost $7,242,039 and non-Federal costs for completed work were $4,440,000 for lands, dockside dredging, construction of terminal, wharves and cargo handling facilities. Deepening a 200-foot wide strip along harbor line east of mouth of Oswego River, remaining feature of work authorized by the 1930 act, is classified as inactive. Deepening to 22 feet a 150-foot wide strip along harbor line in west outer harbor, remaining feature of work authorized by 1940 act, was deauthorized in May 1981. Estimated Federal costs for this work are $246,000 (July 1957) and $2,419,000 (July 1966) respectively, and estimated non-Federal costs are $500,000 (July 1966) for dockside dredging for work authorized by 1940 act. See Table 32-B for authorizing legislation. Local cooperation. Fully complied with. Terminal facilities. Seven piers and wharves in harbor and along river channel. In addition, Port of Oswego Authority owns two public terminals, one of which is west of river and includes a grain elevator and warehouse for miscellaneous freight. Other terminal is east of river and used for handling aluminum and general cargo. State of New York owns a river terminal used for mooring vessels. City of Oswego owns one dock and shore facilities for recreational craft. Facilities considered adequate for existing commerce. Operations and results during fiscal year. Maintenance: Miscellaneous inspection services and condition surveys by Government plant and hired labor cost $18,311. Finalization of costs of FY 84 maintenance dredging contract resulted in credit of $8,575. In-house engineering effort to include economics study, cost $6,842. 21. PORT CLINTON HARBOR, OHIO Location. Comprises lower half-mile of Portage River. River empties into Lake Erie 72 miles westerly from Cleveland, Ohio. (See NOAA Nautical Chart 14820). Existing project Provides for parallel jetties at river mouth and a channel in Lake Erie and Portage River with a project depth of 10 feet. For additional details see page 1899 of Annual Report for 1951. (See Table 32-B for authorizing legislation.) Local cooperation. None required. Terminal facilities. There is one public fish dock, one private sand dock, one private fuel, lumber and coal dock, and five additional private docks. A dock at foot of Madison Avenue is owned by village of Port Clinton and open to the public. A shipyard builds small boats. Terminal facilities are adequate for existing commerce. Operations and results during fiscal year. Maintenance: Miscellaneous inspection services and project condition surveys by Government plant and hired labor cost $8,009. Finalization of plant analysis program, by contract, initiated in FY 84 cost $4,237. 22. PORT ONTARIO HARBOR, N.Y. Location. On southeasterly end of Lake Ontario, 19 miles northeasterly of Oswego, N.Y., and 32 miles southerly of Sackets Harbor, N.Y. (See NOAA Nautical Chart 14803.) Previous projects. Adopted by the River and Harbor Act July 4, 1836. Only information available is the index to the report of the Chief of Engineers. Existing project Existing project, as modified by Phase I General Design Memorandum, provides for. (a) two shore connected rubblemound breakwaters in Lake Ontario at mouth of Salmon River, south breakwater about 1,450 feet and north breakwater about 350 feet long; (b)entrance channel between breakwaters, 100 feet wide and 8 feet deep, from deep water in lake to a limit about 1,200 feet from 8- foot depth contour in lake; (c) river channel 85 feet wide and 6 feet deep from inner limit of entrance channel for a distance upstream of about 450 feet. Estimated Federal cost for new work is $2,905,000 (Oct. 1984). Estimated non-Federal cost for new work is $2,176,300 (Oct 1984) including cash contribution of $1,856,300. Existing project was authorized by the River and Harbor Act of March 2, 1945 (H. Doc. 446, 78th Cong., 2nd Sess.) Local cooperation. See page 32-16 of Annual Report for 1976 for details of requirements of local cooperation. Assurances will be requested upon approval of Phase II Design Memorandum. Terminal facilities. There is no commercial navigation at Port Ontario Harbor. Terminal facilities consist of private docks for recreational craft. Operations and results during fiscal year. New Work Funds in the amount of $10,000 were received late in FY 85. There were no expenditures during the year. 32- 9 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 23. ROCHESTER HARBOR, N.Y. Location. On south shore of Lake Ontario, at mouth of Genesee River, 59 miles westerly from Oswego, N.Y. (See NOAA Nautical Chart 14815.) Previous project. For details see page 1471 of Annual Report for 1915, and page 1623 of Annual Report for 1938. Existing project For description see page 1556 of Annual Report for 1962. Actual cost for new work for completed project is $21,191,514. Non-Federal costs are estimated at $2,260,000, all for 1960 act, for lands, relocation of submarine cable crossing, relocations of small docks and boathouses, dockside dredging, structure modifications, and replacement of Baltimore & Ohio coal loader. See Table 32- B for authorizing legislation. Local cooperation. Complied with except provision for replacement of coal loading facility as required by River and Harbor Act of July 14, 1960. Terminal facilities. One terminal facility at mouth of Genesee River has been leased to the Great Lakes Division of Pittston Stevedoring Corp. Facilities also consist of private docks for recreational craft and privately owned servicing and storage handling facilities for recreational and other small craft. Facilities are considered adequate for existing commerce. Operations and results during fiscal year. Maintenance: Miscellaneous inspection services and condition surveys by Government plant and hired labor cost $49,081. Finalization of pier repair contract initiated under Jobs Bill cost $104,381. Finalization of FY 84 dredging contract cost $82,007. Soil sampling and testing, particle size and specific gravity analysis, and sediment testing, by contract, cost $11,198; $1,761; and $27,950 respectively. Engineering effort cost $146,245. 24. ROCKY RIVER HARBOR, OHIO Location. At mouth of Rocky River which empties into Lake Erie 7 miles westerly from Cleveland, Ohio. (See NOAA Nautical Chart 14826.) Existing project For description see page 1329 of Annual Report for 1966. Federal cost for completed project was $343,494 and non-Federal cost was a cash contribution of $249,346. See Table 32-B for authorizing legislation. of material was removed at cost of $308,916. Repair of the east pier, by contract, was initiated late in FY 85 and cost $50,806. Engineering effort for plans and specs cost $22,495. 25. SANDUSKY HARBOR, OHIO Location. On south shore of Lake Erie, in southeasterly portion of Sandusky Bay, 50 miles westerly from Cleveland, Ohio. (See NOAA Nautical Chart 14845.) Previous projects. For details see page 1960 of Annual Report for 1915, and page 1574 of Annual Report for 1938. Existing project. For description see pages 1511-12 of Annual Report for 1962. Actual costs for new work for completed project were $6,250,121, excluding $325,000 contributed by local interests. Non-Federal costs for completed project are estimated at $675,000 including $325,000 cash contribution and the remaining $350,000 is for dockside dredging adjacent to deepened channels authorized by 1960 act. See Table 32-B for authorizing legislation. Local cooperation. Fully complied with. Local interests contributed $325,000 for new work. Terminal facilities. Fourteen piers and wharves, three at west end of harbor and remainder along dock channel. One is a base for State-owned fish research and patrol boats. One publicly owned and six privately owned are used for mooring fishing boats and recreational craft and for ferry service. Five terminals have railroad connections and five mechanical-handling facilities. Facilities are considered adequate for existing commerce. (See Port Series No. 42, revised 1972, Corps of Engineers.) Operations and results during fiscal year. Maintenance: Miscellaneous inspection services and condition surveys by Government plant and hired labor cost $39,493. Maintenance dredging, by contract, removed 204,399 cubic yards of shoaled material and cost $843,738. Specific gravity analysis, by contract, cost $25,412. Engineering effort cost $47,633. 26. TOLEDO HARBOR, OHIO Location. Comprises lower 7 miles of Maumee River and channel through Maumee Bay to Lake Erie. Maumee River has its source in northern Indiana and empties into Lake Erie. Harbor is at westerly end of Lake Erie, 99 miles westerly from Cleveland, Ohio. (See NOAA Nautical Chart 14847.) Local cooperation. Fully complied with. Local interests Previous projects. For details see page 1959 of Annual contributed $249,346 for new work. Report for 1915, and page 1565 of Annual Report for 1938. Terminal facilities. Facilities consist of private docks for recreational craft and privately-owned servicing and storage handling facilities for recreational and other small craft. Operations and results during fiscal year. Maintenance: Miscellaneous inspection services and project condition surveys by Government plant and hired labor cost $7,645. Environmental testing, by contract, cost $7,790. Maintenance dredging was performed by contract and 47,829 cubic yards Existing project. For description of existing project see pages 32-18 and -19 of Annual Report for 1978. Cost of completed existing project was $15,567,147. See Table 32-B for authorizing legislation. Local cooperation. Fully complied with. 32- 10 BUFFALO, NY DISTRICT Terminal facilities. Maumee River though city of Toledo has been developed extensively for deep-draft navigation. Detailed information on actual port and harbor facilities are in Port Series No. 44 (revised 1972) prepared and published as Part 2, by Board of Engineers for Rivers and Harbors. Information on port administration and Federal services, port and terminal services and charges, and steamship services is prepared and published as Part I by the Port Development Staff, U.S. Department of Commerce. Facilities are considered adequate for existing commerce. Operations and results during fiscal year. Maintenance: Condition surveys, environmental studies, and miscellaneous inspections and reports were performed by hired labor at a cost of $132,432. Expenditure of $45,079 was attributed to the permanent lay-up of the U.S. hopper dredge Markham. Removal of 876,150 cubic yards of shoaled material from the Bay Channel and the Maumee River Channel, by contract, cost $4,059,148. Repairs to diked disposal facility by hired labor cost $16,576. Flooding of disposal area to eradicate botulism problem, by contract, cost $12,350. Biological and environmental study, by contract, cost $26,559. Particle size and specific gravity analysis of dredged material, by contract, cost $27,337. Sediment testing for disposal area, by contract, cost $21,502. Engineering effort, to include studies toward new confined disposal facility, cost $291,684. 27. VERMILION HARBOR, OHIO Location. On south shore of Lake Erie at mouth of Vermilion River, 37 miles westerly from Cleveland, Ohio. (See NOAA Nautical Chart 14826.) Existing project For description of existing project see pages 32-17 and 32-18 of Annual Report for 1975. Actual Federal cost for the completed existing project was $1,156,118. Estimated non-Federal cost for new woric is $754,679 including cash contribution of $740,679 and remainder for relocation of submarine cable and construction of public wharf. See Table 32-B for authorizing legislation. Local cooperation. Fully complied with. Local interests contributed $740.679. Terminal facilities. Facilities consist of private docks for recreational craft and privately owned servicing and storage handling facilities for recreational and other small craft. Operations and results during fiscal year. Maintenance: Miscellaneous inspection and condition surveys by Government plant and hired labor cost $9,067. Snagging and clearing, by government plant and hired labor to clear navigation channel, cost $14,900. Maintenance dredging was performed by contract and 17,072 cubic yards of material was removed from the river and 30,448 cubic yards were removed from the entrance channel at a cost of $463,359. Engineering effort cost $14,802. 28. WEST HARBOR, OHIO Location. On southwest shore of Lake Erie, 13 miles northeast of Port Clinton, Ohio (See NOAA Nautical Chart 14847.) Existing Project For description of existing project, see page 32-10 of Annual Report for 1983. Estimated Federal cost for new work is $3,150,000 (Oct. 1980). Estimated non- Federal cost is $4,330,000 (Oct. 1980), including cash contribution of $3,570,000. Existing project was authorized by 1965 River and Harbor Act (H. Doc. 245, 88th Cong, 2nd sess.) Local cooperation. See page 32-20 of 1978 Annual Report for requirments of local cooperation. By letter dated January 31, 1978, State of Ohio stated its intent to furnish assurances of local cooperation, and executed LCA was received on March 9, 1981. Terminal facilities. Commerce at the harbor presently consists of recreational boating and affiliated activities. Operations and results during fiscal year. New work: Inhouse engineering effort was finalized at a cost of $1,071. Maintenance: Project condition surveys were conducted at a cost of $14,739. 29. WILSON HARBOR, N.Y. Location. At mouth of east branch of Twelve Mile Creek, which enters Lake Ontario 12 miles easterly of mouth of Niagara River, and 67 miles westerly of Rochester Harbor, N.Y. (See NOAA Nautical Chart 14806). Previous project For details see page 2395 of Annual Report for 1889, and page 628 of Annual Report for 1905. Existing project For description see page 32-18 of Annual Report for 1975. Actual Federal cost for the completed existing project was $477,904. Estimated non- Federal costs are $774,000 which includes cost of $16,000 for previously completed work. Remainder of non-Federal costs are for work required for 1968 R&H Act including cash contribution of $166,988. See Table 32-B for authorizing legislation. Local cooperation. Fully complied with. Terminal facilities. Facilities consist of private docks for recreational craft and privately owned servicing and storage handling facilities for recreational and other small craft. Facilities are considered adequate for existing commerce. Operation and results during fiscal year. Maintenance: Miscellaneous inspection and condition surveys by Government plant and hired labor cost $903. Extension of west pier, by contract, cost $67,950. Maintenance dredging was performed by contract and removed 25,640 cubic yards of material at a cost of $195,158. Engineering effort cost $575. 32- 11 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 30. RECONNAISSANCE AND CONDITION SURVEYS Project map updates at following projects: Project Little River, N.Y. Morristown, N.Y. Sackets Harbor, N.Y. Put-in-Bay, OH. Cape Vincent, N.Y. FY Cost $38 38 38 120 38 31. OTHER AUTHORIZED NAVIGATION PROJECTS See Table 32-C. 32. NAVIGATION WORK UNDER SPECIAL AUTHORIZATION See Table 32-D. Navigation work pursuant to Section 302, Public Law 89- 298. Lake Neatahwanta, Fulton, NY-Costs of $18,207 were incurred for preparation of scope of work and appendices for Detailed Project Study Contract Beach Erosion Control 33. LAKEVIEW PARK, LORAIN, OHIO Location. In the city of Lorain, Lorain County, Ohio, on south shore of Lake Erie between 1,500 and 3,000 feet west of Lorain Harbor west breakwater. (See NOAA Nautical Chart 14841.) Existing project For description of existing project see page 32-19 of Annual Report for 1977. The Federal cost of the completed project was $1,360,986 and estimated non- Federal cost (Oct. 1976) was $50,000 for relocation. In addition, local interests contributed $583,280. Annual cost of 5-year program for beach replenishment and monitoring was approximately $75,000. Existing project authorized by 1954 River and Harbor Act (H. Doc. 224, 83rd Cong. 1st sess.) Local cooperation. Fully complied with. Operations and results during fiscal year. New Work: Five-year monitoring program was completed in 1982. Cooperative beach nourishment was conducted in FY 80 and FY 81, during which time a total of 9,000 cubic yards of sand was placed within the project limits. In FY 84 an agreement was made between city of Lorain and the Federal government to continue cost sharing, 70% Federal and 30% local, the costs associated with annual beach nourishment until September 30, 1992, as provided by Section 156, P.L 94-587. A beach nourishment contract was awarded and completed in FY 85, at a cost of $31,704 ($22,465 Federal funds, $9,239 non-Federal funds). In-house engineering effort cost $2,462. The Federal cost for nourishment has totalled approximately $98,000, and costs to local interests have totalled approximately $40,000. 34. PRESQUE ISLE PENINSULA, ERIE, PA Location. At Erie, Pa., on south shore of Lake Erie, 78 miles southwest of Buffalo, N.Y. and 102 miles eastnortheast of Cleveland, Ohio, (See NOAA Nautical Charts 14824 and 14835). Existing project For description of completed portion of existing project see page 1393 of Annual Report for 1963. The Water Resources Development (WRD) Act of March 7, 1974, reinstated and extended authorization for beach erosion control project, as provided in 1960 R&H Act, for a period of five years from date of enactment of 1974 WRD Act, or if the review study of such project is not completed prior to end of such period, until such study is completed and a report thereon submitted to Congress. Work authorized by the 1974 WRD Act was completed in 1979. The 1976 Water Resources Development Act provides for continued annual nourishment by stating "At expiration of authorization provided in Section 57 of Water Resources Development Act of 1974, the Secretary of the Army, acting through the Chief of Engineers, may provide periodic beach nourishment in accordance with cost sharing provisions of Section 103 (a) (2) of Act of October 23, 1962." The act also authorized preparation of a Phase I General Design Memorandum. The Final Phase I General Design Memorandum (GDM) was completed in June 1980 and the recommended plan provides for construction of 58 offshore rubblemound breakwater segments, beach restoration by placement of sand fill, and annual beach replenishment for shore protection. A draft reformulation report was prepared in June 1985 to reassess the Presque Isle project and analyze additional plans for controlling beach erosion. The report recommended that the plan selected in the Phase I GDM be modified to reduce the number of offshore breakwater segments from 58 to 38 and to construct 10,000 feet of bank run gravel beaches along the neck of the peninsula. The project would be constructed by a 12-year staged construction program. On September 20, 1985, the Office, Chief of Engineers recommended to the Assistant Secretary of the Army that the Corps proceed with the ongoing 58-breakwater plan with staged construction. Estimated Federal cost for the authorized project and modifications (Oct 1984) is $16,446,000 which includes $5,646,000 for completed work authorized by the 1954 and 1960 R&H Acts and 1974 WRD Act and $5,771,000 for completed work authorized by the 1976 WRD Act. Emsotdimifiactaetdio nnso n(-OFecdt.e ra1l9 8c4o)s t isf or the authorized project and $8,610,000 which includes $3,983,000 for completed work authorized by 1954 and 1960 R&H Acts and 1974 WRD Act and $2,423,000 for completed work authorized by the 1976 WRD Act. The estimated Federal cost (March 1985) for the breakwater and gravel beach project is $20,678,000 of which $9,548,000 is for continuation of the present annual nourishment project while the permanent features are being built. The estimated 32- 12 BUFFALO, NY DISTRICT non-Federal cost (March 1985) for the breakwaters and gravel beach project is $8,862,000 of which $4,092,000 is for continuation of the present annual nourishment project while the permanent features are being built See Table 32-B for authorizing legislation. Local cooperation. Fully complied with for completed project as authorized by 1954 and 1960 R&H Acts and 1974 WRD Act. An agreement between the United States of America and the Commonwealth of Pennsylvania, acting through the Department of Environmental Resources, was entered into on February 21, 1979 for the annual nourishment which was extended by the 1976 Water Resources Development Act. The plan recommended in the Reformulation Report is contingent upon local sponsor, namely the Department of Environmental Resources of the Commonwealth of Pennsylvania, agreeing in writing to provide without cost to United States all lands, easements and rights-of-way, including suitable borrow and disposal areas for excavated material as determined by the Chief of Engineers and necessary for implementation and for periodic nourishment of the project; provide a cash contribution based on the appropriate percentage of final construction cost, exclusive of lands, easements, and rights-of-way, the percentage to be in accordance with existing law based on shore ownership and use existing at time of construction, which contribution is presently estimated at $8,862,000 or 30 percent; pay 30 percent of the cost for annual beach redistribution and replenishment work for the project; hold and save the United States free from damages due to construction works, except for damages due to fault or negligence of Government or its contractors; maintain and operate all the works, including breakwaters and periodic sand and gravel replenishment and redistribution as needed, after completion in accordance with regulations prescribed by the Secretary of the Army; and assure continued public ownership and continued public use without cost to the United States of appropriate access and facilities including parking and sanitation, necessary for realization of public benefits upon which Federal participation is based, and administer and maintain beach for continued public use during life of project. Formal assurances of local cooperation will be requested and executed prior to initiation of construction of improvements. Operations and results during fiscal year. New worklc Beach nourishment as authorized by the 1976 WRD Act was continued. The FY 84 contract operations which were initiated after the 1984 Labor Day holiday were completed during the first quarter of FY 85. The cobblestone test beach was deleted from the FY 84 contract operations and readvertised as a bank run gravel test beach in FY 85. Two contracts for providing beach nourishment were awarded and completed in FY 85. One contract required placement of the bank run gravel test beach and the second required placement of 278,800 tons of sandfill. During the year a total of $2,579,089 ($1,708,859 Federal and $870,230 non-Federal) was expended for beach nourishment operations. Of this total, contract costs were $1,659,137 Federal and $832,927 non- Federal. In-house engineering effort cost $49,722 Federal and $37,303 non-Federal. The Commonwealth of Pennsylvania, in addition to their FY 84 contribution of $373,254, contributed $497,143 for their share of the FY 85 nourishment operations. The cumulative non-Federal total project share through FY 85 is $6,405,968. The Final Phase I General Design Memorandum was submitted to the Secretary of the Army in October 1981 for his review and transmittal to Congress. In FY 85, a total of $240,241 was expended to investigate whether other plans for reducing cost of the combined beach and Erie Harbor annual cost, exists in lieu of the project recommended in the Phase I General Design Memorandum. Maintenance: Project condition surveys were conducted at a cost of $44. 35. OTHER AUTHORIZED BEACH EROSION CONTROL PROJECTS See Table 32-E. Beach Erosion Work under Special Authorization 36. LAKESHORE PARK ASHTABULA, OHIO Location. Lakeshore Park is located in Ashtabula, Ashtabula County, Ohio, about 40 miles southwest of Erie, Pennsylvania, and about 50 miles northeast of Cleveland, Ohio. Existing project For description of existing project, see page 32-12 of Annual Report for 1983. Construction was completed in July 1983. Local cooperation. For details of local cooperation requirements, see page 32-12 of Annual Report for 1983. Operations and results during fiscal year. New work: Net credit to project after contributed funds were received was $2,808. Non-Federal cost of beach replenishment contract was $14,744. Beach erosion activity pursuant to Section 103, Public Law 87-874 (preauthorization) Century Park, Lorain, OH-Costs of $37,529 were incurred for preauthorization studies. Miller Park, Avon, OH-Costs of $7,500 were incurred for preauthorized studies. Mentor Beach Park, Mentor, OH-Costs of $24,984 were incurred for preauthorization studies. Lake Erie, Huntington, OH-Costs of $3,500 were incurred for preauthorization studies. Port Clinton, OH-Costs of $10 were incurred for preauthorization studies. Simms Park, Euclid, OH-Costs of $35,489 were incurred for preauthorization studies. Flood Control 37. CUYAHOGA RIVER BASIN, OHIO Location. The project is located in northeastern Ohio, in Cuyahoga and Summit Counties, in the Cuyahoga River watershed. (See Geological Survey Map of Cleveland- South.) 32- 13 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Existing project. For details of existing project, see page 32-13 of Annual Report for 1983. Estimated cost (Oct. 1982) for new work is Federal $23,000,000 and non- Federal $1,080,000 for lands, damages and relocations. Existing project was authorized by Section 108 of 1970 River and Harbor act, and Section 102 of PL 97-88. Local cooperation. See page 32-17 of 1981 Annual Report for requirements of local cooperation. These items were adopted and agreed to by the Cleveland Metro Park System on January 20, 1982. Operations and results during fiscal year. New Work: Preconstruction planning was continued at a cost of $508 for in-house engineering effort. 38. DANSVILLE AND VICINITY, CANASERAGA CREEK, N.Y. Location. In towns of North Dansville and West Sparta, Livingston County, New York (See Geological Survey Map Dansville, N.Y. 1942.) Existing project For description of existing project see page 32-13 of Annual Report for 1983. Federal cost for new work is $775,000 (October 1984). Non-Federal cost estimate of $415,000 (October 1984) includes a cash contribution of $375,000 and $40,000 for lands. Existing project was authorized by Sec. 203 of 1948 Flood Control Act (H.D. 206, 80th Cong., I1st Sess.) Local cooperation. See page 32-17 of 1981 Annual Report for requirements of local cooperation. Formal assurances of local cooperation will be requested upon resolution of innovative financing discussions. Operations and results during fiscal year. New Work: Expenditure of $1,068 was attributed to in-house engineering efforts and continued coordination with local cooperator. 39. ELLICOTT CREEK, N.Y. Location. The proposed channel improvement is located on the downstream portion of Ellicott Creek in the towns of Amherst and Tonawanda, Erie County. (See Geological Survey maps of Tonawanda East and Buffalo Northeast, N.Y.) Existing project. For detailed description of the original project as authorized by Section 201 of the 1970 Flood Control Act, see page 32-24 of annual Report for 1973. The basic authorization, as modified by the Water Resources Development Act of 1974, provides authority to undertake flood control measures to alleviate flooding that is compatible with authorized project and any alternatives currently under restudy pursuant to Flood Control Act of 1970. As a result of restudy of alternatives, the project provides for: (a) widening, straightening and deepening about 2.5 miles of existing creek channel including the existing by-pass channel in Ellicott Creek Park; (b) construction of a diversion channel about 5,850 feet long between Maple Road and Millersport Highway; (c) construction of a diversion channel about 1,950 feet long through Pfohl Park; (d) construction of a diversion channel about 9,150 feet long from Niagara Falls Boulevard upstream to about Pfohl Park; (e) construction of 2 highway bridges; (f) modification of culverts at Tonawanda Creek Road; (g) foundation protection of 1 highway bridge; (h) modification of utilities and drainage outlets; and (i) recreation facilities consisting of a bike and hike path about 5.4 miles long, with open space park areas. The estimated Federal cost of existing project is $13,800,000 (Sept. 1984). The estimated non-Federal cost is $9,100,000 (Sept 1984). Completion of preconstruction planning and construction was authorized Dec. 29, 1981, under Section 5, P.L. 97-128. Local cooperation. For details of local cooperation see page 32-22 of Annual Report for 1976. On October 25, 1976, the New York State Department of Conservation furnished a letter of intent to cooperate toward construction of project. On June 22, 1983, a formal Local Cooperation Agreement was requested from N.Y. State. On January 20, 1984 this agreement was fully executed. Operations and results during fiscal year. New Work: A net credit of $239 was attributed to reimbursement of reproduction cost for the advance notice of the improvements to the diversion channel contract. 40. EUCLID CREEK, CLEVELAND, OH Location. Euclid Creek has a drainage area of approximately 25 square miles and is located east of Cleveland in Cuyahoga County and a small portion in Lake County, Ohio. Existing project. For details of existing project, see page 32-14 of the Annual Report for 1983. Local cooperation. For details of local cooperation requirements, see page 32-13 of Annual Report for 1984. Operations and results during fiscal year. New Work: Construction of project is 99% complete, with minor finishing details to be done. Contract cost in FY 85 amounted to $936,899. In-house engineering effort cost $55,680. 41. MT. MORRIS LAKE, N.Y. GENESEE RIVER Location. Dam is on Genesee River 66.9 miles above river mouth and about 3.2 miles southwesterly of Rochester, N.Y. Reservoir is in Livingston and Wyoming Counties, NN..YY.. ) (See Geological Survey maps of Nunda and Portage, Existing project.For description of existing project as authorized by 1944 Flood Control Act see page 1575 of Annual Report for 1962. New Work for completed project cost $23,365,559. In addition $5,000 contributed funds expended for new work. Local cooperation. None required. Local interests contributed $5,000 for new work. 32-14 BUFFALO, NY DISTRICT Operations and results during fiscal year. Operation and maintenance: Operation and ordinary maintenance of dam, reservoir, and service facilities, condition and operation studies and miscellaneous reports were accomplished by hired labor for $307,342. Contract for debris removal cost $229,550. Contract for repairs to roof of control house was completed at a cost of $8,246. Co-Operative Stream Gaging program accomplished by U.S. Geological Survey and National Weather Service reporting and hydroclimatic networks cost $69,445. Operation of the Water Control Center cost $196,628. Bank erosion study, by contract, cost $10,000. Engineering and design costs of $178,616 were incurred for the preparation of specifications for debris removal, annual facility inspection, dam safely study, seismic study by Waterways Experiment Station, and borings project. 42. OTTAWA, OHIO Location. Ottawa is located on the Blanchard River, approximately 22 miles upstream from its confluence with the Auglaize River. The Blanchard River drains about 765 square miles of the extreme southeastern corner of the Maumee River Basin which covers about 6,586 square miles in northwestern Ohio, northeastern Indiana, and southeastern Michigan. Existing project. ie .project is authorized by the Flood Control Act of November 7, 1966. The existing project, as recommended in the Preliminary Assessment Report dated July 1985, provides for: earth levees on both banks of the Blanchard River near the west side of the Village totalling 5,300 feet in length; about 2,500 feet of channel improvement work downstream of the Main Street bridge; snagging and clearing between the Grand Trunk Western bridge and Main Street bridge, and the installation of storm sewer check valves at about 190 homes. Estimated Federal cost of the project (Oct 85) is $952,000. Estimated non-Federal cost is $330,000 (Oct 85) including a cash contribution of $318,000. Local cooperation. The local sponsor, Maumee Watershed Conservancy District, will, prior to construction, enter into a binding w -itten agreement, which addresses project construction and satisfies the requirements of Section 221 of Public Law 91-611. The items of Local Cooperation listed in the Letter of Assurance are: (a) provide, without cost to the United States, all lands, easements, and rights-of-way necessary for the construction and subsequent maintenance of the project, as required; (b) hold and save the United States free from damages due to construction of the project except for damages due to the fault or negligence of the United States or its Contractors; (c) maintain and operate the project, or integral parts, after completion in accordance with regulations prescribed by the Secretary of the Army; (d) provide, without cost to the United States, all alterations and relocations of existing improvements including bridges, highways, buildings, utilities, sewers, and other facilities; (e) comply with applicable provisions of the "Uniform Relocation Assistance and Real Property Acquisition Policies Act of 1970," Public Law 91-646, approved January 2, 1971, in acquiring lands, easements, and rights-of-way for construction and subsequent maintenance of the project and inform affected persons of pertinent benefits, policies, and procedures in connection with the said Act; and (f) comply with Section 601 of Title VI of the Civil Rights Act of 1964 (PL 88-352) and Department of Defense Directive 5500.11 issued pursuant thereto and published in Part 300 of Title 32, Code of Federal Regulations, in connection with the construction and operation of the project Operations and results during fiscal year. New Work A Preliminary Assessment Report was completed and the Reevaluation Report was initiated at a cost of $105,113. 43. POINT PLACE, TOLEDO, OHIO Location. Point Place is located on a peninsula in northeast portion of city of Toledo, Ohio. Its shores are bounded on the east by Maumee Bay of Lake Erie and on the west by Ottawa River. The peninsula extends in a northeasterly direction immediately north of mouth of Maumee River. Existing project. The project provides for: (a) combination of protective structures consisting of 5,700 linear feet of steel sheet pile wall and 18,700 feet of levee; (b) three new pumping stations; and (c) 5,500 linear feet of new storm sewer facilities, including 2,400 linear feet of gravity outfalls. Estimated costs (Oct. 1984) are $9,620,000 Federal and $4,120,000 non-Federal including a cash contribution of $1,180,000. Existing project was authorized by 1972 Flood Control Act (H.D. 363, 92nd Cong., 2d sess.) Local cooperation. For details of local cooperation see pages 32-24 and -25 of Annual Report for 1978. The Local Cooperation Agreement was executed by city of Toledo on January 27, 1982. Operations and results during fiscal year. New Work: A contract for Stage 2c construction to complete 520 linear feet of concrete-faced sheetpile wall protection along the Ottawa River was awarded October 18, 1984. The entire project progressed to 95 percent completion. Total Federal costs for FY 85 were $3,435,112 contract costs, and $77,461 for inhouse engineering efforts. Non-Federal funds expended were $1,333,343 for contract costs and $74,900 for in-house engineering effort. 44. RENO BEACH - HOWARD FARMS AREA, OHIO Location. Area is located in Lucas County, on the south shore of Lake Erie about 15 miles east of Toledo, Ohio. Existing project The project, as authorized, provides for construction of 8,200 feet of roadway seawall, consisting of 32- 15 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 an earth dike, faced on the lakeward side with a quarry-run stone fill; and a steel sheet pile floodwall connecting the easterly end of this seawall at Wards Canal to the existing inland dike paralleling the canal. Estimated Federal cost of new work consisting of reconstructing to a permanent project the "Operation Foresight" work which was completed in 1973, is $6,790,000 (Oct. 1984). Non-Federal cost estimate of $2,260,000 (Oct. 1984) is a cash contribution toward first cost of construction plus all lands, easements, and rights-ofway. Project was authorized under Section 203 of the Flood Control Act of 1948. (H.D. 554, 80th Congress, 2nd Sess). Local cooperation. See page 32-16 of 1982 Annual Report for full requirements of local cooperation. A Local Cooperation Agreement will be requested upon approval of the General Design Memorandum. Operations and results during fiscal year. New Work: In FY 85 the General Design Memorandum was completed and Plans and Specifications initiated at a cost of $94,459 for inhouse engineering effort. Total costs including Construction, General, funds are $588,062. 45. SCAJAQUADA CREEK, N.Y. Location. Scajaquada Creek is a small stream draining to the Black Rock Canal and thence to Niagara River at Buffalo, New York. It flows from east to west and its drainage area is all in Erie County. About 65 percent of the watershed is upstream from the city of Buffalo, mostly in the towns of Cheektowaga and Lancaster, and the village of Depew. (See Geological Survey Maps of Buffalo-Northeast, N.Y. and Larcaster, N.Y.) Existing project. For description of existing project see page 32-23 of Annual Report for 1977. Estimated costs (Oct. 1980) are $5,065,000 Federal and $4,060,000 non-Federal. Existing project was authorized by Section 201 of 1965 Flood Control Act. The project was completed in August 1981. Local cooperation. Fully complied with. Operations and results during fiscal year. New work: FY 85 costs were $1,168 for in-house engineering effort. 46. INSPECTION OF COMPLETED FLOOD CONTROL PROJECTS Inspection of completed flood control works for compliance with Federal requirements were made during the period at a cost of $95,181. Total cost to Sept. 30, 1985 was $540,879. Inspection of non-Federal levees were made at a cost of $284. 47. NATIONAL EMERGENCY PREPAREDNESS FY 85 costs were $130,946. 48. OTHER AUTHORIZED FLOOD CONTROL PROJECTS See Table 32-F. 49. FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION See Table 32-G. 50. DEAUTHORIZED PROJECTS See Table 32-H. 51. SURVEYS During FY 1985, costs of $991,722 were incurred as shown below: Navigation Studies ........................... $494,578 Flood Damage Prevention Studies ............... 271,858 Shoreline Protection Studies...........................0 Special Studies..................................1,070 Miscellaneous Investigations ..................... 19,894 Coordination Studies.............................. 78,910 Phase I GDM Studies .......................... 26,076 Comprehensive Studies.......................... 99,336 52. COLLECTION AND STUDY OF BASIC DATA During the period, costs of $20,489 were incurred in connection with International Water Studies under the General Investigations appropriation and $344,391 incurred under the Operation and Maintenance appropriation for total costs of $364,880. Flood plain management services were performed during the year at a cost of $204,792. During the year, flood hazard evaluation studies were completed for the Sandusky River, in Tiffin, OH, Spring Brook, for the town of Concord and Village of Springville, New York, Kelsey and Cold Creeks in the City of Watertown and towns of Watertown and Pamelia, N.Y., Owasco Inlet, in the village of Groton, N.Y. and Cazenovia Creek in the town of Aurora, N.Y. A preliminary flood hazard evaluation study was presented to the village of South Russell in September. The study will be finalized in the first quarter of FY 1986. Costs for general hydrologic studies were $2,236. 53. ADVANCE ENGINEERING AND DESIGN Costs during the period were $231,539 for advance engineering and design projects. For details of individual projects, see sections I 1, 42 and 44 in text. 54. CONTINUATION OF PLANNING AND ENGINEERING Costs during the period were $240,241 for continuation of planning and engineering. For details of individual project, see section 34 in text. 32- 16 BUFFALO, NY DISTRICT TABLE 32-A COST AND FINANCIAL STATEMENT See Section in Funding FY 82 FY 83 FY 84 FY 85 Total Cost to Text Project Sept 30, 1985 1. Ashtabula Harbor, Ohio 2. Barcelona Harbor, N.Y. (Federal Funds) (Contrib. Funds) 3. Black Rock Channel and Tonawanda Harbor, N.Y. (Federal Funds) (Contrib. Funds) 4. Buffalo Harbor, N.Y. 5. Cattaraugus Harbor, N.Y. (Federal Funds) (Contrib. Funds) 6. Cleveland Harbor Ohio New Work Approp. Cost Maint. Approp. Cost Rehab. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Contrib. Cost New Work Approp. Cost Maint. Approp. Cost New Work Contrib. Cost New Work Approp. Cost Maint. Approp. Cost Rehab. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Contrib. Cost New Work Approp. Cost Maint Approp. Cost Rehab. Approp. Cost - - - - 12,805,339' - - - - 12,805,339' 112,000 770,000 253,762 732,518 9,550,946 34,614 673,834 435,196 757,638 9,509,979 2,512,000 2,357,273 100,000 55,760 -3,239 232,168 1,430,042 11,087 105,051 1,488,727 - - 174,000 - - 15,000 - - - - 6,077,000 - 6,077,000 - 1,185,8532 - 1,185,8532 -103,189 1,921,187 -34,757 1,921,187 159,000 310,000 310,000 174,000 174,000 10,825,1203 10,825,1203 1,408,000 1,065,000 1,502,215 2,423,821 30,865,384' 1,624,585 820,815 1,688,268 2,463,803 30,823,1534 - - - 620,000 620,000 - - - 250,000 250,000 - - - - 23,115,1875 - - - - 23,115,1875 3,042,000 470,000 980,715 2,222,000 49,489,5156 2,452,622 1,033,360 947,421 2,043,936 49,238,2416 - - - - 295,457 - - - - 295,457 3,050,000 951,560 -197,000 3,217,467 954,186 -192,556 - - 956 - - 956 - 192,500 50,029 - - 242,593 - 4,804,060 422 4,803,903 1,425 1,425 2,381 2,381 - 2,566,529 - 2,566,529 15,000 31,668,299' - 31,653,299' 5,067,801 6,169,500 4,472,125 2,942,000 136,296,485' 4,777,586 4,477,275 6,057,166 3,265,105 136,189,536' 16,967 9,492 - 2,915,000 13,209,903 - 2,109,110 12,404,013 32- 17 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 32-A (Continued) COST AND FINANCIAL STATEMENT See Section in Funding FY 82 FY 83 FY 84 FY 85 Total Cost to Text. Project Sept 30, 1985 7. Conneaut Harbor, Ohio 8. Dunkirk Harbor, N.Y. (Federal Funds) (Contrib. Funds) 9. Erie Harbor, Pa. 10. Fairport Harbor, 11. Geneva-on-the-Lake, Ohio 12. Great Sodus Bay Harbor, N.Y. 13. Huron Harbor Ohio (Federal Funds) New Work Approp. Cost Maint. Approp. Cost Rehab. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Contrib. Cost New Work Approp. Cost Maint. Approp. Cost Rehab. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost New Work Approp. Cost Maint. Approp. Cost Rehab. Approp. Cost New Work Approp. Cost Maint. Approp. Cost Rehab. Approp. Cost - 8,346,6419 - 8,346,6419 630,000 1,165,000 901,700 604,527 1,074,711 979,729 54,000 8,734,10210 97,511 8,724,88910 - 651,850 - 651,850 - 3,010,0241" - 3,010,024" 5,439 229,335 8,633 216,150 190,000 187,272 :- 2,588,000 332,770 11,161 20,124 72,944 2,020,193 9,338 1,677,775 13,523 1,677,738 - 1,950,00012 - 1,950,00012 - 3,597,87313 - 3,597,87313 -12,685 14,493,57014 301,108 14,493,570'14 - - - - 1,154 - - - - 1,154 - - - - 2,959,61115 - - - - 2,959,61115 580,000 675,500 692,469 760,500 12,770,672 604,849 595,053 783,369 764,300 12,768,663 18,595 184 639 - 15,000 677,000 - - 662,000 - - 610,95916 - - 610,95916 - 10,925 - 7,500 706 2,366,903 4,131 2,366,903 - 713,544 - 713,544 - - - - 5,103,795" - - - - 5,103,795" 660,000 447,000 1,047,523 465,000 14,226,926 633,426 444,078 996,446 530,980 14,209,976 - - - - 247,030 - - - - 247,030 32- 18 BUFFALO, NY DISTRICT TABLE 32-A (Continued) COST AND FINANCIAL STATEMENT See Section in Funding FY 82 FY 83 FY 84 FY 85 Total Cost to Text Project Sept. 30, 1985 (Contrib. Funds) 14. Irondequoit Bay N.Y. (Federal Funds) (Contrib. Funds) 15. Little Sodus Bay Harbor, N.Y. 16. Lorain Harbor, Ohio 17. Oak Orchard Harbor, N.Y. 18. Ogdensburg Harbor, N.Y. (Federal Funds) (Contrib. Funds) 19. Olcott Harbor N.Y. 20. Oswego Harbor, N.Y. New Work Contrib. Cost New Work Approp. Cost New Work Contrib. Cost New Work Approp. Cost Maint. Approp. Cost Rehab. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Contrib. Cost New Work Approp. Cost Maint. Approp. Cost Rehab. Approp. Cost New Work Approp. Cost Maint. Approp. Cost - 63,079 - 63,079 125,000 113,752 135,800 1,060,000 1,450,000 3,510,800 65,534 838,951 1,747,319 3,503,936 - 1,200,000 - 7,637 4,004 - 12,289 - 1,308 - 1,200,000 788,368 796,005 - 301,394"8 - 301,39418 62 3,044,569 11,043 3,044,569 - 742,822 - 742,822 - 20,739,558"19 59 - 20,739,558"19 1,004,000 1,397,000 1,421,000 906,000 22,112,429 1,005,970 1,377,008 1,271,705 1,064,095 22,098,058 - - - - 1,586,99620 - - - - 1,586,99620 849 2,590 - 1,436 135,076 - 1,436 24,062 - 924,000 - 47,211 6,424 23,818 788 1,017 - 35,000 - - 217,235 106,116 - 150,000 1,720,4661 317,647 703,736 1,715,06021 - 3,801 1,330,18422 - 3,801 1,330,18422 22,000 50,585 6,205 57,000 56,790 - 140,21023 - 140,21023 - 76,804 15,867 - 69,019 620,000 559,000 115,000 625,113 558,442 111,237 538,71224 530,92724 - - 14,4772s - 14,47725 - 8,430,01626 - 8,430,01626 7,000 5,969,815275 16,576 5,969,81527 32- 19 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 32-A (Continued) COST AND FINANCIAL STATEMENT See Section in Funding FY 82 FY 83 FY 84 FY 85 Total Cost to Text Project Sept 30, 1985 21. Port Clinton, Ohio 22. Port Ontario Harbor, N.Y. 23. Rochester Harbor, N.Y. 24. Rocky River, Ohio 25. Sandusky Harbor, Ohio 26. Toledo Harbor, Ohio 27. Vermilion Harbor, Ohio 28. West Harbor, Ohio (Federal Funds) Rehab. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost Rehab. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost Rehab. Approp. Cost New Work Approp. Cost Maint Approp. Cost 307,590 - 307,590 - 71,950 - 71,950 260,000 120,005 64,694 26,781 236,517, 173,630 3,845 12,245 - 10,000 161 - - 909,869 909,869 820,00028 810,00028 - 2,439,30829 - 2,439,30829 595,000 1,721,000 1,795,000 598,867 1,106,232 2,069,140 98,000 14,814,81630 422,623 14,793,17330 - 343,494 - 343,494 4,208 12,584 6,298 7,237 25,004 628,768 2,227,085 14,432 397,652 1,985,397 - - - - 6,727,27031 - - - - 6,727,2703' 525,000 919,000 716,240 909,000 12,872,439 518,185 916,506 683,523 956,276 12,872,284 - - - - 675,606 - - - - 675,606 - - - - 17,191,84232 - - - - 17,191,84232 4,315,000 3,482,500 4,586,188 3,999,000 70,487,053"3 4,101,546 3,540,127 4,037,727 4,632,667 70,404,710"33 - - - - 1,156,11834 - - - - 1,156,11834 42,404 51,950 - 17,839 543,670 1,952,122 - 17,839 502,128 1,910,580 1,840,000 318,898 1,838,914 319,694 -90,000 -88,787 20,364 - 20,364 - 139,775 - 139,775 - 3.303.898 1,071 3,303,898 14,739 35,103 14,739 35,103 32- 20 BUFFALO, NY DISTRICT TABLE 32-A (Continued) COST AND FINANCIAL STATEMENT See Section in Funding FY 82 FY 83 FY 84 FY 85 Total Cost to Text Project Sept. 30, 1985 (Contrib. Funds) 29. Wilson Harbor N.Y. 33. Lakeview Park, Lorain, Ohio (Federal Funds) (Contrib. Funds) 34. Presque Isle Peninsula, Erie, Pa. (Federal Funds) (Contrib. Funds) 36. Lakeshore Park Ashtabula, Ohio (Federal Funds) (Contrib. Funds) 37. Cuyahoga River Basin, Ohio 38. Dansville and Vicinity, Canaseraga Creek, N.Y. 39. Ellicott Creek, N.Y. 40. Euclid Creek OH 41. Mt. Morris Lake, N.Y. Genesee River 43. Point Place, Toledo, Ohio (Federal Funds) (Contrib. Funds) New Work Contrib. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost New Work Contrib. Cost New Work Approp. Cost Maint. Approp. Cost New Work Contrib. Cost New Work Approp. Cost New Work Contrib. Cost New Work Approp. Cost New Work Approp. Cost New Work Approp. Cost New Work Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost New Work Contrib. Cost - 628,000 - 486,266 45 12,048 54,655 61,797 141,747 - 3,795,000 - 3,795,000 _ 535,24631 _ 535,246" 265,885 S 264,586 22,737 25,000 7,108 485,556'36 484,25736 - 1,741,125 24,927 1,741,052 - 10,700 - 9,239 739,700 738,239 1,000,000 740,000 990,000 1,160,000 11,585,562 994,477 741,242 426,294 1,708,859 11,566,421 - 1,092 - 1,092 428,571 368,175 429,914 307,785 410,000 404,205 262,000 150,337 50,000 81,750 13,355 150,000 116,912 195,000 199,957 81,438 10,000 17,903 25,000 16,053 61,000 73,709 140,000 2,220,000 100,497 78,324 44 44 4,978 4,978 373,254 497,143 5,308,569 1,656 870,230 5,249,666 939 3,187 3,163 9,659 21,494 -2,808 -12,293 14,745 786,844 784,036 249,707 249,707 - 1,117,000 508 1,117,000 1,067 490,300 490,300 15,000 1,895,000 -239 1,878,847 - 390,000 3,162,000 1,541,480 992,579 3,113,294 - 23,365,55937 - 23,365,55937 905,000 1,035,000 965,000 856,000 919,439 784,649 1,042,141 999,826 9,901,309 9,849,649 800,000 2,300,000 2,000,000 3,500,000 9,799,000 587,705 1,348,602 3,149,683 3,512,573 9,796,069 - 300,000 690,000 740,000 1,730,000 - 15,150 290,895 1,408,243 1,714,288 32- 21 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 32-A (Continued) COST AND FINANCIAL STATEMENT See Section in Funding FY 82 FY 83 FY 84 FY 85 Total Cost to Text Project Sept. 30, 1985 45. Scajaquada Cr., New Work N.Y. Approp. 40,345 -30,800 - - 4,944,852 Cost 92,343 -6,831 88 1,168 4,944,852 1. Includes $565,192 for previous projects. Excludes $47,000 16. Includes $361,772 for previous projects. contributed funds. 17. Includes $269,789 for previous projects. 2. Includes $56,616 for previous projects. Excludes $7,500 18. Includes $232,328 for previous projects. contributed funds. 19. Includes $292,203 for new work for previous projects. 3. Includes $58,027 for previous projects. Excludes $3,000 contributed funds. Also excludes appro- 4. Includes $4,922 emergency relief authority administrative priation and cost of $29,570 under authority of Section 107, costs transferred from new work to maintenance upon 1960 R&H Act. conversion to programming and budgeting system July 1, 20. Excludes $224,702 contributed funds. 1953, by direction of Office, Chief of Engineers. Also includes 21. Includes $271,380 for previous projects. appropriations and costs under appropriation titles 96x3123 22. Includes $130,512 for previous projects. Operation and Maintenance and 96x5125 Maintenance and 23. Includes $140,210 for previous projects. Excludes $1,500 Operation of Dams and Other Improvements of Navigable contributed funds. Waters. 24. Includes $38,959 for previous projects. Excludes $5,000 5. Includes $4,277,586 for previous projects. Excludes ex- contributed funds. penditures of $239,305 for work authorized by Section 107. 25. Excludes $186,000 Public Works Acceleration Act. 6. Includes $1,883,647 for previous projects. Excludes 26. Includes $1,187,977 for previous projects. $446,805 contributed funds. 27. Includes $945,684 for previous projects. 7. Includes $1,564,154 for previous project and appropriations 28. Includes $50,000 for previous projects. and costs of $16,596 for modification authorized for con- 29. Includes $247,794 for previous projects. struction under authority of Sec. 107, 1960 R&H Act. 30. Includes $617,529 for previous projects and $478 emergency 8. Includes appropriations and costs under appropriation titles relief authority administration costs transferred from new 96x3123 Operations and Maintenance and 96x5125 Maint- work to maintenance upon conversion to programming and tenance and Operation of Dams and Other Improvements of budgeting system, July 1, 1953, by direction of Office, Chief Navigable Waters. Excludes $201,960 contributed funds. of Engineers. 9. Includes $805,272 for previous projects. 31. Includes $477,149 for previous projects. Excludes $325,000 10. Includes $39,784 for previous projects. contributed funds. 11. Includes $811,250 for previous projects. Excludes $11,000 32. Includes $1,624,695 for previous projects. contributed funds. 33. Includes $16,914 for previous projects. 12. Includes $176,520 for previous projects. 34. Excludes $740,679 contributed funds. 13. Includes $736,967 for previous projects. 35. Includes $57,342 for previous projects. Excludes $166,998 14. Includes $104,900 for previous projects. Excludes $154,500 contributed funds. contributed funds. 36. Includes $16,914 for previous projects. 15. Includes $368,940 for previous projects. 37. Excludes $5,000 contributed funds. 32- 22 BUFFALO, NY DISTRICT TABLE 32-B AUTHORIZING LEGISLATION Acts Work Authorized Documents ASHTABULA HARBOR, OHIO (See Section 1 of Text) June 3, 1896 Mar. 3, 1905 June 25, 1910 Mar. 2, 1919 Aug. 30, 1935 Aug. 26, 1937 Mar. 2, 1945 Sept. 3, 1954 July 14, 1960 Oct. 27, 1965 Aug. 11, 1888 June 3, 1896 June 13, 1902 June 13, 1902 Aug. 8, 1917 Mar. 3, 1905 July 27, 1916 Mar. 2, 1919 Mar. 2, 1945 Construction of breakwater. Annual Report, 1895, p. 2132. Enlarge outer harbor by extending west breakwater and constructing new east breakwater; pierheads on lakeward ends of breakwaters; and remove part of old east breakwater. Extend west breakwater to shore; dredge outer harbor to a depth of 20 feet. Remove portion of east breakwater, extend breakwaters to present project dimensions and dredging restrictions in portion of west basin. Dredge channel through outer harbor, channel of approach to Penn Central Co. slip, channel Ashtabula River, to and in turning basin all to present project dimensions; remove portion of old east inner breakwater and maintenance to 24-foot depth of portion of outer harbor. Extend river channel to present project limit. Dredging approach channel and turning basin in east outerharbor to 25-foot depth. A depth of 29 feet in soft and 30 feet in hard material in entrance channel to just inside outer ends of breakwaters; thence 28 feet in soft and 29 feet in hard material in a channel to inner breakwater, thence 27 feet in soft and 28 feet in hard material in a channel extending to Penn Central Co. slip and extending 2000 feet up Ashtabula River; 22 feet in hard material in turning area; and 28 feet in soft and 29 feet in hard material in areas adjacent to 250-foot section of inner breakwater when that section is removed as now authorized Dredging approach, channel and turning basin in east outer harbor to 28 feet in soft material and 29 feet in hard material. BLACK ROCK CHANNEL AND TONAWANDA HARBOR, N.Y. (See Section 3 of Text) Dredging channel through Horseshoe Reef at outlet of Lake Erie and Tonawanda Inner Harbor, to 16 feet. Deepening Tonawanda Creek to 16 feet. Dredging channel from Buffalo outer harbor to foot of Maryland St., Buffalo, to 21 feet. Dredging channel from foot of Maryland St., Buffalo, to natural deepwater pool upstream from Tonawanda Harbor to 21 feet; construction of ship lock and bridge; and repair of Bird Island pier and towpath wall. Dredging channel along Tonawanda Island, with turning basin at its downstream end at the foot of the Island, to 21 feet. Dredging triangular area at junction with Buffalo north entrance channel. H. Doc. 654,61st Cong., 2d sess. H. Doc. 997, 64th Cong., I st sess. H. Doc. 43, 73rd Cong., 1st sess. Rivers and Harbors Committee Doc. 78, 74th Cong., 2d sess. H. Doc. 321, 77th Cong., I1st sess. H. Doc. 486, 83d Cong., 2d sess. H. Doc. 149, 86th Cong., I st sess. H. Doc. 269, 89th Cong., I st sess. 4 H. Ex. Doc. 83, 50th Cong., Ist sess. Annual Report, 1888, p. 2066, and Annual Report, 1897, pp. 3116-3120. H. Doc. 143, 56th Cong., 1st sess., and Annual Report, 1900 p. 4152. H. Doc. 125, 56th Cong., 2d sess., and Annual Report, 1901, p. 3343. H. Doc. 428, 58th Cong., 2d sess. H. Doc. 658, 63rd Cong., 2d sess. H. Doc. 1004, 65th Cong., 2d sess, and H. Doc. 92,79th Cong., I1st sess. 32 - 23 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 32-B (Continued) AUTHORIZING LEGISLATION Acts Work Authorized Documents Sept. 22, 1922 Mar. 3, 1925 June 26, 19341 Aug. 30, 19356 Mar. 2, 1945 Sept. 3, 1954 May 20, 1826 June 23, 1866 June 23, 1874 June 3, 1896 Mar. 3, 1899 Mar. 3, 1909 June 6, 1900 June 13, 1902 Mar. 2, 1907 Mar. 2, 190710 June 25, 1910 July 25, 1912 Mar, 2, 1919 Jan. 21, 1927 July 3, 1930 Aug. 30, 1935" Aug. 30, 1935 Mar. 2, 1945" Widening channel at foot of Maryland St., Buffalo. Widening canal south of International Bridge and removal of westerly end of Rattlesnake Island shoal. Operation and care of improvements provided for with funds from War Department appropriations for rivers and harbors. Removal of rock shoals in Lake Erie entrance to canal, and in canal south of Ferry Street Bridge, to 22 feet; enlargement of North Tonawanda turning basin; extension of Bird Island pier; improvement of guide pier at the lock; and elimination of upper 150 feet of Tonawanda Creek channel from the project.' Widening Lake Erie entrance to canal. Deepen lower 1,500 feet of Tonawanda inner harbor and enlarge turning basin. BUFFALO HARBOR, N.Y. (See Section 4 of Text) Construction of south pier (extended in 1868)' Construction of old breakwater.'9 Extension of old breakwater.9 Stony Point and south breakwater.'9 North breakwater.9 Deepening entrance channel to inner harbor and removing rock shoal therein. Dredging at entrance to canals at South Buffalo in outer harbor.' South entrance breakwater.'9 Extension of Federal project to Commercial St. and removal of Watson elevator site.'9 Deepening areas A, B, and D in outer harbor to 21 feet, and area C in north entrance to 23 feet. Deepening areas F and G in outer harbor to 21 feet. Removal of shoal between entrance channel to Buffalo River and Erie Basin to 21 feet. Deepening areas H, I, and K in outer harbor to 21 feet. Extension of south entrance and south breakwaters, deepening outer harbor to present project dimensions, and removal of shoals on approach to south entrance. Maintenance of channels in Buffalo River and Buffalo ship canal to 21 feet in cooperation with city of Buffalo. Deepening North and Buffalo River entrance channels, and deepening and maintaining Buffalo River and Buffalo ship canal to present project dimensions. H. Doc. 981, 66th Cong., 3d sess. H. Doc. 289, 68th Cong., I st sess. H. Doc. 28, 73d Cong., 1st sess. H. Doc. 92, 79th Cong., Ist sess.4 H. Doc. 423 83d Cong., 2nd Sess. 4 ' Annual Report, 1868, pp. 222 and 232. Annual Report, 1868, pp. 232-236. Annual Report, 1876, pt. 2, pp. 569 and 573. Annual Report, 1895, p. 3153. H. Doc. 72, 55th Cong., 1 st sess., and Annual Report, 1897, p. 3245. Specified in acts. Specified in act. H. Doc. 240, 59th Cong., Ist sess. H. Doc. 298, Rivers and Harbors Committee Doc. 2, 61st Cong., 2d sess. H. Doc. 550, 62d Cong., 2d sess. H. Doc. 1139, 64th Cong., I st sess. H. Doc. 481, 68th Cong., 2d sess. Rivers and Harbors Committee Doc. l, 71st Cong., Ist sess. H. Doc. 46, 73d Cong., I st sess. Rivers and Harbors Committee Doc. 54, 74th Cong., Ist sess. H. Doc. 352, 78th Cong., Ist sess. 32- 24 BUFFALO, NY DISTRICT TABLE 32-B (Continued) AUTHORIZING LEGISLATION Acts Work Authorized Documents July 14, 1960 Oct. 23, 1962 Dec. 15, 1980 Mar. 3, 1875 Aug. 5, 1886 Aug. 11, 1888 June 3, 1896 Mar. 3, 1899 June 13, 1902 June 13, 1902 Mar. 2, 1907 June 25, 1910 July 27, 1916 Aug. 8, 1917 Aug. 29, 1937 Aug. 30, 193512 Aug. 30, 1935"1 Deepening approach to south entrance channel to 30 feet; deepen to 30 feet in outer area and 29 feet in inner area of south entrance channel; and deepen to 28 feet southerly part of outer harbor. Deepening portion of outer harbor to 27 feet over a width of 500 feet for 2,500 feet northward from 28-foot project area, widening within 1,700 feet to limits within 150 feet of breakwater axis and 75 feet from harbor line and continuing within these limits for 7,000 feet. Elimination of 25-foot wide strip between presently authorized and proposed easterly dredging limits. Elimination of easterly 50-foot wide undredged strip in existing 23-foot depth project area, extending northerly from 27-foot depth area to Buffalo River entrance channel. Previously authorized but uncompleted portions of work authorized by 1935 act, combined with this act as a single improvement. Removal of abandoned abutments of South Michigan Avenue bridge. CLEVELAND HARBOR, OHIO (See Section 6 of Text) West breakwater Part of east breakwater.'9 Extension of east breakwater. 9 Reconstruction of piers.'9 Dredging channel between piers and outer harbor to depth of 19 feet; dredging to depth of 23 feet in any portion of harbor in discretion of Secretary of War. Arrowhead breakwater and extension of east breakwater. Removal of deflecting arm of old east breakwater and closure of gap between old and new east breakwaters. Pierhead at easterly end of east breakwater. Maintenance and improvement of channels in Cuyahoga and Old Rivers to a depth of 21 feet to a point 2,000 feet upstream from Clark Ave. viaduct and 18-foot turning basin. Deepening outer harbor and channel between piers to present project dimensions, construction of 400-foot spur breakwater at gap in shore arm of west breakwater; removal of easterly 150 feet of west main breakwater; elimination from project of a 298-foot southerly extension of west pier, and abandonment of inner 932 feet of shore arm of west breakwater. Maintenance dredging in Cuyahoga and Old Rivers for 1 year as an emergency measure. H. Doc. 151, 86th Cong., I1st sess. H. Doc., 451, 87th Cong., 2d sess. Section 107, 1960 River and Harbor Act. Annual Report, 1876, p. 558. H. Ex. Doc. 116, 48th Cong., 2d sess., and Annual Report, 1886, p. 1865. H. Ex. Doc, 189, 50th Cong., 2st sess., and Annual Report, 1888, p. 2005. H. Doc. 326, 54th Cong., 1st. sess., and Annual Report, 1896, p. 2949. H. Doc. 156, 55th Cong., 3d sess., and Annual Report, 1899, pp. 3075 and 3078. H. Doc. 118, 56th Cong., 2d sess. No printed report. H. Doc. 891, 63d Cong., 2d sess. H. Doc. 707, 63d Cong., 2d sess., and Rivers and Harbors Committee Doc. 84, 74th Cong., 2d sess. H. Doc. 477, 72d Cong., 2d sess. Rivers and Harbors Committee Doc. 39. 74th Cong., Ist sess. 32- 25 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 32-B (Continued) AUTHORIZING LEGISLATION Acts Work Authorized Documents Mar. 2, 1945"4 July 24, 1946 July 3, 1958 July 14, 1960 Oct. 23, 1962 Dec. 6, 1966 Oct. 22, 1976 (Sec. 175) June 25, 1910 Aug. 8, 1917 S7 Aug. 30, 1935" Maintenance of extension of Cuyahoga River channel. Extension, maintenance, and improvement to a depth of 21 feet of Cuyahoga River channel to present project limit. 1"'1 Improvement of Cuyahoga and Old Rivers to a depth of 23 feet and replacement or pier construction of 7 railroad bridges.2 Deepening channel 25 feet through east basin of outer harbor; replacement of Erie-Lackawanna Railroad bridge over Cuyahoga River at mile 4.1 and widening of channel at that point, with elimination of reconstruction of east pier of bridge as previously authorized; and replacement of Baltimore & Ohio Railroad Bridge over Old River near its mouth and Willow Avenue Highway Bridge about 800 feet above mouth and widening channel at four locations along lower 2,000 feet of river.' Depth of 29 feet in lake approach to main entrance; 28 feet in entrance channel to lakeward ends of piers at mouth of Cuyahoga River; 27 feet in river to a point just above its junction with Old River, and in Old River to upstream limit of present 23- foot project; 28 feet in west basin within existing project limits as modified to eliminate a triangular area at west end and to extend limits to a line parallel to and75 feet from harbor line; and 28 feet in westerly 800 feet of east basin." An area in east basin 27 feet deep extending about 3,800 feet easterly of 28-foot area with project limits 380 feet from east breakwater and on landward side generally by a line 75 feet lakeward of and parallel to harbor line. A dock channel to Nicholson Cleveland Terminal Co. pier, at easterly end of east basin, from 25-foot contour to a limit 75 feet north of pierhead line, 400 feet wide at shoreward end and flared toward the lake. Deepening upper end of Old River channel from 21 to 27 feet. Preparation of Phase I design memorandum for improvements consisting of removal of portions of entrance breakwater: construction of breakwater extension of east entrance; deepening approach and entrance channels; construction of diked disposal area; and, installation of recreational fishing facilities on west breakwater. CONNEAUT HARBOR, OHIO (See Section 7 of Text) Extension of east breakwater, construction of new west breakwater removal of portion of old west breakwater, and dredging of outer harbor to 19 feet. Realinement of west breakwater, removal of remainder of old west breakwater, and deepening outer harbor to 20 feet. Removal of Bessemer & Lake Erie R.R. Co. of inner 635 feet of west pier. Removal of a portion of west breakwater, extension of breakwaters to present project dimensions; construction of pierheads on outer ends of breakwaters; deepening outer harbor to present project dimensions; removal of portions of river pier, and elimination from project of a 255-foot shoreward extension of west breakwater. Specified in act. H. Doc. 95, 79th Cong., I1st sess. H. Doc. 629, 79th Cong., 2 d sess. H. Doc. 107, 85th Cong., Ist sess. H. Doc. 152, 86th Cong., I1st sess. H. Doc. 527, 87th Cong., 2d sess.4 Sec. 107, 1960 River and Harbor Act. H. Doc. 653, 61st Cong., 2d sess. H. Doc. 983, 64th Cong., I1st sess. H. Doc. 48, 73d Cong., 1st sess. 32 - 26 BUFFALO, NY DISTRICT TABLE 32-B (Continued) AUTHORIZING LEGISLATION Acts Work Authorized Documents Oct. 23, 1962 Nov. 7, 1966' Mar. 2, 1827 Mar. 2, 1867 June 3, 1896 June 25, 1910 June 30, 1948 Dec. 15, 1970 (House Public Works Comm.) June 22, 1971 (Senate Public Works Comm.) Sec. 201 of F.C. Act of 1965 May 26, 1824 Mar. 3, 1899 June 15, 1910 Nov. 28, 192220 Aug. 30, 1935 Deepening easterly part of outer harbor to 28 feet in soft material and 29 feet in hard material; deepening remaining triangular area of outer harbor to 22 feet in soft material and 23 feet in hard material; deepening inner harbor for 2,450 feet upstream of outer end of west pier to 27 feet in soft material and 28 feet in hard material; removal of east pier, extension of east breakwater to shore; and an access channel 8 feet deep in outer harbor to city dock. Previously authorized but uncompleted portion of work authorized by 1917 and 1935 acts combined with this act for accomplishment as a single improvement. Recreational small-boat harbor provided by: a stone dike about 2,200 feet long; access channels 6 feet deep, 2,800 feet long and 100 feet wide; closing of 100-foot gap in existing west breakwater, and personnel guard rail on west breakwater. DUNKIRK HARBOR, N.Y. (See Section 8 of Text) Construction of west pier." ' Breakwater and excavation of entrance channel to 13 feet. Deepening of entrance channel and harbor basin to a depth suitable for vessels of 16-foot draft. Removal of rock reef bordering the inner entrance channel. Deepening outer entrance channel to present project depths; removal of rock shoal on the west side of the entrance channel to a depth of 17 feet, and changed limits of the inner entrance channel and basin to present project dimensions. Construction of small boat harbor. ERIE HARBOR, PA. (See Section 9 of Text) Breakwaters and piers; dredging entrance channel; and brushwood protection of beach of Presque Isle Peninsula.' Deepening channel and harbor basin to 18 feet; repair and extension of piers; and plant growth and emergency protection work on peninsula. Deepening channel and part of harbor to 20 feet. Reconveyed Presque Isle Peninsula to the State of Pennsylvania for park purposes. Deepening, widening, and straightening entrance channel, dredging channel at easterly end of harbor basin, deepening a portion of harbor basin, all to present project dimensions; elimination of north breakwater from project; and limitation of south breakwater to a length of 1,200 feet. H. Doc. 415, 87th Cong., 2d sess. H. Doc 484, 89th Cong., 2d sess.' S. Ex. Doc. 42, 35th Cong., Ist sess., and Annual Report, 1866 pt. IV, p. 155 Annual Report, 1871 p. 214. H. Doc. 63, 54th Cong., Ist sess. H. Doc. 720, 61st Cong., 2d sess.' H. Doc. 632, 80th Cong., 2d sess. H. Doc. 91-423, 91st Cong., 2d sess. Annual Report, 1915, p. 1965. H. Doc. 70, 55th Cong., Ist sess. and Annual Report, 1896, p. 3237."9 Rivers and Harbors Committee Doc. 26, 61st Cong., 2d sess. H. Doc. 52, 73d Cong., 1 st sess. 32- 27 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 32-B (Continued) AUTHORIZING LEGISLATION Acts Work Authorized Documents Mar. 2, 1945 Sept. 3, 1954 July 14, 1960 Oct. 23, 1962 Mar. 3, 182521 June 3, 1896 Mar. 3, 1905 Mar. 2, 1919 Jan. 21, 1927 July 3, 1930 Aug. 30, 193522 Aug. 26, 1937 July 24, 1946 July 14, 196030 May 10, 1977 (House Public Works Comm.) Oct. 1, 1976 (Senate Public Works Comm.) Sec. 201 of F.C. Protection of the peninsula south of the waterworks settling basin. Widen 25-foot deep approach channel to ore dock. Depth of 29 feet in the entrance channel to a point opposite the inner end of the north pier; thence 28 feet in soft and 29 feet in hard material in the remainder of the entrance channel, within the general limits of the 25-foot basin and inner channel opposite the ore dock except as modified to eliminate from the project a triangular area along the easterly side; and a depth of 28 feet over a 300-foot westward extension of the 25-foot basin29 Depth of 27 feet in soft material and 28 feet in hard material in approach area to Duquesne Marine Terminal. Previously authorized but uncompleted portion of work authorized by 1935 act is combined with this act as a single improvement. FAIRPORT HARBOR, OHIO (See Section 10 of Text) Construction of piers. Breakwaters and dredging outer harbor to a depth of 18 feet. 1,400-foot extension of east breakwater, present project dimension of east pier; and deepening of harbor to 19 feet. 4,000-foot extension of east breakwater at limit of cost to the United States of $715,000. Deepening of outer harbor and entrance channel to present project dimensions; extending the west breakwater to present project dimensions with pierhead at its outer end; removal of west pier; and construction of bulkhead on west side of river channel. Dredging of 21-and 24-foot river channels and turning basin in Grand River to present project dimensions. Dredging of 8-foot river channel. Depth of 29 feet in the approach channel from the lake; a depth of 28 feet over a width of 800 feet in the outer harbor; a depth of 27 feet in soft and 28 feet in hard material in Grand River, over a width of 200 feet to the upstream limit of the turning basin, with suitable widening at the bends, thence over widths reducing from 200 to 100 feet to the upstream limit of the existing Federal project, except in the 8-foot channel; enlargement of the turning basin, including deepening of the entire basin to 21 feet; and minor modification of the existing project limits in the outer harbor. Construction of small boat harbor. Specified in act. H. Doc. 345, 83d Cong., 2d sess. H. Doc. 199, 86th Cong., Ist sess. 4 H. Doc. 340, 87th Cong., 2d sess.4 Annual Report, 1889, pp. 2147-2153 H. Doc. 347, 54th Cong., 1st sess. and Annual Reports, 1896,p. 2956; 1903, p. 2084; 1905, p. 2349. H. Doc. 206, 63d Cong., 1st sess. H. Doc. 592, 69th Cong., 2d sess., Rivers and Harbors Committee Doc. 13, 70th Cong., 1st sess. H. Doc. 472, 72d Cong., 2d sess. Rivers and Harbors Committee Doc. 79, 74th Cong., 2d sess.4 H. Doc. 706, 79th Cong., 2d sess.4 H. Doc. 347, 86th Cong., 2d sess.4 H. Doc. 627, 94th Cong., 2d. sess. 32- 28 BUFFALO, NY DISTRICT TABLE 32-B (Continued) AUTHORIZING LEGISLATION Acts Work Authorized Documents Act of 1965 Mar. 2, 1829 Aug. 2, 1882 Mar. 3, 1925 July 3, 1930 Aug. 30, 1935 Mar. 2, 1905 Mar. 2, 1919 Aug. 30, 193522 Oct. 23, 1962 Aug. 30 1852 June 23, 1866 Mar. 3, 1871 Mar. 3, 1881 June 13, 1902 Mar. 3, 1899 Mar. 2, 1907 June 25, 1910 GREAT SODUS BAY HARBOR, N.Y. (See Section 12 of Text) Construction of piers and breakwater.' Extension of piers to 15-foot contour in the lake. Deepening and widening of channel to 18-foot depth and 150-foot width. Widening channel lakeward of piers to 250 feet. Dredging channel to present project dimensions. HURON HARBOR, OHIO (See Section 13 of Text) Extension of west pier, construction of east breakwater, removal of part of old east pier, deepening of channel to 19 feet; and dredging of sheltered area. Widening river to 200 feet; removal of remainder of old east pier; construction of new spur pier; enlargement of sheltered area; and closure of breach at shore end of west pier. Extension of west pier with pierhead at its outer end; removal of outer end of east breakwater and constructing pierhead on new outer end; widening and deepening channel to present project dimensions; enlargement of turning basin at head of channel; shore protection west of west pier, and elimination from project construction of spur pier and dredging sheltered area outside channel limits. Depths of 29 feet in approach channel, 28 feet in entrance channel, 27 feet in river channel, 21 feet in turning basin, a detached breakwater, 1,575 feet long 2,000 feet lakeward of outer end of existing west pier, and, abandonment of lakeward end of existing approach channel." LITTLE SODUS BAY HARBOR, N.Y. (See Section 15 of Text) West entrance pier.' Extension of west pier and construction of west breakwater, and dredging channel to 12 feet deep, 400 feet wide.' East pier and east breakwater.' Extension of piers lakeward to 15.5-foot contour, and dredging channel to 15.5 feet. Extension of east pier 300 feet lakeward. LORAIN HARBOR, OHIO (See Section 16 of Text) Breakwaters and extensions of piers to present dimensions. Extend 18-foot channel from inner end of piers to Erie Avenue Bridge. Extend breakwaters and dredge to depth of 19 feet in outer harbor. Annual Report, 1876, pt.II p. 589. Annual Report, 1881, p. 2442. H. Doc. 192, 68th Cong., 1st sess. Rivers and Harbors Committee Doc. 17, 70th Cong., 1st sess. Rivers and Harbors Committee Doc. 23, 72d Cong., 1st seas H. Doc. 122, 58th Cong., 2d. sess. H. Doc. 5, 63d Cong., 1st sess. H. Doc. 478, 72d Cong., 2d sess. H. Doc. 165, 87th Cong., I1st seas.' Annual Report, 1874, p. 256. Annual Report, 1874 p. 256. Annual Report, 1871, p. 234. Annual Report, 1881, pp. 2444 and 2446. Annual Report, 1901, p. 3364 H. Doc. 131, 55th Cong., 2d sess, and Annual Report 1898, p. 2718. H. Doc. 560, 60th Cong., 1st sess. H. Doc. 644, 61st Cong., 2d seas. 32 - 29 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 32-B (Continued) AUTHORIZING LEGISLATION Acts Work Authorized Documents Aug. 8, 1917 Aug. 8, 1917 July 3, 1930 Aug. 30, 1935 Aug. 30, 1935 Aug. 30, 1935 Mar. 2, 1945 July 14, 1960 Oct. 27, 1965 June 25, 1910 Mar. 2, 1919 Aug. 30, 1935" Apr. 20, 1983 Mar. 2, 1867 Mar. 4, 1913 Extend breakwaters to present project dimensions. Deepen outer harbor and river channel toErie Avenue Bridge to 20 feet. Extend 20-foot channel to American Shipbuilding Co. drydock 2. Widen 2 bends in river and enlarge turning basin opposite National Tube Co. dockn Approach channel to municipal pier. Deepen outer harbor and river channel to American Shipbuilding Co. drydock 2 to present project dimensions and extension of river channel to upper end of National Tube Co. dock with turning basin opposite that dock. Maintenance dredging in Black River from American Shipbuilding Co. drydock 2 upper end of National Tube Co. dock was authorized Apr. 7, 1934, by Public Works Administration. Enlarging turning basin opposite National Tube Co. dock to present project dimensions. Turning basin in bend of Black River immediately upstream from Baltimore & Ohio RR coal dock. Replace Norfolk and Western Railway swing bridge with a vertical lift bridge; construct two detached arrowhead breakwaters lakeward of existing breakwaters; construct extension of east breakwater to shore; remove 300 feet of lakeward end of west break-water, remove outer 1,100 feet of east pier, deepen lake approach to 29 feet, 800-foot wide outer harbor channel to channel to 27 feet; widen river channel at bends; and construct a new turning basin 21 feet deep near upstream limit of existing project.': Construct bank of stabilization works at cut numbered I along left bank of river channel above Erie Avenue Bridge.' OGDENSBURG HARBOR, N.Y. (See Section 18 of Text) Deepening the several channels to 19 feet. Widening upper entrance channel to 400 feet, and city front to 350 feet. Enlarging and deepening lower basin to 21 feet, and removal of elevator wharf. Extend Lower East Entrance Channel, 600 west of existing pier to a depth of 27 feet below LWD. Dredged material to be disposed of in dredged disposal area site 5, owned by Ogdensburg Bridge and Port Authority. OLCOTT HARBOR, N.Y. (See Section 19 of Text) Dredging a channel 11 feet deep between parallel piers' Deepening channel to 12 feet and maintenance of west pier. H. Doc. 980, 64th Cong., 1st sess. H. Doc. 985, 64th Cong., 1st sess. H. Doc. 587, 69th Cong., 2d sess. H. Doc. 469, 72d Cong., 2d sess. Senate Committee print, 73d Cong., 2d sess. Rivers and Harbors Committee Doc. 51, 74th Cong., Ist sess. Specified in act. H. Doc. 161, 77th Cong. 1st sess. H. Doc. 166, 86th Cong., Ist sess.' PL 89-298. H. Doc. 920, 60th Cong., 1st sess. H. Doc. 663, 64th Cong., 1st sess. H. Doc. 266, 72d Cong., 1 st sess. 4'24 Section 107, 1960 River and Harbor Act Annual Report, 1866, pt. III, p. 15 and pt. IV, p. 158. H. Doc. 780, 62d Cong., 2d sess.' 32 - 30 BUFFALO, NY DISTRICT TABLE 32-B (Continued) AUTHORIZING LEGISLATION Acts Work Authorized Documents July 11, 1870 Mar. 2, 1907 July 3, 1930 Aug. 30, 1935 Oct. 17, 1940 June 30, 1948 Sept. 3, 1954 Oct. 23, 1962 June 10, 1872 Mar. 2, 1829 Aug. 2, 1882 June 25, 1910 Aug. 30, 1935' Mar. 2, 1945 OSWEGO HARBOR (See Section 20 of Text) Construction of outer west breakwater.' Repair of outer west breakwater under Plan (A).' Construction of arrowhead breakwaters; deepening outer harbor between arrowhead breakwaters, west outer harbor east of Erie- Lackawanna coal dock, and Oswego River north of Seneca St., to 21 feet; and deepening west outer harbor, west of Erie- Lackawanna coal dock, to 16 feet."' Widening channel to harbor lines in Oswego River north of Seneca St. Closing gap in west breakwater; deepening west outer harbor, west of east line of Erie-Lackawanna coal dock to project depth." Construction of east outer breakwater removal of inner end of east arrowhead breakwater, and dredging channel and basin in east outer harbor." Construction of detached breakwater at harbor entrance and removal of shoals in approach to harbor entrance to 25 feet deep. Depth of 27 feet in lake approach channel; 25 feet deep in outer harbor channel 800 feet wide from entrance gap to a turning basin 25 feet deep about 750 by 1,100 feet, at mouth of Oswego River, depth of 24 feet in earth and 25 feet in hard material in river channel from turning basin to upstream end of Port of Oswego Authority's east side terminal, a distance of about 1,600 feet; relocation of Federal project limits in Oswego River upstream of 24-foot channel to Federal project limit at north line of West Seneca St., on lines parallel to 50 feet channel ward of established harbor lines; elimination of maintenance of inner west breakwater and elimination of modification authorized by River and Harbor Act of 1948. PORT CLINTON HARBOR, OHIO (See Section 21 of Text) Parallel stone and pile jetties at mouth of river, east jetty 2,200 feet long and west jetty 1,980 feet long extending to 10-foot contour in lake. Channel 10 feet deep and 100 feet wide for outer 4,200 foot lenght and 200 feet wide for inner 800foot length to Highway Bridge. ROCHESTER HARBOR, N.Y. (See Section 23 of Text) Construction of piers.'9 Extension of piers to 15 foot contour in the lake. Concrete superstructure on piers.' Deepening channel to 20 feet. Dredging of the entrance channel and turning basin, and the elimination of the inner ends of the east and west piers, all to present project dimensions. Maintenance of the existing channel upstream of the Penn Central Co. bridge. Annual Report, 1870, pp. 54, 220, and 221 H. Doc. 55, 58th Cong., 2d sess. Rivers and Harbors Committee Doc. 24, 71st Cong., 2d sess. Rivers and Harbors Committee Doc. 7, 74th Cong., I st sess. H. Doc. 96,76th Cong. I st sess. H. Doc. 722, 80th Cong., 2d sess. H. Doc. 487, 81st Cong., 2d sess. H. Doc. 471, 87th Cong., 2d sess. Annual Report, 1875, p. 295 Annual Report, 1874, p. 247. Annual Report, 1881, p. 2437. Annual Report, 1905,p. 2383. H. Doc. 342, 61st Cong., 2d sess. H. Doc. 484, 72d Cong., 2d sess. H. Doc. 139, 76th Cong., 1st sess. 32- 31 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 32-B (Continued) AUTHORIZING LEGISLATION Acts Work Authorized Documents July 14, 1960 June 10, 1872 Aug. 26, 1937 Oct. 27, 1965 Mar. 3, 1899 June 13, 1902 Mar. 2, 1919 Jan. 21, 1927 Aug. 30, 193528 Mar. 2, 1945 July 14, 1960 Mar. 3, 1899 Depth of 24 feet in the channel from the lake to the west pier, a depth of 23 feet between the piers and in the lower river to the Penn Central Co. bridge, including the existing turning basin; a depth of 21 feet from the bridge to the upstream project limit, with suitable widening at the bends; and, upstream turning basin 21 feet deep and 650 feet wide adjacent to the improved channel, with two mooring dolphins. ROCKY RIVER HARBOR, OHIO (See Section 24 of Text) East pier and dredging of channel. Extension of east pier and deepening channel to present project dimensions. Realign and extend channel and construct an anchorage basin. SANDUSKY HARBOR, OHIO (See Section 25 of Text) Construction of channel protection works. Widening of straight and dock channels and deepening to 19 feet. Extension of east jetty to total length of 6,000 feet, with pierhead on outer end; deepening of the outer, straight, and easterly portion of dock channels to 21 feet, and westerly portion of dock channel to 20 feet. Deepening of dock channel to 22 feet. Enlargement of turning basin and construction of rock dike. Maintenance of bay channel to 22 feet; and elimination from project of portion of turning basin and rock dike. Extending Moseley channel and deepening that channel and the outer end of Straight channel to 26 feet, from deep water in the lake to the vicinity of Cedar Point dock; widening the bend at the junction of the Moseley and Straight channels and deepening to 26 feet; deepening the Straight Channel to 25 feet from the vicinity of Cedar Point dock to junction with Bay channel; deepening the Bay channel from junction with the Straight channel to the outer end of the Pennsylvania Coal dock No. 3 to 25 feet, thence from outer end of the coal dock to the turning basin to 24 feet in soft material and 25 feet in hard, with no Federal dredging within 50 feet of the dock; and enlarging the turning basin, including removal of approximately 300 feet of the rock dike, and deepening to 24 feet in soft material and 25 feet in hard. TOLEDO HARBOR, OHIO (See Section 26 of Text) A channel 400 feet wide and 21 feet deep from 25-Foot contour in Maumee Bay to Fassett Street Bridge, 200 feet wide and 19 feet deep above that point and a 500-foot turning basin at Upper End. A stone revetted earth dike in Maumee Bay Channel. H. Doc. 409, 86th Cong., 2d sess.' Annual Report, 1871, p. 211. H. Doc. 70, 75th Cong., I st sess. H. Doc. 352, 88th Cong., 2d sess.' H. Doc. 362, 55th Cong., 2d sess., and Annual Report 1898, p. 2708. H. Doc. 120, 56th Cong., 2d sess. H. Doc. 982, 64th Cong., I st sess. H. Doc. 584, 69th Cong., 2d sess. Rivers and Harbors Committee Doc. 2, 73rd Cong., I1st sess. H. Doc. 328, 76th Cong., I1st sess. H. Doc. 144, 86th Cong., I1st sess.' H. Doc. 198, 55th Cong., 2d Sess. and Annual Report 1898, p. 2693. 32 - 32 BUFFALO, NY DISTRICT TABLE 32-B (Continued) AUTHORIZING LEGISLATION Acts Work Authorized Documents June 25, 1910 Aug. 30, 1935 May 17, 1950 Sept. 3, 1954 July 3, 1958 July 14, 1960 July 4, 1836 Mar. 3, 1875 Mar. 3, 1905 July 3, 1958 Mar. 2, 1945 Aug. 13, 1968 Sept. 3, 1954 July 14, 1960 Mar. 7, 1974 Oct. 22, 1976 (Sec. 101) Act 1899 modified to insure a navigable channel to 21 feet from Fassett Street Bridge to Lake. Channel 25 feet deep and 500 feet wide from 25-foot contour to mouth of Maumee River (300 feet wide on each side of center dike in Bay Channel), thence 400 feet wide to Fassett Street Bridge, 200 feet wide above that point and a turning basin at Upper End 18 feet deep. Widening at bend of mouth of River opposite Chesapeake and Ohio Railway Dock. Removal of center dike in Maumee Bay Channel. Enlarge widening at bend opposite Chesapeake and Ohio dock and turning basin opposite American Shipbuilding Co. dock. Deepen Bay Channel including widenings to 28 feet, deepen River channels to New York Central Railroad Bridge to 27 feet and construct new turning basin below Anthony Wayne Bridge. 34 VERMILION HARBOR, OHIO (See Section 27 of Text) Parallel piers and dredging channel to 8 feet deep. Deepening of channel to 12 feet. Reconstruction of piers. New entrance formed by two overlapping arrowhead breakwaters and extension of existing river channel upstream to Liberty St. Bridge. WILSON HARBOR, N.Y. (See Section 29 of Text) Entrance channel 80 feet wide and 8 feet deep; and restore east and west piers. Extend existing channel 300 feet; and construct new channel 3,800 feet long through Tuscarora Bay. PRESQUE ISLE PENINSULA, ERIE, PA. (See Section 34 of Text) Construction of groin system, seawall, bulkhead, placement of beach material at waterworks reservation and along remainder of peninsula; removal of portions of existing structures. Periodic nourishment of shore for a 10-year period. Periodic nourishment of shore for a 5-year period. Preparation of Phase I design memorandum for improvements consisting of construction of five sections of spaced off-shore breakwaters and replenishment of beach area with sandfill. H. Doc. 865, 60th Cong., 1st sess. Rivers and Harbors Committee Doc. 21, 72d Cong., 1st sess. H. Doc. 189, 81st Cong., 1st sess. H. Doc. 620, 81st Cong., 2d sess. H. Doc. 436, 84th Cong., 2d sess. H. Doc. 153, 86th Cong., 1st sess.4 Annual Report, 1880, Annual Report, 1874, p. 219. H. Doc. 252, 58th Cong., 2d sess. H. Doc. 231, 85th Cong., I1st sess. H. Doc. 679, 76th Cong., 3d sess. H. Doc. I 12, 90th Cong., I1st sess. H. Doc 231, 3d Cong., 1st sess. H. Doc. 397, 86th Cong., 2d sess. H. Doc. 796, 93d Cong., 2d sess. 32- 33 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 32-B (Continued) AUTHORIZING LEGISLATION Acts Work Authorized Documents 1. Authorized by Public Works Administration, Sept. 6 1933. 2. Widening Cuyahoga River downstream at end of Cut 4 classified inactive. 3. Replacement of bridges 19 and 32, widening Cuyahoga and Old River Channels, classified deferred. 4. Contains latest published map. S. Permanent Appropriations Repeal Act. 6. Authorized May 28, 1935 by Emergency Relief Administration Act of 1935. 7. Improvement of guide pier at Black Rock lock was deauthorized by Congress in August 1977. 8. Classified deferred. 9. Completed under previous projects. 10. Also Sundry Civil Act of Mar. 3, 1905. 11. Authorized in part by Public Works Administration, Sept. 6, 1933. 12. Authorized by Public Works Administration Sept. 6, 1933. 13. Previously authorized by Public Works Administration. 14. First Deficiency Appropriation Act approved April 1, 1944. 15. Authorized by Defense Plant Corp., May 19, 1942. 16. Deepening left half of channel extension was eliminated from project by 1962 R&H Act. 17. Permit of Secretary of War, Aug. 5, 1927. 18. Modified 1828 apd 1852. 19. Extension of north pier portion of this modification was deauthorized Nov. 81. 20. Public Law 366, 21. Modified 1830, 1881, and 1890. New work completed under previous projects. 22. Partly included in Public Works Administration program, Nov. 15, 1933. 23. First Supplemental National Defense Appropriation Act, 1944, approved Dec. 23, 1943. 24. Removal of remaining hard-material shoals in lower basin is classified inactive. 25. Deepening remainder of Cuyahoga River from bridge I to and including Old River, classified deferred. 26. Deepening a 200-foot strip along harbor line east of mouth of Oswego River is classified inactive. 27. Modification eliminated by River and Harbor Act of Oct. 26, 1962. 28. Included in Public Works Administration program, Nov. 15, 1933. 29. Deepening strips adjacent to north and south piers was deauthorized Aug. 82. 30. Modification classified inactive. 31. Construction of breakwater classified deferred. 32. Deepening and widening remainder ofBlack River channel at Cut 1 classified deferred. 33. Deepening to 22 feet a 150-foot wide strip in west outer harbor deauthorized in May 1981. 34. The 27-foot project extended 2,800 feet and turning basin relocated under authority of Chief of Engineers. 32- 34 TABLE 32-C BUFFALO, NY DISTRICT OTHER AUTHORIZED NAVIGATION PROJECTS (See Section 31 of Text) Cost to September 30, 1985 For Last Full Report See Annual Operation and Project Report For Construction Maintenance Big (Cunnningham) Creek, Ohio' 2 19,7633 - Black River Harbor, N.Y.4 -' 42,401 - Cape Vincent Harbor, N.Y. 1962 275,082 1,562,244 Cattaraugus Creek, N.Y.5 2 57,410 - Elk Creek Harbor, Pa.' 1978 101,500 - Geneva-on-the-Lake, OH 1983 662,000 - Grasse River (Massena), N.Y.4, ' 1891 9,000' - Hamlin Beach Harbor, N.Y.' 1973 72,052 - Kelleys Island, Ohio 1974" 129,874 - Little River at Cayuga Island, N.Y.' 1969 46,8042 42,393 Morristown Harbor, N.Y.' 1949 6,221 9,69412 Niagara Remedial Works, N.Y.',so 1966 6,069,395 510,819 Ottawa River Harbor, Michigan and Ohio" 1977" 99,000 - Port Bay, N.Y. - - - Port Ontario Harbor, N.Y. 1982 810,000 - Pultneyville Harbor, N.Y. 3 1934 68,219 20,087 Put in Bay, Ohio 1951" 51,609 12,720 Sackets Harbor, N.Y. 1982 25,010 24,023 Sandusky River, Ohio' 1894 58,000' 557 1. No commerce reported. 2. Only information available is in index to reports of Chief of Engineers. 3. Amount includes maintenance; not separable. 4. Abandonment recommended in H. Doc. 467, 69th Cong., I1st sess. 5. Abandonment recommended in Ex. Doc. 16, 35th Cong., 1st Sess. 6. Project classified deferred. 7. Channel improved by local interests. 8. Includes local interests contribution of $25,742. 9. Completed. 10. Costs of operation and maintenance of this project will be settled directly by concerned power agencies. No further appropriations will be made to this project. 11. Includes local interests contribution of $27,563. 12. Includes local interests contribution of $5,000. 13. Abandonment recommended in H. Doc. 375, 64th Cong., 1st Sess. 14. Project classified inactive. 15. Annual Report for Detroit Dtistrict. 16. Construction of compensating works as authorized by 1930 R&H Act was deauthorized by Congress in August 1977. 32 - 35 TABLE 32-D REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 NAVIGATION WORK UNDER SPECIAL AUTHORIZATION (See Section 32 of Text) Navigation Activities Pursuant to Section 107, Public Law 86-645 (Preauthorization) Study Identification Braddock Bay, Greece, NY Cooley Canal, Lucas County, OH Edgewater Marina, Cleveland, OH Huron Harbor, OH Lake Erie, Sheffield, OH Lake Erie, Sturgeon Point, NY Little River, Niagara Falls, NY Lorain Small Boat Harbor, OH NFTA-Sm Boat Hbr, Buffalo NY Ogdensburg Harbor, N.Y. Seneca Lake, Watkins Glen, NY Toussaint River, Carrol Twsp, OH Fiscal Year Cost $ 72,933 5,631 50,883 52,432 51,783 19,905 11,520 43,839 42,662 703,736' 61,254 72,933 1. Does not include $6,205 in contributed funds. TABLE 32-E OTHER AUTHORIZED BEACH EROSION CONTROL PROJECTS (See Section 35 of Text) For Last Full Report See Annual Operation and Project Report For Construction Maintenance Cleveland and Lakewood, Ohio: Edgewater Park' White City Park' Fair Haven Beach State Park, Lake Ontario, N.Y.2 Fort Niagara State Park, N.Y.- Hamlin Beach State Park, N.Y.' 1976 $1,769,600 - Selkirk Shore State Park, 1963 58,978 $2,946 Lake Ontario, N.Y.' 1. Project authorized by River and Harbor Act of September 3, 1954 is classifed as deferred. 2. Project authorized by River and Harbor Act of July 3, 1958 is classifed as deferred. 3. Project authorized under provisions of Section 201, 1965 Flood Control Act has been reclassified to active. 4. Federal participation was limited to one-third of first cost when project was authorized by 1954 River and Harbor Act. Federal participation was changed from one-third to 70 percent of remaining work under Public Law 87-874. Uncompleted portion of project is classified as deferred. 5. Project completed. 32- 36 TABLE 32-F BUFFALO, NY DISTRICT OTHER AUTHORIZED FLOOD CONTROL PROJECTS (See Section 48 of Text) For Last Full Report See Annual Operation and Project Report For Construction Maintenance Auburn, N.Y. Owasco Outlet' 1962 371,985' - Batavia and vicinity, Tonawanda Creek, N.Y.' 1957 335,385 - Caledonia, Genesee River, N.Y. 1950 - - Camp Perry, Ohio' 1967 2 275,000"- Cayuga Creek, Cheektowaga, NY' 1984 1,404,500 - Chittenango Creek and tributaries, N.Y.2,3 1948 12,464 - Eastlake, Ohio, Chagrin River' 1976 506,344 - Fremont, Ohio, Sandusky River' 1976 8,589,824"0- Ithaca, N.Y., Cuyahoga Inlet, N.Y.' 1978 3,929,330" - Lackawanna, N.Y., Smokes Creek' 1971 3,542,068' - Lancaster, Cayuga Creek, N.Y.' 1954 797,300 - Marsh Creek, Geneva, N.Y.' - 226,429 - Montour Falls, Oswego River Basin, N.Y.' 1954 1,681,785 - Onondaga Creek, Nedrow, N.Y."' 1964 330,231 - Owasco Inlet and Outlet, Montville and Dry Creek, State Ditch and Crane Brook, N.Y.' 1950 281,559 - Red Creek, N.Y.' 1975 361,241 - Reno Beach-Howard Farms, Lucas County, Ohio 195312 154,467 - Syracuse, Oswego River Basin, N.Y.' 1954 3,349,248 - Warsaw, N.Y., Oatka Creek', s 1969 558,317' - Wellsville, N.Y., Genesee River' 1978 3,145,303" - 1. Completed. 2. Local interests required to contribute $25,000. 3. Project not considered economically justified and is inactive. 4. Inactive portion of work for State Ditch has been done by local interests and work on Crane Brook has been deferred at the request of local interests. 5. Project authorized by Chief of Engineers. 6. Excludes costs of $188,732 under Public Law 84-99, Flood Control and Coastal Emergencies Appropriation, incurred for project rehabilitation as a result of damages due to storm Agnes, June 1972. 7. Excludes costs of $6,766 under Public Law 84-99, Flood Control and Coastal Emergencies Appropriation, incurred for project rehabilitation as a result of damages due to storm Agnes, June 1972. 8. Includes local interests contribution of $50,000. 9. Excludes costs of $26,807 under Public Law 84-99, Flood Control and Coastal Emergencies Appropriation, incurred for project rehabilitation as a result of damages due to storm Agnes, June 1972. 10. Includes local interests contribution of $6,944. Excludes costs of $383,786 under Public Law 84-99, Flood Control and Coastal Emergencies Appropriation, for emergency restoration of levees damaged during 1973. 11. Includes local interests contribution of $125,000. 12. Annual Report for Detroit District. 13. Includes local interests contribution of$99,000. Excludes costs of $104,005 under Public Law 84-99, Flood Control and Coastal Emergencies Appropriation, incurred for project rehabilitation as a result of damages due to storm Agnes, June 1972. 14. Includes local interests contribution of$50,000. Excludes costs of $374,042 under Public Law 84-99, Flood Control and Coastal Emergencies Appropriation, incurred for project rehabilitation as a result of damages due to storms. 32 - 37 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 32-G FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION (See Section 49 of Text) Flood control activities pursuant to Sec. 205, Public Law 858, 80th Congress as amended (preauthorization) Study Identification Fiscal Year Cost Butternut Creek, Dewitt, NY...................................................................................... $ 19,524 Canandaigua Lake, N .Y ........................................................................................... 48,358 Cazenovia Creek Buffalo, NY .................................................................................... 174,739 Chagrin River, W illoughby Hills, OH ................................................................................ 2,577 Conesus Lake, Livonia, NY ........................................................................................ 24,443 Euclid Creek, OH ............................................................................................... 992,579 Keuka Lake Outlet, N Y ........................................................................................... 15,467 Limestone Creek, Fayetteville, NY ................................................................................. 24,132 M aumee River, Defiance, OH ..................................................................................... 42,149 Oneida Creek, Oneida, NY ........................................................................................ 71,916 Onondaga Creek, Syracuse, NY ..................................................................................... 7,500 Plum Creek, Columbia Station, OH ................................................................................ 18,743 Swan Creek, Toledo, OH ......................................................................................... 38,160 W . Br. Limestone Creek, M anlius, NY.............................................................................. 39,601 Flood Control and Coastal Emergencies (Public Law 99, 84th Cong., as amended by See. 206 of Flood Control Act of 1962) Project Federal Cost Advance M easures............................................................................................. $ 17,712 Disaster preparedness............................................................................................ 216,704 Emergency operations.............................................................................................50,486 Total ....................................................................................................... 284,902 Snagging and clearing of navigable streams and tributaries in interest of flood control. (Sec. 208, 1954 Flood Control Act, PL 780, 83rd Cong.) Project and location................................................................................. Fiscal Year Cost Blanchard River, Ottawa, OH ................................................................................... $ 139,269 Emergency bank protection (Sec. 14 of 1946 Flood Control Act, Public Law 526, 79th Cong.) Study Identification Fiscal Year Cost Blanchard River, Ottawa, OH ................................................................................... $ 27,057 Cattaraugus Creek, North St, Arcade, NY.............................................................................7,500 Chagrin River, East Branch, OH ................................................................................ 10,878 Chagrin River, Gates Mills, OH .................................................................................... 218,535 Cuyahoga River, Akron, OH (Bridge) ............................................................................. 149,366 Cuyahoga River, Akron, OH (Sewer)..................................................................................... 2,330' Euclid General Hospital, OH .................................................................................... 132,8662 Genesee River, Amity, NY ........................................................................................... 485 G eneva, SR 531, OH ............................................................................................. 11,199 Lk Ontario State Pkwy, Kendall, NY ................................................................................. 19 Little Elk Creek, G irard, PA ........................................................................................ 4,689 Rogers Cemetery, Amity, NY..................................................................76,592 Salmon River, Selkirk, N Y ......................................................................................... 1,000 State Route 163, M arblehead, OH .................................................................................... 151 W endt Beach Pk, Evans, NY ........................................................................................ 2.348 1. Does not include $76 in contributed funds. 2. Does not include $132,621 in contributed funds. 32- 38 BUFFALO, NY DISTRICT TABLE 32-H DEAUTHORIZED PROJECTS (See Section 50 of Text) For Last Full Report Federal Contributed See Annual Date Funds Funds Project Report For Deauthorized Expended Expended Black Rock Channel and Tonawanda Harbor, NY 1935 R&H Act 1962 Aug 1977 - - Black Rock Channel and Tonawanda Harbor, NY 1954 R&H Act 1962 May 1981 - - Crane Creek State Park, OH 1962 R&H Act 19683 Nov 1979 - - Erie Harbor, PA 1945 R&H Act 1963 Aug 1977 - - Erie Harbor, PA 1899 R&H Act 1963 Nov 1981 - - Erie Harbor, PA 1960 R&H Act 1963 Aug 1982 - - Grandview Bay Harbor, NY 1945 R&H Act 1948 Aug 1977 $ 1,524- Great Sodus Bay Harbor, NY 1962 R&H Act 1963 Aug 1977- Hammondsport, Oswego River Basin, NY 1941 FC Act 1951 Nov 1983 29,000- Ithaca, NY-Cascadilla Creek 1941 FC Act 1950 Aug 1977 8,159- Ithaca, NY-Fall Creek 1941 FC Act 1950 Aug 1977 12,300- Maumee River, above T o, OH 1872 Act 19713 Nov 1977 12,000- Niagara River, Compensating Works, NY 1930 R&H Act 1964 Aug 1977 - - Oswego Harbor, NY 1940 R&H Act2 1963 May 1981 - - Sackets Harbor, NY 1945 R&H Act 1948 May 1981 19,010- Sheffield Lake Community Park, OH 1962 R&H Act - Aug 1977 -- Watkins Glen, NY 1941 FC Act 1958 Aug 1977 43,182- 1. Extension of guide pier only; other improvements completed 2. Deepening of west outer harbor, other improvements completed. 3. Annual Report for Detroit District 32 - 39 LOS ANGELES, CA, DISTRICT* This district (total area, about 226,000 square miles) comprises those drainage basins tributary to the Pacific Ocean that are in California between the Mexican boundary and Cape San Martin (about 265 miles north of entrance to Los Angeles Harbor); lower Colorado River drainage basin (below Lee Ferry, AZ), which is in southeastern California, southeastern Nevada, southwestern Utah, western New Mexico, and all of Arizona, except the northeastern corner; that part of the Great Basin that is in southern Nevada and southeastern California; and the United States parts of those small drainage basins in southern Arizona and southwestern New Mexico west of the Continental Divide that drain southward into Mexico. IMPROVEMENTS Navigation Page 1. Channel Islands Harbor, CA .......... 33-2 2. Los Angeles and Long Beach Harbors, CA ......................... 33-2 3. Morro Bay Harbor, CA ............... 33-3 4. Oceanside Harbor, CA ............... 33-3 5. San Diego Harbor, CA ............... 33-3 6. San Diego River and Mission Bay, CA ............................ 33-3 7. Santa Barbara Harbor, CA ........... 33-4 8. Ventura Marina (Ventura Harbor), CA ......................... 33-4 9. Reconnaissance and condition surveys .............................. 33-4 Beach Erosion Control 10. Imperial Beach, San Diego County, CA .......................... 11. San Gabriel River to Newport Bay (Surfside-Sunset and Newport Beach), Orange County, CA ........................... Flood Control 12. Alamo Lake, Bill Williams River, AZ ............................ 13. Cucamonga Creek, Santa Ana River Basin, CA ...................... 14. Gila River Basin, AZ: ................. 14A. Indian Bend Wash, AZ ................ 14B. Painted Rock Dam (Gila River), AZ ........................... 14C. Phoenix, AZ, and vicinity (including New River) ................ 14D. Tucson diversion channel, AZ ................................ 14E. Whitlow Ranch Dam, Queen Creek, AZ ........................... 15. Los Angeles County drainage area, CA ............................. 33-4 33-4 33-5 33-5 33-5 33-5 33-6 33-6 33-6 33-6 33-6 Flood Control (Cont'd) Page 16. Los Coches Creek, San Diego County, CA ........................... 33-7 17. Lytle and Warm Creeks, Santa Ana River Basin, CA .................. 33-8 18. Mojave River Dam, Mojave River Basin, CA ..................... 33-8 19. Pine and Mathews Canyons Dams, Colorado River Basin, NV ............. 33-8 20. San Jacinto River levee and Bautista Creek channel, Santa Ana River Basin, CA .................. 33-8 21. Santa Ana River Basin (and Orange County), CA .................. 33-8 22. South Fork of the Santa Clara River, Santa Clarita Valley, CA ....... 33-9 23. Sweetwater River, Sweetwater River Basin, CA ...................... 33-9 24. Telegraph Canyon Creek, Chula Vista, CA ............................ 33-9 25. West Magnesia Canyon channel, Rancho Mirage, CA ................... 33-10 26. Inspection of completed flood control projects ....................... 33-10 27. Scheduling flood control reservoir operations ............................ 33-10 28. Flood control work under special authorization .................. 33-10 General Investigations 29. Surveys ............................. 33-11 30. Collection and study of basic data .................................. 33-11 31. Research and development ............ 33-11 32. Continuation of planning and engineering ..................... 33-11 32A. Holbrook levee, Little Colorado River, Colorado River Basin, AZ ...... 33-11 32B. Puerco River and tributaries, Gallup, NM .......................... 33-11 33-1 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 General Investigations (Cont'd) Page 32C. Santa Ana River main stemincluding Santiago Creek and Oak Street Drain, Santa Ana River Basin, CA ............................ 33-11 33. Advance engineering and design ............. .................. 33-11 Goleta, CA, and vicinity, Santa Barbara County ............... 33-11 Tables Table 33-A Cost and financial statement .................... 33-13 Table 33-B Authorizing legislation ................. 33-18 Table 33-C Other authorized navigation projects ........... 33-23 Table 33-D Other authorized beach erosion control projects ............... 33-24 Navigation 1. CHANNEL ISLANDS HARBOR, CA Location. On coast of southern California about a mile northwest of existing harbor of Port Hueneme, 65 miles northwest of Los Angeles Harbor, and 345 miles south of San Francisco. (See Coast and Geodetic Survey Charts 5007 and 5202.) Existing project. For details, see page 33-2 of Annual Report for 1981. Local cooperation. Fully complied with. Terminal facilities. Two thousand and six hundred boat slips in 9 marinas, with restroom and shower facilities; dry storage area for 300 boats with 3-ton and 1-ton hoist facilities; 2 marine construction and repair yards with 5-ton travel lift and 35-ton hoist to 70-ton boatway haulout capacities; a fuel dock facility; a sportfishing complex; 6 restaurants; 2 coffee shops; 800 waterfront apartments-many with adjoining slips; 300 motel units; 4 yacht club buildings; 3 public convenience docks; a 66-slip guest boat complex; a harbor administration building/harbor patrol office and dock complex; a marine emporium complex, housing a chandlery store, a sail loft, a delicatessen, a fishing tackle shop, yacht sales, an underwater repair service, and an adjacent dock complex; a 7-lane free access public launch ramp, with paved pay parking for cars and trailers; a boaters' convenience center; a commercial fishing pier and hoist; 2 large public parks; a fire station; and a U.S. Coast Guard station. Waterwayconnected and north of the harbor is Mandalay Bay, a private keys-type waterfront homes development with an area for about 500 homes and connected dockage for boats. Transition from harbor to Mandalay Bay is Tables (Cont'd) Page Table 33-E Other authorized flood control projects .............. 33-25 Table 33-F Not applicable Table 33-G Deauthorized projects ........ 33-27 Table 33-H Los Angeles County drainage area, CA: Latest approved estimated first costs for all units of improvement under existing project .............. 33-28 Table 33-I Santa Ana River Basin (and Orange County), CA: Latest approved estimated Federal first cost for all units ........................ 33-30 Table 33-J Inspection of completed flood control projects ......... 33-31 Table 33-K Flood control work under special authorization ......... 33-31 restricted by a 4-lane high-rise bridge with a clearance height of 29 feet at high tide. Operations during fiscal year. Initiated and completed maintenance dredging of sand trap and entrance channel in March 1985 at a cost of $3,251,502 regular funds and $808,964 Navy funds. 2. LOS ANGELES AND LONG BEACH HARBORS, CA Location. On coast of southern California in San Pedro Bay about 25 miles south of City of Los Angeles, about 96 miles northwest of San Diego Harbor, and about 410 miles southeast of San Francisco Harbor. (See Coast and Geodetic Survey Chart 5147.) Previous projects. For details, see page 1977 of Annual Report for 1915 and page 1646 of Annual Report for 1938. Existing project. For details, see page 33-3 of Annual Report for 1984. Local cooperation. All items of local cooperation required under the terms of the previous authorizing acts have been fully complied with. See page 33-3 of tAenrmnusa ol f Rtheep o1r9t7 6fo W r ate8rr Resourrecqeus irDeemveelnotpsm uenndt eAr ctth.e Terminal facilities. In Los Angeles Harbor, 83,875 feet of wharves, of which 76,868 feet are owned by the city and 7,007 feet are owned by private interests. In Long Beach Harbor, 58,985 feet of wharves, of which 51,775 feet are owned by the city and 7,210 feet are owned by private interests. In Long Beach Harbor, Federal Government owns 19,700 feet of waterfront inside the Navy mole, exclusive of finger piers. 33-2 LOS ANGELES, CA, DISTRICT Operations during fiscal year. Initiated and completed maintenance repair (phase 2) of San Pedro breakwater in April 1985 at a cost of $752,584 regular funds. In addition, a reconnaissance and condition survey was conducted at a cost of $704. 3. MORRO BAY HARBOR, CA Location. On coast of southern California 110 miles south of Monterey Bay, 120 miles northwest of Santa Barbara Harbor, and nearly midway between San Francisco and Los Angeles. (See Coast and Geodetic Survey Chart 5387.) Existing project. For details, see page 33-4 of Annual Report for 1980. Local cooperation. Fully complied with. None required under rehabilitation plan. Terminal facilities. Facilities, which are adequate for existing commerce, comprise 640 feet of existing piers constructed by Navy; 550 feet of piers and 150 feet of floating docks constructed by San Luis Obispo County; 263 feet of floating docks constructed by California Department of Parks and Recreation; 1,396 feet of floating docks constructed by City of Morro Bay; 1,398 feet of privately owned piers; and 5,435 feet of privately owned floating docks. Operations during fiscal year. Completed maintenance repair of north (phase 1) and south breakwaters in October 1984; and awarded contract for and initiated maintenance repair of north breakwater (phase 2), which is about 46 percent complete, at a cost of $842,999 regular funds. Initiated and completed maintenance dredging in March 1985 at a cost of $1,544,527 regular funds. In addition, a reconnaissance and condition survey was conducted at a cost of $1,874. 4. OCEANSIDE HARBOR, CA Location. On coast of southern California at Oceanside, about 30 miles north of City of San Diego. (See Coast and Geodetic Survey Chart 5101.) Existing project. For details, see page 33-4 of Annual Report for 1981. Local cooperation. Fully complied with for maintenance to date. Terminal facilities. Berthing for 915 boats (750 single-tie slips, 46 double-tie slips, and 119 side-ties, of which 47 are visitors slips); 12 dry storage spaces at Oceanside Marine Center; a fuel dock; a boat hoist; a launching ramp, which can accommodate 4 launchings at the same time; parking for 1,732 cars, with temporary parking for about 141 boat trailers; a boat-repair facility; a pump-out facility; a Coast Guard cutter; restaurants; retail stores; yacht brokers; a boatel/motel; condominiums; and a sport-fishing facility. Operations during fiscal year. Completed contract payment for maintenance dredging at a cost of -$18,259 regular funds and $4,997 Navy funds. Completed construction of first contract for experimental sand bypass system, discharge pipeline, in November 1984. Awarded contract for and initiated construction of second contract for experimental sand bypass system, pump facilities and power system, which is about 3 percent complete. Cost for construction was $289,306 regular funds. 5. SAN DIEGO HARBOR, CA Location. On coast of southern California just north of United States-Mexico boundary line, about 109 miles southeast of Los Angeles and Long Beach Harbors. (See Coast and Geodetic Survey Chart 5107.) Previous projects. For details, see page 1976 of Annual Report for 1915 and page 1642 of Annual Report for 1938. Existing project. For details, see page 33-4 of Annual Report for 1980. Local cooperation. Requirements are described in full on page 33-5 of Annual Report for 1980. Terminal facilities. Consist of 45,070 feet of wharves, exclusive of Government-owned wharves, of which 21,070 feet are Port District owned and 24,000 feet are privately owned. Government-owned wharves at North Island are restricted to military use only. Operations during fiscal year. Completed contract payment for maintenance repair of rubblemound jetty on Zuniga Shoal at a cost of $3,570 regular funds. In addition, a reconnaissance and condition survey was conducted at a cost of $12,027. 6. SAN DIEGO RIVER AND MISSION BAY, CA Location. The San Diego River has its source on the tableland in the Cuyamaca Mountains near Santa Ysabel, CA, and flows southwestward 52 miles to the Pacific Ocean at the City of San Diego. Mission Bay Harbor is adjacent to the outlet of the San Diego River, 77 miles southeast of Los Angeles and Long Beach Harbors and 8 miles north of San Diego Harbor. Existing project. A leveed flood channel 800 feet wide, with a capacity of 115,000 cubic feet per second, from 0.4 mile above Morena Boulevard, 3.3 miles directly to the ocean; an altered railroad bridge over the leveed river flood channel; an entrance channel about 5,200 feet long, 670 feet wide, and 20 to 25 feet deep into Mission Bay; in the bay, a main channel and turning basin about 2,700 feet long, 1,000 feet wide, and 20 feet deep, and two anchorage basins, one about 3,200 feet long, 600 feet wide, and 15 feet deep, and the other about 1,600 feet long, ranging from 800 to 1,800 feet wide, and 20 feet deep; three jetties at the entrance; and stone revetment for the banks of the entrance and main channels and turning basin. Plane of reference is mean lower low water. Range between mean lower low water and mean higher high water is 4.4 feet. Extreme range is about 10 feet. Approved estimated (1985) first cost is $37,700,000 ($20,200,000 Federal and $17,500,000 non- 33-3 REPORT OF TIE CHIEFP OF ENGINEERS, U.S. ARMY 1985 Federal). This project modified the flood control project: "San Diego River Basin, California." (See H. Doc. 635, 77th Cong., 2d sess.) Local cooperation. Fully complied With, Terminal facilities. None, with the exception of mooring facilities for recreational craft and commercial sport-fishing boats only. Operations during fiscal year. Continued preparation of supplemental project plan, which is about 98 percent complete. Continued preparation of environmental assessment, which is about 98 pttent complete. Completed contract payment for mainteiance tepair of rock revetment in Mariners Basin at a ost of $44 regular funds. 7. SANTA BARBARA HARBOR, CA Location. On coast of southern Cal~nia 9t0 iles northwest of Los Angeles Harbor and 0 mi utheast of San Francisco Harbor. (See (oait *nd (iodetic Survey Chart 5261.) Existing project. For details, see page $-4 of Annual Report for 1983. Local cooperation. See page 1015 ofAntual Reeft for 1969 for items of local cooperatio under 1962 authorized modification of existing proect Terminal facilities. A wharf 2,000 f4t hj t piler 325 feet long in harbor for tie-up .m ing .ft Coast Guard cutter; a landing float; an open tn iing and slip anchorage for small craft; and a launching ramp for small craft. Operations during fiscal year. Continued maintenance dredging, which is about 40 percent complete, at a cost of $274,767 regular funds. 8. VENTURA MARINA (V NTURA HARBOR), CA Location. On coit of southern Calitrl1a about 65 miles northwest of the City of Los Angeles, about 70 miles northwest of Los Angeles and Long Beach Harbors, and about 6 miles northwest of Channel Islands Harbor. Existing project. For details, see page 83-5 of Annual Report for 1981. Local cooperation. Fully complied with. Terminal facilities. Two fuel docks; guest berthing docks; 3 boat-repair facilities, 1 full service with a 60- ton travelift, 1 full service with a i10-ton marine elevator, and 1 do-it-yourself boatyard with a 20-ton travelift; Fisherman's Pier, with 3 50-ton jib cranes for off-loading commercial fishing vessels;flake ice manufacturing and distribution system; wholeale fish buying stations; a retail fish market and seafod restau. rant; offshore oil industry crew trans lo; 1,800 boat slips; a mast up dry storage area .etable boats; a 6-lane deluxe launch ramp ; restaurants; cocktail lounges; sport-f i tn' t, harbor and offshore islands excursin boats; a eht sales; marine communications sales and services; 3 marine chandleries; 2 public restroom buildings; a harbor administration building/harbormaster's office; a headquarters/visitors center for Channel Islands National Park; marine related ancillary businesses, including a convenience grocery store, a marine bookstore, a dive shop, gift shops, and a jewelry store; and a 230-room resort and time-share hotel. Operations during fiscal year. Completed maintenance dredging of entrance channel and sand trap in December 1984 at a cost of $1,477,006 regular funds. 9. RECONNAISSANCE AND CONDITION SURVEYS Reconnaissance and condition survey was conducted in December 1984 at Newport Bay Harbor, CA. Beach Erosion Control 10. IMPERIAL BEACH, SAN DIEGO COUNTY, CA Location. On coast of southern California at Imperial Beach in San Diego County. Existing project. Plan as modified by Chief of Engineers in August 1979 provides for a submerged offshore breakwater about 5,000 feet long, extending southward from northern groin; extension of northern groin about 100 feet to connect with breakwater; and a groin about 600 feet long from shoreline to southern end of breakwater. Latest approved estimated (1983) first cost for project as modified is $5,880,000 (includes allowance for estimated inflation through construction period), comprising $3,340,000 Federal and $2,540,000 non-Federal. Map of modified plan is in "Design Memorandum No. 4, General Design Memorandum, Imperial Beach Erosion Control Project, San Diego County, California," prepared by Los Angeles District in September 1978. Local cooperation. Requirements are described in full on page 33-6 of Annual Report for 1981. Operations during fiscal year. Awarded first construction contract, breakwater (phase 1), in September 1985. 11. SAN GABRIEL RIVER TO NEWPORT BAY (SURFSIDE-SUNSET AND NEWPORT BEACH), ORANGE COUNTY, CA Location. Along the coast of southern California for about 17 miles from Anaheim Bay Harbor downcoast to Newport Bay Harbor. Existing project. Original authorized project provided for a single detached offshore rubblemound breakwater, located along the minus 24-foot contour just upcoast from the Newport Beach fishing pier, and 33-4 LOS ANGELES, CA, DISTRICT the deposition of about 3,000,000 cubic yards of suitable beach-building material along the shoreline in the vicinity of Surfside-Sunset Beach to provide a protective beach. Existing project was modified in September 1963 by Chief of Engineers, as follows: (a) Consider south limit of project to be west jetty at entrance to Newport Harbor; (b) construct offshore breakwater, for entrapping sand in littoral movement, near mouth of the Santa Ana River. Periodically transport this entrapped sand to Surfside area to replenish that beach; and (c) construct a groin as an extension of south jetty of the Santa Ana River to compartmentalize beach from this area to Newport pier. Construct additional structures and fills in this area at such time and in such locations, as required, to retain existing beach. Latest approved estimated (1984) first cost for modified project is $43,700,000 ($29,200,000 Federal and $14,500,000 non-Federal). Local cooperation. Requirements are described in full on page 33-8 of Annual Report for 1979. Operations during fiscal year. Completed stage 8 construction, which consisted of placement of beach fill on Surfside-Sunset Beach, in June 1985 at a cost of $40,681regular funds and $20,342 required contributed funds. Flood Control 12. ALAMO LAKE, BILL WILLIAMS RIVER, AZ Location. About 70 miles southeast of Kingman, AZ, in a narrow gorge at river mile 39 on Bill Williams River, AZ, a tributary of Colorado River. Existing project. For details, see page 33-7 of Annual Report for 1981. Local cooperation. Fully complied with. Operations during fiscal year. Maintained dam in good operating condition and administered real estate. 13. CUCAMONGA CREEK, SANTA ANA RIVER BASIN, CA Location. In and near the Cities of Upland, Rancho Cucamonga, and Ontario, and the communities of Alta Loma and San Antonio Heights, San Bernardino and Riverside Counties, CA. Existing project. Plan as modified provides for a debris basin on Cucamonga Creek and a concrete tcoh aPnrnaedl oa loDnagm C; ucaanm oimngpar oCvreede kS farno mA tnhteo ndieob rHise bigahsitns diversion system that would include 6 debris basins and a concrete diversion channel to divert West Cucamongfa Creek headwaters into Cucamongfa Creek; a collection levee and a debris basin downstream from Demens, Thorpe, and Angalls Canyons and a concrete outlet channel from the debris basin to Cucamonga Creek; a debris basin in Deer Canyon and a channel along Deer Creek from the debris basin to Cucamonga Creek; the Hillside debris basin in a canyon just west of Deer Canyon with an outlet channel to Deer Creek channel; improvement of an existing levee system along the west bank of Day Creek to assure that flows from Day Canyon do not enter Deer Creek channel; turnouts to mitigate ground water basin recharge losses; landscaping appropriate for esthetic treatment; and recreational facilities in the project area. Subdrainage would be provided along specific reaches of the channels. Latest approved estimated (1983) first cost for modified project is $117,856,000 (includes allowance for estimated inflation through construction period), comprising $93,900,000 Federal and $23,956,000 non-Federal. Map of modified plan is in "Design Memorandum No. 2, General Design for Flood Control and Recreation, Cucamonga Creek, Santa Ana River Basin, San Bernardino and Riverside Counties, California," prepared by Los Angeles District in June 1973. Local cooperation. Requirements are described in full on page 33-7 of Annual Report for 1981. Operations during fiscal year. Completed construction of twelfth contract, erosion control of Deer Creek and Hillside channels in February 1985. Initiated construction of thirteenth contract, erosion control of Cucamonga and Demens Creeks channels (part 2), which is about 97 percent complete. Completed preparation of plans and specifications for fourteenth contract, erosion control of Cucamonga and Deer Creeks; awarded contract; and initiated construction, which is about 84 percent complete. Initiated and completed preparation of plans and specifications for fifteenth contract, recreational facilities (part 1). Administered rights-of-way acquisition continued by local interests. Cost for construction of channels was $2,152,365 regular funds. 14. GILA RIVER BASIN, AZ 14A. INDIAN BEND WASH, AZ Location. On Indian Bend Wash in Scottsdale and Tempe, AZ. Existing project A greenbelt floodway with an unlined inlet channel, including an unlined interceptor channel, a siphon to carry Arizona Canal irrigation waters under Indian Bend Wash, and a wasteway structure that discharges floodwaters from the canal into the inlet channel; an unlined outlet channel that discharges floodwaters into the Salt River; a collector and side channels system that relieves ponding west of the Arizona Canal; beautification; and recreational facilities. Design flood of 30,000 cubic feet per second is controlled by improvements. Map of modified plan is in r"aDnedsiugmn MPheamsoer aInI,d uPmro jNeoc.t 1D, eGsiegnne rafol rD Iensidgina nM Bemenod- Wash, Arizona," prepared by Los Angeles District in May 1975. Local cooperation. Requirements are described in full on page 33-8 of Annual Report for 1981. 33-5 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Operations during fiscal year. Completed construction of tenth contract, reach 4 of side channels system, in October 1984. Initiated and completed construction of twelfth contract, repair of reach 4 of side channels system, in June 1985. Costs for construction of channels were $349,991 regular funds and $82,632 other contributed funds. Continued preparation of operation and maintenance manual, which is about 65 percent complete. 14B. PAINTED ROCK DAM (GILA RIVER), AZ Location. On Gila River (mile 126) about 20 miles downstream from Gila Bend, AZ, in Gila River Basin, which is a part of Colorado River Basin. Existing project. For details, see page 33-9 of Annual Report for 1981. Local cooperation. Requirements are described in full on page 33-9 of Annual Report for 1981. Operations during fiscal year. Maintained dam in good operating condition and administered real estate. 14C. PHOENIX, AZ, AND VICINITY (INCLUDING NEW RIVER) Location. On Cave Creek, Skunk Creek, Dreamy Draw, New River, and Agua Fria River in and adjacent to metropolitan Phoenix, AZ. Existing project. Plan as modified by Division Engineer, South Pacific Division, in July 1977, provides for four dams and detention basins, one each on Dreamy Draw, Cave Creek, Skunk Creek, and New River; Arizona Canal diversion channel; channel improvements on Cave Creek, Skunk Creek, and New River; flowage easements with some floodproofing along Skunk Creek and New and Agua Fria Rivers; flood plain management along Dreamy Draw, Cave Creek, Skunk Creek, and New River; and recreational facilities. Approved estimated (1985) first cost for modified project is $443,488,000 (full funding estimate and includes allowance forestimated inflation through construction period), comprising $255,298,000 Federal and $188,190,000 non-Federal. Map of modified plan is in "Design Memorandum No.3, General Design Memorandum-Phase I, Plan Formulation for New River and Phoenix City Streams, Arizona," prepared by Los Angeles District in March 1976. Local cooperation. Requirements are described in full on page 33-9 of Annual Report for 1981. Operations during fiscal year. Completed construction of New River Dam in April 1985. Completed construction of recreational facilities (phase 1) at Dreamy Draw Dam in November 1984. Awarded contract in September 1985 for construction of Arizona Canal diversion channel, reach 1, Skunk Creek to Cactus Road. Costs for construction of channels were $23,906 regular funds and $2,719 required contributed funds. Cost for construction of levees was $63,907 regular funds. Costs for construction of dam were $2,817,253 regular funds and $66,322 required contributed funds; for roads, railroads, and bridges, $119,325 regular funds and $2,681 required contributed funds; for buildings, grounds, and utilities, $29,998 regular funds and $745 required contributed funds; and for recreational facilities, $46,923 regular funds and $46,923 required contributed funds. Continued preparation of part 4 of project plan, phase II, Skunk Creek and New and Agua Fria Rivers, which is about 95 percent complete. Completed preparation of part 5 of project plan, phase II, Arizona Canal diversion channel. Initiated preparation of water control manual. Administered rights-of-way acquisition continued by local interests. 14D. TUCSON DIVERSION CHANNEL, AZ Location. In Pima County in drainage areas of Tucson Arroyo and Julian Wash, tributaries of Santa Cruz River near Tucson, AZ. Existing project. For details, see page 33-7 of Annual Report for 1982: Local cooperation. Fully complied with. Operations during fiscal year. Awarded contract for and initiated construction of recreational facilities (phase 1), which is about 98 percent complete, at a cost of $559,610 regular funds and $559,610 required contributed funds. 14E. WHITLOW RANCH DAM, QUEEN CREEK, AZ Location. On Queen Creek, AZ, a tributary of Gila River, about 10 miles west of Superior, AZ. Existing project. For details, see page 33-10 of Annual Report for 1981. Local cooperation. Fully complied with. Operations during fiscal year. Completed preparation of water control manual. Maintained dam in good operating condition; continued acquisition of rights-ofway; and administered real estate. 15. LOS ANGELES COUNTY DRAINAGE AREA, CA Location. Along Los Angeles and San Gabriel Rivers, Rio Hondo, and Ballona Creek, and tributaries thereof in Los Angeles County, CA. Previous project. For details, see pages 1768 to 1772 of Annual Report for 1941; page 1602 of Annual Report for 1942; and page 1535 of Annual Report for 1943. Existing project. Plan provides for flood control improvements in four stream basins in Los Angeles County, CA, as follows: Los Angeles River Basin, San Gabriel River Basin, Rio Hondo Basin, and Ballona Creek Basin. Provides for protection of about 325,000 acres in densely populated Los Angeles County, includ- 33-6 LOS ANGELES, CA, DISTRICT ing areas in Los Angeles, Pasadena, Glendale, Burbank, and other cities. Plan provides for construction of 5 flood control dams (Hansen, Lopes, Santa Fe, Sepulveda, and Whittier Narrows); debris basins at mouths of 22 canyons; channel improvements along 101.8 miles of Los Angeles River, San Gabriel River, Rio Hondo, and Ballona Creek; and channel improvements along 198.69 miles of tributary channels. All units of improvement are physically completed in those four stream basins, except the one listed below, and are described in Annual Report for 1962. A rehabilitation plan was approved in May 1984. The rehabilitation plan provides for restoring deteriorated portions of the Los Angeles River channel along a 22.6- mile reach from Lankershim Boulevard to Stewart and Gray Road, and for repairing and improving the Los Angeles River channel along a 1-mile reach upstream from Sepulveda Dam in the vicinity of Balboa Boulevard. Approved estimated (1985) Federal first cost for rehabilitation is $29,700 (includes allowance for estimated inflation through construction period). A map of the rehabilitation plan is in "General Design Memorandum, Los Angeles River Rehabilitation under the Major Rehabilitation Program," dated January 1984 and revised in March 1984. Unit of improvement not physically completed in Rio Hondo Basin is Sierra Madre Wash. Plan provides for the construction of about 0.8 mile of concrete channel on Sierra Madre Wash extending from inlet to existing Santa Anita Wash channel. (See table 38-H for latest approved estimated (1976) first costs for all units of improvement under existing project.) Local cooperation. Requirements are described in full on page 38-11 of Annual Report for 1981. Operations during fiscal year. Operations for units in Los Angeles River Basin: (a) Compton Creek: Maintained channel in goodoperatingcondition from Alameda Street to Hooper Avenue storm drain. (b) Haines Canyon: Maintained debris basin and channel upstream from Plainview Avenue in good operating condition and administered real estate. (c) Hansen Dam: Maintained dam in good operating condition and administered real estate. (d) Lopes Dam: Continued preparation of water control manual. Maintained dam in good operating condition and administered real estate. (e) Los Angeles River channel, Lankershim Boulevard to Stewart and Gray Road: Administered real estate. Completed construction of first rehabilitation contract, low flow channel (8P&UP RR. to 4th St.), in December 1984. Initiated and completed construction of second rehabilitation contract, channel invert and sidelope toe (Los Feliz Blvd. to Dayton Ave.), in December 1984. Initiated and completed construction of third rehabilitation contract, low flow channel (Lankershim Blvd. to Niagara St.), in December 1984. Initiated and completed preparation of plans and specifications for fourth rehabilitation contract, channel invert (Sepulveda Dam basin); awarded contract; and initiated construction, which is about 95 percent complete. Initiated and completed preparation of plans and specifications for fifth rehabilitation contract, low flow channel (Dayton Ave. to Stewart and Gray Rd.); awarded contract; and initiated construction, which is about 67 percent complete. Initiated and completed preparation of plans and specifications for sixth rehabilitation contract, main channel invert (Burbank-Western confluence); awarded contract and initiated construction, which is about 82 percent complete. Initiated preparation of plans and specifications for seventh rehabilitation contract, sideslope (Olympic Blvd. to Washington Blvd.) and main channel invert (4th St. to Washington Blvd.), which are about 5percentcomplete. Initiated preparation of plans and specifications for eighth rehabilitation contract, subdrain flapgates (Dayton Ave. to Stewart and Gray Rd.), which are about 5 percent complete. Cost for construction of channels was $8,206,886 regular funds. (f) Los Angeles River channel, Santa Ana Branch, Pacific Electric railway bridge to Pacific Ocean: Awarded contract in September 1985 for phase 2A construction of recreational facilities. (g) Sepulveda Dam: Continued preparation of water control manual. Maintained dam in good operating condition and adminiatered real estate. Operations for units in San Gabriel River Basin: (a) Santa Fe Dam: Maintained dam in good operating condition and administered real estate. Completed construction of phase 5 recreational facilities in December 1984 at a cost of $165,920 regular funds and $51,888 other contributed funds. (b) San Gabriel River channel, San Gabriel Canyon to Santa Fe Dam, Approach channel to Santa Fe Dam (remedial work): Maintained channel in good operating condition. (c) Whittier Narrows Dam: Maintained dam in good operating condition and administered real estate. Operations for units in Rio Hondo Basin: (a) Alhambra Wash: Maintained channel upstream from Valley Boulevard in good operating condition. (b) Rio Hondo channel, Whittier Narrows Dam to Los Angeles River (lower): Awarded contract in September 1985 for phase 2A construction of recreational facilities. Operations for unit in Ballona Creek Basin: Ballona Creek channel and jetties: Maintained channel downstream from Washington Boulevard to La Salle Avenue and downstream from Los Angeles city boundary to ocean; jetties; and Pacific Avenue bridge in good operating condition. 16. LOS COCHES CREEK, SAN DIEGO COUNTY, CA Location. In the community of Lakeside, San Diego County, CA. Existing project. Plan provides for a 1.8-mile-long rectangular concrete channel; an inlet structure just downstream from the Los Coches Creek bridge and adjacent to Los Coches and Ha-Hana Roads; and an outlet structure at the confluence of the San Diego River. Plan also provides for 5 double box culverts and 1 33-7 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 triple box culvert. Latest approved estimated (1983) first cost for project is $6,197,000 ($4,000,000 Federal and $2,197,000 non-Federal). Local cooperation. Provide lands, easements, and rights-of-way, including lands for mitigation, and borrow and spoil disposal areas; provide cash contribution for first costs in excess of Federal limitation; perform alterations or relocations of structures, transportation facilities, bridges, utilities, and drainage facilities; provide modification, operation, and maintenance of mitigation lands; maintain and operate works after completion; hold and save the United States free from damages due to construction, operation, and maintenance of project, excluding damages due to fault or negligence of the United States or its contractors; adjust water-rights claims; prescribe and enforce regulations to prevent obstruction or encroachment on flood control works that would reduce their flood-carrying capacity or hinder maintenance and operation; and comply with section 221 of Public Law 91-611. Operations during fiscal year. Initiated and completed preparation of plans and specifications. 17. LYTLE AND WARM CREEKS, SANTA ANA RIVER BASIN, CA Location. Near San Bernardino and Colton, San Bernardino County, CA. Existing project. Plan as modified provides for a rectangular concrete channel extending for 3.5 miles along East Branch of Lytle Creek from existing Foothill Boulevard inlet structure to confluence with Warm Creek; a concrete trapezoidal channel on Warm Creek for 1.5 miles from confluence with East Branch of Lytle Creek to confluence with Santa Ana River; a leveed channel extending about 1.8 miles along Santa Ana River from mouth of existing East Twin and Warm Creeks concrete channel to Mount Vernon Avenue crossing; replacement of 4 railroad bridges and 12 highway bridges; 3 new highway bridges; inlets for side drainage; and relocation and protection of utilities. Design capacities of improvements would be: East Branch of Lytle Creek, 58,000 cubic feet per second; Warm Creek, 60,000 to 90,000 cubic feet per second; and Santa Ana River, 167,000 to 234,000 cubic feet per second. Latest approved estimated (1984) first cost of modified project is $44,410,000 (includes allowance for estimated inflation through construction period), comprising $37,600,000 Federal and $6,810,000 non-Federal. Authorized project was modified by Design Memorandum No. 1, approved in May 1972, which contains a map of modified project plan. Local cooperation. Requirements are described in full on page 33-13 of Annual Report for 1981. Operations during fiscal year. Completed preparation of supplemental project plan. Initiated preparation of plans and specifications, which are about 25 percent complete. 18. MOJAVE RIVER DAM, MOJAVE RIVER BASIN, CA Location. On Mojave River at the Forks site, just downstream from mouth of Deep Creek and about 14 miles upstream from Victorville, in Mojave River Basin, CA. Existing project. For details, see page 33-8 of Annual Report for 1983. Local cooperation. Requirements are described in full on page 33-13 of Annual Report for 1981. Operations during fiscal year. Initiated preparation of water control manual. Maintained dam in good operating condition and administered real estate. 19. PINE AND MATHEWS CANYONS DAMS, COLORADO RIVER BASIN, NV Location. In Lincoln County, NV, about 100 miles north of Hoover Dam and about 17 and 20 miles, respectively, east of Caliente, NV. Existing project. For details, see page 33-13 of Annual Report for 1981. Local cooperation. Fully complied with. Operations during fiscal year. Maintained dams in good operating condition and administered real estate. 20. SAN JACINTO RIVER LEVEE AND BAUTISTA CREEK CHANNEL, SANTA ANA RIVER BASIN, CA Location. In Riverside County, CA, near San Jacinto, Hemet, and Valle Vista, CA. Existing project. A 3.9-mile-long levee on the left side of the San Jacinto River and about 4.8 miles of concrete-lined channel on Bautista Creek upstream from California State Highway 74. Local cooperation. Fully complied with. Operations during fiscal year. Completed construction of a 1.3-mile extension of concrete-lined channel to correct project deficiency on Bautista Creek in February 1985 at a cost of $863,995 regular funds and $179,610 other contributed funds. 21. SANTA ANA RIVER BASIN (AND ORANGE COUNTY), CA Location. On Santa Ana River and tributaries and on other streams in Orange, Riverside, and San Bernardino Counties, CA. General plan of improvement. For details, see page 33-14 of Annual Report for 1981. Existing project. For details on active units, see Annual Report for 1968. For other pertinent information, see table 33-E, "Other Authorized Flood Control Projects," and table 33-G, "Deauthorized Projects." (See 33-8 LOS ANGELES, CA, DISTRICT table 33-I for latest approved estimated Federal first cost for all units.) Local cooperation. Fully complied with. Operations during fiscal year. Operations for units in existing project: (a) Brea Dam: Initiated preparation of water control manual. Maintained dam in good operating condition and administered real estate. (b) Carbon Canyon Dam and channel: Awarded fourth contract for recreational facilities (phase 3) in September 1985. Maintained project in good operating condition; administered real estate; and continued acquisition of rights-of-way. (c) Fullerton Dam: Initiated preparation of water control manual. Maintained dam in good operating condition and administered real estate. (d) Prado Dam: Maintained dam in good operating condition and administered real estate. Completed construction of fifth contract for recreational facilities in December 1984. (e) San Antonio Dam: Maintained dam in good operating condition and administered real estate. (f) San Antonio and Chino Creeks channel: Maintained project in good operating condition and administered real estate. 22. SOUTH FORK OF THE SANTA CLARA RIVER, SANTA CLARITA VALLEY, CA Location. In unincorporated area in Santa Clarita Valley in northern Los Angeles County, CA. Existing project. Plan provides for a debris basin at the junction of Towsley and Wiley Canyons; a 600-footlong rectangular concrete channel, extending from downstream end of debris basin spillway to The Old Road crossing; a 1.2-mile-long rectangular concrete channel, extending from Calgrove to Lyons Avenue; raising walls of existing channel downstream from Lyons Avenue; 7 bridges; and mitigation measures. Latest approved estimated (1984) first cost for project is $11,391,000 ($4,000,000 Federal and $7,391,000 non- Federal). Local cooperation. Provide lands, easements, and rights-of-way, including suitable borrow and spoil disposal areas; provide cash contribution for first costs in excess of Federal limitation; perform alterations and relocations of buildings, transportation facilities, storm drains, utilities, and other structures and improvements (excluding railroad bridges and approaches, and facilities for normal interception and disposal of local interior drainage at line of protection); maintain and operate works after completion; prescribe and enforce regulations to prevent obstruction or encroachment on flood control works that would reduce their flood-carrying capacity or hinder maintenance and operation, and control development in project area to prevent an undue increase in flood damage potential; publicize flood plain information and provide this information to zoning and other regulatory agencies; hold and save the United States free from damages, including water rights claims, due to construction, operation, and maintenance of project, excluding damages due to fault or negligence of the United States or its contractors; and comply with section 221 of Public Law 91-611. Operations during fiscal year. Initiated and completed preparation of plans and specifications. 23. SWEETWATER RIVER, SWEETWATER RIVER BASIN, CA Location. Lower Sweetwater River Valley, along Sweetwater River from Interstate Freeway 805 to San Diego Bay, San Diego County, CA. Existing project. Plan as modified provides for about 3.2 miles of improved trapezoidal channel along Sweetwater River from Interstate Freeway 805 to San Diego Bay as part of a combined flood control and highway project. Approved estimated (1985) first cost for project is $48,600,000 (includes allowance for estimated inflation through construction period), comprising $24,600,000 Federal and $24,000,000 non-Federal. Map of modified plan is in "General Design Memorandum No. 1 for Sweetwater River Flood Control Channel, San Diego County, California," prepared by Los Angeles District in March 1982 and revised in May 1984. Local cooperation. Requirements are described in full on page 33-16 of Annual Report for 1981. Operations during fiscal year. Completed preparation of plans and specifications for stage 2 construction. California State Department of Transportation awarded contract for and initiated stage 2 construction, which is about 15 percent complete. Initiated and completed preparation of plans and specifications for stage 3 construction. Cost for construction of channels was $2,342,000 regular funds. Cost for roads, railroads, and bridges was $2,239,000 regular funds. 24. TELEGRAPH CANYON CREEK, CHULA VISTA, CA Location. In and near the City of Chula Vista, San Diego County, CA. Existing project. Plan provides for a 0.7-mile-long rectangular concrete channel from about 500 feet upstream from 4th Avenue to 0.3 mile upstream from Interstate 5; two 12-foot-wide by 10-foot-high boxes, totaling 0.3 mile in length, that would connect the rectangular concrete channel to existing 0.2-mile-long culvert, which would be incorporated into project; a 0.3-mile-long trapezoidal concrete channel downstream from Interstate 5; a 0.1-mile-long trapezoidal earthbottom channel leading into San Diego Bay; and beautification. Latest approved estimated (1983) first cost for project is $5,390,000 ($4,000,000 Federal and $1,390,000 non-Federal). Local cooperation. Provide lands, easements, and rights-of-way, including borrow and spoil disposal areas; provide cash contribution for first costs in excess of Federal limitation; perform alterations and relocations 33-9 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 of buildings, transportation facilities, storm drains, utilities, and other structures and improvements (excluding railroad bridges and approaches, and facilities for normal interception and disposal of local interior drainage at line of protection); maintain and operate works after completion; hold and save the United States free from water rights claims; prescribe and enforce regulations to prevent obstruction or encroachment on flood control works that would reduce their floodcarrying capacity or hinder maintenance and operation, and control development in project area to prevent an undue increase in flood damage potential; publicize flood plain information and provide this information to zoning and other regulatory agencies; hold and save the United States free from damages due to construction, operation, and maintenance of project, excluding damages due to fault or negligence of the United States or its contractors; and comply with section 221 of Public Law 91-611. Operations during fiscal year. Completed preparation of plans and specifications. 25. WEST MAGNESIA CANYON CHANNEL, RANCHO MIRAGE, CA Location. In the City of Rancho Mirage, Riverside County, CA. Existing project. Plan provides for a debris basin at mouth of Magnesia Spring Canyon; a 1.4-mile-long rectangular concrete channel; and an energy dissipator at the confluence of the Whitewater River. Plan also provides for preservation and enhancement of wildlife habitat values on 20 acres of alluvial cone. Latest approved estimated (1983) first cost for project is $8,279,000 ($4,000,000 Federal and $4,279,000 non- Federal). Local cooperation. Provide lands, easements, and rights-of-way, including borrow and spoil disposal areas, and mitigation area; provide cash contribution for first costs in excess of Federal limitation or for costs required by special cost sharing due to windfall benefits, whichever is greater; perform alterations and relocations of buildings, transportation facilities, storm drains, utilities, and other structures and improvements (excluding railroad bridges and approaches, and facilities for normal interception and disposal of local interior drainage at line of protection); maintain and operate works after completion, including mitigation features; hold and save the United States free from water rights claims; prescribe and enforce regulations to prevent obstruction or encroachment on flood control works that would reduce their flood-carrying capacity or hinder maintenance and operation, and control development in project area to prevent an undue increase in flood damage potential; publicize flood plain information and provide this information to zoning and other regulatory agencies; hold and save the United States free from damages due to construction, operation, and maintenance of project, excluding damages due to fault or negligence of the United States or its contractors; and comply with section 221 of Public Law 91-611. Operations during fiscal year. Completed preparation of plans and specifications. Awarded contract for and initiated construction, which is about 7 percent complete, at a cost of $121,100 regular funds and $200,000 required contributed funds. 26. INSPECTION OF COMPLETED FLOOD CONTROL PROJECTS Inspection costs for fiscal year from regular funds for maintenance were $307,108. (Seetable 33-J on inspection of completed flood control projects.) 27. SCHEDULING FLOOD CONTROL RESERVOIR OPERATIONS In accordance with section 7, Flood Control Act of 1944, studies of reservoir operations for flood control were conducted; and preparation of regulations for the use of storage allocated for flood control was continued for the following Bureau of Reclamation projects: Hoover Dam and Twitchell Dam. Costs for fiscal year from regular funds for maintenance were $50,205. 28. FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION Flood control activities pursuant to section 205, Public Law 80-858, as amended (preauthorization) See table 33-K on flood control work under special authorization. Emergency bank protection (sec. 14 of 1946 Flood Control Act, Public Law 526, 79th Cong.) Federal cost for fiscal year was $22,511 for Rillito River, Pima County, AZ; and $68,524 for Santa Ana River, Colton, CA. Emergency flood control activities - repair, flood fighting, and rescue work (Public Law 99, 84th Cong., and antecedent legislation) Federal cost for fiscal year was $837,525, of which $202,765 were for advance preparation; $28,091 were for flood emergency operations; and $604,189 were for rehabilitation; and $2,480 were for advanced measures. Flood insurance activities (sections 1301-1877, 1968 Housing and Urban Development Act, Public Law 90-448, as amended) In coordination with flood control activities, flood insurance studies were continued in accordance with Inter-Agency Agreements at fiscal year cost of $209,853 under Housing and Urban Development reimbursable order. 33-10 LOS ANGELES, CA, DISTRICT General Investigations 29. SURVEYS Fiscal year cost was $5,509,850 regular funds, of which $599,436 were for navigation studies; $91,559 were for beach erosion control studies; $3,256,171 were for flood control studies; $957,282 were for surveys; $43,345 were for special studies involving coordination with other agencies; $469,646 were for review of authorized projects; $92,144 were for miscellaneous activities; and $268 were for supplemental preauthorization studies, phase I. 30. COLLECTION AND STUDY OF BASIC DATA Fiscal year costs were $153,908 for technical services, including $18 for Southeast, and $11 for Salt and Gila Rivers, both in Maricopa County, AZ; and $17 for Ventura River, Ventura County, CA; $81,146 for flood plain management; and $10 for inspection of dams. 31. RESEARCH AND DEVELOPMENT Fiscal year cost was $10,452 for hydrologic studies. 32. CONTINUATION OF PLANNING AND ENGINEERING 32A. HOLBROOK LEVEE, LITTLE COLORADO RIVER, COLORADO RIVER BASIN, AZ Holbrook levee is on Little Colorado River at Holbrook, Navajo County, AZ, in northeastern Arizona, about 200 miles northeast of Phoenix. Project was authorized by Flood Control Act of 1970, Public Law 91-611, dated December 31, 1970. Plan of improvement provides for raising existing north bank levee and adding a new south bank levee, a low flow channel, recreational facilities, and mitigation features. Existing levee (north) would be raised to a height ranging from 23 feet high upstream from Apache Railroad bridge to about 12 feet high downstream from bridge, and would be about 18,000 feet long. South side levee would be about 5,000 feet long and would have a maximum height of 23 feet. Continued preparation of project plan during fiscal year. Estimated preconstruction planning cost is $970,000. Total costs during fiscal year were $72,142. 32B. PUERCO RIVER AND TRIBUTARIES, GALLUP, NM Puerco River, which rises at the Continental Divide about 32 miles east of Gallup, flows through the heart of the city in McKinley County, NM, and empties into the Little Colorado River about 95 miles west of Gallup near Holbrook, AZ. Project was authorized by House Resolution, dated October 12, 1972. Plan of improvement provides for reconstructing, realigning, and extending existing south bank levee; constructing an auxiliary levee on the north bank; improving interior drainage; and adding recreational and mitigation features. Existing south bank levee would be extended from Munoz Drive downstream to about 1,000 feet upstream from Allison Road bridge, and would be about 7,000 feet long. North bank levee would be along the sag curve in Interstate 40, and would be about 2,000 feet long. Initiated preparation of project plan during fiscal year. Estimated preconstruction planning cost is $600,000. Total costs during fiscal year were $304,142. 32C. SANTA ANA RIVER MAIN STEM -INCLUDING SANTIAGO CREEK AND OAK STREET DRAIN, SANTA ANA RIVER BASIN, CA Santa Ana River main stem-including Santiago Creek and Oak Street Drain, Santa Ana River Basin, CA, is on Santa Ana River and tributaries and on other streams in Orange, Riverside, and San Bernardino Counties, CA. Project was authorized by Water Resources Development Act of 1976, Public Law 94-587, dated October 22, 1976. Plan of improvement provides for construction of Mentone Dam near community of Mentone, San Bernardino County; managementof flood plain between Mentone Dam and Prado Reservoir; improvement of Oak Street Drain in Corona, Riverside County; enlargement of existing Prado Dam and reservoir, Riverside and San Bernardino Counties; improvement of lower Santa Ana River channel from Prado Dam to Pacific Ocean; and improvement of lower reach of Santiago Creek channel in Orange County; recreational development along project length; purchase of 8 acres of salt marsh for mitigation of project effects; purchase of 84 acres of tidal lands at mouth of Santa Ana River for preservation of endangered least tern habitat; landscaping; and recreational features. Continued preparation of project plan, phase II, during fiscal year. Estimated preconstruction planning cost is $21,000,000. Total costs during fiscal year were $3,106,885. 33. ADVANCE ENGINEERING AND DESIGN GOLETA, CA, AND VICINITY, SANTA BARBARA COUNTY Goleta, CA, and vicinity is in Goleta Valley along Atascadero Creek and its tributaries, including Tecolotito, Carneros, San Pedro, Las Vegas, San Jose, and Maria Ygnacio Creeks, from the Santa Ynez Mountains in Santa Barbara County to Pacific Ocean near Goleta, CA. Project was authorized by Flood Control Act of 1970, Public Law 91-611, dated December 31, 1970. 33-11 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Plan of improvement provides for about 12.5 miles of channel improvement, comprising about 1.3 miles of channel clearing and about 11.2 miles of channel construction. Channel clearing would be required on Maria Ygnacio, San Jose, Las Vegas, San Pedro, and Carneros Creeks. Channel construction would include the improvement of Atascadero Creek from San Marcos Road to ocean; Maria Ygnacio Creek from Hollister Avenue to Atascadero Creek; San Jose Creek from 0.2 mile north of U.S. Highway No. 101to San Pedro Creek; Las Vegas Creek from Cathedral Oaks Road to San Pedro Creek; San Pedro Creek from a point 0.1 mile downstream from Stow Canyon Road to Atascadero Creek; Carneros Creek from 0.6 mile upstream from U.S. Highway No. 101, by means of a diversion route, to Tecolotito Creek; and Tecolotito Creek from U.S. Highway No. 101 toAtascadero Creek. Plan also provides for beautification and recreation features. Continued preparation of project plan, phase I, during fiscal year. Estimated preconstruction planning cost is $2,650,000. Total costs during fiscal year were $152,466. 33-12 LOS ANGELES, CA, DISTRICT TABLE 33-A COST AND FINANCIAL STATEMENT See Section in Text Project 1. Channel Islands Harbor, CA 2. Los Angeles and Long Beach Harbors, CA (Regular Funds) (Required Contrib. Funds) (Other Contrib. Funds) 3. Morro Bay Harbor, CA 4. Oceanside Harbor, CA (Regular Funds) (Other Contrib. Funds) 5. San Diego Harbor CA (Regular Funds) Required Contrib. unds) Other Contrib. Funds) 6. San Diego River and Mission Bay, CA (Regular Funds) Other Contrib. unds) Funding New Work: Approp. Cost Maint.: Approp. Cost New Work: Approp. Cost Maint.: Approp. Cost New Work: Contrib. Cost New Work: Contrib. Cost Maint.: Contrib. Cost New Work: Approp. Cost Maint.: Approp. Cost Rehab.: Approp. Cost Maint.: Approp. Cost New Work: Contrib. Cost Maint.: Contrib. Cost New Work: Approp. Cost Maint.: Approp. Cost New Work: Contrib. Cost New Work: Contrib. Cost New Work: Approp. Cost Maint.: Approp. Cost New Work: Contrib. Cost Total Cost to FY 82 FY 83 FY 84 FY 85 Sep. 30, 1985 - - - $5,123,3451 - - - 5,123,3451 $2,212,577 $2,441,000 -$164,000 $3,513,800 21,229,3062 2,226,683 109,904 2,157,690 3,513,156 21,210,4192 12,968,000 5,323,000 -340,000 -69,000 64,710,719 13,626,683 5,721,814 -268,794 17,627 64,299,1643 980,000 2,768,600 704,000 1,102,904 9,948,9634 972,371 358,760 3,062,364 1,065,667 9,852,6214 390,000 214,180 - - 1,203,180 548,526 175,655 80,057 - 1,169,426 11,294,000 4,220,130 147,000 77,000 38,598,7055 14,893,514 4,777,401 801,586 214,111 38,146,1476 -- - - 87,1206 - - - 87,1206 - - - 2,612,0937 - - - - 2,612,0937 1,580 1,573,052 165,000 3,021,874 9,665,8138 22,890 60,846 1,676,263 2,920,156 9,612,7898 -- - - 2,128,411 -- - - 2,128,411 692,825 5,081,782 -1,970,133 1,162,500 9,228,039 649,198 642,862 2,411,303 1,001,590 8,900,311' -- - - 491,28610 - - - 491,286o10 - - - 1,200,000 20,000 7,500 - - 1,187,500 - - - 28,094,09511 - 423 - - 28,092,19911 - 558,390 202,656 13,127 2,280,46512 - 37,114 662,437 66,685 2,272,67212 - - - 717,910 -- - - 715,215 - - - 1,926,56318 -- - - 1,900,06318 285,000 - 35,000 69,000 11,974,09914 269,031 122,034 58,373 58,939 11,952,64614 - 3,627,000 -107,000 -20,600 4,746,873 s - 289,324 3,154,990 14,774 4,706,56115 - 192,125 -192,125 - 557,832 - - - 557,832 33-13 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 33-A (Cont'd) COST AND FINANCIAL STATEMENT See Section in Text Project 7. Santa Barbara Harbor, CA 8. Ventura Marina Ventura Harbor), CA 10. Imperial Beach, CA (Regular Funds) (Required Contrib. Funds 11. San Gabriel River to Newport Bay (Surfside-Sunset and Newport Beach), Orange County, CA Regular Funds) Required Contrib. unds) 12. Alamo Lake, Bill Williams River, AZ 13. Cucamonga Creek, Santa Ana River Basin, CA (Regular Funds) (Required Contrib. unds) Other Contrib. unds) 14A. Gila River Basin, AZ, Indian Bend Wash (Regular Funds) (Required Contrib. unds) (Other Contrib. unds) 14B. Gila River Basin, AZ, Painted Rock Dam (Gila River) 1 1 j Funding New Work: Approp. Cost Maint.: Approp. Cost New Work: Approp. Cost Maint.: Approp. Cost New Work: Approp. Cost New Work: Contrib. Cost New Work: Approp. Cost New Work: Contrib. Cost New Work: Approp. Cost Maint.: Approp. Cost New Work: Approp. Cost New Work: Contrib. Cost New Work: Contrib. Cost New Work: Approp. Cost New Work: Contrib. Cost New Work: Contrib. Cost New Work: Approp. Cost Maint.: Approp. Cost 10 90,107 424,000 411,266 17,256,000 15,700,133 758,083 1,645,662 2,515,000 1,869,796 - 2,577,000 - 5,843,010 4,229 1,496,156 78,897 4,562,303 - - - 16,934,06021 - - -525 16,933,53521 487,000 494,000 546,000 4,428,799 372,021 580,299 579,462 4,401,928 3,950,000 100,000 1,553,000 93,199,900 4,057,329 1,041,150 2,686,070 92,894,840 - - 458,000 543,512 - - - 72,264 -270,893 -39,526 64,521 9,447,853 400,965 6,823 47,380 9,304,550 6,000,000 1,324,000 -100,000 31,820,480 5,006,159 2,126,292 764,626 31,603,887 46,190 - - - 384,754 4,089 37,118 - - 304,720 359,000 668,979 273,000 - 3,576,361 8,345 386,307 458,952 82,632 3,121,769 - - - - 19,980,564n - - - - 19,980,564n 592,000 594,000 472,000 752,000 7,534,148 629,289 551,293 479,419 751,204 7,493,306 33-14 Total Cost to FY 82 FY 83 FY 84 FY 85 Sep. 30, 1985 - - - - 172,00016 - - - - 172,00016 855,169 945,543 341,000 328,000 8,588,11917 855,755 555,992 729,914 324,420 8,583,77017 - - - - 1,711,53918 - - - - 1,711,5391s 1,047,100 2,488,000 653,000 1,635,000 13,928,43719 1,046,894 2,329,024 818,882 1,635,618 13,912,76819 -28,000 - 2,000,000 493,000 3,342,7572 38,174 74,623 103,226 31,271 833,3682 - - - 2,710,000 2,735,601 - - - - 25,584 - 255,000 3,425,000 -172,000 9,722,100 33,321 153,690 3,227,871 133,149 9,718,204 LOS ANGELES, CA, DISTRICT TABLE 33-A (Cont'd) COST AND FINANCIAL STATEMENT See Section in Text Project 14C. Gila River Basin, AZ, Phoenix, AZ, and vicinity (including New River) (Regular Funds) Reqq uired Contrib. Funds) Other Contrib. Funds) 14D. Gila River Basin, AZ, Tucson diversion channel (Regular Funds) (Required Contrib. Funds) 14E. Gila River Basin, AZ, Whitlow Ranch Dam, Queen Creek 15. Los Angeles County drainage area, CA (Regular Funds) Required Contrib. unds) Other Contrib. unds) 16. Los Coches Creek, San Diego County, CA (Regular Funds) Required Contrib. unds) 17. Lytle and Warm Creeks Santa Ana River asin, CA 18. Mojave River Dam, Mojave River Basin, CA (Regular Funds) (Other Contrib. unds) 19. Pine and Mathews Canyons Dams, Colorado River Basin, NV Total Cost to Funding FY 82 FY 83 FY 84 FY 85 Sep. 80, 1985 New Work: Approp. Cost New Work: Contrib. Cost New Work: Contrib. Cost New Work: Approp. Cost New Work: Contrib. Cost New Work: Approp. Cost Maint.: Approp. Cost New Work: Approp. Cost Maint.: Approp. Cost Rehab.: Approp. Cost New Work: Contrib. Cost New Work: Contrib. Cost New Work: Approp. Cost New Work: Contrib. Cost New Work: Approp. Cost New Work: Approp. Cost Maint.: Approp. Cost New Work: Contrib. Cost New Work: Approp. Cost 6,198,000 4,680,000 12,860,000 5,600,000 5,399,656 5,621,403 11,998,004 6,526,194 127,000 47,262 38,700 77,223 7,237 68,355,297 67,584,271 346,000 500,000 621,000 2,335,214 81,743 624,923 149,008 1,527,609 - - 1,775,000 2,234,700 - - 10,169 406,731 80,000 600,000 150,000 6,927,6252 6,638 88,109 561,122 6,752,310" " 47,000 145,000 143,000 42,645 84,911 206,863 815,000 967,700 -23,800 1,337,870 367,925 858,698 3,044,000 9,107,000 3,084,000 2,719,160 5,723,627 6,864,570 - - 5,000,000 - - 1,800,240 127,500 286,818 - 527,013 378,256 166,382 - - 308,007 - - 228,946 235,000 112,557 774 244 773,000 754,707 50,000 154,571 10,054 750,000 567,634 135,000 134,559 207,361 4,264,000 3,474,626 6,520,000 9,475,162 516,000 6,028 200,000 51,373 245,000 240,846 100,000 750,000 567,634 1,867,9633 1,867,963 901,413 900,391 377,026,885" 3 377,019,880" 29 52,180,020" o 50,920,0962 n 11,520,000 11,275,162 14,449,3413 13,873,9903 37,152,872" a5 36,920,207" a 530,000 518,028 100,000 - - 200,000 35,245,831" -21,026 -6,210 202,993 35,219,061" - - - 17,838,198 - - - 17,838,198 653,000 342,000 275,000 3,028,548 244,816 588,335 391,117 2,963,394 - - - 286,300 - - - 284,501 - - - 1,401,248 - - - 1,401,248 33-15 !i REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 33-A (Cont'd) COST AND FINANCIAL STATEMENT see in Text Project Funding FY 82 FY 88 FY 84 FY 85 Sep. 80, 1985 20. San Jacinto River levee and Bautista Creek channel, Santa Ana River Basin, CA (Regular Funds) (Other Contrib. Funds) 21. Santa Ana River Basin (and Orange County), CA (Regular Funds) Rdequired Contrib. Funds) 22. South Fork of the Santa Clara River, Santa Clarita Valley, CA (Regular Funds) (Required Contrib. Funds) 23. Sweetwater River, Sweetwater River Basin, CA 24. Telegraph Canyon Creek, Chula Vista, CA 25. West Magnesia Canyon channel, Rancho Mirage, CA (Regular Funds) (Required Contrib. Funds) Maint.: Approp. Cost New Work: Approp. Cost New Work: Contrib. Cost New Work: Approp. Cost Maint. Approp. Cost New Work: Contrib. Cost New Work: Approp. Cost New Work: Contrib. Cost New Work: Approp. Cost New Work: Approp. Cost New Work: Approp. Cost New Work: Contrib. Cost 44,000 63,000 240,000 39,883 43,070 261,434 239,000 2,631,000 3,553,000 212,270 1,008,903 3,984,060 -1,367 1,291,700 1,224,904 44,056 60,500 63,388 50,000 53,603 150,000 116,097 115,000 116,524 143,000 139,766 -100,000 1,025,682 999,356 993,509 9,349,974 9,257,889 - 386,868 -2,590 712,001 - 176,203 206,318 710,244 819,300 23,800 - 47,994,738- 9 40 83,204 770,398 17,747 47,992,963 m s 41 2,266,000 1,377,000 2,039,000 22,270,810 a " 1,686,767 1,775,951 2,202,404 22,093,309a " - -17,394 75,000 3,197,7624 21,149 -432 - 3,099,1904 80,000 - 140,000 607,500 14,970 65,056 139,200 606,440 - 200,000 11 200,000 145,000 1,500,000 4,000,000 7,124,503 136,413 467,244 4,964,685 7,047,843 - 125,000 157,000 782,000 87,250 114,039 170,276 776,813 20,000 80,000 705,000 1,235,000 16,223 84,040 322,836 852,801 - 350,000 - 266,137 350,000 266,137 1. Excludes $1,361,668 Navy funds; Coast Guard costs; and $210,748 other contributed funds. 2. Includes $7,178 for reconnaissance and condition surveys. Excludes $4,889,313 for maintenance accomplished with Navy funds. 3. Includes $2,187,047 for new work for previous project; $1,593 667 public works funds; a credit of $33,050 for transfer of land at Reservation Point; and $996,792 emergency relief funds. Excludes Federal funds spent by the Navy for new work on middle breakwater, and Coast Guard costs. 4. Includes $139,347 for maintenance for previous project and $122,227 for reconnaissance and condition survey costs since FY 1958. 5. Includes $1,672,575 for new work betterments desired by local interests prior to 1976 modification. 6. Includes $87,120 for maintenance betterments desired by local interests prior to 1976 modification. 7. Navy funds. 8. Includes $264,898 for reconnaissance and condition s$u1r2v4e,5y7s8 sointhcee rF Y 1958 and $307,945 Navy funds. Excludes contributed funds. 9. Includes $69,804 for reconnaissance and condition surveys. Excludes $4,559,487 for maintenance accomplished with Navy funds. 10. For jetty and groin extensions desired by local interests. 11. Includes $154,704 for new work for previous projects: $86,352 public works funds; and $1,226,793 emergency relief funds. Excludes $254,795 Navy funds for dredging entrance channel in FY 1961 to depth of-42 feet mean lower low water (or 2 feet below project depth); and Coast Guard costs. 12. Includes $59,904 for maintenance for previous projects and $200,972 for reconnaissance and condition surveys since FY 1958. In addition, includes $144 for retroactive pay increase shown in "cost" figure only, as reported in 1958 Annual Report, page 1430. Excludes $240,216 for maintenance accomplished with Navy funds. 33-16 - LOS ANGELES, CA. DISTRICT TABLE 33-A (Cont'd) COST AND FINANCIAL STATEMENT 13. Includes $4,441 for betterments desired by local interests prior to modification by 1968 River and Harbor Act. 14. Includes $2,610,000 regular funds and excludes $2,910,000 required contributed funds, both for new work on flood control project, "San Diego River Basin, Calif." 15. Includes $81,941 for reconnaissance and condition surveys. 16. Excludes Coast Guard costs. 17. Includes $29,198 public works funds; $11,000 working funds for work performed in addition to existing project; and $19,741 for reconnaissance and condition surveys. Excludes $462,986 other contributed funds spent by the Corps for maintenance-dredging betterments desired by local interests. 18. Excludes $1,708,836 required contributed funds and Coast Guard costs. 19. Includes $53,899 for reconnaissance and condition surveys. 20. Excludes $66,124 other contributed funds and Coast Guard costs. 21. Includes 57,000 Code 710 funds since FY 1975. 22. Includes $35.7,469 Code 710 funds since FY 1962. 23. Excludes $394,364 other contributed funds. 24. Includes $1,163,000 Code 710 funds since FY 1977. 25. Includes 987,685 Code 710 funds since FY 1977. 26. Includes $,758 Code 710 funds since FY 1962. 27. Includes 11,008,936 emergency relief funds for new work. Excludes 16,726,888 emergency relief funds spent by Corps in connection with emergency relief (previous) project and 107,989 for minor rehabilitation. 28. Includes $8,768,900 Code 710 funds since FY 1974 ($1,226,100 for Sepulveda Dam* $6,290,000 for Whittier Narrows Dam; $22,000 for LACISA prototype; $53,000 for Hansen Dam $10,422 100 for Santa Fe Damn; 15,000 for Tujunga Wash channel; $8,600 for IAes Dam; $,562,200 for Los Angeles River and Ro Hondo channels; $1,483,000 for Balona Creek channel). 29. Includes $23,766,894 Code 710 funds since FY 1974 ($1,223,226 for eiulveda Dam* $6,289,998 for Whittier Narrows Dam; $22,000 for LACIA prototype; ,000 for Hansen Dam $10,419124 for Santa Fe Dam; 15,000 for Tujunga Wash channef; $8,500 for Lones Dam; $3,561,320 for Los Aneles River and Rio Hondo channels; an $1,482,726 for Ballona Creek channel). 30. Includes $475,000 for recreational facilities since FY 1985 ($10,000 for Sepulveda Dam and $465,000 for Los Angeles River and Rio Hondo channels). 31. Includes $8,765 for recreational facilities since FY 1985 ($6,162 for Sepulveda Dam and $2,603 for Los Angeles River and Rio Hondo channels). 82. Includes $14,449 841 Code 710 funds since FY 1974 ($992,s650for lvedSam; $6,797' 56for Whittier Narrows Dm:$199,54foras channel' $460,500 for Hansen Dam; p3400 for Los Angeles aver and Rio Hondochannel; 1i,58for Sants F~Pam;and $1,191,500 for Ballona Creek channel). 8W7 33. Inlud $13,873,990 Code 710 funds since FY 1974 ($992,545 or SelveDam; $6 739 255for Whittier Narrows Dam; $198,91 r Tujung Wash channel' $460,180 for Hansen Dam; 824,054 for Los Angeles kiver and Rio Hondo channels; $1,467,538 for Santa Fe Dam; and $1,191,500 for Iallona (reek channel). 34. Non-Federal funds spent by the Federal Government to September 0, 1985, for replacements required as part of local rs d betterments desired by local interests. Excel 00 other contributed funds spent by the Corps i nin with emergency relief (previous) project. 35. Inc .. $50007 Code 710 funds since FYn1984 ,007 e Dam and $200,000 for Los Angeles River o channels). 36. Inc es$0,319 Code 710 funds for Santa Fe Dam sinceF 194. 37. Excld $5,499,193 other contributed funds. .8C8o. funds for Brea, Fullerton Prado and San Antonio Da , Crbon Canyon Dam and channel, Lytle and Caon Cre channel improvements, and San Antonio and Chino C nel (active units). 39. I $5000 working funds for San Antonio Dam; $67 361 rn .a Dam (inactive unit) (also reported under Other Autor Flood Control Projects"); and $85,310 undistri buted fw . Excludes other contributed funds spent by the Corps afollows: $124,105 for water conservation betterments dired by local interests at Prado Dam; $8,500 for betterments desired by local interests at San Antonio Dam; $24,70 for betterments desired by local interests on San Antnio d Chino Creeks channel; and $601,762 for required ltemsof local cooperation on Lytle and Cajon Creeks channel improvenents. Excludes $290,000 spent direct by local interests.oo San Antonio and Chino Creeks channel for local eratiitms not required. 40. Inludes 920,831 Code 710 funds since FY 1974 ($1,068 731 for Carbon Cyon Dam and channel; $1,264,800 for Fullerona ;and ,97,800 for Prado Dam). 41. Incudes 919, ode 710 funds since FY 1974 ($1,057 288 for Carbon Caon Dam and channel; $1,264,800 for Fulerton Dam; and $3,597,468 for Prado Dam). 42. Includ $75,000 for recreational facilities since FY 1985 ($75,000 Carbon Canyon Dam and channel). 43. Inlud $1,895 for recreational facilities since FY 1985 ($C1, r bn Canyon Dam and channel). 44 Exetu maintenance for Lytle and Cajon Creeks channel improve inents, which are operated and maintained by local lnterest. 4& Include $8,197762 Code 710 funds since FY 1974 ($1, T97fo r Carbon C on Dam and channel; $1,269,789 or F Dmrtoann:dI 42000 for Prado Dam). 46. Inl 099,190 Code 710 funds since FY 1975 ($1 bO Canyon Dam and channel; $1,248,082 orl! ; and $424,185 for Prado Dam). REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 88-B AUTHORIZING LEGISLATION See Date of Section In Authorizing Text Act Project and Work Authorized Documents 1. Sep. 3, 1954 2. June 3, 1896 June 25, 1910 July 25, 1912 Aug. 8, 1917 Sep. 22, 1922 Mar. 3, 1925 July 3, 1980 Do. Aug. 80, 1985 Oct. 17, 1940 CHANNEL ISLANDS HARBOR, CA Harbor for light-draft vessels and shore protection works. H. Doec. 362, 83d Cong., 2d sess. LOS ANGELES AND LONG BEACH HARBORS, CA A breakwater 8,500 feet long, east of Point Fermin. S. Doe. 18, 55th Cong., 1st sess. Extend said breakwater to shore, making a total length H. Doe. 969, 60th Cong., of 11,152 feet from Point Fermin. 1st sess. Dredge Los Angeles outer harbor west of entrance Rivers and Harbors channel. Committee Doe. 8, 62d Cong., 2d sess. For silt-diversion works. Rivers and Harbors Committee Doe. 9, 64th Cong., 2d sess. Triangular area approach to Los Angeles inner harbor H. Doc. 1013, 66th Cong., entrance glannel. 3d sess. Dredge Lop Angeles Harbor main channel and entrance H. Doe. 349, 68th 35 feet deep and 1,000 feet wide; dredge inner harbor Cong., 1st sess. ning basin 85 feet deep; and reclamation of Reservation A detached breakwater 12,500 feet long in prolongation Rivers and Harbors of existing breakwater (authorized by act of 1896). Committee Doc. 33, 71st Cong., 2d seas. Widen fairway on east side of entrance to Los Angeles S. Doc. 130, 71st Cong., iner harbor dredge a channel 85 feet deep and 650 2d sesea. fqet wide in east Basin from turning basin to U.S. station 406; dredge 85 feet deep and 400 feet wide in Cerritos channel from U.S. station 406 to Long uurrbn g basin; a turning basin 85 feet deep at/mn h; entrance channel to Long Beach Harbor 35 feet deep and 500 feet wide; and maintenance of the Long Beach breakwater south of outer end pier A. This act provides that in no ease shall dredging be done within 50 feet of established pierheadlines of existing piers and wharves. Dr dg,O-foot-wide entrance channel to Los Angeles S. Committee print, outerbaror to 40-foot depth and a turning basin 3 500 74th Cong., 1st sees. feet long and 1,500 feet wide to same depth; and enlarge entrance to inner harbor by dredging to 35-foot depth a triangular area at its junction with turning basin. Dredge to a depth of 40 feet areas A and B adjacent to H, Poe. 843, 76th Cong., 40-foot-depth entrance channel; construct and maintain a 3d sess. rubblem.nound breakwater of composite type 21,000 feet long in eastward direction from northeast end of existing detached breakwater; dredge about 4 million cubic yards initially for a settling basin at mouth of Los Angeles River diversion channel and deposit material on beaches eastward therefrom to Belmont pier; maintenance dredging of areas A and B, and at mouth of Los Angeles River diveysion channel; all subject to such modifications as in diseretion of the Chief of Engineers may be advisable to meet requirements of the Navy. 38-18 oDS ANGELES, CA, DISTRICT TABLE 88-B (Cont'd) AUTHORIZING LEGISLATION See Date of Sectio in Autbrisng Text Act Project and Work Authorized Documents Sep. 8, 1964 July 14, 1960 Oct. 22, 1976 3. Mar. 2, 1945 4. Oct. 27, 1965 5. Mar. 8, 1875 Sept. 19, 1890 June 25, 1910 Mar. 4, 1913 July 27, 1916 Aug. 8, 1917 Aug. 8, 1917 Sept. 22, 1922 Mar. 8, 1925 Dredge to a depth of 35 feet in East Basin as a modification of existing project. This act provides that the Secretary of the Army authoried to reimburse local interests for work the have done upon this project prior to July 1, 1968, at actual cost to local interests so far as same shall be approved by Chief of Engee rs and found to have been done in accordance with the project hereby adopted and that such reimbursement shallbe subject to appropriations applicable thereto or funds available therefor and shall not take precedence over other pending proc of hi prioity for harbor i$m50p0ro0v0e0m. ents; and that such payments shall not exceed Dredge to a depth of 85 feet in West Basin as a modification of existing project. Dredge Ls Angeles Harbor entrance channel 45 feet deep, 1,000 feet wide, and about 5,500 feet long; Los Aneles channel 45 feet deep, 750 feet wide, and about 12,500 feet l1ng; inner harbor turninr basin 45 feet deep, 1,850 fee wide, and about 1,650 feet long; East Basmn channel 45 feet deep, 400 feet wide, and about 6,000 feet long, West Basin 45 feet deep, from 50 to 1,850 feet wide, and about 8,800 feet lon, and East Basin 45 feet deep, from 400 to 950 feet wide, and about 2,000 feet lon. This act provides that no dredgin shall be done within 125 feet of established pierheadlines, wharves, or other struetures MORRO BAY HARBOR, CA Adoption and improvement of existing entrance channel to bay a breakwater extending south by west from Morro Rock, and bay channels andbains at locations and of dimensions substantially as shown on the Navy Department map on file in the Office of the Chief of Engineers. OCEANSIDE HARBOR, CA Maintenance of general navigation features of Del Mar Boat Basin and of Oceanside Harbor. SAN DIEGO HARBOR, CA Diversion dike. Jetty on Zuniga Shoal. Dredge channel through outer bar 30 feet deep and 600 feet wide, and a channel through middle ground to 80 feet deep. Dredge channel through outer bar 570 feet wide and 85 feet deep, and a channel through middle ground 82 feet deep. Widen approach (area B) to San Diego municipal pier by dredging area C (north of area B). Dredging area A (south of area B). Dredge 385-foot channel through middle ground. Dredging areas D and E. Widen approach (area C) to San Diego municipal pier 1 by dredging a portion of area F (north of area C). 3388-19 H. Doc. 161, 88d Cong., 1st seas. H. Doe. 401, 86th Cong., 2dseas. H. Doe 94-594, 94th Cong., 2d sess.' H. Doc, 283, 77th Cong., 1st seas. H. Doc. 76, 89th Cong., 1st sess. Annual Report, 1873; p. 1142 H. Ex. Doc. 177, 50th Cong., 1st seas. (Annual Report, 1888; p. 2114) H. Doe. 961, 60th Cong., 1st seas. H. Doe. 1309, 62d Cong., 3d ses. H. Doc. 648, 64th Cong., 1st seas. Rivers and Harbors Committee Doc. 8, 64th Cong., 2d sees. H. Doe. 140, 65th Cong., 1st seas. H. Doc. 1000, 66th Cong., 3d seas. Rivers and Harbors Committee Doc. 2, 68th Cong., 1st sess. REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 88-B (Cont'd) AUTHORIZING LEGISLATION See Date of Section in Authorizing Text Act Project and Work Authorized Documents July 3, 1930 Aug. 30, 198P Aug. 26, 1987 Oct. 17, 1940 Mar. 2, 1945 Aug. 18, 1968 6. July 24, 1946 7. Aug. 30, 1935 Mar. 2, 1945 Oct. 28, 1962 Dec. 31, 1970 8. Aug. 13, 1968 10. July 8, 1958 11. Oct. 28, 1962 12. Dec. 22, 1944 Deepen to 40 feet channel through outer bar; along south S. Doc. 81, 71st Cong., and north banks, main channel; dredge turning basin, 2d sess. widen area H, and dredge a channel to National City and Chula Vista. Widen bay channel to 2,200 feet with depth of 35 feet from H. Doc. 223, 73d Cong., the vicinity of Whalers Bight in lower bay to naval air 2d asess. station opposite turning basin. Dredging areas Q, Q-1, M, N, and O. Rivers and Harbors Committee Doc. 89, 74th Cong., 2d seas. Dredge a seaplane basin (area 8) of about 3,000 acres, 10 H. Doc. 844, 76th Cong., feet deep, and fill an area of about 110 acres adjacent to 3d sess. southern end of basin. Dredge triangular approaches to 26- and 35-foot anchorages, H. Dec. 390, 77th Cong., area M. 1st sess. Deepen and extend existing navigation channels, delete H. Doc. 365, 90th Cong., uncompleted parts, and extend maintenance. 2d sess.1 SAN DIEGO RIVER AND MISSION BAY, CA Modification of existing flood control project for San Diego H. Doc. 760, 79th Cong., River, CA, to include a multiple-purpose project for 2d sess. flood control on San Diego River and small-boat navigation on Mission Bay. SANTA BARBARA HARBOR, CA Maintenance dredging present depths into harbor formed S. Committee Print, 73d by breakwater constructed by local interests. Cong., 2d sess. Permits maintenance by means of a fixed sand-intercept- H. Doc. 348, 77th Cong., ing plant to be provided and operated by and at expense of 1st seas. local interests. United States to contribute to operating expense an amount not to exceed $30,000 annually, whenever funds are allotted therefor; funds thus contributed to be reduced by actual cost of harbor maintenance if and when intercepting plant has been installed. Modification of existing project. H. Doc. 518, 87th Cong., 2d ses. Dredging and maintenance by United States. None VENTURA MARINA (VENTURA HARBOR), CA Adoption and maintenance of existing general navigation H. Doc. 356, 90th Cong., features of harbor, excluding interior basins; construction 2d sess. of an offshore breakwater; dredging a sand trap in lee of breakwater; repairing existing north and middle jetties; and construction of recreational fishing facilities on jetty crests. IMPERIAL BEACH, CA Federal participation by contribution of Federal funds H. Doc. 399, 84th Cong., toward cost of five groins. 2d sess. SAN GABRIEL RIVER TO NEWPORT BAY SURFSIDE-SUNSET AND NEWPORT BEACH), RANGE COUNTY, CA Modification of authorized project at Anaheim Bay H. Doc. 602, 87th Cong., Harbor, CA, to provide for an offshore breakwater at 2d sess. Newport Beach and a protective and feeder beach in the vicinity of Surfside-Sunset Beach. Federal participation by contribution of Federal funds toward first costs and costs of periodic nourishment and maintenance. ALAMO LAKE, BILL WILLIAMS RIVER, AZ Multiple-purpose dam and reservoir. H. Doc. 625, 78th Cong., 2d sess. 33-20 LOS ANGELES, CA, DISTRICT TABLE 33-B (Cont'd) AUTHORIZING LEGISLATION See Date of Section in Authorizing Text Act Project and Work Authorized Documents 13. Aug. 13, 1968 14A. Oct. 27, 1965 Mar. 7, 1974 14B. May 17, 1950 14C. Oct. 27, 1965 14D. June 30, 1948 14E. July 24, 1946 15. June 22, 1936 May 15, 1937 June 28, 1938 Aug. 18, 1941 Dec. 22, 1944 July 24, 1946 May 17, 1950 Sep., 1954 July 3, 1958 July 14, 1960 CUCAMONGA CREEK, SANTA ANA RIVER BASIN, CA Debris-collection facilities, with a system of channels, and a diversion system. INDIAN BEND WASH, GILA RIVER BASIN, AZ Channel, levees, a siphon system, and transition works. Cost of siphon system borne by United States. PAINTED ROCK DAM (GILA RIVER), GILA RIVER BASIN, AZ Dam and flood control basin. PHOENIX AZ., AND VICINITY (INCLUDING NEW RIVER), GILA RIVER BASIN Detention basins, diversion channels, and channel improvements. TUCSON DIVERSION CHANNEL, GILA RIVER BASIN, AZ Channel improvements. WHITLOW RANCH DAM, QUEEN CREEK, GILA RIVER BASIN, AZ Dam and flood control basin. LOS ANGELES COUNTY DRAINAGE AREA, CA Reservoirs and flood channels for flood control and related urposes at an estimated construction cost not to exceed 70 million. Added flood channels on Ballona Creek and tributaries to project. Provision of lands, easements, and rights-of-way and relocations by Federal Government instead of by local interests. (Resultant additional cost to the United States, $12,541,000.) Project extended to include additional flood control reservoirs, flood control channels, and debris basins for flood control and related purposes. Also authorized to be appropriated $25 million for further accomplishment of plan. Authorized to be appropriated an additional $26 million for prosecution of comprehensive plan approved in Flood Control Act of Aug 18, 1941. Authorized to be appropriated an additional $25 million for further prosecution of comprehensive plan. Rio Hondo channel improvement, Whittier Narrows Reservoir to Los Angeles River (in lieu of enlarging channel and bridges on San Gabriel River downstream from reservoir). Also authorized to be appropriated an additional $40 million for further prosecution of comprehensive plan. Authorized to be appropriated an additional $12,500,000 for further prosecution of comprehensive plan. Authorized to be appropriated an additional $44 million for further prosecution of comprehensive plan. Authorized to be appropriated an additional $32 million for further prosecution of comprehensive plan. H. Doc. 323, 90th Cong., 2d sess. H. Doc. 303, 88th Cong., 2d sess. None H. Doc. 331, 81st Cong., 1st sess. H. Doc. 216, 89th Cong., 1st sess. H. Doc. 274, 80th Cong., 1st seas. H. Doc. 220, 80th Cong., 1st sess. None None None H. Doc. 838, 76th Cong., 3d sess. None None None None None None 33-21 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 33-B (Cont'd) AUTHORIZING LEGISLATION See Date of Section in Authorizing Text Act Project and Work Authorized Documents Oct. 28, 1962 Dec. 30, 1968 June 18, 1965 16. Feb. 7, 19858 17. Oct. 27, 1965 18. July 14, 1960 19. May 17, 1950 Authorized to be appropriated an additional $3,700,000 for further prosecution of comprehensive plan. Authorized to be appropriated an additional $30 million for further prosecution of comprehensive plan. In addition to all previous authorizations, completion of improvements under the comprehensive plan for flood control in the Los Angeles River Basin at a presently estimated cost of $31 million for completion. LOS COCHES CREEK, SAN DIEGO COUNTY, CA Channel improvements. LYTLE AND WARM CREEKS, SANTA ANA RIVER BASIN, CA Channels and levees. MOJAVE RIVER DAM, MOJAVE RIVER BASIN, CA Dam and reservoir, and an earthfill dike. PINE AND MATHEWS CANYONS DAMS, COLORADO RIVER BASIN, NV Dams and flood control basins. None None None None S. Doc. 53, 89th Cong., 1st sess. H. Doc. 164, 86th Cong., 1st sess. H. Doc. 530, 81st Cong., 2d sess. 20. May 17, 1950 21. June 22, 1986 June 28, 1988 Aug. 18, 1941 Dec. 22, 1944 July 8, 1968 22. May 15, 1985' SAN JACINTO RIVER LEVEE AND BAUTISTA CREEK CHANNEL, SANTA ANA RIVER BASIN, CA Levees along Mill Creek in zone 1; a system including H. Doc. 135, 81st Cong., levees and channel improvements generally along Devil, 1st sess. East Twin, and Warm Creeks in zone 5* levees along Santa Ana River near Riverside in zone 7; and levees along Bautista Creek and San Jacinto River in zone 9, at an estimated construction cost not to exceed $17,577,000. SANTA ANA RIVER BASIN (AND ORANGE COUNTY), CA Reservoirs and flood channels for flood control and None related purposes for protection of metropolitan area of Orange County, at an estimated construction cost not to exceed $13 million. San Antonio and Chino Creeks channel portion of H. Doc. 688, 75th Cong., improvement. Authorized to be appropriated $6,500,000 3d sess. for initiation and partial accomplishment of plans for those creeks. Rescinded provisions of Flood Control Act of 1936 providing that local interests pay for relocations, lands, easements, and rights-of-way. (Estimated resultant additional cost to United States, ,500,000.) Authorized to be appropriated an additional $2,500,000 for None prosecution of projects approved in above flood control acts. Authorized to be appropriated an additional $10 million H. Doe. 534, 78th Cong., for prosecution of proects adopted in above-mentioned 2d sees.1 flood control acts, including projects on Iytle and Cajon Creeks for local flood protection at San Bernardino and Colton, CA. Authorized to be appropriated an additional $8 million None for prosecution of projects approved in abovementioned flood control acts. SOUTH FORK OF THE SANTA CLARA RIVER, SANTA CLARITA VALLEY, CA Debris basin, channel improvements, bridges, and mitigation measures. None 33-22 LOS ANGELES, CA, DISTRICT TABLE 33-B (Cont'd) AUTHORIZING LEGISLATION See Date of Section in Authorizing Text Act Project and Work Authorized Documents SWEETWATER RIVER, SWEETWATER RIVER BASIN, CA 23g.Aug. 13, 1968 Channel improvement, as part of a combined flood H. Doc. 148, 90th Cong., control and highway project. 1st sess. TELEGRAPH CANYON CREEK, CHULA VISTA, CA 24. Feb. 7, 1985 Channel improvements and beautification. None WEST MAGNESIA CANYON CHANNEL, RANCHO MIRAGE, CA 25. Feb. 7, 1985 Debris basin, channel improvements, energy dissipator, None and preservation and enhancement of wildlife values. 1. Contains latest published map. 3. Date approved by Chief of Engineers under provisions 2. Included in the emergency relief program, May 28, of section 205, Public Law 80-858, as amended. 1935. TABLE 33-C OTHER AUTHORIZED NAVIGATION PROJECTS For Last Cost to Sep. 80, 1985 Full Report See Annual Operation and Project Status Report For Construction Maintenance Dana Point Harbor, CA Completed 1984 $4,737,5501 $545,205 Marina del Rey, Los Angeles County, CA Completed 1981 4,238,7528 1,323,0374 Newport Bay Harbor, CA Inactive 1982 796,8976 609,569' Port Hueneme, CA Completed (part) 1984 1,480,4667 1,242,713' & Deferred (part) Port San Luis, CA Completed & 1984 1,221,8489 846,61410 Active (mod) Redondo Beach Harbor (King Harbor), CA Completed 1984 4,766,89811 1,287,81212 1. Excludes $4,777,000 required contributed funds and Coast Guard costs. 2. Includes $40,396 for reconnaissance and condition surveys. 3. Excludes $4,238,752 required contributed funds; $1,843,146 other contributed funds; and Coast Guard costs. 4. Includes $76,282 for reconnaissance and condition surveys. Excludes $114,000 required contributed funds. 5. Public Works Administration funds. Excludes $796,897 required contributed funds and $1,100 preauthorization costs. 6. Includes $125,646 for reconnaissance and condition survey costs since FY 1958. Excludes $7,000 other contributed funds. Includes $11 expended in FY 1985. 7. Excludes $57,609 other contributed funds. 8. Includes $61,068 for reconnaissance and condition surveys. 9. Includes $568,417 for new work prior to modification by 1965 River and Harbor Act. Excludes Coast Guard costs. 10. Includes $54,715 for maintenance for project prior to modification by 1965 River and Harbor Act and $18,958 for reconnaissance and condition surveys. 11. Excludes Coast Guard costs. 12. Includes $20 517 for reconnaissance and condition survey costs since FY 1958. 33-23 TABLE 33-D REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 OTHER AUTHORIZED BEACH EROSION CONTROL PROJECTS For Last Cost to Sep. 80, 1985 FullR Report See Annual Operation and Project Status Report For Construction Maintenance Anaheim Bay Harbor, Orange County, CA1 Completed 1967 $89,119 - Bird Rock area, La Jolla, San Diego County, CA2 Completed 1967 25,881' - Coast of California, Point Mugu to San Pedro breakwater, CA Completed 1972 1,258,5944 - Doheny Beach State Park (Doheny State Beach), CA Completed 1968 578,7176 - Las Tunas Beach, San Diego County, CA Active 1976 107,484 - Ocean Beach San Diego County, CA* Completed 1960 7,912 - Oceanside, San Diego County, CA Completed 1982 4,365,155 - San Diego (Sunset Cliffs), CA Active 1979 865,000' - Ventura-Pierpont area, CA &Co Dmepelrerteedd ((ppaarrtt)) 1969 715,8190 - 1. The project authorized by the Act of Congress of October 23, 1962, H. Doc. 602, 87th Cong., 2d sess., in lieu of part of the original Anaheim Bay Harbor prject is covered under San Gabriel River to Newport Bay (Surfside-Sunset and Newport Beach), Orange County, CA. 2. Authorized by Chief of Engineers under authority of section 108, Public Law 87-874. 3. Excludes $75,614 required contributed funds. 4. Excludes $1,238,418 required contributed funds. 5. Excludes $431,260 required contributed funds. 6. Plant in service. 7. Excludes $604 817 other contributed funds. Includes $13,907 expended in PY 1985. 8. Excludes $180,438 required contributed funds. 9. Excludes $117,406 other contributed funds for beachnourishment betterments and $618,949 required contributed funds. 33-24 LOS ANGELES, CA, DISTRICT TABLE 33-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS Project Allenville, AZ' Status Completed For Last Full Report See Annual Report For 1984 Cost to Sep. so, 198 Operation and Construction Maintenance $3,000,000s- City Creek levee, San Bernardino County, CAI Gila River Basin, AZ: Camelaback Dam (Gila River) Gila and Salt Rivers levee and channel improvements Lower Gila River levee and channel improvements (Gila River and tributaries downstream from Painted Rock Dam) Middle Gila River channel improvements, upper end of Safford Valley to Buttes damsite Camelsback damsite to Salt River) Pinal Creek channel improvements (Globe) Santa Rosa Wash (Tat Momolikot Dam and Lake St. Clair) Goleta, CA, and vicinity Holbrook levee, Little Colorado River, Colorado River Basin, AZ Needles, San Bernardino County, CAI Oro Grande Wash channel improvements, Mojave River Basin, CA' Quail Wash levee, Joshua Tree, San Bernardino County, CAl Ridgeerest, Kern County, CAl Rose Creek channel improvements, San Diego, CA' San Diego River (Mission Valley), San Diego River Basin, CA San Luis Rey River, San Luis Rey River Basin, CA Santa Ana River Basin, CA: Devil, East Twin and Warm Creeks channel improvements and Lytle Creek levee Mill Creek levees Riverside levees Santa Ana River Basin (and Orange Count), CA: AliCreek Dam San Juan Dam Trabsco Dam Santa Clara River levee improvement, Santa Clara River Basin, CA Santa Maria Valley levees, Santa Maria River Basin, CA Santa Paula Creek channel and debris basins (including Mud Creek), Santa Clara River Basin, CA Completed Deferred Active (part) & Deferre (part) Inactive Active Deferred Completed Active Completed Completed Completed Completed Terminated Completed Inactive Active Completed Completed Completed Inactive Inactive Inactive Completed Completed Active 1963 1966 1975 1970 1968 1982 1982 1950 1978 1970 19783 1972 1978 1982 1962 1961 1969 1950 1961 1984 400,000' 78,201' 2,418,051 402,867 121,509' 10,218,885' 500,000 885,000 1,000,000' 1,000,000' 212,745 196,194 982,432' 1,708,487 1,487,974' 7,758,98710 617,890" 2,104,478 67,861 2,126,672 10,078,8756" 4,710,672" 883-25 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 33-E (Cont') OTHER AUTHORIZED FLOOD CONTROL PROJECTS For Last Cost to Sep. 80, 1985 Full Report See Annual Operation and Project Status Report For Construction Maintenance Sespe Creek at Fillmore, Ventura County, CA' Completed 1984 3,999,9881u Tijuana River Basin, CA Completed 1979 1,703,08116 University Wash and Spring Brook, Riverside, CA Inactive 1975 213,313- Ventura River Basin, CA: Stewart Canyon debris basin and channel Completed 1964 989,908" - Ventura River levee Completed 1950 1,849,63817 - Whitewater River Basin, CA: Banping levee-San Gorgonio River, Riverside County Completed 1966 97,868 - Chino Canyon improvements, Palm Springa Completed 1973 819,8781- Tahchevah Creek detention basin and channel improvetnents Completed 1967 1,420,66552 - Tahquitz Creek Inactive 1974 1,063,600 - Winslow (tributaries of Little Colorado River), Little Colorado River Basin, AZ Completed (part) 1978 1,831,300- & Deferred (part) 1. Authorized by Chief of Engineers under authority of section 205 Public Law 80-858, as amended. 2. Excludes $187,965 required contributed funds. 8. Excludes $371,058 other contributed funds. 4. Advance planning only. 5. Includes -$255 expended in FY 1985. 6. Excludes $619,912 required contributed funds and $91,160 other contributed funds. 7. Excludes $514,806 required contributed funds and $176,296 other contributed funds. 8. Excludes $251,000 required contributed funds and $154,73388 other contributed funds. 9. Includes $73,974 expended in FY 1985. 10. Excludes $200,000 required contributed funds and $1,641,668 other contributed funds. 11. Excludes $6,830 other contributed funds. 12. Excludes 106 364 other contributed funds. 18. Excludes non-Iederal costs of $295,000 for local cooperation items not required and $49,458other contributed funds. 14. Excludes 483516 required contributed funds. 15. International Boundary and Water Commission funds. 16. Excludes $179,148 other contributed funds. 17. Includes $6,000 Code 710 funds since FY 1977. Excludes $17,006 other contributed funds. 18. Excludes $8,718 required contributed funds and $58,470 other contributed funds. 19. Excludes $74,718 required contributed funds. 33-26 TABLE 88G LO ANGELES, CA, DISTRICT DEAUTHORIZED PROJECTS For Iat Full Report Date Federal Contributed See Annual and Punds Funds Project Report For Authority Expended Expended Hodges Dam, San Dieguito River Basin, CA 1968 1978 -- See. 12, Public Law 98-251 Las Vegas Wash tributaries Colorado River Basin, NV 1964 1977 $296,191 - Sec. 12, Public Law 98-251 Villa Park Dam, Santa Ana River Basin (and Orange County), CA 1978 - - See. 12, Public Law 98-251 33-27 REPORT OF THE CHIEF OF ENGINEERS, U.8. ARMY 1985 TABLE 33-H LOS ANGELES COUNTY DRAINAGE AREA CA: LATEST APPROVED ESTIMATED FIRST COSTS FOR ALL UNITS OF IMPROVEMENT UNDER EXISTING PROJECT (See Section 15 of Text) Latest Approved Estimated Cost 1976' Project Units Federal LecaP Total UNITS IN $70 MILLION PROJECT Los Angeles River Basin: Compton Creek, Los Angeles River to Hooper Ave. storm drain $2,510,500 $2,510,500 Haines Canyon 524,000 - 524,000 Hansen Dam 11,848,000 - 11,848,000 Los Angeles River channel: Lankershim Blvd. to Steward and Gray Rd. 40,807,800 - 40,807,800 Los Angeles River channel, Long Beach Blvd. 84,20 - 84,00 Sepulveda Dam 6,657,000 - 6,657,000 Sycamore Wash 24,000 - 24,000 Verdu Wash, Concord St. to upper Canada bridge 1,087,000 - 1,087,000 San Gabriel River Basin: San Gabriel River channel: San Gabriel Canyon to Santa Fe Dam 810,800 - 810,800 Approach channel to Santa Fe Dam (remedial work) 951,900 - 951,900 Santa Fe Dam to Walnut Creek 382,800 - 82,800 Santa Fe Dam 12,647,000 - 12,647,000 Rio Hondo Basin: Alhambra Wash 1,109,000 - 1,109,000 Ballona Creek Basin: Ballona Creek channel and jetties 1,280,000 - 1,280,000 Subtotal 79,818,000 - 79,818,000 UNITS OUTSIDE $70 MILLION PROJECT Los Angeles River Basin: Blanchard Canyon 682,000 $476,000 1,168,000 Blue Gum Canyon 588,000 288,000 766,000 Burbank-Eastern system 7,149,000 1,860,000 8,999,000 Burbank-Western system (lower) 1,279,000 268,000 1,547,000 Burbank-Western system (upper) 4,980,000 2,959,000 7,889,000 Caballero Creek 1,484,200 498,000 1,977,200 Compton Creek: LosAngeles River to Hooper Ave. storm drain 149,000 - 149,000 Hooper Ave. storm drain to Main St. 1,062,000 457,000 1,509,000 Dead Horse Canyon and Royal Blvd. channel 664,000 316,000 980,000 Lopez Canyon diversion 748,500 666,000 1,408,500 Lopez Dam 729,000 - 729,000 Los Angeles River channel: Owenamouth Ave. to Lankershim Blvd.8,15,800 4,247,000 12,82,800 Lankershim Blvd. to Stewart and Gray Rd. 9,202,15,800 - 0 9,202,100 Steward and Gray Rd. to Santa Ana Branch, Pacific Electric railway bridge 5,860,900 81,000 5,941,900 Santa Ana Branch, Pacific Electric railway bridge to Pacific Ocean 32,612,000 9,178,000 41,785,000 Paeoima Wash channel 8,178,100 1,306,000 4,484,100 Tujunga Wash channel 7,822,900 2,557,000 9,879,900 Verdugo Wash, upper Canada bridge to debris basin 685,000 368,000 998,000 Wilson Canyon and Mansfield St. channel 3,917,500 857,000 4,774,500 SaWn Ginaebryr iCela Rniovenr Basin: 418,000 265,000 678,000 Coyote Creek (including North Fork) 18,802,800 8,426,000 27,228,800 Emerald Wash and Live Oak Wash 1,668,600 1,182,000 2,840,600 Marshall Creek 2,577,900 968,000 3,545,900 San Gabriel River channel: Santa Fe Dam to Whittier Narrows Dam 5,748,800 1,797,000 7,545,800 Whittier Narrows Dam to Pacific Ocean 20,887,200 3,108,000 23,995,200 Thompson Creek and San Jose Wash (including San Jose Creek) 21,274,600 6,095,000 27,869,600 Walnut Creek inlet channel 2,879,000 1,091,000 3,970,000 Walnut Creek system 17,232,600 8,715,000 25,947,600 Whittier Narrows Dam 82,254,000 88,000 32,292,000 38-28 LOS ANGELES, CA, DISTRICT TABLE 38-H (Cont'd) LOS ANGELES COUNTY DRAINAGE AREA CA: LATEST APPROVED ESTIMATED FIRST COSTS FOR ALL UNITS OF IMPROVEMENT UNDER EXISTING PROJECT (See Section 15 of Text) Latest Approved Esimated Cost 1976' Project Units Federal Lecals Total Rio Hondo Basin: Arcadia Wash system Eaton Wash Rio Hondo channel: Peck Rd. to Rosemead Blvd. (upper) Whittier Narrows Dam to Los Angeles River (lower) Rubio Canyon diversion Santa Anita Wash Sawpit Wash Sierra Madre Villa channel Sierra Madre Wash Ballona Creek Basin: Ballon Creek channel Benedict Canyon system Centinela Creek Sawtelle-Westwood system (including Sepulveda channel) Subtotal Grand total for comprehensive plan 1. Excludes estimated cost for Code 710 funds and estimated cost for minor rehabilitation. 2. Approved by Los Angeles County Flood Control District as of September 80, 1976, except for Walnut Creek system 5,286,800 4,25,100 4,412,000 8,165,000 1,066,400 8,045,700 2,848,600 781,400 1,782,000 746,600 15,284,900 4,088,800 9,620,700 274,736,000 854,554,000 1,898,000 1,194,000 560,000 2,565,000 254,000 484,000 745,000 866,000 248,000 8,785,000 4,788,000 1,492,000 76,800,000 7,129,800 5,419,100 4,968,000 10,780,000 1,30,400 88,,40799,,870000 1,147,400 1,980,000 746,600 19,069,900 8,871,800 11,112,700 851,06,000 76,800,000 480,854,000 channel estimate, which was increased by $42,000 to permit rounding of overall non-Federal estimate to three sigmcant figures. 33-29 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 88-I SANTA ANA RIVER BASIN (AND ORANGE COUNTY), CA: LATEST APPROVED ESTIMATED FEDERAL FIRST COST FOR ALL UNITS - (See Section 21 of Text) Estimated Cot Project Total Latest Revision Date ACTIVE UNIT' Completed: Bre Dam $1,189,068 * Fullerton Dam 411,076' Iytle and Cajon Creeks channel improvements 7,612,000 * Prado Dam 9,478,273' San Antonio and Chino Creeks channel 10,924,170 * San Antonio Dam 7,001,176' Completed Except for Minor Completion Items: Carbon Canyon Dam and channel 5,150,000' 1961 INACTIVE UNITS' Aliso Creek Dam 840,000 1954 San Juan Dam 5,960,000 1954 Trabuco Dam 2,190,000 1954 DEAUTHORIZED UNIT Villa Park Dam 2,270,000 1954 1. For details~ see section 21 of text. 2. Not includin estimated cost of Code 710 funds. 8. Plant in servce. 4. Includes $5,000 working funds. 5. For additional information, see "Other Authorized Flood Control Projects." 3-30 LOS ANGELES, CA, DISTRICT TABLE 3388-J INSPECTION OF COMPLETED FLOOD CONTROL PROJECTS (See Section 26 of Text) Project Date Banning levee-San Gorsgonio River, Whitewater River Basin, CA Chino Canyon improvements, Palm Springs, Whitewater River Basin, CA City Creek levee, Santa Ana River Basin, CA Devil, East Twin, and Warm Creeks channel improvements and Iytle Creek levee, Santa Ana River Basin, CA Los Angeles County drainage area, CA, channels Lytle and Cajon Creeks channel improvements, Santa Ana River Basin (and Orange County), CA Mill Creek levees, Santa Ana River Basin, CA Needles, San Bernardino County, CA Oro Grande Wash channel improvements, Mojave River Basin, CA Quail Wash levee, Joshua Tree, San Bernardino County, CA Riverside levees, Santa Ana River Basin, CA Rose Creek channel improvements, San Diego, CA San Diego River channel and levees, San Diego River Basin, CA San Jacinto River levee and Bautista Creek channel, Santa Ana River Basin, CA April 1985 April 1985 May 1985 May 1985 April, June July, SeM 1985 May 1985 May 1965 April 1985 May 1985 May 1985 April 1985 June 1985 June 1985 April 1985 FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION Flood Control Activities Pursuant to Section 205, Public Law 80-858, As Amended (Preauthorization) TABLE 88-K (See Section 28 of Text) Project Fsceal Year Costs Ephriam Canyon Wash, Nogales, AZ $91,515 Mission Zanja Creek, CA 269,866 Newhall Creek, Newhall, CA 2,988 33-31 SAN FRANCISCO, CA, DISTRICT* This district comprises the Klamath River Basin in southern Oregon and portions of northern and western California consisting of drainage basins tributary to the Pacific Ocean from the Oregon-California State line on the north to Cape San Martin, CA, on the south, except for basins tributary to the San Francisco Bay system which lie east of the Benicia-Martinez Bridge. IMPROVEMENTS Navigation Page 1. Fisherman's Wharf Area, San Francisco Harbor, CA .............. 34-1 2. San Francisco Bay to Stockton, CA (John F. Baldwin and Stockton Ship Channels).......................... 34-2 3. San Francisco Bay and Delta Model, CA ........................ 34-2 4. Reconnaissance and Condition Surveys ................................ 34-2 5. Navigation Work under Special Authorization........................... 34-2 Flood Control 6. Inspection of Completed Flood Control Projects......................... 34-2 7. Flood Control Work under Special Authorization........................... 34-3 Navigation 1. FISHERMAN'S WHARF AREA, SAN FRANCISCO HARBOR, CA Location. Fisherman's Wharf is located on San Francisco Bay on the northern waterfront of the City of San Francisco, approximately 2-1/2 miles east of the Golden Gate Bridge. (See USGS Quad Sheet San Francisco North, Calif. N3745-W12222.5/7.5) Existing Project. The project consists of a concrete sheet pile breakwater starting 150 feet to the west of Hyde Street Pier; curving around the end of Hyde Street Pier and extending in an easterly direction to an extension of the east fender line of Pier 45. The entrance is to be a 165-foot channel between the breakwater and the end of Pier 45. The total length of this sheet pile breakwater is 1,509 feet. In addition there are two segmented breakwaters (28-foot solid walls with 6-foot openings), one 150 feet long extending in a northerly direction in the abandoned slip at the end of Pier 45, and General Investigations 8. Surveys ................................. 9. Collection and Study of Basic Data ........ 10. Continuation of Planning and Engineering........................ 11. Advance Engineering and Design........ Tables Table 34-A Table 34-B Table 34-C Table 34-D Table 34-E Table 34-F Table 34-G Page 34-3 34-3 34-3 34-3 Cost and Financial Statement .................... 34-4 Authorizing Legislation ........ 34-7 Other Authorized Navigation Projects ............ 34-7 Other Authorized Beach Erosion Control Projects ........ 34-7 Not Applicable Not Applicable Deauthorized Projects .......... 34-8 the second is a 250-foot section 250 feet from the bayward end of, and on the west side of Pier 45. The plan also includes two 10-foot wide pile caps which may be used as walkways for the purpose of recreational pier fishing. Access is to be constructed to the 150-foot segmented breakwater, and the second, included in Phase II construction, will be access to the 1,509-foot solid breakwater. The estimated total cost for the project is $9,600,000 of which $8,900,000 is Federal cost and $700,000 is non-Federal cost. Construction contract was awarded in February 1985 to Riedel International, Inc. of Portland, OR. Total contract award was $7,887,000. Local cooperation. The Agreement of Local Cooperation, along with estimated costs, has been negotiated with, and accepted by, the local sponsor. The 221 Agreement was signed by the local sponsor on 13 November 1984. Terminal facilities. Project will protect existing commercial and recreational waterfront structures: 34-1 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 commercial fishing fleet and fish handling structures; recreational small craft harbor; and Hyde Street Pier used for historic ship berthing. Operations during fiscal year. New Work: Construction contract awarded. 2. SAN FRANCISCO BAY TO STOCKTON, CA (JOHN F. BALDWIN AND STOCKTON SHIP CHANNELS) Location. On navigation channels extending from entrance to San Francisco Bay to vicinity of Concord through San Francisco, Marin, Contra Costa, and Solano Counties. (See Coast and Geodetic Charts 5527 and 5532-5534 for respective areas.) Existing project. Project provides for modification of existing San Francisco Harbor, Richmond Harbor, San Pablo Bay and Carquinez Strait, Suisun Bay Channel to vicinity of Concord to provide depths of 55 feet for San Francisco Bar Channel, 45 feet (currently 35 feet) for main internal bay channels upstream to vicinity of Concord; enlargement and deepening to 45 feet (currently 35 feet) of maneuvering areas adjacent to major petroleum refinery terminals along channel route; widening Suisun Bay Channel. San Francisco Harbor Main Channel was completed February 1974. Approved cost estimate (1983) of Federal cost (Corps), see Sacramento District Annual Report. Existing project was adopted by 1965 River and Harbor Act (H. Doc. 208, 89th Cong., 1st sess., contains latest published map). Local cooperation. See Sacramento District Annual Report. The local sponsor, Contra Costa County, supports the project. Terminal facilities. See Port Series No. 30, revised 1983, No. 31, revised 1982, and No. 32, revised 1975, titled respectively: "The Ports of San Francisco, Redwood City, and Humboldt Bay, Calif."; "The Ports of Oakland, Alameda, Richmond, and Ports on Carquinez Strait, Calif."; and "The Ports of Sacramento, Stockton, Pittsburg, and Antioch, Calif." Facilities are considered adequate for existing commerce and will be adequate for future commerce upon completion of new terminal facilities. Operations during fiscal year. New Work: Construction and continued planning activities. 3. SAN FRANCISCO BAY AND DELTA MODEL, CA Location. The model, including a regional visitor center, is located in Sausalito, CA, adjacent to San Francisco Bay about two miles north of the Golden Gate Bridge. Existing project. The San Francisco Bay/Delta Model, which covers 17 miles of the Pacific Ocean beyond Golden Gate, all of San Francisco Bay proper, San Pablo Bay, Suisun Bay, and all of the Sacramento- San Joaquin Delta east of Suisun Bay to the cities of Sacramento on the northeast and Stockton and Tracy on the south, was constructed in a rehabilitated warehouse at Sausalito, CA, as a part of the San Francisco Bay and Tributaries, California, Study authorized by the River and Harbor Act of May 17, 1950 (PL 81-516, Section 110). The model was authorized as an operation and maintenance project in the Water Resources Development Act of 1974 (PL 93-251, Section 8). The model successfully reproduces to the proper scale the rise and fall of the tide, flow and currents of water, salinity intrusion, and trends in disposition of sediments. It is a useful tool to examine forces existing in the bay and estuarine system and to predict results of proposed changes. Local cooperation. None required. Operations during fiscal year. Maintenance: Operation and maintenance of the model continues. Historical summary. Original model construction was initiated 1956 and completed 1957. The addition of the Sacramento-San Joaquin Delta to the original model was initiated 1966 and completed 1969. The central exhibits were completed in December 1981. Continued testing of proposals affecting the environmental quality of the region including, but not limited to: salinity intrusion, dispersion of pollutants, water quality, improvements for navigation, dredging, bay fill, physical structures, other shoreline changes. Total cost of regional visitor exhibits and model as of September 30, 1985, was $11,635,401, of which $5,183,818 was for the regional visitor center, $870,587 for exhibits, and $5,580,996 for maintenance. 4. RECONNAISSANCE AND CONDITION SURVEYS Reconnaissance and condition surveys of channels to be dredged in years other than FY 85 were conducted on the following projects: Bodega Bay; Napa River; Petaluma River; Richardson Bay Channel; San Leandro Marina; San Rafael Creek; and Suisun Channel, all in California. Fiscal year cost was $143,198. 5. NAVIGATION WORK UNDER SPECIAL AUTHORIZATION Navigation activities pursuant to section 107, Public Law 86-645 (preauthorization). Fiscal year cost for preauthorization studies was $219,168 for Larkspur Ferry, Marin County, CA. 6. INSPECTION OF COMPLETED FLOOD CONTROL PROJECTS Section 3, Flood Control Act of June 22, 1936, as amended and supplemented, included requirement that local interests maintain and operate completed flood control works in accordance with regulations prescribed by the Secretary of War. Inspections made throughout the year to determine effectiveness of operation and 34-2 SAN FRANCISCO, CA, DISTRICT maintenance by local interests of completed local protection projects and works constructed under emergency and special authorities of Sections 205 and 208 of the 1948 Flood Control Act, Section 14 of the 1946 Flood Control Act, and Public Law 99, 84th Congress. Fiscal year cost was $159,543. Total cost to September 30, 1985 was $969,393. Projects inspected included Alameda Creek, March 1985; Butte Creek, August 1985; Canyon Creek, August 1985; Coffee Creek, August 1985; Colma Creek, May 1985; Corte Madera Creek, April 1985; Coyote Creek, April 1985; East Weaver Creek, August 1985; Eel River at Sandy Prairie, June 1985; Klamath River, August 1985; Mad River at Blue Lake, May 1985; Mark West Creek, July 1985; Meiss Lake, August 1985; Pajaro River, April 1985; Pinole Creek, March 1985; Redwood Creek, May 1985; Rheem Creek, March 1985; Rodeo Creek, March 1985; Russian River, August 1985; Salinas River, August 1985; San Leandro Creek, March 1985; San Lorenzo Creek, March 1985; San Lorenzo River, January 1985; Santa Rosa Creek, July 1985; Smith River, April 1985; Sonoma Creek, July 1985; Van Duzen River, May 1985 and Wildcat Creek, July 1985. 7. FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION Flood Control activities pursuant to Section 205, Public Law 858, 80th Congress, as amended (preauthorization). Fiscal year costs were $99,658 for preauthorization studies of which $5,459 was for Papermill Creek, Point Reyes, CA; $21,668 for Pescadero and Butano Creeks, CA; $6,900 for Redwood Creek, San Mateo County, CA; and $65,631 for Soquel Creek, Santa Cruz County, CA. Emergency flood control activities-repair, flood fighting and rescue work (Public Law 99, 84th Congress, and antecedent legislation). Fiscal year costs of $1,234,693 were incurred for emergency flood control activities, of which $377,519 was for disaster preparedness; $80 for emergency operations; and $857,094 for rehabilitation. Emergency bank protection (Section 14, 1946 Flood Control Act, Public Law 526, 79th Congress). Fiscal year costs were $407,181 for emergency bank protection of which $4,215 was for Emeryville and Frontage Road, CA; $7,056 for Emeryville, Alameda, CA; $7,500 for Llagas Creek, Gilroy, CA; $9,500 for Marina County WWTP, CA; $1,300 for Powell Street, Emeryville, CA; $2,480 for Richardson Bay, Belvedere, CA; $25,137 for River Road, Monterey County, CA; $249,242 for San Francisquito Creek, Site 74, CA; $760 for Schulte Road Bridge, Carmel River, CA; $99,991 for Willow County, Water District Wells, Mendocino, CA. General Investigations 8. SURVEYS Fiscal year costs for surveys were $1,218,000, of which $264,665 was for navigation; $913,347 for flood damage prevention; $37,044 for inventory of dams; and $2,944 for coordination with other agencies. 9. COLLECTION AND STUDY OF BASIC DATA Fiscal year total costs of $24,361 were incurred, of which $22,423 was for flood plain management service program and $1,938 was for hydrologic studies. 10. CONTINUATION OF PLANNING AND ENGINEERING Fiscal year total costs were $271,320 of which $104,330 was for Fisherman's Wharf, CA, $22,013 for Oakland Inner Harbor, CA; $50,000 for Oakland Outer Harbor (Deepening), CA, and $94,977 for Richmond Harbor, (Deepening), CA. 11. ADVANCE ENGINEERING AND DESIGN NOYO RIVER AND HARBOR, CA Noyo River rises in the Coast Range, flows westerly, and empties into Noyo Harbor. Noyo Harbor is a cove on the California Coast about 87 miles south of Humboldt Bay and 135 miles northwest of San Francisco. The 1962 Rivers and Harbors Act, modified by the 1976 Water Resources Development Act, authorized up to two breakwaters as necessary to provide protection. The 1976 WRDA authorized construction of additional channel improvements. Recommended plans of improvement for the breakwater and channel improvement were previously considered as a single project. Due to significant differences in the time required for planning and construction, each part is now reported separately. The plans of improvement for Noyo River and Harbor (Breakwater), CA, provide for one or two breakwaters immediately west of the entrance channel in Noyo Harbor. Estimated preconstruction planning cost is $1,560,000. Total costs during the fiscal year were $105,670 with General Investigation funds. Planning is about 50 percent complete. Model studies, using a physical model to test alternative plans, were initiated in FY 84. The plan of improvement for Noyo River and Harbor (Channel Extension), CA, provides for a 60-foot wide channel, 7 feet deep, for a distance of about 3,000 feet upstream from the end of the existing Federal project to the Dolphin Isle Marina. Estimated preconstruction planning cost is $580,000. Total costs during the fiscal year were $10,078 with General Investigation funds. 34-3 TABLE 34-A REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 COST AND FINANCIAL STATEMENT See Section in Text Project Bodega Bay, CA Crescent City Harbor, CA Fisherman's Wharf Area, San Francisco Harbor, CA Humboldt Harbor and Bay, CA Moss Landing Harbor, CA Napa River, CA Noyo River and Harbor, CA Oakland Harbor, CA Petaluma River, CA Funding New Work Approp. Cost Maint. Approp. Cost Major rehab. Approp. Cost New Work Approp. Cost Maint. Approp. Cost Major rehab. Approp. Cost New Work Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp.\ Cost New Work Approp. Cost Maint. Approp. Cost Minor rehab. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost Total Cost to FY 82 FY 83 FY 84 FY 85 Sep. 30, 1985 129,000 - - - 1,226,7651 2 28,721 99,249 4,314 - 1,226,3651 s - - 16,270 204,651 1,015,3154 - - 16,270 179,999 990,6634 -- - - 397,7795 - - - 397,7796 1,070,000 802,000 - -44,000 9,454,9726 549,307 419,303 850,808 11,409 9,452,9786 2,117,000 2,875,300 230,000 1,093,278 13,377,2527 1,677,366 645,408 2,333,215 1,657,383 13,366,2277 -- - - 525,0008 - - - 525,0008 - - 350,000 3,000,000 3,350,00041 - - 180,543 1,138,269 1,138,81241 - - - 9,847,2999 40 - - - 9,847,2999 40 2,123,000 8,562,200 1,475,009 6,107,060 49,697,941 10 40 2,098,890 2,683,029 6,304,195 6,983,429 49,479,8390 40 -- - - 338,21540 - - - 338,21540 256,000 59,000 448,000 161,583 3,930,21412 40 520,680 47,971 427,295 164,383 3,899,31412 40 -- - - 1,021,27413 o40 -- - - 1,021,2741's 40 100,000 72,000 38,254 -426 1,813,63713 14 40 527,787 240,156 43,816 -426 1,813,637's13 14 40 204,000 79,000 275,000 - 1,521,48215s 16 123,148 181,133 156,999 115,747 1,508,23115s 17 279,000 826,900 530,000 405,000 5,655,65418 19 264,329 314,635 991,649 470,898 5,649,24218 19 - - - 222,81020 40 -- - - 222,81020 40 - - - 9,646,98421 40 -- - - 9,646,98421 40 1,191,000 1,796,000 1,294,000 1,325,973 27,642,24622 40 1,185,137 1,771,880 1,251,503 1,414,766 27,628,52122 40 - - - 297,14623 40 - - - 297,14623 40 1,560,000 670,000 1,025,407 26,272 7,981,83824 40 76,490 912,547 1,797,546 446,628 7,927,18024 40 34-4 SAN FRANCISCO, CA, DISTRICT TABLE 34-A (Cont'd) COST AND FINANCIAL STATEMENT See Section Total Cost to in Text Project Funding FY 82 FY 83 FY 84 FY 85 Sep 30, 1985 Redwood City Harbor, CA Richmond Harbor, CA 2. San Francisco Bay to Stockton, CA John F. Baldwin and Stockton Ship Channels) 3. San Francisco Bay and Delta Model, CA San Francisco Harbor, CA San Francisco Harbor and Bay, CA (Removal of Drift) San Leandro Marina, CA San Pablo Bay and Mare Island Strait, CA Santa Cruz Harbor, CA (Federal Funds) (Contrib. Funds) Suisun Bay Channel, CA New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost Minor rehab. Approp. Cost New Work Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost New Work Contrib. Cost Maint. Approp. Cost New Work Approp. Cost 90,000 227,129 44,000 3,079,000 -588,465 61,044 2,868,440 -374,925 - - 15,000 1,672,72225 40 1,672,72225 40 7,324,86026 40 7,324,8602 40 2,901,69527 28 2,886,69527 28 2,011,000 1,650,000 2,047,000 601,226 15,498,34229 1,987,571 493,783 2,663,006 1,136,050 15,463,8732 - - - 164,689 ... 164,689 600,000 432,000 1,200,000 10,580,000 555,315 467,014 628,744 10,246,428 19,122,20042 17,917,25642 513,000 1,782,000 1,141,000 1,159,000 11,782,700 584,347 1,530,770 1,400,852 1,089,231 11,635,402 - - - 2,689,3562s 30 - - - 2,689,35628 30 2,119,500 1,401,000 424,860 2,087,500 20,922,90531 1,928,330 1,409,397 478,865 2,042,272 20,738,74231 .- 40 - - - 40 1,167,000 1,073,000 1,143,000 1,018,000 20,046,18240 1,101,096 1,075,404 1,040,828 1,010,551 19,788,25440 18,000 17,955 410,176 147,205 1,201,73232 45 274,097 261,171 1,179,61982 2,923,000 1,465,000 3,696,143 1,725,125 2,415,274 1,841,748 3,615,383 1,996,024 - - - 120,000 - - 94,699 1,369,37228 33 1,369,37228 33 30,372,70134 30,331,45334 1,972,340 1,947,039 - - 160,0003 - - - 160,000 595,000 742,000 659,000 834,000 8,480,159 679,855 566,161 769,335 935,374 8,429,456 - 36 - 36 34-5 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 34-A (Cont'd) COST AND FINANCIAL STATEMENT See Section Total Cost to in Text Project Funding FY 82 FY 83 FY 84 FY 85 Sep 30, 1985 Maint. Approp. 253,000 594,000 312,000 204,725 2,760,063 6 37 Cost 61,595 782,935 305,091 204,887 2,750,40636 37 Suisun Channel, CA New Work Approp. - - - - 217,6773 Cost - - - - 217,6773 Maint. Approp. 561,000 -32,000 15,130 651 1,351,738" Cost 434,762 94,431 15,130 651 1,351,738w 1. Includes $641,800 for jetties, bulkheads, main Bodega Bay Channel and turning basin completed in 1943. 2. Includes $585,000 for Preconstruction Planning $456,000 Construction, General funds and $129,000 General Investigation funds). 3. Includes $584,563 Preconstruction Planning costs ($455,563 Construction, General costs and $129,000 General Investigation costs). 4. Includes $105,765 for reconnaissance and condition surveys, FY 1956-1985. 5. Excludes contributed funds of $2,000. 6. Excludes contributed funds of $271,116 and $2,138 surplus material from Corps military activities. 7. Excludes contributed funds of $44,340. Includes $75,309 for reconnaissance and condition surveys, FY 1956- 1985. 8. Excludes $2,000 contributed funds in lieu of royaltyfree rock. 9. Includes $2,261,371 for previous project. Excludes $95,000 contributed funds for existing project. 10. Includes $98,206 for previous project and $1,710 for reconnaissance and condition surveys, FY 4956-1985. 11. Excludes $5,337 previous project costs. 12. Excludes $8,539 surplus material from Corps' military activities. Includes $55,695 for reconnaissance and condition surveys, FY 1956-1985. Excludes contributed funds of $180,200. 13. Excludes previous project costs. Excludes $154,500 contributed funds. 14. Includes $241,512 for reconnaissance and condition surveys, FY 1956-1985. 15. Includes $11,985 for previous project. Excludes $7,180 contributed funds for previous project. 16. Includes $1,223,000 for Preconstruction Planning ($773,000 for Breakwater of which $500,000 allocated under Construction, General and $273,000 under General Investigations); ($450,000 for Channel Extension of which $165,000 allocated under Construction, General and $285,000 under General Investigations). 17. Includes $1,209,749 Preconstruction cost ($759,819 for Breakwater of which $500,000 was under Construction, General and $259,819 under General Investigations); ($449,930 for Channel Extension of which $165,000 under Construction, General and $284,930 under General Investigations). 18. Includes $32,097 for previous project and $15,436 for reconnaissance and condition surveys, FY 1956-1985. Excludes contributed funds of $820 for previous project. 19. Excludes contributed funds of $4,000 in lieu of providing dike disposal areas on existing project. 20. Excludes contributed funds of $1,700. 21. Includes $2,899,232 for previous projects. Excludes $397,266 contributed funds on existing project. 22. Includes $684,028 for previous projects and $774 for reconnaissance and condition surveys, FY 1956-1985. 23. Includes $212,083 for previous project. Excludes contributed funds of $15,559 for previous project. 24. Includes $314,692 for previous project and $105,588 for reconnaissance and condition surveys, FY 1956-1985. Excludes contributed funds of $36,430. 25. Includes previous project costs $31,443. Excludes $119,572 contributed funds for existing project. 26. Includes $91,694 for reconnaissance and condition surveys, FY 1956-1985. 27. Excludes contributed funds of $524,778. Includes $105,000 Public Works Administration funds. 28. Excludes modification authorized October 27, 1965, under project "San Francisco Bay to Stockton, CA (John F. Baldwin and Stockton Ship Channels)." 29. Excludes $34,800 contributed funds. Includes $3,364 for reconnaissance and condition surveys, FY 1956-1985. 30. Includes $1,030,399 for previous projects. Excludes $134,591 contributed funds for existing project. Includes 193,000 Public Works Administration funds. 31. Includes $475,321 for previous projects and $20,319 for reconnaissance and condition surveys, FY 1956-1985. 32. Authorized by FC Actof 1965 (Sec. 201); Maintenance R&H Act of 1970 (Sec. 103). Includes $46,732 for reconnaissance and condition surveys FY 1979-1985. See FY 1977 Annual Report for last full report. Excludes contributed funds of $697,784. 33. Includes $1,086,703 for previous projects. 34. Includes $1,359,380 for previous projects and $2,272 for reconnaissance and condition surveys, FY 1956-1985. 35. Excludes $810,046 contributed funds. 36. See Sacramento District FY 1974 Annual Report for details. 37. Project maintenance responsibility to Point Edith was transferred to San Francisco District January 1,1974. Excludes Sacramento District's portion. Includes $9,813 for reconnaissance and project condition surveys, FY 1976-1985. 38. Project maintenance assigned to San Francisco District from Sacramento District January 1, 1974. See Sacramento District 1972 Annual Report for full report. 39. Includes $44,229 for reconnaissance and condition surveys, FY 1978-1985. 40. See FY 1981 Annual Report for last full report. 41. Excludes Contributed Funds of $38,903. 42. See Sacramento District FY 1985 Annual Report for full report. 34-6 SAN FRANCISCO, CA, DISTRICT TABLE 34-B AUTHORIZING LEGISLATION See Date Section in Authorizing Text Act Project and Work Authorized Documents 1. FISHERMAN'S WHARF AREA-SAN FRANCISCO HARBOR, CA Nov. 14, 1983 Breakwater. Cont. Res. (H.J. Res. 413) of 1984, Public Law 98-151, 98th Cong., 1st sess. TABLE 34-C OTHER AUTHORIZED NAVIGATION PROJECTS For Last Cost to Sep 30, 1985 Full Report See Annual Operation and Project Status Report For Construction Maintenance Berkeley Harbor, CA' Completed 1966 155,5502 - Berkeley Marina, CA1 Completed 1979 505,2014 - Halfmoon Bay Harbor, CA Completed 1979 6,697,3963 2,048,79312 Lower San Francisco Bay, CA Inactive 1935 - - Monterey Harbor, CA Inactive 1971 1,108,1825 85,8806 San Francisco Marina (Gas House Cove), CA' Completed 1974 180,4727 - San Francisco Harbor (Islais Creek), CA' Completed 1976 848,2278 - San Leandro Marina (Breakwater), CA' Completed 1976 210,3909 - San Rafael Creek, CA Active 1981 32,35910 2,017,37011 1. Authorized by Chief of Engineers (Sec. 107, Public 7. Includes preauthorization costs $26,855 and excludes Law 86-645). contributed funds $153,618. 2. Excludes $155,551 contributed funds. 8. Includes $94,550 preauthorization costs. 3. Excludes $100,000 contributed funds and $105,000 9. Includes $72,000 preauthorization costs and excludes contributed in lieu of royalty-free rock. contributed funds $138,189. 4. Excludes $378,989 contributed funds. 10. Excludes $41,094 contributed funds. 5. Includes $207,800 Public Works Administration funds 11. Includes $116,923 for reconnaissance and condition and breakwater modifications (1960 Act) placed inactive surveys FY 1956-1985. 1974. 12. Includes $17,567 for reconnaissance and condition 6. Includes $8,041 for reconnaissance and condition surveys FY 1970-1985. surveys for FY 1956-1985. TABLE 34-D OTHER AUTHORIZED BEACH EROSION CONTROL PROJECTS For Last Cost to Sep 30, 1985 Full Report See Annual Operation and Project Status Report For Construction Maintenance Humboldt Bay, CA Inactive 1958 2,000 - Santa Cruz County, CA Inactive 1966 245,639 - 34-7 TABLE 34-G REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 DEAUTHORIZED PROJECTS For Last Full Report Federal Contributed See Annual Date Funds Funds Project Report For Deauthorized Expended Expended Knights Valley Lake, R.R. Basin, CA 1974 Aug. 5, 1977 - - Oakland Harbor, CA (Deepen Tidal Canal) 1981 Nov. 6, 1977 - - Oakland Harbor, CA (Fruitvale Avenue Bridge) 1981 Nov. 6, 1977 - - San Lorenzo Creek, CA (Upper Portion) 1962 Nov. 6, 1977 - - San Pablo Bay and Mare Island Strait, CA (Approaches to Vallejo and South allejo) 1982 Nov. 6, 1977 - - 34-8 SACRAMENTO, CA, DISTRICT* This district comprises basins of Suisun Bay and San Joaquin and Sacramento Rivers in California; Goose Lake in Oregon; basins of the Great Salt Lake and Sevier Lake in Utah; an intervening portion of Great Basin in northern Nevada, northern California, and southeastern Idaho; and the upper Colorado River basin, which is in southwestern Wyoming, eastern Utah, northeastern Arizona, northwestern New Mexico, and western Colorado, west of the Continental Divide. IMPROVEMENTS Navigation Page 1. Sacramento River, CA ................. 35-1 2. San Francisco Bay to Stockton, CA (John F. Baldwin and Stockton Ship Channels) ........................ 35-2 3. San Joaquin River, CA ................. 35-3 Flood Control 4. Buchanan Dam-H.V. Eastman Lake, Chowchilla River, CA .................. 35-4 5. Calaveras River and Littlejohn Creek and tributaries, including New Hogan Lake and Farmington Dam, CA ............................. 35-4 6. Corte Madera Creek, CA ............... 35-5 7. Hidden Dam-Hensley Lake, Fresno River, CA ............................. 35-6 8. Isabella Lake, Kern River, CA........... 35-7 9. Kaweah and Tule Rivers, including Terminus Dam and Success Lake, CA ... 35-8 10. Lower San Joaquin River, CA ........... 35-9 11. Martis Creek Lake, Martis Creek, NV and CA.......................... 35-9 12. Merced County Stream Group, CA ....... 35-10 13. Pine Flat Lake and Kings River, CA ..................................... 35-10 14. Russian River Basin, including Dry Creek (Warm Springs Lake) and Lake Mendocino (Coyote Valley D)am), CA ............................. 35-11 15. Sacramento River and tributaries, CA from Collinsville to Shasta Dam......35-12 Navigation 1. SACRAMENTO RIVER, CA Location. Rises in Trinity Mountains in north-central California, flows generally southerly about 374 miles and empties into Suisun Bay, an arm of San Francisco Flood Control (Cont'd) Page 16. Walnut Creek, CA ..................... 35-14 17. Wildcat and San Pablo Creeks, CA....... 35-15 18. Inspection of Completed Flood Control Projects ....................... 35-15 19. Flood Control Work under Special Authorization .......................... 35-16 20. Scheduling Flood Control Reservoir Operations ............................. 35-16 Multiple-Purpose Projects Including Power 21. New Melones Lake, CA ................. 35-16 General Investigations 22. Surveys ................................ 35-18 23. Collection and Study of Basic Data....... 35-18 24. Research and Development..........35-18 25. Advance Engineering and Design ....... 35-19 26. Other Work under Special Authority..... 35-20 Tables Table 35-A Table 35-B Table 35-C Table 35-D Table 35-E Table 35-F Table 35-G Cost and Financial Statement ................... 35-21 Authorizing Legislation ................. 35-26 Other Authorized Navigation Projects .......... 35-28 Not Applicable Other Authorized Flood Control Projects..............35-29 Not Applicable Deauthorized Projects.........35-31 Bay, at Collinsville, CA. (See Geological Survey topographic map of Sacramento Valley, CA.) Previous projects. For details see page 1985 of Annual Report for 1915 and page 1708 of Annual Report for 1938. 35-1 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Existing project. For description of Sacramento Deep Water Ship Channel, see Annual Report for 1969. Total first cost for completed portion was $43,932,558 ($39,560,558 Federal (Corps), $300,000 (Coast Guard), and $4,072,000 non-Federal for lands and damages, including relocations) and excludes local interests cost $10,741,000 (June 1963) for 30-foot deep water ship channel and 13-foot deep connecting canal basic terminal facilities required under terms of project authorization. Project also provides for a shallow-draft channel 10 feet deep at mean lower low water 150 to 200 feet bottom width, from Suisun Bay to Sacramento, CA, 60 miles; a depth of 6 feet at low water between Sacramento and Colusa, 85 miles; a depth of 5 feet at low water between Colusa and Chico Landing, 50 miles; and such depths as practicable between Chico Landing and Red Bluff, 53 miles, a total distance of 248 miles. Estimated Federal cost (July 1973) of new work for shallow-draft river channel is $1,360,000 (includes $1,163,000 for deferred portion between Colusa and Chico Landing). (See table 35-H on tidal and flood conditions prevailing.) Local cooperation. Fully complied with for deep water ship channel project. None required on shallowdraft feature. Terminal facilities. Piers, wharves, and docks at Port of Sacramento for shallow-draft navigation are open-pile structures with timber decks, some of which are designed to meet extreme high waters of flood stages. All main wharves at Sacramento have rail connections. Three of above facilities are owned by city of Sacramento and remainder by private interests; all are privately operated. For full description see "Port and Terminal Facilities at the Ports of Sacramento, Stockton, Pittsburg and Antioch, Calif., 1975." Deep water terminal facilities comprise wharves and piers, administration and storage buildings, and belt railroad facilities. Majority of these facilities are owned and operated by Sacramento-Yolo Port District; remainder are privately owned and operated. Facilities are considered adequate for existing commerce. Operations and results during fiscal year. New work, Deep Water Ship Channel: None. Maintenance: Shallow Draft Channel: Minor maintenance and operation activities continued in Sacramento River, Sacramento upstream to Colusa. Deep Water Ship Channel: Maintenance and operation activities continued. Fiscal year costs for major maintenance items consisted of: Maintenance dredging on Sacramento River, vicinity of Rio Vista by suction dredge initiated and completed by contract, $1,521,582; and stone protection on levees initiated and completed by contract, $131,501. Historical summary. Construction of 7-foot shallowdraft channel below Sacramento was initiated in September 1899 and completed in 1904. Modified 10-foot shallow-draft channel up to Sacramento was initiated in FY 1928 and completed in 1931. Shallow-draft channel above Sacramento was begun in April 1946 but new work was discontinued when about 48 percent complete. In February 1974, remaining work for shallowdraft portion of project, provision of a 5-foot depth between Colusa and Chico Landing (50 miles), was reclassified as "deferred." Channel is navigable all year; however, there is no regular navigation above Colusa, 145 miles above river mouth. Construction of 30-foot deep water ship channel was initiated in July 1949; improvement dredging by continuing contracts resulted in provision of an operational facility for oceangoing vessels during June 1963. Bascule bridge was completed in April 1960, barge lock in August 1961, barge canal in November 1961, and entire deep water ship channel in June 1970. 2. SAN FRANCISCO BAY TO STOCKTON, CA (JOHN F. BALDWIN AND STOCKTON SHIP CHANNELS) Location. On navigation channels extending from entrance to San Francisco Bay to Port of Stockton through San Francisco, Marin, Contra Costa, Solano, Sacramento, and San Joaquin Counties. (See Coast and Geodetic Charts 5527 and 5532-5534 for respective areas.) Existing project. Project provides for modification of existing San Francisco Harbor, Richmond Harbor, San Pablo Bay and Mare Island Strait, Suisun Bay Channel, and San Joaquin River navigation projects to provide depths of 55 feet for San Francisco Bar Channel; 45 feet for main internal bay channels upstream to vicinity of Avon, and 35 feet from Avon to Stockton; enlargement and deepening to 45 feet of maneuvering areas adjacent to major petroleum refinery terminals along channel route; widening Suisun Bay Channel; reclaiming shoreline marshes and inundated or lowlying areas by spoil deposit for public recreation and for industrial use; providing basic recreation facilities on some of the reclaimed areas for public use; and placing additional rock revetmenton waterside of levees bordering channels. Approved project estimate (October 1985) is $180,500,000, (includes an allowance for estimated inflation through the construction period) comprising Federal cost (Corps) of $138,000,000, including basic recreation facilities ($4,780,000); Federal cost (Coast Guard) for navigation aids $1,100,000; and non-Federal cost of $41,400,000 for lands and damages, relocations, berthing areas, and spoil retention dikes, including the cash contribution ($250,000) that local interests must make for land enhancement at time of construction. Local interests must also pay, contribute in kind, or repay with interest one-half of separable cost of project allocated to recreation ($2,600,000). Existing project was adopted by 1965 River and Harbor Act (H. Doc. 208, 89th Cong., 1st sess., contains latest published map). Local cooperation. Local interests, through a public body legally authorized and financially capable, must give assurances they will furnish lands, easements, and 35-2 SACRAMENTO, CA, DISTRICT rights-of-way for construction and future maintenance of the project and for aids to navigation, including spoildisposal areas designated by the Chief of Engineers; provide necessary spoil retention dikes, bulkheads, and embankments except as applicable to spoil-disposal areas designated as public recreation areas; make utility modifications and relocations required for construction, including new bridges or bridge alterations (except for railroad bridges), and absorb any increased annual maintenance and operation costs resulting therefrom; provide and maintain all necessary berthing areas, at a depth commensurate with project depth, at all terminals and wharves to be served by the deepened channels; and in recognition of the local land enhancement benefits to result from landfill during dredging, contribute to the United States 4 cents per cubic yard of all spoil material placed during initial construction for modification of Suisun Bay Channel project on areas not developed for public use. Local interests must also give satisfactory assurances, before starting construction of the affected units, that they will maintain and operate the Federally provided recreation areas and facilities, continue to maintain to adequate standards the levees altered, set back or provided revetment protection, and hold the U.S. Government free from damages due to deposition of spoil and construction of new levees or reconstruction of existing levees. Local interests, represented by Board of Supervisors of Contra Costa County and Stockton Port District, must, at time of construction, contribute $250,000 in cash for land enhancement; pay, contribute in kind, or repay with interest one-half of separable cost of project allocated to recreation ($2,600,000); and maintain and operate basic recreation facilities after construction and install additional basic facilities required as demands on area expand. No work shall be undertaken on a modification of Suisun Bay Channel project unit to deepen the channel to more than 35 feet between Avon and a proposed refinery or manufacturing plant, until local interests furnish formal assurances and definite plans for such installation within the Avon-Chipps Island reach of channel. Also, no work shall be undertaken on modification of San Joaquin River navigation project unit, regarding access channels in vicinity of Antioch, until local interests furnish formal assurances and definite plans for Port of Antioch. Formal assurances for deepening and otherwise improving the Stockton Deep Water Ship Channel from Pittsburg to Stockton were furnished by Stockton Port District April 9, 1970. The Stockton Port District, in Stockton, by letter of October 20, 1981, stated that they would furnish the necessary assurances for fish and wildlife mitigation and enhancement, and on April 13, 1982, provided formal updated assurances for the Avon to Stockton portion. A sec. 221 agreement satisfying all requirements of local cooperation for Southampton Shoal and Richmond Long Wharf maneuvering area was obtained from Contra Costa County Board of Supervisors and signed by District Engineer July 31, 1984. Terminal facilities. See Port Series No. 30, revised 1983, and 31, revised 1982, titled respectively: "The Ports of San Francisco, Redwood City, and Humboldt Bay, Calif." and "The Ports of Oakland, Alameda, Richmond, and Ports on Carquinez Strait, Calif."; and Port Series No. 32, revised 1975, "The Ports of Sacramento, Stockton, Pittsburg and Antioch, Calif." Facilities are considered adequate for existing commerce and will be adequate for future commerce upon completion of new terminal facilities. Operations and results during fiscal year. New work: Sacramento District: Engineering continued. Channel improvement-dredging mile 41.0-mile 30.9 John F. Baldwin and Stockton Ship Channel was continued at fiscal year contract cost of $218,000. Dredging McDonald Island, mile 30.9 to Jersey Island, mile 10.1 was completed at fiscal year contract cost of $946,003. Dredging Jersey Island to New York Slough was initiated at fiscal year contract cost of $2,471,367. San Francisco District: Continued planning activities. Channel improvement: A dredging contract for Southampton Shoal Channel, Contra Costa County, was awarded December 27,1985; construction was initiated and completed at fiscal year cost of $8,461,395 and removed 3,851,000 cubic yards of material. A dredging contract for Richmond Long Wharf Maneuvering Area was awarded August 22, 1985. No fiscal year costs. Historical summary. Construction of project was initiated in June 1971 and is about 28 percent complete. 3. SAN JOAQUIN RIVER, CA Location. Rises in east central California and flows westerly and northwesterly about 340 miles to its confluence with Sacramento River at head of Suisun Bay, 48 miles northeast of San Francisco. Deep water channel in San Joaquin River extends 41 miles from its mouth in Suisun Bay at Pittsburg to city of Stockton. Waterborne access to city provided by Stockton Channel, an artificial cut extending from river about 2 miles into city. (See Coast and Geodetic Survey Sheet 5527.) Existing project. For description of completed improvement, modifications, and authorizing acts, see Annual Report for 1967. (See table 35-I for total cost of new work for project completed in May 1960.) excPlruodjeedc tsf roumni tpsr o(1je9c5t0 c omsto darifei csaetti ofonr) thr einc latassbilfee d3 5-aJn.d Modification of existing project is included as one unit of San Francisco Bay to Stockton, CA, (John F. Baldwin and Stockton Ship Channels) project, authorized by 1965 River and Harbor Act (H. Doc. 209, 89th Cong., 1st sess.); this modification is reported in detail under Sacramento District, Improvement No. 2. Local cooperation. Fully complied with for completed portion of project; for details of required cash contribu- 35-3 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 tions on completed, inactive and deferred portions of project, see Existing project paragraph, Annual Report for 1967. Terminal facilities. For description of harbor facilities at Port of Stockton, CA, see Port Series 32, "The Ports of Sacramento, Stockton, Pittsburg and Antioch, Calif.," revised 1975. Downstream from Stockton, traffic is accommodated by bank landings and sheds except at Antioch and near Pittsburg, where there are wharves for shallow- and deep-draft vessels. Terminal transfer facilities at public ocean terminal of Port of Stockton are adequate fqr present and immediate future. Operations and results during fiscal year. Maintenance: Condition studies and miscellaneous inspections and reports were accomplished by hired labor. Channel dredging by suction dredge, Stockton Deep Water Channel, San Joaquin River, was completed. Stone protection maintenance on Stockton Deep Water Ship Channel was initiated at fiscal year contract cost of $483,028. (Repair or restoration of wavewash protection is required by legislation authorized by Improvement No. 2.) Historical summary. Active portion of existing project was completed in May 1960. Construction of project was initiated in December 1877. Flood Control 4. BUCHANAN DAM-H. V. EASTMAN LAKE, CHOWCHILLA RIVER, CA Location. On Chowchilla River about 36 miles above its mouth and about 16 miles northeast of city of Chowchilla, CA. (See Geological Survey quadrangles for area.) Existing project. Provides for construction of a 205- foot high rockfill dam to create a reservoir with gross storage capacity of 150,000 acre-feet for flood control, irrigation, recreation, and fish and wildlife. In conjunction with dam, project plan provides for about 12 miles of downstream levee and channel construction on Ash Slough to accommodate a project design flow of 5,000 cubic feet per second within slough and 7 miles of levee and channel improvement on Berenda Slough. Operation and maintenance of dam and reservoir is the responsibility of the Federal Government. Total first cost for existing project is $28,919,597, of which $27,369,597 is Federal cost, including $4,580,000 for basic recreation facilities, and $1,550,000 non-Federal costs for lands and damages, including relocations for downstream levee and channel improvements. Local interests have contracted with the Bureau of Reclamation for irrigation service. For future non-Federal reimbursement, see Local cooperation paragraph. Local interests have also, over a period of years, expended about $500,000 for construction of low levees and clearing downstream channels to provide some local flood protection in project area. This work is inadequate during major floods. Existing project was adopted by 1962 Flood Control Act (S. Doc. 98, 87th Cong., 2d sess., contains latest published map). Lake formed by Buchanan Dam on Chowchilla River was designated "H. V. Eastman Lake" by Public Law 93-217. Local cooperation. Fully complied with. Operations and results during fiscal year. New work: None. Maintenance: Maintenance and operation activities were continued. Chowchilla recreation area: Erosion control and road repair was completed at fiscal year contract cost of $78,306. Dam safety assurance studies were continued at a fiscal year cost of $18,273. Runoff of Chowchilla River above Buchanan Dam was below normal for the year. Maximum storage of 40,800 acre-feetoccurred May 23,1985. Maximum daily inflow to reservoir was 822 cubic feet per second on February 9, 1985. Maximum release of 560 cubic feet per second on June 23, 1985, was below maximum permissible flood release. During the year, a total of 114,900 acre-feet of water was released for irrigation and other purposes. Historical summary. Construction began in July 1971 and was completed in May 1979. Construction of Buchanan and Hidden dam and appurtenances were combined under one contract. Project was completed in September 1983, except for installation of piezometers (now deferred indefinitely). Dam closure was in March 1975; dam was completed in January 1976. Reservoir clearing and boundary marking were completed May 1975. Bifurcation structure was completed in February 1976. Channel improvement, Ash and Berenda Sloughs, was completed in March 1976. Recreation areas: Phase I was completed in January 1976; Phase II was completed in February 1978. Residences, administration building, and visitors center contract was completed in May 1978. Landscaping was completed in May 1979 and erosion control was completed in April 1979. A resources interpretive display and road relocation were completed in FY 1982. Dam safety assurance studies were initiated in FY 1981. Solar heating was installed at Chowchilla recreation area in FY 1984. 5. CALAVERAS RIVER AND LITTLEJOHN CREEK AND TRIBUTARIES, INCLUDING NEW HOGAN LAKE AND FARMINGTON DAM, CA Location. Streams comprising Calaveras River and Littlejohn Creek groups rise in Sierra Nevada and its foothills, flow easterly across flatlands of San Joaquin Valley and empty into San Joaquin River directly, or through various sloughs, in vicinity of Stockton, CA. Littlejohn Creek is in Calaveras, Stanislaus, and San Joaquin Counties. The three principal stream systems of the group are, from south to north, Lone Tree Creek, Littlejohn Creek, and Duck Creek. Calaveras River group is in Calaveras and San Joaquin Counties. The two principal streams of the groups are, from south to north, Calaveras River and Bear Creek. (See Geological 35-4 SACRAMENTO, CA, DISTRICT Survey Valley Springs quadrangle for New Hogan reservoir area and Trigo and Bachelor Valley quadrangles for Farmington reservoir area.) Existing project. For description of completed improvements consisting of Farmington Dam, New Hogan Lake, and BearCreek levee and channel improvement, and authorizing act, see Annual Report for 1967. (a) Farmington: Total first cost (July 1955) for project was $3,995,684, of which $3,676,384 was Federal and $319,300 non-Federal for lands and damages including relocations. (b) New Hogan: Federal cost for project is $15,906,150, including $543,514 for basic recreation facilities. For future non-Federal reimbursement, see Local cooperation paragraph. Federal cost for recreation facilities funded from Code 710 appropriations is $897,742. (c) Bear Creek: Project cost is $6,485,734, of which $3,242,867 is Federal, including reimbursement ($488,096) to local interests of one-half of excess local interest cost of lands, rights-of-way, and relocations over estimated Federal construction cost in accordance with section 3, Public Law 738, 74th Congress. Non- Federal cost included in above amount is $3,242,867 for relocations and lands and damages, exclusive of above Federal reimbursement. Local cooperation. Fully complied with. New Hogan: Local interests must pay portion of first cost and annual operation and maintenance costs allocated to conservation functions of project. These costs are estimated at 36.2 percent of first cost and 38 percent of annual costs. In addition, local interests contributed land, the (July 1964) market value of which was $556,000. For years 1961 through 1970, an interim contract between the Bureau of Reclamation and local water users provided for storage and payment of irrigation water; local interests paid $2,559,294 through December 31, 1984. A long-term contract between that agency and local water users was executed August 25, 1970. A concessionaire at New Hogan Marina provided public use facilities in accordance with lease agreement with the Secretary of the Army at an estimated cost to date of $234,000. Operations and results during fiscal year. New work: New Hogan Lake, regular funds: None. Code 710 funds: None. Bear Creek, San Joaquin County: None. Maintenance: Farmington Dam-Maintenance and operation activities continued; structures were maintained in serviceable condition. During the rainflood season, maximum flow of Littlejohn Creek at Farmington was 1,100 cubic feet per second February 8,1985. Maximum storage in reservoir was 6,100 acre-feet on February 9, 1985, and maximum daily inflow to reservoir was 4,400 cubic feet per second on February 9, 1985. Project prevented an estimated $972,000 in damages from the December 1984-April 1985 rainfloods. New Hogan Lake-Maintenance and operation activities continued. Repaving of the administration area and access road was completed at a fiscal year contract cost of $9,631. Construction of a boathouse was initiated at fiscal year contract cost of $45,000. Road paving at recreation areas was initiated and completed at fiscal year contract cost of $425,274. Structures were maintained in serviceable condition. Runoff of Calaveras River above New Hogan was below normal for the year. Maximum storage of 176,700 acre-feet occurred April 12, 1985. Maximum daily inflow to reservoir was 3,800 cubic feet per second on February 8, 1985. Maximum release of 317 cubic feet per second on June 15, 1985, was below maximum permissible flood release. During the year, 93,500 acre-feet was released for irrigation and other Spurposes. Historical summary. Farmington Dam: Construction of Farmington project was initiated in July 1949 and completed for beneficial flood control operation in 1952. Duck Creek channel improvement was completed in November 1951; and channel improvement on south Littlejohn Creek was completed in May 1955. There are no recreation facilities or public-use areas. All work completed. Dam safety assurance studies were initiated in FY 1982. New Hogan Lake: Construction was initiated May 1960, main dam closure November 1963, project completed for operational use in June 1964, and all work completed October 1973. Recreation facilities have been provided from Code 710 appropriations. Seepage measurement weir constructed in June 1980. Dam safety assurance studies were initiated in FY 1980. Bear Creek, San Joaquin County: Construction began in June 1963 and was completed in June 1967. Final cash contribution was made to local interests December 23, 1970. Solar heating was installed at recreation facilities in FY 1984. A cultural resources survey was completed in FY 1984. 6. CORTE MADERA CREEK, CA Location. Creek and tributaries drain an area of 28 square miles in Marin County, CA, and discharge into west side of San Francisco Bay at a point about 9 miles north of Golden Gate. (See Geological Survey quadrangle San Rafael.) Existing project. Provides for about 11 miles of channel improvements, including realignment, enlargement, levees, riprapping, rectangular concrete sections, interior drainage facilities, bridge relocations, and debris removal on Corte Madera Creek and lower reaches of its tributaries, and a continuous channel rights-of-way to deep water in San Francisco Bay reserved to assure channel outlet in the event of future tideland reclamation. Approved estimated cost for new work (October 1985) is $20,600,000, of which $14,000,000 is Federal cost and $6,600,000 is non-Federal cost (includes $470,000 to be contributed by local interests.) (See table 34-B for authorizing legislation.) Local cooperation. Local interests must provide lands and rights-of-way, including suitable areas for disposal of waste material, modify or relocate all bridges and utilities necessary for construction and maintenance; hold and save the United States free from damages due 35-5 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 to the construction works; maintain and operate the project after completion in accordance with the regulations prescribed by the Secretary of the Army, and prevent encroachment on flood channels that would result in decreasing the effectivenessof project for flood control; adjust all claims regarding water rights that might be affected by.the project; and contribute in cash 1.5 percent of Federal construction cost of Ross Valley unit and tidal areas, an estimated $470,000. Marin County Flood Control and Water Conservation District previously furnished resolution of local assurances dated March 29,1966, March 28,1967, August 15,1967, and July 8,1969, and Marin County Board of Supervisors reaffirmed by letter dated September 28, 1978. Ross Town Council approved the alternative plan on May 25, 1978. Project was authorized by the State of California by 1965 Statute, Chapter 1388. Board of Supervisors of Marin County Flood Control and Water Conservation District furnished assurances of willingness and ability to meet requirements for portion of project below Sir Francis Drake Boulevard. Acquisition of rights-of-way and dredge material disposal areas, relocations and construction for remaining work is being held in abeyance as a result of a request from Congress for a review of alternatives other than completing the project as an open concrete channel. On December 13, 1983, Marin County Board of Supervisors reconfirmed assurances of local cooperation because a Superior Court Judgment ordered that county to take all steps required by law to complete channel downstream of Sir Francis Drake Boulevard (Unit 4) and maintain entire project as agreed. A Local Cooperation Agreement for redredging the lower reach of Corte Madera Creek was executed on June 29, 1985. Operations and results during fiscal year. New work: Plans and specifications for redredging Lower Corte Madera Creek channel were completed. General Design Memorandum No. 2, Supplement No. 1 (Unit 4) was initiated. Historical summary. Project responsibility was transferred from San Francisco District on April 1, 1982. Project is about 75 percent complete considering the portion being held in abeyance upstream of Sir Frances Drake Boulevard. Work remaining: Design and construction of the remaining 3,000 feet of channel downstream of Sir Francis Drake Boulevard and Ross Creek. In lieu of the authorized concrete channel, an alternative plan consisting of wing walls and individual house floodproofing is being recommended in the Significant Post-Authorization Change Report. The portion of Corte Madera Creek upstream of intersection of Sir Francis Drake Boulevard and Corte Madera Creek in Ross, near the city of San Anselmo, was classified as "inactive" on July 11, 1984, due to lack of local support. A Local Cooperation Agreement for redredging lower reach of Corte Madera Creek was executed June 29, 1985. 7. HIDDEN DAM-HENSLEY LAKE, FRESNO RIVER, CA Location. On Fresno River about 50 miles above its mouth and about 15 miles northeast of Madera, CA (See Geological Survey quadrangles for area.) Existing project. Provides for construction of a 163- foot high earthfill dam to create a reservoir with gross storage capacity of 90,000 acre-feet for flood control, irrigation, recreation and other purposes. In conjunction with the dam, the project provides for about 13 miles of downstream levee and channel improvements on Fresno River immediately upstream of Chowchilla Canal crossing to accommodate project design flow of 5,000 cubic feet per second. Operation and maintenance of dam and reservoir is the responsibility of the Federal Government. Total first cost for existing project is $31,785,426, of which $30,555,426 is Federal cost, including $3,564,168 for basic recreation facilities, and estimated $1,230,000 non-Federal cost for lands and damages including relocations for downstream levee and channel improvements. Local interests have contracted with the Bureau of Reclamation for irrigation service. For future non-Federal reimbursement, see Local cooperation paragraph. Local interests have also, over a period of years, expended about $300,000 for construction of low levees and clearing downstream channels to provide some local flood protection in the project area. This work is inadequate during major floods. Existing project was adopted by 1962 Flood Control Act (S. Doc. 37, 87th Cong., 1st sess., contains latest published map). Lake created by Hidden Reservoir project on Fresno River was designated "Hensley Lake" by Public Law 93-603. Local cooperation. Fully complied with. Operations and results during fiscal year. New work. None. Maintenance: Maintenance and operation activities were continued. Erosion repair on downstream face of the dam was initiated at fiscal year contract cost of $129,114. Dam safety assurance studies were continued at a fiscal year cost of $17,514. Runoff of Fresno River above Hidden Dam was below normal for the year. Maximum storage of 35,500 acre-feet occurred May 29, 1985. Maximum daily inflow to reservoir was 520 cubic feet per second on March 28,1985. Maximum release of 228 cubic feet per second on June 18, 1985, was below maximum permissible flood release. During the year, 26,600 acre-feet of water was released for irrigation and other purposes. Project prevented an estimated $455,000 in damages from the December 1984-April 1985 rainfloods. Historical summary. Construction began in July 1971 and was completed in January 1979. Dam closure was in March 1975; dam was completed November 1975. Instrumentation was completed in January 1976. Downstream channel improvement, Fresno River, was completed April 1976. Recreation areas: Phase I was completed in March 1976; Phase II was completed in June 1978. Residences, administration building, grounds, and utilities contract was completed in February 1978. 35-6 SACRAMENTO, CA, DISTRICT Landscaping was completed in December 1978 and erosion control was completed in January 1979. Project was completed in September 1980. Final land audit was approved February 5, 1980. Dam safety assurance studies were initiated in FY 1980. Piezometer installation was completed in. September 1982. Solar heating was installed at recreation areas in FY 1984. 8. ISABELLA LAKE, KERN RIVER, CA Location. About 35 miles northeast of city of Bakersfield, CA, near confluence of north and south forks of Kern River; auxiliary dam is about one-half mile east of main dam. (See Geological Survey quadrangles of area.) Existing project. For description of completed improvement and authorizing act, see Annual Report for 1967. Federal cost for new work is $22,027,452. For future non-Federal reimbursement see Local cooperation and Licenses paragraphs. Federal cost funded from Code 710 appropriations is $2,199,085. Operation and maintenance of dam and reservoir is Federal responsibility. Local cooperation. California officially adopted project by chapter 1514 of statutes of 1945, State of California. Local interests, represented by North Kern, Buena Vista, and Tulare Lake Basin Water Storage Districts and La Hacienda Water District, were required to reimburse the Federal Government the portion of first cost and annual operation and maintenance costs allocated to irrigation functions of project. These costs, based on a cost allocation study completed in December 1955, are $4,573,000 of first cost and 21.7 percent of annual operation and maintenance cost. For the years 1956 through 1964, an interim contract between the Bureau of Reclamation and local water users provided for storage and payment of irrigation water. Under provisions of this interim contract, local interests paid $1,936,229 through December 31, 1964. A long-term contract between the Bureau and local water users was executed October 23, 1964. Balance due on allocated first cost of $4,573,000 was paid by the water users on March 31, 1965. Kern County assumed administration of recreation and development and maintenance of public use areas at project in accordance with a 25-year license February 15, 1955. The agreement with Kern County provided for joint operation and development by the Corps and Kern County including permits granted to concessionaires by the county to provide certain services. As of September 30, 1971, Kern County relinquished all administration of recreation and development and maintenance of public use areas at the project. A State law permitting the Department of Boating and Waterways (known as the Department of Navigation and Ocean Development prior to January 1979) to participate in inland water development with Federal agencies was signed by the Governor on August 11,1972. All concessionaires will operate under permits granted by the Corps. Total cost to date of present recreation facilities developed by the county and the marina concessionaires is about $965,000; $235,000 of this was a grant from the California Wildlife Conservation Board and about $534,000 is investment by marina concessionaires. Licenses. In accordance with Federal Power Commission Docket No. E-6578, issued April 1, 1963, payment of $377,426 was made to the Federal Government by Pacific Gas and Electric Co. ($108,352) and Southern California Edison Co. ($269,074)for headwater benefits to downstream existing plants from Isabella Dam to cover benefits from April 15, 1954, to December 31, 1962. Between 1962 and 1982 the power companies have in the aggregate made annual payments of $44,650 for headwater benefits. That amount was to be paid each year until changes in operation, development, or costs indicated some modification to be advisable. Federal Power Commission Docket No. E-6578 was revised by Docket No. HB07-75-4-000 (order issued July 11, 1983 under 24 FERC, paragraph 62052) which modified cumulative use charges after 1974, effective retroactively. Such charges will now vary each year. An adjustment (years 1974 through 1984) was included in 1984 payment of $244,790. The 1985 payment was $52,747. Cumulative use charges collected by the Federal Power Commission (known as the Federal Energy Regulatory Commission since January 9,1978) and returned to the U. S. Treasury through period ending September 30, 1985, amounted to $1,657,263. Operations and results during fiscal year. New work, regular funds: None. Code 710 funds: None. Maintenance: Maintenance and operation continued. Fiscal year contract costs for major items of work included: Initiation and completion of repair and repaving of roads in Eastside recreation area, $252,102; initiation of Paradise Cove recreation area renovation, $978,074; initiation and completion of road paving at miscellaneous recreation areas, Phase I, $640,079; and initiation of road paving at miscellaneous recreation areas, Phase II, $100,000. Dam safety assurance studies at Isabella Dam were continued at a fiscal year cost of $471. Structures were maintained in good condition. Runoff of Kern River above Isabella Lake was below normal for the year. Maximum storage of 388,600 acrefeet occurred June 13, 1985. Maximum daily inflow to the reservoir was 3,300 cubic feet per second on April 15, 1985, and maximum outflow of 2,210 cubic feet per second occurred June 19,1985. Duringthe year, 701,000 acre-feet was released for irrigation. Historical summary. Construction began in March 1948 and was completed in June 1968. Main dam, Borel Canal outlet works and appurtenances, and auxiliary dam were completed in April 1953. Storage impoundment began December 1952. Piezometer was installed in August 1982. Project is operating to provide flood protection and irrigation benefits for which it was designed. Recreation facilities were provided by Code 35-7 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 710 funds. Dam safety assurance studies were initiated in FY 1979. A cultural resources survey was completed in FY 1984. 9. KAWEAH AND TULE RIVERS, INCLUDING TERMINUS DAM AND SUCCESS LAKE, CA Location. Terminus Dam is on Kaweah River about 20 miles east of Visalia, CA. Success Lake is on Tule River about S5miles east of Porterville, CA. (See Geological Survey quadrangles of area.) Existing project. Terminus Dam: For description of completed improvement and authorizing act, see Annual Report for 1975. Federal costof new work is $19,302,957, including $242,605 for basic recreation facilities and excluding spreading works constructed by local interests at an estimated (July 1957) cost of about $750,000. Spreading works portion of project has been deauthorized. The 90-day Congressional project review period, required by sec. 12, Public Law 93-251, as amended, ended August 5, 1977, and resulted in deauthorization of that portion of project. Federal cost of recreation facilities funded from Code 710 appropriations is $700,004. Success Lake: For description of completion improvement and authorizing act, see Annual Report for 1975. Federal cost of new work for Success Lake is $14,247,221, including $253,697 for basic recreation facilities. Federal cost of recreation facilities funded from Code 710 appropriations is $747,048. For future non-Federal reimbursements, see Local cooperation paragraph. Operation and maintenance of reservoirs is Federal responsibility. Local cooperation. California officially adopted projects by chapter 1514 of statutes of 1945, State of California. Local interests for Terminus Dam are represented by Kaweah Delta Water Conservation District. Local interests for Success Lake are considered to be represented by the Vandalia, Porterville, and Lower Tule River Irrigation Districts, the Tulare Lake Basin Water Storage District, and Pioneer Water Co., which represent over 90 percent of irrigated land and waterright holders along Tule River below damsite. Local interests must reimburse the Federal Government the portion of first cost and annual operation and maintenance costs allocated to irrigation functions of projects. These costs are estimated at 14.1 percent of first and annual costs for Terminus and 9.5 percent of first and annual costs for Success. Local interests for Terminus stated they will continue to operate and maintain spreading works and downstream channel systems to provide required capacity for disposal of floodwaters. Local interests for Success stated they will continue to maintain downstream channel systems to provide required capacity for disposal of floodwaters. Repayment contracts between the Bureau of Reclamation and local water users for irrigation supply from Terminus and Success reservoirs were executed January 11,1965, and April 30, 1965, respectively. Reservoirs are being operated for irrigation storage as well as flood control and incidental recreation use. Tulare County acquired water for recreation pools at the projects. Local interests paid the following total amounts for irrigation services from the reservoirs through December 31, 1984: Terminus, $1,548,205 and Success, $716,568. Tulare County was granted a 25-year license for planning, development, and management of public recreation areas at Success, July 10,1960, and at Terminus, June 5, 1961. Basic public-use facilities constructed by Corps at the Success reservoir were transferred to jurisdiction of Tulare County on January 18, 1962; facilities at Terminus were transferred June 20, 1962. In March 1967, an amendment to the license agreements was approved by the Assistant Secretary of the Army. Under these amended licenses, Tulare County retained administration of only specified land areas and operation and maintenance of recreation facilities in these areas. In addition, they continued their program of water safety, boat inspection, and law enforcement at both reservoirs. The Corps took over the administration of the remainder of the project land areas and the operation and maintenance of recreation facilities in these areas. Calif. Department of Fish and Game expended funds to improve fishery resources of the Terminus reservoir. As of April 1, 1972, Tulare County relinquished all planning, development, and management of public recreation areas at Terminus Dam. Tulare County by expenditure of county funds and by a lease to a marina concessionaire has aided in the development of recreation facilities at an estimated cost of $199,000. Calif. Department of Fish and Game expended funds in conjunction with Tulare Sportsman's Council, developing a habitat for upland game birds at Success Lake. As of April 1, 1972, Tulare County relinquished all planning, development, and management of public recreation areas at Success Lake, except for the Bartlett Park recreation area. Tulare County has aided in development of recreation facilities. Total cost to date of present recreation facilities developed by the county ($360,000) and the marina concessionaires ($373,000) is about $733,000. Operations and results during fiscal year. New work: Terminus Dam, regular funds: None. Code 710 funds: None. Success Lake, regular funds, None. Code 710 funds: None. Maintenance: Terminus Dam: Maintenance and operation continued. Dam safety assurance studies were continued at a fiscal year cost of $3,503. Structures were maintained in serviceable condition. Runoff of Kaweah River above Terminus Dam was below normal for the year. Maximum storage of 143,800 acre-feet occurred on May 24,1985. Maximum daily inflow to the reservoir on April' 15, 1985, was about 1,840 cubic feet per second. Maximum outflow of 2,060 cubic feet per second occurred June 16,1985. Water released for flood control amounted to 47,700 acre-feet and irrigation and spreading releases totaled 281,100 acre-feet.Success Lake: Maintenance and operation continued. Dam safety 35-8 SACRAMENTO, CA, DISTRICT assurance studies were continued at a fiscal year cost of $10,013. Structures were maintained in serviceable condition. Runoff of Tule River above the reservoir was below normal during the year. Maximum daily inflow to the reservoir was 1,390 cubic feet per second on March 27, 1985, and maximum outflow of 860 cubic feet per second occurred on July 8, 1985. Maximum storage of 55,200 acre-feet occurred on May 30, 1985. Water released for flood control amounted to 30,100 acre-feet and irrigation and spreading releases amounted to 83,700 acre-feet. Historical summary. Terminus Dam: Construction of project began in July 1957 and was completed in June 1968 except for final settlement for one tract of land upon decision of pending court case. Construction of main dam and appurtenances, initiated in February 1959, was completed in June 1962. Dam has been operating since November 1961 to provide flood protection for which it was designed; conservation impoundment was commenced May 1962. Appurtenances are in good condition. Recreation facilities were provided by Code 710 funds. Dam safety assurance studies were initiated in FY 1979. Piezometer installation and a cultural resources survey were completed in FY 1984. Success Lake: Construction of project began in November 1956, was completed in June 1968, and final audit of historical land record was approved December 17, 1979. Construction of main dam and appurtenances, initiated in October 1958, was completed in May 1961. Dam has been operating since October 1960 to provide flood protection for which it was designed; conservation impoundment was commenced March 1962. Recreation facilities were provided by Code 710 funds. Dam safety assurance studies were initiated in FY 1979. A cultural resources survey was completed in FY 1984. 10. LOWER SAN JOAQUIN RIVER, CA Location. On Lower San Joaquin River, CA, from city of Stockton, CA, upstream to Friant Dam (about 19 miles northeast of Fresno). Existing project. This project is a modification and extension of the previous Lower San Joaquin River and Tributaries project (see Annual Report for 1976) to provide clearing and snagging on the San Joaquin River from Stockton, CA, upstream to Friant Dam. Approved estimate (October 1985) of Federal cost is $5,600,000 (includes an allowance for estimated inflation through the construction period). Existing project was included in the 1983 Supplemental Appropriations Act, Public Law 98-63, July 29, 1983, which states that the project for flood protection on the Lower San Joaquin River, CA, authorized by the Flood Control Act approved December 22, 1984, as amended, is hereby further modified to authorize the Secretary of the Army, acting through the Chief of Engineers, to perform clearing and snagging on the San Joaquin River from Stockton, CA, to Friant Dam, at an estimated cost of $5,000,000. Local cooperation. Prior to initiation of construction, a non-Federal entity shall furnish adequate assurance for providing all lands, easements, rights-of-way and. utility relocations at no expense to the Federal Government, execute a written agreemefit pursuant to sec. 221 Public Law 96-611; agree to operate and maintain the project works upon completion of construction in accordance with rules and regulations prescribed by the Department of the Army; and hold and save the United States free from damages due to construction, operation, and maintenance of the project, not including damages due to the fault or negligence of the United States or its contractors. Operations and results during fiscal year. First construction contract, dredging Eastside Bypass, was awarded in October 1984, and completed in May 1985 at a fiscal year contract cost of $1,842,480. Historical summary. A Plan of Action, February 1984, has been prepared. Design Memorandum No. 5 for Eastside Bypass at San Joaquin River was prepared in September 1984. First construction contract, dredging Eastside Bypass, was awarded October 12,1984 and completed in May 1985. 11. MARTIS CREEK LAKE, MARTIS CREEK, NV AND CA Location. Reservoir is on Martis Creek a tributary of Truckee River, near Truckee, CA; intermittent channel improvements are on Truckee River in Reno, NV. (See Geological Survey quadrangles for areas.) Existing project. For description of completed improvement and authorizing act, see Annual Report for 1975. Federal cost for project was $8,503,789 including $289,506 for basic recreation facilities. Federal cost of recreation facilities funded from Code 710 appropriations was $1,200. Construction of recreation facilities under Code 710 was determined to be infeasible. Operation and maintenance of reservoir is Federal responsibility. Local cooperation. Fully complied with. Operations and results during fiscal year. New work: None. Maintenance: Maintenance and operation of project, including recreation facilities, was continued. Drainage control system modification at Martis Creek Dam was initiated at fiscal year contract costof $685,297. Structures were maintained in serviceable condition. Runoff above Martis Creek Dam was below normal for the year. Maximum storage of 870 acre-feet occurred on April 9, 1985. Maximum daily inflow to the reservoir on April 9, 1985, was about 100 cubic feet per second and maximum daily outflow of 95 cubic feet per second occurred April 9, 1985. Historical summary. Project construction began in August 1967; dam closure was in October 1971; dam was completed in August 1972; basic recreation facilities were completed in December 1972; and project was completed in June 1974. Recreation facilities under Code 710 funding were considered infeasible. Dam safety assurance studies were initiated in FY 1981. 35-9 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 12. MERCED COUNTY STREAM GROUP, CA Location. Reservoirs and channel improvements are on Bear, Burns, Mariposa, and Owens Creeks, in foothills of Sierra Nevada about 15 to 20 miles east of city of Merced, CA. (See Geological Survey Haystack Mountain quadrangle for Burns and Indian Gulch quadrangle for Bear, Owens, and Mariposa areas.) Existing project. For description of completed improvements and authorizing act, see Annual Report for 1962. Improvements consist of reservoirs at Mariposa, Owens, Burns and Bear Creeks and diversions from Black Rascal Creek to Bear Creek and from Owens Creek to Mariposa Creek. Total first cost for project was $3,899,259, of which $2,751,259 was Federal and $1,148,000 non-Federal for lands including relocations and channel improvement. Local cooperation. Fully complied with. Operations and results during fiscal year. Maintenance: Ordinary maintenance and operation of the four completed reservoirs continued. Structures were maintained in a serviceable condition. Runoff from drainage areas above Merced County stream group reservoirs was below normal for the year. (See table 35-K for maximum inflow storage and outflow for projects.) Outflows were less than channel capacity rates in the project streams. Project prevented an estimated $651,000 in damages from the December 1984-April 1985 rainfloods. Historical summary. Construction was initiated March 1948, with construction of Mariposa project., which was completed in November 1948. Construction of Owens project, initiated in March, was completed in October 1949; Burns project, initiated in July 1949, was completed in January 1950; and Bear project initiated in April, was completed in December 1954. Black Rascal and Owens Creek diversion channels and streamgaging stations were completed in April 1956. Local interests completed channel enlargement and restoration of channel capacities of Miles, Burns, Owens, and Mariposa Creeks in 1956 at their expense. Improvement of Bear Creek and Black Rascal Slough, below their confluence, was deferred pending possible improvements downstream, outside limits of project. 13. PINE FLAT LAKE AND KINGS RIVER, CA Location. Reservoir is on Kings River, about 25 miles east of Fresno, CA, and channel improvements are on Kings River downstream from Lemoore weir, about 25 miles south of Fresno. (See Geological Survey quadrangles of area.) Existing project. Improvement is a unit in comprehensive plan for flood control and other related purposes for Sacramento-San Joaquin Basins. Project consists of a 429-foot high concrete gravity dam, including a gated overflow section with a maximum discharge capacity of 391,000 cubic feet per second, creating a reservoir with gross storage capacity of 1 million acre-feet, for flood control, irrigation, and related purposes. Outlet provisions for future power development are included in dam, but Federal construction of power-generating facilities is not authorized. Improvement also includes levee and channel work on Kings River and its distributaries on valley floor about 25 miles south of Fresno. Channel improvement work will enlarge channel capacities and regulate flows in lower branches of the Kings River. There are nine public-use and recreation areas: One maintained by the Corps, four by the Forest Service, three jointly by the Corps and concession, and one by Fresno County. Also, five boat access-only areas are maintained by the Corps on the south side of the reservoir. Project cost is $42,072,330, of which $41,502,330 is Federal (including $13,700 for basic recreation facilities) and $570,000 non-Federal for rights-of-way for downstream channel improvements. For future non-Federal reimbursement, see Local cooperation paragraph. Federal cost of recreation facilities for Pine Flat Lake, funded from Code 710 appropriations is $1,595,100 exclusive of recreation facilities previously provided at a cost of $13,700. In addition, Federal cost of recreation facilities for Pine Flat Lake, funded from Public Works Acceleration Executive Act of 1962 appropriations, was $239,235 (July 1963). Operation and maintenance of dam and reservoir is Federal responsibility. Existing project was adopted by 1944 Flood Control Act (H. Doc. 630, 76th Cong., 3d sess., contains latest published map). Local cooperation. Local interests must reimburse the Federal Government for first costs allocated to irrigation functions of reservoir portion of project in accordance with reclamation law. Under provision of War Department Civil Appropriations Act of 1947, the Secretary of War, with concurrence of the Secretary of the Interior, determined allocation of cost to irrigation should be set at an amount not to exceed $14,250,000. In addition, local interests must pay 37.4 percent of annual maintenance, operation, and replacement costs of dam and reservoir allocated to irrigation function. Repayment contracts between the Bureau of Reclamation and the local water users for the irrigation use of the reservoir were executed December 23,1963. The Bureau is administering the contracts in accordance with reclamation law as amended by the Reclamation Reform Act of October 12, 1982. That act generally exempts the limitations under the early reclamation laws as being applicable to projects constructed by the Corps with two exceptions; however, all existing contracts to share construction and maintenance costs remain in effect. Prior to execution of the final contracts, the Bureau provided conservation water to local interests under an interim contract. Irrigation interests paid $12,561,530 for irrigation services through December 31, 1984. With respect to the downstream channel improvements, sec. 3, Flood Control Act of June 22, 1936, applies. King River Conservation District represents local interests; assurances were accepted November 20, 1959. Local 35-10 SACRAMENTO, CA, DISTRICT interests have furnished all requirements for construction rights-of-way for construction of channel improvements required to date. Three concessionaires-one each at Lakeridge Marina (Deer Creek), Pine Flat Marina and Trimmer Marina provided public-use facilities in accordance with lease agreements with the Secretary of the Army. Estimated cost to date of facilities installed by these concessionaires is $1,727,000. Fresno County developed public-use facilities on an 85- acre tract immediately downstream from dam for picnicking, camping, swimming, and playground activities, at an estimated cost to date of $476,000 under provisions of a license agreement. The U.S. Forest Service developed and operates a picnic area at the upper end of reservoir. Cost of site development is about $37,500. Installation of a hydroelectric powerplant, located at the downstream toe of the Corps Pine Flat Dam, was completed in January 1984 by Kings River Conservation District. Project consists of an outdoortype powerhouse containing three generating units with capacities of 55 megawatts each for a total of 165 megawatts. Conservation District would make use of the three existing 13.5-foot diameter penstocks that were installed in Pine Flat Dam when constructed in 1954. Licenses. License No. 1988, effective April 1, 1955, was issued by Federal Power Commission to Pacific Gas and Electric Co. for hydroelectric power development of North Fork Kings River by the company upstream from the Pine Flat reservoir. Under interim Contract No. DA-04-167-eng-1182 with the Department of the Army, Pacific Gas and Electric Co. paid for storage of power water in the Pine Flat reservoir May 15,1954, through March 31,1955. Current Contract No. DA-04-167-eng-1328 with the Department of the Army provides for storage of power water at the rate of 0.1375 per acre-foot; the contract covers April 1, 1955, through March 31, 2005. By an agreement of January 1972, supplementing the December 1954 contract, Pacific Gas and Electric Co. transferred ownership of most of its Kings River system water to the Kings River Water Association. Accordingly, no further significant storage service to Pacific Gas and Electric Co. by the reservoir at Pine Flat is anticipated. Total payment under these contracts through June 30, 1972, (last year of payment), amounts to $2,478,798; these funds are paid to Sacramento District and deposited for return to the Treasury. Operations and results during fiscal year. New work, regular funds: None. Code 710 funds: None. Maintenance: Maintenance and operation activities continued. Water stop repair between three monoliths at Pine Flat Dam was initiated and completed at fiscal year contract cost of $90,000. Repaving of recreation road was completed at fiscal year contract cost of $381,548. Structures were maintained in serviceable condition. Runoff of Kings River above Pine Flat Dam was below normal for the year. Maximum storage of 840,300 acre-feet occurred on May 28,1985. Maximum daily inflow to the reservoir was 6,030 cubic feet per second on April 15, 1985, and maximum outflow of 7,880 cubic feet per second occurred on July 19, 1985. During the year, 1,492,600 acre-feet of water was released for irrigation and spreading. Dam safety assurance studies were continued at a fiscal year cost of $65,476. Historical summary. Construction began in April 1947 and project, including channel improvement, was completed in September 1977. Main dam was initiated in January 1950, completed in June 1954, and has been operating since February 1954 to provide flood protection for which it was designed. Total of 35.2 miles of new and reconstructed levees and 13.2 miles of channel clearing have been transferred to the Kings River Conservation District for maintenance. Recreation facilities for various recreation areas under Code 710 appropriation are complete. Completed preliminary design and cost estimates for Pine Flat fish barrier were reviewed by the State, but the State was unable to provide necessary assurances of local cooperation. Dam safety assurance studies were initiated in FY 1982. A cultural resources survey was completed in FY 1984. 14. RUSSIAN RIVER BASIN, CA Location. Russian River rises in Coast Range in northwestern California, flows southerly for 87 miles, and then turns westerly to flow for 23 miles to Pacific Ocean at Jenner, 60 miles northwest of San Francisco, CA. (For general location see Geological Survey map for California.) Existing project. Active authorized project provides for construction of a dam on East Fork of Russian River at Coyote Valley to a height of 160 feet; a dam on Dry Creek at Warm Springs to a height of 319 feet; and channel stabilization works on Russian River between mouth and mile 98, on lower reaches of several tributaries, and on Dry Creek downstream from dam. Coyote Valley Dam (Lake Mendocino), completed in 1959, is operated and maintained by the United States. (See tables 35-L and 35-M for latest approved estimated costs.) Local cooperation. Fully complied with for Coyote Valley Dam and channel improvements accomplished to date. For the Dry Creek portion, local interests are required by the authorizing act to comply with the usual a., b., c. requirements for channel improvements and, in addition, prevent any encroachment in the channel of Dry Creek which would interfere with proper functioning of the channel improvement works; adjust all claims concerning water rights arising from the construction and operation of the improvements, including acquisition of water rights needed for preservation of fish and wildlife resources affected by the project; and reimburse the United States in accordance with the Water Supply Actof 1958, as amended, for that part of the construction cost, (27.8% of total construction cost, currently estimated at $94,500,000) and the annual operation, maintenance, and replacement costs allocated 35-11 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 to municipal and industrial water supply, tentatively estimated at $358,000. The estimated annual cost to local interests for maintenance of channel improvement works is $74,900. Sonoma County Water Agency (formerly Sonoma County Flood Control and Water Conservation District) provided assurances of willingness and ability to meet requtirements by Resolutions No. DR 00793-1, September 25, 1961, No. DR 4770-1, December 17, 1962, and No. DR 45759, August 5, 1974, for Dry Creek (Warm Springs) Lake and Channel. By letter dated March 7, 1967, Sonoma County Flood Control and Water Conservation District further indicated their interest in optimization of the Dry Creek (Warm Springs) damsite to provide additional water supply storage. Reimbursement to the United States for Dry Creek (Warm Springs) Lake and Channel costs allocated to 212,000 acre-feet of water supply storage is specified in a water supply contract with the local sponsor approved in October 1982. Local interests have expended approximately $1,000,000 to provide partial flood protection in project area and have constructed facilities at an approximate cost of $20,000,000 to distribute water from the completed Coyote Valley reservoir. Operations and results during fiscal year. New work: Coyote Valley Dam: None. Dry Creek (Warm Springs) Lake and Channel: Engineering activities included preparation of a feature design memorandum for the Yorty Creek Beach area; continuation of plans and specifications for upgrading Rockpile Road and the Buzzard Rock recreation area; completion of plans and specifications for boat launching ramp, Phase II; and completion of plans and specifications for renovating project administration buildings and modifications to water supply facilities. Remaining recreation facilities beyond minimal plan were unscheduled pending development of cost sharing agreement with local interests for construction and operation and maintenance. Major items of work included: Initiation of boundary fencing, Phase I, $212,850, completion of boat launching facilities, Phase I, $640,616 and initiation of boat launching facilities, Phase II, $499,256. Construction contract for dam and appurtenances, awarded May 1978, is complete. Maintenance: Coyote Valley Dam: Operation and maintenance continued. Structures were maintained in serviceable condition. Runoff of East Fork at Russian River was below normal for the year. Maximum storage of 91,900 acre-feet occurred on April 29, 1985. Maximum bihourly inflow to reservoir was 6,090 cubic feet per second on February 8,1985. Maximum releaseof2,010 cubic feet per second occurred on November 28, 1985. During the year, water released for all purposes totaled 211,400 acre-feet. Project prevented an estimated $36,000 in damages from December 1984-April 1985 rainfloods. Dam safety assurance studies were continued at fiscal year cost of $50,674. Dry Creek (Warm Springs) Lake and Channel: Operation and maintenance continued. Structures were maintained in serviceable condition. Runoff of Dry Creek at Warm Springs Dam was below normal for the year. Maximum storage of 74,000 acre-feet occurred April 27, 1985. Maximum bihourly inflow to reservoir was 6,540 cubic feet per second on February 8, 1985. Maximum release of 230 cubic feet per second occurred February 19, 1985. During the year, water released for all purposes totaled 84,200 acre-feet. Project prevented an estimated $12,000 in damages from the December 1984-April 1985 rainfloods. Historical summary. Entire project, exclusive of recreation facilities at completed project (Lake Mendocino), is about 90 percent complete. Coyote Valley Dam, initiated November 1958, was completed April 1959 (cost $17,550,000, of which $11,952,000 was Federal; and $5,598,000 contributed). Work, including removal of slides resulting from storms in 1958, was completed April 1959. Bank stabilization work on Russian River near Geyserville was completed in 1957 and channel improvements in remaining reaches on Russian River and East Fork of Russian River were completed in 1974 (cost $2,483,900). In April 1982, responsibility was transferred to the Sacramento District. Warm Springs construction completions include fish hatchery in December 1980, reservoir clearing in July 1981, project overlook in May 1981, downstream stabilization sills in October 1981, dam closure in October 1982, spillway repair at Warm Springs Dam in September 1985, and boat launching facilities, Phase I, in September 1985. Initial filling of Warm Springs reservoir was commenced on November 1, 1984. Major items of work remaining include upgrading Rockpile Road, minimal recreation facilities, boat ramp and administration facilities, and vegetation management program with remaining boundary fencing. Responsibility for construction was transferred to Sacramento District in August 1983. Dam safety assurance studies were initiated at Coyote Valley Dam in fiscal year 1984. 15. SACRAMENTO RIVER AND TRIBUTARIES, CA, FROM COLLINSVILLE TO SHASTA DAM Location. Rises in Trinity Mountains in north-central California, flows generally southerly about 374 miles and empties into Suisun Bay, an arm of San Francisco Bay at Collinsville, CA. Works covered by this improvement are on Sacramento River and tributaries from Collinsville to Shasta Dam, about mile 312. Drainage area above Rio Vista is 26,500 square miles (See Geological Survey quadrangles of area for Sacramento River and Upper Butte Basin; Flournoy and Fruto quadrangles for Black Butte Lake; and Tuscan Buttes, Tehama, Redding, and Hooker quadrangles for Table Mountain Lake.) Existing project. Improvement of Sacramento River and tributaries, from Collinsville to Shasta Dam was authorized as a unit of a comprehensive plan for flood control and other related purposes in Sacramento River Basin. (a) Sacramento River and major and minor tributaries, for flood control purposes: Enlargement of existing levees on Sacramento River between vicinity of 35-12 SACRAMENTO, CA, DISTRICT Moulton weir and Ord Bend; construction of new levees from present levee terminus to vicinity of Chico Landing; construction of a weir near Chico Landing, extension of Moulton weir, and construction of a bypass through Upper Butte Basin; construction of new levees in Lower Butte Basin; enlargement of existing levees in Sutter, Tisdale, Sacramento, and Yolo Bypasses; and levee construction and/or channel enlargement on following minor tributaries of Sacramento River: Antelope Creek; Chico and Mud Creeks and Sandy Gulch; Butte and Little Chico Creeks; Cherokee Canal; Elder Creek; Deer Creek (Tehama County); Thomes Creek; and Willow Creek. Improvement provides for about 155 miles of channel improvement and about 294 miles of levees with an average height of 12 feet and a freeboard of 3 feet. Improvement also provides for revetment as required for protection of bypass levee slopes against erosion. Total first cost for project is $18,300,000 (October 1985), of which $11,900,000 is Federal, and $6,400,000 non-Federal for lands and damages, including relocations. (See table 35-N on project units classified and excluded from cost estimate.) (b) Sacramento River, Chico Landing to Red Bluff, CA: An extension of the existing Sacramento River Flood Control project which provides for construction of bank protection works and minor channel improvements as required on Sacramento River between Chico Landing and Red Bluff for flood control purposes. Estimated first cost (October 1985) for project work in Tehama, Butte, and Glenn Counties is $31,800,000, of which $30,000,000 is Federal cost and $1,800,000 non-Federal cost for lands and damages including relocations. (c) Sacramento River, CA, Bank Protection Project: Includes initial phase covering 405,000 lineal feet of bank protection and a second phase covering 430,000 lineal feet of bank protection under a long range program of bank protection, erosion control works, and setback levees at critical locations within limits of authorized or existing levees included in the Sacramento River Flood Control project to protect integrity of levee system for flood control purposes. Total estimated (October 1985) first cost for project is $135,000,000, of which $90,000,000 is Federal (including $2,845,000 for recreation facilities) and $45,000,000 non-Federal comprising $20,000,000 for lands and damages including relocations and $25,000,000 required cash contribution toward first cost. Construction in (a), (b), and (c) above supplements program of levee improvements as accomplished pursuant to 1917 Flood Control Act, as amended by subsequent acts, including 1941 Flood Control Act, and which are reported by California Debris Commission under Sacramento River, CA, flood control. (d) Authorization also provided for Black Butte Lake. For description of completed project see Annual Report for 1975. Federal first cost for project is $14,508,820, including $475,507 for basic recreation facilities. For future non-Federal reimbursement, see Local cooperation paragraph. Federal cost for recreation facilities funded from Code 710 appropriations is $1,000,162. A concessionaire at Black Butte Marina provided public use facilities in accordance with lease agreement with the Secretary of the Army at an estimated cost to date of $87,000. (e) Authorization also provided for construction of Table Mountain (Iron Canyon) project, an earthfill dam on Sacramento River about 3 miles north of Red Bluff, CA. This project unit was deauthorized August 5, 1977. For details, see Annual Report for 1978. Local cooperation. (a) Sacramento River and major and minor tributaries: Sec. 3, Flood Control Act of June 22, 1936, applies. Fully complied with for all work completed or under contract, and local interests indicated they will be able to fulfill requirements for remaining work as scheduled. Levee construction (107 miles) total requirement for the "active" project has been completed, transferred to, and accepted by the State. (b) Sacramento River, Chico Landing to Red Bluff: Sec. 3, Flood Control Act of June 22, 1936, applies; local interests must also assume responsibility for flood plain zoning. Fully complied with for portions completed in Tehama, Butte, and Glenn Counties; completed work, bank protection at 36 sites, was transferred to and accepted by the State. (c) Sacramento River Bank Protection Project: Sec. 3, Flood Control Act of June 22, 1936, applies. Local interests must also contribute an amount in cash that, when added to costs of lands, easements, rights-of-way and utility modifications, equals one-third of cost of each unit of remedial work; this contribution is estimated (October 1985) at $25,000,000. Local interests fully complied with requirements for all work completed or under contract, and indicated they will be able to fulfill requirements for remaining work as scheduled. In addition, for reaches where local interests request bank stabilization in lieu of more feasible levee setbacks, local interests will contribute costs over and above costs of setbacks, and provide local contribution indicated above. Completed units transferred to and accepted by the State. (d) Black Butte Lake: None required for construction. Local interests must pay the portion of first cost and annual operation and maintenance costs allocated to the conservation functions of the project; these costs are estimated at 39.9 percent of first cost and 40.2 percent of annual costs. From March 2,1960, to October 22,1970, contract between the Bureau of Reclamation and the State of California provided for repayment of irrigation storage costs; Bureau administered contract in accordance with reclamation law. Local interests paid a total of $77,205 for irrigation services during this period. Public Law 502, 91st Cong., 2d sess., October 23,1970, provided that Black Butte project be financially integrated with the Central Valley project, coordinated operationally with other Central Valley project storage units by the Bureau under the Secretary of the Interior, and that dam and reservoir at Black Butte be physically operated and maintained by the Corps in a manner compatible with recreational use of the reservoir. Operations and results during fiscal year. New work: (a) Sacramento River and major and minor tributaries-Minor engineering activities continued. 35-13 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 (b) Sacramento River Bank Protection Project-Engi-. neering and design activities continued. (See table 35-0 for construction accomplished and contract costs.) (c) Sacramento River, Chico Landing to Red Bluff-Bank protection. Bank protection on four sites, miles 241.0, 237.9, 237.7, and 239.5 (Unit 7), Sacramento River, Tehama County, way completed. (d) Black Butte Lake, regular funds: None. Code 710 funds: None. Mainte.- nance: Maintenance and operation activities continued. Paving of recreation roads and parking areas at Buckhorn recreation area, Black Butte Lake, was completed at a fiscal year contract cost of $58,276. Dam safety assurance studies were continued at fiscal year cost of $9,342. Structures were maintained in serviceable condition. Runoff above Black Butte Dam was below normal for the year. Maximum storage of 77,900 acrefeet occurred April 23, 1985. Maximum daily inflow to Black Butte reservoir was 2,570 cubic feet per second on November 28, 1984, and maximum outflow of 2,500 cubic feet per second occurred on November 30, 1984. Releases of water for irrigation totaled 178,900 acrefeet and flood control releases totaled 3,900 acre-feet. (e) Table Mountain (Iron Canyon) Lake: None. Historical summary. (a) Sacramento River and major and minor tributaries (active portions): Construction was initiated in May 1949 on Deer Creek and Butte Creek units; Cherokee Canal, Elder Creek, Chico and Mud Creeks, and Sandy Gulch units have been completed. Active portion of this improvement is about 96 percent complete. Work remaining is bypass levee revetment as required. (b) Sacramento River Bank Protection Project: Construction of first unit was initiated in June 1963; initial phase of project was completed in November 1974. Phase II is underway, and overall project is about 78 percent complete. (c) Sacramento River, Chico Landing to Red Bluff: Active portion of project, bank protection in Tehama County, was initiated in June 1963 and completed in March 1964. Project was reopened in June 1968 to place additional necessary bank protection. Work at 36 sites was completed in Tehama, Butte, and Glenn Counties as of September 1985 and transferred to State for maintenance. Bank protection on Sacramento River, Tehama County-one site, mile 215, (Unit 5), was completed November 1982, two sites, mile 209.5 and mile 217.5, (Unit 6), were completed in November 1983, and four sites, 241.0, 237.9, 237.7, and 237.5 (Unit 7) were completed in February 1985. (d) Black Butte Lake: Construction began in March 1960 and project is complete. Final land acquisition was completed in December 1966. Construction of main dam was initiated in June 1960 and completed in December 1963. Dam has been operating since November 1962 to provide the flood protection for which it was designed. Final cost allocation approved May 3, 1977. Dam safety assurance studies were initiated in FY 1980. Piezometer installation and slope for protection at the dam were completed in FY 1983. A cultural resources survey was completed in FY 1984. (e) Table Mountain (Iron Canyon) Lake: Project unit deauthorized as of August 5, 1977. 16. WALNUT CREEK, CA Location. Project is on Walnut Creek and lower reaches of its principal tributaries, Pacheco, Grayson, San Ramon, Las Trampas, Galindo, and Pine Creeks in Contra Costa County, CA. Improvement will extend from Suisun Bay to head of project about 1 mile above southern limits of city of Walnut Creek. City of Walnut Creek is about 10 miles south of Suisun Bay. (See Geological Survey quadrangles for area.) Existing project. Comprises extension of existing levees, construction of new levees and concrete channels, channel rectification and enlargement, and utilization of improvements constructed or planned by local interests. Plan provides for about 21.8 miles of channel improvement, two reinforced-concrete drop structures, two stilling basins, and 13.8 miles of levees. Cost estimate (1985) is $87,500,000 (includes an allowance for estimated inflation through the construction period), of which $62,800,000 is Federal cost and $24,700,000 is non-Federal cost (includes $19,700,000 for lands and damages and relocations except railroad facilities, and $5,000,000 required cash contribution for land enhancement benefits provided by the project). Local interests have expended about $3 million for flood control in the project area during the period 1955-1965, including the concrete conduits constructed through the city of Walnut Creek at an estimated cost of $1,000,000 considered a preproject condition to be incorporated in the Corps project. The cost thereof is not included in above costs of local cooperation. Improvement adopted by 1960 Flood Control Act (H. Doc. 76, 86th Cong., 1st sess., contains latest published map). Local cooperation. Section 3, Flood Control Act of June 22,1936, applies, except that relocation of railroad facilities is a Federal responsibility. In addition, local interests must make a cash contribution to the United States, in amount of 7.4 percent of cost of construction for land enhancement benefits provided by project. Cash contribution is estimated (October 1985) at $5,000,000. Local interests are represented by Contra Costa County Flood Control and Water Conservation District; formal assurances, including evidence of financial and legal ability to fulfill requirement for the cash contribution, were accepted by the Sacramento District Engineer on November 15, 1963. The Flood Control District furnished all rights-of-way required to date and indicated that it will furnish all requirements as needed for future construction. The Flood Control District will arrange for highway bridge modifications and utility relocations before start of work by the Corps contractor. Payment of required contributed funds will be made in installments in amounts equal to 7.4 percent of the estimated construction expenditure for each fiscal year. To date, $2,628,247 has been furnished. Operations and results during fiscal year. New work: Engineering and design for the uncompleted portions of Walnut and San Ramon Creeks and upper Pine Creek are continuing. Construction'contract for 35-14 SACRAMENTO, CA, DISTRICT Lower Pine and Galindo Creek channel improvement, Phase 3, was completed. Landscaping contract was completed at fiscal year cost of $118,693 and the 3.2 miles of landscaping was transferred to local interests for maintenance on January 28, 1985. Historical summary. Construction was initiated June 1964; project is about 80 percent complete. Total of 16.7 miles of channel improvement, 9.2 miles of levee construction, part of channel improvement landscaping, and Drop Structures No. 1 and 2 have been transferred to local interests for operation and maintenance. Planning and design continued on remaining reaches. Work remaining consists of channel improvement on Walnut Creek and San Ramon bypass (Ygnacio Valley Road to Rudgear Road along SPRR alignment) and upper Pine Creek. Construction responsibility was transferred from San Francisco District on April 1, 1982. 17. WILDCAT AND SAN PABLO CREEKS, CA Location. Project is located in vicinity of San Pablo and Richmond, Contra Costa County, CA, about 20 miles northeast of San Francisco, CA. Existing project. Plan of improvement consists of 15,900 lineal feet of channel improvements on Wildcat Creek and 9,600 lineal feet of channel improvements on San Pablo Creek. Improvements include channel deepening, levees, stilling basins, and flow control weirs. Plan would also create a linear park environment with picnic facilities, comfort stations, full environment treatment, and a two-mile segment of trail to connect with other regional park trails in the vicinity. Approved estimated cost of new work (1985) is $30,900,000, of which $17,600,000 is Federal cost, and $13,300,000 is non-Federal cost (includes $1,500,000 cash contribution). Improvements adopted by House and Senate Public Works Committee Resolutions June 9 and 15, 1976, respectively, under provisions of sec. 201 of Flood Control Act of 1965 (H. Doc. 511, 94th Cong., 2d sess., contains latest published map). Local cooperation. Local interests will be required to: (a) provide, without cost to the United States, all lands, easements, and rights-of-way necessary for construction and operation of the project, including disposal areas, and adhere to requirements of sec. 210 of the 1970 Uniform Relocation Assistance and Real Property Acquisition Policies Act, Public Law 91-646; (b)modify or relocate all utilities and bridges (except railroad) necessary for construction and maintenance of the project with such modifications and replacements being in accordance with plans approved by the Chief of Engineers, and replace vehicular traffic facilities, including, but not limited to, streets, curbs, gutters, and signs affected by the project; (c) maintain and operate the flood control portion of the project after completion, in accordance with regulations prescribed by the Secretary of the Army, and prevent encroachment of the flood channels that may result in decreasing the effectiveness of the project; (d) maintain, operate, and replace recreation facilities; (e) hold and save the United States free from damages due to construction works; (f) adjust all claims regarding water rights that might be affected by the project; (g) make a cash contribution prior to start of construction for that portion of the cost of recreation lands and recreational facilities; (h) assure access to all persons on equal terms for approved recreational use; (i) at least annually inform affected interests regarding the limitations of protection afforded by the project; and (j) publicize flood plain information in the areas concerned and provide this information to zoning and other regulatory agencies for their guidance and leadership in preventing unwise future development in the flood plain, and in adopting such regulations as may be necessary to insure compatibility between future development and protection levels provided by the project. The Board of Supervisors of Contra Costa County by Resolution 73- 466, June 25, 1973, agreed to assume obligations of local cooperation. On November 9, 1976, the Board reaffirmed sponsorship by Resolution 76-960. Contra Costa County Flood Control and Water Conservation District Board of Supervisors formed an Assessment District, August 3, 1982, which assures availability of funds for local share of non-Federal portion of project costs for a modified plan of improvement. Prior to construction, the Board of Supervisors of Contra Costa County will be required to furnish assurances to comply with sec. 221 of the 1970 Flood Control Act and sec. 77 of the 1974 Flood Control Act and to furnish assurance that in the acquisition of all lands, easements, and rights-of-way they will comply with requirements of sec. 210 of the 1970 Uniform Relocation Assistance and Real Estate Acquisition Policy Act, Public Law 91-646. A letter of intent to sign sec. 221 agreement was furnished by local sponsor on April 23, 1985. Operations and results during fiscal year. In October 1983, work was resumed by Sacramento District on the project. Drafts of a general design memorandum and an environmental impact statement were continued. Historical summary. Project has been inactive since 1979. Project responsibility was transferred from San Francisco District on April 1, 1982. In October 1983, project work was resumed by Sacramento District. Drafts of a general design memorandum and an environmental impact statement have been initiated. 18. INSPECTION OF COMPLETED FLOOD CONTROL PROJECTS Approved regulations for operation and maintenance of flood control works, part 208, title 33, Code of Federal Regulations, provide for inspection of completed projects transferred to local interests for operation and maintenance to determine status of project and insure compliance with regulations. During fiscal year, inspections were made of: Completed units of Sacramento River and major and minor tributaries; completed units of 35-15 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Sacramento River, Chico Landing to Red Bluff; completed units of Sacramento River flood control project, Kings River Channel Improvement (Pine Flat Lake project), and Walnut Creek project; American River levees; Chester, North Fork Feather River; levee and channel improvements on Chowchilla River (Buchanan project) and Fresno River (Hidden project); Duck Creek diversion, Green Valley Creek, Littlejohn Creek, Mormon Slough, Bear Creek, Kern River-California Aqueduct Intertie, and North Fork, Pit River at Alturas, all in California; Truckee River, CA and NV; completed units of lower San Joaquin River and tributaries, CA; Big Dry Creek Dam and diversion, CA; Reese River, Battle Mountain, NV; Sevier River, Redmond and vicinity, Jordan River, Big Wash near Milford, and Kays Creek, all in Utah; various emergency flood control works under authority of sec. 208, Flood Control Act of June 30, 1948, and September 3, 1954; Public Law 99, June 28, 1955, and antecedent legislation; and sec. 14 of Flood Control Act of July 24,1946. Maintenance inspections conducted indicate that existingagreements and regulations are being complied with on completed flood control works. Continuing effort is required to improve maintenance practices and active steps are being taken by responsible State and local agencies to achieve desired results. Local agencies were advised, as necessary, of measures required to maintain these projects in accordance with standards prescribed by regulations. Total cost of inspection for fiscal year of $630,196 included continuation of dam safety assurance program for Folsom Lake, CA ($518,104). 19. FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION Flood control activities pursuant to sec. 205, Public Law 858, 80th Congress, as amended (Preauthorization). Costs for preauthorization studies for fiscal year were as follows: $106,582 for Fourteenmile Slough, CA; $8 miscellaneous cost for Lower Coyote Creek, CA; and $3,900 for Potter Creek, San Joaquin County, CA (infeasible). Emergency flood control activities-repair, flood fighting, and rescue work (Public Law 99, 84th Cong., and antecedent legislation). Federal cost for fiscal year was $2,757,246, of which $190,834 was for disaster preparedness, $1 for flood emergency operations, $1,526,868 for repair and restoration, and $1,039,543 for advance measures. Emergency bank protection (sec. 14, 1946 Flood Control Act, Public Law 526, 79th Cong.). Federal cost for fiscal year was $4,957 for preparation of an operations and maintenance manual, Mormon Slough, Jack Tone Road. Snagging and clearing navigable streams and tributaries in interest of flood control (sec. 208, 1954 Flood Control Act, Public Law 780, 83d Cong.). No snagging and clearing activities this fiscal year. Flood insurance activities (sec. 1301-1377, 1968 Housing and Urban Development Act, Public Law 90-448 as amended). In coordination with flood control activities, two flood insurance studies were continued and two flood insurance studies were completed in accordance with Inter- Agency Agreement EMW-E-1153 at a fiscal year cost of $229,903 under Federal Emergency Management Agency reimbursable order. 20. SCHEDULING FLOOD CONTROL RESERVOIR OPERATIONS In accordance with sec. 7, Flood Control Act of 1944, summaries of monthly operations at Big Dry Creek, Boca, Camanche, Del Valle, Folsom, Friant (Millerton Lake), Indian Valley, Los Banos Detention, New Bullards Bar, New Don Pedro, New Exchequer (Lake McClure), New Melones, Oroville, Prosser, Shasta, and Stampede, CA; East Canyon, Echo, Lost Creek, Pineview, Starvation, and Wanship, UT; Blue Mesa, Lemon, Paonia, and Vallecito, CO; and Navajo, NM reservoirs were prepared. Work on a revision to the Truckee River Basin water control manual (which includes Boca, Stampede, and Prosser Reservoirs) was completed and work was initiated on the Blue Mesa water control manual. Corps personnel provided advice as requested during flood control operations at all sec. 7 reservoirs. Fiscal year cost was $277,065. Total cost to September 30, 1985, $2,667,156. Multiple-Purpose Projects including Power 21. NEW MELONES LAKE, CA Location. On Stanislaus River about three-quarters mile downstream from existing Melones Dam and about 35 miles northeast of city of Modesto. (See Geological Survey quadrangles of the area.) Existing project. Provides for construction of (a) an earth and rockfill dam about 625 feet high to create a reservoir with gross storage capacity of about 2,400,000 acre-feet for flood control, irrigation, power, general recreation, fish and wildlife, and other purposes, and (b) a powerplant below the dam with an installed capacity of 300,000 kilowatts. Upon completion of construction of dam and powerplant by the Corps, the project became an integral part of Central Valley project and is being operated and maintained by the Secretary of the Interior pursuant to Federal reclamation laws, except that the flood control operation of the project shall be in accordance with rules and regulations prescribed by the Secretary of the Army. Maintenance of Stanislaus River channel from Goodwin Dam to San Joaquin River to a capacity of at least 8,000 cubic feet per second will also be Corps responsibility. Approved estimated (October 1985) Federal cost is $382,000,000 (includes an allowance for estimated inflation through the construction period). For future non-Federal reimbursement, 35-16 SACRAMENTO, CA, DISTRICT see Local cooperation paragraph. In addition, local interests expended $300,000 for levees along lower reaches of Stanislaus River. Existing project was adopted by 1962 Flood Control Act (H. Doc. 453, 87th Cong., 2d sess., contains latest published map). This act modified original authorization adopted by 1944 Flood Control Act. (H. Flooa Control Committee Doc. 2, 78th Cong., 2d sess., contains latest published map.) The 1944 Flood Control act established $8 million monetary limitation for partial accomplishment of project. Further monetary authorizations of $2.5 million, $5 million, $13 million, $2 million, $17 million, $18 million, $44 million, $83 million, $46 million, $6 million, and $61 million were provided for this project by Public Laws 235 and 780, 83d Cong., and 85-500, 90-17, 90-483, 91-282, 92-222, 93-251, 94-397, 95-104, and 95-189, making a total monetary authorization of $305,500,000 available for the basin plan comprising Lower San Joaquin River and tributaries, including Tuolumne and Stanislaus Rivers, CA. Since FY 1979, appropriations have not been subject to the river basin monetary limitation and legislation is before Congress to eliminate the monetary limitation ceiling. Local cooperation. Based on approved preliminary cost allocation studies (July 1965) local interests will be required to pay 35.2 percent of first cost and 12.7 percent of annual operation and maintenance costs allocated to irrigation. In addition, 31.1 percent of first cost and 62.5 percent of annual cost would be allocated to power. Local interests must also maintain existing private levees along Stanislaus River from Goodwin Dam to San Joaquin River and prevent encroachment on channel and floodway between levees to preserve safe carrying capacity throughout the reach of at least 8,000 cubic feet per second. Recovery of costs allocated to irrigation and power will be the responsibility of the Bureau of Reclamation. Reimbursement of costs will be in accordance with Bureau policies and procedures for the Central Valley project. State of California officially adopted project by chapter 918 of statutes of 1963, and by chapter 1438 of those statutes authorized State Reclamation Board to furnish required assurances. The Board, by letter dated December 13, 1963, stated it would furnish required assurances when formally requested to do so. Assurances were requested by letter of December 30, 1977. On October 2, 1979, the Board reaffirmed its intent to furnish the required assurances. On January 6, 1983, the Board provided formal assurances of local cooperation. Operations and results during fiscal year. New work: Engineering activities continued including continuation of plans and specifications for the Lower Stanislaus recreation areas, minimal recreation facilities only. Fiscal year costs for major items of work included: Continuation of land acquisition activities, $1,257,595; continuation of Glory Hole minimal recreation facilities contract, $131,598; initiation and completion of a boundary fencing contract, $134,669; initiation and functional completion of Tuttletown minimal recreation facilities, $1,820,422; completion of Lower. Stanislaus Phase I, minimal recreation facilities; $236,496; and completion of Lower Stanislaus Administration Building contract, $556,575. Maintenance: Maintenance and operation activities continued on Lower Stanislaus River. Historical summary. Construction was initiated in August 1966. Main dam contract which was awarded in March 1974 has been completed; dam dedication ceremonies were held July 14, 1979. Cultural resources preservation, water intake facilities, flood control and irrigation tailrace modification, reservoir area clearing, Tuttletown Phase I recreation area, Oakdale recreation, Glory Hole Phase I recreation area, and operations access road contracts have all been completed. Glory Hole minimal recreation facilities contract has been initiated. A boundary fencing contract, Lower Stanislaus Phase I minimal recreation facilities contract, Lower Stanislaus Corporation Yard contract, and Lower Stanislaus Administration Building contract have been completed. Tuttletown minimal recreation facilities contract has been functionally completed. Overall project is nearing completion except for Lower Stanislaus River recreation facilities. Remaining recreation facilities were unscheduled pending development of cost sharing agreements with local interests. A Memorandum of Understanding between the Department of the Interior and the Department of the Army transferring the New Melones dam and reservoir from the Corps of Engineers to the Bureau of Reclamation was executed on November 20, 1979. Agreement provides that the Corps complete land acquisition actions and retain budgeting, design, and construction responsibility for reservoir clearing and recreation development; completion of cultural resources mitigation in project area was vested in the Department of the Interior. The California State Water Resources Control Board's Decision 1422 of April 1973 established conditions which impacted on the planned filling and operation of the project by the Department of the Interior. As a result, the Department of Interior brought suit against the State of California claiming State limitations on project operation were contrary to Congressional intent and authority. The case was heard before the U.S. District Court in Fresno, CA, and in early March 1981, a Federal judge ruled that the Federal Government could fill the New Melones reservoir for purpose of generating electrical power, but not for agricultural or other purposes. Both the Government and the California State Resources Control Board appealed this decision to the 9th Circuit Court of Appeals in San Francisco, CA. On December 20, 1982, the Court upheld all 25 requirements placed on the Federal Government by the State Water Resources Control Board. The decision reversed the lower court's decision to permit filling of the reservoir for generating electrical power. The Bureau of Reclamation subsequently filed for a permit from the State Water Resources Control Board to fill the reservoir. Permit was approved. The Bureau had 35-17 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 originally started generating power on a limited basis on July 1, 1979; however, after the filling of the reservoir in spring of 1983, full power generating benefits are being attained. Project is about 97 percent complete. General Investigations 22. Surveys Fiscal year costs were $1,803,369, of which $1,640,369 was for flood damage prevention studies; $3,000 for coordination with Soil Conservation Service; $10,000 for coordination with Bureau of Reclamation pertaining to projects under reclamation program (including PL 984); $70,000 for special investigations; $40,000 review of FERC licenses; and $40,000 for planning assistance to states ($15,000, CA; $15,000, UT; and $10,000, CO). MORRISON CREEK STREAM GROUP, CA (PHASE I, FEASIBILITY STUDY) Phase I studies (estimated cost $3,000,000) were authorized by sec. 101(a), Water Resources Development Act, of 1976, in accordance with Report of Chief of Engineers, March 2, 1976. Proposed plan of improvement would be located on streams in Morrison Creek Stream Group Basin in the central part of Sacramento County and would provide for construction of a dam with an 11,000 acre-foot reservoir at the Vineyard site on Elder and Laguna Creeks, diversion of Morrison Creek flows into this reservoir, construction of 26 miles of levee and 66 miles of channel work along streams in the basin, and purchase of lands and related construction for a 7,800-acre flood retardation basin in the Beach- Stone Lakes area. Phase I studies were continued at a fiscal year cost of $373,768. CONTINUATION OF PLANNING AND ENGINEERING CACHE CREEK BASIN, CA Project is located on eastern slope of the Coast Range. Clear Lake unit is about 110 miles north of San Francisco and Settling unit is about 15 miles northwest of Sacramento. Plan of improvement consists of two project units: Upper basin at Clear Lake-widening and/or deepening 3.3 miles of existing 5 mile long Clear Lake outlet channel to a capacity of 8,000 cubic feet per second, constructing a 1.1 mile long bypass channel around the highly developed area adjacent to existing channel, and nonstructural measures; and lower basin at the mouth of Cache Creek-enlarging existing perimeter levees of Cache Creek Settling Basin an average of 12 feet to provide 50 years of sediment storage capacity and enlarging existing project levees from settling basin mouth upstream to County Road 102, reconstructing and enlarging existing Cobble weir, degrading the existing training levees and rebuilding them adjacent to the western perimeter levee to allow utilization of entire basin for sediment deposition, purchasing in fee 3,600 acres of existing settling basin and establishing a wildlife refuge and nonstructural measures. Preconstruction planning estimate is $2,300,000. Continuation of planning and engineering, including a sedimentation study for Upper Basin and separate General Design Memorandums for the Clear Lake Outlet Channel (Upper Basin) and Cache Creek Settling Basin (Lower Basin) was continued at a fiscal year cost of $429,249. REDBANK AND FANCHER CREEKS, CA Project is located northeast of Fresno-Clovis metropolitan area in Fresno County, CA. Plan of improvement includes flood control detention basins on Redbank Creek, Pup Creek, and Alluvial Drain; construction of a flood control reservoir on Fancher Creek; and enlargement of Big Dry Creek project to provide increased flood protection and recreation opportunities. Estimated preconstruction planning cost is $3,425,000. General Design Memorandum studies including environmental, hydrology, real estate, cultural resources, and foundation exploration studies and surveys were continued and Feature Design Memorandums were initiated on Fancher Creek and Big Dry Creek as well as on three detention basins (Pup Creek, Alluvial Drain and Redbank Creek) at a fiscal year cost of $933,870. 23. COLLECTION AND STUDY OF BASIC DATA Technical assistance was performed for other Federal agencies as well as non-Federal agencies in connection with Flood Plain Management Services Program at fiscal year cost of $369,511. No Flood Plain Information Studies were prepared after FY 1980. Fiscal year costs for hydrologic studies were $8,000. 24. RESEARCH AND DEVELOPMENT The Hydrologic Engineering Center was designated as a separate Field Operating Agency as of January 1, 1979, in accordance with OCE permanent orders 1-1, January 10,1979, but Sacramento District is continuing to provide advisory and administrative support services to HEC as specified in local support agreement DACW05-79-A-0038 of March 1979. Fiscal year costs were $1,069,583, of which $148,016 was for planning methodologies, $586,738 was for analytical techniques, $115,900 for Water Conservation and Supply, $171,029 for risk assessment for Corps dams and $47,900 for earth resources satellites, all at the Hydrologic Engineering Center. 35-18 SACRAMENTO, CA, DISTRICT 25. ADVANCE ENGINEERING AND DESIGN COTTONWOOD CREEK, CA Project will be located on main stem and the North, South, and Middle Forks of Cottonwood Creek on eastern slope of the Coast Range and southern slope of Trinity Range between cities of Redding and Red Bluff, CA, and was authorized by the 1970 Flood Control Act (Document not yet printed). Plan of improvement provides for two multiplepurpose reservoirs, one at Dutch Gulch (capacity 900,000 acre-feet) and one at Tehama (capacity 700,000 acrefeet), and includes base facilities for future installation of hydropower generating equipment. General Design Memorandum and Environmental Impact Statement were completed in FY 1984. Advance Engineering and Design activities are being discontinued in FY 1985 as by letter of June 25,1985, the State of California indicated they could not financially participate in the project at this time. Estimated preconstruction planning cost is $20,900,000. FAIRFIELD VICINITY STREAMS, CA Project will be located on five streams in vicinity of cities of Fairfield and Suisun, Solano County, CA, and was adopted under sec. 201, 1965 Flood Control Act (1970 Senate and House Public Works Committee resolutions (H. Doc. 159, 91st Cong., 1st sess., contains latest published map). Plan of improvement provides for 8.7 miles of channel improvementon Ledgewood, Laurel, and McCoy Creeks and diversion of three creeks upstream from Fairfield (Pennsylvania Avenue Creek into Ledgewood Creek, Union Avenue Creek into Laurel Creek, and Laurel Creek into McCoy Creek). Project includes trail-based recreation facilities. Project has been in "deferred" status since September 15, 1977 due to lack of local assurances. In April 1982, the cities of Fairfield and Suisun requested reactivation of project and expressed intent to provide local assurances for a modified project providing 100- year level of flood protection rather than 200-year level as authorized. On June 23,1982, project was reclassified from "deferred" to "active" status. Phase II General Design Memorandum Supplement No.1 was continued. Post Authorization Change is no longer required. Estimated preconstruction planning cost is $1,147,000. Project is included in FY 1985 Supplemental Appropriations Act (Public Law 99-88) as a new construction start. Construction initiation is contingent upon approval of Local Cooperation Agreement (sec. 221). PAJARO PIVER BASIN, CA Pajaro River and tributaries drain an area of 1,300 square miles in the Coast Range and empty into Monterey Bay about 75 miles south of San Francisco. Pajaro Valley sub-basin in Santa Cruz and Monterey Counties includes 112 square miles in lower 13 miles of Pajaro River. Plan of improvement consists of construction of a variable setback levee beginning approximately 1,000 feet upstream of Miller Avenue and ending 2,000 feet below Thomas Road Bridge on north side of Uvas Creek. Phase I General Design Memorandum with Environmental Impact Statement was completed by San Francisco District in FY 1982. A Post Authorization Change was approved by the Office of Chief of Engineers on August 4,1982. Responsibility for remaining portions of advance engineering and design, plans and specifications and construction was transferred to the Sacramento District in April 1982. Phase I General Design Memorandum was approved as basis for continued preconstruction planning as a combined General Design Memorandum. Combined General Design Memorandum was completed in November 1984 and approved on June 17,1985. Record of Decision was signed on June 20, 1985. Plans and specifications for levee improvement and construction of recreation trails were approved in September 1985. Estimated preconstruction planning cost is $560,000. LITTLE DELL LAKE, UT Project will be located on Dell Creek, a tributary of Parleys Creek, about 8 miles east of Salt Lake City, UT. Project providing for construction of a dam about 253 feet high to create a reservoir with a gross capacity of 30,000 acre-feet for flood control, municipal and industrial water supply, recreation and fish and wildlife was authorized by the 1968 Flood Control Act (S. Doc. 53, 90th Cong., 1st sess., contains latest published map) as modified by sec. 170, Water Resources Development Act of 1976, Public Law 94-587, October 22, 1976. The facility would be operated in conjunction with existing downstream 3,200 acre-foot Mountain Dell Reservoir on Parleys Creek for flood control and water supply. Plans and specifications for redesign of Highway 65 realignment and relocation were initiated by the Utah Department of Transportation. An evaluation of cost for relocating the Little Dell Pony Express Station was completed by an architectural-engineering contract as part of the cultural resources aspect of the project. Estimated preconstruction planning cost is $2,620,000. Project is included in FY 1985 Supplemental Appropriations Act (Public Law 99-88), August 15, 1985, as a new construction start. Construction initiation is contingent upon approval of Local Cooperation Agreement (sec. 221). MERCED COUNTY STREAMS, CA Project will be located on streams draining from Mariposa County foothills of Sierra Nevada into Merced County in vicinity of city of Merced, CA. Project is modification of Merced County Stream Group, CA, 35-19 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Improvement No. 13, authorized by 1944 Flood Control Act and completed FY 1957. Project providing for construction of three new reservoirs-Castle, Haystack Mountain, and Marguerite on Canal, Black Rascal, and Deadman-Dutchman Creeks, respectively, and enlargement of four existing reservoirs-Burns, Bear, Owens, and Mariposa, was authorized by 1970 Flood Control Act (Document not yet printed). Current plan of improvement would defer enlargement of existing Burns reservoir, Mariposa reservoir, construction of Marguerite Dam, and the irrigation function associated with the latter two facilities, enlargement of existing Owens reservoir and about 32 miles of levee and channel improvement on Owens, Mariposa, and Deadman-Dutchman Creeks. Phase I General Design Memorandum was approved February 1982 and Phase II General Design Memorandum was approved June 1982. Channel Improvement Design Memorandum was completed in September 1984. Estimated preconstruction planning cost is $4,550,000. Project is included in FY 1985 Supplemental Appropriations Act (Public Law 99-88) as a new construction start. Construction initiation is contingent upon approval of Local Cooperation Agreement (sec. 221). SACRAMENTO RIVER DEEP WATER SHIP CHANNEL, CA Plan of improvement consists primarily of deepening to 35 feet the Suisun Bay and Sacramento River Deep Water Ship Channels from New York Slough to Port of Sacramento, and the Avon to New York Slough reach to 35 feet which will be accomplished under the San Francisco Bay to Stockton (John F. Baldwin and Stockton Ship Channels) project. Selected plan also provides for a water quality monitoring program, authority to construct a submerged sill, 45 acres of land for establishment of wetland habitat, and 156 acres of land for upland habitat to mitigate for losses of such habitat. Draft General Design Memorandum and Environmental Impact Statement were completed in August 1985. Estimated preconstruction planning cost is $1,475,000. Project is included in FY 1985 Supplemental Appropriations Act (Public Law 99-88), August 15, 1985, as a new construction start. Construction initiation is contingent upon approval of Local Cooperation Agreement (sec. 221). 26. OTHER WORK UNDER SPECIAL AUTHORITY Under the Aquatic Plant Control Program (River and Harbor Act of 1965, sec. 302, Public Law 289, 89th Congress) a State Design Memorandum and an environmental assessment regarding the waterhyacinth problem in the Sacramento-San Joaquin Delta, CA, were completed by the Corps in FY 1985. The Calif Department of Boating and Waterways had requested assistance from the Corps on September 28, 1981, to find a solution to the waterhyacinth problems in the Delta. In a meeting on May 28, 1985, the Department of Boating and Waterways notified the Corps that the State control program had reduced the problem to a maintenance problem, that State funding is adequate to operate the current waterhyacinth maintenance program, and that Federal assistance is not needed at this time. State control program included chemicals to eliminate the immediate problem and biological control agents to provide long term control. Cost sharing agreement (70 percent Federal-30 percent State) was not applicable to preparation of State Design Memorandum nor the environmental assessment. Total Federal cost as of September 30, 1985, was $80,649. 35-20 SACRAMENTO, CA, DISTRICT TABLE 35-A COST AND FINANCIAL STATEMENT See Section Total Cost to in Text Project Funding FY 82 FY 83 FY 84 FY 85 Sep 30, 1985 1. Sacramento River, CA 2. San Francisco Bay to Stockton, CA (John F. Baldwin and tockton Ship Channels) New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost 3. San Joaquin River, New Work CA Approp. Cost Maint. Approp. Cost 4. Buchanan Dam-H.V. New Work Eastman Lake, Approp. Chowchilla River, CA Cost (Federal Funds) Maint. Approp. Cost (Contributed Funds, New Work Other) Contrib. Cost 5. Calaveras River and New Work Littlejohn Creek and Approp. Tributaries including Cost New Hogan Lake and Maint Farmin n Dam, CA Approp. (Federa Funds) Cost (Contributed Funds, New Work Other) Contrib. Cost 6. Corte Madera Creek, CA New Work (Federal Funds) Approp. Cost Required Contributed New Work unds) Contrib. Cost (Contributed Funds, New Work ther) Contrib. Cost 7. Hidden Dam-Hensley New Work Lake, Fresno Approp. River, CA Cost (Federal Funds) Maint. Approp. Cost Contributed Funds, New Work her) Contrib. Cost 8. Isabella Lake, Kern New Work River, CA Approp. (Federal Funds) Cost Maint. Approp. Cost (Contributed Funds, New Work Other) Contrib. Cost 2,927,000 3,057,288 1,574,000 1,437,564 1,514,000 618,949 6,700,000 3,890,097 856,000 2,025,601 3,680,000 4,314,658 1,835,000 1,892,496 13,580,000 14,903,051 40,331,1921 40,331,1921 37,115,8312 37,065,7583 34,943,000' 33,663,9276 -- - 5,833,117' - - - 5,833,1176 20,000 943,000 850,000 625,000 11,927,4761 18,645 892,679 898,753 565,138 11,864,581' - - - - 27,369,597 42,078 33 - - 27,369,597 769,000 830,000 804,000 819,000 5,873,500 704,757 766,878 889,621 861,266 5,798,901 - - - - 111,1878 - - - 111,1878 - - - 23,723,1449 - - - - 23,723,1449 921,000 945,000 1,074,000 1,563,000 12,018,1691s0 915,116 923,280 1,093,472 1,551,672 11,880,77110 - 10,000 30,000 40,000 1,374,25111 12 13 - 2,248 24,440 43,920 1,364,85911 12 14 - 35,000 325,000 525,000 7,884,72515 - 34,868 281,271 390,052 7,705,9175 - - - 110,000 216,09516 17 - - - 5,156 106,48017 - - - 536,92118 - - - 536,92118 - - - 30,555,426 - - - 30,555,426 1,216,000 510,000 773,000 969,000 6,984,500 1,456,926 742,736 855,484 940,029 6,906,210 - - - 165,11219 - - - 165,11219 - - - 24,450,53720 21 - - - 24,450,537 021 1,461,640 2,227,400 1,773,000 3,450,000 21,013,99822 1,244,401 1,924,520 1,920,956 3,633,385 20,803,02822 S- - 438,0002 - - - 4 38,0002 35-21 i REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 35-A (Cont'd) COST AND FINANCIAL STATEMENT See Section in Text Project 9. Kaweah and fule Rivers including Terminus Dam and Success Lake, CA Contributed Funds, ther) 10. Lower San Joaquin River, CA 11. Martis Creek Lake, Martis Creek, NV, and CA 12. Merced County Stream Group, CA 13. Pine Flat Lake and Kings River, CA (Federal Funds) (Contributed Funds, Other) 14. Russian River Basin, CA Coyote Valley Dam (Lake Mendocino) and Channel Improvements (Federal Funds) (Contributed Funds, Other) Dry Creek (Warm Springs) Lake and Channel Improvements CA (Federal Funds) Contributed Funds, ther) 15. Sacramento River and Tributaries, CA from Collinsville to hata Dam (ederal Funds) Required Contributed unds) 1 1 j Total Cost to FY 82 FY 83 FY 84 FY 85 Sep 30, 1985 1,616,000 1,534,147 Funding New Work Approp. Cost Maint. Approp. Cost New Work Contrib. Cost New Work Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Contrib. Cost New Work Approp. Cost Maint. Approp. Cost New Work Contrib. Cost New Work Approp. Cost Maint. Approp. Cost New Work Contrib. Cost New Work Approp. Cost Maint. Approp. Cost New Work Contrib. Cost 1,246,000 1,305,758 37,900,000 2 34,273,493 2 - - - 34,997,2302 - - - 34,997,230* 1,850,000 1,524,000 1,652,000 19,080,5252 1,660,695 1,758,899 1,623,969 18,920,600w -- - 20,000 62,420" " - 3,364 45,784" " - 350,000 2,300,000 2,650,000 - 311,799 2,259,644 2,571,443 - - - 8,504,989x S- - 8,504,98930 243,000 242,000 1,069,000 3,446,350 165,188 300,768 947,669 3,294,729 - - - 2,751,2591 - - - 2,751,259"' 120,000 47,000 130,000 1,359,506 100,652 97,228 81,967 1,306,490 - - - 43,356,265m 04 - - - 43,356,265k * 4 1,498,000 1,481,000 1,448,000 16,756,285w 1,381,523 1,401,043 1,632,427 16,669,238k - - - 110,0006 - - 110,000" - - 14,435,869-w - - - 14,435,869v 1,518,000 1,707,000 1,500,000 20,147,075w * 1,196,832 2,036,905 1,565,404 20,056,1511 89 20,000 50,000 85,000 155,00040 12,795 56,295 81,218 150,30841 3,548,000 12,000,000 5,500,000 284,834,6452 2,397,207 16,490,897 5,301,011 283,341,60442 797,000 1,330,000 1,213,000 753,145 1,141,392 1,316,176 - - 30,000 -. -. -. 3,726,000 2,759,156 1,589,000 1,159,591 950,000 1,011,197 2,150,000 1,925,392 1,154,000 1,554,463 752,000 97,482 4,365,000 4,360,826 1,330,000 1,382,425 495,000 484,650 1,508,000 1,524,472 30,000 40,400 4,102,000 5,216,643 969,000 906,080 1,723,000 2,363,965 5,429,0003 5,287,3324 60,000" 40,4004 88,600,508" 47 88,360,711" 47 11,936,3349 11,797,469" 16,955,538 16,860,347 35-22 192,000 192,004 89,000 66,942 1,337,000 1,383,372 SACRAMENTO, CA, DISTRICT TABLE 35-A (Cont'd) COST AND FINANCIAL STATEMENT See Section Total Cost to in Text Project Funding FY 82 FY 83 FY 84 FY 85 Sep 30, 1985 Contributed Funds, New Work ther) Contrib. - 10,000 34,000 75,000 2,561,362,9 0 Cost - 4,428 3,143 96,121 2,546,0544 50o61 16. Walnut Creek, CA New Work (Federal Funds) Approp. 5,965,000 4,050,000 1,335,000 1,280,000 38,856,43062 Cost 4,971,022 4,119,569 2,848,189 994,554 38,481,7100 Required Contributed New Work unds) Contrib. 482,688 928,624 47,165 -483,000 2,628,247" Cost 393,269 800,233 239,037 -476,657 2,604,7255 Contributed Funds, New Work ther) Contrib. 232,200 781,026 220,000 622,000 3,085,0715 Cost 177,082 877,114 - 783,015 3,021,3276 17. Wildcat and San Pablo New Work Creeks, CA Approp. - - 320,000 500,000 1,930,000 Cost - - 313,561 359,187 1,782,748 21. Lower San Joaquin New Work River and Approp. 12,700,000 6,849,000 5,700,000 4,700,000 341,437,99657 8 Tributaries, CA Cost 12,207,662 5,825,274 6,251,283 5,500,387 340,827,02757 58 including Tuolumne Maint. Rnd Sta nislaus Approp. 388,000 410,000 411,000 437,000 2,360,000 Rivers,C AkNee,w CA Cost 361,647 368,700 433,032 462,832 2,329,369 Melones Lake, CA (Federal Funds) (Contributed Funds, New Work Other) Contrib. - - 80,000 - 80,0005 Cost - - 4,486 - 4,4866 1. Includes the following amounts for new work: Regular funds: Previous project, $185,198; existing project, $585,436 for shallow-draft and $39,560,558 for deep-draft. 2. Includes the following funds for maintenance: Regular funds: Previous project, $553,720; existing project, $15,345,907 for shallow-draft and $21,146,204 for deep-draft; and deferred maintenance funds, $70,000 for shallow-draft. 3. Includes the following costs for maintenance: Regular funds: Previous project, $553,720; existing project, $15,280,224 for shallow-draft and $21,161,815 for deep-draft; and deferred maintenance funds, $70,000 for shallow-draft. 4. Includes $15,820,000 funds for Sacramento District and $19,122,000 or San Francisco District. 5. Includes $15,746,670 costs for Sacramento District and 17,917,256 for San Francisco District. was wf.o rI nwclourdke s .$d1o,n1e5 8a,3l4o8npeu b3l0i-cf owoto rkc hfuanndnse,l o fiwn hSicuhi s$u2n0 7B1a9y8 Channel; excludes $19,000 expended for engineering for inactive portion of 1950 modification. In addition, $1,342,500 was expended from required contributed funds. 7. In addition, $1,250 was expended from required contributed funds. 8. Contributed funds, other, from State of California for design and construction of downstream channel improvements on Ash and Berenda Sloughs below Buchanan Dam. 9. Includes Code 710 funds and costs for recreation facilities at New Hogan Lake: Total to date $897,742. 10. Includes $99,000 special recreation use fees and costs at New Hogan Lake. 11. For miscellaneous construction under local cooperation requirements, primaril Bear Creek, San Joaquin County; includes $108,056 as related to Duck and LittleJohn Creeks channel improvements as part of Farmington Dam project unit. 12. Includes $393,195 contributed funds, other, from California Department of Boating and Waterways for design and construction of boat launching and related facilities, and $30,000 for design and construction of a boarding float at North Shore recreation area at New Hogan Lake. 13. Includes $80,000 contributed funds, other, from Calaveras County Water District for New Hogan hydropower studies. 14. Includes $70,608 contributed funds, other, costs for New Hogan hydropower studies. 15. Includes $6,999,725 San Francisco District construction funds and costs. 16. $8,695 contributed funds transferred to Sacramento District in FY 1983. 17. Includes $97,400 San Francisco District required contributed funds and costs. 18. Contributed funds, other, from Marin County for miscellaneous bridge and road relocations at Corte Madera Cre1e9k.. Contributed funds, other, from State of California for miscellaneous design and construction at Hidden Dam. 20. Includes total Code 710 funds and costs for recreation facilities at Isabella Lake: Total to date $2,199,085. 21. Includes $224,000 Code 713 funds and costs for improvement at Tilli Cree ek and Live Oak campgrounds. 22. Includes $407,640 special recreation use fees and costs at Isabella Lake. 23. Includes $56,500 maintenance and operation of dam funds and costs (96X5125) at Isabella Lake for FY 1985. 24. Funds from California Department of Boating and Waterways for design and construction of boat launching and related facilities at Old Isabella Road and Isabella Peninsula. 25. Includes Code 710 funds and costs for recreation facilities: Success Lake: Total to date $747,048. Terminus Dam: Total to date $700,004. 26. Includes $165,000 special recreation use fees and costs at Success Lake. 35-23 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 35-A (Cont'd) COST AND FINANCIAL STATEMENT 27. Contributed funds, other, from State of California Department of Boating and Waterways and costs for acquisition of a boarding float at Success Lake, $30,000 and at Terminus Dam, $12,420. 28. Includes $20,000 contributed funds, other, from the Kaweah River Power Authority, Visalia, CA, for Terminus Dam hydropower studies. 29. Includes $3,364 contributed funds, other, costs for Terminus Dam hydropower studies. 30. Includes $1,200, initiation of plans and specifications for Code 710 recreation facilities, for F Y 1978. Construction of recreation facilities at Martis Creek Lake under Code 710 was determined to be infeasible. 31. In addition, $66,532 expended for new work from contributed funds, other, for miscellaneous construction under local cooperation requirements as related to acquisition of rights-of-way and utility alterations for project. 32. Includes Code 710 funds and costs for recreation facilities at Pine Flat Lake: Total to date $1,595,100. 33. Includes Public Works Acceleration, Executive (PL 87-658) (Transfer to Corps of Engineers, Civil) 1963 funds for recreation facilities: Total appropriations $239,235 and total costs $239,235. 34. Includes $19,600 Code 713 funds and costs for Pine Flat fish barrier. 35. Includes $158,300 special recreation use fees and costs at Pine Flat Lake. 36. Miscellaneous construction and engineering and design services (non-project) accomplished at expense of State of California under local cooperation requirements in connection with acquisition of rights-of-way and utility alterations at Pine Flat Lake. 37. Excludes $5,598,000 contributed funds; $400,000 for recreation facilities at completed projects funded under Public Works Acceleration Program; and $1,628,411 for recreation facilities at completed projects funded under Code 711. 38. Includes $94,459 special recreation use fees and costs (FY 1982-1983), but excludes prior special recreation fees and costs for Coyote Valley Dam, Lake Mendocino. 39. Includes $56,500 maintenance and operation of dam funds and costs at Coyote Valley Dam, Lake Mendocino for FY 1985. 40. Includes $155,000 contributed funds, other, from city of Ukiah for Coyote Valley Dam, Lake Mendocino, hydropower studies. 41. Includes $150,308 contributed fund costs for Coyote Valley Dam, Lake Mendocino, hydropower studies. 42. Includes $253,421,793 San Francisco construction funds and costs through August 1983 for Dry Creek, Warm Springs Dam. 43. Includes $964,114 San Francisco maintenance funds and costs through April 1982 for Dry Creek, Warm Springs Dam. 44. Includes $60,000 contributed funds, other, from Sonoma County for Dry Creek, Warm Springs, hydropower studies. 45. Includes $40,400 contributed fund costs for.Dry Creek, Warm Springs hydropower studies. 46. Excludes $614,608 for Table Mountain (Iron Canyon) project, deauthorized August 5,1977, and $531,000 for Sacramento River and Major and Minor Tributaries portions which are considered inactive and deferred. 47. Includes Code 710 funds and costs for recreation facilities at Black Butte Lake: Total to date $1,000,162. 48. Includes $104,100 special recreation use fees and costs at Black Butte Lake. 49. Miscellaneous construction and engineering and design services (non-project) accomplished at expense of State of California under local cooperation requirements in connection with acquisition of rights-of-way and utility alterations (primarily for Sacramento River and major and minor tributaries roject). Includes State Highway Commission payment, 789,008, for use of excess excavation from Chico and Mud reeks and Sandy Gulch (Sacramento River and Major and Minor Tributaries) for freeway embankment through city of Chico. 50. Includes $41,984, contributed funds, other, from State of California for required modification of existing private facilities, Sacramento River, Chico Landing to Red Bluff; $25,977 contributed funds, other, from State of California Department of Boating and Waterways for replacing a boarding float at Orland Buttes boat launching ramp at Black Butte Lake; and $10,000 contributed funds, other, from the city of Santa Clara for hydropower studies at Black Butte Lake. 51. Includes $7,571 contributed funds, other, costs for Black Butte hydropower studies. 52. Includes $8,849,825 San Francisco construction funds. 53. Includes $9,049,609 San Francisco construction costs. 54. Includes $450,268 San Francisco required contributed funds. 55. Includes $525,846 San Francisco required contributed costs. 56. Includes $400,348 San Francisco contributed funds, other, and contributed fund costs. 57. Excludes funds applicable to other units of this basin authorization (Lower San Joaquin River and tributaries and Tuolumne River Basin, Calif.) (See Table 35-E). 58. Includes $110,000 utilized for preparation of 1957 Economic Feasibility Report and of Revised Feasibility Report (FY 1960,1961, and 1962) applicable to 1962 reauthorization of project. 59. Contributed funds, other, from the Bureau of Reclamation for visitors center at Mark Twain area, New Melones Lake. 60. Contributed fund costs for visitors center at Mark Twain area, New Melones Lake. 35-24 SACRAMENTO, CA, DISTRICT TABLE 35-A COST AND FINANCIAL STATEMENT ADVANCE ENGINEERING AND DESIGN See Section Total Cost to in Text Project Funding FY 82 FY 83 FY 84 FY 85 Sep 30, 1985 Cottonwood Creek, New Work CA Approp. 3,150,000 3,375,000 2,885,000 1,055,000 15,815,000' Cost 3,088,134- 2,667,898 3,472,949 1,019,478 15,727,9592 Fairfield Vicinity New Work Streams, CA Approp. - - 320,000 155,000 1,162,000 Cost - - 282,442 176,886 1,146,329 Little Dell New Work Lake, UT Approp. 100,000 50,000 515,000 90,000 2,809,9003 Cost 87,570 12,430 143,472 358,810 2,657,1824 Merced County New Work Streams, CA Approp. 1,344,000 500,000 - 20,000 6,370,000' Cost 1,317,691 522,953 6,141 100 6,350,000' Pajaro River New Work Basin, CA Approp. - 190,000 50,000 60,000 2,249,96886 Cost 17,228 95,129 132,984 71,498 2,249,5806 Sacramento River Dee New Work Water Ship Channel, CA Approp. 225,000 600,000 650,000 65,000 1,540,000' Cost 214,408 599,416 296,317 372,376 1,481,5178 1. Includes $10,160,000 General Investigation funds. 2. Includes $10,072,959 General Investigation costs. 3. Includes $695,000 General Investigation funds. 4. Includes $358,810 General Investigation costs. 5. Includes $1,034,000 General Investigation funds and costs. 6. Includes $1,949,968 San Francisco construction funds and costs and $240,000 Sacramento General Investigation funds and costs. 7. Includes $1,520,000 General Investigation funds (CP&E). 8. Includes $1,481,517 General Investigation costs (CP&E). 35-25 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 35-B AUTHORIZING LEGISLATION See Date Section in Authorizing Text Act Project and Work Authorized Documents Mar. 3, 1899 July 25, 1912 Jan. 21, 1927 Aug. 30, 1935 Aug. 30, 1935 Aug. 26, 1937 July 24, 1946 SACRAMENTO RIVER, CA A depth of 7 feet below Sacramento H. Doc. 186, 55th Cong., 2d sess., and 48, 55th Cong., 3d sess. (Annual Report 1898, p. 2844 and 1899, p. 3171). For work above Sacramento. H. Doc. 76, 62d Cong., 1st sess.1 The 10-foot channel up to Sacramento. H. Doc. 123, 69th Cong., 1st sess. A depth of 6 feet between Sacramento and Colusa and 5 feet Rivers and Harbors between Colusa and Chico Landing, at a cost of $390,000 Committee Doc. 35, provided flow of rivers is increased to minimum flow of 73d Cong., 2d sess. 5,000 cubic feet per second after Shasta Reservoir is built. Authority for a special direct participation of Federal Rivers and Harbors Government of $12 million in cost of Shasta Reservoir. Committee Doc. 35, 73d Cong., 2d sess. Transfer of authority for expenditure of above $12 million from Secretary of War to Secretary of the Interior. Modified existing navigation project for Sacramento River, S. Doc. 142, 79th Cong., CA, to provide for construction of a ship channel 30 2d sess. feet deep and 200 to 300 feet wide from deep water in Suisun Bay to Washington Lake, including such works as may be necessary to compensate for or alleviate any detrimental salinity conditions resulting from ship channel; a triangular basin of equal depth, 2,400 by 2,000 by 3,400 feet at Washington Lake; and connecting channel 13 feet deep and 120 feet wide, with lock and drawbridge, thence to Sacramento River. Oct. 23, 1962 Nov. 7, 1966 May 17, 1950 Feb. 10, 1956 Oct. 23, 1962 Mar. 7, 1974 15. Dec. 22, 1944 CORTE MADERA CREEK, CA Levees and channel improvements, lower 11 miles of Corte Madera Creek and tributaries, as modified by Chief of Engineers. Local cooperation requirements modified to provide 1.5 percent cash contribution toward cost of Ross Valley unit. RUSSIAN RIVER BASIN, CA Coyote Valley Dam (Lake Mendocino): Channel improvements on lower 98 miles of Russian River and lower reaches of tributaries. Increased appropriation authorization for initial stage of project development. Dry Creek (Warm Springs) Lake; Channel Improvements on Dry Creek below dam. Dry Creek (Warm Springs) Lake and channel; compensate for fish losses on the Russian River which may be attributed to the operation of the Coyote Dam component of the project through measures such as possible expansion of the capacity of the fish hatchery at the Warm Springs Dam component of the project. SACRAMENTO RIVER AND TRIBUTARIES, CA, FROM COLLINSVILLE TO SHASTA DAM Modify Sacramento River Flood Control Project to provide for extensions in levees and other structures along Sacramento River and major and minor tributaries; construct Black Butte Dam and Reservoir; construct lowlevel Table Mountain Dam and Reservoir with power facilities; and provision of monetary authorization of $15 million for initiation of modification. H. Doc. 545, 87th Cong., 2d sess. Sec. 204, 1966 Flood Control Act. H. Doc. 585, 81st Cong., 2d sess. Public Law 404, 84th Cong., 2d sess. H. Doc. 547, 87th Cong., 2d sess. Sec. 95, 1974 WRDA H. Doc. 649, 78th Cong., 2d sess. 2 35-26 6. 14. SACRAMENTO, CA, DISTRICT TABLE 35-B (Cont'd) AUTHORIZING LEGISLATION See Date Section in Authorizing Text Act Project and Work Authorized Documents May 17, 1950 Improvement for protection of Upper Butte Basin (included H. Doc. 367, 81st Cong., full monetary authorization). 1st sess. July 3, 1958 Extend existing Sacramento River Flood Control Project to H. Doc. 272, 84th Cong., Keswick Dam for purposes of zoning area below dam and 2d sess.2 modification of project by construction of bank protection and incidental channel improvements between Chico Landing and Red Bluff (included full monetary authorization). July 3, 1958 Additional authorization of $17 million for comprehensive plan approved in act of December 22, 1944. July 14, 1960 Further modification of Sacramento River Flood Control S. Doc. 103, 80th Cong., Project by construction of initial 10-year phase of 2d sess.' bank erosion control works and setback levees on Sacramento River and authorization of $14,240,000 for prosecution of modification. May 12, 1967 Additional authorization of $7 million for bank protection PL 90-17 approved in act of July 14, 1960. Mar. 7, 1974 Initiation of construction of second phase of bank erosion PL 93-251 control works and setback levees on Sacramento River as approved in act of July 14, 1960, and additional authorization of $16 million for such purpose.' June 19, 1975 Deauthorization of Table Mountain Dam and Reservoir4 H. Doc. 94-192, 94th Cong., 1st sess. 1. Contains latest published ma of section above Sacramento. For map of section below Sacramento, see H. Doc. 1123, 60th Cong., 2d sess. and S. Doc. 142, 79th Cong., 2d sess. 2. Contains latest published map. 3. Total monetary authorization available, exclusive of preauthorization studies from general investigations appropriations, amounts to $72,740,000. 4. The 90-day Congressional project review period, required by sec. 12, PL 93-251, as amended by sec. 157, PL 94-587, ended August 5,1977, and resulted in deauthorization of project unit. 35-27 TABLE 35-C REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 OTHER AUTHORIZED NAVIGATION PROJECTS For Last Cost to Sep 80, 1985 Full Reportr See Annual Operation and Project Status Report For Construction Maintenance Feather River, CA 1951 - 5,752' 3 Middle River and Connecting Channels, CA Completed 1974 8,3543 93,4944 Mokelumne River, CA Completed 1974 8,500 189,152 Navajo Reservoir, NM Completed - 2,132 '* - Old River, CA Completed 1970 23,1857 631,128 Stockton and Mormon Channels, CA Completed 1970 253,151' 218,854 Suisun Bay Channel, CA Completed 1974 200,928' 101o1 3,316,6221s 1s Suisun Channel, CA Completed 1973 217,677 733,48913 14 Suisun Point Channel, CA Completed 1965 191,7285 ' - 1. Maintenance project, channels adequate for commerce. 2. Includes $10 for maintenance for previous project. Excludes $6,160 for previous project and $3,840 for existing proje3c. t Ifnocrl umdaeisn tenance expended from contributed funds. $1,600 for previous project. 4. Includes $790 for previous project. 5. Authorized by Chief of Engineers under authority of sec. 107, Public Law 86-645, as amended. 6. All costs transferred from Los Angeles District in FY 1968. 7. Estimated cost to local interests was $3,600 for lands, damages, and public landings. 8. Upon completion of Mormon Slough, Calaveras River, CA in February 1970, local interests accepted maintenance responsibility for Mormon Slough as well as for Stockton and Mormon Channels, CA, and Federal maintenance was discontinued. No Federal maintenance costs have been incurred since FY 1969. 9. Includes $58,901 for previous projects. 10. Excludes $59,551 expended from required contributed funds for previous project. 11. Excludes work accomplished under existing project at a cost of $207,198 from Public Works Administration funds allotted to San Joaquin River, CA. 12. Includes $59,817 for previous projects. Excludes $5,449 expended from required contribute funds for previous pro1je3c. t.Maintenance responsibility transferred to San Francisco District, January 1, 1974. 14. Includes reconnaissance and condition surveys of $5,496 and $483 for fiscal years 1963 and 1964, respectively. 15. Estimated cost (July 1964) to local interests was $12,000 for lands, damages, and spoil retention dikes. 35-28 SACRAMENTO, CA, DISTRICT TABLE 35-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS For Last Cost to Sep 30, 1985 Full Report See Annual Operation and Project tatus Report For Construction Maintenance Alameda Creek, CA Alhambra Creek, CA American River, CA Aquatic Plant Control, CA Bear River, CA Big Dry Creek Dam and diversion, CA Big Wash, Milford, Beaver County, UT Burch Creek, Weber County, UT Chester, CA Coyote Creek, CA Duck Creek, San Joaquin County, CA East Weaver Creek, CA Eel River, CA Folsom Lake, American River, CA Gleason Creek, NV Green Valley Creek, Solano County, CA Humboldt River and Tributaries, NV Kays Creek, UT Kern River-California Aqueduct Intertie, CA Klamath River, CA Lake Camanche, CA Lake Oroville, CA Lakeport Lake, CA Lower San Joaquin River and Tributaries, including Tuolumne and Stanislaus Rivers, CA Mad River Basin, CA Marysville Lake, CA Merced River, CA Middle Creek, CA Mormon Slough, CA Napa River Basin, CA New Bullards Bar, CA North Fork, Pit River at Alturas, CA Pinole Creek, CA Redwood Creek, Humboldt County, CA Reese River, Battle Mountain, NV Rheem Creek, CA Rodeo Creek, CA Salinas River, CA Salt Lake City, Jordan River, UT San Leandro Creek, CA San Lorenzo Creek, CA San Lorenzo River, CA Sevier River near Redmond, UT Sonoma Creek, CA Truckee River and tributaries, CA and NV Completed Inactive Completed Completed Inactive Completed Completed Active/no FY 85 expenditure Completed Completed Completed Inactive Completed Deferred Completed Inactive Completed Completed Completed Completed Completed Deferred Completed Inactive Active/no FY 85 expenditure Completed Completed Completed Inactive Completed Completed Completed Completed Completed Completed Completed Inactive Completed Completed Completed Completed Completed Inactive Active/no FY 85 expenditure 1978 1981 1959 1967 1980 1955 1961 1964 1981 1968 1967 1965 1971 1967 1977 1963 1982 1973 1977 1972 1976 1981 1976 1976 1973 1980 1976 1967 1976 1979 1972 1974 1968 1970 1969 1962 1966 1952 1961 1973 1962 1966 1952 1973 1968 26,995,350 800,000'1 2,125,8184' 1,000 -5 1,369,931' 217,8797 $ 26,0497 3,570,000' 705,622' 7 664,8257 10 220,6361 7 11 1,272,8161 1 63,014,810 n 215,826" 136,0267 16 1,532,932' 407,9897 '7 1,503,0737 1 4,838,0001 10,252,950" 70,425,4708 2,353,00321 27,835,263n 4,243,750' ~24 10,918,7962 2,643,499 2,965,402V 2,639,9551 12,890,625 m 904,278' 2 3 885,750' 7 4,620,070' s 133,3397 8 400,000' 73 974,1001 7 94,213' " 1,227,570" 1,000,0001 S 5,130,821' '7 4,314,406' 1 919,0006 781,5001 40 1,038,960 35-29 54,7781 2 -, -. -=. -=. REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 35-E (Cont'd) OTHER AUTHORIZED FLOOD CONTROL PROJECTS 1. Project responsibility transferred from San Francisco District to Sacramento District April 1, 1982. 2. Scheduling of reservoir operations costs. 3. Project classified as "inactive" January 19, 1982. 4. Excludes $54,919 other contributed funds for miscellaneous construction for local interests pursuant to requirements of local cooperation. Total costs for all requirements of local cooperation were $951,000 (1959) for lands and relocations. 5. Due to infeasibility, Bear River Phase I study was suspended and project classified as "inactive"on November 6, 1981. 6. Excludes $44,008 other contributed funds for construction in connection with bridge construction pursuant to requirements of local cooperation. Total cost to local interests for all requirements of local cooperation was $370,000 (1959) for lands and relocations. 7. Authorized by Chief of Engineers under authority of sec. 205 Public Law 80-858, as amended. 8. Excludes $22,000 for preauthorization studies. 9. Excludes $69,262 other contributed funds from State of California for two low water crossings and appurtenances at Chester. 10. Excludes $50,000 for preauthorization studies. Estimated costs to local interests were $665,000 for lands and damages including relocations. 11. Includes $174,938 Public Works Acceleration Program Funds. 12. Excludes $194,821 contributed funds and placed inactive 1973. 13. Transferred to Bureau of Reclamation in May 1956 for operation and maintenance by that agency in conjunction with other units of Central Valley project. 14. Due to lack of local support, Gleason Creek project was reclassified as "deferred" on November 3, 1977. Fiscal year 1978 carryover funds of $27,984 were revoked. 15. Excludes $20,000 for preauthorization studies. 16. Vista and Devils Gate reservoirs and channel improvements were classified "inactive" on January 12, 1982, and Hylton reservoir was classified "inactive" on March 21, 1983, due to lack of economic feasibility. 17. Includes $30,000 for preauthorization studies. Estimated costs (FY 1973) to local interests for all requirements of local cooperation were $150,117 for lands and damages including relocations. 18. Includes $73,000 for preauthorization studies. Non- Federal (Kern County Water Agency) cost for road relocation was $18 260 (required contributed funds). 19. constructed by East Bay Municipal Utility District. Final Federal contribution of $51,202 made July 18, 1978 (total $10,111,684). Non-Federal costs $24,876,842. 20. Constructed by State of California. Final Federal contribution of $64,186 was made on February 9, 1981 (total $69,994 015) for flood control reservation. 21. Preconstruction planning complete. Necessary reaffirmation of local cooperation assurances by Lake County Flood Control and Water Conservation District not received. Project was reclassified as "deferred" on September 15,1977. Includes $298,500 costs for advance acquisition of land, Public Law 91-439. 22. Cherry Valley and New Don Pedro Reservoirs constructed by local interests. Federal contributions of $9,000,000 and $5,464,000, respectively, for flood control reservation. Final Federal contribution of $308,898 was made on January 18, 1972, for New Don Pedro. Excludes $3,004,946 contributed funds, other, for miscellaneous engineering and construction (non-project) at local interests expense under local cooperation requirements for acquisition of rights-ofway for levee and channel improvements on Lower San Joaquin River and tributaries. 23. Placed inactive 1974. Excludes $225,000 applicable to Public Works Acceleration Program and $162,761 previous project Blue Lake levee. 24. Planning and any future development is uncertain apwroajietcint.g,j State of California's position on supportof Marysville 25. Constructed by Merced Irrigation District. Final Federal contribution of $839 was made December 2, 1975 (total $10,818,638) for flood control reservation. 26. Estimated costs (FY 1967) to local interests for all requirements of local cooperation were $1,340,000 for lands and damages including relocations. 27. Non-Federal cost $2,965,402 (FY 1976) for lands and relocations. Federal contribution of $599,336 made to State Reclamation Board. 28. Constructed by Yuba County Water Agency. Final Federal contribution of $33,470 was made in FY 1972 (total $12 759 127) for flood control reservation. 29. Includes $41,800 for preauthorization studies. 30. Excludes $146,000 other contributed funds for miscellaneous construction and engineering and design services under local cooperation requirements in connection with acquisition of rights-of-way, relocation, and utility alterations. 31. Includes $107 000 costs for remedial work to drainage system completed in 'Y 1977. 32. Includes $19,000 for preauthorization studies. 33. Excludes $52,549 contributed funds. 34. Cost includes engineering and design prior to June 30, 1952 and costs of $4,288 FY 1962 and 1963 to determine if project classification to an active category was justified. 35. Estimated costs to local interests for all requirements of local cooperation were $463,000 (July 1962) for lands and damages including relocations. Project prevented $2,211,000 in damages from May-June 1985 snowmelt runoff. 36. Excludes $285,329 contributed funds. 37. Excludes $200,000 estimated value of work performed in lieu of cash contribution.- 38. Excludes $421,182 contributed funds. 39. Excludes $48,000 required contributed funds toward first cost. Costs to local interests for all requirements of local cooperation, including required contributions, were $118,000 (1951). 40. Placed inactive 1974. 35-30 SACRAMENTO, CA, DISTRICT TABLE 35-G DEAUTHORIZED PROJECTS For Last Full Report Federal Contributed See Annual Date Funds Funds Project Report For Deauthorized Expended Expended Little Valley Wash, Magna, UT 1951 1977 Spanish Fork River, UT 1955 1977 20,000 Weber River and Tributaries, UT 1974 1972 75,120 (Morgan County) TABLE 35-H SACRAMENTO RIVER, CA: TIDAL AND FLOOD CONDITIONS PREVAILING (See Section 1 of Text) Miles from Range in Feet Mouth of Mean Extreme Ordinary Extreme Place River Tidal' Tidal2 Floods Flood' Collinsville 0 4.3 7 8 10 Sacramento 59 2.02 3 20 28 Verona (Mouth of Feather River) 80 - Trace 22 30 Colusa 144 - - 26 32 Chico Landing 193 - - 20 25 Red Bluff 248 - - 24 30 1. Mean lower low water to mean higher high water. 3. Mean lower low water to flood stage. 2. Tide at low water season only. 4. Extreme low water to indicated flood condition. TABLE 35-I SAN JOAQUIN RIVER, CA: TOTAL COST OF NEW WORK FOR PROJECTi (See Section 3 of Text) Federal Non-Federal= Corps of Coast Required Lands and Engineers Guard Cash Damages (includ- Total Modification (Construction) (Construction) Contribution ing Relocations) Total Project Prior to 1950 Modification $4,009,938 $80,000 $1,307,500 $1,042,000 $2,349,500 $6,439,438 1950 Modification 1,823,179 - 35,000 135,000 170,000 1,993,179 Total $5,833,117 $80,000 $1,342,500 $1,177,000 $2,519,500 $8,432,617 1. Completed in May 1960. 2. Excludes $5 865,000 (Feb. 1954) local interests costs for Stockton Deep Water Channel terminal facilities required under terms of project authorization. 35-31 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 35-J SAN JOAQUIN RIVER, CA: PROJECT UNITS (1950 MODIFICATION) RECLASSIFIED AND EXCLUDED FROM PROJECT COST (See Section 3 of Text) Non-Federal Federal Required Lands and Corps of Cash Damages (includ- Total Unit Engineers Contribution Ing Relocations) Total Project Settling Basin above head of Burns Cutoff' $1,073,000 $ 30,000 $ 200,000 $ 230,000 $1,303,000 Burns Cutoff improvement; new turning basin; dredging Mormon Channel2 7,882,000a 431,000 1,455,000 1,886,000 9,768,000 Upper Stockton Channel enlargement' 535,000 34,000 15,000 49,000 584,000 1. July 1959 price index. Deauthorized August 5, 1977. 4. Deleted by 1965 River and Harbor Act authorization 2. Deferred; July 1960 price index. of San Francisco Bay to Stockton Channel, Sacramento 3. For lands and construction. District, Improvement No. 2. TABLE 35-K MERCED COUNTY STREAM GROUP, CA, MAXIMUM INFLOW, STORAGE, AND OUTFLOW FOR PROJECTS (See Section 12 of Text) Maximum Inflow Maximum Maximum (c.f.s.) Storage Outflow Stream (bihourly) (acre-feet) (c.f.s.) Burns 650 80 635 Bear 1,300 310 920 Owens 200 70 80 Mariposa 2,300 1,220 530 TABLE 35-L RUSSIAN RIVER BASIN, CA: ESTIMATED COST FOR NEW WORK (See Section 14 of Text) Estimated Cost Non-Federal Project Feature Federal Contribution Total Coyote Valley Dam (Lake Mendocino); Channel Improvements below Dam on lower 98 miles of Russian River $ 14,436,000 $ 5,598,000 $ 20,034,000' Dry Creek (Warm Springs) Lake; Channel Improvements below Dam 248,500,000 94,620,0002 343,120,000 Total $262,936,000 $100,218,000 $363,154,000 1. Exclusive of $1,628,000 for recreation facilities at ment for costs allocated to water supply storage to be paid completed projects. over a period not to exceed 50 years after use of storage is 2. Reimbursement by local interests to Federal Govern- initiated and exclusive of lands and damages. 35-32 SACRAMENTO, CA, DISTRICT TABLE 35-M RUSSIAN RIVER BASIN, CA: PROJECT FEATURES AND ESTIMATED COSTS (See Section 14 of Text) Height of Reservoir Nearest City Distance Dam and Capacity Estimated Name (California) Above Mouth Type (Acre-Ft) Cost Coyote Valley Dam (Lake Ukiah Mile 0.8-East Fork 160 Feet-Earthfill 122,500 $ 17,550,000 Mendocino) of Russian River Channel Improvement (East Fork Ukiah Mile 0 to 0.8 East 2,484,000 Fork below Coyote Valley Dam and Guerneville Mile 0 to 98, Russian - lower 98 miles of Russian River) River Dry Creek (Warm Springs) Lake Healdsburg Mile 14.4 Dry Creek 319 Feet-Earthfill 381,000 339,300,000 Channel Improvement (Dry Creek) Healdsburg Mile 1 to 14.4 Dry - 3,700,000 below Dry Creek (Warm Springs Creek Dam) 1. Exclusive of $1,628,000 for recreation facilities at completed projects. TABLE 35-N SACRAMENTO RIVER AND TRIBUTARIES, CA, COLLINSVILLE TO SHASTA DAM: PROJECT UNITS RECLASSIFIED AND EXCLUDED FROM COST ESTIMATE (See Section 15 of Text) Current Estimated Cost Unit Classification Federal Non-Federal' Total 1944 Modification: Antelope Creek2 Inactive $1,400,000 $ 340,000 $1,740,000 Lower Butte Basins Deferred 7,286,000 2,285,000 9,571,000 Thomes Creek2 Deferred 1,140,000 140,000 1,280,000 Willow Creek2 Inactive 1,290,000 120,000 1,410,000 Bypass Levees' Deferred 7,100,000 940,000 8,040,000 Bypass Levees' Inactive 3,010,000 3,010,000 1950 Modification: Upper Butte Basin2 Deferred 3,530,000 1,787,000 5,317,000 1. For lands and damages, including relocations. 2. July 1960 price level. 8. Excludes work applicable to extension of Moulton weir (July 1954 price level). 4. July 1961 price level. 35-33 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 35-0 SACRAMENTO RIVER AND TRIBUTARIES, CA, FROM COLLINSVILLE TO SHASTA DAM: CONSTRUCTION ACCOMPLISHED AND CONTRACT COSTS (See Section 15 of Text) Required Contract Federal Contributed Total Contract 37 continuation (Bank protection, selected sites, Sacramento River and Sloughs, downstream from Sacramento) $2,102,842 $284,219 $2,387,061 Contract 38A initiation (Bank protection, selected sites, Sacramento River, miles 80.0-193.0) 1,087,006 403,354 1,490,360 Contract 39 initiation (Bank protection, selected sites, Sacramento River, miles 178.0-189.0) 999,950 1,233,882 2,233,832 35-34 PACIFIC OCEAN DIVISION* This division comprises the State of Hawaii. The division also performs such actions pertaining to preservation and protection of navigable waters on and about the island of Guam and American Samoa as provided for under River and Harbor Act of 1899, and the Commonwealth of the Northern Mariana Islands as provided for under Public Law 94-241 (H.J. Res 549) (March 24, 1976). IMPROVEMENTS Navigation 1. Barbers Point Harbor, Oahu, Hawaii ...... 2. Honolulu Harbor, Oahu, Hawaii.......... 3. Kaulana Bay Boat Harbor, Hawaii, Hawaii.. 4. Manele Bay Small Boat Harbor, Lanai, Hawaii............................... 5. Nawiliwili Harbor, Kauai, Hawaii ......... 6. Rota Harbor, Northern Marianas ......... 7. Tau Small Boat Harbor, American Samoa.. 8. Reconnaissance and Condition Surveys .... 9. Navigation Work Under Special Authorization........................ Beach Erosion Control 10. Asquiroga Bay, Territory of Guam ........ 11. Beach Erosion Work Under Special Authorization ......................... Flood Control 12. Asan Village, Territory of Guam.......... 13. Iao Stream, Maui, Hawaii ............... 14. Kahoma Stream, l4aui, Hawaii ........... 15. Kaneohe-Kailua Area, Oahu, Hawaii .. .... 16. Paauau Stream, Hawaii, Hawaii .......... 17. Waimea River, Kauai, Hawaii... ......... Page 36-1 36-2 36-2 36-2 36-2 36-2 36-3 36-3 Flood Control (Cont.) 18. Flood Control Work Under Special Authorization........................ 19. Inspection of Completed Flood Control Projects .............................. Multiple-Purpose Projects, Including Power 20. Nanpil River Hydropower, Pohnpei, Trust Territory of the Pacific Islands .......... General Investigations 36-3 21. Surveys.............................. 22. Collection and Study of Basic Data ....... 23. Continuation of Planning and Engineering. 36-3 lb 36-3 36-3 36-3 36-3 36-4 36-4 36-4 Lbles Table 36-A Cost and Financial Statement .... Table 36-B Authorizing Legislation ......... Table 36-C Other Authorized Navigation Projects..................... Table 36-D Other Authorized Beach Erosion Control Projects ............... Table 36-E Other Authorized Flood Control Projects ...................... Table 36-F Not Applicable Table 36-G Deauthorized Projects .......... Page 36-4 36-4 36-4 36-5 36-5 36-5 36-6 36-8 36-10 36-11 36-12 36-12 Navigation 1. BARBERS POINT HARBOR, OAHU, HAWAII Location. On the west coast of Oahu, about 25 miles from metropolitan Honolulu. (See Coast and Geodetic Survey Charts 4110 and 4133.) Existing project. For description of existing project, see page 36-1 of FY84 Annual Report. Approved project cost estimate (October 1982) for deep-draft harbor is $66,000,000 of which Federal cost is $58,000,000 (including $400,000 in U.S. Coast Guard cost) and non-Federal cost is $8,300,000 including lands and rights-of-way and cash contribution of $2,500,000. (See Table 36-B for Authorizing Legislation.) Local cooperation. Local interest must provide lands and rights-of-way for construction and future maintenance, provide and maintain mooring facilities open to all on equal terms; provide such utility and drainage relocations or alterations as necessary; hold the United States free from damages; and provide a cash contribution estimated to be $2,500,000 for the deep-draft harbor. Terminal facilities. See page 36-2 of FY84 Annual Report. 36-1 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Operations during fiscal year. New Work: A construction contract awarded in March 1982 was completed in August 1985 for $53,333,154 of which Federal cost is $48,758,660 (including $320,000 in U.S. Coast Guard cost) and non-Federal cost is $4,574,494. Claim of $6,798,175 submitted by the contractor in August 1984 for restrictions on blasting was settled for $3,500,000 of which Federal cost is $3,346,000 and non-Federal cost is $154,000. Claim payment was made in January 1985. Work remaining to be completed includes construction of revetment absorber, project beautification, and stockpile plantings which is estimated at $1,539,000. Remaining work is scheduled for completion in December 1986. Maintenance: Annual operational cost for the Regional Visitor Center located at Fort DeRussy was $43,226. 2. HONOLULU HARBOR, OAHU, HAWAII Location. On the southern coast of the island of Oahu in the city of Honolulu. (See Coast and Geodetic Survey Chart 4109.) Existing project. See page 36-2 of FY84 Annual Report. (See Table 36-B for Authorizing Legislation.) Local cooperation. Fully complied with. Terminal facilities. See page 36-2 of FY84 Annual Report. Operations during fiscal year. A law suit against the government filed in September 1981 for damages to a marine railway was settled in April 1985. The United States (Department of Justice appropriation) paid $40,000 for its portion of the settlement. 3. KAULANA BAY BOAT HARBOR, HAWAII, HAWAII Location. On the southern tip of the island of Hawaii in the Ka'u Judicial District about 80 road miles southwest of the city of Hilo. (See NOAA Chart 19320.) Existing project. See page 36-2 of FY84 Annual Report. Local cooperation. Requirements are described in full on page 36-3 of FY82 Annual Report. Terminal facilities. There is an existing boat launching ramp owned by the State of Hawaii and open to all on equal basis. Operations during fiscal year. New Work: Favorable constructions bids were received in September 1983 and a lawsuit was filed in October 1983 for permanent injunction to enjoin construction contract award and negate lease agreement. A settlement agreement was signed by plaintiffs on May 30, 1984 removing the Corps from the suit. The project real estate is the subject of a State suit. The construction contract will not be awarded until that suit is resolved. 4. MANELE BAY SMALL BOAT HARBOR, LANAI, HAWAII Location. On the southern coast of the island of Lanai about 6 miles south of Lanai City. (See Coast and Geodetic Survey Chart 4130.) Existing project. Project provides for extension of an existing 100-foot long stub breakwater with a 470-foot rubblemound breakwater with crest elevation of 14 feet at the head and 6 feet at the root; an entrance channel 12 feet deep, and main access channel and maneuvering areas 8 feet deep. The tidal range between mean lower low water and mean higher high water is 1.8 feet. Total project cost for maintenance dredging is $221,000 in federal cost. Project authority is Section 107 of the 1960 River and Harbor Act, as amended. Local cooperation. Fully complied with. Terminal Facilities. Shoreside facilities provided by the State of Hawaii include berths, sanitary facilities, launch ramp and parking areas. Operations during fiscal year. Maintenance: A maintenance dredging contract was awarded in September 1985 for $173,875 with completion scheduled in December 1985. 5. NAWILIWILI HARBOR, KAUAI, HAWAII Location. On the southwest coast of the island of Kauai and about 100 nautical miles northwest of Honolulu. (See NOAA Chart 19383.) Existing project. For description of existing project, see page 36-3 of FY84 Annual Report. Estimated total project cost for breakwater rehabilitation is $3,967,400 in federal cost. (See Table 36-B for Authorizing Legislation.) Local cooperation. Fully complied with. Terminal facilities. See page 36-3 of FY84 Annual Report. Operations during fiscal year. Maintenance: A General Design Memorandum was approved in March 1984 for rehabilitation of the breakwater including repair of the breakwater damaged by Hurricane IWA in November 1982. Plans and specifications for a breakwater rehabilitation contract to be completed for an award of construction contract in FY86. 6. ROTA HARBOR, NORTHERN MARIANAS Location. On the island of Rota within the Commonwealth of the Northern Mariana Islands which is located in the Western Pacific, approximately 3,280 miles west of Hawaii and approximately 40 miles north of Guam. (See U.S. Defense Mapping Agency Hydrographic Map No. 81063.) Existing project. For description of existing project, see page 36-3 of FY84 Annual Report. Total project cost is $2,938,000 of which federal cost is $2,087,000 (including $87,000 in U.S. Coast Guard cost) and non-federal cost is $851,000 in cash contribution. Project authority is Section 107 of the 1960 River and Harbor Act, as amended. Project was approved for construction in October 1980. Local cooperation. Fully complied with. Terminal facilities. See page 36-3 of FY84 Annual Report. Operations during fiscal year. New Work: A construction contract awarded in September 1982 was completed in April 1985 for $2,547,230. 36-2 PACIFIC OCEAN DIVISION 7. TAU SMALL BOAT HARBOR, AMERICAN SAMOA Location. On the island of Tau, American Samoa, about 2,300 miles southwest of Hawaii, 1,236 miles northwest of Tahiti, and 80 miles southeast of Western Samoa. (See Coast and Geodetic Survey Chart 4190.) Existing project. For description of existing project, see page 36-3 of FY84 Annual Report. Total project cost is $2,058,034 of which federal cost is $2,004,800 (including $4,800 in U.S. Coast Guard cost) and non-federal cost is $54,034. Project authority is Section 107 of the 1960 River and Harbor Act, as amended. Project was approved for construction in January 1975. Local cooperation. Fully complied with. Operations during fiscal year. New Work: A construction contract for navigational aids awarded in September 1984 was completed in April 1985 for $16,502 (Corps of Engineers cost). Maintenance: A wave gaging contract awarded in June 1984 was completed in September 1985 for $56,715. 8. RECONNAISSANCE AND CONDITION SURVEYS Condition survey was conducted on Honolulu Harbor, Oahu, in September 1985 for $18,929. 9. NAVIGATION WORK UNDER SPECIAL AUTHORIZATION Navigation activities pursuant to Section 107, Public Law 86-645. Preauthorization studies were continued on Merizo Harbor, Guam, $20,992; Kahana Bay, Oahu, $82,081; East Molokai, Molokai, $87,937; and Kahului Small Boat Harbor, Maui, $72,523; completed on Laupahoehoe Harbor, Hawaii, $158,604; and terminated on Saipan Deep Draft Harbor, Northern Marianas, $134, and Wailoa River Harbor, Hawaii, $35,600. Plans and specifications were continued on Agat Harbor, Guam, $41,838. Prevention or mitigation of navigation shore damages activities pursuant to Section 111, Public Law 90-483. Preauthorization study was completed on Pohoiki Bay, Hawaii, $7,500. Beach Erosion Control 10. ASQUIROGA BAY, TERRITORY OF GUAM Location. On the southeastern shore of the island of Guam, about 3,318 miles west of Honolulu, Hawaii (See NOAA Chart 81408.) Existing project. Project provides for a 275 feet rock revetment with a crest elevation + 14.0 feet MLLW with a slope of 1V on 1.5H. Estimated total project cost is $250,000 in federal cost. Project authority is Section 14 of the 1946 Flood Control Act, as amended. Project was approved for construction in August 1980. Local cooperation. Requirements are described in full on page 36-4 of FY83 Annual Report. Operations during fiscal year. New Work: A construction contract was awarded in February 1985 for $179,600. Construction contract is 51 percent complete with completion scheduled in December 1985. 11. BEACH EROSION WORK UNDER SPECIAL AUTHORIZATION Emergency streambank and shoreline protection activities pursuant to Section 14, Public Law 79-526. Preauthorization studies were completed on Niumalu Peninsula, Kauai, $31; Umatac Bay, Guam, $12,000; and Ofu Airstrip, American Samoa, $7,000. Beach erosion control activities pursuant to Section 103, Public Law 87-874. Preauthorization studies were continued on Lepua Area, American Samoa, $58,805, and Makaha Beach Park, Oahu, $78,920; completed on Masefau Bay, American Samoa, $4,377; and terminated on Coconut Point, American Samoa, $10, and Kahaluu Beach Park, Hawaii, $574. Plans and specifications were continued on Sand Island, Oahu, $38,113. Flood Control 12. ASAN VILLAGE, TERRITORY OF GUAM Location. On the west central coastal area of the island of Guam and about 2.5 miles east of Agana, the capital of Guam. The island of Guam is approximately 3,318 miles west of Honolulu, Hawaii, and 1,300 miles south of Tokyo, Japan. (See NOAA Chart 81048.) Existing project. See page 36-4 of FY84 Annual Report. Local Cooperation. Fully complied with. Operations during fiscal year. New Work: A construction contract awarded iri September 1983 was completed in April 1985 for $1,371,747. A construction deficiency was reported in August 1984 and is under evaluation. 13. IAO STREAM, MAUI, HAWAII Location. Iao Stream on the island of Maui drains a portion of the slopes of the West Maui mountains, and its lower course runs into the sea just to the east of the town of Wailuku, Maui. (See Coast and Geodetic Survey Chart 4124.) Existing Project. See page 36-5 of FY84 Annual Report. (See Table 36-B for Authorizing Legislation.) Local cooperation. Fully complied with. Operations during fiscal year. New Work: Two contractor appeals filed in July 1980 for flood damages and August 1980 for defective specifications were dismissed without prejudice by the Engineer Board of Contract Appeals in June 1983. The contractor may resubmit these claims, but to date have not; however, the subcontractors and contractor are litigating in State and Federal courts. 14. KAHOMA STREAM, MAUI, HAWAII Location. Kahoma Stream drainage basin is located in Lahaina, Maui. Lahaina is on the west coast of Maui about 4 miles from Kaanapali. The drainage basin of Kahoma Stream totals 5.3 square miles. (See NOAA Chart 19348.) 36-3 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Existing project. For description of existing project, see page 36-5 of FY84 Annual Report. Total project cost estimate (October 1985) is $24,100,000 of which federal cost is $16,800,000 and non-federal cost is $7,300,000 for lands, damages, relocations, and cash contributions ($1,200,000). (See Table 36-B for Authorizing Legislation.) Local cooperation. Requirements are described in full on Page 36-5 of FY84 Annual Report. Operations during fiscal year. New Work: Plans and specifications are completed. Section 221 Agreement and related agreements are continuing to be coordinated for finalization prior to initiation of construction contract. This project was included under the FY 1983 budget amendment of May 25, 1982 and was included in the FY 1985 Supplemental Appropriation Act (PL 99-88) new construction start. 15. KANEOHE-KAILUA AREA, OAHU, HAWAII Location. Kamooalii-Kaneohe Stream drainage basin is on the east coast of the island of Oahu. The drainage basin is bounded on west and south by the Koolau Mountain range, on the east by the remnants of Kaneohe volcanic cone and on the north by Kaneohe Bay. (See Coast and Geodetic Chart 4134 and U.S. Geological Survey Quadrangles Kaneohe, Hawaii and Honolulu, Hawaii.) Existing project. See page 36-5 of FY84 Annual Report. (See Table 36-B for Authorizing Legislation.) Local cooperation. Fully complied with. Operations during fiscal year. New Work: Contractor claims were settled in September 1985 for defective specifications filed in October 1979 and suspension of work for spillway filed in December 1980 for $774,000 and $13,937, respectively. 16. PAAUAU STREAM, HAWAII, HAWAII Location. In the Ka'u District on the island of Hawaii, approximately 45 miles southwest of Hilo. (See NOAA Chart 19320.) Existing project. Project provides for a 295 feet levee and three concrete rubble masonry walls of 550 feet, 272 feet and 670 feet. Total project cost is $1,982,300 in federal cost. Project authority is Section 205 of the Flood Control Act of 1948, as amended. Project was authorized for construction in August 1983. Local cooperation. Fully complied with. Operation during fiscal year. New Work: A construction contract awarded in September 1983 was completed in October 1984 for $1,554,481. 17. WAIMEA RIVER, KAUAI, HAWAII Location. On the west-central portion of the island of Kauai which is about 103 statute miles northwest of Honolulu. (See NOAA Chart 19381.) Existing project. Project provides for 3,320 feet of concrete rubble masonry floodwall on existing levee, 4,600 feet of rock toe protection, 500 feet of road raise, 1,030 feet of levee extension, 335 feet of concrete wall, new floodgates and a flood warning system. Estimated total project cost is $3,272,400 of which federal cost is $3,212,400 and nonfederal cost is $60,000 for flood warning system. Project authority is Section 205 of the Flood Control Act of 1948, as amended. Project was authorized for construction in May 1983. Construction funds were alloted under the Jobs Bill Program. Local cooperation. Fully complied with. Operations during fiscal year. New Work: A construction contract awarded in September 1983 was completed in December 1984 for $2,467,005 with flood warning system remaining to be completed at an estimated cost of $300,000. 18. FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION Flood control activities pursuant to Section 205, Public Law 80-858. Preauthoriztion studies were continued on Kahawainui Stream, Oahu, $136,216; Lake Susupe, Northern Marianas, $25,114; Garapan Area, Northern Marianas, $75,215; and Honaunau Area, Hawaii, $48,333. Federal cost during fiscal year for Flood Control and Coastal Emergencies appropriation was $190,129 of which $190,105 was for disaster preparedness, and $24 for rehabilitation work for Kekaha Beach. 19. INSPECTION OF COMPLETED FLOOD CONTROL PROJECTS Inspections were conducted on Paauau Stream, Hawaii, in October 1984; Hanapepe River, Kauai, in November 1984; Namo River, Guam; lao Stream, Maui, Kuliouou Stream, Oahu; Kawainui Swamp, Oahu; and Wailoa Stream, Hawaii, in December 1984 for a total cost of $8,928. Multiple-Purpose Projects Including Power 20. NANPIL RIVER HYDROPOWER, POHNPEI, TRUST TERRITORY OF THE PACIFIC ISLANDS Location. Nanpil River is located on the island of Pohnpei in the Federated States of Micronesia, Trust Territory of the Pacific Islands. (See State of Hawaii, the New Pacific map.) Existing project. The project provides for a 1,700 kilowatt capacity hydropower plant with an average annual energy production of 4,020,000 kilowatt-hours. Plans and specifications were completed in November 1983 based on a Memorandum of Understanding signed in September 1981 between Pohnpei State, the Trust Territory of the Pacific Islands, and Pacific Ocean Division, Corps of Engineers to provide funds on a reimbursable basis. Estimated total project cost is $8,000,000 including operation and maintenance for one year after construction completion. The FY 84 Supplemental Appropriation Bill provided funds of $8,000,000 directly to the Corps as designated agents for Pohnpei State to construct the facility. (See Table 36-B for Authorizing Legislation.) 36-4 PACIFIC OCEAN DIVISION Local cooperation. In accordance with Memorandum of Agreement executed on January 26, 1985: a. Pohnpei shall provide all legal interest in lands, easements, rights-of-way necessary for construction, operation, and maintenance of the intake, road, penstock, powerhouse, and transmission line. b. Pohnpei shall designate the responsible department and officials for coordination of the work and shall also designate an on-site representative who shall coordinate matters pertaining to Pohnpei and who may participate in construction meetings. Only the Corp's representative shall issue contract instructions or directives to the contractor. Project funds are not available for costs associated with stationing the designated representatives at the project site except that the Pohnpei representative may share the Corps' Project office. c. Pohnpei shall provide all required clearances, licenses, or permits that may be required for the Project under the laws of Pohnpei, the Trust Thrritory of the Pacific Islands and/or the United States of America. d. Upon completion and acceptance of the Project from the contractor, and upon completion of the 365-calendar day operation, maintenance and training period, Pohnpei agrees to operate and maintain the Project in accordance with guidelines provided in the operations and maintenance manual to be provided by the Corps. Operations during the fiscal year. Construction contract award is scheduled for October 1985. A contract to operate and maintain the project for a one-year period to October 1988 will be incorporated in the work to be done. General Investigations 21. SURVEYS Fiscal year costs were $783,813 of which $402,221 was for navigation studies, $150,809 for flood damage prevention studies, $57,218 for miscellaneous activities, and $173,565 for coordination with other agencies. 22. COLLECTION AND STUDY OF BASIC DATA Flood plain management services. Flood Plain Management Services Program comes under Section 206, PL 86-645, 1960 Flood Control Act, as-arrended. Through technical services and planning guidance, the program provides information on floods and flood related information to improve planning for the careful use of the nation's flood plains, thereby reducing the potential for losses to life and property from floods and wave actions. Federal and nonfederal agencies and the private sector are assisted with flood hazard evaluation and planning information for flood and coastal hazard areas. This assistance is in the form of local flood plain regulations, National Flood Insurance requirements, and Executive Order 11988 requirements for federal agencies. Such assistance may include flood information and timing, flood-water velocity, extent of flooding, duration of flooding, flood frequency and regulatory floodway limits. Services accomplished during fiscal year. Requests and responses for technical services and planning assistance totaled 625. Of this total, 80 were from other federal agencies, 295 from non-federal agencies, and 250 from individuals, realtors, corporations, lending institutions, engineers, architects and others. Of the 625 requests, assistance resulted in 2,600 site specific responses. A hurricane vulnerability study was initiated in September 1983 as join study with the State of Hawaii and is scheduled for completion in November 1985. The estimated total cost is $225,000 (Federal: $55,000; Non-federal: $170,000.) Costs for providing Flood Plain Management services during fiscal year were $264,197. Hydrologic Studies. Storm studies cost was $5,005. Total costs for collection and study of basic data during fiscal year were $269,202. 23. CONTINUATION OF PLANNING AND ENGINEERING Agana River Flood Control, Guam. Preparation of a combined General Design Memorandum initiated in October 1983 was completed in August 1985 for $326,343. 36-5 TABLE 36-A REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 COST AND FINANCIAL STATEMENT See Section Total Cost To in Text Project Funding FY 82 FY 83 FY 84 FY 85 Sept.. 30, 1985 1. Barbers Point New Work: Harbor, Oahu, Hawaii (Federal Funds) (Contributed Funds) 2. Honolulu Harbor, Oahu, Hawaii (Federal Funds) (Contributed Funds) 3. Kaulana Bay Boat Harbor, Hawaii, Hawaii (Federal Funds) 4. Manele Bay Small Boat Harbor, Lanai, Hawaii (Federal Funds) (Contributed Funds) 5. Nawiliwili Harbor, Kauai, Hawaii (Federal Funds) (Contributed Funds) 6. Rota Harbor Northern Marianas (Federal Funds) (Contributed Funds) Approp. Cost New Work: Contrib. Cost New Work: Approp. Cost Maint. Approp. Cost New Work: Contrib. Cost New Work: Approp. Cost New Work: Approp. Cost Maint: Approp. Cost New Work: Contrib. Cost New Work: Approp. Cost Maint. Approp. Cost New Work: Contrib. Cost New Work: Approp. Cost New Work: Contrib. Cost 10,192,00 17,690,000 16,500,00 5,954,543 21,659,777 14,346,100 11,827,000 8,348,616 594,095 875,801 567,464 374,434 220,615 943,309 673,952 376,920 1,195,000 1,338,290 34,500 39,805 -14,300 6,701 1,248 -35,000 2 -4,417 2,988 20,000 481,000 -406,000 8,096 38,336 13,221 16 86,000 20,823 111,500 1,489,400 -25,000 67,552 1,474,014 34,328 350,000 1,490,500 6,356 1,821,053 19,490 697,000 80,000 119,716 528,819 85,000 53,775 -117 1,000 126,288 36-6 57,900,500 51,840,714 4,249,670 2,214,796 16,044,095 16,044,095 2,038,271 2,038,271 201,282 201,282 195,000 158,192 372,000 372,000 269,622 204,445 370,845 370,845 2,127,724 2,127,724 5,810,220 5,778,989 233,261 233,261 2,000,000 1,999,577 778,000 774,823 PACIFIC OCEAN DIVISION TABLE 36-A (Cont.) COST AND FINANCIAL STATEMENT See Section Total Cost To in 'Text Project Funding FY 82 FY 83 FY 84 FY 85 Sept. 30, 1985 7. 'Thu Small Boat Harbor, American Samoa (Federal Funds) (Contributed Funds) 10. Asquiroga Bay, Thrritory of Guam (Federal Funds) 12. Asan Village, Territory of Guam (Federal Funds) (Contributed Funds) 13. Iao Stream, Maui, Hawaii (Federal Funds) 14. Kahoma Stream, Maui, Hawaii (Federal Funds) 15. Kaneohe-Kailua Area, Oahu, Hawaii (Federal Funds) (Contributed Funds) (Non-Federal) 16. Paauau Stream Hawaii, Hawaii (Federal Funds) 17. Waimea River, Kauai, Hawaii (Federal Funds) 20. Nanpil River Hydropower, Pohnpei, TTPI (Federal Funds) New Work: Approp. Cost New Work: Contrib. Cost Maint: Approp. Cost New Work: Approp. Cost New Work: Approp. Cost New Work: Contrib. Cost New Work: Approp. Cost New Work: Approp. Cost New Work: Approp. Cost New Work: Contrib. Cost Reimb. New Work: Approp. Cost New Work: Approp. Cost New Work: Approp. Cost 27,500 423,803 30,000 18,181 433,219 788 ' - 1,584 - 1,738 - 65,000 - 45,506 -4,400 26 5,381 5,381 14,500 908,400 119,600 14,257 115,838 610,486 - 630,000 15,000 - 409,803 546,000 52,394 242,662 25,000 42,915 8,000 29,744 329,999 20,000 10,000 19,854 10,315 23,500 125,000 25,359 50,875 - 675 7,500 - - 8,159 (359,220) (289,991) (289,991) 85,000 150,000 1,617,300 84,686 134,347 1,502,387 1,000 2,564,000 -69,600 1,421 109,505 2,180,214 60,000 9,188 36-7 28,603 19,156 220,000 48,001 246,330 210,465 278 20,000 10,009 41,105 55,000 183,793 405,000 462,599 114,000 145,350 1,991,569 1,990,960 54,034 54,034 65,000 64,526 249,981 77,982 1,275,500 1,219,857 645,000 620,268 12,299,000 12,284,038 769,000 758,983 24,786,400 24,744,712 8,175 8,159 (939,202) 1,982,300 1,978,513 3,047,400 2,900,318 174,000 154,538 k REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 36-B AUTHORIZING LEGISLATION See Date Section Authorizing in Text Act Project and Work Authorized Documents BARBERS POINT HARBOR, OAHU, HAWAII An entrance channel 42 feet deep, 450 feet wide, and 3,100 feet long; an inshore basin of about 46 acres, 28 feet deep, a breakwater on the north side of the entrance channel, if model study shows it to be necessary; spending beaches with wave absorbers within the harbor totaling 1,320 feet in length; and a main access channel 12 feet deep, 80 feet wide, and 1,200 feet long to a small-boat harbor on the west side of the deepdraft harbor to be developed by local interests. HONOLULU HARBOR, OAHU, HAWAII Deepening to 35 feet the inner harbor with a general width of 1,200 feet and casing the curve between the entrance channel and the inner harbor. Aug. 8, 1917 For the channel 1,000 feet long. Jul. 3, 1930 Channel connecting Honolulu Harbor and Kapalama Basin. Aug. 30, 19351 Jul. 24, 1946 Enlarging entrance channel to present project dimensions, widening of the harbor basin by 320 feet and the maintenance of the improved 400-foot wide portion of the reserved channel. A depth of 35 feet over the full width of 600 feet throughout the reserved channel; a turning basin in Kapalama Basin 35 feet deep by 1,000 feet wide and 3,000 feet long; and a slip of like depth 1,000 feet long on the easterly side of Pier 39. H. Doc. 93, 89th Cong,. 1st sess. Annual Report, 1905 p. 2565 H. Doc. 392, 64th Cong., 1st sess. H. Doc. 753, 69th Cong., 1st sess. H. Doc. 54, 73rd Cong., 1st sess. H. Doc. 705, 79th Cong., 2nd sess. Sep. 3, 1954 The second entrance channel; and installation of a moveable-type bridge across the 2nd entrance channel. (Modified by the Chief of Engineers.) Oct. 27, 1965 Reopening Fort Armstrong entrance channel to 45 feet, Main Harbor Basin and Kapalama Channel to 40 feet, and relocating existing project lines. NAWILIWILI HARBOR, KAUAI, HAWAII Mar. 2, 1919 An entrance channel 35 feet deep; a harbor basin 1,100 feet wide, 35 feet deep, and about 1,950 feet long; and a rubble-mound breakwater. Sep. '3, 1954 Deepening entrance channel to 40 feet; enlarging harbor basin; and constructing a revetted-fill area. (Modified by the Chief of Engineers.) Modification of General Navigation features. H. Doc. 717, 81st Cong., 2nd sess. (Contains latest published map) H. Doc. 93, 89th Cong., 1st sess. H. Doc. 609, 62nd Cong., 2nd sess., as modified by the Chief of Engineers. H. Doc. 453, 83 Cong., 2nd sess. (Contains latest published maps.) River and Harbor Act. 1. Oct. 27, 1965 Mar. 3, 1905 5. Dec. 31, 1970 PACIFIC OCEAN DIVISION TABLE 36-B (Cont.) AUTHORIZING LEGISLATION See Date Section Authorizing in Text Act- Project and Work Authorized Documents 13. IAO STREAM, MAUI, HAWAII Aug. 13, 1968 Channel enlargement, levees, a debris basin and related H. Doc. 151, 90th Cong., works. 1st sess. 14. KAHOMA STREAM, MAUI, HAWAII Oct. 22, 1976 A debris basin 100 feet wide and 700 feet long with a H. Doc. 94-488, 94th capacity of 22,000 cubic yards; a rock sill, a diversion Cong., 2nd. sess. levee which is 80 feet long to direct flows into the concrete channel; a concrete trapezoidal channel about 5,280 feet long; three concrete bridges with clear span of 50 feet; and revetted outlet extending 70 feet seaward of the stream mouth. 15. KANEOHE-KAILUA AREA, OAHU, HAWAII Dec. 31, 1970 Provide a dam and reservoir about 3.2 miles above the H. Doc. 92-141, 92nd mouth of Kaneohe Stream on the tributary Kamooalii Cong., 1st sess. Stream. Project consists of an earthfill dam 80 feet high, with a crest length of about 2,300 feet and about 1,000 feet of channel improvements at the entrance of Kaneohe Stream to Kaneohe bay; and reservoir with storage of 2,500 acre-feet of which 500 acre-feet would be for sediment reserve and recreation use and 2,000 acre-feet for flood control. 20. NANPIL RIVER HYDROPOWER, POHNPEI, TTPI Mar. 20, 1980 Construction of a hydroelectric power facility. Sec. 101, PL 96-205 Dec. 8, 1983 Appropriation of funds for a feasibility study and Sec. 2, PL 98-213 construction of a hydroelectric project. 'Included in the Public Works Administration program, Sep. 6, 1933. 36-9 TABLE 36-C REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 OTHER AUTHORIZED NAVIGATION PROJECTS For Last Cost to September 30, 1985 Full Report See Annual Operation and Project Status Report for: Construction Maintenance Agana Small Boat Harbor, Territory of Guam Completed 1978 $ 937,7981 $ 11,196 Ala Wai Small Boat Harbor, Oahu, Hawaii Deferred 1976 40,117 - Auasi Harbor, American Samoa Completed 1982 1,033,0152 - Aunuu Harbor, American Samoa Completed 1982 1,783,1293 5,883 Haleiwa Small Boat Harbor, Oahu, Hawaii Completed 1978 527,0474 208,902 Heeia-Kea Small Boat Harbor, Oahu, Hawaii Deferred 1972 1,481 - Hilo Harbor, Hawaii, Hawaii Completed 1982 5,423,440 3,680,856 Honokohau Small Boat Harbor, Hawaii, Hawaii Completed 1971 781,0365 63,693 Kahului Beach Road, Maui, Hawaii Completed 1976 751,8676- Kahului Harbor, Maui, Hawaii Completed 1984 7,203,2217 6,738,020 Kailua Small Boat Harbor, Oahu, Hawaii Deferred 1967 -- Kalaupapa Harbor, Molokai, Hawaii Completed 1968 157,9978 3,127 Kaunakakai Harbor, Molokai, Hawaii Deferred 1966 138,188 292,441 Kawaihae Harbor, Hawaii, Hawaii Active 1981 5,983,5019 61,800 Keehi Lagoon, Oahu, Hawaii Completed 1956 3,348,00010 41,857 Kikiaola Small Boat Harbor, Kauai, Hawaii Active 1981 193,000 - Lahaina Small Boat Harbor, Maui, Hawaii Inactive 1977 186,937 - Maalaea Small Boat Harbor, Maui, Hawaii Active 1981 195,000 - Maunalua Bay Small Boat Harbor, Oahu, Hawaii Deferred 1972 30,378 - Nawiliwili Small Boat Harbor, Kauai, Hawaii Completed 1976 584,5131" 30,707 Ofu Small Boat Harbor, American Samoa Completed 1976 980,01812 668,354 Pohoiki Bay, Hawaii, Hawaii Completed 1979 432,52313- Port Allen Harbor, Kauai Hawaii Completed 1984 752,64514 884,833 Reeds Bay Small Boat Harbor, Hawaii, Hawaii Active 1967 15- Saipan Small Boat Harbor, Northern Marianas Active 1982 194,000- Waianae Small Boat Harbor, Oahu, Hawaii Completed 1979 1,940,01116 71,897 Wake Island Harbor, Wake Island Inactive 1950 - 14,493 Welles Harbor, Midway Island Completed 1950 2,448,05617 2,111 'Authorized by the Chief of Engineers and completed in October 1977. In addition, Contributed Funds of $282,747 for Construction. 2Authorized by the Chief of Engineers and completed in February 1982. In addition, Contributed Funds of $86,563 for Construction. 3Authorized by the Chief of Engineers and completed in February 1982. In addition, Contributed Funds of $231,437 Construction. 4Authorized by the Chief of Engineers and completed in November 1975. In addition, Contributed Funds of $410,077 for Construction and $84,388 for Operation and Maintenance. 'Completed in March 1970. In addition, Contributed Funds of $630,568 for Construction. 6Authorized by the Chief of Engineers and completed in April 1976. 7in addition, Contributed Funds of $30,200 for Construction. 8Authorized by the Chief of Engineers and completed in September 1967. 9In addition, Contributed Funds of $62,102 for Construction. 10Abandonment authorized by R & H Act of 1965 (HD 98, 89th Congress, 1st Session). "Authorized by the Chief of Engineers and completed in November 1974. In addition, Contributed Funds of $405,471 for Construction. 2Authorized by the Chief of Engineers and completed in August 1975. In addition, Contributed Funds of $61,953 for Construction. 3Authorized by the Chief of Engineers and completed in April 1979. 14In addition, Contributed Funds of $200,000 for Construction. 15Reclassified from deferred to active category on May 16, 1983. ' 61n addition, Contributed Funds of $1,791,068 for Construction. 17Completed in 1941 and Maintenance transferred to Department of Navy. 36-10 PACIFIC OCEAN DIVISION TABLE 36-D OTHER AUTHORIZED BEACH EROSION CONTROL PROJECTS For Last Cost to September 30, 1985 Full Report See Annual Operation and Project Status Report for: Construction Maintenance Afono Area and Aoa Area, American Samoa Completed 1978 $254,015' $ - Haleiwa Beach, Oahu, Hawaii Completed 1967 240,1482- Hanapepe Bay, Kauai, Hawaii Deferred 1965 -- Kaaawa Beach, Oahu, Hawaii Completed 1976 176,4883 - Kapaa Tbwn, Kauai, Hawaii Completed 1977 158,9164 - Kekaha Beach, Kauai, Hawaii Completed 1981 999,9965 - Kihei Beach, Maui, Hawaii Completed 1972 154,3136 - Kualoa Regional Park, Oahu, Hawaii Terminated 1982 355,4727 - Matafao Shoreline, American Samoa Completed 1984 225,0008 - Pago Pago Airport, American Samoa Completed 1984 174,9419- Pago Pago to Nuuuli, American Samoa Completed 1978 394,18710- Poloa Area, American Samoa Completed 1978 136,040" - Sand Island, Oahu, Hawaii Completed 1981 301,87912- Vatia Area, American Samoa Completed 1978 154,30913 - Waikiki Beach, Oahu, Hawaii Active 1979 729,08714 - Waimea Beach, Kauai, Hawaii Deferred 15 85,043 'Authorized by the Chief of Engineers and completed in October 1977. In addition, $209,549 in Contributed Funds. 2Completed in April 1965. In addition, $160,098 in Contributed Funds. 3Authorized by the Chief of Engineers and completed in April 1975. In addition, $97,075 in Contributed Funds. 4Authorized by the Chief of Engineers and completed in September 1976. In addition, $56,916 in Contributed Funds. 5Authorized by the Chief of Engineers and completed in December 1980. In addition, $1,672,524 in Contributed Funds. 6Authorized by the Chief of Engineers and completed in December 1980. In addition, $1,672,524 in Contributed Funds. 7Authorized by the Chief of Engineers and terminated in April 1980 as a Circuit Court ruled sand mining to be illegal. In addition, $177,300 in Contributed Funds. 8Authorized by the Chief of Engineers and completed in June 1984. 9Authorized by the Chief of Engineers and completed in June 1984. 10Authorized by the Chief of Engineers and completed in September 1978. In addition, $312,480 in Contributed Funds. "Authorized by the Chief of Engineers and completed in October 1977. In addition, $101,547 in Contributed Funds. '2Authorized by the Chief of Engineers and completed .in April 1981. In addition, $255,728 in Contributed Funds. '3Authorized by the Chief of Engineers and completed in October 1977. In addition, Contributed Funds of $132,075 in Contributed Funds. "4In addition $82,000 in Advanced Funds and $17,640 in Contributed Funds. 15No previous full report; project authorized by R & H Act of 1958. 36-11 TABLE 36-E REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 OTHER AUTHORIZED FLOOD CONTROL PROJECTS For Last Cost to September 30, 1985 Full Report See Annual Operation and Project Status Report for: Construction Maintenance Hanapepe River, Kauai, Hawaii Completed 1967 $ 784,8671 $ - Kaunakakai Stream, Molokai, Hawaii Completed 1950 73,7482 Kawainui Swamp, Oahu, Hawaii Completed 1967 1,265,5673 - Kuliouou Stream, Oahu, Hawaii Completed 1971 1,000,0004 - Namo River, Territory of Guam Completed 1982 2,416,3146 - Wailoa Stream and Tributaries, Hawaii, Hawaii Completed 1966 1,044,8886 - 'Completed in November 1966. In addition, $11,953 in 4Authorized by the Chief of Engineers and completed in Contributed Funds. February 1970. In addition, $540,335 in Contributed Funds. 2Authorized by the Chief of Engineers and completed in 'Authorized by the Chief of Engineers and completed in December 1950. April 1982. aCompleted in August 1966. 6Completed in August 1965. TABLE 36-G DEAUTHORIZED PROJECTS For Last Full Report Date Federal Contributed See Annual and Funds Funds Project Report for: Authority Expended Expended Hana Small Boat Harbor, 1967 November 1977 $ Maui, Hawaii HD #94-413 Hanalei Small Boat Harbor, 1967 November 1981 - - Kauai, Hawaii HD #97-59 Kaimu Black Sand Beach, 1975 July 1981 86,235 Hawaii, Hawaii Director of Civil works Kapaakea Homestead Flood Control 1979 July 1981 221,500 Molokai, Hawaii Director of Civil Works Kewalo Harbor, Oahu, Hawaii 1976 September 1975 98,800 Director of Civil Works Talofofo Bay Shore Protection, - August 1981 80,764 Territory of Guam * Director of Civil Works 36-12 PORTLAND, OR, DISTRICT* The territorial limits of the Portland District include the Pacific coastal drainage area of the State of Oregon, the portions of the States of Oregon and Washington which lie within the Columbia River watershed downstream of the Umatilla Bridge below McNary Dam, and south central Oregon west of the Malheur River and the Steens Mountains, but not including that part which drains into the Klamath Lake and River. IMPROVEMENTS Navigation 1. Bandon Small Boat Basin, Coquille, OR .. 2. Charleston Channel, Coos Bay, OR ....... 3. Chetco River, OR ...................... 4. Columbia and Lower Willamette Rivers below Vancouver, WA, and Portland, OR .. 5. Columbia River at Baker Bay, WA ....... 6. Columbia River between Chinook, WA, and Head of Sand Island ............... 7. Columbia River at the Mouth, OR and WA 8. Columbia River between Vancouver, WA and The Dalles, OR ................... 9. Columbia River, Ilwaco, WA ............. 10. Coos Bay, OR ..... ................... 11. Coos and Millicoma Rivers, OR .......... 12. Coquille River, OR ................... 13. Cowlitz River, WA ..................... 14. Depoe Bay, OR....................... 15. Lewis River, WA ...................... 16. Navigation Work Under Special Authorization .. ............... ........ 17. Nehalem Bay, OR ..................... 18. Port Orford, OR ...................... 19. Project Condition Surveys .............. 20. Rogue River Harbor at Gold Beach, OR... 21. Siuslaw River, OR ..................... 22. Skamokawa Creek, WA................ 23. Skipanon Channel, OR ................. 24. South Channel, Government Island, OR . 25. Tillamook Bay and Bar, OR ............ . 26. Umpqua River, OR .................... 27. Willamette River above Portland and Yamhill River, OR.................... 28. Willamette River at Willamette Falls, OR. 29. Winchester Bay, Umpqua River, OR ...... 30. Yaquina Bay and Harbor, OR ........... Page 37-2 37-2 37-2 37-3 37-4 37-4 37-4 37-5 37-5 37-6 37-6 37-7 37-7 37-7 37-7 37-8 37-8 37-8 37-8 37-8 37-9 37-9 37-9 37-10 37-10 37-10 37-11 37-11 37-12 37-12 Flood Control 31. Applegate Lake, Rogue River Basin, OR .. 37-13 32. Blue River Lake, OR .................. 37-13 Page 33. Cottage Grove Lake, OR ................ 37-13 34. Dorena Lake, OR.................... . 37-14 35. Elk Creek Lake, Rogue River Basin, OR .. 37-14 36. Fall Creek Lake, OR .................. 37-14 37. Fern Ridge Lake, OR .................. 37-14 38. Huntington Avenue, Castle Rock, WA .... 37-15 39. Flood Control Work Under Special Authorization......................... 37-15 40. Inspection of Completed Flood Control Projects.............................. 37-16 41. Inspection of Completed PL-99 Works .... 37-16 42. John Day River (West), OR .............. 37-16 43. Lower Columbia River Basin, OR and WA. 37-16 44. Lower Columbia River Basin Bank Protection, OR and WA...................... 37-17 45. McDonald Dike Road, Nehalem River, OR. 37-17 46. Mt. St. Helens & Vicinity, WA .......... 37-17 47. Salmon Creek near Vancouver, WA ....... 37-18 48. Scheduling Flood Control Reservoir Operations ........................... 37-18 49. State Highway 101 and 401, Columbia River, WA ........................... 37-18 50. Tualatin, OR ......................... 37-18 51. Umatilla River, Thorn Hollow, OR ....... 37-18 52. Wahkiakum County Consolidated Diking District No. 1, WA.................... 37-19 53. West Makinster Road, Wilson River, OR .. 37-19 54. Willamette River Basin, OR ............ 37-19 55. Willamette River Basin Bank Protection, OR 37-19 56. Willow Creek Lake, Heppner, OR 37-20 Multiple-Purpose Projects, Including Power 57. Bonneville Lock and Dam - Lake Bonneville, OR and WA ......... 58. Cougar Lake, OR............... 59. Detroit Lake, OR................ 60. Green Peter-Foster Lakes, OR ..... 61. Hills Creek Lake, OR ............ ...... 37-20 ...... 37-21 ...... 37-21 ...... 37-22 ...... 37-22 37-1 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 62. John Day Lock and Dam - Lake Umatilla, OR and WA ................. 63. Lookout Point Lake, OR ................ 64. Lost Creek Lake, Rogue River Basin, OR 65. The Dalles Lock and Dam - Lake Celilo, WA and OR ......................... General Investigations 66. Surveys.............................. 67. Collection and Study of Basic Data ...... 68. Continuation of Planning and Engineering 37-23 37-23 37-24 37-25 37-25 37-25 37-26 Tables Table 37-A Cost & Financial Statement .... 37-27 Table 37-B Authorizing Legislation........ 37-35 Table 37-C Other Authorized Navigation Projects .................... 37-45 Table 37-D Not Applicable Table 37-E Other Authorized Flood Control Projects ................... . 37-46 Table 37-F Other Authorized Multiple Purpose Projects, Including Power .. 37-50 Table 37-G Deauthorized Projects ......... 37-50 Table 37-H Columbia and Lower Willamette River Below Vancouver, WA and Portland, OR................ 37-51 Table 37-I Navigation Activities Pursuant to Section 107, Public Law 86-645 ...................... 37-51 Table 37-J Project Condition Surveys ...... 37-51 Table 37-K Willamette River at Willamette Falls, OR, Principal Features of Existing Canal and Locks ...... 37-51 Table 37-L Flood Control Activities Pursuant to Section 205, Public Law 80-858 ...................... 37-52 Table 37-M Flood Control Reservoir Operations .................. 37-53 Table 37-N Lower Columbia River Basin, OR and WA, Levees and Improvements to Existing Works . 37-54 Table 37-0 Willamette River Basin Comprehensive Plan .............. 37-55 Table 37-P Principal Data Concerning Navigation Lock, Spillway Dam and Powerplant .............. 37-57 Navigation 1. BANDON SMALL BOAT BASIN, COQUILLE RIVER, OR Location. Coquille River rises in Coast Range, flows generally westerly for about 100 miles, and empties into the Pacific Ocean at Bandon, OR, 225 miles south of mouth of Columbia River and 420 miles north of San Francisco Bay. (See NOAA charts 18580 and 18186.) Existing project. Provides for a protective rubblemound breakwater and an entrance and access channel, 13 feet deep, for a small boat basin at Bandon. Mean lower low water is plane of reference. Tidal range between mean lower low water and mean higher high water at mouth is 7 feet and extreme about 10 feet. Local cooperation. Fully complied with. Terminal Facilities. At Bandon, there is a privately owned mill dock used exclusively for shipping lumber on coastwise vessels, a public owned wharf, and a small-boat basin open to all on equal terms. Operations during fiscal year. New work: Final fiscal requirements were completed. 2. CHARLESTON CHANNEL, COOS BAY, OR Location. Charleston Channel is located in south slough tributary of Coos Bay. The Charleston Channel follows the south slough from its confluence with the main channel of Coos Bay south to the Cape Arago highway bridge. Existing project. Plan of improvement provides for a 150-foot wide channel 6,200 feet long with depths between 16 to 17 feet mean lower low water. Also provides for a 180 x 900 foot turning basin and 100 by 400 foot access channel, both - 16 feet mean lower low water. Local cooperation. Port of Coos Bay, project sponsor. Operations during fiscal year. New work: Final fiscal requirements were completed. 3. CHETCO RIVER, OR Location. Rises in Siskiyou Mountains of Coast Range at an elevation of 4,000 feet, flows for about 51 miles in a circuitous route, and empties into Pacific Ocean at Brookings, OR, 300 miles south of entrance to Columbia River and 345 miles north of San Francisco Bay. (See National Oceanic and Atmospheric Administration Charts 18600 and 18203.) Existing project. Provides for two jetties at the mouth of the river. Modification in 1965 authorized an entrance channel 120 feet wide by 14 feet deep; a barge turning basin about 250 feet wide, 650 feet long, and 14 feet deep; and a small boat access channel 100 feet wide by 12 feet deep. Also authorized was a 450-foot extension of north jetty with an increase in elevation of existing portion and a protective dike about 1,800 feet long with a top elevation of 18 feet. Mean lower low water is plane of reference. 37.2 PORTLAND, OREGON DISTRICT Tidal range between lower low water and mean higher high water is 6.9 feet and extreme is about 12 feet. Construction of jetties was completed December 1957. Removal of rock pinnacles and an abandoned bridge structure was accomplished in June 1959. Under authorized modification of October 1965, two contracts were completed. Construction of entrance channel and extension of north jetty was initiated in July 1968 and completed in July 1969. Construction of a protective dike, turning basin and small boat access channel was started in September 1969 and completed in March 1970. Local cooperation. Fully complied with. Terminal facilities. The Port Commission of Brookings has developed two large boat basins, one for commercial fishing boats and the other for small private boats, and a public boat launching ramp. There are four fish receiving docks and a sea-going barge dock for lumber loading and storage. There is also a privately owned marina and a Coast Guard Station. Operations during fiscal year. Maintenance: A total of 35,045 cubic yards of material was removed by the U.S. hopper dredge Yaquina. 4. COLUMBIA AND LOWER WILLAMETTE RIVERS BELOW VANCOUVER, WA, AND PORTLAND, OR Location. The Columbia River rises in British Columbia, through which it flows for 425 miles. It enters the United States in northeastern Washington, and empties into the Pacific Ocean 645 miles north of San Francisco Bay and 160 miles south of Strait of Juan DeFuca. Total length of river is 1,210 miles. (See NOAA Charts 18520, 18521, 18522, 18523, 18524, 18526, & 18531; also Geological Survey Map of Washington). Willamette River rises in Cascade Range in southwestern Oregon, flows northerly, and empties into Columbia River about 100 miles from the sea. Its length from source of Middle Fork is about 294 miles. Project embraces 103.5 miles of Columbia River below Vancouver, WA, and 14.6 miles of Willamette River below Portland, OR. (See NOAA Chart 18526 and Geological Survey Map, State of Oregon.) Existing project. Provides for a channel 35 feet deep and 500 feet wide from River Mile 106.5 to 105.5, the distance between existing highway and railroad bridges; a channel 40 feet deep and 600 feet wide from Vancouver, WA, River Mile 105.5 to mouth of Columbia River, River Mile 3; a turning basin at Vancouver, WA, 40 feet deep, 800 feet wide, and about 5,000 feet long; a turning basin at Longview, WA, 40 feet deep, average width of 1,200 feet, and about 6,000 feet long; and a channel 40 feet deep in the Willamette River with varying widths of 600 to 1,900 feet from mouth (River Mile 0) to Broadway Bridge (River Mile 11.6) which encompasses Portland Harbor area, subject to provisions that channel from mouth of Willamette River to turning basin at Vancouver, WA, be limited to 500 feet in width until need for additional width is demonstrated by developed traffic. Existing project also provides for auxiliary channels 10 feet deep and 300 feet wide near Cathlamet, WA; 30 feet deep and 300 feet wide in St. Helens (Oregon) Channel; and 30 feet deep and 500 feet wide connecting upper end of St. Helens Channel with main ship channel of Columbia; 24 feet deep and 200 feet wide along frontage of town of Rainier, OR, extended at its upper and lower ends to deep water in Columbia River, 8 feet deep and 150 feet wide from this depth in Columbia River through old mouth of Cowlitz River to a point about 3,000 feet upstream from present terminus of harbor line; a channel from Longview Port dock downstream along pierhead line and past Weyerhaeuser Timber Co. ,plant at Longview to a connection with main ship channel below Mount Coffin, the downstream 2,400 feet of this channel to be 30 feet deep and 300 feet wide and remainder to be 28 feet deep and 250 feet wide; construction of a small-boat mooring basin at Astoria, OR, to include a sheet-pile, sand-filled breakwater about 2,400 feet long with a 30-foot roadway along its full length, and steel pile shore wings totaling about 1,460 feet long and for stone-and-pile dikes and revetments. Plane of reference in estuary from mouth to Harrington Point is mean lower low water; thence to Portland and Vancouver, low water. Tidal range between mean lower low water and mean higher high water at mouth of Columbia is about 8 feet, and at Portland and Vancouver about 3 feet at low stages of rivers. Extreme tidal ranges are about 13 and 3 feet, respectively. Annual freshets have little effect on stage of tide at mouth of Columbia; at Portland and Vancouver they average about 12 feet, while highest known reached a stage of 33 feet above low water at Portland. Work on the 40-foot channel in Columbia River from Portland, OR, and Vancouver, WA, to the sea was completed in 1976 except for observation of channel to determine if additional control structures or dredging will be required. Auxiliary channel in vicinity of Longview was completed in 1949, and improvement of mouth of Cowlitz River and small boat mooring basin at Astoria were completed in 1950. Project depths are maintained all year except for the period immediately following the annual freshet in May-June when shoaling occurs at several locations. Timing of vessel movement with tidal fluctuations permit maximum draft conditions. In Columbia and Willamette Rivers between mouth and Broadway Bridge at Portland a depth of 40 feet at low tide and 42 feet at high tide is practicable all year. In Columbia River between mouth of Willamette River and Vancouver, WA, depths of 40 and 42 feet at low and high tide, respectively, are practicable all year. (For details relating to previous project, see pages 1995 and 1998 of Annual Report for 1915 and page 1746 of Annual Report for 1938.) Local cooperation. Fully complied with. Requirements are described in full on page 37-3 of FY 1981 Annual Report. Trminal facilities. At Portland, OR, there are six Port of Portland terminals consisting of 43 berths with total capacity of 8,800,000 tons equipped to handle general cargo, bulk cargo, lumber, automobiles, lift on-lift off and roll on-roll off containers, and breakbulk vessels. The Port of Portland owns and operates a major ship repair yard, which includes the West Coast's largest, and the world's 37-3 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 third largest, floating dry dock. The Port of Portland also has a 450,000-cubic-foot cold storage warehouse. Also available in the harbor area are privately operated facilities with total capacity of 16,200,000 tons for receiving, storing and outloading petroleum, wood chips, grain, logs, sand and gravel, cement and steel products. At Astoria, OR, there is a terminal with facilities for receiving and handling all types of general cargo. At Vancouver, WA, there are municipal facilities capable of berthing five ships simultaneously. Each berth is completely outfitted with mechanical and lift facilities for receiving and handling all types of cargo. The port has a low dock to handle roll on-roll off and side-port discharging vessels. The grain terminal has a storage capacity of 4,500,000 bushels. Port of Longview has a public terminal on Columbia River and a privately owned grain elevator with a capacity of 6,900,000 bushels. This port also has a heavy lift facility, with a capacity of about 600 tons. Port of Kalama has two berthing areas, one port owned and one private, with a capacity of 6,000,000 tons. At other locations on Columbia River between Portland and Columbia River entrance there are sufficient private facilities to accommodate river vessels and fishing craft. These facilities, with planned extensions, are considered adequate for existing commerce. (For details see Port Series Nos. 33 and 34, Corps of Engineers, published in 1974 and 1975 respectively.) Operations during fiscal year. Maintenance: Regular maintenance continued through the year. A total of 1,989,127 cubic yards of material was removed by the U.S. hopper dredges Essayons and Yaquina, and contract hopper dredges removed 140,631 cubic yards. In addition, the pipeline dredge Oregon removed 2,075,813 cubic yards. 5. COLUMBIA RIVER AT BAKER BAY, WA Location. Baker Bay is a shallow body of water about 15 square miles in extent on the north side of Columbia River near its mouth. Bay is separated from river by Sand Island, a low-lying sand bar only a few feet above high tide level. (See NOAA Chart 18521.) Existing project. A mooring basin 10 and 12 feet deep, about 20 acres in extent with protecting breakwaters; and a west channel 10 feet deep connecting basin with deep water in Columbia River, with a width of 150 feet, increased to 200 feet for 3,500 feet at southerly end; a channel east of Sand Island to Port of Ilwaco, a distance of about 4 miles. Mean lower low water is plane of reference. Tidal range between mean lower low water and mean higher high water is about 8 feet, and extreme about 13 feet. Channel extending through easterly passage of Sand Island was completed in 1934. This portion of authorized project is not passable and is not maintained at the present time. Dredging west channel to 8 feet was accomplished September 1948. Deepening west channel to 10 feet, and boat basin and breakwater construction at Ilwaco, WA, finished December 1957, completed the project. Local cooperation. Fully complied with. Terminal facilities. Wharves, floats, ramps, and berths, for fishing craft, barges and tow-boats. Small-boat basin and protecting breakwater provides moorings for numerous fishing and recreational craft all year. Facilities are considered adequate for existing commerce. Operations during fiscal year. Maintenance: Contract pipeline dredge removed 551,772 cubic yards of material. The sand-bypasser, Sandwick displaced shoal areas to provide longer periods of channel depths for navigation traffic within the authorized project. 6. COLUMBIA RIVER BETWEEN CHINOOK, WA, AND HEAD OF SAND ISLAND Location. At easterly end of Baker Bay, lying on north side of Columbia River near mouth. (See Coast and Geodetic Survey Chart 6151.) Existing project. Channel 10 feet deep and 150 feet wide, extending from head of Sand Island to Chinook: a turning and mooring basin at upper end of channel, 10 feet deep, 660 feet long, and ranging from 275 to 500 feet wide; reconstruction of easterly 393 feet of existing breakwater; and extension of existing breakwater easterly and thence northerly to connect with shore in vicinity of Portland Street, Chinook, WA. Tidal range between mean lower low water and mean higher high water is about 8 feet and extreme about 13 feet. Project as originally authorized was completed in 1940. The 10-foot channel depth modification was accomplished September 1958. Rehabilitation of existing breakwater was completed September 1962. Local cooperation. Fully complied with. Terminal facilities. Chinook Packing Company owns a wharf for receiving fresh fish, and one additional fish buying company is located at Chinook. A portion of wharf is also used as a public landing. At upper end of channel there is a turning and mooring basin with facilities for mooring 350 fishing and recreational craft. Adequate terminal and mooring facilities include a public launching ramp, hoist with 10-ton capacity and suitable supply facilities. Operations during fiscal year. Maintenance: U.S. hopper dredge Yaquina removed 21,735 cubic yards of material. 7. COLUMBIA RIVER AT THE MOUTH, OR AND WA Location. The Columbia River entrance is 645 miles north of San Francisco Bay. Project is about 120 miles downstream of Portland, OR, and Vancouver, WA. For description of Columbia River see Section 4. Existing project. Provides for a one-half-mile-wide channel across a bar 55 feet deep (mean lower low water) for the northernmost 2,000 feet, and 48 feet deep (mean lower low water) along the southern 640 feet, to be secured by two rubblemound jetties, spur jetty "B" on the north shore and by dredging. The north jetty is about 2.5 miles long and the jetty about 6.6 miles long. The unconstructed spur jetty "B" would be about 1 mile long. Tidal range 37-4 PORTLAND, OREGON DISTRICT on bar between mean lower low water and mean higher high water is about 8 feet, and extreme about 13 feet. The originally authorized project depth of 40 feet was completed in 1918; south jetty completed in 1914 and north jetty in 1917. A spur jetty (jetty "A") was completed in 1939 (repaired in 1961) for the purpose of channel stabilization. Spur jetty "B" currently is classified "inactive'." Dredging of the 48-foot bar channel started April 1956 was completed in September 1957. South jetty rehabilitation started June 1962 was completed September 1964. North jetty rehabilitation started January 1965 was completed April 1965. Additional rehabilitation of the south jetty was initiated in May 1982 and completed in September 1982. Project dimensions were available at end of fiscal year. (For details relating to previous projects, see page 1999, Annual Report for 1915 and page 1740 of Annual Report for 1938.) Local cooperation. Fully complied with. Local interests contributed $500,000 toward construction of the north jetty which was completed in 1917. Operations during fiscal year. New Work: Work was finished and final fiscal requirements were completed. Maintenance: The U.S. hopper dredge Essayons removed 4,068,060 cubic yards of material and the contract dredge Padre Island removed 1,725,000 cubic yards. 8. COLUMBIA RIVER BETWEEN VANCOUVER, WA, AND THE DALLES, OR Location. On Columbia River, between Interstate Bridge at Vancouver, WA, 106.5 miles above mouth and The Dalles, OR, mile 191, a distance of 84.5 miles. For description of Columbia River, see Section 4, "Columbia and Lower Willamette Rivers Below Vancouver, WA, and Portland, OR." Existing project. Channel 27 feet deep at low water and 300 feet wide between Vancouver, WA, and The Dalles, OR, 84.5 miles; a channel 10 feet deep at low water and 300 feet wide at upstream entrance to Oregon Slough, OR; a suitable turning basin adjacent to site of port development in vicinity of Camas and Washougal, WA; a boat basin at Hood River, OR, 500 by 1,300 feet and 10 feet deep at normal Bonneville pool level, with a connecting channel of same depth to deepwater, and a protecting breakwater on easterly side; a barge channel to waterfront at Bingen, WA, 10 feet deep at normal Bonneville pool level, 200 feet wide and about 1 mile long, and an access channel 7 feet deep at normal Bonneville pool level, 100 feet wide and about 1,000 feet long, to a natural mooring basin for small boats near east end of channel; and construction of The Dalles small boat basin, to provide a breakwater and shear boom protected basin about 400 by 800 feet in size with depth of 8 feet below a pool elevation 72.5 feet at mean sea level. Tidal range between mean lower low water and mean higher high water at Vancouver is about 3 feet and at Bonneville about 0.2 foot at low stages of the river. Extreme tidal ranges are about 4 feet and 0.4 foot, respectively. Existing project is complete. Construction of The Dalles small boat basin, was completed in 1949. Channel dredging at upper end of Oregon Slough was accomplished in 1957. Project depth of 27 feet between Bonneville and The Dalles, OR, was achieved April 1959. The 27-foot channel depth between Vancouver, WA, and Bonneville, OR, was completed May 1960. Improvement of lower entrance of Bonneville Dam lock was completed in May 1961. At the present time, the channel is maintained to a depth of 16 feet, which is adequate for using traffic. Construction of a boat basin at Hood River, OR, and of Camas- Washougal, WA, turning basin was accomplished February 1962. Construction of a barge channel in Columbia River near Bingen, WA, was completed September 1963. Local cooperation. None required. Terminal facilities. At Vancouver, WA, upstream of Interstate Highway bridge at River Mile 108.1 on site of former shipyard are numerous idle ship-building facilities equipped with railway and river moorage facilities. Also in this area are a paper-storage warehouse with barge slip, two boat building businesses (one temporary), and a storage dock with gantry crane. Sites are available for development to suit lessee. At Camas, WA, about 13.5 miles upstream from Vancouver, there is a private wharf used for transfer of papermill supplies and paper to and from barges, and facilities for discharging bulk oils from barges. At Port of The Dalles (mile 44 above Bonneville) there is a municipal wharf 125 by 1,100 feet for use by tugs and barges. There are two one-story timber and corrugated iron warehouses, each 94 by 461 feet, on this wharf. A private elevator with a capacity of 40,000 bushels and a public elevator of 1,113,800-bushel capacity for handling bulk grain to tugs and barges are also at The Dalles. Public elevator has rail, truck, and water connections. There is a port owned rail connection about three-fourths mile below municipal wharf where certain types of cargo may be handled between railroad cars and tugs or barges. At numerous locations over entire waterway there are log rollways for transfer of logs to water from trucks and public and private boat basins. Facilities are considered adequate for present commerce. Operations during fiscal year. Maintenance: The U.S. hopper dredge Yaquina removed 309,935 cubic yards of material and the sand-bypasser Sandwick displaced shoal areas. 9. COLUMBIA RIVER, ILWACO, WA Location. West channel of Baker Bay, starting at Columbia River mile 3 and extending northward 3 miles to the entrance of the mooring basin at Ilwaco, Pacific County, Washington. Existing project. The present channel is 10 feet deep and 200 feet wide for the first 2,000 feet, then 10 feet deep and 150 feet wide to the boat basin. Work was authorized under the special continuing authority contained in Section 107 of the 1960 River and Harbor Act, as amended. The plan of improvement provides for deepening the 37-5 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 channel to 16 feet along the existing alinement and the width to remain the same. This plan will reduce delays, minimize damages to commercial boats, and allow larger boats access to the processing facilities at Ilwaco, WA. Local cooperation. The project sponsor, Port of Ilwaco, has agreed to provide necessary easements, rights-of-way, and utility relocations. The Port also agreed to hold the United States free from damages and to provide and main-. tain mooring and public use facilities. Operations during fiscal year. New work: All scheduled dredging work was completed by August 1985. Future work includes the seeding of disposal area. 10. COOS BAY, OR Location. On Oregon coast 200 miles south of mouth of Columbia River and 445 miles north of San Francisco Bay. It is about 13 miles long and 1 mile wide, with an area at high tide of about 15 square miles. (See NOAA Charts 18580 and 18587.) Existing project. Two rubblemound, high-tide jetties at entrance; a channel across the outer bar 45 feet deep and 700 feet wide, reducing gradually to 35 feet deep and 300 feet wide near River Mile 1 and continuing to about mile 9; thence a channel 35 feet deep and generally 400 feet wide to mile 15; an anchorage area 35 feet deep, 800 feet wide, and 1,000 feet long at Empire (River Mile 5.5); turning basins at North Bend (River Mile 12.5) and Coalbank (River Mile 14.7) 35 feet deep, 650 feet wide and 1,000 feet long; a channel 22 feet deep and 150 feet wide from Smith's Mill (River Mile 15) to Millington (River Mile 17); a small boat basin, about 500 by 900 feet at Charleston, with a connecting channel, 10 feet deep and 150 feet wide, to deep water in Coos Bay, and construction of a protecting breakwater and bulkhead. Plane of reference is mean lower low water. Tidal range between mean lower low water and mean higher high water is 7 feet and extreme is about 11 feet at both the entrance and at Coos Bay. South jetty was completed in 1928, north jetty in 1929, and 24-foot channel in 1937. The south jetty was restored in 1941 and 1942 by construction of a concrete cap for full length of the jetty. Excavation of channel to 30 feet deep and generally 300 feet wide from entrance to Isthmus Slough was completed in 1951. Dredging outer bar channel to a depth of 40 feet, decreasing to 30 feet at Guano Rock was completed in 1952. Construction of the Charleston Channel and small-boat basin was completed in September 1956. Rehabilitation of south jetty was started in June 1962 and completed December 1963. Repair of north jetty was completed in August 1970. Construction of the deeper and wider channel to mile 15 was completed in 1979. (For details relating to previous projects, see page 1987 of Annual Report for 1915 and page 1728 of Annual Report for 1938.) Local cooperation. Fully complied with. Requirements are described in full on page 37-5 of FY 1981 Annual Report. 'Terminal facilities. At North Bend there is a municipal dock 649 feet long fronting on channel, about 2,380 feet of privately owned mill docks, and three oilreceiving terminals in vicinity. At Coos Bay there is a privately owned dock with a frontage of 1,345 feet, open to the public on equal terms; several small landings for fishing and harbor craft; and three lumber docks with 1,300, 576, and 500-foot frontages, respectively. At Eastside, on Isthmus Slough, there is a 200-foot dock. At Empire there is a privately owned lumber dock with frontage of 510 feet, and an oil terminal, also privately owned, for receipt of petroleum products by barge. At Charleston there are four wharves, one public and three private, with usable areas of 1,200, 750, 7,000, and 12,000 square feet, respectively, for receipt of fresh fish and shellfish and a large seafood receiving and processing plant. There is also a municipally owned small-boat basin, open to all on equal terms, capable of mooring 250 fishing and recreation craft. Servicing facilities for small craft are available at all facilities, and public launching ramps have been constructed in Charleston area by private interests. A privately owned floating moorage on Joe Ney Slough has facilities for mooring about 50 fishing vessels. At Jordan Cove area there is a dock, 248 feet long, for wood chip ships. These facilities are considered adequate for existing commerce. (For details see Port Series No. 33, Corps of Engineers, published in 1975.) Operations during fiscal year. Maintenance: U.S. hopper dredge Yaquina removed 114,587 cubic yards; contract pipeline dredge Husky removed 1,025,745 cubic yards; and the contract hopper dredge Padre Island removed 1,130,323 cubic yards of material. 11. COOS AND MILLICOMA RIVERS, OR Location. South Fork and Millicoma Rivers rise in Coast Range in southern Oregon, flow generally westerly and join to make Coos River, 5.3 miles above mouth of Coos River in Coos Bay. (See NOAA Chart 18587, Allegany and Daniels Creek Quadrangle.) Existing project. Originally authorized project: a channel depth of 3 feet, generally, from mouth of Coos River and 1 foot near head of navigation. Project as modified: two channels 5 feet deep and 50 feet wide from mouth of Coos River to Allegany on Millicoma River, mile 13.8 and to Delwood on South Fork, mile 14, and thence a channel 3 feet deep and 50 feet wide to mile 14.7 on South Fork, including stabilization works on Coos River. Mean lower low water is plane of reference. Tidal range between mean lower low water and mean higher high water at the mouth of Coos River is 7 feet and extreme about 11 feet. Tidal range at head of navigation in both forks is about 1 foot. Freshet stages usually reach a height of from 10 to 15 feet at Allegany, head of navigation on Millicoma River. 37-6 PORTLAND, OREGON DISTRICT Originally authorized project providing for a channel from mouth of Coos River to head of navigation in both forks, to provide a depth of 3 feet generally and 1 foot near head of navigation, was completed in 1899. In March 1966 construction of project as modified by 1948 River and Harbor Act was completed. Local cooperation. Fully complied with. Terminal facilities. Several small privately owned docks and landing places on the river are used by towboats and pleasure craft. There are no publicly owned docks. Present facilities are considered adequate for existing commerce. Operations during fiscal year. Maintenance: Inspections were performed along with condition surveys and reports. 12. COQUILLE RIVER, OR Location. Rises in Coast Range, flows generally westerly for about 100 miles, and empties into Pacific Ocean at Bandon, OR, 225 miles south of mouth of Columbia River and 420 miles north of San Francisco Bay. (See NOAA Charts 18580 and 18186.) Existing project. Two rubblemound high-tide jetties at river mouth, south jetty 2,700 feet long and the north, 3,450 feet long; and a channel 13 feet deep at mean lower low water and of suitable width from the sea to a point 1 mile above old Coquille River Lighthouse, and snagging to State highway bridge at city of Coquille. Mean lower low water is plane of reference. Tidal range between mean lower low water and mean higher high water at mouth is 7 feet and extreme about 10 feet. Jetties were completed in 1908 and entrance channel in 1933. North jetty was reconstructed in 1942 and a 750-foot extension to easterly end was constructed in 1951. South jetty was repaired in 1954 and north jetty in 1956. Coquille Lighthouse rehabilitation was completed June 21, 1976. (For details relating to previous projects, see page 1986 of Annual Report for 1915 and page 1727 of Annual Report for 1938.) Local cooperation. None required. However, restoration of lighthouse using Code 710, Recreation Facilities at Completed Projects, funding required 50 percent cost sharing with non-Federal sponsor (Oregon State Parks). Terminal facilities. At Bandon: A privately owned mill dock used exclusively for shipping lumber on coastwise vessels, a publicly owned wharf, and a small-boat basin open to all on equal terms... Operations during fiscal year. Maintenance: U.S. hopper dredge Yaquina removed 14,020 cubic yards of material from entrance channel. 13. COWLITZ RIVER, WA Location. Rises in Cascade Range in Washington, flows westerly and southerly about 120 miles and empties into Columbia River about 69 miles from its mouth. (See NOAA Chart 18524.) Existing project. A channel 8 feet deep at low water and 100 feet wide from the mouth to Kelso (4.2 miles), 4 feet deep and 50 feet wide from Kelso to Ostrander (4.8 miles), 2.5 feet deep and 50 feet wide to Castle Rock (10 miles), and 2.5 feet deep at low water and not less than 40 feet wide to Toledo (18 miles) to be secured by snagging, dredging, and regulating works. Water level due to tides varies from 4 feet at the mouth to zero at Ostrander. During ordinary freshets a stage of 20 feet, and at extreme floods a stage of 25 feet, is reached in the river at Kelso. The project as authorized in 1910 was completed in 1913. The modification authorized in January 1965 for deepening the lower 4.2 miles (old 4.75) to 8 feet was comleted in August 1968. Project is normally maintained to iver Mile 4.2; however, the authorized channel on the Cowlitz between River Miles 0 and 4.2 remains unusable due to continued sedimentation as a result of the Mt. St. Helens eruption. (For details relating to previous project see page 2000, Annual Report for 1915 and page 1763, Annual Report for 1938.) Location cooperation. None required. Terminal facilities. Privately owned and operated landings, a sand and gravel dock, log rollways, and storage booms. Facilities are considered adequate for existing commerce. Operations during fiscal year. Maintenance: Inspections were performed. 14. DEPOE BAY, OR Location. Harbor on Oregon coast 100 miles south of mouth of Columbia River. (See Coast and Geodetic Survey Chart 5902.) Existing project. Two breakwaters north of entrance; an entrance channel 8 feet deep and 50 feet wide; and inner basin 750 feet long, 390 feet wide and 8 feet deep with retaining wall along easterly side; and a stone spending beach. Mean lower low water is plane of reference. Tidal range between lower low water and higher high water is 8 feet and extreme is about 12 feet. Project as originally authorized was completed in 1939 and project modification, enlarging the basin and deepening to 8 feet, was accomplished in June 1952 and August 1966. Local cooperation. Fully complied with. Terminal facilities. Facilities, in inner basin, consist of landings and floats to accommodate operators of excursion and commercial fishing boats. Facilities considered adequate for existing commerce. Operations during fiscal year. Maintenance: Condition surveys, miscellaneous inspections and reports were performed. 15. LEWIS RIVER, WA Location. Rises in Cascade Range in Washington, flows westerly and southwesterly 110 miles, and empties into Columbia River about 88 miles from its mouth. (See NOAA Chart 18524.) Existing project. A low-water channel 6 feet deep and 50 feet wide to mouth of East Fork (3.75 miles); 4 feet deep and 50 feet wide on East Fork from its mouth to La Center (3 miles); 4 feet deep and 50 feet wide on Lewis River from the mouth of East Fork to Woodland (2.5 miles), secured 37-7 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 by dredging and construction of regulating works and channel clearing to Merwin Dam (12.5 miles from Woodland). Maximum variation of water level, due to tide, ranges from about 3 feet at mouth to 1.5 feet at La Center and zero at Woodland, During ordinary freshets a stage of 14 feet and, at extreme floods, a stage of 24 feet is reached in main river at Woodland, WA. Existing project was completed in 1927. (For details relating to previous projects, see page 2001, Annual Report for 1915, and page 1762, Annual Report for 1938.) Local cooperation. None required. Terminal facilities. At Woodland on Lewis River there are several privately owned facilities for mooring, fishing and pleasure craft. Facilities considered adequate for existing commerce. Port of Woodland subleases a commercial log facility at River Mile 1.8, consisting of log rollways and booms for storage. Operations during fiscal year. Maintenance: Inspections and surveys were performed. 16. NAVIGATION WORK UNDER SPECIAL AUTHORIZATION Navigation activities pursuant to Section 107, Public Law 86-645 (preauthorization). See Table 37-I. Aquatic plant control (Section 302, Public Law 89-298): Sampling and identification of aquatic plant infestation in Columbia River and Willamette River Basins were accomplished. Total costs for fiscal year were $12,122. 17. NEHALEM BAY, OR Location. On Oregon coast, 40 miles from Columbia River mouth and 10 miles north of the entrance to Tillamook Bay. Existing project. Provides for a jetty about 3,850 feet long on the north side of entrance and a jetty 4,950 feet long on the south side. Mean lower low water is plane of reference. Tidal range between mean lower low water and mean higher high water is 8 feet, extreme is about 15 feet. Project as originally authorized was completed in 1918. Rehabilitation work was initiated in May 1981 and completed November 1982. Local cooperation. None required. Terminal facilities. Facilities for pleasure craft only: Dart's Marina, Brighton Moorage, Jetty Fishery, Port of Nehalem and city of Nehalem Dock. All areas have approximately 50-60 slips. However, due to shoaling, all are semi-usable. Operations during fiscal year. New work: Project is physically completed except for removal of hazardous railroad crossing by railroad company. 18. PORT ORFORD, OR Location. On Oregon coast 250 miles south of Columbia River entrance and 390 miles north of San Francisco Bay. (NOAA Chart 18203 and Geological Survey Quadrangle, Port Orford, OR.) Existing project. Improvement of harbor by 550-foot extension of existing locally constructed breakwater and dredging of a turning basin, 340 feet long, 100 feet wide and 16 feet deep. Breakwater was completed October 1968. Turning basin was completed September 1971. Local cooperation. Fully complied with. Terminal facilities. A dock which is a timber piling structure about 210 by 70 feet, equipped with hydraulic crane for lifting boats from the water to dock for repairs and/or storage and removing fish catches from boats. Expansion of the dock structure to 210 x 220 feet and the installation of a second hydraulic crane is expected to be completed in FY 1986. About 500 fishing and private boats use this dock each year. Operations during fiscal year. Maintenance: During the summer months, the sand-bypasser Sandwick displaced shoal areas to provide longer periods of channel depths for navigation traffic within the authorized project. A contract bucket loader removed 10,174 cubic yards of material which would provide users with adequate depths to utilize cranes during the winter months. 19. PROJECT CONDITION SURVEYS Surveys were conducted during FY 1985 at a cost of $54,086; cumulative costs, $487,656 (See Table 37-J). 20. ROGUE RIVER HARBOR AT GOLD BEACH, OR Location. Rises in Cascade Range in southwestern Oregon, flows westerly through Coast Range, and empties into Pacific Ocean 264 miles south of mouth of Columbia River and 381 miles north of San Francisco Bay. (See NOAA Chart 18202.) Existing project. Two jetties at entrance, and a channel 13 feet deep and 300 feet wide from ocean to a point immediately below State highway bridge, about 1 mile, including widening channel at a point about 0.25 mile below bridge to form a turning basin 13 feet deep, 500 feet wide, and 650 feet long. At request of local interests, turning basin was located in south portion of estuary downstream from a point 0.25 mile below bridge. This change was effected to permit adequate terminal facilities to be constructed adjacent to turning basin. Mean lower low water is plane of reference. Range of tide between mean lower low water and mean higher high water is 7 feet, and extreme about 14 feet. Project as authorized has been completed. Construction of two jetties at entrance was completed September 1960. Dredging river channel by contract and entrance bar by government plant was completed October 1961. North jetty rehabilitation along channel side was completed October 1966. Breakwater construction and dredging, under contract awarded in September 1964, was 17 percent accomplished when flood of December 1964 destroyed all completed works. Contract was terminated as further construction at that location was considered unfeasible. Bank protection work at Wedderburn location was completed in October 1972. A breakwater, constructed by Port of Gold 37-8 PORTLAND, OREGON DISTRICT Beach, was completed during 1973. In 1984, three pile dikes, south side of channel, oceanward of the boat basin entrance, were completed. Local cooperation. Fully complied with. Terminal facilities. There are various landings for fishing and recreational craft. At Wedderburn, across river from Gold Beach, is a facility to accommodate excursion passengers and small freight items destined for various private landings between Wedderburn and Agness, OR. Facilities considered adequate for existing commerce. Operations during fiscal year. Maintenance: U.S. hopper dredge Yaquina removed 40,095 cubic yards of material and sand-bypasser Sandwick displaced isolated shoals. Contract dredging was accomplished to clear the boat basin entrance channel with 51,858 cubic yards of material removed by a pipeline dredge. 21. SIUSLAW RIVER, OR Location. Rises in coast range, flows about 110 miles westerly and empties into Pacific Ocean about 160 miles south of entrance of Columbia River and 485 miles north of San Francisco Bay, CA. (See NOAA Charts 18583 and 18580.) Existing project. Provides for 2 high-tide, rubblemound jetties 750 feet apart at the outer end, the north jetty 8,390 feet long (600 feet unconstructed) and the south jetty 4,200 feet long; an entrance channel 18 feet deep and 300 feet wide from deep water in ocean to a point 1,500 feet inside the outer end of existing north jetty; thence a channel 16 feet deep, 200 feet wide with additional widening at bends, and about 5 miles long, to a turning basin, 16 feet deep, 400 feet wide, and 600 feet long, opposite Suislaw dock at Florence; a channel 12 feet deep, 150 feet wide from Florence to mile 16.5; and at River Mile 15.5 a turning basin 12 feet deep, 300 feet wide and 500 feet long. Mean lower low water is plane of reference. Tidal range between mean lower low water and mean higher high water at mouth of river is 7 feet and extreme about 11 feet. During low stages of river, tidal effect extends to Mapleton, 20.5 miles above mouth. (For details relating to previous project see page 1988 of Annual Report for 1915.) A modification to the existing project was authorized by Public Law 96-367, October 1, 1980. North and south jetty modifications were completed in FY 85. Modifications provide for extending the north and south jetties by 1,900 and 2,300 feet respectively. The jetty extensions will terminate at approximately the minus 25-foot contour. Spur jetties were constructed on each jetty extension to prevent longshore currents from transporting material around the heads of the jetties. Each spur jetty is 400 feet long and originate approximately 900 feet shoreward of the jetty head. The north jetty spur is oriented 45 degrees to the north of the existing jetty alignment and the south jetty spur 45 degrees to the south of the jetty alignment. Estimated cost of jetty work is $30,727,000; $30,500,000 Corps of Engineers, $183,000 non-Federal, and $44,000 U.S. Coast Guard. Local cooperation. None required. Terminal facilities. The principal terminal facility on the river is at Davidson Lumber Dock at Mapleton which can accommodate ocean-going barges. Port dock at Florence, 150 feet wide and 350 feet long, is about 5.3 miles above river entrance and accommodates a fish-receiving station at east end of wharf which maintains a 2-ton capacity winch and supplies gasoline, oil and ice to fishermen. Other facilities at Florence consist of various floatways which provide docking facilities for fishing vessels and other small craft and a floating dock with accommodations for 75 commercial fishing vessels. The Port has recently acquired a marine travel lift to accommodate vessels 70 feet in length or 60 tons in weight. Adjacent to commercial basin is mooring basin with accommodations for 200 sport boats of all sizes. Across the river and below highway bridge at Glaneda are floatways used by small craft. A modern dock for loading ocean-going barges with packaged lumber is maintained at Mapleton by U.S. Plywood Champion Lumber Company. There are also a number of private landings and log booms between Cushman and Mapleton to accommodate river traffic. These facilities are considered adequate for existing traffic. Operations during fiscal year. New work: Contractual work on extension of the north and south jetties continued. All work is scheduled for completion in FY 86. Maintenance: U.S. hopper dredge Yaquina removed 271,249 cubic yards of material. 22. SKAMOKAWA CREEK, WA. Location. Rises in Wahkiakum County, in southwestern part of the State of Washington, flows southwesterly and southerly about 10 miles, and empties into Columbia River about 34 miles above mouth. (See NOAA Chart 18523.) Existing project. Provides for a channel 6.5 feet deep at low water and 75 feet wide, between Steamboat and Brooks Sloughs, about 1,600 feet long. Tidal range between mean lower low water and mean higher high water is about 7 feet and maximum variation of water level due to tides or freshets is about 12 feet. During ordinary freshets a stage of 12 feet is reached in creek at Skamokawa, WA. Project as authorized was completed in 1920. Local cooperation. None required. Terminal facilities. There are several privately owned docks on Skamokawa Creek, Steamboat Slough, and Brooks Slough for use of towboats, commercial fishing vessels, and pleasure craft. Operations during fiscal year. Maintenance: Contract pipeline dredge removed 21,900 cubic feet of material. 23. SKIPANON CHANNEL, OR Location. In tidal waterway extending south 2.7 miles from deep water in Columbia River. Channel enters Columbia about 10 miles above mouth and 4 miles below Astoria, OR. (See NOAA Chart 18523.) 37-9 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Existing project. Channel 30 feet deep and generally 200 feet wide extending from deep water in Columbia River to railroad bridge at Warrenton, OR, distance of 1.8 miles, turning basin of same depth, mooring basin 12 feet deep at mean lower low water at Warrenton, OR, and channel 6 feet deep, generally 40 feet wide, with increased widths at log dumps and terminals, for 4,500 feet via cutoff channel above railroad bridge. Mean lower low water is plane of reference. Tidal range between mean lower low water and mean higher high water is about 8 feet, extreme is about 13 feet. Project as authorized is complete. Dredging river channel and turning basin was completed in 1939. Construction of small-boat mooring basin at Warrenton, OR, was completed October 1957, and fill stabilization work was accomplished in August 1958. Local cooperation. None required. Terminal facilities. City of Warrenton owns wharf with a 300-foot frontage open to public on equal terms. One privately owned cannery wharf with a 300-foot frontage is used for unloading fish and handling fish nets. One privately owned boatyard has floats and moorage facilities for use of a maximum of 80 small boats. In channel above railroad bridge, facilities consist of log rollways which are no longer operating, that were used for sorting logs. Smallboat basin has facilities for numerous fishing and recreation craft. These facilities, except during the fishing season, are considered adequate for existing commerce. Operations during fiscal year. Maintenance: U.S. hopper dredge Yaquina removed 28,486 cubic yards of material. 24. SOUTH CHANNEL, GOVERNMENT ISLAND, OR Location. South Channel is a side channel of the Columbia River about 7 miles long. It connects the main shipping channel of the Columbia River just downstream of Lemon Island with the main shipping channel just upstream of Maquire Island. The downstream end of the channel is just north of the Portland International Airport. Existing project. Provides for a small boat recreational channel 100 feet wide to a depth of 6 feet (Columbia River datum) between river mile 111.8 and 118.4. Local cooperation. Fully complied with. Project sponsor, Port of Portland, contributed $102,000 towards construction. Operations during fiscal year. New work: Small spot shoals were removed and project is completed. 25. TILLAMOOK BAY AND BAR, OR Location. Bay is on Oregon coast about 50 miles south of mouth of Columbia River. (See NOAA Charts 18520 and 18558.) Existing project. Provides for a jetty about 5,700 feet long on north side of entrance and a jetty 8,000 feet long on south side; a channel through bar 18 feet deep and of such width as can be practically and economically obtained; for a channel 200 feet wide and 18 feet deep from deep water in bay to Miami Cove; and for initial dredging to 12 feet deep of a small-boat basin and approach thereto at Garibaldi, OR. Project also provides for improvement of Bayocean Peninsula, OR, by construction of sand and rockfill dike 1.4 miles long, on alinement extending between Pitcher Point and town of Bayocean. Mean lower low water is plane of reference. Tidal range between mean lower low water and mean higher high water is 8 feet, extreme is about 14 feet. Hobsonville Channel portion of project is inactive. Except for construction of Hobsonville Channel portion, classified inactive, channels were completed in 1927, north jetty in 1933, improvement of Bayocean Peninsula in 1956, and small-boat basin in 1958. Rehabilitation of north jetty was accomplished September 1965. Construction of south jetty was initiated April 1969 and was completed in September 1979. (For details relating to previous projects, see page 1989 of Annual Report for 1915 and page 1474 of Annual Report for 1936.) Local cooperation. Fully complied with. Requirements are described in full on page 37-9 of FY 1981 Annual Report. Terminal facilities. At Garibaldi: A facility owned by the Port of Bay City, for shipping lumber and receiving logs, a public landing suitable for mooring fishing vessels, towboats, and other craft. Small-boat basin has adequate facilities for mooring fishing and recreational craft. A privately owned boat ramp and moorage is available for recreational craft. At Bay City: A privately owned wharf used exclusively for receipt of fresh fish and shellfish. Facilities considered adequate fpr existing commerce. Operations during fiscal year. Maintenance: Condition surveys, miscellaneous inspections and reports. 26. UMPQUA RIVER, OR Location. Rises in Cascade Range, flows westerly about 120 miles, and empties into Pacific Ocean 180 miles south of Columbia River and 465 miles north of San Francisco Bay. (See NOAA Charts 18580 and 18584.) Existing project. A jetty on north side of entrance about 8,000 feet long, a south jetty 4,200 feet long extending to a point 1,800 feet south of outer end of north jetty; dredging to provide a usable entrance channel 26 feet deep, and a river channel 22 feet deep and 200 feet wide, from mouth to Reedsport, a distance of about 12 miles with a turning basin at Reedsport 1,000 feet long, 600 feet wide, and 22 feet deep; deepening of channel at Winchester Bay was completed in 1984, and a turning basin of 16 feet deep, 500 feet wide, and 800 feet long, opposite Gardiner, OR. Project was modified in 1954 to provide a channel in Scholfield River, but this portion of the project is currently inactive. Mean lower low water is plane of reference. Tidal range between mean lower low water and mean higher high water at river mouth is 7 feet, and extreme range is about 11 feet. 37-10 PORTLAND, OREGON DISTRICT Project is complete. North jetty was completed in 1930. Extension to original south jetty was completed in 1938. Dredging a 22-foot channel from mouth of river to Reedsport was completed in 1941. Gardiner Channel and turning basin was completed in 1949 and Winchester Bay Channel and mooring basin in 1956. The 12-foot channel in Scholfield River is currently classified inactive. Rehabilitation of south jetty was completed August 1963. Extension of training jetty was completed October 9, 1980. (For details relating to previous projects see page 2967 of Annual Report for 1898 and page 1732 of Annual Report for 1938.) Local cooperation. None required. Terminal facilities. At Gardiner there is about 650 feet of wharf frontage. Also, there is an oil unloading facility owned by International Paper Co. for exclusive use of tanker barges. Port of Umpqua owns one wharf with 456 feet of water frontage, of which 228 feet is usable for vessels and another with about 75 feet of water frontage which has not been used generally for commercial shipping. On Bolon Island across the river from Reedsport a wharf was constructed which has about 5 acres of open storage for lumber and available to all on equal terms. At Winchester Bay, 2 miles from river entrance there is a major sports and commercial fishing harbor. Facilities are considered adequate for existing commerce. Operations during fiscal year. New work: Final fiscal requirements were completed. Maintenance: U.S. hopper dredge Yaquina removed 290,451 cubic yards of material. 27. WILLAMETTE RIVER ABOVE PORTLAND AND YAMHILL RIVER, OR Location. Yamhill River rises in Coast Range, flows easterly, and empties into Willamette River about 42 miles above Portland. Its length from source of South Fork is about 52 miles. (See NOAA Chart 18526 and Geological Survey map, State of Oregon.) For description of Willamette River see Improvement No. 4. Existing project. Provides for improvement of Willamette River between Portland (mile 14) and Oregon City (mile 26) by a channel 8 feet deep at low water, 200 feet wide below Cedar Island and 150 feet wide thence to Oregon City; such channel improvement and contraction works as may be necessary to secure with streamfiow regulation, controlling depths of 6 feet at low water and of no prescribed width, from Oregon City to mouth of Santiam River (mile 108.5), 5 feet from that point to Albany (mile 120) 2.5 to 3.5 feet deep from Albany to Corvallis (mile 132), and for necessary snagging between Corvallis and Eugene (mile 185). Local interests dredge and maintain a 20-foot channel to the dock at Lake Oswego for receipt of limerock. Project also provides for a channel in Yamhill River 4 feet deep at low water and 60 feet wide from its mouth to McMinnville (18 miles) secured by means of a lock and dam near Lafayette and by removal of obstructions. Section of Willamette River in vicinity of Willamette Falls at Oregon City is covered by Section 28. For Willamette River below falls at Oregon City ordinary fluctuation of stage of water is 15 feet and extreme fluctuation due to flood conditions 35 to 50 feet. Above Oregon City ordinary fluctuation is 12 to 20 feet and extreme is 20 to 27 feet. For Yamhill River ordinary fluctuation is 35 feet and extreme 48 feet. Tidal changes vary from about 2.5 feet at mouth of Willamette to zero, 26 miles above mouth. Project is about 18 percent complete. The 8-foot channel between Portland and Oregon City and 2.5- to 3.5-foot channel between Oregon City and Albany were completed in 1939. The 2.5- to 3.5-foot channel between Albany and Corvallis was completed in 1945. Remaining work required to complete project consists of construction of such contraction works and channel improvements as may be necessary, with streamflow regulation, to secure controlling depths of 6 feet at low water from Oregon City to mouth of Santiam River, and 5 feet from that point to Albany. This remaining portion has been placed in the deferred category. Due to lack of use by commercial traffic for which facilities were provided, operation of Yamhill lock was discontinued February 7, 1954, and the lock and adjacent property reported surplus and turned over to Yamhill County January 16, 1959. There is no maintenance of the channel above Newberg, so it is only usable during higher river stages. (For details relating to previous projects see page 1997 of Annual Report for 1915 and page 1754 of Annual Report for 1938.) Local cooperation. None required. Terminal facilities. Between Ross Island Bridge at Portland and Willamette Falls at Oregon City: Privately owned mill docks, sand and gravel wharves, a cement loading facility, a small shipyard, and oil-receiving stations. Above the falls there are privately owned landings including a facility at Pulp Siding (3 miles above the falls) with rail and water connections for shipment of clay and receipt of papermill products by barge. At Wilsonville and Newberg there are sand and gravel facilities. At numerous locations as far as Corvallis (River Mile 132) there are log rollways which are currently inactive. At Lake Oswego there is a dock for the receipt of limerock used in the manufacture of cement. Facilities considered adequate for existing commerce. Operations during fiscal year. Maintenance: Condition surveys, coordination with Port authorities and resource monitoring continued. 28. WILLAMETTE RIVER AT WILLAMETTE FALLS, OR Location. Locks and dam covered by this project are at Willamette Falls, a rocky reef in Willamette River at Oregon City, OR, about 26 miles above mouth of river. Existing project. Provides for construction of a new single-lift main lock and a guard lock each with clear dimensions of 56 by 400 feet and a minimum depth over sills of 9.5 feet, to replace existing facilities which were 37-11 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 provided for by purchase, rehabilitation, and deepening to 6 feet at low water of existing canal and locks and separation of canal from waterpower intake by construction of a concrete division wall. Construction of a new lock is currently an inactive project. The existing locks are on the National Register for historic sites, making their replacement unlikely. Total length of existing canals and locks is about 3,500 feet. Principal features of existing canal and locks at Willamette Falls are set forth in Table 37-K. Ordinary fluctuation of stage of water above locks is 12 feet and extreme, due to flood conditions, 20 feet. Below locks, ordinary fluctuation is 15 feet and extreme 50 feet. Canal and locks originally constructed by private interests in 1873 were purchased by the United States in April 1915 for $375,000. Final report on purchase and rehabilitation of canal and locks is in Annual Report for 1923, when project was reported 98 percent complete. Replacement of gates Nos. 6 and 7 was completed August 1967 under minor rehabilitation funds. Existing locks and grounds are in fair condition and in continuous operation except when flooded out by high water or undergoing repair. Facilities are obsolete and inadequate for existing traffic. No construction work has been done on lock and guard lock, which was authorized to replace existing facilities by Flood Control Act of 1939, and River and Harbor Act of 1945. This portion of the project has been reclassified "deferred". Local cooperation. Fully complied with. Terminal facilities. Crown Zellerbach Corp. has a timber wharf about 850 feet long, extending to and supported by concrete division wall built in lock canal by United States. This wharf is used for receiving mill supplies and shipping paper and paper products. Operations during fiscal year. Maintenance: Normal operation and maintenance performed. 29. WINCHESTER BAY, UMPQUA RIVER, OR Location. Bay is on the Oregon coast about 180 miles south of the Columbia River, 465 miles north of San Francisco Bay. (See NOAA charts, 18580 and 18584). Existing Project. A channel 16 feet and 100 feet wide from deep water in the river to vicinity of docks in Winchester Bay with a turning basin 16 feet deep, 175 feet wide and 300 feet long; thence a channel 100 feet wide and 16 feet deep for approximately 500 feet, thence 75 feet wide and 12 feet deep for approximately 950 feet; a channel 100 feet wide and 16 feet deep extending from deep water in the river approximately 4,100 feet in length to a turning basin 160 feet wide, 16 feet deep and 200 feet long at the southerly end of the west basin. Local cooperation. Fully complied with. Operations during fiscal year. New work: Final fiscal requirement were completed. 30. YAQUINA BAY AND HARBOR, OR Location. Bay is on Oregon coast, 113 miles south of mouth of Columbia River. (See NOAA Charts 18580 and 18581.) Existing project. Two high tide rubblemound jetties at entrance, north jetty 7,000 feet, and south jetty 8,600 feet long; a spur jetty on channel side of south jetty 4,700 feet from its sea end, 800 feet long; five groins channelward from south jetty; channel 40 feet deep for a general width of 400 feet across bar and at outer end of entrance channel; a channel 30 feet deep and 300 feet wide to a turning basin of same depth, 900 to 1,200 feet wide and 1,400 feet long, and a channel 18 feet deep and 200 feet wide from 30-foot channel at about mile 2.4, thence upstream to abandoned railroad terminus at Yaquina, a distance of about 4.5 miles. Project also provides for two small boat mooring basins at Newport, OR. Mean lower low water is plane of reference. Tidal range between mean lower low water and mean higher high water is 8 feet and extreme is about 12 feet. Project as originally authorized was completed in May 1952. Restoration ofjetties was completed in 1934 and extension of north jetty 1,000 feet seaward was completed in 1940. Construction of mooring basin at Newport and dredging of channel and turning basin to project dimensions were completed during fiscal year 1949. Restoration of north jetty was again accomplished in 1956. Under modification of July 3, 1958, extension of north jetty was completed in September 1966, dredging of 40-foot bar channel and 30-foot river channel was completed in October 1968, and extension of south jetty was completed in June 1972. (For details relating to previous projects see Annual Report for 1893, part 4, page 3314, and Annual Report for 1938, page 1736.) Local cooperation. None required. Terminal facilities. At McLean Point, on north side of bay, about 2 miles from entrance, Yaquina Terminals has two berths capable of serving ocean-going vessels, one 435 feet long, the second 520 feet long. At the time the second berth was dredged, a retaining wall and fill of 6 acres were constructed adjacent to deep water. The company now has 40 acres of filled land adjacent to deep water, and of this total, 7 acres were constructed in 1956-57. This facility has necessary carriers and lift trucks for handling lumber cargoes, warehouse for covered cargo storage, and is open to all on equal terms. In recent years, deep draft vessel usage has been increasing, averaging 1-2 per month in FY 1985. Port of Newport has a public wharf within 300 feet of frontage for servicing fishing boats. In addition, Port of Newport maintains 510 berths for mooring commercial and sport fishing vessels. There are several seafood companies on the bay which have their own facilities for handling fresh fish and crab. Supplies and petroleum products are readily available for small vessels. On south side of bay about 1.2 miles above entrance, Port of Newport has constructed South Beach Marina which can handle approximately 600 small pleasure craft and shallow draft fishing boats. Public facilities include public automobile and boat trailer parking, boat launching ramp, fuel dock, fishing pier, and picnic area. A dry boat moorage for 120 boats, is nearing completion. A swing hoist with 3-ton capacity is currently available and one with 60-ton capacity is planned. 37-12 PORTLAND, OREGON DISTRICT About 1.5 miles above entrance, Oregon Aqua Foods, subsidiary of Weyerhaeuser Company, maintains a commercial fish farm facility. About 2.0 miles above entrance, Oregon State University, in conjunction with the Marine Science Center on 52 acres, maintains a 220-foot.pier for docking large and small research vessels and a 100-foot float for docking small boats. Docking facilities are restricted to research vessels and State of Oregon small boats. Operations during fiscal year. Maintenance: Contract hopper dredge Padre Island removed 302,764 cubic yards of material. 31. APPLEGATE LAKE, ROGUE RIVER BASIN, OR Location. In Jackson County, OR, on Upper Applegate River, a tributary of Rogue River, at River Mile 46, about 23 airline miles southwest of Medford, OR. Existing project. A gravel-fill embankment dam, 242 feet high from streambed to crest with an overall length of 1,300 feet. A gate-controlled concrete chute-type spillway on the left abutment, and a regulating outlet conduit, and intake tower with multilevel intakes on the left side of valley floor. Lake, 5 miles long, provides 75,000 acre-feet of usable storage for flood control and water conservation utilization. Project controls runoff from a drainage area of 223 square miles. In addition to flood control, reservoir is operated to provide irrigation, fish and wildlife enhancement, water quality control, and recreation benefits. Project is complete and operating. Local cooperation. Authorizing act requires that State of Oregon insure maintenance of stream flow released for fishery. In addition, costs allocated to irrigation would have to be repaid in a manner and to an extent consistent with reclamation laws and policies. Oregon Department of Fish and Wildlife made filing May 31, 1962 with State Engineer for water rights for use of stored water and natural flows for fish habitat improvement in amounts and at times specified in project authorization. The U.S. Bureau of Reclamation has made a feasibility study of Applegate Irrigation Division. The results of the study indicate that at present there does not appear to be a feasible Federal irrigation project for the Applegate River valley. Local interests have furnished all local cooperation specified by the 1970 Flood Control Act. The assurances were approved by the Secretary of the Army on May 8, 1975. Operations during fiscal year. New work: Miscellaneous contracts for minor roadway ditch cleanup and roadway repair begun in FY 1984 are now complete. Maintenance: Normal operation and maintenance was performed. Freshets regulated by Applegate Lake on Applegate River and Rogue River are shown in Table 37-M. 32. BLUE RIVER LAKE, OR Location. On Blue River, a major tributary of McKenzie River, 1.8 miles above confluence of the two streams at the confluence of Quartz Creek and Blue River and about 42 miles easterly of Eugene, OR. Existing project. A gravel-fill embankment dam 1,329 feet long at crest including spillway and 319 feet above the lowest point of the general foundation. A concrete gravity chute-type spillway with two gates is located on left abutment. Outlet works are in left abutment. On left shore of reservoir an earth-and-gravel fill embankment, about 1,535 feet long and 70 feet high, closes a low saddle between Blue River and McKenzie River. Project controls runoff from drainage area of 88 square miles. Reservoir provides 85,000 acre-feet of usable flood control storage and is operated as a unit of coordinated reservoir system to protect Willamette River Valley and increase low waterflows for navigation and other purposes. Recreation facilities are provided by the U.S. Forest Service under a Memorandum of Agreement. Project is complete. Construction of dam and appurtenant works was initiated in May 1963 and operation for flood control was effective in October 1968. Settlement of claims was completed in May 1974. Eugene Water and Electric Board made an application in April 1982 for permit to install two small hydropower units at Blue River Lake project. They also made an application in 1982 for permit to build a dam with two hydropower units, called Sunnyside Dam, between Foster and Green Peter project. Local cooperation. None required. Operations during fiscal year. Maintenance: Normal operation and maintenance work performed. Freshets regulated by Blue River Lake project on Blue River, a major tributary of McKenzie River, are shown in Table 37-M. 33. COTTAGE GROVE LAKE, OR Location. On Coast Fork of Willamette River, 29 miles from mouth. Coast Fork rises in Douglas County, OR, on western slope of Cascade Range and northern slope of Calapooia Range, flows north for 49 miles, and unites with Middle Fork to form main Willamette River. Existing project. An earthfill dam, 1,750 feet long at crest, 114 feet high from lowest point of the general foundation, a concrete gravity free overflow spillway 264 feet long near the right abutment, and a concrete gravity nonoverflow section 96 feet long forming the right abutment. 'Tobtal length of dam is 2,110 feet. Outlet works, consisting of three gate-controlled conduits, pass through spillway section. Reservoir provides 30,060 acre-feet of usable flood control storage and controls runoff of drainage area of 104 square miles. Project is operated as a unit of coordinated reservoir system to protect Willamette River Valley and increase low waterflow for navigation and for other purposes. Recreational development consists of day use and overnight facilities at four sites operated by the Corps of Engineers. Construction of project initiated August 1940 was completed April 1952. Dam and reservoir have been in continuous operation since September 1942. Local cooperation. None required. No cost-sharing sponsor for recreation facilities has expressed an interest in this project. Operations during fiscal year. Maintenance: Normal operation and maintenance work performed. Freshets regulated by Cottage Grove Lake on Coast Fork Willamette River are shown in Table 37-M. 37-13 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 34. DORENA LAKE, OR Location. On Row River, OR, 7 miles from mouth. Row River rises in Lane County on western slope of Cascade Range, flows northwest for 19 miles, and enters Coast Fork of Willamette River 19.5 miles above mouth. Existing project. An earthfill embankment dam, 3,352 feet long at crest and 145 feet high from lowest point of the general foundation. Concrete gravity free-overflow spillway, 200 feet long, forms right abutment. Outlet works on five slide-gate-controlled conduits pass through spillway section. Reservoir provides 70,500 acre-feet of usable flood control storage and controls runoff of 265 square miles, practically entire drainage area tributary to Row River. Project is.operated as a unit of coordinated reservoir system to protect Willamette River Valley and increase low waterflows for navigation and other purposes. Construction of project initiated June 1941 was completed October 1952 except for construction of additional recreation facilities that were funded under the Code 710 program. Future recreation facility construction will be accomplished in accordance with the cost-sharing contract with Lane County, OR. Dam and reservoir have been in continuous operation since November 1949. Local cooperation. Lane County Parks is participating in a multiple project cost-sharing (50 percent) contract for many of the existing parks at four projects; therefore, future recreation development at Dorena Lake will require 50 percent contribution by Lane County and is subject to funding availability by the government and Lane County. Operations during fiscal year. Maintenance: Normal operation and maintenance work performed. Freshets regulated by Dorena Lake project on Row and Coast Fork Willamette Rivers are shown in Table 37-M 35 ELK CREEK LAKE, ROGUE RIVER BASIN, OR Location. In Jackson County, OR at River Mile 1.7 on Elk Creek, a tributary of Rogue River, about 26.5 miles northerly from Medford, OR. Existing project. Design work continues to provide for a 249-foot high roller compacted concrete gravity dam, 2,600 feet long at the crest, with a gate controlled concrete chute spillway, regulating outlet conduits, power penstock and multiple use intake tower attached to the upstream face of the dam. Reservoir 6.2 miles long will provide 95,000 acre-feet of usable storage for flood control and water conservation utilization. Project will control runoff from a drainage area of 135 square miles. Reservoir will be operated to provide future municipal and industrial water supply, irrigation, fish and wildlife enhancement, water quality control, and recreation benefits. Construction of the project was initiated in February 1971. Work completed to date includes construction of a bypass road to route traffic away from the damsite and stockpiling of gravels to be used in the main dam and relocated roads. All lands for the project have been acquired with the exception of the cleaning of water rights for a seemingly abandoned irrigation canal which originates within the project boundaries. Final environmental statement was filed with Council of Environmental Quality June 15, 1972 and Supplement No. 1 addressing water quality and social/demographic information was filed with EPA on December 24, 1980. Estimated Federal cost of project is $117,000,000. Local cooperation. Authorizing act requires that State of Oregon take action prior to construction to insure maintenance in stream of flow to be released for fishery. In addition, costs allocated to irrigation would have to be repaid in a manner and to an extent consistent with the U.S. Bureau of Reclamation laws and policies. On February 24, 1966, State of Oregon Water Resources Board filed for withdrawal rights of 25 cfs to maintain minimum flow for fish. Operations during fiscal year. New work: Relocated county roadwork was initiated. 36. FALL CREEK LAKE, OR Location. On Fall Creek, a tributary of Middle Fork Willamette River, about 7 miles above confluence of the streams and about 19 miles southeasterly of Eugene, OR. Existing project. An earth-and-gravel fill embankment about 5,100 feet long at crest and 193 feet high from lowest point of the general foundation. A gated concrete gravity spillway is in left abutment. Outlet is in right abutment. Reservoir provides 115,000 acre-feet of usable flood control storage and is operated as a unit of coordinated reservoir system to protect Willamette River Valley and increase low waterflows for navigation and other purposes. Construction of project began May 1962 and was essentially complete November 1965. Reservoir storage for flood control was effective October 1965. Sky Camp Lodge was completed October 1978. Future recreation facilities will be provided in accordance with the cost-sharing contracts with Lane County and Bethel School District. Local cooperation. Lane County Parks is participating in a multiple project cost-sharing (50 percent) contract for many of the existing 'arks at four projects, including Fall Creek Lake. Operations during fiscal year. Maintenance: Normal operation and maintenance work performed. Freshets regulated by Fall Creek Lake project on Fall Creek, a tributary of Middle Fork, Willamette River, are shown in Table 37-M. 37. FERN RIDGE LAKE, OR Location. On Long Tom River, 23.6 miles from the mouth. Long Tom River rises in Lane County, OR, on eastern slope of Coast Range, flows north for 50 miles, and enters Willamette River 147 miles above its mouth. Existing project. A main dam, 6,624 feet long at crest and 49 feet high from lowest point of the general foundation and two auxiliary dikes, 915 and 3,929 feet long, along northeasterly boundary of lake. Main dam consists of an earthfill embankment dam 6,330 feet long, a concrete gravity spillway near left abutment with a nonoverflow structure 46 feet long, containing outlet works, 37-14 PORTLAND, OREGON DISTRICT and an overflow structure, 248 feet long, controlled by six automatic gates. Project includes rectification of channel of Long ITom River downstream of dam. Reservoir provides 110,000 acre-feet of usable flood control storage and controls runoff of tributary drainage area of 275 square miles. Reservoir protects Long ITom River Valley and is operated as a unit of coordinated reservoir system to protect Willamette River Valley generally and to increase low water-flows for navigation and other purposes. Dam was originally constructed in 1941 to height of 47 feet. Provision of additional storage for flood control was obtained in 1965 by raising embankments 2 feet to 49 feet above.- lowest point of the general foundation. Construction of project initiated April 1940 was completed August 1951, except for provision of additional storage for flood control authorized in 1962 and completed April 1965, and construction of additional recreation facilities funded through the Code 710 program. Dam and reservoir have been in continuous operation since December 1941. Development of future recreation facilities will be in accordance with the cost-sharing contract with Lane County, and requires a 50 percent contribution by the county. Development is subject to availability of funds by the Government and the county. Local cooperation. Lane County currently provides operation and maintenance at three parks at Fern Ridge Lake and is participating in a multiple project costsharing (50 percent) contract for many of the existing parks at four projects, including Fern Ridge Lake. Operations during fiscal year. Maintenance: Normal operation and maintenance work performed. Freshets regulated by Fern Ridge Lake project on Long Tom River are shown in Table 37-M. 38. HUNTINGTON AVENUE, CASTLE ROCK, WA Location. On the left bank of the Cowlitz River at River Mile 15.9 in Castle Rock, Cowlitz County, WA. Existing project. Work was authorized under the special continuing authority contained in Section 14 of the 1946 Flood Control Act. This authority allows construction of emergency bank protection to prevent flood damages to public works. Riprap erosion protection along 550 linear feet of bankline was constructed to protect Huntington Avenue, a road that passes through the City of Castle Rock and provides connection at two locations with Interstate Highway 5. Local cooperation. The project sponsor, City of Castle Rock, provided construction easements and rights-ofway and made necessary utility relocations. The City also agreed to hold the United States free from damages and maintain and operate the completed bank protection works. Operations during fiscal year. New work: Fiscal requirements were finalized. 39. FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION Flood control activities pursuant to Section 205, Public Law 858, 80th Cong., as amended (preauthorization). See Table 37-L. Emergency bank protection (Section 14 of 1946 Flood Control Act, Public Law 526, 79th Cong.). Fiscal year costs for preauthorization studies were: Pudding River, Anderson Road, OR, $2,314. Emergency flood control activities-repair, flood fighting and rescue work (Public Law 99, 84th Congress and antecedent legislation). Federal costs for fiscal year were: $237,321, disaster preparedness; $67,829, emergency operations; $60,549, rehabilitation; $12,262,352, advance measures. Contributed funds for levee raising were $35,918. Mt. St. Helens Emergency Measures. The May 18, 1980 eruption of Mt. St. Helens dramatically altered the hydraulic and hydrologic regimes of the Cowlitz and Toutle River valleys. Volcanic debris substantially reduced the river's hydraulic capacity to the point where major flooding could be expected with even normal runoff. A major recovery program for the Cowlitz and Toutle Rivers funded under advance measures was initiated a short time after the eruption and was essentially completed during FY 1982. Total cost of Mt. St. Helens emergency measures, from initiation through FY 1985, with some contract modifications remaining to be negotiated, is $275,627,000. The authorized navigation channel on the Cowlitz between River Mile 0 and 4.2 remains unusable due to continued sedimentation. Spirit Lake, WA. Portland District was directed on August 24, 1982 to respond to the Presidential declaration of a State of Emergency for the Spirit Lake area. This declaration was precipitated by the release of a U.S. Forest Service Spirit Lake Interagency Task Force report assessing the flood hazard posed by that body of water, which has been without a natural outlet since the May 18, 1980 eruption of Mt. St. Helens. The report concluded that Spirit Lake would fill to an extremely dangerous level by as early as Spring 1983 and also mentioned concern over the structural stability of the debris plug holding back the lake due to the development of an extensive system of deep erosion gullies on its surface, some as deep as 40 feet. iTo contain the threat of a possible devastating flood caused by a failure of the Spirit Lake debris plug, and in response to a tasking from the Federal Emergency Management Agency (FEMA), the Portland District initiated a program aimed at meeting two objectives: (a) undertake interim measures to assure that the lake is not allowed to continue rising unchecked so that the threat of a possible flood during 1983 is averted, and, (b) perform field investigations and preliminary design work necessary to make a recommendation to FEMA for a permanent solution to the threat of flooding from Spirit Lake. An interim solution was implemented to maintain the lake at a safe level through pumping water from the lake from October to July each year. A comprehensive plan for long-term flood control and navigation maintenance, as a result of the Mt. St. Helens eruption, was completed in 1983. This document included 37-15 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 alternative methods of eliminating the threat of catastrophic flooding due to the unstable avalanche debris dam at Spirit Lake. A decision document selecting the final plan for responding to this threat was completed in February 1984. This plan called for the construction of an 8,500-foot-long tunnel through Harry's Ridge to permanently drain Spirit Lake into South Coldwater Creek. Until the tunnel was completed in April 1985, the lake elevation was maintained through pumping from bargemounted pumping plant at Spirit Lake. Pumping was discontinued on April 1, 1985. A contract was initiated in August 1985 to restore the pumping area to a natural condition. The total cost for pumping and pump site restoration through FY 85 is $11,625,000. Construction of the tunnel began in June 1984. The tunnel was completed in April 1985, and the four-month long drawdown of Spirit Lake begain in May 1985. The cost for tunnel construction through FY 85 is $13,660,000. 40. INSPECTION OF COMPLETED FLOOD CONTROL PROJECTS Funds appropriated for inspection of completed local flood protection works are used to determine maintenance condition of completed works and to ascertain whether those works are being properly maintained by local interests. A total of 60 leveed areas and 268 bank protection works were inspected at various locations along both banks of Lower Columbia River below Bonneville Dam, along Oregon Coast, in eastern Oregon, in southern Oregon and in Willamette River Basin. Of this total, 15 leveed areas in Oregon and 45 leveed areas in Washington were inspected during FY 1984. A representative of sponsoring districts accompanied the Portland District representatives performing the levee inspections. Aerial inspection of revetments in Willamette River Basin was supplemented by an onsite inspection at locations requiring maintenance. Deficiencies in maintenance and need for repairs were discussed with sponsoring districts' representatives and a report was made to each sponsor with recommendations for improving maintenance. The program to improve maintenance of completed Federal projects initiated by House Appropriations Committee on Civil Functions was continued. Periodic contact was maintained with uncooperative areas reported in FY 1983 to ascertain any change in attitude and to provide technical assistance, if requested. Of the 81 sponsors for some 125 local flood protection projects inspected in Portland District, 8 were reported deficient in maintenance. Fiscal year costs were $101,104 and total costs to September 30, 1985 were $1,150,977. 41. INSPECTION OF COMPLETED PI99 WORKS Annual inspections are made of levees, flood control structures, and communities that have received previous assistance under the various features of Public Law 84-99 (flood fights, levee rehabilitation, advance measures). Inspections involve determining physical condition of levees and other structures, riprap displacement and vegetation control. Inspections also serve a valuable disaster preparedness function in terms of explaining to local interests their preparedness responsibilities and criteria for qualifying for future emergency assistance under PL 84-99. Local sponsors are advised of results of inspections. Approximately 60 locations throughout the Portland District were inspected under this feature during FY 1985, at a cost of $83,408. 42. JOHN DAY RIVER (WEST), OR Location. Left bank of John Day River Road location, on the left bank of John Day River (West) mile 2.3, approximately 4 miles west of Astoria, OR. Work would be accomplished under the authority of Section 14 of the 1946 Flood Control Act, as amended. Existing Project: Plan of improvement provides protection for 776 linear feet of bankline from erosion at John Day River Road location with quarry stone embankment. A layer of filter fabric will be placed on the damaged bank to provide support for the stone. Local cooperation. Fully complied with. Operations during fiscal year. New work: All work was completed in FY 1985. 43. LOWER COLUMBIA RIVER BASIN, OR AND WA Location. On Columbia River and minor tributaries, channels, and sloughs, between Sandy River, OR, about 15 miles east of Vancouver, WA, and mouth of Columbia River. Existing project. Plan for bank protection work, improvements to existing projects, and construction of flood control works in Lower Columbia River Basin provides for new construction and supplementing and extending projects constructed in Lower Columbia River Basin under authority of 1936 Flood Control Act: (a) Lower Columbia River Bank Protection, OR and WA provides for bank protection works at 96 locations on Columbia River and tributaries between Sandy River and mouth of Columbia River, totaling about 224,000 linear feet. Estimated total Federal cost is $25,400,000 and non-Federal cost is $267,000; (b) See Thble 37-N on Levees and Improvements to Existing Works; (c) Lower Columbia River Basin levees at new locations, Oregon and Washington, provides for construction of flood control works at: Washougal area, Clark County, WA, about 5.5 miles of levee and appurtenant works at a Federal cost of $1,803,488, and non- Federal cost at $98,000; and Vancouver Lake area in vicinity of Vancouver, WA, about 18 miles of levee and appurtenant works at an estimated Federal cost (1980) of $19,500,000 and non-Federal cost at $900,000. This portion, Vancouver Lake, WA, has been reclassified "deferred". Total estimated Federal costs (1980) for both areas of work are $21,303,488 and non-Federal costs $998,000. Federal cost for all work under project, Lower Columbia River Basin, OR, and WA, is $67,461,776. Construction of improvement to existing project in Sandy Drainage District, OR, was completed by local interests at no construction cost to the Government. Improvements of levees have been accomplished by contract at the following 37-16 PORTLAND, OREGON DISTRICT locations: Multnomah County Drainage District, No. 1, OR, June 1962; Sauvie Island Drainage District, OR, October 1962; Woodson Drainage District, OR, December 1963; Rainier Drainage District, OR, June 1964; Cowlitz County Diking Improvement District, No. 15, WA, December 1965; Cowlitz County Diking Improvement Districts, Nos. 2 and 13, WA, June 1965; Midland Drainage District, OR, April 1967; Cowlitz County Consolidated Diking Improvement District, No. 2, WA, June 1974; Beaver Drainage District, OR, June 1978; Wahkiakum County Consolidated Diking District #1, WA, October 1979; and Scappoose Drainage District, OR, September 1980. Washougal Area, WA, (new location) levee construction has been completed. Under authorization for Lower Columbia River Basin bank protection works, construction has been completed at numerous locations. (See Section 44 for additional information). Local cooperation. Flood Control act of 1950 provides local interests furnish lands and rights-of-way; make necessary highway, highway bridge, and utility alterations; hold the United States free from damages; and maintain and operate completed works. ToIbtal non-Federal costs for all work are $4,565,000. For details of status or requirements of local cooperation see individual project reports. Operations during fiscal year. See individual projects. 44. LOWER COLUMBIA RIVER BASIN BANK PROTECTION, OR AND WA Location. On Columbia River and tributaries between Sandy River, OR, and mouth of Columbia River. Existing project. Provides for construction of 224,000 linear feet of bank protection works at 96 locations along Lower Columbia River below River Mile 125 and along principal tributaries in this reach, to protect existing improvements such as levees and developed industrial lands from further erosion. Existing project is a unit of general comprehensive plan for flood control, navigation, and other purposes in Columbia River Basin. Construction of project began in July 1961 and is 84 percent complete. A total of 186,684 linear feet of bank protection work at 81 locations has been completed. Estimated Federal cost is $25,400,000. Local cooperation. Flood Control Act of 1950 provides local interests furnish lands and rights-of-way; make necessary highway, highway bridge, and utility alterations; hold the United States free from damages; and maintain and operate works after completion. Estimated costs for all requirements of local cooperation are $267,000. Operations during fiscal year. New work: Gillnet, Rusty Bumper, Waris, and Elander locations were completed. Construction of Tansy Railroad location near the cities of Hammond and Warrenton, OR was initiated. This will provide 3840 linear feet of protection and is scheduled to be completed by March 1986. 45. MCDONALD DIKE ROAD, NEHALEM RIVER, OR Location. On the right bank of the Nehalem River at River Mile 3.5, along McDonald County Road, in Tillamook County, OR. Existing project. Work was authorized under the special continuing authority contained in Section 14 of the 1946 Flood Control Act. This authority allows construction of emergency bank protection to prevent flood damages to public works. Riprap erosion protection consisting of 780 cubic yards of graded quarry rock along 85 linear feet of bankline was constructed to protect McDonald County Road, a county roadway that provides a local cross road connection between State Highway 53 and North Fork Road. Local cooperation. The project sponsor, Tillamook County, provided construction easements and rights-ofway and made necessary utility relocations. The County also agreed to hold the United States free from damages and maintain and operate the completed bank protection works. Operations during fiscal year. New work: Fiscal requirements were finalized. 46. MOUNT ST. HELENS & VICINITY, WA Location. Along the Cowlitz and Toutle Rivers from Spirit Lake at the base of Mt. St. Helens to the confluence of the Cowlitz with the Columbia River (River Mile 68) approximately 55 miles downstream from Portland, OR. Existing project. The May 18, 1980 eruption of Mt. St. Helens dramatically altered the hydraulic and hydrologic regimes of the Cowlitz and Toutle River valley. Mudflows triggered by the eruption carried large volumes of sediment from the debris avalanche into these river valleys, reducing the hydraulic capacity to the point where major flooding could be expected with even normal runoff. Storm runoff and surface dredging continue to deliver sediment from the debris avalanche into the rivers. Funds allocated under Public Law 84-99 were used for major recovery work on the Cowlitz and Toutle rivers. In late FY 1983, interim flood control measures were implemented under the authority of Public Law 98-63 to assure 100-year flood protection to developed areas along the Cowlitz River. Measures implemented are primarily dredging on the Cowlitz and Toutle Rivers and a monitoring program. Local cooperation. Local sponsors will be requested to obtain any additional lands easements and rights-ofway. The State of Washington has agreed to act as the local sponsor. State funds have been appropriated for acquisition of lands and related expenses for Mt. St. Helens recovery operations. The State of Washington has spent over $2,500,000 to procure disposal sites for dredged material. Operations during fiscal year. New work: From December 1984 through April 1985, 1.9 million cubic yards of sediment were removed at the LT-1 site on the 'lbutle River. The contract was resumed in July 1985, after 37-17 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 the fish passage season, to remove a total of 2.6 million cubic yards for the contract. Cost for LT-1 dredging in FY 85 was $4,106,400. A contract to remove 4.3 million cubic yards of sediment from the LT-3 site on the Toutle River was awarded in late September 1985. 47. SALMON CREEK, NEAR VANCOUVER, WA Location. On the left bank of Salmon Creek at River Mile 6.0 in Clark County, WA. Existing Project. Work was authorized under the special continuing authority contained in Section 14 of the 1946 Flood Control Act. This authority allows construction of emergency bank protection to prevent flood damages to public works. Protection consists of a 23-foothigh binwall, 379 feet in length, backfilled with granular material. Riprap is to be placed at the upstream and downstream ends of the binwalls. This work protects N.E. 117th Avenue which serves as primary access to State Highway 99 and Salmon Greenway Park. Local cooperation. The project sponsor, Clark County, provided construction easements and rights-of-way and made necessary utility relocations. The County also agreed to hold the United States free from damages to maintain and operate the completed bank protection works, and contributed $185,000 towards construction. In addition, the County will lower the grade of 117th Avenue an average of six feet over a length of approximately 700 feet and will install a corrosion protection system for the binwall during the construction season. Operations during fiscal year. New work: Fiscal requirements were finalized. 48. SCHEDULING FLOOD CONTROL RESERVOIR OPERATIONS Corps of Engineers monitored flood control operations at four Bureau of Reclamation projects (Prineville, Ochoco, Emigrant, and Scoggins) and (Mossyrock) a municipal power project operated by Tacoma City Light. The Bureau of Reclamation projects were partially constructed with flood control funds, thereby subjecting project operation to monitoring by the Corps of Engineers under Section 7, Flood Control Act of 1944. Monitoring of Mossyrock flood control operation is assigned to the Corps by the Federal Energy Regulatory Commission as the Mossyrock license calls for specific flood control regulation. Under licensing agreement, the Tacoma City Light utility is required to provide 360,000 acre-feet of flood storage by December of each year. The Bureau of Reclamation sponsored projects were operated satisfactorily during FY 1985 for flood control. At Mossyrock there was one high water period in June 1985. During this period reservoir regulation stored approximately 190,000 acre-feet at Mossyrock. Peak discharges at Castle Rock were well below the regulation goal of 70,000 cubic feet per second during the flood season. Unregulated flows would have also been below the 70,000 cubic feet per second goal. The spring snowmelt runoff was much above normal with very little precipitation during October through December period. Preparation of Reservoir Regulation Manuals for Scoggins and Mossyrock Projects is scheduled. Total cost of monitoring the five projects during FY 1985 was $5,079. 49. STATE HIGHWAY 101 AND 401, COLUMBIA RIVER, WA Location. On the right bank of the Columbia River at river Mile 15.0, along Washington State Route 401 in Pacific County, WA. Existing Project. Work was authorized under the special continuing authority contained in Section 14 of the 1946 Flood Control Act. This authority allows construction of emergency bank protection to prevent flood damages to public works. Riprap erosion protection along 1,450 linear feet of bankline was constructed to protect Washington State Route 401, a principal traffic route for southwestern Washington, including travel along the Washington and Oregon coasts. Local cooperation. The project sponsor, the Washington State Department of Transportation, provided construction easements and rights-of.way and made necessary utility relocations. The State also agreed to hold the United States free from damages and maintain and operate the completed bank protection works. In addition, the State contributed $254,642 for construction. Operations during fiscal year. New work: Work was completed and fiscal requirement were finalized. 50. TUALATIN, OR Location. Tualatin River channel between river mile 7.6 and 8.8 above the confluence with the Willamette River. Project is located in the city of Tualatin. Existing project. Provides channel improvements to reduce potential flood damage in the river basin. Major flood damage is concentrated in the city of Tualatin. Reduction of potential flood damage results from removal of channel constructions in the project area by increasing channel capacity. The city's core area lies in a high water secondary channel which floods when the river surfaces rises above 120 feet NGVD (National Geodetic Vertical Datum). The project will improve channel capacity and exceeding 120 feet NGVD would then average once in 13 years through the project area. Local cooperation. Fully complied with. City of Tualatin is project sponsor. Operations during fiscal year. New work: Contract claims were settled and final fiscal requirement completed. 51. UMATILLA RIVER, THORN HOLLOW, OR Location. On the left bank of the Umatilla River at River Mile 76.4 on the Umatilla Indian Reservation about 20 miles east-northeast of Pendleton in Umatilla County, OR. Existing project. Work was authorized under the special continuing authority contained in Section 14 of the 1946 Flood Control Act. This authority allows 37-18 PORTLAND, OREGON DISTRICT construction of emergency bank protection to prevent flood damages to public works. Riprap erosion protection along 826 linear feet of bankline was constructed to protect a City of Pendleton waterline. Local cooperation. The project sponsor, City of Pendleton, provided construction easements and rightsof- way and made necessary utility relocations. The City also agreed to hold the United States free from damages and maintain and operate the completed bank protection works. Operations during fiscal year. New work: Work was completed and fiscal requirements were finalized. 52. WAHKIAKUM COUNTY CONSOLIDATED DIKING DISTRICT NO. 1, WA Location. District occupies both Puget and Little Islands in Columbia River between River Miles 38.4 and 45.0. These islands are in Wahkiakum County, WA, near town of Cathlamet. Existing project. Provides for raising and strengthening existing levees, removing several abandoned tide boxes, constructing a new tide box, extending and existing tide box and adding a gate well structure, constructing a new pumping station and relocating three existing pumping stations; raising the discharge lines of all pumping stations; and filling borrow ditches along the landward levee toe. Construction of new tide box was completed January 1976. Replacement of three pump stations and one tide box and addition of one pumphouse is complete. Final EIS filed September 18, 1972. Local cooperation. Flood Control Act of 1950 provides local interests furnish lands and rights-of-way; make necessary highway, highway bridge, and utility alterations; hold the United States free from damages; and maintain and operate completed works. Operations during fiscal year. New work: Final fiscal requirements were completed. 53. WEST MAKINSTER ROAD, WILSON RIVER, OR Location. West Makinster location, on the left bank of Wilson River, mile 1, about 2 miles north-northwest of Tillamook, Tillamook County, OR. Work would be accomplished under authority of Section 14 of the 1946 Flood Control Act, as amended. Existing project. Plan of improvement called for approximately 8,400 cubic yards of quarry stone to be placed over a total of 960 linear feet of bankline to correct the erosion problem. A ground stabilizing fabric was placed on the damaged bank to provide support for the stone. Local cooperation. Fully complied with. Operations during fiscal year. New work: Construction began in FY 1985 and was completed the same year. 54. WILLAMETTE RIVER BASIN, OR Location. Willamette River, formed by Coast and Middle Forks which join a few miles above Eugene, OR, flows north 189 miles, and enters Columbia River 101.5 miles above its mouth. The basin has an area of 11,200 square miles and lies between Cascade Range on the east and Coast Range on the west. Major tributaries of Willamette River rise in Cascade Mountains and consist of Coast and Middle Forks and McKenzie, Calapooia, Santiam, Molalla, and Clackamas Rivers. Important tributaries that head in the Coast Range are Luckiamute, Yamhill, and Tualatin Rivers. Minor tributaries, all of which enter the main stream from the west, are Long Tom River, Marys River, and Rickreall Creek. Existing project. Flood Control Act of 1938 approved general comprehensive plan for flood control, navigation, and other purposes in Willamette River Basin and authorized funds for initiation and partial accomplishment of plan recommended for initial development: the reservoirs and related works to be selected by Chief of Engineers. Subsequent Flood Control Acts, 1941 through 1974, authorized additional flood control and other works and increased monetary authority. Following projects were completed as authorized and are in continuous operation: Fern Ridge Lake, August 1951; Cottage Grove Lake, April 1952; Dorena Lake, October 1952; Detroit Lake, December 1960; Lookout Point Lake, June 1961; Hills Creek Lake, June 1963; Cougar Lake, March 1964; Fall Creek Lake, November 1965; Green Peter-Foster Lakes; June-December 1967 respectively; and Blue River Lake, October 1968. Under the authorization for construction of recreation facilities at completed projects, work has been accomplished at Fern Ridge, Cottage Grove, Dorena, Lookout Point, and Fall Creek Lakes. Under the memoranda of agreements with the U.S. Forest Service, recreation facilities also have been constructed at Detroit, Lookout Point, Cougar, Blue River, and Hills Creek Lakes. Recreational facilities were constructed at Green Peter-Foster Lakes with initial construction funds. Details of operation, construction, and financial status of projects are in individual reports. During low-water season, July-September, supplemental water releases are made from Willamette River Basin Reservoirs. Uses which benefit from increased downstream flows include irrigation, navigation, power, fisheries, pollution abatement, and recreation. Although optimum regulation cannot be provided for every purpose, water released from reservoirs during the low-water season for a particular purpose will usually provide benefits to other uses as well. Basic policy is to provide most beneficial overall regulation, consistent with established water-use priorities. (See Table 37-0 on Willamette River Basin comprehensive plan.) Local cooperation. Section 2, Flood Control Act of June 28, 1938 applies. Local cooperation for other projects is in individual reports for those projects. Operations during fiscal year. See individual reports. 55. WILLAMETTE RIVER BASIN BANK PROTECTION, OR Location. On Willamette River and tributaries, between Cascade Range and Coast Range, from a point south of Eugene to Portland, OR. 37-19 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Existing project. Provides for clearing, sloping, and reveting riverbanks; construction of pile and timber bulkheads and drift barriers; minor channel improvements; and maintenance of existing works for control of floods and prevention of erosion at various locations along Willamette River and its tributaries. The current scope of the project is a total of 510,000 linear feet of bank protection at 236 locations. Estimated Federal cost is $31,400,000. Construction of project began in 1938 and is 96 percent complete. A total of 489,795 linear feet of bank protection work at 230 locations consisting of revetment of riverbanks, pile and timber bulkheads, drift barriers, and channel improvements, have been completed on Willamette River and tributaries. Local cooperation. Section 3, Flood Control Act of 1936 applies. Estimated costs for all requirements of local cooperation under terms of project authorization were $377,000. Operations during fiscal year. New work: A total of 3,650 linear feet of riprap revetment bank protection has been constructed at Minto-Brown location. Maintenance: Annual inspection of revetments was made by helicopter in July 1985. 56. WILLOW CREEK LAKE, HEPPNER, OR Location. On Willow Creek immediately upstream from Heppner and just downstream fron junction of Balm Fork and Willow Creek in Section 35, Township 2 South, Range 26 East, Willamette Meridian. Existing project. Project provides flood protection to the city of Heppner and downstream area by controlling runoff from a drainage area of 96 square miles. The dam is a roller compacted concrete structure 160 feet high at crest elevation 2,130. Ancillary features include a center uncontrolled spillway with a maximum flood capacity of 93,300 cfs, an outlet works with a capacity of 500 cfs, a minor flow works and diversion works. Gross storage capacity of the project is 13,250 acre-feet, consisting of 7,750 acre-feet for exclusive flood control, 1,750 acre-feet for joint flood control and irrigation, 1,750 acre-feet exclusive irrigation, and 2,000 acre-feet dead storage for fish, wildlife, recreation, sediment accumulation, and aesthetics. Limited recreation facilities are being provided. The final Environmental Impact Statement was filed with the Environmental Protection Agency on December 20, 1979. The provision of the Clean Water Act were met by a Section 404(bX1) Evaluation and a public notice issued January 12, 1980, and a Section 401 certification from the State of Oregon on February 15, 1980. Land acquisition is about 99 percent complete. Contracts have been completed for relocation of the city water main, and construction of the water tank, road, and main dam. Local cooperation. None required. Operations during fiscal year. New work: (See Walla Walla, WA District Annual Report.) Maintenance: Normal operation and maintenance performed. Multiple-Purpose Projects, Including Power 57. BONNEVILLE LOCK AND DAM-LAKE BONNEVILLE, OR AND WA Location. Project is on Columbia River, 40 miles east of Portland, OR, about 146 miles above mouth of river. For description of Columbia River see Section 4. Existing project. A dam, powerplant, and lock for power and navigation. Spillway dam extends across main channel from Washington shore to Bradford Island, which divides the river at this point. Overflow crest at 24 feet above mean sea level is surmounted by 18 vertical-lift steel gates and 10 remote control main dam hoists placed between piers which extend to elevation 99 feet where a service roadway permits operation of two 350-ton gantry cranes for regulating gates. Powerhouse No. 1 extending across Bradford Slough to the Oregon shore has an installation of 10 units, consisting of two units of 43,200 kilowatts and eight units of 54,000 kilowatts each, totaling 518,400 kilowatts. Ordinary and extreme fluctuations of river at lower lock gate are about 21 and 47 feet respectively. Project includes fish ladders and locks to serve both main channel and Bradford Slough channel. Navigation lock and powerhouse are founded on andesite, and main dam rests upon solidified sedimentary rock of volcanic origin. The pool created by dam provides a navigable channel 15 feet deep between Bonneville and The Dalles Dams, a distance of 47 river miles. Principal data concerning navigation lock spillway dam, and powerplant are set forth in Table 37-P. Dam, navigation lock, 10-unit power generating installation, fishways, and attendant buildings and grounds cost $83,239,395, of which $6,072,480 is for navigation facilities, $39,350,824 for power facilities and $37,816,091 for joint facilities, consisting of dam, fishways, buildings and grounds, and headwall section of power units 0 to 6, cost of which $2,106,000 is allocated to dam and lake facilities. In response to flow regulations and peakings from upstream plants operating under conditions of Canadian storage and Pacific Northwest - Southwest Intertie, two modifications were undertaken at the Bonneville project. The modification for peaking project was undertaken to minimize adverse environmental effects under rapidly changing flow conditions from upstream dams. The project was completed in 1978 at a cost of $27,195,000. The second modification provides for increased power installation by building a second powerhouse located on the Washington shore adjacent to the end of the existing spillway. The new powerhouse contains eight units of 66,500 kilowatts each and two fish turbine generator units of 13,100 kilowatts each for a combined capacity of 558,200 kilowatts, bringing the entire Bonneville capacity to 1,076.6 megawatts. Additional fish facilities consist of the powerhouse collection system, second fish ladder on the Washington shore, transportation channel connecting existing Washington shore fish ladder with new exit control section, and fingerling bypass facilities which include fish screens in both the powerhouses. To provide for the 37-20 PORTLAND, OREGON DISTRICT anticipated increased visitor use, onsite visitor facilities are included. Under authority of the Bonneville Project Act (August 20, 1937), a letter from Bonneville Power Administration to North Pacific Division dated January 21, 1965, requested construction of a second powerhouse. Construction of project started October 1933, was completed February 1953. Modification of powerhouse control equipment started March 1957, was completed September 1958. First two power units were placed in operation during fiscal year 1938. Powerhouse with complete installation of 10 units, was in operation December 1943. Construction of modification for peaking work commenced in September 1970 and was completed in September 1978. Construction of second powerhouse is near completion. Final environmental impact statement was filed with Council on Environmental Quality in April 1972. In response to increasing visitation which now exceeds 800,000 a year at the dam site itself and 1,500,000 projectwide, a visitor center with windows into the fish ladders, a 60-seat theatre, exhibits and displays was completed in 1975. Contracts for relocation of the highway, railroad and town of North Bonneville are 99 percent complete. Construction of the main powerhouse and supply contracts for associated powerhouse equipment are 99 percent complete and Units 11 through 18 were on-line by October, 1982. The visitor facility for the new powerhouse (which does not require cost-sharing) is an integral part of that structure. Estimated cost for construction of second powerhouse is $646,000,000. Construction of future recreational facilities is contingent upon a cost-sharing contract with a non-Federal sponsor. Skamania County, WA has indicated an interest in cost-sharing at Home Valley upstream from Bonneville Lock and Dam and a cost-sharing contract is presently being negotiated. Through September 1985 power generation totaled 185.2 billion kilowatt-hours. Of the gross income from sale of this power by Bonneville Power Administration, $225,399,927 was reimbursed to the U.S. Treasury to recover Corps of Engineers project investment and operating costs. Local cooperation. None required, except for non- Federal cost-sharing for development of recreational facilities. Operations during fiscal year. New work: Construction continued on restoration of areas disturbed by powerhouse construction. Final stages of the juvenile bypass system and monitoring facilities were under construction. Correction of deficiencies in fish guidance efficiency at the Second Powerhouse will reduce fingerling mortality incurred during annual downstream migration. Maintenance: The modernization program continued to be implemented. Normal operation and maintenance was performed during period. During the fiscal year 5,434,005,000 kilowatt-hours of electrical power energy were generated, of which 5,410,257,000 kilowatt-hours were delivered to Bonneville Power Administration, the marketing agency. Traffic through the navigation lock consisting of rafted logs, petroleum products, grains, and miscellaneous cargo amounted to 9,281,775 tons during calendar year 1984. 58. COUGAR LAKE, OR Location. At mile 4.4 on South Fork McKenzie River which joins McKenzie River about 56.5 miles above its confluence with Willamette River. Project is about 42 miles east of Eugene, OR. Existing project. A rockfill dam with an impervious earth core, about 1,738 feet long at crest and 445 feet high above the streambed. Reservoir is 6 miles long with storage capacity at full pool of 219,000 acre-feet and controls runoff of tributary drainage area of 210 square miles. Spillway is on right abutment and outlet and power tunnels in left abutment. Outlet tunnel is provided with a chute and stilling basin. Powerplant consists of two 12,500 kilowatt units with minimum provisions for installing a third unit of 35,000 kilowatts for future peaking capacity. Improvement functions as a unit in coordinated system of reservoirs for multiple-purpose development of water resources in Willamette River Basin. Recreation facilities are provided by the U.S. Forest Service. Also authorized (but unconstructed) is a reregulating dam, Strube Lake, below Cougar Lake, which would permit Cougar to operate as a peaking powerplant. The Strube dam would contain two units totalling 4,600 kilowatts. Construction of project initiated June 1956 is complete, excluding Strube Lake and Cougar Additional Unit for which planning is essentially complete. Also, plans and specifications for the first construction contract (relocations) have been completed. Generating units 1 and 2 were placed in commercial operation March 23 and February 4, 1964, respectively. Physical in-service date for flood control was November 29, 1963. Through September 1985 power generation totaled 2.9 billion kilowatt-hours. Of the gross income from sale of this power by Bonneville Power Administration, $14,521,461 was reimbursed to the U.S. Treasury to recover Corps of Engineers project investment and operating costs. Estimated Federal cost of Strube Lake and Cougar Additional Unit is $107,000,000. Local cooperation. None required. Operations during fiscal year. New work: Continuation of negotiations for the innovative financing of Strube Lake and Couger Additional Unit. Maintenance: Installation of a new alarm reporting system is increasing the ability to remotely operate the project from the Foster Powerhouse. Ordinary operation and maintenance continued. During fiscal year, 146,694,000 kilowatt-hours of electrical energy were generated at project, of which 145,931,000 kilowatt-hours were delivered to Bonneville Power Administration, the marketing agency. Freshets regulated by Cougar Lake on South Fork McKenzie River are shown on Table 37-M. 59. DETROIT LAKE, OR Location. On North Santiam River with dam 50 miles from mouth 45 miles southeast of Salem, OR. North Santiam River flows north and west for 85 miles, and unites 37-21 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 with South Santiam River to form Santiam River, which 10 miles downstream enters Willamette River 108 miles above its mouth. Existing project. One main dam and a reregulating dam, both with power-generating facilities. Detroit Dam is a concrete gravity structure about 1,522 feet long and 454 feet high from lowest point of the general foundation to roadway deck. Spillway is a gate-controlled overflow section, and outlet works are gate-controlled conduits through dam. Powerhouse with two units having a capacity of 50,000 kilowatts each is in right abutment immediately below dam. Reservoir has a storage capacity at full pool of 454,900 acre-feet and controls runoff of tributary drainage area of 438 square miles. It is being operated as a unit in coordinated reservoir system to protect Willamette Valley from floods, to increase low water flows in interest of navigation and irrigation, to generate power, and for other purposes. Reregulating dam 3 miles downstream at Big Cliff site is concrete gravity type, about 191 feet high from lowest point of the general foundation to roadway deck. Power installation consists of one unit with a capacity of 18,000 kilowatts. Reservoir has a storage capacity of 5,930 acre-feet at full pool. Project is a unit of tomprehensive plan for flood control and other purposes in Willamette Basin. Recreation facilities are provided by the U.S. Forest Service, Oregon State Park System and the town of Detroit. Construction of project begun in May 1947 was completed December 1960. The two powerhouse generating units were placed in commercial operation June and October 1953. At Big Cliff powerhouse, single generating unit was placed on-line June 1954. Use of Big Cliff Dam for reregulating fluctuating flow from Detroit units was effected October 1953. Through September 1985 power generation totaled 15.5 billion kilowatt-hours. Of the gross income from sale of this power by Bonneville Power Administration, $52,102,534 was reimbursed to the U.S. Treasury to recover Corps of Engineers project investment and operating costs. Local cooperation. None required. Operations during fiscal year. Maintenance: Installation of a new alarm reporting system is increasing the ability to remotely operate the project from the Foster Powerhouse. Ordinary operation and maintenance continued. During fiscal year 478,749 kilowatt-hours of electrical energy were generated at project of which 475,651 kilowatt-hours were delivered to Bonneville Power.Administration, the marketing agency. Freshets regulated by the Detroit Lake project on North Santiam River are shown in Table 37-M. 60. GREEN PETER-FOSTER LAKES, OR Location. At approximate mile 5.5 on Middle Santiam River which joins South Santiam River about 56.8 miles above its confluence with Willamette River. Dam is about 30 miles southeast of Albany in Linn County, OR. Existing project. One main dam and a reregulating dam, both with power-generating facilities. Green Peter Dam is a concrete gravity structure, 1,400 feet long and 385 feet high above the lowest point of the general foundation with a gate-controlled spillway. Outlet works consist of two conduits through spillway, discharging into a stilling basin. Powerplant, on right bank adjacent to spillway stilling basin, consists of two units with an installed capacity of 80,000 kilowatts. Reservoir provides storage capacity at full pool of 430,000 acre-feet, extending 6.5 miles up Quartzville Creek and some 7.5 miles up Middle Santiam River above creek junction, forming a Y-shaped pool. Reservoir controls runoff of tributary drainage area of 277 square miles. Foster Dam, 7 miles downstream from Green Peter Dam is located on South Santiam River about 38 miles above its confluence with Santiam River and 1.5 miles below its confluence with Middle Santiam River. Foster Dam consists of an earth, gravel, and rock-filled embankment, 146 feet high from lowest point of the general foundation and a concrete gravity gate-controlled spillway and stilling basin for a total length of 4,800 feet. Power installation consists of two units with a capacity of 20,000 kilowatts. Foster Lake has a storage capacity, at full pool, of 61,000 acre-feet. Project functions as a unit in coordinated system of reservoirs for multiple-purpose development of water resources in Willamette River Basin. All construction on Green Peter-Foster Lakes project initiated June 1961 is completed. Green Peter Lake was placed in operation for useful flood control June 1967 as a unit of coordinated reservoir system for protection of the Willamette River Basin. First power-generation unit was placed on the line June 9, 1967 and second, June 28, 1967. Use of Foster Lake for reregulating fluctuating flows from Green Peter units was effective December 1967. First power generation unit was placed on-line August 22, 1968 and second, September 6, 1968. Through September 1984 power generation totaled 6.3 billion kilowatt-hours. Of the gross income from sale of this power by Bonneville Power Administration, $33,908,043 was reimbursed to the U.S. Treasury to recover Corps of Engineers project investment and operating costs. Local cooperation. None required. Operations during fiscal year. Maintenance: Repair of the powerhouse roof was completed. Normal operation and maintenance continued. During the fiscal year 334,734,000 kilowatt-hours of electrical energy were generated at project of which 331,862,000 kilowatt-hours were delivered to Bonneville Power Administration, the marketing agency. Freshets regulated by Green Peter Lake project on Middle Santiam River are shown in Table 37-M. 61. HILLS CREEK LAKE, OR Location. On the Middle Fork, Willamette River, 47.8 miles from mouth and 26.5 miles upstream from Lookout Point Dam. Middle Fork, Willamette River rises on west slope of Cascade Range and flows northwesterly to its junction with Coast Fork, Willamette River. Dam is about 45 miles southeast from Eugene, OR. Existing project. An earth-and-gravel-fill dam about 2,150 feet long at the crest and 338 feet above lowest point 37-22 PORTLAND, OREGON DISTRICT of the general foundation. A gate-controlled concrete gravity chute-type spillway is in right abutment. Diversion tunnel, outlet tunnel and power tunnel are in same abutment. Powerhouse with two 15,000 kilowatt units is located next to spillway. Hills Creek Lake is about 8.5 miles long and provides storage capacity at full pool of 356,000 acre-feet. Project controls runoff of drainage area of 389 square miles and is an integral unit of comprehensive plan for development of water resources of Willamette River Basin. Hills Creek Lake and Lookout Point Lake are operated as a unit for control of floods and generation of power on Middle Fork Willamette River. These projects, in conjunction with Dexter reregulating dam and Fall Creek Lake flood control system, will effectively control floods on Middle Fork and provide maximum efficient generation of hydroelectric power. Recreation facilities are provided by the U.S. Forest Service. Construction of project, initiated May 1956, was completed June 1963. The project was placed in service for useful flood control in November 1961. On May 2, 1962, the two power units were placed on-line. Through September 1985 power generation totaled 3.8 billion kilowatt-hours. Of the gross income from sale of this power by Bonneville Power Administration, $15,238,213 was reimbursed to the U.S. Treasury to recover Corps of Engineers project investment and operating costs. Local cooperation. None required. Operations during fiscal year. Maintenance: Ordinary operation and maintenance continued. During fiscal year 162,614,000 kilowatt-hours of electrical power were generated, of which 162,099,000 kilowatt-hours were delivered to Bonneville Power Administration, the marketing agency. Freshets regulated by Hills Creek Lake on Middle Fork Willamette River are shown in Table 37-M. 62. JOHN DAY LOCK AND DAM-LAKE UMATILLA, OR AND WA Location. On Columbia River about 3 miles downstream from mouth of John Day River and about 215 miles above mouth of Columbia River. Existing project. A dam, powerplant, navigation lock, fish ladders, and appurtenant facilities with a slack-water lake about 75 miles long extending to McNary Lock and Dam. Included is relocation of railroads, highways, utilities, and communities affected by the impoundment. The project as originally authorized would have provided 2,000,000 acre-feet of flood control storage. As modified, the project provides 500,000 acre-feet of flood control storage between elevations 257 and 268. The structure is 5,900 feet in length and stands about 161 feet above streambed. Powerhouse has space for 20 generating units of 135,000 kilowatts each; 16 units have been installed for a present capacity of 2,160,000 kilowatts. Principal project data are set forth in Table 37-P. A detailed description of project as authorized and modified is on pages 1992 and 1993 of Annual Report for 1962 under the Walla Walla District. Construction began July 1958 and the project was opened to navigation April 1968. The main dam contract is complete. Lock rehabilitation work begun in FY 1980 is essentially complete. Entire project is estimated to be 99 percent complete. Through September 1985 power generation totaled 180.6 billion kilowatt-hours. Of the gross income from sale of this power by Bonneville Power Administration, $213,144,883 was reimbursed to the U.S. Treasury to recover Corps of Engineers project investment and operating costs. Estimated Federal cost of new work is $511,333,000, consisting of $511,000,000 Corps of Engineers and $333,000 for Coast Guard navigation aids. Local cooperation. None required. Operations during fiscal year. New work: Contracts were awarded for the second of two phases of construction to complete work on a juvenile by-pass system in September 1985. The contract for the first phase of construction will be physically completed in October 1985. The by-pass facility will consist of a collection system of submersible traveling screens, a conduit mined above the intakes to each turbine-generator unit and across the length of the powerhouse, a conduit extending from the powerhouse to an outfall structure downstream, and an intake gantry crane to handle fish facilities equipment. Maintenance: Normal operation and maintenance continued. During fiscal year 10,227,860,000 kilowatt-hours of electrical power were generated by the 16 generating units of which 10,209,816,000 kilowatt-hours were delivered to Bonneville Power Administration, the marketing agency. Traffic through the navigation lock, consisting of petroleum products, grains, and miscellaneous cargo, amounted to 7,958,217 tons during calendar year 1984. Rehabilitation: Refurbishment of two generator windings and rebuilding (to strengthen) two turbines were completed. A multi-unit generator refurbishment contract awarded will enable completion of 75% of all turbine generator work included in the rehab program. The contract for upgrading the powerhouse control system was awarded, which when complete should increase the reliability and ease of operation of the powerhouse. 63. LOOKOUT POINT LAKE, OR Location. On Middle Fork, Willamette River at Meridian site, 21.3 miles from mouth. Middle Fork, Willamette River, rises in Lane County on western slope of Cascade Range and flows northwesterly to its junction with Coast Fork, which is head of main stem Willamette River. Dam is about 22 miles southeast from Eugene, OR. Existing project. A main dam at Meridian site and a reregulating dam 3 miles downstream at Dexter site. Both dams are earth-and-gravel-fills with concrete spillways and have power generating facilities. Main dam is 258 feet high from lowest point of the general foundation to deck and is 3,381 feet long at crest forming a reservoir 14.2 miles long providing storage of 456,000 acre-feet 37-23 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 at full-pool level. Reservoir controls runoff of tributary drainage area of 991 square miles. Spillway, 274 feet long, is a gate-controlled overflow type, forming right abutment. Outlet works consisting of slide-gate-controlled conduits pass through spillway section. Powerhouse has three main generating units with a capacity of 120,000 kilowatts. Reregulating dam has a maximum height of 107 feet above lowest point of the general foundation and is 2,765 feet long at crest, forming a full pool of 27,500 acre-feet extending upstream to main dam and providing pondage to regulate Lookout Point powerhouse water releases to a uniform discharge. Spillway consists of a gate-controlled overflow section 509 feet long forming right abutment. Flow regulation is accomplished by use of spillway gates and releases through powerhouse, which contains one 15,000-kilowatt unit. Lookout Point and Dexter Lakes are operated as a single unit of a coordinated system of reservoirs to protect Willamette River Valley against floods, to provide needed hydroelectric power, and to increase low water flows for navigation, irrigation, and other purposes. Existing project authorized as a unit of comprehensive plan for flood control and other purposes in Willamette River Basin. Construction of project initiated May 1947 was completed June 1961, except for construction of additional recreation facilities funded through the Code 710 program. Future recreation facilities will be provided in accordance with the cost-sharing contract with Lane County and will require a 50 percent contribution by Lane County and is subject to funding availability by the Government and the County. At Lookout Point powerhouse, generating units 1, 2 and 3 were placed in commercial operation December 1954, February 1955, and April 1955, respectively. At Dexter powerhouse the single unit was placed on-line May 1955. Use of Dexter Lake for reregulating fluctuating flows from Lookout Point units was effected in December 1954. Through September 1984 power generation totaled 12.7 billion kilowatt-hours. Of the gross income from sale of this power by Bonneville Power Administration, $53,312,601 was reimbursed to the U.S. Treasury to recover Corps of Engineers project investment and operating costs. Local cooperation. Lane County Parks is participating in a multiple project cost-sharing (50 percent) contract for many of the existing parks at four projects, including Lookout Point-Dexter. Operations during fiscal year. Maintenance: Normal operation and maintenance continued. During fiscal year 414,379,000 kilowatt-hours of electrical power energy were generated at project of which 412,491,000 kilowatthours were delivered to Bonneville Power Administration, the marketing agency. Freshets regulated by Lookout Point Lake project on Middle Fork Willamette River are shown in Table 37-M. 64. LOST CREEK LAKE, ROGUE RIVER BASIN, OR Location. On upper Rogue River at mile 153.6 about 30 miles northeasterly from Medford, OR. Existing project. A rock and gravel-fill embankment dam about 327 feet high from streambed to crest, with an overall length of 3,750 feet with an impervious earth core and a gate-controlled concrete spillway. Powerhouse is on right abutment and houses two Francis-type turbines with installed capacity of 24,500 kilowatts each. Regulating outlet facility with provisions for temperature regulation for releases in interest of fishery enhancement is also on right bank. Reservoir 10 miles long provides 315,000 acre-feet of usable storage. Project provides control of runoff of drainage area of 674 square miles. In addition to hydroelectric power generation, project provides flood control, irrigation, future municipal and industrial (M&I) water supply, fish and wildlife enhancement, water quality control and recreation benefits. Construction of project initiated July 1967 is complete. Generating units 1 and 2 were placed in commercial operation July 6 and July 13, 1977, respectively. Physical in-service date for flood control was February 18, 1977. Final environmental statement was filed with Council on Environmental Quality in June 1972. Through September 1985 power generation totaled 2.5 billion kilowatt-hours. Of the gross income from sale of this power by Bonneville Power Administration, $11,804,364 was reimbursed to the U.S. Treasury to recover Corps of Engineers project investment and operating costs. Local cooperation. Authorizing act required that local agencies furnish assurances prior to construction that demands will be made for future use of water supply storage within a period that will permit repayment of costs, including interest, allocated to water supply within life of the project; that State of Oregon take action, prior to construction to insure maintenance in stream of flows to be released for fishery; in addition, costs allocated to irrigation would have to be repaid in manner and to an extent consistent with reclamation laws and policies; and costs allocated to power will be repaid on a system basis by revenue from sales of power in Pacific Northwest Federal system by Bonneville Power Administration. A survey in September, 1980 of M&I water supply needs showed nine communities with water supply needs. A contract for M&I supply has been completed with one of the communities. Assurances for municipal and industrial water supply were obtained from six communities in Rogue River Valley. On February 26, 1966 Oregon State Department of Fish and Wildlife agreed to operate Rogue River hatchery for mitigation and enhancement of fish. The hatchery became operational in 1972. Operations during fiscal year. New work: A contract for minor roadway repair was completed. Maintenance: During fiscal year 257,708,000 kilowatthours of electrical power energy were generated at project of which 255,104,000 kilowatt-hours were delivered to Bonneville Power Administration, the marketing agency. Freshets regulated by Lost Creek Lake on Rogue River are shown in Table 37-M. 37-24 PORTLAND, OREGON DISTRICT 65. THE DALLES LOCK AND DAM-LAKE CELILO, WA AND OR Location. On Columbia River at head of pool behind Bonneville Dam, about 192 miles above mouth of river and 88 miles east of Portland, OR. Existing project. A dam, powerplant, navigation lock, and appurtenant facilities. Improvement provides for navigation and hydroelectric power generation. Dam is designed for a normal pool at elevation 160 feet at mean sea level. Normal pool forms a reservoir extending upstream about 23 miles providing slackwater to John Day Dam site. The Dalles Dam is 8,700 feet long and consists of a rock, gravel, and sand river closure section from Oregon shore connecting to a nonoverflow section which in turn joins powerhouse, then concrete nonoverflow sections connecting spillway with powerhouse and spillway with navigation lock at right abutment on Washington shore. Fish-passing facilities including two ladders and a fish lock are provided. Powerhouse was constructed for 14 units initially and substructure for eight additional units, an ultimatetotal of 22 units. Initial installation, excluding two 13,500 kilowatt fishwater units, is 1,092,000 kilowatts. With eight units installed for a capacity of 687,800 kilowatts, the 22 unit total is 1,808,800 kilowatts. Structures are founded on Columbia River basalt. Principal data concerning lock, spillway, and powerhouse are set forth in Table 37-P. Major construction of project initiated February 1952, was completed October 1960 when unit No. 14 was placed in commercial operation. Initial contract for additional units 15-22 was awarded in September 1967. Additional 8-unit phase was completed when unit 22 was placed in commercial operation in November 1973. Construction of future recreational facilities is contingent upon a costsharing contract with a non-Federal sponsor. Studies for adding power generation facilities to the North Shore Fish Ladder Auxiliary Water Supply System were initiated in October 1979 and completed in December 1980. These facilities would provide baseload generation (3.5 megawatts) and would not impact the present operation of the North Fish Ladder. Seufert Visitor Center was completed in September 1980. Through September 1985 power generation totaled 195.1 billion kilowatt-hours. Of the gross income from sale of this power by Bonneville Power Administration, $238,255,560 was reimbursed to the U.S. Treasury to recover Corps of Engineers project investment and operating costs. Local cooperation. None required except for non- Federal cost-sharing for development of Recreation Facilities at Completed Projects. Operations during fiscal year. Maintenance: Ordinary operation and maintenance continued. During fiscal year 8,061,511,000 kilowatt-hours of electrical power energy were generated at project of which 8,042,255,000 kilowatt-hours were delivered to Bonneville Power Administration, the marketing agency. Traffic through the navigation lock, consisting of petroleum products, grains and miscellaneous cargo amounted to 7,986,555 tons during calendar year 1984. General Investigations 66. SURVEYS Fiscal year costs were $2,926,598 of which $169,645 was for navigation studies, $1,878,615 for flood damage prevention studies, $318,028 for comprehensive studies, $350,089 for reviews of authorized projects, $165,559 for miscellaneous activities, and $44,662 for coordination with other agencies. 67. COLLECTION AND STUDY OF BASIC DATA International water studies. The Columbia River Treaty between Canada and the United States of America relating to cooperative Development of the Water Resources of the Columbia River Basin was signed at Washington, D.C., on January 17, 1961, and the exchange of ratifications took place on September 16, 1964. Implementation of the Treaty by the United States and Canada entities under the guidance of the Permanent Engineering Board has continued. The two permanent committees established by the entities, the Operating Committee and the Hydrometeorological Committee, continue to function. Costs for support of both committee activities were $18,833 for the fiscal year. Flood plain management services. Flood Plain Management Services Program comes under Section 206 of the 1960 Flood Control Act, PL 86-645, as amended. Through technical services and planning guidance, the program encourages comprehensive flood plain management planning at all levels to reduce the potential for losses to life and property from floods. Federal and non- Federal agencies and the private sector are assisted with planning and development information for flood hazard areas. This assistance is in the form of local flood plain regulations, Federal Insurance Program requirements, and Executive Order 11988 guidelines. Such assistance may include factual flood information (available or determined) and interpretation on flood frequencies, extent of flooding, flood-water velocity, duration of flooding and floodway limits. The U.S. Army Corps of Engineers this year is commemorating the silver anniversary of its civil works directorate's Flood Plain Management Services Program. This vital civil works program has provided flood plain management assistance to states, counties, cities, individuals and federal agencies. Over the past 25 years, it has become a key element in the federal, state and local partnership to reduce national flood losses. Services accomplished during fiscal year: Technical services and planning guidance responses furnished totaled 734. Of this total, 64 were from other Federal agencies; 248 from non-Federal agencies; and 422 from private sector realtors, corporations, lending institutions, engineers, architects, and others. Cost for providing these services during FY 1985 totaled $152,260. Hydrologic studies. Environmental and ecological aspects are being considered on all hydrologic studies. Improvements in procedures to determine reservoir 37-25 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 temperatures, nitrogen supersaturation, dissolved oxygen, suspended sediment, turbidity, design floods, flood forecasting and flood regulation are a continuing program. Costs for hydrologic studies during the fiscal year were $2,102. Total costs for collection and study of basic data for fiscal year 1985 were $173,196. 68. CONTINUATION OF PLANNING AND ENGINEERING Bonneville Navigation Lock, OR and WA The project will provide for a new lock just south of the existing lock on the Oregon shore and will have dimensions of 86 feet wide, 675 feet long and 19.0 feet deep over the sill. Work on the General Design Memorandum and a feature memorandum (Relocation) was initiated in FY 1982 and completed in FY 1984. Other feature memorandums that were initiated in FY 1983 (with percentages completed) are Site Selection - completed in 1983 (100%); Bonneville Power Administration Substation and Project Power Requirements (70%); Real Estate for Relocation (50%); Instrument and Inspection (80%); Architectural Theme and Site Planning (80%); Geology, Foundation and -Excavation (100%); and Concrete Materials (30%). Lock feature design memorandum was initiated and completed in FY 1984. Estimated preconstruction cost is $10,556,000 and total costs to September 30, 1985 are $10,502,403. Authorizing legislation was contained in the FY 1985 Supplemental Appropriations Act, Public Law 99-88, August 15, 1985. Cowlitz River and Tributaries, WA The project will provide a permanent solution to potential flooding on the Cowlitz River and to potential disruption of navigation on the Columbia River from sedimentation problems created by the eruption of Mt. St. Helens. The Feasibility Report completed in.December 1984 recommended construction of a single retention structure and associated downstream actions. The preferred plan in that report consisted of a 177-foot-high retention structure on the North Fork Tobutle River upstream of its confluence with the Green River. Continuation of planning and engineering was initiated in December 1984. It included a comparative analysis of risks, benefits and costs, and design, at an equal level of detail, of a single state sediment retention structure (SRS), a staged SRS, and dredging program. A General Design Memorandum and a Feature Design Memorandum (Hydrology and Meteorology) were completed in FY 1985. Other Feature Design Memoranda initiated in FY 1985 (with percentages completed) are Excavation, Dewatering, Diversion and Cofferdam (20%); Soils, Geology and Foundations (20%); Concrete Materials (10%); Gravity Dam and Fish Facility (40%); Embankment Dam (20%); Spillway, Outlets, Stilling Basin (40%); Clearing, Project and Bypass Roads (80%); Real Estate (90%); Fish Facilities (70%); and Decision Document (80%). Estimated preconstruction cost is $7,300,000 and total costs to September 30, 1985 are $4,858,040. Authorizing legislation was contained in the FY 1985 Supplemental Appropriations Act, Public Law 99-88, August 15, 1985. 37-26 PORTLAND, OREGON DISTRICT TABLE 37-A COST AND FINANCIAL STATEMENT See Section Total to In Text Project Funding FY 82 FY 83 FY 84 FY 85 Sep. 30, 1985 1. Bandon Small Boat Basin, Coquille, OR 2. Charleston Channel, Coos Bay, OR 3. Chetco River, OR 4. Columbia and Lower Willamette Rivers Below Vancouver, WA and Portland, OR (Federal Funds) (Contributed Funds) 5. Columbia River at Baker Bay, WA 6. Columbia River Between Chinook, WA, and Head of Sand Island 7. Columbia River at The Mouth, OR and WA 8. Columbia River Between Vancouver, WA and The Dalles OR 9. Columbia River, Ilwaco, WA 10. Coos Bay, OR (Federal Funds) New Work Approp. Cost New Work Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Contrib. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost Major Rehab. Approp Cost New Work Approp. Cost Maint Approp. Cost New Work Approp. Cost New Work Approp. Cost Maint Approp. Cost 438,691 601,000 111,798 925,771 63,000 67,032 1,156,000 48,538 345 -3,790 1,173,524 -1,996 1,173,524 143,000 --215,000 1,197,300 1,035,967 -240 1,197,300 -- - 2,043 713' - - - - 2.043,713' 515,000 535,500 361,300 475,000 4,267,426 536,070 537,204 361,560 472,802 4,264,033 - - - - 28,349,3042 - - - - 28,349,3042 9,027,100 15,812,000 20,815,100 15,213,000 224,688,1263 14,286,451 17,042,261 20,716,288 15,306,888 224,657,9963 - - - - 665,9544 - - - - 665,9544 92,000 150,400 107,273 137,965 847,000 220,649 100,000 -35,955 4,075,000 4,583,876 53,150 663,437 -187,772 2,131,100 2,191,396 3,105,000 177,000 3,089,332 191,730 - - 941,252 - - 941,252 16,500 312,000 2,597,185 29,861 312,160 2.597.070 - - 220,2835 - - 220,2835 34,500 338,000 3,049,813 51,058 321,474 3,032,556 7,008,000 7,003,593 5,744,000 5,771,078 938 347,900 352,944 7,250,000 7,243,987 24,913,6616 24,913,6616 75,379,6847 75,360,7687 - 7,322,878 - 7,322,878 - - - - 5,989,509" - - - - 5,989,5098 206,000 189,000 188,400 663,000 10,837,9489 216,986 187,748 190,017 652,345 10,827,244' 81,000 57,528 26,614 22,500 1,384,500 1,552,000 20,374 1,362,243 1,528,548 - - 29,750,09210 - - 29,750,09210 4,566,000 2,263,000 2,971,940 5,042,000 56,183,652" 3,632,808 3,269,872 2,992,359 4,974,845 56,114,997" 37-27 TABLE 37-A (Continued) REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 COST AND FINANCIAL STATEMENT See Section Total to In Text Project Funding FY 82 FY 83 FY 84 FY 85 Sep. 30, 1985 (Contributed Funds) 11. Coos and Millicoma Rivers, OR 12. Coquille River, OR 13. Cowlitz River, WA 14. Depoe Bay, OR 15. Lewis River, WA 17. Nehalem Bay, OR 18. Port Orford, OR 20. Rogue River Harbor At Gold Beach, OR Major Rehab Approp. Cost New Work Contrib. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost Major Rehab Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost 130,000 136,400 121,900 132,768 122,851 135,609 - 2,335,966 - 2,335,966 - 486,680 - 486,680 - 350,2381" - 350,238"2 49,000 1,524,010 43,230 1,517,125 - - - - 693,366'1 - - - - 693,366' 3 383,000 167,600 191,400 426,000 4,710,944' 4 438,165 172,074 193,508 418,273 4,702,425' 4 -6,000 18,244 2,000 2,464 1,419 248 89,700 89,446 53 - 277,436"5 - 277,436" - 1,474;03616 177 1,474,036 " 55,000 52,512 367,364 367,364 720,876 717,921 58,132' 7 58,132'" 685,677'" 41 685,677" 302,006" 302,006" 55,195 55,195 9,020,000 550,000 126,000 - 12,088,000 8,648,997 922,899 134,975 5,724 12,070,974 - - - - 758,69220 - - - - 758,692" 179,000 191,000 365,900 392,000 2,196,329 175,849 198,364 365,818 389,311 2,193,451 - - - - 4,156,252"1 - - - - 4,156,2521 755,000 1,044,500 387,700 1,000,000 7,974,720"2 718,623 796,151 677,713 985,538 7,958,236"2 37-28 PORTLAND, OREGON DISTRICT TABLE 37-A COST AND FINANCIAL STATEMENT (Continued) See Section Total to In Text Project Funding FY 82 FY 83 FY 84 FY 85 Sep. 30, 1985 21. Siuslaw River, OR (Federal Funds) (Contributed Funds) 22. Skamokawa Creek, WA 23. Skipanon Channel, OR 24. South Channel, Government Island, OR (Federal Funds) (Contributed Funds 25. Tillamook Bay and Bar, OR 26. Umpqua River, OR 27. Willamette River Above Portland and Yamhill River, OR Major Rehab Approp. Cost New Work Approp. Cost Maint. Approp. Cost Major Rehab. Approp. Cost New Work Contrib. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost New Work Contrib. Cost New Work Approp. Cost Maint. Approp. Cost Major Rehab. Approp. Cost New Work Approp. Cost Maint. Approp. Cost Major Rehab. Approp. Cost New Work Approp. Cost 115,042 107,638 1,088,000 1,122,756 4,999,813 287,947 504,000 503,248 8,000,000 12,713,495 719,900 723,964 45,000 - 10,000 59 -1,500 177,000 534,100 375,467 214,238 43,500 28,763 67,000 60,312 12,900,000 12,915,368 646,000 641,001 45,000 90,000 - 100,000 143 98,845 635,783 635,783 27,384,21223 27,379,859 "3 9,903,09924 9,897,78324 879,285 879,285 412,532 412,532 2,400 2,400 383,782 382,388 - - 280,854 - - 280,854 80,500 336,000 2,537,014 403,165 334,934 2,535,915 102,000 -5,000 27,643 42,654 - 102,000 - 102,000 68,800 74,903 -100,000 -50,000 18,076 13,654 1,201,000 413,000 1,167,055 503,589 -20,700 20,741 119,800 119,800 102,000 102,000 - - 22,434,827$ - - 22,434,82725 31,000 217,000 2,858,790" 32,593 205,228 2,846,826 ' 9,851 827,700 829,517 - 2,839,799 - 2,839,799 - 17,718,87727 161 17,718,87727 604,000 20,451,989 580,834 20,428,599 - 2,500,677 - 2,500,677 862,918'" 862,918' 37-29 TABLE 37-A REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 COST AND FINANCIAL STATEMENT (Continued) See Section Total to In Text Project Funding FY 82 FY 83 FY 84 FY 85 Sep. 30, 1985 28. Willamette River at Willamette Falls, OR 29. Winchester Bay, Umpqua River, OR 30. Yaquina Bay and Harbor, OR 31. Applegate Lake, Rogue River Basin, OR 32. Blue River Lake, OR 33. Cottage Grove Lake, OR 34. Dorena Lake, OR 35. Elk Creek Lake, Rogue River Basin, OR 36. Fall Creek Lake, OR Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost Minor Rehab Approp. Cost New Work Approp. Cost New Work Approp. Cost Maint. Approp. Cost Major Rehab. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost New Work Approp. Cost 10,000 15,500 100 - 17,900,29329 11,359 16,897 - 144 17,900,29329 - - - - 520,00530 - - - - 520,00530 625,000 720,000 528,000 501,000 13,462,8233' 631,011 537,797 710,319 480,860 13,435,2253' - - - - 234,794 - - - - 234,794 533,000 920,000 8,500 -729 1,616,369 78,148 795,066 596,788 - 1,616,369 - - - - 19,242,04632 - - - - 19,242,04632 737,000 1,085,100 1,493,400 1,131,000 18,182,30233 741,918 1,089,700 1,494,202 1,094,881 18,144,67333 12,005 12,005 3,600,000 291,000 2,658,965 971,353 30,000 189,499 31,300 91,633,189 111,836 91,575,942 410,700 623,500 512,000 580,000 2,206,700 405,951 474,474 650,948 590,699 2,197,921 - - - - 32,038,22534 - - - - 32,038,22534 142,700 221,600 180,000 151,000 1,700,991 115,732 246,991 184,659 147,919 1,693,369 9,025 9,874 531,480 472,734 450,000 96,831 260,500 225,543 - - - 4,013,12335 - - - 4,013,12335 537,698 673,000 623,000 7,270,67836 607,162 655,509 605,928 7,231,37436 354,286 307,200 342,935 1,495,000 1,350,000 1,460,877 1,389,366 14 - 1,200 1,600 342,000 342,563 - 14,568,262 3 - 14,568,26237 352,000 4,038,174 328,889 4,011,971 3,500 10,000,000 21,866,579 -8,100 4,773,965 16,603,475 - - 22,118,26438 - - 22,118,26438 37-30 PORTLAND, OREGON DISTRICT TABLE 37-A (Continued) COST AND FINANCIAL STATEMENT See Section Total to In Text Project Funding FY 82 FY 83 FY 84 FY 85 Sep. 30, 1985 37. Fern Ridge Lake, OR 38. Huntington Avenue, Castle Rock, WA 42. John Day River (West), OR 44. Lower Columbia River Basin Bank Protection, OR & WA 45. McDonald Dike Road, Nehalem River, OR 46. Mt. St. Helens and Vicinity, WA 47. Salmon Creek, Near Vancouver, WA (Federal Funds) (Contributed Funds) 49. State Hwy. 101 & 401, Columbia River, WA (Federal Funds) (Contributed Funds) 50. Tualatin, OR 51. Umatilla River, Thorn Hollow, OR 52. Wahkiakum County Consolidated Diking District No. 1, WA 53. West Makinster Road, Wilson River, OR 55. Willamette River Basin Bank Protection, OR Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost New Work Approp. Cost New Work Approp. Cost New Work Aprop. Cost New Work Approp. Cost New Work Approp. Cost New Work Contrib. Cost New Work Approp. Cost New Work Contrib. Cost New Work Approp. Cost New Work Approp. Cost New Work Approp. Cost New Work Approp. Cost New Work Approp. Cost Maint. Approp. Cost 308,000 261,448 188,975 171,983 510,700 423,165 241,000 270,000 235,000 3,791,415 296,904 269,304 232,116 3,786,406 - - - 8,526,9353� 16,958 77 - 8,526,93538 905,000 937,000 742,000 9,317,63440 961,183 958,097 745,135 9,303,61540 - 250,000 - 249,420 580 250,000 250,000 - - - 122,300 122,300 - - - 122,291 122,291 550,000 1,700,000 2,600,000 1,000,000 17,724,745 690,173 1,710,021 2,458,996 1,149,563 17,721,788 29,500 29,463 29,500 37 29,500 - 15,730,000 10,345,000 6,133,000 32,208,000 - 7,557,368 18,267,493 6,232,116 32,056,977 39,500 210,500 - 9,760 37,780 201,160 - - 185,000 - - 185,000 - 35,000 215,000 - 6,302 78,804 - - 267,500 1,301 164,894 -12,858 254,642 250,000 250,000 185,000 185,000 250,000 250,000 254,642 254,642 35,000 1,200,000 100,000 468,094 1,803,094 31,341 1,200,860 98,545 472,348 1,803,094 oo00,000 317,775 165,000 38,301 -1,000 5,889 10,000 115,546 3,375 -20,400 753 154,600 154,600 - 5,289,833 428 5,289,833 - 178,000 - 175,012 1,150,000 1,054,893 50,000 43,024 1,050,000 1,086,098 160,000 165,055 624,500 636,359 56,600 62,436 744,000 760,094 178,000 179,056 178,000 175,012 23,965,816'41 23,930,57541 3,445,544 3,445,070 37-31 TABLE 37-A (Continued) REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 COST AND FINANCIAL STATEMENT See Section Total to In Text Project Funding FY 82 FY 83 FY 84 FY 85 Sep. 30, 1985 56. Willow Creek Lake, OR 57. Bonneville Lock and Dam-Lake Bonneville, OR and WA 58. Cougar Lake, OR 59. Detroit Lake, OR 60. Green Peter-Foster Lakes, OR 61. Hills Creek Lake, OR 62. John Day Lock and Dam-Lake Umatilla, OR and WA 63. Lookout Point Lake, OR New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost Minor Rehab. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost Major Rehab. Approp. Cost New Work Approp. Cost Maint. Approp. Cost (See Walla Walla, WA District Table 39-A) 86,000 498,000 83,904 467,009 25,417,000 25,151,114 6,440,800 5,652,065 21,456,000 21,390,863 7,350,600 8,369,863 -12 15,000 86 8,233 555,700 682,000 523,511 716,706 12,200,000 12,032,268 8,820,000 8,478,177 6,241 860,000 861,133 17,530,000 17,905,137 10,468,000 10,848,327 584,000 550,913 738,470,60442 738,250,74642 117,276,10143 117,022,10743 - 58,636,393'4 492 58,636,359"44 731,000 8,389,816 733,379 8,376,031 - - - - 62,729,698 - - - - 62,729,698 1,206,600 1,232,000 1,789.000 1,411,000 22,404,772 1,142,679 1,312,198 1,757,050 1,426,060 22,384,652 - - - - 363,086 - - - - 363,086 - - - - 84,005,788 4 - - - - 84,005,78845 1,310,800 1,423,000 1,694,000 1,810,000 18,365,13246 1,236,338 1,550,143 1,679,567 1,825,339 18,357,547"4 - - - - 45,700,619 - - - - 45,700,619 510,600 693,900 591,000 457,000 6,573,267 447,630 747,486 641,968 442,717 6,558,341 2,143,000 1,737,709 7,795,000 7,056,756 645,000 502,806 1,298,000 1,597,688 9,506,100 10,647,483 -45,000 53,108 32 - 10,624,000 9,103,019 9,746,000 9,956,705 6,483,000 8,046,653 10,633,000 10,663,086 501,251,246,7 501,173,45047 84,249,159"4 83,968,2384 - 138,000 7,293,000 18,669 167,842 7,289,294 - - 88,238,39549 - - 88,238,39549 1,911,900 2,092,100 2,348,000 2,119,000 31,720,60550 1,697,620 2,356,652 2,332,882 2,138,429 31,678,3415 37-32 PORTLAND, OREGON DISTRICT TABLE 37-A (Continued) COST AND FINANCIAL STATEMENT See Section Total to In Text Project Funding FY 82 FY 83 FY 84 FY 85 Sep. 30, 1985 64. Lost Creek Lake, New Work Rogue River Approp. - 250,000 - 290,000 136,403,450 Basin, OR Cost 85,018 537,648 235,687 271,310 136,384,408 Maint. Approp. 1,620,000 2,092,300 2,105,000 2,600,000 14,443,80051 Cost 1,761,302 2,157,181 2,100,169 2,522,379 14,343,4255' 65. The Dalles Lock and New Work Dam-Lake Celilo, Approp. - - - - 301,064,28852 WA and OR Cost 301 - - - 301,064,28852 Maint. Approp. 4,196,000 5,120,000 6,201,000 7,606,000 74,043,008"53 Cost 4,151,104 5,763,701 5,840,781 7,851,423 73,848,166"53 'Excludes $17,742 contributed funds for new work. 'Includes $1,529,413 for previous project. aIncludes $150,955 allotted from deferred maintenance funds, Code 700, $62,296 for public works accelerated program repair, and $1,214,865 for previous project. Excludes $24,320 expended from contributed funds prior to 1964. 4Excludes $31,636 contributed by city of Astoria and Bumble Bee Sea Foods, Astoria, OR (not part of regular project). Includes $223,026 expended from contributed funds prior to 1964 and $428,136 contributed by Port of Portland and $14,792 by Port of Vancouver. "Includes $84,930 rehabilitation funds. 'Includes $1,986,253 for previous project and $608,111 allotted and expended under Code 710, recreation facilities at completed project. Excludes $500,000 contributed funds. 7Includes $2,186,000 for previous project and $1,188,625 under deferred maintenance, Code 700. 'Includes funds under Code 721 (small authorized projects) $30,393 Entrance to Oregon Slough; $161,897, Camas- Washougal Turning Basin; $227,908, Hood River Small Boat Basin; $157,470, Bingen, WA, Barge Channel; and $140,619, The Dalles Small Boat Basin. 'Includes $2,033,408 under Code 700 (Deferred Maintenance). "Includes $802,096 for previous project. Excludes contributed funds. "Includes $178,801 for previous project and $1,444,640 under Code 700, Deferred Maintenance. Excludes $8,387 contributed funds. "Excludes $80,000 (other funds) contributed for new work by Port of Coos Bay to cover additional cost of disposing of dredge spoils in Coos Bay, OR; includes $8,000 for previous project. "Includes $340,726 for previous project. Excludes $72,891 contributed funds. Includes $36,000 under Code 711. "Includes $41,467 for previous project and $78,500 under Code 700, Deferred Maintenance. l"Includes $239,529 for Sec. 107 project. 'Includes $48,184 for previous project. "Includes $22,252 for previous project. "Includes $8,098 for previous project. "Excludes $304,826 contributed funds. 'Excludes $9,900 contributed funds. "'Excludes $13,779 (other funds) contributed for additional landfill and extension of drainage lines. "Includes $21,000, Wedderburn Study Funds. "Includes $1,159,357 for previous project. "Includes $10,611 for previous project and $188,000 under Code 700, Deferred Maintenance. "Includes $77,209 for previous project and $57,767 under Code 720 (Small Authorized Projects) Garibaldi Boat Basin. Excludes $592, 622 contributed funds and $300,000 channel dredging by local interest. "Includes $71,498 for previous project. Excludes $6,450 expended from contributed funds. "Includes $39,242 for previous project and $58,824 under Code 720 (Small Authorized Projects) Winchester Bay and Schofield River, OR. Excludes $267,500 contributed funds. "Includes $247,748 for previous project. Excludes $484,900 Emergency Relief Administration flood control funds for bank protection. 29Includes $51,500 deferred maintenance funds Code 700, and $35,935 for Public Works Acceleration program repair. In addition, $7,500 for maintenance from contributed funds and $246,637 on operating and care of improvements under provisions of permanent indefinite appropriation. soExcludes $300,000 contributed funds. 3"Includes $452,110 on operation and care from permanent indefinite appropriation and $150,000 under maintenance and operation of dams and other improvements of navigable waters. "Includes $707,313 for previous project and $170,000 appropriated from public works acceleration program for north jetty rehabilitation. "3Includes $6,026 for previous project. "Inlcudes $96,000 pro rata share of site selection costs in lieu of Quartz Creek Lake. "Includes $1,639,828 allotted and expended under Code 710, recreation facilities at completed project.. "Includes $167,878 special recreation use fees. "37Includes $1,038,790 allotted and expended under Code 710, recreation facilities at completed project. 3"Includes $1,026,264 allotted and expended under Code 710, recreation facilities at completed projects. "Includes $3,894,673 allotted and expended under Code 710, recreation facilities at completed projects and $136,482 allotted under 721 (small authorized project) reservoir modification. Excludes $2,100 (other funds constributed). "Includes $9,750 allotted under Code 700, deferred maintenance. "Excludes $93,733 contributed funds. "Includes $12,200,000 Public Works Administration funds, $20,240,700 National Recovery Act funds, $27,195,400 modification for peaking funds, $436,457 Code 710, recreation facilities at completed project funds and $627,593,352 allotted and 37-33 TABLE 37-A (Continued) REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 COST AND FINANCIAL STATEMENT $627,373,531 expended second powerhouse funds; $6,000 allotted and $5,964 expended, power units funds. "'Includes $540,000 deferred maintenance funds, Code 700 and $1,692,148 maintenance and operation of dams and other improvements of navigable waters. "Includes $96,000 pro rata share of site selection in lieu of Quartz Creek Lake. Includes $1,789,988 allotted and $1,789,954 expended for Strube Lake and Cougar Additional Unit. "Includes $113,000 pro rata share of site selection costs in lieu of Sweet Home Lake. "Includes $56,500 under maintenance and operation of dams and other improvements of navigable waters. 47lIncludes $25,984 allotted and expended under Code 710, recreation facilities at completed projects. "Includes $1,361,900 for O&M and fish evaluation of Spring Creek Hatchery (funds revoked and paid to USFWS at OCE level, but a cost to project); includes $423,800 special recreation use fees. Includes $933,438 allotted under maintenance and operation of dams and other improvements of navigable waters. 4"Includes $457,611 allotted and expended under Code 710, recreation facilities at completed project. 5"Includes $56,500 under maintenance and operation of dams and other improvements to navigable waters. 5'Includes $56,500 under maintenance and operation of dams and other improvements to navigable waters. 5"2Includes $1,140,747 allotted and expended under Code 710, recreation facilities at completed project, and $52,997,220 allotted and expended additional units 15-22 funds. 53Includes $721,490 under maintenance and operation of dams and other improvements of navigable waters. 37-34 PORTLAND, OREGON DISTRICT AUTHORIZING LEGISLATION See Date Section Authorizing in Text Act Project and Work Authorized Documents 1. July 14, 1960 2. 3. July 14, 1960 Mar. 2, 1945 Oct. 27, 1965 Dec. 4, 1981 4. Feb. 27, 1911 July 25, 1912 July 27, 1916 Aug. 8, 1917 Sep. 22, 1922 Mar. 4, 1923' Mar. 3, 1925 Mar. 3, 1927 July 3, 1930 Sep. 6, 1933' Aug. 30, 1935 Aug. 30, 1935 Aug. 30, 1935 BANDON SMALL BOAT BASIN, COQUILLE, OR A breakwater 413 feet in length, an entrance channel 100 feet wide, 250 feet long and 13 feet deep, an access channel 50 feet wide, 500 feet long, and 13 feet deep. CHARLESTON CHANNEL, COOS BAY, OR A channel 150 feet wide, 6,800 feet long with depths between 16 to 17 feet. CHETCO RIVER, OR ITop rovide for the stabilization of the channel, by constructing jetties and dredging. Modification of channel entrance and channel improvements Deepen channel 2 feet to 16 feet, extend the existing jetty system 750 feet for the North, and 1,250 feet for the South jetty. COLUMBIA AND LOWER WILLAMETTE RIVERS BELOW VANCOUVER, WA AND PORTLAND, OR 2 pipeline dredges and accessories. Increasing main channel to 30 feet Consolidating improvement below Portland, OR and between Vancouver, WA and mouth of Willamette. For the Cathlamet channel. Construct an additional dredge (dredge was not built) and accessories for better maintenance, and construct contraction works. Channel from deep water in Willamette Slough to deep water in Columbia River. Depth of 25 feet and width of 300 feet from mouth of Willamette River to Vancouver, WA. Closing east channel at Swan Island in Willamette River on condition that main channel to be opened to project dimensions on west side of island by Port of Portland. For a 35-foot channel 500 feet wide from Portland to the sea. A channel 28 feet deep and 300 feet wide from mouth of Willamette River to Vancouver, with 2 turning basins, each generally 28 feet deep by 800 feet wide by 2,000 feet long. A channel in Columbia River from mouth of Willamette to interstate highway bridge at Vancouver, WA, 30 feet deep and 300 feet wide, with 2 turning basins at Vancouver. Maintenance of not to exceed 35-foot depth at low water in Portland Harbor and Willamette River between its mouth and Broadway Bridge at Portland. Auxiliary channels, 30 feet deep, 300 feet and 500 feet at St. Helens. Section 107, P.L. 86-645, Authorized by Chief of Engineers, Nov. 18, 1981. Section 107, PL. 86-645 Authorized by Chief of Engineers, April 8, 1983. H. Doc. 817, 77th Cong., 2d Sess. S. Doc. 21, 89th Cong., 1st Sess. S. Doc. 10, 96th Cong., 1st Sess. H. Doc. 1278, 61st Cong., 3d Sess. H. Doc. 1278, 61st Cong., 3d Sess? No Prior Report. H. Doc. 120, 63d Cong., 1st Sess? H. Doc. 1009, 66th Cong., 3d Sess. H. Doc. 156, 67th Cong., 2d Sess. H. Doc. 126, 68th Cong., 1st Sess. Rivers and Harbors Committee Doc. 10 69th Cong., 2d Sess. H. Doc. 195, 70th Cong., 1st Sess. and Rivers and Harbors Committee Doc. 8, 71st Cong., 1st Sess.' H. Doc. 249, 72d Cong., 2d Sess? Rivers and Harbors Committee Doc. 1, 74th Cong., 1st Sess. Rivers and Harbors Committee Doc. 6 73d Cong., 1st Sess.? H. Doc. 235, 72d Cong., 1st Sess? 37-35 TABLE 37-B REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 37-B (Continued) AUTHORIZING LEGISLATION See Date Section Authorizing in Text Act Project and Work Authorized Documents Aug. 26, 1937 Aug. 26, 1937 Mar. 2, 1945 Mar. 2, 1945 July 24, 1946 Oct. 23, 1962 Oct. 23, 1962 Dec. 11, 1933 Aug. 30, 1935 Mar. 2, 1945 May 17, 1950 June 20, 1938 Sep. 3, 1954 Mar. 3, 1905 Dec. 22, 1944 as amended Sep. 3, 1954 July 30, 1983 Aug. 26, 1937 Mar. 2, 1945 July 24, 1946 July 24, 1946 Extension of lower turning basin at Vancouver, WA, 1,000 feet downstream. An auxiliary channel 24 feet deep and 200 feet wide along waterfront at Rainier, OR. Improvement of old mouth of Cowlitz River. An auxiliary channel in vicinity of Longview, WA. A small-boat mooring basin at Astoria, OR. A channel 35 feet deep and 500 feet wide from mouth of Willamette River to interstate highway bridge at Vancouver, WA, with 2 turning basins of same depth. A channel 40 feet deep and 600 feet wide from Vancouver, WA, to mouth of Columbia River; a turning basin at Vancouver, WA, a turning basin at Longview, WA, and a channel 40 feet deep in Willamette River from mouth to Broadway Bridge which encompasses Portland Harbor area. COLUMBIA RIVER AT BAKER BAY, WA Main channel Main channel. West channel 8 feet deep. West channel 10 feet deep and mooring basin with protecting breakwaters. COLUMBIA RIVER BETWEEN CHINOOK, WA AND HEAD OF SAND ISLAND Channel 8 feet deep. Channel 10 feet deep and mooring basin. COLUMBIA RIVER AT THE MOUTH, OR AND WA Extend South Jetty and construct North Jetty and dredging. Construction, operation, and maintenance of recreation facilities. Bar channel of 48-foot depth and spur jetty on north shore.? Deepening the northernmost 2,000 feet of the channel cross section to 55 feet. COLUMBIA RIVER BETWEEN VANCOUVER, WA, AND THE DALLES, OR Construct a channel 27 feet deep by 300 feet from Vancouver, WA, to Bonneville, OR. Construct Camas-Washougal turning basin. Construct a channel 27 feet deep by 300 feet wide from Bonneville, OR, to The Dalles, OR. Construct a boat basin at Hood River, OR, 10 feet deep, 500 feet wide, by 1,300 feet long. Rivers and Harbors Committee Doc. 81, 74th Cong., 2d Sess. H. Doc. 203, 75th Cong., 1st Sess. H. Doc. 341, 77th Cong., 1st. Sess.' H. Doc. 630, 77th Cong., 2d Ses.' H. Doc. 692, 79th Cong., 2d Sess. H. Doc. 203, 87th Cong., 1st Sess. H. Doc. 452, 87th Cong., 2d Sess. Public Works Administration H. Doc. 44, 73d Cong., 1st Sess. H. Doc. 443, 76th Cong., 1st Sess. S. Doc. 95, 81st Cong., 1st Sess. Rivers and Harbors Committee Doc. 50, 75th Cong., 2d Sess. S. Doc. 8, 83d Cong., 1st Sess? H. Doc. 94, 56th Cong., 1st Sess. Sec. 4, Flood Control Act of 1944 H. Doc. 249, 83d Cong., 2d Sess.' P.L. 98-63 H. Committee Doc. 94, 74th Cong., 2d Sess.' H. Doc. 218, 76th Cong., 1st Sess. H. Doc. 704, 79th Cong., 2d Sess. H. Doc. 704, 79th Cong., 2d Sess. 37-36 5. 7. 8. PORTLAND, OREGON DISTRICT AUTHORIZING LEGISLATION See Date Section Authorizing in Text Act Project and Work Authorized Documents July 24, 1946 July 24, 1946 July 14, 1960 June 25, 1910 Mar. 2, 1919 Sep. 22, 1922 Jan. 21, 1927 July 3, 1930 Aug. 30, 1935 July 24, 1946 June 30, 1948 Dec. 31, 1970 June 3, 1896 June 30, 1948 June 25, 1910 Mar. 2, 1919 July 3, 1930 Aug. 30, 1935 Dec 22, 1944 as amended Mar. 2, 1945 9. Construct a barge channel at Bingen, WA, 10 feet deep, 200 feet wide, by 1 mile long, and an access channel 7 feet deep, 100 feet wide, by 1,000 feet long to natural mooring basin. Construct The Dalles Harbor 8 feet deep, 400 feet wide by 800 feet long. COLUMBIA RIVER, ILWACO, WA. Deepening of the channel a distance of 3 miles to provide improved access to the Ilwaco small boat basin. COOS BAY, OR Dredging the Ocean Bar Channel. A channel 22 feet deep to Smith's Mill. Restore North Jetty 9,600 feet long, construct a South Jetty about 3,900 feet long, extend 22-foot bay channel from Smith's Mill to Millington. Extend jetties to such lengths as may be practicable within estimate of total cost of jetties, $3,250,000 given in H. Doc. 150, 67th Cong. A channel 24 feet deep and 300 feet wide, through Pigeon Point Reef, following a location along westerly side of bay. For 24-foot channel from Pigeon Point Reef to Smith's Mill and a turning basin above Marshfield. Increased dimensions of channel across bar and to Isthmus Slough and turning basin opposite Coalbank Slough and at city of North Bend; anchorage basins at mile 3.5 and near mile 7. A mooring basin and connecting channel at Charleston. Increase dimensions to provide for bar channel 45 feet deep, inner channel 35 feet deep to mile 15, and deepening and widening existing turning basins and anchorage area. COOS AND MILLICOMA RIVERS, OR Dredging shannel from mouth to head of navigation. For a 5 ft. depth from mouth to head of navigation on the Millicoma River and South Fork. Except on South Fork above M. 14 where 3 ft. will suffice. COQUILLE RIVER, OR Dredging shoals between mouth and Riverton, and removing obstruction between mouth of North Fork and Bandon For a 13-foot channel from ocean to Bandon Deepen channel to 16 feet between sea and eastern end of North Jetty. Present project depth between sea and eastern end of North Jetty. Construction, operation, and maintenance of recreation facilities. For 13-foot depth from sea to a point 1 mile above Coquille River Lighthouse and snagging to State Highway Bridge. 37-37 TABLE 37-B (Continued) H. Doc. 704, 79th Cong., 2d Sess. S. Doc. 89, 79th Cong., 1st Sess? Section 107, P.L. 86-645, Authorized by Chief of Engineers, Oct. 22, 1984. H. Doc. 958, 60th Cong., 1st Sess. H. Doc. 325, 65th Cong., 1st Sess. H. Doc. 150, 67th Cong., 2d Sess. H. Doc. 320, 69th Cong., 1st Sess. H. Doc. 110, 70th Cong., 1st Sess 1 S. Committee Print, 73d Cong., 2d Sess? S. Doc. 253, 79th Cong., 2d Sess. H. Doc. 646, 80th Cong., 2nd Sess. H. Doc. 151, 91st Cong., 2d Sess. H. Doc. 237, 53d Cong., 3d Sess. S. Doc 124, 80th Cong., 2d Sess. H. Doc. 673, 61st Cong., 2d Sess. H. Doc. 207, 65th Cong., 1st Sess. H. Doc. 186, 70th Cong., 1st Sess? S. Committee Print, 74th Cong., 1st Sess. Sec. 4, Flood Control Act of 1944 H. Doc. 672, 76th Cong., 2d Sess? 10. 11. 12. REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 37-B (Continued) AUTHORIZING LEGISLATION See Date Section Authorizing in Text Act Project and Work Authorized Documents 14. 13. June 25, 1910 June 25, 1910 Aug. 26, 1937 Mar. 2, 1945 Mar. 3, 1897 Mar. 4, 1913 July 25, 1912 Oct. 27, 1965 Dec. 31, 1970 Sep. 3, 1954 Sep. 19, 1890 June 25, 1910 Mar. 3, 1925 July 3, 1958 Oct 22, 1976 Oct. 1, 1980 Mar. 2, 1919 July 3, 1930 Aug. 26, 1937 June 30, 1948 37-38 COWLITZ RIVER, WA lb provide a channel 4 feet deep from mouth to Ostrander, 2.5 ft. deep to Castle Rock. Extend channel to Tobledo. DEPOE BAY, OR Construction of inner basin 375 feet long, 125 feet wide and 5 feet deep, with entrance channel of same depth and 50 feet wide. Construction of inner basin 750 feet long, 390 feet wide and 8 feet deep, with entrance channel at same depth and 30 feet wide. LEWIS RIVER, WA Provide a channel to head of navigation. Increase the control depth and widen channel. NEHALEM BAY, OR Two rubble-stone jetties. PORT ORFORD, OR Extension of existing breakwater by 550 feet. Dredging of turning basin 340 feet long, 100 feet wide, 16 feet deep. ROGUE RIVER HARBOR AT GOLD BEACH, OR Two jetties at entrance and improvement of channel. SIUSLAW RIVER, OR Build two high-tide stone jetties. Extends North Jetty 3,700 feet from old work constructed under previous project and provides for 4,200 foot South Jetty. 12-foot deep channel. 18-foot bar channel and 16-foot river channel and a 600-foot extension of North Jetty. (600-foot extension classified deferred.) Phase I advance engineering and design for north and south jetty extensions. Extending north and south jetties about 2,000 and 2,500 feet, respectively. SKAMOKAWA CREEK, WA Channel 6.5 feet deep and 75 feet wide, at low water between Steamboat and Brooks Slough. SKIPANON CHANNEL, OR Channel from deep water in Columbia River to railroad bridge. Channel extending upstream from railroad bridge a distance of 4,500 feet. Mooring basin 12 feet deep at Warrenton. H. Doc. 1167, 60th Cong., 2d Sess. H. Doc. 404, 61st Cong., 2d Sess. H. Doc. 202, 75th Cong., 1st Sess. H. Doc. 350, 77th Cong., 1st Sess. H. Doc. 64, 55th Cong., 1st Sess. H. Doc. 28, 62d Cong., 1st Sess. H. Doc. 623, 62d Cong., 2d Sess. S. Doc. 62, 88th Cong., 2d Sess. H. Doc. 151, 91st Cong., 2d Sess. S. Doc. 83, 83d Cong., 2d Sess. H. Doc. 71, 51st Cong., 1st Sess. H. Doc. 648, 61st Cong., 2d Sess. S. Committee Print, Serial, 68th Cong., 1st Sess. H. Doc. 204, 85th Cong., 1st Sess.' Final Report of Chief of Engineers P.L. 96-367 H. Doc. 3, 63rd Cong., 1st Sess. H. Doc. 278, 70th Cong., 1st Sess' H. Doc. 201, 75th Cong., 1st Sess,.' S. Doc. 95, 81st Cong., 1st Sess. 15. 17. 18. 20. 21. 22. 23. PORTLAND, OREGON DISTRICT AUTHORIZING LEGISLATION See Date Section Authorizing in Text Act Project and Work Authorized Documents 25. 24. July 14, 1960 July 26, 1912 Mar. 4, 1913 Mar. 2, 1919 Mar. 3, 1925 Mar. 2, 1945 June 30, 1948 Sep. 3, 1954 Oct. 27, 1965 Spe. 22, 1922 Jan. 21, 1927 July 3, 1930 Aug. 30, 1935 June 20, 1938 Mar. 2, 1945 Mar. 2, 1945 June 30, 1948 Sep. 3, 1954 June 3, 1896 June 3, 1896 37-39 TABLE 37-B (Continued) SOUTH CHANNEL, GOVERNMENT ISLAND, OR A small boat recreational channel 6 feet deep and 100 feet wide between River Mile 111.8 and 118.4. TILLAMOOK BAY AND BAR, OR Construct North Jetty 5,700 feet long and dredging channel 16 feet deep, 200 feet wide, to Bay City. Abandon that portion of project above Bay City. Abandon Bay City Channel and present project dimension of channels and turning basins with regulating works as needed.' Repair damage and check erosion on Bayocean Peninsula caused by storm Jan. 1939. Dredging small-boat basin and approach at Garibaldi, OR, to depth of 12 feet. Closure of breach in Bayocean Peninsula. Construct South Jetty, 8,000 feet long. UMPQUA RIVER, OR North Jetty, 7,500 feet long. Present project dimensions of North Jetty and dredging ocean bar. A short south jetty. A full length south jetty and maintenance dredging to a 26-foot depth. Channel 22 feet deep and 200 feet wide from mouth to Reedsport Channel 22 feet deep and 200 feet wide from river channel to Gardiner, and turning basin 22 feet deep, 500 feet wide and 800 feet long. Channel 10 feet deep and 100 feet wide from river channel to dock in Winchester Bay with mooring and turning basin 10 feet deep, 175 feet wide, and 300 feet long at inner end. Channel 12 feet deep and 100 feet wide from river channel to dock in Winchester Bay with mooring and turning basin 12 feet deep, 175 feet wide, and 300 feet long at inner end. Channel 12 feet deep, Scholfield River.s WILLAMETTE RIVER ABOVE PORTLAND AND YAMHILL RIVER, OR Improvement of Willamette River above Oregon City. Improvement of Yamhill River by lock and dam construction. Project modified in 1904 by abandoning 20-mile stretch of river between Harrisburg and Eugene as unworthy of improvement. Section 107, P.L. 86-645 Authorized by Chief of Engineers July 25, 1983 H. Doc 349, 62d Cong., 2d Sess. H. Doc 760, 65th Cong., 2d Sess. H. Doc. 562, 68th Cong., 2d Sess. S. Doc. 35, 79th Cong., 1st Sess. H. Doc. 650, 80th Cong., 1st Sess. S. Doc. 128, 83d Cong., 2d Sess.' S. Doc. 43, 89th Cong., 1st Sess. H. Doc. 913, 65th Cong., 2d Sess. H. Doc. 320, 69th Cong., 1st Sess. H. Doc. 317, 70th Cong., 1st Sess Rivers and Harbors Committee Doc. 9, 72d Cong., 1st Sess.' S. Doc. 158, 75th Cong., 3d Sess?1 S. Doc. 86, 76th Cong., 1st Sess S. Doc. 191, 77th Cong., 2d Sess? S. Doc. 154, 80th Cong., 2d Sess? S. Doc. 133, 81st Cong., 2d Sess? H. Doc. 260, 54th Cong., 1st Sess. (Annual Report, 1896, p. 3300) Annual Report, 1895, p. 3602 Annual Report, 1904, p. 3529 26. 27. REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 37-B (Continued) AUTHORIZING LEGISLATION See Date Section Authorizing in Text Act Project and Work Authorized Documents July 25, 1912 June 26, 19346 June 28, 19387 28. June 25, 1910 Aug. 8, 1917 June 26, 19346 Mar. 2, 1945 July 14, 1960 Mar. 2, 1919 Aug. 26, 1937 Mar. 2, 1945 July 24, 1946 July 3, 1958 July 14, 1960 31. Oct. 23, 1962 Mar. 7, 1974 A 6-foot channel in Willamette River below Oregon City. Operating and care of lock and dam at Yamhill River and provided for with funds from War Department appropriations for rivers and harbors. Streamflow regulation with controlling depths of 6 feet to mouth of Santiam River and 5 feet to Albany with enlargement of locks at Oregon City? Operation of Yamhill Lock was discontinued Feb. 7, 1954, and the lock and adjacent property turned over to Yamhill County Jan. 16, 1959. WILLAMETTE RIVER AT WILLAMETTE FALLS, OR For purchase and rehabilitation of system and construction of concrete division wall. Deepening of locks Operation and care of canal and locks provided for with funds from War Department appropriations for Rivers and Harbors. Construction of New Willamette Falls Locks 8 WINCHESTER BAY, UMPQUA RIVER, OR Channel 16 feet deep, 100 feet wide, changing to 75 feet wide by 12 feet deep in Winchester Bay; channel 100 feet wide, 16 feet deep, 4,100 feet long to turning basin 160 feet wide, 16 feet deep and 200 feet long in west basin. YAQUINA BAY AND HARBOR, OR Restoration and extension of jetties constructed under previous projects, rock removal at entrance, and dredging in bay up to railroad terminus at Yaquina. Extension of north jetty seaward 1,000 feet. 26-foot channel of suitable width across entrance bar, so far as rock bottom will allow, a 20-foot channel 300 feet wide along south side of bay to and including a turning basin 22 feet deep, 1,000 feet wide and 1,200 feet long. Construct a small-boat mooring basin at Newport, OR. 40-foot bar channel and 30-foot river channel extension of jetties at entrance. A small boat basin, south shore. APPLEGATE LAKE, ROGUE RIVER BASIN, OR Authorizes a rockfill embankment dam. Authorizes construction of project but no operation for ' irrigation until local interests agree to repay cost allocated. H. Doc. 438, 62d Cong., 2d Sess. H. Doc. 554, 75th Cong., 3d Sess. H. Doc. 202, 56th Cong., 1st Sess. and Annual Report, 1900, P. 4374 H. Doc. 1060, 62d Cong., 3d Sess. H. Doc. 544, 75th Cong., 3d Sess. Sec. 107, P.L. 86-645 Authorized by Chief of Engineers, July 6, 1982. H. Doc. 109, 65th Cong., 1st Sess. S. Committee Print, 75th Cong., 1st Sess. S. Doc. 119, 77th Cong., 1st Sess' S. Doc. 246, 79th Cong., 2d Sess. S. Doc. 8, 85th Cong., 1st Sess.' Section 107, P.L. 86-645 Authorized by Chief of Engineers, Mar. 4, 1977 H. Doc. 566, 87th Cong., 2d Sess. P.L. 93-251 37-40 29. 30. PORTLAND, OREGON DISTRICT AUTHORIZING LEGISLATION See Date Section Authorizing in Text Act Project and Work Authorized Documents 32. 33. 43. May 17, 1950 44. 45. May 17, 1950 July 24, 1946 May 17, 1950 June 28, 1938 Dec. 22, 1944 as amended June 28, 1938 Dec. 22, 1944 as amended Oct 23, 1962 Oct. 7, 1970 May 17, 1950 Dec. 22, 1944 as amended June 28, 1938 Dec. 22, 1944 as amended Oct. 23, 1962 July 24, 1946 July 24, 1946 BLUE RIVER LAKE, OR Authorizes gravel-filled embankment dam. COTTAGE GROVE LAKE, OR Earthfill dam. Construction, operation, and maintenance of recreation facilities. DORENA LAKE, OR Earthfill dam. Construction, operation, and maintenance of recreation facilities. ELK CREEK LAKE, ROGUE RIVER BASIN, OR Rock and gravel embankment dam. Authorizes construction but not operation for irrigation until local interests agree to repay cost allocated. FALL CREEK LAKE, OR Earth and gravel fill embankment dam. Construction, operation, and maintenance of recreation facilities. FERN RIDGE LAKE, OR Earthfill embankment dam. Construction, operation, and maintenance of recreation facilities. Raise height of dam to obtain additional storage. HUNTINGTON AVE, CASTLE ROCK, WA Construction of riprap bank protection. JOHN DAY RIVER (WEST), OR Construction of riprap bank protection. LOWER COLUMBIA RIVER BASIN, OR AND WA Bank protection work, improvements to existing projects, and construction of flood control works in Lower Columbia River Basin. LOWER COLUMBIA RIVER BASIN BANK PROTECTION, OR AND WA Provides bank protection on Columbia River below river mile 125 and along principal tributaries. MC DONALD DIKE ROAD, NEHALEM RIVER, OR Construction of riprap bank protection. 37-41 TABLE 37-B (Continued) H. Doc. 531, 81st Cong., 2d Sess. H. Doc. 544, 75th Cong., 3d Sess. Sec. 4, Flood Control Act of 1944 H. Doc. 544, 75th Cong., 3d Sess. Sec. 4, Flood Control Act of 1944 H. Doc. 566, 87th Cong., 2d Sess. P.L. 91-439 H. Doc. 531, 81st Cong., 2d Sess. Sec. 4, Flood Control Act of 1944 H. Doc. 544, 75th Cong., 3d Sess. Sec. 4, Flood Control Act of 1944 H. Doc. 403, 87th Cong., 2d Sess. Section 14, P.L. 79-526 Authorized by Chief of Engineers, Oct. 18, 1983 Section 14, P.L. 79-526 Authorized by Chief of Engineers, July 25, 1985 H. Doc. 531, 81st Cong., 2d Sess. H. Doc. 531, 81st Cong., 2d Sess. Sec. 14, P.L. 79-526 Authorized by Chief of Engineers, Dec. 1, 1983 34. 3355. . 36. 37. 38. 42. REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 37-B (Continued) AUTHORIZING LEGISLATION See Date Section Authorizing in Text Act Project and Work Authorized Documents A4 MT' T HTQ A I VTT TYTTV IWA July 30, 1983 July 24, 1946 July 24, 1946 June 30, 1948 July 24, 1946 May 17, 1950 July 24, 1946 June 28, 1938 May 17, 1950 June 22, 1936 June 28, 1938 May 17, 1950 Oct. 27, 1965 47. 49. P.L. 98-63 TU. 37-42 . . .z, VAAA iAWA iiJJVL, .IJ AA AA I WVL Implement and maintain flood control measures on the Cowlitz and Toutle Rivers to assure flood protection for developed areas in the vicinity of such rivers against a one-hundred-year flood and to reduce sedimentation flow and the chance of blockage on the Columbia River. SALMON CREEK, NEAR VANCOUVER, WA Construction of riprap bank protection. STATE HWY. 101 & 401, COLUMBIA RIVER, WA Construction of riprap bank protection. TUALATIN, OR Deepening an approximately one mile long reach of the Tualatin River. UMATILLA RIVER, THORN HOLLOW, OR Construction of riprap bank protection. WAHKIAKIM COUNTY CONSOLIDATED DIKING DISTRICT NO. 1, WA Raising and strengthening all levees encircling islands. Construct drainage canal, tide box and pumping plant. WEST MAKINSTER ROAD, WILSON RIVER, OR Construction of riprap protection. WILLAMETTE RIVER BASIN, OR Comprehensive plan for flood control, navigation and other purposes in Willamette River Basin. General improvements. WILLAMETTE RIVER BASIN BANK PROTECTION, OR Bank protection works, with channel clearing. Provide additional protection against flooding. Addition of 77 locations to scope of projects. WILLOW CREEK LAKE, OR Storage project for flood control, recreation, and fish and wildlife. BONNEVILLE LOCK AND DAM-BONNEVILLE LAKE, OR AND WA Existing project was originally authorized Sep. 30, 1933, by Federal Emergency Administration of Public Works. 50. 51. 52. 53. 54. 55. 56. 57. Sec. 14, P.L. 79-526 Authorized by Chief of Engineers, Jan. 20, 1983 Sec. 14, P.L. 79-526 Authorized by Chief of Engineers, Aug. 8, 1984 Section 205, P.L. 80-858 Authorized by Chief of Engineers, April 19, 1983 Sec. 14, P.L. 79-526 Authorized by Chief of Engineers, Sep. 26, 1983 H. Doc. 531, 81st Cong., 2d Sess. Sec. 14, P.L. 79-526 Authorized by Chief of Engineers, July 3, 1985 H. Doc. 544, 75th Cong., 3d Sess. H. Doc. 531, 81st Cong., 2d Sess. F.C. Act 1936 H. Doc. 544, 75th Cong., 3d Sess. H. Doc. 531, 81st Cong., 2d Sess. H. Doc. 233, 89th Cong., 1st Sess. PORTLAND, OREGON DISTRICT AUTHORIZING LEGISLATION See Date Section Authorizing in Text Act Project and Work Authorized Documents Aug. 30, 1935 Aug. 20, 1937 Dec. 22, 1944 as amended Mar. 7, 1974 Aug. 22, 1984 May 17, 1950 Sep. 3, 1954 Oct. 23, 1962 June 28, 1938 June 30, 1948 May 17, 1950 Sep. 3, 1954 July 14, 1960 May 17, 1950 May 17, 1950 Dec. 22, 1944 as amended Mar. 24, 1965 June 28, 1938 Dec. 22, 1944 as amended May 17, 1950 Sep. 21, 1962 Oct 15, 1966 Existing project authorized by Congress. Completion, maintenance, and operation of Bonneville Project under direction of Secretary of War and supervision of Chief of Engineers, subject to certain provisions herein relating to powers and duties of Bonneville Power Administrator. Construction, operation, and maintenance of recreation facilities. Authorizes relocation of town of North Bonneville to new town site. Acquisition of Steigerwald Lake wetland area. COUGAR LAKE, OR Rockfill dam. Addition of power. Strube Lake reregulating dam. DETROIT LAKE, OR Authorizes concrete gravity structure. Addition of power and regulating Big Cliff Dam with power. GREEN PETER-FOSTER LAKES, OR Authorized Green-Peter Dam in lieu of originally authorized Sweet Home Lake (1938). Addition of power at Green-Peter and White Bridge Reregulating Dam. Changes location of reregulating dam from White Bridge location to Foster. HILLS CREEK LAKE, OR Earth and gravel fill dam. JOHN DAY LOCK AND DAM-LAKE UMATILLA, OR AND WA Multiple-purpose dam, flood control, navigation and power. Construction, operation, and maintenance of recreation facilities. John Day waterfowl management area. LOOKOUT POINT LAKE, OR Earth-and-gravel filled dam. Construction, operation, and maintenance of recreation facilities. Addition of power and authorization of Dexter Lake as reregulating dam. LOST CREEK LAKE, ROGUE RIVER BASIN, OR Rock and gravel fill embankment dam, including power. Authorizes construction of project but not operation for irrigation until local interests agree to repay cost allocated. S. Committee Print, 73d Cong., 2d Sess., (Report of Chief of Engineers dated Aug. 21, 1933) Sec. 4, Flood Control Act of 1944 P.L. 93-251 P.L. 98-396 H. Doc. 531, 81st Cong., 2d Sess. P.L. 83-780 P.L. 87-874 H. Doc. 544, 75th Cong., 3d Sess. P.L. 858, 80th Cong., 2d Sess. H. Doc. 531, 81st Cong., 2d Sess. P.L. 83-780 F.C. Act 1954 S. Doc 104, 86th Cong., 2d Sess. H. Doc. 531, 81st Cong., 2d Sess. H. Doc. 531, 81st Cong., 2d Sess. Sec. 4, Flood Control Act of 1944. S. Doc. 28, 89th Cong., 1st Sess. H. Doc. 544, 75th Cong., 3d Sess. Sec. 4, Flood Control Act of 1944 H. Doc. 531, 81st Cong., 2d Sess. H. Doc. 566, 87th Cong., 2d Sess. PL. 89-689, Public Works Approp. Act, 1967. 37-43 TABLE 37-B (Continued) 58. 59. 60. 61. 62. 63. 64. REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 37-B (Continued) AUTHORIZING LEGISLATION See Date Section Authorizing in Text Act Project and Work Authorized Documents 65. THE DALLES LOCK AND DAMLAKE CELILO, WA AND OR May 17, 1950 Multiple-purpose dam, flood control, navigation and H. Doc. 531, 81st Cong., power. 2d Sess. Dec. 22, 1944 Construction, operation, and maintenance of Sec. 4, Flood Control as amended recreation facilities. Act of 1944 1Contains latest published maps. 2Public Resolution 105, 67th Cong. 3Public Works Administration "Includes following work, classified inactive. A channel to Hobsonville 200 feet wide and 16 feet deep, with a turning basin 500 feet wide at Hobsonville, and regulating works as needed. "Inactive. 6Permanent Appropriations Repeal Act. 7Flood Control Act. 'Classified deferred. 'Spur Jetty "B" classified inactive. 37-44 PORTLAND, OREGON DISTRICT TABLE 37-C OTHER AUTHORIZED NAVIGATION PROJECTS For Last Cost to Sep. 30, 1985 Full Report Operation See Annual and Project Status Report For Construction Maintenance Alsea River, OR Astoria Turning Basin, OR' Bridges, Columbia River, Cascade Locks and Hood River, OR (Alteration) Cathlamet, WA' Clatskanie River, OR2 Cushman-Mapleton Channels (Siuslaw River), OR' Deep River, WA2 Depoe Bay, OR' Elochoman Slough, WA2 Grays River, WA2 Hammond Small Boat Basin, OR' Interstate Bridge, Columbia River, Portland, OR to Vancouver, WA (Alteration) Interstate Highway Bridge (Barge Channel), OR' Lake River, WA Long Tom River, OR Mooring for Battleship Oregon, OR Multnomah Channel, OR2 Nestucca River, OR Oregon Slough (North Portland Harbor), OR' Salmon River, OR' Smith River, OR' South Slough (Charleston), OR' The Cascades Canal, Columbia River, OR' � The Dalles-Celilo Canal, OR and WA" Umatilla Harbor, OR' 2 Westport Slough, OR' Yaquina Bay and Harbor Small Boat Basin, OR' Yaquina River, OR' Yaquina River, OR Youngs and Klaskanine River, OR Youngs Bay and Youngs River, OR'2 'Authorized by Chief of Engineers (Sec. 107). 2Channel adequate for present commerce. 'Includes $15,537 for previous project. 'Includes $23,489 for previous project. 'Excludes $42,000 contributed funds. 'Excludes $86,586 contributed funds. 7Excludes $75,000 contributed funds. 'Non-Federal funds, $1,204,100. 'Includes $419,557 for Sec. 107 project. Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Abandoned Abandoned Abandoned Completed Completed Completed Completed Completed Completed 1977 1944 1971 1969 1975 1963 1971 1971 1941 1977 1961 1963 1983 1982 1963 1949 1974 1970 1939 1957 1952 1966 1979 1971 1984 1979 2,000 870,139 1,081,806 171,467 19,240'3 329,423 15,384 145,588' 18,641' 2,500 519,0907 1,154,162' 15,281 2,700 4,000 26,237 - 194,8934 32,768 16,648 35,670 58,127 25,000 437,669' 6,000 16,881 2,145 143,120 26,821 3,903,780 4,716,205 16,276 891,695"3 195,313 4 28,800 2,000 9,348 'OProject abandoned due to flooding by 90,514 205,130 559,858 2,833,888 171,909 749,351"15 34,449 Bonneville Dam pool. "Project abandoned due to flooding by The Dalles Dam pool. "Project transferred to Portland District from Walla Walla District FY 1974 and abandoned due to flooding by the John Day Dam pool. "Excludes $969,342 contributed funds. "Excludes $50,565 contributed funds. "Excludes $3,000 contributed funds. 37-45 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 37-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS For Last Cost to Sep. 30, 1985 Full Report Operation See Annual and Project Status Report For Construction Maintenance COLUMBIA RIVER BASIN Blind Slough Diking District, Clatsop County, OR Completed 1939 163,397- Consolidated Diking and Improvement District 1, Cowlitz County, WA Completed 1941 163,291- Deep River Area, Wahkiakum County, WA Completed 1942 69,724- Deer Island Area, Columbia County, OR Completed 1943 574,123- Diking District 2, Clatsop County, OR Completed 1940 43,150- Diking Dist 5, Clatsop County, OR Completed 1940 25,609- Diking and Improvement District 5, Cowlitz County, WA Completed 1940 161,381- Diking District 1 and 3 (Puget Island) and Little Island, Wahkiakum County, WA Completed 1941 258,795- Diking Improvement District 1, Pacific County, WA Completed 1941 26,810- Diking and Improvement District 4, Wahkiakum County, WA Completed 1951 169,542- Drainage District 1, Clatsop County, OR Completed 1939 240,939- John Day River Area, Clatsop County, OR Completed 1942 33,080- Karlson Island, Clatsop County, OR Completed 1941 25,773 - Knappa Area, Clatsop County, OR Completed 1942 18,789 - Lewis and Clark River Area, Clatsop County, OR Completed 1942 158,419- Lower Cowlitz River Area, Clatsop County, OR Completed 1962 181,652- Magruder Drainage District, Columbia County, OR Completed 1940 61,186- Marshland Drainage District, Columbia County, OR Completed 1940 39,475- Midland Drainage District Columbia County, OR Completed 1939 77,7743 - Multnomah Drainage District 1, OR Completed 1951 593,0344 -- Peninsula Drainage District 1, Multnomah County, OR Completed 1942 211,160- Peninsula Drainage District 2, Multnomah County, OR CQrompleted 1942 241,148 - Port of Kalama, WA1 Completed - 99,844 - Rainier Drainage District, Columbia County, OR Completed 1942 47,662 Sauvie Island Areas A and B, Multnomah County, OR Completed 1951 1,623,505 - Scappoose Drainage District, OR Completed 1984 3,991,558 - Skamokawa Creek Area, Wahkiakum County, WA Completed 1946 178,885 Tenasillahe Island, Clatsop County, OR Completed 1939 133,778 - Upper Grays River Area, WA Completed 1947 61,263 - Walluski River, Clatsop County, OR Completed 1942 66,932 37-46 TABLE 37-E (Continued) PORTLAND, OREGON DISTRICT OTHER AUTHORIZED FLOOD CONTROL PROJECTS For Last Cost to Sep. 30, 1985 Full Report Operation See Annual and Project Status Report For Construction Maintenance Warrenton Diking District 1, Clatsop County, OR Completed 1940 69,503- Warrenton Diking District 2, Clatsop County, OR Completed 1940 117,143- Warrenton Diking District 3, Clatsop County, OR Completed 1940 74,596- Webb District Improvement Co., Columbia County, OR Completed 1940 84,592- Westland District Improvement Co., Columbia County, OR Completed 1940 205,531- Westport District, Columbia and Clatsop Counties, OR Completed 1943 40,658- Woodson Drainage District, Columbia County, OR Completed 1940 22,797- Youngs River Dikes, Clatsop County, OR Completed 1942 248,802 - Total Columbia River Basin 10,605,300 - LEWIS RIVER BASIN Diking and Improvement District 11, Cowlitz County, WA Completed 1943 172,521- COWLITZ RIVER BASIN Cowlitz County Drainage Improvement District 1, WA Completed 1939 42,978- Diking Improvement District 2, Cowlitz County, WA Completed 1940 121,165- Diking Improvement District 13, Cowlitz County, WA Completed 1939 28,592 - Total Cowlitz River Basin 192,735 - LOWER COLUMBIA RIVER BASIN Beaver Drainage District, OR Completed 1984 3,131,944 - Columbia Drainage District 1, OR Inactive - - - Cowlitz County Consolidated Diking Improvement District No. 2, WA Completed 1977 1,661,367- Cowlitz County Diking Improvement District 2, WA Completed 1967 363,000- Cowlitz County Diking Improvement District 13, WA Completed 1967 65,345- Cowlitz County Diking Improvement District 15, WA Completed 1967 304,794 - Cowlitz River, Hopkins Creek, WA' Completed - 236,860 - Deer Island Drainage District, OR Inactive - - - Hayden Island, OR Inactive 1950 - - Midland Drainage District, OR Completed 1971 304,511 - Multnomah County Drainage District 1, OR Completed 1964 1,499,186 - Peninsula Drainage District 2, OR Active 1961 35,265 - Rainier Drainage District, OR Completed 1967 593,945 - Sandy Drainage District, OR Completed 1954 154,012 - Sauvie Island Drainage District, OR Completed 1966 674,137 - Vancouver Lake Area, WA Deferred 1981 889,391 - Wahkiakum Co. Diking District 4, WA Inactive 1971 48,619 Washougal Area Levees, Clark County, WA Completed 1973 1,803,488 - Woodson Drainage District, OR Completed 1964 162,500 - 37-47 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 37-E OTHER AUTHORIZED FLOOD (Continued) CONTROL PROJECTS For Last Cost to Sep. 30, 1985 Full Report Operation See Annual and Project Status Report For Construction Maintenance Total Lower Columbia River Basin 11,928,364- WILLAMETTE RIVER BASIN Amazon Creek, OR Completed 1960 1,214,3006 - Cascadia Lake, OR Deferred 1976 1,066,114' - Gate Creek Lake, OR Deferred 1972 840,0008 - Holley Lake, OR Deferred 1963 241,992 - Sandy River and Sleppy Hollow, OR1 ,Completed - 276,700 - Shelton Ditch, OR Inactive 1967 39,624 - Willamette River Basin Channel Clearing and Snagging Inactive -- - Total Willamette River Basin 3,678,731 - ALL OTHER FLOOD CONTROL Arlington, Alkali Canyon, OR' Abandoned 1950 23,439 - Bear Creek, Medford, OR1 Completed - 23,050 - Beaver Creek Near Tillamook, OR' Completed 1967 106,198 - Castle Rock, Cowlitz River, WA Completed 1957 104,921 - Catching Inlet Drainage District Coos River, OR' Completed 1959 182,655 - Chewaucan River, Paisley, OR1 Completed - 42,761 - Clackamas River at Dixon Farm Location, OR' Completed 1952 70,84510- Days Creek Lake, OR (Phase I) Deferred 1982 1,307,216 - Depoe Bay, Lincoln County, OR' Completed - 22,963 - Johnson Creek, OR Active 1981 170,245 - McKenzie River Near Walterville, OR' Completed 1967 148,358 - Miami River, OR' Completed - 15,321 - Mill Four Drainage District, Yaquina River, OR Completed 1948 118,433- Molalla River at Milk Creek Location, OR' Completed 1955 55,007- Molalla River at Ressel Location, OR' Completed 1952 55,189 - Nestucca River, Condor Road, OR' Completed - 11,690 - Nestucca River, Vicinity Pacific City, OR' Completed - 16,000- Pendleton Levees, Umatilla River, OR" (a)Riverside Area Units Deferred 1960 9,100- (b)State Hospital and City Areas (Zone 1) Completed 1959 267,748- (c)State Hospital and City Areas (Zone 2)2 Completed 1960 161,540- Pendleton, Umatilla River, OR'� Completed 1939 143,263- Reedsport Levees, Umpqua River, OR' Completed 1971 968,716" - Rogue River, OR' Completed - 86,230 - Salmon Creek at Oakridge, OR' Completed 1960 288,447 Siuslaw River, Lane County, OR' Completed - 215,939 Stillwell Drainage District, Tillamook Bay, OR' Completed 1961 176,351 - Sumner Parker Airport, OR' Completed - 92,500 - Trask River, Tillamook County, OR" Completed 1984 121,273 - Umatilla River, Stanfield, OR' Completed - 33,835 - Umpqua River and Tributaries, OR Completed 1952 428,881 37-48 TABLE 37-E (Continued) PORTLAND, OREGON DISTRICT OTHER AUTHORIZED FLOOD CONTROL PROJECTS For Last Cost to Sep. 30, 1985 Full Report Operation See Annual and Project Status Report For Construction Maintenance Vicinity of Nehalem, Nehalem River, OR Completed 1952 45,677 Wilson River, Vicinity Highway 101, OR' Completed - 30,000 - Total All Other Flood Control - 5,543,791 - 1Authorized by Chief of Engineers (Sec. 14). 2Authorized by Chief of Engineers (Sec. 205). 3Includes $26,241, Emergency Relief Act funds. 'Excludes $25,000 contributed funds. 3Previous completed project, $138,956; $15,056 engineering costs project constructed by local interests. 6Excludes $154,751 contributed funds. 7Includes $112,000 pro rata share of site selection in lieu of Sweet Home. 6Includes $95,000 pro rata share of site selection in lieu of Quartz Creek Lake. *Project transferred from Walla Walla District FY 1974 and abandoned due to flooding by the John Day Dam pool. Includes $3,328 FY 1960 preauthorization costs, Sec. 205, P.L. 80-858. See FY 1960 Annual Report, page 1887. 10Excludes $2,520 contributed funds. "Reported by Walla Walla District prior to 1974. 12Excludes $230,070 constributed funds for new work and $31,284 Government furnished sheet steel pile. 37-49 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 37-F OTHER AUTHORIZED MULTIPLE PURPOSE PROJECTS, INCLUDING POWER For Last Cost to Sep. 30, 1985 Full Report See Annual Operation and Project Status Report For Construction Maintenance Restoration of Indian Fishing Grounds, Bonneville, OR Completed 1969 185,000 TABLE 37-G DEAUTHORIZED PROJECTS For Last Contri- Full Report Date Federal buted See Annual Deauth- Funds Funds Project Report For orized Expended Expended Area East of Albany, OR - 1977 - - Bachelor Island, WA - 1977 - - Bear Creek, Long Tom River, OR 1966 1971 4,559 - Calapooya River, OR 1959 1965 11,595 - Clatskanie River Area, Columbia County, OR 1960 1965 268 - Clatskanie Drainage Dist. 1, OR 1964 1978 18,543 - Clatsop County Drainage District 1, OR 1960 1974 4,472 - Clatsop County Diking District 3, OR 1938 1961 258 - Clatsop County, Diking District 4, OR - 1978 - - Clatsop County Diking District 6, OR 1961 1978 8,824 - Columbia Slough, OR 1953 1978 21,352 - Coquille River, OR 1948 1953 908 - Cowlitz County Consolidated Diking Improvement Dist. 1, OR - 1977 - - Cowlitz River at Randle, WA 1962 1977 11,095 - Coyote and Spencer Creek, Long Tom River, OR 1960 1970 6,819 - East Muddy and Lake Creek, OR 1959 1970 6,465 - Ferguson Creek, Long Tom River, OR - 1978 - - Flat Creek, Long Tom River, OR - 1977 - - Floodwall and Levees at Portland, OR - 1977 - - John Drainage District, OR 1961 1979 23,754 - John Day River, OR 1974 1974 210,220 - Kalama River (South Area) Levee, Cowlitz County, WA 1969 1978 55,594 - Lake River Delta Area, WA - 1977 - - Lewis River Area, WA - 1978 - - Magruder Drainage District, OR 1940 1974 774 - Mud and Basket Slough Rickreall Creek, OR - 1977 - - Peninsula Drainage District 1, OR 1942 1977 43,292 - Pilot Rock, Birch Creek, OR 1963 1968 4,558 - Prescott Area, Columbia County, OR 1941 1978 125 - Prineville Area, Crooked River and Ochoco Creek, OR 1962 1977 11,318 - Pudding River, OR 1950 1979 5,000 - Skamokawa (Steamboat Slough), WA 1939 1979 - - Soap Creek, WA - 1977 - - Turner Prarie, Mill Creek, OR - 1978 - - Umatilla River (Echo), OR 1960 1964 24,145 - Waldo Lake Tunnel, OR - 1958 - - West Muddy Creek and Mary's River, OR 1962 1970 4,056 - Westport Slough, OR (Modification for 32-foot channel) 1966 1977 - - Wiley Creek Lake, OR - 1960 112,000 - Willamette Falls Fishladder, OR - 1961 - - 37-50 PORTLAND, OREGON DISTRICT TABLE 37-H COLUMBIA AND LOWER WILLAMETTE RIVER BELOW VANCOUVER, WA, AND PORTLAND, OR TOTAL COST OF EXISTING PROJECT TO SEP. 30, 1985 (See Section 4 of Text) Funds New Work Maintenance Total Regular 26,235,146 223,329,949 249,565,095 Public Works 446,296 14,515 460,811 Emergency Relief Administration 138,449 98,668 237,117 Total U.S. 26,819,891 223,443,132 250,263,023 Contributed Prior to 1964 223,026 24,320 247,346 Contributed (1975) 35 to 40-foot Channel 442,928 - 442,928 Total Contributed 665,954 24,320 690,274 Total All Funds 27,485,845 223,467,452 250,953,297 TABLE 37-I NAVIGATION ACTIVITIES PURSUANT TO SECTION 107, PUBLIC LAW 86-645 (PREAUTHORIZATION) Study Identification Fiscal Year Costs (1985) Astoria Deep Draft Anc, OR $26,359 Kalama Turning Basin, WA 14,878 Skamokawa Creek, WA 7,353 Wind River, WA 4,662 TOTAL $53,252 TABLE 37-J PROJECT CONDITION SURVEYS Project Date Survey Conducted Clatskanie, River, OR August/September 1985 Elochoman Slough, WA December 1984 Lewis River, WA March 1985 Skamokawa Creek, WA March 1985 Willamette River, OR March/May 1985 Yaquina River, OR February/March 1985 Youngs Bay, OR February 1985 TABLE 37-K WILLAMETTE RIVER AT WILLAMETTE FALLS, OR PRINCIPAL FEATURES OF EXISTING CANAL AND LOCKS (See Section 28 of Text) Usable Lock Dimensions Series of 4 locks, each 175 feet by 37 feet' Lift of Each Lock Lock 1 (Lower), 22.5 feet; Lock 2, 8.7 feet; Lock 3, 10.9 feet and Lock 4 (Upper), 8.1 feet2 Depth of Miter Sills at Lower Water Lower Lock, 8.4 feet; Upper Lock, 6 feet Character of Foundation Rock Kind of Dam Fixed3 Type of Construction Concrete Year of Completion 1873; Purchased by United States Apr. 26, 1915 Cost Unknown; purchase price $375,000 'A guard lock 210 by 40 feet, which is used only at higher states of water, is at upper end of canal basin. 'A concrete division wall, 1,227 feet long, extending from Lock 4 to Guard Lock, separates upper basin of canal from head race, which formerly led directly from basin and supplied water for powerplants operated by Crown Zellerbach Corp., and Portland Ry., Light & Power Co., which is now being operated by Portland General Electric Co. 3The dam is owned by private parties. 37-51 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 37-L FLOOD CONTROL ACTIVITIES PURSUANT TO SECTION 205, PUBLIC LAW 80-858 (PREAUTHORIZATION) Study Identification Clatsop County Drainage District Nos. 2 and 5, OR Deschutes River, Bend, OR Libby Dike, Coos County, OR Newton Creek, Roseburg, OR Salmon Creek Levee, Oakridge, OR South Rivergate, OR Tucker and Battle Creeks Dike, OR Warrenton Diking Dist. I, OR Youngs River Dike No. 22, OR TOTAL Fiscal Year Costs (1985) $24,718 28,405 161,933 23,250 36,181 7,500 95,903 24,013 199,032 $ 600,935 37-52 PORTLAND, OREGON DISTRICT TABLE 37-M See Section in Text Proj 31. Appl 32. 33. FLOOD CONTROL RESERVOIR OPERATIONS ject egate Lake, OR Blue River Lake, OR Cottage Grove Lake, OR 58. 59. 34. 36. Cougar Lake, OR Detroit Lake, OR Dorena Lake, OR .Fall Creek Lake, OR 37. Fern Ridge Lake, OR 60. 60. 61. 63. 64. Foster Lake, OR Green Peter Lake, OR Hills Creek Lake, OR Lookout Point Lake, OR Lost Creek Lake, OR 37-53 Date of Peak Inflow November 2, 1984 November 12, 1984 November 2, 1984 November 10, 1984 November 30, 1984 November 2, 1984 November 10, 1984 November 13, 1984 November 30, 1984 November 2, 1984 November 12, 1984 November 30, 1984 November 3, 1984 November 11, 1984 November 30, 1984 November 2, 1984 November 10, 1984 November 30, 1984 November 2, 1984 November 10, 1984 November 14, 1984 November 30, 1984 November 13, 1984 November 29, 1984 November 2, 1984 November 10, 1984 November 30, 1984 November 3, 1984 November 10, 1984 November 28, 1984 November 3, 1984 November 12, 1984 November 30, 1984 November 3, 1984 November 13, 1984 November 30, 1984 November 2, 1984 November 12, 1984 Peak Inflow Cu. Ft./Sec. 1,940 5,050 6,200 3,700 2,100 1,800 1,550 1,800 5,850 6,850 4,100 2,700 18,580 11,030 7,340 9,800 5,350 12,300 6,000 4,550 3,400 7,700 6,150 4,950 14,500 12,320 10,480 17,690 11,680 7,770 6,740 11,750 7,230 18,430 13,540 15,950 5,330 6,450 Storage Used Acre/Feet 2,420 5,200 9,820 5,090 3,690 1,040 3,800 3,800 7,970 19,050 6,240 6,030 56,470 32,610 10,720 16,140 22,690 23,090 9,420 7,250 5,250 12,050 10,160 20,990 670 60 1,010 49,240 6,720 14,900 16,270 20,250 4,790 22,580 35,750 20,040 9,060 1,300 TABLE 37-N REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 LOWER COLUMBIA RIVER BASIN, OR AND WA LEVEES AND IMPROVEMENTS TO EXISTING WORKS (See Section 43 of Text) Estimated Cost of Work Location Approved 1985 Beaver Drainage District, OR Cowlitz County Diking Improvement District 2, WA Cowlitz County Diking Improvement District 13, WA Cowlitz County Diking Improvement District 15, WA Cowlitz County Consolidated Diking Improvement District 2, WA Midland Drainage District, OR Multnomah County Drainage District 1, OR Peninsula Drainage District No. 2, OR Rainier Drainage District, OR Sandy Drainage District, OR Sauvie Island Drainage District, OR Scappoose Drainage District, OR Wahkiakum County Consolidated Diking District 1, WA Woodson Drainage District, OR Total Estimated Cost, Federal Funds Estimated Non-Federal Cost Locations deauthorized or reclassified inactive and excluded from above cost estimate: Bachelor Island, WA (Deauthorized - 1977) Clatskanie Drainage District, OR (Deauthorized - 1978) Clatskanie River Area, OR (Deauthorized - 1965) Clatsop County Drainage District 1, OR (Deauthorized - 1974) Clatsop County Diking District 4, OR (Deauthorized - 1978) Clatsop County Diking District 6, OR (Deauthorized - 1978) Columbia Drainage District 1, OR (Inactive) Cowlitz County Consolidated Diking Improvement District 1, WA (Deauthorized - 1977) Deer Island Drainage District, OR (Inactive) Hayden Island, OR (Inactive) John Drainage District, OR (Deauthorized - 1979) Kalama River Levee, WA (Deauthorized - 1978) Lake River Delta Area, WA (Deauthorized - 1977) Lewis River Area, WA (Deauthorized - 1977) Magruder Drainage District, OR (Deauthorized - 1974) Peninsula Drainage District 1, OR (Deauthorized - 1977) Wahkiakum County Diking District 4, WA (Inactive) 'Cost is for Engineering only. Project was constructed by local interests. 37-54 $ 2,857,366 363,000 65,345 304,794 1,661,367 304,511 1,499,186 3,400,000 593,945 15,056' 674,137 3,567,248 5,289,833 162,500 20,758,288 3,300,000 TABLE 37-0 PORTLAND, OREGON DISTRICT WILLAMETTE RIVER BASIN COMPRENENSIVE PLAN (See Section 54 in Text) Estimated Federal Project Authorizing Act Cost (1985) Blue River Lake, McKenzie Basin 1 Cascadia Lake, South Santiam River' Channel Clearing and Snagging on Willamette River and Major Tributaries Channel Improvements for Flood Control Major Drainage on 16 Streams Tributary to Willamette River' Cottage Grove Lake, Coast Fork' Cougar Lake, South Fork McKenzie' 3 Detroit Lake, Including Big Cliff Lake, North Santiam River' Dorena Lake, Row River' Fall Creek Lake, Middle Fork' Fern Ridge Lake, Long Tom River,' Gate Creek Lake, McKenzie Basin3 S Green Peter-Foster Lakes, Middle Santiam' 4 Hills Creek Lake, Middle Fork' Holley Lake, Calapooya River's Johnson Creek, Vicinity of Portland, OR Lookout Point Lake, Including Dexter Lake, Middle Fork' Strube Lake & Cougar Additional Unit, (South Fork McKenzieX)(Modification to Cougar Lake) Waldo Lake Tunnel and Reregulating Works North Fork, Middle Fork, Willamette River May 17, 1950, H. Doc. 531, 81st Cong., 2d Sess. Oct. 23, 1962, H. Doc. 403, 87th Cong., 2d Sess. May 17, 1950, H. Doc. 531, 81st Cong., 2d Sess. May 17, 1950, H. Doc. 531, 81st Cong., 2d Sess. June 28, 1938, H. Doc. 544, 75th Cong., 3d Sess. May 17, 1950, H. Doc. 531, 81st Cong., 2d Sess. and Sep. 3, 1954, S. Doc. 131, 83d Cong., 2d Sess. June 28, 1938, H. Doc. 544, 75th Cong., 3d Sess. and June 30, 1948, Public Law 858, 80th Cong., 2d Sess. June 28, 1938, H. Doc. 544, 75th Cong., 3d Sess. May 17, 1950, H. Doc. 531, 81st Cong., 2d Sess. June 28, 1938, H. Doc. 544, 75th Cong., 3d Sess. Oct. 23, 1962, H. Doc. 403, 87th Cong., 2d Sess. May 17, 1950, H. Doc. 531, 81st Cong., 2d Sess. and Sep. 3, 1954, S. Doc. 131, 83d Cong., 2d Sess. and July 14, 1960, S. Doc. 104 86th Cong., 2d Sess. May 17, 1950, H. Doc. 531, 81st Cong., 2d Sess. May 17, 1950, H. Doc. 531, 81st Cong., 2d Sess. May 17, 1950, H. Doc. 531, 81st Cong., 2d Sess. June 28, 1938, H. Doc. 544, 75th Cong., 2d Sess. and May 17, 1950, H. Doc. 531, 81st Cong., 2d Sess. Oct. 23, 1962, H. Doc. 403, 87th Cong., 2d Sess. May 17, 1950, H. Doc. 5318, 81st Cong., 2d Sess. $ 32,038,2252 104,000,000 (1975) 3,005,000 (1960) 1,214,3003 4,013,1232 9 56,750,40521 62,729,6982 14,568,2622 9 22,118,2642 9 8,526,9352 9 127,000,000 (1980) 84,005,7882 45,700,6192 13,300,000 (1960) 5,710,000 (1984) 88,238,3952 9 107,000,000 (1984) 37-55 Project Willamette River Bank Protection' 'See individual reports for details of the project. 2Actual cost. 'For construction in lieu of originally authorized Quartz Creek Lake. 4For construction in lieu of originally authorized Sweet Home Lake. 'Project classified deferred. 'Project classified inactive. Estimated Federal Authorizing Act Cost (1985) ne 22, 1936, Special Report 31,400,000 )ivision Engr., June 28, (1984) 1938, H. Doc. 544, 75th Cong., 3d Sess., and May 17, 1950, H. Doc. 531, 81st Cong., 2d Sess. 7Does not include Reclassified Locations. "Authorization rescinded August 28, 1958, Public Law 85-820. 'Includes cost of Recreation Facilities at Completed Projects. (710). l0Does not include $96,000 pro rata share of site selection costs in lieu of Quartz Creek Lake and Strube Lake and Cougar Additional Units. 37-56 TABLE 37-0 (Continued) REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 WILLAMETTE RIVER BASIN COMPREHENSIVE PLAN (See Section 54 of Text) PORTLAND, OREGON DISTRICT TABLE 37-P PRINCIPAL DATA CONCERNING NAVIGATION LOCK, SPILLWAY DAM, AND POWERPLANT Project Bonneville Lock and Dam, OR and WA-Lake Bonneville (See Section 57 of Text) John Day Lock and Dam, OR and WA-Lake Umatilla (See Section 62 of Text) NAVIGATION LOCK Dimensions: Clear Width of Chamber Greatest Length Available for Full Width Lift (Vertical): At Extreme Low Water and Normal Pool Level At Normal River Stage At Extreme High Water Depth Over Miter Sills at Adopted Low Water Character of Foundation Opened to Navigation SPILLWAY DAM Type of Construction Completed Capacity Elevation of Gate Sills on Crest of Spillway Height Above Lowest Foundation Length of Dam Proper Length of Dam Overall Width at Base Gate Openings Crest Overflow (Above Mean Sea Level) Pool Elevation (NormalXAbove Mean Sea Level) POWERPLANT Length Length (Second Powerhouse) Width Width (Second Powerhouse) Height (Roof to Bedrock) Height (Roof to BedrockXSecond Powerhouse) Generator (Station Unit) Generators Generators (Second Powerhouse) Fishwater Supply Units (Second Powerhouse) Total Rated Capacity Speed NAVIGATION Clear Width Clear Length Lift: Minimum Average Maximum Minimum Water Depth Over Sills Opened to Navigation SPILLWAY DAM Type of Construction Completed Maximum Capacity Crest Elevation Control Gates: Type Size, Width by Height Number 76 Feet 500 Feet 66 Feet 59 Feet About 30 Feet 24.2 Feet Andesite January 1938 Concrete Gravity 1938 1,600,000 Cubic Feet Per Second 23.3 Feet About 170 Feet 1,090 Feet 1,230 Feet 200 Feet 18 24 Feet 72 Feet 1,027 Feet 953 190 Feet 235 190 Feet 200 Feet 1-4,000 kw 2 @ 43,200 kw each 8 @ 54,000 kw each 8 @ 66,500 kw each 2 @ 13,100 kw each 1,076,600 kw 75 Revolutions per Minute 86 Feet 669 Feet 97 Feet 105 Feet 113 Feet 15 Feet April 1968 Concrete Gravity March 1968 2,250,000 cfs 210 Tainter 50 Ft. by 58.5 Ft. 20 37-57 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 PRINCIPAL DATA CONCERNING NAVIGATION LOCK, SPILLWAY DAM, AND POWERPLANT Project POWERPLANT The Dalles Lock and Dam, WA and OR-Lake Celilo (See Section 65 of Text) Length Width Generating Units: Number Installed Space for Additional Rating, Each Total Installed Capacity Total Potential Capacity Maximum Structural Height First Power-On-Line IMPOUNDMENT Elevations: Normal Operating Range Maximum Flood Control Storage Lake Length Lake Water Surface Area at Elevation 268 Navigation Channel, Depth by Width Length of Shoreline NAVIGATION LOCK Type Lift Normal Net Clear Length Net Clear Width Normal Depth Over Upper Sill Minimum Depth Over Lower Sill Opened to navigation SPILLWAY DAM Type Elevation of Crest Top of Crest Gates Number of Gates Size of Gates Height (Foundation to Crest) Design Flood POWERPLANT Powerhouse Dimensions Generators Main Units Generators Main Units Fishwater Supply Units Total Rated Capacity Station Service Units 1,975 Feet 243 Feet 16 4 135,000 kw 2,160,000 kw 2,700,000 kw 235 Feet July 1968 268-257 276 500,000 Ac.-Ft. 76.4 Miles 55,000 Acres 15 Ft. by 250 Ft. 200 Miles Single Lift 87.5 Feet 675 Feet 86 Feet 20 Feet 15 Feet March 17, 1957 Controlled 121 Ft. msl 162 Ft msl 23 50 by 43 Feet 120 Feet 2,290,000 cfs 240 by 2,150 Feet 14 @ 78,000 kw each Additional 8 @ 86,000 kw each 2 @ 13,500 kw each 1,807,000 kw 2 @ 3,000 kw each 37-58 TABLE 37-P (Continued) SEATTLE, WA, DISTRICT* This District comprises Washington State except southern and southeastern portions, northern Idaho, and northwestern Montana embraced in drainage basins tributary to Pacific Ocean south of international boundary to Cape Disappointment, and to Columbia River above Yakima River, inclusively. IMPROVEMENTS Navigation 1. Bellingham Harbor, WA ............... 2. East Bay Marina, Olympia Harbor, WA . 3. Ediz Hook, WA ...................... 4. Everett Harbor and Snohomish River, W A .......................... 5. Floating Breakwater Prototype Test Program, West Point, Seattle, WA... 6. Friday Harbor Marina, WA ............ 7. Grays Harbor and Chehalis River, W A .......................... 8. Lake Washington Ship Canal, WA ....... 9. Navigation Work under Special Authorization........................ 10. Project Condition Surveys .............. 11. Puget Sound and its Tributary Waters, WA ................. 12. Quillayute River, WA................. 13. Seattle Harbor, WA ................. 14. Swinomish Channel, WA ............... 15. Waterway Connecting Port Townsend and Oak Bay, WA ..................... 16. Willapa River and Harbor and Naselle River, WA ................... Beach Erosion Control 17. Beach Erosion Work under Special Authorization......................... Flood Control 18. Dungeness River, Sequim, WA .......... 19. Howard A. Hanson Dam, WA ........... 20. Inspection of Completed Flood Control Projects....................... 21. Inspection of Completed PL-99 Works .... 22. Mud Mountain Dam, WA............... 23. Nooksack River, Acme, WA ............. 24. Pilchuck River, WA .................. 25. Placer Creek, ID ...................... 26. Scheduling Flood Control Reservoir Operations ................. Page 38-2 38-2 38-2 27. Stillaguamish River, WA ............... 28. Tacoma, Puyallup River, WA ........... 29. Wynoochee Lake, WA................. Page 38-9 38-9 38-9 38-2 Multiple-Purpose Projects, Including Power 38-3 30. Albeni Falls Dam, ID .................. 38-9 38-3 31. Chief Joseph Dam - Rufus Woods Lake, WA........................... 38-10 38-3 32. Libby Dam - Lake Koocanusa, MT....... 38-10 38-4 General Investigations 38-4 33. Surveys............................. 38-11 38-5 34. Collection and Study of Basic Data.......................... 38-11 38-5 35. Continuation of Planning 38-5 and Engineering ..................... 38-11 38-5 38-6 Tables Table 38-A Cost & Financial Statement .... 38-13 38-6 Table 38-B Authorizing Legislation ....... 38-18 Table 38-C Other Authorized Navigation 38-6 Projects ..................... 38-24 Table 38-D Not Applicable Table 38-E Other Authorized Flood Control Projects . . . . . . . . . . . . . . . . . . ... 38-25 38-7 Table 38-F Other Authorized Multiple Purpose Projects, Including Power ..................... 38-29 38-7 Table 38-G Deauthorized Projects ......... 38-29 38-7 Table 38-H Lake Washington Ship Canal, WA Principal Features of Double 38-7 Lock and Dam ............... 38-30 38-8 Table 38-I Project Condition Surveys ...... 38-30 38-8 Table 38-J Flood Control Activities 38-8 Pursuant to Section 205, Public 38-8 Law 80-858.................. 38-31 38-8 Table 38-K Emergency Flood Control Activities - Public Law 99, 84th 38-8 Congress ................... 38-31 38-1 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Navigation 1. BELLINGHAM HARBOR, WA Location. Part of Bellingham Bay, an arm of Puget Sound, at Bellingham, in northwestern Washington. (See NOAA Survey Chart 18424.) Existing project. Channel 30 feet deep in Whatcom Creek Waterway from deep water to head of harbor, 363.2 feet wide to 750 feet from inner end, thence 18 feet deep for inner 750 feet; Squalicum Creek Waterway, including dredging an entrance channel 200 feet wide and 26 feet deep from deep water in the bay to main pierhead line, and maintenance of southerly half and westerly end of Squalicum Creek basin to 26 feet deep, provided that no dredging can be done within 75 feet of wharves, piers, or similar structures; and small-boat basin adjacent to Squalicum Creek Waterway by construction and maintenance of two sections of rubblemound breakwater with combined length of 5,400 feet, including maintenance of minimum depths of 12 feet in entrance to basin. Plane of reference is mean lower low water. Range between mean lower low water and mean higher high water is 8.6 feet. Extreme range is about 16 feet. Project was completed in February 1961. (For further details see Annual Report for 1961. For details relating to previous project see page 797 of Annual Report for 1907.) Local cooperation. Fully complied with. Requirements are described in full on page 38-2 of FY 1980 Annual Report. Terminal facilities. Of the forty wharves and piers in Bellingham Harbor, 9 are on Whatcom Creek Waterway; 3 on Squalicum Creek Waterway; 3 on I&J Street Waterway; and 9 on Bellingham Bay. Two wharves on Whatcom Creek Waterway serve general cargo terminals. One is publicly owned and operated and is suitable for use by ocean-going vessels; the other one is privately owned and operated. There is one publicly owned terminal and small-boat harbor with 11 wharves handling private craft and fishing boats. (See Port Series No. 37 - Ports of Everett, Bellingham, Port Angeles, and Anacortes, WA, revised 1976.) Operations during fiscal year. Maintenance, hired labor: Conducted channel condition surveys. 2. EAST BAY MARINA, OLYMPIA HARBOR, WA Location. The city of Olympia, capital of the State of Washington, is located at the extreme southern end of Puget Sound. East Bay is just north of Olympia. (See NOAA Survey Charts 18445 and 18456.) Existing project. Construction of a 656-foot long general navigation facility which includes a 150-foot wide and 13-foot deep entrance channel, two access channels 12 and 13 feet deep, and a concrete floating breakwater for a new 800-boat marina. Dredging of the entrance channel and two access channels was completed in July 1982 and construction of the breakwater was completed in May 1983. The marina is currently in operation and project is physically complete. Local cooperation. Fully complied with. Requirements are described in full on page 38-3 of FY 1981 Annual Report. Operations during fiscal year. New work, hired labor: Completed documentation of project and as-built drawings: 3. EDIZ HOOK, WA Location. Ediz Hook and the city of Port Angeles are on the Strait of Juan de Fuca in Clallam County, WA, about 100 miles northwest of Seattle. (See NOAA Survey Chart 18468.) Existing project. Provides for about 13,300 lineal feet of rock revetment and 3,100 lineal feet of rock blanketing, together with initial beach replenishment and annual nourishment. Project was completed in October 1978. (For further details, see Annual Report for 1979.) Local cooperation. Fully complied with. Terminal facilities. There are 17 docks, wharves, and piers in Port Angeles protected by Ediz Hook, of which nine are public. Four of the private docks are operated by timber mills for transfer of logs, pulp and fuel. There are five general cargo/log docks, a ferry dock, three moorage docks (including docks for the Coast Guard and pilots), a fish unloading dock, and three log dump piers. Operations during fiscal year. Maintenance, contract: A contract for revetment repair and beach feed was completed in August 1985. Total rock placed was 36,580 tons and displaced rocks were rekeyed. Beach feed amounted to 42,798 tons. Total contract cost was $970,088. 4. EVERETT HARBOR AND SNOHOMISH RIVER, WA Location. On Port Gardner Bay, at northern end of Possession Sound, an arm of Puget Sound at Everett, in northwestern Washington; and Snohomish River for 6.3 miles above mouth. (See NOAA Survey Chart 18443.) Existing project. Training dike extending from a point opposite 23d Street northward 12,550 feet to outlet of Snohomish River, with spur dike extending 400 feet to pierhead line from north end of main dike; spur dike extending 1,410 feet westward from Preston Point; removal of a section of training dike north of Snohomish River outlet; channel 150 to 425 feet wide and 15 feet deep from deep water in Port Gardner Bay to 14th Street dock; thence a settling basin 700 feet wide, 1,200 feet long, and 20 feet deep, thence a channel 150 feet wide and 8 feet deep up river to head of Steamboat Slough, a total distance of about 6.3 miles; settling basin within upper channel reach about 1 mile long with a capacity of 1 million cubic yards and maintaining East Waterway to 30 feet deep. The 1968 modification included raising the southerly 4,100 feet of existing training dike, extending the training dike 1,500 feet farther south, and constructing a breakwater along the south and west sides of the existing small boat basin. Plane of reference is mean lower low water. Range between mean lower low water and mean higher high water is 11.1 feet. Extreme tidal range is about 19 feet. The boat basin breakwater has 38-2 SEATTLE, WASHINGTON DISTRICT been deleted at the request of the local sponsor, and the remainder of the 1968 modification has been deferred indefinitely. Project was completed in April 1963, excluding the deleted and deferred portions. (For further details, see page 1683 of Annual Report for 1963. For details relating to previous projects, see page 704 of Annual Report for 1905, page 2005 of Annual Report for 1915, and page 1883 of Annual Report for 1938.) Local cooperation. Fully complied with. Requirements are described in full on page 38-3 of FY 1981 Annual Report. Terminal facilities. There are 42 piers and wharves in the Port of Everett, 17 in Port Gardner and 25 on the Snohomish River. These include: 19 publicly owned terminals with 4 berths handling ocean-going vessels and 1 publicly owned terminal and small-boat basin handling fishing and pleasure craft. The rest are at Bayside and the Snohomish River. Operations during fiscal year. Maintenance, hired labor: Channel condition surveys were conducted throughout the year. Maintenance, contract: A dredging contract to maintain the Upper Snohomish River settling basin, initiated in FY 84, was completed in October 1984. The volume was 213,586 cubic yards at a cost of $489,850. 5. FLOATINGBREAKWATERPROTOTYPE TEST PROGRAM, WEST POINT, SEATTLE, WA Location. The floating breakwater prototype test was located at West Point, a point of land located about 6.8 miles northwest of Elliott Bay in Puget Sound within the boundaries of the city of Seattle, WA. The site was well suited for the project in that it often experiences waves that equal and exceed design waves contemplated at most potential floating breakwater sites. The site provided quick and easy access for purposes of maintenance and monitoring. (See NOAA Survey Chart 18440.) Existing project. The project provided for the construction, placement, monitoring, and removal of two types of floating breakwater at a site with a high occurrence of wave attack. The prototype structures built and monitored were a concrete box design, 16 feet wide and 150 feet long, with a depth of 5 feet and a 3.5-foot draft, and a pipe-tire mat design, 45 feet wide and 100 feet long. Information from the test program will be used on other Corps of Engineers projects throughout the nation to design and construct more economical and efficient wave protection structures. Test program information will also be available to other public entities and to the private sector. Construction was begun in September 1981 and the structures installed in June and July 1982. Estimated total cost is $1,800,000, Federal funds, ($1,446,000, Corps of Engineers; $354,000, Coastal Engineering Research Center). Local cooperation. None required. Operations during fiscal year. New work, hired labor: A detailed report on the test program was prepared by the Seattle District with a data analysis appendix provided by the U.S. Army Waterways Experiment Station, Coastal Engineering Research Center (CERC). The draft report was submitted to CERC for final editing. After editing, the report will be published as CERC Technical Report in early 1986. 6. FRIDAY HARBOR MARINA, WA Location. Friday Harbor is located on the eastern shore of San Juan Island on the inland waters of northwestern Washington, about 28 nautical miles east of Victoria, British Columbia, and 60 nautical miles north of Seattle, WA. San Juan Island is one of over 170 islands in the San Juan Archipelago. Friday Harbor is the San Juan County seat and a United States Customs Port of Entry. (See NOAA Survey Chart 18425.) Existing project. Construction of a 1,600-foot concrete breakwater to protect the existing port facilities and to allow the Port of Friday Harbor to provide 294 additional permanent moorage spaces and 44 additional transient spaces. Total cost of project is $2,886,418, of which $1,618,537 is Federal funds and $1,267,881 is non-Federal funds. Construction was completed in March 1984. The marina is currently in operation and project is physically complete. Local cooperation. Fully complied with. Requirements are described in full on page 38-4 of FY 1981 Annual Report. Operations during fiscal year. New work, hired labor: Finalization of cost distribution with local sponsor. 7. GRAYS HARBOR AND CHEHALIS RIVER, WA Location. Harbor lies at mouth of Chehalis River, in southwestern part of Washington, 45 miles north of entrance to Columbia River. Inner portion comprises two main channels, the south and the north, connecting harbor proper with Chehalis River at Aberdeen. Chehalis River rises in southwestern part of Washington about 40 miles east of Pacific Ocean, flows generally northwesterly and empties into eastern part of Grays Harbor. (See NOAA Survey Chart 18502.) Existing project. Provides for an entrance channel across the bar 600 feet wide and 30 feet deep, to be secured by a south jetty 13,734 feet long and a north jetty 17,200 feet long, both at an elevation of 16 feet, and by dredging; maintenance of channel 30 feet deep and 350 feet wide from deep water in Grays Harbor 14 miles to Cow Point; thence 30 feet deep and 200 feet wide, suitably widened at bends, to a point 13,700 feet upstream from Union Pacific Railroad bridge at Aberdeen, a distance of 4.125 miles; a turning basin 30 feet deep, 550 feet wide, and 1,000 feet long at upstream end of 30-foot channel near Cosmopolis; a channel 14 feet deep and 100 feet wide in South Bay to Bay City; three breakwaters at, and maintenance of entrance channel to Westhaven Cove; and protection of Point Chehalis for an exposed length of about 7,500 feet. Plane of reference is mean lower low water. Tidal range between mean lower low water and mean higher high water is 8.9 feet at Point Chehalis, 10.1 feet at Aberdeen, and 8.1 feet at Montesano. Extreme range is 17.5 feet at Point Chehalis, 17.8 feet at Aberdeen, and 38-3 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 23.8 feet at Montesano (river flood of 1935). Project was completed in March 1965 excluding deferred and inactive portions. Rehabilitation of 4,000 feet of the south jetty was completed in October 1966. (For further details, see Annual Report for 1967. For details relating to previous projects, see pages 2002-03 of Annual Report for 1915 and page 1863 of Annual Report for 1938.) Local cooperation. Fully complied with. Terminal facilities. There are 23 waterfront facilities (piers, wharves,*and docks), exclusive of those available to recreational craft, at Grays Harbor, of which five are publicly owned. In foreign and domestic trade they serve various purposes which include the receipt and/or shipment of: logs and lumber, woodchips, conventional and containerized general cargo, seafood and fishing supplies, sand and gravel, and construction materials. Other uses include: mooring and icing fishing boats, mooring small vessels for outfitting and repair, and mooring companyowned tugs. Those piers operated by the U.S. Coast Guard moor government-owned vessels. Refer to Port Series No. 35, revised 1983. Operations during fiscal year. Maintenance, hired labor: Channel condition surveys were conducted throughout the year. The Corps hopper dredge Yaquina accomplished dredging in the outer harbor in October 1984, removing 49,745 cubic yards of material at a cost of $277,600. Maintenance, contract: Maintenance dredging of the inner and outer harbors was completed in July1985 at a cost of $3,197,213 with 1,641,950 cubic yards of material being removed. Emergency maintenance dredging of the entrance to the Westport Marina was performed in June 1985.6,042 cubic yards of material were removed at a cost of $23,751. The turning basin at Cosmopolis in the inner harbor was relocated a half-mile downstream to naturally deeper water. This dredging removed 62,794 cubic yards at a cost of $157,259. 8. LAKE WASHINGTON SHIP CANAL, WA Location. Entirely within city of Seattle and extends from Puget Sound through Shilshole Bay, Salmon Bay, Lake Union, Portage Bay, and Union Bay to deep water in Lake Washington. (See NOAA Survey Chart 18447.) Existing project. Provides for a double lock and fixed dam with gated spillway and necessary accessory works, including fishladder, at the Narrows at entrance to Salmon Bay, about 1.25 miles from deep water in Puget Sound; for a channel 34 feet deep and 300 feet wide from Puget Sound to Burlington Northern Railway bridge, about 5,500 feet, with a passing basin 34 feet deep and log basin 8 feet deep at turn below railway bridge; then 34 feet deep and 150 feet to 200 feet wide to locks, about 900 feet; and a guide pier 600 feet long; for revetment of canal banks between locks and Lake Union and between Lakes Union and Washington; and for a channel 30 feet deep with a width of 100 feet from locks to Lake Union, 200 feet thence to Portage Cut, 100 feet through Portage Cut, and thence 200 feet wide through Union Bay to Lake Washington. Section included in project is about 10 miles long. Plane of reference is mean lower low water. Extreme tidal range is 19.3 feet. Range between mean lower low water and mean higher high water is 11.3 feet, and between mean lower low water and extreme low water is 4.6 feet. Ordinary fluctuation in upper pool is about 22 inches; extreme fluctuation has been 3.6 feet. Principal features of double lock and dam (structures are at Seattle, WA) are set forth in Table 38-H. Project was completed in 1934. (For further details, see Annual Report for 1935. For details relating to previous projects, see page 2003 of Annual Report for 1915, and page 1880 of Annual Report for 1938.) Local cooperation. Fully complied with. Terminal facilities. The eight waterfront facilities at Lake Washington Ship Canal are used for fuel oil, seafood, marine repair, drydocking, outfitting, mooring fishing vessels and repairs to the locks' equipment. Project is a part of Seattle Harbor's inner harbor. Refer to Port Series No. 36, revised 1983. Operations during fiscal year. Maintenance, hired labor: Locks were operated and maintained all year, passing 20,000 commercial and 65,000 pleasure vessels, and 2,200,000 tons of commerce. Fishladder passed 500,000 fish and there were more than 800,000 project visitors. Maintenance, contract: Contract for stilling basin apron repairs was completed in September 1985 at a cost of $150,051. Contract for purchase of small lock crane in the amount of $51,422 was let in September 1985. Major Rehabilitation. New work: Contract for construction of a new Emergency Closure System and rehabilitation of the downstream guard gate continues and is scheduled for completion in May 1986. 9. NAVIGATION WORK UNDER SPECIAL AUTHORIZATION Navigation activities pursuant to Section 107, Public Law 86-645 (preauthorization). Fiscal year costs for preauthorization studies were: Gooseberry Point Small Boat Harbor, Hale Passage, WA, $17,370; Oak Harbor Marina, WA, $98,097; Sandy Point Harbor, Whatcom County, WA, $25,764. Aquatic plant control (Section 302, Public Law 89-298): The program consists of control measures for selected water bodies currently infested with Eurasian watermilfoil and measures to prevent its spread into uninfested waters. Operations under the cost-share program included mechanical harvesting of 87 acres and maintaining 5 acres of fiberglass bottom screens at Lake Washington, Lake Union and Lake Sammamish, WA; treating with 2,4-D/polymer 80 acres at Pend Oreille River, WA. The Fiscal Year 1985 work also included a 2,4-D drift monitoring study, a treatment effectiveness and carry-over study, cooperation with the University of Washington on a Grass Carp study, interpretation of aerial photography to determine aquatic plant acreages in Columbia River reservoirs and the preparation of a worst case analysis for 2,4-D. Total costs for fiscal year were $333,855. Streambank erosion control evaluation and demonstration (Section 32, Public Law 93-251). Total costs for fiscal year were $7,496. 38-4 SEATTLE, WASHINGTON DISTRICT 10. PROJECT CONDITION SURVEYS Preliminary and detailed surveys to determine navigation conditions at boat basins, small navigation projects, channels, and tributaries of major rivers not within major project boundaries. Soundings and visual inspections in subject areas are conducted in order to evaluate shoaling conditions. Channel centerline markers are inspected for visibility and proper operation in applicable areas frequented by boating traffic consisting mostly of recreationalists. In addition, all subject areas are inspected to insure that they are clean of snags and obstructions. Total costs for fiscal year were $354,753. 11. PUGET SOUND AND ITS TRIBUTARY WATERS, WA Location. Puget Sound is in the western part of Washington. Cities of Seattle, Tacoma, Olympia, Everett, Bellingham, and many small towns are on its bays and inlets. (See NOAA Survey Charts 18400, 18441 and 18448.) Existing project. Maintenance of Puget Sound and its tributary waters by snagging and dredging; and removal, in cooperation with city of Seattle, of floating debris from the Seattle Harbor area. Work consists of collecting large pieces of drift, waterlogged pilings, logs and other debris, considered hazardous to navigation from Puget Sound and Federally authorized channels. (For details relating to previous projects, see page 2003 of Annual Report for 1915 and page 1869 of Annual Report for 1938.) Local cooperation. None required. City of Seattle is cooperating in a program for control of floating debris in Seattle Harbor. Terminal facilities. Terminal facilities at numerous localities on Puget Sound and its tributary waters are, in general, considered adequate for existing commerce. Operations during fiscal year. Maintenance, hired labor: The debris vessel Puget operated continuously throughout Puget Sound and its tributary waters. The patrol boat Walton removed floating debris in the greater Seattle vicinity. Together they removed approximately 1,800 tons of floating debris and hazards to navigation. Debris was disposed of locally or loaded aboard barges and disposed of by contract. Snagging operations were accomplished at Blaine Harbor, Bellingham Harbor, Swinomish Channel, Skagit River, Everett Harbor, Lake Washington Ship Canal, Lake Washington, Tacoma Harbor, Olympia Harbor, Duwamish River, and Elliott Bay. Maintenance, contract: 1,404 tons of harbor debris were disposed of at a cost of $35,086. Current contractor is recycling most of the debris and placing the remainder in a landfill. 12. QUILLAYUTE RIVER, WA Location. River is formed by junction of Soleduck and Bogachiel Rivers, in northwestern Washington, and flows westerly 5 miles to Pacific Ocean at La Push, about 30 miles south of Cape Flattery. (See NOAA Survey Chart 18480.) Existing project. Provides for: (a) Jetty 15 feet high on easterly side of river mouth, and a dike on westerly side, with a view of stabilizing entrance; (b) channel 10 feet deep and 100 feet wide extending 2,000 feet upstream from deep water; (c) basin 10 feet deep, 300 to 425 feet wide, and 2,400 feet long upstream of channel; and (d) maintenance of an ocean spit. Plane of reference is mean lower low water. Range between mean lower low water and mean higher high water at La Push is 8.3 feet. Extreme range is about 15 feet. The spit was nourished in conjunction with channel dredging contracts completed in 1973 and in 1977. The spit was rehabilitated with quarry rock in 1974, in 1979-80, and in 1982. In addition, a 500-foot breakwater section paralleling the channel and extending the spit was constructed. Project was completed in February 1960; however, the channel upstream of the boat basin has been classified as inactive. (For further details, see Annual Report for 1963.) Local cooperation. Complied with except that the requirement to provide a public landing open to all on equal terms in the boat basin was not complied with between May and July 1981, due to the closure of the Quileute Indian Reservation to the landing of salmon by sport and charter fishermen. Terminal facilities. There are 6 privately-owned docks at La Push, near the mouth of the Quillayute River. In addition, there is a protected boat basin owned by the Quileute Tribe Port Authority which is used by fishing boats, pleasure craft, and the Coast Guard, which has a separate pier. Operations during fiscal year. Maintenance, hired labor: Condition surveys and studies were made of the river channel throughout the year. Maintenance, contract: Maintenance dredging of the entrance channel was performed in February and March of 1985. The volume removed was 87,687 cubic yards at a cost of $411,730. Contract for repairs to the gabion revetments at the boat basin were made at a cost of $4,862. 13. SEATTLE HARBOR, WA Location. Harbor at Seattle, WA, includes all waterways within city limits. Chief anchorage basin is Elliott Bay, an arm of Puget Sound. (See NOAA Survey Chart 18450.) Existing project. Maintenance of East and West Waterways, 34 feet deep and 750 feet wide for 6,500 and 5,200 feet, respectively, from pierhead line in Elliott Bay; maintenance of East Waterway between upper end of 750-foot section and Spokane Street, 34 feet deep, 700 feet long, and 400 feet wide, and a turning basin, including head of East Waterway at junction of waterways south of Chicago, Milwaukee, St. Paul & Pacific Railroad Bridge, to 30 feet deep, after these sections of waterway are dredged by local interests to full project dimensions; and dredging Duwamish Waterway 200 feet wide and 30 feet deep between West Waterway and First Avenue South, 150 by 20 feet between First and Eighth Avenues South, thence 150 feet by 15 feet to a point about 1.4 miles above 14th Avenue South Bridge, with turning basin 600 by 350 feet and 20 feet deep just south of First Avenue South Bridge, and turning basin 500 by 250 feet and 15 38-5 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 feet deep, and settling basin of about 100,000 cubic yardscapacity at upper end of waterway, a distance of 5.12 miles. Total length of waterways included in project is about 7.5 miles. Plane of reference is mean lower low water. Range between mean lower low water and mean higher high water is 11.3 feet. Extreme tidal range is 19.3 feet. Project was completed in 1931, excluding the settling basin at upstream end which is classified inactive and East Waterway above the 750-foot section. (For further details, see Annual Report for 1932.) Local cooperation. Complied with, except for inactive portion of project. Terminal facilities. There are 196 piers, wharves, and docks located on the inner and outer harbors at Seattle, WA. Salmon Bay, Lake Union, Portage Bay and Lake Washington form the inner harbor; Elliott Bay and East, West and Duwamish Waterways form the outer harbor. (Lake Washington Ship Canal, a part of the inner harbor, is a separate project in this report.) These terminals serve a variety of purposes which include cargo handling, bunkering vessels, ferry service (vehicular, passenger and rail car), marine repair/outfitting/drydocking/conversion, shipbuilding, handling supplies and equipment, and mooring company-owned equipment, excursion vessels, fire boats, fishing vessels, government equipment, harbor craft/tugs, and oceanographic research vessels. The numerous waterfront facilities in the port used exclusively by recreational craft are not included. Refer to Port Series No. 36, revised 1983. Operations during fiscal year. Maintenance, hired labor: Condition surveys made of channels. 14. SWINOMISH CHANNEL, WA Location. An inland passage, 11 miles long, between Saratoga Passage and Padilla Bay, in northwestern part of Washington, about 60 miles north of Seattle. (See NOAA Survey Charts 18400, 18427 and 18421.) Existing project. A channel 100 feet wide and 12 feet deep for 11 miles from deep water in Saratoga Passage to deep water in Padilla Bay, by dredging and dike construction where necessary; and removal of protecting rocky points of McGlinn and Fidalgo Islands obstructing navigation at "Hole-in-the-Wall". Plane of reference is mean lower low water. Range between mean lower low water and mean higher high water is 11.5 feet at south end of channel, 8.4 feet at north end, and 10 feet at La Conner. Extreme tidal range is about 19.5 feet at south end of channel and about 16 feet at north end. Project was completed in March 1965. (For further details, see Annual Report for 1965.) Local cooperation. Fully complied with. Terminal facilities. There are 18 wharves, docks, and piers on Swinomish Channel, all but 3 of which are privately owned. Of these, 1 is used for handling general cargo, 5 are used exclusively for moorage, unloading, and servicing of fishing vessels; 2 are used for handling petroleum products; 3 facilities are used for log dumps; and 2 for handling non-metallic minerals. Three publicly owned facilities for launching, mooring, and servicing small craft are within the city limits of La Conner. Operations during fiscal year. Maintenance, hired labor: Condition surveys were made of various reaches of the channel. 15. WATERWAY CONNECTING PORT TOWNSEND AND OAK BAY, WA Location. Canal connects two bays which are arms of Admiralty Inlet on west side of Puget Sound, in northwestern part of Washington, about 40 miles north of Seattle. (See U.S. Coast and Geodetic Survey Chart No. 6405.) Existing project. Provides for a canal 15 feet deep, 75 feet wide on the bottom, and about 4,800 feet long, and for construction of jetties to protect channel at southern or Oak Bay end, and a bulkhead for retention of dredged material. Plane of reference is mean lower low water. Range between mean lower low water and mean higher high water is 8.3 feet in Port Townsend Bay and 9.4 feet in Oak Bay. Extreme tidal range is 16 feet. Local cooperation. Fully complied with. Terminal facilities. None directly served by the canal. Operations during fiscal year. Maintenance, hired labor: Conducted channel condition surveys. 16. WILLAPA RIVER AND HARBOR AND NASELLE RIVER, WA Location. Willapa Harbor consists of lower reaches of Willapa River and Bay, an inlet of Pacific Ocean about 30 miles north of mouth of Columbia River in Washington. Willapa River rises about 30 miles east of harbor, flows generally westerly, and empties into the bay. Naselle River enters the bay near its southerly end. (See NOAA Survey Chart 18504.) Existing project. Provides for: (a) channel over bar at mouth of Willapa Bay, 26 feet deep and at least 500 feet wide; (b) channel 24 feet deep and 200 feet wide from deep water in Willapa Bay to foot of Ferry Street at South Bend, thence 300 feet wide to westerly end of narrows, thence 250 feet wide to forks of river at Raymond, including a cutoff channel 3,100 feet long at narrows and a closing dike at Mailboat Slough; (c) channel 24 feet deep and 150 feet wide up south fork to deep basin above Cram lumber mill, and up north fork to 12th Street, with a turning basin 250 feet wide, 350 feet long, and 24 feet deep at latter point; (d) channel 10 feet deep and 40 feet wide from deep water in Palix River to Bay Center dock, with widening at shoreward end to provide a small mooring basin; (e) mooring basin 15 feet deep, 340 feet wide, and 540 feet long adjacent to port wharf at Tokeland; (f) entrance channel at Nahcotta 10 feet deep and 200 feet wide, and mooring basin 10 feet deep, 500 feet wide, and 1,150 feet long, protected by a rubblemound breakwater about 1,500 feet long; and (g) removal of snags, piles, and other obstructions in navigable channel of Naselle River between Naselle and mouth. Project includes about 26 miles of channel from entrance through Willapa River forks, 2,800 feet of Palix River-Bay Center channel, and 9 miles of Naselle River upstream of U.S. Highway 101 Bridge. Plane of reference is mean lower low water. Tidal range between mean lower low water and mean higher high 38-6 SEATTLE, WASHINGTON DISTRICT water is 8.9 feet at Toke Point, 9.9 feet at Raymond, 8.9 feet at Bay Center, and 10.8 feet near Naselle. Extreme range is 18 feet at Toke Point, 19.3 feet at Raymond, 16 feet at Bay Center, and 18 feet near Naselle. Project was completed in November 1958. (For further details, see Annual Report for 1959. For details relating to previous projects, see page 968 of Annual Report for 1910, page 2001 of Annual Report for 1915, and page 1861 of Annual Report for 1938.) Local cooperation. Complied with except that local sponsor is financially unable to dredge Tokeland Boat Basin moorage area which has resulted in the deferral of maintenance dredging of the boat basin access channel. Terminal facilities. There are 24 wharves on Willapa River and Harbor, including 5 in Willapa Bay, 4 in Bay Center, 12 in Raymond and South Bend, and 1 in Tokeland. Two of the wharves at Raymond and South Bend are suitable for use by ocean-going vessels; one of these is publicly owned and operated as a general cargo terminal, and one is located at a sawmill. The other wharves, including 3 that are publicly owned and operated, are used by shallow-draft vessels. These facilities are considered adequate for existing commerce. Operations during fiscal year. Maintenance, hired labor: Condition surveys were made of various segments of the project. Conducted ocean disposal study. Beach Erosion 17. BEACH EROSION WORK UNDER SPECIAL AUTHORIZATION Beach erosion control activities pursuant to Section 103, Public Law 84-874 (preauthorization). Fiscal year costs for Lincoln Park Beach, Seattle, WA, were $80,444. Flood Control 18. DUNGENESS RIVER, SEQUIM, WA Location. The project is located in Clallam County on the right bank of the Dungeness River, 4.5 miles southwest of Sequim, Wa, in Carlsborg Lake Quadrangle SW1/4 sec. 1,T. 29 N., R. 4 W. Existing project. Protection of the access road (210 feet), near the intake structure for the water system, consists of a riprap blanket 36 inches thick on a 1V to 2H slope and a 10-foot-wide, 4-foot-thick weighted riprap toe with gravel fill to reconstruct the required 1:2 embankment slope. Protection of the waterline and access road (150 feet) requires construction of a concrete block wall, back filled with quarry spalls. This work is the most effective and least costly method of protecting the city of Sequim's sole source of domestic water supply, where the streambank is threatened by current and floating debris impinging directly upon it. Total estimated cost of the project is $71,000 of which $70,000 is Federal. Local participation costs are estimated to be $1,000 for legal requirements. Construction began September 4, 1985. Local cooperation. Section 3, Flood Control Act of June 22, 1936, applies. Operations during fiscal year. New work, hired labor: Work includes initial appraisal and plans and specifications. Construction by equipment rental was physically complete on September 13, 1985. 19. HOWARD A. HANSON DAM, WA Location. Green River, in northwestern Washington, flows westerly for 40 miles to Auburn, thence northerly 32 miles to its mouth in Elliott Bay at Seattle. Dam is at river mile 64, 6 miles southeast of Kanaskat, and 1 mile downstream from mouth of North Fork. (See Geological Survey topographic sheet, "Cedar Lake quadrangle, Wash.") Existing project. Rockfill dam about 235 feet high, with gated spillway having a concrete weir at elevation 1176 feet above mean sea level and top of gates at elevation 1206, creating a reservoir with capacity of 106,000 acre-feet. Dam along crest is about 675 feet long. Improvement is designed to control flooding in Green River Valley to alleviate agricultural and urban flood damage, and make possible further expansion of Seattle industrial area. It also supplements Tacoma water supply which was included as a betterment. Project was completed in June 1963. (For further details, see Annual Report for 1963.) Local cooperation. Fully complied with. Operations during fiscal year. Maintenance, hired labor: Operation continued all year. Routine maintenance was accomplished on roads, gages, debris booms, turbidimeter, ditches, powerline, and other project features. The outlet works stilling basin was inspected. Work continued on water quality surveys, water storage studies, and channel capacity study. Maintenance, contract: Settlement of the fill for the relocated Burlington Northern Railway between stations 10989 and 10991 was under continued surveillance. The deferred construction period has been extended to cover this area to observe effect of remedial work. (Improvements to the drainage system have apparently stabilized the railroad fill.) 20. INSPECTION OF COMPLETED FLOOD CONTROL PROJECTS Inspections are made of Federally constructed local flood protection projects which are maintained by local interests; and agencies responsible for their operation and maintenance are advised of any needed repairs. During the fiscal year, inspections were made on Okanogan River at Omak and Oroville, Dungeness River at Sequim, Sammamish River, Shelton Creek, Stillaguamish River and Yakima River, all in Washington State; Clark Fork at Missoula, MT; Coeur d'Alene, Lightning Creek and St. Maries projects in Idaho. Streambank vegetation evaluations were made at Omak and Oroville and on the Green River in Washington. Fiscal year costs were $73,688. Costs to date have been $596,814. 38-7 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 21. INSPECTION OF COMPLETED PL-99 WORKS Inspections are made of levees that have been rehabilitated under Public Law 84-99. Inspections involve determining condition of levees, riprap displacement and vegetative control. Local sponsors are advised of results and recommendations. Inspections made this fiscal year were on Flathead River, MT; Chehalis, Hoquiam, Stillaguamish, and Wenatchee Rivers, Crab and Wilson Creeks and the Olympic Peninsula, all in Washington State. Fiscal year costs were $44,235. Total costs to date have been $122,947. 22. MUD MOUNTAIN DAM, WA Location. On White River, principal tributary of Puyallup River, near Mud Mountain, 28 miles above its confluence with Puyallup River, and 38 miles above mouth of Puyallup River. Dam is 6 miles southeast of Enumclaw, in northwestern Washington, and 38 miles east of Tacoma. (See Geological Survey topographic sheet "Cedar Lake quadrangle, Washington.") Existing project. Rockfill dam, 700 feet long at crest elevation, rises 425 feet above bedrock. Reservoir has storage capacity of about 106,000 acre-feet. Outlet works are in right abutment and permit controlled discharge of 17,700 cubic feet per second through two concrete-lined tunnels with uncontrolled discharge over spillway having maximum capacity of 139,000 cubic feet per second. Improvement affords flood protection to White and Puyallup River Valleys and protects Tacoma industrial district in conjunction with Puyallup River project at Tacoma against floods about 50 percent greater than maximum discharge of record. Project was completed in June 1953, except for recreational facilities. (For further details, see Annual Report for 1953.) To date the Corps has constructed two vistas, a picnic area, and playground adjacent to the project office, a reservoir access point for hunters and fishermen, and a 1,760-foot trail leading to the lower vista area. Local cooperation. None required. Operations during fiscal year. Maintenance, hired labor: Project features were operated all year. Maintenance was accomplished on dam facilities, intake structure, gages, debris booms, power lines, roads, ditches, and fish facilities. Approximately 1,000 fish are transported annually from the fish collection facility. Engineering and design for major modification work under the Dam Safety Assurance was initiated, focusing on preparation of a Design Memorandum. Waterways Experiment Station conducted hydraulic model studies. Exploration drilling contract in the amount of $391,279 was completed. 23. NOOKSACK RIVER, ACME, WA Location. The project is located in Whatcom County along the Mosquito Lake Road, adjacent to the Middle Fork Nooksack River, 6 miles northeast of Acme, WA, in Canyon Lake Quadrangle NW1/4 sec. 13, T. 38 N., R. 5 E. Existing project. A 300-lineal-foot bank protection project consisting of riprap 42 inches thick on a 1V to 1.5H slope and a 12-foot-wide, 4-foot-thick weighted riprap toe. Construction of a quarry spall filter beneath the riprap blanket and of an access road approximately 200 feet long was required. Riprapping the streambank is the most effective and least costly method in protecting the roadway from further erosion and in preventing its total failure. Local cooperation. Section 3, Flood Control Act of June 22, 1936, applies. Operations during fiscal year. New work, hired labor: Work includes initial appraisal and plans and specifications. Construction by equipment rental began on February 5, 1985 and was physically complete on February 15, 1985, at a cost of $77,300, Federal funds. 24. PILCHUCK RIVER, WA Location. The project is located on the right bank of the Pilchuck River, five miles northeast of Granite Falls, WA, in Granite Falls Quadrangle NE 1/4 sec. 9, T. 29N., R. 7E. Existing project. A 1,000-lineal-foot riprap bank protection project consisting of a blanket 36 inches thick on a 1V to 2H slope and a 12-foot-wide, 4-foot-thick weighted riprap toe with a 12-inch gravel filter constructed beneath the blanket. Proposed work is considered the most effective and least costly method of protecting the waterline and treatment plant in the city of Snohomish and surrounding areas threatened by continual erosion at the river bank. Construction began September 10, 1984, and was physically complete on September 20, 1984, at a cost of $85,000, Federal funds. Local cooperation. Section 3, Flood Control Act of June 22, 1936, applies. Operations during fiscal year. New work, hired labor: Completed as-built drawings. 25. PLACER CREEK, ID Location. Placer Creek rises in the St. Joe Mountains of northern Idaho, flows northerly about 7.8 miles, and discharges into the South Fork of Coeur d'Alene River at the city of Wallace. Existing project. Provides for flood control by construction of a 3,700-foot-long concrete channel to confine Placer Creek flows through Wallace. A debris basin capable of storing 17,000 cubic yards of debris is located upstream from the channel to prevent plugging of the channel. Project was physically complete in September 1983. Local cooperation. Fully complied with. Requirements are described in full on page 38-10 of Fiscal Year 1981 Annual Report. Operations during fiscal year. New work, contract: A flood warning system contract was awarded and costshared by local sponsor. 26. SCHEDULING FLOOD CONTROL RESERVOIR OPERATIONS Flood control storage space was available in Hungry Horse Reservoir, MT, Flathead Lake, MT (controlled by Kerr Dam), Grand Coulee Project, WA, Upper Baker and 38-8 SEATTLE, WASHINGTON DISTRICT Ross Reservoirs, WA. Guidance forecasts were made during the flood control season, as required. No Lost Valley storage replacement was requested at Rocky Reach, Priest Rapids, and Wells Dams. Daily and/or hourly data were collected and tabulated as required to check compliance with operating criteria. Coordination necessary in preparation or revision of reservoir regulation manuals was carried on during the year with agencies responsible for the operation of these projects. Fiscal year costs were $142,627. 27. STILLAGUAMISH RIVER, WA Location. Formed by confluence of its north and south forks at Arlington, in northwestern Washington, Stillaguamish River flows westerly 22 miles to Puget Sound, entering Port Susan through Hat Slough and South Pass, and Skagit Bay through West Pass. (See NOAA Survey Chart 18441, and Geological Survey quadrangles Stanwood, Marysville, and Stillaguamish, WA.) Existing project. Works to reduce bank erosion and channel changes on Stillaguamish River 15 miles between Arlington and head of Hat Slough, and on Cook Slough, 3 miles long, as follows: Revetment at 26 places on river and Cook Slough; concrete weir 275 feet long between steel-sheet-pile piers at head of Cook Slough to limit flow through slough; and two cutoff channels, each about 900 feet long, to eliminate sharp bends in Cook Slough. Tidal influence extends about 3 miles into improved section. Flood stages of 16 feet above low water at Cook Slough weir have been observed. Project was completed in July 1939. (For further details, see Annual Report for 1940.) Local cooperation. None required. Operations during fiscal year. Maintenance, hired labor: Removed brush and trees on 11,500 linear feet of 7 segments; repaired 4 segments with gravel and placed riprap on 3 segments. Quarry spalls were used to repair 4 segments. 28. TACOMA, PUYALLUP RIVER, WA Location. Puyallup River has its source in glaciers on western slopes of Mount Rainier, WA, flows northwesterly 50 miles, and empties into Commencement Bay, an arm of Puget Sound, at Tacoma. Work covered by this project is on Puyallup River, within city limits of Tacoma. (See NOAA Survey Chart 18453.) Existing project. A channel with a capacity of 50,000 cubic feet per second between East 11th Street Bridge and lower end of inter-county improvement, a distance of about 2.2 miles, by straightening channel, building levees, revetting channel and levees, and making necessary bridge changes. The 11th Street Bridge at lower end of project is 0.75 mile above mouth of Puyallup River. Diurnal tidal range at mouth of river is 11.8 feet and extreme range is 20 feet. Improvement was planned in conjunction with Mud Mountain Dam and affords protection against floods about 50 percent greater than maximum discharge of record. Project was completed in May 1950. (For further details, see Annual Report for 1950.) Local cooperation. None required. Operations during fiscal year. Maintenance, hired labor: Removed brush and trees on approximately 17,000 lineal feet. Rental equipment was used to redress and crown the levee road on the right bank. 29. WYNOOCHEE LAKE, WA Location. On Wynoochee River, a tributary of Chehalis River, about 28 miles north of Montesano, Grays Harbor County, WA. (See Geological Survey quadrangles, Grisdale, Wynoochee Valley, and Montesano.) Existing project. Provides for a concrete and earthfill dam, 177 feet high, and reservoir of 70,000 acre-feet of total storage for water supply, flood control, irrigation, and fish and wildlife. Upstream fish facilities were operational in the fall of 1970. The project was completed and became operational in December 1972. Installation of power-generating facilities was not authorized, pending a reexamination report by the Chief of Engineers. In February 1966, the Federal Power Commission asserted that power production as part of the Wynoochee project was not feasible at that time. (For further details, see Annual Report for 1972.) Local cooperation. Fully complied with. Requirements are described in full on page 38-12 of FY 1981 Annual Report. Operations during fiscal year. Maintenance, hired labor: Project facilities were operated all year. Maintenance was accomplished on dam and fish facilities, roads, ditches, culverts, and visitors' facilities. The project tank truck hauled upstream migrant fish past the dam. Maintenance, contract: Contract for spillway gate repainting in the amount of $96,188 is 58% complete. Multiple-Purpose Projects, Including Power 30. ALBENI FALLS DAM, ID Location. Dam is on Pend Oreille River about 25 miles west of Sandpoint, in northern Idaho, and 50 miles northeast of Spokane, WA. Dam is 838 and 90 miles upstream from mouths of Columbia and Pend Oreille Rivers, respectively. (See Geological Survey topographic sheets, Sandpoint, ID, and Newport, WA.) Existing project. Provides flood control, hydroelectric power, and related water uses on Pend Oreille River as a part of the multiple-purpose plan for development of Columbia River Basin, including recreation development. At the dam, channel was formerly divided by an island and a low waterfall of about 7 feet. Dam is a gated, gravitystructure spillway in left channel and a powerhouse having an installation of 42,600 kilowatts in right channel, creating a reservoir with a usable storage capacity of 1,153,000 acrefeet. Project was completed in June 1957. (For further details, see Annual Report for 1957.) Recreational facilities for public use have been provided at Albeni Cove, Priest River, Riley Creek, Johnson Creek, Trestle Creek, Strongs Island, and Springy Point. (Strongs Island was closed in FY 1982 to reduce O&M costs.) (Refer to Albeni Falls Master Plan dated June 1981 for further planned development.) 38-9 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Local cooperation. None required. Operations during fiscal year. Maintenance, hired labor: Reservoir was operated through its annual cycle of storage and release. Routine structural, mechanical, and electrical maintenance was performed on spillway, dam, powerhouse, and equipment. Maintenance, contract: A $147,327 debris facility rehabilitation contract, awarded in July 1985, is 95% complete. Contract in the amount of $251,000 for a shop and storage building was awarded in August 1985 and is 25% complete. Work continued on the station service circuit breaker contract. 31. CHIEF JOSEPH DAM, RUFUS WOODS LAKE, WA Location. On Columbia River in north central Washington, at river mile 545, just upstream from mouth of Foster Creek, 1.5 miles upstream from Town of Bridgeport. (Geological Survey topographic sheet Okanogan, WA, shows general locality.) Existing project. A concrete gravity structure which consists of a 19-gate spillway and a 27-unit powerhouse. The powerhouse has sixteen 64,000 kilowatt and eleven 95,000 kilowatt generators with nameplate capacity of 2,069,000 kilowatts. Pool raising to elevation 956 was completed in 1981 which increased the powerplant capability to 2,482,000 kilowatts. Project providing initial 16 power units was completed in FY 1961. (For further details, see Annual Report for 1962.) Generator units 17 through 27 are producing power; however, additional work will be required to bring turbine efficiency up to design standards. Construction of structural modifications to dam and powerhouse, installation of additional units, uprating and plant modernization of units 1-16, and other miscellaneous project work is approximately 85 percent complete. Estimated cost of current construction project is $387,000,000. Local cooperation. None required. Operations during fiscal year. New work, hired labor: Continued real estate acquisition and excavation for O&M maintenance building and dock. New work, contract: Contracts were awarded for O&M maintenance building and dock, powerhouse shops, and mobile sealing inspection unit. Contracts continuing through the fiscal year included cultural resources relocation, spillway gate deficiencies, pier crack grouting, battery chargers, generator stator rewind, installation and fire protection, transformers, governor system, station service system, protective relays, 15 kV circuit breakers, turbine cavitation, main unit excitation system, accessioning of cultural resources artifacts, warehouse additions and sandblast building, and wildlife mitigation: mule deer study and mitigation evaluation. Contracts completed during the fiscal year included drilling to install additional inclinometers ($156,495), purchase of barges and maintenance boats ($265,780), wildlife mitigation, boat dock ($81,218), and project roads, paving and utilities ($2,314,461). Maintenance, hired labor: Project was operated all year, and routine maintenance work was performed. Maintenance, contract: Contracts awarded during the fiscal year included: tubes for units 1 - 16, magnesium anodes, circuit breaker replacement parts, and brake shoe pads. Completed contracts included: generator air coolers, stator bars, and stator laminations. 32. LIBBY DAM-LAKE KOOCANUSA, MT Location. On Kootenai River in Lincoln County, MT, about 17 miles upstream from Libby, and 219 miles upstream from confluence of Kootenai with Columbia River. (See Geological Survey topographic sheet, Thompson Lakes, MT.) Existing project. Provides storage for local flood control protection in Montana and Idaho, and main stem flood control in Lower Columbia River, hydroelectric power generation at-site and at downstream plants through storage release. Project will be operated as a unit of comprehensive system for improvement of Columbia River Basin for flood control, navigation, hydroelectric power, and other purposes. Local cooperation. Fully complied with. Libby Dam-Lake Koocanusa Project. Dam is a straight concrete gravity overflow type, 420 feet high, 3,055 feet long, with normal full pool at elevation 2459 feet above mean sea level. Powerhouse has an initial installed capacity of 420,000 kilowatts from four hydroelectric generating units with provision for four additional units, one of which is currently under construction. Lake Koocanusa is 90 miles long, backing water 42 miles into Canada and has a usable storage capacity of 4,965,000 acre-feet at 50 percent drawdown. Construction of dam was in accordance with treaty between United States and Canada relating to international cooperation in waterresource development of the Columbia River Basin. Construction is complete. Operations during fiscal year. New work, contract: Contract for flood contingency plan was completed. Regarding Libby downstream effects in Kootenai Flats, ID, payments for damage claims were made in the amount of $186,500. Maintenance, hired labor: Reservoir was operated through its annual cycle of storage and release. Routine structural, mechanical, and electrical maintenance was performed on spillway, dam powerhouse, and equipment. Maintenance, contract: Contract in the amount of $143,700 for chip seal coating project roads was awarded in August 1985 and is 90% complete. Contract in the amount of $55,000 for storage building, Murray Springs Fish Hatchery was completed. Libby Additional Units Project. Provides for installation of 4 additional units at the Libby Dam Powerhouse. Fabrication of generators for units 5 through 8 is complete; however, only the unit 5 generator was installed. Installation of the electrical equipment is limited to unit 5. Parts for units 6 through 8 will be stored at the site. Project is 99% complete. Units 6 through 8 have been reclassified inactive. 38-10 SEATTLE, WASHINGTON DISTRICT Operations during fiscal year. New work, contract: Contracts for governors, switchgear, transformers, bus and grounding equipment,unit 5 installation, and closing out construction facilities were completed. Contracts for turbines and generators continued. Libby Reregulating Dam Project. Provides for construction of a reregulating dam about 10 miles downstream of Libby Dam and associated relocation of about 9 miles of Burlington Northern Railroad, 7.5 miles of St. Regis log'haul road, 0.5 miles of Forest Development Road, and 7.5 miles of Montana State Highway. Funds were provided for a construction start in 1977; however, courts have found that Congress did not authorize construction of the reregulating dam. Operations during fiscal year. All work has been terminated due to court direction. Libby Reregulating Dam - Power Units Project. Provides for installation of three hydroelectric generating units at the reregulating dam with 78,900 kilowatt installed capacity. A General Design Memorandum 1, Phase II, Preliminary Design Report was approved by the Office, Chief of Engineers on March 3, 1981. General Investigations 33. SURVEYS Fiscal year costs were $210,004 for navigation studies, $129,466 for flood damage prevention studies, $199,669 for comprehensive studies, $323 for review of authorized projects, $75,624 for miscellaneous activities and $35,240 for coordination with other agencies and non-Federal interests, a total of $650,326. 34. COLLECTION AND STUDY OF BASIC DATA The work programmed for collection and study of basic data covers precipitation studies,international water studies, flood plain management services, and hydrologic studies. Work on international water studies included checking Kootenay Lake storage computations to determine compliance of West Kootenay Power & Light Co. with orders of International Joint Commission, and coordination with International Kootenay Lake, Osoyoos Lake, and Skagit River Board of Control in enforcement of International Joint Commission orders. In late March 1985, shortly after the signing of the Ross Dam Treaty between the United States and Canada, the Skagit River Board of Control was disbanded. Technical assistance was provided other Federal and non-Federal agencies in flood hazard evaluation and related services as requested. Fiscal year costs were $49 for precipitation studies, $3,191 for international water studies, $110,885 for flood plain management services, and $4,999 for hydrologic studies, a total of $119,124. 35. CONTINUATION OF PLANNING AND ENGINEERING Blair and Sitcum Waterways, Tacoma Harbor, WA Tacoma Harbor, Pierce County, is located in southern Puget Sound at Taco: .a, WA, about 30 miles south of Seattle. The proposed plan of improvement provides for (a) modification of the existing Federal project for Blair Waterway to provide for the construction and maintenance of a 45-foot and a 41-foot channel including replacement of the East 11th Street Bridge and (b) Federal maintenance of the locally constructed Sitcum Waterway to depths of 40 and 35 feet. Accomplishments during the fiscal year included environmental coordination on contaminated sediments and contracting with the Washington State Department of Transportation for bridge replacement evaluations. Estimated preconstruction planning cost is $980,000. Fiscal year costs were $94,208. Total costs to date have been $660,588, including $300,000 appropriated and expended under Section 101(c). Chehalis River at South Aberdeen and Cosmopolis, WA The cities of Aberdeen and Cosmopolis are located at the mouth of the Chehalis River in Grays Harbor County, west central Washington. The Chehalis River, about 125 miles in length, rises in the Willapa Hills in west central Washington. The proposed plan of improvement would protect most of the left bank flood plain at the mouth of the Chehalis River in the cities of Aberdeen and Cosmopolis. The improvement would include: an earthen levee 22,500 feet long roughly following the left bank of the Chehalis River from Devonshire Slough to Cosmopolis; 2,200 feet of concrete floodwall in two industrial areas; five pumping stations and tide gates; and 10 smaller gravity drain culverts with flap gates. The levee would protect 1,318 acres of the cities from inundation by the standard project flood. Accomplishments during the fiscal year included environmental, hydrologic and hydraulic, and economic studies and Fish and Wildlife coordination. Estimated preconstruction planning cost is $1,097,000. Fiscal year costs were $322,790. Total costs to date have been $483,834. East, West and Duwamish Waterways, Seattle Harbor, WA Harbor at Seattle, WA, an authorized project, includes East, West and Duwamish Waterways within its city limits. Chief anchorage basin is Elliott Bay, an arm of Puget Sound. The proposed plan of improvement includes: Deepening and narrowing East and West Waterways (from 34 x 750 feet to 39 x 500 feet); deepening and widening Duwamish Waterway (from 34 x 200 feet to 39 x 250 feet); replacement of the constrictive Burlington Northern Railroad Bridge with one having 250 feet horizontal clearance; deepening one turning basin to 39 feet; deauthorizing an unneeded turning basin; mitigation for loss of 4 acres shallow-water and 27 acres deep-water fish habitat; creation of 2 acres of shallow-water habitat for fish enhancement; and construction of a public boat ramp for recreation access. Continuation of planning and engineering studies were initiated in October 1984. During the fiscal year a plan of 38-11 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 action was completed and environmental studies and Fish and Wildlife coordination were begun. . Estimated preconstruction planning cost is $1,370,000. Fiscal year costs were $361,417. Grays Harbor, Chehalis and Hoquiam Rivers, WA Grays Harbor is a large tidal estuary in southwestern Washington. The entrance is 45 miles north of the mouth of the Columbia River and 110 miles south of the Strait of Juan de Fuca. The estuary lies entirely within Grays Harbor County, State of Washington. The proposed plan of improvement consists of modifying the existing Federal project for Grays Harbor. The existing 30-foot channel would be deepened to a depth of 46 feet through the Outer Bar and widened in this reach from the existing 600 feet to a 1,000-foot-wide channel; thence, the entrance reach would be widened and deepened from the existing designated 350 feet wide by 30 feet deep channel to a channel tapering landward from 1,000 to 600 feet wide and 46 to 38 feet deep; thence, the existing channel to Cow Point would be widened and deepened from 350 feet wide and 30 feet deep to 400 feet wide by 38 feet deep for the South reach and Crossover reach and to 350 feet wide by 38 feet deep for the Moon Island, Hoquiam, and Cow Point reaches; and thence, the Aberdeen and South Aberdeen reaches would be widened and deepened from the existing designated 200 feet wide by 30 feet deep channels to channels 250 feet wide by 36 feet deep. Two turning basins located at Aberdeen would be constructed and the existing railroad bridge would be replaced with a new bridge having horizontal clearance of 250 feet. During the fiscal year major progress was made on environmental and engineering studies. Estimated preconstruction planning cost is $3,360,000. Fiscal year costs were $1,534,632. Total costs to date have been $1,864,158. Yakima River at Union Gap, WA The flood plain under study is located between the confluence of the Yakima and Naches Rivers and the community of Union Gap, within Yakima County, in southeastern Washington State. The proposed plan of improvement consists of: Constructing two levees downstream of the Moxee Bridge on the Yakima River (1.1 miles of levee on the west bank and 2.5 miles on the east bank); improving sections of existing 7 miles of levee by raising and providing additional riprap; installation of drainage control gates on existing culverts and flood plain management for unprotected areas. Continuation of Planning and Engineering studies were initiated in October 1984. During the fiscal year a plan of action was completed and environmental, survey, economic, hydrologic and hydraulic studies were begun. Estimated preconstruction planning cost is $556,000. Fiscal year costs were $216,980. 38-12 SEATTLE, WASHINGTON DISTRICT TABLE 38-A COST AND FINANCIAL STATEMENT See Section Total to In Text Project Funding FY 82 FY 83 FY 84 FY 85 Sep. 30, 1985 1. Bellingham Harbor WA (Federal Funds) (Contrib. Funds) 2. East Bay Marina, Olympia Harbor, WA (Federal Funds) (Contrib. Funds) 3. Ediz Hook, WA (Federal Funds) (Contrib. Funds) 4. Everett Harbor and Snohomish River, WA (Federal Funds) (Contrib. Funds) 5. Floating Breakwater Prototype Test Program, WA 6. Friday Harbor Marina, WA (Federal Funds) (Contrib. Funds) 7. Grays Harbor and Chehalis River, WA (Federal Funds) New Work Approp. Cost Maint. Approp. Cost New Work Contrib. Cost Maint. Contrib. Cost New Work Approp. Cost New Work Contrib. Cost New Work Approp. Cost Maint. Approp. Cost New Work Contrib. Cost Maint. Contrib. Cost New Work Approp. Cost Maint. Approp. Cost New Work Contrib. Cost Maint. Contrib. Cost New Work Approp. Cost New Work Approp. Cost New Work Contrib. Cost New Work Approp. Cost Maint. Approp. Cost 49,000 50,687 - 1,566,840 - 1,566,8401 15,000 1,064,067 11,813 1,060,8802 3,025 3,270 29,421 29,4213 9,103 9,103 905,000 341,000 917,529 318,254 -10,000 11,341 -100,020 1,619,956 -98,541 1,619,9494 1,614,000 276,000 163,478 133,134 1,044,205 723,671 279,634 139,102 - - - 1,860 - - - 1,860 34,000 31,394 1,655 3,284 15,000 8,925 855 2,165 2,186,612 2,186,612 5,878,740 5,878,7405 80,000 950,000 1,128,000 81,492 947,282 1,116,681 - - 396,000 - - 396,000 122,375 1 111,793 130,585 117,243 - - - - 1,775,744 - - - - 1,775,7446 522,000 363,617 792,000 155,000 6,771,079 523,497 363,615 689,169 253,987 6,767,2347 - - - - 116,618 - - - - 116,618 - - - - 584,090 - - - - 584,090 793,000 402,000 792,047 403,779 115,000 1,115,000 110,148 1,042,099 - 60,000 37,545 35,000 38,026 35,010 3,193,000 3,289,000 3,224,499 3,289,402 -19,913 210,500 185,825 1,200,000 1,239,917 15,590 35,296 -130,000 -25,290 1,461,590 1,461,330 1,618,537 1,618,5048 7,881 1,267,881 27,964 1,267,881 - 5,165,396 -9,635 5,155,760' 4,347,000 4,252,725 74,310,189 4,339,277 4,243,299 74,289,77010 38-13 TABLE 38-A (Continued) REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 COST AND FINANCIAL STATEMENT See Section Total to In Text Project Funding FY 82 FY 83 FY 84 FY 85 Sep. 30, 1985 (Contrib. Funds) 8. Lake Washington Ship Canal, WA 11. Puget Sound and its Tributary Waters, WA 12. Quillayute River, WA (Federal Funds) (Contrib. Funds) 13. Seattle Harbor, WA (Federal Funds) (Contrib. Funds) 14. Swinomish Channel, WA (Federal Funds) Minor Rehab. Approp. Cost Major Rehab. Approp. Cost New Work Contrib. Cost Maint. Contrib. Cost New Work Approp. Cost Maint. Approp. Cost Major Rehab. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Contrib. Cost New Work Approp. Cost Maint. Approp. Cost New Work Contrib. Cost Maint. Contrib. Cost New Work Approp. Cost Maint. Approp. Cost - 120,592 - 120,592 - 4,606,145 - 4,606,145 - 35,834 - 35,834 - 47,889 - 47,889 -7,545 -7,519 2,837,000 2,814,197 - - - 4,803,952 - - - 4,803,95211 2,851,000 2,999,240 3,595,440 57,368,910 2,856,510 2,936,228 3,560,062 57,240,48912 1,100,000 2,275,000 2,970,000 1,120,230 7,465,230 1,099,779 2,275,220 2,951,805 994,066 7,320,870 - - - - 43,337 - - - - 43,337 927,000 600,000 593,000 542,500 15,797,802 928,715 601,269 552,674 575,607 15,790,58313 - - - - 521,850 - - - - 521,850' 4 3,074,000 -310,000 454,000 536,261 9,119,022 2,262,394 501,062 452,875 530,793 9,110,928 - - - - 20,000 - - - - 20,000 - - - - 170,335 - - - - 170,335 312,000 428,358 405,000 274,000 6,191,746 312,240 428,995 398,225 273,308 6,184,277 - - - - 69,333 - - - - 69,333 - - - - 20,000 - - - - 20,000 - - - - 808,332 - - - - 808,332'5 114,000 124,922 70,000 347,760 65,360 352,506 20,000 5,514,940 19,797 5,514,510 38-14 SEATTLE, WASHINGTON DISTRICT TABLE 38-A (Continued) COST AND FINANCIAL STATEMENT See Section Total to In Text Project Funding FY 82 FY 83 FY 84 FY 85 Sep. 30, 1985 (Contrib. Funds) 15. Waterway Connecting Port Townsend and Oak Bay, WA 16. Willapa River and Harbor and Naselle River, WA (Federal Funds) (Contrib. Funds) 18. Dungeness River, WA 19. Howard A. Hanson Dam, WA (Federal Funds) (Contrib. Funds) 22. Mud Mountain Dam, WA (Federal Funds) (Contrib. Funds) 23. Nooksack River, WA 24. Pilchuck River, WA 25. Placer Creek, ID 27 Stillaguamish River, WA (Federal Funds) New Work Contrib. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Contrib. Cost New Work Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Contrib. Cost New Work Approp. Cost Maint. Approp. Cost Minor Rehab. Approp. Cost Maint. Contrib. Cost New Work Approp. Cost New Work Approp. Cost New Work Approp. Cost New Work Approp. Cost Maint. Approp. Cost 90,000 89,712 113,000 116,137 60,000 578,000 59,914 573,690 16,500 16,169 32,000 32,000 73,322 73,322 326,378 325,759 - 1,579,269 - 1,579,26916 84,000 13,240,978 80,542 13,233,12417 - - - - 98,372 - - - - 98,372 - - - 66,500 66,500 - - - 43,934 43,934 - - - - 37,048,061 - - - - 37,048,061 530,000 528,000 515,000 693,049 8,831,300 531,095 527,245 496,871 681,307 8,800,391 - - - - 2,000,000 - - - - 2,000,000 - - - - 13,295,848 - - - - 13,295,84818 828,000 1,136,162 1,138,000 2,967,944 16,960,476 830,027 1,110,512 1,118,723 2,937,358 16,873,26519 - - - - 285,908 - - - - 285,908 - - - - 3,928 - - - - 3,928 - - 85,000 - - 67,692 3 3 77,300 77,300 -4,000 13,308 77,300 77,300 81,000 81,000 ,225,000 845,000 390,000 - 5,865,000 ,235,803 722,954 497,172 20,329 5,863,301 - - - - 220,594 - - - - 220,59420 141,000 150,000 155,000 100,000 1,464,845 148,672 142,972 162,671 100,163 1,464,418 38-15 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 COST AND FINANCIAL STATEMENT See Section Total to In Text Project Funding FY 82 FY 83 FY 84 FY 85 Sep. 30, 1985 (Contrib. Funds) New Work 28. Tacoma, Puyallup River, WA 29. Wynoochee Lake, WA 30. Albeni Falls Dam, ID 31. Chief Joseph Dam- Rufus Woods Lake, WA 32. Libby Dam, Lake Koocanusa, MT (Federal Funds) (Contrib. Funds) Contrib. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost Major Rehab. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Contrib. Cost 3,270 39,000 41,406 21,000 21,000 - 3,947,853 - 3,947,85321 40,000 39,947 40,000 39,829 50,000 48,911 456,597 455,283 - - - - 23,494,445 - - - - 23,494,44522 891,000 908,000 994,500 1,047,877 9,877,446 873,785 934,637 963,671 1,027,462 9,824,035 - - - - 31,878,297 - - - - 31,878,29723 1,377,320 1,923,231 2,018,000 2,580,000 1,364,305 1,843,759 2,062,473 2,555,530 8,170,000 11,900,000 18,200,000 13,990,000 8,091,788 12,088,050 18,292,811 14,012,821 4,381,000 5,198,000 5,890,000 5,968,576 4,379,283 5,194,095 5,811,108 5,966,340 10,090,000 9,943,442 1,997,000 1,990,590 6,250,000 6,365,210 2,590,900 2,583,965 1,915,000 1,844,303 2,860,500 2,824,490 830,000 853,369 2,877,000 2,852,195 25,499,831 25,396,75524 495,068,235 495,018,82025 66,262,511 66,142,21326 297,630 297,630 543,096,14027 542,990,76428 21,807,479 21,707,51329 - 1,458,252 - 1,458,252 lIncludes $56,582 appropriated and expended for previous project. 2Includes $1,092 appropriated and expended for previous project. 3Excludes $13,000 Coast Guard funds expended and $2,159,633 expended by Port of Bellingham in fulfilling requirements of local cooperation. 4Includes $330,517 appropriated and expended for preauthorization cost. 5Includes $1,157,570 preauthorization cost. lIncludes $418,209 appropriated and expended for previous projects. Excludes $43,000 Coast Guard funds expended. 'Includes $5,869 appropriated and expended for previous project. $Includes $43,037 for previous project and $235,341 preauthorization cost, appropriated and expended. 9Includes $134,545 appropriated and $124,909 expended for recreation facilities at completed project (Code 710), and $113,134 appropriated and expended for previous projects. Excludes $162,000 Navy funds and $6,000 Coast Guard funds expended. 1"lncludes $37,415 appropriated and expended for previous projects. Excludes $798,135 Emergency Relief Funds and $57,000 Public Works Administration funds expended. "Includes $779,655 for recreation facilities at completed project (Code 710), and $485,002 for previous projects, appropriated and expended. Excludes $246,567 expended by State of Washington and $742,071 expended by King County. Excludes $192,516 Public Works Administration funds expended. 12Includes $1,631,195 (1916 to 1936) and $338,163 subsequently appropriated and expended under Maintenance and Operation of Dams and Other Improvements of Navigable Waters. 13lIncludes $67,496 appropriated and expended for previous project. 38-16 TABLE 38-A (Continued) SEATTLE, WASHINGTON DISTRICT TABLE 38-A (Continued) COST AND FINANCIAL STATEMENT 14Excludes Navy funds expended on dredging river channel in 1944 and Coast Guard funds expended for channel dredging in 1948 and 1949. "sExcludes $1,000 Coast Guard funds expended and $9,000 expended by Skagit County in fulfilling requirements of local cooperation. "Includes $228,084 appropriated and expended for previous projects. Excludes $40,000 Coast Guard funds and $192,557 Emergency Relief Funds expended. 17Includes $309,177 appropriated and expended for previous projects. Excludes $78,532 Public Works Administration Funds expended. ""Includes $87,785 appropriated and expended for recreation facilities at completed project (Code 710). Excludes $26,000 Emergency Relief Funds expended. 9"Includes $5,000 Advance Procurement Funds expended and $56,500 appropriated and expended under Maintenance and Operation of Dams and Other Improvements of Navigable Waters. 20Excludes $281,000 Works Progress Administration Funds and $85,999 Emergency Relief Funds expended. 21lIncludes $5,035 appropriated and expended for recreation facilities at completed project (Code 710). 22Includes $102,200 appropriated and expended for recreation facilities at completed project (Code 710). 23Includes $136,736 Public Works Acceleration Act Funds and $971,947 for recreation facilities at completed project (Code 710), appropriated and expended. "Includes $174,776 Special Recreation Use Fees and $10,000 Advance Procurement Funds, appropriated and expended. Includes $56,500 appropriated and expended under Maintenance and Operation of Dams and Other Improvements of Navigable Waters. 2"Includes $58,000 Public Works Acceleration Act Funds and $147,983 for recreation facilities at completed project (Code 710); appropriated and expended. 26Includes $774,561 appropriated and expended under Maintenance and Operation of Dams and Other Improvements of Navigable Waters. 2 7Includes $42,221,634 for additional units, $16,276,363 for reregulating dam, and $475,000 for power planning. 28Includes $42,116,678 for additional units, $16,276,363 for reregulating dam, and $475,000 for power planning. 29Includes $224,146 appropriated and expended under Maintenance and Operation of Dams and Other Improvements of Navigable Waters. 38-17 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 38-B AUTHORIZING LEGISLATION See Date Section Authorizing in Text Act Project and Work Authorized Documents June 25, 1910 July 3, 1930 Aug. 26, 1937 Sep. 3, 1954 July 3, 1958 July 14, 1960 as amended Mar. 7, 1974 June 25, 1910 July 3, 1930 June 20, 1938 Sep. 3, 1954 July 14, 1960 Aug. 13, 1968 5. July 14, 1960 as amended July 14, 1960 as amended June 3, 1896 BELLINGHAM HARBOR, WA Whatcom Creek Waterway 26- and 18-foot channels. Entrance channel in Squalicum Creek Waterway. Maintenance of southerly half and westerly end of Squalicum Creek Basin. Small-boat basin adjacent to Squalicum Creek Waterway. Whatcom Creek Waterway, 30-foot channel. EAST BAY MARINA, OLYMPIA HARBOR, WA Construction of 656 feet of concrete floating breakwater and dredging of the entrance and access channels and turning basin. EDIZ HOOK, WA Construction of 10,000 lineal feet of rock revetment, together with initial beach replenishment and annual nourishment. Emergency interim measures necessary to prevent breaching of Ediz Hook prior to construction of authorized project. EVERETT HARBOR AND SNOHOMISH RIVER, WA Training dike 10,500 feet long extending across bar at outlet of old river channel. Raise 6,000 feet of training dike, extend spur dike, widen gap in dike as required, maintain East Waterway and channel to gap. Abandon project for Snohomish River and provide settling basin near 14th Street. Spur dike at Preston Point, remove training dike north of river outlet, enlarge channel to 14th Street, and deepen settling basin. Widen channel from settling basin to gap; extend channel to head of Steamboat Slough; and a settling basin within upper channel reach. Raise and extend existing training dike; and construct breakwater on westerly and southerly sides of 14th Street small-boat basin.4 FLOATING BREAKWATER PROTOTYPE TEST PROGRAM, WEST POINT, SEATTLE, WA Construction, placement, monitoring, and removal of two types of floating breakwater, a concrete box design and a pipe-tire mat design. FRIDAY HARBOR MARINA, WA Construction of 1600 feet of concrete floating breakwater. GRAYS HARBOR AND CHEHALIS RIVER, WA South jetty. H. Doc. 1161, 60th Cong. 2d Sess. H. Doc. 187, 70th Cong., 1st Sess. Rivers and Harbors Committee Doc. 70, 74th Cong., 1st Sess? H. Doc. 558, 82d Cong., 2d Sess? S. Doc. 46, 85th Cong., 1st Sess? Sec. 107, P.L. 86-645. Authorized by Chief of Engineers, May 13, 1981 H. Doc. 93-101, 93d Cong., 1st Sess., P.L. 93-251 H. Doc. 1108, 60th Cong., 2d Sess. H. Doc. 377, 71st Cong., 2d Sess. H. Doc. 546, 75th Cong., 3d Sess. H. Doc. 569, 81st Cong., 2d Sess. H. Doc. 348, 86th Cong., 2d Sess. H. Doc. 357, 90th Cong., 2d Sess.5 Sec. 107, P.L. 86-645. Authorized by Chief of Engineers, Feb. 5, 1981 Sec. 107, P.L. 86-645. Authorized by Chief of Engineers, July 9, 1981 Annual Report, 1895, pp. 3517-3533 38-18 2. 6. SEATTLE, WASHINGTON DISTRICT AUTHORIZING LEGISLATION See Date Section Authorizing in Text Act Project and Work Authorized Documents Mar. 2, 1907 Mar. 2, 1907 June 25, 1910 June 25, 1910 Aug. 8, 1917 Jan. 21, 1927 July 3, 1930 Aug. 30, 1935 Aug. 30, 1935 Dec. 22, 1944 as amended Mar. 2, 1945 June 30, 1948 Sep. 3, 1954 Sep. 3, 1954 June 25, 1910 Mar. 4, 1913 Aug. 8, 1917 Sep. 22, 1922 June 26, 19348 Aug. 30, 19359 Dec. 22, 1944 as amended A north jetty 9,000 feet long. The 18-foot channel. Extend north jetty 7,000 feet; length of south jetty fixed at 13,734 feet. A 6-foot channel above Cosmopolis Dredging in bar channel. Dredging in bar channel. 16-foot channel from Cosmopolis to Montesano Reconstruct north and south jetties to an elevation of 16 feet above mean lower low water. Maintain 26-foot channel below Aberdeen (as authorized by Public Works Administration Dec. 11, 1933) and combining projects for Grays Harbor and bar entrance and Grays Harbor, inner portion, and Chehalis River under a modified project for Grays Harbor and Chehalis River. Construction, operation, and maintenance of recreation facilities Maintain 30-foot depth in channel from deep water in Grays Harbor to Port of Grays Harbor Commission terminal, which was deepened from 26 to 30 feet with Navy funds. 14-foot channel to Bay City; breakwater at Westhaven; protection of IPbint Chehalis; and maintenance of Westhaven entrance channel? Dredging and maintenance of a 30-foot channel and turning basin from Aberdeen to Cosmopolis. Additional breakwater, 1,400 feet long, at Westhaven Cove. LAKE WASHINGTON SHIP CANAL, WA For a double lock and fixed dam with gated spillway and necessary accessory works at entrance to Salmon Bay; dredging a channel from locks to deep water in Puget Sound, and excavation by local interests of a channel from locks into Lake Washington. Dredging below locks and revetting canal banks. Increased dimensions of channel between Puget Sound and locks and a 600-foot extension of lower guide pier. Operating and care of locks and dam provided for with funds from War Department appropriations for Rivers and Harbors. Enlarge channel between locks and Lake Washington. Construction, operation, and maintenance of recreation facilities. Rivers and Harbors Committee Doc. 2, 59th Cong., 2d Sess. H. Doc. 507, 59th Cong., 1st Sess. Rivers and Harbors Committee Doc. 29, 61st Cong., 2d Sess. H. Doc. 1125, 60th Cong., 2d Sess. H. Doc. 1729, 64th Cong., 2d Sess. H. Doc. 582, 69th Cong., 2d Sess. H. Doc. 315, 70th Cong., 1st Sess. Rivers and Harbors Committee Doc. 2, 74th Cong., 1st Sess. H. Doc. 53, 73rd Cong., 1st Sess.; Rivers and Harbors Committee Doc 2, 74th Cong., 1st Sess. Sec. 4, Flood Control Act of 1944 Report in Office, Chief of Engineers H. Doc. 635, 80th Cong., 2d Sess. H. Doc. 412, 83d Cong., 2d Sess. H. Doc. 30, 84th Cong., 1st Sess? H. Doc. 953, 60th Cong., 1st Sess. H. Doc. 800, 64th Cong., 1st Sess. H. Doc. 324, 67th Cong., 2d Sess. H. Doc. 140, 72d Cong., 1st Sess.5 Sec. 4, Flood Control Act of 1944 38-19 TABLE 38-B (Continued) 8. REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 AUTHORIZING LEGISLATION See Date Section Authorizing in Text Act Project and Work Authorized Documents 11. PUGET SOUND AND ITS TRIBUTARY July 13, 1892 July 3, 1930 Mar. 2, 1945 Sep. 3, 1954 Mar. 2, 1919 Mar. 3, 1925 July 3, 1930 Aug. 30, 1935 July 13, 1892 Aug. 30, 1935 Oct. 23, 1962 Mar. 4, 191314 16. July 27, 1916 Aug. 30, 19359 Aug. 30, 193515 Mar. 2, 1945 Sep. 3, 1954 12. WATERS, WA Maintenance of the rivers tributary to Puget Sound by snagging and dredging; and removal of floating debris from Seattle Harbor. QUILLAYUTE RIVER, WA Jetty (5 feet high) on easterly side of mouth, and a dike with groins, on westerly side, to stabilize entrance.' Maintenance dredging to provide a channel 6 feet deep and of suitable width from ocean to within river mouth. Raising jetty to 15 feet; channel 10 by 100 feet, 2,000 feet long; moorage basin?12 SEATTLE HARBOR, WA Maintenance of East and West Waterways 750 feet wide and 34 feet deep, and of Duwamish Waterway 20 feet deep and 150 feet wide as far south as Eighth Avenue South Bridge. Enlargement of Duwamish Waterway.i3 Maintenance of East Waterway between 750-foot section and Spokane Street, and turning basin at junction of East and Duwamish Waterways. SWINOMISH CHANNEL, WA Channel 4 feet deep and 100 feet wide, and dike construction. Enlargement of channel to present project dimensions. Removal of navigation hazards at "Hole-in-the-Wall". WATERWAY CONNECTING PORT TOWNSEND AND OAK BAY, WA Canal 15 feet deep, 75 feet wide on the bottom, and about 4,800 feet long; construct jetties to protect channel at southern or Oak Bay end, and a bulkhead for retention of dredging material. WILLAPA RIVER AND HARBOR AND NASELLE RIVER, WA Channel 24 feet deep, 200 feet wide, in Willapa River, and 150 feet wide in the forks. Maintenance of channel over bar to a depth of 26 feet and minimum width of 500 feet. For cutoff channel at Narrows. Channel from deep water in Palix River to Bay Center dock. Widen Willapa River channel to 360 and 250 feet between South Bend and the forks; Tokeland and Nahcotta basins; and Naselle River clearance. 38-20 TABLE 38-B (Continued) Annual Report for 1893, page 342510 H. Doc. 125, 71st Cong., 1st Sess. H. Doc. 218, 78th Cong., 1st Sess. H. Doc. 579, 81st Cong., 2d Sess s S. Doc. 313, 65th Cong., 3d Sess. H. Doc. 108, 68th Cong., 1st Sess. and H. Doc. 126, 71st Cong., 2d Sess s H. Doc. 211, 72d Cong., 1st Sess5 H. Doc. 31, 52d Cong., 1st Sess., and Annual Report, 1892, p. 2752 S. Committee Print, 73rd Cong., 1st Sess. H. Doc. 499, 87th Cong., 2d Sess s H. Doc. 625, 62d Cong., 2d Sess. H. Doc. 706, 63d Cong., 2d Sess. Rivers and Harbors Committee Doc. 41, 72d Cong., 1st Sess. Rivers and Harbors Committee Doc. 37, 73d Cong., 2d Sess. H. Doc. 481, 76th Cong., 2d Sess. H. Doc. 425, 83d Cong., 2d Sess s 13. 14. 15. SEATTLE, WASHINGTON DISTRICT AUTHORIZING LEGISLATION See Date Section Authorizing in Text Act Project and Work Authorized Documents 18. 19. 22. DUNGENESS RIVER, SEQUIM, WA July 24, 1946 Construction of riprap bank protection. as amended May 17, 1950 Aug. 6, 1958 June 22, 1936 Dec. 22, 1944 as amended July 24, 1946 as amended July 24, 1946 as amended Dec. 15, 1970 June 22, 1936 June 28, 1938 June 22, 1936 Dec. 22, 1944 as amended Oct. 23, 1962 Dec. 22, 1944 as amended Mar. 7, 1974 Mar. 7, 1974 May 17, 1950 Dec. 22, 1944 as amended HOWARD A. HANSON DAM, WA Eagle Gorge flood control dam on Green River. Redesignation of project as Howard A. Hanson Dam MUD MOUNTAIN DAM, WA Flood control dam on White River. Construction, operation, and maintenance of recreation facilities. NOOKSACK RIVER, ACME, WA Construction of riprap bank protection. PILCHUCK RIVER, WA Construction of riprap bank protection. PLACER CREEK, ID Construction of 3,700-foot concrete channel to confine Placer Creek flows through Wallace, Idaho. STILLAGUAMISH RIVER, WA Improvement of flood channel by clearing and bank revetment at 26 places; concrete weir at head of Cook Slough; and 2 cutoff channels in Cook Slough. Maintenance of improvements. TACOMA, PUYALLUP RIVER, WA Channel improvement to protect people and industrial section of city of Tacoma. Construction, operation, and maintenance of recreation facilities. WYNOOCHEE LAKE, WA Dam and reservoir for water supply, flood control, irrigation, fish and wildlife, and recreation. Construction, operation, and maintenance of recreation facilities. Transfer of State of Washington as a part of project costs, $696,000 for construction of fish hatchery facilities. Amend contract between city of Aberdeen and United States for use of storage space, permitting deferral of the major portion of the first 10-year payments. ALBENI FALLS DAM, ID Multi-purpose dam with powerhouse. Construction, operation, and maintenance of recreation facilities. 38-21 TABLE 38-B (Continued) Sec. 14, P.L. 79-526 Authorized by Chief of Engineers, June 21, 1985 H. Doc. 271, 81st Cong., 1st Sess? P.L. 85-592 S. Committee Print, Puyallup River, WA, 74th Cong., 2d Sess. Sec. 4, Flood Control Act of 1944 Sec. 14, P.L. 79-526 Authorized by Chief of Engineers, Jan. 10, 1985 Sec. 14, P.L. 79-526 Authorized by Chief of Engineers, July 2, 1984 H. Doc. 357, 91st Cong., 2d Sess' H. Doc. 657, 71st Cong., 3d Sess.s P.L. 75-761 S. Committee Print, Puyallup River, WA, 74th Cong., 2d Sess? Sec. 4, Flood Control Act of 1944 H. Doc. 601, 87th Cong., 2d Sess. Sec. 4, Flood Control Act of 1944 P.L. 93-251 P.L. 93-251 S. Doc. 9, 81st Cong., 1st Sess? Sec. 4, Flood Control Act of 1944 23. 24. 25. 27. 28. 29. 30. REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 AUTHORIZING LEGISLATION July 24, 1946 June 30, 1948 July 9, 1952 Dec. 22, 1944 as amended Oct. 22, 1976 as amended May 17, 1950 Nov. 7, 1966 Jan. 2, 1968 Aug. 13, 1968 June 19, 1970 Dec. 31, 1970 Dec. 31, 1970 Mar. 7, 1974 Mar. 7, 1974 Mar. 7, 1974 Mar. 7, 1974 Mar. 7, 1974 Project and Work Authorized CHIEF JOSEPH DAM - RUFUS WOODS LAKE, WA Multi-purpose dam and powerhouse on Columbia River at Foster Creek. Redesignation of the project as Chief Joseph Dam. Designation of reservoir as Rufus Woods Lake. Construction, operation, and maintenance of recreation facilities. School facilities for education of dependents of construction personnel. LIBBY DAM - LAKE KOOCANUSA, MT Multi-purpose dam and powerhouse, and reregulating facilities. School facilities for education of dependents of construction personnel, Libby project. Airport facility at Kelley Flats, MT. Design standards for relocation of Montana State Highway 37 to be those adopted by State of Montana pursuant to provisions of Highway Safety Act of 1966. Participation with State of Montana in construction, operation and maintenance of fish hatchery facilities. Designation of lake formed by the waters impounded by Libby Dam as Lake Koocanusa. Design and construction of sewage collection and sewage treatment facility as part of relocation of municipal facilities of Rexford, MT; and compensation for railroad employees suffering longterm economic injury through reduction of income as result of the relocation of rail transportation facilities due to the construction of Libby Dam. Phase I design memorandum stage for installation of power generating facilities at Libby Reregulating Dam. Construction of fish production measures to compensate for fish losses attributed to the project, and for acquisition of necessary real estate, construction of access roads and utilities (amends P.L. 91-282 by increasing limitation from $750,000 to $4,000,000). Acquisition of land not to exceed $2,000,000 for prevention of wildlife grazing losses caused by the project. Reimbursement (not to exceed $350,000) to Boundary County, ID for reconstruction of Deep Creek Bridge made necessary by duration of high flows during drawdown operations at Libby Dam. Compensation, not to exceed $1,500,000, to Drainage Districts and owners of leveed and unleveed lands, in Kootenai Flats, Boundary County, ID, for damages caused by duration of higher flows during drawdown operations at Libby Dam. Documents H. Doc. 693, 79th Cong., 2d Sess.s P.L. 858, 80th Cong., 2d Sess. P.L. 469, 82d Cong., 2d Sess. Sec. 4, Flood Control Act of 1944 P.L. 94-587 P.L. 95-26 H. Doc. 531, 81st Cong., 2d Sess.s P.L. 89-789 P.L. 90-23916 P.L. 90-48317 P.L. 91-28218 P.L. 91-625 P.L. 91-611 S. Doc. 93-29, 93d Cong., 1st Sess., P.L. 93-251 P.L. 93-251 P.L. 93-251 P.L. 93-251 P.L. 93-251 38-22 TABLE 38-B (Continued) See Date Section Authorizing in Text Act 31. 32. SEATTLE, WASHINGTON DISTRICT TABLE 38-B AUTHORIZING LEGISLATION (Continued) 1 Contains latest published map of Squalicum Creek Waterway. 'Contains latest published map of small-boat basin. 'Contains latest published map of Whatcom Creek Waterway. 'Deferred. sContains latest published map. 6Inactive. 7A portion deferred. 'Permanent Appropriations Repeal Act. 'Included in Public Works Administration Program. lOAnnual Report for 1913 contains latest published map (page 3127). 11A portion inactive. 12Maintenance of these items, as well as sandspit north of James Island, is included in this modification. "Includes settling basin of 100,000 cubic yards capacity which has been classified as inactive. 14Annual Report of 1915 contains latest published map (page 3441). "Included in Emergency Relief Program, May 28, 1935. 16 Supplemental Appropriations Act of 1968, Section 502. "17Flood Control Act of 1968, Section 212. 1 River Basin Monetary Authorization and Miscellaneous Civil Works Amendments Act of 1970, Section 7. 38-23 TABLE 38-C REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 OTHER AUTHORIZED NAVIGATION PROJECTS For Last Cost to Sep. 30, 1985 Full Report Operation See Annual and Project Status Report For Construction Maintenance Anacortes Harbor, WA Completed 1983 222,3455 544,23925 Anacortes Navigation Channel, WA' Completed 1977 825,2636 - Bellingham Harbor, WA (I&J Street Waterway)' Completed 1966 125,634- Bellingham, Squalicum Small Boat Harbor, WA' Completed 1981 1,744,0257 - Blaine Harbor, WA Completed 1958 346,650 - Columbia River, Wenatchee to Kettle Falls, WA Completed 1923 274,3908 7,693 Edmonds Harbor, WA2 Completed 1966 - - Flathead River, MT Completed 1901 9,811 - Hammersley Inlet, WA Completed 1950 9,000 10,683 Hoquiam River, WA Completed 1950 51,294 5,316 Kenmore Navigation Channel, WA' Completed 1982 946,0009 - Kingston Harbor, WA Completed 1967 262,57010 5,00011 Kootenai River, ID and MT Completed 1933 9,255 5,643 Lake Crockett, WA Completed 1983 377,89712 512,940 Mats Mats Bay, WA' Completed 1970 137,679 ' 3 -- Neah Bay, WA Completed 1982 2,057,266 1,854,058" Okanogan and Pend Oreille Rivers, WA Abandoned 1913 63,880 7,634 Olympia Harbor, WA Deferred 1975 442,782"5 525,37716 Polson Bay, Flathead Lake, MT Completed 1918 4,491 259 Port Angeles Harbor, WA3 Completed 1960 470,873 - Port Gamble Harbor, WA Completed 1953 11,911' 7 13,337 Port Orchard Bay, WA4 Completed 1928 42,804 - Port Townsend, WA Completed 1974 480,89918 26,787 Shilshole Bay, Seattle, WA Completed 1962 2,575,091"9- Skagit River, WA Completed 1950 102,33020 36,258 Stillaguamish River, WA Inactive 1946 4,23421"- Tacoma Harbor, WA Completed 1983 2,383,89122 1,314,745" Westhaven Cove Small Boat Basin, WA' Completed 1981 2,000,00024 - . 'Authorized by Chief of Engineers under authority of Section 107, Public Law 86-645. 2Constructed by local interests. Corps of Engineers is responsible for maintenance. 3Maintenance by Port of Port Angeles. 4No maintenance required. "Excludes $59,523 contributed funds and $2,000 Coast Guard funds expended. 6Includes $87,963 preauthorization cost. Excludes $457,200 contributed funds expended. 'Includes $132,349 preauthorization cost and excludes $1,570,886 contributed funds expended. Includes $40,790 appropriated and expended for WA State Sales and Use Tax, FY 85. gIncludes $8,005 expended for previous project. Excludes $50,000 expended by State of Washington in fulfilling terms of local cooperation. 'Includes $148,765 preauthorization cost. "Excludes $390,753 contributed funds and $3,000 Coast Guard funds expended. "Mitigation shore damages 12 study expended. Includes $146,150 appropriated and $117,657 expended for recreation facilities at completed project (Code 710). "Excludes $28,288 contributed funds expended. "Includes $34,352 appropriated and expended for WA State Sales and Use Tax, FY 85. " Includes $258,011 for previous projects, and $13,765 expended for restudy Fiscal Years 1970-1973. Excludes $160,936 Public Works Administration Funds expended. "Includes $14,488 expended for previous project. "Excludes $21,260 contributed funds expended. "Excludes $92,423 contributed funds expended. "Excludes $15,000 Coast Guard funds expended. 2"I0ncludes $2,500 expended for previous project. 21For economic study only. "Includes $159,584 appropriated and expended for previous projects. Excludes $51,609 Public Works Administration Funds and $1,144,416 contributed funds expended. Excludes $62,697, value of work contributed by Port of Tacoma in fulfilling requirements of local cooperation. "Includes $5,347 appropriated and expended for previous projects. Excludes $222,500 contributed funds expended. 24Includes $178,371 preauthorization cost and excludes $1,230,035 contributed funds expended. "Excludes $5,000 contributed funds expended. 38-24 SEATTLE, WASHINGTON DISTRICT TABLE 38-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS For Last Cost to Sep. 30, 1985 Full Report Operation See Annual and Project Status Report For Construction Maintenance American Lake, Vicinity of Fort Lewis, WA' Completed 1957 59,5825- Bear Creek, Flathead County Bridge, near Essex, MT2 Completed 1971 1,424- Blackfoot River, Matt Little Road, MT2 Completed 1964 17,836- Bogachiel River, Highway 101, near Forks, WA2 Completed 1981 156,000- Bogachiel River, Undie Road, Forks, WA2 Completed 1981 57,000- Cedar River, Renton, WA2 Completed 1949 32,264- Chehalis River, City of Chehalis, Raw Water Pumphouse, WA2 Completed 1966 35,454- Chehalis River, Independence Road, Thurston County, WA2 Completed 1965 47,916- Chehalis River, Montesano, WA2 Completed 1977 140,080- Clallam Bay, Sekiu, WA2 Completed 1977 48,698- Clallam River, Highway 112, WA2 Completed 1981 43,500- Clark Fork River, Drummond, MT2 Completed 1978 18,660- Clark Fork River, Missoula, MT Completed 1983 385,0106- Clark Fork River, Missoula, MT2 Completed 1978 31,548- Clark Fork River, Superior, MT2 Completed 1971 28,356- Clark Fork River, Vicinity of Plains, MT2 Completed 1950 27,947- Clearwater River, Jefferson County Road, WA2 Completed 1968 50,0007- Clearwater River, Queets River Bridge, WA2 Completed 1950 49,165- Coeur d'Alene, Spokane River, ID Completed 1941 152,872- Coeur d'Alene River, Springston, ID2 Completed 1950 25,452- Columbia River Basin, Local Protection Projects, ID, MT, and WA: Entiat River, WA Inactive 1958 -- Lightning Creek, Clark Fork, ID Completed 1959 42,726- Methow River, WA Inactive 1958 -- Okanogan River, WA Inactive 1958 1,1008- Yakima River at Ellensburg, WA Inactive 1980 30,0009 Deschutes River, Gleason Road Bridge, near Tumwater, WA2 Completed 1965 26,292- Deschutes River, Rich Road Bridge, near East Olympia, WA s Completed 1967 22,956- Dungeness River, Area #5, WA2 Completed 1950 2,155- Dungeness River, Area #8, WA2 Completed 1950 2,895 Dungeness River, Clallam County, WA1 Completed 1964 52,0401 Dungeness River, Sequim, WA2 Completed 1981 99,000 Dungeness River, Taylor Cut-off Road, WA2 Completed 1961 14,0931 Elwha River, Clallam County, WA2 Completed 1951 17,303 Entiat River, Chelan County, WA2 Completed 1978 38,000 Flathead River, MT2 Completed 1972 20,940 Flathead River, Bradley Channel Area, MT2 Completed 1955 26,265 Flathead River, near Kalispell, MT2 Completed 1948 33,347 38-25 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 38-E OTHER AUTHORIZED FLOOD CONTROL (Continued) PROJECTS For Last Cost to Sep. 30, 1985 Full Report Operation See Annual and Project Status Report For Construction Maintenance Flathead River, near Kalispell, MT Flathead River, Old Steel Bridge, near Kalispell, MT2 Foster Creek Road, Douglas County, WA2 Green River between Kent and Auburn, WA and Allentown, WA2 Green River, State Highway 181, WA2 Henderson Bay, Purdy, WA2 Hoh River, County Road 16, WA2 Hoh River, U.S. Highway 101, WA2 Hoh River Road, Jefferson County, WA (HO 1360)2 Hoh River Road, Jefferson County, WA (HO 1361)2 Hoh River Road, Jefferson County, WA (HO 1362)2 Hoh River, near Forks, WA2 Hoko River, Sekiu, WA2 Hood Canal, Hoodsport, WA2 Hoquiam River, WA2 Kootenai River, Bonners Ferry, ID2 Kootenai River, Kootenai Flats Area, District #1, ID2 La Conner, Swinomish Channel, WA2 Methow River, WA (MET 1-74)2 Methow River, WA (MET 2-74)2 Methow River, WA (MET 3-74)2 Methow River, Barclay Canal, WA2 Methow River, Twisp, WA2 Methow River, Twisp-Carlton Highway, Vicinity of Twisp, WA2 Methow River, Vicinity of Pateros, WA2 Mineral Creek, Lewis County, WA2 Moclips River, Moclips, WA2 Naches River, Naches, WA2 Newaukum River, Lewis County, Hamilton, WA2 Nisqually River, near Elbe, WA2 Nisqually River, Thurston County, WA2 Nisqually River, Vicinity of Elbe, WA2 Nooksack River, Guide Bridge Location, WA2 Nooksack River, above Highway 1Z Bridge, WA2 North Fork Skykomish River, WA2 Okanogan River, WA2 Deferred 1981 300,0008 Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed 1964 1962 1972 1976 1977 1980 1980 1956 1961 1964 1983 1977 1977 1977 1950 1965 1979 1974 1974 1974 1976 1949 1951 1951 1972 1977 1982 1972 1948 1960 1952 1950 1960 1981 1974 13,438 50,000 24,605 27,001 37,359 143,000 194,000 22,08212 11,916 41,622 173,00012 21,083 59,812 52,600 42,325 14,885 40,525 15,700 11,200 13,450 19,810 31,783 33,200 11,726 11,836 17,608 59,000 24,792 37,636 26,790 19,445 6,075 10,807 222,500 10,100 38-26 SEATTLE, WASHINGTON DISTRICT TABLE 38-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS (Continued) For Last Cost to Sep. 30, 1985 Full Report Operation See Annual and Project Status Report For Construction Maintenance Okanogan River, Omak, WA' Completed 1981 2,231,03014 - Okanogan River, Oroville, WA Completed 1982 1,787,63015- Pilchuck River, WA2 Completed 1971 10,713- Pilchuck River, Everett, WA2 Completed 1980 54,000- Pilchuck River, State Highway 92, Granite Falls, WA2 Completed 1971 30,973- Powell County High School, Deer Lodge, MT2 Completed 1964 11,291- Pysht River, Sekiu, WA2 Completed 1977 86,160- Queets River, Jefferson County Sewage Lagoon, WA2 Completed 1981 125,000- Quillayute River, Quileute Tribal Float and Bridge, WA2 Completed 1972 39,300- Quinalt River, Grays Harbor, WA2 Completed 1981 208,000 Quinalt River Road, Jefferson County, WA2 Completed 1961 15,9281" Rock Creek, Granite County, MT2 Completed 1974 49,657- Rock Creek, Missoula County, MT2 Completed 1973 31,565- Rock Creek Road, MT2 Completed 1980 50,000- Rye Creek, MT2 Completed 1973 22,819 St. Maries, St. Joe River, ID Completed 1942 357,698- Sammamish River, WA Completed 1967 2,582,53617 Sauk River, WA2 Completed 1974 20,860- Sewage Treatment Plant, Missoula, MT2 Completed 1965 50,00018- Shelton Creek, WA1 Completed 1979 872,02119- Skagit Creek, WA (Avon Bypass) Deferred 1968 54,4687- Skagit River, WA (Levee and Channel Improvements) Inactive 1982 1,934,79220 Skagit River, Cape Horn Road, WA2 Completed 1966 46,489- Skagit River, Deadman's Slough, WA2 Completed 1980 93,000- Skagit River, Pressentin Creek, WA2 Completed 1980 137,000- Skagit River, South Skagit Highway, WA2 Completed 1963 40,753- Skagit River, South Skagit Highway, WA Job 66-1)2 Completed 1966 17,719 Skagit River, South Skagit Highway, WA (Job 67-1)2 Completed 1967 50,0001 Snohomish River, Lowell- Snohomish River Road, WA2 Completed 1969 44,227 Snohomish River, Snohomish, WA2 Completed 1970 60,9002 Snoqualmie River, West Snoqualmie, WA2 Completed 1977 15,565 Soleduck River Bridge, WA2 Completed 1961 16,43623 Soleduck River, near Mora Road Bridge, WA2 Completed 1963 11,433 Spokane, Spokane River, WA Inactive 1939 2,944- Startup, Skykomish and Wallace Rivers, WA1 Completed 1970 271,713 38-27 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 38-E OTHER AUTHORIZED FLOOD CONTROL (Continued) PROJECTS For Last Cost to Sep. 30, 1985 Full Report Operation See Annual and Project Status Report For Construction Maintenance Stillaguamish River, South Fork, Mountain Loop Highway, near Robe, WA2 Completed 1964 50,0002- Stillwater River, MT2 Completed 1973 17,457- Stillwater and Whitefish Rivers, MT2 Completed 1977 34,513- Strong Creek, Hope, ID2 Completed 1970 8,442- Tahola. WA2 Completed 1979 223,893- Upper Puyallup River, WA3 Completed 1938 71,49525- Wenatchee Canyons 1 and 2, WA4 Active 1977 544,331- West Fork Foster Creek, WA2 Completed 1958 19,513- Willapa River at Raymond, WA Deferred 1982 508.,13026- Wynoochee River, County Road 141, WA2 Completed 1976 111,072- Wynoochee River, near Montesano, WA2 Completed 1969 50,00027 Wynoochee River, near Montesano, WA (WR-1-72)2 Completed 1972 50,000- Yakima. Yakima River, WA Completed 1948 381,961- Yakima River, Cle Elum, WA2 Completed 1949 8,047- Yakima River, below mouth of Teanaway River, near Cle Elum, WA2 Completed 1947 48,272- Yakima River, West Richland, WA2 Completed 1977 36,768- Yakima River, Yakima, WA2 Completed 1983 125,500- 1Authorized by Chief of Engineers under authority of Section 205, Public Law 858, 80th Congress, as amended. 2Authorized by Chief of Engineers under authority of Section 14, Public Law 526, 79th Congress, as amended. 3Authorized by Works Progress Administration Project No. OP 65-93-917. 4Authorized by Secretary of Army under authority of Section 201, Public Law 298, 89th Congress, H. Doc. 91-370. 'Excludes $10,000 contributed funds expended. 6Includes $7,850 appropriated and expended for recreation facilities at completed project (Code 710). Excludes $13,500 contributed funds expended. 7Excludes $24,728 contributed funds expended. 8Preconstruction planning only. 9Excludes $14,300 for restudy. '�Excludes Public Works Acceleration Act funds of $340,066. "Excludes $3,314 contributed funds expended. 12Excludes $21,807 contributed funds expended. 13Excludes $189,000 Federal Highway Administration funds expended. "'Includes $125,000 preauthorization cost. Includes $1,030 appropriated and expended for WA State Sales and Use Tax, FY 85. 15"Includes $160,700 preauthorization cost. Includes $8,130 appropriated and expended for WA State Sales and Use Tax, FY 85. "Excludes $4,843 contributed funds expended. "Excludes $696,923 contributed funds expended. Includes $117,420 preconstruction planning cost. "Excludes $5,340 contributed funds expended. 19"Includes $100,221 preauthorization cost. 2oIncludes $1,806,792 preauthorization planning cost. 21Excludes $24,488 contributed funds expended. 22Excludes $14,307 contributed funds expended. 23Excludes $1,960 contributed funds expended. 24 2-EEmxcelrugdeensc y$ 46,182 contributed funds expended. Relief Funds, Works Progress Administration. Excludes $13,704 contributed funds expended. 26Includes $32,630 preconstruction planning cost. 27Excludes $21,311 contributed funds expended. 38-28 SEATTLE, WASHINGTON DISTRICT TABLE 38-F OTHER AUTHORIZED MULTIPLE PURPOSE PROJECTS, INCLUDING POWER For Last Cost to Sep. 30, 1985 Full Report See Annual Operation and Project Report For Construction Maintenance Priest Rapids Dam, Columbia River, WA 1954 350,0001 'For partnership planning. Excludes funds expended for 544. 83d Congress. Project constructed by Grant County Public acquisition of lands under partnership arrangement for Priest Utility District. Rapids and Wanapum Dams. in accordance with Public Law TABLE 38-G DEAUTHORIZED PROJECTS For Last Full Report Federal Contributed See Annual Date Funds Funds Project Report Deauthorized Expended Expended Columbia River Basin, Local Protection Projects, ID, MT, and WA: Crab and Wilson Creeks, WA 1958 1964 $9,1001 St. Regis River, MT 1958 1978 4,4002 Wenatchee River, WA 1958 1978 2,0003 Hammersley Inlet, WA 1950 1978 - (Uncompleted Portion) Port Angeles Harbor, WA 1960 1977- (Uncompleted Portion) Port Gamble Harbor, WA 1953 1977 -- (Uncompleted Portion) Skagit River, WA 1950 1978 - - (Uncompleted Portion) 'Includes $100 for preauthorization studies and $9,000 for preconstruction planning. 2Includes $3,000 for preauthorization studies and $1,400 for preconstruction planning. 3Preauthorization studies only. 38-29 TABLE 38-H REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 LAKE WASHINGTON SHIP CANAL, WA PRINCIPAL FEATURES OF DOUBLE LOCK AND DAM (See Section 7) Section Large Lock Small Lock Miles above mouth 11/4 11/4 Clear width of chamber Feet 80 28 Maximum available length Feet 760 123 Lift Feet 26 26 Depth on upper miter sill1 Feet 331/2 16 Depth on intermediate miter sill 2 Feet 29 - Depth on lower miter sill2 Feet 29 16 Character of foundation Clay Clay Kind of dam Fixed dam with Fixed dam with gated spillway. gated spillway. Type of construction Concrete Concrete Year completed 1916 1916 Cost 3 3 1Low water in upper pool. 3Cost of double lock and dam was $2,224,712 and the 2Mean lower low water in Puget Sound. emergency gates, completed in 1923, $174,693. TABLE 38-I PROJECT CONDITION SURVEYS Name of Project Date Survey Conducted Washington: Anacortes Harbor Bellingham Harbor Blaine Harbor Edmonds Harbor Hoquiam River Kenmore Navigation Channel Port Townsend Shilshole Bay, Seattle Tacoma Harbor April February-June June February January May July January October 38-30 1985 1985 1985 1985 1985 1985 1985 1985 1984 SEATTLE, WASHINGTON DISTRICT TABLE 38-J FLOOD CONTROL ACTIVITIES PURSUANT TO SECTION 205, PUBLIC LAW 858, 80TH CONGRESS, AS AMENDED (PREAUTHORIZATION) Study Identification Fiscal Year Costs (1985) Bowman Hilton Mobile Home Park, WA $ 51,653 Cottonwood Creek, Deer Lodge, MT 314 Dosewallips River, Brinnon. WA' 1,086 Elwha Klallam Reservation, Elwha River, WA 105,763 Sultan, WA' 82 TOTAL $ 158,898 'Study terminated. TABLE 38-K EMERGENCY FLOOD CONTROL ACTIVITIES REPAIR, FLOOD FIGHTING, AND RESCUE WORK (PUBLIC LAW 99, 84TH CONG., AND ANTECEDENT LEGISLATION) Project and Location Fiscal Year Costs (1985) Disaster Preparedness Emergency Operations Rehabilitation $ 240,301 30,769 13 TOTAL $ 271,083 38-31 ___ WALLA WALLA, WA, DISTRICT* This District' consists of all Columbia River drainage and tributaries thereto between the head of the McNary pool (River Mile 345.4) and the Umatilla Bridge (River Mile 290.5) below McNary Dam, except the Yakima River Basin above the Van Giesen Street Bridge (River Mile 8.4) near Richland, WA. IMPROVEMENTS Navigation 1. Navigation Work Under Special Authorization .................. Flood Control 2. Columbia River Basin, Local Flood Protection Projects ............... 3. Big Wood River, ID .................... 4. Boise River, ID ...................... 5. Catherine Creek OR................... 6. Colfax, Palouse River, WA .............. 7 Flood Control Work Under Special Authorization ............ 8. Inspection of Completed Flood Control Projects....................... 9. Inspection of Completed PL-99 Works .... 10. Lucky Peak Lake, ID ................. 11. Mill Creek Lake, WA .................. 12. Rapid Creek, ID ....................... 13. Scheduling Flood Control Reservoir Operations.................. 14. Sewage Lagoons, Vale, OR .............. 15. South Fork, Boise River, ID ............. 16. Weiser River, ID ..................... 17. Willow Creek Lake, Heppner, OR ........ Multiple-Purpose Projects, Including Power 18. Dworshak Dam and Reservoir, ID ..... .. 19. Ice Harbor Lock and Dam-- . Lake Sacajawea, WA ................... 20. Lewiston-Clarkston Bridge, ID and WA .......................... 21. Little Goose Lock and Dam- Lake Bryan, WA ..................... 22. Lower Granite Lock and Dam, WA...... Page 23. Lower Monumental Lock and 39-2 Dam-Lake Herbert G. West, WA ........ 24. Lower Snake River Fish & Wildlife Compensation Plan, WA, OR, ID......... 25. McNary Lock and Dam-Lake Wallula, 39-2 OR and WA ......................... 39-2 26. Snake River Downstream from Johnson 39-2 Bar Landing, OR, WA and ID .......... 39-2 39-2 General Investigations 27. Surveys.............................. 39-2 28. Collection and Study of Basic Data ...... 29. Continuation of Planning and Engineering 39-3 39-3 39-3 39-3 39-4 39-4 39-4 39-4 39-4 39-4 39-5 39-5 39-6 39-6 39-6 30. Adva Tables nce Engineering and Design ........ Page 39-7 39-8 39-8 39-8 39-9 39-9 39-9 39-9 Table 39-A Cost & Financial Statement .... 39-10 Table 39-B Authorizing Legislation ........ 39-13 Table 39-C Other Authorized Navigation Projects ..................... 39-16 Table 39-D Not Applicable ............... Table 39-E Other Authorized Flood Control Projects ..................... 39-16 Table 39-F Not Applicable ............... Table 39-G Deauthorized Projects ......... 39-18 Table 39-H Columbia River Basin, Local Flood Control Projects ......... 39-18 Table 39-I Inspection of Completed Flood Control Projects .............. 39-19 Table 39-J Principal Data Concerning Navigation Lock, Spillway Dam, Powerplant and Impoundment .. 39-20 Table 39-K Snake River Downstream from Johnson Bar Landing, OR, WA and ID ...................... 39-24 39-1 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Navigation 1. NAVIGATION WORK UNDER SPECIAL ATHORIZATION Navigation activities pursuant to Section 107, Public Law 86-645 (preauthorization). Fiscal year costs were $28,283 for Port of Clarkston, WA reconnaissance report and $18,378 for Clearwater River, Lewiston, ID appraisal report. Flood Control 2. COLUMBIA RIVER BASIN, LOCAL FLOOD PROTECTION PROJECTS Location. Improvements included in this project are along Columbia River and its tributaries. Existing project. Flood Control Act of 1950 approved a general comprehensive plan for Columbia River Basin for flood control and other purposes based on plans in H. Doc. 531, 81st Cong., 2d Sess., and authorized $75 million to be appropriated for partial accomplishment of certain projects. Of that authorization, an amount not to exceed $15 million was allotted for construction of local flood protection works throughout Columbia River Basin, subject to conditions that all work undertaken pursuant to authorization should be economically justified prior to construction, and local cooperation specified in 1936 Flood Control Act, as amended, should be required. (See Tables 39-B and 39-H for projects in Walla Walla District.) Local cooperation. Section 3, Flood Control Act of June 22, 1936, applies. Operations during fiscal year. No projects were recommended for deauthorization during the fiscal year. 3. BIG WOOD RIVER, ID Location. Along Big Wood River from Eagle Creek downstream through the cities of Ketchum, Hailey and Bellevue to the Glendale Bridge in Blaine County, ID. Existing project. Debris removal from a 27.2-mile reach of the Big Wood River near Hailey, ID. Local cooperation. Flood Control District No. 9 has sponsored the project and complied with sponsorship requirements. Operations during fiscal year. New work: Work was completed in FY 1985. 4. BOISE RIVER, ID Location. In Ada and Canyon Counties, ID from the mouth of Boise River, upstream through city of Caldwell, ID to city of Boise, ID. Existing project. Tree and brush removal from Boise River starting at Boise, ID downstream to Caldwell, ID and gravel removal at six locations from Caldwell, ID downstream to the mouth of the Boise River, a total of 54.5 miles. Local cooperation. Flood Control Districts Nos. 10 and 11 and the city of Boise, ID sponsored the project for their respective areas of jurisdiction and complied with sponsorship requirements. Operations during fiscal year. New work: Work was completed in FY 1985. 5. CATHERINE CREEK, OR Location. Catherine Creek is a tributary to the Grande Ronde River located 8 miles east of the City of La Grande, Union County, OR. Existing project. Organic debris such as fallen trees, brush, and a select number of large cottonwood trees were removed from the creek to increase its capacity to convey future floods. The work was funded under authority of Section 208 of the Flood Control Act of 1956. Local cooperation. The Catherine Creek Corridor Improvement District sponsored the project and complied with requirements as set forth in Section 3 of the Flood Control Act of 1936 plus additional requirements set forth in the project document. Estimated cost to the district was $1,000. Operations during fiscal year. New work: Removal of debris was initiated and is scheduled for completion in FY 1986. 6. COLFAX, PALOUSE RIVER, WA Location. On the main stem North and South Forks of the Palouse River and includes a portion of Spring Flat Creek, a tributary stream, all within the city of Colfax, WA. Existing project. Project consists of 3740 feet of concrete lined channel, 4910 feet of revetted channel, and 2330 feet of unrevetted channel and drainage structures. Authorizing legislation was provided under PL 78-534, Section 10, Flood Control Act of 1944. Local cooperation. The city of Colfax has provided the necessary right of way and other sponsorship requirements. Operations during fiscal year. New work: Several concrete flood slabs on the South Fork were cracked and in danger of being uplifted; they were removed and replaced. A problem with storm water collecting behind the levees was corrected by the construction of a drainage ditch on the North Fork in the vicinity of the Sixth Street Bridge. A study was also initiated to determine the adequacy of the present dewatering pump just downstream of Sixth Street Bridge. 7. FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION Flood control activities pursuant to Section 205, Public Law 858, 80th Congress, as amended. Fiscal year costs were $168,694 for preauthorization studies: $29,223, Oakley Westside Channel, ID. An Appraisal Report was submitted and approved. Work was started on hydraulic studies and material investigation of channel; $4,000, Raft River, Cassia County ID; $131,071, Salmon River, Vicinity of Salmon, ID; $4,400, S. Fork Boise River, Elmore County, ID. Emergency flood control activities-repair, flood fighting, and rescue work (Public Law 99, 84th Congress, and antecedent legislation). 39-2 WALLA WALLA, WASHINGTON DISTRICT Federal costs for fiscal year were $66,717 for disaster preparedness, $799,996 for emergency operations, $387,160 for rehabilitation, and $376,354 for advance measures. Emergency Bank Protection (Section 14, 1946 Flood Control Act, Public Law 526, 79th Congress) Fiscal year costs were $8,300 for preauthorization studies: $5,000, Bully and Willow Creeks, OR and $3,300, Lemhi River, Lemhi County, ID. Snagging and clearing of navigable streams and tributaries in interest of flood control (Section 208, 1954 Flood Control Act, Public Law 780, 83d Congress). Fiscal year costs were $9,100 for preauthorization studies: $3,500, Cassia Creek, Cassia County, ID; $1,000, Grande Ronde River, Union County, OR; $2,400, Lemhi River, Lemhi County, ID; $2,200, Little Wood River, Lincoln County, ID. 8. INSPECTION OF COMPLETED FLOOD CONTROL PROJECTS Federal law requires local interests to maintain and operate completed local protection projects in accordance with regulations prescribed by Secretary of Army. Inspections were made to determine extent of compliance and to advise local interests as necessary of measures required to correct deficiencies. A contract to investigate the geological and seismological conditions at Ririe Dam, ID continued through the fiscal year. See Table 39-I for inspections made during fiscal year. Fiscal year costs were $234,873. Total costs to September 30, 1985 have been $1,451,940. 9. INSPECTION OF COMPLETED PL-99 WORKS Inspections are pursuant to Public Law 84-99 which directs the Corps to establish through inspection whether non-federal flood control works will continue to provide the intended degree of flood protection and to determine if the maintenance program is adequate. FY 1985 costs for this program were $31,853. 10. LUCKY PEAK LAKE, ID Location. On Boise River in southwestern Idaho about 10 miles southeast of city of Boise. Existing project. A rolled-earthfill dam about 250 feet high above streambed and 1,700 feet long at crest, with a lake providing a total storage at upper operating lake level of 306,000 acre-feet. (For further details see page 2000 of Annual Report for 1962.) Construction of existing project was initiated November 1949 and completed June 1961. A feasible method of achieving better flood control through diversion into New York Canal, through Lake Lowell, and into the Snake River has been developed but rejected by local interests due to the infrequent use of this diversion method. Since 1961, $103,699,000 in potential flood damages have been prevented by the project. Final Environmental Impact Statement on the initial project was filed with the Council on Environmental Quality on November 29, 1976. A revised draft Environmental Impact Statement for the modification work was filed with the Council on Environmental Quality on September 18, 1978. During the detailed investigation of outlet capacity and the potential for adding hydropower to the existing project, a need for an auxiliary outlet became apparent. Construction of an auxiliary outlet was authorized in the Water Resource Development Act of 1976 but to date it has not been funded. In FY 1978, an "Interim Feasibility Report on Modification of Lucky Peak Dam and Lake" (power facilities) was submitted to the Board of Engineers for Rivers and Harbors and approved. States, agencies, and the Chief of Engineers have commented on the report to the Secretary of the Army. The report was forwarded to the Office of Management and Budget in February 1982. No further action has been taken. A license to construct and operate power facilities at the project was issued by the Federal Energy Regulatory Commission (Project #2832) to the Boise Project Board of Control on June 10, 1980 and modified on October 9, 1980. The license required that construction begin within two years and be completed within four years of the issuing date of the license. A two year extension of the license was granted on June 10, 1982 by FERC. Construction of the Phase I portion of an auxiliary outlet tunnel was started in May 1984 and completed in June 1984. Phase II (the final phase) was started in July 1985 and is expected to be completed in July 1986. Local cooperation. None required. Operations during fiscal year. Maintenance: Normal operation for flood control, recreation, and irrigation continued. A contract was awarded and work began on rehabilitation of the existing outlet structure. Work consists of the placement of steel liners on the flip lip section which is immediately downstream from the outlet control valves and is scheduled for completion in December 1985. 11. MILL CREEK LAKE, WA Location. In and upstream from Walla Walla, WA, on Mill Creek, a tributary of Walla Walla River. Existing project. Off-stream earthfill storage dam about 145 feet high and 3,200 feet long at the crest, two concrete-lined outlet channels, an earthfill diversion dam, and division structures. Authorizing legislation to provide a channel through the city of Walla Walla was added to the project in 1941. Federal cost of original project was $2,162,155. Adding recreation facilities has thus far increased project costs by $96,340 to $2,258,495. Not included in that cost is $80,000 contributed by local interests toward construction of the channel through Walla Walla. (For further details see page 2005 of Annual Report for 1962.) Construction of dam and appurtenant works was completed in 1942. Paving of channel through city of Walla Walla was completed in 1948. Park and recreation facilities were opened to the public July 1, 1964. Since 1942, $4,143,000 in potential flood damages have been prevented by the combined storage and channel operation. Final Environmental Impact Statement was filed with the Council on Environmental Quality on December 12, 1975. 39-3 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 The rehabilitation of the existing project is designed to correct the seepage and internal erosion which have occurred during each subsequent filling of the reservoir requiring limited flood control use of the project. Project cost estimate for the rehabilitation is $17,400,000. Local cooperation. Fully complied with. For details see page 2006 of Annual Report for 1962. Operations during fiscal year. Major rehabilitation. New work: Contracts for the concrete cutoff wall at the dam, return channel, the debris barrier and seals on control gates are completed. Rehabilitation work continues on the segment of the channel from the Diversion Dam to Tausick Way Phase II & 9th Street to Gose Street Phase I. This work will enable the channels to handle short duration standard project floods. Maintenance: Routine maintenance by Government forces continued, which included regulation of water control structures and care of recreation areas. 12. RAPID CREEK, ID Location. The project was on one mile of Rapid Creek through the City of Inkom, Bannock County, ID. Existing project. Gravel, brush, and small trees were removed from the creek to increase its capacity to convey future floods. The work was funded under authority of Section 208 of the Flood Control Act of 1956. Local cooperation. The City of Inkom sponsored the project and complied with requirements as set forth in Section 3 of the Flood Control Act of 1936 plus additional requirements set forth in the project document. Estimated cost to the district was $1,000. Operations during fiscal year. New work: Removal of debris was completed in FY 1985. 13. SCHEDULING FLOOD CONTROL RESERVOIR OPERATIONS Functional regulation of non-Corps projects was accomplished under several authorities. Regulations of Palisades, Little Wood, and Anderson Ranch Reservoir in Idaho, and Bully Creek, Warm Springs, Agency Valley, and Mason Reservoirs in Oregon, was accomplished as authorized under Section 7, Flood Control Act of 1944, and coordinated with the Bureau of Reclamation. Flood control operations at Jackson Lake, Arrowrock Reservoir, and Lake Lowell were in accordance with formal agreements with the Bureau of Reclamation. Regulation of American Falls, Owyhee, Magic, Mackay, Cascade, and Deadwood Reservoirs, Idaho, for flood control was accomplished under informal agreements. Brownlee, Oxbow, and Hells Canyon Reservoirs provided flood control regulation in accordance with provisions of the Federal Power Commission license to Idaho Power Company. Fiscal year costs were $201,189. 14. SEWAGE LAGOONS, VALE, OR Location. On the Malheur River, Malheur County, OR. The project is located on the west half of Section 21 and east half of Section 20, T18S, R45E, Boise Meridian. Existing project. Channel rectification, levees and Sbank protection were provided to the city of Vale under Public Law 516 in 1960. The city has maintained the project and periodically placed concrete and asphalt rubble on the streambank for protection. Local cooperation. The city has sponsored the project and complied with sponsorship requirements. Operations during fiscal year. New work: Work was fiscally completed. 15. SOUTH FORK, BOISE RIVER, ID Location. In Elmore County, ID from village of Pine, ID (River Mile 58) upstream to village of Featherville, ID (River Mile 68). Existing project. Organic debris removal from a 10-mile distance and restoring channel alignment and an existing levee near the Ballentyne Subdivision (River Mile 63). Local cooperation. Elmore County has sponsored the project and complied with sponsorship requirements. Operations during fiscal year. New work: Since the region receives heavy recreational use in the late summer months, work was restricted to non-peak recreation season and was completed in FY 1985. 16. WEISER RIVER, ID Location. In Washington County from mouth of Weiser River upstream to Galloway Diversion Dam. Existing project. Gravel removal at six locations from a distance of approximately 13.2 miles. Local cooperation. Flood Control District No. 3 has sponsored the project and complied with sponsorship requirements. Operations during fiscal year. New work: Work physically was completed. 17. WILLOW CREEK LAKE, HEPPNER, OR Location. On Willow Creek immediately upstream from Heppner and just downstream from junction of Balm Fork and Willow Creek in Section 35, Township 2 South, Range 26 East, Willamette Meridian. Existing project. Project provides flood protection to the city of Heppner and downstream area by controlling runoff from a drainage area of 96 square miles. The dam is a roller compacted concrete structure 160 feet high at crest elevation 2130. Ancillary features include a center uncontrolled spillway with a maximum flood capacity of 93,300 cfs, an outlet works with a capacity of 500 cfs, a minor flow works and diversion works. Gross storage capacity of the project is 13,250 acre-feet, consisting of 7,750 acre-feet for exclusive flood control, 1,750 acre-feet for joint flood control and irrigation, 1,750 acre-feet exclusive irrigation, and 2,000 acre-feet dead storage for fish, wildlife, recreation, sediment accumulation, and aesthetics. Limited recreation facilities are being provided. The final Environmental Impact Statement was filed with the Environmental Protection Agency on December 39-4 WALLA WALLA, WASHINGTON DISTRICT 20, 1979. The provisions of the Clean Water Act were met by a Section 404(bXl) Evaluation and a public notice issued January 12, 1980, and a Section 401 certification from the State of Oregon on February 15, 1980. Land acquisition is about 99 percent complete. Contracts have been completed for relocation of the city water main, and construction of the water tank, road, and main dam. Local cooperation. None required. Operations during fiscal year. New work: Main dam construction was completed in March 1983. Contract work on Alfalfa Street bridge and channel, and fencing at the site were completed in FY 1985. Maintenance: (See Portland, OR District Annual Report). Multiple-Purpose Projects, Including Power 18. DWORSHAK DAM AND RESERVOIR, ID Location. Dam is on North Fork Clearwater River 1.9 miles above its junction with Clearwater River, near Orofino, ID, and about 35 miles east of Lewiston, ID. Existing project. A straight concrete gravity dam about 717 feet in maximum structural height above foundation and 3,300 feet long at crest elevation 1613. The reservoir has a gross storage capacity of 3,453,000 acrefeet, of which 2,000,000 acre-feet are effective for both local and regional flood control, and for at-site and downstream power generation. In addition, the reservoir, extending 53 miles into a rugged and relatively inaccessible timberland, provides important transportation savings in connection with movements of marketable logs. The project also provides substantial recreation benefits. Powerhouse includes two 90,000 and one 220,000 kilowatt generating units, with provisions for three additional 220,000 kilowatt units for an ultimate installed capacity of 1,060,000 kilowatts. Principal project data are set forth in Table 39-J. Fish passage at Dworshak Dam is not feasible due to the height of the dam and a hatchery has been built below the dam to assure continuance of anadromous fish runs. The reservoir area has been habitat for elk, deer, and other wildlife. Project plans include acquisition of land outside reservoir limits to mitigate losses of big game winter browse areas inundated by reservoir. Construction of the project started April 1963 and is complete except for recreation facilities and fish and wildlife development. It became operational for flood control June 1972 and has prevented about $737,000 in potential flood damages downstream since then. All project lands have been acquired except those required to replace the loss of wildlife browse areas from inundation by reservoir. Relocations are estimated to be 100 percent complete; dam, 100 percent; fish and wildlife facilities, 96 percent; powerplant, 100 percent; reservoir clearing, 100 percent; and recreation facilities, 90 percent. A reconnaissance report justifying the feasibility and cost benefits for the addition of a 220,000-kilowatt fourth generating unit was completed in FY 1978. Environmental and economic studies on additional generating units have been curtailed due to public opposition. Units 4, 5, and 6 are now classified "inactive". Power generating Unit No. 1, 90,000-kilowatt capacity, was put in service March 1, 1973; Unit No. 2, also 90,000-kilowatt capacity, began producing April 6, 1973; Unit No. 3, 220,000-kilowatt capacity, went on the line April 20, 1973. Power generation through September 1984 has been 22.47 billion kilowatt hours. Eighty mini-recreation sites have been established along the reservoir shoreline. Each site includes at least a picnic table, U.S. Forest Service-type fireplace, and chemical toilet. Some of the sites have several picnic tables. Dent Acres and Freeman Creek recreation sites are open to the public. Facilities consist of a boat launching ramp, boat docks, car-trailer parking, comfort stations, and fully developed overnight camping at each site. Local cooperation. None required. Operations during fiscal year. New work: Wildlife habitat browse development continues on project lands to provide winter browse for elk and deer. Contracts were awarded and work begun on Energy Recovery Contract at the Dworshak Hatchery, Three Meadows Group Camp, Freeman Creek Road slide repair, electrical service to Three Meadows Group Camp. Work was completed on electrical service to Big Eddy Recreation area. Maintenance: Normal operation and maintenance continued. Hatchery operations were impaired by an infection of IHN virus which caused a nine percent decrease in steelhead smolt releases from 1984 levels. In Spring 1985, 1,700,000 steelhead smolts weighing 225,000 pounds were released. A return of 14,000 adults in Spring 1985 is expected to produce the hatchery's capacity of 2,900,000 smolts for 1986 release. In addition to steelhead, the hatchery released 100,000 rainbow trout weighing 25,000 pounds into the reservoir in 1985. 19. ICE HARBOR LOCK AND DAM-LAKE SACAJAWEA, WA Location. On Snake River, 9.7 miles above river mouth at head of Lake Wallula and 12 miles east of Pasco, WA. Existing project. The project includes a dam, powerplant, navigation lock, fish ladders, appurtenant facilities, and relocation of railroads. Project provides for navigation, hydroelectric power generation, recreation, and incidental irrigation. Reservoir has normal operating range between elevations 440 and 437 mean sea level, and extends upstream about 31.9 miles, providing slack water to Lower Monumental Lock and Dam. Structure is about 2,790 feet long and about 130 feet high above streambed. Beginning at south end, project consists of a concrete nonoverflow section, concrete powerhouse, spillway dam, navigation lock, and an earth and rockfill embankment at north abutment. Fish passing facilities, including two ladders, are provided. Powerplant now has three 90,000-kilowatt units and three 111,000-kilowatt units in operation. Spillway dam is 610 feet long, and overflow crest at Elevation 391 mean sea level is surmounted by 10 39-5 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 radial gates, 50 feet wide by 51 feet high, which provide the capacity to pass a design flood of 850,000 cubic feet per second. Deck is at Elevation 453 mean sea level and provides a service road and track for a gantry crane. Navigation lock is single-lift type with clear plan dimensions of 86 by 675 feet and 15-foot minimum depth over the sills. A navigation channel 250 feet wide and 14 feet deep is provided from the mouth of the Snake River to the dam. Principal project data are set forth in Table 39-J. Construction started December 1955 and the project was placed in useful operation January 1962. The project is complete. An Environmental Impact Statement concerning power units 4 through 6 was filed with the Council on Environmental Quality August 1971. Power generation through September 1985 has been 53.36 billion kilowatt hours. Local cooperation. None required. Operations during fiscal year. New Work: Settlement of Washington State Sales and Use Tax Liability Maintenance: Normal operation and maintenance continued. Work was started on painting of spillway gates, washers for fish viewing windows and relocation of sanitary facilities at Levey and Windust Parks. 2.80 billion kilowatt hours of electric energy were delivered to Bonneville Power Administration, the marketing agency. A total of 3,896,607 tons of cargo passed through the navigation lock during calendar year 1984. 20. LEWISTON-CLARKSTON BRIDGE, ID AND WA Location. On the Snake River, River Mile 141.3, 1.7 miles upstream of the existing interstate bridge connecting the towns of Lewiston, ID and Clarkston, WA. Existing project. The project consists of a new fixed high-level four lane highway bridge and approaches on U.S. Highway 12 across the Snake River constructed at a cost "not to exceed $21,000,000". In December 1981 Congress authorized an additional expenditure of $2,200,000 for construction of Lewiston's North Ramp. An approach roadway from the bridge to 16th Avenue in Clarkston, WA was authorized in July 1983 at an additional expenditure of $800,000. Final Environmental Impact Statement Supplement was filed with the Council on Environmental Quality on July 16, 1979. Local cooperation. Non-Federal interests have provided without cost to the United States all lands, easements, and rights-of-way necessary for the construction of the bridge and its approaches, and after construction have agreed to own, operate toll free, and maintain the bridge and approach facilities. The non-Federal costs for land and relocation are $755,193. Operations during fiscal year. New work: Construction of the main bridge structure and Lewiston ramp, and 1600 foot roadway from the bridge to 16th avenue in Clarkston WA. was completed. 21. LITTLE GOOSE LOCK AND DAM-LAKE BRYAN, WA Location. Dam is 70.3 miles above mouth of Snake River at head of Lower Monumental Lake, about 40 airline miles northerly of Walla Walla, WA, and 50 miles westerly of Lewiston, ID. Existing project. The project includes a dam, powerplant, navigation lock, fish ladder, and appurtenant facilities. Improvements provide navigation, hydroelectric power generation, recreation, and incidental irrigation. The reservoir has a normal operating range between Elevations 638 and 633 mean sea level. Lake Bryan extends upstream about 37.2 miles and provides slack water to Lower Granite Lock and Dam. Dam structure is 2,670 feet long and about 160 feet high above streambed and consists of a powerhouse, spillway dam, navigation lock, and necessary nonoverflow sections. Fish passage facilities include one ladder with entrances on both shores with a fish channel through the spillway which connects to the powerhouse fish collection system and south shore ladder. Powerhouse now has six 135,000-kilowatt generating units for a capacity of 810,000 kilowatts. Spillway dam can pass a design flood of 850,000 cubic feet per second. Navigation lock is single-lift type with clear plan dimensions of 86 by 675 feet and a minimum depth of 15 feet over the sills. Relocations along the lake include 32 miles of Camas Prairie Railroad, 5.8 miles of county roads, 2.2 miles of state highways, and Central Ferry bridge. Principal project data are set forth in Table 39-J. A final Environmental Impact Statement was filed with the Council on Environmental Quality on January 8, 1975. Power generation through September 1985 has been 43.24 billion kilowatt hours. Local cooperation. None required. Operations during fiscal year. New work: Settlement of Washington State Sales and Use Tax liability. Maintenance: Normal operation and maintenance continued. A total of 2.99 billion kilowatt hours of electric energy was delivered to Bonneville Power Administration, the marketing agency. Work continued on reconditioning of spillway gates. Work was started on washer for fish viewing windows and repair of lock guide wall anchor cables. Problems with the fish collection facilities caused a high incidence of gas bubble disease sysmptoms and generally poor fish conditions causing an early closure in 1983. Several interim modifications were made in 1984 including the application of shotcrete to the surface of the fingerling collection channel and remodeling of the bypass pipe to alleviate last year's problems, until a new permanent facility can be constructed. A total of 3,165,532 tons of cargo passed through the navigation lock during calendar year 1984. 22. LOWER GRANITE LOCK AND DAM, WA Location. At River Mile 107.5 on Snake River at head of Lake Bryan and about 33 miles downstream from Lewiston, ID. 39-6 WALLA WALLA, WASHINGTON DISTRICT Existing project. The facility includes a dam, powerplant, navigation lock, fish ladder, and appurtenant facilities, and requires about 8 miles of backwater levees along Snake and Clearwater Rivers at Lewiston, ID. Benefits afforded by project include slack-water navigation, power generation, recreation, and incidental irrigation. Water surface at the dam varies between Elevations 738 and 724 to maintain a normal operating range between Elevations 738 and 733 in the Lewiston, IDClarkston, WA area. Dam structure is about 3,200 feet long and about 146 feet high above streambed. Powerhouse now has six 135,000-kilowatt units. Spillway has a capacity for a design flood of 850,000 cubic feet per second. Navigation lock is a single-lift type (105 feet maximum) with clear plan dimensions of 86 by 675 feet and a minimum depth of 15 feet over the sills. Principal project data are set forth in Table 39-J. Construction started July 1965 and is complete. Acquisition of lands is also complete. Lake was filled February 15, 1975 and the first power generating unit went on the line April 15, 1975. Approximately $4,111,000 in potential flood damage has been prevented since the levees became functional. An Environmental Impact Statement was filed with the Council on Environmental Quality November 1971. A revised statement to include the additional units was filed with the Council on Environmental Quality on July 23, 1975. Installation of three additional 135,000-kilowatt generating units was completed in May 1978. Power generation through September 1985 has been 30.78 billion kilowatt hours. Local cooperation. None required. Operations during fiscal year. New work: Settlement of Washington State Sales and Use Tax liability. Maintenance: Normal operation and maintenance continued. Modification to irrigation system at Hellsgate Park, turbine shaft sleeves, fish barge modifcations and purchase of speed reducers for fish pumps. Also, completion of restroom facilities at Clarkston Resource Office. As the first juvenile fish collection point on the Snake River, Lower Granite is a primary component in the District's fish collection and transport program. This program was begun because construction of eight dams on the Columbia and Snake Rivers has had a significant impact on the survival during downstream migration of juvenile anadromous fish such as salmon and steelhead trout. Since the early 1960's, efforts to mitigate the adverse impacts have included extensive research, structural modifications of the dams, installation of turbine screening systems, and implementation of a system for collecting and transporting juvenile fish. The Walla Walla District operates the fish collection and transportation program for the Columbia-Snake system. Three primary collection points have been established at Lower Granite, Little Goose and McNary dams, with fish sorting and handling facilities. Fingerlings collected at these facilities are taken by specially designed barges and trucks to an area downstream of Bonneville Dam and released to make the rest of their journey to the sea. In 1984 and 1985 a total of 9,028,959 and 14,787,592 fingerlings were transported. In 1982 and 1983, state and federal fishery agencies, as well as the tribes, requested increased spills at each dam and separation and bypass of spring chinook at Little Goose and McNary Dams as a back-up means of insuring continuance of the fish runs. This philosophy of spreading-therisk is likely to continue for the foreseeable future and will necessitate both increased spillage for fish passage and a viable trapping and transport program. Advances in fish research and technology will no doubt require modifications to the facilities currently in use. A total of 3.01 billion kilowatt hours of electric energy were delivered to Bonneville Power Administration, the marketing agency. A total of 2,118,148 tons of cargo passed through the navigation lock during calendar year 1983. 23. LOWER MONUMENTAL LOCK AND DAMLAKE HERBERT G. WEST, WA Location. On Snake River at head of Lake Sacajawea, about 45 miles northeast of Pasco, WA, and 41.6 miles above river mouth. Existing project. The facility includes a dam, powerplant, fish ladders, navigation lock, appurtenant facilities, and relocated railroads and highways. The project functions include navigation, hydroelectric power generation, recreation and irrigation. Reservoir has normal operating range between Elevations 540 and 537. The lake extends about 28.7 miles upstream to Little Goose Lock and Dam. The dam is concrete gravity type with earthfill and rockfill abutments. It is 3,800 feet long including abutments, spillway, navigation lock, and powerhouse, and is about 135 feet high above streambed. There are two fish ladders, one at each end of the dam. Powerhouse has six 135,000-kilowatt units for a total capacity of 810,000 kilowatts. Spillway is 508 feet long, and overflow crest at Elevation 483 feet above mean sea level is surmounted by 8 radial gates, each 50 feet wide and 61 feet high. Deck is at Elevation 553 feet and provides a service road and track for a gantry crane. Navigation lock is single-lift type, with lock chamber 86 by 675 feet and minimum depth of 15 feet over the sills. Principal project data are set forth in Table 39-J. Construction began June 1961, and the project was opened to navigation April 1969. The project is complete. A final Environmental Impact Statement was filed with the Council on Environmental Quality on May 21, 1976. Power generation through September 1985 has been 44.23 billion kilowatt hours. Local cooperation. None required. Operations during fiscal year. New work: Settlement of Washington State Sales and Use Tax liability. Maintenance: Normal operation and maintenance continued. Concrete repair to the navigation lock monolith was completed. Work is completed on the restroom facilities at Texas Rapids Park, turbine repair to Unit #1 and continues on repairs to spillway gates, and washer for fish viewing windows. A total of 3.72 billion kilowatt 39-7 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 hours of electric energy was delivered to Bonneville Power Administration, the marketing agency. Cargoes totaling 3,315,635 tons passed through the navigation lock during calendar year 1984. 24. LOWER SNAKE RIVER FISH & WILDLIFE COMPENSATION PLAN, WA, OR, ID Location. At various locations within the Columbia Snake River drainage in the States of Idaho, Oregon and Washington. Existing project. The project will consist of a series of fish hatcheries and wildlife development areas at sites to be selected. The project will compensate for loss of wildlife habitat and anadromous and resident fishery inundated as a result of construction of four multiple purpose dams and reservoirs on the Lower Snake River (Ice Harbor, Lower Monumental, Little Goose, Lower Granite). In 1980 the first release from the McCall, ID summer chinook hatchery was made, and the adult trapping facility which provides the fish egg supply for the McCall Hatchery became operational. The real estate design memorandum, and feature design memorandums on the McCall Hatchery, Hagerman Hatchery, Lookingglass Hatchery, Lyons Ferry Hatchery, Dworshak Hatchery Expansion, Irrigon Hatchery, Magic Valley Hatchery, Sawtooth Hatchery, East Fork Salmon River Satellite Facility, the off-project wildlife lands, and the site selection report have all been approved. A final Environmental Impact Statement was filed with Council on Environmental Quality on November 2, 1977. The compensation plan is 62 percent complete. Estimated Federal cost of the project is $168,000,000. Local cooperation. None required. Operations during fiscal year. New work: McCall Hatchery, Lookingglass Hatchery, Lyons Ferry Hatchery, Sawtooth Hatchery, Hungerman Hatchery, Tucannon Sattelite Hatchery, and spring chinook rearing facilities at Dworshak National Fish Hatchery are in operation. Construction contracts were awarded for: test water well for Magic Valley and Tucannon Hatcheries, also water supply for Magic Valley Hatchery (Phase I). The design for Magic Valley, formerly called Crystal Springs, is complete and scheduled to be awarded in December 1985. The final hatchery site has been selected at Ahsahka, Idaho, for the Clearwater River basin. This hatchery will rear both spring chinook and steelhead. Red River-Crooked River & Powell hatcheries have been identified as satellite sites for the Clearwater Hatchery. 25. McNARY LOCK AND DAM-LAKE WALLULA, OR AND WA Location. On Columbia River 292 miles above mouth, near Umatilla, OR, and 3 miles above mouth of Umatilla River. Existing project. Includes a concrete dam 7,300 feet long overall and 183 feet high above streambed, powerplant with 14 power generating units, navigation lock, fishways, levees and pumping plants, incidental irrigation, and modification and relocation of railroad bridges over the Columbia and Snake Rivers in order to 'eliminate hazards to navigation. Principal project data are set forth in Table 39-J. Construction started May 1947 and is complete. project placed on permanent operating basis and lake raised to Elevation 340 in November 1953. Except for maintenance interruptions, all 14 power units have been in commercial operation since February 1957. A final Environmental Impact Statement was filed with Council on Environmental Quality in June 1976. Power generation through September 1985 has been 190.43 billion kilowatt hours. Local cooperation. None required. Operations during fiscal year. New work: Settlement of Washington State Sales and Use Tax liability. Maintenance: Normal operation and maintenance of project continued. Work accomplished under modernization program included modifications to intake gates, bridge crane and purchase of oil purifier. Contractual work continued on modernization of generator control system. Approximately 6.66 billion kilowatt hours of electric energy were delivered to Bonneville Power Administration, the marketing agency. A total of 5,719,175 tons of commodities passed through the navigation lock during calendar year 1984. 26. SNAKE RIVER DOWNSTREAM FROM JOHNSON BAR LANDING, OR, WA, AND ID Location. On Snake River downstream from Johnson Bar Landing, River Mile 230. Snake River, which is largest tributary of Columbia River, rises in Yellowstone National Park in western part of Wyoming, flows generally westerly for about 1,000 miles, and empties into Col" umbia River near Pasco, WA, 324 miles from Pacific Ocean. Existing project. The River and Harbor Act of 1945 authorized construction of dams as necessary and open channel improvements for purposes of providing slack-water navigation and irrigation between mouth of Snake River and Lewiston, ID. That authorization modified previous authorizations only for that portion of improvement below Lewiston, ID. Acts of June 13, 1902, and August 30, 1935, as they pertain to open river improvement from Lewiston, ID, to Johnson Bar Landing, remain part of existing project. Improvements included in existing project are Ice Harbor Lock and Dam-Lake Sacajawea; Little Goose Lock and Dam-Lake Bryan; Lower Granite Lock and Dam; Lower Monumental Lock and Dam-Lake Herbert G. West; and open-river improvement, Lewiston to Johnson Bar Landing. Each of the four locks and dams is described in an individual report, and cost and financial data for the entire project are shown on Tables 39-A and 39-K. Ice Harbor, Lower Monumental, Little Goose and Lower Granite are in full operation. (See individual reports for details.) (For further details see Annual Reports, page 2246 for 1903; page 1986 for 1906; page 1991 for 1915; and page 1981 for 1962.) 39-8 WALLA WALLA, WASHINGTON DISTRICT Local cooperation. None required. Terminal facilities. On Snake River from the mouth to Johnson Bar Landing there are 18 privately owned barge terminals in use for shipping grain, petroleum products, fertilizers, cement, and other general cargo. There are also 5 marinas and 28 small-boat launching ramps, all open to public use. The facilities serve slack-water navigation to Snake River Mile 140, the site of Lewiston, ID. That slack-water reaches the Lewiston, ID-Clarkston, WA area since the lake behind Lower Granite Dam was filled in February 1975. Operations during fiscal year. See individual reports for Ice Harbor, Lower Monumental, Little Goose, and Lower Granite locks and dams. On Snake River from Lewiston, ID, to Johnson Bar Landing, reconnaissance and condition surveys were conducted and survey markers were maintained. General Investigations 27. SURVEYS The Upper Snake River and Tributaries is the principal ongoing survey. The area covered by the study extends from the headwaters of the Snake River in Wyoming down to and including the Weiser River in Idaho. The potential for supplemental water storage, power generation, and streamflow augmentation to enhance fisheries, continues to be the primary focus. A survey study of the Mill Creek Basin continued in FY 1985. Mill Creek originates in the Blue Mountains in northern Oregon and southern Washington, and is tributary to the Walla Walla River. Water resource problems and needs being investigated include municipal and industrial water supply, power generation, fish enhancement, flood control, and irrigation. The Columbia River and Tributaries is a survey study directed by the North Pacific Division in which the Walla Walla District is participating. A major activity of the CR&T study in FY 85 was the Regional Hydropower Assessment being performed in coordination with the Northwest Power Planning Council. Other work on the CR&T study involved preparation of basin summary reports, development of flood control operational information, completion of the McNary additional Purposes Report and continued work on the John Day and Clearwater River Basin interim studies. A survey study is underway that is investigating the flooding problems associated with the rising water levels of Malheur Lake in Harney County, Oregon. Four consecutive years of above normal runoff from the basin have raised the level of this closed basin lake above any historical record and caused great economic and social impacts on Harney County. Alternatives being investigated include a canal from Malheur Lake that would discharge lake water into the South Fork of the Malheur River, relocations of transportation facilities and land exchange and/or buy out of private lands. Total cost of surveys during fiscal year was $1,218,954. That sum was expended for: flood control studies, $1,060,099; special studies including Soil Conservation Service, Bureau of Reclamation, River Basin and Regional Planning Commissions, Cooperation with States, $37,563; and Special Investigations and FERC Licensing Activities, $121,292. 28. COLLECTION AND STUDY OF BASIC DATA During the fiscal year flood hazard data for a number of locations in the District were collected and analyzed. Flood information was provided to several Federal agencies, to the States of Idaho, Oregon, and Washington, to various cities and counties in those states, and to some private organizations. Total cost of collection and study of basic data during fiscal year was $109,622 which was expended for flood plain management services, $49,792; and technical services, $59,830. 29. CONTINUATION OF PLANNING AND ENGINEERING McNary Lock and Dam (Second Powerhouse), OR and WA McNary Second Powerhouse is a proposed addition on the south shore of McNary Lock and Dam on the Columbia River near Umatilla, OR. The project will increase the present 1127 megawatt generating capacity by an additional 742 megawatts. Provisions are included for compensation of negative impacts on fish and wildlife. The project is estimated to cost $649,000,000 at October 1, 1984 price levels. Annual power benefits are estimated to be $90,063,000. The General Design Memorandum Phase I was prepared under the Water Resource Development Act of 1976, Public Law 94-587, and submitted to the Secretary of the Army on July 1, 1981. Studies were initiated in FY 1982 and continued through FY 1984 on the General Design Memorandum Phase II and the Powerhouse Preliminary Design Report. 1985 expenditures were $21,787 spent on hydraulic model study by Waterway Experiment Station in Vicksburg, MS. 30. ADVANCE ENGINEERING AND DESIGN Zintel Canyon Dam, WA The proposed project consists of a roller compacted concrete dam 102 feet high with uncontrolled spillway and a fixed maximum release outlet works that would create a detention reservoir of 2,500 acre-feet of capacity. The storage comprises 2,100 acre-feet for flood control and 400 acre-feet for sediment. In addition, the project also includes a channel with a capacity of 400 cfs. The plan of improvement would provide protection against heavy rainfall, snowmelt, and thunderstorm floods to the city of Kennewick, WA. Estimated Federal project cost is $5,600,000. Reevaluation of the project was initiated to review economic feasibility with fiscal year costs of $1,556. 39-9 TABLE 39-A REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 COST AND FINANCIAL STATEMENT See Section Total to In Text Project Funding FY 82 FY 83 FY 84 FY 85 Sep. 30, 1985 3. Big Wood New Work 4. Boise River, ID Catherine Creek, OR Colfax, Palouse River, ID 10. Lucky Peak Lake, ID 11. Mill Creek Lake, WA 12. Rapid Creek, ID 14. Sewage Lagoons, Vale, OR 15. South Fork, Boise River, ID 16. Weiser River, ID 17. Willow Creek Lake OR 18. Dworshak Dam and Reservoir, ID 19. Ice Harbor Lock and Dam, WA River, ID 179,000 166,554 232,300 202,864 5. Approp. Cost New Work Approp. Cost New Work Approp. Cost New Work Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost Rehab. Approp. Cost New Work Approp. Cost New Work Approp. Cost New Work Approp. Cost New Work Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost 299,044 298,254 1,596,734 1,594,699 27,894 27,894 317,200 302,422 1,775,000 1,710,362 2, 2, -9,000 3,446 4,200 33,636 38,000 15,603 170,000 170,000 236,500 236,500 38,000 15,603 68,000 5,810,240 131,581 5,796,789 - 19,652,0811 - 19,652,0811 211,650 9,103,854 358,698 9,060,644 - 2,258,4952 - 2,258,4952 302,500 5,901,893 309,107 5,890,055 281,043 15,278,607 346,813 15,277,308 19,500 19,500 67,000 8,100 20,000 -12,000 78,473 -11,573 92,500 12,073 108,000 65,738 19,730,000 19,820,937 4,993,540 4,269,000 4,977,858 3,937,107 -48,100 32,327 -1,100 41,162 19,500 19,500 75,000 75,000 44,400 44,400 106,900 106,900 50,000 37,168,114 402,108 37,168,114 (See Portland, OR District Table 37-A) 3,755,000 1,630,000 3,081,100 3,983,000 4,061,316 1,634,122 3,052,306 3,487,491 4,798,496 3,750,922 4,527,800 5,481,000 4,079,228 4,515,463 4,478,567 5,369,881 30,000 -2,299 200,106 49,004 131,082 -3,290 200,106 50,004 3,549,684 4,800,141 4,004,900 4,168,629 3,665,786 4,869,452 3,969,635 3,875,053 329,473,2963 328,948,0573 43,141,7874 42,942,4514 167,240,7575 167,240,7571 45,374,1036 45,021,4756 39-10 - - 185,000 - - 107,968 - - 71,400 - - 71,400 658,700 698,800 839,000 1, 647,109 740,442 654,651 1, 220,400 223,960 2,770,000 2,846,712 WALLA WALLA, WASHINGTON DISTRICT COST AND FINANCIAL STATEMENT See Section Total to In Text Project Funding FY 82 FY.83 FY 84 FY 85 Sep. 30, 1985 20. Lewiston-Clarkston New Work Bridge, ID & WA 21. Little'Goose Lock and Dam, WA 22. Lower Granite Lock and Dam, WA 23. Lower Monumental Lock and Dam, WA 24. Lower Snake Fish & Wildlife Compensation, ID, OR & WA (Contributed Funds) 25. McNary Lock & Dam-Lake Wallula, OR & WA (Contributed Funds) 26. Snake River Downstream from Johnson Bar Landing, OR, WA & ID Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost New Work Contrib. Cost New Work Approp. Cost Maint. Approp. Cost Maint. Contrib. Cost New Work Approp. Cost Maint. Approp. Cost 4,535,000 692,664 640,000 80,000 22,957,644 4,979,230 693,216 486,402 227,516 22,951,456 - 1,000,500 11 1,000,036 4,904,122 5,436,056 4,868,523 5,292,141 2,052,181 2,047,995 5,896,535 5,776,641 394,800 396,804 5,249,400 5,263,880 - -2,600 -906 -1,706 3,677,483 4,300,500 3,691,797 3,390,678 55,995 56,460 4,338,143 3,998,368 74,689 84,600 5,706,000 5,594,704 18,121 18,141 3,220,629 3,819,029 505,000 1,044,258 2,896,600 2,913,390 2,885,000 2,956,258 4,684,500 4,788,472 49,298 2,372,100 2,540,071 221,355,0227 221,355,0227 35,509,394' 34,889,018' 367,780,3159 367,780,312' 36,194,29710 35,885,27510 236,373,73211 236,373,73211 30,747,40212 30,394,39612 104,165,909 103,709,444 223,965 223,965 322,515,10513 322,515,10513 117,363,03614 115,765,34314 43,707 0 993,184,5891s 993,184,5875 148,387,71916 146,749,02716 18,660,000 19,656,180 25,225,000 13,235,129 19,253,981 19,706,580 25,024,768 12,989,270 - - - 223,965 - - - 223,965 1,137,000 2,822,859 8,944,380 8,582,087 3,420,000 4,180,896 13,533,584 13,933,979 439,000 479,320 10,317,455 11,024,478 2,049,882 2,043,810 19,311,281 19,254,422 202,600 203,380 14,767,500 12,505,395 1,592,806 1,595,240 18,990,856 17,916,334 19,019 19,242 13,147,025 13,859,268 43,707 197,809 209,206 17,455,401 17,305,877 1Includes $570,831 appropriated and expended for Code 710, Recreation Facilities at Completed Projects. 'Excludes $80,000 contributed funds, but includes $96,340 appropriated and expended for Code 710, Recreation Facilities at Completed Projects. 'Includes $2,046,100 regular project construction funds appropriated for and expended by Department of Interior in Fiscal Years 1969 through 1972 for hatchery operations. Includes $655,000 appropriated and expended for additional unit. 4Includes $14,337,680 regular project operation and maintenance funds expended by Department of Interior starting FY 1972 for hatchery operations. FY 72-78 funds of $6,097,000 were charged to the project as a cost, but not as an expenditure for accounting purposes. Includes $59,996 allotted and expended under Special Recreation Use Fees. Includes $56,500 allotted and expended under Maintenance and Operation of Dams and Other Improvements of Navigable Waters. "Excludes $82,500 contributed for artificial spawning channel. Includes $36,748,021 appropriated and expended for additional units 4 through 6. Includes $914,256 appropriated and expended for Code 710, Recreation Facilities at Completed Projects. 'Includes $71,507 allotted and expended under Special Recreation Use Fees; $641,063 appropriated and expended under Maintenance and Operation of Dams and Other Improvements of Navigable Waters. 39-11 TABLE 39-A (Continued) TABLE 39-A (Continued) REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 COST AND FINANCIAL STATEMENT 'Includes $60,941,807 appropriated and expended for additional units 4 through 6. �Includes $621,063 appropriated and expended under Maintenance and Operation of Dams and Other Improvements of Navigable Waters. 'Includes $46,212,534 appropriated and expended for additional units 4 through 6. Excludes $405,819 contributed funds on lock and dam pioject. Includes $63,800 appropriated and expended for Code 710, Recreation Facilities at Completed Projects. 1 lIncludes $338,163 appropriated and expended under Maintenance and Operation of Dams and Other Improvements of Navigable Waters. n'Includes $51,661,371 appropriated and expended for additional units 4 through 6. 12Includes $372,376 appropriated and expended under Maintenance and Operation of Dams and Other Improvements of Navigable Waters. "'Includes $1,976,586 appropriated and expended for Code 710, Recreation Facilities at Completed Projects. "Includes $125,258 allotted and expended under Special Recreation Use Fees and $1,035,860 allotted and expended under Maintenance and Operation of Dams and Other Improvements of Navigable Waters. 15lIncludes $400,150 for new work on previous projects (Pasco to Lewiston), and $34,613 for new work appropriation used for maintenance prior to 1953. Excludes $167,500 contributed funds for new work consisting of $82,500 for new work on existing projects (Pasco to Riparia), plus $82,500 for new work on existing artificial spawning channel. "Includes $186,570 appropriated and expended for maintenance on previous projects (Pasco to Lewiston) and $375,953 appropriated and $372,293 expended open river Pasco to Lewiston and Lewiston to Johnson Bar Landing. 39-12 TABLE 39-B WALLA WALLA, WASHINGTON DISTRICT AUTHORIZING LEGISLATION See Date Section Authorizing in Text Act Project and Work Authorized Documents May 17, 1950 Sep. 24, 1954 as amended Sep. 24, 1954 as amended Sep. 24, 1954 as amended Dec. 22, 1944 July 24, 1946 2. COLUMBIA RIVER BASIN, LOCAL FLOOD PROTECTION PROJECTS Blackfoot Area, Snake River, ID. Levee left bank Blackfoot River, ID. Levees, channel improvement, and rectification works. Boise Valley, Boise River, ID. Channel improvement and enlargement, levees, and revetments in Ada County. Canyon County unit was deauthorized April 18, 1967. Grande Ronde Valley, OR. Levees and channel clearing, straightening, and realignment; would complement stream regulation by upstream storage projects. Heise-Roberts Extension, Snake River, ID. Channel clearing and rectification, levees, and bank protection. Kendrick, Potlatch River, ID. Revetted levee. Malheur River, OR. Channel rectification, levees, and bank protection at Vale. Willow Creek unit was deauthorized October 14, 1969. Palouse River, WA. Flood protection for urban and rural areas at Garfield and near Malden. Payette Valley, ID. Channel rectification, levees, and bank protection along 38 miles of Payette River below Black Canyon Dam. Payette Valley was deauthorized October 3, 1978. Portneuf River and Marsh Creek, ID. Concrete-lined channel through Pocatello. Inkom-Marsh Creek unit was deauthorized October 14, 1969. Shelley Area, Snake River, ID. Bank protection Weiser River, Weiser Area, ID. Intermittent channel realignment and improvement, levees, and bank protection, lower river area. BIG WOOD RIVER, ID Debris removal along Big Wood River. BOISE RIVER, ID Tree and brush removal from Boise River; gravel removal at six locations from Caldwell, ID downstream CATHERINE CREEK, OR Organic debris removal along Catherine Creek COLFAX, PALOUSE RIVER, WA Provides for flood control works in vicinity of and through Colfax, WA, by channel enlargement and modification, levees, floodwalls, revetments, and modification of railroad bridges LUCKY PEAK LAKE, ID Dam for flood control, irrigation, and recreation. 39-13 H. Doc. 531, 81st Cong., 2nd Sess. Sec. 208, P.L. 83-780 Authorized by Chief of Engineers Oct. 27, 1983 Sec. 208, P.L. 83-780 Authorized by Chief of Engineers March 5, 1984 Sec. 208, P.L. 83-780 Authorized by Chief of Engineers Sep. 3, 1985 Flood Control Act of 1944 H. Doc. 888, 77th Cong., 2nd Sess. P.L. 79-526, Chief of Engineers Report dated May 13, 1946 3. 4. 5. 6. 10. REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 39-B (Continued) AUTHORIZING LEGISLATION See Date Section Authorizing in Text Act Project and Work Authorized Documents 11. 21: Mar. 2, 1945 Dec. 31, 1970 Oct. 22, 1976 Dec. 22, 1944 as amended June 28, 1938 Aug. 18, 1941 Sep. 24, 1954 as amended July 24, 1946 Sep. 24, 1954 as amended Sep. 24, 1954 as amended Oct. 27, 1965 July 3, 1958 Oct. 23, 1962 Aug. 15, 1963 Mar. 2, 1945 Dec. 22, 1944 as amended Oct. 22, 1976 Dec. 29, 1981 July 30, 1983 Second outlet for streamflow maintenance. Construction, operation, and maintenance of recreation facilities. MILL CREEK LAKE, WALLA WALLA, WA Off-stream storage project upstream from Walla Walla. Channel improvement through Walla Walla; concrete lined channel. RAPID CREEK, INKOM, ID Gravel, brush and small tree removal from Rapid Creek. SEWAGE LAGOONS, VALE, OR Construction of riprap bank protection. SOUTH FORK, BOISE RIVER, ID Organic debris removal and restoring channel alignment and an existing levee near the Ballentyne Subdivision. WEISER RIVER, ID Gravel bar removal from Weiser River at six locations. WILLOW CREEK LAKE, OR Storage project for flood control, recreation, and fish and wildlife. (BRUCES EDDY) DWORSHAK DAM AND RESERVOIR, ID Preparation of detailed plans. Bruces Eddy dam and reservoir for flood control, navigation, power, recreation, and area redevelopment. Redesignation of project as Dworshak Dam and Reservoir. ICE HARBOR LOCK AND DAM - LAKE SACAJAWEA, WA Unit 1 of 4, Lower Snake River project, Lock and dam for navigation, power, recreation, and irrigation. Construction, operation, and maintenance of recreation facilities. LEWISTON-CLARKSTON BRIDGE, ID AND WA Four lane highway bridge and approaches. Increase of authorized amount to $23,200,000. Approach roadway from bridge to Sixteenth Avenue in Clarkston, WA. Increase of authorized amount to $24,000,000. LITTLE GOOSE LOCK AND DAMLAKE BRYAN, WA Unit 3 of 4, Lower Snake River project. Lock and dam for navigation, power, recreation, and irrigation. Designation of reservoir as Lake Bryan. 39-14 P.L. 94-587 Sec. 4, Flood Control Act of 1944 H. Doc. 578, 75th Cong., 3d Sess. H. Doc. 719, 76th Cong., 1st Sess. Sec. 208, P.L. 83-780 Authorized by Chief of Engineers Feb. 11, 1985. Sec. 14, P.L. 79-526 Authorized by Chief of Engineers Aug. 3, 1983 Sec. 208, P.L. 83-780 Authorized by Chief of Engineers May 11, 1984 Sec. 208, P.L. 83-780 Authorized by Chief of Engineers Feb. 14, 1984 H. Doc. 233, 89th Cong., 1st Sess. S. Doc. 51, 84th Cong., 1st Sess. H. Doc. 403, 87th Cong., 2d Sess. P.L. 88-96 H. Doc. 704, 75th Cong., 3d Sess. Sec. 4, Flood Control Act of 1944 P.L. 94-587 P.L. 97-140 P.L. 98-63 H. Doc. 704, 75th Cong., 3d Sess. P.L. 91-638 12. 14. 15. 16. 17. 18. 19. 20. TABLE 39-B (Continued) WALLA WALLA, WASHINGTON DISTRICT AUTHORIZING LEGISLATION See Date Section Authorizing in Text Act Project and Work Authorized Documents 22. 23. LOWER GRANITE LOCK AND DAM, WA Unit 4 of 4, Lower Snake River project. Lock and dam for navigation, power, recreation, irrigation. LOWER MONUMENTAL LOCK AND DAMLAKE HERBERT G. WEST, WA Unit 2 of 4, Lower Snake River project. Lock and dam for navigation, power, recreation, and irrigation. Designation of reservoir as Lake Herbert G. West. LOWER SNAKE RIVER FISH & WILDLIFE COMPENSATION PLAN, WA, OR AND ID Fish hatcheries and replacement of wildlife habitat. McNARY LOCK AND DAM-LAKE WALLULA, OR AND WA Lock and dam for navigation, power, recreation, and irrigation. Construction, operation, and maintenance of recreation facilities. SNAKE RIVER MOUTH TO JOHNSON BAR, OR, WA AND ID Open-river navigation. Riparia to Pittsburg Landing. Mouth to Riparia. Pittsburg Landing to Johnson Bar. Supersedes previous legislation mouth to Lewiston, ID only. See Ice Harbor, Lower Monumental, Little Goose, and Lower Granite Locks and Dams. H. Doc. 704, 75th Cong., 3d Sess. H. Doc. 704, 75th Cong., 3d Sess. P.L. 95-285 P.L. 94-587 H. Doc. 704, 75th Cong., 3d Sess. Sec. 4, Flood Control Act of 1944 H. Doc. 127, 56th Cong., 2d Sess. H. Doc. 411, 55th Cong., 2d Sess. Rivers and Harbors Committee Doc. 25, 72d Cong., 1st Sess. H. Doc. 704, 75th Cong., 2d Sess. 39-15 Mar. 2, 1945 Mar. 2, 1945 May 25, 1978 Oct. 22, 1976 Mar. 2, 1945 Dec. 22, 1944 as amended June 13, 1902 June 25, 1910 Aug. 30, 1935 Mar. 2, 1945 24. 25. 26. REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 39-C OTHER AUTHORIZED NAVIGATION PROJECTS For Last Cost to Sep. 30, 1985 Full Report Operation See Annual and Project Status Report For Construction Maintenance Columbia River and Tributaries Completed 1968 1,851,195 - above Celilo Falls to Kennewick, WA' 'Obviated by 'The Dalles, John Day, and McNary projects TABLE 39-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS For Last Cost to Sep. 30, 1985 Full Report Operation See Annual and Project Status Report For Construction Maintenance Asotin Creek, Asotin, ID' Completed 1951 12,019 - Bear Creek, Kendrick, ID' Completed 1970 133,518 - Blackfoot Area, Snake River, Columbia River Basin, ID Completed 1958 42,796 - Blackfoot Reservoir, ID Inactive 1980 267,626 - Blackfoot River, Columbia River Basin, ID Completed 1965 391,143 - Boise Valley, Ada County Unit, Columbia River Basin, ID Deferred 1967 46,084 - Catherine Creek Lake, OR Deferred 1978 1,552,000 - Connell, WA1 Completed 1967 60,000 - Cottonwood Creek Community Church, Culdesac ID2 Completed 1984 23,400 - Dayton, Touchet River, WA Completed 1966 380,617 - Dry Creek, WA1 Completed 1961 384,426 - Esquatzel Coulee, Connell, WAx Completed 1967 232,792 - Esquatzel Coulee, Mesa, WA' Completed 1969 2,665 - Gooding Area, IDx Completed 1954 59,167 - Grande Ronde Lake, OR Deferred 1966 - - Grande Ronde Valley, Columbia River Basin, OR Deferred 1958 102,458 - Graves Creek, IDx Completed 1953 75,469 - Heise-Roberts Area, Snake River, ID Completed 1955 1,575,838 - Heise-Roberts Extension, Columbia River Basin, ID 1968 (a)Henrys Fork Unit Deferred 27,800 - (b) Snake River Unit Completed 3,375,158 - Jackson Hole, Snake River, WY Completed 1978 2,388,270 - Kendrick, Potlatch River, Columbia River Basin, ID Completed 1960 59,942 - Lapwai Creek, Culdesac, IDx Completed 1972 176,833 - Lava Hot Springs, Portneuf River, IDx Completed 1973 113,296 - Lower Dry Creek, Lowden, WA' Completed 1972 17,592 - Lower Walla Walla River, Columbia River Basin, WA Inactive 1953 4,000 - Lyman Creek, ID' Completed 1971 230,315 - Malheur Improvement District, Snake River, OR Completed 1957 55,894 - Malheur River, Vale Unit, Columbia River Basin, Or Completed 1961 325,581 - Milton-Freewater, Walla Walla River, OR' Completed 1968 1,786,753 - 39-16 WALLA WALLA, WASHINGTON DISTRICT TABLE 39-E (Continued) OTHER AUTHORIZED FLOOD CONTROL PROJECTS For Last Cost to Sep. 30, 1985 Full Report Operation See Annual and Project Status Report For Construction Maintenance Mission and Lapwai Creeks, ID1 Mud Lake, Columbia River Basin, ID Orofino Creek & Clearwater River, Orofino, ID2 Palouse River, Columbia River Basin WA Pataha Creek, Pomeroy, WA2 Payette River, Emmett Sewage Lagoon, ID2 Portneuf River & Marsh Creek Pocatello Unit, Columbia River Basin, ID Pullman, Palouse, WA Riverside Area, Pasco, WA1 Ririe Lake, ID Shelley Area, Snake River, Columbia River Basin, ID Shobe Canyon, Heppner, OR1 Snake River, Blackfoot, ID1 Snake River, Heise Bridge Location, ID2 Snake River, Stevens, Blackfoot, ID1 South Fork Clearwater River, Coluumbia River Basin, ID South Fork Clearwater River, Kooskia-Stites, ID1 Teton River, Columbia River Basin, ID Tomanovich-Salmon City, ID1 Touchet River, Waitsburg, WA1 Tucannon River, Wooten, WA1 Umatilla River, OR' Wallowa River, Weaver Bridge OR2 Weiser River, Columbia River Basin, ID Whitebird Creek, Columbia River Basin, ID Willow Creek, ID1 Yakima River, West Richland, WA1 4 Completed 1965 54,538 Inactive Inactive Deferred Completed Completed Completed Deferred Completed Completed Completed Completed Completed Completed Completed Inactive Completed Inactive Completed Completed Completed Completed Completed Deferred Inactive Completed Completed 1957 1949 1977 1967 1969 1964 1972 1983 1958 1970 1980 1952 1968 1973 1973 1955 1955 1973 1971 1961 1960 1960 1956 1963 1964 5,996 23,050 110,815 39,172 6,456,032 99,540 28,839 39,677,448 32,335 5,000 131,700 8,501 32,425 3,899 61,055 10,387 128,635 72,140 73,932 161,540 16,118 37,757 1,896 976 238,890 'Authorized by Chief of Engineers pursuant to Section 205, PL 80-858. 'Authorized by Chief of Engineers pursuant to Section 14, PL 79-526 'Exclusive of $6,300 contributed funds. 'Includes $9,000 contributed funds. 39-17 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 39-G DEAUTHORIZED PROJETS For Last Full Report Federal Contributed See Annual Date Funds Funds Project Report For Deauthorized Expended Expended Asotin Dam, Snake R. ID & WA 1964 1975 - - Boise Valley, Canyon County Unit, ID , - 1967 10,600 - Camas Creek, ID - 1965 9,080 - Cottonwood Creek Dam, Boise, ID - 1984 183,100 - Little Wood River, ID - 1965 21,334 - Malheur River, Willow Creek Unit, OR - 1969 13,000 - Mill Creek, WA - 1977 3,537 - Payette Valley, ID - 1978 23,178 - Portneuf River, Inkom-Marsh Creek, ID - 1969 - - Stuart Gulch Dam, Boise, ID 1974 1979 234,100 - Touchet River, WA - 1977 11,198 - Weiser River, Cambridge- Midvale, ID - - 75,000 - TABLE 39-H COLUMBIA RIVER BASIN, LOCAL FLOOD PROTECTION PROJECTS (See Section 2 of Text) Estimated Federal Project Status Cost Cost to Sep. 30, 1985 Blackfoot Area, Snake River, ID Completed - 42,796 Blackfoot River, ID Completed - 391,143 Boise Valley, ID Ada County Unit Deferred 1,060,000 46,084 Canyon County Unit Deauthorized - 10,600 Camas Creek, ID Deauthorized - 9,080 Grande Ronde Valley, OR Deferred 8,639,000 102,458 Heise-Roberts Extension, ID Henrys Fork Unit Deferred 165,000 27,800 Snake River Unit Completed - 3.375.158 Kendrick, Potlatch River, ID Completed - 59,942 Little Wood River, ID Deauthorized - 21,334 Lower Walla Walla River, WA Inactive 372,000 4,000 Malheur River, OR Vale Unit Completed - 325.581 Willow Creek Unit Deauthorized - 13,000 Mill Creek, WA Deauthorized - 3,537 Mud Lake, ID Inactive 1,187,000 5,996 Palouse River, WA Deferred 914,000 - Payette Valley, ID Deauthorized - 23,178 Portneuf River and Marsh Creek, ID Pocatello Unit Completed - 6,456,0321 Shelley Area, Snake River, ID Completed - 32,335 South Fork Clearwater River, ID Inactive - 3,899 Teton River, ID Inactive - 10,387 Touchet River, WA Deauthorized - 11,198 Weiser River, ID Deferred 1,565,000 37,757 Weiser River, ID Cambridge-Midvale Deauthorized - 75,000 Whitebird Creek, ID Inactive - 1,896 Total 11,090,191 1Exclusive of $36,800 contributed funds. 39-18 WALLA WALLA, WASHINGTON DISTRICT TABLE 39-I INSPECTION OF COMPLETED FLOOD CONTROL PROJECTS (See Section 8 of Text) Bear Creek, Kendrick, ID September 1985 Big Canyon Creek, Peck, ID February 1985 Big Wood River, ID July 1985 Blackfoot River, Blackfoot, ID April 1985 Blackfoot #2, Blackfoot, ID May 1985 Boise River, Boise, ID September 1985 Camp Wooten, Tucannon River, WA August 1985 Catherine Creek, Union, OR April 1985 Colfax, Palouse River, WA June 1985 Culdesac, Lapwai Creek, ID September 1985 Dayton, Touchet River, WA March 1985 Dry Creek, Lowden, WA March 1985 Emmett Sewage Lagoon, Payette River, ID September 1985 Esquatzel Coulee, WA March 1985 Falk Bridge Loc., Payette River, ID March 1985 Ferry Butte, Snake River, ID May 1985 Heise Bridge, Snake River, ID April 1985 Heise-Roberts Area, Snake River, ID August 1985 Heise-Roberts Extension, Snake River, ID August 1985 Jackson Hole, Snake River, WY August 1985 Kendrick, Potlatch River, ID September 1985 Link Ross Location, Boise River, ID September 1985 Little Salmon River, Riggins, ID March 1985 Little Wood River, Carey, ID July 1985 Lyman, Lyman Creek, ID May 1985 Malheur River, Vale, OR March 1985 Mission Creek, ID September 1985 Pataha Creek, Pomery, WA August 1985 Pocatello, Portneuf River, ID April 1985 Power River, Baker, OR April 1985 Shelly Area, Snake River, ID August 1985 Slate Creek, Slate, ID March 1985 Snake River, Annex, OR March 1985 Soldier Creek, Fairfield, ID July 1985 South Fork, Boise River; ID September 1985 Stillwell Location, Boise River, ID September 1985 Tomanovich - Salmon City, Salmon River, ID May 1985 Walla Walla River, Milton-Freewater, OR March 1985 Weiser River, ID March 1985 West Richland, Yakima River, WA March 1985 Whitebird Creek, Whitebird, ID March 1985 39-19 TABLE 39-J REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 PRINCIPAL DATA CONCERNING NAVIGATION LOCK, SPILLWAY DAM, POWERPLANT, AND IMPOUNDMENT Project SPILLWAY DAM Dworshak Dam and Reservoir, ID (See Section 18 of Text) Ice Harbor Lock and Dam, WA (See Section 19 of Text) Type of Construction Completed Maximum Capacity Crest Elevation Control Gates: Type Size, Width by Height Number POWERPLANT Length Generating Units: Number Installed Space for Additional Rating, Each Total Capacity Installed Total Potential Capacity Maximum Structural Height First Power-On-Line IMPOUNDMENT Elevations: Normal Operating Range Maximum Flood Control Storage Lake Length Lake Water Surface Area at Elevation 1600 Length of Shoreline NAVIGATION LOCK Clear Width Clear Length Lift: Minimum Average Maximum Minimum Water Depth Over Sills Opened to Navigation SPILLWAY DAM Type of Construction Completed Maximum Capacity Crest Elevation Control Gates: Type Size, Width by Height Number Concrete Gravity September 1974 150,500 Cubic Feet Per Second 1613 Feet Tainter 50 Ft. by 55 Ft. 2 428 Feet 33 2 @ 90,000 kw; 4 @ 220,000 kw 400,000 kw 1,060,000 kw 150 Feet March 1973 1600-1445 Feet 1605 Feet 2,000,000 Ac.-Ft. 53 Miles 17,090 Acres 175 Miles 86 Feet 675 Feet 97 Feet 100 Feet 103 Feet 15 Feet May 1962 Concrete Gravity January 1962 850,000 cfs 391 Feet Tainter 50 Ft. by 51 Ft. 10 39-20 TABLE 39-J (Continued) WALLA WALLA, WASHINGTON DISTRICT PRINCIPAL DATA CONCERNING NAVIGATION LOCK, SPILLWAY DAM, POWERPLANT, AND IMPOUNDMENT Project POWERPLANT Length 671 Feet Generating Units: Number Installed Rating, Each Little Goose Lock and Dam WA (See Section 21 of Text) Total Installed Capacity Maximum Structural Height First Power-On-Line IMPOUNDMENT Elevations: Normal Operating Range Maximum Lake Length Lake Water Surface Area at Elevation 440 Navigation Channel, Depth by Width Length of Shoreline NAVIGATION LOCK Clear Width Clear Length Life: Minimum Average Maximum Minimum Water Depth Over Sills Opened to Navigation SPILLWAY DAM Type of Construction Completed Maximum Capacity Crest Elevation Control Gates: Type Size, Width by Height Number POWERPLANT Length Width Generating Units: Number Installed Rating, Each Tobtal Installed Capacity Maximum Structural Height First Power-On-Line IMPOUNDMENT Elevations: Normal Operating Range Maximum Lake Length Lake Water Surface Area at Elevation 638 Navigation Channel, Depth by Width Length of Shoreline 6 3 @ 90,000 kw; 3 @ 111,000 kw 603,000 kw 226 Feet December 1961 440-437 Feet 446 Feet 31.9 Miles 9,200 Acres 14 Ft. by 250 Ft. 80 Miles 86 Feet 675 Feet 93 Feet 98 Feet 101 Feet 15 Feet May 1970 Concrete Gravity January 1970 850,000 cfs 581 Feet Tainter 50 Ft. by 60 Ft. 8 656 Feet 243 Feet 6 135,000 kw 810,000 244 Feet March 1970 638-633 Feet 646.5 Feet 37.2 Miles 10,025 Acres 14 Ft. by 250 Ft. 92 Miles 39-21 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 394J (Continued) PRINCIPAL DATA CONCERNING NAVIGATION LOCK, SPILLWAY DAM, POWERPLANT, AND IMPOUNDMENT Project Lower Granite Lock and Dam, WA (See Section 22 of Text) Lower Monumental Lock and Dam, WA (See Section 23 of Text) NAVIGATION LOCK Clear Width Clear Length Life: Minimum Average Maximum Minimum Water Depth Over Sills SPILLWAY DAM Type of Construction Completed Maximum Capacity Crest Elevation Control Gates: Type: Size, Width by Height Number POWERPLANT Length Width Generating Units: Number Installed Rating, Each Total Capacity Installed Maximum Structural Height First Power-On-Line IMPOUNDMENT Elevations: Normal Operating Range Maximum Lake Length Lake Water Surface area at Elevation 738 Navigation Channel, Depth by Width Length of Shoreline NAVIGATION LOCK Clear Width Clear Length Lift: Minimum Average Maximum Minimum Water Depth Over Sills Opened to Navigation SPILLWAY DAM Type of Contruction Completed Maximum Capacity Crest Elevation Control Gates: Type Size, Width by Height Number 86 Feet 675 Feet 95 Feet 100 Feet 105 Feet 15 Concrete Gravity February 1975 850,000 cfs 581 Feet Thinter 50 Ft. by 60.5 Ft. 8 656 Feet 243 Feet 6 135,000 kw 810,000 kw 246 Feet April 1975 738-733 Feet 746.5 Feet 38 Miles 8,900 Acres 14 Ft. by 250 Ft. 91 Miles 86 Feet 675 Feet 97 Feet 98 Feet 103 Feet 15 Feet April 1969 Concrete Gravity March 1969 850,000 cfs 483 Feet Tainter 50 Ft. by 61 Ft. 8 39-22 TABLE 39-J (Continued) WALLA WALLA, WASHINGTON DISTRICT PRINCIPAL DATA CONCERNING NAVIGATION LOCK, SPILLWAY DAM, POWERPLANT, AND IMPOUNDMENT Project POWERPLANT McNary Lock and Dam, OR and WA (See Section 25 of Text) Length Width Generating Units: Number Installed Rating, Each Total Installed Capacity Maximum Structural Height First Power-On-Line IMPOUNDMENT Elevations: Normal Operating Range Maximum Lake Length Lake Water Surface Area at Elevation 540 Navigation Channel, Depth by Width Length of Shoreline NAVIGATION LOCK Clear Width Clear Length Life: Minimum Average Maximum Minimum Water Depth Over Sills Opened to Navigation SPILLWAY DAM Type of Construction Completed Maximum Capacity Crest Elevation Control Gates: Type Size, Width by Height Number POWERPLANT Length Generating Units: Number Installed Rating, Each Total Installed Capacity Maximum Structural Height First Power-On-Line IMPOUNDMENT Elevations: Normal Operating Range Maximum Lake Length Lake Water Surface Area at Elevation 340 Navigation Channel, Depth by Width Length of Shoreline 656 Feet 243 Feet 6 135,000 kw 810,000 kw 242 Feet May 1969 540-537 Feet 548 Feet 28.7 Miles 6,590 Acres 14 Ft. by 250 Ft. 78 Miles 86 Feet 675 Feet 67 Feet 75 Feet 83 Feet 15 Feet November 1983 Concrete Gravity October 1953 2,200,000 cfs 291 Feet Vertical Life 50 Ft. by 51 Ft. 22 1,348 Feet 14 70,000 kw 980,000 kw 193 Feet November 1953 340-335 Feet 356.5 Feet 64 Miles 38,800 Acres 14 Ft. by 250 Ft. 242 Miles 39-23 TABLE 39-K REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 SNAKE RIVER DOWNSTREAM FROM JOHNSON BAR LANDING OR, WA, AND ID (See Section 26 of Text) Estimated Cost (Corps New Work Maintenance Percent of Engineers to Sep. 30, 1985 to Sep. 30, 1985 Comrn- Constr. Project Funds Only) Approp. Cost Approp. Cost pleted Started Ice Harbor Lock & Dam Initial Project Code 710 Recreation Facilities Power Units 4-6 Totals Little Goose Lock & Dam Initial Project Power Units 4-6 Totals Lower Granite Lock & Dam Initial Project Code 710 Recreation Facilities Power Units 4-6 Totals Lower Monumental Lock & Dam Initial Project Power Units 4-6 Totals Open River Lewiston to Johnson Bar Landing Open River Pasco to Lewiston Totals Existing Project Previous Projects Pasco to Lewiston Totals Authorized Project 129,578,480 129,578,480 129,578,490 45,374,103 45,021,475 914,256 36,748,021 167,240,757 160,413,215 60,941,807 221,355,022 321,503,981 63,800 46,212,534 367,780,315 184,712,361 51,661,371 236,373,732 34,613 914,256 36,748,021 167,240,757 160,413,215 60,941,807 221,355,022 914,256 36,748,021 167,240,757 160,413,215 60,941,807 221,355,022 100 FY 57 - - 100 - - 100 45,374,103 45,021,475 100 35,509,394 34,889,018 35,509,394 34,889,018 321,503,981 321,503,979 36,194,297 35,885,275 63,800 46,212,534 367,780,315 184,712,361 51,661,371 236,373,732 63,800 46,212,534 367,780,313 184,712,361 51,661,371 236,373,732 FY 57 FY 71 100 FY 63 100 FY 74 100 100 FY 65 - - 100 - - 100 36,194,297 35,885,275 100 30,747,402 30,394,396 30,747,402 30,394,396 100 100 100 FY 84 FY 74 FY 61 FY 75 34,6131 34,6131 371,603 367,9432 - - - 4,350 4,350 992,784,439 400,150 993,184,589 992,784,439 992,784,437 148,201,149 146,562,457 400,150 400,150 186,570 186,570 993,184,589 993,184,587 148,387,719 146,749,027 100 'New Work appropriations used for maintenance prior to 1953. 2Includes $18,723 FY 1985 project condition survey cost. 39-24 ALASKA DISTRICT* This District consists of the State of Alaska. IMPROVEMENTS Navigation 1. Anchorage Harbor, AK ................. 2. Bethel Small Boat Harbor, AK .......... 3. Cordova Small Boat Harbor, AK ......... 4. Dillingham Harbor, AK ............... 5. Homer Harbor, AK .................... 6. Kake Harbor, AK .................... 7. King Cove Harbor, AK ................. 8. Metlakatla Harbor, AK ................ 9. Ninilchik Harbor, AK .................. 10. Nome Harbor, AK ..................... 11. Port Lions Small Boat Harbor, AK ....... 12. Project Condition Surveys .............. 13. Stikine River, AK ..................... Flood Control 14. Chena River Lakes, AK ................ 15. Kuskokwim River, Bethel, AK .......... 16. Flood Control Work Under Special Authorization .................. 17. Inspection of Completed Flood. Control Projects ....................... 18. Inspection of Completed PL-99 Works .... Page 40-1 Multiple-P 40-1 Including 40-2 19. Snetti 40-2 40-2 General In 40-3 20. Surve3 40-3 21. Collec 40-3 Basic. 40-4 22. Contin 40-4 40-5 Tables 40-5 40-5 40-5 40-5 40-6 40-6 40-6 urpose Projects, Power sham, AK .................... vestigations rs .............................. tion and Study of D ata ........................... uation of Planning and Engineering Page 40-6 40-6 40-6 40-6 Table 40-A Cost & Financial Statement .... 40-8 Table 40-B Authorizing Legislation ........ 40-10 Table 40-C Other Authorized Navigation Projects ..................... 40-12 Table 40-D Not Applicable............... Table 40-E Other Authorized Flood Control Projects ................... . 40-13 Table 40-F Not Applicable .... ......... Table 40-G Deauthorized Projects ......... 40-13 Table 40-H Navigation Work Under Special Authorization ................ 40-14 Table 40-I Project Condition Surveys ....... 40-14 Navigation 1. ANCHORAGE HARBOR, AK Location. Anchorage is in southcentral Alaska on the southeast shore of Knik Arm, north of Turnagain Arm near its junction with Cook Inlet. (See NOAA Charts 16660 and 16664.) Existing project. Provides for dredging along a 3,000-foot baseline adjacent to the Port of Anchorage dock to a depth of 35 feet below mean lower low water. Tidal range between mean lower low water and mean higher high water is 29.0 feet and the extreme range is 42.0 feet. Local cooperation. Fully complied with. Terminal facilities. The Port of Anchorage facility consists of a POL terminal at the southern end and three general cargo terminals northward. The northernmost terminal, completed during 1976 and 1977 was outside the Federal project limits. Extension of limits from 2,070 feet northward to 3,000 feet was authorized by Public Law 94-587 and funded in FY 1978. Operations during fiscal year. Maintenance: The dredging contract to remove 550,000 cubic yards of material (450,000 cubic yard in the base area and 100,000 cubic yard in the additive area) was awarded April 16, 1985. The contractor used a 10 and 15 cubic yard clamshell dredger. Dredging has been accomplished across the entire project during FY 1985. A total of 481,800 cubic yards were dredged. Controlling depth at the harbor was -36 feet mean lower low water, with a majority of the harbor at project depth. 2. BETHEL SMALL BOAT HARBOR, AK Location. The city of Bethel is 65 miles upriver on the north bank of the Kuskokwim River, which flows through southwestern Alaska. Bethel is about 400 miles west of 40-1 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Anchorage. (See Coast and Geodetic Survey Chart 9302 and USGS Map Bethel D8.) Existing project. Project (Section 107) includes provision of a 12-acre small boat harbor and 1,270 foot entrance channel by deepening, widening, and straightening a portion of the Lousetown Slough which is 0.3 miles east of Bethel. Range between mean lower low water and mean higher high water is 4.0 feet and extreme tidal range is 10.0 feet, during low summer water flow in Kuskokwim River. Water level also depends on river state; tidal effects decrease with higher river flows, disappearing only at the 20-year-frequency flood stage. Local cooperation. Fully complied with. Terminal facilities. Bethel serves as a regional transportation center for approximately 50 villages. A medium-draft port facility was built along the city's riverfront in 1975. Goods, including gas, oil, food, clothing, and construction material are all brought into Bethel for redistribution to outlying villages. Generally, river shipments of bulk goods are transported by medium-draft barges. Personal supplies are often moved in individually owned riverboats which also are used for fishing activities. The riverboat fleet in Bethel is estimated to number between 1,000 and 1,100 boats, of which 400 are transient boats from other villages along the Kuskokwim River. There are also eight river barges varying in size to as large as 30 by 100 feet. The barges are powered by five locally-based tug boats with lengths ranging from 25 to 40 feet. No protected berthing areas exist at Bethel for any water craft. The riverboats are beached on the sandbars and banks for temporary storage. Brown's Slough is particularly popular as a berthing area, resulting in overcrowding and congestion. Operations during fiscal year. New work: Construction was physically completed in FY 1983. Grass stabilization of slope study was accomplished in FY 1985. 3. CORDOVA SMALL BOAT HARBOR, AK Location. Cordova is on Orca Inlet, a strait near the eastern entrance of Prince William Sound, about 150 air miles south-southeast of Anchorage. (See Coast and Geodetic Survey Charts 8520, 8525, and 8551.) Existing project. The Office of the Chief of Engineers approved construction of a harbor expansion from 8.26 acres to 20 acres by removal of the existing 1400-foot breakwater and construction of a new 2000-foot long breakwater. The entrance channel is dredged to -16 feet mean lower low water and the turning basin is dredged from -10 to -12 mean lower low water. Tidal range between mean lower low water and mean higher high water is 12.4 feet with an extreme range of 21.7 feet. The dredged material is disposed of in two diked upper tidal areas which will be used as staging facilities. Local cooperation. Fully complied with. Terminal Facilities. Two municipal docks accommodate general cargo and passengers, including automobile ferry traffic. One privately owned wharf, reduced by fire, provides oil handling and bunkering facilities. Three privately owned wharves are used for industrial purposes. A small boat float system for public use is in original basin. State ferry dock in basin has been superseded by municipal dock and is inactive. Facilities are considered adequate for present commerce. Operations during fiscal year. New work: Project is physically complete; however, Supplemental Appropriations Act, 1985, PL 99-88, authorized payment of estimated $7,400,000 judgment and any associated interest resulting from decision of the Engineer Board of Contract Appeals, September 6, 1985. 4. DILLINGHAM HARBOR, AK Location. At head of Nushagak Bay, an arm of Bristol Bay, on right bank of Nushagak River just below its confluence with Wood River; about 470 miles northeasterly of Dutch Harbor and 300 miles southwest of Anchorage. (See NOAA/NOS Chart #16660.) Existing project: A small-boat basin 230,000 square feet in area with a depth of 2 feet above mean lower low water along Scandinavian Creek; with entrance channel 1,100 feet long and 40 feet wide in Scandinavian Creek; and a sheet pile sill across the basin outlet with a top elevation of 7 feet above mean lower low water. During design stage the project was revised to include a rock sill with adjacent scour-protection blankets and the embankment was relocated to include a berm between the basin and the embankment. Tidal range between mean lower low water and mean higher high water is 19.8 feet. Extreme range is 30.0 feet. Local cooperation. Fully complied with. Terminal facilities. Four docks at the city of Dillingham; three privately owned one owned by the city of Dillingham, and four publicly owned small-boat floats in the project basin. Two docks are used for salmon-cannery operations; the third is an oil handling and bunkering terminal; the fourth dock is used by the city to unload barges which come into Dillingham. New floats for the harbor were installed in June 1982, and removed before fall freezeup. They will be replaced each spring. Cargo and passengers from ocean vessels are unloaded at the docks or in the small-boat basin. Facilities are inadequate for number of boats using small boat harbor. Operations during fiscal year. Maintenance: Government plant and hired labor performed dredging from May through June 1985 and 121,000 cubic yards of material were removed. Modifications to the dredge, combined with operating 24 hours a day, resulted in more cubic yards being dredged in the shortest time period since annual maintenance dredging of the harbor began in 1969. 5. HOMER HARBOR, AK Location. In Kachemak Bay, on Kenai Peninsula, 152 miles by water southwest of Anchorage. Harbor site is land based near the extremity of Homer Spit which varies to one-quarter mile in width and extends 4.5 miles southeasterly from the mainland. (See NOAA/NOS Chart #16645.) Existing project. Provides for sheltered small-boat harbor, relocated and based within Homer Spit about 50 40-2 ALASKA DISTRICT acres in area. Project depth varies from 10 feet mean lower low water in the most western segment of the harbor to 20 feet below mean lower low water in the entrance channel and the most eastern segment of the harbor; a north entrance channel; protected by a main rock breakwater 1,018 feet long and secondary rock breakwater 238 feet long. Tidal range between mean lower low and mean higher high water is 18.1 feet, with an extreme range of 30.4 feet. (For details relating to previous projects, see page 1593 of Annual Report for 1964.) Local cooperation. Fully complied with. Terminal facilities. One publicly owned and operated wharf capable of handling oceangoing vessels serves for passengers and general cargo. Small-boat facilities in basin area include publicly owned mooring floats, a publicly owned wharf, and an industrial wharf. Construction has tripled size of the harbor. The city of Homer has tripled the size of its fish dock located at the southern end of the harbor. Operations during fiscal year. New work: The contract for expansion of the Homer Small Boat Harbor was completed in November 1984. A total of 1,869,132 cubic yards were dredged, armor rock was placed, and a new four-lane launch ramp was built. Maintenance: Hydrographic surveys were performed. 6. KAKE HARBOR, AK Location. Kake Harbor is located in the city of Kake, on the northwest corner of Kupreanof Island in southeastern Alaska, 39 air miles west of Petersburg, AK, and 850 water miles northwesterly of Seattle, WA. (See Coast and Geodetic Chart 8201.) Existing project. The authorized project consists of a 1,580-foot-long west breakwater and a 900-foot long south breakwater, enclosing a 7-acre berthing area. Poor foundation conditions found during preconstruction investigations have forced modification of the project to include a 1,760-foot-long west breakwater and a 1,750-foot-long south breakwater. Tidal range between mean lower low water and mean higher high water is 14.0 feet with an extreme range of 22 feet. Estimated project cost is $12,538,000 (October 1984), including $12,500,000 Corps of Engineers funds $22,000 Coast Guard funds, and $16,000 non-Federal cost. Local cooperation. Fully complied with. Terminal facilities. At Kake, a publicly owned wharf with seaplane float equipped airplanes and shallow-draft vessels is located within area of proposed basin. At cannery 1 mile from city, there are two privately owned deepdraft piers: one for cargo, open to all local boat owners, the second for fuel, including a float for fueling small boats. At Portage Cove, there is one publicly-owned smallboat float. Facilities are not considered adequate for present commerce due to the following deficiencies in smallboat facilities: the complete lack of protection in the directions of the most severe storms; shallow water at Portage Cove float and its approaches; ice formation on the cove during the winter months causes major boat damage and limits the use of the mooring float; and transportation problems between city and present small-boat float at Portage Cove. Operations during fiscal year. New work: A biological study was completed which investigated the aquatic habitats and organisms of the project area through the use of a joint United States Fish and Wildlife Service - Corps of Engineers dive effort. The data gathered is being used to understand temporal changes in these natural systems, pre- and post-project conditions, as well as provide background information for a recolonization study of man-made rubble structures in Alaska. Analysis of the data was completed and the report will be prepared in FY 1986. A temporary automatic meteorburst wind monitoring station was maintained to gather wind velocity and directional data more closely associated with the location of the project for comparison with data used in complying with the plans and specifications. 7. KING COVE HARBOR, AK Location. The city of King Cove, Alaska, is located near the southwesterly tip of the Alaska Peninsula in southwestern Alaska, 630 miles southwest of Anchorage. (See NOAA/NOS Chart #16549.) Existing project. Provides for an 11-acre small-boat basin having an anchorage basin 900 feet long by 550 feet wide and an entrance channel 100 feet wide and about 400 feet long, both at a depth of 15 feet below mean lower low water, a 1,400-foot long training dike, top elevation 10 feet above mean lower low water; and a 200-foot long rock sea groin, top elevation 14 feet above mean lower low water. Tidal range between mean lower low water and mean higher high water is 6.8 feet, with an extreme range of 14.0 feet. Local cooperation. Fully complied with. Terminal facilities. Consists of twin wharves with a small basin between them; marine rail and slipways flanked by catwalks and oil terminal facilities; and mooring buoys, dolphins, and piling for small boats. All are privately owned. Facilities are considered adequate for present oceangoing commerce but inadequate for the commercial fishing vessels operating in the area. A study for a new dock to be built by the State has been completed and engineering specifications for the new dock are now in the process of being written. The new dock will be leased to the city after construction. Operations during fiscal year. Maintenance: A contract for dredging of the harbor was awarded July 20, 1984. Dredging of the harbor started September 1, 1984 and was completed on October 21, 1984. A total of 17,250 cubic yards were removed. 8. METLAKATLA HARBOR, AK Location. Metlakatla is located in the southern portion of Port Chester, a small bay on the northwest coast of Annette Island in southeastern Alaska, 18 miles south of Ketchikan. (See Coast and Geodetic Charts 8074, 8075, and 8102.) Existing project. Consists of two small-boat basins. Existing basin is 2.18 acres in extent with a depth of 10 40-3 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 feet below mean lower low water, protected by a rubblemound breakwater 900 feet long. New basin consists of two rubblemound breakwaters, 1,255 and 1,150 feet long, and an entrance channel and maneuvering area, 1,100 feet long, 100 feet wide, dredged to a depth of 15 feet below mean lower low water and a basin area of 6.25 acres dredged to a depth of 15 feet below mean lower low water. Tidal range between mean lower low water and mean higher high water is 14.7 feet, with an extreme range of 24 feet. Local cooperation. Fully complied with. Terminal facilities. Publicly owned facilities are one general-cargo dock, one barge ramp, and a small-boat float system in existing basin. Privately owned facilities are one oil pier and one industrial wharf. Facilities are not adequate for mooring the commercial fishing vessels operating from Metlakatla. Existing protected harbor area is fully utilized. Operations during fiscal year. New work: Project is physically complete; however, various contractor claims are still pending. Maintenance: In October 1984 erosion problems at the beach adjacent to the east breakwater of the Metlakatla Small Boat Harbor were first reported. A site investigation was made on October 30, 1984. Beach erosion in this area has accelerated since construction of the harbor. A letter report describing the erosion and two recommended alternatives was completed in January 1985, and forwarded to higher authority for review and funding. Funding was obtained and a contract for placing a 4-foot thick riprap blanket (approximately 3,300 cubic yards of quarry spalls) on the beach and placing riprap on the landward connection of the east breakwater was awarded on September 30, 1985. The work is scheduled for completion in November 1985. 9. NINILCHIK HARBOR, AK Location. At mouth of Ninilchik River in Cook Inlet, at the community of Ninilchik, AK, about 40 miles upcoast from Homer and 112 miles southwest of Anchorage. (See NOAA/NOS Chart #16640.) Existing project. A small-boat basin 320 feet long by 150 feet wide dredged to elevation of 2 feet above mean lower low water, with an approach channel 400 feet long and 50 feet wide dredged to an elevation of 9 feet above mean lower low water; protected by a pile jetty 410 feet long. Project was modified in design stage to delete pile jetty and revise harbor dimensions to 400 feet long by 125 feet wide, and was completed in November 1961. Modification, including river channel diversicn, two armor rock jetties, and beach protection, was accomplished 1967 and 1969. Range between mean lower low water and mean higher high water is 19.1 feet, with an extreme range of 29.3 feet. Local cooperation. Fully complied with. Terminal facilities. Facilities, limited to shallow-draft vessels and accessible from Cook Inlet only at half-tide or higher, are a cannery dock along Ninilchik River available for offloading fish, and small-boat floats in project basin, provided by State of Alaska. Other supplies are landed on beach or brought by road from deep-draft ports in the vicinity. Facilities are extremely inadequate for the number of boats presently using harbor. Expansion of facilities would require construction of additional protected harbor area. Operations during fiscal year. Maintenance: Dredging of the harbor and entrance channel was accomplished with 6,800 cubic yards removed in 1985. A survey of the basin during May 1985 indicated project depth was available throughout the Federal limits. 10. NOME HARBOR, AK Location. At mouth of Snake River at the city of Nome, AK, on northerly shore of Norton Sound, an arm of Bering Sea. It is a shallow open roadstead, 581 nautical miles north of Dutch Harbor and 545 air miles northwest of Anchorage. (See NOAA/NOS Chart #16206.) Existing project. Provides for two jetties, the easterly 951 and the westerly not exceeding 676 feet long, at mouth of Snake River; a channel 8 feet at mean lower low water, 75 feet wide, from Norton Sound through Snake River to mouths of Bourbon and Dry Creeks, in city of Nome, ending in a turning basin of the same depth, 250 feet wide and 600 feet long; revetting banks of rivers; and protecting all existing water-front improvements on easterly beach by means of rock-mound seawall 3,350 feet long extending easterly from east jetty. Project has been completed except extension of jetties beyond present 400 and 240 feet, which is classified inactive. Range between mean lower low water and mean higher high water is 1.6 feet and extreme tidal range is 7.5 feet, but water levels are influenced more by wind than tide. Levels of 5 feet below mean lower low water have been observed during offshore winds, and a level of 14 feet above mean lower low water has been observed during a southerly storm. Local cooperation. Fully complied with. Terminal facilities. Cargoes and passengers from ocean vessels are lightered to and from shore a distance of about 2 miles. Traffic enters dredged channel and is handled over revetment, where lighterage company has transfer facilities which are open to the public. Facilities considered inadequate for existing commerce. In July 1984, the city of Nome received Department of Army authorization (permit) to construct a 3,600-foot gravelfilled causeway. Construction of the causeway began in July 1985. Due to lack of complete funding the length of the causeway was shortened to 2,500 feet. Construction is scheduled to be completed in FY 1987. Operations during fiscal year. Maintenance: Dredging by contract was accomplished throughout the ice-free season. 15,200 cubic yards were removed in FY 1985. A Design Memorandum (DM) for the rehabilitation of the Nome Harbor jetties and revetments was prepared. The draft DM was distributed for review and comment in FY 1985. The scheduled submittal of the final DM to higher authority is November 1985. 40-4 ALASKA DISTRICT 11. PORT LIONS SMALL BOAT HARBOR, AK Location. Port Lions is located on the north end of Kodiak Island, approximately 19 air miles west of the city of Kodiak. (See NOAA/NOS Chart #16594.) Existing Project. The Office of the Chief of Engineers approved construction for a small boat harbor at Port Lions on April 9, 1979. Construction consisted of a 600-foot-long breakwater, a 170-foot-long stub breakwater inclosing a 12-acre harbor. Tidal range between mean lower low water and mean higher high water is 9.6 feet with an extreme range of 18 feet. A severe storm in November 1981 badly damaged the project. The repair work included replacing material of the existing main breakwater, extending the main breakwater 125 feet, changing the seaward breakwater slope to a 2.OH:1.OV adding a layer of armor rock and raising the design crest elevation from + 18.5 mean lower low water to +22.0 mean lower low water. Minor dredging in the entrance channel to -15.0 mean lower low water was also included. Local Cooperation. Fully complied with. Terminal facilities. A municipal timber pile dock at Port Wakefield serves as both a shallow-draft and deepdraft facility for Port Lions. Operations during fiscal year. Maintenance: Project is complete. Contractor claim for differing site conditions for dredging is pending. 12. PROJECT CONDITION SURVEYS Preliminary and detailed surveys to determine navigation conditions at boat basins, small navigation projects, channels, and tributaries of major rivers not within major project boundaries. Total costs for fiscal year were $473,826 (See Table 40-I). 13. STIKINE RIVER, AK Location. Rises in northwestern Canada and flows southwesterly through Canada for about 200 miles, then about 30 miles westerly across Panhandle of Alaska to Sumner Strait. Mouth of river is on coast of mainland about 3 miles north of Wrangell. (See NOAA/NOS Chart #17360.) Existing project. Snagging Stikine River from its mouth for about 30 miles to Canadian border. The Canadian Government maintains that portion of the river between Alaskan border and Telegraph Creek, British Columbia, a distance of 130 miles. The head of navigation is at Telegraph Creek, B.C., about 160 miles above the mouth. No data is available concerning stages of high and low water in river. At mouth, tidal range between mean lower low water and mean higher high water is 13.9 feet, and maximum range is about 25 feet. Tidal effects have been reported at a distance of 20 miles from the mouth. Local cooperation. None required. Terminal facilities. None along Alaskan portion of river. Vessels operating on Stikine River are dependent on terminal facilities at Wrangell Harbor. Facilities include a city operated pier for general cargo and passengers; two publicly operated small-boat mooring floats; two privately operated small-boat fueling floats; a State of Alaska Ferry Pier, and three industrial wharves. Operations during fiscal year. Maintenance: Memorandum of Understanding between Corps and Forest Service signed August 1972 provided for Forest Service personnel to do project clearing. However, due to environmental restraints, no work was accomplished until 1977 after completion of an environmental assessment. The work has been accomplished annually by the U.S. Forest Service since 1977. Two contracts were awarded by the Corps for maintenance of the Stikine River Channel. One contract was for removing snags and the other was for clearing the channel. Both contracts were completed in FY 1985. Flood Control 14. CHENA RIVER LAKES, AK Location. In the vicinity of Fairbanks, AK, and encompassing the Tanana River, Chena River, Little Chena River, and their tributaries. (See USGS map Fairbanks, Cl, Dl, D2, and Big Delta D6.) Local cooperation. Fully complied with. Existing project. Moose Creek Dam has been constructed 17 miles east of Fairbanks with control works on Chena River. The dam itself extends from a bluff one mile north of the Chena River and south past the control works for approximately six miles to the Tanana River. The dam connects with a completed 22-mile levee system along the north boundary of the Tanana River to a point south and west of Fairbanks. Estimated Federal cost is $263,000,000, (excluding Little Chena Dam, presently deferred) and estimated non-Federal cost is $12,548,000. Operations during fiscal year. New work: Constructtion of Groins 4 thru 8 was completed in June 1985. The Debris Control Structure constructed on the Moose Creek Dam control works was completed in September 1985. Maintenance: A major high water event in May 1985 necessitated lowering the flood gates. Although no direct flooding was caused by the highwater event, underseepage of Moose Creek Dam raised the existing ground water table causing some basement annd crawl space flooding. 15. KUSKOKWIM RIVER, BETHEL, AK Location. Kuskokwim River bank at Bethel, AK. Existing project. Work was authorized under the continuing authority contained in Section 14 of the 1946 Flood Control Act. This authority allows construction of emergency bank protection to prevent loss of the city's multipurpose bulkhead and petroleum dock. Approximately 200 linear feet of rock riprap was placed at the toe of the sheet pile petroleum transfer facility that provides the fuel for Bethel and the 48 surrounding communities. Approximately 40 lineal feet of rock toe was constructed at the downstream end of the Mission Road section of the city's multipurpose pipeline bulkhead which protects their commercial and residential district. Local cooperation. The project sponsor, city of Bethel, provided construction easements and rights-of-way, and 40-5 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 agreed to hold the United States free from damages and maintain and operate the completed bank protection works. Operations during Fiscal year. New work: Contract was awarded in September 1985 and work is scheduled for completion in October 1985. 16. FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION Emergency flood control activities- repair, flood fighting, and rescue work (Public Law 99, 84th Congress, and antecedent legislation). Federal costs for the fiscal year were $105,045 for disaster preparedness. Flood control activities pursuant to Section 205, Public Law 858, 80th Cong., as amended (preauthorization). Fiscal year cost for preauthorization study was: Aniak, $61,417. 17. INSPECTION OF COMPLETED FLOOD CONTROL PROJECTS Inspections were made of flood control works at Lowell Creek in March 1985, Skagway River on April 10, 1985, Gold Creek and Salmon River during August 5-7, 1985. Repairs at each project were recommended to the local authority. Total costs for the fiscal year: $14,014. 18. INSPECTION OF COMPLETED PIL99 WORKS Inspections were made of levees rehabilitated under Public Law 84-99 and local sponsors advised of results and recommendations. Fiscal year costs were $856. Multiple-Purpose Projects, Including Power 19. SNETTISHAM, AK Location. At mouth of Speel River, between Crater Lake to the west and Long Lake to the north, 28 nautical miles southeast of Juneau. (See Coast Geodetic Survey Chart 8227.) Existing project. Snettisham is a multi-stage power project. The initial stage of the initial phase which was completed in 1977 tapped Long Lake and included an underground powerhouse with two 23.4 megawatt units and a transmission line to Juneau, AK. The project was turned over to the Alaska Power Administration for operation and maintenance. The second stage, under design and construction, will provide a tunnel to Crater Lake and add a third unit. The final phase will provide a dam on Long Lake to increase storage and the energy capability of Long Lake. The Long Lake Dam is currently unscheduled. The existing Long Lake (elevation 815 feet) water is transported through an approximately horizontal 13-foot diameter tunnel 8,400 feet long and a 1,400-foot penstock dropping at a 46 degree angle to the undergound powerhouse at tidewater to drive two turbines with a combined generating capacity of 47,600 kilowatts. Power from two generators is supplied to Juneau by a 13.8 kilovolt overhead transmission line and a submarine cable traversing Taku Inlet. Crater Lake stage of construction provides for tapping Crater Lake (elevation 1,022 feet) to drive a third turbine to be installed in the existing underground powerhouse to provide an additional nameplate-rated generating capacity of 34,500 kilowatts. Estimated cost of initial phase construction is $139,000,000. Local cooperation. None required. Operations during fiscal year. New work: Engineering and Design on the Crater Lake Phase included 100 percent completion of the feature design memorandum for power tunnel, penstock, lake tap, gate structure and surge tank; 80 percent completion of plans and specifications for completing the initial development including gate structure, penstock surge tank, machine shop powerhouse completion and lake tap; and 99 percent completion of plans and specifications for generator, powerhouse completion and electrical contracts. Investigations included an extensive lake tap study using refraction seismic survey, sub-bottom profiling, and corehole drilling to determine the amount and type of overburden and bedrock conditions in the lake tap area and beginning of a study to determine the economic viability of proceeding with the final phase of development of the Long Lake Dam. The initial construction contract of the Crater Lake phase was awarded September 28, 1984. Work performed under the contract included rock excavation of the power tunnel, penstock access adit, and machine shop adit, chamber and tunnel to powerhouse with contract scheduled for completion in October 1985. General Investigations 20. SURVEYS Fiscal year costs of $1,067,506 for surveys include $105,516 for navigation studies, $844,456 for flood control studies, $24,352 for coordination studies and $93,182 for miscellaneous activities. 21. COLLECTION AND STUDY OF BASIC DATA Technical assistance, information, flood plain management guidance and other flood plain management services have been provided to military and nonmilitary Federal agencies, local communities, State agencies, Architectural/ Engineering firms, lending institutions and private individuals at a fiscal year cost of $108,565. Fiscal year costs for Hydrologic Studies were $16,822. 22. CONTINUATION OF PLANNING AND ENGINEERING Bethel Bank Stabilization, AK The proposed project would provide steambank protection to the city of Bethel, AK, located in western Alaska on the Kuskokwim River. The recommended plan calls for rock riprap protection for 8,000 feet of river bank with the rock extending from above the active wave zone to the thalweg of the river. A Plan of Study was prepared for the General Design Memorandum in FY 1984. Work on the General Design Memorandum initiated in FY 1984 is 50% complete and scheduled for completion 40-6 ALASKA DISTRICT in FY 1986. Estimated preconstruction planning cost is Federal project authorization. A storm in May 1985 $550,000. Fiscal year costs were $225,896. critically endangered portions of their bulkhead and a Sec- The city of Bethel constructed a bulkhead to protect tion 14 Emergency Streambank Protection project was approximately 4,000 feet of river bank while awaiting constructed by the Corps to protect the city's investment. 40-7 TABLE 40-A REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 COST AND FINANCIAL STATEMENT See Section Total to In Text Project Funding FY 82 FY 83 FY 84 FY 85 Sep. 30, 1985 1. Anchorage Harbor, AK Bethel Small Boat Harbor, AK (Contrib. Funds) Cordova Small Boat Harbor, AK 3. (Contrib. Funds) 4. Dillingham Harbor, AK (Contrib. Funds) 5. Homer Harbor, AK (Contrib. Funds) 6. Kake Harbor, AK King Cove Harbor AK M tlakatla Harbor AK (Contrib. Funds) Ninilchik Harbor, AK New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost New Work Contrib. Cost New Work Approp. Cost New Work Contrib. Cost New Work Approp. Cost Maint. Approp. Cost Maint. Contrib. Cost New Work Approp. Cost Maint. Approp. Cost Rehab. Approp. Cost New Work Contrib. Cost New Work Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Contrib. Cost New Work Approp. Cost - - - - 533,235 - - - - 533,235 2,374,900 946,000 2,001,021 1,225,405 690,000 307,000 73,665 915,017 1,679,000 1,181,725 15,410,172 754,434 2,086,585 15,259,016 - - 1,520,272 2,090 406 1,514,450 2,000,000 -1,284,600 -106,290 299,975 550,205 -633 - 113,000 1,954,080 301,525 609,110 609,110 - 7,562,000 9,562,0001 - 7,561,366 9,560,3391 52,800 - 4,813,000 53,677 98,731 4,811,891 - - - - 548,790 - - - - 548,790 384,500 266,000 350,000 372,000 4,938,821 352,356 295,862 325,219 421,969 4,928,377 - - - - 1,700 - - - - 1,700 115,000 90,786 30,000 1,723,000 78,817 1,729,421 296,400 294,000 288,570 316,897 70,000 72,435 - 3,512,3502 - 3,512,3502 50,000 2,398,711 49,655 2,398,297 - - - 67,974 - - - 67,974 - 8,057,500 258,960 8,316,4603 - 8,010,237 275,719 8,285,9563 - 120,000 2,685 91,298 70,000 85,533 25,000 34,887 855,700 852,437 - 2,264,948 - 2,264,948 - 491,494 76,000 - 436,119 131,314 621,898 -25,000 -229,000 28,597 -204,702 567,494 567,433 75,000 4,922,470 17,134 4,844,602 99,000 13,839 200,000 200,007 - -206827 - -206,827 149,520 64,359 830,644 621,173 428,720 428,720 40-8 8. 9. 7. ALASKA DISTRICT TABLE 40-A (Continued) COST AND FINANCIAL STATEMENT See Section Total to In Text Project Funding FY 82 FY 83 FY 84 FY 85 Sep. 30, 1985 10. Nome Harbor, AK (Contrib. Funds) 11. Port Lions Small Boat Harbor, AK (Contrib. Funds) 13. Stikine River, AK 14. Chena River Lakes, AK (Contrib. Funds) 15. Kuskokwim River, Bethel, AK 19. Snettisham, AK Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Contrib. Cost Maint. Contrib. Cost New Work Approp. Cost Maint. Approp. Cost New Work Contrib. Cost Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Contrib. Cost New Work Approp. Cost New Work Approp. Cost 270,700 237,000 300,000 156,000 3,120,476 260,871 244,916 302,425 155,806 3,120,268 - - - - 1,348,240 - - - - 1,348,240 753,700 291,000 273,000 561,000 6,954,907 432,511 532,403 367,979 407,142 6,769,830 - - - - 125 - - - - 125 2,500 2,500 5,000 - -7,000 - 44,738 - 80,000 1,600,000 32,008 1,555,354 1,110,000 22,000 17,544 904,018 4,000 10,000 15,100,000 13,900,000 14,794,879 13,522,702 459,700 538,000 571,821 536,356 - 2,031,700 - 1,616,440 2,500 510 -83,423 9,215 56,378 10,000 4,722 4,656,300 5,349,609 718,000 685,741 150,600 522,722 5,000 157,500 5,000 157,500 - 1,825,311 - 1,825,311 - 1,596,577 - 1,596,577 35,171 22,000 27,255 1,061,137 1,037,113 183,364 181,549 7,103,000 196,517,7654 7,114,257 196,373,7634 859,000 2,926,3245 938,688 2,910,9155 - 2,182,300 6,767 2,145,929 - 132,500 - 15,028 132,500 15,028 2,000,000 570,000 1,499,700 7,997,000 93,449,556 1,347,018 1,157,838 1,258,244 8,226,946 93,372,633 'Includes judgment and associated cost. Includes $2,672 of Code 710 Rec. Funds and $1,509,677 for previous project. 3Includes only actual Funds retained and cost incurred. 4Includes $310,000 for previous project (Fairbanks). 5Includes $1,624 for previous project (Fairbanks). 40-9 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 40-B AUTHORIZING LEGISLATION See Date Section Authorizing in Text Act Project and Work Authorized Documents July 3, 1958 Oct.' 22, 1976 July 14, 1960 July 14, 1960 Aug. 15, 1985 July 3, 1958 July 2, 1958 Aug. 19, 1964 Jul. 14, 1960 Aug. 13, 1968 Aug. 13, 1968 Mar. 2, 1945 Oct. 27, 1965 July 3, 1958 1. ANCHORAGE HARBOR, AK Deep water harbor, adjacent to docks, dredge to 35 feet below mean lower low water, protected by two jetties. Extension of project limits. BETHEL SMALL BOAT HARBOR, AK Construct 7,700-foot-long small boat harbor and entrance channel by deepening, widening, and straightening the upper 6,800 feet of Brown's Slough. CORDOVA SMALL BOAT HARBOR, AK Construction of 2,000-foot breakwater. Payment of judgment and associated interest. DILLINGHAM HARBOR, AK Basin 230,000 square feet in area with depth of 2 feet above mean lower low water along Scandinavian Creek, with entrance channel 1,100 feet long and 40 feet wide. HOMER HARBOR, AK Basin 2.7 acres in area with depth of 12 feet below mean lower low water, and rock breakwater 1,260 feet long. Relocation and rehabilitation of project destroyed by March 27, 1964 earthquake, by construction of basin 10 acres in area with 12-foot depth over 2.75 acres and 15-foot depth over 7.25 acres protected by rock breakwaters, 1,018 feet and 238 feet long. Increased width and depth of entrance channel and an enlarged staging area. Basin enlarged from 16.5 to 50 acres. KAKE HARBOR, AK Basin 7-acre berthing area, 15 feet deep, inclosed by a 1,580-foot west rock breakwater and a 900-foot south rock breakwater. KING COVE HARBOR, AK Anchorage basin of 11 acres, 15 feet deep, an entrance channel 125 feet wide and 15 feet deep; an earth fill training dike; and a rockfill groin. METLAKATLA HARBOR, AK Dredging small boat basin 2.18 acres in extent to a depth of 10 feet below plane of mean lower low water; construction of rubblemound breakwater 900 feet long. Entrance channel and two rubblemound breakwaters inclosing a 7.0 acre basin. NINILCHIK HARBOR, AK Basin 320 feet long by 150 feet wide with depth of 2 feet above mean lower low water, approach channel 400 feet long and 50 feet wide with depth of 9 feet above mean lower low water, protected by 410-foot jetty. 40-16 H. Doc. 34, 85th Cong., 1st Sess? P.L. 94-587 Section 107, P.L. 86-645 Authorized by Chief of Engineers, June 29, 1978 Section 107, P.L. 86-645 Authorized by Chief of Engineeers, April 23, 1981 P.L. 98-88 H. Doc. 390, 84th Cong., 2d Sess? H. Doc. 34, 85th Cong., 1st, Sess? P.L. 88-451 Section 107, P.L. 86-645 Authorized by Chief of Engineers, Nov. 13, 1981 S. Doc. 70, 90th Cong., 2d Sess? S. Doc. 13, 90th Cong., 1st Sess? H. Doc. 138, 76th Cong., 91st Sess. Section 201, P.L. 89-298 S. Doc. 92-64, 92d Cong., 2d Sess? Authorized Oct. 12, 1972 H. Doc. 34, 85th Cong., 1st Sess? 3. 4. 6. 7. 8. 9. ALASKA DISTRICT TABLE 40-B AUTHORIZING LEGISLATION (Continued) See Date Section Authorizing in Text Act Project and Work Authorized Documents 10. NOME HARBOR, AK Aug. 8, 1917 Two jetties, easterly 335 feet and westerly 460 feet long H. Doc. 1932, 64th Cong., revetment, channel and basin 200 feet wide and 250 2d Sess? feet long. Aug. 30, 1935 Extension of the jetties and enlarging basin to 250 H. Doc. 404, 71st Cong., feet wide and 600 feet long? 2d Sess., and Rivers and Harbors Committee Doc. 38, 73d Cong., 2d Sess? June 16, 1948 Seawall Report of Chief of Engineers dated March 8, 1948 11. PORT LIONS SMALL BOAT HARBOR, AK July 14, 1960 Construction of a 600-foot breakwater and a 170-foot Section 107, P.L. 86-645 stub breakwater inclosing a 12-acre harbor. Authorized by Chief of Engineers, April 9, 1979 13. STIKINE RIVER, AK Aug. 30, 1935 Snagging from mouth to Canadian border. H. Doc. 210, 72d Cong., 1st Sess? 14. CHENA RIVER LAKES, AK Aug. 13, 1968 Dam and reservoir on the main Chena River, a dam S. Doc. 89, 90th Cong., and detention reservoir on the Little Chena River, and 2d Sess? a levee along the north side of the Tanana River.4 15. KUSKOKWIM RIVER, BETHEL, AK July 24, 1946 Construct rock and riprap mat in front of pile Section 14, P.L. 79-526 structures. Authorized by Chief of Engineers Sep. 13, 1985 19. SNETTISHAM, AK Oct. 23, 1962 Multi-purpose dam, with powerhouse and transmission H. Doc. 40, 87th Cong., facilities. 1st Sess? 'Purchase of dredge and deepwater jetties deauthorized November 6, 1977 under section 12, Public Law 93-251. 2Contains latest published map. 3Extension of jetties classified "inactive". 4Little Chena Dam classified "deferred". 40-11 TABLE 40-C REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 OTHER AUTHORIZED NAVIGATION PROJECTS For Last Cost to Sep. 30, 1985 Full Report Operation See Annual and Project Status Report For Construction Maintenance Apoon Mouth of Yukon River, AK' Completed 1920 $ 128,896 $ 2,154 Bar Point Harbor, AK2 Completed 1983 2,000,0003 - Cook Inlet Shoals, AK Completed 1977 1,220,000 5,000 Cordova Harbor, AK Completed 1978 843,534 488,156 Craig Harbor, AK Completed 1983 1,033,5004 72,500 Douglas Harbor, AK Completed 1963 282,019 - Dry Pass, AK Completed 1983 943,351 23,466 Egegik River, AK Completed 1972 4,441 3,107 Elfin Cove, AK Completed 1959 154,191 - Gastineau Channel, AK Completed 1964 789,461 102,701 Haines Harbor, AK2 Completed 1977 1,000,0005 - Hoonah Harbor, AK Completed 1983 4,255,0008 - Humboldt Harbor, AK Completed 1977 3,679,6837 - Iliuliuk Harbor, AK Completed 1941 66,037 - Juneau Harbor, AK Completed 1974 1,381,150 260,991 Kasilof Harbor, AK2 Completed 1975 109,848 - Ketchikan Harbor, AK Completed 1979 1,602,417 331,256 Kodiak Harbor, AK Completed 1973 1,891,2128 37,946 Myers Chuck Harbor, AK Inactive 1970 9,700 - Naknek River, AK Completed 1961 20,789 - Neva and Olga Straits, AK Completed 1960 155,009 - Old Harbor, Kodiak Island, AK2 Completed 1972 370,415 132,946 Pelican Harbor, AK Completed 1964 369,683 18,973 Petersburg Harbor, AK Completed 1972 252,932 26,800 Port Alexander, AK Completed 1949 17,000 - Rocky Pass, AK Completed 1960 337,668 - St. Michael Canal, AK Completed 1916 377,062 560 Seldovia Harbor, AK Completed 1974 1,051,8839 5,518 Sergius Whitestone, AK Completed 1973 1,798,010 1,934 Seward Harbor, AK Completed 1973 712,36910 219,789 Sitka Harbor, AK Completed 1973 1,611,009 15,490 Skagway Harbor, AK Completed 1972 133,180 32,665 Valdez Harbor, AK Completed 1968 649,7401 221,498 Wrangell Harbor, AK Completed 1969 537,020 331,352 Wrangell Narrows, AK Completed 1979 3,562,343 309,260 1Adandonment recommended in H. Doc. 467, 69th Cong., 1st Sess. 2Authorized by Chief of Engineers (Sec. 107). 3In addition, $272,779 of State funds. 4Includes $656,240 for Sec. 107 project. 5In addition, $925,500 of State funds. 6In addition, $973,875 of State funds. 7In addition, $857,000 of State funds. "Includes $594,163 for rehabilitation. 9Includes $400,000 for rehabilitation. 10Ion cludes $90,026 for rehabilitation and $2,528 Code 710, Recreation Facilities at Completed projects. "Includes $73,000 for rehabilitation and $2,713 Code 710, Recreation Facilities at Completed projects. 40-12 ALASKA DISTRICT TABLE 40-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS For Last Cost to Sep. 30, 1985 Full Report Operation See Annual and Project Status Report For Construction Maintenance Fairbanks, Tanana River & Chena Slough, AK Completed 1943 557,000 - Gold Creek, AK Completed 1975 876,0061 4,301 Klutina River, Copper Center, AK2 Completed 1973 260,681 - Lowell Creek, AK Completed 1945 416,3823 30,771 Salmon River, AK Completed 1963 37,7704 162,9256 Skagway River, AK Deferred7 1966 26,385 - Talkeetna River, AK Completed 1981 516,694 - 'In addition, $25,000 expended from contributed funds. 5In addition, $7,000 expended from contributed funds. 2Authorized by Chief of Engineers (Sec. 205). "In addition, $27,400 expended from contributed funds. 3In addition $25,000 expended from contributed funds. 7Project eligible for deauthorization. Includes $34,197 of PWA funds. TABLE 40-G DEAUTHORIZED PROJECTS For Last Full Report Federal Contributed See Annual Date Funds Funds Project Report Deauthorized Expended Expended Anchorage Harbor, AK 1967 1977 - - (Uncompleted Portion) Bradley Lake, AK Ketchikan Harbor, AK (West Breakwater) Port Alexander, AK (Inner Harbor) Tolovana River, AK (Snagging) 1983 1979 1949 1931 1982 1979 1977 1977 $6,701,000 40-13 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 40-H NAVIGATION WORK UNDER SPECIAL AUTHORIZATION Navigation Activities Pursuant to Section 107, Public (Preauthorization) Study Identification Chignik, AK Dillingham Small Boat Harbor, AK Juineau Harbor, AK Larson Bay Small Boat Harbor, AK Mekoryuk, AK Sand Point, AK Saxman, Ak Seward, AK St. George Island AK Togiak Harbor, AK Whittier, AK TOTAL Fiscal Year Costs $ 166,618 3,807 109,094 83,479 65,372 267,862 93,388 155,419 41,540 67,520 198,841 $1,252,940 TABLE 40-I PROJECT CONDITION SURVEYS Name of Project Date Survey Conducted Alaska: Humbolt Harbor October 1984 Old Harbor November 1984 Metlakatla January 1985 Wrangell Harbor January 1985 Sergus/Whitestone January 1985 Juneau Harbor March 1985 Pelican Harbor March 1985 Elfin Cove March 1985 Seward Harbor April 1985 Cordova Harbor May 1985 Valdez September 1985 40-14 Law 86-645 BOARD OF ENGINEERS FOR RIVERS AND HARBORS The Board of Engineers for Rivers and Harbors is a continuing body created by Section 3 of the 1902 River and Harbor Act. The Board is selected by the Chief of Engineers and consists of seven senior engineer officers. The Deputy Chief of Engineers normally serves as Chairman. Five members are Division Engineers with membership rotated among divisions having Civil Works missions. The seventh member, assigned full time to the Board as Resident Member, also directs the staff in carrying out the responsibilities of the Board. The Board meets quarterly or on call of the Chairman. The Board has several statutory duties. It conducts independent reviews of Corps survey reports covering water resources projects and reports its conclusions and recommendations to the Chief of Engineers. The Chief of Engineers then forwards the reports with his conclusions and recommendations to the Assistant Secretary of the Army (Civil Works) for transmission to the Congress. The Board also conducts independent reviews of special reports ordered by the Congress. It considers and approves general plans for major modification and reconstruction of any lock, canal, canalized river or other work for the use or benefit of navigation. In addition to its statutory duties, the Chief of Engineers has assigned further duties to the Board. It reviews Corps policies and procedures as directed, additional special reports for the Secretary of the Army and the Chief of Engineers, reports of other Federal agencies pertaining to water resources development as directed, and conducts a 10-month program of in-service training for approximately 15 Corps planners anually-generally at GS 12 and 13 levels-in all aspects of Federal water resources development. The training program helps meet Corps needs for increased numbers of qualified people in the planning field. The Board also has administrative responsibility for processing proposed reports of the Chief of Engineers, along with Final Environmental Impact Statements, to states and Federal agencies for their 90-day review. In addition to other duties, the Resident Member of the Board has served as second alternate for the Secretary of the Army on the Foreign Trade Zones Board. The Secretary of the Army has also appointed the Resident Member to serve as his representative on the Committee of Alternates of the Foreign Trade Zones Board and authorized him to act directly on the Secretary's behalf on all nondiscretionary matters involving foreign trade zones. This appointment relieves the Assistant Secretary of the Army for Civil Works of routine duties in this regard; however, discretionary matters concerning the Foreign Trade Zones Board remain under previous delegations of authority. Total membership of the Board is fixed by law at seven. In December 1982, the Chief of Engineers instituted a mechanism for predesignating future members based on their time of service as division engineers, geographical factors, and other criteria. This procedure achieves a wider involvement of division engineers and their staffs with the proceedings of the Board. Members Designate attend and participate in meetings of the Board, but are not permitted to vote on Board actions. �he nti,,ti ,, .. 1oara as of Septeiter 1, IMS65 was as follows: Members: Major General Norman G. Delbridge, Jr., Chairman, Deputy Chief of Engineers, Casimir Pulaski Building, Washington, DC Brigadier General (P) Jerome B. Hilmes, Division Engineer, Southwestern, Dallas, Texas Brigadier General Thomas A. Sands, Division Engineer, Lower Mississippi Valley, Vicksburg, Mississippi Brigadier General Donald J. Palladino, Division Engineer, South Pacific, San Francisco, California Brigadier General Peter J. Offringa, Division Engineer, Ohio River, Cincinnati, Ohio Brigadier General Charles E. Dominy, Division Engineer, Missouri River, Omaha, Nebraska Colonel John W. Devens, Resident Member, Board of Engineers for Rivers and Harbors, Fort Belvoir, Virginia Members Designate: Brigadier General (P) George R. Robertson, Division Engineer, North Pacific, Portland, Oregon Brigadier General Charles E. Edgar III, Division Engineer, South Atlantic, Atlanta, Georgia Official Board Actions. In compliance with resolutions of Congress and instructions from the Chief of Engineers, the Board completed 44 official report reviews during Fiscal Year 1985. The favorable reports category includes favorable recommended projects for Federal construction as well as projects for solving water resources problems for major metropolitan areas, even though they may not include recommendations for construction by any agency of the Federal Government. Reports Recommending Favorably for Federal Construction: The Board recommended 26 projects at an estimated total first cost of $1,212,619,000, of which $572,670,000 is the first to the United States, as follows: Roanoke River Upper Basin, Virginia Wisconsin River at Portage, Wisconsin Falfurrias, Texas Mt. St. Helens, Washington Oakland Inner Harbor, California Sarasota County, Florida Pinellas County, Florida Palm Beach Harbor, Florida Arkansas City, Kansas Nassau County, Florida Unalaska, Small Hydropower, Alaska Pascagoula Harbor, Mississippi William H. Harsha Lake, Ohio Ste. Genevieve, Missouri Lower Saddle River, New Jersey Ramapo River at Oakland, New Jersey Molly Ann's Brook, New Jersey St. Anthony Falls Hydropower, Minnesota Truckee Meadows, Nevada Delaware River from Philadelphia to Wilmington Palo Duro Lake, Texas Island Creek Basin, West Virginia Rio Puerto Nuevo, Puerto Rico 41-1 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 During this fiscal year, four reports were recalled by reporting officers without Board Action: Gulf Coast Passes, Florida; Port Bienville Industrial Park, Mississippi; Tampa Harbor, Alafia River and Big Bend Channel, Florida; and Providence Harbor and River, Seekonk River, Providence, Rhode Island. The Providence Harbor and River Report, however, was returned and processed by the Board du'ino the Fiscal Year. Report; Recommending Unfavorably for Federal Construction: During Fiscal Year 1985, the Board concurred in unfavorable recommendations of the reporting officers :or Federal construction on 18 projects: Oswego River Basin, New York Mississippi Sound and Adjacent Areas Fox River and Tributaries, Illinois and Wisconsin Rippowam River Basin, Connecticut and New York Delaware River Basin, New York, New Jersey, Pennsylvania, and Delaware Cady Marsh Ditch, Little Calument River, Indiana Jones Inlet to Freeport, New York Cape Fear River from Acme to Fayetteville, North Carolina San Pedro Bay Ports Transportation Study Chesapeake Bay Special Study Hampton Roads, Virginia, Water Supply Black Warrior and Tombigbee Rivers, Alabama Richland Creek, Illinois Delaware River Basin Ice Jam Study Providence Harbor, Rhode Island (Debris Study) Pine Island Bayou, Texas Seal Beach, Anaheim Bay Harbor, Orange County, California Alice, Texas General Design Memoranda: The Board reviewed and submitted favorable recommendations on three General Design Memoranda during the reporting period: Virginia Beach, Virginia; O'Hare System, Chicagoland Underflow, Illinois; and Cleveland Harbor, Ohio. During Fiscal Year 1985, the Board held four meetings: October 30, 1984, December 19, 1984, March 13, 1985, and June 26, 1985. Since 1902, the Board has acted on 8,725 reports, recommending favorably on 3,895 and unfavo-ably on 4,830. 41-2 MISSISSIPPI RIVER COMMISSION* The Mississippi River Commission (MRC) was created by an act of Congress on Jun. 28, 1879. The Flood Control Act of May 15, 1928, authorized the Flood Control, Mississippi River and Tributaries (MR&T) Project. The Commission consists of three officers of the Corps of Engineers, one from the former Coast and Geodetic Survey (presently the National Oceanic and Atmospheric Administration), and three civilians, two of whom must be civil engineers. All members are appointed by the President with the advice and consent of the Senate. During the fiscal year the Commissioners were: BG Thomas A. Sands, U.S. Army, President, appointed May 10, 1985; Mr. Sam E. Angel, appointed Sept. 25, 1979; Mr. R. D. James, civil engineer, appointed Dec. 1, 1981; BG Jerome B. Hilmes, U.S. Army, appointed Nov. 21, 1983; RA John D. Bossler, NOAA, appointed Mar. 14, 1984; BG Robert J. Dacey, appointed May 10, 1985; COL Joseph Yore, U.S. Army, served as Secretary of the Commission till his retirement Jul. 31, 1985. The MRC is charged, under direction of the Secretary of the Army and supervision of the Chief of Engineers, with prosecution of improvements for flood control of the Mississippi River and of its tributaries and outlets in its alluvial valley, so far as they are affected by Mississippi River backwater, between Head of Passes, LA (mile 0), and Cape Girardeau, MO (1,006 miles AHP-Lower Mississippi mileage terminates at mile 954 AHP), and with prosecution of improvements in the interest of navigation between Cairo, IL (954 miles AHP), and Baton Rouge, LA (234 miles AHP); and for stabilization of the lower 7 miles of the right bank of the Ohio River, to former mouth of Cache River. It also is charged with prosecution of certain flood control works on the Mississippi River and tributaries, as far as they are affected by backwater, between Cape Girardeau, MO, and Rock Island, IL (1,437 miles AHP), and with prosecution of improvements on designated tributaries and outlets below Cape Girardeau for flood control, navigation, major drainage, and related water uses. Authorized operations of the Commission below Cape Girardeau are conducted by District Engineers of New Orleans, Vicksburg, and Memphis Districts within the areas described below, in accordance with approved directives and programs and congressional appropriations therefor. New Orleans District: Mississippi River project levees and river channel stabilization as required from Head of Passes, mile 0 to 320 AHP, construction of four salinity-control structures for fish and wildlife enhancement in lower Mississippi River Delta region; Bonnet Carr4 and Morganza Floodways; maintenance and improvements of Mississippi River navigation channel from Baton Rouge, LA (mile 234 AHP), to mile 320; Baton Rouge Harbor (Devils Swamp); navigation improvement of Atchafalaya and Old Rivers from Mississippi River to Morgan City; control of Old and Atchafalaya Rivers; Atchafalaya Basin Floodways; flood control and drainage improvements in Bayou Cocodrie and tributaries, in Bayou des Glaises, and in Upper Pointe Coupee Loop area; flood protection in eastern Rapides and south-central Avoyelles Parishes, LA; and freshwater distribution from Atchafalaya River to Teche-Vermilion Basins. Vicksburg District: Mississippi River project levees and river channel stabilization as required from upper limits of New Orleans District (mile 320 AHP) in vicinity of Black Hawk, LA, to Coahoma-Bolivar County line, MS (mile 620 AHP) on left bank, and to vicinity of mouth of White River, AR (mile 599 AHP), on right bank including south bank Arkansas River levee to vicinity of Pine Bluff, AR, and north bank levee to vicinity of Tucker on left bank of Plum Bayou, AR; bank stabilization in lower 36.1 miles of Arkansas River; maintenance and improvement of Mississippi River navigation channel between miles 320 and 599 AHP; Vicksburg and Greenville Harbors; specific fish and wildlife facilities in Tensas, Yazoo, and Big Sunflower Basins; a streambank erosion control project in the Yazoo Basin; flood control and drainage improvements in Red River backwater area including leveed portion east and west of Black River and south of Red River; Jonesville, LA, Boeuf and Tensas Rivers, Bayou Macon Basins and tributaries, AR and LA, and Bayou Lafourche, LA; Yazoo River Basin, MS, including backwater area; Big and Little Sunflower Rivers, Deer Creek, and Steele Bayou, MS; and Grand Prairie Region and Bayou Meto Basin, AR, including provision for agricultural water supply. Memphis District: Mississippi River project levees and river channel stabilization as required, from upper limits of Vicksburg District to north bank of Little River diversion channel, MO (1,003 miles AHP), a few miles below Cape Girardeau, MO, on right bank, and to Cache River diversion channel (967 miles AHP) above Cairo, IL, on left bank, including levees and revetment on right bank of Ohio River, in Mounds-Mound City area, IL; except operations above Cairo, IL, do not * Authorizing legislation (Tables 42-D and 42-E) is listed at the end of this chapter. All other tables are referenced in text and also appear at the end of this chapter. 42-1 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 include channel stabilization on the Mississippi River. Maintenance and improvement of Mississippi River navigation channel between mile 599 and 954 AHP and of Memphis Harbor, TN; specific fish and wildlife facilities in St. Francis Basin; levees in White River backwater area up to vicinity of Augusta, AR, and a pumping plant near mouth of White River; levees and pumping plants at De Valls Bluff and Des Arc, AR; channel improvements in Cache River Basin, AR; channel improvements in Big Creek and tributaries, AR; improvement works in St. Francis River Basin, MO and AR, including backwater area improvements in Belle Fountain Ditch and Drainage District No. 17, AR; Little River diversion channel, MO, and L'Anguille River, AR; Wolf River Basin, TN; Obion and Forked Deer River Basins, TN; Reelfoot Lake area, including channel improvement for Bayou du Chien and Lake No. 9, TN and KY; West Kentucky tributaries, KY; Mud Lake pumping station, TN; and pumping plants and outlet structures in the Cairo-Mounds-Mounds City area, IL. Field operations of the Commission restricted to levee construction under Sec. 6, 1928 Flood Control Act (local interests contributing one-third of costs and furnishing rights-of-way) are conducted within the following limits by two districts reporting directly to the Commission on matters within their jurisdiction- St. Louis District: Mississippi River (Sec. 6) levees from upper limits of Memphis District to Clemens Station, MO (1,254 miles AHP), on right bank, and Hamburg Bay, IL (1,215 miles AHP), on left bank, and Illinois River from its mouth to mile 120 at Havana, IL. Rock Island District: Mississippi River (Sec. 6) levees from upper limits of St. Louis District to Rock Island, IL (1,437 miles AHP). For work accomplished see Table 42-N, page 42-50, Annual Report for 1975. MISSISSIPPI RIVER AND ALLUVIAL VALLEY BELOW CAPE GIRARDEAU, MO. Location and description. The Mississippi River rises in Lake Itasca, MN, and flows generally southerly for 2,340 miles through the central portion of United States to empty into the Gulf of Mexico 115 miles below New Orleans. It is improved for barge navigation for 1,832 miles to Minneapolis, MN. The Mississippi River and its major tributaries, the Missouri, Ohio, St. Francis, White, Arkansas, Yazoo, and Red-Old Rivers, drain 1,245,000 square miles in all or part of 31 states between the Rocky and Appalachian Mountains and part of two Canadian provinces. Below Cape Girardeau, MO, 53 miles above Ohio River, river bottomlands widen abruptly into an alluvial valley of 35,460 square miles which was originally subjected to flood overflow. A major part of the alluvial valley has been protected from floods by levees which confine floodflows within a floodplain having an average width of 5 miles. (See map of alluvial valley of Mississippi River, scale 1:500,000.) Observations made by Mississippi River Commission to Sep. 30, 1982, show approximate alltime maximum and minimum discharges between levees as follows: Cairo to White River, 2,000,000 and 70,000 cubic feet per second; thence to Red River, 2,150,000 and 90,000 cubic feet per second; thence to the Gulf of Mexico, 1,500,000 and 50,000 cubic feet per second in Mississippi River and 660,000 and 11,000 cubic feet per second in Atchafalaya River. As the 1927 floodflow was not confined between levees, maximum discharges recorded do not include entire flow of the 1927 flood, maximum of record below White River. High water and flood stages usually occur in late winter or early spring, but great floods such as that of 1937 occurred as early as January. Low water stages generally prevail from August to December. Extreme all-time ranges in stages recorded at representative gages (rounded to nearest foot) are 60 feet at Cairo, 49 feet at Memphis, 57 feet at Red River Landing, and 21 feet at New Orleans (Carrollton). The river is nontidal above Red River Landing where tidal amplitude rarely exceeds 0.1 foot during extreme low water. Previous projects. For details see page 1944, Annual Report for 1932. Existing project. The Mississippi River and Tributaries Project in the alluvial valley between Head of Passes, LA, and Cape Girardeau, MO, provides protection from floods by means of levees, floodwalls, floodways, reservoirs (in Yazoo and St. Francis Basins), bank stabilization, and channel improvements in and along the river and its tributaries and outlets insofar as affected by backwater of Mississippi River, including levee work on the main stem between Cape Girardeau and Rock Island. When completed, 23,621 square miles will be protected from the Mississippi River project flood. The project also provides for a 12- by 300-foot navigation channel between Baton Rouge, LA, and Cairo, IL; for salinity-control structures; and for channel realinement and improvement including bank stabilization and dikes to reduce flood heights, control natural tendency of river to lengthen by meandering, and protect levees from being destroyed by caving banks. Locations of major main stem Mississippi River improvements are shown in Table 42-A and those for off-main stem tributaries are shown in Table 42-B. Pertinent data on dams and lakes are shown in Table 42-C. Authorizing and incorporating legislation are shown in Tables 42-D and 42-E. Summary of presently estimated Federal cost of authorized improvements is shown in Table 42-F. Construction of the existing project began in 1928 and has continued throughout ensuing years. Based on the estimated cost of $9,402,902,000 (Cost projected through the construction period), and actual expenditures through Sep.30, 1985, of $3,947,321,196, the entire project is about 77.4 percent complete. Recommended modifications. None. Local cooperation. The Flood Control Act of 1928, as amended, applies. Such requirements have, in general, been complied with by local interests. Terminal facilities. See volume 1 of two-volume Port Series No. 21, 1979, "Ports on the Gulf Coast of the United States," for Baton Rouge and Lake Charles, LA; 42-2 MISSISSIPPI RIVER COMMISSION Port Series No. 20, 1981, for New Orleans, LA; also folio of Flood Control and Navigation Maps of Mississippi River Cairo, IL, to the Gulf of Mexico (52nd edition), 1984. Project cost. Total allotted for flood control, including maintenance charges through Aug. 18, 1941, chargeable under authorizations to Sep. 30, 1985, was $3,971,920,837. (See Table 42-S.) (See also Tables 42-R, 42-T, and 42-U for additional financial statements.) Operations and results during fiscal year. Commission activities: The 323rd session was held on October 1-5, 1984, on board the U.S. MV Mississippi en route on the Mississippi River from Cairo, IL, to Morgan City, LA. Bank protection works, levees and channel conditions were observed en route. Approximately 205 persons attended public meetings held at Cairo, IL; Memphis, TN; Greenville, MS; and Morgan City, LA. About 43 of the representatives presented various problems pertaining to flood control and navigation. This session adjourned at Morgan City, LA, at 10:30 a.m., October 5, 1984. The 324th session was held on Jan. 10, 1985, at the headquarters in Vicksburg, MS, for the purpose of considering the New Orleans District project report entitled "Mississippi and Louisiana Estaurine Areas Feasibility Study." Approximately 35 persons attended this meeting. This session adjourned at 1:55 p.m., Jan. 10, 1985. The 325th session was held May 6-10, 1985, on board the U.S. Motor Vessel Mississippi en route on the Mississippi River from Cairo, IL, to New Orleans, LA. Bank protection works, levees and channel conditions were observed en route. Approximately 211 persons attended public meetings held at Cairo, IL; Memphis, TN; Vicksburg, MS; and New Orleans, LA. About 36 representatives presented various programs for flood control and navigation. This session adjourned at New Orleans, LA, at 10:30 a.m., May 10, 1985. Records of Proceedings of all sessions of the Mississippi River Commission are on file in the office of the President. Alluvial Valley Mapping General. Contoured quadrangles and general maps of the alluvial valley are and public distribution uavnadielar bpler efsocrr idbeepda rrtmegeunlatatilo unsse. Preparation, revision, and publication of quadrangle maps (scale 1:62,500) continued. Road-map-type information brochures of principal portions of the overall project were published along with pamphlets on the subject of flood control and navigation. Maps and supplemental data sheets for active works were updated and published as required. The 1984 (52nd) edition of the folio of flood control and navigation maps (scale 1:62,500) covering the Mississippi River from Cairo, IL, to the Gulf of Mexico was revised and printed. Approximately 754.5 flight-line miles of infra-red color; 11,885 flight-line miles of black-and-white aerial photography (various scales); 191 flight-line miles of color photography; and about 349.2 hours of oblique photography were flown along the Mississippi River and tributaries in the New Orleans, Vicksburg, and Memphis Districts. Work accomplished in-the Districts: New Orleans Revisions of Chef Menteur, and Spanish Fort, LA, 1:62,500-scale quadrangles are nearing completion. Revision of New Orleans Area Map, 1:250,000-scale is nearing completion. Memphis District-Series conversion of USGS 1:24,000 scale to 1:62,500 scale quads of Horseshoe Lake, AR, Tilton, AR, Marked Tree, AR, and Manila, AR are in progress. Vicksburg District-Series conversion of U.S. Geological Survey 1:24,000-scale to 1:62,500-scale quadrangles, with addition of flood control features of Hernando, MS. Senatobia, Greenwood, Lexington, Seven Pines, Sardis, Mileston, and Terry, MS, were printed. Revision of Baton Rouge, Jackson, Helena, Greenwood, and Shreveport, scale 1:250,000 is in progress. Natchez, Fort Smith, and McAlester, scale 1:250,000 were printed. Floods Streamflow observations during the fiscal year follow: Memphis District-Mississippi River crest stage of 49.2 feet at Cairo gage on March 4-7, 1985, and maximum discharge of 1,195,000 cubic feet per second, occurred on March 5, 1985, at Hickman, KY and crest stage of 32.9 feet at Memphis on March 12, 1985, with maximum discharge of 1,281,000 cubic feet per second on March 5, 1985. Vicksburg District-There was no significant flooding in the Vicksburg District during FY 85. Peak stages and discharges on the Vicksburg District's reach of the Mississippi River were as follows: Arkansas City-36.9 feet on Mar. 15, 1985, and maximum discharge of 1,450,000 cubic feet per second; Vicksburg-42.2 feet on Mar. 18-19, 1985, and maximum discharge of 1,430,000 cubic feet per second; and Natchez-49.2 feet on Mar. 19-22, 1985, and maximum discharge of 1,360,000 cubic feet per second. New Orleans District-On the Mississippi River, the Red River Landing gage recorded a maximum stage of 53.15 feet NGVD on Mar. 20, 1985, and the New Orleans gage recorded a maximum stage of 16.24 feet NGVD on Mar. 20, 1985. On the Atchafalaya River, the Simmesport gage recorded a maximum stage of 36.03 feet NGVD on Mar. 21, 1985. Studies and Investigations General investigations. Surveys and reports, authorized by laws and by Senate and House Public Works 42-3 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Committee resolutions, were made as required. Collection and study of basic data continued. Actions taken on various requests for modifications of the existing project, Mississippi River and Tributaries, authorized by the Flood Control Act of May 15, 1928, as amended (see Table 42-D), follow: West Memphis, AR Feasibility Report-The MRC Report dated May 5, 1983, contained recommendations for 23.86 miles of channel improvement on Ten and Fifteen Mile Bayous, restrictive easements and a limited revegetation program and to provide a 10-year degree of protection in urban and rural areas. The total estimated cost of this recommended improvement is $21,300,000 (Oct. 85). Helena, AR and Vicinity Feasibility Report-The MRC Report dated Dec. 16, 1982, contained recom-. mendations for a 225 cfs pumping station, 1.85 miles of channel enlargement to contain a 10 year storm and 7' x 7' gated culvert at Long Lake. The total estimated cost of this improvement is $14,100,000 (Oct. 85). Yazoo Backwater Project, Mississippi, Mitigation Report. The Chief of Engineers Report dated July 12, 1984, recommended the acquisition of perpetual landuse easements on 11,300 acres of woodlands, or any combination of easements and fee title that would provide the same level of mitigation for fish and wildlife losses associated with the Yazoo Area Pump Project. The total estimated cost of this acquisition is $4,993,000 (Oct. 84). Mississippi and Louisiana Estuarine Areas, Louisiana and Mississippi Feasibility Report-The MRC Report, dated Jan. 10, 1985, contained recommendations for a diversion structure through the mainline Mississippi River levee adjacent to the Bonnet Carre Spillway; inflow and outflow channels; a sediment trap; and levee modifications necessary to accommodate the diversion structure. Total estimated cost of the recommended improvement is $58,200,000. Engineering studies. A research program was continued for development of materials and more effective and economical design of regulation features for placing and stabilizing the Mississippi River in a suitable alinement. Potamology investigations of river behavior continue to be made. Investigations into the major cause-andeffect relationships attributable to major changes in stage-discharge relationships on the Mississippi River as a result of both natural and man-made modifications are continuing. Mississippi River and Tributaries-Levees Operations and results during fiscal year. This feature consists of construction of new, and enlargement of existing, levees to approved grade and section; construction and restoration of levee berms; and construction, repair, and maintenance of roads on levees. Work accomplished is summarized in Table 42-N and further broken down as follows: New Orleans District-Enlarged 17.5 miles of levees and surfaced 6.7 miles of roads on levees in the Main Stem System. See Table 42-K. Vicksburg District-Constructed 0.0 mile of berms, and enlarged 0.0 miles of levees in the Main Stem System. See Table 42-L. Memphis District-Constructed 5.6 miles of seepage control measures in the Main Stem System. See Table 42-M. Condition as of Sep. 30. (See Tables 42-K, 42-L, 42- M, and 42-N.) There are 1,608.3 miles of levees authorized for the Mississippi River below Cape Girardeau, of which 1,601.5 arein place with 1,173.8 built to approved grade and section. The Main Stem Levee System consists of 2,202.1 miles, of which 2,195.3 are in place with 1,588.8 miles completed to approved grade and section. Included in this system are additional levees and structures along the south bank of Arkansas River (85.4 miles); along the south bank of Red River (59.2 miles, with 59.2 completed); and 449.2 miles in the Atchafalaya River Basin, with 449.2 in place with 270.5 completed to grade and section (see Table 42-N). Of the authorized 723 miles of berms, 493.4 are complete. Graveled or hard-surfaced roads have been constructed on 1,790.2 miles of these levees. There are an additional 1,608.2 miles of authorized levees off the main stem, of which 1,110.9 are in place with 814.3 to approved grade and section. Berms have been completed on 9.8 miles and 800.7 miles of graveled or hard-surfaced roads have been constructed on the levees. For last summary of levee work accomplished under Sec. 6, 1928 Flood Control Act, see Table 42-N, pages 42-50, Annual Report for 1975. Mississippi River and Tributaries- Channel Improvements Operations and results during fiscal year. Dredging: Mississippi River Main Stem-(See Table 42-G). Work included dredging 36,275,459 cubic yards for maintenance of channel and harbor improvements. Minimum channel depth of 9 feet was maintained. Dredging was done with the following plant: New Orleans District, Baton Rouge Harbor (Devil's Swamp) was maintained by Unit Price dredge BTD51. Vicksburg District, channel maintenance was performed by Louis James and leased Dustpan dredge Lenel Bean, government-owned Dustpan dredge Jadwin and leased cutterhead dredge George D. Williams. The MR&T Harbors maintained were Greenville and Vicksburg. Memphis District channel maintenance dredging was performed by Governmentowned dustpan dredges, Burgess & Potter, leased cutterhead dredge, Natchez, and leased dustpan dredge, Lenel Bean. The MR&T Harbor maintained was Memphis Harbor (MCKeller Lake). Bank revetment and dikes: (See Table 42-H, 42-I, 42-4 MISSISSIPPI RIVER COMMISSION and 42-J.) Construction of 11.01 miles of new bank revetment and 155,583 squares of concrete mattress, for maintenance, along the Mississippi River was completed by Government plant and hired labor. Also, 1.51 miles of new dikes were constructed and 0 squares were placed for maintenance. In addition, work on tributaries consisted of 1.20 miles of new bank revetment and 19,646 squares of concrete mattress for maintenance. Other work performed in the interest of navigation, supplementing maintenance dredging on Mississippi River between Cairo, IL, and Baton Rouge, LA, included removal of snags, wrecks, and obstructions; issuance of bulletins by the Vicksburg District providing information on available high-water velocities at selected locations; maintenance of bulletin boards showing daily gage readings at regular MRC gages; and contact pilot service furnishing navigation interests with latest information and advice on channel conditions and navigation interests. Cost of this work is given in Table 42-R. Condition as of Sep. 30. In carrying out authorized channel improvement program between Baton Rouge and Cairo, 16 cutoffs were developed between 1933 and 1942. These, combined with chute channel development and alignment improvements, decreased channel length between these cities by about 170 miles. However, current velocities increased the attack on the banks and the river began to regain its length. As a result, the net shortening between 1933 and 1962 was 114 miles of the theoretical 170-mile cutoff. There are now in place 851.69 miles of operative bank revetment and 212.22 miles of dikes on the lower Mississippi River. This amount of channel stabilization should prevent the river from regaining much more of its length due to meandering. A navigation channel 9-by 300-feet is being accomplished by revetment and dikes and maintained by dredging as required during the low-water season. Due to growing effectiveness of channel improvement program, average maintenance dredging requirements are steadily being reduced, and an increase in navigable depth is being obtained. Approximately 99.8 miles of foreshore protection have been constructed along the lower Mississippi River. There are 67.65 miles of revetment and 5.2 miles of dikes on tributary channels as listed in Tables 42-H, 42-I, and 42-J. New Orleans District ATCHAFALAYA BASIN, LA Operations and results during fiscal year. New work by hired labor: Real estate activities and planning for construction were continued. New work by contract: Construction of floodside and landside berms and levee enlargement continued intermittently on the east and west protection levees, although there was considerable delay during the year due to exceptionally high water flooding the borrow pits. Four contracts on the east protection levee, three initiated in prior years and one initiated this period, were completed over a distance of 8.1 miles with placement of 291,580 cubic yards. An additional 10.6 miles of levee enlargement and floodside and landside berms are under construction on the west protection levee involving placement of 1,520,499 cubic yards during this period and 3.6 miles of levee enlargement and floodside and landside berms on the east protection levee with placement of 1,097,401 cubic yards. Contract for 5.2 miles of steel sheet piling in the east protection levee, initiated this period, is 51 percent complete. Contract for the new Tiger Island floodwall, initiated in a prior year, was completed Dec. 31, 1984. Contract for the new Morgan City floodwall, south of Brashear Avenue, initiated in a prior year, was completed Aug. 16, 1985. Contract for the new Morgan City floodwall, north of Brashear Avenue, initiated last fiscal year, is 76 percent complete. A contract for the Berwick floodwall initiated in a prior year was completed Jul. 16, 1985. Two additional contracts for 4.6 miles of floodwall, initiated this period, are under construction on the east protection levee. Maintenance by hired labor: Operation and maintenance of Bayou Boeuf, Berwick, and Bayou Sorrell Locks, Morganza Control Structure, and numerous drainage structures as required, condition and operation studies, and water control management. Maintenance by contract: Contract for Goodwood levee setback, West Atchafalaya River levee, initiated last fiscal year, was completed Nov. 5, 1984. Maintenance dredging was performed, resulting in the removal of 1,398,561 cubic yards by one leased cutterhead dredge from Berwick Bay harbor between Jun. 5 and Aug. 22, 1985. Condition as of Sep. 30. Construction was initiated Aug. 7, 1929, with commencement of the west protection levee from Bordelonville to Hamburg, LA. The project is 70 percent complete, based on the current estimated Federal cost of $1,433,000,000 and non- Federal cost of $11,000,000. Of the 449.2 miles of levees and floodwalls authorized for the Atchafalaya system, 270.5 miles are built to grade. See Table 42-K for status of levees. Major items remaining to be completed include completion of levees to grade and section, training works in the lower basin, engargement of Wax Lake Outlet, and construction of two freshwater distribution structures. Drainage improvements in Upper Pointe Coupee Loop area have not been initiated. Approximately 36.7 miles of bank stabilization have been placed as shown in Table 42-H. BATON ROUGE HARBOR (DEVILS SWAMP), LA Operations and results during fiscal year. Maintenance by contract: Dredging for the removal of shoal 42-5 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 from the entrance channel was performed, resulting in the removal of 196,525 cubic yards between Aug. 1 and 13, 1985. Condition as of Sep. 30. Construction of the first 2.5 miles of the proposed 5.0 miles of channel was initiated in January 1958 and completed in July 1959, with 7,458,086 cubic yards excavated. The project is 16 percent complete, based on the current estimated Federal cost of $699,200 and cash contributions of $650,000. Completion of the remaining 2.5 miles is dependent on economic justification by developments on the initial channel. BAYOU COCODRIE AND TRIBUTARIES, LA Operations and results during fiscal year. Maintenance by hired labor consisted of water control management. Condition as of Sep. 30. Construction was initiated in June 1946 and is 57 percent complete, based on the current estimated Federal cost of $26,500,000 and non- Federal cost of $323,000. See page 2031, Annual Report for 1961, for description of completed work. Work required to complete the project consists of enlargement of 13.5 miles of upper Bayou Boeuf, channel improvement of 25.3 miles of Bayou Cocodrie, enlargement of Bayou Courtableau from Washington, LA, to the west protection levee, and additional culverts through the west protection levee at 100 percent Federal cost in lieu of the previously authorized diversion channel from Washington to the Bayou Courtableau drainage structure. BONNET CARRIL SPILLWAY, LA Operations and results during fiscal year. Maintenance by hired labor: Condition and operation studies, water control management, and ordinary maintenance of the control structure and spillway continued. Condition as of Sep. 30. Construction of the spillway was initiated in Fiscal Year 1929. The control structure was completed in 1931, levees were completed in 1932, and utility crossings were completed in 1936. The cost of the completed work is $14,212,200. It was necessary to operate the structure to reduce flood stages in 1937, 1945, 1950, 1973, 1975, 1979, and 1983. OLD RIVER, LA Operations and results during fiscal year. New work by hired labor consisted of engineering studies. New work by contract: Old River Control Auxiliary Structure, Phase II construction initiated in a prior year, is 89 percent complete. Maintenance by hired labor consisted of operation and maintenance of the lock and control structures as required, condition and operation studies, water control management, maintenance of cleared areas, levee shaping, operation of a picket boat at the inflow channel to the low-sill control structure during high river stages, and engineering studies. Maintenance by contract: On Sep. 30, 1985, 10,000 cubic yards of shoal were dredged from the lock forebay. Contract for the overbank outlet riprap repairs, initiated Oct. 17, 1983, was completed Dec. 18, 1983. A contract for the overbank outlet gabion repairs was awarded Oct. 11, 1984, initiated Nov. 5, and completed Dec. 30, 1984. Condition as of Sep. 30. Construction began September 1955 and is 92 percent complete based on the current estimated Federal cost of $306,000,000. Principal items completed are as follows: Low-sill structure, June 1959; overbank structure, October 1959; levees and levee enlargements, October 1963; inflow and outflow channels for the low sill structure, February 1961; navigation lock completed December 1962 and opened to navigation March 1963, at which time Old River was closed to navigation with a rock and earthfill dam; highway approaches and bridge over the lock completed March 1965. Approximately 4.7 miles of bank protection have been constructed at the inflow and outflow channels. (See Table 42-H for details of bank protection.) Principal items remaining to complete the project consist of constructing additional bank protection works and completion of the Auxiliary Structure, including relocations, construction of inflow channel, and bank stabilization. TECHE VERMILION BASINS, LA (WATER SUPPLY) Operations and results during fiscal year. New work by hired labor consisted of scour repairs to the outlet channel of the Bayou Courtableau borrow pit control structure which were completed in June 1985. New work by contract: A contract for dredging the inlet channel, Teche Vermilion pumping station, initiated last fiscal year, was completed Dec. 20, 1983. Condition as of Sep. 30. Construction of the project was initiated in July 1976. The project was completed in December 1982. All repairs were completed in June 1985. The cost of the completed works is $34,650,000. Vicksburg District TENSAS BASIN, ARK AND LA Operations and results during fiscal year. (a) Boeuf and Tensas Rivers, and Bayou Macon, AR and LA. Planning and design were continued on 42-6 MISSISSIPPI RIVER COMMISSION project features. Contracts for the pumps and motors, Phase I recreational facilities, Connerly Bayou Dam, and Ditch Bayou Dam, slurry trench, and storage building are complete on the Lake Chicot Pumping Plant Project. The contract for the Lake Chicot Pumping Plant is under way. (b) Red River backwater area. Planning and design continued on project features. The channel improvement contract for Wild Cow Bayou and additional channel work contract for the Tensas-Cocodrie Pumping Plant have been completed. The gravity structure contract is complete, and the pumping plant contract was initiated in FY 83. Design and right-ofway acquisition are continuing for the remainder of the Tensas-Cocodrie levee enlargement. An 8A contract has been completed for construction of the 1.5-mile connecting channel and drainage structure at the Six Mile Bayou Project. A contract for Sicily Island Item 1A is complete. Item 1A includes 1.0 mile of levee and a water control structure (two 60" pipes). An 8A contract for construction of Item 1B was awarded on Aug. 16, 1985 and preparation of the Fool River Bayou Pumping Plant design document is being initiated. Work on the Below Red River Phase II GDM is under way. Condition as of Sep. 30. (a) Boeuf and Tensas Rivers, and Bayou Macon, AR and LA. Channel improvement has been accomplished on 741.7 miles of project streams, providing major drainage outlets for the tributary areas. Additionally, 61.0 miles of the Tensas River has been cleared and snagged. A Reevaluation report for the Tensas River Project, above mile 61.0, and the Mill Bayou-Bayou Vidal project has been completed and work on the Phase II GDM is under way. (b) Red River backwater area. Levees in Tensas- Cocodrie area are complete except for levee raising of which 17.9 miles has been completed. The work comprised 93.1 miles of new levee, excluding 2.1 miles of high ground where no levees are required, and 86.9 miles of gravel road on levees. Construction of 68.6 miles of levee, Larto Lake to Jonesville levee system, has been completed. A levee grade reevaluation study for all levee systems in the Red River Backwater area was completed in Mar. 1985. Based on results of that study, work is underway to complete enlargement of the Tensas-Cocodrie levee system. LOWER ARKANSAS BASIN, AR Condition as of Sep. 30. Arkansas River levees. A total of 56.2 miles of the 61.5 miles of north bank levees and all of the 85.4 miles of south bank levees have been completed to approved grade and section. These levees above mile 36.1 are protected by bank-protection works constructed as a feature of project for Arkansas River and tributaries, AR and OK. For present status of this work, see report of Little Rock District. Below mile 36.1, needed bank protection is constructed with project maintenance funds. YAZOO BASIN, MS Operations and results during fiscal year. (a) Yazoo City and Belzoni protection works. Hired labor forces continued operation and maintenance of levees, drainage facilities, and pumping plant. (b) Greenwood protection works. Hired labor forces continued operation and maintenance of pumping plant, levees, and drainage facilities. Two bank stabilization projects, Site 2, and Claiborne Ave., are included under the "not less than $250,000" authority in the Appropriations bill. Site 2 contract was awarded September 12, 1983, with a contract price of $582,850 and terminated in 1984 because of high water stages. A new contract for this work was awarded July 9, 1984, with a contract price of $432,782. The Claiborne Street contract was awarded July 2, 1984, at a contract cost of $620,965. (c) Main stem. Planning is under way to provide drainage structure and levee closure at Bee Lake. Construction is complete on the Wasp Lake drainage structure and levee closure. Bank stabilization of Sheley Bridge was completed. Channel maintenance. No clearing and snagging and herbicide willow control were exercised in the Yazoo Basin Main Stem in FY 84. However, there are plans to initiate random clearing and snagging and herbicide willow control in the Coldwater, Little Tallahatchie, Tallahatchie, and Yazoo Rivers in FY 85. (d) Big Sunflower River, etc. A contract was awarded on Item 55A, Steele Bayou Channel Improvement, Miles 51.6 to 63.0, on March 15, 1982, and was completed Dec. 1, 1984. Plans and specifications are being prepared for the next item which is scheduled foraward in December 1985. (e) Tributaries. Construction: (1) Levees. Levee work associated with the last item of work on Ascalmore-Tippo Project and also Panola-Quitman Levee Item C(R) was awarded in FY 83 and are still under construction. (2) Channels. Removal of a portion of the plug on Alligator-Catfish Bayou channel at the site of bridge relocations was accomplished. The Alligator-Catfish channel enlargement project is now complete except for removal of the remaining portion of the plug. Controls in Alligator-Catfish channel may be necessary prior to removal of the plug. A study is under way to evaluate these needs. Construction on the remaining channel work on the Ascalmore-Tippo Project is under way. (3) Bank Stabilization. A construction contract for Tillatoba Creek Phase II was completed in Dec. 84. The planning of the Pelucia Creek Levee Project, printed as Supplement B to the Greenwood Protection Works (GDM #1), is complete. Pelucia Creek, Item 1 contract was awarded Jun. 24, 1985. Channel maintenance was continued for Yalobusha, Little Tallahatchie, and Yocona Rivers; Cassidy, David, Burrell, and Bobo Bayous; and Ascalmore Creek, by 42-7 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 random clearing and snagging and herbicide willow control. (f) Enid Lake. (See Table 42-C.) The dam and appurtenant structures were maintained and operated. Rehabilitation of boat channels and snagging and clearing of tributary streams in the lake area continued. Maximum pool elevation in the lake was 250.90 feet NGVD on Aug. 23, 1985, when storage in the flood control pool was 271,500 acre-feet. Peak 24-hr. inflow was 10,700 cubic feet per second on Feb. 24, 1985. On Sep. 30, 1984, pool elevation was 243.80 feet NGVD and storage in the flood control pool was 182,100 acre-feet. (g) Grenada Lake. (See Table 42-C.) Construction of remaining public-use facilities has been deferred pending development of cost-sharing agreements with local interests for construction and non-Federal operation and maintenance, consistent with projects for which recreation facilities are being constructed under the provisions of the Federal Water Project Recreational Act of 1965 (Public Law 89-72), as amended. Maximum pool elevation in the lake was 207.53 feet NGVD on Aug. 27-29, 1985, when storage in the flood control pool was 322,600 acre-feet. Peak 24- hour inflow was 19,300 cubic feet per second on Feb. 12, 1985. On Sep. 30, 1985, the pool elevation was 206.9 feet NGVD and storage in the flood control pool was 307,800 acre-feet. Construction of a levee to provide protection to the community of Coffeeville from high Grenada Lake stages was begun in FY 82. In addition to the levee, other features of Coffeeville project include: three drainage structures through the levee; portable pumps; area rehabilitation; and raising of a town street. Construction of the levee and two of the drainage structures was completed in FY 82. The remaining feature of the Coffeeville project was completed in early FY 84. (h) Sardis Lake. (See Table 42-C.) The dam and appurtenant structures were maintained and operated. Clearing of tributary streams in the lake area continued. Maximum pool elevation in the lake was 258.6 feet NGVD on Aug. 11, 1985, when storage in the flood control pool was 567,900 acre-feet. Peak 24-hour inflow was 13,350 cubic feet per second on Feb. 26, 1985. On Sep. 30, 1985, the pool elevation was 250.8 feet NGVD and storage in the flood control pool was 354,800 acrefeet. An 8-mile reach of the Little Tallahatchie River from Sardis Dam to Highway 51 was clogged with sediment restricting releases from the lake. This reach has been dredged to restore the design capacity of the river. Six disposal sites were selected, located in upland hill areas to reduce the adverse impact on prime agricultural lands along the river and still be in compliance with environmental laws and regulations. Dredging was completed in August 1982. (i) Arkabutla Lake. (See Table 42-C.) The dam and appurtenant structures were maintained and operated. Clearing of tributary streams in the lake area was continued. Maximum pool elevation in the lake was 221.0 feet NGVD on Aug. 7-10, 1985, and storage in flood control pool was 135,200 acre-feet. Peak 24-hour inflow was 17,900 cubic feet per second on Feb. 24, 1985. On Sep. 30, 1985, the pool elevation was 217.7 feet NGVD, and storage in the flood control pool was 95,700 acre-feet. (j) Yazoo Basin backwater. The Yazoo Area backwater levees are complete, including the backwater levee from the Mississippi River levee to the west levee of the lower Auxiliary Channel, the Little Sunflower River drainage structure, and the connecting channel from the Steele Bayou drainage structure to the Big Sunflower River. A Phase I GDM was completed in FY 82 which addresses rural flooding from ponded runoff inside the backwater levee. A GDM for a pumping station of 17,500 cfs to reduce this ponding was approved Jul. 12, 1985. Construction of this item is pending approval by the Assistant Secretary of the Army. The Satartia area backwater levee is complete. Rocky Bayou area levee Item 1A was awarded in March 1985. Plans and specifications are being prepared for levee Item 1B with award scheduled for March 1986. Completed backwater levees will require raising to provide the degree of protection intended based on the project design flow line developed for the Mississippi River following the 1973 flood. Four Greentree Reservoirs are now complete. Two of the three remaining reservoirs will be constructed when funds are appropriated. One reservoir has been indefinitely delayed because of right-of-way problems. Project funds will not be available until FY 85. The supply contract for the pumps and motors for the four completed reservoirs was awarded in FY 1985. The project is 52 percent complete. Greentree Reservoir #8 Pump Station is under construction and is scheduled for completion in FY 86. (k) Upper Yazoo projects. The first seven items of work, approximately 54 miles of channel improvement has been completed. This work extends from Yazoo city to about 15 miles upstream of Belzoni, MS. About 1.6 miles of channel enlargement along the Belzoni Front was skipped until bank stabilization problems at this location were resolved. The next item of work, Item 2-B, consisting of the 1.6 miles of channel improvement and bank stabilization along the Belzoni Front that was previously skipped is now under construction. Planning is continuing on upstream channel and levee work. (1) Streambank erosion control. Construction of the following projects has been completed: Tillatoba and Hunter Creeks, Items 1 and 2; Hunter Creek lA; South Fork Tillatoba Creek, Items 5A and 5B; North Fork Tillatoba Creek, Items A and 3A; Batupan Bogue, Items 4A, 4A-1, and 4A-2; Perry Creek, Items 6A and 6B; Johnson Creek, Items 9A, 9B, and vegetative treatment, Item 12; Goodwin Creek, Items 8A, 8B, and 8C; and Hotopha Creek, Item 7. All construction under this feature is complete, and a final report was submitted to the Secretary of the Army Jan. 5, 1982. All work constructed has been turned over to the local sponsors for operation and 42-8 MISSISSIPPI RIVER COMMISSION maintenance except for the instrumented system on Goodwin Creek where the structures were retained for possible future studies. Condition as of Sep. 30. The first feature of Yazoo Basin project was started in 1936, and the total project is about 35 percent complete. A total of 47.9 miles of backwater levee has been completed to the interim grade. The ongoing Yazoo Basin Comprehensive Study will address other water resources problems and needs in the area to include urban and rural flood damage prevention, hydropower, and water supply. LOWER RED RIVER-SOUTH BANK RED RIVER LEVEES, LA Operations and results during fiscal year. New work by hired labor consisted of engineering studies. Maintenance by hired labor consisted of water control management and economic studies. Condition as of Sep. 30. Construction was initiated in FY29 and is 90 percent complete, based on the current estimated cost of $42,000,000. Of the 59.2 miles of levees authorized, 59.1 miles is complete. (See Table 42-L for status of levees and Table 42-I for status of revetments. Memphis District ST. FRANCIS BASIN, AR AND MO Operations and results during fiscal year. (a) Little River Drainage. Ditch 290 channel enlargement awarded May 31, 1984, completed Nov. 26, 1984. Ditch 19, Item 2, Parcel 3 awarded Feb. 27, 1984, completed Oct. 4, 1984. Alternation to Railroad Bridge Ditch 19, Item 2, awarded Jan. 17, 1983, completed Sep. 18, 1984. Castor River, Item 1 awarded Jul 26, 1982, completed Dec. 20, 1983. (b) Upper St. Francis River. Ditch 251 channel cleanout awarded Jul. 9, 1985, 27 percent complete. Upper Ditch 1 channel cleanout awarded Jun. 26, 1985, 39 percent complete. Ditch 81 channel cleanout awarded Jun. 28, 1985, 47 percent complete. Stateline Ditch channel cleanout awarded May 17, 1985, 7 percent complete. Drainage Ditch 17 Storage Building awarded May 6, 1985, 88 percent complete. Scour repair to Highway 90 awarded Jan. 8, 1985, completed Aug. 28, 1985. Scour repair to Mingo Ditch awarded Jul. 17, 1984, completed Jul. 11, 1985. Ditch 81, Bridge 9.04 awarded Jun. 27, 1984, completed Aug. 25, 1985. Highway 181, Ditch 29, bridge alterations awarded Jul. 12, 1985. Highway 18 alterations awarded Dec. 12, 1984, 35 percent complete. Upper Buffalo Creek Bridges 30.70 and 33.04 awarded Jul. 31, 1985, 1 percent complete. Upper Buffalo Creek Bridges 29.65 and 34.10 awarded Jul. 29, 1985, 21 percent complete. Upper Buffalo Creek Mile 26.30 and 28.27 awarded Sep. 26, 1984, completed Jun. 3, 1985. (c) Lower St. Francis River. Upper Buffalo Creek Alterations of Highways 77 and 119 awarded Aug. 29, 1983, 65 percent complete. Huxtable Access Road awarded Sep. 17, 1985. Helena Floodwall awarded Aug. 23, 1985. Blackfish Bayou Item 2 awarded Jun. 28, 1985, 7 percent complete. Ditches 9 and 10 awarded Jun. 13, 1985, 4 percent complete. Big Creek, Item 2 awarded Sep. 26, 1984, completed Sep. 10, 1985. Upper Buffalo Creek Bridge 19.62 awarded Jul. 25, 1985, completed May 13, 1985. Blackfish Bayou Item 2 Railroad Bridge awarded Aug. 10, 1984, 82 percent complete. Condition as of Sep. 30. (a) Little River Drainage. Project was initiated during 1938 and is 76 percent complete. (b) Upper and Lower St. Francis River and Tributaries. Project was initiated during 1937 and is 78 percent complete. WHITE RIVER BACKWATER LEVEES Operations and results during fiscal year. (a) Graham Burke cleaning and painting awarded Sep. 26, 1984, 91 percent complete. Condition as of Sep. 30. (a) Graham Burke Pumping Plant, awarded Sep. 17, 1982, and is 91 percent complete. LOWER WHITE RIVER Operations and results during fiscal year. (a) Augusta to Clarendon Levee. There were no contracts awarded or completed during the fiscal year. (b) Clarendon Levee. There were no contracts awarded or completed. Condition as of Sep. 30. (a) Augusta to Clarendon Levee. Project was initiated during 1946 and is 39 percent complete. (b) Clarendon Levee. Project was initiated during 1972 and is 36 percent complete. CACHE BASIN, AR Operations and results during fiscal year. No contracts awarded or completed during the fiscal year. Condition as of Sep. 30. Project was initiated during 1971 and is 4 percent complete. REELFOOT LAKE-LAKE NO. 9, TN AND KY Operations and results during fiscal year. No contracts awarded or completed during the fiscal year. Condition as of Sep. 30. Project was initiated during 1974 and is 89 percent complete. 42-9 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 WEST TENNESSEE TRIBUTARIES, TN Operations and results during fiscal year. (a) Obion River, TN. South Fork-Forked Deer River awarded Aug. 22, 1985. Scour repairs, Sandy Creek Sep. 21, 1984, completed Dec. 17, 1984. Obion River Channel Improvement awarded Aug. 29, 1984, 78 percent complete. Obion River Channel Improvement, Item 1, Parcel 3 awarded Aug. 30, 1982, completed May 1, 1985. Grays Creek Canal Streambank Protection awarded Jun. 26, 1985, completed Aug. 12, 1985. Mengelwood Channel Item 1, Parcel 4 on the main stem and Mengelwood Channel, Item 1, Parcel 3 on the main stem were completed Mar. 1, 1985. Obion Rivers channel improvement is 59 percent complete. (b) Forked Deer River, TN. Fowlkes Channel Item 1-1 on the South Fork was awarded Aug. 22, 1985. Forked Deer River channel improvement is 13 percent complete. Condition as of Sep. 30. West Tennessee Tributaries Project is 30 percent complete. Work resumed in Sep. 1985 after having a court injunction lifted in May 1985. WEST KENTUCKY TRIBUTARIES, KY Operations and results during fiscal year. No contract awarded or completed during fiscal year. Condition as of Sep. 30. Project was initiated during 1978 and is 4 percent complete. MISSISSIPPI RIVER LEVEES Operations and results during fiscal year. (a) L-10 AC Cairo awarded Sep. 27, 1985. Birds Point-New Mardid awarded Aug. 21, 1985, 98 percent complete. Seepage control-Parcel 3 Cairo Mound City Jun. 25, 1985, 8 percent complete. Highway 51 Cairo gravel awarded Mar. 25, 1985, completed Apr. 27, 1985. Madrid Bend L-899 awarded Sep. 28, 1984, completed Mar. 19, 1985. Seepage control RO5AC Parcel I Cairo, Mound City awarded Aug. 27, 1984, 83 percent complete. Caruthersville floodwall repairs awarded Mar. 27, 1984, completed Dec. 6, 1984. L-628 Rena Lara Coahoma awarded Sep. 30, 1985. Walnut Bend Seepage berm R-679 awarded Nov. 21, 1984, completed Jul. 22, 1984. Lambethville R-752 berm awarded May 30, 1984, completed Aug. 30, 1985. 42-10 MISSISSIPPI RIVER COMMISSION TABLE 42-A MISSISSIPPI RIVER IMPROVEMENTS Mileage Above Head of Passes Locality Improvement Remarks 0-9571 10-81 11-25 Dredging, revetment, and contraction work Main line levee, right bank Main line setback, left bank 38 45 59 75 44-91 81-96 91-104 96-279 101-234 127-129 235 279-287 287-303 303-314 306-572 437 437-721 490 537 646 605-666 672-993 722-725 721-734 Head of Passes, LA-Cairo, IL The Jump-New Orleans, LA Baptiste Collette-Bayou Ostrica, LA Homeplace, LA Bohemia, LA Myrtle Grove, LA Caernarvon (Scarsdale), LA Bohemia, LA-New Orleans, LA New Orleans, LA New Orleans, LA New Orleans-Morganza, LA New Orleans-Baton Rouge, LA Bonnet Carr4 Floodway, LA Baton Rouge Harbor Morganza Floodway, LA Morganza-Old River, LA Old River, LA control Old River-Cypress Creek, AR Vicksburg Harbor, MS Vicksburg-Lake View, MS Wilson Point, LA Greenville Harbor, MS Long Lake, Helena, AR Henrico-Helena, AR St. Francis River-Commerce, MO3 Industrial levee (Ensley Bottoms) Memphis Harbor, TN 42-11 Salinity control structure, right bank Salinity control structure, left bank Salinity control structure, right bank Salinity control structure, left bank Main line levee and floodwall, left bank Main line levee, right bank Main line levee and floodwall, left bank Main line levee, right bank Main line levee and floodwall, left bank Regulating spillway, left bank Devils Swamp barge channel Regulating spillway, right bank Main line levee, right bank Levee closure and enlargement, low and high water spillway structures, navigation lock, and approach channels, right bank Main line levee, right bank Harbor extension and industrial fill Main line levee, left bank Pumping Plant and drainage structure, right bank Harbor improvements and port area Culvert and floodgate, right bank Main line levee and floodwall, right bank Main line levee, right bank Levee and pumping station Closure of Tennessee Chute, industrial fill, levee, harbor channels, etc. Authorized by Public Law 89-298 (HD 308/74/1). Included in MS Delta Region, LA feature. Authorized by Public Law 89-298 (HD 308/74/1). Included in MS Delta Region, LA feature. Authorized by Public Law 89-298 (HD 308/74/1). Included in MS Delta Region, LA feature. Authorized by Public Law 89-298 (HD 308/74/1). Included in MS Delta Region, LA feature. Authorized by Public Law 81-516. Authorized by Public Law 81-516. Modified by Public Law 87-874. Extends up south bank of Old River to Barbre Landing. Authorized by Public Law 83-780. Joins Arkansas River, south bank levee. Authorized by Public Law 70-391. Modified by Public Laws 79-526 and 83-780. Unpublished Vicksburg District's MRC report approved Apr. 14, 1966.2 Authorized by Public Law 85-500. Authorized by Public Law 79-526.2 Authorized by Public Law 79-526. REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 42-A MISSISSIPPI RIVER IMPROVEMENTS (Continued) Mileage Above Head of Passes 803-873 T 857 Main exte Riv( Pum char 890 St. Johns Bayou, MO Draii clos 890 New Madrid Floodway, MO Draii clos 890-954 New Madrid-Birds Point, MO Floo 902-922 Slough Bend, Hickman, KY Main 922 Hickman, KY Floo 946 Peafield, MO Drai] 9571 Cairo, Cairo drainage district Floo 9571 Cairo, Cairo drainage district, Floo Mounds, Mound City, and play vicinity Thebes-Rock Island, IL Levee Cape Girardeau, MO to Rock Leve Island, IL 1. Cairo, IL, is on Ohio River about 3 miles above its mouth (Mississippi River mile 954 AHP). 2. Also see Table 42-D, "Authorizing Legislation." Improvement line levee, left bank, levee nsion, and diversion Obion er ping station and adjacent nnel improvements nage floodgate and levee ure nage floodgate and levee ure dway, right bank line levee, left bank dwall, left bank nage floodgate dwalls and levees dwalls, levees, and pumping nt es, both banks es Remarks Modified by Acts of Jul. 24, 1946 and Dec. 23, 1971. Authorized Dec. 15 and 17, 1970 under Sec. 201 of Oct. 27, 1965 FC Act. Modified by Jul. 24, 1946 Act. Modified by Sep. 3, 1954 Act. Authorized by Sep. 3, 1954 Act. Intermittent (Sec. 6). Intermittent (Sec. 6). 3. Commerce, MO, is on Upper Mississippi River, 39 miles above mouth of Ohio River. 42-12 Locality 'iptonville-Obion River Near Mud Lake, TN MISSISSIPPI RIVER COMMISSION TABLE 42-B MISSISSIPPI RIVER TRIBUTARY AND OUTLET IMPROVEMENTS Mileage Below Head of Atchafalaya River Locality Improvement Remarks 0-54 27-54 54-117 20-27 25-117 27 0-27 31-57 80 53-117 117 117-129 117-129 105 105-120 115 116 5 5-105 29 29 40 40 40 Floodway Floodway Floodway ATCHAFALAYA BASIN, LA' Atchafalaya Basin. Morganza and West Atchafalaya Floodways West Atchafalaya Floodway between Red River and Alabama Bayou Morganza Floodway between Mississippi River and Alabama Bayou Atchafalaya Basin Floodway between Alabama Bayou and Morgan City East protection levee (Morganza and Atchafalaya Floodways) Lacour-Red Cross Morganza-Morgan City Bayou Latenache Upper Pointe Coupee Loop area Bayou Fordoche-Ramah Bayou Sorrell Bayou Sorrel Lock-Morgan City Morgan City Below Morgan City Below Morgan City Atchafalaya Basin Floodway lower protection levee Calumet Below Morgan City Berwick' Patterson West protection levee (Atchafalaya Basin and West Atchafalaya Floodways) Simmesport-Hamburg Mansura to Wax Lake Outlet Coulee des Grues West Atchafalaya Floodway Morganza Floodway Bayou Darbonne West Atchafalaya Floodway Morganza Floodway Including lower Morganza Floodway guide levee. Through upper Morganza guide levee and enlargement of outlet channel. Enlargement of Bayou Latenache. Approved Jun. 4, 1970. See Table 42-D. Levee landside borrow pit. Alternate route, Gulf Intracoastal Waterway . Port Allen to Morgan City. Gulf Intracoastal Waterway utilizes levee west side borrow pit channel. Gulf Intracoastal Waterway. Bypass route for Gulf Intracoastal Waterway. East of lower river. Bayou Teche-Wax Lake Outlet. Inclosed area between Wax Lake Outlet and Berwick. Lower Atchafalaya River. Adjustment to provide fresh water. West Atchafalaya Floodway. Through West Atchafalaya protection levee. 42-13 Levee, upper Morganza guide Levee and Morgan City floodwall Drainage structure, Pointe Coupee, and channel enlargement Additional drainage facilities Drainage channel Lock Alternate navigation channel, Gulf Intracoastal Waterway Lock in Bayou Boeuf 1 Channel relocation Levee, floodwall Floodgate, east Levees, floodwall, drainage structures, and pumping plants Lock Water system Levee fuse plug Protection levee Levee enlargement and floodgate extension Railway Railway Gated drainage structures Highway Highway TABLE 42-B (Continued) REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 MISSISSIPPI RIVER TRIBUTARY AND OUTLET IMPROVEMENTS Mileage Below Head of Atchafalaya River Locality Improvement Remarks 41 41 41 94 94 105 105 0-54 5-6 5-66 28-30 40-41 54-117 94-106 Mileage Above Mouth 0-8 50-133 96 133 0-17 17-40 40-51 51-60 17-42 87-107 40 60 Bayou Courtableau West Atchafalaya Floodway Morganiza Floodway Charenton Jaws-Lake Fausse Pointe Calumet Wax Lake Outlet Atchafalaya River Barbre Landing-Alabama Bayou Simmesport Simmesport-Bayou Garofier Melville Krotz Springs Below Alabama Bayou Mississippi River-Morgan City TECHE-VERMILION BASINS, LA Atchafalaya River to Teche- Vermilion Basins Courtableau Basin, LA, and outlets Charenton Canal West Atchafalaya protection levee borrow pit channel Bayou Courtableau spillway Bayou des Glaises BAYOU COCODRIE AND TRIBUTARIES Bayou Courtableau Bayou Cocodrie Bayous Cocodrie-Bouef diversion Bayou Boeuf Bayous Boeuf-Rapides diversion Upper Cocodrie Bayou Boeuf Bayou Lamourie to Kincaid Structures Lecompte Control Structure Bayou Rapides Control Structure Gated drainage control structures and channels Railway Railway Floodgate and approach channels Outlet, Charenton drainage canal and protection levee. Floodgate, west Drainage canal-railway and highway bridges East bank, levee Levee, ring, and drainage structure West bank, levee Levee, ring Levee, ring Channel enlargement 12- by 125-foot navigation channel Pumping station above Krotz Springs, conveyance channels, and appurtenant works Drainage channel Drainage channel Drainage control structure Diversion channel Enlargement and additional culverts Enlargement and realinement New channel New channel New channel Enlargement, clearing, and snagging Enlargement, realinement, clearing and snagging Fixed elevation weir Gated drainage structure 42-14 Borrow pit channel to Grand Lake through West Atchafalaya protection levee. Restoration of drainage west of West Atchafalaya Basin protection levee. Bayou Teche and Wax Lake Outlet. To lower flood heights. Increase channel capacities to decrease flood heights. Through Grand and Six Mile Lakes. Freshwater distribution from Atchafalaya River to Teche-Vermilion Basins. Outlet to gulf. Intercepting drainage channel. Washington to west protection levee. MISSISSIPPI RIVER COMMISSION MISSISSIPPI RIVER TRIBUTARY AND OUTLET IMPROVEMENTS Mileage Below Head of Atchafalaya River Locality Improvement Remarks 87 Bayou Lamourie Control Gated drainage structure n , , 82-145 3-56 3-56 5 56 0-32 0-56 151-235 210-286 286-296 0-75 Structure Various LAKE PONTCHARTRAIN, LA Lake Pontchartrain, Jefferson Parish, LA AMITE RIVER, LA Amite River, LA LOWER RED RIVER, SOUTH BANK, RED RIVER LEVEES, LA Moncla-Hotwells Red River-Moncla to Lake Long EASTERN RAPIDES AND SOUTH-CENTRAL AVOYELLES PARISHES, LA Eastern Rapides and southcentral Avoyelles Parishes, LA TENSAS BASIN, AR AND LA Red River backwater area Tensas-Cocodrie area Larto Lake-Jonesville Sicily Island area Below Red River area Black River, LA Six Mile Bayou area Jonesville, LA Ouachita River Boeuf and Tensas Rivers and Bayou Macon, AR, and LA Boeuf River, AR, and LA Below Bayou La Fourche Bayou LaFourche Boeuf River, AR, and LA above Bayou LaFourche Canal 19 Canal 19 extension Big and Colewa Creeks Railway, highway, and local road bridges, and pipeline crossing Flood protection Bank protection Levee, south bank Levees Flood protection and drainage improvement Levees, drainage channels, structures, and pumping plant Levees, drainage channels, and structures Levees, drainage channels, and structures Levees, drainage channels, and structures Drainage structure and appurtenant channel works Levees, floodwall, pumping plant, and interior drainage Levees, drainage channels, and structures Clearing Channel improvement and realinement Channel improvement Channel improvement Channel improvement Channel improvements (2, 3) Authorized by Public Law 81-516. Eliminated by Public Law 89-298. Intermittent (Sec. 6). Authorized by Public Law 91-611. (4) (4) (4) (4) Unpublished VXD-MRC Letter Report dated May 31, 1977. MR&T authority. 2 Portion of levee built under Sec. 6. Incorporated in MR&T by Public Law 81-516.2 Monroe to Sandy Bayou and Bawcomville (Sec. 6). (5) (5) Authorized by Public Laws 78-534 and 79-526.2 3 (5) (6) Authorized by Public Law 78-534.3 42-15 TABLE 42-B (Continued) TABLE 42-B (Continued) REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 MISSISSIPPI RIVER TRIBUTARY AND OUTLET IMPROVEMENTS Mileage Below Head of Atchafalaya River Locality Improvement Remarks 0-8 0-7 0-33 0-10 0-9 0-14 0-170 0-34 0-35 Lake Chicot 0-6 0-160 0-16 0-0.2 Channel improvement Channel improvement Channel improvement Channel improvement Channel improvement Channel improvement Channel improvement Channel improvement Channel improvement To divert flows from Lake Chicot Tributaries of Boeuf River- Canal 19 Fleschmans Bayou Caney Bayou Big Bayou Canal 18 Kirsch Lake Canal Black Pond Slough Bayou Macon, AR, and LA Bayou Macon Canal 43 Canal 81 Pumping plant and drainage structure Tributary of Bayou Macon Rush Bayou Tensas River, AR and LA Tensas River Tributary of Tensas River Mill and Vidal Bayous Grant's Canal, LA Grant's Canal at Lake Providence LOWER ARKANSAS RIVER, AR Yancopin-Pine Bluff Fletcher Bend, AR to Pine Bluff North Little Rock to Gillett (below Plum Bayou) GRAND PRAIRIE-BAYOU METO, AR Grand Prairie Region and Bayou Meto Basin, AR YAZOO BASIN, MS Yazoo Backwater area Yazoo River System below Arkabutla Lake Yazoo River between Yazoo City and Prichard Yazoo River between Yazoo City and Askew Will M. Whittington Auxiliary Channel Yazoo City protection Rocky Bayou area Belzoni protection Greenwood protection Arkabutla Lake Channel improvement Channel improvement Filling canal (6) (6) (6) (6) (6) (6) See Table 42-E (5) (5) Authorized by Public Law 90-483. (6) Authorized by Public Law 78-534. 3 Authorized by Public Law 89-298. Authorized by Public Law 81-516. Levee, south bank Revetment Levee, north bank (5) Water supply and drainage improvements Levees and pumping plants Channel improvement Levees, right bank Levees, left bank Floodway channel Levee, drainage structure, and pumping plant Channel clearing and enlargement Levee and floodwall Levees, channel improvement, drainage structures, and pumping plants Flood detention and conservation Authorized by Public Law 81-516. Including Tallahatchie and Coldwater Rivers. Intermittent. Intermittent. Improvement of 7.8 miles was approved Apr. 29, 1970. See Table 42-C. 42-16 Clearing 23-98 35-98 48-102 0-75 0-381 75-366 75-345 45-109 75 127 185 381 TABLE 42-B (Continued) MISSISSIPPI RIVER COMMISSION MISSISSIPPI RIVER TRIBUTARY AND OUTLET IMPROVEMENTS Mileage Below Head of Atchafalaya River 0-64 64 0-24 0-26 26 0-13 13 0-88 137-260 75-381 0-8.3 0-23 0-42 275-290 0-204 0-8 0-28 0-81 0-43 0-4 0-27 153-160 0-68 13-55 0-68 99 Locality Yalobusha River below Grenada Lake Grenada Lake Tallahatchie River-Little Tallahatchie River Little Tallahatchie River below Sardis Lake Sardis Lake Yocona River below Enid Lake Enid Lake Cassidy Bayou below Old Coldwater River Upper Yazoo Projects Area between main stem and hills including Bobo Bayou McKinney Bayou Alligator-Catfish Bayous Bear Creek Whiteoak Bayou Tallahatchie River, MS Big Sunflower River, etc. Big Sunflower River Hull Brake-Mill Creek Canal Hushpuckena River Quiver River Gin and Muddy Bayous, MS Bogue Phalia Ditchlow Bayou Little Sunflower River Deer Creek Steele Bayou Muddy Bayou LOWER WHITE RIVER AND BASIN, AR Laconia Circle-Old Town Lake Big Creek and tributaries Clarendon levee 42-17 Improvement Channel improvement Flood detention and conservation Levees, Panola-Quitman Floodway Channel improvement Flood detention and conservation Channel improvement Flood detention and conservation Channel improvement Floodway channel Levees and channel improvement Channel improvement and enlargement of pumping plant Channel improvement Channel improvement Channel improvement Two road crossings of Panola- Quitman Floodway, MS and for protection of Sheley Bridge Channel improvement Channel improvement Channel improvement Channel improvement Channel improvement Channel improvement Channel improvement Channel improvement Channel improvement Channel improvement Water-control structure Levee, backwater including outlet Pumping plant Channel improvement and structures Levee and outlet structures Remarks See Table 42-C. See Table 42-C. See Table 42-C. Including Moores Bayou, Cutoff Bayou, Whiting Lake and outlet. Authorized by Public Law 79-526. Authorized by Public Law 79-526. Authorized by Public Law 89-298. As modified in GDM in 1967. Authorized by Public Law 89-298. Authorized by Public Law 89-298. Authorized by Public Law 90-147. Authorized by Public Law 78-534.3 Authorized by Public Law 87-874. Authorized by Public Law 78-534.3 Authorized by Public Law 78-534.3 Authorized by Public Law 78-534.3 Authorized by Public Law 78-534.s Authorized by Public Law 78-534.3 Modified in December 1970. See Table 42-D. Approved Mar. 3, 1970. See Table 42-D. Mile 605-645 Mississippi River. (6) Authorized by Public Law 89-298. Authorized by Public Law 89-298. TABLE 42-B (Continued) REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 MISSISSIPPI RIVER TRIBUTARY AND OUTLET IMPROVEMENTS Mileage Below Head of Atchafalaya River Locality Improvement Remarks Augusta to Clarendon De Valls Bluff 143 0-196 0-90 260 0-225 225 0-105 86 0-36 0-29 0-17 0-12 0-108 0-25 0-20 0-15 108-192 122 (5) (5) Des Arc, AR CACHE BASIN, AR Cache River, AR Bayou DeView, AR ST. FRANCIS RIVER AND BASIN, AR, AND MO Inter-River Drainage District in Missouri Mouth of St. Francis River- Wappapello Dam Wappapello Lake Little River Basin Marked Tree, AR Tyronza River Big Slough Ditch Mayo Ditch Cross County Ditch Belle Fountain Ditch Drainage District No. 17 L'ANGUILLE RIVER, AR L'Anguille River and tributaries, Brushy and First Creeks WEST TENNESSEE TRIBUTARIES Wolf River and tributaries, TN Obion River and tributaries, North, South, Middle, and Rutherford Forks Forked Deer River and tributaries, North, Middle, and South Forks Mud Lake Pumping Station, TN Harris Fork Creek, TN and KY Porter Gap, TN REELFOOT LAKE-LAKE NO. 9, TN AND KY Running Reelfoot Bayou, TN Bayou du Chien and Lake No. 9, KY and TN 42-18 Levees, outlet structures Levee, outlet structure, and pumping station Levee, outlet structure, and pumping station Channel improvement and structures Channel improvement and structures Channel improvement and two outlet structures Floodway, levees, drainage channels, and structures Flood detention and conservation Floodway, levees, drainage channels, and structures Marked Tree Siphon Channel improvement Channel improvement Channel improvement Channel improvement Channel improvement Channel improvement and pumping station Channel improvement Channel improvement Channel improvement Channel improvement Pumping plant Flood control improvements Construction to main-stem standards, levee and appurtanent structures for flood control Channel improvement Channel improvements and pumping station Authorized by Public Law 81-516. Authorized by Public Law 81-516. Authorized by Public Law 81-516. Authorized Dec. 16, 1975. See Table 42-D. See Table 42-C. Authorized by Public Law 90-483. Authorized by Public Law 90-483. Authorized by Public Law 80-858. (6) Authorized by 1948 Flood Control Act. Authorized by 1948 Flood Control Act. Authorized by Resolutions Dec. 15 and 17, 1970.2 Authorized by Water Resources Act of Oct. 22, 1976.2 Section 102, 1976.2 Section 183, 1976.2 Authorized by Public Law 83-780. Authorized in December 1970, See Table 42-D. MISSISSIPPI RIVER COMMISSION TABLE 42-B (Continued) MISSISSIPPI RIVER TRIBUTARY AND OUTLET IMPROVEMENTS Mileage Below Head of Atchafalaya River Locality Improvement Remarks WEST KENTUCKY TRIBUTARIES, KY 0-47 Obion Creek, KY Channel improvement Authorized by Public Law 89-298. LITTLE RIVER DIVERSION CHANNEL, MO Delta to Ancell, MO Levees Mile 49 above Cairo. MISSOURI RIVER, MO 0-28 Mouth to St. Charles, MO Levees Intermittent (Sec. 6). ILLINOIS RIVER, IL 0-120 Mouth to Havana, IL Levees Intermittent (Sec. 6). OHIO RIVER, IL AND KY Cairo to Mound City and Mounds, Floodwall, levee, revetment, and IL pumping plant 1. General data concerning Bayou Boeuf, Bayou Sorrel, and Berwick locks where Atchafalaya Basin protection levees cross Gulf Intracoastal Waterway, alternate route to Plaquemine, LA and lower Atchafalaya River (extension of Bayou Teche Waterway), respectively, are in report of New Orleans district. 2. Also see Table 42-D, "Authorizing Legislation." 3. Public Law 81-516 modified requirements of local cooperation. 4. Authorized by Public Law 77-228. Modified by Public Law 89-298. 5. Authorized or incorporated in MR&T by Public Law 79-526. 3 See Table 42-D. 6. Authorized by Public Law 85-500. 42-19 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 42-C MISSISSIPPI RIVER TRIBUTARY DAMS AND LAKES Grenada Enid Sardis Arkabutla Wappapeilo Name' Lake Lake Lake Lake Lake River Yalobusha Yocona Little Tallahatchie Coldwater St. Francis Nearest town to damsite Grenada Enid Sardis Arkabutla Wappapello Drainage area, square miles 1,320 560 1,545 1,000 1,310 Conservation pool: Area, thousand acres 10 6 11 5 4 Volume, thousand acre-feet 86 58 108 31 31 Elevation, feet, NGVD 193 230 236.0 209.3 354.7 Flood control pool: Area, thousand acres 65 28 58.5 33 23 Volume, thousand acre-feet 1,252 602 1,462 494 582 Runoff, inches 17.8 20.2 17.7 9.3 8.4 Outlet gates: Number 3 2 4 3 3 Size, feet 7.5by 14 8 by 16 6 by 12 8.5 by 19 10 by 20 Capacity, thousand cubic feet per second 10.7 9.4 10.0 10.0 18.0 Spillway: Type, uncontrolled Chute Chute Chute Chute Gravity Length, feet 200 200 400 300 740 Elevation, crest, feet, NGVD 231 268 281.4 238.3 394.7 Discharge capacity, thousand cubic feet per second 52 50 132 89 229 Surcharge pool: Area, thousand acres 106 41 90 63 32 Volume, thousand acre-feet 1,385 554 1,447 858 521 Runoff, inches 19.7 18.5 17.6 16.1 7.5 Elevation, feet, NGVD 247.5 284.0 301.0 256.3 413.7 Dam: Type, earthfill Rolled Rolled Hydraulic Rolled Rolled Length, thousand feet 13.9 8.4 15.3 11.5 2.7 Elevation, crest, feet, NGVD 256.0 293.0 311.4 264.3 419.7 1. Grenada, Enid, Sardis and Arkabutla Lakes are in Yazoo River Basin, MS; Wappapello Lake is in St. Francis River Basin, MO. 42-20 TABLE 42-D MISSISSIPPI RIVER COMMISSION AUTHORIZING LEGISLATION Act or Authorization Work Authorized Document May 15, 1928 Jun. 19, 1930 Feb. 15, 1933 Apr. 23, 1934 Aug. 30, 1935 Jun. 15, 1936 Aug. 28, 1937 Jun. 28, 1938 Aug. 18, 1941 Dec. 22, 1944 Jul. 24, 1946 Flood protection in alluvial valley of Mississippi River, revetment and contraction works and dredging to provide least channel depth of 9 feet and width of 300 feet below Cairo. Provided for allotment of the balance of emergency rescue funds to reimburse levee districts and others for expenditures in floodcontrol works during the 1927 and subsequent floods. Provided for ownership of lands in Bonnet Carr6 Spillway and Floodway with proviso for granting rights-of-way, easements, and permits, in said lands Authorized payment for purchase of, or to reimburse states and local levee districts for the cost of, levee rights-of-way for flood control work in the Mississippi Valley, and for other purposes. Improvement of Wolf and Nonconnah Rivers, TN (Nonconnah Creek is correct title) Improvement of Wolf River (Memphis Harbor), TN Modification of the 1928 Act to provide for: Construction of a backwater levee at mouth of White River, AR Construction of Eudora floodway in lieu of Boeuf floodway; flood control, Yazoo River; construction of Morganza floodway; and an outlet to the Gulf of Mexico west of Berwick, LA, including a 6-year program for the improvement and regularization of the Mississippi River between Arkansas and Red Rivers, and Atchafalaya River; and construction of roads on levees and drainage adjustments incident to floodway levees. Provided for construction of floodwalls, levees, and revetments along Wolf River and Nonconnah Creek for protection of Memphis, TN Modify the Yazoo River project to substitute a combined reservoir floodway and levee plan. Construction of Mounds to Mound City levee and control works along Cache River, IL Modification of previous act pertaining to floodways and outlets and lands therein; including program for the improvement and regularization of the Mississippi River, between Cairo and Arkansas River, extension of levee road system; strengthening of levees. Enlarge main line levees to offset abandonment of floodways between Arkansas and Red Rivers, flood control works in backwater areas of Yazoo and Red Rivers, and in Bayous Rapides, Boeuf, and Cocodrie, LA Navigation channel 12 feet deep and 300 feet wide between Baton Rouge and Cairo; flood protection of Yazoo River Backwater Area in vicinity of Satartia, MS Continue prosecution of channel improvement and stabilization program, $200 million. Flood control on the Big Sunflower, Little Sunflower, Hushpuckena, and Quiver Rivers and their tributaries, and on Hull Brake-Mill Creek Canal, Bogue Phalia, Ditchlow Bayou, Deer Creek, and Steele Bayou, MS' Improve Boeuf and Tensas Rivers and Bayou Macon, AR' Improve Bayou Lafourche, LA Improve Yazoo River tributaries. North bank, Arkansas River levees (below Plum Bayou).' 42-21 H. Doc. 90, 70th Cong., 1st sess. Public 395, 71st Cong., 2d sess. Public 351, 72d Cong. Public 171, 73d Cong. R&H Comm. Doc. 26, 72d Cong., 1st sess. R&H Comm. Doc. 45, 74th Cong., 1st sess. Unpublished report dated Apr. 2, 1925. H. Comm. on Flood Control, Doc. 1, 74th Cong., 1st sess. Unpublished report on record in OCE. H. Comm. on Flood Control, Doc. 1, 75th Cong., 1st sess. H. Comm. on Flood Control, Doc. 1, 75th Cong., 1st sess. H. Doc. 359, 77th Cong., 1st sess. H. Doc. 509, 78th Cong., 2d sess. Public Law 534, 78th Cong., 2d sess. H. Doc. 516, 78th Cong., 2d sess. S. Doc. 151, 78th Cong., 2d sess. S. Doc. 191, 79th Cong., 2d sess. H. Doc. 516, 78th Cong., 2d sess. H. Doc. 308, 74th Cong., 1st sess. TABLE 42-D (Continued) REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 AUTHORIZING LEGISLATION Act or Authorization Work Authorized Levees on White River (Augusta to Clarendon).' Bayou des Glaises diversion channel, LA' Modify local cooperation requirements in St. Francis and Yazoo Basins. Tiptonville-Obion levee and drainage improvements.1 Improvement of St. Johns Bayou, MO Big Sunflower River, etc.1 Tennessee Chute (Memphis Harbor), TN Continue prosecution of project for flood control and channel improvement, $100 million. Improve Mississippi River below Cape Girardeau, MO with respect to West Tennessee tributaries. Improve L'Anguille River, AR Baton Rouge Harbor (Devils Swamp), LA' Flood protection at Des Arc, AR Improve St. Francis River and Basin, AR and MO Improve Cache River and Bayou DeView, AR and MO Improve Grand Prairie Region and Bayou Meto Basin, AR Flood protection, Lake Pontchartrain, Jefferson Parish, LA' Filling Grant's Canal, Lake Providence, LA Additional protection to Red River Backwater Area. Extend Federal jurisdiction to cover levees in Orleans Parish, LA Bank protection, Amite River, LA Continue prosecution of project for flood control and channel improvement, $200 million. Jonesville, LA levee, retaining wall, and drainage structure.' Modify requirements for local cooperation in White River Backwater Area, AR Navigation improvement of Atchafalaya from Mississippi River to Morgan City, LA Modify project for Vicksburg-Yazoo Area (Harbor), MS Improve New Madrid Floodway, MO, including Peafield drainage floodgate. Control of Old and Atchafalaya Rivers and a lock for navigation. Improve Reelfoot Lake area, KY and TN Improve Greenville Harbor, MS 42-22 Jun. 30, 1948 May 17, 1950 Oct. 30, 1951 Sep. 3, 1954 Jul. 3, 1958 Document H. Doc. 98, 76th Cong., 1st sess. H. Doc. 602, 79th Cong., 2d sess. Public Law 526, 79th Cong., 2d sess. H. Doc. 757, 79th Cong., 2d sess. H. Doc. 138, 80th Cong., 1st sess. H. Doc. 516, 78th Cong., 2d sess. S. Doc. 51, 80th Cong., 1st sess. Public Law 526, 79th Cong., 2d sess. H. Doc. 627, 80th Cong., 2d sess. H. Doc. 651, 80th Cong., 2d sess. H. Doc. 321, 80th Cong., 1st sess. H. Doc. 485, 81st Cong., 2d sess. H. Doc. 132, 81st Cong., 1st sess. S. Doc. 88, 81st Cong., 1st sess. H. Doc. 255, 81st Cong., 1st sess. S. Doc. 139, 81st Cong., 2d sess. Public Law 516, 81st Cong., 2d sess. Public Law 516, 81st Cong., 2d sess. Public Law 516, 81st Cong., 2d sess. Public Law 516, 81st Cong., 2d sess. Public Law 516, 81st Cong., 2d sess. S. Doc. 117, 81st Cong., 1st sess. Public Law 237, 82d Cong., 1st sess. S. Doc. 53, 82d Cong., 1st sess. H. Doc. 85, 83d Cong., 1st sess. H. Doc. 183, 83d Cong., 1st sess. H. Doc. 478, 83d Cong., 2d sess. S. Doc. 160, 83d Cong., 2d sess. S. Doc. 15, 86th Cong., 1st sess. TABLE 42-D (Continued) MISSISSIPPI RIVER COMMISSION AUTHORIZING LEGISLATION Act or Authorization Work Authorized Document Jul. 14, 1960 Oct. 23, 1962 Jun. 18, 1965 Oct. 27, 1965 Apr. 14, 19662 Nov. 7, 1966 Nov. 20, 1967 Aug. 13, 1968 Sep. 10, 19683 Mar. 3, 19703 Extensions to project for Boeuf and Tensas Rivers and Bayou Macon in Arkansas. White River backwater area pumping plant. Wolf River and tributaries for flood protection in Tennessee. Continue prosecution of project for channel improvement-$50 million. Modification-Baton Rouge Harbor (Devils Swamp), LA Construct improvements in Gin and Muddy Bayous, Yazoo River Basin, MS Replace 2 bridges with adequate floodway over Boeuf River and Big Bayou in Boeuf Basin, AR Continue prosecution of project for flood control and channel improvement, $53 million. Modify and expand levees and channel improvement features of main stem project. Modify flood control improvements in following tributary areas and basins: Cairo-Mounds-Mounds City, St. Francis, Lower White, Boeuf-Tensas-Macon, Red River backwater, Yazoo headwater, Grand Prairie, and Bayou Meto. Acquire any modified easements required in New Madrid Floodway as provided by Sec. 4 of May 15, 1928 act. Operate and maintain pumping plant in Red River backwater area (Tensas-Cocodrie Pumping Plant). Provide improvements in West Kentucky tributaries. Provide fish and wildlife facilities in St. Francis and Big Sunflower Basins; Yazoo Headwater and Backwater Areas; and Mississippi Delta region. Deauthorize Amite River, LA project. Modify St. Francis River, MO and AR, project within District No. 7, Poinsett County, AR Provide pumping plant and drainage structure at Wilson Point, LA Construction of improvements to supplement freshwater supply in Teche-Vermilion Basins in Louisiana. Bank revetment for protection of existing industrial facilities along Mississippi River below Baton Rouge, LA Modification of West Tennessee tributaries feature to provide relocation of gas transmission lines at Federal expense. Continue emergency work, $87,135,000, which includes $100,000 for road crossing of Panola-Quitman Floodway, MS, and $80,000 for protection of Sheley Bridge, Tallahatchie River, MS Improvements in Boeuf and Tensas Rivers and Bayou Macon Basin to divert flows that would otherwise enter Lake Chicot, AR Improvements in the Belle Fountain ditch and tributaries, MO, and Drainage District No. 17, AR Provide pumping plants and other drainage facilities in Cairo, IL, and vicinity. Modification of Yazoo Headwater Project to include cleanout along David Bayou, MS Modify Yazoo Backwater feature to include a control structure in Muddy Bayou, MS 42-23 H. Doc. 108, 85th Cong., 1st sess. S. Doc. 26, 85th Cong., 1st sess. H. Doc. 76, 85th Cong., 1st sess. Public Law 86-645. Public Law 87-874. Public Law 87-874. Public Law 87-874. Public Law 89-42. H. Doc. 308, 88th Cong., 2d sess. H. Doc. 308, 88th Cong., 2d sess. H. Doc. 308, 88th Cong., 2d sess. H. Doc. 308, 88th Cong., 2d sess. H. Doc. 308, 88th Cong., 2d sess. H. Doc. 308, 88th Cong., 2d sess. H. Doc. 308, 88th Cong., 2d sess. S. Doc. 57, 89th Cong., 1st sess. Unpublished Vicksburg District's MRC report Approved-Apr. 14, 1966. H. Doc. 524, 89th Cong., 2d sess. Public Law 89-789. Public Law 89-789. Public Law 90-147. H. Doc. 168, 90th Cong., 1st sess. H. Doc. 339, 90th Cong., 2d sess. Public Law 90-483. Unpublished MRC report dated May 8, 1968. Unpublished MRC report dated Feb. 2, 1970. REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 42-D (Continued) AUTHORIZING LEGISLATION Act or Authorization Work Authorized Document Apr. 29, 19703 Jun. 4, 19703 Dec. 31, 1970 Senate and House Public Works Resolutions adopted Dec. 17 and 15, 1970, respectively. 4 River Basin Monetary Act of Dec. 23, 1971 Jan. 19, 19732 TITLE I Water Resources Development Act of 1974. Modification of Yazoo Headwater Project to include drainage structure and channel improvement on Rocky Bayou, MS Provide for enlargement of Bayou Latenache from Pointe Coupee drainage structure to Alabama Bayou, LA Modify and expand project to include flood protection within the area of eastern Rapides and south-central Avoyelles Parishes, LA, that are drained by Bayou des Glaises diversion channel and Lake Long, and their tributaries. Modify the project for West Kentucky tributaries (Obion Creek), KY, to provide for all relocations, at Federal expense, of all transmission lines required by the project. Report on Western Tennessee Tributaries, TN and KY, authorized: a. Modification of Reelfoot Lake feature to provide channel improvements on Bayou du Chien and Lake No. 9 in KY and TN b. Modification of Mississippi levee feature to include a pumping station near Mud Lake floodgate and adjacent channel improvements. Modification of Big Sunflower Basin feature to provide additional improvements in Steele Bayou Basin, MS Continue prosecution of project for the comprehensive development of the basin, $97 million. Modification of Tiptonville-Obion River levee feature to relieve local interests of all responsibility except that of providing maintenance. Modification of the Mississippi levee feature to provide additional drainage facilities in Long Lake area, vicinity of Helena, AR Projects recommended by four completed reports were authorized for accomplishment of Phase I design memorandum of advance engineering and design on: a. Greenville Harbor, Greenville, MS b. East bank of Mississippi River, Warren to Wilkinson Counties, MS (Natchez area). c. East bank of Mississippi River, Warren to Wilkinson Counties, MS (Vicksburg-Yazoo area). d. Bushley Bayou Area of Red River Backwater Area, LA Modification of West Tennessee tributaries feature (Obion and Forked Deer Rivers), TN, to acquire lands for fish and wildlife, recreation, and environmental purposes. Modification of the Yazoo Basin, MS, feature to provide for a streambank erosion control demonstration project for the delta and hill areas of basin. Modification of project to provide that the Secretary of the Army, acting through the Chief of Engineers, can substitute authorized mitigation lands, not yet acquired and no longer suitable, for like acreage in the same or adjacent subbasins of the project area. This section provides the authority to substitute authorized mitigation lands in: a. Tensas Basin, LA and AR, feature (Red River backwater). b. St. Francis Basin, AR and MO, feature. Modification of Bayou Cocodrie and tributaries, LA, feature, to provide for: enlargement of Bayou Courtableau from ashington to west protection levee; right-of-way and spoil disposal areas at Federal expense; and necessary additional culverts through west protection levee. Unpublished MRC report dated Mar. 6, 1970. Unpublished MRC report dated Sep. 22, 1969. S. Doc. 91-113, 2d sess. Public Law 91-611. H. Doc. 91-414, 2d sess. S. Doc. 91-74, 2d sess. Sec. 1, Public Law 92-222. Sec. 7, Public Law 92-222. Unpublished Memphis District's MRC report dated Oct. 4, 1972. Sec. 1, Public Law 93-251. Mar. 7, 1974. S. Doc. 93-38, 1st sess. H. Doc. 93-148, 1st sess. H. Doc. 93-148, 1st sess. H. Doc. 93-157, 1st sess. Sec. 3, Public Law 93-251. Sec. 32, Public Law 93-251. Sec. 42, Public Law 93-251. Sec. 87, Public Law 93-251. 42-24 TABLE 42-D (Continued) MISSISSIPPI RIVER COMMISSION AUTHORIZING LEGISLATION Act or Authorization Work Authorized Document TITLE II River Basin Monetary Authorization Act of 1974 River Basin Monetary Act of Oct. 2, 1975 Dec. 16, 19752 TITLE II Public Works for Water and Power Development and Energy Research Appropriation Act 1976. TITLE II Public Works for Water and Power Development and Energy Research Appropriation Act, 1977. Water Resources Development Act of 1976. TITLE II Public Works for Water and Power Development and Energy Research Appropriation Act, 1978. Modification of Cache River Basin, AR, feature to provide for: acquisition by fee easements of lands for fish and wildlife management, recreation, and environmental purposes. Continue prosecution of project for the comprehensive development of the basin, $211 million. Continue prosecution of project for the comprehensive development of the basin, $158,000,000. Modification of St. Francis Basin, AR and MO, feature to provide relief from ponding of interior runoff in the Inter-River Drainage District of Missouri. Continue prosecution of project for comprehensive development during period Jul. 1 - Sep. 30, 1976, $60,300,000. Continue prosecution of project for flood control, rescue work, repair, restoration, and control of bank erosion, $231,497,000. Sec. 101(a) authorized accomplishment of Phase I - Advanced Engineering and Design Memoranda - On: a. St. Johns Bayou and New Madrid Floodway, MO, project: Report of OCE - Sep. 26, 1975. b. Nonconnah Creek, TN and MS, project: Report of OCE - Jun. 23, 1976, and as an independent part of the project: Improvements for flood control and allied purposes on Horn Lake Creek and tributaries, including Cowpen Creek, TN and MS. Modification of West Tennessee Tributaries feature (Obion and Forked Deer Rivers), TN, to: a. (Sec. 102)- Provide project for flood control for Harris Fork Creek, TN and KY: (H.D. 94-221) except that highway bridge relocations and alterations shall be at Federal expense. b. (Sec. 183) - Provide for construction of a levee and appurtenant works from mouth of Obion diversion channel to vicinity Highway 88 and thence to vicinity of Porter Gap, TN Continue prosecution of project for flood control, rescue work, repair, restoration, and control of bank erosion, $253,081,000. Sec. 99, Public Law 93-251. Sec. 201, Public Law 93-251. Mar. 7, 1974. Sec. 1, Public Law 94-101. Unpublished Memphis District's MRC report dated Nov. 11, 1975. Public Law 94-180, Dec. 26, 1975. Public Law 94-355, Jul. 12, 1976. Public Law 94-587, Oct. 22, 1976. Public Law 95-96 Aug. 7, 1977. 42-25 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 42-D (Continued) AUTHORIZING LEGISLATION Act or Authorization Work Authorized Document Dec. 9, 1977, 5th Modification of the Tensas Basin Project, Red River Backwater Unpublished Vicksburg Ind. on VXD Area, to include a drainage structure and appurtenant channel District report dated May May 31, 1977, works in the Six Mile Bayou area of Concordia Parish, LA 31, 1977, on Cynthia and Letter Report.2 Six Mile Bayous, LA Jun. 28, 1980 The establishment of the Tensas River National Wildlife Refuge Public Law 96-285, Jun. 28, for the preservation and development of environmental 1980. resources and in lieu of mitigation acquisitions which otherwise would be required for certain water resources projects, within designated limits, in the basins of the Tensas, Boeuf, and Red Rivers in the State of Louisiana. Energy and For expenses necessary for prosecuting work of flood control Public Law 96-367, Oct. 1, Water projects, rescue work, repair, restoration or maintenance of 1980. Development flood control projects threatened or destroyed by flood, Appropriation $232,519,000: Provided, That not less than $250,000 be available Act, 1981 for control of bank erosion of streams in the Yazoo Basin, including the foothill area. Provided further, That funds for the Tensas Basin Red River Backwater Area, be used for flood control, etc. for Sicily Island and Below Red River including pumping stations. Supplemental Authorizes and directs the Secretary of the Army acting through FY 1985 Supplemental Appropriations the Chief of Engineers to proceed with planning, design, Appropriations Bill (PL Bill for FY engineering and construction of 41 water resources projects, 99-88) Ending Sep. including Atchafalaya Basin Floodway System. The bill 30, 1985 (PL provides that the funds appropriated shall lapse on Jun. 30, 1986 99-88) unless formal cost-sharing agreements have been reached with the local sponsor. For the Atchafalaya Basin Floodway Systems project, cost-sharing will be as recommended in the Report of the Chief of Engineers, Feb. 28, 1983. 1. Incorporated into Mississippi River and tributaries project as shown in Table 42-E. 2. Date minor modification for blocked drainage was approved under delegated authority of the President, Mississippi River Commission, and in accordance with Sec. 10(p) of the 1946 Flood Control Act (Public Law 79-526). 3. Date minor modification was approved under discretionary authority of Chief of Engineers contained in May 15, 1928, Flood Control Act, as amended. 4. Projects approved under the provisions of Sec. 201 of Flood Control Act of Oct. 27, 1965. 42-26 MISSISSIPPI RIVER COMMISSION TABLE 42-E INCORPORATING AND AUTHORIZING LEGISLATION For Last Public Full Report Act of Law Authorizing See Annual Incorporation No. Act Description Report for Jul. 24, 1946 79-526 Jun. 22, 1936 Tiptonville-Obion levee and drainage 1941, p. 943 improvements, TN Jul. 24, 1946 79-526 Jun. 22, 1936 Bayou des Glaises diversion ditch, LA 1946, p. 1029 Jul. 24, 1946 79-256 Jun. 22, 1936 From North Little Rock, AR, to Gillett, AR, on 1946, p. 1053 north bank of Arkansas River (portion below Plum Bayou). Jul. 24, 1946 79-256 Aug. 18, 1941 White River levees, Augusta to Clarendon and De 1946, p. 1083 Valls Bluff, AR Jul. 24, 1946 79-526 Dec. 22, 1944 Boeuf and Tensas Rivers and Bayou Macon, LA 1945, p. 982 Jul. 24, 1946 79-526 Dec. 22, 1944 Big Sunflower River, etc. 1946, p. 1061 Jun. 30, 1948 80-858 Jul. 24, 1946 Devils Swamp barge channel at Baton Rouge, LA 1948, p.1059 (Baton Rouge Harbor) May 17, 1950 81-516 Jun. 22, 1936 Jonesville, LA 1953, p.773 May 17, 1950 81-516 Jul. 24, 1946 Lake Pontchartrain-Jefferson Parish, LA 1953, p. 737 42-27 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 42-F SUMMARY OF PRESENTLY ESTIMATED FEDERAL FIRST COST OF AUTHORIZED IMPROVEMENTS Project Title Estimated Cost1 Fiscal Year 1985 Completed features 2 Mississippi River levees Mud Lake Pumping Station, TN Sec. 6 levees, 1928 Flood Control Act Channel improvement Atchafalaya Basin, LA Bayou Cocodrie and tributaries, LA Old River, LA Lower Red River- South Bank Red River levees, LA Eastern Rapides and South-Central Avoyelles Parishes, LA Mississippi Delta Region, LA Teche-Vermilion Basins, LA Tensas Basin, AR and LA Lower Arkansas River, AR Grand Prairie-Bayou Meto, AR Yazoo Basin, MS Lower White River, AR Cache Basin, AR St. Francis Basin, AR and MO L'Anguille Basin, AR West Tennessee Tributaries, TN Harris Fork Creek, TN & KY Reelfoot Lake-Lake No. 9, TN & KY Reelfoot Lake, TN & KY (Completed) Reelfoot Lake-Lake No. 9, TN & KY West Kentucky Tributaries, KY Tensas River National Wildlife Refuge Atchafalaya Basin Floodway System, LA Eight Mile Creek, AR Sardis Dam (Dam Safety Assurance) TOTAL $ 165,432,000 1,229,000,000 4,470,000 4,000,000 3,010,000,000 1,433,000,000 26,500,000 306,000,000 28,700,000 62,300,000 35,700,000 35,700,000 470,000,000 35,000,000 130,900,000 1,405,000,000 54,800,000 157,000,000 361,000,000 26,400,000 104,000,000 21,500,000 (10,400,000) 440,000 9,960,000 23,800,000 40,000,000 194,000,000 19,300,000 9,000,000 $ 9,402,902,000 1. Inflation projected through the construction period. 2. Includes Bonnet Carr&, Morganza, and New Madrid Floodways; Memphis, Greenville, and Vicksburg Harbors; Lake Pontchartrain; Wolf River; completed roads on main stem levees; channel construction works; Atchafalaya River and Basin; Wax Lake Outlet; Charenton Canal; Bayou des Glaises diversion channel, Boeuf Basin levees; Grant's Canal; De Valls Bluff, Jonesville, and Des Arc protection works; Baton Rouge Harbor; and miscellaneous features. 42-28 - TABLE 42-G MISSISSIPPI RIVER COMMISSION MISSISSIPPI RIVER MAIN STEM CHANNEL IMPROVEMENTS Operations in 1,000 Cubic Yards Location Fiscal Year 1985 Mileage Above Head Channel District of Passes Construction Maintenance Total New Orleans Baton Rouge Harbor (Devils Swamp) 235 - 216.1 216.1 Main stem channel 234-320 - 0.0 0.0 Vicksburg Main stem channel 320-600 - 1,192.6 1,192.6 Vicksburg Harbor 437 - 380.9 380.9 Greenville Harbor 537 - 755.3 755.3 Memphis Main stem channel 600-954 - 30,416.8 30,416.8 Memphis Harbor 726 - 3,313.7 3,313.7 TOTAL - 36,275.4 36,275.4 42-29 TABLE 42-H BANK REVETMENTS AND DIKES: NEW ORLEANS DISTRICT (FISCAL YEAR 1985) Operations This FY Construction Nonop- Operaerative tive Above New Work Reinforcement Since Thru Head Bank Exten- Prior This Location of R sion Lap Mainte- FY FY Passes or (Linear (Linear (Linear nance (Linear (Linear (Miles) L Feet) Feet) (Squares)' Feet) (Squares)' (Squares)' Feet) Feet) MISSISSIPPI RIVER Standard revetment: Venice, LA .................. 12 Lower Childress- Fort Jackson, LA ............ 22 Buras, LA ................... 25 Tropical Bend, LA ........... 30 Bayou Lamoque, LA .......... 33 Port Sulphur, LA ............ 39 Point Michel, LA ............ 44 Bohemia, LA ................ 46 Diamond, LA ................ 49 Gravolet, LA ................ 51 Junior, LA .................. 54 Harlem, LA ................. 56 Myrtle Grove, LA ............ 59 Monsecour, LA .............. 61 Alliance, LA ................ 62 Belair, LA .................. 65 Jesuit Bend, LA ............. 68 Linwood, LA ................ 71 Oak Point, LA ............... 72 Scarsdale, LA ............... 75 English Turn, LA ............ 78 Poydras, LA ................. 82 Cutoff, LA .................. 88 Third district reach, LA ....... 93 Algiers Point, LA ............ 95 Gouldsboro Bend, LA ......... 96 Gretna Bend, LA ............ 97 Greenville Bend, LA ......... 100 Carrollton Bend, LA ......... 104 Avondale Bend, LA .......... 109 Kenner, LA ................. 114 Luling, LA .................. 119 Good Hope, LA .............. 126 Waterford, LA .............. 128 Montz, LA .................. 132 Lucy, LA .................... 136 Reserve, LA ................. 138 Willow Bend, LA ............ 141 Angelina, LA ................ 145 Vacherie, LA ................ 148 Belmont, LA ................ 152 R RRRL RRL RL RL RL RLRL RL RL RL RRRRLRLRLRL RL RL RL 2,254 9,757 4,090 1,775 1,546 1,513 1,050 2,773 406 17,623 508 49,405 264 28,415 52 8,213 156 5,024 52 6,627 83 6,219 32 11,484 - - 404 1,702 2,230 9,864 - - - - - - 5,912 1,714 1,523 11,302 1,823 2,177 - !r 16,210 15,430 y 17,283 0 25,012 t 7,264 36,995 21,932 12,380 178,,473550 . 19,345 15,148 15,925 10,020 9,750 22,841 22,860 10,638 12,377 11,575 16,408 0 45,864 cn 21,256 27,167 7,728 4,960 9,662 - 22,045 0 15,015 C 22,371 32,404 28,908 16,298 12,295 17,502 17,826 20,947 7,618 19,000 13,295 24,785 Rich Bend, LA .............. 157 Romeville, LA ............... 161 St. Alice, LA ................ 165 Burnside, LA ................ 170 Aben, LA ................... 172 St. Elmo, LA ................ 174 Smoke Bend, LA ............. 177 Marchand, LA .............. 180 Philadelphia Point, LA ........ 183 New River Bend, LA .......... 185 White Castle, LA ............. 193 St. Gabriel, LA .............. 201 Plaquemine Bend, LA ........ 209 Manchac, LA ................ 215 Missouri Bend, LA ........... 222 Arlington, LA ............... 227 Port Allen, LA .............. 231 Allendale, LA ............... 238 Springfield Bend, LA ......... 244 Arboth, LA .................. 250 Grand Bay, LA .............. 258 Bayou Sara, LA ............. 265 Red Store, LA ............... 269 Arrow Bend, LA ............. 272 Boies Point, LA .............. 275 Morganza, LA ............... 279 Iowa Point, LA .............. 282 Brunette Point, LA ........... 285 Greenwood Bend, LA ......... 289 Hog Point, LA ............... 296 Carr Point, LA .............. 304 Above Old River, LA .......... 305 Fort Adams, MS ............. 308 Point Breeze, LA ............. 313 Coochie, LA ................. 317 Palmetto, MS ................ 322 Subtotal New Orleans District, Mississippi River ....... RLRLRL RL RL RL RL RL RRL RRL RL RRL RL RRRL RRL Dikes: None OLD RIVER CONTROL Standard revetment: Inflow channel .............. 315 L Inflow channel .............. 315 R Outflow channel ............. 315 R Total standard revetment, Old River ............... 6,291 - - 2,299 5,626 1,648 65 29,099 56 11,388 - - 200 36,866 370 10,890 4,695 648 3,376 920 302 9,096 12,792 27,408 21,625 27,052 20,279 10,063 10,240 17,075 10,144 5,379 30,020 33,333 26,809 36,137 35,480 22,632 12,244 14,073 17,940 25,690 13,190 7,090 - 16,958 11,315 13,600 16,094 4 20,513 11,375 8,038 - 14,987 < 13,368 8,600 4,800 17,219 11,165 17,150 30864 12,962 - 45,317 2,244 234,215 3,282 14,942 52,561 - 1,372,473 (8.58 Miles) (0.62 Miles) (259.94 Miles) - - - - - - - 2,415 - - - - - - - 4,365 2,137 78 6,280 - - - - 19,891 z 2,137 78 6,280 (0.40 Mile) 26,671 TABLE 42-H BANK REVETMENTS AND DIKES: NEW ORLEANS DISTRICT (Continued) (FISCAL YEAR 1985) Operations This FY Construction eNroantoivpe- Otpiverea- Above New Work Reinforcement Since Thru Head Bank Exten- Prior This Location of R sion Lap Mainte- FY FY Passes or (Linear (Linear (Linear nance (Linear (Linear (Miles) L Feet) Feet) (Squares)' Feet) (Squares)1 (Squares)' Feet) Feet) ATCHAFALAYA RIVER Below Confluence of Red and Atchafalaya Rivers Standard revetment: Mile One, LA ................ 1 Coville, Bayou, LA ............ 3 Legonier, LA ................ 4 Simmesport, LA ............. 6 Kuhlman Bayou, LA .......... 7 Odenburg, LA ............... 9 Cason, LA ................... 12 McCrea, LA ................. 13 Woodside, LA ............... 14 Provosty, LA ................ 17 Crooked Bayou, LA ........... 18 Mercier, LA ................. 22 Barberton, LA .............. 23 Evans Point, LA ............. 24 Goudeau, LA ................ 26 Morris Bayou, LA ............ 27 Goodwood, LA ............... 28 Red Cross, LA ............... 29 Melville, LA ................. 30 Cross Bayou, LA ............. 31 Melville South, LA ........... 33 Toles, LA ................... 35 Petite Prairie, LA ............ 36 Holloway Lake, LA ........... 37 Bayou Sherman, LA .......... 38 Krotz Springs, LA ........... 40 Sherburne, LA ............. 43 Bayou Big Graw, LA .......... 46 Morgan City ................ 115 Total standard revetment ... L RL RL RRL RL RLRL RL RL RL RLRLLRRRL 738 740 1,099 2,577 (0.49 Mile) 3,192 3,371 - - 12,186 799 4,794 4,953 11,516 17,779 O 0 4,150 6,550 8,940 10,636 55,,357655 10,798 O 5,027 13,002 97,,670608 10,478 3,592 4,898 3,938 3,800 Y 8,505 8,065 m 4,870 3,815 4,070 6,355 4 8,381 . 7,085 5,200 4,625 7,035 8,394 3,410 193,927 (36.73 Miles) Dikes: None II LOWER RED RIVER Below Confluence of Old River Outflow Channel and Red River Standard revetment: Long Lake, LA ............... Naples, LA .............. Turnbull Island, LA ........ Total standard revetment 10 79 RRL 4,223 4,223 (0.80 Mile) 140 19,903 140 19,903 - - 1,867 - - - 1,867 - Dikes: None 1. Gross squares articulated concrete mattress (100 square feet). 6,652 6,190 11,038 23,880 (4.52 Miles) CAD W C12 C7J C, C 0 TABLE 42-I BANK REVETMENTS AND DIKES: VICKSBURG DISTRICT (FISCAL YEAR 1985) Operations This FY Construction eNroantiovpe- Otpiveera- Above New Work Reinforcement Since Thru Head Bank Exten- Prior This Location of R sion Lap Mainte- FY FY Passes or (Linear (Linear (Linear nance (Linear (Linear (Miles) L Feet) Feet) (Squares)' Feet) (Squares)' (Squares)' Feet) Feet) MISSISSIPPI RIVER Standard revetment: Bougere Bend, LA ........... Dead Mans Bend, MS ........ Railroad Landing, MS ....... St. Catherine Bend, LA ...... Morville, LA ................ Natchez Island, MS .......... Carthage, MS ............... Natchez Front, MS .......... Gibson, LA .................. Ashland, LA-MS ............ Kempe Bend, LA ............ Browns Field, LA ........... Goldbottom, MS ............. Hardscrabble, LA ........... Grand Gulf, MS ............. Point Pleasant, MS-LA ....... Togo Island, LA ............. Lake Karnac, LA-MS ........ Diamond Point, LA-MS ....... Reid-Bedford, LA ........... Racetrack, MS .............. Barge Line Terminal, MS ..... Vicksburg Harbor, MS ....... Delta Point, LA .............. King's Point-Opposite Delta Point, LA-MS ........ False Point, LA .............. Marshall-Brown's Point, LA-M S ................... Milliken Bend, LA ........... Belle Island, LA-MS ......... Goodrich, LA ................ Cottonwood Bar, MS, TF ...... Fitler-Cottonwood, MS ........ Hagaman, LA ............... Ben Lomond, MS ............. Baleshed Towhead-Stack Island, LA-MS ............ Lake Providence, LA ........ Mayersville, MS ............. Sarah Island-Opossum Point, LA-M S ................... 329 335 346 350 356 357 361 364 371 374 383 389 392 398 403 413 415 419 423 429 433 437 437 437 439 443 446 453 460 467 470 474 481 486 488 489 497 503 RLL RRRLL RL RRL RL RRL RRLLLR LR LRL R RL RL RRL 910 2052 4,361 3,285 5,2851 2,2701 - 12,7061 25,1711 10,6201 2,761 9,917 - 20,805 0 18,280 11,595 1216,,841953 2,180 x 14,700 6,510 n 22,735 x 18,862 28,285 m 9,280 30,250 22,530 53,948 Z 3,345 0 5,670 19,260 m 12,125 M 18,392 13,935 - 3,040 7,350 7,650 19,330 12,860 19,580 44,650 24,160 37,220 7,500 28,427 37,756 10,235 7,500 R 915 - 3,266 52,1243 11,600 34,992 456 17,885 co Carolina, MS ................ Cracraft, AR ................ Worthington, MS-AR ........ Walnut Point Kentucky Bend, MS ................. American Cutoff, MS-AR ..... Sunnyside-Lakeport, AR ...... Vancluse, AR ................ Island 84, AR, MS ........... Warfield Point, MS .......... Leland-LaGrange, AR-MS .... Spanish Moss, AR ........... Tarpley Island, MS .......... Miller Bend, MS ............. Island 82, AR ................ Ashbrook Island, MS ........ Arkansas City-Yellow Bend, AR .................. Huntington Point, MS ....... Pair O'Dice, AR .............. Eutaw-Mounds, MS ......... Cypress Bend, AR ............ Catfish Point, MS ............. Ozark, AR-MS .............. Prentiss, AR-MS ............ Rosedale Bend, AR .......... Riverton, MS ................ Klondike, AR ................ Victoria Bend-Terrene, MS ... Big Island, AR .............. Smith Point, MS ............. Dennis, MS .................. Cessions, MS ................ Total revetment, Vicksburg District, Mississippi River ......... Dikes: Jackson Point, MS ............ Opposite Warnicott Ldg, MS Natchez Island, LA-MS ....... Waterproof Bar, LA ......... Spithead Towhead, MS ...... Browns Field, LA ............ Cottage Bend, LA-MS ........ Bondurant Towhead, LA ...... Coffee Point, LA ............. Yucatan, MS ................ Togo lsland, LA .............. Below Racetrack, MS ........ Racetrack Towhead, MS ...... Marshall Cutoff, LA .......... Forest Home Towhead, LA .... Willow Cutoff, LA ........... Arcadia Point, MS ........... Point Lookout, LA ........... 507 511 514 519 526 530 534 535 537 538 539 542 544 546 549 553 556 561 563 568 573 578 582 585 586 588 593 598 601 611 615 LRR L L RR LLLRRL R R RL RL RL RLLL RL RLLL 2,030 (0.38 Miles) 0 7,627 720- LLRRL RL RRRLLR RL RL R 2,259 11,080 22,210 8,350 45,653 2,980 33,685 4,300 13,475 4,320 14,150 4,580 2,000 29,360 3,080 3,455 40,560 10,045 9,095 40,188 26,585 20,075 22,015 20,315 4,820 12,500 23,400 29,245 16,515 18,185 25,195 10.910 3,007 2,963 2,796 11,560 50,756 21,900 0 1,308,680 (247.86 Miles) (4) 330 352 358 379 386 388 389 394 405 410 416 430 431 448 449 462 470 478 4,306 5,351 7,695 11,372 3,6615 4,8355 14,049 4,421 3,260 9,010 8,256 10,299 1,752 5,1665 4,609 4,574 3,900 2,751 c C2 0 z I 7 TABLE 42-I (Continued) BANK REVETMENTS AND DIKES: VICKSBURG DISTRICT (FISCAL YEAR 1985) Operations This FY Construction eNroantoivpe- Otpiveera- Above New Work Reinforcement Since Thru Head Bank Exten- Prior This Location of R sion Lap Mainte- FY FY Passes or (Linear (Linear (Linear nance (Linear (Linear (Miles) L Feet) Feet) (Squares)' Feet) (Squares)' (Squares)' Feet) Feet) MISSISSIPPI RIVER continued Dikes: Ajax Bar, MS ............... Ben Lomond, MS ............ Balshed Ldg., MS ............ Wilson Point, LA ............ Corregidor, MS .............. Carolina, AR ................ Cracraft Lower, AR ......... Cracraft, AR ................ Leota, M S ................... Island, 86, AR ............... Seven Oaks, AR ............. Walnut Point, MS ........... Refuge, MS ................. Island 84, AR ................. Leland Bar, AR-MS .......... Leland Neck, AR-MS ........ Tarpley Cutoff, MS-AR ....... Island 82-Miller Bend, AR-MS .................... Ashbrook-Miller Bend, AR-M S ............ ......... Ashbrook Cutoff, MS ........ Chicot Ldg., AR ............. Catfish Point, MS ............ Below Prentiss, MS .......... Malone Field, AR ............ Terrene, MS ................. White River Landing, AR ..... Montgomery Towhead, AR .... Victoria Bend, AR............ Smith Point, MS .............. Island 70, MS ................ Total dikes, Vicksburg District, Mississippi River ........ 482 488 493 500 505 509 510 513 514 520 523 525 528 532 538 540 540 544 547 549 564 571 580 585 590 591 592 596 600 608 LLL RLL RRL RRLLLRL R R&L L&R L RL RRL RR RLL 0 24,319 24,6675 8,238 3,592 6,730 2,897 9,614 73,,587019 56,,755942 O 4,725 5,278 4,580 15,928 4,315 10,318 13,646 500 - - - - - - - 13,015 - - - - - - - 8,728 - - - - - - - 17,451 - - - - - - - 5,290 - - - - - - - 7,813 - - - - - - - 7,549 - - - - - - - 7,921 - - - - - - - 2,201 - - - - - - - 6,071 - - - - - - - 5,0335 - - - - - - - 7,617 - - - - - - - 14,949 500 (0.09 Miles) cI: C01 375,144 (71.05 Miles) ARKANSAS RIVER6 Standard Revetment: Menard Bend, AR ........... Como, AR ................... Morgan Bend, AR ........... Yancopin, AR ............... Total standard revetment, Arkansas River .......... Dikes Hopedale Cutoff, AR ......... Morgan Bend, AR ........... Fletcher Bend, AR ........... Total dikes, Arkansas River ... LOWER RED RIVER Standard revetment: Long Lake, LA .............. Naples, LA .................. Turnbill Island, LA .......... Total standard revetment Dikes: None RED RIVER7 Standard revetment:8 Dupre, LA .................. Bringol, LA ................. Egg Bend, LA ............... Cologne Bend, LA ........... Roxana, LA ................. Ryland, LA .................. Whittington, LA ............. Smith, LA ................... Latanier, LA ................ Hudson, LA ................. Robert, LA .................. Alexandria Front, LA ........ Callahan, LA ................. Cotton, LA ................... Rapides, LA .................. Boyce, LA ................... Total standard revetment, Red River ................... Miles Above Mouth 31 34 36 24 30 36 39 L RL R 11,770 11,720 5,250 2,800 31,540 (5.97 Miles) 1,848 3,658 2,187 7,693 (1.46 Miles) RL R Below Confluence of Old and Mississippi Rivers 10 79 69 73 75 77 83 88 89 91 93 99 102 105 110 116 119 125 RRL RRRRRRRRRRRRRRRR - - - - - - - 6,652 - - - - - - - 6,190 - - - - - - - 6,815 - - - - - - - 19,657 (3.72 Miles) - - - - - - - 2,690 - - - - - - - 4,000 - - - - - - - 2,400 - - - - - - - 650 - - - - - - - 3,325 - - - - - - - 3,925 - - - - - - - 2,900 - - - - - - - 2,700 - - - - - - - 2,460 - - - - - - - 1,458 - - - - - - - 5,500 - - - - - - - 5,280 - - - - - - - 4,000 - - - - - - - 14,700 - - - - - - - 1,030 - - - - - - - 4,548 - - - - - - - 61,566 (11.66 Miles) 03 It 0 CI) z TABLE 42-I (Continued) BANK REVETMENTS AND DIKES: VICKSBURG DISTRICT (FISCAL YEAR 1985) Operations This FY Construction .erative Nonop- Otpiverea- Above New Work Reinforcement Since Thru Head Bank Exten- Prior This Location of R sion Lap Mainte- FY FY Passes or (Linear (Linear (Linear nance (Linear (Linear (Miles) L Feet) Feet) (Squares)1 Feet) (Squares)1 (Squares)' Feet) Feet) RED RIVER7 continued Dikes7: Choctaw Bayou Bend, LA ..... 71 R - - - - - - - 2,000 Bringol (Egg Bend), LA ....... 73 R - - - - - - - 2,477 Egg Bend, LA ............... 75 R - - - - - - - 900 Cologne Bend, LA ............ 77 R - - - - - - - 1,850 Echo, LA ................... 78 R - - - - - - - 1,900 Richardson, LA .............. 79 R - - - - - - - 2,700 Alexandria, LA .............. 105 R - - - - - - (Rock groin) 270 Bertrand, LA ............... 122 R - - - - - - - 7,630 Total dikes, Red River ......- - - - - - - 19,727 (3.74 Miles) 1. Gross squares articulated concrete mattress (100 square feet). 2. Additional work required to reinforce failure at upstream tie in. 3. Contains 7,814 linear feet of trenchfill revetment (stone). 4. Linear feet of dike on which repairs were made. 5. Changed to correct previous errors. 6. See report on Arkansas River and tributaries, AR and OK, under Little Rock District. 7. Mileages based on 1967 hydrographic survey. 8. Includes all types of dikes and retards. 0 O0 0 0 z c: TABLE 42-J BANK REVETMENTS AND DIKES: MEMPHIS DISTRICT (FISCAL YEAR 1985) OpeCraotniostnrsu Tcthioisn FY Nonop- Opera- Constructionerative tive Above New Work Reinforcement Since Thru Head Bank Exten- Prior This Location of R sion Lap Mainte- FY FY Passes or (Linear (Linear (Linear nance (Linear (Linear (Miles) L Feet) Feet) (Squares)' Feet) (Squares)' (Squares)' Feet) Feet) MISSISSIPPI RIVER Standard revetment: Big Island, AR ............... 598 R - - - - - 8,327 - 3,905 Scrubgrass Bend, AR ......... 600 R - - - - - - 7,315 Henrico, AR .................. 606 R - - - - - - - 25,040 Cessions Towhead, AR ........ 615 L - - - - - - - 10,615 Knowlton, AR ............... 620 R - - - - - - - 16,900 Island 67, MS ................ 621 L - - - - - - - 7,625 Island 68 Bar, AR ............ 622 R - - - - - - - 6,445 Ludlow, AR .................. 626 R - - - - - - -10,390 Rescue Landing, AR-MS ...... 629 L - - - - - - - 27,020 Fair Landing, AR ............ 632 R - - - 1,244 3,393 - - 25,690 Burke Landing, MS ........... 637 L - - - - - - - 19,070 Island 62, AR ................ 638 R - - - - - - - 9,030 Island63,MS ............... 639 L - - - - - - - 11,454 Island 63 Bar, MS ............ 639 L - - - - - - - 3,795 Oldtown Bend, AR ........... 644 R 865 - 3,327 - - 4,444 - 26,860 Horseshoe, MS .............. 647 L - - - - - - - 16,385 Westover, AR ............... 650 R - - - - - - - 12,730 o Delta-Friars Point, MS ....... 655 L - - - - - - - 30,090 Helena, AR ................. 660 R - - - - - - - 36,460 Trotters Landing, MS ......... 665 L - - - - - - - 32,905 Flower Lake, MS ............. 667 L - - - - - - - 16,385 St. Francis, AR ............... 672 R - - - - - - - 24,663 Harbert Point, MS ........... 675 L - - - - - - - 9,065 z Walnut Bend, AR ............ 680 R - - - - - 1,833 - 27,220 Mhoon Bend, MS ............. 685 L - - - - - - - 35,828 Peters, AR .................. 692 R - - - - - - - 23,675 Commerce, MS .............. 695 L 6,6007 10 - - - - - 18,215 Porter Lake, AR ............. 700 R - - - - - - - 34,155 Pickett, MS-AR ............. 703 R - - - 540 1,478 - - 12,575 Norfolk-Star, MS ............ 709 L - - - - - - - 35,582 Cow Island Bend, AR ......... 714 R - - - - - 12,850 - 22,274 Cow Island Bend (Upper), TN ..................... 716 R - - - - - - 6,853 Coahoma, TN ............... 717 L - - - - - - - 9,270 Ensley, TN ................. 723 L - - - - - - - 41,766 Dismal Point, AR ............ 724 R - - - - - 7,129 - 7,200 Bauxippi-Wyanoke, AR ....... 730 R - - - - - - 24,530 Presidents Island, TN ......... 733 L - - - - - - 12,755 Hopefield Point, AR, TN ...... 736 R - - - - - - - 5,390 Loosahatchie-Memphis, TN ... 737 L - - - - - - -31,293 Loosahatchie Bar, TN ......... 740 R - - - - - - 2,070 St. Clair, AR ................ 742 R - - - - - 2,9302 Island 40, TN-AR ............ 744 R - - - - - - - 30,750 TABLE 42-J BANK REVETMENTS AND DIKES: MEMPHIS DISTRICT (Continued) (FISCAL YEAR 1985) Operations This FY Construction eNroantoivpe- Otpiveera Above New Work Reinforcement Since Thru Head Bank Exten- Prior This Location of R sion Lap Mainte- FY FY Passes or (Linear (Linear (Linear nance (Linear (Linea (Miles) L Feet) Feet) (Squares)' Feet) (Squares)' (Squares) Feet) Feet) MISSISSIPPI RIVER continued Standard Revetment: Brandywine, AR-TN .......... 750 R - - - - - - - 18,01 Shelb Forest, TN ............ 753 L - - - - - - - 9,55 Dean Island, AR ............. 756 R - - - - - - - 7,55 Cedar Point-Densford, TN .... 759 L - - - - - - - 20,19 Chute of Island 35, TN ........ 764 R - - - - - 1,077 - 29,19 Lookout Bar, TN ............. 772 R - - - - - 2,99 Lookout, TN .................. 774 R - - - - - 5,005 Sunrise Towhead, TN ......... 776 R - - - - - 14,615 Lower Bullerton, AR .......... 782 R - - - - - 28,35( Kate Aubrey Towhead- Island 30, TN .............. 786 R - - - - - 30,808 Osceola, AR ................ 786 R - - - - 1,35( Osceola, AR .................. 786 R - - - - - 5,823 Ashport-Keyes Point, TN ...... 791 L - - - - - 44,232 Kate Aubrey Island 30, TN .... 793 R - - - - - 1,626 - 2,500 Island 26, TN ................. 798 R - - - - - 15,69( Bend of Island 25, TN ......... 803 L - - - - - 22,730 Barfield, AR ................. 808 R - - - - - 46,07( Obion-Tamm, TN............. 819 L 1,490 705 5,267 - - - - 51,321 Huffman-Hickman, AR-TN ... 826 R - - -26,984 Heloise, TN ................. 831 L - - - - - 12,935 Island 18, MO ............... 836 R - - - - - 22,170 Linwood Bend, TN ............ 841 L - - - - - 14,850 Blaker Towhead, TN .......... 845 L - -17,087 Bells Point, MO ............... 845 R - - - - - 5,420 Gayoso-Caruthersville, MO .... 848 R - - - - - 25,600 Island 15, TN ................. 851 L - - - - 3,630 Hathaway Landing, TN ....... 852 L - - - - - 1,00 Robinson Bayou, MO .......... 852 R - - - - - 22,630 Fritz Landing, TN ........... 857 L - - - - - 15,670 Lee Towhead, MO ............ 859 L - - - - - 3,455 - 8,470 Bend of Island 14, TN ......... 859 L - - - - - 12,050 Above Lee Towhead, TN ...... 861 L - - - - - 4,943 Little Cypress, MO ........... 864 R 1,850 140 4,827 - -34,090 Merriwether-Cherokee, TN ... 869 L - - - 41,058 Linda, MO ................... 876 R - - - - - 11,950 Below Toney's Towhead, TN ... 879 L - - - - - 20,895 New Madrid Bend, MO ....... 886 R - - - - - 30,348 Kentucky Point, KY .......... 887 L - - - - - 7,960 New Madrid Bar, KY ......... 888 R - - - - - 15,375 New Madrid, MO ............ 889 R - - - - - 5,559 - Lr O 0 0 2 W 3 z0 I 1 z m )s SC ) La Forge, MO ................ Slough Landing Neck, TN-KY ................... Winchester Towhead, MO ..... Island 9, KY-TN ............. Milton Bell, MO ............. Chute of Island 8, KY ........ Bend of Island 8, MO ......... Island 8, KY ................. Hickman-Reelfoot, KY ....... Beckwith Bend, MO ......... Williams, KY ............... Wolf Island, KY ............. Columbus, KY ............... Belmont, MO ................ Island 3 and 4, KY ............ Campbell, KY ............... Pritchard, MO............... Mayfield Creek, KY ......... Wickliffe, KY ................ Cache-Cairo, IL (Ohio River) .. Total revetment, Memphis District Mississippi River ........ Dikes: Henrico, AR ................. Below Knowlton, AR ......... Island67,MS ............... Below Ludlow, AR ........... Sunflower, AR .............. Island 64, AR ................ Island 62, AR ................ Island 63 Bar, MS ........... Island 63, MS ............... Kangaroo Point, AR ......... Friars Point, MS ............ Montezuma Bar, MS ......... Montezuma Towhead, AR ..... Prairie Point, AR ............ Flower Lake, MS ............ St. Francis Towhead, MS ..... Below Walnut Bend, AR ...... Bordeaux Point, MS ......... Commerce, MS .............. Basket Bar, AR .............. Buck Island, MS ............. Porter Lake, AR ............. Pickett, MS ................. Seyppel, AR ................. CatIsland, AR ............... Coahoma, TN ............... Armstrong, AR-TN .......... Dismal Point, AR ............ Hopefield Point, AR ......... Robinson Crusoe, TN........ 892 899 900 905 908 913 914 914 919 924 927 934 937 938 940 943 948 949 953 958 R L RL RL RRL RLRLRRLRLLR 10,805 (2.05 Miles) 603 616 621 624 627 630 638 639 640 649 652 657 656 668 668 671 676 681 694 696 700 701 704 706 710 718 720 724 736 738 RRLRLRRLLRLLRRLL RLL RL RL RRLR RR R 855 13,421 7,828 3,697 1,784 4,871 52,266 (5) 900 250 1,100 - 1,215 1,680 610 - 20,680 32,940 5,540 33,585' 14,375 12,620 9,800 13,175 43,359 14,588 10,015 19,205 3,825 5,785 19,970 6,865 15,045 8,935 8,455 26,152 0 1,815,735 (343.89 Miles) (6) 6,310 10,233 4,320 5,040 5,520 7,330 23,180 2,600 5,640 5,730 6,870 12,430 3,450 10,391 11,0609 3,380 6,420 4,920 5,700 5,060 4,7058 , to 17,4809 , to 7,180 12,250 15,590 4,640 18,690 25,5109 1,330 21,9391 41 H1 C12 0 0z TABLE 42-J BANK REVETMENTS AND DIKES: MEMPHIS DISTRICT (FISCAL YEAR 1985) Operations This FY Construction .erative Nonop- Otpiveera- Above New Work Reinforcement Since Thru Head Bank Exten- Prior This Location of R sion Lap Mainte- FY FY Passes or (Linear (Linear (Linear nance (Linear (Linear (Miles) L Feet) Feet) (Squares)' Feet) (Squares)' (Squares)' Feet) Feet) MISSISSIPPI RIVER continued Dikes: Loosahatchie Bar, TN ......... 739 R - - - - - - - 3,950 Above Loosahatchie, TN ...... 742 L - - - 390 - - - 8,990 Redman Point, AR ............ 743 R - - - - - - - 7,750 Randolph Point, TN .......... 747 L - - - - - - - 16,740 Poker Point, AR ............. 748 R - - - - - - - 8,050 Corona Bar, TN-AR .......... 755 R - - - - - - - 8,430 Densford, TN ............... 757 L - - - - - - - 7,780 Cedar Point, TN ............. 759 L - - - - - - 2,890 Below Richardson Landing, TN ....................... 767 L - - - - - - - 5,950 Lookout, TN-AR ............. 771 R - - - - - - - 5,538 0 Plum Point, TN .............. 784 L - - - - - - 7,910 Lake Neark .................. 786 R - - - - - 2,545 Kate Aubrey, TN ............ 791 R - - - 500 - - - 11,270 Z Keyes Point, TN .............. 791 L - - - - - - - 19,775 Ashport-Goldust, TN-AR ...... 795 R - - - - - - -17,330 Forked Deer, TN ............. 798 L - - - - - - - 8,550 Island 25, AR ................. 804 R - - - - - - - 5,450 Nebraska Point, TN .......... 808 L - - - 600 - - - 12,149 Below Tamm Bend, TN ....... 813 L - - - - - - - 8,300 Wrights Point, AR ........... 820 R - - - 800 - - - 30,505 Island 21, Chute, TN .......... 824 L - - - - - 3,170 Head of Island 21, TN ......... 828 L - - - 300 - - - 5,460 Island20, MO-TN ............ 831 R - - - - - - - 18,139 Island 18, TN ................. 837 L - - - - - - - 8,670 Tennemo, TN ............... 842 L 1,885 - - - - - - 4,390 Blaker Towhead, TN .......... 843 L 4,070 - - - - - - 4,070 Caruthersville-Linwood Bend, MO .................. 844 R - - - - - - - 25,877 Sandy Hook, TN ............. 850 R - - - - - - 2,350 Island 15, TN ................. 851 L - - - - - - 7,510 Robinson Bayou, MO .......... 853 R - - - - - - 9,890 Hathaway, TN .............. 854 L 1,310 - - - - - 26,750 Island 15 Neck, TN ........... 854 L - - - - - - 21,100 Above Lee Towhead, TN ...... 859 L - - - - - - - 1,300 Below Cherokee, TN .......... 866 L - - - - - - - 6,230 Stewart Towhead, MO ........ 871 R - - - - - - - 18,290 Ruddles Point, MO ........... 874 R - - - - - - - 8,130 Island 11, MO ............... 882 R - - - - - - -4,039 Kentucky Point, KY .......... 887 L - - - - - - - 11,550 Morrison Towhead, MO ....... 890 R - - - - - - 1,070 Hotchkiss Bend, MO ......... Below Island 9, TN .......... Donaldson Point, MO ......... Island 9, KY ................. Above Williams, KY ......... Moore Island, KY-MO ........ Campbell, KY ................ Pritchard, MO ............... Island 1, KY ................. Total dikes, Memphis District, Mississippi River ......... 895 901 905 906 930 929 942 944 948 RL RLL RL RL 1,600 365 4,685 6,583 18,859 8,320 7,0106 1,1508 4,685 2,610 9,390 15,260 220 15,455 (2.9 Miles) 7,475 736,602 (139.51 Miles) 1. Gross squares-articulated concrete mattress (100 square feet). 2. Lumber mattress revetment 3. Rock groins. 4. Stone in pile dike. 5. Linear feet of dike on which repairs were made. 6. Linear feet of triangular frame retards and pile dikes. 7. No AC mattress, riprap paving only, 1000 foot upstream extension. 5,600 feet of unattached trench fill included also. 8. Erronously omitted in FY 84. 9. Erronously omitted in FY 84. 10. Net quantity after deducting feet of dike removed. 1 2 Mj1 C Cz TABLE 42-K PROJECT LEVEES: NEW ORLEANS DISTRICT (FISCAL YEAR 1985) Levees and Floodwalls Berms (Miles) Surfaced Roads on Levees (Miles) (Miles) Built to Approved Total Location Total Grade andSection In In Com- In Total System Com- System plete Authorized Place Thru When Built lete When Built Thru for This This This Com- This This Com- This This System FY FY FY pleted' FY FY pleted FY FY MISSISSIPPI RIVER Fifth Louisiana Levee District .......... (16.8) (16.8) (1.1) (10.7) (-) (-) (1.1) (15.5) (-) (15.5) Levees ..... ......................... 15.5 15.5 1.1 9.4 - - 1.1 15.5 - 15.5 Floodwalls ..........................- - - - - - - Old River structures and levees ....... 1.3 1.3 - 1.3 - - - . Atchafalaya Basin Levee District ....... .(126.3) (126.3) (-) (85.4) (5.3) (-) (-) (118.7) (-) (118.7) Levees .............................. 118.7 118.7 - 77.8 5.3 - - 118.7 - 118.7 Floodwalls ..........................- - - - - - - - Morganza structure and levee ........ 0.8 0.8 - 0.8 - - Morganza forebay levee .............. 6.7 6.7 - 6.7 - " Port Allen lock ...................... 0.1 0.1 - 0.1 - - - - - - Lafourche Basin Levee District ......... . (61.7) (61.7) (-) (24.1) (0.1) (-) (0.1) (61.7) (-) (61.7) Levees ............................. 61.7 61.7 - 24.1 0.1 - 0.1 61.7 - 61.7 Plaquemines West Levee District ....... . (37.9) (37.9) (-) (28.5) (-) (-) (-) (37.9) (-) (37.9) Levees ..... ......................... 37.9 37.9 - 28.5 - - - 37.9 - 37.9 Z Floodwalls ..........................- - - - - - - - - - Buras Levee District ................... (34.1) (34.1) (-) (19.7) (-) (-) (-) (34.0) (-) (34.0) Z Levees ............................. 34.0 34.0 - 19.7 - - - 34.0 - 34.0 Floodwalls ..........................- - - - - - - - Empire lock ........................ 0.1 0.1 - - - - - Baton Rouge front levees ............... . (2.1) (2.1) (-) (0.9) (-) (-) (-) (2.1) (-) (2.1) Pontchartrain Levee District ........... (124.9) (124.9) (4.2) (86.1) (4.7) (-) (-) (110.8) (-) (110.8) Levees ............................. 110.8 110.8 4.2 72.0 4.7 -110.8 - 110.8 Floodwalls ..........................- - - - - - - - Bonnet Carr guide levees ............ 11.3 11.3 - 11.3 - - - Bonnet Carre forebay levee ........... 1.3 1.3 - 1.3 - - - Bonnet Carre structure .............. 1.5 1.5 - 1.5 - - - - - - East Jefferson Levee District ........... .(11.6) (11.6) (2.0) (10.8) (-) (-) (-) (11.6) (-) (11.6) Levees ............................. 11.6 11.6 2.0 10.8 - -11.6 - 11.6 Floodwalls ..........................- - - - - - - - West Jefferson Levee District ........... .(20.0) (20.0) (-) (4.5) (-) (-) (-) (19.9) (-) (19.9) Levees ............................. 19.8 19.8 - 4.3 - - - 19.8 - 19.8 Floodwalls ......................... 0.1 0.1 - 0.1 - - - 0.1 - 0.1 Harvey Canal Lock .................. 0.1 0.1 - 0.1 - - - Orleans Levee District ................. (27.2) (27.2) (1.2) (17.7) (-) (-) (-) (18.4) (-) (18.4) Left descending, east bank Levees .............................. 4.6 4.6 - 2.3 - - - 4.6 - 4.6 Floodwalls ......................... 8.6 8.6 1.2 3.5 - - - IHNC lock ......................... 0.1 0.1 - 0.1 - - - i Right descending, west bank Levees ............................. Floodwalls ......................... Algiers Canal lock .................. Lake Borgne Basin Levee District ....... Levees ............................. Floodwalls .................... Grand Prairie Levee District ........... Levees ............................. Floodwalls .................... Total Mississippi River .......... ATCHAFALAYA BASIN FLOODWAY Atchafalaya River and Bayou des Glaises ..................... East bank Atchafalaya River ........ Bayou des Glaises ................... West bank Atchafalaya River ........ Simmesport Ring ................... M elville Ring ....................... Krotz Springs Ring ................. Mansura Hills to Hamburg ........... West protection levee, Hamburg to Berwick drainage canal via Calumet ....... Levees west of Berwick, Berwick drainage canal to Charenton drainage canal ..... Morganza upper guide levee ............ East protection levee, Morganza to Cutoff Bayou, including 19.5 miles of Morganza lower guide levee ..................... Total Atchafalaya Basin and Floodway .................... Total-Main Stem System ...... LAKE PONTCHARTRAIN, LA Lake Pontchartrain, LA ................ Item A levees ........................ Item B levees ....................... Item C levees ....................... Total .......................... 0p1 13.8 0.1 (11.6) 11.6 (37.4) 37.4 511.6 (148.4) 52.5 7.9 60.1 1.6 4.1 1.7 20.5 13.8 0.1 (11.6) 11.6 (37.4) 37.4 511.6 (148.4) 52.5 7.9 60.1 1.6 4.1 1.7 20.5 (128.7) (128.7) (56.5) (56.5) (8.9) (8.9) - (-) - (0.2) 0.2 8.7 (-) 11.7 0.1 (11.5) 11.5 (19.2) 19.2 319.1 (143.9) 52.5 7.9 55.6 1.6 4.1 1.7 20.5 (1.0) (67.3) (-) (-) (9.6) (8.9) (-) (-) 10.1 (-) (-) (-) (-) (-) (-) 1.2 (-) (-) (-) (-) (-) (-) (-) 13.8 (11.6) 11.6 (37.4) 37.4 479.6 (148.4) 52.5 7.9 60.1 1.6 4.1 1.7 20.5 (-) (127.7) (-) (-) (56.5) (8.9) (-) (-) (-) 13.8 (11.6) 11.6 (37.4) 37.4 479.6 (43.9) 20.2 12.0 - 11.7 (-) (66.3) (-) (-) (-) (8.9) (106.7) (106.7) (7.8) (40.8) (-) (-) (-) (105.0) (6.7) (39.2) 449.2 449.2 8.8 270.5 - - - 446.5 6.7 158.3 960.8 960.8 17.5 589.6 10.1 - 1.2 926.1 6.7 637.9 (17.4) (17.4) (-) (17.4) (-) (-) (-) (17.4) (-) (17.4) 5.0 5.0 - 5.0 - - - 5.0 - 5.0 10.1 10.1 - 10.1 - - - 10.1 - 10.1 2.3 2.3 - 2.3 - - - 2.3 - 2.3 17.4 17.4 - 17.4 - - - 17.4 - 17.4 n c z 1. Figures indicate landside seepage berms only. -- TABLE 42-L PROJECT LEVEES: VICKSBURG DISTRICT (FISCAL YEAR 1985) Levees and Floodwalls Berms (Miles)' Surfaced Roads on Levees (Miles) (Miles) Built to Approved Total Location Total Grade andSection In In Com- In Total System Com- Sstem lete Authorized Place Thru When Built lete When Built ru for This This This Com- This This Comr- This This System FY FY FY2 pleted3 FY4 FY pleted FY FY MISSISSIPPI RIVER East bank in Mississippi ................ 178.35 178.3 - 109.1 158.9 - 108.1 168.4 - 168.4 Greenville Harbor dikes ................ 7.8 7.8 - 7.8 - - - - West bank in Arkansas................. 75.6 75.6 - 45.2 51.1 - 47.0 75.4 - 75.4 West bank in Louisiana (above Red River) ..................... 198.7 198.7 - 67.1 88.7 - 67.3 197.8 - 197.8 Total Mississippi River ............. .460.4 460.4 - 229.2 298.7 - 222.4 442.5 - 442.5 YAZOO RIVER BASIN Headwater ........................... 624.76 305.6 .5 130.6 - - - 620.7 (-) 281.5 Backwater ............................ 96.6 44.6 - 0.0 - - - 96.6 - 39.0 Total Yazoo River Basin ............ 721.3 350.2 .5 130.6 - - - 717.3 (-) 320.5 ARKANSAS RIVER, ARKANSAS North bank ............................ 61.5' 56.2 - 56.2 8.3 - 8.3 47.4 - 47.4 South bank ............................ 85.4 85.4 - 85.4 24.7 - 24.7 84.1 - 81.1 Total Arkansas River .............. 146.9 141.6 - 141.6 33.0 - 33.0 131.5 - 128.5 RED RIVER BACKWATER LEVEES Total Red River backwater ......... 263.6 157.7 - 82.58 - - - 249.0 - 141.9 LOWER RED RIVER-SOUTH BANK RED RIVER Lower Red River-South Bank Red River levees .................... (59.2) (59.2) (-) (59.1) (-) (-) (-) (59.2) (-) (33.6) Hotwells to Moncla, LA, levees ....... 59.2 59.2 - 59.19 - - - 59.2 - 33.6 Floodwalls .........................- - - - - - - - Total Lower Red River ............. 59.2 59.2 - 59.1 - - - 59.2 - 33.6 1. This tabulation does not include riverside berms which are considered an integral part of the levee section. Riverside berms will be constructed along with levee enlargements or seepage berm contracts. 2. Levee that has adequate freeboard based on the refined 1973 MR&T project flood flow line for the Mississippi River. Levees with more than 2 feet of freeboard are considered adequate. 3. Subject to change as planning progresses. Does not include existing berms which need restudy. 4. Based on refined 1973 MR&T project flood flow line. 5. Includes 1.4 miles of concrete floodwall and 0.3 mile of levee on Vicksburg city front. 6. Includes 36.9 miles of local protection works; 61.3 miles along Whittington Auxiliary Channel; 210 miles in Upper Yazoo Projects; 156.1 miles along main stem; and 160.4 miles on tributaries. 7. Includes 5.3 miles for Gillett new levee. 8. Revised to reflect 1973 project design flow line. 9. Reflects results of flowline reanalysis. O -a 0 lJ C0 y1 TABLE 42-M PROJECT LEVEES: MEMPHIS DISTRICT (FISCAL YEAR 1985) Levees and Floodwalls Berms (Miles) ' Surfaced Roads on Levees (Miles) (Miles) Built to Approved Total Location Total Grade andSection In In Com- In Total System Corn- System plete Authorized Place Thru When Built plete When Built Thru for This This This Corn- This This Corn- This This System FY FY FY pleted' FY FY pleted FY FY MISSISSIPPI RIVER M ounds, IL ........................... Mound City, IL ....................... Cairo Drainage District ............... City of Cairo .......................... Little River Drainage District .......... Levee District No. 2, Scott County, MO .................... Levee District No. 3, Mississippi County, MO .............. St. Johns Leveee and Drainage District .................... St. Francis Levee District of MO ....... City of Hickman, KY .................. Board of Levee Commissioners Fulton County, KY .................... Reelfoot Levee District of Lake and Obion Counties, TN .................. Madrid Bend Levee District, Lake Co., TN ........................ Lake County Levee and Drainage District .................... Dyer County Levee and Drainage District No. 1 .............. Tipton-Obion levee extension .......... St. Francis Levee District of AR ....... Helena Improvement District No. 1 ..... Cotton Belt Levee District No. 1 ......... Laconia Drainage and Levee District Phillips County, AR ................ Laconia Levee District No. 1 of Desha County, AR ................... Laconia Circle Special Drainage District of Desha County, AR ........... Yazoo-Mississippi Delta Levee District ..... .................. New Madrid, MO, St. Johns Levee and Drainage District .......... 3.9 2.7 13.82 6.2 19.3 13.8 3.9 2.7 13.8 6.2 19.3 13.8 3.9 2.7 13.8 6.2 19.3 13.8 26.0 58.2 55.7 1.4 26.0 26.0 58.73 58.7 55.7 55.7 1.4 1.4 16.7 16.7 4.5 4.5 5.2 5.2 15.9 21.3 6.5 156.7 5.3 23.9 15.9 21.3 156.7 5.3 23.9 0.5 2.7 4.6 4.4 4.9 4.2 12.9 42.7 23.0 .5 .7 .5 .7 0.9 1.6 1.7 4.9 26.0 12.0 16.74 15.5 11.4 4.54 5.24 15.9 21.3 153.24 5.3 23.9 20.5 20.5 18.1 18.1 6.6 6.6 93.6 93.6 20.5 0.6 9.1 1.3 94.6 2.4 18.8 11.5 0.3 4.5 5.2 4.5 15.9 - 0.4 2.7 80.3 - 2.4 - 18.8 11.5 18.14 12.9 6.64 93.6 9.2 16.5 87.3 85.1 0.3 - - - 0.3 3.6 1.1 8.5 4.0 19.3 13.8 46.6 55.1 0.5 16.3 3.6 1.1 8.5 3.5 19.3 13.8 26.0 46.1 55.1 16.3 4.3 5.2 15.9 21.3 6.5 156.7 4.7 23.9 20.5 21.3 156.7 4.2 23.9 20.5 16.5 93.6 93.6 0.3 TABLE 42-M (Continued) PROJECT LEVEES: MEMPHIS DISTRICT (FISCAL YEAR 1985) Levees and Floodwalls Berms (Miles)' Surfaced Roads on Levees (Miles) (Miles) Built to Approved Total Location Total Grade and Section In In Com- In Total System Corn- System plete Authorized Place Thru When Built plete When Built Thru for This This This Com- This This Com- This This System FY FY FY pleted' FY FY pleted FY FY MISSISSIPPI RIVER-continued Madrid Bend L.D., Fulton Co., KY ....................... 4.4 4.4 - 4.44 - -- 4.4 - 4.4 Birds Point-New Madrid setback levee ........................ 35.3 35.3 - 35.3 35.3 - - 35.3 - 35.3 Total Mississippi River ............. .636.3 629.5 - 625.5 389.5 5.6 245.1 604.1 - 595.1 ST. FRANCIS RIVER East bank ............................ 159.5 156.2 - 156.2 - - - 156.7 - 81.7 West bank ............................ 148.7 146.7 - 146.7 - - - 144.3 - 38.8 Total St. Francis River ............. 308.2 302.9 - 302.9 - - - 301.0 - 120.5 LITTLE RIVER East bank (left) ....................... 40.7 40.7 - 40.7 - - - 40.7 - 13.1 West bank ............................ 35.1 35.1 - 35.1 - - - 35.1 - 23.7 Elk Chute ............................. 39.9 39.9 - 39.9 - - - 39.7 - 17.3 West Basin and middle valley .......... 14.4 14.4 - 14.4 - - - 13.4 - 13.4 Total Little River .................. 130.1 130.1 - 130.1 - - - 128.9 - 67.5 LOWER WHITE RIVER White River backwater levee ........... 40.2 40.2 - 40.2 - - - 38.8 - 38.8 Augusta to Clarendon .................. 49.2 39.5 - 39.5 - - - 49.2 - 36.2 Clarendon levee ....................... 6.2 6.2 - 4.4 - - - - Total Lower White River ........... 95.6 85.9 - 84.1 - - - 88.0 - 75.0 MEMPHIS HARBOR Memphis Harbor ...................... 10.5 10.5 - 10.5 7.0 - 1.5 10.5 - 10.5 1. Subject to change as planning progresses. 2. Includes 5.1 miles of Cache River levee. This levee was enlarged to 1928 grades with Federal funds, but since that time has been classified as a secondary levee. 3. Includes 12.1 miles of Farrenburg levee. This levee was enlarged to 1928 grades with Federal funds, but since that time has been classified as a secondary levee. 4. Shown complete. Authority MSRC-ED-TL (MD 19 Mar. 80) 1st Ind. 21 Apr. 80. 0 O m0 z z C1 P RECAPITULATION TABLE 42-N PROJECT LEVEE TABLES 42-K, -L, AND-M (FISCAL YEAR 1985) Levees and Floodwalls Berms (Miles) Surfaced Roads on Levees (Miles) (Miles) Built to Approved Total Location Total Grade and Section In In Com- In Total System Com- System plete Authorized Place Thru When Built plete When Built Thru for This This This Com- This This Com- This This System FY FY FY pleted FY FY pleted FY FY MISSISSIPPI RIVERMAIN STEM New Orleans District, Table 42-K ....... 511.6 511.6 8.7 319.1 10.1 (-) 1.2 479.6 - 479.6 Vicksburg District, Table 42-L ......... 460.4 460.4 - 229.2 298.7 - 222.4 442.5 - 442.5 Memphis District, Table 42-M .......... 636.3 629.5 - 625.5 389.5 5.6 245.1 604.1 - 595.1 Subtotal-Main Stem ................ 1,608.3 1,601.5 8.7 1,173.8 698.3 5.6 468.7 1,526.2 - 1,517.2 TRIBUTARIES (OFF MAIN STEM) INCLUDED IN MR&T SYSTEM Atchafalaya Basin Floodway-NOD .................... .449.2 449.2 8.8 270.5 - - - 446.5 6.7 158.3 Lower Red River- South Bank-VXD................... 59.2 59.2 - 59.1 - - - 59.2 - 33.6 Arkansas River-South Bank-VXD ..... 85.4 85.4 - 85.4 24.7 - 24.7 84.1 - 81.1 Subtotal-Tribs. in MR&T System .... 593.8 593.8 8.8 415.0 24.7 - 24.7 589.8 6.7 273.0 Total in MR&T System ............ 2,202.1 2,195.3 17.5 1,588.8 723.0 5.6 493.4 2,116.0 6.7 1,790.2 OTHER TRIBUTARIES IN MR&T PROJECT Lake Pontchartrain, LA,-NOD ........ 17.4 17.4 - 17.4 - - - 17.4 - 17.4 Yazoo River Basin-VXD ............. 721.3 350.2 .5 130.6 - - - 717.3 - 320.5 Arkansas River-North Bank-VXD ..... 61.5 56.2 - 56.2 8.3 - 8.3 47.4 - 47.4 Red River Backwater-VXD ........... 263.6 157.7 1.2 82.5 - - - 249.0 - 141.9 St. Francis River-MD ................. 308.2 302.9 - 302.9 - - - 301.0 - 120.5 Little River-MD ...................... 130.1 130.1 - 130.1 - - - 128.9 - 67.5 Lower White River-MD .............. 95.6 85.9 - 84.1 - - - 88.0 - 75.0 Memphis Harbor-MD ................ 10.5 10.5 - 10.5 7.0 - 1.5 10.5 - 10.5 Subtotal-Other Tribs. in MR&T Project .................... 1,608.2 1,110.9 1.7 814.3 15.3 - 9.8 1,559.5 - 800.7 Grand Total in Project ............. 3,810.3 3,306.2 19.2 2,403.1 738.3 5.6 503.2 3,675.5 6.7 2,590.9 C rJ) z REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 42-0 CHANNEL IMPROVEMENTS: NEW ORLEANS DISTRICT (FISCAL YEAR 1985) In Total System Complete Year When Built Thru Location Initi- Com- This This Percent ated pleted FY FY Complete (Miles) Bayou des Glaise diversion channel ................. 1938 6.0 - 6.0 100 Bayous Rapides, Boeuf, and Cocodrie ............... 1946 92.6 - 63.4 75 Charenton drainage and navigation canal ........... 1939 6.3 - 6.3 100 Wax Lake Outlet .................................. 1938 15.7 - 15.7 100 Atchafalaya Basin Floodway ...................... 1933 244.2 - 186.4 76 Morganza Floodway ............................... 1941 3.3 - 3.3 100 Old River outflow channel ........................ 1956 . 8.3 0.9 8.3 100 Old River inflow channel ........................... 1960 2.3 - 0.4 17 Old River lock approach channels .................. 1961 2.2 - 2.2 100 Baton Rouge Harbor (Devils Swamp) ............... 1958 2.5 - 2.5 100 Eastern Rapides-S.C. Avoyelles .................... - 83.5 - - - Teche-Vermillion Water Supply .................... - 6.3 - 6.3 100 42-50 MISSISSIPPI RIVER COMMISSION TABLE 42-P CHANNEL IMPROVEMENTS: VICKSBURG DISTRICT (FISCAL YEAR 1985) In Total System Corplete Year When Built Thru Location Initi- Com- This This Percent ated pleted FY FY Complete (Miles) BIG SUNFLOWER RIVER, ETC., MS Big Sunflower River .............................. 1947 199.1 - 199.1 100 Quiver River ..................................... 1947 69.6 - 69.6 100 Deer Creek ...................................... 1947 7.0 - 7.0 100 Steele Bayou ..................................... 1947 54.9 - 54.9 100 Steele Bayou ... . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1965 71.2 - 63.0 70 Main Canal ...................................... 1959 21.1 - 21.1 100 Main Canal2 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . - 22.2 - - Black Bayou ..................................... - 36.5 - - Big Sunflower River tributaries .................... 1957 227.2 - 227.2 100 Quiver River tributaries .......................... 1960 35.4 - 35.4 100 YAZOO BACKWATER Yazoo Backwater ................................ 1960 39.9 - 39.9 100 YAZOO BASIN HEADWATER, MS Upper Yazoo Project ............................. 1976 179.0 6.1 54.1 30 Coldwater River ................................. 1941 54.6 - 54.6 100 Arkabutla Canal ................................. 1948 0.4 - 0.4 100 Tallahatchie Canal ............................... 1940 74.8 - 73.5 85 Little Tallahatchie River and Panola-Quitman Floodway ...................... 1939 48.0 - 48.0 100 Greenwood protection works ...................... 1971 2.9 - 2.9 100 Yacona River .................................... 1952 1.8 - 1.8 100 Bobo Bayou ...................................... 1944 16.1 - 16.1 100 Cassidy Bayou ................................... 1934 69.0 - 69.0 100 Cassidy Bayou3 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . - 26.0 - - Bear Creek Diversion ............................. - 4.8 - - Lake Cormorant ................................. - 20.9 - - Hurricane Bayou ................................. - 2.5 - - Opossum Bayou .................................. - 20.8 - - Abaica Creek .................................... - 7.7 - - Chicopa Creek ................................... - 7.0 - - Bear Creek ...................................... - 23.3 - - Rocky Bayou ..................................... - 7.8 - - Whiteoak Bayou .................................. - 55.9 - - Miscellaneous ditches ............................. - 12.3 - - Yalobusha River .................................. 1939 46.0 - 46.0 100 Yazoo River ...................................... 1940 160.2 - 160.2 100 Whittington Auxiliary Channel .................... 1956 30.8 - 30.8 100 Tchula Lake ..................................... 1964 26.4 - 26.4 100 David-Burrell Bayou .............................. 1957 40.4 - 40.4 100 McKinney Bayou ................................. 1960 3.5 - 3.5 100 Hillside Floodway ................................ 1964 11.0 - 11.0 100 Yazoo City protection works ....................... 1 953 1.6 - 1.6 100 Ascalmore-Tippo Bayous ......................... 1975 30.2 - 15.1 50 Alligator-Catfish Bayou .......................... 1973 8.3 - 8.2 99 Pelucia Creek .................................... 1975 6.4 - 2.9 25 BOEUF & TENSAS RIVERS, ETC., LA AND AR Bayou Lafourche ................................. 1949 45.3 - 45.3 100 Bayou Lafourche4 .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1972 43.0 - 4.4 10 Big & Colewa Creeks ............................. 1947 81.4 - 81.4 100 42-51 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 42-P CHANNEL IMPROVEMENTS: VICKSBURG DISTRICT (Continued) (FISCAL YEAR 1985) In Total System Complete Year When Built Thru Location Initi- Com- This This Percent ated pleted FY FY Complete (Miles) BOEUF & TENSAS RIVERS, ETC., LA AND AR- continued Big & Colewa Creeks .............................. 1965 86.8 - 51.5 60 Tensas River ..................................... 1947 96.5 - 96.5 100 Tensas River6 .... . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1968 165.0 - 61.0 37 Boeuf River, AR and LA .......................... 1953 103.9 - 103.9 100 Fleschmans Bayou, AR ........................... 1963 6.6 - 6.6 100 Caney Bayou, AR ................................. 1964 7.4 - 7.4 100 Canal 18, AR ..................................... 1963 10.3 - 10.3 100 Big Bayou, AR ................................... 1952 33.3 - 33.3 100 Black Pond Slough, AR ............................ 1962 14.3 - 14.3 100 Bayou Macon, AR and LA 1959 150.8 - 150.8 100 Rush Bayou, AR ................................... 1964 6.7 - 6.7 100 Canal 19, AR ..................................... 1957 50.2 - 50.2 100 Canal 43, AR .................................. 1956 34.5 - 34.5 100 Canal 81, AR ...................................... 1957 32.7 - 32.7 100 Mill Bayou-Bayou Vidal ........................... - 14.8 - -- Kirsch Lake Canal ............................... - 9.3 - - Canal 19 Extension ............................... 1964 9.4 - 9.4 100 Lake Chicot Pumping Plant ....................... - 2.5 - 2.5 100 RED RIVER BACKWATER, LA Tensas-Cocodrie Pumping Plant ................... 1976 6.9 - 6.5 94 Six Mile Bayou, LA ............................... - 1.5 - 1.5 100 GRAND PRAIRIE, AR ........................... - 338.1 - - BAYOU METO, AR ............................. . - 164.9 - - 1. Includes further work on 54.9 miles and adds 16.3 miles of channel to the project. 2. Includes further work on 21.1 miles and adds 1.1 miles of channel to the project. 3. Includes further work on 26.0 miles. 4. Includes further work on 38.6 miles and adds 4.4 miles of channel to the project. 5. Includes further work on 75.3 miles and adds 11.5 miles of channel to the project. 6. Includes further work on 96.5 miles and adds 68.5 additional miles of channel to the project. 42-52 MISSISSIPPI RIVER COMMISSION TABLE 42-Q CHANNEL IMPROVEMENTS: MEMPHIS DISTRICT (FISCAL YEAR 1985) In Total System Complete Year When Built Thru Location Initi- Comn- This This Percent ated pleted FY FY Complete (Miles) BIRDS POINT-NEW MADRID FLOODWAY Birds Point-New Madrid Intercepting Ditch Enlargement, Samos and Vicinity, MO ........... 1952 9.6 - 9.5 100 ST. FRANCIS BASIN Little River Drainage, MO......................... 1963 291.3 7.3 247.0 85 St. Francis River, MO and AR ..................... 1953 602.7 7.0 378.0 63 West Memphis Drainage, AR ...................... 1951 19.8 - 19.8 100 Big Slough and Mayo Ditch, AR .................... 1960 28.0 - 28.0 100 Tyronza River, AR ............................... 1939 12.7 - 12.7 100 L'Anguille River, AR ............................. (1) 112.0 - - LOWER WHITE RIVER BASIN, AR Cache River Basin, AR ........................... 1972 231.5 - 7.2 3 Big Creek and tributaries, AR ...................... (1) 103.8 - - WEST KENTUCKY TRIBUTARIES Obion Creek, KY ................................. (1) 41.7 - - WEST TENNESSEE TRIBUTARIES MS River, Western TN tributaries (Backwater Areas)(1946 Act) .................... 1952 34.3 - 34.3 100 Obion River Diversion Channel, TN (1946 Act) .................................. (1) 9.3 - - Reelfoot Lake-Lake No. 9, KY and TN ........................................ 1974 15.8 - 3.0 19 Running Reelfoot Bayou, TN ...................... 1955 19.7 - 19.7 100 MS River Below Cape Girardeau; West TN tributaries. (1948 Act) ...................... 1961 225.0 5.0 89.8 40 Wolf River and tributaries, TN .................... 1960 25.5 - 25.5 100 1. Not started. 42-53 TABLE 42-R REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 COSTS DURING FISCAL YEAR 1985 Item Construction Maintenance Other FEDERAL FUNDS Flood control, Mississippi River and tributaries: St. Louis District: General investigations Advance engineering and design St. Francis Basin-Wappapello Lake Subtotal Memphis District: General investigations Advance engineering and design Mississippi River levees St. Francis Basin Lower White River Cache Basin, Ark. Channel improvement West Tennessee tributaries West Kentucky tributaries Inspection of completed works Mapping Reelfoot Lake No. 9, TN-KY Mud Lake, TN Subtotal Vicksburg District: General investigations Advance engineering and design Mississippi River levees Lower Arkansas River Tensas Basin Yazoo Basin Channel improvement Mapping Inspection of completed works Streambank erosion control Tensas National Wildlife Refuge, LA Lower Red River-South Bank Red River Levee Subtotal New Orleans District: General investigations Advance engineering and design Mississippi River levees Old River Bayou Cocodrie and tributaries Atchafalaya Basin Channel improvement Bonnet Carrb Teche-Vermilion Basin water supply Inspection of completed works Mapping Major Rehabilitation Old River Subtotal Total Federal Funds 72,317,336 30,151,260 2,027,627 -- -- 1,446,394 10,196,161 8,170,901 -- 53,276,538 5,638,514 -- 256,993 97,103 -- 32,797,077 8,054,669 -- 34,852,103 10,069,595 -- 198,656 -- -- -- 187,686 -- -- 109,066 -- 131,577,528 32,327,534 1,446,394 224,369,411 104,920,222 5,499,309 42-54 $ $ 2,822,913 2,025,288 -- -- -- 2,025,288 2,027,627 -- 5,531,456 6,037,215 -- 3 5,393 6,818,552 2,064,423 7,994 -- 2,104 7,410 20,474,547 5,759,354 13,485,614 17,854,269 20,064,827 749 15,052,979 99,544 2,822,913 1,860,505 5,335,233 577,996 31,159,019 583,743 102,019 --. 39,618,515 561,777 232,567 844,688 19,490,114 8,554,612 214,504 120,516 132,482 TABLE 42-R (Continued) MISSISSIPPI RIVER COMMISSION COSTS DURING FISCAL YEAR 1985 Item Construction Maintenance Other CONTRIBUTED FUNDS Memphis District: Lake Neark AR, Recreation Facility 39,788 -- -- New Orleans District: Old River -- 111,379 -- Atchafalaya Basin 20,000 --- Mississippi River Levees 4,087 131,197 -- Total Contributed Funds 63,875 242,576 -- Grand Total, Federal and Contributed Funds 224,433,286 105,162,798 -- 42-55 TABLE 42-S REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 STATEMENTS OF ALLOTMENTS AND ACCRUED EXPENDITURES FOR FLOOD CONTROL, MISSISSIPPI RIVER AND TRIBUTARIES, FROM MAY 15, 1928, THROUGH SEP. 30, 1985 Unexpended Accrued Balance District or Installation and Class of Work Allotments Expenditures Sep. 30, 1985 ALLOTMENTS AND ACCRUED EXPENDITURES CHARGEABLE AGAINST FLOOD CONTROL ACT LIMITATIONS: COMPLETED WORKS: Waterways Experiment Station Office, Chief of Engineers Rock Island District: S. G. & O. prior to Aug. 18, 1941 St. Louis District: S. G. & O. prior to Aug. 18, 1941 Subtotal Memphis District: Des Arc, Ark. Contraction works DeValls Bluff, Ark. Mapping Memphis Harbor New Madrid Floodway Wolf River and tributaries Roads on levees (Mississippi River levees) S. G. & O. prior to Aug. 18, 1941 Subtotal Vicksburg District: Boeuf Basin levees Channel realignment, Arkansas River Contraction works Eudora Floodway Vicksburg Harbor Greenville Harbor Grants Canal (Mississippi River levees) Mapping Jonesville, LA Roads on levees S. G. & O. prior to Aug. 18, 1941 Subtotal New Orleans District: Baton Rouge Harbor, LA Atchafalaya River and Basin, LA Bonnet Carr& Spillway, LA Contraction works Mapping Roads on levees S. G. & O. prior to Aug. 18, 1941 Wax Lake Outlet and Charenton Canal Morganza Floodway and structure Lake Pontchartrain Atchafalaya Basin, rights-of-way and flowage, Bayou des Glaises setback Subtotal All other completed items: Surveys under Sec. 10, Flood Control Act of 1928 Impounded savings Plant transferred to revolving fund OCE (portion of allotment transferred to revolving fund, Washington Dist.) Subtotal Total completed works $ 874,000 19,158 14,010 $ 874,000 19,158 14,010 169,352 169,352 -- 1,076,520 1,076,520 -- 178,925 178,925 -- 8,692,791 8,692,791 -- 231,215 231,215 -- 1,450,337 1,450,337 -- 18,736,432 18,736,432 -- 6,521,543 6,521,543 -- 1,723,620 1,723,620 -- 12,426 12,426 -- 1,998,766 1,998,766 -- 39,546,055 39,546,055 -- 2,764,605 2,764,605 -- 125,074 125,074 -- 1,972,183 1,972,183 -- 826,235 826,235 -- 4,664,515 4,664,515 -- 2,864,516 2,864,516 -- 7,070 7,070 -- 1,531,021 1,531,021 -- 172,950 172,950 -- 105,660 105,660 -- 2,350,201 2,350,201 -- 17,384,030 17,384,030 -- 699,185 699,185 -- 3,375,492 3,375,492 -- 14,212,198 14,212,198 -- 1,258,916 1,258,916 -- 1,112,967 1,112,967 -- 540,838 540,838 -- 2,701,566 2,701,566 -- 10,098,817 10,098,817 -- 35,992,117 35,992,117 -- 5,513,110 5,513,110 -- 387,917 387,917 -- 75,893,123 75,893,123 -- 4,995,215 4,995,215 -- 1,593,097 1,593,097 -- 24,924,578 24,924,578 -- 19,882 19,882 -- 31,532,772 31,532,772 -- 165,432,500 165,432,500 -- 42-56 MISSISSIPPI RIVER COMMISSION TABLE 42-S (Continued) STATEMENTS OF ALLOTMENTS AND ACCRUED EXPENDITURES FOR FLOOD CONTROL, MISSISSIPPI RIVER AND TRIBUTARIES, FROM MAY 15, 1928, THROUGH SEP. 30, 1985 Unexpended Accrued Balance District or Installation and Class of Work Allotments Expenditures Sep. 30,1985 UNCOMPLETED WORKS: Rock Island District: Levees under Sec. 6, Flood Control Act of 1928 St. Louis District: Levees under Sec. 6, Flood Control Act of 1928 Subtotal Memphis District: Mississippi River levees Mississippi River levees New Madrid Channel improvement: Revetments Dredging Dikes Reelfoot Lake Reelfoot Lake, Lake No. 9, TN-KY St. Francis Basin: Wappapello Lake St. Francis River and tributaries Big Slough and Mayo ditch Little River drainage Lower White River: Clarendon Levee Augusta to Clarendon, AR White River backwater levee, AR Levees under Sec. 6, Flood Control Act of 1928 West Tennessee tributaries Cache Basin, AR West Kentucky tributaries Mud Lake Pumping Station, TN Eight Mile Creek Subtotal Vicksburg Distict: Mississippi River levees (excludes Grants Canal, $7,070, shown under completed works) Lower Arkansas River: North Bank South Bank Tensas Basin: Lake Chicot pumping plant Boeuf and Tensas Rivers, etc. Red River Backwater: Red River backwater levee, LA Tensas, Cocodrie pumping plant Lower Red River South Bank Red River Levees Tensas National Wildlife Refuge, LA Channel improvement: Revetments Dredging Dikes Levees under Sec. 6, Flood Control Act of 1928 Yazoo Basin: Sardis Lake Enid Lake Arkabutla Lake 579,462 1,897,980 2,477,442 579,462 1,897,980 2,477,442 158,446,354 98,000 313,427,307 57,249,400 107,265,000 439,434 7,895,000 9,019,908 183,460,282 965,429 46,316,992 496,715 1,779,846 10,624,501 108,651 32,440,900 7,915,000 994,000 107,000 40,000 939,089,719 188,849,991 7,049,414 15,676,286 87,155,800 40,125,200 51,011,646 44,726,300 438,400 39,800,000 341,922,065 23,549,260 74,014,040 958,175 26,512,600 21,325,400 16,017,700 156,732,233 98,000 313,394,349 57,249,400 107,246,916 439,434 7,836,342 9,019,908 181,670,229 965,429 46,281,427 496,715 1,779,846 10,624,501 108,651 31,804,609 7,915,000 993,944 73,127 934,729,520 186,453,733 7,049,414 15,676,286 86,054,179 40,007,467 49,865,199 43,808,039 186,626 39,727,414 340,259,537 23,549,260 73,674,470 958,175 26,476,521 21,270,371 16,017,406 1,714,121 32,958 18,084 58,658 1,790,053 35,565 636,831 56 33,873 40,000 4,360,199 2,396,258 1,101,621 117,733 1,146,447 918,261 251,774 72,586 1,662,528 339,570 36,079 55,029 294 42-57 TABLE 42-S (Continued) REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 STATEMENTS OF ALLOTMENTS AND ACCRUED EXPENDITURES FOR FLOOD CONTROL, MISSISSIPPI RIVER AND TRIBUTARIES, FROM MAY 15, 1928, THROUGH SEP. 30, 1985 Unexpended Accrued Balance District or Installation and Class of Work Allotments Expenditures Sep. 30,1982 Yazoo Basin: (Continued) Grenada Lake Greenwood Belzoni Yazoo City Will M. Whittington auxiliary channel Big Sunflower, etc. Main Stem Upper Yazoo Projects Yazoo Basin-Tributaries Tributaries (Except Ascal-Tippo-Opossum Bayous) Tributaries-Bank Stabilization Ascalmore-Tippo-Opossum Bayous Yazoo Basin Backwater Yazoo Backwater (Except Muddy Bayou) Muddy Bayou Steambank Erosion Control, Eval. and Demo. Demonstration Erosion Control Dam Safety Assurances-Sardis Dam Subtotal New Orleans District: Teche-Vermilion Basin Water Supply Bayou Cocodrie and Tributaries Channel improvement: Dredging Revetments Lower Red River (South Bank Levees) Levees Under Sec. 6, Flood Control Act of 1928 Mississippi River Levees Atachafalaya Basin: Atachafalaya Basin Floodway Atachafalaya River Navigation Atachafalaya Basin Floodway System Old River Subtotal TOTAL UNCOMPLETED WORKS ADVANCE ENGINEERING AND DESIGN (CONSTRUCTION) Memphis District: L'Anguille River Basin, AR Reelfoot Lake, Lake No. 9 Cache River Big Creek and Tributaries, Lower White River Clarendon Levee, Lower White River West Kentucky Tributaries Mud Lake Pumping Station, TN Harris Fork Creek, KY & TN Subtotal Vicksburg District: Yazoo Basin, Big Sunflower River, Steele Bayou Tensas - National Wildlife Refuge, LA Subtotal 45,246,900 11,630,000 316,656 2,205,611 10,950,966 34,169,300 27,407,000 46,355,006 59,900,310 612,484 22,682,200 57,720,200 5,145,200 14,767,000 5,399,000 100,000 1,323,740,110 33,819,000 4,774,008 35,945,266 489,149,117 18,056,600 200,680 194,048,000 503,208,537 303,463 60,000 246,866,000 1,526,430,671 45,183,627 11,521,276 316,656 2,205,611 10,950,966 33,520,223 27,323,927 44,421,717 58,067,895 612,484 21,795,476 56,272,477 5,145,200 14,767,000 3,911,360 1,307,049,992 33,802,041 4,733,483 35,945,266 488,250,841 18,056,600 200,680 192,740,837 502,355,547 303,463 246,497,667 1,522,886,425 63,273 108,724 -- -- 649,077 83,073 1,933,289 1,832,415 886,724 1,447,723 -- 1,487,640 100,000 16,690,118 16,959 40,525 -- 898,276 -- 1,307,163 852,990 -- 60,000 368,332 3,544,246 3,791,737,942 3,767,143,379 24,594,563 150,000 150,000 -- 30,000 30,000 -- 420,000 420,000 -- 365,000 364,339 -- 65,000 65,000 -- 175,000 175,000 -- 350,000 350,000 -- 540,000 540,000 -- 2,095,000 2,095,000 -- 29,700 29,700 -- 200,000 200,000 -- 229,700 229,700 -- 42-5$ MISSISSIPPI RIVER COMMISSION TABLE 42-S (Continued) STATEMENTS OF ALLOTMENTS AND ACCRUED EXPENDITURES FOR FLOOD CONTROL, MISSISSIPPI RIVER AND TRIBUTARIES, FROM MAY 15,1928, THROUGH SEP. 30, 1985 Unexpended Accrued Balance District or Installation and Class of Work Allotments Expenditures Sep. 30,1985 New Orleans District: Mississippi Delta Region 69,753 69,753 -- Teche Vermilion Basin-Water Supply 1,109,000 1,109,000 -- East Rapides & S. Central Avoyelles Parishes 965,247 965,247 -- Subtotal 2,144,000 2,144,000 -- TOTAL ADVANCE ENGINEERING AND DESIGN 4,468,700 4,468,700 -- TOTAL COMPLETED WORKS, UNCOMPLETED WORKS AND ADVANCE ENGINEERING AND DESIGN 3,961,639,142 3,937,044,579 24,594,563 RECREATION FACILITIES-COMPLETED PROJECTS Eight-Year Program Funds St. Louis District: Wappapello Lake, MO 2,405,300 2,400,222 5,078 Wappapello Lake, MO, Rockwood Landing 203,286 203,286 -- Subtotal 2,608,586 2,603,508 5,078 Vicksburg District: Sardis Lake 1,584,339 1,584,339 -- Enid Lake 2,268,209 2,268,209 -- Arkabutla Lake 2,189,280 2,189,280 -- Grenada Lake 1,631,281 1,631,281 -- Subtotal 7,673,109 7,673,109 -- Total Eight-Year Program Funds 10,281,695 10,276,617 5,078 Total chargeable against Flood Control Act Limitations excluding flood control emergencies 3,971,920,837 3,947,321,196 24,599,641 Total maintenance since Aug. 18, 1941 1,486,947,855 1,481,393,833 5,554,022 Total rehabilitation 31,113,000 31,113,000 -- Total flood control emergencies 14,900,300 14,900,300 -- Total general investigations 53,532,881 52,273,597 1,259,284 Total flood control, MR&T appropriations 5,558,414,873 5,527,001,926 31,412,947 Appropriations in addition to flood control, MR&T Other appropriations itemized in footnote (1), pp. 2068-69, Annual Report for 1953 32,068,909 32,068,909 -- Grand total appropriated to Sep. 30, 1985 5,590,483,782 5,559,070,835 31,412,947 Note: Preauthorization study costs chargeable to the MR&T authorization have been transferred to completed work. Costs not chargeable have been exluded from this report. 42-59 TABLE 42-T REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 STATEMENTS OF EXPENDITURES FOR LEVEES BY STATE AND LOCAL ORGANIZATIONS THROUGH DEC. 31, 1984 Engineer District St. Louis Memphis Vicksburg New Orleans Total Expenditures $ 77,752,969 254,274,707 121,899,060 513,937,811 $967,864,547 42-60 MISSISSIPPI RIVER COMMISSION TABLE 42-U COST AND FINANCIAL STATEMENT1 Total Project Funding FY 82 FY 83 FY 84 FY 85 Sep. 30,1985 Mississippi River General investigations: and tributaries Alloted 5,315,000 4,271,000 6,805,000 4,510,000 53,532,8812 (Regular Funds)' Cost 4,158,386 4,583,214 5,722,645 5,499,308 52,273,597 Construction (includes advance engineering and design): Alloted 179,793,000 289,370,000 199,330,000 216,083,000 3,791,737,942 Cost 176,047,889 204,211,601 265,108,622 224,369,411 3,767,143,380 Maintenance Alloted 78,290,000 109,548,000 94,345,000 102,554,000 1,537,326,406 Cost 79,934,108 90,732,587 111,777,503 104,920,222 1,321,931,935 Rehabilitations Alloted 600,000 137,000 -- -- 31,113,000 Cost 339,193 18,385 -- -- 31,113,000 Flood control emergencies (Maintenance): Alloted -- -- -- -- 14,885,922 Cost -- -- -- -- 14,885,922 (Contributed Funds) New Work: Contributed 40,736 393,600 46,311 315,294 9,560,771 Cost 81,201 296,065 56,321 63,875 9,206,129 Maintenance Contributed 169,852 125,424 128,923 279,972 2,165,735 Cost 145,008 51,592 161,616 242,576 2,030,703 1. Appropriations were as follows: Appropriations chargeable against Flood Control Act authorizations: Flood Control, MR&T except for emergencies (excludes Maintenance allotments Aug. 18, 1941, through Sep. 30, 1985): Net total allotted for works under Mississippi River Commission: $3,961,369,370 Eight-Year Program Funds, Construction General: 10,131,695 Surveys under Sec. 10, Flood Control Act of 1928 (not under MRC): 4,995,215 Transferred to revolving fund: 24,944,460 Impounded savings: 1,593,097 $4,003,033,837 Flood control emergencies: Net total alloted: 14,885,922 Impounded savings: 14,378 14,900,300 Additional funds not chargeable against Flood Control Act authorizations: Appropriations for Flood Control,MR&T, except for flood control emergencies: General investigations: 53,532,881 Maintenance allotments Aug. 18, 1941, through Sep. 30, 1985 1,486,947,855 1,540,480,736 Appropriations in addition to appropriations for Flood Control, MR&T (itemized in footnote (1), pp. 2068-69, Annual Report for 1953): 32,068,909 Budgetary and OCE Reserves: Grand total: 5,590,483,782 Reconciliation of appropriations and allotments: Total allotted to Sep. 30, 1985 5,558,936,632 Transferred to revolving fund: 24,944,460 Surveys under Sec. 10, Flood Control Act of 1928 (not under MRC): 4,995,215 Impounded savings withdrawn by Chief of Engineers: 1,607,475 Total Appropriations to Sep. 30, 1985: 5,590,483,782 Appropriations for past four reporting periods were as follows: FY 82: $262,798,000; FY 83: $403,052,000; FY 84: $300,480,000; FY 85: $323,297,000. 2. Totals for General Investigations include four projects transferred from Construction totals per DAEN-CWB-W, Aug. 4, 78, teletype. 42-61 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 13-V MISSISSIPPI RIVER AND TRIBUTARIES ACTIVE GENERAL INVESTIGATIONS (96x3112) Federal Cost Totals by Item and CWIS Number FY 85 Categories SURVEYS (Category 100) ($) ($) Flood Damage Prevention (112) New Orleans District Atchafalaya Basin Water & Land Res - 12026 368,580 Mississippi-Louisiana Estuarine Area - 121193 1,849 Subtotal 370,429 Vicksburg District Boeuf-Tensas Basin, AR & LA - 81273 455,423 Larto Lake-Saline Lake, LA - 12065 234,721 Southwest Tributaries Basin, MS - 12351 212,448 Yazoo River Basin, MS - 12074 762,248 Subtotal 1,664,840 Memphis District Bayou du Chien - 33008 233,717 Eastern AR Reg-Comprehensive Study - 81266 453,479 Helena & Vicinity - 12165 525 Mayfield Creek - 10850 232,016 St. Francis River Below Wappapello - 22000 377,596 West Memphis, AR - 12164 1,627 Wolf-Loosahatchie Rivers, TN & MS Nonconnah - 33009 901 Subtotal 1,299,861 TOTAL (Category 110) 3,335,130 COLLECTION AND STUDY OF BASIC DATA (Category 120) New Orleans District 0 Vicksburg District 187,248 Memphis District 77,564 TOTAL (Category 120) 264,812 SUPPLEMENTAL PRE-AUTH STUDIES (Category 130) Flood Damage Prevention 132) Vicksburg District MS River East Bank Natchez - 76022 93,978 Memphis District Nonconnah Creek, TN (Phase I) - 77007 10 TOTAL (Category 130) 93,988 CONTINUATION OF PLANNING & ENGINEERING (Category 140) Navigation Projects (141) Vicksburg District Greenville Harbor, MS- 76021 80,658 Flood Control Projects (142) New Orleans District MS-LA Estuarine Area ADVCPE - 12193 271,063 Vicksburg District Bushley Bayou Area, LA - 75226 903 Memphis District St. Johns Bayou & New Madrid Fdwy - 77005 374,037 TOTAL (Category 140) 727,201 42-62 MISSISSIPPI RIVER COMMISSION TABLE 13-V (Continued) MISSISSIPPI RIVER AND TRIBUTARIES ACTIVE GENERAL INVESTIGATIONS (96x3112) Federal Cost Totals by Item and CWIS Number FY 85 Categories ADVANCE ENGINEERING & DESIGN (Category 160) Flood Control Projects (162) New Orleans District Eastern Rapides & S.C. Avoyelles Parishes - 75031 51,586 Mississippi Delta Region - 23270 752,776 Subtotal 804,362 Memphis District Harris Fork Creek, TN & KY- 77009 124,797 L'Anguille River Basin - 00082 149,018 Subtotal 273,815 TOTAL (Category 160) 1,078,177 GRAND TOTAL MR&T GENERAL INVESTIGATIONS 5,234,496 42-63 NATURAL DISASTER PREPAREDNESS RESPONSE AND RECOVERY ACTIVITIES Authority. Public Law 84-99, as amended, (Flood Control and Coastal Emergencies) provides authority for the Chief of Engineers to undertake disaster preparedness activities, flood fighting and rescue work, rehabilitation of flood control works damaged or destroyed by flood, protection or repair of Federally authorized shore protec- .ive works threatened or damaged by coastal storm, provision of emergency drinking water, and drought assistance. Activities. FY 1985, disaster preparedness activities included the review and update of existing emergency response plans; development of required new plans; training of response personnel; exercises to test plans, personnel and training; procurement and maintenance of critical supplies and equipment not readily available during initial response phase; maintenance and required upgrade of emergency operations centers; coordination with Federal, state and local response agencies and other public entities; and overall management of the preparedness program. The Corps responded to various flood problems across the Midwest beginning in January 1985 and continuing through May. Flood problems occurred during the entire period in the area from the lower Great Lakes to the Ohio River Valley. In February and March, problems developed along the Mississippi River mainstem and its tributaries. The Corps provided technical assistance, flood fighting equipment and materials to Federal, state, and local entities. After the flood waters receded, the Corps undertook necessary investigations and appropriate rehabilitation of damaged flood control projects. In the South and East, the Corps responded to several hurricanes and tropical storms from July through September 1985. FY 1985 saw four hurricanes strike the USA, killing 13 and doing more than $2 billion in damage. Hurricane Bob moved across Florida as a tropical storm, then hit South Carolina with 75 mph winds on June 25, killing one and causing $20 million in damage. Hurricane Danny hit Louisiana on August 15 with winds of up to 100 mph, and later spawned tornadoes in Alabama. Danny caused more than $50 million in damage and killed three. Hurricane Elena battered the Gulf Coast for several days before hitting Mississippi on September 2 with 125 mph winds. Over 1-1/2 million people were evacuated, 500,000 of them twice. Damages exceeded $1 billion, 3 were killed. Finally, Hurricane Gloria swept the east coast from North Carolina to Maine on September 26-27. Nearly one million people were evacuated. There were six deaths and damages were more than $1 billion. Corps assistance as a result of these major storms included flood fight assistance and rehabilitation activities under the Corps PL 84-99 emergency authority, and work in support of the Federal Emergency Management Agency under its PL 93-288 disaster assistance authority. Status of the PL 84-99 Emergency Fund Unallocated Balance as of 30 Sep 84 FY 1985 Appropriation FY 1985 Supplemental Appropriation Revocations, FY 1985 Total Funds Available Allocations Disaster Preparedness Emergency Operations Rehabilitation Advance Measures Hazard Mitigation Unallocated Balance as of 30 Sep 85 $ 8,849,151 25,000,000 25,000,000 9,357,656 $68,206,807 $ 9,244,150 2,402,945 13,892,297 18,083,240 24,872 $24,559,303 43-1 CALIFORNIA DEBRIS COMMISSION This Commission, consisting of three Corps officers appointed by the President with the consent of the Senate, created by act of March 1, 1893 (27 Stat. L., p. 507), was organized in San Francisco, CA, on June 8, 1893, and has jurisdiction and duties extending over drainage area of Sacramento and San Joaquin Rivers, comprising great central valley of California and extending from crest of the Sierra Nevada on the east to that of the Coast Range on the west, and from Mount Shasta and Pit River Basin on the north to Tehachapi Mountains on the south. These rivers empty into head of Suisun Bay ultimately discharging into Pacific Ocean through connecting bays and straits and the Golden Gate. Duties of the Commission comprise regulation of hydraulic mining in drainage area of Sacramento and San Joaquin Rivers, CA, so that debris will not be carried into navigable waters or otherwise cause damage; jurisdiction over construction and control of water storage facilities for domestic, irrigation, and power development purposes; and direction of improvements for control of floods on Sacramento River. IMPROVEMENTS Navigation Pag( 1. Regulation of hydraulic mining and preparation of plans ..................... 44-1 2. Sacramento River and tributaries, CA (debris control) .......................... 44-2 3. Treatment of Yuba River debris situation-restraining barriers, CA ........ 44-2 e Flood Control Page 4. Sacramento River, CA ................... 44-3 Tables Table 44-A Cost and Financial Table 44-B Statement ...................... 44-5 Authorizing Legislation .................... 44-6 Navigation 1. REGULATION OF HYDRAULIC MINING AND PREPARATION OF PLANS Location. Operations largely limited to territory between Mount Lassen on the north and Yosemite Valley on the south, on western watershed of Sierra Nevada. (See Geological Survey sheets for the area, 25 in number.) Existing project. Provides for regulating hydraulic mining operations, planning improvement of conditions upon Sacramento and San Joaquin Rivers and their tributaries affected by such operations, and preparation of plans to enable hydraulic mining to be resumed in their drainage areas. In addition, the Secretary of the Army is authorized to enter into contracts to supply storage for water and use of outlet facilities from debris-storage reservoirs for domestic and irrigation purposes and power development upon such conditions of delivery, use, and payment as he may approve. Applications of prospective miners arefullyinvestigated by California Debris Commission and permits to operate are issued to those who provide satisfactory debrisrestraining basins by construction of suitable dams where necessary or agree to make payment for storage in Government-constructed debris-restraining reservoirs constructed under act of June 19, 1934, as set forth below. For location and description of Governmentconstructed, debris-restraining reservoirs for general hydraulic mining, see Improvement 2. Local cooperation. Mineowners must bear all expenses incurred in complying with orders of the Commission for regulation of mining and restraint of debris. Operations and results during fiscal year. Minor administrative duties were accomplished. Administrative work overlaps that of improvements 2, 3, and 4, hereunder, and that of Sacramento District. Historical summary. The Commission received 1,292 applications for hydraulic mining licenses; 1 mine is licensed, but does not use storage behind Government debris dams. Work remaining is, in general, continuation of above or similar operations. 44-1 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 2. SACRAMENTO RIVER AND TRIBUTARIES, CA (DEBRIS CONTROL) Location. Project reservoirs are to be constructed in watersheds of Yuba, Bear, and American Rivers, CA (See Geological Survey sheets for basin areas, seven in number.) Existing project. For description of completed North Fork and Harry L. Englebright projects and authorizing act, see Annual Report for 1975. Initial recreation facilities were provided in FY 1959. Recreation areas at Harry L. Englebright Dam are maintained by the Corps. Recreation areas at North Fork Dam are no longer maintained and operated by Auburn Recreation Park and Parkway District, but have been turned over to the Bureau of Reclamation (known as the Water and Power Resources Service between November 6, 1979, and May 18, 1981) on a permit basis. Total Federal cost of new work for construction of these reservoirs was $4,646,872, including $40,000 and $25,000, respectively, for basic recreation facilities at Englebright Dam and North Fork Dam. Reservoir project sites on Middle Fork of American River and on Bear River have been deauthorized and excluded from foregoing cost. The 90-day Congressional project review period, required by sec. 12, Public Law 93-251, as amended, ended August 5, 1977, and resulted in deauthorization of that portion of the project. Estimated cost of that portion is $1,820,000 (1935). Local cooperation. Fully complied with. Improvements made to facilities at North Fork Dam by Auburn Recreation Park and Parkway District under a lease agreement with the Secretary of the Army and Auburn Boat Clubs (concessionaire) at an estimated cost of $46,000 since September 1953. On March 1, 1979, lands and waters at North Fork Dam were turned over to the Bureau of Reclamation on a 5-year renewable basis. On March 1, 1984, Permit No. DACWO5-4-79-527 was renewed for another 5 years and will be effective until February 28, 1989. Bureau will operate and maintain such use until Auburn project is completed, then a fee transfer will be made. Actual operation and maintenance of the recreation resource is being done by State of California by contract with the Bureau. Licenses. Under provisions of Contract No. W-1105- eng-2998 with Pacific Gas and Electric Co., payment is to be made to the Federal Government of $18,000 per year for the first 30 years (December 29, 1942 through December 28, 1972) and $48,000 per year between December 29, 1972, and December 28, 1992, in return for use of head at Englebright Dam and generation of hydroelectric power. Total payment through September 30, 1985, amounts .to $1,134,393; these funds are paid to California Debris Commission and deposited for return to the Treasury. License No. 2246, effective April 9, 1970 (date New Narrows powerplant put in operation) was issued by Federal Power Commission (known as the Federal Energy Regulatory Commission since January 9, 1978) to Yuba County Water Agency for hydroelectric power development of Yuba River by the company upstream from Englebright Dam. Under provisions of Contract No. DA-04-167-CIVENG-66-95 with Yuba County Water Agency, payment is to be made to the Federal Government of $100,000 per year for no more than 50 years. First payment (partial) of $73,151 was made April 1, 1971; total payment through September 30, 1985, amounts to $1,473,151. These funds are paid to Sacramento District and deposited for return to the Treasury. Operations and results during fiscal year. New work: Maintenance: Maintenance and operation activities continued at North Fork Dam at a cost of $2,445; and at Harry L. Englebright Dam at a cost of $644,655, including recreation facilities. Dam safety assurance studies were continued at Englebright Dam at a fiscal year cost of $204,667. Historical summary. Construction of dams was initiated in 1937; North Fork project was completed and in use at end of FY 1939, and Harry L. Englebright project was completed in January 1941. The two debriscontrol structures are in good condition. Public use of these reservoir recreation areas greatly overtaxes present capacities. Dam safety assurance studies were initiated at Englebright Dam in FY 1981. 3. TREATMENT OF YUBA RIVER DEBRIS SITUATIONRESTRAINING BARRIERS, CA Location. Works are on Yuba River between Marysville and where the river emerges from the foothills, near Hammonton, some 10 miles easterly from Marysville, or about 9 miles below the Narrows. (See Geological Survey Topographic map of Sacramento Valley, CA) Existing project. For description of completed project and authorizing act, see Annual Report for 1975. Total cost of new work was $723,259, of which $361,482 was U.S. funds and $361,777 required contributed funds by State of California. (For details of project in its original form, see Annual Report, 1917, p. 1810.) In February 1963, center section of dam failed and major rehabilitation of structure was completed in December 1964. Total cost for required rehabilitation was $1,660,000, of which $830,000 was Federal cost and $830,000 required contribution by State of California toward rehabilitation cost. During the December 24, 1964, floodflows on the Yuba River, the rehabilitated Daguerre Point Dam sustained considerable damage. (See 1965 Annual Report, p. 1647 "Operations and results during fiscal year.") The reconstructed portion of the dam completed earlier in December 1964 was undamaged by the flood. Permanent repair of Daguerre Point Dam abutment and fish facilities was completed in October 1965 at a cost of $447,808 with Federal and required State contributed funds on a matching basis. Local cooperation. Fully complied with for new work and major rehabilitation work. Total first cost to 44-2 CALIFORNIA DEBRIS COMMISSION local interests for new work was $361,777 (required contribution by State of California). In addition, training walls were built on each bank below Daguerre Point for 11,250 feet and just above Daguerre Point, on the south bank, for 11,000 linear feet by two gold-dredging companies in connection with their dredging operations. To build these training walls would have cost the United States $450,000 (1902 estimate). Flood channels were also built by gold-dredging companies within confines of project works. Cost to the United States of equally effective works to restrain debris movement would have been more than $776,000 (1926 estimate). Total costs to local interests for initial and permanent major rehabilitation works were $830,000 and $223,904, respectively, (required contribution by State of California). State of California must contribute annually an amount equal to the Federal allotment for maintenance. Operations and results during fiscal year. Maintenance: Operations included condition and operation studies by hired labor; and bank protection, Yuba River, various locations upstream from Marysville completed by contract, $7,078. Historical summary. Construction of project works was initiated in November 1902. Construction of Daguerre Point Dam was completed in May 1906; diversion of river over dam was completed in 1910; training walls and dikes were completed in 1935. About 149 million cubic yards of debris are held in lower 7 miles of Yuba River between Marysville and downstream end of training walls. About 20 million cubic yards are confined in river channel by Daguerre Point Dam. Additional millions of yards of loose material are in mine tailing fields adjacent to project training walls in upper 7-mile reach of project. Initial rehabilitation of Daguerre Point Dam begun in July 1963 was completed in December 1964. Contract for permanent rehabilitation of structure was initiated in July and completed in October 1965. Flood Control 4. SACRAMENTO RIVER, CA Location. Works covered by this improvement are on Sacramento River and tributaries in north-central California from Collinsville to Ordbend, a distance of 184 miles. Previous project. For details see page 1815 of Annual Report for 1917, page 1995of Annual Report for 1938, and page 2262 of Annual Report for 1907. Existing project. Sacramento River flood control project is a comprehensive plan of flood control for Sacramento River and lower reaches of its principal tributaries. Improvement extends along Sacramento River from Ordbend in Glenn County, CA, 184 miles downstream to its mouth at Collinsville at upper end of Suisun Bay, and comprises a system of levees, overflow weirs, drainage pumping plants, and flood bypass channels or floodways designed to carry surplus floodwaters without inundation of valley lands. About 980 miles of levee construction, with an average height of 15 feet, and 98 miles of bank protection are involved in project. For further details, see Annual Report for 1962, page 2115. (See table 44-B for authorizing legislation.) Estimated (October 1985) cost for existing project (exclusive of supplemental levee improvements), including new work and maintenance, is $169,950,000 of which $74,950,000 is Federal cost and $95 million non- Federal ($90,050,562 for lands and damages and relocations and $4,949,438 required contributed funds for levee construction, bank protection works, and levee setbacks). Of this amount, $4,939,752 was for new work and $9,686 for maintenance. In addition to project requirements, local interests constructed several pumping plants for drainage of agricultural and urban land protected by project levees. Some channel clearing work was accomplished by State of California and other local interests to supplement project levee construction. Dredging below Cache Slough and reconstruction of Cache Creek settling basin weir are considered deferred and excluded from foregoing cost estimate. Estimated cost (July 1962) of these project units is $2,560,000 and $520,000, respectively, a total of $3,080,000 plus U.S. costs, for construction. Operation and maintenance of completed project will be responsibility of local interests; as units of project are completed, they are transferred to agencies of State of California for operation and maintenance. Existing project was adopted by 1917 Flood Control Act (H. Doc 81, 62d Cong., 1st sess., as modified by Rivers and Harbors Committee Doc. 5, 63d Cong., 1st sess.), 1928 Flood Control Act (S. Doc. 23, 69th Cong., 1st sess.), River and Harbor Act of 1937 (S. Committee print 75th Cong., 1st sess.), and 1941 Flood Control Act (H. Doc. 205, 77th Cong., 1st sess.). Local cooperation. Local interests have fully complied with requirements for all work completed or under contract, and indicated they will be able to fulfill requirements for remaining work as scheduled. Local interest costs from required contributed funds for project work total $4,949,438 for levee construction, bank protection works, and levee setbacks, of which $4,939,752 was for new work and $9,686 for maintenance. Operations and results during fiscal year. Regular funds: Engineering continued. Historical summary. Construction of existing project began in FY 1918 and is about 99 percent complete. Channel improvement to date has produced a channel with a capacity of 579,000 cubic feet per second in Sacramento River below Cache Slough. In addition, discharges up to 21,000 cubic feet per second can be diverted from Sacramento River through Georgiana Slough. Completed major project items include about 977 miles of levees; five weirs with a combined discharge capacity of 602,000 cubic feet per second; two cutoff channels; two sets of outfall gates: channel improvement and clearing in Sacramento River, Butte Creek, Putah Creek, and Sutter and Tisdale Bypasses; construction of two main bypasses or floodways and secondary bypasses at Tisdale and Sacramento weirs and at Wadsworth 44-3 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Canal; construction of Knights Landing ridge cut and of Cache Creek settling basin; installation of gaging stations; and enlargement of Sacramento River below Cache Slough. Cutoffs at Collins Eddy and between Wild Irishman and Kinneys Bends were made in 1918 and 1919, respectively. Sacramento weir was completed in 1917, Fremont weir in 1924, Tisdale and Moulton weirs in 1932, and Colusa weir in 1933. Outfall gates at Knights Landing were constructed in 1930 and at mouth of Butte Slough in 1936. Pumping plants on Sutter Bypass were completed in 1944. Work items with reference to clearing, snagging, rectification of channels, and bank protection on Sacramento River and tributaries in Tehama County and from Red Bluff southerly, provided for by 1941 Flood Control Act were accomplished in fiscal years 1947, 1948, 1949, and 1951. Work remaining comprises completion of levee stage construction, Yolo Bypass and Cache Slough. (See table 44-C for total cost of existing project to September 30, 1985.) 44-4 CALIFORNIA DEBRIS COMMISSION TABLE 44-A COST AND FINANCIAL STATEMENT See Section n Text Project 1. RHey dralautliiocn M ofining and Preparation of Plans 2. Sacramento River and Tributaries, CA (Debris Control) Contributed Funds, Other) 3. Treatment of Yuba River Debris Situation Restraining Barriers, CA (Federal Funds) Required Contributed Funds) Cont ributed Funds, Other) 4. Saacramento River, (Federal Funds) (Contributed Funds) Total Cost to FY 82 FY 83 FY 84 FY 85 Sep 30, 1985 821,325 821,325 50,000 - - 50,000 - - 633,000 713,000 554,000 70; 635,354 605,227 653,198 691 i1 Lh Funding Maint. Approp. Cost New Work Approp. Cost Maint. Approp. Cost New Work Contrib. ost New Work Approp. Cost Maint. Approp. Cost Rehab. Approp. Cost New Work Contrib. Cost Maint. Contrib. Cost Rehab. Contrib. Cost New Work Contrib. Cost New Work Approp. Cost Maint. Approp. Cost New Work Contrib. ost Maint. Contrib. Cost 1. Exclusive of $644,503 appropriation and cost on inactive portion of project. 2. Includes $447,127 for recreational facilities at North Fork ($32,473) and Harry L. Englebright ($414,654), Code 710 appropriations. 3. Includes $447,127 for recreational facilities at North Fork ($32,473) and Harry L. Englebright ($414,654), Code 710 costs. 4. Includes $5,386,961from regular funds and $1,080,082 from Hydraulic Mining in California funds. 5. Includes $5,339,384 from regular costs and $1,080,082 from Hydraulic Mining in California costs. 6. Funds from State of California Department of Navigation and Ocean Development for acquisition of a boarding float at Englebright Dam. 7. Includes deferred maintenance funds in amount of $207,500. 8. Miscellaneous engineering and construction accomplished at expense of local interests in connection with rehabilitation of Daguerre Point Dam necessitated by December 1964 floodflows. 9. Includes appropriation and cost of $680,000 for new work for previous project and $1,486,469 public works funds for new work for existing project. 10. Includes $680,000 required contribution for previous project; $4,939,752 required contributed funds for existing project; and $310,801 voluntary contribution for bank protection for existing project. 11. Includes $9,686 required contributed funds for existing project. 44-5 28,000 344 2,851 3,255 16,564 20,000 19,026 2,257 25,000 2 22,435 1 15,000 1 19,436 1 - 30 - 27 S 5,093,9991 2 S 5,093,9991 3 2,000 6,467,0434 5,102 6,419,4666 - 12,4206 - 12,420 - 361,482 - 361,482 4,000 1,646,6567 0,066 1,618,8717 - 1,053,904 - 1,053,904 - 361,777 - 361,777 4,000 1,634,223 1,282 1,615,423 - 11,,005533,,990044 - 134,000 - 34,0008 0,000 67,926,3359 4,092 67,900,4279 - 1,979,104 - 1,979,104 - 10,724,08510 - 10,724,08510 9,68611 - 9,686" REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 TABLE 44-B AUTHORIZING LEGISLATION See Date Section in Authorizing Text Act Project and Work Authorized Documents 1. Mar. 1, 1893 Feb. 27, 1907 June 19, 1934 June 25, 1938 Dec. 22, 1944 and May 17, 1950 July 3, 1958 July 14, 1960 REGULATION OF HYDRAULIC MINING AND PREPARATION OF PLANS Created California Debris Commission and authorized: (a) Ex. Doc. 267, 51st Cong., Hydraulic mining under its regulation in drainage areas of 2d sess., Ex. Doc. 98, Sacramento and San Joaquin Rivers, if possible without 47th Cong., 1st sess.1 injury to navigability of these river systems or to lands adjacent thereto; and (b) preparation of plans by Commission for improvement of navigability of these river systems, and flood and debris-control therein. Authorized California Debris Commission to permit (Amendment of sec. 13, hydraulic mining without construction of impounding Act of Mar. 1, 1893.)' works, provided there is no injury to navigability of above river systems or lands adjacent thereto. Amended act of Mar. 1, 1893, which provides for construction of debris dams or other restraining works by California Debris Commission and collection of a 3-percent tax on gross proceeds of each mine using such facilities, so as to eliminate this tax and substitute an annual tax per cubic yard mined, obtained by dividing total capital cost of each dam, reservoir, and rights-of-way, by total capacity of reservoir for restraint of debris; and authorized revocation of Commission orders permitting such mining, for failure to pay this annual tax within 30 days after its due date; and also authorized receipt of money advances, from mineowners to aid such construction, to be refunded later from annual payments of yardage taxes on material mined. Added at end of sec. 23 of above act, a provision that the Secretary of the Army is authorized to enter into contracts to supply storage for water and use of outlet facilities from debris-storage reservoirs for domestic and irrigation purposes and power development, upon such conditions of delivery, use, and payment as he may approve, these payments are to be deposited to credit of such reservoir project, reducing its capital cost to be repaid by tax on mining operations. SACRAMENTO RIVER, CA Additional levee construction and reconstruction, including H. Docs. 649, 78th Cong., levee protection of Upper Butte Basin, and multipurpose 2d sess., and 367, 81st reservoirs.2 Cong., 1st sess. Bank protection and incidental channel improvements, H. Doc. 272, 84th Cong., Sacramento River from Chico Landing to Red Bluff, and 2d sess. local interests flood plain zoning above Chico Landing.2 Bank protection works at critical locations, Sacramento S. Doc. 103, 86th Cong., River.2 2d sess. 1. For latest published map, see Annual Report for 1913, p. 3170, and Rivers and Harbors Committee Document 50, 74th Cong., 1st seas. 2. This supplemental work is reported in detail under Sacramento District, Improvement No. 15. 44-6 4. CALIFORNIA DEBRIS COMMISSION TABLE 44-C SACRAMENTO RIVER, CA: TOTAL COST OF EXISTING PROJECT TO SEPTEMBER 30, 1985 (See Section 4 of Text) Funds New Work Maintenance Total Regular $65,733,958 $1,979,104 $67,713,062' Public Works 1,486,469 - 1,486,469 Total U.S. $67,220,427 $1,979,104 $69,199,531 Contributed Project Work 4,939,752 9,686 4,949,438 Contributed, Other 5,104,333 - 5,104,333 Total All Funds $77,264,512 $1,988,790 $79,253,302 1. Includes $429,671 representing book value of plant purchased with previous project funds and transferred to existing project without reimbursement. 44-7 U. S. ARMY ENGINEER WATERWAYS EXPERIMENT STATION Organization and functions. The Waterways Experiment Station (WES) is a field operating agency of the Chief of Engineers operating under the staff supervision of the Director, Research and Development. COL Allen F. Grum, Corps of Engineers, is Director. Dr. Robert W. Whalin, PE, is Technical Director. WES, the Corps of Engineers largest laboratory complex for research, testing, and development, consists of five technical laboratories: Hydraulics, Geotechnical, Structures, Environmental, and Coastal Engineering Research Center. The Hydraulics Laboratory, the largest laboratory of its kind in the world, uses a wide range of working models and computer-based numerical models for research and analysis of dams, levees, river and harbor projects, soil and streambank erosion, thermal pollution, etc. The Geotechnical Laboratory conducts research in soil mechanics, structural foundation design, embankment design and slope stability, seepage analysis, military pavements, engineering geology, rock mechanics, expedient surfacing, earthquake engineering, and mobility and trafficability. The Structures Laboratory uses theoretical, analytical, experimental, and modeling approaches to research the effects of nuclear and nonnuclear explosions, the response of structures to natural and explosive disturbances, and various construction materials with emphasis on concrete, especially the testing, repair, and preservation of existing concrete structures. The Environmental Laboratory researches the problems caused by man's activities with respect to the environment. Research programs include Dredged Material, Aquatic Plant Control, Environmental and Water Quality Operational Studies, Environmental Impact, Wetlands, and the Natural Resources Research Program. These and other programs of the Environmental Laboratory range through waste management, environmental regulations, and military aspects of terrain and camouflage. The Coastal Engineering Research Center conceives, plans, and conducts research and data collection in coastal/ocean engineering and nearshore oceanography to: provide a better understanding of waves, winds, water levels, tides, and currents; provide scientific and engineering data and design criteria; and determine the effects of the coastal activities of the Corps of Engineers which are important to environmental considerations in the coastal zone. WES Laboratories are engaged in research and engineering investigations in support of the civil and military missions of the Chief of Engineers. On a reimbursable basis, WES performs basic and applied research, develops state-of-the-art methods and techniques, tests materials and equipment, and provides consulting services. Subject to the approval of the Chief of Engineers, studies and investigations may be undertaken for agencies outside the Department of the Army. WES maintains an extensive scientific and engineering reference library to serve the specialized needs of the Corps of Engineers and issues publications of general interest; operates DoD Information Analysis Centers in the fields of Pavements and Soils Trafficability, Concrete Technology, Hydraulic Engineering, Soils Mechanics, and Coastal Engineering; and maintains the Corps of Engineers Engineering Computer Programs Library. During Fiscal Year 1985, 217 WES numbered reports of individual studies conducted at or for WES, 9 instructional reports, and 55 unnumbered publications (conference reports, special study reports, etc.) for WES and other offices were printed and distributed to Corps offices and interested outside agencies. Operations and results during the period. Work accomplished at WES is, in general, initially financed by the Corps of Engineers Revolving Fund, with direct reimbursement from agencies requesting research investigations and related services. The Station's total program during Fiscal Year 1985 was $114,290,000 which included $41,522,000 performed by contract. Of the total program $59,730,000 was oriented toward the civil sector and $54,560,000 to military. The plant replacement and improvement program was $4,920,990 for this period. 45-1 PERMANENT INTERNATIONAL ASSOCIATION OF NAVIGATION CONGRESSES (PIANC) The Permanent International Association of Navigation Congresses (PIANC) is an international organization with headquarters in Brussels, Belgium. It is a clearinghouse where engineers and port operators of the nations of the world exchange views and experiences on problems relating to ocean and inland navigation improvements. Its objective is broadly stated "to promote the progress of inland and maritime navigation." In 1902, the United States appropriated $3,000 annually for support and maintenance of the Permanent International Commission of Congresses of Navigation and for payment of the actual expenses of properly accredited national delegates of the United States to meetings of the Congresses and Commissions. An increase in the appropriation to $5,000 annually was authorized by the 1948 River and Harbor Act and an appropriation of $22,000 annually by the 1965 River and Harbor Act. The currenit appropriation of $45,000 was authorized by the 1974 Water Resources Development Act. Of this amount, an annual subvention of about $6,900 is paid by the U.S. Section to the International Association in Brussels, Belgium. The objective of the Association - to promote the progress of inland and maritime navigation - is met by holding International Congresses and publishing technical bulletins and other documents. The Congresses are held in various member countries, usually at four-year intervals. The Association is supported principally by member governments, but membership also extends to corporations and to individuals. Member governments are represented at the Congresses and at meetings of the Permanent International Commission by delegates, the number of official delegates to be determined by the amount of the annual subvention paid by the government, but not to exceed ten in number. Corporate members may send one official representative to the Congresses. Currently, the Permanent International Commission has 37 countries represented. Individual membership is of two classses - Annual and Life - depending on the method of payment of dues. There are 1,489 annual international members, 609 life members, and 690 corporate members, for a total of 2,788. Membership of the U.S. Section on May 31,1985, totaled 637, consisting of 113 life members, 426 individual members, and 98 corporate members. The affairs of the Association are managed by the Permanent International Commission composed of delegates from the supporting governments. The National Commission constitutes the governing body of the U.S. Section and the U.S. members of the Permanent International Commission. The Director of Civil Works, Office of the Chief of Engineers, US Army, and the Commander and Director, Water Resources Support Center, are the exofficio Chairman and Secretary, respectively, of the National Commission. The Secretary handles all administrative matters of the U.S. Section. During fiscal year 1985, National Commissioners were: Major General John F. Wall, USA, ex-officio Chairman; Colonel George R. Kleb, CE, ex-officio Secretary; Mr. J. Ron Brinson; Mr. Harry N. Cook; Mr. John A. Downs; Mr. James M. Goldston; Rear Admiral John Paul Jones, USN; Mr. John Pisani; Mr. Jack E. Ravan; and the Honorable William A. Vaughan. Lieutenant General John W. Morris, USA (Ret.) is an honorary Vice President of PIANC, having served two terms as a Vice President. Major General Charles G. Holle, USA (Ret.), Secretary-General, XXth International Navigation Congress, 1961, is ex-officio member of the Permanent International Commission. The Annual meeting of the Permanent International Commission (PIC) and the XXVI Congress, commemorating the 100th Anniversary of PIANC, was held in Brussels, Belgium, June 16-28, 1985, and was attended by all National Commissioners. Lieutenant General E. R. Heiberg III, PIANC International Vice President; Mr. William R. Murden, Chairman, PIANC International Finance Committee; and other members of the U.S. Section, also attended the PIC meeting and XXVI Congress. American representatives attended meetings of the International Study Commissions, two Permanent Technical Committees (PTCs) and Working Groups of PTCs. U.S. representation on these groups during this fiscal year was as follows: International Commission for Study of Locks, Ship Lifts, and River Weirs - Mr. John Davis Permanent Committee for Developing Countries - Major General Bates Burnell, USA (Ret.) Permanent Technical Committee I - Major General Robert Seedlock, USA (Ret.) Working Group 1, Economic Implications of Inland Waterway Development - Mr. Howard Olson Working Group 2, Disposal and Land Dumping of Dredged Material: Impact on the Environment - Mr. Charles C. Calhoun Working Group 3, Consideration of Risk in Determining Bank Protection - Mr. Alan D. Crowhurst Working Group 4, Use of Geotextiles for Inland Waterway Bank Protection - Mr. Rodney Resta Working Group 5, Container Transport with Inland Vessels - Mr. Morris A. Clyde Permanent Technical Committee II - Mr. Eugene H. Harlow Working Group 1, Navigation in Muddy Areas - Dr. John B. Herbich Working Group 2, Stability of Rubble Mound Breakwaters in Deeper Water - Mr. Eugene Harlow Working Group 3, Ice Navigation - Professor C. Allen Wortley Working Group 4, Handling of Dangerous Goods in Ports - Captain William R. Riedel Working Group 5, Classification of Soils and Rocks to be Dredged - Mr. J. W. Bean Working Group 6, Underkeel Clearance, Hard Bottoms/ Sea Conditions - Mr. Ronald C. Uhlin Working Group 7, Disposal of Dredged Materials Into the Sea - Colonel Herbert R. Haar, Jr., USA (Ret.) Working Group 8, Dimensions and Layout of Channels, Including two-way Channels - Mr. Leonard E. Van Houten Working Group 9, Damage Inflicted by Ships with Bulbous Bows on Underwater Structures - Mr. Wesley Allen, Jr. Working Group 10, Development of Modern Marine Terminals - Mr. Charles R. Roberts 46-1 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 Working Group 11, The Performance and Design Parameters of 10 to 20 (to be selected) Rubble-Mound Breakwaters, also Including the Causes for Failure - Dr. Robert W. Whalin Working Group 12, Floating Breakwaters - Mr. D.D. Davidson Working Group 13, Consequences of New Developments of Passenger Car Ferries - U.S. Section not participating Working Group 14, Economical Channel Maintenance Methods - Mr. James W. Bean Working Group 15, Graving Docks - Mr. John Davis and Dr. Michael Yachnis (This working group was created from the former Locks Commission.) Joint Subcommittee on Sport and Pleasure Navigation - Mr. John M. Nichol Working Group 1, Ecological Conservation in Relation to Sport and Pleasure Navigation - Mr. Neil Ross Working Group 2, Waves in Yacht Harbors and Marinas - Mr. Orson Smith Working Group 3, Provisions of Navigation Aids for Sport & Pleasure Craft - Mr. Austin E. Brant, Jr. U.S. Section regional meetings were held May 8-9, 1985 in Norfolk, Virginia, jointly sponsored by the Eastern Region and the Western Dredging Association; October 2- 4, 1985 in Corpus Christi, Texas, by the Central Region; and October 25-26, 1985 in Long Beach, California, by the Western Region. During 1985, the U.S. Section also held concurrent meetings and the PIANC exhibit was displayed at meetings with the Water Resources Congress, National Waterways Conference, and the Western Dredging Association. 46-2 INVESTIGATION OF PROJECTS UNDER FEDERAL POWER ACT The Federal Water Power Act of June 10, 1920, created the Federal Power Commission (in 1977 renamed the Federal Energy Regulatory Commission, FERC) composed of the Secretaries of War, Interior, and Agriculture, with authority to grant permits and licenses for hydroelectric development in all water over which Congress has jurisdiction. The act further required that work of the commission be performed by and through the Departments of War, Interior and Agriculture and their engineering, technical, and other personnel except as may be otherwise provided by law. By an act of June 23, 1930, entitled "An Act to Reorganize the Federal Power Commission," Secs. 1 and 2 of the Federal Water Power Act of 1920 were amended. A commission was provided for, to be composed of five commissioners to be appointed by the President, by and with the advice and consent of the Senate. The necessity of performing work through the Department of War, Interior and Agriculture was removed and the commission was authorized to appoint such officers and employees as necessary in executing its function. By Title II, Public Utility Act of 1935, the original Federal Water Power Act was made Part I of the Federal Power Act, and Parts II and III were added to that Act. On October 1, 1977, pursuant to the provisions of the Department of Energy Organization Act (DOE Act), Public Law 59-91 Stat. (August 4, 1977) and Executive Order No. 12009, 42 Fed. Reg. 46267 (September 15, 1977), the Federal Power Commission ceased to exist and its functions and regulatory responsibilities were transferred to the Secretary of Energy and the Federal Energy Regulatory Commission (FERC) which, as an independent commission within the Department of Energy was activated on October 1, 1977. Section 4(e) of the Federal Power Act provides that no water power license affecting navigable capacity of any navigable waters of the United States shall be issued until plans of the dam or other structures affecting navigation have been approved by the Chief of Engineers and the Secretary of the Army. By an action, notice of which was published in the Federal Register Volume 40, Number 74, dated April 16, 1975, the Secretary of the Army delegated to the Chief of Engineers his authority under Sec. 4(e) of the Federal Power Act. The Chief of Engineers on September 5, 1980 delegated to the Corps division engineers the authority for Section 4(e) approval of plans for non- Federal hydropower development affecting navigation. The following work of an engineering nature was accomplished by the Corps division and district offices under the direction of the Chief of Engineers during the fiscal year: 920 applications from non-Federal entities for planning, design, construction and operation of hydropower projects were reviewed and appropriate recommendations in the interest of flood control, navigation, and structural safety, relative to Corps projects, were furnished to the FERC. Of the total 920 applications, 103 applications were specifically for hydropower development at the existing Corps projects. Recommendations were furnished to the Commission concerning the impact of hydroelectric power development on the existing and proposed Federal water resources projects. Recommendations also were provided to the Commission on the environmental impacts of constructing power plant(s) at either proposed or existing projects. To date, there are 34 constructed non-Federal power plants at Corps projects with a total capacity of 1,227 MW. Non-Federal entities had 7 power plants under construction at Corps projects during the fiscal year, and had 14 licensed power plants in final design stages. The Corps bills FERC licensees for the costs incurred by the Corps in approving final design, plans and construction of power plants at Corps projects. In FY 1985 the total cost reimbursement to the Corps for this service was $553,538. Review of license applications is funded by the Corps as a line item in the General Investigation Account. In FY 85, the cost for this pre-licensing activity was $732,124. 47-1 REGULATORY, SUNKEN VESSEL REMOVAL & NATIONAL EMERGENCY PREPAREDNESS ACTIVITIES 1. Regulatory Activities Authorities. The following authorities charge the Corps of Engineers with the regulation of various water-related construction activities: Sections 9 and 10 of the River and Harbor Act of 1899 (structures in an alteration of waterways, e.g. boat docks); Section 103 of the Marine Protection and Sanctuaries Act of 1972 (ocean dumping); and Section 404 of the Clean Water Act (discharge of dredged and fill material). Work Completed. During FY 1985, the Corps received approximately 14,000 applications for permits and issued 7,000 permits and 2,400 letters of permission. In addition about 20,000 activities were authorized by regional or statewide permits which did not require individual applications from the public. Many thousands of other minor activities were authorized by the Corps' nationwide permits. The Corps discovered or was notified of a total of 4,500 alleged violations to be investigated. In FY 1985 the Corps continued its efforts toward regulatory reform based on a May 7, 1982, directive from the President's Task Force on Regulatory Relief. By the end of FY 1985, actions to streamline the Corps' procedures had reduced average permit application processing time to 75 days compared with 119 days at the end of FY 1982. TABLE 48-A GENERAL REGULATORY FUNCTIONS Obligations Unobligated Balance-30 Sep 84 .......... $1,283,823 Allotments .......................... +53,237,587 Total Funds Available .................... 54,521,410 Obligations...........................53,662,738 Unobligated Balance-30 Sep 85 .......... $ 858,672 Expenditures Unexpended Balance-30 Sep 83 ........... 4,207,694 Allotments .......................... +53,237,587 Total Funds Available .................... 57,445,281 Expenditures .............. ............... 53,784,944 Unexpended Balance-30 Sep 84 .......... $3,660,337 2. Investigation and Removal of Sunken Vessels Under the authority of Sections 19 and 20 of the River and Harbor Act of 1899, the Corps of Engineers investigated sunken vessels in navigable waters and removed those obstructing navigation. For obligations expenditures, see Table 48-B. 3. National Emergency Preparedness Activities Authority. Executive Order 11490, as amended, assigns responsibilities to executive departments and agencies to undertake national emergency planning and preparedness to develop an effective national capability to meet essential civilian and defense needs during major domestic emergencies and national security emergencies. Status: During FY 1985, the Corps of Engineers continued its efforts to improve its readiness posture and ability to respond to various national emergencies. Emphasis was placed on the initiation of program activities that require a long-term commitment of resources. These activities included regional macro-analysis of mobilization requirements and resources: maintenance of, planning for and development of emergency facilities to support continuity of operations: and, planning to meet the nation's water resources requirements during a national emergency. In the latter case, Executive Order 11490 has tasked the Corps of Engineers to be the Executive Agency responsible for emergency water planning. Significant strides were made in the development of preparedness guidance and execution plans at all levels. While the efforts undertaken identified additional shortfalls or problems to be addressed, the Corps program continues to move towards the goal of ensuring a national engineering and construction capability that can respond to any national emergency. For fiscal year obligations and expenditures see Table 48-C. TABLE 48-B REMOVAL OF SUNKEN VESSELS Obligations Unobligated Balance-30 Sep 84 .......... $ 68,175 Allotments ........................... -2,675,791 Total Funds Available ................... -2,607,616 Obligations.......................... -2,613,014 Unobligated Balance-30 Sep 85 .......... $ 5,398 Expenditures Unexpended Balance-30 Sep 85 ............ 209,533 Allotments .............. ................ -2,675,791 Total Funds Available ................... -2,466,258 Expenditures ......................... -2,471,656 Unexpended Balance-30 Sep 85 .......... $ 5,398 TABLE 48-C NATIONAL EMERGENCY PREPAREDNESS Obligations Unobligated Balance-30 Sep 84 .......... $ 256,166 Allotments ........................... +8,452,563 Total Funds Available ...................... 8,708,729 Obligations ............ .................. 7,670,581 Unobligated Balance-30 Sep 85 ............. $1,038,148 Expenditures Unexpended Balance-30 Sep 84 ............ 596,270 Allotments .................. ........... 8,452,563 Total Funds Available ..................... 9,048,833 Expenditures ............ ................ 7,383,817 Unexpended Balance-30 Sep 85 ............ $1,665,016 48-1 INTERNATIONAL BOUNDARY WATERS BOARDS In order to carry out United States obligations under international agreements, the Office of the Chief of Engineers and several Corps Divisions and Districts with jurisdiction over areas bordering Canada have representation on numerous international boards and committees. The majority of these boards were established by the International Joint Commission (IJC) as empowered in accordance with the provisions of the Boundary Waters Treaty of 1909 between the United States and Great Britain (for Canada). IJC boards fall into two broad categories: boards of control, which are more or less permanent and supervise compliance over an IJC order; and engineering or technical boards, which are usually dissovled after completing and reporting on an investigation assignment. In addition to boards created by the Commission, other international boards and committees are created by treaties or other informal arrangement in matters concerned with the water resources of joint interest, and the members report directly to the Governments or establishing agency. International boundary waters boards and committees having Corps of Engineer memberships during the fiscal year are listed in Table 49- 1. For an explanation of the constitution of the various boards and committees, see the FY 77 and FY 80 annual reports. TABLE 49-1 LJC BOARDS OF CONTROL HAVING CE MEMBERS BOARD NAME 1. Int. Lakes Superior 2. Int. St. Croix River 3. Int. Lake of the Woods 4. Int. Lake Champlain 5. Int. Kootenay Lake 6. Int. Rainy Lake 7. Int. Osoyoos Lake 8. Int. Niagara 9. Int. St. Lawrence River 10. Int. Skagit River *Signifies U.S. Section Chairman. YEAR ESTABLISHED 1914 1915 1925 1937 1938 1941 1943 1953 1953 1967 UNITED STATES REPRESENTATION *Div. Engr., NCD *Div. Engr., NED *Dist. Engr., St. Paul *Dist. Engr., New York * 1. Dist. Engr. Seattle 2. Dept of Interior, USGS, Boise, ID *Dist. Engr., St. Paul 1. Dist Engr. Seattle *2. Dept. of Interior, USGS, 'acoma, WA 3. Washington State Parks & Recreation Commission *1. Div. Engr., NCD 2. Dept. of Energy, FERC, Washington, D.C. *1. Div. Engr., NCD 2. St. Lawrence Seaway Development Corporation Massena, NY 3. St. Lawrence-Eastern Ontario Commission, Waterton, NY 4. NY State Pbwer Authority, Massena, NY *Dist. Engr., Seattle 49-1 IJC ENGINEERING OR STUDY BOARDS HAVING CE MEMBERS YEAR BOARD NAME ESTABLISHED 1. Int. Souris-Red Rivers Engineer 2. Int. Champlain-Richelieu :3. Int. Lake Erie Regulation Study 4. Int. Great Lakes Diversions and Consumptive Uses Study 15. Int. Great Lakes Technical Information Network Board 1948 1975 1977 1977 1979 UNITED STATES REPRESENTATION 1. Dist. Engr., St. Paul *2. Dept. of Interior, BOR, Washington, D.C. 3. Dept. of Interior, USGS, Washington, D.C. *1. New York Dept. Envir. Conser. 2. Dist. Engr., New York 3. Vermont Agency Envir. Conser. 4. New England River Basins Commission, Staff Associate 5. Dept. of Interior F&WS Boston, MA *1. Div. Engr., NCD 2. Ohio Environmental Protection Agency 3. New York Dept. Envir. Conser. 4. Dept. of Interior, F&WS, Boston, MA *1. Div. Engr., NCD 2. Michigan Dept. Nat. Res. 3. Illinois Dept. of Trans. 4. Pennsylvania Dept. of Envir. Res. 5. Dept. of Energy, FERC, New York, NY *1. NCEED-L, Detroit, MI 2. Great Lakes Environmental Research Lab., NOAA, Ann Arbor, MI 3. USGS, Reston, VA OTHER INTERNATIONAL BOARDS OR GROUPS HAVING CE MEMBERS BOARD NAME 16. Int. Lake Memphremagog 17. Coordinating Committee on Great Lakes Basic Hydraulic and Hydrologic Data 18. Int. Niagara Committee 19. Columbia River Treaty Entities 20. Columbia River Treaty Permanent Engineering *Signifies U.S. Section Chairman. YEAR ESTABLISHED 1920 1953 1955 1964 1964 UNITED STATES REPRESENTATION *Dist. Engr., New York *1. Eng. Div., North Central Div. 2. Dept. of Commerce, NOAA, Rockville, MD *Div. Engr., NCD 1. Div. Engr., NPD *2. Bonneville Power Admin., Portland, OR *1. OCE, DAEN-ECZ, Washington, D.C. 2. Dept. of Energy, Washington, D.C. 49-2 U.S. ARMY CONSTRUCTION ENGINEERING RESEARCH LABORATORY Organization and functions. The U.S. Army Construction Engineering Research Laboratory (CERL) is a field operating agency of the Chief of Engineers operating under the supervision of the Chief, Directorate of Research and Development. CERL, which is located in Champaign, IL, was officially dedicated on July 25, 1969, and is one of the Corps' four major laboratories. The laboratory is closely affiliated with the University of Illinois, sharing laboratory, library, computer, and personnel resources with the University. Colonel Paul J. Theuer, Corps of Engineers, is Commander and Director. CERL research programs are oriented toward the support of the total Army, the Army in garrison, the military installation, the Department of Defense, and the nation as a whole. The laboratory, which has base support, combat support, and civil works missions, is engaged in a construction research program designed to improve planning, design, construction, operation, and maintenance of a variety of Army facilities. The ultimate goal of the overall research effort is to create products that will save the Army resources. Research findings are transmitted directly to the field, as well as to private industry and the academic community. Within the Corps, research supports both military and civil works projects in the general areas of environmental quality, energy, materials, engineering management, and military engineering. In the area of environmental quality, CERL has developed a broad-based program designed to maintain military readiness standards, while still conforming to environmental quality regulations. These programs have included development of methods to predict noise impacts, water and air pollution control techniques, adaptations of currently used technologies to more stringent fluid and solid waste control, and computerized methods to cut the time and costs involved in environmental impact assessment. Energy research is oriented toward helping the Army meet its energy conservation goals. These projects include development of computer simulation technology for selection of more fuel-efficient energy systems and design methods and exploration of alternative fuel sources like solar energy and biomass. CERL's materials program is designed to lower the Army's costs for construction, modification, operation, and maintenance of its facilities. These projects include investigations on protective coatings, polymer technology, seismic criteria, quality monitoring systems, and materials syntheses and selection programs. CERL supports the Army decision-maker through its engineering management programs that are designed to increase facility efficiency and productivity. The development of automated data processing systems for management information, cost estimating, profit determination, architecture and design, corrosion mitigation, pavement management, housing contract maintenance, and habitability information have helped reduce costs throughout the military. CERL's military engineering program provides direct support to the battlefield engineer and to the maintenance of military readiness. This research has developed training aids, field-protective structures to increase combat survivability, and methods to enhance the effectiveness of operations during combat situations. In mobilization, CERL research has led to the development of planning systems to evaluate installation troop housing and other requirements, and to the development of low-cost, troop constructible foam shelters for use as emergency housing during the critical early stages of mobilization. During Fiscal Year 1985, USA-CERL produced 160 publications, of which 63 were technical reports, 15 were Army-level publications, and 82 were publications presented in the public domain. In addition, USA-CERL personnel presented 51 papers at scientific meetings. USA-CERL personnel prepared and presented 17 training programs in areas such as corrosion, automated specification editing and energy conservation. Operations and results during the period. Work performed during Fiscal Year 1985 was funded both directly and through reimbursable programs. USACERL's total program was $37.0 million, of which $13.9 million was direct RDT&E funding and $12.2 million was reimbursable funding from the Office of the Chief of Engineers and Corps Divisions and Districts. Other Federal agencies, such as the Air Force, Navy, Federal Aviation Administration, and Environmental Protection Agency accounted for $10.9 million. 50 -1 U.S. ARMY ENGINEER TOPOGRAPHIC LABORATORIES Organization and functions. The U.S. Army Engineer Topographic Laboratories (ETL) began during World War I as a temporary Engineer Detachment, formed to test aerial photography for topographic mapping. Since that time, ETL has grown into a sophisticated, modern research and development laboratory, applying the latest advances in electronics, computer data processing, space sciences, and related technologies to military and civil problems in mapping, surveying, land navigation, and geodesy. ETL is now a field operating activity of the Corps of Engineers commanded by Colonel Alan L. Laubscher. The Engineer Topographic Laboratories is the only defense research and development laboratory that addresses the full range of development from basic research to a final product in the topographic sciences. Support is provided to both the Military and Civil Works elements of the Corps and to the Army Materiel Command, Army Space Program Office, Defense Advanced Research Projects Agency, and the Defense Mapping Agency. To provide this support, ETL is organized into five operational elements, three of which are developmental laboratories. The Geographic Sciences Laboratory performs research and development associated with the extraction and presentation of geographic data for the Army in the field. The Topographic Developments Laboratory supports technological development in surveying and mapmaking. The Computer Sciences Laboratory develops advanced computer techniques and systems for processing, analyzing, and displaying topographic data derived from digital photography. The Research Institute performs most of the Laboratories' basic and applied research, and the Terrain Analysis Center prepares terrain studies needed by field Army elements, as directed by the Assistant Chief of Staff of the Army for Intelligence. During FY 85 copies of 35 ETL reports on individual studies conducted at or for ETL were distributed to Corps' offices and interested outside agencies. In recent years, the emphasis of ETL's research and development program has shifted from conventional mapmaking and surveying equipment and related techniques to new topographic data systems, which are required to support the coming generation of complex weapons systems and military geographic information systems required by field commanders for improved command, control, communications, and intelligence. The new systems frequently use data acquired by remote sensing, and much of the work done at ETL involves this technology. Several projects are investigating the types of data derived from sensors and means for exploiting those data. Central to this work are studies regarding the possibilities of automating image interpretation. Research in pattern recognition theory and artificial intelligence methodologies offers long-range promise toward this objective. Meanwhile, the extension of manual photo analysis to create knowledge-based/expert software indicates near-term improvements to interactive computer- assisted photo interpretation. The knowledge gained in these areas will be applicable not only to the mapping and terrain analysis missions of ETL, but also to the Army thrust of teleoperated and autonomous robotic vehicles. Other work is to investigate the digital processing of remotely sensed data and to define remote sensing inputs required for Army terrain graphics and terrain data bases. In addition, a Remote Sensing Consultant conducts short courses on remote sensing for Corps of Engineers and other government personnel. Operations and results during FY 85. The ETL's total program for FY 85 was $47,830,000. This included work done for other agencies as well as for the Corps of Engineers. Of this total program, $32,037,000 supported work performed by contract. Work in FY 85 included $232,000 charged to civil works funds. Civil works efforts in FY 85 focused on developing and demonstrating new survey techniques and equipment for use by Districts and Divisions. Scientists evaluated the use of Global Positioning System survey equipment for establishing control stations and performing other precise survey jobs. They established new techniques for using a north-seeking gyro to measure azimuths. Researchers also advised Corps officials on the use of lab-developed dam monitoring techniques, began work on a new technique for computing dredge volumes, and investigated the use of low-cost digital image analysis equipment for detecting permit violations in areas under the Corps' protection. 51-1 U.S. ARMY COLD REGIONS RESEARCH AND ENGINEERING LABORATORY Background. The U.S. Army Cold Regions Research and Engineering Laboratory (USACRREL), located in Hanover, New Hampshire, was created in January 1961. It merged the Snow, Ice and Permafrost Research Establishment (created in 1949) and the Arctic Construction and Frost Effects Laboratory (created in 1953), both of which were outgrowths of the Army's World War II experience in Alaska, Iceland and Greenland. The Laboratory's mission is to conduct and coordinate research and technology applicable to the Army's needs in those geographic areas of the world where cold presents a problem. The total authorized strength of USACRREL is 296 (278 civilian and 18 military), with a budget for FY85 of $25 million. USACRREL has six main buildings in Hanover (which total 284,000 square feet on 31 acres of land), including the main laboratory, the ice engineering facility, the logistics and supply building, the plant and equipment building, the equipment storage building and the frost effects research facility. USACRREL maintains a presence in Alaska at facilities located at Ft. Wainwright in Fairbanks. Applied cold regions research, appropriate to the Alaska location, is carried out by CRREL researchers. Facilities available include six buildings (totaling 30,000 square feet) and a permafrost tunnel (360-ft shaft drilled into frozen ground). USACRREL's basic and applied research covers a broad spectrum of cold regions studies. Basic research includes work in the physical, mechanical and chemical properties of snow and other forms of frozen precipitation, freshwater ice, sea ice and frozen ground. Basic research supports applied research in the major cold regions mission areas of Fire Support, Combat Support, Combat Service Support, Base Support, Flood Control and Navigation, Surveying and Remote Sensing, Civil Works Environmental Quality and Civil Works Construction, and Operation and Maintenance. Major Civil Works cold regions research topics include Ice Engineering, River Ice Management, Cold Regions Hydrology, Remote Sensing, and Environmental Impact. As the only Federal laboratory dedicated to cold regions research, USACRREL has an international reputation and maintains close ties with the international research community and with Federal and state agencies where it provides consulting services on a reimbursable basis. As the center of cold regions scientific and engineering expertise for the Corps of Engineers, USACRREL supports Corps districts and divisions by publishing field engineering reports, conducting demonstrations, sponsoring technical seminars for field engineers, and by making field visits to consult on engineering problems. Operations and Results During FY85. During FY85, USACRREL published and distributed 339 scientific and engineering reports (CRREL Reports; Monographs; Special Reports; Technical Notes; Technical Digests and information bulletins; journal articles; conference papers and abstracts; Corps, DA and other government publications; and books and nongovernment publications), contributed to 20 U.S. Army publications and presented 33 technical seminars and meetings. CRREL personnel consulted with divisions and districts on a broad range of topics and problems, including Ice Engineering and Remote Sensing and the SPOT Simulation evaluation. Also, prototype sensor packages have been installed and interfaced within the St. Paul, Detroit and Pittsburgh Corps districts using near-real time collection systems. A total of 415 One-Stop Consulting Services were performed in FY85. The CRREL River Ice Management Program began in FY83. Included in the RIM start was the initiation of the development of an ice forecasting model. FY85 accomplishments in RIM included the analysis of data collected along a 25-mile test reach on the Ohio River. The analysis indicates that freezingdegree- days are the driving input to forecasting ice conditions. This year the test reach on the Ohio was extended over 400 miles, from Pittsburgh to Meldahl lock and dam. Also underway is an analysis of Landsat images for mapping ice conditions on the Mississippi, Illinois and Ohio rivers. CRREL is directly supporting the upcoming basing of light infantry divisions at Ft. Drum, N.Y. An assistance group has been established to provide technical points of contact to assure that the most up-todate cold regions facilities technology is made available to Army construction agencies for these new facilities. CRREL is maintaining close contact with the Ft. Drum DEH, New York District, and participating architect-engineer firms. Consultations have been provided on design of wastewater treatment plant, heating plant and distribution system, roofing systems, including roofing type and snow load criteria, and paving system. In response to the Army's heightened concern over the winter battlefield and to expand the critical task of identifying customer requirements for CRREL's military R&D program, staff visits to all 13 TRADOC schools were made. From these visits it was deter- S.1 mined that 90% of our programs were addressing the TRADOC mission area deficiencies. Also as a result of these visits, a number of programming changes were made, particularly in the area of winter camouflage and robotics on the winter battlefield. Along similar lines during FY85, an Army regulation was drafted making the Ad Hoc Winter Warfare Committee established by CRREL several years ago into the U.S. Army Winter Warfare Board, an official Army panel on cold regions warfare doctrine. Also noteworthy among the FY85 accomplishments is CRREL's support to the Air Force in the reconnaissance of 33 sites in Canada and Alaska for the USAF North Warning System. 52"2 U.S. ARMY CORPS OF ENGINEERS WATER RESOURCES SUPPORT CENTER The Water Resources Support Center (WRSC), under the staff supervision of the Director of Civil Works, Headquarters, U.S. Army Corps of Engineers, is commanded by Colonel George R. Kleb. The Center is located at the Humphreys Engineer Center, Ft. Belvoir, Virginia. Its divisions are the Institute for Water Resources. Dredging Division, Data Collection and Management Division, Publications and Training Division, and Office of Budget and Management Support. Elements managed by the Center in other locations include the Hydrologic Engineering Center at Davis, California; the Marine Design Branch of the Dredging Division at Philadelphia, Pennsylvania; and the Waterborne Commerce Statistics Center of the Data Collection and Management Division at New Orleans, Louisiana. The accomplishments of WRSC during 1985 are given by division. Video Disc WRSC-C is the program manager for the interagency emergency operations video disc prototype system which was deployed for test and evaluation in the fall 1985. This cooperative program involves Chief of Engineers Civil Works Operations and Readiness Division (DAEN-CWO), Southwestern Division (SWD), Lower Mississippi Valley Division (LMVD), Federal Emergency Management Agency (FEMA), U.S. Geological Survey (USGS), National Oceanic and Atmospheric Administration (NOAA) and United States Coast Guard. The objective is to provide the capabilities to transfer geographically related emergency operation data in nearreal- time between Corps elements and other Federal, state, and local organizations for improved emergency management coordination. The system integrates "off the shelf," low cost video disc, microcomputers, graphics, and telecommunications technologies. Other applications for storage and retrieval of map products, training and briefing systems,. as a subsystem for information network, are being explored. Remote Sensing WRSC conducted the Corps 5th Remote Sensing Symposium held in Ann Arbor, Michigan, October 28-30, 1985. It was hosted by the North Central Division and there was an attendance of 325 people and 90 papers presented. The Southwestern Division has accepted to host the 6th Corps Remote Sensing to be held in Galveston, Texas, fall 1987. The Administration transfered the LANDSAT Civil Land Satellite System to the Private Sector in September 1985. WRSC is beginning discussions with EOSAT, the company awarded the contract, to develop terms of agreement for satellite data. Water Control Data Systems The Corps use of the Geostationary Operational Environmental Satellite (GOES) data collection system (DCS) continues to increase significantly. The number of data collection platforms installed or authorized to operate on this system through FY 1985 totaled 1,898. A major procurement of several minicomputers dedicated to water control, occurred in 1985. With the advent of these dedicated computers and the receipt of realtime data through the GOES DCS, water control management of Corps projects is becoming increasingly automated. The cooperative stream gaging program with the U.S. Geological Survey, automated in 1982, and tested in 1983 was fully operational for the 1985 program. Telecommunications Planning Telecommunications is one of the most important resources in support of the U.S. Army Corps of Engineers operational functions. Today, the technological opportunities and the effects of deregulation together with increasing costs and dependencies has created a need for a centralized planning function within the USACE to formulate a more coherent and integrated plan for utilization of the resource. In 1985, WRSC-C was tasked to establish a telecommunications planning organization responsible for developing and recommending a clear direction for mangement control and to formulate guidelines to ensure a more integrated and cost effective approach to implementation and management of telecommunications systems and networks within the agency. Waterborne Commerce Statistics Center The Waterborne Commerce Statistics Center (WCSC) has accomplished several significant milestones during CY 1985. WCSC has implemented a new reporting form and instructions which simplifies the reporting and improves the accuracy of waterborne commerce statistics. WCSC has established a remote dial-up capability which allows Corps offices to log on to WCSC's computer system. Several Corps districts have downloaded files from WCSC's computer to their IBM PC's. WCSC plans to develop standard queries which will allow Corps offices to extract data directly from WCSC's data base. WCSC has developed the computer software to create a public domain data base using the "Rule of Three." The "Rule of Three" requires that for any given commodity at least three vessel operating companies move the commodity from at least three loading facilities in the area of origin to at least three unloading facilities in the area of destination. WCSC is now trying to define a set of geographic areas that will result in a meaningful and useful public domain data set while maintaining the confidentiality of individual company's movements. The schedule is to have a public domain data base by the end of FY 86. The transition of data collection function from the Corps District to WCSC's contractor has been completed. Only the data collection in the Ohio River Division (ORD) is still collected by district personnel; Huntington District collects the ORD data. Future plans include improvement of WCSC's communications capability to facilitate remote data access at faster baud rates. WCSC will be receiving a new Harris 1000 computer system in FY 86 which will provide better response times and improve WCSC's data base capabilities. WCSC will be creating data bases containing preliminary data which will allow for earlier, more timely estimates of waterborne traffic and tonnage. 53-1 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 Port Facilities Branch The Port Facilities Branch collects and publishes data on the physical characteristics of the coastal, Great Lakes, and inland waterway ports of the United States. Fifty-six port series reports are published at intervals of approximately six to eight years, covering 190 port areas. During the calendar year 1985, 6 reports covering 25 port areas were published and offered for sale. No. 1 - Portland and Searsport, ME, and Portsmouth, NH No. 8 - Philadelphia, PA; Camden, NJ; Wilmington, DE; and Ports on Delaware River No. 23 - Galveston and Texas City, TX No. 28 - Los Angeles, Long Beach, and Port Hueneme, CA No. 34 - Portland, OR No. 64 - Minneapolis, MN, and Ports on Upper Mississippi River Miles 300-860 AOR. INSTITUTE FOR WATER RESOURCES Navigation Division The Navigation Division was formed in 1983 by combining the Navigation Analysis Center and the National Waterways Study staff. The Navigation Division supports Corps planners by development and maintenance of transportation planning data bases on waterway carriers, other transportation modes, and commodity movements; development of analytical capabilities; and dissemination of technical information and advice with regard to use of navigation data and analytical techniques. The division also conducts policy studies and. performs reimbursable and research studies for HQ, USACE and field offices. One of the important data bases is the lock Performance Monitoring System (PMS), which contains information of Corps lock operations on the inland waterways. This data base enables Corps personnel to study lock operation and performance; to determine methods, benefits, and costs of improving the waterway system; to monitor traffic and commodities moving on the inland waterways; and to monitor conditions that could affect traffic flow. The Navigation Division led Corps efforts to develop and test methodologies for evaluating the economic and financial leverage from competing ports on any given coastal port. This information increases the ability of local ports to design and implement practical and feasible cost recovery policies. It also systematically identifies elements of land side transportation infrastructure that contributes to each port's natural tributary area. These procedures are being tested in several field studies to determine costs and implementability. A draft manual combining significant economic and engineering attributes of non-deepening alternatives which facilitate loading and unloading of deep draft vessels has been developed. Vessel operating costs (ocean and inland), waterway and tow characteristics, and commodity and other economic projections are maintained to support various navigation systems studies. The Navigation Division has developed computer models to estimate economic development which would occur due to water resource and navigation projects, and supports the navigation user charge data base, which is used to estimate impacts of various cost recovery policies and strategies. Policy Studies The Policy Studies Division provides analysis and decision support on critical policy issues for the Director of Civil Works through investigations in policy development, program management and evaluations methods, and new missions and strategic planning. Fiscal Year 1985 work included studies of the clarity and effectiveness of O&M requirements for local protection projects, the future of intergovernmental relations and the USACE, state institutional arrangements affecting agreements for costshared planning and project financing, access to Performance Monitoring System (PMS) lock statistics, the potential role for the Civil Works planner in mobilization, and cost-shared study management. Other work included various support activities for elements of OCE and the field. These included support to the Chief of Engineer's Green Ribbon Panel implementation work group on programming and budgeting issues, support to Corps professional hydrologic engineers, support for the Chesapeake Bay Forum sponsored by the Secretary of the Army, classroom instruction on a variety of subjects to the Planning Associates at the Board of Engineers for River and Harbors and others, an analysis of potential impacts of pending legislation on the Civil Works program, and a financial and cost recovery analysis for Oregon Inlet, N.C. Additionally, the division provided similar support to interagency efforts. These included planning and conducting co-sponsored meetings between the Corps and the Interstate Conference on Water Problems, facilitation of high level interagency meetings for the Federal Preparedness Guide on Emergency Water Planning, support for the national high school debates on national water policy, as well as support to the United Nations Economic and Social Commission for Asia and the Pacific. Research Division The Research Division work in FY 1985 included development of a water demand forecasting model for use in water supply and conservation studies, development of a contingent valuation methodology for recreation assessment, and Deep Draft Evaluation procedures. Work continues in the areas of economic and demographic forecasting, economic effects of lock congestion, and flood damage assessment techniques. Research into microcomputer applications for planning analysis continues. Research to develop techniques for risk assessment related to the safety of Corps DAWS was initiated. The Institute's training program provides a means for transferring technical information and state-of-the-art techniques to various Corps users. Courses on topics ranging from Conflict Management and Economic Analysis for Water Resources Planning were conducted during the year. During FY 1985 approximately 375 persons attended 15 sessions of 10 training courses. 53-2 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 THE HYDROLOGIC ENGINEERING CENTER The Hydrologic Engineering Center's (HEC) programs in research training, methods systemization, planning analysis, and technical assistance make every effort to be aware of the problems and needs of the Corps and the Nation. To keep abreast of the latest developments throughout the profession, and to make use of this information in a manner best suited to the needs of the Corps, HEC maintains close contacts with universities, private industry and other Federal agencies, alike. The Center provided substantial technical assistance to 27 Corps offices during FY 1985, including the Office of the Chief of Engineers, the Waterways Experiment Station and the Institute for Water Resources. Technical assistance was also provided to other Federal agencies and to the Government of India (through the U.N.). One-fourth of HEC's resources were devoted to direct field assistance projects during FY 1985. Eleven formal training courses involving eighteen weeks of training were conducted at HEC. Three workshops, totaling two weeks, were also held. Research funding was a relatively high (about one-half) proportion of HEC's budget this year. Research Planning, design, construction, operation and maintenance of today's multiple-purpose water projects requires complex interdisciplinary analyses. These complex problems present major methodological and computational tasks to the water resources planner and engineer. The HEC seeks solutions to these problems through development of systematic methods and the use of computational power of computers. Research activities were carried out in 12 work units. These work units represent specific technical areas that have been identified in the Corps R&D program. The HEC's primary research area is entitled "Analytical Techniques in Water Resources Planning Studies." The HEC is also involved in the Corps research programs in water conservation and supply, planning methodologies, remote sensing, and environmental quality. A major new work unit addressing hydrologic dam safety and risk analysis procedures for spillway sizing began this year. HEC's R&D work units for FY 1985 are shown below. Improvements in Methods of Evaluating Hydrologic Phenomena Computer Methods for Water Resources Planning Water Resource Data Storage System Spatial Data Management and Analysis System Flood Forecasting for Use During Flood Emergencies Real-Time Reservoir Regulation Analytical Techniques for Evaluating Reservoir Systems Modernization of Computer Programs Hydrologic Methods for Determining Water Supply Potential Groundwater Recharge and Storage Remote Sensing and Spatial Data Applications Hydrologic/Hydraulic Risk Assessment of Dams Technical Assistance About $950,000 in technical assistance was provided to 27 offices during FY 1985. The offices included: 20 division and district offices; the Office of the Chief of Engineers (OCE); the Waterways Experiment Station (WES); the Bureau of Reclamation; the National Park Service; the Federal Highway Administration (FHWA); and the Institute for Water Resources (IWR). The largest single amount was $190,640 for portion of the $300,000 FHWA Water Surface Profiles Accuracy Research Study. Comprehensive Project Reports were prepared for four studies: Two-Dimensional Flow Modeling at Lock and Dam No. 8, Upper Mississippi River Evaluation of Proposed Modification Mojave River Dam, California Toutle River Mudflow Investigation La Junta, Colorado Local Protection Project, Phase I GDM Sediment Study Technical assistance projects involving the development of systems for real-time water control and data mangement continued to be a major emphasis of reimbursable work. About one-third of funding was for real-time water control systems. Work for the Huntington and Pittsburgh Districts involved the development of models for forecasting runoff and evaluating operations alternatives in major river basins. Assistance was provided to Rock Island District in implementing real-time data acquisition and management systems. Continuing assistance was provided to OCE in procuring water control computer equipment and in negotiations with the National Weather Service to establish a data exchange agreement and a generalized data exchange procedure between field offices. Testing of NWS-COE data exchange in Standard Hydrometeorological Excliange Format (SHEF) was accomplished. Training The HEC conducted a total of 20 weeks of training during FY 1985. Courses and workshops conducted were: Formal Courses (18 weeks - 11 courses) Basic HEC-2 Reservoir System Analysis Sediment Transport in Rivers and Reservoirs Hydrologic Engineering for Planning Water Quality Modeling Flood Plain Hydrology Onsteady Flow Analysis Flood Plain Management Planning Hydrologic Analysis of Floods Water Supply Hydrology Statistical Methods in Hydrology Workshops (2 weeks - 3 workshops) Flood Damage Analysis Using HEC-FDA Package, 3 days, Pittsburgh, PA Density Floodway, 2 days, Portland, OR World Meterorological Organization Reservoir Control, 4 days, Davis, CA 53-3 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 Video Tapes With the increased numbers of 1/2 inch video tape equipment in the Corps and in other offices, the decision was made to duplicate HEC's currently active library of tapes onto the VHS format. All current tapes are being recorded in the VHS format. Starting in FY 1986, all loan tapes will be available in the 3/4 inch UMATIC and the 1/2 inch VHS format. Planning Analysis Work effforts in FY 1985 were conducted in several areas: Flood Control Planning Damage Computations and Data Management Spatial Data Management Water Supply Planning Dredged-Material Disposal Management Water Surface Profile Accuracy Research Focus continues on the development of practical computer programs and companion user materials for use by field office professional staff. Areas that received particular emphasis this past year include water supply analysis, flood damage computations and data management, spatial data management, and water surface profile accuracy. A significant research milestone was achieved with the publication of Training Document No. 23 "Flood-Damage- Mitigation Plan Selection with Branch-and-Bound Enumeration." Adaptation of this system analysis method to flood control plan formulation resulted from several years of modes research efforts coupled with the specific request by the Los Angeles District for a documented formulation procedure for use in the LACDA study. The method structures a flood control plan formulation problem as a decision tree and then provides an efficient, systematic approach for solving the tree. The use of microcomputers to assist in flood control planning is receiving increased attention. Several important HEC planning computer programs, reported later, are now available for microcomputer applications and increased field office usage is expected. The HEC has adopted the United States Geological Survey (USGS) groundwater simulation model as the tool to analyze groundwater withdrawal and recharge. The HEC has subsequently developed a preprocessor program to aid in automating preparation of input data and has prepared linkages that direct output to graphics display routines to enable effective analysis of model results. Documentation of these enhancements to the USGS model is in preliminary draft form. The software has been made operational on the Corps Harris system. Computer Program Support Significant advances were made in improving HEC's library of computer programs during FY 1985. Thirteen new programs were developed; most serving the water control data communications area. Sixteen HEC programs were upgraded to Fortran 77 standards to make them more transportable to other computers. Fourteen HEC programs were added to the five microcomputer versions already available in FY 1984 from HEC. These nineteen microcomputer programs cover technical areas of rainfallrunoff, river hydraulics, flood flow frequency, flood damage computations, groundwater analysis, small-scale hydropower costs, and spatial data management. Also utility programs for printing summary output reports, editing files, and assisting in preparing data input for reservoir analysis are also available. Several others will be available next year. During FY 1985 HEC distributed about 2,400 computer programs to other Federal, state and local governments, universities, and private industry, both domestic and foreign. HEC actively provides assistance to all its program users. THE DREDGING DIVISION National Dredging Program In FY85, the U.S. Army Corps of Engineers spent $447 million for maintenance and improvements to dredge rivers, channels, and harbors to remove 303 million cubic yards of material. This was a slight decrease from FY84 but still above the average since FY77. Private industry dredged 238 million cubic yards of material for $374 million. Environmental Studies During FY85, the Dredging Division continued to place a high priority on completing required designation studies for the 124 historically-used ocean disposal sites which the Environmental Protection Agency (EPA) designated on an interim basis in 1977. The Corps-established goal for completing all remaining studies to support EPA final designation for these sites is by the end of FY88. To date, EPA has provided final designation for eleven of these sites. The EPA is continuing to place emphasis on completing the supporting environmental documentation required by its policies for final designation of these sites. The Corps designated three new ocean disposal sites necessary for proposed coastal deepening projects, using its own site designation authority provided for in the Ocean Dumping Act. Based on guidance from the Office of the Assistant Secretary of the Army for Civil Works, the Dredging Division further revised 33 CFR 209.145, the Corps regulation specifying environmental compliance requirements for Corps O&M dredging projects. This proposed regulation revision, which will be moved to 33 CFR Parts 335-338 to follow the Corps permit regulation, was published 30 May 1986 in the Federal Register. The Dredging Division continued technical discussions with EPA on the development of consistent and technically appropriate testing procedures and disposal alternative evaluations for projects requiring the removal of highly contaminated bottom sediments. During FY85, the Corps technical protocol on this subject was completed and transmitted to Corps FOAs as national policy guidance. This protocol is also being applied by EPA at two of its major Superfund projects, Commencement Bay, Washington, and New Bedford Harbor, Massachusetts, where dredging is being evaluated as a remedial action alternative for cleaning up highly contaminated bottom sediment "hot spots" within the waterways. The Corps will 53-4 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 continue to refine this protocol based on experience gained at these Superfund sites as well as through other project applications within the Corps. Under a Memorandum of Understanding (MOU) and a broad agreement for cooperation in the field of environmental protection between the United States and Japan, the tenth annual meeting of experts on the management of bottom sediments containing toxic sediments was held in Kyoto, Japan. Papers of particular importance were delivered on dewatering of dredged sediments, long-term management of dredged material disposal and containment activities, rehabilitation of contaminated water bodies, eutrophication, control of dredge-induced turbidity, and effects of contaminated sediments on the water column and the biological community. Developments in recent technology for stabilizing soft, highly organic sediments such as found at Superfund projects have proven particularly useful in ongoing efforts. Revolving Fund The Dredging Division of the Water Resources Support Center allocated $106 million from the Plant Replacement and Improvement Program (PRIP) Fund to all divisions, districts, and field operating activities for FY85. These allocations were for replacements and improvements to structures, dredges, floating plant, mobile and fixed land plant, as well as tools, office furniture and equipment necessary to support Corps-wide missions and activities. The Director of Civil Works has reviewed the use and status of the PRIP and has implemented procedures for more effective management of the Plant Replacement and Improvement Program. Marine Design Center In FY85, the Marine Design Center (MDC) managed 39 floating plant projects on a fully reimbursable basis. The work can be broken down into design and construction contract management. The design work was carried out by the regular staff of naval architects and marine engineers together with architect engineer contract support. Approximately 75 percent of the engineering and design program, which consisted of 26 projects for 14 Corps districts, was contracted out. These projects included modifications and special studies for the hopper dredges ESSAYONS, WHEELER, and McFARLAND; repowering of the dustpan dredged JADWIN and preliminary design of a new dustpan dredge; conceptual design of a SWATH surveyboat and a drift collection vessel, and various other engineering studies. Construction contract management was carried out on 11 projects for nine districts at a total contract value of $9,778,333. New plant delivered to the operators in FY85 consisted of five deck cargo barges, a 100-foot towboat, and a floating crane. A major effort was expended in the design of a diesel electric plant and the purchase of $2 million worth of government-furnished equipment to modernize the dustpan dredge JADWIN. The project will be completed in FY86 at an estimated total project cost of $8.5 million, including scheduled repair and rehabilitation work. The life of the 50-year old vessel will be extended by 15 years with little loss of productive dredging time. The managers of MDC have aggressively pursued work for the U.S. Army Troop Support Command (TROSCOM) and U.S. Navy at Mare Island Naval Shipyard (NAVSEA). It appears that NAVSEA will request the MDC to provide the design and construction management for a new dredge approved for use at Mare Island, San Fransisco Bay, in FY88. Support to Others The Dredging Division prepared a cost-estimate, construction methodology, geotechnical assessment and environmental review of the Gaillard Cut Widening Project for the Panama Canal Commission. The final report on this effort will be provided to the Commission during the last quarter of 1986. 53-5 APPENDIX A FLOOD CONTROL RESERVOIRS OPERABLE SEPTEMBER 30, 1985 Permanent Pool Characteristics of Dam Cal. Year Total (Acreage) Community Placed in Storage or No Project- Height Length Name River Basin Stream in Vicinity Useful Op. (Acre-Ft.) Pool (NPP) Functions Type (Feet) (Feet) ALASKA Chena River Lakes ARIZONA Adobe Alamo Cave Buttes Dreamy Draw New River Painted Rock Tat Momolikot Whitlow Ranch ARKANSAS Yukon-Kuskokwim Gila Colorado Gila Gila Gila Gila Gila Gila Blakely Mountain Dam Ouachita Blue Mountain Arkansas DeGray Ouachita DeQueen Red Dierks Red Gillham Red Millwood Red Narrows Dam Ouachita Nimrod Arkansas CALIFORNIA Black Butte Sacramento Brea Santa Ana Buchanan Dam- H.V. Eastman Lake San Joaquin Carbon Canyon Santa Ana Coyote Valley Russian Dry Creek (Warm Springs) Lake and Channel Russian Farmington San Joaquin Fullerton Santa Ana Hansen Los Angeles Harry L. Englebright Sacramento Hidden Dam-Hensley Lake San Joaquin Isabella San Joaquin Lopez Los Angeles Martis Creek Sacramento Merced County Stream Group: Bear San Joaquin Burns San Joaquin Mariposa San Joaquin Owens San Joaquin Mojave River Mojave New Hogan San Joaquin North Fork Sacramento Pine Flat San Joaquin Prado Santa Ana San Antonio Santa Ana Santa Fe San Gabriel Sepulveda Los Angeles Success San Joaquin Terminus San Joaquin Whittier Narrows San Gabriel COLORADO Bear Creek Chatfield Cherry Creek John Martin Trinidad CONNECTICUT Black Rock Colebrook River Hancock Brook Hop Brook Mansfield Hollow Northfield Brook Thomaston West Thompson IDAHO Lucky Peak Missouri Missouri Missouri Arkansas Arkansas Housatonic Connecticut Housatonic Housatonic Thames Thames Housatonic Thames Columbia Chena River Fairbanks Skunk Creek Phoenix Bill Williams River Wenden Cave Creek Phoenix Dreamy Draw Phoenix New River Phoenix Gila River Gila Bend Santa Rosa Wash Casa Grande Queen Creek Superior Ouachita Hot Springs Petit Jean River Paris Caddo Arkadelphia Rolling Fork River DeQueen Saline River Dierks Cossatot River Gillham Little River Ashdown Little Missouri Murfreesboro Fourche La Fave River Plainview Stony Creek Orland Brea Creek Fullerton Chowchilla River Chowchilla Carbon Canyon River Brea East Fork Russian River Ukiah Dry Creek Healdsburg Littlejohn Creek Farmington East Fullerton Creek Fullerton Big Tujunga Wash Los Angeles Yuba River Marysville Fresno River Madera Kern River Bakersfield Pacoima Wash San Fernando Martis Creek Reno Bear Creek Merced Burns Creek Merced Mariposa Creek Merced Owens Creek Merced Mojave Victorville Calaveras Valley Springs American River Auburn Kings River Piedra Santa Ana River Corona San Antonio Creek Upland San Gabriel River Duarte Los Angeles River Van Nuys Tule River Porterville Kaweah River Visalia San Gabriel River and Rio Hondo El Monte Bear Creek Denver South Platte River Denver Cherry Creek Denver Arkansas River Lamar Purgatoire River Trinidad Branch Brook Thomaston West Branch, Farmington River Riverton Hancock Brook Plymouth Hop Brook Middlebury Natchaug River Willimantic Northfield Brook Thomaston Naugatuck River Thomaston Quinebaug Thompson Boise River Boise 1981 2,000 NPP FR Earth 1982 18,350 1968 1.046.310 1979 46,600 1973 320 1985 43,520 1959 2,491,700 1974 198,550 1960 35,590 1955 2.768,500 1947 257,900 1971 881,900 1977 136,100 1975 96,800 1975 221,800 1966 1,854,930 1949 407.900 1942 336,010 1963 160,000 1942 4,010 1975 150,000 1961 6,610 1959 122,500 1983 381,000 1952 52,000 1941 760 1940 25.450 1941 69,000 1975 90,000 1953 570,000 1954 440 1971 20,400 1954 7.700 1950 7,000 1948 15,000 1949 3,600 1971 89,670 1963 325,000 1939 14,700 1954 1.000,000 1941 196,240 1956 7,700 1948 32,110 1941 17,430 1960 85,000 1961 150,000 1957 35,150 1978 30,810 1974 231,429 1950 93,920 1943 615,500 1977 123,500 1970 8,700 1969 97,700 1960 4,030 1968 6,970 1952 52,000 1965 2,430 1960 42,000 1965 26,800 1956 306,000 NPP FR Earth 560 FRWX Earth NPP FRX Earth NPP FRX Earth NPP F Earth NPP FRWX Earth NPP FWX Earth NPP FX Earth 50 40,200 109 2,275 283 975 109 2,275 50 448 104 2,320 181 4,780 75.5 12,500 149 837 20,900 FP Earth 235 1,100 2,910 FRWX Earth 115 2,800 6,400 FPQRS Earth 243 3,400 1,680 FSQRW Earth 160 2,360 1,360 FSRAW Earth & Rock 153 2,500 1.370 FSQW Earth & Rock 160 1,750 29.200 FSW Earth 88 17,554 2,500 FP Concrete 175 941 3,550 FSWX Concrete 97 1,012 770 FIRX Earth 156 2,970 NPP FRX Earth 87 1,765 470 FIRW Earth & Rock 205.5 1,800 NPP FRX Earth 99 2,610 1,700 FRX Earth 160 3,500 500 FRSW Earth 319 3,000 NPP F Earth 60 7,800 NPP FRX Earth 46 575 120 FRWX Earth 97 10,475 400 DR Concrete 280 1,142 5,000 FIRW Earth 163 5,730 1.850 FIRW Earth 185 4,952 NPP FX Earth 50 1,300 71 FSR Earth 113 2,670 NPP F Earth 92 1,830 NPP F Earth 55 4,075 NPP F Earth 88 1,330 NPP F Earth 75 790 NPP FRWX Earth 200 2,200 715 FIRX Earth & Rock 210 1,960 280 DR Concrete 155 620 NPP FIRX Concrete 429 1,820 NPP FRX Earth 106 2,280 NPP FX Earth 160 3,850 NPP FRX Earth 92 23,800 NPP FRX Earth 57 15,444 400 FIRX Earth 142 3,490 345 FIRX Earth 250 2,375 NPP FRWX Earth 56 16,960 109 FRX Earth 180 5,300 1,412 FRX Earth 148 12,500 852 FRX Earth 141 14,300 1,844 FIR Concrete & Earth 106 13,274 280 FIRX Earth 200 6,610 20 FR Earth 760 FRSX Earth 40 FRW Earth 21 FR Earth 450 FRW Earth 8 FRW Earth NPP F Earth 200 FRW Earth 2,850 FIR Earth 154 933 223 1,300 57 630 97 520 68 12,420 118 810 142 2,000 70 2,550 250 1,700 A-1 APPENDIX A (Continued) FLOOD CONTROL RESERVOIRS OPERABLE SEPTEMBER 30, 1985 Permanent Pool Characteristics of Dam Cal. Year Total (Acreage)' Community Placed in Storage or No Project Height Length Name River Basin Stream in Vicinity Useful Op. (Acre-Ft.) Pool (NPP) Functions Type (Feet) (Feet) ILLINOIS Carlyle Farmdale Fondulac Shelbyville Rend Lake INDIANA Brookville Cagles Mill Cecil M. Harden Huntington Mississinewa Monroe Patoka Salamonie IOWA Coralville Rathbun Red Rock Saylorville KANSAS Clinton Council Grove El Dorado Elk City Fall River Hillsdale John Redmond Kanopolis Marion Melvern Milford Pearson Skubitz Big Hill Perry Pomona Toronto Tuttle Creek Wilson KENTUCKY Barren River Buckhorn Carr Fork Cave Run Dewey Fishtrap Grayson Green River Martins Fork Paintsville Nolin Rough River Taylorsville LOUISIANA Bayou Bodcau Caddo Lake Wallace Lake MARYLAND Bloomington Lake MASSACHUSETTS Barre Falls Birch Hill Buffumville Charles River Natural Valley Storage Conant Brook East Brimfield Hodges Village Knightville Upper Mississippi Upper Mississippi Upper Mississippi Upper Mississippi Upper Mississippi Ohio Ohio Ohio Ohio Ohio Ohio Ohio Ohio Upper Mississippi Missouri Upper Mississippi Upper Mississippi Missouri Arkansas Arkansas Arkansas Arkansas Missouri Arkansas Missouri Arkansas Missouri Missouri Arkansas Missouri Missouri Arkansas Missouri Missouri Ohio Ohio Ohio Ohio Ohio Ohio Ohio Ohio Cumberland Ohio Ohio Ohio Ohio Red Red Red Potomac Connecticut Connecticut Thames Charles Connecticut Connecticut Connecticut Connecticut Kaskaskia River Farm Creek Fondulac Creek Kaskaskia River Big Muddy River East Fork of Whitewater River Mill Creek Raccoon Creek Wabash River Mississinewa Salt Creek Patoka River Salamonie Carlyle East Peoria East Peoria Shelbyville Benton Brookville Terre Haute Rockville Huntington Peru Harrodsburg Ellsworth Wabash Iowa River Iowa City Chariton River Centerville Des Moines River Des Moines Des Moines River Des Moines Wakarusa River Lawrence Grand (Neosho) Council Grove Walnut River El Dorado Elk River Independence Fall River Fall River Big Bull Creek Kansas City Grand (Neosho) Burlington Smoky Hill River Salina Cottonwood River Marion Marias Des Cygnes Melvern Republican River Junction City Big Hill Creek Cherryvale Delaware River Perry 110 Mile Creek Pomona Verdigris River Toronto Big Blue River Manhattan Saline River Wilson Barren River Middle Fork of Kentucky River Carr Fork Licking River Johns Creek Levisa Fork, Big Sandy River Little Sandy Green River Martins Fork Paint Creek Nolin River Rough River Salt River Bayou Bodcau Cypress Bayou Cypress Bayou North Branch Potomac River Ware River Millers River Little River Charles River Conant Brook Quinebaug River French River Westfield River Glasgow Buckhorn Hazard Farmers Paintsille Pikeville Grayson Campbellsville Harlan Paintsville Kyrock Leitchfield Taylorsville Shreveport Shreveport Shreveport Barnum Barre So. Royalston Charlton Millis Monson Fiskdale Oxford Huntington 1967 983,000 1951 15,500 1951 3.780 1970 684,000 1970 294,000 1974 359,600 1952 228,120 1960 132,800 1969 153,100 1967 368,400 1964 441,000 1978 301,600 1966 263,600 1958 492,000 1969 552,000 1969 1,830,000 1975 602,000 1977 397,200 1964 112,265 1981 236,200 1966 284,300 1949 256,400 1981 160,000 1964 630,250 1948 450,000 1968 143,850 1972 363,000 1965 1,160,000 1981 40,600 1969 770,000 1963 230,000 1960 200,800 1962 2,346,000 1964 776,000 1964 815,200 1960 168,000 1976 47,700 1974 614,100 1949 93,000 1968 164,360 1967 118,990 1969 723,200 1978 21,000 1983 73,500 1963 609,400 1958 334,400 1983 291,670 1949 357,300 1971 175,000 1946 88,300 1981 130,900 1958 24,000 1941 49,900 1958 12,700 1983 35,000 1966 3,740 1960 30,000 1959 12,800 1941 49,000 26,000 FSNRWA Earth NPP F Earth NPP F Earth 11,100 FSNRW Earth 18,900 FQRSW Earth 67 6,570 80 1,275 67 1,000 108 3,000 54 10,600 2,250 FRSW Earth & Rock 182 3,000 1,400 FRX Earth 150 950 1,100 FRX Earth 117 1,790 500 FRW Earth 91 5,332 1,100 FRW Earth 137 8,100 3,280 FARS Earth 93 1,400 2,010 FRSQW Earth & Rock 84 1,550 976 FRW Earth 133 6,100 1,820 FARW Earth 11,000 FNRWXQ Earth 8,950 FARWQ Earth 74,000 FARWQ Earth 100 1,400 86 10,600 110 5,676 125 6,750 7,000 FSWAXR Earth 114 9,250 3,235 FSQR Earth 96 6,500 8,000 FSQR Earth 99 20,930 4,450 FSQ Earth 107 4,840 2,350 FSX Earth 94 6,015 4,580 FSQR Earth 75 11,600 9,280 FSQR Earth 86.5 21,790 3,815 FRWX Earth 131 15,360 6,200 FRQS Earth 67 8,375 6,930 FRQWX Earth 98 9,700 15,600 FRSXWQ Earth & Rock 126 6,300 1,240 FSR Earth 83 3,870 12,200 FRSXW Earth & Rock 95 7,750 4,000 FRSWXQ Earth & Rock 85 7,750 2,660 FX Earth 90 4,712 15,800 FRWXQAN Earth & Rock 157 7,500 9,000 FIRWXNA Earth 160 5,600 4,340 FARS Earth 146 3,970 550 FR Earth 162 1,020 530 FQRW Earth & Rock 130 720 6,790 FQRW Earth & Rock 148 2,740 1,100 FARW Earth 118 913 569 FARW Rock 195 1,100 1,050 FQRW Earth & Rock 120 1,460 5,070 FRSQW Earth & Rock 142 2,350 578 FQ Concrete 97 574 261 FQRW Earth & Rock 160 1,600 2,890 FAR Earth & Rock 174 990 2,180 FRX Earth & Rock 124 1,530 1,625 FQRW Earth & Rock 164 1,280 NPP FRW Earth 32,700 NFRS Concrete & Earth 2,300 FR Earth 76 12,850 3,600 48 4,934 952 FQRS Earth & Rock 296 2,130 NPP FRW Earth & Rock 62 885 NPP FRW Earth & Rock 56 1,400 200 FRW Earth & Rock 66 3,255 NPP F Nonstructural - - NPP F Earth & Rock 85 1,050 360 FRW Earth & Rock 55 520 NPP FRW Earth & Rock 55 2,140 NPP FRW Earth & Rock 160 1,200 A-2 APPENDIX A (Continued) FLOOD CONTROL RESERVOIRS OPERABLE SEPTEMBER 30, 1985 Permanent Pool Characteristics of Dam Cal. Year Total (Acreage)' Community Placed in Storage or No Project Height Length Name River Basin Stream in Vicinity Useful Op. (Acre-Ft.) Pool (NPP) Functions Type (Feet) (Feet) MASSACHUSETTS (Continued) Littleville Tully West Hill Westville MINNESOTA Big Stone Lake- Whetstone River Lac Qui Parle Chippewa River Lac Qui Parle Marsh Lake Orwell Red Lake MISSISSIPPI Arkabutla Lake Enid Lake Grenada Lake Okatibbee Sardis Lake MISSOURI Clearwater Long Branch Pomme de Terre Smithville Wappapello NEBRASKA Harlan County Papillion Creek and Tributaries: Glenn Cunningham (Site 11) Standing Bear Lake (Site 16) Salt Creek & Tributaries: Olive Creek (Site 2) Blue Stem (Site 4) Wagon Train (Site 8) Stagecoach (Site 9) Yankee Hill (Site 10) Conestoga (Site 12) Twin Lake (Site 13) Pawnee (Site 14) Holmes Park Lake (Site 17) Branched Oak (Site 18) NEW HAMPSHIRE Blackwater Edward MacDowell Franklin Falls Hopkinton-Everett Otter Brook Surry Mountain NEVADA Mathews Canyon Pine Canyon NEW MEXICO Abiquiu Cochiti Conchas Connecticut Connecticut Blackstone Thames Upper Mississippi Upper Mississippi Upper Mississippi Upper Mississippi Red River of the North Red River of the North Lower Mississippi Lower Mississippi Lower Mississippi Pascagoula Lower Mississippi White Grande Chariton Missouri Missouri Lower Mississippi Missouri Missouri Missouri Missouri Missouri Missouri Missouri Missouri Missouri Missouri Missouri Missouri Missouri Merrimack Merrimack Merrimack Merrimack Merrimack Connecticut Connecticut Colorado Colorado Middle Branch, Westfield River Tully River West River Quinebaug River Minnesota River Chippewa River Minnesota River Minnesota River Otter Tail River Red Lake River Coldwater River Yocona River Yalobusha River Okatibbee Creek Little Tallahatchie River Black River Little Chariton Pomme de Terre River Little Platte River St. Francis River Chester Fryville Uxbridge Sturbridge Ortonville Montevideo Montevideo Montevideo Fergus Falls Red River Arkabutla Enid Grenada Meridian Sardis Piedmont Macon Hermitage Smithville Wappapello 1965 1949 1960 1961 1973 1950 1950 1950 1953 1951 1943 1951 1954 1969 1940 1948 1980 1961 1982 1941 32,400 22,000 12,350 11,100 45,000 (2) 122,800 35,000 14,100 2,680,000 525,300 660,000 1,337,400 142,400 1,570,000 413,700 65,000 650,000 246,500 613,200 275 FRWS 300 FRW NPP FRW 23 FRW 12,700 NPP 6,500 5,100 210 279,000 FRW FRWX FRWX FRWX FARS FARSX 5,100 F Earth & Rock 6,100 F Earth & Rock 9,800 F Earth & Rock 1,280 FQSR Earth 10,700 F Earth & Rock 1,630 FRWX 2,430 FRSQW 7,820 FRWX 7,190 FSQRW 4,100 FR Republican River Republican City 1952 850,000 13,600 FIRWX Earth & Rock 107 11,827 Knight Creek Trib. of Big Papillion Creek S. Trib. Olive Br. Creek N. Trib. Olive Br. Creek N. Trib. Hickman Creek S. Trib. Hickman Creek Cardwell Creek Holmes Creek Middle Creek N. Middle Creek Antelope Creek Oak Creek Blackwater River Nubanusit Brook Pemigewasset River Contoocook River Piscataquog River Otter Brook Ashuelot River Omaha Omaha Kramer Sprague Holland Hickman Denton Denton Pleasantdale Emerald Lincoln Raymond Webster West Peterborough Franklin West Hopkinton East Weare Keene Keene Mathews Canyon Caliente Pine Canyon Caliente Rio Grande Rio Grande Arkansas Rio Chama Rio Grande Canadian River Abiquiu Pena Blanca Tucumcari 1975 1973 1964 1963 1963 1964 1966 1964 1966 1965 1963 1968 1941 1950 1943 1962 1962 1958 1941 17,910 392 FQRX Earth 5,220 137 FRX Earth 5,470 10,260 9,280 6,640 7,560 10,640 8,080 29,520 6,510 97,560 46,000 12,800 154,000 71,500 87,500 18,300 32,500 174 315 303 196 208 230 255 728 100 1,780 NPP NPP NPP 200 120 85 265 FR FR FR FR FR FR FR FR FR FR FRW FRW FRW FRW FRW FRW FRW 1957 6,270 NPP FX Earth 1957 7,750 NPP FX Earth 1963 1,212,000 NPP FXS Earth 1975 596,300 1,200 FRWX Earth 1939 529,000 3,000 FI Concrete & Earth A-3 Earth & Rock Earth & Rock Earth & Rock Earth & Rock Earth Earth & Rock Earth & Rock Earth & Rock Earth & Rock Earth & Rock 1,164 62 51 78 25 23.3 21 19.5 47 15.5 81 99 102 67 117 154 71 155 95 109 1,360 1,570 2,400 560 13,700 17,975 4,100 11,800 1,355 36,500 11,500 8,400 13,900 6,543 15,300 4,225 3,800 4,630 4,200 2,700 Earth & Rock Earth Earth & Rock Earth Earth & Rock 67 70 45 57 52 48 52 63 58 65 55 70 Earth Earth Earth Earth Earth Earth Earth Earth Earth Earth Earth Earth Earth Earth Earth Earth Earth 1,940 1,460 3,020 2,760 1,650 2,250 3,100 3,000 2,075 5,000 7,700 5.200 1,150 1,030 1,740 790 2,000 1,288 1,670 75 67 140 76 115 133 86 71 800 92 884 325 251 200 1,540 28,300 19,400 APPENDIX A (Continued) FLOOD CONTROL RESERVOIRS OPERABLE SEPTEMBER 30, 1985 Permanent Pool Characteristics of Dam Cal. Year Total (Acreage)' Community Placed in Storage or No Project Height Length Name River Basin Stream in Vicinity Useful Op. (Acre-Ft.) Pool (NPP) Functions Type (Feet) (Feet) NEW MEXICO (Continued) Galisteo Rio Grande Jemez Canyon Rio Grande Two Rivers: Diamond "A" Dam Rio Grande Rocky Dam Rio Grande Santa Rosa Dam & Pecos Reservoir NEW YORK Almond Arkport East Sidney Mount Morris Whitney Point NORTH CAROLINA B. Everett Jordan Falls W. Kerr Scott NORTH DAKOTA Baldhill Bowman-Haley Homme Pipestem OHIO Susquehanna Susquehanna Susquehanna Genesee Susquehanna Cape Fear Neuse Yadkin-Pee Dee Galisteo Creek Jemez River Rio Hondo Rocky Arroyo Pecos Canacadea Creek Canisteo Creek Ouleout Creek Genesee River Otselic River New Hope Neuse Yadkin Albuquerque Bernalillo Roswell Santa Rosa Hornell Hornell Sidney Mount Morris Binghamton Durham Raleigh Wilkesboro Red River of the North Sheyenne River Valley City Missouri North Fork, Grand River Haley Red River of the North South Branch of Park River Park River James River Pipestem Creek Jamestown Alum Creek Ohio Berlin Ohio Caesar Creek Ohio Clarence J. Brown Ohio Deer Creek Ohio Delaware Ohio Dillon Ohio Michael J. Kirwan Ohio Mosquito Creek Ohio Muskingum River Reservoirs: Atwood Ohio Beach City Ohio Bolivar Ohio Charles Mill Ohio Clendening Ohio Dover Ohio Leesville Ohio Mohawk Ohio Mohicanville Ohio Piedmont Ohio Pleasant Hill Ohio Senecaville Ohio Tappan Ohio Wills Creek Ohio North Branch, Ohio Kokosing River Lake Paint Creek Ohio Tom Jenkins Ohio West Fork Mill Creek Ohio William H. Harsha Ohio OKLAHOMA Birch Canton Copan Fort Supply Greak Salt Plains Heyburn Hugo Hulah Kaw Oologah Optima Pine Creek Sardis Skiatook Waurika Wister Arkansas Arkansas Arkansas Arkansas Arkansas Arkansas Red Arkansas Arkansas Arkansas Arkansas Red Red Arkansas Red Arkansas Alum Creek Mahoning River Caesar Creek Buck Creek Deer Creek Olentangy River Licking River West Branch, Mahoning River Mosquito Creek Africa Deerfield Wilmington Springfield New Holland Delaware Zanesville Newton Falls Cortland Indian Fork New Cumberland Sugar Creek Beach City Sandy Creek Bolivar Black Fork Mufflin Brushy Fork Tippecanoe Tuscarawas River Dover McGuire Creek Leesville Walhonding River Nellie Lake Fork Mohicanville Stillwater Creek Piedmont Clear Fork Perrysville Seneca Fork Senecaville Little Stillwater Creek Tappan Wills Creek Conesville North Branch of Fredericktown Kokosing River Paint Creek New Petersburg East Branch, Gloucester Sunday Creek Mill Creek Mount Healthy Little Miami River Williamsburg Birch Creek Barnsdall North Canadian River Canton Little Caney River Copan Wolf Creek Fort Supply Salt Fork, Cherokee Arkansas River Polecat Creek Sapulpa Kiamichi River Hugo Caney River Caney Arkansas River Ponca City Verdigris River Oologah North Canadian River Hardesty Little River Wright City Jackfork Creek Clayton Hominy Creek Skiatook Beaver Creek Waurika Poteau River Wister 1970 89,000 1953 102,700 1963 168,000 1979 447,000 1949 14,800 1939 7,900 1950 33,550 1952 337,000 1942 86,440 1982 778,000 1983 335,600 1963 153,000 1950 70,000 1967 92,980 1951 3,650 1974 146,880 1975 134,800 1943 91,200 1978 242,200 1974 63,700 1968 102,500 1951 132,000 1961 273,000 1966 78,700 1944 104,100 1937 49,700 1937 71,700 1938 149,600 1936 88,000 1937 54,000 1938 203,000 1937 37,400 1937 285,000 1936 102,000 1937 65,000 1938 87,700 1937 88,500 1936 61,600 1937 196,000 1973 14,900 1972 145,000 1951 26.900 1952 11,380 1978 284,500 1977 58,200 1948 377,100 1983 227,700 1942 100,700 1941 271,400 1950 55,030 1974 966,700 1951 289,000 1976 1,348,000 1963 1,519,000 1978 229,500 1969 465,780 1983 429,600 1985 300,200 1977 343,500 1949 427,900 NPP FX Earth NPP FX Earth NPP FX Earth NPP FIX Earth 124 FRW Earth NPP F Earth 210 FRW Concrete & Earth 170 FR Concrete 1,200 FRW Earth 14,300 FQRSWX Earth 11.300 FQRSWX Earth 1,470 FARSX Earth 325 FARS Earth 1,750 FSRWX Earth 51 FARS Earth 885 FRWX Earth 158 2,820 135 780 98 4,885 118 2,940 212 1,950 90 1,260 113 1,200 130 2,010 210 1,028 95 4,900 112 1,330 92 1,915 148 1,740 61 1,650 79 5.730 67 865 108 4,000 348 FRSW Concrete 93 10,000 & Earth 240 FARSWQ Concrete 96 5,750 & Earth 13,300 FRSQW Earth & Rock 165 2,750 1,010 FQRW Earth & Rock 72 6,620 727 FRW Earth 93 3,880 950 FARWX Earth 92 18,600 1,325 FRWX Earth 118 1,400 580 FAQRSW Earth 83 9,900 700 FARSWQ Earth 47 5,650 1,540 FRX Earth 65 3,700 420 FRX Earth 64 5,600 NPP FR Earth 87 6,300 1,350 FRX Earth 48 1,390 1,800 FRX Earth 64 950 350 FRX Concrete 83 824 1,000 FRX Earth 74 1,694 NPP FR Earth 111 2,330 NPP FR Earth 46 1,220 2,270 FRX Earth 56 1,750 850 FRX Earth 113 775 3,550 FRSX Earth 45 2,350 2,350 FRX Earth 52 1,550 900 FRX Earth 87 1,950 98 FRW Earth 71 1,400 710 FRSQW Earth & Rock 118 700 394 FRSWX Concrete 84 944 200 FRX Earth 100 1,100 18,760 FRSQW Earth 200 1,450 1,137 FSQRW Earth 7,910 FSI Earth 4,850 FSQRW Earth 1,820 FSX Earth 8,690 FRWX Earth 880 FRWXS Earth 13,250 FSQRW Earth 3,570 FSAX Earth 17,040 FSQRW Earth 29,460 FSN Earth 5,340 FSRW Earth 3,750 FSQW Earth 14,360 FSRW Earth 10,190 FSQRW Earth 10,100 FISQWR Earth 5,360 FSAX Earth 97 3,193 73 15,140 70 7,730 85 12,225 68 6,010 89 2,920 101 10,200 94 5,200 125 9,466 137 4,000 120 15,200 124 7,712 81 14,138 143 3,590 106 16,600 99 5,700 A-4 APPENDIX A (Continued) FLOOD CONTROL RESERVOIRS OPERABLE SEPTEMBER 30, 1985 Permanent Pool Characteristics of Dam Cal. Year Total (Acreage)' Community Placed in Storage or No Project Height Length Name River Basin Stream in Vicinity Useful Op. (Acre-Ft.) Pool (NPP) Functions Type (Feet) (Feet) OREGON Applegate Blue River Cottage Grove Dorens Fall Creek Fern Ridge Willow Creek Rogue River Columbia Columbia Columbia Columbia Columbia Columbia Applegate River Blue River Coast Fork. Willamette River Row River Middle Fork, Willamette River Long Tom River Willow Creek PENNSYLVANIA Alvin R. Bush Susquehanna Kettle Creek Aylesworth Creek Susquehanna Aylesworth Creek Beltaville Delaware Pohopoco Blue Marsh Delaware Tulephocken Conemaugh Ohio Conemaugh River Cowanesque Susquehanna Cowanesque River Crooked Creek Ohio Crooked Creek Curwenaville Susquehanna River West Branch, Susquehanna River East Branch, Ohio East Branch, Clarion River Clarion River Foster Joseph Sayers Susquehanna Bald Eagle Creek Francis E. Walter Delaware Lehigh River (Bear Creek) Gen. Edgar Jadwin Delaware Dyberry Creek Indian Rock Susquehanna Codorus Creek Kinzua Ohio Allegheny River Loyalhanna Ohio Loyalhanna Creek Mahoning Creek Ohio Mahoning Creek Prompton Delaware Lackawaxen River Raystown Susquehanna Raystown Branch, Junista River Shenango Ohio Shenanago River Stillwater Susquehanna Lackawanna River Tioga-Hammond Lakes Susquehanna Tioga River -Hammond Lakes Susquehanna Crooked Creek Tionesta Ohio Tionesta Creek Union City Ohio French Creek Woodcock Creek Ohio French Creek Youghiogheny River Ohio Youghiogheny River SOUTH DAKOTA Cold Brook Missouri Cold Brook Cottonwood Springs Missouri Cottonwood Springs Creek Lake Traverse: Reservation Control Red River of the North Bois de Sioux River Dam White Rock Red River of the North Bois de Sioux River TEXAS Addicks San Jacinto Aquilla Brazos Bardwell Trinity Barker San Jacinto Belton Brazos Benbrook Trinity Canyon Guadalupe Ferrells Bridge Dam- Red Lake O' the Pines Granger Dam and Lake Brazos Grapevine Trinity Hords Creek Colorado Lake Kemp Red Lavon Trinity Lewisville Trinity Navarro Mills Trinity North San Gabriel Dam, Brazos Lake Georgetown Medford Blue River Cottage Grove Cottage Grove Eugene Eugene Heppner Renovo East Jermyn Lehighton Reading Saltsburg Lawrenceville Ford City Clearfield Wilcox Blanchard Wilkes-Barre Honesdale York Warren Saltsburg New Bethlehem Honesdale Huntingdon Sharpsville Forest City Tioga Tioga Tionesta Union City Meadville Confluence Hot Springs Hot Springs Wheaton Wheaton South Mayde Creek Addicks Aquilla Creek Hillsboro Waxahachie Creek Ennis Buffalo Bayou Barker Leon River Belton Clear Fork, Trinity River Fort Worth Guadalupe New Braunfels Cypress Creek Jefferson San Gabriel River Granger Denton Creek Grapevine Hords Creek Coleman Wichita River Wichita Falls East Fork, Trinity River Fort Worth Elm Fork. Trinity River Lewisville Richland Creek Corsicana North Fork. Georgetown San Gabriel River 1981 82,000 1968 85,000 1942 30,060 1949 70,500 1965 115,000 1941 110,000 1983 13,250 1962 75,000 1970 1,760 1971 68,250 1979 500,000 1952 274,000 1980 89,000 1940 93,900 1965 124,200 1952 84,300 1969 99,000 1961 110,000 1959 24,500 1942 28,000 1965 1,180,000 1942 95,300 1941 74,200 1960 52,000 1973 762,000 1966 191,400 1960 12,000 1979 62,000 1979 63,000 1940 133,400 1970 47,640 1973 20,000 1943 254,000 1953 7,200 1970 8,385 1941 164,500 1941 85,000 1948 204,500 1983 146,000 1965 140,000 1945 207,000 1954 1,097,600 1952 258,600 1964 740,900 1959 842.100 1980 244,200 1952 425,500 1948 25,310 1972 502,900 1953 748,200 1954 989,700 1962 212,200 1980 130.800 988 AFIQRSW Gravel Em- 242 1,300 bankment 975 FINR Earth 319 1,329 1,155 FINR Concrete 114 2,110 & Earth 1,885 FINR Concrete 145 3,352 & Earth 1,865 FINR Rockfill 193 5,100 & Concrete 10,305 FINR Rockfill 49 6,624 & Concrete 96 FRN Roller 160 1,780 Compacted Concrete 160 FRW Earth & Rock 165 1,350 NPP F Earth & Rock 90 1,270 947 FQRSW Earth & Rock 170 4,200 22,900 FAQRS Earth 98 1,775 300 FW Concrete 137 1,265 & Earth 410 FR Earth & Rock 151 3,100 350 FRW Earth 143 1,480 790 FR Earth 131 2,850 90 FARQW Earth 184 1,725 1,730 FRW Earth 100 6,835 90 FNRW Rockfill 263 3,500 NPP F Earth 109 1,255 NPP FRW Earth 83 1,000 1,900 PFAQRW Concrete 177 1,877 & Earth 210 FRW Concrete 114 960 & Earth 170 FRW Concrete 162 926 290 FNRW Earth 140 1,230 8,300 FRW Earth & Rock 225 1,700 1,910 FAQRW Concrete 68 720 85 FS Earth 77 1,700 470 FR Earth & Rock 140 2,738 680 FR Earth & Rock 122 6,000 480 FRW Earth 154 1,050 NPP F Earth 88 1,420 118 FQRA Earth 90 4,650 450 FARWQ Earth 184 1,610 36 FRWX Earth 41 FRWX Earth 10,925 FRX Earth 6,500 FRX Earth 127 925 123 1,190 14 9,100 16 14,400 NPP FX Earth 49 61,166 3,280 FSX Earth 104.5 11,890 3,570 FRSX Earth 82 15,400 NPP FX Earth 37 72,844 12,300 FIRSX Earth 192 5,524 3,770 FNRXA Earth 130 9,130 8,240 FRSX Earth 224 6,830 18.700 FRS Earth 97 10,600 4,400 FRSWX Earth 115 16,320 7,280 FNRSXA Earth 137 12,850 510 FARSX Earth 91 6,800 15,590 FX Earth & Rock 115 8,890 21,400 FRSX Earth 81 19,483 23,280 FRSX Earth 125 32,888 5,070 FRSX Earth 82 7,570 1.310 FRSWX Rock 164 6.700 A-5 APPENDIX A (Continued) FLOOD CONTROL RESERVOIRS OPERABLE SEPTEMBER 30, 1985 Permanent Pool Characteristics of Dam Cal. Year Total (Acreage)' Community Placed in Storage or No Project Height Length Name River Basin Stream in Vicinity Useful Op. (Acre-Ft.) Pool (NPP) Functions Type (Feet) (Feet) TEXAS (Continued) O. C. Fisher Pat Mayse Proctor Somerville Stillhouse Hollow Waco Wright Patman VERMONT Ball Mountain North Hartland North Springfield Townshend Union Village VIRGINIA John W. Flannagan Gathright Dam & Lake Moomaw North Fork of Pound River WASHINGTON Howard A. Hanson Mill Creek Mud Mountain Wynoochee WEST VIRGINIA Beech Fork Bluestone Burnsville East Lynn R. D. Bailey Summersville Lake Sutton Tygart River WISCONSIN Eau Galle Colorado Red Brazos Brazos Brazos Brazos Red Connecticut Connecticut Connecticut Connecticut Connecticut Ohio James Ohio Green Columbia Puyallup Chehalis Ohio Ohio Ohio Ohio Ohio Ohio Ohio Ohio Chippewa North Concho River Sanders Creek Leon River Yegua Creek Lampasas River Bosque River Sulphur River West River Ottauguechee River Black River West River Ompompanoosuc River Pound River Jackson North Fork, Pound River Green River Mill Creek White River Wynoochee River Beech Fork New River Little Kanawha Twelve Pole Creek Guynabdot River Gauley River Elk River Tygart River Eau Galle San Angelo Paris Comanche Somerville Belton Waco Texarkana Jamaica North Hartland Springfield Townshend Union Village Haysi Alleghany Pound Kanaskat Walla Walla Enumclaw Montesano Lavalette Hinton Burnsville East Lynn Justice Summersville Sutton Grafton Spring Valley 1952 1967 1963 1967 1968 1965 1957 1961 1960 1960 1961 1950 1963 1979 1966 1961 1942 1953 1972 1977 1952 1977 1970 1979 1965 1960 1938 396,400 189,100 374,200 507,500 630,400 726,400 2,654.300 54.600 71,420 51,067 33,700 38,000 145,700 123,739 11,293 106,000 8,300 106,000 70,000 37,540 631,000 65,400 82,500 203,700 413,800 265,300 287,700 5,440 5,993 4,610 11,460 6,430 7,270 20,300 75 220 290 100 NPP FRSX FRSX FRSX FRSX FRSX FRSX FRSX FRW FRW FRW FRW FRW Earth Earth Earth Earth Earth Concrete & Earth Earth Concrete & Earth Concrete & Earth Concrete & Earth Concrete & Earth Concrete & Earth 310 FAQR Concrete & Earth 2,532 FQR Earth & Rock 106 FR Rock 1,600 FAS 225 FR NPP FR 1,150 FSARI 450 1,800 550 823 440 407 270 620 1969 43,600 FRW FRWX FQRW FQRW FQRW FANR FARWX FNAR Rock Earth Rock Concrete & Earth Earth Concrete Earth & Rock Earth & Rock Earth & Rock Rock Concrete Concrete 150 FR Earth A-6 128 40,885 96 7,080 86 13,460 80 26,175 200 15,624 140 24,618 100 18,500 265 915 185 1,520 120 2,940 133 1,700 170 1,100 250 960 257 1,172 122 600 235 675 145 3,200 425 700 177 1,700 86 1,080 180 2,048 89 1,400 122 650 310 1,397 390 2,280 220 1,178 230 1,921 122 1,600 FLOOD CONTROL RESERVOIRS CONSTRUCTED OR CONTRIBUTED TO BY CORPS OF ENGINEERS BUT OPERATED BY OTHERS SEPTEMBER 30, 1985 Permanent Pool Characteristics of Dam Cal. Year Total (Acreage)' Community Placed in Storage or No Project Height Length Name River Basin Stream in Vicinity Useful Op. (Acre-Ft.) Pool (NPP) Functions Type (Feet) (Feet) CALIFORNIA Big Dry Creek Camanche 2 Cherry Valley' Del Valle Eaton Wash New Bullards Bar 2 New Don Pedro 3 New Exchequer 2 Oroville 2 Tahchevah Creek COLORADO Pinon Canyon CONNECTICUT East Branch Hall Meadow Brook Mad River Sucker Brook HAWAII Kaneohe Dam IDAHO Ririe MARYLAND Savage River MISSOURI Bear Creek NEW YORK Onondaga OKLAHOMA Altus* Lake Hudson* Grand Lake 0' the Cherokees UTAH Big Wash VERMONT East Barre Waterbury Wrightsville San Joaquin San Joaquin Tuolumne Alameda Rio Hondo Sacramento San Joaquin San Joaquin Sacramento Whitewater Colorado Housatonic Housatonic Connecticut Connecticut Kaneohe Upper Snake Potomac Upper Mississippi, Oswego Red Arkansas Arkansas Beaver Winooski Winooski Winooski Big Dry Creek Mokelumne River Cherry Creek Arroyo Del Valle Eaton Wash Yuba River Tuolumne River Merced River Feather River Tahchevah Creek Pinon Canyon Arroyo East Branch, Naugatuck River Hall Meadow Brook Mad River Sucker Brook 1948 1963 1956 1968 1937 1968 1970 1966 1964 1965 Fresno Clements Sonora Livermore Pasadena Marysville Modesto Merced Oroville Palm Springs Trinidad Torrington Torrington Winchester Winchester Kaneohe Stream Kaneohe Willow Creek Savage Bear Creek Idaho Falls Western Port Hannibal Onondaga Creek Syracuse North Fork, Red Grand (Neosho) River Grand (Neosho) River Big Wash Jail Branch Waterbury North Branch, Winooski River Altus Locust Grove Disney Milford East Barre Waterbury Wrightsville 16,250 431,500 268,000 77,000 960 960,000 2,030,000 1,026,000 3,539,000 950 NPP NPP 475 200 NPP 1.910 3,520 1,900 5,838 NPP F FRS FS FRS F FIRPW FISP FIR FIRSW F Earth Earth & Rock Earth & Rock Earth Earth Concrete Earth & Rock Rock Earth Earth 1964 4,350 NPP FRW Earth 1964 1962 1963 1970 4,350 NPP FR 8,620 NPP F 9,700 10 FR 1,480 NPP F Earth Earth & Rock Earth Earth 1981 3,800 26 FR Earth 1979 100,500 364 FIR Earth 1952 20,000 360 FRS Earth 1962 8,700 NPP F Earth 1949 18,200 NPP F 1948 152,429 1964 444,500 1941 2,197,000 6,260 FISR 10,900' FRP 46,500* FRP 1961 1,200 NPP F 1938 1938 1938 23,550 NPP F 82,100 900 FRH 36,000 90 FR Earth Concrete Concrete & Earth Concrete Earth Earth & Rock Fill Earth & Rock Fill Earth & Rock Fill NOMENCLATURE FOR PROJECT FUNCTIONS: A-Low Flow Augmentation D-Debris Control F -Flood Control I -Irrigation N -Navigation P -Power Q -Water Quality Control R -Public Recreation (Annual Attendance exceeding 5,000) S -Water Supply W-Fish and Wildlife (Federal or State) X- Water Conservation and Sedimentation ' Acres of water surface at top of permanent pool. 2 Federal Government contributed for flood control storage. 2 Cherry Valley Reservoir: Planned and constructed by local interests as initial phase; provided flood control on interim basis. Second and final phase, New Don Pedro Reservoir: Federal Government contributed for flood protection, construction and operation by City and County of San Francisco, and Turlock and Modesto Irrigation Districts. " Construction by Bureau of Reclamation. Participation by Department of the Army to finance flood control portion. * Construction by Grand River Dam Authority. Participation by Department of the Army to finance flood control portion. ' Top of power pool. A-7 40 171 315 223 82 645 565 480 770 42 20,038 2,450 2,500 880 1,795 2,323 1,920 1,200 6,850 3,610 92 700 92 73 178 68 100 1,200 940 1,160 76 2,200 184 840 t 184 1,050 65 1,450 67 1,782 98 90 147 1,112 4,494 6,565 34 2,814 65 158 115 1,460 1,800 1,525 APPENDIX B FLOOD CONTROL PROJECTS UNDER CONSTRUCTION DURING FISCAL YEAR 1985 Fiscal Year Fiscal Placed in Completed or Year Useful Scheduled for Project Started Operation Completion Nature of Project Airport Rel, 20 Mile Cr, Prentiss Co, MS (Sec 14) ................... Alamosa, CO (Sec 14) ............................................. Allegheny River, Oil City, PA (Sec 205) ............. ................ Allegheny River, Tionesta, PA (Sec 14) ............. ................ A lpena, M I (Sec 14) ....................... ..... .......... ........ Alton to Gale Levee System, Mississippi River, IL and MO ........... Alum Creek Lake, OH ............................................ Alum Creek Lake, OH .......................................... Ararat River, M t. Airy, NC (Sec 205) ............. .................. A rcadia Lake, O K ............................................... Arkansas-Red Basins Chloride Control (Area VIII), OK, TX, and KS (Stage I).................................. ................ Arroyo Colorado River, Rio Hondo, TX (Sec 14) ..................... Asan Village (Guam) (Sec 205) ..................................... Ascalmore-Tippo Items, MS ...................................... Asquiroga Bay Shoreline (Guam) (Sec 14) ........................... B. Everett Jordan Dam and Lake, NC .............................. Barkers Island, WI (Sec 14) ....................................... Bayshore, WI (Sec 14) ............................................ Beaver Brook, Keene, NH (Sec 205) ............. ................... Beech Fork Lake, W V ............... ........... ................. B ettendorf, IA ................. ............... .................. Big South Fork National River & Recreation Area, KY and TN ........ Big Stone Lake & Whetstone River, MN and SD ..................... Big Thompson River, Johnstown, CO (Sec 14) ....................... Big W ood River, ID (Sec 208) ...................................... Black Bear and Miller Lakes, Crow Wing County, WI (Sec 205) ........ Black River, Butler County Road 607, MO (Sec 14) ................... Blackstone River, Millbury, MA (Sec 14) ............. ............... Blanchard River, Ottawa, OH (Sec 14) ............. ................. Bloomington Lake, MD and WV ................................... Blue River Channel, MO .......................................... Boise River, ID (Sec 208) .......................................... Bonnes Coulee, Velva, ND (Sec 14) ............. .................... Bradford, TN (Sec 208) ........................................... Bridgeport, MI (Sec 14) ........................................... Brookville Lake, IN .................................... Brown Co., Bridge, Wolf River, KS (Sec 14) ......................... Brush Bayou, LA ...................................... Buffalo Bayou and Tributaries, TX ............ .................... B urlington, IA .............. . ................................... Burnsville Lake, WV ............................................. Cache LaPoudre River, Winsor, CO (Sec 14) ........................ Caesar Creek Lake, OH ...................... .................... Calloway Branch, TX ............................................. C andy Lake, O K ................................................. Catherine Creek, OR (Sec 208) ..................................... Cave Run Lake, KY .............................................. Central and Southern, FL ......................................... Chagrin River, Gates Mills, OH (Sec 14) ............................ Charlevoix, MI (Sec 14) ........................................... Chatfield Lake, CO ............................................... Chena River Lakes, AK ........................................... Chillicothe, OH .................................................. Colfax, Palouse River, WA ........................................ Columbus, NE (Sec 205) .......................................... Cooper Lake and Channels, TX .................................... Copan Lake, OK ................................................. Corte Madera Creek, CA .......................................... Creek Road Bridge, MS .......... ............................. Cucamonga Creek, CA.......................... ........ Cuyahoga River, Akron, OH (Sewerline) (Sec 14) ................ Cuyahoga Street Bridge, Akron, OH (Sec 14) ...................... Dade County, FL ......... ................................... Dayton, KY .................................. ........ Demonstration Erosion Control, MS ........ ................ Devils Lake, ND (Sec 205).......... ...................... 1984 1983 1982 1983 1982 1983 1970 1970 1985 1980 1976 1984 1983 1984 1985 1967 1985 1985 1985 1970 1982 1979 1971 1985 1984 1984 1985 1985 1983 1971 1984 1984 1984 1983 1985 1966 1985 1977 1956 1982 1972 1985 1971 1985 1976 1985 1965 1950 1984 1984 1967 1973 1971 1962 1982 1958 1973 1966 1985 1976 1985 1984 1975 1978 1985 1983 1984 1983 1984 1983 1975 1975 1984 1985 1982 1985 1985 1978 1975 1985 1985 1983 1981 1984 1984 1974 1986 1984 1985 1978 1982 1985 1985 1974 1981 1966 1983 1985 1982 1985 1985 1984 1984 1984 1983 1984 1984 1984 1987 1987 19853 1984 1985 1985 1986 1989 1986 1985 1987 1986 1987 1988 1986 1985 1985 1987 1986 1986 1985 1984 1993 1985 1985 1984 Indefinite 1984 1986 1980 Indefinite 1984 1986 1985 1986 1986 Deferred 1986 1987 1996 1985 1985 1988 1994 1985 1984 1986 1992 1985 1988 1985 1988 1986 1985 1993 1985 Indefinite 1986 Streambank protection Streambank protection Streambank protection Local protection Local protection Local protection Reservoir Reservoir Local protection Reservoir Chloride Control Streambank protection Local protection Local protection Emergency protection Reservoir Streambank protection Streambank protection Local protection Reservoir Local protection National Recreation Area Local protection Streambank protection Snagging and Clearing Local protection Streambank protection Streambank protection Local protection Reservoir Local protection Snagging and Clearing Streambank protection Local protection Streambank protection Reservoir Streambank protection Local protection Local protection Local protection Reservoir Streambank protection Reservoir Local protection Reservior Snagging and Clearing Reservoir Local protection Local protection Streambank protection Reservoir and Channel Improvement Reservoirs and levee Local protection Local protection Local protection Reservoir, channel improvement and levees Reservoir Local protection Streambank protection Local protection Local protection Local protection Shore protection Local protection Local protection Local protection B-i APPENDIX B (Continued) FLOOD CONTROL PROJECTS UNDER CONSTRUCTION DURING FISCAL YEAR 1985 Fiscal Year Fiscal Placed in Completed or Year Useful Scheduled for Project Started Operation Completion Nature of Project Dry Creek (Warm Springs) Lake & Channel, CA ..................... Duck Creek Channel Improvement, TX ............................. Dungeness River, Sequim, WA (Sec 14) ............................. Eagle Cr, SC (Sec 205) ............................................ East Lynn Lake, WV ............................................. East Moline, IL.................................................. East Rockaway Inlet to Rockaway Inlet & Jamaica Bay, NY, Part I ......................................................... East St. Louis and Vicinity, IL .................................... Eighteen Mile Creek, Hamburg, NY (Sec 208) ....................... El Dorado Lake, KS .............................................. El Paso, TX ..................................................... Elizabeth, NJ ................................................... Elk Creek, Lagoon, NE (Sec 14) .................................... Elk Creek, Lake, OR ............................................. Elkhart, IN (Sec 14) .............................................. Elm Creek, Bridges, Burt Co., NE (Sec 14) .......................... Elm Creek, Decatur, NE (Sec 14) ................................... Enderlin, Maple River, ND (Sec 205) ............................... Euclid Creek, OH (Sec 205) .................................... Euclid General Hospital, Euclid, OH (Sec 14) ........................ Evansdale, IA ................................................... Falls Lake, NC .................................................. Fike Bridge, Clay Co., NE (Sec 14) ............................. Fire Island Inlet to Montauk Point, NY ............................ (Remainder) ................................................... Four Rivers Basin, FL ............................................ Fulton, IL ...................................................... Genoa Sewer Facility, Wayne Co., NC (Sec 14) ....................... Grand Prairie, TX (Meyers Road-Sec 14) ............................ Grand Prairie, TX (Sanitary Landfill-Sec 14) ........................ Grays Creek, Memphis, TN (Sec 14) ................................ Great Falls, MT ................................................. Greenville, TX ................................................... Greenwood, Claiborne St., M S ............ ......................... Greenwood, Site, 2, MS ........................................... Hillsdale Lake, KS ............................................... Hwy 90, St. Francis River, AR (Sec 14) ............................. Indian Bend Wash, AZ ........................................... Indian Creek, Emerson, IA (Sec 205) ............................... Irving Township at Nicols Road, Jackson County, WI (Sec 14) ........ Joe Pool Lake, TX (formerly Lakeview Lake) ........................ John Day River (West), OR (Sec 14) ................................ Kansas City, KS (1962 Mod.) ...................................... Kaskaskia Island Drainage & Levee Dist, IL ........................ Kuskokwim River, Bethel, AK (Sec 14) ............................. Lake Chicot Pumping Plant, AR ............................... Lake Darling, Souris River, ND............................... Lake Michigan, Pt. Washington, WI (Sec 14) ........................ Lake Pontchartrain, LA ..................................... Larose to Golden Meadow, LA .................................... Lavon Lake Modification and East Fork Channel Improvement, TX ........................................................... Lead Bayou, MS (Sec 205) ........................................ Levee Unit 5, W abash River, IN ................................... Levisa & Tug Forks of the Big Sandy River & Cumberland River, KY, WV & VA ........................................... Lewisville Dam, TX ......................................... Little Blue River Channel, MO .................................... Little Blue River, Gilead, NE (Sec 14) .............................. Little Blue River Lakes, MO .................................. Little Massard Creek, Ft. Smith, AR (Sec 205) .................... Little Red River, Clinton, AR (Sec 205) .......................... Lipovsky Bridge, Clay Co., NE (Sec 14) ......................... Long Branch Lake, MO ...................................... Lorraine Rd, Biloxi River, MS (Sec 14) .......................... Lower Columbia River Bank Protection, OR and WA .............. Mahoning River, Highway 139 A, OH (Sec 14) .................... Manistee, MI (Sec 14) ........ ............................... 1967 1973 1985 1983 1965 1980 1975 1974 1983 1974 1971 1972 1985 1971 1984 1984 1985 1982 1983 1984 1981 1973 1985 1963 1963 1966 1978 1984 1984 1983 1984 1982 1973 1984 1984 1975 1984 1976 1983 1985 1975 1985 1971 1980 1985 1981 1985 1984 1967 1972 1970 1982 1964 1981 1979 1975 1985 1978 1983 1985 1985 1973 1983 1962 1985 1984 1983 1988 Indefinite 1986 1985 1986 1970 1982 1984 1984 1977 1988 1986 1984 1981 1986 1973 Indefinite 1986 1985 1985 1990 1985 1985 1984 1985 1985 1985 1986 1986 1986 1983 1983 1983 1990 1985 1985 Indefinite Indefinite 1988 1984 1984 1985 1985 1985 1985 1985 1984 1985 1986 1979 1983 1985 1985 1981 1983 1985 1985 1985 1985 1986 1989 1985 1979 Indefinite 1986 1986 1985 1991 1985 1985 Indefinite 1992 1976 1985 (mod.) 1985 1969 1986 Indefinite 1984 1984 1986 1986 1986 1987 1984 1984 1987 1985 1985 1980 Indefinite 1983 1984 Indefinite 1985 1985 1985 1985 Reservoir Local protection Snagging and Clearing Local protection Reservoir Local protection Beach nourishment Local protection Local protection Reservoir Local protection Local protection Streambank protection Reservoir Streambank protection Streambank protection Streambank protection Local protection Local protection Local protection Local protection Reservoir Streambank protection Local protection Local protection Local protection Local protection Streambank protection Streambank protection Streambank protection Streambank protection Local protection Local protection River bank protection River bank protection Reservoir Streambank protection Local protection Local protection Streambank protection Reservoir Streambank protection Local protection Local protection Streambank protection Local protection Reservoir Streambank protection Local protection Local protection Reservoir and channel improvement Local protection Local protection Local protection Major protection Local protection Streambank protection Reservoir Local protection Local protection Streambank protection Reservoir Streambank protection Local protection Streambank protection Streambank protection B-2 APPENDIX B (Continued) FLOOD CONTROL PROJECTS UNDER CONSTRUCTION DURING FISCAL YEAR 1985 Fiscal Year Fiscal Placed in Completed or Year Useful Scheduled for Project Started Operation Completion Nature of Project Mankato and N. Mankato, MN .................................... MMaaurtvianiss eF oTrekr Lrea,k IeL, K."Y ........................................... ." .... Mauvaise Terre, IL............... ............... ......... McGee Creek Drainage and Levee Dist., IL ......................... Middle Pebble Creek, Snyner, NE (Sec 14) .......................... Middle River at Argyle, MN (Sec 205) ............. ................. Milan, IL ....................................................... M ill C reek, O H ................. . . ... .. .......................... Minnesota River at Le Sueur, MN (Sec 14) .......................... M iss R. Ag Area 8, Elsberry, MO ................... ............... Missouri River Levee System, IA, NE, KS, and MO .................. Mt. St. Helens & Vicinity, WA .................................... Muddy Creek, Syracuse, NE (Sec 14) ............ ................... Mudline to Pineville, MS .......................................... Muskingham River Lakes, OH .................................... Muskingum River Lakes, OH (Dam Safety Assurance) ........................................ New London, CT ................................................. New Orleans to Venice, LA .............. ......................... Newark, OH.................................. .......... Nonewaug River, Woodbury, CT (Sec 14) ........................... Nooksack River, W A (Sec 14) ...................................... North Fork Big Nemaha River, Richardson Co., NE (Sec 14) .......... Ohio River, Chester, WV (Sec 14) .................................. Otter Creek, Shannon Hills, AR (Sec 205) ........................... Paauau Stream, Hawaii, Hawaii (Sec 205) ........................... Paintsville Lake, KY ............................................. Panola-Quitman Item C, MS ...................................... Papillion Creek and Tributaries Lake, NE ........................... Patoka Lake, IN...................................... Pawnee Ranch Bridge, Clay County, NE (Sec 14) .................... Pawtuxet River, Warwick, RI (Sec 205) .............. ............... Pearl River, MS .................................................. Perry County L & D Nos. 1, 2,3, MO ............. .................. Phoenix, AZ, and Vicinity (including New River) ..................... Platte River, Brady, NE (Sec 14) .............. .. ................... Porter Bayou, MS (Sec 205) ....................................... Plum Creek, Penn Hills, PA (Sec 14) ............. ................... Pt. Leflore, MS .................................................. Point Place, OH ................................................. Portugues and Bucana Rivers, PR ............ ..................... Prairie Du Chien, WI ............................................. Presque Isle Peninsula, PA ............... ........................ Quenemo Lagoon, KS (Sec 14) ..................................... R. D. Bailey Lake, WV ............................................ Rapid Creek, ID (Sec 208) ......................................... Rapidan River, Orange, VA (Sec 14) ........................ ........ Raritan Bay and Sandy Hook Bay, NJ, Matawan and Union Beach Sections ................................................ Ray Roberts Lake, TX ............................................ Red Oak, IA (Sec 205) ............................................ Red River below Denison Dam, TX ............. ................... Red River Emergency Bank Protection ............................. Red River of the North at Argusville, ND (Sec 205) .................. Red River of the North at Halstad, MN (Sec 205) .................... Roberto Clemente Park, Pittsburgh, PA (Sec 14) .................... Rockford, IL (Kent Creek) ........................................ Rogers Cemetery, Amity, NY (Sec 14) ............. ........ ........ Root Creek, Bolivar, NY (Sec 205) ............... ................... Sacramento River Bank Protection, CA ............................ Sacramento River, Chico Landing to Red Bluff, CA .................. Sacramento River Flood Control, CA .............. .......... Sacramento River, Major and Minor Tributaries, CA ................ Saginaw River, MI ............. ........................ Salt Creek, Lincoln, NE (Sec 14) ......... ..................... San Antonio Channel Improvement, TX . .................... San Gabriel River, TX . .................................. San Jacinto River Levee & Bautista Creek Channel, CA .............. Sandy Creek, Jackson, TN (Sec 14) .......... ................... 1971 1973 1985 1979 1985 1985 1980 1981 1985 1979 1948 1983 1984 1984 1976 1982 1978 1969 1976 1984 1985 1985 1983 1984 1983 1973 1984 1972 1972 1984 1982 1984 1977 1973 1985 1982 1983 1985 1982 1975 1979 1975 1985 1967 1985 1983 1965 1975 1982 1948 1971 1985 1983 1983 1979 1985 1979 1963 1963 1918 1949 1965 1985 1957 1973 1960 1983 1978 1985 1982 1985 1989 1982 1987 1985 1985 1987 1987 1998 1986 1982 Indefinite 1988 1985 1985 1988 Indefinite 1985 1986 Indefinite 1988 1984 1985 1985 1985 1984 1984 1984 1985 1985 1985 1983 1987 1985 1974 1988 1978 1985 1985 1985 1986 1985 1985 1991 1985 1985 1985 1984 1984 1985 1985 1986 1998 1985 1975 1989 1985 1985 1986 1985 1984 Indefinite 1990 1983 1985 1986 1987 1986 1985 1985 1984 1984 1988 1985 1985 1984 1984 1991 Indefinite 1989 1988 1979 1992 1985 1985 1990 19801 19842 1985 1985 1984 Local protection Reservior Local protection Local protection Streambank protection Local protection Local protection Local protection Streambank protection Local protection Local protection Local protection Streambank protection Streambank protection Major rehabilitation Modernization of Dams Local protection (hurricane) Local protection Local protection Local protection Streambank protection Streambank protection Local protection Local protection Local protection Reservoir Local protection Reservoirs Reservior Streambank protection Local protection Local protection Local protection Local protection Streambank protection Local protection Streambank protection Streambank protection Local protection Local protection Non-structural local protection Beach replenishment Streambank protection Reservoir Snagging and Clearing Streambank Erosion Local protection Reservior Local protection Local protection Streambank protection Local protection Local protection Streambank protection Local protection Local protection Local protection Local protection Local protection Local protection Loc 1 protection Local protection Streambank protection Local protection Reservoir Local protection Streambank protection B-3 APPENDIX B (Continued) FLOOD CONTROL PROJECTS UNDER CONSTRUCTION DURING FISCAL YEAR 1985 Fiscal Year Fiscal Placed in Completed or Year Useful Scheduled for Project Started Operation Completion Nature of Project Sardis Lake, OK ................................................. Saylorville Lake, IA .............................................. Scajaquada Creek, NY ........................................... Sicily Island, LA, Levee .......................................... Siena Center, Racine, W I (Sec 14) ............. ..................... Skiatook Lake, O K ..................... ........................ Sheley Bridge, MS ............................................... Shoshone River, Byron, WY (Sec 14) ............. .................. Smithville Lake, MO ............................................. South Fork, Big Nemaha River, Dubois Bridge, NE (Sec 14) .......... South Fork, Boise River, ID (Sec 208) .............................. South Platte River, Iliff, CO (Sec 14) ............. .................. South Platte River, Merino, CO (Sec 14) ............................ South Platte River, Platteville, CO (Sec 14) ......................... Southwestern Jefferson County, KY ............ .............. . Spring Ranch Bridge, Clay County, NE (Sec 14) ..................... St. Joseph HS, Cleveland, OH (Sec 14) ............... ................ State Hwy 101 & 104, Columbia River, WA (Sec 14) .................. Steele B ayou, M S ........ ....... ................................ Stonewall Jackson Lake, W V .................... .................. Stratmoor Hills, Colorado Springs, CO (Sec 14) ................... Sweetwater River, CA ............................................ Tarkio River, Coin, IA (Sec 14) .................................... Taylors B ayou, TX ................. ............................... Taylorsville Lake, KY .................... ........................ Tensas Cocodrie Pumping Plant, LA 11 ............................ Texas City and Vicinity, TX (1958 authorization) .................... Tillatoba Creek Levee Repair, MS .............................. Tombigbee River Tributaries, AL and MS .......................... Trout Run, Portage Borough, PA (Sec 14) ........................... Truchas Creek, Ft Summer, NM (Sec 14) ............................ Twenty-mile Creek, Airport Rd., Prentiss County, MS (Sec 14) ........ Umatilla River, Thorn Hollow, OR (Sec 14) .......................... Upper Yazoo Projects, M S ................. ...................... U.S. Hwy. 11 Bridge, Fosters, AL (Sec 14) .......................... U.S. Hwy. 82 Bridge, Columbus, MS (Sec 14) ........................ U.S. Interstate 59 Bridges, Fosters, AL (Sec 14) ..................... Valley Creek, A L (Sec 14) ............... . ......................... Vermillion River, Vermillion, SD (Sec 14) ............. .............. Vince and Little Vince Bayous, TX ................................. Waimea River, Kauai, Hawaii (Sec 205) ............. ................ Walnut Creek, CA ............................................... Waterloo, IA .................................................... W eiser River, ID (Sec 208) ..................... ................... West Fork Grand River, Isadora, MO (Sec 14) ....................... West Magnesia Canyon Channel, CA (Sec 205) ...................... West Makinster Road, Wilson River, OR (Sec 14) .................... West Papillion Creek, Douglas Co., NE (Sec 14) ...................... Wheeler Creek, Gainesville, TX (Sec 205) ........................... White River, Jacksonport, AR (Sec 205) ............................ Wild Rice River, Mahnomen County, MN (Sec 14).................... Willamette River Basin Bank Protection, OR ................... William H. Harsha Lake, OH ...................................... Wilson Branch, Cheraw SC (Sec 205) ............. .................. Winona, MN .................................................... Wolf Cr., Hwy 45, Prentiss Co, MS (Sec 14) ......................... Wood River Drainage and Levee District, IL ........................ Wyoming Valley, PA ............................................. Yatesville Lake, KY..................................... ......... Yellowstone River, Glendive, MT (Sec 14) ........................... Yonkers, NY . ........................................ 1976 1965 1978 1983 1981 1974 1984 1983 1974 1985 1984 1985 1985 1985 1974 1984 1983 1984 1966 1977 1983 1984 1984 1982 1974 1983 1962 1983 1965 1984 1983 1984 1984 1976 1985 1985 1985 1985 1985 1968 1983 1964 1973 1984 1985 1985 1985 1985 1983 1984 1985 1938 1970 1982 1979 1984 1953 1983 1964 1985 1975 1983 1977 1982 1982 1985 1985 1984 1982 1985 1985 1985 1985 1983 1985 1984 1984 1985 1984 1984 1984 1985 1985 1985 1984 1978 1984 1985 1962 1976 1985 1986 Indefinite 1982 2010 1982 1986 1985 1985 1986 1985 1985 1985 1986 1985 1989 1985 1984 1985 1995 1988 1984 1988 1985 1990 1987 1986 1986 1984 Indefinite 1984 1984 1985 1984 2013 1986 1985 1986 1986 1986 1988 1985 1988 1986 1985 1985 1986 1985 1986 1984 1986 1986 Indefinite 1986 1985 1985 1985 1986 1986 Not scheduled 1985 1985 Reservoir Reservoir Local protection Local protection Local protection Reservoir Streambank protection Streambank protection Reservoir Streambank protection Snagging and Clearing Streambank protection Streambank protection Streambank protection Local protection Streambank protection Local protection Streambank protection Local protection Reservoir Streambank protection Local protection Streambank protection Local protection Reservoir Local protection Local protection Local protection Local protection Streambank protection Streambank protection Streambank protection Streambank protection Local protection Streambank protection Streambank protection Streambank protection Sewerline protection Streambank protection Local protection Local protection Local protection Local protection Snagging and Clearing Streambank protection Local protection Streambank protection Streambank protection Local protection Local protection Streambank protection Local protection Reservoir Local protection, FP Evacuation Local protection Streambank protection Local protection Rehabilitation of levee system Reservoir Streambank protection Local protection 1 Granger Dam & Lake Georgetown - complete FY 83 2 South Fork - Construction deferred indefinitely, work on Reevaluation Report only 3 Completion of Stage I (Truscott facilities) only. Stage II (Ross facilities) indefinite B-4 APPENDIX C NAVIGATION LOCKS AND DAMS OPERABLE SEPTEMBER 30, 1985 Locks Dams Authorized Channel Lift at Miles Width Available Normal Depth on Sills Above Community of Length for Pool Length Year Length Depth Width Project Mouth In Vicinity Chamber Full Width Level Upper Lower Type' (feet) Opened (miles) (feet) (feet) Alabama-Coosa Rivers. AL Claiborne Lock and Dam 81.82 Claiborne, AL Millers Ferry Lock and Dam 142.32 Camden. AL Jones Bluff Lock and Dam 254.42 Benton, AI, Allegheny River. PA and NY Lock and Dam No. 2 6.7 Aspinwall. PA Lock and Dam No. 3 14.5 Cheswick. PA Lock and Dam No. 4 24.2 Natrona, PA Lock and Dam No. 5 30.4 Freeport, PA Lock and Dam No. 6 36.3 Clinton, PA Lock and Dam No. 7 45.7 Kittanning. P, Lock and Dam No. 8 52.6 Templeton. PA Lock and Dam No. 9 62.2 Rimer, PA Apalachicola, Chattahoochee. and Flint Rivers, GA, AL and FL Jim Woodruff Lock and Dam 107.6' Chattahooche George W. Andrews Lock and Dam 154.3' Columbia. GA Walter F. George Lock and Dam 182.85 Fort Gaines, Atlantic Intracoastal Waterway Albemarle and Chesapeake Canal Route: Great Bridge Lock 11.56 Great Bridge, Dismal Swamp Canal Route: Deep Creek Lock 10.6' Deep Creek,V South Mills Lock 33.2' South Mills, A A 84 84 84 56 56 56 56 56 56 56 56 82 82 82 e, FL GA VA VA NC Bayou Teche, LA Berwick Lock 1.5' Berwick, LA Keystone Lock 72.5' New Iberia, LA Black Rock Channel and Tonawanda Harbor, NY Black Rock Lock 0.0 Buffalo, NY Black Warrior. Warrior and Tombigbee Rivers. AL Coffeeville (Jackson) Lock and Dam 116.6 '0 Coffeeville, AL Demopolis Lock and Dam 213.2 '0 Demopolis, AL Armistead I. Selden Lock and Dam 261.1' 0 Eutaw. AL Win. Bacon Oliver Lock and Dam 338.1'" Tuscaloosa, AL Holt Lock and Dam 347.0"o Holt, AL John Hollis Bankhead Lock and Dam (new lock) 365.1'" Adger, AL Canaveral Harbor. FL Canaveral Lock 2.7 Cocoa, FL Cape Fear River. NC Lock and Dam No. 1 67.0 Kings Bluff. NC Lock and Dam No. 2 99.0 Browns Landing, NC William O. Huske Lock and Dam 123.0 Tolars Landing. NC Central and Southern Florida S-61 Lock 0.0 St. Cloud. FL S-65 Lock 56.0 Frostproof, FL S-65A Lock 46.0 Avon Park, FL S-65B Lock 32.0 Sebring. FL S-65C Lock 25.0 Sebring. FL S-65D Lock 16.0 Okeechobee, FL S-65E Lock 12.0 Okeechobee, FL S-308B 38.7 Port Mayaca, FL S-310 0.0 Clewston. FL Chicago Harbor. IL Chicago Lock 0.0 Chicago, IL Columbia River. OR and WA Bonneville Lock and Dam 146.0 Bonneville, OR The Dalles Lock and Dam 190.0 The Dalles. OR John Day Lock and Dam 215.0 Rufus, OR McNary Lock and Dam 292.0 Umatilla. OR Cross-Florida Barge Canal Inglis Lock, Dam and Spillway 168.6" Inglis. FL Eureka Lock and Dam 20.0 Sparr. FL Harry H. Buckman Lock 90.4 Palatka, FL 600 600 600 360 360 360 360 360 360 360 360 450 450 450 30 45 45 11 13 10 12 12 13 18 22 33 25 88 16 16 16 11 12 9 10 11 11 14 11 14 19 18 13 Movable 3,1603 1973 60.5 13 Movable 9,9003 1969 103.1 13 Movable 14,9623 1974 88.0 12 Fixed 11 Fixed 10 Fixed 11 Fixed 11 Fixed 10 Fixed 10 Fixed 11 Fixed 1,393 19342 1,436 193420 876 1927 780 1927 1.140 1928 916 1930 984 1931 950 1938 14 Movable 5,924 1957 13 Movable 620 1963 13 Movable 13,371 1963 75 600 3 16' 16' None 52 300 12 12' 12' None 52 300 12 12' 12' None 1932 1940 1941 45 307 79 9' 9' None 1950 36 162 9 9 8 Fixed 175 1913 68 625 5 21.6 21.6 None 1914 110 110 110 95 110 110 600 600 600 460 600 600 33 40 22 28 64 68 90 600 40 40 40 30 30 30 30 30 30 30 56 50 200 200 300 90 90 90 90 90 90 90 400 60 13 13 13 12 19 13 13 Movable 1,185 1965 13 Fixed 1,485 1962 13 Movable 1,832 1962 12 Fixed 700 1940 13 Movable 1,138 1969 13 Fixed 1,170 1975 3 14 14 None 11 9 9 2 666 7 6 5 14 5 9 12 9 6 666666 14 13 9 Fixed 12 Fixed 9 Fixed 6 None 6 None 6 None 6 None 6 None 6 None 6 None 14 Movable 13 Movable 1965 275 1915 229 1917 220 1935 1963 1964 1967 1965 1965 1964 1964 1977 1980 80 600 4 23 23 None 76 86 86 86 84 84 84 500 675 675 675 600 600 600 C-1 65 88 110 75 28 20 20 32 15 15 15 18 14 14 7.8 9.7 6.2 5.9 9.4 6.9 9.6 9.8 46.7 28.5 85.0 9 200 9 200 9 200 9 200 9 200 9 200 9 200 9 200 9 200 9 200 9 200 6 100 6 100 6 100 9 90 9 50 9 50 8 80 34.5 6 80 7.1 21 200 96.6 47.9 77.0 8.9 18.1 42.7 32.0 24.0 20.0 28.0 10.0 14.0 7.0 9.0 4.0 5.0 .5 200 200 200 200 200 200 12 125 1939 .15 21 24 Movable 2,680 1938 15 Movable 8,735 1957 15 Movable 5,900 1968 20 Movable 7,365 1953 15 Movable 5.100 1968 Movable 3,830 1971 15 None 1972 47.5 27 25.0 14 76.0 14 64.0 14 11.0 12 12 21.2 12 100 100 100 20 30 30 30 30 30 30 100 50 470 300 250 250 250 150 150 150 APPENDIX C (Continued) NAVIGATION LOCKS AND DAMS OPERABLE SEPTEMBER 30, 1985 Locks Dams Authorized Channel Lift at Miles Width Available Normal Depth on Sills Above Community of Length for Pool Length Year Length Depth Width Project Mouth In Vicinity Chamber Full Width Level Upper Lower Type' (feet) Opened (miles) (feet) (feet) Cumberland River, KY and TN Barkley Dam 30.6 Kuttawa. KY Cheatham Lock and Dam 148.7 Ashland City. TN Old Hickory Lock and Dam 216.2 Old Hickory, TN Cordell Hull Dam and Reservoir 313.5 Carthage, TN Fox River, WI DePere Lock 7.1 DePere, WI DePere Dam 7.2 DePere, WI Little Kaukauna Lock 13.0 DePere, WI Little Kaukauna Dam 13.1 DePere, WI Rapide Croche Lock 19.2 Wrightstown, WI Rapide Croche Dam 19.3 Wrightstown, WI Kaukauna Fifth Lock 22.8 Kaukauna, WI Kaukauna Fourth Lock 23.1 Kaukauna, WI Kaukauna Third Lock 23.3 Kaukauna, WI Kaukauna Second Lock 23.4 Kaukauna, WI Kaukauna First Lock 23.6 Kaukauna, WI Kaukauna Dam 24.0 Kaukauna, WI Kaukauna Guard Lock 24.0 Kaukauna, WI Little Chute combined Lock Lower 25.4 Little Chute, WI Upper 25.4 Little Chute, WI Little Chute Second Lock 26.4 Little Chute, WI Little Chute First (Guard) Lock 26.5 Little Chute, WI Little Chute Dam 26.6 Little Chute, WI Cedars Lock 27.3 Little Chute, WI Cedars Dam 27.4 Little Chute, WI Appleton Fourth Lock 30.7 Appleton, WI Appleton Lower Dam 30.9 Appleton, WI Appleton Third Lock 31.3 Appleton, WI Appleton Second Lock 31.6 Appleton, WI Appleton First Lock 31.9 Appleton, WI Appleton Upper Dam 32.2 Appleton, WI Menasha Lock 37.8 Menasha, WI Menasha Dam 37.8 Menasha, WI Freshwater Bayou, LA Freshwater Bayou Lock 19.0' Intracoastal City, Green and Barren Rivers, KY Green River: Lock and Dam No. 1 9.1 Spottsville, KY Lock and Dam No. 2 63.1 Calhoun, KY Gulf Intracoastal Waterway Inner Harbor Navigation Channel Lock 92.612 New Orleans, LA Harvey Lock 98.312 Harvey, LA Algiers Lock 88.012 Algiers, LA Bayou Boeuf Lock 93.3 Morgan City, LA Bayou Sorrel Lock 131.0" Plaquemine, LA Port Allen Lock 228.512 Port Allen, LA Vermilion Lock 162.7"1 Abbeville, LA Calcasieu Lock 238.5" Lake Charles, LA Brazos River Floodgates 404.113 Freeport, TX Colorado River East Lock 444.8 Matagorda, TX West Lock 444.8 Matagorda, TX Hudson River, NY Troy Lock and Dam 153.8 Troy, NY Illinois Waterway, IL LaGrange Lock and Dam 80.2 Beardstown, IL Peoria Lock and Dam 157.7 Peoria, IL Starved Rock Lock and Dam 231.0 Utica, IL Marseilles Lock 244.6 Marseilles, IL Marseilles Dam 247.0 Marseilles, IL Dresden Island Lock and Dam 271.5 Morris, IL Brandon Road Lock and Dam 286.0 Joliet, Il1 Lockport Lock 291.1 Lockport, IL Thomas J. O'Brien Lock and Dam 326.5 Chicago, IL Inland Route, MI Crooked River Lock and Weir 30.0 Alanson, MI 110 110 84 84 36 36 36 36 37 31 35 35 40 35 36 35 35 35 35 35 35 34 34 LA 800 800 400 400 146 146 146 144 144 144 144 144 147 144 144 144 144 144 145 145 144 57 26 60 59 9 7 8 9 10 10 10 11 9 11 11 14 7 10 8 9 10 10 8 84 600 11 14 14 14 10 8 9 7 7 7 6 7 688 7 8 6 7 7 7 13 Movable 12 Movable 10 Movable 13 Movable 12 10 10 96666 9 6 6 7 8 96 6 9,959 1964 801 1959 3.605 1957 1,138 1973 1936 Movable 986 1929 1938 Movable 588 1926 1934 Movable 461 1930 1898 1879 1879 1903 1883 Movable 603 1931 1891 1879 1879 1881 1904 Movable 562 1932 1888 Movable 654 1933 1907 Movable 549 1934 1900 1901 1884 Movable 691 1940 1899 Movable 401 1937 16 16 None 84 600 12 12 11 Fixed 84 600 14 15 12 Fixed 75 75 75 75 56 84 56 75 75 640 425 797 1,158 800 1,198 1,200 1,205 9 10' 10' 6' 10' 45 3' 6' 75 1,200 75 1,200 31' 12'7 13'7 13'7 14'7 13' 11' 13' 15' 31' None 12' None 13' None 13' None 14' None 14' None 11' None 13' None 15' None 5' 15' 15' None 5' 15' 15' None 118.1 9 67.5 9 97.3 9 71.9 9 5.9 6.2 3.6 0.3 0.2 0.1 0.2 0.4 1.4 1.0 0.7 3.4 0.6 0.3 0.3 5.1 28.3 401 1968 150 150 150 150 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 12 125 482 1956 54.0 9 200 519 1956 45.4 9 200 1923 1935 1956 1956 1952 1961 1934 1950 1943 1954 1954 12 12 16 16 12 12 16 16 12 12 125 12 125 44 493 17 16 13 Fixed 1,495 1917 2.2 14 200 110 110 110 110 110 110 110 110 600 600 600 600 600 600 600 1,000 10 11 19 24 22 34 40 2 17.8 66 16 16 17 19 17 18 12 14 13 Movable 12 Movable 14 Movable 14 Movable 12 Movable 14 Movable 15 None 14 Movable 1,066 1939 536 1939 1,280 1933 1933 819 1933 1,616 1933 2,373 1933 1933 257 1960 77.5 9 73.3 9 13.6 9 26.9 9 24.6 14.5 9 5.1 9 9 6.9 9 6.9 7.9 SSP Weir 83 1967 4.0 5 30 C-2 150 125 150 150 125 125 200 200 125 300 300 300 300 300 300 300 300 APPENDIX C (Continued) NAVIGATION LOCKS AND DAMS OPERABLE SEPTEMBER 30, 1985 Locks Dams Authorized Channel Lift at Miles Width Available Normal Depth on Sills Above Community of Length for Pool Length Year Length Depth Width Project Mouth In Vicinity Chamber Full Width Level Upper Lower Type' (feet) Opened (miles) (feet) (feet) Kanawha River, WV Winfield Lock and Dam Marmet Lock and Dam London Lock and Dam Kaskaskia River, IL Kaskaskia Lock and Dam Kentucky River, KY Lock and Dam No. 1 Lock and Dam No. 2 Lock and Dam No. 3 Lock and Dam No. 4 Lock and Dam No. 524 Lock and Dam No. 624 Lock and Dam No. 724 Lock and Dam No. 82' Lock and Dam No. 924 Lock and Dam No. 102' Lock and Dam No. 1124 Lock and Dam No. 122' Lock and Dam No. 132' Lock and Dam No. 1424 Lake Washington Ship Canal Hiram M. Chittenden Lock Large Lock Small Lock McClellan-Kerr Arkansas River Navigation System, AR and OK Norrell Lock and Dam Lock No. 2 Dam No. 2 Lock and Dam No. 3 Lock and Dam No. 4 Lock and Dam No. 5 David D. Terry Lock and Dam Murray Lock and Dam Toad Suck Ferry Lock and Dam Lock and Dam No. 9 Dardanelle Lock and Dam Ozark-Jetta Taylor Lock and Dam Lock and Dam No. 13 W. D. Mayo Lock and Dam Robert S. Kerr Lock and Dam and Reservoir Webbers Falls Lock and Dam Chouteau Lock and Dam Newt Graham Lock and Dam Mississippi River Between Ohio and Missouri Rivers Lock and Dam No. 27 Mississippi River Between Missouri River and Minneapolis, MN Lock and Dam No. 26 Lock and Dam No. 25 Lock and Dam No. 24 Lock and Dam No. 22 Lock and Dam No. 21 Lock and Dam No. 20 Lock and Dam No. 19 Lock and Dam No. 18 Lock and Dam No. 17 Lock and Dam No. 16 Lock and Dam No. 15 Lock and Dam No. 14 Lock and Dam No. 13 Lock and Dam No. 12 Lock and Dam No. 11 Lock and Dam No. 10 Lock and Dam No. 9 Lock and Dam No. 8 Lock and Dam No. 7 31.1 Winfield, WV 67.8 Marmet, WV 82.8 London, WV .8 Ellis Grove, IL 4.0 Carrolton, KY 31.0 Lockport, KY 42.0 Gest, KY 65.0 Frankfort, KY 82.2 Tyrone, KY 96.2 High Bridge, KY 117.0 High Bridge, KY 139.9 Camp Nelson, KY 157.5 Valley View, KY 176.4 Ford, KY 201.0 Irvine, KY 220.9 Ravenna, KY 239.9 Willow, KY 249.0 Heidelberg, KY 1.3 Seattle, WA 1.3 Seattle, WA 10.3 Arkansas Post, AR 13.3 Arkansas Post, AR 40.5 Arkansas Post, AR 50.2 Grady, AR 66.0 Pine Bluff, AR 86.3 Redfield, AR 108.1 Little Rock, AR 125.4 Little Rock, AR 155.9 Conway, AR 176.9 Morrilton, AR 205.5 RussellvillAeR, 256.8 Ozark, AR 292.8 Fort Smith, AR 319.6 Fort Smith, AR 336.2 Sallisaw, OK 366.6 Webbers Falls, OK 401.2 Muskogee, OK 421.4 Inola, OK 185.1" Granite City, IL 202.9'" Alton, IL 241.4 ' " Cap Au Gris, MO 273.4'" Clarksville, MO 301.2 ' " Saverton, MO 324.9'" Quincy, IL 343.2 ' " Canton, MO 364.2 ' Keokuk, IA 410.5' " Burlington, IA 437.1"5 New Boston, IL 457.2" Muscatine, IA 482.91" Rock Island, IL 493.1'" LeClaire, IA 493.3 ' " LeClaire, IA 522.5 ' " Clinton, IA 556.7'" Bellevue, IA 583.0 ' " Dubuque, IA 615.1 ' " Guttenberg, IA 647.9'" Lynxville, IA 679.2'" Genoa, WI 702.5'" Dresbach, MN 56 56 56 360 360 360 28 24 24 18 18 18 12 Movable 834 1937 36.7 12 Movable 707 1934 15.0 12 Movable 707 1934 7.8 9 99 300 300 300 84 600 32 18 11 Movable 130 1973 35.0 9 225 38 38 38 38 38 52 52 52 52 52 52 52 52 52 145 145 145 145 145 147 147 146 148 148 148 148 148 148 8 14 13 13 15 14 15 19 17 17 18 17 18 17 88 96 10 99 11 11 9 10 10 10 9 15 Fixed 6 Fixed 7 Fixed 6 Fixed 6 Fixed 6 Fixed 7 Fixed 6 Fixed 7 Fixed 6 Fixed 6 Fixed 6 Fixed 6 Fixed 6 Fixed 80 760 26 33.5 29 Movable 28 123 26 16 16 110 110 110 110 110 110 110 110 110 110 110 110 110 110 110 110 110 600 600 600 600 600 600 600 600 600 600 600 600 600 600 600 600 600 30 20 20 14 17 18 18 16 19 54 34 20 20 48 30 21 21 16 18 18 18 18 18 18 18 18 18 18 18 14 18 19 15 15 424 400 465 543 556 413 350 257 362 472 208 240 248 248 1839 1939 1844 1844 1844 1891 1897 1900 1907 1907 1906 1910 1915 1917 27.0 11.0 23.0 17.2 14.0 20.8 22.9 17.6 18.9 24.6 19.9 19.0 9.1 9.6 100 100 100 100 100 100 100 100 100 100 100 100 100 100 235 1916 17.0 34 150 15 Fixed 4,677 1967 14 1967 Movable 42,073 1968 14 Movable 6,110 1968 14 Movable 5,745 1968 14 Movable 7,455 1968 14 Movable 8,890 1968 14 Movable 3,930 1969 14 Movable 1,580 1969 14 Movable 1,505 1969 14 Movable 1,815 1969 15 Movable 2,480 1969 14 Movable 4,725 1969 15 Movable 7,400 1970 14 Movable 7,230 1970 16 Movable 4,370 1970 14 Movable 11,490 1970 14 Movable 1,629 1970 3.0 36.9 15.8 20.3 21.8 17.3 30.5 21.0 28.6 51.3 36.0 26.8 16.6 30.4 34.8 20.2 23.7 250 250 250 250 250 250 250 250 250 250 250 250 250 250 250 150 150 110 1,200 21 16 15 Fixed 3,240 1953 17.8 9 200 110 110 110 110 110 110 110 110 100 110 110 110 80 110 110 110 110 110 110 110 110 600 360 600 600 600 600 600 1,200 600 600 600 600 360 320 600 600 600 600 600 600 600 600 24 24 15 15 10 10 10 38 10 8 9 16 16 11 11 11 9 11 8 9 11 8 19 16 19 19 18 17 15 15 17 16 17 27 27 18 21 19 17 19 15 16 22 18 10 Movable 1,725 10 12 Movable 1,296 12 Movable 4,280 14 Movable 1,024 12 Movable 1,066 12 Movable 2,144 13 Fixed 4,434 14 Movable 1,350 13 Movable 921 12 Movable 1,099 11 Movable 1,203 11 11 14 Movable 1,343 13 Movable 1,066 13 Movable 849 13 Movable 1,278 12 Movable 763 13 Movable 811 14 Movable 935 12 Movable 940 1938 1939 1940 1938 1938 1936 1913 1937 1939 1937 1934 1922 1939 1939 1938 1937 1937 1937 1937 1937 38.5 32.0 27.8 23.7 18.3 21.0 46.3 26.6 20.1 25.7 10.4 29.2 34.2 26.3 32.1 32.8 31.3 23.3 11.8 200 200 200 NS NS NS NS NS NS NS NS NS NS NS NS NS NS NS NS C-3 APPENDIX C (Continued) NAVIGATION LOCKS AND DAMS OPERABLE SEPTEMBER 30, 1985 Locks Dams Authorized Channel Lift at Miles Width Available Normal Depth on Sills Above Community of Length for Pool Length Year Length Depth Width Project Mouth in Vicinity Chamber Full Width Level Upper Lower Type' (feet) Opened (miles) (feet) (feet) Mississippi River (Continued) Between Missouri River and Minneapolis, MN Lock and Dam No. 6 714.3"6 Trempealeau, WI Lock and Dam No. 5A 728.5 ' Winona, MN Lock and Dam No. 5 738.1" Minneiska, MN Lock and Dam No. 4 752.8'6 Alma, WI Lock and Dam No. 3 796.9 ' " Red Wing. MN Lock and Dam No. 2 815.2' Hastings, MN Lock and Dam No. 1 847.6 ' ' Minneapolis-St. Paul. MN St. Anthony Fails Lower Lock and Dam 853.3"5 Minneapolis, MN Upper Lock and Dam 853.9" Minneapolis, MN Monongahela River, PA and WV Locks and Dam No. 2 11.2 Braddock, PA Locks and Dam No. 3 23.8 Elizabeth, PA Locks and Dam No. 4 41.5 Monessen, PA Maxwell Locks and Dam 61.2 Maxwell, PA Locks and Dam No. 7 85.0 Greensboro, PA Locks and Dam No. 8 90.8 Point Marion, PA Morgantown Lock and Dam 102.0 Morgantown, WV Hildebrand Lock and Dam 108.0 Morgantown, WV Opekiska Lock and Dam 115.4 Morgantown, WV Ohio River locks and Dam No. 53 18.4 Mound City, IL Locks and Dam No. 52 42.1 Bl3rookport. IL Smithiand Locks and Dam 35.3 Smithland, KY Uniontown Locks and Dam 135.0 Uniontown. KY Newburgh Locks and Dam 204.9 Newburgh, IN Carinelton Locks and Dam 260.3 Cannelton, IN McAlpine Locks and Dam 374.2 Louisville, KY Markland Locks and Dam 449.5 Markland, IN Captain Anthony Meldahi Locks and Dam 544.8 Chilo, OH Greenup Locks and Dam 640.0 Greenup. KY Gailipolis Locks and Dam 701.8 Hogsett, WV Racine Locks and Dam 743.5 Letart Falls, OH Belleville Locks and Dam 777.1 Reedsville. OH Willow Island Locks and Dam 819.3 Waverly, WV Hannibal Locks and Dam 854.6 New Martinsville, WV Pike Island Locks and Dam 896.7 Warwood, WV New Cumberland Locks and Dam 926.6 Stratton. OH Montgomery Island Locks and Dam 949.3 Industry, PA Dashields Locks and Dam 967.7 Glenwillard, PA Emsworth Locks and Dam 974.8 Emsworth, PA Okeechobee Waterway, FL St. Lucie Lock and Dam Moore Haven Lock Ortona Lock and Dam W. P. Franklin Lock and Control Structure 15.1 Stuart, FL 78.0 Moore Haven, FL 93.6 LaBelle FL 121.4 Fort Myers, FL 110 600 110 600 110 600 110 600 110 600 110 600 500 56 400 56 400 7 17 13 Movable 6 18 13 Movable 9 18 12 Movable 7 17 13 Movable 8 17 14 Movable 12 22 13 Movable 12 16 15 38 13 8 Fixed 38 13 10 56 400 25 14 10 Movable 56 400 49 16 14 Fixed 56 360 110 720 56 360 56 720 56 360 56 720 84 720 84 720 56 360 56 360 84 600 84 600 84 600 110 600 110 1,200 110 600 110 1.200 110 1,200 1,200 110 1,200 600 110 1,200 110 600 110 1,200 110 600 110 1,200 110 600 56 360 110 1,200 110 600 110 1,200 110 600 110 1,200 110 600 110 600 110 360 110 1,200 110 600 110 1,200 110 600 110 1,200 110 600 110 1,200 110 600 110 1,200 110 600 110 1,200 110 600 110 600 56 360 110 600 56 360 110 600 56 360 50 250 50 250 50 250 56 400 9 16 16 Fixed 9 16 16 8 12 12 Fixed 8 12 12 17 20 11 Movable 17 20 11 20 21 15 Movable 20 21 15 15 11 10 Fixed 19 15 10 Movable 17 18 15 Movable 21 14 15 Movable 22 18 14 Movable 12 15 10 Movable 12 15 10 Temporary Lock 12 15 11 Movable 12 15 11 Temporary Lock 22 34 12 Movable 22 34 12 22 34 12 Movable 22 34 12 16 32 16 Movable 16 32 16 25 38 13 Movable 25 38 13 37 49 12 Movable 37 19 11 37 19 11 35 50 15 Movable 35 50 15 30 45 15 Movable 30 45 15 30 45 15 Movable 30 45 15 23 18 15 Movable 23 18 15 22 37 15 Movable 22 37 15 22 37 15 Movable 22 37 15 20 35 15 Movable 20 35 15 21 38 17 Movable 21 38 17 21 17 18 Movable 21 17 18 21 17 15 Movable 21 17 15 18 16 15 Movable 18 16 15 10 13 18 Fixed 10 13 18 18 17 13 Movable 18 16 13 13 14 12 Movable 2 10 11 None 11 12 11 Movable 3 13 - Movable 893 1936 14.2 9 NS 682 1936 9.6 9 NS 1,619 1935 14.7 9 NS 1,367 1935 44.1 9 NS 365 1938 18.3 9 NS 822 1931 32.4 9 NS 1948 574 1932 5.7 9 NS 1917 188 1956 0.6 9 100 3,584 1963 3.8 9 100 748 1951 12.6 9 300 195321 670 1907 17.7 9 300 190721 535 1932 197 9 300 1932"21 460 1964 23.8 9 300 1964 610 192521 5.8 9 300 560 192521'22 11.2 9 300 410 1950 6.0 9 300 530 1959 7.4 9 300 366 1964 7.0 9 300 3,978 1929 23.7 9 300 1980 3,073 1928 35.8 9 300 1969 3,560 1980 99.7 9 300 3,516 1975 69.9 9 300 2,272 1975 55.4 9 300 1,965 1972 116.3 9 400 8,627 1961 75.3 9 300 1921 1930 1,395 1963 95.3 9 300 1963 9 300 1,756 1962 95.2 9 300 1962 1,287 1962 61.8 9 300 1,132 1937 41.7 9 300 1,202 1970 33.6 9 300 1,206 1969 36.4 9 300 1,128 1973 35.3 9 1,000 1,098 1972 36.0 9 300 1,306 1965 29.9 9 300 1,315 1961 22.7 9 300 1,379 1936 18.4 9 300 1,585 1929 7.1 9 300 1,717 1921 6.2 9 300 170 1941 15.1 8 80 1953 15.6 8 90 104 1937 15.6 8 90 1,150 1965 7.9 8 90 C-4 APPENDIX C (Continued) NAVIGATION LOCKS AND DAMS OPERABLE SEPTEMBER 30, 1985 Locks Dams Authorized Channel Lift at Miles Width Available Normal Depth on Sills Above Community of Length for Pool Length Year Length Depth Width Project Mouth In Vicinity Chamber Full Width Level Upper Lower Type' (feet) Opened (miles) (feet) (feet) Old River, LA Old River Lock 304.0 Simmesport, L Ouachita and Black Rivers. AR & LA Jonesville Lock and Dam (Black River) 25.0 Jonesville, LA Columbia Lock and Dam (Ouachita River) 117.2 Columbia, LA Calion Lock (Ouachita River) 281.7 Felsenthal Lock (Ouachita River) 226.8 Pearl River, MS and LA Lock 1 29.4" Pearl River, L Lock 2 40.7" Bush, LA Lock 3 43.9" Sun, LA Red River Waterway Lock 1 43.8 Sacramento River, CA Barge Canal Lock 42.8 West Sacramer Snake River, WA Ice Harbor Lock and Dam 9.7 Pasco, WA Lower Monumental Lock and Dam 41.6 Kahlotus, WA Little Goose Lock and Dam 70.3 Starbuck. WA Lower Granite Lock and Dam 107.5 Pomeroy, WA St. Mary's River, MI South Canal: MacArthur Lock 47.0 Sault Ste. Mar Poe Lock 47.0 Sault Ste. Mar North Canal: Davis Lock 47.0 Sault Ste. Mar Sabin Lock 47.0 Sault Ste. Mar A A 75 1,200 35 11 11 None 84 84 84 84 65 65 65 nto, CA ie, MI ie, MI ie, MI ie, MI 600 600 600 600 310 310 310 30 18 18 18 12 18 13 18 14 Movable 13 Fixed 13 Movable 13 Movable 26.7 10 10 None 15 10 10 None 11 10 10 None 84 685 36 22 13 Fixed 86 600 4 13 13 None 86 86 86 86 80 110 80 80 675 675 675 675 100 15 98 15 98 15 100 15 800 22 31 1,200 22 32 1,350 22 24 1,350 22 24 1963 450 1972 400 1972 350 1984 350 1984 12 125 92.2 106.2 50.3 55.2 100 100 100 100 80 80 80 1951 11.1 1951 3.2 1951 13.2 550 1984 44.2 9 200 1961 1.5 13 120 15 Movable 2,790 1962 15 Movable 3,800 1969 15 Movable 2,670 1970 15 Movable 3,200 1975 31 None 32 None 23 None 23 None 31.9 28.7 37.2 32.0 1943 1968 1914 1919 14 14 14 14 27 250 250 250 250 Savannah River, GA New Savannah Bluff Lock and Dam 187.2 Augusta, GA Tennessee River, TN, AL, MS, and KY'* Kentucky Lock and Dam 22.4 Gilbertsville, KY Pickwick Landing Lock and Dam Auxiliary Lock 206.7 Hamburg, TN Main Lock 206.7 Hamburg, TN Wilson Lock and Dam Main Lock 259.4 Florence, AL Auxiliary Lock 259.4 Florence, AL General Joe Wheeler Lock and Dam Main Lock 274.9 Florence, AL Auxiliary Lock 274.9 Florence, AL Guntersville Lock and Dam Main Lock 349.0 Guntersville, AL Auxiliary Lock 349.0 Guntersville, AL Nickajack Lock and Dam 424.7 Chattanooga, TN Chickamauga Lock and Dam 471.0 Chattanooga, TN Watts Bar Lock and Dam 529.9 Breedenton, TN Fort Loudon Lock and Dam 602.3 Lenoir City, TN Melton Hill Lock and Dam (Clinch River) 23.1 Kingston, TN Waterway Connecting Tombigbee and Tennessee Rivers, AL and MS Gainesville Lock and Dam 49.1 Gainesville, AL Aliceville Lock and Dam 89.8 Aliceville, AL Columbus Lock and Dam 117.6 Columbus, MS Aberdeen Lock and Dam 140.4 Aberdeen, MS Lock A and Spillway 154.1 Amory, MS Lock B and Spillway 159.3 Smithville, AL Lock C and Spillway 174.0 Fulton, MS Lock D and Spillway 181.4 Fulton, MS Lock E and Spillway 189.7 Belmont, MS Bay Springs Lock and Dam 194.9 Tupelo, MS 56 360 15 14 12 Movable 360 1936 16.2 9 90 110 600 56 11 13 Tainter 7,976 1944 184.3 9 300 110 110 110 60 110 60 110 60 110 60 60 60 75 110 110 110 110 110 110 110 110 110 110 600 55 10 1,000 55 10 600 94 13 292 94 11 600 400 600 400 600 360 360 360 400 600 600 600 600 600 600 600 600 600 600 48 13 48 15 39 13 39 13 39 13 49 10 58 12 72 12 54 13 36 15 27 15 27 15 27 15 30 15 25 18 25 18 30 18 30 18 84 18 13 Bulkhead 7,385 1937 13 Bulkhead 7,385 1984 13 Bulkhead 3,728 1959 11 Bulkhead 3,728 1927 13 Bulkhead 5,738 1963 13 Bulkhead 5,738 1962 13 Tainter 3,837 1965 12 Tainter 3,837 1939 11 Tainter 3,763 1967 14 Tainter 5,654 1940 12 Tainter 2,646 1942 12 Tainter 3,687 1943 13 Tainter 1,072 1963 15 Movable 15,460 1978 15 Movable 14,790 1979 15 Movable 10,040 1981 15 Movable 10,640 1984 15 Movable - 1985 18 Movable - 1985 18 Movable - 1985 18 Movable - 1985 18 Movable - 1985 18 None 10,640 1985 52.7 9 300 52.7 9 300 15.5 9 300 15.5 9 300 74.1 74.1 75.7 75.7 46.3 58.9 72.4 49.8 38.2 49.1 40.7 27.8 22.8 13.7 14.7 7.4 8.3 5.2 64.5 9 300 9 300 9 300 9 300 9 300 9 300 9 300 9 300 9 300'* 9 300 9 300 9 300 9 300 9 300 9 300 9 300 9 300 9 300 9 300 C-5 APPENDIX C (Continued) NAVIGATION LOCKS AND DAMS OPERABLE SEPTEMBER 30, 1985 Locks Dams Authorized Channel Lift at Miles Width Available Normal Depth on Sills Above Community of Length for Pool Length Year Length Depth Width Project Mouth In Vicinity Chamber Full Width Level Upper Lower Type' (feet) Opened (miles) (feet) (feet) Willamette River at Willamette Falls, OR Lock No. 1 26.0 Oregon City, OR 40 210 20 6 8 None 1872 6 150 Lock No. 2 26.0 Oregon City, OR 40 210 10 6 8 None 1872 Lock No. 3 26.0 Oregon City, OR 40 210 10 6 8 None 1872 Lock No. 4 26.0 Oregon City, OR 40 210 10 6 8 None 1872 .4 Guard Lock 26.4 Oregon City, OR 40 210 10 6 8 None 1872 23.6 6 NS ' Fixed: crest without gates or other facility to control streamflow. Movable: includes any type of crest gates, tainter gates, wickets, or others to control streamflow. ' Above mouth of Mobile River. * Includes length of earth dikes. ' From mouth of Apalachicola River. ' From mouth of Chattahoochee River. * Above Norfolk, VA. ' ' With reference to mean low water, or low mean Gulf as case may be. ' From Gulf Intracoastal Waterway. ' Average high and low water conditions, lift varying widely, depending on tides and river stages. o From foot of Government Street, Mobile, AL. " From mouth of St. Johns River. " Above Head of Passes. " From New Orleans, LA. "Salt water barrier in down position. Will clear 15-foot vessels in normal position. " Above the Ohio River. " Channel completed to depth of 6.5 feet. "From mouth of West Pearl River. " Tennessee River locks operated by the Corps, dams operated by the Tennessee Valley Authority. " 300-foot width from lock to mouth of Clinch River and 175-foot width upstream from lock to Clinton, TN. - Dates shown represent replacement structures. " Dates shown represent reconstruction for locks and dams Nos. 2-8 inclusive. " Dam was rebuilt in 1959. *Old 110' X 358' lock replaced in 1957. " Inoperable, caretaker status September 7, 1982. " Inoperable, caretaker status October 1, 1981. C-6 APPENDIX D NAVIGATION PROJECTS UNDER CONSTRUCTION DURING FISCAL YEAR 1985 Fiscal Year Fiscal Placed in Completed or Year Useful Scheduled for Project Started Operation Completion Nature of Project AIWW-Replacement of Federal Hwy Bridges in NC ......... Barbers Point Harbor, Oahu, Hawaii ........................ Barnegat Inlet, NJ ............................ ........ Brandon Road Lock and Dam, Illinois Waterway, IL .......... Burns Waterway Small Boat Harbor, IN (Sec 107) ............ Calumet Harbor & River, IL and IN ......................... Calumet-Sag. Mod., Illinois Waterway, IL and IN, Part 1 ....... Cannelton Locks and Dam, Ohio River, IN and KY ........... Channel to Newport News, VA (1965 Mod.) .................. Columbia River at the Mouth, 55' Channel, WA and OR ....... Columbia River, Ilwaco, W A ............. .................. Cooper River, Charleston Harbor, SC ....................... Corpus Christi Ship Channel, TX ........................... Dresden Island Lock and Dam, Illinois Waterway, IL ......... Emsworth Locks and Dams, Ohio River, PA ................. Fisherman's W harf Area, CA ............................... Falls of the Ohio National Wildlife Conservation Area, IN and KY .................................................... Gallipolis Locks and Dam, Ohio River ....................... Homer Harbor, AK (Sec 107) ............ ................... Irondequoit Bay, NY ...................................... Kaskaskia River, IL ....................................... Krebs Lake, M S (Sec 107) ................. ................. Lock and Dam 26 Replacement IL and MO .................. Lockport Lock, Illinois Waterway, IL ....................... Locks and Dam 52, IL and KY ............. ................. Locks and Dam 53, IL and KY ............. ................. M anitowoc Harbor, W I ........................ ............ Marseilles Lock and Dam, Illinois Waterway, IL ............. McClellan-Kerr Arkansas River Navigation System, AR ...... M etlakatla Harbor, AK ............................ ........ Mississippi River between Ohio and Missouri Rivers .......... Mississippi River, Gulf Outlet, LA .......................... Missouri River, Sioux City, IA to mouth .................. Montgomery Locks & Dams, Ohio River, PA ................. Mouth of Colorado River, TX (Gulf Intracoastal Waterway) ... New York Harbor, NY and NJ .............................. Newburgh Locks & Dam, Ohio River, IN and KY ............. Norfolk Harbor Channel, VA (1965 Mod.) .................... Ocean City Harbor and Inlet, MD ............. .............. Ogdensburg Hbr, NY (Sec 107) ............ ................. Ouachita and Black River, AR and LA ...................... Port Everglades Harbor, FL ............ ................... Red River Emergency Bank Protection ...................... Red River WW, Mississippi River to Shreveport, LA .......... Rota Harbor, Northern Marianas (Sec 107)................. San Diego River and Mission Bay, CA ..................... San Francisco Bay to Stockton, CA (John F. Baldwin and Stockton Ship Channels) ......... ................. Santa Cruz Harbor, CA ......... ...................... Siuslaw River and Bar, OR ......... ................. Smith Island, MD (Sec 107) ........ ................. 1974 1982 1985 1983 1984 1964 1955 1962 1967 1984 1985 1977 1972 1980 1980 1984 1984 1985 1984 1984 1966 1983 1974 1983 1979 1979 1981 1985 1963 1979 1910 1958 1912 19811 1985 1966 1968 1966 1968 1985 1984 1974 1983 1984 1968 1981 1980 1983 1984 1976 Incremental 1965 1969 1966 1983 1983 1964 1979 1973 1974 1982 1948 1971 1985 1983 1982 D-1 1967 1936 1985 1984 1985 1982 Indefinite Replacement of existing bridges 1985 Dredging and breakwater 1991 Jetty realignment and dredging 1988 Major rehabilitation of lock and dam 1986 Dredging and breakwater Indefinite Dredging and channel, widening and deepening Indefinite Channel improvements and relocation 1986 Replacement of existing locks and dams 43-45 inclusive Indefinite Deep draft channel widening and deepening, deferred anchorage construction 1985 Dredging 1985 Dredging, deepening channel 1986 Rediversion of river and powerhouse construction 1989 Dredging 1984 Major rehabilitation of locks and dams 1985 Major rehabilitation of lock and dam 1987 Breakwater 1986 Protection of a National Natural Landmark 1995 Replacement of existing locks and major rehabilitation of the dam 1985 Harbor expansion 1986. Dredging and breakwater 1986 Lock, dam and channel 1984 Dredging, navigation channel 1991 Lock and dam 1987 Major rehabilitation of lock 1985 Major rehabilitation of locks and dam 1987 Major rehabilitation of locks and dam 1984 Dredging and breakwater 1989 Major rehabilitation of lock and dam 1989 Locks and dams 1984 Breakwater and dredging 2000 Regulating works 1984 Dredging and jetties Indefinite Navigation and bank stabilization complete. Wildlife mitigation awaiting authorization 1987 Major rehabilitation of locks & dams 1989 Breakwaters, dredging, and recreation 1993 Collection and removal of drift 1987 Replacement of locks and dams 46 and 47 Indefinite Deep draft channel, deepening and deferred anchorage const. 1985 Rehabilitation of south jetty 1985 Dredging and diked disposal 1994 Replacement of six locks and dams, channel deepening to 9 feet and realignment 1986 Dredging 1985 Bank protection Indefinite Lock and dam construction. Channel improvement and realignment 1985 Dredging and breakwater Indefinite Dredging and breakwater Indefinite Deep draft channel, widening, deepening and dredging 1986 Sand bypass system 1986 Extending jetties 1983 Channel cut with breakwater APPENDIX D (Continued) NAVIGATION PROJECTS UNDER CONSTRUCTION DURING FISCAL YEAR 1985 Fiscal Year Fiscal Placed in Completed or Year Useful Scheduled for Project Started Operation Completion Nature of Project Smithland Locks and Dam, IL, IN, and KY ................. 1971 South Channel, Government Island, OR (Sec 107) ........... 1983 Starved Rock Lock and Dam, Illinois Waterway, IL ......... 1980 Tampa Harbor, FL (Main Channel) ........................ 1976 Tennessee-Tombigbee Waterway, AL and MS .............. 1973 Uniontown Locks and Dam, Ohio River, IN and KY ......... .1965 W allisville Lake, TX ............... ...................... 1967 1980 1985 1985 1970 1987 Replacement of existing locks and dams 50 and 51 1985 Dredging 1985 Major rehabilitation of lock and dam 1986 Dredging 1985 Dredging and locks and dams 1986 Replacement of locks and dams 48 and 49 Indefinite Multipurpose lake (navigation, salinity control, water supply, fish & wildlife, & recreational) 'Walter Jones Bridge completed; Coinjock Bridge under contract; the three remaining bridges have not been funded. D-2 APPENDIX E MULTIPLE-PURPOSE PROJECTS INCLUDING POWER IN OPERATION SEPTEMBER 30, 1985 Flood Control andlor Total Nav. Feature Storage Placed Initial Existing Scheduled Ultimate Community in Capability in Useful Power Installation Installation Installation Project Height Length Project River Vicinity (acre-feet)' Operation CY In FY (KW) (KW) (KW) Functions Type' (Feet) (Feet) Albeni Falls, ID Pend Oreille Newport, WA 1,153,000 Allatoona Lake, GA Etowah Cartersville, GA 670,000 Barkley Dam & Cumberland Grand Rivers, Lake Barkley, KY KY & TN 2,082,000 Beaver Lake, AR White Eureka Springs, AR 1,952,000 Big Bend Dam (Lake Sharpe), SD Missouri Chamberlain, SD 1,883,000 Blakely Mountain Dam-Lake Ouachita, AR Ouachita Mt. Pine, AR 2,768,000 Bonneville L&D Lake Bonneville, OR & WA Columbia Bonneville, OR 537,000 Broken Bow Lake, OK Mountain Fork Broken Bow, OK 1,368,230 Buford Dam Lanier, GA Chattahoochee Buford, GA 2,554,000 Bull Shoals Lake, White Mountain Home, AR & MO AR 5,408,000 Clarence Cannon Dam Salt Perry, MO 1,428,000 Carters Dam, GA Coosawatte Carters, GA 472,756 Center Hill Lake, TN Caney Fork Lancaster, TN 2,092,000 Cheatham L&D, TN Cumberland Ashland City, TN 104,000 Chief Joseph Dam (Rufus Woods Lake), WA Columbia Bridgeport, WA 593,100 Clark Hill Lake, GA & SC Savannah Augusta, GA 2,900,000 Cordell Hull L&D, TN Cumberland Carthage, TN 310,900 Cougar Lake, OR S. Fork McKenzie Blue River, OR 219,000 Dale Hollow Lake, TN & KY Obey Celina, TN 1,706,000 Dardanelle L&D, AR Arkansas Dardanelle, AR 486,200 DeGray Lake, AR Caddo Arkadelphia, AR 831,900 Denison Dam (Lake Texoma), TX & OK Red Denison, TX 5,312,300 Detroit Lake, OR, including Big Cliff Lake, OR North Santiam Mill City, OR 461,000 Dworshak Dam & N. Fork, Reservoir, ID Cleanwater Orofino, ID 3,453,000 Eufaula Lake, OK Canadian Eufaula, OK 3,825,400 Fort Gibson Lake, OK Grand (Neosho) Ft. Gibson, OK 1,284,400 Fort Peck Lake, MT Missouri Glasgow, MT 18,909,000 Fort Randal Dam (Lake Francis Case), SD Missouri Lake Andes, SD 5,574,000 Garrison Dam (Lake Sakakawea), ND Missouri Riverdale, ND 24,137,000 Gavins Point Dam (Lewis & Clark Lake), SD & NE Missouri Yankton, SD 504,000 Green Peter Lake, OR, including Foster Lake, OR Middle Santiam Sweet Home, OR 491,000 Greers Ferry Lake, AR Little Red Heber Springs 2,844,000 Harry S. Truman Dam & Res. Osage Warsaw, MO 5,202,000 Hartwell Lake, GA & SC Savannah Hartwell, GA 2,842,700 Hills Creek Lake, Middle Fork OR Willamette Oakridge, OR 356,000 Ice Harbor L&D (Lake Sacajawea), WA Snake Pasco, WA 417,000 Jim Woodruff Dam (Lake Seminole), FL, GA & AL Appalachicola Chattahoochee, FL 367,300 John Day L&D (Lake Umatilla), OR & WA Columbia Rufus, OR 2,500,000 John H. Kerr Dam & Reservoir, NC & VA Roanoke Boydton, VA 2,750,300 Robert F. Henry L&D, AL Alabama Benton, AL 234,200 J. Percy Priest Dam & Reservoir, TN Stones Nashville, TN 652,000 1952 1955 42,600 1950 1950 74,000 1964 1963 1964 1966 130,000 1965 112,000 1965 468,000 1953 1956 75,000 1938 1968 1956 1952 1983 1975 1948 1952 1955 1952 1973 1963 1943 1969 1969 1944 1953 1972 1964 1950 1938 1953 1954 1938 1,076,600 1970 100,000 1957 86,000 1953 340,000 1985 58,000 1975 500,000 1951 135,000 1958 36,000 42,600 NFPR C 74,000 FPRW C 130,000 NPFR CE 112,000 FPSR CE 468,000 FPRIW E 75,000 FPRW E 1,076,600 NPR C 100,000 FPWSR E 86,000 NFPW E 340,000 FPR C 58,000 FNPRSW CE 500,000 FPRW ER 135,000 FPR CE 36,000 NPR C 1956 2,069,000 204,1603 2,273,160 PIR C 1953 280,000 280,000 NFPRS CE 1974 100,000 100,000 NPR CE 1964 25,000 64,600 NFPRI ER 1949 54,000 54,000 FPR C 1965 124,000 124,000 NPR C 1972 68,000 108,000 FNPRS E 1945 70,000 175,000 FPSRN E 1954 118,000 1973 400,000 1964 90,000 1953 45,000 1944 185,250 1954 320,000 1956 430,000 1956 1957 100,000 1967 1962 1982 1961 1961 1967 100,000 1964 96,000 1982' 160,000 1962 344,000 1962 30,000 1962 1962 603,000 1957 1957 30,000 1968 1969 2,160,000 1952 1972 1953 204,000 1975 68,000 1967 1970 28,000 118,000 NFPRI C 1,060,000 PNFR C 90,000 ENPS E 67,500 FP CE 185,250 NFPRIW E 320,000 NFPRIW E 430,000 NFPRIW E 100,000 NFPRIW E 100,000 PFNIR C 96,000 FPRS C 160,000 FPRW CE 344,000 NFPRS CE 30,000 NFPRI GE 603,000 NPRI CE 30,000 NPRW CE 2,700,000 NPRFI CE 204,000 FPRW CE 68,000 NPRW CE 28,000 FPRW CE 90 1,055 190 1,250 157 9,959 228 2,575 95 1G,570 235 1,100 122 2,690 225 2,750 192 5,400 258 2,256 138 1,700 450 1,950 250 2,160 75 801 220 4,300 200 5,680 93 1,306 445 1,738 200 1,717 68 2,683 243 3,400 165 17,200 382 1,528 717 3,300 114 3,200 110 2,990 251 21,026 165 10,700 210 11,300 74 8,700 340 1,380 243 1,704 96 5,000 204 17,852 304 2,150 130 2,790 67 6,150 161 5,900 144 22,285 101 14,962 147 2,716 E-1 APPENDIX E (Continued) MULTIPLE-PURPOSE PROJECTS INCLUDING POWER IN OPERATION SEPTEMBER 30, 1985 Flood Control and/or Total Nav. Feature Storage Placed Initial Existing Scheduled Ultimate Community in Capability in Useful Power Installation Installation Installation Project Height Length Project River Vicinity (acre-feet)' Operation CY In FY (KW) (KW) (KW) Functions Type 2 (Feet) (Feet) Keystone Lake, OK Laurel River Lake, KY Libby Dam, Lake Koocanusa, MT Little Goose L&D (Lake Bryan), WA Lookout Point Lake, including Dexter Lake, OR Lost Creek Lake, OR Lower Granite L&D, WA Lower Monumental L&D, WA McNary L&D - Lake Wallula, OR & WA Millers Ferry L&D, AL Narrows Dam - Lake Greeson, AR New Melones Lake, CA' Norfolk Lake, AR & MO Oahe Dam (Lake Oahe), SD & ND Old Hickory L&D, TN Ozark-Jeta Taylor L&D, AR Philpott Lake, VA Robert S. Kerr L&D and Reservoir, OK Sam Rayburn Dam & Reservoir, TX St. Mary's River, MI Snettisham, AK' Stockton Lake, MO Table Rock Lake, AR & MO Tenkiller Lake, OK The Dalles L&D (Lake Celilo), WA & OR Walter F. George L&D, GA & FL Webbers Falls L&D, OK West Point Lake, AL & GA Whitney Lake, TX Wolf Creek Dam (Lake Cumberland), KY Arkansas Laurel Kootenai Snake Middle Fork, Willamette Rogue Snake Snake Columbia Alabama Little Missouri Stanislaus North Fork Missouri Cumberland Arkansas Roanoke Arkansas Angelina Great Lakes Speel Sac White Illinois Columbia Chattahoochee Arkansas Chattahoochee Brazos Tulsa, OK London, KY Libby, MT Starbuck, WA Lowell. OR Trail, OR Pomeroy, WA 1.737,600 1964 435,600 1973 5,869,000 1972 565.000 1970 483,000 1954 465.000 1977 484,000 1975 Kahlotus, WA 376,000 1969 Umatilla, OR 1,550,000 1953 Camden. AL 331,800 1969 Murfreesboro, AR 407,900 1950 Oakdale, CA 2,400,000 1978 Norfolk, AR 1,983,000 1943 Pierre, SD 23,337,000 1959 Hendersonville, TN 545,000 1954 Ozark, AR 148,400 1969 Bassett, VA 318,500 1951 Sallisaw. OK Jasper, TX Sault Ste. Marie, MI Juneau, AK Stockton, MO Branson, MO Gore, OK 525,700 1970 3,997,600 1965 1855 352,400 1,674,000 1969 3,462,000 1958 1,230,800 1952 The Dalles, OR 53,000 1957 Fort Gaines, GA 934,000 1963 Webbers Falls, OK 170,100 1970 West Point, GA 604,500 1975 Whitney. TX 1,999,500 1953 Cumberland Jamestown, KY 6,089,000 1950 1968 1978 1975 1970 1955 1977 1975 70,000 61,000 525,000 810,000 135,000 49,000 810,000 1969 810,000 1954 1970 1350 1979 1944 1962 1957 1973 1954 1971 1966 1952 1973 1973 1959 1953 980,000 75,000 25,500 300,000 80,550 595,000 100,000 100,000 14,000 110,000 52,000 18,400 46,700 27,000' 45,200 200,000 34,000 1957 1,806,800 1963 130,000 1973 60,000 1975 73,375 1954 30,000 1952 270,000 70,000 FNPWS E 121 4,600 61,000 FPRW R 282 1,420 840,000 FPR C 420 3,055 810,000 NPRI CE 160 2,670 135,000 NFPRI CE 243 3,381 49,000 DFPISWR CE 345 3,600 810,000 NPRIF CE 146 3,200 810,000 NPRI CE 135 3,800 1,625,000 NPRI CE 183 7,300 75,000 NPRW CE 90 11,380 25,500 FPRW C 183.5 941 300,000 FIPRW ER 625 1,560 163,000 FPRS C 216 2,624 595,000 NFPRIW E 245 9,300 100,000 NPR CE 98 3,605 100,000 NPR C 58 2,480 14,000 FPR C 220 892 110,000 NPR E 75 7,230 52,000 FPWR CE 120 19,430 18,400 NP ControlG ate 73,700 P C9 18 338 45,200 FPRW CE 128 5,100 200,000 FPR CE 252 6,423 3 000 FP E 197 3,000 1,806,800 NPR CR 300 8,875 130,000 NPRW CE 114 13,585 60,000 NP E 84 4,370 108,375 FPRW CE 97 7,250 30,000 FPR CE 159 17,695 270,000 FPR CE 258 5,736 Total of all storage functions, including inactive and dead storage to normal full pool level 2 G: gravel; R: rock; C: concrete; E: earth ' Chief Joseph Additional Units & Operating Units 1-16 2 All units are synchronized-to-line and two units have passed the pumpback test. However, due to damaging effects to fish, no further pumping will be done for their testing or operation until a solution to the problem is found. ' Being operated for the Department of Interior by the Bureau of Reclamation ' Being operated by the Alaska Power Administration * Crater Lake Unit ' Weir for Long Lake Nomenclature for Project Functions D-Debris Control P -Power F-Flood Control R -Public Recreation Annual Attendance exceeding 5,000 I -Irrigation S -Water Supply N-Navigation W-Fish and Wildlife (Federal or State) E-2 APPENDIX F MULTIPLE-PURPOSE PROJECTS INCLUDING POWER UNDER CONSTRUCTION SEPTEMBER 30, 1985 Nameplate Capacity Fiscal Scheduled Scheduled Year for for Scheduled Ultimate Project Started Operation Completion Functions Installation Installation Bonneville Second Powerhouse, OR and WA ...... 1974 1981 1991 PR 558,200 558,200 Clarence Cannon Dam, Salt River, MO ............ 1966 1985 1986 FNPRSW 58,000 58,000 Harry S. Truman Dam and Reservoir, Osage River, MO .................................. 1965 * 19821 19871 FRPW 160,000 160,000 Richard B. Russell Dam and Lake, Savannah River, GA and SC ............................ 1975 1985 1991 FRP 600,000 600,000 Copper River, Charleston Hbr, SC ................ 1977 1985 1986 NWD 84,000 84,000 Snettisham, AK .............................. 1967 1989 1989 P 73,700 27,000 1 All units are synchronized-to-line and two units have passed the pumpback test. However, due to damaging effects to fish, no further pumping will be done for either testing or operation until a solution to the problem is found. KEY D-Redevelopment F -Flood Control I -Irrigation N-Navigation P -Power R -Recreation S -Water Supply W-Fish and Wildlife F-l FLOOD DAMAGES PREVENTED BY CORPS-CONTROLLED PROJECTS (IN THOUSANDS OF DOLLARS) DISTRIBUTION BY CORPS DISTRICT District Memphis New Orleans St. Louis Vicksburg Kansas City Omaha New England Baltimore New York Norfolk Philadelphia Buffalo Chicago Detroit Rock Island St. Paul Alaska Portland Seattle Walla Walla Huntington Louisville Nashville Pittsburgh Pacific Ocean Charleston Jacksonville Mobile Savannah Wilmington Los Angeles Sacramento San Francisco Albuquerque Fort Worth Galveston Little Rock Tulsa TOTAL During FY 1985 254,050 8,454,803 28,540 1,083,311 18,365 14,190 625 11,557 1,438 0 5,828 14,910 0 15,197 56,569 3,093 6,846 92,309 1,703 338 75,544 133,954 45 59,298 0 167 2,079 130 1,440 17,485 85,000 4,300 0 127,698 10,040 18,800 77,661 90,897 10,768,210 G-1 FLOOD DAMAGES PREVENTED BY CORPS-CONTROLLED PROJECTS (IN THOUSANDS OF DOLLARS) DISTRIBUTION BY REGION Region New England Mid-Atlantic Gulf and South Atlantic Ohio Tennessee Great Lakes Upper Mississippi Souris-Red-Rainy Missouri Arkansas-Red-White Lower Mississippi Rio Grande Texas and Gulf Colorado Great Basin California Columbia-North Pacific Alaska Hawaii TOTAL During FY 1985 625 18,823 21,301 268,796 45 30,107 57,941 1,721 32,555 168,558 9,820,704 127,698 28,840 14,300 2,200 72,800 94,350 6,846 0 10,768,210 * Revised Figures. INDEX ANNUAL REPORT FY 85 OF THE CHIEF OF ENGINEERS ON CIVIL WORKS ACTIVITIES INDEX The following abbreviations are used in the index: VICKSBURG, MISS., DISTRICT MEMPHIS, TENN., DISTRICT NEW ORLEANS, LA., DISTRICT ST. LOUIS, MO., DISTRICT MISSISSIPPI, RIVER AND TRIBUTARIES PROJECT KANSAS CITY, MO., DISTRICT OMAHA, NEBR., DISTRICT BALTIMORE, MD., DISTRICT NEW YORK, N.Y., DISTRICT NORFOLK, VA., DISTRICT PHILADELPHIA, PA., DISTRICT BUFFALO, N.Y., DISTRICT CHICAGO, ILL., DISTRICT MISSISSIPPI RIVER BETWEEN MISSOURI RIVER AND MINNEAPOLIS, MINN. DETROIT, MICH., DISTRICT ROCK ISLAND, ILL., DISTRICT ST. PAUL, MINN., DISTRICT NEW ENGLAND DIVISION ALASKA DISTRICT PORTLAND, OREG., DISTRICT A Aberdeen, Ohio (ORH) 25-21 Aberdeen Creek, Va. (NAO) 5-22 Abilene, Kans. (MRK) 20-19, 20-21 Abiquiu Dam, N. Mex. (SWA) 17-4, 17-9, 17-11 Absecon Creek, N.J. (NAP) 3-21 Absecon Inlet, N.J. (NAP) 3-21 Accotink Creek, Va. (NAB) 4-34 Adams, Mass. (NAN) 2-32 Adams Creek, S.C. (SAN) 7-7, 7-15 Adams Levee, Ind. (ORL) 24-22, 24-26 Addison, N.Y. (NAB) 4-13, 4-25 NPS NPW ORD ORH ORL ORN ORP POD SAJ SAM SAN SAS SAW SPK SPL SPN SWA SWF SWG SWL SWT SEATTLE, WASH., DISTRICT WALLA WALLA, WASH., DISTRICT OHIO RIVER DIVISION HUNTINGTON, W. VA., DISTRICT LOUISVILLE, KY., DIVISION NASHVILLE, TENN., DISTRICT PITTSBURGH, PA., DISTRICT PACIFIC OCEAN DIVISION JACKSONVILLE, FLA., DISTRICT MOBILE, ALA., DISTRICT CHARLESTON, S.C., DISTRICT SAVANNAH, GA., DISTRICT WILMINGTON, N.C., DISTRICT SACRAMENTO, CALIF., DISTRICT LOS ANGELES, CALIF., DISTRICT SAN FRANCISCO, CALIF., DISTRICT ALBUQUERQUE, N. MEX., DISTRICT FORT WORTH, TEX., DISTRICT GALVESTON, TEX., DIVISION LITTLE ROCK, ARK., DISTRICT TULSA, OKLA., DISTRICT Adena, Ohio (Short Creek) (ORP) 26-23 Adkin Branch, N.C. (SAW) 6-28 Afono Area and Aoa Area, American Samoa (POD) 36-11 Agana Small Boat Harbor, Guam (POD) 36-10 AIWV--Mooring Basins, N.C. (SAW) 6-28 Airport Road Bridge, Frankstown, Miss. (SAM) 10-13, 10-28, 10-39 Ala Wai Small Boat Harbor, Hawaii (POD) 36-10 Alabama River at Montgomery, Ala. (SAM) 10-43 I-1 LMK LMM LMN LMS MR+T MRK MRO NAB NAN NAO NAP NCB NCC NCD NCE NCR NCS NED NPA NPP REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Alabama-Coosa Rivers, Ala. and Ga. (SAM) 10-18, 10-29, 10-40, 10-45 Alameda Creek, Calif. (SPK) 35-29 Alamo Lake, Ariz. (SPL) 33-5, 33-14, 33-20 Alamogordo Diversion Channel, Tularosa (Closed) Basin, N. Mex. (SWA) 17-11 Albemarle and Chesapeake Canal (Great Bridge, Va.) (NAO) 5-21 Albeni Falls Dam, Idaho (NAS) 38-9, 38-16, 38-21 Albuquerque Diversion Channels, N. Mex. (SWA) 17-1, 17-8 Alford, Mass. (NED) 1-22, 1-42, 1-49 Algiers Lock and Canal, La. (LMN) 11-3, 11-18 Algoma Harbor, Wis. (NCE) 31-76, 31-77 Alhambra Creek, Calif. (SPK) 35-29 Aliso Creek Dam, Calif. (SPL) 33-30 Allatoona Lake, Ga. (SAM) 10-21, 10-30, 10-41 Allegany, N.Y. Unit I (Allegheny River) (ORP) 26-22, 26-26 Allegany, N.Y. Unit II (Five Mile Creek Area) (ORP) 26-22, 26-26 Allegheny River, Pa. (0RP) 26-2, 26-13, 26-17, 26-21, 26-26 Allegheny River, Pa., Locks and Dams (ORP) 26-24 Allegheny River, Oil City, Pa. (0RP) 26-3, 26-13 Allentown, Pa. (NAP) 3-23 Allenville, Ariz. (SPL) 33-25 Alley Bay, Beals, Maine (NED) 1-42 Alloway Creek, N.J. (NAP) 3-21 Alluvial Valley Mapping (MR+T) 42-3 Alma Harbor, Wis. (NCD) 29-7 Almond Lake, N.Y. (NAB) 4-14, 4-25 Almond Village, N.Y. (NAB) 4-37 Aloha-Rigolette Area, Grant and Rapides Parishes, La. (LMN) (LMK) 11-22, 12-24, 12-25 Alpena Harbor, Mich. (NCE) 31-2, 31-39, 31-55 Alpine Dam, Rockford, Ill. (NCR) 28-16 Alpine, Tex. (SWA) 17-11 Alsea River, Oreg. (NPP) 37-45 Altamaha, Oconee, and Ocmulgee Rivers, Ga. (SAS) 8-1, 8-11, 8-12 Alteration of Berwick Bay Bridge (LMN) 11-20 Alternative for Sugar Hill Reservoir (NED) 1-44 Alton, Ind. (ORL) 24-22, 24-25 Altus Reservoir, Okla. (SWT) 19-18 Alum Creek Lake, Ohio (ORH) 25-2, 25-12, 25-16 Alvin R. Bush Dam, Pa. (NAB) 4-19, 4-26 Amazon Creek, Oreg. (NPP) 37-48 American Lake, Vicinity of Fort Lewis, Wash. (NPS) 38-25 American River, Calif. (SPK) 35-29 Ames Dam and Reservoir, Skunk River, Iowa (NCR) 28-3, 28-8, 28-12 Amesbury, Mass. (NED) 1-22, 1-42 Amesbury, Powow and Merrimack Rivers, Mass. (NED) 1-50 Amite River, La. (MR+T) 42-15 Amite River and Bayou Manchac, La. (LMN) 11-20 Amite River and Tributaries, La. (LMN) 11-22 Amsterdam, Ohio (ORP) 26-22, 26-28 Anacortes Harbor, Wash. (NPS) 38-24, 38-30 Anacortes Navigation Channel, Wash. (NPS) 38-24 Anacostia River and Flats (NAB) 4-34 Anacostia River and Tributaries, Md. (NAB) 4-36, 4-39 Anacostia River and Tributaries, Flood Protection and Navigation Improvements, D.C. and Md. (NAB) 4-36 Anacostia River Basin, Md. (NAB) 4-39 Anaheim Bay Harbor, Orange County, Calif. (SPL) 33-24 Anahuac Channel, Tex. (SWG) 15-7 Anchorage Harbor, Alaska (NPA) 40-1, 40-8, 40-10, 40-13 Anchorages, Va. (NAO) 5-19 Anclote River, Fla. (SAJ) 9-47 Andalusia Harbor, Ill. (NCP) 29-7 Anderson, Ind. (ORL) 24-21 Anderson Park, Newport News, Va. (NAO) 5-23 Andover Lake, Conn. (NED) 1-44 Andrews, George W., Lock and Dam, Ala. and Ga. (SAM) 10-22, 10-30, 10-41 Andrews River, Mass. (NED) 1-37 Angler-Use Sites, Meramec Basin, Mo. (LMS) 14-14 Annapolis Harbor, Md. (NAB) 4-34 Ansonia, Conn. (NED) 1-22, 1-42, 1-49 Anthony Shoals Dam and Lake, Ga. (SAS) 8-17 Apalachee Bay, Fla. to New Orleans, La. (SAM) 10-35 Apalachicola Bay, Fla. (SAM) 10-3, 10-26, 10-32 Apalachicola Bay to St. Marks River, Fla. (SAM) 10-35 Apalachicola, Chattahoochee and Flint Rivers, Ala. Ga. and Fla. (SAM) 10-21, 10-30, 10-41, 10-46 Apalachicola River to St. Andrew Bay, Fla. (SAM) 10-35 I-2 INDEX Apoon Mouth of Yukon River, Alaska (NPA) 40-12 Appleton First Lock, Wis. (NCE) 31-75 Appleton Fourth Lock, Wis. (NCE) 31-75 Appleton Lower Dam, Wis. (NCE) 31-75 Appleton Second Lock, Wis. (NCE) 31-75 Appleton Third Lock, Wis. (NCE) 31-75 Applegate Lake, Oreg. (NPP) 37-13, 37-30, 37-40, 37-53 Appomattox River, Va. (NAO) 5-22 Apponaug Cove, R.I. (NED) 1-37 Appoquinimink River, Del. (NAP) 3-21, 3-24 Aquashicola Reservoir, Pa. (NAP) 3-23 Aquatic Plant Control Charleston, S.C., District (SAN) 7-2, 7-9, 7-11, 7-15 Detroit, Mich., District (NCE) 31-35 Galveston, Tex., District (SWG) 15-2, 15-12, 15-15, 15-26 Jacksonville, Fla., District (SAJ) 9-2, 9-26, 9-33, 9-47 Mobile, Ala., District (SAM) 10-3, 10-26, 10-32 New England Division (NED) 1-3, 1-25, 1-32 New Orleans, La., District (LMN) 11-20 New York, N.Y., District (NAN) 2-2, 2-19, 2-23 Philadelphia, Pa., District (NAP) 3-21 Portland, Oreg., District (NPP) 37-8 Sacramento, Calif., District (SPK) 35-29 Savannah, Ga., District (SAS) 8-2, 8-11, 8-16 Seattle, Wash., District (NPS) 38-4 Southwestern Division (SWG) 15-2, 15-12, 15-15, 15-26 St. Paul, Minn., District (NCS) 27-18 Wilmington, N.C., District (SAW) 6-2, 6-18, 6-25 Aquia Creek, Va. (NAB) 4-34 Aquilla Lake, Tex. (SWF) 16-2, 16-14, 16-18 Ararat River, Surry County, N.C. (SAW) 6-9, 6-19 Arbuckle Reservoir, Okla. (SWT) 19-18 Arcadia, Wis. (NCS) 27-28 Arcadia Harbor, Mich. (NCE) 31-3, 31-39, 31-55 Arcadia Lake, Okla. (SWT) 19-2, 19-9, 19-13 Arch Creek, Fla. (SAJ) 9-54 Archers Creek, S.C. (SAN) 7-15 Ardsley, N.Y. (NAN) 2-15, 2-21, 2-26 Area East of Albany, Oreg. (NPP) 37-50 Arecibo Harbor, P.R. (SAJ) 9-2, 9-26, 9-33, 9-46 Arkabutla Lake, Miss. (MR+T) 42-20, 42-59 Arkansas-Red River Basins Chloride Control, Okla. and Tex. (SWT) 19-2, 19-3, 19-9, 19-13 Arkansas River Basin, Ark. Okla. & Kans. (SWL) (SWT) 18-2, 18-10, 18-13, 18-18, 18-21, 19-16 Arkansas River Project Levees (MR+T) 42-46, 42-49 Arkansas River Standard Revetments and Dikes (MR+T) 42-37 Arkport Dam, N.Y. (NAB) 4-14, 4-25 Arlington, Alkali Canyon, Oreg. (NPP) 37-48 Arlington Lake, Mo. (MRK) 20-20 Armuchee Creek, Ga. (SAM) 10-43 Arroyo Colorado, Tex. (SWG) 15-9, 15-13, 15-24 Asan Village, Territory of Guam (POD) 36-3, 36-7 Ashland, Ky. (ORH) 25-20, 25-22 Ashland Harbor, Wis. (NCE) 31-3, 31-39, 31-55 Ashley River, S.C. (SAN) 7-7, 7-15 Ashtabula Harbor, Ohio (NCB) 32-2, 32-17, 32-23 Asotin Creek, Idaho (NPW) 39-16 Asotin Dam, Idaho and Wash. (NPW) 39-18 Asquiroga Bay, Territory of Guam (POD) 36-3, 36-7 Astoria Turning Basin, Oreg. (NPP) 37-45 Atchafalaya Basin Floodway (MR+T) 42-45, 42-49, 42-50 Atchafalaya River, Morgan City to Gulf of Mexico, La. (LMN) 11-20 Atchafalaya River and Bayous Chene, Boeuf, and Black, La. (LMN) 11-20 Atchalafaya River Basin, La. (MR+T) 42-5, 42-13, 42-28, 42-56, 42-58 Atchafalaya River, Morgan City to Gulf of Mexico, La. (LMN) 11-32 Atchalafaya River, Standard Revetments (MR+T) 42-32 Atchison, Kans. (MRK) 20-19 Athalia, Ohio (ORH) 25-21 Athens, Ohio (ORH) 25-20, 25-22 Atlantic Beach Channels, N.C. (SAW) 6-25, 6-29 Atlantic City, N.J. (NAP) 3-23 Atlantic Coast of N.J. Sandy Hook to Barnegat Inlets (NAN) 2-31 Atlantic Gulf Ship Canal, Fla. (SAJ) 9-47 Atlantic Intracoastal Waterway between Norfolk, Va. and St. Johns River, Fla. (NAO) (SAW) (SAN) (SAS) (SAJ) 5-2, 5-13, 5-17, 5-21, 6-2, 6-18, 6-22, 7-2, 7-9, 7-11, 8-2, 8-11, 8-13, 9-2, 9-26, 9-33 I-3 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Au Sable Harbor, Mich. (NCE) 31-3, 31-39, 31-55 Auasi Harbor, American Samoa (POD) 36-10 Aubrey Lake, Tex. (SWF) 16-9, 16-15, 16-19 Auburn, N.Y., Owasco Outlet (NCB) 32-37 Augusta, Ga. (SAS) 8-16 Augusta, Ky. (ORB) 25-20 Augusta Levee, Kans. (SVT) 19-15 Aunuu Harbor, American Samoa (POD) 36-10 Aurora, Ind. (ORL) 24-22, 24-26 Aurora, Westerly Creek-Kelley Road Dam, Colo. (MRO) 21-20 Avoca, N.Y. (NAB) 4-14, 4-25 Avon Harbor, N.C. (SAW) 6-4, 6-18, 6-29 Aylesvorth Creek Lake, Pa. (NAB) 4-13, 4-24 B B. Everett Jordan Dam and Lake, N.C. (Formerly New Hope Lake, N.C.) (SAW) 6-10, 6-15, 6-20 Bachelor Island, Wash. (NPP) 37-50, 37-54 Back Creek, Md. (NAB) 4-34 Bad River, Bank Protection, Fort Pierre, S. Dak. (MRO) 21-20 Bagaduce River, Maine (NED) 1-20, 1-30, 1-36, 1-37, 1-44 Bailey, R.D., Lake, W. Va. (ORB) 25-9, 25-14, 25-18 Bainbridge, N.Y. (NAB) 4-36, 4-39 Baker Brook, Mass. (NED) 1-44 Bakers Haulover Inlet, Fla. (SAJ) 9-3, 9-26, 9-33, 9-46 Ball Mountain Lake, Vt. (NED) 1-12, 1-27, 1-47 Baltimore Harbor, Md. Collection and Removal of Drift (NAB) 4-4, 4-22, 4-28 Baltimore Harbor, Md. Prevention of Obstruction and Injurious Deposits (NAB) 4-8, 4-23, 4-30 Baltimore Harbor and Channels, Md. and Va. (NAB) 4-3, 4-22, 4-27 Baltimore Harbor and Channels (Norfolk District) (NAO) 5-2, 5-13, 5-17 Bandon Small Boat Basin, Oreg. (NPP) 37-2, 37-27, 37-35 Bank Revetments and Dikes (MR+T) 42-30, 42-32, 42-34 Bank Stabilization & Channel Rectification, Ark. (SWL) 18-2, 18-10, 18-20 Bank Stabilization and Channel Rectification, Arkansas River, Ark. and Okla. (SWT) 19-16 Banner Special Drainage and Levee Districts (NCR) 28-14, 28-16 Banning Levee-San Gorgonio River, Calif. (SPL) 33-31 Bar Harbor, Maine (NED) 1-37 Bar Point Harbor, Alaska (NPA) 40-12 Barataria Bay Waterway, La. (LMN) 11-20 Barbers Point Harbor, Hawaii (POD) 36-1, 36-6, 36-8 Barbourville, Ky. (ORN) 23-13, 23-19 Barcelona Harbor, N.Y. (NCB) 32-2, 32-17 Bardvell Lake, Tex. (SWF) 16-3, 16-14, 16-18 Barkley Dam and Lake Barkley, Ky. and Tenn. (ORN) 23-14 Barnard, Kans. (MRK) 20-19 Barnegat Inlet, N.J. (NAP) 3-2, 3-15, 3-18 Barnegat Light, N.J. (NAP) 3-23 Barnett Creek, Ky. (ORL) 24-24 Barre Falls Dam, Mass. (NED) 1-12, 1-27, 1-47 Barren River Lake, Ky. (ORL) 24-5, 24-14, 24-27 Bartley, Nebr. (MRK) 20-19, 20-21 Bass Harbor, Maine (NED) 1-37 Bass Harbor Bar, Maine (NED) 1-37 Bassett Creek, Minn. (NCS) 27-3, 27-19 Bastrop Bayou, Tex. (SWG) 15-26 Batavia and Vicinity, N.Y. (NCB) 32-37 Bath, N.Y. (NAB) 4-36, 4-39 Baton Rouge Harbor, La. (LMN) 11-20 Baton Rouge Harbor (Devil's Swamp), La. (MR+T) 42-5, 42-29, 42-50 Battle Creek, Bank Protection, Battle Creek, Nebr. (MRO) 21-20 Baudette Harbor, Minn. (NCS) 27-23 Bay City Harbor, Wis. (NCD) 29-7 Bay Ridge and Red Hook Channels, N.Y. (NAN) 2-2, 2-19, 2-23, 2-29 Bay River, N.C. (SAW) 6-25 Bayard, W. Va. (NAB) 4-36, 4-39 Bayfield Harbor, Wis. (NCE) 31-76, 31-77 Bayou Bartholomew and Tributaries, Ark. and La. (LMK) 12-5, 12-14, 12-17, 12-21, 12-22 Bayou Bodcau and Tributaries, Ark. and La. (LMK) 12-6, 12-14, 12-17, 12-23 Bayou Bodcau, Red Chute, and Loggy Bayou, La. (LMN) (LMK) 11-22, 12-24, 12-25 Bayou Bodcau Reservoir, La. (LMK) 12-6, 12-14, 12-17, 12-22, 12-24 Bayou Bonfouca, La. (LMN) 11-20 Bayou Choupique, La. (LMN) 11-22 Bayou Cocodrie and Tributaries, La. (MR+T) 42-6, 42-14, 42-28, 42-54, 42-58 Bayou Coden, Ala. (SAM) 10-3, 10-26, 10-32 I-4 INDEX Bayou Dorcheat, Loggy Bayou and Lake Bisteneau, La. (LMN) 11-20 Bayou Dupre, La. (LMN) 11-20 Bayou Galere, Hiss. (SAM) 10-43 Bayou Grosse Tete, La. (LMN) 11-20 Bayou La Batre, Ala. (SAM) 10-4, 10-26, 10-32, 10-45 Bayou La Loutre, St. Halo, and Yscolskey, La. (LHN) 11-20 Bayou Lacombe, La. (LMN) 11-20 Bayou Lafourche and Lafourche-Jump Waterway, La. (LMN) 11-20 Bayou Meto, Ark. (MR+T) 42-52 Bayou Nicholas, Coushatta, La. (LMN) (LMK) 11-22, 12-23 Bayou Pierre, La. (LHN) (LMK) 11-22, 12-7, 12-14, 12-17, 12-23, 12-24, 12-25 Bayou Plaquemine Brule, La. (LMN) 11-20 Bayou Queue de Tortue, La. (LMN) 11-20 Bayou Rapides, La. (LMN) 11-22 Bayou Segnette Waterway, La. (LMN) 11-20 Bayou Teche, La. (LMN) 11-20 Bayou Teche and Vermilion River, La. (LMN) 11-20 Bayou Terrebonne, La. (LMN) 11-20 Bayou Vermilion, La. (LMN) 11-20 Bayous D'Arbonne and Corney, La. (LMK) 12-21 Bayous Des Glaise Diversion Channel, La. (MR+T) 42-50 Bayous Rapides, Boeuf, and Cocodrie (MR+T) 42-50 Bayport, Fla. (SAJ) 9-47 Bayport Harbor, Mich. (NCE) 31-76, 31-77 Baytown, Tex. (SWG) 15-26 Beals, Maine (NED) 1-22 Beals Harbor, Maine (NED) 1-37 Bear Creek, Mont. (NPS) 38-25 Bear Creek, Oreg. (NPP) 37-48, 37-50 Bear Creek Dam (City of Hannibal, Mo.) (NCR) 28-14 Bear Creek, Kendrick, Idaho (NPW) 39-16, 39-19 Bear Creek Lake, Colo. (HRO) 21-2, 21-10, 21-13 Bear Creek Reservoir, Hannibal, Mo. (NCR) 28-16 Bear River, Calif. (SPK) 35-29 Beards Brook Reservoir, N.H. (NED) 1-44 Beatrice, Nebr. (MKR) 20-20 Beaufort Harbor, N.C. (SAW) 6-4, 6-18, 6-23 Beaver and Mahoning Rivers, Pa. and Ohio (ORP) 26-21 Beaver Bay, Minn. (NCE) 31-77 Beaver Brook, Keene, N.H. (NED) 1-12, 1-27, 1-35 Beaver Brook Lake, N.H. (NED) 1-44 Beaver Creek, Montezuma, Ga. (SAM) 10-43 Beaver Creek near Tillamook, Oreg. (NPP) 37-48 Beaver Drainage District, Oreg. (NPP) 37-54 Beaver Lake, Ark. (SWL) 18-7, 18-11, 18-23 Bedford, Iowa (HRK) 20-19 Beech Fork Lake, W. Va. (ORH) 25-2, 25-12, 25-16 Belfast Harbor, Maine (NED) 1-37 Belhaven Harbor, N.C. (SAW) 6-25 Bell Foley Lake, White River Basin, Ark. (SWL) 18-16, 18-23 Bellaire, Ohio (ORP) 26-23 Bellamy River, N.H. (NED) 1-37 Belle Fourche, S. Dak. (HRO) 21-16, 21-20 Belle River Harbor, Mich. (NCE) 31-76, 31-77 Belleville Locks and Dam, Ohio (ORD) 22-3, 22-8 Bellevue, Ky. (ORL) 24-22, 24-25 Bellingham Harbor, Wash. (NPS) 38-2, 38-13, 38-18, 38-30 Bellingham Harbor, Wash. (I and J Street Waterway) (NPS) 38-24 Bellingham, Squalicum Small Boat Harbor, Wash. (NPS) 38-24 Belpre, Ohio (ORB) 25-21 Belton Lake, Tex. (SWF) 16-3, 16-14, 16-18 Belton Lake Modification, Tex. (SWF) 16-12 Beltzville Lake, Pa. (NAP) 3-10, 3-16 Benbrook Lake, Tex. (SWF) 16-3, 16-14, 16-18 Bennett-McDonald-Smithland D.D., Little Sioux River, Iowa (MRO) 21-21 Bennington, Vt. (NAN) 2-32 Bennington Reservoir, N.H. (NED) 1-44 Benwood, W. Va. (ORP) 26-22, 26-26 Berkeley Harbor, Calif. (SPN) 34-7 Berkeley Marina, Calif. (SPN) 34-7 Berlin Lake, Ohio (ORP) 26-5, 26-13, 26-18 Berwick Bay Bridge Alteration (LMN) 11-20 Bethel Bank Stabilization, Alaska (NPA) 40-6 Bethel Small Boat Harbor, Alaska (NPA) 40-1, 40-8, 40-10 Bethlehem, Pa. (NAP) 3-23 Bettendorf, Iowa (NCR) 28-4, 28-8, 28-12 Betterton Harbor, Md. (NAB) 4-34 Beverly Harbor, Mass. (NED) 1-37 Big Bay Harbor, Mich. (NCE) 31-76, 31-77 Big Bend, W. Va. (ORH) 25-21 Big Bend Dam-Lake Sharpe, S. Dak. (MRO) 21-7, 21-12, 21-15 Big Black River, Miss. (LMK) 12-21, 12-25 Big Blue Lake, Ind. (ORL) 24-22, 24-28 Big Blue River, Nebr. (MRK) 20-19 Big Canyon Creek, Peck, Idaho (NPW) 39-19 I-5 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Big Choctaw Bayou, La. (LMK) 12-25 Big Creek and L'Anguille River, Ark. (LMM) 13-7 Big Creek Canal, Millington, Tenn. (LMM) 13-7 Big (Cunningham) Creek, Ohio (NCB) 32-35 Big Darby, Ohio (ORB) 25-21 Big Dry Creek Dam and Diversion, Calif. (SPK) 35-29 Big Fossil Creek, Tex. (SWF) 16-21 Big Fossil Creek Floodvay, Tex. (SWF) 16-21 Big Bole River, Pennington Bridge, near Twin Bridges, Mont. (MRO) 21-19 Big Born River, Two Leggin Bridge, near Hardin, Mont. (MRO) 21-19 Big Lake Drainage and Levee District, Ill. (NCR) 28-14, 28-16 Big Pigeon and Little Pigeon Bayous, La. (LMN) 11-20 Big Pine Lake, Ind. (ORL) 24-21 Big Pine Lake, Tex. (SWT) 19-15 Big Run, Pa. (ORP) 26-22, 26-28 Big Sandy Lake, Tex. (SWF) 16-3, 16-14, 16-18 Big Sandy River, W. Va. and Ky., including Levisa and Tug Forks (ORB) 25-19 Big Sioux River at Sioux City, Iowa and S. Dak. (MRO) 21-16 Big Sioux River, Fink Bridge, near Flandreau, S. Dak. (MRO) 21-19 Big Sioux River, Schofield Bridge, near Flandreau, S. Dak. (MRO) 21-19 Big Slough & Mayo Ditch, Ark. (MR+T) 42-57 Big South Fork National River and Recreation Area, Ky. and Tenn. (ORN) 23-4, 23-9 Big Spring, Tex. (SWF) 16-21 Big Stone Lake and Whetstone River, Minn. and S. Dak. (NCS) 27-4, 27-19 Big Stranger Creek, Kans. (MRK) 20-19 Big Suamico River, Wis. (NCE) 31-76, 31-77 Big Sunflower River, Miss. (LMK) (MR&T) 12-21, 42-51 Big Swan Drainage and Levee District, Ill. (LMS) 14-14 Big Timber Creek, N.J. (NAP) 3-21 Big Walnut Lake, Ind. (ORL) 24-21, 24-28 Big Wash, Milford, Utah (SPK) 35-29 Big Wood River, Idaho (NPW) 39-2, 39-10, 39-13, 39-19 Billings, Montana (MRO) 21-18 Biloxi Barbor, Miss. (SAM) 10-4, 10-5, 10-26, 10-33, 10-45 Biloxi River at Lorraine Road, Harrison County, Miss. (SAM) 10-13, 10-28, 10-39 Binghamton, N.Y. (NAB) 4-14, 4-25 Birch, W. Va. (ORB) 25-20 Birch Bill Dam, Mass. (NED) 1-12, 1-27, 1-47 Birch Lake, Okla. (SWT) 19-3, 19-9, 19-13 Bird Rock Area, La Jolla, Calif. (SPL) 33-24 Birds Point-New Madrid Floodway, Mo. (MR+T) 42-53 Biscayne Bay, Fla., Burricane Protection (SAJ) 9-54 Black Bayou-Pine Island Area, La. (LMN) 11-22 Black Bayou Reservoir, La. (LMN) (LMK) 11-22, 12-24, 12-25 Black Bear and Miller Lakes, Minn. (NCS) 27-4, 27-19 Black Creek, Gadsden, Ala. (SAM) 10-43 Black Fork at Bendricks, W. Va. (ORP) 26-22 Black River, Ark. & Mo. (SWL) 18-15 Black River, Mich. (NCE) 31-77 Black River, N.C. (SAW) 6-25, 6-27 Black River, Wis. (NCS) 27-23, 27-25, 27-28 Black River Barbor, Mich. (NCE) 31-4, 31-39, 31-55, 31-56, 31-77, 31-79 Black River Harbor, N.Y. (NCB) 32-35 Black River Lake, Wis. (NCS) 27-25 Black River, Poplar Bluff, Mo., to Knobel, Ark. (SWL) 18-16 Black River (Port Buron), Mich. (NCE) 31-4, 31-39 Black Rock Channel and Tonawanda Harbor, N.Y. (NCB) 32-2, 32-17, 32-23, 32-39 Black Rock Barbor, Conn. (NED) 1-3, 1-25, 1-32 Black Rock Lake, Conn. (NED) 1-48 Black Walnut Point, Md. (NAB) 4-12, 4-24, 4-32, 4-34 Black Warrior and Tombigbee Rivers, Ala. (SAM) 10-5, 10-26, 10-33, 10-47 Blackbird Creek near Macy, Nebr. (MRO) 21-16, 21-20 Blackfoot Area, Snake River, Idaho (NPW) 39-16, 39-18 Blackfoot Reservoir, Idaho (NPW) 39-16 Blackfoot River, Idaho (NPW) 39-16, 39-18 Blackfoot River, Mont. (NPS) 38-25 Blackstone, Mass. (NED) 1-22 Blackstone River Basin, Mass. and R.I. (NED) 1-10, 1-23, 1-27, 1-35, 1-46 Blackwater Dam, N.B. (NED) 1-18, 1-30, 1-50 Blackwater River, Fla. (SAM) 10-42, 10-45 Blackwater River, Va. (NAO) 5-22 Blaine, Maine (NED) 1-22 Blaine Barbor, Wash. (NPS) 38-24, 38-30 Blair and Sitcom Waterways, Tacoma Harbor, Wash. (NPS) 38-11 I-6 INDEX Blakely Mountain Dam-Lake Quachita, Ark. (LMK) 12-7, 12-14, 12-17, 12-22 Blind Slough Diking District, Oreg. (NPP) 37-46 Bloomington Lake, Md. and V. Va. (NAB) 4-12, 4-24, 4-32 Blue Marsh Lake, Pa. (NAP) 3-11, 3-17 Blue Mountain Lake, Ark. (SWL) 18-5, 18-11, 18-21 Blue River Basin (Kansas City District) (MRK) 20-19 Blue River Channel, Kansas City, Mo. (MRK) 20-2, 20-11, 20-15 Blue River Lake, Oreg. (NPP) 37-13, 37-30, 37-41, 37-53, 37-55 Bluestone Lake, V. Va. (ORH) 25-3, 25-12, 25-16 Bluff Creek, Miss. (SAM) 10-42 Board of Engineers for Rivers and Harbors (BERH) 41-1 Bodega Bay, Calif. (SPN) 34-2, 34-4 Bodie Island, N.C. (SAW) 6-28 Boeuf and Tensas Rivers and Bayou Macon, Ark. and La. (MR+T) 42-51 Boeuf River, La. (LMN) 12-21 Bogachiel River, Wash. (NPS) 38-25 Boggy Creek, Tex. (SWF) 16-4, 16-14, 16-18 Boise River, Idaho (NPW) 39-2, 39-10, 39-13 Boise Valley, Idaho (NPW) 39-16, 39-18 Bolles Harbor, Mich. (NCE) 31-4, 31-39, 31-56 Bon Secour River, Ala. (SAM) 10-6, 10-26, 10-34, 10-42 Bonnes Coulee, Velva, N.D. (NCS) 27-5, 27-19, 27-27 Bonnet Carre Spillway, La. (MR+T) 42-6, 42-54, 42-56 Bonneville Lock and Dam-Lake Bonneville, Oreg. and Wash. (NPP) 37-20, 37-26, 37-32, 37-42, 37-57 Bonpas Creek, Ill. (ORL) 24-22, 24-26 Bonum Creek, Va. (NAB) 4-34 Boone County, Ky. (ORL) 24-20 Booneville Lake, Ky. (ORL) 24-21, 24-27 Boothbay Harbor, Maine (NED) 1-37 Boston Harbor, Mass. (NED) 1-37, 1-51 Bosvell Lake, Okla. (SWT) 19-15 Boulder Creek, Boulder, Colo. (MRO) 21-16 Bound Brook, Scituate, Mass. (NED) 1-42 Bouquet River, Elizabethtown, N.Y. (NAN) 2-36 Bowman, Leland, Lock, La. (formerly Vermilion Lock) (LMN) 11-4, 11-13, 11-15 Bowman-Haley Lake, N. Dak. (MRO) 21-2, 21-10, 21-13 Brackenridge, Tarentum and Natrona, Pa. (ORP) 26-22, 26-26 Bradford, Pa. (ORP) 26-22, 26-28 Bradford, Tenn. (LMM) 13-7 Bradley Lake, Alaska (NPA) 40-13 Bramwell, W. Va. (ORB) 25-22 Brandon Road Lock and Dam, Ill. (NCC) 28-20, 28-21 Branford Harbor, Conn. (NED) 1-37 Branson Cove, Va. (NAB) 4-34 Brant Rock Beach, Marshfield, Mass. (NED) 1-44 Braymer Lake, Mo. (MRK) 20-19 Brays Bayou, Tex. (SWG) 15-10 Brazos Island Harbor, Tex. (SWG) 15-2, 15-12, 15-15, 15-27, 15-28, 15-35 Brazos River, Tex., Velasco to Old Washington (SWG) 15-26 Brea Dam, Calif. (SPL) 33-30 Breckenridge, Minn. (NCS) 27-28 Breton Bay, Md. (NAB) 4-34 Brevard County, Fla. (SAJ) 9-17, 9-29, 9-41 Brevoort Levee, Ill. (ORL) 24-20, 24-29 Bridge Alterations Authorized Chicago, Ill., District (NCC) 30-14 Nashville, Tenn., District (ORN) 23-4 New England Division (NED) 1-9 Bridgeport Harbor, Conn. (NED) 1-37, 1-44 Bridges, Columbia River, Oreg. (NPP) 37-45 Bridgevater, Va. (NAB) 4-36, 4-39 Brilliant, Ohio (ORP) 26-23 Bristol Harbor, R.I. (NED) 1-37 Broad Creek, Md. (NAB) 4-34 Broad Creek, N.C. (SAW) 6-27 Broad Creek, Va. (NAO) 5-3, 5-13, 5-17 Broad Creek River, Del. (NAB) 4-34 Broadkill River, Del. (NAP) 3-21 Broadvater Creek, Md. (NAB) 4-37 Broadway Lake, S.C. (SAS) 8-7, 8-11, 8-15 Brockway, Pa. (ORP) 26-23 Brockway Lake, Vt. (NED) 1-44 Broken Bow, Nebr. (MRO) 21-20 Broken Bow Lake, Okla. (SWT) 19-7, 19-12, 19-14 Bromley, Ky. (ORL) 24-22, 24-25 Bronx River, N.Y. (NAN) 2-2, 2-19, 2-23, 2-34 Brookfield Lake, Mo. (MRK) 20-19 Brooklyn, W. Va. (ORH) 25-21 Brookport, Ill. (ORL) 24-20, 24-24, 24-29 Brookville, Pa. (ORP) 26-22, 26-28 Brookville Lake, Ind. (ORL) 24-5, 24-14, 24-27 I-7 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Broward County, Fla., Beach Erosion Control and Hillsboro Inlet, Fla., Navigation Project (SAJ) 9-18, 9-30, 9-41 Brown, Clarence J., Dam and Reservoir, Ohio (ORL) 24-8, 24-15 Browns Creek, N.Y. (NAN) 2-34 Brownwood Channel Improvement, Tex. (SWF) 16-21 Brunswick County Beaches, N.C. (Cape Fear to North Carolina-South Carolina State Line) (SAW) 6-27 Brunswick Harbor, Ga. (SAS) 8-3, 8-11, 8-13 Buchanan Dam-H. V. Eastman Lake, Calif. (SPK) 35-4, 35-21 Buck Creek, N.C. and S.C. (SAN) 7-8, 7-16 Buckhannon, W. Va. (ORP) 26-22, 26-23, 26-28 Buckhannon River, W. Va. (ORP) 26-21 Buckhorn Lake, Ky. (ORL) 24-6, 24-14, 24-27 Bucks Harbor, Machiasport, Maine (NED) 1-37 Bucksport Harbor, Maine (NED) 1-37 Buena Vista, Ohio (ORB) 25-21 Buena Vista, Va. (NAO) 5-23 Buffalo, Wyo. (MRO) 21-16 Buffalo Bayou and Tributaries, Tex. (SWG) 15-9, 15-13, 15-24 Buffalo Creek, Meadow Grove, Nebr. (MRO) 21-16, 21-20 Buffalo Creek, Scranton, N. Dak. (MRO) 21-16, 21-20 Buffalo Harbor, N.Y. (NCB) 32-3, 32-17, 32-24 Buffalo River, Miss. (LMK) 12-25 Buffumville Lake, Mass. (NED) 1-21, 1-31, 1-51 Buford Dam, Ga. (SAM) 10-22 Bull Run, Pa. (NAB) 4-36 Bull Shoals Lake, Ark. (SWL) 18-7, 18-11, 18-23 Bullocks Point Cove, R.I. (NED) 1-37 Bunker Harbor, Maine (NED) 1-37 Burbank-Eastern System, Calif. (SPL) 33-28 Burbank-Western System (Lower) Calif. (SPL) 33-28 Burbank-Western System (Upper) Calif. (SPL) 33-28 Burch Creek, Weber County, Utah (SPK) 35-29 Burgettstown, Pa. (ORP) 26-22 Burgettstown-Slovan, Pa. (ORP) 26-28 Burial Hill Beach, Westport, Conn. (NED) 1-41 Burketts Creek, Amory, Miss. (SAM) 10-43 Burlington, Ohio (ORH) 25-20 Burlington Dam, N. Dak. (NCS) 27-24 Burlington Harbor, Vt. (NAN) 2-30 Burns Waterway Harbor, Ind. (NCD) 30-2, 30-6,30-8, 30-10, 30-13, 30-14 Burnsville Lake, V. Va. (ORB) 25-3, 25-12, 25-16 Bush, Alvin R., Dam, Pa. (NAB) 4-19, 4-26 Butler, Pa. (ORP) 26-22, 26-28 Buttermilk Bay Channel, Mass. (NED) 1-3, 1-25, 1-32 Buttermilk Channel, N.Y. (NAN) 2-3, 2-19, 2-23 Byram River at Pemberwick, Conn. (NAN) 2-32 C Cache Basin, Ark. (MR+T) 42-9, 42-18, 42-28, 42-53 Cache Creek Basin, Calif. (SPK) 35-18 Cache La Poudre River, Ft. Collins, Colo. (MRO) 21-16, 21-20 Cache River Diversion, Ill. (LMS) 14-14 Caddo Lake, La. (LMK) 12-7, 12-14, 12-17, 12-23 Cadet Bayou, Miss. (SAM) 10-42 Cadle Creek, Md. (NAB) 4-37 Caesar Creek Lake, Ohio (ORL) 24-6, 24-15, 24-27 Cagles Mill Lake, Ind. (ORL) 24-6, 24-15, 24-27 Cahaba River, Ala. (SAM) 10-42 Cairo, V. Va. (ORB) 25-22 Calabash Creek, N.C. (SAN) 7-15 Calapooya River, Oreg. (NPP) 37-50 Calaveras River and Little John Creek and Tributaries, including New Hogan Lake and Farmington Dam, Calif. (SPK) 35-4, 35-21 Calcasieu River at Coon Island, La. (LMN) 11-20 Calcasieu River at Devil's Elbow, La. (LMN) 11-20 Calcasieu River Salt Water Barrier, La. (LMN) 11-20 Caledonia, N.Y. (NCB) 32-37 Calf Pasture Beach Park, Conn. (NED) 1-41 California (Cincinnati) Ohio (0RL) 24-22, 24-26 California Debris Commission (CDC) 44-1 Calion, Ark. (LMK) 12-22 Calumet Harbor and River, Ill. and Indiana (NCC) 30-2, 30-8, 30-10, 30-13, 30-14 Calumet River Bridges, Ill. (NCC) 30-14 Camas Creek, Idaho (NPW) 39-18 Cambridge Harbor, Md. (NAB) 4-34 Cambridgeport Lake, Vt. (NED) 1-44 I-8 INDEX Camden Harbor, Maine (NED) 1-37 Camelsback Dam, Ariz. (SPL) 33-25 Camp Ground Lake, Ky. (ORL) 24-21 Camp Perry, Ohio (NCB) 32-37 Camp Wooten, Wash. (NPW) 39-19 Campbells Island, Ill. (NCR) 28-16 Campti-Clarence Area in Natchitoches Parish, La. (LMN) (LMK) 11-22, 12-23, 12-25 Canapitsit Channel, Mass. (NED) 1-37 Canaveral Harbor, Fla. (SAJ) 9-3, 9-26, 9-33, 9-43 Candy Lake, Okla. (SWT) 19-3, 19-9, 19-13 Cane River, La. (LMN) 11-20 Caney Fork River, Tenn. (ORN) 23-13 Canisteo, N.Y. (NAB) 4-15, 4-25 Cannelton, Ind. (ORL) 24-20, 24-24, 24-29 Cannelton Locks and Dam, Ind. (ORD) 22-3, 22-9 Cannon, Clarence, Dam and Reservoir, Mo. (LMS) 14-8, 14-10, 14-12 Canoe Creek, Henderson, Ky. (ORL) 24-20 Canton, Mass. (NED) 1-22, 1-42 Canton, Mo. (NCR) 28-14, 28-16 Canton Lake, Okla. (SWL) (SWT) 18-21, 19-3, 19-9, 19-13, 19-16 Canton (Nimishillen), Ohio (ORB) 25-22 Canyon Lake, Tex. (SWF) 16-4, 16-14, 16-18 Cape Charles City Harbor, Va. (NAO) 5-22 Cape Cod Canal, Mass. (NED) 1-3, 1-25, 1-32 Cape Fear River, N.C., above Wilmington (SAW) 6-4, 6-18 Cape Fear River Basin, N.C. (SAW) 6-10, 6-30 Cape Florida State Park, Fla. (SAJ) 9-48 Cape Girardeau, Mo., No. 2 (LMS) 14-14 Cape Girardeau, Mo., Reaches Nos. 1, 3 and 4 (LMS) 14-14 Cape Henry Channel, Va. (NAO) 5-2, 5-13, 5-17 Cape Lookout, N.C. (SAW) 6-28 Cape May City, N.J. (NAP) 3-23 Cape May Inlet to Lower Township, N.J. (NAP) 3-21 Cape Porpoise Harbor, Maine (NED) 1-37 Cape Vincent Harbor, N.Y. (NCB) 32-12, 32-35 Captain Anthony Meldahl Locks and Dam, Ky. (ORD) 22-3, 22-8 Carden's Bottom Drainage District No. 2, Arkansas River, Ark. (SWL) 18-16 Carl L. Estes Dam and Lake, Tex. (SWF) 16-21 Carlyle Lake, Ill. (LMS) 14-14 Carolina Beach and Vicinity, N.C. (SAW) 6-11, 6-20 Carr Fork Lake, Ky. (ORL) 24-7, 24-15, 24-27 Carrabelle Bar and Harbor, Fla. (SAM) 10-42 Carrabelle, Fla. (SAM) 10-43 Carroll County Levee and Drainage District, Ill. (NCR) 28-16 Carrollton, Ky. (ORL) 24-22, 24-25 Carters Creek, Va. (NAO) 5-22 Carters Lake, Ga. (SAM) 10-19, 10-29 Caruthersville Harbor, Mo. (LMM) 13-6 Carvers Harbor, Vinalhaven, Maine (NED) 1-37 Cascadia Lake, Oreg. (NPP) 37-48, 37-55 Caseville Harbor, Mich. (NCE) 31-76, 31-77 Caseyville, Ky. (ORL) 24-21, 24-24 Cashie River, N.C. (SAW) 6-25 Cassville Harbor, Wis. (NCD) 29-7 Castle Rock, Wash. (NPP) 37-48 Castlewood Lake, Colo. (MRO) 21-16 Catching Inlet Drainage District, Oreg. (NPP) 37-48 Cathance River, Maine (NED) 1-37 Catherine Creek, Oreg. (NPW) 39-2, 39-10, 39-13 Catherine Creek Lake, Oreg. (NPW) 39-16 Cathlamet, Wash. (NPP) 37-45 Catlettsburg, Ky. (ORH) 25-20, 25-22 Cattaraugus Creek, N.Y. (NCB) 32-35 Cattaraugus Harbor, N.Y. (NCB) 32-3, 32-17 Cave Run Lake, Ky. (ORL) 24-7, 24-15, 24-27 Cave-In-Rock, Ill. (ORL) 24-22, 24-25 Cayuga Creek, Cheektowaga, N.Y. (NCB) 32-37 Cecil M. Harden Lake, Ind. (ORL) 24-7, 24-15, 24-27 Cedar Cedar Cedar Cedar Cedar Bayou, Tex. (SWG) 15-26 Canyon Dam, S.Dak. (MRO) 21-16, Creek, Del. (NAP) 3-21 Keys Harbor, Fla. (SAJ) 9-47 Point, Ga. (SAS) 8-16 21-20 Cedar Point Lake, Kans. (SWT) 19-15 Cedar River, Wash. (NPS) 38-25 Cedar River Harbor, Mich. (NCE) 31-77 Cedars Lock and Dam, Wis. (NCE) 31-75 Celina Dam, Ky. (ORN) 23-14 Center Hill Lake, Ohio River Basin, Tenn. (ORN) 23-6, 23-9, 23-18 Central and Southern Florida (SAJ) 9-22, 9-31, 9-41, 9-48, 9-49, 9-50, 9-51, 9-52 Central City Lake, Iowa (NCR) 28-16 Ceredo-Kenova, W. Va. (ORB) 25-20, 25-22 Chambersburg, Ohio (ORB) 25-21 Channel between North and South Hero Island, Lake Champlain, Vt. (NAN) 2-30 Channel Clearing and Snagging on Willamette River and Major Tributaries, (NPP) 37-55 Channel Connecting Plain Dealing Creek and Oak Creek, Md. (NAB) 4-37 Channel Connecting Thoroughfare Bay with Cedar Bay, N.C. (SAW) 6-25 I-9 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Channel Connecting York River, Va. with Back Creek to Slaights Wharf (NAO) 5-22 Channel from Back Sound to Lookout Bight, N.C. (SAW) 6-5, 6-18 Channel from Naples to Big Marco Pass, Fla. (SAJ) 9-4, 9-26, 9-33, 9-46 Channel from Pamlico Sound to Rodanthe, N.C. (SAW) 6-25 Channel from Phoebus, Va. to Deep Water in Hampton Roads (NA0) 5-22 Channel Improvements for Flood Control and Major Drainage on 16 Streams Tributary to Willamette River (NPP) 37-55 Channel Islands Harbor, Calif. (SPL) 33-2, 33-13, 33-18 Channel to Liberty, Tex. (SWG) 15-7 Channel to Newport News, Va. (NAO) 5-3, 5-13, 5-17 Channel to Port Bolivar, Tex. (SWG) 15-26 Chaplin River, Perryville, Ky. (ORL) 24-20 Chappaqua, N.Y. (NAN) 2-36 Charenton Drainage and Navigation Canal (MR+T) 42-50 Chariton River, Mo. (1944 Act) (MRK) 20-19 Chariton-Little Chariton Basin, Mo. (1965 Act) (MRK) 20-19 Charles River (Natural Valley Storage Areas), Mass. (NED) 1-11, 1-27, 1-35 Charles River Dam, Mass. (NED) 1-22, 1-42 Charleston Channel, Oreg. (NPP) 37-2, 37-27, 37-35 Charleston Harbor, S.C. (SAN) 7-2, 7-9, 7-11, 7-15 Charlestown, N.H. (NED) 1-22, 1-42, 1-48 Charlevoix Harbor, Mich. (NCE) 31-5, 31-40, 31-56 Charlotte Harbor, Fla. (SAJ) 9-4, 9-26, 9-33 Chartiers Creek, Pa. (ORP) 26-3, 26-13, 26-28 Chaska, Minn. (NCS) 27-5, 27-19 Chatfield Lake, Colo. (MRO) 21-2, 21-10, 21-13 Chatham (Stage) Harbor, Mass. (NED) 1-37 Chattanooga, Tenn. and Rossville, Ga. (ORN) 23-13 Chattooga Dams and Lakes, Ga. and S.C. (SAS) 8-17 Cheat River, W. Va. (ORP) 26-21 Cheatham Lock and Dam, Tenn. (ORN) 23-14 Cheboygan Harbor, Mich. (NCE) 31-5, 31-40, 31-56 Cheesequake Creek, N.J. (NAN) 2-34 Chefuncte River and Bogue Falia, La. (LMN) 11-20 Chehalis River, Wash. (NPS) 38-11, 38-25 Chelsea Street Highway Bridge, Mass. (NED) 1-9 Chena River Lakes, Alaska (NPA) 40-5, 40-9, 40-11 Cheney Reservoir, Kans. (SVT) 19-18 Cherry and Red Fork Creeks Channel Improvement, Okla. (SWT) 19-15, 19-16 Cherry Creek Lake, Colo. (MRO) 21-3, 21-10, 21-13 Cherryfield, Maine (NED) 1-22, 1-42 Chesapeake, Ohio (ORB) 25-20 Cheseonessex Creek, Va. (NAO) 5-22 Cheshire, Ohio (ORB) 25-21 Chester, Calif. (SPK) 35-29 Chester River, Md. (NAB) 4-34 Chester River, Pa. (NAP) 3-21 Chester River at Chester, Pa. (NAP) 3-13 Chetco River, Oreg. (NPP) 37-2, 37-27, 37-35 Chevaucan River, Oreg. (NPP) 37-48 Chicago Harbor, Ill. (NCC) 30-3, 30-8, 30-10, 30-13, 30-14 Chicago River, Ill. (NCC) 30-3, 30-8, 30-10, 30-13 Chicago River, Ill. (North Branch) (NCC) 30-6, 30-9 Chichester Creek, Shandaken, N.Y. (NAN) 2-36 Chickamauga Lock and Dam, Tenn. (0RN) 23-17 Chicopee, Mass. (NED) 1-22, 1-42, 1-44, 1-48 Chicopee Falls, Mass. (NED) 1-42, 1-48 Chief Joseph Dam-Rufus Woods Lake, Wash. (NPS) 38-10, 38-16, 38-22 Chillicothe, Ohio (ORH) 25-3, 25-12, 25-16, 25-22 Chilo, Ohio (ORH) 25-21 Chincoteague Bay, Va. (NAO) 5-22 Chincoteague Harbor of Refuge, Va. (NAO) 5-3, 5-13, 5-17 Chincoteague Inlet, Va. (NAO) 5-4, 5-13, 5-18, 5-24 Chino Canyon Improvements, Palm Springs, Calif. (SPL) 33-31 Chippewa Harbor, Isle Royale, Mich. (NCE) 31-77 Chittenango Creek and Tributaries, N.Y. (NCB) 32-37 Choctaw Bayou and Tributaries, La. (LMN) 11-22 Choctawhatchee Bay to Pensacola Bay, Fla. (SAM) 10-35 Choctawhatchee Bay to Vest Bay, Fla. (SAM) 10-35 Choctawhatchee River, Fla. and Ala. (SAM) 10-42 Choptank River, Md. (NAB) 4-34 I-10 INDEX Chouteau Lock and Dam, Okla. (SWL) (SWT) 18-19, 19-16 Chouteau, Nameoki, and Venice Drainage and Levee District, Ill. (LMS) 14-14 Chowan River, N.C. (NAO) 5-22 Chovan River, N.C. (SAW) 6-25 Christiansted Harbor, V.I. (SAJ) 9-46, 9-47 Cibolo Creek, Tex. (SWA) 17-11 Cincinnati, Ohio (ORL) 24-20, 24-22, 24-24, 24-25, 24-29 Cincinnatus, N.Y. (NAB) 4-39 City Creek Levee, Calif. (SPL) 33-25, 33-31 City of Aurora, Colo. (MRO) 21-16 Clackamas River at Dixon Farm Location, Oreg. (NPP) 37-48 Claiborne County Port, Miss. (LMK) 12-2, 12-13, 12-16 Claiborne Harbor, Md. (NAB) 4-4, 4-22, 4-29 Claiborne Lock and Dam, Ala. (SAM) 10-19, 10-29 Clallam Bay, Wash. (NPS) 38-25 Clallam River, Wash. (NPS) 38-25 Clanton, Ala. (SAM) 10-43 Claremont Lake, N.H. (NED) 1-44 Clarence Cannon Dam and Reservoir, Mo. (LMS) 14-8, 14-10, 14-12 Clarence J. Brown Dam and Reservoir, Ohio (ORL) 24-8, 24-15 Clarendon to Laconia Circle, Ark. (LMM) 13-7 Clarington, Ohio (ORP) 26-23 Clark Fork River, Mont. (NPS) 38-25 Clark Point Beach, New Bedford, Mass. (NED) 1-41 Clarks Hill Lake, Ga. and S.C. (SAS) 8-8, 8-11, 8-15, 8-17 Clarkson, Nebr. (MRO) 21-16, 21-20 Clarksville, Ark. (SWL) 18-16 Clatskanie Drainage District 1, Oreg. (NPP) 37-50, 37-54 Clatskanie River, Oreg. (NPP) 37-45 Clatskanie River Area, Oreg. (NPP) 37-50, 37-54 Clatsop County Diking District 3, Oreg. (NPP) 37-50 Clatsop County Diking District 4, Oreg. (NPP) 37-50, 37-54 Clatsop County Diking District 6, Oreg. (NPP) 37-50, 37-54 Clatsop County Drainage District 1, Oreg. (NPP) 37-50, 37-54 Clear Creek, Tex. (SWG) 15-11 Clear Creek and Clear Lake, Tex. (SWG) 15-26 Clear Creek Drainage and Levee District, Ill. (LMS) 14-14 Clear River, R.I. (NED) 1-10, 1-27, 1-35 Clearwater Lake, Mo. (SWL) 18-5, 18-11, 18-23 Clearwater Pass, Fla. (SAJ) 9-47 Clearwater River, Minn. (NCS) 27-28 Clearwater River, Wash. (NPS) 38-26 Cleveland and Lakewood, Ohio (NCB) 32-36 Cleveland Harbor, Ohio (NCB) 32-4, 32-17, 32-25 Cleves, Ohio (ORL) 24-22, 24-25 Cliff Walk, Newport, R.I. (NED) 1-41 Clifton, W. Va. (0RH) 25-21 Clifty Creek Lake, Ind. (ORL) 24-22 Clinch River, Tenn., and Va. (ORN) 23-13 Clinton, Ind. (ORL) 24-22, 24-25 Clinton, Iowa (NCR) 28-14, 28-16 Clinton Harbor, Conn. (NED) 1-4, 1-25, 1-32 Clinton Harbor, Iowa (NCD) 29-7 Clinton Lake, Kans. (MRK) 20-2, 20-11, 20-15 Clinton River, Mich. (NCE) 31-6, 31-40, 31-56 Cloverport, Ky. (ORL) 24-21, 24-24, 24-30 Clyde, R.I. (NED) 1-44 Clyde Park, Mont. (MRO) 21-19 Coal Creek and Tributaries (Lake City), Tenn. (ORN) 23-13 Coal Creek Drainage and Levee District, Ill. (NCR) 28-14, 28-16 Coal Grove, Ohio (ORH) 25-20 Coal River, W. Va. (ORH) 25-20 Coan River, Va. (NAB) 4-37 Coast of California, Point Mugu to San Pedro Breakwater, Calif. (SPL) 33-24 Coastal Engineering Research Center (CERC) 45-1 Coasters Island Harbor, R.I. (NED) 1-37 Cobscook Bay, Maine (NED) 1-37 Cocheco River, N.H. (NED) 1-37, 1-42 Cochiti Lake, N. Mex. (SWA) 17-4, 17-9, 17-11 Cochrane, Wis. (NCS) 27-28 Cockrells Creek, Va. (NAO) 5-22 Coeur D'Alene, Idaho (NPS) 38-26 Cohansey River, N.J. (NAP) 3-2, 3-14, 3-15, 3-18 Cohasset Harbor, Mass. (NED) 1-37 Colchester, Conn. (NED) 1-22 Cold Regions Research Engineering Laboratory (CRREL) 52-1 Cold Spring Inlet, N.J. (NAP) 3-21 Colebrook River Lake, Conn. (NED) 1-13, 1-27, 1-47 Colfax, Wash. (NPW) 39-2, 39-10, 39-13, 39-19 Colfax, Grant Parish, La. (LMN) (LMK) 11-22, 12-24, 12-25 I-11 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Colliers, W. Va. (ORP) 26-28 Collinsville, Ala. (SAM) 10-43 Colonial Beach, Va. (NAB) 4-11, 4-24, 4-32 Colorado River, Matagorda, Tex. (SWG) 15-10, 15-26 Colorado Springs, Colo. (Templeton Gap Floodway) (SWA) 17-11 Columbia, La. (LMK) 12-22 Columbia and Lower Willamette Rivers below Vancouver, Wash., and Portland, Oreg. (NPP) 37-3, 37-27, 37-35, 37-51 Columbia Drainage and Levee District No. 3, Ill. (LMS) 14-14 Columbia Drainage District 1, Oreg. (NPP) 37-46, 37-54 Columbia River and Tributaries above Celilo Falls to Kennewick, Wash. (NPW) 39-16 Columbia River at Baker Bay, Wash. (NPP) 37-4, 37-27, 37-36 Columbia River at the Mouth, Oreg. and Wash. (NPP) 37-4, 37-27, 37-36 Columbia River Basin, Local Flood Protection Projects (NPW) 39-2, 39-13, 39-18 Columbia River Basin, Local Protection Projects, Idaho, Mont., and Wash. (NPS) 38-25, 38-29 Columbia River between Chinook, Wash., and Head of Sand Island (NPP) 37-4, 37-27, 37-36 Columbia River between Vancouver, Wash., and The Dalles, Oreg. (NPP) 37-5, 37-27, 37-36 Columbia River, Ilwaco, Wash. (NPP) 37-5, 37-27, 37-35 Columbia River Treaty Permanent Engineering Board 49-2 Columbia River, Wenatchee to Kettle Falls, Wash. (NPS) 38-24 Columbia Slough, Oreg. (NPP) 37-50 Columbus, Nebr. (MRO) 21-20 Columbus, Ohio (ORH) 25-21 Compo Beach, Westport, Conn. 1-41 Computer Sciences Laboratory 51-1 Conant Brook Dam, Mass. (NED) 1-13, 1-28, 1-47 Conchas Lake, N. Mex. (SWA) 17-2, 17-8 Concordia, Ky. (ORL) 24-21, 24-24 Conemaugh River Lake, Pa. (ORP) 26-6, 26-14, 26-18 Conetoe Creek, N.C. (SAW) 6-27 Coney Island Creek, N.Y. (NAN) 2-34 Coney Island Inlet, N.Y. (NAN) 2-30 Conklin-Kirkwood, N.Y. (NAB) 4-36, 4-39 Conneaut Harbor, Ohio (NCB) 32-4, 32-18, 32-26 Connecticut River (above Hartford), Conn, (NED) 1-37 Connecticut River Basin, Vt., N.H., Mass. and Conn. (NED) 1-11, 1-22, 1-47 Connecticut River below Hartford, Conn. (NED) 1-4, 1-25, 1-32, 1-44 Connecticut River, North Stratford, N.H. (NED) 1-42 Connecticut River, V. Stewartstown, N.H. (NED) 1-42 Connell, Wash. (NPW) 39-16 Conoho Creek, N.C. (SAW) 6 -28 Consolidated Diking and Improvement District 1, Cowlitz County, Wash. (NPP) 37-46 Construction Engineering Research Laboratory (CERL) 50-1 Construction of Locks and Dams, Ohio River (ORD) 22-1, 22-5, 22-6 Contentnea Creek, N.C. (SAW) 6-25, 6-27, 6-28 Conway County Drainage & Levee District No. 1, Arkansas River, Ark. (SVL) 18-16 Conway County Levee District No. 6, Arkansas River, Ark. (SWL) 18-16 Conway County Levee Districts Nos. 1, 2, & 8, Arkansas River, Ark. (SWL) 18-16 Cook Inlet Shoals, Alaska (NPA) 40-12 Cooper Lake and Channels, Tex. (LMN) 11-22 Cooper Lake and Channels, Tex. (SWF) 16-4, 16-14, 16-18 Cooper River, Charleston Harbor, S.C. (SAN) 7-3, 7-9, 7-12 Cooper River, N.J. (NAP) 3-21 Cooper River Seismic Modification, S.C. (SAN) 7-4, 7-9, 7-12 Coordinating Committee on Great Lakes Basic Hydraulic and Hydrologic Data Board 31-37, 49-2 Coos and Millicoma Rivers, Oreg. (NPP) 37-6, 37-28, 37-37 Coos Bay, Oreg. (NPP) 37-6, 37-27, 37-36 Coosa River Navigation, Ala. (SAM) 10-20, 10-30 Copan Lake, Okla. (SWT) 19-3, 19-9, 19-13 Copes Corner Lake, New York (NAB) 4-37 Coquille River, Oreg. (NPP) 37-7, 37-28, 37-37, 37-50 Coralville Lake, Iowa (NCR) 28-4, 28-8, 28-12 Coraopolis, Pa. (ORP) 26-23 Corbin, Ky. (ORN) 23-19 Corbin (Lynn Camp Creek), Ky. (ORN) 23-13 Cordell Hull Lock and Dam, Tenn. (ORN) 23-14 Cordova Harbor, Alaska (NPA) 40-12 I-12 INDEX Cordova Small Boat Harbor, Alaska (NPA) 40-2, 40-8, 40-10 Core Creek, N.C. (SAW) 6-27 Corea Harbor, Maine (NED) 1-37 Corning, N.Y. (NAB) 4-15, 4-25 Corning-Monkey Run, N.Y. (NAB) 4-39 Cornucopia Harbor, Wis. (NCE) 31-6, 31-40, 31-56 Corpus Christi, Tex., Channel to Navy Seaplane Base, Encinal Peninsula (SWG) 15-26 Corpus Christi Beach, Tex. (Restoration Project) (SWG) 15-8, 15-13, 15-24 Corpus Christi Ship Channel, Tex. (SWG) 15-2, 15-12, 15-15, 15-27, 15-28, 15-33 Corsica River, Md. (NAB) 4-34 Corson Inlet and Ludlam Beach, N.J. (NAP) 3-23 Corte Madera Creek, Calif. (SPK) (SPN) 34-5, 35-21, 35-26 Cortland, N.Y. (NAB) 4-36, 4-39 Cottage Grove Lake, Oreg. (NPP) 37-13, 37-30, 37-41, 37-53, 37-55 Cottonwood Creek, Calif. (SPK) 35-19, 35-25 Cottonwood Creek Community Church, Idaho (NPW) 39-16 Cottonwood Creek Dam, Boise, Idaho (NPW) 39-18 Cottonwood Slough Pumping Plant, Ill. (LMN) 13-7 Cotuit Harbor, Mass. (NED) 1-44 Cougar Lake, Oreg. (NPP) 37-21, 37-32, 37-43, 37-53, 37-55 Council Bluffs, Iowa (MRO) 21-16, 21-21 Council Grove Lake, Kans. (SWT) 19-3, 19-9, 19-13 Courtenay Channel, Fla. (SAJ) 9-47 Cove Island, Stamford, Conn. (NED) 1-41 Covington, Ky. (ORL) 24-20, 24-24, 24-29 Cow Castle Creek, S.C. (SAN) 7-7, 7-10, 7-14 Cow Creek Channel Improvement, Kans. (SVT) 19-15 Cowanesque Lake, Pa. (NAB) 4-18, 4-26 Cowlitz County Consolidated Diking Improvement District 1, Wash. (NPP) 37-46, 37-50, 37-54 Cowlitz County Diking Improvement Districts 2, 13, and 15, Wash. (NPP) 37-47, 37-54 Cowlitz County Drainage Improvement District 1, Wash. (NPP) 37-47 Cowlitz River, Wash. (NPP) 37-7, 37-26, 37-28, 37-38, 37-47 Cowlitz River at Randle, Wash. (NPP) 37-50 Covpens Swamp, S.C. (SAN) 7-8, 7-16 Coyote and Spencer Creeks, Oreg. (NPP) 37-50 Coyote Creek, Calif. (SPK) 35-29 Coyote Valley Dam (Lake Mendocino) and Channel Improvements, Calif. (SPK) 35-22, 35-32 Crabtree Swamp, S.C. (SAN) 7-8, 7-16 Craig Harbor, Alaska (NPA) 40-12 Cramerton, S. Fork, S.C. (SAN) 7-16 Crane Creek Drainage and Levee District (NCR) 28-14, 28-16 Crane Creek State Park, Ohio (NCB) 32-39 Cranes Creek, Va. (NAO) 5-4, 5-14, 5-18 Crawford County Levee District, Arkansas River, Ark. (SWL) 18-16 Creede, Willow Creek, Colo. (Floodway) (SWA) 17-11 Crescent City Harbor, Calif. (SPN) 34-4 Criehaven Harbor, Maine (NED) 1-37 Crisfield Harbor, Md. (NAB) 4-34 Crooked Creek Lake, Pa. (ORP) 26-6, 26-14, 26-18 Crooked Creek Lake & Levee, Ark. (SWL) 18-16 Cross Creek, Rossville, Kan. (MRK) 20-8 Cross-Florida Barge Canal (SAJ) 9-4, 9-26, 9-33, 9-43, 9-44 Cross Rip Shoals Nantucket Sound, Mass. (NED) 1-37 Crutcho Creek Channel Improvement, Okla. (SVT) 19-15 Crystal River, Fla. (SAJ) 9-46, 9-47 Cucamonga Creek, Calif. (SPL) 33-5, 33-14, 33-21 Cuckold Creek, Md. (NAB) 4-37 Cuivre River, Mo. (LMS) 14-13 Culdesac, Idaho 39-19 Cumberland, Ky. (ORN) 23-18 Cumberland, Md., and Ridgeley, W. Va. (NAB) 4-12, 4-24, 4-32, 4-39 Cumberland River, Tenn. and Ky. (ORN) 23-2, 23-9, 23-11, 23-15 Cummings Park, Stamford, Conn. (NED) 1-41 Cunninghill Cove, Md. (NAB) 4-37 Current River, Ark. & Mo. (SWL) 18-15 Curry Creek Dam and Lake, Ga. (SAS) 8-16 Curvensville Lake, Pa. (NAB) 4-19, 4-26 Cushman-Mapleton Channels Oreg. (NPP) 37-45 Cuttyhunk Harbor, Mass. (NED) 1-37 Cuyahoga River Basin, Ohio (NCB) 32-13, 32-21 Cypress Bayou and Waterway between Jefferson, Tex., and Shreveport, La. (LMN) (LHK) 11-20, 12-21 Cypress Creek, Ky. (ORL) 24-30 Cypress Creek, Md. (NAB) 4-34 1-13 REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1985 D Dade County, Fla. (SAJ) 9-18, 9-30, 9-41 Dade County, North of Haulover Beach, Fla. (SAJ) 9-19 Dale Hollow Lake, Ohio River Basin, Tenn. and Ky. (ORN) 23-7, 23-9, 23-18 Dallas Floodway, Tex. (SWF) 16-21 Dam "A" Lake, Tex. (SWF) 16-12, 16-18 Dam Neck Disposal Area, Va. (NAO) 5-24 Dam Safety Program, New York District (NAN) 2-18 Damariscotta River, Maine (NED) 1-37 Dana Point Harbor, Calif. (SPL) 33-23 Danbury, Conn. (NED) 1-22, 1-42, 1-49 Dansville and Vicinity, N.Y. (NCB) 32-14, 32-21 Dardanelle Lock & Dam, Ark. (SWL) 18-7, 18-12, 18-19 Darien Harbor, Ga. (SAS) 8-16 Dashields Locks and Dam, Pa. (ORD) 22-1, 22-7 Data Collection and Management Division, 53-1 Dauphin Island Bay, Ala. (SAM) 10-6, 10-27, 10-34, 10-45 Davenport, Iowa (NCR) 28-4, 28-8, 28-12 Davenport Center Lake, N.Y. (NAB) 4-37 Davenport Harbor, Iowa (Lindsay Park) (NCD) 29-7 David D. Terry Lock & Dam, Ark. (SWL) 18-2, 18-18 Davids Creek Lake, Iowa (MRO) 21-16 Davis, N.C. (SAW) 6-28 Davis Creek, Va. (NAO) 5-22 Day, John, Lock and Dam-Lake Umatilla, Oreg. and Wash. (NPP) 37-23, 37-32, 37-43, 37-57 Day, John, River, Oreg. (NPP) 37-16, 37-31, 37-41, 37-46 Days Creek Lake, Oreg. (NPP) 37-48 Dayton, Ky. (ORL) 24-3, 24-14, 24-24, 24-29 Dayton, Wash. (NPW) 39-16, 39-19 Dayton, Wyo. (MRO) 21-18 De Kalb, Ill. (NCR) 28-16 Deep Creek, N.C. (SAW) 6-27 Deep Creek, Va. (NA0) 5-22 Deep Creek, Newport News, Va. (NAO) 5-22 Deep Fork River, Okla. (SWT) 19-17 Deep River, Wash. (NPP) 37-45 Deep River Area, Wash. (NPP) 37-46 Deer Creek Lake, Ohio (0RB) 25-4, 25-12, 25-16 Deer Creek Prairie Levee, Ind. (ORL) 24-22, 24-25 Deer Island Area, Oreg. (NPP) 37-46 Deer Island Drainage District, Oreg. (NPP) 37-47, 37-54 Deer Island Thoroughfare, Maine (NED) 1-37 Degonia and Fountain Bluff Levee and Drainage District, Ill. (LMS) 14-14 Degray Lake, Ark. (LMK) 12-7, 12-14, 12-22 DeKalb, Ill. (NCR) 28-16 Delavare Coast Protection, Del. (NAP) 3-11, 3-17 Delaware Lake, Ohio (ORB) 25-4, 25-12, 25-16 Delaware River, Mouth of Neversink (NAP) 3-24 Delaware River, Pa., N.J. and Del., Philadelphia to the Sea (NAP) 3-3, 3-15, 3-18 Delaware River at Camden, N.J. (NAP) 3-21 Delaware River at East Branch, N.Y. (NAP) 3-13 Delaware River at Pennsville, N.J. (NAP) 3-21 Delaware River between Philadelphia, Pa., and Trenton, N.J. (NAP) 3-2, 3-15, 3-18 Delphi, Ind. (ORL) 24-20, 24-24, 24-29 Denison Dam-Lake Texoma, Tex. and Okla. (SWT) 19-12 Dennis Creek, N.J. (NAP) 3-21 Depere Lock and Dam, Wis. (NCE) 31-75 Depoe Bay, Oreg. (NPP) 37-7, 37-28, 37-38, 37-45, 37-48 Dequeen Lake, Ark. (SWL) 18-5, 18-11, 18-22 Derby, Conn. (NED) 1-22, 1-42, 1-49 Derby, Ind. (ORL) 24-22, 24-25 Des Moines, Iowa (NCR) 28-14, 28-16 Des Moines and Mississippi Levee District No. 1, Mo. (NCR) 28-14, 28-16 Des Moines Recreational River and Greenbelt, Iowa (NCR) 28-4, 28-8, 28-12 Deschutes River, Wash. (NPS) 38-25 Detour Harbor, Mich. (NCE) 31-6, 31-40, 31-57 Detroit Lake, Oreg. (NPP) 37-21, 37-32, 37-43, 37-53, 37-55 Detroit River, Mich. (NCE) 31-6, 31-40, 31-57, 31-73, 31-79 Devils Lake, N. Dak. (NCS) 27-6, 27-19 Devil's Swamp, JLa. (MR+T) 42-5, 42-29 Dewey Lake, Ky. (ORB) 25-4, 25-13, 25-16 Dickey Lake, Maine (NED) 1-44 Dickinson Bayou, Tex. (SWG) 15-26 I-14 INDEX Dierks Lake, Little River Basin, Ark. (SWL) 18-5, 18-11, 18-22 Diking and Improvement District 4, Wahkiakum County, Wash. (NPP) 37-46 Diking and Improvement District 5, Cowlitz County, Wash. (NPP) 37-46 Diking and Improvement District 11, Cowlitz County, Wash. (NPP) 37-47 Diking Districts 1 and 3 (Puget Island) and Little Island, Wash. (NPP) 37-46 Diking Districts 2, 3, and 5, Clatsop County, Oreg. (NPP) 37-46 Diking Improvement District 1, Pacific County, Wash. (NPP) 37-46 Diking Improvement Districts 2 and 13, Cowlitz County, Wash. (NPP) 37-47 Dillingham Harbor, Alaska (NPA) 40-2, 40-8, 40-10 Dillon Lake, Ohio (ORB) 25-5, 25-13, 25-16 Dillonvale, Ohio (Short Creek) (ORP) 26-23 Dismal Swamp Canal (Deep Creek), Va. (NAO) 5-21 Dismal Swamp Canal, (South Mills, N.C.) (NAO) 5-21 Dively Drainage & Levee District, Ill. (LMS) 14-14 Dodge City, Kans. (SWT) 19-17 Dog and Fowl Rivers, Ala. (SAM) 10-6, 10-27, 10-34 Doheny Beach State Park (Doheny State Beach), Calif. (SPL) 33-24 Dorchester Bay and Neponset River, Mass. (NED) 1-37 Dorena Lake, Oreg. (NPP) 37-14, 37-30, 37-41, 37-53, 37-55 Double Bayou, Tex. (SWG) 15-26 Double Creek, N.J. (NAP) 3-21 Douglas Harbor, Alaska (NPA) 40-12 Dover, Ky. (ORB) 25-20 Downeyville Lake, Ind. (ORL) 24-21, 24-28 Drainage District 1, Clatsop County, Oreg. (NPP) 37-46 Dresden Island Lock and Dam, Ill. (NCC) 28-20, 28-21 Drinkwater Sewer, Mo. (LMM) 13-7 Drum Inlet, N.C. (SAW) 6-25 Drury Drainage District, Ill. (NCR) 28-14, 28-16 Dry Creek, Wash. (NPW) 39-16 Dry Creek, Hawarden, Iowa (MRO) 21-16, 21-21 Dry Creek (Warm Springs) Lake and Channel Improvements, Calif. (SPK) 35-22, 35-32 Dry Fork and East Fork Lakes, Mo. (MRK) 20-19 Dry Pass, Alaska (NPA) 40-12 E Dry Run, Iowa (NCS) 27-24 Dubois, Pa. (ORP) 26-22, 26-28 Dubuque, Iowa (NCR) 28-14, 28-16 Dubuque Harbor, Iowa (NCD) 29-7 Duck Creek, Calif. (SPK) 35-29 Duck Creek Channel Improvement, Tex. (SWF) 16-21 Duck Island Harbor, Conn. (NED) 1-37 Duck Point Cove, Md. (NAB) 4-34 Duck River, Tenn. (ORN) 23-13 Duluth-Superior Harbor, Minn. and Wis. (NCE) 31-7, 31-40, 31-58 Dungeness River, Wash. (NPS) 38-7, 38-15, 38-21, 38-25 Dunkirk Harbor, N.Y. (NCB) 32-5, 32-18, 32-27 Dunn Branch, Woodbine, Camden County, Ga. (SAS) 8-7, 8-16 Duval County, Fla. (SAJ) 9-19, 9-30, 9-41 Duxbury Harbor, Mass. (NED) 1-37 Dworshak Dam and Reservoir, Idaho (NPW) 39-5, 39-10, 39-14, 39-20 Dyersburg, Tenn. (LMM) 13-7 Dyersburg, Tenn. (Southwest) (LMM) 13-7 Dymers Creek, Va. (NAO) 5-22 E Eagle Bay and Fort Yates Highway Bridges, N. Dak. (MRO) 21-16 Eagle Creek, S.C. (SAN) 7-7, 7-10, 7-14 Eagle Creek Lake, Ky. (ORL) 24-21 Eagle Creek Reservoir, Ohio (ORP) 26-22 Eagle Harbor, Mich. (NCE) 31-8, 31-41, 31-58 East Barre Dam, Vt. (NAN) 2-32 East Bay (Hanna Reef), Tex. (SWG) 15-26 East Bay Marina, Olympia Harbor, Wash. (NPS) 38-2, 38-13, 38-18 East Boothbay Harbor, Maine (NED) 1-37 East Branch, Clarion River Lake, Pa. (ORP) 26-6, 26-14, 26-18 East Branch, Conn. (NED) 1-22 East Branch Dam, Conn. (NED) 1-42, 1-48 East Brimfield Lake, Mass. (NED) 1-21, 1-31, 1-51 East Cape Girardeau and Clear Creek Drainage District, Ill. (LMS) 14-14 East Chester Creek, N.Y. (NAN) 2-3, 2-19, 2-23 East Fork, Tex. (SWF) 16-21 East Hartford, Conn. (NED) 1-22, 1-42, 1-48 East Liverpool Drainage and Levee District (NCR) 28-14, 28-16 East Lynn Lake, W. Va. (ORB) 25-5, 25-13, 25-17 1-15 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 East Moline, Ill. (NCR) 28-14, 28-16 East Muddy and Lake Creek, Oreg. (NPP) 37-50 East Muddy Creek, Mo. (MRK) 20-19 East Nishnabotna River, Near Grisvold, Iowa (MRO) 21-21 East Nishnabotna River, Page Co. Bridge, Near Essex, Iowa (MRO) 21-21 East Nishnabotna River, Red Oak, lova (MRO) 21-3, 21-10, 21-13 East Pass Channel from Gulf of Mexico into Choctawhatchee Bay, Fla. (SAM) 10-7, 10-27, 10-34 East Peoria Drainage and Levee District (NCR) 28-14, 28-16 East Peoria Sanitary District, Ill. (NCR) 28-16 East Point, La. (LMN) (LMK) 11-22, 12-25 East Poplar Bluff & Poplar Bluff, Mo. (SWL) 18-16 East Rainelle, V. Va. (ORB) 25-20, 25-22 East River, N.Y. (NAN) 2-4, 2-19, 2-23 East Rockavay (DEBS) Inlet, N.Y. (NAN) 2-34 East Rockavay Inlet, N.Y. (NAN) 2-4, 2-19, 2-23 East Rockavay Inlet to Rockavay Inlet and Jamaica Bay, N.Y. (Part I) (NAN) 2-14, 2-21, 2-26 East Rockavay Inlet to Rockavay Inlet and Jamaica Bay, N.Y. (Part II) (NAN) 2-32 East Sidney Lake, N.Y. (NAB) 4-15, 4-25 East St. Louis and Vicinity, Ill. (LMS) 14-3, 14-9, 14-11 East Weaver Creek, Calif. (SPK) 35-29 East, West and Duvamish Waterways, Seattle Harbor, Wash. (NPS) 38-11 Eastern Branch, Va. (NAO ) 5-19 Eastern Rapides and South-Central Avoyelles Parishes, La. (MR+T) 42-15, 42-28, 42-50, 42-59 Eastlake, Ohio (NCB) 32-37 Eastman, H. V., Lake, Calif. (SPK) 35-4, 35-21 Eastport Harbor, Maine (NED) 1-37 Eau Galle River, Wis. (NCS) 27-6, 27-19 Eau Gallie Harbor, Fla. (SAJ) 9-5, 9-26 Echo Bay Harbor, N.Y. (NAN) 2-30 Edenton Harbor, N.C. (SAW) 6-25 Edgar Jadvin, General, Dam and Reservoir, Pa. (NAP) 3-13, 3-17 Edgartown Harbor, Mass. (NED) 1-37 Edisto River, S.C. (SAN) 7-8, 7-15, 7-16 Edisto River, North Fork, S.C. (SAN) 7-16 Edisto River, Vicinity Canadays Landing, S.C. (SAN) 7-16 Ediz Hook, Wash. (NPS) 38-2, 38-13, 38-18 Edmonds Harbor, Wash. (NPS) 38-24, 38-30 Edward Macdovell Lake, N.H. (NED) 1-19, 1-30, 1-50 Eel River, Calif. (SPK) 35-29 Eel River, Ind. (ORL) 24-30 Egegik River, Alaska (NPA) 40-12 Eighteen Mile Island, Ky. (ORL) 24-30 El Dorado, Kans., V. Br., Walnut River, Channel Improvement (SWT) 19-15 El Dorado Lake, Kans. (SWT) 19-4, 19-9, 19-13 El Paso, Tex. (SWA) 17-2, 17-8, 17-10 El Tuque Beach, P.R. (SAJ) 9-20, 9-30, 9-41 Eldred, Ill. (LMS) 14-14 Eldred, Pa. (ORP) 26-28 Eldred and Spankey Drainage and Levee District, Ill. (LMS) 14-3, 14-9, 14-11 Elfin Cove, Alaska (NPA) 40-12 Elizabeth, N.J. (NAN) 2-15, 2-21, 2-26, 2-34 Elizabeth River, N.J. (NAN) 2-36 Elizabethtown, Ill. (ORL) 24-22, 24-25 Elk and Little Elk Rivers, Md. (NAB) 4-34 Elk City Lake, Kans. (SWL) (SWT) 18-21, 19-4, 19-10, 19-13, 19-16 Elk Creek, Clyde, Kans. (MRK) 20-19 Elk Creek Harbor, Pa. (NCB) 32-35 Elk Creek Lake, Oreg. (NPP) 37-14, 37-30, 37-41 Elk River, Ala. and Tenn. (ORN) 23-13 Elk River, Minn. (NCS) 27-24, 27-28 Elk River, W. Va. (ORB) 25-19 Elkhorn River, Q Street Bridge, near Gretna, Nebr. (MRO) 21-20 Elkhorn River, Ray Bridge, near Norfolk, Nebr. (MRO) 21-20 Elkins, W. Va. (ORP) 26-4, 26-13, 26-18, 26-26 Elkland, Pa. (NAB) 4-36, 4-39 Elkport, Iowa (NCR) 28-14, 28-16 Ellerbe Creek, Durham County, N.C. (SAW) 6-27 Ellicott Creek, N.Y. (NCB) 32-14, 32-21 Ellis Swamp, Gates County, N.C. (SAW) 6-27 Elm Fork Floodway, Tex. (SWF) 16-5, 16-14, 16-18 Elmira, N.Y. (NAB) 4-16, 4-25 Elochoman Slough, Wash. (NPP) 37-45 Elvha River, Wash. (NPS) 38-25 Emergency Bank Protection Activities Albuquerque, N. Mex., District (SWA) 17-8 Buffalo, N.Y., District (NCB) 32-38 Chicago, Ill., District (NCC) 30-7 1-16 INDEX Detroit, Mich., District (NCE) 31-32 Huntington, V. Va., District (ORH) 25-11 Kansas City, Mo., District (MRK) 20-8 Little Rock, Ark., District (SWL) 18-7 Los Angeles, Calif., District (SPL) 33-10 Louisville, Ky., District (ORL) 24-13, 24-31 Nashville, Tenn., District (ORN) 23-19 New England Division (NED) 1-23 New York, N.Y., District (NAN) 2-36 Omaha, Neb., District (MRO) 21-7 Pittsburgh, Pa., District (ORP) 26-29 Portland, Oreg., District (NPP) 37-15 Rock Island, Ill., District (NCR) 28-18 Sacramento, Calif., District (SPK) 35-16 San Francisco, Calif., District (SPN) 34-3 St. Louis, Mo., District (LMS) 14-8, 14-14 St. Paul, Minn., District (NCS) 27-29 Tulsa, Okla., District (SVT) 19-19 Vicksburg, Miss., District (LMK) 12-11 Walla Walla, Wash., District (NPW) 39-3 Emergency Flood Control Activities Alaska District (NPA) 40-6 Albuquerque, N. Mex., District (SWA) 17-8 Baltimore, Md., District (NAB) 4-20 Charleston, S.C., District (SAN) 7-16 Chicago, Ill., District (NCC) 30-7 Detroit, Mich., District (NCE) 31-34 Fort Worth, Tex., District (SWF) 16-12 Galveston, Tex., District (SWG) 15-11 Huntington, V. Va., District (ORB) 25-11 Jacksonville, Fla., District (SAJ) 9-25 Kansas City, Mo., District (MRK) 20-8 Little Rock, Ark., District (SWL) 18-7 Los Angeles, Calif., District (SPL) 33-10 Louisville, Ky., District (ORL) 24-13 Memphis, Tenn., District (LMM) 13-3 Mobile, Ala., District (SAM) 10-44 New England Division (NED) 1-23 New York District (NAN) 2-18 Norfolk, Va., District (NAO) 5-11 Omaha, Neb., District (MRO) 21-6 Philadelphia, Pa., District (NAP) 3-12 Portland, Oreg., District (NPP) 37-15 Rock Island, Ill., District (NCR) 28-19 Sacramento, Calif., District (SPK) 35-16 San Francisco, Calif., District (SPN) 34-3 Savannah, Ga., District (SAS) 8-7 Seattle, Wash., District (NPS) 38-31 St. Louis, Mo., District (LMS) 14-8 St. Paul, Minn., District (NCS) 27-29 Tulsa, Okla., District (SWT) 19-19 Vicksburg, Miss., District (LMK) 12-11 Walla Walla, Wash., District (NPW) 39-2 Wilmington, N.C., District (SAW) 6-14 Emergency protection for highway and railroad facilities at Chester, Ill., bridge (LMS) 14-14 Emergency repairs to levees on Mississippi, Illinois and Kaskaskia Rivers (LMS) 14-14 Emergency Streambank and Shoreline Protection Detroit, Mich., District (NCE) 31-32 Jacksonville, Fla., District (SAJ) 9-25 Little Rock, Ark., District (SWL) 18-7 Mobile, Ala., District (SAM) 10-42 New York, N.Y., District (NAN) 2-36 Tulsa, Okla., District (SWT) 19-19 Emmett Sewage Lagoon, Payette River, Idaho (NPW) 39-19 Empire-Stratton, Ohio (ORP) 26-22, 26-26 Emsworth Locks and Dam, Pa. (ORD) 22-2, 22-7 Enderlin, N. Dak. (NCS) 27-6, 27-19, 27-28 Endicott-Johnson City and Vestal, N.Y. (NAB) 4-36, 4-39 Engineer Topographic Laboratories (ETL) 51-1 England Pond Levee, Ill. (ORL) 24-20, 24-24, 24-29 English, Ind. (ORL) 24-20, 24-30 Enid, Okla. (SWT) 19-17 Enid Lake, Miss. (MR+T) 42-20, 42-59 Enid Levee Floodway, Okla. (SWT) 19-15 Entiat River, Wash. (NPS) 38-25 Ephraim Canyon Wash, Nogales, Ariz. (SPL) 33-31 Erie Harbor, Pa. (NCB) 32-5, 32-18, 32-27, 32-39 Escambia and Conecuh Rivers, Fla. and Ala. (SAM) 10-42, 10-45 Esopus Creek, N.Y. (NAN) 2-36 Esquatzel Coulee, Wash. (NPW) 39-16, 39-18 Essex River, Mass. (NED) 1-37 Estes, Carl L., Dam and Lake, Tex. (SWF) 16-21 Euclid Creek, Cleveland, Ohio (NCB) 32-14, 32-21 Eufaula Lake, Okla. (SWL) (SWT) 18-21, 19-7, 19-12, 19-14, 19-16 Evansdale, Iowa (NCR) 28-14, 28-16 Evanston, Ill. (NCC) 30-14 Evansville, Ind. (ORL) 24-3, 24-14, 24-24, 24-29, 24-30 Everett Harbor and Snohomish River, Wash. (NPS) 38-2, 38-13, 38-18 Everglades Harbor, Fla. (SAJ) 9-46, 9-47 Exeter River, N.H. (NED) 1-37 I-17 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Existing levees and extensions from Bastrop, La. to mouth of Boeuf River (LMK) 12-22 F Fabius River Drainage District, Mo. (NCR) 28-14, 28-16 Fair Haven Beach State Park, N.Y. (NCB) 32-36 Fairbanks, Tanana River and Chena Slough, Alaska (NPA) 40-13 Fairbury, Nebr. (MRK) 20-19 Fairfield Vicinity Streams, Calif. (SPK) 35-19, 35-25 Fairport Harbor, Ohio (NCB) 32-5, 32-18, 32-28 Fajardo Harbor, P.R. (SAJ) 9-47 Falk Bridge Loc., Payette River, Idaho (NPW) 39-19 Fall Brook Lake, Pa. (NAB) 4-37 Fall Creek Lake, Oreg. (NPP) 37-14, 37-30, 37-41, 37-53, 37-55 Fall River Basin, S. Dak. (MRO) 21-3, 21-10, 21-13 Fall River Harbor, Mass. (NED) 1-37 Fall River Lake, Kans. (SWL) (SWT) 18-21, 19-4, 19-10, 19-13, 19-16 Falls Lake, N.C. (SAW) 6-12, 6-15, 6-20 Falmouth Harbor, Mass. (NED) 1-37 Falmouth Lake, Ky. (ORL) 24-21, 24-27 Fancy Bluff Creek, Ga. (SAS) 8-16 Far Creek, N.C. (SAW) 6-5, 6-18 Fargo, N. Dak. (NCS) 27-28 Farm Creek, Ill. (NCR) 28-4, 28-8, 28-12 Farmers Drainage and Levee District (NCR) 28-14, 28-16 Farmers Levee and Drainage District (NCR) 28-14, 28-15 Farmington, N.H. (NED) 1-22 Faulkner County Levee District No. 1, Arkansas River, Ark. (SWL) 18-16 Feather River, Calif. (SPK) 35-28 Federal Energy Regulatory Commission 47-1 Federal Energy Regulatory Commission Licenses at Locks and Dams, Ohio River (ORD) 22-6 Ferguson Creek, Oreg. (NPP) 37-50 Fern Ridge Lake, Oreg. (NPP) 37-14, 37-31, 37-41, 37-53, 37-55 Fernandina Harbor, Fla. (SAJ) 9-5, 9-27, 9-33 Ferrells Bridge Dam-Lake O' The Pines, Tex. (LMN) 11-22 Ferrells Bridge Dam-Lake O' The Pines, Tex. (SWF) 16-5, 16-14, 16-18 Ferry Butte, Idaho (NPW) 39-19 Filberts Creek, N.C. (SAW) 6-27 Fire Island Inlet to Jones Inlet, N.Y. (NAN) 2-5, 2-19, 2-23, 2-31 Fire Island Inlet to Montauk Point, N.Y. (NAN) 2-32 Fisher, 0. C., Dam and Lake, Tex. (SWF) 16-9, 16-15, 16-19 Fisherman's Wharf Area, San Francisco Harbor, Calif. (SPN) 34-1, 34-4, 34-7 Fishing Bay, Md. (NAB) 4-4, 4-22, 4-29 Fishing Creek, Md. (NAB) 4-4, 4-22, 4-29 Fishing Creek, N.C. (SAW) 6-25 Fishing Creek, Pine Grove, W. Va. (ORH) 25-22 Fishtrap Lake, Ky. (ORH) 25-5, 25-13, 25-17 Fitchburg, Mass. (NED) 1-22, 1-42 Fivemile River Harbor, Conn. (NED) 1-37, 1-44 Flannagan, John W., Dam and Reservoir, Va. (ORH) 25-6, 25-13, 25-17 Flat Creek, Oreg. (NPP) 37-50 Flat Rock Creek Channel Improvement, Tulsa, Okla. (SWT) 19-15, 19-16 Flathead River, Mont. (NPS) 38-24, 38-25, 38-26 Fletcher and Sunshine Gardens Levee, Ind. (ORL) 24-22, 24-25 Floating Breakwater Prototype Test Program, Seattle, Wash. (NPS) 38-3, 38-13, 38-18 Flood Control and Coastal Emergency Activities Buffalo, N.Y., District (NCB) 32-38 Huntington, W.Va., District (ORH) 25-11 Pittsburgh, Pa., District (ORP) 26-12 Tulsa, Okla., District (SWT) 19-19 Flood Damage Prevention Studies, Tulsa, Okla., District (SWT) 19-17 Flood Insurance Activities Los Angeles, Calif., District (SPL) 33-10 Sacramento, Calif., District (SPK) 35-16 Flood Insurance Studies and Flood Hazard Information Reports, Mobile, Ala. (SAM) 10-49 Floodwall and Levees at Portland, Oreg. (NPP) 37-50 Florence Levee, Kans. (SWT) 19-15, 19-16 Floyd River, Sioux City, Iowa (MRO) 21-17, 21-21 Flushing Bay and Creek, N.Y. (NAN) 2-30 Fly Creek, Ala. (SAM) 10-7, 10-27, 10-35, 10-45 Follansbee, W. Va. (ORP) 26-23 I-18 INDEX Folly Brook, Wethersfield, Conn. (NED) 1-42, 1-48 Folly River, S.C. (SAN) 7-4, 7-9, 7-12 Folsom Lake, Calif. (SPK) 35-29 Forest Heights, Md. (NAB) 4-36, 4-39 Forest River, N.D. (NCS) 27-28 Forestville, Mich. (NCE) 31-77 Forked Deer River, Tenn., including South Fork (LMM) 13-6 Forsyth, Mont. (MRO) 21-17, 21-19 Fort Chartres and Ivy Landing Drainage District No. 5 and Stringtown Drainage and Levee District No. 4, Ill. (LMS) 14-14 Fort Cobb Reservoir, Okla. (SWT) 19-18 Fort Fisher and Vicinity, N.C. (SAW) 6-26 Fort Gibson Lake, Okla. (SWL) (SWT) 18-21, 19-7, 19-12, 19-14, 19-16 Fort Kent, Maine (NED) 1-22, 1-42 Fort Leavenvorth, Kans., Bridge Removal (MRK) 20-18 Fort Loudon Lock and Dam, Tenn. (ORN) 23-17 Fort Macon State Park, N.C. (SAW) 6-26 Fort Madison Harbor, Iowa (NCD) 29-7 Fort Myers Beach, Fla. (SAJ) 9-5, 9-27, 9-34, 9-46 Fort Niagara State Park, N.Y. (NCB) 32-36 Fort Peck Lake, Mont. (MRO) 21-7, 21-12, 21-15 Fort Pierce, Fla. (SAJ) 9-20, 9-27, 9-30 Fort Pierce Harbor, Fla. (SAJ) 9-6, 9-27, 9-34, 9-46 Fort Randall Dam-Lake Francis Case, S. Dak. (MRO) 21-7, 21-12, 21-15 Fort Scott Lake, Kans. (MRK) 20-19, 20-21 Fort Smith, Arkansas River, Ark. (SWL) 18-16 Fort Supply Lake, Okla. (SWT) 19-4, 19-10, 19-13 Fort Worth Floodway (Clear Fork), Tex. (SWF) 16-21 Fort Worth Floodway (West Fork), Tex. (SWF) 16-21 Foss Reservoir, Okla. (SWT) 19-18 Foster Creek Road, Wash. (NPS) 38-26 Foster Joseph Sayers Dam, Pa. (NAB) 4-19, 4-27 Foster Lake, Oreg. (NPP) 37-53 Four Pole Creek, W. Va. (ORB) 25-22 Four River Basins, Fla. (SAJ) 9-23, 9-31, 9-42, 9-53 Fourche Creek, Little Rock, Ark. (SWL) 18-16 Fourmile Run, Va. (NAB) 4-36 Fowl River, Ala. (SAM) 10-45 Fox Point Barrier, R.I. (NED) 1-22, 1-23, 1-42 Fox River, Wis. (NCE) 31-8, 31-41, 31-59 Fox River Locks and Dams, Wis. (NCE) 31-75 Francis B. Walter Dam, Pa. (NAP) (NAB) 3-12, 3-17 Frankfort, Kans. (MRK) 20-19 Frankfort, Ky. (ORL) 24-20, 24-21, 24-24, 24-29 Frankfort Harbor, Mich. (NCE) 31-9, 31-41, 31-59 Franklin Falls Dam, N.H. (NED) 1-19, 1-30, 1-50 Franklin, V. P., Lock and Dam, Fla. (SAJ) 9-49 Frazer-Wolf Point, Mont. (MRO) 21-17 Frazeysburg, Ohio (ORH) 25-21 Freeport, Ill. (NCR) 28-15 Freeport, Pa. (ORP) 26-23 Freeport and Vicinity, Tex. Hurricane-Flood Protection (SWG) 15-10, 15-26 Freeport Harbor, Tex. (SWG) 15-3, 15-12, 15-17, 15-27, 15-28, 15-33 Fremont, Ohio (NCB) 32-37 French Broad and Little Pigeon Rivers, Tenn. (ORN) 23-13 Frenchboro Harbor, Maine (NED) 1-37 Freshwater Bayou, La. (LMN) 11-20 Friday Harbor Marina, Wash. (NPS) 38-3, 38-13, 38-18 Friendly, W. Va. (ORH) 25-21 Friendsville, Md. (ORP) 26-22, 26-28 From North Little Rock to Gillett, Ark. (Above Plum Bayou) (SWL) 18-16 Fullerton, Ky. (ORH) 25-20 Fullerton Dam, Calif. (SPL) 33-30 Fulton, Ill. (NCR) 28-14, 28-16 G Galax, Va. (ORB) 25-20, 25-22 Galena, Ill. (NCR) 28-14, 28-17 Galisteo Dam, N. Mex. (SWA) 17-4, 17-9, 17-11 Gallepolis Locks and Dam, V. Va. (ORD) 22-3, 22-8 Gallipolis, Ohio (ORH) 25-21 Galveston Harbor and Channel, Tex. (SWG) 15-3, 15-12, 15-18, 15-27, 15-28, 15-33 Galveston Seawall Extension, Tex. (SWG) 15-10 Gapway Swamp, N.C. and S.C. (SAN) (SAW) 6-27, 7-8 Gardner, Mass. (NED) 1-22, 1-42, 1-48 Gardners Creek, N.C. (SAW) 6-27 Garland City, Ark. (LMN) (LMK) 11-22, 12-23, 12-25 Garnett Lake, Kans. (MRK) 20-19, 20-21 I-19 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Garrison Dam-Lake Sakakavea, N. Dak. (MRO) 21-8, 21-12, 21-16 Gasconade River, Mo. (MRK) 20-18 Gastineau Channel, Alaska (NPA) 40-12 Gate Creek Lake, Oreg. (NPP) 37-48, 37-56 Gathright Dam and Lake Moomav, Va. (NAO) 5-10, 5-16, 5-20 Gauley River, W. Va. (OR) 25-19 Gavins Point Dam-Levis and Clark Lake, Nebr. and S. Dak. (MRO) 21-8, 21-12, 21-16, 21-18, 21-19 Gaysville Lake, Vt. (NED) 1-44 Genegantslet Lake, N.Y. (NAB) 4-37 General Edgar Jadvin Dam and Reservoir, Pa. (NAP) 3-13, 3-17 General Joe Wheeler Dam (ORN) 23-17 Geneva-On-The-Lake, Ohio (NCB) 32-6, 32-18, 32-35 Genoa Sever Facility, N.C. (SAW) 6-11, 6-20 Geographic Sciences Laboratory 51-1 George, Walter F., Lock and Dam, Ala. and Ga. (SAM) 10-24, 10-30, 10-41 George W. Andrews Lock and Dam, Ala. and Ga. (SAM) 10-22, 10-30, 10-41 Georges River, Maine (NED) 1-37 Georgetown Harbor, S.C. (SAN) 7-4, 7-9, 7-12 Gering Valley, Nebr. (MRO) 21-17, 21-20 Gila and Salt Rivers Levee and Channel Improvements, Ariz. (SPL) 33-25 Gila River Basin, Ariz. (SPL) 33-5, 33-14, 33-15, 33-21, 33-25 Giles Creek, Elkhorn, Nebr. (MRO) 21-18 Gill Township Levee, Ind. (ORL) 24-20, 24-29 Gillham Lake, Ark. (SWL) 18-6, 18-11, 18-22 Gill's Creek, Lancaster, S.C. (SAN) 7-17 Girty's Run, Millvale, Pa. (ORP) 26-4, 26-13 Glasgow, Mont. (MRO) 21-17, 21-19 Gleason Creek, Nev. (SPK) 35-29 Glen Cove Creek, N.Y. (NAN) 2-30 Glen Cove Harbor, N.Y. (NAN) 2-34 Gloucester Harbor and Annisquam River, Mass. (NED) 1-37 Goat Island, Ga. and S.C. (SAS) 8-17 Golconda, Ill. (ORL) 24-20, 24-24, 24-29 Gold Creek, Alaska (NPA) 40-6, 40-13 Goldsboro, Neuse River, N.C. (SAW) 6-27 Goleta, Calif., and Vicinity (SPL) 33-11, 33-25 Gooding Area, Idaho (NPW) 39-16, 39-18 Goose Creek, Md. (NAB) 4-34 Goose Creek, S.C. (SAN) 7-15 Gordons Creek, Hattiesburg, Miss. (SAM) 10-14, 10-28, 10-39 Gordons Landing, Lake Champlain, Vt. (NAN) 2-30 Goshen Creek, N.J. (NAP) 3-21 Governor's Run, Md. (NAB) 4-37 Govanus Creek Channel, N.Y. (NAN) 2-30 Grafton, N. Dak. (NCS) 27-24 Grafton Small Boat Harbor, Ill. (LMS) 14-13 Grahn, Ky. (ORB) 25-22 Grand Bayou Pass, La. (LMN) 11-20 Grand Calumet River Lock, Ind. (NCC) 28-21 Grand Forks, N. Dak. (NCS) 27-28 Grand Haven Harbor and Grand River, Mich. (NCE) 31-9, 31-41, 31-59, 31-79 Grand Isle and Vicinity, La. (LMN) 11-9, 11-13, 11-16 Grand Lake 0' the Cherokees, Okla. (SWT) 19-7, 19-12, 19-14, 19-16 Grand Marais Harbor, Mich. (NCE) 31-76, 31-77 Grand Marais Harbor, Minn. (NCE) 31-10, 31-41, 31-60 Grand Prairie, Tex., Sanitary Landfill (SWF) 16-6, 16-14, 16-18 Grand Prairie, Tex., Streambank Erosion at Meyers Road (SWF) 16-6, 16-14, 16-18 Grand Prairie-Bayou Meto, Ark., (MR+T) 42-16, 42-28, 42-52 Grand River, Grandville, Mich. (NCE) 31-78, 31-79 Grand River, Lansing, Mich. (NCE) 31-78 Grand Tower Drainage and Levee District, Ill. (LMS) 14-14 Grand Traverse Bay Harbor, Mich. (NCE) 31-10, 31-42, 31-60 Grande Ronde Lake, Oreg. (NPW) 39-16 Grande Ronde Valley, Oreg. (NPW) 39-16, 39-18 Grandview, Ind. (0RL) 24-22, 24-25 Grandview Bay Harbor, N.Y. (NCB) 32-39 Granger, Tex. (SWF) 16-16 Grant Parish, Below Colfax, La. (LMN) (LMK) 11-22, 12-24, 12-25 Grant's Canal Lake Providence, La. (MR+T) 42-56 Granville, Pa. (ORP) 26-22, 26-28 Grapevine Lake, Tex. (SWF) 16-6, 16-15, 16-18 Grasse River (Massena), N.Y. (NCB) 32-35 Grassy Creek, Ind. (ORL) 24-20, 24-30 Graves Creek, Idaho (NPW) 39-16 Grays Creek Canal, Shelby Co., Tenn. (LMM) 13-1, 13-4, 13-5 Grays Harbor and Chehalis River, Wash. (NPS) 38-3, 38-12, 38-13, 38-18 I-20 INDEX Grays Landing Lock and Dam, Pa. (ORP) 26-25 Grays Reef Passage, Mich. (NCE) 31-77 Grays River, Wash. (NPP) 37-45 Grayson Lake, Ky. (ORB) 25-5, 25-13, 25-17 Great Chazy River, N.Y. (NAN) 2-30 Great Egg Harbor Inlet and Peck Beach, N.J. (NAP) 3-23 Great Falls, Mont. (MRO) 21-4, 21-10, 21-13 Great Kills Harbor, N.Y. (NAN) 2-30 Great Lakes Information Management 31-37 Great Lakes to Hudson River Waterway, N.Y. (NAN) 2-30 Great Miami River, Ind. (ORL) 24-27, 24-30 Great Pee Dee River, S.C. (SAN) 7-15 Great Salt Plains Lake, Okla. (SWT) 19-4, 19-10, 19-13 Great Salt Pond, R.I. (NED) 1-37 Great Sodus Bay Harbor, N.Y. (NCB) 32-6, 32-18, 32-29, 32-39 Great South Bay, N.Y. (NAN) 2-30 Green and Barren Rivers, Ky. (ORL) 24-2, 24-14, 24-18, 14-23, 24-27 Green Bay Harbor, Wis. (NCE) 31-10, 31-42, 31-60 Green Bay Levee and Drainage District No. 2, Iowa (NCR) 28-14, 28-17 Green Harbor, Mass. (NED) 1-4, 1-25, 1-33 Green Island Levee and Drainage District, Iowa (NCR) 28-16 Green Peter-Foster Lakes, Oreg. (NPP) 37-22, 37-32, 37-43, 37-53, 37-55 Green River, Wash. (NPS) 38-26 Green River Lake, Ky. (ORL) 24-8, 24-15, 24-27 Green Valley Creek, Calif. (SPK) 35-29 Greene, N.Y. (NAB) 4-36, 4-39 Greenfield Bayou Levee, Ind. (ORL) 24-21, 24-24 Greenport Harbor, N.Y. (NAN) 2-30 Greenup, Ky. (ORB) 25-20 Greenup Locks and Dam, Ky. (ORD) 22-3, 22-8 Greenvale Creek, Va. (NAO) 5-22 Greenville, Tex. (SWF) 16-21 Greenville Harbor, Miss. (MR+T) 42-29, 42-56 Greenwich Bay, R.I. (NED) 1-37 Greenwich Harbor, Conn. (NED) 1-37 Greenwich Point Beach, Conn. (NED) 1-44 Greenwood Beach, Evanston, Ill. (NCC) 30-6 Greers Ferry Lake, Ark. (SWL) 18-8, 18-12, 18-23 Gregory Drainage District, Mo. (NCR) 28-14, 28-17 Grenada Lake, Miss. (MR+T) 42-20, 42-59 Greybull, Wyo. (MRO) 21-17, 21-19 Griffithsville-Yawkey, W.Va. (ORB) 25-22 Grove Lake, Kans. (MRK) 20-19 Guadalupe River (Remove Log Jams), Tex. (SWG) 15-26 Guayanes Harbor, P.R. (SAJ) 9-47 Guilford Harbor, Conn. (NED) 1-37 Guilford Point Beach (Jacobs Beach), Guilford, Conn. (NED) 1-41 Gulf Beach, Milford, Conn. (NED) 1-41 Gulf Intracoastal Waterway between Apalachee Bay, Fla. and Mexican Border (Mobile District) (SAM) 10-8, 10-27, 10-35 Gulf Intracoastal Waterway between Apalachee Bay, Fla., and Mexican Border (New Orleans Dist.) (LMN) 11-2, 11-13, 11-15, 11-18 Gulf Intracoastal Waterway between Apalachee Bay, Fla., and Mexican Border (Galveston, Tex., District) (SWG) 15-4, 15-12, 15-18, 15-27, 15-31, 15-32, 15-33 Gulf Intracoastal Waterway St. Marks to Tampa Bay, Fla. (SAJ) 9-47 Gulf Street and Trumbull Avenue, Milford, Conn. (NED) 1-17, 1-29, 1-36 Gulfport Harbor, Miss. (SAM) 10-8, 10-27, 10-36 Gull Lake Reservoir, Minn. (NCS) 27-26 Guntersville Lock and Dam, Ala. (ORN) 23-17 Guttenberg, Iowa (NCS) 27-24 Guyandotte River, W. Va. (ORB) 25-19 Gypsum, Kans. (MRK) 20-19 H H. V. Eastman Lake, Calif. (SPK) 35-4, 35-21 Hackleman Corners Lake, Mo. (MRK) 20-20 Haines Harbor, Alaska (NPA) 40-12 Haleiwa Beach, Hawaii (POD) 36-11 Haleiwa Small Boat Harbor, Hawaii (POD) 36-10 Halfmoon Bay Harbor, Calif. (SPN) 34-7 Hall Meadow Brook, Conn. (NED) 1-22 Hall Meadow Brook Dam, Conn. (NED) 1-42, 1-48 Halsite Area, Huntington, N.Y. (NAN) 2-36 Hamburg L-575, Iowa (MRO) 21-21 Hamlin Beach Harbor, N.Y. (NCB) 32-35 Hamlin Beach State Park, N.Y. (NCB) 32-36 Hammersley Inlet, Wash. (NPS) 38-24, 38-29 Hammonassett Beach, Madison, Conn. (NED) 1-41 Hammond Bay Harbor, Mich. (NCE) 31-11, 31-42, 31-60 Hammond Small Boat Basin, Oreg. (NPP) 37-45 Hammondsport, N.Y. (NCB) 32-39 Hampton Beach, Hampton, N.H. (NED) 1-41 Hampton Creek, Va. (NAO) 5-22 I-21 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Hampton Harbor, N.H. (NED) 1-37 Hampton Institute, Va. (NAO) 5-23 Hampton Roads and Harbors of Norfolk and Newport News, Va.-Collection and Removal of Drift (NA0) 5-4, 5-14, 5-18 Hampton Roads Harbor, Supervision of (NAO) 5-7, 5-15 Hana Small Boat Harbor, Hawaii (POD) 36-12 Hanalei Bay Small Boat Harbor, Hawaii (POD) 36-12 Hanapepe Bay, Hawaii (POD) 36-11 Hanapepe River, Hawaii (POD) 36-12 Hancock Brook Lake, Conn. (NED) 1-16, 1-29, 1-49 Hanging Rock, Ohio (ORH) 25-21 Hannibal, Mo. (NCR) 28-7, 28-9, 28-13 Hannibal Harbor, Mo. (NCD) 29-8 Hannibal Locks and Dam, W. Va. (ORD) 22-1, 22-7 Hanson, Howard A., Dam, Wash. (NAS) 38-7, 38-15, 38-21 Harbor Beach Harbor, Mich. (NCE) 31-11, 31-42, 31-60 Harbor of Refuge, Block Island, R.I. (NED) 1-37 Harbor of Refuge, Delaware Bay, Del. (NAP) 3-4, 3-15, 3-19 Harbor of Refuge, N.C. (SAW) 6-28 Harbor of Refuge and Pt. Judith Pond, R.I. (NED) 1-7, 1-26, 1-34, 1-44 Harden, Cecil M., Lake, Ind. (ORL) 24-7, 24-15, 24-27 Barkers Island Harbor, N.C. (SAW) 6-29 Harlan County Lake, Nebr. (MRK) 20-3, 20-11, 20-15, 20-21 Harlem River, N.Y. (NAN) 2-30 Harpers Ferry, W. Va. (NAB) 4-37 Harpswell, Maine (NED) 1-22 Harraseeket River, Maine (NED) 1-37 Harriet Island Harbor, St. Paul, Minn. (NCD) 29-7 Harris Fork Creek, Tenn. and Ky. (MR+T) 42-58 Harrisburg, Ill. (ORL) 24-20, 24-24, 24-29 Harrison County, Miss. (SAM) 10-42 Harrisonville Levee and Drainage District, Ill. (LMS) 14-14 Harrisville Harbor, Mich. (NCE) 31-12, 31-42, 31-61 Harrodsburg, Ky. (ORL) 24-30 Harry S. Truman Dam and Reservoir, Mo. (MRK) 20-9, 20-13, 20-17, 20-21 Harsha, William H., Lake, Ohio (ORL) 24-12, 24-17, 24-27 Hartford, Conn. (NED) 1-22, 1-42, 1-48 Hartford, Vt. (NED) 1-42, 1-48 Hartford, V. Va. (ORB) 25-21 Hartland, Maine (NED) 1-22 Hartwell Drainage and Levee District, Ill. (LMS) 14-3, 14-9, 14-11 Hartvell Lake, Ga. and S.C. (SAS) 8-8, 8-12, 8-15, 8-17 Harvey Canal, Bayou Barataria Levee, La. (LMN) 11-22 Hastings Harbor, Minn. (NCD) 29-7 Hatchie River, Miss. (LMM) 13-2, 13-4, 13-5 Haverhill, Mass. (NED) 1-22 Havre, Mont. (MRO) 21-17, 21-19 Havre, Scott Coulee-Bull Hook Dam, Mont. (MRO) 21-19 Hawarden, Iowa (MRO) 21-21 Havesville, Ky. (ORL) 24-20, 24-24, 24-29, 24-30 Hay Creek, Birdsboro, Pa. (NAP) 3-23 Hay (West Harbor), Fisher's Island, N.Y. (NED) 1-37 Hayden Island, Oreg. (NPP) 37-47, 37-54 Hays, Kans. (MRK) 20-20 Haysi, Va. (ORH) 25-20 Hayward Creek, Mass. (NED) 1-22 Hayward Creek, Quincy-Braintree, Mass. (NED) 1-22, 1-42 Heela-Kea Small Boat Harbor, Hawaii (POD) 36-10 Heise-Roberts Area, Idaho (NPV) 39-16, 39-19 Heise-Roberts Extension, Idaho (NPW) 39-16, 39-19 Helena Harbor, Ark. (LMN) 13-6 Hellens Creek, Md. (NAB) 4-37 Helm Lake, Ill. (ORL) 24-22, 24-28 Hempstead County Levee District No. 1, Ark. (LMN) (LMK) 11-22, 12-24, 12-25 Hempstead Harbor, N.Y. (NAN) 2-30 Henderson, W. Va. (ORH) 25-21 Henderson Bay, Wash. (NPS) 38-26 Henderson County Drainage Districts Nos. 1, 2 and 3, Ill. (NCR) 28-14, 28-17 Henderson River, Ill. (NCR) 28-16 Hendrick's Harbor, Maine (NED) 1-37 Hennepin Drainage and Levee District, Ill. (NCR) 28-14, 28-17 Henry, Robert F., Lock and Dam, Ala. (SAM) 10-20, 10-30 Henry T. Rainey Dam, Ill. (NCD) 29-6 Hergot Drainage and Levee District (NCR) 28-17 Herkimer, N.Y. (NAN) 2-32 Herreid, Spring Creek, S. Dak. (MRO) 21-17, 21-20 I-22 INDEX Herring Bay & Rockhold Creek, Md. (NAB) 4-35, 4-22, 4-29 Herring Creek, Md. (NAB) 4-34, 4-38 Heyburn Lake and Polecat Creek, Okla. (SWT) 19-4, 19-10, 19-13 Hickman Harbor, Ky. (LMM) 13-6 Hidden Dam-Hensley Lake, Fresno River, Calif. (SPK) 35-6, 35-21 Higginsport, Ohio (ORH) 25-21 Highland Bayou, Tex. (SWG) 15-10, 15-26 Highway 12, Colo. (SWA) 17-2, 17-8, 17-10 Highway 362 Bridges, Prentiss County, Miss. (SAM) 10-16, 10-17, 10-29, 10-40 Hildebrand Lock and Dam, W. Va. (ORP) 26-25 Hills Creek Lake, Oreg. (NPP) 37-22, 37-32, 37-43, 37-53, 37-55 Hillsborough Bay, Fla. (SAJ) 9-54 Hillsborough River, Fla. (SAJ) 9-39 Hillsdale Lake, Kans. (MRK) 20-3, 20-11, 20-15, 20-21 Hillview Drainage and Levee District, Ill. (LMS) 14-4, 14-9, 14-11 Hilo Harbor, Hawaii (POD) 36-10 Hingham Harbor, Mass. (NED) 1-37 Hivwassee River, Tenn. (ORN) 23-13 Hockingport, Ohio (ORH) 25-21 Hodges Dam, Calif. (SPL) 33-27 Hodges Village Dam, Mass. (NED) 1-21, 1-31, 1-51 Hoh River, Wash. (NPS) 38-26 Hoko River, Wash. (NPS) 38-26 Holbrook Levee, Ariz. (SPL) 33-11, 33-25 Holland Harbor, Mich. (NCE) 31-12, 31-43, 31-61 Holley Lake, Oreg. (NPP) 37-48, 37-55 Holly, Colo. (SWA) 17-3, 17-8, 17-10 Hollywood-Ardmore Beach along Lake Michigan, Ill. (NCC) 30-14 Holmes Bay, Whiting, Maine (NED) 1-42 Holmes Creek, Fla. (SAM) 10-42 Holston River, Tenn. (ORN) 23-13 Holyoke, Mass. (NED) 1-22, 1-42, 1-48 Homer Harbor, Alaska (NPA) 40-2, 40-8, 40-10 Hominy Swamp, N.C. (SAW) 6-28 Homme Lake and Dam, N. Dak. (NCS) 27-7, 27-20 Homochitto River, Miss. (LMK) 12-21, 12-25 Homosassa River, Fla. (SAJ) 9-46, 9-47 Honey Creek Levee, Ind. (ORL) 24-22, 24-25 Honey Hill Lake, N.H. (NED) 1-44 Honga River and Tar Bay, Md. (NAB) 4-5, 4-22, 4-29 Honokohau Small Boat Harbor, Hawaii (POD) 36-10 Honolulu Harbor, Hawaii (POD) 36-2, 36-6, 36-8 Hood Canal, Wash. (NPS) 38-26 Hoonah Harbor, Alaska (NPA) 40-12 Hooper, Nebr. (MRO) 21-17, 21-20 Hoosic Falls, Hoosic River Basin, N.Y. (NAN) 2-32 Hop Brook Lake, Conn. (NED) 1-16, 1-29, 1-49 Hopkinton-Everett Lakes, N.H. (NED) 1-19, 1-30, 1-50 Hoquiam River, Wash. (NPS) 38-24, 38-26, 38-30 Hords Creek Lake, Tex. (SWF) 16-7, 16-15, 16-19 Horn Harbor, Va. (NAO) 5-22 Hornell, N.Y. (NAB) 4-16, 4-26 Horseshoe Cove, Fla. (SAJ) 9-46, 9-47 Hoskins Creek, Va. (NAO) 5-4, 5-14, 5-18, 5-22 Hot Springs, S. Dak. (MRO) 21-20 Houlka Creek, Miss. (SAM) 10-43 Houma Navigation Canal, La. (LMN) 11-20 Housatonic River, Conn. (NED) 1-37, 1-44 Housatonic River, Pittsfield, Mass. (NED) 1-17, 1-29, 1-35 Housatonic River, Salisbury, Conn. (NED) 1-42 Housatonic River, Sheffield, Mass. (NED) 1-42 Housatonic River Basin, Conn. (NED) 1-16, 1-22, 1-48 Houston Ship Channel, Tex. (SWG) 15-5, 15-13, 15-20, 15-27, 15-29, 15-33 Howard A. Hanson Dam, Wash. (NAS) 38-7, 38-15, 38-21 Howards Mill Lake, N.C. (SAW) 6-27 Hudson River, Fla. (SAJ) 9-47 Hudson River, N.Y. (NAN) 2-5, 2-19, 2-24, 2-28, 2-34 Hudson River Channel, N.Y. (NAN) 2-30 Hugo Lake, Okla. (SWT) 19-4, 19-10, 19-13 Hulah Lake, Okla. (SWT) 19-4, 19-10, 19-13 Humboldt, Tenn. (LMM) 13-2, 13-4, 13-5 Humboldt Bay, Calif. (SPN) 34-7 Humboldt Harbor, Alaska (NPA) 40-12 Humboldt Harbor and Bay, Calif. (SPN) 34-4 Humboldt River and Tributaries, Nev. (SPK) 35-29 Hunt Drainage District and Lima Lake Drainage District, Ill. (NCR) 28-14, 28-17 Hunting Island Beach, S.C. (SAN) 7-15 Huntingdon, Tenn. (LMM) 13-7 Huntington, Mass. (NED) 1-22, 1-42, 1-48 Huntington, W. Va. (ORH) 25-20, 25-22 Huntington Avenue, Castle Rock, Wash. (NPP) 37-15, 37-31, 37-41 Huntington Harbor, N.Y. (NAN) 2-34 I-23 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Huntington Lake, Ind. (ORL) 24-8, 24-15 Huot, Minn. (NCS) 27-28 Huron Harbor, Ohio (NCB) 32-6, 32-18, 32-29 Hurricane Barrier Operations, New England Division (NED) 1-23 Hutchins, Ky. (ORH) 25-22 Hutchinson Levee and Channel, Kans. (SWT) 19-15, 19-16 Hyannis Harbor, Mass. (NED) 1-5, 1-25, 1-33 Hyde County Dike, N.C. (SAW) 6-28 Hydraulics and Hydrology of the Great Lakes 31-37 Hydrologic Engineering Center 53-3 I lao Stream, Hawaii (POD) 36-3, 36-7, 36-9 Ice Harbor at Marcus Hook, Pa. (NAP) 3-21 Ice Harbor at New Castle, Del. (NAP) 3-21 Ice Harbor Lock and Dam-Lake Sacajawea, Wash. (NPW) 39-5, 39-10, 39-14, 39-20, 39-24 Ida Grove, Iowa (MRO) 21-17, 21-21 Iliuliuk Harbor, Alaska (NPA) 40-12 Illinois and Mississippi Canal, Ill. (NCR) 28-2, 28-8 Illinois River, Ill. (MR+T) 42-19 Illinois Waterway, Ill. and Ind. (NCR) 28-3, 28-8, 28-10, 28-16, 28-20, 28-21, 28-22 Imperial Beach, Calif. (SPL) 33-4, 33-14, 33-20 Indian Bend Wash, Ariz. (SPL) 33-5, 33-14, 33-21 Indian Creek Area, Ill. (LMS) 14-14 Indian Creek, Corydon, Ind. (ORL) 24-20, 24-30 Indian Creek Lake, Emerson, Iowa (MRO) 21-4, 21-10, 21-13, 21-18 Indian Grave Drainage District, Ill. (NCR) 28-14, 28-17 Indian Island, Maine (NED) 1-22 Indian Lake, Kans. (MRK) 20-19 Indian River Inlet and Bay, Del. (NAP) 3-4, 3-15, 3-19 Indiana Dunes National Lakeshore Emergency Stone Repairs, Beverly Shores, Ind. (NCC) 30-6, 30-8, 30-12 Indiana Harbor, Ind. (NCC) 30-4, 30-8, 30-11, 30-13, 30-14 Indianapolis, Ind. (ORL) 24-21, 24-30 Indianapolis, Ind. (Fall Creek Section) (ORL) 24-20 Indianola, Nebr. (MRK) 20-19, 20-21 Industry, Pa. (ORP) 26-23 Inez, Ky. (ORH) 25-22 Inland Route, Mich. (NCE) 31-13, 31-43, 31-61 Inland Waterway from Chincoteague Bay, Va., to Delaware Bay, Del. (NAP) 3-21 Inland Waterway from Delaware River to Chesapeake Bay, Del. and Md. (NAP) 3-5, 3-15, 3-19 Inland Waterway from Franklin to Mermentau River, La. (LMN) 11-20 Inland Waterway from the Mississippi River to Bayou Teche, La. (LMN) 11-20 Inland Waterway, Rehoboth Bay to Delaware Bay, Del. (NAP) 3-5, 3-15, 3-19 Institute for Water Resources 53-5 Intercounty D. D., Little Sioux River, Iowa (MRO) 21-21 International Boundary Waters Boards, 49-1 International Champlain-Richelieu Board 49-1 International Great Lakes Diversions and Consumptive Uses Study Board 31-36, 49-1 International Great Lakes Technical Information Network Board 31-36, 49-2 International Joint Commission Board of Control (IJC) 49-1 International Kootenay Lake Board of Control 49-1 International Lake Champlain Board of Control 49-1 International Lake Erie Regulation Study Board 31-36, 49-2 International International Board 49-1 International 31-36, 49-1 International 31-36, 49-1 International International 31-36 International 49-1 Lake Memphremagog Board 49-2 Lake of the Woods Control Lake Superior Board of Control Niagara Board of Control, Niagara Committee 49-2 Niagara Working Committee Osoyoos Lake Board of Control International Rainy Lake Board of Control 49-1 International Skagit River Board of Contrql 49-1 International Souris-Red Rivers Engineering Board, 49-1 International St. Croix River Board of Control 49-1 International St. Lawrence River Board of Control 31-36, 49-1 I-24 1 INDEX Interstate Bridge, Portland, Oreg. (NPP) 37-45 Interstate Highway Bridge (Barge Channel), Oreg. (NPP) 37-45 Interstate 20 Bridges, Jackson, Miss. (SAM) 10-17, 10-29, 10-40 Interstate 59 Bridges, Fosters, Ala. (SAM) 10-17, 10-29, 10-40 Intracoastal Waterway, Caloosahatchee River to Anclote River, Fla. (SAJ) 9-6, 9-27, 9-34 Intracoastal Waterway, Jacksonville to Miami, Fla. (SAJ) 9-7, 9-27, 9-34, 9-46 Intracoastal Waterway, Miami to Key West, Fla. (SAJ) 9-46, 9-47 Intracoastal Waterway, Mississippi River to Bayou Teche, La. (LMN) 11-20 Investigations of Projects Under the Federal Power Act 47-1 Iola Levee, Kans. (SWT) 19-15, 19-16 Iowa River-Flint Creek Levee District No. 16, Iowa (NCR) 28-14, 28-17 Ipswich Harbor, Mass. (NED) 1-38 Irondequoit Bay, N.Y. (NCB) 32-7, 32-19 Ironton, Ohio (ORH) 25-20, 25-22 Irving Township, Jackson Co., Wis. (NCS) 27-7, 27-20, 27-24, 27-28 Irvington Harbor, N.Y. (NAN) 2-34 Isabella Lake, Kern River, Calif. (SPK) 35-7, 35-21 Island Avenue, Quincy, Mass. (NED) 1-22, 1-42 Island Creek, Md. (NAB) 4-34 Island Creek, St. Georges Island, Md. (NAB) 4-34, 4-38 Island End River, Chelsea, Mass. (NED) 1-38 Island Levee, Ind. (ORL) 24-21, 24-24 Isle Au Haut Thoroughfare, Maine (NED) 1-38 Isle of Shoals Harbor, Maine and N.H. (NED) 1-38 Islesboro (The Narrows), Maine (NED) 1-18, 1-22, 1-29, 1-36 Israel R., Lancaster, N.H. (NED) 1-48 Ithaca, N.Y., Cascadilla Creek (NCB) 32-39 Ithaca, N.Y., Cayuga Inlet (NCB) 32-37 Ithaca, N.Y., Fall Creek (NCB) 32-39 J J. Percy Priest Dam and Reservoir, Ohio River Basin, Tenn. (ORN) 23-7, 23-9, 23-18 Jackson, Ky. (ORL) 24-20, 24-24, 24-30 Jackson and East Jackson, Miss. (SAM) 10-43 Jackson Creek, Va. (NAO) 5-22 Jackson Hole, Wyo. (NPW) 39-16, 39-19 Jacksonburg, Fishing Creek, W.Va. (ORH) 25-22 Jacksonville Harbor, Fla. (SAJ) 9-7, 9-27, 9-35 Jadvin, General Edgar, Dam and Reservoir, Pa. (NAP) 3-13, 3-17 Jamaica Bay, N.Y. (NAN) 2-6, 2-19, 2-24, 2-30 James River, Va. (NAO) 5-5, 5-14, 5-18 Jamestown Reservoir, N. Dak. (MRO) 21-17 Janesville and Indian Ford Dams, Wis. (NCR) 28-16 Jarvis Creek, Va. (NAO) 5-22 Jefferson River, Bank Protection, near Waterloo, Mont. (MRO) 21-19 Jefferson River, Willow Creek Bridge, near Three Forks, Mont. (MRO) 21-19 Jeffersonville-Clarksville, Ind. (0RL) 24-20, 24-24, 24-29 Jemez Canyon Dam, N. Mex. (SWA) 17-5, 17-9, 17-11 Jenkins, Tom, Dam, Ohio (ORH) 25-15, 25-18 Jenkins, Tom, Reservoir, Ohio (ORH) 25-10 Jenks Levee, Okla. (SWT) 19-15, 19-16 Jennings Beach, Fairfield, Conn. (NED) 1-41 Jeremy Creek, S.C. (SAN) 7-5, 7-9, 7-12 Jim Woodruff Lock and Dam, Ga. and Fla. (SAM) 10-23, 10-30, 10-41 JOBS ACT CONTRACTS AWARDED Albuquerque, New Mex., District (SWA) 17-12 Fort Worth, Tex., District (SWF) 16-23 Galveston, Tex., District (SWG) 15-35 Little Rock, Ark., District (SWL) 18-25 Tulsa, Okla., District (SVT) 19-21 Joe Creek Channel Improvement, Okla. (SWT) 19-16 Joe Pool Lake (Lakeville Lake), Tex. (SWF) 16-7, 16-15, 16-19 John Day Lock and Dam-Lake Umatilla, Oreg. and Wash. (NPP) 37-23, 37-32, 37-43, 37-57 John Day River, Oreg. (NPP) 37-16, 37-31, 37-41, 37-46, 37-50 John Drainage District, Oreg. (NPP) 37-50, 37-54 John H. Kerr Dam and Reservoir, Va. and N.C. (SAW) 6-14, 6-16, 6-20 John Martin Reservoir, Colo. (SWA) 17-3, 17-9 John Redmond Dam and Reservoir, Kans. (SVT) 19-4, 19-10, 19-13 John W. Flannagan Dam and Reservoir, Va. (ORH) 25-6, 25-13, 25-17 Johns Pass, Fla. (SAJ) 9-8, 9-27, 9-35, 9-46 I-25 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Johnson Bay, Lubec, Maine (NED) 1-18, 1-29, 1-36 Johnson Bayou, La. (SWG) 15-26 Johnson Creek, Vicinity of Portland, Oreg. (NPP) 37-48, 37-55 Johnsonburg, Pa. (ORP) 26-22, 26-26, 26-28 Johnstown, Pa. (ORP) 26-4, 26-13, 26-18, 26-26 Jones Inlet, N.Y. (NAN) 2-6, 2-19, 2-24, 2-29 Jonesport Harbor, Maine (NED) 1-5, 1-25, 1-33 Jordan, B. Everett, Dam and Lake, N.C. (SAW) 6-10, 6-15, 6-20 Josias River, Maine (NED) 1-38 Joyce Creek, Camden County, N.C. (SAW) 6-27 Julian, Nebr. (MRO) 21-20 Juneau Harbor, Alaska (NPA) 40-12, 40-14 K Kaaawa Beach, Hawaii (POD) 36-11 Kahoma Stream, Hawaii (POD) 36-3, 36-7, 36-9 Kahului Beach Road, Hawaii (POD) 36-10 Kahului Harbor, Hawaii (POD) 36-10 Kailua Small Boat Harbor, Hawaii (POD) 36-10 Kaimu Black Sand Beach, Hawaii (POD) 36-12 Kake Harbor, Alaska (NPA) 40-3, 40-8, 40-10 Kalama River (South Area) Levee, Wash. (NPP) 37-50, 37-54 Kalamazoo River (Battle Creek), Mich. (NCE) 31-78 Kalamazoo River (Kalamazoo), Mich. (NCE) 31-78 Kalaupapa Harbor, Hawaii (POD) 36-10 Kanawha River, W. Va. (ORH) 25-2, 25-12, 25-16 Kaneohe-Kailua Area, Hawaii (POD) 36-4, 36-7, 36-9 Kankakee River, Ill. and Ind. (NCC) 30-14 Kanopolis Lake, Kans. (HRK) 20-3, 20-11, 20-15, 20-21 Kansas City, Kans. (1962 Mod.) (HRK) 20-19 Kansas Citys on Mo. and Kansas Rivers, Mo. and Kans. (MRK) 20-19 Kansas River and Minor Tributaries (MRK) 20-22 Kansas River Navigation, Kans. (MRK) 20-18, 20-18 Kapaa Town, Hawaii (POD) 36-11 Kapaakea Homestead Flood Control, Hawaii (POD) 36-12 Karlson Islnd, Oreg. (NPP) 37-46 Kasilof Harbor, Alaska (NPA) 40-12 Kaskaskia Island Drainage and Levee District, Ill. (LMS) 14-4, 14-9, 14-11, 14-14 Kaskaskia River, Ill. (LMS) 14-2, 14-9, 14-11 Kaukauna Dam, Wis. (NCE) 31-75 Kaukauna Fifth Lock, Wis. (NCE) 31-75 Kaukauna First Lock, Wis. (NCE) 31-75 Kaukauna Fourth Lock, Wis. (NCE) 31-75 Kaukauna Guard Lock, Wis. (NCE) 31-75 Kaukauna Second Lock, Wis. (NCE) 31-75 Kaukauna Third Lock, Wis. (NCE) 31-75 Kaulana Bay Boat Harbor, Hawaii (POD) 36-2, 36-6 Kaunakakai Harbor, Hawaii (POD) 36-10 Kaunakakai Stream, Hawaii (POD) 36-12 Kay Lake, Okla. (SVT) 19-5, 19-10, 19-13 Kawaihae Harbor, Hawaii (POD) 36-10 Kawainui Swamp, Hawaii (POD) 36-12 Kaweah and Tule Rivers, including Terminus Dam and Success Lake, Calif. (SPK) 35-8, 35-22 Kawkawlin River, Mich. (NCE) 31-32, 31-53, 31-72 Kays Creek, Utah (SPK) 35-29 Keach Drainage and Levee District, Ill. (LMS) 14-14 Keehi Lagoon, Hawaii (POD) 36-10 Keene, N.H. (NED) 1-22, 1-42, 1148 Kehoe Lake, Ky. (ORH) 25-20 Keithsburg Drainage District, Ill. (NCR) 28-16 Kekaha Beach, Hawaii (POD) 36-11 Kelleys Island, Ohio (NCB) 32-35 Kendrick, Idaho (NPW) 39-16, 39-19 Kenmore Navigation Channel, Wash. (NPS) 38-24, 38-30 Kennebec River, Maine (NED) 1-38 Kennebunk River, Maine (NED) 1-6, 1-25, 1-3 Kenosha Harbor, Wis. (NCE) 31-13, 31-43, 31-61 Kentucky Lock and Dam, Ky. (ORN) 23-17 Kentucky River, Ky. (ORL) 24-2, 24-14, 24-23, 24-27 Keokuk Harbor, Iowa (NCD) 29-8 Kern River-California Aqueduct Intertie, Calif. (SPK) 35-29 Kerr, John H., Dam and Reservoir, Va. and N.C. (SAW) 6-14, 6-16, 6-20 Kerr, Robert S., Lock and Dam, Okla. (SWL) (SWT) 18-19, 19-7, 19-12, 19-14, 19-16 Kerr, Robert S., Marine Terminal, Sallisaw, Okla. (SWT) 19-16 I-26 INDEX Kerton Valley Drainage and Levee District, Ill. (NCC) 28-17 Ketchikan Harbor, Alaska (NPA) 40-12, 40-13 Kevalo Harbor, Havaii (POD) 36-12 Kevaunee Harbor, Wis. (NCE) 31-13, 31-43, 31-62 Kewaunee River, Wis. (NCE) 31-79 Keveenav Watervay, Mich. (NCE) 31-14, 31-44, 31-62 Key West, Fla. (SAJ) 9-48 Key West Harbor, Fla. (SAJ) 9-46, 9-47 Keyport Harbor, N.J. (NAN) 2-7, 2-19, 2-24 Keystone Lake, Okla. (SWL) (SWT) 18-21, 19-7, 19-12, 19-14, 19-16 Kihei Beach, Hawaii (POD) 36-11 Kikiaola Small Boat Harbor, Hawail (POD) 36-10 Kindred Lake, N.D. (NCS) 27-15, 27-21 King Cove Harbor, Alaska (NPA) 40-3, 40-8, 40-10 Kings Creek, Va. (NAO) 5-22 Kingston-Edwardsville, Pa. (NAB) 4-36, 4-39 Kingston Harbor, Wash. (NPS) 38-24 Kingston Harbor (North Plymouth), Mass. (NED) 1-38 Kingstree Branch, S.C. (SAN) 7-8, 7-16 Kinzua Dam and Allegheny Reservoir, Pa. and N.Y. (ORP) 26-7, 26-14, 26-18 Kirwan, Michael J., Dam and Reservoir, Ohio (ORP) 26-8, 26-14, 26-19 Kishvaukee River at De Kalb, Ill. (NCR) 28-14 Kissimmee River, Fla. (SAJ) 9-47 Kittanning, Pa. (ORP) 26-28 Kittanning, Pa. Part I (ORP) 26-22, 26-26 Kittanning, Pa. Part II (ORP) 26-23 Kitzmiller, Md. (NAB) 4-36, 4-39 Klamath River, Calif. (SPK) (SPN) 35-29 Klutina River, Copper Center, Alaska (NPA) 40-13 Knappa Area, Oreg. (NPP) 37-46 Knapps Narrows, Md. (NAB) 4-5, 4-22, 4-29 Knife River Harbor, Minn. (NCE) 31-14, 31-44, 31-62 Knights Valley Lake, Calif. (SPN) 34-8 Knightville Dam, Mass. (NED) 1-13, 1-28, 1-47 Knobb's Creek, N.C. (SAW) 6-25 Kodiak Harbor, Alaska (NPA) 40-12 Kootenal River, Idaho and Mont. (NPS) 38-24, 38-26 Kualoa Regional Park, Hawaii (POD) 36-11 Kuliouou Stream, Hawaii (POD) 36-12 Kuskokwim River, Betheg, Alaska (NPA) 40-5, 40-9, 40-11 L L'Anguille Basin, Ark. (MR+T) 42-28 L'Anguille River, Ark. (MR+T) 42-18 La Conner, Wash. (NPS) 38-26 La Crosse, Wis. (NCS) 27-24 La Farge Lake and Channel Improvement, Wis. (NCS) 27-8, 27-20 La Grange Bayou, Fla. (SAM) 10-42 La Grange Lock and Dam, Ill. (NCC) 28-20 La Pointe Harbor, Wis. (NCE) 31-15, 31-44, 31-62 La Trappe, Md. (NAB) 4-34 Lac La Belle Harbor, Mich. (NCE) 31-15, 31-44, 31-63 Lac Qui Parle Lake, Minnesota River, Minn. (NCS) 27-8, 27-20 Lacey Drainage and Levee District, Ill. (NCC) 28-17 Lacey, Langellier, West Mantanzas and Kerton Valley Drainage and Levee District, Ill. (NCR) 28-14 Lackawanna, N.Y. (NCB) 32-37 Lackawanna River Basin, Pa. (NAB) 4-13, 4-32 Lafayette Lake, Ind. (ORL) 24-21 Lafayette River, Va. (NAO) 5-22 Lago De Cerrillos, P.R. (SAJ) 9-42 Lago De Portugues, P.R. (SAJ) 9-42 Lagoon Pond, Martha's Vineyard, Mass. (NED) 1-38 Lahaina Small Boat Harbor, Hawaii (POD) 36-10 Lake Ashtabula and Baldhill Dam, Sheyenne River, N. Dak. (NCS) 27-8, 27-20 Lake Borgne and Chef Menteur-Bulkheads and Jetties (LMN) 11-20 Lake Brownwood Modification, Tex. (SWF) 16-21 Lake Bryan, Wash. (NPW) 39-6 Lake Camanche, Calif. (SPK) 35-29 Lake Celilo, Wash. and Oreg. (NPP) 37-25, 37-33, 37-44, 37-57 Lake City, Tenn. (ORN) 23-19 Lake Champlain Narrows, N.Y. and Vt. (NAN) 2-8, 2-20, 2-24 Lake Charles Deep Water Channel, La. (LMN) 11-20 Lake Chautauqua and Chadakoin River, N.Y. (ORP) 26-23 Lake City Harbor, Minn. (NCD) 29-7 Lake Crescent and Dunns Creek, Fla. (SAJ) 9-47 Lake Crockett, Wash. (NPS) 38-24 Lake Darling, N. Dak. (NCS) 27-9, 27-20 Lake Douglas, Ga. (SAM) 10-43 I-27 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Lake Erie-Ohio Canal, Ohio and Pa. (ORP) 26-23 Lake Fork Lake, Sabine River, Tex. (SWF) 16-21 Lake Francis Case, S. Dak. (MRO) 21-7, 21-12 Lake Georgetown, Tex. (SWF) 16-16 Lake Greeson, Ark. (LMK) 12-8, 12-14, 12-17 Lake Herbert G. West, Wash. (NPW) 39-7 Lake Hudson, Okla. (SWT) 19-16 Lake Kemp, Tex. (SWT) 19-5, 19-10, 19-13 Lake Meredith, Okla. (SWT) 19-18 Lake Michigan-Lake Bluff, Ill. (NCC) 30-14 Lake Michigan-Lake Forest, Ill. (NCC) 30-14 Lake Montauk Harbor, N.Y. (NAN) 2-30 Lake Neatahwanta, Fulton, N.Y. (NCB) 32-12 Lake Ocklawaha, Fla. (SAJ) 9-5 Lake Ogleton, Md. (NAB) 4-37 Lake Oroville, Calif. (SPK) 35-29 Lake Ouachita (Blakely Mountain Dam), Ark. (LMK) 12-7, 12-14, 12-17 Lake Pontchartrain, La. (MR+T) 42-15, 42-56 Lake Pontchartrain, La. Project Levees (MR+T) 42-45, 42-49 Lake Pontchartrain and Vicinity, La., (Hurricane Protection) (LMN) 11-9, 11-14, 11-16 Lake Providence Harbor, La. (LMK) 12-2, 12-13, 12-16 Lake River, Wash. (NPP) 37-45 Lake River Delta Area, Wash. (NPP) 37-50, 37-54 Lake Rousseau, Fla. (SAJ) 9-5 Lake Sacajawea, Wash. (NPW) 39-5 Lake Sakakawea, N. Dak. (MRO) 21-8, 21-12 Lake Sharpe, S. Dak (MRO) 21-7, 21-12 Lake Shelbyville, Ill. (LMS) 14-14 Lake Sidney Lanier, Ga. (SAM) 10-30, 10-41 Lake St. Clair, Mich., Channels (NCE) 31-15, 31-44, 31-63 Lake Texoma, Tex. and Okla. (SWT) 19-7, 19-12, 19-14. Lake Thunderbird, Okla. (SWT) 19-18 Lake Traverse, Minn. and S. Dak. (NCS) 27-23 Lake Traverse and Boise De Sioux River, S. Dak. and Minn. (NCS) 27-9, 27-20 Lake Umatilla, Oreg. and Wash. (NPP) 37-23, 37-32, 37-43, 37-57 Lake Wallula, Wash. (NPW) 39-8, 39-10 Lake Washington Ship Canal, Wash. (NPS) 38-4, 38-14, 38-19, 38-30 Lakeport Lake, Calif. (SPK) 35-29 Lakeshore Park, Ashtabula, Ohio (NCB) 32-13, 32-21 Lakeview Lake, Tex. (SWF) 16-7, 16-15, 16-19 Lakeviev Park, Lorain, Ohio (NCB) 32-12, 32-21 Lamoille River, Vt. (NAN) 2-32, 2-34 Lamprey River, N.H. (NED) 1-38 Lancaster, Mass. (NED) 1-22 Lancaster, N.H. (NED) 1-42 Lancaster, N.Y. (NCB) 32-37 Langdon Park, Wilmette, Ill. (NCC) 30-6 Langellier Drainage and Levee District, Ill. (NCC) 28-17 Lansing (Grand River), Mich. (NCE) 31-79 Lansing Harbor, Iowa (NCD) 29-7 Lapwai Creek, Culdesac, Idaho (NPW) 39-16 Larchmont Harbor, N.Y. (NAN) 2-30 Largo Sound Channel, Fla. (SAJ) 9-47 Larned, Kans. (SWT) 19-16 Larose to Golden Meadow, La. (Hurricane Protection) (LMN) 11-10, 11-14, 11-17 Las Animas, Colo. (SWA) 17-11 Las Cruces, N. Mex. (SWA) 17-11 Las Tunas Beach, Calif. (SPL) 33-24 Las Vegas Wash Tributaries, Nev. (SPL) 33-27 Latrobe, Pa. (ORP) 26-22, 26-26, 26-28 Latta Brook Road, N.Y. (NAB) 4-36 Laurel River Lake, Ohio River Basin, Ky. (ORN) 23-7, 23-9, 23-18 Lava Hot Springs, Idaho (NPW) 39-16 Lavaca-Navidad River, Tex. (SWG) 15-26 Lavon Lake, Tex. (SWF) 16-7, 16-15, 16-19 Lavon Lake Modification and East Fork Channel Improvement, Tex. (SWF) 16-7, 16-15, 16-19 Lawrence, Kans. (MRK) 20-3, 20-12, 20-15, 20-21 Lawrenceburg, Ind. (ORL) 24-20, 24-24, 24-29 Lead Bayou, Miss. (LMK) 12-8, 12-14, 12-17 Leading Creek, V. Va. (ORH) 25-20 Leaf and Chickasawhay River, Miss. (SAM) 10-42 Leavenworth, Ind. (ORL) 24-22, 24-25 Lebanon Junction, Ky. (ORL) 24-20, 24-29 Le Claire Lock (Canal), Iowa (NCD) 29-5 Lee, Mass. (NED) 1-22, 1-42 Lee County, Fla. (SAJ) 9-48 Leech Lake Reservoir, Minn. (NCS) 27-26 Leesville, Va., Roanoke River, Sec. 32, Demo. Project (SAW) 6-12, 6-20 Leetonia, Ohio (ORP) 26-22 Leetsdale, Pa. (ORP) 26-22, 26-26 Lehigh River at Allentown, Pa. (NAP) 3-13 Lehigh River at Bethlehem, Pa. (NAP) 3-13 Leipsic River, Del. (NAP) 3-21 Leith's Creek, N.C. (SAW) 6-27 Leith's Creek, S.C. (SAN) 7-16 1-28 INDEX Leland Bowman Lock, La. (formerly Vermilion Lock) (LMN) 11-4, 11-13, 11-15 Leland Harbor, Mich. (NCE) 31-16, 31-44, 31-63 Lemon Creek, N.Y. (NAN) 2-30 Les Cheneaux Islands, Channels, Mich. (NCE) 31-77 Letart, W. Va. (ORB) 25-21 Letart Falls, Ohio (ORB) 25-21 Levee Districts between Carlyle and New Athens, Ill. (LMS) 14-14 Levee Districts between Cowden and Vandalia, Ill. (LMS) 14-14 Levee Unit No. 1, Ill. (ORL) 24-21 Levee Unit No. 5, Ind. (ORL) 24-4, 24-14, 24-29 Levee Unit No. 8, Ind. (ORL) 24-20, 24-29 Levees (LMK) (LMS) (MR+T) (ORL) 42-4, 42-10, 42-28, 42-44, 42-46, 42-47, 42-54, 42-55, 42-57, 14-14, 24-22, 24-25 Levels of the Great Lakes 31-37 Levisa and Tug Forks of the Big Sandy River and Cumberland River, W. Va., Va., and Ky. (ORB) 25-6, 25-13, 25-17 Lewis and Clark Lake, Nebr. and S. Dak. (MRO) 21-8, 21-12, 21-16 Lewis and Clark River Area, Oreg. (NPP) 37-46 Lewis River, Wash. (NPP) 37-7, 37-28, 37-38 Lewis River Area, Wash. (NPP) 37-50, 37-54 Lewisport, Ky. (ORL) 24-21, 24-24 Leviston-Clarkston Bridge, Idaho and Wash. (NPW) 39-6, 39-11, 39-14 Lewisville Dam, Tex. (SW) 16-8, 16-15, 16-19 Lexington Harbor, Mich. (NCE) 31-16, 31-45, 31-63 Libby Dam-Lake Koocanusa, Mont. (NAS) 38-10, 38-16, 38-22 Liberty Local Protection Project, Tex. (SWG) 15-26 Liberty State Park Levee and Seawall, N.J. (NAN) 2-16, 2-21, 2-26 Lick Run, Roanoke, Va. (SAW) 6-27 Licking River, Ky. (ORL) 24-19, 24-30 Lido Key, Fla. (SAJ) 9-48 Lighthouse Point Park, Conn. (NED) 1-41 Lincoln, N.H. (NED) 1-22 Lincoln, Nebr. (MRO) 21-20 Lincoln Lake, Ind. (ORL) 24-22 Lincoln School Lake, Me. (NED) 1-42 Link Ross Location, Boise River, Idaho (NPW) 39-19 Linton, N. Dak. (MRO) 21-17 Lisle, N.Y. (NAB) 4-16, 4-26 Little Bay, Tex. (SWG) 15-26 Little Bay De Noc, Gladstone Harbor, Mich. (NCE) 31-77 Little Blue River Channel Improvement, Mo. (MRK) 20-4, 20-12, 20-15 Little Blue River Lakes, Mo. (MRK) 20-4, 20-12, 20-15 Little Caillou Bayou, La. (LMN) 11-20 Little Calumet River, Ill. (NCC) 30-14 Little Chute Combined Lock, Wis. (NCE) 31-75 Little Chute Dam, Wis. (NCE) 31-75 Little Chute First (Guard) Lock, Wis. (NCE) 31-75 Little Chute Second Lock, Wis. (NCE) 31-75 Little Cove Creek, Glencoe, Ala. (SAM) 10-43 Little Creek, Kent Island, Md. (NAB) 4-34 Little Dell Lake, Utah (SPK) 35-19, 35-25 Little Egg Harbor, N.J. (NAP) 3-21 Little Goose Lock and Dam-Lake Bryan, Wash. (NPW) 39-6, 39-11, 39-14, 39-21, 39-24 Little Harbor, N.H. (NED) 1-38 Little Harbor, Woods Hole, Mass. (NED) 1-38 Little Kanawha River, W. Va. (ORH) 25-19 Little Kaukauna Lock and Dam, Wis. (NCE) 31-75 Little Lake Harbor, Mich. (NCE) 31-16, 31-45, 31-63 Little Machipongo River, Va. (NA0) 5-5, 5-14, 5-18 Little Manatee River, Fla. (SAJ) 9-47 Little Missouri River, Ark. (LMK) 12-21, 12-22 Little Little Little Little S.C. Little Little Little Neck Bay, N.Y. (NAN) 2-30 Nemaha River, Nebr. (MRO) 21-17 Papillion, Nebr. (MRO) 21-17, 21-20 Pee Dee and Pee Dee Rivers, N.C. and (SAN) 7-17 River, Del. (NAP) 3-21 River, La. (LMK) 12-21 River at Cayuga Island, N.Y. (NCB) 32-12, 32-35 Little River Basin (Little Rock District) (SWL) 18-4, 18-10, 18-22 Little River (Creek), Va. (NAO) 5-22 Little River Dike, Westfield, Mass. (NED) 1-42 Little River Diversion Channel, Mo. (MR+T) 42-19 Little River Inlet, N.C. and S.C. (SAN) 7-5, 7-9, 7-13 Little River Project Levees (MR+T) 42-48, 42-49 Little Rock Levee, Ark. (East End Fourche Bayou) (SWL) 18-14, 18-16 I-29 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Little Rockfish Creek, Hope Mills, N.C. (SAW) 6-27 Little Salmon River, Idaho (NPW) 39-19 Little Sioux River and Tributaries, Iowa (MRO) 21-4, 21-10, 21-13 Little Sodus Bay Harbor, N.Y. (NCB) 32-7, 32-19, 32-29 Little Sugar Creek, Charlotte, N.C. (SAW) 6-27 Little Tallahatchie River, Miss. (LMK) 12-21 Little Tennessee River, Tenn. (ORN) 23-13 Little Valley Wash, Magna, Utah (SPK) 35-31 Little Wicomico River, Va. (NAB) 4-6, 4-22, 4-29 Little Wood River, Idaho (NPW) 39-18, 39-19 Littleville Lake, Mass. (NED) 1-13, 1-28, 1-47 Liverpool Drainage and Levee District, Ill. (NCR) 28-14, 28-17 Lloyd Park, Winnetka, Ill. (NCC) 30-6 Lock and Dam No. 1, Minn. (NCD) 29-5, 29-9 Lock and Dam No. 2, Allegheny River, Pa. (ORP) 26-24 Lock and Dam No. 2, Ark. (SWL) 18-3, 18-18 Lock and Dam No. 2, Minn. (NCD) 29-5 Lock and Dam No. 2, Monongahela River, Pa. (ORP) 26-25 Lock and Dam No. 3, Allegheny River, Pa. (ORP) 26-24 Lock and Dam No. 3, Ark. (SWL) 18-3, 18-18 Lock and Dam No. 3, Minn. (NCD) 29-5 Lock and Dam No. 3, Monongahela River, Pa. (ORP) 26-25 Lock and Dam No. 4, Allegheny River, Pa. (ORP) 26-24 Lock and Dam No. 4, Ark. (SWL) 18-3, 18-18 Lock and Dam No. 4, Monongahela River, Pa. (ORP) 26-25 Lock and Dam No. 4, Wis. (NCD) 29-5 Lock and Dam No. 5, Allegheny River, Pa. (ORP) 26-24 Lock and Dam No. 5, Ark. (SWL) 18-3, 18-18 Lock and Dam No. 5, Minn. (NCD) 29-5 Lock and Dam No. 5A, Minn. (NCD) 29-5 Lock and Dam No. 6, Allegheny River, Pa. (ORP) 26-24 Lock and Dam No. 6, Wis. (NCD) 29-5 Lock and Dam No. 7, Allegheny River, Pa. (ORP) 26-24 Lock and Dam No. 7, Minn. (NCD) 29-5 Lock and DamNo. 7, Monongahela River, Pa. (ORP) 26-25 Lock and Dam No. 8, Allegheny River, Pa. (ORP) 26-24 Lock and Dam No. 8, Monongahel Pa. (ORP) 26-25 Lock and Dam No. 8, Wis. (NCD) Lock and Dam No. 9, Allegheny I Pa. (0RP) 26-24 Lock and Dam No. 9, Ark. (SWL) Lock and Dam No. 9, Wis. (NCD) Lock and Dam No. 10, Iowa (NCD Lock and Dam No. 11, Ark. (SWL Lock and Dam No. 11, Iowa (NCD Lock and Dam No. 12, Iowa (NCD Lock and Dam No. 13, Ark. (SWL 18-19, 19-16 Lock and Dam No. 13, Iowa (NCD Lock and Dam No. 14, Iowa (NCD Lock and Dam No. 15, Ill. (NCD Lock and Dam No. 16, Iowa (NCD Lock and Dam No. 17, Ill. (NCD Lock and Dam No. 18, Iowa (NCD Lock and Dam No. 19, Iowa (NCD Lock and Dam No. 20, Mo. (NCD) Lock and Dam No. 21, Ill. (NCD Lock and Dam No. 22, Mo. (NCD) Lock and Dam No. 24, Mo. (NCD) Lock and Dam No. 25, Mo. (NCD) Lock and Dam No. 26, Ill. (NCD Lock and Dam No. 52, Ill. (ORD Lock and Dam No. 53, Ill. (ORD Lock S-53, Fla. (SAJ) 9-49 Lock S-55, Fla. (SAJ) 9-49 Lock S-57, Fla. (SAJ) 9-49 Lock S-58, Fla. (SAJ) 9-49 Lock S-59, Fla. (SAJ) 9-49 Lock S-60, Fla. (SAJ) 9-49 Lock S-61, Fla. (SAJ) 9-49 Lock S-62, Fla. (SAJ) 9-49 Lock S-63, Fla. (SAJ) 9-49 Lock S-63A, Fla. (SAJ) 9-49 Lock S-65, Fla. (SAJ) 9-49 Lock S-65A, Fla. (SAJ) 9-49 Lock S-65B, Fla. (SAJ) 9-49 Lock S-65C, Fla. (SAJ) 9-49 Lock S-65D, Fla. (SAJ) 9-49 Lock S-65E, Fla. (SAJ) 9-49 Lock S-96, Fla. (SAJ) 9-49 Lock S-96A, Fla. (SAJ) 9-49 Lock S-157, Fla. (SAJ) 9-49 Lock S-158, Fla. (SAJ) 9-49 Lock S-193, Fla. (SAJ) 9-49 Lock S-308B, Fla. (SA) 9-49 Lock S-310, Fla. (SAJ) 9-49 Lock Haven, Pa. (NAB) 4-36 Locklies Creek, Va. (NAO) 5-22 a River, 29-5 River, 18-3, 18-18 29-5 29-5 18-19 29-5 29-5 (SWT) 18-3 ) 29-5 ) 29-5 ) 29-5 ) 29-5 ) 29-6 ) 29-6 ) 29-6 29-6 ) 29-6 29-6 29-6 29-6 ) 29-6 ) 22-3, 22-10 ) 22-3, 22-10 I-30 ))))) , INDEX Lockport Lock and Dam, Ill. (NCC) 28-20, 28-21 Locks in Pearl River Project, La. (LMK) 12-20 Lockvoods Folly River, N.C. (SAW) 6-5, 6-18 Logan, Ohio (ORB) 25-20 Logan Creek, Bank Protection, near Bancroft, Nebr. (MRO) 21-20 Lone Rock, Ark. (SWL) 18-17 Long Beach Island, N.J. (NAP) 3-23 Long Branch Lake, Mo. (MRK) 20-4, 20-12, 20-15 Long Island Intracoastal Waterway, N.Y. (NAN) 2-30 Long Lake Area, Helena, Ark. (LMM) 13-7 Long Tom River, Oreg. (NPP) 37-45 Longboat Pass, Fla. (SAJ) 9-8, 9-27, 9-35 Lookout Point Lake, Oreg. (NPP) 37-23, 37-32, 37-43, 37-53, 37-55 Lopez Canyon Diversion, Los Angeles River Basin, Calif. (SPL) 33-28 Lopez Dam, Los Angeles River Basin, Calif. (SPL) 33-28 Lorain Harbor, Ohio (NCB) 32-7, 32-19, 32-29 Los Angeles and Long Beach Harbors, Calif. (SPL) 33-2, 33-13, 33-18 Los Angeles County Drainage Area, Calif. (SPL) 33-6, 33-15, 33-21, 33-28, 33-31 Los Coches Creek, Calif. (SPL) 33-7, 33-15, 33-22 Lost Creek, Columbus, Nebr. (MRO) 21-4, 21-11, 21-13 Lost Creek Drainage and Levee District, Ill. (NCR) 28-14, 28-17 Lost Creek Lake,. Oreg. (NPP) 37-24, 37-33, 37-43, 37-53 Lost River, Minn. (NCS) 27-24, 27-28 Louisville, Ky. (ORL) 24-20, 24-24, 24-29 Louisville Lake, Ill. (ORL) 24-21, 24-28 Loup River, Columbus, Nebr. (MRO) 21-17 Loves Park, Ill. (NCR) 28-6, 28-9 Lowell, Mass. (NED) 1-22, 1-42, 1-50 Lowell Creek, Alaska (NPA) 40-13 Lover Arkansas River, Ark. (MR+T) 42-16, 42-28, 42-54, 42-57 Lover Arkansas River Basin, Ark. (MR+T) 42-7 Lover Big Sioux River, lowa and S. Dak. (MRO) 21-17 Lover Branch Rush River, N. Dak. (NCS) 27-24, 27-28 Lover Columbia River Basin, Oreg. and Wash. (NPP) 37-16, 37-41, 37-54 Lover Columbia River Basin Bank Protection, Oreg. and Wash. (NPP) 37-17, 37-31, 37-41 Lover Cowlitz River, Wash. (NPP) 37-46 Lover Dry Creek, Lowden, Wash. (NPW) 39-16 Lover Gila River Levee and Channel Improvements (Gila River and Tributaries) Downstream from Painted Rock Dam, Ariz. (SPL) 33-25 Lover Grand River, Mo. (MRK) 20-19 Lover Granite Lock and Dam, Wash. (NPW) 39-6, 39-11, 39-15, 39-22, 39-24 Lover Guyandotte River Basin, W. Va. (0RH) 25-20 Lover Heart River, N. Dak. (MRO) 21-17 Lover Machodoc Creek, Va. (NAB) 4-34, 4-38 Lover Monumental Lock and Dam, Wash. (NPW) 39-7, 39-11, 39-15, 39-22, 39-24 Lover Red River-South Bank, Red River Levees, La. (MR+T) 42-9, 42-15, 42-28, 42-46, 42-49, 42-57 Lover Red River Standard Revetments (MR+T) 42-33, 42-37 Lover San Francisco Bay, Calif. (SPN) 34-7 Lover San Joaquin River and Tributaries, including Tuolumne and Stanislaus Rivers, Calif. (SPK) 35-9, 35-23, 35-29 Lover Snake River, Wash., Oreg., Idaho, Fish and Wildlife Compensation (NPW) 39-8, 39-11, 39-15 Lover Thorofare, Deal Island, Md. (NAB) 4-6, 4-22, 4-29 Lover Walla Walla River, Wash. (NPW) 39-16, 39-18 Lover White River and Basin, Ark. (MR+T) 42-9, 42-17, 42-28, 42-53 Lover White River Levees (MR+T) 42-9, 42-48, 42-49, 42-57 Lover Woonsocket, R.I. (NED) 1-42, 1-47 Loves Wharf, Md. (NAB) 4-34 Loyalhanna Lake, Pa. (ORP) 26-7, 26-14, 26-19 Loyalsock, Pa. (NAB) 4-39 Lubec, Maine (NED) 1-22 Lubec Channel, Maine (NED) 1-38 Lucky Peak Lake, Idaho (NPW) 39-3, 39-10, 39-13 Ludington Harbor, Mich. (NCE) 31-17, 31-45, 31-63 Ludlow, Ky. (ORL) 24-22, 24-25 Ludlow Lake, Vt. (NED) 1-44 Lukfata Lake, Okla. and Ark. (SWT) 19-15 Lumber River, N.C. and S.C (SAN) 7-17 Lutsen Harbor, Minn. (NCE) 31-77 Lyford Levee, Ind. (ORL) 24-20, 24-29 1-31 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Lyman, Idaho (NPV) 39-19 Lyman Creek, Idaho (NPV) 39-16, 39-19 Lynches River and Clark Creek, S.C. (SAN) 7-15 Lynn Harbor, Mass. (NED) 1-38 Lynn-Nahant Beach, Mass. (NED) 1-41 Lynnhaven Inlet, Va. (NAO) 5-6, 5-14, 5-18, 5-24 Lytle and Cajun Creeks channel improvements, Calif. (SPL) 33-30, 33-31 Lytle and Warm Creeks, Calif. (SPL) 33-8, 33-15, 33-22 M Maalaea Small Boat Harbor, Hawaii (POD) 36-10 Macdowell, Edward, Lake, N.H. (NED) 1-19, 1-30, 1-50 Machias River, Maine (NED) 1-38 Mackay Creek, N.C. (SAW) 6-25, 6-28 Mackinac Island Harbor, Mich. (NCE) 31-77 Mackinaw City Harbor, Mich. (NCE) 31-17, 31-45, 31-63 Macon, Ga. (SAS) 8-16 Macy, Nebr. (MRO) 21-20 Mad Creek, Muscatine, Iowa (NCR) 28-17 Mad River, Conn. (NED) 1-22, 1-47 Mad River Basin, Calif. (SPK) 35-29 Mad River Lake, Conn. (NED) 1-42 Madison, Ind. (0RL) 24-22, 24-25, 24-30 Madison, Nebr. (MRO) 21-17, 21-20 Madison Bay, Md. (NAB) 4-34 Madison Parish Port, La. (LMK) 12-2, 12-13, 12-16 Magruder Drainage District, Oreg. (NPP) 37-46, 37-50, 37-54 Mahnomen, Minn. (NCS) 27-28 Mahoning Creek Lake, Pa. (ORP) 26-7, 26-14, 26-19 Maiden Creek Reservoir, Pa. (NAP) 3-23 Maintenance and Repair Fleet and Marine Terminals, Ark. (SWL) 18-3, 18-20 Malden River, Mass. (NED) 1-38 Malheur Improvement District, Oreg. (NPW) 39-16 Malheur River, Oreg. (NPV) 39-16, 39-18, 39-19 Mamaroneck Harbor, N.Y. (NAN) 2-30 Manasquan River, N.J. (NAP) 3-6, 3-16, 3-19 Manatee County, Fla. (SAJ) 9-48 Manatee River, Fla. (SAJ) 9-47 Manchester, Ohio (ORH) 25-21 Manchester Harbor, Mass. (NED) 1-44 Mandan, N. Dak. (MRO) 21-17, 21-20 Manele Small Boat Harbor, Hawaii (POD) 36-2 Manhasset Bay, N.Y. (NAN) 2-30 Manhattan, Kans. (MRK) 20-19, 20-21 Maniece Bayou, Ark. (LMN) (LMK) 11-22, 12-23, 12-25 Manistee Harbor, Mich. (NCE) 31-17, 31-45, 31-64 Manistique Harbor, Mich. (NCE) 31-18, 31-46, 31-64 Manitovoc Harbor, Wis. (NCE) 31-18, 31-46, 31-64 Mankato and North Mankato, Minn. (NCS) 27-9, 27-20, 27-28 Mann's Harbor, N.C. (SAW) 6-28 Manokin River, Md. (NAB) 4-34 Mansfield Hollow Lake, Conn. (NED) 1-21, 1-31, 1-51 Manteo (Shallowbag) Bay, N.C. (SAW) 6-6, 6-19 Mantua Creek, N.J. (NAP) 3-21 Maple River, N. Dak. (NCS) 27-25 Mapleshade, Ohio (ORH) 25-21 Marais de Cygnes River, Kan. (MRK) 20-8 Marblehead Harbor, Mass. (NED) 1-44 Marengo, Iowa (NCR) 28-14, 28-17 Marietta, Ohio (0RB) 25-21 Marina Del Rey, Calif. (SPL) 33-23 Marine Design Center 53-5 Marion, Ind. (ORL) 24-21, 24-28 Marion, Kans. (SWT) 19-5, 19-10, 19-13, 19-17 Marion County Drainage District, Mo. (NCR) 28-14, 28-17 Marion Diversion Channel and Levee, Kans. (SVT) 19-18 Marion Lake, Kans. (SWT) 19-5, 19-11, 19-13 Markham Ferry Lake, Okla. (SWL) 18-21 Markham Ferry Reservoir, Okla. (SWT) 19-18 Markland Locks and Dam, Ind. (ORD) 22-3, 22-9 Marmarth, N. Dak. (MRO) 21-17, 21-20 Marquette Harbor, Mich. (NCE) 31-19, 31-46, 31-64 Marseilles Lock and Dam, Ill. (NCC) 28-20 Marsh Creek, Geneva, N.Y. (NCB) 32-37 Marsh River, Minn. (NCS) 27-28 Marshall, Minn. (NCS) 27-28 Marshalltown, lova (NCR) 28-14, 28-17 Marshland Drainage District, Oreg. (NPP) 37-46 Martin, John, Reservoir, Colo. (SWA) 17-3, 17-9 Martin, Ky. (ORH) 25-20 1-32 INDEX Martins Ferry, Ohio (ORP) 26-22, 26-26 Martins Fork Lake, Ky. (ORN) 23-5, 23-9, 23-18 Martis Creek Lake, Martis Creek, Nev. and Calif. (SPK) 35-9, 35-22 Marysville, Kans. (MRK) 20-20 Marysville Lake, Calif. (SPK) 35-29 Mason, W. Va. (ORB) 25-21 Mason and Menard Drainage District, Ill. (NCR) 28-14, 28-17 Mason J. Niblack Levee, Ind. (ORL) 24-4, 24-14, 24-20, 24-24, 24-29 Massillon, Ohio (ORH) 25-6, 25-13, 25-17 Matafao Shoreline, American Samoa (POD), 36-11 Matagorda Ship Channel, Tex. (SWG) 15-6, 15-13, 15-21, 15-29, 15-33 Matawan Creek, N.J. (NAN) 2-30 Matinicus Harbor, Maine (NED) 1-38 Mats Mats Bay, Wash. (NPS) 38-24 Mattapoisett Harbor, Mass. (NED) 1-44 Mattituck Harbor, N.Y. (NAN) 2-30 Matunuck Beach, South Kingston, R.I. (NED) 1-41 Mauckport, Ind. (ORL) 24-22, 24-25 Maumee River, above Toledo, Ohio (NCB) 32-39 Maunalua Bay Small Boat Harbor, Hawaii (POD) 36-10 Maurice River, N.J. (NAP) 3-21, 3-24 Mauvaise Terre Drainage and Levee District, Ill. (LMS) 14-4, 14-9, 14-11 Maxwell Locks and Dam, Pa. (ORP) 26-25 Mayaguez Harbor, P.R. (SAJ) 9-9, 9-28, 9-35, 9-46 Mayo, V. D., Lock and Dam, Okla. (SWL) (SWT) 18-19, 19-16 Mayse, Pat, Lake, Tex. (SWT) 19-5, 19-11, 19-14 Maysville, Ky. (ORH) 25-20, 25-22 McAlpine Locks and Dam (ORD) 22-3, 22-9 McClellan-Kerr Arkansas River Navigation System (SWT) 19-2, 19-9, 19-13, 19-16 McCook Lake, S. Dak. (MRO) 21-17 McDonald Dike Road, Ore. (NPP) 37-17, 37-31, 37-41 McGee Creek Drainage and Levee District, Ill. (LMS) 14-5, 14-9, 14-12 McGinnis Levee, Ind. (ORL) 24-22, 24-25 McKees Rocks, Pa. (ORP) 26-23 McKenzie River near Walterville, Oreg. (NPP) 37-48 McKinney Bayou, Finn Bayou Segment, Ark. (LMN) (LMK) 11-22, 12-23, 12-25 McLean Bottom Levee District No. 3, Arkansas River, Ark. (SWL) 18-16 McNary Lock and Dam-Lake Wallula-Oreg. and Wash. (NPW) 39-9, 39-11, 39-15, 39-23 Meadow Grove, Nebr. (MRO) 21-20 Medomak River, Maine (NED) 1-38 Meherrin River, N.C. (NAO) 5-22 Melbourne Harbor, Fla. (SAJ) 9-9, 9-28, 9-35, 9-46 Meldahl, Captain Anthony, Locks and Dam, Ky. (ORD) 22-3, 22-8 Melton Hill Lock and Dam, Tenn. (ORN) 23-17 Melvern Lake, Kans. (MRK) 20-5, 20-12, 20-16, 20-21 Melvern Lake and Pomona Lake (Road Improvement), Kans. (MRK) 20-21 Memphis Harbor, Tenn. (MR+T) 42-29 Memphis Harbor Project Levees (MR+T) 42-48, 42-49 Memphis, Wolf River, and Nonconnah Creek, Tenn. (LMM) 13-7 Menasha Lock and Dam (NCE) 31-75 Menemsha Creek, Martha's Vineyard, Mass. (NED) 1-38 Menominee Harbor and River, Mich. and Wis. (NCE) 31-19, 31-46, 31-65 Meramec Park Lake, Mo. (LMS) 14-5, 14-9 Meramec River Basin, Mo. (LMS) 14-4, 14-12, 14-13 Merced County Stream Group, Calif. (SPK) 35-10, 35-22, 35-32 Merced County Streams, Calif. (SPK) 35-19, 35-25 Merced River, Calif. (SPK) 35-29 Mercer Lake, Mo. (MRK) 20-19 Meredosia, Ill., and Meredosia, Willow Creek, and Coon Run Drainage and Levee Districts, Ill. (LMS) 14-5, 14-9, 14-12 Meredosia Lake and Willow Creek Drainage and Levee District, Ill. (LMS) 14-6, 14-10, 14-12, 14-14 Meredosia Levee and Drainage District, Ill. (NCR) 28-14, 28-17 Mermentau River, La. (LMN) 11-4, 11-13, 11-15 Mermentau River, Bayou Nezpique, and Bay Des Cannes, La. (LMN) 11-20 Merriam, Kans. (MRK) 20-20 Merriconeag Sound, Harpswell, Maine (NED) 1-42 Merrimack River, Mass. (NED) 1-38 Merrimack River Basin, N.H. and Mass. (NED) 1-18, 1-22, 1-50 Metamora Lake, Ind. (ORL) 24-22, 24-27 Methow River, Wash. (NAS) 38-26 Metlakatla Harbor, Alaska (NPA) 40-3, 40-8, 40-10 I-33 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARNY 1985 Metropolis, Ill. (0RL) 24-21, 24-24 Miami Harbor, Fla. (SAJ) 9-9, 9-28, 9-35, 9-46 Miami River, Oreg. (NPP) 37-48 Mianus River, Conn. (NED) 1-6, 1-26, 1-33 Michael J. Kirvan Dam and Reservoir, Ohio (0RP) 26-8, 26-14, 26-19 Michigan City Harbor, Ind. (NCC) 30-5, 30-8, 30-11, 30-13, 30-14 Middle Beach, Conn. (NED) 1-41 Middle Creek, Calif. (SPK) 35-29 Middle Gila River Channel Improvements, Upper End of Safford Valley to Buttes Damsite (Camelsback Damsite to Salt River), Ariz. (SPL) 33-25 Middle River and Connecting Channels, Calif. (SPK) 35-28 Middle River and Dark Head Creek, Md. (NAB) 4-34 Middle River at Argyle, Minn. (NCS) 27-10, 27-20 Middleport, Ohio (ORB) 25-21 Middlesboro, Ky. (ORN) 23-5, 23-9 Middlesboro, Ky. (Diversion Canal) (ORN) 23-19 Middlesboro, Ky. (Yellow Creek) (ORN) 23-13, 23-18, 23-19 Middleton Shoals, Ga. and S.C. (SAS) 8-17 Midland Drainage District, Oreg. (NPP) 37-46, 37-47, 37-55 Milan, Ill. (NCR) 28-5, 28-9, 28-12, 28-17 Miles City, Mont. (MRO) 21-17 Milford Harbor, Conn. (NED) 1-38 Milford Haven, Va. (NA0) 5-22 Milford Lake, Kans. (MRK) 20-5, 20-12, 20-16, 20-21 Mill Creek, Ky. (ORL) 24-20, 24-30 Mill Creek, Md. (NAB) 4-37 Mill Creek, N.C. (SAW) 6-28 Mill Creek, Ohio (ORL) (ORB) 24-4, 24-14, 25-21 Mill Creek, Tex. (SWG) 15-26 Mill Creek, Va. (NA0) 5-22 Mill Creek, Wash. (NPW) 39-18 Mill Creek and South Slough at Milan, Ill. (NCR) 28-3, 28-8, 28-11 Mill Creek Lake, Wash. (NPW) 39-3, 39-10, 39-14 Mill Creek levees, Calif. (SPL) 33-31 Mill Four Drainage District, Oreg. (NPP) 37-49 Mill Lake, Mo. (MRK) 20-19 Miller, Ohio (ORH) 25-20 Miller Pond Drainage District, Ill. (LMS) 14-14 Millers Ferry Lock and Dam, Ala. (SAM) 10-20, 10-30 Millersburg, Ohio (ORH) 25-21 Millican Lake, Tex. (SWF) 16-8, 16-15, 16-19 Millvood, W. Va. (ORH) 25-21 Millvood Lake, Little River Basin, Ark. (SWL) 18-6, 18-11, 18-22 Milton, Ky. (ORL) 24-22, 24-25 Milton, Pa. (NAB) 4-39 Milton-Freewater, Oreg. (NPW) 39-16 Milton Harbor, N.Y. (NAN) 2-30 Milwaukee Harbor, Wis. (NCE) 31-20, 31-46, 31-65 Mineral Creek, Wash. (NPS) 38-26 Mingo Creek, S.C. (SAN) 7-15 Mingo Junction, Ohio (0RP) 26-23 Mining City Lake, Ky. (ORL) 24-21, 24-27 Minneota, Minn. (NCS) 27-24, 27-28 Minnesota River, Minn. (NCS) 27-2, 27-19, 27-22 Minnesota River at Le Sueur, Minn. (NCS) 27-11, 27-20 Minot, N. Dak. (NCS) 27-24, 27-28 Mispillion River, Del. (NAP) 3-7, 3-16, 3-19 Misquamicut Beach, Westerly, R.I. (NED) 1-41 Mission and Lapvai Creeks, Idaho (NPW) 39-17 Mission Creek, Idaho (NPW) 39-19 Mission Zanja Creek, Calif. (SPL) 33-31 Mississineva Lake, Ind. (ORL) 24-9, 24-16 Mississippi and Leech Rivers, Minn. (NCS) 27-23 Mississippi Delta Region, La. (MR+T) 42-28 Mississippi River Agricultural Area No. 8, Mo. (LMS) 14-6, 14-10, 14-12 Mississippi River Agricultural Area No. 10, Mo. (LMS) 14-15 Mississippi River Agricultural Area No. 12, Mo. (LMS) 14-15 Mississippi River Alluvial Valley Mapping (MR+T) 42-3 Mississippi River, Alton to Gale, Ill., Underseepage Measures (LMS) 14-15 Mississippi River and Alluvial Valley below Cape Girardeau, Mo. (MR+T) 42-2 Mississippi River and Tributaries (MR+T) 42-1 to 42-63 Mississippi River and Tributaries-Channel Improvements (MR+T) 42-4 Mississippi River and Tributaries-Levees (MR+T) 42-4 Mississippi River at Alton, Ill. (LMS) 14-13 I-34 INDEX Mississippi River at St. Louis, Mo. (LMS) 14-15 Mississippi River Bank Revetments and Dikes (MR+T) 42-30, 42-34, 42-39 Mississippi River, Baton Rouge to Gulf of Mexico, La. (LMN) 11-5, 11-13, 11-16 Mississippi River between Brainerd and Grand Rapids, Minn. (NCS) 27-23 Mississippi River between Missouri River and Minneapolis, Minn. (NCS) (NCD) 27-2, 29-1, 29-4, 29-10 Mississippi River between Ohio and Missouri Rivers, Mo. and Ill. (LMS) 14-2, 14-9, 14-11 Mississippi River Channel Improvements (MR+T) 42-29, 42-50, 42-51, 42-53 Mississippi River Commission (MR+T) 42-1 Mississippi River Delta at and below New Orleans, La., (New Orleans to Venice, La., Hurricane Protection) (LMN) 11-14 Mississippi River Delta Region, La. (MR+T) 42-59 Mississippi River-Gulf Outlet, La. (LMN) 11-17, 11-13, 11-16 Mississippi River-Gulf Outlet, Michoud Canal, La. (LMN) 11-20 Mississippi River Headwater Reservoirs, Minn. (NCS) 27-2, 27-19, 27-22 Mississippi River Improvements (MR+T) 42-11 Mississippi River Levees (MR+T) 42-10, 42-28, 42-44, 42-46, 42-47 Mississippi River Main Stem Channel Improvements (MR+T) 42-29 Mississippi River near Aitkin, Minn. (NCS) 27-24 Mississippi River Outlets, Venice, La. (LMN) 11-8, 11-13, 11-16 Mississippi River Project Levees (MR+T) 42-44, 42-46, 42-47,.42-49 Mississippi River Tributary and Outlet Improvements (MR+T) 42-13 Mississippi River Tributary Dams and Lakes (MR+T) 42-20 Mississquoi River at Richford, Vt. (NAN) 2-32, 2-36 Missouri National Recreational River, Nebr. and S. Dak. (MRO) 21-4, 21-11, 21-13 Missouri River, Mo. (MR+T) 42-19 Missouri River at New Haven, Mo. (MRK) 20-19 Missouri River, Aten, Nebr. (MRO) 21-17 Missouri River, Bank Protection, Greenwood, S. Dak. (MRO) 21-20 Missouri River, Bank Stabilization, Fort Benton, Mont. (MRO) 21-19 Missouri River, Garrison Dam to Lake Oahe, N. Dak. (MRO) 21-5, 21-11, 21-13 Missouri River, Kenslers Bend, Nebr. to Sioux City, Iowa (MRO) 21-5, 21-11, 21-13 Missouri River Levee System, Iowa, Nebr., Kans., and Mo. (Rulo, Nebr. to Mouth) (MRK) 20-5, 20-12, 20-16, 20-20, 20-21 Missouri River Levee System, Iowa, Nebr., Kans., and Mo. (Sioux City, Iowa, to Rulo, Nebr.) (MRO) 21-5, 21-11, 21-14, 21-18, 21-19, 21-21 Missouri River Main Stem (MRK) 20-22 Missouri River, Marina, Sioux City, Iowa (MRO) 21-21 Missouri River, Niobrara, Nebr. (MRO) 21-17 Missouri River, Sioux City, Iowa, to Fort Benton, Mont. (MRO) 21-16 Missouri River, Sioux City, Iowa, to Mouth (Rulo, Nebr., to Mouth) (MRK) 20-2, 20-11, 20-14, 20-21 Missouri River, Sioux City, Iowa, to Rulo, Nebr. (MRO) 21-2, 21-10, 21-12, 21-18 Mitigation of Shore Damages, Detroit, Mich., District (NCE) 31-32 Mobile Bay, Ala. to New Orleans, La. (SAM) 10-35 Mobile Harbor, Ala. (SAM) 10-9, 10-27, 10-36 Mocassin Swamp, N.C. (SAW) 6-28 Moccasin Springs, Mo. (LMS) 14-13 Moclips River, Wash. (NPS) 38-26 Mojave River Dam, Calif. (SPL) 33-8, 33-15, 33-22 Mokelumne River, Calif. (SPK) 35-28 Molalla River at Milk Creek location, Oreg. (NPP) 37-49 Molalla River at Ressel location, Oreg. (NPP) 37-49 Moline, Ill. (NCR) 28-7, 28-9, 28-13 Moline Harbor, Ill. (NCD) 29-7 Monongahela River, Pa. and W. Va. Locks and Dams (ORP) 26-2, 26-13, 26-17, 26-25, 26-26 Monoosnoc Brook, Mass. (NED) 1-42, 1-50 Monoosnoc Lake, Mass. (NED) 1-42, 1-50 Monroe, La., floodvall extension (LMK) 12-22 Monroe Bay and Creek, Va. (NAB) 4-34 Monroe Floodwall, La. (LMK) 12-25 Monroe Harbor, Mich. (NCE) 31-20, 31-47, 31-65 Monroe Lake, Ind. (ORL) 24-9, 24-16, 24-27 Montcalm, W. Va. (ORH) 25-22 Monterey Harbor, Calif. (SPN) 34-7 Montgomery Locks and Dam, Pa. (ORD) 22-2, 22-7 Montour Falls, N.Y. (NCB) 32-37 I-35 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Moore Haven Lock, Fla. (SAJ) 9-49 Moorefield, V. Va. (NAB) 4-37 Moores Ferry, Va. (ORB) 25-20 Moorhead, Minn. (NCS) 27-25 Mooring for Battleship Oregon, Oreg. (NPP) 37-45 Moosabec Bar, Maine (NED) 1-38 Morehead, Ky. (ORL) 24-30 Morehead City Harbor, N.C. (SAW) 6-7, 6-19 Morgan City and Vicinity, La. (LMN) 11-11, 11-14, 11-17 Morgantown Lock and Dam, V. Va. (ORP) 26-25 Morganza Floodway, La. (MR+T) 42-50 Moriches Inlet, N.Y. (NAN) 2-7, 2-20, 2-24 Mormon Slough, Calif. (SPK) 35-29 Morrison, Colo. (MRO) 21-18 Morrison Creek Stream Group, Calif. (SPK) 35-18 Morristown, N.Y. (NCB) 32-12 Morristown Harbor, N.Y. (NCB) 32-35 Morro Bay Harbor, Calif. (SPL) 33-3, 33-13, 33-19 Moscow, Ohio (ORL) 24-22, 24-25 Mosquito Creek Lake, Ohio River Basin, Ohio (ORP) 26-8, 26-14, 26-19 Moss Bluff Lock, Fla. (SAJ) 9-53 Moss Landing Harbor, Calif. (SPN) 34-4 Mott, N. Dak. (MRO) 21-17 Mound City Locks and Dam, Ill. (ORD) 22-1, 22-10 Mounds and Mound City, Ill. (LMM) 13-7 Moundsville, V. Va. (ORP) 26-22, 26-26 Mount Clemens, Clinton River, Mich. (NCE) 31-78 Mount St. Helens and Vicinity, Wash. (NPP) 37-17, 37-31, 37-42 Mount St. Helens Emergency Measures, Wash. (NPP) 37-15 Mountain Brook Dam, N.H. (NED) 1-44 Mountain Park Reservoir (Tom Steed Lake), Okla. (SVT) 19-18 Mouth of Yazoo River, Miss. (LMK) 12-21 Moyock Creek, N.C. (SAW) 6-28 Mt. Baldy, Indiana Dunes National Lakeshore, Ind. (NCC) 30-14 Mt. Carmel, Ill. (ORL) 24-20, 24-29 Mt. Holly, N.J. (NAP) 3-23 Mt. Morris Lake, N.Y. (NCB) 32-14, 32-21 Mud and Basket Slough, Rickreall Creek, Oreg. (NPP) 37-50 Mud Creek, Broken BoW, Nebr. (MRO) 21-17, 21-20 Mud Lake, Idaho (NPW) 39-17, 39-19 Mud Lake Pumping Station, Tenn. (MR+T) 42-28 Mud Mountain Dam, Wash. (NAS) 38-8, 38-15, 38-21 Mud River, W. Va. (ORH) 25-21 Muddy Creek Dam, Pa. (ORP) 26-22 Muddy Hook and Tyler Coves, Md. (NAB) 4-34 Mulberry Creek, Va. (NAO) 5-22 Mullet Key, Fla. (SAJ) 9-48 Multnomah Channel, Oreg. (NPP) 37-45 Multnomah Drainage District 1, Oreg. (NPP) 37-46, 37-47, 37-54 Muncie, Ind. (ORL) 24-20, 24-29 Munday Floodway, Tex. (SWF) 16-21 Murder and Burnt Corn Creeks, Brewton, Ala. (SAM) 10-43 Murder Creek, East Brewton, Ala. (SAM) 10-14, 10-28, 10-39 Murderkill River, Del. (NAP) 3-21 Murfreesboro Dam and Lake (LMK) 12-25 Murray Lock & Dam, Ark. (SWL) 18-3, 18-18 Murrells Inlet, S.C. (SAN) 7-5, 7-10, 7-13 Muscatatuck River, Crothersville, Ind. (ORL) 24-30 Muscatine, Iowa (Mad Creek) (NCR) 28-14 Muscatine Harbor, Iowa (NCD) 29-7 Muscatine Island L. and D. D., Louisa D. D. No. 13, Iowa (NCR) 28-14, 28-17 Muscooten Bay, Ill. (NCR) 28-3, 28-8, 28-11 Muskegon Harbor, Mich. (NCE) 31-21, 31-47, 31-66 Muskingum River, Ohio (ORH) 25-19 Muskingum River Lakes, Ohio (ORH) 25-7, 25-14, 25-17 Mustinka River, Minn. (NCS) 27-27, 27-28 Myers Chuck Harbor, Alaska (NPA) 40-12 Myrtle Beach, S.C. (SAN) 7-17 Mystic, Conn. (NED) 1-44 Mystic River, Conn. (NED) 1-38 Mystic River, Mass. (NED) 1-38 N Naches River, Naches, Wash. (NPS) 38-26 Nagel Drainage District, Iowa (MRO) 21-21 Nahunta Swamp, N.C. (SAW) 6-28 Naknek River, Alaska (NPA) 40-12 Namo River, Territory of Guam (POD) 36-12 Nan Cove, Md. (NAB) 4-34 Nandua Creek, Va. (NAO) 5-22 Nanpil River Hydropower, Pohnpei, Trust Territory of the Pacific Islands (POD) 36-4, 36-7, 36-9 Nansemond River, Va. (NAO) 5-22 Nantasket Beach, Mass. (NED) 1-41 Nanticoke River, Md. (NAB) 4-34, 4-38 I-36 INDEX Nanticoke River at Bivalve, Md. (NAB) 4-34 Nanticoke River (including Northwest Fork), Del. and Md. (NAB) 4-34 Nantucket (Harbor of Refuge), Mass. (NED) 1-38 Napa River, Calif. (SPN) 34-4 Napa River Basin, Calif. (SPK) 35-29 Napatree Beach, R.I. (NED) 1-44 Narragansett Pier, R.I. (NED) 1-44 Narraguagus River, Maine (NED) 1-38 Narrows Dam-Lake Greeson, Ark. (LMK) 12-8, 12-14, 12-17, 12-22 Narrows of Lake Champlain, N.Y. and Vt. (NAN) 2-8, 2-20, 2-24 Nashua, N.H. (NED) 1-22, 1-42, 1-50 Natchez Port Area, Miss. (LMK) 12-25 Natchitoches Parish, La. (LMN) (LMK) 11-22, 12-24, 12-25 National Dredging Program 53-4 National Emergency Management Activities, Huntington, W.Va., District (ORH) 25-11 National Emergency Preparedness Activities, 32-16, 48-1 Natural Disaster Activities, New York District (NAN) 2-18 Natural Disaster Preparedness, Response and Recovery Activities, 43-1 Navajo Reservoir, N. Mex. (SPK) 35-28 Navarro Mills Lake, Tex. (SWF) 16-8, 16-15, 16-19 Navasota Lake, Tex. (SWF) 16-21 Navigation Aids (U.S. Coast Guard), Ark. (SWL) 18-20 Navigation Locks and Dams, Ark. (SWL) 18-10 Navigation Work under Special Authorization (Calcasieu Pass Channel in Old River Bend at Cameron, La.) (LMN) 11-20 Nawiliwili Harbor, Hawaii (POD) 36-2, 36-6, 36-8 Nawilivili Small Boat Harbor, Hawaii (POD) 36-10 NCD Master Plan for Water Control Data System 31-37 Neabsco Creek, Md. (NAB) 4-34 Neah Bay, Wash. (NPS) 38-24 Neale Sound, Md. (NAB) 4-34 Near Dardanelle, Arkansas River, Ark. (SWL) 18-16 Near Springfield on Sangamon River, Ill. (NCR) 28-14 Neavitt Harbor, Md. (NAB) 4-34 Neches River and Tributaries, Salt Water Barrier at Beaumont, Tex. (SWG) 15-26 Needles, Calif. (SPL) 33-25, 33-31 Nehalem Bay, Oreg. (NPP) 37-8, 37-28, 37-38 Neodesha Lake, Kans. (SWL) (SWT) 18-21, 19-15, 19-16 Neon-Fleming, Ky. (ORL) 24-20, 24-30 Neshaminy State Park Harbor (NAP) 3-21 Nestucca River, Oreg. (NPP) 37-45, 37-48 Neuse River, N.C. (SAW) 6-25, 6-28, 6-29 Neuse River Barrier, N.C. (SAW) 6-28, 6-30 Neuse River Basin, N.C. (SAW) 6-12, 6-30 Neva and Olga Straits, Alaska (NPA) 40-12 Nevile Island, Pa. (ORP) 26-22, 26-26 New Albany, Ind. (ORL) 24-20, 24-24, 24-29 New Amsterdam, Ind. (ORL) 24-22, 24-25 New Bedford and Fairhaven Harbors, Mass. (NED) 1-38 New Bedford, Fairhaven, and Acushnet, Mass. (NED) 1-19, 1-30, 1-36 New Bedford-Fairhaven Barrier, Mass. (NED) 1-23 New Boston Harbor, Ill. (NCD) 29-7 New Buffalo Harbor, Mich. (NCE) 31-21, 31-47, 31-66 New Bullards Bar, Calif. (SPK) 35-29 New Cumberland, W. Va. (ORP) 26-23 New Cumberland Locks and Dam, Stratton, Ohio (ORD) 22-1, 22-7 New Fairfield, Conn. (NED) 1-22 New Harbor, Maine (NED) 1-38 New Harmony, Ind. (ORL) 24-22, 24-25, 24-30 New Harmony Bridge, Ill. and Ind. (0RL) 24-20, 24-21, 24-24 New Haven Breakwater, Conn. (NED) 1-38 New Haven Harbor, Conn. (NED) 1-38 New Hope Lake (B. Everett Jordan Dam and Lake), N.C. (SAW) 6-10, 6-15, 6-20 New Jersey Intracoastal Waterway (NAP) 3-7, 3-16 New Kensington and Parnassus, Pa. (ORP) 26-22, 26-26 New Lock and Dam 26, Ill. (NCD) 29-6 New London, Conn. (NED) 1-19, 1-22, 1-23, 1-30, 1-36 New London Harbor, Conn. (NED) 1-6, 1-26, 1-33 New Madrid Harbor, Mo. (LMM) 13-6 New Martinsville, W. Va. (ORH) 25-21 New Matamoras, Ohio (ORH) 25-21 New Melones Lake, Calif. (SPK) 35-16 New Orleans to Venice, La. Hurricane Protection (LMN) 11-11, 11-14, 11-17 New Pass, Sarasota, Fla. (SAJ) 9-10, 9-28, 9-36 New Richmond, Ohio (0RL) 24-22, 24-25 New River, Fla. (SAJ) 9-47 New River, N.C. (SAW) 6-27 New River, Onslow County, N.C. (SAW) 6-27 1-37 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 New River, Va. and W. Va. (ORB) 25-19 New Rochelle Harbor, N.Y. (NAN) 2-30 New York and New Jersey Channels, (NAN) 2-9, 2-20, 2-25, 2-28, 2-34 New York Harbor-Collection and Removal of Drift (NAN) 2-9, 2-20, 2-25 New York Harbor-Entrance Channels and Anchorage Areas (NAN) 2-10, 2-20, 2-25 New York Harbor, Supervisor of (NAN) 2-13, 2-21, 2-28 Newark, Ohio (ORH) 25-7, 25-14, 25-17, 25-20 Newark Bay, Hackensack and Passaic Rivers, N.J. (NAN) 2-8, 2-20, 2-24, 2-34 Newaukum River, Wash. (NPS) 38-26 Nevbegun Creek, N.C. (SAW) 6-25 Newburgh, Ind. (0RL) 24-20, 24-31 Newburgh Locks and Dam, Ind. (ORD) 22-3, 22-9 Newburyport Harbor, Mass. (NED) 1-6, 1-26, 1-33 Newhall Creek, Calif. (SPL) 33-31 Newmarket Creek, Va. (NAO) 5-23 Newport, Ark. (SWL) 18-16 Newport, Ky. (ORL) 24-20, 24-21, 24-24, 24-29 Newport, Ohio (ORH) 25-21 Newport Bay Harbor, Calif. (SPL) 33-23, 33-28 Newport Harbor, R.I. (NED) 1-38 Newport News, Va. (NAO) 5-23 Newport News Creek, Va. (NAO) 5-22 Newry-01d Pickens Dam and Lake, S.C. (SAS) 8-17 Newt Graham Lock and Dam, Okla. (SWL) (SWT) 18-19, 19-16 Newtown Creek, N.Y. (NAN) 2-30 Niagara Remedial Works, N.Y. (NCB) 32-35 Niagara River, N.Y. (NCB) 32-39 Niantic Bay and Harbor, Conn. (NED) 1-38 Niblack, Mason J., Levee, Ind. (ORL) 24-4, 24-14, 24-20, 24-24, 24-29 Nicholasville, (Townfork) Vicinity, Ky. (ORL) 24-30 Nichols, N.Y. (NAB) 4-36, 4-39 Nickajack Lock and Dam, Tenn. (ORN) 23-17 Nimrod Lake, Ark. (SWL) 18-6, 18-11, 18-21 Ninilchik Harbor, Alaska (NPA) 40-4, 40-8, 40-10 Nishnabotna River at Hamburg, Iowa (MRO) 21-17, 21-21 Nisqually River, Wash. (NPS) 38-26 Nixon Creek, Tenn. (LMM) 13-17 Nolin Lake, Ky. (ORL) 24-9, 24-16, 24-27 Nome Harbor, Alaska (NPA) 40-4, 40-9, 40-11 Nomini Bay and Creek, Va. (NAB) 4-34 Nonconnah Blvd., Nonconnah Creek, Tenn. (LMM) 13-7 Nonconnah Creek, Interceptor Sever, Memphis, Tenn. (LMM) 13-12, 13-4, 13-5 Nonevaug River, Conn. (NED) 1-17, 1-29, 1-36 Nookagee Lake, Mass. (NED) 1-42, 1-50 Nooksack River, Wash. (NPS) 38-8, 38-15, 38-21, 38-26 Norfolk, Nebr. (MRO) 21-17, 21-20 Norfolk Floodwall, Va. (NAO) 5-23 Norfolk Harbor, Va. (NAO) 5-6, 5-15, 5-18, 5-24 Norfork Lake, Ark. (SWL) 18-8, 18-12, 18-23 Normal, Ky. (ORH) 25-20 Norman Reservoir (Lake Thunderbird), Okla. (SWT) 19-18 Norrell Lock & Dam (No. 1) & Entrance Channel, Ark. (SWL) 18-3, 18-18 North Adams, Mass. (NAN) 2-32 North Alexander Drainage and Levee District, Ill. (LMS) 14-15 North Andover and Lawrence, Mass. (NED) 1-44 North Branch of Kokosing River Lake, Ohio (ORH) 25-7, 25-14, 25-17 North Canaan, Conn. (NED) 1-22, 1-42, 1-49 North Ellenville, N.Y. (NAN) 2-32 North Fork of Pound River Lake, Va. (ROH) 25-8, 25-14, 25-17 North Fork, Pit River at Alturas, Calif. (SPK) 35-29 North Fork Skykomish River, Wash. (NPS) 38-26 North Hampton Beach, North Hampton, N.H. (NED) 1-44 North Hartland Lake, Vt. (NED) 1-13, 1-28, 1-47 North Little Rock, Arkansas River, Ark. (SWL) 18-16 North Middletown, Ky. (ORL) 24-30 North Nashua River, Fitchburg, Mass. (NED) 1-42 North Nashua River, Lancaster, Mass. (NED) 1-42, 1-50 North Platte River, Bank Stabilization, Minatare, Nebr. (MRO) 21-20 North River Dike, N.C. (SAW) 6-28 North Scituate Beach, Scituate, Mass. (NED) 1-41 North Second St., Memphis, Tenn. (Wolf River Bridge) (LMM) 13-7 North Shore of Long Island, Suffolk County, N.Y. (NAN) 2-31 I-38 INDEX North Springfield Lake, Vt. (NED) 1-14, 1-28, 1-47 North Stratford, N.H. (NED) 1-22, 1-48 North Wildwood, N.J. (NAP) 3-23 Northampton, Mass. (NED) 1-22, 1-42, 1-48 Northeast (Cape Fear) River, N.C. (SAW) 6-25, 6-27 Northeast Harbor, Maine (NED) 1-38 Northeast River, Md. (NAB) 4-34 Northfield Brook Lake, Conn. (NED) 1-17, 1-29, 1-48 Northport Harbor, N.Y. (NAN) 2-30 Northport Harbor, Wis. (NCE) 31-77 Norwalk, Conn. (NED) 1-22, 1-42 Norwalk Harbor, Conn. (NED) 1-38 Norvalk-Wilton, Conn. (NED) 1-44 Norwich, Conn. (NED) 1-42, 1-51 Norwich, N.Y. (NAB) 4-36, 4-39 Nottoway River, Va. (NAO) 5-22 Noxubee River, Miss. (SAM) 10-14, 10-28, 10-39, 10-42 Noyo River and Harbor, Calif. (SPN) 34-3, 34-4 Nutwood Drainage and Levee District, Ill. (LMS) 14-6, 14-10, 14-12 0 0. C. Fisher Dam and Lake, Tex. (SWF) 16-9, 16-15, 16-19 Oahe Dam-Lake Oahe, Missouri River Basin S. Dak. and N. Dak. (MRO) 21-8, 21-12, 21-16 Oak Bluffs Town Beach, Mass. (NED) 1-41 Oak Orchard Harbor, N.Y. (NCB) 32-8, 32-19 Oakdale, Pa. (ORP) 26-22 Oakford Special Drainage District (NCR) 28-14, 28-17 Oakland Beach, Warwick, R.I. (NED) 1-41 Oakland Harbor, Calif. (SPN) 34-4, 34-8 Obey River, Tenn. (ORN) 23-13 Obion River, Tenn. (LMM) 13-6 O'Brien, T.J., Lock and Dam, Ill. (NCC) 28-19, 28-20 Occohannock Creek, Va. (NAO) 5-22 Occoquan Creek, Va. (NAB) 4-34, 4-38 Ocean Beach, Calif. (SPL) 33-24 Ocean City, N.J. (NAP) 3-23 Ocean City Harbor and Inlet and Sinepuxent Bay, Md. (NAB) 4-6, 4-23, 4-29 Oceana, W. Va. (ORH) 25-20 Oceanside, Calif. (SPL) 33-24 Oceanside Harbor, Calif. (SPL) 33-3, 33-13, 33-19 Ocholockonee (Ochlockney) River, Ga. and Fla. (SAM) 10-42 Oconto Harbor, Wis. (NCE) 31-22, 31-48, 31-66 Ocracoke Inlet, N.C. (SAW) 6-7, 6-19 Ocracoke Island, N.C. (SAW) 6-27 Ofu Small Boat Harbor, American Samoa (POD) 36-10 Ogdensburg Harbor, N.Y. (NCB) 32-8, 32-19, 32-30 Ohio National Wildlife Conservation Area (ORD) 22-3 Ohio River, Ill. and Ky. (MR+T) 42-19 Ohio River Basin (Huntington District) (0RH) 25-8, 25-14 Ohio River Basin (Louisville Dist.) (ORL) 24-10, 24-16, 24-18, 24-24, 24-30 Ohio River Basin (Nashville District) (ORN) 23-6, 23-12, 23-18 Ohio River Basin (Pittsburgh District) (ORP) 26-9, 26-14, 26-19, 26-26, 26-27 Ohio River, Locks and Dams (ORD) 22-1, 22-5, 22-6, 22-7 Ohio River, Open Channel Work (ORD) 22-4, 22-5, 22-6 Oil City, Pa. (ORP) 26-22 Okabena Creek at Worthington, Minn. (NCR) 28-14 Okanogan and Pend Oreille Rivers (NPS) 38-24 Okanogan River, Wash. (NPS) 38-26 Okanogan River, Omak, Wash. (NPS) 38-27 Okanogan River, Oroville, Wash. (NPS) 38-27 Okatibbee Lake, Miss. (SAM) 10-12, 10-28, 10-38 Okeechobee Waterway, Fla. (SAJ) 9-10, 9-28, 9-36, 9-45, 9-46 Oklahoma City Floodway, Okla. (SWT) 19-15, 19-17 Oklawaha River, Fla. (SAJ) 9-11, 9-28, 9-36, 9-46 01cott Harbor, N.Y. (NCB) 32-8, 32-19, 32-30 Old Field Swamp, N.C. (SAW) 6-27 Old Harbor, Kodiak Island, Alaska (NPA) 40-12 Old Hickory Lock and Dam, Tenn. (ORN) 23-14 Old Highway 82 Bridge, Columbus, Miss. (SAM) 10-16, 10-29, 10-40 Old River, Calif. (SPK) 35-28 Old River, La. (MR+T) 42-6, 42-28, 42-50 Old River, Standard Revetments (MR+T) 42-31 Old Town Creek, Miss. (SAM) 10-42 Oldmans Creek, N.J. (NAP) 3-21, 3-24 Olean, N.Y. (ORP) 26-22, 26-26 Olive Hill, Ky. (ORH) 25-22 Olympia Harbor, Wash. (NPS) 38-24 I-39 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Omaha, Nebr. (MRO) 21-17, 21-20 Onaga Lake, Kans. (MRK) 20-19 Onancock River, Va. (NAO) 5-22 Oneonta, N.Y. (NAB) 4-39 Onondaga Creek, Nedrow, N.Y. (NCB) 32-37 Ontonagon Harbor, Mich. (NCE) 31-22, 31-48, 31-66 Oologah Lake, Okla. (SWL) (SWT) 18-21, 19-5, 19-11, 19-13, 19-16 Oostanaula and Coosawatee River, Ga. (SAM) 10-42 Opekiska Lock and Dam, W. Va. (ORP) 26-25 Open Channel Work, Ohio River (ORD) 22-4, 22-5, 22-6 Open River Lewiston to Johnson Bar Landing (NPW) 39-24 Open River Pasco to Lewiston (NPW) 39-24 Optima Lake, Okla. (SWT) 19-5, 19-11, 19-14 Orange River, Fla. (SAJ) 9-46, 9-47 Orchard Beach, Bronx, N.Y. (NAN) 2-35 Oregon Slough (North Portland Harbor), Oreg. (NPP) 37-45 Orleans, Ind. (ORL) 24-22 Oro Grande Wash Channel Improvements, Calif. (SPL) 33-25, 33-31 Orofino Creek and Clearwater River, Idaho (NPW) 39-17 Orowoc Creek, N.Y. (NAN) 2-30 Orwell Reservoir (Ottertail River) (NCS) 27-27 Osage River, Kans. and Mo. (MRK) 20-22 Osage River, Mo., Lock and Dam (MRK) 20-18 Osawatomie, Kans. (MRK) 20-19, 20-21 Osceola Harbor, Ark. (LMM) 13-6 Oslo, Minn. (NCS) 27-28 Oswego Harbor, N.Y. (NCB) 32-9, 32-19, 32-31, 32-39 Ottawa, Kans. (MRK) 20-19, 20-21 Ottawa, Ohio (NCB) 32-15 Ottawa River Harbor, Mich. and Ohio (NCB) 32-35 Otter Brook Lake, N.H. (NED) 1-14, 1-28, 1-47 Otter Creek, Vt. (NAN) 2-30 Otter Creek Park, Ky. (ORL) 24-31 Otter Tail River, Minn. (NCS) 27-27, 27-28 Ottumwa, Iowa (NCR) 28-15 Ouachita and Black Rivers, Ark. and La. (Felsenthal Canal) (LMK) 12-21 Ouachita and Black Rivers, Ark. and La., Locks and Dams (LMK) 12-19 Ouachita and Black Rivers below Camden, Ark. (LMK) 12-2, 12-13, 12-16 Ouachita River and Tributaries, Ark. and La. (LMK) 12-8, 12-18, 12-22 Ouachita River Levees, La. (LMK) 12-8, 12-15, 12-22 Overton-Red River Waterway, La. (LMK) 12-3, 12-13, 12-16 Ovasco Inlet and Outlet, Montville and Dry Creek, State Ditch and Crane Brook, N.Y. (NCB) 32-37 Owego, N.Y. (NAB) 4-39 Ovensboro, Ky. (ORL) 24-21, 24-24 Owl's Head Harbor, Maine (NED) 1-38 Oxford, Md. (NAB) 4-35 Oxford, N.Y. (NAB) 4-17, 4-26 Oyster Channel, Va. (NAO) 5-22 Oyster Creek, Tex. (SWG) 15-26 Ozan Creek, Ark. (LMK) 12-22 Ozark-Jeta Taylor Lock & Dam, Ark. (SWL) 18-8, 18-12, 18-19 Ozona, Fla. (SAJ) 9-46, 9-47 P Paauau Stream, Hawaii (POD) 36-4, 36-7 Paducah, Ky. (ORL) 24-20, 24-24, 24-29 Pagan River, Va. (NA0) 5-22 Pago Pago Airport, American Samoa (POD) 36-4, 36-11 Pago Pago to Nuuuli, American Samoa (POD) 36-11 Paint Creek at Chillicothe, Ohio (ORH) 25-22 Paint Creek at Washington Court House, Ohio (ORH) 25-22 Paint Creek Lake, Ohio (ORH) 25-8, 25-14, 25-18 Paint Rock River, Ala. (ORN) 23-13, 23-19 Painted Post, N.Y. (NAB) 4-36, 4-39 Painted Rock Dam, Ariz. (SPL) 33-6, 33-14, 33-21 Paintsville Lake, Ky. (ORH) 25-8, 25-14, 25-18 Pajaro River Basin, Calif. (SPK) 35-19, 35-25 Palm Beach, Fla. (SAJ) 9-47 Palm Beach County, Fla., from Lake Worth Inlet to South Lake Worth Inlet (SAJ) 9-48 Palm Beach County, Fla., from Martin County Line of Lake Worth Inlet and from South Lake Worth Inlet to Brovard County Line (SAJ) 9-21, 9-30, 9-41 Palm Beach Harbor, Fla. (SAJ) 9-11, 9-28, 9-36 Palouse River, Wash. (NPW) 39-17, 39-18 Pamlico and Tar Rivers, N.C. (SAW) 6-7, 6-19 I-40 INDEX Pamunkey River, Va. (NAO) 5-22 Panacea Harbor, Fla. (SAM) 10-42, 10-45 Panama City Harbor, Fla. (SAM) 10-10, 10-27, 10-37 Pantego Creek and Cucklers Creek, N.C. (SAW) 6-27 Panther Creek, Curdsville, Ky. (ORL) 24-20, 24-30 Panther Creek, V. Va. (ORH) 25-20 Papillion Creek and Tributaries Lakes, Nebr. (MRO) 21-5, 21-11, 21-14 Parish Creek, Md. (NAB) 4-37, 4-23, 4-30 Park City, Kans. (SWT) 19-17 Park River, N.D. (NCS) 27-28 Park River, Hartford, Conn. (NED) 1-14, 1-28, 1-35, 1-48 Parker Creek, Va. (NAO) 5-27, 5-15, 5-20 Parkersburg, V. Va. (ORH) 25-20, 25-22 Parrotts Creek, Va. (NAO) 5-22 Pascagoula Harbor, Miss. (SAM) 10-10, 10-28, 10-37 Pascagoula River, Miss. (SAM) 10-42, 10-45 Pasquotank River, N.C. (SAW) 6-27 Pass Christian, Miss. (SAM) 10-45 Pass Christian Harbor, Miss. (SAM) 10-42 Pass Manchac, La. (LMN) 11-21 Pass-a-Grille Pass, Fla. (SAJ) 9-46, 9-47 Passaic River Basin, N.J. and N.Y., Phase I (NAN) 2-16, 2-21, 2-27 Passamaquoddy Tidal Power Project, Maine (NED) 1-43 Pat Mayse Lake, Tex. (SWT) 19-5, 19-11, 19-14 Pataha Creek, Wash. (NPW) 39-17 Patchogue River, Conn. (NED) 1-38 Patman, Wright, Dam and Lake, Tex. (LMN) (SWF) 11-22, 16-11, 16-16, 16-20 Patoka Lake, Ind. (ORL) 24-10, 24-16, 24-27 Patoka River at Jasper, Ind. (ORL) 24-30 Patriot, Ind. (ORL) 24-22, 24-25 Pattonsburg Lake, Mo. (MRK) 20-19 Patuxent River, Md. (NAB) 4-34 Pawcatuck, Conn. (NED) 1-22, 1-42 Pawcatuck River, R.I. and Conn. (NED) 1-38, 1-44 Pawtucket, R.I. (NED) 1-44 Pawtuxet Cove, R.I. (NED) 1-38 Pavtuxet River, Warwick, R.I. (NED) 1-10, 1-27, 1-35 Pax, V. Va. (0RH) 25-22 Payette River, Idaho (NPW) 39-17 Payette Valley, Idaho (NPW) 39-18 Peacock Creek, Liberty County, Ga. (SAS) 8-7, 8-16 Pearl River, Miss. and La. (LMK) 12-3, 12-13, 12-15, 12-16, 12-15, 12-18 Pearl River Basin, Miss. and La. (LMK) 12-9 Pearl River Project Locks, La. (LMK) 12-20 Pearson-Skubitz Big Hill Lake, Kans. (SWT) 19-5, 19-11, 19-14 Pebble Creek, Scribner, Nebr. (MRO) 21-22 Pecan Bayou Lake, Pecan Bayou, Tex. (SWF) 16-21 Pecatonica River at Darlington, Wis. (NCR) 28-16 Peconic River, N.Y. (NAN) 2-30 Pecos, Tex. (SWA) 17-11 Peekskill Harbor, N.Y. (NAN) 2-30 Pekin-LaMarsh Drainage and Levee District, Ill. (NCR) 28-15, 28-17 Pelican Harbor, Alaska (NPA) 40-12 Pembina, N. Dak. (NCS) 27-28 Pembina River, N. Dak. (NCS) 27-24 Pembina River Lake, N. Dak. (NCS) 27-24 Pembroke Creek, N.C. (SAW) 6-25 Pendleton, Oreg. (NPP) 37-48 Pendleton Levees, Oreg. (NPP) 37-48 Peninsula Drainage District 1, Oreg. (NPP) 37-46, 37-50, 37-54 Peninsula Drainage District 2, Oreg. (NPP) 37-46, 37-47, 37-54 Penny Slough, Ill. (NCR) 28-15, 28-17 Penobscot River, Maine (NED) 1-7, 1-20, 1-26, 1-30, 1-33, 1-36 Pensacola Bay, Fla. to Mobile Bay, Ala. (SAM) 10-35 Pensacola Harbor, Fla. (SAM) 10-11, 10-28, 10-38 Pensacola Lake, Okla. (SWL) (SWT) 18-21, 19-18 Pensacola Reservoir, Okla. (SWT) 19-18 Pensaukee Harbor, Wis. (NCE) 31-76, 31-77 Pentwater Harbor, Mich. (NCE) 31-22, 31-48, 31-66, 31-79 Peoria, Ill. (NCC) 28-15 Peoria Lock and Dam, Ill. (NCC) 28-20 Pepin Harbor, Wis. (NCD) 29-7 Pepper Creek, Del. (NAP) 3-21 Pepperell Cove, Maine (NED) 1-38, 1-44 Perdido Pass Channel, Ala. (SAM) 10-11, 10-28, 10-38 Permanent International Association of Navigation Congress (PIANC) 46-1 Perquimans River, N.C. (SAW) 6-25, 6-27 Perry County Drainage and Levee Districts Nos. 1, 2, and 3, Mo. (LMS) 14-6, 14-10, 14-12 Perry Lake, Kans. (MRK) 20-5, 20-12, 20-16, 20-21 1-41 REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1985 Perry Lake Area (Road Improvements) Kans. (MRK) 20-19 Perth Amboy, N.J. (NAN) 2-31 Petaluma River, Calif. (SPN) 34-4 Petersburg Harbor, Alaska (NPA) 40-12 Petit Anse, Tigre, and Carlin Bayous, La. (LMN) 11-21 Petit Jean River, Ark. (SWL) 18-16 Petoskey Harbor, Mich. (NCE) 31-23, 31-48, 31-66 Peyton Creek, Tex. (SWG) 15-26 Phillippi Creek Basin, Fla. (SAJ) 9-54 Phillips Lake, Mass. (NED) 1-42, 1-50 Philpott Lake, Va. (SAW) 6-15, 6-16, 6-20 Phoenix, Ariz., and Vicinity (including New River) (SPL) 33-6, 33-15, 33-21 Pick-Sloan Missouri Basin Program (Kansas City Dist) (MRK) 20-6, 20-16, 20-21 Pick-Sloan Missouri Basin Program (Omaha Dist) (MRO) 21-5, 21-14, 21-19 Pickwick Landing Lock and Dam, Tenn. (0RN) 23-17 Pierce, Nebr. (MRO) 21-17, 21-20 Pig Island Gut, Maine (NED) 1-38 Pike Island Locks and Dam, W. Va. (ORD) 22-1, 22-7 Pilchuck River, Wash. (NPS) 38-8, 38-15, 38-21, 38-28 Pilot Rock, Oreg. (NPP) 37-50 Pinal Creek Channel Improvements (Globe), Ariz., (SPL) 33-25 Pine and Mathews Canyons Dams, Nev. (SPL) 33-8, 33-15, 33-22 Pine Bluff, Ark. (LMK) 12-22 Pine Creek, Angle Inlet, Minn. (NCS) 27-23 Pine Creek Lake, Okla. (SWT) 19-5, 19-11, 19-14 Pine Flat Lake and Kings River, Calif. (SPK) 35-10, 35-22 Pine Ford Lake, Mo. (LMS) 14-5, 14-9 Pine Mountain Lake, Ark. (SWL) 18-6, 18-11 Pine River, Mich. (NCE) 31-76, 31-77 Pine River Reservoir, Minn. (NCS) 27-26 Pinellas County, Fla. (SAJ) 9-21, 9-30, 9-41 Pineville, Ky. (ORN) 23-13, 23-19 Pineville, La. (LMN) (LMK) 11-22, 12-24, 12-25 Pinole Creek, Calif. (SPK) 35-29 Pinon Canyon Dam, Trinidad, Colo. (SWA) 17-11 Pioneer Lake, Kans. (MRK) 20-20 Pipestem Lake, N. Dak. (MRO) 21-5, 21-11, 21-15 Pithlachascotee River, Fla. (SAJ) 9-47 Pittsburgh, Pa. (Golden Triangle) (ORP) 26-23 Pittsburgh, Pa. (North Side) (ORP) 26-23 Pittsburgh, Pa. (The Strip) (ORP) 26-23 Pittsburgh Harbor, Pa. (ORP) 26-21 Pittsfield, Mass. (NED) 1-22, 1-49 Placer Creek, Idaho (NPS) 38-8, 38-15, 38-21 Plainview Local Flood Protection Project (SWF) 16-21 Platoro Reservoir, Colo. (SWA) 17-7 Platte River, Mo., Channel Improvement (MRK) 20-19 Platte River and Lost Creek, Schuyler, Nebr. (MRO) 21-17, 21-20 Platte River and Tributaries, Nebr. (MRO) 21-17 Platte River, Bank Protection, Louisville, Nebr. (MRO) 21-20 Platte River, M.U.D. Protection, Cedar Island, Nebr. (MRO) 21-20 Platte River near Schuyler, Nebr. (MRO) 21-17, 21-20 Plattsburgh Harbor, N.Y. (NAN) 2-30 Pleasant Bay, Mass. (NED) 1-38 Pleasant River, Maine (NED) 1-38 Pleasanton Floodway, Tex. (SWF) 16-21 Plum Creek, Colo. (MRO) 21-17 Plum Creek, Ky. (ORL) 24-30 Plum Creek, Minn. (NCS) 27-27 Plum Creek, Bank Stabilization, Aurora, Colo. (MRO) 21-20 Plum Island, Mass. (NED) 1-41 Plymouth, Pa. (NAB) 4-36, 4-39 Plymouth Harbor, Mass. (NED) 1-38 Poca, W. Va. (ORH) 25-21 Pocatello, Idaho (NPW) 39-19 Pocomoke River, Md. (NAB) 4-7, 4-23, 4-30 Pohoiki Bay, Hawaii (POD) 36-10 Point Judith Pond and Harbor of Refuge, R.I. (NED) 1-7, 1-26, 1-34, 1-44 Point Lookout Harbor (Au Gres River), Mich. (NCE) 31-23, 31-48, 31-67 Point Place, Toledo, Ohio (NCB) 32-15, 32-21 Point Pleasant, W. Va. (ORL) 25-20, 25-22 Pokegama Reservoir, Minn. (NCS) 27-26 Pollock Rip Shoals, Nantucket Sound, Mass. (NED) 1-38 Poloa Area, American Samoa (POD) 36-11 Polson Bay, Flathead Lake, Mont. (NPS) 38-24 Pomeroy, Ohio (ORL) 25-21 Pomme De Terre Lake, Mo. (MRK) 20-6, 20-13, 20-17, 20-21 Pomona Lake, Kans. (MRK) 20-6, 20-13, 20-17, 20-21 I-42 INDEX Ponce, P.R. (SAJ) 9-42 Ponce De Leon Inlet, Fla. (SAJ) 9-12, 9-28, 9-37, 9-46 Ponce Harbor, P.R. (SAJ) 9-12, 9-29, 9-37, 9-46 Pontiac Diversion, R.I. (NED) 1-44 Pool, Joe, Lake (Lakeviev Lake), Tex. (SWF) 16-7, 16-15, 16-19 Port Alexander, Alaska (NPA) 40-12, 40-13 Port Allen Harbor, Havaii (POD) 36-10 Port Angeles Harbor, Wash. (NPS) 38-24, 38-29 Port Arthur and Vicinity, Tex. Hurricane-Flood Protection (SVG) 15-9, 15-10, 15-14, 15-24 Port Austin Harbor, Mich. (NCE) 31-23, 31-48, 31-67 Port Bay, N.Y. (NCB) 32-35 Port Chester Harbor, N.Y. (NAN) 2-10, 2-20, 2-25 Port Clinton Harbor, Ohio (NCB) 32-9, 32-20, 32-31 Port Dickenson, N.Y. (NAB) 4-39 Port Everglades Harbor, Fla. (SAJ) 9-13, 9-29, 9-37, 9-46 Port 5 Facility, Bridgeport, Conn. (NED) 1-18, 1-29, 1-36 Port Gamble Harbor, Wash. (NPS) 38-24, 38-29 Port Henry Harbor, N.Y. (NAN) 2-30 Port Hueneme, Calif. (SPL) 33-23 Port Jefferson Harbor, N.Y. (NAN) 2-30 Port Jervis, N.Y. (NAP) 3-13 Port Lions Small Boat Harbor, Alaska (NPA) 40-5, 40-9, 40-11 Port of Kalama, Wash. (NPP) 37-46 Port Ontario Harbor, N.Y. (NCB) 32-9, 32-20, 32-35 Port Orchard Bay, Wash. (NPS) 38-24 Port Orford, Oreg. (NPP) 37-8, 37-28, 37-38 Port Royal Harbor, S.C. (SAN) 7-6, 7-10, 7-13 Port San Luis, Calif. (SPL) 33-23 Port Sanilac Harbor, Mich. (NCE) 31-24, 31-49, 31-67 Port St. Joe Harbor, Fla. (SAM) 10-42, 10-45 Port Townsend, Wash. (NPS) 38-24, 38-30 Port Washington Harbor, Wis. (NCE) 31-24, 31-49, 31-67 Port Wing Harbor, Wis. (NCE) 31-24, 31-49, 31-67 Portage, Pa. (ORP) 26-22 Portage Lake Harbor, Mich. (NCE) 31-23, 31-49, 31-67 Portchester Harbor, N.Y. (NAN) 2-34 Porter Bayou, Miss. (LMK) 12-9, 12-15, 12-18 Portland, Ind. (ORL) 24-20, 24-30 Portland, Ohio (ORH) 25-21 Portland Harbor, Maine (NED) 1-8, 1-26, 1-34 Portneuf River and Marsh Creek, Idaho (NPW) 39-17, 39-18 Portsmouth Harbor, Va. Channel to Nansemond Ordnance Depot (NAO) 5-22 Portsmouth Harbor and Piscataqua River, Maine and N.H. (NED) 1-38 Portsmouth-New Boston, Ohio (ORH) 25-20, 25-22 Portugues and Bucana Rivers, P.R. (SAJ) 9-24, 9-31, 9-42 Portville, N.Y. (ORP) 26-22, 26-26 Posten Bayou, Ark. and La. (LMN) (LMK) 11-22, 12-23, 12-25 Poteau River Navigation, Ark. and Okla. (SWT) 19-15 Poteet Floodway, Tex. (SWF) 16-21 Potomac and Anacostia Rivers, D.C., Collection and Removal of Drift (NAB) 4-7, 4-23, 4-30 Potomac River and Tributaries at and below Washington, D.C., Elimination of Waterchestnut (NAB) 4-34 Potomac River at Alexandria, Va. (NAB) 4-34 Potomac River at Lower Cedar Point, Md. (NAB) 4-34 Potomac River at Mount Vernon, Va. (NAB) 4-34 Potomac River below Washington, D.C. (NAB) 4-34 Potomac River North Side of Washington Channel, D.C. (NAB) 4-34 Potowomut River, R.I. (NED) 1-38 Pottstown and Vicinity, Pa. (NAP) 3-23 Poverty Point, La. (LMN) 12-10, 12-15, 12-18 Powell County High School, Mont. (NPS) 38-27 Power River, Baker, Oreg. (NPW) 39-19 Povhatan Point, Ohio (ORP) 26-22, 26-26 Prado Dam, Calif. (SPL) 33-30 Prairie Du Chien, Wis. (NCS) 27-11, 27-20 Prairie Du Chien Harbor, Wis. (NCD) 29-7 Prairie du Pont Levee and Sanitary District, Ill. (LHS) 14-15 Prairie du Rocher and Vicinity, Ill. (LMS) 14-15 Prattville, Ala. (SAN) 10-43 Pre-Authorization Studies for Beach Erosion Control Activities Baltimore, Md., District (NAB) 4-12 Buffalo, N.Y., District (NCB) 32-13 Chicago, Ill., District (NCC) 30-6 Detroit, Mich., District (NCE) 31-32 Galveston, Tex., District (SWG) 15-8 Jacksonville, Fla., District (SAJ) 9-22 1-43 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Mobile, Ala., District (SAM) 10-12, 10-44 New England Division (NED) 1-45 New York, N.Y., District (NAN) 2-36 Pacific Ocean Division (POD) 36-3 Philadelphia, Pa., District (NAP) 3-10 Savannah, Ga., District (SAS) 8-6 Seattle, Wash., District (NPS) 38-7 Pre-Authorization Studies for Flood Control Activities Alaska District (NPA) 40-6 Albuquerque, N. Mex., District (SWA) 17-8 Baltimore, Md., District (NAB) 4-20 Buffalo, N.Y., District (NCB) 32-38 Charleston, S.C., District (SAN) 7-16 Chicago, Ill., District (NCC) 30-7 Fort Worth, Tex., District (SWF) 16-12, 16-22 Galveston, Tex., District (SWG) 15-11 Huntington, W. Va., District (ORH) 25-11 Jacksonville, Fla., District (SAJ) 9-54 Kansas City, Mo., District (MRK) 20-8, 20-24 Little Rock, Ark., District (SWL) 18-7 18-24 Los Angeles, Calif., District (SPL) 33-31 Louisville, Ky., District (ORL) 24-13, 24-31 Memphis, Tenn., District (LMM) 13-3 Mobile, Ala., District (SAM) 10-44 Nashville, Tenn., District (ORN) 23-6, 23-19 New England Division (NED) 1-46 New Orleans, La., District (LMN) 11-12 New York, N.Y., District (NAN) 2-18 Omaha, Nebr., District (NRO) 21-6, 21-22 Pacific Ocean Division (POD) 36-4 Philadelphia, Pa., District (NAP) 3-12 Pittsburgh, Pa., District (ORP) 26-29 Portland, Oreg., District (NPP) 37-52 Rock Island, Ill., District (NCR) 28-18 Sacramento, Calif., District (SPK) 35-16 San Francisco, Calif., District (SPN) 34-3 Savannah, Ga., District (SAS) 8-7 Seattle, Wash., District (NPS) 38-31 St. Louis, Mo., District (LMS) 14-7 St. Paul, Minn., District (NCS) 27-29 Tulsa, Okla., District (SWT) 19-7, 19-19 Vicksburg, Miss., District (LMK) 12-12 Walla Walla, Wash., District (NPW) 39-2 Wilmington, N.C., District (SAW) 6-31 Pre-Authorization Studies for Navigation Activities Alaska District (NPA) 40-14 Baltimore, Md., District (NAB) 4-11 Buffalo, N.Y., District (NCB) 32-12, 32-36 Charleston, S.C., District (SAN) 7-15 Chicago, Ill., District (NCC) 30-6 Detroit, Mich., District (NCE) 31-31 Galveston, Tex., District (SWG) 15-8 Jacksonville, Fla., District (SAJ) 9-17 Memphis, Tenn., District (LMM) 13-1 Mobile, Ala., District (SAM) 10-12, 10-43 Nashville, Tenn., District (ORN) 23-4 New England Division (NED) 1-45 New Orleans, La., District (LMN) 11-9, 11-21 New York, N.Y., District (NAN) 2-36 Norfolk, Va., District (NAO) 5-9 Pacific Ocean Division (POD) 36-3 Philadelphia, Pa., District (NAP) 3-7 Portland, Oreg., District (NPP) 37-51 San Francisco, Calif., District (SPN) 34-2 Savannah, Ga., District (SAS) 8-6 Seattle, Wash., District (NPS) 38-4 St. Louis, Mo., District (LMS) 14-7 St. Paul, Minn., District (NCS) 27-27 Vicksburg, Miss., District (LMK) 12-5 Walla Walla, Wash., District (NPW) 39-2 Wilmington, N.C., District (SAW) 6-29 Prescott Area, Oreg. (NPP) 37-50 Presque Isle Harbor, Mich. (NCE) 31-25, 31-49, 31-67 Presque Isle Peninsula, Erie, Pa. (NCB) 32-12, 32-21, 32-33 Prestile Stream, Blaine, Maine (NED) 1-42 Preston Drainage and Levee District, Ill. (LMS) 14-15 Prestonburg, Ky. (ORH) 25-22 Prestonville, Ky. (0RL) 24-22, 24-25 Priest, J. Percy, Dam and Reservoir, Tenn. (ORN) 23-7, 23-9, 23-18 Priest Rapids Dam, Wash. (NPS) 38-29 Princeton, W. Va. (ORH) 25-20, 25-22 Prineville Area, Oreg. (NPP) 37-50 Proctor, Vt. (NAN) 2-34 Proctor, W. Va. (ORP) 26-22, 26-26 Proctor Lake, Tex. (SWF) 16-9, 16-15, 16-19 Proctorville, Ohio (ORH) 25-20 Prompton Lake, Pa. (NAP) 3-13, 3-17 Prospect Beach, West Haven, Conn. (NED) 1-41 Providence River and Harbor, R.I. (NED) 1-38 Provincetown Beach (Herring Cove), Mass. (NED) 1-44 1-44 INDEX Provincetown Harbor, Mass. (NED) 1-8, 1-26, 1-34, 1-44 Pudding River, Oreg. (NPP) 37-50 Pueblo Arkansas River, Colo. (Floodway Levee Extension) (SWA) 17-11 Pueblo Reservoir, Colo. (SWA) 17-7 Puerco River and Tributaries, Gallup, N. Mex. (SPL) 33-11 Puget Sound and Its Tributary Waters, Wash. (NPS) 38-5, 38-14, 38-20 Pullman, Palouse, Wash. (NPW) 39-17 Pultneyville Harbor, N.Y. (NCB) 32-35 Pumpkinvine Creek, Emerson, Ga. (SAM) 10-14, 10-28, 10-39 Pungo Creek, N.C. (SAW) 6-27 Pungo River, N.C. (SAW) 6-27 Punta Salinas, P.R. (SAJ) 9-48 Punxsutawney, Pa. (ORP) 26-5, 26-13, 26-18, 26-26 Punxsutawney, Pa. (Allegheny River Basin) (ORP) 26-26 Put In Bay, Ohio (NCB) 32-12, 32-35 Pysht River, Wash. (NPS) 38-27 0Q Quail Wash Levee, Joshua Tree, Calif. (SPL) 33-25, 33-31 Queens Creek, Va. (NAO) 5-23 Queenstown Harbor, Md. (NAB) 4-8, 4-23, 4-30 Queets River, Wash. (NPS) 38-27 Quillayute River, Wash. (NPS) 38-5, 38-14, 38-20, 38-27 Quinault River, Wash. (NPS) 38-27 Quinby Creek, Va. (NAO) 5-23 Quincy, Ill., Harbor Access Channel (NCR) 28-13 Quincy, Mass. (NED) 1-22 Quincy Harbor, Ill. (NCD) 29-8 Quincy Shore Beach, Quincy, Mass. (NED) 1-41 R R. D. Bailey Lake, W. Va. (ORB) 25-9, 25-14, 25-18 Raccoon Creek, N.J. (NAP) 3-21 Raccoon Levee, Ind. (ORL) 24-22, 24-25 Racine, Ohio (ORB) 25-21 Racine Harbor, Wis. (NCE) 31-25, 31-50, 31-67 Racine Locks and Dam, Ohio (ORD) 22-3, 22-8 Rahway, N.J. (NAN) 2-32 Rahway, South Branch, N.J. (NAN) 2-32 Rahway River, N.J. (NAN) 2-34 Rainey, Henry T., Dam, Ill. (NCD) 29-6 Rainier Drainage District, Oreg. (NPP) 37-46, 37-47, 37-54 Rancocas Creek at Mt. Holly, N.J. (NAP) 3-13 Rancocas River, N.J. (NAP) 3-24 Randleman Lake, N.C. (SAW) 6-10, 6-20 Rapid City, Cedar Canyon Dam, S. Dak. (MRO) 21-20 Rapid Creek, Idaho (NPW) 39-4, 39-10, 39-14 Rapid Creek, Rapid City, S. Dak. (MRO) 21-17, 21-20 Rapide Croche Lock and Dam, Wis. (NCE) 31-75 Rappahannock River, Va. (NAO) 5-23 Rappahannock River at Bowlers Wharf, Va. (NAO) 5-23 Rappahannock Shoal Channel, Va. (NAO) 5-2, 5-13, 5-17 Raritan Bay and Sandy Hook Bay, N.J. (NAN) 2-32 Raritan River, N.J. (NAN) 2-11, 2-20, 2-25, 2-34 Raritan River to Arthur Kill Cutoff Channel, N.J. (NAN) 2-30 Rathbun Lake, Iowa (MRK) 20-6, 20-13, 20-17 Rathbun Lake Fish Hatchery (MRK) 20-19 Ravenswood, W. Va. (ORH) 25-20 Ray Roberts Lake, Tex. (SWF) 16-9, 16-15, 16-19 Rayburn, Sam, Dam and Reservoir, Tex. (SWF) 16-12, 16-15, 16-19 Raystown Lake, Pa. (NAB) 4-13, 4-25, 4-33 Red Bank and Fancher Creeks, Calif. (SPK) 35-18 Red Brook Harbor, Bourne, Mass. (NED) 1-38 Red Creek, N.Y. (NCB) 32-37 Red Lake and Red Lake River, Minn. (NCS) 27-23 Red Lake Falls, Minn. (NCS) 27-28 Red Lake River, Minn., including Clearwater River, Minn. (NCS) 27-11, 27-20 Red Lake River at Huot, Minn. (NCS) 27-24, 27-28 Red Lake River at Red Lake Falls, Minn. (NCS) 27-24 Red River, Tenn. (ORN) 23-13 Red River at East Grand Forks, Minn. (NCS) 27-27 Red River at Fargo, N. Dak. (NCS) 27-27 Red River at Grand Forks, N. Dak. (NCS) 27-27 Red River Backwater Levees (MR+T) 42-46, 42-49, 42-52 Red River below Denison Dam including Little River Basin, Okla. and Ark. (SWL) 18-14 I-45 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Red River below Denison Dam, Levees and Bank Stabilization (LMK) (SWT) 12-10, 12-18, 12-23, 19-15 Red River below Denison Dam (Vicksburg District) (LMK) 12-10, 12-23, 12-24 Red River below Fulton, Ark. (LMK) 12-21 Red River Emergency Bank Protection (LMK) 12-4, 12-13, 12-16 Red River from Fulton, Ark., to Mouth of Washita River (SWT) 19-15 Red River in Vicinity of Shreveport, La. (LMN) (LMK) 11-22, 12-24, 12-25 Red River Lake, Ky. (ORL) 24-21 Red River of the North, Minn. and N. Dak. (NCS) 27-23 Red River of the North, Argusville, N. Dak. (NCS) 27-12, 27-20 Red River of the North at Oslo, Minn. (NCS) 27-24 Red River of the North at Pembina, N. Dak. (NCS) 27-24 Red River of the North Drainage Basin, Minn., S. Dak. and N. Dak. (NCS) 27-12, 27-21, 27-27 Red River of the North, Halstad, Minn. (NCS) 27-13, 27-21 Red River Parish, La. (LMN) (LMK) 11-22, 12-24, 12-25 Red River Standard Revetments (MR+T) 42-37 Red River Waterway, La., Ark., Okla., and Tex. (LMK) 12-21 Red River Waterway-Mississippi River to Shreveport, La. (LMK) 12-4, 12-13, 12-16 Red River Waterway, Shreveport, La., to Daingerfield, Tex. (LMK) 12-21 Red River Waterway-Shreveport, La., to Index, Ark. (LMK) 12-11, 12-15, 12-18 Red Rock Dam and Lake Red Rock, Iowa (NCR) 28-5, 28-9, 28-12 Red Run Drain-Lower Clinton River, Mich. (NCE) 31-78 Red Wing Harbor, Minn. (NCD) 29-7 Redbank and Fanches Creeks, Calif. (SPK) 35-18 Redbank Creek Lake, Pa. (ORP) 26-23 Reddies River Lake, N.C. (SAN) (SAW) 6-27, 7-16 Redmond, John, Dam and Reservoir, Kans. (SWT) 19-4, 19-10, 19-13 Redondo Beach Harbor (King Harbor), Calif. (SPL) 33-23 Redwater River and Hay Creek, S.D. (MRO) 21-18 Redwood City Harbor, Calif. (SPN) 34-5 Redwood Creek, Humboldt County, Calif. (SPK) 35-29 Redwood River at Marshall, Minn. (NCS) 27-13, 27-21 Redwood River below Marshall, Minn. (NCS) 27-24, 27-28 Reeds Bay Small Boat Harbor, Hawaii (POD) 36-10 Reedsport Levees, Oreg. (NPP) 37-48 Reedy River, S.C. (SAN) 7-16 Reelfoot Lake-Lake No. 9, Tenn. and Ky. (MR+T) 42-9, 42-18, 42-28 Reese River, Battle Mountain, Nev. (SPK) 35-29 Reevesville, Ill. (ORL) 24-20, 24-24, 24-29 Regulation of Hydraulic Mining and Preparation of Plans (CDC) 44-1, 44-5, 44-6 Regulatory and Sunken Vessel Removal and National Emergency Preparedness Activities 48-1 Rehoboth Beach to Indian River Inlet, Del. (NAP) 3-23 Removal of Aquatic Growth, La. (LMN) 11-21 Removal of Aquatic Growth from Navigable Waters in the State of Florida (SAJ) 9-13, 9-29, 9-37, 9-46 Removal of Sunken Vessels 48-1 Removing Snags and Wrecks from Mississippi River below Mouth of Missouri River and from Old and Atchafalaya Rivers (LMK) (LMM) 12-21, 13-6 Removing Water Hyacinths, Mobile District (SAM) 10-42 Rend Lake, Ill. (LMS) 14-7, 14-10, 14-12 Reno Beach-Howard Farms Area, Ohio (NCB) 32-15, 32-37 Republican River, Neb. and Kan. (MRK) 20-22 Reservoirs at Headwaters of Mississippi River, Minn. (NCS) 27-2, 27-19, 27-22, 27-26 Restoration of Indian Fishing Grounds, Bonneville, Oreg. (NPP) 37-50 Revere Beach, Mass. (NED) 1-9, 1-27, 1-35 Reynoldsville, Pa. (ORP) 26-22 Rheem Creek, Calif. (SPK) 35-29 Rhodes Point to Tylerton, Md. (NAB) 4-8, 4-23, 4-30 Rice Creek, Fla. (SAJ) 9-46, 9-47 Richard B. Russell Dam and Lake, Ga. and S.C. (Formerly Trotters Shoals Lake) (SAS) 8-9, 8-12, 8-15 Richland Creek, Ill. (LMS) 14-15 Richland Lake, Mo. (MRK) 20-20 1-46 INDEX Richmond Filtration Plant, Va. (NAO) 5-10, 5-16, 5-20 Richmond Harbor, Calif. (SPN) 34-5 Richmond Harbor, Maine (NED) 1-38 Richmond's Island Harbor, Maine (NED) 1-38 Richwood and Fenwick, W. Va. (ORH) 25-22 Ridgecrest, Calif. (SPL) 33-25 Ridgeley, W.Va. (NAB) 4-39 Ridgway, Pa. (Allegheny River Basin) (ORP) 26-26 Ridgway, Pa. (Elk Creek) (ORP) 26-22 Ridgway and Vicinity, Pa. (On Clarion River) (ORP) 26-22 Right and Left Forks of Beaver Creek, Ky. (ORH) 25-22 Rio Grande Basin, N. Mex. (SWA) 17-3, 17-9, 17-10, 17-11 Rio Grande Floodway, N. Mex. (SWA) 17-5, 17-9, 17-10, 17-11 Ripley, Ohio (ORH) 25-21 Ripley, W. Va. (ORH) 25-22 Ririe Lake, Idaho (NPW) 39-17 Rising Sun, Ind. (ORL) 24-22, 24-25 River Rouge, Mich. (NCE) 31-78 Riverdale, Mass. (NED) 1-42, 1-48 Riverland Levee District, Mo. (LMS) 14-15 Riverside Area, Pasco, Wash. (NPW) 39-17 Riverside levees, Santa Ana River Basin, Calif. (SPL) 33-31 Riverview, W. Va. (ORH) 25-21 Roanoak Lake, Tex. (SWF) 16-21 Roanoke River, N.C. (SAW) 6-25 Roanoke River Basin, Va. and N.C. (SAW) 6-14, 6-30 Roaring River, N.C. (SAN) 7-16 Roaring River Lake, N.C. (SAW) 6-27 Robert F. Henry Lock and Dam, Ala. (SAM) 10-20, 10-30 Robert S. Kerr Lock and Dam, Okla. (SWL) (SWT) 18-19, 19-7, 19-12, 19-14, 19-16 Robert S. Kerr Marine Terminal, Sallisaw, Okla. (SWT) 19-16 Roberts, Ray, Lake, Tex. (SWF) 16-9, 16-15, 16-19 Rochester and McCleary's Bluff Levee, Ill. (ORL) 24-20, 24-24, 29-29 Rochester, Minn. (NCS) 27-14, 27-21 Rochester, Pa. (ORP) 26-22, 26-26 Rochester Harbor, N.Y. (NCB) 32-10, 32-20, 32-31 Rochester Lake, Iowa (NCR) 28-16 Rock Creek, Mont. (NPS) 38-27 Rock Hall Harbor, Md. (NAB) 4-34 Rock Island, Ill. (NCR) 28-15, 28-17 Rock Island District (NCD) 29-4 Rock Island Harbor, Ill. (NCD) 29-7 Rock River Agricultural Levees, Ill. (NCR) 28-15 Rockfish Creek, N.C. (SAW) 6-28 Rockford, Ill. (NCR) 28-5, 28-9, 28-12 Rockland Harbor, Maine (NED) 1-38 Rockland Lake, Tex. (SWF) 16-12, 16-19 Rockport, Ind. (ORL) 24-22, 24-25 Rockport Harbor, Maine (NED) 1-38 Rockport Harbor, Mass. (NED) 1-38 Rocky Ford Drainage and Levee District, Ill. (NCR) 28-15 Rocky Fork, Ohio (ORH) 25-21 Rocky Pass, Alaska (NPA) 40-12 Rocky River Harbor, Ohio (NCB) 32-10, 32-20, 32-32 Rodeo Creek, Calif. (SPK) 35-29 Rogers City Harbor, Mich. (NCE) 31-79 Rogue River, Oreg. (NPP) 37-48 Rogue River Harbor at Gold Beach, Oreg. (NPP) 37-8, 37-28, 37-38 Roland Drainage District, Arkansas River, Ark. (SWL) 18-16 Rollinson Channel, N.C. (SAW) 6-25, 6-29 Rome, Ga. (SAM) 10-43 Rome, Ind. (ORL) 24-22, 24-25 Rome, N.Y. (NAN) 2-34 Rondout Harbor, N.Y. (NAN) 2-30 Root Creek, Bolivar, N.Y. (ORP) 26-5, 26-13 Rose Creek Channel Improvements, San Diego, Calif. (SPL) 33-25, 33-31 Roseau River, Minn. (NCS) 27-14, 27-21 Rosedale Harbor, Miss. (LMK) 12-5, 12-13, 12-17 Rosendale, N.Y. (NAN) 2-32 Roseville, Ohio (ORH) 25-9, 25-15, 25-18, 25-22 Rosiclare, Ill. (ORL) 24-20, 24-29 Rossview Reservoir, Ohio River Basin, Tenn. and Ky. (ORN) 23-13, 23-18 Rota Harbor, Northern Marianas (POD) 36-2, 36-6 Rouge River, Mich. (NCE) 31-25, 31-50, 31-68, 31-79 Rough River, Ky. (ORL) 24-19, 24-24, 24-30 Rough River Lake and Channel Improvements, Ky. (ORL) 24-10, 24-16, 24-27 Rouses Point, Lake Champlain, N.Y. (NAN) 2-30 Rouseville, Pa. (ORP) 26-22 Rowlesburg Lake, W. Va. (ORP) 26-22 Royal River, Maine (NED) 1-8, 1-26, 1-34 Ruby River, Wheatly Bridge, near Twin Bridges, Mont. (MRO) 21-19 Ruffy Brook, Minn. (NCS) 27-25 I-47 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Rufus Woods Lake, Wash. (NPS) 38-10, 38-16, 38-22 Rush River, N. Dak. (NCS) 27-27, 27-28 Rushford, Minn. (NCS) 27-24 Russell, Ky. (ORH) 25-20, 25-22 Russell and Allison Levee, Ill. (ORL) 24-20, 24-24 Russell, Richard B., Dam and Lake, Ga. and S.C. (SAS) 8-9, 8-12, 8-15 Russian River Basin, Calif. (SPK) 35-11, 35-22, 35-26, 35-32, 35-33 Rutland, Otter Creek, Vt. (NAN) 2-32 Rutledge Hollow Creek Channel Improvement, Poteet, Tex. (SWF) 16-21 Rye Creek, Mont. (NPS) 38-27 Rye Harbor, N.H. (NED) 1-38 S Sabine-Neches Waterway, Tex. (SWG) 15-6, 15-13, 15-21, 15-27, 15-29, 15-33 Sabine River and Tributaries, Tex. (Echo to Morgan Bluff) (SWG) 15-26 Sabula, Iowa (NCR) 28-15, 28-17 Sackets Harbor, N.Y. (NCB) 32-12, 32-35, 32-39 Saco, Mont. (MRO) 21-17, 21-19 Saco River, Maine (NED) 1-8, 1-26, 1-33, 1-44 Sacramento River, Calif. (CDC) 44-3, 44-5, 44-6, 44-7 Sacramento River, Calif. (SPK) 35-1, 35-21, 35-26, 35-31 Sacramento River and Tributaries, Calif. (CDC) 44-2, 44-5 Sacramento River and Tributaries, Calif., from Collinsville to Shasta Dam (SPK) 35-12, 35-22, 35-26, 35-33, 35-34 Sacramento River Deep Water Ship Channel, Calif. (SPK) 35-20, 35-25 Sacred Heart Hospital, Yankton, S. Dak. (MRO) 21-17, 21-20 Sag Harbor, N.Y. (NAN) 2-30 Saginaw River, Mich. (NCE) 31-26, 31-33, 31-50, 31-53, 31-68, 31-72 Saint John River Basin, Maine (NED) 1-20 Saipan Small Boat Harbor, Northern Marianas (POD) 36-10 Sakonnet Harbor, R.I. (NED) 1-38, 1-44 Sakonnet River, R.I. (NED) 1-38 Salamanca, N.Y. (ORP) 26-22 Salamonie Lake, Ind. (ORL) 24-11, 24-16 Salem Church Lake, Va. (NAO) 5-23 Salem Harbor, Mass. (NED) 1-38 Salem River, N.J. (NAP) 3-8, 3-16, 3-20 Salina, Kans. (MRK) 20-19, 20-21 Salinas River, Calif. (SPK) 35-29 Saline Point, La. (LMN) (LMK) 11-22, 12-24, 12-25 Saline River, Ark. (LMK) 12-21 Saline River and Tributaries, Ill. (ORL) 24-20, 24-30 Salisbury, Conn. (NED) 1-22, 1-49 Salkahatchie River, S.C. (SAN) 7-15 Salmon Creek at Oakridge, Oreg. (NPP) 37-48 Salmon Creek near Vancouver, Wash. (NPP) 37-18, 37-31, 37-42 Salmon River, Alaska (NPA) 40-6, 40-13 Salmon River, Oreg. (NPP) 37-45 Salmon River, Colchester, Conn. (NED) 1-42, 1-48 Salt Creek, Ohio (0RH) 25-20 Salt Creek and Tributaries, Nebr. (MRO) 21-6, 21-11, 21-15 Salt Creek, Barnard, Kans. (MRK) 20-19 Salt Lake City, Jordan River, Utah (SPK) 35-29 Saluda River, S.C. (SAN) 7-16 Salyersville, Ky. (ORL) 24-21 Sam Rayburn Dam and Reservoir, Tex. (SWF) 16-12, 16-15, 16-19 Sammamish River, Wash. (NAS) 38-27 San Antonio Channel Improvement, Tex. (SWF) 16-9, 16-16, 16-19 San Antonio Dam, Calif. (SPL) 33-30 San Antonio Floodway, Tex. (SWF) 16-21 San Diego Creek, Alice, Tex. (SWG) 15-26 San Diego Harbor, Calif. (SPL) 33-3, 33-13, 33-19 San Diego River and Mission Bay, Calif. (SPL) 33-3, 33-13, 33-20 San Diego River (Mission Valley), Calif. (SPL) 33-25, 33-31 San Diego (Sunset Cliffs), Calif. (SPL) 33-24 San Francisco Bay and Delta Model, Calif. (SPN) 34-2, 34-5 San Francisco Bay to Stockton, Calif. (John F. Baldwin and Stockton Ship Channels) (SPK) (SPN) 34-2, 34-5, 35-2, 35-21 San Francisco Harbor, Calif. (SPN) 34-5, 34-7 San Francisco Harbor and Bay (Removal of Drift), Calif. (SPN) 34-5 San Francisco Marina (Gas House Cove), Calif. (SPN) 34-7 San Gabriel River, Tex. (SWF) 16-10, 16-16, 16-19 1-48 INDEX San Gabriel River to Newport Bay (Surfside-Sunset and Newport Beach), Calif. (SPL) 33-4, 33-14, 33-20 San Jacinto River Levee and Bautista Creek Channel, Calif. (SPL) 33-8, 33-16, 33-22, 33-31 San Joaquin River, Calif. (SPK) 35-3, 35-21, 35-31, 35-32 San Juan, P.R. (SAJ) 9-48 San Juan Dam, Calif. (SPL) 33-30 San Juan Harbor, P.R. (SAJ) 9-15, 9-29, 9-38, 9-46 San Leandro Creek, Calif. (SPK) 35-29 San Leandro Marina, Calif. (SPN) 34-2, 34-5 San Leandro Marina (Breakwater), Calif. (SPN) 34-7 San Lorenzo Creek, Calif. (SPK) (SPN) 34-8, 35-29 San Lorenzo River, Calif. (SPK) 35-29 San Luis Rey River, Calif. (SPL) 33-25 San Pablo Bay and Mare Island Strait, Calif. (SPN) 34-5, 34-8 San Rafael Creek, Calif. (SPN) 34-7 Sand Creek Channel Improvement, Kans. (SWT) 19-15, 19-17 Sand Hill Cove Beach, R.I. (NED) 1-41 Sand Hill River, Minn. (NCS) 27-27, 27-28 Sand Island, Hawaii (POD) 36-11 Sand Lake, Okla. (SWT) 19-15 Sandburg Creek, Spring Glen, N.Y. (NAN) 2-32, 2-36 Sandusky Harbor, Ohio (NCB) 32-10, 32-20, 32-32 Sandusky River, Ohio (NCB) 32-35 Sandy Bay, Cape Ann, Mass. (NED) 1-44 Sandy Bay (Harbor of Refuge), Cape Ann, Mass. (NED) 1-38 Sandy Creek, Jackson, Tenn. (LMM) 13-3, 13-4, 13-5 Sandy Drainage District, Oreg. (NPP) 37-47, 37-54 Sandy Hook Bay, N.J. (NAN) 2-12, 2-20, 2-26 Sandy Hook Bay at Leonardo, N.J. (NAN) 2-30 Sandy Lake Reservoir, Minn. (NCS) 27-26 Sandy River and Sleepy Lake, Oreg. (NPP) 37-48 Sanford Reservoir (Lake Meredith), Okla. (SWT) 19-18 Sangamon River (Mouth), Ill. (NCR) 28-15 Sanitary District of Beardstown, Ill. (NCR) 28-17 Sans Bois Navigation Channel, Okla. (SWT) 19-16 Santa Ana River Basin (and Orange County), Calif. (SPL) 33-8, 33-16, 33-22, 33-25, 33-30 Santa Ana River Basin, Calif.: Devil, East Twin, and Warm Creeks Channel Improvements (SPL) 33-25 Santa Ana River Main Stem, Calif. (SPL) 33-11 Santa Barbara Harbor, Calif. (SPL) 33-4, 33-14, 33-20 Santa Clara River Levee Improvement, Calif. (SPL) 33-25 Santa Cruz County, Calif. (SPN) 34-7 Santa Cruz Harbor, Calif. (SPN) 34-5 Santa Fe River and Arroyo Mascaras, N. Mex. (SWA) 17-11 Santa Maria Valley Levees, Calif. (SPL) 33-25 Santa Paula Creek Channel and Debris Basins (including Mud Creek), Calif. (SPL) 33-25 Santa Rosa Dam and Lake, N. Mex. (SWA) 17-5, 17-9 Santa Rosa Wash (at Momolikot Dam and Lake St. Clair), Ariz. (SPL) 33-25 Santee River, N.C. and S.C. (SAN) 7-7, 7-15 Sapelo Harbor, Ga. (SAS) 8-16 Sardis, Ohio (ORH) 25-21 Sardis Lake, Miss. (MR+T) 42-20, 42-59 Sardis Lake, Okla. (SWT) 19-6, 19-11, 19-14 Sasanoa River, Maine (NED) 1-39 Sasco Hill Beach, Fairfield, Conn. (NED) 1-41 Satilla River, Ga. (SAS) 8-16 Saugatuck Harbor and Kalamazoo River, Mich. (NCE) 31-29, 31-51, 31-70 Saugerties Harbor, N.Y. (NAN) 2-30 Sauk River, Wash. (NPS) 38-27 Sauquoit Creek, Whitesboro, N.Y. (NAN) 2-36 Sauvie Island Drainage District, Oreg. (NPP) 37-46, 37-47, 37-54 Savage, Md. (NAB) 4-39 Savage River Dam, Md. (NAB) 4-36 Savanna Harbor, Ill. (NCD) 29-7 Savannah Harbor, Ga. (SAS) 8-4, 8-11, 8-14 Savannah River above Augusta, Ga. (SAS) 8-16 Savannah River at Augusta, Ga. (SAS) 8-16 Savannah River Basin, Ga. and S.C. (SAS) 8-8, 8-17 Savannah River below Augusta, Ga. (SAS) 8-5, 8-11, 8-15 Saw Mill River at Elmsford and Greenburgh, N.Y. (NAN) 2-17, 2-21, 2-27 Sawmill Branch, S.C. (SAN) 7-8, 7-16 Saxon Harbor, Wis. (NCE) 31-29, 31-51, 31-70 I-49 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Saxonville, Mass. (NED) 1-22, 1-42, 1-50 Sayers, Foster Joseph, Dam, Pa. (NAB) 4-19, 4-27 Saylorville Lake, Iowa (NCR) 28-5, 28-9, 28-12 Scajaquada Creek, N.Y. (NCB) 32-16, 32-22 Scappoose Drainage District, Oreg. (NPP) 37-46, 37-54 Scarboro River, Maine (NED) 1-39 Schuyler, Nebr. (MRO) 21-20 Schuylkill River, Pa. (NAP) 3-9, 3-16, 3-20 Schuylkill River above Fairmount Dam, Pa. (NAP) 3-21 Scioto River at Portsmouth, Ohio (ORB) 25-19 Sciotoville, Ohio (ORB) 25-21 Scituate, Mass. (NED) 1-22 Scituate Harbor, Mass. (NED) 1-39 Scott, V. Kerr, Dam and Reservoir, N.C. (SAW) 6-13, 6-16, 6-20 Scott County Drainage and Levee District, Ill. (LMS) 14-15 Scotts Creek, Va. (NA0) 5-19 Scottsville, Va. (NA0) 5-10, 5-16, 5-20 Scranton, Pa. (NAB) 4-36, 4-39 Scranton, Buffalo, N. Dak. (MRO) 21-20 Scuppernong River, N.C. (SAW) 6-13, 6-20, 6-25 Sea Bright to Ocean Township, N.J. (NAN) 2-14, 2-21, 2-26 Seahorn Drainage and Levee District, Ill. (NCR) 28-15, 28-17 Searsport Harbor, Maine (NED) 1-39 Seaside Park, Conn. (NED) 1-41 Seattle Harbor, Wash. (NPS) 38-5, 38-14, 38-20 Sebasticook River, Hartland, Maine (NED) 1-20, 1-30, 1-36 Sebevaing, Mich. (NCE) 31-34, 31-72 Sebewaing River, Mich. (NCE) 31-53, 31-77 Seekonk River, R.I. (NED) 1-39 Seldovia Harbor, Alaska (NPA) 40-12 Selkirk Shore State Park, N.Y. (NCB) 32-36 Sergius Whitestone, Alaska (NPA) 40-12 Sespe Creek at Fillmore, Calif. (SPL) 33-26 Sesuit Harbor, Mass. (NED) 1-39 Sevier River near Redmond, Utah (SPK) 35-29 Sewage Lagoons, Vale, Oreg. (NPW) 39-4, 39-10, 39-14 Sevage Treatment Plant, Missoula, Mont. (NPS) 38-27 Seward, Nebr. (MRK) 20-19 Seward Harbor, Alaska (NPA) 40-12 Sewerline Protection, Valley, Ala. (SAM) 10-14, 10-29, 10-39 Shad Landing State Park, Md. (NAB) 4-34 Shallotte River, N.C. (SAW) 6-25 Shark River, N.J. (NAN) 2-30 Shawneetown, Ill. (ORL) 24-21, 24-24, 24-29 Sheboygan Harbor, Wis. (NCE) 31-29, 31-52, 31-71 Sheepshead Bay, N.Y. (NAN) 2-30, 2-35 Sheffield, Mass. (NED) 1-22, 1-49 Sheffield Lake Community Park, Ohio (NCB) 32-39 Shelburne, N.H. (NED) 1-22, 1-42 Sheldon Brook, Tarrytown, N.Y. (NAN) 2-36 Shell Creek, Nebr. (MRO) 21-18 Shelley Area, Idaho (NPW) 39-17, 39-18 Shelton Creek, Wash. (NAS) 38-27 Shelton Ditch, Oreg. (NPP) 37-48 Shenango River Lake, Pa. and Ohio (ORP) 26-9, 26-14, 26-20 Shepard Road, St. Paul, Minn. (NCS) 27-14, 27-21 Sherburne, N.Y. (NAB) 4-39 Sheridan, Wyo. (MRO) 21-17, 21-19 Sherwood Island State Park, Conn. (NED) 1-41 Sheyenne River, N. Dak. (NCS) 27-15, 27-21, 27-25, 27-28 Shidler Lake, Okla. (SWT) 19-15 Shields River, near Clyde Park, Mont. (MRO) 21-17, 21-19 Shilshole Bay, Seattle, Wash. (NPS) 38-24, 38-30 Shinnecock Inlet, N.Y. (NAN) 2-12, 2-21, 2-26, 2-35 Shipyard River, S.C. (SAN) 7-6, 7-10, 7-13 Shoal Harbor and Compton Creek, N.J. (NAN) 2-30 Shoals, Ind. (ORL) 24-22 Shobe Canyon, Oreg. (NPW) Shooters Island, N.Y. and Shoreline Erosion Control Philadelphia, Pa. (NAP) Shoreline Erosion Control Authorization 39-17 N.J. (NAN) 2-30 Demonstration, 3-10 Work Under Special Philadelphia, Pa., District (NAP) 3-10 Pittsburgh, Pa., District (ORP) 26-29 Short Beach, Conn. (NED) 1-41 Shoshone River, Bank Protection, Lovell, Wyo. (MRO)21-17, 21-19 Shoshone River, Lovell, Wyo. (MRO) 21-17, 21-19 Shot Pouch Creek, S.C. (SAN) 7-8, 7-16 Shrewsbury River, N.J. (NAN) 2-12, 2-21, 2-26 Shufflebarger Levee, Ind. (0RL) 24-22, 24-25 Sid Simpson Project, Ill. (NCR) 28-15 I-50 INDEX Silver Beach to Cedar Beach, Conn. (NED) 1-41 Silver Lake Harbor, N.C. (SAW) 6-8, 6-19, 6-23 Simmons Bay, N.C. (SAW) 6-27 Simpson Creek, S.C. (SAN) 7-8, 7-16 Sioux City, Iowa (MRO) 21-21 Sioux Falls, S. Dak. (MRO) 21-17, 21-20 Sistersville, Ohio (ORH) 25-21 Sitka Harbor, Alaska (NPA) 40-12 Siuslaw River, Oreg. (NPP) 37-9, 37-29, 37-38, 37-48 Six Runs Creek, N.C. (SAW) 6-28 Sixes Bridge Lake, Md. and Pa. (N) 4-37 Skaggs Ferry, Black River, Ark. (SWL) 18-16 Skagit River, Wash. (NPS) 38-24, 38-27, 38-29 Skagit River, Wash. (Avon By-Pass) (NPS) 38-27 Skagit River, Wash. (Levee and Channel Improvements) (NPS) 38-27 Skagway Harbor, Alaska (NPA) 40-12 Skagway River, Alaska (NPA) 40-13 Skamokava Creek, Wash. (NPP) 37-9, 37-29, 37-38, 37-50 Skamokava Creek Area, Wash. (NPP) 37-46 Skiatook Lake, Okla. (SWT) 19-6, 19-11, 19-14 Skipanon Channel, Oreg. (NPP) 37-9, 37-29, 37-38 Slate Creek, Idaho (NPW) 39-19 Slaughter Creek, Md. (NAB) 4-34 Slovan, Pa. (ORP) 26-22 Small Boat Harbor Opposite Chester, Ill. (LMS) 14-13 Small Boat Harbor Opposite Hamburg, Ill. (LMS) 14-13 Small Navigation Project at Sioux City, Iowa (MRO) 21-16 Smelt Brook, Mass. (NED) 1-42 Smith Creek, Colo. (SWA) 17-6, 17-9, 17-10 Smith Creek, Md. (NAB) 4-35 Smith Creek, Pamlico County, N.C. (SAW) 6-25 Smith River, Oreg. (NPP) 37-45 Smithfield, W. Va. (ORB) 25-22 Smithland, Ky. (ORL) 24-21, 24-24 Smithland Locks and Dam, Ky. (ORD) 22-3, 22-9 Smiths Creek (Wilmington), N.C. (SAW) 6-25 Smiths Ferry, Pa. (ORP) 26-23 Smithville Channel, Little Platte River, Mo. (MRK) 20-19 Smithville Lake, Mo. (MRK) 20-7, 20-13, 20-17 Smoky Hill, Saline, and Solomon Rivers (MRK) 20-22 Smyrna River, Del. (NAP) 3-21, 3-24 Snagging and Clearing Activities Buffalo, N.Y., District (NCB) 32-38 Charleston, S.C., District (SAN) 7-7 Huntington, W.Va., District (ORB) 25-11 Louisville, Ky., District (ORL) 24-13, 24-31 Mobile, Ala., District (SAM) 10-18 New England Division (NED) 1-23 Rock Island, Ill., District (NCR) 28-18 Sacramento, Calif., District (SPK) 35-16 Tulsa, Okla., District (SWT) 19-19 Vicksburg, Miss., District (LMK) 12-11 Walla Walla, Wash., District (NPW) 39-3 Snake River, Idaho (NPW) 39-17 Snake River, Minn. (NCS) 27-29 Snake River Downstream from Johnson Bar Landing, Oreg., Wash., and Idaho (NPW) 39-8, 39-11, 39-15, 39-24 Snettisham, Alaska (NPA) 40-6, 40-9, 40-11 Snohomish River, Wash. (NPS) 38-27 Snoqualmie River, Wash. (NPS) 38-27 Sny Basin, Ill. (NCR) 28-15, 28-17 Sny Island Levee Drainage District, Ill. (NCR) 28-15, 28-17 Soap Creek, Wash. (NPP) 37-50 Socorro Diversion Channel, Tributaries of Rio Grande, N. Mex. (SWA) 17-11 Soldier Creek, Idaho (NPW) 39-19 Soleduck River Bridge, Wash. (NPS) 38-27 Somerville Lake, Tex. (SWF) 16-10, 16-16, 16-19 Sonoma Creek, Calif. (SPK) 35-29 Sope Creek, Marietta, Ga. (SAM) 10-15, 10-29, 10-39 South Amsterdam, Mohawk River, N.Y. (NAN) 2-32 South Bank Arkansas River, (Head Fourche Island to Pennington Bayou), Ark. (SWL) 18-16 South Bank Arkansas River, Little Rock to Pine Bluff, Ark. Tucker Lakes (SWL) 18-16 South Beardstown and Valley Drainage and Levee District, Ill. (NCR) 28-15 South Beardstown Drainage and Levee District, Ill. (NCR) 28-15, 28-17 South Beloit, Ill. (NCR) 28-15 South Bristol Harbor, Maine (NED) 1-39 South Channel, Government Island, Oreg. (NPP) 37-10, 37-29, 37-39 South Coventry Lake, Conn. (NED) 1-44 South Creek, N.C. (SAV) 6-27 South Deer Creek Levee, Okla. (SWT) 19-17 South Ellenville, N.Y. (NAN) 2-32 South Fork, Boise River, Idaho (NPV) 39-4, 39-10, 39-14 1-51 REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1985 South Fork, Clearvater River, Idaho (NPW) 39-17, 39-18 South Fork of Cumberland River, Ky. (ORN) 23-13 South Fork of the Santa Clara River, Calif. (SPL) 33-9, 33-16, 33-22 South Haven Harbor, Mich. (NCE) 31-30, 31-52, 31-71 South Milwaukee Harbor, Wis. (NCE) 31-79 South Orange, N.J. (NAN) 2-32 South Platte River, Bank Protection, Denver, Colo. (MRO) 21-17, 21-20 South Platte River Basin, Colo. (MRO) 21-6, 21-15 South Platte River Levees and Channel Improvements, Chatfield Lake to Ft. Morgan, Colo. (MRO) 21-17 South Plymouth Lake, N.Y. (NAB) 4-38 South Point, Ohio (ORH) 25-20 South Portsmouth, Ky. (ORH) 25-20 South Quincy Drainage and Levee District, Ill. (NCR) 28-7, 28-9, 28-15, 28-17 South River, N.C. (SAW) 6-25 South River Drainage District, Mo. (NCR) 28-15, 28-17 South Slough (Charleston), Oreg. (NPP) 37-45 South Tunbridge Lake, Vt. (NED) 1-44 South Williamson, Ky. (0RH) 25-22 South Williamsport, Pa. (NAB) 4-39 Southern Branch, Va. (NAO) 5-19 Southern New York Flood Control Projects (NAB) 4-13, 4-33 Southport Beach, Conn. (NED) 1-41 Southport Harbor, Conn. (NED) 1-39 Southwest Harbor, Maine (NEO) 1-39 Southwestern Jefferson County, Ky. (ORL) 24-5, 24-14 Sowashee Creek, Meridian, Miss. (SAM) 10-43 Spanish Fork River, Utah (SPK) 35-31 Spewrell Bluff Lake, Ga. (SAM) 10-23, 10-30, 10-41 Spirit Lake, Wash. (NPP) 37-15 Spokane, Wash. (NAS) 38-27 Spring City, Tenn. (ORN) 23-19 Spring Lake Drainage and Levee District, Ill. (NCR) 28-15, 28-17 Springdale, Mass. (NED) 1-42, 1-48 Springer, William L., Lake, Ill. (NCR) 28-15 Springfield, Mass. (NED) 1-22, 1-43, 1-48 Springfield, S.D., Water Intake (MRO) 21-18 Squantz Pond, New Fairfield, Conn. (NED) 1-22, 1-43, 1-49 Squaw Chute at Quincy, Ill. (NCR) 28-13 St. Albans Harbor, Lake Champlain, Vt. (NAN) 2-30 St. Anthony Falls, Lover Lock and Dam, Minn. (NCD) 29-5, 29-9. St. Anthony Falls, Upper Lock, Minn. (NCD) 29-5 St. Augustine Harbor, Fla. (SAJ) 9-14, 9-29, 9-38 St. Catherines Sound, Md. (NAB) 4-34, 4-38 St. Clair River, Mich. (NCE) 31-27, 31-51, 31-68, 31-73, 31-79 St. Croix River, Maine (NED) 1-38 St. Croix River, Minn. and Wis. (NCS) 27-3, 27-19, 27-22 St. Francis and L'Anguille Rivers and Blackfish Bayou, Ark. (LMM) 13-6 St. Francis Basin, Ark. and Mo. (MR+T) 42-9, 42-28, 42-53 St. Francis River and Basin, Ark. and Mo. (MR+T) 42-9, 42-18 St. Francis River, Highway 90, Ark. (LMM) 13-3, 13-4, 13-5 St. Francis River Levees (MR+T) 42-48, 42-49 St. George Creek, Md. (NAB) 4-9, 4-23, 4-31, 4-35 St. James, Beaver Island, Mich. (NCE) 31-77 St. Jeromes Creek, Md. (NAB) 4-35 St. Johns River, Fla. (SAJ) 9-46 St. Johns River, Fla., Jacksonville to Lake Harney (SAJ) 9-14, 9-29, 9-38, 9-46 St. Jones River, Del. (NAP) 3-21, 3-22 St. Joseph Harbor, Mich. (NCE) 31-27, 31-51, 31-69 St. Joseph River, Mich. (NCE) 31-77 St. Louis County Drainage and Levee District No. 1, Mo. (LMS) 14-15 St. Louis District (NCD) 29-4 St. Lucie Inlet, Fla. (SAJ) 9-15, 9-29, 9-38 St. Maries, Idaho (NAS) 38-27 St. Marks River, Fla. (SAM) 10-42, 10-45 St. Marys, Pa. (ORP) 26-23 St. Marys, W. Va. (ORH) 25-21 St. Marys River, Ga. and Fla., and North River, Ga. (SAS) 8-16 St. Marys River, Mich. (NCE) 31-28, 31-51, 31-69, 31-74, 31-79 St. Michael Canal, Alaska (NPA) 40-12 St. Michaels Harbor, Md. (NAB) 4-35 St. Patricks Creek, Md. (NAB) 4-9, 4-23, 4-31 St. Paul, Minn. (NCS) 27-28 St. Paul and South St. Paul, Minn. (NCS) 27-24 St. Paul District (NCD) 29-4 1-52 INDEX St. Paul Harbor, Minn. (NCD) 29-7 St. Peters Creek, Md. (NAB) 4-35 St. Petersburg Harbor, Fla. (SAJ) 9-46, 9-47 St. Thomas Harbor, V.I. (SAJ) 9-47 Ste. Genevieve County Drainage and Levee District No. 1, Mo. (LMS) 14-15 Stamford, Conn. (NED) 1-20, 1-22, 1-30, 1-36 Stamford Barrier, Conn. (NED) 1-23 Stamford Harbor, Conn. (NED) 1-39, 1-44 Starlings Creek, Va. (NAO) 5-23 Startup, Wash. (NAS) 38-27 Starved Rock Lock and Dam, Ill. (NCC) 28-20 State Highway 101 and 401, Wash. (NPP) 37-18, 37-31, 37-42 State Road and Ebner Coulees, Wis. (NCS) 27-15, 27-21 Staten Island, N.Y. (NAN) 2-32 Staten Island Rapid Transit Railway Co. Bridge Across Arthur Kill, N.Y. (NAN) 2-30 Steinhatchee Riv -, Fla. (SAJ) 9-47 Stewart Canyon Deoris Basin and Channel, Calif. (SPL) 33-26 Stikine River, Alaska (NPA) 40-5, 40-9, 40-11 Stillaguamish River, Wash. (NPS) 38-9, 38-15, 38-21, 38-24, 38-28 Stillhouse Hollow Dam, Tex. (SWF) 16-11, 16-16, 16-20 Stillwater Lake, Pa. (NAB) 4-17, 4-26, 4-33 Stillwater River, Mont. (NPS) 38-28 Stillwell Drainage District, Oreg. (NPP) 37-48 Stillwell Location, Boise River, Idaho (NPW) 39-19 Stockton and Mormon Channels, Calif. (SPK) 35-28 Stockton Harbor, Maine (NE ) 1-39 Stockton Lake, Mo. (MRK) 20-9, 20-14, 20-18, 20-21 Stone Harbor, N.J. (NAP) 3-23 Stonehouse Creek, Kans. (MRK) 20-19 Stonewall Jackson Lake, W. Va. (ORP) 26-9, 26-15, 26-20 Stonington Harbor, Conn. (NED) 1-39 Stonington Harbor, Maine (NED) 1-9, 1-27, 1-35, 1-44 Stony Brook, Wilton, N.H. (NED) 1-43 Stony Creek, Branford, Conn. (NED) 1-39 Stratford, Conn. (NED) 1-44 Streambank Erosion Control Evaluation and Demonstration Project Louisville, Ky., District (ORL) 24-13 New England Division (NED) 1-23 Omaha, Nebr., District (MRO) 21-9, 21-12, 21-16 Pittsburgh, Pa., District (ORP) 26-29 Seattle, Wash., District (NPS) 38-4 Strington, Ft. Chartres and Ivy Landing, Ill. (LMS) 14-15 Strong Creek, Idaho (NPS) 38-28 Strube Lake & Cougar Additional Unit, (South Fork McKenzie) (Modification to Cougar Lake) Oreg. 37-55 Stuart, Va. (SAW) 6-13, 6-20 Stuart Gulch Dam, Boise, Idaho (NPW) 39-18 Stumpy Point Bay, N.C. (SAW) 6-25 Sturgeon Bay and Lake Michigan Ship Canal, Wis. (NCE) 31-30, 31-52, 31-71 Sturgis, Ky. (ORL) 24-20, 24-24, 24-29 Subdistrict No. 1 of Drainage Union No. 1 and Bay Island Drainage and Levee District No. 1, Ill. (NCR) 28-15, 28-17 Sucker Brook, Conn. (NED) 1-22, 1-43, 1-47 Sugar Creek Basin, N.C. and S.C. (SAN) 7-17 Sugar Creek Levee, Ind. (ORL) 24-22, 24-25 Sugar Hill Reservoir, N.H. (NED) 1-44 Suisun Bay Channel, Calif. (SPK) (SPN) 34-5, 35-28 Suisun Channel, Calif. (SPK) (SPN) 34-6, 35-28 Suisun Point Channel, Calif. (SPK) 35-28 Sullivan Falls Harbor, Maine (NED) 1-39 Sulphur River, Ark. and Tex. (LMN) 11-21 Sulphur River Levees, Tex. (SWF) 16-21 Summer Reservoir, N.M. (SWA) 17-7 Summersville Lake, W. Va. (ORH) 25-9, 25-15, 25-18 Sumner Parker Airport, Oreg. (NPP) 37-48 Sumpawanus (Babylon Creek) Inlet, N.Y. (NAN) 2-30 Sun Creek, Miss. (SAM) 10-43 Sunbury, Pa. (NAB) 4-36, 4-39 Sunken Vessel Removal 48-1 Supervision of the Harbor of Hampton Roads (Prevention of Obstructive and Injurious Deposits) (NAO) 5-7, 5-15 Supervisor of New York Harbor (NAN) 2-13, 2-21, 2-28 Surry Mountain Lake, N.H. (NED) 1-14, 1-28, 1-47 Surveillance of Northern Boundary Waters (NCE) 31-35, 31-53 Susquehanna River above and below Havre De Grace, Md. (NAB) 4-9, 4-23, 4-31 Susquehanna River at Williamsport, Pa. (NAB) 4-35 Susquehanna River Flood Control Projects, N.Y. and Pa. (NAB) 4-17, 4-33 Sutton Lake, W. Va. (ORH) 25-10, 25-15, 25-18 I-53 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Suvannee River, Fla. (SAJ) 9-47 Swanton Harbor, Vt. (NAN) 2-34 Sweetwater Creek, N.C. (SAW) 6-28 Sweetwater River, Calif. (SPL) 33-9, 33-16, 33-23 Swift Creek, N.C. (SAW) 6-25 Swiftcreek, Pitt and Craven Counties, N.C. (SAW) 6-27 Swinomish Channel, Wash. (NPS) 38-6, 38-14, 38-20 Swoyersville, and Forty Fort, Pa. (NAB) 4-36, 4-39 Sykesville, Pa. (ORP) 26-22 Syracuse, N.Y. (NCB) 32-37 Syracuse, Ohio (ORH) 25-21 T T. J. O'Brien Lock and Dam, Ill. (NCC) 28-20, 28-21 Table Rock Lake, Mo. (SWL) 18-8, 18-12, 18-23 Tacoma, Wash. (NPS) 38-9, 38-16, 38-21 Tacoma Harbor, Wash. (NPS) 38-24, 38-30 Tahchevah Creek Detention Basin and Channel Improvements, Calif. (SPL) 33-26 Tahola, Wash. (NPS) 38-28 Tahquitz Creek, Calif. (SPL) 33-26 Talkeetna River, Alaska (NPA) 40-13 Tallahala Creek Lake, Miss. (SAM) 10-13, 10-28, 10-38 Tallahatchie and Coldwater Rivers, Miss. (LMK) 12-21 Tallapoosa River, Ala. (SAM) 10-42 Tallow Hill, Ga. (SAS) 8-17 Talofofo Bay Shore Protection, Guam (POD) 36-12 Tamaqua, Pa. (NAP) 3-23 Tampa and Hillsborough Bays, Fla. (SAJ) 9-39 Tampa Bay, Fla. (SAJ) 9-39 Tampa Harbor, Fla. (SAJ) 9-16, 9-29, 9-39 Tangeman, Nebr. (MRO) 21-20 Tangier Channel, Va. (NAO) 5-8, 5-15, 5-20 Tangipahoa River, La. (LMN) 11-8, 11-13, 11-16 Tar River, N.C. (SAW) 6-27 Tar River and Tributaries, N.C. (SAW) 6-27 Tar River, Princeville, N.C. (SAW) 6-27 Tarentum, Pa. (ORP) 26-22 Tarkio River, Iowa (MRK) 20-8 Tarrytown Harbor, N.Y. (NAN) 2-30 " Taskinas Creek, Va. (NAO) 5-23 Tau Small Boat Harbor, American Samoa (POD) 36-3, 36-7 Taunton River, Mass. (NED) 1-39 Tavas Bay Harbor, Mich. (NCE) 31-76, 31-77 Taylors Bayou, Tex. (SWG) 15-9, 15-14, 15-24 Taylorsville, Ky. (ORL) 24-20, 24-24, 24-29 Taylorsville Lake, Ky. (ORL) 24-11, 24-17 Teche-Vermilion Basins, La. (Water Supply) (MR+T) 42-6, 42-14, 42-28, 42-50, 42-59 Telegraph Canyon Creek, Calif. (SPL) 33-9, 33-16, 33-23 Tell City, Ind. (ORL) 24-20, 24-24, 24-29 Tenants Harbor, Maine (NED) 1-39 Tenasillahe Island, Oreg. (NPP) 37-47 Tenkiller Ferry Lake, Okla. (SWL) (SWT) 18-21, 19-8, 19-12, 19-14, 19-16 Tenmile Creek at Marianna, Pa. (ORP) 26-22 Tennessee River, Tenn., Ala., and Ky. (ORN) 23-3, 23-9, 23-11, 23-17, 23-18 Tennessee-Tombigbee Waterway, Ala. and Miss. (ORN) (SAM) 10-48, 23-4, 23-9, 23-12 Tensas Basin, Ark. and La. (MR+T) 42-6, 42-15, 42-28 Tensas River and Bayou Macon, La. (LMK) 12-21 Tensas River National Wildlife Refuge (MR+T) 42-28 Terrain Analysis Center 51-1 Terre Haute, Ind. (ORL) 24-22 Terre Haute (Conover Levee), Ind. (ORL) 24-20, 24-29 Terre Noire Creek, Ark. (LMK) 12-22 Terry, David D., Lock and Dam, Ark. (SWL) 18-2, 18-18 Teton River, Idaho (NPW) 39-17, 39-18 Texas City and Vicinity, Tex., Hurricane-Flood Protection (SWG) 15-10, 15-14,15-24 Texas City Channel, Tex. (SWG) 15-6, 15-13, 15-23, 15-27, 15-34 Thames River, Conn. (NED) 1-39 Thames River Basin, Conn., R.I., and Mass. (NED) 1-21, 1-22, 1-51 The Cascades Canal, Oreg. (NPP) 37-45 The Dalles-Celilo Canal, Oreg. and Wash. (NPP) 37-45 The Dalles Lock and Dam-Lake Celilo, Wash. and Oreg. (NPP) 37-25, 37-33, 37-44, 37-57 The Island Lake, Vt. (NED) 1-44 Thimble Shoal Channel, Va. (NAO) 5-8, 5-15, 5-20 Thomaston Dam, Conn. (NED) 1-17, 1-29, 1-48 Thoroughfare Swamp, N.C. (SAW) 6-28 Three Forks, Mont. (MRO) 21-19 I-54 INDEX Three Islands Reservoir, Tenn. (ORN) 23-14 Three Rivers, Mass. (NED) 1-22, 1-43, 1-48 Three Rivers, Tex. (SWF) 16-21 Thumpertown Beach, Eastham, Mass. (NED) 1-44 Tickfaw, Natalbany, Ponchatoula, and Blood Rivers, La. (LMN) 11-21 Ticonderoga River, N.Y. (NAN) 2-34 Tijuana River Basin, Calif. (SPL) 33-26 Tilghman Island Harbor, Md. (NAB) 4-35 Tillamook Bay and Bar, Oreg. (NPP) 37-10, 37-29, 37-39 Tioga-Hammond Lakes, Pa. (NAB) 4-18, 4-26 Tionesta Lake, Pa. (ORP) 26-10, 26-15, 26-20 Toad Suck Ferry Lock & Dam, Ark. (SWL) 18-4, 18-18 Tocks Island Lake, Pa., and N.Y. (NAP) 3-24 Tocks Island (Relocation of U.S. Route 209 Only) Pa. (NAP) 3-24 Todd Swamp, S.C. (SAN) 7-8, 7-16 Toledo Harbor, Ohio (NCB) 32-10, 32-20, 32-32 Tolovana River, Alaska (NPA) 40-13 Tolu, Ky. (ORL) 24-21, 24-24 Tom Jenkins Dam, Ohio (ORH) 25-15, 25-18 Tom Jenkins Reservoir, Ohio (ORH) 25-10 Tomahawk Lake, Kans. (MRK) 20-19 Tomanovich-Salmon City, Idaho (NPW) 39-17, 39-19 Tombigbee River, Miss. and Ala. (SAM) 10-15, 10-29, 10-39 Tombigbee River Tributaries, Miss. and Ala. (SAM) 10-15, 10-29, 10-39 Toms River, N.J. (NAP) 3-21, 3-24 Tongue River Lake, N. Dak. (NCS) 27-24 Topeka, Kans. (MRK) 20-19, 20-21 Topographic Laboratory 51-1 Topsail Beach and Surf City, N.C. (SAW) 6-28 Toronto Lake, Kans. (SWL) (SWT) 18-21, 19-6, 19-11, 19-14, 19-16 Torrington, Conn. (NED) 1-22, 1-43, 1-49 Totuskey Creek, Va. (NAO) 5-23 Touchet River, Wash. (NPW) 39-17, 39-18 Towanda Lake, Kans. (SWT) 19-15 Town Beach, Plymouth, Mass. (NED) 1-41 Town Bluff Dam-B. A. Steinhagen Lake, Tex. (SWF) 16-12, 16-16, 16-20 Town Bluff Hydropower, Tex. (SWF) 16-12, 16-20 Town Creek, Md. (NAB) 4-35 Town Creek, S.C. (SAN) 7-6, 7-10, 7-13 Town Creek, Americus, Ga. (SAM) 10-43 Town Creek, Harrodsburg, Ky. (ORL) 24-20 Town Neck Beach, Sandwich, Mass. (NED) 1-41 Townsend Inlet and Seven Mile Beach, N.J. (NAP) 3-23 Townshend Lake, Vt. (NED) 1-15, 1-28, 1-47 Trabuco Dam, Calif. (SPL) 33-30 Tradewater River, Ky. (ORL) 24-19 Tranquitas Creek, Kingsville, Tex. (SWG) 15-26 Tranters Creek, N.C. (SAW) 6-28 Trask River, Oreg. (NPP) 37-48 Traverse City Harbor, Mich. (NCE) 31-76, 31-77 Treasure Island, Mo. (LMM) 13-7 Treatment of Yuba River Debris Situation-Restraining Barriers, Calif. (CDC) 44-2, 44-5 Tred Avon River, Md. (NAB) 4-9, 4-24, 4-31 Trent River, N.C. (SAW) 6-25, 6-27, 6-28 Trenton Lake, Mo. (MRK) 20-19 Trexler Lake, Pa. (NAP) 3-24 Trim Cane Creek, Miss. (SAM) 10-43 Trinidad Lake, Colo. (SWA) 17-6, 17-9 Trinity River and Tributaries, Tex. (SWG) 15-7, 15-13, 15-23, 15-27 Trinity River Project, Tex. (SWF) 16-2, 16-14, 16-20 Triplett Creek, Morehead, Ky. (ORL) 24-20, 24-30 Tri-Pond Levee, Ill. (ORL) 24-22, 24-25 Trotters Shoals Lake (SAS) 8-9, 8-12, 8-15 Troublesome Creek, Hindman, Ky. (ORL) 24-30 Troy, Ind. (ORL) 24-22, 24-25, 24-30 Truckee River and Tributaries, Calif. and Nev. (SPK) 35-29 Truman, Harry S., Dam and Reservoir, Mo. (MRK) 20-9, 20-13, 20-17, 20-21 Trumbull Lake, Conn. (NED) 1-43 Trussville, Ala. (SAM) 10-43 Truth or Consequences (Hot Springs) Unit, N. Mex. (SWA) 17-5, 17-10, 17-11 Tualatin, Oreg. (NPP) 37-18, 37-31, 37-42 Tucannon River, Camp Wooten, Wash. (NPW) 39-17 Tuckahoe River, Md. (NAB) 4-35 Tuckerton Creek, N.J. (NAP) 3-21 Tucson Diversion Channel, Ariz. (SPL) 33-6, 33-15, 33-21 Tug and Levisa Forks of the Big Sandy River and Cumberland River, W. Va., Va., and Ky. (ORN) 23-6, 23-9 Tully Lake, Mass. (NED) 1-15, 1-28, 1-47 Tulsa and West Tulsa Levee, Okla. (SWT) 19-15, 19-17 Turkey Creek, S.C. (SAN) 7-8, 7-16 Turner Prairie, Mill Creek, Oreg. (NPP) 37-51 Turtle Creek, Pa. (ORP) 26-22 Turtle Creek Channel Improvement, Yukon, Okla. (SWT) 19-15 I-55 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Tuskahoma Lake, Okla. (SWT) 19-15 Tuttle Creek Lake, Kans. (MRK) 20-7, 20-13, 20-17, 20-21 Tuttle Creek Lake (Road Improvement), Kans. (MRK) 20-21 Twelvemile Bayou, La. (LMN) (LMK) 11-22, 12-25 Twin Valley Lake, Wild Rice River, Minn. (NCS) 27-16, 27-21 Twitch Cove and Big Thorofare, Md. (NAB) 4-10, 4-24, 4-31 Two Harbors, Minn. (NCE) 31-76, 31-77 Two Rivers Dam, N. Mex. (SWA) 17-7, 17-9 Two Rivers Harbor, Wis. (NCE) 31-30, 31-52, 31-71 Tyaskin Creek, Md. (NAB) 4-35 Tybee Island, Ga. (SAS) 8-6, 8-11, 8-15 Tygart Lake, W. Va. (ORP) 26-3, 26-13, 26-17 Tylers Beach, Va. (NAO) 5-23 Tyrone, Pa. (NAB) 4-36, 4-39 U Umatilla Harbor, Oreg. (NPP) 37-45 Umatilla River (ECHO), Oreg. (NPP) (NPW) 37-18, 37-31, 37-42, 37-48, 37-50, 39-17 Umpqua River, Oreg. (NPP) 37-10, 37-29, 37-39 Umpqua River and Tributaries, Oreg. (NPP) 37-48 Unadilla, N.Y. (NAB) 4-36, 4-39 Union City Dam, Pa. (ORP) 26-10, 26-15, 26-20 Union Lake, Mo. (LMS) 14-15 Union River, Maine (NED) 1-39 Union Township Drainage District, Mo. (NCR) 28-15, 28-17 Union Village Dam, Vt. (NED) 1-15, 1-29, 1-47 Uniontown, Ky. (ORL) 24-20, 24-24, 24-29 Uniontown, Pa. (ORP) 26-22, 26-26 Uniontown Locks and Dam, Ky. (ORL) 22-3, 22-9 University Wash and Spring Brook, Riverside, Calif. (SPL) 33-26 Upper and Lower Woonsocket, R.I. (NED) 1-22 Upper Chipola River, Fla., from Mariana to its mouth (SAM) 10-42 Upper Grand River, Mo. (MRK) 20-19 Upper Grays River Area, Wash. (NPP) 37-46 Upper Iowa River, Iowa (NCS) 27-24 Upper Machodoc Creek, Va. (NAB) 4-35 Upper Marlboro, Md. (NAB) 4-36, 4-39 Upper Mississippi River Environmental Management Program, Ill., Ia., Minn., Mo., Wis. (NCR) 28-3, 28-8, 28-11 Upper Puyallup River, Wash. (NAS) 38-28 Upper River Road, Jefferson Co., Ky. (ORL) 24-30 Upper River Rouge, Mich. (NCE) 31-78 Upper Thorofare, Deal Island, Md. (NAB) 4-10, 4-24, 4-31 Upper White River, Ark. (SWL) 18-15 Urban Areas at Alton, Ill. (LMS) 14-15 Urbanna Creek, Va. (NAO) 5-23 U.S. Highway 43 Bridge, Linden, Ala. (SAM) 10-16, 10-29, 10-39 U.S. Highway 45 Bridge, Prentiss County, Miss. (SAM) 10-16, 10-29, 10-40 U.S. Highway 51, Tenn. (LMM) 13-7 Utica, Ind. (ORL) 24-22, 24-26 Utica, Ohio (ORB) 25-20, 25-22 V Valdez Harbor, Alaska (NPA) 40-12 Valley City Drainage and Levee District, Ill. (LMS) 14-15 Valley Drainage and Levee District, Ill. (NCR) 28-17 Van Buren, Arkansas River, Ark. (SWL) 18-16 Van Meter, Iowa (NCR) 28-15, 28-17 Vanceburg, Ky. (ORH) 25-20 Vancouver Lake Area, Wash. (NPP) 37-47 Vatia Area, American Samoa (POD) 36-11 Vaughn, Mont. (MRO) 21-17, 21-19 Velva, N. Dak. (NCS) 27-24, 27-28 Ventnor, Margate and Longport, N.J. (NAP) 3-23 Ventura Marina (Ventura Harbor), Calif. (SPL) 33-4, 33-14, 33-20 Ventura-Pierpont Area, Calif. (SPL) 33-24 Ventura River Basin, Calif. (SPL) 33-26 Vermilion Harbor, Ohio (NCB) 32-11, 32-20, 32-33 Vermilion Lock, La. (Replacement of Lock) (LMN) 11-3, 11-4, 11-13, 11-15 Vermillion River, S.D. (MRO) 21-18 Vermillion River, Hastings, Minn. (NCS) 27-24 Verona Lake, Va. (NAB) 4-36 Veteran's Memorial Levee, Hastings, Minn. (NCS) 27-16, 27-21 Vevay, Ind. (ORL) 24-22, 24-25 Vicinity of Nehalem, Oreg. (NPP) 37-49 Vicksburg Harbor, Miss. (MR+T) 42-29 Victory Lake, Vt. (NED) 1-44 Villa Park Dam, Calif. (SPL) 33-27, 33-30 Village Creek, S.C. (SAN) 7-6, 7-7, 7-10, 7-13, 7-15 I-56 INDEX Village Creek, Jackson & Lawrence Counties, Ark. (SWL) 18-16 Village Creek, White River, and Mayberry Levee District, Ark. (SWL) 18-14, 18-16 Village of New Athens, Ill. (LMS) 14-15 Village of Saxtons, Vt. (NED) 1-15, 1-29, 1-35 Vince and Little Vince Bayous, Tex. (SWG) 15-10, 15-14, 15-24 Vincennes, Ind. (ORL) 24-20, 24-24, 24-29 " Vineyard Haven, Mass. (NED) 1-39 Vinton Waterway, La. (LMN) 11-21 Virginia Beach, Va. (NAO) 5-9, 5-15, 5-20 Virginia Beach Streams Canal Number 2, Va. (NAO) 5-11, 5-16, 5-20 Virginia Key and Key Biscayne, Fla. (SAJ) 9-48 W W. D. Mayo Lock and Dam, Okla. (SWL) (SWT) 18-19, 19-16 V. Kerr Scott Dam and Reservoir, N.C. (SAW) 6-13, 6-16, 6-20 W. P. Franklin Lock and Dam, Fla. (SAJ) 9-49 Wabash Railroad Bridges, Illinois River, Meredosia, and Valley City, Ill. (LMS) 14-13 Wabash River Basin, Ind., Ill., and Ohio (ORL) 24-12, 24-19, 24-28 Wabasha Harbor, Minn. (NCD) 29-7 Waccamaw River, N.C. and S.C. (SAN) 7-7, 7-15 Waccamaw River and Seven Creeks, N.C. and S.C. (SAN) 6-27 Waco Lake, Tex. (SWF) 16-11, 16-16, 16-20 Wahkiakum County Consolidated Diking District No. 1, Wash. (NPP) 37-19, 37-31, 37-42, 37-54 Wahkiakum County Diking District 4, Wash. (NPP) 37-47, 37-54 Waianae Small Boat Harbor, Hawaii (POD) 36-10 Walkiki Beach, Hawaii (POD) 36-11 Wailoa Stream and Tributaries, Hawaii (POD) 36-12 Waimea Beach, Hawaii (POD) 36-11 Waimea River, Hawaii (POD) 36-4, 36-7 Wake Island Harbor, Wake Island (POD) 36-10 Waldo Lake Tunnel and Reregulating Works, Oreg. (NPP) 37-50 Walla Walla River, Oreg. (NPW) 39-19 Wallabout Channel, N.Y. (NAN) 2-30 Wallace, W. Va. (ORP) 26-22 Wallace Channel, Pamlico Sound, N.C. (SAW) 6-25 Vallace Lake, La. (LMN) (LMK) 12-11, 12-15, 12-18, 12-22, 12-24 Wallis Sands State Beach, N.H. (NED) 1-41 Wallisville Lake, Tex. (SWG) 15-8 Wallova River, Oreg. (NPW) 39-17 Walluski River, Oreg. (NPP) 37-46 Walnut Creek, Calif. (SPK) 35-14, 35-23 Walter, Francis E., Dam, Pa. (NAP) 3-12, 3-17 Walter F. George Lock and Dam, Ala. and Ga. (SAM) 10-24, 10-30, 10-41 Walters Slough, N.C. (SAW) 6-29 Wappapello Lake, Mo. (MR+T) 42-20, 42-59 Wappinger Creek, N.Y. (NAN) 2-30 Wappinger Creek at Pleasant Valley, N.Y. (NAN) 2-32 Ware, Mass. (NED) 1-22, 1-43, 1-48 Wareham Harbor, Mass. (NED) 1-39 Wareham-Marion, Mass. (NED) 1-44 Warren River, R.I. (NED) 1-39 Warrenton Diking Districts 1, 2, and 3, Oreg. (NPP) 37-47 Warroad Harbor and River, Minn. (NCS) 27-3, 27-19, 27-22, 27-25 Warroad River and Bull Dog Creek, Minn. (NCS) 27-24 Warsaw, N.Y. (NCB) 32-37 Warsaw Harbor, Ill. (NCD) 29-8 Warwick Cove, R.I. (NED) 1-39 Warwick River, Md. (NAB) 4-35 Warwood, W. Va. (OPR) 26-22, 26-26 Washington, D.C. and Vicinity (NAB) 4-36, 4-39 Washington, Pa. (ORP) 26-22 Washington Aqueduct (NAB) 4-20 Washington Canal and South River, N.J. (NAN) 2-30 Washington Harbor, D.C. (NAB) 4-10, 4-24, 4-32 Washington Island, Wis. (NCE) 31-76, 31-77 Washougal Area Levees, Wash. (NPP) 37-47 Water Resources Support Center (WRSC) 53-1 Water Valley, Ark. and Mo. (SWL) 18-17 Waterborne Commerce Statistics Center 53-2 Waterbury, Vt. (NAN) 2-34 Waterbury Dam, N.Y. (NAN) 2-18 Waterbury Reservoir, Vt. (NAN) 2-32 Waterbury-Watertown, Conn. (NED) 1-22, 1-43, 1-49 Wateree River, S.C. (SAN) 7-15 Waterford, N.Y. (NAN) 2-34 Waterloo, Iowa (NCR) 28-6, 28-9, 28-12, 28-17 Waterloo, Nebr. (MRO) 21-17, 21-20 I-57 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Waterway Connecting Pamlico Sound and Beaufort Harbor, S.C. (SAW) 6-8, 6-19, 6-23, 6-29 Waterway Connecting Port Townsend and Oak Bay, Wash. (NPS) 38-6, 38-15, 38-20 Waterway Connecting Svanquarter Bay with Deep Bay, N.C. (SAW) 6-25 Waterway Connecting Tombigbee and Tennessee Rivers, Ala. and Miss. (SAM) 10-11, 10-28, 10-38 Waterway from Empire, La., to Gulf of Mexico (LMN) 11-21 Waterway from Indian River Inlet to Rehoboth Bay, Del. (NAP) 3-21 Waterway from Intracoastal Waterway to Bayou Dulac, La. (Bayous Grand Caillou and LeCarpe, La.) (LMN) 11-8, 11-13, 11-16 Waterway from Little Choptank River to Choptank River, Md. (NAB) 4-38 Waterway from White Lake to Pecan Island, La. (LMN) 11-21 Waterway-Norfolk, Va. to Sounds of N.C. (SAW) 6-25 Waterway on the Coast of Virginia (NAO) 5-9, 5-15, 5-20 Waterways Experiment Station (WES) 45-1 Watkins Glen, N.Y. (NCB) 32-39 Watts Bar Lock and Dam, Tenn. (ORN) 23-17 Waukegan Harbor, Ill. (NCC) 30-5, 30-8, 30-11, 30-13, 30-14 Waurika Lake, Okla. (SWT) 19-6, 19-11, 19-14 Waverly, W. Va. (ORH) 25-21 Wax Lake Outlet, La. (MR+T) 42-50 Waycake Creek, N.J. (NAN) 2-30 Webb District Improvement Co., Oreg. (NPP) 37-47 Webbers Falls Lock and Dam, Okla. (SWL) (SWT) 18-19, 19-8, 19-12, 19-14, 19-16 Weber River and Tributaries, Utah (SPK) 35-31' Weiser River, Weiser Area, Idaho (NPW) 39-4, 39-10, 39-14, 39-17, 39-18 Welles Harbor, Territory of Guam (POD) 36-10 Wellfleet Harbor, Mass. (NED) 1-39 Wells Harbor, Maine (NED) 1-39 Wellsburg, W. Va. (ORP) 26-23 Wellsville, N.Y. (NCB) 32-37 Wellsville, Ohio, Sec. I (ORP) 26-22, 26-26 Wellsville, Ohio, Sec. II (ORP) 26-22, 26-26 Wenatchee Canyons 1 and 2, Wash. (NPS) 38-28 Wessagusset Beach, Weymouth, Mass. (NED) 1-41 West, Herbert G., Lake, Wash. (NPW) 39-7 West Atchalafaya Floodway, La. (MR+T) 42-13 West Branch Chisholm Creek Channel Improvement, Kans. (SWT) 19-15 West Branch of Susquehanna River, Pa. (NAB) 4-18, 4-33 West Branch, Westfield River, Mass. (NED) 1-43 West Bridgewater, Pa. (ORP) 26-23 West Brookfield Reservoir, Mass. (NED) 1-44 West Canaan Lake, N.H. (NED) 1-44 West Fork, W. Va. (ORH) 25-20 West Fork, Foster Creek, Wash. (NPS) 38-28 West Fork Grand River, Mo. (MRK) 20-8 West Fork of Mill Creek Lake, Ohio (0RL) 24-12, 24-17, 24-27 West Glendive, Mont. (MRO) 21-19 West Harbor, Ohio (NCB) 32-11, 32-20 West Hickman Area, Hickman, Ky. (LMM) 13-7 West Hill Dam, Mass. (NED) 1-11, 1-27, 1-46 West Kentucky Tributaries, Ky. (MR+T) 42-10 42-19, 42-28, 42-53 West Magnesia Canyon Channel, Calif. (SPL) 33-10, 33-16, 33-23 West Makinster Road, Wilson River, Oreg. (NPP) 37-19, 37-31, 37-42 West Matanzas Drainage and Levee District, Ill. (NCR) 28-17 West Muddy Creek and Marys River, Oreg. (NPP) 37-50 West Nishnabotna River, Mills Co. Bridge, near Hastings, Iowa (MRO) 21-21 West Nishnabotna River, Mills Co. Bridge, near Malvern, Iowa (MRO) 21-21 West Nishnabotna River, near Hancock, Iowa (MRO) 21-21 West of Morrilton, Arkansas River, Ark. (SWL) 18-16 West Oneonta Lake, N.Y. (NAB) 4-38 West Point, Ga. (SAM) 10-43 West Point, Ky. (ORL) 24-21, 24-24 West Point, Nebr. (MRO) 21-17, 21-20 West Point Lake, Ga. and Ala. (SAM) (SAS) 8-9, 10-24, 10-31, 10-41 West Richland, Wash. (NPW) 39-19 West Springfield, Mass. (NED) 1-15, 1-22, 1-29, 1-35, 1-43, 1-48 West Stewartstown, N.H. (NED) 1-22 West Tennessee Tributaries, Tenn. (MR+T) 42-10, 42-18, 42-28, 42-53 West Terre Haute, Ind. (ORL) 24-20, 24-24, 24-29 West Thompson Lake, Conn. (NED) 1-21, 1-31, 1-51 West Union, W. Va. (ORH) 25-22 West Warren, Mass. (NED) 1-22, 1-43, 1-48 I-58 INDEX Westchester Creek, N.Y. (NAN) 2-34 Westcott Cove, Conn. (NED) 1-39 Westerly, R.I. (NED) 1-43 Western Branch, Va. (NAO) 5-19 Westfield, Mass. (NED) 1-44 Westhaven Cove Small Boat Basin (Westport Marina), Wash. (NPS) 38-24 Westland District Improvement Co., Oreg. (NPP) 37-47 Weston, Vt. (NED) 1-22, 1-43, 1-48 Weston Mills, Olean, N.Y. (ORP) 26-22 Weston Mills, Portville, N.Y. (ORP) 26-22 Westport, Conn. (NED) 1-44 Westport, Ky. (ORL) 24-22, 24-25 Westport District, Oreg. (NPP) 37-47 Westport Harbor and Saugatuck River, Conn. (NED) 1-39, 1-44 Westport River, Mass. (NED) 1-39 Westport Slough, Oreg. (NPP) 37-45, 37-50 Westville Lake, Mass. (NED) 1-22, 1-31, 1-51 Wethersfield, Conn. (NED) 1-22 Weymouth Back River, Mass. (NED) 1-39 Weymouth-Braintree, Mass. (NED) 1-22 Weymouth-Fore & Town Rivers, Boston Hbr., Mass. (NED) 1-39 Wheeler, General Joe, Lock and Dam, Ala. (ORN) 23-17 Wheeling, W. Va. (ORP) 26-22, 26-26 Wheeling, W. Va. (North Wheeling) (ORP) 26-22, 26-27 Wheeling, W. Va. (Wheeling Island) (ORP) 26-22, 26-27 White Lake Harbor, Mich. (NCE) 31-31, 31-53, 31-71 White Oak Bayou, Tex. (SWG) 15-10 White Oak Creek, Ohio (ORH) 25-21 White Oak Dike, Bladen and Pender Counties, N.C. (SAW) 6-27 White Oak River, N.C. (SAW) 6-29 White River, Ark. (above Peach Orchard Bluff) (SWL) 18-15 White River, Ark. (below Newport) (LMM) 13-6 White River, Ind. (ORL) 24-19, 24-30 White River Backwater Levees (MR+T) 42-9 White River Basin (Little Rock District) (SWL) 18-4, 18-10, 18-14, 18-23 Whitebird Creek, Idaho (NPW) 38-17, 39-18 Whitefish Point, Mich. (NCE) 31-76, 31-77 Whitesburg, Ky. (ORL) 24-30 Whitevater River Basin, Calif. (SPL) 33-26 Whiting, Maine (NED) 1-22 Whitings Creek, Va. (NAO) 5-23 Whitlow Ranch Dam, Ariz. (SPL) 33-6, 33-15, 33-21 Whitmanville Lake, Mass. (NED) 1-43, 1-50 Whitney Lake, Tex. (SWF) 16-13, 16-16, 16-20 Whitney Point Lake, N.Y. (NAB) 4-17, 4-26 Whitney Point Village, N.Y. (NAB) 4-17, 4-26 Wichita and Valley Center Channel Improvement, Kans. (SWT) 19-15, 19-17 Wickford Harbor, R.I. (NED) 1-39 Wicomico River, Md. (NAB) 4-11, 4-24, 4-32 Wiedmer Chemical Drainage and Levee District, Mo. (LMS) 14-15 Wilcox, Pa. (ORP) 26-23 Wild Rice and Marsh Rivers, Minn. (NCS) 27-27 Wild Rice River, Minn. (NCS) 27-28 Wild Rice River, Mahnomen Co., Minn. (NCS) 27-17, 27-21 Wild Rice River, South Branch and Felton Ditch, Minn. 27-17, 27-21 Wildcat and San Pablo Creeks, Calif. (SPK) 35-15, 35-23 Vilders, Ky. (ORL) 24-24 Wiley Creek Lake, Oreg. (NPP) 37-50 Wilkes-Barre, Pa. (NAB) 4-36, 4-39 Willamette Falls Fishladder, Oreg. (NPP) 37-50 Willamette River above Portland and Yamhill River, Oreg. (NPP) 37-11, 37-29, 37-39 Willamette River at Willamette Falls, Oreg. (NPP) 37-11, 37-30, 37-40, 37-51 Willamette River Basin, Oreg. (NPP) 37-19, 37-48, 37-55 Willamette River Basin, Oreg.-Bank Protection (NPP) 37-19, 37-31, 37-42, 37-56 Willamette River Basin Channel Clearing and Snagging (NPP) 37-48 Willapa River and Harbor and Naselle River, Wash. (NPS) 38-6, 38-15, 38-20 Willapa River at Raymond, Wash. (NPS) 38-28 Willard Beach, South Portland, Me. (NED) 1-41 William H. Harsha Lake, Ohio (ORL) 24-12, 24-17, 24-27 William L. Springer Lake, Ill. (NCR) 28-15 Williamson, W. Va. (ORH) 25-20, 25-22 Williamsport, Pa. (NAB) 4-36, 4-39 Williamstown, W. Va. (ORH) 25-21 Williaavsville Reservoir, Vt. (NED) 1-44 Williston, N.D., Water Intake (MRO) 21-18 Willoughby Channel, Va. (NAO) 5-23 Willow Creek, Idaho (NPW) 39-17 Willow Creek Lake, Heppner, Oreg. (NPP) 37-20, 37-32, 37-42 Willow Creek Lake, Heppner, Oreg. (NPW) 39-4, 39-10, 39-14 I-59 REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 Willow Island Locks and Dam, W. Va. (ORD) 22-3, 22-7 Wilmington Harbor, Del. (NAP) 3-9, 3-16, 3-20 Wilmington Harbor, N.C. (SAW) 6-9, 6-19 Wilmore, Pa. (0RP) 26-22 Wilson Branch, Cheraw, S.C. (SAN) 7-7, 7-10, 7-14 Wilson Harbor, N.Y. (NCB) 32-11, 32-21, 32-33 Wilson Lake, Kans. (MRK) 20-7, 20-13, 20-17, 20-21 Wilson Lock and Dam, Ala. (ORN) 23-17 Wilson Point Harbor, Conn. (NED) 1-39 Wilson River, Oreg. (NPD) 37-49 Wilton, N.H. (NED) 1-22 Winchester Bay, Oreg. (NPP) 37-12, 37-30, 37-40 Winfield Levee, Kans. (SVT) 19-15 Winnibigoshish Reservoir, Minn. (NCS) 27-26 Winnipesaukee Lake, N.H. (NED) 1-39 Winona, Minn. (NCS) 27-17, 27-21 Winona Harbor, Minn. (NCD) 29-7 Winooski River, Vt. (NAN) 2-32, 2-36 Winslow (Tributaries of Little Colorado River), Ariz. (SPL) 33-26 Winsted, Conn. (NED) 1-22, 1-43, 1-48 Winter Harbor, Maine (NED) 1-39 Winter Harbor, Va. (NAO) 5-23 Winthrop Beach, Mass. (NED) 1-41 Winthrop Harbor, Mass. (NED) 1-39 Wisconsin River, Wis. (NCS) 27-23 Wishart Point Channel, Va. (NA0) 5-23 Wister Lake, Okla. (SWL) (SVT) 18-21, 19-6, 19-11, 19-14, 19-16 Withlacoochee River, Fla. (SAJ) 9-46, 9-47 Wolf and Jordan Rivers, Miss. (SAM) 10-42, 10-45 Wolf-Coffee Lake, Kans. (MRK) 20-19 Wolf Creek Dam-Lake Cumberland, Ohio River Basin, Ky. (ORN) 23-8, 23-10 Wolf River (Memphis Harbor), Tenn. (LMM) 13-6 Wood Island Harbor, Maine (NED) 1-39 Wood River Drainage and Levee District, Ill. (LMS) 14-7, 14-10, 14-12 Woodbridge Creek, N.J. (NAN) 2-30 Woodbury Creek, N.J. (NAP) 3-21 Woodcock Creek Lake, Pa. (ORP) 26-11, 26-15, 26-20 Woodland St. Bridge, Tenn. (ORN) 23-4 Woodlands1 W. Va. (0RP) 26-22, 26-27 Woodmont Shore, Milford, Conn. (NED) 1-41 Woodruff, Jim, Lock and Dam, Ga. and Fla. (SAM) 10-23, 10-30, 10-41 Woods Hole Channel, Mass. (NED) 1-39 Woodson Drainage District, Oreg. (NPP) 37-47, 37-47, 37-54 Woonsocket, R.I. (NED) 1-43, 1-47 Worcester, Mass. (NED) 1-22, 1-47 Worcester Diversion, Mass. (NED) 1-43 Vorthington, Minn. (NCR) 28-17 Wrangell Harbor, Alaska (NPA) 40-12 Wrangell Narrows, Alaska (NPA) 40-12 Wright Patman Dam and Lake, Tex. (LMN) (SWF) 11-22, 16-11, 16-16, 16-20 Wright's Creek, N.C. (SAW) 6-25 Wrightsville Beach, N.C. (SAW) 6-27 Wrightsville Dam, Vt. (NAN) 2-32 Vynoochee Lake, Vash. (NPS) 38-9, 38-16, 38-21 Wynoochee River, Wash. (NPS) 38-28 Wyoming Valley, Pa. (NAB) 4-19, 4-27, 4-33 Y Yadkin River Basin, N.C. & S.C. (SAW) 6-13, 6-30 Yakima, Wash. (NPS) 38-28 Yakima River at Union Gap, Wash. (NPS) 38-12 Yakima River, Cle Elum, Wash. (NPS) 38-28 Yakima River, Vest Richland, Wash. (NPS) (NPW) 38-28, 39-17 Yakima River, Yakima, Wash. (NPS) 38-28 Yalobusha River, Miss. (LMR) 12-21 Yaquina Bay and Harbor, Oreg. (NPP) 37-12, 37-30, 37-40 Yaquina Bay and Harbor Small Boat Basin, Oreg. (NPP) 37-45 Yaquina River, Oreg. (NPP) 37-45 Yatesville Lake, Ky. (ORH) 25-10, 25-15, 25-18 Yazoo River, Miss. (LMK) 12-5, 12-14, 12-17 Yazoo River Backwater Area (MR+T) 42-51 Yazoo River Basin, Miss. (MR+T) 42-7, 42-16, 42-28, 42-46, 42-51 Yazoo River Basin Project Levees (MR+T) 42-46, 42-49 Yellow Jacket Creek, Hogansville, Ga. (SAM) 10-43 Yellowstone River, Bank Protection, Billings, Mont. (MRO) 21-19 Yellowstone River, Greycliff Bridge, Mont. (MRO) 21-19 Yellowstone River, near Miles City, Mont., Water Intake and Sewage Lagoon (MRO) 21-19 Yellowstone River, Reedpoint Bridge, Mont. (MRO) 21-19 I-60 INDEX Yellowstone River, Springdale Bridge, Mont. (MRO) 21-19 Yellowstone River, Voges Bridge, near Big Timber, Mont. (MRO) 21-19 Yellowstone River, V. Glendive, Mont. (MRO) 21-17, 21-19 Yellowstone River, Water Plant, Livingston, Mont. (MRO) 21-19 Yellowstone River, Yellowstone Co. Bridge, near Billings, Mont. (MRO) 21-19 Yonkers, N.Y. (NAN) 2-32 York, Pa. (NAB) 4-20, 4-27, 4-33 York Harbor, Maine (NED) 1-39 York River, Va. (NAO) 5-9, 5-15, 5-20 York Spit Channel, Va. (NAO) 5-2, 5-13 Youghiogheny River, Pa. and Md. (ORP) 26-21 Youghiogheny River Lake, Pa. and Md. (ORP) 26-11, 26-15, 26-20 Youngs and Klaskanine River, Oreg. (NPP) 37-45 Youngs Bay and Youngs River, Oreg. (NPP) 37-45 Youngs River Dikes, Oreg. (NPP) 37-47 Youngstown, Ohio (ORP) 26-22 Z Zacate Creek Channel Improvement, Tex. (SWF) 16-21 Zanesville, Ohio (ORH) 25-21 Zintel Canyon Dam, Wash. (NPW) 39-9 Zippel Bay, Minn. (NCS) 27-27 Zippel Bay Harbor, Minn. (NCS) 27-23 Zumbro River, Minn. (NCS) 27-24, 27-28 *U. S, GOVERNMENT PRINTING OFF ICE: 1987-720-457:60127 1-61